PRINCIPLES OF COST ACCOUNTING- MARCH 2022 COURSE CONTENTS: Job costing Batch costing Contract costing Process costing Joint product and by-product costing Absorption and marginal costing C-V-P Analysis By Lwanga, D A Page 1 JOB ORDER COSTING Introduction: Job-order costing is a form of specific order costing which is employed where work is undertaken to meet customer’s requirements and is of relatively short durations. Where the duration of work is long the term used is contract costing. In case of special-order concerns products produced or job undertaken are of diverse nature. They involve materials and labour in different quantities and entail different amounts of overheads. A separate job card or cost sheet is maintained for each job or product in which all expenses of materials, labour and overheads are entered and cost of completing a job or manufacturing a product is found. Examples of the firms that use job-order costing are aircraft manufacturers, printers, furniture manufacturers, etc. Features of job-order costing (a) Products are heterogeneous i.e. cost objects are distinct and separately identifiable (b) Products are made in accordance to customers special requirements Objectives of job-order costing (a) It helps in finding out the production cost for every order (b) It helps management in future estimation of similar job-order. It provides information on progress of a job in cost term (c) Helps to control operational efficiency Factors to consider in job-order costing (a) Each order or job should be continuously identifiable from raw materials stage to completion stage (b) The system is very expensive since it needs a lot of clerical work Accumulating costs in a job-order costing system In a job-order costing system, costs of direct material, direct labour, and manufacturing overhead are assigned to each production job. These costs comprise the inputs of productcosting system. As costs are incurred, they are added to the work-in-process inventory account in the ledger. To keep track of the manufacturing costs assigned to each job, a subsidiary ledger is maintained. The subsidiary ledger account assigned to each job is a document called a job-cost sheet By Lwanga, D A Page 2 Note: A job cost card or job cost sheet is the most important document used in the jobcosting system. This will be maintained for each job/order and expensed for material, labour and overheads Procedure for a job-order costing system In job-order costing a job may be initiated internally or externally in the form of customers order to make a particular product. For jobs which are initiated externally, the procedure usually starts by receiving an inquiry from a customer about a particular job. The company uses this inquiry to prepare estimates of how much a job would cost and therefore prepare and send a quotation to the customer. Accounting entries Purchase of materials When materials are purchased, the entry passed to record purchase of materials is: Dr. Stores Control Account xx Cr. Accounts payable xx Materials requisition form As raw materials are needed for the production process, they are transferred from a warehouse to the production department. To authorize the release of materials, the production department completes a materials requisition form and presents it to warehouse supervisors. If materials issued are indirect materials the requisition, the requisition will indicate the overhead account number to be debited. The following entry is passed to record issue of materials to production: Dr. Work in process- Direct materials xx Cr. Stores control account xx The above entry is used to charge the cost of direct materials to the job. Indirect materials are charged to overheads as follows: Dr. Manufacturing overhead control-indirect materials xx Cr. Stores control account xx Direct labour costs By Lwanga, D A Page 3 The assignment of direct labour costs to jobs is based on time tickets filled out by the employee. A time ticket is a form that records the amount of time an employee spends on each production job. The time ticket is the source document used in the cost accounting department as the basis for adding direct labour costs to Work-in-Process Inventory and to the job-cost sheets for the various jobs-in-process Entries to charge labour costs to a job are similar to entries for recording materials cost applied to the job: Dr. Work-in-process account (direct labour) xx Manufacturing overheads (indirect labour) xx Cr. Wages control account xx Manufacturing overhead costs It is relatively simple to trace direct material and direct labour costs to production jobs, but manufacturing overheads is not easily traced to a job. By definition manufacturing overhead is a heterogeneous pool of indirect production costs, such as indirect material, indirect labour, utility costs and depreciation. These costs often bear obvious relationship to individual jobs or units of products but they must be incurred for production to take place. Therefore, it is necessary to assign manufacturing overhead costs to jobs in order to have a complete picture of product costs. This process of assigning overhead manufacturing costs to production jobs is called Overhead application (or sometimes overhead absorption) Pre-determined overhead rate = Budgeted manufacturing costs budgeted amount of cost driver Applied overhead = pre-determined overhead rate x actual amount of cost driver Overheads are charged to the job using pre-determined overhead absorption rates. Also, actual overheads are accumulated in the manufacturing overhead control account as follows: Dr. Work-in-process account Cr. Manufacturing overhead account xx xx By amount of overhead applied to the job By Lwanga, D A Page 4 When overheads are incurred, actual amounts are recorded by debiting the manufacturing overhead control account, i.e. Dr. Manufacturing overhead control account xx Cr. Expense, creditors, accumulated depreciation, etc. xx When the job is completed it is transferred from the factory floor to the stores. Costs related to the job must be transferred from work-in-process account to finished goods inventory account, i.e. Dr. Finished goods account xx Cr. Work-in-process account xx Completed jobs are then sold or delivered to customers. Two entries are passed at this stage. The first entry is an entry to recognize revenue from the job and second entry is an entry to transfer the cost from finished goods to the cost of sales account as shown below: (i) (ii) Dr. Debtors/ Cash account Cr. Sales account Dr. Cost of sales account Cr. Finished goods account xx xx xx xx Note: When a job is completed, the job cost card is still maintained by the entity for future reference. It can be used for estimating costs for similar jobs. Discussion questions: Question one: Mwembechai Outfitters, Inc. worked on two production jobs for the month of November, 2011. The data relating to these production jobs are provided below: Job number C 12-80 deluxe wooden canoes Job number F 16-80 deluxe aluminum fishing boats (a) 4,000 Square metres of rolled aluminum sheet metal were purchased on account for shs10,000,000 (b) On November 1, the following material requisitions were filed. Requisition number 802: 8,000 board metre of lumber, at shs2,000 per (for job number C12-80) board metre, for a total of shs16,000,000 By Lwanga, D A Page 5 Requisition number 803: (for job number F16-80) 7,200 square metre of aluminum sheet metal, at shs2,500 per square metre , for a total of shs16,000 (c) On November, 15 the following material requisition was filed: Requisition number 804: 5 gallons of bonding glue, at shs10,000 per gallon for a total cost of shs50,000 (d) At the end of November, the cost accounting department uses labour time tickets filed during the month to determine the following direct labour costs of each job. Direct labour: Job number C12-80 shs9,000,000 Direct labour: Job Number F16-80 12,000,000 Total direct labour shs21,000,000 (e) The analysis of the labour time cards undertaken on November 30 also revealed the following use of indirect labour. Indirect labour: Not charged to any particular job, shs14,000,000 This cost comprises the production supervisor’s salary and the wages of various employees who spent some of their time on maintenance and general clean up duties during November. (f) The following manufacturing overhead costs were incurred during November Manufacturing overheads Shs Rent on factory building 3,000,000 Depreciation on equipment 5,000,000 Utilities (electricity and natural gas) 4,000,000 Property taxes 2,000,000 Insurance 1,000,000 Total shs15,000,000 (g) Factory machine-usage records, indicate the following usage machine hours during November Machine hours used Job number C12-80 1,200 hours Machine hours used Job number F16-80 2,000 hours Total machine hours 3,200 hours The application of overhead to the firm’s products is based on a pre-determined overhead rate. This rate was computed by the accounting department at the beginning of 2011 as shs9,000 per machine hour. (h) During November, the company incurred selling and administrative costs as follows: Shs 1,500,000 Rental of sales and administrative office By Lwanga, D A Page 6 Salaries and sales personnel 4,000,000 Salaries of management 8,000,000 Advertising 1,000,000 Office supplies issued 300,000 Total 14,800,000 (i) Job number F16-80 was completed during November, whereas Job C12-80 remained in process. The total cost of Job number F16-80 was shs48,000,000 (j) 60 deluxe aluminum fishing boats manufactured in Job number F16-80 were sold were sold for shs900,000 each in November. The Cost of each unit sold is shs600,000 as shown in the job-cost sheet Required: Prepare journal entries to record the above transactions Question Two: Masumini Printers Ltd had the following transactions during the month of January (a) Raw materials purchased on credit shs18,000,000 (b) Direct materials issued to production during the month was shs16,500,000 (c) Indirect materials issued into production during the month was shs1,200,000 (d) Labour cost incurred during the month was analyzed as follows: (i) Direct wages shs12,000,000 (ii) Indirect wages shs6,000,000 (e) Depreciation of factory equipment was shs4,500,000 and other factory overheads incurred were: (i) Rent of factory building shs1,000,000 (ii) Insurance factory equipment 4,500,000 (iii) Electricity 1,300,000 (f) Factory are applied to jobs based on direct labour hours used during the period at the rate of shs1,050,000 per hour. In January Masumini Printers recorded 1,200 direct labour hours as the actual labour spent on jobs. (g) During the month Jobs costing shs35,000,000 were completed and transferred to finished goods. Of these, jobs costing shs28,000,000 were delivered to customers (h) Completed jobs which were delivered to customers earned Masumini Printers income ofshs33,600,000 Required: (a) Prepare Journal entries to record the above transactions (b) Prepare ledger entries to record the above information and show how the entries will appear in the Work-in-Process Control Account, Factory Overhead Control Account and Cost of Sales account. Question three By Lwanga, D A Page 7 Mecco Engineering Ltd has three departments, preparation, machining and assembly. The budgeted direct labour hours for these three departments are 8,000, 12,000 and 10,000 respectively. Factory fixed overheads are budgeted at shs180,000 for the year and variable overheads are as under:Shs Preparation 24,000 Machining 84,000 Assembly 60,000 The agreed hourly wage rates are: Shs Preparation 12 Machining 20 Assembly 10 The following details