Report No. 2319 Griffin Environmental Asbestos Management REPORT NO. 02319 Re-inspection of Asbestos Containing Materials (Supplement to report No 01126, 01919, 02104) Carried out by N Griffin On 4th October 2018 ! Abnormal Load Engineering New Road Hixon Staffordshire CLIENT SURVEYORS Abnormal Load Engineering New Road Hixon Staffordshire Nigel Griffin Flora Griffin For the attention of:- SURVEY CHECKED BY: Rob Gardner Signature: Name: N H Griffin Brookfield House, No 9 St. Helier Close, Seabridge, Newcastle under Lyme, Staffordshire, ST5 3SF Tel/Fax 01782 617844 Mobile 07831 811 001 e-mail: info@griffinenvironmental.co.uk www.griffinenvironmental.co.uk Company Reg. No 3244304 Griffin Environmental is a trading name of Point to Point Contracts Ltd Page 1 Report No. 2319 CONTENTS PAGE 1.0 IMPORTANT INFORMATION ------------------------------------------------------------------------------------3 1.1 SURVEY DETAILS ..................................................................................................................................................... 4 1.2 BRIEF .........................................................................................................................................................................5 1.3 CONTENT/SURVEY REPORT FORMAT ...................................................................................................................6 1.4 MATERIAL RISK ASSESSMENT ...............................................................................................................................7 1.5 SUMMARY .................................................................................................................................................................8 1.6 REVIEW OF REGISTER ............................................................................................................................................ 8 1.8 REMOVAL AND WORKING WITH ASBESTOS CONTAINING MATERIALS STATUTORY REQUIREMENTS......... 9 1.9 CAVEAT ....................................................................................................................................................................11 2.0 MATERIAL REPORTS -------------------------------------------------------------------------------------------12 3.0 PLANS ----------------------------------------------------------------------------------------------------------------18 APPENDICES -----------------------------------------------------------------------------------------------------------21 APPENDIX A: SUMMARY OF SAMPLES CONTAINING ASBESTOS........................................................................... 21 APPENDIX B: PRIORITY ASSESSMENT SCORE SHEETS .........................................................................................23 APPENDIX C: TOTAL RISK SCORE SUMMARY .......................................................................................................... 30 Page 2 Report No. 2319 SECTION 1 1.0 IMPORTANT INFORMATION Page 3 Report No. 2319 IMPORTANT INFORMATION 1.1 SURVEY DETAILS Re-inspection survey A visual Re-inspection of asbestos containing materials previously identified at ALE, New Road, Hixon, Staffordshire. Supplement to report No’s 1126 01919, and 02104. The re-inspection included material assessment of all previously identified asbestos items in accordance with Regulation 4 of the Control of Asbestos Regulations 2012 Inaccessible area/reasons for no access:- N/A Reservations and Concerns:Extensive Asbestos cement debris was identified to the permitter were the original Storage Hut 2 was located. Material now requires removal Page 4 Report No. 2319 1.2 BRIEF Re-Inspection Survey: The purpose of a re-inspection is to locate as far as reasonably practicable; Asbestos Containing Materials identified within the original survey to assess their condition and update the site register. This re-inspection is produced directly from the original survey report. Any information such as clearance certificates should also be retained along with the report, to give confirmation of any asbestos removal and its scope. Where no such confirmation exists at the time of re-inspection, it may be presumed that the asbestos