Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 6. Conceptual Design 6.1. Overhead Transmission Line Design Concept The design concept, including the following criteria focused on cost reduction, will be implemented based on the information collected and organized. The details of each criterion will be discussed with the counterpart organization based on the results of the field survey. For the 500kV Pharyargyii ~ Sar Ta Lin transmission line, in order to systematically connect the Pharyargyii ~ Hlaingthaya transmission line to the Pharyargyii Substation in the future, the same equipment specifications were implemented considering system reliability and O&M for the 500kV transmission system. The 230kV transmission line will also be matched with the existing transmission line in Yangon city, so that the equipment specifications will not conflict, for reasons of system reliability and O&M. In addition, if the transmission line is heavily loaded with current flow, the application of low-loss conductor technology will be considered. Normal ACSR Conductor Low-loss Conductor Figure 6.1-1 Normal ACSR Conductor and Low-loss Conductor 6.2. 500kV Transmission Line Design Overview of Transmission Line Route The route connecting Pharyargyii Substation and Sar Ta Lin Substation has an approximate route distance of 70km. Most of the route is along the river side. Pharyargyii-Sar Ta Lin 500kV T/L Route Pharyargyii S/S Sar Ta Lin S/S Figure 6.2-1 Route of 500kV Pharyargyii S/S – Sar Ta Lin S/S Design Conditions The basic design conditions are as mentioned below. 6-1 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (1) Ambient Temperature Maximum air temperature Minimum air temperature Annual average temperature 46 ºC 10 ºC 27 ºC (2) Conductor Temperature Maximum temperature Minimum temperature 75 ºC 10 ºC (3) Wind Velocity Maximum wind velocity 35 m/s (4) Wind Pressure Tower Conductor Ground wire Insulator 2,150 Pa 900 Pa 970 Pa 900 Pa (5) Stringent (the most severe design) Conditions and EDS (Every Day Stress) Conditions Conductors: Condition Stringent EDS Temperature 15 ºC 27 ºC Wind 900 Pa Still air Tension 40.0% UTS 22.2% UTS Temperature 15 ºC 27 ºC Wind 970 Pa Still air Tension 40.0% UTS 22.2% UTS Ground Wires: Condition Stringent EDS *UTS: Ultimate Tension Strength (6) Pollution Level Medium (IEC standard); 34.7 mm/kV (7) Other conditions assumed Maximum humidity 100% (8) Voltage Level for Insulation Design Lightning Impulse Withstand Voltage 1, 550 kV Switching Impulse Withstand Voltage 1,175 kV Maximum System Voltage 550 kV (9) Air Clearance Normal condition (D1) Normal wind condition (D2) Maximum wind condition (D3) 4,700 mm 4,200 mm (swing angle: 15º - 20º) 1,900 mm (max. swing angle: 60º) (10) Safety Factors Required minimum safety factors for the transmission line facilities were determined as follows. (a) Towers 1.6 to yield strength of the material under normal conditions (= stringent conditions) 1.3 to yield strength of the material under broken-wire conditions (= normal conditions + one ground wire or one phase conductor breakage) (b) Conductor/Ground wire 2.5 to UTS (Ultimate Tensile Strength) for stringent conditions 4.5 to UTS for Everyday Stress (EDS) condition at average temperature in still air at supporting point (c) Insulator string 2.5 to RUS (Rated Ultimate Strength) for maximum working tension at supporting point (d) Foundation 2.0 under normal conditions 6-2 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 1.5 under broken wire conditions Conductor and Ground Wire Design (1) Conductor and ground wire The results from power flow system analysis showed that 4 bundles of ACSR 468 mm2 (Drake) for conductors are appropriate for the project. Therefore, ACSR 468 mm2 for conductor and OPGW 115 mm2 and AS 110 mm2 for ground wire are applied. The technical characteristics of the conductor and ground wires are shown in the following tables. Table 6.2-1 Technical Characteristics of Conductor Type ACSR 468 ASTM (Drake) Al: 26/4.442 mm St: 7/3.454 mm 28.13 mm Component of stranded wire (Nos./Dia.) Overall Diameter 402.8 mm2 468.6 mm2 1,628 kg/km 140.2 kN 76.0 GPa 19.1 x 10-6/℃ 0.07167 Ω/km Cross Sectional Area of Aluminum wires Cross Sectional Area (Total) Nominal Weight Ultimate Tensile Strength Modulus of Elasticity Co-efficient of linear expansion DC Resistance at 20℃ Table 6.2-2 Technical Characteristics of Ground Wires OPGW115 mm2 AA: 12/2.85 mm AS: 19/2.85 mm SUS: 1/2.80 mm 14.25 mm 114.83 mm2 483 kg/km 72.4 kN 97.7 GPa 17.5 x 10-6/℃ 0.366 Ω/km (including OP unit) 24 Type Component of stranded wire (Nos./Dia.) Overall Diameter Cross Sectional Area (Total) Nominal Weight Ultimate Tensile Strength Modulus of Elasticity Co-efficient of linear expansion DC Resistance at 20℃ Number of Optical Fibers AC110 mm2 20SA: 19/2.7 mm 13.5 mm 108.8 mm2 722.5 kg/km 145.8 kN 155.2 GPa 12.6 x 10-6/℃ 0.787 Ω/km – (2) Maximum Tension and Every Day Stress (EDS) The standard span length was assumed as 450 m. The values of the maximum working tension and the EDS of both the conductor and the ground wires satisfy the determined safety factors shown in the following table. Table 6.2-3 Maximum Working Tension and Every Day Stress Type ACSR 468 mm2 (Drake) OPGW115 mm2 AC110 mm2 UTS 140.2 kN 72.4 kN 145.8 kN Tension Maximum Tension Every Day Stress Maximum Tension Every Day Stress Maximum Tension Every Day Stress 53.2 kN 31.0 kN 26.5 kN 11.6 kN 32.0 kN 18.8 kN Safety Factors 2.63 > 2.5 4.52 > 4.5 2.73 > 2.5 6.24 > 4.5 4.55 > 2.5 7.75 > 4.5 (3) Sag and tensions of the ground wires The sags of the ground wires under EDS conditions must be below 80% of the conductors’ sag at the standard span length to avoid a reverse flashover from the ground wires to the conductors and direct lightning stroke to the conductors. The tensions of the ground wires are determined to satisfy the safe separation of conductors and ground wires in the mid-span. (4) Standard Span Length The standard span length between towers is 450 m 6-3 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (5) Right of Way (ROW) The right of way of the 500kV transmission line is assumed to be 60.96m Insulator Design (1) Insulator type and size The insulator unit applied to the transmission line is a standard disc type porcelain insulator with ball and socket, complying with IEC 60305. 210kN type insulators are applied for the suspension towers and 300kN type insulators are applied for the tension towers. The technical characteristics of the insulators are shown in the following table Table 6.2-4 Technical Characteristics of the Insulator Rated Ultimate Strength IEC Designation Shell Diameter Unit Spacing Nominal Creepage Distance Ball & Socket Coupling 210 kN U210B 280 mm 170 mm 405 mm 20 mm 300 kN U300B 320 mm 195 mm 505 mm 24 mm (2) Number of insulator units per string The number of insulator units per string is 30 units for the suspension towers and 26 units for the tension towers. (3) Determination of Number of Insulator Strings per set The determinations of the number of insulators per string are as shown below. Contamination design Contamination level: Medium Creepage distance per voltage: 34.7 mm/kV Highest Voltage, Um: 500 kV × 1.2/1.1 ≒ 550 kV Total Insulator Creepage Distance: 550 kV ÷ √3 × 34.7 mm/kV ≒ 11,100 mm Number of insulator units: U210B: 11,100 mm ÷ 405 mm = 27.41 ≒ 28 units/string U300B: 11,100 mm ÷ 505 mm = 21.98 ≒ 22 units/string Lightning Impulse Withstand Voltage Taking highest voltage, Um = 550 kV Horn gab distance is 4,200 mm as specified by DPTSC in MYP8 project. However, referring to IEC60071-1-2006, standard rated lightning impulse withstand voltage at 550 kV is 1,550 kV and minimum horn gap distance is 3,100 mm. The ratio of horn gap distance to length of insulator string length (Z/Zo) is decided as 85% from standard practices across the world. Number of insulator units: U210B: 4,200 mm ÷ 0.85 ÷ 170 mm = 29.06 ≒ 30 units/string U300B: 4,200 mm ÷ 0.85 ÷ 195 mm = 25.33 ≒ 26 units/string Switching Impulse Withstand Voltage (SIWV) Given, Surge multiplier: 2.0; Insulation deterioration coefficient: 1.1; Withstand voltage coefficient: 1/0.85 50% Switching Surge Flashover Voltage, V50: V50 = Um × √2 ÷√3 × 2.0 × 1.1 × 1/0.85 = 1162.3 kV Horn gap distance without flashover in V50: V50 = k × 1080 × ln(0.46d+1); where k: gap factor = 1.32 d = 2.74 m Number of insulator units: U210B: 2,740mm ÷ 0.85 ÷ 170 mm = 18.96 ≒ 19 units/string U300B: 2,740mm ÷ 0.85 ÷ 195 mm = 16.53 ≒ 17 units/string 6-4 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Table 6.2-5 Determination of Number of Insulators per Strings Type of Insulator Contamination Level U210B U300B Medium Medium Number of Insulators by Lightningt Switching Impulse Impulse Withstand Withstand Voltage Voltage 30 19 26 17 Contamination Design 28 22 Result 30 26 (4) Mechanical Strength of Tension Insulator For the suspension towers, the number of insulator strings per set is either single or double 210kN insulators, which was determined in accordance with the transmission line crossing places. For the tension towers, the number of insulator strings per set is double the 300kN insulator. The tension insulators must satisfy the safety factor at RUS for maximum working tension at the standard span of 450 m, as follows. Table 6.2-6 Tension Insulator Assembly Conductor ACSR 468 mm2 "Drake'' Maximum Tension (Span length: 450m) Insulator Tension Safety Factor 212.8kN (53.2kN × 4) Double strings 600kN (300kN × 2) 2.81 > 2.5 (5) Tension Insulator Assembly Insulator assembly fittings also have to maintain the same strength as the insulators. Table 6.2-7 Tension Insulator Assembly Conductor ACSR 468 mm2 "Drake'' Maximum Tension (Span length: 450m) Insulator Tension Safety Factor 212.8kN (53.2kN × 4) Double strings 600kN (300kN × 2) 2.81 > 2.5 (6) Ground Clearance The most severe state for the ground clearance of the conductors will occur when the conductor’s temperature rises to 75 ºC under still air conditions. The minimum height of the conductor above ground at the 500 kV level is determined as per the below. Table 6.2-8 Minimum Height of the Conductor above Ground Classification Areas where people rarely enter, such as mountains, forests, waste fields, etc. Area where people enter or will enter frequently Applied areas for the project Bush lands, forests, grass land and narrow rivers Paddy fields with mosaic of croplands, general roads and wide rivers River crossing Clearance 11.0 m 14.0 m 20.0 m Determination of Tower Configuration (1) Electrical Clearance Table 6.2-9 Swing Angle and Insulation Clearance Wind velocity Swing angle of suspension strings (Type DA) Swing angle of tension strings without jumper loop (Type DB) Swing angle of tension strings with jumper loop (Type DC, DD, DE) Clearance Normal Middle Abnormal 0 to 10 m/s 0 to 15 deg 10 to 20 m/s 15 to 20 deg 20 to 35 m/s 20 to 60 deg 0 to 15 deg 15 to 20 deg 20 to 60 deg 0 to 15 deg N/A N/A 4,700 mm 4,200 mm 1,900 mm (2) Length of String Set and Drop of Jumper Loop Length of the suspension string set and drop of jumper loop are estimated as follows. 6-5 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Table 6.2-10 Length of Suspension String Set and Drop of Jumper Loop Type Length of suspension string set for U210B Length of tension string set for U300B Drop of jumper loop for tension string set Length of support insulator string set for DC, DD Determination 170 mm × 30 units+1,535 mm (fitting length) + 65 mm (margin) 195 mm × 26 units+2,050 mm (fitting length) + 80 mm (margin) 4,700 mm (normal insulation distance) × 1.2+200 mm (half of length between conductors) + 60 mm (margin) 170 mm × 30 units + 1,250 mm (fitting length) + 50 mm (margin) Length 6,700 mm 7,200 mm 5,900 mm 6,400 mm (3) Clearance Diagram Clearance diagrams of suspension insulator string and drop of jumper loop are shown as follows. Suspension Type DA Tension Type DB Figure 6.2-2 Clearance Diagram Type DC, DD, DE (4) Clearance to Ground and Obstacles Clearances above ground and to each obstacle are determined as follows, including some errors which might happen in drawings, survey, and construction. Table 6.2-11 Clearances to Ground and Obstacles Object Ground (Mountains or forest area) Ground (Paddy field) River crossing (Above highest water level) Road Railway Trees (Rubber plants, etc.) Distribution line (including pole) Transmission line (including tower) 66 kV transmission line 132 kV transmission line 230 kV transmission line Other Conditions At maximum conductor temperature of 75 ºC Clearance 11.0 m 14.0 m 20.0 m 15.0 m 16.0 m 7.0 m 8.0 m – 9.0 m 9.0 m 9.0 m 7.0 m Towers (1) Type of Towers (a) Type DA Suspension type tower on a straight section of the line or on a section of the line with a horizontal deviation angle up to 3 degrees with suspension insulator sets. (b) Type DB Tension type tower on a section of the line with a horizontal deviation angle up to 20 degrees with tension insulator sets. (c) Type DC Tension type tower on a section of the line with a horizontal deviation angle from 20 degrees to 40 degrees with tension and jumper suspension insulator sets. 6-6 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (d) Type DD Tension type tower on a section of the line with a horizontal deviation angle from 40 degrees up to 60 degrees with tension and jumper suspension insulator sets. (e) Type DE Tension type tower used at the terminal of the line with tension insulator sets having jumper insulator sets where required with a horizontal angle up to 40 degrees. Table 6.2-12 Tower Types and the Applied Conditions Type DA DB DC DD DE Position of Use Straight line Angle Angle Angle Terminal Angle of Deviation [deg.] 0–3 4 – 20 21 – 40 41 – 60 0 – 40 String Type Suspension Tension Tension Tension Tension (2) Design Span The design of all towers will provide for the following wind spans and weight spans. Table 6.2-13 Tower Type DA DB DC DD DE Design Span Wind Span [m] 450 450 450 450 450 Weight Span [m] 700 700 700 700 350 (3) Maximum Sag Calculation and Standard Height of Towers Conductor temperature: 75 deg. Wind pressure: still air Table 6.2-14 Maximum Sag and Standard Height of Towers Maximum conductor sag Insulator length Ground Clearance Standard height of tower above ground (below bottom cross arm) Suspension type 15.3 m 6.7 m 14.0 m Tension type 15.3 m 14.0 m 36.0 m 29.5 m 6-7 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (4) Shape of Tower Figure 6.2-3 Type DA Tower Figure 6.2-4 Type DB Tower Figure 6.2-5 Type DC Tower Figure 6.2-6 Type DD Tower 6-8 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Figure 6.2-7 Type DE Tower (5) Unit Weight of Towers The unit weights of types of towers for different extension lengths are shown below. Table 6.2-15 Tower extension [m] 0 +3 Unit Weight of the Towers (Estimated) DA 42.9 46.7 Unit weight of towers [ton] DB DC DD 48.3 60.0 64.1 50.9 65.7 67.1 DE 70.0 – Tower Foundations (1) Tower load condition The foundation loads that are transmitted from each tower at ±0.0 m extension Table 6.2-16 Tower Load Conditions ( 2 cct 500 kV) Tower type DA DB DC DD DE Compressive load [kN] 1393.6 1909.5 2671.2 3228.4 2554.0 Tensile load [kN] 1090.2 1573.7 2266.6 2803.6 2031.4 Quantities of the Transmission Line Materials (1) Number of Towers and Total Weight of Towers The assumed tower types, number of towers and the tower weight for the transmission lines are summarized in the following table. Table 6.2-17 Tower type Numbers of Towers and Tower Weight Extension [m] Unit weight [ton] 6-9 No. of towers [unit] Total weight [ton] Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) DA: Suspension (Horizontal angle: 0 – 3 deg.) Subtotal DB: Tension (Horizontal angle: 3 – 20 deg.) Subtotal DC: Tension (Horizontal angle: 20 – 40 deg.) Subtotal DD: Tension (Horizontal angle: 40 – 60 deg.) Subtotal DE: Dead-end (Horizontal angle: 0 – 40 deg.) Subtotal Total 0.0 +3.0 42.9 46.7 0.0 +3.0 48.3 50.9 0.0 +3.0 60.0 65.7 0.0 +3.0 64.1 67.1 0.0 70.0 117 5 122 4 2 6 9 4 13 6 3 9 5019.3 233.5 5252.8 193.2 101.8 295.0 540.0 262.8 802.8 384.6 201.3 585.9 2 140.0 2 152 140.0 7076.5 (2) Quantities of Conductors and Ground Wire The quantities of conductors and ground wires for the transmission line are computed by multiplying the numbers of conductors or ground wires by the route length, and multiplying that number by 1.05 for the sag allowance and margin for stringing work. Table 6.2-18 Conductor/Ground wire type LL-ACSR 728 mm2 OPGW115 mm2 AC110 mm2 Quantities of Conductors and Ground Wire No. of bundles 4 1 1 No. of phases 3 – – No. of circuits 2 1 1 Route length [km] 70.0 70.0 70.0 Line length [km] 1764.0 73.5 73.5 (3) Quantities of Insulators and Insulator Assemblies The quantities of insulators and insulator assemblies for the transmission line are computed from the number of suspension and tension towers, considering the number of strings. Table 6.2-19 Insulator type Quantities of Insulators and Insulator Assemblies Tower type Jumper support Double Single Single Tension Dead-end Double Double Suspension U210B U300B Assembly type No. of No. of No. of insulators strings per towers per set [pcs] tower [set] [unit] 54 6 5 26 6 117 26 6 22 Total number for U210B 60 12 28 60 12 2 Total number for U300B Subtotal of strings [set] 30 702 132 864 336 24 360 Subtotal of insulators [pcs] 1620 18252 3432 23304 20160 1440 21600 (4) Quantities of Foundation Concretes Quantities of reinforced concrete of the foundations for 5 types of 500kV towers based on dfferent geological type are summarized in the following table. Table 6.2-20 Type of foundation Tower type DA Pile DB DC DD Quantities of Foundation Concretes Geological type Standard Flood area Standard Flood area Standard Flood area Standard Unit concrete [m3] 44.0 42.8 45.6 43.6 59.2 63.6 96.8 6-10 No. of tower [unit] 73 31 2 1 7 4 4 Total concrete [m3] 3212.0 1326.8 91.2 43.6 414.4 254.4 387.2 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Pad 6.3. DE Flood area Standard DA DB DC DD DE – – – – – 108.4 53.6 Subtotal 86.6 131.1 179.0 219.1 163.8 Subtotal TOTAL 2 1 125 18 3 2 3 1 27 152 216.8 53.6 6000.0 1558.8 393.3 358.0 657.3 163.8 3131.2 9131.2 230kV Transmission Line Design Overview of Transmission Line Route The 230kV transmission line routes are described below and shown in Figure 6.3-1 and Figure 6.3-2. The route connecting Sar Ta Lin Substation to Hlawga Substation has an approximate route length of 17km. The overhead transmission line branches into underground line 5km before Hlawga Substation due to there being a populated residential area around Hlawga Substation. The towers used in this route are 4 circuit transmission towers. The route connecting Sar Ta Lin Substation to East Dagon Substation has an approximate route length of 19km. The towers used in this route are 2 circuit transmission towers. Sar Ta Lin-Hlawga 230kV T/L Route Sar Ta Lin-East Dagon 230kV T/L Route Sar Ta Lin S/S Hlawga S/S East Dagon S/S Figure 6.3-1 230kV Sar Ta Lin S/S – Hlawga S/S and Sar Ta Lin S/S – East Dagon Transmission Line Route Map The route connecting Hlawga Substation to East Dagon Substation has an approximate route length of 22km. The overhead transmission line branches into underground line 5km before Hlawga Substation due to there being a populated residential area around Hlawga Substation. The new 2 circuit transmission towers will be constructed in the same position as the existing one circuit transmission towers. 6-11 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Hlawga S/S Hlawga-Thaketa 230kV T/L Route Thaketa S/S Figure 6.3-2 230kV Hlawga S/S – East Dagon S/S Transmission Line Route Map Design Conditions The basic design conditions are as mentioned below. (1) Ambient Temperature Maximum air temperature Minimum air temperature Annual average temperature 46 ºC 10 ºC 27 ºC (2) Conductor Temperature Maximum temperature Minimum temperature 75 ºC 10 ºC (3) Wind Velocity Maximum wind velocity 35 m/s (4) Wind Pressure Tower Conductor Ground wire Insulator 2,150 Pa 900 Pa 970 Pa 900 Pa (5) Stringent (the most severe design) Conditions and EDS (Every Day Stress) Conditions Conductors: Condition Stringent EDS Temperature 15 ºC 27 ºC Wind 900 Pa Still air Tension 40.0% UTS 22.2% UTS Temperature 15 ºC 27 ºC Wind 970 Pa Still air Tension 40.0% UTS 22.2% UTS Ground Wires: Condition Stringent EDS *UTS: Ultimate Tension Strength (6) Pollution Level Heavy (IEC standard); 43.3 mm/kV (7) Other Conditions Assumed Maximum humidity 100% 6-12 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (8) Voltage Level for Insulation Design Lightning Impulse Withstand Voltage 1, 050 kV Switching Impulse Withstand Voltage 460 kV Maximum System Voltage 245 kV (9) Air Clearance Normal condition (D1) Normal wind condition (D2) Maximum wind condition (D3) 2,480 mm 1,760 mm (swing angle: 10º - 30º) 550 mm (max. swing angle: 60º) (10) Safety Factors Required minimum safety factors for the facilities of the transmission line were determined as follows. (a) Tower 1.6 to yield strength of the material under normal conditions (= stringent conditions) 1.3 to yield strength of the material under broken-wire conditions (= normal conditions + one ground wire or one phase conductor breakage) (b) Conductor/Ground wire 2.5 to UTS (Ultimate Tensile Strength) for stringent conditions 4.5 to UTS for Everyday Stress (EDS) conditions at average temperature in still air at supporting point (c) Insulator string 2.5 to RUS (Rated Ultimate Strength) for maximum working tension at supporting point (d) Foundation 2.0 under normal conditions 1.5 under broken wire conditions Conductor and Ground Wire Design (1) Conductor and ground wire The results of the power flow system analysis showed that 2 bundles of ACSR 1272MCM 644 mm2 (Pheasant) conductor are appropriate for the project. However, since a large amount of current is expected to flow in the three 230kV T/L in the future, the LL-ACSR 782mm2 conductors, which have 13% lower loss in conductivity and the same weight and outer shape as Pheasant, is applied. Therefore, LL-ACSR 782mm2 for conductors, and OPGW 115 mm2 and AS 110 mm2 for ground wire, are applied. The technical characteristics of the conductors and ground wires are shown in the following tables. 6-13 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Table 6.3-1 Technical Characteristics of Conductors ACSR 1272 LL-ACSR/AS Type MCM 728 mm2 (Pheasant) 16/TW*1 – AL 12/TW – AL Al: 54/3.899 mm 8/TW – AL Component of stranded wire (Nos./Dia.) St: 19/2.339 mm 7/3.25 – 14EAS*2 35.09 mm 33.05 mm Overall Diameter 2 644.5 mm 727.5mm2 Cross Sectional Area of Aluminum wires 2 726.4 mm 785.6 mm Cross Sectional Area (Total) 2,434 kg/km 2,434 kg/km Nominal Weight 194.1 kN 194.1 kN Ultimate Tensile Strength 77.9 GPa 69.8 GPa Modulus of Elasticity Co-efficient of linear expansion 19.6 x 10-6/℃ 21.0 x 10-6/℃ 0.04501 Ω/km 0.0392 Ω/km DC Resistance at 20℃ Cross Sectional View *1 TW: Trapezoid shaped wire *2 14EAS: Extra high strength aluminum clad steel with 14% IACS conductivity Table 6.3-2 Technical Characteristics of Ground Wires OPGW115 mm2 AA: 12/2.85mm AS: 19/2.85 mm SUS: 1/2.80 mm 14.25 mm 114.83 mm2 483 kg/km 72.4 kN 97.7 GPa 17.5 x 10-6/℃ 0.366 Ω/km (including OP unit) 24 Type Component of stranded wire (Nos./Dia.) Overall Diameter Cross Sectional Area (Total) Nominal Weight Ultimate Tensile Strength Modulus of Elasticity Co-efficient of linear expansion DC Resistance at 20℃ Number of Optical Fibers AC110 mm2 20SA: 19/2.7 mm 13.5 mm 108.8 mm2 722.5 kg/km 145.8 kN 155.2 GPa 12.6 x 10-6/℃ 0.787 Ω/km – (2) Maximum Tension and Every Day Stress (EDS) The standard span length was assumed as 400 m. The values of the maximum working tension and the EDS of both the conductors and the ground wires satisfy the determined safety factors shown in the following table. Table 6.3-3 Maximum Working Tension and Every Day Stress Type LL-ACSR 728 UTS mm2 194.1 kN OPGW115 mm2 72.4 kN AC110 mm2 145.8 kN Tension Maximum Tension Every Day Stress Maximum Tension Every Day Stress Maximum Tension Every Day Stress 66.0 kN 43.0 kN 24.5 kN 10.7 kN 30.0 kN 17.7 kN Safety Factors 2.94 > 2.5 4.51 > 4.5 2.95 > 2.5 6.76 > 4.5 4.86 > 2.5 8.23 > 4.5 (3) Sag and tensions of the Ground Wires The sags of the ground wires under EDS conditions must be below 80% of the conductors’ sag at the standard span length to avoid a reverse flashover from the ground wires to the conductors and direct lightning stroke to the conductors. The tensions of the ground wires are determined to satisfy 6-14 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) the safe separation of conductors and ground wires in the mid-span. (4) Standard Span Length The standard span length between towers is 400 m. (5) Right of Way (ROW) The right of way for the 230kV transmission line is assumed to be 45.72m. Insulator Design (1) Insulator type and Size The insulator unit applied to the transmission line is a standard disc type porcelain insulator with ball and socket, complying with IEC 60305. 