ESTIMATION OF EARTHWORKS IN CONSTRUCTIONS Prepared by Aldrin Justado SOIL CONDITIONS • There are three principal conditions or states in which earthmoving material may exist: 1) Bank 2) Loose 3) Compacted SOIL CONDITIONS Figure 1.0 Typical Soil Volume Change during Earthmoving SWELLING A soil increases in volume when it is excavated because the soil grains are loosened during excavation and air fills the void spaces created. SWELLING Find the swell of a soil that weighs 1661 kg/m3 in its natural state and 1186 kg/m3 after excavation. SWELLING 40% SHRINKAGE When a soil is compacted, some of the air is forced out of the soil's void spaces. SHRINKAGE Find the shrinkage of a soil that weighs 1661 kg/m3 in its natural state and 2077 kg/m3 after compaction. EARTHWORKS-CUT AND FILL ESTIMATIONS BY SECTION METHOD STA. 0+000 5.25 5.4 6.2 7.5 6.7 STA. 0+100 5.2 5.46 7 7.9 6.78 STA. 0+200 4.8 4.9 4 3.6 2.8 STA. 0+300 5.2 5.46 7 7.9 6.78 Assign the depth at each corner or segment intersection a weight according to its location (number of segment lines intersecting at the point). • interior points (intersection of four segments) are assigned a weight of FOUR • exterior points at the intersection of two segments are assigned a weight of TWO • corner points are assigned a weight of ONE. The figure below shows the topographic map of a certain lot. The soil that weighs 17386.38 BCM after excavation and 21584.65 BCM after compaction. An excavator has a bucket capacity of 30CM and an output of 1220 m3/day. Its operation consist of the cycle: a) excavation time (45 s); b) travel time (4min); c) dumping time (30s). Assume an overall efficiency factor for the excavator = 90% and 8-hours working days. Determine the following: a) Bank Cubic Meter (BCM) b) Swell Percentage (%) c) Loose Cubic Meter (LCM) d) Shrinkage Percentage (%) e) Compacted Cubic Meter (CCM) f) No. of days to complete the job. g) No. of excavator required. STA. 0+000 5.25 5.4 6.2 7.5 6.7 STA. 0+100 5.2 5.46 7 7.9 6.78 STA. 0+200 4.8 4.9 4 3.6 2.8 STA. 0+300 5.2 5.46 7 7.9 6.78 ANSWERS AND SOLUTIONS The figure below shows the topographic map of a certain lot. The soil that weighs 17386.38 BCM after excavation and 21584.65 BCM after compaction. An excavator has a bucket capacity of 30CM and an output of 1220 m3/day. Its operation consist of the cycle: a) excavation time (45 s); b) travel time (4min); c) dumping time (30s). Assume an overall efficiency factor for the excavator = 90% and 8-hours working days. Determine the following: a) Bank Cubic Meter (BCM) = 19368.72 cu. meter b) Swell Percentage (%) = 11.4 % Factor = 1.1140 c) Loose Cubic Meter (LCM) = 21576.75408 cu. meter d) Shrinkage Percentage (%) = 10.27 % Factor = 1.1027 e) Compacted Cubic Meter (CCM) = 21357.88754 cu. meter f) No. of days to complete the job. = 9 days g) No. of excavator required. = 2 Nr