Implications of Frequency Bias Settings on AGC Minh-Luan D. Ngo & Roger L. King Department of Electrical & Computer Engineering Mississippi State University Rogelio Luck Department of Mechanical Engineering Mississippi State University Abstract Reliability Council (NERC) has established two criteria for the performance of ACE. These criteria are as follow: This paper describes the effects the frequency bias setting, B , har on the operation of Automatic Generation Control systems that are operating with tie-linefrequency bias control. Since B can not be continuously measured, it must be estimated annually. The closer the frequency bias setting matches the actual control area's frequency response characteristic, the better AGC will pe,erform. In order to minimize the estimating error of the frequency bias setting, a better understanding of it is necessary. 1) A1 Criterion - Zero Crossing : "The A1 Criterion requires that a control's area's ACE return to zero within ten minutes of previously reaching zero." [41 2) A2 Criterion - Ld Compliance : "The A2 Criterion requires that the average ACE for each of the 6 ten-minute periods during the hour be within specific limit, referred to as L,."[4] Ld is calculated as follows: L , = (0.025)AL + 5MW Keywords: Frequency Bias,Automatic Generation Control, Area Control Error where AL can be one of following: [4] 1) The largest hourly load change (increasing or decreasing) in the control's area Net Energy for Load during peak demand. 2) The average of any ten hourly load changes (increasing or decreasing) in the control's area Net Energy for Load during a year. The strategy of ACE provides a steady-state target according to which a control area meets its own load during normal conditions in the interconnection, contributes to fquency regulation, and provides assistance to extemal areas when necessary. A more detailed discussion of AGC can be seen in [l]. If there is an overgeneration in any mea,ACE will be positive in that area, and the action to be taken will be to reduce area generation. On the other hand, if there is under-generation in any area, ACE will be negative in that area, and the action to be taken will be to increase area generation. ACE is determined as follow: 1. Introduction In actual power system operation, many meas are connected to each other allowing the interchange of energy for various reasons. However, each is responsible to meet its native load with its own resources. In order for each area to meets its long-term dynamic load, supplemental control is applied to the speed governon of most generators. The purpose of this control is to attempt to match the moment-tu-moment load changes in the system. The supplemental control is known as Automatic Generation Control or AGC. AGC has the following primary objectives: [l] a) To maintain scheduled tie line interchanges between areas; b) To maintain scheduled system frequency error to zero; c) To match generation to lod; d) To economically dispatch area generations to minimize operation costs. ACB . (2'' - T,) - 10 B (Fa - F,) where 2. Area Control Error (ACE) The state of the art in AGC is represented by tieline frequency bias control.[6] It is defined for a control area as a mode of operation under AGC in which the Area Control Error or ACE, represents the mismatch between area load and generation. The North American Electric a3 0094-2898/95$04.00 0 1995 IEEE (1) T, - actual net interchange T, - scheduled net interchange F. - actual frequency F, - scheduled frequency. B - area frequency bias constant (MWD.1 Hz numerically negative) indicated by the additional power being exported out of Area 1 and by the fact that the frequency is higher than the scheduled frequency. The result is that Area 1 needs to reduce generation and Area 2 needs to wait to see if the problem is corrected. As mention earlier B has to be estimated annually because it can not be continuously measured. In equation (2). the term lOB(f,-f,) is known as the area frequency response. Without this term a control area will not be able to distinguish between an internal or external disturbance. For example, assume there are two control areas (1 and 2) connected to each other via a tie-line as shown in Figure 1. Also, assume both have the same the same generation and l o d characteristics. EXAMPLE 2 The same data in example 1 are assumed, except fa = 59.99 Hz. Solution ACE1 = [110 - 1001 - lo(-100)(59.99 - 60) = 0 MW ACE, = [-110 - (-100) - lo(-100)(59.99 - 60) = -20 MW Figure 1 lines. ACE, indicates that there is nothing wrong within Area 1 and no actions is needed, However, ACE, indicates that there is a disturbance in its area and action is needed. The problem identified in this example is that Area 2 is under generating. This is indicated by the additionalpower being imported from Area 1 and by the fact that the frequency is lower than the scheduled frequency. The result is that Area 2 needs to increase generation and Area Two control areas interconnected with tie- Area 1 has agreed to sell 100 MW of power to Area 2. Now assume Area 2 experiences a sudden load increase of 30 MW. Since both areas have the same generation characteristics, 15 MW of the 30 M W l o d increase in Area 2 will be shared by Area 1. Area 1 will now have an additional 15 M W exported via the tie lines. Since Area 2 received an extra 15 MW from the tie lines, it will only have to generate an additional 15 MW to satisfy the 30 MW load increase. However, Area 1 is only supposed to supply 100 MW, not 115 MW, to Area 2. Now Areal has had to increase its generation by 15 MW [3]. Now, with the area frequency response added to the equation (2), the control areas will be able to determine if a disturbance is intemal or external. The following two examples will demonstrate the calculation of ACE with tieline frequency bias control. 