Installation challe enges - Polarled pipeline e project Ins stallatio on challe enges - Polarle ed pipeliine projject 1. Abstract A t This paperr presents the T t techniccal challeng ges and en ngineering solutions a associated d with the ssuccessful installation n of the 36--inch pipeline for the P Polarled piipeline projject. Installlation of the e Polarled pipeline w was carried out b Allseas’’ dynamica by ally position ned pipelayy vessel So olitaire. The e main c challenges s that had to t be overccome during the insta allation cam mpaign are s summarise ed below: • • • • • • Stinge er setup; Pipelin ne initiation n at Nyham mna; Pipela ay through the Bjørnssundet area a; Installation of fou ur single in n-line tees and a one du ual in-line ttee; Coatin ng transitio on point at 700 7 m water depth; Laydo own on the pre-installed foundattion sliding plate (FSP P) at Aasta a Hanstteen. A compreh hensive con ntingency p procedure was developed for co oping with the u unlikely scenario of a deep wate er wet buckle, includiing design and fabriccation o some un of nique equip pment; a 36-inch isola ation plug and a 1,00 00 t pipeline e r recovery to ool capable e of launch hing a dewa atering pig. 2. Abbrevia A ations A&R A C CWC F FSP F FSPP H HSS I ILT O OD P PE P PP P PLEM R ROV Abandon nment and Recovery Concrete e Weight Coating C Foundattion Sliding g Plate Flame S Spray Polyp propylene Heat Shrinkable Slleeve In-line te ees Outside Diameter hylene Poly Eth Poly Pro opylene Pipeline End Maniffold d Vehicle Remotelly Operated T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 1 Installation challe enges - Polarled pipeline e project 3. The T Pola arled pipe eline pro oject The Polarle T ed pipeline e project co omprises o of a 482 km m long and 36-inch OD D gas t transmissio on pipeline e from the A Aasta Hanssteen field in the Norw rwegian Se ea, r reaching w water depth hs of 1,265 m, to the N Nyhamna p plant at the e western ccoast o Norway.. The Polarrled pipelin of ne includess four single e in-line tee es assemb blies a one du and ual in-line ttee assemb bly, all with h 12-inch b branch pipin ng. The pip peline s system will transport a dry, rich gas opera ating in the dense pha ase, as single p phase gas, with an operating prressure of between 231 2 and 115 barg. Figure 3.1 – Polarled pipeline p overvview The pipelin T ne was laid d from the N Nyhamna landfall tow wards the P PLEM and i initiated byy means off a shore pu ull-in opera ation at the e landfall. Following F i initiation, th he pipeline e was laid tthrough the e Bjørnsundet area where w the p pipelay wa as parallel tto existing pipelines with w tight in nstallation ttolerances and p presence o unstable of e curves with pre-insta alled tempo orary coun nteracts. The Polarle T ed pipeline e consists o of pipe secctions with 10 differen nt combinattions o wall thicckness (28..9, 30.5, 34 of 4.6 and 37..5 mm), an nti-corrosion coating (PE ( a PP) an and nd concrete e weight co oating thickkness (50 a and 70 mm m). In total there a 21 tran are nsitions bettween the various v pip pe sectionss. The pipelin T ne route co ontains 110 0 curves. T The radii of the curvess vary betw ween 1,000 m an nd 20,000 m. Some o of the curve es were un nstable, the erefore counteractts were pre t temporary e-installed.. Polarled ccrosses 28 8 pipelines and c cables. Final laydo F own at Aasta Hanstee en was perrformed using a cut-to o-length joint for d direct laydo own onto the pre-insttalled found dation slidiing plate (F FSP) using g an i innovative w ± 1.5 m axial tole erance in 1,265 1 m wa ater laydown cconnector, with d depth. T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 2 Installation challe enges - Polarled pipeline e project 4. Stinger S s setup Pipelay by means of an S-Lay installation vessel, fro P om very shallow to ve ery d deep water, creates a challenge e for selectting the op ptimum stinger c configuratio on. IIn deep wa ater, a depa arture anglle as close e to verticall as possib ble is desire ed in o order to de ecrease the e required ttension levvels, resultiing in a sm maller stinge er r radius. How wever, in sshallow watter departu ure angles are typicallly low as the v vessel thru ust is used to keep the sagbend d strains within limitations. This r results in a shorter sttinger lengtth or a larg ger radius ((or a combination of b both). C Changing t stingerr length and the d/or radius is an operration that is difficult tto p perform in the field an nd generallly requiress the vesse el to make a port call. M Minimising g project co ost is a sign nificant