Uploaded by vandhyathevan

Basic Engineering Design Guide R 0

advertisement
El Palito Refinery Expansion Project
EPsCm - Phase
Basic Engineering Design Guide
Doc. No :
EB020401-G00-FP14500P0001
TOYO Doc. No : ED-U00-PRS-INF-000-0002
Authorized
-/0
Feb-08-2013
S.Io
F.Kashani
H.Matsumoto
H.Semizu
For Consortium Review
Rev
Issue Date
Prepared
Checked
Approved
Authorized
Description
FEED Doc. No. : 00-PMGM-BD-0001
FEED Latest Rev : E/9
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 2 of 93
Revision List
-----------------------------------------------------------------------------------------------------------------------Rev. No.
Description
------------------------------------------------------------------------------------------------------------------------/0
For Consortium Review
- Revised parts from FEED stage are marked as 0
- Section 10, 11 and 12 have been re-arranged (substances are same as
previous version)
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 3 of 93
CONTENSTS
1.
INTRODUCTION ............................................................................................................................ 8
2.
GENERAL PROJECT SCOPE....................................................................................................... 9
3.
2.1.
MAIN PROCESS UNITS SCOPE ............................................................................................ 9
2.2.
PROJECT CONFIGURATION SCHEME ............................................................................... 12
ENGINEERING EXECUTION PROCEDURES ............................................................................. 13
3.1.
PROJECT UNITS IDENTIFICATION ..................................................................................... 13
3.2.
DRAWINGS AND DOCUMENTS PREPARATION ................................................................ 15
3.3.
DOCUMENTS & DRAWINGS ISSUING AND REVISION...................................................... 15
3.4.
TECHNICAL DOCUMENTS IDENTIFICATION AND CODIFICATION .................................. 15
3.5.
EQUIPMENT IDENTIFICATION AND NUMERATION ........................................................... 15
3.5.1.
Mechanical Equipment ................................................................................................. 15
3.5.2.
Electrical Equipment ..................................................................................................... 16
3.6.
NEW LINES NUMERATION AND IDENTIFICATION SYSTEM ............................................. 17
3.7.
STANDARD DRAWINGS AND SPECIFICATIONS FOR REVAMPING ................................ 18
3.7.1.
Revamp philosophy for P&IDs (see attached example) ............................................. 18
3.7.2.
Revamp symbology for equipment .............................................................................. 18
3.7.3.
Revamp lines numbering system ................................................................................. 19
3.7.4.
PID revamp symbology for existing PID ...................................................................... 20
3.7.5.
Existing PID for identification of dismantling and modifications area ...................... 21
3.7.6.
New PID for description of new or modified items and tie-ins location .................... 22
3.8.
STANDARDS FOR UNITS INTEGRATION LINES ................................................................ 23
3.9.
INSTRUMENT NUMERATION .............................................................................................. 24
3.9.1.
Symbols and Instruments Identification...................................................................... 24
3.9.2.
Junction Boxes Identification ...................................................................................... 24
3.9.3.
Instrument Wiring Identification................................................................................... 24
4.
REGULATIONS, INDUSTRY CODES AND STANDARDS .......................................................... 24
5.
GEOGRAPHIC AND METEOROLOGICAL DATA....................................................................... 25
6.
UNITS OF MEASURE .................................................................................................................. 25
7.
UTILITIES AND ELECTRICAL POWER INFORMATION ............................................................ 26
8.
SAFETY AND ENVIRONMENTAL REQUIREMENTS ................................................................. 26
8.1.
SIS (SAFETY INSTRUMENTED SYSTEMS) RELATED TO CHEMISTRY ........................... 26
8.2.
SIS NOT RELATED TO CHEMISTRY ................................................................................... 26
8.3.
FAST DEPRESSURIZATION ................................................................................................ 26
8.4.
PUMP SHUTDOWN BY LOW LEVEL IN UPSTREAM VESSEL ........................................... 27
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 4 of 93
8.5.
MINIMUM FLOW LINE BYPASS ON CENTRIFUGAL PUMPS WITH FLOW CONTROL ..... 27
8.6.
AUTOMATIC ISOLATION VALVES BETWEEN PROCESS VESSEL AND PUMPS ............ 28
8.7.
DRIVER FOR CRITICAL SERVICE PUMP............................................................................ 28
8.8.
HIGH LEVEL IN FEED DRUM, COMPRESSOR KO DRUM, SEPARATOR DRUM AT
REACTION SECTION ..................................................................................................................... 28
8.9.
COMPRESSOR ISOLATION CONSIDERRATIONS ............................................................. 29
8.10.
BACK FLOW OVERPRESSURE CONTROL / MITIGATION ............................................. 29
8.11.
FIRED HEATER ISOLATION CONSIDERATIONS ............................................................ 29
8.12.
PUMP SEALS .................................................................................................................... 30
8.13.
CONSTRAINTS DUE TO BENZENE HANDLING .............................................................. 30
8.14.
CONSTRAINT DUE TO STREAMS CONTAINING H2S .................................................... 31
8.15.
BATTERY LIMIT ISOLATION ............................................................................................ 31
9.
DESIGN CONSIDERATIONS ...................................................................................................... 32
9.1.
DESIGN PRESSURE AND TEMPERATURE ........................................................................ 32
9.1.1.
Design pressure for individual equipment items ........................................................ 32
9.1.2.
Shell and tube heat exchangers ................................................................................... 33
9.1.3.
Design pressure for complete systems ....................................................................... 34
9.1.4.
Fractionation tower and auxiliaries ............................................................................. 34
9.1.5.
Exchangers, vessels and other equipment on the pump discharge ......................... 35
9.1.6.
Process system similar to that of a reactor-recycle gas-loop.................................... 35
9.2.
DESIGN TEMPERATURE ..................................................................................................... 35
9.3.
EQUIPMENT STEAM PURGING ........................................................................................... 36
9.4.
CYCLIC OPERATING CONDITIONS .................................................................................... 36
9.5.
EQUIPMENT FLUSHING OR WASHING .............................................................................. 36
9.6.
TRANSIENT OPERATING CONDITIONS ............................................................................. 37
9.7.
CORROSION ALLOWANCE ................................................................................................. 37
9.7.1.
Equipment Design Life ................................................................................................. 37
9.7.2.
Pressure Retaining Equipment .................................................................................... 37
9.7.3.
Internals ......................................................................................................................... 38
9.8.
10.
P&ID’S PREPARATION AND PRESENTATION ................................................................... 39
9.8.1.
Equipment item number, service name and short specification ............................... 39
9.8.2.
Representation of Equipment....................................................................................... 41
9.8.3.
Instrumentation ............................................................................................................. 44
9.8.4.
P&ID of Package Units by Vendor ................................................................................ 44
EQUIPMENT DESIGN BASIS................................................................................................... 45
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
10.1.
VESSELS ........................................................................................................................... 45
10.1.1.
Inside Diameter .......................................................................................................... 45
10.1.2.
Required Length ........................................................................................................ 46
10.1.3.
Nozzle and Flange...................................................................................................... 49
10.1.4.
Miscellaneous ............................................................................................................ 51
10.2.
TRAYS AND PACKING ..................................................................................................... 52
10.2.1.
Selection of Tray or Packing ..................................................................................... 52
10.2.2.
Hydraulics .................................................................................................................. 52
10.2.3.
Material ....................................................................................................................... 52
10.3.
SHELL AND TUBE HEAT EXCHANGERS ........................................................................ 53
10.3.1.
Heat Exchanger Type ................................................................................................ 53
10.3.2.
Process Specification................................................................................................ 53
10.3.3.
Reboiler ...................................................................................................................... 53
10.4.
AIR FIN COOLER .............................................................................................................. 54
10.4.1.
Process Specification................................................................................................ 54
10.4.2.
Selection of Water Cooler or Air Cooler ................................................................... 55
10.4.3.
Miscellaneous ............................................................................................................ 55
10.5.
HEATERS .......................................................................................................................... 56
10.5.1.
General ....................................................................................................................... 56
10.5.2.
Burners ....................................................................................................................... 57
10.5.3.
Miscellaneous ............................................................................................................ 57
10.6.
PUMPS .............................................................................................................................. 58
10.6.1.
Process Specification................................................................................................ 58
10.6.2.
Pump Type ................................................................................................................. 58
10.6.3.
Driver .......................................................................................................................... 58
10.6.4.
Spare .......................................................................................................................... 59
10.6.5.
Minimum Flow ............................................................................................................ 59
10.6.6.
Miscellaneous ............................................................................................................ 60
10.7.
11.
Page 5 of 93
COMPRESSORS ............................................................................................................... 61
10.7.1.
Process Specification................................................................................................ 61
10.7.2.
Type ............................................................................................................................ 61
10.7.3.
Driver .......................................................................................................................... 62
10.7.4.
Spare .......................................................................................................................... 62
PIPING ...................................................................................................................................... 63
11.1.
PIPING LAYOUTS ............................................................................................................. 63
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
11.1.1.
Page 6 of 93
General ....................................................................................................................... 63
11.2.
DESIGN PRESSURE AND TEMPERATURES .................................................................. 65
11.3.
DESIGN DETAILS ............................................................................................................. 65
11.3.1.
Line and Connection Sizes ....................................................................................... 65
11.3.2.
Material Specification Changes ................................................................................ 66
11.3.3.
Flanges ....................................................................................................................... 66
11.3.4.
Valves ......................................................................................................................... 67
11.3.5.
Blinds.......................................................................................................................... 69
11.3.6.
Sampling System ....................................................................................................... 69
11.3.7.
Flame Arrestors ......................................................................................................... 69
11.3.8.
Silencers..................................................................................................................... 69
11.3.9.
Battery Limit ............................................................................................................... 70
11.3.10.
Block Valves around Equipment and Instrument .................................................... 71
11.3.11.
Vents and Drains ....................................................................................................... 74
11.3.12.
Purge Connection to Process Line........................................................................... 81
11.3.13.
Warming-up and pressure equalizing bypass of steam lines ................................. 82
11.3.14.
Valve Size for Suction and Discharge Lines of Pumps ........................................... 82
11.3.15.
Steam inlet line to steam turbine .............................................................................. 82
11.3.16.
Pressure gauge for Pumps ....................................................................................... 82
11.3.17.
Utility Stations............................................................................................................ 82
11.3.18.
Sampling Connections .............................................................................................. 82
11.3.19.
Insulation and Steam Tracing ................................................................................... 83
11.3.20.
Double Block Valve for On-stream Maintenance ..................................................... 83
11.4.
LINE SIZING CRITERIA..................................................................................................... 83
11.5.
PIPING SERVICE IDENTIFICATION ................................................................................. 84
12.
INSTRUMENTATION AND CONTROL ..................................................................................... 85
12.1.
FLOW INSTRUMENTS ...................................................................................................... 86
12.2.
LEVEL INSTRUMENTS ..................................................................................................... 87
12.3.
PRESSURE INSTRUMENTS ............................................................................................. 88
12.4.
TEMPERATURE INSTRUMENTS ...................................................................................... 88
12.5.
CONTROL VALVES........................................................................................................... 89
12.6.
PRESSURE RELIEF VALVES ........................................................................................... 90
12.7.
ALARMS AND SHUTDOWN DEVICES ............................................................................. 90
12.8.
INSTRUMENT AIR SUPPLY .............................................................................................. 91
12.9.
INSTRUMENT ELECTRICAL POWER SUPPLY ............................................................... 91
El Palito Refinery Expansion Project
Phase II
13.
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 7 of 93
CIVIL ENGINEERING DESIGN................................................................................................. 92
13.1.
MEASUREMENT UNIT AND LANGUAGE ........................................................................ 92
13.2.
SITE PREPARATION AND EARTHWORK........................................................................ 92
13.3.
ROAD DESIGN AND CONSTRUCTION ............................................................................ 92
13.4.
UNDERGROUND PIPING AND SURFACE DRAINAGE ................................................... 92
13.5.
HVAC, PLUMBING AND SANITARY SERVICES .............................................................. 93
13.6.
DESIGN AND CONSTRUCTION BASIS FOR STRUCTURES .......................................... 93
13.7.
FIREPROOFING ................................................................................................................ 93
13.8.
DIKE CAPACITY REQUIREMENT..................................................................................... 93
El Palito Refinery Expansion Project
Phase II
1.
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 8 of 93
INTRODUCTION
The Basic Engineering Design Guide is intended to provide Consortium with the technical
information required to complete the “El Proyecto de Expansión Refinería El Palito (RELP)”
Engineering Design Specifications, on a once-through basis, with minimum revisions and time
delay.
Consortium and PDVSA agreed to use FWI standards to prepare the Job Specification and
Standard for the RELP expansion project. PDVSA and Consortium also agreed that Job Spec and
Standards should be customized in order to comply with the Venezuelan law and regulations.
During review of the job Specification and Standard for the RELP Expansion Project, if it is needed
to add some PDVSA criteria as specific refinery requirements for obtaining a better design, the
Consortium is willing to integrate these comments if after a discussion between PDVSA and
Consortium is considered that the comments are not in contradiction with FWI standards.
For the above mentioned reasons, PDVSA BEDG handed over to Consortium during the 1st Task
Force Meeting held in Milan in December 2007 have been revised incorporating the design criteria
agreed with PDVSA during the Engineering KOM, deleting the sections not related to the Process
Design Basic and FEED phase (e.g. reference to Licensor documentation) and modifying the
sections in contrast with FWI standards that shall be considered as a binding document for the
development of the Project.
The design consideration reported in this document shall be then read as supplementary
information not included in the Job Specification/Standards issued for the RELP Project.
El Palito Refinery Expansion Project
Phase II
2.
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 9 of 93
GENERAL PROJECT SCOPE
The project “Proyecto de Expansión Refinería El Palito (RELP)” is intended to adapt El Palito
Refinery to new environmental regulations and for processing new heavy crude blend, by means of
revamping existing units and installing new process plants associated with auxiliary units, utilities
and offsites facilities.
2.1. MAIN PROCESS UNITS SCOPE
El Palito Refinery Expansion Project is based on the installation and revamp of the following main
process units:
• New Atmospheric and Vacuum Distillation Units:
The modification in the current Refinery’s crude blend feedstock density due to the change in its
composition through adding more heavy/extra heavy crudes requires a new grass roots
atmospheric and vacuum distillation units. The final Blend (22 °API) is known as Leona Crude
which is a mixture between Mesa 30 and Merey 16. The maximum overall atmospheric distillation
capacity shall be 140 kBPD.
• Revamp of Existing Atmospheric and Vacuum Distillation Units:
Considering that the feedstock to RELP will be changed in a short time period, it is required to
evaluate the feasibility to use the equipment in existing ADU/VDU to process 140 kBPD of a mixed
crude of 28 oAPI case (blend of 4 crudes namely Zuata Sweet; Mesa 30; Merey 16 and Residual
El Chaure)(Out of Consortium EPsCm Work Scope).
• Naphtha Complex:
Involves the installation of a new Naphtha Hydrotreating Unit to reduce the naphtha pool sulfur
and nitrogen content from 50 wt ppm and 9 wt ppm to a maximum of 0.5 wt ppm for each,
respectively. Also, a new Continuous Catalytic Reforming Unit to reformate the naphthas delivered
by the hydrotreating unit, improving the RON number to 104.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 10 of 93
• VGO Hydrotreating Unit:
The unit has been designed to process a blend of straight run VGO of 58000 BPSD (18.0 °API)
from both New and Existing ADU/VDU with a sulfur content of 2.25 wt% and 2,634 wt ppm of
nitrogen. It is expected a DVGO average production of 54,552(SOR)/50,976(EOR) BPSD of
0
24.68(SOR)/24.17(EOR) °API with a sulfur content of less than 200 wt ppm. The unit design per
Licensor Basic Engineering Package suits to process a blend of cracked/straight run feedstock as
original configuration.
• Diesel Hydrotreating Unit:
This unit has been designed to process a blend of straight run gas oil of 45,000 BPSD
(31.86 °API) from both New and Existing ADU/VDU with a sulfur content of 0.7676 wt% and a
cetane index of 47.7 to produce an average of 46,512(SOR)/46,080(EOR) ULSD BPSD with a
cetane number up to 51.0 and a sulfur content lower than 7.0 wt ppm. The unit design per
Licensor Basic Engineering Package suits to process a blend of cracked/straight run feedstock as
original configuration.
Furthermore, to guarantee the proper functioning and reliability of these process units, El Palito
Refinery Expansion Project RELP” includes the installation of new auxiliary units and utilities units,
to supply the requirements of water, steam, air, nitrogen, gas and electricity under the conditions
required. The utility units are out of Consortium EPsCm Work Scope.
Finally new offsite facilities (flare system, intermediate storage tanks, fire protection unit, new dock,
etc.) are provided, designed and constructed according to process, auxiliary and utilities plants
requirements in order to guarantee a safety and environmental supported operation.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 11 of 93
The major process and auxiliary units and their capacities are listed below.
•
New Atmospheric Distillation Unit
140,000 BPSD
•
New Vacuum Distillation Unit
105,000 BPSD
•
Existing Atmospheric Distillation Unit
140,000 BPSD
•
Existing Vacuum Distillation Unit
87,500 BPSD
•
LPG Unit(Treating+Fractionation)
1,750 BPSD(Note-1)
•
Naphtha Hydrotreating
24,500 BPSD
•
Continuous Catalyst Reformer
24,500 BPSD
•
Reformate Splitter
19,213 BPSD
•
Kerosene Treatment Unit (KTU)
14,450BPSD(Note-2)
•
VGO Hydrotreating
58,000 BPSD
•
Diesel Hydrotreating
45,000 BPSD
•
Hydrogen Production
55 MMSCFD x 2 trains
•
Hydrogen Recovery
38 MMSCFD
•
Sour Water Stripping
355 klb/hr x 3 trains(Note-3)
•
Amine Regeneration
606 klb/hr x 2 trains(Note-3)
•
Sulfur Recovery & TGT
125 TPD x 3 x50% SRU trains
+ 250TPD x 2 x 100%TGTU trains
+ 250TPD x 2 x 100% Incinerators
+ 250TPD x 1 x 100% Degassing Section
Notes:
1.
LPG processing scheme is on HOLD. Final configuration to be confirmed by PDVSA.
2.
Indicated figure is operating capacity. Design capacity to be defined by PDVSA.
3.
Indicated figure is total operating capacity, Design Capacity of each train to be finalized with
PDVSA approval.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
2.2. PROJECT CONFIGURATION SCHEME
Page 12 of 93
El Palito Refinery Expansion Project
Phase II
3.
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 13 of 93
ENGINEERING EXECUTION PROCEDURES
3.1. PROJECT UNITS IDENTIFICATION
The Units involved at the project scope “Proyecto de Expansión Refinería El Palito (RELP)” are
classified according to the plant code assigned by the Refinery, and are numbered as follows:
The codification mentioned below is actually used by PDVSA and involves 4 digits, that do not
load the computer systems and allow the insertion of letters for codifications the different
equipment of each unit; this also help the unit understanding.
Table 3.1: El Palito Refinery Units Codes
Process Units
Atmospheric Distillation
Vacuum Distillation
Revamp of Existing Atmospheric Distillation
(Out of Consortium EPsCm Work Scope)
Revamp of existing Vacuum Distillation
(Out of Consortium EPsCm Work Scope)
CCR Reaction
CCR Catalyst Regeneration
Naphtha Hydrotreating
Reformate Splitter
(Out of Consortium EPsCm Work Scope)
Kerosene Treatment
(Out of Consortium EPsCm Work Scope)
VGO Hydrotreating
Diesel Hydrotreating
LPG Unit (Treating + Fractionation)
Plant Code
1100
1200
ID code
11
12
100
10
6000
60
2100
2200
2600
21
22
26
2700
27
1500
15
2800
2900
5100
28
29
51
Auxiliary Units
Hydrogen Production
Hydrogen Recovery
Amine Regeneration
Sour Water Stripping
Sulphur Recovery & Tail GasTreating
Plant Code
3500
3600
3200
3300
3400
ID code
35
36
32
33
34
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Utilities
Raw Water Treatment / Desalination
(Out of Consortium EPsCm Work Scope)
BFW / Steam / Condensate
(Out of Consortium EPsCm Work Scope)
Cooling Water
(Out of Consortium EPsCm Work Scope)
Plant / Instrument Air
(Out of Consortium EPsCm Work Scope)
Page 14 of 93
Plant Code
ID code
5300
53
5400
54
5500
55
5600
56
5700
57
5800
58
5900
59
7250
72
Power Distribution
1900
19
Power Generation
(Out of Consortium EPsCm Work Scope)
7800
78
Plant Code
9000
9200
ID code
90
92
XXXX
XX
9300
9300
9400
9500
9600
9700
1800
93
93
94
95
96
97
18
XXXX
AH
XXXX
A9
9800
9900
98
99
Fuel Gas
Nitrogen
(Out of Consortium EPsCm Work Scope)
New Waste Water Treatment
(Out of Consortium EPsCm Work Scope)
Revamp of Existing Waste Water Treatment
(Out of Consortium EPsCm Work Scope)
Off Site
Interconnecting
Flare System
LPG-Storage Capacity Increase
(Out of Consortium EPsCm Work Scope)
LPG Unit (Storage + Loading)
Product Storage
Module Offloading Jetty
Shipping Facilities (Oil)
Shipping Facilities (Storage & Tank Loading for Sulphur)
Technical Buildings
Control System
Administrative Complex
(Out of Consortium EPsCm Work Scope)
Social Club
(Out of Consortium EPsCm Work Scope)
Fire Protection
Site Preparation
0
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 15 of 93
3.2. DRAWINGS AND DOCUMENTS PREPARATION
See Job Specification “00-FMGM-SP-0007” CAD Procedure
3.3. DOCUMENTS & DRAWINGS ISSUING AND REVISION
Document will be issued for PDVSA’s review as per Coordination Procedure,
“EB-020401-G00-GGL0100P0001”
3.4. TECHNICAL DOCUMENTS IDENTIFICATION AND CODIFICATION
See Coordination Procedure “EB020401-G00-GGL0100P0001”
3.5. EQUIPMENT IDENTIFICATION AND NUMERATION
3.5.1. Mechanical Equipment
a.
Identification Codes
The mechanical equipment will be identified according to the codes usually used by El Palito
Refinery. The detail is indicated at the following table:
Table 3.2 Mechanical Equipment Identification Codes
CODE
EQUIPMENT
B
Boilers, Heaters, Burners, Dryers, Incinerators, Flares
D
Fractionating Towers, Strippers, Absorbers, Reactors, Drums, Spheres,
Pressure Vessels.
E
Heat Exchangers, Air Coolers, Condensers, Cooling Towers.
G
Pumps, Compressors, Blowers, Fan coolers, Exhaust Fans,
GT
Turbine Driver
GE
Engine Driver
GM
Motor Driver
J
Ejectors.
M
Miscellaneous Equipment, Mixers, Agitators, Coalescers, Filters, Silos,
Bins, Bag House, Rotary Valves,
N
Electrical Generation.
S
Solids Handling: Mills, Conveyors, Screeners, and Feeders.
T
Tanks, Hoppers
X
Package units.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
b.
Page 16 of 93
Numeration
i. Equipment Numeration
For the new mechanical equipment to be installed at the “Proyecto de Expansión Refinería
El Palito (RELP)” the identification used actually in the refinery will be used:
Equipment Type(Pump)
Unit Identification
Sequential Number
Similar Equipment
G-6003-A
ii. Driver Numeration
0
Driver Type
GM: Motor Driver
GE: Engine Driver
GT: Turbine Driver
Mechanical Equipment Tag Number
GM-G2104
iii. Auxiliary Equipment Numeration
Numeration of auxiliaries’ equipment shall follow the table 3.2.
iv. Tankage Numeration
For the new intermediate and final storage tanks to be installed at the “Proyecto de
Expansión Refinería El Palito (RELP)” the identification used actually in the refinery will be
used:
Tank Volume (kBLS)
Sequential Number
350X1
3.5.2. Electrical Equipment
See Job Specification 00-FELE-SP-0004
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 17 of 93
3.6. NEW LINES NUMERATION AND IDENTIFICATION SYSTEM
The process lines codification in the new areas will become according to the following structure:
For the Area Identification code See Section 3.1 Table El Palito Refinery Expansion Units Code.
Nominal Pipe Size (NPS)
Line Service Code as per symbology P&ID
Area Identification (Expansion Project Units-first two digitis)
P&ID Number referred to each unit P&ID
Sequential Number (see also 3.7)
Material Specification Number
Insulation Code (2 digits - letter)
4”-P-6101-001-AA-1F-PP
Example of Line Numeration
Table 3.3 Heat Insulation Piping Codes
Item
Designation
HC
Insulation – Heat Conservation
PP
Personnel Protection
CC
Cold Conservation
PS
Insulated for Process Stabilization
ET
Electrical Tracing
ST
Steam Tracing
NI
No Insulation
SJ
Steam Jacket
A
Acoustic Insulation
Notes:

Numbering will start at 001.

The line number changes aline number changes after control valves and main equipment.

The number is different for the lines connected to equipment in parallel.

Each type of fluid will have a separate numbering sequence.

Drains and vents without permanent flows are neither identified nor listed.

Design pressures and temperatures are shown on line list.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 18 of 93
3.7. STANDARD DRAWINGS AND SPECIFICATIONS FOR REVAMPING
3.7.1. Revamp philosophy for P&IDs (see attached example)
Existing P&IDs shall be used to identify area of dismantling (Dismantling P&IDs) and area of
modification of existing equipment or circuit, in case of small extent modifications. In order to
avoid difficulty in representation of modifications, existing P&IDs shall not be used to represent
large extent modifications.
New P&IDs shall be used to describe new equipment, large extent modifications of existing
equipment/circuits and new circuits through witness marker revamping. Existing area reused
will be shown. Consortium will spread existing P&ID into separate P&IDs only if extended
modification is required
3.7.2. Revamp symbology for equipment
New items, modification of existing equipment or circuit and reusing of existing equipment to be
modified, line, valve, instrument, shall be identified using the standard symbols presented on
PDVSA standard drawings and specifications symbols and legends.The letter R (for revamping)
will identify the drawings of existing and new P&ID’s (see attached examples).
•
For existing P&IDs (see attached standards)
•
For new P&IDs
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 19 of 93
3.7.3. Revamp lines numbering system
•
Line, instrument, valve and equipment numbers, once deleted, shall not be re-used.
•
The symbol (N): new or (M): modified put beside a tag number, is identification for new or
modified line, instrument, valve, PSV and equipment.
•
Equipment numbering must follow section 3.4 “EQUIPMENT IDENTIFICATION AND
NUMBERING”
•
This will appear as such one corresponding lists and drawings.

Example: Equipment, G-102 A (N), E-160 (M)

Example: Line:
P-1607-6"-B (N)
50°F – HC
Where:
P: Service
1607: Sequential Correlative Number
6": Line Diameter
B: Piping Service Class
50°F: Operating Temperature
HC: Insulation Code (according to Section 3.6, Table 3.3)

