TECHNICAL FEATURE This article was published in ASHRAE Journal, February 2022. Copyright 2022 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/or distributed electronically or in paper form without permission of ASHRAE. For more information about ASHRAE Journal, visit www.ashrae.org. Air-Cooled Chillers Chilled-Water VAV System Configuration And Design BY NABIL NASSIF, PH.D., P.E., MEMBER ASHRAE The air-handling unit (AHU) of a typical variable air volume (VAV) system includes two coils connected to two separate water loops. One coil, the cooling coil, is connected to cooling sources through a chilled-water loop. The other coil, the heating coil, is connected to heating sources through a hot water loop. This separate water loop configuration eliminates the opportunity to use both already-installed piping systems and coils during full cooling or heating seasons and reduces both initial and operating cost savings. This article proposes two possible improvements with several configuration options for chilled-water VAV systems with air-cooled chillers. Typical Chilled-Water VAV System Figure 1 shows typical chilled and hot water loop configurations. Figure 1a shows the heating coil (HC) connected to the hot water loop and Figure 1b shows the cooling coil (CC) connected to the chilled-water loop. Pre-reheat coils may be also added to the hot water loop. The hot water loop also serves VAV box reheat coils. For clarity and discussion, an example will be presented on all figures. It is assumed to have two 5 MBtu/h (1.5 MW) boilers (B1 and B2) and two 500 ton (1.8 MW) chillers (Ch1 and Ch2) required to serve multiple AHUs and zone VAV boxes. One of the AHUs provides 10,000 cfm (4719 L/s) at design cooling and heating loads. The design heating and cooling performance data across the coils, chillers and boilers are also illustrated in Figure 1. This traditional configuration will be replaced by several proposed options as discussed below using the same example numbers for comparison. Option 1: One Common Coil In this case, one common coil (Cl) in each AHU will be used instead of two coils, as shown in Figure 2. This single two-pipe coil will be used either for cooling or heating as needed. The water loop connected to the common coil (Cl), called Loop 1, contains both heating and cooling sources, as shown in Figure 2b and Figure 2d. Nabil Nassif, Ph.D., P.E., is an associate professor of architectural engineering at the University of Cincinnati. 40 ASHRAE JOURNAL ashrae.org FEBRUARY 2022 TECHNICAL FEATURE 400 gpm FEBRUARY 2022 ashrae.org 70 gpm 28 gpm 70 gpm 800 gpm 800 gpm 800 gpm 400 gpm 400 gpm 800 gpm 28 gpm 400 gpm In typical VAV systems, no need exists FIGURE 1 Typical chilled and hot water configurations. for mechanical cooling at a relatively Design Heating Conditions Design Cooling Conditions A. B. low outside air temperature (OAT) 115°F 57°F (e.g., 50°F [10°C]) when the system is Chilled Water Loop Hot Water Loop Air in full free-cooling economizer mode. B1 B2 Ch1 Ch2 Air DB = 38°F CC Air At this temperature, there is also no HC 5 5 500 500 DB = 85°F 10,000 cfm DB = 70°F Air heating provided by the heating coil MBtu/h MBtu/h Tons Tons DP = 65°F 352 kBtu/h DB = 55°F 10,000 cfm due to warm air recirculation. Thus, DP = 54°F 1,600 gpm 800 gpm the same coil can be used for heating 43.2 Tons 42°F 140°F at a lower OAT and for cooling at an To Other AHU To Other AHU Coils elevated OAT. Coils And VAV Boxes The second water loop, called Loop 2, connects the VAV boxes to FIGURE 2 Option 1 Configuration. One common coil in each AHU. heating sources, and it is always Design Cooling Conditions A. B. available in heating conditions. 