Uploaded by Carolina López Villegas

END

advertisement
Part A
General Requirements
8.1 Scope
This clause contains requirements for inspection and nondestructive testing. It is divided into seven parts as
follows:
Part A- General Requirements
Part B - Contractor Responsibilities
Part C - Acceptance Criteria
Part D - NDT Procedures
Part E - Radiographic Testing (RT)
Part F - Ultrasonic Testing (UT) of Groove Welds
Part G - Other Examination Methods
.8.1.1 Information Furnished to Bidders. When NDT other than visual is to be required, it shall be so stated in
the
information furnished to the bidders. This information shall designate the categories of welds to be examined, the
extent
of examination of each category, and the method or methods of testing .
.8.1.2 Inspection and Contract Stipulations. For the purpose of this code, fabrication/erection inspection and
testing,
and verification inspection and testing shall be separate functions .
.8.1.2.1 Contractor's Inspection. This type of inspection and testing shall be performed as necessary prior to
assembly, during assembly, during welding, and after welding to ensure that materials and workmanship meet the
requirements of the contract documents. Fabrication/erection inspection and testing shall be the responsibilities of
the
Contractor unless otherwise provided in the contract documents .
.8.1.2.2 Verification Inspection. This type of inspection and testing shall be performed and their results reported
to the Owner and Contractor in a timely manner to avoid delays in the work. Verification inspection and testing are
the
prerogatives of the Owner who may perform this function or, when provided in the contract, waive independent
verification, or stipulate that both inspection and verification shall be performed by the Contractor .
.8.1.3 Definition of Inspector Categories
.8.1.3.1 Contractor's Inspector. This inspector is the duly designated person who acts for, and in behalf of, the
Contractor on all inspection and quality matters within the scope of the contract documents .
.8.1.3.2 Verification Inspector. This inspector is the duly designated person who acts for, and in behalf of, the
Owner or Engineer on all inspection and quality matters within the scope of the contract documents .
.8.1.3.3 Inspector(s). When the term inspector is used without further qualification as to the specific inspector
category described above, it applies equally to inspection and verification within the limits of responsibility
described in
8.1.2 .
.8.1.4 Qualification of Inspection Personnel
8.1.4.1 Engineer's Responsibilities. If the Engineer requires a specific basis of inspection personnel qualification
other than those listed in 8.1.4.2, the basis shall be designated in the contract documents.
8.1.4.2 Basis for Qualification of Welding Inspectors. Inspectors responsible for acceptance or rejection of
material and workmanship on the basis of visual inspection shall be qualified.
The acceptable qualification basis shall be one of the following:
(1) Current or previous certification as an AWS Certified Welding Inspector (CWl) or Senior Certified Welding
Inspector
(SCWl) in conformance with the requirements of AWS QCl, Standard for AWS Certification of Welding
Inspectors,
(2) Current or previous certification as a Level 2 or Level 3 Welding Inspector in conformance with the
requirements
of Canadian Standard� Association (CSA) Standard Wl 78.2, Certification of Welding Inspectors,
(3) Current or previous qualification as a Welding Inspector (WI) or Senior Welding Inspector (SWI) in
conformance
with the requirements of AWS B5.1, Specification for the Qualification of Welding Inspectors,
(4) Current or previous qualification as an ASNT SNT-TC-lA-VT Level II in conformance with the requirements of
ASNT Recommended Practice No. SNT-TC-JA. Personnel Qualification and Certification in Nondestructive
Testing. or
ANSI/ASNT CP-189 ASNT Standard for Qualification and Certification of Nondestructive Personnel or
ill An individual who, by training or experience, or both, in metals fabrication, inspection and testing, is competent
to perform inspection of the work.
8.1.4.3 Alternative Inspector Qualifications .
The basis of alternative qualification for inspection personnel shall be specified in contract documents if different
than
the requirements in 8.1.4.2. When requested by the Engineer, or an authorized representative of the owner,
documentation
of the specified alternative qualification of inspection personnel shall be submitted for verification and approval.
8.1.4.4 Assistant Inspector. The Inspector may be supported by Assistant Inspectors who may perform specific
inspection functions under the supervision of the Inspector. The work of Assistant Inspectors shall be regularly
monitored
by the Inspector.
