Uploaded by loboskyrim

imca 2020

advertisement
Dynamic Positioning Station Keeping
Review – Incidents and Events Reported for
2020 (DPSI 30)
IMCA M 256
February 2021
The International Marine Contractors Association (IMCA) is the international trade association representing offshore marine
contractors, service companies, and the industry’s supply chain.
IMCA’s mission is to improve performance in the marine contracting industry. Our value proposition is to influence our industry in
key technical, contractual, policy and regulatory matters that are in the collective best interest of the marine contracting industry.
For over 25 years IMCA has maintained an important body of knowledge to assist our industry in the form of published guidance
documents promoting good practice across a wide range of technical and professional disciplines. Documents have a selfexplanatory title and are catalogued using a code containing letters and numbers. The letter indicates the discipline, and the
number is simply sequential within that discipline.
Members are expected to adopt as a minimum standard the technical guidelines (published documents, information notes and other
materials) produced by the Association appropriate to the technical division(s) and region(s) to which the relevant Member belongs.
Legal Notice
IMCA’s store terms and conditions are available at https://www.imca-int.com/legal-notices/terms/ and apply to all downloads
from IMCA’s website, including this document.
IMCA makes every effort to ensure the accuracy and reliability of the data contained in the documents it publishes, but IMCA shall
not be liable for any guidance and/or recommendation and/or statement herein contained. The information contained in this
document does not fulfil or replace any individual’s or Member's legal, regulatory or other duties or obligations in respect of their
operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.
Feedback – If you have any comments on this document, please email us:
feedback@imca-int.com
IMCA M 256 – Version History
Date
Reason
Revision
January 2021
Initial publication
Rev. 0
DP Station Keeping Review
Incidents and Events Reported for 2020
IMCA M 256 – February 2021
1
Introduction ................................................................................................................... 1
2
DP Station Keeping Summary for 2020 .......................................................................... 2
3
2.1
Participation....................................................................................................................2
2.2
Summary of Causes 2020 ................................................................................................3
2.3
Comparison of DP Incidents and DP Undesired Events/ Observations ..............................9
2020 DP Event Trees and Case Studies ......................................................................... 11
1
Introduction
This volume of DP station keeping events, reported during 2020, has been prepared by the IMCA
secretariat and continues to maintain a high degree of confidentiality and security. Each report
received by IMCA is treated on an individual basis. The person submitting the report is contacted by
email and only once the information contained in the report is anonymised is it used as feedback to
the industry. The importance of receiving reports from the industry cannot be over emphasised; the
information the reports contain is used across all IMCA’s DP activity. This includes new and revised
guidance documents, feedback to client and regulatory organisations and to users through the IMCA
DP Bulletin.
The review and analysis of received reports is ongoing with the aim of encouraging and improving
reporting throughout the industry and providing valuable lessons learnt and meaningful analysis and
feedback. Statistically, authoritative conclusions about the safety of DP operations cannot be drawn
from analysis of the reports received; however, trends or patterns may be determined over time.
In addition to this review, initiating events, causes and comments reported by users have been
incorporated into a summary table for easy comparison. This enables individual DP vessels to readily
complete an onboard comparison of actual events occurring in the industry with the situation on-board
their vessel.
The IMCA 2020 DP Station Keeping Event summary table is available here.
DP station keeping reports are welcome from both IMCA members and non-members alike. Reports
can be accepted in company or other format providing that the analysis can be carried out from the
information received.
The IMCA DP station keeping event report form is available here.
IMCA M 256
1
2
2.1
DP Station Keeping Summary for 2020
Participation
Between 1 January and 31 December 2020, a total of 144 DP station keeping reports were
received from 104 different DP vessels; all these reports have been analysed and included
within this report. Participation in the scheme remains high; this is a positive reaction from
the industry recognising the importance placed on sharing data for the purposes of DP incident
prevention and the safe and efficient operation of DP vessels. However, there is still an
awareness that DP incidents and undesired events are occurring and not being reported. IMCA
will continue to provide lessons learnt from received reports and engage with vessel operators
and other industry bodies to ensure the industry receives the maximum benefit and value from
participation in the IMCA DP station keeping reporting scheme.
The 144 reports submitted by 104 vessels gave an average of 1.4 reports per vessel. As in
previous years, the average rests between one and two reports per vessel. Twenty-eight
vessels reported more than one DP station keeping event; 76 vessels reported just one event.
If the rate of 1.4 reports per vessel were to be repeated throughout the global DP fleet, there
should be a much higher number of reported DP station keeping events.
Reports received
5
4
3
2
1
0
1
5
9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89 93 97 101
Reporting vessels
Figure 1– DP station keeping reports per vessel
It is important to understand the principle behind the reporting of DP station keeping events
as not all reports received indicate an inability to maintain automatic DP control. The reports
are used by IMCA primarily to inform the DP industry of lessons to be learnt, therefore
contributing to the safe and efficient operation of DP vessels.
Three categorisation levels are used by vessel operators when reporting a DP station keeping
event:
DP Incident
A major system failure, environmental or human factor which has
resulted in loss of DP capability.
DP Undesired Event
A system failure, environmental or human factor which has caused a
loss of redundancy and/or compromised DP capability.
DP Observation
An event that has not resulted in a loss of redundancy or
compromised DP operational capability but is still deemed worthy of
sharing.
During 2020 there were 41 DP incident, 79 DP undesired event and 24 DP observation reports
submitted.
2
IMCA M 256
Figure 2 – Regional split of DP reporting
The above chart represents the number of reports received from each region by IMCA. It
should not be used to suggest which region is having more DP incidents but could indicate
where the reporting of DP undesired events and observations should be further encouraged.
2.2
Summary of Causes 2020
The IMCA DP station keeping event scheme requires the reporter to provide both a main and
secondary cause of the event. The main cause is the event that caused the vessel to lose
redundancy or position keeping ability; the secondary cause is the reason why that main cause
occurred. This is explained in the following simple example:
A DP equipment class 2 vessel configured with four thrusters, bus tie open, has one stern and
one bow thruster on each bus. One thruster stops, and the root cause was found to be a power
module failure on the thruster frequency drive. Given this example, the IMCA DP reporting
scheme would record the main cause as thruster/propulsion; because that was why
redundancy was lost. The reason the thruster stopped, and thus the secondary cause, would
be ‘electrical’.
