Get Complete eBook Download by Email at discountsmtb@hotmail.com Get Complete eBook Download by Email at discountsmtb@hotmail.com Get Complete eBook Download link Below for Instant Download: https://browsegrades.net/documents/286751/ebook-payment-link-forinstant-download-after-payment Get Complete eBook Download by Email at discountsmtb@hotmail.com Contents Acknowledgments About the Author Preface Disclaimer Introduction The Goals of This Book What Are the Benefits of This Book? Contractor & Owner Conventions Private Contracts or Government Contracts? Key Contracting Concepts Two Types of Commercial Terms & Conditions The Most Important Commercial Terms & Conditions The Contracting Process Excuses for Not Negotiating Better Commercial Terms & Conditions The Concept of Risk Transfer This Is a Book Developed Just for Contractors Three Final Suggestions Chapter 1: Contracts: Basic Training What Is a Contract? The Steps to a Contract xiii xv xvii xix xxi xxi xxi xxii xxii xxii xxiii xxv xxv xxv xxvi xxvii xxvii 1 1 1 vii Get Complete eBook Download by Email at discountsmtb@hotmail.com 2 Coming to the Party? The Starting Point 3 “Here’s My Proposal” 4 “Consideration,” or Something of Value 5 The “Happy Test” 5 “Can That Person Sign This Contract?” 6 Call in the Enforcer to Close the Breach! 6 A Contract Example 8 Strange Words & Long Paragraphs 10 11 Contracting Myths Contract Negotiations 12 Chapter 2: Types & Forms of Contracts 15 Fixed Price & Fixed Schedule Contracts 16 Reimbursable Type Contracts 16 18 Combined Fixed Price & Reimbursable Contracts 20 Cost Plus Fee Contracts Guaranteed Maximum Price Contracts 21 Target Price Contracts 21 22 Contracts with Performance Incentives Form of Contracts 23 30 Some Final Contract Housekeeping—­Definitions Conclusion32 Chapter 3: Scope of Work 33 37 The Scope of Work Matrix Scoping Drawings 39 Conclusion40 Chapter 4: Terms of Payment & Cash Flow 41 Cash Flow 42 44 Interest Rates Periodic Progress & Milestone Payments 45 Conclusion59 Chapter 5: The Schedule 61 Float62 Time Is of the Essence 64 Extra Time, but No Money 66 Conclusion68 Chapter 6: Assurances of Performance 69 Guaranties & Bonds 70 What Does “Failure to Perform” Mean? 72 viii Get Complete eBook Download by Email at discountsmtb@hotmail.com 72 What Is a Bond? Forms of Assurances of Performance 73 Surety Companies 78 Some Language Considerations on Guaranties & Bonds 82 Types of Performance Assurances 82 Conclusion101 Chapter 7: Insurance 103 What Is Insurance? 104 Claims Made vs. Occurrence 105 Types of Insurance 106 Important Issues Associated with Insurance 112 120 Additional Insured Status Additional Insurance Basics 121 A Typical Insurance Clause in a Construction Contract 134 Safety140 Chapter 8: Indemnity 141 142 Insurance & Indemnity Indemnity Definitions 142 143 Transferring the Owner’s Risks to Contractors Fairness Is Not a Consideration 143 Is an Indemnity Required in a Construction Contract? 144 144 Anti-­Indemnity Legislation Examples of Indemnification Clauses 150 Indemnification, Additional Insured Status, & Contractual Liability Insurance 157 Owners Love CLAIMS! 161 Negotiating Indemnity Clauses 162 Knock-­for-­Knock Indemnities 165 Conclusion166 Chapter 9: Changes 169 Some Ground Rules 170 Protecting the Project Manager 170 Owners’ Directives 171 Constructive Changes 171 Payment for Changes 172 Sample Change Clauses 172 Major Contract Changes 178 Negotiating Change Clauses 179 Conclusion180 ix Get Complete eBook Download by Email at discountsmtb@hotmail.com 183 Chapter 10: Disputes & Their Resolution What’s a Project Manager to Do? A Short Story to Start With 183 Disputes—­The Construction Contract’s Bad Actor 184 An Ounce of Prevention 186 Dispute Resolution Options 186 The Folks who Negotiate, Mediate, Arbitrate, & Litigate 188 Dispute Resolution Clauses 189 Conclusion192 Chapter 11: Damages 193 194 Breach of Contract/Failure to Perform Contractors’ Financial Exposure 194 Actual Damages—­A Silent Risk? 194 Liquidated Damages 196 Consequential Damages 204 Conclusion206 207 Chapter 12: Warranties A Workable Definition of Warranty 207 Warranty Issues 208 214 The Uniform Commercial Code When Is No Warranty Appropriate? 217 219 Extended Duration Warranties Limiting Provisions in Warranties 221 Pass-­Through Warranties 221 222 Latent Defects & Warranty A Sample Warranty 224 Conclusion224 Chapter 13: Termination & Suspension 227 Termination for Cause 228 229 Termination for Convenience Suspension232 Cancellation236 Conclusion236 Chapter 14: Force Majeure 239 Negotiating Clauses 239 Sample Contract Language 240 Conclusion244 Chapter 15: Other Contract Clauses 245 Site Conditions 246 Use of Completed Portions of the Work 251 x Get Complete eBook Download by Email at discountsmtb@hotmail.com 252 Patent Indemnity Secrecy & Confidentiality Clauses & Agreements 253 Owner’s Right to Inspect 254 Independent Contractors 257 Assignment258 Acceptance & the Punch List 260 Advance & Partial Waiver of Liens 262 265 Final Waiver of Liens Audit Rights 268 Severability or Validity Clauses 269 269 Venue & Applicable Law Florida Civil Code Chapter 47 Venue 270 Texas Business & Commercial Code Annotated §272.001 271 Venue and Choice of Law State Statutes 271 271 Contractual Rendition? 272 Changes in the Law Some Interesting Clauses to Close 273 Chapter 16: A Construction Contractor’s Contract Checklist 275 Chapter 17: International Contracting 283 284 International Contracts The U.S. Foreign Corrupt Practices Act 285 286 Letters of Credit Split Contracts: Onshore & Offshore Contracts 288 289 Political, Religious, & Economic Risks Overseas Private Investment Corporation (OPIC) 290 Legal Systems in Foreign Countries 290 Local Employees, Partners, & Agents 291 Offshore Companies 292 Currency Risks 293 Applicable Law 297 Joint Ventures 299 Joint Operations 299 Import & Export Considerations 300 Understanding INCOTERMS 302 The Export‐­Import Bank of the United States 305 Where to Get Some Help—­Ask the U.S. Government 306 Lastly, Use the Right Paper Size! 307 Conclusion307 xi Get Complete eBook Download by Email at discountsmtb@hotmail.com Chapter 18: What’s It Take to Do Business in Southeast Asia? Patience Is Golden Walk the Talk Time and Money The US Foreign Corrupt Practices Act Center for Strategic and International Studies Trans Pacific Partnership (TPP) Backdoor to China and India SPECIAL SECTION—­The Socialist Republic of Vietnam (Vietnam) Resources for Business in Southeast Asia Chapter 19: Some Final Thoughts on Negotiating Contracts Why Negotiate? The Concept of Standard Terms & Conditions Risk Transfer Item 1: Get Rid of the Indemnity Clause! Risk Transfer Item 2: Don’t Provide Additional Insured Status Risk Transfer Clauses, Insurance, & Safety How to Say No without Aggravating the Owner The Worst Contracting Word: “Reasonable” The Best Contracting Word: “Notwith- standing” Win-­Win & Lose-­Lose in Contract Negotiations—­Fairy Tales? Is There a Price for Bad Commercial Terms & Conditions? Terms of Payment Some Tips on Successful Negotiating Three First (and Final) Suggestions Resources Glossary Index xii 309 310 310 311 312 313 314 314 316 317 319 320 320 322 323 323 324 324 325 326 327 327 328 328 329 333 349 Get Complete eBook Download by Email at discountsmtb@hotmail.com Acknowledgments I am grateful to the following people who, by sharing their long-­term experience in working with construction contracts, added significantly to this book. John T. (J.T.) Wodarski and Joseph J. Newman Jr., each of whom has over 30 years of valuable experience in negotiating commercial terms and conditions of engineering and construction contracts, provided many suggestions for improvements in how the issues were covered in this book. Neither of these two friends (and tough negotiators) hesitated to challenge me to clarify or expand on some of the contracting and negotiating guidance I drafted. The results were significant improvements to the content of the book. Robert W. Wolfe Esq. has negotiated and reviewed many large and small domestic and international engineering and construction contracts from a legal standpoint for more than 25 years. He kept me straight on the many legal fine points associated with the riskiest commercial terms and conditions found in contracts. He is the most practical and effective lawyer I have ever had the opportunity to deal with in the engineering and construction business. Bruce Wilkinson Esq. has been working with a wide variety of contracts for over 35 years. He provided many insightful and useful comments and suggestions on construction contract commercial terms and conditions. Gwen A. Schroder and Ed Jacobs shared their extensive knowledge of the insurance industry to help guide me through the technical issues associated with insurance for construction projects. xiii Get Complete eBook Download by Email at discountsmtb@hotmail.com And my wife, Marilyn, a former teacher, reviewed every word in the book at least twice and made every effort to ensure my spelling and grammar were generally correct. While she did an excellent job, she told me she never again wants to read anything about indemnities. Amen. xiv Get Complete eBook Download by Email at discountsmtb@hotmail.com About the Author Kit Werremeyer is the owner and president of Southernstar Consultants LLC, of Valrico, Florida, a company that provides training in the understanding and negotiating of construction contracts. The company also offers a broad range of other professional services to United States and international engineering and construction companies. Mr. Werremeyer’s experience includes more than 30 years of sales, contracting, claims settlement, dispute resolution, and EPC project development, including work for a broad range of major U.S. and international companies, such as Bechtel; Kellogg, Brown & Root (KBR); Fluor; J.A. Jones; Black & Veatch; DuPont; Shell Oil; Caltex; Exxon/Mobil; BP/Amoco/ARCO; Air Products and Chemicals; Koch Industries; Florida Power and Light; Chiyoda Corporation (Japan); Japan Gasoline Corp.; Mitsui (Japan); Mitsubishi Heavy Industries (Japan); Petronas (Malaysia); Thai Oil Company; Pertamina (Indonesia); SINOPEC (Peoples Republic of China); Voest-­Alpine (Austria); Daelim (Korea); and Hyundai (Korea). Among prior positions, Mr. Werremeyer served as vice president and area director of sales and marketing in Asia for Chicago Bridge & Iron Company, an international engineering and construction company. This position included responsibility for contracting and the general management of area subsidiaries. He is a graduate of the University of Illinois at Urbana-­Champaign, Illinois, with a master’s degree in mechanical engineering. xv Get Complete eBook Download by Email at discountsmtb@hotmail.com Preface In 1977, I entered a year-­long sales training course presented by my company, Chicago Bridge & Iron Company (CBI), an international engineering, procurement, and construction contractor founded in 1889. CBI believed that all of its salespeople must have a strong foundation in understanding, evaluating, and negotiating the commercial terms and conditions typically found in engineering and construction contracts. Specifically, the course was to prepare its future salespeople to provide clients with “one-­stop shopping.” This meant being able to work out all the technical and constructability details of the contract with the client, and then negotiating appropriate commercial terms and conditions without necessarily having to go back to CBI’s legal department for advice. This extra capability—­evaluating and negotiating commercial terms and conditions for construction contracts—­was designed to give us a clear edge over our competitors. We could work closely with the client on all aspects of the project—­both technical and commercial—­ and then close the deal commercially without ever leaving his side or making an outside telephone call. The sales training program included a lot of classroom time on such seemingly routine contractual considerations as terms of payment, scope of work, schedule, claims and disputes, termination and suspension, and warranties. It also introduced us neophyte contractors to such new and mysterious contractual terms as indemnity, additional insured status, force majeure, advance waivers of rights, specialty insurance xvii Get Complete eBook Download by Email at discountsmtb@hotmail.com coverage, and assurances of performance. The instructors told us horror stories about the financial consequences that arose out of accepting a client’s risky commercial terms and conditions for engineering and construction contracts. This training course set the path of my career as, for the next 25 years, I worked in several different sales offices located on the East Coast and the Midwest of the U.S. and for 13 of those 25 years, in Southeast Asia. I participated in and/or managed the negotiations of the commercial terms and conditions for hundreds of engineering and construction contracts ranging in value from small $50,000 repair projects, to major engineering, procurement, and construction (EPC) projects worth over $100 million. Clients ranged from small owners to major international oil, gas, chemical, and petrochemical clients, and major domestic and international EPC contractors from the U.S., Europe, and Asia. There were a huge variety and complexity of commercial terms and conditions in all these contracts over those 25 years. Every owner or EPC contractor had their own favorite idea of what constituted acceptable commercial terms and conditions. Negotiating acceptable terms and conditions for CBI projects was always a challenge; nothing ever was the same. On a few occasions, the client’s commercial terms and conditions were so one-­sided and unacceptable, and the client was so reluctant to change them, that the only thing left to do was close the file and walk out the door. It was time to let some other poor contractor suffer with those lousy commercial terms and associated risks. When I retired in 2001 after 32 years with CBI to form my own company, I looked back at all the diverse practical negotiating experience I had with engineering and construction contracts in the U.S. and internationally and felt it was important to write a practical, user-­friendly, and non-­legalistic book about this subject. It is my hope that my own experience will help contractors, regardless of the size or sophistication of their companies, to negotiate better and less risky commercial terms and conditions for construction contracts—­and thereby better protect their assets. I hope that contractors can learn something from this book and use it as a practical desk reference. If by reading this book, they learn nothing more than to be able to better identify, understand, and evaluate risky commercial terms and conditions, and then negotiate or otherwise seek help to resolve them, I have succeeded. xviii Get Complete eBook Download by Email at discountsmtb@hotmail.com Disclaimer During the course of writing this book, I was reminded on several occasions by my good friends and excellent reviewers that I needed to include a written disclaimer regarding the reader’s use of the contracting and negotiating guidance provided—­as it is impossible to anticipate all the circumstances that may arise in a construction contract. I have tried my best to provide what, in my experience and opinion, is practical information gained from my over 30 years in the engineering and construction business. My hope is that this book will help contractors and subcontractors understand, evaluate, and favorably negotiate construction and construction-­related contracts and thereby help protect their assets. I do not provide any express or implied warranty on the use of any of the information contained in this book as it may be applied to understanding, evaluating, and negotiating construction contracts. Readers should consult, as needed, with professionals on their particular contracts and circumstances. – Kit Werremeyer xix Get Complete eBook Download by Email at discountsmtb@hotmail.com Introduction There is no price for bad terms. ~ Construction contractor from Toledo, Ohio The Goals of This Book This book was written with three important goals in mind: 1. Assisting contractors in improving their abilities to identify, understand, and evaluate certain high-­risk commercial terms and conditions typically found in all construction contracts. 2. Providing contractors with negotiating suggestions on how to lower or eliminate the risk associated with commercial terms and conditions. 3. Providing straightforward information in as uncomplicated and non-­legalistic a manner as possible. The book will help contractors in their effort to negotiate favorable commercial terms and conditions for their construction contracts. By doing so, this will help lower their commercial risk; assist in improving their terms of payment; and reduce their exposure to claims, disputes, and unnecessary or inappropriate risk transfer and its associated potential financial liability. What Are the Benefits of This Book? Contractors must be able to identify, understand, and evaluate all the commercial risks that are accepted by agreeing to an owner’s proposed contract. They must then be able to effectively minimize and manage those commercial risks—­mitigating or eliminating them through negotiations—­and thereby lessen their exposure to any potential financial liabilities. This will ultimately protect the assets of their companies. This is the primary benefit of this book. xxi Get Complete eBook Download by Email at discountsmtb@hotmail.com Contractor & Owner Conventions This book refers to contractors and owners—­both in the general sense, and capitalized in actual sample contract clauses. “The contractor” refers to you, the reader of this book—­whether general contractor or subcontractor—­working hard in the construction business trying to make a living. “The owner” refers to the company that the contractor is providing construction work for, and with whom he will sign a construction contract. (Note that throughout this book, the masculine singular “he” is used, for simplicity only, and to avoid the more cumbersome “he/she”/“his/her” construction.) Also for simplicity, the book refers to the construction contract between the owner and contractor. Often, however, the contractor will have a contract with another construction company who works for the owner, perhaps in the role of the owner’s project manager, or the owner’s main contractor. In this case, the contractor would typically be considered a subcontractor, and his construction contract would likely be called a subcontract with the owner’s project manager or main contractor. It doesn’t matter whether the contract is made directly with the owner, or whether it’s a subcontract with the owner’s PM or main contractor—­the information contained in this book about understanding and negotiating construction contracts applies equally to all of these contracting relationships. Private Contracts or Government Contracts? The contracting concepts presented in this book apply to contractors working with private U.S. owners, and not federal or state government owners. Construction contracts with U.S. federal, state, and local governments may have different commercial contracting challenges. Sometimes, for instance, government contracts are, by law, nonnegotiable with respect to the types of commercial terms and conditions a contractor must accept. However, the concepts and suggestions in this book can be used to help better understand and manage similar commercial issues in government construction contracts, and can assist the contractor, particularly in those situations where negotiation is an acceptable part of the government’s contracting process. In Chapter 16, “International Contracting,” the additional concepts presented also apply to contracts between a private contractor and a private owner. Contracting with foreign governments and their various departments often presents exceptional contracting challenges that are beyond the scope of this book. Key Contracting Concepts Throughout this book, two key contracting issues with construction contracts are discussed: • Commercial Risk: The risk associated with the potential for the contractor to be harmed in some