210kN type insulators are applied for the suspension towers and the tension towers. The technical characteristics of the insulators are shown in the following table. Table 6.3-4 Technical Characteristics of the Insulators Rated Ultimate Strength IEC Designation Shell Diameter Unit Spacing Nominal Creepage Distance Ball & Socket Coupling 210kN U210B 280 mm 170 mm 405 mm 20 mm (2) Number of insulator Units per String The number of insulator units per string is 17 units for the suspension towers and 15 units for the tension towers. (3) Determination of number of Insulator Strings per Set The determinations of the number of insulators per string are as shown below. Contamination design Contamination level: Heavy Creepage distance per voltage: 43.3 mm/kV Highest Voltage, Um: 230 kV × 1.15/1.1 ≒ 241 kV Total Insulator Creepage Distance: 241 kV ÷ √3 × 43.3 mm/kV ≒ 6,025 mm Number of insulator units: U210B: 6,025 mm ÷ 405 mm = 14.88 ≒ 15 units/string Light Impulse Withstand Voltage Taking highest voltage, Um = 241 kV ≒ 245 kV Referring to IEC60071-1-2006, standard rated lightning impulse withstand voltage at 245 kV is 1,050 kV and minimum horn gap distance is 2,100 mm. The ratio of horn gap distance to length of insulator string length (Z/Zo) is decided as 75% from normal practice in the world. Number of insulator units: U210B: 2,100 mm ÷ 0.75 ÷ 170 mm = 16.47 ≒ 17 units/string Switching Impulse Withstand Voltage (SIWV) Given, Surge multiplier: 3.3; Insulation deterioration coefficient: 1.1; Withstand voltage coefficient: 1/0.9 50% Switching Surge Flashover Voltage, V50: V50 = Um × √2 ÷√3 × 3.3 × 1.1 × 1/0.9 = 793.6 kV Horn gap distance without flashover in V50: V50 = k × 1080 × ln(0.46d+1); where k: gap factor = 1.24 d = 1.76 m Number of insulator units: 6-15 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) U210B: 1,760 mm ÷ 0.75 ÷ 170 mm = 13.81 ≒ 14 units/string Table 6.3-5 Determination of Number of Insulators per Strings Number of Insulator by Light Switching Type of Contamination Contamination Impulse Impulse Insulator Level Result Design Withstand Withstand Voltage Voltage Heavy 15 17 14 U210B 17 (4) Mechanical Strength of Tension Insulators For the suspension towers, the number of insulator strings per set is either the same as, or double the amount of, the 210kN insulators, which was determined in accordance with the transmission line crossing places. As for the tension towers, the number of insulator strings per set is double the number of 300kN insulators. The tension insulators must satisfy the safety factor at RUS for maximum working tension at the standard span of 400 m, as follows. Table 6.3-6 Tension Insulator Assembly Conductor Maximum Tension (Span length: 400m) Insulator Tension Safety Factor LL-ACSR 728 mm2 132.0kN (66.0kN × 2) Double strings 600kN (300kN × 2) 4.54 > 2.5 (5) Tension Insulator Assembly Insulator assembly fittings also have to maintain the same strength as the insulators. Table 6.3-7 Tension Insulator Assembly Conductor Maximum Tension (Span length: 450m) Insulator Tension Safety Factor LL-ACSR 728 mm2 133.0kN (66.0kN × 2) Double strings 600kN (300kN × 2) 4.54 > 2.5 Ground Clearance The most severe state for the ground clearance of the conductors will occur when the conductor’s temperature rises to 75 ºC under still air conditions. The minimum height of the conductor above ground at 230 kV level is determined as below. Table 6.3-8 Minimum Height of the Conductor above Ground Object Ground (Paddy field) Road Railway Clearance 8.0 m 10.0 m 20.0 m Determination of Tower Configuration (1) Electrical Clearance Table 6.3-9 Swing Angle and Insulation Clearance Wind velocity Swing angle of suspension strings (A) Swing angle of tension strings without jumper loop (B) Swing angle of tension strings with jumper loop (C, D, E) Clearance (suspension strings) Clearance (tension strings) Normal 0 to 10 m/s 0 to 10 deg Middle 10 to 20 m/s 10 to 30 deg Abnormal 20 to 35 m/s 30 to 60 deg 0 to 5 deg 5 to 15 deg 15 to 40 deg 0 to 15 deg N/A N/A 2,760 mm 2,530 mm 1,910 mm 1,910 mm 700 mm 700 mm *The above figures considered the length of the step bolts and thickness of materials. 6-16 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (2) Length of String Set and Drop of Jumper Loop The length of the suspension string set and drop of jumper loop are estimated as follows. Table 6.3-10 Length of Suspension String Set and Drop of Jumper Loop Type Length of suspension string set for U210B Length of tension string set for U210B Drop of jumper loop for tension string set Length of support insulator string set for C, D, 4C, E Determination Length 170mm × 17units+1,080mm (fitting length) 3,970mm 170mm × 17units+1,035mm (fitting length) 3,925mm 2,480mm* × 1.2+100mm (influence of slope) 3,080mm 170mm × 17units+785mm (fitting length) 3,675mm *Air clearance (Normal conditions): 2,480mm (3) Clearance Diagram Clearance diagrams of suspension insulator strings and drop of jumper loop are shown below. Suspension A Tension B, 4B C, D, E, 4C Figure 6.3-3 Clearance Diagram Towers (1) Types of Towers (a) Type A Suspension type towers on straight sections of the line or on sections of the line with a horizontal deviation angle up to 3 degrees with suspension insulator sets. (b) Type 4A 4 circuits Suspension type tower on straight sections of the line or on sections of the line with a horizontal deviation angle up to 3 degrees with suspension insulator sets. (c) Type B Tension type tower on sections of the line with a horizontal deviation angle up to 20 degrees with tension insulator sets. (d) Type 4B 4 circuits tension type tower on sections of the line with a horizontal deviation angle up to 20 degrees with tension insulator sets. (e) Type C Tension type tower on sections of the line with a horizontal deviation angle from 20 degrees to 40 degrees with tension and jumper suspension insulator sets. (f) Type 4C 4 circuits tension type tower on sections of the line with a horizontal deviation angle from 20 degrees to 40 degrees with tension and jumper suspension insulator sets. (g) Type D Tension type tower on sections of the line with a horizontal deviation angle from 40 degrees up to 60 degrees with tension and jumper suspension insulator sets. 6-17 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (h) Type E Tension type tower used at the terminal of the line with tension insulator sets having jumper insulator sets where required, with a horizontal angle up to 40 degrees. Table 6.3-11 Tower Types and the Applied Conditions Type A, 4A B, 4B C, 4C D E Position of Use Straight line Angle Angle Angle Terminal Angle of Deviation [deg.] 0–3 4 – 20 21 – 40 41 – 60 0 – 40 String Type Suspension Tension Tension Tension Tension (2) Design Span The design of all towers will provide for the following wind spans and weight spans. Table 6.3-12 Tower Type A, 4A B, 4B C, 4C D E Design Span Wind Span [m] 400 400 400 400 400 Weight Span [m] 600 600 600 600 300 (3) Maximum Sag Calculation and Standard Heights of Towers Conductor temperature: 75 deg. Wind pressure: still air Table 6.3-13 Maximum Sag and Standard Heights of Towers (Proposal) Maximum conductor sag Insulator length Ground Clearance Standard height of tower above ground (below bottom cross arm) Suspension type 13.3 m 4.0 m 10.0 m Tension type 13.3 m -m 10.0 m 27.3 m 23.3 m 6-18 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (4) Shape of Tower Figure 6.3-4 Figure 6.3-5 Type A Tower Figure 6.3-6 Type E Tower 6-19 Type B, C, D Tower Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Figure 6.3-7 Figure 6.3-8 Type 4A Tower Type 4B, 4C Tower (5) Unit Weight of Towers The unit weights of towers for different extension lengths are shown below. Table 6.3-14 Unit Weight of the 2 Circuit Towers Unit weight of towers [ton] Tower extension [m] A B C D 23.8 32.0 38.3 42.2 0 28.3 38.7 45.9 51.8 +3 Table 6.3-15 Tower extension [m] 0 E 48.4 – Unit Weight of the 4 Circuit Towers Unit weight of towers [ton] 4A 4B 4C 58.4 87.3 116.3 6-20 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Tower Foundations (1) Tower load conditions The foundation loads that are transmitted from each tower at ±0.0 m extension Table 6.3-16 Tower Load Conditions (2 cct 230 kV) Tower type A B C D E Compressive load [kN] 642.5 996.2 1438.0 1855.1 2122.3 Tensile load [kN] 494.4 771.0 1131.7 1524.8 1668.4 Table 6.3-17 Tower Load Conditions (4 cct 230 kV) Tower type 4A 4B 4C Compressive load [kN] 1619.9 2686.2 3960.1 Tensile load [kN] 1135.3 2016.8 3148.5 Quantities of the Transmission Line Materials (1) Number of Towers and Total Weight of Towers The assumed tower types, number of towers and the tower weight for the transmission line are summarized in the following table. Table 6.3-18 Numbers of Towers and Tower Weight (Sar Ta Lin S/S to East Dagon S/S) Tower type A: Suspension (Horizontal angle: 0 – 3 deg.) Subtotal B: Tension (Horizontal angle: 3 – 20 deg.) Subtotal C: Tension (Horizontal angle: 20 – 40 deg.) Subtotal D: Tension (Horizontal angle: 40 – 60 deg.) Subtotal E: Dead-end (Horizontal angle: 0 – 40 deg.) Subtotal Total Table 6.3-19 Extension [m] 0.0 +3.0 Unit weight [ton] 23.8 28.3 0.0 +3.0 32.0 38.7 0.0 +3.0 38.3 45.9 0.0 +3.0 42.2 51.8 0.0 48.4 No. of towers [unit] 33 1 34 2 – 2 2 1 3 4 – 4 Total weight [ton] 785.4 28.3 813.7 64.0 – 64.0 76.6 45.9 122.5 168.8 – 168.8 2 96.8 2 45 96.8 1265.8 Numbers of Towers and Tower Weight (Sar Ta Lin S/S to Hlawga S/S) Tower type 4A: Suspension (Horizontal angle: 0 – 3 deg.) Subtotal 4B: Tension (Horizontal angle: 3 – 20 deg.) Subtotal 4C: Tension (Horizontal angle: 20 – 40 deg.) Subtotal Extension [m] Unit weight [ton] 0.0 0.0 0.0 6-21 58.4 87.3 116.3 No. of towers [unit] Total weight [ton] 33 1927.2 33 1927.2 3 261.9 3 261.9 5 581.5 5 581.5 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) E: Dead-end (Horizontal angle: 0 – 40 deg.) Subtotal Total 0.0 48.4 4 193.6 4 45 193.6 2964.2 Table 6.3-20 Numbers of Towers and Tower Weight (Hlawga S/S to Thaketa S/S) Extension Unit weight No. of towers Total weight Tower type [m] [ton] [unit] [ton] 0.0 23.8 38 904.4 A: Suspension +3.0 28.3 4 113.2 (Horizontal angle: 0 – 3 deg.) Subtotal 42 1017.6 0.0 32.0 4 128.0 B: Tension +3.0 38.7 – – (Horizontal angle: 3 – 20 deg.) Subtotal 4 128.0 0.0 38.3 1 38.3 C: Tension +3.0 45.9 – – (Horizontal angle: 20 – 40 deg.) Subtotal 1 38.3 D: Tension 0.0 42.2 – – (Horizontal angle: 40 – 60 deg.) +3.0 51.8 – – – Subtotal – E: Dead-end 0.0 48.4 4* 193.6 (Horizontal angle: 0 – 40 deg.) Subtotal 4 193.6 Total 51 1377.5 *2 type E towers branch to Kyaikkasan S/S. (2) Quantities of Conductors and Ground Wire The quantities of conductors and ground wires for the transmission line are computed by multiplying the numbers of conductors or ground wires by the route length, and multiplying that number by 1.05 for the sag allowance and margin for stringing work. Table 6.3-21 Conductor/Ground wire type LL-ACSR 728 mm2 Sar Ta Lin – East Dagon T/L Sar Ta Lin – Hlawga T/L Hlawga – Thaketa T/L Total OPGW115 mm2 Sar Ta Lin – East Dagon T/L Sar Ta Lin – Hlawga T/L Hlawga – Thaketa T/L Total AC110 mm2 Sar Ta Lin – East Dagon T/L Sar Ta Lin – Hlawga T/L Hlawga – Thaketa T/L Total Quantities of Conductors and Ground Wire No. of bundles No. of phases No. of circuits Route length [km] Line length [km] 2 3 2 19.0 239.4 2 2 3 3 4 2 17.0 17.0 428.4 214.2 882.0 1 – 1 19.0 19.95 1 1 – – 1 1 17.0 17.0 17.85 17.85 55.65 1 – 1 19.0 19.95 1 1 – – 1 1 17.0 17.0 17.85 17.85 55.65 (3) Quantities of Insulators and Insulator Assemblies The quantities of insulators and insulator assemblies for the three transmission lines are computed from the number of suspension and tension towers considering the number of strings. 6-22 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Insulator type Table 6.3-22 Quantities of Insulators and Insulator Assemblies Tower type Assembly type No. of insulators per set [pcs] No. of strings per tower [set] No. of tower [unit] Subtotal of strings [set] Subtotal of insulators [pcs] Double Single Single Double Double 34 17 17 34 34 6 6 6 12 12 1 33 9 9 2 Subtotal 6 198 54 108 24 390 204 3366 918 3672 816 8976 Double Single Single Double Double 34 17 17 34 34 12 12 12 24 12 1 32 9 8 4 Subtotal 12 384 108 192 48 744 408 6528 1836 6528 1632 16932 Double Single Single Double Double 34 17 17 34 34 6 6 6 12 12 4 38 5 5 4 Subtotal TOTAL 24 228 30 60 48 390 1524 816 3876 510 2040 1632 8874 34782 Sartalin – East Dagon T/L Suspension U210B Jumper support Tension Dead-end Sartalin – Hlawga T/L Suspension U210B Jumper support Tension Dead-end Hlawga – Thaketa T/L Suspension U210B Jumper support Tension Dead-end (4) Quantities of Foundation Concretes Quantities of reinforced concrete of the foundations for different types of 230kV towers based on dfferent transmission lines are summarized in the following table. Table 6.3-23 Quantities of Foundation Concretes Type of Tower type foundation Sartalin – East Dagon T/L A B C Pile D E Unit concrete [m3] No. of tower [unit] Total concrete [m3] 43.6 44.0 45.6 45.6 45.6 Subtotal 34 2 3 4 2 45 1482.4 88.0 136.8 182.4 91.2 1980.8 4A 4B 4C E 45.6 45.6 150.0 45.6 Subtotal 33 3 5 4 45 1504.8 136.8 750.0 182.4 2574.0 A B C D E 43.6 44.0 45.6 45.6 45.6 Subtotal TOTAL 42 4 1 0 4 51 141 1831.2 176.0 45.6 0.0 182.4 2235.2 6790.0 Sartalin – Hlawga T/L Pile Hlawga – Thaketa T/L Pile Table 6.3-24 Total Quantities of Insulators Insulator type U210B U300B Total No. of insulators [pcs] 18462 9600 6-23 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Obstacle Limitation Surface The height of the towers within the obstacle limitation surface of Yangon International Airport are shown in Figure 6.3-9 and the height limitation of obstacles is illustrated in Figure 6.3-10. The height of the towers (Hlawga – Thaketa T/L) within the 2.0% slope area must be within 60m and the height of the towers (Sar Ta Lin – Hlawga T/L) within the horizontal area must be within 150m. Figure 6.3-9 Obstacle Limitation Surface of Yangon International Airport Figure 6.3-10 6.4. Illustration of the Limitation Surface Design of Foundations Soil Conditions Most of the 500 kV and 230 kV TL routes are Alluvium, which is new and relatively soft. Therefore, pile foundations will be applied for most of the towers. In addition, we judged that pile foundations were appropriate based on the results of boring logs shown in Figure 3.3-6 to Figure 3.3-11. It is necessary to conduct a detailed soil investigation at each TL tower position before implementing the detailed design to determine the type of each tower foundation and the depth of the support layer. (1) Soil Conditions for Pile Foundations The concept for the supporting layer of pile foundations is in accordance with the Basic Design in "500kV TRANSMISSION LINE BETWEEN PHARYARGYII AND HLAING THARYAR FOR NATIONAL POWER TRANSMISSION NETWORK DEVELOPMENT PROJECT PHASE I". A 6-24 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) supporting layer should be a clay layer for which the N-value is 20 or more, or a sand layer, gravel or rock for which the N-value is 30 or more. The depth of supporting layer is BH1 (21.0m), BH2 (30.0m), BH3 (40.5m*), BH4 (28.5m), BH5 (40.5m*) and BH6 (40.5m*) based on boring logs shown in Figure 3.3-6 to Figure 3.3-11, and the average depth is 33.5m. Here, the depths of 40.5 m in three logs - BH3, BH5 and BH6 - are considered to be almost enough to satisfy the supporting conditions. In addition, the following boring logs from near East Dagon SS, published on the website, were referenced. The data source is "The Project for the Improvement of Water Supply, Sewerage and Drainage System in Yangon City Vol IV Water Supply System Feasibility Study, Appendix". The depth of the supporting layer is 33.0 m. From the above results, the supporting layer depth of pile foundations in the Alluvium was estimated to be about 33.0 m. East Dagon S/S Figure 6.4-1 Location of Boring Logs near East Dagon SS 6-25 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Figure 6.4-2 Soil Conditions of Pile Foundation (1/5) 6-26 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Figure 6.4-3 Soil Conditions of Pile Foundation (2/5) 6-27 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Figure 6.4-4 Soil Conditions of Pile Foundation (3/5) 6-28 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Figure 6.4-5 Soil Conditions of Pile Foundation (4/5) 6-29 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Figure 6.4-6 Soil Conditions of Pile Foundation (5/5) 6-30 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (2) Soil Conditions for Pad and Chimney Foundations Near Phayargi S/S, near the middle of the TL route between Pharyargyii S/S and Sar Ta Lin S/S is the Irrawaddy Formation, which is relatively solid from Miocene to Pliocene. The TL route near Phayargi S/S is shown in Figure 6.4-7. The TL route between Phayargi S/S and Sar Ta Lin S/S is shown in Figure 6.4-8. According to basic design in “500kV TRANSMISSION LINE BETWEEN PHARYARGYII AND HLAING THARYAR FOR NATIONAL POWER TRANSMISSION NETWORK DEVELOPMENT PROJECT PHASE I”, most of the tower foundations on Irrawaddy were Pad and Chimney, and the soil conditions of this Irrawaddy were applied for Type II in Table 6.4-1. Table 6.4-1 Classification of Foundations Selective number for calculation 1 2 3 Foundation type I II III few few Underground water level low subsoil water subsoil water Hilly area, Land use Soft farm Paddy field Solid farm Unit weight of concrete Wc (kN/m3) 24 24 24 3 Unit weight of soil We (kN/m ) 18 16 14 Angle of repose θ (゜) 30 20 0 2 Yielding bearing capacity w (kN/m ) 600 300 200 2 Yielding bearing capacity for lateral force wf (kN/m ) 750 400 250 Irrawaddy Alluvium Figure 6.4-7 Geology Near Phayargi S/S 6-31 4 IV high Paddy field 15 10 0 100 130 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Irrawaddy Alluvium Figure 6.4-8 Geology between Phayargi S/S and Sar Ta Lin S/S Loads Conditions for Pile Foundations The tower load conditions for 230kV TL are shown in Table 6.4-2 and those for 500kV TL are shown in Table 6.4-3. Legends by tower angle are shown below. A: B: C: D: E: 0°~3° (Suspension) 3°~20° (Tension) 21°~40° (Tension) 41°~60° (Tension) 0°~40° (Terminal) Table 6.4-2 Tower load conditions for 230kV TL 6-32 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Table 6.4-3 Tower load conditions for 500kV TL Results of Foundation Design The specifications and shape of the foundations need to be determined through a detailed design based on the soil investigation results at each tower before construction. The basic design for the foundations was conducted based on the current geological and loading conditions. In addition, the depth of the support layer for the pile foundations was assumed to be 33m, where the N value becomes 24 or more in cohesive soil based on “Soil Conditions of Pile Foundation (4/5) in Table 6.4-4. (1) Pile Foundations for 500kV (2 circuits) The dimensions of the pile foundations for 500kV (2 circuits) are shown in Table 6.4-4. 6-33 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Table 6.4-4 Dimensions of the pile foundations for 500 kV (2 circuits) Tower Type DA DB DC DD DE (a) m 0.60 0.75 0.75 0.75 0.75 (b) m 0.85 1.00 1.00 1.00 1.00 (f') m 0.50 0.50 0.50 0.50 0.50 (h1) m 1.50 1.50 1.50 1.50 1.50 (B) m 3.20 3.20 3.70 4.80 3.50 (t) m 1.00 1.00 1.00 1.00 1.00 Depth of Pad Bottom (H) m 2.00 2.00 2.00 2.00 2.00 Length (L) GL-m 34.00 34.00 34.00 34.00 34.00 Diameter (D) mm 800 800 800 800 800 No. of Piles (n) - 4 4 4 4 4 Chimney Pad Pile (2) Pile Foundations for 230kV (2 circuits) The dimensions of the pile foundations for 230kV (2 circuits) are shown in Table 6.4-5. 6-34 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Table 6.4-5 Dimensions of the pile foundations for 230kV (2 circuits) Tower Type A B C D E (a) m 0.55 0.60 0.75 0.75 0.75 (b) m 0.80 0.85 1.00 1.00 1.00 (f') m 0.50 0.50 0.50 0.50 0.50 (h1) m 1.50 1.50 1.50 1.50 1.50 (B) m 3.20 3.20 3.20 3.20 3.20 (t) m 1.00 1.00 1.00 1.00 1.00 Depth of Pad Bottom (H) m 2.00 2.00 2.00 2.00 2.00 Length (L) GL-m 34.00 34.00 34.00 34.00 34.00 Diameter (D) mm 800 800 800 800 800 No. of Piles (n) - 4 4 4 4 4 Chimney Pad Pile 6-35 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (3) Pile Foundations for 230kV (4 circuits) The dimensions of the pile foundations for 230kV (4 circuits) are shown in Figure 6.4-6. Table 6.4-6 Dimensions of the pile foundations for 230kV (4 circuits) Tower Type 4A 4B 4C (a) m 0.75 0.75 0.75 (b) m 1.00 1.00 1.00 (f') m 0.50 0.50 0.50 (h1) m 1.50 1.50 1.50 (B) m 3.20 3.20 5.50 (t) m 1.00 1.00 1.20 Depth of Pad Bottom (H) m 2.00 2.00 2.20 Length (L) GL-m 34.00 34.00 34.00 Diameter (D) mm 800 800 800 No. of Piles (n) - 4 4 4 Chimney Pad Pile 6-36 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (4) Pad and Chimney Foundations for 500kV (2 Circuits) The dimensions of Pad and Chimney foundations for 500kV (2 circuits) are shown in Table 6.4-7. Table 6.4-7 Dimensions of the Pad and Chimney foundations for 230kV (4 circuits) Tower Type DA DB DC DD DE Geological Type II II II II II Chimney Pad Depth of Pad Bottom (a) m 0.60 0.80 0.80 0.80 0.80 (b) m 1.20 1.40 1.40 1.50 1.40 (f') m 0.50 0.50 0.50 0.50 0.50 (h1) m 3.50 3.60 3.90 4.00 3.80 (B) m 4.30 5.30 6.30 7.00 6.00 (t) m 1.00 1.00 1.00 1.00 1.00 (H) m 4.00 4.10 4.40 4.50 4.30 6-37 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 6.5. Preliminary Design for Underground Transmission Lines Design for Burial Method There are, in general, two types of underground transmission line systems: direct burial and duct burial. The optimal construction method will be selected in consideration of economy, construction period, surrounding environment, etc. In particular, the duct burial method is effective for narrow roads in urban areas in order to prevent traffic jams and avoid disturbing daily life, as it does not require a prolonged excavation because it can be backfilled on the same day after excavating and installing duct pipes. The duct burial method is basically examined at the preliminary design stages. Source: JICA survey team Figure 6.5-1 Overview of direct burial method and duct burial method Source: JICA survey team Figure 6.5-2 Overview of duct burial method Source: JICA survey team Figure 6.5-3 Horizontal Directional Drilling Method 6-38 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Table 6.5-1 Evaluation of direct burial and duct burial method Length of one driving Shaft Direct burial ◎ None Not needed Duct ◎ None Not needed ◎ Dairy yard ◎ Dairy yard Temporary Yard HDD △ Less than 1000m Need for connection to next duct △ Wide and Long Period (HDD machine at start and end site) △ ◎ Backfilling can ◎ Backfilling can be done after only be done after No backfill installing duct (the same day) installing the cable ◎ ◎ Cable replacement is possible Cable replacement is possible in ○ in the event of an accident or the event of an accident or expansion expansion Workability Maintenance Cost (at the time of an accident) Overall Evaluation Note: ◎---Very good, △ ◎ ◎ ○ ◎ ○ ○----Good, △----Not suitable Source: JICA survey team Direct burial method and Duct burial method are evaluated via the items of workability, maintenance, and cost (at the time of an accident) etc. The duct burial method does not require a prolonged excavation because it can be backfilled on the same day after excavating and installing duct pipes. After commissioning of the power cable, cable replacement in an accident and replacement of old cables can be performed in the duct without digging the road. The duct burial method is more advantageous than the direct burial method in terms of workability, maintenance and so on. The HDD method is applied for crossing rivers and railways, which present difficulties in digging the road. Design of Ducts The recommended material for duct pipes is Polyester Concrete Fiberglass Reinforced Plastic Pipe (PFP), which is widely used in Japan for multi-pipe conduit. Source: Kurimoto web site and so on Figure 6.5-4 Overview of HDPE duct (right) and PFP duct (left) 6-39 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Source: kurimoto web site Figure 6.5-5 Overview of PFP duct This table shows an evaluation of HDPE duct and PFP duct. Table 6.5-2 Evaluation of HDPE duct and PFP duct HDPE PFP Workability ◎ Workers can carry one. Easy handling by worker Unit of straight length: 10m Easy duct to duct connection Weight: around 17kg/m (nominal diameter: 250mm) 〇 Workers can carry one. Heavier than HDPE Unit of straight length: 2m Weight: around 31kg/m (nominal diameter: 250mm) Maintenance ◎ ◎ Strength △ Weaker than PFP and it has never been used with pipe clieats. ◎ Resilient to outer damage with polycon Fiber Reinforced and widely used with pipe clieats in Japan. Cost ◎ 〇 Overall Evaluation △ ◎ Source: JICA survey team Note: ◎---Very good, ◯----Good, △----Not suitable HDPE ducts are more advantageous in terms of workability and cost. However, in this project nine pipes will be arranged in horizontal 3 rows and vertical 3 rows with pipe clieats, so the recommended material for duct pipes is Polyester Concrete Fiberglass Reinforced Plastic Pipe (PFP). Design of Manholes and Joint Bays There are two types of cable connection construction methods for underground transmission lines: the joint bay method (generally used abroad) and the manhole method (generally used in Japan). The manhole method is expensive in terms of the initial construction costs, but maintenance costs can be reduced by adopting the manhole system integrally with the duct pipe method, because cable replacement in an accident and replacement of old cables can be performed from the manhole neck. The manhole method is also effective for narrow roads in urban areas in terms of preventing traffic jams and avoiding disturbances to daily life, because all maintenance work can be performed from the 6-40 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) manhole neck. This figure shows an overview of the joint bay and manhole. Joint Joint Joint Source: JICA survey team Figure 6.5-6 Overview of Joint Bay Manhole Cable Jointing Source: TEPCO PG leaflet Figure 6.5-7 Overview of Manhole This table shows an evaluation of the Joint Bay and Manhole. Table 6.5-3 Evaluation of Joint Bay and Manhole Joint Bay Manhole ◎ Workability ○ Cable joint work in a manhole is not affected by weather conditions with workers entering from the manhole neck ◎ Maintenance Maintenance of cables in the manhole and replacement of cables in an △ accident with workers entering from the manhole ◎ Expandability △ It is possible to expand the duct and make branch ducts in the future Cost (at the time of an △ ◎ accident) Overall Evaluation Note: ◎---Very good, ○ ○----Good, ◎ △----Not suitable 6-41 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Source: JICA survey team The Manhole method is superior to the Joint Bay method in terms of workability and maintenance, with the maintenance staff entering the manhole through manhole neck. With a manhole, it is possible to expand the duct and make branch ducts in the future, so the Manhole method is superior to the Joint Bay method in terms of expandability. After commissioning of the power cable, cable replacement in an accident and replacement of old cables can be performed in the duct without digging the road. The duct burial method is more advantageous than the direct burial method in terms of workability, maintenance and so on. The manhole method is expensive in terms of the initial construction costs, but maintenance costs can be reduced by adopting the manhole system integrally with the duct pipe method, because cable replacement in an accident and replacement of old cables can be performed from the manhole neck without digging the road. Furthermore, if a manhole is made in a precast system, manufactured at a local plant and installed at the site using a truck crane, the construction period can be significantly shortened, and it is also possible to reduce the impact of construction on the surrounding environment. Figure 6.5-8 Overview of precast manhole The features of precast manholes are as follows. Molding concrete with reinforced rod into precast manhole in factory Each piece of precast manhole is connected with a bolt at the construction site Attach rubber packing along the Jointing Waterproof treatment to the surface of molding concrete Jointing with mortar at the construction site Design of Cable The recommended material for the 230kV Cable is cross-linked polyethylene insulated vinyl sheath cable (XLPE cable), which is the dominant material used abroad. Cable conductor size is calculated via required transmission capacity after confirmation of conditions. The optimal cable specification is selected taking the employer’s needs, site conditions and so on into consideration. This figure shows two types of cable, with aluminum sheath and lead sheath. 