DESIGN MANUAL for ROADS and BRIDGES PAVEMENT DESIGN MANUALS Proposed Design for New and Reconstructed Bituminous, Gravel and Concrete Roads DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Table of Contents 1 2 3 4 5 General .......................................................................................................................... 1 1.1 Introduction ............................................................................................................. 1 1.2 Units of Measurement ............................................................................................. 3 1.3 Definitions and Abbreviations .................................................................................. 4 1.3.1 Pavement ........................................................................................................ 4 1.3.2 Pavement layers .............................................................................................. 5 1.3.3 General Terms ................................................................................................. 5 1.3.4 Bituminous Materials........................................................................................ 6 1.3.5 Traffic .............................................................................................................. 7 1.3.6 Abbreviations ................................................................................................... 8 1.3.7 Comparison of BS and ASTM Sieve Sizes ..................................................... 11 Traffic........................................................................................................................... 12 2.1 General ................................................................................................................. 12 2.2 Present Kenya legislation...................................................................................... 12 2.3 Evaluation of Traffic for Design Purposes ............................................................. 14 2.3.1 Traffic Counts ................................................................................................ 14 2.3.2 Axle Load Surveys ......................................................................................... 15 2.3.3 Evaluation of Axle Loads ............................................................................... 16 2.3.4 Estimating the Cumulative Number of Standard Axles ................................... 17 2.3.5 Length of Design Period ................................................................................ 18 2.4 Traffic Classification .............................................................................................. 18 Natural Environment .................................................................................................... 20 3.1 Climate ................................................................................................................. 20 3.2 Geology ................................................................................................................ 23 3.3 Demography ......................................................................................................... 25 Earthworks ................................................................................................................... 27 4.1 Cuttings ................................................................................................................ 27 4.1.1 Type, volume and position of the materials to be excavated .......................... 27 4.1.2 Level and flow of water table and springs ...................................................... 28 4.1.3 Stability of the slopes ..................................................................................... 28 4.1.4 Drainage and protection against erosion ........................................................ 28 4.2 Embankments ....................................................................................................... 29 4.2.1 Foundation Conditions ................................................................................... 29 4.2.2 Acceptable fill material ................................................................................... 30 4.2.3 Slope stability................................................................................................. 30 4.2.4 Placing and compaction of fill......................................................................... 31 Drainage and Erosion Control ...................................................................................... 33 5.1 Drainage of Surface Water.................................................................................... 33 5.1.1 Side Ditches .................................................................................................. 33 5.1.2 Cut Off Ditches .............................................................................................. 33 5.1.3 Discharge Channels....................................................................................... 33 5.1.4 Collection of Water in Embankments ............................................................. 33 5.1.5 Embankment Toe Ditches .............................................................................. 34 5.2 Drainage of Ground Water .................................................................................... 34 5.2.1 Drainage Remedies ....................................................................................... 34 5.3 Erosion Control ..................................................................................................... 35 5.3.1 Protection of Slopes ....................................................................................... 36 5.3.2 Protection of Ditches and Channels ............................................................... 37 The Republic of Kenya – Ministry of Roads 1—3 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 6 Subgrade ..................................................................................................................... 38 6.1 Subgrade Classes................................................................................................. 