CHEVRON AUSTRALIA PTY LTD DESIGN BASIS FOR SEA TRANSPORT ANALYSIS For The GORGON PROJECT BARROW ISLAND LNG PLANT Document No.: G1-TE-S-OOOO-PDB0003 Revision: 0 1 Prepared by: P. Minchin ffG.MacAmh~ Reviewed by: P. McCarthy h l P McCarry CI () mJ1<~\ fJ.- (:fUCoJJL KJVG Approved by: ( D. Rowe IV ~~YA'~. I'Y"II.... D. Rowe ~ Approved by: J. Kelly J. Kelly Revision Date: 060ct09 06Aug10 Issue Purpose: IFD RFD Kellogg Joint Venture Gorgon , ,,~. . Quentin -htrill A..,(, CVX ~ . Chevron KBR flIeD) Pl:i HATCH-4"m:l!m!I "Confidential Property of Chevron Australia Pty Ltd. May be reproduced and used only in accordance with the express written permission of Chevron Australia Pty Ltd." Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD SUMMARY OF DOCUMENT REVISIONS Rev. No. Date Revised Section Revised A 31 Jul 09 - Issued for Client Review (ICR) 0 06 Oct 09 - Issued for Design (incorporating CVX comments) 1 06 Aug 10 1.3 4.4/ 4.5/ 4.6 4.7 5.2/ 5.3/ 5.4 5.5 7.1 - Revision Description References updated Grillage & Sea Fastenings updated Added Accelerations updated Wind speeds clarified Combinations updated Miscellaneous updates Business Page 2 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD TABLE OF CONTENTS 1. GENERAL 5 1.1 1.2 1.3 Background Scope of Document Applicable Documents 1.3.1 Project Documents 1.3.2 Codes and Standards Abbreviations Definitions 5 5 5 5 6 6 7 DESIGN DATA AND ASSUMPTIONS 8 2.1 2.2 8 8 1.4 1.5 2. 3. 4. OUTLINE PROCEDURE 9 3.1 3.2 9 9 11 4.1 4.2 4.3 4.4 4.5 11 11 11 12 13 13 15 17 17 17 17 17 18 19 20 21 22 22 22 4.7 Structural Model Orientation on Transport Vessel Transverse Location on Transport Vessel Support Conditions Modules 4.5.1 Grillages 4.5.2 Sea-fastenings 4.5.3 Uplift Restraints PARs 4.6.1 General 4.6.2 Elevated PARs 4.6.3 3 m PARs 4.6.4 6 m PARs 4.6.5 PARs < 12 m wide 4.6.6 PARs ≥ 12 m wide 4.6.7 Stacked PARs PAUs 4.7.1 PAUs 9 m or Wider 4.7.2 PAUs Less Than 9 m Wide LOADS 5.1 5.2 5.3 5.4 5.5 5.6 6. Description Application in StaadPro COMPUTER MODEL 4.6 5. Criteria & Assumptions Steel 24 Weight Vessel Motions - Modules Vessel Motions - PARs Vessel Motions – PAUs Wind Loads Vessel Deflection 24 24 25 25 26 26 BASIC LOAD CASES 28 6.1 28 28 28 28 6.2 Stage 1 – Static Loads Analysis 6.1.1 Static Loads 6.1.2 CG Envelope Stage 2 – Inertia Loads Analysis Business Page 3 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis 7. Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD DESIGN VERIFICATION 30 7.1 7.2 30 32 Load Combinations Code Checks Business Page 4 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis 1. GENERAL 1.1 Background Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD The Modules, PARs and PAUs for the Gorgon LNG Plant will be transported by sea from the fabrication yards in North-East or South-East Asia to Barrow Island, Australia. The modularised structures addressed in this Design Basis will be loaded out at the fabrication yard onto the transport vessel using self-propelled modular transporters (SPMT) or by lifting. On reaching Barrow Island, the structures will be moved to their design locations in the facility using SPMT. The transport vessels will be self-propelled and capable of weather routing to avoid the most severe cyclone conditions en route to Australia. If any structures are to be carried by barge, additional Sea Transport criteria will be developed. 1.2 Scope of Document This Design Basis describes the procedure to be used during Phase 4 (Detail Design) for the structural strength analysis of modularised structures for Sea Transport operations. The purpose of the analysis is to obtain forces and deflections in the structure for input to primary member and joint design. The Design Basis gives the principles and methods for determining forces on the structure, the modelling and analysis method, and defines the load combinations for code checking. Sea Transport is one of several design conditions for the structure. Other design conditions are covered in Reference [2] and referenced documents. 9 Any re-sizing of members and joints arising from the Sea Transport analysis must be done in conjunction with results from these other design conditions. Fatigue design, including the Sea Transport condition, is addressed in Reference [19]; the fatigue methodology for Sea Transport is described in Ref. [22]. 9 1 1.3 Applicable Documents The applicable CVX, KJVG documents, Codes, Industry Standards and Government Regulations are referenced below. 