Guide to the Code for Assessment, Repair, and Rehabilitation of Existing Concrete Structures University of Toronto User. @Seismicisolation @Seismicisolation MNL-3(20) Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. An ACI / ICRI Manual A Companion to ACI 562-19 Guide to the Code Requirements for Assessment, Repair, and Rehabilitation of Existing Concrete Structures ACI MNL-3(20) Third Edition Updated by Khaled Nahlawi, ACI Distinguished Engineer, under the review and approval of an ACI/ICRI review group consisting of Chair Keith E. Kesner and members Tarek Alkhrdaji, Eric L. Edelson, and Fred R. Goodwin Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 1 University of Toronto User. @Seismicisolation @Seismicisolation Guide to the Code Requirements for Assessment, Repair, and Rehabilitation of Existing Concrete Structures ACI MNL-3(20) Third Edition First Printing: November 2020 ISBN: 978-1-64195-121-0 Copyright © 2020 by the American Concrete Institute and the International Concrete Repair Institute. All rights reserved. Managing Editor: Khaled Nahlawi, PhD, PE Art Program: Claire Hiltz Photo Editor: Ken Lozen, FICRI, FACI Director, Events and Publishing Services: Lauren E. Mentz Production Editors: Kaitlyn J. Dobberteen, Tiesha Elam, Hannah Genig, Kelli R. Slayden Page Design & Composition: Ryan Jay Front cover photos: copyright 2010 Mark Johnson Photography Manufacturing: Marie Fuller Printed in Eau Claire, WI American Concrete Institute 38800 Country Club Drive Farmington Hills, MI 48331 USA www.concrete.org @Seismicisolation @Seismicisolation University of Toronto User. International Concrete Repair Institute 1000 Westgate Drive, Suite #252 St Paul, MN 55114 USA www.icri.org Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 2 On the Cover Inspection and Evaluation Together with the Houston Fire Department, the Engineer performed an initial visual review. The extent of the fire damage was confined within the two bays adjacent to the garage expansion joint on the east side. Shoring and cleaning requirements for the damaged members were provided on-site on April 26, 2018, the same day that the fire occurred. Available background information and plans were reviewed, and a follow-up visual assessment of the damage was conducted on May 2, 2018. Prior to the second visual evaluation, the structural members within the fire-damaged area were cleaned using dry ice blasting that allowed a closer look at the extent of the damage. Fig. 1—University of Houston East Garage Fig. 2—Fire damage on Level 3 of parking garage Fig. 3—Fire damage at exterior of garage @Seismicisolation Fig. 4—Shoring installed in affected areas @Seismicisolation University of Toronto User. University of Houston East Garage Fire Emergency Response 2019 ICRI Award of Excellence – Parking Structures Category The following summary is taken from the November/December 2019 issue of the ICRI Concrete Repair Bulletin. The University of Houston’s 2006 Campus Framework Plan included the addition of parking spaces to accommodate the growing population of students. The East Garage was designed to meet the needs of students, faculty, visitors, and residents of the nearby campus lofts (Fig. 1). Utilizing a “double zero” ramp configuration, the garage was designed to have “nested” visitor parking with the capability to use the upper levels for overflow parking. In April 2018, a multiple-vehicle fire occurred on the third level of the four-level University of Houston East Garage (Fig. 2). Significant structural damage occurred to two columns, the framing of the level above, and the exterior signage (Fig. 3). Before a survey of the damage could be completed, shoring was installed as a precaution to prevent the possible collapse of damaged members (Fig. 4). Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 3 Fig. 7—Spandrel beam replacement Site Preparation, Demolition, and Repairs Repairs included replacement of members that experienced severe distress, along with localized repairs of members with moderate or minor distress. Repair drawings were issued on June 1, 2018. Once mobilization took place, the perimeter of the precast double tees was saw-cut, creating separation of each member to be replaced prior to removal. In preparation of hoisting the existing damaged precast double tees, cores were drilled at each of the four pick points, allowing a sling to be wrapped around the stem for each double tee. A 350 ton (317,500 kg) crane was used to bring down each damaged precast double tee, with a total of six removed and four new double tees reinstalled. Two of the damaged double tees were found to be salvageable after removal. These @Seismicisolation members were temporarily placed on the ground, repaired, and @Seismicisolation University of Toronto User. In addition to visual observations, a limited floor delamination survey was performed utilizing a chain dragging device to detect unsound concrete. An acoustical monitoring wheel and hammer sounding was used to detect delaminated concrete on the vertical and overhead elements. Concrete testing was performed (compressive strength and petrographic examination) and nondestructive evaluation (NDE) methods were used to determine the severity of damage and repair approach. NDE methods included ground-penetrating radar (GPR) survey, ultrasonic pulse velocity (UPV) testing, and pulse-echo scanning (Fig. 5). The visual reviews and delamination survey indicated that fire-related Fig. 5—Nondestructive testing performed at damaged column distress had occurred in the form of concrete cracking and spalling, including delaminations identified in several crucial structural beams and columns (Fig. 6). The concrete distress was more severe at members near the expansion joint. Core compressive strength testing did not show degradation of compressive strength as a result of the fire event. However, the petrographic examination of the concrete cores indicated the extent of surficial concrete damage as a result of exposure to fire-elevated temperatures was up to a depth of 0.4 in. (10 mm). Significant carbonation and cracking were also observed in several core samples and correlated with the Fig. 6—Concrete cracking and spalling due to fire NDE (UPV and pulse echo) results at multiple locations at each structural member. GPR scanning of cracked doubletee beams with significant longitudinal cracking showed that these cracks were located along the prestressing strands, thus indicating possible debonding between the strand and concrete with subsequent reduction in structural capacity. The petrographic examinations also indicated that the concrete members were exposed to elevated temperatures up to 1400°F (800°C). Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 4 reinstalled in their original position. Two spandrel beams were hoisted down, removed from the site, and replaced with new members (Fig. 7). New replacement double tees were hoisted into place for final repairs (Fig. 8). Other repair works included the repair of concrete columns supporting Level 4 (Fig. 9), spandrel beams on Levels 3 and 4, double-tee members on Level 4, topping slab replacement on Level 3, and waterproofing installation on Levels 3 and 4. The damaged expansion joint system on Level 3 was replaced and a new expansion joint system was installed on Level 4. Joints were tooled in the topping slab and sealed above the double-tee flange-toflange joints, and construction joints were routed and sealed. Cove sealant was installed at the perimeter bumper wall and columns. Fig. 8—New replacement double-tee beams at completion Logistics The public garage proved to be a limited-space jobsite, leaving little room for repair materials and contractor use/laydown. While complexities were abundant, the project team worked efficiently to have the garage fully operational by the start of the fall semester. Ultimately, the team was able to come in under budget and ahead of schedule on repairs. Fig. 9—Column during repair (left) and after repair (right) University of Houston East Garage Fire Emergency Response OWNER University of Houston Houston, TX PROJECT ENGINEER/DESIGNER Walter P Moore & Associates, Inc. Houston, TX REPAIR CONTRACTOR United Restoration and Preservation Houston, TX MATERIALS SUPPLIER/MANUFACTURER BASF Houston, TX @Seismicisolation @Seismicisolation University of Toronto User. Safety Emergency shoring addressed the initial safety concerns for assessing the damage and reduce the threat of a possible collapse. With student finals around the corner at the University of Houston, it was understood that the East Garage would need to remain in use on all undamaged levels. This presented another challenge to the construction team: safely making localized repairs to damaged elements with limited intrusion to occupants while considering the safety. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 5 Acknowledgments edition of the repair code, “Code Requirements for Assessment, Repair, and Rehabilitation of Existing Concrete Structures (ACI 562-19) and Commentary,” and this guide corresponding to the new repair code, have been updated to address comments received from users. The major revisions in ACI 562-19 are as follows: (a) Text was added to simplify use of new materials that have the equivalent of an ICC-ES evaluation report in Chapter 1. (b) The requirements for the basis of design report were simplified in Chapter 1. (c) Clarified requirements related to detailing of existing reinforcing steel in Chapter 7. (d) The commentary in Chapter 8 was updated to include a listing of exposure categories that may affect durability. This edition contains updated chapters to reflect the changes in ACI 562-19, updated Examples 1 through 5, three new examples (Examples 6 through 8), and a new Appendix B, which provides an overview of the new “Specifications for Repair of Concrete in Buildings (ACI 563-18).” “Vision 2020: A Vision for the Concrete Repair, Protection and Strengthening Industry” was published in 2006 with the facilitation of the Strategic Development Council (SDC) (a council of the ACI Foundation). One goal in Vision 2020 was the development of a concrete repair code. SDC also called for the development of documents in a more expedient manner than typically achieved in the volunteer committee development process. Their support of these goals continues with this document. ACI and ICRI would like to thank SDC for their vision in calling for the development of a concrete repair code and for providing financial support toward the development of the first two editions of this guide. Finally, ACI and ICRI would like to thank the review group for this guide consisting of Chair Keith E. Kesner and members Tarek Alkhrdaji, Eric L. Edelson, and Fred R. Goodwin. Their careful review and dedication to the project on top of all their other volunteer time for both Institutes made it possible to develop and revise this guide in a timely manner while maintaining the quality expected by the industry. Khaled Nahlawi Managing Editor @Seismicisolation @Seismicisolation University of Toronto User. The development of “Code Requirements for Evaluation, Repair, and Rehabilitation of Concrete Buildings (ACI 562-13) and Commentary” and the first edition of the “Guide to the Code for Evaluation, Repair, and Rehabilitation of Concrete Buildings” were major milestones in the concrete repair industry. Prior to the publication of these documents in 2013, the industry lacked code requirements specific to the repair of concrete buildings, leading to inconsistent repair practices. To provide guidance to the repair community, yet maintain the flexibility necessary to address widely varying conditions, many of the repair code requirements took the form of performance requirements rather than the prescriptive requirements seen in many other concrete industry codes. Because of the performance nature of the requirements, however, there was significant room for interpretation when deciding whether a particular code requirement had been met. Early in the development of ACI 562-13, the need was recognized for a document that would provide guidance and examples to assist engineers in understanding how to satisfy the Repair Code requirements. This was particularly important considering that ACI 562 was a new code that engineers would be using for the first time and with which they would have no prior experience. The second edition of the repair code, “Code Requirements for Assessment, Repair, and Rehabilitation of Existing Concrete Structures (ACI 562-16) and Commentary,” and corresponding guide to the repair code, were updated to address comments received from these first-time users. Chapters 1 and 4 were reorganized and properly defined the difference between evaluation and assessment. A new section in Chapter 7 addressed bond interface between an existing concrete substrate and a new concrete overlay. Appendix A was added to provide requirements in cases where a jurisdiction has not adopted a repair code, allowing ACI 562-16 to be used as a stand-alone code. If a jurisdiction had adopted a repair code, then the licensed design professional must use Chapter 4. For the third edition of the repair guide, examples were updated to reflect the changes in ACI 562-19. The current Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 6 Preface University of Toronto User. Introduction to the ACI 562-19 Code ingly, while ACI 562 currently defines the standard for the Advancements in the practice of assessment, repair, rehabiliconcrete assessment, repair, and rehabilitation industry, the tation, and strengthening of concrete structures have developed code provisions of ACI 562 will likely then become mandathrough a collaboration of design professionals, contractors, tory requirements as part of the governing building codes suppliers, manufacturers, researchers, educators, and lawyers. that regulate work in existing buildings. The annual cost to owners for repair, protection, and strengthening of existing concrete structures is estimated between $18 Overview of the guide to ACI 562 Code content and $21 billion (Vision 2020). Simply put, even sound concrete The primary purpose of this guide is to help licensed design may require repair, rehabilitation, maintenance, or strengthprofessionals (LDPs) gain more knowledge, skill, and judgening throughout the service life of a structure. Accordingly, ment to interpret and properly use the ACI 562 Code. Although from 2004 to 2006, the Strategic Development Council (SDC), specifically developed for LDPs, this guide also provides an interindustry development group dedicated to supporting the insight into the use and benefits of ACI 562 for contractors, concrete industry’s strategic needs, facilitated the development material manufacturers, and building owners and building of “Vision 2020: A Vision for the Concrete Repair, Protection, officials. To achieve this goal, the guide is separated into three and Strengthening Industry” to establish a set of goals that main components: Chapter Guides including Appendix A, would improve the efficiency, safety, and quality of concrete Project Examples, and Appendix B, providing an overall view repair and protection activities. One of the goals established by of the new standard, ACI 563, “Specifications for Repair of Vision 2020 was to create a concrete repair and rehabilitation Concrete in Buildings.” code by 2015. The ACI 562-13 standard, “Code Requirements The Chapter Guides and Project Examples are provided in for Evaluation, Repair, and Rehabilitation of Concrete Buildtandem for clarity and understanding of the relative portions ings and Commentary,” is the end result of that initiative. ACI of ACI 562 Code. The Project Examples illustrate the process 562-19 is the third edition of the Code with revisions, additions, of carrying out a concrete building assessment, repair, rehaand reorganized information to enhance the Code, providing bilitation, or strengthening project from inception through more clarity and additional, updated information to assist the completion. This guide, including the Project Examples, is design professional. intended as a supplement to the ACI 562 Code and not as a The purpose of the ACI 562 Code is to provide minimum “how-to” manual for performing concrete assessment, repair, material and design requirements for the assessment, repair, rehabilitation, or strengthening. Several additional documents and rehabilitation of structural concrete members. Like other are referenced in ACI 562 Commentary and this guide to assist ACI codes, ACI 562 is organized in a dual-column format, in evaluating the various options and approaches to performing with mandatory code provisions to the left of each page, successful concrete assessment, repair, rehabilitation, or and nonmandatory commentary to the right to provide addistrengthening projects. The intent of each Project Example is tional guidance and information on the content presented in not to be a prescriptive formula for each of the project scenarios the Code provisions. Unlike other ACI standards, ACI 562 presented, but to illustrate how various sections of ACI 562 includes both prescriptive and performance requirements. are applied together to execute the project. For convenience, The performance requirements provide great latitude and related provision numbers from ACI 562 are given at the top flexibility to the licensed design professional in satisfying of each corresponding paragraph of the project example text. the requirements of ACI 562. Accordingly, ACI 562 serves to Eight Project Examples are included within the guide: unify and strengthen concrete assessment, repair, and rehabili1. Typical parking structure repairs tation projects while accommodating the diverse and unique 2. Typical façade repairs strategies and materials used in the industry. 3. Repair of historic structure for adaptive reuse In general, the overall use and function of ACI 562, with 4. Strengthening of two-way flat slab respect to existing concrete structures, can be compared to that 5. Strengthening of double-tee stems for shear of ACI 318-19, “Building Code Requirements for Structural 6. Concrete beam repair by section enlargement Concrete and Commentary,” with new concrete construction. 7. Concrete repair by steel jacket As with ACI 318 and the 2018 International Building Code 8. Beam repair with fire protection analysis: (2018 IBC), plans are underway for ACI 562 an ANSI stana. Beam strengthening due to live load increase dard, to be adopted into the International Existing Building b. Beam with inadequate existing concrete cover Code (IEBC) to address matters pertaining to assessment, In the third edition of this repair guide, a new chapter, repair, rehabilitation, and strengthening of concrete members Appendix B, was added to address specifications. This is within existing buildings. Local jurisdictions and building another goal by Vision 2020 to create a concrete repair specauthorities can also adopt ACI 562 directly. Cities and states ification standard. The ACI 563-18 standard, “Specification have both adopted ACI 562 and adopted use of ACI 562 on for Repair of Concrete in Buildings,” is a reference stanspecific projects. Other jurisdictions are in the process of dard that the LDP can apply to any construction repair and reviewing the Code for consideration and adoption. @Seismicisolation Accordrehabilitation project involving structural concrete by citing @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 7 repair and rehabilitation for varying levels of damage, deterioration, or faulty construction. Load combinations in Chapter 5, which define the minimum strength of a structure with unprotected external reinforcement, were revised. Chapter 6 directs the LDP to provide an assessment before rehabilitation of an existing structure. This chapter includes historical material property data to help the design professional in the assessment if existing documents related to the existing structure are not available or physical samples cannot be extracted, because of the historical value of the structure. The interface bond provisions in Chapter 7 were revised to provide specific requirements based on shear test, as well as when to provide interface reinforcement, and commentary in Chapter 8 was clarified. The third edition of ACI 562, published in 2019, has: (a) Added text to simplify use of new materials that have the equivalent of an ICC-ES evaluation report in Chapter 1; (b) Simplified the requirements for the basis of design reported in Chapter 1; (c) Clarified requirements related to detailing of existing reinforcing steel in Chapter 7; and (d) Updated commentary in Chapter 8 to include a listing of exposure categories that may affect durability. In addition, three new repair examples are added to demonstrate the flexibility of the Code and its applicability to different repair and strengthening methods. Example 6 is related to concrete beam repair by section enlargement, Example 7 addresses concrete frame strengthening by steel jacketing, and Example 8 focuses on the effect of fire on concrete members and possible protection based on two scenarios: scenario one—concrete structure subjected to increase in live load; and scenario two—reinforcement with low concrete cover. Lastly, a summary of the various provisions of ACI 562, as well as the corresponding location where each provision is covered within the guide, is provided in the Provision Coverage Matrix at the end of this guide. This serves as a useful tool when searching for additional information to a specific provision of ACI 562. @Seismicisolation @Seismicisolation University of Toronto User. it in the Project Specifications. It provides direction to the contractor and clearly defines the responsibilities and scope of the repair, rehabilitation, or strengthening. The specifications detail the work, material, and installation required to complete a project the way the client wants. The Chapter Guides follow the general organization of ACI 562, broken down by the corresponding sections of ACI 562. Section numbers in Chapters 1 to 10 and Appendix A of this guide correspond to the provision numbers in ACI 562. The Chapter Guides include background information and an explanation of the various ACI 562 provisions, with particular insight into how the particular chapter and section of the Code fit within the project. Where applicable, flowcharts are provided to illustrate how to navigate the various provisions of ACI 562. References to Project Examples are provided where applicable to illustrate how specific provisions within each chapter of ACI 562 are incorporated into the design process. In some instances, additional limitedscope examples are included to better illustrate a point that is not covered by the Project Examples. The first edition of ACI 562 was published in 2013, and was not available when the work for the projects discussed in the Project Examples was actually performed. All Project Examples assume that ACI 562 was available and accepted by local jurisdiction when the example projects were performed. The second edition of ACI 562, published in 2016, includes additional definitions used in the Code for consistency with 2018 IEBC and other similar standards for existing structures. The title of ACI 562-16 was changed by replacing the word “Evaluation” with “Assessment.” The two terms, which are used interchangeably by other standards and the first version of this Code, have received distinct definitions in the second edition of ACI 562 (Stevens et al. 2016). Specific criteria requirements for assessment and design of repair and rehabilitation for varying levels of damage, deterioration, or faulty construction was added in Chapter 4 when using the Code with IEBC, and in Appendix A when using the Code as a stand-alone code. Chapters 1 and 4 were revised to include specific criteria requirements for assessment and design of Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 8 Contents Acknowledgments 6 Preface 7 About This Book 12 Chapter 1—General Requirements 1.1—General 1.2—Criteria for the assessment and design of repair and rehabilitation of existing concrete structures 1.3—Applicability of the Code 1.4—Administration 1.5—Responsibilities of licensed design professional 1.6—Construction documents 1.7—Preliminary assessment 13 13 Chapter 2—Notation and Definitions 2.1—Notation 2.2—Definitions 19 19 19 Chapter 3—Referenced Standards 21 14 15 16 16 16 16 Chapter 5—Loads, Factored Load Combinations, and Strength Reduction Factors 31 5.1—General 32 5.2—Load factors and load combinations 33 5.3—Strength reduction factors for repair design 33 5.4—Strength reduction factors for assessment 33 5.5—Additional load combinations for structures rehabilitated with external reinforcing systems 34 37 37 38 40 Chapter 7—Design of Structural Repairs 7.1—General 7.2—Strength and serviceability 7.3—Behavior of repaired systems 7.4—Interface bond 7.5—Materials 7.6—Design and detailing considerations 7.7—Repair using supplemental post-tensioning 7.8—Repair using fiber-reinforced polymer (FRP) composites 7.9—Performance under fire and elevated temperatures 47 47 47 48 49 57 57 58 44 45 45 45 46 46 59 60 Chapter 8—Durability 8.1—General 8.2—Cover 8.3—Cracks and deterioration of reinforcement and metallic embedments 8.4—Corrosion 8.5—Surface treatments and coatings 61 61 62 Chapter 9—Construction 9.1—General 9.2—Stability and temporary shoring requirements 9.3—Temporary conditions 9.4—Environmental issues 65 65 65 66 68 Chapter 10—Quality Assurance 10.1—General 10.2—Inspection 10.3—Testing of repair materials 10.4—Construction observations 69 69 70 70 70 @Seismicisolation @Seismicisolation 62 63 64 University of Toronto User. Chapter 4—Basis for Compliance 23 4.1—General 23 4.2—Compliance method 24 4.3—Potentially dangerous structural conditions 25 4.4—Substantial structural damage 26 4.5—Conditions of deterioration, faulty construction, or damage less than substantial structural damage 26 4.6—Conditions of deterioration, faulty construction, or damage less than substantial structural damage without strengthening 30 4.7—Additions, 4.8—Alterations, 4.9—Changes in occupancy 30 Chapter 6—Assessment, Evaluation, and Analysis 6.1—Structural assessment 6.2—Investigation and structural evaluation 6.3—Material properties 6.4—Test methods to determine or confirm material properties 6.5—Structural analysis of existing structures 6.6—Structural serviceability 6.7—Structural analysis for repair design 6.8—Strength evaluation by load testing 6.9—Recommendations Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 9 Chapter 11: Commentary References 71 Appendix A—Criteria When Using ACI 562 as a Stand-Alone Code 73 A.1—General 73 A.2—Design-basis code criteria 73 A.3—Potentially dangerous structural conditions 75 A.4—Substantial structural damage 76 A.5—Conditions of deterioration, faulty construction, or damage less than substantial structural damage 76 A.6—Conditions of deterioration, faulty construction, or damage less than substantial structural damage without strengthening 78 A.7—Additions 79 A.8—Alterations 80 A.9—Changes in occupancy 82 Project Examples 104 Chapter 13: Project Example 2—Typical Façade Repair 121 Description of structure 121 Project initiation and objectives 122 Governing building codes 122 Preliminary observations and assessment 123 Observed concrete conditions 124 Laboratory findings 125 Findings 125 Structural assessment and repair design 126 Shear wall reveal strip repairs 126 North and south walls away from reveal strips and east and west slab and column edges 128 Balcony repairs 128 Performance under fire and elevated temperatures 130 Contract specifications 130 Construction 131 Quality assurance 131 Project close-out 132 Periodic maintenance 132 Record documents 132 @Seismicisolation @Seismicisolation University of Toronto User. Appendix B—Repair Guide 83 General 83 Section 1—General requirements 83 General procedures 84 Preinstallation conference 84 Quality assurance, quality control, testing, and inspection 85 Quality assurance (QA) 85 Advantages of quality assurance 87 Disadvantages of quality assurance 87 Quality control (QC) 87 Advantages of quality control 87 Disadvantages of quality control 87 Testing and inspection 88 Section 2—Shoring and bracing 90 Section 3—Concrete removal and preparation for repair 91 Section 4—Formwork 94 Section 5—Reinforcement and reinforcement supports 97 Section 6—Conventional concrete mixtures 99 Section 7—Handling and placing of conventional concrete 101 Section 8—Proprietary cementitious and polymer repair materials 102 Sections 9 and 10 102 Notes to Specifier (nonmandatory) 102 Checklists 102 Chapter 12: Project Example 1—Typical Parking Structure Repair 105 Description of structure 105 Project initiation and objectives 105 Governing building codes 106 Preliminary assessment 107 Investigation of existing site conditions 107 Capacity and demand of existing structure 108 Findings of preliminary assessment 108 Area 1 109 Area 2 111 Report to owner 113 Structural Assessment 113 Existing conditions 113 Structural analysis for repair design 114 Area 1 115 Area 2 115 Design of structural repairs and durability 116 Slab Area 1 116 Slab Area 2 and columns 117 Slab soffit repairs 118 Construction specifications 118 Construction 119 Quality assurance 119 Project close-out 120 Periodic maintenance 120 Record documents 120 Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 10 Chapter 14: Project Example 3—Adaptive Reuse of Historic Depot 133 Description of structure 133 Project initiation and objectives 134 Governing building codes 134 Preliminary observations and evaluation 135 Concrete conditions 135 Material evaluation findings 137 Summary 137 Structural assessment 138 Requirement for structural assessment 138 Existing properties 138 Structural analysis 138 Structural analysis findings 139 Recommended repair program 140 Train deck rehabilitation 140 Column rehabilitation 142 Concrete repair details 144 Contract specifications 146 Construction 148 Quality assurance 148 Project close-out 148 Periodic maintenance 148 Record documents 148 149 149 149 149 150 150 150 150 153 154 154 154 155 155 155 155 156 157 159 160 163 163 163 163 167 168 168 168 169 169 169 170 171 171 171 171 173 173 173 174 176 176 176 177 177 178 179 179 179 180 181 181 182 182 182 182 183 183 186 186 186 Chapter 17: Project Example 6—Concrete Beam Repair by Section Enlargement 187 Description of structure 187 Project initiation and objectives 187 Governing building code 188 Structural assessment 189 Structural analysis 189 Repair options 190 Design of repairs 191 Durability of repairs 192 Contract documents 193 Construction specifications 193 Construction 193 Quality assurance/construction observations 193 Project Close-out 194 Periodic maintenance 194 Record documents 194 @Seismicisolation @Seismicisolation University of Toronto User. Chapter 15: Project Example 4—Parking/Plaza Slab Strengthening Description of structure Project initiation and objectives Governing building codes Preliminary evaluation Document review Existing site conditions Strength of as-built structure Compliance method and design-basis code Structural assessment Requirement for structural assessment Structural assessment Structural analysis Strengthening concepts Strengthening Concept 1 Strengthening Concept 2 Assessment of strengthening concepts Structural analysis for repair design Design of structural repairs and durability Contract specifications Construction Quality assurance Load test Test procedure Test results Project close-out Periodic maintenance Record documents Chapter 16: Project Example 5—Precast/ Prestressed Double-Tee Repair Description of structure Project initiation and objectives Governing building codes Preliminary assessment Existing site conditions Design strength of existing structure Findings of preliminary assessment Design-basis code Structural evaluation Existing site conditions Structural analysis for evaluation Structural safety Repair/replacement options Repair/replacement Option 1 Repair/replacement Option 2 Repair/replacement Option 3 Repair/replacement Option 4 Evaluation of repair/replacement options Design of strengthening repairs Structural analysis for repair design Design of strengthening repairs Design of structural repairs and durability Development and bond of CFRP strips Acceptance of CFRP repairs by the authorities having jurisdiction Durability of repairs Aesthetics of repairs Contract specifications Construction Quality assurance Project close-out Periodic maintenance Record documents Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 11 Chapter 18: Project Example 7—Concrete Frame Strengthening by Steel Jacket 195 Description of structure 195 Project initiation and objectives 195 Governing building codes 196 Preliminary evaluation 196 Strengthening concepts 199 Structural analysis and repair design 199 Durability 200 Contract documents 200 Construction specifications 200 Construction 203 Quality assurance 203 Project close-out 204 Periodic maintenance 204 Record documents 204 Chapter 19: Project Example 8—Building Subjected to Fire Description of structure Project initiation, objectives, and remediation summary Governing codes Fire resistance rating calculations Contract specifications Construction Quality assurance Load test Test procedure Project close-out Periodic maintenance Record documents References Referenced Standards and Reports Authored documents 205 205 206 208 208 217 218 218 218 218 219 219 219 219 221 224 About This Book mance provisions of ACI 562. It does not, however, purport to represent the only suitable way to satisfy the requirements for every project. Engineering judgment must be applied to the unique requirements of individual projects. This edition added Appendix B, which provides an overall view of ACI 563-18, “Specifications for Repair of Concrete in Buildings.” @Seismicisolation @Seismicisolation University of Toronto User. The Chapter Guides in Chapters 1 to 11 and Appendix A of this guide correspond to the identically numbered sections of ACI 562-19, “Code Requirements for Assessment, Repair, and Rehabilitation of Existing Concrete Structures.” Related ACI 562 provision numbers are included at the top of each corresponding paragraph of the Project Example text in Examples 1 to 8. This Guide is intended to provide examples and guidance for how licensed design professionals may satisfy the perfor- Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 12 Structural strengthening of girders with carbon fiber-reinforced polymer (CFRP) at a bridge in Canada (Photo courtesy of KMo Foto on www.flickr.com) 1.1—General ACI 562 Code is written to the licensed design professional (LDP) and provides guidance and consistency when assessing, designing, repairing, and rehabilitating concrete structures. It is intended to supplement the International Existing Building Code (IEBC), as part of a locally adopted code governing existing buildings or structures, or as a stand-alone code for existing concrete structures. The intent of the Code is to address minimum safety requirements and provide some uniformity and standardization to the industry for assessing existing concrete structures. The requirements based on performance, which encompass the majority of the requirements in ACI 562 Code, direct the design professional to satisfy specific requirements, while providing some leeway, flexibility, and direction with the repair and rehabilitation of concrete structures. Concrete structures constructed before 1971 that require @Seismicisolation repair, rehabilitation, or strengthening were probably designed based on the @Seismicisolation 13 University of Toronto User. Overview Chapter 1 of ACI 562 specifies the applicability of ACI 562, including review of the various building codes that might affect the repair design, as well as selecting the building code for the repair design; applicability of the code; responsibilities of the licensed design professional including submittals to building officials and the owner; and development of maintenance recommendations. Chapter 1 also specifies the requirements for performing a preliminary assessment by examining the available information and determining if the proposed changes, imposed changes, or both, are safe, followed by how the structure will be affected by these changes. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 1—General Requirements GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES allowable stress approach, whereas the demand and capacity requirements of ACI 562 are based on strength design. The LDP is encouraged to consider strength design provisions of this Code as a check when assessing existing structures originally designed with allowable stress methods. An existing structure, as defined in Chapter 2, is one for which a legal certificate of occupancy has been issued, or one that is finished and permitted for use. If no certificate of occupancy has been issued, or the building has not been permitted for use, the building is still considered new construction, and existing design provisions of ACI 318 will govern. Licensed design professional—The LDP, as defined in the Code and consistent with ACI Concrete Terminology (CT), refers to an individual for a project who is licensed to provide design services as defined by the statutory requirements of professional licensing laws of the state or jurisdiction in which the project is to be executed, and who is in responsible charge of the structural assessment, rehabilitation design, or both. The LDP should exercise sound engineering knowledge, experience, and judgment when interpreting and applying ACI 562. University of Toronto User. building may undergo several alterations, additions, rehabilitations, repairs, or strengthening during its service life, spanning several code cycles, and more than one code type may have been applied. Therefore, the LDP should determine the original building code for each of the alterations, additions, rehabilitations, repair, or strengthening, during the preliminary assessment and apply the specific original code for the area where work will be done. There are cases of existing concrete structures where alterations, additions, rehabilitations, repair, or strengthening were completed prior to the adoption of a building code by the jurisdiction where the structure is located. The LDP should, in this case, research available standards and practices in effect at the time of construction. The Historic American Engineering Record, a program of the United States Park Service, has information on construction and preservation of historic structures (https://www.nps.gov/ hdp/haer/index.htm). In the U.S., the existing building code is most often based on an edition of the IEBC, which was first published in 2003. As of January 2016, the IEBC has been adopted in approximately 80 percent of the United States, Guam, and Puerto 1.2—Criteria for the assessment and design of Rico (International Code Council 2014). Chapter 34 of the repair and rehabilitation of existing concrete IBC, before the 2015 edition, also covers existing structures structures and has similar provisions as IEBC that permit the use of Determination of applicable building codes—Before the original code for rehabilitations, and when it is required performing an assessment, repair, rehabilitation, or strengthto upgrade an existing structure to the current code. Chapter ening of an existing concrete building or concrete structural 34 has since been deleted from the 2015 IBC. The intent of element, the LDP of the project should first determine the ACI 562 is that existing building code refers to the IEBC building codes applicable to the project, understand their releand not sections of other current building codes that contain vance to assessment and repair, rehabilitation, and strengthprovisions pertinent to existing construction. For jurisdicening design decisions, and the relationship between the tions that have not adopted an edition of the IEBC or the different standards. Per ACI 562, the LDP should identify the IBC with Chapter 34 version before 2015, that jurisdiction following codes per the specific section numbers of ACI 562: is considered to have no existing building code. In this case, a. Current building code (1.2.2) the provisions of Appendix A of ACI 562 and any chapters b. Original building code (1.2.3) in the current building code that address existing buildings c. Existing building code (1.2.1) must be met. d. Design-basis code (1.2.4) Once the original building code and current building In the United States, the current building code is usually code have been identified, the LDP can use the flowchart based on an edition of the International Building Code (IBC), presented in Fig. 1.2 as a guide to determine the design-basis which was first published in 2000; a few large cities have code for repair, rehabilitation, or strengthening design. The their own customized building codes. The current building design-basis code is dependent on the adoption of an existing code establishes the design and construction regulations building code within the jurisdiction of the project. If a jurisfor new construction and provides limits that need not be diction has not adopted an existing building code, Appendix exceeded if designing new construction or assessing and A of ACI 562 is used to determine the design-basis code. In designing repairs and rehabilitation of existing structures. jurisdictions that have adopted an existing building code, the For the design and construction of new concrete structures, design-basis code is determined in accordance with Chapter 4 IBC references ACI 318. The code used to initially design of ACI 562. The Project Examples included within this guide the building is referred to as the original building code and is illustrate how Fig. 1.2 is used to determine the design-basis typically identified in the construction documents, or may be code. Chapter 4 and Appendix A provide the design-basis obtained by contacting the local jurisdiction and requesting criteria for the repair and rehabilitation work. Designing new information regarding the building code in effect at the time members and their connections to existing structures must be of original construction. The most common original codes based on ACI 318. prior to the IBC in the U.S. include the Building Officials The LDP may forego the determination of the design-basis Code Administrators National Building Code (BOCA/ code based on Chapter 4 or Appendix A and select the current NBC), the Uniform Building Code (UBC), and the Stanbuilding code for assessment criteria. This is a conservative dard Building Code (SBC) that typically reference previous approach and may result in expensive repair or strengthening versions of ACI 318 with modification. An existing concrete @Seismicisolation options. The LDP should, therefore, review this option with @Seismicisolation the owner before proceeding with the assessment. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 14 1.3—Applicability of the Code tion work, or installing remedial work of existing structures. Owners are required to maintain existing structures to The Code applies to nonstructural concrete or for aesthetic prevent unsafe conditions from occurring, or repair potentially improvements, if there is a potential for these materials to fail dangerous conditions that are present. ACI 562 is applicable resulting in a potentially dangerous condition. to existing concrete structures including the concrete elements Provisions for seismic resistance—ACI 562 refers to of buildings; nonbuilding structures; building foundation the existing building code for the evaluation of seismic members, both plain and reinforced concrete; soil-supported resistance and seismic rehabilitation design. If an existing structural slabs; concrete portions of composite members; and building code has not been adopted, ACI 562 requires that prestressed and precast concrete structures including cladthe LDP use ASCE/SEI 41 for voluntary seismic retrofits ding, which transmits lateral loads to diaphragms or bracing supplemented by ACI 369.1. These references provide guidmembers. ACI 562 includes provisions specific to performing ance for the LDP regarding forces, analysis and modeling assessment, repair, rehabilitation, and strengthening of existing procedures, and seismic rehabilitation design. The effect concrete elements of buildings or nonbuilding concrete strucof repairs or rehabilitations to existing concrete buildings tures. These provisions provide minimum level of repair for should be considered in the assessment of the structure’s an existing building and typically address these unsafe and seismic response per ACI 562, 6.7.4. potentially dangerous conditions. The LDP can exceed the ACI 562 permits voluntary retrofit for seismic resistance if minimum requirements of ACI 562, such as those for progresthe existing building code or ACI 562 do not require rehabilsive collapse resistance, redundancy, or integrity provisions. itation for existing buildings. If IEBC is adopted, then IEBC Regulations of the current building code, however, need not and ACI 562 are used for voluntary retrofit of seismic resisbe exceeded when assessing, designing repair and @Seismicisolation rehabilitatance. If, however, an existing building code has not been @Seismicisolation University of Toronto User. Fig. 1.2—Flowchart for determination of design basis code in ACI 562-19. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 1—General Requirements15 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Which ACI Code Governs? The assessment, repair, and rehabilitation of existing concrete structures present several unique considerations as compared to the design and construction of new concrete structures. Accordingly, ACI 562 provides directions for how existing structures are treated with respect to various building codes. For example, repairs, additions, or alterations to structures may result in the redistribution of moments in continuous flexural members. ACI 562 provisions address these effects and allow the analysis of existing structures to consider the actual state of redistributed moments, even if they exceed the moment distribution permitted in ACI 318 (ACI 562, R6.5.4). Some of the provisions, calculations, and methods presented in ACI 318 are also applicable to the design of repair and rehabilitation measures for existing concrete structures. In these instances, ACI 562 provides direcadopted, then ACI 562 directs the LDP to use the current building code supplemented by ASCE/SEI 41 and ASCE/ SEI 7 to design seismic retrofits. be presented to the owner and jurisdictional authorities in form of a basis of design report. The items to be included in a basis of design report are summarized in the following titled text box “Basis of design report example.” The Project Examples presented in this guide provide specific examples of the responsibilities of the LDP, including the responsibility for notifying and communicating information to the owner through the duration of the assessment, repair, and rehabilitation. Specifically, Project Example 4 presents the reporting of potentially dangerous structural conditions. 1.6—Construction documents Construction documents need to clearly communicate the information necessary to perform the repair, rehabilitation, or strengthening work, and the material specified must satisfy ACI 562 and the local jurisdictional authority. The LDP may perform calculations necessary to evaluate the structure and design the repairs. Computer analyses and model analysis may be used. Pertinent calculations are required to be submitted to the building official if required. The LDP will furnish the owner with copies of the project documents, including reports, repair documents, construction submittals, field reports, and locations of completed repairs to the extent of the LDP’s contractual obligations. The Project Examples presented in this guide provide specific examples of the types of information that are to be specified in the construction documents, as well as any additional information that should be delivered to the owner, the building official, or both throughout the duration of the assessment, repair, and rehabilitation. Essential information that should be included in the construction documents is listed in the following titled text box “Construction document example.” 1.5—Responsibilities of licensed design professional The LDP for the project is responsible for the repair process, from assessing a structure to designing and specifying repair materials, developing details to producing quality assurance programs covering the repairs, and advising the owner on future maintenance requirements to maintain a durable structure. ACI 562, 1.5.2, requires the LDP to report observations of exposed structural defects within the work area representing obvious conditions requiring immediate attention to the owner and should alert the contractor of potentially dangerous conditions that require urgent action that may be discovered during construction to protect the public. Some jurisdictions may require the LDP to report potentially dangerous conditions directly to them. The LDP should be aware of thoese requirements when working in such a jurisdiction. The LDP should document these findings in a report that includes a summary of the assessment of the existing 1.7—Preliminary assessment structure, and a summary of or reference to the construcA preliminary assessment is the first step in the repair tion documents used for rehabilitation. These findings may @Seismicisolation process in which the LDP reviews plans, construction data, @Seismicisolation University of Toronto User. 1.4—Administration This Code, unless in conflict with the IEBC or jurisdiction authority regulations, will govern in the assessment and repair or rehabilitation of existing concrete structures. If ACI 562, however, is in conflict with requirements in referenced standards in thie ACI 562, then this Code will govern. ACI 562 permits the use of repair design or construction systems that do not conform to ACI 562, provided such systems are approved by the building official based on successful use, analysis, or testing in accordance with ACI 562, 1.4.2. tion regarding the scope and applicability of ACI 318 provisions for use with existing structures. For example, horizontal shear and shear-friction provisions presented in ACI 318 are applicable for force transfer at the interface between existing members and repair materials, and designing supplementary reinforcement for repairs (ACI 562, 7.3.2 and 7.4.1). Similarly, postinstalled anchors and dowels are often used in repairs of existing concrete members. Accordingly, the provisions provided in ACI 318 Chapter 17 are applicable for the design of post-installed anchors in existing structures (ACI 562, 7.6.5). Chapter 1 of ACI 562 describes how ACI 562, ACI 318, and other codes adopted by the local jurisdiction are used by the licensed design professional in the assessment, repair, and rehabilitation of existing concrete structures. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 16 Basis of design report example* 1. Building description including: a. Address b. Date of construction c. Structural systems d. Original building code e. Past and current uses 2. Documenting of potentially dangerous structural conditions in the work area, as determined in the assessment 3. Documenting of substantial structural damage in the work area 4. History of concrete repairs and rehabilitations 5. Members and systems of the work area requiring increase in capacity beyond the demand of the original building code 6. Modifications such as additions, alterations, or changes in occupancy 7. Conditions and details of the proposed rehabilitation work 8. Assessment criteria and findings 9. Design-basis code criteria and basis of rehabilitation design 10. Material selection parameters 11. Shoring needs 12. Quality assurance and quality control (QA/QC) requirements 13. Types and frequency of future inspection 14. Types and frequency of future maintenance * A basis design report should include, but is not limited to, this information. Construction document example* 5. Magnitude and location of prestressing forces† 6. Anchor details for prestressing reinforcement† 7. Development length of reinforcement and length of lap splices 8. Type and location of mechanical or welded splices of reinforcement† 9. Shoring or bracing criteria necessary before, during, and at completion of the assessment, repair, or rehabilitation projects† 10. Quality assurance program including specific inspections and testing requirements * A construction document should include, but is not limited to, this information. † Items not required on every project. reports, local jurisdictional codes, and other available docubuilding code, Appendix A of ACI 562 is applicable and ments of the existing structure to assess the damage, capacity, provides criteria for selecting the design-basis code. or load thresholds that will determine the design-basis code. The level and extent of the preliminary assessment is The preliminary assessment is done to determine if visibly subject to the professional judgment of the LDP. In some dangerous structural conditions are present. If present, the cases, where the repair project addresses structural damage, LDP must report these conditions to the owner, contractor, the extent of deterioration or deficiency and cause of damage or both (ACI 562, Section 1.7.2). For additions and alteraare clearly defined and known. If the structure’s historical tions, the preliminary assessment will generally include the performance and visual observation of the structural condidetermination of the effect of the work on live and dead tion of members and systems are acceptable, the level of loads and the capacity of members. The level of damage to damage or deterioration is low and modifications for addian existing structure is also an important determining factor tions, alterations, and changes in occupancy are not planned, in selecting the design-basis code and, therefore, a prelimithen, per ACI 562, 4.6 or A.6, the structure is acceptable and nary assessment is carried out to assess the level of structural repairs addressing durability and serviceability issues could damage, to determine that the structure is in compliance with be performed without performing analysis. the original design code, and that the structure is safe. A preliminary assessment is also important to determine Chapter 4 applies if a jurisdiction has adopted the IEBC if an existing member, portions of a structure, or the entire and defines the design-basis code criteria references. In structure exhibits signs of deterioration, structural deficiency, the case of a jurisdiction that has not adopted an @Seismicisolation existing or behavior that are inconsistent with available design and @Seismicisolation University of Toronto User. 1. Name and date of issue of building code and supplements to which the assessment, repairs, or rehabilitation conforms 2. Design-basis code criteria used for conditions addressed by the documents 3. Design assumptions and construction requirements, including specified properties of existing and remedial materials used for the project and the strength requirements at stated ages or stages of construction 4. Details, locations, and notes indicating the size, configuration, reinforcement, anchors, repair materials, preparation requirements, and other pertinent information to implement the repairs, strengthening, or rehabilitation of the structure Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 1—General Requirements17 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Useful references for evaluating existing concrete structures The following documents are listed in the commentary of ACI 562 and may provide guidance for evaluating existing concrete structures. ACI 201.2R––Guide to Durable Concrete ACI 214.4R––Guide to Obtaining Cores and Interpreting Compressive Strength Results ACI 228.1R––In-Place Methods to Estimate Concrete Strength ACI 364.1R––Guide for Evaluation of Concrete Structures before Rehabilitation AC1 437.1R––Load Tests of Concrete Structures: Methods, Magnitude, Protocols, and Acceptance Criteria ASCE/SEI 11––Guideline for Structural Condition Assessment of Existing Buildings ASCE/SEI 31––Seismic Evaluation of Existing Buildings ASCE/SEI 41––Seismic Rehabilitation of Existing Buildings FEMA P-58—Seismic Performance Assessment of Buildings FEMA P-154—Rapid Visual Screening of Buildings for Potential Seismic Hazards FEMA 306 and 307—Evaluation of Earthquake Damaged Concrete and Masonry Wall Buildings The Concrete Society TR 68––Assessment, Design and Repair of Fire-damaged Concrete Structures International Organization for Standardization (ISO) Maintenance and Repair of Concrete Structures 16311-3:2014 (ISO/TC 71/SC 71) documents are available, then listed material properties can be used in a preliminary assessment. If construction documents, however, are not available, ACI 562 Chapter 6 provides historical properties based on typical values used at the time of construction. The LDP should document all deficiencies including cracking, spalls, member deflection, cross section dimensions different than specified on the original construction drawings, and construction tolerances exceeding those permitted under the original building code. Deficiencies or unusual behavior identified in the preliminary assessment are evaluated in more detail through a structural assessment, structural analysis, or both, as discussed in Chapter 6 of ACI 562. The existing conditions, as well as any observed deficiencies or deterioration, should be considered in the course of a preliminary assessment. In other cases, a preliminary assessment may suggest the need for a more detailed assessment, when a member or structure exhibits damage, displacements, deterioration, or structural deficiencies, or behavior that is unexpected or inconsistent with available design and construction documents or code requirements in effect at the time of construction of the structure (Section 1.7.5). As described in the ACI 562 commentary, numerous published references are available for guidance on performing assessments of existing concrete structures. Several of these are listed in “Useful references for evaluating existing concrete structure.” Each of the Project Examples provides a specific example of performing a preliminary assessment, including some of the assumptions and professional judgments that may be considered by the LDP. @Seismicisolation @Seismicisolation University of Toronto User. construction documents or code requirements in effect at the time of construction (ACI 562, 6.2.1). The LDP of the project may limit the access to the structure, take specific measures to mitigate these conditions, or require the installation of shoring to support the structure or member, if potentially dangerous conditions are present. As deemed necessary by the LDP, the preliminary assessment may include a review of design and construction documents and verification of existing site conditions by visual inspection and other means. Per ACI 562, 1.7.4, the preliminary assessment should also include a determination of the design strength of the existing structure, including the impact of deficiencies, and a determination if substantial structural damage has occurred. The concept of substantial structural damage is not addressed by ACI 562 if a jurisdiction has adopted the IEBC as an existing code; thus the LDP should use IEBC to determine if substantial structural damage has occurred. The LDP, however, should use ACI 562 Appendix A, A.4, that defines substantial structural damage if a jurisdiction has not adopted an existing building code. The preliminary assessment should be based on in-place conditions and should use actual material properties and member sizes to calculate the impact of damage on the members and the overall performance of the existing structure. Fire damage or other deterioration mechanisms could affect the material properties of reinforced concrete members; for example, compressive strength and modulus of elasticity of concrete and loss of steel reinforcement area due to corrosion. If a member does not show significant deterioration and construction ATC 20––Post Earthquake Evaluation of Buildings ATC 45––Field Manual: Safety Evaluation of Buildings after Wind Storms and Floods ATC 78—Identification and Mitigation of Nonductile Concrete Buildings Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 18 Concrete spalling and corrosion of reinforcing steel at floor slab underside (left). Severe concrete and reinforcing steel deterioration in a wastewater treatment basin (right) Overview Chapter 2 of ACI 562 provides a summary of the notation and terminology used in the ACI 562 Code. 2.2—Definitions Section 2.2 of ACI 562 defines unique and specific terminology used in the code and commentary of ACI 562. In some cases, multiple, slightly different definitions are provided for the same term where it is uncertain which definition might be most appropriate for a given scenario or use. For example, “repair process” may have several possible definitions. The list of definitions provided in Section 2.2 of ACI 562 is not intended to be comprehensive of all terminology used within ACI 562. ACI and the International Concrete Repair Institute (ICRI) provide online resources for terminology: a. ACI––“ACI CT-16 Concrete Terminology,” https://www.concrete.org/store/productdetail.aspx?ItemID=CT18&For mat=DOWNLOAD&Language=English&Units=US_Units b. ICRI––“ICRI Concrete Repair Terminology,” https://www.icri.org/page/terminology_H?&hhsearchterms=%22termin ology%22 Where indicated in the commentary, some definitions in ACI 562 are repeated verbatim from the 2018 International Existing Building Code (IEBC). Other terms used can differ from the definitions provided within other building codes, specifically the 2018 IEBC. In such cases, the definitions@Seismicisolation provided in Section 2.2 of ACI @Seismicisolation 19 University of Toronto User. 2.1—Notation Section 2.1 of ACI 562 defines the various symbols and letters used in the formulas and text in the ACI 562 code and commentary. Most often the notation used in a given formula is also defined within the text of the code after the formula is presented. Section 2.1 of ACI 562 is intended to provide the user with an easy single-source reference location. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 2—Notation and Definitions GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES 562 or the definitions provided in ACI CT should be used when interpreting the language of ACI 562. Similarly, the definitions presented in 2018 IEBC should be used when interpreting the language of 2018 IEBC. To further assist the user, specific terminology that is defined in unique ways to ACI 562 and 2018 IEBC are presented as follows: Existing structure — a. ACI definition: structure for which a legal certificate of occupancy has been issued. For structures that are not covered by a certificate of occupancy, existing structures are those that are complete and permitted for use or otherwise legally defined as an existing structure or building. b. IEBC definition: a structure erected prior to the date of adoption of the appropriate code, or one for which a legal building permit has been issued. Rehabilitation— a. ACI definition: repairing or modifying an existing structure to a desired useful condition. b. IEBC definition: any work, as described by the categories of work defined herein, undertaken in an existing building (2018 IEBC). Repair— a. ACI definition: the reconstruction or renewal of concrete parts of an existing structure for the purpose of its maintenance or to correct deterioration, damage, or faulty construction of members or systems of a structure. b. IEBC definition: the reconstruction, replacement, or renewal of any part of an existing building for the purpose of its maintenance or to correct damage (2018 IEBC). Repair section— the combination of the installed repair material(s) and the substrate material(s). Restoration— a. ACI definition: the process of reestablishing the materials, form, and appearance of a structure to those of a particular era of the structure (ACI CT-16). b. IEBC definition: no specific definition provided in 2018 IEBC. Structural repair— a. ACI definition: restoring a damaged or deteriorated structure or increasing the capacity of a structure. b. IEBC definition: no specific definition provided in 2018 IEBC. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 20 University of Toronto User. @Seismicisolation @Seismicisolation Application of an epoxy-based, quartz-reinforced composite overlay on effluent trough of a clarifier basin 21 University of Toronto User. Overview Chapter 3 of ACI 562 provides the full document titles for referenced standards presented in the code portion of ACI 562. These standards include building codes, specifications, and test methods, and are referenced to specify, clarify, or expand upon the code requirements presented within ACI 562. Each of these standards are written with mandatory language and considered part of the code requirements of ACI 562 for the purposes indicated within ACI 562. The context of the reference within the code language of ACI 562 governs the use and applicability of each of the referenced standards. In some cases, the code requirements of ACI 562 limit the applicability of the referenced standard. The entire standard is not necessarily considered part of the code requirements of ACI 562. For example, Section 5.1.6 of ACI 562 limits the use of ASCE/SEI 7, “Minimum Design Loads for Buildings and Other Structures,” by excluding seismic load requirements, but references ASCE/SEI 41, “Seismic Rehabilitation of Existing Buildings,” for the treatment of seismic loads. Current, past, and withdrawn standards are referenced as indicated in Chapter 3 of ACI 562. The dates provided refer to the applicable version of the reference. Those references indicated as being withdrawn refer to the standard at the time it was withdrawn, and not the superseding standard. For example, ASTM A160, “Specifications for Axle-Steel Bars for Concrete Reinforcement (withdrawn 1969),” refers to the version in effect in 1969, and not ASTM A617/A617M, “Standard Specification for Axle-Steel Deformed and Plain Bars for Concrete Reinforcement,” which superseded this standard. Additional resources that are referenced within the commentary text of ACI 562 are listed in Chapter 11 of ACI 562. The following ACI codes are referenced in Chapter 3 of ACI 562. A brief description of each document is included. @Seismicisolation @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 3—Referenced Standards GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES ACI 216.1-14—Code Requirements for Determining Fire Resistance of Concrete and Masonry Construction Assemblies Fire resistance of building elements is an important consideration in building design. While structural design considerations for concrete and masonry at ambient temperature conditions are addressed by ACI 318 and TMS 402/ACI 530/ASCE 5, respectively, these codes do not consider the impact of fire on concrete and masonry construction. This standard contains design and analytical procedures for determining the fire resistance of concrete and masonry members and building assemblies. Where differences occur in specific design requirements between this standard and the aforementioned codes, as in the case of cover protection of steel reinforcement, the more stringent of the requirements shall apply. Much of the research data referenced in preparing the Code arecited for the user desiring to study individual questions in greater detail. Other documents that provide suggestions for carrying out the requirements of the Code are also cited. ACI 437.2-13—Code Requirements for Load Testing of Existing Concrete Structures and Commentary This code provides requirements for test load magnitudes, test protocols, and acceptance criteria for conducting a load test as a means of evaluating the safety and serviceability of concrete structural members and systems for existing buildings as provided for by ACI 562-19. A load test may be conducted as part of a structural assessment to determine whether an existing building requires repair and rehabilitation, or to verify the adequacy of repair and rehabilitation measures applied to an existing building, or both. This code contains provisions for both a cyclic load test and a monotonic load test procedure. An ACI Standard ACI 563-18 Reported by ACI Committee 563 University of Toronto User. ACI 318-19—Building Code Requirements for Structural Concrete and Commentary ACI 563-18—Specifications The “Building Code Requirefor Repair of Concrete in ments for Structural Concrete” Buildings Specifications for Repair of Concrete in Buildings (“Code”) covers the mateThis is a Reference Specifica(ACI 563-18) rials, design, and construction tion that the Architect/Engineer of structural concrete used in can apply to any construction buildings and where applicable repair and rehabilitation project in nonbuilding structures. The involving structural concrete Code also covers the strength by citing it in the Project Specievaluation of existing concrete structures. fications. Mandatory requireAmong the subjects covered are: contract documents; ments and Optional requirements inspection; materials; durability requirements; concrete checklists are provided to assist the Architect/Engineer in quality, mixing, and placing; formwork; embedded pipes; supplementing the provisions of this Specification, as required reinforcement details; member design of slab systems, or needed, by designating or specifying individual project beams, columns, diaphragms, walls, structural plain requirements. The first section covers general construction concrete, construction joints; strength and serviceability; requirements for all repair work. The second section covers development and splices of reinforcement; strength evalushoring and bracing of the structure or member to be repaired, ation of existing structures; provisions for seismic design; and addresses sequencing of repair work as the structure is strut-and-tie modeling; and anchoring to concrete. unloaded and reloaded. The third section covers concrete The quality and testing of materials used in construction are removal and preparation of the concrete substrate for repair, covered by reference to the appropriate ASTM standard speciand defines common equipment and methods. The next fications. Welding of reinforcement is covered by reference to five sections cover materials and proportioning of concrete; the appropriate American Welding Society (AWS) standard. proprietary cementitious and polymer repair materials; reinUses of the Code include adoption by reference in general forcement; production, placing, finishing, and curing of repair building codes, and earlier editions have been widely used in materials; formwork performance criteria and construction; this manner. The Code is written in a format that allows such treatment of joints; embedded items; repair of surface defects; reference without change to its language. Therefore, backmockups; and finishing of formed and unformed surfaces. ground details or suggestions for carrying out the requireProvisions governing testing, evaluation, and acceptance of ments or intent of the Code portion cannot be included. repair materials as well as acceptance of the repair Work are The Commentary is provided for this purpose. Some of included. Sections 9 and 10 incorporate by reference two the considerations of the committee in developing the Code other specifications—ACI 503.7 and ACI 506.2—into this portion are discussed within the Commentary, with emphasis ACI Standard to cover crack repair by epoxy injection and given to the explanation of new or revised provisions. @Seismicisolation shotcrete, respectively. @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 22 Step repair project at government building 4.1—General Chapter 4 of ACI 562 applies if a jurisdiction has adopted a code that addresses assessment, repair, and rehabilitation of existing concrete structures such as the International Existing Building Code (IEBC). Per ACI 562, 1.2.4.2, this chapter does not apply to existing structures located in jurisdictions that have not adopted the IEBC. Where Chapter 4 of ACI 562 applies, the LDP has to determine the design-basis code based on the results of the preliminary assessment (ACI 562, 1.7), detailed assessment (ACI 562 Chapter 6), and on the criteria in the existing building code (IEBC) as stated in Section 4.1.2 of ACI 562.@Seismicisolation The LDP may choose, however, @Seismicisolation 23 University of Toronto User. Overview Chapter 4 provides the criteria for use of ACI 562 with the IEBC. Section 1.7 specifies a preliminary assessment of deteriorated or damaged existing structures to determine the extent and significance of damage and deterioration and the reduced structural capacity of individual existing members and structures. Based upon the findings of the preliminary assessment, the licensed design professional (LDP) has to make a decision regarding potentially dangerous structural conditions and the required extent of further assessment. The findings from the assessment are used to make a decision regarding the design-basis code for required repairs and IEBC compliance method. This chapter establishes limits based on demand-capacity ratios for ultimate strength design and allowable stress principles to determine if existing members, systems, or structures are safe or if strengthening, repair, or both, are necessary. The level of strengthening, repair, or both, is influenced by the calculated demand-capacity limits. The Project Examples illustrate various types of preliminary assessments and methods of determining the design-basis code. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 4—Basis for Compliance GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES to use the current building code referencing ACI 318-19 for concrete structures, TMS 402/602-16 for masonry structures, and AISC-16 for steel structures as the design-basis criteria for all damage states, deterioration, faulty design, or faulty construction instead of the original building code. This may be unnecessarily conservative, however, and may lead to a solution that is cost prohibitive or uneconomical. The LDP is confronted in the initial stages of a project with the challenge to determine what design-basis code criteria applies. This is more prevalent when a structure was constructed prior to a jurisdiction having adopted a general building code. The structure may have design and construction that do not satisfy current building code requirements. ACI 562, with the IEBC, is used to determine if an existing structure should be rehabilitated or retrofitted to satisfy the requirements of the current building code. The LDP, in the absence of mandatory local ordinances, should determine if a seismic evaluation is necessary for potentially hazardous conditions. Consistent with the IEBC, ASCE/ SEI 41 should be used for evaluation of seismic damage to members, systems, or structures that are seismically unsafe. ASCE/SEI 41 may or may not be applicable to nonbuilding structures. The requirements in ASCE/SEI 41 may apply to nonbuilding structures, but the LDP should use judgment as the applicability of these requirements has not been fully verified for every type of structure. This is particularly true for nuclear power plants or other structures designed by nonbuilding standards. Table 4.1—Design-basis code criteria references for rehabilitation categories Rehabilitation category Additions Alterations Changes in occupancy 4.3.2 4.3.3 IEBC Section 405.2.3 IEBC Section 405.2.4 4.5 4.2—Compliance method A compliance method as per the 2018 IEBC is used for assessing the code basis for repair or rehabilitation projects 4.5 is described in this section. The design-basis code for repair and rehabilitation projects varies based on the extent of alter4.6 ations, additions, or repairs. In general, the original building IEBC Sections 502, 606, or code is the design basis for minor alterations without signifiChapter 11 cant changes in load. The current building code serves as IEBC Section 503; the design basis for elements subject to major alterations or Sections 602 and Chapter 7; significant load changes. It should be noted, however, that Sections 603 and Chapter 8; or Sections 604 and Chapter 9 ACI 562-19 1.3.8.1, requires the selection of the existing IEBC Sections 506, 605, or building code for assessment and design for seismic considChapter 10 @Seismicisolation erations. Similarly, the design of repairs subject to elevated @Seismicisolation 4.6 University of Toronto User. Potentially dangerous structural conditions for gravity and wind loads Potentially dangerous structural conditions for seismic forces in regions of high seismicity Substantial structural damage to vertical elements of the lateral-forceresisting system Substantial structural damage to vertical elements of the gravity-loadresisting system Damage less than substantial structural damage with strengthening Damage less than substantial structural damage without strengthening Deterioration and faulty construction with strengthening Deterioration and faulty construction without strengthening Design-basis code criteria reference ASCE/SEI 41 states that its provisions do not have to apply to large nonbuilding structures, such as large tanks found in heavy industry or power plants, floating-roof oil storage tanks, and large (greater than 10 ft long) propane tanks at propane manufacturing or distribution plants. ACI 562 and IEBC should be used to determine the assessment and design-basis criteria for a structure as shown in Table 4.1 (ACI 562 Table 4.1.4) unless the local jurisdiction imposes more restrictive requirements. The IEBC references in Table 4.1 are to sections in the 2018 IEBC. The LDP is faced with several questions when confronted with deteriorated or weakened structures, which he or she should clarify prior to engaging in the assessment. ACI 562 4.1.5 and 4.1.6, require that new reinforced concrete members, added to an existing structure, are designed and detailed to satisfy the current design code (ACI 318-19). This also applies to the connections between the new member and the existing structure. When new concrete and reinforcing members are integrated with the repairs, however, the original building code can be used for design. Detailing of the existing structure, however, need not meet the current design code if the following conditions are satisfied: a. The damage or deterioration to the existing reinforcement is addressed b. The repaired work area of the structure has capacity equal to or greater than demand per ACI 562, 5.2.2, using the original building code requirements or satisfies the requirements of ACI 562, 4.5.3, when using allowable stress design The LDP should review the development length of existing reinforcement when cracking is evident near the ends of reinforcement or in regions where reinforcement splices are present. Research has shown that the development length equations from previous versions of ACI 318 may be unconservative for top cast plain reinforcement (Feldman and Cairns 2017). The LDP should also determine if the structure has demonstrated statistically acceptable performance based on historic data, such as acceptable resistance of previous loads that equal or exceed the loads that would be predicted for the remaining life of the structure, the LDP may judge the structure to have demonstrated historic structural reliability. The commentary in ACI 562 lists a few references that provide guidance in judging acceptable performances. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 24 Useful references for assessing and evaluating existing concrete structures ACI 562 Chapter 2 defines potentially dangerous structural condition as follows: The following documents are listed in the commentary of ACI 562, R4.1.6, and may provide guidance in judging acceptable performance. • ACI 224.1R, “Causes, Evaluation, and Repair of Cracks in Concrete Structures” • ACI 437R, “Strength Evaluation of Existing Concrete Buildings” • ACI 437.1R, “Load Tests of Concrete Structures: Methods, Magnitude, Protocols, and Acceptance Criteria” potentially dangerous structural condition— (1) Structural state of existing concrete within a work area for an individual structural member, structural system, or structure that meets the definition of dangerous or unsafe, is unstable, has potential of collapse of overhead components or pieces (falling hazards), has been determined to have demand/capacity ratio exceeding the limit of Section 4.3.2.2, or has potentially hazardous resistance for seismic events. (2) A limit state of unacceptably low margin of safety against collapse without supplemental resistance. factored load combinations of ASCE/SEI 7. In this chapter, the term “gravity loads” refers to dead, live, and snow loads. Reduction factors from ACI 562 Section 5.3 or 5.4, are used whether a structure is rehabilitated or assessed. If the demand-capacity ratio, as given in ACI 562 Eq. (4.3.2) is greater than 1.5, then the structure is considered potentially dangerous and must be strengthened or repaired based on the current building code. Uc > 1.5 φRcn (ACI 562, Eq. 4.3.2) where Uc is defined as strength design demand by using nominal loads of the current building code and factored load combinations of ASCE/SEI 7 for strength design provisions (LRFD); Rcn is the current in-place nominal resistance of the structural member, system, or connection including the effects of damage, deterioration of concrete and reinforcement, and faulty construction; and φ is the strength reduction factor obtained from Section 5.3 or 5.4 of ACI 562. A demand-to-capacity ratio greater than 1.5 calculated using Eq. (4.3.2) represents a condition with limited to no margin of safety against failure (Stevens et al. 2019). Potentially dangerous structural conditions requiring immediate attention are reported immediately to the owner per ACI 562, 1.5.2, and to the appropriate authorities when required by the authorities having jurisdiction per ACI 562, 1.5.2.1. The LDP may also consider the following to satisfy Eq. (4.3.2): a. Adding structural redundancies, which are desirable to ensure the safety of a structural system 4.3—Potentially dangerous structural conditions b. Providing alternate load paths, redistributing the load, or The LDP needs to determine if potentially dangerous limiting the live load such that existing members are not structural conditions exist by carrying out a thorough overstressed assessment of the deterioration or damage to the existing c. Adding secondary supporting members to relieve overstructure, as discussed in Chapter 1 and 6 of this guide. The stressed members risk for collapse of each proposed strengthening procedure If the demand-capacity ratio, however, is less than 1.5, should be assessed to determine an economical and safe then less restrictive requirements are implemented as repair strategy. The LDP calculates the strength demand described in Section 4.5 of this guide. based on the current building code, considering gravity and Unless addressed by the authority having jurisdiction, for fluid loads and lateral wind and soil loads but excluding structures in Seismic Design Categories D, E, and F, the LDP seismic loads. The governing load is determined @Seismicisolation using should review the structure for potentially hazardous seismic @Seismicisolation University of Toronto User. temperatures and fire needs to satisfy the applicable existing building code. The LDP should confirm specific requirements of selected compliance method which may vary depending upon IEBC edition. The 2018 IEBC describes three compliance methods: the prescriptive method, the work area method, and the performance method, which are summarized in The Compliance Methods in the 2018 IEBC chapter at the end of this guide. Assessing structural safety, level of structural damage or conditions with less than substantial structural damage—In the industry, a quantitative measure or scale to determine the level of deterioration or damage exhibited by an existing structure does not exist. There are, however, processes that can be applied to determine the safety level of an existing structure. Nevertheless, the LDP is confronted with several questions that require careful planning and response. Some of the questions may be: a. When should an existing structure be strengthened or repaired? b. What is an acceptable demand-capacity ratio limit to consider an existing structure safe? c. What is the minimum acceptable strengthening or repair level that is considered safe? d. When should an existing structure’s capacity be increased? e. How should an existing structure be evaluated by the working stress method? f. When should an existing structure be strengthened or repaired to the original building code, IEBC, or applicable existing building code level? These and other questions that may arise are addressed in ACI 562-19, 4.3 through 4.5. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 4—Basis for Compliance25 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES ACI 562-19 Useful references for potentially dangerous structural conditions ACI 562-19 Chapter 2 defines substantial structural damage as follows: The following documents are listed in the commentary of ACI 562 and may provide target reliability indexes, basic probability theory and concepts for an assessment using the specific details of the demand as it relates to the capacity with the strength reduction factors of Chapter 5 for concrete structures. • ASCE/SEI 7, “Minimum Design Loads for Buildings and Other Structures” • Galambos, T.V.; Ellingwood, B.R.; MacGregor, J.G.; and Cornell, C.A., 1982, “Probability Based Load Criteria: Assessment of Current Design Practice,” Journal of the Structural Division, ASCE, V. 108, No. 5, pp. 959-977. • Ellingwood, B.R., and Ang, A. H.-S., 1972, “A Probabilistic Study of Safety Criteria for Design,” Structural Research Series 387, University of Illinois Experiment Station, University of Illinois at Urbana-Champaign, Champaign, IL. Substantial structural damage—Except when using Appendix A, substantial structural damage per the IEBC shall be - A condition where one or both of the following apply: 1. In any story, the vertical elements of the lateral force resisting system have suffered damage such that the lateral load-carrying capacity of the structure in any horizontal direction has been reduced by more than 33 percent from its predamage condition. 2. The capacity of any vertical gravity load carrying component, or any group of such components, that supports more than 30 percent of the total area of the structure’s floor(s) and roof(s) has been reduced more than 20 percent from its predamage condition and the remaining capacity of such affected elements, with respect to all dead and live loads, is less than 75 percent of that required by this code for new buildings of similar structure, purpose and location. When using this code as a stand-alone code, substantial structural damage shall be as defined in A.4. there is reason to question the capacity of the structure, ACI 562 requires that it be assessed by checking one of the criteria in ACI 562, 4.5.1, 4.5.2, or 4.5.3. These sections must not be applied in combination with each other. The demand-capacity ratio of a member, system, or structure is evaluated in accordance with Eq. (4.5.1): Uo > 1.0 φo Rcn where Uo is the strength design demand determined by using 4.4—Substantial structural damage the nominal loads and factored load combinations of the A structure with substantial structural damage, as defined original building code, excluding seismic loads; foRcn is the in ACI 562 Chapter 2, is assessed and rehabilitated per 2018 current in-place nominal resistance of the structural member, IEBC Sections 404.2 through 404.3, or 606.2.2 through system, or connection including the effects of damage, dete606.2.3 that requires the LDP to submit to the building offirioration of concrete and reinforcement, and faulty construccial the structure’s assessment and whether “the damaged tion adjusted by the strength reduction factor (fo) of the building, if repaired to its pre-damaged state, would comply original building code. with the provisions of the IBC for wind and earthquake If Uo/foRcn is greater than 1.0, repairs are required to loads.” 2018 IEBC has, however, two exceptions; for buildrestore the structure to the pre-damage or pre-deteriorated ings in SDC A, B, or C, if the substantial damage was not states based on the original building code. Most existing due to an earthquake, and for one-and two-family dwellings. concrete structures with damage less than substantial strucBoth do not need to “be evaluated or rehabilitated with load tural damage, deterioration, or containing faulty construccombinations that include earthquake effects.” tion, will provide acceptable safety if restored to the strength of the original building code based on the material proper4.5—Conditions of deterioration, faulty ties of the original construction. New concrete members and construction, or damage less than substantial connections to existing construction must comply with ACI structural damage 562, 4.5.1. For structures having less than substantial structural For structures with a demand-capacity ratio (Uo/ϕcRcn) damage but have deterioration or faulty construction @Seismicisolation and less than 1.0, strengthening is not required. @Seismicisolation University of Toronto User. conditions. The review should be completed to confirm the structure is adequate for either the seismic performance level required by the local authorities, or confirm the structure is compliant with ASCE/SEI 41 for Structural Performance Level – Collapse Prevention using Earthquake Hazard Level, BSE-1. Earthquake Hazard Level BSE-1 has a 20 percent probability of exceedance in 50 years, or a 225-year return period. When the local authority having jurisdiction does not provide requirements for potentially hazardous seismic structural conditions, then the LDP should refer to ATC-78, the IEBC, and ASCE/SEI 41 appendixes for guidance. The LDP is not required to assess potentially hazardous seismic conditions for concrete structures located in moderate to low seismicity regions. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 26 IEBC adopted? No Go to Appendix A Yes Yes Go to Chapter 4 Is structure unsafe for gravity and wind loads, Uc / φRcn > 1.5? No Report unsafe conditions to Owner/Jurisdiction (Section 1.5.2) Is structure in SDC D, E, F? No Yes Yes Is structure unsafe for seismic forces? No Design-basis code is the current building code and ASCE/SEI 7 Yes Substantial structural damage to gravity-force-resisting system? Design-basis code IEBC Section 404.3 or 606.2.3 Yes Design-basis code is the ACI 562 and ASCE/SEI 41 Substantial structural damage to lateral-force-resisting system? No No Report unsafe conditions to Owner/Jurisdiction (Section 1.5.2) Yes Design-basis code IEBC Section 404.2 or 606.2.2 Strengthening required? Uo / φoRcn > 1.0? Restore structure to pre-damaged or pre-deteriorated state No Less than substantial structural damage (Section 4.6) Section 4.6.1 Strengthening per ACI 562 Chapters 7 through 10 Section 4.6.2 Assessing effects of deflection, vibration, and levelness No structural damage Additions (Section 4.7) Alterations (Section 4.8) Change in occupancy (Section 4.9) Fig. 4.5a—Selecting design-basis code. For an existing structure that was subjected to known the original structure is significantly inconsistent with the loads equal to or higher than specified in the design docucurrent standards, which may result in unacceptable strucments during its service life that has performed satisfactotural safety issues. The references listed under Section 4.3 of rily, then it should be taken as an indicator that the existing this guide should be considered in the selection of a relevant structure has an adequate safety factor and strengthening is assessment criteria. The applicability of the original building not required. Figure 4.5a provides a road map for selecting code for assessing existing structures should be questioned if the design-basis code. there are any of the following: ACI 562 Section 4.5.2 permits the LDP to use alternaa. Increased load intensity tive assessment criteria using engineering principles for b. Added loads members, systems, or structures with deterioration, faulty c. Changes in load factors, strength-reduction factors, or construction, or damage less than substantial structural load combinations damage when approved by authority having jurisdiction. d. Modifications of analytical procedures The LDP should assess whether the demand or capacity @Seismicisolation of e. Changes in determining capacity between the original and @Seismicisolation University of Toronto User. Uc – demand using nominal loads of the current building code and factored load combinations of ASCE/SEI 7 for strength design provisions Uo – demand using nominal loads and factored load combinations of the original building code for strength design provisions Rcn – current in-place nominal capacity of structural member, system, or connection including the effects of damage, deterioration of concrete and reinforcement, and faulty construction φ – strength reduction factor per ACI 562, Section 5.3 or 5.4 φo – strength reduction factor of the original building code Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 4—Basis for Compliance27 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES current building codes, such as a change from allowable stress design to ultimate strength design f. The benefits received from strengthening or repair do not justify the incurred cost ACI 562 defines demand based on the current building code (Uc) as the effect of nominal gravity loads and lateral wind and soil loads, excluding earthquake loads, using ASCE/ SEI 7 factored load combinations. ACI 562 defines demand based on the original building code (Uo*) as the effect of the original building code nominal gravity loads and lateral wind and soil loads, excluding earthquake loading, using the factored load combinations of ASCE/SEI 7. The LDP should compare the demand based on the current building code (Uc) to the demand of the original building code (Uo*). If Uc > 1.05Uo*, then the LDP should determine the demand-capacity ratios based on the current building code, Uc/fRcn. If the ratio exceeds 1.1, (Uc/fRcn > 1.1), then strengthening of the structure to the current building code is required. Otherwise, strengthening is not required. If the current building code demand, however, does not exceed the original building code demand by more than 5 percent (Uc ≤ 1.05Uo*), then the LDP should check the demand-capacity ratio using the original building code demand and the current building code capacity. If the ratio exceeds 1.05 (Uo*/fRcn > 1.05), then the system or member strength should be restored to its original strength using the original building code. Otherwise, strengthening is not required (refer to Fig. 4.5b). For both conditions, the strength reduction factors are obtained from ACI 562 Chapter 5. The LDP is often confronted with deteriorated or damaged structures designed using the working or allowable stress method that was the only available method for designing structures prior to ACI 318-63. In 1963, the strength design method was introduced into ACI 318 next to the working Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 28 University of Toronto User. Uc – demand using nominal loads of the current building code and factored load combinations of ASCE/SEI 7 for strength design provisions Uo* – demand using nominal loads of the original building code and factored load combinations of ASCE/SEI 7 for strength design provisions Rcn – current in-place nominal capacity of structural member, system, or connection including the effects of damage, deterioration of concrete and reinforcement, and faulty construction φ – strength reduction factor per ACI 562, 5.3 or 5.4 Fig. 4.5b—Alternate method for evaluating reinforced concrete @Seismicisolation structure. @Seismicisolation Table 4.5—Assessment conditions for reinforced concrete buildings ACI 562 Section Demand/capacity Design-basis code Potentially dangerous structural condition, Section 4.3 Gravity and wind load (4.3) Seismic (4.3) Uc/fRcn > 1.5 Current building code and ASCE/SEI 7 for factored load combinations ASCE/SEI 41 and ACI 562 Substantial structural damage, Section 4.4 Gravity and wind load (4.4) Seismic (4.4) Section 4.5.1 Section 4.5.2C(a) Section 4.5.2C(b) Section 4.5.3 IEBC 404.3 or 606.2.3 IEBC 404.2 or 606.2.2 Deterioration, faulty construction, or damage less than substantial Original building code Uo/foRcn > 1.0 New members use current building code Alternate assessment criteria for deterioration, faulty construction, or damage less than substantial Uc > 1.05Uo* and Current building code Uc/fRcn > 1.1 Uc > 1.05Uo* and Strengthening not required Uc/fRcn < 1.1 * Uc < 1.05Uo and Original building code Uo*/fRcn > 1.05 * Uc < 1.05Uo and Strengthening not required Uo*/fRcn < 1.05 1.0 < Uc/fRcn < 1.5 Original building code only used allowable stress design and design service loads Us/Ra > 1.0 Original building code Strengthening not required Us/Ra < 1.0 Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 4—Basis for Compliance29 University of Toronto User. Chloride extraction performed on historic viaduct stress method. In 1971, ACI 318 dropped the working stress then strengthening of a structure is required using the origmethod and retained the strength design method. inal building code. If the demand-capacity ratio, however, is ACI 562, 4.5.3, provides provisions to assess such a strucless than 1.0, Us/Ra < 1.0, then strengthening is not required. ture. The demand-capacity ratio is based on service load The service load demand includes nominal gravity loads demand, Us, and resistance using allowable stresses, Ra. If and lateral wind and seismic forces using load combinations the demand-capacity ratio is greater than 1.0, Us@Seismicisolation /R of the original building code. The LDP should be aware that a > 1.0, @Seismicisolation GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES using the allowable stress design method is inconsistent with the reliability principles of current strength design provisions. Therefore, ACI Committee 562 recommends verifying the structure following ACI 562, 4.5.2, and checking the seismic resistance using ASCE/SEI 41. Table 4.5 summarizes the different assessment conditions that the LDP has to address when analyzing a structure for repair, rehabilitations, or strengthening. 4.6—Conditions of deterioration, faulty construction, or damage less than substantial structural damage without strengthening For other structures not strengthened using ACI 562, 4.3 through 4.5, the LDP needs to follow ACI 562, 4.6 through 4.9, to determine the design-basis criteria to implement for strengthening. For structures with minimal or no damage or faulty construction that do not require strengthening per ACI 562, 4.5, the LDP can use Chapters 7 through 10 of ACI 562 as the design-basis criteria to rectify the shortcomings. Corroded or damaged reinforcement affects the behavior of the concrete structure. It may result in concrete cracking, possible reduction in section capacity resisting the applied loads, or both. The licensed design professional should evaluate the effectiveness of the reinforcement per Chapter 7 of ACI 562. ACI 318, as well as other codes, control predicted design deflections by either limiting calculated deflections to some specified allowable limits or specifying a minimum spanto-thickness ratio. These limits, however, are based on past experience with loads (for example, normalweight concrete with loads less than approximately 100 lb/ft2 [488 kg/m2] live load for two-way slabs), boundary conditions, and spans, among other factors. Structures with aggressive construction Type 1A embedded galvanic anodes on bridge pier schedules resulting in heavier-than-planned construction loads, premature form removal, and accelerated shoring and re-shoring may result in members or structures with excessive deflections or having vibration issues that should be assessed for safety and comfort of the occupants. Deflections exceeding the code-prescribed design limits may be acceptable to the owner or user provided the member or structure performance is not adversely affected. 4.7—Additions, 4.8—Alterations, 4.9—Changes in occupancy In case a structure receives additions, alterations, or has a change in occupancy, ACI 562 requires that the LDP assess and rehabilitate the structure and ensure that any change in loading, addition, or alteration warrants that the existing structure or member with the addition(s), alteration(s), or changes in occupancy conforms to the IEBC (refer to Table 4.1). Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 30 University of Toronto User. @Seismicisolation @Seismicisolation Tensioning new post-tensioning cables on parking deck repair project 31 University of Toronto User. Overview The primary objective of building standards is to limit risk and establish the safety of structures. Chapter 5 of ACI 562 addresses the licensed design professional (LDP)’s responsibilities for determining the load and strength requirements throughout the assessment, repair, rehabilitation, or strengthening process, both relative to the member under investigation and the structure as a whole. The basic requirements for the determination of design strength ϕRn and required strength U of existing structural members subject to assessment or repair and rehabilitation design are described. Chapter 5 of ACI 562 also addresses loads and factored load combinations, and specifically the treatment of loading scenarios that may change over the duration of the repair, rehabilitation, or strengthening work. Unlike new construction, this work may take place while the structure remains in service. Additional factored load combinations are provided for repairs with external reinforcing systems to achieve a minimum level of safety during extraordinary events. The assessment of existing buildings is different from the design of new buildings because the as-built geometries, in-place materials, and material properties can be documented as required. Having knowledge of these attributes greatly reduces the uncertainty associated with the parameters used in the design of reinforced concrete buildings. As such, the strength reduction factors used for design in ACI 318-19 may, in some cases, be unnecessarily conservative. Chapter 5 of ACI 562 addresses this difference for existing buildings and specifies when increased strength reduction factors may be used for assessment and repair design. These alternate strength reduction factors are the same as those in Chapter 27 of ACI 318-19, which applies to strength assessment of existing @Seismicisolation structures. @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 5—Loads, Factored Load Combinations, and Strength Reduction Factors GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES 5.1—General The minimum level of safety regarding load and strength requirements for a given project are stipulated in the designbasis code, which should be determined as described in Chapters 1 and 4 or Chapter 1 and Appendix A of ACI 562, following the general procedure presented in Chapter 1 of this guide. When the design-basis code requires use of ACI 318-19 for the assessment or repair design, the load factors, factored load combinations, and strength reduction factors are obtained from Chapter 5 of ACI 562. When the designbasis code references other standards, such as the original building code, that specify loads, factored load combinations, and strength reduction factors that are different than ACI 318-19, certain sections of ACI 562 Chapter 5 will not apply. The application of Chapter 5 in ACI 562 is dependent on reference to ACI 318-19 in the design-basis code, as shown in Fig. 5.1. As described in ACI 562 Section 5.1.2, it is not permitted to use load factors and factored load combinations from the original building code with strength reduction factors from ACI 562 Chapter 5, or load factors and factored load combinations from ACI 562 Chapter 5, with strength reduction factors from the original building code. Load factors and strength reduction factors within a given code are calibrated to achieve an appropriate level of reliability in design. Mixing factors from different codes may result in an unsatisfactory level of reliability. The LDP should exercise judgment in applying loads from current editions of ASCE/SEI 7, ASCE/SEI 37, or ASCE/SEI 41 to previous factored load combinations, considering that load magnitudes and combinations may have changed over the years. Wind loads in particular were changed in recent editions of these ASCE/SEI standards. Using current wind loads with factored load combinations, load factors, and strength reduction factors from an earlier code may not yield the desired level of safety that was intended in the development of the current wind loads in these standards. If the loads specified in the current building code have increased significantly from the loads specified in the original building code, then the demand-to-capacity ratio of a member can be evaluated using procedures in ACI 562, R4.5.2 or RA.5.2. Generally, use of current gravity loads with load factors, factored load For repair and rehabilitation design: Follow procedures in Chapters 1 and 4 or Chapter 1 and Appendix A to determine the design-basis code. No Is ACI 562-19 part of the design-basis code? Only Sections 5.1.1, 5.1.3, 5.1.5, and 5.2.1 are applicable for the repair design. * Where permitted by the original building code, allowable stress design (ASD) principles may be used. All sections of Chapter 5 are applicable, in particular: • Determine loads in accordance with Sections 5.1.2 and 5.1.4; factored load combinations in accordance with Section 5.2.3; and strength reduction factors in accordance with Section 5.3. • If an unprotected external reinforcing system is used, ACI 562 requires that the required strength of the unrepaired structure satisfy the factored load effects determined according to Section 5.5.2 or 5.5.3. Fig. 5.1—Flowchart for determination of loads, factored load combinations, and strength reduction factors for repair and rehabilitation design. @Seismicisolation @Seismicisolation University of Toronto User. Use the design-basis code to determine the factored loads, factored load combinations, and strength reduction factors*. Yes Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 32 combinations, and strength reduction factors from the original building code may be prudent if the design-basis code is the original building code. The LDP for the project should use the design-basis code loads during construction. ACI 562 Section 5.1.3 requires shoring and temporary construction to be designed to support loadings that may vary throughout the repair process. When shoring and temporary construction is required to support occupied structures and ACI 562 is the design-basis code, the loadings are specified to conform to ASCE/SEI 7. If, however, the structure or portion of the structure where work is performed is unoccupied during the construction period, then less-stringent temporary design loads could be specified based on ASCE/SEI 37. ASCE/SEI 37 provides minimum load requirements during construction, which can often reduce the demand on shoring and temporary construction based on a probabilistic assessment of the factored loads and factored load combinations that could occur during the finite construction period. Section 5.1.4 of ACI 562 requires the LDP to consider the unique circumstances involved in assessing and designing repairs, rehabilitations, and strengthening of existing structures. Several considerations that may not have been specified or present during the original design and construction may be applicable, including secondary and service load conditions such as those mentioned in Section R5.1.5 of ACI 562. These load consideration requirements are applicable regardless of the design-basis code used for the assessment or repair design. reinforcement jacking force for the design of post-tensioned anchorage zones, respectively, are specified in Sections 5.2.4 and 5.2.5 of ACI 562; these load factors are also consistent with the design methodology of ACI 318-19. 5.3—Strength reduction factors for repair design For the repair design, the strength reduction factors, ϕ, in Section 5.3 of ACI 562 are used when the design-basis code references ACI 318-19; these factors are consistent with those provided in ACI 318-19. The strength reduction factors of Section 5.3 of ACI 562 are used in conjunction with the loads specified in Section 5.1.4 of ACI 562 and the factored load combinations specified in ASCE/SEI 7, as referenced through Section 5.2.3 of ACI 562. When designing a repair of an existing member or structure, the LDP can use the flowchart presented in Fig. 5.1 as a guide to determine the loads, factored load combinations, and strength reduction factors for the repair design. If ACI 562 is part of the design-basis code for assessment and rehabilitation design, then the strength reduction factors of Section 5.3 of ACI 562 apply. The project examples included within this guide illustrate how Fig. 5.1 is used. University of Toronto User. 5.4—Strength reduction factors for assessment For assessment of a member, the design strength reduction factors, ϕ, in Section 5.4.1 of ACI 562 are used when the design-basis code references ACI 318-19. The higher strength reduction factors in Section 5.4.1 of ACI 562 may be used when the as-built member dimensions and reinforcement location are 5.2—Load factors and load combinations determined as part of the structural assessment, as defined in Section 5.2.1 of ACI 562 requires the LDP to consider the Chapter 6 of ACI 562, and material properties are determined existing loads on the structure as well as the effects of the per Section 6.3.5 of ACI 562. These increased strength reducrepair process. For example, removal of concrete can cause tion factors are consistent with those provided in Chapter 27 of stresses to be redistributed to other members of the structure ACI 318-19 and are justified by the improved reliability due or within the member itself. If shoring is provided in this to the use of accurate field-obtained material properties and scenario, the ACI 562 Code requires the LDP to consider the actual in-place dimensions. If the increased strength reduction effect of shoring loads transmitted to supporting members factors of Section 5.4.1 of ACI 562 are used, the assessment of the existing structure during each phase of the repair. should be performed using the factored load combinations Additionally, stresses in the member under repair need to specified in ASCE/SEI 7, per Section 5.2.3 of ACI 562. Project be assessed at each stage of the repair process to properly Example 3 provides a specific example of using the strength assess the influence of shoring, concrete removal, concrete reduction factors of Section 5.4 of ACI 562. replacement, and eventual return to service. If shoring is not When evaluating a member using material properties provided, the ACI 562 Code requires the LDP to consider based on Tables 6.3.1a through 6.3.1c of ACI 562, the stresses in the remaining elements of the original member strength reduction factors should not be greater than the combined with stresses in the repair and original member factors in Section 5.3 in ACI 562. If the material properacting compositely. The LDP should consider the effects and ties are estimated based on Tables 6.3.1a through 6.3.1c of sequencing of the repair process, both on the member being ACI 562, there is still some uncertainty regarding the actual assessed and the structure as a whole. Consideration of the material properties, which is reflected in the lower strength repair process is applicable regardless of the design-basis reduction factors in Section 5.3 of ACI 562. code used for the repair design. When performing an assessment of an existing member or Section 5.2.3 of ACI 562 stipulates that the required structure, the LDP can use the flowchart presented in Fig. 5.4 strength U should be at least equal to the effects of the as a guide to determine the loads, factored load combinations, factored load combinations specified in ASCE/SEI 7 for and strength reduction factors for the assessment. If ACI 562 is the applicable design loads from the design-basis code. part of the design-basis code, then the strength reduction factors The factored load combinations in ASCE/SEI 7 are consisof Section 5.4 of ACI 562 apply. Each of the project examples tent with those in ACI 318-19. For example, a load factor included within this guide illustrate how Fig. 5.4 is used. of 1.0 and 1.2 for the internal load effects due to reactions For both assessment and rehabilitation design, Sections induced by prestressing and for the maximum prestressing @Seismicisolation 5.3.4 and 5.4.3 of ACI 562 specify the same load reduc@Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 5—Loads, Factored Load Combinations, and Strength Reduction Factors33 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES tion factor of 0.6 for all plain structural concrete members independent of the member’s behavior, flexure, compression, shear, or bearing, because plain concrete failures are usually brittle. 5.5—Additional load combinations for structures rehabilitated with external reinforcing systems Section 5.5.1 of ACI 562 is used to determine the minimum required strength of an existing structure that will be repaired with an external reinforcing system, including, but not limited to, bonded fiber-reinforced polymer (FRP), bonded or anchored steel plates, or external post-tensioning systems. The minimum required strength, expressed in ACI 562 Sections 5.5.2 and 5.5.3 equations, ensures sufficient strength of members with external reinforcing systems when subject to damage by vandalism or fire and elevated temperatures that may limit the performance of the external reinforcing system. The LDP may specify protection to No exposed reinforcing systems to resist fire, collision, and vandalism. Repaired members or structures with external reinforcing systems exposed routinely to elevated temperatures are not addressed in this chapter and the LDP is referred to Section 7.9 of ACI 562. The LDP needs to verify that the strengthened structure or members have at least the capacity to exceed the effects of the factored load combinations specified in ACI 562, Sections 5.5.2 and 5.5.3. The factored load combinations in Section 5.5.2, Eq. (5.5.2a) and (5.5.2b), are intended to minimize the risk of overload or damage to the existing unstrengthened members in the case where, during normal operating conditions, the nonmechanically bonded external reinforcing system is damaged. This would give the owner ample time to be alerted of the damage and allow the structure to remain in service until the damaged external reinforcing system is repaired. For assessment purposes: Is ACI 562-19 part of the design-basis code? Yes Use the factored loads, factored load combinations, and strength reduction factors* as specified in the original building code for the assessment. Sections 5.1.1, 5.1.3, and 5.1.5 are applicable during the evaluation. Yes Use loads in accordance with Section 5.1.4, factored load combinations in accordance with Sections 5.2.2 and 5.2.3, and strength reduction factors in accordance with Section 5.4.1 for the assessment Have the in-place structural element dimensions, reinforcement location, and material properties been determined in accordance with Section 5.4.1 and Ch. 6? No Use loads in accordance with Section 5.1.4, factored load combinations in accordance with Section 5.2.3, and strength reduction factors in accordance with Section 5.3 for the assessment. Fig. 5.4—Flowchart for determination of loads, factored@Seismicisolation load combinations, and strength reduction factors for assessment. @Seismicisolation University of Toronto User. *Where permitted by the original building code, allowable stress design (ASD) principles may be used. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 34 ϕRn ≥ 1.1D + 0.5L + 0.2S (5.5.2a) ϕRn ≥ 1.1D + 0.75L (5.5.2b) where D, L, and S are the dead, live, and snow loads, respectively, as defined in Chapter 5 of ACI 562; φ is the strengthreduction factor obtained from ACI 562 Section 5.3 or 5.4; and Rn is the nominal strength of the structure without the external reinforcement. These equations also serve as a limit on the amount of strengthening that can be resisted by the external reinforcement. Repaired structures with external reinforcement need to satisfy Eq. (5.5.3) without considering the added external reinforcement to ensure that the repaired member has sufficient strength during a fire event. ϕexR ≥ (0.9 or 1.2)D + 0.5L + 0.2S (5.5.3) where fex = 1.0; and R is the nominal resistance of the structure, calculated using the probable material properties during a fire event, determined based on the required fire rating duration. The dead load factor of 0.9 governs when the dead load effect reduces the total factored loads effect. The load effect from fire is a secondary effect caused by restraint to thermally induced expansion, resulting in thrust and moment redistribution. Except for simple span members, the analysis of a member exposed to fire should be based on a design fire scenario and its effect on the behavior of the overall structure. The analysis will require accurate modeling of numerous parameters, including fire characteristics, boundary conditions, connection fixity, heat transfer, and deformations. A broader discussion regarding the effect of fire on buildings can be found in NIST Technical Note 1681 (National Institute of Standards and Technology). Guidance regarding the reduced strength of concrete under exposure to elevated temperature is provided in ACI 216.1. The factored load combination given in ACI 562 Section 5.5.3 is based on provisions contained in ASCE/SEI 7. As indicated in the commentary of ASCE/SEI 7, provisions regarding loading from extraordinary events are not intended to replace traditional approaches to ensure fire endurance (that is, fire ratings specified in model building codes based on ASTM E119 using full service loads). However, the provisions of ASCE/SEI 7, and therefore the factored load combination of ACI 562 Section 5.5.3 might be determined by the authority having jurisdiction to be acceptable based on the alternative methods of design and construction provision contained in model building codes. Therefore, the LDP responsible for repair of the structure should consult Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 5—Loads, Factored Load Combinations, and Strength Reduction Factors35 University of Toronto User. New post-tensioning cables installed on parking deck repair project @Seismicisolation @Seismicisolation GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Hydrodemolition concrete removals on waffle floor slab with involved parties to determine if use of ACI 562 Section 5.5.3 is a viable approach for satisfying the applicable building code as relates to fire resistance. A sustained live load, as in libraries or warehouses, or a live load exceeding 100 lb/ft2 (488 kg/m2) will receive an increased live load factor of 1.0 in Eq. (5.5.2a), (5.5.2b), and (5.5.3). When considering the effect of fire on a structure, the loads associated with firefighting operations such as additional water surcharge and wetted materials need to be included in the analysis. The commentary to ACI 562 recommends a live load of 20 lb/ft2 to account for wetted material during firefighting operations. The provisions of Sections 5.5.2 and 5.5.3 of ACI 562 are not applicable if ACI 562-19 is not part of the design-basis code. The strength reduction factors in Section 5.3 or 5.4 of ACI 562 should be used with the factored loads provided in Eq. (5.5.2) and (5.5.3) of ACI 562. Project Example 5 illustrates the application of Section 5.5 of ACI 562. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 36 University of Toronto User. @Seismicisolation @Seismicisolation Impulse-response testing being performed on a bridge pier 6.1—Structural assessment A structural assessment consists of documenting the current condition of the structure or member, including the as-built construction and any distress and deterioration. Several assessment tools and approaches are available for use at the judgment of the LDP, including document review, visual survey, material sampling, laboratory evaluation, and destructive and nondestructive testing. A number of publications, including those discussed in ACI 562 Section, R6.1.1, and the related ASTM standards listed in the textbox, are available for guidance and specific aspects of performing assessments of existing concrete structures. Section 6.1 of ACI 562 describes that structural assessment must be performed if required by ACI 562, 1.7.5. It consists of structural evaluation and, if necessary, structural analyses. The goal of a structural assessment is to determine if members or portions of the structure in their current condition have adequate strength and meet serviceability requirements. Structural assessment covers the following @Seismicisolation three steps: @Seismicisolation 37 University of Toronto User. Overview Chapter 6 of ACI 562 provides requirements for conducting a structural assessment of existing concrete members, portions of a structure, or entire structures. The provisions are presented in the order in which a structural assessment would normally be conducted, including provisions for conducting structural evaluation, obtaining and determining material properties, and performing structural analyses. Strength assessment by load testing is also addressed. The assessment method and major tasks that are provided in Chapter 6 and Section 1.7 of ACI 562 are summarized in Fig. 6. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 6—Assessment, Evaluation, and Analysis GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Structural Assessment (Ch. 6) Preliminary Evaluation (Section 1.7) 1. Structural assessment of affected members (Section 6.2). 1. Review of plans and available documents (Section 1.7.1). 2. Existing conditions visually or otherwise assessed for deterioration, damage, or distress (Section 1.7.2). 2. Obtain material properties as required to perform assessment (Section 6.3 or Section 6.4). 3. Preliminary analysis and evaluation to determine strength based on in-place or assumed geometry and material properties (Section 1.7.4). Perform the following as required based on the results of the assessment. 3. Structural analysis of existing member or structure (Section 6.5). Is a structural assessment necessary based on the requirements of Section 6.2.1 or Section 6.2.2? Yes 4. Serviceability assessment of member or structure (Section 6.6). 5. Strength assessment by load testing if appropriate (Section 6.8). Based on results of assessment proceed with design of repair or rehabilitation if required. Perform analysis for design in accordance with Section 6.7. Fig. 6—Summary of assessment methodology of ACI 562. 1. An investigation to establish the in-place condition of the structure in the work area, including environment, geometry, material strengths, reinforcing steel sizes and placement, and signs of distress 2. An evaluation to define the causes of distress, goals of the rehabilitation, and criteria for selection of rehabilitation solution(s) 3. Development of appropriate repair strategies, if required 6.2—Investigation and structural evaluation If the strength of a structure is not in question or there is no reason to suspect structural issues, a structural assessment is not necessary when making improvements to address strength, serviceability, durability, and fire protection requirements. If a preliminary evaluation (ACI 562, 1.7) determines that there is reason to question the strength or behavior of one or more members of the structure, a structural evaluation @Seismicisolation @Seismicisolation University of Toronto User. No Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 38 Is a structural assessment always required? Use of lower-bound default material properties ACI 562 does not require the LDP to perform a detailed structural assessment in cases where the capacity of the structure is known. Consider the following scenarios when a structural assessment would not be required: While in most cases it is conservative to use the lower-bound values for concrete compressive strength and steel reinforcement yield strength, the LDP should use engineering judgment when selecting historic property values from Tables 6.3.1a through 6.3.1c in ACI 562. In some instances, assuming higher strengths may be more conservative. For example, when evaluating a beam column joint, ACI 318-19, 18.7.3.2, requires the net moment strength of the columns be greater than 6/5 the net moment strength of the beams, which is meant to ensure inelastic deformations occur primarily at the beams instead of the columns during a seismic event. When performing this analysis, it may be more conservative to assume higher yield strengths in the beam reinforcement when evaluating the joint. Scenario No. 1: A beam at the lower level of a recently constructed shopping center is impacted by an errant vehicle. The plans and available documents were reviewed by the LDP as part of the preliminary evaluation and indicate the beam was designed to satisfy the required loading. Based on the preliminary evaluation performed by the LDP, the damage is limited to cracking and spalling of the cover at a single beam location. There are no visible signs of damage to the existing reinforcement. Based on the results of the preliminary evaluation, the LDP may proceed with the design of the repair without performing a more detailed structural assessment or structural analysis of the existing beam or structure. @Seismicisolation @Seismicisolation University of Toronto User. Scenario No. 2: An LDP is retained to review the in-place condition of a parking garage that was opened approximately 5 years ago and provide documents for repairs or maintenance. During the preliminary evaluation, the owner shares that the manager has recently started using de-icing salts after receiving complaints regarding ice on the ramps and parking areas. In addition to replacing failed sealant joints and performing other routine maintenance, the LDP is considering a coating or sealer for durability considerations of the salt-exposed deck. The preliminary evaluation performed by the LDP indicates that the garage is in otherwise good structural condition with no signs of deterioration or structural deficiency. The LDP may proceed with the coating system design and durability repairs without performing a structural assessment or structural analysis of the existing deck or garage. In this instance, additional assessment (for example, material sampling to determine chloride levels in the deck) may be considered by the LDP, but is not required based on ACI 562 Sections 6.1.2 and 6.1.3. A chain drag survey of the deck might also be considered prior to performing any coating repairs. should be performed (ACI 562, 6.2.1). The licensed design professional (LDP) may question the capacity of a member or strength of its constituent materials if the member exhibits signs of deterioration, such as spalling, corrosion, or distress, such as wide cracking. As an example, loss of concrete cross section in a compression member or severely corroded tension reinforcement in a beam would likely affect capacity and thus trigger a structural evaluation and analysis of the affected member. The capacity may also be questioned if there is reason to believe the in-place geometry or reinforcement is incorrect. The structural evaluation may be limited to the area identified during the preliminary evaluation; however, if repairs are required on a member, the LDP should determine if an assessment is required on similar members (ACI 562, 6.2.3). If the structural evaluation conducted as part of this assessment determines that the strength of the structure is in fact not in question, a structural analysis is not required (ACI 562, 6.2.1 and 6.2.2). The Project Examples illustrate various scenarios for determining if a structural assessment is necessary. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 6—Assessment, Evaluation, and Analysis39 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Useful references for performing evaluations of existing concrete structures The following standards from ASTM International may provide guidance for performing evaluations of existing concrete structures. • ASTM C42/C42M, “Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of Concrete” • ASTM C597, “Standard Test Method for Pulse Velocity Through Concrete” • ASTM C803/C803M, “Standard Test Method for Penetration Resistance of Hardened Concrete” • ASTM C805/C805M, “Standard Test Method for Rebound Number of Hardened Concrete” • ASTM C856, “Standard Practice for Petrographic Examination of Hardened Concrete” • • • • ASTM C876, “Standard Test Method for Corrosion Potentials of Uncoated Reinforcing Steel in Concrete” ASTM C1383, “Standard Test Method for Measuring the P-Wave Speed and the Thickness of Concrete Plates Using the Imapct-Echo” ASTM C1740, “Standard Practice for Evaluating the Condition of Concrete Plates Using the Impulse-Response Method” ASTM D4580/D4580M, “Standard Practice for Measuring Delaminations in Concrete Bridge Decks by Sounding” ASTM D6432, “Standard Guide for Using the Surface Ground Penetrating Radar Method for Subsurface Investigation” 6.3—Material properties Determining the material properties of an existing concrete member or structure is critical to performing a structural analysis. ACI 562 Section 6.3 describes the requirements and various methods for obtaining material properties. When required by ACI 562, concrete compressive strength and steel reinforcement yield strength must be determined (ACI 562, 6.3.2). The concrete compressive strength and steel reinforcement yield strength used for analysis can be obtained by one of three methods (ACI 562, 6.3.3): a. Material properties based on historical information (ACI 562, Tables 6.3.1a through 6.3.1c) b. From available design drawings, specifications, or previous testing documentation (ACI 562, 6.3.4) c. Physical testing of in-place or sampled materials (ACI 562, Section 6.4) Figure 6.3 summarizes the process for determining material properties in accordance with ACI 562. Load test being performed @Seismicisolation @Seismicisolation University of Toronto User. The LDP needs to determine the nature of concerns with the as-built construction or the structural implications of distress and deterioration. The structural assessment should then be tailored to obtain information so that these concerns can be evaluated and, if necessary, a structural analysis performed. While there are commonalities between many structural assessments, it is not unusual for unique information to be required to evaluate specific concerns. If an analysis is to be performed, the structural assessment should include, per ACI 562, 6.2.4, documentation of existing conditions including any construction deficiencies or deterioration as required for the analysis which, as a minimum, per ACI 562, 6.2.5, includes the following: a. As-measured structural section properties and dimensions b. The presence and effect of any alterations to the structure c. Load, occupancy, or usage changes that are different from the original design • Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 40 No No Has visible material deterioration, degradation, or distress occurred (Section 6.3.4)? Do available drawings, specifications, and other existing construction documents provide sufficient information to characterize the material properties (Section 6.3.1)? Use material properties from either: (a) historical material property data provided in Tables 6.3.1a through 6.3.1c* or (b) physical testing in accordance with † Section 6.4 . Yes Yes Use material properties from either: (a) existing drawings, specifications, or documentation, or (b) physical testing in † accordance with Section 6.4 . Perform physical testing in accordance † with Section 6.4 as required to confirm material properties (Section 6.3.4C). * If data is not given in either Table 6.3.1b or 6.3.1c, the historic default value for yield strength should be taken as 27,000 psi (185 MPa) (Section 6.3.6). † Locations and numbers of material samples should be defined by the LDP (Section 6.3.5). Fig. 6.3—Summary of process to determine material properties in accordance with ACI 562, 6.3. The material properties in the tables are lower limits and may be conservative for many structures. More accurate material properties can be obtained by sampling and testing the actual concrete and steel. In general, ACI 562 permits the use of material properties provided in the original construction documents or material test reports, except in cases where visible material deterioration has occurred (ACI 562, 6.3.4). In cases where material degradation may have occurred, such as alkali-silica reaction, sulfate attack, delayed ettringite formation, freezingand-thawing damage, or reinforcement corrosion, additional material testing may be required to verify the current material properties for the purpose of assessing the effects of material degradation on strength and durability. The various approaches described in ACI 562 Section 6.3 provide flexibility to the LDP in determining the material properties of existing construction. When material properties are determined by material sampling and testing and the as-built element dimensions and reinforcement location are determined, the LDP can take advantage of higher strength reduction factors shown in ACI 562, 5.4.1. Example 6.1 highlights the various approaches to determining material properties and the potential benefit when higher strength reduction factors can be used. @Seismicisolation @Seismicisolation University of Toronto User. When dealing with existing structures, previous drawings, specifications, or test reports are often unavailable. Furthermore, obtaining and testing material samples may not be possible or desirable for a number of reasons. For example, destructive sampling is often undesirable in historic structures. Other times, accessibility or building operations may make sampling difficult or costly to the owner. Accordingly, ACI 562 Tables 6.3.1a through 6.3.1c provide default historical data for use during the structural analysis. These tables include concrete material properties from 1900 to present and steel reinforcement data from 1911 to present. When the steel grade is unknown, the lowest grade of reinforcement for a given historic period is required to be used (ACI 562, 6.4.4). If the historic data for the reinforcement is not included in the tables, a lower-bound yield strength of 27,000 psi (185 MPa) is required to be used (ACI 562, 6.3.6). In some cases, it may be possible to determine the grade of reinforcement based off the bar markings from original fabrication. The Concrete Reinforcing Steel Institute (2010) has information available regarding current reinforcing bar marking sequences, as well as markings used with historical reinforcement. The Wire Reinforcement Institute (2014) has information available regarding historical data on wire, triangular wire fabric mesh and welded wire reinforcement. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 6—Assessment, Evaluation, and Analysis41 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Example 6.1—Methods for determining material properties Background New mechanical equipment is to be installed within the attic of a historic academic building constructed in 1930. The concrete framing that supports the attic space consists of a concrete slab with integral inverted T-beams. The original construction documents are available and show that the reinforcing for the 6 in. (150 mm) wide by 12 in. (300 mm) tall beams consist of two 5/8 in. (16 mm) deformed diameter bars at top and bottom. No material properties are indicated on the construction documents. strength or the steel reinforcement yield strength, which are required for the structural analysis. Historic values As an initial check, the LDP uses the historical data from Tables 6.1a and 6.1b (Tables 6.3.1a and Table 6.3.1b, respectively, in ACI 562) to perform an analysis of the existing structure with its current loading configuration. Based on the tables, a concrete compressive strength of 2000 psi (14 MPa) is used for the analysis. A default yield strength of 33,000 psi (230 MPa) is used for the steel reinforcement based on the age of construction and the fact that no information is available regarding the grade of steel. Based on these values and the strength reduction factors of ACI 562, 5.3.2, a demand-capacity ratio of 0.90 was calculated for the existing configuration, indicating the strength of the existing member is adequate for the current loading. When the additional loading for the new mechanical equipment is considered, however, the controlling demandcapacity ratio of the beam increases to 1.27, indicating that the beams require strengthening. For the analysis using historic values, the strength Evaluation The LDP is retained by the owner to evaluate the capacity of the beams to support the loading from the new mechanical equipment. ACI 562 is applicable, as described in ACI 562, 1.1.2. In accordance with ACI 562, 6.2.5, the LDP measures section dimensions and confirms that the as-built member geometry agrees with the construction documents. The LDP also verifies the quantity and cover depth to the reinforcing bars using a concrete cover meter (pachometer). The existing documents do not provide sufficient information to characterize the concrete compressive Table 6.1a—Default compressive strength of structural concrete, psi (MPa)* (after ACI 562 Table 6.3.1a) Time frame 1900-1919 1920-1949 1950-1969 1970-present Beams 2000 (14) 2000 (14) 3000 (21) 3000 (21) Slabs 1500 (10) 2000 (14) 3000 (21) 3000 (21) Columns 1500 (10) 2000 (14) 3000 (21) 3000 (21) Walls 1000 (7) 2000 (14) 2500 (17) 3000 (21) Note: Adopted from ASCE/SEI 41-13. Table 6.1b—Default tensile and yield strength properties for steel reinforcing bars for various periods, psi (MPa)* (after ACI 562 Table 6.3.1b) Year Grade Minimum yield, psi (MPa) Minimum tensile, psi (MPa) 1911-1959 1959-1966 1966-1972 1972-1974 1974-1987 1987-present Structural† 33 (230) Intermediate† 40 (280) Hard† 50 (345) 33,000 (230) 40,000 (280) 55,000 (380) 70,000 (485) 60 (420) 65 (450) 70 (485) 75(520) 50,000 (345) 60,000 (420) 65,000 (450) 70,000 (485) 75,000 (520) 80,000 (550) 90,000 (620) 75,000 (520) 80,000 (550) 100,000 (690) — X X X — X — X — — — — X X X X X X X X X X X X X X X X X X X X X X X X X Note: Adopted from ASCE/SEI 41-13 * An entry of X indicates the grade was available in those years. †The terms “structural,” “intermediate,” and “hard” became obsolete in 1968. @Seismicisolation @Seismicisolation X — — — — University of Toronto User. * Footings 1000 (7) 1500 (10) 2500 (17) 3000 (21) Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 42 reduction factors for flexure and shear were 0.90 and 0.75, respectively. Material testing Given the outcome of the analysis using historical properties, the LDP recommends a material sampling program to better determine the actual material properties. Samples were obtained, tested, and the results evaluated in accordance with Section 6.4 of ACI 562. Core sampling and testing are to be performed in accordance with ASTM C42/C42M. The ASTM procedure provides a standard moisture conditioning protocol for the concrete core samples and a correction for core length to diameter ratio. For situations when the core samples do not satisfy ASTM C42 requirements, the procedure in ACI 214.4R can be followed. The equivalent concrete strength (fceq) was determined per ACI 562 Eq. (6.4.3.1), and the equivalent yield strength as determined per ACI 562 Eq. (6.4.6), using the following material properties: f c (average) = average core strength ƒceq = equivalent specified concrete strength per ACI 562 Eq. (6.4.3.1) determined in accordance with ACI 562, 6.3.5, the LDP can take advantage of increased strength reduction factors per ACI 562, 5.4. Using the material property test results and increased strength reduction factors results in a demand-capacity ratio of 1.06 for the beam when considering the new mechanical equipment. The strength reduction factors for flexure and shear were 1.0 and 0.80, respectively. Rather than proceed with a design to strengthen the beams, the LDP elects to collect two more samples for yield strength testing of the reinforcement. The additional samples will improve the coefficient of variation modification factor.The revised steel reinforcement testing results were calculated and are shown in Table 6.1e. The corresponding demand-capacity ratio of the beam reduces to 0.99 based on the revised testing results for the steel reinforcement. Thus, the beams satsify the strength requirement for the new mechanical equipment. Table 6.1c—Concrete core results based on ACI 562 Eq. (6.4.3.1) (6.4.3.1) (kcV ) 2 + 0.0015 f ceq = 0.9 f c 1 − 1.28 n ƒy (average) = average steel yield strength value from tests ƒyeq = equivalent yield strength of steel reinforcement per ACI 562 Eq. (6.4.6) f yeq = ( f y − 3500) exp(−1.3k sV ) (6.4.6, in.-lb) (6.4.6, SI) Results 8 f c (average) 6218 psi (42.9 MPa) V kc fceq 0.15 1.10 5095 psi (35.1 MPa) Table 6.1d—Steel reinforcement results based on ACI 562 Eq. (6.4.6) Variable n fy (average) V ks fyeq kc = concrete coefficient of variation modification factor per ACI 562 Table 6.4.3.1 ks = steel coefficient of variation modification factor per ACI 562 Table 6.4.6 Results 4 42,225 psi (291.1 MPa) 0.05 2.34 33,261 psi (229.3 MPa) n = number of sample tests V = coefficient of variation determined from testing Results from the use of Eq. (6.4.3) and (6.4.6) in ACI 562 for this scenario are presented in Table 6.1c and 6.1d. The material property test results yield an equivalent specified strength for the concrete of more than twice the historical value and a comparable equivalent yield strength for the steel to the historical value. Because the material properties were Table 6.1e—Revised steel reinforcement results based on ACI 562 Eq. (6.4.6) @Seismicisolation @Seismicisolation Variable n ƒy (average) V ks ƒyeq Results 6 42,860 psi (295.5 MPa) 0.04 1.69 36,049 psi (248.5 MPa) University of Toronto User. f yeq = ( f y − 24) ( −1.3 ksV ) Variable n Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 6—Assessment, Evaluation, and Analysis43 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES sampling program. As a minimum, two concrete samples are required to determine kc and three steel samples are required to determine ks. The equivalent specified strength obtained from Eq. (6.4.3.1) can be used in strength equations with the strength reduction factors from Chapter 5. ACI 562, 6.4.3.2, permits the use of nondestructive testing methods for assessment of in-place concrete compressive strength provided that a valid correlation of the nondestructive test method is established between the nondestructive results with data obtained from testing representative core samples. ACI 228.1R provides information for developing statistical correlations between nondestructive testing and core test results and the following nondestructive testing methods: a. ASTM C597, “Standard Test Method for Pulse Velocity Through Concrete” b. ASTM C803/C803M, “Standard Test Method for Penetration Resistance of Hardened Concrete” c. ASTM C805/C805M, “Standard Test Method for Rebound Number of Hardened Concrete” d. ASTM C873/C873M, “Standard Test Method for Compressive Strength of Concrete Cylinders Cast in Place in Cylindrical Molds” e. ASTM C900, “Standard Test Method for Pullout Strength of Hardened Concrete” f. ASTM C1074, “Standard Practice for Estimating Concrete Strength by the Maturity Method” If welding of reinforcement is required as part of repair or rehabilitation, ACI 562 requires that the carbon equivalent of the existing reinforcing steel be calculated prior to welding, as required by AWS D1.4/D1.4M. In general, the lower the carbon equivalent, the more weldable the steel. Steel with higher carbon equivalent is susceptible to cracking in the heat affected zone. Most common reinforcing bars used in construction are ASTM A615/A615M and ASTM A706/ A706M. Welding of ASTM A615 reinforcing bars should be approached with caution, as no provisions are included in AWS D1.4 to enhance its weldability; however, ASTM A706 reinforcing bars are manufactured with a chemical Local zone reinforcement installed within the post-tensioned Preparation for beam section enlargement to add shear anchorage zone @Seismicisolation capacity to the structural member @Seismicisolation University of Toronto User. 6.4—Test methods to determine or confirm material properties ACI 562 Section 6.4 presents requirements for test methods to obtain in-place mechanical properties of five different types of materials: concrete (ACI 562, 6.4.2 and 6.4.3), steel reinforcement (ACI 562, 6.4.4 through 6.4.6), connector steel (ACI 562, 6.4.7), embedded structural steel (ACI 562, 6.4.8), and prestressing steel reinforcement (ACI 562, 6.4.9). ACI 562 references ASTM C42/C42M and ASTM C823/C823M for concrete sample removal and testing, ASTM A370 for testing yield and tensile strength of steel reinforcement and structural steel, and ASTM A1061/A1061M for testing prestressing reinforcement. Care should be taken in sampling prestressing steel as the steel may still be under some tension and significant energy can be released when the steel is cut. Nondestructive testing may be used to locate existing reinforcement and other embedded material in existing concrete members. This is critical when taking core samples from existing concrete members as the presence of reinforcement or other foreign material such as conduits or wood may adversely affect the strength test results. Core samples should be similar in length-to-diameter ratio as standard strength cylinders, thus the recommended maximum length-to-diameter ratio of 2 to 1. Cores with length-to-diameter ratio of less than 1 are unreliable, yield erroneous test results, and should be rejected. The minimum acceptable core diameter per ASTM C42/C42M is 3.70 in. (94 mm). Smaller-diameter cores are likely to have more variability and a lower strength (Bartlett and MacGregor 1994b). ACI 562 provides latitude for the LDP to determine the appropriate material sampling and testing program for each particular project, while also providing minimum requirements for sampling, testing, and calculating the equivalent specified strength of the various materials. The equations provided for calculating the equivalent specified strength (Eq. (6.4.3.1), (6.4.6), and (6.4.8) in ACI 562) reflect the uncertainty of sample standard deviation for a small sample size. The coefficient of variation modification factors (kc and ks) provide a means to effectively reduce the equivalent specified strength due to the smaller sample sizes. This provides additional flexibility to the LDP to determine an appropriate Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 44 Unique analysis considerations Numerous situations are encountered with existing structures that require unique analysis considerations, both for the existing structure and the design of repairs. ACI 562 specifies that the LDP consider the various analysis aspects of each situation. Although not intended to be comprehensive, the following scenarios present unique analysis considerations for various cases: • Spalling has occurred at the top side of a continuous girder, resulting in loss of bond at some of the top longitudinal reinforcing steel. The damage may have caused loss of development in the reinforcing steel and additional structural demand in other portions of the existing structure as a result of redistribution of the negative moments. • Full-depth slab repair is required to address top and bottom reinforcing bar corrosion in a parking deck. During repairs, the unbraced length of the adjacent columns could significantly increase composition that is enhanced for welding. ASTM A706 reinforcing bars are typically stamped with a W in the deformation to indicate the bar is weldable. Table 5.2 in AWS D1.4 defines the required carbon equivalent for various size reinforcement. If the carbon equivalent is not less than the value indicated in Table 5.2 of AWS D1.4, then the bars should be preheated as required by AWS D1.4 to preclude the formation of microcracking in the heat affected zone. • • evaluated when identified (ACI 562, 6.6.1). Serviceability concerns may be related to the design strength of a member. If this occurs, the member should be evaluated as described by ACI 562 Chapter 6. A service-load-level analysis as described in ACI 562, R6.5.1, may also be required to evaluate deflections and expected crack size and distribution. The LDP should investigate the effect of floor levelness, vibrations, and deflections on the structural performance and to determine if it is acceptable to the owner and users of the structure. These criteria should be established for the structure based upon the intended use of the structure and should consider the existing material properties, existing geometry of the members, and the condition of the existing members. 6.7—Structural analysis for repair design Section 6.7 of ACI 562 specifies the minimum requirements for the structural analysis used for repair design. As with performing a structural analysis of existing structures, there are several unique considerations that are not typically considered during design of new members or structures. The provisions of ACI 562 are focused on requiring that the LDP consider the actual performance and behavior of the repaired system. These considerations include the sequence of the repair process, the variability of section properties, and the composite action (or lack thereof) in the repair and substrate. These provisions are presented in Sections 6.7.1 through 6.7.3 of ACI 562. ACI 562, 6.7.4, requires several seismic considerations as part of the analysis for repair design. These provisions are focused on requiring that the seismic response of the repaired 6.6—Structural serviceability structure has been considered by the LDP. The particulars ACI 562 requires that serviceability concerns such as unusual of seismic rehabilitation, including analysis, are not specificracking, excessive deflections, floor levelness, vibrations, cally prescribed in ACI 562, as these are addressed through water infiltration or leakage, and excessive heat exposure @Seismicisolation be reference to ASCE/SEI 41 and ACI 369R. @Seismicisolation University of Toronto User. 6.5—Structural analysis of existing structures Section 6.5 of ACI 562 specifies the minimum requirements for performing a structural analysis of existing structures. The goal of the analysis is to accurately model the current condition of the structure as a whole and the member under assessment in particular. This includes accounting for the as-built geometry and existing material properties, as discussed in ACI 562, 6.2 and 6.3, respectively. Although the specific method of analysis is left to the judgment of the LDP, ACI 562 requires that the analysis consider material degradation, bond loss, redistribution of forces, modified load paths, and previous repairs or modifications (ACI 562, 6.5.4 through 6.5.6). Material degradation and corrosion of reinforcement often lead to spalling and loss of concrete bond. Any analysis of the existing structure should consider the current state of the structural system, included any associated bond loss. The LDP is cautioned that member deterioration or damage may result in redistribution of internal forces that is different than that assumed in the original design. The redistribution of forces may be determined by analysis or testing. • and temporary bracing of the column may be required. Alterations as a result of change of occupancy will include new openings in a two-way slab. The demolition for the alteration may result in redistribution of existing moments and shear forces in the remaining structure. Damage, deterioration, or repairs of prestressed concrete structure that may have resulted or will result in prestressing force release (reference ACI 562, 7.6.4). Repairs that affect the development of prestressing steel reinforcement may reduce member capacity. Concrete spalling has occurred on a column. The concrete removal during repair may result in redistribution of internal forces that are locked in. The strength of such columns should be considered in accordance with provision Section 6.5.4 in ACI 562. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 6—Assessment, Evaluation, and Analysis45 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES 6.8—Strength evaluation by load testing For some structures, it may be difficult to document the as-built construction and the current conditions in sufficient detail to have confidence that a structural analysis reflects actual structural behavior with a reasonable degree of accuracy. Similarly, the effectiveness of proposed repairs may need to be confirmed. In such cases, load testing might be an option to determine if an existing structure requires repair and rehabilitation or to verify the adequacy or performance of repair and rehabilitation measures. ACI 562, 6.8, permits the use of load testing to supplement structural analysis or to demonstrate the strength of the original or repaired structure. ACI 562, 6.8.1, specifies that load testing needs to be in accordance with ACI 437.2, which establishes the minimum requirements for the test load magnitudes, load test procedures, and acceptance criteria applied to existing concrete structures. ACI 437.2 was developed specifically for use with ACI 562 and contains provisions for both a cyclic load test and a monotonic load test, which provides the LDP with flexibility in determining which procedure is best for a particular application. The load test procedure presented in Chapter 27 of ACI 318-19 presents a similar monotonic test procedure and acceptance criteria. The LDP may waive the deflection limit of ℓt/180 set in ACI 437.2 when the tested member is not damaged by excessive deflections or when the residual deflection criteria is satisfied. If retesting is required because the member or structure failed the cyclic load test, the LDP can waive the deflection limit of ℓt/180. In some cases, in-place load tests in accordance with ACI 437.2 may not be practical or necessary. Accordingly, ACI 562, 6.8.5, permits the use of full or scale models to supplement the structural analysis. The LDP should document experimental model analysis results, interpret the results, and correlate the results with the in-place condition of the structure. 6.9—Recommendations The structural evaluation performed on a member or structure are the basis for recommending whether the member or structure should be repaired or rehabilitated. If a member or structure needs to be repaired or rehabilitated, then the work should be performed in accordance with ACI 562. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 46 University of Toronto User. @Seismicisolation @Seismicisolation Steel bracing installed prior to concrete removals at core walls, columns, and perimeter walls (plywood sheeting was installed to protect steel members from damage during the demolition process) 7.1—General Structural repairs need to be designed so that the repaired structure, including members and connections, have the required strength and serviceability specified by the design-basis code and ACI 562. A repaired section is considered to be the combination of the installed repair material(s) and the substrate material(s). Determination of the design capacity need to consider load factors, load combinations, and strength reduction factors in the design-basis code and ACI 562. Durability considerations are described in ACI 562 Chapter 8. 7.2—Strength and serviceability The strength and serviceability behavior of existing concrete structures can be evaluated using information from the original design and construction. When deterioration is present, however, the strength and stiffness @Seismicisolation may no longer be adequately @Seismicisolation 47 University of Toronto User. Overview The need for structural repairs is based upon the results of the preliminary assessment (ACI 562 Chapter 1) or, when required, a more in-depth structural investigation and assessment (ACI 562 Chapter 6). Design-basis code requirements for repair design are determined using ACI 562 Chapter 4 or Appendix A. The design and implementation of structural repairs and the performance of the repaired members and structure vary significantly from the design, construction, and performance of new members and structures. ACI 562 Chapter 7 specifies factors that need to be considered in the design of the structural repairs to achieve the intended performance of the repaired members and structures. The project examples that accompany this guide further illustrate the unique design considerations in the development of a structural repair program in accordance with ACI 562 Chapter 7. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 7—Design of Structural Repairs GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES predicted using the assumptions from the original design. Deterioration and changes to member stiffness associated with repair work may result in the redistribution of internal forces to other portions of the member or to other members not anticipated by the original design. The deterioration may also cause inelastic behavior, with permanent deformations or cracking. As a result, load redistribution may increase forces and stresses in portions of members less affected by deterioration. This behavior should be carefully considered in the repair and serviceability design process. While a structural repair is in progress, concrete may be removed from the structure or reinforcing steel bars may be unintentionally damaged or even cut during concrete removal or, in some instances, intentionally cut to achieve a desired outcome (for instance, when creating openings in slabs or walls). The result of concrete removal is a decrease in effective concrete section, which the licensed design professional (LDP) has to consider for the impact it may have on the member integrity both during and after the repair process. Concrete removal may also affect the development or lateral restraint of reinforcing bars, possibly resulting in a decrease in the effectiveness of the reinforcing steel. Damage to reinforcing bars during concrete removal may affect the bar capacities and may result in redistribution of the load effects into adjacent bars; cutting bars may also result in a redistribution of the load effects into adjacent bars. Thus, the repair process could 7.3—Behavior of repaired systems In some cases, repairs or strengthening of existing Fig. 7.1—Buckled vertical reinforcing bars due to a lack of members or structures are performed by adding new struclateral restraint caused by excessive concrete chipping. @Seismicisolation tural members. ACI 562, 7.3.1, stipulates the minimum @Seismicisolation University of Toronto User. result in further deformations and redistribution of internal forces. Dead load and in-service live loads acting on the structure during repair construction need to be supported by the remaining portions of the members and structure if shoring and bracing is not provided. Excessive concrete removal or damage or deterioration of reinforcing, particularly for compression members such as columns, could result in member distress or collapse. The stress in the remaining concrete could exceed the compressive strength of the concrete, resulting in crushing of the concrete. If the unbraced length of reinforcing bars in compression increases due to excessive concrete removal, one or more bars could buckle and lose capacity (Fig. 7.1). Contractors need to be made aware of the importance of concrete removal and reinforcing ties on the stability of compression members. As such, the LDP should determine a safe limit for concrete removal in terms of maximum depth, maximum surface area, maximum unsupported length of reinforcing bar, or some other measure. The LDP should also specify these limits and the monitoring requirements in the repair documents. Unless measures, such as shoring, are taken before and during the repair process, the deformations and redistributed forces will remain locked into the sound portions of the structure. The LDP should consider the effect of these locked-in internal forces on the safety of the structure during repairs. Internal forces and deformations may be reduced in the sound portions of the members prior to beginning repairs by jacking, shoring, or bracing the members. Initial bracing and shoring may need to be adjusted to accommodate construction dead and live loads that can vary over the course of the repair process. Construction dead and live loads can be later transferred to the repaired members and other portions of the structure. These concepts are further explained in Chapter 9 of this guide. In many repair programs, the sound portions of the existing members and structure will support most if not all the prerepair and repair dead loads and, perhaps, some pre-repair and live loads during repairs. After the repair materials have cured and reached design strength, the repair should act compositely with the remaining portions of the existing structure in supporting subsequent superimposed dead and live loads. Accordingly, ACI 562 Sections 7.2.1 and 7.2.2 require that the LDP develop repair design and construction procedures that consider the stiffness, loading, internal forces, and deformations of both the existing and repaired structure. The repair design needs to consider if the distribution of internal forces and deformations in the members and structure are significantly affected by the repair process and accommodate or alter the repair process accordingly. The effect of the repair process on the stiffness of the structure and member under repair should also be considered. ACI 562, 7.2.2, requires the repair design and construction procedures consider the loadings, the magnitude and redistribution of internal forces, and deformations of the existing and repaired structure. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 48 strength throughout its depth, removing more of the substrate concrete will have no effect on the achievable bond strength and a lower design bond strength may need to be used. 7.4.2 Strength of repair material—The compressive strength of the repair material is typically not a critical factor in determining the interface strength between the concrete substrate and the repair. Repair materials with a higher strength than the substrate concrete may not result in greater interfacial bond strength. The shear strength of a concrete section with a repair or overlay is influenced by the depth of the compression block in the section and the longitudinal tensile reinforcement ratio (ρs). In a study by Kim et al. (2016), the shear strength of composite beams made with combinations of a high-strength concrete material on either the tensile or compressive faces was examined. The study indicated the compressive strength of the overlay material did not affect the interface strength. 7.4.3 Quality of surface preparation of substrate concrete and construction procedures—The preparation of the substrate concrete is an important factor in the success of repair that affects bond strength and should result in a sound, clean surface with some surface profile and minimal microfracturing (bruising) of the substrate. Increased surface roughness of the substrate improves the shear bond strength between the existing substrate and added overlay. The construction method in which a surface is prepared affects the bond between the two layers. Improperly used concrete removal equipment may result in poor quality bond, delamination, or both. Abrasive, shot, and water blasting methods typically do not result in extensive bruising. The level of bruising damage to existing concrete is directly related to the preparation tools and methods used (Warner et al. 1998). The LDP must specify removal limits that may otherwise compromise the integrity and stability of the concrete member, if not set, and to prevent potential damage to embedded reinforcement or other embedded items. In 7.4—Interface bond general, the contractor determines methods and equipBond between the existing concrete substrate and the ment to be used when removing or cutting of concrete is new repair material or overlay, is an essential component required, unless the LDP limits the weight of equipment that of successful, durable repairs. ICRI 210.3R discusses bond the contractor may use during the repair or strengthening strength in repairs, and ICRI 310.2R focuses on various operation. If removal methods produce bruised surfaces or methods used to prepare concrete surfaces to achieve the microcracking of the prepared substrate, then the contractor desired performance of concrete repairs. ACI 318, 16.4, must follow up with secondary removal/surface preparation concentrates on the determination of the nominal shear methods to remove the bruised surface layer. strength at horizontal interfaces in composite members. When considering which surface preparation technique will ACI 562, 7.4.1 requires the evaluation of the interface be best for a job, the LDP must balance the desired outcomes stresses, shear, and tension across bonded interfaces between the owner is seeking with practical concerns, including: the overlay and the existing substrate. a. Avoiding damage to the structure Bond strength is influenced by the strength of the substrate b. Preventing any deterioration of reinforcements concrete, the strength of the repair material, the quality of or the bond between bars and existing concrete the surface preparation of the substrate concrete, construcc. Ensuring the impact of the chosen method tion procedures, characteristics of the repair materials, and will not compromise the concrete’s structural time-dependent factors such as shrinkage of the concrete and integrity variations in repair material properties with time. The advantages of proper surface preparation include: 7.4.1 Strength of substrate concrete—Substrate concrete a. Smoothing out rough spots with low strength may be the limiting factor for bond b. Addressing surface irregularities strength. If the substrate concrete has consistently @Seismicisolation low c. Correcting edge curling @Seismicisolation University of Toronto User. requirements for such systems. Per ACI 562, 1.3.5, new concrete members are to be designed in accordance with ACI 318-19. ACI 562 requires the repaired structure be designed to act compositely, with repaired and new members designed to share loads with the existing members and structure. ACI 562 also requires the force transfer between the new member and the existing structure to be considered in the repair design. The effect of the new member on the existing structure is to be evaluated and should not compromise the performance of the existing structural system. In cases where existing members will be repaired or strengthened, ACI 562, 7.3.2, requires the LDP to account for force transfer between the repair section and the existing structure. Composite action between existing and new concrete can be achieved by bond, mechanical means, or a combination thereof. ACI 562 permits the use of ACI 318-19 for the design of force transfer between new and existing concrete. ACI 318-19 addresses bond between existing and new concrete in Section 17.5 and shear friction in Section 16.4. Furthermore, design for composite action between concrete and structural steel members is addressed in ANSI/ AISC 360-10, Chapter I, and bond between concrete and fiber-reinforced-polymer systems is addressed in ACI 440.2R. ACI 562 requires that repairs designed to resist structural loading (that is, structural repairs) must act compositely with the member or structure being repaired under all limit states. For example, repairs to columns should maintain full composite action under service and factored loadings. When repairs are only needed to improve the durability or aesthetics of a member, full composite behavior should be maintained as a minimum under service loads. In situations where a nonstructural repair could pose a life-safety concern, as might occur with an overhead or façade repair, the repair should consider composite behavior under both service and factored loadings or redundancy through supplemental means of restraint for loads in excess of service loadings. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 7—Design of Structural Repairs49 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES d. Removing unwanted or worn finishes or coatings e. Paving the way for more extensive repairs to your concrete f. Providing a uniform surface to better accept any type of new overlay or coating g. Removing existing coatings, glue removal, or epoxy demo 7.4.4 Bond material—Overlays are bonded to the existing concrete substrate by either cementitious material, modified cementitious material, or resin-based material. Good bonding is achieved by roughening the surface and removing existing deteriorated, damaged, or contaminated concrete. The selection and installation of the repair material can be designed to not be a limiting factor for the bond strength. Several test methods are available in the industry to measure the bond strength and are presented in Table 7.4.4. Each method has its advantages and shortcomings that should be considered when measuring the bond strength (ACI 546.3R). The advantage of pulloff tests is that they can be performed in-place, while the other tests require removal of samples and testing in a laboratory. If the composite section is subjected to tension, then reinforcement is added crossing the interface and properly doweled in the concrete substrate and overlay. 7.4.5 Time-dependent factors—The long-term performance of the bonding procedure should be evaluated. The effects of the load type, duration, and the in-service (a) Pulloff test (b) Splitting test Fig. 7.4.4a—Tension test. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 50 University of Toronto User. Fig. 7.4.4c—Direct shear test. Fig. 7.4.4b—Slant shear test. Table 7.4.4—Required test methods to measure bond strength Measured bond in Tension Shear and compression Shear Test type Pulloff Splitting Slant shear Direct shear Test method ASTM ASTM C1583/C1583M ASTM C496/C496M ASTM C882/C882M ASTM D6916-06c (Reapproved 2011) @Seismicisolation @Seismicisolation Figure 7.4.4a(a) 7.4.4a(b) 7.4.4b 7.4.4c environment on the bond should be considered. The existing concrete substrate has usually undergone most of its shrinkage, while the added concrete in the repair has not yet gone through significant shrinkage. Therefore, differential shrinkage, an important time-dependent factor, occurs between the two layers resulting in added stress at the interface. Differential shrinkage strain may be less significant in cases where the overlay is lightweight concrete as the aggregate may supply moisture for internal curing resulting in reduced shrinkage. 7.4.6 Shear stress calculation—At a minimum, ACI 562, 7.4.1.1, requires that the calculated horizontal shear strength to be at least equal to the required bond strength or tensile strength of the concrete substrate, such that: vu ≤ fvni (7.4.1.1) where vu is the calculated bond demand shear stress based upon mechanics, Table 7.4.4; φ is the reduction factor obtained from ACI 562, 5.3.2; and vni is the measured bond stress from a valid test method. The overlay should be tested for proper bonding as required by ACI 562, 7.4.2 through 7.4.4, and as presented in Table 7.4.5. A calculated shear stress of less than 30 psi (0.2 MPa), from ACI 562, Section 7.4.2, requires qualitative bondintegrity testing only. Some of the nondestructive test methods are hammer sounding in accordance with ASTM D4580/ D4580M, ground penetrating radar, or impact-echo described in ACI 228.2R or ICRI 210.4, and impulse response in accordance with ASTM C1740. ICRI 210.3 suggests a minimum measured tensile bond strength of 100 psi (0.7 MPa) as an acceptable limit for less-critical applications, whereas a measured tensile bond strength in the range of 175 to 215 psi (1.2 to 1.5 MPa) is suggested for structural repair in Volume 10 of The European Standard 1504 series (EN 1504-10). A calculated shear stress between 30 to 60 psi (0.2 to 0.4 MPa) in ACI 562, 7.4.3, does not require interface reinforcement; quantitative testing, however, is required. A shear stress of 60 psi (0.4 MPa) is calculated from the nominal shear stress; 80 psi (0.55 MPa), listed in ACI 318-19, Tables 16.4.4.2(c) and (d), multiplied by the reduction factor ϕ = 0.75 of ACI 562, 5.3.2; and 30 psi (0.2 MPa) is based on half of the 80 psi (0.55 MPa) multiplied by the reduction factor ϕ = 0.75. Any test presented in Table 7.4.4 can be used to determine the adequacy of the bond between the overlay and substrate. While direct shear test, splitting tension test, and slant test are performed in a laboratory, the direct tension pull-off test can be performed on site, which helps the LDP make informed design decisions. The relationship between the different test methods is not directly apparent. If the calculated shear stress exceeds 60 psi (0.4 MPa) from ACI 562, 7.4.4, but less than 375 psi (2.6 MPa) from ACI 562, R7.4.6, the LDP should provide minimum interface reinforcement between the substrate and overlay. Quantitative testing as discussed in ACI 562, 7.4.3, should be specified. Interface reinforcement is calculated per ACI 318-19, 16.4.4.1, to resist the total shear strength when the calculated shear stress exceeds 375 psi (2.6 MPa) and quantitative testing is not required for this condition. The LDP should specify in the construction documents the required testing for the interface reinforcement. Tension testing in accordance with ACI 355.2, ACI 355.4, and ICRI 210.3 can be performed using the number of tests similar to the pulloff tests from ACI 562, 7.4.7. Table 7.4.5—Testing requirements based upon interface bond stress demand (vu) ACI 562 7.4.2 7.4.5 Testing requirements Bond-integrity testing Quantitative bond strength testing Enlargement systems were used to strengthen the column footers in the parking structure @Seismicisolation @Seismicisolation University of Toronto User. vu Less or equal to 30 psi (0.2 MPa) Greater than 30 psi (0.42 MPa) Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 7—Design of Structural Repairs51 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Example 7.1—Determining bond strength The LDP checked the horizontal shear between the existing precast concrete beams and the new cast-in-place elevated slab. ACI 562, R7.4.1, refers the LDP to ACI 318-19, 16.4, for designing the interface for horizontal shear. ACI 318 has two procedures for checking the factored horizontal shear strength Vuh. In this example, both methods are presented. Background A parking structure floor was constructed of 12 x 22 in. (300 x 560 mm) precast concrete beams spanning 28 ft (8.5 m) and spaced at 10 ft (3 m) on center. The beams support precast concrete simply supported 5 in. (125 mm) thick slab panels. The structure is subjected to a live load of 40 lb/ft2 (195 kg/m2) per ASCE/SEI 7 (parking structure). The beams and slab panels were deteriorated due to corrosion, delamination, and spalling. The beams were repaired, but the licensed design professional (LDP) decided to replace the precast slab panels with 5 in. (125 mm) thick cast-in-place concrete slab. Solution: The beams are simply supported at both ends. Vu@d = 20.6 kip, where d = 22 in. (beam) + 5 in. (slab) – 2.5 in. (cover + db/2) = 24.5 in. Vu@d = 92 kN, where d = 560 mm (beam) + 125 mm (slab) – 65 mm (cover + db/2) = 620 mm ACI 318-19, 16.4.3.1, requires that fVnh ≥ Vu at all sections, where the strength reduction factor φ = 0.75, Vnh is the horizontal shear strength calculated in accordance with ACI 318-19, 16.4.4, and Vu is the factored shear force. From 12 in. × 22 in. 3 ACI 318-19, 16.4.4.2, assuming that the top surface w= ( 0 . 1 5 kip/ft ) = 0 . 27 5 kip/ft 144 in.2 /ft 2 of each precast concrete beam was intentionally roughened: (300 mm × 560 mm) w= (2400 kg/m 3 ) = 403 kg/m = (4 kN/m) 2 (1000 mm/m) vu = (20.6 kip)(1000 lb/kip)/[(12 in.)(24.5 in.)] = 3 70 psi > φ80 psi = (0.75)(80 psi) = 60 psi g/m ) = 403 kg/m = (4 kN/m) Calculations: It is assumed that the beam has adequate reinforcement to support the weight of wet concrete slab and construction load during construction and the total dead and live load during service. Beam self-weight: Slab self-weight: 5 in. w= (10 ft )(0.15 kip/ft 3 ) = 0.625 kip/ft 12 in./ft 125 mm (3 m)(2400 kg/m3 ) = 900 kg/m (8.9 kN/m) 1000 mm/m (3 m)(2400 kg/m3 ) = 900 kg/m (8.9 kN/m) Live load: w = (40 lb/ft2)(10 ft) = 0.4 kip/ft φVnh = φ(260 + 0.6(Av/bvs)fyt)lbvd = (0.75)[260 + 0.6(0.11 in.2)(60,000 psi)/(12 in.)(20 in.)](1.0) (12 in.)(24.5 in.) = φVnh = 61 kip > Vu@d = 20.6 kip w = (195 kg/m )(3 m) = 585 kg/m = 5.8 kN/m 2 U = 1.2(0.275 kip/ft + 0.625 kip/ft) + 1.6(0.4 kip/ft) = 1.72 kip/ft U = 1.2(4 kN/m + 8.9 kN/m) + 1.6(0.58 kN/m) = 24.8 kN/m φVnh = φ(1.8 + 0.6(Avfyt/bws))lbvd = (0.75)[1.8 + 0.6 (71 mm2)(420 MPa)/(300 mm)(500 mm)](1.0) (300 mm)(620 mm) = 268 kN > 92 kN Therefore, maximum tie spacing is adequate to transfer the horizontal shear between the @Seismicisolation @Seismicisolation University of Toronto User. w= vu = (92,000 N)/[(300 mm)(620 mm)] = 0.495 MPa > φ0.55 MPa = (0.75)(0.55 psi) = 0.4 MPa Therefore, according to ACI 562, 7.4.4, anchors between precast beams and cast-in-place slab are required. Assume No. 3 dowels are anchored into the precast beams at 20 in. (500 mm) on center and hooked into the slab to provide the horizontal shear transfer between the precast beam and cast-in-place slab. Use Eq. 16.4.4.2(a) from ACI 318-19. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 52 precast concrete beam and cast-in-place slab. The maximum tie spacing is calculated from ACI 318-19, 16.4.7.2, which is the lesser of four times the least dimension of the supported element and 24 in. (600 mm) s = (4)(5 in.) = 20 in. < 24 in., (s = (4)(125 mm) = 500 mm < 600 mm), therefore, use s = 20 in. (500 mm) in Eq. 16.4.4.2(a). Second method ACI 318-19, 16.4.5.1, requires the LDP to calculate the factored horizontal shear force from the change in flexural compressive or tensile force (T) in any segment of the composite concrete member such that Eq. (16.4.5.1) of ACI 318-19 is satisfied at all locations along the contact surface. vuh = vuh = (92 kip − 68.8 kip)(1000 lb/kip) = 23 psi (12 in.)(7 ft)(12 in./ft) < 30 psi vuh = (401 kN − 301 kN) = 0.157 MPa (300 mm)(2125 mm) < 0.2 MPa Therefore, per Section 7.4.2 of ACI 562, interface reinforcement is not required. Between quarter span and support: vuh = Tu@ midspan − Tu@1/ 4 span (68.8 kip − 0 kip)(1000 lb/kip) = 68 psi (12 in.)(7 ft)(12 in./ft) > 60 psi bv ls The moment diagram of a simply supported beam is parabolic that results in relatively large moment changes (∆M) near the supports compared to the mid-third of the beam moment diagram. Therefore, the LDP could divide the half-span of the beam into three or more sections; at 1/3 and 1/8, and calculate the factored horizontal shear stress over those sections. Due to the large moment change close to the supports, the factored horizontal shear stress is expected to be greater close to the supports compared to the calculated factored horizontal in the midthird of the span. For this example, however, it was determined that quarter span was adequate to illustrate the calculation procedure. Moment at midspan: vuh = (301 kN − 0 kN) = 0.472 MPa (300 mm)(2125 mm) > 0.4 MPa Therefore, per ACI 562, 7.4.4, interface reinforcement is required and the minimum reinforcement is provided. No. 3 at 20 in. on center (No. 10 at 500 mm on center) is adequate to resist the horizontal shear force as shown previously. Conclusion: The LDP provided No. 3 (No. 10) dowels over the full length of the precast concrete beam at maximum spacing of 20 in. (500 mm) on center. University of Toronto User. Mu = (1.72 kip/ft)(28 ft)2/8 = 168.6 ft-kip and Tu1 = Mu/0.9d = 92 kip Mu = (24.8 kN/m)(8.5 m)2/8 = 224 kN.m and Tu1 = Mu/0.9d = 401 kN Moment at quarter span: Mu = (1.72 kip/ft)[(14 ft) (7 ft) – (7 ft)2/2] = 126.4 ft-kip and Tu1 = Mu/0.9d = 68.8 kip Mu = (24.8 kN/m)[(4.25 m)(2.125 m) – (2.125 m)2/2] = 168 kN.m and Tu1 = Mu/0.9d = 301 kN Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 7—Design of Structural Repairs53 Fig. 7.4—New cast-in-place concrete slab to existing precast concrete beam connection. @Seismicisolation @Seismicisolation GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Example 7.2—Determining bond strength of overlay to an elevated slab Background A nine-story parking structure located in the Midwest of the United States was constructed of 8 in. thick lightweight concrete flat slabs in 1971. The design concrete compressive strength was 3750 psi and the reinforcing steel was ASTM A615 Grade 60. The top surfaces of the decks were sounded and visually inspected and were found to be badly deteriorated. The LDP estimated that the extent of deterioration on top side ranged between 30 to 70 percent. Delamination and cracking were also observed on the bottom surfaces of the decks, but less extensive than that on the top surfaces. Samples were taken from areas that exhibited deterioration and tested for chloride content. Cores were extracted from several areas of the elevated slab and tested for strength and chloride content. Tests revealed that the concrete compressive strength of the slab matched the design concrete compressive strength and that chloride was present over the full depth of the slab with excessive concentration levels near the top. Insufficient cover over the reinforcement at various locations was detected throughout the garage. Fig. 7.2a—Pulloff test. @Seismicisolation @Seismicisolation University of Toronto User. Procedure: The LDP determined that the repair would consist of the removal of 3-1/2 in. (90 mm) of top of the deck slabs and replace with a bonded lightweight concrete overlay. There are several methods for concrete removal; blasting, cutting, impact milling, pre-splitting, and abrading each having its advantage and shortcomings. Irrespective of the method used it should be effective, safe and economical, and should produce minimum damage to the concrete surface left in place (free of micro cracks). The contractor and the LDP evaluated the different methods and it was decided to use hydrodemolition for this job for the following reasons: a. It results in a rough, irregular surface profile that provides an excellent bond for all types of repair materials creating a monolithic repair b. Minimization or elimination of surface microcracking caused by other methods c. Exposed aggregates are not fractures or damaged, thus interlocking wall with the overlay d. Selectively removing lower strength and deteriorated concrete (delamination) e. Minimizing vibration to surrounding structure f. Preserves and cleans reinforcing bars for reuse and eliminates the need for sandblasting Robotic equipment was used for this job to ensure uniform removal of concrete. But prior to the start of the production work, a mockup was installed that was extensively tested to ensure the success of the recommended procedure. The testing of the mockup slab included: a. Tensile bond tests by pulloff of the overlay concrete to the substrate (Fig. 7.2a) b. Cores comparing the lightweight aggregate of the substrate and the repair concrete A total of six tests were performed and the bond strength was measured (Table 7.2a). The test results exceeded 100 psi (0.7 MPa) (ACI 562 Section R7.4.2 and ICRI 210.3) and the difference between maximum and minimum test results was 47 psi (0.32 MPa), or 30 percent. Once the LDP was satisfied with the test results and the process was confirmed, the contractor proceeded with the implementation of the repair work to the full slab starting with removal of the slab (Fig. 7.2b). The LDP requested extensive testing of the repair work throughout the duration of the project. The testing for the overlay concrete was similar to the testing for new cast-in-place concrete. Pulloff testing in accordance with ASTM C1583 was performed to confirm the adequacy of the bond of the overlay to the substrate concrete. The test results of the pulloff test are presented in Table 7.2b. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 54 The test results were scattered and varied between 32 psi (0.22 MPa) and 190 psi (1.3 MPa) or a difference of 158 psi (1.09 MPa) or 83 percent (Table 7.2b). This is a large scatter and unacceptable. The LDP ordered petrographic testing on some of the samples. The test results revealed that the contractor did not remove all debris and loose material from the substrate surface area, thus creating a weak bond between the substrate and overlay (Fig. 7.2c). Table 7.2a—Test results of the pulloff test of the mockup area Test parameters Test No. A1 A2 A3 B1 B2 B3 Test location Level P8 Floor slab Mock-up area A Level P8 Floor slab Mock-up area A Level P8 Floor slab Mock-up area A Level P8 Floor slab Mock-up area B Level P8 Floor slab Mock-up area B Level P8 Floor slab Mock-up area B Bond force, lb (kN) Bond Strength, psi (MPa) Separation plane 900 (4.0) 126 (0.87) Substrate concrete 790 (3.5) 110 (0.76) Surface of the substrate concrete 790 (3.5) 110 (0.76) Surface of the substrate concrete 1125 (5.0) 157 (1.08) Substrate concrete 1000 (4.5) 142 (0.98) Surface of the substrate concrete 1000 (4.5) 142 (0.98) 50 percent substrate concrete 50 percent surface of the substrate concrete Table 7.2b—Test results of the pulloff test of the partial completed work Test No. BT-1 BT-2 BT-3 BT-5 Bond force, lb (kN) 6-29-06 560 (2.5) 79 (0.54) Substrate concrete 6-29-06 670 (3.0) 96 (0.66) Substrate concrete 7-08-06 (225) 1.0 32 (0.22) 75 percent interface between substrate concrete and overlay, 25 percent within substrate concrete 7-14-06 1350 (6.0) 190 (1.31) Test epoxy media 7-14-06 1350 (6.0) 190 (1.31) Substrate concrete Fig. 7.2b—Removal of 3-1/2 in. of slab by hydrodemolition. Fig. 7.2c—Petrographic of new overlay to existing slab. @Seismicisolation @Seismicisolation University of Toronto User. BT-4 Test area and location Level P9 on Column Line 2 between Column Lines G and H Level P9 on Column Line 2 between Column Lines K and L Level P9 West of Column Line 2 between Column Lines N and P Level P9 between Column Lines 8 and 9 and J and K Level P9 between Column Lines 8 and 9 and F and G Test parameters Bond strength, psi (MPa) Separation place Date of placement Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 7—Design of Structural Repairs55 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Example 7.2—continued Corrective actions were implemented to improve the bond strength: a. Contractor improved methods to the clean surface of the substrate and to remove all residue resulting from hydrodemolition b. Inspectors more closely examined the substrate surface for suitability to receive bonded overlay The pulloff tests after the corrective measures were more consistent and were equal to or exceeded 100 psi (0.7 MPa), with the exception of one test result as shown in Table 7.2c. The LDP ordered another set of petrographic testing on some of the samples. The test results showed that the bond between the substrate and new overlay is acceptable (Fig. 7.2d). Conclusion: The construction phase of the work should be performed with high-quality workmanship and materials that satisfy the intent of the construction documents to warrant a successful project. Table 7.2c—Test results of pulloff tests after remedial actions Test No. BT-16 BT-17 BT-17A BT-17B BT-18 BT-19 Test area and location Level P9, NWC Level P9, SWC Level P9, SWC, 9’ N of Core BT-17 Level P9D, West, 3’ N of Core BT-17 Level P8D, West Level P8D, West, column 2 between N&P Date of concrete placement Not provided Not provided Bond force, lb (kN) 1240 (5.5) 560 (2.5) Test parameters Bond strength, psi (MPa) 174 (1.2) 79 (0.54) Separation place Interface zone Substrate concrete Not provided 790 (3.5) 100 (0.7) Interface zone Not provided 790 (3.5) 100 (0.7) Interface zone Not provided 1450 (6.5) 206 (1.42) Interface zone Not provided 1350 (6.0) 190 (1.31) Interface zone Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 56 University of Toronto User. Fig. 7.2d—Proper bond between substrate and overlay. @Seismicisolation @Seismicisolation University of Toronto User. 7.5—Materials 7.6—Design and detailing considerations ACI 562, 7.5.1, requires the LDP to evaluate the adequacy 7.6.1 Existing materials, reinforcement detailing, deteof the proposed repair materials. The repair materials are rioration, and repair considerations—ACI 562, 7.6.1, selected based on short-term and long-term compatibility requires that the repair design consider the condition of with the existing structure and durability in the service the existing concrete, including the actual compressive environment. The existing materials in the structure need to strength and variations in that strength; the current condiconform to the design-basis code (ACI 562, 7.5.2) and repair tion and types and extent of deterioration of the concrete materials need to conform to ACI 318-19 or be permitted (ACI 562, 7.6.2); and the sizes, locations, detailing, and by ACI 562, 7.5.3. Alternate repair materials should be current condition of the existing reinforcement (ACI 562, approved by the LDP and the building official (ACI 562, 1.4 7.6.3). In a reinforced concrete structure, these items are and 7.5.4). difficult to determine due to the size and complexity of A key part of any repair program is the selection of repair the structure and conditions concealed below the concrete materials. The remaining existing concrete usually has been surfaces. A preliminary assessment (ACI 562, 1.7) consisting in service for many years, so that initial drying shrinkage and of visual and selective sounding surveys, which are relacreep effects would have occurred. The existing concrete will tively easy and quick to conduct, are used to locate areas of be required to respond to changes in the service environment, possible concrete and steel deterioration along with design such as variations in loadings and temperatures. Therefore, it and construction deficiencies. Conditions that are identified is important that the repair material be compatible with the in the preliminary assessment are investigated in more depth existing concrete. Compatibility does not necessarily mean in structural assessment, evaluation, and analysis (ACI 562 having similar properties, but having properties that result in Chapter 6). It should be recognized that the preliminary successful repair performance. assessment and the structural assessment, evaluation, and ACI 562 requires that physical properties of the repair analysis may not identify all deterioration that reduces the material, such as drying shrinkage in cementitious materials, capacity or design and construction deficiencies. The goal is be considered when specifying repair materials. The requireto identify all unsafe and structurally significant conditions. ments for each repair should be evaluated when selecting mateThe repair design needs to address structurally significant rials. For instance, if shrinkage cracking is not desirable for a deterioration such as loss of sound concrete cross section or given repair, restraint of drying shrinkage could be addressed concrete strength, and loss of reinforcing steel cross section by developing sufficient tensile strength in the repair material or development. Existing reinforcement development length to avoid cracking or sealing the shrinkage cracks that develop may be inadequate due to corrosion, mechanical damage, with a crack treatment or a waterproofing coating. Alternately, insufficient or loss of concrete cover, delaminated concrete, a repair material that does not experience significant initial or other conditions. The current design building code, ACI shrinkage, such as a polymer concrete, or the addition of 318-19, has new development equations that may require shrinkage-reducing admixtures could be considered. longer development lengths than earlier development equaTo perform satisfactorily, a repair material needs to be tions present in earlier building code versions. ACI 562, compatible with the long-term concrete behavior and antici4.1.6, states that the LDP may not comply with the current pated environmental conditions. If the repair material is building code if two conditions are met: designed to share load with the existing concrete, it may be a. Damage or deterioration to existing reinforcedesirable that the repair material have similar or less stiffment is addressed ness and reduced creep properties. It is also desirable that the b. The repaired work area of the structure has repair material have a similar coefficient of thermal expancapacity equal to or greater than demand per sion so that the existing concrete and the repair material will Section 5.2.2 of ACI 562 using the original experience similar strains due to temperature variations in building code requirements. the service environment. If the existing concrete and the The repair design need to also address structurally signifirepair material are expected to behave significantly different cant deficiencies in the design and construction, such as in the service environment, the differential strains need to be inadequate concrete thickness or misplaced reinforcing bars. accounted for in some manner. Methods that could be used ACI 562, 7.6.6, requires that the repair geometry consider include using a lower modulus of elasticity in the repair matethe potential for stress concentrations within the repair and rial, increasing bond and tensile strength in the repair mateexisting structure. Where possible, reentrant corners and rial, or periodic crack sealing maintenance to address cracks other geometric irregularities should be avoided in the repair that form due to differential strains. It should be noted that and in the existing member to reduce stress concentrations the existing concrete properties generally cannot be changed and the potential for cracking in either the repair or the and may limit the ability to address differential strains and existing member. the projected service life of the repaired members. 7.6.2 Prestressed members and structures—The repair A detailed list of repair materials for various concrete of members subject to prestressing forces presents unique repairs, such as replacements, crack treatments, and surface challenges. The prestressing force is designed to counter the treatments, as well as discussions of test procedures, typical effects of dead and live load strains to effectively impart a test values, and the selection of repair materials is included general state of compression throughout the member cross in ACI 546.3R. @Seismicisolation section. If part of the concrete section becomes ineffective due @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 7—Design of Structural Repairs57 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES be rendered fully ineffective in the case of a cut or fracture. Some structures are designed with excess prestress and can tolerate the loss of one or more unbonded tendons with no significant reduction in the structural capacity; however, in many other structures, this is not the case. Temporary support such as shoring or reduced live load of the affected area(s) should be considered until the adequate structural capacity is confirmed or restored. End anchorages of many of the unbonded post-tensioning systems used in the 1960s, 1970s, and 1980s are particularly susceptible to concrete and tendon deterioration due to water infiltration. Modern, fully encapsulated, unbonded post-tensioning systems have significantly less risk of water penetration or corrosion. Usually, repair of unbonded tendons requires detensioning as the first step in the repair process. Then the unbonded tendon can be spliced, strand or anchorages removed and replaced as needed, and the tendon restressed. Accordingly, ACI 562, 7.6.4, requires that the effects of prestressing be considered in the repair design (ACI 562, 7.6.4.1), including prestressing force release and construction sequence (ACI 562, 7.6.4.2), and stresses in remaining concrete (ACI 562, 7.6.4.3). ACI 562, R7.6.4.1, references various ACI, PTI, and ICRI documents for more information on this subject. 7.6.3 Post-installed anchors and dowels—ACI 562, 7.6.5, specifies minimum requirements for the design of post-installed anchors, which is to be in accordance with ACI 318-19. Extensive testing has been performed on the behavior and capacity of post-installed anchors and dowels, which is reflected in Chapter 17 of ACI 318-19. Factors affecting the selection of the anchor type include the expected concrete cracking condition (cracked or uncracked), the duration of design loads, the inclination of the anchor or dowel installation (downwardly inclined, horizontal, or upwardly inclined), the concrete strength, the concrete moisture content, anchor hole size, and the acceptable failure mode. Post-installed anchors and dowels should be prequalified by laboratory testing in accordance with ACI 355.2 or ACI 355.4. Installation procedures (including cleaning the drilled holes, the moisture condition of the concrete for adhesive anchors, torque magnitude for mechanical anchors, and curing for adhesive anchors) and testing and inspection procedures are critical for a satisfactory installation. 7.7—Repair using supplemental post-tensioning Supplemental post-tensioning consists of tendons or bars that are positioned externally along the concrete members. The external reinforcement may be straight or draped, and may be positioned inside hollow portions of members such as hollow-core planks and box girders. Supplemental post-tensioning is normally used to increase the member capacity or to resolve a deficiency by introducing moments and shears to partially offset the effects of gravity loads. Supplemental post-tensioning can also be used to decrease member deflection. EssenPlacement of bonded overlay over the parking structure tially, the supplemental post-tensioning is anchored created a strengthened deck for the public transportation area @Seismicisolation near the ends of the member and held in position along @Seismicisolation University of Toronto User. to deterioration or is removed during the repair, the state of strain across the member cross section will need to be evaluated considering the remaining, sound concrete section. The repair design needs to confirm that the remaining concrete section is not overstressed. The potential for buckling and instability should also be considered by the LDP. The reduction in sound concrete cross section could also result in a reduction in prestress force due to shortening of the concrete member; this loss of prestress force could affect the member capacity. These later effects are particularly critical in prestressed joists and beams that have larger prestress forces than slabs. Repair of deteriorated reinforcement in prestressed and post-tensioned structures also has unique considerations. In structures with bonded reinforcement, forces are transferred to the concrete through a combination of bearing at the anchorages and bond over the entire length of the tendon. Bonded reinforcement will become ineffective at locations subject to deterioration of concrete or at locations where force transfer is disrupted by debondment, reinforcement fracture, or intentional modification as part of the repair. Outside of these areas, the reinforcement may continue to provide prestress force. The redistribution of internal forces in these scenarios will need to be carefully considered in the repair design. Replacement of bonded tendons is rarely possible. External post-tensioning is commonly used to restore the reinforcement forces lost as a result of damaged tendons, as described in ACI 562, 7.7. There are limited options available for the repair of bonded tendons; for example, repair of voids in the grout in a bonded tendon can be achieved by vacuum or pressure grouting. With these methods, specific grouting procedures and quality assurance measures must be specified to assure complete filling of the duct. In structures with unbonded tendons, the prestressing force is transferred to the concrete at the end anchorages and at locations where the tendons are deviated from a straight profile. If an unbonded tendon loses some or all of its prestress, fractures, or is cut, the entire length of the tendon experiences a proportional loss of prestress or will Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 58 Strengthening with external post-tensioning A 60 ft (18.3 m) long post-tensioned concrete beam in a parking structure needs to be strengthened, possibly because one or more tendons have fractured, the beam has excessive deflection, or design loads are increasing. Repair options include enlarging the beam section, externally bonded fiberreinforced-polymer reinforcement, supplemental steel elements, and external post-tensioning. Of these options, only external post-tensioning is an active system that introduces external forces into the beam, unless an attempt is made to unload the beam by jacking before one of the other repair options is installed. After considering serviceability, strength, durability, appearance, fire rating, constructability, aesthetics, disruption to garage activities, and cost, the external post-tensioning option is selected. In the schematic, the external post-tensioning introduces upward forces at the beam third points. This reaction serves to partially offset the effects of the downward dead and live loads. The external post-tensioning forces decrease the internal tension and compression forces due to flexure and the shear forces. The external post-tensioning forces and the remaining original post-tensioning forces are combined and compared to the limits in the design-basis code (ACI 562, 7.7.2.1). The upward, reverse effect of the external post-tensioning also serves to decrease the beam deflection. To provide a minimum capacity should the external post-tensioning system fail, the strength of the unrepaired beam is checked for the load combination in ACI 562, 5.5.1. The horizontal component of the external post-tensioning at the end anchorages introduces lateral loads and resulting moments into the columns. The column capacities and stresses are checked for these added moments (ACI 562, Sections 7.7.2 and 7.7.3). The end anchorages and intermediate saddles are designed to transfer the post-tensioning force into the beam. The capacity of the concrete members is evaluated with respect to the effects of the force transferred at those locations (ACI 562, 7.7.2.2). Post-tensioning forces, including some transfer of post-tensioning forces into the adjacent slab, are estimated. The amount of effective prestress in the beam is estimated by the upward deflection of the beam under prestress (ACI 562, 7.7.4). The tendon placement and anchorages are fully detailed on the repair drawings, and the incremental stressing sequence and monitoring of prestress are specified (ACI 562, 7.7.5). The external post-tensioning system is evaluated for serviceability concerns related to fire and vehicular protection. Protection can be provided through concrete encapsulation or spray-on fireproofing to provide the required fireproofing (ACI 562, 7.9). Concrete encapsulation or supplemental steel framing can be provided for vehicular protection. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 7—Design of Structural Repairs59 University of Toronto User. the length of the member by intermediate saddles force into the structure without causing damage in the or supports. anchorage zones. The restraint imposed by adjacent ACI 562, Section 7.7, specifies the minimum requireelements, post-tensioning losses, and the sequencing of ments for repairs using supplemental post-tensioning. the post-tensioning repair should be considered. The effects of the supplemental post-tensioning on the internal stresses in the member being repaired and on the 7.8—Repair using fiber-reinforced polymer (FRP) adjacent structural members should be considered, and composites the combined stress levels should not exceed prescribed ACI 562, 7.8.1, permits the use of fiber-reinforced limits in the design-basis code. The end anchorage zones polymer (FRP) composites in conformance with ACI should be designed and detailed to transfer the@Seismicisolation prestress 440.6 and 440.8. ACI 440.2R discusses the design and @Seismicisolation GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES detailing of externally bonded FRP systems. ACI 562, 7.8.2, requires that the unrepaired strength of members with externally applied FRP meet the minimum requirements of ACI 562, 5.5. The minimum strength requirement ensures sufficient strength if the FRP is damaged or otherwise compromised. Unless protection is provided, based on the requirements of ACI 562, 5.5, the use of externally bonded FRP to resist design dead and live loads of a structure will be limited. 7.9—Performance under fire and elevated temperatures ACI 562, 7.9, specifies the minimum requirements for the performance of repairs under fire and elevated temperatures. The performance of the repairs and the repaired structure should comply with the fire safety requirements of the applicable building code. The properties of the repair materials, particularly adhesives, at elevated temperatures must also be considered. ACI 440.2R reports that the physical and mechanical properties of the resin components of FRP systems are influenced by temperature and can degrade at temperatures close to and above their glass-transition temperature, Tg. Therefore, FRP-strengthened concrete beams require protection to maintain their strength, to prevent combustion of the material, and to preserve their bond with the substrate. An acceptable service temperature for the element of the structure should not exceed Tg – 27°F when FRP is used for strengthening. This value accounts for typical variation in test data for dry environment exposures. Adhesive-bonded FRP reinforcement should not be used if the maximum service temperature for the element of the structure exceeds Tg – 27°F. A service temperature exceeding this limit temperature should be addressed using an adhesive system with a higher Tg value, using heat protection or insulation systems, or using alternate repair systems. Similar service temperature considerations apply to adhesivebonded steel reinforcement. Fire rating of the repaired structure and supplemental fire protection are permitted, but no supplemental fire protection may be necessary if the repair satisfies the load combination in ACI 562, 5.5. Project 8 of this guide addresses two fire rating/protection scenarios. In Scenario 1, the LDP specified spray-applied fire-resistant material to protect the applied FRP. In Scenario 2, fire protection to existing reinforcement with low cover was accomplished by installing a 1 in. (25.4 mm) concrete jacket to provide additional cover to the existing reinforcement. Fire resistance or rating of a repaired system or assembly can be determined through full-scale testing in accordance with ASTM E119. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 60 University of Toronto User. @Seismicisolation @Seismicisolation Protective deck coating installed on a floor slab of a parking deck 8.1—General The desired design service life of the repairs and the repaired structure is established by the licensed design professional (LDP) in consultation with the owner. As such, the overall solution should consider the desired service life for the repairs and the expected remaining service life for the structural elements to remain. The overall solution should also consider maintenance efforts over the design service life for both the repair and remaining structural elements. The durability of the repair solution requires compatibility between the materials of the repair and the existing structure, as well as consideration of the anticipated exposure conditions over its life span. Service life is discussed in ACI 365.1R. @Seismicisolation @Seismicisolation 61 University of Toronto User. Overview The durability of repairs to existing concrete structures is dependent upon the properties and characteristics of the existing concrete and the repair materials, as well as their service environment. Properties and characteristics such as cover of reinforcing steel, cracks, spalls, protective treatments and coatings, permeability, corrosion potential, and air-void parameters (for concrete subject to cycles of freezing and thawing) are typically considered in a durability assessment. Moisture, freezing-and-thawing cycles, chlorides, chemical attack, and other factors are typically considered when performing an assessment of the effects of service environment on durability. Chapter 8 of ACI 562 sets forth the durability requirements and considerations for the repair materials and the repaired structure. The project examples that accompany this guide illustrate the application of durability considerations in the development of a repair program. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 8—Durability GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES 8.2—Cover Concrete cover is one of the primary methods of protecting reinforcing steel from corrosion and fire and ensuring proper development of reinforcement. ACI 318, which is frequently used for concrete design as the design basis code, specifies minimum design cover requirements for different types of construction and environmental exposures. Other ACI guidelines provide recommendations for concrete cover for specific applications and exposure conditions, such as ACI 362.1R for parking garages. As part of a condition assessment, the existing concrete cover should be determined and compared to the cover requirements in the design basis code. ACI 562 addresses inadequate concrete cover in repair areas and elsewhere in the structure by increasing the concrete cover or employing alternative means (termed “equivalent cover” in ACI 562) for corrosion (ACI 562, 8.2.2) and fire protection (ACI 562, 7.9). Concrete overlays and concrete-encased jackets can be used to address inadequate concrete cover. Where such solutions are impractical or not cost effective in existing concrete structures, alternate means of addressing member and structure durability due to shallow concrete cover issues should be considered. Alternative means of corrosion protection include the application of waterproof membranes on the surface of the concrete, corrosion-inhibiting coatings on reinforcing bars, use of concrete with lower permeability, or corrosion mitigation technologies such as cathodic protection systems or galvanic protection. ACI 216.1 contains design and analytical procedures for determining the fire resistance of concrete, including minimum concrete cover for slabs and beams to achieve various fire resistance ratings. In cases where the minimum cover cannot be achieved, alternative materials such as intumescent coatings or other finish materials may be used to achieve the required fire rating (ACI 562, 7.9.5). Alternate methods of fire protection should be approved by the building official as required in ACI 562, 1.4.2. Section 8.2.2 of ACI 562 requires that the influence of the existing concrete cover on the anchorage and development requirements for reinforcement be assessed regardless of the durability method selected. ACI 562 requires anchorage and development requirements be in accordance with the design basis code. Project Example 1 includes considerations for cover in a typical parking garage slab repair. Project Example 2 illustrates a scenario where cover is built out during repair. Project Example 3 illustrates a scenario where coatings are used as an alternate means of corrosion protection. 8.3—Cracks and deterioration of reinforcement and metallic embedments Concrete cracking can be caused by load effects and volume changes are common. Cracking may also be indicative of structural deficiencies or ongoing deterioration mechanisms. Cracks may be active or inactive. Active cracks are subject to movement whereas inactive cracks are not. It is important to determine the cause and nature of the cracking during the condition assessment. ACI 224.1R discusses the causes, assessment, and repair of cracks in concrete structures. ACI 503.7 provides a specification for repair of cracks through polymer injection. The comparative cracking potential of different cementitious materials can be assessed using ASTM C1581/C1581M. The influence of cracks on the durability of the repair and existing concrete structure should be considered by the LDP. Cracks allow moisture and chemicals to enter into the concrete and access the reinforcement. Exposure to moisture and chemicals can cause deterioration of the reinforcement, the concrete, or both. Many repair programs include treatment of existing cracks and provisions for treating new cracks that may form after the repairs have been installed. The LDP should select an @Seismicisolation @Seismicisolation University of Toronto User. Depending on the owner’s planned use of the structure, the design service life may range from short-term to longterm. To achieve the desired design service life, the repair program should address the causes of the distress and deterioration. Deterioration will likely return if its causes are not accurately determined and addressed. Future routine maintenance is essential to achieving the targeted design service life, in addition to the assessment, repair program, and materials. ACI 562, 8.1.2, requires the repair program development consider the compatibility of the repair materials, the interaction of the repair materials with the existing structure, the durability of the repair materials and the existing structure, and anticipated maintenance requirements. The expected service life of the repaired structure is determined in consultation with the owner considering strength, safety, and serviceability requirements and the available repair budget. In many situations, the available budget and other factors limit the extent of repairs that can be completed. To establish an expected service life for a repaired structure, the LDP should understand both the causes of observed deterioration and the impact of the repairs on the performance of the structure. ACI 546.3R discusses the various considerations for how compatibility, interaction, and durability are judged for various repair materials. For example, in many concrete repair applications, the properties of repair materials, such as the coefficient of thermal expansion and creep, should be similar to those of the substrate. In contrast, the success of many crack repair applications depends on repair materials that have significantly different properties from that of the substrate, such as high elasticity and low modulus of elasticity, which will perform better than the base concrete in the service environment (ACI 546.3R). The project examples presented in this guide illustrate project-specific maintenance recommendations that generally result in improved service life of the repairs. Additional discussion of maintenance recommendations is provided in Chapter 1 of this guide. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 62 approach for crack treatment that considers the causes of cracking and the anticipated exposure conditions. Rigid crack repair materials are generally not effective where crack widths are likely to widen or experience cyclic opening and closing due to load effects and restrained volume change. Each of the project examples illustrates unique considerations for the effects of cracks on durability and particular examples of how cracks are considered in the repair design. The following documents may provide guidance for the causes, assessment, and repair of concrete structures. • ACI 201.2R, “Guide to Durable Concrete” • ACI 222R, “Protection of Metals in Concrete Against Corrosion” • ACI 222.2R, “Corrosion of Prestressing Steels” • ACI 423.4R, “Corrosion and Repair of Unbonded Single Strand Tendons” • ACI 423.8R, “Report on Corrosion and Repair of Grouted Multistrand and Bar Tendon Systems” • ACI 546R, “Concrete Repair Guide” • ICRI 310.1R, “Guide for Surface Preparation for the Repair of Deteriorated Concrete Resulting from Reinforcing Steel Corrosion” • ICRI 510.1, “Guide for Electrochemical Techniques to Mitigate the Corrosion of Steel for Reinforced Concrete Structures” • The Concrete Society TR 50, “Guide to Surface Treatments for Protection and Enhancement of Concrete” • NACE SP 0187-2017-SG, “Design for Corrosion Control of Reinforcing Steel in Concrete” • NACE SP 0290-2007, “Impressed Current Cathodic Protection of Reinforcing Steel in Atmosherically Exposed Concrete Structures • NACE SP 0408-2014, “Cathodic Protection of Reinforced Steel in Buried or Submerged Concrete Structures” • NACE 01101-2018-SG, “Electrochemical Chloride Extraction from Steel-Reinforced Concrete—A State-of-the Art Report” 364.3T, and ACI RAP-8 provide further information on the anodic ring (halo) effect. In such cases, the LDP might consider galvanic anodes to reduce the risk of premature corrosion due to the ring anode effect. Dissimilar materials that might result in galvanic corrosion are also to be considered. ACI 222R discusses strategies for avoiding galvanic corrosion. If electrochemical protection systems are recommended, the impact of the cost of these systems on the life cycle of the repaired members and the structure as a whole should be considered. ACI 546.3R discusses corrosion protection and material compatibility in the development of repair solutions. Project Example 1 illustrates several durability considerations and various options for corrosion protection as part of a representative parking garage repair. Project Examples 2 and 3 also include corrosion considerations and mitigation strategies for each specific case. @Seismicisolation @Seismicisolation University of Toronto User. 8.4—Corrosion Corrosion of embedded reinforcement is a common cause of concrete distress and deterioration in many environments. The documents listed in the textbox discuss the causes, assessment, and repair of reinforcement corrosion in concrete structures. There are a number of methods for addressing reinforcement corrosion. These include locations where the reinforcement is in contact with repair materials as well as in locations where the reinforcement remains embedded in the existing concrete. ACI 562, 8.4, requires that corrosion be considered in developing a durable repair strategy. The level of damage to existing reinforcement due to corrosion, including mild and prestressing steel, should be assessed to determine its effects on member strength and bond and development of the reinforcement. For locations where reinforcement will be in contact with repair concrete, various methods such as corrosionresistant reinforcement coatings, galvanic anodes, and replacement concrete materials with enhanced properties (such as corrosion-inhibiting admixtures, additional concrete cover, surface treatments, or coatings) can be used in combination or individually to provide a cost-effective and durable repair. For locations where reinforcement will remain embedded in existing concrete, crack treatments, surface treatments or coatings, surface-applied penetrating corrosion inhibitors, active cathodic protection, galvanic protection, chloride extraction, realkalization, and other measures warrant consideration. A cost-effective repair program usually includes some combination of these measures. For further discussion of corrosion mitigation measures, refer to ACI 546R and The Concrete Society Technical Report 50. Information about the design, monitoring, and maintenance of cathodic protection systems can be found in NACE SP0187, NACE SP0290, NACE SP0408, and NACE 01101. ACI 562 requires that the specified repair materials and reinforcement be compatible with respect to the existing concrete materials and reinforcement, as well as other building materials that remain. Therefore, the new materials should not adversely affect the durability of the existing materials. For example, a difference in electrical potential can arise in existing reinforcement that is continuous between the repair area and existing concrete, and that potential can accelerate reinforcement corrosion at the perimeter of the repair. This phenomenon is termed “the ring anode effect”. ACI 546R, ACI Useful references on the causes, assessment, and repair of reinforcement corrosion in concrete structures Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 8—Durability63 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES 8.5—Surface treatments and coatings Most types of concrete deterioration, including cyclic freezing-and-thawing deterioration, reactive aggregates, and corrosion of embedded reinforcement require the ingress of moisture into the concrete. Surface coatings and treatments, sealant joints, and other waterproofing considerations such as flashings can be effective at limiting moisture and chemical penetration into the concrete and therefore reduce the potential for concrete deterioration. For repair projects where the concrete is already contaminated with chloride or other chemicals and the deterioration processes are already occurring, surface coatings and treatments can be effective remedies to reduce the ongoing deterioration of elevated structures that can dry over time. This is accomplished by limiting the ingress of additional moisture into the concrete. For concrete that is saturated, however, surface membranes can actually accelerate deterioration, as indicated in ACI 562, R8.5.1. The use of surface coatings should be assessed for each project by the LDP prior to specifying them to alleviate deterioration mechanisms. Surface treatments can also help reduce penetration of moisture into cracks. For instance, elastomeric coatings can be effective in bridging moving cracks whereas penetrating epoxy or methacrylate sealers can penetrate and fill narrow nonmoving cracks. Surface treatments, sealant joints, and coatings have a finite service life, and require maintenance to ensure continued effectiveness. These systems also generally require replacement or repair during the service life of the structure. Cracks that may limit the effectiveness of surface treatments and coatings should be assessed and may require special treatment before the selected surface treatment or coating is installed. Project Examples 1, 2, and 3 provide case studies where the use of surface treatments were considered for improved durability. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 64 University of Toronto User. @Seismicisolation @Seismicisolation Hydrodemolition used to remove deteriorated concrete on the supported level of a parking structure 9.1—General The licensed design professional (LDP) needs to communicate the owner’s requirements in clear, well-understood, and coordinated construction documents to the contractor. Accordingly, the contractor is to safely and properly implement the repair, rehabilitation, and strengthening work for the structure to perform as intended. The cost of formwork can be greater than half the total cost of the concrete structure. Therefore, this investment requires careful thought and planning by the LDP when designing and specifying the structure and by the contractor when designing and constructing the formwork. The contractor needs to abide by the construction documents to ensure that work is performed as intended, that testing and inspection are coordinated and performed as specified, and any deviation from the construction documents or unexpected findings during construction are properly communicated to the LDP. The construction documents for repair, rehabilitation, and strengthening should specify, if applicable, specific temporary shoring and bracing requirements, specific jacking requirements, project-specific inspection, testing, and field observation requirements. 9.2—Stability and temporary shoring requirements ACI 562, 9.2.1, 9.2.2, 9.2.3, and 9.2.4, require that temporary shoring and bracing provisions for the project be described in the contract @Seismicisolation documents. Shoring, bracing, @Seismicisolation 65 University of Toronto User. Overview Repair of existing structures presents challenges that may not be encountered in new construction. Chapter 9 of ACI 562 highlights three construction considerations specific to repair projects: stability and temporary shoring, temporary conditions, and environmental issues. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 9—Construction GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES documents. ACI 562 requires the temporary shoring or bracing remain in place until the member is repaired. Continuity of the structure and the required strength of the repair should also be considered prior to removal of the shoring. The shoring and bracing requirements developed by the specialty engineer should consider the following during each phase of the assessment and repair: a. In-place conditions and superimposed loads due to repair construction or continued building operations b. Displacement compatibility between existing members and temporary shoring or bracing c. Global stability of the structure and stability of compression elements or bracing members, including changes in unbraced length d. Lateral forces determined by generally accepted engineering principles or as required by the current building code e. Stiffness of the shoring and bracing systems as required to prevent excessive displacement of existing braced members f. The impact of shoring or bracing loads transmitted to other areas of the existing structure g. Redistribution of loads and internal forces in members subject or adjacent to repair h. The effects of section loss or material degradation on structural member capacity i. Specified camber to ensure completed work is within the tolerance limits j. Constructed formwork dimensions should result in concrete members having dimensions within the specified dimensional tolerances Section 6.0 of Project Example 1 illustrates how the provisions of ACI 562 Chapter 9 might be used to assess stability and temporary shoring requirements during the assessment and repair process for a parking structure. Section 5.3 of Project Example 2 illustrates the process of considering stability and temporary shoring during a typical balcony repair project. Section 6.3 of Project Example 3 illustrates the process of considering stability and temporary shoring for concrete removal on compression members. 9.3—Temporary conditions ACI 562 stipulates loads and load factors during the assessment and repair construction process, including the design of shoring and other temporary construction, be in accordance with ASCE/SEI 7 for buildings occupied during the construction period, and ASCE/SEI 37 for buildings that will be unoccupied during the construction period. ACI 562 requires the design strength of the existing structure or member exceed the required strength for all phases of the assessment and repair process. For example, if during the assessment unsafe conditions are identified, it may be @Seismicisolation @Seismicisolation University of Toronto User. or both is needed to address concrete distress or deterioration that has reduced the structural capacity or stiffness of one or more members below safe levels. Temporary shoring or bracing may also be required to support the existing structure or structural elements, depending on the means and methods adopted by the contractor to execute the repair. For example, the concrete repair process frequently involves the removal of unsound and, as necessary, sound concrete in preparation for the installation of repair materials. Consequently, at one or more stages of the repair process, member structural capacity or stiffness may be reduced below design safety factors, necessitating temporary shoring and bracing. Likewise, complete demolition of one or more structural members can diminish the strength or stability of nearby members that relied on the demolished member(s) for continuity or bracing. For example, shoring may be warranted at slabs or beams adjacent to areas where concrete removal is being performed, prior to the removal of concrete, to minimize the introduction of stresses into these elements due to redistribution of moments. ACI 562 requires the design of temporary shoring and bracing to be performed by an LDP. The LDP responsible for shoring and bracing design will typically be a specialty engineer retained by the contractor. The specialty engineer will develop the details of the shoring and bracing system in conformance with the requirements specified on the contract documents developed by the LDP for the repair and to suit the contractor’s means and methods. In accordance with ACI 562, 9.2.1a, 9.2.2a, 9.2.3, and 9.2.4, the LDP for the repair need only provide the information necessary to design the shoring and review the shoring design to verify design intent and loads imposed on the structure. For example, for a structural alteration that requires removal of an existing column, the LDP for the repair might provide the shoring loads and locations on the contract documents, and require the contractor to submit a design for the shoring for review and approval. In accordance with ACI 562, the specialty engineer will determine where shoring or bracing is necessary to maintain global and individual member capacity and stability, including bracing of compression members. Conditions requiring temporary shoring or bracing may be identified during the assessment of the structure, prior to repairs, or when conditions become apparent during repair construction. As discussed in Section 7.2 of this guide, it is essential that the LDP specify in the repair documents where it is known that shoring or bracing is required, and that the LDP clearly specify limitations on the extent of concrete removal before the specialty engineer is notified to determine if shoring or bracing might be necessary. The contractor should notify the LDP if damage observed during construction is more severe than anticipated by the contract Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 66 Shoring due to failure of columns during repair A high-rise façade repair project involved removing and replacing unsound concrete on exposed concrete columns and slab edges. As much as 20 to 30 percent of the concrete on some columns was removed and replaced following a structurally safe sequence determined by the LDP. During concrete removal on one floor, four columns collapsed and the corner of the building dropped 3/4 in. (19 mm). The LDP was immediately notified and the corner of the affected floor as well as several floors above and below were shored (ACI 562, 9.2.2f and 9.2.8). The owner and the authorities having jurisdiction were also notified (ACI 562, 1.5.2). The shoring layout and system were designed to transfer the entire dead and live load in the collapsed columns out of the columns above the affected floor and back into the columns below the affected floor. The increased shears in the adjacent beams were considered (ACI 562, 9.2.1a, 9.2.2a, 9.2.2d, 9.2.3, 9.2.4, and 9.2.7). A structural assessment was performed on the affected members (ACI 562, 6.2.1 and 6.2.2). Visual, destructive, and nondestructive testing were performed as part of the structural assessment. Evaluation of removed core samples determined that over 50 percent of the column concrete had been patched with mortar (in other words, no coarse aggregates) and the interior column surfaces had then been painted, concealing the patches. The patch material crumbled during coring and was deemed to be very weak. No further strength testing was deemed necessary by the LDP (ACI 562, 6.3.5). Ultrasonic testing and additional coring of other columns determined that the extensive patching was limited to these four columns (ACI 562, 6.2.3). The poor-quality repair mortar resulted in significantly reduced column strength, and the resulting collapse. Assessment of the surrounding members and other areas did not indicate any other structural damage as a result of the collapse. The full section of concrete and poor-quality repair mortar was removed at the affected columns and rebuilt using quality ready mixed concrete. The LDP determined that the design strength for the replacement concrete would be the same as the original column concrete design strength (ACI 562, 7.5). Per ACI 562, 1.2.4.5, 4.1.5, A.2.5, and A.4.1, the replacement columns were reinforced and detailed consistent with the requirements of the current building code. The predicted shortening of the rebuilt columns due to the application of loads and creep; the transfer of axial forces and moments into the new column sections; and the adverse effects of the column replacements on the adjacent portions of the structure were assessed and considered acceptable (ACI 562, 7.2, 7.3, and 7.4). After the concrete had reached its design compressive strength, the shoring was removed and the façade repair program continued. The new columns had the same fire resistance as the existing structure (ACI 562, 7.9). Because it was not feasible to raise the corner of the floors 3/4 in. (19 mm), the corner portions of the affected floor slabs were repaired with a leveling course. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 9—Construction67 University of Toronto User. @Seismicisolation @Seismicisolation GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES necessary to provide temporary shoring and bracing prior to the repair phase. 9.4—Environmental issues ACI 562 requires the contract documents assign the contractor or other designated party responsibility for all specified environmental remediation measures, reporting of any new conditions encountered, and control of all construction debris, including environmentally hazardous materials. Known environmentally hazardous materials and legally required handling and disposal procedures are to be included in the contract documents. Section 8.0 of Project Example 1, Sections 6.0 and 8.0 of Project Example 3, and Section 10.0 of Project Example 5 illustrate environmental concerns during repair projects including the control of water with debris on the site, the control of construction dust and debris, and the disposal of construction debris. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 68 University of Toronto User. @Seismicisolation @Seismicisolation Inspector examining the externally bonded fiber-reinforced polymer (FRP) system installed on the bottom of a concrete beam 10.1—General Quality assurance measures are planned, such as systematic activities that confirm the quality of materials and workmanship used in the work. These activities typically include inspections, testing of repair materials, and other construction observations as necessary to determine if the work conforms to the requirements specified in the contract documents. ACI 562 requires that testing and inspection requirements of the general existing building code or local jurisdiction be described in the contract documents. Quality assurance requirements are included in the contract documents by the licensed design professional (LDP) either through reference to the existing building code or through specified testing and inspection requirements applicable to the project. The LDP should consider the minimum @Seismicisolation inspections required by the @Seismicisolation 69 University of Toronto User. Overview Repair and rehabilitation work is sensitive to quality. Deficiencies in surface preparation, repair material installation, or repair material curing can cause the repair or rehabilitation work to fail prematurely or not perform as intended. Studies such as CON REP NET 2004 indicate that 80 percent of concrete repairs will continue to perform satisfactory after 5 years, but that after 10 years, the percentage of repairs exhibiting satisfactory performance drops to 30 percent. An earlier study completed by the U.S. Army Corps of Engineers (COE ) (McDonald and Campbell 1985) determined that 50 percent of the repairs completed on COE projects are not performing properly. The COE attributed the failure of repairs to a combination of design, material specification, and construction errors. Thus, quality assurance and quality control during construction are essential for the success of a repair or rehabilitation program. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 10—Quality Assurance GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES local jurisdiction, the structural importance of the repairs, the desired service life for the repairs, and the associated costs of the various inspections or tests. Each of the project examples illustrate representative quality assurance programs customized for each of the project scenarios. 10.3—Testing of repair materials ACI 562, 10.3, requires that the LDP specify in the contract documents repair material tests and test frequencies, test reporting requirements, and the time period that the testing agency must retain the test records. The LDP should review the existing building code and general building code, or other requirements adopted by the local jurisdiction governing the repair or rehabilitation construction, and provide appropriate reference to the applicable testing provisions of these requirements in the contract documents. In the absence of any requirement from the local jurisdiction, ACI 562 requires that the test records be retained by the testing agency for a minimum of 3 years beyond completion of construction. ACI 546.3 and ICRI 320.2R discuss various tests of repair materials, including bond strength, dimensional behavior, durability properties, mechanical properties, and constructability properties. As with all components of the quality assurance program, the importance of the tested property, the desired service life for the repair, and the associated costs of the test should be considered when developing the testing requirements. In general, testing for all the listed properties is not practical. Each of the project examples illustrate representative testing requirements for each of the project scenarios. 10.4—Construction observations As required in ACI 562, 10.2.2, the LDP needs to include project-specific testing and inspection requirements in the contract documents. Section 10.4.1 of ACI 562 requires that construction observations be performed as specified in the contract documents. Inspections as specified in ACI 562 Sections 10.2 and 10.3 are intended to verify the quality of materials installed, workmanship used, and compliance of the work to the intent of the construction documents. Observations as specified in ACI 562, 10.4, are intended to verify critical assumptions used in the design of the rehabilitation work. @Seismicisolation @Seismicisolation University of Toronto User. 10.2—Inspection ACI 562, 10.2.1, requires that the inspection and testing meet the minimum inspection requirements of the existing building code or as required by the local jurisdiction. For jurisdictions that have adopted the IEBC, Section 109 of the 2018 IEBC provides the minimum inspections required by the building code official for work where a permit is required. Additionally, special inspections are required per Section A109.3.8 of the 2018 IEBC. Special inspections are to be provided by the owner or owner’s representative and include continuous and periodic inspections or verifications for construction. The required special inspections and verifications for concrete construction are provided in Table 1705.3 of the 2018 IBC. The inspections should be performed by an LDP, a qualified inspector or individual, or a combination thereof per recommendations by the LDP to the owner. The LDP should develop repair construction documents that specify the inspections required by the existing building code, as well as supplemental inspections and tests that are appropriate to the project. ACI 562, 10.2.2, requires that the LDP include project-specific testing and inspection requirements in the contract documents. The repair inspectors should be qualified individuals who are experienced in this type of work and have been certified as an ICRI Concrete Surface Repair Technician – Grade 1, or as an ACI Concrete Construction Special Inspector (ACI C630). The ICRI Concrete Surface Repair Technician Certification Program consists of a two-tiered online educational training program with the second tier providing full certification, qualifying the individual to perform pre- and postplacement inspections and testing on concrete repairs. The ACI Concrete Construction Special Inspector program qualifies a person to inspect and record the results of concrete construction inspection based on codes and job specifications. These programs meet the repair inspector qualifications discussed in ACI 562, R10.2.2. As required by ACI 562, 10.2.3, the project-specific requirements are to state that existing conditions and reinforcement shall not be concealed with materials that preclude visual inspection before completion of the inspection, unless the LDP determines that only representative repair locations need be inspected. Unanticipated conditions are often uncovered during construction. The repair inspector should inform the LDP so that the LDP could assess the situation and determine what actions should be taken before proceeding with the repair or strengthening construction. In addition to the commentary provided in ACI 562, R10.2.2, numerous publications are available that discuss various methods and considerations for quality assurance inspections. ACI 546R discusses particular quality assurance and control measures for concrete repair, and ICRI 210.4 discusses the use of nondestructive evaluation methods for purposes of quality assurance during repair. Additionally, ACI 311.1R and ACI 311.4R provide guidance on quality control, inspection, and testing procedures for concrete. Each of the project examples illustrate representative inspection requirements for each of the project scenarios. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 70 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Chapter 11: Commentary References Restoration of a lock in Florida @Seismicisolation @Seismicisolation 71 University of Toronto User. Overview Chapter 11 of ACI 562 provides the full document titles for references presented in the commentary portion of ACI 562. These references include building codes, guides, reports, standards, and various other published materials and are presented to the LDP for additional information and resources on a given topic. As these references are not all written with mandatory language, the references are not considered part of the code requirements of ACI 562 unless referenced specifically within the body of the ACI 562 code language. The standards that are referenced within the code text of ACI 562 are listed in Chapter 3 of ACI 562. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 71 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Shoring of prestressed beam due to corrosion of prestressed reinforcement. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 72 University of Toronto User. Cast-in-place shear block with anchored external post-tensioning to strengthen beam. @Seismicisolation @Seismicisolation 73 University of Toronto User. The LDP is confronted in the initial stages of a project with the challenge to determine what design-basis code criteria applies. This is more prevalent when a structure was constructed prior to a jurisdiction having adopted a general building code. The structure may have design and construction elements that do not satisfy the original or current building code requirements based on the preliminary assessment in ACI 562 Section 1.7 and the detailed assessment of ACI 562 Chapter 6. Accordingly, the LDP will use Appendix A of ACI 562 to determine if an existing structure should be rehabilitated to satisfy original design requirements or strengthened to satisfy requirements of the current building code. ACI 562 Appendix A is used to determine if an existing structure should be repaired, rehabilitated, or retrofitted to satisfy the requirements of the current building code. When a jurisdiction has not adopted a standard for the assessment of structures for seismic resistance as well as for the repair or strengthening or retroft of individual members, systems, or structures, the LDP should make the determination if seismic assessment is required by using ACI 562 Appendix A.3.3. ACI 562 and ASCE/SEI 41 should be used for evaluation of seismic damage to members, systems, or structures that are seismically unsafe. ASCE/ A.1—General SEI 41 may or may not be applicable to nonbuilding strucAppendix A of ACI 562 applies if a jurisdiction has not tures. Its requirements may apply to nonbuilding structures adopted a code that addresses assessment, repair, and rehasuch as pipe racks, steel storage racks, structural towers bilitation of existing concrete structures such as the Interfor tanks and vessels, piers, wharves, and electrical powernational Existing Building Code (IEBC). Per ACI 562, generating facilities, but the LDP should use judgment, as 1.2.4.2, Appendix A also applies if a jurisdiction has adopted the applicability of these requirements has not been fully ACI 562 as the only existing building code. It can also be used verified for every type of structure. ASCE/SEI 41 states, to supplement Chapter 34 in the 2012 and previous versions of however, that its provisions do not have to apply to large the IBC. nonbuilding structures, such as large tanks found in heavy industry or power plants, floating-roof oil storage tanks, A.2—Design-basis code criteria and large (greater than 10 ft [3 m] long) propane tanks at Where Appendix A of ACI 562 applies, the LDP has to propane manufacturing or distribution plants. determine the design-basis code based on the criteria stated ACI 562 Appendix A should be used to determine the in ACI 562, A.2.1. The LDP may choose, however, to use the assessment and design-basis criteria for a structure, as current building code referencing ACI 318-19 as the designshown in Table A.2 (ACI 562 Table A.2.3) unless the local basis criteria for all damage states, deterioration, faulty jurisdiction imposes more restrictive requirements. design, or faulty construction. The LDP should discuss this The LDP is faced with several questions when confronted option with the owner before using it as it may be unnecwith deteriorated or weakened structures, which should be essarily conservative and may lead to a solution that is not clarified before engaging in the assessment. cost-effective or economical. ACI 562, A.2.4 and A.2.5, require that any new reinforced concrete member added to an existing structure should be designed and detailed to satisfy the current building code (ACI 318). This also applies to the connections between new Chapter 4 and Appendix A of ACI 562 are compamembers and the existing structure. Consequently, when the rable. The reader may perceive similarities in the original building code is used as the design-basis criteria for code text between them, which is mirrored in this repairs, rehabilitation, and strengthening, new concrete or reinguide text as well. Major changes, however, occur forcing members built integrally with the existing concrete strucin A.4—Substantial structural damage, A.7— ture, or both, must be designed using the original building code. Additions, A.8—Alterations, and A.9—Change in In the case where the design-basis criteria for the design occupancy. @Seismicisolation of repairs to existing structures is the original building code, @Seismicisolation Overview Appendix A of this guide provides the criteria for use of ACI 562 to assess and strengthen existing concrete structures when a jurisdiction has not adopted an existing building code. In this case, Chapter 4 of ACI 562, which is used to assess and strengthen existing structures when a jurisdiction has adopted an existing building code, does not apply. Section 1.7 of ACI 562 specifies a preliminary assessment of deteriorated or damaged existing structures to determine the extent and significance of damage and deterioration and the reduced structural capacity of individual existing members and structures. Based on the findings of this assessment, a compliance method is selected by the licensed design professional (LDP) to determine the design basis code. This appendix establishes limits based on demandcapacity ratios for ultimate strength design and allowable stress principles to determine if existing members, systems, or structures are safe or if strengthening, repair, or both, are necessary. The level of strengthening, repair, or both, is influenced by the calculated demand-capacity limits. Project Example 1 illustrates a type of preliminary assessment and method of determining the design basis code and how to apply Appendix A of ACI 562. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Appendix A—Criteria when Using ACI 562 as a Stand-Alone Code GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Table A.2—Design-basis code criteria references for rehabilitation categories Rehabilitation category Potentially dangerous structural conditions for gravity and wind loads Potentially dangerous structural conditions for seismic forces in regions of high seismicity (Seismic Design Category D or higher) Substantial structural damage to vertical members of the lateral-force-resisting system Substantial structural damage to vertical members of the gravity-load-resisting system Damage less than substantial structural damage, deterioration, and faulty construction with capacity increase Damage less than substantial structural damage, deterioration, and faulty construction without capacity increase Sections of this code to use for the assessment criteria Preliminary code of the design-basis criteria used with this code A.3.2 A.3.3 For potentially dangerous structures, current building code* supplemented by ASCE/SEI 41 for seismic if the structure is in Seismic Design Category D or higher A.4 Current building code* for substantial structural damage A.4 Current building code* for substantial structural damage A.5 Current building code* unless compliant with Sections A.5.1, A.5.2 or A5.3 for the original building code† A.6 This code, Chapters 8 through 10 Additions A.7 Alterations A.8 Changes in occupancy A.9 Current building code* unless compliant with Section A.7 for the original building code† Current building code* unless compliant with Section A.8 for the original building code† If rehabilitation is required, then use the current building code* Note: Section and chapter numbers refer to ACI 562. Wording such as “this code” also refers to ACI 562. * Current building code is as per 1.2.2. † Original building code is as per 1.2.3. The LDP should determine if the structure has demonstrated statically acceptable performance based on historical data, such as acceptable resistance of previous loads that equal or exceed the loads that would be predicted for the remaining life of the structure. The LDP may judge the structure to have demonstrated historic structural reliability. The following references provide guidance in judging acceptable performances. The design basis code for repair and rehabilitation projects varies based on the extent of alterations, additions, or repairs. In general, the original building code is the design basis for minor alterations without significant changes in load. The current building code serves as the design basis for elements subject to major alterations or significant load Useful references for assessing and changes. For evaluation of seismic resistance and rehabilitaevaluating existing concrete structures tion design, ACI 562 requires that ASCE/SEI 41 needs to The following documents are listed in the commenapply per Section 1.3.8.1. Similarly, the design of repairs tary of ACI 562 Section RA.2.4 and may provide subject to elevated temperatures and fire should satisfy the guidance in judging acceptable performance. applicable existing building code. • ACI 224.1R, “Causes, Evaluation, and Repair In the industry, a quantitative measure or scale to determine the of Cracks in Concrete Structures” level of deterioration or damage exhibited by an existing structure • ACI 437R, “Strength Evaluation of Existing does not exist. There are, however, processes that can be applied Concrete Buildings” to determine the safety level of an existing structure. Neverthe• ACI 437.1R, “Load Tests of Concrete Strucless, the LDP is confronted with several questions that require tures: Methods, Magnitude, Protocols, and careful planning and response. Some of the questions may be: Acceptance Criteria” a. When should an existing structure be strengthened or @Seismicisolation repaired? @Seismicisolation University of Toronto User. detailing of the existing reinforcement does not need to comply with the current building code requirements if the following conditions are satisfied: a. The damage or deterioration to the existing reinforcement is addressed b. The repaired work area of the structure has capacity equal to or greater than demand per ACI 562 Section 5.2.2 using the original building code requirements or satisfies the requirements of ACI 562 Section A.5.3 when using allowable stress design Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 74 ACI 562 Chapter 2 defines potentially dangerous structural condition as follows: potentially dangerous structural condition— structural state of an individual structural member, structural system, or structure with instability, potential collapse of overhead components or pieces (falling hazards), noncompliance with fire resistance ratings or demand to capacity ratio limits above acceptable limits defined in this code. b. What is an acceptable demand-capacity ratio limit to consider an existing structure safe? c. What is the minimum acceptable strengthening or repair level that is considered safe? d. When should an existing structure’s capacity be increased? e. How should an existing structure be evaluated by the working stress method? f. When should an existing structure be strengthened or repaired to the original building code or applicable existing building code level? These and other questions that may arise are addressed in ACI 562, A.3 through A.5. ACI 562-19 useful references for potentially dangerous structural conditions The following documents are listed in the commentary of ACI 562-19 and may provide target reliability indexes, basic probability theory, and concepts for an assessment using the specific details of the demand as it relates to the capacity with the strength reduction factors of Chapter 5 for concrete structures. • ASCE/SEI 7-16, “Minimum Design Loads for Buildings and Other Structures” • Galambos, T.V.; Ellingwood, B.R.; MacGregor, J.G.; and Cornell, C.A., 1982, “Probability Based Load Criteria: Assessment of Current Design Practice,” Journal of the Structural Division, V. 108, No. 5, pp. 959-977. • Ellingwood, B.R.; MacGregor, J.G.; Galambos, T.V.; and Cornell, C.A., 1982, “Probability Based Load Criteria: Load Factors and Load Combinations,” Journal of the Structural Division, V. 108, No. 5, pp. 978-997. • Ellingwood, B.R., and Ang, A. H.-S., 1972, “A Probability Study of Safety Criteria for Design,” Structural Research Series No. 387, Engineering Experiment Station, University of Illinois at Urbana-Champaign, Champaign, IL. The LDP may also consider the following to satisfy Eq. (A.3): a. Adding structural redundancies which are desirable to ensure the safety of a structural system b. Providing alternate load paths, redistributing the load, or limiting the live load such that existing members are not overstressed c. Adding shoring to support members and to relieve overstressed members If the demand-capacity ratio is less than 1.5, however, then less-restrictive requirements are implemented as described in A.4 through A.9 of this guide. Potentially dangerous structural conditions in Seismic Design Category (SDC) D, E, and F structures, as deterUc (A.3) mined per ASCE/SEI 7, are assessed using ASCE/SEI 41. > 1.5 φRcn The design-basis criteria for rehabilitation design and where Uc is defined as strength design demand by using nominal construction of potentially dangerous structures are loads of the current building code and factored load combinaASCE/SEI 41 and ACI 562. tions of ASCE/SEI 7 for strength design provisions (LRFD); Rcn Unless addressed by the authority having jurisdiction, is the current in-place nominal capacity of structural member, for structures in SDC D, E, and F, the LDP should review system, or connection including the effects of damage, deteriothe structure for potentially hazardous seismic conditions. ration of concrete and reinforcement, and faulty construction; The review should be completed to confirm the structure is and φ is the strength reduction factor obtained from Section 5.3 adequate for either the seismic performance level required or 5.4 of ACI 562. A demand-capacity ratio greater than 1.5 by the local authorities, or confirm the structure is compliant calculated using Eq. (A.3) represents a condition with limited with ASCE/SEI 41 for Structural Performance Level – to no margin of safety against failure. Potentially hazardous Collapse Prevention using Earthquake Hazard Level, BSE-1. structural conditions requiring immediate attention should be Earthquake Hazard Level BSE-1 has a 20% probability of reported to the owner per ACI 562, 1.5.2. @Seismicisolation exceedance in 50 years, or a 225-year return period. @Seismicisolation University of Toronto User. A.3—Potentially dangerous structural conditions The LDP needs to determine if potentially dangerous structural conditions exist by carrying out a thorough assessment of the deterioration or damage to the existing structure, as discussed in Chapters 1 and 6 of this guide. The risk for collapse of each proposed strengthening procedure should be assessed to determine an economical and safe repair strategy. The LDP calculates the strength demand based on the current building code, considering gravity and fluid loads and lateral wind and soil loads but excluding seismic loads. The governing load is determined using factored load combinations of ASCE/SEI 7. In this appendix, the term “gravity loads” refers to dead, live, and snow loads. Reduction factors from ACI 562, 5.3 or 5.4, are used whether a structure is rehabilitated or assessed. If the demand-capacity ratio, as given in Eq. (A.3) (ACI 562-16, Eq. (A.3.2)), is greater than 1.5, then the structure should be strengthened or repaired based on the current building code 75 Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. APPENDIX A GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES When the local authority having jurisdiction does not provide requirements for potentially hazardous seismic structural conditions, then the LDP should refer to ATC-78, the IEBC, and ASCE/SEI 41 appendixes for guidance. The LDP is not required to assess potentially hazardous seismic conditions for concrete structures located in moderate to low seismicity regions. A.4—Substantial structural damage A structure determined safe should be assessed to decide if the sustained damages are substantial. If a jurisdiction has not adopted IEBC, the IEBC definition of substantial structural damage cannot be used. The ACI 562 approach to substantial structural damage is based upon the requirements presented in the IEBC, with some modifications added to enhance clarity. When substantial structural damage has occurred, ACI 562 requires the structure be strengthened to satisfy current code requirements. ACI 562 focuses on substantial structural damage to lateral-force-resisting systems and to gravity-load-resisting systems. Gravity load per ACI 562 is considered to consist of dead load D, live load L, and snow load S. A lateral-force-resisting system of a structure is considered to have substantial structural damage if the vertical members in any story, shear walls, or columns of the lateralforce-resisting system are damaged such that the lateralforce-resisting nominal capacity of the structure, ∑Rcn, in any horizontal direction is reduced by more than 33 percent from its predamaged condition, ∑Rn, as presented by Eq. (A.4a) (ACI 562 Eq. (A.4.1a)). ∑ Rn ≥ 1.25 (A.4b) ∑ Rcn The gravity-load-resisting system of a structure should also satisfy the condition such that ratio of the factored gravity load of the current building code, ∑Uc, to the in-place vertical design capacity, ∑Rn, of these damaged members is greater than 33 percent per Eq. (A.4c) (ACI 562 Eq. (A.4.1c)). ∑ Uc ≥ 1.33 (A.4c) ∑ Rcn Equations (A.4a), (A.4b), and (A.4c) use the reduction factors of ACI 562 Chapter 5. A.5—Conditions of deterioration, faulty construction, or damage less than substantial structural damage This section addresses reinforced concrete structures that are safe, have less than substantial structure damage, but have deterioration or faulty construction and there is reason to question the capacity of the structure. Accordingly, assessment is performed by checking one of the criteria in ACI 562 Sections A.5.1, A.5.2, or A.5.3. ACI 562 requires that demand-capacity ratio of a member, system, or structure be assessed in accordance with Eq. (A.5) (ACI 562 Eq. (A.5.1)). Uo > 1.0 φo Rcn (A.5) where Uo is the strength design demand determined by using the nominal loads and factored load combinations of the original building code, excluding seismic loads, and foRcn is the capacity adjusted by the strength reduction factor (fo) of the original building code. If Uo/fRcn is greater than 1.0, the LDP is permitted to repair and restore the structure to the predamaged or predeteriorated states and satisfy the original building code requirements. Most existing concrete structures with damage less than substantial structural damage, deterioration, or containing faulty construction, will provide acceptable safety if restored to the strength of the original building code. The LDP is permitted to use material properties of the original construction when designing the repair or rehabilitation work to existing concrete structures. New members or connections to @Seismicisolation @Seismicisolation University of Toronto User. ∑ Rn (A.4a) ≥ 1.5 ∑ Rcn A gravity-load-resisting system is considered to have substantial structural damage if any wall, column, or a group of vertical members of the gravity-load-resisting system having a tributary area greater than 30 percent of the total area of the structure’s floor(s) or roof(s) are damaged such that the total vertical nominal capacity, ∑Rcn, is reduced by more than 20 percent from its predamaged condition, ∑Rn, as presented in Eq. (A.4b) (ACI 562 Eq. (A.4.1b)). For substantial structurally damaged structures, the design-basis code is the current building code demands supplemented by ACI 562 for existing structures and ASCE/ SEI 41 for seismic design provisions for the following: a. Lateral-force-resisting system in both directions for the case of substantial structural damage in either direction from lateral force b. Vertical member of the gravity-load-resisting system for the case of substantial structural damage from gravity loads Structures assigned to SDC D, E, and F per ASCE/SEI 7 with substantial structural damage caused by earthquake are assessed or rehabilitated for load combinations that include earthquake effects. The level to which a structure is assessed or rehabilitated is based on seismic design provisions of ASCE/SEI 41. When the objective is life safety, use ASCE/ SEI 41 Earthquake Hazard Level BSE-1E and use BSE-2E when the objective is to prevent the collapse of the structure. The design-basis code for new members and connections to existing members is the current design building code. Structures with substantial structural damage caused by wind should be assessed or rehabilitated using load combinations that include the current building code gravity and wind loads. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 76 77 Fig. A.5a—Selecting design basis code. existing members, however, should be designed to satisfy the current building code. For structures with a demand-capacity ratio of less than 1.0 (Eq. (A.5)), strengthening is not required. For an existing structure that was subjected to known loads equal to or higher than specified in the design documents during its service life but has performed satisfactorily, it should be taken as an indicator that the existing structure has an adequate safety factor and strengthening is not required. Figure A.5a provides a road map for selecting the designbasis code. ACI 562 Section A.5.2 provides alternative assessment criteria for structures with deterioration, faulty construction, or damage less than substantial structural damage. The LDP @Seismicisolation @Seismicisolation University of Toronto User. Uc – Demand using nominal loads of the current building code and factored load combinations of ASCE/SEI 7 for strength design provisions Uo – Demand using nominal loads and factored load combinations of the original building code for strength design provisions Rcn – Current in-place nominal capacity of structural member, system, or connection including the effects of damage, deterioration of concrete and reinforcement, and faulty construction Rn – Nominal capacity of structural member, system, or connection excluding the effects of damage, deterioration of concrete and reinforcement, and faulty construction φ – Strength reduction factor per ACI 562 Section 5.3 or 5.4 φο – Strength reduction factor of the original building code Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. APPENDIX A GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES University of Toronto User. should assess whether the demand or capacity of the origACI 562, A.5.3, provides provisions to assess such a inal structure is significantly inconsistent with the current structure. The demand-capacity ratio is based on service standards, which may result in unacceptable structural load demand, Us, and resistance using allowable stresses, safety issues. ASCE/SEI 7, Galambos et al. (1982a, b), and Ra. If the demand-capacity ratio is greater than 1.0 (Us/Ra > Ellingwood and Ang (1972) should be considered in the 1.0), then strengthening of a structure is required using selection of a relevant assessment criteria. The applicathe original building code. If the demand-capacity ratio, bility of the original building code for assessing existing however, is less than 1.0 (Us/Ra < 1.0), then strengthening structures should be questioned if any of the following is not required. conditions exists: The service load demand includes nominal gravity loads a. Increased load intensity and lateral wind and seismic forces using load combinations b. Added loads of the original building code. The LDP should be aware c. Changes in load factors, strength-reduction factors, or that using the allowable stress design method is inconsisload combinations tent with the reliability principles of current strength design d. Modifications of analytical procedures provisions. Therefore, the structure should be verified e. Changes in determining capacity between the original and following ACI 562, A.5.2, and the seismic resistance should current building codes, such as a change from allowable be checked using ASCE/SEI 41. The LDP may restore a stress design to ultimate strength design member or system to the capacity of the original building f. The benefits received from strengthening or repair do not code using the material properties of the original construcjustify the incurred cost tion. New members, however, must satisfy the requirements The LDP may use a probabilistic approach of loads and of current building code. capacities to show that the structure has adequate reliTable A.5 summarizes the different assessment condiability indexes or may use an assessment procedure based tions the LDP may consider when analyzing a structure for on demand-capacity ratios that are derived from the basic repair, rehabilitation, or strengthening. The alternate assessengineering principles as presented in current standards. ment criteria, Section RA.5.2, are included in the table even ACI 562 defines demand based on the current building though they are not code requirements. However, the LDP code (Uc) as the effect of nominal gravity loads and lateral will likely find these criteria useful in situations where wind and soil loads, excluding earthquake loads, using significant differences exist between the original design ASCE/SEI 7 factored load combinations. ACI 562 defines loads and current design requirements. demand based on the original building code (Uo*) as the effect of the original building code nominal gravity loads A.6—Conditions of deterioration, faulty and lateral wind and soil loads, excluding earthquake construction, or damage less than substantial loading, using the factored load combinations of ASCE/ structural damage without strengthening SEI 7. The LDP has to compare the demand based on the For structures not strengthened using ACI 562, A.3 current building code (Uc) to the demand of the original through A.5, the LDP should follow ACI 562, A.6 through building code (Uo*). A.9, to determine the design-basis criteria to impleIf Uc > 1.05Uo*, then the LDP has to determine the demandment for strengthening. For structures with minimal or capacity ratios based on the current building code, Uc/fRcn. no damage or faulty construction that do not require If the ratio exceeds 1.1(Uc/fRcn > 1.1), then strengthening strengthening per ACI 562, A.5, the LDP can use Chapof the structure or member to the current building code is ters 7 through 10 of ACI 562 as the design-basis criteria required. Otherwise, strengthening is not required. to rectify the shortcomings. If the current building code demand, however, does not Corroded or damaged reinforcement affects the behavior exceed the original building code demand by more than of the concrete structure. It may result in concrete cracking, 5 percent (Uc ≤ 1.05Uo*), then the LDP should check the possible reduction in section capacity resisting the applied demand-capacity ratio using the original building code loads, or both. The LDP should evaluate the effectiveness of demand and the current building code capacity. If the ratio the reinforcement per Chapter 7 of ACI 562. exceeds 1.05(Uo*/fRcn > 1.05), then the system or member ACI 318, as well as other codes, control predicted deflecstrength should be restored to its original strength using tions by either limiting calculated deflections to some the original building code. Otherwise, strengthening is not specified allowable limits, or specifying a minimum spanrequired (refer to Fig. A.5b). For both conditions, the strength to-thickness ratio. These limits, however, are based on past reduction factors are obtained from ACI 562 Chapter 5. experience with loads (for example, normalweight concrete The LDP is often confronted with deteriorated or with loads less than approximately 100 lb/ft2 [488 kg/m2] damaged structures designed using the working or allowlive load for two-way slabs), boundary conditions, and spans, able stress method that was the only available method for among other factors. Structures with aggressive construction designing structures prior to ACI 318-63. In 1963, the schedules resulting in heavier-than-planned construction strength design method was introduced into ACI 318 next loads, premature form removal, and accelerated shoring and to the working stress method. In 1971, ACI 318 dropped reshoring may result in members or structures with excessive the working stress method and retained the strength deflections or having vibration issues that should be assessed design method. @Seismicisolation for safety and comfort of the occupants. Excessive deflec@Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 78 79 Uc – Demand using nominal loads of the current building code and factored load combinations of ASCE/SEI 7 for strength design provisions Uo* – Demand using nominal loads of the original building code and factored load combinations of ASCE/SEI 7 for strength design provisions Rcn – Current in-place nominal capacity of structural member, system, or connection including the effects of damage, deterioration of concrete and reinforcement, and faulty construction φ – Strength reduction factor per ACI 562 Section 5.3 or 5.4 Fig. A.5b—Alternate method for evaluating reinforced concrete structure. A.7—Additions Structures without structural damage, deterioration, or faulty construction and receive additions, undergo alterations, or there are changes in occupancy, need to satisfy the provision of Sections A.7, A.8, or A.9 of ACI 562. In a case where a structure is receiving additions such as new columns, beams, or a new expansion to the existing structure, the LDP should evaluate the gravity load demands of the existing gravity-load-resisting systems and members with the additions based on the current building code and the original building code. If the gravity load demands based on the current building code, Uc, are greater than 5 percent than the demands based on the original building code, Uo, then the design-basis criteria is the current building code with ACI 562 for the assessment and design of existing systems and members and ACI 318 for the design of new members. If an addition results in a decrease in the gravity-loadresisting systems and members’ capacity, Rn, using ACI 562, then the LDP needs to ensure that the in-place capacity exceeds the current building code demand, Uc. If the vertically self-supporting addition is dependent on the existing structure for lateral-force resistance, then the design-basis code for the existing lateral force-resisting system with the new addition is the current building code supplemented by ASCE/SEI 41 for seismic assessment and design. ACI 562 provides an exception to the aforementioned guidance to new additions by allowing the LDP to use the original building code for the assessment and designbasis criteria of the lateral-force-resisting system if the calculated demand-capacity ratio of the existing structure based on the original building code increased by 10 percent is at least equal to the demand-capacity ratio of @Seismicisolation @Seismicisolation University of Toronto User. tions exceeding the maximum allowed by code, however, may be acceptable to the owner or user, provided the member or structure performance is not adversely affected. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. APPENDIX A GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Table A.5—Assessment conditions for reinforced concrete buildings ACI 562 Section Demand/capacity Design-basis code Potentially dangerous condition, Section A.3 Gravity and wind load A.3 Current building code and ASCE/SEI 7 for factored load combinations Uc/fRcn > 1.5 Seismic A.3 ASCE/SEI 41 and ACI 562 Substantial structural damage, Section A.4 Gravity load ∑ Rn ≥ 1.25 ∑ Rcn A.4.1b and and ∑ Uc ≥ 1.33 φo Rcn Current building code demand supplemented by requirements of ACI 562 A.4.1c ∑ Rn ≥ 1.5 ∑ Rcn Lateral-force-resisting system A.4.1a Seismic Section A.5.1 Section A.5.2C(a) Section A.5.2C(b) Current building code demand supplemented by ASCE/SEI 41 ASCE/SEI 41—Earthquake Hazard Level BSE-1E with the Basic Performance Objective of “Life Safety” for Risk Category I, II, or III (ASCE/SEI 7) and of “Immediate Occupancy” for Risk Category IV Deterioration, faulty construction, or damage less than substantial Original building code, Uo/foRcn > 1.0 new members use current building code Alternate assessment criteria for deterioration, faulty construction, or damage less than substantial Uc > 1.05Uo* and Current building code Uc/fRcn > 1.1 * Uc > 1.05Uo and Strengthening not required Uc/fRcn < 1.1 Uc < 1.05Uo* and Original building code Uo*/fRcn > 1.05 * Uc < 1.05Uo and Strengthening not required Uo*/fRcn < 1.05 — Original building code only used allowable stress design and design service loads Us/Ra > 1.0 Original building code Strengthening not required Us/Ra < 1.0 Section A.5.3 Condition Design-basis code For existing structure and addition: Uc > 1.05Uo Current building code w/ Decrease in gravity-load-resisting systems and member capacity due to addition Addition depends on existing building for lateral-force resistance Exception: Uc/Rn (w/addition) ≤ 1.1Uo/Rn (w/o addition) the existing structure, including the addition based on the current building code; refer to Table A.7. A.8—Alterations In case a structure undergoes alterations such as creating an opening in an elevated slab, removing a beam, or change in the load path, the LDP should evaluate the gravity load demands of the existing gravity-load-resisting systems and members with the alterations based on the current building code and the original building code. If the gravity load Existing members: ACI 562 New members: ACI 318 Rn (existing structure + addition) per ACI 562 > Uc per current building code Current building code supplemented by ASCE/SEI 41 Original building code for any lateral-force-resisting member demands based on the current building code are greater than 5 percent than the demands based on the original building code, then the design-basis criteria is the current building code with ACI 562 for the design of existing systems and members and ACI 318 for the design of new members. Increasing member sizes or creating openings in a slab may increase or decrease the design lateral loads on a structure and may result in a structural irregularity, as defined in ASCE/SEI 7. @Seismicisolation @Seismicisolation University of Toronto User. Table A.7—Design-basis code for different addition requirements to existing structures Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 80 Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. University of Toronto User. @Seismicisolation @Seismicisolation Removing deteriorated concrete Column after repair Framing in place ready for repair material 81 APPENDIX A GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Table A.8—Design-basis code for different alteration requirements to existing structures Condition Design-basis code For existing structure and alteration: Uc > 1.05 Uo Current building code w/ Decrease in gravity-load-resisting systems and members capacity due to alteration Alteration results in structural irregularity and increase in lateral loads or decreases lateral capacity Exception: Uc/Rn (w/alteration) ≤ 1.1Uo/Rn (w/o alteration) ACI 562 provides an exception to the aforementioned guidance of structural alterations by allowing the LDP to use the original building code for the assessment and designbasis criteria of the lateral-force-resisting system if the calculated demand-capacity ratio of the existing structure based on the original building code increased by 10 percent is at least equal to the demand-capacity ratio of the existing structure, including the alterations based on the current building code; refer to Table A.8. A.9—Changes in occupancy When a change in use or occupancy is proposed by the owner, the LDP should review the demand resulting Existing members: ACI 562 New members: ACI 318 Rn (existing structure + alteration) per ACI 562 > Uc per current building code Current building code and ASCE/SEI 41 Original building code for any lateral-force-resisting member from the new use or occupancy using the appropriate current building code mandated loads compared to the demands determined using the original building code demands. The change in use or occupancy is acceptable if the structure is evaluated and shown to comply with current building code or rehabilitated. The rehabilitation of the existing structure should be performed in accordance with ACI 562 and the current building code. ACI 318 should be used for the design and connection of new members to the existing structure. Seismic design criteria, when required, should be obtained from ASCE/SEI 41. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 82 University of Toronto User. @Seismicisolation @Seismicisolation 83 University of Toronto User. Overview any statement within this document in the format of “Section After the publication of ACI 562, the next logical step was x.x” refers to a section within ACI 563, “Specification for to publish a standard that covers the specification of repair Repair of Concrete in Buildings,” directing the reader where of existing concrete structures. Hence, the publication of the relevant information can be found. ACI 563, “Specification for Repair of Concrete in Buildings.” The architect/engineer (A/E) should cite ACI 563 in General any construction repair and rehabilitation project involving Complete specifications and good quality workmanship structural concrete in the project specifications. It is worth are fundamental to the success of construction and duramentioning that ACI 318 and ACI 562 use licensed design bility of concrete repair work. Owners need assurance from professional (LDP) when referring to the person in charge A/Es and contractors that the repaired concrete structures of the design new structures or repair and strengthening of will achieve the intended design life expectancy as desired existing structures, whereas ACI 301 and ACI 563 use the by owners. Therefore, to achieve lasting and durable repair term architect/engineer (A/E). work of structures beyond the design phase, sound, clear, Each technical section of ACI 563 is written in the threeand applicable project specification is required that allows part section format of the Construction Specifications Instifor an effective quality management program to be impletute, as modified by ACI (Suprenant 2019): mented. This can be achieved at two levels: the design level, 1. Part 1 covers general administrative requirements such as were the A/E produces specifications that are specific and definitions, submittals, referenced standards, and acceptance address the actual conditions present in the project and criteria provides requirements for the contractor; and at the execu2. Part 2 addresses products and materials tion level, where the contractor ensures that the personnel 3. Part 3 deals with execution performing the work are well trained, adept, and are familiar ACI 563 is divided into 10 sections, Notes to Specifier, with the type of work to be performed. Mandatory Requirements Checklist, and Optional Satisfied The A/E should include only pertinent provisions to the Requirements Checklist. The first section covers general project in the project specifications and not reference the construction requirements for all repair work, including entire ACI 563 document and have the contractor search for terminology (Section 1.3) and referenced standards (Section the relevant sections in the document; otherwise, it may lead 1.4). The second section includes shoring and bracing to confusion, frustration, and possible conflicts. of the structure or members to be repaired, and addresses It is in the best interest of the contractor to have the workers sequencing of repair work as the structure is unloaded and properly trained in the execution of the Work to be applied. reloaded. The third section deals with concrete removal and Many material producers/suppliers provide training on the preparation of the concrete substrate for repair and defines application of their material. ICRI has developed certificates common equipment and methods. The fourth section covers to ensure that workers are familiar and able to perform repair formwork performance criteria and construction, shoring, work satisfactorily. and backshoring. Section 5 focuses on the different types of reinforcement and reinforcement supports. Section Section 1—General requirements 6 covers materials and proportioning of concrete, duraThis section addresses general information for repair work bility of concrete, trial mixtures, and concrete compressive in existing concrete structures. It states that this specificastrength determination. Section 7 covers placing, finishing, tion governs if there is conflict with referenced material and and curing of repair materials; treatment of joints; repair of testing standards. The contractor, however, is permitted to surface defects; mockups; embedded items; and finishing submit alternative requirements to any provision in this of formed and unformed surfaces. Provisions governing specification for consideration. The specification claritesting, evaluation, and acceptance of repair materials as fies language how to interpret language when “and,” “or,” well as acceptance of the repair work are included. Section 8 “may,” or “will” are used. For example, when two or more includes proprietary cementitious and polymer repair mateitems are connected by “and,” then all conditions, requirerials. Sections 9 and 10 incorporate by reference two other ments, events, or connected items apply, whereas connected specifications—ACI 503.7, “Specification for Crack Repair items, conditions, requirements, or events connected by “or” by Epoxy Injection,” and ACI 506.2, “Specification for only apply to one item. “May” or “will” are for information Shotcrete,” respectively. To help the specifier, Mandatory purposes to the contractor only (Section 1.2). and an Optional requirements checklists are provided at the The specification further states that the user should interend of the specification standard. pret the provisions with the plain meaning of the words In this chapter, where appropriate, the text will reference and terms used. For example, the phrase “as indicated in specific sections within the specification to help the reader the contract documents” (Section 1.2.1.8) means that the better navigate the specification and become familiar and specifier included the provision requirements in the contract get better understanding of the document content. Therefore, @Seismicisolation documents. The phrase “unless otherwise specified” (Section @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Appendix B—Repair Guide GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Example B.1a—Language used in the specification as a direction to the contractor EXAMPLES 1) Field bending of reinforcing bars partially embedded in concrete shall not be permitted, except as indicated in contract documents 2) Owner will furnish, as indicated in the contract documents, all required rights to use the lands upon which the work occurs. 3) Unless otherwise specified in the contract documents, construct formwork so concrete surfaces conform to the tolerance limits of ACI 117. 4) Concrete for slab-on-ground shall be 4000 psi unless otherwise specified 5) If specified, admixtures shall be subjected to the following limitations: … 6) Foundation shall consist of portland cement concrete, and reinforcement if specified on the plans … The contractor is not only required to protect the members or structure itself but must also protect adjacent properties and public, especially if exterior repair work is involved (Fig. B.1b and B.1c), as well as the work itself. For example, protecting concrete work while curing from mechanical disturbances or environmental conditions if exposed to high temperature variations, sunlight, wind, and other conditions. University of Toronto User. Preinstallation conference After the signing of the construction contract and before the commencement of construction, it is important that all parties meet, discuss the project, and address all issues related to the project. A successful project must have proper, clear, and transparent communication between all parties. Therefore, having a preinstallation conference, also termed “preconstruction meeting” or “project start-up meeting,” is essential to set the project on a path that promises a wellorganized and successful project and provides a platform for effective communication between all involved parties. The preinstallation conference or preconstruction meeting will set expectations and will help to ensure that issues will be addressed on time, minimizing downtime and resolving disagreements that may arise during construction through the established lines of communication, saving owner both time and money. 1.2.1.9) means that the specifier may have included an alterIt is the A/E’s responsibility to prepare a comprehennative to the default requirement in the contract documents. sive agenda to the project and distribute to all involved The phrase “if specified” (Section 1.2.1.10) means that the parties designated representatives ahead of time (Section specifier may have included a requirement in the contract 1.6). At the meeting, the A/E should facilitate the discusdocuments for which there is no default in the specification sion to ensure that all parties involved fully understand the (Example B.1a). goals and objectives for the repair project and the expected requirements to achieve them. It will also serve as setting the General procedures ground rules for the project for defining the lines of commuThis section addresses construction loads, protection, and nication, the coordination of inspections, the handling of completed repair work. It is imperative for the contractor to nonconformances, and the chain of command. protect the structure and its content during the work. The At the preinstallation conference, several items are usually contractor is directed not to overload the structure by propdiscussed at length and ground rules are set for the duration erly distributing repair materials stored in the vicinity of of the project, such as the submittal schedule and turnaround construction work. Equipment and other construction loads of the shop drawings and request of information (RFI) should be strategically located such that its effects do not responses’ timeframe. For example, what is the process/ exceed the capacity of the member, thus jeopardizing the procedure when a shop drawing or submittal is rejected capacity of the supporting member or, in extreme cases, the or declined? This will help move the project forward and capacity of the structure itself (Fig. B.1a). Sometimes, due realize a successful project while minimizing surprises. to construction sequencing or extent of repair, the stability From the contractor’s perspective, the meeting creates of a member or capacity is compromised. The contractor an opportunity for the contractor to discuss special project should consult the A/E to alleviate this unsafe condition features and requirements; to understand the design intent of by designing for temporary shoring, bracing, or both the repair work; to have specific details or repair sequencing (Section 1.5.2). clarified by the A/E; and to propose alternate details, repair The material delivered to the job site should be in conformaterials, or both, to be used on the project to reduce or mance with the specifications. Often, the contractor will minimize future conflicts. propose alternates to the specified materials and, if approved Although on small projects the issues can be handled as the by the A/E, then the alternate materials can be used. It is project progresses, the preconstruction meeting, however, is therefore required that any material delivered to the job site a chance to handle these important issues in a more formal, should be clearly marked with legible and intact labels with less haphazard, and less painful way. manufacturers’ name, brand name, lot number, and identiIn summary, the preinstallation conference is used to fying contents of containers to be easily identified by the establish the line of communication between all involved inspector and compared to the specified material in the parties, to define items to be inspected, to outline how to contract documents or approved alternate. @Seismicisolation handle nonconformances, and to determine the chain of @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 84 85 Fig. B.1a—Construction load during change of occupancy work of Frederick Douglass Building, University of Rochester, Rochester, NY (photo courtesy of University photo/J. Adam Fenster). command in the project as a whole. It ensures that the project proceeds efficiently. Refer to Example B.1b for a preinstallation meeting agenda sample (ACI 132R and ICRI 110). Fig. B.1c—Sidewalk debris containment and overhead protection for workers and pedestrians underneath (photo courtesy of Superior Scaffold Services). d. What are the expectations from the QA/QC programs? The first step in the QA/QC program is to develop an organizational chart and assign the responsibilities to individuals. This will provide a roadmap of the process for easy reference. QA and QC are sometimes used interchangeably but they have different practices and meanings (refer to Example B.1c). Quality assurance, quality control, testing, and inspection The preinstallation conference is the first step in the quality assurance and quality control (QA/QC) program. At the preinstallation conference, matters and issues related to QA/QC are raised and addressed (Section 1.8): Quality assurance (QA) a. Who is responsible for the QA/QC program? ISO 9000 (2005a) defines QA as, “part of quality manageb. How will the parties involved solve the problems that ment focused on providing confidence that quality requirearise? Who must be notified and when? What is the ments will be fulfilled.” In other words, it is the process in procedure? which a construction company provides the best possible c. How often should the QA/QC team meet to discuss project product to an owner. QA is planned and developed prior to status and quality issues? @Seismicisolation any construction activity and is performed during the dura@Seismicisolation University of Toronto User. Fig. B.1b—Sidewalk overhead pedestrian and traffic protection (photo courtesy of CityRealty by CityRealty Staff). Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. APPENDIX B Example B.1b—Preinstallation meeting agenda example University of Toronto User. @Seismicisolation @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES 86 87 Example B.1c—Differences between QA and QC programs (Sam-solutions.com) Quality assurance and quality control comparison chart QA QC A managing tool A corrective tool Process-oriented Product-oriented Proactive strategy Reactive strategy Prevention of defects Detection of defects Everyone’s responsibility Testing team’s responsibility Performed in parallel with a project tion of a construction project to ensure that the project meets the quality standards. It provides the owner with a sense of comfort that all the agreed-upon methods, approaches, and techniques will be implemented as agreed upon and will possibly be modified during the course of a project, as deemed necessary, to prevent mistakes, omissions, or substandard practices. To achieve this goal, the QA program must rely on welldeveloped and complete project specifications and contract documents specifying what should be tested and the frequency of tests, which activities require certified workers, and which tests require certified technicians. The QA process has both advantages and disadvantages. Disadvantages of quality assurance a. Time-consuming; it adds more time to a project schedule for periodical meetings and implementing the process. It also requires time to train the workers. b. High cost; to train and implement the process will add to the cost of the project. In conclusion, the value of implementing a QA program outweighs the inconveniences and cost of implementing one. the authority, given as a signed letter by the owner, to stop work if construction is substandard and does not meet the minimum standard requirements and installed material deviated from the specifications, or did not pass the specified test standards. In general, for a project without a QC program, the final inspection that contractors and owners usually do, also termed as “walk-through,” is at the end of a project. The concern with such an approach is that the contractor/subcontractor has to fix any shortcoming when encountered. This will result in expensive repairs and a delay in project delivery that generally supersedes the additional cost had the contractor implemented a robust QC program. A QC program has both advantages and disadvantages. Advantages of quality control a. Develops quality-conscious construction workers, which helps achieve a better product and a satisfied owner. b. Minimizes owner complaints and can result in a repeat client. c. Reduction in construction cost, as the substandard construction quality and consequently rework is reduced. d. Improvement in performance; workers are familiar with the work and avoid the common errors. This will result in reduced inspection costs. e. Updates and changes can be introduced to projects and plans without much difficulty or effort. f. Improves the relationship between employer and employees. Disadvantages of quality control a. Increase in project cost due to: 1. Training workers to better perform tasks related to the project 2. More labor hours/employees are needed to maintain a QC program resulting in added time to the process Quality control (QC) b. Hiring inspectors to oversee the process and perform the ISO 9000 defines quality control as “A part of quality required inspections. management focused on fulfilling quality requirements.” c. It does not encourage all workers to be responsible for While QA concentrates on the process of construction, quality. QC deals mainly with the end or finished product. It ensures In conclusion, a QC program is a reactive approach to that the defects or shortcomings at the construction phase ensure that a constructed project meets the owner’s expecare detected early on so that corrective actions are taken. tations and conforms to the defined standards. Failure to It helps ensure that the owner receives a structure that is detect defective work or material will not prevent rejection usable and functional. Therefore, it is the QC’s manager if a defect is discovered later and does not obligate the A/E responsibility to ensure that the QC plan is implemented for final acceptance. QC is considered as the final checkpoint and followed closely. The QC manager should @Seismicisolation also have before the delivery. @Seismicisolation University of Toronto User. Advantages of quality assurance The benefits of quality assurance are significant: a. Prevents substandard construction as well as errors in construction at early stages; this will save time, money, and effort on reworking faulty workmanship and meeting owner’s expectations. b. Workers understand the importance of quality work, or lack thereof and the consequences associated with it. c. Helps create teamwork within an organization rather than supervision. It is a path for securing a smooth and tranquil end result of a project. d. Builds trust between contractor and owner, providing the contractor an edge over others in a competitive market. Performed after the final product is ready Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. APPENDIX B GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Testing and inspection To ensure that QA and QC programs are properly implemented and performing as planned, testing and inspection of material and of the work must be performed as work progresses by trained and often certified personnel (ACI 563 Mandatory Requirements Checklist) (Example B.1d). It is up to the contractor to ensure and verified by the owner’s testing agency that the certificate of the person performing the work is valid and conforms to the type of test to be performed. The contractor must submit test data, test results, and documentation on proposed repair material to be used per construction contract documents for review and approval by the A/E. These submittals are properly logged, documented, and must remain accessible for the duration of the project. The contractor is permitted to propose alternate repair materials from what was specified by the A/E. The contractor must provide reasons for the substitution, demonstrate compliance of substituted repair materials with the specified performance criteria, and what impact the alternate repair materials may have on the project schedule and overall cost for approval by the A/E. As work progresses, repair materials and operations are tested and inspected to verify that work is being performed in accordance with approved procedures, manufacturer’s instructions, specific instructions from A/E if given, or reference standards cited in contract documents (Section 1.8.1). Accordingly, the contractor must coordinate and schedule with the owner’s testing agency and provide them with minimum 24 hours advance notice before performing tests on specific work to allow ample time for the testing agency for review of project requirements and assigning the appropriate personnel to perform inspection and testing (Section 1.8.2.2(b)). On the day of the testing, the contractor must arrange for safe access to the location where test is to be performed, assist in obtaining and handling samples at the project site, and provide easy access and sources to water and electrical power. ACI 563 Mandatory Checklist table lists minimum tests that must be performed. The A/E may specify additional tests, if needed, to ensure proper installation of the repair material and work (Examples B.1e and B.1f). The owner’s testing agency will report test and inspection results of the work to owner, A/E, contractor, and repair material supplier within 7 days after tests and inspections have been performed (Section 1.8.3.2(c)). After reviewing test results, the owner may choose to verify the test results of proposed concrete mixture, test samples of production materials at plants or stockpiles for compliance with contract documents, collect samples of fresh concrete and test as Example B.1d—Mandatory Requirements Checklist Section/Part/Article 1.8.2.1 Example B.1e—Required tests to be performed per ACI 563 Section/Part/Article 1.8.3.2(a) 1.8.3.3(c) 1.8.3.3(d) 1.8.3.3(e) 1.8.3.3(g) 1.8.3.3(h) 1.8.3.3(i) 1.8.3.4(a) 1.8.3.4(b) 1.8.3.4(c) 1.8.3.4(d) 1.8.4.1 1.8.4.2 1.8.7.1(a) 1.8.7.1(b) 1.8.7.1(c) Tests to be performed by owner’s testing agency Sample and test fresh and hardened repair materials Collect samples of production materials at plants or stockpiles Obtain samples of fresh concrete Concrete strength test Testing proprietary materials Examine completed repairs for cracking and sound repairs Direct-tension bond testing of prepared surfaces and completed repairs Inspect batching, mixing, and delivery operations Inspect forms, foundation preparation, surface preparation, reinforcement placement, and repair material placing, finishing, and curing operations Sample repair material at point of placement and other locations as directed by A/E Review manufacturer’s report for each shipment of repair materials Hardened concrete strength Nondestructive testing Concrete air-content Concrete slump Concrete temperature @Seismicisolation @Seismicisolation University of Toronto User. Notes to Specifier Indicate the required certifications and experience for every repair material, when deemed necessary and possible alternate credentials and experience. Examples of possible field personnel include, but are not limited to: a. ACI Concrete Field Testing Technician - Grade I b. ACI Adhesive Anchor Installation Inspector c. ACI Concrete Construction Special Inspector d. ACI Masonry Field Testing Technician e. CSA-Based Concrete Construction Special Inspector (Canada Only) f. CSA-Based Concrete Field Testing Technician - Grade I (Canada Only) g. ICRI Concrete Surface Repair Technician—Grade 1 h. ICRI Concrete Slab Moisture Testing Technician—Grade 1 i. NACE Coatings Inspector Program, Levels 1 through 3 j. SSPC Concrete Coating Inspector Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 88 indicated in contract documents, or conduct concrete strength test on hardened concrete at no cost to the contractor unless test results by contractor’s testing agency were flawed, did not meet the acceptance criteria specified in the construction contract documents, or both. If test results are found flawed or work is not in compliance with the contract documents, the owner’s testing agency and its representatives do not have the authority to revoke, alter, relax, enlarge, or release requirements of contract documents, nor to accept or reject any portion of work (Section 1.8.3.2(b)). If tested concrete compressive strength did not achieve the specified strength in the contract documents, the contractor is required to verify the actual concrete strength by extracting cores from the work area and test them no earlier than 48 hours after drilling or last wetting and no later than 7 days after the cores were drilled from the structure (Section 1.8.4.3(a)). At least three representative cores should be extracted from each area of in-place concrete that is considered potentially deficient. The A/E determines the location of cores to limit damage to the strength of the structure. If, before testing, cores show evidence of having been 89 damaged after or during removal from the structure, replacement cores should be taken (Section 1.8.4.3(b)). The holes of the extracted cores should be filled with low-slump concrete or mortar of strength equal to or greater than the original concrete by the contractor and provide moist curing for at least 3 days, unless otherwise specified (Section 1.8.4.3(c)). The acceptance criteria for the tested cores is provided in Section 1.8.6 and detailed information is presented in Section 6. Example B.1g elucidates the method for evaluating the concrete cores. ACI 214R and ACI 214.4R provide a method for proper evaluation. Every average of three consecutive strength tests equals or exceeds fc′. Strength of concrete is acceptable if no strength test result falls below fc′ by more than 500 psi (3.5 MPa) when fc′ is 5000 psi (35 MPa) or less, or by more than 0.10 fc′ when fc′ is more than 5000 psi (35 MPa), and average compressive strength of the cores is at least 85 percent of fc′, and no single core is less than 75 percent of the specified compressive strength fc′. Nondestructive in-place tests are not acceptable as the sole basis for accepting or rejecting concrete. The use of the rebound hammer or the pulse-velocity method may be Example B.1f—Required inspection to be performed per ACI 563 Section/Part/Article 1.8.2.2(f) 1.8.2.2(g) 1.8.2.2(h) 1.8.2.2(i) 1.8.2.2(j) 1.8.3.2(a) 1.8.3.4(a) 1.8.3.4(b) 1.8.3.4(e) Inspection to be performed by owner Surface preparation Reinforcement Work in progress to verify that work is being performed in accordance with approved procedures Completed work Bracing and shoring Fresh and hardened repair materials Additional testing and inspection services Batching, mixing, and delivery operations Forms, foundation preparation, surface preparation, reinforcement, embedded items, reinforcement placement, and repair material placing, finishing, and curing operations Testing or inspection operations as required by A/E Acceptable test results Test No. 1 2 3 4 5 Individual cylinders No. 1, psi (MPa) No. 2, psi (MPa) 4110 (28.3) 4260 (29.4) 3840 (26.5) 4080 (28.1) 4420 (30.5) 4450 (30.7) 3670 (25.3) 3820 (26.3) 4620 (31.9) 4570 (31.5) Average test, psi (MPa) 4185 (28.9) 3960 (27.3) 4435 (30.6) 3745 (25.8) 4595 (31.7) Average of three consecutive tests, psi (MPa) — — 4193 (28.9) 4047 (27.9) 4258 (29.4) Average test, psi (MPa) 3585 (24.7) 4015 (27.7) 4040 (27.9) 4780 (33) 3250‡ (22.4) Average of three consecutive tests*, psi (MPa) — — 3880† (26.8) 4278 (29.5) 4023 (27.7) Low test results, not acceptable Test No. 1 2 3 4 5 Individual cylinders No. 1, psi (MPa) No. 2, psi (MPa) 3620 (25) 3550 (24.5) 3970 (27.4) 4060 (28) 4080 (28.1) 4000 (27.6) 4860 (33.5) 4700 (32.4) 3390 (23.4) 3110 (21.4) All cores are above 75 percent of the specified compressive strength greater than 4000 psi (28 MPa) (Section 1.8.6.2). * Average concrete compressive strength of three consecutive cores is low, but above 85 percent of fc′ (Section 1.8.6.2). † @Seismicisolation One test result is more than 500 psi (3.5 MPa) below the specified concrete compressive strength (Section 1.8.6.1(b)). @Seismicisolation ‡ University of Toronto User. Example B.1g—Example of core test results Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. APPENDIX B GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Example B.1h—Decision for approval of repair work ACI 563 Section No. 1.9.1.1 1.9.1.2 Condition Concrete repair work fails to meet one or more requirements of contract documents but if repaired, work is in compliance Concrete repair work to meet one or more project requirements and cannot be brought into compliance permitted by A/E to evaluate uniformity of in-place concrete or to select areas to be cored or tested by other in-place test methods. For additional information, refer to Chapter 6 of this guide. Repair work approval is contingent that completed work is in conformance with the specification and contract documents. ACI 563 Section 1.9 provides criteria for approval of repair work. Example B.1h summarizes those requirements: In case concrete repair work is rejected, the contractor must submit a proposed method, repair material, and modification needed to correct work shortcomings and to satisfy the requirements in the contract documents. Terminology related to concrete repair work is provided in Section 1.3 Decision Accepted Rejected University of Toronto User. as required by ACI 563 Section 2.1.2, signed and sealed calculations by the specialty engineer (Section 2.2.2.2), and shoring layout shop drawings to be reviewed by the A/E. The calculations may specify the construction loads per ASCE 37 if the repair work area is unoccupied and must specify construction loads per ASCE/SEI 7 if the repair work area is occupied. Conservatively, ASCE/SEI 7 may, however, be used for all load conditions irrespective of occupancy status. The specialty engineer must consider the load effects on the structure and parts thereof occurring throughout the duration of the repair work and establish that all loadings supported by the shoring and bracing system are safe. The shoring layout shop drawings must show the arrangement of equipment for shoring, inclusive of installation Section 2—Shoring and bracing details, maintenance requirements, and permitted changes. ACI 347R defines shoring as the vertical or inclined The contractor must submit sequencing requirements of support member or braced frame designed to carry the shoring installation and removal, concrete removals, surface weight of the formwork, concrete, and construction loads, preparation, repair installation, curing, and minimum and defines bracing as a structural member used to provide concrete strength at removal for A/E’s approval. lateral support for another member, generally for the purpose Per ACI 563 Section 2.2, the specialty engineer can select of ensuring stability or resisting lateral loads. the shoring system that provides economy, safety, and reliShoring and bracing provide support to beams and floors ability to a project. The shoring system can be manufacin a building to prevent collapse if a beam, column, or wall is tured pre-engineered components where manufacturers of removed, or if the structure’s vertical framing system, lateral shoring equipment develop descriptive literature and strucframing system, or both, have been compromised. Theretural performance data that helps the specialty engineer in fore, this requires careful attention and planning by the A/E the design of the shoring system (Example B.2a). It also by clearly identifying the shortcomings in the existing strucprovides installation procedures and safety data that helps ture, what modifications will occur, and which members will the contractor in the installation and removal of the shoring be removed or altered. ACI 563 Section 2.1.1.1 places the system per the manufacturer’s requirement (Section 2.2.2.3). responsibility of design, installation, stability, and removal of The specialty engineer may select to design the shoring shoring and bracing on the contractor’s engineer or a specialty system that are not a premanufactured system. engineer hired by the contractor. Therefore, it is prudent that Irrespective of what system the specialty engineer selects, the specialty engineer interacts with the A/E to understand the the calculations must be prepared following the state, local, structural behavior of the system, what will be removed and and federal codes; ordinances; and regulations pertaining to when, and what will be added to the existing structure. shoring and bracing. The specialty engineer must consider The specialty engineer must consider the deficiencies when designing and preparing the shoring shop drawings within the structure and unsafe structural conditions, if design and layout following safety requirements by the present, including the effect of loads and deflection requireSafety and Health Regulations for Construction, Standard ments during repair, and must consider the effects of compat-29 CFR (2020). ibility of deformations on the shoring system and supported The installation and removal must be in accordance with and supporting structural members while maintaining stability the sequencing shown in the shop drawings and reviewed by of the structure and structural members when designing the the A/E. This information must be complete, accurate, and shoring and bracing systems. Must also consider redistribuclearly stated. As part of the QA/QC program, the contractor tion of forces in the structure as a result of member removal or must submit documentation of inspections and certifications addition and deformation of a member. A member may require required from specialty engineer as specified by 2.1.2.1(d). jacking during repair to restore its levelness or to remove a The specialty engineer must inspect the shoring and supporting member. The specialty engineer must account for temporary bracing before the start of the repair/strengththis jacking load and its effect on the existing concrete strucening work and at appropriate intervals throughout the ture and shoring (Section 2.1.1.2(a)). process, and certify that they, as installed, meet the intent As part of the QA program, the specialty engineer must of the design. During construction and per ACI 563 Section take into consideration the safety of the structure and submit, @Seismicisolation 2.3, the contractor must survey the shoring elevation and @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 90 91 Example B.2a Minimum information furnished by the preengineered manufacturer shoring manufacturer may provide the following list: a. Provide education and training related to the product b. Implied warrantees to the end user (contractor) when equipment is selected, installed, and used properly by the contractor’s competent person: i. Application guide ii. Tabulated data (structural limitations) iii. Assembly instructions iv. Installation sequence v. Identify safety issues vi. Maintenance and repair Fig. B.2a—Shoring of beams at Norristown, PA, Main Street parking garage in Montgomery County (photo courtesy of Superior Scaffolding Services). stability to ensure that the shores did not move or displace due to construction activities. If such movement or displacement occurs, the contractor must stop the work in the area and adjust the shores/bracing and inspect shoring and temporary bracing before the repair process commences again. The contractor can remove erected shoring or bracing when repair or strengthening work is complete, added new materials have attained the specified strength, and existing members work together to support the applied loads. University of Toronto User. Section 3—Concrete removal and preparation for repair This chapter covers the partial removal of concrete for repair and preparation of substrate to receive repair material. Fig. B.2b—Bracing of columns at Harvard Towers Parking Proper surface preparation of existing concrete is essential Garage, Cambridge, MA (photo courtesy of Simpson for achieving a successful project (ACI 515.3R). Therefore, Gumpertz & Heger). before any concrete removal work begins, it is recommended that the A/E, contractor, and owner hold a preconstruction coating with limited thickness (thin), a smoother CSP of 2 meeting; refer to Section 1, Preinstallation conference, of to 4 is appropriate. When using thicker self-leveling and this Appendix. In the preinstallation conference, one of the polymer overlays, the appropriate CSP will range from 4 to issues that the parties involved will address is the means 6 (Fig. B.3b). proposed to achieve the recommended concrete surface There are several methods that can be used for surface profile (CSP); the equipment the contractor is proposing to preparation. The main goal, however, is to minimize damage use on the job to achieve the CSP; and the methods planned to the existing structure. An effective method for concrete to remove the debris, laitance, and bond-inhibiting material removal, however, may not be effective or appropriate for to achieve the suggested bond between the existing substrate a specific surface preparation requirement. For example, and the new overlay as directed by the A/E in the contract some concrete removal methods leave the concrete surface documents. In the meeting, the method and frequency of too rough or irregular for the intended repair material such testing the bond strength between the existing substrate and as membrane coatings. In these cases, removal methods the new overlay should also be discussed. specifically intended for the final surface preparation may ICRI developed a concrete surface profile (CSP) (310.2R) be required. Therefore, in the preinstallation conference/ system to measure the acquired roughness of the repaired meeting, the contractor should present the means and concrete surface. The CSPs are rated from 1 to 10; with 1 methods proposed for concrete removal such that damage to being the smoothest, nearly flat, and 10 being the roughest, the structure and bruised surfaces on the concrete substrate is close to 1/4 in. (6 mm) amplitude (Fig. B.3a). These clasminimized (3.2.1.1). The equipment proposed for use should sifications are accepted industry criteria to help guide the be selected based on the area of concrete to be removed, contractor verify the proper texture achieved for successful the orientation of the member, its suitability to produce the bonding of the overlay or coating. Generally, when using required CSP, and the capacity of the structural member that a thick overlay, the CSP needs to be higher. When @Seismicisolation using a will support the equipment. @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. APPENDIX B GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES ACI 563 Section 3.2.1 does not restrict the contractor to a specific method for the removal and roughening of the concrete substrate. ACI 563 lists several methods for concrete removal, including concrete breakers (Section 3.2.1.3); hydrodemolition (Section 3.2.1.4); and scarifying, scabbling, and milling/rotomilling (Section 3.2.1.5). Each of the listed methods has its advantages and shortcomings that should be considered before implementing such a method. Concrete breakers vary in size, weight, and type of tip based on the application and type of structure. It depends on the level of concrete surface preparation whether it is partial or full-depth concrete removal. To minimize bruising to the concrete surface in partial depth removal, the contractor should use sharp tips on breaker equipment (Section 3.2.1.3). This will dictate the size and weight of the equipment to be used. In general, for handheld concrete breakers, the Fig. B.3a—Concrete surface profiles (image courtesy of Graco Contractor). Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 92 University of Toronto User. Fig. B.3b—Possible surface profiles to be used with various protective systems (image courtesy of ICRI 310.2R). @Seismicisolation @Seismicisolation Fig. B.3c—Handheld concrete breaker chipping concrete cover off brick wall. a. Roughened surface to 1/4 in. (6 mm) amplitude with aggregate undamaged 93 Fig. B.3d—Hydrodemolition of concrete wall (image courtesy of CVM). b. Machined roughened surface 1/4 in. (6 mm) amplitude with aggregates cut through Fig. B.3e—Roughened concrete surface. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. APPENDIX B University of Toronto User. Fig. B.3f—Roughening concrete surface using scarifier (image courtesy of ConcreteHire). recommended weight should be limited to 15 lb (6.8 kg) When using the hydrodemolition method, the contractor equipment (Fig. B.3c). must address how water is collected or providing runoffs. Hydrodemolition uses high-pressure water to break and Scarifiers, also called surface planers or milling machines, remove concrete (Fig. B.3d). Unsound concrete can be remove concrete faster and more aggressively than grinders quickly and efficiently removed creating a highly rough and (Fig. B.3f). Equipment choices range from small handheld bondable surface. Concrete that is still sound is left ready units with 2 to 3 in. (50 to 75 mm) cutting widths to manual to be bonded with a new surface (Fig. B.3e). Concrete that push or self-propelled walk-behind machines with working has become delaminated or contaminated by chloride can paths of 4 to 16 in. (100 to 400 mm). Cutting depths are be removed, leaving behind concrete that still has@Seismicisolation integrity. adjustable on most machines, with some models achieving @Seismicisolation GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. B.3h—Concrete surface roughening using rotomilling (image courtesy of NovaPave). Fig. B.3g—Scabbler on concrete (image courtesy of TrelawnySPT). up to 1/4 in. (6 mm) of material removal in one pass. A scarifier generally leaves behind a rough finish and may create ridges in the concrete. On jobs where a smoother finish is required, the contractor needs to grind the surface after scarifying. Scabbling is a technique that involves applying cutting heads powered by pistons to the substrate at right angles to remove rigid coatings and deteriorated concrete that is less than 1/4 in. (6 mm) in thickness (Fig. B.3g). The resulting surface texture ranges from CSP 7 to CSP 9. Scabbling can cause microcracks in the concrete that negatively affects the ability of the substrate to bond with a new surface. Contractors usually combine this method with either abrasive blasting, high-pressure water blasting, or shotblasting to improve bond. Both milling and rotomilling can remove the thickest surfaces for the most involved surface preparation project (Fig. B.3h). This method results in a coarse, fractured aggregate surface that is usually CSP 9, the highest measure of texture on the CSP scale. Because this process involves heavy machinery and a high level of impact, it is only used in limited cases. The A/E may specify in the contract documents to the contractor to produce a mockup of the work so that the owner, contractor, and A/E can agree on repair procedure, quality of repairs, and the post-repair aesthetics before starting the repair program. This step will reduce unrealistic expectations as to the performance and appearance of the repair areas (Section 3.1.3.2). Mockups are usually a sample of the work performed on a limited area of the repair project with the proposed equipment and material. Field testing mockups of selected removal techniques can help determine the best procedures to use for the repair. The contractor will check the validity of removing the debris, laitance, and other loose material before applying the overlay (Section 3.2.2) and notify the A/E before beginning concrete removal and surface Section 4—Formwork preparation per the contract documents (Section 3.3.2.1). ACI 563 Chapter 4 covers the design, construction, The specifications require the contractor to follow the and treatment of formwork to support, confine, and shape Contract Document requirements when it comes to the @Seismicisolation area repair materials to required dimensions. ACI 347R defines @Seismicisolation University of Toronto User. and depth of concrete removal unless the contractor comes across additional delamination or fractured or unsound concrete in adjacent areas, in which case the contractor must notify the A/E for direction (Section 3.3.2.2). The contractor should avoid directly striking reinforcement with impact tools used for concrete removal so as not to damage and jeopardize the structural integrity of the member (Section 3.3.2.2(a)). ACI 563 directs the contractor to provide perpendicular edges and avoid reentrant corners at the perimeter of the repair area, saw cut to a depth of 0.50 to 0.75 in. (12 to 20 mm), and must ensure not to cut or damage embedded reinforcement or other embedded items, obtaining uniformity of depth (Section 3.3.2.2(b)) (Fig. B.3i). Assessments performed onsite are critical at this stage of a repair project. Contractors must often perform inspections to identify cracked, delaminated, spalled, disintegrated, and otherwise unsound concrete for removal. If embedded reinforcing bars or other embedded items are too close to the surface to provide the perpendicular edge cut, the contractor must notify the A/E for direction before proceeding (Section 3.3.2.2(b)). Methods listed in ACI 563 Section 3.2.2 for cleaning concrete surface and reinforcement are abrasives and shotblasting, compressed air, high- and ultra-high-pressure water jetting, low-pressure water cleaning, and vacuum approaches. All equipment must be operated so not to damage reinforcing bar, other embedded items, or adjacent concrete. It is important for the contractor to ensure that the completed work satisfies the requirements of the contract documents by performing the pull-off test to measure the bond strength between the existing substrate and the new overlay (Fig. B.3j). This test is usually done at the mockup level so that adjustments to the work can be done before fullscale construction and after completion of the work (Section 3.1.3) (refer to Example 7-2 of this guide). Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 94 Fig. B.3i—Preferred sawcut perimeter with few reentrant corners. 95 Fig. B.3j—Pull-off test. University of Toronto User. a. Shop drawings for engineered-designed formwork signed formwork as the total system of support for freshly placed and sealed by a specialty engineer (Section 4.1.2.2(a)) concrete, including the mold or sheathing that contacts the b. Design calculations for engineered design formwork, concrete as well as supporting members, hardware, and shoring, reshoring, and backshoring signed and sealed by necessary bracing. specialty engineer (Section 4.1.2.2(b)) The cost of formwork can comprise most of the repair work c. Manufacturer’s product data sheet for form ties and cost. This investment requires planning by the A/E when anchors to existing concrete (Section 4.1.2.2(c)) designing and specifying the structure and by the specialty d. Product data sheet for expansion joint materials (Section engineer when designing and constructing the formwork. 4.1.2.2(d)) Hence, it is imperative that the Contactor and specialty engie. Product data sheet for waterstop materials and splices neer work closely together on the design of formwork and (Section 4.1.2.2(e)) shoring. The layout, design, and construction of formwork Section 4.2 specifies products requirements for formwork should be the responsibility of the specialty engineer. This material, location of construction, expansion, and contracis fundamental to the achievement of safe and economical tion joints, and type of form-facing materials required to formwork design and of the required formed surface quality produce the required appearance and texture. If the design or of the concrete. Some of the items that the contract docudesired finish requires special attention, the A/E can specify ments should consider and clarify are: in the contract documents the formwork materials and any a. Who will design the formwork? other feature necessary to attain the objectives. b. Who will design shoring and the reshoring system? Hence, all formwork should be well planned before c. Who will inspect the specific features of formwork and construction begins, designed for strength and serviceability, when will the inspection be performed? and investigated for system stability and member buckling. d. What reviews, approvals, or both, will be required for: The safety of formwork is particularly significant in formi. Formwork drawings, calculations, or both work construction because it supports concrete during its ii. Post-tensioning support plastic state and until concrete becomes structurally selfiii. Reshoring design supporting. In addition to the adequacy of the formwork, iv. Formwork preplacement inspection special structures require consideration of the behavior of e. Who will give such reviews, approvals, or both? existing structural members that are used to support formACI 563 Chapter 4 is divided into three sections; General, work and other construction loads. Although the safety Products, and Execution. In Section 4.1.2, the specification of formwork is the responsibility of the contractor, the directs the Contactor to submit as a minimum the following: A/E should review the formwork, including drawings and a. Form-facing material if different from what is specified in calculations by including this requirement in the contract 4.2.1.1 and 4.1.2.1(a) documents. Formwork for unusually complicated strucb. Construction and contraction joint layout if different from tures, structures whose designs were based on a particular the contract documents (Section 4.1.2.1(b)) method of construction, structures in which the forms impart c. Testing for formwork removal if methods other than fielda desired architectural finish, certain post-tensioned struccured cylinders is proposed (Section 4.1.2.1(c)) tures, folded plates, thin shells, or long-span roof structure d. Shoring and backshoring procedure, including drawmust receive special attention by the A/E during the review ings signed and sealed by a specialty engineer (Section process. 4.1.2.1(d)) When designing formwork and shoring, the Specialty Engie. Data on formwork release agent or form liner proposed for neer should follow all state, local, and federal codes, ordiuse with each formed surface (Section 4.1.2.1(e)) nances, and regulations pertaining to forming and shoring Section 4.1.2 further compels the Contactor to submit the before submitting the signed and sealed calculations and shop following information before installing shoring or formwork: @Seismicisolation drawings to A/E for review. The design calculations should @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. APPENDIX B GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES show that formwork can withstand the repair material pressures, pressure resulting from placement, and consolidation procedures to maintain specified tolerances (Section 4.2.2.2). ACI 563 Section 4.2.2.3 does not allow for use of earth cuts as forms for vertical and sloping surfaces and limits the deflection of exposed repair material surface to view to 1/240 of span between structural members of formwork. Section 4.3, Execution, covers construction and erection of formwork, removal of formwork, and strength of repaired material required for formwork removal. The contractor should, before placement of cementitious repair material, inspect the formwork to ensure that the erected formwork is watertight to prevent any leakage of the repair material that may adversely affect strength and appearance of final product. Also, the contractor should ensure that there are no loose or deleterious material within the formwork that may affect the final appearance and quality of the concrete surface (Section 4.3.1.3). If the A/E does not call for specific materials or accessories, the Specialty Engineer can choose any materials that meet the contract requirements. The specification, however, specifies a minimum of, Class B for surfaces exposed to view and Class D for concrete surfaces that will be permanently concealed (Section 4.3.1.5 and Example B.4a). The A/E should specify the tolerances so that the contractor will know precisely what is required and can compensate for deflections and anticipated settlements in formwork during concrete placement. It should be noted that tolerances normally found in construction specifications, such as those in ACI 117, are for the as-built concrete members and not the formwork used to shape these members. Therefore, formwork should be constructed with such dimensions so the resulting concrete members are within the specified dimensional tolerances (Fig. B.4a). The contractor should set and maintain concrete forms, including any specified camber, to ensure completed work is within the tolerance limits (Section 4.3.1.7). Wedges are typically used for final alignment before repair material placement and telltale devices are installed on shores or forms to stabilize and secure the erected formwork in position before the final check and to detect formwork movements during concrete placement. Formwork should be anchored to the shores below so that undesired movement of any part of the formwork system is prevented during concrete placement. Such anchoring and bracing should be installed in such a way as to allow for anticipated take-up, settlement, or deflection of the formwork members (Sections 4.3.1.8 and 4.3.1.9). After securing the formwork in place and before repair material placement, the contractor should ensure that the formwork surfaces and embedded objects are clean from all foreign material and formwork surfaces are sprayed with the approved material that prevents bond with the repair material (Sections 4.3.1.14 and 4.3.1.15). Formwork can be removed when the repair cementitious material has attained the minimum strength to support its self-weight and will not result in damage to the repair material (Sections 4.3.2.1). If the repaired member, however, will support construction loads, then formwork should remain until concrete has attained the specified compressive strength in the contract documents and verified by testing specimens field cured in the same manner as repair material they represent (4.3.2.5 and 4.3.4.1). All repaired surfaces must be true and even, free of open or rough spaces, depressions, or projections. Immediately after the removal of forms, all bulges, fins, form marks, or other irregularities that, in the judgment of the A/E, will adversely affect the appearance or function of the structure Class of surface A 1/8 in. (3 mm) B 1/4 in. (6 mm) C 1/2 in. (13 mm) D 1 in. (25 mm) Example B.4b Concrete surface category (CSC) levels (ACI 117) are specified for individual parts of the structure to reflect the Owner’s needs, desires, and budget. Possible examples include: • Basement walls: CSC1 • Industrial structures: CSC1 or CSC2 • Electrical and mechanical rooms: CSC1 or CSC2 • Stairwells: CSC1, CSC2, or CSC3 • Commercial building exteriors: CSC3 • High-end commercial building exteriors: CSC3 or CSC4 • Religious structures or museums: CSC3 or CSC4 • Monumental or landmark structures: CSC4 where: CSC1 is for concrete surfaces in areas with low visibility or of limited importance CSC2 is for concrete surfaces where visual appearance is of moderate importance CSC3 is for concrete surfaces that are in public view or where appearance is important CSC4 is for concrete surfaces where the exposed concrete is a prominent feature of the completed structure or visual appearance is important @Seismicisolation @Seismicisolation University of Toronto User. Example B.4a—Permitted abrupt or gradual irregularities in formed surfaces as measured within a 5 ft (1.5 m) length with a straightedge Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 96 Fig. B.4a—Formwork for beam cross section enlargement (image courtesy of Pullman, A Structural Technologies Company). must be removed. All form bolts and ties must be removed to a minimum depth of 1 in. (25 mm) below the surface of the repair. The cavities produced by form ties and all other holes of similar size and depth must be thoroughly cleaned. Holes resulting from form bolts or straps that pass through the wall must be entirely filled with mortar to form a dense, well-bonded unit. ACI 347.3R defines four quality levels of formed concrete surfaces and provides methods to achieve and evaluate them (Example B.4b). These quality levels are identified by three surface finish categories: 1) form facing; 2) concrete surface void ratio; and 3) characteristics of formfacing materials (Fig. B.4b). 97 Fig. B.4b—General view of formed repaired surface with unacceptable number of voids. University of Toronto User. using normal handling tools and machines, such as slings, are usually acceptable and must be kept off ground and, if stored outdoors, then they must be covered. Epoxy-coated bars, however, require additional precaution to protect the coating from damage due to collision or dragging. Some of measures that the contractor can take are by using bare chains and cables, using spreader bars or strong backs with multiple pick-up points to minimize sagging, using synthetic slings to reduce damage to coating, and placing wood and plastic between bars when shipping. Epoxy-coated bars should be stored off ground on timber cribbing or wooden boards Section 5—Reinforcement and reinforcement and should remain from mud, debris, and other deleterious supports material. Other requirements apply to other types of bars, ACI 563 Section 5, Reinforcement and reinforcement such as stainless steel bars or galvanized bars, but irrespecsupports, covers material selection by specifying the grade tive of the type, bars should be stored elevated from the of bars determining its yield strength, ultimate strength, ground and stored indoors or under cover to protect them chemical composition, and percentage of elongation. It also from the elements (Section 5.1.3.2 and Example B.5). covers fabrication tolerances, proper placement of the bars The contractor must comply with the reinforcement in the right place, maintaining tolerances of new steel reingrades, types, and sizes as indicated in the contract docuforcement and reinforcement supports, and methods acceptments. Each bar requires identification marks to be rolled able for repair of existing reinforcement to remain. into the surface of one of its sides (Section 5.2.1.1) The contractor is required to submit bar data and bar place(Fig. B.5b). If welding is required, then the contractor must ment drawings of reinforcement for approval by the A/E follow the requirements of AWS D1.4/D1.4M. (Section 5.1.2). The data are in the form of manufacturer’s ACI 563 Section 5.3 covers the execution work of certified test report, which accompanies each shipment of preparing, placing, cutting, field bending and straightening, reinforcing bars. The mill reports certify that the reinforcing and preheating of bars. New and existing bars must be free bar conforms to the project specifications and reveals the of contaminants deleterious to the bond and existing bars chemical composition of the reinforcing bar and mechanical must have minimum deformation for proper bonding, otherproperties (Fig. B.5a). The drawings should also include wise the contractor must inform the A/E on the status of length and location of splices. If mechanical splices are used existing reinforcement for any modifications to the original on the job, the contractor must submit type and coating of design (Section 5.3.2.2). To maintain the specified cover of sleeves, bolts, and nuts for approval (Sections 5.1.2.1(b) the bars required by the contract documents, the contractor through (d)). The submitted placement drawings should also must provide supports or what is normally termed “chairs.” include request for field cutting if required, including locaPlacing reinforcement in the right place and keeping it tion and type of bar to be cut and reason for the field cutting there during concrete placement is critical to the structure’s (Section 5.1.2.1(h)). performance (Section 5.3.3.3). Placing bars on supports, The contractor must properly handle and store reinforcehowever, is not enough. Bars must be secured in place to ment and protect it from soil, petroleum products, or other prevent displacement during construction activities and materials that will inhibit its bond to concrete (Section concrete placement. This is usually accomplished with tie 5.1.3.1). There are different ways of handling and storing wires. For epoxy-coated bars, PVC or similar ties are usually bars, depending on type. For example, typical black bars, used (Fig. B.5c(a) and (b)). @Seismicisolation @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. APPENDIX B GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Sometimes it is necessary to move or relocate new reinforcement beyond the specified placing tolerances to avoid interference with existing reinforcement, conduits, or embedded items. The contractor must submit a proposed plan for the alternate spacing to the A/E to approve the relocation of new bars beyond the placement tolerances (Section 5.3.3.2). The contractor is permitted to bend or straighten reinforcing steel bars partially embedded in concrete in the field. Bar sizes No. 3 through 5 may be cold bent the first time, provided bar temperature is above 32°F (0°C) (Section 5.3.3.8). For other bar sizes, bars must be preheated before bending or straightening. Heat is applied such that it does not harm bar material or cause damage to concrete. The minimum preheat length is usually five bar diameters in each direction from center of bend provided preheating is not extended below the concrete surface. Maintain bar preheat temperature of 500°F (260°C) at concrete interface and between 1100 and 1200°F (593 and 649°C) away from concrete until bending or straightening is complete. Allow bar to cool down slowly. Artificial cooling methods can be used when bar temperature falls below 600°F (316°C) (Section 5.3.3.8(a)). This method is consistent with ACI 301 Section 3.2.2.8. ACI 318 Section 26.6.3.2, however, does not allow bending unless shown in the construction documents or permitted by the A/E. The commentary in ACI 318 further elaborates that tests have shown that ASTM A615 Grade 40 and 60 bars can be cold bent and straightened up to 90 degrees, provided the minimum diameter provided in Section 25.3 is maintained. ACI 318 Section 26.6.3.2 further explains that heating of bars up to 1500°F may be necessary if cracking or breakage is encountered and bars should be spliced outside the bend region. Field-bending or straight- Example B.5—Simple steps save time and effort (ACI 347R): a.Order the reinforcing bar with the construction schedule in mind. b. When reinforcing bar is delivered to the site, check the shipping list or manifest, dray ticket, or loading sheet as each bundle is unloaded. c.Save time by hoisting the bundles of bars directly from the truck to the area on the structure where the bars are going to be placed. d. Put bundles in an area with easy access for rehandling. Make sure the reinforcing bar is placed on timbers to keep it away from or standing water. e. Keep stockpiles orderly. Straight bars are usually stored by sizes and by lengths for easy identification. Stockpile similar bent bars together. f. Make sure all bar tags are at the same end for quick identification. When bars are removed, make sure the bar tag stays with the bundle and does not get lost. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 98 University of Toronto User. Fig. B.5a—Sample of certified mill test report (image courtesy of CRSI). @Seismicisolation @Seismicisolation ening of zinc-coated (galvanized) or epoxy-coated bars is permissible, but damage to coating must be repaired. Section 6—Conventional concrete mixtures ACI 563 Chapter 6, Conventional concrete mixtures, covers the requirements for materials, proportioning, producing, and delivery of concrete prepared from constituent materials. The A/E conveys those requirements through the contract documents in the form of specifications to the contractor to perform the work as intended. The A/E should be aware that specifications for concrete mixtures can be either prescriptive or performance-based. When prescriptive specifications are used, the A/E assumes responsibility for the prescribed materials and process to meet the performance requirements by including clauses for means and methods (Example B.6). Performance specifications, on the other hand, are a set of instructions that address requirements for mechanical and functional properties of the concrete. This method requires the designer to clearly specify the test methods that are needed to be performed, ensure that the specified requirements are achievable by the method the contractor chooses, and that the specified requirements are measurable and enforceable, satisfying the relevant testing standards. Performance-based specification puts the respon- sibility on the contractor to achieve the requirements specified in the contract documents. ACI 563 requires the contractor to submit to the A/E concrete mixture proportions and characteristics, field test records used to establish the required average compressive strength, and documentation indicating that the proposed concrete proportions will produce an average compressive strength equal to or greater than the specified average compressive strength (Section 6.1.2). For a repair job, the contractor must submit data on concrete materials per specified ASTM standards—that is, cementitious material type, aggregates, water and ice source, and admixtures. As part of the QC program, the A/E must maintain records verifying that materials used are the specified and accepted types and sizes and are in conformance with the requirements of Section 6.2.1, while the contractor must ensure that concrete production and delivery conform to the corresponding ASTM standards. If the contractor proposes changes of one or more of the materials used in a mixture design, new field data, data from new trial mixtures, or other evidence must be submitted to the A/E for approval that the change will not adversely affect the relevant properties of the concrete before changes are made. When concrete is mixed at the job site, the contractor should store cementitious material and other material related (a) Chair supporting a bar. Note: bar not post- (b) Chair supporting a bar and strands. Strands are tensioning tied to chair. tied to chair, while bar is not yet. @Seismicisolation @Seismicisolation University of Toronto User. Fig. B.5b—Bar identification (image courtesy of CRSI). Fig. B.5c—Typical bar chairs. 99 Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. APPENDIX B GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES University of Toronto User. Section 6.2.2 directs the contractor to ensure that the cementitious material content is adequate to satisfy the specified Sections with dimension h Temperature in 24 hours requirements for strength, water-cementitious materials ratio a. < 12 in. (300 mm) 50°F (10°C) (w/cm), durability, finishability, and placement constraints of b. 12 in. (300 mm) ≤ h < 36 in. (900 mm) 40°F (4°C) the project. The specification permits the contractor to lower c. 36 in. (900 mm) ≤ h < 72 in. (1800 mm) 30°F (–1°C) the cementitious material content contingent upon verificad. h ≥ 72 in. (1800 mm) 20°F (–7°C) tion that concrete mixtures with lower cementitious material content will meet the specified strength requirements and will produce concrete with equal finish quality, appearance, durability, surface hardness, and placeability. The contractor must Example B.6—Prescriptive specification submit a history of the proposed modified mixture design or, for an interior reinforced concrete building by evaluating the proposed mixture, by placing concrete in a beam representative location at the project site using project mateConcrete shall be a minimum of 4000 psi (28 MPa) rials, equipment, and personnel. concrete compressive strength with a maximum Section 6.2.2.5 sets limitations on the maximum delivw/cm of 0.4 and a minimum cement content of ered concrete temperature of 95°F (35°C), unless the A/E 3 3 600 lb/yd (9611 kg/m ), a maximum fly ash content specifies a different temperature when placing concrete. If of 10 percent by mass of cementitious material, and the ambient temperature from midnight to the following a maximum slump of 4 in. (100 mm). midnight is expected to be less than 40°F (4°C) for more Discussion: than three successive days, concrete should be delivered to The concrete compressive strength, 4000 psi meet the minimum temperatures noted in Table B.6 immedi(28 MPa), is the critical characteristic in this ately after placement. prescriptive specification. The beam is protected Durability—Architect/Engineers strive to design from exposure; therefore, the low w/cm limit is concrete that is durable and can withstand extreme envinot required for durability. Listing the minimum ronmental conditions without deterioration or damage. cementitious content is not necessary to meet Therefore, properly designed, proportioned, transported, strength requirements. Limiting fly ash content to placed, finished, and cured concrete can provide decades 10 percent is possibly to ensure rapid strength gain of service with little or no maintenance; however, certain for form stripping, which is an issue of means and conditions or environments exist that can lead to premature methods of construction and should not be included concrete deterioration. There are various factors that influin the specification. ence the durability of concrete and should be considered in In addition, the specification is in contradiction in the context of the environmental exposure of the concrete. requesting 4000 psi (28 MPa) concrete compresThe specification sets durability requirements such as sive strength with low w/cm (0.4). sulfate resistance, freezing-and-thawing resistance, low permeability, corrosion protection of reinforcement, and shrinkage limits to protect concrete from such exposures. For example, it is essential that concrete of an exposed reinforced concrete bridge girder resists water and chloride and other chemical migration for its longevity and proper service (Fig. B.6). Use of fibers—The use of steel fibers and macrosynthetic fiber-reinforced concrete must be based on fiber-reinforced concrete’s flexural performance requirements as indicated in the contract documents when tested and calculated in accordance with ASTM C1609/1609M, ASTM C1399/C1399M, or ASTM C1550 (Sections 6.2.2.8 and 6.2.2.9). Proportioning—Section 6.2.3 provides direction to the contractor to analyze statistically existing data of field test records within the past 12 months and that span no less than 60 days for a class of concrete within 1000 psi (7 MPa) of Fig. B.6—Bridge girder damage due to chemical migration that specified in the contract documents to justify its use. (image courtesy of Helpiks). When test data are not available, the contractor must provide to the concrete mixture in a dry place, protecting them from data form trial mixtures using the specified material requiregetting contaminated. In addition, aggregates should be ments in the contract documents (Section 6.2.3.1). stored and handled in a way to prevent segregation and avoid Execution—Durable concrete is not obtained by using mixing with other materials or other sizes of aggregates and good materials and proper mixture proportioning alone, but to protect stored admixtures against evaporation or damage also by appropriate placement practices and workmanship (Section 6.1.4). @Seismicisolation that are essential to the production of durable concrete. @Seismicisolation Table B.6—Minimum concrete temperature immediately after placement Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 100 Section 6.3 provides direction to the contractor for the mixing and placement of concrete when concrete is readymixed or site-produced. Sections 6.3.2.1 and 6.3.2.2 direct the contractor when and how to adjust the slump and what measurements to take when the maximum concrete discharge time, drum revolution, or both, have exceeded the requirements set in ASTM C94/C94M. 101 Example B.7—Surface finish criteria Surface Finish-1.0 (SF-1.0) a. No formwork facing material is specified b. Patch voids larger than 1-1/2 in. (38 mm) wide or 1/2 in. (13 mm) deep c. Remove projections larger than 1 in. (25 mm) d. Tie holes need not be patched e. Surface tolerance Class D as specified in ACI 117 f. Mockup not required University of Toronto User. Section 7—Handling and placing of conventional concrete Section 7 covers the handling and placing of cast-in-place and precast concrete, and localized partial-depth concrete repairs. The requirements for handling and placing of concrete on a repair project are identical to the conventional placeSurface Finish-2.0 (SF-2.0) ment of concrete. Therefore, this section will not cover a. Patch voids larger than 3/4 in. (20 mm) wide or these requirements in detail. The contractor, however, must 1/2 in. (13 mm) deep still submit data to the A/E for approval (Section 7.1.2.1(a) b. Remove projections larger than 1/4 in. (6 mm) through (f)), such as field control test data; qualifications c. Patch tie holes of finishers; shop drawings of placing, handling, and d. Surface tolerance Class B as specified in ACI construction methods and data; placement notifications; 117 and preplacement requirements. The contractor must also e. Unless otherwise specified, provide mockup of submit data to the A/E on the conveying equipment type to concrete surface appearance and texture be used on the repair job and proposed methods for removal of stains, rust, efflorescence, and surface deposits (Section Surface Finish-3.0 (SF-3.0) 7.1.2.2). Also, data must be submitted to the A/E when the a. Patch voids larger than 3/4 in. (20 mm) wide or contractor proposes alternatives, such as construction and 1/2 in. (13 mm) deep contraction or expansion joint locations and layout, underb. Remove projections larger than 1/8 in. (3 mm) water placement, initial and final curing methods, and c. Patch tie holes coated ties. d. Surface tolerance Class A as specified in ACI Products—Section 7.2 specifies the material that should 117 be used on a repair job. For example, water when used for e. Provide mockup of concrete surface appearcuring must be potable (Section 7.2.1.1). Seawater or water ance and texture containing contaminants that may discolor concrete is prohibited (Fig. B.7). Membrane-forming curing compounds that conform to ASTM C309 or ASTM C1315 are acceptable except for silica-based liquid surface densifiers that are prohibited from use (Section 7.2.1.2). Execution—Section 7.3 covers the actual concrete work such as preparation, placement, and curing of concrete, finishing formed surfaces, finishing unformed surfaces, sawed joints, curing and protection, and repair of surface defects. It provides a road map for the contractor to perform the work, requiring the contractor to complete the following tasks before placing concrete in forms or against prepared concrete (Section 7.3.1.2): a. Comply with surface preparation requirements in Section 3. b. If formwork is used, comply with formwork requirements Fig. B.7—Concrete discoloration due to curing with contamspecified in Section 4. inated water. c. Remove snow, ice, frost, water, and other foreign materials, if present, from surfaces against which concrete will be placed, and from reinforcement and embedded items. The specification directs the contractor to take precautions d. Comply with reinforcement placement requirements specwhen placing concrete in wet, cold, or hot weather. Additional ified in Section 5; position and secure in-place expansion precautions should be taken by maintaining minimum and joint materials, anchors, and other embedded items. maximum reinforcement, embedded material, and formwork e. Provide properly conditioned concrete surface substrate as surface temperatures that will be in contact with concrete for indicated in contract documents in Section 3. @Seismicisolation cold and hot weather concrete placement (Section 7.3.2.1). @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. APPENDIX B GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Section 7.3.3 lists the acceptable surface finishes of placed concrete (Example B.7). Section 7.3.7 provides direction to the contractor for repairing surface defects. Sections 9 and 10 These two chapters incorporate two other standards into this standard by reference: ACI 503.7, “Specification for Crack Repair by Epoxy Injection,” and ACI 506.2, “Specification for Shotcrete.” Notes to Specifier (nonmandatory) ACI 563-18 lists nonmandatory Notes to the Specifier. Those notes are provided to help the A/E determine how to use ACI 563 in a project Contract Document. It advises the A/E to reference or incorporate the reference specification in its entirety in the project specification (Example B.NS). Copying sections, parts, or paragraphs into the project specification may take them out of context or may change their meaning. It also directs the A/E to determine which standard controls when two standards are referenced in the project document that are in conflict. The Notes to the Specifier include two checklists for the A/E to use in incorporating ACI 563 into the concrete specification. The first of these checklists, the Mandatory Requirements Checklist, indicates specific qualities, procedures, and performance criteria that the specifier must define in a project specification. The second, the Optional Requirements Checklist, identifies choices and alternatives that the specifier can include as requirements in a specification. Checklists ACI 563 has a mandatory and nonmandatory requirements checklist. It is recommended that the A/E references ACI 563 when the project is designed in accordance with ACI 562; this assures the designer that the requirements that are in ACI 562 are written in specification language. The A/E must specify the items in the Mandatory Requirements Checklist as the information is required on any project. The A/E also needs to review ACI 563 Sections 1 through 8 to determine which of the special concrete requirements are needed for the specific project. The Optional Requirements Checklist allows the A/E to determine if alternative tolerances or other specification items should be included in the contract documents. These items should be adjusted to the needs of a particular project by including those selected alternatives or additions as mandatory requirements in the Project Specification. @Seismicisolation @Seismicisolation University of Toronto User. Section 8—Proprietary cementitious and polymer repair materials Section 8 covers properties, proportioning, mixing, and use of proprietary cementitious and polymer repair materials. The contractor must submit the following to the A/E for approval before proceeding with repair: a. Repair material manufacturer (RMM) product data sheets and certifications with performance data; collected data must follow nationally standardized test methods whenever possible and provide sufficient detail to allow verification of the data within reasonable testing variation. such as precision and bias used in ASTM test methods b. Material safety data sheets (MSDS) or safety data sheets (SDS) c. Product samples d. Aggregates The contractor must submit supplemental testing data to ensure the specified material conforms with the specified requirements not included in the RMM product data sheet. The contractor must also prepare mockups to demonstrate that workers have mastered the construction techniques to the manufacturer’s representative satisfaction and to the approval of the A/E and owner that the product conforms to the specified requirements in the contract documents. If the contractor proposes alternate material than what was specified in the contract documents, then the contractor must submit new field data, data from new trial mixtures, or other evidence that the substituted repair material conforms to the specified performance criteria as indicated in the contract documents. The data must be submitted at least 7 days in advance for acceptance before changes are made, unless continuation of the work is accepted by the A/E with the alternative material(s). The contractor must provide a rationale for the substitution. If the substituted products have properties that deviate from the specified performance in the contract documents, then it cannot be used without a written approval by the A/E and owner (Section 8.1.4). As part of the QC, the material production and delivery must follow the manufacturer’s requirements. Testing and inspection of the repair material must be performed as indicated in the contract documents and test records must be saved for future reference (Section 8.1.6). During the execution of the repair work, the contractor must notify the A/E in writing before proceeding if there are deviations between the contract documents surface preparation requirements and the RMM’s written instructions (Section 8.3.2). The contractor, however, must follow the RMM’s written instructions for batching, mixing, placing, and curing of repair materials (Section 8.3.3). If there is any deviation from the RMM’s instruction, the contractor must obtain approval from the A/E before proceeding with the repair work. The repair material must be installed within the time frame specified, finished, and cured in accordance with the RMM’s written instructions and as indicated in the contract documents. As part of the QA/QC, the manufacturer’s representative must be available at the job site advising the contractor on the proper use, handling, and application of the material until the manufacturer’s representative is confident and assured that the workers have mastered the work and understand how to apply it. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 102 103 ACI 503.7-07 An ACI Standard Specification for Shotcrete Specification for Crack Repair by Epoxy Injection An ACI Standard Reported by ACI Committee 503 ACI 506.2-13(18) Reported by ACI Committee 506 Example B.NS—Referencing specifications into a construction document References The specification listed below forms a part of this specification. American Concrete Institute (ACI) 563-18—Specification for Repair of Concrete in Buildings Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. APPENDIX B University of Toronto User. @Seismicisolation @Seismicisolation The first 11 chapters and Appendix A of this guide describe the chapters and Appendix A of ACI 562 and provide additional information about the background and application of the provisions. Section numbers in these chapters correspond to the ACI 562 section number of that is being described. Appendix B of this guide describe the chapters of ACI 563. The following eight project examples illustrate how the requirements of ACI 562 can be applied to satisfy the code provisions for typical repair project scenarios. For convenience, the relevant sections of ACI 562 are listed to the top right of each corresponding paragraph of the Project Example text. The Project Examples are based on real projects. Because ACI 562 was not available at the time the projects were actually performed, they have been modified to reflect compliance with ACI 562, assuming that ACI 562 was accepted by the local jurisdiction having authority over the project. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Project Examples University of Toronto User. @Seismicisolation @Seismicisolation 104 Description of structure Chapter 2 Investigation of the structure shows it is a two-story, enclosed parking structure located in the northern United States. The parking structure, constructed in the 1960s, measures approximately 240 x 150 ft (73.2 x 45.7 m) in plan, as shown in Fig. 12.1. The lower level is on ground, and the middle level and roof consist of reinforced concrete flat slabs with drop panels. The middle-level deck is 9 in. (225 mm) thick with 10 ft-0 in. x 10 ft-0 in. x 2-1/4 in. (3 m x 3 m x 57 mm) drop panels centered around 2 ft-6 in. x 2 ft-6 in. (750 x 750 mm) reinforced concrete columns. The slab is covered with 1 in. (25 mm) asphalt topping. No design information or drawings were available. Project initiation and objectives Table A.2.3 At the middle-level deck, the owner noted potholes and unevenness in the asphalt topping and water leakage through cracks. A few small pieces of concrete had fallen from the underside of the slab. The project was initiated to determine the current condition of the parking structure and to develop a plan for repair of ACI 562-19 provision numbers applying to each section of text are shown in red at the top right of each paragraph. @Seismicisolation @Seismicisolation 105 University of Toronto User. Fig. 12.1––Middle-level deck plan showing Slab Area 1 with approximately 60 percent delaminated or spalled top surface concrete and Slab Area 2 with approximately 10 to 20 percent delaminated or spalled top surface concrete. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 12: Project Example 1—Typical Parking Structure Repair GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES the parking structure deterioration using the assessment and design criteria in Table A.2.3. Governing building codes Based on discussions with the building officials, the building codes adopted by the jurisdiction were determined. Jurisdiction—Northern U. S. city. Original building code—1961 Uniform Building Code (1961 UBC). Current building code—2015 International Building Code (2015 IBC). Existing building code—Not adopted. 1.2.3 1.2.2 1.2.1 1.1.2 ACI 562 supplements the existing building code, which is normally the International Existing Building Code (IEBC) and the 2015 IBC Chapter 34, and governs in all matters pertaining to concrete members in existing buildings, except wherever ACI 562 is in conflict with requirements in the 2015 IEBC, in which case the 2015 IEBC governs. 1.2.4, A.2 The design-based criteria are determined based on the assessment criteria in Chapter 4, if the IEBC is used, and in Appendix A, if ACI 562 is used without the IEBC. Because the repairs are intended to increase the structural safety (strength) by remediating the observed deterioration and Appendix A does not conflict with Chapter 34 of the 2015 IBC, design-basis criteria of Appendix A apply. A.3 a. Section A.3 – 2015 IBC supplemented by ACI 562-19, excluding detailing of the existing reinforcement. b. Section A.5.3 – 1961 UBC supplemented by ACI 562-19. A.5.3 A.5.2 c. Section A.5.2 – 2015 IBC supplemented by ACI 562-19, excluding detailing of the existing reinforcement. A.5.2, A.5.3 1961 UBC uses allowable stress design and service loads. An option, which was chosen by the licensed design professional (LDP), was to use Section A.5.2 of ACI 562-19 and the 2015 IBC supplemented by ACI 562 as a check for the Section A.5.3. @Seismicisolation @Seismicisolation University of Toronto User. 1.7.1, 1.7.3, A.3, A.5.3, A.5.2 Design-basis codes—Based on a preliminary assessment as described in Section 1.7 and considering the requirements of Sections A.3, A.5.3, and A.5.2 of ACI 562 and the existing building code, the design-basis code was determined to be as follows: Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 106 Preliminary assessment 1.7.1, 1.7.3 No documents were available for review, and the design-basis code for the preliminary assessment was assumed for purposes of practicality to be the current building code, 2015 IBC, that references ACI 318-14. The LDP is to use judgment to determine if a preliminary assessment is necessary and how to make their assessment considering the minimum requirements of ACI 562-19. Investigation of existing site conditions 1.7.4 Existing structural geometry—The existing structural geometry, including typical dimensions and member sizes, was measured on-site as part of the investigation. 1.7.1, 1.5.3 Existing concrete condition––On the top surface of the middle-level deck, the asphalt topping was removed, exposing the top concrete surface. Exposed concrete surfaces were visually surveyed for types and patterns of distress and deterioration (ACI 201.1R). Concrete surfaces were selectively sounded by chain drag, hammer tapping, or tapping with a reinforcing bar to estimate the extent of delaminated concrete. The pattern of deterioration suggested that deicing salts had been transported into the parking structure by vehicles causing corrosion-related deterioration particularly in areas near the parking structure entrance and where vehicles are most apt to park. Concrete powder samples were procured from the upper portion of the middle-level slab and tested for chloride content (ACI 364.1R). Samples were removed from areas near the parking structure entrance/primary parking area that exhibited deterioration as well as areas farther removed from these areas where less or no deterioration was exhibited. The purpose of this testing was to ascertain the level of chloride contamination at the level of the reinforcement. The following concrete distress and deterioration was documented. Typical types of observed concrete deterioration are illustrated in Fig. 12.2. 1.7.1, 1.7.4 Reinforcement—The reinforcing layout and condition were documented at a few typical locations by measurement of exposed bars, magnetic survey, and exploratory chipping to expose bars. No. 7 @ 7-1/2 in. (No. 22 @ 190 mm) on center and No. 7 @ 15 in. (No. 22 @ 380 mm) on-center bars were determined in column strips for top and bottom reinforcement, respectively. No. 7 @ 18 in. (No. 22 @ 450 mm) on center were determined @Seismicisolation in@Seismicisolation middle strips top and bottom University of Toronto User. a. The underside of the roof slab was determined to be in generally good condition. b. The top surface of the middle-level slab had two areas with distinctly different levels of concrete deterioration, as shown in Fig. 12.1. Slab Area 1, consisting of approximately half of the slab surface and located near the parking structure entrance/exit and the main drive aisle, was approximately 60 percent delaminated or spalled due to corrosion of the embedded reinforcement. The regions around the columns were completely delaminated or spalled. Slab Area 2, consisting of the remainder of the middle-level slab, was 10 to 20 percent delaminated or spalled. c. The underside of the middle-level slab was 10 to 20 percent delaminated or spalled due to corrosion of the embedded reinforcement, with greater damage observed in Slab Area 1. d. Just above the slab, the bases of columns had small areas of delamination due to corrosion of the embedded reinforcement mostly in Slab Area 1. e. The upper portion of the middle-level slab was heavily contaminated with chloride, greatly exceeding the corrosion threshold value (ACI 222R), particularly in areas that were delaminated, spalled, or cracked. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 12: Project Example 1—Typical Parking Structure Repair107 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 12.2––Typical concrete deterioration details. reinforcement, respectively. Cover was measured at 3/4 in. (19 mm). Surface corrosion and some section loss were documented for the top slab bars in Slab Area 1 (ACI 364.1R). Findings of preliminary assessment 1.7.4 The following determinations were made based on the preliminary assessment: RA.5.2 A comparison of the nominal loads in the 1961 UBC and the 2015 IBC shows no changes in these nominal loads for the parking structure. U c = U o* @Seismicisolation @Seismicisolation University of Toronto User. Capacity and demand of existing structure 1.7.4, 6.2.1, Table 6.3.2a, Table 6.3.2b, 1.7.3, A.3, A.5.3, A.5.2 A preliminary assessment was performed to estimate the existing capacity of the middle-level slab and the columns, including the impact of the observed deterioration. Rather than sampling and testing to determine the concrete and steel properties, the concrete compressive strength was assumed to be 3000 psi (21 MPa) and the yield strength of the reinforcing bars was assumed to be 33,000 psi (230 MPa) in accordance with Tables 6.3.2a and 6.3.2b of ACI 562. The demand for the middle-level slab and the columns were analyzed based on nominal loads and procedures in the 1961 UBC for ACI 562, Section A.5.3, and in the 2015 IBC for ACI 562, Section A.3 and A.5.2. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 108 Chapter 2 where Uc is defined as demand using nominal loads of the current building code and factored load combinations of ASCE/SEI 7 for strength design provisions (LRFD); and Uo* is the demand using nominal loads of the original building code and factored load combinations of ASCE/SEI 7 for strength design provisions (LRFD). 5.3 Without deterioration when using strength design provisions, the middle-level slab and the columns have capacity greater than demand with strength reduction factors of Section 5.3 of ACI 562 and using the 2015 IBC and 1961 UBC nominal loads along with ASCE/SEI 7 load factor combinations. Area 1 A.3.2 As there was substantial documented top surface concrete deterioration in Slab Area 1 but significant effort would be necessary to accurately determine the structural effects of this deterioration, approximately 60 percent of the top slab reinforcing bars were conservatively judged to be debonded at delaminations (Fig. 12.3) and therefore structurally ineffective. ACI 562 requires that the licensed design professional determines if the slab is potentially dangerous (ACI 562, Section A.3.): Column strip negative moment region: The slab capacity with no deterioration or delamination was calculated for the negative column strip region to be: fRn = 344 ft-kip (466 kN·m). This is greater than the factored applied load calculated at: Mu,cs– = 285 ft-kip (386 kN·m) for the same region. However, because 60 percent of the reinforcement is considered to be ineffective, this results in a slab capacity of: fRcn = 137 ft-kip (186 kN·m). Evaluating the demand-capacity ratio of the column strip negative moment region: A.3.2 Uc/fRcn = 285 ft-kip/137 ft-kip = 2.1 > 1.5 (Uc/fRcn = 386 kN·m /186 kN·m = 2.1 > 1.5) Demand (Uc) Mu,cs– = 285 ft-kip (386 kN·m) Design capacity fRn = 344 ft-kip (466 kN·m) Actual capacity fRcn = 137 ft-kip (186 kN·m) Demand/capacity Uc/fRcn 285 ft-kip/137 ft-kip = 2.1 > 1.5 (386 kN·m/186 kN·m = 2.1 > 1.5) Column strip positive moment region: It was determined conservatively that 20 percent of the bottom slab area was deteriorated and accordingly reinforcement in that area was debonded. The slab capacity with no deterioration or delamination was calculated for the positive column strip region to be: fRn = 133 ft-kip (180 kN·m). This is greater than the factored applied load calculated at: Mu,cs+ = 123 ft-kip (167 kN·m) for the same region. But due to deterioration, the slab capacity was reduced by 20 percent to: fRcn = 106 ft-kip (144 kN·m). Without repairs, however, the negative moment not resisted by the column strip is redistributed and added to @Seismicisolation @Seismicisolation University of Toronto User. As indicated in Section A.3.2 of ACI 562, an element or structure with a demand/ capacity ratio of greater than 1.5 is considered unsafe and requires shoring or other measures. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 12: Project Example 1—Typical Parking Structure Repair109 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 12.3––Effects of unsound concrete on reinforcing steel development. ℓd = tension development length, per ACI 318-05. Uc = Mu,cs+ = 123 ft-kip + (285 ft-kip – 137 ft-kip) = 271 ft-kip (Uc = Mu,cs+ = 167 kN·m + (386 kN·m – 186 kN·m) = 367 kN·m) Evaluating the demand-capacity ratio of the column strip positive moment region: A.3.2 Uc/φRcn = 271 ft-kip/106 ft-kip = 2.56 > 1.5 (Uc/φRcn = 367 kN·m /144 kN·m = 2.5 > 1.5) Therefore, the slab is structurally unsafe. @Seismicisolation @Seismicisolation University of Toronto User. the column strip positive moment region increasing the positive bending demand on the slab to: Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 110 Demand (Uc) Mu,cs+ = 271 ft-kip (367 kN·m) Design capacity fRn = 133 ft-kip (180 kN·m) Actual capacity fRcn = 106 ft-kip (144 kN·m) Demand/capacity Uc/fRcn 271 ft-kip/106 ft-kip = 2.56 > 1.5 (367 kN·m /144 kN·m = 2.55 > 1.5) If the negative column strip bending capacity is repaired, then the positive column strip bending demand need not include any redistribution of negative moment to the positive moment except for redistributed moment that is locked in, and the positive bending demand is: Uc = Mu cs+ = 123 ft-kip (167 kN·m) and Uc/φRcn = 123 ft-kip/106 ft-kip = 1.16 < 1.5 (Uc/φRcn = 167 kN·m /144 kN·m = 1.16 < 1.5) With the demand-capacity ratio of the column strip negative bending at 2.56 (2.55), the slab is currently considered to be structurally unsafe. There was substantial deterioration of the top reinforcement near the columns in Area 1, which rendered the slab shear capacity determined using the 1961 UBC provisions to be structurally insufficient. v = V / bjd (from 1961 UBC) A.3.2 Area 2 Current concrete deterioration has little or no effect on the allowable member capacities in Slab Area 2 and of the columns. The factored applied moment at the negative column strip is Mu,cs– = 285 ft-kip (386 kN·m) and the capacity for that section is fRn = 344 ft-kip (466 kN·m). Assuming that only 20 percent of the reinforcement is unbonded, then the capacity is reduced to fRcn = 275 ft-kip (373 kN·m) resulting in demand-capacity ratio of: A.3.2 Uc/fRcn = 285 ft-kip/275 ft-kip = 1.04 < 1.5 (Uc/fRcn = 386 kN·m/373 kN·m = 1.03 < 1.5) The slab in Area 2 is therefore considered safe. Demand (Uc) Mu,cs– = 285 ft-kip (386 kN·m) Design capacity fRn = 344 ft-kip (466 kN·m) Actual capacity fRcn = 275 ft-kip (373 kN·m) Demand/capacity Uc/fRcn 285 ft-kip/275 ft-kip = 1.04 < 1.5 (386 kN·m /466 kN·m = 1.03 < 1.5) @Seismicisolation @Seismicisolation University of Toronto User. A.3.2 Following ACI 562-16 Section A.3 requirements, the demand-capacity ratio (Uc/fRcn) for both bending moment and shear varies with the extent of damage. As an estimate of the shear strength in Area 1, h was used for plain concrete from ACI 318-14, Chapter 14 as the depth from the bottom of the slab to the delamination layer, Table 14.5.5.1 shear strength equations, and a strength reduction factor of 0.6 for plain concrete, which resulted in an effective two-way shear capacity of approximately 60 percent of the strength calculated without delamination. Where concrete is delaminated in Area 1 at the critical shear boundary, the section shear capacity can be considered as having dropped significantly and accordingly the demand-capacity ratio for shear is likely approaching or at 1.5. Therefore, the structure in Area 1 is considered unsafe (Uc/fRcn >1.5). Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 12: Project Example 1—Typical Parking Structure Repair111 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Column strip positive moment region: It was determined conservatively that 15 percent of the bottom slab area was deteriorated and accordingly reinforcement in that area was debonded. If deterioration did not exist, the slab capacity in that region was calculated to be: fRn = 133 ft-kip (180 kN·m). The slab capacity must be reduced by 15 percent to 113 ft-kip (153 kN·m) and additional moment demand from the negative region of the top slab must be added to determine the current condition. Mu,cs+ = 123 ft-kip + (285 ft-kip – 275 ft-kip) = 133 ft-kip (Mu,cs+ = 167 kN·m + (386 kN·m – 373 kN·m) = 180 kN·m) This will result in a demand-capacity ratio: Uc/fRcn = 133 ft-kip/113 ft-kip = 1.18 < 1.5 (Uc/fRcn = 180 kN·m/153 kN·m = 1.18 < 1.5) A.3.2 Per ACI 562 Section A.3.2, the section is safe and further assessment per Sections A.4 through A.9 is required. Demand (Uc) Mu,cs+ = 133 ft-kip (180 kN·m) Design capacity fRn = 133 ft-kip (180 kN·m) Actual capacity fRcn = 113 ft-kip (153 kN·m) Demand/capacity Uc/fRcn 133 ft-kip/113 ft-kip = 1.18 < 1.5 (180 kN·m /153 kN·m = 1.18 < 1.5) Per the commentary for the definition of damage, deterioration from aging should not be considered as damage. The columns had only small localized concrete deterioration and the check of Section A.5.2 of ACI 562 was not done in this example. A.5.3 For Area 2, the slab is considered safe per ACI 562, Section A.3.2, and accordingly Section A.5.3 or A.5.2 may be checked to determine if strengthening is required. The following table lists the demand and capacity at critical sections in a typical interior two-way slab of the parking structure using Eq. (RA.5.3). Column strip Middle strip Reinforcement A s– As + A s– As + Demand, Us As,req’d in.2 (mm2) 12.5 (8065) 6.8 (4387) 5 (3226) 5 (3226) Capacity, Ra As,prov. in.2 (mm2) 13.5 (8710) 7.2 (4645) 6 (3871) 6 (3871) Us / Ra 0.93 < 1 0.94 < 1 0.83 < 1 0.83 < 1 The slab two-way shear capacity was calculated at 89 psi (0.61 MPa), which is less than the allowable required by code of 0.03fc′ = 90 psi (0.62 MPa) and therefore, increasing slab shear punching strength was not required. A.5.3 ACI 562 Section A.5.3 commentary states that, “using the allowable design is inconsistent with the reliability principles of current strength design provisions. To adequately address safety, consideration should be given to verification using A.5.2 and a check of seismic resistance using ASCE/SEI 41.” Seismic resistance is not an issue in the region and was excluded from the analysis. ACI 562 Sections A.5.1, A.5.2, or A.5.3 per Table A.2.3 were used to verify the structural adequacy in Area 2. This was not required to be performed at Area 1 because it was already determined to be unsafe and would be repaired to be in compliance with the current code. @Seismicisolation @Seismicisolation University of Toronto User. Location Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 112 Report to owner The owner was notified of the safety concerns. Shoring was promptly installed to support Slab Area 1 to address the safety concern and to allow continued access to the parking structure until repairs could be installed. Also, loose concrete was promptly removed from the underside of the slabs. As immediate safety concerns were promptly addressed, it was not necessary to notify the authorities having jurisdiction. The LDP considered the following factors: 1.5.3 a. Based on the simplifying preliminary assumption made by the LDP that the top slab reinforcement in Slab Area 1 is over 60 percent debonded and ineffective, the slab was deemed unsafe. b. As no excessive cracking or deflections were noted, the slab is apparently still performing satisfactorily despite the extensive deterioration and, therefore, the preliminary assumption is conservative particularly for areas with little to minimal deterioration. c. Structural elements outside of Slab Area 1 have some concrete deterioration but were not considered by the LDP or authorities having jurisdiction as unsound or structurally deficient. A.2.4, A.2.5, RA.5.1 d. Code changes in detailing and other requirements make it difficult, if not impossible, to bring existing concrete structures into full compliance with current code requirements. Although Area 1 has unsafe structural conditions, the structure has demonstrated historical structural reliability having been in service for more than 50 years, is located in a region where seismic activity is minimal, and is to be repaired; therefore, full compliance with detailing requirements was not necessary. The LDP determined, and the authorities having jurisdiction agreed, that the design basis code should be 1961 UBC, with the provision that where possible, the slab in Slab Area 1 should be brought into conformance with the requirements of the current building code 2015 IBC. STRUCTURAL ASSESSMENT 6.1.1, 6.2.2, 6.2,3, 6.2.4 Existing structural geometry—The existing structural geometry was documented in more detail than was done for the preliminary assessment (4.1.1). a. All column spacing, column dimensions, and drop panel dimensions were measured. b. The slab thickness was determined with ground-penetrating radar and confirmed by physical measurements at holes drilled through the slab. 6.4.2.1, 6.4.3.1 Concrete strength—Concrete core samples were extracted and tested in compression to determine the slab concrete compressive strength. The strength values were consistent with the strength assumed in the preliminary analysis. 6.2.4, 6.4.4.1 Reinforcing steel layout and strength—Reinforcing steel spacing and cover were determined with ground-penetrating radar and confirmed at exposed bars and exploratory openings. Exposed reinforcing bars were examined for identification marks that might indicate the steel yield strength. No marks were found. Additional areas were investigated for reinforcing layout, sizes and, cover using magnetic survey, cover meter, and exploratory chipping to expose bars. The extent of measurement of expanded from the preliminary measurements and the results @Seismicisolation @Seismicisolation University of Toronto User. Existing conditions Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 12: Project Example 1—Typical Parking Structure Repair113 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES were consistent with the preliminary findings. Therefore, the same assumptions for the preliminary assessments were used for the final assessments. 6.4.5.1 Coupons were removed from reinforcing bars and tested in tension to determine the steel yield strength. Strength values were consistent with the strength assumed in the preliminary analysis. Structural analysis for repair design @Seismicisolation @Seismicisolation University of Toronto User. 1.3.8.2, 5.2.3 Loads factors and load combinations—The loads, load factors, and load combinations are as specified in ASCE/SEI 7-10. 6.5.1, 6.5.2, 6.5.3, 6.5.5, 6.5.7, 6.7.1, 6.7.2, 6.7.3 Analysis—In the preliminary assessment, the direct design method was used to determine the elevated slab moments, whether the slab was safe, and if strengthening was required. For the final assessment, a three-dimensional finite element model was developed to confirm the preliminary assessment findings, to evaluate the proposed repair procedure, and to assess the repaired system potential performance. For the current state, the LDP used the actual reduced slab thicknesses due to delamination and the actual material properties obtained from in-place testing removing eight cored cylinders. The LDP took caution not to drill through existing reinforcement by locating the bars before drilling. Additional nondestructive testing was performed using rebound hammer to collect additional data. Correlation was established between the nondestructive data and test results obtained from the extracted cylinders. The finite element analysis confirmed the preliminary assessment calculation for Area 1 and Area 2. The calculated demand of the gravity loads based on the current design code to the obtained capacity from the software output exceeded 1.5 for Area 1 indicating an unsafe condition. For Area 2, the demand-capacity ratio calculated per A.5.1 did not exceed 1.0; therefore, the structure did not require strengthening. The elevated slab was then reanalyzed considering the structural repair process, including the effects of the sequence of shoring for Area 1, load application, and material removal for both areas. The final finite element analysis assumed that the replacement concrete would be fully bonded to the existing concrete and, hence, there would be full composite action between repair materials and existing materials. The demand-capacity ratio of both repaired areas (Areas, 1 and 2), obtained from the final analysis, was below 1.0; therefore, the repair design deemed theoretically satisfactory. Note that the asphalt overlay was removed and replaced with concrete overlay. The difference in the material unit weight was considered in the final finite element analysis. 7.4.1, 7.4.1.1 Bonding of the new concrete to the existing concrete was critical to satisfactory performance of the repaired structure. The horizontal shear demand at the interface of the repair and existing concrete was calculated based on the loads and combinations described previously. ACI 562 Section 7.4.1 requires the bond strength demand to be at least equal to the bond strength capacity (nu ≥ fnni). Shear was calculated at face of columns and at face of drop panels, change in slab thickness. Based on the applied load, the ultimate shear stress at face of columns and at face of drop panels were calculated at 22 and 28 psi (0.15 and 0.19 MPa), respectively. 7.4.1.2 These stress values were compared to the shear stress values in Table 7.4.1.2 of ACI 562. Because the calculated ultimate stress values were smaller than 30 psi (0.21 MPa), interface reinforcement was not required and bond-integrity testing as specified in the construction documents must be performed. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 114 As part of the field assessment, pulloff testing of the substrate determined that the substrate had adequate strength to achieve the required bond strength. Based on required bond strength, the LDP concluded that the required bond could be attained by chemical or mechanical means with proper surface preparation and repair material application (ICRI 310.1R discusses surface preparation for repair of deteriorated concrete). Therefore, no supplemental reinforcement was required. Refer to Example 7.2 of this guide for more detailed information on the testing requirements, and pulloff test to ensure adequacy of the bond between overlay and substrate. Area 1 6.5.4 While the extent of debonding of the top reinforcing steel was unclear, the analysis also considered the possible redistribution of load effects and resulting increases in concrete and steel stresses due to the deterioration and subsequent installation of shoring, as follows: a. It was assumed that approximately 60 percent of the negative moment capacity had been lost, and the increased steel and concrete stresses in the positive moment region were calculated. b. It was then assumed that the shoring supported the slab during construction, such that no loads from construction were resisted by the slab. c. When construction had been completed and the shoring removed, it was assumed that the topping weight and design live load were supported by the repaired composite section. The capacity of the repaired section was examined and determined to have adequate strength to resist design loads. Area 2 University of Toronto User. 6.5.4 The extent of debonding area of the top reinforcing steel was substantially smaller than what was observed in Area 1; therefore, redistribution of load effects was not considered and subsequently installation of shoring was not considered: a. It was assumed that approximately 20 percent of the negative moment capacity had been lost, and the increased steel and concrete stresses in the positive moment region were calculated and found to be negligible. b. When the construction was completed, it was assumed that the topping weight and the design live load were supported by the repaired composite section. The capacity of the repaired section was examined and determined to have adequate strength to resist the design loads. A.3.2, A.5.1 Consideration of punching shear––The LDP understood the 1961 UBC considered only vertical shear, or punching shear, transfer from the slab to columns. Newer codes, such as ACI 318-14 referenced by the current building code (2015 IBC), specified that a portion of the unbalanced slab moments must be transferred into the column by eccentricity of the shear, thus increasing the maximum punching shear. A.2.4, A2.5, RA.5.1 A close visual inspection of the top and bottom surfaces of the middle-level slab around the first interior columns, where the unbalanced slab moments are greatest, did not detect any cracking that might be indicative of distress due to inadequate punching shear capacity. Although ACI 318-14 predicts an inadequate punching shear capacity at some columns, the LDP determined that because the slab prior to deterioration had performed satisfactorily for 50 years, and that it was being repaired back to original strength, that it was unnecessary to bring the punching shear capacity into conformance with provisions of the current building code. 1.5.3.a, 1.5.3.b, 1.5.3e, 1.5.3g The LDP provided the owner with a basis of design report providing a description of the structure, identifying the structural system, and listing the codes used for the design and construction of the structure. The basis of design report also included documentation of unsafe structural conditions in the @Seismicisolation work area as presented previ@Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 12: Project Example 1—Typical Parking Structure Repair115 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES ously and identified members that required strengthening. Strengthening options were presented to the owner along with the advantages and disadvantages of each option along with the recommendation of the LDP. DESIGN OF STRUCTURAL REPAIRS AND DURABILITY Slab area 1 Slab repairs were designed according to the provisions of the 1961 UBC. Two repair options for deteriorated concrete on the top surface were discussed with the owner: 1. Removal and replacement of deteriorated concrete only on the top slab surface. 2. Removal and replacement of the top 3 to 4 in. (75 to 100 mm) of concrete in the entire area. Option 2 was recommended for the reasons described in the following. Option 2 advantages–– University of Toronto User. 8.4.3, 8.4.4 a. Chloride-contaminated concrete around the top reinforcing mat is to be removed and replaced with uncontaminated concrete with low permeability, improving durability and reducing future maintenance. 7.5.2 b. The new concrete will have similar or slightly enhanced properties compared to the existing concrete. 7.3.2, 7.3.3, 7.4 c. After concrete removal work has been completed, the exposed concrete surfaces will be cleaned and a suitable bonding procedure will be used to attain the minimum required bond strength and ensure composite behavior under service loads. Surface roughness of the exposed concrete surfaces will be specified per a Concrete Surface Profile number from ICRI Guideline No. 310.2R or some other means. 7.3.2, 8.4.2, 8.4.4 d. Existing reinforcing bars, except for those embedded in columns, are to be removed and replaced with new epoxy-coated reinforcing bars, replacing bars with reduced cross-sectional area. Because the new bars are uncontaminated and coated with epoxy, their resistance to corrosion is much improved, improving durability and reducing future maintenance of the slab system. Existing bars to remain are to be cleaned and coated with a corrosion-inhibiting material. 8.2.1, 8.2.2 e. Top reinforcing bars with shallow cover can be relocated downward in the slab for increased corrosion protection cover. This is assuming that the slab still has adequate calculated shear capacity with a decreased effective depth, and that additional bars are added as necessary to provide adequate calculated flexural capacity. 7.6.3.3 f. New reinforcing bars are to be fully encapsulated and developed in the replacement concrete. 7.1.1, 7.2.1, 7.2.2 g. The repaired slab will have similar or greater strength and stiffness to the originally constructed sections. 8.5.1 h. Due to the new uncontaminated concrete with low permeability, and the epoxycoated reinforcement, new surface coatings such as a traffic-bearing elastomeric coating or a surface sealer were not recommended, reducing initial and maintenance costs. i. The new slab will have similar or enhanced fire resistance rating compared to that of the existing slab. @Seismicisolation @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 116 7.9.1, 7.9.2, 7.9.3 j. The higher initial cost of this repair option will be at least partially offset by lower future maintenance costs. k. As this repair area is at the parking structure entrance, less future maintenance also equates to fewer, shorter parking structure closures and less user inconvenience. Option 2 disadvantages— 7.3.2, 7.3.3, 7.6.3.3 a. The perimeter of the partial-depth replacement area must be located and detailed to account for shear and moment transfer and reinforcing steel development. 9.2.5, 9.2.6 b. The slab will need to be shored prior to the slab removal and remain shored until the new slab concrete has been placed and cured. c. Cracks that may form in the replacement concrete should be sealed. 8.3.1 d. This repair option has a higher initial cost as compared to Option 1. Slab Area 2 and columns Replacement of deteriorated concrete only was recommended in this slab area, as the partial-depth replacement option recommended for Slab Area 1 was not a cost-effective approach for the limited concrete deterioration in this area. Similarly, the columns have very limited concrete deterioration and only replacement of deteriorated concrete was recommended. This limited approach has the following advantages and disadvantages. University of Toronto User. Advantages–– a. Only deteriorated concrete is to be removed and replaced, limiting repairs and repair costs to current requirements. 7.6.6 b. Reentrant corners will be avoided in both the repair and existing concrete. 7.3.2, 7.4 c. After concrete removal work has been completed, the exposed concrete surfaces will be cleaned and a suitable bonding procedure used to attain the minimum required bond strength and ensure composite behavior under service loads. Surface roughness of the exposed concrete surfaces will be specified per a Concrete Surface Profile number from ICRI Guideline No. 310.2R or some other means. 8.4.2, 8.4.4 d. Existing reinforcing bars that are exposed in removal areas will be cleaned and coated with a corrosion-inhibiting material to reduce ongoing corrosion in and around the replacement concrete areas. 7.6.3.1, 8.4.2, 8.4.4 e. New epoxy-coated reinforcing bars will be lapped with existing bars that are exposed in removal areas and that have lost structurally significant crosssectional area. 8.4.1, 8.4.4 f. Discrete galvanic anodes will be installed around the perimeter of slab concrete replacements to reduce corrosion in the existing concrete around the concrete replacements. To function properly, the anodes must be attached to uncoated portions of the reinforcing bars in the removal areas before the bars are coated with a corrosion-inhibiting material. 8.2.2 g. As much of the existing concrete will remain, the as-built reinforcing steel cover generally will not be modified. 7.5.2 h. The replacement concrete will have similar or slightly enhanced properties compared to the existing concrete. @Seismicisolation @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 12: Project Example 1—Typical Parking Structure Repair117 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES 7.6.3.3 i. The existing and new reinforcing bars will be developed in the existing concrete, the repair concrete, or both. 7.1.1, 7.2.1, 7.2.2 j. The repaired sections will have similar strength and stiffness to the originally constructed sections. 8.3.1, 8.3.2 k. Existing cracks will be addressed prior to the installation of the traffic-bearing elastomeric coating. New cracks that may form in the replacement concrete may be sealed by the traffic-bearing elastomeric coating or will be addressed by future maintenance repairs. 8.5.1, 8.5.2 l. A traffic-bearing elastomeric coating will be applied on the repaired slab surface to drastically reduce moisture penetration into the slab concrete and reduce ongoing corrosion activity in the remaining existing concrete and concrete replacements. The membrane will extend several inches up the column bases so that moisture on the deck surface cannot directly access the column concrete. 7.9.1, 7.9.2, 7.9.3 m. The repaired slab will have similar or enhanced fire resistance rating compared to that of the existing slab. This repair approach has a relatively low initial cost but periodic maintenance repairs will be necessary. It is a very cost-effective approach to address the present condition of the parking structure. 7.2.2 n. Analysis of the middle-level slab determined that the slab concrete remaining after the assumed extent of removal of deteriorated concrete can safely support the dead and construction live loads during the repair installation and its portion of the long-term dead and live loads after the repairs have been completed. Disadvantages— Slab soffit repairs 1.5.1, 1.6.1 The replacement of deteriorated concrete only was recommended on the slab soffit throughout the supported slab areas. Construction specifications The LDP prepared contract documents that specified repair materials satisfying governing regulatory requirements and conveyed necessary information to perform the work. The LDP used ACI 563 as a source for construction specifications. The specification sections that were referenced included: Section 1—General requirements Section 2—Shoring @Seismicisolation and bracing @Seismicisolation University of Toronto User. 8.4.3 a. Except at repair locations, chloride-contaminated concrete will remain in place, resulting in some ongoing corrosion activity with concrete and steel deterioration requiring periodic maintenance repairs. The corrosion reduction measures incorporated into the repair program should significantly reduce ongoing corrosion activity and periodic repair requirements. 9.2.2, 9.2.5 b. The LDP must establish limits for concrete removal and monitor the removal work so that shoring can be installed before the load limits are exceeded. 9.2.2, 9.2.5, 9.2.6, 10.2.3 c. The LDP must monitor the concrete removal work for loss of reinforcing steel development and possible short-term and long-term structural implications, and for possible structurally significant loss of reinforcement cross-sectional area, as determined by the LDP. The LDP must determine if unsafe conditions may exist and if temporary shoring should be installed. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 118 Construction 9.2 The LDP monitored the construction for unexpected conditions that may affect the short-term or long-term safety of the structure. Temporary shoring or bracing may be necessary (Sections 6.2.1 and 6.2.4). 9.4.1 Environmental issues, such as allowing water with debris to flow into floor drains or off of the site and disposal of construction debris, will be specified in conformance with local ordinances. Quality assurance 1.5.1, 10.2.1, 10.2.2, 10.4.1 The repair specifications included quality assurance and control measures for material approvals and field verification of quality. The specified quality control measures and construction observations were performed during the construction, including the following: a. Review of material submittals and reinforcement shop drawings for Slab Area 1. b. Visual inspection of the work in progress. c. Sounding of concrete surfaces to remain to determine if all loose concrete was removed prior to repair. @Seismicisolation @Seismicisolation University of Toronto User. Section 3—Concrete removal and preparation for repair Section 5—Reinforcement and reinforcement support Section 6—Conventional concrete mixtures Section 7—Handling and placing of conventional concrete Section 9—Crack repair by epoxy injection The repair work did not require any formwork, therefore, Section 4—Formwork, was not referenced. Based on the size of the repairs, a conventional concrete was specified by the LDP in place of a proprietary material or shotcrete. ACI 563, “Specifications for Repair of Concrete Buildings,” addresses conditions that are unique to the project. The standard has mandatory and nonmandatory requirements checklists at the end of the standard to help the specifier submit as complete a specification as possible. For the parking structure slab repair, only a few sections from the mandatory checklists are extracted to include in the Project Contract Document: a. Section 1.5.1.1—State the maximum dead and live loads and any temporary reduction in loads, to be permitted during repair and after completion of repair program, in concert with the requirements of 2.1.1.1. b. Section 1.5.4.1—Show the demarcation line of the project location, specific work areas, and adjacent construction. c. Section 1.8.2.1—Identify work to be performed by certified personnel. d. Section 3.1.1.2—Provide the surface profile and remove laitance, debris, and bond-inhibiting materials. e. Section 3.1.3.1—Indicate testing locations, type, number, and frequency of tests. f. Section 3.2.1.1—Select the means and methods for concrete removal that will minimize damage to the structure and bruised surfaces on the concrete substrate that remains within and adjacent to the work areas. g. Section 3.2.1.5—State the required surface profile. h. Section 3.3.1.1—Show the required depth of concrete removal. i. Section 3.3.4.2—Indicate that tensile pull-off tests shall be performed at specified locations in accordance with ASTM C1583/C1583M. j. Section 5.2.1.2(b)—Indicate ASTM specification to which epoxy-coated reinforcing bars are to conform. k. Section 6.2.2.6(d)—State the chloride exposure classification for are of work. l. Section 6.2.2.7—Indicate the specified concrete compressive strength fc' for the work. m. Section 7.1.2.2—List the information in 7.1.2.2(a) to 7.1.2.2(g) that is to be submitted. n. Section 9—Repair of cracks by epoxy injection in accordance with ACI 503.7. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 12: Project Example 1—Typical Parking Structure Repair119 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES 10.2.3 d. Observation of the prepared concrete surfaces and of the concrete placement and curing operations. 10.3.1 e. Testing of repair concrete, including slump, temperature, and compressive strength. f. Bond strength testing of in-place repair concrete to confirm that the bond strength was in accordance with Table 7.4.1.2 of ACI 562. PROJECT CLOSE-OUT Periodic maintenance R1.5.3k, 8.1.2 Periodic maintenance requirements were discussed with the owner during the selection of the most appropriate repair concepts. A schedule of recommended monitoring and possible maintenance requirements was provided to the owner at the conclusion of the repair construction, including the following: a. Periodic inspections every 3 to 5 years to monitor the condition of the parking structure. b. Limited concrete deck repairs every 5 years. c. Limited repair of the traffic-bearing elastomeric coating every 3 to 5 years to address areas of high wear such as near the parking structure entrance/exit. d. Top coating the traffic-bearing elastomeric coating and restriping the parking structure every 15 to 20 years. Record documents 1.6.3, 1.5.3d, R1.5.3j The owner was provided with copies of the project and construction documents and the recommended monitoring and maintenance program. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 120 University of Toronto User. @Seismicisolation @Seismicisolation Description of structure The structure is a 28-story residential tower located in the northern United States. The building, constructed in the 1970s, measures approximately 80 x 90 ft (24.4 x 27.4 m) in plan, as shown in Fig. 13.1. The north and south elevations are cast-inplace reinforced concrete shear walls with 1 in. (25 mm) deep reveal strips at every floor line. The east and west elevations consist of exposed slab and column edges with glass-and-metal curtainwall infills. Several tiers on the east and west elevations have reinforced concrete balconies that cantilever out from the building. The original design drawings were available. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 13: Project Example 2—Typical Façade Repair University of Toronto User. Fig. 13.1—Plan of residential tower. ACI 562-19 provision numbers applying to each section of text are shown in red at the top right of each paragraph. @Seismicisolation @Seismicisolation 121 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Project initiation and objectives The owner had noted spalled areas of concrete and exposed corroded reinforcing bars on all elevations. The project was initiated to determine the current condition of the concrete façade, identify unsafe conditions, and develop a plan and schedule for façade maintenance. Governing building codes Based on discussions with the local building officials, as well as the information available on the original design drawings, the building codes adopted by the jurisdiction were determined as follows. Jurisdiction—Northern U.S. city Original building code—1973 municipal code Current building code—2013 municipal code Existing building code—Not adopted 1.2.3 1.2.2 1.2.1 LDP interpretation: The repairs proposed will not exceed this threshold, therefore the municipal code provisions for new construction are not applicable as the design-basis code. No change in use was proposed. LDP interpretation: The compliance criteria for the determination of the designbasis code for change in use as set forth in the municipal code are not applicable. “Every existing building shall be so constructed and maintained as to support safely the loads prescribed in” the current building code. LDP interpretation: The floors were well maintained and there was no condition of deterioration or other reasons to suggest that the capacity of the floors had been impaired over time. The original building code specified a live load of 40 lb/ft2 (1.91 kN/m2) for “dwelling units or sleeping rooms.” No specific loading provisions were provided in the original building code for balconies. A design review indicated that the balconies had been designed for a live load of 40 lb/ft2 (1.91 kN/m2). The current building code specified a live load of 100 lb/ft2 (4.81 kN/m2) for balconies of residential units. Because the previsions of the current building code applicable to existing structures @Seismicisolation specified that the structure should safely support the floor @Seismicisolation University of Toronto User. 1.1.2, 1.7.3, 1.2.4.2, A.2.1, A.2.4 Design-basis code—Because the local jurisdiction has not adopted an existing building code, the design-basis code will be determined in accordance with ACI 562 Section 1.7.3. A preliminary assessment was performed using ACI Appendix A and Chapter 6. It was determined that the structure was in compliance with the version of ACI 318 referenced in the original building code (1973 municipal code). The assessment also determined that the structure was safe. Therefore in accordance with Section A.2.4, the repairs could be designed in accordance with the version of ACI 318 used for the original construction and ACI 562. It should be noted that requirements pertinent to existing buildings contained in the current building code must also be checked by the licensed design professional (LDP). A review of the two chapters for existing construction from the 2013 municipal code yielded the following pertinent provisions relative to the determination of the design-basis code. “Any building over 80 ft (24.4 m) in height that is altered or repaired, the cost of which in any 30 months exceeds 50 percent of the reproduction cost of the building, shall comply with the requirements,” for new construction of high-rise buildings. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 122 loads in the current building code, the building code official was consulted. It was concluded that it was satisfactory for the balconies serving single units, which were unlikely to experience loads approaching 100 lb/ft2 (4.81 kN/m2), to be designed for the live load in the original building code, As such it would not be necessary to strengthen the balconies to meet the current building code requirement for live load. Because it is frequently an overwhelming burden for building owners to upgrade structural elements to current design load requirements, this approach is not uncommon if it is unlikely that the structural elements will actually experience the larger current design loads associated with the current code. The following provisions in the current building code for exterior walls of existing buildings were also checked by the LDP. “It shall be the duty of the owner of every building regardless of height to maintain the building’s exterior wall in a safe condition.” For unsafe conditions of exterior walls, the owner is obligated, “to take appropriate precautionary measures, which may include the erection of a construction canopy and effect such repairs or reinforcements in a timely manner to remediate such unsafe conditions.” LDP interpretation: In this scenario, the primary structural system also serves as the exterior wall; as such, the exterior concrete must be maintained in a safe condition and unsafe conditions must be made safe. Furthermore, as confirmed with the building official, the original building code should be used as the designbasis code for exterior concrete repairs. 1.2.4.2 Therefore, the design-basis code is the original building code, which for this scenario is the 1973 municipal code along with ACI 562. Preliminary observations and assessment University of Toronto User. 1.5.1, 1.7.1 The LDP visually surveyed the façade from the ground with binoculars. Based on this survey, two locations on each elevation were selected for tactile inspection from a suspended swing stage. Surveys from the swing stage included close-up visual inspections and hammer sounding of concrete for delaminated and loose concrete. The span of the swing stage and width, length, and configuration of the building was such that nearly all exterior vertical concrete surfaces were visually examined from a close proximity. 1.7.1, 6.4.1.1 Approximately 5 percent of the balconies were also accessed by swing stage or through the residential units, and the topside and underside concrete surfaces and concrete handrails were visually surveyed and sounded for delaminated and loose concrete. 6.1.1, 6.4.1.1, 6.4.1.2, 8.3.1, 8.4.3 In addition, samples of concrete, consisting of six 2 in. (50 mm) diameter core samples and 10 concrete powder samples were obtained for laboratory investigation of chlorides, carbonation, and concrete quality. The objective of the sampling plan was to obtain information that can be used to evaluate the condition of the concrete and the constructions, and to corroborate observed satisfactory performance, or to document and explain distress or failure. The sampling plan was specific to the structure and the needs of the LDP to make informed designs about repair solutions, and generally followed the provisions of ASTM C823/C823M. Concrete cores were obtained and tested in accordance with ASTM C42/C42M. The purpose of the cores was to determine the quality of the concrete cover and depth of penetration of chlorides and carbonation. As such, the depth of the cores extended to approximately 1 in. (25 mm) beyond the reinforcing bars. The depth of reinforcing was measured at selected locations. ASTM C1152/C1152M was consulted for the obtaining of concrete powder samples. The original design drawings and maintenance history of the building were@Seismicisolation also thoroughly reviewed. @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 13: Project Example 2—Typical Façade Repair123 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Observed concrete conditions Typical types of observed concrete deterioration are described in the following and illustrated in Fig. 13.3 and 13.4. (a) Concrete spalls with exposed reinforcing bars at a reveal in a shear wall. (b) Concrete spall with exposed reinforcing bars and delaminated loose concrete at slab edge. Fig. 13.3—Typical small isolated areas of deteriorated concrete on balconies. @Seismicisolation @Seismicisolation University of Toronto User. Fig. 13.2—Typical types of concrete deterioration. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 124 North and south shear walls––The concrete deterioration on the north and south shear walls mainly consisted of numerous small delaminations and spalls at the location where reinforcing bars crossed beneath the reveal strips, resulting in shallow cover. A few larger areas of delaminations, approximately 100 to 200 ft2 (9.3 to 18.6 m2) in area each, were noted; generally, in these areas the wall reinforcing bars had been misplaced with shallow cover. East and west slab and column edges––The exposed slab and column edges had small areas of concrete delaminations and spalls, most typically at locations where reinforcing bars were located close to the surface. Balconies––The top and edge balcony surfaces were 10 to 20 percent delaminated. The balcony soffits were delaminated over 5 percent or less of their surface. Delaminations and spalls typically occurred at isolated locations where reinforcing bars were located close to the surface. The metal handrails were in generally good condition with a few small areas of localized corrosion and peeling paint. Reinforcing bars––Reinforcing bars, typically No. 5 (No. 16) bars, exposed at spalls and locations where loose concrete was removed exhibited minor surface corrosion and the bar deformations remained clearly visible. Typically, the exposed bars had 1 in. (25 mm) or less of concrete cover. The cover was further reduced locally, sometimes too little or no cover, at the location where the bar crossed a reveal or near slab edges and corners. The exposed reinforcing bars were generally associated with slab bars that were provided with a 180-degree hook at the slab edge. 1.5.2, 1.7.2 Unsafe conditions––Areas of loose concrete were identified by the LDP and removed as part of the swing stage inspection. The owner was notified of these unsafe conditions and advised that additional areas of loose concrete were likely present in areas not accessed by the LDP. The owner elected to have a contractor promptly remove all remaining loose concrete from the entire façade. It was therefore not necessary to notify the authorities having jurisdiction as unsafe conditions had been eliminated. Findings Spalled and delaminated concrete was mostly limited to locations where reinforcing bars were placed too close to the surface and located in carbonated concrete. The loss of concrete was limited to the depth of the steel in an area slightly wider than the bar at these locations. In limited instances, the small areas of spalled and delaminated concrete combined to form larger areas of concrete loss with shallow depth that did not extend behind the bars. Steel reinforcement had not experienced appreciable section loss. 1.7.1, 1.7.2, 1.7.4, A.2.3 Assessment of the structural implications associated with the spalled and delaminated concrete by the LDP concluded that there was no substantial structural damage and, in fact, the observed distress and deterioration were of no consequence to the structural integrity of the members being assessed or the building as a whole. The current depth of carbonation in the concrete had only reached and affected reinforcing bars with shallow cover. As the depth of carbonation increases, more reinforcing bars may be affected. An anti-carbonation coating could be considered to greatly reduce the rate of carbonation. @Seismicisolation @Seismicisolation University of Toronto User. Laboratory findings Petrographic examination of concrete core samples revealed that the concrete was of good quality with good durability characteristics. Neither the slab nor the wall concrete had elevated chloride contents, but the concrete was carbonated to a depth of approximately 1/2 in. (13 mm) below the concrete surface. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 13: Project Example 2—Typical Façade Repair125 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Structural assessment and repair design Shear wall reveal strip repairs It is very difficult to repair concrete over shallow reinforcing bars in a durable, yet visually acceptable manner. In some locations, ends of bars or hooks at the ends of bars could be cut off, but at most locations the end hooks were necessary for the development of the reinforcing bars and could not be removed. The following approaches were discussed with the owner and are illustrated in Fig. 13.4: Approach 1: Build out the concrete replacement so that a minimum concrete cover of 1 in. (25 mm) is attained. This procedure results in the most durable repair, but results in build-outs in the concrete surface that may not be visually acceptable. The tops of the build-outs would be sloped downward and outward to shed water. Approach 2: Install a repair material, such as cementitious or polymer mortar, flush with the existing concrete surface. This procedure eliminates build-outs in the concrete surface. However, it is difficult to find a repair material that can be applied at thicknesses less than 1 in. (25 mm) (and perhaps much thinner at some locations) over the reinforcing bars and that will not crack or debond in an exterior northern environment. If the material cracks, subsequent reinforcing bar corrosion may cause the repair material to debond, creating a hazard of falling material. Approach 3: Remove unsound concrete and clean and coat the exposed reinforcing @Seismicisolation bars with a corrosion-inhibiting material. As no concrete or @Seismicisolation University of Toronto User. 7.2.2, 9.1c, 9.2 Concrete columns exposed as façade elements are commonly part of the gravityload-carrying system and may be part of the lateral-load-carrying system. Consequently, the effect of concrete and reinforcing steel deterioration and the repair procedures on the ability of the columns to carry loads must be evaluated. Fortunately, on some façade repair projects such as this example, the extent of concrete and steel deterioration is relatively minor and of minimal structural consequence. However, the LDP must be cognizant of the role of the column in the structure and must specify appropriate bracing and shoring measures and repair procedures. Refer to 7.2 and 9.1 of this guide for considerations related to column deterioration and repair. 5.1.2 The extent of the deterioration for this example does not have structural implications to the affected members or the building as a whole. Furthermore, the designbasis code does not require structural upgrades to satisfy current building code requirements. Hence, the factored loads, factored load combinations, and strength reduction factors of ACI 562 Chapter 5 are not applicable to this project. 6.2.1, 6.2.2 Based on visual observations of the structure, the LDP determined there was no reason to question the design strength of affected members or the structure. Therefore, a structural analysis and evaluation was not required per ACI 562 Chapter 6. 1.3.7.1, 7.3.3 The primary purpose of the repair is to restore the concrete façade to its original cross section for durability and aesthetic purposes. In accordance with the design-basis code, the repair shall also remediate unsafe conditions associated with falling hazards. 7.5.1, 7.5.2, 8.1.1, 8.1.2 The specifics of the repair design will consider the existing construction, including the reinforcing bars with shallow cover; properties of the repair materials, including adhesion, shrinkage, and thermal movement; installation procedures, including curing requirements and environment conditions; and performance in the service environment, including durability and corrosion resistance, per ACI 562 Section 7.5. The LDP selected the repair materials and developed the installation procedures based on the experience of the LDP as well as ACI and ICRI documents on concrete repair. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 126 University of Toronto User. @Seismicisolation Fig. 13.4—Repair options at concrete delaminations and spalls at shear wall reveal strips. @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 13: Project Example 2—Typical Façade Repair127 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES North and south walls away from reveal strips and east and west slab and column edges The owner generally elected to build out concrete replacements in these areas to provide a minimum concrete cover of 1 in. (25 mm), similar to at the reveal strips, as the most durable repair. A slab edge build-out is illustrated in Fig. 13.5. The owner felt that the build-outs would not be that visible from the ground and would not be aesthetically objectionable. Balcony repairs 8.4.1, 8.4.2, 8.4.3 The balconies had limited areas of concrete deterioration, primarily due to shallow concrete @Seismicisolation cover. To maintain aesthetics and uniform walking surfaces, @Seismicisolation University of Toronto User. other material replacement will be performed, this procedure will leave depressions in the concrete surface at the shallow reinforcing bars. Unavoidable imperfections in the coating application, particularly at the interface between the bars and the concrete, will result in unsightly rust stains over time. This coating would need to be maintained to prevent corrosion of reinforcing that could lead to continued delamination of concrete. The existing concrete is not uniform in appearance. As such, the repair concrete mixture will need to be carefully controlled to minimize an uneven, blotchy appearance. For Approaches 1 and 2, it will be difficult and costly to match the appearance of the repair concrete to that of the adjacent existing concrete. Alternatively, the owner could consider covering the façade with a somewhat breathable architectural coating that would result in a uniform appearance, and also reduce water and carbon dioxide penetration into the concrete. This coating would need to be reapplied periodically to maintain an acceptable appearance. After discussing the various repair approaches and the associated advantages and disadvantages, the owner elected to go with Approach 1 and build-out the concrete replacements for better durability. The owner also elected to coat the façade for improved durability and appearance. 8.2.2, 8.4.2, 8.4.4, 7.4, 7.5.1, 7.5.2, 7.6.3.2 In this repair approach, unsound and, as necessary, sound concrete was removed to provide minimum patch depths and minimum gaps behind the reinforcing bars. The concrete and steel surfaces were cleaned by wire brushing and the steel surfaces were coated with a corrosion-inhibiting material for improved corrosion resistance. To achieve the best quality of the installed repairs, removal areas on vertical surfaces were formed and placed using bird mouths (small angled extensions from the face of the formwork to allow placement of concrete) so that the plastic replacement material did not have to resist gravity. The bird mouths produce small extensions of concrete from the surface that are ground off after form removal. Use of a proprietary latex-modified concrete with 3/8 in. (9.5 mm) coarse aggregate provided a suitable replacement concrete with good bond to the existing concrete. The selected material could be mixed in small batches and placed in locations that generally did not exceed 3 ft2 (0.3 m2) in surface area. Proprietary materials generally are manufactured with good quality control, reducing the risk of batching problems at the site. Further, the material exhibited minimal shrinkage cracking. The build-outs increased the concrete cover at the shallow reinforcing bars, improving the durability of the replacements. 8.3.1, 8.5.1, 8.5.2 The architectural coating of repaired areas decreased the surface permeability of the repair concrete and sealed non-moving cracks, which improved the durability of the repair. (Non-moving cracks are generally formed as a result of shrinkage during the curing process.) Coating of the remainder of the façade provided a uniform surface appearance and provided improved durability for areas with shallow cover that had yet to experience delaminations or spalls. Moving cracks were routed and sealed prior to application of the architectural coating. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 128 concrete cover could not be increased in replacement areas by building up the replacement material. Thus, the recommended repair was to remove the deteriorated concrete and install replacement concrete in the removal areas flush with the surface. The concrete delaminations and spalls were relatively small and isolated and had no effect on the structural capacity of the balconies. No unsound concrete extended into the residential units. No shoring was necessary during the repairs. While concrete deterioration was limited and isolated on this project, on some projects, cantilever balconies can have significant top surface deterioration near the building wall and even into the building interior, resulting in reduced structural capacity. It may be necessary to shore such balconies for one or more levels below during the repair process. 7.6.3.2, 8.1.3, 8.5 Unsound and, as necessary, sound concrete was removed to provide minimum removal depths and minimum gaps behind the @Seismicisolation reinforcing bars. The exposed @Seismicisolation University of Toronto User. Fig. 13.5—Built-out replacement at balcony slab edge. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 13: Project Example 2—Typical Façade Repair129 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES concrete and steel surfaces were cleaned by sandblasting and the steel surfaces were coated with a corrosion-inhibiting material for improved corrosion resistance. To achieve the best quality of the installed repairs, removal areas on vertical surfaces were formed and placed using bird mouths. Removal areas on overhead surfaces were formed and cast by dry packing so that the plastic replacement material did not have to resist gravity. A proprietary portland cement concrete with 3/8 in. (9.5 mm) coarse aggregate was used for top surface and edge concrete replacements. A proprietary latex-modified concrete with 3/8 in. (9.5 mm) coarse aggregate was used on overhead concrete surfaces for increased bond to the existing concrete. The selected materials could be mixed in small batches and placed in locations that generally did not exceed 3 ft2 (0.3 m2) in surface area. Proprietary materials generally are manufactured with good quality control, reducing the risk of batching problems at the site. 8.4.1, 8.5.1, 8.5.2 It was also recommended, and the owner agreed, to coat the top surface and edges of the balconies with a traffic-bearing elastomeric coating and coat the balcony soffits with the architectural coating used on the façade. The surface coating along with a corrosion-inhibiting coating on reinforcing bars serve to improve durability of the balconies, particularly at locations of shallow concrete cover. The trafficbearing elastomeric coating will significantly reduce moisture penetration into the balcony concrete and reduce the potential for future corrosion activity in the remaining existing concrete and the replacement concrete. The traffic-bearing elastomeric coating will require periodic maintenance over its lifetime. 8.3.1 The surfaces to receive an architectural coating were cleaned by pressure washing and the architectural coating was applied, all per the recommendations of the coating manufacturer. On top and edge balcony surfaces to receive a traffic-bearing elastomeric coating, the surfaces were cleaned by sandblast, existing cracks were also filled with sealant, and the coating was installed, all per the recommendations of the coating manufacturer. Performance under fire and elevated temperatures Contract specifications 1.6.1, 9.4.1 The LDP prepared contract documents that specified repair materials that satisfied governing regulatory requirements and that conveyed necessary information to perform the @Seismicisolation work. The LDP determined and specified limits of concrete removal @Seismicisolation University of Toronto User. 7.9 Except at the reveal strips where the concrete replacements will be built out, increasing the fire protection, the repairs will restore the concrete structural elements to their original as-built condition. The LDP determined that exterior façade elements were unlikely to be exposed to design fire conditions due to a lack of nearby flammable materials. Also, the limited small areas of concrete replacements would have no effect on the overall fire resistance of the structure and, even if repair areas with inadequate fire resistance were enhanced, adjacent unrepaired sections might still have inadequate fire resistance. Therefore, the LDP determined that the concrete repairs did not need any special detailing to enhance their fire resistance, and the authorities having jurisdiction agreed. 1.5.3, 1.5.3a, R1.5.3b, 1.5.3h, 1.5.3e The LDP provided the owner with a basis of design report providing a description of the structure, identifying the structural system, listing the codes used for the design and construction of the structure, and the design-basis code that will be used for the repair work. The basis of design report also included documentation of structural conditions in the work area as presented above and identified members that required repair. The report noted that the structure was safe and that substantial structural damage was not present. The LDP presented the owner with three approaches for the repair of the structure of which the owner selected one to perform the repair work. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 130 areas to ensure that no members would be overstressed. The contract documents also instructed the contractor to be responsible for the control of all construction debris, including environmentally hazardous materials. The LDP used ACI 563 as a source for construction specifications. The specification sections that were referenced included: Section 1—General requirements Section 3 —Concrete removal and preparation for repair Section 4 —Formwork Section 5 —Reinforcement and reinforcement support Section 8 —Proprietary cementitious and polymer repair material The repair work did not require any shoring and bracing, therefore, Section 2— Shoring and bracing, was not referenced. Based on the size of the repairs, latexmodified concrete was specified by the LDP in place of a conventional concrete. ACI 563, “Specifications for Repair of Concrete Buildings,” addresses conditions that are unique to the project. The standard has mandatory and nonmandatory requirements checklists at the end of the standard to help the specifier submit as complete a specification as possible. For the parking structure slab repair, only few sections from the mandatory and nonmandatory checklists are extracted to include in the Project Contract Document: a. Section 1.5.4.1—Show the demarcation line of the project location, specific work areas, and adjacent construction. b. Section 1.8.2.1 —Identify work to be performed by certified personnel. c. Section 3.1.1.2—Provide the surface profile and remove laitance, debris, and bond-inhibiting materials. d. Section 3.2.1.1 —Select the means and methods for concrete removal that will minimize damage to the structure and bruised surfaces on the concrete substrate that remains within and adjacent to the work areas. e. Section 3.3.1.1—Show the required depth of concrete removal. f. Section 4.2.2.6—Specify appearance and texture required. g. Section 5.2.1.2(b)—Indicate repair coating, application procedures, and coating repair approval process. h. Section 8.1.2.1(a)—Review the submittal list and indicated the testing required to be submitted. Construction Quality assurance 1.5.3d The repair specifications included quality assurance and control measures for material approvals and field verification of quality. The specified quality control measures and construction observations were performed during the construction, including the following: a. Review of material submittals. 10.2.3 b. Visual inspection of the work in progress. 1.5.1, 10.2.1, 10.2.2, 10.4.1 c. Sounding of concrete surfaces to determine if all loose concrete was removed prior to repair. @Seismicisolation @Seismicisolation University of Toronto User. 9.1, 9.2.1, 9.2.2, 9.2.3, 9.2.4, 9.2.5 Based on the assessment by the LDP, the observed distress and deterioration was of no consequence to the structural integrity of the members being repaired. Consequently, while temporary shoring is sometimes necessary on balcony repair projects, it was not required on this project. Nonetheless, the contract documents required the contractor to notify the LDP when removal amounts exceeded the maximum areas expected for this project. This allowed the LDP to assess global and individual member stability, if required, for these areas. Areas of unsound concrete to be removed and replaced were identified by hammer tapping the concrete surfaces. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 13: Project Example 2—Typical Façade Repair131 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES d. Observation of removal areas to ensure that excessive removal or damage to steel was not occurring. 10.2.3 e. Observation of the prepared concrete surfaces, the applied corrosion-inhibiting coating, and the concrete placement and curing operations. This monitoring is particularly important in the early stages of the repairs so that a minimum level of quality can be established. 10.3.1 f. Testing of repair concrete, including slump, temperature, air content, and compressive strength. 10.2.1, 10.2.2 g. Sounding of cured replacements to verify that the replacements are bonded to the substrate. As none of the concrete replacements were of structural significance, the LDP determined that bond pulloff testing was not necessary, but that the replacements should be sounded for debonding. 10.3.1 h. Prior to installation of the traffic-bearing elastomeric coating, the vapor emissions of representative concrete replacements on top balcony surfaces were tested to verify that the emissions were less than that recommended by the coating manufacturer. PROJECT CLOSE-OUT Periodic maintenance Record documents 1.6.3, 1.5.3d, 1.5.3j, 1.5.3k The owner was provided with copies of the project and construction documents as well as the recommended monitoring and maintenance program. @Seismicisolation @Seismicisolation University of Toronto User. R1.5.3k Periodic maintenance requirements were discussed with the owner during the selection of the repair approach, and a schedule of recommended monitoring and possible maintenance requirements was provided to the owner at the conclusion of the repair construction, including the following: 1.5.3j a. In conformance with the current building code, inspections for unsafe façade conditions from ground level are required every 2 years and close-up inspections from a swing stage are required every 4 years. Findings of the periodic façade inspections are to be reported to the building code official. b. If unsafe conditions are found, the owner should take appropriate precautionary measures in a timely manner to remediate such unsafe conditions. c. Cleaning and maintenance of the coated façade surfaces are recommended every 10 to 15 years (depending on performance of the coating) to maintain a satisfactory appearance and assure continued integrity of the coating. d. Top coating the traffic-bearing elastomeric coating is recommended every 10 to 20 years (depending on performance of the elastomeric coating) to maintain a satisfactory appearance and assure continued integrity of the coating. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 132 Description of structure The 300,000 ft2 (28,000 m2) facility, shown in plan in Fig. 14.1, is a two-story structure constructed in the 1920s. Until 1971, the supported train deck included train tracks and loading platforms. The train deck was then converted into parking and loading facilities for a postal distribution center. As part of an adaptive reuse project, the train deck will be reconfigured into a multimodal transportation hub servicing light rail commuter trains, Class 1 rail trains, and buses. The facility is listed on the National Register of Historic Places. The train deck, shown in cross section in Fig. 14.2, is constructed of a two-way, 21 in. (530 mm) thick reinforced concrete slab with drop panels that spans between reinforced concrete columns with capitals. The train deck is covered with 23 to 60 in. (580 to 1500 mm) of granular fill and is divided into four areas by northsouth expansion joints. The top surface of the train deck is protected with a waterproofing system applied directly to the deck. The self-adhering rubberized sheet waterproofing system was installed in 1993. The asphalt-paved lower, or ground, level of the facility is used for automobile parking and storage. The reinforced concrete columns are typically spaced 21 ft (6.4 m) apart in both orthogonal directions and are 12 to 15 ft (3.7 to 4.6 m) tall. The majority of the columns are 30 in. (760 mm) in diameter, and approximately two-thirds of the columns had original or supplemental steel jackets installed on the bottom third of the columns for impact protection and in response to corroded reinforcing steel and concrete deterioration that was apparent many years ago. ACI 562-19 provision numbers applying to each section of text are shown in red at the top right of each paragraph. @Seismicisolation @Seismicisolation 133 University of Toronto User. Fig. 14.1—Grid layout of train deck. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 14: Project Example 3—Adaptive Reuse of Historic Depot GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 14.2—Typical cross section. Project initiation and objectives Governing building codes Based on discussions with the building officials, as well as the information available on the original design drawings, the relevant building codes adopted by the jurisdiction were determined as follows. Jurisdiction—northern U.S. city. 1.2.3 Original building code—Proposed Standard Building Regulation for the Use of Reinforced Concrete (ACI 1910 with Chicago ruling of 1915 for flat slab design). In response to the need for uniform design standards for flat slab construction, the Chicago Building Commission in 1915 adopted the Flat Slab Ruling (commonly referred to as the Chicago Ruling), which gives formulas for the design of flat slab structures. As described in the Thirteenth Proceedings of the Annual Convention of the American Concrete Institute, the ACI Committee on Reinforced Concrete and Building @Seismicisolation Laws took up the proposed changes offered in the Chicago Ruling @Seismicisolation University of Toronto User. 1.7 Prior to undertaking the adaptive reuse project, the owner needed to evaluate the condition of the train deck structure and columns, which after 80 years of service exhibited areas of freezing-and-thawing damage and corrosion-related concrete deterioration. The evaluation was required to determine the structural adequacy of the deck and columns to support the new multimodal transportation hub and determine appropriate repairs, as necessary. The owner also established a desired 50-year service life for the rehabilitated concrete structures. The evaluation and repair design was executed per the guidance offered in ACI 562. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 134 Preliminary observations and evaluation 1.3.1, 1.3.2, 1.7.1 The track deck and columns exhibited deterioration consistent with 90 years of exposure to a harsh northern climate. Deterioration was most prevalent along expansion joints, at column bases, and along exposed slab edges. To understand the extent and impact of deterioration of the structural capacity of the existing structure, the LDP recommended that an investigation and assessment be performed. Concrete conditions 1.7.2 All surfaces of the track deck soffit and supporting columns were visually surveyed and selectively sounded by hammer tapping. In addition, selective areas were identified for in-depth study. The expanse of the train deck and potential for significant cost and disruption associated with removing @Seismicisolation the fill to expose the top @Seismicisolation University of Toronto User. and included these in their 1917 proposed revisions to the 1910 Standard Building Regulation for the Use of Reinforced Concrete. An article by the assistant engineer for the project published in the December 17, 1921, edition of Railway Age describes the design of the track structure. 1.2.2 Current building code—2015 International Building Code (2015 IBC), which references ACI 318-08. 1.2.1 Existing building code—2015 International Existing Building Code (2015 IEBC). 1.1.2, 1.4.1 ACI 562 supplements the 2015 IEBC and the 2015 IBC Chapter 34 and governs in all matters pertaining to concrete members in existing buildings, except wherever ACI 562 is in conflict with the requirements in the 2015 IEBC, in which cases the 2015 IEBC governs. 1.2.4 Design-basis code—Because the local jurisdiction has adopted an existing building code, Sections 1.2.4.1, 1.2.4.2, and 1.2.4.4 of the ACI 562 code directs the licensed design professional (LDP) to determine the design-basis code in accordance with ACI 562, Chapter 4. 4.1 Per ACI 562 Section 4.1, the design-basis code was determined based on criteria set forth in the existing building code, which for this project example is the 2015 IEBC. The IEBC contains specific requirements that determine when existing structures should be upgraded to satisfy the requirements of the current building code. Per Chapter 11 of the 2015 IEBC, the repair, alteration, addition, restoration, and change of occupancy of a historic structure should comply with the work classifications described in Chapter 4 of the 2015 IEBC. The work classification was considered a Level 3 Alteration given that more than 50 percent of the aggregate building was planned for major renovations as part of the adaptive reuse. The occupancy classification would remain unchanged. Therefore, the existing structural elements supporting gravity loads (per 707.4 of the 2015 IEBC) need to comply with the existing building code. The design-basis code was therefore established as the 2015 IBC. This code specifies the applicable gravity and lateral loads used for the evaluation and the rehabilitation design. Live loads not covered by the 2015 IBC are required to be determined in accordance with a method approved by the building official. For the determination of truck and railroad loading requirements, the LDP received approval from the building official to supplement the design-basis code with AASHTO and AREMA (American Railway Engineering and Maintenance-ofWay Association) codes, respectively. As the facility was on the National Register of Historic Places, the LDP also had to consider the Secretary of the Interior’s Standards for the Treatment of Historic Properties. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 14: Project Example 3—Adaptive Reuse of Historic Depot135 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES The following types of concrete distress and deterioration were noted in the train deck slab: a. Localized areas of freezing-and-thawing deterioration were identified in the top surface of the train deck slab; no corrosion-related distress was observed at the top slab surface. b. The condition of the deck soffit varied widely. Corrosion-related delaminations and spalls@Seismicisolation were prevalent at expansion and construction joints and at drains and @Seismicisolation University of Toronto User. deck surface dictated the scope of the selective opening and concrete sampling program. In consultation with the owner and contractor, the LDP recommended four study areas based on their condition from best to worst, as assessed through visual inspection and nondestructive testing. The selected areas were also representative of the most common design features across the 6 acre (24,000 m2) site. The fill was removed from each study area, which included at least one structural bay. The steel jackets were also removed to expose the lower portion of the columns. 1.7.2 The exposed areas of the top deck surface were visually examined and sounded by chain dragging and hammer tapping. Because the waterproofing membrane may affect the acoustic emission from a chain drag survey, the LDP predominately relied on hammer sounding results to quantify the extent of damage. In-depth examination was performed at selected areas of the deck and columns, including materials sampling for laboratory testing of concrete quality through petrographic examination, chloride content analysis, carbonation testing, and strength testing. In-place measurement of corrosion potentials and corrosion rates was also performed. Samples of steel reinforcing bars were removed and tested to determine appropriate properties to use in the analysis. The waterproofing membrane was in fair condition. Refer to ACI 364.1R for more detailed information on the evaluation of concrete structures. 1.7.2 The LDP originally anticipated that delaminations and spalling on the deck underside could be quantified for estimating repair areas based on the visual survey, confirmed by delamination surveys in the four study areas. The white paint on the deck underside was expected to highlight distress in the underlying concrete. Based on this expectation, the area of distress was first calculated from the visual survey notes. However, during the close-up inspections and sounding of the deck study areas, it became clear that numerous delaminations were present that were not visually identifiable from ground level. Thus, to provide a more accurate basis for quantifying distress, the LDP selected and hammer sounded 18 bays outside of the deck study areas. These included several bays for each condition state from best to worst based on the visual assessment. 1.7.4, 1.7.5, 6.3.5, 6.4.2.1 The material sampling program included the removal of 60 cores. The LDP selected core locations to ensure that all elements and areas of the structure were represented and to permit further investigation of conditions of interest. Based on the preliminary evaluation by the LDP and the robust design of the original structure, concrete strength was not a significant limiting factor in the adaptive reuse. Thus, lower-bound values of concrete strength would be sufficient for determining safety of the repaired structure. As such, it was concluded that an exhaustive concrete coring program was not required for the determination of concrete strength. However, information collected through the material sampling program was required to assess the cause and extent of observed concrete deterioration and to guard against distress mechanisms that might limit the durability of repairs or unrepaired areas that appeared good at the time of the assessment. The LDP selected concrete cores located both inside and outside of the in-depth study areas. Core locations were selected to be representative of the various conditions observed. The findings of the laboratory analysis of concrete and steel samples yielded consistent results and indicated that further sampling was not required. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 136 openings in the deck. This included areas of original concrete and locations that had been previously repaired with shotcrete patches. c. Hammer sounding of the deck soffit detected significantly greater quantities of delamination than suspected based on visual examination. d. Corrosion potential and corrosion rate testing indicated that moderate corrosion was occurring at the deck soffit, particularly around joints, drains, and openings in the deck. Little if any corrosion activity was detected at the top of the deck. The following distress and deterioration were noted on the columns: a. Many of the columns without jackets had deteriorated concrete that extended 1 to 2 ft (0.3 to 0.6 m) above the pavement. b. Localized areas of corrosion-induced concrete deterioration were noted above the steel jackets. c. Steel jacket corrosion was variable, ranging from minor surface corrosion to heavy rust scaling. d. Some of the steel jackets were split along vertical seams, which was most likely associated with the expansion of columns due to the corrosion of embedded reinforcement. Material evaluation findings 1.5.3, 8.4.3 Carbonation depth and chloride contents were obtained to evaluate the durability of the concrete against corrosion-related damage from embedded steel reinforcement. Petrographic examination of concrete samples was used to evaluate concrete quality and deterioration. The laboratory testing demonstrated that the concrete quality and composition was typical for site-batched concrete construction of the early twentieth century. Specific observations included: a. Typical to above-typical compressive strengths, as described in Section 5.2.2 b. Carbonated concrete beyond the reinforcing steel at the deck underside and columns c. Chloride levels in the deck near joints and drains were above the corrosion threshold values presented in ACI 222R d. High chloride levels at the column bases (ACI 222R) e. Highly porous concrete not intentionally air entrained Summary University of Toronto User. 1.5.3, 1.5.3a The LDP provided the owner with a basis of design report that summarized the findings from the preliminary evaluation. The basis of design report included a brief description of the age of construction, gravity-load structural system, the original building code used to design the structure, and historical overview of the uses the structure was subjected to. The basis of design report documented the shortcomings in the structure, such as the existing porous, non-air-entrained concrete being susceptible to damage from cyclic freezing and thawing. Minor to moderate depths of freezing-and-thawing damage have occurred in areas throughout the structure where existing concrete surfaces are exposed and subject to water saturation during freezing conditions. The most severe deterioration has occurred at the deck underside, particularly along construction joints and near expansion joints, and at the bases of columns due to chloride contamination of the concrete. The high level of carbonation reduces the pH of the concrete and destroys the passive film on the reinforcement, which encourages corrosion. Future freezing-and-thawing damage deterioration was likely in exposed portions of the structure, unless protection from quantities of water sufficient to saturate the concrete is provided. Additional corrosion-related deterioration was also expected if the chloride-contaminated and carbonated concrete was not addressed. The LDP addressed these issues to meet the project objective for a 50-year service life. @Seismicisolation @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 14: Project Example 3—Adaptive Reuse of Historic Depot137 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Structural assessment Requirement for structural assessment 6.2.2 A structural assessment was performed to determine the gravity and lateral load effects associated with the new loadings proposed for the adaptive reuse. Specifically, the concrete columns and slab structure were evaluated for truck and rail loadings. Deteriorated portions of individual members would be repaired, so that any strength reduction due to the deterioration was not considered in the assessment. Existing properties Structural analysis 5.2.3, 5.1.3 Loads—The applicable gravity, wind, and seismic loads were determined using the design-basis code. The dead loads were based on the documented self-weight of the existing structure @Seismicisolation and the weight of the proposed fill and additions associated with @Seismicisolation University of Toronto User. 1.7.1, 1.7.2, 1.7.4, 6.2.4 Existing structural geometry—The existing structural geometry was obtained from the original construction documents and verified through field measurements. Column spacings, column dimensions, and drop panel dimensions were measured. The slab thickness was confirmed by physical measurements at core holes drilled through the slab. Fill depths were measured at exploratory openings. 6.3.2, 6.3.3, 6.4.2.1, 6.4.3.1, 5.1.3 Concrete strength—Concrete core samples were extracted from the train deck and the columns and tested in compression to determine properties for use in the analysis. A total of 60 cores were removed, with 26 tested in compression. Ten cores from the slab and 10 cores from the columns were tested. The average strength of the deck cores was 8130 psi (56 MPa), with a range of 4790 to 9980 psi (33.0 to 68.8 MPa) and a standard deviation of 1500 psi (10.3 MPa). Based on Eq. (6.4.3.1) in ACI 562, the equivalent specified concrete strength was approximately 6600 psi (45.5 MPa). The average strength of the column cores was 5070 psi (35.0 MPa), with a range of 3070 to 8580 psi (21.1 to 59.2 MPa) and a standard deviation of 1560 psi (10.8 MPa). Based on Eq. (6.4.3.1) of ACI 562, the equivalent specified concrete strength was approximately 3900 psi (26.9 MPa). The equivalent specified concrete strengths are significantly greater than the default value of 2000 psi (13.8 MPa) for slabs and columns in Table 6.3.1a in ACI 562. The historic documents indicated that each slab bay was batched on-site, which could produce variable concrete properties throughout the depot. The sample size was considered relatively small given the extensive quantity and method of batching. As such, the LDP elected to use lower-bound concrete strengths of 5000 psi (34.5 MPa) for the slabs and 3000 psi (20.7 MPa) for the columns in the structural assessment, which are greater than the values presented in Table 6.3.1a. The visual survey of concrete and the 30 additional cores suggested generally consistent quality from the sampled areas, which represented conditions varying from good to poor. The structural analyses yielded suitable results to accommodate the owner’s objectives for the reused structure. As such, a more costly and thorough concrete sampling program was not deemed necessary. 6.4.4.1 Reinforcing steel layout and strength—Reinforcing steel spacing and cover were determined by magnetic surveys and confirmed at inspection openings on the train deck and the columns. The field measurements were in good agreement with the design drawings. 6.4.5.1, 6.4.6 Reinforcing bar samples were obtained from deck and columns and tested in tension to determine the steel material properties. The bars were determined to be intermediate grade reinforcing steel with a yield strength of 40,000 psi (276 MPa). Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 138 Structural analysis findings 5.1.3, 9.2.1, 9.2.2 Gravity load effects—The structural analysis, which was based on the requirements of the design-basis code and the project load criteria, determined that the structure had adequate calculated capacity to support the gravity loads from the proposed adaptive reuse. Analysis of the structure under repair, which considered concrete removal when determining member limit states, indicated that shoring was not required to support dead loads and construction live loads. Live load effects—The structural analysis indicates that the existing track deck did not have adequate flexural capacity to support the Cooper E-80 trainaxle loading (AREMA code), but was sufficient for lighter Cooper loadings. The Cooper E-80 loading was the most severe load case required by the project criteria. The track deck was found to be adequate for the light rail and bus loadings anticipated in the adaptive reuse. The columns had adequate capacity to support E-80 loadings, and thus by extension the lighter rail and bus loadings. Lateral load effects—The lateral-load-resisting system was slab-column frames in both orthogonal directions. The original structure was designed for wind load effects, but seismic loads were not considered in the 1920s. The wind load effects from the design-basis code were relatively modest for the two-story structure and by structural engineering judgment and analysis did @Seismicisolation not control the design. @Seismicisolation University of Toronto User. the adaptive reuse. Live loads were prescribed by the project load criteria, including a series of train axle loads and bus uniform and axle loads. The uniform load for platform areas was based on the requirements of the 2015 IBC. Impact factors and braking forces were estimated based on the provisions of AREMA codes. 1.3.8 Wind and seismic loads were determined in conformance with the requirements of the 2009 IEBC. The 2015 IEBC references ASCE/SEI 41-2013 for the seismic evaluation of existing buildings and ASCE/SEI 41-2013 for the seismic rehabilitation of existing buildings. 5.1.3 Loads during the construction and repair process were also considered and evaluated in accordance with ASCE/SEI 37-2014, as the structure was unoccupied during the construction period. 6.5.1 Load factors and load combinations—The load factors and load combinations were determined based on the requirements of the 2005 AREMA Manual in conformance with the project design criteria, which were at least equal to the effects of factored load combinations specified in ASCE/SEI 7-2005. 6.5.2, 6.5.3 Analysis—A portion of the train deck was modeled as uncracked concrete sections using finite element modeling. The model included the support columns and appropriate boundary conditions. A linear elastic analysis was performed. The analysis was in general conformance with the 2005 AREMA Manual and was consistent with general industry practice. 6.7.1 Because all unsound deck and column concrete was planned for repair before the construction on top of the train deck was installed, the effects of the concrete deterioration were not included in the finite element model for evaluating the adaptive reuse. An analysis was also performed to determine if the train deck and column concrete remaining after the assumed extent of removal of deteriorated concrete could safely support the dead and construction live loads during the repair installation and its portion of the long-term dead and live loads after the repairs had been completed. 5.1.2, 5.2.2 Flexural and shear capacities were calculated based on the requirements of the 2005 AREMA Manual, which as a supplement to the design-basis code took precedence over the provisions of Section 5.4 in ACI 562. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 14: Project Example 3—Adaptive Reuse of Historic Depot139 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Recommended repair program Train deck rehabilitation Based on the assessment and evaluation work, the LDP recommended widespread repairs to the deck underside, whereas only localized repairs at the deck top surface were necessary. Future periodic maintenance of the deck underside was also anticipated to achieve the desired 50-year service life. Measures to protect the topside of the @Seismicisolation repaired deck from future water ingress through full-depth cracks @Seismicisolation University of Toronto User. 6.7.4.3, 1.7.3 A basic check of the seismic demands and column capacities was performed by the LDP to understand the overall magnitude of the seismic risk and if a more detailed seismic analysis would be required. The effort of the LDP here was considered a preliminary analysis. Per ACI 562 Section 1.7.3, the LDP was permitted to assume a design-basis code and selected the Equivalent Lateral Force Procedure in ASCE/SEI 7-2010. A typical column was checked for its tributary seismic mass using the seismic requirements in ASCE/SEI 7-2010. The ground motion values SDS and SD1 were obtained from the USGS Design Maps website using the project latitude and longitude coordinates, a soil classification of D (stiff soil), a risk Category of I, and a seismic importance factor of 1. The SDS and SD1 values placed the structure in the Seismic Design Category A, which defines the applied lateral forces to be 0.01W per story (that is, the lateral force applied at the top of the column is 0.01 × the tributary dead load that the column supports). Comparing this demand with the flexural capacity of a typical column the demand to capacity ratio (DCR) was calculated to be approximately 1.5 percent. Given the low seismic demand, the LDP decided that no further seismic evaluations were necessary. Note that the evaluation of the structure using the procedures of ASCE/SEI 31 yields a similar conclusion. Under this analysis, the structure and assessment allow for the use of the Low Seismicity Checklist per Section 3.6 of ASCE/SEI 31. The two checklist items for structural components were both found to be compliant. Load path was compliant because the slab and columns and retaining walls allow for transfer of inertial forces to the foundations. Wall anchorage was compliant to satisfy the forces calculated in the referenced Quick Check Procedure. No further analysis was therefore required. Seismic Design Category—To determine the detailing requirements in the 2015 IBC it was necessary to determine the Seismic Design Category of the structure (2015 IBC, Section 1908.1.2). As noted previously, the computed SDS and SD1 values place the structure in Seismic Design Category A (2015 IBC Table 1613.5.6 (1) and (2)). For Seismic Design Category A structures, the requirements of Chapter 21 of ACI 318-14 did not apply (2015 IBC Section 1908.1.2; ACI 318-14 Section 21.1.1.3). 6.5 Lateral-load-resisting system—The capacities of the as-built slab and column frame members were calculated based on provisions of the 2015 IBC. The seismic demands were extremely small relative to the member capacities. In fact, the calculations demonstrated that, due to the relatively large dead loads, the columns under seismic loadings remained elastic. The slab also had adequate calculated capacity to resist the moment and shear effects of the design load combinations. As-built detailing—The as-built detailing did not strictly conform to the requirements of the 2015 IBC and ACI 318-14, excluding Chapter 21. It would be prohibitively expensive to bring the as-built detailing into conformance with the requirements of the design-basis code. As the existing structure has performed satisfactorily for 90 years with no visible signs of structural distress, and as the adaptive reuse would not significantly increase the structural loadings, the LDP determined that no structural rehabilitation was necessary for the adaptive reuse. It should be noted that the Chicago Ruling of 1915 was one of the first guides published for flat slab design. Flat slab design at the time was a relatively new concept that yielded structures with very robust reinforcement schemes. The authorities having jurisdiction concurred with this assessment. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 140 and joints were determined to be critical to prolonging the life of the repairs and the repaired structure. The execution of localized repairs was determined to be considerably more cost effective than complete deck replacement. However, complete deck replacement at areas of severe deterioration, such as expansion joints, was cost effective and considered. Repairs recommended for the train deck: a. Partial-depth topside and underside surface repairs b. Full-slab-thickness repairs, primarily along expansion joints and near drains c. Removal and repair of all underside slab deterioration not addressed by fullslab-thickness repairs d. Crack and construction joint sealing e. New expansion joint seals f. New drains g. Topside waterproofing/deck protection Of these, the buried fully adhered waterproofing with an unbonded concrete topping was likely the most durable in this application. Bonded overlays (concrete or polymer resin) would be designed similar to those used in bridge deck rehabilitation and protection. An exposed traffic-bearing waterproofing membrane @Seismicisolation was also considered, but the @Seismicisolation University of Toronto User. The partial-depth surface repairs and full-slab-thickness repairs would include removal of unsound concrete and sufficient sound concrete to create minimum replacement depths and gaps around exposed reinforcing bars, and restoration of the structural cross section at the repair areas. Because chloride contamination was limited to deteriorated areas where the concrete would be removed as part of the repair process, supplemental corrosion mitigation such as galvanic anodes were not considered to be of significant value in these deck repairs. 8.4.3 Given the level of underside concrete deterioration, significant areas of the deck soffit required repair. The areas to remain are known, based on testing, to be carbonated to the level of reinforcing steel. As such, future corrosion-related deterioration of these areas should be anticipated. Several alternatives were considered, as described in the following paragraphs, to address the long-term durability of these areas. The historic character of the structure also required that soffit repairs be developed to mimic the plank formwork look of the original, existing surface. 8.2.2, 8.5 Elimination of water and chlorides will slow the rate of embedded steel corrosion. The adaptive reuse recommendations for the train deck included the new deck joints and drains and the removal and replacement of the entire topside waterproofing, which would eliminate water ingress from the top surface. The LDP also recommended coating the deck soffit with a breathable surface sealer to limit water and chloride ingress. Both of these treatments will slow the rate of deterioration and extend the life of original concrete areas to remain. Nonetheless, periodic maintenance of the deck soffit should be expected. 8.4.7 Electrochemical realkalization of the original concrete areas to remain was also considered to mitigate future corrosion-related damage due to the carbonated concrete. The realkalization process restores the alkalinity of carbonated concrete, thereby increasing its pH to levels that will slow the corrosion rate. The cost and benefits of this treatment did not justify its use in the context of other treatments proposed as part of the adaptive reuse. 8.5.1, 8.5.2, 8.3.1, 8.4.1 The elimination of water leakage through the deck was critical to achieving the desired service life for the repaired structure. Several topside waterproofing/deck protection strategies were developed for the owner’s consideration: a. Buried, fully adhered, flexible, monolithic waterproofing with unbonded concrete wear course b. Bonded, high-performance concrete overlay c. Bonded, thin, polymer-resin-based overlay Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 14: Project Example 3—Adaptive Reuse of Historic Depot141 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES LDP determined that this system would not have the desired durability for this project as it would require significant maintenance and repair due to wear. The owner selected the buried, fully adhered, flexible, monolithic waterproofing with an unbonded concrete wear course as the system that best protected the structure for purposes of achieving the desired 50-year service life. This waterproofing system served to improve the durability of both the repaired and original train deck concrete and mitigate leakage at locations where new cracks could form after the repair program was completed. Installation of the new waterproofing required removal of 23 to 60 in. (580 to 1500 mm) of fill, removal of the existing waterproofing and preparation of the deck to receive the new waterproofing membrane. The LDP developed details and specifications for this work. The LDP also designed a variable thickness concrete protection course to protect the membrane and improve sub-surface drainage beneath the fill. The LDP presented the following alternatives for the owner’s consideration: 1. Fully welded structural steel jacket with sacrificial galvanic anodes (Fig. 14.3 and 14.4). The steel jacket would provide structural confinement, so spiral reinforcement that might corrode in the future would not require repair and would be a barrier to future water and chloride infiltration, which should reduce future corrosion rates. The sacrificial galvanic anodes would provide long-term protection against anticipated ongoing corrosion of original column reinforcement that would remain embedded in chloride-contaminated concrete. Based on consultations with various product and material manufacturers and personal experience, the LDP estimated that this repair would have a service life of approximately 50 years. 2. Structural steel jacket with corrosion-inhibiting admixture (Fig. 14.3 and 14.4). The repair was similar to Alternative 1. The new concrete included a corrosion-inhibiting admixture and the galvanic anodes were omitted. The corrosion-inhibiting admixture would help reduce corrosion of the spiral reinforcement, but was not expected to be effective in preventing ongoing corrosion of the vertical bars that remain embedded in chloride-contaminated concrete. The estimated service life is lower because there is not a direct means to mitigate the anticipated ongoing corrosion of existing vertical reinforcement. Based on consultations with various product and material manufacturers and personal experience, the LDP estimated that this @Seismicisolation repair would have a service life of approximately 20 to 30 years. @Seismicisolation University of Toronto User. Column rehabilitation Several constraints limited the rehabilitation options for the columns. The columns were reinforced with tightly spaced spirals (pitch of less than 3 in. [75 mm]) that would complicate the removal of chloride-contaminated concrete. To gain access behind the vertical bars for concrete demolition and replacement, the spirals would need to be removed. This would create the potential for buckling of vertical bars under construction loads. Shoring was not feasible from a cost and scheduling perspective due to the extensive work associated with timber foundations and other rehabilitation work in the area of the columns. A solution that left the vertical bars in chloridecontaminated concrete with protection provided by alternative corrosion mitigation strategies was required. The steel jackets had been installed for impact resistance and in response to corroded reinforcing steel and concrete deterioration that was apparent many years ago. Split seams in some of the jackets and continued corrosion of the column reinforcement indicated that the reinforcing steel corrosion activity has continued. Accordingly, the LDP judged that the steel jackets had or were close to reaching their effective service life. Therefore, the rehabilitation option would also need to include provisions for impact protection of the column bases. Five foot (1.5 m) tall steel and concrete jackets were considered for impact protection. Installation of the new jackets would require removal of existing steel jackets, removal of chloride-contaminated concrete to the depth of the exterior of the vertical reinforcing bars, installation of new fully grouted steel jackets or bonded reinforced concrete jackets that extended to the column bases, and corrosion mitigation measures. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 142 3. Concrete jacket with sacrificial galvanic anodes (Fig. 14.3 and 14.5). New horizontal hoop reinforcement included in the concrete jacket provided additional structural confinement so existing spiral reinforcement that might corrode in the future would not require repair. New reinforcement would be epoxy-coated to provide resistance to future corrosion. Sacrificial galvanic anodes were recommended to provide long-term protection against anticipated ongoing corrosion of existing column reinforcing bars that remain embedded in chloride-contaminated concrete. The concrete jacket would protrude 2 to 3 in. (50 to 75 mm) beyond the column surface, altering the column appearance. Based on consultations with various product and material manufacturers and personal experience, the LDP estimated that this repair would have a service life of approximately 50 years. 4. Concrete jacket with corrosion-inhibiting admixture (Fig. 14.3 and 14.5). The repair was the same as Alternative 3, except it did not include galvanic anodes and the new concrete included a corrosion-inhibiting admixture. The corrosioninhibiting admixture would help reduce corrosion of the spiral reinforcement, but was not expected to be effective in preventing ongoing @Seismicisolation corrosion of the vertical @Seismicisolation University of Toronto User. Fig. 14.3—Column jacket repair concept. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 14: Project Example 3—Adaptive Reuse of Historic Depot143 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 14.4—Steel jacket repair concept: Alternate 1 (shown); and Alternate 2 (as noted). Concrete repair details 7.4, 7.5.1, 7.5.2, 7.4.1.1, 7.4.1.2, 7.4.5, 7.4.6 Bonding of the new concrete to the existing concrete was considered critical to satisfactory performance of the deck soffit repairs, particularly with regard to underside repairs becoming loose and falling in the future. The research and test results for various repair materials were reviewed to develop appropriate project material specifications @Seismicisolation and procedures for concrete replacement. The horizontal @Seismicisolation University of Toronto User. bars that remain embedded in chloride-contaminated concrete. The estimated service life was lower because there was not a direct means to mitigate the anticipated ongoing corrosion of original vertical reinforcement. Based on consultations with various product and material manufacturers and personal experience, the LDP estimated that this repair would have a service life of approximately 20 to 30 years. If galvanic anodes were used in the column repairs, the size and spacing of the anodes would be determined in consultation with the anode manufacturer. The size and spacing of anodes would be dependent on the amount of reinforcement to be protected, the desired service life extension, and the severity of the environment. Localized, conventional, partial-depth concrete surface repairs would also be required above the new jackets at some columns. Because these repairs were expected to be generally small, localized removal of concrete behind vertical bars could be performed and the column cross section restored. The owner selected corrosion mitigation Alternative 1, fully welded structural steel jackets with sacrificial galvanic anodes, as the option that best met the 50-year service life criteria and maintained the historic character of the structure. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 144 Fig. 14.5—Concrete jacket repair concept: Alternate 3 (shown); and Alternate 4 (described). In addition to the items discussed previously, the concrete repairs included the following features: a. Reentrant corners were avoided in both the repair and existing concrete. 7.6.6, 7.3.3, 7.4 b. After concrete removal work was completed, the exposed concrete surfaces were cleaned and prepared to receive the repair material. To achieve composite, monolithic behavior, replacement concrete was bonded to existing substrate using chemical or mechanical means, or both. 8.4.4 c. Existing reinforcing bars that were exposed in concrete removal areas were cleaned and coated with a corrosion-inhibiting material to reduce future corrosion in and around the concrete replacements, except in areas where galvanic anodes were installed. 8.4.4 d. New epoxy-coated reinforcing bars were lapped with existing bars that were exposed in removal areas and had lost structurally @Seismicisolation significant cross-sectional @Seismicisolation University of Toronto User. shear demand at the interface of the repair and existing concrete was calculated based on the loads and combinations described previously; vu = 45 psi (vu = 0.31 MPa). The calculated design interface shear stress was verified by performing pulloff tests and a mean capacity of 100 psi (0.7 MPa) was determined with the specified surface preparation, such that vu ≤ fvni is satisfied. As part of the field assessment, pulloff testing of the substrate determined that the substrate had adequate strength to achieve the required bond strength. Based on the required bond strength, the LDP concluded that the required bond could be attained by chemical or mechanical means with proper surface preparation (ICRI 310.1R, ICRI 320.2R, and ICRI 210.3R) and repair material application. Therefore, no supplemental reinforcement was required. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 14: Project Example 3—Adaptive Reuse of Historic Depot145 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Contract specifications 1.5.1, 1.6.1, 9.4.1, 10.2.2 The LDP prepared contract documents that specified repair materials that satisfied governing regulatory requirements and that conveyed necessary information to perform the work, including environmental considerations. The LDP used ACI 563 as a source for construction specifications. The specification sections that were referenced included: Section 1—General requirements Section 2—Shoring and bracing Section 3—Concrete removal and preparation for repair Section 4—Formwork Section 5—Reinforcement and reinforcement support Section 6—Conventional concrete mixtures Section 7—Handling and placing of conventional concrete @Seismicisolation @Seismicisolation University of Toronto User. area. The epoxy coating was used as a corrosion-reduction measure. Uncoated bars were used in areas where galvanic anodes were installed. 8.2.2 e. Because much of the existing concrete was scheduled to remain, the as-built reinforcing steel cover would generally not be modified. The corrosion reduction measures incorporated into the repair program were therefore developed to reduce future corrosion activity, offsetting any shallow cover issues. 8.1.1, 8.1.2, 8.1.3 f. The replacement concrete was developed to have similar or slightly enhanced properties compared to the existing concrete and, in particular, was required to have adequate air content for freezing-and-thawing resistance. 7.6.3.3 g. The existing and new reinforcing bars were developed in the existing concrete, the repair concrete, or both. h. Deck soffit repairs were formed with planks to simulate the appearance of the original concrete surface and cast with concrete. Replacement concrete was generally cast from the top deck surface through core holes. 7.1.1, 7.2.1, 7.2.2 i. The repaired sections were designed to have similar strength and stiffness to the originally constructed sections. 7.9.1 j. The repaired slab was designed to have similar fire resistance rating compared to that of the existing slab. 8.5.1, 8.5.2 k. The column surfaces, including the steel jackets, were coated to limit future moisture penetration into the concrete and corrosion of the steel jackets. Appropriate coatings were selected in consultation with the architect and coating suppliers. 9.1c, 9.2.1c l. The LDP established limits for concrete removal and required monitoring of the removal work. If these limits were exceeded, the contractor was required to engage a licensed engineer to verify the integrity of the structure or design shoring, as necessary. 9.2.5 m. The LDP required monitoring of the concrete removal work for loss of reinforcing steel development and possible short-term and long-term structural implications, and for possible structurally significant loss of reinforcement cross-sectional area. n. The LDP required the contractor to notify the LDP if unsafe conditions were encountered or if the in-place reinforcement was different than shown on the contract documents. If unsafe conditions were encountered, additional temporary shoring was specified for installation. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 146 @Seismicisolation @Seismicisolation University of Toronto User. Section 8—Proprietary cementitious and polymer repair materials Section 9—Crack repair by epoxy injection Based on the size of the repairs, conventional concrete and proprietary cementitious and polymer repair materials were specified by the LDP in place of a proprietary material or shotcrete. ACI 563, “Specifications for Repair of Concrete Buildings,” addresses conditions that are unique to the project. The standard has mandatory and nonmandatory requirements checklists at the end of the standard to help the specifier submit as complete a specification as possible. For the adaptive reuse of a historic structure, the main sections from the mandatory and nonmandatory checklists are extracted to include as a minimum in the Project Contract Document: a. Section 1.5.1.1—State the maximum dead and live loads and any temporary reduction in loads, to be permitted during repair and after completion of repair program, in concert with the requirements of 2.1.1.1. b. Section 1.5.2—Designate Owner-approved work areas and schedule requirements. c. Section 1.5.4.1—Show the demarcation line of the project location, specific work areas, and adjacent construction. d. Section 1.8.2.1—Identify work to be performed by certified personnel. e. Section 1.8.2.2(d)—Point out specific repair procedures that require review and approval. f. Section 1.8.2.2(e)—Specify submittal of component materials, repair material mixture proportions or batch requirements, and concrete supplier’s or repair material manufacturer’s QC program. g. Section 1.8.3.2.(d)—Determine frequency of sampling and whether sampling will be performed on a random basis. Indicate testing requirements in accordance with critical design performance requirements. h. Section 2.3.3.2—State whether specialty engineer inspection is required. i. Section 3.1.1.2—Provide the surface profile and remove laitance, debris, and bond-inhibiting materials. j. Section 3.1.3.1—Indicate testing locations, type, number, and frequency of tests. k. Section 3.1.3.1(a)—Determine if pulloff strength testing is required and provide the minimum pulloff strength. l. Section 3.2.1.1—Select the means and methods for concrete removal that will minimize damage to the structure and bruised surfaces on the concrete substrate that remains within and adjacent to the work areas. m. Section 3.1.2.4—Specify whether high-pressure water for concrete removal by hydrodemolition is permitted to be used for the project and permitted locations. n. Section 3.2.1.5—State the required surface profile. o. Section 3.3.1.1—Show the required depth of concrete removal in Contract Documents. p. Section 3.3.4.2 –— Indicate that tensile pull-off tests shall be performed at specified locations in accordance with ASTM C1583/C1583M. q. Section 4.1.2.2—Review the submittal list and indicate in Contract Documents the items to be submitted. r. Section 5.2.1.1—Specify required grades, types, and sizes of reinforcing bars. s. Section 5.3.3.7—Indicate locations of splices. t. Section 6.2.2.6(d)—State the chloride exposure classification for are of work. u. Section 6.2.2.7—Indicate the specified concrete compressive strength, fc′ for the work. v. Section 7.1.2.2—List the information in 7.1.2.2(a) to 7.1.2.2(g) that is to be submitted. w. Section 8.1.2.1—Indicate which repair products require samples, and the quantity and size(s) of samples required. x. Section 9—Repair of cracks by epoxy injection in accordance with ACI 503.7. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 14: Project Example 3—Adaptive Reuse of Historic Depot147 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Construction 9.1b, 9.4.1 The LDP monitored the construction for unexpected conditions that could affect the short-term or long-term safety of the structure. The contractor was required to notify the LDP if reinforcement with 10 percent or more loss of cross-sectional area (ACI 364.10T) was encountered. Temporary shoring or bracing may be necessary (Section 7.1.3). Environmental concerns, such as limiting water with debris to flow into floor drains or off of the site and disposal of construction debris, were specified in conformance with local ordinances. Quality assurance 10.2.1, 10.2.2, 10.4.1 The repair specifications included quality assurance and control measures for material approvals and field verification of qualities. The specified quality control measures and construction observation were performed during the construction, including the following: a. Review of material submittals. 10.2.3 b. Visual inspection of the work in progress. c. Sounding of concrete surfaces to determine if all loose concrete was removed prior to repair. 10.2.3 d. Observation of the prepared concrete surfaces prior to placement of repair materials, and of the concrete placement and curing operations (ICRI 310.1R discusses surface preparation for repair of deteriorated concrete). 10.3.1 e. Testing of repair concrete, including slump, temperature, air content, and compressive strength. f. Bond strength testing of in-place repair concrete to confirm assumption of full composite action between repair materials and existing materials. g. Electrical connectivity testing of the column reinforcing steel and the galvanic anodes. h. Moisture testing by an ICRI-certified floor moisture technician prior to the installation of coatings and waterproofing (ICRI Concrete Surface Repair Testing Technician). Periodic maintenance 1.5.3k Periodic maintenance requirements were discussed with the owner during the selection of the most appropriate repair concepts, and a schedule of recommended monitoring and possible maintenance requirements was provided to the owner at the conclusion of the repair construction, including the following: a. Periodic inspections of the train deck soffit and columns every 3 to 5 years to monitor the condition of the concrete b. Limited concrete deck soffit and column repairs every 5 years c. Injection of leaking train deck cracks every 5 to 10 years d. Coating repair or recoating of concrete and steel jacket surface treatments Record documents 1.6.3, 1.5.3d, 1.5.3j The owner was provided with copies of the project and construction documents and the recommended monitoring and maintenance program. @Seismicisolation @Seismicisolation University of Toronto User. PROJECT CLOSE-OUT Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 148 Description of structure The facility consists of an 11-story office building over a two-story, 100,000 ft2 (9300 m2) parking structure supporting an open-air plaza. The building is located in the northern United States, and construction was completed in 2013. The supported garage slab is a reinforced concrete flat plate, and the plaza slab is a reinforced concrete flat slab with drop panels. Project initiation and objectives Shortly after construction was completed and the certificate of occupancy was obtained excessive deflections and top surface cracking were noted on the supported garage slab. Crack maps of the supported garage slab are shown in Fig. 15.1. The project was initiated to determine the causes of the cracking and deflections and the overall safety of the as-built structure. Governing building codes The building codes adopted by the jurisdiction were determined. Jurisdiction—Northern U.S. city. Original building code—2009 International Building Code (2009 IBC). Current building code—2018 International Building Code (2018 IBC). 1.2.3 1.2.2 Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 15: Project Example 4—Parking/Plaza Slab Strengthening University of Toronto User. Fig. 15.1—Supported garage slab with top surface cracking mapped. ACI 562-16 provision numbers applying to each section of text are shown in red at the top right of each paragraph. @Seismicisolation @Seismicisolation 149 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES 1.2.1, 1.4.1 Existing building code —The jurisdiction had adopted the International Existing Building Code (2018 IEBC). 1.1.2, 1.3.1 ACI 562 supplements the existing building code and governs in all matters pertaining to concrete members in existing buildings, except wherever ACI 562 is in conflict with the requirements in the existing building code in which case the existing building code governs. 1.2.4, 4.1 Design-basis code—Based on a preliminary evaluation as described in Section 4 of this example and considering the requirements of the existing building code, the design-basis code was determined to be the 2009 IBC and, by reference, ACI 318-14. Preliminary evaluation Document review 1.7.1 The design drawings, construction documents, and various reports were available and reviewed by the licensed design professional (LDP). The construction documents and reports confirmed that the concrete and reinforcing bars met the specified material properties. Existing site conditions Strength of as-built structure 1.7.3, 1.7.4 Preliminary analysis—A preliminary analysis was performed for a few locations of the supported garage slab and the plaza slab to estimate the decrease in the as-built strength compared to the design strength due to the documented construction deficiencies; that is, the decreased drop panel thicknesses and the increased concrete cover over the top reinforcing bars. The 2009 IBC was assumed to be the design-basis code for the purposes of the preliminary evaluation. Effects of shallow drop panels—The shallow drop panel condition on the plaza slab decreased the effective depth of the slab reinforcement d, the distance from the extreme compression fiber to the centroid of the longitudinal tension reinforcement, from the design value of 26 3/4 in. (680 mm) to the as-constructed value of 18 3/4 in. (475 mm), a decrease of approximately 30 percent. In accordance with ACI 318-14 Section 10.3, the slab flexural capacity is calculated as follows φM@Seismicisolation = φ (As)(fy)(d){1 – [(ρ)(fy) / (2 (0.85)(f'c ))]} n@Seismicisolation University of Toronto User. 1.7.1, 1.7.2 Existing structural geometry—The existing structural geometry, including typical dimensions and member sizes, was measured on site. The thickness of the drop panels in the plaza slab was measured to be approximately 6 in. (150 mm) compared to the design thickness of 14 in. (355 mm), as shown in Fig. 15.2. 1.7.1 Existing concrete condition—The top surface cracks on the supported garage slab were mapped (Fig. 15.1) and the top surface elevations were surveyed to document the slab deflections. 1.7.1 Reinforcement—The reinforcement layout in the garage slab was documented using ground penetrating radar (GPR) supplemented by exploratory chipping at isolated locations to expose reinforcing bars and confirm the GPR findings. The investigation revealed areas having over 4 in. (100 mm) of concrete cover to the top reinforcing bars compared to the as-designed cover of 0.75 in. (19 mm), as shown in Fig. 15.3. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 150 where φ is the strength reduction factor for tension-controlled flexural sections; Mn is the nominal flexural strength of the section; As is the area of steel reinforcement; fy is the specified yield strength of the reinforcement; ρ is the steel reinforcement ratio, As/bd; and f′c is the specified concrete compressive strength. The slab flexural capacity is directly and indirectly related to d. The measured decrease in d resulted in a calculated flexural deficiency of 30 to 40 percent. 4.3.1, 4.5.1 The calculated demand-capacity ratio of nominal loads of the current building code and factored load combinations of ASCE/SEI 7 to the current in-place nominal capacity of the plaza slab adjusted by the reduction factor in ACI 562 Section 5.4 was 1.3, which is less than 1.5 (Uc/fRcn = 1.3 < 1.5). The LDP assessed the structural Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 15: Project Example 4—Parking/Plaza Slab Strengthening151 University of Toronto User. Fig. 15.2—Illustration of as-designed drop panel thickness on plaza slab compared to as-built drop panel thickness. @Seismicisolation @Seismicisolation GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES 24” TO 30” (610 TO 760 mm) 10” (250 mm) 3/4” (19 mm) CLEAR COVER 3/4” (19 mm) CLEAR COVER AS-DESIGNED 24” TO 30” (610 TO 760 mm) 2” TO 4” (50 TO 100 mm) CLEAR COVER (3” [75 mm] COVER DEPICTED HERE) Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. University of Toronto User. 10” (250 mm) 152 3/4” (19 mm) CLEAR COVER AS-BUILT Fig. 15.3—Illustration of as-designed concrete cover compared to as-built concrete cover for top reinforcing bars of supported garage slab. @Seismicisolation @Seismicisolation slab by calculating the demand-capacity ratio using the strength design demand determined using the nominal loads and factored load combinations of the original building code and the structural slab capacity adjusted by the strength reduction factor of the original building code (Uo/fRcn = 1.18 > 1.0). Therefore, repairs are needed to restore the plaza slab to its pre-damaged state. The slab punching shear capacity is calculated in accordance with ACI 318-14 as follows fVn = φ(4)(√f′c)(bo)(d)ACI 318-14 Eq. (22.6.9.6) (in.-lb units) fVn = φ(0.33)(√f′c)(bo)(d)ACI 318-14 Eq. (22.6.9.6) (SI units) where φ is the strength reduction factor for shear; Vn is the nominal punching shear strength of the section; and bo is the perimeter of the critical section for shear in slabs. Refer to Fig. 15.4 for an illustration of bo and d. Compliance method and design-basis code 4.2.1 Compliance method—For this project, the LDP elected to use the prescriptive compliance method in the 2012 IEBC, Chapter 4, which was previously Chapter 34 of the IBC. Specific minimum construction work requirements are prescribed in this chapter. 4.1.2, 4.1.4 Design-basis code—The construction deficiencies do not constitute substantial structural damage, as defined by the 2012 IEBC. Therefore, the design-basis code for the required strengthening repairs was the 2009 IBC. 1.5.3.1, 1.5.3.1a, 1.5.3.1b, 1.5.3.1c, 1.5.3.1h, 1.5.3.1i Basis of design report—The LDP presented the owner with a basis of design report in which a description of the building was reported; unsafe structural conditions as determined by the preliminary evaluation were listed; and a slab plan with cracks mapped was included in the report as well as the main calculations validating that the existing elevated slabs were unsafe in their present condition. The design-basis code used for the strengthening of the elevated slabs was also listed in the basis of design report. @Seismicisolation @Seismicisolation University of Toronto User. The slab punching shear capacity is also directly related to d. The measured decrease in d resulted in a calculated shear deficiency of 30 percent. Effects of excessive cover—The excessive cover for the top reinforcing bars in the supported garage slab similarly decreased the slab d from the as-designed dimension of 8-3/4 in. (220 mm) to as little as 5-3/4 in. (145 mm), a decrease of approximately 35 percent. Again, the flexural and punching shear capacities were adversely affected, with a calculated flexural deficiency of 15 to 45 percent and a calculated shear deficiency of 18 to 46 percent. 1.5.2, 1.7.2, 4.3.1, 5.4.1 Safety concerns—The LDP determined that the cracking and deflections of the supported garage slab and the gross deviations of the construction from the design were significant safety concerns. The LDP determined that both the supported garage slab and the plaza slab had sufficient calculated capacity to support the estimated dead loads, but did not have sufficient calculated capacity to support the estimated dead loads and the design live loads, even if the strength reduction factors for evaluation permitted by Section 5.4 of ACI 562 were used. The LDP advised the owner that the supported garage slab and the plaza should be immediately removed from service or shored to grade. Accordingly, the owner elected to remove both slabs from service. The owner deemed it prudent to notify the authorities having jurisdiction of the temporary measures that had been taken due to the structural deficiencies. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 15: Project Example 4—Parking/Plaza Slab Strengthening153 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Structural assessment Requirement for structural assessment 6.2.1 Structural deficiency—A structural assessment was necessary due to the structural deficiencies determined in the preliminary analysis. Structural assessment 6.2.4, 6.2.5 Existing structural geometry—The existing structural geometry was documented in more detail than was done for the preliminary evaluation (Section 4.2.1). a. All column spacings, column dimensions, and drop panel dimensions were measured.@Seismicisolation @Seismicisolation University of Toronto User. Fig. 15.4—Illustration of effects of steel bracket or reinforced concrete column capital on punching shear capacity, φVn, of slab. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 154 b. The slab thickness was determined with GPR. The reliability of the measurements was confirmed by physical measurements at several holes drilled through the slab. 6.3.4 Concrete strength—The concrete compressive strength was assumed to be the design strength, as confirmed by the construction testing laboratory reports that were available. Reinforcing steel layout and strength— a. Reinforcing steel spacing and cover were determined at all locations with GPR and confirmed at exploratory openings. Bar sizes were also measured at the exploratory openings. 6.3.4 b. The reinforcing steel tensile strength was assumed to be the design strength, as confirmed by the mill certificates in the construction records. Structural analysis 5.1.2 Load factors and load combinations—The load factors and load combinations were as specified in 2009 IBC and, by reference, ACI 318-14. 6.5.2 Analyses of slab designs—The supported garage slab and the plaza slab were analyzed as two-dimensional plates. These analyses were performed to confirm the accuracy of the computer models and the adequacy of the original slab designs. 6.5.3, 6.5.7 Analyses of as-built slabs—The two-dimensional plate models were modified to reflect the documented as-built construction. The supported garage slab and the plaza slab were then analyzed to determine locations with inadequate calculated structural capacity and the magnitude of the calculated capacity deficiency. Strengthening concepts Two strengthening concepts were considered by the LDP and reviewed with the owner. Strengthening Concept 1 Strengthening Concept 2 Strengthening repairs—The strengthening repairs would include the following activities. @Seismicisolation @Seismicisolation University of Toronto User. 7.4.4, 8.2.1 At locations with excessive concrete cover—On the supported garage slab, the top portion of the slab concrete would be removed and reconstructed with new top bars correctly placed and vertical shear connectors crossing the bond line between the existing and new concrete, as illustrated in Fig. 15.5. 6.7.1 After the removal work, but before the reconstruction work, the slab would be unloaded by jacking so that the entire slab design load, including dead load and live load, would be transferred to the new repaired slab after the repairs have been installed, cured, and the jacks removed. This approach would restore the supported garage slab to its as-designed configuration, thus restoring its design capacity. 7.3.1.1 At locations with thin drop panels—For the plaza slab, steel brackets would be installed on the columns at the underside of the slab. The steel brackets would move the critical punching shear section further from the column, increasing the perimeter of the section, bo, and thus the punching shear capacity (Fig. 15.4). The brackets also would move the critical negative moment section further from the column, decreasing the design negative moment to the moment capacity of the slab section with the reduced drop panel thickness (Fig. 15.6). Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 15: Project Example 4—Parking/Plaza Slab Strengthening155 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 15.5—Illustration of Strengthening Concept 1. a. Reinforced concrete column capitals (Fig. 15.7) would be constructed on the columns at the underside of both supported slabs. At a few short span conditions where there was no positive moment, supplemental drop panels would be constructed on the underside of the supported garage slab. 7.3.1.1 b. At a few locations on the underside of the plaza slab, carbon-fiber-reinforcedpolymer (CFRP) laminate installed by manual lay-up (laminate) would be installed as supplemental flexural reinforcement to allow some moment redistribution from the negative moment regions at the columns. Assessment of strengthening concepts The preliminary details of the strengthening concepts were determined based on the findings of structural analyses performed in Section 5.0, and cost estimates were obtained for both strengthening concepts. Strengthening Concept 2 was estimated to cost approximately 20 percent of the estimated cost of Strengthening Concept 1. Other @Seismicisolation factors such as construction scheduling and sequencing were not @Seismicisolation University of Toronto User. These repairs have the following effects on the structural capacity. a. Punching shear capacity—The column capitals move the critical punching shear section further from the columns, increasing the perimeter of the section and the punching shear capacity (Fig. 15.4). The supplemental drop panels increase the effective slab depth, further increasing the punching shear capacity (Fig. 15.8). b. Design negative moment—The column capitals also move the critical negative moment section further from the columns, decreasing the design negative moment (Fig. 15.6). The supplemental drop panels increase the effective slab depth, increasing the negative moment capacity (Fig. 15.8). c. Moment redistribution—The CFRP reinforcement on the underside of the slab increases the positive moment capacity of the slab and allows some redistribution of negative moments to the positive moment regions. 6.8.1 Load test—The effectiveness of this repair concept would be verified by load test. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 156 RSLAB = (1/4) wℓ1ℓ2 – Slab reaction into column Mu-A-B– = MCL– – RSLAB ℓA-B + (1/2) wℓA-B2 ℓ2 = MCL– – (1/2) wℓA-Bℓ2 (ℓ1/2 – ℓA-B) Mu-REP – = MCL– – RSLABℓREP + (1/2) wℓREP2 ℓ2 = MCL– – (1/2) w ℓREPℓ2 (ℓ1/2 – ℓREP) Fig. 15.6—Illustration of effects of steel bracket or reinforced concrete capital on design negative moment, Mu, of slab. substantially different for the two concepts on this project. Using cost as the key differentiator, the owner elected to pursue Strengthening Concept 2. Structural analysis for repair design 6.6.1, 6.7.1, 6.5.4, 7.2.2, 7.4.1.1, 6.7.3 The effects of the repair process and the installed repairs were analyzed using the two-dimensional plate models of the as-built slabs. The analysis considered the current condition of the slabs, including the cracking, the deflected shape, and the stresses in the slab due to dead loads. The stress increases due to live load in the repaired existing slabs were also evaluated. The adequacy of the bond strength at the interface between the repair material and the existing concrete was evaluated based on Section 16.4.5.1 of ACI 318-14. The analysis assumed full composite action at the repair material interface. @Seismicisolation @Seismicisolation University of Toronto User. where ℓ1 is the length of the slab span in the direction of the moments being determined, measured center-to-center of supports; ℓ2 is the length of the slab span perpendicular to l1, measured center-to-center of supports; and MCL– is the negative moment at column centerline Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 15: Project Example 4—Parking/Plaza Slab Strengthening157 University of Toronto User. Fig. 15.7—Illustration of column capital in Strengthening Concept 2. @Seismicisolation @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES 158 Fig. 15.8—Illustration of effect of increasing drop panel thickness on d, distance from extreme compression fiber to centroid of longitudinal tension reinforcement, and hence on punching shear capacity and negative moment capacity of slab. Design of structural repairs and durability University of Toronto User. 7.1.1, 7.2.2, 7.3.1, 7.5.1, 7.5.2 The strengthening requirements of the repairs were determined based on the findings of the analyses of the original design, the as-built construction, and the repair design. The stiffening effects of the repairs were also evaluated. The repair design included the following details and considerations. 7.3.1, 7.4.4, 7.6.5, 7.5.1 a. The column capitals were designed and detailed to integrate and act compositely with the columns and the slab above. The column surfaces were intentionally roughened and hoop reinforcement was included in the capitals to transfer forces into the columns by shear friction. Self-consolidating concrete (SCC) was used to facilitate filling of the forms to the slab soffit. 7.3.3, 7.3.3.1, 7.4.4, 7.6.5, 7.5.1 b. The supplemental drop panels were also designed and detailed to integrate and act compositely with the columns and slab above. Reinforcing steel extended between the column capitals and the drop panels, and the capitals and drop panels were placed monolithically. Epoxy-grouted dowels were installed in the slab soffit to transfer the horizontal flexural shear by shear friction. SCC was used to facilitate filling of the forms to the slab soffit. 7.8.1, 7.8.2, 1.4.2, 7.4.2, 7.5.1, 7.5.2, 7.9.1, 7.9.3, 7.9.4, 7.9.5, 8.3.1, 8.3.2 c. The CFRP sheets were designed as a supplemental strengthening measure, based on the recommendations of ACI 440.2R. The structural strength of the repaired slab was adequate to carry the factored loads specified in the current building code without the CFRP sheets. The CFRP sheets were used to increase the calculated slab positive moment capacity to account for the increased positive moments due to moment redistribution that occurred before the repairs were installed, and to limit further deflections from these moments. CFRP reinforcing was not a preapproved material in the local jurisdiction, so the design philosophy, product information, and design calculations were presented to the authorities having jurisdiction for approval. The contractor was required to select a CFRP system possessing an Evaluation Service Report (ESR) to verify that the system complied with code requirements as per ACI 440.2R. The CFRP sheets were detailed and bonded to the slab soffit per the @Seismicisolation manufacturers recommenda@Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 15: Project Example 4—Parking/Plaza Slab Strengthening159 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES tions and ACI 440.2R. Bond pulloff testing was performed to verify the bond. The authorities having jurisdiction required that the CFRP sheets be coated with intumescent paint, even though the CFRP sheets would likely debond before the paint became effective in the event of a fire. 8.5.1 d. The injection of epoxy into cracks on the top surface of the supported garage slab was requested by the owner and also served to increase the slab stiffness and seal the cracks against intrusion of water and deicing salts into the concrete, improving the durability of the slab. 8.1.1, 8.1.2, 8.1.3 e. A traffic-bearing elastomeric coating was applied on the top slab surface in the negative moment regions around the columns on the supported garage slab to prevent the intrusion of water and deicing salts into cracks that may not have been sealed and to minimize the intrusion of water and deicing salts into the concrete and improve the durability of the slab. f. As the column capital and drop panel repairs and the CFRP reinforcement were all installed on the undersides of the slabs, the repairs are not directly exposed to the harsh top slab surface service environment and the repairs were judged to be durable. Photographs of the repairs in progress are shown in Fig. 15.9 to 15.12. Contract specifications University of Toronto User. 1.6.1, 9.1c The LDP prepared contract documents that specified repair materials that satisfied governing regulatory requirements and conveyed necessary information to perform the work. The contract documents included the minimum requirements for shoring and bracing for all phases of the repair project, including requirements for the contractor to submit shoring documents that were signed and sealed by an LDP. The LDP used ACI 563 as a source for construction specifications. The specification sections that were referenced included: Section 1—General requirements Section 2—Shoring and bracing Section 3—Concrete removal and preparation for repair Section 4—Formwork Section 5—Reinforcement and reinforcement support Section 6—Conventional concrete mixtures Section 7—Handling and placing of conventional concrete Section 9—Crack repair by epoxy injection Based on the size of the repairs, conventional concrete and proprietary cementitious and polymer repair materials was specified by the LDP in place of a proprietary material or shotcrete. ACI 563, “Specifications for Repair of Concrete Buildings,” addresses conditions that are unique to the project. The standard has a mandatory and nonmandatory requirements checklists at the end of the standard to help the specifier submit as complete a specification as possible. For the adaptive reuse of a historic structure, the main sections from the mandatory and nonmandatory checklists are extracted to include as a minimum in the Project Contract Document: a. Section 1.5.1.1—State the maximum dead and live loads and any temporary reduction in loads, to be permitted during repair and after completion of repair program, in concert with the requirements of 2.1.1.1. b. Section 1.5.2—Designate Owner-approved work areas, and schedule requirements. c. Section 1.5.4.1—Show the demarcation line of the project location, specific work areas, and adjacent construction. d. Section 1.8.2.1—Identify work to be performed by certified personnel. e. Section 1.8.2.2(d)—Point out specific repair procedures that require review and approval. @Seismicisolation @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 160 Fig. 15.10—New supplemental drop panel with capital at various stages of construction: (top) reinforcement and dowels; (middle) formwork with port holes; and (bottom) completed drop panel and capital. f. Section 1.8.2.2(e)—Specify submittal of component materials, repair material mixture proportions or batch requirements, and concrete supplier’s or repair material manufacturer’s QC program. g. Section 1.9.2.1—Indicate if tolerances different from those in ACI 117. h. Section 2.3.3.2—State whether specialty engineer inspection is required. i. Section 3.1.1.2—Provide the surface profile and remove laitance, debris, and bond-inhibiting materials. j. Section 3.1.3.1—Indicate testing locations, type, number, and frequency of tests. k. Section 3.2.1.1—Select the means and methods for concrete removal that will minimize damage to the structure and bruised surfaces on the concrete substrate that remains within and adjacent to the work areas. l. Section 3.3.1.1—Show the required depth of concrete removal in Contract Documents. m. Section 4.1.2.2—Review the submittal list and indicate in Contract Documents the items to be submitted. n. Section 4.3.4.2—Establish if alternative methods for evaluating repair material strength for formwork removal are permitted. o. Section 5.2.1.1—Specify required grades, types, and sizes of reinforcing bars. p. Section 6.2.2.6(d)—State the chloride exposure classification for are of work. @Seismicisolation @Seismicisolation University of Toronto User. Fig. 15.9—New supported parking and plaza slab capitals at various stages of construction: (top) reinforcement consisting of hoops plus supplemental shrinkage reinforcement; (middle) pumping self-consolidating concrete (SCC); and (bottom) completed capital. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 15: Project Example 4—Parking/Plaza Slab Strengthening161 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 15.11—CFRP strip repair: (top) installation; and (bottom) installed and painted sheets. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 162 University of Toronto User. Fig. 15.12—Epoxy injection of cracks on top surface of supported garage slab. @Seismicisolation @Seismicisolation q. Section 6.2.2.7—Indicate the specified concrete compressive strength, fc′ for the work. r. Section 7.1.2.2—List the information in 7.1.2.2(a) to 7.1.2.2(g) that is to be submitted. s. Section 9—Repair of cracks by epoxy injection in accordance with ACI 503.7. Construction 9.1a, 9.1c, 9.2.1a, 9.2.6 The contract documents required the contractor to monitor the construction for any conditions that were not consistent with the available information or that might affect the short-term or long-term safety of the structure, including the possible need for temporary shoring or bracing. 9.4.1 Requirements for environmental issues, such as allowing water with debris to flow into floor drains or off of the site and disposal of construction debris, were specified in conformance with local ordinances. Quality assurance Load test 6.8.1 After the repairs had been installed, a representative portion of the repaired supported garage slab was evaluated by load testing to demonstrate the strength of the repaired slab. The test area was selected based on typical repairs in the area and ease of setting up and running the test. Test procedure 6.8.1, 1.1.2, 1.4.1 ACI 562 references ACI 437.2 for load testing. The 2009 IBC, the design-basis code, references ACI 318-14, which includes Chapter 20, “Strength Evaluation of Existing Structures.” Based on ACI 562 Sections 1.1.2 @Seismicisolation and 1.4.1, ACI 562 governs @Seismicisolation University of Toronto User. 1.5.1, 10.2.1, 10.2.2, 10.4.1 The repair specifications included quality assurance and control measures for material approvals and field verification of quality. The specified quality control measures and construction observations were performed during the construction, including the following: a. Review of material submittals and reinforcement shop drawings. 10.2.3 b. Visual inspection of the work in progress at critical stages of the repair. c. Observation of the prepared concrete surfaces and comparison with ICRI concrete surface profiles (ICRI 310.2R) to verify that minimum roughness had been achieved. d. Observation of the installed reinforcement. e. Periodic inspection and pullout testing of epoxy-grouted dowels in the slab soffit in accordance with ACI 355.4. f. Observation of the concrete placement and curing operations. 10.3.1 g. Testing of repair concrete, including slump flow, air content, temperature, and compressive strength. h. Impact-echo testing to verify the continuity between the slab soffit and the new capitals (Fig. 15.13). i. Observation of the surface preparation and installation of the CFRP sheets. j. Bond strength testing of installed CFRP sheets (ASTM D7522/D7522M). Impact-echo testing was performed on the top slab surface over drop panel and capital repairs to detect possible gaps between the slab soffit and the repairs. Some areas with gaps were detected (Fig. 15.13). Open joints between the slab soffit and drop panel and capital repairs were injected with epoxy (Fig. 15.14) to fill the joints and bond the repairs to the soffit. Continuity was confirmed by impact-echo testing. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 15: Project Example 4—Parking/Plaza Slab Strengthening163 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 164 University of Toronto User. Fig. 15.13—Impact-echo testing of joint between slab soffit and capital: (top) test in progress; and (bottom) field notes of areas with open joints to be injected with epoxy. for all matters pertaining to evaluation and shall govern when in conflict with other referenced standards. Accordingly, the monotonic load test procedure described in ACI 437.2 was used for the evaluation. The monotonic load test was selected after consultation with the contractor’s available means, methods, and familiarity with the monotonic test. The test procedure included the following details. Loading—The test load magnitude (TLM) was calculated per ACI 437.2 Section 4.2.2. @Seismicisolation @Seismicisolation TLM = 1.3 (DW + DS) TLM = 1.0DW + 1.1DS + 1.6L + 0.5 (Lr or S or R) TLM = 1.0DW + 1.1DS + 1.6 (Lr or S or R) + 1.0L where Dw is load due to self-weight of the concrete structural system; Ds is superimposed dead load other than self-weight of structural system; L is live load due to use and occupancy of the building; Lr is roof live load produced during maintenance by workers, equipment, and materials or by moveable objects or people; S is snow load; and R is rain load. Fig. 15.14—Epoxy leakage from injection of gap between slab soffit and capital. Δr < Δ1/4 or Δ1 < 0.05 in. (1.3 mm) or Δ1 < ℓt/2000 and @Seismicisolation @Seismicisolation University of Toronto User. The test loads were applied by hydraulic jacks (Fig. 15.15) that reacted against the soffit of the plaza slab. Back-up shoring was installed underneath the supported garage slab. The jack arrangement included two interior panels of the supported garage slab (Fig. 15.16). Instrumentation—Instrumentation included load cells (Fig. 15.15) to measure the load applied by the jacks; cable-extension transducers (Fig. 15.17) to measure vertical deflections; strain gauges (Fig. 15.17) to measure the strain in individual reinforcing bars; Whittemore strain gauges to measure strains in the concrete; and linear variable differential transformers (LVDTs) for measuring crack widths. All of the instrumentation was wired to a data acquisition system. Test setup—The test setup is shown in Fig. 15.18. Test procedure—The test procedure (ACI 437.2 Section 5.3) consisted of applying the load in four equal increments; holding the load after each increment for deflection measurements; holding the total load for 24 hours; and releasing the load as quickly as practicable. Acceptance criteria—The acceptance criteria (ACI 437.2 Section 6.3) included the following items Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 15: Project Example 4—Parking/Plaza Slab Strengthening165 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Δ1 < ℓt / 180 where Δ1 is the measured maximum deflection; ℓt is the shorter span under load for a two-way slab; and Δr is the measured residual deflection. Fig. 15.15—Load application: (left) jacks at plaza slab soffit, on towers; and (right) close-up of jack with load cell (arrow) on top. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 166 University of Toronto User. Fig. 15.16—Arrangement of jacks. @Seismicisolation @Seismicisolation Test results The load results are summarized as follows: a. Δ1 = 0.558 in. < 1.63 in. passed test (Δ1 = 14.2 mm < 41.4 mm passed test) b. Δr after 24 hours: 0.125 in. < 0.139 in. (Δ1 / 4) passed test (3.2 mm < 3.5 mm (Δ1 / 4) passed test) The repaired structure passed the load test. The measured maximum deflection from the load test corresponded with calculated deflections based on the gross moment of inertia, Ig, in the negative moment regions where surface cracks had been injected and the cracked moment of inertia, Icr, in the positive moment regions that had not been injected. @Seismicisolation @Seismicisolation University of Toronto User. Fig. 15.17—Instrumentation: (top) cable-extension transducer; and (bottom) strain gauge on reinforcing bar. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 15: Project Example 4—Parking/Plaza Slab Strengthening167 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 15.18—Test setup. (Note: data acquisition equipment in lower right corner.) PROJECT CLOSE-OUT Periodic maintenance 1.5.3k The LDP recommended that a visual inspection of the repaired structure be performed 1 year after the repair installation to verify that no unanticipated behavior had occurred. The LDP also recommended periodic monitoring and maintenance of crack repairs, traffic bearing membranes, and CFP. The northern climate dictated that these durability maintenance issues be monitored. Record documents 1.6.3, 1.5.3d, 1.5.3j The owner was provided with copies of the project and construction documents and the recommended monitoring and maintenance program. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 168 University of Toronto User. @Seismicisolation @Seismicisolation Description of structure The facility is a water treatment plant in the northern United States. The plant includes a concrete framed structure that houses water treatment tanks and a pump room. The plant began operation in 2018 and is not accessible to the general public. The roof over the steel tank area (Fig. 16.1) includes 43 precast, prestressed concrete double tees and the roof over the pump room includes five double tees. The double tees are generally 12 ft (3.7 m) wide and 28 in. (710 mm) deep, and span from 59 to 72 ft (18.0 to 21.9 m). In the west bay, the double tees are 24 in. (610 mm) deep and span approximately 31 ft (9.4 m). Along the south side of the facility the double-tee widths decrease to 8.5 ft (2.6 m). The ends of the double tees are dapped, as shown in Fig. 16.2. For the 28 in. (710 mm) deep double tees, the daps are typically 16.5 in. (420 mm) long by 10.5 in. (267 mm) deep. The steel tank area measures approximately 230 x 132 ft (70.1 x 40.2 m) in plan, and the adjacent pump room measures approximately 62 x 60 ft (18.9 x 18.3 m) in plan, as shown in Fig. 16.3. Project initiation and objectives Shortly after construction, the owner’s personnel observed a wide diagonal crack in the stem at the end of a double tee (Fig. 16.4). Further inspections revealed fine diagonal cracking at the ends of other double-tee stems. A temporary retrofit was designed and installed for the severely cracked member as an emergency safety measure. The owner then retained a licensed design professional (LDP) experienced in the investigation and repair of problems with existing structures to determine the cause of the cracking, assess any structural implications, and develop long-term repair details, as necessary. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 16: Project Example 5—Precast/Prestressed Double-Tee Repair University of Toronto User. Fig. 16.1—Precast, prestressed double-tee roof members over steel tank area. ACI 562-19 provision numbers applying to each section of text are shown in red at the top right of each paragraph. @Seismicisolation @Seismicisolation 169 Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 170 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 16.2—Dapped ends of double tees. Governing building codes Based on discussions with the building officials, the building codes adopted by the jurisdiction were determined. Jurisdiction—Northern U.S. city Original building code—2009 International Building Code (2009 IBC) Current building code—2018 International Building Code (2018 IBC) 1.2.3 1.2.2 1.2.1 Existing building code—The jurisdiction has adopted the 2018 International Existing Building Code (2018 IEBC) 1.1.2, 1.4.1, 1.4.2 ACI 562 supplements the existing building code and governs in all matters pertaining to concrete members in existing buildings, except wherever ACI 562 is in conflict with the requirements in the existing building code in which cases the 2012 IEBC @Seismicisolation governs. @Seismicisolation University of Toronto User. Fig. 16.3—Roof plan over steel tank area and pump room, showing double tee layout. 1.2.4 Design-basis code—Because the jurisdiction has adopted a general existing building code, ACI 562 Section 1.2.4 specifies that the design-basis code shall be determined in accordance with ACI 562 Chapter 4 or Appendix A. If a jurisdiction has adopted the IEBC, as in this example, Chapter 4 applies. 4.2 The Prescriptive Method was selected for compliance. The Prescriptive Method (2018 IEBC Chapter 4) allows existing materials in use to remain in use unless determined to be unsafe. New and replacement materials as permitted for new construction may be used. Under repair scenarios, vertical gravity load-carrying components that have sustained substantial structural damage are required to be rehabilitated to comply with the current building code. Snow loads are required to be considered if the substantial structural damage was caused by snow load effects. Existing gravity load-carrying members are permitted to be designed using original design loads. Undamaged gravity load-carrying members receiving loads from the rehabilitated member are required to be shown to have sufficient capacity to carry the design loads of the rehabilitation design. 1.7.1 A preliminary assessment was performed to investigate the extent of structural damage, from which a determination of the design basis requirement could be made. Preliminary assessment 1.7.1 The precast concrete shop drawings, including erection plans, individual precast piece drawings, connection details, and design calculations were available and reviewed by the LDP. Existing site conditions Design strength of existing structure 1.7.1, 1.7.2, 1.7.3 The precast concrete shop drawings and design calculations were reviewed. The loads were in accordance with the original building code. The design shear strength of a typical double-tee stem end was based on the procedures of ACI 318-08, as referenced by the 2009 IBC. The as-designed shear strength was confirmed to be adequate for the design load effects. Findings of preliminary assessment 6.2.1 Initially, a wide diagonal crack was noted at the end of only one double-tee beam. A temporary retrofit had been installed at this location. The preliminary assessment documented relatively fine diagonal cracks at the ends of many of the other tee beam ends and confirmed that the as-designed shear strength was adequate. At this point, it was unclear if the fine diagonal cracks were indicative of unusual structural behavior and, perhaps, a structural deficiency, @Seismicisolation or if the cracks were just @Seismicisolation University of Toronto User. 1.7.1 Existing structural geometry—The layout and dimensions of the double tees were determined to be in conformance with the precast concrete shop drawings. 1.7.1, 1.7.2 Existing concrete condition—Accessible double-tee stem ends were visually inspected from various walkways and catwalks. Binoculars and ladders were used where appropriate. Over 75 percent of the double-tee stem ends were observed. It was determined that the stem adjacent to the daps had an apparent concrete shear cracking problem, as illustrated in Fig. 16.4 and 16.5. 1.7.1 Reinforcement—The precast concrete shop drawings detailed the prestressing steel and vertical reinforcement in the stems, and the reinforcement at the ends. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 16: Project Example 5—Precast/Prestressed Double-Tee Repair171 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES normal concrete behavior. The owner reported no excessive loads, including snow loads, that could have caused the observed damage. 1.7.2, 1.7.5, 6.2.2, 6.2.3, 4.5, 4.5.1, 6.1.1 The LDP recommended to the owner that further investigative studies be performed to verify the as-built construction and determine the structural implications of the Shear crack Splitting Fig. 16.4—Diagonal shear and longitudinal splitting cracks observed at end of double-tee stem. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 172 University of Toronto User. Fig. 16.5—Typical types of cracking observed at ends of@Seismicisolation double-tee stems. @Seismicisolation cracking. The LDP notified the owner that the diagonal cracks might be indicative of a potential safety concern. The LDP recommended that a structural assessment per ACI 562 Section 6.1.1 be performed as soon as possible. The LDP recommended that the structural assessment include both a structural assessment and structural analysis. As the cracks were relatively fine at this time, the LDP recommended that the crack widths be visually monitored and determined that temporary shoring was not necessary given the timing of the investigation and potential repairs would take place between April and October to minimize the likelihood of snow load. Design-basis code 1.2.4, 1.7.1 Based on the work completed by the LDP, there was reason to suspect that the as-built construction may differ from the precast concrete shop drawing details. The condition did not meet the definition of substantial structural damage as given in IEBC. Accordingly, the LDP concluded that repairs could be designed to restore the members to their original design capacity based on material properties and design strengths applicable at the time of original construction. (2012 IEBC Section 404.4). Therefore, repairs would be required to meet the requirements of the original building code (2009 IBC), which references ACI 318-08. Structural evaluation Existing site conditions @Seismicisolation @Seismicisolation University of Toronto User. 6.2.4 Existing structural geometry—The existing structural geometry was documented in more detail than was done for the preliminary assessment (Section 1.7). a. Double-tee spans, widths, and stem depths and widths were measured. b. The flange thicknesses were determined with ground-penetrating radar (GPR) that was calibrated by physical measurements at holes drilled through the flange. 6.1.1, 6.2.4, 8.1.2 GPR uses electromagnetic waves that are transmitted into the member to discern internal objects within the concrete. The waves reflect off material interfaces and the optical reflections are processed to determine the location and depth of reinforcing bars. Reflected waves off of the back side of the member can also be used to determine the member thickness (ACI 228.2R-13). 6.3.1 Reinforcing steel layout and strength—Reinforcing steel spacing and cover were determined with GPR and confirmed at exploratory openings (Fig. 16.6 and 16.7). The steel yield strength was assumed to conform to the steel grades specified on the precast concrete shop drawings. 6.2.4 The location of the reinforcing steel was determined at 41 stem ends. At five of the stem ends, the vertical reinforcement started within 10 in. (255 mm) of the dapped end. At the other 36 locations, or almost 90 percent of those inspected, the vertical reinforcement started 1 ft-6 in. to 7 ft-7 in. (0.46 to 2.31 m) from the dapped end, with most of the reinforcement starting 4 to 6 ft (1.2 to 1.8 m) from the dapped end. A typical GPR scan and marked-up dapped end illustrating the location of the first vertical reinforcing bar is shown in Fig. 16.8. The as-built construction is illustrated in Fig. 16.9. 6.3.4 Concrete strength—Concrete cylinder tests performed during fabrication indicated that the concrete achieved its design strength. No visible deterioration of the concrete was observed. The concrete strength was therefore assumed to be 5500 psi (37.9 MPa), as shown in the shop drawings. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 16: Project Example 5—Precast/Prestressed Double-Tee Repair173 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 16.6—Ground-penetrating radar (GPR) survey in progress. Reinforcing bar Fig. 16.7—Vertical reinforcement exposed at exploratory opening along shear crack. Structural analysis for evaluation Load factors and load combinations—The load factors and load combinations were as specified in the 2009 IBC, which references ACI 318-08. 6.5.2 Analysis—The shear strength at the as-constructed beam ends was calculated according to the provisions of ACI 318-08. It was determined that the calculated shear strength provided by the concrete alone was less than the design shear force, necessitating shear reinforcement per the provisions of ACI 318-08. Accordingly, the original design included vertical reinforcing steel at the ends of the double-tee stems adjacent to the daps. The GPR testing found that vertical reinforcing was mislocated or missing. Consequently, @Seismicisolation the stems had inadequate calculated strength that resulted in the @Seismicisolation University of Toronto User. Shear crack Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 174 Start of vertical Fig. 16.8—Gap at end of stem before start of vertical reinforcement: (top) GPR scan of cracked double-tee stem shown in Fig. 16.4 (WWR is welded wire reinforcement); and (bottom) markup of vertical reinforcement on double-tee stem. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 16: Project Example 5—Precast/Prestressed Double-Tee Repair175 University of Toronto User. Fig. 16.9—Illustration of as-built double-tee stem construction, showing gap from @Seismicisolation end of dap to start of vertical reinforcement. @Seismicisolation GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES observed diagonal cracking. The absence of vertical reinforcement also meant that, after cracking had initiated, there was inadequate steel to limit the crack widths. As shown in Fig. 16.9, the ends of the double-tee stems also have vertical, C-shaped hanger bars adjacent to the daps. In many locations the bottom horizontal hook extensions of the hanger bars had little concrete side cover. Small side cover results in less concrete resistance to splitting along the bond length of the hook, causing splitting cracking of the concrete at lower than anticipated bond stresses. The splitting cracking reduces the development of the bar and the transfer of stresses between the bar and the surrounding concrete. Based on the side cover measured on some beams, ACI 318-08 provisions were used to predict the likelihood of the observed horizontal splitting cracking. Well-detailed vertical reinforcement along the hanger bar bottom hooks would limit the splitting crack widths. The absence of this reinforcement meant that, after cracking had initiated, there was no steel to limit the crack widths. Structural safety Repair/replacement options 1.5.3f, 1.5.3g Four repair/replacement options were considered: 1. Complete replacement of the double-tee roof with new precast members 2. Strengthening of the double-tee ends by concrete jacketing 3. Strengthening of the double-tee ends with steel plates 4. Strengthening of the double-tee ends with carbon fiber-reinforced polymer (CFRP) Repair/replacement Option 1 This option included the complete removal of the roof over the steel tank area and the pump room and the installation of a new double-tee roof and a new roofing system. This option would be very disruptive to operations as a temporary protection/weatherproofing platform would need to be constructed underneath the existing roof structure and all attachments to the underside of the double tees such as lights, conduits, and pipes would need to be temporarily relocated. Also, the existing facility and grounds caused staging difficulties for the large crane necessary for the @Seismicisolation removal and replacement of the double tees. @Seismicisolation University of Toronto User. 1.5.1, 4.3.1, 1.5.2, 1.7.2 The observed diagonal cracking at the ends of most of the double-tee stems and the mislocated or missing vertical reinforcement in these areas made it difficult to reliably assign a concrete shear capacity at these locations. However, as shown in Fig. 16.9, there were horizontal reinforcing bars in the dapped end, attached to the bearing plate, and vertical hanger bars that extended across the diagonal cracks, providing a nominal shear transfer mechanism and some ductility at the cracks. The horizontal reinforcement and vertical hanger bars provided some ductility at the double-tee ends and prevented the complete failure of the double tees. The owner was advised of the precarious and unsafe nature of the present structural conditions, and the urgency of addressing the unsafe conditions. The owner was also advised that if repairs were delayed, the double-tee stems should be visually surveyed and monitored for increased distress on a monthly basis. The recommendation was also made to limit roof live and snow loads by removing accumulated snow. 1.5.3a, R1.5.3b, 1.5.3c, R1.5.3d, 1.5.3e The LDP provided the owner with a basis of design report providing a description of the structure, identifying the structural system, and listing the codes used for the design and construction of the structure. The basis of design report also included documentation of unsafe structural conditions in the work area as presented previously and identified members that required strengthening. Four rehabilitation options were presented to the owner along with the advantages and disadvantages of each option along with the recommendation of the LDP. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 176 Repair/replacement Option 2 This option consisted of constructing reinforced concrete jackets at the ends of the double-tee stems, as shown schematically in Fig. 16.10. The jackets would increase the stem width from 6 in. (150 mm) to 12 to 15 in. (305 to 380 mm). The new reinforcement would provide the vertical shear capacity and confinement steel that was lacking at numerous existing tee stems. 7.4, 7.5.2 This work would require significant field labor to prepare the concrete surfaces, place the reinforcement, form the jackets, and then place the concrete. Enclosed temporary work platforms would be necessary at the ends of the double tees to access the undersides of the double-tee stems and contain dust and other debris from the construction activities. As an alternate, a permanent catwalk was also considered. In either case, the cost for the temporary work platforms or new catwalk was substantial. 7.3.1.1 This option would require additional engineering considerations and analysis of the original design. For example, the concrete jackets would add dead weight to the double-tee stem ends and thus the cast-in-place girders that support the double tees would have to be evaluated for the additional loads. Repair/replacement Option 3 7.5.2 This option consisted of installing steel-plate assemblies at the ends of the double-tee stems, as shown schematically in Fig. 16.11. The assemblies would provide the necessary shear capacity and confinement at the ends of the double-tee stems. 7.3.1.1 This work would require field labor to install the plate assemblies. The various plates would have to be sized so that one or two iron workers could handle them. Enclosed temporary work platforms would be necessary at the ends of the double tees to access the undersides of the double-tee stems and contain dust and other debris from the construction activities. As an alternate, a permanent catwalk was also considered. In either case, the cost for the temporary work platforms or new catwalk was substantial. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 16: Project Example 5—Precast/Prestressed Double-Tee Repair177 University of Toronto User. Fig. 16.10—Schematic of Repair/replacement Option 2, reinforced concrete jacket. @Seismicisolation @Seismicisolation GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 16.11—Schematic of Repair/replacement Option 3, steel-plate assembly. 8.1, 8.4.1, 8.4.6 As the environment may have elevated humidity, corrosion protection would need to be considered for the exposed as well as the concealed steel surfaces. A high-quality paint system could be applied, but periodic maintenance would be expected. Alternately, stainless steel plates could be used; in this case, however, workers with experience in stainless steel fabrication and welding would have to be employed. Repair/replacement Option 4 @Seismicisolation @Seismicisolation University of Toronto User. 7.5.2 This option consisted of installing externally bonded, CFRP strips at the double-tee stem ends, as shown schematically in Fig. 16.12. This repair would be relatively easy to install over open water tanks; very lightweight, thereby not affecting supporting structural elements; and could be finished with a surface coating to enhance the aesthetics of the beam end repair area and maintain the overall appearance of the structure. This work would require trained field labor experienced with FRP installation to prepare the concrete surfaces and install the CFRP strips. Enclosed temporary work platforms would be necessary at the ends of the double tees to access to the undersides of the double-tee stems and contain dust and other debris from the construction activities. As an alternate, a permanent catwalk was also considered. In either case, the cost for the temporary work platforms or new catwalk was substantial. 7.4.1, 7.4.2 The success of a CFRP system relies on adequate bond to the substrate. The risk of bond failure could be mitigated with a good quality assurance/quality control program, including selection of a proven, high-quality repair system and an experienced installation contractor, regular observation of the installation, and testing for debonding and bond strength of the installation. Once properly installed, the CFRP strips would be expected to perform throughout the anticipated service life of the structure. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 178 Fig. 16.12—Schematic of Repair/replacement Option 4, carbon fiber-reinforced polymer (CFRP) reinforcement. 7.9 A second concern is damage to the repair due to fire. Considering the lack of flaMmable material housed or generated in the treatment process, the possibility of a fire in this facility appeared quite low. A natural gas pipeline in the facility could create a torch effect if the pipe ruptures, but existing emergency shut-offs mitigate this occurrence. Heat shields/deflectors could also be considered at repair areas above this pipeline. DESIGN OF STRENGTHENING REPAIRS Structural analysis for repair design 6.7.1, 7.2.1, 7.2.2 The structural analysis for repair followed the provisions of the 2009 IBC to determine the repair design forces. The means and methods for the CFRP installation require minimal equipment and construction loadings. Nonetheless, the effect of these loads were evaluated to assess the safety of the double-tee members during construction. @Seismicisolation @Seismicisolation University of Toronto User. Evaluation of repair/replacement options The costs of each of the repair/replacement options were estimated. Options 1 and 4 had similar estimated costs and Options 2 and 3 also had similar estimated costs that were approximately double the estimated costs of Options 1 and 4. The cost to access the repair areas for Options 2, 3, and 4 included temporary scaffolding or a new catwalk system represented over 40 percent of the repair cost, and was the primary factor that caused the costs between Option 1 and 4 to be so closely related despite the fact that Option 1 included the complete removal and replacement of the double-tee members. Based on cost and interruption to operations, the owner elected to pursue Option 4. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 16: Project Example 5—Precast/Prestressed Double-Tee Repair179 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Design of strengthening repairs 7.8.1, 7.8.2 Design provisions—The structural design of the CFRP repairs was in conformance with the provisions of ACI 440.2R. The provisions of ACI 440.2R are based on the provisions of ACI 318. 5.5, 7.8.2 Strength of existing members—The cracks at the ends of the double-tee stems would be injected with epoxy to restore the sections to their uncracked condition. For rehabilitation achieved with external reinforcing systems, ACI 562 requires that the structural members without rehabilitation have capacity to equal or exceed the effects of the load combinations specified in ACI 562 Sections 5.5.2 and 5.5.3. 5.5.2 The nominal shear strength, (Vn)unc, of the existing unstrengthened concrete sections were calculated and were found to exceed the minimum strength required by ACI 562 Eq. (5.5.2a) and (5.5.2b). (φVn)unc > 1.1D + 0.5L + 0.2S (5.5.2a) (φVn)unc > 1.1D + 0.75L (5.5.2b) where φ is the strength reduction factor for shear; D is the dead load effect; L is the live load effect; and S is the specified snow load. These load combinations are intended to minimize the risk of overload or damage to the existing unstrengthened elements in the case where, during normal operating conditions, the external reinforcement is damaged. This would allow the structure to remain in service until the damage to FRP is repaired. 5.5.3 To ensure adequate member strength during a fire event, ACI 562 requires that strength of the structural member without externally applied CFRP satisfy ACI 562 Eq. (5.5.3) fex Rn > (0.9 or 1.2)D + 0.5L + 0.2S (5.5.3) fVn = φ (Vc + Vs + ψfVf) where Vc is the nominal shear strength provided by the concrete; Vs is the nominal shear strength provided by the reinforcing steel, in this case ‘0’; ψf is the additional CFRP strength reduction factor, suggested as 0.85 by ACI 440.2R-08; and Vf is the nominal shear strength provided by the CFRP stirrups. @Seismicisolation @Seismicisolation University of Toronto User. where fex = 1.0; and Rn is the nominal resistance of the structure, calculated using the reduced material properties due to effects of fire, determined based on the required fire rating duration. The dead load factor of 0.9 governs when the dead load effect reduces the total factored loads effect. Considering the lack of flammable material housed or generated in the treatment process, the possibility of a fire in this facility appeared quite low. Based on these conditions, it was concluded that fire evaluation is not required for this application. 4.3.1 As there was no roof live load expected during the repair installation, the LDP determined that shoring would not be necessary to prevent recracking of cracked sections after epoxy injection and before the CFRP repairs were installed. The owner was advised not to access the roof while repairs were curing. 7.1.1, 7.5.1, 7.5.2 Strength of repaired members—The nominal shear strengths, Vn, of the repaired members were calculated as suggested by ACI 440.2R-08 Eq. (11-2) Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 180 The nominal shear strength provided by the concrete was calculated by ACI 318-08 Eq. (11-3) Vc = 2 ( fc′ ) bwd Vc = 0.17 ( fc′ ) bwd (in.-lb units) (SI units) where fc' is the concrete compressive strength; bw is the stem width; and d is distance from the extreme compression fiber to the centroid of the longitudinal tension reinforcement. The nominal shear strength provided by the CFRP stirrups was calculated as suggested by ACI 440.2R Eq. (11-3) Vf = (Afv ffe (sin α + cos α) dfv) / sf where Afv is the area of CFRP shear reinforcement with the spacing sf; ffe is the effective stress in the CFRP; α is angle of inclination of the CFRP shear reinforcement relative to horizontal; dfv is the effective depth of the CFRP shear reinforcement; and sf is the horizontal spacing of the CFRP shear reinforcement. The effective stress in the CFRP was calculated as suggested by ACI 440.2R-08 Eq. (11-5) ffe = εfe Ef where εfe is the effective strain in the CFRP reinforcement attained at failure; and Ef is the tension modulus of elasticity of CFRP. For bonded U-wraps, the effective strain in the CFRP reinforcement attained at failure is calculated as suggested by ACI 440.2R-08 Section 11.4.1.2 εfe = κν εfu < 0.004 The design rupture strain was calculated as suggested by ACI 440.2R-08 Eq. (9-4) εfu = CE εfu* where CE is an environmental reduction factor—0.95 for carbon fiber in internal exposures (ACI 440.2R, Table 9-1); and εfu* is the ultimate rupture strain of CFRP reinforcement. DESIGN OF STRUCTURAL REPAIRS AND DURABILITY Development and bond of CFRP strips 7.6.3.3 Development—To develop the effective stress in the CFRP, the active bond length Le was calculated as suggested by ACI 440.2R-08 Eq. (11-8) Le = 2500 / (ntfEf)0.58 (in.-lb units) Le = 23,300 / (ntfEf)0.58 (SI units) where n is the number of plies of CFRP reinforcement; tf is the nominal thickness of one ply of CFRP reinforcement; Ef is the tensile modulus @Seismicisolation of elasticity of the CFRP. @Seismicisolation University of Toronto User. where κν is a bond reduction coefficient defined in Section 11.4.1.2; and εfu is the design rupture strain of CFRP reinforcement. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 16: Project Example 5—Precast/Prestressed Double-Tee Repair181 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES The required development was provided by the installation details. 7.8.1 Bond—Bond of the CFRP strips to the concrete was critical to the success of the repair. Surface preparation included grinding protrusions and undulations on the concrete surfaces, and all corners to the radius prescribed by the CFRP manufacturer; and sandblasting the concrete surfaces to remove contaminants and laitance. After the CFRP strips had been installed, bond pulloff testing was performed to verify the quality of the bond in accordance with ASTM D7522/D7522M. Acceptance of CFRP repairs by the authorities having jurisdiction 7.8.1 Repair material—CFRP reinforcement in accordance with ACI 440.8 is a permitted repair material in ACI 562, which in this case has been adopted as a supplement by the local jurisdiction. 7.9.1, 7.9.3, 7.9.4 Performance under fire and elevated temperatures—The potential for fire and elevated temperatures at the repair locations was evaluated and reviewed with the authorities having jurisdiction. It was noted that there were no flammable materials in the steel tank area and that the treatment process did not generate flammable materials, so that the probability of fire in this area appeared quite low. A natural gas pipeline in this area could create a torch effect if the pipe ruptured, but the pipe included emergency shut-offs to mitigate this occurrence. 5.5.1, 5.5.2, 5.5.2.1, 5.5.3, 7.9.2 Heat shields/deflectors could also be installed at repair areas above this pipeline. The owner and the authorities having jurisdiction found these considerations persuasive and no supplemental fire protection was required. Durability of repairs Aesthetics of repairs The CFRP repairs were coated with an acrylic coating to blend the repairs with the adjacent concrete. The coating also provided protection to the epoxy from the degradation effects of ultraviolet light, which in an interior exposure were minimal. Contract specifications 1.6.1 The LDP prepared contract documents that specified repair materials that satisfied governing regulatory requirements and that conveyed necessary information to perform the work. The LDP used ACI 563 as a source for construction specifications. The specification sections that were referenced included: Section 1—General requirements Section 2—Shoring and bracing Section 9—Crack repair by epoxy injection Based on the size of the repairs, conventional concrete and proprietary cementitious and polymer repair materials were specified by the LDP in place of a proprietary material or shotcrete. ACI 563, “Specifications for Repair of Concrete Buildings,” addresses conditions that are@Seismicisolation unique to the project. The standard has mandatory and nonmandatory @Seismicisolation University of Toronto User. 8.1.1, 8.1.2, 8.1.3, 8.3.1, 8.3.2, 8.4.1, 8.5.1 The durability of the repair materials and the repairs was considered. The service environment was an interior space with no special exposures, such as to acids or moisture, or other potentially deleterious conditions. Cracks at the ends of the double-tee stems would be injected with epoxy to restore the concrete strength and seal the cracks, and the repairs addressed the causes of the cracking. Corrosion was not an issue in this environment, so no special corrosion-resistance measures or surface treatments were necessary. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 182 requirements checklists at the end of the standard to help the specifier submit as complete a specification as possible. For the adaptive reuse of a historic structure, the main sections from the mandatory and nonmandatory checklists are extracted to include as a minimum in the Project Contract Document: a. Section 1.5.1.1—State the maximum dead and live loads and any temporary reduction in loads, to be permitted during repair and after completion of repair program, in concert with the requirements of 2.1.1.1. b. Section 1.5.2—Designate Owner-approved work areas, and schedule requirements. c. Section 1.5.4.1—Show the demarcation line of the project location, specific Work areas, and adjacent construction. d. Section 1.8.2.1—Identify work to be performed by certified personnel. e. Section 1.8.2.2(d)—Point out specific repair procedures that require review and approval. f. 1.8.2.2(e)—Specify submittal of component materials, repair material mixture proportions or batch requirements, and concrete supplier’s or repair material manufacturer’s QC program. g. 1.8.3.2(d)—Determine frequency of sampling and whether sampling will be performed on a random basis. Indicate testing requirements in accordance with critical design performance requirements. h. Section 2.3.3.2—State whether specialty engineer inspection is required. i. Section 9—Repair of cracks by epoxy injection in accordance with ACI 503.7. Construction Quality assurance 1.5.1, 10.2.1, 10.2.2, 10.4.1 The repair specifications included quality assurance and control measures for material approvals and field verification of quality. The specified quality control measures and construction observations were performed during the construction, including the following: a. Review of material submittals b. Review of sealed calculations submitted by the CFRP manufacturer, confirming the design details c. Review of shop drawings of the CFRP layouts d. Review of contractor qualifications, including previous experience installing CFRP strips and certified training by CFRP manufacturer e. Inspection of each stem end for cracks to inject. GPR testing to confirm the as-built reinforcement and determine the exact extent of CFRP reinforcement f. Required presence of a representative of the CFRP manufacturer at the site during the early stages of the installation g. Visual inspection of the work in progress @Seismicisolation @Seismicisolation University of Toronto User. 9.1c, 9.2.1a, 9.2.1b, 9.4.1 As discussed in Section 5.4, the LDP evaluated the need for temporary shoring and bracing and determined that none was required. The as-constructed condition was sufficient for dead loads. The owner was notified to ensure no live load would be present. Additionally, repairs were to be completed prior to the winter season such that snow loads would not be present. The contract documents required the contractor to monitor the construction for any conditions that were not consistent with the available information or that might affect the short-term or longterm safety of the structure, including the possible need for temporary shoring or bracing. Enclosures were erected around repair areas to control dust and debris from construction activities. Disposal of construction debris was specified in conformance with local ordinances. The construction is shown in Fig. 16.13 to 16.16. As shown in Fig. 16.15 and 16.16, the contractor elected to install CFRP sheets at the double-tee stem ends, rather than the CFRP strips envisioned in Repair/replacement Option 4 (6.4) and shown in Fig. 16.12. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 16: Project Example 5—Precast/Prestressed Double-Tee Repair183 Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 184 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 16.13—Epoxy-injected cracks on primed double-tee stem. University of Toronto User. Fig. 16.14—Laying up CFRP sheet into epoxy saturant. h. Observation of the crack injection work i. Observation of the prepared concrete surfaces j. Observation of the CFRP installation 10.2.3 10.3.1 k. Daily fabrication of CFRP composite coupons for visual examination and testing of physical properties (ASTM D3039/D3039M) l. Hammer tapping the installed CFRP strips to verify bond through the absence of hollow sounds, and pulloff bond strength testing of installed sheets (ASTM D7522/D7522M) (Fig. 16.17) @Seismicisolation @Seismicisolation Fig. 16.15—Installed CFRP sheets. Note that contractor elected to install CFRP sheets rather than CFRP strips shown in Fig. 16.12. @Seismicisolation @Seismicisolation University of Toronto User. Fig. 16.16—Completed CFRP installation with acrylic coating. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 16: Project Example 5—Precast/Prestressed Double-Tee Repair185 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 16.17—Pulloff bond testing of the CFRP sheets. PROJECT CLOSE-OUT Periodic maintenance 1.5.1, 10.2.1, 10.2.2, 10.4.1 Periodic maintenance requirements were discussed with the owner. The LDP recommended annual monitoring of the repairs for visible deterioration and debonding. The LDP also recommended periodic maintenance or reapplication of the acrylic coating on the CFRP. Record documents 1.6.3, 1.5.3d, 1.5.3j The owner was provided with copies of the project and construction documents and the recommended monitoring and maintenance program. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 186 University of Toronto User. @Seismicisolation @Seismicisolation Description of structure The structure is a multi-level post-tensioned parking structure, constructed in the early 1980s (Fig. 17.1), and is located in the northern United States. The facility provides parking for approximately 500 vehicles, with the majority of the vehicles entering and exiting the facility daily. The structure was constructed using a combination of post-tensioned beams and slabs with a typical span of 24 ft (7.3 m) for the slabs and a beam span of 54 ft (16.5 m). The parking slabs are 6 in. (152 mm) thick, and post-tensioned with 0.5 in. (12.7 mm) diameter Grade 270 ksi (1862 MPa) strands. Project initiation and objectives During the condition assessment survey, three beams were observed with a nontypical cracking pattern (Fig. 17.2). The cracking typically started approximately 3 ft (0.9 m) from the end of the beam and extended diagonally to approximately 12 ft (4.5 m) from the beam ends. Therefore, the cracks were approximately 9 ft (2.7 m) long. Two of the affected beams were adjacent to each other, and the third was located on a different floor. Based on the crack widths observed during the Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 17: Project Example 6—Concrete Beam Repair by Section Enlargement University of Toronto User. Fig. 17.1—Exterior of post-tensioned parking structure. ACI 562-19 provision numbers applying to each section of text are shown in red at the top right of each paragraph. @Seismicisolation @Seismicisolation 187 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 17.2—Non-typical cracking of post-tensioned beam. preliminary evaluation, a detailed investigation of the cracking was performed. The condition survey of the remaining portions of the garage identified only limited damage, including corrosion with low cover reinforcing steel, isolated failures of post-tensioning strands with inadequate cover, and deterioration of a waterproofing membrane over a retail space. The durability-related repairs were addressed in a multi-year repair program. 1.7 The non-typical cracking of the girders required a detailed investigation to determine the cause of the cracking and if required to develop appropriate repair strategies. Jurisdiction—Northern U.S. City Original building code—1983 Municipal Building Code Original concrete design code—ACI 318-77 Current building code—2019 Municipal Building Code Existing building code—Not adopted 1.2.3 1.2.2 1.2.1 1.1.2, 1.4.2 Design-basis code—Because the local jurisdiction had not adopted an existing building code, use of ACI 562-19 as the design-basis code was approved by the Building Official. A.2.3, A.2.5 The overall rehabilitation project was limited to repairs to the existing structure, with no changes in use, occupancy or alterations. Therefore, the structural design was based upon the original concrete design code, ACI 318-77, using the additional requirements of ACI 562 in the design of the repairs. The use of ACI 562-19 and the original concrete design code was also consistent with the level of damage present in the @Seismicisolation structure (Chapter 4 of ACI 562-19). @Seismicisolation University of Toronto User. Governing building code Based upon discussions with the local building officials, as well as the information available in the original design drawings, the original design code and the current building codes adopted by the jurisdiction were determined as follows: Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 188 Structural assessment Structural analysis 6.5, 4.3 The structural analysis to review the adequacy of the original design was completed using the material properties shown in Table 17.1. These values were obtained from the design drawings and were not confirmed by testing. Therefore, the load combinations and strength reduction factors shown in Chapter 9 of ACI 318-77 were used in the analysis. The analysis confirmed the original design of the beams was adequate for a design live load (parking)@Seismicisolation of 50 psf (2.4 kPa). The analysis @Seismicisolation University of Toronto User. 1.7, 6.1, 6.2 The preliminary assessment of the beams by the licensed design professional (LDP) identified cracking inconsistent with available construction documents. The unexpected cracking served as a trigger to complete a detailed assessment of the cracked beams. At the time of the assessment, the structure had been in service for over 35 years and routinely experienced loading from full vehicle occupancy. Outside of the observed cracking, no signs of durability-related damage or distress were observed in the three cracked beams. Further, the cracking damage was limited to the near-end region of the three beams. The remaining beams in the structure had no apparent damage. Therefore, the goal of the structural assessment was to determine the likely cause of the cracking and then ensure the affected beams had adequate ultimate strength. 6.2.1, 6.2.2, 6.2.3, 6.3.1 Given the satisfactory structural performance of the remaining members in the structure, the investigation focused on the damaged beams. To limit the impact of the investigation on the operation of the structure, and to limit assessment costs, no materials testing was performed in the investigation. The material properties used in the assessment were obtained from original design drawings. 6.2.4, 6.4.1.1, 8.1.2 Based upon their previous experience, the LDP suspected that the observed cracking was likely caused by misplacement of the post-tensioning tendons during initial construction. To evaluate the cause of the cracking, ground-penetrating radar (GPR) was used to determine the location of the post-tensioning tendons and shear stirrups. As described in ACI 228.2R, GPR is a test method that uses radar to locate embedded elements in concrete structures. GPR test results showed the tendon bundle profiles were inconsistent with the design drawing, as shown in Figure 17.3, with the measured tendon bundles found to have “kinks” along the span. 6.1, 6.2.4, 6.4.1.1 GPR results also showed the stirrup spacing near the beam ends was consistent with the design drawings. Away from the beam ends, the measured stirrup spacing in the cracked portion of the beams exceeded the maximum design spacing of 24 in. (610 mm) on center in some locations. Similar GPR results were obtained from each of the three cracked beams. 1.5.2, 1.5.3, 1.7.2, 6.1.1 The measured post-tensioning tendon bundle profiles indicated the cracking likely occurred during initial stressing or shortly thereafter. During stressing, the tendons attempted to straighten and eliminate kinks, resulting in the localized downward pressure that caused the observed cracking. The large spacing between the existing stirrups contributed to the cracks extending over an extended length of the beams. 1.6.2, 1.7.4, 1.7.5, 6.1.1, 6.2.1 The flexural capacity of the cracked sections was not a significant concern as the highest force on the post-tensioning strands occurred during initial stressing. No flexural cracking was observed in the beams, indicating the beams were effectively prestressed. Therefore, at an ultimate load level, the post-tensioning strands were expected to have sufficient capacity to resist design loads. Further, no damage was documented at the critical sections for flexure. Due to concerns about the shear capacity of the affected beams, repairs to address the damage were considered. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 17: Project Example 6—Concrete Beam Repair by Section Enlargement189 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 17.3—Typical results of GPR scanning to locate stirrups and post-tensioning tendons. Table 17.1—Material properties used in structural assessment Material / property Concrete / compressive strength Reinforcing steel / yield strength Post-tensioning strand / yield strength Value / standard 4000 psi (28 MPa) / ASTM C39 60,000 psi (414 MPa) / ASTM A615 270 ksi (1862 MPa) / ASTM A416 Source Design drawings Design drawings Design drawings results confirmed that the demand-capacity ratio for the cracked beams was less than 1.5 and was therefore not a potentially dangerous structural condition. Repair options University of Toronto User. 6.7.1 The results of the structural assessment indicated the shear strength of the section was a concern due to uncertainty in the shear capacity of the concrete in the cracked portion of the beams. Therefore, the primary goal of the repair was to ensure the shear capacity of the section, and to provide an independent mechanism to resist shear loads in the cracked area. If the section was unrepaired, spalling of the cracked concrete section was possible. Therefore, an additional consideration in the repair design was to provide supplemental confinement for the section. 6.7.2, 6.7.3, 7.8, 7.9 Options considered for the repairs included use of fiber-reinforced polymer (FRP) materials to provide supplemental shear strength of the section, epoxy injection of the cracks, encasement of the section with concrete, or the addition of steel plates. The use of either FRP or steel plates was not adopted due to concerns about anchorage of the FRP reinforcement near the top of the beam, and the need for fire protection of the FRP or steel components. 7.3.1 Removal of the cracked concrete section of the beams was not considered as a repair option. If the cracked concrete were removed, it is possible for the beam post-tensioning force to cause the reinforcing steel in the beams to buckle. Buckling of reinforcing steel can occur when concrete surrounding the steel is removed when a compression force is present. 7.3.1, 7.3.2, 8.3 After reviewing repair options, a strategy of epoxy injection of the cracks and concrete encasement was selected. The epoxy injection was intended to restore the structural integrity of the cracked concrete section. The epoxy injection was considered a viable strategy as the cracks were relatively narrow in width, reinforcement @Seismicisolation was present that crossed the crack, and the loads were well defined. @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 190 Due to concerns about creep deformation of the epoxy, injection may not be a viable strategy when wide cracks are present without crossing reinforcement. The encasement of the section was intended to provide supplemental capacity of the section. The combination of epoxy injection and encasement provided a “belt and suspenders” approach to restoring the shear capacity of the section. Design of repairs University of Toronto User. 7.3, 9.2 At the start of the design process, the LDP considered shoring of the affected beams prior to completion of the repairs. Rather than install shoring, the LDP selected to remove the live load and account for the remaining loads due to the self-weight and post-tensioning forces in the design. The parking area above the damaged beams was closed during the repair period to remove the live load. Given the post-tensioned nature of the beams and the need for multiple levels of shoring in an operating parking structure, installation and engagement of a shoring system to relieve the dead load was not considered. The added section was conservatively designed to resist all superimposed live load. The repair zone was selected to be 12 ft (3.7 m) long starting 1 ft (0.3 m) from the end of the beam and allowed the repairs to extend beyond the affected area. During construction, the contractor chose to start the encasement at the face of the column. 7.4 A concrete encasement was designed to supplement the shear capacity of the affected beams. Figure 17.4 outlines the steps and details used for the repairs, including preparation and placement procedures. The repair design included injection of the cracks in the affected three beams. The epoxy injection specification was based upon ACI 563/503.7. Prior to injection, the crack faces were routed and injection ports installed. The injection was specified to start at the base of the crack and proceed upwards when epoxy was observed flowing from injection port to the next injection port. The owner of the structure was not willing to pay for additional testing (coring or non-destructive testing) to confirm the epoxy injection. Confirmation of epoxy injection is typically recommended. ICRI 210.1R describes quality assurance methods to verify quality of injection. 7.3.1, 7.6.4 A complete encasement of the affected section of the beams created a repaired section that behaved as an integral member with the original construction. To fully encapsulate the original beam, channels were removed from the top of the beam. The channel spacing was adjusted slightly in the field based upon GPR results to avoid damage to existing reinforcement and post-tensioning. Removing concrete to create the channels allowed for the supplemental stirrups to be anchored by doweled reinforcing bars at the top of the beam, and by the bars at the bottom of the beam. Consistent with ACI 318-77 Section 12.14.2.3, stirrups are developed when anchored in this manner. The added encasement concrete provided sufficient capacity to resist the live load from vehicular traffic. The concrete channels also provided a means for concrete placement from the top side of the beam. A uniform encasement thickness of 4 in. (102 mm) was selected to provide sufficient space in the enlarged section to allow for concrete cover, while minimizing the decrease in parking head room. The new encasement was reinforced with shear stirrups at 12 in. (305 mm) on center and horizontal skin reinforcement to help mitigate the potential for shrinkage cracks. One bar on the bottom of the added section was placed outside of the stirrups in a non-traditional manner. The intent of the bar placement outside of the stirrups was to have the bar closer to the face of concrete and therefore be more effective at crack control. The added encasement concrete provided sufficient capacity to resist applied live load shear. 7.4 To promote bond between the new concrete and the original structure, the surface of the concrete beam was specified to be sandblasted and wetted prior to new concrete placement. Although the design of the encasement did not rely upon bond to transfer load, the complete encasement of @Seismicisolation the beam allowed for integral @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 17: Project Example 6—Concrete Beam Repair by Section Enlargement191 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 17.4—Detail of concrete encasement installation. Durability of repairs 8.1.2, 8.1.3, 8.3 The primary concern of the project was the development of a structural repair to address significant cracks in three concrete beams. The cracked beams were not directly exposed to chlorides or other deleterious materials, and outside of the cracking damage, showed no signs of deterioration. Therefore, the durability requirements were based upon satisfying requirements equivalent to new construction for a similar exposure. Specific durability requirements for the repairs included: • The concrete was specified to be a 5000 psi (34.5 MPa), air-entrained concrete with a maximum water-cementitious materials ratio of 0.40; • Epoxy-coated reinforcing steel was used in the repairs; and • The perimeters of the slab channels were tooled during concrete placement to allow for sealant installation after the encasement concrete cured. The sealant was intended to prevent infiltration of water and other deleterious materials at these locations. @Seismicisolation @Seismicisolation University of Toronto User. behavior of the repaired beam with the new section. Alternately, the section could have been doweled to the original beam to provide for load transfer between the new section and the original beam. The repaired section was painted a high-visibility yellow due to the decrease in head space for vehicles. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 192 Contract documents The design professional prepared contract documents that specified repair materials which satisfied governing regulatory requirements and conveyed necessary information to perform the work. The contract documents included minimum requirements for temporary closure of affected portions of the structure. Construction specifications The LDP used ACI 563 as a source for construction specifications. The specification sections that were referenced included: Section 1—General requirements Section 3—Concrete removal and preparation for repair Section 4—Formwork Section 5—Reinforcement and reinforcement support Section 6—Conventional concrete mixtures Section 7—Handling and placing of conventional concrete Section 9—Crack repair by epoxy injection As discussed previously, the repair design strategy selected by the design professional did not require the use of shoring of the affected beams prior to repairs, therefore Section 2 was not referenced. Based upon the size of the repairs, a conventional concrete was specified by the design professional in lieu of a proprietary material or shotcrete. The ACI 563 specifications are intended to address conditions that are unique to repair applications. For the section enlargement, these include: • Section 3.1.1.2—Provide the surface profile and remove laitance, debris, and bond-inhibiting materials using methods that satisfy the requirements indicated in the contract documents. • Section 3.1.2.4—Submit documentation of existing conditions, especially areas of preexisting damage and deterioration unrelated to the work, including finishes of surfaces, before starting demolition. • Section 3.2.1.1—Select the means and methods for concrete removal that will minimize damage to the structure and bruised surfaces on the concrete substrate that remains within and adjacent to the work areas. • Section 9—Repair of cracks by epoxy injection in accordance with ACI 503.7 Construction Quality assurance / construction observations 10.2, 10.3, 10.4 The project specifications included quality assurance and control requirements for material approvals and field verification of quality. During construction, specific quality control measures included: • On-site review during the epoxy injection to confirm filling of the crack and port to port travel of the epoxy during injection; • Review of shop drawings for the reinforcing steel; • Review of the concrete mixture design for conformance with project requirements; • Review of reinforcing steel placement prior to installation of formwork; • Observation of concrete placement and curing operations; and • Testing of the repair concrete for slump, air content, temperature and compressive strength. After the removal of formwork, the concrete section was hammer sounded to confirm bond of the new concrete to the substrate.@Seismicisolation @Seismicisolation University of Toronto User. 9.1 The contract documents required the contractor to monitor the construction for any unexpected conditions or conditions that may impact the execution of the repairs. Specific requirements to the contractor included instructions related to observation of possible damage to existing post-tension system during the repair phase. Figure 17.5 shows the repairs in progress, with the completed repair is shown in Figure 17.6. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 17: Project Example 6—Concrete Beam Repair by Section Enlargement193 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 17.5—Reinforcing steel in place prior to formwork installation. PROJECT CLOSE-OUT Periodic maintenance The beam repairs were completed in one phase of a multi-year repair program. As a part of the overall repair program, recommendations for routine maintenance of the structure were provided to the owner. The maintenance recommendations included: • Annual cleaning of the parking decks to remove deicing salts carried in by vehicles; • Use of rubber-bladed plows for snow removal to avoid damage to traffic bearing coatings; and • Use of a non-chloride-containing material for deicing of the structure Record documents The owner was provided with copies of the construction documents including results from repair phase concrete testing and the recommended periodic maintenance program. @Seismicisolation @Seismicisolation University of Toronto User. Fig. 17.6—Completed repair, painted yellow with warning sign of low clearance. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 194 Description of structure The structure is a two-story concrete frame constructed of mild-reinforced perimeter beams and columns supported on pile foundations (Fig. 18.1). The concrete frame structure was constructed in 1954 and is located in the western United States. The 30 ft (9.1 m) tall structure is octagonal-shaped in plan, approximately 33.5 ft (10.2 m) wide, and includes two levels of concrete beams: a lower level approximately 16 ft (4.9 m) above grade and an upper level at the top of the frame. The lower-level beams are approximately 30 in. (762 mm) tall by 30 in. (762 mm) wide and the upper-level beams are approximately 54 in. (1372 mm) tall by 33 in. (838 mm) wide. The frame supports a vertical vessel on the upper level beams with a design weight of approximately 500 kip (226,800 kg). Project initiation and objectives The frame structure is located at an industrial site that is subject to the local jurisdiction’s Accidental Release and Prevention (ARP) Program. The objective of the program is to prevent the release of regulated substances with potential consequences to the public and environment. The owner of a facility that contains a regulated substance, as defined by the state, works closely with the authority having jurisdiction (AHJ) to determine the level of documentation required to develop a site-specific risk management plan. As part of the risk management plan, the owner should conduct a hazard analysis to identify, evaluate, and control hazards associated with the regulated substance considering a variety of natural or manmade events, including earthquakes. The ARP program requires that a licensed design professional (LDP) perform a seismic evaluation of any structures, distribution systems, and equipment where failure or displacement could release the regulated substance and that the hazard analysis, including the seismic evaluation, be revalidated every 5 years. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 18: Project Example 7—Concrete Frame Strengthening by Steel Jacket University of Toronto User. Fig. 18.1—Overall view of concrete frame structure. ACI 562-19 provision numbers applying to each section of text are shown in red at the top right of each paragraph. @Seismicisolation @Seismicisolation 195 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES The project was initiated to meet the AHJ’s program for accidental release prevention and to review the risk for release of a regulated substance during a seismic event. The LDP performed a seismic assessment of the concrete frame to evaluate the structure’s ability to resist the required seismic forces and to identify conditions that require maintenance, repair, or both. Governing building codes Based on discussions with the local building officials, as well as the information available in the original design drawings, the original design code and current building codes adopted by the jurisdiction were determined to be as follows: Jurisdiction—Western U.S. city Original building code—1943 Uniform Building Code (1943 UBC) Current building code—2013 State Building Code Existing building code—2013 State Building Code 1.2.3 1.2.2 1.2.1 The State Building Code was modeled after the 2012 International Building Code (IBC) and included provisions for the alteration, repair, addition, and change of occupancy of existing structures. Additionally, the State Building Code included alternative compliance provisions for work performed on existing buildings in accordance with the 2012 International Existing Building Code (IEBC). In addition to the adopted codes, the AHJ required the use of ACI 562 for repair of concrete structures. Preliminary evaluation 1.2.4.5.1 The seismic evaluation of the concrete frame structure began with a preliminary evaluation to review the actual condition of the structure and to determine if calculations are needed to complete the evaluation of the structure. The preliminary evaluation included a visual survey supplemented by a review of related documents. Document review 1.7.1 The original design drawings, construction documents, and previous ARP report were available and reviewed by the LDP. The prior ARP report included the results of the previous seismic evaluation and associated repairs and retrofits that were made. The original construction documents showed the configuration of the existing frame structure, the location of embedded reinforcement, and the foundation for the concrete frame. The drawings were used to verify anchorage details and to identify configurations that were not readily accessible for visual observation (Fig. 18.2 and 18.3). @Seismicisolation @Seismicisolation University of Toronto User. 1.2.4.2 Design-basis code—Because the AHJ adopted an existing building code, ACI 562 directs the LDP to determine the design-basis code in accordance with ACI 562-19 Chapter 4. 4.1.1, 4.1.3 Based on a preliminary evaluation of the frame structure, its location in a region of high seismicity, and discussion with the AHJ, the design-basis code was determined to be the 2013 State Building Code. Additional supplemental requirements were identified in the guidance document for the ARP Program seismic assessments. The guidance document identifies recommendations for performing a deterministic evaluation of structural systems and components to provide reasonable assurance for preventing the release of regulated substances. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 196 Fig. 18.2—Original construction drawing for concrete frame structure (plan view). Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 18: Project Example 7—Concrete Frame Strengthening by Steel Jacket197 University of Toronto User. Fig. 18.3—Original construction drawing for concrete@Seismicisolation frame structure (elevation view). @Seismicisolation GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Existing site conditions review 1.7.1, 1.7.2, 1.7.5, 6.1, 6.2 A critical part of the preliminary evaluation was the on-site review of the existing structure by the LDP. This was primarily a visual survey that considered the current condition of the structure in a systemic manner. The LDP walked throughout the concrete frame to look for potential seismic vulnerabilities in the primary seismicload-resisting elements and potential areas of weakness due to the following: a. Original design b. Construction c. Previous modifications d. Deterioration or damage The on-site review identified localized sections of spalled concrete that exposed rectangular reinforcing bars. Based on the experience of the LDP, the age of the structure, and the presence of rectangular reinforcing bars, the LDP determined that additional analysis was necessary to evaluate the adequacy of the concrete frame structure. The LDP did not observe any other readily visible signs of distress within the concrete frame. Uc = D + L ± Ehoriz + Evert ≤ φRn Q and Uc = D ± Ehoriz − Evert ≤ φRn Q where Uc is the strength design demand; D is the dead load including operating loads; L is any sustained live load expected during an earthquake; Ehoriz is the unreduced elastic earthquake horizontal load; Q is the ductility factor in accordance with the ARP guidance document; Evert is the unreduced elastic earthquake vertical load; f is the strength reduction factor; and Rn is the nominal strength of the member. 6.5 Following the previous inspection cycle, the ARP guidance document was changed to reflect updates to the seismic assessment criteria. The changes resulted in increased seismic loads compared to previous seismic evaluations. The LDP performed a structural evaluation of the concrete frame using the increased seismic loads to assess @Seismicisolation the reliability of the concrete frame structure. @Seismicisolation University of Toronto User. Structural assessment Because the visual survey did not reveal signs of structural distress that would have indicated overstress of the gravity supporting system, the LDP performed a lateral analysis to assess the concrete frame. Based on the observed spacing of the square steel ties in the beams and columns and the LPD’s experience, the LDP determined that the frame structure could be nonductile. Therefore, the LDP determined that seismic loading and ductility requirements governed the structural assessment. 6.3.1, 6.3.2 Based on the age of the structure, the LDP used ACI 562-19 Table 6.3.2a to determine a concrete compressive strength of 3000 psi (21 MPa) and Table 6.3.2b to determine a yield strength of 40 ksi (280 MPa) for the reinforcing steel in the analysis. 4.5.2, 6.5 In accordance with the design basis code and the supplemental ARP guidance document, the seismic ground motion for evaluation of the concrete frame was calculated in accordance with ASCE 7 for new design of a nonbuilding structure. The strength design demands were calculated using the modified load combinations in accordance with the ARP guidance document. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 198 The concrete frame and foundation were evaluated in accordance with the recommendations of the ARP guidance document. The LDP used structural analysis software to model the existing concrete frame and proposed retrofit strengthening. The effects of torsion and drift were included in the analysis model. The analysis considered a uniform acceleration equal to the spectral response acceleration parameter SDS (at a period of approximately 0.5 seconds) and a ductility factor Q of 1.5 to account for damage and possible nonductile behavior of the frame structure. Considering the load combinations from the guidance document identified previously, the LDP determined that under lateral loading from the design seismic event, the beams and columns would be overstressed in both shear and flexure. The calculated demandto-capacity ratios were a maximum 4 for columns, 2.3 for the upper beams, and 7.5 for the lower beams. The existing foundation was evaluated for the potential of overturning and sliding considering the reactions obtained from the analysis model and found to be adequate to support the increase seismic load. Strengthening concepts The results of the structural assessment indicated that the shear and flexural strength of the beams and columns were inadequate for the design seismic event. Therefore, the primary goal was to perform a seismic retrofit to strengthen the concrete frame structure. The concrete frame was located adjacent to other supporting structures on site and had to remain operational during the repairs. The effect of fire was not considered as part of the seismic retrofit design as the open frame structure does not support a flammable material and the facility has dedicated fire suppression systems throughout the site to mitigate the risk of damage due to fire. The following strengthening concepts were discussed with the owner: Concept 1 Carbon fiber reinforced polymer (CFRP)—Wrap beams and columns with CFRP to strengthen the member sections. This strengthening concept was not considered feasible due to level of overstress in all structural members calculated in the structural analysis. Concept 3 Steel jackets and supplemental bracing—Wrap beams and columns with steel plate jackets to provide additional strength and ductility, and install new steel cross-bracing between lower-level columns. The LDP determined that steel jackets could be installed considering clearances to adjacent structures and in conjunction with bracing would provide sufficient strength increase to the structure to meet the requirements of the ARP program. Structural analysis and repair design 7.2.1, 7.2.2 Design loads were calculated based on ASCE 7-10 Chapter 15 for nonbuilding structures. Because the lower level would be symmetrically braced with supplemental braced frames, but the upper bay would remain unbraced, two different coefficients were calculated, using the response modification factors (R) of 3.0 and 2.0, respectively. The design of drag strut and seismic connections requires an over strength factor (Ω) of 2.0. Each element was therefore checked based on the appropriate set of load combinations considering R and, where applicable, Ω. 7.3.1, R7.3.2 The final repair design included steel jackets around the columns and upper beams. The columns were fully encased by steel jackets @Seismicisolation and analyzed as a concrete@Seismicisolation University of Toronto User. Concept 2 Section enlargement—Increase the size of beams and columns with reinforced concrete. This strengthening concept was not considered feasible due to size limitations. The columns and beams could not be sufficiently enlarged due to the location of the concrete frame relative to other adjacent structures and piping. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 18: Project Example 7—Concrete Frame Strengthening by Steel Jacket199 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES filled rectangular box section in accordance with ANSI/AISC 360. The compactness of the steel jacket section was determined considering a concrete filled tube in accordance with ANSI/AISC 360. The existing concrete column was not considered to contribute to the column capacity and the built-up tube section (steel jacket) was designed to independently support the additional seismic loads. Figure 18.4 shows the column jacket detail designed by the LDP for the strengthening. The upper beams were encased in a U-shaped steel jacket because the supports for the vertical vessel were attached to the top of the concrete beams and access was not available to install a continuous top plate. The U-shaped steel jackets were bolted through the concrete beams as shown in Fig. 18.5 to transfer shear flow between the concrete beam and the supplemental steel plates, and to brace the steel plates against buckling. The through bolts were staggered top and bottom and spaced 14 in. (356 mm) on center. After the through bolts were installed, the holes were filled with nonshrink grout to ensure bearing between the bolts and concrete. In addition to the steel jackets, structural strengthening included adding supplemental diagonal braces in alternate bays below the lower beams to increase the lateral resistance of the frame structure. Steel wide flange beams were added below all lower-level concrete beams to increase the strength of the lower level beams and act as a drag strut between the braced bays. New concrete grade beams were installed on top of the mat foundation between the concrete columns to support the new diagonal braces (Fig. 18.6). The grade beams were doweled to the mat foundation and the columns at each end with epoxy-set reinforcing bars to transfer the brace forces to the existing foundation. In conjunction with the structural strengthening, traditional concrete repairs were performed to address localized concrete damage and distress observed during the walkthrough assessment and provide a uniform substrate under the steel jackets. Based on observations made during the initial walkthrough, the LDP determined that the localized concrete damage was the result of low concrete cover over the reinforcing steel. Durability Contract documents 1.5.1, 1.6.1, 9.4.1 The LDP prepared contract documents that specified repair materials that satisfied governing regulatory requirements and conveyed necessary information to perform the work. The work shown in the contract documents was considered a voluntary seismic upgrade of an existing structure to address specific issues identified as part of the ARP seismic assessment. The contract documents also instructed the contractor to provide all measures to protect life and property during construction. Construction specifications The LDP used AISC 303 and AISC 341 as sources for construction specifications for fabrication and erection of the supplemental steel strengthening. The LDP used ACI 563 as a source for construction specifications for all remaining aspects @Seismicisolation of the project including new concrete construction and concrete @Seismicisolation University of Toronto User. 8.1.1, 8.2.1, 8.4.1, 8.5.1 The durability of the repair materials and steel jackets was considered. The structure was exposed to the environment and was located at an industrial site with hazardous materials. During installation, the gap between the steel jackets and the concrete members was grouted to ensure intimate contact between the plates and the concrete surface. The new steel members, plates, and jackets were completely coated with a protective paint during fabrication to protect the exposed steel. Consideration was given to environmental conditions and exposure to chemicals when selecting an appropriate coating. The paint was selected by the owner for chemical resistance, cost, and ease of maintenance. The top surface of the upper beams was also painted to limit moisture penetration through the concrete. The transition between the concrete and the steel plate was sealed with a sealant to prevent water infiltration behind the steel jackets. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 200 Fig. 18.4—Construction drawing for strengthening: section detail for steel jacket around column. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 18: Project Example 7—Concrete Frame Strengthening by Steel Jacket201 University of Toronto User. Fig. 18.5—Construction drawing for strengthening: section detail for upper beam steel jacket. @Seismicisolation @Seismicisolation GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES repair of the existing structure. The specification sections that were referenced included the following: Section 1—General requirements Section 3—Concrete removal and preparation for repair Section 4—Formwork Section 5—Reinforcement and reinforcement support Section 6—Conventional concrete mixtures Section 7—Handling and placing of conventional concrete Section 8—Proprietary cementitious and polymer repair materials As discussed previously, the repair design strategy selected by the LDP did not require the use of shoring of the structure prior to repairs, therefore Section 2 was not referenced. Appropriate surface preparation was required for the conventional concrete repairs to the@Seismicisolation existing concrete structure and for preparation of the existing column @Seismicisolation University of Toronto User. Fig. 18.6—Construction drawing for strengthening: concrete frame elevation for typical braced bay. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 202 and foundation surfaces for installation of the new concrete grade beams. For the steel jacket strengthening, surface preparation was required to remove any surface contaminant prior to installation of the steel plates. The ACI 563 specifications are intended to address conditions that are unique to concrete repair applications. The concrete surface preparation was considered in accordance with the following: Section 3.1.1.2—Provide the surface profile and remove laitance, debris, and bond-inhibiting materials using methods that satisfy the requirements indicated in the contract documents. Construction 9.1, 9.4.1 The structural strengthening did not require removing members from the existing structure; therefore, the seismic retrofit could be installed without interrupting day-to-day operation of the facility and supported equipment. The contractor was required to notify the LDP of any discrepancies between the contract documents and existing construction and to repair any damage caused as a result of the work. The contractor was also required to maintain a continuous fire watch during welding or cutting near combustible materials. During construction, the contractor notified the LDP that the two-sided steel jacket sections would be difficult to install around the column due to the location of existing piping and adjacent structures. To address these conflicts with the steel jacket installation, the contractor proposed modifying the steel jacket detail for the columns to include separate steel plates on each side of the column that were fastened together at the column corners. The LDP evaluated the design modification and determined that the proposed alternate steel jacket fabrication and installation procedure was acceptable and provided sufficient capacity for the seismic retrofit (Fig. 18.7). Quality assurance @Seismicisolation @Seismicisolation University of Toronto User. 1.5.1, 10.2.1, 10.2.2, 10.4.1 The repair drawings and specifications included quality assurance and control measures for material approvals and field verification of quality. The specified quality control measures and construction observations were performed during construction, including the following: a. Visual inspection of the work for conformance with the approved construction documents b. Inspection of formwork and bracing to verify that supports, fastenings, wedges, ties, and items were secure prior to concrete placement 10.2.3 c. Observation of installed reinforcement and reinforcing bar accessories for new concrete grade beams d. Observation of the concrete placement and curing operations for new concrete grade beams 10.3.1 e. Testing of repair concrete, including slump, temperature, compressive strength, and air content 10.4.1 f. Observation of post-installed dowel preparation and installation g. Inspection of welded connections to verify conformance with approved welding performance specifications, including materials, surface preparation, alignment, weld size, length, and location h. Inspection of bolted connections to verify preparation and installation 10.2.3 i. Inspection of anchor rods and other items embedded in the concrete which supported the structural steel to verify diameter, grade, type, length, and depth of embedment Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 18: Project Example 7—Concrete Frame Strengthening by Steel Jacket203 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 18.7—Overall view of completed steel jacket strengthening with protective paint coating. PROJECT CLOSE-OUT R1.5.3 Periodic maintenance requirements were discussed with the owner. The LDP recommended yearly visual inspection and touch-up painting of the protective coating. Record documents 1.6.3 The owner was provided with copies of the project and construction documents and the recommended monitoring and maintenance schedule. @Seismicisolation @Seismicisolation University of Toronto User. Periodic maintenance Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 204 Description of structure The building is a three-story retail structure constructed in 2004 with a footprint of 120 x 66 ft (36.6 x 20 m). The primary structural frame is composed of reinforced concrete (RC) columns, RC beams, and one-way RC slabs. The typical floor has 10 spans in the long direction at 12 ft (3.6 m) each and three spans in transverse direction at 22 ft (6.7 m) each. The span for one-way slab is 12 ft (3.6 m) centerto-center of beams and the span for the beams is 22 ft (6.7 m) center to-center of the columns. The slabs are 6 in. (150 mm) thick and reinforced with No. 5 (No. 16) steel bars at 16 in. (400 mm) on center both bottom and top. A typical floor plan showing the layout of slab, beams, and columns is provided in Fig. 19.1. The beams are 12 in. (300 mm) wide by 24 in. (600 mm) deep and reinforced with three No. 7 (No. 22) bottom steel bars, assumed three No. 6 (No. 19) top bars, and No. 3 (No. 10) stirrups at 8 in. (200 mm) on center. The RC beams have a clear concrete cover of 1.5 in. (40 mm) and were constructed using 4000 psi (28 MPa) concrete made up of carbonate aggregate as obtained from the contract document concrete mixture design data sheet. The floors are supported on 18 x 18 in. (450 x 450 mm) columns. All the steel reinforcement used in the original construction is ASTM A615/A615M Grade 60 ksi (420 MPa) steel bars. A typical elevation of the beam is provided in Fig. 19.2 and a typical section is provided in Fig. 19.3. As the lengths of the top steel bars could not be confirmed, the beams are analyzed assuming simply supported end conditions with a clear span of 20.5 ft (6.25 m). The existing retail store floors were originally designed to carry a live load of 75 lb/ft2 (366 kg/m2) and a superimposed dead load of 25 lb/ft2 (122 kg/m2). A fire resistance rating of 2 hours was specified on the original design documents for the building. In this example, only flexural design will be performed. Shear strength was found to be adequate and fire load had no effect on shear capacity. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 19: Project Example 8—Building Subjected to Fire University of Toronto User. Fig. 19.1—Typical floor plan. ACI 562-19 provision numbers applying to each section of text are shown in red at the top right of each paragraph. @Seismicisolation @Seismicisolation 205 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 19.2—Typical beam elevation. Assumed top bars Fig. 19.3—Typical beam section. University of Toronto User. Project initiation, objectives, and remediation summary Scenario 1 (higher live loads) After a change in the ownership of the building in 2017, the entire second floor was repurposed to be a wholesale store. Due to the change in occupancy of the second floor, the new live load for the second floor was increased from 75 lb/ft2 (366 kg/m2) (original design) to 125 lb/ft2 (610 kg/m2) (wholesale). It was estimated that there would be minimal change in the superimposed dead load, which remains at 25 lb/ft2 (122 kg/m2). Structural evaluation of the second floor revealed that the columns and slabs are adequate to support the new live load and the fire rating requirement of 2 hours. However, the existing beams were found to be deficient in positive flexural strength and require strengthening to carry the higher new live load. The licensed design professional (LDP) for the project was tasked with developing a strengthening solution for the second-floor beams and to evaluate and enhance the fire resistance of the beams to meet the required 2-hour fire rating. The LDP determined that strengthening of the beams can be achieved using a one-ply, 12 in. (300 mm) wide strip of externally bonded carbon fiber-reinforced polymer (FRP) system on the soffit of the beams. To achieve the required fire rating, the LDP specified a UL-certified 3/4 in. (20 mm) thick spray-applied cementitious fire protection system that was tested with the FRP system selected for the project. A schematic for the beam with FRP and spray applied fire protection is shown in Fig. 19.4 and 19.5. The design approach and calculation steps used to determine the fire resistance rating of an existing and strengthened RC beam are discussed in the following sections. @Seismicisolation @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 206 Fig. 19.4—Typical beams strengthened with FRP and insulated with fire protection system. University of Toronto User. Fig. 19.5—Installation of fire protection system. @Seismicisolation @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 19: Project Example 8—Building Subjected to Fire207 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Scenario 2 (lower concrete cover) After the change of ownership of the building, the design live load for the second floor was changed to 125 lb/ft2 (610 kg/m2); however, an area on the second floor was selected to remain at 75 lb/ft2 (366 kg/m2) live load to house some lightweight equipment. During the site investigation of the second-floor slab, it was discovered that the clear concrete cover thickness for the bottom steel bars at two of the beams in the 75 lb/ft2 (366 kg/m2) area was, on average, 3/4 in. (20 mm), which is less than the 1.5 in. (40 mm) clear cover specified on the original design documents. These conditions created concerns for the LDP with the fire resistance of the beams with lower concrete cover. Upon preliminary analysis, the existing beams were found to provide only 1-hour fire resistance rating with the existing conditions. The LDP was requested to develop a solution to enhance the fire resistance of the two beams to meet the required 2-hour fire rating. The fire resistance rating of the beams was enhanced by installing a 1 in. (25 mm) thick concrete jacket to provide additional cover to the existing reinforcement. Governing codes Based on discussions with the building officials, the building codes adopted by the jurisdiction were determined, as described in the following: Jurisdiction—Northeastern U.S. city Original building code—2009 International Building Code (IBC 2009) Current building code—2015 International Building Code (IBC 2015) Concrete design code—ACI 318-14 Fire design code—ACI 216.1-14 Design loads—ASCE 7-16 Repair code—ACI 562-19 1.2.3 1.2.2 1.2.1 Muθ,Exist = 1.2MD + 1.6ML,Exist + 0.5MSL = (1.2)(75) + (1.6)(48) + (0.5)(0) = 166 ft-kip (225 kN·m) where MD = 75 ft-kip (102 kN·m); ML,Exist = 48 ft-kip (65 kN·m); and MSL = 0 ft-kip. New higher live loads Muθ,Exist = 1.2MD + 1.6ML,Exist + 0.5MSL = (1.2)(75) + (1.6)(78) + (0.5)(0) = 215 ft-kip (292 kN·m) where MD = 75 kip-ft (102 kN·m); ML = 78 kip-ft (106 kN·m); and MSL = none (load due to super imposed live load). Fire loading Based on the geometrical configuration and tributary width, loadings during fire conditions are calculated per ACI 562 Eq. (5.5.3). ϕexR ≥ (0.9 or 1.2)D + 0.5L + 0.2S 5.5.3 Existing loads: @Seismicisolation @Seismicisolation 5.5.3 University of Toronto User. Fire resistance rating calculations Ambient condition loading (room temperature) Based on the geometrical configuration and tributary width, loadings under room temperature conditions are calculated per ASCE/SEI 7 Section 2.3.1. Existing loads Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 208 Muθ,Exist = 1.2MD + 0.5ML,Exist + 0.2MSL = (1.2)(75) + (0.5)(48) + (0.2)(0) = 114 ft-kip (155 kN·m) where MD = 75 ft-kip (102 kN·m); ML,Exist = 48 ft-kip (65 kN·m); and MSL = 0 ft-kip. New higher loads Muθ,Exist = 1.2MD + 0.5ML,Exist + 0.2MSL = (1.2)(75) + (0.5)(78) + (0.2)(0) = 130 ft-kip (176 kN·m) where MDL = 75 ft-kip (102 kN·m); ML = 78 ft-kip (106 kN·m); and MSL = 0 ft-kip. Material properties Once the temperatures of the steel bars at 1 and 2 hours have been established, the yield strength of the steel at these elevated temperatures can be determined using the strength versus fire exposure time curve provided in Fig. 19.9 (Fig. 4.4.2.2.1.b of ACI 216.1-14). The reduced yield strength of the steel bars at 1 hour and 2 hours into fire exposure are listed in the following. At 1 hour Reduced yield strength of corner bars, fyθC,1HR = 0.95fy Reduced yield strength of middle bar, fyθM,1HR = 1.0fy At 2 hours Reduced yield strength of corner bars, fyθC,2HR = 0.68fy Reduced yield strength of middle bar, fyθM,2HR = 0.90fy For simplicity, in this design example, the member capacity at elevated temperature will be conservatively calculated using the yield strength of corner steel bars only. Because temperature in the concrete in compression remain relatively low, there is minimal or no strength degradation in the concrete compression block. @Seismicisolation @Seismicisolation University of Toronto User. Scenario 1 (new 125 lb/ft2 [610 kg/mm2] live loads) The beams are exposed to fire on the bottom three sides. The existing beam has three No. 7 (No. 22) bottom steel bars, out of which two are corner bars and one is in the middle of the section. The distance from the center of the bars to the outside surface is calculated at 1.5 in. (cover) + 0.375 in. (No. 3 stirrup) + 0.4375 in. (1/2 No. 7 bar) = 2.31 in. (70 mm) on two exterior sides for the corner bars, 2.31 in. (70 mm) on the bottom side, and 6 in. (150 mm) from the side of the beam for the middle bar (Fig. 19.3). ACI 216.1-14 provides isotherms for beam section for 1-, 2-, and 3-hour fire exposure. These curves can be used to determine the temperature of the steel bars at various times into the fire exposure. The temperature of the three bottom bars were determined using Fig. 19.6 and 19.7, respectively (Fig. 4.4.2.3i and 4.4.2.3j in ACI 216.1-14) and are listed in the following at 1 hour and 2 hours into fire exposure. At 1 hour Temperature of corner bars at 1 hour, TC,1HR = 600°F (320°C) Temperature of middle bar at 1 hour, TM,1HR = 450°F (230°C) At 2 hours Temperature of corner bars at 2 hours, TC,2HR = 900°F (480°C) Temperature of middle bar at 2 hours, TM,2HR = 700°F (370°C) Considering the thickness of the beam and slab, fire exposure on the bottom sides of the beams typically has minimum effect on top steel bars. In addition, most damage during a fire event occurs on the upper portions of columns and wall and underside of the slabs. This is mainly due to heat that rises during a fire event, causing the top of slabs and beams to stay at relatively low temperature (refer to fire effect on a reinforced concrete building; Fig. 19.8). For beam geometries that are not covered in ACI 216.1, simplified equations to calculate sectional and steel bar temperatures can be found in Kodur et al. (2013). Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 19: Project Example 8—Building Subjected to Fire209 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 19.6—Temperature distribution in a normalweight concrete rectangle unit at 1 hour of fire exposure. 2.65 φM n = φAs f y (d − a /2) = (0.9)(3)(0.6)(60) 21.68 − /12 = 165 ft-kip (224 kN·m) 2 a= (3)(0.6)(60) = 2.65 in. (67 mm) (0.85)(4)(12) where fc′ = 4000 psi (28 MPa); fy = 60,000 psi (420 MPa); As = 3(0.6 in.2) = 1.8 in.2 (852 mm2); d = 24 – (1.5 + 3/8 + 7/16) = 21.68 in. (551 mm); b = 12 in. (300 mm); and ϕ = 0.9. Per ACI 562-19 Section 5.5.2, the existing member without FRP strengthening is required to satisfy the following equation. ϕMn ≥ Mu = 1.1MD + 0.75ML = (1.1)(75) + (0.75)(78) = 141 ft-kip (191 kN·m) @Seismicisolation @Seismicisolation University of Toronto User. Flexural capacity Using the reduced yield strength of steel bars, the moment capacity of the beam at midspan under fire exposure can be evaluated using standard sectional analysis. The strength contribution of external FRP strengthening during fire exposure can be ignored per ACI 562-19 Section 5.5.3.3. In addition, per ACI 562-19 Section 5.5.3, the strength reduction factor (ϕ) is taken as 1.0 for strength calculations under fire exposure Buchanan (2009). Beam capacity at room temperature: Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 210 Fig. 19.7—Temperature distribution in a normalweight concrete rectangle unit at 2 hours of fire exposure. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 19: Project Example 8—Building Subjected to Fire211 University of Toronto User. Fig. 19.8—Effect of fire on reinforced concrete structure—notice spalling of concrete cover of beam and exposure of bottom bars (image courtesy of Sandberg. co.uk). @Seismicisolation @Seismicisolation GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 19.9—Strength of flexural reinforcement steel bar and strand at high temperature. ϕMn = 165 ft-kip (224 kN·m) > Mu = 141 ft-kip (191 kN·m) Based on the calculations, the existing beams exhibit the minimum required strength indicating that FRP strengthening is feasible for these beams under the new higher live loads. Beam capacity after having been exposed to fire for 1 hour: a 2.85 /12 φM nθ,1HR = φAs f yθ,1HR d − θ = (1.0)(3)(0.6)(0.95)(60) 21.68 − 2 2 aθ = (3)(0.6)(0.95)(60) = 2.85 in. (72 mm) (0.85)(4)(12) where fcT = 4000 psi (28 MPa); fyθ,1H = (0.95)(60 ksi) = 57 ksi (399 MPa); As = 3(0.6 in.2) = 1.8 in.2 (852 mm2); d = 24 – (1.5 + 3/8 + 7/16) = 21.68 in. (551 mm); b = 12 in. (300 mm); and ϕ = 1.0. 5.5.3.2 Beam capacity after having been exposed to fire for 2 hours a 1.82 /12 φM nθ,2HR = φAs f yθ,2HR d − θ = (1.0)(3)(0.6)(0.68)(60) 21.68 − 2 2 = 127 ft-kip (172 kN.m) aθ = (3)(0.6)(0.68)(60) = 1.82 in. (46 mm) (0.85)(4)(12) where fcT = 4000 psi (28 MPa); fyθ,2HR = (0.68)(60 ksi) = 40.8 ksi (281 MPa); As = 3(0.6 in.2) = 1.8 in.2 (852 mm2); d = 24 – (1.5 + 3/8 + 7/16) = 21.68 in. (551 mm); b = 12 in. (300 mm); and ϕ = 1.0. 5.5.3.2 @Seismicisolation @Seismicisolation University of Toronto User. = 174 ft-kip (236 kN·m) Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 212 Fire resistance rating The fire resistance rating of the beam is calculated as the duration (in hours) during which the member is able to support the load combination during a fire event, as shown by the following equation. ϕMn,θ ≥ Mu,fire 5.5.3.2 Under the new higher loads, the beams exhibited only 1-hour fire resistance rating and did not meet the required 2-hour rating for the structure. Therefore, the FRP strengthened beams are required to be protected with fire protection system. Table 19.1 summarizes the fire rating calculation for the original condition and the new condition of higher live loads at 1 hour and 2 hours into fire exposure. Note that the moment capacity of beams at 1-hour fire rating is greater than the moment capacity at room temperature. This is because concrete members subjected to fire have a reduction factor of 1.0, and the reduction in steel strength at 1-hour is 5 percent only (0.95fy), thus resulting in 5 percent increase in moment capacity. University of Toronto User. Scenario 2 (lower concrete cover) The beams are exposed to fire on the bottom three sides. The existing beam has three No. 7 (No. 22) bottom steel bars, out of which two are corner bars and one is in the middle of the section. Because the existing concrete cover for the steel bars was found to be 3/4 in. (20 mm), the existing distance from the center of the bars to the outside surface is 1.56 in. (40 mm) on two exterior sides for the corner bars and 1.56 in. (40 mm) on the bottom side and 6 in. (150 mm) from the side of the beam for the middle bar. ACI 216.1 provides isotherms for beam section for 1-, 2-, and 3-hour fire exposure. These curves can be used to determine the temperature of the steel bars at various times into the fire exposure. The temperature of the three bottom bars were determined using Fig. 19.10 and 19.11, respectively (Fig. 4.4.2.3i and 4.4.2.3j in ACI 216.1-14), and are listed in the following at 1 hour and 2 hours into fire exposure. Beam capacity after having been exposed to fire for 1 hour: Temperature of corner bars at 1 hour, TC,1HR = 900°F (480°C) Temperature of middle bar at 1 hour, TM,1HR = 680°F (360°C) At 2 hours Temperature of corner bars at 2 hours, TC,2HR = 1150°F (620°C) Temperature of middle bar at 2 hours, TM,2HR = 900°F (480°C) Considering the thickness of the beam and slab, fire exposure on the bottom sides of the beams typically has minimum effect on top steel bars. In addition, as discussed previously, as heat rises up during a fire event, the top of slabs and beams stay at relatively low temperature. Material properties Once the temperatures of the steel bars at 1 and 2 hours have been established, the yield strength of the steel at these elevated temperatures can be determined using the strength versus fire exposure time curve provided in Fig. 19.12 (Fig. Table 19.1—Summary of beam capacity with higher live load at room temperature and at fire loading Condition Clear cover, in. (mm) MD, ft-kip (kN·m) ML, MU, MU,fire, ft-kip ft-kip ft-kip ϕMn,Room, ϕMn,fire2HR, (kN·m) (kN·m) (kN·m) ft-kip (kN·m) ft-kip (kN·m) SCENARIO #1 (NEW 125 lb/ft2 LIVE LOAD) ϕMn,fire1HR, ft-kip (kN·m) Original design with lower cover 1.5 (40) 75 (102) 48 (65) 165 (226) 114 (155) 165 (224) 127 (172) 174 (236) New design with higher load 1.5 (40) 75 (102) 78 (106) 215 (292) 130 (176) 165 (224) 127 (172) 174 (236) @Seismicisolation @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 19: Project Example 8—Building Subjected to Fire213 Fire rating 1 hour (enlarge section to meet cover to meet 2HR) GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES 4.4.2.2.1.b of ACI 216.1-14). The reduced yield strength of the steel bars at 1 hour and 2 hours into fire exposure are listed in the following. At 1 hour Reduced yield strength of corner bars, fyθC,1HR = 0.69fy Reduced yield strength of middle bar, fyθM,1HR = 0.92fy At 2 hours Reduced yield strength of corner bars, fyθC,2HR = 0.38fy Reduced yield strength of middle bar, fyθM,2HR = 0.69fy For simplicity, in this design example, the member capacity at elevated temperature will be conservatively calculated using the yield strength of corner steel bars only. Sectional capacity Using the reduced yield strength of steel bars, the moment capacity of the beam at midspan @Seismicisolation under fire exposure can be evaluated using standard sectional @Seismicisolation University of Toronto User. Fig. 19.10—Temperature distribution in a normalweight concrete rectangular unit at 1 hour of fire exposure. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 214 analysis. The strength contribution of external FRP strengthening during fire exposure can be ignored per ACI 562-19 Section 5.5.3.3. In addition, per ACI 562-19 Section 5.5.3, the strength reduction factor (ϕ) is taken as 1.0 for strength calculations under fire exposure (Buchanan 2009). Beam capacity at room temperature: a 2.65 φM n = φAs f y d − (0.9)(3)(0.6)(60) 22.43 − /12 2 2 = 170 ft-kip (230 kN·m) a= (3)(0.6)(60) = 2.65 in. (67 mm) (0.85)(4)(12) where fcT = 4000 psi (28 MPa); fy = 60,000 psi (420 MPa); As = (3)(0.6 in.2) = 1.8 in.2 (852 mm2); d = 24 – (1.5 + 3/8 + 7/16) = 22.43 in. (570 mm); b = 12 in. (300 mm); and ϕ = 0.9. @Seismicisolation @Seismicisolation University of Toronto User. Fig. 19.11—Temperature distribution in a normalweight concrete rectangular unit at 2 hours of fire exposure. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 19: Project Example 8—Building Subjected to Fire215 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Fig. 19.12—Strength of flexural reinforcement steel bar and strand at high temperatures. Beam capacity after having been exposed for 1 hour: a 1.82 /12 φM nθ,1HR = φAs f yθ,1HR d − θ = (1.0)(3)(0.6)(0.69)(60) 22.43 − 2 2 = 133 ft-kip (180 kN.m) aθ = (3)(0.6)(0.69)(60) = 1.82 in. (46 mm) (0.85)(4)(12) = 75 ft-kip (102 kN.m) aθ = (3)(0.6)(0.387)(60) = 1.0 in. (25 mm) (0.85)(4)(12) where fcT = 4000 psi (28 MPa); fyθ,1HR = (0.38)(60) = 22.8 ksi (157 MPa); As = (3)(0.6 in.2) = 1.8 in.2 (852 mm2); d = 24 – (1.5 + 3/8+ 7/16) = 22.43 in. (570 mm); b = 12 in. (300 mm); and ϕ = 1.0. 5.5.3.2 Fire resistance rating With the lower concrete cover, the beams exhibited only 1-hour fire resistance rating and did not meet the required 2-hour rating for the structure. Therefore, the beams are required to be strengthened to achieve the minimum concrete cover thickness and the required fire resistance rating using concrete jacketing. Table 19.2 summarizes the fire rating calculation for the condition of lower concrete cover at 1 hour and 2 hours into fire exposure. @Seismicisolation @Seismicisolation University of Toronto User. where fcT = 4000 psi (28 MPa); fyθ,1HR = (0.68)(60) = 40.8 ksi (281 MPa); As = (3)(0.6 in.2) = 1.8 in.2 (852 mm2); d = 24 – (1.5 + 3/8 + 7/16) = 22.43 in. (570 mm); b = 12 in. (300 mm); and ϕ = 1.0. 5.5.3.2 Beam capacity after having been exposed for 2 hours: a 1.0 M nθ,2 HR = As f yθ,1HR d − θ = (3)(0.6)(0.38)(60) 22.43 − /12 2 2 Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 216 Fire protection system For Scenario 1, the beams were strengthened with a one-ply, 12 in. (300 mm) wide FRP system to carry higher design loads. There are certified fire protection systems that can be used to enhance the fire rating of FRP-strengthened flexural members. The fire resistance rating of these beams was enhanced by installing 3/4 in. (20 mm) thick fire protection system compatible with the FRP system. For Scenario 2, the beams were discovered with lower concrete cover. To address lower fire rating of these beams, additional nonstructural lightweight 1 in. (25 mm) thick concrete jacket was installed. Concrete screws were installed at 12 in. (300 mm) on center each way to facilitate proper adherence of the new concrete material to the existing substrate. This additional concrete cover satisfied the code required minimum clear cover and enhanced the fire resistance rating of the beam to meet the required fire rating of 2 hours. Contract specifications University of Toronto User. 1.5.1, 1.6.1, 9.4.1, 10.2.2 The LDP prepared contract documents that specified repair materials that satisfied governing regulatory requirements and conveyed necessary information to perform the work. The contract documents included the minimum requirements for shoring and bracing for all phases of the repair project, including requirements for the contractor to submit shoring documents that were signed and sealed by an LDP. The LDP used ACI 563 as a source for construction specifications. The specification sections that were referenced included: Section 1—General requirements Section 3—Concrete removal and preparation for repair Section 6—Conventional concrete mixtures Section 7—Handling and placing of conventional concrete Based on the size of the repairs, conventional concrete material was specified by the LDP instead of a proprietary material or shotcrete. ACI 563, “Specifications for Repair of Concrete Buildings,” addresses conditions that are unique to the project. The standard has a mandatory and nonmandatory requirements checklists at the end of the standard to help the specifier submit as complete a specification as possible. The main sections from the mandatory and nonmandatory checklists are extracted to include as a minimum in the Project Contract Document: a. Section 1.5.1.1—State the maximum dead and live loads and any temporary reduction in loads, to be permitted during repair and after completion of repair program, in concert with the requirements of 2.1.1.1. b. Section 1.5.2—Designate Owner-approved work areas and schedule requirements. c. Section 1.5.4.1—Show the demarcation line of the project location, specific work areas, and adjacent construction. d. Section 1.8.2.1—Identify work to be performed by certified personnel. e. Section 1.8.2.2(d)—Point out specific repair procedures that require review and approval. f. Section 1.8.2.2(e)—Specify submittal of component materials, repair material mixture proportions or batch requirements, and concrete supplier’s or repair Table 19.2—Summary of beam capacity due to low concrete cover at room temperature and at fire loading Condition Original design with lower cover Clear cover, in. (mm) MD, ft-kip (kN·m) 0.75 75 (102) ML, ft-kip MU, ft-kip MU,fire, ft-kip ϕMn,Room, (kN·m) (kN·m) (kN·m) ft-kip (kN·m) SCENARIO #2 (LOW CONCRETE COVER) 48 (65) 165 (225) 114 (154) @Seismicisolation @Seismicisolation 165 (230) Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 19: Project Example 8—Building Subjected to Fire217 ϕMn,fire2HR, ft-kip (kN·m) ϕMn,fire1HR, ft-kip (kN·m) 75 (102) 133 (180) Fire rating 1 hour (enlarge section to meet cover to meet 2HR) GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES material manufacturer’s quality control program. g. Section 2.3.3.2—State whether specialty engineer inspection is required. h. Section 3.1.1.2—Provide the surface profile and remove laitance, debris, and bond-inhibiting materials. i. Section 6.2.2.7—Indicate the specified concrete compressive strength fc′ for the work. j. Section 7.1.2.2—List the information in 7.1.2.2(a) to 7.1.2.2(g) that is to be submitted. Construction 9.1b, 9.4.1 The contract documents required the contractor to monitor the construction for any conditions that were not consistent with the available information or that might affect the short- or long-term safety of the structure, including the possible need for temporary shoring or bracing. Requirements for environmental issues, such as allowing water with debris to flow into floor drains or off the site and disposal of construction debris, were specified in conformance with local ordinances. Quality assurance 10.2.1, 10.2.2, 10.4.1 The repair specifications included quality assurance and control measures for material approvals and field verification of quality. The specified quality control measures and construction observations were performed during the construction, including the following: a. Review of material submittals 10.2.2 b. Visual inspection of the work in progress at critical stages of the repair c. Observation of the prepared concrete surfaces and comparison with ICRI concrete surface profiles (ICRI No. 310.2R) to verify that minimum roughness had been achieved 10.2.3 d. Observation of the concrete placement and curing operations e. Observation of the surface preparation and installation of the CFRP sheets f. Bond strength testing of installed CFRP sheets (ASTM D7522/D7522M) 6.8 After the repairs had been installed, a representative portion of the repaired supported garage slab was evaluated by load testing to demonstrate the strength of the repaired slab. The test area was selected based on typical repairs in the area and ease of setting up and running the test. Test procedure 6.8.2 ACI 562 references ACI 437.2 for load testing. The 2009 IBC references ACI 318-08, which includes Chapter 20, “Strength Evaluation of Existing Structures.” Based on ACI 562 Sections 1.1.2 and 1.4.1, ACI 562 governs for all matters pertaining to evaluation and shall govern when in conflict with other referenced standards. Accordingly, the monotonic load test procedure described in ACI 437.2 was used for the evaluation. The monotonic load test was selected after consultation with the contractor’s available means, methods, and familiarity with the monotonic test. The test procedure included the following details. Loading—The test load magnitude (TLM) was calculated per ACI 437.2-13, Section 4.2.2. TLM = 1.3(DW + DS) @Seismicisolation @Seismicisolation University of Toronto User. Load test Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 218 TLM = 1.0DW + 1.1DS + 1.6L + 0.5(Lr or S or R) TLM = 1.0DW + 1.1DS + 1.6(Lr or S or R) + 1.0L where Dw is load due to self-weight of the concrete structural system; Ds is superimposed dead load other than self-weight of structural system; L is live load due to use and occupancy of the building; Lr is roof live load produced during maintenance by workers, equipment, and materials or by moveable objects or people; S is snow load; and R is rain load. The test loads were applied by hydraulic jacks that reacted against the soffit of the plaza slab. Back-up shoring was installed underneath the supported garage slab. The jack arrangement included two interior panels of the supported garage slab. Instrumentation—Instrumentation included load cells to measure the load applied by the jacks, cable-extension transducers to measure vertical deflections, strain gauges to measure the strain in individual reinforcing bars, Whittemore strain gauges to measure strains in the concrete, and linear variable differential transformers (LVDTs) for measuring crack widths. All the instrumentation was wired to a data acquisition system. Test procedure—The test procedure (ACI 437.2-13 Section 5.3) consisted of applying the load in four equal increments, holding the load after each increment for deflection measurements, holding the total load for 24 hours, and releasing the load as quickly as practicable. Acceptance criteria—The acceptance criteria (ACI 437.2-13 Section 6.3) included the following items: Δr ≤ Δ1/4 or Δ1 < 0.05 in. (1.3 mm) or Δ1 ≤ ℓt/2000 and Δ1 ≤ ℓt /180 where Δ1 is the measured maximum deflection; ℓt is the shorter span under load for a two-way slab; and Δr is the measured residual deflection. PROJECT CLOSE-OUT Periodic maintenance Record documents 1.6.3, 1.5.3 The owner was provided with copies of the project and construction documents and the recommended monitoring and maintenance program. References Buchanan, A. H., 2009, Structural Design for Fire Safety, John Wiley and Sons, Ltd., Devon, UK. Kodur, V. K. R.; Yu, B.; and Dwaikat, M. M. S., 2013, “A Simplified Approach for Predicting Temperature in Reinforced Concrete Members Exposed to Standard Fire,” Fire Safety Journal, V. 56, pp. 39-51. @Seismicisolation @Seismicisolation University of Toronto User. 1.5.3, 8.1.3 The LDP recommended that a visual inspection of the repaired structure be performed 1 year after the repair installation to verify that no unanticipated behavior had occurred. The LDP also recommended periodic monitoring and maintenance of crack repairs, traffic-bearing membranes, and CFP. The northern climate dictated that these durability maintenance issues be monitored. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Chapter 19: Project Example 8—Building Subjected to Fire219 University of Toronto User. @Seismicisolation @Seismicisolation Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES 220 Committee documents are listed first by document number and year of publication followed by authored documents listed alphabetically. Because these documents are revised frequently, the reader is advised to contact the sponsoring group if it is desired to refer to the latest version. American Concrete Institute (ACI) ACI 1910 Standard Building Regulation for the Use of Reinforced Concrete ACI 117-10 (Reapproved 2015) Specification for Tolerances for Concrete Construction and Materials and Commentary ACI 201.1R-08 Guide for Conducting a Visual Inspection of Concrete in Service ACI 201.2R-16 Guide to Durable Concrete ACI 214.4R-10 (Reapproved 2016) Guide for Obtaining Cores and Interpreting Compressive Strength Results ACI 216.1-14 (Reapproved 2019) Code Requirements for Determining Fire Resistance of Concrete and Masonry Construction Assemblies ACI 222R-19 Protection of Metals in Concrete against Corrosion ACI 222.2R-14 Report on Corrosion of Prestressing Steels ACI 224.1R-07 Causes, Evaluation, and Repair of Cracks in Concrete Structures ACI 228.1R-19 In-Place Methods to Estimate Concrete Strength ACI 228.2R-13 Report on Nondestructive Test Methods for Evaluation of Concrete in Structures ACI 311.1R-07 ACI Manual of Concrete Inspection (SP-2) ACI 311.4R-05 Guide for Concrete Inspection ACI 318-63 Building Code Requirements for Reinforced Concrete ACI 318-05 Building Code Requirements for Structural Concrete and Commentary ACI 318-08 Building Code Requirements for Structural Concrete and Commentary ACI 318-14 Building Code Requirements for Structural Concrete and Commentary ACI 347R-14 Guide to Formwork for Concrete ACI 347.3R-13 Guide to Formed Concrete Surfaces ACI 355.2-19 Qualification of Post-Installed Mechanical Anchors in Concrete and Commentary ACI 355.4-11 Qualification of Post-Installed Adhesive Anchors in Concrete and Commentary ACI 362.1R-12 Guide for the Design and Construction of Durable Concrete Parking Structures ACI 364.1R-19 Guide for Evaluation of Concrete Structures before Rehabilitation @Seismicisolation @Seismicisolation 221 University of Toronto User. ACI 364.3T-15 Treatment of Exposed Epoxy-Coated Reinforcement in Repair ACI 365.1R-17 Service-Life Prediction ACI 369R-11 Guide for Seismic Rehabilitation of Existing Concrete Frame Buildings and Commentary ACI 423.4R-14 Corrosion and Repair of Unbonded Single Strand Tendons ACI 423.8R-10 Report on Corrosion and Repair of Grouted Multistrand and Bar Tendon Systems ACI 437R-19 Load Tests of Existing Concrete Buildings ACI 437.1R-07 Load Tests of Concrete Structures: Methods, Magnitude, Protocols, and Acceptance Criteria ACI 437.2-13 Code Requirements for Load Testing of Existing Concrete Structures and Commentary ACI 440.2R-17 Guide for the Design and Construction of Externally Bonded FRP Systems for Strengthening Concrete Structures ACI 440.6-08(Reapproved 2017) Specification for Carbon and Glass-Fiber Polymer Bar Materials for Concrete Reinforcement ACI 440.8-13 Specification for Carbon and Glass FiberReinforced Polymer (FRP) Materials Made by Wet Layup for External Strengthening of Concrete and Masonry Structures ACI 503.7-07 Specification for Crack Repair by Epoxy Injection ACI 515.3R-20 Guide for Assessment and Surface Preparation for Application of Protection Systems for Concrete ACI 546R-14 Concrete Repair Guide ACI 546.3R-14 Guide for the Selection of Materials for the Repair of Concrete ACI 562-13 Code Requirements for Evaluation, Repair, and Rehabilitation of Concrete Buildings and Commentary ACI 562-16 Code Requirements for Assessment, Repair, and Rehabilitation of Existing Concrete Structures and Commentary ACI 562-19 Code Requirements for Assessment, Repair, and Rehabilitation of Existing Concrete and Commentary ACI 563-18 Specifications for Repair of Concrete in Buildings ACI C630 Concrete Construction Special Inspector ACI CT-16 Concrete Terminology ACI RAP-8(05) Installation of Embedded Galvanic Anodes Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Referenced Standards and Reports GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES American National Standards Institute (ANSI) ANSI/AISC 360-10 Specification for Structural Steel Buildings American Society of Civil Engineers (ASCE) ASCE/SEI 7-05 Minimum Design Loads for Buildings and Other Structures ASCE/SEI 7-10 Minimum Design Loads for Buildings and Other Structures ASCE/SEI 7-16 Minimum Design Loads for Buildings and Other Structures ASCE/SEI 11-99 Guideline for Structural Condition Assessment of Existing Buildings ASCE/SEI 31-03 Seismic Evaluation of Existing Buildings ASCE/SEI 37-14 Design Loads on Structures during Construction ASCE/SEI 41-17 Seismic Rehabilitation of Existing Buildings @Seismicisolation @Seismicisolation University of Toronto User. ASTM International ASTM A160 Specification for Axle-Steel Bars for Concrete Reinforcement (withdrawn 1969) ASTM A370-17 Standard Test Methods and Definitions for Mechanical Testing of Steel Products ASTM A615/A615M-20 Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement ASTM A617/A617M-96a Standard Specification for AxleSteel Deformed and Plain Bars for Concrete Reinforcement ASTM A706/A706M-16 Standard Specification for Low-Alloyed Deformed and Plain Bars for Concrete Reinforcement ASTM A1061/A1061M-20a Standard Test Methods for Testing Multi-Wire Steel Strand ASTM C42/C42M-20 Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of Concrete ASTM C94/C94M-20 Standard Specification for ReadyMixed Concrete ASTM C309-19 Standard Specification for Liquid Membrane-Forming Compounds for Curing Concrete ASTM C496/C496M-17 Standard Test Method for Splitting Tensile Strength of Cylindrical Concrete Specimens ASTM C597-16 Standard Test Method for Pulse Velocity through Concrete ASTM C803/C803M-18 Standard Test Method for Penetration Resistance of Hardened Concrete ASTM C805/C805M-18 Standard Test Method for Rebound Number of Hardened Concrete ASTM C823/C823M-12(2017) Standard Practice for Examination and Sampling of Hardened Concrete in Construction ASTM C856-20 Standard Practice for Petrographic Examination of Hardened Concrete ASTM C873/C873M-15 Standard Test Method for Compressive Strength of Concrete Cylinders Cast in Place in Cylindrical Molds ASTM C876-15 Standard Test Method for Corrosion Potentials of Uncoated Reinforcing Steel in Concrete ASTM C882/C882M-20 Standard Test Method for Bond Strength of Epoxy-Resin Systems Used With Concrete By Slant Shear ASTM C900-19 Standard Test Method for Pullout Strength of Hardened Concrete ASTM C1074-19 Standard Practice for Estimating Concrete Strength by the Maturity Method ASTM C1152/C1152M-20 Standard Test Method for Acid-Soluble Chloride in Mortar and Concrete ASTM C1315-19 Standard Specification for Liquid Membrane-Forming Compounds Having Special Properties for Curing and Sealing Concrete ASTM C1383-15, Standard Test Method for Measuring the P-Wave Speed and the Thickness of Concrete Plates Using the Impact-Echo Method ASTM C1399/C1399M-10(2015) Standard Test Method for Obtaining Average Residual-Strength of FiberReinforced Concrete ASTM C1550-19 Standard Test Method for Flexural Toughness of Fiber Reinforced Concrete (Using Centrally Loaded Round Panel) ASTM C1581/C1581M-18a Standard Test Method for Determining Age at Cracking and Induced Tensile Stress Characteristics of Mortar and Concrete under Restrained Shrinkage ASTM C1583/C1583M-20 Standard Test Method for Tensile Strength of Concrete Surfaces and the Bond Strength or Tensile Strength of Concrete Repair and Overlay Materials by direct Tension (Pull-off Method) ASTM C1609/C1609M-19a Standard Test Method for Flexural Performance of Fiber-Reinforced Concrete (Using Beam With Third-Point Loading) ASTM C1740-16 Standard Practice for Evaluating the Condition of Concrete Plates Using the Impulse-Response Method ASTM D3039/D3039M-17 Standard Test Method for Tensile Properties of Polymer Matrix Composite Materials ASTM D4580/D4580M-12(2018) Standard Practice for Measuring Delaminations in Concrete Bridge Decks by Sounding ASTM D6432-19 Standard Guide for Using the Surface Ground Penetrating Radar Method for Subsurface Investigation ASTM D6916-18 Standard Test Method for Determining the Shear Strength Between Segmental Concrete Units (Modular Concrete Blocks) ASTM D7522/D7522M-15 Standard Test Method for Pull-Off Strength for FRP Laminate Systems Bonded to Concrete Substrate ASTM E119-20 Standard Test Method for Fire Tests of Building Construction and Materials Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 222 American Welding Society D1.4/D1.4M:2018 Structural Reinforcing Steel Welding Code— Applied Technology Council (ATC) ATC 20 Post Earthquake Evaluation of Buildings ATC 45 Field Manual: Safety Evaluation of Buildings after Wind Storms and Floods ATC 78 Identification and Mitigation of Nonductile Concrete Buildings Federal Emergency Management Agency (FEMA) FEMA P-58—Seismic Performance Assessment of Buildings FEMA P-154—Rapid Visual Screening of Buildings for Potential Seismic Hazards FEMA 306 and 307—Evaluation of Earthquake Damaged Concrete and Masonry Wall Buildings International Code Council (ICC) 2006 IBC 2006 International Building Code 2009 IBC 2009 International Building Code 2012 IBC 2012 International Building Code 2015 IBC 2015 International Building Code 2018 IBC 2018 International Building Code 2012 IEBC 2012 International Existing Building Code 2015 IEBC 2015 International Existing Building Code 2018 IEBC 2018 International Existing Building Code International Organization for Standardization (ISO) Maintenance and Repair of Concrete Structures 163113:2014 (ISO/TC 71/SC 71) ISO 9000 International Standards for Quality Management International Council of Building Officials (ICBO) 1961 Uniform Building Code 1961 UBC National Association of Corrosion Engineers (NACE) NACE SP0290-2019 Impressed Current Cathodic Protection of Reinforcing Steel in Atmospherically Exposed Concrete Structures NACE SP0187-2017 Design Considerations for Corrosion Control of Reinforcing Steel in Concrete NACE SP0408-2019 Cathodic Protection of Reinforcing Steel in Buried or Submerged Concrete Structures NACE 01101-2018 Electrochemical Chloride Extraction from Steel-Reinforced Concrete Occupational Safety & Health Administration (OSHA) Construction Industry Regulations & Standards 2020 Edition (Standards-29 CFR 1926). Retrieved from https:// www.osha.gov/laws-regs/regulations/standardnumber/1926 Southern Building Code Congress International (SBCCI) Standard Building Code (SBC) The American Railway Engineering and Maintenance-of-Way Association (AREMA) AREMA 2005 Manual for Railway Engineering The Concrete Society The Concrete Society TR 50 Guide to Surface Treatments for Protection and Enhancement of Concrete The Concrete Society TR 68 Assessment, Design and Repair of Fire-damaged Concrete Structures European Committee for Standardization EN 1504-10: 2003 Products and systems for the protection and repair of concrete structures. Definitions. Requirements. Quality control and evaluation of conformity. Site application of products and systems and quality control of the works The Masonry Society TMS 402/602-16 Building Code Requirements and Specification for Masonry Structures Wire Reinforcement Institute TF 101-R-14 Historical Data on Wire, Triangular Wire Fabric/ Mesh and Welded Wire Concrete Reinforcement (WWR) @Seismicisolation @Seismicisolation University of Toronto User. International Concrete Repair Institute (ICRI) ICRI No. 210.3R-2013 Guide for Using In-Situ Tensile Pulloff Tests to Evaluate Bond of Concrete Surface Materials ICRI No. 210.4-2009 Guide for Nondestructive Evaluation Methods for Condition Assessment, Repair, and Performance Monitoring of Concrete Structures ICRI No. 310.1R-2008 Guide for Surface Preparation for the Repair of Deteriorated Concrete Resulting from Reinforcing Steel Corrosion ICRI No. 310.2R-2013 Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings, Polymer Overlays, and Concrete Repair ICRI No. 320.2R-2018 Guide for Selecting and Specifying Materials for Repair of Concrete Surfaces ICRI No. 510.1-2013 Guide for Electrochemical Techniques to Mitigate the Corrosion of Steel for Reinforced Concrete Structures ICRI Concrete Surface Repair Technician ICRI Concrete Repair Terminology: http://www.icri.org/ GENERAL/repairterminology Building Officials and Code Administrators International (BOCA) Building Officials Code Administrators National Building Code (BOCA/NBC) Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. Referenced Standards and Reports223 GUIDE TO THE CODE FOR ASSESSMENT, REPAIR, AND REHABILITATION OF EXISTING CONCRETE STRUCTURES Authored documents Bartlett and MacGregor, 1994, “Effect of Core Length-toDiameter Ratio on Concrete Core Strength,” ACI Material Journal, V. 91, No. 4, July-Aug., pp. 339-348. Concrete Reinforcing Steel Institute, 2010, Vintage Steel Reinforcement in Concrete Structures, Schaumburg, IL, 2010, 352 pp. CON REP NET, Network Newsletter, No. 3, May 2004, 10 pp. http://projects.bre.co.uk/conrepnet/pdf/newsletter3. pdf Ellingwood, B.; MacGregor, J. G.; Galambos, T. V.; and Cornell, C. A., “Probability based load criteria: load factors and load combinations,” Journal of Structural Division ASCE, V. 108, no. 5, pp. 978-997, 1982 Ellingwood, B.R., and Ang, A. H.-S., 1972, “A Probabilistic Study of Safety Criteria for Design,” Structural Research Series No. 387, University of Illinois, UrbanaChampaign, Champaign, IL. Feldman, L. R., and Cairns, J., 2017, “Assessing Historical Provisions for Bond of Plain Bars,” ACI Structural Journal, V. 114, No. 2, Mar.-Apr., pp. 463-472. Galambos, T. V.; Ellingwood, B.; MacGregor, J. G.; and Cornell, C. A. “Probability Based Load Criteria: Assessment of Current Design Practice,” Journal of Structural Division ASCE, V. 108, No. 5, 1982, pp. 959-977. International Code Council, 2014, “International Code Adoptions,” http://www.iccsafe.org/about-icc/overview/. Kim, C.-G.; Park, H.-G.; Hong, G.-H.; and Kang, S.-M., 2016, “Shear Strength of Composite Beams with Dual Concrete Strengths,” ACI Structural Journal, V. 113, No. 2, Mar.-Apr., pp. 263-274. McDonald, J. E., and Campbell, R. L. Sr., 1985, “The Condition of Corps of Engineers Civil Works Concrete Structures,” Technical Report REMR-CS-2, Department of the Army, Corps of Engineers, Vicksburg, MS, 141 pp. National Institute of Standards and Technology, 2010, “Best Practice Guidelines for Structural Fire Resistance Design of Concrete and Steel Buildings,” NIST Technical Note 1681, Gaithersburg, MD, 217 pp. Stevens, G. R.; Bartlett, F. M.; Liu, M.,; Kesner, K. E., and Johnson, G., 2019, “Quantification of Reliability for Concrete Elements with Demand-Capacity Ratios Greater than One,” Concrete International, V. 41, No. 4, Apr., pp. 56-60. Stevens, R. G., and Kesner, K., 2016, “Evaluation of the ACI 562 Code—Part 1,” Concrete International, V. 38, No. 2, Feb., pp 37-40. Strategic Development Council, 2006, “Vision 2020: A Vision for the Concrete Repair, Protection, and Strengthening Industry,” American Concrete Institute, Farmington Hills, MI, 29 pp. Suprenant, B., 2019, “ACI Reference Specifications,” Concrete International, V. 41, No. 10, Oct., pp. 42-48. Warner, J.; Bhuyanm S.; Smoak, W. G.; Hindo, K. R.; and Sprinkel, M., 1998, “Surface Preparation for Overlays,” Concrete International, V. 20, No. 5, May, pp. 43-46. Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 224 University of Toronto User. @Seismicisolation @Seismicisolation 1000 Westgate Drive, Suite #252 St. Paul, MN 55114 USA www.icri.org Copyrighted material licensed to University of Toronto by Clarivate Analytics (US) LLC, subscriptions.techstreet.com, downloaded on 2020-12-30 19:07:47 +0000 by No further reproduction or distribution is permitted. 38800 Country Club Drive Farmington Hills, MI 48331 USA www.concrete.org 38800 Country Club Drive Farmington Hills, MI 48331 USA www.concretesdc.org University of Toronto User. @Seismicisolation @Seismicisolation 9 781641 951210