57°F Figure 2a and Figure 2b shows the Cooling design cooling performance, and Air Cl Figure 2c and Figure 2d shows the DB = 85°F B1 Ch1 Ch2 B2 Air DP = 65°F design heating performance. In Off On On Off DB = 55°F 10,000 cfm heating mode, Cl raises the supply DP = 54°F Loop 2 Loop 1 air temperature (SAT) to a certain 43.2 Tons Off 42°F value, for instance 70°F (21°C), and 1,600 gpm To Other AHU Coils VAV Boxes the VAV box reheat coil adds additional heat, for instance, to 90°F Design Heating Conditions C. D. (32°C). Thus, the boiler can serve 85°F 115°F hot water to the Cls at a lower temHeating Heating perature (e.g., 110°F [43.3°C]) and Air CI thereby operates at a higher effiB1 Ch1 Ch2 B2 DB = 38°F ciency compared to a traditional On Off Off On Air 10,000 cfm DB = 70°F system. Coil Cl can be designed and Loop 2 Loop 1 352 kBtu/h selected for cooling (typically with 110°F four to eight rows), as the heating 140°F To Other AHU Coils will be done mostly by the Loop 2 VAV Boxes local reheat VAV boxes. Let us now look at the control. When the OAT drops below 45°F (7.2°C), for instance, Loop 1 in each AHU should be available in heating or coolswitches from cooling to heating, so the cooling sources ing, accordingly, which is based on the OAT. The SAT should be locked off. When the OAT increases above 50°F resetting algorithm can also be identical to the one in (10°C), the loop will switch from heating to cooling so a traditional VAV system.1 However, during the heatthe heating sources should be locked off. Five degrees ing period, the supply air temperature setpoint may is a dead band to avoid cycling between cooling and be adjusted upward or downward to split equally the heating. heating loads between Loop 1 and Loop 2 in a way that The supply air temperature control loop could be the heating load will be shifted from Cl to the VAV identical to when two coils are used in a traditional box or vice versa. Loop 1 serving the VAV box provides VAV system as shown in Figure 3. The only difference is always hot water to VAV box coils for heating whenever that the same coil is controlled in cooling or heating needed as in a traditional VAV system. mode, and associated Loop 1 serving this single coil ASHRAE JOURNAL 41 TECHNICAL FEATURE Option 2: One Common Coil With Heat Pumps FIGURE 3 Supply Air Temperature Control for Option 1 and Option 2. Single coil with and without heat pumps. OAT = 45°F OAT = 50°F Water Loop 1 in Heating Water Loop 1 in Cooling 100 Valve Position (%) The main advantage of this configuration is the use of one coil instead of two coils in each AHU, leading to smaller AHU size, less piping and control valves and lower fan energy use due to reduced flow resistance. This configuration also eliminates the need for a preheat coil. Free Cooling Economizer Damper Control CI 0 0 100 Control Signal CI 200 300 42 ASHRAE JOURNAL ashrae.org FEBRUARY 2022 28 gpm 400 gpm 800 gpm 70 gpm Some or all air-cooled chillers and FIGURE 4 Option 2 Configuration. One common coil with heat pumps. boilers in Option 1 can be replaced with air-source heat pumps (HPs). Design Cooling Conditions B. A. Figure 4 shows two chillers replaced 57°F Cooling by heat pumps of the same capacity. Air Figure 4a and Figure 4b show the design CI DB = 85°F B1 HP1 HP2 cooling performance, and Figure 4c Air DP = 65°F Off On On DB = 55°F and Figure 4d show the design heat10,000 cfm DP = 54°F Loop 2 Loop 1 ing performance. This configuration Off 43.2 Tons holds the same advantages of Option 1 42°F but with fewer boilers to be installed. VAV Boxes 3,200 gpm To Other AHU Coils This option reduces burning fuel at the site and provides a pathway to Design Heating Conditions C. D. the future trend in electrifying and 115°F 85°F decarbonizing buildings. The coil Heating Heating design and control are identical to HP2 Air CI B1 HP1 (May Be Option 1 discussed earlier and shown DB = 38°F Dual-Fuel Air On On in Figure 3. 