50
45
40
35
30
25
20
15
10
5
0
Figure 3 – Number of DP station keeping events by main cause
IMCA M 256
3
Figure 4 – Main cause – all DP station keeping events
It can be seen from Figure 4 that the largest percentage of the main causes reported for 2020
was thruster/propulsion at 33% (47); this continues to be the most reported main cause since
2012. It is worth noting that 11 of the 47 (23%) resulted in the vessel not maintaining
automatic DP control, this is an increase on last year when only 9% resulted in a loss of
automatic DP control. Power and Computer were two other main causes making a large
contribution to reporting, 18% of these reported events culminated in a loss of automatic DP
control.
60
50
40
30
20
10
0
Figure 5 – Number of DP station keeping events by secondary cause
4
IMCA M 256
2% 2% 1% 2%
Computer
Electrical
10%
13%
Environment
External factors
Human factor
Mechanical
41%
26%
Position references
Power
Sensors
Thruster/Propulsion
2% 2%
Figure 6 – Secondary cause – all DP station keeping events
A secondary cause was identified in 129 of the reports; the most frequent causes remain the
same as last year electrical 41% and human factors 26%. These causes together with the newly
introduced cause of mechanical (13%) represent more than 75% of all secondary causes.
The category of ‘human factors’ is broad in nature however all 30 reported causes could be
categorised as ‘unintentional behaviour’. There may be many reasons for such unintentional
behaviour, these have been subdivided into four categories as follows:
1) Sensory Error – e.g., errors caused by difficulty distinguishing functions, controls, colours,
labelling, etc.
2) Memory Error – e.g., errors caused by forgetting to make a selection or setting
3) Decision Error – e.g., errors where a clear decision was made to operate in a particular way
4) Action Error – e.g., errors where a function or control was selected incorrectly
9
8
7
6
DP Incidents
5
DP Undesired Events
4
DP Observations
3
2
1
0
Sensory error Memory error Decision error
Action error
Figure 7 – Secondary cause – Human Factors
These errors may be because of design factors, ergonomic factors, familiarisation issues,
training issues, documentation issues, competency issues and so on. It can clearly be seen that
IMCA M 256
5
decision and action errors led to proportionately more events leading to loss of DP control
than any other error.
The category of ‘electrical’ & ‘mechanical’ is also broad in nature. Reviewing these secondary
causes, we can subdivide the total number of 73 reported causes into two categories as
follows:
1) Lack of / insufficient maintenance
2) Natural Failure
30
25
20
DP Incidents
15
DP Undesired Events
DP Observations
10
5
0
Lack of maintenance
Natural Failure
Figure 8 – Secondary cause – Electrical & Mechanical
Natural failure has been assigned where the received report details a simple component
failure. Further investigation into the cause of these component failures may have indicated
lack of or insufficient maintenance.
2.2.1
DP Incidents
Event
20118
20005
20080
20108
20036
20086
20071
20079
20060
20091
20092
20041
20072
20096
20115
20043
20084
20094
6
Main Cause
Computer
Computer
Computer
Computer
Computer
Computer
Computer
Environment
Environment
Environment
Environment
Environment
Environment
External Factor
Human Factor
Human Factor
Human Factor
Human Factor
Secondary Cause
Computer
Computer
Computer
Computer
Electrical
Human Factor
Human Factor
Environment
Human Factor
Human Factor
Human Factor
Human Factor
Position References
Mechanical
Computer
Human Factor
Human Factor
Human Factor
Operation
Cable laying
Cargo
Gangway
ROV
Standby
Cargo
ROV
Cable laying
Geotechnical drilling
Geotechnical drilling
Geotechnical drilling
Well stimulation
ROV
Pipelaying
ROV
Cargo
Saturation Diving
Surface Diving
DP Class
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
IMCA M 256
20101
20134
20031
20029
20102
20116
20077
20046
20130
20042
20088
20033
20082
20140
20078
20017
20028
20061
20093
20011
20089
20023
20128
2.2.2
Event
20037
20074
20047
20070
20063
20105
20014
20129
20131
20006
20059
20113
20020
20081
20095
20098
20138
20035
20039
20045
20099
20104
20110
20004
20040
20126
20127
20120
IMCA M 256
Human Factor
Human Factor
Position References
Position References
Position References
Position References
Position References
Power
Power
Power
Power
Sensors
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
External Factors
Human Factor
Human Factor
Human Factor
Electrical
Human Factor
Mechanical
Thruster / Propulsion
Electrical
Electrical
Electrical
Environment
Human Factor
Human Factor
Human Factor
Human Factor
Human Factor
Mechanical
Cargo
ROV
Cargo
Cargo
Cargo
Cargo
Pipelaying
Cargo
Standby
Standby
Drilling
ROV
Cargo
Cargo
Cargo
Cargo
Cargo
Cargo
Geotechnical drilling
Saturation Diving
Cargo
Cargo
Cargo
2
2
2
2
1
2
2
3
2
2
2
2
2
2
2
1
2
2
2
2
2
2
2
Operation
Cargo
Cargo
Standby
ROV
Saturation Diving
Cargo
Cargo
Drilling
Cable laying
Standby
Standby
Geotechnical drilling
Saturation Diving
Standby
DP Trials
Cargo
Pipelaying
Cargo
Cargo
Cargo
Cargo
Cargo
Cargo
Cargo
DP Trials
DP Trials
Geotechnical drilling
Heavy lift
DP Class
2
3
2
2
2
2
2
3
2
2
2
2
2
3
2
2
3
2
2
3
2
2
2
2
2
3
2
3
DP Undesired Events
Main Cause
Computer
Computer
Computer
Computer
Computer
Computer
Computer
Computer
Computer
Electrical
Electrical
Environment
Environment
Human Factor
Position References
Position References
Position References
Power
Power
Power
Power
Power
Power
Power
Power
Power
Power
Power
Secondary Cause
Computer
Computer
computer
Computer
Computer
Electrical
Electrical
Electrical
Electrical
Electrical
Human Factor
Human Factor
Power
Mechanical
Position References
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
7
Event
20073
20015
20038
20107
20075
20132
20114
20065
20008