way by accepting the wording xxii Get Complete eBook Download by Email at discountsmtb@hotmail.com in an owner’s construction contract’s commercial terms and conditions. • Potential Financial Liability: The possibility of having to pay money, which would arise from the obligations that a contractor agrees to accept in the owner’s construction contract’s commercial terms and conditions, and that might arise also from the contractor’s common law obligations. Common law is the body of law that develops out of decisions made by courts—­ called precedence—­rather than law that is created by statute. Examples of Commercial Risk Commercial risk creates an exposure to the potential for financial liability and flows directly from the commercial terms and conditions contained in the owner’s construction contract. Commercial risk is probably the risk a contractor finds most difficult to understand and manage. Some typical examples of a contractor’s exposure to commercial risk found in a construction contract’s commercial terms and conditions are: • Exposure to the financial liability to pay liquidated damages or other consequences of contractor’s late performance. • Exposure to the financial liability to pay for damages that are caused by the owner’s negligence. • Not being paid for legitimate changes for additional work. • Not being able to settle legitimate disputes in favor of the contractor. • Exposure to an owner cashing in a contractor’s performance or payment bond without legitimate reasons. • Exposure to the financial consequences—­not enough cash to pay bills—­of not being paid by the owner on time for progress payments. • Exposure to the financial liability that may arise out of lengthy warranty periods or requests by an owner to perform warranty work that is really not warranty work. • Exposure to the financial liability that may arise out of other risks encountered on a construction project, such as differing site conditions and force majeure. Two Types of Commercial Terms & Conditions The commercial terms and conditions typically found in a construction contract can be split generally into two categories: • Administrative terms • Financial liability terms xxiii Get Complete eBook Download by Email at discountsmtb@hotmail.com Administrative terms are those commercial terms and conditions that have a low probability of creating a significant financial liability for the contractor. Financial liability terms have a high probability of doing so. The focus of this book is to improve the contractor’s ability to understand and evaluate these financial liability terms and conditions and learn ways to lower or eliminate the commercial risk associated with them through effective negotiations. A typical construction contract can be divided between administrative and financial liability terms as shown in Figure 1. This book will discuss only those commercial terms and conditions that tend to create a high probability of financial liability for the contractor. This doesn’t mean, however, that other terms and conditions should be ignored or taken lightly. It just means that if the contractor has to focus his effort primarily on one of these sets of commercial terms, it should be on the commercial terms that have the greatest potential for harm. Figure 1: Types of Contract Terms xxiv Get Complete eBook Download by Email at discountsmtb@hotmail.com The Most Important Commercial Terms & Conditions The Contracting Process The three most important commercial terms and conditions contained in all construction contracts are: 1. Scope of work 2. Pricing and terms of payment 3. Schedule These commercial terms are the three foundation stones of all contracts, as shown in Figure 2. Here’s a bold statement: There is no difference between a construction contract for a new one-­story office building worth $500,000 and a new grassroots oil refinery worth $1 billion. Think about this for moment. The contractor for each project must have a written construction contract to perform the work described. Each contract will have a scope of work section, terms of payment, and a schedule. Further, each contract will likely have contractual obligations for insurance, warranty, changes, dispute resolution, termination and suspension, damages, indemnity, and assurances of performance. Certainly, the complexities of the two projects are significantly different, but the contracting process of understanding and negotiating commercial risk issues and potential financial liability issues are the same, and must be properly dealt with by each contractor in order to protect the assets of their companies. Excuses for Not Negotiating Better Commercial Terms & Conditions What are the typical excuses given by contractors when faced with the prospect of having to try to negotiate better commercial terms and conditions in the owner’s construction contract? Some of the most common: • “It’s too hard to deal with the owner and his lawyers.” • “The owner will disqualify me if I take exception to his terms and conditions.” Figure 2: Three Foundation Stones of a Contract xxv Get Complete eBook Download by Email at discountsmtb@hotmail.com • “I don’t understand the terms and conditions well enough to negotiate better ones, and I don’t want to hire a contracts expert or a lawyer.” • “The competition accepts the owner’s terms and conditions all the time, so I don’t have much of a chance.” • “I don’t like to negotiate. Maybe the best thing to do is just sign the contract, put it in the bottom drawer of the desk, and hope nothing happens.” The last excuse basically says this: “sign, do nothing, and pray for the best.” This strategy works fine as long as nothing goes wrong during the execution of the contract. However, things often do go wrong during the course of executing construction contracts! Let’s say the owner creates lengthy delays to the construction schedule, refuses to acknowledge his fault, then penalizes the contractor by imposing liquidated damages for late performance. Once something like this happens to a contractor just once in his lifetime, he will wish he had made the effort to negotiate more favorable commercial terms and conditions prior to signing the contract. One good reason to negotiate changes to the owner’s commercial terms and conditions is simply to improve the contract for the benefit of the contractor, and to lower the contractor’s exposure to potential financial liability at the same time. For example, creating a detailed scope of work document that carefully outlines what the contractor, owner, and all other parties involved in the contract are obligated to do will always serve to minimize misunderstandings and disputes over the scope of work. Often the contractor has the best experience and background to assist the owner with developing a detailed and comprehensive scope of work document. The Concept of Risk Transfer Another contracting concept that will be discussed throughout the book is the concept of risk transfer. Commercial terms and conditions, such as those associated with insurance and indemnity clauses, transfer the risk of potential financial liability for certain events from one organization to another. Insurance transfers the risk of certain potential financial liabilities from the contractor—­the named insured—­to the insurance company in return for the payment of a premium. An indemnity clause in a construction contract can transfer to the contractor the risk of certain potential financial liabilities that may arise due to the negligence of the owner—­in return for nothing! Contractors must understand the consequences of accepting risk transfer clauses in a construction contract. Negotiating changes to risk transfer clauses can significantly lower exposure to the possibility of unnecessary or unwarranted financial loss. xxvi Get Complete eBook Download by Email at discountsmtb@hotmail.com This Is a Book Developed Just for Contractors Before the contractor signs the contract, he needs to understand the commercial risks and their possible financial consequences. The contractor’s assets are at stake. This book is not designed to be antilawyer or anti-owner. It is designed to be pro-contractor. Every attempt has been made to write this book in as non-legalistic a manner as possible. It was written for those contractors who have no legal training in contract law and are simply in business to engineer, procure, and safely build construction projects. Anyone who is willing to take the time to understand the basic concepts of construction contracting can become effective in understanding, evaluating, and managing commercial risk and negotiating more favorable commercial terms and conditions. Can a lawyer who specializes in construction contracting help a contractor understand and negotiate a construction contract? Certainly he can, but that assistance, and cost, is not always necessary. The book features samples of actual contract language—both the good and the bad, the fair and the unfair. Each chapter contains these easyto-understand clauses, in boxes for quick reference, which show contractors the kind of language that should be used, as well as jargon and unreasonable terms that should be avoided. Having a good working knowledge of the major commercial issues involved in construction contracting will help a contractor understand what he is getting into, the risks he is taking, and the risks he doesn’t want to take. Is the contractor agreeing to a fair contract, or taking on a lot of unnecessary responsibilities and commercial risks? Will he get paid on time? These are the types of questions a contractor will be able to answer and resolve after reading this book—before signing a construction contract. It may appear when reading through this book that owners are cast in a bad light, and that all too often they demand unacceptable commercial terms and conditions. This is not true. Some progressive owners have, or will negotiate, commercial terms and conditions that are fair and balanced for both parties—the owner and the contractor. The contractual issues covered in this book are meant to raise the awareness of contractors to worst-case situations that can arise from accepting certain commercial terms and conditions in a construction contract—and how to edit and reword unfair clauses. Three Final Suggestions Finally, contractors should remember these three important things: 1. Read and understand everything in the construction contract. 