6-42 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Source: JICA survey team Figure 6.5-9 Typical cross-section of Extra High Voltage cable with different metallic sheath (left figure: lead sheath, right figure: Aluminum sheath) This table shows an evaluation of cable specifications with different metallic sheaths. Table 6.5-4 Evaluation of cable specifications with different metallic sheaths Type of metallic sheath Extruded corrugated Aluminum Lead alloy Short-current of Xx kA - y second Continuous Current Capacity Water Impermeability Corrosion in Water ○: Additional copper wire layer is required ◎ ◎ ◎: Steady Flexibility ◎ ◎ ◎ ◎ ○:Sensitive Mechanical Protection Cost Environmental Effects ○ ○ (As 100%) △:Toxic ◎:Required annular shaped corrugation ◎: (Approx.60- 70%) [Less Cable pulling tension, compared to lead sheath] ◎ ◎:(Approx.80-90%) ◎ Overall Evaluation ○ ◎ ○: (As 100%) Weight of Cable Note: ◎---Very good, ○----Good, △----Not suitable Source: JICA survey team For the cable, there are concerns about corrosion in terms of sensitivity to water, but the cable can be covered by an outer sheath. In view of the permissible short circuit current, cable with an extruded corrugated aluminum sheath is more advantageous than lead sheath in terms of workability (30% less weight than lead sheath) and cost (approximately 10 – 20 % less than lead sheath). Preliminary Design (1) Basic Conditions for Design Basic Conditions (Common Items) This table shows the basic conditions for the preliminary design. The route for the underground transmission line is shown in Chapter 3. Required transmission capacity is in accordance with Chapter 1. 6-43 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Item Voltage Number of circuits Maximum conductor temperature Maximum ambient temperature in tunnel Wind velocity in tunnel Air temperature at ventilation tower Ambient temperature of soil Thermal resistivity of soil Necessity network fault current and continuous time Table 6.5-5 Basic conditions for design Value Unit Remarks 230 kV 4 Circuit Sar Ta Lin SS – Hlawga SS 2 Circuit Hlawga SS – Thaketa SS 90 Centigrade 40 Centigrade Less than 3 28 m/s Centigrade 30 Centigrade IEC60287-3-1 1.0 40 ☓ 1 40 ☓ 3 K.m/W kA ☓ sec kA ☓ sec IEC60287-3-1 Earth fault Phase fault Maximum wind velocity during work (TEPCO guidelines) Source: JICA survey team The ambient temperature of soil and thermal resistivity of soil is decided in accordance with IEC60287. These tables show the ambient temperature of soil and thermal resistivity of soil in IEC standards. Climate Tropical Subtropical Temperate Table 6.5-6 Ambient temperature of soil Ambient temperature of soil at depth of 1m Unit: ℃(centigrade) Min Max 25 40 15 30 10 20 Source: IEC60287 Table 6.5-7 Thermal resistivity of soil Thermal resistivity of Soil Conditions Weather Conditions soil (K.m/W) 0.7 Very Moist Continuously moist 1.0 Moist Regular rainfall 2.0 Dry Seldom rain 3.0 Very Dry Little or no rain Source: IEC60287 The climate in Myanmar is an almost subtropical climate, and 30° C is selected as the maximum ambient temperature of soil. For thermal resistivity of soil, Myanmar has a rainy season and a dry season, and 0.7 K.m/W is selected when considering only the rainy season. However, there are also dry periods in the year, and 1.0Km/W may be selected considering safety. The cable selected is single core type 2500mm2 with corrugated aluminum sheath. This table shows the technical particulars of the cable. 6-44 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Aluminum sheath Table 6.5-8 Technical Particulars of the selected 230kV 1C Cable Item Unit Particulars 2 Size 2500 mm Material Copper Conductor Shape Segmental Compact round Diameter mm 62.2 Thickness of conductor shielding mm 1.5 Thickness of insulation mm 22 Thickness of semi-conductive layer mm 2 Thickness of swellable layer mm 1.9 Diameter over the cable core mm 117 Thickness of Al-sheath mm 2.5 Average diameter of Al-sheath mm 126.52 External diameter of Al-sheath Thickness of PE jacket layer Outside diameter of cable Estimated unit weight of cable DC conductor resistance at 20℃ mm mm mm Kg/m Ω/km 136.04 5 151 36 0.0072 Electro-static capacitance at 20℃ μF/km 0.25 Source: JICA survey team Calculation of transmission capacity for cable conductor size Calculation in normal operation is carried out in accordance with IEC60287. Calculation of short circuit rating is carried out based on IEC60949. The necessary conditions for the design are as follows: 1) Number of circuits 2) Continuous current rating (MVA/circuit or ampere) 3) Ambient temperature of soil (degrees centigrade) 4) Thermal resistivity of soil 5) Necessity network fault current and continuous time (kA, sec) Design for ducts and tunnels The study team uses the “duct burial system” in sections of 2 circuits between branch towers to the NH3 road, for every underground transmission line, taking the results of the calculation of transmission capacity into consideration. This is identified as an appropriate distance between ducts (cables). The study team uses the “tunnel system” in sections of more than 4 circuits between the MH3 road to Hlawga substation, taking the results of the calculation of transmission capacity into consideration. This is identified as an appropriate distance between cables in a tunnel. A ventilation system is applied for tunnels, with ventilation towers to secure the state temperature in tunnels. The interval between ventilation towers is around 500m. 6-45 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Source: JICA survey team Figure 6.5-10 Conceptual diagram of Underground transmission system Manhole design Manhole design is carried out after the decision on cable conductor size via a calculation of the required transmission capacity. Manhole design is carried out in accordance with the permissible bending radius of cable (15D: D is the overall diameter of the cable). The necessary manhole size is also decided. (2) Results of the Calculation of the Capacities based on the Power Flow in 2027 This sections shows the results of the calculation of the capacities based on the following assumptions of the power flows in 2027 (Figure 1.5-13). Sar Ta Lin SS – Hlawga SS: 770 MVA for 4 circuits Hlawga SS – Thaketa SS: 430 MVA for 2 circuits Results of calculation (Duct burial system) This table shows the results of the calculation in accordance with IEC60287, with a cable conductor size of 2500mm2. Other conditions are as follows: Depth of duct from ground: 1.2m Distance ducts: 345mm (manufacturer’s standard) Table 6.5-9 Result (Duct system: Sar Ta Lin - Hlawaga) Operational conditions Transmission capacity (MVA/circuit) Number of circuits Total (MVA) Conductor temperature (Centigrade) Normal 200 2 400 42 N-1 622 1 622 90 Source: JICA survey team The number of circuits is 4. Conductor temperature is 42 centigrade at normal operation to around 6-46 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 400MVA/2 circuits of each route. This result is good because it is less than 90 centigrade. In the case of N-1 operation, the result of the calculation is 622MVA at 90 centigrade conductor temperature. This result is good as it is more than 400MVA, which is the required transmission capacity. Required transmission capacity from Thaketa to Hlawga is 423MVA per 2 circuits at normal operation. This table shows the results of the calculation for Thaketa to Hlawga in the duct system. Conductor temperature is 44 centigrade at normal operation to around 440MVA/2 circuits. This result is good because it is less than 90 centigrade. In the case of N-1 operation, the result of the calculation is 622MVA at 90 centigrade conductor temperature. This result is good as it is more than 430MVA, which is the required transmission capacity. Table 6.5-10 Results (Duct system: Thaketa - Hlawga) Operational conditions Transmission capacity (MVA/circuit) Number of circuits Total (MVA) Conductor temperature (Centigrade) Normal 220 2 440 44 N-1 622 1 622 90 Source: JICA survey team Results of calculation (Tunnel system) It is necessary to carry out the calculation to maintain the state temperature in the tunnel. It is also necessary to take the inlet temperature from the ventilation tower and the interval of ventilation towers into consideration. Monthly average temperature in Yangon city between Jan. 2013 to Jan. 2020 is as follows: Average temperature: 27.6 degree centigrade Average high temperature: 33.5 degree centigrade Average low temperature: 21.7 degree centigrade This figure shows three average temperatures between Jan. 2013 and Jan. 2020 in Yangon city. Average temperature is less than 30 degree centigrade between the terms. 28 degree centigrade is appropriate for inlet air temperature from ventilation tower to tunnel. Source: JICA survey team arrangement based on the Japan Meteorological Agency website Figure 6.5-11 Monthly average temperature in Yangon city An appropriate state temperature is maintained by this ventilation system, which locates ventilation towers on the tunnel between Hlawga and the NH3 road. The ventilation system is set with a fan in ventilation towers. The interval between ventilation towers is around 500m. The disposition of three Phase cable is trefoil in tunnels. 6-47 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 1) Results for normal operation (Power flow in 2027, Figure 1.5-13) This table shows the results of the calculation for the tunnel system. Table 6.5-11 Results (Tunnel system: Sar Ta Lin - Hlawga) Operational conditions Transmission capacity (MVA/circuit) Number of circuits Total (MVA) Conductor temperature (deg. C) Normal 200 4 800 47 Table 6.5-12 Tunnel (Tunnel system: Hlawga –Thaketa) Operational conditions Transmission capacity (MVA/circuit) Number of circuits Total (MVA) Conductor temperature (Centigrade) Normal 220 2 440 48 Source: JICA survey team In conditions of maximum tunnel temperature, 40 degree centigrade, conductor temperature is less than 90 degree centigrade. This result secures the required transmission capacity of 200MVA and 220MVA. The next step is to carry out calculations for required wind velocity in conditions of 500m intervals of ventilation towers to maintain less than 40 degree centigrade in the tunnel. Table 6.5-13 Wind velocity in tunnel (Normal operation) Operational conditions Transmission capacity (MVA/route) Total heat loss (W/cm) Sar Ta Lin – Hlawga 800 1.1 Thaketa - Hlawga 440 0.6 Required wind velocity (m/s) 1.1 Source: JICA survey team Source: JICA survey team Figure 6.5-12 Interval of ventilation towers and Air Temp. (1.1 m/s) Required wind velocity in tunnels is 1.1m/s to maintain less than 40 degree centigrade in tunnels. The next calculation is for N-1 operation. 6-48 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 2) Results for N-1 conditions (Sar Ta Lin – Hlawga) (Power flow in 2027, Figure 1.5-13) This table shows the results of the calculation in the case of N-1 conditions (Sar Ta Lin – Hlawga). Table 6.5-14 Results of calculation for N-1 (Sar – Hlw) in 2027 Conditions Transmission capacity (MVA) Circuits Conductor temperature (Centigrade) 800 3 50 440 2 48 Sar Ta Lin – Hlawga (N-1) 4 circuits --> 3 circuits Thaketa – Hlawga Source: JICA survey team Table 6.5-15 Line Wind velocity in tunnel (N-1 Sar - Hlw) Transmission capacity (MVA/route) Total heat loss (W/cm) Sar Ta Lin – Hlawga (N-1) 4 circuits --> 3 circuits 800 1.4 Thaketa - Hlawga 440 0.6 Required wind velocity (m/s) 1.4 Source: JICA survey team Source: JICA survey team Figure 6.5-13 Interval of ventilation towers and Air Temp. (N-1 Sar - Hlw) Conductor temperature is 50 centigrade and less than 90 centigrade in the case of N-1 conditions. Required wind velocity in tunnels is 1.4m/s to maintain less than 40 degree centigrade in tunnels, with 500m intervals between ventilation towers. 3) Results for N-1 conditions (Thaketa – Hlwaga) (Power flow in 2027, Figure 1.5-13) This table shows the results of the calculation in the case of N-1 conditions (Thaketa – Hlwaga). 6-49 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Table 6.5-16 Results of calculation for N-1 (Tha – Hlw) in 2027 Conditions Transmission capacity (MVA) circuit Conductor temperature (Centigrade) Sar Ta Lin – Hlwaga 800 4 47 Thaketa – Hlwaga (N-1) 2 circuits --> 1 circuit 440 1 62 Table 6.5-17 Wind velocity in tunnel (N-1 Tha - Hlw) Line Transmission capacity (MVA) Total heat loss (W/cm) Sar Ta Lin - Hlwaga 800 1.1 Thaketa - Hlawga (N-1) 2 circuits --> 1 circuit 440 1.1 Required wind velocity (m/s) 1.5 Source: JICA survey team Source: JICA survey team Figure 6.5-14 Interval of ventilation towers and Air Temp. (N-1 Tha - Hlw) Conductor temperature is 62 centigrade and less than 90 centigrade in the case of N-1 conditions. Required wind velocity in tunnels is 1.5m/s to maintain less than 40 degree centigrade in tunnels, with 500m intervals between ventilation towers. (3) Results of the calculation of the capacities based on the power flow in 2030 Study for normal conditions 230kV underground transmission lines capacities are calculated based on the power flow in 2030 (Figure 1.5-14). 1) Normal conditions in 2030 Sra Ta Lin – Hlawga: 1492MVA (373MVA×4 circuits) Thaketa – Hlawga: 777MVA (388MVA×2 circuits) ◎Results of calculation (Duct burial system) Permissible transmission capacity is 527MVA per circuit at 90 centigrade in normal operation for the duct burial system. 6-50 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Table 6.5-18 Results of calculation for Duct burial system Conditions Permissible transmission capacity (MVA/circuit) Number of circuits Total capacity (MVA) Conductor temperature (Centigrade) Normal 527 2 1054 90 Source: JICA survey team Sar Ta Lin – Hlwaga 373MVA < 527MVA Thaketa – Hlwaga 388MVA < 527MVA This figure (527MVA) is enough to meet the demand (373MVA and 388MVA) in normal operation in 2030 for the duct burial system. ◎Results of calculation (Tunnel system) This table shows the results of the calculation for cables with trefoil formation in the tunnel system. Table 6.5-19 Results of calculation for Tunnel system (trefoil) Name of line Transmission capacity (MVA) Total heat loss (W/cm) Sar Ta Lin – Hlwaga 1492 3.3 Thaketa – Hlawga 777 1.8 Temperature in tunnel (Centigrade) Required wind velocity (m/s) 40.0 3.1 Source: JICA survey team The required velocity to keep the temperature in the tunnel below 40 centigrade is 3.1 m/ s, which exceeds the allowable wind speed in the tunnel of 3.0 m/s. Cable spacing is secured between conductor axes of more than the Cable Diameter and a recalculation was carried out to reduce the total heat loss generated from the cable in the tunnel. The cable spacing is 200 mm. Table 6.5-20 Results of calculation for Tunnel system (phase separation) Name of line Transmission capacity (MVA) Total heat loss (W/cm) Sar Ta Lin – Hlwaga 1492 2.3 Thaketa – Hlawga 777 1.2 Required wind velocity(m/s) 2.2 Source: JICA survey team This result is enough to meet the demand (1492MVA and 777MVA) in normal operation in 2030 for the tunnel system. Temperature in the tunnel is 40 centigrade. Required wind velocity is 2.2m/s. ◎Results These results are enough to meet the power flow in 2030 in normal operation for the duct burial sections and tunnel sections. Sra Ta lin – Hlawag: 1492MVA (373MVA×4 circuits) 6-51 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Thaketa – Hlwaga: 777MVA (388MVA×2 circuits) Sar Ta Lin – Hlwaga in the case of N-1 conditions 230kV underground transmission line capacities are calculated in the case of N-1 for the Sar Ta Lin – Hlwaga line. Source: JICA survey team Figure 6.5-15 Conceptual diagram of Underground transmission system (N-1 Sar – Hlw) ◎Results of calculation (Duct burial system) This table shows the permissible transmission capacity for N-1 conditions in duct sections. Table 6.5-21 Results of calculation in Duct for N-1 (Sar – Hlw) Condition Permissible transmission capacity (MVA/circuit) Conductor temperature (Centigrade) N-1 622 90 Source: JICA survey team Permissible transmission capacity is 622MVA per circuit in the case of N-1 (Sar Ta Lin – Hlwaga) ◎Results of calculation (Tunnel system) This table shows the permissible transmission capacity of Sar Ta Lin (3 circuits) in the case of N-1 conditions with an indication of the transmission capacity for the Thaketa - Hlwaga line (2 circuits), which is installed in the same tunnel as the Sar Ta Lin – Hlwaga line. Wind velocity is 2.9m/s. 6-52 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Table 6.5-22 Results of calculation for Tunnel (N-1 Sar – Hlw) Transmission capacity (MVA) Thaketa Hlwaga 0 796 Sar Ta Lin - Hlwaga 1912 1581 Source: JICA survey team Transmission capacity of the Sar Ta Lin – Hlwaga line is 1912MVA in tunnel sections at 0MVA capacity of the Thaketa – Hlwaga line. However, transmission capacity of the Sar Ta Lin line is 1581MVA (527MVA x 3 circuits) in the duct burial section. Permissible transmission capacity of the Sar Ta Lin line is 1581MVA in N-1 conditions. ◎Results Permissible transmission capacity of the Sar Ta Lin – Hlwaga line is 1581MVA in the case of N-1 conditions. Therefore, transmission capacity of the Thaketa – Hlwaga line is 796MVA. Thaketa – Hlwaga in the case of N-1 conditions 230kV underground transmission line capacities are calculated in the case of N-1 for the Thaketa – Hlwaga line. Source: JICA survey team Figure 6.5-16 Conceptual diagram of Underground transmission system (N-1 Tha – Hlw) ◎Results of calculation (Duct burial system) This table shows the permissible transmission capacity for N-1 conditions in duct sections. 6-53 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Table 6.5-23 Results of calculation in Duct for N-1 (Tha – Hlw) Condition Permissible Transmission Capacity (MVA/circuit) Conductor temperature (Centigrade) N-1 622 90 Source: JICA survey team Permissible transmission capacity is 622MVA per in the case of N-1 (Thaketa – Hlwaga). ◎Results of calculation (Tunnel system) This table shows permissible transmission capacity for the tunnel system. Permissible transmission capacity is 828MVA per circuit at maximum conductor temperature. Table 6.5-24 Results of calculation of permissible transmission capacity for Tunnel Permissible transmission capacity (MVA/circuit) Conductor temperature (Centigrade) 828 90 Source: JICA survey team This table shows permissible transmission capacity for the Thaketa – Hlwaga line (1 circuit) in the case of N-1 conditions, with an indication of the transmission capacity for the Sar Ta Lin line (4 circuits), which is installed in the same tunnel as the Thaketa – Hlwaga line. Wind velocity is 2.9m/s. Table 6.5-25 Results of calculation for Tunnel (N-1 Tha – Hlw) Transmission capacity (MVA) Sar Ta Lin Hlwaga Thaketa Hlwaga 1418 1492 828 777 Source: JICA survey team Permissible transmission capacity for the Thaketa – Hlwaga line is 828MVA in N-1 conditions. Then transmission capacity of the Sar Ta Lin line is 1418MVA. ◎Results Permissible transmission capacity of the Thaketa – Hlwaga line is 828MVA in the case of N-1 conditions. Then transmission capacity of the Sar Ta Lin line is 1418MVA. The figure of 828MVA is defined for tunnel sections. In actual fact, the permissible transmission capacity of the Thaketa – Hlwaga line in the case of N-1 conditions is 622MVA because of the limited transmission capacity of 622MVA in duct sections. This figure shows the ventilation system to meet the power flow in 2030. Ventilation fans may be required for each ventilation tower. 6-54 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Figure 6.5-17 Example of ventilation system (cross section) Source: JICA survey team Figure 6.5-18 Example of ventilation system (plane figure) (4) Design for short and ground fault currents The study team calculates for short and ground currents in accordance with IEC 60949. The below two tables show the other conditions. Table 6.5-26 for conductor Item S θf θi Unit Basic conditions (Short fault) Description Remarks mm 2500 for copper conductor deg. C 250 final temperature deg. C 90 initial temperature 2 Table 6.5-27 Basic conditions (Ground fault) for metallic sheath Item Unit 2 Description Remarks S mm 1820 for aluminum sheath θf deg. C 150 final temperature θi deg. C 85 initial temperature 6-55 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Table 6.5-28 Results for short and ground faults Permissible short-circuit current and continuous time Necessity network fault and continuous time Conductor 208kA > 40kA 3sec 40kA Metallic sheath 122kA > 40kA 1sec 40kA 3sec 1sec Source: JICA survey team This result indicates that characteristics of the conductor and metallic sheath meet those for short and ground fault currents. (5) Design for Ducts Duct dispositions are basically designed with 345mm intervals from the results for transmission capacity and the manufacturer’s standards. There are two types of duct material: PFP and HDPE. PFP is more advantageous than HDPE in terms of strength. This figure shows the standard positons for ducts. Source: JICA survey team Figure 6.5-19 Standard distance for ducts (left) and Spacer (right) This table shows standard depth and other specifications. Table 6.5-29 PFP φ250 Duct specifications Item Value Standard depth 1200 mm Duct Interval 345 mm Outer diameter 286 mm Inner diameter 250 mm Remarks Refer to spacer catalog Source: JICA survey team (6) Design of Tunnel Cut and Cover Tunnels (Box Culvert Tunnel) or Non-Cut and Cover Tunnels (Shield Tunnel) can be considered for tunnel methods for Underground TL 230kV 6-circuit and 4-circuit sections from Hlawga S/S to Sar Ta Lin S/S. A comparison table of tunnel construction methods is shown in Table 6.5-30. In consideration of the impact on the surrounding area, road width, traffic congestion, 6-56 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) noise and vibrations from the 230kV 6-circuit and 4-circuit sections, Non-Cut and Cover Tunnels (Shield Tunnel) are proposed. A cross section of a Shield Tunnel with jointing cables in the tunnel is shown in Source: JICA survey team Figure 6.5-20. Table 6.5-30 Comparison table of tunnel construction methods Source: JICA survey team Source: JICA survey team Figure 6.5-20 Cross section of Shield Tunnel Per the survey results for the existing buried underground TL from Hlawga S/S to Sar Ta Lin S/S, the following existing buried facilities were confirmed on the underground TL route. The detailed report on existing facility investigation for the underground TL route is to be referred attached “Final Report for Route Study and Geological Survey for Transmission Lines under The Republic of the Union of Myanmar National Power Transmission Network Development Project - Preliminary Survey & Site Survey for Underground Transmission line on Phase III project”. 