relevant to Job number M50-888 are also provided: Shs Raw materials from stock 8,500 Bought-in- components 2,700 Direct labour Preparation 50 hours Machining 200 hours Assembly 120 hours Painting by outside customers shs3,200 Administration and selling overheads are to be absorbed by adding 10% of all the costs. Profit is charged at 25% of total costs. Required: By Lwanga, D A Page 8 Draw up a cost estimate for Job Number M50-888 Question four: Kichangani Toy Company incurred the following costs to produce Job number TB178, which consisted of 1,000 teddy bears which can walk, talk, and play cards. Direct materials Requisition Number 101: 400 metres of fabric at shs800 per metre Requisition Number 108: 500 cubic metres of stuffing at shs300 per cubic metre Direct labour Time card number 72: 500 hours at shs1,200 per hour Manufacturing overheads: Applied on the basis of direct-labour hours at shs200 per hour 700 of bears were shipped to a local toy store Required: Prepare a job cost sheet and record the information given above. Question five: Indoor Company manufactures carpets for the hotel trade. They do not carry any inventory of finished goods as they only manufacture specifically to customers’ orders. They do, however, hold a range of materials in their storeroom. At 30 November 2012 they had two incomplete jobs in progress. The details of this work and the costs incurred up to and including the 30th November 2012 were as follows: Job X 123 Job X 124 Direct material shs1,250 shs722 Direct labour shs820 (164 hour) shs600 (120 hours) Factory overhead shs1,640 shs1,200 For the period from 1 December 2012 to 31 December, 2012 the Company accepted two more jobs, X 125 and X126 and incurred additional costs as follows: By Lwanga, D A Page 9 Job X 123 Direct materials issued from stores shs420 Job X 124 shs698 shs1.900 shs1,221 (shs70) (shs217) Direct materials returned to stores (shs120) Nil Direct materials transfers (shs100) Nil Direct labour hours 52 Job X 125 Job X 126 78 shs100 312 Nil 151 Direct labour is paid at the rate of shs5.00 per hour and factory production overhead is absorbed at the rate of 200% of the labour cost During the month of December Jobs X 123, X 124 and X 125 were completed, but Job X 126 would not be completed until January 2013. On completion of the Job the company adds 20% to the total production cost in order to recover its selling, distribution and administration costs. The amounts invoiced to customers during December for the completed Jobs were: Job X 123 Job X 124 Job X 125 Shs6,250 shs6,000 shs7,900 Required: (a) Calculate the total production cost for Jobs X 123, X 124, X 125 and X 126 taking into account the recovery of selling, distribution and administration overhead as appropriate (b) Calculate the profit or loss arising on those Jobs completed and invoiced to customers during December, 2012 By Lwanga, D A Page 10 SUGGESTED SOLUTIONS QUESTION ONE: (a) Dr. Stores Control (Raw materials inventory) account Cr. Accounts payable account (b) Dr. Work-in-process account Cr. Stores Control (c) Manufacturing overheads control account Cr. Stores Control account (d) Dr. Work-in-process account Cr. Wages payable account (e) Dr. Manufacturing overheads Cr. Wages payable (f) Dr. Manufacturing overheads Cr. Rent Depreciation on equipment shs10,000,000 shs10,000,000 34,000,00 34,000,000 50,000 50,000 21,000,000 21,000,000 14,000,000 14,000,000 15,000,000 3,000,000 5,000,000 By Lwanga, D A Page 11 (g) (h) (i) (j) Utilities (electricity and natural gas) 4,000,000 Property taxes 2,000,000 Insurance 1,000,000 Total 15,000,000 Dr. Work-in-process 28,800,000 Cr. Manufacturing overheads 28,800,000 Note: the total manufacturing overhead applied to work-in-process inventory during the month is calculated as follows: Machine pre-determined manufacturing overhead Hours overhead rate applied Job No C12-80 1,200 shs9,000 shs10,800,000 Job No F16-80 2,000 9,000 18,000,000 Total 28,800,000 Dr. Selling and administration expenses shs14,800,00 Cr. Wages payable 12,000,000 Rental of sales and administrative office 1,500,000 Advertising 1,000,000 Office supplies 300,000 Total 14,800,00 Dr. Finished Goods Inventory 48,000,000 Cr. Work-in-process 48,000,000 Dr. Accounts receivable 54,000,000 Cr. Sales revenue 54,000,000 Dr. Cost of goods sold Cr. Finished goods inventory 36,000,000 36,000,000 QUESTION THREE: MECCO ENGINEERING LTD COST STATEMENT FOR JOB NUMBER M50-888 Direct materials shs Raw materials from store 8,500 Bought-in-components 2,700 Direct labour Preparation 50 hours at shs12 Machining 200 hours at shs20 shs 11,200 600 4,000 By Lwanga, D A Page 12 Assembly department 120 hours at shs10 Prime cost Production overheads Variable overhead Preparation 50 hours at shs3 Machinery 200 hours at shs7 Assembly 120 hours at shs6 Variable cost 1,200 150 1,400 720 5,800 17,000 2,270 19,270 Fixed overhead 370 hours at shs6 2,220 Factory cost 21,490 Administration and selling overheads (10%) 2,149 Total cost 23,639 Profit 5,910 Selling price 29,549 Workings: 1- Variable overhead absorption rate= variable overhead/hours worked Preparation= shs24,000/8,000 hours = shs3 per hour Machining = shs84,000/12,000 hours= shs7 per hour Assembly= shs60,000/10,000 shs6 per hour 2- Fixed overhead absorption rate= fixed overhead/total hours worked =shs180,000/ (8000+12,000+ 10,000) Shs180,000/30000= shs6 per hour 3- Total hours worked for Job No M50-888= 50+200+120 =370 4- Administration and selling overhead is 10% of shs21,490= shs2,149 5- Profit is to be charged at 25% of total cost, it is 25% of 23,639, i.e. 5909.75 or shs5,910 By Lwanga, D A Page 13 BATCH COSTING Introduction: Batch costing consists of elements of both process costing and job-order costing. Batch costing is therefore a variant of job costing and is therefore applicable where homogeneous products are produced in batches and each batch is treated as a single job A batch is a group of similar articles which maintains its identity throughout one or more stages of production and it is treated as a cost unit (CIMA terminology) When dealing with a batch we consider a batch as a group of items that are closely related, and are being made for a single customer, or are being made at the same time; and the key point for our purposes is that the group of items maintains its identity as a batch, serial numbers, product numbers, production numbers, all identify the goods as a batch. In batch costing, costs are accumulated by batches as described in the preceding paragraph. The cost per unit of a product is calculated at completion of the batch, by dividing total costs by number of units in a batch. Examples of industries employing batch costing include footwear and clothing industries. The accumulation and recording of costs under batch costing is very similar to the techniques used in job-costing Example one: The budgeted overheads of Heko Printers Ltd for the year are given as under: Variable overheads Department Amount Overhead absorption base Shs Typesetting 150,000 15,000 labour hours Plate making 200,000 25,000 labour hours Printing 300,000 30,000 machine hours Binding 120,000 20,000 labour haours Selling and administration overheads are charged at 10% of production cost Profit is charged at 25% of the total cost An order for 2,000 books was received from publisher. The batch number of this order is 2315. By Lwanga, D A Page 14 The following additional information in respect to Batch No.2315 is provided:Materials shs87,000 Labour: Typesetting 150 hours at shs12 per hour Platemaking 40 hours at shs15 per hour Printing 60 hours at shs20 per hour Binding 100 hours at shs10 per hour The machine hours used on this Job were 50 Required: Calculate the total cost of the batch, cost per unit, selling price of the batch and selling price per unit. Example two: Jane Peter uses a batch costing system for her drilling and boring business; she uses a cost plus system of price setting and sets a mark-up of 25% on a sales values. Administration costs are absorbed at the rate of 10% of the selling price, whereas factory overheads are absorbed at the rate of shs12 per direct labour hour for Department C and shs9 per direct labour hour for Department L. Batch C-A consists of 1,000 shafts to be drilled and bored and the following costs have been incurred on it: Department C 500 direct labour hours at shs10 per hour Department L 750 direct labour hours at shs8 per hour Direct materials costing shs6,475 have also been used on Batch C-A Required: In drawing a batch cost card show (a) Total cost and total cost per unit (b) Selling price and selling price per unit By Lwanga, D A Page 15 BATCH COSTING SUGGESTED SOLUTION: QUESTION ONE: Shs Materials shs 87,000 Labour: Typesetting 150 hours at shs12 1,800 Platemaking 40 hours at shs15 600 Printing 60 hours at shs20 1,200 Binding 100 hours at shs10 1,000 Prime cost 4,600 91,600 Production overheads: Variable overheads Typesetting 150 hours at shs10 1,500 Platemaking 40 hours at shs8 320 Printing 50 hours at shs10 500 Binding 100 hours at shs 6 600 Production cost 2,920 94,520 Administration and selling overhead (10% of shs94,520) 9,452 Total cost of the batch 103,972 Profit (25% of shs103,972) 25,993 Selling price of the batch 129, 965 Cost per unit By Lwanga, D A Page 16 Total cost of the batch = total cost of the batch/ number of books = shs103,972/2,000 = shs51.98 Selling price per unit= selling price of the batch/ number of books = shs129,965/2,000= shs64.98 Workings: Overhead absorption rates Typesetting = total overhead/total labour hours= shs150,000/15,000= shs10 Platemaking = total overheads/total labour hours= shs200,000/25,000= shs8 Printing= total overheads/total machine hours= shs300,000/30,000 =shs10 Binding =total overheads heads/total labour hours= shs120,000/20,000=shs6 By Lwanga, D A Page 17 CONTRACT COSTING Introduction: Contract costing is a system of job-costing that is applied to relatively large cost units which normally take a considerable length of time to complete. Examples are buildings and construction work, civil engineering, ship buildings, dams, bridges, roads, etc. All these contracts are large in size and extend over more than one accounting period. A significant part of the work is normally carried out on the customer’s site. A contract account is maintained for each individual contract. All the direct costs of the contract are debited to the specific contract and overheads are apportioned. The difference between the contract price and the costs charged is a profit made from the contract Characteristics of contract costing Higher proportion of direct costs: Because of the self-contained nature of most site operations, many items are classified as direct Low indirect costs: For most contracts, the only item of indirect costs would be a charge of head office expenses Difficulties of cost control: This is because of the size of the site and the nature of the contract Surplus materials: All materials bought for a contract would be charged directly to a contract. At the end of a contract, a contract account would be credited with the cost of materials not used and if they were transferred directly to another contract, the new contract account is debited. If they are not required immediately the materials would be stored and the cost debited to the stock account Contract plant (a) When a plant is leased: the leasing charges are charged direct to a contract (b) When plant is purchased: one of the two methods are used: i) Charge new plant at cost to the contract for which it has a purchase, at the end credit with the second-hand value of the plant ii) Where