1.3.1 Project Documents The following are referenced or associated Project Documents: 1. G1-TE-S-0000-SPC0001 Design Requirements for Wind Loads 2. G1-TE-S-0000-SPC2001 Structural Steel Design Criteria 3. G1-TE-S-0000-SPC2002 Modularised Structural Steel Fabrication and Welding 4. G1-TE-S-0000-SPC2060 Structural Steel Fabrication and Welding 5. G1-TE-T-0000-SPC0002 Loadout and Seafastening Specification 6. G1-TE-Z-0000-REP1006 Module Weight Report 7. G1-TE-Z-0000-REP1014 PARs and PAUs Weight Report 8. G1-TE-S-0000-PDB0001 Design Basis for Structural Analysis Computer Model Business Page 5 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis 1.3.2 Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD 9. G1-TE-S-0000-PDB0002 Design Basis for Land Transport Analysis 10. G1-TE-S-0000-PDB0005 Design Basis for Primary Joints 11. G1-TE-T-0000-REP0005 Module Transportation Phase 4 Design Accelerations 12. G1-TE-T-0000-REP0007 PAR Transportation Phase 4 Design Accelerations 13. G1-TE-T-0000-REP0008 PAU Transportation Phase 4 Design Accelerations 14. G1-TE-T-0000-TCN0001 Design of Transportation Grillages and Seafastening Steelwork 15. G1-TE-T-0000-TCN0002 Module Transportation - Vessel Deflections 16. G1-TE-T-0000-TCN0003 PAR Transportation - Vessel Deflections 17. G1-TE-T-0000-TCN0004 PAU Transportation - Vessel Deflections 18. G1-TE-S-0000-PDB0004 Design Basis for In-Service Analysis 19. G1-TE-S-0000-PDB0008 Design Basis for Fatigue Analysis 20. G1-PP-DWN-WIN-KS200009 StaadPro Guidance Notes 21. G1-PP-DWN-WIN-KS200013 Structural Analysis Load Combinations 22. G1-PP-DWN-WIN-KS200019 Sea Transport Fatigue Methodology 23. G1-NT-REPKZ900002 Modules Sea Transport Schedule Codes and Standards Structural design shall be carried out in accordance with the following codes and standards: 1.4 24. AISC 360-05 Specification for Structural Steel Buildings [Allowable Stress Design] 25. API RP 2A-WSD Recommended Practice for Planning, Designing and Constructing Fixed Offshore Platforms – Working Stress Design – 21st Edition Abbreviations ASD Allowable Stress Design ASF Allowable Stress Factor CG Centre of Gravity COR Centre of Rotation MOD Module PAR Pre-Assembled Rack/ Pipe Track PAU Pre-Assembled Unit SHLV Semi-Submersible Heavy Lift Vessel SPMT Self-Propelled Modular Transporter WSD Working Stress Design Business Page 6 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis 1.5 Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD Definitions Definitions of Primary/ Major/ Secondary and Tertiary Steel are given in Table 1 of Reference [2]. Business Page 7 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD 2. DESIGN DATA AND ASSUMPTIONS 2.1 Criteria & Assumptions The accelerations for Structural Design of MODs, PARs and PAUs are obtained from References [11], [12] and [13]. They are an envelope of the various acceleration components for all the cargo and vessel cases considered. 1 1 1 The corresponding stowage plans and deflected shapes for the transport vessels are given in [15], [16] and [17]. Proposed stowage plans are collated in Reference [23]. 1 1 1 1 In determining structure orientation on the transport vessel, it is assumed that load-out and load-in are over the stern of the vessel. Unless specified otherwise, the transport vessel in harbour will be assumed to be on level keel, i.e. the structural supports lie in the same horizontal plane. 2.2 Steel Steel material properties for analysis and design shall be as given in Reference [2]. 1 Business Page 8 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis 3. OUTLINE PROCEDURE 3.1 Description Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD The structural strength model will have supports corresponding to the grillage positions on the transport vessel. In general, the support locations will be arranged so that transfer of longitudinal hogging and sagging deflections of the vessel to the structure will be minimised. Where there are multiple support positions along the axis of the vessel, such that deflections are imposed on the structure, the vessel deflection will be modelled by imposing support deflections on the structural model. The sea transport loading conditions are complex combinations of hydrodynamic loads applied to the transport vessel and inertial gravitational loads associated with the resulting motions. For the motion-induced loads, the analysis will assume that the most onerous combination of displacement and acceleration may occur simultaneously. Mass moment of inertia effects are considered in the derivation of inertial forces. STATIC CONDITION The structure is supported on the transport vessel in the harbour, immediately after setdown on the seafastening grillage, and before weld-out of seafastenings. The structure is analysed for gravity load only and is free to deflect in the horizontal plane. STATIC AND INERTIA FORCES The structure is supported on the transport vessel in the sea-going state, with the seafastening restraints applied. The structure is subject to combinations of inertia forces caused by the vessel accelerations, and the varying effects of gravity forces corresponding to the pitch and roll angles of rotation. Although the forces are dynamic, the wave periods (typically 10 to 15 sec) are much longer than the natural periods of the structure, so that the motions can be analysed as quasi-static forces. The static loads, together with loads to balance any spurious restraints, are combined with the inertial loads. Support displacements, due to flexibility of the vessel, are modelled. 