containing material remains. Areas not accessed during the original survey will generally be omitted from the re-inspection and must be presumed to contain asbestos until confirmed otherwise. The survey findings have been compiled into a register format that includes photographs and plans showing sample locations. All samples of asbestos materials taken during the original survey are numbered with the original report number to identify their origin. Where additional samples are taken as part of the re-inspection, these will normally be numbered with the re-inspection report number . Page 5 Report No. 2319 1.3 CONTENT/SURVEY REPORT FORMAT The register includes survey forms providing the following information:• • • • • Sample locations Fibre content and material type Photographs Estimated quality of asbestos containing material Relevant comments The survey findings have been compiled into a register format that includes photographs and plans showing sample locations. All samples of asbestos materials taken or presumed to contain asbestos during the survey are numbered to identify their origin. Abbreviations may be used on the test report forms. These are as follows:AC - asbestos cement AIB - asbestos insulating board ins - insulation spray - sprayed coating dec finish - decorative finish (i.e. Artex) Page 6 Report No. 2319 1.4 MATERIAL RISK ASSESSMENT A risk assessment incorporates a scoring system for each asbestos item relating to its potential for fibre release. This provides a simple and effective method by which priorities for action can be assigned. Points are accumulated according to the product type, extent of damage, surface treatment and asbestos type. The risk assessment code ranges between 2 and 12 with:- V-Low = 2 - 4 Low = 5 - 6 Medium = 7 - 9 High = 10 - 12 The material risk assessment identifies asbestos containing materials most likely to release fibres into the air, and will give a good initial guide to the priority for management. Management priority however must be determined by undertaking a priority assessment in addition to the material assessment. This will determine the likelihood of the asbestos containing materials being disturbed by taking into account maintenance activities, human exposure potential, likelihood of disturbance and occupant activity. The combined risk assessments are then to be used to form a management plan in accordance with the HSE Management of Asbestos Containing Materials Regulations. 'High' Risk Category Materials in the 'high' category require urgent consideration. Factors to be taken into account include future use of the building, company policy and available finance. The following options may be appropriate:1) Complete removal. 2) Encapsulation, sealing or other protection including marking with appropriate warning labels. 3) Decontamination works. 4) Close monitoring of condition and potential for persons to be exposed to airborne asbestos fibres. (This may involve air sampling adjacent to the material to determine whether airborne asbestos fibres are being produced). 'Medium' risk category The condition of any material in the 'medium' category requires regular monitoring and a programme of encapsulation or removal may well be appropriate in the medium to long term. 'Low' risk category 'Low' risk category materials are generally not considered to cause any immediate concern and are unlikely to present any significant risk under reasonably foreseeable circumstances. Periodic condition monitoring is however advisable. 'Very Low' risk category 'Very Low' risk category materials are generally of a cement, resin or plastic based material and are not considered to cause any immediate concern, as these are unlikely to present any significant risk under reasonably foreseeable circumstances. Periodic condition monitoring is however advisable. Page 7 Report No. 2319 1.5 SUMMARY When a summary of the asbestos samples taken is included in a survey report it is located in Appendix A. This summary must be read in conjunction with the test reports to categorically determine the extent of the Asbestos Containing Materials present in this building. The summary in Appendix A is of sample locations only. This report must be read in its entirety. Each sample containing asbestos, identified within the survey, has been given a recommendation based on the surveyor’s assessment of that material. 