TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 TABLE OF CONTENTS 1.0 SCOPE 2.0 GENERAL REQUIREMENTS 3.0 SAFETY REQUIREMENTS 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 4.0 MATERIALS 4.1 4.2 4.3 5.0 Materials for Backfill Materials for Pavements Sand or Special Backfill EXECUTION 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 6.0 Safety Rules and Regulations Shoring or Bracing Roads and Highways Residential Gateways Restricted Areas Housekeeping Signboards Clearance from Underground Utilities Excavation Protection of Underground Construction De-watering Compaction Restoration Repair Work Field Quality Control Completion CABLE DUCTS REQUIREMENTS 6.1 6.2 6.3 6.4 6.5 6.6 6.7 General Requirements Specific Requirements Installation Reinforced Concrete Cable Trench Conduit Hangers or Spacers End Bells Duct Sealing Requirements TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 2 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 LIST OF FIGURES FIGURE 1: Minimum Trench Dimensions and Amount of Backfill Required to Reduce Soil Thermal Resistivity to an Average Value of 120°C cm/W (Typical). FIGURE 2: Restoration of Asphalt Pavement at Trenching Crossings FIGURE 3: Typical Conduit Hangers or Spacers FIGURE 4: Typical End-Bell TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 3 OF 30 TRANSMISSION CONSTRUCTION STANDARD 1.0 TCS-P-104.03, Rev. 0 SCOPE This standard sets forth the construction requirements for cable trenches and cable ducts including protection, support, maintenance and reconstruction of existing utility facilities affected by such construction in the 69 kV and above transmission system of Saudi Electricity Company, (SEC). This Standard does not cover Thrust Boring Pipes and Horizontal Directional Drilling. 2.0 GENERAL REQUIREMENTS High voltage underground cable circuits shall be installed directly buried, in ducts, in underground vaults or in a combination of these. In addition to meeting the physical requirements of the trenches and duct installations, all necessary precautions to insure the safety of personnel working in the trenches and the safety of the general public must be ascertained. All backfilling and restoration work of the cable trenches and ducts shall be performed in a manner, which will not damage the cable installation. The replacement of all backfilling material and final restoration shall be equal to or better than the original condition that existed prior to the trenching operation. 3.0 SAFETY REQUIREMENTS 3.1 Safety Rules and Regulations The construction of cable trenches and ducts shall conform to the rules and regulations pertaining to safety established by the concerned Government agencies, Municipalities, concerned companies and SEC Accident Prevention and Construction Safety Manuals. 3.2 Shoring or Bracing Where cable trenches and ducts are excavated to a depth of 0.90 meter or more, shoring or bracing shall be installed to prevent cave-ins of unstable soil and to prevent rock debris falling from top and walls of the trench. Where the trench walls are sloped at a 35o angle or less from horizontal, shoring or bracing may be omitted. 3.3 Roads and Highways Where cable trenches and ducts cross or are in close proximity to vehicular traffic roads and highways, all necessary barriers, steel plates, warning lights and signs shall be installed to protect the general public from any hazards associated with the open trenches. TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 4 OF 30 TRANSMISSION CONSTRUCTION STANDARD 3.4 TCS-P-104.03, Rev. 0 Residential Gateways Where cable trenches and ducts block residential gateways, stable and safe bridges shall be provided with all necessary barriers. 3.5 Restricted Areas In restricted areas, the work shall be carried out under the Work Permit Procedure and as per the right-of-way approval and conditions. Mechanized trenching equipment are prohibited in areas within the proximity of energized cables, flammable liquids/gas pipelines, up to 1.5 meters outside substations where grounding grid is present and under overhead transmission lines. 3.6 Housekeeping Good housekeeping shall be strictly observed. Materials/equipment being used shall be arranged so as not to cause obstruction to traffic or to the public. 3.7 Signboards The contractor shall provide cable trenching signboards on every trench/road crossing and 200 meters on straight run. (The contractor may consult the drawing # SB-036883 as an example of a typical case). 3.8 Clearance from Underground Utilities It is a requirement to take clearance for excavation on designated cable routes from all Underground Utilities like Water, Telephone etc. 4.0 MATERIALS 4.1 Materials for Backfill 4.1.1 Backfill materials shall be as per the requirements of TCS-Q113.02. 4.1.2 Maximum particle size shall be 50 mm at its greatest dimension. 4.1.3 No organic materials, debris or other deleterious materials shall be permitted. TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 5 OF 30 TRANSMISSION CONSTRUCTION STANDARD 4.2 TCS-P-104.03, Rev. 0 Materials for Pavements 4.2.1 Asphalt concrete shall be hot-mixed and shall be as per the requirements of TCS-Q-113.01. 4.2.2 Physical Requirements The physical requirements for Asphalt concrete shall be as per the SEC Standard TCS-Q-113.01. 4.2.3 Prime Coat and Tack Coat Materials Prime Coat and Tack Coat Materials shall be as per the requirements of the SEC Standard TCS-Q-113.01. The type and the rates of application are as specified in TCS-Q-113.01. 