2. Negotiate better commercial terms and conditions with the goal of reducing commercial risk and the associated exposure to potential financial liability. 3. Get all agreements in writing from an authorized representative of the owner! xxvii Get Complete eBook Download by Email at discountsmtb@hotmail.com Get Complete eBook Download link Below for Instant Download: https://browsegrades.net/documents/286751/ebook-payment-link-forinstant-download-after-payment Get Complete eBook Download by Email at discountsmtb@hotmail.com Chapter 1 What Is a Contract? The Steps to a Contract Contracts: Basic Training This isn’t a trick question, and it doesn’t have a complicated answer. For the purposes of this book, the following definition will be used: A contract is a written agreement that clearly defines the responsibilities and obligations of each included party, is legally enforceable, and is dated and signed by an authorized representative of each party. A contract may also be called an agreement. The term contract will be used throughout the book. 1. Receive an inquiry or request for proposal (RFP) from the owner. 2. Prepare a proposal for the work and submit it to the owner. 3. Negotiate all the details of the contract with the owner. 4. Sign the contract. Understanding and Negotiating Construction Contracts: A Contractor’s and Subcontractor’s Guide to Protecting Company Assets, Second Edition. Kit Werremeyer. © 2023 John Wiley & Sons, Inc. Published 2023 by John Wiley & Sons, Inc. 1 Get Complete eBook Download by Email at discountsmtb@hotmail.com It doesn’t appear to be too complicated, does it? However, there are hundreds of issues—­small and large—­to consider and things to do during the process of responding to an owner’s RFP. The contractor must: • Review and analyze all the written bid documents, including any attached plans, drawings, and specifications. • Resolve questions about the scope of work. • Visit the site. • Assess the physical and commercial risks. • Select subcontractors and suppliers. • Prepare an estimate and proposal. • Review and comment on the commercial terms and conditions. • Sort out insurance details. • Negotiate improvements to the contract. This chapter covers the basic concepts of contracting and explains some of the terminology contractors most often encounter. Coming to the Party? So who is a party to a contract? In almost all construction contracts, there will be at least two parties. One is the contractor (who is going to build something), and the other is the owner (who has a need for what is being built). If the owner hires a project manager to manage all the contractors on the project, then the owner’s project manager would also be considered a party to the contract. All persons or organizations that have not signed the contract are called third parties. Some typical third parties a contractor might see at or near the project job site are: 1. The owner of the commercial property and buildings adjacent to the project site. 2. An OHSA safety inspector making a visit to the job site. 3. Another contractor, his subcontractors, and their personnel who are also working for the owner on the project site. 4. Subcontractors working for the contractor who are not signatory to the contract with the owner. 5. Local private homeowners or small business owners and tenants adjacent to the site. 6. Environmental protection groups. 7. The general public, who may wander onto the job site. 2 Get Complete eBook Download by Email at discountsmtb@hotmail.com The Risk Associated with Third Parties What’s all the fuss over this business of third parties? The actions of these people or organizations can create serious commercial risks and potential financial liability for both the contractor and owner. Contractors must manage a multitude of job site safety issues in order to avoid employees’ injuries. Damage to a third party’s adjacent property or injury to a third-­party individual, such as a member of the general public, exposes both the owner and the contractor to lawsuits, legitimate or otherwise, that could financially ruin either or both of them. Much of the concept of commercial risk transfer involves transferring risk from the owner to the contractor. Risk includes potential financial liability associated with damage to property belonging to third parties and injury to or death of third-­party individuals, regardless of any contributing fault or negligence of the owner. This transfer of risk is accomplished mainly by the use of indemnity and additional insured clauses. (These topics are covered in detail in Chapters 7 and 8 of this book.) So although the contract is between the contractor and the owner, the contractor has to recognize that individuals or organizations not associated directly with the contract—­third parties—­may have an impact on the contract risk. The Starting Point The starting point for a construction contract is when an individual or company decides to construct a new facility to meet its needs. An Example Wilson Properties conducts a search of local building contractors and finds several that are qualified, including National Construction Company. Wilson Properties prepares a written inquiry, or as it is commonly called, a Request for Proposal (RFP), and sends it out to several contractors for competitive bids. The RFP would typically include: • A description of the scope of work • Some idea of a schedule • The plans and specifications prepared by a design team and approved by the building department • Applicable codes and standards • Commercial terms and conditions the owner expects the contractor to accept 3 Get Complete eBook Download by Email at discountsmtb@hotmail.com The RFP might also require the contractor to indicate in writing whether he will provide a proposal for the work by the time specified in the inquiry, or whether he will decline to bid. “Here’s My Proposal” The written proposal, such as prepared by National Construction Company, to perform the work is called an offer and is the first half of the contracting concept of offer and acceptance. The offer will include the contractor’s price and schedule to perform the work and may contain responses to information requested by the owner’s inquiry. It may also address specific work scope and commercial clarifications, as well as any other concerns of the contractor. An Example Offer and acceptance is the technical term used to test whether a contract has been arrived at or not. A more workable and practical definition of the offer and acceptance process is successful contract negotiations. 4 National Construction Company may propose a different completion schedule than required by Wilson Properties’ RFP documents, technical substitutions, or other cost- or time-saving alternatives. National Construction Company may also propose changes to the commercial terms and conditions that were included in the Wilson Properties’ RFP documents. “And I accept, but. . .” Wilson Properties receives the proposal (offer) to perform the work from National Construction Company, reviews it for general compliance with the RFP, and decides that it is a good offer and that they would like to award the project to National Construction Company. However, Wilson Properties has some issues with the schedule, the price, and the clarifications to the commercial terms and conditions proposed by National Construction Company. Wilson Properties has National Construction Company come to their office to negotiate and tells them, “We would like to accept your offer, but. . .” The two companies then proceed to negotiate a mutually agreed-on schedule, price, and set of commercial terms and conditions. The acceptance of the offer in this instance is actually a process. Wilson Properties and National Construction Company negotiate back and forth until they reach a mutually-agreeable deal. The final offer is defined through the negotiations, and both parties say, “Okay, we agree. We have a deal.” This back and forth negotiation is the contract negotiation process. All of the negotiated changes to Wilson Properties’ original RFP are documented in writing. The best way to do this is to make the appropriate changes in the body of the signed contract. An alternate way is to document all the changes in a separate letter signed by Get Complete eBook Download by Email at discountsmtb@hotmail.com both parties noting that the changes agreed on supersede and take precedence over the contract and any similar or conflicting provisions. Wilson Properties then advises National Construction Company in writing that they have been awarded the project, referencing the original RFP and the letter documenting all the negotiated changes to the RFP. This written notification by Wilson Properties signifies their acceptance of National Construction Company’s offer, as was revised and agreed on through the two companies’ negotiations. These are the first two key steps taken in the process of arriving at a contract: offer and acceptance. “Consideration,” or Something of Value Each party to the contract must receive something of value in order for the contract to be legally enforceable. In the previous example, the contract calls for Wilson Properties to receive a new office building that will be built in accordance with the RFP—­and the changes to the RFP mutually agreed to in writing by both parties. The finished building that Wilson Properties will receive is referred to as something of value. National Construction Company receives the agreed-­on contract price to construct the building for Wilson Properties. The money—­ contract price—­that National Construction Company receives is also considered something of value. Both parties to the contract receive something of value, also known as consideration. The “Happy Test” Both parties must mutually and freely agree to all the conditions spelled out in the contract. In