Uploaded by sailikith6742

TDC PPT 1

advertisement
1
Presentation for Revision of Mining Plan
Tadicherla-I Coal Block Opencast Mine
Submitted to
Submitted By
Dr. Harish Gupta
P. Mohan Rao
Dept. Of Mining Engg.
ME(PTPG)-Sem-II
06-Aug-2023
2
Location Plan
Tadicherla-1 Coal
Opencast mine
3
Mine & Power Plant locations
4
Mine location in Google Map
Kapuram
5
Project Background
• Tadicherla-I Coal Block was allotted to M/s TSGENCO for
captive mining in August-2015.
• TSGENCO appointed AMR India Limited (AMRIL) as MDO.
• The mining operations started with in 28 months from the block
allotment against the scheduled time line of 44 months, i.e. on
11.12.2017.
• Coal production commenced from 28.04.2018.
• Mining plan approved
…… Aug- 2008
• Mine Closure plan Approved
…… Sep- 2017
• Environment Clearance Obtained .….. Feb- 2016
6
Present status
Production particulars
Year
Coal Production in LT
% of
Achievement
SR
Target
Actual
2018-19
7.33
7.58
103.4
29.15
2019-20
18.00
16.58
92.11
17.98
2020-21
20.00
20.23
101.17
15.06
2021-22
20.00
22.11
110.50
13.61
2022-23
25.00
25.00
100.00
12.27
7
8
Cost comparison between TDC & SCCL Coal price
Cost Of Coal from Tadicherla-I Coal Mine with stripping Ratio of 11.34
(for the operating year 2023-24)
S.No. Description
SCCL Coal Price for G-8 Coal
Amount in Rs. Per
Tonne
GCV
1
Base Mining Fee for stripping ratio of 8.9
1986.00
2
2426.53
(a)
3
Base Mining Fee adjusted to Stripping Ratio of
11.34
Escalated Coal Mining fee Q1(P)
3960.24
(b)
4
Royalty @14% on SCCL Notified Price of G9
427.00
5
10% DMFT on Royalty
6
2% NMET on Royalty
7
Premium Price
8
Cess on Mineral Bearing Lands Rs.20/- per
Tonne
Total Cost of Coal (S.No. 3 +4+5+6+7+8)
9
GST @18%
10
Total cost of coal including GST
11
Transportation Charges 4.12 per KM/Tonne
(Lead Distance 67.5 KM)
12
GST@5%
13
Total Landed Cost(S.No. 10+11+12)
14
Cost difference between SCCL coal &
Tadicherla Coal
Total Cost difference between SCCL coal & Tadicherla
Coal for a quantity of 25L MT of coal in Crores
G8
4901-5200
SCCL Basic Price(ROM) w.e.f.01.05.2023
3730.00
3810.00
(c )
Basic Price (CROM) Crushed Coal
w.e.f.01.05.2023
Royalty (Revised @ 14% of ROM Price w.e.f.
10.05.2012)
NMET @2% on Royalty
42.70
(d)
DMFT @30% on Royalty
522.20
10.44
156.66
8.54
(e)
Surface Transportation Approx
90.00
100.00
(f)
71.00
20.00
(g)
Land Adjustment Cost @ Rs. 61/- & Forest
Permit Fee @ Rs. 10/-wef 7.11.2018
Sampling/Facility Charges
4558.48
(h)
Shunting Charges/ Railway charges
50.00
712.84
(i)
Fuel Surcharge (Revised w.e.f.01.07.2022)
5271.32
(j)
Pre-Weigh Bin Charges
60.00
278.10
(k)
CPMS Corpus charges ( wef 19.12.2020)
10.00
(l)
Explosive cost adjustment wef 1.1.23
13.91
(m)
Taxable value ((a) to (j))
5563.33
886.71
(n)
CGST @2.5%
140.44
221.68
(o)
SGST @2.5%
140.44
(p)
GST Compensation Cess
400.00
Total Cost (m+n+o+p)
Average transportation cost from sccl
Total landed Cost
5.00
686.00
146.40
5617.70
6298.59
151.45
6450.04
9
Year wise Stripping Ratio
11.34
10
Year wise Cost of Coal / Tonne
11
Top soil Storage
12
Settling Pond
13
Flood protection Bund & Settling Pond
14
Drain around mine
15
Plantation in mine
16
Geological Reserves
S No.
DESCRIPTION
MECL GR
1992
SCCL GR
2012
New GR
2021
1
Block Area
(Sq. Km)
6.56
6.29
7.066
2
No of seams
10
14
15
3
Reserves (MT)
50.08
76.69
89.85
41
95
229
6.7
13.37
32.41
4 seam
6 seam
6 seam
4
5
6
No. of Bore
Holes
BH Density
(per sq.km)
Reserves
considered upto
17
Salient Features- Approved Mining Plan
S.No. Description
1
As per Approved Mining
Plan
50.08
2
Total Geological Reserves
(MT)
Extractable Reserves (MT)
3
4
Overburden
(M.Cum)
Avg. stripping ratio (Cum/T)
619.61
13.66
5
6
Life of the Mine in Years
Total land requirement in Ha
22
930
7
8
Rated Capacity (MTPA)
No. of seams present
9
Seams extraction upto
10
Internal dump height
Violation
47.51
2.50
10 ( reserves considered 6 Presently extracting 15 seams
seams only)
4 seam
Presently working upto 6
seam
Upto Ground Level
Internal dump height to be
increased above ground level
18
Reasons for revision of Mining Plan
As per new Guidelines for Revision of Mining Plan
The mining plan may be modified for

