Reference Issue Publication date Compliance date NR/L2/CIV/140 12 04 March 2017 03 June 2017 User information User information This Network Rail standard contains colour-coding according to the following Red–Amber– Green classification. Red requirements – no variations permitted • Red requirements are to be complied with and achieved at all times. • Red requirements are presented in a red box. • Red requirements are monitored for compliance. • Non-compliances will be investigated and corrective actions enforced. Amber requirements – variations permitted subject to approved risk analysis and mitigation • Amber requirements are to be complied with unless an approved variation is in place. • Amber requirements are presented with an amber sidebar. • Amber requirements are monitored for compliance. • Variations can only be approved through the national variations process. • Non-approved variations will be investigated and corrective actions enforced. Green guidance – to be used unless alternative solutions are followed Guidance should be followed unless an alternative solution produces a better result. Guidance is presented with a dotted green sidebar. Guidance is not monitored for compliance. Alternative solutions should be documented to demonstrate effective control. Page 2 of 10 Reference Issue Publication date Compliance date NR/L2/CIV/140 12 04 March 2017 03 June 2017 Compliance This Network Rail standard/control document is mandatory and shall be complied with by Network Rail Limited and its contractors if applicable from 3rd June 2017. Where it is considered not reasonably practicable1 to comply with the requirements in this standard/control document, permission to comply with a specified alternative should be sought in accordance with the Network Rail standards and controls process, or with the Railway Group Standards Code if applicable. If this standard/control document contains requirements that are designed to demonstrate compliance with legislation they shall be complied with irrespective of a project’s GRIP stage. In all other circumstances, projects that have formally completed GRIP Stage 3 (Option Selection) may continue to comply with any relevant Network Rail standards/control documents that were current when GRIP Stage 3 was completed. NOTE 1: Legislation includes Technical Specifications for Interoperability (TSIs). NOTE 2: The relationship of this standard/control document with legislation and/or external standards is described in the purpose of this standard. Disclaimer In issuing this standard/control document for its stated purpose, Network Rail Limited makes no warranties, expressed or implied, that compliance with all or any standards/control documents it issues is sufficient on its own to provide safety or compliance with legislation. Users are reminded of their own duties under legislation. Compliance with a Network Rail standard/control document does not, of itself, confer immunity from legal obligations. Where Network Rail Limited has granted permission to copy extracts from Network Rail standards or control documents, Network Rail Limited accepts no responsibility for, nor any liability in connection with, the use of such extracts, or any claims arising there from. This disclaimer applies to all forms of media in which extracts from Network Rail standards and control documents might be reproduced. Supply Copies of standards/control documents are available electronically, within Network Rail’s organisation. Hard copies of this document might be available to Network Rail people on request to the relevant controlled publication distributor. Other organisations can obtain copies of this standard/control document from an approved distributor. 1 This can include gross proportionate project costs with the agreement of the Network Rail Assurance Panel (NRAP). Page 3 of 10 Reference Issue Publication date Compliance date NR/L2/CIV/140 12 04 March 2017 03 June 2017 Issue record Issue Date Comments 12 March 2017 Section 80 withdrawn. First issue of section 1700 11 June 2016 Section 90 withdrawn. First issue of section 1800 10 June 2010 Updated Sections 50 to 53 9 June 2010 Updated Sections 23 and 100 8 March 2010 Updated Model Clauses: Sections 70 to 79 7 Dec 2009 Updated Model Clauses: Sections 160 to 164 6 Sept 2009 Updated Model Clauses: Sections 200 to 204 5 6th June 2009 Updated Model Clauses: Sections 170 to 176 4 December 2008 Updated Model Clauses: Sections 110 to 114 3 August 2008 Updated Model Clauses 2 June 2008 Superseded Issue 1 of RT/CE/S/140 and Issue 1 of RT/CE/C/008 1 April 2004 Superseded RT/CE/P/008 Page 4 of 10 