Uploaded by d818cc

Design Principles Of Earth Dams

advertisement
Log InJoin
The Constructor
The Constructor Navigation

Articles

Community

Categories

Case Studies
Report this ad
Design Principles Of Earth Dams
Home/ Water Resources/ Dams
Report this ad
Reading time: 2 minutes
Report this ad
Design of earth dams starts with calculation of forces acting on the dam structure. The loads
acting on earth dams is same as loads acting on gravity dams. Earth dams are made of non-rigid
materials i.e. soil.
2.9M
theconstructor.org - heavy construction equipment types
Fig: Earth Dam Structure
Report this ad
The design principles of earth dams:
1. The filling material to be used for earth dams should be sufficiently less permeable. 2. The
earth dams should be constructed by utilizing available materials in local area to serve the
intended purpose with low cost. In order to reduce the leads for carrying excavated earth, the
borrow pits should be as close to the dam site as possible. 3. Sufficient outlets and spillways
should be provided to avoid the possibility overtopping during design floods. 4. For frost
action, wave action and earthquake motions, sufficient freeboard must be provided. 5. If the
stability of foundations and embankments is not impaired by piping, sloughing etc., there
should be little harm in seepage through a flood control dam. But a conservation dam should be
as water-tight as possible. 6. To avoid sloughing of face of earth dam, the phreatic line i.e.
seepage line should be within the downstream face of the dam. 7. The downstream face must
be protected properly against rain, waves, up to tail water and the upstream face against wave
action. To reduce erosion due to flow of rain water horizontal berms may be provided at
suitable intervals in the downstream face. Ripraps may be provided on the entire upstream
slope and on the downstream slope near the toe so as to prevent erosion. 8. By providing
suitable horizontal filler drain or chimney drain or toe drain, the portion of the dam and
downstream of the impervious core should be properly drained. 9. There must be no possibility
of free flow of water from upstream to downstream face. 10. The upstream and downstream
slopes should be designed so as to be stable under worst conditions of loading. Such critical
conditions occur for the upstream slope during sudden downstream of the reservoir and for
the downstream slope during steady seepage under full reservoir. 11. The upstream slope and
downstream slope must be flat enough to provide sufficient base width at the foundation level,
such that the maximum shear stress developed remains well below the corresponding
maximum shear strength of the soil so as to provide suitable factor of safety. 12. Due to
development of excessive pore pressure and consequent reduction in shear strength of soil, the
stability of the embankment and foundations is very critical during construction or even after
the construction during the period of consolidation. So under this critical condition the
embankment slopes must remain safe.
Download