plant is moved frequently from contract to contract or where contracts are relatively short, a “Plant Service Department” is created. This department organizes the transfer of plant from contract as required and each contract is charged a daily or weekly rental Note that whatever method is used for charging capital costs of plant, the ordinary running costs, i.e. fuel, repairs and insurance would be charged direct to the contract By Lwanga, D A Page 18 Progress payments and architect’s certificate: The contract normally provides for a client to make progress payments either at specific stage of work or at particular agreed intervals. The basis for these interior payments is an architect’s certificate of work satisfactorily completed, which shows the value of the work done at shillings prices and this certificate accompanies the invoice sent to the customer. The amount paid is normally the certified values less a percentage retention which is released when the contract is full completed by a contractor. Retention A specific percentage of the work certified is withheld by contractee or client. This amount withheld is known as retention money. This amount is paid to the contractor on the completion of a contract. The main purpose of this retention money is to ensure that the contract has been completed according to the satisfaction of the client and all defects in the work have been cleared by the contractor. This retention money is shown as a debtor in the books of contractor Example one: An architect assesses the value of the work done to be shs265,000,000. The client has already paid shs110,000,000 and the agreed retention percentage is 15% Required: a) Compute the amount of progress payment b) Pass the accounting entries for this payment when received Profit on uncompleted contracts Where a contract extends for a period of more than one accounting period it is necessary to estimate the amount of profit earned in a particular period. Total profit is estimated by comparing contract value with costs incurred and expected costs required to complete the contract Where a loss occurs, prudence concept requires full recognition of loss in the period in which it occurs. However, if there is a profit there must be a way of recognizing a portion of this profit during a particular accounting period The following guidelines are useful in determining profit attributable to contracts in progress: (a) If the contract is in its early stages, profit should not be taken. Profit is taken when the outcome of the contract can be reasonably foreseen; (b) Where substantial costs have been incurred on the contract (say the contract is 30-80% complete), profit to date is estimated as: By Lwanga, D A Page 19 Profit taken= 2 or 3 x Notional profit x cash received 3 4 Value of work certified Notional profit is the value of work certified to date less the cost of work certified to date and the provision of unforeseen losses. (c) When the contract is nearing completion (say over 80% complete) and eventual profit can be assessed with reasonable certainty there is no need for excessive prudence and one of the following methods may be used: Profit attributable= cash received to date x estimated profit from the contract Contract price This formula allows for retention percentage. In unlikely event of there being no retention by the client the formula would be: Profit taken =value of work certified x estimated profit) Contract price The above method is probably the most usual but there are other possibilities Profit taken= value of work certified-cost of work certified Or profit taken = cost of work done x estimated total profit Estimated cost of a contract (d) If a loss occurs, it should be recognized in full in a period in which it occurs Note that profit is calculated on cumulative basis, therefore profit for the current period is determined by deducting profit taken in P&L account of the previous periods from calculated profit. Further, it is important to note that costs incurred on the contract are recorded in a contract account and is debited by the amounts incurred on the contract. Credits in this account normally consist of contract price. Thus the contract account is in effect, the profit and loss account for each contract. Example two: At the year-end Apple Development has three contracts in progress and their details are as follows: Contract Contract price AP 10 AP 11 AP12 Shs shs shs 150,000 275,000 185,000 Costs to date 35,000 144,000 154,000 Estimated costs of completion 88,000 96,000 7,000 By Lwanga, D A Page 20 Value of work certified 40,000 165,000 172,000 Progress payment received 34,000 140,250 146,200 Cost of work certified 28,000 138,000 150,000 Required: What interim profits if any, should be taken on the three contracts? (no profit has been taken so far) Accounting entries for contracts A separate account will be kept for each contract with the general objective of establishing the overall contract profit or loss. In addition there are contract entries within the contract account relating to carry forward/brought forward items, accrual and pre-payments Book keeping and contract cost costing entries Direct costs: Debit the contract account Cost of plant: Hire of the plant: debit the contract account Plant bought: Dr. Contract account with cost Contract account with depreciation Cr. Contract account with balance c/d Dr. Plant account with depreciation and running expenses Dr. Contract account with overheads included at the end of contract otherwise does not include them as part of WIP c/d: Deriving the balance sheet entries Some items which are entered into contract accounts are conventionally and produce straight forward balance sheet entries. The two main items in this category are unused materials on site and plant on site There more difficulties however with work-in-progress and the differences the amounts recognized as turnover and the progress payments received. The balances relating to long term contracts are split into categories: By Lwanga, D A Page 21 (a) The costs of work done which is not yet recognized in the profit and loss account is shown under stocks as “long term-contract balances” (b) The difference between shs i) Amount taken as turnover xx ii) Less: Progress payments received xx = net difference xx Will grouped with Debtors as Amounts recoverable on long term contracts if i) is greater than ii). Alternatively, the net difference will be offset against the balances in (a) above if ii) is greater than i) Thus, it will be seen that various separate contract balances are calculated and then netted to produce final balances which appear suitably segregated, in the firms’ aggregated published balance sheets Example three: The following information relates to Contract F-887 on Mwanakwelekwe Site on 31st December 2011 CONTRACT F-887 MWANAKWELEKWE SITE CUSTOMER – MKUNAZINI CORPORATION Shs’000 Wages Materials delivered direct to site 42,156 54,203 Materials from main stores 657 Materials transferred to Mwembeladu Site 1,590 Plant purchased (at cost) 12,500 Plant transferred to Mwanakwelekwe 5,250 Sub-contractor’s charges 19,580 Site expenses (power, etc.) 5,086 Materials on site 31st December 2011 18,300 Plant on site 31st December 2011 14,750 Pre-payments at 31st December 2011 507 By Lwanga, D A Page 22 Accrued wages at 31st December 2011 921 Sales value of the stage completed 117,500 Cost of stages completed 102,300 Head office charges are 10% of wages Progress payments received from client 115,000 The contract value is shss550,000,000 and it is anticipated that there will be further costs of shs375,000,000 (including guarantee and rectification claims). As this is the first year no profit has been taken previously. Required: From the above: (a) Prepare a contract account for the year ended 31st December, 2011 (b) Balance sheet as at 31st December 2011 (c) The opening entries for 1st January 2012 It is the company’s policy to take as interim profit the difference between the sales value and cost of stages completed. Question four: Usangu Construction Co. won a contract for the construction of a mult-story at a cost of shs200,000,000 The data relating to the contract for the year ended 31st December, 2012 were as under: Shs’000 Materials issued to the site 80,000 Materials purchased locally 15,700 Direct wages: Paid Accrued Plant purchased and installed 5,800 350 48,800 Direct expenditure Paid 1,780 By Lwanga, D A Page 23 Accrued 70 Establishment charges 180 Materials returned to store 850 Work certified 150,000 Cost of work not certified 3,800 Materials on site on December 31 5,330 Value of plant on December 31 41,500 The company has received from a client payments amounting shs126,000,000 Required: (a) Prepare the contract account (b) Prepare the contractee account (c) Show how the various items will appear in the balance sheet (statement of financial position) Example five: (assignment) A construction company is currently undertaking three separate contracts and information relating to these contracts for the year 2010 together with other relevant data is as follows: Contract Contract price Contract Contract Construction Moro Pwani Songea Services dept Tshs’000 Tshs’000 Tshs’000 800,000 675,000 1,100,000 190,000 370,000 Tshs’000 Balances b/f at beginning of the year: - Cost of work completed - - Materials on site - - Written down value of plant and machinery Wages accrued - 35,000 170,000 12,000 - 2,000 - - - - - 25,000 By Lwanga, D A Page 24 Profit previously transferred to P&L a/c - - 15,000 Materials delivered to site 40,000 99,000 180,000 Wages paid 20,000 47,000 110,000 Payments to sub-contractors - - Salaries and other costs 6,000 20,000 90,000 15,000 8,000 35,000 - 25,000 21,000 Written down value of plant: Issued to sites Transferred from sites - 8,000 Balances c/d at the end of the year: Materials on site Written down values of plant and machinery 8,000 70,000 Wages accrued - Pre-payment to sub-contractors - Value of work certified ate the end of the year Cost of work not certified at year end 90,000 - 110,000 5,000 5,000 15,000 390,000 950,000 26,000 The cost of operating the construction services department, which provides technical advice to each of the contracts, is apportioned over the contracts in proportion to wages incurred Contract Songea is scheduled for handing over to the contractee in the near future and the site engineer estimates that the extra costs required to complete the contract in addition to those tabulated above, will total shs138,000,000. This amount includes an allowance for plant depreciation, construction services and contingencies Required: By Lwanga, D A Page 25 (a) Construct a contract account for each of the three contracts for the previous year and show the cost of work completed at the year end (b) Recommend how much profit or loss should be taken for each contract, for the previous year, and explain the reasons for each of your recommendations. SOLUTIONS TO DISCUSSION QUESTIONS Example one: Current payment =value certified-retention-payment already made =shs265,000-15%(265,000)- 110,000 = shs265,000-39,750-110,000 = shs115,250 The accounting entries for this payment when received are: Dr. Bank a/c Cr. Client account Example two: First check the degree of completion and whether the contracts are expected to make profit on completion. Only if an overall profit is expected can taking an interim profit be considered. If contract showed an overall loss, this must be taken, in full, in the current accounting year in accordance with prudence concept Contract price Less: estimated total costs Estimated