6-57 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) The vicinity of Hlawga S/S ・Φ14” Gas Pipe (Steel) Depth = 6 feet; Crossing Pyay Road ・Φ30” and Φ14” Gas Pipe (Steel) Depth = 6 feet; Buried on the sidewalk of Brochan Road Source: JICA survey team Figure 6.5-21 Existing facilities in the vicinity of Hlaga S/S The vicinity of the middle of Hlaga S/S and No. 3 Main Road ・Φ60” Water Pipe (Steel) Depth = 1.7m; Crossing Brochan Road ・Φ30” Gas Pipe (Steel) Depth = 0.7m; Crossing Brochan Road ・Φ30” and Φ14” Gas Pipe (Steel) Road Level; Buried on the sidewalk of Brochan Road ・Φ32” Water Pipe (HDPE) Depth?; Buried on the sidewalk of Brochan Road ・Φ24” Water Pipe (Ductile) Depth?; Buried on the sidewalk of Brochan Road Source: JICA survey team Figure 6.5-22 Existing facilities in the vicinity of the middle of Hlaga S/S and No. 3 Main Road The vicinity of the intersection of Brochan Road and No. 3 Main Road ・Φ30” Gas Pipe (Steel) Depth?; Crossing No. 3 Main Road 6-58 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) ・Φ24” Water Pipe (Ductile) Depth?; Buried on the sidewalk of Brochan Road ・Φ48” Water Pipe Depth?; Crossing Brochan Road ・Water Valve and Manholes; Buried on the sidewalk of Brochan Road Source: JICA survey team Figure 6.5-23 Existing facilities in the vicinity of the intersection of Brochan Road and No. 3 Main Road The schematic longitudinal section of the Shield Tunnel is shown inSource: JICA survey team Figure 6.5-24. The boring logs for Hlawga S/S shown in Figure 3.3-28 are adopted. The groundwater level is estimated to be 4.1m below the ground surface, and the target soil for the Shield Tunnel is sandy soil with an N value of about 8. The depth of tunnel is determined to be 5.0m considering existing facilities and the impact on the ground surface due to tunnel excavation. It will be necessary to consider the results of surveys on existing buried facilities and the results regarding the cable installation method at the detailed design stage. Source: JICA survey team Figure 6.5-24 Longitudinal section of Shield Tunnel (7) Design for Manholes Manhole design is carried out in accordance with the permissible bending radius of cable (15D: D is the overall diameter of cable -> around 2300mm). This figure shows a Manhole for a cable joint of 2 circuits and 6 circuits. Manhole for 2 circuits: length 12.5(m) height 3.4(m) width: 2.1(m) Manhole for 6 circuits: length 15(m) height 5.7(m) width: 2.5(m) 6-59 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) A cable joint is fabricated in each manhole in each section of ducts (2 circuits). Source: JICA survey team Figure 6.5-25 Standard type of manhole (2 circuits) Source: JICA survey team Figure 6.5-26 Standard type of manhole (6 circuits) The tunnel for 6 circuits is built using the shield method. A cable joint is fabricated in a tunnel (6 circuits). Joint Box Around 130m/3 circuits Source: JICA survey team Figure 6.5-27 Cable joint in Tunnel 6-60 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Joint Box for 1 Phase Figure 6.5-28 Cable joint in tunnel (cross section) (8) Overall construction schedule for transmission line This figure shows a tentative schedule for civil and cable work. Civil construction is the first step. Cable installations are implemented after civil work for the section of duct as soon as possible. Then, cable installations in the tunnel are implemented after the civil work for the shield tunnel. (month) Item 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Design Preparation for work Building shoring shoring Starting Shaft1 Starting Shaft2 Building shoring Building Arriving Shaft1 ①Shield Tunnel (2.3km) ②Shield Tunnel0 (0.9km) Ventolaton Tower Cable work Restoratiojn for road Source: JICA survey team Figure 6.5-29 Overall construction schedule for cable (Month) Item 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Civil work Survey and Design Preparation for work Installation for cable (Duct) 3teams Fabrication for cable joint(Duct) 1team/circuit Inatallation(Tunnel) 3teams Fabrication for cable joint(Duct) 1team/circuit Incidential work Final site test Source: JICA survey team Figure 6.5-30 Overall construction schedule for civil work 6-61 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 6.6. Substations General The JICA Survey Team has visited the candidate substation sites and confirmed the availability and technical viability of the new constructions and extensions, and carried out basic designs for each substation as described in the subsequent sections. Design Concepts The following concepts shall be applied to the design of substations to maximize their functions: (1) General Concept Daily operation and maintenance (O&M) shall be performed safely and in accordance with approved procedures. The connection shall be made as simple as possible without affecting the required performance from installed substation equipment. If a fault occurs in a substation, the extent of the fault’s impact shall be kept to a minimum, and the necessary switching operation for shifting loads to other substations shall be performed immediately, without delay or trouble. Design considerations must include facilitating future reinforcement and/or augmentation, when necessary. Design must be technically and economically feasible. (2) Type of Substation The standard substation in Myanmar is, in principle, an outdoor type with conventional equipment. An outdoor type substation is a substation with major facilities, such as main transformers, switchgear instruments, etc. installed in the open air. Other options for switchgear are gas-insulated switchgear (GIS) or Hybrid gas-insulated switchgear (H-GIS). A GIS system requires only 15% of the space necessary for an air-insulated switchgear (AIS) system, and an H-GIS system, to be applied to Pharyargyii substation in Phase 2, requires 70%. The costs for the GIS system and buildings, however, are twice those of the AIS system. The GIS system is mostly suitable for areas with space constraints, such as city centers, industrial areas, etc. or areas with high air pollution levels. The basic design considers AIS systems for outdoor, as well as GIS or H-GIS systems depending on installation requirements and site conditions. (3) Busbar Arrangement Currently, a one and a half circuit breaker arrangement for 500 kV switchgear and double busbar arrangement for 230 kV switchgear are employed for the substation systems in Myanmar, including the Phase 2 project. Therefore, the busbar arrangement shall be carefully decided considering the following: - Existing busbar arrangement (in case of extension) Supply reliability and security Operational performance and flexibility Capital costs Maintenance and repair requirements Space requirements Busbar #1 DS CB DS DS CB DS DS Source: JICA SURVEY TEAM Figure 6.6-1 One and a Half CB Arrangement CB DS (4) Main Transformers Busbar #2 The main transformers which will be installed in the new 500 kV substation are of an oil-immersed type with on-load tap changer. Three units with single phase transformer (auto transformer) and with star-star-delta (Y-Y-Δ) winding connections are applied for the main transformers. Natural oil circulation and natural air cooling (ONAN) conventions and/or a natural oil circulation and forced air cooling (ONAF) system is applied for the cooling system of the main transformers. The unit capacity and number of units of main transformers in a substation are determined 6-62 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) comprehensively taking into account the results of the system analysis in Chapter 1. (5) Short-Circuit Fault Current Capacity Short-circuit fault current capacity for substation facilities will be determined via the results of the system analysis. However, in the case of expansion of an existing substation, the rated short-circuit fault current shall be the same as that of the existing substation or the transmission feeder of the connected substation. (6) Transmission Line Protection Protection relays for 500 kV and 230 kV transmission lines are designed with dual protection in accordance with existing facilities in Myanmar, as follows: 500 kV Transmission Line Protection Main Protection 1 : Differential Relay (87) Main Protection 2 : Distance Protection (21) Back-up Protection : Overcurrent and ground fault protection (50/51N) 230 kV Transmission Line Protection Main Protection 1 : Differential Relay (87) Main Protection 2 : Distance Protection (21) Back-up Protection : Overcurrent and ground fault protection (50/51N) (7) Control Equipment We understand that there is a vision to collect all data/information from power plants and substations in Myanmar at the National Control Center (NCC) located in Nay Pyi Taw, and there is a guiding principle that the equipment for collecting data/information shall be based on IEC 61850. Under these circumstances, we will propose to configure the Substation Automation System (SAS) based on IEC 61850 after careful confirmation of the intentions and planning by the Myanmar side. System Configuration of SCADA Based on IEC61850 - P o s s i b l e t o a c h i ev e t h e unifi ed prote cti on of each substation in NCC by digitalizing all signals from facility level in substation to high-order system. - Easy interface because all signals including measured value and communication between all devices are connected in digital telecommunication network SCADA Internet Work Station CPU Gateway Station Level Control IEC61850 Station Bus Bay Controller IED IED NCC Bay Controller IED IED Bay Level Control IEC61850 Process Bus Ethernet Switch IED: Intelligent Electronic Device MD: Merging Unit ICU: Intelligent Control Unit CB: Circuit Breaker CT: Current Transformer VT: Voltage Transformer ICU CB Ethernet Switch MU VT MU CT VT ICU CT CB Process Level Control Source: JICA Survey Team Figure 6.6-2 System Configuration of Substation based on IEC 61850 (8) Tele-protection system Optical telecommunication via OPGW for the main system and Power Line Communication (PLC) as a back-up system are used in Myanmar. Therefore, the telecommunication system in this Project is basically an Optical telecommunication system with OPGW, and a PLC system will also be considered, if necessary. (9) Other Concepts 1) Earthing system In the switchyard of the new substation, an underground earthing system should be properly laid in the form of a meshed grid. In the case of extension of an existing substation, the new earthing system should connected the existing system. 6-63 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) All equipment installed in a substation should be connected to an earthing system effectively. Resistance of the earthing system shall be designed based on IEEE 80. 2) Countermeasures for disasters i) Dust Pollution For substations constructed in areas affected by dust contamination, appropriate countermeasures shall be taken into account in the design based on the level of pollution. ii) Lightning For the protection of substation equipment from lightning, appropriate measures shall be taken in the design of the substation to achieve the required network reliability and site-specific conditions. iii) Fire Appropriate measures shall be taken to protect operators and equipment from fire or explosions and, in the worst situations, to localize the fire to within a limited area. iv) Earthquakes The effect of earthquakes will be considered in the basic design of substations. 3) Considerations for environment i) Noise Include in the planning of a substation, which is to be newly constructed or expanded, necessary measures to limit noise to within reasonable levels. ii) Vibration Include in the planning of a substation, which is to be constructed or expanded, necessary measures to limit the vibration levels in the substation to within the country-recognized standard values. iii) Harmony with environment For a substation that is to be constructed or expanded, special attention should be given to the protection of the natural environment in the surrounding areas, and to the presentation of the living environment, such as sunshine, scenery, radio interference, etc., as well as harmony with the regional community. Design Criteria (1) Applicable Standards The design, materials, manufacture, testing, inspection and performance of all electrical and electromechanical equipment shall comply with the latest revision of the International Electrotechnical Commission Standards (IEC), as listed below: Instrument transformers – Part 1: Current transformers Instrument transformers – Part 5: Capacitor voltage transformers Insulation coordination Power transformers Surge arresters – Part 4: Metal-oxide surge arresters without gaps for a.c. systems IEC 60265-2 High-voltage switches – Part 2: High-voltage switches for rated voltage of 52 kV and above IEC 60694 Common specifications for high-voltage switchgear and control gear standards IEC 61850 Communication network and systems in substations IEC 62271-100 High-voltage switchgear and control gear – Part 100: High-voltage alternative-current circuit breakers IEC 62271-102 High-voltage switchgear and control gear – Part 102: Alternative-current disconnectors and earthing switch IEC 62271-203 High-voltage switchgear and control gear – Part 203: Gas-insulated metal -enclosed switchgear for rated voltage above 52 kV In cases where IEC standards are not applicable to the conditions, international standards such as ANSI, ASTM, BS, JIS, JEC and JEM will be applied. IEC 60044-1 IEC 60044-1 IEC 60071 IEC 60076 IEC 60099-4 (2) Insulation Co-ordination Insulation co-ordination for the design of 500 kV, 230 kV, 66 kV and 33 kV equipment are as 6-64 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) follows: (1) (2) (3) (4) Nominal system voltage Rated voltage (Highest voltage) Rated frequency Insulation levels Rated short-duration power frequency withstand voltage (r.m.s) Rated lightning impulse withstand voltage (peak value) Minimum clearance of phase-toearth Standard clearance of phase-toearth Minimum clearance of phase-tophase Standard clearance of phase-tophase 500 kV 525 kV 50 Hz 230 kV 245 kV 50 Hz 66 kV 69 kV 50 Hz 33 kV 36 kV 50 Hz 80 kV 1,550 kV 750 kV 350 kV 195 kV 4,100 mm 2,100 mm 700 mm 400 mm 8,000 mm 2,600 mm 1,000 mm 500 mm 5,400 mm 3,000 mm 1,100 mm 600 mm 8,000 mm 4,000 mm 1,500 mm 900 mm Sar Ta Lin New 500 kV Substation (1) Location and Current Situation As described in Chapter 2.6, Sar Ta Lin substation will be constructed at latitude 17° 03’ 50” north and longitude 96° 17’ 28” east on the northern side of the YCDC area. The location map of the new Sar Ta Lin 500 kV substation is referred to in Figure 2.6-1 and Figure 4.2-4. Although the land acquisition will be conducted on the initiative of DPTSC, the current situation of the land is a farm, as shown in the following pictures: Source: JICA Survey Team Figure 6.6-3 Photos of Planned Location for Construction of Sar Ta Lin Substation (2) Scope of Work for the Project The JICA Study Team carried out a site survey and basic design for construction of the new 500 kV substation considering future expansion and augmentation of the substation. (3) Busbar Arrangement and Layout 1) Busbar Arrangement Since the new Sar Ta Lin 500 kV substation will play a significant role in supplying power to Yangon City, the configuration of the 500 kV switchgear, as a backbone facility, must be reliable. Therefore, the JICA Survey Team adopted a one and a half circuit breaker arrangement, the same as the Pharyargyii substation. As for 230 kV switchgear, a double busbar arrangement is adopted considering expandability and reliability. 2) Layout In order to avoid influence on surrounding residences, Sar Ta Lin Substation will be constructed 6-65 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) within land of approx. 530 m x 450 m, as shown in Annexure-6-4-2. (4) Equipment Procurement and Quantities In this Project, 500 kV switchgear with eight bays of transmission line, three bays of main transformer having a capacity of 500 MVA per each unit, two bays of 500 kV shunt reactors and 230 kV switchgears with eight bays of transmission lines, three bays of transformers and bus coupler bays are to be installed in Sar Ta Lin new 500 kV substation. The drawings in Appendix 6-4-1 show the basic design of new 500 kV substation. - DWG No. MY-TLP3-NS-SLD_01 Single Line Diagram (Appendix 6-4-1) 1) 500 kV Substation Facility i) Ten units, including spares for 500/230/33 kV, 166.7 MVA and single-phase main transformer with on-load tap changer (OLTC) ii) Two units of 500 kV shunt reactor, 100 MVar iii) 500 kV switchgear in one and a half circuit breaker arrangement The 500 kV switchgear in one and a half circuit breaker scheme includes eight (8) transmission line bays and three (3) transformer bays 500 kV GCB 24 sets 500 kV DS/ES 60 sets 500 kV CT 60 sets 500 kV VT 13 sets 500 kV CVT 8 sets 420 kV SA 12 sets Line trap 16 sets 500 kV busbar 1 lot (One and a Half CB arrangement) The associated gantry structures for the above system shall be supplied and installed. The associated steel support structures and foundations for the above equipment with all necessary connecting materials shall be supplied and installed. The connection work between the dead-end towers, associated gantry structures and the above equipment shall be carried out and all necessary materials for the work such as power conductors, tension insulator sets, fittings, post insulators, connectors, accessories, power and control cables, etc. shall be supplied and installed. The above equipment shall be properly earthed with underground earthing mesh and all necessary materials such as earthing conductors shall be supplied. 2) 230 kV Switchgear i) 230 kV double busbar scheme switchgear The 230 kV double busbar scheme includes eight (8) transmission line bays, three (3) transformer bays and one (1) bus coupler bay. 230 kV GCB 12 sets 230 kV DS/ES 11 sets 230 kV DS 22 sets 230 kV CT 12 sets 230 kV CVT 13 sets 196 kV SA 11 sets Line trap 16 sets 230 kV busbar 1 lot (Double busbar scheme) The associated gantry structures for the above system shall be supplied and installed. The associated steel support structures and foundations for the above equipment with all necessary connecting materials shall be supplied and installed. The connection work between the dead-end towers, associated gantry structures and the above equipment shall be carried out and all necessary materials for the work such as power conductors, tension insulator sets, fittings, post insulators, connectors, accessories, power and control cables, etc. shall be supplied and installed. The above equipment shall be properly earthed with underground earthing mesh and all necessary materials such as earthing conductors shall be supplied. 3) Installation of Control and Protection panels 6-66 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Protection relay panel Main transformer protection relay panel 3 panels 500 kV shunt reactor protection relay panel 2 panels 500 kV transmission line protection relay panels 8 panels 500 kV busbar protection relay panels 2 panels 230 kV transmission line protection relay panels 8 panels 230 kV busbar protection relay panels 2 panels Control panel Main transformer primary side control panel 3 panels Main transformer OLTC panels 3 panels 500 kV shunt reactor control panel 2 panels 500 kV transmission line control and synchronizing panel 8 panels 230 kV transmission line control and synchronizing panel 8 panels SCADA (SAS) Remote control and monitoring system 1 lot The associated power and control cables with necessary accessories shall be supplied and installed. All necessary meters including ammeters, voltmeters and watt-hour meters, etc. shall be supplied and installed. SCADA system shall be designed with control, monitoring and measuring of 500 and 230 kV switchyard, 500/230/33 kV main transformers, 500 kV shunt reactors and 33 kV switchgear 4) Installation of communication equipment The following optical-fiber telecommunication equipment shall be supplied and installed. Optical distribution frame (ODF) for connection and 24 core optical fiber cable Patch cables connecting ODF with synchronous transport module -1 (STM-1) and multiplexer Supply STM-1 and multiplexer with multi channels of not less than 2 Mbit/s interface. Optical fiber splicing boxes (i.e., for termination of OPGW on the steel gantry structure in the substation) 5) Miscellaneous electrical equipment Indoor type 500 kVA auto start module type diesel generator set with associated switchgear, power cables and fuel tank 400 V AC distribution switchboard equipped with double-throw breaker including necessary cables and accessories 110 V DC system including two sets of 110 kV battery banks, two sets of chargers, and one set of distribution boards 50 V DC system including two sets of 50 V batteries, two sets of chargers, and one set of distribution board Earthing system covering the new substation area including earthing rods, conductors, etc. Overhead substation shield wire system including shield wires and supporting structures for protection against lightning Outdoor substation lighting system 6) Civil and building work The associated civil and building work for the above work shall be carried out as follows: Cleaning, cutting, filling, leveling and compacting of the new substation area Excavation and backfilling as required Gravelling of the complete additional substation area Construction of external security fences Construction of station service road Construction of gantries for 500 kV and 230 kV switchyards Construction of steel structures and equipment support Construction of concrete foundations for all equipment Construction of oil pit from main transformers and shunt reactors Construction of drainage pit and conduit Construction of cable pit 6-67 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Construction of a complete substation control building with control room, 33 kV cubicle room, office, workshop, storage room, battery room, kitchen, toilet, etc. Construction of guard house for security personnel beside the main gate Supply and installation of air conditioning and ventilation equipment for the substation building Supply and installation of water well and storage facility and wastewater and septic tank facility Supply and installation of firefighting equipment associated with air conditioning system for the control building All necessary materials for the above work such as concrete, aggregate, reinforcements, accessories, etc. shall be supplied. 6) Other work Spare parts for at least 5 years of operation Tools and erection accessories as required Complete documentation for operation and maintenance Training for DPTSC staff at manufacturer’s factory and at site (5) Specifications of Major Equipment 1) 500/230/33 kV Main transformer i) Type Single-phase, oil-immersed type, outdoor and ONAN/ONAF cooling type with on-load-tap changing device, designed in accordance with IEC 60076 and 60289. ii) Ratings Rated power Rated frequency Rated voltage ratio Vector group notation Short circuit impedance Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) iii) - 166.7 MVA (ONAN/ONAF) 50 Hz 500/230/33 kV YNa0d11 About 12.0 % HV LV 750 kV 395 kV 1,550 kV 750 kV On-load tap changing equipment (OLTC) Step: ±8 x 1.25 % Number of taps: 17 taps 2) 500 kV Shunt Reactor i) Type Three-phase, oil-immersed type, outdoor and ONAN cooling type shall be designed in accordance with IEC 60076 and 60289. ii) Ratings Rated voltage Rated Rated frequency Rated insulation level at HV side (LI&PF)/current 500 kV 100 MVA 50 Hz To be determined in Final Report 3) Gas Insulated Switchgear i) Type The GIS or H-GIS shall be metal-enclosed, three-phase busbar and switchgear type, for outdoor use, and filled with SF6 insulation gas. ii) Circuit breaker Rated voltage Rated main busbar normal current Rated feeder normal current Rated frequency Rated short-circuit breaking current Rated interrupting time 500 kV 6,000 A 2,500 A 50 Hz 40 kA, 1 sec. less than or equal to 3 cycle 6-68 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Rated operating sequence Rated closing operation voltage Rated control voltage Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) O - 0.3 sec. - CO - 3 min. - CO DC 110 V DC 110 V 750 kV 1,550 kV The circuit breakers shall be suitable for single-pole tripping and rapid auto-reclosing, provided with a motor-operated spring mechanism, and shall comply with the related IEC standards/recommendations. The circuit breakers shall be equipped with an operation mechanism for DC and the mechanism shall ensure uniform and positive closing and opening. iii) Disconnectors and earthing switches Rated voltage Rated normal current Rated frequency Rated short-circuit withstand current Rated control voltage Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) 500 kV 2,500 A 50 Hz 40 kA, 1 sec. DC 110 C 750 kV 1,550 kV The disconnectors and earthing switch shall both be motor-operated and provided with a manual operating mechanism. Motor-operated disconnectors and earthing switch shall be designed with three-pole operation and the motor shall be operated on DC auxiliary power. iv) Current transformer Highest system voltage Rated frequency Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) Rated current ratio Accuracy classes v) 525 kV 50 Hz 750 kV 1,550 kV 2,500-1,250 A : 1 A(TL and busbar) 1,000A : 1A (SS) 5P20 for protection, Class 0.2 for metering Voltage transformer Highest system voltage Rated frequency Voltage ratio Accuracy classes Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) 525 kV 50 Hz 500 𝑘𝑉 110 𝑉 110 𝑉 : : √3 √3 √3 3P+0.5 750 kV 1,550 kV 4) Air Insulated Switchgear i) Circuit breaker The 230 kV circuit breakers shall be SF6 gas type, with three-pole collective arrangement and for outdoor use. The circuit breakers shall be suitable for single-pole tripping and rapid auto-reclosing, provided with a motor-operated spring mechanism, and shall comply with the related IEC standards/recommendations. Rated voltage Rated feeder normal current Rated frequency 230 kV 2,000 A 50 Hz 6-69 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Rated short-circuit breaking current Rated interrupting time Rated operating sequence Rated closing operation voltage Rated control voltage Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) 40 kA, 1 sec. less than or equal to 3 cycle O - 0.3 sec. - CO - 3 min. - CO DC 110 V DC 110 V 395 kV 750 kV The circuit breakers shall be equipped with an operation mechanism for DC power, motor operated and with a manual handle and the mechanism shall ensure uniform and positive closing and opening. ii) Disconnectors and earthing switches The 230 kV disconnectors shall be three-phase, two-column, rotary and center air break type with horizontal operation. Earthing switches shall be triple-pole, single-throw, vertical single break and manual three-phase group operation type. The disconnectors and earthing switches shall be suitable for outdoor use. The earthing switches shall be mounted on the disconnectors whenever necessary and where specified. Rated voltage Rated normal current Rated frequency Rated short-circuit withstand current Rated control voltage Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) 230 kV 2,000 A 50 Hz 40 kA, 1 sec. DC 110 C 395 kV 750 kV The disconnectors shall be motor-operated and provided with a manual operating mechanism with a hand crank. The earthing switch shall be provided with a manual operating mechanism. Motor-operated disconnectors shall be designed with three-pole operation and the motor shall be operated on DC power. iii) Current transformer The 230 kV current transformers shall be single-phase, porcelain-insulated, oil-immersed and airtight sealed post insulator type, for outdoor use and shall be designed in accordance with IEC 600441. Highest system voltage Rated frequency Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) Rated current ratio Accuracy classes 230 kV 50 Hz 750 kV 1,550 kV 4,000-2,000 A : 1 A(TL) 2,000-1,000 A : 1 A(TL) 4,000 A : 1 A (Busbar) 2,500-1,250 A : 1 A (SS) 1,000A : 1A (SS) 5P20 for protection, Class 0.2 for metering iv) Capacitor Voltage transformer The 500 and 230 kV voltage transformers shall be single-phase, capacitor type and shall be designed in accordance with IEC 60044-5. Highest system voltage Rated frequency Voltage ratio Accuracy classes 525 kV 50 Hz 500 𝑘𝑉 110 𝑉 110 𝑉 : : √3 √3 √3 3P+0.5 6-70 245 kV 230 𝑘𝑉 110 𝑉 110 𝑉 : : √3 √3 √3 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Rated insulation level Rated short-duration power-frequency withstand a) voltage (r.m.s. value) Rated lightning impulse withstand voltage (peak b) value) 750 kV 395 kV 1,550 kV 750 kV v) Surge Arresters The 420 and 196 kV surge arresters shall be gapless, metal-oxide, outdoor and heavy duty type. The arresters shall be designed in accordance with IEC 60099-4. Rated voltage (r.m.s. value) Rated frequency Nominal discharge current Long-duration discharge class Pressure-relief current Rated insulation levels for insulators Rated short-duration power-frequency a) withstand voltage (r.m.s. value) Rated lightning impulse withstand voltage b) (peak value) 420 kV 196 kV 50 Hz 10 kA 10 kA Class 3 (Table-5, IEC 60099-4) 40 kA 750 kV 395 kV 1,550 kV 750 kV East Dagon Substation (1) Location and Current Situation 1) Location As shown in the following figure, the East Dagon S/S is located at latitude 16° 57’ 02” north and longitude 96° 16’ 43” east in the East Dagon Township of Yangon City. Source: JICA Survey Team by using Google Earth Figure 6.6-4 Location Map of East Dagon Substation 2) Current situation The East Dagon substation has been operating since 2016 and consists of the following equipment: 230 kV Gas insulated switchgear (Manufacturer: Hyundai) 6-71 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Double busbar scheme Two (2) transmission line bays to Thaketa substation and Thanlyin substation, one circuit for each Two (2) transformer bays Bus coupler Two (2) sets of 230/66/11 kV main transformers (Manufacturer: Hyundai) Rated capacity: 125 MVA OLTC: 17 taps Cooling method: ONAF/ONAN Impedance: 12.328 % 66 kV Gas insulated switchgear (Manufacturer: Hyundai) Double busbar scheme Eight (8) transmission line bays Two (2) transformer bays Bus coupler 11 kV switchgear Station service facilities Source: JICA Survey Team Figure 6.6-5 Photos of Current East Dagon Substation The arrangement of control and protection panels for 230 and 66 kV switchgear in the control room is shown in Figure 6.6-6 below. After examination, the JICA Survey Team confirmed that there is enough space for installation of additional panels in the case of expansion of switchgear in the Project. Panel List: 1. 