Options Next 80 MW of Electricity from Biofuel in Kymin Voima Asko Rantee Kvaerner Power Oy Finland Jouni Kinni Kvaerner Power Oy Finland Antti Rainio Kymin Voima Oy Finland Options Previous Next 1. POWER PLANT PROJECT Kymin Voima made the investment decision for a new 80MW electricity and 180 MW heat producing biomass power plant in June 2000. The main equipment was purchased in August and in less than two years, in summer 2002, the new power plant was in operation. The project was spread over ten main contracts and dozens of smaller delivery agreements. The project team was assembled from UPM-Kymmene’s project and mill personnel. PVO Engineering and Projekti-insinöörit acted as the main engineering consultants. The main equipment suppliers and the project time schedule are shown below. Table 1: Main equipment suppliers: Bubbling fluidized bed boiler plant: Kvaerner Power Oy Fuel handling: BMH Wood Technology Oy Back pressure turbine and generator: Alstom Finland Oy LP and HP feed water heat exchangers: Andritz-Ahlstrom Oy Feed water pumps: KSB Demineralized water plant: YIT Environment Oy HP and connecting piping: YIT Power Oy LP and heating piping: Steka Oy Electrification: Vaasa Engineering Oy, ABB Industry Oy, Siemens Osakeyhtiö DCS: Metso Automation Oy Table 2: The Kymin Voima project time schedule Investment decision: June 2000 Main equipment purchases: August 2000 Start of construction: March 2001 End of erection: March - June 2002 Commissioning: June - August 2002 Options Previous Kymin Voima is the company that was established for this power plant. Pohjolan Voima, a Finnish forest industries power company, owns 76% of Kymin Voima. Kouvolan Seudun Sähkö, a local utility company, owns the rest. The power plant is located in the UPMKymmene’s Kymi Paper mill in Kuusankoski. The towns of Kuusankoski and Kouvola, with a combined population of around 50,000, are located within 5 kilometres of the plant. Each of these towns has its own district heating networks. Figure 1: Kymin Voima Power plant Next Options Previous Next 2. COMBINED HEAT AND POWER PRODUCTION Kymi Paper is the third largest pulp and paper mill in Europe with an annual paper production of 920,000 tons and pulp production of 520,000 tons. The mill uses 2.3 million cubic meters of wood annually as raw material. The bark from this wood accounts for approximately half of the fuel used in the new power plant. The heat demand from the mill and the towns forms the basis for the operation of the power plant. At nominal load it produces 125 MW of process steam and 15 MW of hot water for Kymin Voima as well as 40 MW of district heat for the area. At this load the power production is 76 MW and fuel input to the boiler is 290 MW. The plant achieves an overall efficiency of over 88% and the power to heat ratio is 0.42. The Kymin Voima power plant is connected to the Kymi Paper medium and low-pressure steam networks for distributing the process steam to the three paper machines and other heat consumers at the mill. In addition to the new plant, the two existing recovery boilers produce at maximum 94 kg/s of steam for two older turbines with nominal capacities of 28 and 15 MW. As a back-up, the mill has a natural gas fired boiler producing medium pressure steam. The mill steam network is shown in figure 2. KYMIN VOIMA Kymi Paper Oy SK1 110 t/h 114 bar 540°C KPA 265 MWf 385 t/h SK2 250 t/h MK 120 t/h 84 bar 84 bar 480°C 480°C G GT1 G GT2 MAX 15 MW 0 – 20 t/h 16 bar 200°C 230 t/h 110 t/h MAX 85 MW G MAX 28 MW 0-50 t/h 0-15 t/h 13,5 bar 0 – 10 t/h Accumulator 3,5 bar 115-300 t/h OWN USE OWN USE OWN USE Kouvola + Kuusankoski 0-40 MW 4,5 bar COOKING C3 ja PK7 KYMI Hydro power plant Koskela 0 - 15 MW 3,5 bar Kni. heating Pk1/2, FC,Ky.läm CONDENSOR 0-60 t/h PK9 PK8 PK7 KAL COOKING EVAP. DRYING Figure 2: Kymin Voima Power plant and Kymi Paper steam network. Options Previous Next 3. FUELS The main fuel for the new boiler will be bark from the pulp mill’s debarking plant. It will cover about half of the expected 2100 GWh annual fuel demand. UPM-Kymmene’s nearby saw mills produce saw dust and wood residue, which are also combusted in Kymin Voima. The mill’s waste water treatment plant produces sludge, which needs to be burned off. After mechanical drying the sludge gets a positive heating value and produces energy in the boiler. In the first years the main fuel purchased will be peat, covering about 28% of the annual fuel energy. However, the target is to reduce the peat consumption and increase the share of forest residue and whenever its production in the area increases. Table 3: Expected fuel usage 2100 GWh / year Bark 49 % Forest residue 6 % initially Saw dust and wood residue 12 % Sludges 3% Peat 3% Natural gas 28 % 2 % start up and back up fuel The moisture content and heating value of the bark varies according to the species of wood and the time of year. The moisture is at its highest during winter time, when the boiler load is also at maximum. This situation provides the dimensioning basis for the boiler. Peat and forest residue somewhat level off the variation in heating value. Natural gas is used as startup fuel. It can be used as an auxiliary fuel with load burners, in the case of any disturbances in the solid fuel handling system. Options Previous Next Table 4: Fuel properties Moisture % LHV, MJ/kg Bark 50-59 (44-65) 6.6-10.2 Peat 45 (40-60) 11.3 Forest residue 55 (40-60) 7.4 Biosludge 70 (60-70) 2.5 Bark and water treatment sludge are conveyed from the Kymi Paper mill via belt conveyors to Kymin Voima’s 5000 m3 field storage. Wood fuels from the sawmills and forest residues are fed to the same storage. Before passing through to the storage they go though a screening and crushing station. Two screw feeders at the bottom of the wood fuel storage feed the fuel to a belt conveyor taking it to the boiler house. Peat