contract profit AP10 Shs 150,000 123,000 27,000 AP11 shs 275,000 240,000 35,000 AP12 shs 185,000 161,000 24,000 Approximate degree of completion Costs to date =35,000 144,000 154,000 Total costs 123,000 240,000 161,000 =28% 60% 96% Thus all contracts are expected to make an overall profit on completion so taking an interim profit can be considered provided that the degree of completion justifies doing so By Lwanga, D A Page 26 Contract AP10 only 28% is complete so it would be prudent not to take any profit until more of the contract is completed Contract AP11 60% is complete so a prudent amount of profit can be taken. As there is retention of 15% a reasonable method of calculation would be: Profit taken= 2 x Notional profit x progress payment 3 value of work certified = 2 x (165,000-138,000) x 140,250 3 165,000 = shs15,300 Note that the above figure is considered below the difference between the value and cost of work certified which is shs27,000. This means that the amounts taken to the P&L for turnover and cost of sales should be less than shs165,000 and shs138,000 respectively AP12 96% complete so a somewhat less prudent view can be taken of the interim profit. A reasonable calculation would be Profit taken= Progress payments x estimated total profit Contract price = shs146,200 x24,000 185,000 =shs18,966 It will be seen from the initial data that, in each case there was work done but not yet certified i.e. costs to date less cost of work certified. This must be carried at cost not sales value. Question three: CONTRACT NO F-887 CUSTOMER: MKUNAZINI CORPORATION SITE: MWANAKWELEKWE CONTRACT ACCOUNT Shs’000 shs’000 shs’000 Site wages 42,156 material transferred out 1,590 Add: accrued 921 43,077 prepayment c/d 507 Materials purchased 54,203 Materials fro stores 627 54,860 Plant purchased 12,500 Materials at site c/d 18,300 By Lwanga, D A Page 27 Plant transferred in Subcontractors Site expenses Head office charges 5,250 Cost of stages completed 17,750 19,580 5,086 4,308 144,661 Plant at site c/d 14,750 WIP c/d 7,214 (see note a) Cost of stages completed 102,300 144,661 102,300 Sales value Profit for the year (See note b) 15,200 117,500 1st Jan,2012 (see note c) Prepayment b/d Materials b/d Plant b/d WIP b/d 117,500 507 18,300 14,750 7,214 117,500 accrued wages 921 Notes: (a) Total costs to date are shs109,514 (shs144,661- items c/d and transferred out) As the cost of stages completed is shs102,300 the contract balance (WIP) is: Shs’000 109,514 Less: cost of sales 102,300 = long term contract balance 7,214 (b) Before any profit can be taken for the year it is necessary to estimate the overall project outcome to whether a profit or loss is expected , thus: Expected contract outcome: Shs Contract value 550,000 Less: costs to date 109,514 Future costs 375,000 484, 514 Expected overall contract profit 65,486 As an overall profit is expected it is reasonable to take a proportion into this year’s accounts. The profit is the difference between the cost and the sales value of the stages completed as shown By Lwanga, D A Page 28 (c) All the entries shown appear in the balance sheet as at31st December year 2011 and would be aggregated with the other pre-payments, accruals and stocks and work in progress of the firm In addition a balance sheet entry arises from a personal account of the client, Mkunazini Corporation thus: MKUNAZINI CORPORATION BALANCE SHEET Cash (progress payments) Sales value of completed stages 117,500 Balance c/d (debtors) 117,500 1st January, 2012 balance b/d 115,000 2,500 117,500 2,500 The shs2,500 balance on Mkunazini account would be grouped with debtors termed “Amounts recoverable on long-term contracts” It should be noted that a debtor arises because the amount taken for Turnover (shs117,500) exceeds the progress payments (shs115,000) Question four: Refer Salemi, N.A, (2005) Cost Accounting Simplified (4ed), pg161-164 By Lwanga, D A Page 29 PROCESS COSTING Process costing system is used in situations where homogeneous products are produced from a continuous production process. Given the nature of production process and the facts that the outputs are identical, it is not feasible to identify costs with individual units or jobs. Consequently, in a process costing system cost of a unit of a product is assumed to be the average cost of all units produced during the period Examples of industries where process costing is applicable includes cement, petroleum refining, food processing and clothing manufacturing Flow of costs in a process costing system In an enterprise, which use process costing system production move from one process to the next or from one department to the next. Each process performs some work on the units as part of the total operation of transforming the units of finished product. Therefore, each process applies resources in carrying out this transformation process and incurs costs. When the process is complete units are transferred to the next process where they become inputs. Again the resources are applied to the units until a stage is reached when they are transferred to the next process or department. This flow continues until the final processing stage where a finished product emerges. As the units are transferred from one process to the next, costs relating to the previous process are also transferred with those units. Therefore the cost becomes cumulative and at the end the finished product will bear costs incurred from the first to the last processing operation It follows therefore that in process costing system costs are accumulated by processes and a separate account is maintained for each process. When units are transferred from one process to another, the process account of transferring department (or process) is credited and that of the receiving department is debited with the costs of units transferred. When transfers are made from the final process the finished goods account is debited. Features of process costing Although details vary from one concern to another, there are common features in most process costing systems. These include: By Lwanga, D A Page 30 Clearly defined cost centers and accumulation of all costs (materials, labour and overheads) by the cost centers The maintenance of accurate records of units and part units produced and the costs incurred by each process The averaging of the total costs of each process over the total production of that process, including partly completed units The charging of the cost of the output of one process as the raw materials input cost of the following process Clearly defined procedures for separating costs where the process produces two or more products (i.e. Joint products) or where by-products arise during production Accounting entries Materials The materials used at each process are debited to the respective process account Labour Direct labour of each process is debited to the respective process account. In process costing, the proportion of direct labour cost is small compared to material cost. The main reason is the use of automatic plant or equipment in such industries Direct expenses Expenses incurred in respect of any particular process are debited to the process account Production overheads In process costing, the proportion of production overheads is comparatively high. Each process is charged with a reasonable share of production overhead Example one: The manufacture of product “GWALA” requires three distinct processes numbered I-III to finished goods stock. The following information was obtained in respect of product GWALA for the month of March, 2012 3,000 units of raw materials at shs75,000,000 were issued to process I and the costs incurred are given below: ELEMENT OF COST PROCESS By Lwanga, D A TOTAL Page 31 I II III Shs’000 Shs’000 Shs’000 Shs’000 Direct materials 5,000 12,000 18,000 35,000 Direct labour 30,000 20,000 10,000 60,000 Direct expenses 2,800 5,200 2,000 10,000 - - 90,000 Production overheads - Production overhead is absorbed by each process at 150% of direct labour. There was no stock of raw materials or work-in-process either at the beginning or at the end of the period Required: Prepare process accounts Process Losses With many forms of production the quantity, weight or volume of the process output will be less than the quantity, weight or volume of materials input. This may be due to various reasons: Evaporation, residuals, ash Unavoidable handling, breakage and spoilage loses Withdrawal for testing and inspection Because of increasing material costs, careful records must be maintained of loses occurring and the resulting cost implications. If loses are in accordance with normal practice, i.e. standard levels, they are termed normal process losses. If they are above expectation, they are known as abnormal process losses. The cost of normal loss is absorbed in the cost of production for good production. If defective units in respect of normal loss can be sold for a reduced value then the proceeds of these units are subtracted from total cost Process costing when output is full complete i) No losses within the process To calculate the cost per unit of output for this case we merely divide the total cost incurred for the period by the output for the period By Lwanga, D A Page 32 ii) Normal losses in process with no scrap value Certain losses are inherent in the production process and cannot be eliminated, e.g. liquids may evaporate, part of cloth required to make a suit may be lost and losses occur in cutting wood to make furniture. Because they are an inherent part of the production process normal losses are absorbed by the good production. Where normal losses apply the cost per units of an output is calculated by dividing the costs incurred for a period by the expected output from actual input for the period iii) Abnormal losses in process with no scrap value Because they are not inherent part of the production process they are not included in the process cost, but removed from an appropriate process account and reported separately as an abnormal loss. Abnormal losses are written off in the P&L a/c iv) Normal losses in a process with a scrap value If all of the units lost represent a normal loss in process and the units lost have a scrap value (sales value) then the sales value of the spoiled units should be offset against the cost of appropriate process where the loss occurred Therefore, the sales value of the normal loss is credited to the process account and a corresponding debit entry will be made in a cash or accounts receivable (debtors) account The calculation of the cost per unit of an output is as follows: = input cost-scrap value of the normal loss Expected output v) Abnormal losses in process with scrap value If it happens that the lost units have a scrap value and the objective is to calculate the cost per unit for the expected output only the scrap value of the normal loss will be deducted by ascertaining the cost per unit The sales value of the units lost represent revenue of abnormal nature and should not be used in the process unit cost. This revenue is in effect against the cost of abnormal loss which is of interest to management vi) Abnormal gains with no scrap value By Lwanga, D A Page 33 On occasions the actual loss in process may be less than expected in which case an abnormal gains results. We are assuming that in this case abnormal gain does not have a scrap value. The value of the gain is calculated in the same way as abnormal loss and removed from process account by debiting the account and crediting the abnormal gains account vii) Abnormal gains with a scrap value The issue is to find the cost of normal