OTC 19800 Medium Radius Horizontal Sidetracks Reduce Time, Cost and Risks in HT Ghawar Field Wells Michael A. Simpson, Abdul Al-Hamid, Yusri Faraj, Mohamed Khalil, Roberto Duran, Clayton L. Miller, and Shaker Al-Khamees, Saudi Aramco, and Jeff Stewart, Halliburton Copyright 2009, Offshore Technology Conference This paper was prepared for presentation at the 2009 Offshore Technology Conference held in Houston, Texas, USA, 4–7 May 2009. This paper was selected for presentation by an OTC program committee following review of information contained in an abstract submitted by the author(s). Contents of the paper have not been reviewed by the Offshore Technology Conference and are subject to correction by the author(s). The material does not necessarily reflect any position of the Offshore Technology Conference, its officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written consent of the Offshore Technology Conference is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of OTC copyright. Abstract Saudi Aramco’s first medium radius horizontal sidetrack gas well, Haradh-AX1, was drilled and completed in June, 2008 in a record time of 48.7 days with 4,989 ft of reservoir contact and a 33% reduction in overall cost. The previous, Khuff-C Horizontal sidetracks which included the same operations; de-completion, sidetracking and re-completion, averaged 83 days with 3,441 ft of sidetracked lateral across the Khuff-C. Directional drilling in the medium radius lateral after building at 12°/100 ft to a sail inclination of 88° was characterized by better bit performance, lower torque and drag, improved wellbore stability and steerability. In the previously employed long radius horizontal sidetrack design, extensive milling operations were required to gain access to the 8-3/8” open hole to sidetrack. The 8-3/8“long radius build section would then be drilled from the Base Jilh Dolomite, across the troublesome and sometimes abnormally pressured Lower Jilh and Sudair Shale formations to the top of the Khuff-C where a new 7” liner would be run and cemented. The 57/8” lateral would then be drilled across the Khuff-C and an open-hole completion run. In the medium radius design, the sidetrack (ST) could be made deeper, in the same pressure regime, by cutting a ST window in the existing 7” liner 450 ft true vertical depth (tvd) above the Khuff-C target reservoir, kicking off and drilling 5-7/8” hole across the Khuff-C to total depth (TD). This paper further details the time and cost savings possible from the application of proven medium radius drilling technology from Saudi Aramco’s Arab-D Horizontal Oil wells produced from 6,500 ft tvd to the deep gas wells produced from the Khuff formation at 12,000 ft tvd, a new drilling environment. More medium radius horizontal sidetracks are planned and a similar medium radius Khuff-B Horizontal ST, ANDRAX1, which built at 32°/100 ft, was just successfully completed at 14,819 ft with a 2,400 ft horizontal section. Introduction Previously, a total of nine horizontal re-entry/sidetracks were performed on existing poor to non-producing gas wells in the Ghawar field of Saudi Arabia owned and operated by Saudi Aramco. The general procedure was to mill out the 7” liner overlap (500 ft -1100 ft) to around 150 ft below the 9-5/8” shoe. The milling was extremely tedious and time consuming because of milling related problems such as the formation of “bird’s nests” (packing off of swarf in the milling annulus), stuck pipe, inconsistent mill performance and difficulty maintaining milling fluid low-end rheology. A cement sidetrack plug would then be set in the 8-3/8” open hole, after which the sidetrack would be kicked-off with a long radius build trajectory (typically 3 to 7°/100 ft) to the top of the Khuff-C formation and a new 7” liner was run and cemented in place. Once the usually higher pressured by as much as 2,400 psi, Khuff-A & Khuff-B formations are cased off, the 57/8 in. section of the long radius trajectory would continue building inclination to about 90° across the target producing zone; the Khuff-C; using the minimum required mud weight to drill to TD. An alternate approach was to set a whipstock in the 9-5/8”. casing above the 7” liner top, cut an 8-3/8” window in the 2 OTC 19800 9-5/8” casing and continue drilling with a long radius build trajectory in the same manner as cited above to the 7” liner point in the top of the Khuff-C. It was not always possible to apply this approach in all horizontal sidetrack candidate wellbore configurations. To minimize torque and drag, a lubricant was added to the drilling fluid after making a cost-benefit comparison between using a lubricant with a (Positive Displacement Motor) PDM vs. a Rotary Steerable system for drilling the horizontal section. By applying a medium radius horizontal drilling trajectory, considerable improvements