Test of anti-islanding protections according to IEC 62116: an experimental feasibility assessment F. Belloni, P. Groppelli, C. Chiappa, R. Chiumeo, C. Gandolfi Ricerca sul Sistema Energetico – RSE s.p.a. – via Rubattino 54, 20134, Milano, Italy Email: belloni@rse-web.it, Piero.Groppelli@rse-web.it, Claudio.Chiappa@rse-web.it, Riccardo.Chiumeo@rse-web.it, Chiara.Gandolfi@rse-web.it Abstract - One of the main issues concerning the Inverter based Distributed Generators (DGs) is the possibility that inverters could feed parts of the public grid, even when the grid is disconnected from the main power system. Such a condition, that is called unwanted island, is potentially critical both for safety and for consumers’ operations. In order to avoid unwanted islands, it’s mandatory equipping the generating plant with an Interface Protection (IP) which has to detect the islanding condition and, in this case, to disconnect the generator from the public grid. Several methods for identifying island condition have been proposed, both passive and active, each one characterized by its pros and cons. The standard IEC 62116 was promulgated with the aim of regulating a test procedure to evaluate the IP effectiveness of PhotoVoltaic (PV) inverters independently from the island detection method implemented. The paper discusses the test procedure proposed by the standard IEC 62116 and presents some experimental activities developed by RSE spa, aimed at the assessment of test feasibility and effectiveness. Index Terms - Anti-islanding protections, Distributed Generators, Photovoltaic Inverters I. INTRODUCTION The growing installed power from Distributed Generators (DG) is changing the traditional paradigm in which the primary substation is the only power source of a distribution grid. The presence of a significant number of power sources along the entire distribution system gives rise to phenomena and issues which do not occur in a more conventional passive distribution scheme. In this scenario one of the main issues is the possibility that inverters could feed parts of the public grid, even when the grid is disconnected from the main power system, due to a protection trip or to maintenance on the utility side. Such a condition is called unwanted island and it is potentially critical both for safety, since a part the distribution grid remains energized even if disconnected from the rest of the system, and for consumers’ operations, since the island voltage level and frequency are not related with those of the mains grid, but only related to the power balance between DG and loads [1, 2]. In order to avoid unwanted islands, it’s mandatory equipping each grid-connected generating unit with an Interface Protection (IP) whose purpose is to detect the occurrence of a loss of mains and, in this case, to disconnect the generator from the public grid [3]. Several methods for islanding detection have been proposed and developed. They can be classified in three main categories: • passive methods [4], which are based only on the monitor of the local measurements at the DG’s Point of 978-1-4799-3254-2/13/$31.00 ©IEEE Common Coupling PCC (such as voltage, frequency, phase and/or their rate of variation); in this case the island condition is detected when parameters run out of the required thresholds; • active methods [2, 5÷7], which intentionally introduce a perturbance in the grid in order to amplify the quantities deviation from nominal values; • communication-based methods: recent standards have introduced the possibility of a forced trip of the IP, that is driven by an external signal under the control of distribution system operators [3]. The most traditional passive methods based protections, also used in the Italian electric system, are based on voltage and frequency measurements: • over-voltage; • under-voltage; • over-frequency; • under-frequency. Even though passive methods are easier and less expensive to implement with respect to the active ones, they show some difficulties about the proper setting of the admissible parameter ranges. Narrow ranges may lead to recurring IP unwanted trips and unnecessary DG disconnections, while wide ranges may fail the island detection. The main drawback of this methods is the so called Non-Detection Zone (NDZ). In other words, passive methods are unable to detect islanding if the mismatch between the DG generated power and loads consumption in the island is small [4, 6]. Such limitation is partially overcome by active island detection methods, which introduce perturbations in the current injected purposely by the inverter to unbalance the power generation and