10,000 cfm HP) DB = 70°F Loop 2 In cold climates when the air-source Loop 1 352 kBtu/h 400 gpm heat pump efficiency reduces sig140°F 110°F nificantly, dual-fuel heat pumps can VAV Boxes 400 gpm To Other AHU Coils be used. In addition, at lower OATs, when the heating load is too high and when the SAT is maintained by the heating coil rather any of those coils in heating or cooling modes. To achieve than the economizer dampers, the SAT setpoint can be that, each water loop contains both heating and cooling reset to a lower value (e.g., 60°F [16°C] or even lower) to sources as shown in Figure 5 and Figure 6. Loop 1 serves shift the heating to the local reheats served by the boiler the first AHU coil (called Cl1), one chiller and one boiler. and consequently reduce the load on HPs when they Loop 2 serves the second coil (Cl2) and contains one are not that efficient. This will also reduce the load on chiller and one boiler. The zone VAV boxes will be conthe coil (Cl) that is designed and selected for the cooling nected to Loop 1. season. The Cl1 coil can be designed for heating with two rows, as an example, and the Cl2 coil can be designed Option 3: Two Coils for cooling with four to eight rows. Cl1 will provide the Now let us examine a different scenario when two coils second stage of cooling during warm weather when no in each AHU and two separate water loops are installed heating is needed. Cl2 will provide the second stage of as in a traditional system but with the possibility of using TECHNICAL FEATURE 44 ASHRAE JOURNAL ashrae.org FEBRUARY 2022 35 gpm HC 5.2 gpm 400 gpm 400 gpm 400 gpm 400 gpm 22.8 gpm 35 gpm CC heating during cold weather when no FIGURE 5 Typical Air-Handling Unit AHU vs. Option 3 or Option 4. Two coils. mechanical cooling is needed as disExhaust Air (EA) Return Air (RA) Exhaust Air (EA) Return Air (RA) cussed later in Figure 7. Many advantages result from this CI1 CI2 Supply Air Supply (SA) configuration, but all depend on how Air (SA) Outdoor Outdoor Mixed Mixed the coils are selected. If the sizes of Air (OA) Air (OA) Air (MA) Supply Fan Supply Fan Air (MA) coils and water loops are kept the VAV Boxes VAV Boxes Water Loop 1 Water Loop 2 Chilled Water Loop Hot Water Loop same as in a traditional system, this B. Typical AHU A. Option 3 or Option 4 configuration can reduce pump energy uses as chilled or hot water will split between the two coils during FIGURE 6 Option 3 Configuration. Two coils. full cooling or full heating periods. It Design Cooling Conditions B. A. can enhance heat transfer between 57°F 67°F water and air as more surface areas Cooling Cooling Air (both coils instead of just one coil) are DB = 63°F Air Air CI1 B1 Ch1 Ch2 B2 used. However, to reduce the size of DP = 63°F CI2 DB = 85°F DB = 55°F Air Off On On Off DP = 65°F DP = 54°F AHU and water loop pipes, combined DB = 63°F 10,000 cfm 21.6 Tons coils and associated water loops can DP = 63°F Loop 2 Loop 1 400 gpm 21.6 Tons be designed to meet the peak cooling 52°F 42°F loads and the peak heating loads, cut400 gpm VAV Boxes ting the size of those coils and piping diameters compared to a traditional Design Heating Conditions C. D. system. 115°F 85°F Heating Heating Another advantage is related to Air DB = 44°F the opportunity to run the chiller Air CI1 B1 Ch1 Ch2 B2 CI2 10,000 cfm DB = 38°F Air in Loop 1 serving Cl1 at an elevated On Off Off On Air 10,000 cfm DB = 70°F chilled-water supply temperature DB = 44°F 286 kBtu/h Loop 1 (e.g., 52°F [11°C]). Looking at the 66 kBtu/h Loop 2 800 gpm 400 gpm example in Figure 6b, the first coil 110°F 140°F (Cl1), which is typically designed for VAV Boxes heating with two rows, cools the air to an elevated value—for instance to 63°F (17°C)—and the chillers in Loop 1 can produce be locked off, and Loop 1 will be available in heata higher supply water temperature of 52°F (11°C) and ing so the VAV box reheat coil can provide heating if operate more efficiently than the chillers in traditional needed. Loop 2 continues providing cooling through configurations. Cl2 if needed. When the OAT drops below 40°F (4.4°C) A similar scenario for heating can be obtained as (adjustable) so no mechanical cooling is needed, Loop shown in Figure 6d: Cl1 heats the air to 44°F (6.7°C) for 2 and Cl2 become available for heating. The chillexample, the boilers in Loop 1 can operate at lower supers in Loop 2 should be also locked off. When the ply water temperature (e.g., 110°F [43.3°C]), but this OAT increases above 45°F(7.2°C) (adjustable), Loop 2 is possible