drivver, leading g to an emphasis on s setting up o one stinger configura ation for the e entire pro oject. As mention A ned above,, a smaller stinger rad dius allowss for the ten nsion level to b reduced be d, which ha as the follo owing advantages: • Decre eased fuel cconsumptio on, resultin ng in less e environmen ntal impact and lower project cossts; • Creatiing shorterr free spanss, consequ uently less seabed inttervention is ed which h has comme ercial benefits; require • Installation of tig ghter curve radius, wh hich creates more flexxibility for rroute optimisation. However, b H by setting a stinger in n a smaller radius, hig gher strainss are i introduced , mainly in the overbe end region. This impa acts with re egard to the a acceptance e criteria on which the pipeline is to be insstalled. The e following key c constraints s were veriffied during g stinger radius selecttion for the e Polarled p pipeline insstallation: • • • • Local buckling lim mit state; Globa al buckling limit state; Fatigu ue limit statte; Concrrete crushin ng limit sta ate. As a resultt of extensiive enginee A ering, a stin nger config guration wa as selected d c consisting of 140 m le ength set in combination with a radius in tthe range of o 2 m to 2 240 220 m, suita able for insstallation off all pipe prroperties along a the ro oute f from very sshallow to vvery deep water. T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 3 Installation challe enges - Polarled pipeline e project Figure 4.1 – Solitaire sstinger during g Polarled pip peline installa ation IIn addition to the setu up of the sttinger radiu us, the elevvation of ro ollerboxes plays a significan nt role in piipeline insttallation. An n optimal rollerbox r elevation se etup m minimises strains and d stresses in the pipe e. Each rollerrbox is con E nstrained byy its design n load. The erefore, the e rollerbox s setup mustt ensure th hat the load ds are distrributed as e evenly as p possible accross a rollerboxxes, thereb all by decreassing the strresses on the pipe ass well as the e l load on the e rollerboxe es. Due to the large num D mber of diffe erent pipeliine section ns and wate er depth v variances, several se ensitivity ch hecks were e conducted to determ mine a sing gle r rollerbox setup suitab ble for the entire e proje ect. On Solitairre, the sting O ger can be rotated arround the m main hinge between the t h and se hull ection 1, the hinge be etween secctions 1 and d 2, and the hinge b between se ections 2 a and 3. Thiss feature wa as used to accommodate simple s stinger adjustments during d the shore s pull--in operatio ons where tthe water d depth a the sting at ger main hiinge was o only 61 m. 5. Pipeline P initiation n at Nyha amna 5.1. Introd 5 duction T Polarle The ed pipeline e installatio on was initia ated by an onshore p pull-in operration. nging and congested T shore approach is located in a challen The d area at th he live N Nyhamna G Proce Gas essing Plan nt. In additio on, the high pressure e Langeled d e export gas pipeline ru unning to th he UK is lo ocated onlyy 5 m from pipeline ro oute. For the pulll-in operattion, a linea F ar winch with a capaccity of 500 t was seleccted. T landfa The all, including g the found dation for the pull-in w winch, support blockss u under the p pull-in wincch/tempora ary pig laun ncher and foundation f for the pull-in c cable reel, was consttructed prio or to the arrrival of Sollitaire in th he field. T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 4 Installation challe enges - Polarled pipeline e project A 4-inch diiameter pull-in cable w with recove ery rigging was installed on the p pipeline route by a su upport vesssel prior to the arrivall of Solitairre in the fie eld. O arrival of Solitaire On e the pull-in n cable wa as connecte ed subsea to the A&R R w of Sollitaire by a wire an ROV. Fig gure 5.1 – Ge eneral arrang gement of pull-in winch The first 2 20 joints of the pipelin ne were coa ated with p polypropyle ene (PP), followed by b concrete e weight co oated (CWC C) pipe join nts. The fie eld joint coa ating on this secction was m made with flame spra ay polyprop pylene (FSPP) for the e first segment and a heat sh hrink sleevves (HSS) o on the CW WC pipe. 5.2. Installlation eng 5 gineering c challenges s T This sectio on highlightts the technical issue es faced du uring the de etailed e engineerin g in order to achieve a safe, co ost effective e and robusst pipeline s shore pull--in operatio on in a cong gested are ea. 5.2.1. P Pull-in ana alysis Comprehensive analyses were performed C d for the pu ull-in operation