4.2.4 TCSP10403R0/YM Marl Bases a. Marl bases shall be uniformly graded with material passing the 100 mm sieve and less than 15 percent passing the 75 µm sieve and as specified in the SEC Standard TCS-Q-113.02. b. The soaked California Bearing Ratio (CBR) of the Marl as determined by ASTM D1883 at the optimum moisture content for maximum dry density using ASTM D1557, Procedure C, shall not be less than 50 for base material and not less than 15 for subbase material. Marl shall be sampled, tested by independent testing laboratory and approved by SEC. c. When work falls within the jurisdiction of Ministry of Transportation, Municipality and/or other government agencies, the materials and methods used shall also conform to the Specifications of Ministry of Transportation and/or Municipality. Date of Approval: June 25, 2008 PAGE NO. 6 OF 30 TRANSMISSION CONSTRUCTION STANDARD 4.3 TCS-P-104.03, Rev. 0 Sand or Special Backfill 4.3.1 To improve heat dissipation and to provide protective mechanical cushion around the cables, clean quartz sand or special backfill shall be used around cables or ducts. This quartz sand or special backfill, also called as “thermal sand backfill” has special characteristics and the supplier shall provide all the required information and test reports for SEC review and approval. 4.3.2 The clean sand to be furnished shall conform to SEC Standards TCS-Q-113.02, along with the following requirements: 4.3.3 a. The sand may contain clay or Marl in an amount not more than 3%. b. Random samples shall be taken under the supervision of SEC and shall be tested by an independent testing laboratory approved by SEC. The sample shall be from each 25 m3 or portion thereof loaded during a day's shipment. A suitable size sample shall then be obtained for a clay test and standard sieve analysis. c. Samples for moisture content tests shall be taken from each day's shipment. Moisture content shall be determined before and after drying. Certified results of all these tests shall be forwarded to the SEC within one week indicating loading dates. The Thermal Resistivity characteristics of the sand shall comply with the values as given in the table below. Max. Thermal Resistivity (oC cm/W) Minimum Density (kN/m3) Minimum Specific Gravity Sandy Soil (Dry) 120 14.75 1.46 Sandy Soil (Wet) 50 18.50 1.86 Materials TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 7 OF 30 TRANSMISSION CONSTRUCTION STANDARD 5.0 TCS-P-104.03, Rev. 0 4.3.4 The minimum trench dimension around a pipe or cable to reduce the soil thermal resistivity to an average value of 1200C cm/W shall be determined from Figure-1. 4.3.5 Irrespective of field conditions encountered, the installation shall be controlled by the "Dry" backfill condition parameters as given in the table under clause 4.3.3. 4.3.6 SEC shall be provided with daily logs covering the pertinent field excavation conditions. EXECUTION 5.1 Excavation 5.1.1 Excavation shall be sheeted, braced and shored, as necessary, to prevent caving-in or sliding, and to provide protection for existing structures and facilities. Sheeting, bracing and shoring shall be designed and built to withstand all loads caused by any earth movement or pressure and shall be rigid, maintaining shape and position under all circumstances. 5.1.2 Bottoms of excavations shall be firm, level, smooth and free of loose earth, soft/loose sand, mud, gravel, rocks and debris. Any soft spots shall be compacted per TCS-Q-113.02 requirements. In case of sabkhah and high water table areas, a minimum of 150 mm layer of sand bedding shall be provided and compacted per TCS-Q-113.02. 5.1.3 Soil and wastes from excavation shall be disposed-off properly to a municipality designated dumping area. 5.1.4 Excavations shall not be done below the bottom level of adjacent existing foundations unless underpinning and shoring has been done after approval by SEC. 5.1.5 Sides of unshored excavation shall be sloped back to the angle of natural repose of the soil to avoid sliding or caving. The angle of repose shall be the angle of internal friction for the material. 5.1.6 Construction materials or heavy machinery shall not be placed near the top of excavations or slopes within twice the depth of the excavation. TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 8 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 5.1.7 Where excavated trench blocks the access of municipality watering trucks to trees/grass, the trees/grass shall be watered and maintained in accordance with the Municipality requirements. Any repairs, fines and damages during execution shall be at no cost to SEC. Pedestrians and traffic guide/signs shall be placed for a clear passage. 5.1.8 All repairs of damages to the existing underground and/or overhead facilities shall be at no cost to SEC. 5.1.9 Precautions shall be taken to maintain the condition of the trenches prior to the installation of the cables. Maintenance shall include prevention of cave-ins or sloughing of the trench walls, de-watering of the trenches and putting barriers for vehicles or cable laying equipment. 5.1.10 Excavations shall be done by observing continuity of traffic flow per latest revision of Ministry of Transportation, Traffic Control Guide on Work Area and shall follow Traffic Police Department requirements as per Work Permit issued. 5.1.11 Sidewalks for use by the public during excavations shall be protected by guardrails or fences. 5.1.12 Structures/Equipment adjacent to excavations shall be braced to prevent settlement and lateral movement. 5.1.13 5.2 At SEC facilities where grounding grid is provided, care shall be taken to avoid cutting. If cutting is unavoidable, it shall be done after providing temporary grounding conductor under SEC supervision. Permanent joint shall be provided and filling shall be done only after approval by company representative. Protection of Underground Construction 5.2.1 TCSP10403R0/YM Underground facilities and other underground construction, which may be uncovered or otherwise affected by the work shall be located, protected, shored, braced, supported, and maintained. The facilities shall be exposed either by hand tools or methods acceptable to the respective Ministry/Utility Departments. All protective covers, warning tapes, position markers, etc., pertaining to existing underground utilities shall be preserved during excavation and shall be restored in position during the backfilling phase of the cable trenches. Date of Approval: June 25, 2008 PAGE NO. 9 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 5.2.2 If existing active utility lines are encountered and get damaged, all steps necessary to report damage(s) to concerned authority for immediate repair shall be done. No utility damage shall be repaired unless otherwise authorized by the concerned Ministry/Utility Departments. If existing utilities are found to interfere with the construction operations, SEC shall be immediately notified in writing, requesting instructions. Work shall not proceed until written instructions from SEC are received. 