order for the contract to be legally enforceable, neither party can use coercion to get the other party to sign. A contract cannot obligate one party or the other to do something illegal. An illegal obligation would cause the contract to be unenforceable. For example, if one party to a contract brings in a group of armed thugs and says to the other party, “sign, or else,” then that clearly is coercion, and the resulting contract would not be legally enforceable. This is an extreme example, but it makes the point. If the written conditions in the contract require one of the parties to have the responsibility of periodically bribing the local customs official (an illegal act) in order to have him under-­apply import duties, then the contract would not be enforceable. There can be nothing in a contract that requires one party or the other to do something illegal. The best advice is: when in doubt, don’t agree to do it. 5 Get Complete eBook Download by Email at discountsmtb@hotmail.com “Can That Person Sign This Contract?” There are two issues here: the first one involves the competency of the person signing the contract, and the second one involves whether that person has the authority to sign. Both parties signing the contract must be competent. If the person signing the contract is under the influence of drugs or alcohol, or has a serious mental incapacity, then that person probably does not have the competency to sign the contract. The contract would likely be legally unenforceable. A more common concern is whether the person signing the contract for one of the parties has the authority to do so. An Example A contract may be unenforceable if it is signed by someone who does not have the proper authority to commit the party he represents to the requirements in the contract. A young employee of the owner who has just graduated from college is getting ready to sign a high-value EPC contract on behalf of the owner for a major expansion to a complex petrochemical plant. The contractor for the expansion questions the young person’s authority to sign the contract. The contractor is accustomed to having much more senior representatives of the owner sign contracts for such major projects. In a situation like this, the contractor might request that the proposed signer of the contract produce a power of attorney document from the company president, or some other senior officer, granting specific authority to sign the contract. This is a simple solution to resolving the issue of proper authority. It’s not too unusual for the owner’s RFP to require the contractor to have an officer of the company sign the contract. If someone other than an officer of the contractor’s company plans to sign the contract, then he must present to the owner an appropriate power of attorney document giving the signer the authority to sign contracts and commit the resources of the contractor. Call in the Enforcer to Close the Breach! What does the term legally enforceable mean? A legally enforceable contract exists when: 1. A written contract has been negotiated (offered and accepted), without any coercion, between the owner and the contractor. 2. There is nothing illegal contained in the contract. 3. The contract has been signed by representatives of the owner and the contractor. The contractor and owner (or representatives) have the authority to commit the resources of their companies. If a contract is legally enforceable, the owner can, if necessary, sue the contractor in court to make him live up to his agreed-on obligations as defined by the contract. Likewise, the contractor can, if necessary, sue the owner in court to make him live up to his agreed-on obligations. The court can act as an enforcer of contract obligations. 6 Get Complete eBook Download by Email at discountsmtb@hotmail.com Into the Breach! If the owner or the contractor does not abide by his respective obligations as contained in the contract, then he may be determined to be in breach of contract. This just means that someone who is party to the contract is not living up to what he has contractually agreed to do. Breach of contract is also commonly called failure to perform. It’s mentioned here only because the issue rears its head all the time. How many times have contractors heard it said that, if you don’t do this or that, you are in breach of the contract? There is no reason to get excited; the term is overused to exert leverage on the contractor and is subject to far too many personal interpretations. An Example If an owner agrees in the contract to pay the contractor’s payment invoices 30 days from the date of each invoice, and does not pay until the 32nd day, then the owner technically has committed a breach of contract. The owner may have a variety of reasons—­ legitimate or otherwise—­why he didn’t pay the contractor on time as required by the contract, but he is still technically in breach of contract. Unfortunately, the contractor would have to go to court to have it determined that the owner was actually in breach of contract. It’s always better to find a way to resolve the issue with the owner to get him to live up to the terms of payment he agreed to accept. The court acts as an enforcer in breach of contract disputes by compelling the party who has failed to perform to live up to his contractual obligations, or else pay monetary damages to the other party. Sometimes a contractor will hear the owner use the term material breach of contract. Like many things in a contract, this term is open to much interpretation. In general, a material breach of contract is a failure to perform a contractual obligation, and the failure is extremely serious and damaging to one or both parties. In the previous example, the owner paid the contractor on the 32nd day and so was two days late. That probably would not stand up to the test or interpretation of what constitutes a material breach of contract. However, if the owner paid the contractor 60 days late and did not have a legitimate reason for the delay, it would certainly have a much better chance of being deemed so. 7 Get Complete eBook Download by Email at discountsmtb@hotmail.com A Contract Example The following is an example of a simple “supply and install” construction contract that illustrates contracting basics. An Example National Construction Company responds to Wilson Properties’ RFP for a new office building, negotiates the details (offer and acceptance), and enters into a construction contract, agreeing to supply and construct the office building (something of value for Wilson Properties) in accordance with the drawings and specifications contained in the RFP. National Construction Company also agrees to perform the work within a fixed time period and for a certain fixed price (something of value for National Construction Company). National Construction Company is to receive a downpayment from Wilson Properties prior to starting the work, and will receive the balance upon satisfactorily completing the building. No coercion was used by either party regarding the terms of the contract, and the contract does not include any illegal requirements. The contract document is signed by Wilson Properties’ President and by National Construction Company’s Project Manager (competent parties with authority). In written form, the contract would look something like this: Article 1 – Scope of Work and Price National Construction Company agrees to supply and build a one-story office building on a site provided by Wilson Properties strictly in accordance with the attached Plans and Specifications for a fixed, lump-sum price of $250,000. Article 2 – Schedule National Construction Company agrees to complete the one-story office building within one year from the date of this Contract. Article 3 – Terms of Payment Wilson Properties agrees to pay National Construction Company $50,000 as downpayment immediately upon the signing of this Contract, and the balance of $200,000 immediately upon the completion of the one-story office building. Dated: January 1, 2007 Signed: 8 Wilson Properties National Construction Company __________________ _________________________ President Project Manager Get Complete eBook Download by Email at discountsmtb@hotmail.com This is an example of a legally enforceable construction contract in its simplest form. But that’s all that’s actually required. It includes all the basics: 1. National Construction Company made an offer. 2. Wilson Properties accepted the offer. 3. National Construction Company provides something of value: the one-story office building. 4. Wilson Properties also provides something of value: the payment of $250,000. 5. The contract document is signed by a representative of each company who is competent, and who also has the authority to commit the resources of the company. 6. No coercion was used and no illegal activities are required. This sample contract is extremely simple, but it would be perfectly legal and enforceable. However, almost all construction contracts will very likely be a lot more complex and will have numerous additional clauses to cover a variety of commercial terms and conditions, such as insurance, indemnity, performance and payment bonds, changes, dispute resolution, safety requirements, and schedule and progress reporting requirements. This example could have been expanded to include an additional clause requiring National Construction Company to provide Workers’ Compensation insurance and other types and amounts of insurance, which would read as follows: Article 4 – Insurance National Construction Company will provide statutory Workers’ Compensation insurance in accordance with state laws, Comprehensive General Liability insurance in the amount of $1,000,000, and Automobile insurance in the amount of $300,000. These insurance requirements are typical. Most states require contractors to participate in a Workers’ Compensation insurance program, and owners typically require contractors to also provide General Liability and automobile insurance at a minimum. All the clauses in a construction contract are collectively called the commercial terms and conditions. Commercial terms and conditions define all the responsibilities and obligations of each party to the construction contract. 