to spe ecify t minimu the um required d pull-in force for the winch, the e minimum required p pull-in c cable lengtth and the minimum rrequired So olitaire top p tension to o be applie ed d during eacch pull-in sttep. This in n order to maintain m the e shape off the catena ary m meeting the limit state criteria and a the corrresponding g strains in n the pipelin ne d during the pull-in ope eration. The e analysess consisted of: • Calculation of top and botto om tension ns and stra ains in the p pipeline catena ary; n • Calculation of the required winch forcce by taking g upper bo ound friction ne and seabed; factorss between the pipelin • Calculation of pipeline stab bility after rreleasing th he pull-in winch w by adoptiing lower b bound axial friction factors. T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 5 Installation challe enges - Polarled pipeline e project The resultts of the ab bove analysses are pre esented in Table 5.1 below. T Table 5.1 - Su ummary of pu ull-in analysiss M Maximum lay tension S Stand-off position M Maximum pipe length to b be pulled over seabed up to tie-in M Maximum botttom tension R Required tenssion capacityy of the winch h [t] [m] [m] [t] [t] 112 2 670 0 368 8 86 6 334 4 • The m maximum pull-in winch h tension w which was experience ed at Nyha amna was approximate ely 300 t. T This value was w 10% le ess than th he calculate ed pull-in tension. Flange loa ad analysis s 5.2.2. F T pull-in head wass connected The d to the pip peline via a flange asssembly, p preventing e pull-in he ead by a pig launcherr. In hot work ffor replacement of the over o order to faccilitate passsage of the e flange asssembly through the ffiring line, o t stingerr and onto the the t seabed d, a cocoon n-shaped rollerguide r was designed. To design the cocoon T n, the axiall loads, ben nding mom ments and ssupport r reactions a applied to tthe flange w were separrately calcu ulated. The e flange wa as m modelled a as a stiff se ection and the offset b between th he flange and pipeline e was t taken into account. T The analysis was repe eated for each individ dual rollerbox a the ma and aximum axxial tension and bendiing momen nt were con nsidered ass the b basis for th he cocoon design. Figure 5 5.2 – Genera al arrangeme ent of pull-in h head assemb bly 5.2.3. H Holdback clamp des sign A After comp pletion of th he pull-in o operation, the intention was to re elease the pulli winch ass soon as tthe pull-in h in head reach hed the tarrget box. The Polarle T ed pipeline e was route ed in such a way that immediate ely after the e p pull-in operation the p pipeline layy on a veryy steep slop pe of 14 de egrees follo owed b a long ccurve on a free span. Hence, there was a risk of the pipeline sliding by T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 6 Installation challe enges - Polarled pipeline e project after releassing the pu a ull-in tensio on due to te ension fluctuations ass result of v vessel dyn namics and d the installation in a ccurve. A holdbackk clamp wa as designed and mou unted on the pipeline close to th he p pull-in head, secured d to an anchor point constructed c d at the landfall by d dedicated rigging, ass shown in Figure 5.3. After layin ng approximately 2 km of p pipe, for which the an nalysis sho owed that the pipeline e stability criteria c were e s satisfied du uring norm mal pipelay operation, the tension in the pu ull-in cable was s slowly redu uced to zerro and the pull-in cab ble was discconnected from the p pull-in h head. Figure 5 5.3 – Onshorre hold-back clamp 6. Pipeline P installattion challlenges 6 Pipela 6.1. ay through h the Bjørn rnsundet a area Pipelay in tthe nearsh P hore section n of the Po olarled routte, the so-ccalled B Bjørnsunde et area, is considered d to be one e of the mo ost challeng ging pipelin ne i installation n operationss ever atte empted. The area, characteris T c sed by a wide range o of water de epths and ffrequent c changes in n seabed gradient, cre eated man ny challenges during both b the d detailed insstallation engineering e g and execcution phasses of the p project. T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 7 Installation challe enges - Polarled pipeline e project Figure 6.1 – Overview off Polarled pip peline route in n Bjørnsunde et area Combinatio C on of the lim mitations p presented b below were e associate ed with pipe elay i the Bjørn in nsundet arrea: • The firrst 14 km of o the pipelline route – through th he Bjørnsu undet area – is restriccted by the existing La angeled No orth pipelin ne and Orm men Lange e pipelin nes and ca