could be achieved; mainly because it makes it possible to drill the entire horizontal sidetrack through one pressure regime and hole section, and thereby considerably reduce drilling time, cost and risk. A 73 pounds per cubic foot (pcf) low solids-non dispersed drilling fluid system was selected to minimize reservoir damage using the minimum required overbalance to maintain control of formation pressures during drilling operations. The hydraulics program and the wellbore cleaning techniques were designed to avoid cuttings build up in the horizontal section. Well Objective, Trajectory Selection For the candidate well, HRDH-AX1 the requirement from the Gas Reservoir Management Department was to decomplete the vertical well, clean-out the 7” liner, drill a 5,000 ft lateral into the Khuff-C Reservoir and run a new completion. Initially, two options were considered, the first consisted of milling out 870 ft of 7 in. liner, setting a 9-5/8”. whipstock, cutting a sidetrack window in the 9-5/8 in. casing, drilling 2,985 ft of 8-3/8” open hole and setting/cementing a new 7” liner. The 5,000 ft 5-7/8” lateral would then have to be drilled to TD. The total estimated time for this option was 80 days. The second option was to mill out 1,070 ft of 7” liner, set a cement sidetrack plug in the open hole and perform the sidetrack operation in 8-3/8” hole to the top of the KhuffC; then run and cement a new 7” liner. The 5,000 ft of 57/8” lateral would then have to be drilled to TD. The total estimated time for this option was 85 days. Applying medium radius horizontal drilling, the whipstock could simply be set in the 7” liner, a 5-7/8” window cut, and the 5-7/8” lateral drilled with a 12°/100 ft build rate from below the Khuff-B reservoir into the Khuff-C formation and reservoir. The total estimated time for the medium radius option was only 50 days along with significant cost and risk reductions and was therefore selected. Wellbore schematics and the directional plan are shown in Figures 1, 2 and 3. Well design considerations. For cutting the sidetrack window, a single trip mechanical whipstock was selected with a conventional (lead/follow/dress) tri-mill assembly to cut the window. It was deemed advantageous to minimize dog-leg severity across the window section and rat hole and to re-dress the window if any of the mills came out more than 1/8” undergauge. Torque and drag analysis were performed prior to the start of operations to select the optimum drill string configuration and to avoid drill string failures which may have led to time and cost consuming fishing operations. Drilling Results De-completion / Whipstock / Window The well was de-completed in a total of seven days. A GR/CCL log was run prior to running the whipstock for correlation purposes and to assure the whipstock was not set across a casing collar. It was critically important that the whipstock was set at the correct depth, i.e., below the higher pressured Khuff-B reservoir to avoid differential sticking problems while drilling the lateral across the Khuff-C formation later on. The proper whipstock setting point was selected at 11,104 ft. The cutting of the window from 11,104 ft to 11,116 ft and drilling out of 5 ft of rat hole was accomplished in four days; two BHA’s (bottom hole assembly’s) were used for this purpose, the second trip was used to dress out the window in order to avoid problems later on while tripping through it. High viscosity hole cleaning pills were also run to assure adequate borehole cleaning. Directional Drilling The build section was drilled with a build-up rate of 12.1°/100 ft with an average rate of penetration (ROP) of 10.3 ft per hour (fph). For the first build assembly, an International Association of Drilling Contractor’s (IADC) code 6-2-7 tungsten carbide insert (TCI) bit was run on a 7/8 lobe low speed/high torque PDM with (adjustable bent housing (AKO) set a 1.5°. The TCI bit was run because of its superior tool face control as compared to PDC’s across the build section. The build section was successfully drilled in 15 days very close to the plan line as shown in Figure 4. PDC bits were used to drill the rest of the trajectory with a “soft landing” into the lateral section of this carbonate reservoir, with ROP’s up to 26.1 fph and 495 ft progress per day at the end of the 4,989 ft lateral. The lateral section was drilled in 28 days with an average ROP of 18 fph to a TD of 16,810 ft MD/11,904 ft TVD. A total of five BHA's were used to control inclination and azimuth in the well; two for the build-up section, two for drilling the lateral section and one for lateral section geosteering to TD. OTC 19800 3 entry sidetracks for Saudi Aramco in the Ghawar Field. Detailed BHA's, Motor performance and bit runs are shown in Tables 1, 2 and 3. Drilling Optimization The bulk of the overall time savings were