1.6 REVIEW OF REGISTER It is normal practice to review all asbestos registers on an annual basis or more frequently where there is potential for rapid deterioration. This involves re-evaluating all risk assessment codes during a 'walk around' inspection then amending the register accordingly. Page 8 Report No. 2319 1.8 REMOVAL AND WORKING WITH ASBESTOS CONTAINING MATERIALS STATUTORY REQUIREMENTS This short summary is intended to provide an overview of legal requirements and is not comprehensive. The relevant statutes, statutory instruments and official publications should be consulted as necessary. Legislation The Control of Asbestos Regulations 2012 places numerous obligations on persons removing, working with or disturbing asbestos containing materials. The Regulations cover the following main areas:• • • • Licensing of contractors for work with most asbestos containing materials Working procedures and methods Management of asbestos which is left in situ Prohibitions on the use and re-use of materials containing asbestos Further practical information is then given in two Health and Safety Commission Approved Codes of Practice – Work with Materials Containing Asbestos, L143 and The Management of Asbestos in Non-domestic Premise, L127. In addition to the above asbestos specific regulations it is important to appreciate that other safety related legislation may be relevant in some circumstances. For example The Health and Safety at Work etc Act 1974 places general duties on employers and persons in control of premises to ensure the health and safety of employees and others. The Management of Health and Safety at Work Regulations 1999 obliges employers assess risks from work activities (including potential exposure to asbestos) and The Construction (Design and Management) Regulations 2015 place a range of safety related duties on clients, planning co-ordinators and principal contractors. Work Which Requires an HSE Asbestos Licence Most work with asbestos containing materials may only be carried out by a specialist contractor licensed by the Health and Safety Executive under Regulation 8. The only exception is where the work is extremely low risk (ie when worker exposure is below 0.6 fibres of asbestos per millilitre of air over any 10 minute period, below the 4 hour Control Limit of 0.1 fibres of asbestos per millilitre of air and is restricted to work on bonded materials or consists of resealing of asbestos containing materials that are already well sealed). Working Procedures and Methods There is no known safe level of exposure to asbestos, therefore very detailed and onerous working procedures have been published by the Health and Safety Executive – see Asbestos: The Licensed Contractors Guide, HSG247 and Asbestos Essentials, HSG210. Work on inherently friable (dust producing) asbestos materials requires full enclosure with negative differential pressure produced by air extraction plant equipped with high efficiency filtration. Entry to the working area is by an airlock system and on site personal decontamination facilities must be provided. Workers must be subject to medical surveillance and receive detailed certified training. Work for which an asbestos licence is required must be notified to the enforcing authority at least 14 days before commencement on form ASB5 and upon completion it is necessary to obtain a Certificate of Reoccupation from an independent testing laboratory. The issuing laboratory is required to hold accreditation from the United Kingdom Accreditation Service (UKAS) for the certification procedure. Procedures for work on bonded materials do not necessarily require full enclosure but this must be fully justified in the written assessment and plan of work which should be prepared before the work starts. Page 9 Report No. 2319 Waste Disposal Virtually all materials which contain asbestos are classified as ‘hazardous’. This includes asbestos cement, asbestos vinyl floor tiles etc. Transport from the site requires pre-notification to the Environment Agency and