ables togeth her with the e topograp phy of the fjord, fj resultting in limited d manoeuvvrability for the pipelayy vessel du ue to the tight installa ation toleran nces. • The stteep slope at the land dfall resultss in a rapid d increase in the tension level. Increasing g the top tension has a direct efffect on the bottom ten nsion, which must be kkept as low as feasible e for curve e stability and on-botto om mprehensivve approacch was nee eded during g roughness analyyses. A com ay analysis in order to o optimise tthe require ed tension llevel which h pipela satisfie ed the limitt state crite eria of pipe eline installation and tto provide proper input for the t counteracts desig gn. T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 8 Installation challe enges - Polarled pipeline e project Figure 6.2 – Slope at landfall locattion • There were 8 tig ght radius ccurves in th he Bjørnsun ndet area ffor which th he laterall seabed frriction was insufficient to provide e on-bottom m stability of the pipelin ne so the curves c were e unstable. According gly, counte eracts had tto be installe ed within th he narrow corridor. In nstallation of the pipe eline next to o the counte eracts wass very difficcult at locattions where e the countteracts werre installe ed inside the lay corrridor, conse equently fu urther reducing the lay corrido or. Figure 6.3 3 – Pipelay next to counte eract • In the Bjørnsund det area the ere are larg ge lateral in nclinationss and an extrem mely uneve en seabed resulting in n a large nu umber of frree spans; T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 9 Installation challe enges - Polarled pipeline e project • Pipelin ne wall thicckness tran nsitions in the t Bjørnsu undet area a required chang ges in the te ension leve el in order to maintain n the pipeliine catenary as require ed as per tthe installa ation speciffication. Du ue to the ch hanges in tthe bottom m tension a and the varrying latera al stability of o the pipelline on the seabe ed, the curvve stability assessme ent was con nverted to a more compllicated ana alysis. • The Polarled P pip peline insta alled in the Bjørnsund det area wa as very stifff due to a w wall thicknesss of 37.5 mm (in add dition to the concrete e weight coatin ng). Installa ation of succh a rigid pipe with co onstraints, ssuch as lon ng pans, tight curve radiii laying next to countteracts and d a narrow free sp laying corridor, g generated a significan nt number of challeng ges. These e were d dealt with b both during g the engin neering pha ase to asse ess the behavviour of the catenary a and during the execu ution phase e with regard to the acccurately co ontrolling b barge posittion and ten nsion. • In add dition to the e pipeline in nstallation challengess discussed above, th he Polarle ed pipeline e was route ed through no loading g zones in the Bjørnssundet area, due to p proximity off the Lange eled pipelin ne and sevveral other ssubsea pip pelines and d umbilicalss over the ffirst 14 km. An overview of the pipeline ro oute in the Bjørnsund det area is sshown in F Figure 6.1. Solitaiire has the e capacity tto store ap pproximately 10 km off 36-inch pipe p where e the length h of the pip peline throu ugh the Bjø ørnsundet a area was 14 km m. This wou uld mean th hat after layying 10 km m of pipe, th he pipeline would need to be e laid down n and the vessel v wou uld have to sail to a g pipe. loading area for restocking er to avoid d the laydow wn operatio on, which w would intro oduce safetty In orde risks and a consum me operational time, research w was perform med to iden ntify areas in the Bjørrnsundet area where pipe loadin ng would b be allowed.. The assessment wass performed n the requirements in ndicated in d based on ence 1 and d three loca ations were e considere ed to be accceptable Refere loading zones, allowing a pip pelay to continue thro oughout the e first 14 km m withou ut having to o temporarrily lay dow wn the pipe. Figure 6.4 – Schematic of drop d cone ob bject and accceptable load ding zone T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 10 Installation challe enges - Polarled pipeline e project 6.2. Pipela 6 ay along th he route 6.2.1. A&R restrricted area as A Along the rroute, seve eral restrictted zones w were identiified where e A&R o operations could not be perform med for the e following rreasons: • In orde er to ensurre a one-tim me touchdo own of the Polarled p pipeline ove er existin ng subsea assets, a special s wea ather windo ow was de efined in ord der to guarantee eitherr a safe passsage of th he subsea assets or a an