achieved in the open hole drilling section, whereas the de-completion, whipstock setting and window cutting operation times were basically the same as in previous wells as shown in Figure 12. A great portion of the time and cost savings in the drilling phase are attributed to the fact that on bottom drilling time constituted 51% of the total time, while trip time was only 19%. Good hydraulics and drilling fluid properties resulted in only 8% circulating time to sweep and clean the hole. A detailed operational summary is given in Figure 5. The regular additions of the commercial lubricant achieved torque reductions ranging from 2,000 to 2,500 ftlb. The open hole friction factor was reduced from 0.38 to 0.22 as shown in Figures 6 and 7. • Planning and careful performance tracking are essential tools to achieve optimum performance from each bit and BHA run. • The use of a commercial lubricant in the drilling fluid system and good hydraulics were very effective in reducing torque, drag and hole problems. • The theoretical advantage of reducing build section length to reduce overall torque across the trajectory was fully realized in HRDH-AX1. • It is apparent that the Khuff-A, B and C reservoirs all have sufficient thickness and spacing such that they can be selectively sidetracked into and drilled in the same pressure regime and hole size, using medium and short radius trajectories. By carefully selecting, monitoring and re-analyzing BHA and bit performance, several impressive bit runs were achieved in this well, the last two bit runs were both in excess of 2000 ft. Detailed performance data is provided in Figures 8, 9 and 10. Figure 11 depicts the drilling days vs. depth curve; the total operation time employed was 48.7 days compared to 56 days planned. Completion The well was completed with a 7” production packer and 4-1/2” carbon steel tubing string in 10 days. Acknowledgements The authors wish to thank the management of Saudi Aramco and Halliburton for permission to publish this paper. Special thanks to Saudi Aramco Drilling Foreman Ghazi Ali, Nick Copely and Kenton Paul; without whose hard work and expertise, this project may not have been successful. Conclusions • The Medium Radius horizontal drilling technique was successfully applied on the Haradh-AX1 well with a build rate of 12.1°/100’. References 1. Schuh, F. J.: “Horizontal Well Planning – Build Curve Design,” SPE Reprint Series No. 33 “Horizontal Drilling,” 1991. • A reduction of 34 operating days and 33% in operating cost was achieved using the Medium Radius Horizontal Drilling Technique with conventional BHA’s, Drill Pipe and Directional Tools compared to the last nine Long Radius Re- 2. Joshi, S.D.: Horizontal Well Pennwell Books, Tulsa (1991). Technology, 3. Azar, J. J. and Robello S, G.: Drilling Engineering, Pennwell Books, Tulsa (2008). OTC 19800 4 30” 108 ft 24” 440 ft 18 5/8” 1843 ft 13 3/8” 6308 ft 9 5/8” 8446 ft 7” 11983 ft Fig. 1. HRDH-AX1 Pre Re-entry/Workover Wellbore Schematic 30” 108 ft 24” 440 ft 18 5/8” 1843 ft 13 3/8” 6308 ft 7” Packer 9 5/8” 10,949 ft 8446 ft TOW 11,104 ft EZSV 11,122 ft BOW 11,116 ft 16,810 ft MD/11,904 ft TVD 7” 11983 ft 5313 ft Fig. 2. HRDH-AX1 Post Re-entry/Workover Wellbore Schematic OTC 19800 5 Fig. 3. HRDH-AX1 Directional Plan. OTC 19800 6 SECTION DETAILS PLAN VIEW Fig. 4. HRDH-AX1 Actual Directional trajectory BHA # MOTOR RUN # 1 2 3 4 5 6 7 1 2 3 4 5 HOLE SIZE (IN) 5.7 5.875 5.85 5.875 5.875 5.875 5.875 INC. IN (DEG) 1.3 1.6 2.1 19.4 79.8 86.2 89.3 INC. OUT (DEG) 1.6 2.1 19.4 79.8 86.2 89.3 75 DRLG (HRS) 10 2 19 73 28 119 130 OBJECTIVE ORIENT WHIPSTOCK DRESS WINDOW BUILD UP BUILD UP LAND INTO RESERVOIR GEOSTEERING DRILLING LATERAL GEOSTEERING Table 1. BHA Summary MOTOR RUN # LOBE OD (IN) BEND (DEG) DLS (°/100 FT) 1 2 3 4 5 7/8 4/5 4/5 4/5 4/5 4.75 4.75 4.75 4.75 4.75 1.5 1.5 1.5 1.5 1.5 16 15 12 12 8 Table 2. Motor Summary ROP (ORI) (FT/HR) 10 7 3 10 6 ROP (ROT) (FT/HR) 6 11 18 20 18 OTC 19800 7 BIT # STYLE 1 2 3 3RR 4 SL51 DSX411X SCD320 SCD320 HCM407Z OD (IN) 5.875 5.875 5.875 5.875 5.875 TFA 2 (IN ) 0.389 0.442 0.435 0.435 0.383 FOOTAGE HRS ROP DULL GRADE 174 582 367 2281 2273 19 73.25 27.5 119.08 129.5 9 8 13 19 18 1-1-WT-A-E-I-ER-PR 3-3-BT-G-X-I-LN-BHA 1-1-CT-G-X-I-WT-BHA 1-4-CT-G-X-I-NO-BHA 1-2-CT-A-X-I-NO-TD Table 3. Bit Summary Fig. 5. Operation Summary/Time Breakdown OTC 19800 8 Fig. 6. Torque Reduction with lubricant in mud system. Fig. 7. Friction factor reduction with commercial lubricant in drilling fluid OTC 19800 9 Fig. 8 -BHA Breakdown Fig. 9. BHA Performance OTC 19800 10 Fig. 10. – BHA Footage OTC 19800 11 Fig. 11. – HRDH-AX1 Days vs. Depth Drilling Curve after Setting Whipstock @ 11,104 ft OTC 19800 12 35 PROGRAM ACTUAL 33 30 28 25 20 DAYS 15 10 10 10 7 7 4 5 2 2 2 0 DE-COMPLETION WHIPSTOCK WINDOW OPERATION DRILLING Fig. 12. Actual/Planned Distribution Time COMPLETION