Powerpoint Powerpoint T Templates emplates Page 1 Introduction to Quantity Surveying Powerpoint Templates QUANTITY SURVEY??? Introduction Once a construction project is completed or depending on the form of contract upon completion of certain parts of the work, the contractor must be paid for appropriately completed works. This would then require that the actual works done be somehow estimated or measured for payment purposes. On the other hand to estimate how much a civil engineering project may cost, the actual quantities of materials, labor, equipment etc. that is needed for the construction work must be calculated at the beginning of the work. Such work of calculating the amount of materials and other incidentals necessary for the realization of the work is called quantity surveying. Page 2 Powerpoint Templates QUANTITY SURVEY??? Introduction Cont. Quantity surveying is a term or processes used in the construction industry to take measurements of civil works, prepare specifications, and estimate the cost of works either for each trade of work or for the whole project. The term “surveying” means to inspect, study, review, investigate, asses, and hence “to measure” therefore the term “quantity surveying” means “quantity measuring” as applied to civil engineering projects. Quantity surveying is the application of standard methods of measurement to quantify the amount of various items in a construction project, for the undertaking of valuation, and certifying payments. Page 3 Powerpoint Templates QUANTITY SURVEY??? Introduction Cont. The following tasks are covered in quantity surveying. 1. Preparation of Specification 2. Taking measurements of civil works (Taking off quantities and preparing BOQ) 3. Preparation of approximate (preliminary) cost estimate at the very early stage of the project 4. Preparation of detail cost estimate at different stages (taking as built measurements and preparing payment certificates or approval of payment certificates prepared by taking measurements) 5. Valuation of property Page 4 Powerpoint Templates QUANTITY SURVEY??? Pur pose of Quantity Sur veying The purpose of quantity surveying hence the preparation of Bill of quantities is: i. Assist the client to have an accurate estimate of the volume of work as well as the required budget. ii. To assist in the accurate preparation of tenders, by providing uniform measurement of quantities. iii. To give an accurate checklist of work accomplished iv. To assist in the certification of payments v. To give insight into the required variation work amounts. Page 5 Powerpoint Templates ESTIMATE??? a. to judge tentatively or approximately the value, worth, or significance of b. to determine roughly the size, extent, or nature of c. to produce a statement of the approximate cost of Merriam - Webster “It is a valuation based on opinion or roughly made from imperfect or incomplete data, a calculation not professedly exact, an appraisement; also a statement, as by a builder, in regard to the cost of certain work.” Max B. Fajardo Page 6 Powerpoint Templates “Estimating is the most important of the practical aspects of construction management and the subject deserve a closest attention of one aspiring to a career in the profession. It is comparatively simple subject to understand, however, as it bring one up against practical work, methods and procedure, knowledge of it cannot be acquired without close application.” Page 7 Powerpoint Templates Purpose of Estimating To give a reasonably accurate idea of the cost An estimate is necessary to give the owner a reasonably accurate idea of the cost to help him decide whether the work can be undertaken as proposed or needs to be curtailed or abandoned, depending upon the availability of funds and prospective direct and indirect benefits. For government works proper sanction has to be obtained for allocating the required amount. Works are often let out on a lump sum basis, in which case the Estimator must be in a position to know exactly how much expenditure he is going to incur on them 1. Estimating Materials 2. Estimating Labor 3. Estimating Equipment 4. Estimating Time Page 8 Powerpoint Templates Types of Construction Estimates 1. Estimates for Conceptual Planning Based on very general parameters of facility size, anticipated quality of construction and use of facility. Conceptual Estimate – is prepared based from only a conceptual description of the project. -Is done before plans, specifications and other project details have been developed. - ±15 – 20 % accurate Page 9 Powerpoint Templates Types of Construction Estimates 2. Estimates for Feasibility Using preliminary design information and after project scope is completely defined. An estimate of project cost that is prepared before complete construction documents are available. ±15 – 20 % accurate Page 10 Powerpoint Templates Types of Construction Estimates 3. Estimate During Engineering and Design Based on schematic level design documents, it is probable that major quantities can be quantified, concrete, steel based from type of construction. The designer and owner may use the estimate to evaluate expected total project cost but for the purpose of reviewing design cost drivers and performing value engineering Value Engineering – a evaluation of a project objective function for the purpose of bettering the objectives in terms of cost and functional parameters Page 11 Powerpoint Templates Types of Construction Estimates 4. Estimates for Construction Itemized cost computation based on complete set of contract documents (incl. plans and specifications) Bid estimate submitted to the owner either for competitive bidding or negotiation consists of direct construction cost including field supervision, plus a mark-up to cover general overhead and profits. The direct cost of construction for bid estimates is usually derived from a combination of the following approaches. •Subcontractor quotations •Quantity takeoffs •Construction procedures. 5% accuracy Page 12 Powerpoint Templates Types of Construction Estimates 5.Control Estimates. For monitoring the project during construction, a control estimate is derived from available information to establish: Budget estimate for financing Budgeted cost after contracting but prior to construction Estimated cost to completion during the progress of construction. 