donment att a sufficien nt length be efore the crossing. c aband • During g the installlation of a curve, the pipelay ve essel does not follow the design n route. Co onsequentlyy, in case of o any requ uired abandonment, the t pipelin ne will not be b laid dow wn on the d designed ro oute. In case survey data are no ot available e for such locations, these areass have to b be defined as a restriccted area fo or pipeline abandonm ment. In thesse areas, temporary t pipeline ab bandonmen nt had to b be avoided.. Therefore, for ea ach of the iidentified zzones, a we eather wind dow was define ed and used d as a guid deline to en nsure sufficcient pipe ccould be la aid to pass tthe zone prrior to aban ndonment. Figure 6.5 – Schem matic of barge e track at currve installatio on 6.2.2. Critical crrossings The Polarle T ed pipeline e route crossses a tota al of 28 pipe elines, ME EG lines and u umbilicals, which werre covered by rock du umping prio or to pipela ay to preve ent a damag any ges. The piipelay corrridor was re educed from ±10 m to o ±1 m at these c crossing lo ocations in order to m minimise the e amount o of rock dum mping required. Several of the crosse S ed pipeliness and cable es are loca ated close to each oth her. I order to hit all target boxes, p In pipelay had d to be veryy accurate and was by two RO c controlled OVs. Figure e 6.6 showss one of the e most critical crossin ngs a along the Polarled P route. T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 11 Installation challe enges - Polarled pipeline e project Figure 6.6 – Typical critical crrossing along g Polarled rou ute 6.2.3. Coating trransition p point at 70 00 m waterr depth At the transsition from concrete w A weight coa ated pipe to o polypropyylene coate ed p pipe, Solita aire’s tensioners had to hold the e PP coate ed pipe with h the full c catenary frrom the vesssel to the seabed co onsisting off concrete weight coa ated p pipe. The tensions during tthis operation with the T e least favo ourable wa ave and wind d direction w were analyssed to be: • Static tension: 32 27 t • Dynam mic tension n at Hs 4 m m: 438 t The above T e tensions a are spread over the vvessel’s thrree tension ners, which h r results in th he followin ng: • Static tension: 109 t/tensioner • Dynam mic tension n at Hs 4m: 146 t/tenssioner The tensioner pads p T play a signiificant role in translating the tensioner cap pacity ntify the re t holding ccapacity. A slip test w to was perform med to iden equired squ ueeze p pressure o of the tensio oners and to verify th he maximum m holding ccapacity off e each tensio oner. The slip s test esstablished tthat, with a single ten nsioner usin ng h hard pads a holding ccapacity off 300 t coulld be achie eved and 3 325 t with soft p pads. Therefore it could be concluded T d that this o operation ccould be exxecuted safely w either hard padss or soft pads because the tension levels would with w not reach r s levels. In order to slip o decrease e the risk off pipeline sslippage, a decision was w T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 12 Installation challe enges - Polarled pipeline e project made to usse hard pads for the cconcrete co m oated pipe, which wo ould be rep placed b soft pad by ds prior to rreaching th he coating transition p point. 7. Installati I ion of in--line tees s 7.1. Generral descrip ption Along the P A Polarled pipeline routte, four single tees an nd one dua al in-line tee e ( (ILTs) need ded to be installed fo or future tie-ins. Table e 7.1 presents an ove erview o the weig of ght of the structures. Table 7.1 – Weightt of inline stru uctures Inline Tee Weight [t] [-] Dry Subm merged Dual 38 18 S Single 20 10 Figure 7.1 – Co onfiguration o of single and dual ILTs IInstallation n tolerances of the ILT Ts were ±6 6.1 m and ± 1 m in lon ngitudinal a and directions respective t transverse ely. The rolll tolerance e of the ILT Ts was ±15 5 d degrees. Any in-line structure that A t is to be installed from an S-lay installa ation vesse el m must be de esigned so that it fits through the tensione ers and can n travel ove er the s stinger whiile the overrbend straiins remain acceptable e. This is a common issue w when insta alling in-line e structuress in S-mod de and wass addressed during th he d detailed de esign phase. T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 13 Installation challe enges - Polarled pipeline e project Figure e 7.2 – Schem matic overvie ew of tension ner envelope 7.2. Rotati tion mitiga ation A Although ro otation of the t pipeline e is not pro oblematic fo or normal p pipelay, m maintaining