5.2.3 When utility lines that are not made known or indicated, are encountered within the area of operations, the concerned Ministry/Utility Departments shall be notified immediately about their presence for necessary measures to be taken to prevent interruption of the service, where service is to be maintained. 5.2.4 During the tie-in phases, utilities to adjacent buildings may be affected. In such cases, the work shall be coordinated through the concerned Ministry/Utility Departments and SEC, so that interruption of utilities will be minimal or eliminated altogether. 5.2.5 During all operations, the access to residences and buildings shall remain fully functional. Supports, covers, trench crossing means, services connections, etc., shal1 be provided as necessary to maintain functions within the existing residences, industries and other buildings uninterrupted, and to the satisfaction of SEC. 5.2.6 Open excavations shall be barricaded and warning lights shall be installed. Warning lights shall operate from sunset to sunrise each day or as required by the Municipality and Traffic Police. The power supply generator to the warning lights shall not create excessive noise, which might disturb the residents. 5.2.7 Existing structures, utilities and other facilities shall be protected, from damage caused by settlement, lateral movement, undermining and other hazards created by trenching operations. 5.2.8 Minimum interference shall be ensured with streets, walkways and other adjacent facilities, occupied or used, while engaged in operations or in the removal of debris. 5.2.9 Operations shall be conducted in such a manner so as to prevent injury to persons, property in general, structures, other facilities and utilities. TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 10 OF 30 TRANSMISSION CONSTRUCTION STANDARD 5.3 5.4 TCS-P-104.03, Rev. 0 5.2.10 In case of utility damage, the repairs shall be done at no cost to SEC. 5.2.11 Dust shall be controlled within populated areas of the construction operations to the satisfaction of the SEC, by thoroughly moistening all surfaces as required to prevent dust being a nuisance to the public and to personnel working on the site or along transport routes. De-watering 5.3.1 In areas where high water table causes the trench to become flooded, the trench shall be kept in dry either by pumping or installation of a well point system depending upon the actual site conditions until cable laying and backfilling operations are completed. Trenches subject to high water table must be shored to minimize trench-wall sloughing. The water removed from the trench shall be disposed of in a proper manner either by pumping to a storm water system or water tank trucks. If water is to be pumped in to municipal sewage water system, prior approvals must be obtained from the Municipal Sewage Authority. 5.3.2 Grading in the vicinity of excavations shall be controlled to prevent surface water running into excavated areas. Any water accumulated in the excavations shall be removed by pumping or other means approved by SEC. Compaction 5.4.1 Backfill materials shall be placed in uniform layers not exceeding 200 mm of uncompacted thickness. The method of compaction shall be subject to the approval of SEC. Field density tests shall be carried out to verify the degree of compaction and the results shall satisfy the requirements of SEC Standards TCS-Q-113.02. 5.4.2 For static load up to 320 kPa, trench backfill shall be compacted to not less than 70% relative density for noncohesive materials (ASTM D4253, D4254) or 95% modified Proctor for Marl or cohesive materials (ASTM D1557) unless otherwise specified by the concerned Municipality. 5.4.3 For static load over 320 kPa, trench backfill shall be compacted to not less than 85% relative density for noncohesive materials (ASTM D4253, D4254) or 95% modified proctor for marl or cohesive materials (ASTM D1557) unless otherwise specified by the concerned Municipality. TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 11 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 5.4.4 All backfills located more than 3 m away from buildings and other structures shall be mechanically compacted. Hand tampers or small vibratory compactors shall be used within 3 m of buildings and other structures. 5.4.5 For non-cohesive materials, compaction of backfill by saturating with water may be used if proven to SEC that the required compaction can be achieved with this method. 5.4.6 Warning tapes shall be buried 300 mm below finished grade level (i.e., in lawn areas just below sweet sand, in paved areas, just below the base course, etc.). The warning tapes shall have the words “CAUTION-POWER CABLES BELOW, CONTACT SEC”, in Arabic and English lettering in Traffic Black (RAL 9017) alternatively and with the following requirements: Color Width of tape Thickness 5.4.7 Flame Red (RAL 3000) 450 mm 200 microns Red concrete or calcium silicate tile cable covers shall be provided for each cable being protected. The minimum spacing between the cable and the tile cable cover shall be as shown in Figure-2. The tiles shall cover the entire width of trench and should satisfy the following requirements: Dimensions Min. Compressive Strength Density 390 mm x 200 mm x 80 mm 28.0 MPa 17 kN/m3 5.4.8 PVC coated steel wire mesh shall be provided above the tile cover. The steel wire mesh shall be 2.5 mm diameter and shall cover the entire width of trench. The minimum depth between the cable cover tiles and the PVC coated steel wire mesh shall be per Figure-2. 