38 6.2 Classification of Kenyan Subgrades ...................................................................... 39 6.3 Determining the Subgrade Strength ...................................................................... 40 6.3.1 Recommended Subgrade CBR Test Procedure............................................. 40 6.3.2 Subgrade Compaction Requirements ............................................................ 40 6.3.3 Estimating the Subgrade Moisture Content .................................................... 41 6.3.4 Determining the Subgrade Design Strength ................................................... 41 6.4 Subgrade Requirements for Pavement Design ..................................................... 42 6.4.1 Materials Suitable for Pavement Support ....................................................... 42 6.4.2 Improved Subgrade ....................................................................................... 42 6.4.3 Lime Treated Subgrade ................................................................................. 43 7 Pavement Materials .................................................................................................. 44 7.1 Subbases ............................................................................................................ 44 7.1.1 Natural Materials ......................................................................................... 44 7.1.2 Graded Crushed Stone .................................................................................. 45 7.1.3 Stabilised Natural Materials ........................................................................... 46 7.2 Bases.................................................................................................................... 46 7.2.1 Natural gravel ................................................................................................ 46 7.2.2 Graded Crushed Stone ............................................................................. 47 7.2.3 Stabilized materials ........................................................................................ 48 7.2.4 Lean Concrete ............................................................................................... 51 7.2.5 Sand Bitumen Mixes ...................................................................................... 51 7.2.6 Dense Bitumen Macadam .............................................................................. 53 7.2.7 Dense Emulsion Macadam ............................................................................ 55 7.3 Surfacings ............................................................................................................. 56 7.3.1 Prime Coat..................................................................................................... 56 7.3.2 Tack Coat ...................................................................................................... 56 7.3.3 Surface Dressing ........................................................................................... 56 7.3.4 Slurry Seals and Cape Seals ......................................................................... 62 7.3.5 Otta seal .......................................................................................................... 63 7.3.6 Sand Seal ...................................................................................................... 64 7.3.7 Fog Spray ...................................................................................................... 64 7.3.8 Thin Surfacings .............................................................................................. 64 7.3.9 Asphalt Concrete ........................................................................................... 66 7.3.10 Gap-graded Asphalt ....................................................................................... 74 7.3.11 Sand Asphalt ................................................................................................. 75 7.4 Other Materials ..................................................................................................... 75 7.4.1 Reclaimed Asphalt Pavement (RAP) ............................................................. 75 7.4.2 Modified Bitumens ......................................................................................... 77 7.4.3 Cold Bituminous Mixes .................................................................................. 77 7.4.4 Block Paving .................................................................................................. 78 7.4.5 Geosynthetic materials .................................................................................. 79 7.4.6 Hand-Packed Stone ....................................................................................... 80 7.4.7 Rumble Devices ............................................................................................. 82 7.4.8 Speed Humps ................................................................................................ 85 8 Structural Design Method ............................................................................................. 87 8.1 Design Principles .................................................................................................. 87 8.1.1 Thicknesses and Materials Characteristics .................................................... 87 8.1.2 Design Period ................................................................................................ 87 8.1.3 Stage Construction ........................................................................................ 87 8.1.4 Safety Factor ................................................................................................. 88 8.1.5 Minimising Base and Surfacing Thicknesses ................................................. 88 The Republic of Kenya – Ministry of Roads 1—4 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 8.2 Practical and experimental considerations ............................................................ 