absorption. Even though more effective than passive methods, also active detection methods have some limitations and drawbacks: • NDZ still exists for some specific load impedances; • unwanted trips can be caused by other disturbance signals coming from the grid; • the perturbing signals injected into the grid may be disturbing for other grid connected systems. In order to assess the effectiveness of islanding prevention measures, independently from their implementation and from the adopted island detection method, the International Electrotechnical Commission (IEC) proposed the IEC 62116 standard [8], where a test procedure for the IP of utility interconnected photovoltaic generators has been indicated. This work describes the RSE experimental and theoretical activities for the feasibility assessment of the IEC 62116 test procedures. The paper is organized as follows: Section II describes the IEC 62116 test procedure and in Section III the relation between power unbalance and island voltage/frequency is deduced; Section IV reports the testing rig and Section V show the activities performed on three different PV inverters; finally, some remarks of the test procedure feasibility and effectiveness are given in the conclusions. II. IEC 62116 TEST DESCRIPTION The main goal of the standard IEC62116 is to provide a test procedure to evaluate the reliability of islanding prevention measure that is implemented by the inverters used to connect PV plant to the grid. The experimental arrangement for the IEC 62116 tests is shown in Figure 1 [8]. Equipment Under Test (EUT) continues to supply the load before the IP operation. The test must be repeated for different active and reactive power conditions: • the balance condition (resonance), corresponding to the (1) ÷ (4), between generation and load; • the controlled unbalance conditions, in accordance with the set of (ΔP, ΔQ) percentage unbalances that are reported in TABLE I1. TABLE I PERCENT POWER UNBALANCE CONDITIONS FOR IEC 62116 TESTS. -10, +10 -5, +10 0, +10 +5, +10 +10, +10 -10, +5 -5, +5 0, +5 +5, +5 +10, +5 -10, 0 -5, 0 0, 0 +5, 0 +10, 0 -10, -5 -5, -5 0, -5 +5, -5 +10, -5 -10, -10 -5, -10 0, -10 +5, -10 +10, -10 It’s worthwhile to note that the central line is related to variations of only active power, while the central vertical column is the related to variations of only reactive power. The IP passes the test if both the following results for the recorded run-up time are satisfied: • it has to be less than 2 s in each transient; • in each unbalanced condition of the white area of TABLE I, it has to be less than that in the balanced one (cell 0,0); if not, the tests must be extended to the greyshaded area. III. RELATIONS BETWEEN POWER UNBALANCE AND ISLAND Figure 1: Experimental arrangement for the IEC 62116 test procedure. The test procedure can be applied both to single phase and three phase inverters. In particular this standard defines that a suited behavioural model of a portion of a distribution grid during island operation can be obtained neglecting line transversal parameters, and considering the parasitic capacitances to ground and the loads as lumped parameters element, that are equivalent to a parallel Resistive-InductiveCapacitive (RLC) impedance. The prescribed test consists in connecting a PV inverter in parallel to a power grid (or a power grid simulator) and to a local adjustable RLC load with given resonance characteristics. The nominal load conditions are: 2 0 V = Pinv R Q L = QC (2) f 0 = 1 2π LC = 50 Hz (3) Qf = R C / L =1 (4) Pload = ( ) (1) Where V0 is the nominal grid voltage, QL is the inductive reactive power, QC the capacitive one, f0 is the nominal resonance frequency and Qf is the quality factor. When the system is at the steady state, the test begins by the opening of the switch S1 (Figure 1). The test consists in measuring the time, the so called run-up time, for which the VOLTAGE AND FREQUENCY When the load is supplied by both the inverter and the grid (switch S1 and S2 of Figure 1 are closed), voltage and frequency are kept almost constant at their nominal values, V0 and f0. In this case the grid supplies an amount of active and reactive power equal to the difference between the active powers that are supplied by the inverter and absorbed by the load [9]. During the island condition (switch S1 open), voltage and frequency must change values to V1 and f1 in order to keep the power balance between load and generation. If the inverter supplies power at unitary power factor the follow general equations can be considered: V12 R + ΔR f1 = 1 2π (L + ΔL )(C + ΔC ) (5) Pinv = ( ) (6) where R+ΔR, L+ΔL and C+ΔC are