only if the VAV box is designed for this low and Cl2 become available for cooling. When the OAT temperature. increases above 70°F(21°C) (adjustable), Loop 1 and Looking at the control, both loops and associated Cl1 become available for cooling. Five degrees is a dead coils (Cl1 and Cl2) will provide cooling when the OAT band to avoid cycling between cooling and heating. is greater than 65°F (18°C) (adjustable). The boilers in The two coils could simply be controlled in sequence both loops should be locked off. When the OAT drops as shown in Figure 7. In cooling, the SAT is controlled by below 65°F (18°C), the chillers in this loop should Cl2, and when the valve position becomes fully open, TECHNICAL FEATURE 22.8 gpm In this option, some or all cooling and heating sources in Option 3 can be replaced by air-source 110°F heat pumps. Here the two boilers and two chillers were replaced by two heat pumps as shown in Figure 8. A dual-fuel heat pump in Loop 1 serving hot water to VAV boxes may be selected. In a cold climate when HPs operate inefficiently, dual-fuel heat pumps in both loops may be selected. Another other option is to add an emergency gas-fired or electric boiler in Loop 1 and/or in Loop 2. This configuration holds the same advantages of Option 3 but with additional benefits of installing fewer boilers and chillers. The SAT control in this option is identical to the one in Option 3 presented in Figure 7. Loop 2 35 gpm 800 gpm HP2 On HP1 On DB = 38°F 10,000 cfm Loop 1 110°F 400 gpm CI1 5.2 gpm Air DB = 70°F 286 kBtu/h 400 gpm Option 4: Two Coils With Heat Pumps 10,000 cfm CI2 400 gpm 800 gpm Valve Position (%) the control will modulate the Cl1 valve FIGURE 7 Supply Air Temperature Control for Option 3 and Option 4 Configurations. Two coils with and without heat pumps. position. In economizer mode, the SAT is controlled in a similar way as OAT = 40°F OAT = 65°F OAT = 45°F OAT = 70°F in traditional control. In partial free Loop 2 in Heating Loop 1 in Heating Loop 1 and Loop 2 in Cooling cooling economizer mode, the SAT is maintained by Cl2 when the outside 100 Max Valve Position economizer damper is fully opened. Full Free Cooling CI2 Economizer Damper In full free cooling economizer mode, CI2 Control CI1 CI1 the SAT is controlled by the economizer dampers. In heating, the SAT is maintained by Cl1, and when the 0 0 100 200 300 400 500 valve position reaches a maximum Supply Air Temperature Control Loop Signal value, the control will modulate to the Cl2 valve position. FIGURE 8 Option 4. Two coils with heat pumps. As Loop 1 should serve hot water Design Cooling Conditions B. A. for both Cl1 and VAV boxes, the heat57°F 67°F ing capacity of this loop should be Air carefully examined. Depending on Air DB = 63°F Air the design VAV box reheat loads, the DB = 85°F CI DP = 63°F CI2 DB = 55°F HP2 HP1 DP = 65°F maximum value of the Cl1 valve posiDP = 54°F On On Air 10,000 cfm 21.6 Tons tion could be set to lower than 100% DB = 63°F DP = 63°F Loop 2 Loop 1 (e.g., 70%) so the heating load will be 21.6 Tons shifted from Loop 1 to Loop 2, and 52°F 800 gpm 800 gpm VAV Boxes 42°F consequently Loop 1 will have more capacity to serve the VAV boxes. This Design Heating Conditions C. value could be dynamically reset D. 85°F 85°F based on VAV box hot water valve Air position readings. Air DB = 44°F Air DB = 44°F 66 kBtu/h VAV Boxes Cost Saving Estimation The equipment cost savings due to the configuration options presented are shown in Table 1. The initial costs were obtained by consulting with local HVAC companies, and a conservative approach is used. The cost range should be treated very carefully as this may vary from project to project and location. The objective is not to get exact cost estimation but rather to get approximate meaningful comparisons between those options as opposed to the traditional design (base) shown in Figure 1. The operating cost is obtained by running models for 40,000 ft2 (3716 m2) office building using the FEBRUARY 2022 ashrae.org ASHRAE JOURNAL 45 TECHNICAL FEATURE