9 Get Complete eBook Download by Email at discountsmtb@hotmail.com Strange Words & Long Paragraphs There are no requirements—legal, cosmic, religious, or otherwise— for Latin terms to be used in a contract. For example, the Latin term inter alia, which pops up all the time in construction contracts, simply means “among other things.” It’s perfectly okay to say “among other things” if necessary for clarity. Use English! Using only English terms in a simple and concise manner is a much better way to write a clear and understandable contract. Also, there are no requirements, legal or otherwise, for the use of complicated and abnormally lengthy sentences or paragraphs, or any other confusing language that could lead to misunderstanding. The following is an example of an unnecessarily wordy, complex contract clause stating that a contractor has to complete the work in accordance with the contract documents. Article 25 – Contract Completion by Contractor In consideration of all the mutual and independent agreements set forth on the part of the Owner in the Contract as contained herein, Contractor shall, without exception, construct, complete, and maintain the Work in absolute full conformity and in all respects with any and all the provisions of the Contract and Contractor will perform, fulfill, comply with, submit to, and observe all and singular the provisions, conditions, stipulations, and requirements and all matters and things expressed or shown in or reasonably to be inferred from the Contract and which are to be performed, fulfilled, complied with, submitted to, observed by, or on the part of Contractor. Here’s how this clause could be revised to simplify the usual obligation of the contractor to complete the work in accordance with the contract documents: Article 25 – Contract Completion by Contractor Being clear, concise, and specific is the preferred way to write a contract, so that all those individuals responsible for executing the contract understand what they have to do. 10 Contractor shall complete all the Work in full conformity with Owner’s Contract documents. Clear and concise English is the best way to write a construction contract! Being as specific as possible in writing the commercial terms and conditions is okay, too. Broadly worded commercial terms and conditions are subject to broad interpretation, usually to the detriment of the contractor. If there is a dispute over what the language in a particular commercial clause means, the more specific and concise the language, the better the chances are of resolving the dispute. Get Complete eBook Download by Email at discountsmtb@hotmail.com One thing to remember is that if a contractor ends up in a contract dispute, and a third party, like a court or an arbitration panel, reads the commercial terms related to the dispute, there is no assurance that they will interpret the clause the way the contractor believes it should be interpreted. Be as specific as possible so that the interpretation of the wording is clear to everyone. If a contractor does not understand a paragraph in a proposed contract because of its length, construction, or use of legal terms, then he should negotiate a revision to it so that everyone responsible for actually executing the contract can understand and interpret it, too. Contracting Myths One myth to dispel about construction contracts is that of the so-­ called standard construction contract. There is no such thing as a standard construction contract. There can’t be. There’s no such thing as a standard construction project. This “standard construction contract” approach is sometimes used as a negotiating tool to get one party to the contract to accept unnecessary and/ or onerous commercial terms and conditions that are in favor of the other party. Owners will often insist on using their preferred, standard construction contract as a barrier, or stonewall, to try to stop the contractor from negotiating more favorable, less onerous commercial terms and conditions. Their tactic is something like this, “These standard terms and conditions are well established and can’t be changed.” On the other hand, legitimate attempts have been made to try to standardize construction contracts so that the commercial terms and conditions they contain have some balance, are easier to understand and interpret, and are seemingly fair to all parties. This is admirable in its intent, but can lead to laziness in addressing issues unique to individual construction projects, and it may actually increase the commercial risk assumed by one or both of the parties to the contract. Caution should always be taken whenever a “standard contract” is suggested. Examples of standard commercial terms and conditions for construction contracts are those published by the American Institute of Architects (AIA) and the Associated General Contractors of America (AGC). Other options include standard forms from the Engineers Joint Contract Documents Committee (EJCDC) in the U.S. and the International Federation of Consulting Engineers (FIDIC) in Switzerland. There are certainly opportunities to use these standardized terms on construction contracts, but contractors must read them carefully and 11 Get Complete eBook Download by Email at discountsmtb@hotmail.com understand how they apply to the specific project. If some of the standard terms don’t apply, or tend to create excessive commercial risk, then the contractor should modify them or delete them. These standardized terms are not cast in stone, despite the impressiveness of the contract’s appearance. A Second Contracting Myth Another myth to dispel is that only lawyers can write construction contracts. Once a contractor has an understanding of the risk and consequences of accepting certain commercial terms and conditions that can create a potential financial liability for his company, he can negotiate favorable changes to any offending commercial terms and conditions and better protect the assets of his company. Contract Negotiations One important thing to remember about construction contracts is this: all the wording of all the commercial terms and conditions in a proposed contract is negotiable. This is especially so if the contractor’s proposal for the work contains a good price, an achievable schedule, and is technically solid. As long as what the contractor is trying to achieve by changing or modifying the language in a proposed contract is not illegal, then all the commercial terms and conditions that may create a potential financial liability for the contractor are fair game for change. As noted earlier, many owners will have standardized wording for most all of the commercial clauses in a proposed construction contract. They would like for this wording to be accepted by all their contractors. That’s fine, as much of the standardized wording can probably be classified as administrative terms, or, as it is sometimes called, boilerplate, and may not impose any additional or excessive commercial risk and potential financial liability on the contractor. However, a conscientious and careful contractor needs to make sure he carefully reads the contract terms and conditions and understands all the commercial risk associated with accepting the owner’s standard contract wording. If the commercial risk is unacceptable, then negotiations are necessary in order to change the wording to lower or eliminate the risk. An unfortunate caution: some owners have been known to insert unrelated high-­risk terms and conditions within what might be considered administrative terms, perhaps hoping the contractor will overlook them. A final waiver of mechanic’s liens, for example, is a fairly normal requirement for the contractor to provide to the owner 12 Get Complete eBook Download by Email at discountsmtb@hotmail.com There is no substitute for reading and understanding the contract. It is probably the most important part of the contracting process. Of equal importance is the ability to successfully identify and then negotiate changes to any commercial terms and conditions that can create unnecessary commercial risk and financial liability. at the conclusion of a construction contract. The owner may even have a standard form for this. Sometimes that final waiver of liens also contains extra language that waives all of the contractor’s rights to claim legitimate extras that are outstanding. This is unfair, but it does happen, so be careful. After the basics of contracts are understood, the next step is developing an understanding of the general types and forms of contracts that contractors will commonly encounter. This is discussed in the next chapter. 