5.4.9 Any of the work performed or installed shall not be covered up or enclosed by other work prior to inspection and approval by SEC. 5.4.10 Before backfilling, the cables in position shall be inspected and certified by SEC. Any of the work enclosed or covered up before it has been inspected by SEC, shall be uncovered at no cost to SEC. TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 12 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 5.4.11 The trench backfill shall be made level with adjacent surfaces to a 95% minimum compaction using modified Proctor density. Should any material such as marl, gravel, etc., be contaminated while excavating, new uncontaminated materials shall be provided for backfilling. Excavated materials shall be tested and approved by SEC prior to use as backfill. 5.4.12 5.5 The backfill material shall be compacted immediately after placing. Each rolling operation shall follow the preceding operation as early as possible. In areas too small for roller a vibrating plate compactor or hand tamper may be used to achieve through compaction. Restoration If the work is carried out on an area falling within the jurisdiction of a Municipality, the Ministry of Transportation and/or restricted areas like defense, navy, etc., then the materials and methods used shall conform to the specifications of the appropriate governmental authority. Otherwise, the following requirements shall apply: 5.5.1 TCSP10403R0/YM Pavements a. Restore street pavements as per the requirements of SEC Standards TCS-Q-113.02 such that the thickness shall not be less than the existing. Reinstatement of asphalted surfaces over duct banks at road junctions shall be completed within three days of backfilling. b. A prime coat shall consist of the initial application of liquid asphalt onto the surface of a non-asphalt base course. The base shall be surface dry, free from dust and compacted before the prime coat is applied. If the base has a high clay content, a light application of water may be applied to the surface of the base course prior to application of the prime coat to facilitate penetration of the liquid asphalt into the base. After the base has been prepared, and when in a warm, surface dry condition, the prime coat shall be applied uniformly to the surface of the base using a pressure distributor. c. The priming material shall be applied to a width 300 mm greater on each side of the roadway than the specified width of the finished surface. Where there is a concrete curb at the edge of the asphalt pavement, the curb face shall be primed by means of a spouted water can or hand sprayer and shielding to prevent spillage on exposed concrete surfaces. The prime coat shall be permitted to cure until penetration Date of Approval: June 25, 2008 PAGE NO. 13 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 into the underlying surface, but at no time shall the curing period be less than 24 hours. TCSP10403R0/YM d. Pools of liquid asphalt occurring in depressions shall be broomed or squeezed over the surrounding surface the same day the prime coat is applied. At no time during the period of curing shall traffic be allowed upon the primed surface of the road. At locations where the prime coat has failed, it shall be repaired to the satisfaction of SEC. If the primed surface is damaged by equipment and personnel, it shall be repaired and rolled prior to placement of binder course. The prime coat shall be maintained at all times until the binder course is laid. If required by SEC, the primed surface shall be swept prior to laying binder. Care shall be taken to prevent over priming. The prime coat shall be fully set and cured before placing an asphalt mixture on the base. e. The tack coat shall be very thin and uniformly applied over the entire surface of the area to be covered. A tack coat application shall be made to all cold butt joints in both asphalt base and asphalt surface courses of the paving. The temperature of the liquid asphalt at the time of application shall range from 40o to 80oC. If a sand storm occurs between the application of a tack coat and the initiation of paving, the excess sand blown by the wind shall be removed and a new tack coat shall be applied. f. Unless otherwise indicated, restore grades to conditions existing prior to excavation. g. Pavement markings and striping, if existing prior to the start of any work, shall be replaced with the application of white or yellow, reflectorized or non-reflectorized traffic zone paint, to match existing conditions, or as directed by SEC. h. The work site shall be cleared after completion of the job. Debris should be hauled to the dump area approved by the Local Municipality. i. The work site shall at all times be kept neat, clean and free of waste material or rubbish. Any surplus equipment and material not required for further performance of the work shall be promptly removed from the work site. Upon completion of the work, all equipment, temporary structures, rubbish and unused materials shall be removed from the work site. Date of Approval: June 25, 2008 PAGE NO. 14 OF 30 TRANSMISSION CONSTRUCTION STANDARD j. 5.5.2 TCS-P-104.03, Rev. 0 All existing vegetation such as trees, shrubs and grasses on or adjacent to the work site which are not to be removed and which do not unreasonably interfere with the work shall be preserved and protected. Traffic Protection a. Traffic protection devices and methods of protection shall be provided and shall comply with the requirements of the Municipality