Uploaded by nam260

1Z0-1075-23 PDF Dumps Your Guide to a Excellent Performance

advertisement
Oracle
1Z0-1075-23
Oracle Manufacturing Cloud 2023 Implementation
Professional
QUESTION & ANSWERS
https://www.genuinedumps.com/1Z0-1075-23-exam-questions.html
QUESTION 1
Your customer is a light assembly manufacturing company that doesn’t require shop floor control. A
manufacturing engineer wants to generate a work definition automatically for some items, and wants
to
eliminate the explicit maintenance of work definitions.
Which three steps must be completed and verified in the Work Definition area?
A. Ensure the predefined work definition name ORA_MAIN name is active.
B. Select a resource that is to be used in automatic work definition by enabling the attribute Default
for automatic work definition.
C. Select a standard operation that is to be used in automatic work definition by enabling the
attribute Default for automatic work definition.
D. Ensure the item is a standard item with a secondary item structure.
E. Ensure there is only one default standard operation at a given point in time.
Correct Answer: A,C,D
QUESTION 2
A user wants to transfer the work order status updates and resource transaction data for costed
resources to Cost Management. Which scheduled process should you run to achieve this requirement?
A.
B.
C.
D.
Transfer Cost to Cost Management
Transfer Transactions to Costing
Transfer Ledger Balances
Transfer General Ledger Balances to Balance Cubes
Correct Answer: A
QUESTION 3
Work order costs are computed based on material and resource transactions reported and the cost
method of the product. In a manufacturing plant, the production operator has completed a work order
WO-001 ensuring proper materials and resource transactions. The materials are costed and resources
are defined with rates. A cost accountant has created cost accounting distributions. Upon reviewing
the accounting distributions of the work order WO-001, resources charged to the work order are
missing. Identify the Concurrent Request that needs to be submitted to transfer resource charges to
cost accounting.
A.
B.
C.
D.
Create accounting
Transfer Transactions from Production to Costing
Transfer Transactions from Inventory to Costing
Transfer Costs to Cost Management
https://www.genuinedumps.com/1Z0-1075-23-exam-questions.html
Correct Answer: B
QUESTION 4
A plant runs 24x7 daily using three continuous shifts of 8 hours each. One unit of an equipment
resource R1 is assigned to each of the three shifts. On a specific work order, the resource R1 is
required to work for 2 hours. The resource is set up with an efficiency of 50% and utilization of 100%.
R1 is scheduled to start on the given work order at noon. What time will R1 be scheduled to finish,
assuming no calendar exceptions have been set?
A.
B.
C.
D.
E.
8:00 PM
12:30 PM
2:00 PM
4:00 PM
1:00 PM
Correct Answer: D
QUESTION 5
Your customer runs two daily shifts in her plant: Morning Shift and Evening Shift. A resource LATHE is
assigned to the work center W1. There are five units of LATHE available, of which three units are
available for the Morning Shift and the remaining units are available for the Evening Shits. Which two
actions must you perform to associate LATHE with W1?
A. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 3
against the resource LATHE in the Morning Shift column.
B. Select the Available 24 Hours check box and in the Resource Availability region, enter 3 against
the resource LATHE in the Morning Shift column.
C. Select the Available 24 Hours check box and in the Resource Availability region, enter 2 against
the resource LATHE in the Evening Shift column.
D. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 2
against the resource LATHE in the Evening Shift column.
E. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 60%
against the resource LATHE in the Morning Shift column.
F. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 40%
against the resource LATHE in the Evening Shift column.
Correct Answer: A,D
https://www.genuinedumps.com/1Z0-1075-23-exam-questions.html
QUESTION 6
A plant operates three continuous daily shifts of eight hours each for five days in a week. One unit of
the
resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given
week,
due to unscheduled maintenance that needed to be performed on the resource R1, it was not
available for two
hours during each of the assigned shifts.
Determine the available capacity of the resource R1 for that week.
A.
B.
C.
D.
78 hours
76 hours
60 hours
70 hours
Correct Answer: B
https://www.genuinedumps.com/1Z0-1075-23-exam-questions.html
Download