88 8.2.1 Use of Flexible Pavements ............................................................................ 88 8.2.2 Influence of Subgrade .................................................................................... 88 8.2.3 The Behaviour of Pavement Materials ........................................................... 90 8.3 Calculation of stress, strain, deflection and layer thickness ................................... 91 8.3.1 Calculation of stress, strain and deflection ..................................................... 91 8.3.2 Determination of layer thicknesses ................................................................ 92 8.4 Construction Principles ......................................................................................... 93 8.4.1 Minimum layer thickness ................................................................................ 93 8.4.2 Minimum significant thickness increments ..................................................... 93 8.4.3 Compliance with the specifications ................................................................ 93 9 Standard Pavement Structures .................................................................................... 95 10 Pavement Shoulders, Drainage and Cross Sections .............................................. 110 10.1 Shoulders ........................................................................................................ 110 10.1.1 Bearing Capacity of the Shoulders ............................................................... 110 10.1.2 Surfacing of Shoulders................................................................................. 111 10.1.3 Prevention of cracks in the shoulders .......................................................... 111 10.2 Drainage.......................................................................................................... 112 10.2.1 Drainage on the Road Surface and Shoulders ............................................. 112 10.2.2 Drainage of the Pavement Layers ................................................................ 112 10.2.3 Granular bases ............................................................................................ 112 10.2.4 Cemented or Bituminous bases ................................................................... 112 10.2.5 Drainage of the Subgrade ............................................................................ 113 10.3 Cross Sections ................................................................................................ 113 10.3.1 Edge Restraint ............................................................................................. 113 10.3.2 Recommended Cross-Sections.................................................................... 113 11 Problem Soils ......................................................................................................... 116 11.1 Low Strength Soils .......................................................................................... 116 11.2 Expansive Soils ............................................................................................... 116 11.2.1 Definition...................................................................................................... 116 11.2.2 Distribution ................................................................................................... 117 11.2.3 Identification ................................................................................................ 117 11.2.4 Remediation ................................................................................................ 118 11.3 Saline Soils ..................................................................................................... 120 11.4 Organic Soils ................................................................................................... 121 12 Gravel Roads ......................................................................................................... 122 12.1 Introduction ..................................................................................................... 122 12.2 Design Elements of Gravel Roads ................................................................... 122 12.3 Design of Gravel Roads .................................................................................. 123 12.4 Material Specifications..................................................................................... 124 12.4.1 Gravel wearing course materials (GW) ........................................................ 124 12.4.2 Subgrade materials (S2, S3) ........................................................................ 126 12.5 Deterioration and Maintenance........................................................................ 126 12.5.1 Gravel Loss and Recharge .......................................................................... 126 12.5.2 Maintenance ................................................................................................ 127 13 Concrete Roads ..................................................................................................... 129 13.1 Introduction ..................................................................................................... 129 13.2 Concrete Pavement Characteristics & Types .................................................. 130 13.2.1 Characteristics ............................................................................................. 130 13.3 Types .............................................................................................................. 131 13.4 Pavement Components and Functions ............................................................ 131 13.4.1 Subgrade and Subbase ............................................................................... 131 13.4.2 Concrete Slab .............................................................................................. 132 The Republic of Kenya – Ministry of Roads 1—5 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 13.5 Factors influencing the design process and selection of pavement type .......... 141 13.6 Stress Development and Design Criteria ......................................................... 