8.1.4.5 Basis for Qualification of Assistant Inspectors. Assistant Inspectors shall be qualified to perform the
specific functions to which they are assigned.
The acceptable qualification basis shall be one of the following:
(l) Current or previous certification as an AWS Certified Associate Welding Inspector (CAWI) or higher in
conformance
with the requirements of AWS OCl, Standard for AWS Certification of Welding Inspectors,
(2) Current or previous certification as a Level 1 Welding Inspector or higher in conformance with the requirements
of Canadian Standards Association (CSA) Wl 78.2, Certification ofW elding Inspectors,
(3) Current or previous qualification as an Associate Welding Inspector (AWi) or higher in conformance with the
requirements of AWS B5.1, Specification for the Qualification of Welding Inspectors,
(4) Current or previous qualification as an ASNT SNT-TC- lA-VT Level I in conformance with the requirements of
ASNT Recommended Practice No. SNT-TC-JA. Personnel Qualification and Certification in Nondestructive
Testing. or
ANSI/ASNT CP-189, ASNT Standard for Qualification and Certification of Nondestructive Personnel or
(5) An individual who is qualified by training and experience to perform the specific functions they are assigned.
8.1.4.6 Eye Examination . Inspectors and Assistant Inspectors, and personnel performing NDT shall have passed
an eye examination to prove natural or corrected near vision acuity, in at least one eye, of Jaeger J -2 at a minimum
distance of 12 in [300 mm]. Alternatively, an equivalent test as determined by ophthalmic medical personnel is
acceptable.
Vision tests are required every three years, or less if necessary, to demonstrate adequacy.
8.1.4.7 Term of Effectiveness . The qualification of an Inspector shall remain in effect indefinitely, provided the
Inspector remains active in inspection of welded steel fabrication and their eye examinations are current, unless
there is
specific reason to question the Inspector's ability.
�.1.5 Inspector Responsibility. The Inspector shall ascertain that all fabrication and erection by welding is
performed
in conformance with the requirements of the contract documents.
�.1.6 Items to be Furnished to the Inspector. The Inspector shall be furnished complete detailed drawings
showing
the size, length, type, and location of all welds to be made. The Inspector shall also be furnished the portion of the
contract
documents that describes material and quality requirements for the products to be fabricated or erected, or both.
�.1.7 Inspector Notification. The Inspector shall be notified in advance of the start of operations subject to
inspection
and verification.
8.2 Inspection of Materials and Equipment
The Contractor's Inspector shall ensure that only materials and equipment conforming to the requirements of this
code
shall be used.
8.3 Inspection of WPSs
�.3.1 Prequalified WPS. The Contractor's Inspector shall ensure that all prequalified WPSs to be used for the work
conform with the requirements of Clauses J., 1, 10 (if tubular), and the contract documents.
�.3.2 WPSs Qualified by Test. The Contractor's Inspector shall ensure that all WPSs qualified by test conform with
the requirements of Clauses .6., 1, 10 (if tubular), and the contract documents.
�.3.3 WPSs in Production. The Contractor's Inspector shall ensure that all welding operations are performed in
conformance with WPSs that meet the requirements of this code and the contract documents.
8.4 Inspection of Welder, Welding Operator, and Tack Welder
Qualifications
�.4.1 Determination of Qualification. The Inspector shall allow welding to be performed only by welders, welding
operators, and tack welders who are qualified in conformance with the requirements of Clause .6., or Clause 10 for
tubulars, or shall ensure that each welder, welding operator, or tack welder has previously demonstrated such
qualification
under other acceptable supervision and approved by the Engineer in conformance with .6.2.2.1.
�.4.2 Retesting Based on Quality of Work. When the quality of a qualified welder's, welding operator's, or tack
welder's work appears to be below the requirements of this code, the Inspector may require that the welder, welding
operator, or tack welder demonstrate an ability to produce sound welds of the type that has not met requirements by
means of a simple test, such as the fillet weld break test, or by requiring complete requalification in conformance
with
Clause .6., or Clause 10 for tubulars.
�.4.3 Retesting Based on Qualification Expiration. The Inspector shall require requalification of any welder,
welding operator, or tack welder who has not used the process (for which they are qualified) for a period exceeding
six
months (see .6.2.3.1).