comes to a separate receiving station and it is also screened, and larger pieces crushed before passing to the 2000 m3 field silo. The peat is conveyed from this field silo to its own feeding silo in the boiler house. BMH Wood Technology Figure 3: Outside fuel handling Options Previous 4. HYBEX BOILER During the last 20 years Bubbling Fluidized Boiler technology has become a dominant boiler technology in applications where a variaty of wet biofuels is combusted and high availability and low emissions are sought. Kvaerner Power Oy was selected as the supplier for the Kymin Voima project. When commissioned in summer 2002, the HYBEX boiler was the largest biofuel-fired BFB boiler in the world. Figure 4: Side view of the Kymin Voima HYBEX boiler Next Options Previous 4.1 Boiler systems The steam parameters of the boiler are 107 kg/s, 114 bar and 541 °C. With these parameters the boiler capacity is 269 MWth. The furnace width is 12 m, depth 11,4 and height 33 m. The boiler has three-stage superheating, the two last stages being made from high chromium alloy AC66. The boiler is equipped with a hydrobeam floor. The coarse removal system consists of 12 hoppers, three screw conveyor, one drag conveyor and a sieving station. Figure 5: Coarse removal system The Kymin Voima boiler is equipped with two independent fuel feeding line. Each line serves three fuel feeding points and has a capacity of up to 70 % MCR. In this project special attention was paid to the fuel feeding system in order to achieve accurate and even fuel feeding. Each feeding line has its own bark silo. There is a common peat silo in between the bark silos. Peat is mixed with the other fuels in a mixing screw. The drag conveyor has a special levelling chamber for the mixing and equalisation of fuel flow. Each feeding point is equipped with a feeding screw. Next Options Previous The separate peat silo at the boiler house makes it possible to adjust the heating value without delay when there is a variation in the moisture content of the main fuel. Figure 6: Fuel feeding system The air system consists of a primary air fan, a secondary air fan, steam coils and flue gas air preheaters. The boiler has a staged after-air system and the design is based on CFD modelling. The has four start-up and four load burners as an auxiliary and reserve firing system. The load burner capacity is designed for 200 MW, and the burners are combined natural gas / oil burners. The boiler is equipped with two ESPs and flue gas fans on the flue gas side. Next Options Previous 5. OPERATING EXPERIENCE 5.1 Start-up Boiler commissioning started in spring 2002. The first solid fuel firing was on 10.5.2002 and the boiler was handed over on 1.8.2003, two months ahead the original time schedule. The boiler has been running continuously since the end of July. 5.2 Operation mode The heat demand from the mill and the towns forms the basis for the operation of the power plant. Loads were therefore low during the summer. Towards the end of 2002 load demand had been increasing. The new HYBEX boiler also handles the load swings at the mill, while the two recovery boilers are running at constant load. This means that there is a great deal of daily load variation, as can be seen in Figure 7. 100 KYMIN VOIMA OY - BOILER LOAD SINCE START-UP HYDRO TEST 11.1.2002 FIRST GAS FIRING 9.4.2002 FIRST SOLID FUEL FIRING 10.5.2002 75 50 25 0 Figure 7: Boiler load variation Next Options Previous Next 5.3 Fuels The boiler has been operated with different fuel mixtures since start up. On a daily basis the fuel mixture varies a lot, as does the moisture content. Figure 9 shows the fuel usage. The natural gas consumption is exceptional due to the commissioning period. NATURAL GAS 7% PEAT 33 % HEAVY FUEL OIL <1% BARK +FOREST RESIDUES 59 % Figure 8: Fuel usage after start up 5.4 Emissions The official plant performance test was carried out during the last week of January 2003. The official test report will be published after submittal of this paper. Preliminary results shows, however, that the boiler performance appears to be according to design in terms of aspects such as overall process design, boiler adjustability, controllability and flue gas emissions. The guaranteed emissions for the boiler are 150 mgNO2/MJ, 15 mgN2O/MJ, 250 mgCO/nm3 (6 % O2 dry) and dust 30 mg/nm3 (6 % O2 dry). Previous Next EMISSION [mg/Nm3 at 6% O2] STEAM FLOW [kg/s] 250 STEAM FLOW CO NOx O2 after boiler 4.0 EMISSION AVERAGES: NOx 188 mg/Nm3 @ 6% O2 CO 25 mg/Nm3 @ 6% O2 3.5 200 3.0 2.5 150 2.0 100 1.5 1.0 50 0.5 0 OXYGEN AFTER BOILER [Vol-% wet] Options 0.0 0 10 20 30 40 50 60 70 80 90 100 110 120 MINUTES Figure 9: Emissions during a test run 5.5 Other experiences The start up and operation of the Kymin Voima HYBEX boiler has proceeded very smoothly. The boiler is the fourth new boiler in this size class (under 300 MW) to be delivered in the last seven years. This signifies that the design for this size of boiler has become very standardised, and the designers were able to utilize all the experiences gained from the earlier deliveries. It is well known that in a fluidized bed boiler operation the key factor in load and emission control is the fuel feeding system. Special attention was paid to the fuel feeding system in this project and the results so far are very positive. Options Previous 6. CONCLUSION The pulp industry has traditionally utilised biofuels to produce a large portion of their energy demand. The Kymin Voima project is a good example of the co-operation between a pulp mill and the surrounding communities in the co-generation of heat and power utilizing different kinds of biofuels. In large-scale biofuel firing, the fuel is typically a mixture of different kinds of fuels with different properties. This emphasises the role of the mixing and equalisation of fuel in emission and load control.