Example: Instruments, 10-TI-05
Where:
10: Unit Area Code
TI: Instrument Identification in accordance with the standard ISA-S5.1
05: Instrument Identification Consecutive Numerical Code
Procedures to identify the lines on P&IDs:
•
Existing lines to be maintained shall keep their original identification
•
New lines shall be identified with the symbol (N) and tie-in identification (number, description,
location).
•
Concerning modification, a point (・) will define the witness marker revamping with brief
description if necessary.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
3.7.4. PID revamp symbology for existing PID
Page 20 of 93
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
3.7.5. Existing PID for identification of dismantling and modifications area
Page 21 of 93
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
3.7.6. New PID for description of new or modified items and tie-ins location
Page 22 of 93
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 23 of 93
3.8. STANDARDS FOR UNITS INTEGRATION LINES
The followings standards must be used to prepare the documents and Drawings for the
integration.
The interconnecting Lines in the revamped units should keep the original standard design.
These lines should be shown in the interconnecting system diagram with both numbering and
identification system separated with a battery limit line.
Example:
Existing Units Diagrams
(Atmospheric Distillation Unit)
Interconnecting System Diagrams
P-1607-6"-B-50°F-HC
New Units Diagram (CCR Unit)
6"-P-XX-16-07-B-HC
To CCR Unit
From Crude Unit
CCR
Unit
Crude
Unit
B.L
B.L
Where:
P: Service
16: P&ID Number
07: Sequential Correlative Number
6": Line Diameter
B: Piping Class Specs
50°F: Operating Temperature
HC: Insulation Code (according to Section 3.6, Table 3.3)
XX: Unit Code (section 3.1)
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 24 of 93
3.9. INSTRUMENT NUMERATION
3.9.1. Symbols and Instruments Identification
All symbols and instruments identification will be represented on symbology P&ID prepared by
Consortium in accordance with the standard ISA S5.1 "Instrument Symbols and Identification"
and following the normalized codification of the El Palito Refinery.
Blocks of numbers will be reserved for Package Unit Instruments.
The basic representation of symbols for instrumentation shall be accommodated by the detail
engineering following final customer specifications and recommendations.
Instruments Identification and loop numbering for the project will be as per document
00-FINS-SP-0001
3.9.2. Junction Boxes Identification
Reference shall be made to the consortium job specification number 00-FINS-SP-0001
“INSTRUMENTATION SYMBOLS AND IDENTIFICATION.
3.9.3. Instrument Wiring Identification
Reference shall be made to the CONSORTIUM Job Specification number 00-FINS-SP-0001
“INSTRUMENTATION SYMBOLS AND IDENTIFICATION.
4.
REGULATIONS, INDUSTRY CODES AND STANDARDS
Consortium and PDVSA agreed to use Consortium standard(mainly FWI’s) for the Project, but if it is
needed to add some PDVSA criteria as specific refinery requirements for obtaining a better design it
must be discussed between Consortium and PDVSA in order not to contradict FWI standards.
Consortium will produce Job Specification and Standard customized for the Project needs based on
the latest version of regulation(as of before 31/12/2011), industry codes and standard like ASME,
API, ISA, IEC, ASTM, NACE, ANSI, NEMA, NFPA, etc.
Consortium will also include those Venezuelan requirements that are mandatory for the Venezuelan
Laws.
The list of International Standards to be applied will be recalled in detail in each Job
Specification/Standard issued for the project
El Palito Refinery Expansion Project
Phase II
5.
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 25 of 93
GEOGRAPHIC AND METEOROLOGICAL DATA
See document EB020401-G00-FP14400P0001 (Basic Engineering Design Data)
6.
UNITS OF MEASURE
The specific units to be used on this project are listed below.
Table 6.1: Measure Units
Description
Units
Description
Units
Temperature
ºF
Flow of steam
Lb/h
Pressure
Psi
Enthalpy
BTU/lb
Vacuum
mmHg
Heat duty/Power
MMBTU/h, kW
Mass
Lb
Transfer rate
Force
Lbf
ft3
Fouling resistance
BTU/ft2. ºF.h
ft2. ºF.h/BTU
Viscosity
CP
Flow of Process fluid
Equipment size
mm (*)
•
Pipe length
mm (*)
Volume
Liquid
•
- Mass flow
Lb/h
Pipe diameter
In
- Volume flow
US gpm
Vessel nozzle sizes
In
Gas
- Mass flow
Lb/h
- Volume flow
SCFM - SCFH
(*) For Engineering design and in Construction drawings, dimensional length will be shown in
millimeters, except for mechanical drawings where dimensional lengths will be shown both in
millimeters and ft-in (either of the two units to be shown in parenthesis as reference). While, in
P&IDs, the dimensional length will be shown at least in ft-in.
Additionally, the following unit of measure must be considered:
•
Unit Capacities
BPSD
•
Millions
MM
•
Miles
M
•
Thousands
k
•
Power for Rotating Equipment
HP
The normalized conditions for gas measurement are:
Standard:
760 mmHg, 60 ºF (15.5 ºC)
(Sft3/min or SCFM)
The normalized conditions for liquid specific gravity are:
Standard:
760 mmHg, 60 oF (15.5 oC)
(-)
El Palito Refinery Expansion Project
Phase II
7.
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 26 of 93
UTILITIES AND ELECTRICAL POWER INFORMATION
See document EB020401-G00-FP14400P0001 (Basic Engineering Design Data)
8.
SAFETY AND ENVIRONMENTAL REQUIREMENTS
8.1. SIS (SAFETY INSTRUMENTED SYSTEMS) RELATED TO CHEMISTRY
In case of risk due to chemical reactions, Licensor advises the SIL (Safety Integrity Level) in order
to specify the corresponding SIS.
For this unit, the SIS chemistry risk is:
•
Applicable and will be SIL: (as per ISA S84.01 or IEC 61508/61511).
•
Not applicable
If applicable, a typical SIS configuration will be represented only for concerned loop(s) and close
to the safety interlock corresponding to the loop, the following note will be indicated:
This Safety Instrumented System (SIS) has to be in accordance with safety Integrity Level (SIL x)
for this loop.
Consortium and Owner shall make sure that the type and quality of the instrumentation supplied
for the SIS, the redundancies which are possibly necessary for sensors and final elements, the
logic system, and the on-site test frequency will be compatible with the SIL level which is specified.
8.2. SIS NOT RELATED TO CHEMISTRY
The SIL and the corresponding SIS connected to equipment protection will be the responsibility of
the Consortium and Owner. Licensor will show on the P&IDs a detailed configuration of the SIS.
8.3. FAST DEPRESSURIZATION
Fire case: Normally considered for the reaction sections operating at a pressure equal or higher
than 250 psig (17.2 barg), the depressurization to normally 100 psig (6.9 barg) or 50 per cent of
the vessel design pressure shall be done manually from a push button. Above values of final
pressure shall be reached in at least in 15 minutes.
Runaway case: Considerations for the possibility of runaway in the reactor, –Consortium (based
on the information provided by Licensor will specify depressurization device and the activation in
accordance with the SIL value. The SIS corresponding to this depressurization shall be in
accordance with the SIL value already specified for the risk of runaway
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 27 of 93
8.4. PUMP SHUTDOWN BY LOW LEVEL IN UPSTREAM VESSEL
Consortium will specify pump automatic shutdown by low level in upstream vessel for:
•
Feed pumps with elevated delta P higher than or equal 1015 psi (70 bar).
•
Sealless pumps.
•
Hot pumps handling flammable liquids, where flammable liquids are defined as:
1.
Low-flash liquids (flash point below 100°F (38°C)
2.
Combustible liquids with an operating temperature range starting from 15 °F (8 °C) below
the liquid flash point temperature and above
•
Pumps handling LPG.
•
Pumps handling toxic or carcinogenic compounds where Toxic materials is defined as a liquid,
vapour or solid with a total concentration of 5% wt or greater of materials with an Health
Category rating of "2" or greater as per NFPA 704 "Standard System for the Identification of
the Hazards of Materials for Emergency Response
•
Pumps where the shutdown requirement has been specified by the Licensors.
For all other cases, Consortium will check with the pump’s vendor if automatic shutdown is
required.
8.5. MINIMUM FLOW LINE BYPASS ON CENTRIFUGAL PUMPS WITH FLOW CONTROL
Consortium will provide minimum flow line with flow control for each centrifugal pump for the
0
following cases:
- Multistage pumps with differential pressure higher than or equal to 508 psi (35 bar);
- Large pumps with driver power higher than 160 kW;
The pump data sheet will specify the process flow without provision for the minimum flow, which
will be specified by the pump’s vendor.
For medium size pumps (i.e. below the limit specified above), Consortium will provide a minimum
flow line with flow control, common for both centrifugal pumps, for the following cases:
- For process reason (turndown), the flowrate is lower than pump minimum flowrate.
0
For small size pumps (i.e. driver power below 20 kW), Consortium will provide a minimum flow line
with flow orifice, common for both centrifugal pumps, for the following cases:
- For process reason (turndown), the flowrate is lower than pump minimum flowrate.
For pumps working in parallel minimum flow bypass shall be indicated for each pump.
The pump data sheet will specify the process flow including provision for the minimum flow, to be
confirmed by the pump’s vendor.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 28 of 93
8.6. AUTOMATIC ISOLATION VALVES BETWEEN PROCESS VESSEL AND PUMPS
The followings valves closure shall result in the corresponding pump automatic shutdown. The
valves shall be located as close as possible to the vessel nozzle (preferably on the nozzle flange
itself) in order to allow an effective isolation in case of leakage in any point of the circuit
downstream the process vessel inventory.
These valves and associated actuation system shall be fire safe and shall be operated by a local
push button (in safe location) and from control room.
-
A process vessel inventory over 283 ft3 (8 m3) of light ends (LPG).
-
A process vessel inventory over 283 ft3 (8 m3) and with a product above its auto ignition
temperature or at a temperature above 482 °F (250°C).
-
A process vessel inventory above 565 ft3 (16 m3) and a flammable product where flammable
liquids are defined as:
1.
Low-flash liquids (flash point below 100°F (38°C)
2.
Combustible liquids with an operating temperature range starting from 15 °F (8 °C) below
the liquid flash point temperature and above
8.7. DRIVER FOR CRITICAL SERVICE PUMP
Motor will be applied as a rule taking into account reliable power supply from captive power
generation system. However, steam turbine may also be applied in consideration of the overall
steam balance. In the case the applied code so requires, diesel driver may be applied (e.g. fire
water pumps).
8.8. HIGH LEVEL IN FEED DRUM, COMPRESSOR KO DRUM, SEPARATOR DRUM AT
REACTION SECTION
To avoid overfilling, an independent High High Level alarm (HHLA) via a Level Transmitter (LT)
will be specified and connected to SIS.
The level transmitter will be connected to the drum with independent nozzles of the others LT/LG
nozzles.
It shall be validated by a SIL Study when such high level shut down interlock will be applied.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 29 of 93
8.9. COMPRESSOR ISOLATION CONSIDERRATIONS
To reduce the consequences of a fire in compressor area, remote activated isolation valves will be
installed in the suction and discharge of any compressor with a power higher than or equal 150 kW
and handling flammable or toxic gases.
These valves and associated actuation system shall be fire safe and shall be operated by a local
push button (in safe location) and from control room
These valves closure shall result in the corresponding compressor automatic shutdown.
The
need of associated emergency depressurisation of the isolated compressor shall be investigated
for each compressor through HAZOP and/or Vendor recommendation.
8.10. BACK FLOW OVERPRESSURE CONTROL / MITIGATION
Following minimum devices will be considered at the pump discharge.
Additional provisions to be defined in each case individually through HAZOP
•
Pressure lower than or equal to 580 psig (40 barg): one check valve
•
Pressure higher than 580 psig (40 barg) and smaller than 1160 psig (80 barg): two check
valves of different type (steam or shaft blow out resistant, preferably of the non-slamming
type).
•
Pressure higher than or equal 1160 psig (80 barg): two check valves of different type (stem or
shaft blow out resistant, preferably of the non-slamming type) plus an automatic shut-off valve
in case of low flow.
Additional provision could consist of either sizing PSV for backflow flowrate or providing redundant
initiators activating closure of a dedicated ESD valve or the flow control valve on pump discharge.
8.11. FIRED HEATER ISOLATION CONSIDERATIONS
In case of tube rupture in a fired heater and to minimize the consequences of a fire the following
option can be considered depending on liquid/gas inventory and operating pressure:
•
A motor operated isolation valve will be installed at the inlet of the fired heater, if it is not
possible to shut down the feed flow.
•
Feed stops and steam displacement of coils
•
A check valve or motor operated isolation valve shall be installed at the outlet of heaters that
operate above 1000 psig
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 30 of 93
8.12. PUMP SEALS
Unpressurized dual mechanical seals or sealless pumps shall be considered in the following
cases:
•
LPG
•
Hydrocarbons above their auto ignition temperature or at a temperature higher than 482 °F.
(250°C)
•
Hazardous/Flammable fluid
•
Pump with operating pressure at stuffing box higher than or equal to 725 psig (50barg)
Pressurized dual seals or sealles pumps shall be adopted for high toxicity or carcinogenic fluids).
The criteria for liquids containing H2S is as follows:
1)
H2S content in the liquid ≥ 500 ppm(wt) ・・・・・・・・・・・・・・・・・・・・・・・・・Toxic/Highly Toxic
(Dual pressurized seals is required per Arrangement 3 of API 682)
2)
H2S content in the liquid ≥ 50 ppm(wt) and <500 ppm(wt) ・・・・・・・・・Hazardous
(Dual un-pressurized seals per Arrangement 2 of API 682)
3)
H2S content in the liquid < 50 ppm(wt) ・・・・・・・・・・・・・・・・・・・・・・・・・・Mildly Hazardous
(Single Seals as per arrangement 1of API 682)
For seal specifications, when a pressurized dual seal is selected, API Plan -53B shall be adopted,
unless high temperature prevents its use.
Final definition of the seal arrangement will be done during the EPsCm stage with the selected
manufacturer.
8.13. CONSTRAINTS DUE TO BENZENE HANDLING
Due to the benzene carcinogenetic knowledge, the following precautions shall be taken when
applicable:
•
For all streams containing 0.5 per cent weight benzene or more and 25 per cent weight C7
through C9 aromatics or more, the following shall apply:

Closed sampling

Closed collection system with a below grade drum in an open pit receiving all
corresponding process part drains. For high benzene concentration, a threshold shall be
agreed with PDVSA.