output with the scrap value, i.e. input cost less scrap value of the normal loss. Note that the cost per unit is based on the normal production cost per unit and is not affected by the fact that abnormal gain occurred on the sales of spoiled units of which the sales value did not materialize. The issue is to produce the cost per unit based on normal operating efficiency. Abnormal gain units be removed from the process account and that it is valued at the cost per unit of normal production. However, as there is a gain also there is a loss of sales and this lost revenue should be offset against the abnormal gains. Example two: Mwenemtapa Company manufactures product “PEKEE”. During the month of February, 2012, 2000 kg of materials at shs5,000 per kg were supplied to process I. Labour costs amounted to shs3,000,000 and production overheads of shs2,300,000 were incurred. The normal loss has been estimated at 10%. The actual production was 1,750 kg Required: Prepare process account and calculate the cost per unit Example three: Assume the same data as in example two except that the scrap value of the normal loss and abnormal loss was shs1,800 per kg Required: Prepare process account and calculate the cost per unit Example four: Assume the same data as in example two except that the scrap value of normal loss was shs1,800 per kg and actual production was 1,830 units Required: Calculate the abnormal gain and show the relevant accounts By Lwanga, D A Page 34 Hint: examples two-four: Refer Salemi, N.A, (2005) Cost Accounting Simplified (4ed), pages 187-191 Example five: Chemical Company Ltd makes a chemical that passes through three production processes 1, 2 and 3. In the month of February, 2012, 6,000 liters of basic raw materials priced at shs240,000 were introduced into process 1. Subsequently, the following costs were incurred: Element of cost total process 1 2 3 shs shs shs 87,000 30,000 40,000 110,000 16,900 40,000 6,000 shs Direct materials (additional) Direct labour Direct expenses 50,000 1,600 17,500 20,000 9,300 Normal loss per process was estimated as: Process 1 10% Process 2 5% Process 3 8% Output of each process was: Process 1 5,300 Process 2 5,000 Process 3 4,700 The loss in each process represented a scrap which could be sold of the following values Process 1- shs20 per unit Process 2 – shs44 per unit Process 3 –shs65 per unit There was no stock of materials or work-in-progress at the beginning or end of the month. The output of each process passes directly to the next process and finally to the finished stock Production overhead is absorbed by each process on basis of 50% of cost of direct labour By Lwanga, D A Page 35 Required: (a) Prepare separate process accounts for each of the three processes (b) Prepare the abnormal loss and abnormal gains accounts The concept of equivalent units When some of the output started during a period is partially complete at the end of the period, unit costs cannot be computed by simply dividing the total costs for a period by output for that period. For that case we must convert the WIP into finished equivalents (equivalent production) so that the unit costs can be obtained. For that case we must estimate the percentage of degree of completion of the WIP and multiply by the number of units in progress at the end of the accounting period Elements of costs with different degree of completion Sometimes WIP not all as the elements that make up the total cost may have reached the same degree of completion. Where this situation arises separate equivalent production calculations must be made for each element of costs Previous process cost As production moves through processing, the output of one process becomes the input of the next process. The next process will carry out additional conversion work and may add further materials. It is important to distinguish between these different cost items: this is achieved by labeling the transferred cost from the previous process “previous process cost”. This element of cost will always be full as far as closing WIP is concerned Valuation of opening WIP The closing WIP at the end of specific period appears as opening WIP at the start of next period. This opening WIP at the start of next period will be partially complete and will have a value brought forward from a previous period. In most of the cases, there is both opening and closing WIP. In such cases the equivalent units can be calculated by adopting two different methods: i) FIFO method of valuation In FIFO method, it is assumed that the production is completed on the First-in-First Out basis. It means the first work done in the period is the completion of the opening WIP and the closing WIP is valued at current period costs. This method is most suitable when the costs are relatively stable By Lwanga, D A Page 36 In this method, opening work in progress keeps its identity. The cost of output completed in the period is worked in three parts: ii) The cost incurred during the current period to complete work-in-progress b/f The cost of units started and completed in the current period The cost of work started but not completed in the current period Average cost method of valuation This method is also known as average price method. In this method, an average cost is calculated using the total of opening WIP valuations plus the current period costs. The opening WIP is treated as the current production. It means the opening WIP losses its identity. Under this method, both closing WIP and completed units are valued using the same average unit cost. The effect of this is that previous period’s costs included in the opening WIP influences the valuation of the closing WIP. This method is more suitable when costs fluctuate from period to period FIFO versus Average Cost Method FIFO and average cost methods can be used under the following conditions When the value of the opening WIP is given in lump sum amount and the stage of completion is given then only FIFO method is possible When the value of the opening WIP is given in terms of material, labour and production overhead but the stage of completion is not given then only average cost method is possible If the degree of completion and the value of WIP in terms material, labour and overheads is given then use any method Cost of production report A departmental cost of production report shows all costs chargeable to a department. It is not only the source of summary journal entries at the end of the month but also a most convenient vehicle for presenting and disposing of costs accumulated during the month. A cost of production report shows: Total unit costs transferred to it from a preceding department Materials, labour and factory overheads added by the department Unit cost added by the department Total and unit costs accumulated to the end of operations in the department The cost of the beginning and ending work in process inventory Costs transferred to succeeding department or to a finished goods storeroom. By Lwanga, D A Page 37 It is customary to divide the cost section of the report into two parts; one showing costs for which the department is accountable, including departmental and cumulative total and unit costs and the other showing the disposition of these costs. A quantity schedule showing the total number of units for the department is accountable and the disposition made of these units is also part of the department’s cost of production report. Information in this schedule adjusted for equivalent production is used to determine the unit costs added by a department, the cost of ending work in progress inventory, and the cost to be transferred out of the department A cost of production report determines periodic total and unit costs. However, a report that would merely summarize the total cost of materials, labour and factory overheads and shows only the unit cost for a period would not be satisfactory for controlling costs. Total figures mean very little; cost control requires detailed data. Therefore, in most instances, the total cost is broken down by cost elements for each department head responsible for costs incurred. Furthermore, detailed departmental figures are required because of the various completion stages of the work in process inventories. Either in the cost of production report itself or in the supporting schedules, each item of material used by a department is listed, every labour operation is shown separately, factory overhead operations are noted individually, and a unit cost is derived for each item. To condense the illustrated cost of production reports, only total materials, labour and factory overheads charged to the departments are considered, and unit costs are computed only for each cost element rather than for each item. Example six: Mapambo Ltd is a manufacturing company which uses a process costing system to determine costs of one of its products, body lotion. Mapambo Ltd commenced production in March, 2012 and the following data was available at the end of March, 2012: Opening work in process (units) 0 Units started during the period 200,000 Units completed during the month and transferred to finished goods 160,000 shs Cost of materials added during the month 9,600,000 Cost of labour and overheads during the month: By Lwanga, D A Page 38 Labour 7.680,000 Overheads 5,760,000 Materials are added in the production process at the beginning of the process, labour and overheads are applied uniformly throughout the process. The stage of completion of units in process at the end of the month is estimated to be 80% Required: Determine the cost of units completed and transferred out to finished goods and the cost of closing work in process inventory Solution: The following stages are involved when determining solution for this question (a) Summarize flow of units in the production process (b) Compute equivalent units of production (c) Summarize the total costs to account for during the period and calculate the cost per equivalent unit (d) Apply cost per equivalent units to determine cost of units completed and cost of work in process We present the solution in the cost of production report Mapambo ltd Cost of Production Report for the March, 2012 Equivalent units Physical units Opening work-in-process materials Conversion 0 Units started 200,000 Units to account for 200,000 Accounted for as follows: By Lwanga, D A Page 39 Completed and transferred out 160,000 160,000 160,000 Closing WIP (80%) 40,000 40,000 32,000 Units accounted for 200,000 200,000 192,000 Summary of costs total Opening WIP 0 0 0 Costs added during March 23,040,000 9,600,000 13,440,000 Costs to account for 23,040,000 9,600,000 13,440,000 200,000 192,000 48 70 Divide by equivalent units Cost per equivalent units 118 Costs accounted for as follows: Units completed and transferred out Closing WIP: (160,000 x118) 18,880,000 Materials (40,000 x48) 1,920,000 conversion (32,000x70) 2,240,000 4,160,000 23,040,000 Opening stock Materials 9,600,000 Labour 7,680,000 Overheads 5,760,000 Mapambo Ltd Work-in-Process Account 0 Finished Goods Balance c/d – closing stock By Lwanga, D A 18,880,000 4,160,000 Page 40 23,040,000 23,040,000 Example seven: The following information is provided in respect of Process 2 of the month of March, 2013: Opening stock 400 units valued at shs12,800 Degree of completion: Material 80% Labour 50% Overheads 50% Transfer from Process 1 Transfer to Process : 6,000 units at shs177, 200 3 : 5,000 units Production costs during the period were: Shs Direct material 42,880 Direct labour 53,080 Production overheads 36,036 Closing stock: 800 units Degree of completion: Material 