Uploaded by dfaizal89

NR L2 CIV 140

advertisement
Reference
Issue
Publication date
Compliance date
NR/L2/CIV/140
12
04 March 2017
03 June 2017
User information
User information
This Network Rail standard contains colour-coding according to the following Red–Amber–
Green classification.
Red requirements – no variations permitted
•
Red requirements are to be complied with and achieved at all times.
•
Red requirements are presented in a red box.
•
Red requirements are monitored for compliance.
•
Non-compliances will be investigated and corrective actions enforced.
Amber requirements – variations permitted subject to approved risk analysis and
mitigation
•
Amber requirements are to be complied with unless an approved variation is in place.
•
Amber requirements are presented with an amber sidebar.
•
Amber requirements are monitored for compliance.
•
Variations can only be approved through the national variations process.
•
Non-approved variations will be investigated and corrective actions enforced.
Green guidance – to be used unless alternative solutions are followed

Guidance should be followed unless an alternative solution produces a better result.

Guidance is presented with a dotted green sidebar.

Guidance is not monitored for compliance.

Alternative solutions should be documented to demonstrate effective control.
Page 2 of 10
Reference
Issue
Publication date
Compliance date
NR/L2/CIV/140
12
04 March 2017
03 June 2017
Compliance
This Network Rail standard/control document is mandatory and shall be complied
with by Network Rail Limited and its contractors if applicable from 3rd June 2017.
Where it is considered not reasonably practicable1 to comply with the requirements
in this standard/control document, permission to comply with a specified alternative
should be sought in accordance with the Network Rail standards and controls
process, or with the Railway Group Standards Code if applicable.
If this standard/control document contains requirements that are designed to
demonstrate compliance with legislation they shall be complied with irrespective of a
project’s GRIP stage. In all other circumstances, projects that have formally
completed GRIP Stage 3 (Option Selection) may continue to comply with any
relevant Network Rail standards/control documents that were current when GRIP
Stage 3 was completed.
NOTE 1: Legislation includes Technical Specifications for Interoperability (TSIs).
NOTE 2: The relationship of this standard/control document with legislation and/or external standards
is described in the purpose of this standard.
Disclaimer
In issuing this standard/control document for its stated purpose, Network Rail Limited
makes no warranties, expressed or implied, that compliance with all or any
standards/control documents it issues is sufficient on its own to provide safety or
compliance with legislation. Users are reminded of their own duties under legislation.
Compliance with a Network Rail standard/control document does not, of itself, confer
immunity from legal obligations.
Where Network Rail Limited has granted permission to copy extracts from Network
Rail standards or control documents, Network Rail Limited accepts no responsibility
for, nor any liability in connection with, the use of such extracts, or any claims arising
there from.
This disclaimer applies to all forms of media in which extracts from Network Rail
standards and control documents might be reproduced.
Supply
Copies of standards/control documents are available electronically, within Network
Rail’s organisation. Hard copies of this document might be available to Network Rail
people on request to the relevant controlled publication distributor. Other
organisations can obtain copies of this standard/control document from an approved
distributor.
1
This can include gross proportionate project costs with the agreement of the Network Rail
Assurance Panel (NRAP).
Page 3 of 10
Reference
Issue
Publication date
Compliance date
NR/L2/CIV/140
12
04 March 2017
03 June 2017
Issue record
Issue
Date
Comments
12
March 2017
Section 80 withdrawn. First issue of section 1700
11
June 2016
Section 90 withdrawn. First issue of section 1800
10
June 2010
Updated Sections 50 to 53
9
June 2010
Updated Sections 23 and 100
8
March 2010
Updated Model Clauses: Sections 70 to 79
7
Dec 2009
Updated Model Clauses: Sections 160 to 164
6
Sept 2009
Updated Model Clauses: Sections 200 to 204
5
6th June 2009
Updated Model Clauses: Sections 170 to 176
4
December 2008
Updated Model Clauses: Sections 110 to 114
3
August 2008
Updated Model Clauses
2
June 2008
Superseded Issue 1 of RT/CE/S/140 and Issue 1
of RT/CE/C/008
1
April 2004
Superseded RT/CE/P/008
Page 4 of 10
Reference
Issue
Publication date
Compliance date
NR/L2/CIV/140
12
04 March 2017
03 June 2017
Contents
1
Purpose
6
2
Scope
6
3
Roles and responsibilities
6
4
Definitions and abbreviations
6
5
Referencing of Model Clauses
7
6
Format of Model Clauses
7
7
Work not covered by the Model Clauses
8
8
Index of Model Clauses
8
Page 5 of 10
Reference
Issue
Publication date
Compliance date
1
NR/L2/CIV/140
12
04 March 2017
03 June 2017
Purpose
The purpose of this standard is to define the requirements for the production and use
of Model Clauses for specifying Civil Engineering Works. The Model Clauses
incorporated into the Technical Workscope should meet the relevant requirements of
Group Standards and Network Rail standards and also reflect industry good practice,
so that the Contact documentation for the Works will;
2