g the verticcality of the e in-line strructure on tthe seabed d is alwayss a c concern. A Any unexpe ected large angles willl result in an a increase ed duration n of t future ssubsea tie--in operatio the ons and will require modification m ns to the tie e-in e equipment t. According to the theo A ory describ bed in Refe erence 2, piipelines tha at are subjected t residual curvature during pipeline installlation tend to d to rotate while w trave eling t through the e sagbend. The seve erity of the rotation r inccreases witth the level of b bending strain introdu uced in the e overbend d and the suspended pipeline length i the sagb in bend. The rotation r ca an howeverr be counte eracted effe ectively by a applying an n external moment to o the system m. A common nly applied measure to ensure vvertical insttallation of in-line is to conne s structures ect a buoya ancy modu ule via a yo oke on top o of the pipe eline. I the pipe and thus yyoke rotates, an up-rig If ghting mom ment is cre eated and this r reduces the rotation to t an acceptable ang gle. The anti-ro T otation arra angement ffor the Pola arled pipeline (see Fig gure 7.3) c consisted o of an 8 m long yoke w with an 8 t buoyancy for the sing gle ILTs, and 11 t of buo oyancy per yoke for th he dual ILT T, as follow ws: • One arrangemen a nt at appro oximately 275 m in fro ont of the centre c of the ILT. • One arrangemen a nt at appro oximately 75 m behind d the centrre of the ILT T. T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 14 Installation challe enges - Polarled pipeline e project Figure 7.3 3 – Anti-rotatiion arrangem ment The anti-ro T otation arra angement a as describe ed above g generated tthe followin ng asi installed co onditions p presented in n Table 7.2 2. Table 7 7.2- ILT rotatiions on seab bed [deg] ILT An nalysed Acttual Dual Victoriia Zidane n Kristin Drauge en 1.4 -0.11 1.7 -1.71 -0.18 +2.08 -1.17 Figure 7.4 – In-lin ne double tee e assembly including anti-rotation arra angements T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 15 Installation challe enges - Polarled pipeline e project 7.3. Installation of dual d ILT T dual IL The LT length w was greate er than the distance between two o tensioners a therefo and ore, it was necessaryy to open tw wo tensioners simulta aneously, r resulting in n the pipelin ne being held by one e tensioner only. Figu ure 7.5 – Passage of dual ILT through tensioners Due to the tension levvels (staticc tension off 186 t and D d dynamic ttension of 286 2 t a Hs of 3 m), at m it was already a known that S Solitaire wo ould have ssufficient c capacity to o hold the P Polarled pip peline with only one ttensioner. However, iin order to minimise tthe risk of p H pipe slippa age, some safety s were taken m measures n. The major safeguard was to continuously monitor th T he tension levels l durin ng t transfe the er of the dual ILT to th he beadsta all, the weld ding of the dual ILT to o the p pipe string and before e opening the tension ners. IIn case of any indicattion of an increase in the tensio on, an A&R R head wou uld be i introduced to the system to tran nsfer loadss from the tensioners to the A&R R w winch and accordinglly increase e the cumulative holdiing capacitty. H However, d during the actual installation of tthe dual IL LT, it was fo ound that the t t tension wa as well belo ow the sing gle tensione er capacityy and there efore installation o an A&R head was not require of ed. 8. Laydown L n onto th he FSP att Aasta H Hansteen n 8.1. Generral descrip 8 ption T Polarle The ed laydown n operation n was the d deepest 36 6-inch pipeline laydow wn o operation e ever perforrmed by an ny pipelay ccontractor. The waterr depth at tthe l laydown ta arget box w was 1,265 m m. The layd down operration at Aa asta Hanste een s started at a approximattely 7.5 km m before the e laydown location in a water de epth T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 16 Installation challe enges - Polarled pipeline e project of 1170 m, where the o e first transsponder wa as attached d to the pip peline and tthe t transponde er location relative to the laydow wn target box b was me easured ussing t LBL array. This to the o calculate the remain ning pipelin ne length a and to d determine the length required fo or the cut-tto-length jo oint. Figurre 8.1 - Impre ession of pipeline and layydown conne ector landing on the FSP The laydow T wn operatio on was perrformed byy means of a so-called d collet c connector, designed and fabrica ated by Fre eudenberg g (Vector C Co.), locked d onto a special la aydown joint. The layydown