1 needs to wait to see if the problem is corrected. The last two examples have shown the importance of the area frequency response term in AGC. A detail discussion of Tie-Line Frequency Bias and the area frequency response is the objective of the remainder of this Paper. 2.1 Tie-Line Frequency Bias When frequency deviates from the scheduled frequency due to a load imbalance, all of the systems within an interconnection area respond to stabilize the frequency. The process of the systems responding to the load imbalance is known as System Response to Frequency Deviation Characteristic, SRC. In order for a unit to be responsive to frequency deviation, the governor response’s reserve must be available in both the raise and lower direction. The deviated frequency will be stabilized, but it will not be returned to the scheduled value. The control area will monitor the frequency deviation and will take any necessary actions to c o m t it, The control area will send out control actions to adjust generation to return the frequency back to the scheduled frequency. The control area’s AGC uses SRC to determine whether the frequency deviation is external ar internal to the area. If the deviation is internal, the control m ’ s AGC should take action to correct deviation. If the deviation is external, then no AGC actions should take place. However, the control area should continue to respond to the frequency deviation until the external system corrects its imbalance and returns the frequency to its scheduled value. Since the control area’s EXAMPLE 1 The same two areas previously discussed are used. The B term is assumed to be 100 MW/O.lHz. Area 1 has agreed to sell 100 MW to Area 2 (Ts = 100). However, the actual net interchange is 110 MW (”a = 110), and first, let’s assume the actual frequency is 60.01 Hz (fa = 60.01). Where is the disturbance? Solution ACE, = [110 - loo)] - 10(-100)(60.01 - 60) = 20 MW ACE, = [-110 - (-100)l -10(-100)(60.01 - 60) = 0 MW ACE, indicates that there is a problem in its area and actions need to be taken to correct the problem. However, ACE, indicates that its area has no disturbance and no actions need to be taken. The problem identified in this example is that Area 1 is over generating. This is 84 the system regulation directly.[5] It helps the generation in regulating the load changes. A load change will produce a frequency change with a magnitude that depends on the droop characteristics of the govemor and the frequency characteristics of the system load. SRC is continuously changing and cannot be measured, it must be estimated. The estimated value of SRC is known as the Tie-Line Frequency Bias, B.[2] The closer B matches with SRC, the better AGC will be able to distinguish intemal and external disturbances and reduce the number of unnecessary control actions. NERC guidelines require that the annual estimate of B be based on the average of the area’s SRC, fl, as observed for past disturbances during peak hours. Guidelines also require that the monthly average of IBI should not be less then 1% of the control area’s annual estimated peak loadJ41 3. Actual vs Estimated ACE The actual errof between generation and load of an area is the area’s actual ACE.[7] The estimated ACE is calculated using the estimated values of the tie line interchange, fiequency deviations from the nominal, and the estimated frequency bias factor. It is this estimated ACE that is used by AGC. When the fkequency bias of the estimated ACE matches with the actual fkequency bias of the area, the estimated ACE and the actual ACE are identical.[3] Since the objective of AGC is to regulate generation, its input should be the actual ACE. It can be argued that integral action in AGC results in both actual and estimated ACE being averaged to zero over time [7], but the transient response of AGC can be significantly degraded by errors in the frequency bias factor. For example, variations in the estimated ACE can be much larger than variations in the actual ACE, if the frequency bias term in the estimated ACE is too large. Also, an estimated ACE based on a constant frequency bias factor is non-linearly related to the required change in generation because the actual frequency bias facta is non-linearly related to the operating state of the area, i.e., frequency and load. Using an estimated ACE based on a constant frequency bias setting as the system error in AGC introduces an undesirable nonlinearity into the control system. In practice, the load frequency controller (AGC) depends on the estimated ACE and, uses the system frequency, the net tie line data, and the estimated value of frequency bias as inputs. However, an AGC controller based on the actual ACE would provide a better control over the generatioddemand ratio and, therefore, have a better control over the ACE obtained from equation (2). 