Uploaded by Hubert Phan

Assignment 3 LOPA

advertisement
School of Chemical and Biomedical Engineering
Division of Chemical and Biomolecular Engineering
Plant Safety
LOPA Analysis
Name:
Ong Ding Shan
Matric number:
U1920546E
Current Existing System
Figure 1 shows the selected operation that was used for analysis.
Figure 1 Solvent intermediate storage tank
A layer of protection analysis was done on a solvent intermediate storage tank targeting the potential overpressure of the vessel. In essence, this study
evaluates the functionality of current existing independent protection layers that reduces the likelihood of vessel rupture and proposes new implementations
to minimize the overall likelihood at greatest risk to be less than the target hazard of 3 × 10−5 per year. In the event of vessel rupture, the initial failure will
spread and the sudden release of flammable gas will result in potential fire balls and explosions, causing damages to lives and properties.
Some assumptions were made within the scope of this study.
-
Steam pressure control valve is periodically tested.
PSV is meant to proect the over pressurization of pipeline for trapped liquid expansion scenario.
Check valve maintained in accordance with manufacturer’s recommendations.
-
A vessel failure will result in a tear because the vessel is made from ductile carbon steel. (The maximum pressure the vessel can withstand is 3 barg.)
Table 1 shows the LOPA analysis done on the selected operation.
Scenario
Overpressure of a Solvent Intermediate Storage Tank leading to PV Energy Explosion/Deflagration of Flammable Liquid
Targeted
Frequency
3.0E-05
Calculated Frequency
4
5
2
6
8
9
10
BPCS Relief
Valve
Check
Valve
Discharge
Isolation
Block Valve
Unmitigated
Likelihood
0.1
1
0.1
1
1.0E-03
1
1
0.1
1
1.0E-02
1
2
3
Initiating Event
Description
Initiating Cause
Cause
Likelihood
Tank design
Fatality
BPCS Vent Valve
Short circuit causing
electrical signal from
level switch failing to
reach transfer pump
0.1
1
1
Clogging of Vent Line
0.1
1
1
Backflow of highpressure solvent steam
mixture causing
substantial overpressure
ratio
Build up of pressure
within the storage tank
due to lack of venting
7
Protective Layers
S/No.
1
1.1E-02
Table 1 LOPA analysis of unmitigated operation
The level switch protects the transfer pump by translating the level of the solvent in the tank to the operation of the transfer pump via an electrical signal. A
short circuit will cause the electrical signal to be jammed and the transfer pump to cease operation.
-
The initiating frequency of short circuit: 0.1/year.
Maximum pressure that the vessel can withstand without rupture is no greater than 3 barg, 50’C. The vessel contains no innate ability to rectify increasing
pressure hence it was attributed a factor of 1.
Probability of a person present was assumed to be at 100%, hence fatality was given a factor of 1.
Vent line relieves the pressure within the tank. The probability of it being clogged was assumed a conservative value of 0.1/year. In the second scenario, the
vent pipe was assumed to have failed, hence it has no credit.
Relief valve allows high pressured steam solvent mixture to return to the vessel. It does not relief pressure within the tank hence it was given a factor of 1.
Check valve prevents the backflow of steam solvent mixture back to the pump, thus preventing a build up of pressure in the tank. It has a probability of failure
of 0.1/year.
Discharge isolation block valve is kept open always, and thus does not mitigate the overpressure scenario, hence it was given a factor of 1.
References for the probability of failure in these scenarios were retrieved from lecture slides and notes.
Modified System
Figure 2 shows the selected operation that was modified.
Figure 2: Modified Solvent intermediate storage tank
Table 2 shows the LOPA analysis done on the modified operation.
Scenario
Targeted
Frequency
S/No.
1
2
Overpressure of a Solvent Intermediate Storage Tank leading to PV Energy Explosion/Deflagration of Flammable Liquid
3.0E-05
Calculated Frequency
4
5
Cause
Likelihood
Tank
design
Fatality
Short circuit
causing electrical
signal from level
switch failing to
reach transfer
pump
0.1
1
1
0.1
1
Clogging of Vent
Line
0.1
1
1
1
1
1
2
3
Initiating Event
Description
Initiating Cause
Backflow of highpressure solvent
steam mixture
causing
substantial
overpressure
ratio
Build up of
pressure within
the storage tank
due to lack of
venting
1.1E-05
6
7
8
Protective Layers
BPCS BPCS Check
Vent
Relief
Valve
Valve
Valve
9
10
11
Additional Layers
12
Discharge
Isolation
Block Valve
Alarm
Rupture
Disc
Mitigated
Likelihood
0.1
1
0.1
0.01
1.0E-06
0.1
1
0.1
0.01
1.0E-05
The design of the intermediate storage tank can be improved by adding the following implementations.
1) Independent pressure tapping on the storage tank with an alarm, pressure alarm high PAH (PFD = 0.1)
This device tracks the pressure within the storage tank and is set at 2 x MAWP of the vessel (2.0 barg). At 2.0 barg, the critical alarm will be set off. Operators
will be activated and respond to the situation on ground to take effective action. For instance, shutting down the plant. The probability of failure of this
implementation is linked to the operator failure that is tagged to be at 10−1 per opportunity, found from a reference material of LOPA analysis [1].
Periodic maintenance should be scheduled to ensure operating conditions of the alarm. These checks should be recorded and logged for auditing purposes.
2) Installation of rupture disc with an emergency tank (PFD 0.01)
A rupture disc is a one-time use pressure safety disc that fails at a set differential pressure. For this operation, the pressure will be set at 2.5 x MAWP of the
vessel (2.5 barg). At 2.5 barg, the membrane ruptures and causes solvent within the storage vessel to flow into the emergency tank. This provides instant
response to critical pressure levels of the tank. The probability of failure of this implementation was tagged to be at 0.01, found from a reference material
online.
Periodic checks should be done to ensure that the rupture disc is not damaged, and it should be replaced as accordance to manufacturer’s recommendations.
Conclusion
The LOPA analysis highlighted that the initial design did not satisfy the target hazard of 3 × 10−5 per year. Hence, two solutions were crafted to minimize the
target hazard down to 1.1 × 10−5 per year.
In the initial analysis, two potential initiating events were considered that assumes the failure of different independent protection layers and computing if
the vessel will rupture. Every equipment was analyzed to understand if their function and deviation could impact the pressure of the storage tank. The
probabilities of both scenarios were added that highlights a vessel rupture chance of 1.1 × 10−2 per year.
The installation of the PAH and the rupture disc would relieve the pressure within the storage vessel at critical pressure. These initiatives are independent of
the existing measures and serves to mitigate the likelihood of vessel rupture. They are also accessible to the operator, hence, auditable. Hence, the hazard
risk was mitigated to 1.1 × 10−5 per year, meeting the targeted hazard tolerance of 3 × 10−5 per year.
References
[1]
Raman, B. (2020). Layer of protection analysis [pdf]. Singapore: Nanyang Technological University.
[2]
American Institute of Chemical Engineers, Guidelines for Initiating Events and Independent Protection Layers in Layer of Protection Analysis, New
Jersey: Wiley, 2015.
Download