230/66/11 kV Transformer No.2 Control & Protection Panel 2. 230 kV Transmission Line No.2 (Tharketa) Control & Protection Panel 3. 230 kV Bus Coupler Control & Protection Panel 4. 230 kV Transmission Line No.1 (Thanlyin) Control & Protection Panel 5. 230/66/11 kV Transformer No.2 Control & Protection Panel 6. 230 kV Busbar Differential Protection Panel 800 3 4 5 6 800 7 13 800 19 800 20 600 800 2 800 800 800 1 800 2,630 2,630 800 21 14 800 9 15 800 10 16 600 11 17 800 23 12 18 800 24 830 830 8,530 800 8 800 600 22 800 2,000 1,020 830 11,800 7. 66 kV Transmission Line Control & Protection Panel No.8 8. 66 kV Transmission Line Control & Protection Panel No.7 9. 66kV Transformer Control & Protection Panel No.2 10. 66 kV Transmission Line Control & Protection Panel No.6 11. 66 kV Transmission Line Control & Protection Panel No.5 12. 66kV Bus Coupler Control & Protection Panel 13. 66 kV Transmission Line Control & Protection Panel No.4 14. 66 kV Transmission Line Control & Protection Panel No.3 15. 66kV Transformer Control & Protection Panel No.1 16. 66 kV Transmission Line Control & Protection Panel No.2 17. 66 kV Transmission Line Control & Protection Panel No.1 18. 66kV Busbar Differential Protection Panel 19. 20. 21. 22. 23. 24. Remote Control Panel No.2 Remote Control Panel No.1 Under Frequency Protection Panel Central Processing Module East Dagon S/S Fault Recording System No.1 East Dagon S/S Fault Recording System No.2 :Available Space for Panel Installation in Phase 3 Source: JICA Survey Team Figure 6.6-6 Layout of Control Room in East Dagon Substation 6-72 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (2) Scope of Work for the Project In the Project, two (2) additional 230 kV transmission line bays in GIS shall be installed in order to connect the 230 kV T/L to the new 500 kV substation. Therefore, the JICA Survey Team carried out a basic design for the augmentation of the 230 kV transmission line bay. (3) Busbar Arrangement and Layout i) Busbar arrangement Double busbar scheme is applied to 230 kV GIS in East Dagon substation, as per the following figure: 230kV Thanlyin 230kV Tharkheta SA SA VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M DS+ES 1,600A 40kA DS+ES 1,600A 40kA M M M M 3,000-1,600/1A 5P20, 20VA 3,000-1,600/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 0.2FS5, 20VA 1,600-800/1A 0.2FS5, 20VA GCB 1,600A 40kA GCB 1,600A 40kA M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M M 245kV BB1-B, 3,150A, 40kA 245kV BB1-A, 3,150A, 40kA 245kV BB2-B, 3,150A, 40kA 245kV BB2-A, 3,150A, 40kA M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA DS 1,600A 40kA DS 1,600A 40kA M M M DS+ES 3,150A, 40kA M DS+ES 3,150A, 40kA M M M 3,000-1,600/1A 5P20, 20VA M DS 1,600A 40kA DS 1,600A 40kA M M M 3,000-1,600/1A 5P20, 20VA 3,000-1,600/1A 5P20, 20VA GCB 1,600A 40kA GCB 1,600A 40kA 3,000-1,600/1A 0.2FS5, 20VA GCB 3,150A 40kA 3,000-1,600/1A 5P20, 20VA 800-400/1A 5P20, 30VA 800-400/1A 5P20, 30VA 800-400/1A 5P20, 30VA 800-400/1A 0.2FS5, 20VA M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA 3,000-1,600/1A 5P20, 20VA 800-400/1A 5P20, 30VA M M 800-400/1A 0.2FS5, 20VA M DS+ES 1,600A 40kA M M DS+ES 1,600A 40kA M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA SA SA 230/66/11 kV Transformer No.1 125MVA YNyn0d11 ONAF/ONAN 230/66/11 kV Transformer No.2 125MVA YNyn0d11 ONAF/ONAN Source: JICA Survey Team Figure 6.6-7 Single Line Diagram of 230 kV Switchgear in East Dagon Substation Since there are no spare feeders in the existing 230 kV GIS, installation of two (2) additional feeders of transmission line is required in the Project. A single line diagram of 230 kV switchgear after the Project is shown below: 6-73 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Spare Spare 230kV Sar Ta Lin SS (1) 230kV Sar Ta Line SS (2) VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M DS+ES 1,600A 40kA M M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M DS+ES 1,600A 40kA DS+ES 1,600A 40kA M M M M SA SA DS+ES 1,600A 40kA M M M M M 3,000-1,600/1A 5P20, 20VA 3,000-1,600/1A 5P20, 20VA 3,000-1,600/1A 5P20, 20VA 3,000-1,600/1A 5P20, 20VA 3,000-1,600/1A 5P20, 20VA 3,000-1,600/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 5P20, 20VA 1,600-800/1A 0.2FS5, 20VA 1,600-800/1A 0.2FS5, 20VA 1,600-800/1A 0.2FS5, 20VA 1,600-800/1A 0.2FS5, 20VA 1,600-800/1A 0.2FS5, 20VA 1,600-800/1A 0.2FS5, 20VA GCB 1,600A 40kA GCB 1,600A 40kA M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M DS+ES 1,600A 40kA DS+ES 1,600A 40kA 230kV Thanlyin 230kV Tharkheta SA SA M M M GCB 1,600A 40kA GCB 1,600A 40kA M M M GCB 1,600A 40kA GCB 1,600A 40kA M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M M 245kV BB1-A, 3,150A, 40kA 245kV BB1-B, 3,150A, 40kA 245kV BB2-A, 3,150A, 40kA 245kV BB2-B, 3,150A, 40kA M Scope of This Project VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA DS 1,600A 40kA DS 1,600A 40kA M M M DS+ES 3,150A, 40kA M 3,000-1,600/1A 5P20, 20VA M DS+ES 3,150A, 40kA M M M DS 1,600A 40kA DS 1,600A 40kA M M M 3,000-1,600/1A 5P20, 20VA 3,000-1,600/1A 5P20, 20VA GCB 1,600A 40kA GCB 1,600A 40kA 3,000-1,600/1A 0.2FS5, 20VA GCB 3,150A 40kA 3,000-1,600/1A 5P20, 20VA 800-400/1A 5P20, 30VA 800-400/1A 5P20, 30VA 800-400/1A 5P20, 30VA 800-400/1A 0.2FS5, 20VA M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA 3,000-1,600/1A 5P20, 20VA 800-400/1A 5P20, 30VA M M 800-400/1A 0.2FS5, 20VA M DS+ES 1,600A 40kA M M DS+ES 1,600A 40kA M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA SA SA 230/66/11 kV Transformer No.1 125MVA YNyn0d11 ONAF/ONAN 230/66/11 kV Transformer No.2 125MVA YNyn0d11 ONAF/ONAN Source: JICA Survey Team Figure 6.6-8 Single Line Diagram of 230 kV Switchgear in East Dagon Substation After the Project 2) Layout There is unused space of approx. 30 m at the east side of the existing 230 kV GIS, as per the following figure. This is sufficient to install four (4) additional GIS feeders including spares for the Project. 230 kV TL to Sar Ta Lin 500 kV SS – 2 cct Existing 66kV TL Gantry Structure for 230 kV TL Existing 66kV TL Existing 66kV TL About 30 m Expansion of 230 kV GIS 230 kV Underground Cable To Existing 230 kV GIS 6-74 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Source: JICA Survey Team Figure 6.6-9 Layout of 230 kV Switchgear in East Dagon Substation 3) Method of Expansion for 230 kV GIS When the 230 kV GIS is extended in the Project, it is desirable to connect additional bays to the existing GIS via the optimum method in order to reduce the power outage time at the substation to the minimum. The method of expansion obtained from the original manufacturer is attached in Appendix 6-4-6. (4) Equipment Procurement and Quantities In this Project, two (2) additional bays are installed in the East Dagon substation. The drawings in Appendix 6-4-3 show the basic design of East Dagon substation. DWG No. MY-TLP3-ED-SLD_02 Single Line Diagram (Appendix 6-4-3) 1) i) ii) Expansion of 230 kV switchgear 230 kV GIS transmission line bay 245 kV feeder 4 feeders GIS local control panel 4 panels Cable head (GIS) 2 sets 230 kV outdoor switchgear 245 kV CVT 6 sets Line trap 4 sets Cable head (AIS) 2 sets 196 kV SA 3 sets The associated gantry structures for the above system shall be supplied and installed. The associated steel support structures and foundations for the above equipment with all necessary connecting materials shall be supplied and installed. The connection work between the dead-end towers, associated gantry structures and the above equipment shall be carried out and all necessary materials for the work such as power 6-75 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) conductors, tension insulator sets, fittings, post insulators, connectors, accessories, power and control cables, etc. shall be supplied and installed. The above equipment shall be properly earthed with underground earthing mesh and all necessary materials such as earthing conductors shall be supplied. iii) Extension of protection and control panels Protection relay panel 230 kV transmission line protection relay panels 2 panels Control panel 230 kV transmission line control and synchronizing panel 4 panels SCADA system Modification of existing SCADA system The associated power and control cables with necessary accessories shall be supplied and installed. All necessary meters including ammeters, voltmeters and watt-hour meters, etc. shall be supplied and installed. 2) Civil and building work Cleaning, cutting, filling, leveling and compacting around additional GIS and 230 kV T/L terminal tower. Excavation and backfilling as required 3) Other work Spare parts for at least 5 years of operation Tools and erection accessories as required Complete documentation for operation and maintenance Training for DPTSC staff at manufacturer’s factory and at site (5) Specifications of Major Equipment 1) Gas insulated switchgear i) Type The GIS shall be metal-enclosed, three-phase busbar and switchgear type, for outdoor use, and filled with SF6 insulation gas. ii) Circuit breaker Rated voltage Rated main busbar normal current Rated feeder normal current Rated frequency Rated short-circuit breaking current Rated interrupting time Rated operating sequence Rated closing operation voltage Rated control voltage Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) 245 kV 3,150 A 1,600 A 50 Hz 40 kA, 1 sec. less than or equal to 3 cycle O - 0.3 sec. - CO - 3 min. - CO DC 110 V DC 110 V 395 kV 750 kV The circuit breakers shall be suitable for single-pole tripping and rapid auto-reclosing, provided with a motor-operated spring mechanism, and shall comply with the related IEC standards/recommendations. The circuit breakers shall be equipped with an operation mechanism for DC power, motor operated and with a manual handle and the mechanism shall ensure uniform and positive closing and opening iii) Disconnectors and earthing switches Rated voltage Rated normal current Rated frequency Rated short-circuit withstand current Rated control voltage Rated insulation level 245 kV 1,600 A 50 Hz 40 kA, 1 sec. DC 110 C 6-76 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) a) b) Rated short-duration power-frequency withstand voltage (r.m.s. value) Rated lightning impulse withstand voltage (peak value) 395 kV 750 kV The disconnectors and earthing switch shall both be motor-operated and provided with a manual operating mechanism. Motor-operated disconnectors and earthing switch shall be designed with three-pole operation and the motor shall be operated on DC auxiliary power. iv) Current transformer Highest system voltage Rated frequency Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) Rated current ratio Accuracy classes v) 245 kV 50 Hz 395 kV 750 kV 3,000-1,600 A : 1 A 1,600-800 A : 1 A 5P20 for protection, Class 0.2 for metering Voltage transformer Highest system voltage Rated frequency Voltage ratio Accuracy classes Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) 245 kV 50 Hz 230 𝑘𝑉 110 𝑉 110 𝑉 : : √3 √3 √3 3P+0.2 395 kV 750 kV 2) Capacitor voltage transformer i) Type The 230 kV voltage transformers shall be single-phase, capacitor type and shall be designed in accordance with IEC 60044-5. ii) Ratings Highest system voltage Rated frequency 245 kV 50 Hz 230 𝑘𝑉 110 𝑉 110 𝑉 : : √3 √3 √3 Voltage ratio Accuracy classes Rated insulation level Rated short-duration power-frequency withstand a) voltage (r.m.s. value) Rated lightning impulse withstand voltage (peak b) value) 6-77 3P, 0.2 395 kV 750 kV Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 3) 196 kV Surge Arrester The 196 kV surge arresters shall be gapless, metal-oxide, outdoor and heavy duty type. The arresters shall be designed in accordance with IEC 60099-4 Rated voltage (r.m.s. value) Rated frequency Nominal discharge current Long-duration discharge class Pressure-relief current Rated insulation levels for insulators Rated short-duration power-frequency a) withstand voltage (r.m.s. value) Rated lightning impulse withstand voltage b) (peak value) 196 kV 50 Hz 10 kA Class 3 (Table-5, IEC 60099-4) 40 kA 395 kV 750 kV Hlawga Substation (1) Location and Current Situation 1) Location As shown in the following figure, the Hlawga S/S is located at latitude 16° 58’ 54” north and longitude 96° 07’ 35” east in the Mingaladon Township of Yangon City. Because the Hlawga substation is surrounded by a national park and military reservation, it is required to expand and/or augment the substation within the existing land. Source: JICA Survey Team Editing Google Earth Figure 6.6-10 Location Map of Hlawga Substation 2) Current situation The Hlawga substation has been operating since 1960 and consists of the following equipment: 230 kV Air insulated switchgear Single busbar scheme Three (3) transmission line bays to Shwedaung substation, Tharyagone substation and Thaketa substation Four (4) transformer bays 6-78 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Three (3) 230 kV Capacitor banks, 50 MVar x 2 and 20 MVar x 1 One (1) 230/66/11 kV main transformer Rated capacity: 125 MVA Three (3) 230/33/11 kV main transformer Rated capacity: 100 MVA 66 kV switchgear Single busbar scheme Three (3) transmission line feeders One (1) transformer feeder 33 kV switchgear Double busbar scheme Thirty (30) transmission line feeders Six (6) transformer feeders 11 kV switchgear Station service facilities Source: JICA Survey Team Figure 6.6-11 Photos of Current Hlawga Substation (2) Scope of Work for the Project In the Project, the existing 230 kV switchgear is upgraded to a GIS system, including expansion for the connection of four (4) circuits to the new Sar Ta Lin 500 kV substation in order to secure the reliability of equipment in future. In addition, the JICA Survey Team conducted the basic design in consideration of future expansion since there are several plans to extend the 230 kV facilities. In accordance with the discussion with DPTSC, the number of feeders in the GIS system constructed via the Project will be 17, as below. In this connection, the transmission line feeder to Tharyagone substation is not counted in the upgrade to GIS because the power flow of this line after the Project will be low. Transmission Line feeders 11 bays To Sar Ta Lin substation 4 bays To Thaketa substation 2 bays To Wartayar substation 2 bays To Shwedaung substation 1 bay Spare 2 bays Transformer feeders 4 bays 230/33/11 kV, 150 MVA transformer 3 bays 230/66/11 kV, 125 MVA transformer 1 bay Bus coupler 2 bays (3) Busbar Arrangement and Layout i) Busbar arrangement A single busbar arrangement is applied to the 230 kV switchgear in Hlawga substation, as shown in the following figure. Although 230 kV capacitor banks are installed for voltage control, it is assumed that these capacitor banks were necessary when Hlawga substation started operation due to there not 6-79 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) being enough supply lines. Therefore, our design considered removing these capacitor banks because it seems they will not be necessary for the Project’s implementation. (- 170.2 MW) (- 0.2 MW) ( -162.0 MW) (-7.4 MW) 230kV Shwedaung 230 kV, 50 MVAR Cap Bank (3) 150-300/5/5/5 A 500-1000/1/1/1/1/1 A GCB 1250 A 230 kV, 50 MVAR Cap Bank (1) 200-400/5/5/5 A GCB 3150 A 230kV Tharyargone 230 kV, 25 MVAR Cap Bank (2) 200-400/5/5/5 A GCB 3150 A 350-700/5/5/5 A 400-800/1/1/1 A GCB 1250 A GCB 3150 A GCB 3150 A Bus Section D/S 800A GCB 1250 A 300-600/1/1/1/1/1 A 250-500/5/5/5 A 66/0.11kV 250-500/5/5/5A 250-500/5/5/5A GCB 1250 A 200-400/1/1/1A GCB 3150 A GCB 3150 A GCB 1250 A 100 MVA 230/33/11 kV Bank (4) GCB 1250 A GCB 1250 A 200-400/1/ 125 MVA 230/66/11 kV Bank 100 MVA 230/33/11 kV Bank (1) 100 MVA 230/33/11 kV Bank (2) GCB 1250 A 200-400/1/ 1/1A 1A 2000/5/5/5 A 2000/5/5/5 A 1/ 2000/5/5/5 A 1000-2000/1/1/1/1/1 A GCB 1600 A GCB 2500 A GCB 2000 A GCB 2000 A (1260.0 A) (1304.0 A) (1117.0 A) Source: DPTSC Figure 6.6-12 Single Line Diagram of 230 kV Switchgear in Hlawga Substation A single line diagram after the Project is shown below. Because Hlawga substation doesn’t have enough space for the full installation of GIS with the required feeders above, we planned to conduct the upgrading work step by step as below: First step: Installation of GIS as far as possible in available space Second step: Changing the connection of the 230kV transmission line feeders in AIS which have been already prepared in GIS Third step: Removal of the non-used 230 kV AIS and installation of remaining feeders of GIS Fourth step: Changing the connection of remaining transmission feeder in AIS to GIS Spare Shwedaung SA SA M M M M M M GCB 1,250A 40kA M M M GCB 1,250A 40kA M M M M GCB 1,250A 40kA M M M GCB 1,250A 40kA M M M M M DS 2,000A, 40kA M M M M GCB 1,250A 40kA GCB 1,250A 40kA M M M DS+ES 1,250A 40kA DS+ES 1,250A 40kA M DS+ES 1,250A 40kA M M M GCB 1,250A 40kA GCB 1,250A 40kA M New 230 kV GIS (1st Phase) SA M M DS+ES 1,250A 40kA DS+ES 1,250A 40kA M Thaketa SS (1) SA SA M M DS+ES 1,250A 40kA M Thaketa SS (2) Sar Ta Lin (1) SA SA DS+ES 1,250A 40kA M Sar Ta Lin (2) Sar Ta Lin (3) SA DS+ES 1,250A 40kA M GCB 1,250A 40kA VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M Sar Ta Lin (4) SA DS+ES 1,250A 40kA M Wartayar (1) SA DS+ES 1,250A 40kA M M Wartayar (2) M M GCB 1,250A 40kA M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M M M 245kV BB1-B, 3,150A, 40kA 245kV BB1-A, 3,150A, 40kA 245kV BB2-B, 3,150A, 40kA 245kV BB2-A, 3,150A, 40kA DS+ES 2,000A, 40kA DS+ES 2,000A, 40kA M M M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M M M DS 2,000A, 40kA M M M M 2,000-1,000/1/1/1 A GCB 2,000A 40kA M M M M M M M SA M M SA M M SA GCB 2,000A 40kA M M M M M M 2,000-1,000/1/1/1 A M DS+ES 2,000A, 40kA DS+ES 2,000A, 40kA M M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M SA SA New 230 kV GIS (2nd Phase) 230/33/11 kV, 150MVA TR(4) 230/66/11 kV, 125MVA TR(3) 230/33/11 kV, 150MVA TR(2) 230/33/11 kV, 150MVA TR(1) Spare Source: JICA Survey Team Figure 6.6-13 Single Line Diagram of 230 kV Switchgear in Hlawga Substation after the Project 2) Layout As shown in Figure 6.6-14, when considering the connection of transmission lines currently planned to Wartayar substation with two circuits, East Dagon substation with one circuit and Thaketa substation with one circuit, there is only space of approx. 27 m x 35 m on the southern side of the 230 kV switchgear. Therefore, installation of GIS shall be separated into two phases. 6-80 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Source: JICA Survey Team from DPTSC Drawing Figure 6.6-14 Layout of 230 kV Switchgear in Hlawga Substation Before the Project Source: JICA Survey Team from DPTSC Drawing Figure 6.6-15 Layout of 230 kV Switchgear in Hlawga Substation After the Project The available space after connection of the current planned transmission lines as mentioned above will be approximately 27 m x 35 m. The JICA Survey Team judged that a 230 kV GIS with a double busbar scheme having six feeders, which requires 15.5 m x 7.4 m dimensions, can be installed in that available space. 6-81 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Source: JICA Survey Team Figure 6.6-16 Necessary Dimensions of 230 kV GIS with Double Busbar (Reference) Sar Ta Lin (2) SA M M M GCB 1,250A 40kA M M DS+ES 1,250A 40kA DS+ES 1,250A 40kA M DS+ES 1,250A 40kA M M M GCB 1,250A 40kA GCB 1,250A 40kA M New 230 kV GIS (1st Phase) SA M M DS+ES 1,250A 40kA M Thaketa SS (1) SA SA M M DS 2,000A, 40kA Thaketa SS (2) Sar Ta Lin (1) M M GCB 1,250A 40kA M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M M 245kV BB1-A, 3,150A, 40kA 245kV BB2-A, 3,150A, 40kA DS+ES 2,000A, 40kA DS+ES 2,000A, 40kA M M M M M 2,000-1,000/1/1/1 A M GCB 2,000A 40kA M M M M M M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M M SA SA 230/33/11 kV, 150MVA TR(1) DS (Existing) Existing 230 kV Busbar Source: JICA Survey Team Figure 6.6-17 Single Line Diagram of GIS in Hlawga Substation after 1st Phase (4) Equipment Procurement and Quantities In this Project, 230 kV GIS is installed in the Hlawga substation as an upgrade, instead of the existing AIS. The drawings in Appendix 6-4-5 and 6-4-6 show the basic design of Hlawga substation. - DWG No. MY-TLP3-HG-SLD_02 Single Line Diagram (Appendix 6-4-5) - DWG No. MY-TLP3-HG-LYT_01 Layout Drawing (Appendix 6-4-6) 1) i) Installation of 230 kV switchgear 230 kV GIS of double busbar scheme 6-82 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) The 230 kV GIS with double busbar scheme includes eleven (11) transmission line bays, four (4) transformer bays and two (2) bays for bus coupler. 230 kV GCB 17 sets 230 kV DS/ES 19 sets 230 kV DS 30 sets 230 kV CT 19 sets 500 kV VT 19 sets 196 kV SA 11 sets Connection with the existing busbar The associated gantry structures for the above system shall be supplied and installed. The associated steel support structures and foundations for the above equipment with all necessary connecting materials shall be supplied and installed. The connection work between the existing equipment, underground transmission lines and the above equipment shall be carried out and all necessary materials for the work such as cable head, connectors, accessories, power and control cables, etc. shall be supplied and installed. The above equipment shall be properly earthed with underground earthing mesh and all necessary materials such as earthing conductors shall be supplied. iii) Extension of protection and control panels Protection relay panel 230 kV transmission line protection relay panels 11 panels 230 kV transformer feeder protection relay panels 4 panels 230 kV busbar coupler protection relay panels 2 panels 230 kV GIS busbar protection relay panels 2 panels Control panel 230 kV transmission line control and synchronizing panel 11 panels 230 kV busbar connection control and synchronizing panel 2 panels SCADA System Modification of existing SCADA system The associated power and control cables with necessary accessories shall be supplied and installed. All necessary meters including ammeters, voltmeters and watt-hour meters, etc. shall be supplied and installed. 