for change in method of mining;

change in leased area;

conservation of minerals;

addition of reserve by way of proving of reserve in the existing lease area;

for changes in final mine closure conditions;
19
Reasons for revision of Mining Plan
After 2024-25 there will be no place for dumping the Over burden.
The present internal dump yard is having permission to dump upto
Ground Level only.
-To dump the re-handled OB the height of the internal dump yard has to
be increased, which requires revision of Mining plan and EC.
-The present external OB dumpyard-2 has to be re-handled and to be
dumped in the internal dump yard for removal of coal after 2 years.
20
Revision of Mining Plan-Working Plan
Mine has the production capacity of upto 2 more years as there is no place to dump ob extracted after two years.
-The present ob external dumpyard-2 has to be re-handled and to be dumped in the internal dump yard for removal of coal
beyond 2 years.
- The present internal dump yard is having permission upto Ground Level only. To dump the re-handled OB the height of the
21
internal dump yard has to be increased, which requires revision of Mining plan and EC.
Reasons for Revision of Mining Plan
Tadicherla -1 Mining plan revision comes under the below category
for change in method of mining;
To increase the internal dump height above
the ground level
change in leased area;
To extract the coal with in the New GR
boundary
conservation of minerals;
To extract upto 6 seam
addition of reserve by way of proving of reserve
in the existing lease area;
As per New GR total reserves estimated as
89.85 MT
for changes in final mine closure conditions; or
To change the final void as it is instead of reclaiming
the land upto ground level
22
Revision of Mining Plan-option-1
Option-1
Option-1:
Acquiring 500m danger zone
area beyond the existing
Mining Lease
Coal : 58.30 MT
OB:642.03 M Cum
SR:1:11.01
23
Revision of Mining Plan-Option-2
Option-2
Option-2:
Quarry with New Geological
boundary duly acquiring
Additional land & Danger Zone
area
Coal : 74.77 MT
OB:896.30 M Cum
SR:1:11.99
24
Cost Benefit analysis of the options
Option
Strategy
Analysis of the costs and benefits of the difference in
Reserves between the options with the price of SCCL
coal
Option -1
Option -2
Additional Land acquisition(Ha)
93.54
239.5
Option -1 &
Option-2
145.96
A) Mineable Coal(Mt)**
58.30
74.77
16.47
B) Cost towards acquisition of land & R&R (in
Cr.)*
C) Land &R&R Cost per Tonne in Rs.
D) Mining Fee@ SR 8.9 in Rs./Tonne(for Q3((P) of FY 22-23)
E) Total Cost /Tonne for production in Rs.
712.79
763.30
50.51
F) Cost of Procurement of G-8 Coal from
SCCL(Rs./Tonne)
G) Diff in cost in Rs./Tonne
H) Total savings to TSGENCO in Rs (Crores)
between option 1 &2 –Rs 812.58*16.47
463.45
4651.03
5114.48
5927.06
(+)812.58
13,383
25
26
Download