8.5 Inspection of Work and Records
�.5.1 Size, Length, and Location of Welds. The Inspector shall ensure that the size, length, and location of all welds
conform to the requirements of this code and to the detail drawings and that no unspecified welds have been added
without the approval of the Engineer.
�.5.2 Scope of Examinations. The Inspector shall, at suitable intervals, observe joint preparation, assembly practice,
and the welding techniques, and performance of each welder, welding operator, and tack welder to ensure that the
applicable requirements of this code are met.
�.5.3 Extent of Examination. The Inspector shall examine the work to ensure that it meets the requirements of this
code. Other acceptance criteria, different from those described in the code, may be used when approved by the
Engineer.
Size and contour of welds shall be measured with suitable gages. Visual inspection for cracks in welds and base
metal and
other discontinuities should be aided by a strong light, magnifiers, or such other devices as may be found helpful.
�.5.4 Inspector Identification of Inspections Performed. Inspectors shall identify with a distinguishing mark or
other recording methods all parts or joints that they have inspected and accepted. Any recording method which is
mutually
agreeable may be used. Die stamping of cyclically loaded members without the approval of the Engineer shall be
prohibited.
�.5.5 Maintenance of Records. The Inspector shall keep a record of qualifications of all welders, welding operators,
and tack welders; all WPS qualifications or other tests that are made; and such other information as may be
required.
PartB
Contractor Responsibilities
8.6 Obligations of the Contractor
CLAUSE 8. INSPECTION
.B.6.1 Contractor Responsibilities. The Contractor shall be responsible for visual inspection and necessary
correction
of all deficiencies in materials and workmanship in conformance with the requirements of this code .
.B.6.2 Inspector Requests. The Contractor shall comply with all requests of the Inspector(s) to correct deficiencies
in
materials and workmanship as provided in the contract documents .
.B.6.3 Engineering Judgment. In the event that faulty welding, or its removal for rewelding, damages the base
metal
so that in the judgment of the Engineer its retention is not in conformance with the intent of the contract documents,
the
Contractor shall remove and replace the damaged base metal or shall compensate for the deficiency in a manner
approved
by the Engineer .
.B.6.4 Specified NDT Other than Visual. W hen NDT other than visual inspection is specified in the information
furnished to bidders, it shall be the Contractor's responsibility to ensure that all specified welds shall meet the
quality
requirements of Clause .8., Part C or Clause 10, Part F for tubulars, whichever is applicable .
.B.6.5 Nonspecified NDT Other than Visual. If NDT other than visual inspection is not specified in the original
contract agreement but is subsequently requested by the Owner, the Contractor shall perform any requested testing
or
shall allow any testing to be performed in conformance with 8.14. The Owner shall be responsible for all associated
costs
including handling, surface preparation, NDT, and repair of discontinuities other than those described in 8.9,
whichever
is applicable, at rates mutually agreeable between Owner and Contractor. However, if such testing should disclose
an
attempt to defraud or gross nonconformance to this code, repair work shall be done at the Contractor's expense.
PartC
Acceptance Criteria
8.7 Scope
Acceptance criteria for visual and NDT inspection of statically and cyclically loaded nontubular connections are
described
in Part C. The extent of examination and the acceptance criteria shall be specified in the contract documents in the
information
furnished to the bidder.
8.8 Engineer's Approval for Alternate Acceptance Criteria
The fundamental premise of the code is to provide general stipulations applicable to most situations. Acceptance
criteria
for production welds different from those described in the code may be used for a particular application, provided
they
are suitably documented by the proposer and approved by the Engineer. These alternate acceptance criteria may be
based
upon evaluation of suitability for service using past experience, experimental evidence or engineering analysis
considering
material type, service load effects, and environmental factors.
8.9 Visual Inspection
All welds shall be visually inspected and shall be acceptable if the criteria of Table 8.1, or Table 10.15 (if tubular)
are
satisfied.
8.10 Penetrant Testing (PT) and Magnetic Particle Testing (MT)
Welds that are subject to PT and MT, in addition to visual inspection, shall be evaluated on the basis of the
acceptance
criteria for visual inspection. The testing shall be performed in conformance with 8.14.4 or 8.14.5, whichever is
applicable.
Download