conn nector had a total length of 6.3 m, a m maximum d diameter of o 1920 mm m and a dryy weight of 24.5 t. Figure 8.2 - Layydown conne ector and layd down joint 8 8.2. Shroud design n A compreh hensive ana alysis was performed d for the de esign of the e protection n s shroud, wh hich would compensa ate the effe ect of rollerbox loads o on the systtem, c caused by the large o offset betw ween the bo ottom of the e pipeline and a the bo ottom o the laydo of own conne ector, and ffacilitate sm mooth passsage of the e laydown c connector over the sttinger and firing line d during both h the laydown operatiion a a pote and ential contin ngency reccovery. T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 17 Installation challe enges - Polarled pipeline e project Figurre 8.3 - Laydo own shroud Several de S esign limitations were taken into o account w which are ssummarised d b below: • The la arge weightt of the layydown conn nector and shroud asssembly at the end off the pipe string s would d lead to in ncreased sstresses at the connection betwe een the pipe eline and the connecctor. Thereffore, the lim mitation of the weight of the shrroud was a an importan nt considerration in the e design. Additio onally, afte er completio on of the la aydown op peration, the shroud w would be rem moved from m the laydo own connecctor and re ecovered by a separa ate ROV vvessel. Inccreasing the e weight off the shroud would ha ave a direcct impacct on this op peration. hroud would experien nce a large e reaction fforce from the rollerbo oxes • The sh and th herefore req quire sufficcient streng gth. The strengthenin ng of the sh hroud was achieved byy increasing g the thickness of the e plates. Ass discusse ed above e, optimisattion betwee en weight a and strength was an issue due to the ressulting high h stress on n the pipe. • Mountting of the shroud ove er the pipeline and laydown con nnector wa as also cconsidered a constrain nt. In Solita aire’s bead dstall there e is a space e of neral, rollerguides ca an be approxximately 5 m between the rollerrs so in gen easily installed. However, H d due to the dimensions of the co onnector, th he shroud d had a len ngth of app proximatelyy 9 m and ttherefore th he decision n was made to design a four-partt shroud. The modified four-partt shroud de esign onsiderablyy and, as a conseque ence, improvved the insstallation effficiency co limited d the opera ational time e. T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 18 Installation challe enges - Polarled pipeline e project • Severral lift pointss had to be e installed on the shro oud for easse of recovvery by an ROV vesssel. 8.3. Cut-tto-length m 8 measurem ment C Common p practice forr measuring g the cut-to o-length for hitting a ttarget box is to u surveyy equipmen use nt such as transponde ers in an L LBL array. T The distancce b between th he transpon nders and centre of th he target b box can be calculated d u using the a array. In ad ddition, durring the fina al approach the exact length of each p pipe joint iss measured by laser and, accorrdingly, the e required length for the c cut-to-leng gth joint is calculated. c Figure 8.4 - Cut to leng gth measurem ment using survey equipm ment On the Pollarled proje O ect, the abo ove method dology had d some ope erational rissks d to the following: due • A veryy tight longitudinal tolerance of ± ±1.5 m, considering a suspende ed pipe le ength of 3,800 m (312 2 pipe jointts), needed d to be acccounted forr. • Althou ugh the LBL array is a an accurate e survey syystem, som me tolerancces had to o be taken into account. • Joint length mea asurement errors as small s as 5 mm per joiint would re esult arget box. in missing the ta onmental fa actors such h as tempe erature cha anges, seab bed slopess, and • Enviro possib ble curves in the final pipeline approach ne eeded to be b accounte ed for. Hence, in o H order to en nsure the la aydown con nnector of the Polarle ed pipeline e l landing on the pre-insstalled FSP P within the e specified d longitudin nal tolerancces, t decisio the on was mad de to perfo orm an intermediate A A&R operattion a approxima tely 150 m before the e FSP, usin ng the avaiilable A&R R head. Thiss e enabled a final checkk of the rela ative position and the e required length of th he c cut-to-leng gth joint. T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 19 Installation challe enges - Polarled pipeline e project 8 8.4. Pass sage throu ugh the ten nsioner For the layydown operration, the tension ha F ad to be tra ansferred frrom the t tensioners to the A&R R winch an nd the