20085
20044
20049
20052
20083
20109
20025
20121
20112
20117
20021
20050
20067
20002
20097
20007
20026
20027
20058
20003
20030
20032
20076
20034
20064
20069
20087
20122
20124
20013
20119
20012
20111
20125
20141
20142
20068
20053
20022
20090
20133
20018
8
Main Cause
Power
Power
Power
Power
Power
Power
Power
Power
Power
Power
Power
Power
Power
Power
Power
Power
Power
Power
Sensors
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Secondary Cause
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Human Factor
Human Factor
Human Factor
Human Factor
Mechanical
Mechanical
Mechanical
Mechanical
Mechanical
Mechanical
Mechanical
Computer
Computer
Computer
Computer
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Human Factor
Mechanical
Mechanical
Mechanical
Mechanical
Mechanical
Mechanical
Power
Thruster / Propulsion
Operation
Pipelaying
ROV
ROV
ROV
Standby
Standby
Cargo
Pipelaying
Standby
Standby
Cargo
Cargo
Cargo
Cargo
Cargo
Geotechnical drilling
Pipelaying
Standby
ROV
Cargo
Cargo
Standby
Saturation Diving
Cable laying
Cargo
Cargo
Cargo
Cargo
Cargo
DP Trials
DP Trials
FPSO heading control
ROV
ROV
ROV
ROV
ROV
ROV
Saturation Diving
Standby
Saturation Diving
Cargo
Cargo
Cargo
Cargo
Well stimulation
Standby
Cargo
ROV
Cargo
ROV
DP Class
2
2
2
3
3
2
2
2
2
2
3
2
2
2
2
2
3
2
2
2
2
2
3
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
3
2
2
2
2
2
2
2
2
2
2
2
IMCA M 256
2.2.3
Event
20136
20137
20066
20001
20100
20139
20019
20010
20055
20051
20009
20143
20106
20062
20016
20048
20054
20057
20103
20024
20144
20123
20135
20056
2.3
DP Observations
Main Cause
Computer
Computer
Computer
Computer
Computer
Computer
Computer
Electrical
Electrical
Electrical
Position References
Position References
Position References
Power
Power
Power
Power
Power
Power
Sensors
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Thruster / Propulsion
Secondary Cause
Electrical
Electrical
Electrical
Sensor
Human Factor
Human Factor
Electrical
External Factors
Human Factor
Electrical
Mechanical
Mechanical
Mechanical
Mechanical
Power
Mechanical
Electrical
Electrical
Electrical
Human Factor
Operation
Pipelaying
Pipelaying
Saturation Diving
Saturation Diving
Cargo
Pipelaying
ROV
Cargo
Saturation Diving
ROV
Cargo
Saturation Diving
Cargo
Cargo
Cargo
Cargo
Cargo
Pipelaying
Cargo
DP Trials
DP Trials
Saturation Diving
Standby
Saturation Diving
DP Class
3
3
3
3
2
3
2
2
3
2
2
2
2
1
2
2
2
3
2
2
2
2
1
3
Comparison of DP Incidents and DP Undesired Events/ Observations
A comparison has been undertaken of the number of DP incidents (loss of automatic control)
and the number of DP undesired events/DP observations (potential loss of automatic control),
for each of the nine recorded DP event main causes. Of the 144 DP events reported to IMCA
during 2020, 41 of these resulted in loss of automatic control and 103 were DP undesired
events or DP observations.
For any given DP event main cause, if effective barriers are in place, there should be a low ratio
of DP incidents to DP undesired events and DP observations. Whereas if there is a high ratio
of loss of automatic control to DP undesired event and DP observations, this might indicate
that barriers are not being effective.
IMCA M 256
9
40
35
30
25
Loss of
automatic DP
control
20
15
10
5
DP undesired
event &
observation
0
Figure 9 – Reported DP incidents/DP undesired events & DP observations by main cause 2020
A high ratio of loss of automatic control to DP undesired event and DP observations was
recorded for environment, human factor and position references. This suggests that barriers
might not have been so effective for these events. When considering the secondary cause for
these 17 recorded events 13 of them had human factor or no conclusion as the cause.
45
40
35
30
Loss of
automatic DP
control
25
20
15
10
5
DP Undesired
event &
observation
0
Figure 10 – Reported DP incidents/DP undesired events & DP observations by operation 2020
Only limited conclusions should be drawn from the above. The proportion of DP undesired
events and DP observation to loss of automatic DP control is more than 2:1 for all types of
operation except cable laying, drilling and other. There were only two DP station keeping
events reported by DP drilling operators. Operations included in the ‘other’ category are
geotechnical drilling, often in shallow water, gangway transfer, FPSO heading control, heavy
lift and well stimulation. Since 2015, Cargo operations have shown a relatively high number
of DP incidents (loss of automatic DP control); this is thought to be because the operation was
generally not as position sensitive as some other DP operations and can, on most occasions,
be quickly terminated.
It is pleasing that there is a good spread of reporting across all sectors of the industry.
10
IMCA M 256
3
2020 DP Event Trees and Case Studies
All IMCA DP Event Bulletins can be found and downloaded here.
DP Undesired Event Due to Online Maintenance Work
DP Class 2, on DP in
1900m water depth,
engaged in ROV
operations
6 thrusters online, nil
on standby
4 generators online, nil
on standby, bus tie
open, 4 redundant
groups
3 DGNSS & 1 HPR
online
3 Gyros, 3 MRUs and 3
wind sensors online
0249 Local alarm
Remote MultiPurpose input/output
card frozen
0400 risk assessment
completed, RMP
module to be replaced
0413 Generator 2
circuit breaker
reconnected
automatically
Two ROV in water
0412 During
replacement the circuit
breaker for generator
2 tripped
Power restored to
thruster 3 and other
affected equipment
Main crane with load in
water, not connected
to seabed
Thruster 3 tripped and
supplementary power
lost to the crane
Vessel maintained
position on DP
Wind 12kts 187°,
current 2.5kts 149°,
wave height 1.4m,
visibility good
Comments from the report:
The vessel reported that they had changed these modules in the past whilst on DP without any issues.