contain all the necessary technical requirements for quality, buildability,
maintainability, serviceability and decommissioning,

be consistent in format and content,

be able to be produced without undue time and effort.
Scope
This standard covers the use of Model Clauses for Civil Engineering Works that may
be undertaken on the rail network.
The Clauses are appended to this standard, and an index of them is provided in 8.
3
Roles and responsibilities
The Specifier shall:
4
1
Use the Model Clauses appended to this standard when preparing the
Technical Workscope: only those relevant to the Works should be included
in the Workscope.
2
Prepare suitable wording to cover elements of work not covered by the
appended Model Clauses: all such additional Clauses shall comply with
the requirements of the relevant Group Standards and Network Rail
standards. Where appropriate, advice on the suitability of the wording
shall be sought from the Professional Head of Buildings and Civils.
Definitions and abbreviations
Technical Workscope
The Section of the Contract documentation which provides all the project-specific
information; defines the specification, implementation standards and assurance
requirements; and incorporates the appropriate Model Clauses for the Works.
Works
The design, construction and maintenance of a structure which is located on,
supports or crosses Network Rail property.
Page 6 of 10
Reference
Issue
Publication date
Compliance date
5
NR/L2/CIV/140
12
04 March 2017
03 June 2017
Referencing of Model Clauses
Each Section of the Model Clauses is referenced individually: for example,
NR/L3/CIV/140/010C.
1
The first two letters identify the document as a Network Rail standard.
2
The following letter and number define the type of standard - in this case
Level 3.
3
The next three letters define the ownership of the standard - in this case
Civil Engineering.
4
The next three numbers define the standard number - in this case 140.
5
The last three numbers refer to the Section of the Model Clauses that form
the Appendix to this standard - in this case Section 10.
6
The final letter is one other of the following:
o C - this suffix identifies that part of the Appendix as a Model Clause.
o N - this suffix identifies that part of the Appendix as Notes for Guidance
for a Specifier. These provide (a) advice on the selection of alternative
text for some Model Clauses, (b) the template for these alternatives, (c)
references and (d) information on the relationship between various
Clauses.
o GN - this suffix identifies that part of the Appendix as a Guidance Note.
6
Format of Model Clauses
At present, the Model Clauses (suffix C) are provided in one or other of the following
formats:
1
The parts issued before 1st June 2008 are provided in both read-only (pdf)
and Word versions.
2
Those issued from 1st June 2008 on are provided in a read-only (pdf)
version, and form the main document. These shall not be amended by the
Specifier without the prior approval of the Head of Structures; where
approval is given the amended Clause shall be included in the appendices
document.
In both cases, the accompanying Notes for Specifiers (suffix N) are provided in both
read-only and Word versions. The latter version includes those Model Clauses that
may be amended by the Specifier to suit the Works at hand: where these Clauses
are used they form the appendices document.
Page 7 of 10
NR/L2/CIV/140
12
04 March 2017
03 June 2017
Reference
Issue
Publication date
Compliance date
7
Work not covered by the Model Clauses
Where the proposed contract involves elements of work not covered by the
appended Model Clauses, the Specifier shall prepare suitable wording to cover such
elements, and incorporate this into the appendices document. All such additional
Clauses shall comply with the requirements of the relevant Group Standards and
Network Rail standards. Where appropriate, advice on the suitability of the wording
shall be sought from the relevant Head of Asset.
8
Index of Model Clauses
Section
Title
10
21
22
23
25
30 - 35
General
Aerial Survey
Land and Trackwork Surveys
Structural Repair Survey
Presentation of Survey Data and Information
Ground Investigation
30: General Requirements for Ground Investigation
31: Schedule 1: Information
32: Schedule 2: Exploratory Holes
33: Schedule 3: Employer’s Representative’s Facilities
34: Schedule 4: Specification Amendments
35: Schedule 5: Specification Additions
Demolition and Site Clearance
General requirements for Earthworks and Excavations
Excavations
Earthworks
Grouting of Embankments
General Requirements for Piling
Precast Concrete Piles
Cast-in-place Piles
Steel Piles
Timber Piles
Testing of Piles
General Requirements for Embedded Retaining Walls
Diaphragm Walls
Embedded Retaining Walls constructed using Bored
Concrete Piles
Sheet Pile Walls
Structural Concrete withdrawn
Structural Concrete Repairs
Concrete for Ancillary Purposes
Steelwork (BS 5400) withdrawn
Structural Steelwork Repairs
Bearings
Guidance Note for the specification of bearings
40
50
51
52
53
70
71
72
73
74
75
76
77
78
79
80
83
85
90
93
100
100GN
Issue of
Section
2
1A
1A
2
1A
1C
Publication
date
June 2008
Sept 1996
Sept 1996
June 2010
Sept 1996
Dec 1996
2
2
2
2
2
2
2
2
2
2
2
2
2
June 2008
Sept 2010
Sept 2010
Sept 2010
Sept 2010
March 2010
March 2010
March 2010
