The Southern African Institute of Mining and Metallurgy 8th International Corrosion Conference N Webb COMBINED EXTERNAL COATING AND CATHODIC PROTECTION ASSESSMENT TECHNIQUES – A CASE STUDY FOR A PIPELINE IN WEST AFRICA Neil WEBBc , Brian WYATTa, Marcel ROCHEb, John THIRKETTLEa, a Corrosion Control Associates Ltd, 3 Ivy Court, Action Trussell, Staffs, ST17 0SN, UK b Total SA, Tour Coupole 22D60, 92078 Paris-La Defense Cedex, France c Corrolec cc, 9 Kareeboom Ave, Fourways Gardens, 2191, RSA SUMMARY Recent developments in survey techniques and measuring equipment now allow for an accurate assessment of external coating condition and cathodic protection performance. These developments build on 20 years of experience of using Direct Current Voltage Gradient (DCVG) and Close Interval Potential Survey (CIPS) methods. The techniques use the latest advances in measurement systems coupled to a bespoke data processing system. The paper describes tests and trial surveys carried out on a hydrocarbon transmission pipeline in West Africa during 2005. The survey works described and conclusions drawn are from the data collected. Of particular interest are the apparent capacitance effects which are thought to occur under disbonded coating and the characteristics that these may show on the integrated CIPS and recorded DCVG profiles. This paper was originally presented at the Cefracor conference in Aix, France, in June 2006 The pipeline was originally installed on a phased basis between 1989 and 1994. The external coatings were three layer polyethylene factory coating and shrink sleeve field joint coating. An impressed current cathodic protection system was installed. The pipeline has subsequently been affected by disbondment of the coatings. It was a primary objective of the trials to attempt to identify such affected areas. In addition to a technically detailed account of the survey works undertaken and the results obtained the authors will consider the practical and commercial aspects of these surveys with input that provides a perspective from the specifier, pipeline surveyor, pipeline operations personnel and the pipeline owner. It is intended that the data presented will provide greater awareness of the benefits and limitations of the techniques used and their role for both stand-alone interpretation and the integration of the survey information with other inspection methods used for external corrosion assessment. The application of the described techniques is well developed and proven to locate and characterise through–coating defects and to provide a full audit of cathodic protection status. However, the possibility of the techniques being able to indicate disbonded coating is unproven and further tests and trials are planned which may allow a greater understanding of the electrical characteristics which are believed to be associated with disbonded coatings which may or may not be filled with an electrolyte. Further work is currently planned in West Africa, South Africa and Scotland in order to improve the understanding of this technique and to determine if the reported indications do actually represent a method of locating disbonded coatings. Keywords: External Coating, Cathodic Protection, DCVG, CIPS, corrosion assessment. Page 1 The Southern African Institute of Mining and Metallurgy 8th International Corrosion Conference N Webb INTRODUCTION It is widely accepted that no single method or technique exists that will locate where external coating systems have become disbonded from steel pipelines. Indeed, recent international technical seminars have addressed this issue in an attempt to create impetus for the conception of such a technique using innovative instrumentation. Recent advances in techniques for accurate cathodic protection performance assessment and external coating condition assessment/defect location have promoted the possibility that these systems, if used jointly, may provide sufficient data that can subsequently be analysed to show trademark indications where the coating may have become disbonded. At the commencement of this study it was considered possible that the characteristics of the data profiles at these locations could indicate through–coating defects that were associated with disbonded coating areas significantly larger than the through–coating defects that were known to be locatable. During the work certain unexpected electrical characteristics were recorded that may provide indications of the presence of disbonded coating. The techniques used are well developed and have been previously described [1]. The possibility that these data might locate disbonded coatings is in its infancy but has now been observed on pipelines both in West Africa and Scotland. Similar effects have been seen when surveying plastic sheathed power cables in South Africa. This Paper focuses on surveys and analysis of data collected from a pipeline located in Gabon, West Africa. The pipeline was constructed between 1989 and 1994 in phases to transport hydrocarbons from Production Centres to a process terminal some 234 km distant. The route of the pipeline is through heavily vegetated tropical rainforest to open scrublands. Numerous water courses and open saline water crossings are transited whilst crossings include vehicle access tracks and surfaced roadways. Pipeline Details Terminal Cathodic Protection Installations. Transformer Rectifier