80% Labour 60% Overheads 40% Units scrapped: 600 units Degree of completion: Material 100% By Lwanga, D A Page 41 Labour 70% Overheads 70% There was a normal loss in the process of 10% of production. Units scrapped were sold at shs25 per unit Required: Prepare Process 2 Accounts by using FIFO method Example eight: The following data relates to Process Y for accounting period 2 At the beginning of period 2 there were 800 units partly completed which had the following values: Value shs’000 % age complete Input materials (from Process X) 8,200 100 Materials introduced 5,600 55 Labour 3,200 60 Overheads 2,400 45 During the period 4,300 units were transferred from Process X at a value of shs46,500,000 and other costs were: Shs’000 Materials introduced 24,000 Labour 19,500 Overheads 18,200 At the end of the period, the closing WIP was 600 units which were at the following stages of completion: Input material 100% By Lwanga, D A Page 42 Materials introduced 50% Labour 45% Overheads 40% The balance of 4,500 units was transferred to Finished Goods Required: Calculate the value of units transferred to Finished Goods and the value of WIP and prepare the Process account using: (a) FIFO method and (b) Average Cost method Example nine: (Assignment) A company operates expensive process plant to produce a single product from one process. At the beginning of October, 3,400 completed units were still in the processing plant, awaiting transfer to finished stock. They were valued as follows: Shs’000 Direct materials 25,500 Direct wages 10,200 Production overheads (200%of direct wages) 20,400 During October, 37,000 further units were put into process and the following costs charged to the process: Shs’000 Direct materials 276,340 Direct wages 112,000 Production overheads 224,000 36,000 units were transferred to Finished Stock and 3,200 units remained in WIP at the end of October which were complete as to material and half-complete as to labour and production overheads. A loss of 1,200 units, being normal occurred during the process The average method of pricing is used By Lwanga, D A Page 43 Required: (a) Prepare for the month of October, a statement (or statements) showing: i) Production cost per unit in total and by element of cost ii) The total cost of production transferred to Finished Goods iii) The valuation of closing WIP in total and by element of cost (b) Describe five characteristics which distinguish process costing from job costing Example seven: The following information is provided in respect of Process 2 of the month of March, 2013: Opening stock 400 units valued at shs12,800 Degree of completion: Material 80% Labour 50% Overheads 50% Transfer from Process 1 Transfer to Process : 6,000 units at shs177, 200 3 : 5,000 units Production costs during the period were: Shs Direct material 42,880 Direct labour 53,080 Production overheads 36,036 Closing stock: 800 units Degree of completion: Material 80% Labour 60% Overheads 40% Units scrapped: 600 units By Lwanga, D A Page 44 Degree of completion: Material 100% Labour 70% Overheads 70% There was a normal loss in the process of 10% of production. Units scrapped were sold at shs25 per unit Required: Prepare Process 2 Accounts by using FIFO method By Lwanga, D A Page 45 JOINT PRODUCT AND BY-PRODUCT COSTING Introduction: Joint products and by-products arise in situations where the production of one product makes inevitable the production of other products A distinguishing feature of the production of joint and byproducts is that the products are not identifiable as different products until a specific point in the production process is reached. Before this point joint costs are incurred on the production of all products emerging from the joint production process. It is therefore not possible to trace joint costs to individual products Definitions A joint product is the term used when two or more products arise simultaneously in the course of processing, each of which has a significant sales value in relation to each other A by-product is a product which arises incidentally in the production of the main product(s) and which has a relative small sales value compared with the main product By-product costing By Lwanga, D A Page 46 Because by-products by definition have a relatively small sales value, elaborate and expensive costing system should be avoided The following are the most common methods of dealing with by-products: (a) By-product net realizable value is deducted from the total cost of the products (b) Total cost (main product and by-products if any) are deducted from total sales value of main and byproducts (c) By-product receipts are treated as incidental other income and transferred to general P&L account. This method is generally considered unsatisfactory except where the value is very small (d) By-products treated as joint products. This method is most appropriate where the value of a by-product is relatively large Joint-product costing Because joint products arise due to the inherent nature of the production process, it follows that none- of the products can be produced separately. The various products become identifiable at a point known as splitoff point. Up to that stage all costs are joint costs, By Lwanga, D A Page 47 subsequent to the split-off point any cost incurred can be identified with specific products and they are known as subsequent or additional processing costs Joint costs are costs of manufacturing process that produce two or more products simultaneously. When the product produced have “high total sales values compared with the total sales value of other products” (Horngren et al,2006) they are called joint products. There are several methods that can be used to allocate joint costs. Some of these methods include: i) Physical measure method ii) Net realizable value (NRV) method iii) Sales value at split-off point method We shall use example one below to illustrate how these methods are used: Example one: During the month of July, 2011 the Nyamisati Nakagawa Company processes a basic raw material through a manufacturing process that yields three products-products By Lwanga, D A Page 48 X, Y and Z. There were no opening inventories and the products are sold at split-off point without further processing. Details of the production process and the sales revenues are given below: Joint costs Product shs600,000 units sales value per unit X 40,000 shs7.50 Y 20,000 25.00 Z 60,000 3.33 Assume that all the output is sold during the period Required: Show how the above methods are used to allocate joint costs (a) Physical measures method Using this method, the cost allocation is a simple allocation of joint costs in proportion to volume. Each product is assumed to receive similar benefits from the joint cost, and is therefore charged with its proportionate share of total cost. The cost allocations using this method are as follows: Units Product produced Proportion Joint costs to total Cost per allocated unit Shs Shs By Lwanga, D A Page 49 X 40,000 Y 20,000 Z 60,000 120,000 1/ 1 3 200,000 5 /6 100,000 5 ½ 300,000 5 600,000 Note that this method assumes the cost per unit is the same for each of the products Thus, an alternative method of allocating joint costs is as follows: Cost per unit= (shs600,000/120,000)= shs5 (b) Sales value at split-off point method When the sales value at split-off point method is used, joint costs are allocated to joint products in proportion to estimated sales value of the production on the assumption that higher selling prices indicate higher costs. To certain extent, this method could better be described as a means of apportioning profits or losses, according to sales value, rather than a method for allocating costs. Using the information in example one, the allocations under the sales value method would appear as follows: By Lwanga, D A Page 50 Proportion of Joint Units Product produced Sales sales value to costs value total allocated Shs (%) shs X 40,000 300,000 30 180,000 Y 20,000 500,000 50 300,000 Z 60,000 200,000 20 1,000,000 (c) 120,000 600,000 Net Realizable Value (NRV) Method In example one above we assumed all products are sold at the split-off point and that no additional costs are incurred beyond that point. In practice however, it is likely that joint products will be processed individually beyond the split-off points and market values may not exist at this point. To estimate the sales value at splitoff point, it is therefore necessary to use the estimated sales value at the point of sales and then work backwards. The net realizable value at split-off point can be estimated by deducting from the sales revenue the further processing costs at the point of sale. By Lwanga, D A Page 51 Assume the same situation in example one except that further processing costs now apply. Details of the production process and sales revenue are given below Joint costs shs600,000 Further processing Product Sales Costs Value Shs Shs X 80,000 300,000 Y 100,000 500,000 Z 20,000 200,000 The calculation of the net realizable value and the allocation of joint costs using this method is as follows: Estimated Costs net realizable Beyond value at split-off split-off value point point to total allocated Shs shs shs (%) shs X 300,000 80,000 220,000 27.5 165,000 Y 500,000 100,000 400,000 50.0 300,000 Z 200,000 20,000 180,000 22.5 135,000 1,000,000 200,000 Sales Product proportion 800,000 joint costs 600,000 By Lwanga, D A Page 52 Note: The joint costs are allocated in proportion to each product’s net realizable value at split-off point Example two: The following data relates to three joint products: A B C Sales value shs18,000 shs15,000 shs24,000 Selling costs 4,500 1,000 3,500 Weight (kg) 240 150 180 Joint costs are shs35,000. Required: Calculate the profit made by each product apportioning joint costs on: a) Sales value basis b) Physical basis Solution: By Lwanga, D A Page 53 (a) Apportionment on sales value Product Sales value costs apportioned Apportionment Shs shs A x35,000= 24,000 14,737 ( 24,000/57.000) B x35,000 = 18,000 11,053 (18,000/57,000) C x35,000 = 15,000 9,210 (15,000/57,000) 57,000 35,000 Profit statement Product C Total shs A B Shs shs shs Sales value 15,000 57,000 24,000 18,000 By Lwanga, D A Page 54 Less: apportioned costs (14,737) (9,210) (35,000) Selling costs (1,000) (9,000) Profit 4,790 (11,053) (3,500) (4,500) 5,763 2,447 13,000 Apportionment on physical unit basis Product weight apportioned apportionment costs A 11,053 180 (180/570) x shs35,000 B 737 240 (240/570) x shs35,000 C 9,210 150 (150/570) x shs35,000 14, 570 shs35,000 Profit Statement Product C A B Total By Lwanga, D A Page 55 Shs shs 24,000 18,000 (11,053) (14,737) Selling costs (1,000) (9,000) (3,500) (4,500) Profit 4,790 9,447 1,237 shs shs Sales value 15,000 57,000 Less: Apportioned costs (9,210) (35,000) 13,000 Example three: (Assignment) Two products X and Y are produced from the same material. The material costs shs0.95 per kg and the products appear after Process 1 X can be sold directly but Y needs further processing in Process 2 The following data relate to one period Materials Overheads Labour Total By Lwanga, D A Page 56 Process shs 1 15,000 shs 144,000 shs shs 21,000 180,000 2 18,000 10,000 28,000 Product (kg) Sales Kg sold Closing stock X shs52,500 30,000 15,000 Y shs150,750 45,000 There were no materials on hand at the end of the period Required: Calculate: (a) The unit price of X and its market value at splitoff point (b) The total joint cost to be apportioned between the two products By Lwanga, D A Page 57 (c) The total cost of X and Y using the sales value method of apportionment. Example four: (a) Explain why is it necessary to allocate joint costs to products (b) Describe three different methods of allocating joint costs to products (c) Explain the factors that should influence the choice of method when allocating joint costs to products (d) Describe the accounting treatments of by-product COST-VOLUME-PROFIT ANALYSIS By Lwanga, D A Page 58 Objective of C-V-P analysis The objective of CVP analysis is to establish what will happen to the financial results if a specified level of activity or volume fluctuates. This information is vital to the management, since one of the most important variables influencing sales level, total costs and profits, is output or volume. For this reason output is given special attention, since knowledge of this relationship will not enable management to identify the critical output levels such as levels at which neither profit nor loss will occur. C-V-P analysis is based on the relationship between volume and sales revenue and costs and profits in the short-run, the short-run normally being a period of one year, or less in which the output of the firm is restricted to that available from the current operating capacity. In the short run some inputs can be increased but others cannot. For example, additional supplies of materials can be obtained at short notice, but it takes time to expand the capacity of plant and machinery. Thus output is limited in the short run because plant capacity cannot be expanded. It also takes time to reduce capacity and therefore in a short-run a firm must operate on a relatively constant stock of production resources. Furthermore, most of the costs and prices of a firm’s products will have already been determined, and the major area of uncertainty will be sales volume. Short-run profitability will therefore be sensitive to sales volume on the level of profits in the short-run Basic terminologies Relevant range Break-even- point Contribution margin Margin of safety Margin of safety is the excess of budgeted (or actual) sales over the break even volume of sales. It states the amount by which the sales can drop before losses begin to be incurred. The formula for calculation is as follows: Margin of safety= total budgeted (or actual) sales-break even sales The margin of safety can also be expressed in percentage form. This percentage is obtained by dividing the margin of safety in shillings terms by total sales: Margin of safety percentage= margin of safety in shillings Total budgeted (or actual) sales Target profit analysis By Lwanga, D A Page 59 CVP formulas can be used to determine the sales volume needed to achieve a target profit. One method is the use of the equation method we have discussed. Instead of solving for units sales where profits are zero, you instead solve for units of sales are shillings amount (e.g. in the forthcoming example shs30 000) Sales=variable expenses+ fixed expenses + profits Alternatively, Units sold to attain a target profit= Fixed expenses+ target profit Unit contribution margin Example one: Tema Beach Entertainment Ltd operate in the leisure and entertainment industry and one of it’s activities is to promote concerts at locations throughout Tanzania. The company is examining the viability of a concert in Mwanza. Estimated fixed costs are Shs6,000,000. These include the fees paid to the performers, the hire of venue and advertising costs. Variable costs of the costs of prepacked buffet which will be provided by a firm of caterers at a price, which is currently being negotiated, but is likely to be in a region of Shs1000 per ticket sold. The proposed price for the sale of a ticket is Shs2000. The management of Tema Beach has requested the following information: a) The number of tickets that must be sold to break-even (that is, the point at which there is neither profit or loss) b) How many tickets must be sold to earn Shs3,000,000 target profit? c) What profit would result if 8000 tickets were sold? d) What selling price would have to be charged to give a profit of Shs3,000,000 on sales of 8,000 tickets, fixed cost of Shs6,000,000 and variable costs of Shs1,000,000 per ticket? e) How many additional tickets must be sold to cover the extra costs of television advertising of Shs800,000? Example two: Aziz Ally Co manufactures and sells a single product. Price and cost data regarding the company’s product and operations are as follows: Tshs Selling price per unit Tshs 2,500 Variable costs per unit: By Lwanga, D A Page 60 Raw materials 1,100 Direct labour 500 Manufacturing overheads 250 Selling expenses 130 Total variable expenses 1,980 Annual fixed costs: Manufacturing overheads 19,200,000 Selling and administration costs 27,600,000 Total fixed costs 46,800,000 Required: (a) Calculate the break-even point in units and shillings (b) The management is considering reducing the selling price to Tshs2,400 or spend on an advertising Tshs5,000,000 in order to increase the level of demand. What is the level of sales in units that will make the company earn the same profits whatever the scheme is adopted? Example three: (a)Mention and explain the three important assumptions of break-even-analysis (b) The management of Company X is anxious to improve the company’s profits performance and has asked for several items of information Total Per unit Sales (20,000 units) 1,200,000 60 Less: Variable costs 900,000 45 Contribution margin 300,000 15 Less: fixed costs 240,000 Net income 60,000 Required: By Lwanga, D A Page 61 (i) Compute the company’s break-even point in both units and shillings value. Compute the company’s margin of safety in both shillings and percentage form (ii) Assume that sales increase by shs400,000 next year. If cost behavior patterns remain unchanged, by how much company’s net income increase? Use the CM ratio to determine your answer Example Four: A fresh graduate from one of the VETA colleges is contemplating whether to start a brick making business. After carrying out a brief market research he came up with the following estimates per brick Direct material cost Tshs150 Direct labour cost 50 Variable overhead cost 40 240 In addition the following costs have been paid each month if he decides to start the business Rental for the premises Tshs45,000 Rental for the brick machine 60,000 Watchman’s salary 50,000 Other miscellaneous fixed expenses 25,000 Total fixed costs per month 180,000 He would be nearby competitors are selling each brick at shs320/=each and he believes he will have to charge about the same price Required: (a)What is the monthly break-even point in both units and sales value? (b)What is the total contribution margin at break-even point? (c) How many units will he need to sell each month to earn a target profit of Tshs360,000 each month? (d)Suppose the owner of premises increases rent by Tshs720,000, but at the same time selling price increases to shs360 per brick. What will be the new break-even point? By Lwanga, D A Page 62 (e) Mention at least five assumptions of the computations you made above (i.e. of break- even analysis Example five: You have recently graduated at CBE with a Diploma in Business Studies and you have been appointed the Production Manager of KTM Company Ltd. The company produces pairs of Khanga to be sold within and outside the country. The following costs need to be incurred in production of each pair of Khanga: Shs Raw materials 1,500 Direct labour 1,200 Variable overheads 1,300 In addition to the above, the following costs are incurred: Salaries shs4,000,000 Advertisement 3,000,000 Rent 5,000,000 Currently, the company produce and sell 15,000 pairs of Khanga at a price of shs5,000 per pair. Required: (a) Compute the break-even point in a number of pairs of Khanga sold and in shillings (b) How many pairs of Khanga should be produced and sold to earn a profit of shs1,000,000? Construction of Break-even Charts Break-even Charts are used to find out profit/loss at a specific level of activity. These charts are based on the principles of marginal costing. A break-even Chart may be defined as graph which shows profit or loss at different levels of activity within the limited range. The break even chart is also known as cost volume profit chart. Contribution/sales graph This is a simple form of break-even chart. It is also known as profit volume chart. This chart shows the profit or loss at various levels of sales. At zero level of activity the loss is equal to total fixed costs. The fixed costs along Y axis is joined by a straight line to the break-even point of sales and then this line is extended to the profit point against the present sales By Lwanga, D A Page 63 Example: You are required to prepare from the following information: (a) A break-even Chart (b) Contribution/sales graph or profit volume graph (c) Show the margin of safety in these charts if actual level of output is 20,000 units. Selling price per unit Shs100 Variable cost per unit Fixed costs Shs50 Shs600,000 Solution: In order to draw break-even-chart, we assume the following levels of output and show the relevant sales and costs against these levels output Level of output Units 5,000 Fixed costs variable costs Shs 600,000 shs 250,000 total costs shs sales shs profit/loss shs 850,000 500,000 (350,000) 10,000 “ 500,000 1,100,000 1,000,000 (100,000) 15,000 “ 750,000 1,350,000 1,500,00 20,000 “ 1,000,000 1,600,000 150,000 2,000,000 400,000 We draw the sales and cost curves on the bases of the sales figures (levels of activity) above (refer lecture notes on drawing graphs) Assumptions underlying C-V-P Analysis 1) The behavior of total costs and total revenue have been reliably determined over relevant range 2) All costs may be divided into fixed and variable elements 3) Fixed costs remain unchanged over the relevant volume range of break-even analysis 4) Total variable costs are directly proportional to the volume 5) Selling price per unit remains constant 6) A single product is being sold, and where than one products are being sold, this done in a constant mix. 7) Volume is the only relevant factor affecting costs. Of course other factors also affect costs and sales Ordinary cost-volume-profit analysis is a crude oversimplification when these factors are unjustifiably ignored. By Lwanga, D A Page 64 8) There is little or no change in ending and beginning inventory. INCOME EFFECTS OF ALTERNATIVE COST ACCUMULATION SYSTEMS (MARGINAL AND ABSORPTION COSTING SYSTEMS) Tutorial Note: By Lwanga, D A Page 65 The main difference between marginal and absorption costing principles lies in the treatment of fixed manufacturing overheads. Whereas marginal costing treats fixed manufacturing overheads/costs as period costs, absorption costing system treats these costs as product costs and forms part of inventory valuation. Marginal costing is used for internal reporting whereas absorption costing is used for external reporting. Absorption Costing may be defined as a technique whereby all costs are absorbed into production and there is no distinction between variable and fixed costs. The stocks and WIP contain both fixed and variable elements. In this system, fixed factory overheads, are absorbed on the basis of predetermined overhead rate based on the normal capacity. Under/over absorbed overheads are adjusted before computing the profit for the period. Closing stock is also valued at cost which includes fixed factory overhead. Absorption costing is a traditional approach and is also known as Conventional Costing or Full Costing. Production overheads are recovered by absorbing them into a cost of the product. The main aim of absorption costing is to recover overheads in a