wastes may only be deposited at specially licensed disposal sites. Using Unlicensed Contractors for Work with Low Risk Materials As described above it is occasionally permissible to use non licensed contractors, such as general builders or demolition contractors, to work on low risk asbestos containing materials. Griffin Environmental would strongly advise against this approach as the other provisions such as non specialists are unlikely to produce the necessary documentation such as exposure assessments and waste consignment forms, they will not have appropriate equipment and their operatives are unlikely to have received the training required by Regulation 10. It is also important that adequate insurances are in place for work with asbestos which are generally not available to un-licensed companies and without which a client will be in difficulty should a claim arise against the contractor. MANAGING ASBESTOS CONTAINING MATERIALS LEFT IN SITU It is permissible to leave asbestos containing materials in-situ in appropriate circumstances providing that the risks are properly managed. The Approved Code of Practice, L127 and The Comprehensive Guide to Managing Asbestos in Premises, HSG227 provide much useful information including the development of an asbestos management plan. Retained asbestos materials must also be regularly re-inspected to confirm that their condition has not deteriorated. Comprehensive records should be retained for inspection by enforcement inspectors. Further Information and Assistance from Griffin Environmental The proper management of asbestos is highly complex and failure to adequately control risk can lead to asbestos related disease, reduced property values or result in enforcement action. Griffin Environmental is always pleased to provide information and assistance for comprehensive asbestos removal and asbestos management services. Page 10 Report No. 2319 1.9 CAVEAT Every reasonable effort has been made to ensure that the information contained in this report is as accurate and as comprehensive as was practicable at the time of preparation. However due to the nature of asbestos survey techniques, it is not reasonably practicable to categorically state whether all asbestos containing materials were identified. Certain asbestos products contain asbestos fibres that are so well bound into the matrix of the parent material that they do not readily generate respirable asbestos fibres under reasonably foreseeable circumstances. Examples of such materials include sealing mastics, rubber gaskets, bitumen patches and damp proof membranes. All such materials have therefore been excluded from the report. Certain ‘Artex’ type textured coatings and decorative plasters may contain very small quantities of asbestos. In situ these coatings are often composed of different batches of product or may have been repaired/patched at different times. It is therefore possible that any ‘Artex’ samples taken may not be representative of the entire coating. Recent research suggests that in some cases, the fibres may have diameters below 0.1µm. These may not be visible by the optical microscopy method described in HSE publication HSG 248 (2005). Where asbestos containing materials were installed during construction it is possible that unidentified contamination may exist within or below other components, for example below floor screeds. It is also possible that unidentified asbestos residues resulting from earlier asbestos removal works may be present in relatively inaccessible locations e.g., behind claddings, plant services or fixtures and fittings. Where such residues are found, these may be more extensive than those identified, due to previously mentioned areas of restricted access or due to paint finishes etc., encapsulating the residues. Access to electrical and process equipment was not possible due to safety and technical considerations. Such items may therefore contain unidentified asbestos materials or components. We would be pleased to make appropriate arrangements to complete the inspection if required but would require your authority to isolate or dismantle the relevant items using competent tradesmen where necessary. Griffin Environmental cannot