3.2 Application in StaadPro The application in StaadPro of the Staged analysis method (above) is described in Section 6.3 of [8]. 1 Where the support condition is geometrically non-linear, e.g. “compression-only” supports, all loads need to be included in a single analysis step to ensure convergence to the correct result. Static loads are analysed in isolation (as described in 3.1) to determine the restraint forces generated in roll- or pitch-restraints if they were present. These forces, or equivalent deflections, are introduced into the inertial analysis as an additional loadcase, ensuring that spurious forces are removed from the model and the correct member forces induced. Business Page 9 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD The detailed procedure in Reference [20] has been developed to allow the application of vessel hog and sag deflections together with the gravity and inertial forces. 1 Business Page 10 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis 4. COMPUTER MODEL 4.1 Structural Model Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD The computer model for Sea Transport will include all significant items of equipment present during the Sea Transport. Items such as tall vessels, large skids, etc. are modelled explicitly using nodes and dummy elements to give the correct mass properties, particularly the vertical CG. The sea transport analysis model will include sets of supports for the static loads and for the inertia loads. • Vertical supports representing the dead-weight supports on the vessel grillages • Lateral restraints, which are different for the static and inertia analyses • Any loads or parts of the structure not present during sea transport will be excluded • Displacement load cases to represent vessel deflection. This is applicable where the structure is supported at more than two locations along the length of the vessel • Dead load cases to represent the weight of any temporary items present during sea transport • Six unit load cases to represent the individual acceleration components, referenced to the appropriate centre of rotation • Load combinations of static, inertia loads and vessel displaced shape. It should be noted in particular that, because on the “legs down” philosophy adopted for module construction and installation, the main grillage lines are eccentric to the main structural framing lines. The analysis model must reflect the true proposed support and load transfer arrangement. 4.2 Orientation on Transport Vessel The orientation of the structure on the transport vessel is influenced by: • SPMT alignment with respect to the transport vessel. The analyses assume that load-out and load-in are over the stern of the vessel, so that the SPMT are aligned bow-stern. • SPMT alignment with respect to the structure. The alignment of the SPMT with respect to the structure is determined by the direction in which the structure is to approach its final location at the Gorgon LNG Plant. This is dictated by the construction philosophy. The orientation of each structure with respect to the vessel must be confirmed explicitly on a case-by-case basis. In particular, smaller structures may have to be analysed for more than one orientation and position on the vessel. In each case, reference will be made to the stowage plans. 4.3 Transverse Location on Transport Vessel In general, wider or heavier structures will be centred on the longitudinal centreline of the transport vessel at an extreme bow or stern location. Smaller structures will be assumed to be in an extreme port or starboard quarter location. Business Page 11 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD The different positions will be considered in the transport motions analysis; the accelerations generated by the Naval Architect [11] [12] [13] reflect the selected location. 1 4.4 1 1 Support Conditions Supports will be modelled as fixed joint restraints in the global X, Y or Z directions. Longitudinal (hog or sag) bending of the vessel will be modelled by applying imposed deflections to the model restraints. In the static loads analysis, the model will be supported vertically at the points corresponding to the dead weight supports on the transport vessel. In practice, the structure is free to translate horizontally, being restrained only by friction. Therefore, ‘dummy’ lateral restraint forces will be induced in the static model. An example of a suitable configuration is shown in [8]. 1 In the inertia loads analysis, horizontal restraints will be applied that replicate the proposed pitch and roll restraints, as outlined in Section 4.5.2. Deflections will be applied to the roll and pitch braces to balance/ eliminate the unintended static restraints included in the preliminary static analysis. 1 The supports system in Figure 4-1 is to be used for the final verification analysis. 