March 2010
March 2010
March 2010
March 2010
March 2010
2
March 2010
2
2
2
2
1B
1A
2
2
March 2010
Aug 2008
Aug 2008
Aug 2008
Jan 1996
Feb 1997
June 2010
June 2010
Page 8 of 10
NR/L2/CIV/140
12
04 March 2017
03 June 2017
Reference
Issue
Publication date
Compliance date
110
111
112
113
114
120
121
122
123
124
125
126
130 - 134
140 & 141
150
153
160
161
162
163
164
160GN
170
171
172
173
174
175
176
180 - 182
185 & 186
General requirements for Waterproofing Underline
Bridges
Tightly bonded systems for Underbridge Bridges
Loose-laid systems for Underline Bridges
Waterproofing road carrying Bridges
Tanking
General Requirements for Bridge Installation Methods
and Temporary Works
Bridge Installation by Sliding or Rolling
Bridge Installation by Large Capacity Crane
Bridge Installation Using Self Propelled Lifting Vehicles
Temporary Works Tunnels Constructed Using a Shield
Bridge Installation by Thrust Boring
Temporary Bridges
Inspection of New Steelwork, Precast Concrete,
Protective Treatment and Waterproofing
130: General Requirements for Inspection
131: Inspection of New Steelwork
132: Inspection of Precast Concrete
133: Inspection of Protective Treatment
134: Inspection of Waterproofing
Steelwork (BS 5950) withdrawn
140: Steelwork Hot Rolled Sections withdrawn
141: Steelwork Cold Formed Sections withdrawn
Brickwork, Blockwork and Masonry
Brickwork and Masonry Repairs
General requirements for structural timber
Design requirements for structural timber
Workmanship for structural timber
Maintenance and repair of structural timber
Timber preservation and fire protection
Guidance Note for structural timber
General requirements for protective treatments
Maintenance coating works
Protective coating of new structural steelwork
Protective coating of existing structural steelwork and
ironwork
Protective coating of timber surfaces
Protective coating of concrete and masonry surfaces
Protective coating systems
Building and Structure Drainage
180: General Requirements for Drainage
181: Materials
182: Installation
Track Drainage
185: Track Drainage
186: Maintenance of Track Drainage
2
Dec 2008
2
2
2
2
Dec 2008
Dec 2008
Dec 2008
Dec 2008
3
June 2008
3
3
3
3
3
3
June 2008
June 2008
June 2008
June 2008
June 2008
June 2008
1A
Jan 1997
1B
March 1996
1C
1A
2
2
2
2
2
2
2
2
2
Sept 1994
May 1997
Dec 2009
Dec 2009
Dec 2009
Dec 2009
Dec 2009
Dec 2009
June 2009
June 2009
June 2009
2
June 2009
2
2
2
1C
June 2009
June 2009
June 2009
March 1996
1B
Jan 1997
Page 9 of 10
NR/L2/CIV/140
12
04 March 2017
03 June 2017
Reference
Issue
Publication date
Compliance date
190 & 191
200
201
202
203
204
210
211
212
213
214
215
216
217
218
219
220
221
225
226
227
230
230GN
231
232
233
240
250 - 253
255 - 257
1700
1800
External Service Ducts and Cable Troughing
190: Ducts
191: Cable Troughing
General Requirements for Roads and Pavings
Subgrade and Formation Works
Road Pavements
Kerbs, Footways and Paved Areas
Traffic Signs and Road Markings
Permanent Way General
Permanent Way Design
Installation of New and Renewal of Existing Permanent
Way
Permanent Way Acceptance Standards
Inspection of Permanent Way
Maintenance of Permanent Way
Permanent Way Materials
Construction Standards for Permanent Way
Permanent Way Small Plant, Tools and Equipment
Permanent Way Ancillary Equipment
Permanent Way Incident Management
Permanent Way for Bridgework
Permanent Way Particular Specification (Plain Line
Renewals)
Permanent Way Particular Specification (S&C
Renewals)
Permanent Way Particular Specification for
Bridgeworks
General Requirements for Level Crossings
Level Crossing Guidance Notes for Specifiers
Public Vehicular Level Crossings
Occupation and Accommodation Level Crossings
Footpath, Bridleway and Other Minor Types of Level
Crossings
Fencing and Gates
Landscaping
250: Preparation of Topsoil
251: Grass Seeding and Turfing
252: Planting of Shrubs and Trees
253: Maintenance of Landscaped Works
Management of Lineside Vegetation
255: General Requirements for the Management of
Lineside Vegetation
256: Weedkilling
257: Tree Felling and Scrub Clearance
Structural concrete
Structural steelwork
1C
Feb 1996
2
2
2
2
2
1B
1B
Sept 2009
Sept 2009
Sept 2009
Sept 2009
Sept 2009
Mar 1997
Mar 1997
1B
Mar 1997
1B
1B
1B
1B
1B
1B
1B
1B
1A
Mar 1997
Mar 1997
Mar 1997
Mar 1997
Mar 1997
Mar 1997
Mar 1997
Mar 1997
Mar 1997
1B
Mar 1997
1A
Mar 1997
1A
Mar 1997
1A
1A
1A
1A
Jan 1997
Jan 1997
Jan 1997
Jan 1997
1A
Jan 1997
2
1C
June 2008
March 1996
1B
March 1996
1
1
March 2017
June 2016
Page 10 of 10
Standard and control document briefing note
Ref: NR/L2/CIV/140
Issue: 12
Title: Model Clauses for Civil Engineering Works
Publication date: 04/03/2017
Compliance Date: 03/06/2017
Standard/Control Document Owner: Head of Structures
Non-compliance rep (Approver of TRACKER applications): Ben Wilkinson, Principal Engineer, Track and Civils
Technical lead/contact for briefings: Ben Wilkinson, Principal Engineer, Track and Civils
Tel: 07801334269
Purpose:
The purpose of this standard is to define the requirements for
the production and use of Model Clauses for specifying Civil
Engineering Works. The Model Clauses incorporated into the
Technical Workscope should meet the relevant requirements of
Group Standards and Network Rail standards and also reflect
industry good practice, so that the Contact documentation for
the Works will;