Pumps will be equipped with dual mechanical pressurized seals or pumps will be sealless
if operating conditions allow it.
•
Valve, flanges and joints shall be such as to satisfy the TWA (Time-Weighted Average)
requirements exposure limit of 1 ppm for an 8-hour workday (OSHA’s requirement). The
application of low emission vales & fittings to all CCR units shall be confirmed by PDVSA
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 31 of 93
during detailed engineering. All water streams saturated with aromatics shall be sent to a
suitable processing or treating facility in order to minimize aromatic emissions to the
environment.
8.14. CONSTRAINT DUE TO STREAMS CONTAINING H2S
When a process unit contains hydrocarbons or water streams with H2S content higher than or
equal 10 wt ppm, the following precautions shall be taken to avoid H2S release to atmosphere:
•
Closed Loop Sample Connections.
•
Closed collection system with a below grade drum in an open pit receiving all corresponding
process part drains from where flashed H2S can be routed to flare.
Consortium shall provide adequate H2S detection system in the process unit.
8.15. BATTERY LIMIT ISOLATION
For flammable hydrocarbon liquid and gas services except flare service, double block valves, a
check valve and spectacle blind in between block valves and two bleeder valves (one just after
first block valve and the other before the second block valve ) shall be provided at each process
unit battery limit.
A single block valve, a spectacle blind and two bleeder valves (one at either
side of spectacle blind) arrangement shall be provided for non-hazardous streams (i.e. utility
streams). The following are standard practices for specifying battery limit isolation:
•
Battery limit isolation shall be specified for all process lines leaving the designed unit.
•
Process lines arriving at the designed unit, from facilities or process units outside scope of
design shall be specified with battery limit isolation.
•
Above isolation policies shall be applied to chemical and hydrogen lines entering or leaving
the designed unit.
•
A block valve (CSO) shall be specified between each unit independent flare header and the
main refinery flare header. To fulfil the CSO specification the valves shall have horizontal or
downward directed stem.
Spectacle blinds shall normally be used for piping up to 12”. Spade (paddle blinds) shall be used
for piping 14” and above.
0
El Palito Refinery Expansion Project
Phase II
9.
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 32 of 93
DESIGN CONSIDERATIONS
As a general rule, while defining the scenarios (different from the normal operating one) for the
selection of the design conditions of equipment, no double occurrence shall be considered.
As an example, during steam out operations, system blocking-in and steam network at the design
conditions, considered at the same time, is not deemed a credible scenario.
9.1. DESIGN PRESSURE AND TEMPERATURE
9.1.1. Design pressure for individual equipment items
Design pressure does not include the liquid static, as this will be added by the vessel design
group based on the high level.
Pressure drop across trays or vessel internals should be included if it is significant.
Design pressure shall be selected among the below listed values, whichever is greater:
•
51 psig (3.5 barg), same as minimum low pressure and acid flares design pressure.
•
Maximum flare back pressure if the vessel is directly connected to the high pressure flare
network
•
For maximum operating pressures less than 247 psig (17 barg), use the maximum operating
gage pressure + 25 psi (1.7 bar).
•
For maximum operating pressures between 247 psig (17 barg) and 1450 psig (100 barg),
use 110 per cent of the maximum operating gage pressure.
•
For maximum operating pressure between 1450 psig (100 barg) and above, use the
maximum operating pressure plus 145 psi (10bar).
•
Design pressure for atmospheric tanks and drums (normally vented to atmosphere) shall be
as per following.
Roof Type
Design Pressure
Floating
ATM
Cone Roof (for Water Service)
ATM
Cone Roof (for Oil Service *1)
38mmH2Og / -25mmH2Og
Note:*1 breather valve to be installed.
•
In case of nitrogen blanketing for tank roof type of Cone Roof/Cone Roof with Internal
Floating, the design pressure shall be up to 200 mm H2Og /-25 mm H2Og
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 33 of 93
Full Vacuum shall be specified for equipment in the following cases:
•
Equipment that normally operates under vacuum conditions. Full Vacuum shall be specified
at the design temperature of the equipment.
•
Equipment subject to start up, shutdown and/or regeneration evacuation. Full Vacuum shall
be specified at the corresponding evacuation phase temperature.
•
Equipment subject to steam out. Full Vacuum shall be specified at ambient temperature.
•
Equipment, which normally operates liquid full and that, can be blocked in and cooled down.
Full Vacuum shall be specified at the equipment normal operating temperature.
•
Equipment containing fluid having a vapour pressure lower than atmospheric pressure at
ambient temperature. Full Vacuum shall be specified at ambient temperature.
•
Fractionators and associated equipment that can undergo a vacuum through the loss of heat
input. The temperature at which this full vacuum occurs must also be specified.
Equipment normally operated under vacuum or frequently exposed to start-up or shut down
evacuation shall be designed for full vacuum and for the highest pressure the equipment can
experience in case of vacuum system failure.
9.1.2. Shell and tube heat exchangers
ASME rules have to be followed for shell and tube heat exchangers where the design pressure
of one side is considerably higher than the other one. According to these criteria the tube side
design pressure cannot be under 10/13 of the shell side design pressure value. For
high-pressure exchangers a maximum differential pressure of 725 psi should be considered.
The updated API / ASME rule regarding the design pressure of low-pressure side compared to
high-pressure side is now equal to the 10/13 rule as follows.
When the design pressure of LP side is lower than 10/13 of the design pressure of HP side
(according to code ASME Section VIII div. I) Or (10/12.5 per ASME Code Section VIII div. 2), the
design pressure of LP side will be increased up to 10/13 of the design pressure of HP side (or
10/12.5) for the heat exchanger and the piping up to and including manual isolation valves on LP
side, but not for the associated low pressure side piping system beyond the manual isolation
valves. No specific safety device will be provided for tube rupture at FEED stage. However the
low-pressure side piping is to be evaluated for overpressure by the detailed engineering
contractor. The piping design pressure is to be up-rated if required or appropriate protection to
be provided.
Hydrostatic test pressure shall be as specified in ASME Code UG-99.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 34 of 93
9.1.3. Design pressure for complete systems
When the same relief valve protects several equipment pieces, each one will be designed, at
least, for the pressure imposed by the relief valve discharge conditions in case of emergency.
For fractionating columns, the reference design pressure is taken at the column bottom. No
isolation valves, or other devices that may restrict the flow, are allowed in between the protected
equipment and the PSV location.
9.1.4. Fractionation tower and auxiliaries
The design pressure of the overhead equipment shall be increased of the corresponding static
head of the liquid column between the overhead accumulator and the overhead condenser, in
order to account the case of condensation loss due to overhead system flooding.
Example:
Tower bottom design pressure:
250 psig x 1.1 = 275 psig
Relief valve set pressure:
245 psig x 1.1 = 269.5 psig
Reflux drum design pressure:
269.5 psig
PSV
Set Pressure=269.5 psig
235
245
250
HLL
LLL
Operating Pressure: psig
Fig 9.1 Design Pressure of Tower and Auxiliaries
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 35 of 93
9.1.5. Exchangers, vessels and other equipment on the pump discharge
Equipment, which could have to bear a pump shut-off pressure because a closing valve (either
control valve or block valve) must be designed for the following pressure:
Design pressure = Suction Vessel Design Pressure + liquid height at vessel HLL at pump suction
+ 120 per cent of pump differential pressure.
In case of steam turbine drive equipment the shut off pressure should be calculated based on
maximum continuous speed of steam turbine, which is 105% of pump rated speed
corresponding to 132% of pump differential pressure.
The same Design pressure of pump discharge line shall be applied to the suction line of the
pump up to and including the manual isolation valves on suction line or the automatic block valve
(where foreseen), in order to protect the suction line in case of wrong switch over operation
9.1.6. Process system similar to that of a reactor-recycle gas-loop
In this case, the recommendations given in the API Standard 521, last edition, Annex "B" and
API Standard 520, last edition, Annex "B", will be followed.
9.2. DESIGN TEMPERATURE
Design temperature shall be selected among the below listed values, whichever is greater:
•
Maximum operating temperature plus 27 °F, with a minimum of 176 °F, in the absence of any
other specific criteria.
•
For feed/effluent exchangers of reaction sections, the maximum operating temperature plus
45 °F, to take into account the operating temperature profile modification at low capacity.
•
For reaction sections, the loss of feed and air cooling (i.e. power failure) shall be considered in
order to evaluate the temperature profile due to the generated heat wave. The resulting
maximum operating temperatures shall be selected as design temperatures of the involved
equipment, if higher than any other temperature calculated as per the above criteria.
•
In case of coolant failure, the cooler upstream maximum operating temperature shall be
considered as the downstream equipment design temperature.
•
In case of local air-cooler failure, the maximum outlet temperature, considering the residual
natural draft cooling capacity, shall be considered as the downstream equipment design
temperature.
It shall be observed that whenever heat exchanger is provided with bypass line on its hot side for
process/maintenance purposes the maximum inlet temperature shall be considered as the
downstream equipment design temperature.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 36 of 93
The Minimum Metal Design Temperature (MMDT) shall be selected among the below listed values,
whichever is lower as per ASME Section VIII, Division 1:
•
Minimum ambient temperature.
•
For operating temperatures below 32 °F, minimum operating temperature minus 9 °F.
•
For equipment containing LPG, the minimum operating temperature considering the
equipment depressurisation down to atmospheric pressure.
9.3. EQUIPMENT STEAM PURGING
For equipment subjected to steam out, the following sentence will be specified on the data sheet:
“Subject to steam out conditions”. The normal operating pressure and temperature of the steam
shall be indicated as additional design conditions for the equipment.
Steam out of large equipment should be performed using MP steam unless the equipment design
conditions are heavily affected.
For low design pressure and temperature equipment, due to economical reasons, the use of LP
steam is recommended.
The choice between the two steam levels shall be based on economic considerations.
9.4. CYCLIC OPERATING CONDITIONS
For equipment exposed to pressure and temperature swings, the magnitude and frequency of
these swings will be given on the specification sheet.
9.5. EQUIPMENT FLUSHING OR WASHING
In some process units, equipment may be subject to flushing or washing operations prior to
shutdown or maintenance (i.e. Vacuum units flushing with gas oil of residue circuits).
For equipment involved in these kinds of operations, the same design conditions of the
flushing/washing network shall be applied as additional design conditions, unless the equipment
design conditions are heavily affected.
In case of flushing/washing operations having a big impact on the equipment design conditions, a
properly sized PSV shall be installed to protect all the equipment involved in such operations.
The selection between the above-described solutions shall be based on economic considerations
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 37 of 93
9.6. TRANSIENT OPERATING CONDITIONS
In case of particular operating transient conditions, such as start-up, shutdown, catalyst activation,
catalyst regeneration, etc., the maximum operating conditions shall be considered in order to
identify any additional equipment design conditions as per the general criteria mentioned in the
preceding paragraphs.
9.7. CORROSION ALLOWANCE
9.7.1. Equipment Design Life
The following design life may be applied to the unit design as a standard base:
•
Heavy Wall Reactors/Vessels:
30 years
(Including non-removable internals and catalyst bed support beams)
•
Reactor Removable Internals:
20 years
•
Columns & Vessels:
20 years
•
Exchangers: Shell, Channel, Tubesheets:
20 years
•
Exchanger Tubes Bundles:
Carbon Steel and Low Alloy
5 years
High Alloy and Non-Ferrous
10 years
•
Furnace Tubes:
10 years
•
Piping:
10 years
9.7.2. Pressure Retaining Equipment
The calculated corrosion allowance shall be based on the designed number of years in service
(See Section 9.7.1).
Metallurgy specified will be based upon that required for process considerations. The Contractor
work scope shall include the Corrosion Control and Corrosion Inspection Programs.
Corrosion allowance shall be specified as per the following general criteria:
•
A minimum CA of 1/8” (3 mm) for carbon steel in general non-corrosive environment such as
general hydrocarbon service.
•
In normal operation under Wet H2S Service, carbon steel shall have a CA of 1/4” (6 mm) for
most severe services and minimum CA of 1/8”(3mm) for other wet H2S services.
•
Minimum CA shall be 1/8” (3 mm) for low-alloyed steels (up to 2 1/4 % Cr included).
•
Minimum CA shall be 1/16” (1.5 mm) for low-alloyed steels (up to 9 % Cr included). This CA
may be extended, in accordance with PDVSA, to 1/8” (3 mm) for critical equipment (i.e.
Reactors, HP Vessels and Furnaces).
•
Minimum CA shall be 1/32” (0.75mm) for stainless steels.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 38 of 93
For tubular heat exchangers, CA defined for tubes and shell sides, is applied to pressure
retaining elements.
•
Tubesheet is concerned by CA on each side.
•
Tubes are not concerned by specified CA, whichever the side. If equipment is cladded or
weld overlayed, only undiluted thickness of clad weldings or weld overlay shall be
considered as corrosion allowance.
9.7.3. Internals
a.
"NON REMOVABLE INTERNALS" means: welded internals to vessels (support rings,
support lugs, etc.)
b.
"REMOVABLE INTERNALS" means: non welded internals to vessels (fractionation trays,
distributor trays, mixing trays, catalyst support trays, support beams, inlet diffusors, outlet
collectors, Quench pipes, thermocouples supports, etc.)
•
Removable parts of carbon steel and low-alloyed steels (up to 9% Cr) internals shall have a
minimum CA of one half of total vessel shell CA on each side in contact with the operating
fluid.
•
Fixed internals carbon steel and low alloyed steel (up to 9% Cr) made shall have the full
corrosion allowance on each face (in total 2 times the designed CA of shell).
•
In general, no corrosion allowance will be given for removable internals made of stainless
steel (13 % Cr and above) and also for those non-ferrous high alloyed made.
However, a corrosion allowance shall be specified for some internals exposed to severe
conditions such as non-removable internals of reactor, catalyst bed support beams of
reactor. These internals shall therefore have the CA, based on the reactor design life
specified in paragraph “Equipment Design Life”, on each exposed surface.
•
Tubular Heat Exchanger non-removable internals are not concerned by CA, whichever the
side.
•
No corrosion is considered for internals made with V wire screen or wire mesh.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 39 of 93
9.8. P&ID’S PREPARATION AND PRESENTATION
In order to prepare diagrams (P&ID´S), symbols must be according to Instrumentation, Systems
and Automation Society (I.S.A.) standard and 00-FINS-SP-0001 Rev.C02 are used for
instrumentation symbols and identification.
9.8.1. Equipment item number, service name and short specification
The following information is indicated as short specification.
1) Pump, Fan, Blower, Turbine and Compressor
Item No.
Service Name
Design Capacity
gpm(Pump)
SCFH(Compressor /Blower/Fan)
Lb/h(Turbine)
Head
ft
Rated Power
HP
Shut-off Pressure
PSIG
Material
Insulation
2) Drum, Tower & Column
Item No.
Service Name
Size: ID x T-T
(ft-in) x (ft-in) as typical
Design/Operating Pressure
PSIG
Design/Operating Temperature
O
F
Material
Insulation
3) Heater and Air Fin Cooler
Item No.
Service Name
Type
Design Heat Duty
MMBTU/h
Design/Operating Pressure
PSIG
Design/Operating Temperature
O
Material
Insulation
F
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
4) Shell & Tube Heat Exchangers
Item No.
Service Name
Type
Design Heat Duty
MMBTU/h
Surface Area
ft
Design/Operating Pressure
(Shell/Tube)
Design/Operating Temperature (Shell/Tube)
Material
2
PSIG
O
F
(Shell/Tube)
Insulation
5) Tank
Item No.
Service Name
Size: ID x H
(ft-in) x (ft-in) as typical
Normal Capacity
BARRELS
Design/Operating Pressure
PSIG
Design/Operating Temperature
O
F
Material
Insulation
6) Others
Item No.
Service Name
Design/Operating Pressure
PSIG
Design/Operating Temperature
O
Material
Insulation
F
Page 40 of 93
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 41 of 93
9.8.2. Representation of Equipment
The following information are to be shown on the P&IDs and UFDs, as minimum:
1) Heater
a.
Equipment Tag
b.
Shape of Heater
c.
Radiation Coils
d.
Convection Coils, if any
e.
Connection Type (flange or welding) and Size
f.
Inlet and Outlet Manifold for Multi-Pass Heaters
g.
Decoking Nozzle Connection, if any
h.
All Attached Instruments
i.
Snuffing Steam Connection
j.
Stack Damper
k.
Flue Gas Sample Connection
l.
Fuel Gas System to Heater
m. Heater Decoking System, if any
2) Tower / Vessel (Reactor & Drum) / Filter
a.
Equipment Tag
b.
Shape of Tower and Vessel (including boot, if any)
c.
Trays or Packing (Typical Trays are shown on P&IDs for Tray Tower)
d.
Tray No. for Tray Tower
e.
Distributor Simple Representation or Indication, if any
f.
Mesh Blanket, if any
g.
Vortex Breaker, if any
h.
Manhole and its Size
i.
Skirt Height or Elevation of Vessels
j.
All Piping and their Sizes with Connection Type (flange or welding)
k.
All Attached instruments
l.
Vent and Drain Valves, if any
m. Diameter and T-T Length of Tower and Vessel (including boot, if any)
n.
Slope Requirement for Horizontal Vessel, if required
o.
Relief Valves with Set Pressure and Size Indications, if any
p.
Steam-out System, if any
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 42 of 93
3) Heat Exchanger (Shell & Tube, Double Pipe, etc.)
a.
Equipment Tag
b.
Shape of Exchanger for Kettle, Vertical, Double Pipe and Other Special Type
c.
Manhole and its Size, if any
d.
All Piping and their Sizes with Connection type (flange or welding)
Special cases as neutralization flanges shall be complemented by spectacle blinds and
referred notes.
e.
All Attached Instruments
f.
Vent and Drain Valves, if any
g.
Symmetrical Piping (clearly indicated)
h.
Relief Valves with Set Pressure and Size, if any
4) Air Fin Cooler
a.
Equipment tag
b.
Type of Air Fin Cooler (forced or induced)
c.
Number of Bundles (to be shown in detail, if required)
d.
Number of Fans and Motors (to be shown in detail, if required)
e.
Louver, if any
f.
Inlet and Outlet Manifold with Size and Connection Type (flange or welding)
g.
Steam Coils, if any
h.
Vibration Switches, if any
i.
Variable Speed Motor Indication or Referred Note, if any
j.
Vent and Drain Valves, if any
k.
All Attached Instruments
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 43 of 93
5) Pump/Compressor/Blower
a.
Equipment Tag
b.
Type of Pump, Compressor and Blower
c.
Type of Driver
d.
Connection Size and Rating of Suction and Discharge
e.
All Connection Size and Rating of Process Piping (utility lines are indicated on vendor's
P&ID. Only lines to tie-in with Vendor Scope are indicated on UFD.)
Specific cases of flushing shall be indicated
f.
All Instruments related to Main Process Fluid Control and Monitoring (other instruments
are indicated on vendor's P&ID)
g.
Relief Valves installed on Pumps and Compressors with Set Pressure and Size
Indications
h.
Vent and Drain Valves, if any (include the destination and special requirements for closed
systems)
i.
Simplified Representation of Seal System for Compressor, if any
6) Tanks
a.
Equipment Tag
b.
All Piping and their Sizes with Connection Type (flange or welding)
c.
All Attached Instruments
d.
Relief Valves with Set Pressure and Size Indications, if any
e.
Vent and Drain Valves
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 44 of 93
9.8.3. Instrumentation
The following information are to be shown on P&ID and UFDs
a.
Type of Instrument
b.
Instrument Nozzle Installed on Vessel with Size and Rating
c.
Heat Tracing Requirements
d.
Type of Control Valve (e.g. globe or butterfly)
e.
Air Failure Positions for Control Valves
f.
Limit Switch
g.
Tight Shut-off (TSO) Requirements for Control Valves
h.
Hand-Wheels for Control Valves
i.
Control Valve, Block Valve and Bypass Valve Size (including indication Locked Open/Close
as LO/LC, if any)
j.
Interlock and Linkage among Related Instrument and Equipment
k.
Set Pressure and Size of Pressure Safety Valves
The instrument block valves will not be indicated in each P&ID, but the provision and
size/specification shall be as per piping details prepared by Consortium (00-FPIP-SS-0001) and
as per Instrument Job Specification 00-FINS-SP-0007
Symbols and Identification to be referred on GENERAL NOTES, SYMBOLS AND LEGEND,
“EB020401-G00-DP20800P0001 to EB020401-G00-DP20800P0016”
9.8.4. P&ID of Package Units by Vendor
Vendor’s Package P&IDs such as Compressors, Heaters, etc are used as one of process P&ID.
On process P&ID, the simplified flow scheme of vendor’s portion and the drawing no. of Vendor’s
P&ID is indicated on process P&ID to refer the P&ID easily. Connection of Process P&ID and
Vendor P&ID should be one. Any duplicated indication on process and vendor P&ID shall be
prohibited to avoid confusion.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 45 of 93
10. EQUIPMENT DESIGN BASIS
0
10.1. VESSELS
10.1.1. Inside Diameter
For drums with a continuous vapor flow, the cross sectional area above the high liquid level must
be large enough to limit the vapor velocity to the values given below.
𝜌𝐿 − 𝜌𝐺
𝑉𝑔 = 𝐾 �
𝜌𝐺
Where:
Vg: Allowable Gas Velocity (ft/sec)
ρL: Liquid Density at Operating Condition (lb/ft3)
ρG: Gas Density at Operating Condition (lb/ft3)
K: Separation constant, as calculated from the values shown below
a.
For Vertical Separators & Scrubbers
WL/W G<0.1
K=0.35
0.1<W L/W G<1.0
K=0.25
1.0<W L/W G
K=0.20
Where:
WL: Liquid Mass Flowrate (lb/h)
WG: Liquid Mass Flowrate (lb/h)
b.
For Horizontal Separators
2.5<L/D<4.0(*1)
K=0.40
4.0<L/D<6.0
K=0.50
6.0<L/D(*2)
K=0.50(L/Lbase)0.05
(*1) Minimum Allowable L=7.5ft
(*2) Maximum Allowable K=0.7 and Lbase/D=6.0
c.
For the vessel without mist eliminator, use K as the above K multiplied by 0.8.
For the vessel of critical services, use K as the above K multiplied by 0.5.
d.
For hydrogen service (free hydrogen or mixture of hydrogen with hydrocarbons where the
hydrogen partial pressure exceeds 75psia), use K=0.15.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 46 of 93
10.1.2. Required Length
a.
Between Inlet Nozzle C/L and High Liquid Level for Vertical Vessel
For vertical separators, the distance between the inlet nozzle centerline and the high liquid level
(HLL) should be 0.3 times the diameter (2 ft minimum).
b.
Between Inlet Nozzle C/L (or Mist Eliminator) and Top Tangent Line for Vertical Vessel
In case no mist eliminator is present, 0.6 times the diameter (4 ft minimum) should be allowed
between the inlet center line and the top tangent line.
In case a mist eliminator is present, allow for 0.6 times the diameter (3 ft minimum) to the bottom
of the mist eliminator plus 1 ft from the top of the mist eliminator to the tangent line. Mist
eliminators shall be at least 6 inches thick.
c.
Between Top and High Liquid Level for Horizontal Vessel
The vapor space in horizontal separators above the high liquid level (HLL) must be at least 0.2
times the diameter (1 ft minimum). If a mist eliminator is used, it shall be placed 18 inches above
the high liquid level (HLL).
High-high liquid level (HHLL, used for SIS) shall be 6” bellow the inlet for vertical separators or 6”
below the top tangent line (or below the outlet mist eliminator, if present) for horizontal
separators.
d.
Between Bottom and Low Liquid Level for Horizontal Vessel
Low-low liquid level (LLLL, used for SIS) shall be one foot above the vertical vessel bottom
tangent and one foot above the bottom of horizontal vessels.
e.
Reboiler Return Nozzle for Tower
- 12” + Reboiler return nozzle nominal diameter between the nozzle bottom and the high liquid
level (HLL).
- A tray spacing + 6” between the top of the nozzle and the bottom tray.
- Orient the reboiler return nozzle parallel to the seal pan bellow the bottom tray downcomer, so
reboiler vapor does not impinge directly on seal pan overflow (this could entrain liquid to the
bottom tray).
El Palito Refinery Expansion Project
Phase II
f.
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 47 of 93
Surge and Hold-up Time
The minimum surge and hold-up times shown below shall be used for vessel sizing.
Hold-up time is defined as the time from normal liquid level (NLL) to low limit of the level indicator
(LLL), with no feed and normal flow out.
Surge time is defined as the time from normal liquid level (NLL) to high limit of the level indicator
(HLL), with normal feed and no flow out. The following table present the minimum surge &
hold-up time for design, When only one figure is given, it corresponds to HLL-LLL , in the case of
others criteria, contractors shall be used the most stringent.
Table 10.3 Minimum Surge and Hold-up Time in General
SERVICE
MINIMUM SURGE
& HOLDUP TIME (Minutes)
General
To storage without pump
2
Feed to low head charge pump
2 & 5*1
Feed to high head multi-stage pump or fired heater
3 & 10*1
To further processing (based on product flow)
5*1
*1 If the vessel can be considered part of a closed loop system (like lean/rich amine), use minimum 7.5 minutes for the
storage vessel and 3 minutes for all other vessels.
Table 10.4 Minimum Surge and Hold-up Time for Feed Surge Drum
SERVICE
MINIMUM SURGE
& HOLDUP TIME (Min.)
Feed Surge Drum (feed to unit)
Feed coming from more than two sources
5 & 15
One to two feed sources (upstream on flow control)
5 & 10
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 48 of 93
Table 10.5 Minimum Surge and Hold-up Time for Column
SERVICE
MINIMUM SURGE
& HOLDUP TIME (Min.)
Column Bottoms
Shall be based on greater of :
product flow (based in General) or on flow to fired reboiler
3
Column Lateral Drawoff / Side Stripper
Shall be based on greater of :
On product flow
2
On reflux
5
Reflux Drums
Shall be based on greater of:
product flow (based in General) or on reflux
Steam Reboiler Condensate Pot
5
15 sec.*2
*2 Size Condensate Pot based on maximum condensate flow (max. Cv of condensate valve) and so that the tangent to
tangent elevation is:
For horizontal reboilers;
2’ + reboiler diameter
For vertical reboilers;
2’ + reboiler tube length
Note: For Vacuum Column Bottoms, the residence time (product + quench) will be based on 150 seconds from HLL
to LLL
Table 10.6 Minimum Surge and Hold-up Time for KO Drum
SERVICE
MINIMUM SURGE
& HOLDUP TIME (Min.)
KO Drum
Based on 1% carryover for Compressor Suction KO Drum
Fuel Gas KO Drum
5
HLL to LLL based on 20 feet slug of liquid in inlet pipe
g.
L/D Ratio
An optimum L/D ratio will be considered from a viewpoint of cost. In general, the L/D ratio should
be as high as possible, complying at all times with the minimum diameter as set for the allowable
gas velocity criteria. For reactors, L/D ratios up to 8 will be acceptable, in absence of other
special consideration.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 49 of 93
10.1.3. Nozzle and Flange
a.
Inlet Nozzle
Inlet nozzle should be equipped with a deflector device to spin the inlet to the separator, for
better liquid degassing. A vane type inlet is a good choice for crude column applications.
However, tangential-helical entrances are preferred for crude, vacuum and FCC tower feeds.
b.
Outlet Nozzle
The velocity at the liquid outlet shall be less than 3 ft/sec.
For the inlet and vapor outlet, the
velocity shall be based on:
Where:
𝑉𝑛𝑜𝑧𝑧𝑙𝑒 =
ρm: vapour or vapour-liquid mixture density (lb/ft3)
c.
80
�𝜌𝑚
For Instrument
Thermowell nozzles on vessels shall be flanged and shall be 1½” minimum inside diameter.
Alloy lined thermowell nozzles will be larger nominal diameter to ensure 1½” lining minimum
inside diameter. For trayed columns, thermowell nozzles will be located in the downcomer area,
rather than in the vapor space.
For vessels constructed in accordance with a pressure vessel code, Class 150 flange rating as a
minimum shall be specified, except for level instrumentation pipe columns and pressure relief
valve connections which are specified with a Class 300 minimum flange rating.
d.
Level Instrument
In general, nozzles on vessels shall be provided for the installation of external displacement
(float) type level instruments, level switches and gauge glasses as follows:

For controlled and viewed liquid level or for installations requiring multiple gauge glasses,
two flanged nozzles in minimum 2” with a minimum Class 300 flange rating shall be provided
to install a 2” (use 3" for high pour point services like vacuum residue) pipe column for spans
between vessel nozzles up to and including 15´-0". Multiple pipe columns shall be provided
for spans greater than 15´-0".
The external displacement type level instrument, level switches (including SIS switches) and
gauge glasses shall be installed on the pipe column. Where concern for plugging exists
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 50 of 93
(high pour point materials, salt deposits, etc) or when only one level switch is provided, SIS
switches will be installed direct to the vessel with the proper isolation facilities.

For horizontal vessels with a boot, the liquid interface boot bridle upper connection to the
vessel is not to be combined with the bottom bridle connection on the drum section.

On the vessel inside at the top flanged connection, a baffle must be provided to minimize
level fluctuations.
e.
Drain and Vent
Vessels shall normally be provided with blind flanged drains and vents in accordance with the
following table:
Table 10.1: Vent and Drain Size
VESSEL DIAMETER
DRAIN SIZE
VENT SIZE
1-1/2"
1-1/2"
Over 9´-6" through 14´-6" (4500 mm)
2"
1-1/2"
Over 14´-6" through 19´-6" (6000 mm)
3”
2”
Over 19´-6" (6000 mm)
4”
3”
9´-6" (2900 mm) and less
For services 1,500 psig and above, vents and drains will be provided with double globe valves
and sized as per the table above.
Separate steam-out connections (MP or LP steam) are to be generally provided, according to:

For vessels greater than 15,000 ft3 and no less than 13’-0” I.D., one 3" steam-out hard
piped connection with double block and bleed and a 6” blinded gate vent.

For vessels greater than 5,000 ft3 and no less than 8’-0” I.D., one 2" steam-out hard piped
connection with double block and bleed and a 3” blinded gate vent.

For vessels greater than 5,000 ft3 and less than 8’-0” I.D., one 2" steam-out hard piped
connection with double block and bleed and a 2” blinded gate vent.

2" nozzle with a gate and a blind and a 2" blinded gate vent, for all the rest.
Additionally, on horizontal vessels 10 feet or over in tangent length, a blanked off ventilation
nozzle shall be provided on the top of the vessel near the end opposite the manway.
ventilation nozzle shall be sized as follows:
The
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 51 of 93
Table 10.2: Ventilation Nozzle
VESSEL TANGENT LENGTH
NOZZLE SIZE
10´-0"(3100 mm) through 14´-6"(4500 mm)
4”
Over 14´-6"(4500 mm) through 24´-6"(7500 mm)
6”
Over 24´-6"(7500 mm)
8”
10.1.4. Miscellaneous
a.
Skirt Height
Required skirt heights above grade will be set by process conditions (e.g., pump NPSH). When
skirt height is not influenced by process factors, it will be specified as “Minimum” on the
equipment data sheet.
b.
Liquid Drop Legs (Drawoff Boots)
When required, liquid drop legs (drawoff boots) shall be provided on horizontal vessels as follows

Drop leg diameter is based on comparison of water droplet settling velocity versus HC
droplet rising velocity. The minimum diameter will be 24" and the vessel diameter ratio to
drop leg diameter shall be between 3 and 4.

Minimum length is 3 ft for level controller connections.

If the vessel is lined, the drop leg shall be internally lined and welded to the vessel.
If the
vessel is unlined, the drop leg shall be unlined and welded to the vessel.
c.
Vortex Breaker
All pump suctions from vessels and columns will be provided with Vortex Breakers.
d.
Others
Insulation, heat tracing, PWHT, hydrogen service (hydrogen partial pressure greater than 100
psia), sour wet service, and other special services, if required, shall be indicated on the vessel
data sheet.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 52 of 93
10.2. TRAYS AND PACKING
10.2.1. Selection of Tray or Packing
Valve trays shall be specified for fractionation services.
Packing shall be used for specific services such as revamps of existing towers, new towers
under 36 inches in diameter and internals modification with high economic incentives like
vacuum towers.
Even in this case, since towers diameter are determined by two factors,
flooding limit and pressure drop, the diameter should be determined so that limits do not exceed
for either two criteria and so using packing up to 36 inches diameter shall be asked for PDVSA
approval.
Whether packing for new towers larger than 36 inches can be applied in PDVSA clarification
In case of selection of tray, Valve Trays will be normally specified.
Trays will be numbered from bottom to top
10.2.2. Hydraulics
a.
Overdesign for Columns will correspond to 10 % of normal flow rates.
b.
Operating range for the trays will be at least 50 to 110 % of normal loads.
c.
Fractionator’s trays shall generally be designed for the same turndown as indicated for the
process units. However, in some services, the reflux rates and reboiler duties may not be turned
down in proportion to the unit turndown when higher tray loadings are required to maintain
desired efficiency.
d.
Three pass trays shall not be specified
e.
Column diameters are estimated using calculation methods provided by the major packing
manufacturers.
f.
The following flooding limits for column sizing will be applied for all tray applications (valve, sieve
etc.):
 Jet Flooding Limit
・85% for all applications
 Down Comer Choke Flooding Factor:
・75% for high-pressure service (vapor density>2.5 lb/cf) and for column diameters under 36”
・80% for other applications.
10.2.3. Material
a.
410 SS trays shall be specified except where corrosive conditions during normal operation
warrant the use of other alloy, unless material already specified by Licensors of relevant Units.
b.
11-13 chromium alloy tray material is generally specified without corrosion allowance.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 53 of 93
10.3. SHELL AND TUBE HEAT EXCHANGERS
10.3.1. Heat Exchanger Type
Unless impractical, shell and tube type exchanger shall be specified. Double-pipe or
multiple-tube type heat exchanger will be specified where appropriate.
For shell and tube heat exchangers, space for maintenance of the tube bundles shall be
provided
10.3.2. Process Specification
a.
No overdesign will be considered for the heat exchangers, except:

Overhead condensers
Greater of either 110 % of the estimated operating duty or the duty, increase of the
corresponding reboiler.

Effluent cooler (or feed preheater)
10 % of cooler duty (or preheater duty) or 5 % of feed/effluent exchange duty, whichever is
greater.

Reboiler
5 % of feed/bottom exchange or 10 % of reboiler duty, whichever is greater.

Bottom cooler
10 % of cooler duty or 5 % of feed/bottom exchange duty, whichever is greater.
b.
The recommended normal cold end temperature approach is 18°F minimum. For reboilers, a
temperature difference of at least 25°F shall be used between condensing steam and the
process fluid.
c.
Fouling factors for utility services shall be specified as per BEDD
10.3.3. Reboiler
a.
Horizontal thermosiphon reboilers are preferred. Once-through vertical thermosiphon reboilers
will not be used if the vapor flow is greater than 30 weight percent. Horizontal thermosiphon
reboilers can be designed for vapor flow as high as 50 weight percent. When once-through
thermosiphon reboilers are specified a chimney tray for the collection and disengagement of
vapor-liquid stream from the bottom tray must be specified before feeding the reboiler.
b.
Reboiler hydraulics shall be based upon a liquid level of 1’-0” above the tower bottom tangent
line and a Safety Factor of 1.2-1.3 should be used for exchanger friction and line losses.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 54 of 93
Beware of mean temperature difference suppression for pure fluids or low design MTD’s as a
result of an increase in the boiling medium pressure (normal operating level in the column
much higher than 1’-0”) and thus an increase in boiling temperature. The use of a flow
restriction valve in the inlet of the reboiler is not allowed.
c.
When steam is used as the heating medium, condensate control scheme shall be specified for
low-pressure steam. For medium and high-pressure steam, condensate control scheme shall
be considered as the preferred choice over steam flow control. For corrosive or fouling services,
such as sour water stripper and amine regenerator reboilers, a steam desuperheater located
downstream of the steam throttling valve (locate temperature sensing point 25 pipe diameters
from injection point and control 20°F above saturation) and steam flow control with a
condensate pot and associated condensate level control, shall be specified. When low
pressure steam is used in a steam flow control scheme, the condensing pressure can fall to a
level, which could compromise the ability for condensate removal. Therefore, care should be
exercised in the condensate system hydraulic design. The difference in elevation from the
reboiler condensate outlet flange to the condensate pot inlet shall be at least 2'-0" and the
balance line shall be 1” in diameter.
10.4. AIR FIN COOLER
10.4.1. Process Specification
a.
Dry bulb temperature to be used for air cooled exchanger sizing, is mentioned in document
EB020401-G00-FP14400P0001 BEDD (Basic Engineering Design Data). Indicate the air
design temperature.
b.
Designer shall specify the process outlet temperature at a minimum of 27°F above the design
dry bulb temperature. Indicate the preferred process outlet temperature if different.
c.
An overdesign will be considered for the air coolers:

Overhead air condensers
Greater of either 110 % of the estimated operating duty or the duty increase of the
corresponding reboiler.

Reactor effluent air cooler
10 % of air cooler duty or 5 % of feed/effluent exchange duty, whichever is greater.

Bottom air cooler
10 % of air cooler duty or 5 % of feed/bottom exchange duty, whichever is greater.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 55 of 93
10.4.2. Selection of Water Cooler or Air Cooler
a.
Where process considerations allow, air cooled heat exchange is preferred over water-cooled
heat exchange. If air cooling is preferred but process considerations require trim cooling,
indicate the temperature breakpoint between air and water cooling.
b.
Air cooling must be maximized, generally for cooling of the process fluids with temperature
above 140oF. If further cooling is required, cooling water should be used and the temperature at
the outlet of the air cooler can be reduced down to 130oF, according to designer judgment and
practice.
c.
Forced draft is preferred over induced draft fans
10.4.3. Miscellaneous
a.
In general, no temperature control device shall be installed on air coolers. When required to
help control the process fluid outlet temperature, the use of fan pitch shall be considered as the
preferred temperature control device.
b.
No winterizing is required.
c.
Air-cooled heat exchangers handing a high pour point process fluid shall be equipped with
heating coils under tube bundles
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 56 of 93
10.5. HEATERS
10.5.1. General
a.
Heater efficiencies shall be based on an economic analysis.
PDVSA resident engineer shall recommend waste heat recovery:

Steam generation with as high as possible pressure level or

Air preheat (in general, economics do not favour air preheat)
If air preheats is selected, then recuperative (stationary) type air preheater shall be specified.
b.
Oversizing will be considered as follows:
To take into account the risk of undersizing of heat recovery systems (i.e. feed-effluent,
feed-bottom), following oversizing is typically specified:

Feed heater: 10 % of heater duty or 5 % of feed/effluent exchange duty, whichever is
greater.

c.
Reboiler: 5 % of feed/bottom exchange or 10 % of reboiler duty, whichever is greater.
For hydrocracking heaters a higher turndown could be considered based on Licensor
recommendation.
d.
For multipass heaters the following will be specified:

Mixed phase: symmetrical arrangement of the passes and board temperature indicator on
each pass outlet.

Liquid phase: flow control valve with a minimum flow stopper on each pass inlet and board
temperature indicator on each pass outlet.

Vapour phase: symmetrical arrangement of the passes and board temperature indicator on
each pass outlet (except for box-type heaters: in this case see the manufacturer's
recommendations).
e.
Heater passes in services subject to coke formation (diesel and heavier products), shall have
automatic flow control with signal (and low flow alarm) to the control room. Pass control
valves should have limit stops to maintain 25% of normal flow. Manifolds shall be sized so that
the dynamic head in the manifold at the point of maximum velocity is not more than 5% of the
individual pressure.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
f.
Page 57 of 93
An automatic shutdown system shall be specified in the event of:

Low flow through the heater’s tubes. In case of multiple passes, the shutdown will be
activated when there is low-low flow detected by 2 out of 3 voting in each heater pass to be
confirmed by SIL verification study during detailed engineering.

High stack heater temperature.

A check valve or motor operated isolation valve shall be installed at the outlet of heaters
that operate above 1000 psig.
Note: The before specifications do not apply to the Slurry Load Furnace.
g.
Heaters in services subject to coke formation shall have precautions for steam-air decoking,
including decoking pot. Consortium shall provide a complete design of this system.
10.5.2. Burners
a.
Heaters shall be designed for gas burning only. Precautions for oil burnings are not required.
b.
Burners shall be operable when excess air reaches a minimum of 15 percent.
c.
The pilot natural gas supply system shall be independent of the burner supply system.
10.5.3. Miscellaneous
In services subject to coke formation, skin thermocouples shall be specified.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 58 of 93
10.6. PUMPS
10.6.1. Process Specification
a.
10 % oversizing will normally be specified. All centrifugal pumps shall normally be rated for
110 % of maximum process flow except for reflux and reboiler pumps, where 120 % shall be
used.
b.
The rated head is that required, at rated capacity, to overcome process pressure, line and
equipment pressure losses, static head, control valve pressure drop, and contingency. The
head contingency should be 5 psi for 10% differential head less than 5 psi; 10% differential
head when it is larger than 5 psi but smaller than 50 psi; 50 psi for 10% differential head more
than 50 psi.
c.
In estimating the shutoff pressure of centrifugal pumps for initial setting of downstream
equipment design conditions, reference to section 9 shall be made. The shutoff pressure shall
be rechecked when the certified characteristic curves of the selected pumps are available.
d.
Pump centreline is assumed to be 3 Ft above grade. Pump available NPSH shall be at least 2 ft
greater than the required NPSH of the pump.
10.6.2. Pump Type
a.
b.
Use of vertical pumps shall be avoided except following possible cases.