or the concerned Traffic Police of the area where the work is carried on. Steel sheets or wooden planks shall be provided in order to permit safe crossing of the trenches. b. The traffic flow shall be maintained as required in the vicinity of the work site. At substation yards and entrances, the trenches shall be covered with steel sheet covers to have a free access during and after working hours. c. Flagmen, barricades, warning signs and warning lights shall be provided as required. d. Also, during restoration operations, traffic cones, barricades, lights and other protective devices required to protect traffic and workmen shall be furnished, installed and maintained. These shall be removed when restoration work is complete and area is ready to receive traffic. e. All materials, equipment and safety items shall be placed or stored in an orderly manner at suitable locations to avoid traffic hazard. f. All energized lines used for temporary lights and power for construction equipment shall be properly guarded/insulated. 5.5.3 Parking areas and driveway pavements shall be restored to the lines, grades, thickness and construction existing prior to excavation. 5.5.4 Sidewalks and Curbs TCSP10403R0/YM a. Asphalt and concrete or tile sidewalks and curbs shall be restored as directed by the Municipality or SEC, using new asphalt and concrete of equal quality to the existing and to match the lines, grades, thicknesses and construction existing prior to removal. b. Surfaces damaged during work shall be repaired/reinstated as directed by the Municipality or SEC at no cost to SEC. Date of Approval: June 25, 2008 PAGE NO. 15 OF 30 TRANSMISSION CONSTRUCTION STANDARD 5.5.5 5.5.6 TCS-P-104.03, Rev. 0 Signs and Markers a. Temporary sign shall be provided for each permanent sign removed. These shall be removed on completion of construction and replaced with the permanent signs as before. b. Survey monument markers, survey control markers, elevation bench markers, utility markers and right-of-way monuments shall be removed and replaced at the original location and elevation as before. Landscaping After completion of operations related to the work covered under this Standard, all grassed areas and all landscaping in general shall be brought up to a condition similar to or better than that existed before and as approved by the Municipality or SEC. 5.6 5.7 Repair Work 5.6.1 No-objection certificates shall be obtained from all the related authorities of the underground facilities like water, sewerage, telephone, etc., before excavation or backfilling. 5.6.2 Backfills that settle or erode pavements, structures and any other facilities damaged by such settlement or erosion shall be repaired. 5.6.3 If soil tests indicate that proper compaction has not been obtained, it shall be re-compacted. Tests for compaction shall be performed by SEC approved laboratory under the supervision of SEC. Field Quality Control 5.7.1 TCSP10403R0/YM Allowable Tolerances a. The finished grade shall not vary by more than 10 mm above or below the adjacent grade or elevation. b. The moisture content of the fill materials shall be maintained within plus or minus two percent (±2%) of the optimum moisture content of the material as determined by ASTM D1557 to facilitate compaction. Date of Approval: June 25, 2008 PAGE NO. 16 OF 30 TRANSMISSION CONSTRUCTION STANDARD 5.7.2 Compaction a. 5.8 TCS-P-104.03, Rev. 0 One (1) composite sample of asphalt mix shall be taken for each production day from the first truckload of mix delivered to the site for laboratory testing. The sample shall be taken by the SEC approved Laboratory and tested per SEC Standards TCS-Q-113.01, and the test reports for the following shall be submitted: i. Gradation ii. Flow test iii. Stability iv. Asphalt cement b. The degree of compaction for asphalt pavement placed in the field shall be equal to or greater than 96% of the laboratory Marshall density determined for the material being used in accordance with ASTM D1559. c. One (1) core sample of the compacted asphalt pavement shall be taken for each 100 linear meters of road reinstated and tested per ASTM D1559. Completion Following completion of all construction, the work site shall be cleaned of all debris and leftover materials from excavation and construction operations. 6.0 CABLE DUCTS REQUIREMENTS 6.1 General Requirements 6.1.1 TCSP10403R0/YM Cable ducts shall be installed in those areas where access to the cables for maintenance or repair is restricted. Such locations include areas beneath existing or future roads and highways, areas in near proximity to structures or footings where future excavations would be difficult and areas where additional physical protection to the cables is required and inside the substation also. Date of Approval: June 25, 2008 PAGE NO. 17 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 6.1.2 All non-metallic ducts and/or metallic conduit shall be installed with all elbows, bends, couplings, end bells, spacers and nonmetallic duct to metallic conduit adapters as required for the underground electrical systems. 6.1.3 Underground ducts smaller than 50mm in size, shall be rigid metallic conduit. Underground ducts, 50mm and larger, shall be PVC ducts, except as otherwise specified. 6.1.4 Underground ducts shall be installed to ensure a minimum cover of 600mm with respect to final grade except for high tension cables which shall have a minimum cover of 750mm. 6.1.5 Duct lines shall be installed so that a minimum pitch of 75mm per 30 meters is maintained. Where elevations or slopes are not otherwise determined, duct lines shall be installed so as to drain into manholes. 