The risk assessment had identified that the consequence would not lead to loss of equipment greater
than worst case and proceeded due to the status of the vessel operations, open water and not
connected to the seabed.
Considerations of the IMCA Marine DP Committee from the above event:
 Incident validates the redundant capability of the vessel, but also potentially highlights a hidden
failure leading to generator 2 failure;
 The report did not identify the root cause for the loss of equipment whilst replacing the RMP
module, a successful online activity undertaken previously;
 This event highlights the benefit of considering mission equipment during risk assessments;
 It also event highlights that expected results of repairs are not always guaranteed;
 As far as is possible, maintenance or replacement of critical DP equipment should not be done
while conducting DP operations;
 In this instance, it would have been prudent for ROVs to return to their TMS and the crane made
safe prior to undertaking the work.
IMCA M 256
11
Change of Heading Leads to DP Incident
DP Class 2, on DP in
+3000 m water depth,
engaged in ROV
operations
6 thrusters online,
2 on standby
3 generators online,
2 on standby,
bus tie closed,
2 DGNSS & 1 HPR
online
3 Gyros, 3 MRUs and
3 wind sensors online
12:35 ROV operations
ended and crane was
deployed to recover
dead ROV
12:47: T 2 started &
selected to DP and
load shared with the
other two Thusterrs
successfully
12:51 ON MAIN
CONTROL UNIT,
stop button was
pressed allowing
restart of all 3 bow
thrusters
12:43 Vessel heading
was changed 15˚ away
from the wind to
accommodate recovery
of ROV to deck
12:49: Thrusters 1, 2 &
3 stopped with No DP
or Thruster alarms
Vessel drifted off
position 200 m
12:46 Change of vessel
heading caused high
load on bow thrusters
1&3
On Thrusters Main
Control Unit showed
T 1, 2 & 3 Start
Interlock
12:52 Bow thrusters 1,
2 & 3 all online again
and operations
resumed
Wind 40 kts, wave
height 2.5 m, visibility
moderate
Comments from the report:
The vessel had been on DP for the whole day and in order to lift the ROV on deck with the crane, vessel
heading had to be changed 15 degrees away from the wind. This caused a high load on two running
bow thrusters and the third bow thruster was started, selected to DP and successfully shared the load.
Increased windward force on the vessel due to high wind velocity acting on it as it changed heading,
caused all the three bow thrusters to trip on overspeed with no DP or thrusters’ control system alarms!
Further investigation revealed the overspeed settings were too tight and had to be increased in
accordance with manufacturer’s recommendation.
Considerations of the IMCA Marine DP Committee from the above event:
 It is not clear why the additional bow thruster was not put online before the heading change;
 A simulated alteration of heading and or referring to the vessel’s capability plots should have been
considered to ensure that the heading change could have been performed within vessel’s DP
capability;
 The overspeed trip of all thrusters during DP operations shows inadequate initial commissioning
and full power testing during the FMEA proving trials and annual DP trials and following any
modification;
 This incident further highlights the importance of equipment protection settings with respect to
DP redundancy concept, in addition to equipment safety. DP FMEAs require to consider the effects
of equipment protection system on the wider DP redundancy concept. Reference Guidance on
Failure Modes & Effects Analysis (FMEA) (IMCA M 166).
12
IMCA M 256
Unreliable Component Causes a DP Undesired Event
On DP in 500m water
depth, standby awaiting
cargo operations
5 thrusters online, nil
on standby
2 generators online, 2
on standby, bus tie
open
2 DGNSS online 1
laser system on
standby
3 Gyros, 2 MRUs and 2
wind sensors online
Standing by 400m
from drill ship
awaiting instruction
One stern and one
bow thruster
unavailable
Vessel in drift off
position Task
Appropriate Mode
Vessel maintained
position on DP
Port switchboard
blacked out
Departed the 500m
zone for investigation
Wind 5kts 240°,
current 1.2kts 220°,
wave height 1.0m,
visibility good
Comments from the report:
Investigation found that a 24v bridge rectifier supplying voltage to the main generator switchboard
breakers 1 and 2 had burned out. The age and quality of the rectifier was thought to be the main
reason for failure. Planned maintenance routines were updated and shared with the fleet. It was
recognised that the system was vulnerable due to a single 24v bridge rectifier supplying the entire port
switchboard.
Considerations of the IMCA Marine DP Committee from the above event:
The vessel validated that it could maintain position following the worst-case failure of a complete
switchboard. Though redundancy is a must in DP 2/3 designs, components quality may impact the
likelihood of such DP events occurring.
IMCA M 256
13
DP Incident Caused by Software Glitch
DP Class 2, on DP
in 1501-3000 m
water depth,
engaged in Cargo
operation
6 thrusters
online, nil on
standby
2 generators
online, nil on
standby, bus tie
open, 2
redundant groups
2 DGNSS & 1
Laser based
online
3 Gyros, 3 MRUs
and 2 wind
sensors online
1330 With hose
connected the
vessel was asked
to move a short
distance
1333 DP system
showed the new
position as zero
latitude and
longitude
1338 Vessel
holding position
and was
instructed to
retrieve the hose
1332 2 meters to
Stbd was initiated
in two
instalments of 1m
each
1335 Control was
taken by
independent
joystick to
maintain position
1345 Vessel
headed out of the
500m zone in DP
mode for
investigation
The vessel
suddenly
commenced an
uncontrolled
drive off
1336 Vessel in
control and DP
mode selected as
position readings
back to normal
Wind 4kts 47°,
current 1kts 51°,
wave height 1m,
visibility good
Comments from the report:
The two meters move command was given in two one-meter steps to the DP system by the operator
with a time lapse of a few seconds. This was investigated by the DP system vendor and was identified
as a software glitch. Two consecutive incremental move commands before the window screen has
time to refresh resets the DP system to a zero position automatically. Instructions were put in place
on-board this and similar vessels until the vendor remedies the software issue.