contain all the necessary technical requirements
for quality, buildability, maintainability,
serviceability and decommissioning;

be consistent in format and content;

be able to be produced without undue time and
effort.
Scope:
This standard covers the use of Model Clauses for Civil
Engineering Works that may be undertaken on the rail network.
The Clauses are appended to this standard, and an index of them
is provided in 8.
What’s new/ what’s changed:
These are new modules of NR/L2/CIV/140.
A new concrete specification has been added to the Model Clauses for Civil Engineering Works that complies with the
Structural Eurocodes. This specification has the same basis as Highway’s England guidance.
The previous concrete specifications are withdrawn as these are based on British Standards that have been superseded.
Affected documents:
Reference
Impact
NR/L2/CIV/140 ISSUE 11
Superseded
NR/L3/CIV/140/80C ISSUE 2
Withdrawn
NR/L3/CIV/140/80N ISSUE 2
Withdrawn
NR/L2/CIV/140/1700C ISSUE 1
New issue
NR/L2/CIV/140/1700N ISSUE 1
New issue
Briefing requirements:
Technical briefings are given to those who have specific responsibilities within this standard/control document.
Awareness briefings are given to those who might be affected by the content but have no specific responsibilities within the standard/control document.
Details of the briefing arrangements are included in the associated briefing programme.
Briefing
T
Senior Design Engineer
Infrastructure Projects
Responsible for
cascade briefing?
Y/N
N
T
Principal [Structures] Design Engineer
Infrastructure Projects
N
T
Programme Engineering Manager
Infrastructure Projects
Y
Post
(A-Awareness/
Function
T-Technical)
T
Senior Project Engineer
Infrastructure Projects
N
T
Senior Design Engineer
Infrastructure Projects
N
T
Infrastructure Head of Design
Infrastructure Projects
N
T
Route Asset Manager [Buildings and Civils]
Network Operations
Y
T
Senior Asset Engineer [Buildings and Civils]
Network Operations
N
A
Chief Buildings and Civils Engineer
N
A
Head of Engineering
Safety, Technical and
Engineering
Infrastructure Projects
A
Head of Structures
N
A
Head of Buildings
A
Buildings and Civils team
Safety, Technical and
Engineering
Safety, Technical and
Engineering
Safety, Technical and
Engineering
N
N
N
NOTE: Contractors are responsible for arranging and undertaking their own Technical and Awareness Briefings in accordance with their own processes
and procedures.
Download