6.1.6 Plastic spacers shall be installed with a maximum horizontal interval of 1.5 meter so that minimum horizontal and vertical separation between outside diameter or ducts is as follows: a b c Duct banks (below 600 volts) 50mm Duct banks (above 600 volts) 75mm Between communication and adjacent power ducts75mm 6.1.7 Duct banks shall be installed so as to clear all underground piping, concrete footings, rock ledge, etc. with a minimum separation of 150mm. A cushion of stone free sand shall be used at such crossing points. 6.1.8 Non-metallic ducts shall be free from all substances which may injuriously affect any wire or cable sheath or jacket. The duct shall have a dense, uniform and homogeneous wall with a smooth interior surface free from obstructions, rough or flaky areas. The duct shall be non-magnetic, resistant to corrosive action, unaffected by electrolysis and shall not soften, deform or deteriorate when exposed to maximum safe operating temperature of cables or upon immersion for long periods of time in ground water. The bore of the duct shall be straight and circular in cross section. 6.1.9 Elbows, bends, fittings and couplings shall be made of the same grade material as straight lengths, except that plastic coupling may be used in place of non-metallic coupling on non-metallic duct. TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 18 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 6.1.10 The duct and fittings shall be of the tapered sleeve joint type. A coupling shall be provided for each joint of conduit and for each bend or elbow. Joints for plastic conduit shall be made with solvent cement after the conduit has been cut square, deburred, cleaned and dried. The joints shall be manufactured so that they are sufficiently tight to prevent water, silt or concrete from entering the duct. 6.1.11 The length for each size duct shall be standard with the manufacturer. Each length shall be marked with the manufacturer's name or trade-mark. 6.1.12 Plastic ducts shall be composed of high impact Polyvinyl Chloride (PVC). Plastic ducts shall be light wall type where encased in concrete and heavy wall type where direct buried. Plastic ducts shall be from the approved manufacture. Plastic ducts shall be used to protect the cables at point where the cables cross in close proximity to other underground utilities & duct banks 6.1.13 Underground ducts which are installed below the building structure, or encased to form part of the building structure or are within 1.5 meters of the building structure shall be heavy duty galvanized steel. 6.2 6.3 Specific Requirements 6.2.1 All cable ducts/conduits, couplings and accessories shall be installed in strict compliance with the manufacturer’s instructions. 6.2.2 The conduit material, size, class and type shall conform to 23TMSS-01. The system or manner of burial will depend on required physical protection or loading of structures above the ducts, which shall be specified by SEC. 6.2.3 The construction of direct buried or concrete duct banks shall include conduit hangers or spacers. Refer to Figure-3. 6.2.4 Both ends of all conduit runs shall have end-bells to prevent damage to the cables during installation. Refer to Figure-4. Installation 6.3.1 Clean the ducts with swab. 6.3.2 After the ducts are laid and concrete encased or back-filled, they shall be rodded by the contractor. A flexible mandrel, 6mm less in diameter than the bore of the duct shall then be drawn through followed by a wire brush cleaner 6mm larger in diameter than the TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 19 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 bore. All foreign matter shall be removed. If obstructions are found which cannot be removed by cleaning so as to pass the mandrel, the ducts shall be removed and re-laid at the expense of the contractor. 6.3.3. The testing and cleaning of a concrete encased duct shall be done on the day after the concrete has been poured to remove any concrete splash or spills in the ducts. Construction drawings, which indicate duct line length and routing shall be verified and field noted in conjunction with duct testing operations. 6.3.4 Install a pull rope for future cable installation. The pull rope shall be of nylon with 13 mm diameter. 6.3.5 Plug the ends with ducts Seals. Duct sealing unit shall be as per 23-TMSS-02. The installation and removal of any duct sealing unit shall comply with the manufacturer’s recommendations. 6.3.6 For the selection of the type of conduits to be used, the following factors shall be considered: a b c d The lower coefficient of friction available. Refer to TES-P-104.05. Heat transfer ability of the material Resistance to deformation and fusion when cables are short-circuited Dimensions of the conduit shall be according to NEMA. 6.3.7 Duct banks shall be run as straight as possible from termination to termination. Ducts shall be laid in the excavated trenches in continuous alignment and in the formation required. 6.3.8 Ducts shall be laid horizontally so that the butt joints of adjacent ducts are not opposite each other. Changes in direction elevation shall be made with the largest practical radium using bends, sweeps, curved segments and/or deflection couplings as required. Fittings shall be selected so that the minimum numbers of joints occur in each change of direction. Joints shall be tight and well fitted. All field cuts shall be square reamed and the ends of nonmetallic ducts properly tapered with tools designed for the task and waterproofed in accordance with the manufacturer's recommendations. 6.3.9 Ducts entering manholes and vaults shall terminate in end bells. Vertical risers from underground duct banks shall utilize concrete encased long radius rigid steel elbows, coated as specified herein. Expansion joints shall be installed as required. TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 20 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 6.3.10 During duct installation, both the completed and uncompleted units of all duct sections shall be closed with suitable tight fittings, caps or plugs to prevent the entrance of mud or foreign matter into the duct bore. Wood plugs may be used for closing the non-metallic ducts. 