the actual values of the load representative of the test power unbalance (TABLE I). Combining (3) and (6) and defining fmin and fmax the trip values of under-frequency relay and over-frequency relay respectively, it’s possible to obtain the following relations: 1 In particular, the active power unbalances are generated modifying the resistive load, while reactive power unbalances are induced acting either on the inductive component of the load or on the capacitive one. f1 − f 0 LC = −1 f0 ( L + ΔL )(C + ΔC ) f min − f 0 ≤ f0 (7) LC f − f 0 (8) − 1 ≤ max f0 ( L + ΔL )(C + ΔC ) Considering only small variations of the parameters (ΔLΔC~0), the relation (8) can be written as: 2 2 ⎛ f0 ⎞ ΔC ΔL ⎛ f 0 ⎞ ⎜⎜ ⎟⎟ − 1 ≤ ⎟ −1 + ≤⎜ C L ⎜⎝ f min ⎟⎠ ⎝ f max ⎠ (9) Assuming ΔQ the unbalance between the reactive power inverter generated and the load absorbed one, after the loss of mains, the following relation comes from (4), (5), (6) : ΔQ ⎛ ΔC ΔL ⎞ = −Q f ⎜ + ⎟ P L ⎠ ⎝ C (10) Combining (9) and (10) a relation between the NDZ of the frequency protections and the reactive power unbalance can be obtained: ⎡ ⎛ f ⎞ 2 ⎤ ΔQ ⎡ ⎛ f ⎞2 ⎤ Q f ⎢1 − ⎜⎜ 0 ⎟⎟ ⎥ ≤ ≤ Q f ⎢1 − ⎜⎜ 0 ⎟⎟ ⎥ P ⎢⎣ ⎝ f max ⎠ ⎥⎦ ⎢⎣ ⎝ f min ⎠ ⎥⎦ (11) A similar relation linking the NDZ of voltage protections and active power unbalance, ΔP, can be obtained from (5): 2 2 ⎛ V0 ⎞ ΔP ⎛ V0 ⎞ ⎟⎟ − 1 ≤ ⎜⎜ ⎟ −1 ≤⎜ P ⎜⎝ Vmin ⎟⎠ ⎝ Vmax ⎠ IV. THE EXPERIMENTAL ARRANGEMENT The system represented in Figure 1 has been implemented at the RSE laboratory in Piacenza (Italy). It consists of: • a DC source with PV array VI characteristic emulation feature (P=20 kW, Vmax=500 V); • a single/three phase connection to the public LV grid (alternatively, a 12 kVA grid simulator is available); • a data acquisition system which monitors AC and DC measurements and allows on-line calculations of active, reactive power and root-mean-square (RMS) values; the Supervision system offers some visual tool to easily check the power balance between generator and load; an example of the Man to Machine visual Interface (MMI) of the data acquisition system is shown in Figure 3; • an adjustable parallel RLC load (single or three phase) with overall power capability up to 18 kW (resistive) and ±18 kVAr (inductive and capacitive). A power absorption from 2 kW/±2 kVAr to 18 kW/±18 kVAr can be set through series/parallel connections of load elements, and small power variations (up to about ±5 % of the nominal value) can be produced for every load component. In implementing each load component, particular care was given in minimizing the parasitic effects. Some details of the resistive load actual implementation are shown in Figure 4. Manually operated switches and differential relays, for safety purposes, complete the experimental set-up. An overview of the laboratory environment is shown in Figure 5. (12) where Vmin and Vmax are the lower and upper limits of the NDZ of the voltage relay. A typical NDZ for a passive island detection method based on the measurements of voltage and frequency is reported in Figure 2 [7]. If the active/reactive power unbalance between generation and load are within the NDZ, the loss of mains is not detected by the IP and the island remains supplied by the inverter. Figure 3: Topological diagram of the experimental set-up (taken from the data acquisition system visual interface). Figure 2: Non Detecting Zone for an Interface Protection with passive island recognition. According to relation (11) frequency variations are mainly related to reactive power unbalances, while active power unbalances are responsible for voltage variations (12). Figure 4: Resistive component of the load. The wirewound resistor is implemented so that inductive parasitic effects are minimized. V. EXPERIMENTAL RESULTS The IP of three different Low Voltage (LV) single and three phase PV inverters, rated 3 kW, 6 kW and 10 kW respectively, are tested according to the IEC 62116 standard. All of them adopt the passive island recognition criterion based on measurements of frequency and voltage with the same setting, reported in TABLE II. TABLE II INTERFACE PROTECTIONS SETTINGS Protection relay Threshold value Intentional Delay Inv I Inv II e III Over-voltage 110% VN 50 ms 200 ms Under-Voltage 90% VN 50 ms 100 ms Over-frequency 50.3 Hz 50 ms 100 ms Under-Frequency 49.7 Hz 50 ms 100 ms In the follow the experimental results are presented. The nominal values of the LV grid are V0=230V and f0=50Hz. A. Single phase 3 kW PV inverter The actual balance condition corresponds to: • PV array power: PN=2.8 kW; • AC side inverter active power: 2.7 kW; • load active power: 2650 W; • capacitive/inductive