Stations Section 3 – 29Kms Station Section 2 – 100Kms Solar Station Total Length 234Kms Station Section 1 – 105Kms Line constructed in sections as shown above. Section 1 – Constructed 1989 Section 2 – Constructed 1989 Section 3 – Constructed 1994 Page 2 Production Centre Section operating at temperature higher than 55°C (13 Kms) The Southern African Institute of Mining and Metallurgy 8th International Corrosion Conference N Webb Technical details of the pipelines are shown hereunder: • • • • • Constructed to 100 bar MAOP Inlet pressure to transmission pipeline – 40 bar at Production centre Pipeline inlet temp – 60° C (to prevent wax deposition in Production Centre) General electrolyte conditions – wet compacted sand pH 5.4 (measured at a location where corrosion underneath disbonded coating was detected) • External Coating: o Factory applied coating - 3 Layer Low Density Polyethylene (LDPE) applied in accordance with internationally recognised corporate specification including FBE thickness of >70 microns. o Field joints - heat shrink sleeves with hot melt adhesive applied to fast curing liquid epoxy on brush-cleaned surface. o Coating application fully inspected during installation in both factory and field. • Pipeline wall thickness – 7.67 mm • Corrosion allowance on wall thickness – zero Cathodic Protection was installed at the time of construction and was of impressed current design. Conventional cathodic protection stations, powered by transformer-rectifier units, were installed at the end of each pipeline section between the Production Centre, intermediate Stations and the Terminal where ac power was available and two additional solar powered stations were installed at intermediate points within Section 1. Several years after the commissioning of the cathodic protection systems, excessively negative pipe/soil potentials were recorded in Section 1 for a short period of time due to the malfunction of one of the solar powered systems. The solar powered system controllers were vulnerable to lightning strikes in the area and this resulted in uncontrolled excessive current output; these were subsequently decommissioned. This occurrence in 1991 led to the readjustment of cathodic protection levels throughout Section 1 in accordance with international standards. At that time the cathodic protection criteria for minimum (least negative) pipe/soil potential levels was set at –950mV and maximum (most negative) potential levels –1150mV with reference to a saturated copper/copper sulphate reference electrode. Generally, potential levels have been maintained in accordance with these criteria but have normally been recorded as energised (ON) potentials recorded with the cathodic protection flowing. Recent survey potential measurements recorded with current interrupters fitted to the cathodic protection power sources, to allow the more accurate measurement of Instant OFF (polarised near IR drop error free) potentials have indicated that operating levels have actually been less negative than –950mV with respect to Cu/Cu SO4. An Intelligent Pigging / In Line Inspection [Magnetic Flux Leakage (MFL)] survey carried out in 2004 indicated the presence of external corrosion on the transmission pipeline. A total of 13600 defects were reported and these were categorised as follows: 12494 № Defects (92%) – metal loss at less than 20% wall thickness 1168 № Defects (approx 8%) – metal loss between 20% and 40% wall thickness 11 № Defects (approx 0.08%) – metal loss greater than 40% wall thickness Page 3 The Southern African Institute of Mining and Metallurgy 8th International Corrosion Conference N Webb The maximum metal loss defect recorded by the MFL intelligent pig was pitting to 57% of wall thickness (4.38mm) recorded some 2.2Kms from the Production centre. An analysis of the defects recorded was carried out in accordance with ASME B31G specification and this concluded that the mechanical integrity of the pipeline, under the service conditions, had not been compromised. The areas of greatest corrosion damage have been repaired. Following receipt of this information, three excavations were carried out along the pipeline route close to locations where defects had been recorded and these endorsed the findings of the intelligent pig survey. External corrosion was confirmed and pit depth measurements were in accordance with the expectations from the intelligent pig survey. The cause of the external corrosion was established as disbonded coating such that cathodic protection currents were prevented from flowing to the steel substrate surface. Pipe/soil potential measured in a conventional manner (ON) with the reference electrode positioned close to the pipeline at the location indicated a level of –1012mV with respect to Cu/CuSO4. Investigations carried out at the time concluded that the disbonded coating was confined to the heat shrink field joints. It was later established that the coating disbondment had also occurred to the factory applied 3 Layer LDPE [2]. A survey technique was therefore required that would indicate the presence of disbonded coating together with locations where corrosion may not have occurred to the steel substrate but the risk prevailed. Ideally the characteristics of disbonded coatings under the conditions where the void was either filled with a conductive electrolyte or not was required. As no single proprietary method was