therefore accept liability for loss, injury, damage or penalty caused by omissions or errors contained in this report. The report does not waive the responsibility of the building owner, contractor etc. to ascertain for himself as to the composition of materials which may be disturbed or with which he may work. Fuel burning boilers and associated flues were not dismantled or sampled for safety reasons. Where samples are required of these, qualified engineers are to be provided by yourselves to isolate or dismantle the relevant components. Any areas not accessed during the survey are to be presumed to contain asbestos until proved otherwise. E&OE Page 11 Report No. 2319 SECTION 2 2.0 MATERIAL REPORTS Page 12 Report No. 2319 Griffin Environmental Re-inspection Survey Asbestos Management Client: Abnormal Load Engineering Location Address: New Road Survey Date: 04/10/2018 Hixon Staffordshire Survey by: Nigel Griffin: Flora Griffin Area/Location: Hanger 1 Position: Exterior Roof Item/Material: Corrugated Panels and Fascias Sample Taken: Yes Sample Number: Analysis: No Extent of Damage Surface Treatment Asbestos Type Plastic/Resin /AC Dec Finish 1 Good no damage 0 Plastics/resin 0 Chrysotile 1 AIB/Millboard/ Woven/Paper 2 Low –scratches/ broken edge 1 AC/Painted AIB/ Enclosed ins/spray 1 Amphibole excluding crocidolite 2 Ins/Spray Coating Medium broken boards/debris 2 Unsealed AIB/ Sealed ins/spray 2 Crocidolite 3 High damage ins/spray debris 3 Unsealed ins/spray 3 1 1 1 3 N/A Analysis Date: Crocidolite 1126/842 Product Type Analyst: x 3 N/A Material Assessment Score 6 Asbestos Cement Approximate Quantity of Material: In excess of 30 Mtrs Sq Recommendations: Manage Comments: Corrugated roof panels and facias remain in a fair condition throughout. Page 13 Report No. 2319 Griffin Environmental Re-inspection Survey Asbestos Management Client: Abnormal Load Engineering Location Address: New Road Survey Date: 04/10/2018 Hixon Staffordshire Survey by: Nigel Griffin: Flora Griffin Area/Location: Hanger 1 Position: Walls to Store Item/Material: Bituminous damp proof course Sample Taken: Yes Sample Number: Analysis: No Extent of Damage Surface Treatment Asbestos Type Plastic/Resin /AC Dec Finish 1 Good no damage 0 Plastics/resin 0 Chrysotile 1 AIB/Millboard/ Woven/Paper 2 Low –scratches/ broken edge 1 AC/Painted AIB/ Enclosed ins/spray 1 Amphibole excluding crocidolite 2 Ins/Spray Coating Medium broken boards/debris 2 Unsealed AIB/ Sealed ins/spray 2 Crocidolite 3 High damage ins/spray debris 3 Unsealed ins/spray 3 1 0 1 3 N/A Analysis Date: Chrysotile 1126/843 Product Type Analyst: x 1 N/A Material Assessment Score 3 Asbestos Bituminous Approximate Quantity of Material: In excess of 4 Mtrs Sq Recommendations: Manage Comments: Bituminous material remains in good condition to the DPC Page 14 Report No. 2319 Griffin Environmental Re-inspection Survey Asbestos Management Client: Abnormal Load Engineering Location Address: New Road Survey Date: 04/10/2018 Hixon Staffordshire Survey by: Nigel Griffin: Flora Griffin Area/Location: Store Hut 2 Position: Exterior Roof Item/Material: Corrugated Cement Sheets Sample Taken: Yes Sample Number: Analysis: No Extent of Damage Surface Treatment Asbestos Type Plastic/Resin /AC Dec Finish 1 Good no damage 0 Plastics/resin 0 Chrysotile 1 AIB/Millboard/ Woven/Paper 2 Low –scratches/ broken edge 1 AC/Painted AIB/ Enclosed ins/spray 1 Amphibole excluding crocidolite 2 Ins/Spray Coating Medium broken boards/debris 2 Unsealed AIB/ Sealed ins/spray 2 Crocidolite 3 High damage ins/spray debris 3 Unsealed ins/spray 3 0 0 0 3 N/A Analysis Date: Crocidolite 1126/849 Product Type Analyst: x 0 N/A Material Assessment Score 0 N/A Approximate Quantity of Material: N/A Recommendations: No Further Action Required Comments: Corrugated sheets have been removed. Store Hut 2 has been demolished and replaced with a modern modular construction. Page 15 Griffin Environmental Report No. 2319 Asbestos Management Re-inspection Survey Client: Abnormal Load Engineering Location Address: New Road Survey Date: 04/10/2018 Hixon Staffordshire Survey by: Nigel Griffin: Flora Griffin Area/Location: Store Hut 2 Position: / Item/Material: Debris Sample Taken: Yes Sample