6.3.11 Concrete Encased Duct Bank – Ducts shall be installed as a self supporting structure before pouring the concrete. The ducts shall be securely fastened in place with heavy twine or steel wire and anchored so as to maintain accurate position during the concrete pour. Concrete shall be placed as soon as practicable after ducts have been secured in place, checked for alignment and grade, and approved by SEC. The ducts shall be protected so that they are not damaged during the pour. 6.3.12 Concrete for encasement shall attain a 20N/mm2 strength at 28days (SEC spec. # 70-TMSS-03) and shall be colored with tile – red cement color. 6.3.13 Underground Ducts and Conduit without Concrete Encasement TCSP10403R0/YM a Excavate trenches for all direct buried conduits in locations indicated on the contractor's approved drawings. Excavate trenches to allow for 150mm sand bed, and 600mm minimum cover over top of conduits. Grade the bottom of trenches reasonably free from stones and other sharp objects which could injure the conditions. b Conduits shall be laid on a 150mm sand bed with a minimum separation between conduits of 50mm. c Backfill with sand and approved backfill as soon as the conduit has been installed and the installation approved by SEC. Place a 150mm sand layer, by hand, directly above and on each side of the conduit and hand tamp to compact. Backfill the balance of the trench above the sand with approved backfill in 300 mm maximum layers. Compact each layer (as per SEC standard # TCS-Q-113.02) with power tampers to the density of adjacent undisturbed materials. d Bricks, planks and other supports shall not be used in lieu of sand to bring ducts to grade. Multi-level duct runs shall be installed in layers 150mm apart with sand backfill surrounding and above each level placed and tamped before the next level is laid. e Install a 150mm wide yellow warning tape marked "Electrical" directly over the buried conduits 300 mm below the finished grade. Date of Approval: June 25, 2008 PAGE NO. 21 OF 30 TRANSMISSION CONSTRUCTION STANDARD 6.4 TCS-P-104.03, Rev. 0 Reinforced Concrete Cable Trench The Contractor is responsible for the construction of cable trench, duct banks and manhole where necessary. It should conform to the applicable established standards. The specification is intended for use within the substation also. e underground system shall be either an open trench or backfilled trench and are classified as direct-buried or concrete encased. The reinforced concrete cable trench shall be designed to provide natural ambient air cooling to the cables. The cable trench shall be provided with cover that will not impede the natural air circulation and offer easy access to cables during maintenance/ inspection procedures. Reinforced concrete cable trench shall be used for the substation as follows: 6.4.1 Inside the building – reinforced concrete cable trench with removable checkered steel plate cover painted according to TESH-107.01 shall be provided inside the building whereever required. 6.4.2 Outside the building – reinforced concrete cable trench with removable precast concrete cover or fabricated steel grill cover painted according to TES-H-107.01 shall be provided outside the building to route the Power, Control and NFOC cables. Reinforced concrete cable trench shall be designed and constructed with adequate size and strength suitable for the following features: TCSP10403R0/YM a Sufficient space to accommodate the required cables, cable ducts and associated accessories. b Space for maintenance and operations. c Provide Steel ladder rung, painted according to TES-H107.01, at proper location for maintenance. d Cable trays, supports and other associated accessories. e Provide drain holes of sufficient size and spacing throughout the trench length. At the bottom of drain holes, sufficient amount of graded gravel shall be provided to drain water, this shall be done prior to pour trench floor. Date of Approval: June 25, 2008 PAGE NO. 22 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 f Provide at least 0.5% slope for the trench floor to allow the water to flow towards the drain holes and away from the building cable cellar. g Heavy traffic rated trench cover (precast reinforced concrete or fabricated steel) shall be provided at the heavy traffic area, i.e. road crossing, etc. The Contractor may also provide concrete encased duct bank for this portion. h Trench shall be provided with natural ventilation for cooling the power cables. i Provide 75mm thick lean concrete prior to pour trench floor. j Provide 200 microns polyethylene sheet prior to pour lean concrete. k Necessary concrete protective coating shall be provided. l Concrete works for the trench shall conform to 70-TMSS-03 and TCS-Q-113.03. m Trenching and earthworks shall conform to TCS-Q-113.02. 6.5 Conduit Hangers or Spacers In the assembly of a duct bank, the conduits shall be supported in air by hangers or spacers, which hold the conduits in place during the backfilling of inter-conduit space with sand, or cement. The material of spacer shall be polypropylene plastic. Spacers for supporting conduits shall be installed at intervals not exceeding 1.5 meters. Spacers shall be with interlocking lugs and matching holes for field assembly and into multiple units. Base spacers with pads shall be provided in sandy or soft soil condition or where the number of vertical tiers is grater than two. Intermediate spacers shall be used as the base unit in good soil and in conduit banks of two (2) or less tiers. Figure-3 shows typical conduit hangers for a 4x3 conduit arrangement. However, a suitable conduit hanger or spacer can support any number of conduit arrangements. 