available to determine this condition, trials were carried out using traditional, well proven methods. These included Close Interval Potential Survey (CIPS) techniques to closely examine the profile of applied cathodic protection values together with a recorded Direct Current Voltage Gradient (DCVG) to examine the characteristics of coating defects and the capacitance effects of voltage gradient and attenuation. The intent was to determine, as far as possible using highly accurate measurements, that the cathodic protection potential at the steel interface was operating at a level that complied with international standards for minimum polarised values and that voltage gradients were acceptable and operating within conventional limits. A trial survey programme was set up and carried out during April and May 2005 under different circumstances to replicate the prevailing conditions and to characterise the pipeline in an attempt to determine the most likely locations of disbonded coating. SURVEY DETAILS In order that the trials would provide meaningful data a specification was prepared to ensure that the testing carried out was to the highest possible accuracy. Consultants were therefore engaged to prepare a specification for the proposed trials. The specification detailed requirements for the characterisation of the pipeline in respect of cathodic protection polarised potentials, cathodic protection currents flowing, other DC earth currents flowing along the pipeline and AC earth currents flowing along the pipeline. This was required in order to provide base indices against which the close interval potential and direct current voltage gradient surveys could be calibrated. Specified and rigorous requirements were also detailed for the close interval potential and direct current voltage gradient survey equipment, the accuracy of synchronisation between current interrupter units and data loggers, the accuracy of measured voltage values, the regular calibration and demonstration of all these characteristics in the field, and the competence of operating personnel. This was to ensure that Page 4 The Southern African Institute of Mining and Metallurgy 8th International Corrosion Conference N Webb precision measurements were recorded by personnel experienced in the measurement and interpretation of the data that was collected. In total nine tests were carried out on selected sections of pipe where coating defects including disbondment had been previously noted and on sections which were thought to be free of coating defects and disbondment. Seven of these tests were recorded CIPS and DCVG, where data sets were recorded and profiled for analysis. A recorded Pearson survey was also used as a comparative technique in an attempt to seek synergy. The Pearson survey provided information regarding through–coating defects, where the steel substrate had become exposed to the electrolyte but provided no information which was indicative of coating disbondment. Following a two trial surveys this technique was abandoned. For the purposes of clarity the following information is provided: Close Interval Potential Survey (CIPS) The technique entailed the measurement of the structure/electrolyte/reference electrode potential (ON and Instant OFF) at close intervals along the route of the selected pipeline section. Typically, pipe/soil potential measurements were recorded at between 1 and 2 metre intervals along the pipeline route. The potential measurements were recorded by a specifically designed cathodic protection measurement data logger from which a graphical profile of the pipe/soil potential data could be produced following the completion of the data collection survey. The accuracy of potential measurements recorded was determined, in part, by the location of the reference electrode relative to the protected structure. This was as close to the crown of the pipe as reasonably possible but was restricted in the field by the practical placement of the reference electrode with respect to the pipeline. It was not always possible to place the electrode directly over the crown of the pipeline at all locations due to vegetation growth and other obstacles. Right of way showing Jungle encroachment CIPS surveyor with DCVG trailing cable. In order that the Instant OFF potential measurements were as accurate as possible, minimising the IR drop error caused by the cathodic protection current flow, the applied cathodic protection current was interrupted for a brief time period. Typically all cathodic protection current sources to the section of pipeline being protected were interrupted simultaneously and the Instant OFF potential measured, before depolarisation of the pipe but after switching spikes and pipeline capacitive effects had decayed. This wait time for switching spikes and reactive effects was normally within 100 – 200 ms of the switch OFF time. It was necessary that the data logger measurement period occurred immediately after this wait period and that Page 5 The Southern African Institute of Mining and Metallurgy 8th International Corrosion Conference N Webb all switching devices and the data logger were sufficiently synchronised. The 10ms specified accuracy of the system ensured this, and that all switching devices were switched open circuit for the entire OFF measurement period. In order to minimise depolarisation of the pipe during the survey a current