Reference Issue Publication date Compliance date NR/L2/CIV/140 12 04 March 2017 03 June 2017 Contents 1 Purpose 6 2 Scope 6 3 Roles and responsibilities 6 4 Definitions and abbreviations 6 5 Referencing of Model Clauses 7 6 Format of Model Clauses 7 7 Work not covered by the Model Clauses 8 8 Index of Model Clauses 8 Page 5 of 10 Reference Issue Publication date Compliance date 1 NR/L2/CIV/140 12 04 March 2017 03 June 2017 Purpose The purpose of this standard is to define the requirements for the production and use of Model Clauses for specifying Civil Engineering Works. The Model Clauses incorporated into the Technical Workscope should meet the relevant requirements of Group Standards and Network Rail standards and also reflect industry good practice, so that the Contact documentation for the Works will; 2 contain all the necessary technical requirements for quality, buildability, maintainability, serviceability and decommissioning, be consistent in format and content, be able to be produced without undue time and effort. Scope This standard covers the use of Model Clauses for Civil Engineering Works that may be undertaken on the rail network. The Clauses are appended to this standard, and an index of them is provided in 8. 3 Roles and responsibilities The Specifier shall: 4 1 Use the Model Clauses appended to this standard when preparing the Technical Workscope: only those relevant to the Works should be included in the Workscope. 2 Prepare suitable wording to cover elements of work not covered by the appended Model Clauses: all such additional Clauses shall comply with the requirements of the relevant Group Standards and Network Rail standards. Where appropriate, advice on the suitability of the wording shall be sought from the Professional Head of Buildings and Civils. Definitions and abbreviations Technical Workscope The Section of the Contract documentation which provides all the project-specific information; defines the specification, implementation standards and assurance requirements; and incorporates the appropriate Model Clauses for the Works. Works The design, construction and maintenance of a structure which is located on, supports or crosses Network Rail property. Page 6 of 10 Reference Issue Publication date Compliance date 5 NR/L2/CIV/140 12 04 March 2017 03 June 2017 Referencing of Model Clauses Each Section of the Model Clauses is referenced individually: for example, NR/L3/CIV/140/010C. 1 The first two letters identify the document as a Network Rail standard. 2 The following letter and number define the type of standard - in this case Level 3. 3 The next three letters define the ownership of the standard - in this case Civil Engineering. 4 The next three numbers define the standard number - in this case 140. 5 The last three numbers refer to the Section of the Model Clauses that form the Appendix to this standard - in this case Section 10. 6 The final letter is one other of the following: o C - this suffix identifies that part of the Appendix as a Model Clause. o N - this suffix identifies that part of the Appendix as Notes for Guidance for a Specifier. These provide (a) advice on the selection of alternative text for some Model Clauses, (b) the template for these alternatives, (c) references and (d) information on the relationship between various Clauses. o GN - this suffix identifies that part of the Appendix as a Guidance Note. 6 Format of Model Clauses At present, the Model Clauses (suffix C) are provided in one or other of the following formats: 1 The parts issued before 1st June 2008 are provided in both read-only (pdf) and Word versions. 2 Those issued from 1st June 2008 on are provided in a read-only (pdf) version, and form the main document. These shall not be amended by the Specifier without the prior approval of the Head of Structures; where approval is given the amended Clause shall be included in the appendices document. In both cases, the accompanying Notes for Specifiers (suffix N) are provided in both read-only and Word versions. The latter version includes those Model Clauses that may be amended by the Specifier to suit the Works at hand: where these Clauses are used they form the appendices document. Page 7 of 10 NR/L2/CIV/140 12 04 March 2017 03 June 2017 Reference Issue Publication date Compliance date 7 Work not covered by the Model Clauses Where the proposed contract involves elements of work not covered by the appended Model Clauses, the Specifier shall prepare suitable wording to cover such elements, and incorporate this into the appendices document. All such additional Clauses shall comply with the requirements of the relevant Group Standards and Network Rail standards. Where appropriate, advice on the suitability of the wording shall be sought from the relevant Head of Asset. 