2.2 System Natural Response Coefficient (p) The value of area p can not be obtained accurately. Area p is sensitive to the status of generation and govemor response of on-line units, as well as the frequency response of the total area load, all of which are constantly varying. The number of unit governors coming out of dead-band vary according to the upset size of the predisturbance frequency. The coefficient, p, is negative and is given in MWIO.1 Hz. A mathematical equation for fl can be seen as follow: [3] 1 p . - + D R where (3) 1/R - the generator regulation or droop D - the load damping characteristic. R is the steady state characteristic of frequency and generated power. All of the system individual unit droop characteristics are set to be about equal to minimize turbine govemor oscillation. With the same droop, each unit will share the system load change. This load change is proportional to the individual unit’s M W rating. The droops ideally range from 3 to 5 percent. However, according to a recent EPRI survey, the true measured droop characteristic of the generators actually range from 6.9 to 12.2 percent.[8] These values are much higher than the predicted range of 3 to 5 percent. D is the relationship between the change in actual load due to a change in frequency. It is expressed as percent change in the fiial connected load divided by the percent change in frequency. The load damping characteristic is an important factor on system stability. D represents the self-regulating characteristic of load. It means that when system load increases the frequency decreases and the total load will respond to this effect by a small decrease, causing the f d load to be less than that at rated frequency. The load damping characteristic affects 4. Actual Frequency Response of a Utility Using actual frequency data for the month of July, 1994 provided by Southem Company Services for the Southern Electric System (SES), the estimated frequency responses, 10B(f, - f,), were calculated. For 1994,SES used a constant B term of 321 MW/O.lHz. The calculated values are the average frequency responses over a thirty days period. The calculated values of the frequency response can be seen in Table 1. Table 1 shows that the mean value of the kequency response term of the ACE equation actually used 85 on the SES is less than 0.5 MW. This is as expected since integral action of the controller should work to zefo out the error. Note that 95% of the excursions for the month were within 57.6 M W (i.e., two standard deviations). Note that if the B setting was 10 percent too high (and NERC prefers utilities to err towards supplying additional frequency response), then the mean would worsen by 10 percent. Also, note that two standard deviations in this case would be 63.3 MW. Conversely, if the B setting was 10 percent less than what is presently used we would see an improvement in the inadvertent energy interchange due to the system frequency contribution and an improvement in the magnitude of the excursions. H 1 1 I 1 Frequency Response Term of ACE I SCS'sB 1 +lo% B I -10% B 1 I1 1 Standard Deviation -0.4909 -0.5399 -0.4418 28.7729 31.6509 25.8%1 characteristic of the generator. Research is presently ongoing to develop an on-line method of estimating a utilities tie-line frequency bias term. 6. Acknowledgements The research reported in this paper has been supported by grant number ECS-92-16549from the National Science Foundation and contract number RI' 8030-12 from the Electric Power Research Institute. The data for the ACE calculations was supplied by Southern Company Services. 7. References N.Jaleeli, D.N. Ewart, and L.H. Fink, "Undemtandmg Automatic Generation Contro1,"IEEE Transactions on Power System, Vol. 7, No. 3 August 1992. pp. 11061122. T. Kennedy, S. M.Hoyt, C. F. Abell, "Variable NonLmear Tie-Line Frequency Bias for Interconnected System Control," IEEE Transactions on Power System, Vol. 3, No. 3, August 1988, pp. 1244-1253. A.J. Wood and B.F. Wollenberg, Power Generation, Operation. & Control, John Wiley & Sons, 1984. Table 1: Calculated Frequency Response with Different B's for the SES July 1994 data. North American Electric Reliability Council Operating 5. Conclusions "Determination of Natural Frequency Response of a Power System for Automatic Generation Control." A Thesis of Jesus Jativa, University of Texas at Arlington. The tie-line firequency bias of an interconnected power system can be obtained through estimation of the natural response of the system. The mismatch between area's natural frequency response characteristic and the tieline frequency bias setting used in AGC is a major cause of inadvertent energy interchange, system time deviation, fighting among system control areas, and unnecessary control actions. Therefore a better way for approximating the B coefficient is needed to reduce the mismatch between B and p. Also, with the introduction of Independent Power Producers (IPP) selling power to utilities, existing utilities have to be more concerned with the mismatch between B and p. As more IPPs appear in the generation mix, utilities inadvertently using power hthem may fmd that paying power back to the grid will no longer be an acceptable operational technique. The IPPs may very likely ask the utility to pay back them back with money instead of power, since the IPP does not have any native load. A better approximation of the B coefficient is possible, if the D coefficient from the system natural response can be approximated through load modeling. This is possible because D is not constant like the droop Guides, Guide I. System Control, April 1. 1992. "IEEE Standard Definitions of Terms For Automatic Generation Control on Electric Power System." IEEE Transactions on Power apparatus and System, Vol. PAS-89. pp. 1358-1362. July/Aug. 1970. S . Rahman and 0. Hazim, "A Generalized KnowledgeBased Short-Term Load-ForecastingTechnique," IEEE Transactions on Power Systems, Vol. 8, N0.2, May 1993. "Impacts of Govemor Response Changes on the Security of North American Interconnections," EPRI Final Report October 1992.