energy simulation software TABLE 1 Cost estimation for several option configurations. EnergyPlus2 for seven cliCOST EQUIPMENT OPTION 1 OPTION 2 OPTION 3A OPTION 3B OPTION 4B mate zone locations. Option 3a is when the same coils Base – Base – – Base – Coil + Valve Base (15% toBase (40% to 50%) (40% to 50%) 25%) (15% to 25%) and water loops of the base (traditional system) is used. Base – Base – – Base – Pipe Base (20% toBase Initial (10% to 20%) (10% to 20%) 30%) (20% to 30%) Cost of Option 3b is when the comEquipment Base – – bined coils are designed to Listed Cooling or Heating Base Base Base (25% toBase Equipment (15% to 25%) 35%) meet the peak loads. Option Base – Base – – Base – 4b is identical to Option Pumps Base (15% toBase (2% to 7%) (2% to 7%) 25%) (15% to 25%) 3b but using heat pumps. Base – Base – Base – Base – Dual-fuel heat pumps or AHU Fan Base (20% to 30%) (20% to 30%) (5% to 15%) (5% to 15%) possible needed emergency Operation Cost of Base – Base – Base – Base – Base – heaters are not included in Pump Equipment (5% to 10%) (5% to 10%) (40% to 50%) (10% to 15%) (10% to 15%) the cost as the needs of those Listed Base – Base – Base – Base – Base – depend heavily on location. Chillers/Boiler/HPs (2% to 7% Boiler) (2% to 7% Boiler) (10% to 20%) (15% to 25%) (15% to 25%) In all options, the initial and operation equipment costs are equal and lower than the base. Using air-source heat pumps instead of traditional boilers and chillers as in Option 4 lowers the number of Conclusion equipment to be installed, further dropping the system’s The common design in traditional VAV systems, using initial cost. two separate chilled and hot water loops, reduces the All recommended options, with a simple changeover opportunity to achieve initial and operating cost savings. temperature control and SAT temperature control Including heating and cooling sources in both loops can loop, provide huge energy and cost benefits for any make any of those loops provide heating or cooling when buildings designed to be conditioned by traditional needed, reducing the number of coils or cooling and chilled-water VAV systems with air-cooled chillers. heating equipment to be installed. Attention should be taken to increase the time when In the first configuration option, when a common coil both coils and loops operate during mechanical coolis used instead of two coils, the required cooling and ing-only seasons or heating-only seasons. The control heating by AHUs is provided with fewer coils, smaller can limit the coil valve opening to a maximum valve AHU, fewer pipes and valves and reduced fan energy position, so the loads can somewhat split between use. Compared to the traditional design, this option the coils. This maximum value can dynamically reduces both initial and operating cost as indicated in be adjusted based on the number of chillers, boilTable 1. If air-source heat pumps are used in the water ers or heat pumps that operate in each loop. Also, it loop, as in Option 2, fewer cooling and heating sources requires careful examining of coil selections such as are required to be installed, further reducing the projnumber of rows of tubes, fins, coil face area, etc., and ect’s initial cost. optimal design of those parameters so the same coil Other possible improvements as in Option 3 are to can provide effective cooling or heating in different use the traditional two coils, each connected to a water seasons. loop equipped with both cooling and heating sources so it can provide heating or cooling as needed. Thus, the References 1. ASHRAE Guideline 36-2018. High-Performance Sequences of combined coils and water loops are designed to meet Operation for HVAC Systems. the peak loads, reducing the size of coils, AHU and pipe 2. DOE. 2018. “EnergyPlus.” Version 9.0.1. U.S. Department of diameters. It also reduces chiller, fan and pump energy Energy. https://energyplus.net/ use. This option reduces significantly both initial and operating cost as indicated in Table 1. 46 ASHRAE JOURNAL ashrae.org FEBRUARY 2022