13 Get Complete eBook Download by Email at discountsmtb@hotmail.com Chapter 2 Types & Forms of Contracts Construction contracts do not come in all shapes and sizes. They conform to a fairly well-­defined set of types and forms. Seven common types of construction contracts are: 1. Fixed price and fixed schedule 2. Reimbursable (unit rate and cost plus) 3. Combined fixed price and reimbursable 4. Cost plus fee 5. Guaranteed maximum price 6. Design build 7. Design-­bid-­build Two additional types of contracts that are commonly encountered are similar to the seven listed above, but with an added twist: 1. Target price contracts 2. Contracts with performance incentives Understanding and Negotiating Construction Contracts: A Contractor’s and Subcontractor’s Guide to Protecting Company Assets, Second Edition. Kit Werremeyer. © 2023 John Wiley & Sons, Inc. Published 2023 by John Wiley & Sons, Inc. 15 Get Complete eBook Download by Email at discountsmtb@hotmail.com Fixed Price & Fixed Schedule Contracts All well-defined work that can be accurately estimated and planned is a candidate for a fixed, lump-sum price and schedule contract. These are the most common types of construction contracts. The contractor submits a fixed, lump-sum price for the owner-provided scope of work, as well as a finite completion time schedule. This type of contract can be used for small projects, such as a $5,000 addition to a single-family house, to large contracts, such as a petrochemical manufacturing facility worth hundreds of millions of dollars. An example of this would be when a contractor submits a fixed, lumpsum price of $1,000,000 to an owner, with a firm schedule of 52 weeks to complete an office building. In a fixed price contract, the contractor must have the ability to accurately estimate the costs and time required to perform the work. The contractor also must have the capabilities to execute the contract for the price and schedule as promised. This type of contract requires the owner to provide a comprehensive and accurate definition of the scope of work. For the owner, this type of contract will likely provide the lowest cost or best schedule (or both) to get the work done, since he will probably have asked several contractors to compete for the work and provide a formal bid. Having a fixed price and firm schedule allows the owner to plan better for scheduling and for financing or paying for the project. For the contractor, this type of contract requires estimating and execution skills. It also requires him to make a judgment on how high to price the work to compete with other contractors. One good thing about fixed price and schedule contracts is that, if the contractor performs well against his costs and schedule, it’s likely he will have savings and thereby increase his estimated profit, and there’s nothing wrong with that! On the other hand, if the contractor overruns his estimated costs and/or schedule, it’s unlikely he will get much sympathy—or money—from the owner. Reimbursable Type Contracts There are two common and similar types of reimbursable contracts: • Unit rate • Cost plus Unit Rate Contracts The contractor submits a menu of prices for materials, labor, and equipment to the owner. These prices include all of the contractor’s costs and markups, including profit, for the respective items listed. 16 Get Complete eBook Download by Email at discountsmtb@hotmail.com An Example The owner wants to install approximately one mile of 24" diameter underground cast iron pipe in a 6' deep trench. The contractor provides the following example menu of prices to the owner: • 24" diameter cast iron pipe: $50/linear foot delivered • Project foreman: $75/labor hour worked, no overtime • Laborers: $35/labor hour first 40 hours per week, $55/labor hour overtime • Backhoe: $175/hour fueled and operated • Side-­boom tractor to lay pipe: $175/hour fueled and operated • 12" rock backfill over pipe: $30/cubic yard delivered • Miscellaneous expendables: $250/day At the end of each week during the project, the contractor adds up the length of pipe installed, the labor hours worked by the foreman and laborers, the time of use for the backhoe and the side-­boom tractor, the amount of rock backfill, and miscellaneous expenses. The contractor then applies the reimbursable rates to each, sums them up, and sends the owner a bill. Cost Plus Contracts In a cost plus construction contract, the contractor submits a menu of direct costs and associated markups for materials, labor, subcontracts, and equipment to the owner. The markups (the “plus”) include all of the contractor’s overhead and profit applied to the respective items in the menu. An Example The owner wants to install approximately one mile of 24" diameter underground cast iron pipe in a 6' deep trench. The contractor provides the following menu of costs and markups to the owner: • All pipe materials delivered to site: direct invoice cost plus 20% • Project foreman: $45/labor hour worked, plus 50% fringes and 20% overhead and profit • Laborers: straight time, first 40 hours/week: $23/hour, plus 35% fringes and 20% overhead and profit • Laborers: overtime, after first 40 hours/week: $34/hour, plus 25% fringes and 15% overhead and profit • Backhoe: $145/hour, fueled and operated, plus 20% overhead and profit 17 Get Complete eBook Download by Email at discountsmtb@hotmail.com • Side-­boom tractor to lay pipe: $145/hour, fueled and operated, plus 20% overhead and profit • Rock backfill over pipe delivered to site: direct invoice cost plus 20% • Subcontracts: cost plus 15% overhead and profit • Miscellaneous expenses: direct invoice cost plus 20% At the end of each week during the project, the contractor adds up the invoice costs of all materials delivered to the site, the labor hours worked by the foreman and laborers, the time of use for the backhoe and the side-­boom tractor, the amount of rock backfill, and miscellaneous expenses. He then applies the noted markups to each, sums them all up, and sends the owner a bill. For the owner, these types of reimbursable contracts are useful where the scope of work and schedule are difficult to define. Maybe there’s some rock in the ground, or the terrain is difficult, or the weather is really lousy—­and trying to determine a fair fixed, lump-­sum price might prove difficult or turn out to be very expensive, as the contractor will load up his contingency costs. For the contractor, these types of reimbursable contracts allow him to take on a job without having to provide a large contingency cost for unknown conditions and schedule delays. The contractor probably has to compete with others to get the work, so he’s careful about the level of his reimbursable pricing and the time he estimates it will take to complete the work. On all reimbursable contracts, the contractor should expect that the owner will want to audit his work records for the labor hours billed, the time the equipment was used and billed, and for any other reimbursable work item. Combined Fixed Price & Reimbursable Contracts 18 As the name suggests, this contract is a blend of the two types of contracts. It tends to be used where some of the work is well-­defined, and some isn’t. An Example An owner wants to build a standard-­design, 300-­foot-­tall radio relay tower on the top of a 10,000-­foot-­high, heavily-­wooded mountain. There isn’t anything special or unique about the engineering effort required or the supply of the materials for the tower. However, getting the materials from the base of the mountain to the top on an unimproved roadway, and then installing them, is not conducive to a fixed price, as too many undefinable work and schedule issues are involved. Get Complete eBook Download by Email at discountsmtb@hotmail.com The owner ends up with the following example contract pricing format: • Engineering: $20,000 lump sum • Radio tower material supply: $80,000 lump sum • Transport materials to base of mountain: $5,000 lump sum • Mobilize crew and equipment at site: $5,000 lump sum • Project manager: $100/labor hour worked • Project superintendent: $75/labor hour worked • Steel erectors: $45/labor hour • Clearing and installation labor: $30/labor hour • 10-­ton mobile crane: $125/hour fueled and operated • 5-­ton special transport: $85/hour fueled and operated • Excavation: $5/cubic yard excavated and removed • Portable air compressor and generator: $45/hour fueled and operated • Small tools and expendables: $200/day • Demobilize crew and equipment from site: $3,000 lump sum The contractor bills the owner for the stated lump sums for the engineering costs, supply of materials, transport, mobilization, and demobilization. These scope of work items were well-­defined by the owner in his inquiry documents, and thus are conducive to fixed, lump-­sum pricing. The field installation work proceeds on a “best effort” basis, given the adverse and difficult-­to-­estimate working conditions. The contractor bills the owner for the work performed based on the menu of reimbursable prices provided, just like in the reimbursable contract example. For the owner, this type of contract is useful where some aspects of the scope of work and schedule are easy to define, but some of the work is difficult to define. Trying to get a fair lump-­sum price for the entire project might prove difficult, as the contractor will feel the need to load up his contingency costs for the difficult field working conditions. For the contractor, the combined fixed price/reimbursable contract will allow him to take on a job without having to include a large contingency cost for unknown field working conditions and any delays in schedule. He probably will have to compete with others to get the work, so he’s careful about the level of his fixed, lump-­sum pricing, the level of the reimbursable pricing, and the time he estimates it will take to complete the work. 19 Get Complete eBook Download by Email at discountsmtb@hotmail.com Cost Plus Fee Contracts A cost plus fee construction contract format is often used for large, complex projects. Typically, these projects require a significant amount of conceptual and design engineering, along with a major effort to procure a lot of expensive equipment and materials. These projects also require construction services, including a large and diverse project management staff and a multi-­disciplined craft labor force. There might be a completion schedule of several years or more. In this type of construction contract, the contractor provides, for example, all permits, studies, design services, detail engineering, major equipment, materials, and field construction management and labor, often in a joint effort with the owner. The contractor then bills the owner for the actual costs, and, in addition, bills the owner a fixed fee, which would typically include the contractor’s project management costs, overhead costs, and profit. All the actual costs associated with engineering, procuring, and constructing the project are billed directly to the owner for payment, or reimbursement if the contractor is paying the bills in the first instance as part of the contract with the owner. In addition, the owner will pay the contractor the agreed-­on fee on a prorated basis based on the physical or cost progress of the project. Many cost plus fee contracts have a provision in them to increase the fee should the estimated costs or scope of work exceed a certain amount, or if the estimated schedule extends beyond what was originally estimated. For the owner, a key benefit of this type of contract is that it allows him to build a