142 13.6.1 Horizontal Tensile ........................................................................................ 142 13.6.2 Horizontal Compressive ............................................................................... 142 13.6.3 Vertical......................................................................................................... 143 13.7 Concrete Pavement Design ............................................................................. 143 13.7.1 Traffic .......................................................................................................... 143 13.7.2 Failure Criteria ............................................................................................. 143 13.7.3 Thickness design ......................................................................................... 144 13.8 Construction issues ......................................................................................... 149 13.8.1 Labour Intensive works ................................................................................ 149 13.8.2 Medium mechanisation works ...................................................................... 149 13.8.3 High mechanisation works ........................................................................... 149 13.8.4 Roller-compacted concrete pavements ........................................................ 149 13.8.5 Surface finish ............................................................................................... 150 13.9 Maintenance and repair ................................................................................... 150 13.10 References ...................................................................................................... 151 Appendix : Construction details for Mbagathi Way, Nairobi............................................ 152 14 Materials Sampling and Testing ............................................................................. 159 14.1 Introduction ..................................................................................................... 159 14.2 Mass of Samples Required ............................................................................. 159 14.2.1 Soil and Gravel ............................................................................................ 159 14.2.2 Stone ........................................................................................................... 159 14.2.3 Feasibility Study........................................................................................... 160 14.2.4 Preliminary Design ....................................................................................... 160 14.3 Final Design .................................................................................................... 163 14.3.1 Earthworks and Subgrade............................................................................ 163 14.3.2 Soil and Gravel Borrow Pits ......................................................................... 166 15 Standard Methods of Testing.................................................................................. 169 15.1 Soils ................................................................................................................ 169 15.2 Aggregates ...................................................................................................... 170 15.2.1 Determination of Average Least Dimension ................................................. 171 15.3 Cement or Lime Stabilised Materials ............................................................... 171 15.4 Cement and Lime Testing ............................................................................... 172 15.5 Bituminous Binders ......................................................................................... 172 15.5.1 Sampling procedures ................................................................................... 172 15.5.2 Testing procedures ...................................................................................... 172 15.6 Bituminous Mixtures ........................................................................................ 173 15.6.1 Sampling procedures ................................................................................... 173 15.6.2 Testing procedures ...................................................................................... 173 15.6.3 CEN Tests ................................................................................................... 174 16 Footpaths ............................................................................................................... 176 The Republic of Kenya – Ministry of Roads 1—6 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 1 General 1.1 Introduction This Manual relates to the construction of new bituminous, gravel and concrete roads in Kenya. It updates the Kenya Road Design Manual, Part III, Materials & Pavement Design for New Roads (RDM III), published in August 1987. A Seminar attended by 45 stakeholders in 1997 reviewed RDM III in the light of their own knowledge and experience. Their conclusions, together with subsequent developments, particularly in pavement design and asphalt mix design, are included in this revision. The updated Manual has attempted to ‘harmonise’ with the Standards of neighboring countries, such as Tanzania, Uganda, South Africa and Ethiopia, whose Standards have all been updated in the last 10 years. Since the Manuals of these countries show considerable differences in style and content, the approach adopted has been to harmonize their principles and procedures but retain the format and style of the old Kenyan Manual in order to retain familiarity. For the first time a section has been included on concrete roads. When the Kenyan Manuals were first prepared the modern computer age was in its infancy. Now it is possible to obtain information for pavement materials and design from the World Wide Web and therefore the updating of any manual is a dynamic and on-going process. Notwithstanding the recommendations contained in this