Number: Analysis: No Extent of Damage Surface Treatment Asbestos Type Plastic/Resin /AC Dec Finish 1 Good no damage 0 Plastics/resin 0 Chrysotile 1 AIB/Millboard/ Woven/Paper 2 Low –scratches/ broken edge 1 AC/Painted AIB/ Enclosed ins/spray 1 Amphibole excluding crocidolite 2 Ins/Spray Coating Medium broken boards/debris 2 Unsealed AIB/ Sealed ins/spray 2 Crocidolite 3 High damage ins/spray debris 3 Unsealed ins/spray 3 3 1 1 3 N/A Analysis Date: Crocidolite 1126/849 Product Type Analyst: x 3 N/A Material Assessment Score 8 N/A Approximate Quantity of Material: In Excess of 1 Mtr Sq Recommendations: Removal Comments: Extensive asbestos cement debris was identified in the surrounding perimeter of Storage Hut 2. This requires removal. Page 16 Report No. 2319 Griffin Environmental Re-inspection Survey Asbestos Management Client: Abnormal Load Engineering Location Address: New Road Survey Date: 04/10/2018 Hixon Staffordshire Survey by: Nigel Griffin: Flora Griffin Area/Location: Store Hut 2 Position: Exterior Roof Item/Material: Bituminous felt and adhesive Sample Taken: Yes Sample Number: Analysis: No Extent of Damage Surface Treatment Asbestos Type Plastic/Resin /AC Dec Finish 1 Good no damage 0 Plastics/resin 0 Chrysotile 1 AIB/Millboard/ Woven/Paper 2 Low –scratches/ broken edge 1 AC/Painted AIB/ Enclosed ins/spray 1 Amphibole excluding crocidolite 2 Ins/Spray Coating Medium broken boards/debris 2 Unsealed AIB/ Sealed ins/spray 2 Crocidolite 3 High damage ins/spray debris 3 Unsealed ins/spray 3 0 0 0 3 N/A Analysis Date: Chrysotile 1126/850 Product Type Analyst: x 0 N/A Material Assessment Score 0 N/A Approximate Quantity of Material: N/A Recommendations: No Further Action Required Comments: Bituminous felt and adhesive has been removed. Store Hut 2 has been demolished and replaced with a modern modular construction. Page 17 Report No. 2319 SECTION 3 3.0 PLANS Page 18 Report No. 2319 SITE MAP Page 19 Report No. 2319 Area locations where Asbestos materials were found within the original survey Page 20 Report No. 2319 APPENDICES APPENDIX A: SUMMARY OF SAMPLES CONTAINING ASBESTOS Page 21 SAMPLE REFRENCE 1126/842 1126/843 1126/849 LOCATION Exterior to Hanger 1 Stores roof Exterior to Hanger 1 Stores walls Debris to the permi@er of Storage Hut 2 MATERIAL Corrugated cement panels and fascias Crocidolite Bituminous Damp proof course Chrysotile Debris Crocidolite PAGE NUMBER Page 13 Page 14 Page 16 RECOMMENDATIONS Manage Manage REMOVE * This summary must be read in conjunction with the test reports. The summary is of sample locations only. Page 2 ! 2 APPENDIX B: PRIORITY ASSESSMENT SCORE SHEETS Page 2 ! 3 CLIENT: ALE SITE: New Road, Hixon, Staffordshire REPORT NO. 2319 SAMPLE NO. 1126/842 Assessment Parameter A Examples of score variables Score Normal occupant activity: Main type of activity in area Average (√) Rare disturbance activity (eg., little-used store room) 0 Low disturbance activities (eg., office-type activity) 1 Periodic disturbance (eg., industrial or vehicular activity which may contact ACM’s) 2 High levels of disturbance (eg., fire door with AIB sheet in constant use) 3 Outdoors 0 Large rooms or well-ventilated areas 1 Rooms up to 100m² 2 Confined spaces 3 Usually inaccessible or unlikely to be disturbed 0 Occasionally likely to be disturbed 1 Easily disturbed 2 Routinely disturbed 3 Small amounts or items (eg., strings, gaskets) 0 <10m² or <10m pipe run 1 >10 - <50m² or >10 - <50m pipe run 2 >50m² or > 50m pipe run 3 3 None 0 0 1–3 1 4 – 10 2 >10 3 Infrequent 0 Monthly 1 Weekly 2 2 =2 Secondary activity B Likelihood of disturbance: Location Accessibility Extent/amount C 0 0 =1 Human exposure potential: Number of occupants Frequency of use of area 0 =0 Page 2 ! 4 Average time area is in use D Daily 3 <1 hour 0 >1 - <3 hours 1 >3 - <6 hours 2 >6 hours 3 Minor disturbance (eg., possibility of contact when gaining access) 0 Low disturbance (eg., changing light bulbs in AIB ceiling) 1 Medium disturbance (eg., lifting one or two AIB ceiling tiles to access a valve) 2 High levels of disturbance (eg., removing a number of AIB ceiling tiles to replace a valve or for re-cabling) 3 ACM unlikely to be disturbed for maintenance 0 < 1 per year 1 > 1 per year 2 > 1 per month 3 0 Maintenance activity: Type of maintenance activity Frequency of maintenance activity 0 =0 1 TOTAL PRIORITY RATING: =0 3 * This summary must be read in conjunction with the test reports. The summary is of sample locations only. Page 2 ! 