Considerations of the IMCA Marine DP Committee from the above event:
 This and similar incidents highlight the need for extensive testing of the software at all stages;
 Many vendors continuously update their software with patches, revisions, etc. Vessel operators
must ensure a robust management of change (MoC) procedure and suppliers should provide an
appropriate rigorous testing program;
 The DP operator(s) appear to have initially responded well to the incident and this is a credit to
their training and competence;
 Reference IMCA documents Guidance for developing and conducting DP annual trials programmes
(IMCA M 190) and Guidance on failure modes and effects analysis (FMEA) (IMCA M 166).
14
IMCA M 256
DP Incident with Assisted Mooring
DP Class 1, on DP in
100m water depth,
engaged in Cargo
operations
5 thrusters online, nil
on standby
3 generators online,
one on standby, bus
tie status not
mentioned, no
redundant groups
2 Gyros one online and
one on standby, 1
MRUs and 2 wind
sensors online
2 DGNSS online
0715 Vessel in DP
assisted mooring
involved in cargo
operations
0732 Mooring line aft
breaks due to PS
propeller pitch goes to
100%
0733 Sway control taken
in joy stick mode to
reduce t hrust commands
preventing vessel bow to
come close t o the
install ation
0729 DP alarms
initiated due to
insufficient thrust
Vessel swings out of
position with load
connected
0734 Vessel back in
posi tion wi th sway
control in joystick, hook
disconnected, and v essel
set up i n auto DP mode
Heading out of limits
and crew already
fastened crane hook
to the load
Crane driver
maintains slack on the
crane cable until
position restored
0740 Vessel all fast
again and resumes
operation
Wind 10kts 260°,
current 2.5kts 292°,
wave height 1m,
visibility good
Comments from the report:
During cargo operations in DP assisted mooring, due to undefined information being fed to the DP
system, the pitch on the port propeller increased to maximum. The vessel started to drive off the
installation with the crane connected to the load, dimensions 3.5*10.5*6.5 m weighing 11 M Tons. All
deck crew were already in safety area behind crash bar ready with tug lines for the lift.
Considerations of the IMCA Marine DP Committee from the above event:
 There appears to be no consideration to the external force being applied to the vessel due to the
use of mooring lines when in DP;
 If an external force is applied to a DP vessel without feedback and correct configuration within the
DP system, it will have unintended consequences;
 It appears an appropriate Activity Specific Operating Guideline (ASOG) was not in use.
IMCA M 256
15
DP2 Semi-submersible MODU DP Incident
Case narrative:
A DP2 Semi-submersible mobile offshore drilling unit (MODU) was working in field preparing for drilling
operations on location. The environmental conditions at the time were benign. Cargo operations were
ongoing with a DP2 platform supply vessel alongside.
The vessel experienced a total loss of all online thrusters leading to the MODU starting to drift. The
power management system standby started offline generators; however, it could not re-engage
thrusters to DP automatically. The supply vessel was ordered to relocate out of the 500m zone, and
the crane driver instructed to lower the crane boom to rest.
With no thrusters available the vessel drifted before the DPOs were able to start three previously
offline thrusters manually, which were then selected to DP. Subsequently, the Electrical Technical
Officer reset a further two thrusters locally allowing them to be selected to DP control. Within 3
minutes a sufficient level of thrusters were online and station keeping was stable. Within 17 minutes,
all remaining thrusters were reset and operational. The vessel management team commenced a failure
investigation thereafter.
At the time of the event, the vessel was being operated on automatic DP2 mode with 3 of 8 generators
and 4 of 8 thrusters online. The main 11kV switchboards were being operated with closed bus tie,
each side of the main switchboard powering one forward and one aft thruster as per the proven
redundancy concept.
The investigation revealed that, as a result of an incorrect maintenance action, the initiating event was
caused by a human factor – an offline generator was accidently connected to one of the main
switchboards which resulted in an instant severe power instability, causing a significant active and
reactive power demand and subsequent voltage and frequency drop. The generator in question then
tripped on its reverse power protection resulting in significant voltage spike as a result of removing
the large inductive load from the network.
The large voltage and frequency drop caused the thrusters to phase back. It is not clear from the
investigation whether this was a function of the power management system or the fast acting blackout
prevention function of the thruster drive (or a combination of both). The subsequent voltage spike
caused by the removal of the stopped generator led to the online thrusters tripping offline. Although
the investigation did not detail the reason for this, it is assumed that the thruster drives were
protecting themselves from internal damage by tripping offline. Most modern thruster drives have
sophisticated monitoring and protection systems measuring internal DC voltage and ensuring that this
voltage does not increase or decrease beyond limits that would otherwise result in internal component
damage.
The lessons:
1. The investigation report highlighted a number of findings and subsequent actions as follows:
a) Undertake a full review of maintenance procedures on high voltage circuit breakers to
ensure that this work is undertaken at suitable windows of opportunity and not during
DP operations;
b) Undertake refresher crew training and review switchboards for any need for additional
safety or warning labelling;
c) Engage with the voltage regulator and thruster drive vendors to ensure their products
reacted as would be expected in such an event;
d) Investigate the ‘locking off’ of the manual close buttons of ‘key’ HV circuit breakers
including the permit to work system;
16
IMCA M 256
e) Share lessons learned internally within the vessel owner’s fleet and externally within
industry.
2. The investigation report did not consider bus tie position and the overall redundancy concept of
the vessel. There are well documented arguments for open or closed bus tie position; however,
this event clearly demonstrates the risk of a failure on one redundant group affecting the other
redundant group through the common point of the bus tie. It is not inconceivable to assume that
had environmental conditions been greater, necessitating more thrusters online at the point of
failure, then this failure may have resulted in insufficient thrusters offline available to be selected
to DP thus causing a significant delay manually resetting thrusters and a significant drift off.
3. Continuing with the theme of closed bus operations, the investigation report did not discuss the
DP FMEA specifically considering the suitability of the overall protection scheme coupled with the
power management system and thruster blackout prevention functions, such that a fault cannot
be transferred from one redundant group to another.
4. The investigation report detailed the desire to ‘lock off’ manual controls on the switchboard.
Careful consideration of such an action is needed to ensure that emergency functionality is not
inhibited. For example, manual circuit breaker controls may be required for emergency
synchronisation of generators.