1 The pitch restraints will be at or close to the centre of the Module and all the vertical restraints along this transverse frame will be acting both in tension and compression. All other vertical restraints will be modelled as compression only members. Roll braces will be modelled at each transverse frame. Horizontal restraints will be applied at the underside of the lower deck girders. If seafastening braces need to be introduced at a higher elevation (for example to reduce stresses in a slender or tall structure), these bracing members will be modelled in the analysis. Business Page 12 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD Figure 4-1 Grillage Arrangement Typical Grillage Support Beams Forward Vessel Unless noted otherwise all the Vertical Supports at the Grillage Beam positions are to be Compression Only Supports 1) Pitch Restraints to be in or near the middle of the module centreline 2) All Vertical supports at the grillage points at or near the middle of the module are to be both tension and compression supports. 3 Different positions of internal Roll Braces have been shown. Any one which suits the module should be selected. 4.5 Modules 4.5.1 Grillages A typical Module grillage layout is shown in Figure 4-2. The main load is taken by the two 1300 mm deep plate girders (nominally 400 mm wide) under the transverse beams on either side of the main columns. These plate girders then distribute the loads to four 1100 mm deep plate girders which then transfer the load to the SHLV web frames at eight points. The dimensions are “typical” and may need to be varied in specific cases. 1 Business Page 13 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD Figure 4-2: Typical Grillage Arrangement Longitudinal Beam SHLV Web Frames B Transverse Beam B A A Plan View SHLV Deck View B -- B SHLV Web Frames Business Page 14 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis 4.5.2 Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD Sea-fastenings The Module roll and pitch braces will frame to the underside of the primary steel to ensure they are easy to install and remove. For 36 m-wide modules, the roll braces will be within the structure footprint. For structures of other widths, depending on the location on the transport vessel, some of the roll braces may need to be outside the footprint. Additional members, from the centreline of the primary member to the top of the grillage, will be introduced to model the eccentricities to top of grillage supports. Vertical restraints will be modelled at these ends, nodes N2, N6, N9 and N13. Roll braces will be modelled from centreline of the primary members and roll restraints will be applied at the bottom ends of the roll braces, node N7 (Figure 4-3). The most appropriate position of the roll braces along transverse frames will be decided by the engineer to minimise the support reactions and will be one of the three options shown in Figure 4-1. 1 1 In the case of external roll braces, additional members will be modelled for the roll braces and to represent the eccentricity of the connection to the primary steel member centreline and also to top of the grillages. Roll restraints will be applied at the bottom end of the roll braces, node N1; vertical restraints will be applied at nodes N4 and N8, ref. Figure 4-4. 1 In Figure 4-3 and Figure 4-4, uplift restraints are shown connecting the grillage to the underside of the module. Uplift restraints are discussed further in Section 4.5.3. 1 1 1 Figure 4-3: Typical Internal Roll Brace Arrangement N1 N3 N2 N5 N8 N6 N9 N4 Vertical Restraints at N2, N6, N9 & N13 Roll Restraints at N7 N10 N12 N13 N11 N7 Internal Roll Braces Business Page 15 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD Figure 4-4: Typical External Roll Brace Arrangement Pitch braces will be modelled at or near the middle of the Module (Figure 4-1) and will be connected to one transverse frame only, to avoid load being induced into the module as the transport vessel deflects under wave loads; they will be in line with the longitudinal frames. Typical arrangements are shown in Figure 4-5 and Figure 4-6. Pitch restraints will be applied at node N4. 1 1 1 The preferred arrangement is shown in Figure 4-5, where the pitch braces are connected to an intermediate transverse frame. In this case, the pitch braces will be connected to nodes N1 and N4 and pitch restraint will be applied at node N4. Figure 4-6 may be adopted if Figure 4-5 cannot be used in a particular case. 1 1 1 Figure 4-5: Preferred Pitch Brace Business Page 16 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD Figure 4-6: Pitch Stop Arrangement 4.5.3 Uplift Restraints Uplift forces will be taken by grillage supports on transverse frames at or close to the centre of the Module (Figure 4-1), or elsewhere as optimised. Other grillage supports are to be designed to take compressive forces only. 1 4.6 PARs 4.6.1 General PARs will be transported from the fabrication yard to Barrow Island on board SHLV type vessels. A number of PARs will be transported on each vessel, where they are close to each other. This leaves restricted space for installing roll or pitch braces. The pitch restraints will be located at a single transverse frame close to or at the centre of the PAR. Roll restraints will be located at each transverse frame. 