tenssioners had d to be ope ened in orde er to a allow for th he laydown n connectorr to pass th hrough. However, w H with tensioners in the e open position, the p pipe string ccan be lifte ed off t rollerbo the oxes due to o its stiffne ess and the e shape of the catena ary. The de eep w water sectiion of the 36-inch 3 Polarled pipeline had a wall thickn ness of 3 34.6 mm, w which can be conside ered to be a very stiff pipe. In orrder to mod del t lift off, sseveral analyses werre performe the ed using F FE software e. The m maximum cclearance between th he pipe botttom and th he rollers ju ust before the was calcu t tensioners ulated to be e maximum m 10 cm. A geometryy check wa as performed and it w was concluded that no o clashing w would occu ur during th he passage e of the layydown conn nector thro ough the t tensioners . 8.5. Stinge 8 er tip clearance A Allseas’ pip pelay insta allation philosophy is b based on m maintaining g a separattion o at least 0.3 m betw of ween the piipeline and d the stinge er tip at all times. Durring l laydown an nd/or any abandonme a ent and reccovery ope eration, half the OD size of p pipe is to b be added to o the above e mentione ed criterion n in order to o model the e c cable in the e laydown analysis in n a correct manner. Therefore, T t keep the to e s stinger tip clearance during the passage of o the large e OD laydo own connecctor, t tension the n level wou uld have to be increassed prior to o the laydown connecctor l leaving the e stinger. H However, ffor this layd down, the stinger s tip clearance was achievved by rota ating t stingerr downward the d when the e connectorr had reach hed rollerbox no. 7, while w m maintaining g the same e tension. Figure 8.5 - Impression of o stinger rotation during laydown ope eration T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 20 Installation challe enges - Polarled pipeline e project 8 Final laydown and 8.6. a recove ery of the laydown rrigging Following tthe landing F g of the laydown joint in the forkk on the FS SP the laydown c connector was only 0 0.5 m off ta arget. F Figure 8.6 - A As-installed p position on th he FSP The Polarle T ed pipeline e laydown w was performed using a 500 t rig gging set. This T r rigging wass to be discconnected by an ROV V. In orderr to preventt this heavyy r rigging hitting the FSP, after confirmation of the succcessful laydown, Soliitaire m moved aste ern toward ds the FSP while retrieving the A A&R cable. When the e R ROV cut th he sacrificia al sling, it was w ensure ed that the A&R was in a vertica al p position an nd without any a slack, preventing g the rigging to drop on o the FSP P. F Figure 8.7 – R Recovery of Solitaire S A&R cable 9. Conclus C ions IInstallation n of the reccord-breaking Polarled d pipeline w was complleted in a ssingle s season witthout encou untering an ny major co ontingencie es or safetty issues. S Some c challenges s were enco ountered, a and overco ome, during g the installation e engineerin g and execcution phasses. T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 21 Installation challe enges - Polarled pipeline e project Allseas devveloped methodologiies, as brie A efly describ bed in this p paper, in order t successsfully installl the Polarlled pipeline to e, one of th he toughesst subsea p pipeline pro ojects everr carried ou ut, in a watter depth never n beforre reached with t this the pip pe diameter. The main ffactors con T ntributing to o the succe ess of the p pipeline insstallation were: w • Develo opment of a well-plan nned installlation strattegy, which h reduced tthe producction time and lowere ed the overrall cost; • Effective commu unication w with all partiies involved in finding g the best ons, while taking t into account sa afety, operrational cosst and solutio installa ation sched dule; • Implem menting co omprehenssive risk asssessmentss with all pa arties involved and th he proper u utilisation o of risk mitigation mana agement in n order to achievve the high hest safety class for th his project.. 10. Ackno owledgm ments The authorrs on behalf of Allsea T as and Stattoil would liike to thank all the c companies s involved iin the proje ect for theirr contributio on to the success s of the P Polarled prroject. 11. Referen nces 1- DNV-R RP-F107, 2 2010, Riskk assessme ent of pipeline protecttion 2- Endal,G., Ness, O.B., Verle ey, R., Holte, K., Rem mseth, S., ““Behaviourr of Offsho ore Pipeline es Subjectted to Residual Curva ature Durin ng Laying”, Paperr, 1995 OM MAE - Volum me V. T 2016 OPT Sam man Dabighi – Arne Foss se 5, 2016 Febrruary 24 & 25 Page 22