Sump pump; in sump pit or sump tank

Sundyne Pump; Integrally geared pump for small capacity and high head application

For the service of limited available NPSH; such as hot well pump of surface condenser

Intake pumps

Liquid Sulphur pumps installed in Sulphur pit.
Chemical injection pumps shall be of the reciprocating type and supplied by the vendors in
approved vendor list.
10.6.3. Driver
a.
Type of driver for critical service and extent of redundancy shall be as per Process/Licensor
requirement.
b.
Electrical motor drivers will be specified. For critical service, type of drive and extent of
redundancy to be defined process/Licensors requirement, drivers will be either steam turbines
or electrical motors connected to the electrical emergency network.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 59 of 93
10.6.4. Spare
a.
Most process pump services shall be specified with installed spares. However, intermittent
pump services may not be specified with installed spares. Spares in critical service (i.e. lube oil
pumps, condensate circulation in steam generation systems) shall be automatic start, with the
spare pump actuated by loss of discharge pressure or flow rate of the regular pump.
b.
Continuous service process pump will be specified with full spare.
c.
Common spares can be specified whenever appropriate for metering pumps.
10.6.5. Minimum Flow
a.
A minimum flow line shall be provided in all cases listed in Para 8.5 of this BEDG.
b.
In case minimum flow protection for a pump is required, two ARC valves - one per pump
(Yarway or equivalent) shall be specified for pipe diameters up to and including 6". For 8" and
larger the arrangements described in section 8, shall be considered, with the exception of high
head pump services, where ARC valves are the preferred choice, whatever the pipe diameter.
The provision of ARC valve shall not be considered if in contrast with Licensor’s requirement
(e.g. Licensor requirements as per P&IDs representation are binding) or Consortium operating
experience.
Unless otherwise specified per cent margin for motor selection should be in accordance with
the following table as per Job specification 00-FMPC-SP-0002.
Table 10.4: MOTOR NAME PLATE POWER AND MARGIN FOR RATING
MOTOR NAMEPLATE RATING (HP)
PERCENT OF RATED PUMP POWER
<30
125
30 to 75
115
>75
110
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 60 of 93
10.6.6. Miscellaneous
a.
Pumps in the process area shall be specified as per applicable API standard. However, pumps
in non-hazardous area or utility areas or included in vendor packages may be specified to
comply with ANSI or equivalent codes.
b.
Specifications for pumps shall require unsheltered, outdoor installation
c.
Single mechanical pump seals shall be specified except for specific services such as high
temperature, dirty service, light hydrocarbon, and environmentally hazardous or toxic service.
Refer to section 8.12 and 8.13 in this BEDG.
0
d.
Water cooling is preferred over air cooling for turbine exhaust steam condensers
e.
Bearing temperature and vibration monitoring equipment shall be specified for most large size
rotating equipment
f.
A proper drain line shall be provided for the removal of liquid remaining in the line between the
check valve and the main stop valve
g.
A warm-up bypass shall be provided for pumps which will operate at or above 300ºF, or if the
process fluid will solidify or vaporize at ambient temperature under normal operating pressure.
The bypass shall be sized for 2% of the normal flow or shall be 3/4” line min. The bypass shall
have a block valve followed by RO(Restriction Orifice) and shall be installed
discharge check and block valve unless otherwise indicated on P&ID.
around the pump
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 61 of 93
10.7. COMPRESSORS
10.7.1. Process Specification
a.
All other compressors shall normally be rated for 110 % of maximum process flow
b.
For some particular compressors services, overdesign will be specified as follows:

Make-up: minimum 10 % overcapacity

Recycle: minimum 20 % overcapacity on gas Quench
10.7.2. Type
a.
Centrifugal compressors shall be specified conforming to API Standard 617 whenever suitable.
Axial compressors shall be specified conforming to applicable sections of API Standard 617 for
large air blower services. Due to their high reliability, centrifugal and axial compressors shall
not be spared, but a spare rotor shall be specified. Driver selection shall be evaluated for each
application based upon process requirements, critical services, utilities and capital costs.
Motor drivers will be preferred.
Reciprocating compressor services shall be specified conforming to API Standard 618.
Screw compressors shall be specified conforming to API Standard 619
b.
Reciprocating compressors shall have manual-pneumatic suction valve unloaders for 0, 50 and
full load capacity. Three-step unloading is considered a minimum. The process may require
additional steps
c.
Reciprocating compressor services shall be specified with sufficient spare capacity to permit
maintenance of one machine while the plant remains on stream (in general 2 at 100% capacity
shall be specified, unless economic reasons dictate 3 at 50% to be more convenient).
Process gas temperature shall be limited to 250 °F (270°F max only with PDVSA approval) for
services with non-lubricated cylinders above 1000 PSIG pressure and more than 300
HP/cylinder.
d.
Screw compressors shall be specified in special instances when determined to be
advantageous over alternate choices. Due to their high reliability, screw compressors shall not
be spared, however a spare set of rotors shall be specified. Process gas temperature shall be
limited to 320°F (340°F max only with PDVSA approval).
e.
Air blowers and air compressors shall be specified in accordance with the refinery climatic
conditions.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 62 of 93
10.7.3. Driver
Electrical motor drivers will be specified. Critical service drivers will be either steam turbines
or electrical motors connected to the electrical emergency network.
10.7.4. Spare
For compressor types other than centrifugal, sparing philosophy can be 2 × 100 %, 3 × 50 %,
and 2 × 60 %.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 63 of 93
11. PIPING
Piping design conditions, including temperature and pressure shall conform to the requirements of
ASME B31.3
11.1. PIPING LAYOUTS
11.1.1. General
All piping shall be routed for the shortest and economical run. Layout shall be sufficient flexible to
offset thermal effects, in order to avoid:

Failure for excessive thermal expansion stress

Flanged joint leakage

Excessive loads to connected equipment
11.1.2. Support
a.
Generally all lines, inside battery limits of process units, shall be run on overhead pipe supports.
Exceptions are fire water lines and drain lines. New pipe racks shall have 15 percent of available
width unused for future lines
b.
Lines that cannot be run overhead shall be run on sleepers. Lines outside battery limits generally
shall be run at grade on sleepers except in areas adjacent to units where vehicular and
pedestrian access is required.
c.
All piping over 3 inches nominal diameter with operating temperature 121° C (250°F) and over
supported directly on concrete sleepers shall be provided with pipe shoes or saddles, with the
bottom of the pipe 75 mm (3 inches) above the top of supporting concrete. Pipe shoes and
saddles shall be of sufficient length to handle any possible line expansion.
d.
Bare pipes shall rest directly on structural steel provided a smooth round steel bar (1/2 or 3/4
inch diameter) be welded on structural steel in order to minimize contact area and corrosion.
e.
Where possible, all lines shall be run at levels that would enable them to be supported on
structural steel at a common elevation.
f.
All piping and accessories shall be arranged to facilitate support
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 64 of 93
11.1.3. Maintenance
a.
Piping arrangement shall be planned for ease of equipment removal for inspection, servicing
and/or maintenance
b.
Piping and structures shall be arranged to permit mobile lifting equipment to approach process
equipment and make lifts without obstruction
c.
Maintenance areas shall be clear of piping insofar as possible.
d.
Control valves, relief valves, etc. shall be accessible from platforms or grade and grouped at
main operating levels.
e.
Where a drain valve is required, Bottom Of Pipe (BOP) shall be above ground or base level so a
plug can be easily installed and/or removed. A 100 mm (4 inches) minimum clearance is
recommended.
f.
Bottom of pipe inside the trench shall be minimum 200mm above the bottom of the trench. 50
mm min shall be kept from trench wall. When flange joints are provided minimum clearance shall
be 150mm from bottom or edge of the trench to the edge of the flange
11.1.4. Miscellaneous
a.
Deflections over 1/2 inch are not permitted in all lines.
b.
All process and utility piping entering battery limits shall be provided with a block valve. Piping
leaving battery limits shall also be provided with block valve in accordance with the Battery Limit
Isolation agreed between CON and PDVSA
c.
Large, thin walled lines in non-–flammable service, such as cooling water lines, may be buried
and continuously supported on sand cushions.
d.
Buried pipe shall be externally coated, and provided with cathodic protection if required
e.
Piping insulated for “Hot Service” over 3 inches and larger nominal diameter shall not be
supported directly on structural steel or on a round smooth bar welded to structural steel, and
shall be provided with pipe shoes or saddles, with the bottom of the pipe 100 mm (4 inches)
above the top of supporting structural steel. Pipe shoes or saddles shall be sufficiently length to
handle any possible line expansion
f.
In process areas, specific elevations shall be selected for lines running north and south and other
specific elevations for lines running east and west. These elevations shall be used throughout
the unit, except where pockets must be avoided
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 65 of 93
11.2. DESIGN PRESSURE AND TEMPERATURES
a.
The design pressures and temperatures to be used as a basis for the design of piping systems
and the selection of standard piping material components shall be in accordance with the
requirements of the ASME Code B31.3, with the maximum operating conditions shown on the
applicable P&I Diagrams.
b.
Piping shall be designed for the maximum expected severe coincidental of conditions of pressure
and temperature during normal operation, reached on the basis of the following considerations:

Design pressure of the equipment to which it is connected.

Set pressure of the safety valve that protects the system.

Discharge piping of a centrifugal pump not protected by a safety valve shall be designed at
pump shut-off pressure (see section 9 for details):
All systems operating below atmospheric pressure, or connected to an equipment/system
designed for full vacuum, shall be designed for full vacuum as well.
c.
Particular care shall be given to the aboveground cooling water headers in case of circulation
pumps stop and consequent back drainage of return headers. As alternative, vacuum breakers
may be installed as required on the headers. All piping leaving the battery limits shall be designed
for a closed valve at the battery limits of destination plant or off site installation.
d.
The design pressure shall apply from the source to the last valve before entering equipment at a
lower pressure.
11.3. DESIGN DETAILS
11.3.1. Line and Connection Sizes
Allowable pipe sizes in inches are: 1/2, 3/4, 1, 1 1/2, 2, 3, 4, 6, 8, 10, 12, 16, 20, 24 and larger, in
2-inch increments for interconnection piping, except for uncommon line size such as 26 inches
and for other piping 6-inch increment for pipe size larger than 24 inches shall be observed. The
requirement is observed to the practical extent. For some technical reason or nominated by
Process Licensor, intermediate pipe size may as well be selected. In this case, Consortium
should ask PDVSA for approval.
In general, the minimum pipe sizes shall be as follows,

1/2 inch for utility lines

1 inch for process lines

no size limitations for instrument connections and steam tracing lines

4 inches for underground sewer lines

1 1/2 inches for slurry lines and other than sewer underground lines.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 66 of 93
11.3.2. Material Specification Changes
a.
When a piping system of one material Line Spec is connected to a piping system of a higher
rated material Line Spec, the connecting piping system shall be constructed of the higher rated
material Line Spec up to and including the first valve in the connecting piping system.

The higher rated material Line Spec shall be used up to and including the valve on the
bypass around equipment or pressure reducing valves.

b.
Block valves after the reducing valves shall be of the higher rated material Line Spec.
Where vessels have higher design ratings than the connecting lines, the valves at the vessels
shall equal the pressure rating of the vessels if the valves are or can be normally closed during
operation.
c.
Drilled holes in orifice flanges shall be upward in gas or vapor lines, and lateral in liquid lines.
Where these orientations are not applicable for spacing reasons, alternative orientation, as
shown on Job Standard 00-FPIP-SS-0001, is acceptable.
11.3.3. Flanges
The use of flanges in piping shall be limited to connections at flanged equipment, valves and
appurtenances as indicated on P&I diagrams.
Flanges shall also be provided in cases such as:

Where frequent dismantling of piping is required.

Where plastic, non–metallic or internally coated piping systems cannot be welded or
otherwise joined except by flanges.

To provide clearance for dismantling of equipment such as pumps, compressors, reactors,
etc.

Where it is not permitted to fabricate welding pipe.

Where it is not feasible to weld piping sections of dissimilar materials, e.g. Carbon Steel to
Cast Iron, Carbon Steel to FRP, etc.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 67 of 93
11.3.4. Valves
a.
Valve Type
Manually operated valves shall be selected based on their properties as described below. Valves
shall be provided of the type and number shown on the P&I diagrams

Gate Valves
Gate valves are used for services where throttling adjustment is not required during normal
operation, generally. Gate valves are used for bypass lines for control valves at the diameter
equal and bigger than 8”.
Valve size for cooling water service is up to 8”.

Globe Valves
Globe valves are used for lines requiring manual control, but globe valves in 3 inches and
larger shall be used only when throttling is required. The following services will require globe
valves:

•
By-pass lines for control valves (diameter up to 6”)
•
Where throttling is required globe valve in size 3 inches and larger shall be used.
•
Small bypass valve for main gate valve
•
In warm-up line on pumps discharge (refer to section 10 for provision details)
•
PSV bypass, where indicated on P&IDs if used as manual depressurisation lines.
•
Any other services as specified by Licensors on unit P&IDs.
•
Cooling water service (return line) for diameters up to 8”.
Needle Valves
Needle Valves are used where manual control of a small quantity is required.

Check Valves
•
Check valves are provided on the discharge side of pumps and compressors.
•
Inert gas lines for seal, purging, vacuum break and pressurizing shall have a check
valve.
•
Utility lines leading to the process line shall have a check valve for each line.
•
However, utility lines, which are used only during shutdown maintenance, will each have
a spectacle blind with a check valve.
•
Silent no-slam and other requirements shall be indicated on P&ID, following licensor
requirement.
•
Check valves shall be suitable for installation in horizontal or vertical lines where a
reversal of flow may occur.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001

Page 68 of 93
Butterfly Valves
Butterfly valves are used for the following gas and water services, taking into consideration
its properties for less tight shut-off and lower differential pressure:
•
Liquid and gas services for low differential pressure
•
Cooling water, sea water, utility water, drinking water, demineralised water, and
desalinated water services for diameters at 10” and larger

Ball Valves
Ball valves are applied for the tight shut-off services when operating temperature is within
acceptable limits;
•
LPG service
•
Fuel gas service
•
In lieu of gate valves for services where solids may collect to prevent de-seating of the
wedge.

Angle Valves
Angle valves are used for high differential pressure service.

Electrical-motor operated Valves
Electrical-motor operated valves are applied at compressor suction and discharge.
Face–to–face dimensions of gate, globe, check, ball, and plug valves shall be in accordance with
ASME B16.10.
Block valves shall in general be gate, ball, and butterfly or plug valves. Plug or ball valves shall
be used (when operating temperature is within acceptable limits) in lieu of gate valves for
services where solids may collect to prevent the seating of the wedge
b.
Valve Arrange

Double block valve and bleeder installations shall be provided as shown on the P&I
diagrams where necessary to avoid product contamination, or a hazardous condition.

The valve for which bypasses are to be furnished shall be indicated on the applicable P&I
Diagrams.

Integral valve bypass shall not be used unless absolutely required due to design limitations.
If used, it shall be globe valves only.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
c.
Page 69 of 93
Miscellaneous

The bypass valve and the related bypass piping shall be of the same piping class as the
principal valve.

Stem positions of all valves shall be indicated on the drawings, preferably not below the
horizontal.

Pipelines containing hazardous solutions (i.e. acids, caustic, etc.) shall not have valve stems
below the horizontal.