4.6.2 Elevated PARs Elevated PARs will be transported from the fabrication yard to Barrow Island on board SHLV type vessels. A number of these PARs are being transported on each vessel, where they are fairly close to each other. This leaves restricted space for installing roll or pitch braces. 4.6.3 3 m PARs The 3 m wide PARs require only one row of SPMT for load-on and load-off from the SHLV. Due to column spacing and the base plates which will be required for fixing to the main columns on site, there is not sufficient space for the single row of trailers. Hence for load-on and load-off from the SHLV temporary spreader beams will be required under the main columns. These spreader beams will also be used for sea transportation such that grillages will be set apart at 3500 mm, Figure 4-7. 1 The computer analysis model for the 3 m wide PARs will be as shown in Figure 4-7, where the eccentricities will be modelled to represent grillage supports under the spreader beams relative to the main columns. Vertical and roll restraints will be applied 1 Business Page 17 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD at nodes N5 and N10 and on one transverse frame the pitch restraints will be applied at nodes N3 and N8. Alternatively, pitch restraints could be considered at N1 and N6, to reduce minor-axis bending of the columns. Figure 4-7: 3m Interconnecting PARs 4.6.4 6 m PARs The 6 m wide PARs will be loaded using a temporary frame and the grillage will be supported off the stubs connected to the main columns, Figure 4-8. The grillage beams will then distribute the loads to the SHLV web frames at four points adjacent to each column. 1 The computer analysis model will as shown in Figure 4-8; eccentricities will be modelled to represent the intersection of the braces with the columns and the grillage supports. Vertical and roll restraints will be applied at node N5 and on one transverse frame the pitch restraints will be applied at node N3. 1 Business Page 18 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Figure 4-8 Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD Support for 6 m PAR N1 N4 ~420 N2 ~420 N5 ~510 N3 ~510 ~800 ~800 4.6.5 PARs < 12 m wide For PARs below 12 m width, the preferred option is to use a permanent load-out beam, the underside of which will be set 2900 mm above the underside of the column base plate level and the grillage will be under the stubs connected to the main columns, Figure 4-9. The grillage beams will then distribute the loads to the SHLV web frames at two points adjacent to each column. If this option is unsuitable then a temporary loadout beam will be used [Figure 4-10] but with grillage arrangement similar to that for the preferred option. 1 1 For the preferred option, the computer analysis model will as shown in Figure 4-9, with eccentricities modelled to represent the actual points of intersection of the braces with the columns and also where the grillage supports will be. Vertical and roll restraints will be applied at node N5 and on one transverse frame the pitch restraints will be applied at node N3. 1 The computer analysis model for the second option will as shown in Figure 4-10, with eccentricities modelled to represent the intersection of the braces with the columns and also where the grillage supports will be. Vertical and roll restraints will be applied at node N5 and on one transverse frame the pitch restraints will be applied at node N3. 1 Business Page 19 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Figure 4-9 Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD PARs up to 12m Wide – Preferred BEAM FOR TRANSPORTATION IS APPROX 3m ABOVE GRADE, WILL ALLOW SMALL VEHICLE ACESS AND ENCE NEED NOT BEAM FOR TRANSPORTATION IS APPROX 3m ABOVE GRADE, WILL ALLOW SMALL VEHICLE ACESS AND ENCE NEED NOT ~2900 ~2900 N1 150 N4 ~750 N2 N5 ~950 N3 ~750 300 ~900 ~950 300 ~900 Figure 4-10 PARs up to 12m Wide – Alternative 4.6.6 PARs ≥ 12 m wide For PARs with width of 12 m or more, the load-out will use a temporary frame and the grillage will be under the stubs connected to the main columns, Figure 4-11. The grillage beams will then distribute the loads to the SHLV web frames at four points adjacent to each column. 1 For the 12 m and wider PARs the computer analysis model will as shown in Figure 4-11, where the eccentricities will be modelled to represent the actual points of intersection of the braces with the columns and also where the grillage supports will be. Vertical and 1 Business Page 20 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD roll restraints will be applied at nodes N5 and N7 and on one transverse frame the pitch restraints will be applied at node N3. Figure 4-11: PARs ≥ 12 m Wide N1 N4 N6 N2 N5 N7 1050 N3 1050 ~1250 1000 ~300 1000 ~1250 ~300 ~1250 4.6.7 1000 1000 ~1250 Stacked PARs Stacked PARs are to be transported using spreader beams over the SPMTs - Figure 4-12. The analysis scheme follows that of Figure 4-7. 