reactive power: 2.7 kVAr. With reference to the Figure 6, the loss of mains occurs at t=2 s and is fully corresponding to the zeroing of the frominverter-to-grid current (white curve). According to the previous calculated load values, the island voltage and frequency would be V1=232.16 V and f1=50.02 Hz well, within the NDZ of the IP. Indeed, the load remains supplied by the inverter for some minutes after the loss of mains, as shown in Figure 6, where the island voltage waveform is shown in green, the inverter currents are reported in blue and the grid current in white. Figure 6: Voltage and current waveforms recorded by the data acquisition system during a test in balanced power conditions for a 3 kW inverter. The periodic voltage drop of the green waveform of Figure 6 is due to the Maximum Power Point Tracking (MPPT) algorithm implemented within the inverter control. The voltage remains above 90% VN even during these phenomena and no under-voltage protection trip occurs. The IP fails the test also for some unbalanced conditions with small excess of capacitive reactive power. B. Single phase 6 kW PV inverter In this case, the actual balance condition at the rated inverter power is: • PV array power: PN=5.6 kW; • AC side inverter active power: 5.5 kW; • load active power: 5.5 kW, • capacitive/inductive reactive power: 5.5 kVAr. Even though the balance condition is expected to give rise to an island, according to theoretical calculations (voltage and frequency within the NDZ of the IP), an island condition for more than few hundreds milliseconds was never recorded. An example of recorded test result is shown in Figure 7. In this case the IP trips in 70 ms. Many comparable results were obtained for unbalanced conditions and for reduced PV array power (66% PN and 33% PN). Figure 7:Voltage and current waveforms recorded by the data acquisition system during a test in balance power conditions for a 6 kW inverter. To explain the experimental results, a simulation model of the experimental set-up is developed in the ATPDraw environment. In general the modelling activities are mainly focused on: • confirming relations among power unbalances and island voltage and frequency; • forecasting the behavior of the inverter, grid and IP in different conditions; • explaining experimental results (even though the simulation model represents a three phase inverter and the actual inverter is single phase, the overall behavior remains the same). The grid frequency simulated is reported in Figure 8 for the power balanced case (i.e. equations (1)÷(4) are satisfied). The loss of mains occurs at t=1.0 s, (the frequency deviation visible at t=1.0 s is due to some transient voltage perturbation occurring at the loss of mains). In Figure 9 the current (red curve) and voltage (green curve) simulated in case of power balance during island are presented. Then, a reasonable explanation of the ‘unexpected’ IP operation in balance condition (Figure 7) may be found in the active power variations introduced by the MPPT algorithm. This can cause enough large voltage drops to be detected by the under-voltage relay. Figure 8: Island frequency simulated with balance between generation and load. C. Three phase 10 kW inverter The tested three phase inverter offers some advanced features such as the Fault Ride Through (FRT) and the control of reactive power injection/absorption for grid voltage support. The inverter is tested in each condition, according to the TABLE I, also at reduced PV array power (66% PN and 33% PN). In every test case, the run-up time is less than 200 ms; the Figure 12 shows the voltage and currents measured in the balance condition. Voltage [V] 400 200 0 -200 -400 1.8 1.85 1.9 1.95 2 2.05 2.1 2.15 2.2 2.25 2.3 1.85 1.9 1.95 2 2.05 2.1 2.15 2.2 2.25 2.3 1.85 1.9 1.95 2 2.05 2.1 2.15 2.2 2.25 2.3 In the model, a “perturb and observe” MPPT algorithm is embedded within the PV inverter control, in order to take into account the power variations introduced by the MPPT itself. This algorithm is set to have an active power variation 300 ms after the loss of mains. Simulation results are presented in Figure 10 for a power variation of -5% PN and in Figure 11 for -10% PN. In both cases, the loss of mains occurs at t=1.0 s and the MPPT reduces the active power at 1.3 s, but only in case of a 10% active power reduction the islanding condition has been detected. 400 [V] 300 200 100 0 -100 -200 -300 -400 0,8 1,0 1,2 1,4 1,6 [s] 1,8 Figure 10: Voltage drop due to a -5% PN inverter power variation. 400 [V] 300 200 100 0 -100 -200 -300 -400 0,8 1,0 1,2 1,4 1,6 [s] 1,8 Figure 11: Voltage drop due to a -10% PN inverter power variation. 