Uploaded by NEET KATHIRIA

7 Project Cash flows

advertisement
Project Cash Flows
Introduction
• Organization involved in implementation of project, receives and spends different
amounts of money at different points of time
• A cash flow diagram is a visual representation of the inflow and outflow of funds
• This inflow and outflow does not follow a particular pattern
• It is however, assumed that all transactions take place either at the beginning or
end of a particular period (week, month, quarter, year etc.)
• eg., if it is decided that all transactions in a month will be recorded as having
occurred on the last day of that month, or first day of that month, either
approach can be followed provided the system is consistently followed.
Cash Flow Diagram
• In a cash flow diagram, time is drawn on X axis in an appropriate scale in terms of
weeks, months, year etc. ; Y axis represents the amount involved in the
transaction.
• Receipts and payments are drawn on positive and negative sides respectively on
the Y axis. Representation on Y axis may not be to the scale but should be
proportional.
• Amount of transaction is written on the side of arrow.
•
•
Time
0
1
2
3
n-1
n
+ve incoming
- ve outgoing
Example
• The details of transactions during the months of April, may and June for Alpha
Industries are given below. Draw a cash flow diagram for the transactions using
month as a single unit showing all transactions during a month at the end of
that month.
Example
Date
Description
Amount
(Rs.)
April 05
Receipt of running account bill #9
150,000
April 10
Salary disbursement
80,000
April 16
Payment for supply of aggregates
20,000
April 21
Payment for supply of stationery
5,000
May 07
Receipt for RA bill # 10
May 10
Salary disbursement
80,000
May 28
Payment for supply of cement
50,000
June 06
Receipt for running account bill #11
June 10
Salary disbursement
June 16
Payment for supply of structural steel
100,000
June 28
Payment of rent of premises for July and August
100,000
180,000
250,000
80,000
Compound Interest
• Given transactions are summarised as given below :
Month
Receipts (Rs.)
Expenditure (Rs.)
April
150,000
105,000
May
180,000
130,000
June
250,000
280,000
Total
580,000
515,000
Cost & Revenue Cash Flow Diagrams
• In construction economics, we come across two main types of problems :
• (i) income expansion and (ii) Cost reduction
• Correspondingly, the cash flow diagrams can also be distinguished as revenue
dominated and cost dominated cash flow diagrams
• In revenue dominated cash flow diagrams, incomes or savings are emphasized
while the latter diagrams largely concentrate on periodic costs or expenditures.
• Cash flow diagrams are frequently used to find the equivalence of money
received paid or received at different times and many other objectives.
Cost & Revenue Cash Flow Diagrams
• Cost Dominated Cash Flow :
• Revenue Dominated Cash Flow :
Project Cash Flow Diagram
• In the earlier problem, the information on the cash transactions and period of
their occurrence was available.
• In practice, we have to derive this information from some conditions.
• Based on the concepts of cash flow diagram discussed earlier, we can draw cash
flow diagram for a project as also for a company.
• The former is known as project cash flow diagram while the latter is known as
company cash flow diagram.
• Project cash flow diagram is a graphical representation of receipts and
disbursements versus time. Time is generally represented in months.
Project Cash Flow Diagram : Information Required
• Gross bill value and its time of submission
• Measurement period – Contractors are generally paid once in a month. These
conditions are found in ‘terms of payment’ of the contract.
• Certification time taken by the Owner.
• Retention money deducted by the owner and the time to release the retention
money.
• Mobilization advance and other advances and their terms of recovery
• Details of costs incurred by the contractor for raising a particular bill value.
• Credit period
Factors Affecting Project Cash Flow
• Profit Margin – Profit margin is the excess over costs. Thus higher the margin in a
project, the better it is for Contractor’s cash flow.
• Retention – Retention tends to reduce the margin obtained from a project. In
case of very low margins, actual margin after retention can reduce to zero also.
Retention affects contractor’s cash flow in a negative manner. Higher the
retention bigger is the cash flow problem. These days, contractors request for
retention in form of a Bank Guarantee.
• Extra Claims – extra claims in a contract mainly result from extra work, changes
in quantities, changes in specifications etc. These claim take long time to settle
as they are not part of original contract. Sometimes they are settled even after
completion of project. Thus in practice extra claims tend to worsen the cash flow
position.
Factors Affecting Project Cash Flow
• Distribution of margin – Keeping the overall margin amount same, the margin
can be distributed across different items of project either in a uniform manner,
or it can be front and back loaded.
• Front loading means the items that are executed early, carry higher margin than
the item executed later which improves contractor’s cash flow although overall
margin derived from the project remains same. Back loading is reverse of front
loading.
• Delay in receiving payment from Client – Any delay in receiving payment from
the client, results in capital lock up.
• Delay in paying labour, plant hires, material suppliers and sub contractors – The
time interval between receiving goods or services and paying for these is the
credit the contractor receives from his suppliers.
Using cash Flow Diagrams
• Determining Capital Lock Up –
• While estimating the effect of margin and retention money on cash flows, one
can see that a contracting company faces negative cash flows in the early stages
of the project.
• This negative cash flow is the locked up capital that is supplied either from
internal reserves of the company or borrowed money.
• A company borrowing money has to pay interest
• A company utilising own funds has to forego interest on this money.
• The negative cash flow indicates the requirement of funds to execute the project
at a given instant.
Using cash Flow Diagrams
• Plot the month-wise cumulative cash out flows and cumulative cash inflows with
time on X axis.
• Plot the month wise net cash flow on Y axis with time on X axis.
Download