2) Civil and building work Cleaning, cutting, filling, leveling and compacting around new GIS Excavation and backfilling as required 3) Other work Spare parts for at least 5 years of operation Tools and erection accessories as required Complete documentation for operation and maintenance Training for DPTSC staff at manufacturer’s factory and at site Partial removal of existing AIS 6-83 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (5) Specifications of Major Equipment 1) Gas insulated switchgear i) Type The GIS shall be metal-enclosed, three-phase busbar and switchgear type, for outdoor use, and filled with SF6 insulation gas. ii) Circuit breaker Rated voltage Rated main busbar normal current Rated feeder normal current Rated frequency Rated short-circuit breaking current Rated interrupting time Rated operating sequence Rated closing operation voltage Rated control voltage Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) 245 kV 3,150 A 1,250 A 50 Hz 40 kA, 1 sec. less than or equal to 3 cycle O - 0.3 sec. - CO - 3 min. - CO DC 110 V DC 110 V 395 kV 750 kV The circuit breakers shall be suitable for single-pole tripping and rapid auto-reclosing, provided with a motor-operated spring mechanism, and shall comply with the related IEC standards/recommendations. The circuit breakers shall be equipped with an operation mechanism for DC and the mechanism shall ensure uniform and positive closing and opening. iii) Disconnectors and earthing switches Rated voltage Rated normal current Rated frequency Rated short-circuit withstand current Rated control voltage Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) 245 kV 1,250 A 50 Hz 40 kA, 1 sec. DC 110 C 395 kV 750 kV The disconnectors and earthing switch shall both be motor-operated and provided with a manual operating mechanism. Motor-operated disconnectors and earthing switch shall be designed with three-pole operation and the motor shall be operated on DC auxiliary power. iv) Current transformer Highest system voltage Rated frequency Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) Rated current ratio Accuracy classes 6-84 245 kV 50 Hz 395 kV 750 kV 2,000-1,000 A : 1 A (busbar) 1,600-800 A : 1 A (TL and busbar connection) 5P20 for protection, Class 0.2 for metering Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) v) Voltage transformer Highest system voltage Rated frequency Voltage ratio Accuracy classes Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) 245 kV 50 Hz 230 𝑘𝑉 110 𝑉 110 𝑉 : : √3 √3 √3 3P+0.2 395 kV 750 kV 2) 196kV Surge arrester The 196 kV surge arresters shall be gapless, metal-oxide, outdoor and heavy duty type. The arresters shall be designed in accordance with IEC 60099-4 Rated voltage (r.m.s. value) Rated frequency Nominal discharge current Long-duration discharge class Pressure-relief current Rated insulation levels for insulators Rated short-duration power-frequency a) withstand voltage (r.m.s. value) Rated lightning impulse withstand voltage b) (peak value) 196 kV 50 Hz 10 kA Class 3 (Table-5, IEC 60099-4) 40 kA 395 kV 750 kV Thaketa Substation (1) Location and Current Situation 1) Location As shown in the following figure, the Thaketa S/S is located at latitude 16° 48’ 42” north and longitude 96° 13’ 33” east in the Thaketa Township of Yangon City. Source: JICA Survey Team Editing Google Earth Figure 6.6-18 Location Map of Hlawga Substation 6-85 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 2) Current Situation Thaketa substation, including 230 kV equipment, is upgraded under ‘Urgent Rehabilitation and Upgrade Project Phase 1 (hereinafter referred to as “MY-P2 Project”)’ with a Japanese ODA Loan. Facility configuration after rehabilitation and upgrade in MY-P2 will be as follows: 230 kV Air insulated switchgear Single busbar scheme Two (2) transmission line bays to Hlawga substation and Thanlyin substation Four (4) transformer bays Two (2) 230/66/11 kV main transformers Rated capacity: 200 MVA Two (2) 230/33/11 kV main transformers Rated capacity: 100 MVA 66 kV switchgear Double busbar scheme Nineteen (19) transmission line feeders Two (2) transformer feeders Two (2) bus couplers 33 kV switchgear Double busbar scheme Thirteen (13) transmission line feeders two (2) transformer feeders One (1) bus coupler 11 kV switchgear Station service facilities Source: JICA Survey Team Figure 6.6-19 Photos of Current Hlawga Substation (2) Scope of Work for the Project In the Project, one bay of 230 kV switchgear including line protection panel in Thaketa substation is added, corresponding to augmentation of the existing 230 kV transmission line from one circuit to two circuits. Replacement of existing 230 kV switchgear for the transmission line feeder to Hlawga substation is not considered in the Project because this equipment will be rehabilitated in the MY-P2 Project. (3) Busbar Arrangement and Layout 1) Busbar arrangement The busbar arrangement of 230 kV AIS in Thaketa substation will be a single busbar arrangement, the same as the existing configuration, even after the Project. 6-86 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Source: MY-P2 Project Figure 6.6-20 Single Line Diagram of 230 kV Switchgear in Thaketa Substation Before the Project The single line diagram of 230 kV switchgear after the Project is shown in the following figure. The space for additional 230 kV switchgear to be installed in the Project can be secured on the west side of the existing transmission line bay to Hlawga substation. Hlawga (Additional) LA 10kA LT CVT DS 2000A CT 500-1000/1/1/1A GCB 2000A DS 2000A ES Source: JICA Survey Team Figure 6.6-21 Single Line Diagram of 230 kV Switchgear in Thaketa Substation After the Project 2) Layout As stated above, the additional 230 kV transmission line bay to Hlawga substation will be installed on the west side of the rehabilitated transmission line bay. 6-87 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Hlawga SS (2) SS Hlawga SS (1)East DagonThanlyn SS 66kV T/L DPTSC agreed that this space is used for construction of 230kV T/L bay for additional circuit to Hlawga Substation Source: MY-P2 Project Figure 6.6-22 Layout of 230 kV Switchgear in Thaketa Substation After the Project (4) Equipment Procurement and Quantities In the Project, one (1) additional 230 kV transmission line bay is installed in Thaketa substation. The drawing in Appendix-6-4-7 shows the basic design of Thaketa substation. - DWG No. MY-TLP3-TK-SLD_02 Single Line Diagram (Appendix 6-4-7) 1) i) Expansion of 230 kV switchgear 230 kV switchgear of single busbar arrangement 230 kV GCB 1 set 230 kV DS/ES 1 set 230 kV DS 1 set 230 kV CT 1 set 230 kV CVT 1 set 196 kV SA 1 set Line trap 2 sets The associated gantry structures for the above system shall be supplied and installed. The associated steel support structures and foundations for the above equipment with all necessary connecting materials shall be supplied and installed. The connection work between the dead-end towers, associated gantry structures and the above equipment shall be carried out and all necessary materials for the work such as power conductors, tension insulator sets, fittings, post insulators, connectors, accessories, power and control cables, etc. shall be supplied and installed. The above equipment shall be properly earthed with underground earthing mesh and all necessary materials such as earthing conductors shall be supplied. ii) Expansion of Control and Protection panel Protection relay panel 230 kV transmission line protection relay panels 1 panel Control panel 230 kV transmission line control and synchronizing panel 1 panel SCADA system Modification of existing SCADA system 6-88 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 2) The associated power and control cables with necessary accessories shall be supplied and installed. All necessary meters including ammeters, voltmeters and watt-hour meters, etc. shall be supplied and installed. Civil and building work Cleaning, cutting, filling, leveling and compacting around additional 230 kV switchgear 3) - Excavation and backfilling as required Other work Spare parts for at least 5 years of operation Tools and erection accessories as required Complete documentation for operation and maintenance (5) Specifications of Major Equipment 1) Air Insulated Switchgear i) Circuit Breaker The 230 kV circuit breakers shall be SF6 gas type, with a three-pole collective arrangement and for outdoor use. The circuit breakers shall be suitable for single-pole tripping and rapid autoreclosing, provided with a motor-operated spring mechanism, and shall comply with the related IEC standards/recommendations. Rated voltage Rated feeder normal current Rated frequency Rated short-circuit breaking current Rated interrupting time Rated operating sequence Rated closing operation voltage Rated control voltage Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) 230 kV 2,000 A 50 Hz 40 kA, 1 sec. less than or equal to 3 cycle O - 0.3 sec. - CO - 3 min. - CO DC 110 V DC 110 V 395 kV 750 kV The circuit breakers shall be equipped with an operation mechanism for DC power motor operated and manual handle, and the mechanism shall ensure uniform and positive closing and opening. ii) Disconnectors and earthing switches The 230 kV disconnectors shall be three-phase, two-column, rotary and center air break type with horizontal operation. Earthing switches shall be triple-pole, single-throw, vertical single break and manual three-phase group operation type. The disconnectors and earthing switches shall be suitable for outdoor use. The earthing switches shall be mounted on the disconnectors whenever necessary and where specified. Rated voltage Rated normal current Rated frequency Rated short-circuit withstand current Rated control voltage Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) 230 kV 2,000 A 50 Hz 40 kA, 1 sec. DC 110 C 395 kV 750 kV The disconnectors shall be motor-operated and provided with a manual operating mechanism with a hand crank. The earthing switch shall be provided with a manual operating mechanism. Motor-operated disconnectors shall be designed with three-pole operation and the motor shall be operated on DC power. iii) Current transformer 6-89 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) The 230 kV current transformers shall be single-phase, porcelain-insulated, oil-immersed and airtight sealed post insulator type, for outdoor use and shall be designed in accordance with IEC 600441. Highest system voltage Rated frequency Rated insulation level Rated short-duration power-frequency withstand voltage (r.m.s. a) value) b) Rated lightning impulse withstand voltage (peak value) Rated current ratio Accuracy classes 230 kV 50 Hz 750 kV 1,550 kV 500-1,000A : 1/1/1A) 5P20 for protection, Class 0.2 for metering iv) Capacitor Voltage transformer The 500 and 230 kV voltage transformers shall be single-phase, capacitor type and shall be designed in accordance with IEC 60044-5. Highest system voltage Rated frequency 245 kV 50 Hz 230 𝑘𝑉 110 𝑉 110 𝑉 : : √3 √3 √3 Voltage ratio Accuracy classes Rated insulation level Rated short-duration power-frequency withstand a) voltage (r.m.s. value) Rated lightning impulse withstand voltage (peak b) value) 3P+0.5 395 kV 750 kV v) 196 kV Surge Arresters The 196 kV surge arresters shall be gapless, metal-oxide, outdoor and heavy duty type. The arresters shall be designed in accordance with IEC 60099-4. Rated voltage (r.m.s. value) Rated frequency Nominal discharge current Long-duration discharge class Pressure-relief current Rated insulation levels for insulators Rated short-duration power-frequency withstand a) voltage (r.m.s. value) Rated lightning impulse withstand voltage (peak b) value) 6.7. 196 kV 50 Hz 10 kA Class 3 (Table-5, IEC 60099-4) 40 kA 395 kV 750 kV Work and Procurement Plan Work Plan (1) Procedure for Changing-over to GIS in Hlawga Substation As stated above, it is necessary to install GIS in 2 phases due to the limited current space for upgrading the existing 230 kV switchgear to GIS in Hlawga substation. In addition, since Hlawga substation plays an important role in supplying power to Yangon City, the changing-over work to GIS shall be conducted maintaining the operation of existing transmission lines as much as possible. Therefore, the JICA Survey Team proposes to change over to GIS in four (4) steps, as described below: 1) Step-1: Installation of GIS (1st Phase) in available space In Step-1, GIS with six (6) line feeders, of which one is for connection with the existing busbar, and one bus coupler shall be installed in the available space of approximately 27 m x 32 m. The details of GIS feeders to be installed in Step-1 are as below: Transmission line feeder To Sar Ta Lin substation x 2 To Thaketa substation including additional circuit x 2 Transformer feeder 230/33/11 kV 150 MVA main transformer x 1 Bus connection feeder to existing busbar x 1 6-90 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Bus coupler for GIS in Step-1 In Step-1, the JICA Survey Team also recommends constructing the cable trench in advance of the next step to lay the cable connecting from GIS to transformer, because the GIS in Hlawga substation is designed to connect by cable from GIS to each piece of equipment like transformers and overhead/underground transmission lines. 230 kV GIS by 7 feeders including bus coupler bay is installed in current available space. New cable trench for 230kV power cables shall be installed prior to Step-2. Installation of Cable Head Bushing at the existing CVT position Source: JICA Survey Team Figure 6.7-1 Layout of 230 kV Switchgear in Hlawga Substation (Step-1) SA SA SA M M M DS+ES 1,250A 40kA M M M M M GCB 1,250A 40kA M DS 2,000A, 40kA M DS+ES 1,250A 40kA DS+ES 1,250A 40kA M DS+ES 1,250A 40kA M M M GCB 1,250A 40kA GCB 1,250A 40kA M New 230 kV GIS (1st Phase) SA M M GCB 1,250A 40kA M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M M 245kV BB1-A, 3,150A, 40kA 245kV BB2-A, 3,150A, 40kA DS+ES 2,000A, 40kA DS+ES 2,000A, 40kA M M M M M GCB 2,000A 40kA M M M M M M M 2,000-1,000/1/1/1 A M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M SA SA Source: JICA Survey Team Figure 6.7-2 Single Line Diagram of 230 kV GIS in Hlawga Substation (Step-1) 2) Step 2: Changing the connection from GIS in Step-1 to Related Equipment In Step-2, the connection between GIS installed in Step-1 and related equipment shall be conducted. All transmission line feeders in GIS installed in Step-1 are connected by cables to Hlawga substation from underground transmission lines. For transformers, it is recommended to install the cable head 6-91 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) with bushing at the position of existing surge arresters and to connect the circuit from underground cables to overhead conductors. Furthermore, for the connection with the existing busbar, it is also recommended to install the cable head with bushing in from of disconnectors, currently for CVT, and to connect with the existing busbar for synchronization with the existing 230 kV system. After all changing-over has been completed, non-used existing AIS connected to Thaketa substation and Tharyagone substation shall be removed. Connecting power cables for transmission lines from 230kV GIS though cable trench Remove of existing AIS switchgear after connection the power cable from 230kV Connecting power cables for busbar and TR (1) from 230kV GIS though cable trench Installation of Cable Head Bushing at surge arrester position Source: JICA Survey Team Figure 6.7-3 Layout of 230 kV Switchgear in Hlawga Substation (Step-2) 6-92 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Sar Ta Lin (2) SA M M M GCB 1,250A 40kA M M DS+ES 1,250A 40kA DS+ES 1,250A 40kA M DS+ES 1,250A 40kA M M M GCB 1,250A 40kA GCB 1,250A 40kA M New 230 kV GIS (1st Phase) SA M M DS+ES 1,250A 40kA M Thaketa SS (1) SA SA M M DS 2,000A, 40kA Thaketa SS (2) Sar Ta Lin (1) M M GCB 1,250A 40kA M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M M 245kV BB1-A, 3,150A, 40kA 245kV BB2-A, 3,150A, 40kA DS+ES 2,000A, 40kA DS+ES 2,000A, 40kA M M M M M 2,000-1,000/1/1/1 A M GCB 2,000A 40kA M M M M M M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M M SA SA 230/33/11 kV, 150MVA TR(1) DS (Existing) Existing 230 kV Busbar Source: JICA Survey Team Figure 6.7-4 Single Line Diagram of 230 kV GIS in Hlawga Substation (Step-2) 3) Step-3: Installation of remaining GIS in 2nd Phase In Step-3, GIS with nine (9) feeder bays and one (1) bus coupler bay shall be installed at the location where the existing AIS was removed in Step-2. The details of GIS feeders to be installed in Step-3 are as below: Transmission line feeder To Sar Ta Lin substation x 2 To Wartayar substation x 2 Spare x 1 Transformer feeder 230/33/11 kV 150 MVA main transformer x 2 230/66/11 kV 150 MVA main transformer x 1 Bus coupler for GIS in Step-1 In Step-3, the JICA Survey Team recommends constructing the cable trench in advance of the next step to lay the cable connecting from GIS to the existing overhead transmission lines, to Watayar substation and Shwedaung substation. 6-93 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Expansion of 230kV GIS in AIS space after removal New cable trench for 230kV power cables shall be installed prior to Step-4. Source: JICA Survey Team Figure 6.7-5 Layout of 230 kV Switchgear in Hlawga Substation (Step-3) Spare Sar Ta Lin (4) SA SA M SA M M DS+ES 1,250A 40kA M M M M M M GCB 1,250A 40kA M M GCB 1,250A 40kA M M M DS+ES 1,250A 40kA M M GCB 1,250A 40kA M M M GCB 1,250A 40kA M M M M M DS 2,000A, 40kA M M M M M GCB 1,250A 40kA GCB 1,250A 40kA M M DS+ES 1,250A 40kA DS+ES 1,250A 40kA M DS+ES 1,250A 40kA M M M GCB 1,250A 40kA GCB 1,250A 40kA M New 230 kV GIS (1st Phase) SA M M DS+ES 1,250A 40kA DS+ES 1,250A 40kA M Thaketa SS (1) SA SA M M DS+ES 1,250A 40kA M Thaketa SS (2) Sar Ta Lin (1) SA SA M DS+ES 1,250A 40kA M GCB 1,250A 40kA SA M DS+ES 1,250A 40kA M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA SA Sar Ta Lin (2) Sar Ta Lin (3) M M GCB 1,250A 40kA M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M M M 245kV BB1-B, 3,150A, 40kA 245kV BB1-A, 3,150A, 40kA 245kV BB2-B, 3,150A, 40kA 245kV BB2-A, 3,150A, 40kA DS+ES 2,000A, 40kA DS+ES 2,000A, 40kA M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M M M M M M DS 2,000A, 40kA M M M GCB 2,000A 40kA M M M M M SA M M M 2,000-1,000/1/1/1 A M M M M M 2,000-1,000/1/1/1 A M DS+ES 2,000A, 40kA DS+ES 2,000A, 40kA M M M M M SA M SA GCB 2,000A 40kA M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M SA SA New 230 kV GIS (2nd Phase) 230/33/11 kV, 150MVA TR(1) DS (Existing) Existing 230 kV Busbar Source: JICA Survey Team Figure 6.7-6 Single Line Diagram of 230 kV GIS in Hlawga Substation (Step-3) 4) Step-4: Changing the connection from GIS in Step-3 to Related Equipment In Step-4, the connection between the GIS installed in Step-3 and related equipment shall be conducted. For transformers, it is recommended to install the cable head with bushing at the position of the existing surge arresters and to connect the circuit from underground cables to overhead conductors, the same as Step-2. For connection to overhead transmission lines, it is also recommended to install the cable head with bushing at the position of existing surge arresters and to connect with overhead transmission lines from the cable trench. After all changing-over has been completed, non-used existing AIS shall be removed. Then, the upgrade to GIS will be completed. 6-94 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Connecting power cables for transmission lines from 230kV GIS though cable trench Removal of existing AIS switchgear after connection of the power cable from 230kV GIS Installation of Cable Head Bushing at surge arrester position Connecting power cables for busbar and TR (2) to (4) from 230kV GIS though cable trench Source: JICA Survey Team Figure 6.7-7 Layout of 230 kV Switchgear in Hlawga Substation (Step-4) Spare Shwedaung SA SA M M M M M M GCB 1,250A 40kA M M M GCB 1,250A 40kA M M M M GCB 1,250A 40kA M M M GCB 1,250A 40kA M M M M M DS 2,000A, 40kA M M M M GCB 1,250A 40kA GCB 1,250A 40kA M M M DS+ES 1,250A 40kA DS+ES 1,250A 40kA M DS+ES 1,250A 40kA M M M GCB 1,250A 40kA GCB 1,250A 40kA M New 230 kV GIS (1st Phase) SA M M DS+ES 1,250A 40kA DS+ES 1,250A 40kA M Thaketa SS (1) SA SA M M DS+ES 1,250A 40kA M Thaketa SS (2) Sar Ta Lin (1) SA SA DS+ES 1,250A 40kA M Sar Ta Lin (2) Sar Ta Lin (3) SA DS+ES 1,250A 40kA M GCB 1,250A 40kA VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M Sar Ta Lin (4) SA DS+ES 1,250A 40kA M Wartayar (1) SA DS+ES 1,250A 40kA M M Wartayar (2) M M GCB 1,250A 40kA M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M M M 245kV BB1-B, 3,150A, 40kA 245kV BB1-A, 3,150A, 40kA 245kV BB2-B, 3,150A, 40kA 245kV BB2-A, 3,150A, 40kA DS+ES 2,000A, 40kA DS+ES 2,000A, 40kA M M M M M M M M DS 2,000A, 40kA M M M M 2,000-1,000/1/1/1 A GCB 2,000A 40kA M M M M M M SA M M M M M 2,000-1,000/1/1/1 A M M M DS+ES 2,000A, 40kA DS+ES 2,000A, 40kA M M M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M SA M M SA GCB 2,000A 40kA M VT 0.5 P: 230kV/ 3 S: 110V/ 3, 0.2, 30VA T: 110V/ 3, 3P, 30VA M M SA SA New 230 kV GIS (2nd Phase) 230/33/11 kV, 150MVA TR(4) 230/66/11 kV, 125MVA TR(3) 230/33/11 kV, 150MVA TR(2) 230/33/11 kV, 150MVA TR(1) Spare Source: JICA Survey Team Figure 6.7-8 Single Line Diagram of 230 kV GIS in Hlawga Substation (Step-4) 6-95 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 7. Project Implementation Policy 7.1. Safety of Construction Work Substation work under the Project includes extension of three existing substations. As most of the field work will be carried out under live conditions or tentative de-energized conditions at the existing facilities in the substations, the contractors for the Project should proceed carefully and always work paying full attention to the possibility of workers’ accidents, damage to the existing facilities, unscheduled system supply interruptions, etc. Transmission line work over a long distance will cover various kinds of operations, such as on high towers, in deep foundation excavated pits, with special stringing tools, or frequent travelling on major roads/small village roads, etc. There are many opportunities for fatal accidents and damage to public facilities. It has been observed that local workers take little care in such construction work, working without any safety tools to protect themselves. To prevent unexpected accidents, terms for the safety work should be specified in the contract documents. 7.2. COVID-19 Infection Prevention Measures It may be necessary to take the following measures during the construction period to prevent COVID-19 infections. - Wearing a mask. - Face shields. - Daily physical condition and hygiene management (habitual actions such as checking body temperature, checking physical condition, hand washing, and frequent disinfection). - If someone is not feeling well, ask him/her to leave the work area and take a rest or PCR test if necessary. - Maintain distance between each worker whenever possible. - Temperature checks and alcohol disinfection by guards at the guard gates of new substation construction sites and consulting offices (temperature checks and disinfection will have to be conducted several times, each time the workers move). - Reduction of meetings for all workers (limiting the number of people in meetings and communicating information through instructions from the work manager). - Separate work areas and the creation of a process schedule that avoids the proximity of each work area (limit the number of workers in the substation building and allocate them to outdoor work, etc.). - Installation of air cleaners in the field office. - Limit the number of people moving vehicles. Depending on the situation regarding the spread of infections, station a doctor at the construction site and conduct PCR testing at the site. 7.3. Contract Management In terms of contract management considering the particular conditions in the Project, the items to be taken into consideration are as below: (1) Force Majeure (referring to GC G.37 in “Plant”) As represented by the recent spread of COVID-19 infections, there are cases in which the contractor is forced to suspend work due to force majeure even in an ODA project. Although there are concerns that such suspension will have a significant impact on the completion time of the planned project, if the Employer (DPTSC in this case) forcibly demands that the contractor accelerate the construction work when the construction is resumed, it is necessary to have a common understanding that the project should be completed securing safety management and quality assurance, and allow an extension to the construction period as necessary. (2) Extension of Time for Completion (referring to GC H.40 in “Plant”) When the contract package is divided between transmission line and substation as in this project, 7-1 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) there is a concern that a delay in either one will affect the completion time of the other. At such time, it will be necessary to consider extending the construction period as needed, but it is necessary to sort out in advance who is responsible for such delay and the period of influence for each area of work. Therefore, it is important to coordinate the processes and work between each package during implementation of the Project. (3) Contractor’s Claim of Time for Completion (referring to GC I.44 in “Plant”) In the transmission line construction project, land negotiation and land acquisition will be carried out by the Employer. In this case, it is assumed that the land acquisition process will run into trouble during the construction of the transmission line, and the construction work will have to be interrupted. In the past, there was a case whereby the Employer was reluctant to charge the costs during the waiting period of the contractor. On the other hand, there was also a case whereby the contractors, who were unfamiliar with the contracts, did not charge for the costs themselves. Therefore, it is considered necessary to properly raise issues in order to carry out the project in a way that the contractor will not be disadvantaged. 