1 1 Figure 4-12: Stacked PARs The spreader beams will be transported with the PARs to Barrow Island where they will be re-used to off-load the PARs before being separated for transport and installation. Business Page 21 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis 4.7 PAUs 4.7.1 PAUs 9 m or Wider Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD For PAUs with width of 9 m or more, grillage beams will be located on one side of the main column only and external roll braces will be used, see Figure 4-13. The grillage beams will then distribute the loads to the SHLV web frames at four points adjacent to each column, typical side elevation will be similar to Figure 4-2 View B – B. 1 1 The computer analysis model for these PAUs will be as shown in Figure 4-13. Eccentricities will be modelled to represent the grillage supports points. Vertical restraints will be applied at nodes N4 and N9. The external roll braces will be modelled as in Figure 4-13 and roll restraints will be applied at nodes N5 and N10. 1 1 Pitch braces will be modelled on one transverse frame near the middle of the PAU. Modelling of these braces will be similar to those shown in Figure 4-5 for the Modules. 1 Figure 4-13: PAU 9m or Wider 4100 400 400 400 1205 1205 N8 N3 N1 N4 N6 N 4100 N5 N2 N1 0 N7 400 400 1205 4.7.2 400 1205 PAUs Less Than 9 m Wide For PAUs less than 9 m wide, the grillage beams will be located below the permanent cantilever steelwork on the external side of the main columns - Figure 4-14. External roll braces will be used and will be connected to the cantilever steelwork, Figure 4-14. The grillage beams will then distribute the loads to the SHLV web frames at four points adjacent to each column, typical side elevation will be similar to that in Figure 4-2 View B – B. 1 1 1 Business Page 22 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD For these PAUs, the computer analysis model will as shown in Figure 4-14 where the eccentricities will be modelled to represent the actual points of intersection of the braces with the columns and also where the grillage supports will be. Vertical restraints will be applied at nodes N4 and N11 and roll restraints will be applied at nodes N5 and N10. 1 Pitch braces will be modelled on one transverse frame near the middle of the PAU. Modelling of these braces will be similar to those shown in Figure 4-5 for the Modules. 1 Figure 4-14: PAUs less than 9m Wide 4100 400 400 400 1205 1205 150 150 N1 N3 N8 N6 N4 N9 N1 N1 4100 N2 N7 400 N5 400 400 1205 N10 1205 Dimensions are “typical” and may need to be varied in specific cases. Business Page 23 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis 5. LOADS 5.1 Weight Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD The Sea Transport analysis will use the latest transport weight derived from the Weight Report [6] [7]. 1 1 Load cases will be adjusted to ensure that the weight and CG (including the vertical CG) from the analysis match the Weight Report values, taking into account demonstrable weight changes. 5.2 Vessel Motions - Modules Module Transport design accelerations are given in Table 5-1 (from [11]). components are defined in Figure 5-1. 1 1 The 1 Table 5-1: Design Accelerations In applying rotational accelerations to the structural model, it is necessary to define the centre of rotation (COR) to which the acceleration sets are referenced. Figure 5-1 shows the directions of positive inertia forces and moments. 1 Business Page 24 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD The horizontal linear accelerations include the variations in gravity forces caused by the pitch and roll rotations of the vessel. The acceleration components are ‘single-amplitude’. The components are equal in magnitude in the positive and negative directions. Thus, for example, roll accelerations to port and to starboard are of the same magnitude, but in the opposite direction. The values in the table correspond to positive roll and pitch displacements; the full list of load conditions will consider all possible combinations of motion couplings (positive and negative). 5.3 Vessel Motions - PARs PAR Transport design accelerations are given in Table 5-2 (from [12]). 1 1 These apply to PARs generally except Jetty PARs. Table 5-2: PAR Design Accelerations 5.4 Vessel Motions – PAUs Design accelerations for PAUs are given in Reference [13]. 