way that fairly reflects the amount of time and effort that has gone into making a product or service Absorption costing involves the following stages: Allocation and apportionment of overheads Reapportionment of service (non-production) cost Centre overheads Absorption of overheads Marginal Costing Under this technique, only variable manufacturing costs are charged as product costs and included in inventory valuation. Fixed manufacturing costs are not allotted to products but are considered as period costs and thus charged directly to the profit and loss account for that period. Fixed costs do not enter in stock valuation. Both marginal and absorption costing treat non- manufacturing costs (i.e. administration, selling and distribution overheads) as period costs. i.e. these are not inventoriable costs. Product and Period Costs Product costs are those costs which become a part of production costs. Such costs are included in inventory valuation. Period costs, on the other hand, are those costs which are not associated with production. Such costs are treated as expenses of the period in which they were incurred. Distinction between Marginal and Absorption Costing Principles By Lwanga, D A Page 66 The points of distinction between marginal and absorption costing are summarized as follows: 1- Treatment of fixed and Variable costs. In marginal costing, only variable costs are charged to products. Fixed costs are treated as period costs and charged to profit and loss account of the period. In absorption costing all costs (fixed and variable are charged to products. The fixed factory overhead is an absorption in units produced at the rate pre- determined on the basis of normal capacity utilization (and not on the basis of actual overheads) 2- Valuation of stocks In marginal costing, stocks of WIP are valued at marginal costs only. In absorption costing stocks are valued at total cost which includes both fixed and variable costs. Thus, stock values in marginal costing are lower than that in absorption costing 3- Measurement of Profitability In marginal costing, relative profitability of products or departments is based on the study of relative contribution made by respective products or departments. The managerial decisions are thus guided by the contribution. In absorption costing relative profitability is judged by profit figure which is also a guiding factor for managerial decisions. Differences in Profits under Marginal and Absorption Costing Profits under the two systems may be different because of the difference in the stock valuation. Position in this regard is summarized as follows: 1- Production equals to sales: Marginal Costing profit=Absorption costing profit 2- Production more than sales Closing stock more than opening stock Absorption costing profit>marginal costing profit This is because in absorption costing a part of fixed overhead included in closing stock value is carried forward to the next accounting period in the form of closing stock. 3-Production less than sales When production during the period is less than sales i.e. when opening stock is more than closing stock By Lwanga, D A Page 67 Marginal costing profit> absorption costing profit This is because under absorption costing cost of goods sold is higher because a part of fixed cost from preceding period is added to the current year’s cost of goods sold in the form of opening stock Advantages of absorption costing 1- Fixed costs are related to the production 2- This method is more logical for fixing selling prices 3- Profits can be calculated more accurately Advantages of Marginal Costing 1234- Fixed costs are not taken because they are incurred on time basis Under/over absorption of overheads does not arise** This method is more simple It helps to assess the effects of alternative policies Example one: A small Company that produces a single product has the following cost structure Number of units produced 6,000 Variable costs per unit shs Direct materials 2 Direct labour 4 Variable manufacturing overheads 1 Fixed costs per year Fixed manufacturing overheads 30,000 Fixed selling and administration expenses 10,000 Required: By Lwanga, D A Page 68 (a)Compute the unit product cost under absorption costing method (b) Compute the unit product cost under variable/marginal costing method Example two: The following data relates to a manufacturing company Number of units produced per year 6,000 Variable costs per unit shs Direct materials 2 Direct labour 4 Variable manufacturing overhead 1 Variable selling and administration expenses 3 Fixed costs per year Fixed manufacturing overhead 30,000 Fixed selling and administration expenses 10,000 Units in beginning inventory 0 Units produced 6,000 Units sold 5,000 Units in ending inventory 1,000 Selling price per unit shs20 Required: (a)Prepare income statement using: By Lwanga, D A Page 69 i) ii) (b) Absorption costing Variable costing Prepare a reconciliation schedule Example three: Tumbi Motors Limited assembles and sells motor vehicle. It uses an actual costing system. In which unit costs are calculated on a monthly basis. Data relating to the month of March,2004 is as given below:Particulars Units Opening inventory 150 Production 400 Sales Shs 520 Variable Cost Data: Manufacturing cost per unit produced 10,000 Distribution costs per unit sold 3,000 Fixed Cost Data: Manufacturing Costs 2,000,000 Marketing Costs 600,000 The selling price per motor vehicle is Shs24,000. (a) Prepare an income statement for Tumbi Motors Ltd under:(i) Variable Costing By Lwanga, D A Page 70 (ii) Absorption Costing (b) Clearly explain the differences between (a) (i) and (ii) above for the month of March Example five: In the year 2011 20,000 units of Karabaka were produced and sold. Costs and revenues were Sales Production costs: Variable Fixed Administrative and selling overheads Fixed Shs 100,000 35,000 15,000 25,000 Required: Prepare operating statements based on both adsorption and marginal costing Assume the level of activity is 25,000 units, what would be the effect. Catarina Co. management wants to prepare an income statement for 2011 (the fiscal year just ended) to evaluate the performance of telescope product line. The operating information for the year is: Units Beginning inventory 0 Production 8,000 Sales 6,000 Ending inventory 2,000 Actual price and cost data for 2011 are: Shs Selling price 1,000 Variable manufacturing cost per unit: Direct material 110 Direct manufacturing labour 40 By Lwanga, D A Page 71 Manufacturing overhead 50 Total variable manufacturing cost per unit 200 Variable marketing cost per unit sold 185 Fixed manufacturing costs (all indirect) 1,080,000 Fixed marketing costs (all indirect) 1,380,000 Required: (a) Compute inventoriable costs per unit produced in 2011 under (i) Marginal costing (ii) Absorption costing (b) Prepare profit statements for the year 2011 under (i) Marginal costing (ii) Absorption costing (c) Clearly explain the difference between profits in (b)(i) and (b)(ii) above Example seven: (a) Differentiate between direct costs and direct costing (b) Distinguish between period costs and product costs (c) Why does the direct costing or variable costing theorists exclude fixed manufacturing costs from inventory valuations (d) In the process of determining a proper sales price, what kind of cost figures are likely to be most helpful? By Lwanga, D A Page 72 OPERATION AND SERVICE COSTING Operation costing Operation costing is a hybrid costing system that employs certain aspects of job order costing and process costing systems. It is also referred to as specification costing. In an operation costing system goods are manufactured in batches that have some common characteristics as well as some individual characteristics. In such situations each batch is charged with specific materials where labour and overheads are accumulated by operation or process and then assigned to batches on a per unit basis Operation costing is used in manufacturing processes where the conversion activities are very similar across all of different types of products but the materials used in the various products differ significantly. Examples of industries where operation costing is applied include clothing and shoe making. In these industries production is undertaken in batches, each batch representing a particular style or decision. Batches of production are charged with specific cost of materials (a feature of job-order costing) whereas conversion costs are charged to batches on the basis of the same per unit cost regardless of design or style (a feature of process costing) Thus, in operation costing system, whereas direct materials are traced to the final product, conversion costs are not specifically traced to batches produced In order to apply conversion costs of each operation to batches produced in an operation costing system, an average conversion cost of each operation is computed using budgeted figures for each operation: Average conversion costs=budgeted conversion costs/budgeted activity Service costing By Lwanga, D A Page 73 Service costing is a cost accounting system concerned with establishing the costs of services rendered. Although the system deals with intangible services the accounting procedures used are the same as if the company was engaged in the production of tangible goods. In such cases input costs include labour and overheads that are part of the service provided In consulting, public sector and similar service oriented organizations, the organization collects costs by departments as well as by job or client. In some cases they also maintain work in progress in their internal records, representing cost of services rendered but not yet billed Examples of areas where service costing is applied include transport, tourism, hotels, financial services, education, etc. Service costing is also applied in a manufacturing setting where, for example, a manufacturing company wishes to establish the costs of services such as catering, accounting, information technology, etc. Differences between service and product costing There are two differences between service and product costing There are no or very few materials in service costing. Inventories in most cases comprises supplies only Overhead is the most significant portion of costs, of which labour contributes the largest portion of cost Key issues in service costing Service costing involves the following key issues Selecting cost units Establishing cost centres Selecting an appropriate rate for charging customers for service rendered The selection of cost units is not easy task since in most cases the cost of services is related to several factors. For example, transportation cost depends on such as distance and weight. Therefore, a problem arises of determining a cost of unit that represents a suitable measure of the service provided. In most cases a composite cost unit is considered most appropriate, for example ton-km, patient days, For each organization will have to determine what cost unit is most appropriate for its own purposes. The cost unit selected is then used to determine the cost per unit Cost per service unit= total cost per period/number of service units provided By Lwanga, D A Page 74 The second key issue is tom establish cost centers for the purpose of cost allocation and apportionment. Again the decision on appropriate cost center will depend on the type of services and the organization structure along which such services are provided. Likewise, the selection of an appropriate charging rate for services will depend on the nature of service provided By Lwanga, D A Page 75