This case study demonstrates the risks of undertaking maintenance of critical DP components or
systems while undertaking DP operations. The case study also highlights the challenges that exist
for vessels operating in closed bus mode, i.e., where the otherwise redundant groups are connected
via a common point and the risks presented as a result.
Such factors should be considered at the design stage of DP vessels and fully analysed within the
vessel’s DP FMEA, confirming through FMEA proving trials and subsequent DP Annual Trials
Programmes.
IMCA M 256
17
DP Incident Caused by Human Factor
DP Class 2, on DP in
30 m water depth,
engaged in
Geotechnical drilling
5 thrusters online, nil
on standby
3 generators online, 2
on standby, bus tie
open, 2 redundant
groups
3 Gyros, 2 MRUs and
3 wind sensors online
3 DGNSS & 1 Taut
wire online
09:55:16 Alarm on
DG#1 – Fuel
differential pressure
09:59:37 DG#1 is
disconnected from the
Port Swbd for repairs
Decision made to start
DG#4 and stop DG#1
10:02:47 After 3.5
minutes running,
DG#4 trips for
unknown reasons
causing partial blackout
09:59:28 DG#4 started
and connected to Port
switchboard
Due to the partial
blackout, port azimuth
thruster and bow
tunnel T1 are lost
Wind 20kts 225°,
current 1.6 kts at 250°
wave height 4.2 m,
visibility moderate
Vessel drifts off 3.1m
and then regains
position
Comments from the report:
It is mentioned in the report that DG#4 tripped out for unknown reasons. Elsewhere in the report the
cause of this incident is mentioned as complacency or lack of knowledge with DP redundancy concept.
Considerations of the IMCA Marine DP Committee from the above event:
•
The set-up of the PRS was such that the DGNSS had the majority of the “PRS Weight” calculation
in the DP controller, which is not recommendable.
•
When a fuel filter differential pressure alarm is received, ensure that the correct procedures for
filter changeover and filter replacement are carried out as soon as reasonably practicable.
Always ensure that standby diesel generator is checked to ensure continuous service.
•
The excursion was 3.1m but it should be noted that this is 10% of the water depth and could
have been critical depending on the industrial mission.
•
There is no mention of the DP watch circle in the report. It is particularly important that an
Activity Specific Operating Guidance (ASOG) document is compiled and utilised for all DP
operations, in accordance with IMO Circular 1580, chapter 4, see IMCA M 220 Operational
Activity planning.
18
IMCA M 256
Lack of Operational Planning Leads to DP Incident
DP Class 2, on DP in
60m water depth,
engaged in saturation
diving operation
5 thrusters online, nil
on standby
2 generators online, nil
on standby, bus tie
closed
2 DGNSS online 1
Radar based & 1 HPR
system on standby
3 Gyros, 2 MRUs and 2
wind sensors online
07:56 Diver in water
08:09 No available
reference system and
vessel lost position
Vessel made contact
with installation
07:58 DGNSS No. 1
alarmed on high noise,
deselected by DPO
Joystick selected by
Master/DPO
08:14 Diver was
recovered, and vessel
clear of installation
08:00 DGNSS No. 1
restarted exhibiting
the same alarm
Dive control asked to
surface the diver
08:35 Vessel clear out
of 500m zone for
investigation
08:08 DGNSS No. 2
alarmed Invalid
HDOP (Horizontal
Dilution of Precision)
08:11 Vessel getting
close to the rig due to
wind effect
Wind 13kts 180°,
current 0.6kts 296°,
wave height 1.2m,
visibility good
Comments from the report:
It was concluded that the loss of both DGNSS were due to huge superstructure of the installation
interfering with satellite signals. This phenomenon is called reflection meaning DGNSS picks up
reflected signals from the surroundings.
Considerations of the IMCA Marine DP Committee from the above event:
•
The vessel was not being operated as a DP Equipment Class 2, as the requirement is at least
three independent position reference systems should be installed and simultaneously available
to the DP control system. Reference IMCA M 252 Guidance on Position Reference Systems and
Sensors for DP Vessels.
•
Loss of more than one DGNSS position reference system is a well-known issue due to external
common cause failures, for example shielding of reference satellites and/or differential
corrections.
•
Operational planning and decision support tools, such as Activity Specific Operating Guidelines
(ASOG), were clearly not in use or were inadequate. Reference IMCA M 220 Rev 1 provides
Guidance on Operational Activity Planning.
•
•
It appears that the DP Alert system was not used.
It is mentioned in the report that at 08:09, master takes control of the vessel by the IJS. It is
unclear from the report why the vessel then made contact with the installation. Reference IMCA
M 117 The Training and experience of Key DP personnel.
 This event clearly demonstrates the benefit that can be gained from regular DP exercises and drills.
IMCA M 256
19
Loss of Gyro Input Causes Loss of Position
Case narrative:
A DP 2 vessel was involved in ROV operations in deep water with good visibility. The environmental
conditions were moderate with a wind speed of 15 Knots and a current speed of 1.2 knots during the
time of event. The vessel was operating in open bus tie mode with two redundant groups. There were
five (05) thrusters and four (04) generators installed on the vessel and all were selected to DP. There
were three (03) gyros, two (02) position reference systems and two wind sensors available and all
selected to DP.
The following diagram depicts the system configuration prior to the event:
G1
Bow tunnel 2
G2
Port Azimuth
G3
Bow Tunnel 1
Stbd. Azimuth
G4
Bow Tunnel 3
Figure 11 Vessel power system configuration
The event: An alarm “Gyro 2 Not Ready” appeared and gyro 2 was automatically deselected from the
DP system. Immediately after this, gyro 1 also dropped out with alarms, “Gyro 1 Not Ready” and “Gyro
1 Heading Dropout”. Within one second the third gyro failed with the following alarms in succession,
“Gyro not enabled”, “All Reference systems rejected” and “Position Dropout”.
It was noted that gyro 1 repeater on the bridge continued to display the correct heading, while heading
input from gyro 1 was missing at the DP operator station (OS). Concurrently, it was further noticed
that gyro 2 repeater was in alarm with no heading display and gyro 3 was displaying the heading with
10 degrees offset. Orders were given to recover the ROVs on deck and the vessel control was
transferred to full Manual mode.