1 Table 5-3: PAU Design Accelerations Business Page 25 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD Figure 5-1: Inertia Force Components 5.5 Wind Loads Wind loads are included in the Naval Architect’s inertia analysis, applied in the same direction as the horizontal forces caused by the vessel motion. Wind speed (1-min mean at 10 m above sea level) [2] is 25 m/s (non-cyclonic) for units transported on SHLV. 1 Local wind loads on the structural elements may be generated using the Ultimate Limit State wind loads from the In-Service analysis, and scaled down for the correct wind speed using the REPEAT LOAD facility in STAAD.Pro. 5.6 Vessel Deflection The transport vessel will deflect longitudinally into hogging and sagging shapes during sea transit. These deflections can affect the structural integrity, depending on the configuration of the seafastenings provided. If the structure is restrained longitudinally at two or more locations, it will act compositely with the vessel. Hogging and sagging deflections in the vessel will then produce longitudinal shear forces between barge and structure that could exceed the structural capacity. This effect is avoided if longitudinal (pitch) restraint is provided at only one longitudinal position, with the structure free to displace longitudinally elsewhere. Therefore, where practical, pitch restraints will be provided at only one longitudinal location. Depending on the number of vertical support positions, sagging and hogging displacements of the vessel could impose vertical displacements and curvatures on the structure. For structures with more than two lines of support on the vessel the hogging and sagging of the vessel will impose vertical displacements on the structure supports. These displacements will be included in the analysis using forced-displacement load cases. The vessel deflected shapes for the various transportation voyages are defined in [15], [16] and [17]. It is assumed that the grillage supports are shimmed so that the structure is level in the Stillwater condition. The effective vessel hog and sag will be relative to the Stillwater condition, as demonstrated in Figure 5-2. 1 1 1 1 Business Page 26 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD Figure 5-2: Effective Hog and Sag Effective Vessel Hog (90m from stern) Effective Vessel Sag (90m from stern) The effective vessel hog and sag deflection will be calculated at each support, taking into account the support location along the length of the vessel and using the curve for the applicable voyage. Forced displacements will be applied in STAAD to the supports located within the length of the structure (rows 2, 3 and 4 in Figure 5-3), and will be calculated relative to the displacements at the end supports (rows 1 and 5 in Figure 5-3). Zero displacement will be applied in STAAD to the end supports. 1 1 Figure 5-3: Longitudinal Section of Example Structure on Vessel Vessel Deck Support Row: 1 2 3 4 5 Hog and sag of the transport vessel will be combined with the surge, pitch and heave accelerations. Transverse and torsional deflections of the transport vessel will be assumed to be negligible. Business Page 27 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD 6. BASIC LOAD CASES 6.1 Stage 1 – Static Loads Analysis 6.1.1 Static Loads Basic load cases that define the total transport weight in the static analysis are outlined in Table 6-1 (this is an indicative list). These will be analysed in the static loads analysis, for later combination with results of the inertia loads analysis. 1 Table 6-1: BASIC LOAD CASES FOR STATIC ANALYSIS Load Case Description Load cases developed as required Dead: Self Generated Dead Weight Dead: Non-generated Structural Dead Loads Dead: Architectural Dead Loads Dead: Mechanical and HVAC Equipment - Dry Dead: Electrical Equipment Dead: Instrumentation Dead: Loss Prevention Dead: Piping - Dry Temporary items (slings, rigging, or equipment in temporary location) Temporary: HUC Equipment transported with structure 6.1.2 CG Envelope Uncertainty in the Centre of Gravity is accounted for as described in Reference [9]. 1 The dimensions of the CG envelope are the same for Land Transport and Sea Transport analyses. Two load cases, simulating moments about the Global X and Z axes, are used to shift the static load CG to the four corners of the CG envelope. The load combinations will incorporate each location for the static load CG. 6.2 Stage 2 – Inertia Loads Analysis Unit inertia load cases lists are given in Table 6-2. These load cases will be suitably factored in Stage 3 to give the appropriate total inertia loads on the structure. 1 The basic unit acceleration load cases (701 – 706) will be generated using the weight load cases in Table 6-1 to define the total mass of the model. 1 Rotational accelerations are defined using the angular acceleration and the reference centre of rotation. The latter describes the cargo location relative to the transport vessel, according to the Naval Architect data. The height of the seafastening grillage and the depth of the structure framing need to be taken into account in when defining the coordinates of the location of the cargo in the Naval Architectural model. Where “compression only” supports are to be used, Stage 1 and Stage 2 loads are combined directly in a single analysis, as the gravity loads are required for convergence to the correct results. The restraint forces derived from the Stage 1 analysis are balanced out in the combined analysis. Business Page 28 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD Table 6-2: BASIC LOAD CASES FOR INERTIA ANALYSIS