8 Index of Model Clauses Section Title 10 21 22 23 25 30 - 35 General Aerial Survey Land and Trackwork Surveys Structural Repair Survey Presentation of Survey Data and Information Ground Investigation 30: General Requirements for Ground Investigation 31: Schedule 1: Information 32: Schedule 2: Exploratory Holes 33: Schedule 3: Employer’s Representative’s Facilities 34: Schedule 4: Specification Amendments 35: Schedule 5: Specification Additions Demolition and Site Clearance General requirements for Earthworks and Excavations Excavations Earthworks Grouting of Embankments General Requirements for Piling Precast Concrete Piles Cast-in-place Piles Steel Piles Timber Piles Testing of Piles General Requirements for Embedded Retaining Walls Diaphragm Walls Embedded Retaining Walls constructed using Bored Concrete Piles Sheet Pile Walls Structural Concrete withdrawn Structural Concrete Repairs Concrete for Ancillary Purposes Steelwork (BS 5400) withdrawn Structural Steelwork Repairs Bearings Guidance Note for the specification of bearings 40 50 51 52 53 70 71 72 73 74 75 76 77 78 79 80 83 85 90 93 100 100GN Issue of Section 2 1A 1A 2 1A 1C Publication date June 2008 Sept 1996 Sept 1996 June 2010 Sept 1996 Dec 1996 2 2 2 2 2 2 2 2 2 2 2 2 2 June 2008 Sept 2010 Sept 2010 Sept 2010 Sept 2010 March 2010 March 2010 March 2010 March 2010 March 2010 March 2010 March 2010 March 2010 2 March 2010 2 2 2 2 1B 1A 2 2 March 2010 Aug 2008 Aug 2008 Aug 2008 Jan 1996 Feb 1997 June 2010 June 2010 Page 8 of 10 NR/L2/CIV/140 12 04 March 2017 03 June 2017 Reference Issue Publication date Compliance date 110 111 112 113 114 120 121 122 123 124 125 126 130 - 134 140 & 141 150 153 160 161 162 163 164 160GN 170 171 172 173 174 175 176 180 - 182 185 & 186 General requirements for Waterproofing Underline Bridges Tightly bonded systems for Underbridge Bridges Loose-laid systems for Underline Bridges Waterproofing road carrying Bridges Tanking General Requirements for Bridge Installation Methods and Temporary Works Bridge Installation by Sliding or Rolling Bridge Installation by Large Capacity Crane Bridge Installation Using Self Propelled Lifting Vehicles Temporary Works Tunnels Constructed Using a Shield Bridge Installation by Thrust Boring Temporary Bridges Inspection of New Steelwork, Precast Concrete, Protective Treatment and Waterproofing 130: General Requirements for Inspection 131: Inspection of New Steelwork 132: Inspection of Precast Concrete 133: Inspection of Protective Treatment 134: Inspection of Waterproofing Steelwork (BS 5950) withdrawn 140: Steelwork Hot Rolled Sections withdrawn 141: Steelwork Cold Formed Sections withdrawn Brickwork, Blockwork and Masonry Brickwork and Masonry Repairs General requirements for structural timber Design requirements for structural timber Workmanship for structural timber Maintenance and repair of structural timber Timber preservation and fire protection Guidance Note for structural timber General requirements for protective treatments Maintenance coating works Protective coating of new structural steelwork Protective coating of existing structural steelwork and ironwork Protective coating of timber surfaces Protective coating of concrete and masonry surfaces Protective coating systems Building and Structure Drainage 180: General Requirements for Drainage 181: Materials 182: Installation Track Drainage 185: Track Drainage 186: Maintenance of Track Drainage 2 Dec 2008 2 2 2 2 Dec 2008 Dec 2008 Dec 2008 Dec 2008 3 June 2008 3 3 3 3 3 3 June 2008 June 2008 June 2008 June 2008 June 2008 June 2008 1A Jan 1997 1B March 1996 1C 1A 2 2 2 2 2 2 2 2 2 Sept 1994 May 1997 Dec 2009 Dec 2009 Dec 2009 Dec 2009 Dec 2009 Dec 2009 June 2009 June 2009 June 2009 2 June 2009 2 2 2 1C June 2009 June 2009 June 2009 March 1996 1B Jan 1997 Page 9 of 10 NR/L2/CIV/140 12 04 March 2017 03 June 2017 Reference Issue Publication date Compliance date 190 & 191 200 201 202 203 204 210 211 212 213 214 215 216 217 218 219 220 221 225 226 227 230 230GN 231 232 233 240 250 - 253 255 - 257 1700 1800 External Service Ducts and Cable Troughing 190: Ducts 191: Cable Troughing General Requirements for Roads and Pavings Subgrade and Formation Works Road Pavements Kerbs, Footways and Paved Areas Traffic Signs and Road Markings Permanent Way General Permanent Way Design Installation of New and Renewal of Existing Permanent Way Permanent Way Acceptance Standards Inspection of Permanent Way Maintenance of