20
IMCA M 256
The crew managed to get the vessel back to full DP control within twenty-eight (28) minutes from the
onset of the first failure with one hundred and fifty (150) metres of uncontrolled movement during
that time.
The following actions were executed:
• Gyro 2 restarted, rebooted and realignment completed
• DP OS 1 & OS 2 soft rebooted
• Controllers A & B of OS 1 rebooted after which all PRS and DP sensors online and enabled
The investigation revealed that gyro 2 was lost due to the loss of its Interface and Power Supply Unit.
After replacing this unit, a test was carried out to prove the independence of gyro 1 from gyro 2. On
disconnecting the power supply to gyro 2, it was observed that gyro 1 was also lost. Further system
analysis concluded that the gyro 1 ready signal was linked with that of gyro 2 in the DP controller
cabinet. This cross-connection issue caused a detrimental effect on both gyros’ performance. In
addition, following a malfunction on any gyro, the No. 1 Control and Display Unit would force the gyro
1 ready signal to disappear at the DP operator station. These issues were corrected and tested to the
satisfaction of all involved parties.
During the time of the incident gyro 3 sensor value was found to be approximately ten (10) degrees
different from gyro 1 and gyro 2 headings. When both gyros 1 and 2 were deselected from DP, gyro 3
was selected to the DP system. However due to the large deviation in the heading value of gyro 3
compared with the estimated heading, which in this case should not have been more than two
degrees, the DP controller rejected gyro 3.
The lessons
•
•
•
•
If a gyro has a static deviation from other gyros, this should have been identified, investigated,
and rectified so that all gyros’ measured headings are within the DP control system limits to
avoid any such problems
The common mode failure related to the ready signal of gyros’ 1 and 2, should have been
identified during commissioning, FMEA proving trials and DP annual trials programme. IMCA
documents M 166, “Guidance on Failure Modes & Effects Analyses (FMEAs) and M 190,
“Guidance for Developing and Conducting DP Annual Trials Programmes”, underline the
importance of having robust FMEA and set of annual trials
IMCA M 252 “Guidance on Position Reference Systems and Sensors for DP Operations”
provides general information on use of reference systems and the good practice of multiple
references and sensors
Importance of proper investigations and robust testing of cross connections in redundancy
groups of DP vessels is highlighted in this case study
This case study demonstrates the importance of robust testing procedures during FMEA proving
trials, annual trials or 5-yearly trials program. The case study also highlights the importance of
conducting daily compass checks and completion of all other operational checklists so that
differences in redundancy groups are identified early and can be corrected.
IMCA M 256
21
Simultaneous activities on the bridge caused a DP Incident
DP Class 2, on DP in
125m water depth,
engaged in
saturation diving
operations
5 thrusters online,
nil on standby
5 generators online,
nil on standby, bus
tie open
1 DGNSS, 1 HPR &
1 laser-based system
online, 3 DGNSS &
2 taut wire on
standby
3 Gyros, 3 MRUs
and 3 wind sensors
online
Vessel on DP
preparing to start the
diving operations,
DPO engaged in
completing 6 hourly
checklists
The vessel was taken in
joystick control auto
heading to move away
from the platform
Heading change
inadvertently selected
unnoticed
Joystick mode set to
manual heading
continuing to sway
clear
The master observed
the stern of the vessel
coming close to the
platform and alerted
the DPO
Joystick auto heading
with the exact heading
selected
The amber status was
immediately activated
DP selected clear of
the platform and vessel
stepping away on DP
Wind 22kts 225°,
current 1kts 060°,
wave height 1m,
visibility moderate
Comments from the report:
The DPO, though experienced, was new to the vessel and the DP system. He had undergone
familiarisation of the system but misinterpreted 30 o heading increment as being a 30o / min rate of
turn. As the 6-hourly checklists were being completed, the vessel was making moves and deploying
references. Multiple operations were initiated just prior to watch handover which could have been
delayed by a few more minutes.
Considerations of the IMCA Marine DP Committee from the above event:
 Bridge resource management was not properly exercised. In principle, the second DPO should fill
out the checklists and the DPO at the desk should concentrate on vessel position keeping only;
 The familiarisation process should be reviewed to be more robust to ensure new DPOs are
completely familiar with the desk and functions;
 Reference should be made to IMCA M 117 “The training and experience of key DP Personnel;
 It should be noted that a 30o per minute rate of turn was considered to be far too high whilst
engaged in diving operations.
22
IMCA M 256
Inadequate Position Reference Systems Caused DP Incident
DP Class 2, on DP in
40 m water depth,
engaged in cargo
operations
4 thrusters online, 1
on standby
2 generators online,
1 on standby, bus tie
open, 2 redundant
groups
2 DGNSS online & 1
laser based offline
2 Gyros, 2 MRUs
and 2 wind sensors
online
The vessel was
involved in a
SIMOPS with a PSV
Interference from a
faulty RADIUS of the
PSV caused the loss
of the signals to both
DGNSS
During the
operation, the
vessel lost inputs to
both her DGNSSs
Switched to manual
control and
manoeuvred clear of
the platform
The third PRS was
out of order during
the incident
Vessel drifted off 5m
while transferring to
manual mode
Wind 8 kts at 260°,
current 0.8 kts at
060°, wave height
1m, visibility good
The vessel lost
automatic control
due to the loss of all
its position
reference systems
Comments from the report:
It is mentioned in the report that task appropriate mode (TAM) and activity specific operating
guidelines (ASOG) were in use, with the limitation identified for 2 DGNSS subject to common mode
failure.