Load Case 431 Sea Transport Wind: towards bow (10 yr return, 1min. mean), Structure +X direction 432 Sea Transport Wind: towards stern (10 yr return, 1min. mean), Structure -X direction 433 Sea Transport Wind: towards starboard (10 yr return, 1min. mean), Structure +Z direction 434 Sea Transport Wind: towards port (10 yr return, 1min. mean), Structure -Z direction 701 Unit 1.0 m/s² surge force towards bow (Structure +DX) 702 Unit 1.0 m/s² heave force upwards (Structure +DY) 703 Unit 1.0 m/s² sway force towards starboard (Structure +DZ) 704 Unit Rotational Accn. 1.0 deg/s² about longitudinal axis (Structure +RX) 705 Unit Rotational Accn. 1.0 deg/s² about vertical axis (Structure +RY) 706 Unit Rotational Accn. 1.0 deg/s² about transverse axis (Structure +RZ) 751 Vessel sagging deflection 752 Vessel hogging deflection Description Business Page 29 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis 7. DESIGN VERIFICATION 7.1 Load Combinations Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD The static and inertia loads are assembled into combinations (Table 7-1) for code checking. The combination factors are derived from the acceleration values (m/s², deg/s²) calculated by the Naval Architects. Gravity loads (Case 1800), Centre of Gravity Shift, vessel deflections and wind loads (in appropriate directions) are included in the combinations. 1 The engineer shall check manually the total loads output for these combinations. The load combinations derive from the specified sets of unit accelerations, using the accelerations as the combination factors (in all permutations of positive and negative senses). Ensure that gravity (in the vertical direction) is not double-counted. Where the analysis requires ‘compression-only’ (or ‘tension-only’) supports, a singlestage (combined) analysis must be used, so that it converges to the correct solution. Business Page 30 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD Table 7-1: COMBINATIONS OF MOTION FORCES Sea Transport Wind Factored from Operating ULS Wind Create REPEAT loads by factoring ULS wind cases by (Vsea/VULS) 2 -2 Positive Inertia Loadcases (1ms unit in STAADOffshore) Module +X axis parallel to Vessel 702 703 704 705 Module +X axis parallel to Vessel 1800 Load comb No. 431 Wind to Bow REPEAT (REPEAT load: All 401 x Transport (V /V )2 dead loads sea ULS x diagonal) Load Combination Description 432 Wind to Stern (REPEAT 402 x (Vsea/VULS)2 x diagonal) 433 Wind to Starb'd (REPEAT 403 x (Vsea/VULS)2 x diagonal) 434 621 Wind to Port (REPEAT 404 x (Vsea/VULS)2 x diagonal) CG Correction, unit ΣMX = 1000kNm 622 CG Correction, unit ΣMZ = 1000kNm 701 DX DY DZ RX RY 706 RZ 751 Sag 752 Hog Adjustment factor = 0.114 Sea Transport (AISC - WSD) 1.0 Stillwater 1802 Surge/Pitch to Bow Sway/Roll to Stbd +Yaw Surge/Pitch to Stern Sway/Roll to Stbd -Yaw Surge/Pitch to Bow Sway/Roll to Port -Yaw Surge/Pitch to Stern Sway/Roll to Port +Yaw Surge/Pitch to Bow Sway/Roll to Stbd +Yaw Surge/Pitch to Stern Sway/Roll to Stbd -Yaw Surge/Pitch to Bow Sway/Roll to Port -Yaw Surge/Pitch to Stern Sway/Roll to Port +Yaw 1805 1806 1807 1808 1809 1810 1811 1812 1813 1814 1815 1816 1817 Min Heave 1804 Min Max Min Max Heave Heave Heave Heave 1803 Max Heave 1801 Surge/Pitch to Bow Sagging Surge/Pitch to Stern Sagging Surge/Pitch to Bow Sagging Surge/Pitch to Stern Sagging Surge/Pitch to Bow Hogging Surge/Pitch to Stern Hogging Surge/Pitch to Bow Hogging Surge/Pitch to Stern Hogging 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 + 1.0 1.0 1.0 1.0 + 1.0 1.0 1.0 1.0 + + + + + + + + + + + + + + + + + + + + + + + + + + - + + + + + + + + - + + + + - + + + + + + + + - + + + + - + + + + - + + + + - + + + + + + + + + + + + + + + + + + + + Notes: The load combinations in Table 7-1 are suitable for where the structure longitudinal (X) axis is parallel to the vessel and pointing towards the bow. 1 Further information on load combinations is contained in Ref [21]. 1 Business Page 31 of 32 Uncontrolled when printed Gorgon Project, Barrow Island LNG Plant Contract No: 68500019 Job No 6300 Design Basis For Sea Transport Analysis 7.2 Document No: G1-TE-S-0000-PDB0003 Revision: 1 Issue Purpose: RFD Code Checks The structure will be checked to the provisions of AISC-ASD [24]. 1 The Allowable Stress Factor (ASF) shall be in accordance with Table 7-2, based on Reference [2]. 1 1 Table 7-2: Sea Transport - Allowable Stress Factors Design Condition Allowable Stress Factor (ASF) Sea Transport – Harbour or Still-water Case 1.0 Sea Transport – Inertial Cases: all members, including Tie-downs 1.33 Sea Transport – Inertial Cases: Tie-down connections to SHLV 1.0 The target normalised member utilisation ratio shall be in the range 0.80 to 0.90. Where members need to be re-sized to the target utilisation range, this will be done in conjunction with results from In-Service and Land Transport analyses. ‘Dummy’ members – included in the model to represent loading mechanisms – are excluded from all code checks. Business Page 32 of 32 Uncontrolled when printed