7.4. Anti-graft Plan In order to realize transparent procurement in PQ and bidding, it is necessary to clarify the evaluation criteria on the premise that a quantitative evaluation is performed at each evaluation with consultant support. In addition, if any unnatural corrections are made to the bid evaluation report prepared and supported by the consultant, the consultant should discuss and confirm the content with the Employer, and consider discussing with JICA, if necessary. In order to carry out transparent procurement procedures, it is recommended to comply with transparent international standards such as the JICA guidelines. The JICA guidelines "Chapter 2: Guidelines for Procurement under Japanese ODA Loans, Section 1.06 Corrupt or Fraudulent Practices" are quoted below. Source: JICA 7.5. Actions concerning Gender Necessary actions concerning gender to be proposed in each phase of the implementation stage in this project are as below: 7-2 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (1) Before Construction Construction of the access road for work considering easy access for daily activities (drinking water, washing and farming etc.) (2) Construction Period Equal work and pay Employment promotion for women who want to work in cooking and material carrying work Preparation of toilets, shower rooms and bedrooms by gender at accommodation and site Arrangement of female supervisor at the site for female workers Technical transfer of maintenance work for female staff in new substation (3) After Construction Indirect improvement of the lives of women and children and their safety due to stable power supply by strengthening the power grid 7-3 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 8. Project Implementation System 8.1. Suggestions for Configuring the Project Implementation and Operation and Maintenance Systems Confirmation of Project Implementation System The MOEE organizational chart is shown in Figure 8.1-1. The Execution Agency (E/A) for the Project will be assigned to DPTSC, which is in charge of the construction of transmission and substation facilities above 132 kV, as per Phase 1 and Phase 2. Source: MOEE Figure 8.1-1 Organizational Chart of MOEE There are three departments in DPTSC, the management department, Power Transmission Projects Department (PTP) and Power System Department (PSD). Of these, PTP prepares the bidding documents and manages the project during construction. Figure 8.1-2 shows the organization of DPTSC. Director General Deputy Director General Administration Department Finance Department Material Planning Department Deputy Director General Deputy Director General Power Transmission Projects Department (PTP) Power System Department (PSD) Power Transmission Projects (Southern) Office Power Transmission Projects (Northern) Office Primary Substation Projects Transmission Line Source: MOEE Figure 8.1-2 Organizational Chart of DPTSC Capabilities of Each Department Related to the Project and its Role in the Project The capabilities and roles of each department shown in Figure 8.1-2 are described below. (1) 1) 2) Management Department Financial Department Management of budget and allocation to PTP Reporting to Ministry of Planning and Finance (MOPE) Confirmation of payment conditions Material Planning Department (Yangon and Nay Pyi Taw) Work for Custom Duties during Loading at port Storage of materials 8-1 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Confirmation of quantity of materials (2) Power Transmission Projects Department (PTP) 1) Project Implementation Branch Planning for fuel supply and construction materials for transmission line and substation projects Evaluation of cost estimations for transmission line and substation projects 2) Design and Planning Branch Preparation of design, BOQ and specifications and quality management Preparation of bidding documents Materials inspections Technical and price evaluation for bidding System analysis 3) Civil Branch Management of civil work in transmission line and substation projects Reporting on work progress Inspection of civil work in each project 4) Power Transmission Projects (Southern) Office Site management for transmission line and substation projects Management of quality and performance Coordination with region for land acquisition and reserved forest areas in project Reporting to MORR on environmental and social impacts (3) 1) 2) Power System Department (PSD) Transmission Line Branch Operation and maintenance for 230/132/66/33 kV transmission lines Procurement of necessary materials for operation and maintenance Primary Substation Branch Operation and maintenance of 230 kV and 132 kV primary substations Procurement of necessary materials for operation and maintenance Execution Department for each Component Based on the capabilities and roles of each department mentioned in Chapter 10.2.2, the execution department for the Project is shown in Table 8.1-1. Table 8.1-1 Execution Department for each Component in the Project Department Management PTP PSD Financial Material PIB Design Civil PTPO T/L S/S Branch X X Design X X X Bidding Documents X Bidding Evaluation X X Contract Negotiation X X Drawing Approval X X X X X Installation and Work Management X X Individual Inspection X Commissioning Test X X O&M Source: JICA Survey Team 8-2 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Organizational Structure of Executing Agency and main related Organizations (Organizational Chart) The organizational chart of the “Power System Department”, which maintains and manages the transmission and substation facilities, including the numbers of standard personnel, is shown below. Department of Power Transmission and System Control (DG) Power System Department (DDG) (Operation and Maintenance) Power Transmission Project (DDG) (Design and Implementation) System Planning (NPT) (Director) 57 National Control Center (NPT) (Director) 68 Load Dispatch Center (YGN) (Director) 68 Substation (NPT) (Director) System Protection and Testing (NPT) Section head: DD 45 System Protection and Testing (YGN) Section head: DD 45 Mobile Team (NPT) Section head: DD Primary Substation Substation head: AD Figure 8.1-3 20 58 Admin/Finance/Materials Planning (DDG) Transmission Line (NPT) (Director) 20 SCADA and communications (NPT), (Director) 60 Line Office (each regional) Office head: AD 137/office Total: 15 offices Organizational Chart of41/substation Power System Department Table 8.1-2 Standard Numbers of Personnel for each Organization System Planning (NPT) National Control Center (NPT) Load Dispatch Center (YGN) SCADA and communications (NPT) Substation (NPT) System Protection and Testing (NPT) System Protection and Testing (YGN) Mobile Team (NPT) Primary Substation Transmission Line (NPT) Line Office (each regional) Total (Standard) Total (Real) Number of personnel 57 68 68 60 20 45 45 58 2,829 20 2,055 5,325 3,994 Remarks 41 x 69 substations 137 x 15 offices 5,325 x 75% The actual working number of personnel is about 75% of the standard number, and the total number of working personnel who operate, maintain and manage the transmission and substation facilities is about 4,000. The standard number of personnel at the 500kV substation is assumed to be 67. <O&M in substations> All substations above 132kV are manned, and the standard number of personnel in each substation is 41 people. Since a new 500kV substation will be constructed in this project, it will be necessary to increase the number of new substation personnel by 67 people x 75%. In addition, in order to carry 8-3 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) out expansion work at three substations, it is considered necessary to increase the number of personnel at each substation by about two. <O&M for transmission facilities> The transmission line maintenance area is divided into 15 regions, as shown below, and transmission maintenance offices in each region carry out the maintenance. The standard number of personnel at each transmission line maintenance office is 137. New transmission lines will be constructed via this Project, but all lines are within the maintenance area of the Kamarnat Transmission Line Maintenance Office (the office outlined in red). For this reason, it is considered necessary to increase the number of new personnel for transmission line O&M by 34, equivalent to 25% of the standard 137 personnel at Kamarnat Transmission Line Maintenance Office. Figure 8.1-4 Each Transmission Line Maintenance Office’s Area of Operations The organization involved in the construction for this project is the “Power Transmission Project”. The organizational chart of the “Power Transmission Project” is shown below. 8-4 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Power Transmission Project (Deputy Director General) Project Planning & Design Branch Naypyitaw, (Director) 35 (DDG) Project Implementation Branch Naypyitaw, (Director) 30 Project Director Office (Northern) Naypyitaw, (Director) 45 Project Director Office (Southern) Naypyitaw, (Director) 45 PM Office (1), Shwesaryan (Deputy Director) 120 PM Office (1), Yangon (Deputy Director) 120 PM Office (2), Meiktila (Deputy Director) 120 PM Office (2), Tharyargone (Deputy Director) 120 PM Office (3), Mandalay (Deputy Director) 120 PM Office (3), Shwe Taung (Deputy Director) 120 Figure 8.1-5 Power Transmission Project (Civil) Branch Naypyitaw, (Director) 25 PM Office (Civil), (Northern) Naypyitaw, (Deputy Director) 60 PM Office (Civil), (Southern) Naypyitaw, (Deputy Director) 60 Organizational Chart of Power Transmission Project Project Implementation Unit (PMU) The following is a description of the project implementation structure for this project (Phase III) with reference to the structure of the currently operating project (Phase I). In Phase I, there were two substations, Meikhtila Substation and Taungoo Substation, and the Deputy Project Manager managed each substation. In Phase III, the project will be divided into substation and transmission lines according to the package. Since this project also includes the upgrade and expansion of 230kV, it is further divided into 500kV and 230kV. The underground transmission lines will be included in the 230 kV transmission section. The draft structure table is shown below. 8-5 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Organization Chart of Project Management Unit (PMU) for National Power Transmission Network Development Project Phase III (DRAFT) Project Director {Deputy Director General of Power Transmission Project Department (PTPD), DPTSC} Director General of DPTSC Director Material Planning Dept. Procurement Director Finance Dept. Project Implementation Dept. Deputy Project Director {Director of PTPD} Finance In charge of Substations (SS) Deputy Project Director {Director of PTPD} In charge of Transmission Lines (TL) In charge of 500kV TL In charge of Sar Ta Lin SS Deputy Project Director {Director of PTPD} Project Manager {Deputy Director} Deputy Project Manager 1 {Assistant Director} Deputy Project Director {Director of PTPD} Civil Dept. Project Planning Department (Dept.) Deputy Project Director {Director of PTPD} In charge of 230kV SS Project Manager {Deputy Director} Deputy Project Manager 2 {Assistant Director} Deputy Project Manager {Assistant Director} In charge of 230kV TL (including Underground TL) Project Manager {Deputy Director} Project Manager {Deputy Director} Project Manager {Deputy Director} Project Manager {Deputy Director} Deputy Project Manager {Assistant Director} Deputy Project Manager {Assistant Director} Deputy Project Manager {Assistant Director} Deputy Project Manager {Assistant Director} Assistant Director Assistant Director Assistant Director Assistant Director Figure 8.1-6 Phase III Implementation Structure (PMU) (Draft) 8-6 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 9. Evaluation of the Project 9.1. Quantitative Evaluation Benefits The following two ideas can be considered as benefits from the implementation of this project. (1) Reduction of Transmission Line Losses By comparing the power flow in 2030 with and without this project, the transmission line losses across the whole system are calculated as follows. In this calculation, thermal power generations in Yangon city are assumed to be the same. With this Project Without this Project (Source: JICA Survey Team) Figure 9.1-1 Comparison of the Power Flow in 2030 with and without this Project Thus, a comparison of the power transmission line losses for the two is as follows. Table 9.1-1 Comparison of Transmission Line Losses Outside Area Total with 109.6 MW 64.4 MW 174.0 MW without 127.3 MW 134.6 MW 261.9 MW Difference 87.9 MW (Source: JICA Survey Team) In the 2030 grid configuration, there will be an 87.9 MW transmission line loss difference during peak hours. If the power transmission losses are reduced, the difference will help curtail power generation at thermal power plants, and the implementation of this project will create benefits. (2) Reduction of Thermal Power Generation in Yangon city Without this project, transmission capacity from the northern hydropower and China, which have low power generation costs, to Yangon city will be limited due to a transmission capacity bottleneck. For this reason, contracts with rental thermal power plants in Yangon City, where power generation costs are high, must be extended. By implementing this project, it will be possible to increase the amount of power transmitted from the low-cost northern hydropower and China to Yangon city, and avoid extending contracts with rental thermal power plants. The following shows a comparison of power flow in 2030 with and without this project. In the case with this project, the contracts with rental thermal power plants have not been extended, so the supply capacities in Yangon city have decreased and the amount of power transmission from the north has increased. 9-1 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) With this Project Without this Project (Source: JICA Survey Team) Figure 9.1-2 Comparison of the Power Flow in 2030 with and without this Project (change in operating amount of thermal power in Yangon city) In the case without this project, part of the power flow from the north to the 500 kV PYG substation will be transmitted to the 230 kV Kamarnat substation, but most of the power will be transmitted once to the 500 kV HLT substation and electricity will be supplied to Yangon city from it. However, the 500 kV HLT substation receives 1,390 MW of electricity from the west and there is a limit on the transmission capacity that can be supplied to the 230 kV system from the 500 kV HLT substation. As a result, the power flow from the north into the 500 kV PYG substation must be limited. For this reason, there will be a shortage of power in the city and it will be necessary to increase the amount of power generated by thermal power plants, including rental thermal power plants in Yangon city, which have a high generation cost. Table 9.1-2 Comparison of Supply Capacity in 2030 5,555 MW Without this Project 3,723 MW 2,429 MW 4,199 MW 7,706 MW 278 MW 7,706 MW 216 MW With this Project Supply Demand From outside of Yangon city From thermal power plants in Yangon city Demand in substations Transmission losses etc. (Source: JICA Survey Team) By implementing this project, it will be possible to stop rental thermal power plants (Phase I, II: 1,770 MW). <Evaluation of the transmission line loss increase> As the power supply inside the city is stopped, and power is transmitted from the northern area, this increases the overall transmission line losses. In this case, the transmission line losses between the two are compared as follows, resulting in an increase in transmission line losses of 206.5 MW. Table 9.1-3 Comparison of Transmission Line Losses (change in operating amount of thermal power in Yangon city) Outside Area Total with 239.0 MW 229.4 MW 468.4 MW without 127.3 MW 134.6 MW 261.9 MW Difference - 206.5 MW (Source: JICA Survey Team) 9-2 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Based on the calculation method described in the previous section, the decrease in annual benefits (2020 value) due to the increase in transmission line losses is as follows. 206.5MW x 0.553 x 8760 x 185.0 Kyat/kWh = 185,064 million Kyat (123.4 million USD) <Overall benefits (2020 value)> The benefits are expected to be 505,718 million Kyat (337.1 million USD) annually in terms of fuel cost savings by stopping high fuel cost rental thermal power plants (1,770 MW) and switching to lowcost hydropower and imports from the neighboring countries. The increase in fuel costs due to an increase in transmission line losses results in an annual increase of 185,064 million Kyat (123.4 million USD). The shutdown of high-cost rental thermal power plants has a significant effect on reducing fuel costs, and the total benefits are 320,654 million Kyat (213.8 million USD) per year. Greater benefits can be expected than those that result only from the reduction of transmission line losses as described in the previous section. EIRR and FIRR (1) FIRR DPTSC, the implementing agency for the Project, is in charge of the construction and management of the transmission network as an internal agency of MOEE, but it does not receive revenue from the transmission business; MOEE earns revenue by selling electricity procured from power generators through DPTSC's transmission network. The revenue from the transmission business, i.e. DPTSC's business revenue, can be regarded as the revenue from the sale of MOEE's electricity minus the payment to the power producers. In general, the benefits of transmission lines are as follows, and the revenues of transmission projects are also derived from benefits 1 to 3. 1. Increase in revenue from sales of electricity due to increased power transmission 2. Reduction of power generation costs by reducing transmission losses 3. Reduction of power generation costs through procurement of cheaper power sources by changing the power supply composition (in this case, since it involves an increase or decrease in transmission losses, the increase or decrease in transmission losses is counted as an increase or decrease in power generation costs) In the FIRR calculation, the following approach was used to calculate the increase in business income. 1. Increase in revenue from sales of electricity due to increased power transmission. Considering the emergency power supply, the amount of electricity supplied to Yangon will not change with or without the implementation of the project, and the revenue from the sale of electricity by 1 will not change. 2. Reduction of power generation costs by reducing transmission losses. Transmission losses will be reduced by the implementation of the project, resulting in higher financial revenues, as payments to the power producers will be reduced. 3. Reduction of power generation costs through procurement of cheaper power sources by changing the power supply composition. This effect is excluded from the increase in financial revenue, as the scope of implementation by the project to achieve this effect is considered to be limited. Therefore, the only change in financial revenue due to the implementation of the project is the reduction of payments to the power generation companies due to the reduction of transmission losses in 2. FIRR is calculated as follows by simply evaluating the transmission line loss reduction effect as the benefit gained from implementing this project. FIRR = 5.6%. 9-3 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Table 9.1-4 FIRR Calculation Sheet 2020 FIRR (Base Case) NPV B/C Year Activities 5.6% -163.8 0.6 Financial Costs (C) Construction Work O&M costs Maintenance Personnel million USD Total Costs (C) Financial Benefit (B) Net (B) - (C) -6 2020 0.00 0.00 0.00 0.00 -5 2021 6.31 6.31 0.00 (6.31) -4 2022 -3 2023 -2 -1 94.09 94.09 0.00 (94.09) 154.73 154.73 0.00 (154.73) 2024 188.33 188.33 0.00 (188.33) 2025 157.52 157.52 0.00 (157.52) 0 2026 32.51 32.51 0.00 (32.51) 1 2027 1.70 1.14 2.84 52.52 49.68 2 2028 1.70 1.14 2.84 52.52 49.68 3 2029 1.70 1.14 2.84 52.52 49.68 4 2030 1.70 1.14 2.84 52.52 49.68 5 2031 1.70 1.14 2.84 52.52 49.68 6 2032 1.70 1.14 2.84 52.52 49.68 7 2033 1.70 1.14 2.84 52.52 49.68 8 2034 1.70 1.14 2.84 52.52 49.68 9 2035 1.70 1.14 2.84 52.52 49.68 10 2036 1.70 1.14 2.84 52.52 49.68 11 2037 1.70 1.14 2.84 52.52 49.68 12 2038 1.70 1.14 2.84 52.52 49.68 13 2039 1.70 1.14 2.84 52.52 49.68 14 2040 1.70 1.14 2.84 52.52 49.68 15 2041 1.70 1.14 2.84 52.52 49.68 16 2042 1.70 1.14 2.84 52.52 49.68 17 2043 1.70 1.14 2.84 52.52 49.68 18 2044 1.70 1.14 2.84 52.52 49.68 19 2045 1.70 1.14 2.84 52.52 49.68 20 2046 1.70 1.14 2.84 52.52 49.68 21 2047 1.70 1.14 2.84 52.52 49.68 22 2048 1.70 1.14 2.84 52.52 49.68 23 2049 1.70 1.14 2.84 52.52 49.68 24 2050 1.70 1.14 2.84 52.52 49.68 25 2051 1.70 1.14 2.84 52.52 49.68 26 2052 1.70 1.14 2.84 52.52 49.68 27 2053 1.70 1.14 2.84 52.52 49.68 28 2054 1.70 1.14 2.84 52.52 49.68 29 2055 1.70 1.14 2.84 52.52 49.68 30 2056 1.70 1.14 2.84 52.52 Construction Operation NPV 417.86 (at 10% Discount Rate) 9-4 254.05 49.68 -163.81 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (2) EIRR The EIRR calculation takes into account the change in the power supply mix, i.e., cheaper power supply procurement by avoiding the extension of emergency power supply contracts, and the associated increase in transmission losses; the Local Currency portion is considered non-tradable goods, and the project cost converted from the price of the non-tradable goods by SFC is used. In terms of the benefits gained from implementing this project, the EIRR is calculated as follows by evaluating the fuel cost reduction effect of avoiding the extension of contracts with rental thermal power plants in Yangon City. The EIRR is 21.4%. Table 9.1-5 EIRR Calculation Sheet 2020 FIRR (Base Case) NPV B/C Year Activities 21.4% 1,988.4 75.3 Economical Costs (C) Construction Work O&M costs Maintenance Personnel million USD Total Costs (C) Economic Benefit (B) Net (B) - (C) -6 2020 0.00 0.00 0.00 0.00 -5 2021 6.18 6.18 0.00 (6.18) -4 2022 -3 2023 -2 -1 92.61 92.61 0.00 (92.61) 152.47 152.47 0.00 (152.47) 2024 185.49 185.49 0.00 (185.49) 2025 155.08 155.08 0.00 (155.08) 0 2026 32.00 32.00 0.00 1 2027 1.70 1.14 2.84 213.77 210.93 2 2028 1.70 1.14 2.84 213.77 210.93 3 2029 1.70 1.14 2.84 213.77 210.93 4 2030 1.70 1.14 2.84 213.77 210.93 5 2031 1.70 1.14 2.84 213.77 210.93 6 2032 1.70 1.14 2.84 213.77 210.93 7 2033 1.70 1.14 2.84 213.77 210.93 8 2034 1.70 1.14 2.84 213.77 210.93 9 2035 1.70 1.14 2.84 213.77 210.93 10 2036 1.70 1.14 2.84 213.77 210.93 11 2037 1.70 1.14 2.84 213.77 210.93 12 2038 1.70 1.14 2.84 213.77 210.93 13 2039 1.70 1.14 2.84 213.77 210.93 14 2040 1.70 1.14 2.84 213.77 210.93 15 2041 1.70 1.14 2.84 213.77 210.93 16 2042 1.70 1.14 2.84 213.77 210.93 17 2043 1.70 1.14 2.84 213.77 210.93 18 2044 1.70 1.14 2.84 213.77 210.93 19 2045 1.70 1.14 2.84 213.77 210.93 20 2046 1.70 1.14 2.84 213.77 210.93 21 2047 1.70 1.14 2.84 213.77 210.93 22 2048 1.70 1.14 2.84 213.77 210.93 23 2049 1.70 1.14 2.84 213.77 210.93 24 2050 1.70 1.14 2.84 213.77 210.93 25 2051 1.70 1.14 2.84 213.77 210.93 26 2052 1.70 1.14 2.84 213.77 210.93 27 2053 1.70 1.14 2.84 213.77 210.93 28 2054 1.70 1.14 2.84 213.77 210.93 29 2055 1.70 1.14 2.84 213.77 210.93 30 2056 1.70 1.14 2.84 213.77 210.93 Construction Operation NPV 26.77 (at 10% Discount Rate) 9-5 (32.00) 2015.19 1988.41 (Source: JICA Survey Team) Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) In the above calculation, the unit price for power received from the neighboring countries is assumed to be 80% of rental thermal power plants, but if it is assumed to be 90% of rental thermal power plants, the benefit will be reduced to 99.15 million USD, and EIRR = 18.1%. 9.2. Reducing Greenhouse Gas Emissions The implementation of the project is expected to reduce greenhouse gas emissions from the fuel combustion of thermal power because implementing the project will make it possible to avoid the extension of thermal power contracts for the emergency power supply in Yangon City, and will enable the supply of power to Yangon City through hydropower in the north and transmission from other countries. However, the power supply from inside the city will be shut down and power will come from the north, increasing the overall transmission losses. The greenhouse gas emission reduction amount was calculated by subtracting the increase in emissions due to increased transmission losses from the greenhouse gas emission reduction by replacing the electricity supplied by emergency power sources in Yangon before the project with hydropower sources in the north and power sources from other countries after the project. The format of the JICA Support Tool for Change Measures was used as the calculation tool. The amounts of power supply and transmission losses used for the comparison before and after the implementation of the project were calculated in accordance with the previous section. The CO2 reductions were calculated under the following conditions. Electricity will be supplied by an emergency power source before the project is implemented (natural gas with an emission factor of 56,100 kg/TJ (Appendix 2 of the Support Tool) assuming 35% efficiency) After the implementation of the project, the following power sources will be used to supply electricity 3 months of rainy season: supply from northern hydropower, and neighboring countries' hydropower 9 months of dry season: supplied by neighboring countries (emission factor for grid electricity is 672 g-CO2/kWh, which is the Asian average) The result was a reduction of 615,703 tCO2/year. The calculation table is shown in Table 9.2-1. 