Considerations of the IMCA Marine DP Committee from the above event:
 Use of only 2 DGNSS was contrary to the MSc.1 / Circ. 1580 requirements. This meant the vessel
was not set up in accordance with DP class 2 requirements of 3 position reference systems based
on at least two different principles;
 Vessel sensors selection did not appear to comply with DP class 2 requirements, though this noncompliance was not a factor in the incident;
 Task appropriate mode was in place, indicating that a loss of position was acceptable. However,
the incident indicates that an adequate risk assessment was not done and TAM and ASOG were
not thoroughly reviewed prior to their approvals;
 When the vessel lost its automatic DP control due to the loss of all its PRSs, the position could have
been maintained for a period of time using the DP mathematical model;
 The report states that interference from a faulty laser-based system on the PSV caused the loss of
signals to both the DGNSSs. However, this could have been caused by interference of the
differential correction signal receivers caused by shielding or reflection;
 Information on radio interference is provided in IMCA M 252 Guidance on Position Reference
Systems and Sensors for DP Operations, Section 4.6 Operational Consideration Summary.
IMCA M 256
23
Lack of Experience in Dealing with Environmental Conditions Caused Loss of Position
Case narrative:
A DP 2 vessel with two redundant groups and operating in open bus mode, was involved in drilling
operations in water depths of approximately 38 metres. The vessel was performing cone penetration
testing (CPT) at a location with a drilling depth up to 90 metres. There were six thrusters and four
generators available onboard and all were selected to DP. The available position reference systems
(PRS) onboard were three DGNSS, one taut wire and one HPR, out of which only two DGNSS were
selected to DP.
Also, out of the available four wind sensors, three of them were selected into DP, along with three
gyros and three motion reference systems. The visibility was reported to be good with wind speed of
fifteen knots at 045˚, current speed of four knots at 040˚and swells of 2 metres height with a duration
of ten seconds at 220˚ were recorded during the operation. At the time of the incident, the vessel was
drilling at a depth of 54 metres.
N
The vessel was encountering strong currents from the stern, as expected, and experienced by the
DPO’s during the earlier spring tides. For this reason, the vessel receives location specific current
modelling from a remote centre during its operations. These models display peak marine current’s
direction and speed at any given time. During these strong currents, it is prudent to change the vessel
heading regularly to follow the currents direction and to keep them at the stern.
The Event
At 20:00 hrs the senior DPO took over the watch at the DP desk and at 20:10 noticed the current was
changing direction and intensity. The vessel heading was changed from 020˚ to 024˚ to keep the
current at the stern. After the heading change, the loading on the vessel’s thrusters were observed to
be within normal operating limits and the vessel maintained its position. At 20:45, the SDPO noticed
another change in the direction and speed of the current, and further observed that the load was
increasing on all thrusters. The drilling control was advised of the need to make a further heading
change as the CPT operation was ongoing.
At 20:54 the DP consequence analysis advised that the load was higher than one of the two redundancy
groups could tolerate post worst-case failure. Ten seconds later, power consumption was within limits
again. The SDPO advised the drilling control of a further heading change which was confirmed at 20:56,
24
IMCA M 256
and the heading was changed from 024˚ to 028˚. At 21:00 the DP consequence analysis warning
indicated that the power online was in excess of the capacity of one redundant group, post worst-case
failure. This alarm lasted for one and a half minutes. After completion of the heading change and at
21:05, the loading on the vessel’s thrusters were observed to be within normal operating limits and
the vessel maintained its position. The SDPO handed over the watch to the DPO.
At 21:15 the DPO alerted the SDPO that the load on thrusters T3 and T4 were increasing. The SDPO,
immediately attended the DP desk, noticing that thrusters T3 and T4 loads were increasing and that
the vessel was struggling to maintain its position. At 21:19 the heading was changed by 2˚ to 030˚. At
21:21 the DP system indicated high loads on T3 and T4 followed by a consequence analysis “Off Position” warning alarm. Simultaneously, there were speed feedback faults on both T3 and T4. At
21:22 a DP yellow alert was given to the drill operators as the vessel excursions overshot the ten
percent of the water depth limitation.
The drillers immediately stopped their drilling operation, lifted the drilling equipment, and hoisted it
back at the moonpool. The heading was changed to 040˚ where the current was at the vessel’s stern.
At 21:25 the vessel settled down and could maintain position. At this time, the drilling assembly was
inspected, and the pipe and the bottom hole assembly were observed to be in good condition. After
a complete inspection, it was confirmed that there was no damage to the drilling equipment. Distance
of uncontrolled movement during the event was nine metres and the duration of the event was
recorded to be six minutes.
The lessons
 It needs to be fully understood that the current indicated was the “DP current” and not a
“measured current”. A DP current value could be affected by other disturbing factors and needs
to be relied on with care with regard to magnitude as well as direction.
 It was mentioned in the report that the current strength was above the thresholds specified in the
vessel ASOG. It is essential the ASOG is continually reviewed to ensure it covers all possible hazards
during a specific operation.
 IMCA M 220 Guidance on Operational Activity Planning, discusses the importance of various
documentations such as CAM, TAM and ASOG. DP and emergency response drills discussed in the
document, highlight the importance that all DP personnel must know what actions to take and
what to expect when operating parameters are exceeded.
 It is concluded in the report that current must be included as a factor in the vessel’s manual of
permitted operations. The effect of the stern thrusters, running at near full power and throwing
the wash against the hull, will be reduced due to thruster-hull interaction. The vessel DP capability
plots should be consulted.
 It needs to be highlighted that only two position reference systems of the same kind were being
used. Therefore, with regard to position reference systems, the vessel was not set up according
to DP class 2 requirements. A minimum of three position reference systems with one being of
different type are required in a DP class 2 or 3 operation.
 The contents of the ASOG for this operation was not disclosed. However, it was stated in the
report that immediately after the yellow alert, drilling operations stopped, and the drilling
equipment lifted and hoisted up in the moonpool. It is not clear whether these actions were
precautionary measures or mandates arising from the ASOG. In this instance a Yellow alert was
indicated to the drill operators, if a loss of position was occurring a Red light should have been
given to the drill operators.
 It is not clear in the report as to why the speed feedbacks on both T3 and T4 became faulty. One
possibility was that the speed feedback discrepancies of T3 and T4 could have been caused by the
strong current inflow and thrusters running at near or above full speed.
IMCA M 256
25
This case study demonstrates the importance of fully understanding the vessels capability and
normal operating limits, and also ensuring that this level of detail is clear within the ASOG. The case
study also highlights the significance of training in emergency situations for key DP personnel.
26
IMCA M 256
Download