Manual gear actuators shall be supplied for gate and globe valves (which are operated more
than four times a year), ball and plug valves, and fire–safe butterfly valves
11.3.5. Blinds
a.
Blinds shall be supplied only to the extent required for normal operations and as shown on the
P&I diagrams.
b.
Blinds (spacers and spectacles) shall normally be installed on all process lines at battery limits
and where required to facilitate testing, inspections or maintenance of equipment, in particular in
case of vessel entry.
c.
Show all spectacle blinds, steamout, sample connections, vents and drains, manual vents, all
injection points such as chemicals, flushing oil etc.
11.3.6. Sampling System
Sampling system details shall be in accordance with Licensors and Consortium standard
for each unit. See also symbology P&ID for further details
11.3.7. Flame Arrestors
Flame arrestors shall be provided for the following lines in order to prevent propagation
of flame into equipment:
 Vent line from tanks containing inflammable material
 Off gas line connected to fire box to be incinerated.
11.3.8. Silencers
Silencers are usually provided for following locations.
 Steam exhaust line to atmosphere
 Compressed air line exhausted to atmosphere
 Any non-hazardous process vent (i.e. Regeneration Loop vent in CCR unit)
 Evacuation or start-up ejectors discharge line
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 70 of 93
11.3.9. Battery Limit
See Job Specification 00-FMGM-SP-0001
The following instrumentation shall be installed at the Unit B.L, in addition to local pressure
indication
Flowmeter
Pressure
Temperature
(Remote)
(Remote)
(Remote)
Steam Supply Lines
X
X
X
BFW Supply Lines
X
X
Cooling Water Supply Lines
X
X
Cooling Water Return Lines
X
Demineralized Water Supply Lines
X
Fuel Gas Supply Lines
X
X
X
Instrument Air Supply Lines
X
X
X
X
X
X
Recovered Condensate
(on recovery pumps discharge line)
Nitrogen
X
(only for the line connected as continuous process stream)
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 71 of 93
11.3.10. Block Valves around Equipment and Instrument
i.
Pumps, Turbine and Compressors
 Block valves shall be installed at the suction (inlet) and discharge (outlet) of pumps,
turbines and compressors, with the exception of submerged type pumps that have
discharge valves but no suction valves.
 The size of block valves shall be the same as the main line size.
 Air compressors and air blowers have no suction valves.
 For pumps on LPG service, block valve shall be of ball valve type.
Cooling Water Heat Exchanger
Cooling Water Heat Exchangers shall have block valves at the inlet and outlet of the
cooling water line. The types of block valves shall be as follows,
1"
TW
Note 1
CSO
ii.
3/4" Grade
3/4"
CWR
PG
Note 3
CWS
Note 2
Note:
1.
For line size in 8” or smaller, use globe valve. For line size in 10” or larger use butterfly
valve
2.
Drain shall be seized 3/4” for lines in 8” or smaller and 1” for lines in 10” or larger.
3.
For line size in 8” or smaller, use gate valve. For line size in 10” or large use butterfly
valve
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
iii.
Page 72 of 93
Control Valves
a.
Automatic control valves shall be furnished with block valves for isolation and a by-pass valve
for hand control, except for the following cases:






Where a by-pass would involve a risk to safety
Where manual control of the process cannot be mastered
Where realization is not possible because of dampers and three-way valves
Where control is used rarely or intermittently
Where a control system can be repaired without plant shutdown
Where specified on Licensor P&ID.
Block valves shall have the same size of the main process line
b.
Gate valves shall be used as block valves.
c.
The block valves and by-pass valve for the control valve assembly shall be sized in accordance
with the symbology EB020401-G00-DP20800P0016
0
Where piping is expanded after a control valve assembly (e.g., flashing condition), the block
valve downstream of the control valve shall be equal to the expanded downstream piping.
d.
Unless differently specified by Licensors on P&IDs or in valve data sheet, all the control valves
without by-pass shall be specified with a hand wheel.
Reducer, if required
Hand Wheel
3/4"
FC or FO
3/4"
3/4
Reducer, if required
Without bypass
Gate or Globe Valve
Note:
In case that control valve without bypass is connected with interlock system, no hand wheel is
provided.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
iv.
Page 73 of 93
Flow Meters
The following types of flow meters shall have block valves and a bypass valve of the gate type,
the size of which is the same as that of the main line.

Rotameter

Turbine Meter

Positive Displacement Flowmeter
Around flow meters
or
Turbine
PD
PDI
Calibration
Connection (same size as main pipe)
FT
3/4"
3/4"
STR
3/4"
3/4"
Flow straightener
for turbine meter
v.
Same Size as
Main Pipe
Safety Valves
a.
Valve arrangement and “Car Seal Open/Close (CSO/CSC)” requirement shall be indicated on
P&ID per valve arrangement with mechanical interlock as shown in Note-4 of General Notes,
Symbols ans Legend (DWG. No. EB020401-G00-DP20800P0002) the detail of mechanical
interlock system to be finalized in detailed engineering.
b.
Spare PSV will normally be specified with the following exceptions.

Spared equipment that can be taken out of service without affecting the plant operation. In
this case, the block valve on the PSV inlet line shall not be provided.

Non-spared equipment that can be blocked-in and needs to be protected for fire only, but
are protected by another PSV during normal operations. In this case, the block valve on the
PSV inlet line shall be provided.

Thermal relief valves. In this case, the block valve on the thermal relief valve inlet line shall
be provided.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 74 of 93
c.
Isolating outlet block valve will not be specified if discharge is routed to atmosphere.
d.
When two relieving devices are installed with block valves on the inlet and outlet piping, the
block valves shall be interlocked to ensure that the equipment being protected will never be
isolated from the relieving device per valve arrangement with mechanical interlock as shown in
Note 4 of General Notes, Symbols and Legend (DWG. No. EB020401-G00-DP20800P0002)
0
the detail of mechanical interlock system to be finalized in detailed engineering.
e.
The size of bypass lines shall be as follows,
Safety Valve Inlet Line
Bypass Line
4” and smaller
1 1/2”
6” and larger
2”
11.3.11. Vents and Drains
Vents and drains are classified as either open or closed.
a.
Closed System
Closed vents and drains are connected to the flare system, blow down system, amine recovery
system and sour water recovery system in order to minimize the release of explosive and toxic
materials to the atmosphere.
These vents and drains shall be applied for equipment where venting and draining is necessary
during operation or when hazardous or flammable products are drained or vented during
start-up and shutdown.
b.
Open System
Open vents and drains, on the other hand, are exhausted to the atmosphere and recovered
with oily sewer. This type of vent and drain is to be utilized during start-up and shutdown steam
out operations or during normal operations in case non-hazardous or non-flammable products
needs to vented or drained.
For more details, refer to document EB020401-G00-DP14500T0006 Drainage Basic Design.
In case of provision for vents and drains, their size and methods of installation are given
according to the type of equipment, pressure rating and fluid services. For the types of
equipment, towers, drums, heat exchangers, fin fan coolers pumps and piping are taken into
consideration.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 75 of 93
Light Hydrocarbons
Surge Pond
0
Atmosphere
Non-Contaminated
Strom Water
Chemical Sewer
Oily Sewer
Sour Water Slop
X
Amine Slop
Light Slop
Blowdown System
X
Heavy Slop
Blowdown System
Flare
The classification of vent and drain is defined as follows;
X
(Hydrogen, Naphtha, Fuel Gas, Gas Oil)
(Note1,2)
Heavy Hydrocarbons
X
X
X
(LVGO, HVGO, AR, VR)
(Note1,2)
Steam
X
X
Steam Condensate
X
(Note2)
X
Oily Water and Oily Contaminants
(Note2)
X
Amine
X
X
(Note3)
Chemical (Caustic / Acid)
X
X
Sour Water
X
X
(Note3)
Contaminated Strom Sewer
X
Sour Water Slop System (Note4)
Note:
1.
Slop blowdown header is routed via trenched pipe to Lighter or Heavy Slop Oil Drum
2.
In principle, drain line from the vessel shall be connected to the Light or Heavy Slop Blowdown system. During the final
phase of steam-out, the steam condensate can be routed to the nearby oily sewer funnel.
3.
Amine sump header is routed via trenched pipe to Amine Sump Drum. During the final phase of steam-out, the steam
condensate can be routed to the nearby oily sewer funnel.
4.
To SWS Unit for Reprocessing
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 76 of 93
Vents and drains for equipment and piping are as follows,
a.
Towers and Drums
Vents shall be installed at the top of towers and drums. These vents can be installed on their
associated piping which is the highest point. Location of vents shall be followed indication on
P&ID. Vents at the top of drums shall be open vents, unless otherwise indicated on P&ID.
Drains shall be installed at the bottom of towers and reboiler drains shall be connected to the
tower drain piping. These drains can be installed on towers or their associated piping.
Vents and drains shall be provided with blind flange in accordance with following:

Minimum Size
See Table 10.1 in Section 10.1 VESSELS
Note: The above size is applied unless otherwise indicated on P&ID or equipment data sheet

Installation
Open System
Closed System
For 600# and lower
Single Valve w/blind or cap
For 900# and higher
Double Valve w/blind or cap
For all Rating
Single Valve w/bleeder
Note: Bleeder for closed vent (or drain) can be utilized as open vent (or drain)
Typical Installation to refer to Piping detail Standard 00-FPIP-SS-0001
b.
Heat Exchangers
Vents shall be provided in the highest pocket of heat exchangers and/or inlet or outlet piping in
order to prevent accumulation of non-condensable vapor and shall be open vents principally,
unless otherwise indicated on P&ID.
Drains shall be provided in the lowest pocket of heat exchangers and/or inlet or outlet line for
drainage of liquid in the exchangers during shutdown and shall be open drains principally,
unless otherwise indicated on P&ID.


Minimum Size
Rating
Vent Size
Drain Size
Lower than 900#
3/4”
1”
900# and higher
1”
1”
Installation
Open System
Closed System
For 600# and lower
Single Valve w/blind or cap
For 900# and higher
Double Valve w/blind or cap
For all Rating
Single Valve w/bleeder
Note: Bleeder for closed vent (or drain) can be utilized as open vent (or drain)
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
c.
Page 77 of 93
Air Coolers
Vents shall be provided in the highest pocket of fin fan coolers in order to prevent accumulation
of non-condensable vapor and shall be open vents principally, unless otherwise indicated on
P&ID. Drains shall be provided in the lowest pocket of fin fan coolers for drainage of liquid in the
exchangers during shutdown and shall be open drains, unless otherwise indicated on P&ID.

Minimum Size
Vent Size: 1”

Drain Size: 1-1/2”
Installation
Open System
Closed System
For 600# and lower
Single Valve w/blind or cap
For 900# and higher
Double Valve w/blind or cap
For all Rating
Single Valve w/bleeder
Note: Bleeder for closed vent (or drain) can be utilized as open vent (or drain)
d.
Pumps
Vents shall be provided at pump discharge lines if pump casing vents are not provided. Open
vents shall be applied in principle, unless otherwise indicated on P&ID.
Drains shall be provided at pump casing. Drainage of liquid in discharge line shall be drained
out through pump casing principle, unless otherwise indicated on P&ID.


Minimum Size
Rating
Vent Size
Drain Size
Lower than 900#
3/4”
1”
900# and higher
1”
1”
Installation
Open System
Closed System
For 600# and lower
Single Valve w/blind or cap
For 900# and higher
Double Valve w/blind or cap
For all Rating
Single Valve w/bleeder
Note: Bleeder for closed vent (or drain) can be utilized as open vent (or drain)
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 78 of 93
Typical Installation is shown as follows,
B.V.
OS
OS
NOTE 1
Note: Refer to drain classification in general description of 11.3.11
Non-Hydrocarbon Drain for Pumps
600# and Lower
900# and Higher
B.V.
B.V.
*
*: CS or
OS or
NS
*
*: CS or
OS or
NS
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
e.
Page 79 of 93
Piping
Two types of vents are normally present:
1. Process Vent (e.g. they are operated during normal operations/maintenance)
2. Hydrostatic Test Vent
Process vents are shown on P&ID while hydrostatic vents are not shown, however both will be
indicated in the Isometric Drawings
Process vents will be provided with valves, while hydrostatic vents will be sealed after testing
with a welded cap.
Process vents and drains shall be open, where necessary. Closed vents and drains are of
special use during start-up, shutdown, etc. and their sizes shall be specified respectively on P&I
Diagrams.
The following general requirement shall be applied:

Unless they serve as drains for large equipment (exchangers, etc.), process drains shall:
- Be minimum size and conform to individual Piping Materials and Job Specification
00-FPIP-SS-0001 “A/G PIPING STANDARDS”.
- Valved drains open to atmosphere in hydrocarbon, hydrogen, steam, or chemical
service shall have a cap, plug, or blind flange on atmospheric side of valve. Socketweld
end drain valves shall have a short pipe nipple with one end threaded and capped.
- Drains located below grade on underground lines shall consist of a thread-o-let, nipple,
and valve.

High points of piping shall have vents as required for hydrostatic testing in accordance with
the following:
- Steam lines that require hydrostatic testing shall have NPS 1-threaded valves on
schedule 160 nipples welded in line. After initial test, nipple shall be cut to 3/4 inch in
length and sealed with a weld cap
- Vents on other lines shall be minimum size, and conform to Piping Materials and Job
Specification 00-FPIP-SS-0001 “A/G PIPING STANDARDS”

If possible, vent connections shall be located in accessible locations adjacent to platforms
or structural members.

Piping systems shall have drain valves at all low points
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 80 of 93
Size and Installation shall be as follows,
Standard Vent Connection
Flange Class
600# AND LOWER
900# AND HIGHER
FOR
NOTE1
PROCESS
USE
NOTE1
FOR
HYDROSTATIC
TEST
NOTE2
NOTE2
3/4”
3/4”
Standard Drain Connection
Flange Class
FOR
600# AND LOWER
900# AND HIGHER
NOTE1
PROCESS
USE
Note:
1)
Cap or Blind Flange as per Piping Class requirements
2)
Screwed Cap shall be seal welded after hydrostatic test
NOTE1
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 81 of 93
11.3.12. Purge Connection to Process Line
For the utility line connection to the process line, valve arrangement shall be applied as
follow
a.
Fuel Gas Steam and Nitrogen
min
FG
utility spec
process spec
Note:
Process spec to be shifted upstream of manual isolation valve if process side piping
specification is rated higher than utility side piping specification
b.
Flushing Oil
min
FO
utility spec
process spec
Note:
Process spec to be shifted upstream of manual globe valve if process side piping specification
is rated higher than utility side piping specification. Positive isolation through manual isolation
valve shall be verified upstream in the FO supply line; if such valve is not present, an additional
manual isolation valve shall be added upstream of the globe valve
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 82 of 93
11.3.13. Warming-up and pressure equalizing bypass of steam lines
For 12” and larger or 600# and higher for steam lines, provide 1” bypass with globe valve
around B.L. valves for warming-up and pressure equalizing.
11.3.14. Valve Size for Suction and Discharge Lines of Pumps
The size of valves installed in the suction and discharge lines of pumps shall be the same as
the main line size.
11.3.15. Steam inlet line to steam turbine
Spool piece for initial flushing is installed at steam inlet line to steam turbine.
Warning-up line discharged to atmosphere to be foreseen.
11.3.16. Pressure gauge for Pumps
Pressure gauges shall be provided at the discharge lines only for all centrifugal pumps.
11.3.17. Utility Stations
a.
Utility stations consisting of LP steam, plant air, nitrogen and utility water lines shall be
provided for the appropriate equipment and following points.
All over the unit, with an approximate 30m span and close to heat exchangers, towers
and vessels manholes with 10 meters or above elevation.
b.
Connections between utility stations and equipment shall be done with temporary hose.
c.
The size of each utility line shall be 1 inch, and the gate valve with hose connection
shall be provided for all services.
d.
For LP steam, additional connection shall be supplied with screwed connection and
permanent hose for fire abatement purposes.
11.3.18. Sampling Connections
In principle, closed sampling system shall be provided, whose sample bypass shall be returned
to process line and exhaust gas shall be vented to flare.
All sampling points shall be shown on P&ID.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 83 of 93
11.3.19. Insulation and Steam Tracing
In principle, the lines and instruments of the following services shall have steam tracing.
 Gas line in which any condensing is prohibited.
 Liquid line with high pour point fluid.
11.3.20. Double Block Valve for On-stream Maintenance
To ensure on-stream maintenance, double block valves should be applied for equipment and
instrument which subject to on-stream maintenance for the following services,

Toxic and H2S lethal service (Gas containing H2S in excess of 1%)

