PROJECT MANAGEMENT RISK MANAGEMENT CONTENT 01 02 03 04 PERT CPM OTHER SIGNIFICANT INFORMATION STEPS PROGRAM EVALUATION & REVIEW TECHNIQUE Pert is a tool to determine the duration of an event and/or task to produce a more realistic timeline for a project Project managers often use this chart to make realistic schedules by setting estimates for each duration. PERT uses the following three-time estimates to get the expected activity time for planning projects with uncertain activity durations (https://ca.indeed.com/career-advice/career-development/pert-vs-cpm) RISK MANAGEMENT PERT PROGRAM EVALUATION & REVIEW TECHNIQUE PERT OPTIMISTIC SHORTEST PERIOD TO FINISH A PROJECT MOST LIKELY COMPLETION TIME WITH THE HIGHEST PROBABILITY PESSISMISTIC LONGEST DURATION TO COMPLETE A PROJECT CRITICAL PATH METHOD (CPM) in project management is a technique used to oversee projects where there's a specific time required to complete a project. Project managers use it to determine the critical and non-critical tasks that can help reduce conflicts and achieve desired results (https://ca.indeed.com/career-advice/career-development/pert-vs-cpm) When using CPM, managers start by preparing a list of all activities needed to complete a project. Next, you can estimate the time required to complete each activity and determine the dependencies between the activities. You can then define the path as a sequence of activities in a (https://ca.indeed.com/career-advice/career-development/pert-vs-cpm) network RISK MANAGEMENT CPM SIGNIFICANT INFORMATION MANPOWER PRODUCTIVITY RATE CONSTRUCTION SEQUENCE BUDGETARY ESTIMATES STEPS CREAT A WBS TABLE, IDENTIFY EVENTS and TASKS IDENTIFY ALL ACTIVITIES THAT NEEDS TO BE DONE ON A PROJECT IDENTIFY EACH SUCCESSORS OF EACH ACTIVITIES IDENTIFY EACH PREDECESSORS OF EACH ACTIVITIES ACTIVITIES PREDECESSORS SUCCESSORS STEPS CREAT A WBS TABLE, IDENTIFY EVENTS and TASKS STEPS DETERMINE DURATION