Permanent Way Permanent Way Materials Construction Standards for Permanent Way Permanent Way Small Plant, Tools and Equipment Permanent Way Ancillary Equipment Permanent Way Incident Management Permanent Way for Bridgework Permanent Way Particular Specification (Plain Line Renewals) Permanent Way Particular Specification (S&C Renewals) Permanent Way Particular Specification for Bridgeworks General Requirements for Level Crossings Level Crossing Guidance Notes for Specifiers Public Vehicular Level Crossings Occupation and Accommodation Level Crossings Footpath, Bridleway and Other Minor Types of Level Crossings Fencing and Gates Landscaping 250: Preparation of Topsoil 251: Grass Seeding and Turfing 252: Planting of Shrubs and Trees 253: Maintenance of Landscaped Works Management of Lineside Vegetation 255: General Requirements for the Management of Lineside Vegetation 256: Weedkilling 257: Tree Felling and Scrub Clearance Structural concrete Structural steelwork 1C Feb 1996 2 2 2 2 2 1B 1B Sept 2009 Sept 2009 Sept 2009 Sept 2009 Sept 2009 Mar 1997 Mar 1997 1B Mar 1997 1B 1B 1B 1B 1B 1B 1B 1B 1A Mar 1997 Mar 1997 Mar 1997 Mar 1997 Mar 1997 Mar 1997 Mar 1997 Mar 1997 Mar 1997 1B Mar 1997 1A Mar 1997 1A Mar 1997 1A 1A 1A 1A Jan 1997 Jan 1997 Jan 1997 Jan 1997 1A Jan 1997 2 1C June 2008 March 1996 1B March 1996 1 1 March 2017 June 2016 Page 10 of 10 Standard and control document briefing note Ref: NR/L2/CIV/140 Issue: 12 Title: Model Clauses for Civil Engineering Works Publication date: 04/03/2017 Compliance Date: 03/06/2017 Standard/Control Document Owner: Head of Structures Non-compliance rep (Approver of TRACKER applications): Ben Wilkinson, Principal Engineer, Track and Civils Technical lead/contact for briefings: Ben Wilkinson, Principal Engineer, Track and Civils Tel: 07801334269 Purpose: The purpose of this standard is to define the requirements for the production and use of Model Clauses for specifying Civil Engineering Works. The Model Clauses incorporated into the Technical Workscope should meet the relevant requirements of Group Standards and Network Rail standards and also reflect industry good practice, so that the Contact documentation for the Works will; contain all the necessary technical requirements for quality, buildability, maintainability, serviceability and decommissioning; be consistent in format and content; be able to be produced without undue time and effort. Scope: This standard covers the use of Model Clauses for Civil Engineering Works that may be undertaken on the rail network. The Clauses are appended to this standard, and an index of them is provided in 8. What’s new/ what’s changed: These are new modules of NR/L2/CIV/140. A new concrete specification has been added to the Model Clauses for Civil Engineering Works that complies with the Structural Eurocodes. This specification has the same basis as Highway’s England guidance. The previous concrete specifications are withdrawn as these are based on British Standards that have been superseded. Affected documents: Reference Impact NR/L2/CIV/140 ISSUE 11 Superseded NR/L3/CIV/140/80C ISSUE 2 Withdrawn NR/L3/CIV/140/80N ISSUE 2 Withdrawn NR/L2/CIV/140/1700C ISSUE 1 New issue NR/L2/CIV/140/1700N ISSUE 1 New issue Briefing requirements: Technical briefings are given to those who have specific responsibilities within this standard/control document. Awareness briefings are given to those who might be affected by the content but have no specific responsibilities within the standard/control document. Details of the briefing arrangements are included in the associated briefing programme. Briefing T Senior Design Engineer Infrastructure Projects Responsible for cascade briefing? Y/N N T Principal [Structures] Design Engineer Infrastructure Projects N T Programme Engineering Manager Infrastructure Projects Y Post (A-Awareness/ Function T-Technical) T Senior Project Engineer Infrastructure Projects N T Senior Design Engineer Infrastructure Projects N T Infrastructure Head of Design Infrastructure Projects N T Route Asset Manager [Buildings and Civils] Network Operations Y T Senior Asset Engineer [Buildings and Civils] Network Operations N A Chief Buildings and Civils Engineer N A Head of Engineering Safety, Technical and Engineering Infrastructure Projects A Head of Structures N A Head of Buildings A Buildings and Civils team Safety, Technical and Engineering Safety, Technical and Engineering Safety, Technical and Engineering N N N NOTE: Contractors are responsible for arranging and undertaking their own Technical and Awareness Briefings in accordance with their own processes and procedures.