The West African Gas Pipeline (WAGP) Offshore Pipeline Intelligent Pigging Project By: Afolabi Oladimeji Ogunmefun (DM Asset Integrity. WAPCo) Summary The West African Gas Pipeline (WAGP) network consists of both onshore and offshore segments. The Offshore segment is a 20” x 569km pipeline with 3 laterals of 8”x20km, 10”x 17km and 18”x14 km, transporting natural gas from east, Itoki, Nigeria and the west, Western Region of Ghana. In the east, the WAGP system at Itoki Custody Transfer in Ogun State Nigeria links into the existing Escravos-Lagos pipeline at the Nigeria Gas Company’s Itoki Natural Gas Export Terminal in Ogun State, Nigeria. The pipeline proceeds to a compressor station near Badagry, Lagos State. From there it stretches offshore to Takoradi, in Ghana, with gas delivery laterals from the main line extending to Cotonou (Benin), Lomé (Togo) and Tema (Ghana). The construction of the pipeline began in 2006 and it was commissioned in 2008. The West African Gas Pipeline Company Limited (WAPCo) owns and operates the pipeline. Regulatory authorities and the company’s internal pipeline integrity management system require periodic cleaning of the offshore pipeline and an assessment of its integrity. The most recent of these mandatory activities was planned and executed early 2020.The intelligent pigging of the offshore segment was carried out in 36 days, from January 22, 2020 to February 25, 2020. Five (5) pig runs were done, 8004 litres of liquid, and 5kg of debris during the pig retrieval were evacuated. The exercise was adjudged successful, with no stalled pigs, no failed run and pipeline safely returned to operation. The 2020 Inline Inspection (ILI) project: A project of this nature for a pipeline that runs across four countries involves complex and high level stakeholder’s management. The significance of this project cannot be over emphasized as the WAGP supports energy security in three West African countries, Ghana, Togo and Benin. In addressing the risks and the management of the identified stakeholders for this project, we considered the following: Gas supply and availability, Gas offtake, Contracting Securing inspection window Pig launch & Pig retrieval Effluent management I. Gas Supply and availability Gas availability and supply into and through WAGP is critical to the four WAGP States as this supports their energy security. Hence, it is important to maintain the required volume and pressure during the inspection and not jeopardise energy security of the nations involved. II. Gas offtake The challenge of the inspection with respect to the gas offtake is based on reverse flow from the western corridor, balancing the power grid of Ghana and avoiding gas interruption at Tema, Ghana, Benin and Togo. WAPCo’ s Takoradi Regulating and Metering Station in Ghana which is the receipt site for the pig must be ready to take gas when gas flow to Tema is suspended for the pigging exercise. III. Contracting The contracting has to do with, securing the intelligent pig tool and ensuring all the required resources are available for the proposed window, including issues relating to flight for the IP, and the project team taking into account weather challenges during the proposed window. (NB. Flights could not land in Nigeria a week after the IP came). Outside the aforementioned, we had extensive and detailed legal review of all contracts basically due to differences in midstream and upstream operations and inter-country regulations. IV. Securing Inspection window Consideration was given to priorities across the operating countries, Hence, engagement of nation’s representatives and other stakeholders. Offtake nations need to prepare for alternative source of fuel. Alignment with producers and shippers to align shutdown or critical maintenance activities to avoid disruption. The above necessitated the need for identification of the various stakeholders and robust stakeholder mapping for effective engagement and management (see the table below) WAGP 20" OFFSHORE PIPELINE PIGGING PROJECT STAKEHOLDER MAPPING KEEP THEM SATISFIED 3 MANAGE CLOSELY 4 Share intermittent report Consult, Collaborate and engage • Gas off-taker TOGO • PRODUCERS/SHAREHOLDER • Gas off-taker BENIN • REGULATORS • KEY OFFTAKERS • TRANSPORTERS & SHIPPERS • CONTRACTORS MONITOR 1 KEEP THEM INFORMED 2 Engagement with generic Information on progress and communication changes(PROJECT ALLIES) • COMMUNITY • Ghana Ministry of Energy & • CUSTOMS SERVICE Environmental Protection Agency(EPA) • FIRE SERVICE • West Africa Rescue Association (WARA) Risk The complexity of this type of project warrants detailed project risk assessment. In view of this, a lessons learned work shop was held to learn from experiences of one of WAPCo’s shareholders with similar project (32” x 258km subsea Gas pipeline). Based on this and the project risk assessment the following risks were identified, considered and adequately planned for: Stuck Pig; o Robust procedure developed to deal with stuck pig o Subsea sub-contractor was put on alert o IP tool designed with mechanical drive and special cups with high mechanical properties o Flow simulation and modelling in conjunction with the inline inspection contractor. The West African Gas Pipeline (WAGP) Offshore Pipeline Intelligent Pigging Project By: Afolabi Oladimeji Ogunmefun (DM Asset Integrity. WAPCo) o Progressive pigging methodology was adopted Low gas flow upstream the compressor station due to low pressure o High level stakeholders engagement o Weekly meeting with producers and shippers to ensure gas availability Off taker at receipt site is not available to offtake gas due to plant shut down o High level stakeholders engagement