6.6 End-Bells An end-bell is a flared opening for easy pulling of cables. End-bell eliminates sharp corner that might damage the cable jacket as cable is pulled in conduit or duct. It also protects the cable sheath as the cable TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 23 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 moves longitudinally due to thermal load cycling. End-bells shall be installed on all cable conduits. The beveled radius feature provides a smooth surface over which the cable passes when it is pulled into the duct. The beveled radius also minimizes elongation of the cable caused by frictional drag between cable and duct interface. 6.7 Duct Sealing Requirements The duct sealing units shall be of the manufacturer’s standard design and shall meet or exceed the requirements mentioned in SEC specification # 23-TMSS-02. Cable duct sealing units shall be designed for the expected cable jacket temperature in addition to the service conditions specified in 01-TMSS-01 The duct sealing units shall be designed and constructed to maintain sealing efficiency for a period of 20 years under a constant pressure of 69 kPa (10 psig, 7.05 m of water head) under service conditions. TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 24 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 FIGURE-1 MIN. TRENCH DIMENSIONS Minimum Trench Dimensions and Amount of Backfill Required to Reduce Soil Thermal Resistivity to an Average Value of 120°C cm/W.(Typical) 2040 CURVE FOR MIN. DEPTH 1785 CURVE FOR MIN. WIDTH 1530 1275 1020 765 510 255 140 150 160 170 180 190 CURVE FOR MIN. AMOUNT OF SPECIAL BACKFILL AROUND PIPE OR CABLE 200 ORIGINAL SOIL THERMAL RESISTIVITY IN °Ccm/W NOTE: FIGURE-1 is for 150 mm diameter pipe or cable buried at a depth of 915 mm (Typical). 1. For original soils with Thermal Resistivity (TR) as indicated below, the following changes shall control: For TR <140: use min. requirements as outlined in Fig-1 above, i.e., trench width of 405 mm and depth of 1220 mm. However, this 405 mm minimum trench width shall be adjusted to 450 mm to accommodate the width of the terratape cable marker. For TR >200, for every 10% increase in TR over 200ºC cm/W, both the trench width and the depth of burial shall be increased by 10%. SEC approval shall be obtained prior to any alteration of trench dimensions or where increase in depth of burial is not feasible. 2. Cable/pipe diameter For cable/pipe diameter of more than 150 mm, trench dimensions shall be increased by 20% for every 25 mm over 150 mm of diameter, and the amount of the special backfill shall be increased as required. TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 25 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 FIGURE-2 RESTORATION OF ASPHALT PAVEMENT AT TRENCH CROSSINGS IMPORTANT: SEE NEXT PAGE FOR NOTES AND LEGEND DWG # TC-0403-0100-00 TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 26 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 LEGEND 1. Final-Surface course per TCS-Q-113.01 2. Asphalt Binder course per TCS-Q-113.01. Also see Note 3. 3. Corners rounded off 4. Existing pavement thickness varies. 5. Cable trench in cohesive soil that will have stable vertical trench walls or when suitably braced as approved by the SEC 6. Cable Warning Tape (Terratape) 7. PVC coated steel wire mesh 8. Red/green concrete or calcium silicate tile cover with dimensions 50 x 200 x 400 mm or 80 x 190 x 390 mm (Red color tiles for electric cables & green color tiles for communication cables) 9. Angle of repose (see Note 4) 10. Cable or Duct. For particular cable or duct arrangement, refer to Figure Nos. 05-01 to 05-08 of TES-P-104.05. 11. Backfill with clean sand in 150 mm lifts and compacted per TCS-Q113.02 12. Cable trench in non-cohesive soil. See Note 4. 13. Marl (cohesive) material shall be placed on the top of the backfill and compacted to 95% modified Proctor (ASTM D1557) per TCS-Q-113.02. 14 Loose placing of mix to protrude above pavement by 12 mm to 20 mm for 6A mix 15. Tamped mix to protrude above the existing pavement by: 6 mm to 12 mm for 6A mix. 16. Existing pavement to be straight saw cut only. 17. Prime coat application per TCS-Q-113.01, on base course of roadways prior to paving and also on base course of nonroad pavement if asphalt is not placed within 48 hours. TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 27 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 NOTES: 1. For particular trench dimensions, refer to Figure nos. 05-01 to 05-08 of TES-P-104.05. 2. For all cases, saw cutting shall be done for Asphalt pavements. If during construction the saw cut vertical sides of the existing asphalt pavement are damaged, the Asphalt shall be cut along a parallel line and asphalting done. 3. Traffic shall not be allowed before the tamped surface lift has cooled off for at least three hours or as directed by SEC. 4. For unusual conditions or shallow trenches in non-cohesive soil , and where the use of sheeting is not feasible or justified, the trench walls may be sloped at the angle of repose. 5. Open, unbraced trenches shall not be excavated below existing ground water level without dewatering by means of well points or other methods, subject to approval of SEC. 6. In cases where base course is collapsing, SEC shall be informed and the existing pavement shall be cut further to repair it upon approval. The additional pavement cut will depend on the severity of the collapsing base course or as required by the concerned Municipality. In SEC areas, the COMPANY REPRESENTATIVE shall specify this additional pavement cut. TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 28 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 FIGURE-3 TYPICAL CONDUIT HANGERS OR SPACERS ASSEMBLED CONDUIT HANGERS (TYPICAL) DWG # TC-0403-0200-00 TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 29 OF 30 TRANSMISSION CONSTRUCTION STANDARD TCS-P-104.03, Rev. 0 FIGURE-4 TYPICAL END-BELL DWG # TC-0403-0300-00 TCSP10403R0/YM Date of Approval: June 25, 2008 PAGE NO. 30 OF 30