6.Estimate for Change Order Performed on the project site in response to an owner – directed change in the project. Page 13 Powerpoint Templates Estimating Techniques Approximate Estimates An approximate estimate is an approximate or rough estimate prepared to obtain an approximate cost in a short time. For certain purposes the use of such methods is justified. Detailed Estimate A detailed estimate of the cost of a project is prepared by determining the quantities and costs of every thing that a contractor is required to provide and do for the satisfactory completion of the work. It is the best and most reliable form of estimate. A detailed estimate may be prepared in the following two ways Page 10 Powerpoint Templates Qualification of an Quantity Surveyor 1. A thorough understanding of architectural drawings. 2. A sound knowledge of building materials, construction methods and customs prevailing in the trade. 3. A fund of information collected or gained through experience in construction work, relating to materials required, hourly output of workers and equipment, overhead expenses and costs of all kinds. 4. An understanding of a good method of preparing an estimate. 5. A systematic and orderly mind. 6. Ability to do careful and accurate calculations. 7. Ability to collect, classify and evaluate data that would be useful in estimating. Page 15 Powerpoint Templates Data Required for Preparing an Estimate 1. Plans, sections and other relevant details of the work. 2. Specifications indicating the exact nature and class of materials to be used. 3. The rates at which the different items of work are carried out. Page 16 Powerpoint Templates Steps in Preparing Estimates 1 . Taking out quantities - Measurements are taken off from the drawings and entered on measurement sheet or dimension paper. The measurements to be taken out would depend upon the unit of measurement. 2. Squaring out - Working out volumes, areas, etc. and casting up their total in recognized units. 3. Abstracting - In the third step all the items along with the net results obtained in the second step are transferred from measurement sheets to specially ruled sheets having rate column ready for pricing. Page 17 Powerpoint Templates Work Breakdown Structure Work Breakdown Structure (WBS)– provide a common hierarchical framework for summarizing information and for the quantitative reporting to customers (client/owner) and management. Purpose of Work Breakdown Structure 1.Provide an organized manner of collecting project cost data in a standard format for estimating, cost reporting and cost tracking 2. Provide a checklist for categorizing cost 3.Provide a means to maintain historical cost data in a standard format. Page 18 Powerpoint Templates Page 19 Powerpoint Templates Basics for Preparation of Estimates Review Contract Documents Thoroughly examine the constructions documents Drawings and Specifications General Conditions – part of the contract documents that defines the rights, responsibilities and relationships of all parties to the construction contract. It is appropriate to make notes of anything that can affect construction duration and the cost to perform the work or add indirect and overhead cost to the work Prebid Conference – a meeting held prior to bid opening for the purpose of explaining the project and answering questions that bidders have with respect to the contract documents and the work. Page 20 Powerpoint Templates Basics for Preparation of Estimates Planning The Work Thoroughly understand the scope of work and the project environment. A detailed review enables the estimator to formulate a construction sequence and duration. A site visit is strongly recommended to enable the estimator to relate the physical site characteristics to the available design parameters and details. Quantities Quantity Take-off – must be as accurate as possible and should be based on all available engineering and design data. Quantities should be shown in standard units of measure and should be consistent with the design units. Page 21 Powerpoint Templates Basics for Preparation of Estimates Types of Cost Direct Cost – all cost elements that can be associated with a specific item of project work e.g. cost of labor, cost of materials, cost of equipment Indirect Cost – cost that cannot be attributed to a single task of construction work e.g. overhead, profit, and bonds. Profit – amount of money, if any that a contractor retains after completing a project and paying all cost for materials, labor and overhead. Page 22 Powerpoint Templates Basics for Preparation of Estimates Productivity and Price Resources Historical production and cost data from similar past work are excellent resources of when adequate details have been saved and adjustments to project specifics can be defined. Development of Specific Task Developed task descriptions must describe the scope and material requirement. Page 23 Powerpoint Templates Basics for Preparation of Estimates Unit Cost Labor Unit Cost – cost based on a defined crew that performs the task at an assigned production rate. Equipment Unit Cost Material Unit Cost – developed using vendor quotes , historical cost commercial pricing sources and component calculations. Page 20 Powerpoint Templates Basics for Preparation of Estimates Cost and Pricing cost for each task is developed by summing up the direct cost elements for labor, equipment, materials, supplies and subcontractors. Indirect cost and other markups associated with each task or work item should be identified and considered properly. When using historical pricing, adjustment must be made for location, work methodology, quantity of work, and other dissimilarities that affect prices. Page 25 Powerpoint Templates Basics for Preparation of Estimates Supporting Documents Should always remain mindful of the documentation necessary to support the estimates. Narratives of Contract Cost – contains discussion, considerations and the developed construction plan. Project Narrative Construction Schedule Equipment and Material Utilization Labor Discussion and Utilization Estimate Backup Data – backup documentation Quotations Drawing and Sketches Page 26 Powerpoint Templates Reference: Introduction to Estimates by Engr. Cyrus D. Esguerra http://pmbook.ce.cmu.edu/05_Cost_Estimation.html http://www.misronet.com/estimating.htm Construction Management Fundamentals by Knutson, Schenayder, Fiori, Mayo Page 27