Hydrocarbon and hydrogen service with ASME Rating Class 600# and higher

Others (non-flammable) service with ASME Rating Class 900# and higher
Note: Following subject to on-stream maintenance,
- All equipment that need to be isolated during operation
- Control valve with bypass
- Relief valve with a spare (inlet only)
- Instrument that need to be isolated during operation (level, flow, pressure)
11.4. LINE SIZING CRITERIA
Lines sized by Licensors shall be checked with the requirements of PDVSA. Any resulting
deviation shall be promptly transmitted to Licensors/PDVSA for concurrence.
General recommendations are as follows,
a.
Lines shall be sized for the most economical overall design and according to “PDVSA –Manual de
Ingenieria de Diseño, Volumen 13-III, Section: Guidelines 90616.1.024- Dimensionamiento de
Tuberias” and PDVSA-Manual de Ingenieria de Diseño, Volumen 13-III, Tuberias y Oleoductos,
Section “L-TP-1.5 Calculos Hidraulicos de Tubería”.
b.
Effects of line loss, pump characteristics, and heat exchanger and control valve pressure drops
shall be considered. Final design shall be based on largest total pressure drop consistent with
economy, ease of operation, and noise abatement and according to “PDVSA – Manual de
Ingenieria de Diseño, Volumen 13-III, Tuberias y Oleoductos,
c.
Section Guidelines 90616.1.024- Dimensionamiento de Tuberias” and PDVSA-Manual de
Ingenieria de Diseño, Volumen 13-III, Section: L-TP-1.5 Calculos Hidráulicos de Tubería”.
d.
Unless otherwise limited, maximum line velocity shall be governed by such factors as erosion and
noise.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 84 of 93
Velocities of fluids inside of pipe and pressure drop shall be according to: “PDVSA-Manual de
Ingenieria de Diseño, Volumen 13-III, Tuberias y Oleoductos, Section: – Guidelines
90616.1.024- Dimensionamiento de Tuberias” and L-TP-1.5 Calculos Hidraulicos de Tubería”.
Piping within process units will be sized based on the rated flow case. The sizing criteria based
on the velocities and the pressure drop are as follows,
Service
Velocity
Pressure Drop
Boiling Liquid
< 0.3psi/100ft
Viscous Liquid(>30cP)
< 0.3psi /100ft
Pump Suction Lines
Pump Discharge Lines
1 to 2 psi/100ft
General
1 to 3 ft/sec
Self-venting
1 to 3 ft/sec
Gravity Flow
Pressure Service
Vapor/Gas Transfer Lines
Vacuum Service
Vacuum Service
Column Overhead Lines
𝑉𝑚𝑎𝑥 = 100√𝑆𝑉
SV: Specific Volume
𝑉𝑚𝑎𝑥 = 100√𝑆𝑉
SV: Specific Volume
0.2 to 2 psi/100ft
(to suit available)
less than 10% of
absolute pressure
less than 10% of
absolute pressure
Atm/Moderate Pressure
< 0.5 psi/100ft
Pressure > 200psi
< 2.0 psi/100ft
Vertical Thermosyphon Reboiler
Header
Utility Lines
< 3ft/sec
< 0.5 ft-liquid/100ft
less than 5% of operating
gauge pressure
Branch
Compressor Suction and Discharge
Inlet
Relief Valve
(Note 1)
Outlet
(for Conventional Type)
Outlet
(for Balanced Type)
total pressure drop
less than 1% of
absolute pressure
total pressure drop
less than 3% of
set gauge pressure
Back Pressure
less than 10% of
set gauge pressure
Back Pressure
less than 30% of
set gauge pressure
Note:
1. Refer to document 92-FPRO-BD-0006 Flare System Design Basis Memorandum for
additional design criteria
11.5. PIPING SERVICE IDENTIFICATION
See symbology P&ID
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 85 of 93
12. INSTRUMENTATION AND CONTROL
a.
0
Reference Documents for the Instrumentation design and installation are represented by the
CONSORTIUM Job Specifications, documents numbers: 00-FINS-SP-0001 ÷ 0018,
EB020401-G00-FI11400T0001, EB020401-G00-FI14100T0001 and EB020401-G00-FI30100T001.
b.
Control Systems and Instrumentation for the Atmospheric and Vacuum Distillation Revamp,
including equipment package Instrumentations, shall be specified as 4 to 20 mA HART Protocol.
For the new plants, the criteria defined by AIT RELP will be taken. Fieldbus protocol is to be applied
to the practical max extent.
c.
All the instruments shall be specified in agreement with the applicable area classification and
resistant to marine atmosphere.
d.
All the instrumentation, as far as possible, will have to be of repairable type; the equipment of
disposable type will not have to be specified.
e.
Project will contemplate a new control room that includes new facilities of this project.
f.
Designer shall specify continuous stream analyzers where required for process monitoring and
control. Designer shall describe his suggested control strategy to insure optimum and safe plant
operations.
g.
Designer shall describe his suggested Distributed Control System (DCS) to insure optimum and
safe plant operations.
h.
Additional control devices / systems will be specified based on a risk analysis of the control function
and the location propose.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 86 of 93
12.1. FLOW INSTRUMENTS
a.
Calibration ranges for differential instruments for flow measurement shall be in inches of water.
b.
Use 300 # connection as a minimum on orifice plates flanges.
c.
Orifice plates will be fabricated in accordance with ISO-5167, generally 316 stainless steel as
minimum 304 Stainless Steel, Monel, Hastelloy or other suitable material will be used to resist the
fluid corrosion and erosion properties.
d.
The minimum rating will be 300# ANSI, and will be accordance with ANSI B16.5, ANSI B16.36,
ANSI B 46.1 and ISO 5167. The flange thickness will not be less than 38 mm (1.5 in.) and the
flange bore will match the internal diameter of the piping schedule. Spreader bolts (jack screws)
will be provided in flanges, in diametrically opposing directions.
For sour service, connections shall be in accordance with NACE Standard MR 0103-2005.
The flow primary element sizing will be performed with a software program based on:

ISO-5167/ASME

SPINK precise calculation

AGA 3 to 8
e.
Glass tube rotameters shall not be used. On all applications, metal tube rotameters will be used.
f.
Rotameters will be installed with by-passes in order to facilitate maintenance without shutting
down the process.
g.
Other type of instruments, such as positive displacement, turbine type meters, electromagnetic,
vortex, ultrasonic, Coriolis may be used where the use thereof is strictly required by process
conditions.
h.
For low differential pressure drops, averaging type of pitot tubes may be used
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 87 of 93
12.2. LEVEL INSTRUMENTS
a.
Use connection size 2”, 300 # as minimum on external displacement type level instrument.
b.
Level gauges will generally be of the reflex type, except in the following services, when
transparent gauge glasses will be specified:
c.

Interface between two liquids

Colored liquids with specific gravities of 0.9 or higher

Liquids containing gum, sediment or other solid particles which cling to the glass

Glasses requiring mica shields

Liquids not easily visible or tend to be opaque
Level indicators with magnetic coupling will not be used on applications where agitation is present
into the vessel or where suspended solids are present in the process liquids.
d.
Level bridles will be used for installation of multiple instruments on the same vessel. Level
transmitter used for shutdown purposes will have separate vessel connections.
e.
The preferred primary sensing element will be a differential pressure (d/p) cell operating on the
hydrostatic head pressure principle. They will be complete with range elevation/suppression
facilities.
f.
Bubble type level applications using d/p cells may be used on sumps and corrosive fluid services.
g.
Displacers on process fluids operating at more than 400°F will be provided with cooling fins.
h.
External cage connection size will be NPS 2" 300# RF, unless the vessel connection specification
requires a higher rating.
i.
When the level measurement is wired to the SIS system, the transmitter will be independent of any
other level measuring device installed on the same vessel/tank/sump
j.
For special applications, nuclear or ultrasonic level instruments may be considered but with the
authorization of PDVSA
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 88 of 93
12.3. PRESSURE INSTRUMENTS
a.
A local pressure gage shall be installed on top of each vessel.
A board mounted temperature
indicator shall be installed near the bottom of each vessel.
b.
Pressure gauges installed above the process connection on hot fluids (steam, condensable gases,
hot liquids) may be protected by a pigtail (siphon).
c.
Pressure Instrument installed at pulsating services such as reciprocating equipment will be
provided with snubbers to dampen the vibration and provide a real measurement.
d.
All pressure instruments to be installed on slurry, viscous (>10cSt) fluids with suspended solids,
toxic and corrosive services, will be provided with diaphragm seals. The diaphragm seal will be
easily cleanable type. Where capillaries are required the capillary will be stainless steel complete
with PVC covered stainless steel bendable armour.
e.
The pressure instrument will be capable of withstanding an overpressure 1.5 times the maximum
operating pressure, without producing any damage.
f.
Wherever a pressure or temperature transmitter used for control is installed, provide a pressure
gage or a local temperature indicator for calibration purposes.
For critical services, a board
mounted pressure or temperature indicator shall be supplied.
12.4. TEMPERATURE INSTRUMENTS
a.
When a signal is transmitted to DCS, the thermocouple/RTD shall be provided with a remote
temperature transmitter or multiplexer.
b.
Temperature measurement points for process monitoring and control shall be specified and
represented on the Piping and Instrument Diagram with item numbers. Thermowells for each heat
exchanger shell shall be specified.
c.
ISA type K thermocouples shall be specified for general services
d.
Thermowells in temperatures greater than 1100°F and those installed in large vacant spaces such
as radiant sections of furnaces, will be inserted from the top of the equipment rather than the side,
in order to prevent sagging of the thermowell due to high temperatures.
e.
Use class 150# flanges as a minimum for thermowells.
f.
Head mounted transmitters shall normally be used. Separate transmitters shall be used
when operating temperature is above 570 degF.
g.
For process furnaces, each tube-surface temperature measurement shall be done by a main skin
point, which signal go to DCS, and a reference skin point, which is available just on field.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 89 of 93
12.5. CONTROL VALVES
a.
Use 300 # connection as a minimum on control valves flanges.
b.
Control valves shall be sized such that the valve capacity is approximately 1.25 times the
maximum calculated flow capacity.
c.
Control valve sizing pressure drops will be determined as follows:

For flowrates less than 750 gpm and a system pressure drop (excluding the control valve) of
less than 250 psi, the control valve sizing pressure drop shall be equal to 15 psi or 25 % of the
total system pressure drop (including the control valve), whichever is greater.

For flow rates outside the above ranges, the control valve sizing pressure drop shall be equal
to 25 psi or 20 % of the total system pressure drop (including the control valve), whichever is
greater
d.
Control valves will be sized for the minimum, normal and maximum operating conditions to ensure
the valve will operate between 17 and 90 percent opening.
e.
Valve trims will be selected to enable operation without any cavitation.
f.
In general the limit for noise generated by control valves shall be 85dBA or less, as measured at a
distance of 1 meter from the valve for continuous flow condition
g.
Valves used on emergency shut off service applications will be dedicated solely to that service
only and will not be used for normal process control purposes.
h.
The valve trim material will be 316 stainless steel as minimum required. Other materials will be
considered to suit the fluid erosion and corrosion properties. Stellited or harder trim material will be
used on:
i.
j.

Flashing fluids

Fluids with entrained solids

Pressure drops over 145 psig.
Pneumatic diaphragm or piston type actuator will be used to ensure that the valve:

Operates correctly under all specified operating conditions.

Withstands a pressure drop equal to the maximum upstream pressure.

Speed of response complies with the process operational requirements.
The use of electro-hydraulic, electric, hydraulic or digital actuators will be considered only in cases
where pneumatic diaphragms or piston actuators will not work correctly.
k.
All control valves will be fitted with positioners.
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 90 of 93
12.6. PRESSURE RELIEF VALVES
a.
The relief system shall be designed in accordance with API RP-520 and API RP-521.
b.
A single operating pressure relief valve (PSV) will be specified for each service unless:

Multiple valves are necessary because the required capacity cannot be provided in a single
valve.

Dual valves are required in accordance with the American Society of Mechanical Engineers
(ASME) boiler and pressure vessel code, section I.
c.
For steam service governed by ASME Boiler and Pressure Vessel Code, Section I, the use of inlet
or outlet block valves is not permitted. Isolating inlet and outlet block valves will normally not be
specified for non-spared PSV.
For spared valves, block valves should be CSC(inlet)/CSO(outlet)
with mechanical interlock as shown in Note-4 of General Notes, Symbols and Legend(DWG. No.
EB020401-G00-DP20800T0002) the detail of mechanical interlock system to be finalized in
detailed engineering.
d.
Pressure relief valves are normally installed at an elevation sufficient to slope the outlet line
towards the main flare header without any pocket.
e.
When two relieving devices are installed with block valves on the inlet and outlet piping, the block
valves shall be interlocked to ensure that the equipment being protected will never be isolated
from the relieving device.
f.
Relief header shall be sized based on criteria included in document 92-FPRO-BD-0006 Flare
System design Basis Memorandum:
g.
Discharge piping on relieving devices venting to atmosphere will extend at least 3 meters above
any platform or working area located within 24.5 ft /7.5m) meters radius of the point of discharge.
The distance from a “working area” may be increased for the purpose of attenuation of exit noise,
if necessary. Atmospheric vent piping will be square cut across the end.
12.7. ALARMS AND SHUTDOWN DEVICES
a.
Alarms and shutdown devices will be specified where required for process, safety or equipment
protection considerations.
b.
Shutdown device connections will be independent from instrument connections.
c.
All safety devices are connected to one specific system (SIS type).
0
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 91 of 93
12.8. INSTRUMENT AIR SUPPLY
a.
The instrument air supply will be filtered and dried to a dew point of -85°F at 110 psig. In general,
the quality of the instrument air will meet the requirements of ISA S7.3, Quality Standard for
Instrument Air.
b.
Air supply piping to locally mounted instruments and local panels will conform to the piping
specification.
c.
Instrument air system should have sufficient capacity for 20 minutes operation to execute safe
shutdown .
12.9. INSTRUMENT ELECTRICAL POWER SUPPLY
a.
The preferred power supply for field instruments is 24 volts DC.
b.
Control systems such as DCS/SIS/F&G and other PLC systems, RTU systems, etc. will be
powered by 115 volts AC supplied from an un-interruptible power supply (UPS) system.
c.
The power system will be designed for 25% spare capacity.
d.
The main unregulated AC power supplies to instrumentation systems will be derived from the
essential services distribution system.
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 92 of 93
13. CIVIL ENGINEERING DESIGN
13.1. MEASUREMENT UNIT AND LANGUAGE
Unless otherwise noted, Metric System Unit shall be used, for drawings and Calculation Report.
Drawings
Calculation Report
Distances
millimeters
Elevations
meters
Loads
kg or metric tons(t)
Pressures
kg/cm2
Reinforcement bar diameter
inches
Distances
meters or millimeters
Elevations
meters
Loads
kg or metric tons(t)
Moments
kg-m, kg-cm or t-m
Pressures
kg/cm2 , kg/m2 or t/m2
Unit Weights
kg/m3 or t/m3
Wind Speed
km/h (kilometres/hour)
Reinforcement bar diameter
inches
13.2. SITE PREPARATION AND EARTHWORK
Refer to the following Consortium Job Specification /documents:
 FCIV-SP-0001 for site preparation and earthwork
 00-FCIV-SP-0004 Earthen dikes for storage tanks
13.3. ROAD DESIGN AND CONSTRUCTION
Refer to the Consortium Job Specification 00-FCIV-SP-0002
13.4. UNDERGROUND PIPING AND SURFACE DRAINAGE
Refer to the following Consortium Job Specification/documents:
 00-FCIV-SP-0003 for underground piping and surface drainage
 00-FCIV-SS-0001 for underground standard details
El Palito Refinery Expansion Project
Phase II
Document Title
Basic Engineering Design Guide
Document No.
EB020401-G00-FP14500P0001
Page 93 of 93
13.5. HVAC, PLUMBING AND SANITARY SERVICES
Refer to the following Consortium Job Specifications:
 97-YMEC-SP-0006 for design basis
 97-YMEC-SP-0007 for materials and construction
 97-YMEC-SP-0008 for factory acceptance test
 97-YMEC-SP-0009 for commissioning and performance test
 97-YMEC-SP-0010 for field inspection and test
13.6. DESIGN AND CONSTRUCTION BASIS FOR STRUCTURES
Refer to the following Consortium Job Specifications:
 00-FSTC-SP-0001 for design loads and load combinations
 00-FSTC-SP-0002 for design of blast resistant buildings
 00-FSTC-SP-0003 for design of reinforced concrete structures and foundations
 00-FSTC-SP-0004 for design of storage tank foundations
 00-FSTC-SP-0005 for construction of reinforced concrete structures and durability
 00-FSTC-SP-0006 for design of steel structures
 00-FSTC-SP-0007 for fabrication and erection of steel structures
 AIG-2009-IF-155 Geotechnical Onshore Consolidation Study for the Expansion
Project of El Palito Refinery, Final Report (Rev. 1)
 10-1209 Seismic Study associated to the Expansion Project of El Palito Refinery,
Final Report (version 1), CORAL 83, May 2010
 AJ-YCIV-SP-0001 for design of bridges
 97-TARQ-SP-0001 Design basis and facility description of buildings
 97-TARQ-SP-0002 General requirement for design and engineering of buildings
 97-TARQ-SP-0003 General requirements for materials and construction of buildings
13.7. FIREPROOFING
Refer to the Consortium Job Specification 00-FSTC-SP-0008
13.8. DIKE CAPACITY REQUIREMENT
In case of multiple tanks inside the dike, volumetric capacity of the dike area shall be not
less 1_1/2 times (150%) of the sum of each tank capacity in accordance with the
requirement in local regulation, LOPTYMAT.
Download