interruption cycle ratio of 4:1 ON: OFF was typically used. Where fluctuating stray earth currents were suspected to be present and affecting the pipe/soil potential with time, a second (static location) data logger was deployed to collect pipe/soil potential data simultaneously on the same synchronised time base as the (mobile) data logger which was used to survey along the pipeline. The data was used for the purpose of identification of interaction effects which could cause local variances in pipe/soil potential measurement at specific times/locations. Direct Current Voltage Gradient Survey (DCVG) The technique measured voltage gradients caused by the cathodic protection current flow through the soil to the pipeline (without any additional or increased impressed current which is sometimes employed in analogue DCVG measurements). Greater current density occurs at coating defects that expose bare steel with resulting increased voltage gradients in the soil. The locations of defects in the external coating are therefore identified by peaks in the soil voltage gradients. In conventional, non-recorded analogue DCVG surveys, the measurements recorded are not absolute but show changes in the voltage gradient by indicating a fluctuating value on a centre zero analogue instrument. Transformer Rectifier Precision Timer / Switching Device Optional Static Data Collector Defect Defect Defect Stray Current Soil Variance 0 Metallic Contact Static Data on another graph -200 DCVG +200 0 -200 Precise Time Linkage Mobile , DCGV and Static Combined Enhanced CIPS and Recorded DCVG to Indicate Defect Size Page 6 The Southern African Institute of Mining and Metallurgy 8th International Corrosion Conference N Webb In the combined CIPS and DCVG technique used in the survey work (see previous illustration) the actual ON/OFF values were measured and recorded on the data logger at the same time and at the same location as the ON/OFF potential measurements. A detailed resumé of the technique may be found in reference [1]. The data collections were effectively a combination of the CIPS, DCVG and Intensive methods defined in EN 13509: 2003 and DIN 50925: 1992. The simultaneous recording of CIPS and DCVG data allows the calculation of defect size in terms of the formulae developed by Baeckman and Schwenk [3] ANALYSIS OF RESULTS During the surveys, it was noted from the daily data download and review that there appeared to be a large number of soil voltage gradient indications, and that these indications were frequently not of the classical sine wave shape that would be expected of individual defects. Given that the pipeline field joints were a known point of concern, the survey team was concerned that the standard spacing between the front and back poles for DCVG measurement (10m) was possibly too close to the pipe joint length of 12m to allow adequate resolution. Surveys with lateral electrode DCVG measurements and trials with both 9m and 18m spacing in the front – back trailing electrode DCVG measurements were undertaken, and a final electrode spacing of 9m front – back trailing electrodes was selected for all further work. During the survey, it was further noted that there was a significant variation in soil potential gradient measurements depending on the exact position of the poles. This variation was of a similar magnitude to the actual gradients being measured. Further, it was at times impossible to survey over the crown of the pipe due to encroachment of vegetation. The accuracy of the individual reference electrodes was checked on several occasions prior to, during and after individual surveys. These tests comprised both comparison against a standard electrode and measurement of differential between electrodes at a common point during the survey. The electrode potentials were found to be within the specified limits at all times. The survey conditions were ideal, with no significant stray current, and wet conditions ensuring good electrical contact between the electrodes and the ground. The “scatter” was therefore related to the positioning of the electrodes, resulting from very small potential gradients in the soil. As the linear resolution of the survey was one metre, several readings were obtained per metre due to the slow survey speed. In order to extract significant data from the results, the raw data was processed to provide a single “average” data point per metre. This exercise has clarified the graphs and facilitated the identification of very small gradients along the route. The figure below illustrates the resulting traces of CIPS, DCVG and calculated defect size from a typical section of the survey. Page 7 The Southern African Institute of Mining and Metallurgy 8th International Corrosion Conference N Webb Defect Size Equivalent Defect radius (m) 0.2 0.1 0 -0.1 -0.2 0 100 200 300 400 500 300 400 500 DCVG -100 Gradient (mV) Chainage (m ) -50 0 50 100 0 100 200 CIPS -1500 Defect marker -700 Access path Detour -900 Marker post 201.6 -1100 Defect marker -1300 TP 90 Potential (mV) Chainage (m ) -500 0 100 200 Chainage (m ) 300 400 500 Test 2 - 22/04/2005 - CIPS and Recorded DCVG from TP 90 towards Rabi The extensive, albeit small, gradient pattern exhibited along the pipeline sections surveyed was found to be related to the pipe joint length. There were many instances where the gradient peaks were exactly 12m apart. A typical example is shown in