5 CLIENT: ALE SITE: New Road, Hixon, Staffordshire REPORT NO. 2319 SAMPLE NO. 1126/842 Assessment Parameter A Examples of score variables Score Normal occupant activity: Main type of activity in area Average (√) Rare disturbance activity (eg., little-used store room) 0 Low disturbance activities (eg., office-type activity) 1 Periodic disturbance (eg., industrial or vehicular activity which may contact ACM’s) 2 High levels of disturbance (eg., fire door with AIB sheet in constant use) 3 Outdoors 0 Large rooms or well-ventilated areas 1 Rooms up to 100m² 2 Confined spaces 3 Usually inaccessible or unlikely to be disturbed 0 Occasionally likely to be disturbed 1 Easily disturbed 2 Routinely disturbed 3 Small amounts or items (eg., strings, gaskets) 0 <10m² or <10m pipe run 1 >10 - <50m² or >10 - <50m pipe run 2 >50m² or > 50m pipe run 3 None 0 1–3 1 4 – 10 2 >10 3 Infrequent 0 Monthly 1 Weekly 2 0 =0 Secondary activity B Likelihood of disturbance: Location Accessibility Extent/amount C 0 0 =1 1 Human exposure potential: Number of occupants Frequency of use of area 0 0 =0 Page 2 ! 6 Average time area is in use D Daily 3 <1 hour 0 >1 - <3 hours 1 >3 - <6 hours 2 >6 hours 3 Minor disturbance (eg., possibility of contact when gaining access) 0 Low disturbance (eg., changing light bulbs in AIB ceiling) 1 Medium disturbance (eg., lifting one or two AIB ceiling tiles to access a valve) 2 High levels of disturbance (eg., removing a number of AIB ceiling tiles to replace a valve or for re-cabling) 3 ACM unlikely to be disturbed for maintenance 0 < 1 per year 1 > 1 per year 2 > 1 per month 3 0 Maintenance activity: Type of maintenance activity Frequency of maintenance activity 0 =0 0 TOTAL PRIORITY RATING: =0 1 * This summary must be read in conjunction with the test reports. The summary is of sample locations only. Page 2 ! 7 CLIENT: ALE SITE: New Road, Hixon, Staffordshire REPORT NO. 2319 SAMPLE NO. 1126/849 Assessment Parameter A Examples of score variables Score Normal occupant activity: Main type of activity in area Average (√) Rare disturbance activity (eg., little-used store room) 0 Low disturbance activities (eg., office-type activity) 1 Periodic disturbance (eg., industrial or vehicular activity which may contact ACM’s) 2 High levels of disturbance (eg., fire door with AIB sheet in constant use) 3 Outdoors 0 Large rooms or well-ventilated areas 1 Rooms up to 100m² 2 Confined spaces 3 Usually inaccessible or unlikely to be disturbed 0 Occasionally likely to be disturbed 1 Easily disturbed 2 Routinely disturbed 3 Small amounts or items (eg., strings, gaskets) 0 <10m² or <10m pipe run 1 >10 - <50m² or >10 - <50m pipe run 2 >50m² or > 50m pipe run 3 None 0 1–3 1 4 – 10 2 >10 3 Infrequent 0 0 =0 Secondary activity B Likelihood of disturbance: Location Accessibility Extent/amount C 0 =2 2 0 Human exposure potential: Number of occupants Frequency of use of area 1 Page 2 ! 8 Average time area is in use D Monthly 1 Weekly 2 Daily 3 <1 hour 0 >1 - <3 hours 1 >3 - <6 hours 2 >6 hours 3 Minor disturbance (eg., possibility of contact when gaining access) 0 Low disturbance (eg., changing light bulbs in AIB ceiling) 1 Medium disturbance (eg., lifting one or two AIB ceiling tiles to access a valve) 2 High levels of disturbance (eg., removing a number of AIB ceiling tiles to replace a valve or for re-cabling) 3 ACM unlikely to be disturbed for maintenance 0 < 1 per year 1 > 1 per year 2 > 1 per month 3 =1 2 0 Maintenance activity: Type of maintenance activity Frequency of maintenance activity 0 2 =2 =3 3 TOTAL PRIORITY RATING: 8 * This summary must be read in conjunction with the test reports. The summary is of sample locations only. Page 2 ! 9 APPENDIX C: TOTAL RISK SCORE SUMMARY Page 3 ! 0 SAMPLE NO. MATERIAL ASSESSMENT PRIORITY ASSESSMENT TOTAL RISK SCORE 1126/842 3 6 9 1126/843 1 3 4 1126/849 8 8 16 * This summary must be read in conjunction with the test reports. The summary is of sample locations only. Page 3 ! 1