project on a fast-­track basis. He can negotiate a contract with a specialized and experienced contractor for the project and proceed immediately with conceptual and detailed engineering and procurement of major, long-­lead-­time pieces of equipment. The owner avoids the lengthy fixed-­price process of selecting a main contractor, then going through the development of engineering and the production of bid documents, the bidding and bid review, and final contractor selection process. The owner might expect to save up to a year or more on the completion schedule of major projects with this contracting approach. This type of contract requires full participation of the owner in the cost control and subcontractor selection process. For the contractor, this approach allows him to be reimbursed for all costs associated with the project and provides him with a fee to cover project management, overhead, and profit for the project. If the project expands beyond what was originally expected, then the contract should allow for an adjustment to the contractor’s fee. 20 Get Complete eBook Download by Email at discountsmtb@hotmail.com In this type of contract, all reimbursable actual cost records are auditable by the owner. In addition, the owner might expect to negotiate the amounts in the fee for the contractor’s project management, overhead, and profit. Guaranteed Maximum Price Contracts This type of contract would likely be a reimbursable type, or some combination of reimbursable and fixed price contracts. The distinguishing feature of this type of contract is that the contractor would agree with the owner that the final price to the owner would not exceed a fixed, certain value. In other words, the contract would have a guaranteed maximum price. This is a risky agreement for contractors. If the contractor’s cost of the project exceeds the guaranteed maximum price, then that’s too bad for the contractor. The extra money comes out of his pocket. It is especially risky if the scope of work is poorly defined, and if external factors like weather or labor conditions create expenses that he cannot recover through claims or changes to the contract. For owners, this type of contract is useful where he may, for example, have to fund the project with outside financing and want to cap his exposure to project costs. Target Price Contracts A target price contract is one where the contractor and the owner agree on a certain fixed, lump-­sum price, the target price, and the contractor tries to execute the contract at or below it. One unique feature is that the contractor shares all the costs in the estimates, including his markups and expected profit, with the owner. The owner understands the contractor’s estimating process and supports it. In a target price contract, both parties agree on the level of costs and contractor markups and profit. This type of contract also requires the contractor and owner to have a working relationship based on a high degree of trust. In the event the contractor completes the project below the estimated cost, there will be a cost savings, and the contractor and owner will share that savings in a previously agreed-­on proportion. In the event the contractor overruns the project costs, then the contractor and owner will share the expense of the overrun in a similar fashion. An Example A contractor and owner agree on a price of $3,500,000 to build a new, concrete marine cargo unloading jetty for the owner’s ships. After finishing the project, the contractor manages to save $100,000 on his estimated costs and shares that information with the owner. 21 Get Complete eBook Download by Email at discountsmtb@hotmail.com The contract between the owner and contractor calls for any savings against the target price to be split 50-­50. Therefore, the owner ends up paying $3,450,000 for the project, and the contractor ends up with an additional $50,000 profit. In this type of contract, both the owner and contractor have a strong incentive to work closely together and pool their talents and resources to find legitimate ways to reduce costs and safely expedite the overall project schedule. Design Build Contracts In this type of construction contract, the Owner signs a single-­source contract with a Contractor that will cover all the aspects of the design and construction for the project. The theory is that this will eliminate multiple contracts and subcontracts for the Owner, find cost and time savings, reduce paperwork, and streamline the overall bidding and completion schedule. Contractor led design-­build contracts can be considered where the selected contractor has demonstrated engineering, design, and construction strengths in the type of project being proposed. For example, a refinery or petrochemical plant. Architect-­led design-­build contracts can be considered where the project has some complex and nuance design issues. For example, a hospital or custom home. The contractor for the construction might be part of the architect’s organization or perhaps a joint venture partner. Design-­Bid-­Build Contracts The difference between this type of contract and a design-­build contract is that the Owner issues a separate contract to an architect for the design of the project and a separate contract for the construction of the project. In a design-­bid-­build contract, the construction contractor does not participate in the project’s design. An example of this type contracting process might be a single-­or multistory commercial building. Contracts with Performance Incentives 22 Any of the above-­mentioned types of construction contracts can have performance-­based incentives included. Some typical performance-­ based incentives are: • Safety: such as an incentive bonus for no lost time or recordable accidents. Get Complete eBook Download by Email at discountsmtb@hotmail.com • Quality: such as an incentive bonus for achieving 98% or better flawless x-­rays on all full-­fusion welds in high-­pressure piping. • Subcontracts: such as an incentive bonus for utilizing a certain percentage of minority-­owned subcontractors or suppliers. • Schedule: such as an incentive bonus for finishing ahead of schedule. Performance-­based incentives can play a strong role in achieving certain goals for the owner. For example, if the owner’s company assigns utmost importance to safety, then the owner should be willing to “put his money where his mouth is” by making a pool of extra money available to those contractors on the project who achieve exemplary safety records. On the flip side of this issue are those contracts that contain certain performance disincentives. An example of this may also involve job site safety, a common performance-­based incentive. In addition to the pool of extra money that might be available to the contractor for exemplary safety, the contract may also provide for the contractor to put, say, 2% (or more) of his contract price at risk for poor safety. If the contractor doesn’t meet the project’s minimum stated safety goals for his portion of the work, then the owner has the right to deduct some or all of the 2% from the contractor’s contract price. One common disincentive that can be used by the owner is the imposition of liquidated damages when the contractor fails to meet or beat the contractual schedule. (Liquidated damages and how to deal with them are covered thoroughly in Chapter 11.) Form of Contracts Like the types of contracts, the form that a construction contract takes is fairly standard, too. Organization is typically as follows: 1. Preamble 2. 3. 4. 5. 6. General contract and the commercial terms and conditions Special terms and conditions Attachments incorporated by reference Signature block Order of precedence Preamble Most contracts begin with what is called a preamble, used to specifically identify the parties to a contract. This is an excellent convention to use, as owners may have many different, independent, and separate business units, both U.S. and foreign subsidiaries, that 23 Get Complete eBook Download by Email at discountsmtb@hotmail.com have the ability to enter into construction contracts and commit the use of corporate resources. Preambles are straightforward in their structure and typically read as follows: This Contract is between Wilson Properties (Owner), an organization registered in the State of Florida and having its registered office at 3160 Ponce DeLeon Way, Orlando, Florida, and National Construction Company (Contractor), an organization registered in the State of Delaware and having its registered office at 125 East Orange Street, New York, New York. Note the convention of capitalizing and putting “contractor” and “owner” in parentheses after they are identified as a party to the contract. This is done to define important terms to be used throughout the contract. It’s also a simplifying procedure. Rather than using “National Construction Company” to define the contractor throughout the contract, the capitalized term “Contractor” is used. Defined terms and additional examples are more thoroughly discussed later in this chapter. Recitals Often following the preamble in a contract is something called recitals. Recitals typically begin with the word “Whereas,” or “WHEREAS,” or “WITNESSETH.” A recital typically states facts, issues, or conditions related to the contract and may read similar to the following: WHEREAS: Owner has decided to build a new 10,000 square foot warehouse on property located in Orlando, Florida. WHEREAS: Contractor warrants that it is qualified, experienced, and competent to perform the work. WHEREAS: Contractor has agreed to do the work subject to the terms and conditions of the Contract. The recitals section ends with the following, or similar, sentence: NOW, THEREFORE, IT IS HEREBY MUTUALLY COVENANTED AND AGREED AS FOLLOWS: What follows is the body of the construction contract. The recitals section is an old, and some might say, antiquated practice that doesn’t 24 Get Complete eBook Download by Email at discountsmtb@hotmail.com Get Complete eBook Download link Below for Instant Download: https://browsegrades.net/documents/286751/ebook-payment-link-forinstant-download-after-payment