o Weekly meeting with producers and shippers Compressor is not available o Redundancy plan in place o Critical spares and OEM support available on standby Effluent management facilities not adequate o Engagement of experienced contractor o Effluent simulation with two models o Emergency response plan in place Fire Service on standby Medical evacuation Two 33,000litres evacuation tank on standby Project execution Project management team set up 6 months before the exercise. Completed pre mobilization and equipment inspection 3 weeks before project commencement Developed communication protocol to manage simultaneous operations Developed pigging checklist and Project Execution Plan (PEP) Weekly project team meeting 6 months before the project, updating the pigging checklist Weekly meeting with gas producers Daily project meeting ( twice daily AM & PM) The following pigs were ran o Foam pig travelled for 5days o Cup pig travelled for 5days o Bi di Pig with Pipeline Data logger (PDL) travelled 5 days o Bi di with gauge plate travelled 5 days o MFL AXT Combo travelled for 6 days. Intelligent Pig tool Challenges during execution Effluent Management: Given the length of the offshore pipeline (569km) 354miles) and recent liquid in flow at our Tema R & M station, there was a high probability of liquid slug during this exercise. Outside this, the instantaneous liquidflow rate and "energy" surge ahead of the pig was likely to exceed the process design capacity at Takoradi Regulating & Metering station (receipt site). Hence, the need for slug" catching systems to handle the intermittent liquid slugs generated by the pigging activities as pigging effluent management system. Based on the liquid inflow into Tema over a period and onshore pipeline pigging effluent recovered during 2014 and 2019 intelligent pigging of 30” x 56Km onshore pipeline, a model was developed to estimate the volume of liquid expected during the WAGP 20” x 569km offshore pipeline pigging to be 8000litres of liquid. This model was chosen because the liquid drop out simulation based on the gas analysis in WAGP pipeline did not show any sign of liquid in the line. A multinational process company was awarded the project, and series of design reviews, risk assessment and pre start-up safety review ensued to ensure that the project would be done safely without incident. The calculated flow required to drive the IP was 70mmscfd at 60barg. However, the system could not deliver the 70mmscfd due to restriction and piping set up. Management of Change (MOC) was raised to increase the pressure to 80 barg. to allow for more volume to the off-taker. Outside the above, benzene, toluene, ethylbenzene and xylene (BTEX), and naturally occurring radioactive material (NORM) sampling were conducted and communication protocol established for simultaneous flow operation via pressure management between a major natural gas transporter and WAPCo Finally, given that the first four pigs (foam pig, cup pig, brush pig and plain bidi with gauge plate) came undamaged without any liquid and less than 5kg of debris across 569km, a conscious decision was made to demobilise the effluent management equipment for the following reasons. Intelligent pig must travel with a speed of 1.6m/s to 1.8m/s for data quality purpose; to achieve this, the off taker must offtake 70mmscfd. Hence effluent management piping restriction must be removed to achieve this. Given that 4 pigs had been removed without liquid, liquid was not being expected during the Intelligent Pig (IP) run. However, the IP run shut the Takoradi R & M station down due to high liquid inflow into the station and we had to improvise via valve operations and liquid evacuation to bring the IP into the station. 8004 litres of liquid was finally evacuated The West African Gas Pipeline (WAGP) Offshore Pipeline Intelligent Pigging Project By: Afolabi Oladimeji Ogunmefun (DM Asset Integrity. WAPCo) Foam Pig at Takoradi RMS MFL Tool at Takoradi RMS Key issues The following are the key issues of the project Non-inclusion of XYZ mapping in the intelligent tool Frequent black powder into Tema station after the inspection. 1.5% free water detected in effluent analysis Result The project was completed ahead of schedule The inspection was declared successful per Pipeline Operators Forum 2016 (POF) standards Data quality o The collected data is overall within the contractual agreed limits. o The MFL-A system check shows a primary data (sensor) loss of 0.95 %. o The XT system check shows no data (sensor) loss. Important anomalies o No anomalies have been reported which meet the rules as described in POF 2016, ‘list of important anomalies. Benefits The intelligent pigging exercise and it’s execution is in total compliance with some key tenents of WAPCo’ s Operations Excellence Management System (OEMS) which include but not limited to the following: Always operate within design and environmental limits Always operate in a safe and controlled condition Always maintain integrity of dedicated system Always comply with all applicable rules and regulation. The benefit of this exercise cannot be over emphasized. Beyond meeting regulatory requirements and public safety, this exercise has improved customers’ confidence in WAPCo as a business entity. Also the exercise has given WAPCo the required information about her asset, and WAPCo can now strategically make some decisions to align her actions toward achieving her objective as a world class organization. Pig type Foam pig Cup pig Bi Di Pig Gauge pig MFL Combo Solid waste 3.5 o.5 0.2 Liquid waste 8004 Remarks Excellent Excellent Excellent Excellent Very good Profile pig gauge plate at receive site Takoradi