10 0 -10 -20 1.8 2 Current [A] Figure 9:Voltage and current waveforms simulated. Current [A] 20 1 0 -1 -2 1.8 Time [s] Figure 12: Experimental results for the test of island detection for a 10 kW inverter. Voltages are shown in the upper graph, inverter currents in the central one and from-inverter-to-grid currents in the lower one. Loss of mains occurs when the grid currents drop to zero. VI. CONCLUSIONS The main goal of the standard IEC 62116 is to provide a test procedure to evaluate the reliability of islanding prevention measure that must be implemented by the grid connected PV Inverters. The paper discusses the test procedure proposed by the standard IEC 62116 and shows the experimental activities oriented to its feasibility assessment made by RSE in 2012. The experimental results allow to claim the main IEC 62116 merit: the focus on the specific balance condition (QL=QC, PLOAD=PINV) as the most critical condition for island detection. Besides, thanks to the actual RSE implementation, it is possible to evaluate the most critical parts related to the test laboratory developments that are: • the implementation of the adjustable RLC load, which must have low parasitic parameters and high thermal stability and whose power should be adjustable ; • the difficulty to achieve a stable steady state with the desired match between power Inverter generation and load absorption before the loss of mains. At the same time, the reading of the experimental results points out some issues concerning this standard: • possible interactions among more inverters, are not considered; • the RLC load is not representative of all the possible grid loads, such as nonlinear or distorting loads. Finally, the experimental activities, made on three PV inverters (single and three phase), show the possibility of supporting island condition, also in presence of unbalanced power exchanges between generation and loads. Maximum Power Point Tracking algorithm plays an important role in creating power unbalances which is useful for the island detection. The phenomenon has been further investigated and confirmed also by simulations. REFERENCES [1] [2] [3] [4] ACKNOWLEDGEMENTS This work has been financed by the Research Fund for the Italian Electrical System under the Contract Agreement between RSE S.p.A. and the Ministry of Economic Development - General Directorate for Nuclear Energy, Renewable Energy and Energy Efficiency in compliance with the Decree of March 8, 2006. [5] [6] [7] [8] [9] Figure 5: Overview of the test laboratory. S. P. Chowdhurya, S. Chowdhurya, P.A. Crossleyb, “Islanding protection of active distribution networks with renewable distributed generators: A comprehensive survey”, Electric Power System Research Journal, Volume 79, Isuue 6, 2009, Page(s): 984 – 992. D. Menniti, A. Pinnarelli, N. Sorrentino, G. Brusco, “Islanding detection active methods: implementation of simulation models using ATP-EMTP”, 14th International Conference on Harmonics and Quality of Power (ICHQP), Bergamo, Italy, 26-29 Sept. 2010, pp. 1-8. CEI 0-21 “Regola tecnica di riferimento per la connessione di Utenti attivi e passivi alle reti BT delle imprese distributrici di energia elettrica”, Italian Standard, download: www.ceiweb.it, in Italian lenguage. Zhihong Ye; Kolwalkar, A.; Yu Zhang; Pengwei Du; Reigh Walling; "Evaluation of anti-islanding schemes based on nondetection zone concept", IEEE Transactions on Power Electronics, Volume: 19, Issue: 5, 2004, Page(s): 1171 – 1176. T. Thacker, F. Wang, R. Burgos, D. Boroyevich, “Islanding detection using a coordinate transformation based phase-locked loop”, Power Electronics Specialists Conference 2007. PESC 2007, 17-21 June 2007, Orlando (USA), Page(s): 1-6. M.G.M. Abdolrasol, S. Mekhilef, “Robust hybrid anti-islanding method for inverter based distributed generation”, IEEE Region 10 Conference, TENCON 2010, 21-24 Nov. 2010, Fukuoka (Japan), Page(s): 13-18. X. Zhu, C. Du, G. Shen, M. Chen, D. Xu, “Analysis of the Nondetection Zone with Passive Islanding Detection Methods for Current Control DG System”, Twenty-Fourth Annual IEEE Applied Power Electronics Conference and Exposition 2009. APEC 2009, 15-19 Feb. 2009, Washington DC (USA), Page(s): 358 - 363. IEC 62116 “Test procedure of islanding prevention measure for utility interconnected photovoltaic inverters”, Ed.1.0, 09 2008. Zengqiang Mi, Fei Wang, "Power Equations and Non-Detection Zone of Passive Islanding Detection and Protection Method for Grid Connected Photovoltaic Generation System", Pacific-Asia Conference on Circuits, Communications and Systems, 2009. PACCS '09, 2009, Page(s): 360 – 363.