9-6 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Table 9.2-1 -Calculation Table for Greenhouse Gas Emissions Reduction 12. Transmission System Efficiency Improvement Project Name National Power Transmission Network Development Project Phase III Country Myanmar Emission Reduction Value Unit ERy Emission reduction 615,703 tCO2/year BEy Baseline emissions 6,441,799 tCO2/year PEy Project emissions 5,826,096 tCO2/year Input *Input only orange cell Parameter Description Value Amount of electricity from power sources (emergency generators) in base line in year y Unit 11,163.7 GWh/year Amount of electricity from power sources (hydropower) during wet seasons in the project in year y 2,790.9 GWh/year Amount of electricity from power sources (from other countries) during dry seasons in the project in year y 8,372.8 GWh/year Increase in transmission line losses in the project in year y 1,000.3 GWh/year Calculations Value Emission reduction Unit 615,703 tCO2/year Baseline emission 6,441,799 tCO2/year Amount of electricity from power sources in base line in year y CO2 emission factor of electricity (emergency generators) Power generation effiency of emergency generators Effective CO2 Emission Factor (kg/TJ) Natural Gas Project emission 11,163.7 0.577 35% 56,100.0 5,826,096 GWh/year tCO2/MWh 2,790.9 0.0 8,372.8 0.672 1,000.3 0.266 GWh/year tCO2/MWh GWh/year tCO2/MWh GWh/year tCO2/MWh Amount of electricity from power sources during wet seasons in the project in year y CO2 emission factor of electricity (hydro) Amount of electricity from power sources during dry seasons in the project in year y CO2 emission factor of electricity (other countries Asia) Increase in transmission line losses in the project in year y CO2 emission factor of loss kg/TJ tCO2/year Table Default Values Effective CO2 Emission Factor (kg/TJ) (Natural Gas) Power generation effiency of emergency generators CO2 emission factor of electricity (Hydropower) CO2 emission factor of electricity (From other countries) CO2 emission factor of electricity (Myanmar) 56,100 0.35 0 0.672 0.266 kg/TJ tCO2/MWh tCO2/MWh tCO2/MWh (Source: Format of the JICA Climate Change Support Tool) 9-7 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 9.3. Performance Effectiveness Indicators (1) Performance Effectiveness Indicators The performance indicators are set as the availability (%) of the new 500 kV transmission lines, 230 kV transmission lines, and 500 kV substations to be built under the Project at maximum load and the amount of power sent at the end of transmission lines in 2028, after the Project starts operation. The performance effectiveness indicators are shown in Table 9-1. Table 9-1Operational Effectiveness Indicators Number of lines/units Rated capacity of equipment (MVA) 2028 Maximum load (MW) 500 kV Pharyargyii Sartalin transmission line 500 kV Sartalin Substation 500 kV/230 kV Transformer 500 kV Sartalin Substation - 230 kV Hlawga Substation 500 kV Sartalin Substation - 230 kV East Dagon Substation 230 kV Hlawga Substation - 230 kV Thaketa Substation 2 4,420 1,451 33%. Target value 2 Amount of electricity at transmission end (GWh/year) 7,888 3 1,500 1,445 96%. 7,862 i 914 61%. 4,844 2 1,391 333 24%. 1,712 2 777 ii 517 67%. 2,400 4 1,492 Target value 1 Operating rate at maximum load (2) Calculation of Each Indicator Each indicator was calculated according to the results of the power flow calculation for 2028 shown in Figure 9.3-1 Power Flow Diagram in 2028 after completion of . The power factor is assumed to be 90%. During peak demand Off-peak demand Figure 9.3-1 Power Flow Diagram in 2028 after completion of Phase III The operating rate of facilities at maximum load is given by Operating rate at maximum load (%) = Maximum load (MW) / Rated capacity (MVA) x Power Factor Note that for the sections between the 500 kV Sartalin substation and 230 kV Hlawga substation, 9-8 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) and between the 230 kV Hlawga substation and 230 kV Thaketa substation, the capacity of these sections is equal to the capacity of the underground line section because the capacity of the underground line section is smaller than the capacity of the overhead line section. The amount of energy sent at the end of the transmission line (GWh/year) was estimated using the following method. Off-peak demand was set at 50% of maximum demand. The annual amount of energy transmitted was the average of the energy transmitted during maximum and off-peak demand. The power generated in Yangon during off-peak demand was assumed to be the same as the power generated during peak demand. The reasons are given below. In the power supply operation for one day in April 2019 shown in Figure 9.3-2, thermal power plants have hardly changed their output, and the supply-demand balance is maintained by adjusting the output of hydroelectric power plants. For this reason, it was assumed that there would be no adjustment of thermal power output during the day or night. In the plans for this project, the thermal power plants in Yangon are almost at full output, and yet the project is considering transmitting the necessary power from the north. On the other hand, during the rainy season, the amount of electricity that can be generated by the hydroelectric power plants is higher, so there is a possibility that surplus electricity from the north can be transmitted to Yangon, thereby reducing the amount of electricity generated by the thermal power plants. However, the appropriateness of the additional transmission lines needed to curb the output of the thermal power plants in Yangon during the rainy season is considered to be something to be explored after the implementation of this project, which is urgently needed to ensure stable supply in Yangon. The appropriateness of these additional transmission lines will be considered by taking into account the type of contracts with thermal power plant IPPs (feed-in tariff, etc.), the development plans for hydropower plants, the amount of electricity that can be generated during the wet and dry seasons, and the costs of generation and transmission lines. For this reason, in this project, the same amount of power generated was assumed for the wet and dry seasons without anticipating any change in the amount of power generated by thermal power plants during the wet and dry seasons. Therefore, it was assumed that the power generated in Yangon would be the same during both peak and off-peak demand. Figure 9.3-2 One-day Operation of Power Generation in April 2019 9-9 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (3) Voltage Drops and Transmission Loss Indexing As described in 1.5.4, the voltage in the city center tends to decrease in the Yangon City 230 kV system, and power capacitors need to be installed to improve voltage drops. In order to improve the voltage drop issue, power capacitors should be installed on the load side of Yangon's 230 kV system at Thaketa, Ahlone, and Thanlyin, or on the lower 66 kV and 33 kV systems. However, the load power factor assumed in this planning study is 90%, which is an approximate setting, and the distribution of grid voltage can only be approximately calculated. Therefore, in order to study the effective amount and location of power capacitors to be installed, it is considered that this matter should be studied in detail by monitoring the load power factor, power flow, and voltage during actual operation after the completion of Phase III. Therefore, voltage drop was not adopted as an indicator for this project. After the completion of Phase II, it will be necessary to investigate the degrees of voltage drops, the magnitudes of power flows in the transmission lines, the magnitudes of loads in the substations, the power factors of the loads, and the power generated, to study the locations and the capacities of the capacitors to be installed. It should be noted that power capacitors can be installed within about two years of planning. 9-10 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 10. Preliminary Data Collection Survey for Plan for Power Grid Extension to Mawlamyaing 10.1. Outline of the Survey A preliminary data collection survey was conducted for the Yangon region, particularly on the expansion of the bulk power transmission lines between Yangon and Mawlamyaing. This chapter presents an overview of the survey. The results will be reported separately in February 2021. In Myanmar, there is an urgent need to improve the bulk power transmission lines in the northern, western and southeastern regions of the country, with Yangon at the center. The 500 kV system from the north to the Yangon area is already under construction in Phase I/II, and there is an urgent need to improve the power transmission network to the southeast. Mawlamyaing is a city located about 300 km southeast of Yangon, with plans for an industrial park in the vicinity. A power plant is planned in the Dawei district (Kanbouk) in the south. In addition, an interconnected transmission line from Thailand is planned at Myawaddy, on the border with Thailand, northeast of Mawlamyaing. Since there is only a single circuit line of 230 kV between Mawlamyaing and Pharyargyi, which does not meet the N-1 requirement, and the load is getting heavier, a new 230 kV transmission line with double circuits is currently planned to be built by DPTSC. In addition, a 230 kV transmission line with double circuits between Mawlamyaing and Myawaddy was recently constructed. 10.2. Data Collection on System Configuration Current Status and Plans for System Configuration (1) Current Status of Grid Structure The system diagram from Pharyargyi to the southeast, obtained from DPTSC, is shown in Figure 10.2-1. 500 kV and 230 kV systems are planned from Pharyargyi to the southeast. Source: left: obtained from DPTSC, November 2018; right: prepared by the JICA Survey Team. Figure 10.2-1 System Map of the Southeast from Pharyargyi 10-1 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Thaephyu 2 x 265/35 sqmm 40.28 miles Lawpita Taungoo Pyu 1 x 795 MCM 60.55 miles Kun Tharyargone Shewtaung 2 x 605 MCM 58.8 miles (336.4 MCM per side?) 2 x 605 MCM 65.39 miles Phryargyi Minhla 2 x 605 MCM 62.96 miles Kamarnat Sittaung 230/33/11 kV 50 MVA 2 x 605 MCM2 x 605 MCM Myaungtagar 19.14 miles 39.97 miles 2 x 605 MCM 36.6 miles 1 x 795 MCM 94.01 miles Hlawga East Dagon 1 x 795 MCM 13.85 miles Thaketa 2 x 605 MCM 7.7 miles 2 x 605 MCM 60.25 miles Thaton. 2 x 605 MCM 2 x 605 MCM 61 miles (to 50.95 MW 49.77 miles Myawaddy. Thanlyin) Mawlamyaing 230/66/11 kV 150 MVA (->2x100) Thilawa 2 x 605 MCM 8.4 miles (Thilawa 1 x 795 MCM In/Out) 2 x 605 MCM 12.4 miles (Dagon (East) In/Out) Myanmar Lighting IPP 230 MW 1,230 MW Kanbouk. Thanlyin Source: Prepared by JICA Survey Team Figure 10.2-2 System Configuration in Eastern Yangon and Southeast from Pharyargyi (2) Consideration of Power System Planning The power flows for each section of the system from Pharyargyi to the southeast were estimated and the adequacy of the system plan was discussed. (3) Assumptions regarding Power Demand Based on the power demand forecast in the JICA Master Plan, the maximum demand at the district level was assumed based on the maximum demand forecast for the region and the population ratio. 10-2 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) (4) Existing Power Supply The existing power sources connected to the transmission system are three units of EPGE's Thaton generators, with a total capacity of 50.95 MW, and Myanmar Lighting Company's IPP, with a total capacity of 230 MW. New Power Plant Construction Plans MOEE is planning to build an LNG-fired power plant in Kanbauk (Dawei district). It was noted that the power supply envisioned from DPTSC to Kanbouk is uncertain and therefore does not need to be considered in this planning survey. Therefore, this power source will not be considered in this survey. There are plans for an interconnection with Thailand. Approximate Current Forecast Approximate power flows were estimated. The direction and magnitude of the power flows vary greatly depending on the power outputs of power sources and the amount of power demand. Based on the approximate stability estimates, it is considered that stable transmission of electricity may be difficult in some cases, depending on the power outputs of the power sources and the amount of power demand, with the existing single circuit of a 230 kV line and the double circuits of a 230 kV line. For this reason, a new 500 kV transmission line with double circuits is to be constructed, and the following system configuration is considered. Existing: 230 kV 1cct Kamarnat - Mawlamyaing New: 230 kV 2cct Kamarnat - Mawlamyaing New: 500 kV 2cct Pharyargyi - Mawlamyaing Thailand Phryargyi Myawaddy 500 kV 230 kV Kamarnat Sittaung Thaton . 50 MW Mawlamyine 230 MW Source: Prepared by JICA research team Figure 10.2-3 Recommended System Configuration In the future, it will be necessary to examine the amount of power that can be transmitted in detail by calculating the stability of the system, including the interconnection with Thailand. 10-3 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 10.3. Data Collection on New Power Transmission Lines Conceptual Study of Transmission Line Routes (1) Methodology of the Study on Power Transmission Line Routes The study on the 500 kV transmission line route between Pharyargyi and Mawlamyaing, which is the target of this project, was conducted via desk research using the latest map data, such as Google Earth. (2) Location of Substations The substations to be included in this project are the 500 kV Pharyargyi substation, currently under construction, and the new 500 kV Mawlamyaing substation. Source: Prepared by JICA research team from Google Earth Figure 10.3-1 500 kV Mawlamyaing Substation (3) Transmission Line Routes Overview of Transmission Line Routes A general overview of the 500 kV transmission line route between Pharyargyi and Mawlamyaing, which is the target of this project, is shown in Figure 10.3-2. The route is based on the south of the existing 230 kV Kamarnat-Thaton-Mawlamyaing transmission line route, which has the shortest distance between Pyaryargyi and Mawlamyaing and easy access roads during construction. In addition, the planned future 230 kV Kamarnat-Thaton-Mawlamyaing transmission line route was also considered. The existing 230 kV Kamarnat-Thaton-Mawlamyaing transmission line route is in the north, between Mawlamyaing and the Thaton substation. In this project, the shortest route to the north of the conservation forests around Kamarnat is proposed. 10-4 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) ; New 500 kV Pharyargyii―Mawlamyaing (210km) ; Existing 230 kV Kamarnut―Thaton― Mawlamyaing ; New 230 kV Karmanat―Pharyargyii ource: Prepared by JICA research team from Google Earth Figure 10.3-2 Overview of the Transmission Line Routes Figure 10.3-3 Status of Conservation Forests and Other Areas near Transmission Line Routes 10-5 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) 10.4. Data Collection for Construction and Expansion of Substations 500 kV Pharyargy Phayagyi substation is under construction in the Phase II Project and 500 kV H-GIS switchgear for Mawlamyaing’s new 500 kV Substation, and auxiliary equipment, such as transmission line protection panels, are also being installed in the Phase II Project. Therefore, it is not necessary to install new equipment for 500 kV transmission lines to Mawlamyaing substation and the scope of work in the new project will cover only the connection of 500 kV transmission lines to the gantry structures in Phayagyi substation. North Side Mawlamyaing S/S Sar Ta Lin S/S 500kV Switchyard 230kV Switchyard Figure 10.4-1 Layout of Phayagyi Substation under Phase II Project 500 kV Mawlamyaing (1) Location of Substation It is necessary to secure the space for the new 500 kV substation at the northern side of the existing Mawlamyaing 230 kV substation and construct the new 500kV substation in that space, because the existing Mawlamyaing 230 kV substation doesn’t have sufficient space for expansion as a 500 kV substation. (2) Equipment configuration The new Mawlamyaing 500kV substation will use H-GIS with a one and a half circuit breaker system for 500 kV switchgear and AIS with a double busbar system for 230 kV switchgear, in reference to similar projects like Phase I and Phase II of the JICA project, subject to securing enough space for the construction of H-GIS. The major equipment in the new Mawlamyaing 500 kV substation is shown in the following table: 10-6 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Table 10.4-1 Equipment Configuration of New Mawlamyaing 500kV Substation Equipment name 500kV Switchgear (H-GIS) 230kV switchgear (AIS) 500/230kV transformer On-site power supply Protection and control equipment Overview 2 feeders for Pyaji substation x 2 feeders for Daway Power line spare x 4 feeders 500/230kV transformer connection x 2 feeders 2 feeders for 230kV substations in Mauramyne 2 feeders for Myawaddy Substation Power line spare x 4 feeders 500/230kV transformer connection x 2 feeders Main line contact x 1 Outdoor installation, single phase, oil type, ONAF/ONAN cooling system 166.7 MVA/phase x 7 400/230V AC panel, 110V DC panel, 48V DC panel, DC battery, emergency generator, internal transformer (33/0.4kV) SCADA, power line protection equipment, transformer protection equipment, etc. Remarks 1+1/2CB method dual bus bar system OLTC included 10.5. Environmental and Social Considerations Environmental Considerations Strategy of the study is described below. The results of the study will be reported sepaetely following further technical examination in Feburary 2021. (1) Confirmation of the Situation regarding Protected Areas, Key Biodiversity Area and Areas Surrounding the Planned Transmission Line Route Status of Protected Areas and Reserved Forests There are no protected areas and or Key Biodiversity Areas (KBAs) on the planned transmission line route from Phayargy to Mawlamyaing, but there is one reserved forest, Kalama Taung Reserved Forestassumed to be a commercial conservation forest (e.g. rubber plantation), judging by satellite images, as shown in Table 10.5-1. According to a Forest officer ofthere, Kalama Taung Reserved ForesForest, it is defined as a Reserved Forest for 3 purposes;: (a) commercial reserved forest; (b) local supply reserved forest; (c) watershed or catchments protection reserved forest as described in the Forest Law (2018). Also, it is It was also confirmed that this Reserved Forest can be modified by following the necessary procedure. In addition, although the actual area of influence on the environment differs depending on the impact item, protected areas/reserved forests that exist within a range of 10 km from the project target area were identified to secure a safe margin for this survey. 10-7 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) Source: Forest Department of related townships (2019); Protected areas and Reserved Forests Figure 10.5-1 Protected Areas/KBA (left) and Reserved Forests (right) near the Project Site Status of Cultural Heritage Sites Surrounding the Project Site There are no special cultural heritage sites on the planned transmission line route from Pharyargyi to Mawlamyaing. (2) Outline of Environmental and Social ConsideratoinsCategories required in accordance with the JICA Guidelines for Environmental and Social Considerations Procedures in line with the EIA Procedure (2015) in Myanmar In accordance with the EIA Procedures, stipulated in December 2015, as prepared by the Ministry of Environmental Conservation and Forestry (the former name of the Ministry of Natural Resources and Environmental Conservation (MONREC)), the Project can be categorized as “EIA or IEE is required”, as shown in Table 10.5-1. Table 10.5-1 No. EIA/IEE/EMP Requirements related to the Project in Myanmar Type of Investment Project ENERGY SECTOR DEVELOPMENT 27 Electrical Power Transmission Lines ≥ 230 kV Size of Project which requires IEE All sizes Size of Project which requires EIA Notes All activities where the Ministry requires that the Project shall undergo EIA - * EIA: Environmental Impact Assessment IEE: Initial Environmental Examination Source: Extract from EIA Procedures (2015) Procedures in line with the JICA Guidelines for Environmental and Social Considerations There are descriptions concerning the illustrative list of sensitive sectors, characteristics, and areas in Appendix 3 of the JICA Guidelines for Environmental and Social Considerations (2015), and the Project was compared/summarized with these descriptions. With regard to the number of Project10-8 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) affected people during the construction of the new substations and the development of transmission lines, the relocation of residents, businesses, and commercial activities due to land acquisition would be avoided to the extent possible. Therefore, it is considered that it does not fall under sensitive sectors, characteristics, and areas in Appendix 3 of the JICA Guidelines for Environmental and Social Considerations (2015). Table 10.5-2 Outline of the Project’s in line with the JICA Guidelines for Environmental and Social Considerations (2010) Category 1. Sensitive Sectors 2. Sensitive Characteristics 3. Sensitive Areas Contents (6) Power transmission and distribution lines involving large-scale involuntary resettlement, largescale logging, or submarine electrical cables (1) Large-scale involuntary resettlement (2) Large-scale groundwater pumping (3) Large-scale land reclamation, land development, and land clearing (4) Large-scale logging (1) National parks, nationally-designated protected areas (coastal areas, wetlands, areas for ethnic minorities or indigenous peoples and cultural heritage, etc. designated by national governments) (2) Areas that are thought to require careful consideration by the country or locality a) Primary forests or natural forests in tropical areas b) Habitats with important ecological value (coral reefs, mangrove wetlands, tidal flats, etc.) c) Habitats of rare species that require protection under domestic legislation, international treaties, etc. d) Areas in danger of large-scale salt accumulation or soil erosion e) Areas with a remarkable tendency towards desertification Outine of the Project Technically, large-scale involuntary resettlement and large-scale deforestation can be avoided Technically, (1) and (4) can be avoided. (2) and (3) are not applicable. No direct impact is expected for protected areas, cultural heritage, and or Key Biodiversity Areas (KBA). Although the planned transmission line route passes through one reserved forest, this it can be changed through appropriate procedures because if it is a Kalama Taung Reserved Forest, it which is defined as a commercial//local supply/watershed or catchments protection reserved forestcommercial reserved forest. In addition, it does not modify vulnerable areas, such as areas in danger of soil erosion, or areas with a remarkable tendency towards desertification, will not be modified. Note: The numbers listed correspond to the numbers listed in Attachment 3 of the JICA Environmental and Social Considerations Guidelines (2010). Source: The JICA Environmental and Social Considerations Guidelines (2010), with modifications by the JICA Survey Team Social Considerations Strategy of the study is described below. The results of the study will be reported sepaetely following further technical examination in Feburary 2021. (1) Satellite Photo Analysis of the Proposed Site for the 500kV Mawlamyaing Substation The 500kV Mawlamyaing Substation (80 acres/32.4 ha) is proposed to be in Mawlamyaing District, Mon State. Satellite photos of the area surrounding the proposed site, as well as a close-up of the proposed site, were collected from Google Earth. The oldest available photos were taken in the year 2002, and the most up-to-date were taken in 2019. The latest photos, taken in July 2019, are not suitable for the analysis since the site is covered by clouds. The photos taken in December 2018 will be used to identify and count the assets (such as structures, trees and crops) at the site and in the area surrounding the site to understand the significance of the impacts of the substation construction. (2) Satellite Photo Analysis of the Proposed Route for the 500kV Transmission Line Between Pharyargyi and Mawlamyaing Substations The proposed route for the transmission line between Pharyargyi and Mawlamyaing Substations will be studied using satellite photos of the surrounding area collected from Google Earth. Land use and locations of structures and towns will be analyzed to understand the types and significance of the impacts of the transmission line construction. Advice for the detailed study of the ROW location will 10-9 Transmission Project Preparatory Survey Phase III Final Report (Advanced Release) be listed to avoid and minimize the negative impacts. (3) Preliminary Alternative Study for the Substation and Transmission Line In addition to the proposed project, the no-project case, and a case with a different site will provide three (3) alternatives for a preliminary, qualitative comparative study. Gayng River Religious school Source: JICA Study Team, Google Earth (December 2018) Figure 10.5-2 Satellite Photos of the Proposed Substation Site and Surrounding Area Source: JICA Study Team, Google Earth Figure 10.5-3 Satellite Photos of the Proposed Transmission Line Route i Capacity of four combined lines in the underground line sinusoidal section (case with increased gap between phases) ii Capacity of two lines in the underground line conduit section 10-10