the figure below. Recorded DCVG channel indicating 12m signature Gradient (mV) -50 -25 0 25 50 650 662 674 686 698 710 722 734 746 Chainage (m ) 758 770 782 794 806 818 830 Extract of the “gradient” channel plotted on 12m grid However, most of these did not have through–coating defects. This is indicated by these locations showing the same soil potential gradient profile with the CP current on and off; through–coating defects would have shown significant variation between the ON and OFF soil potential gradient. Those that did exhibit a differential between “ON” and “OFF” gradients are the most likely candidates for corrosion underneath the disbonded sleeves as they would appear to have through–coating defects that will allow electrolyte to access the steel surface under the disbonded coating. Examination of the survey results revealed that those indications with a differential between “ON” and “OFF” soil potential gradients were accompanied by a characteristic “valley” in the CIPS traces. This is further evidence that these locations are typical of through–coating defects: they may be with or without disbonded coating. Page 8 The Southern African Institute of Mining and Metallurgy 8th International Corrosion Conference N Webb The soil potential gradient traces which show no difference between “ON” and “OFF” (standing gradients) cannot be related to through–coating defects as there is no current flow. Similar characteristics have been observed on other surveys where disbonded coatings were known to exist, and where the electrical characteristics of the outer insulation layer had been compromised. The exact mechanism of this phenomenon is unknown at present, but is postulated to be related to capacitance effects between the pipe and the soil. Indications are that the combined CIPS and Recorded DCVG survey has apparently provided a means of locating disbonded sleeves and differentiating between those where corrosion beneath the sleeve is likely to occur as a result of capillary water ingress. The “standing” and “differential” gradients revealed by the survey are apparently associated with joint sleeves, with the differential gradient locations displaying typical coating defect characteristics in the CIPS results. Defect sizes are apparently small, which is commensurate with capillary defects under sleeves. It is intended that these indications will be verified by excavation and visual examination of pertinent locations. A second aspect of the survey, which is related to the conventional use of CIPS to establish polarised CP levels, was the relatively high IR factor identified in the ON readings for the pipeline. The pipeline CP system had historically been operated based on the ON readings at test posts. Using a relatively conservative IR factor, extrapolation of historical test post potential data revealed that the pipeline had possibly not been fully protected. This may have contributed to the extent of corrosion at the disbonded sleeves. The survey also confirmed that the test post data at 3km intervals was not fully representative of conditions throughout the pipeline. The following figure indicates a recent set of test post ON data with an extrapolated OFF data-set based on IR factors observed during the survey. ON and extrapolated OFF potential data from 3km spaced test points. Page 9 The Southern African Institute of Mining and Metallurgy 8th International Corrosion Conference N Webb CLIENT PERSPECTIVE It is too early to conclude whether this new technique (without over-impressed DC) gives significantly more detailed and valuable information, compared with the association of “conventional” ON/OFF CIPS and DCVG (unrecorded, generally performed using additional current source to accentuate the voltage gradients at the coating defects, carried out separately). The first analysis of data has given a good enough impression to justify further study of the “Integrated method”. This will be done, first through a complete and detailed comparison of the results obtained on the sections surveyed with the conventional methods and this new one, together with the results of In-line Inspection. Depending on the results of this comparative study, a programme of new surveys and measurements will be formulated and carried out on the field. The final objectives are to be able to develop survey methods that will ensure: - Detection of all corrosion locations underneath disbonded coatings - Identification and location of disbonded coating areas - Appreciation of corrosion risks underneath disbonded coatings (presence or not of electrolyte and renewal thereof). In order to achieve these ambitious objectives (if they are achievable), a lot of effort and further field testing will be required in the near future. Collaboration by all - end users and service specialised companies - is necessary to expedite this process. *** REFERENCES [1] Brian Wyatt, “Advanced Systems Of Overline Assessment Of Coatings And Cathodic Protection”, UMIST Cathodic Protection Conference, UMIST, Manchester10-11th February 2003. [2] Marcel Roche, Denis Mélot, Gildas Paugam, “Recent experience with pipeline coating failures”, 16th International Conference on Pipeline Protection, Paphos, Cyprus, 2-4 Nov. 2005, BHR Group [3] Von Baeckmann, W. Schwenk, W. & Prinz, W., eds., “Handbook of Cathodic Corrosion Protection”, 3rd Edition, Gulf Publishing Co, Houston, Texas, 1997 Page 10