Manual it is the engineer’s responsibility to propose modifications he considers will result in a superior and costeffective design. The adoption of this Manual does not guarantee a serviceable and economic road design. This can only be achieved by balancing the various controls, criteria and elements involved. This Manual is part of a set, listed in Table 1.1, which have now been updated in 2009 by Egis-BCEOM, listed in Table 1.2, courtesy of a grant from the European Union. EgisBCEOM gratefully acknowledges the contribution from other works of reference in the east and south African region together with the collaboration of various Ministry of Works staff and other local stakeholders. Table 1.1: Current Kenya Road Design Manuals Road and Bridge Design Part I Geometric Design of Rural Roads Part II Geometric Design of Urban Roads (draft) Part III Materials & Pavement Design for New Roads Part IV i Bridge Design (draft) Part IV ii Hydraulic Design of Drainage Structures Part V Pavement Rehabilitation and Overlay Design Traffic Control Devices Part I Road Marking Part II Traffic Signs Part III Traffic Signals (never produced) Standard Drainage Structures The Republic of Kenya – Ministry of Roads 1 Previous Date of Publication 1979 2001 1987 1982 1983 1988 1972 1975 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Part I Small Span Concrete Bridges Part II Concrete Box Culverts Standard Specification for Road & Bridge Construction Road Maintenance 1987 1987 1986 Road Maintenance Manual (JICA) 2004 ‘Roads 2000’ Manuals for rural roads 2009 Minor Roads Programme: Technical & Maintenance Manuals Table 1.2: Proposed New Kenya Road Design Manuals Standard Specifications 1000 General 2000 Drainage 3000 Earthworks and Pavement Layers of Natural or Crushed Gravel 4000 Bituminous Layers and Seals 5000 6000 7000 Design Manuals Part 1 Geometric Design Part 2 Drainage Design Part 3 Design for New Bituminous, Concrete and Gravel Roads Part 4 Overlay and Asphalt Pavement Rehabilitation Ancillary Roadworks Part 5 A) Traffic Signs and Road Marking B) Road Furniture, Lighting, Traffic Control Devices and Signals C) Traffic Surveys Structures Part 6 a) Bridge and Culvert Design b) Catalogue of Typical Bridges, Culverts and Miscellaneous Structures Tolerances, Testing and Quality Part 7 Environmental Guidelines Control The Republic of Kenya – Ministry of Roads 2 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 1.2 Units of Measurement The standard units of measurement used are based on the International System (SI) units together with some not strictly part of SI but applicable to road design. Multiples and submultiples of SI units are formed either by the use of indices or prefixes. Definitions of applicable prefixes are given in Table 1.2. The basic units and the derived and supplementary units which will normally be required for road design are listed in Table 1.3. Table 1.3: Definitions of Prefixes Prefix mega kilo hecto deca deci centi milli micro Symbol M k h da d c m µ Multiplication factor 106 103 102 10 10-1 10-2 10-3 10-6 Table 1.4: Basic Units, Multiples & Sub-Multiples Quantity Unit Length Mass Time Area Volume (solids) Volume (liquid) Density Metre Kilogram Second square metre cubic metre Symbol Multiples and Sub-multiples m km, mm kg Mg, g, mg s day (d), hour (h), minute (m) m2 km2, hectare (=10,000m2), mm2 m3 cm3, mm3 Litre l ml, 1ml=10-3l=1cm3 kilogram per cubic metre Newton kg/m3 Pascal N/m2 1Mg/m3=1kg/l = 1g/ml MN, kN (1N = 1kgm/s2 1kgf = 9.81N) 2 kN/m (kPa), N/mm2 (MPa) Force Pressure & Stress Velocity (speed) Angle N metre per second m/s degree or grade Temperature degree Celsius 0 Km/h (1km/h =1/3.6 m/s) Minute (‘), second (“), (3600 circle) (400g circle) 0 C The Republic of Kenya – Ministry of Roads 3 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 1.3 Definitions and Abbreviations 1.3.1 Pavement Figure 1.1 Road Pavement Terminology Fig 1-1 shows the terms used in describing the principal pavement and cross section components. The Republic of Kenya – Ministry of Roads 4 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 1.3.2 Pavement layers Formation is the surface of the ground, in its final shape, upon which the pavement structure, consisting of subbase, base and surfacing is constructed. Subgrade consists of all the material below the subbase, including in-situ material, fill and improved subgrade. (In AASHTO subgrade has the same meaning as roadbed: another name for the subgrade is Foundation). For design purposes the following subgrade classes are recognized: Subgrade Class S1 S2 S3 S4 S5 S6 CBR Range 2 3 to 4 5 to 7 8 to 14 15 to 29 30 or more Fill is approved imported material used below formation level to construct embankments or replace unsuitable natural material. Most types of soil and broken rock can be used but highly plastic soil, expansive soil and organic soil should be avoided. Improved (or selected) subgrade is a layer of selected fill material, the top of which is at formation level, placed where the natural in-situ or fill material is unsuitable for the direct support of the pavement. Its purpose is to increase the strength and stiffness of the insitu material and thus reduce the pavement thickness. Subbase consists of a medium quality granular layer resting on the subgrade and supporting the base course. Base (or road base) consists of a pavement layer lying between the surfacing and the subbase, which can be constructed from asphalt, granular or stabilised material. Binder Course consists of the lower bituminous layer of the pavement, usually asphalt concrete. It is not always present; the wearing course may rest directly on the base course. Surfacing is the uppermost pavement layer which provides the riding surface for vehicles. It will normally consist of one of the following: surface dressing, sand asphalt or asphalt concrete. If constructed of asphalt it will include a surfacing and an optional binder course. Wearing Course consists of the uppermost bituminous layer of the pavement, usually asphalt concrete. The top surface of this layer should provide a smooth surface but with adequate texture to provide adequate friction for safe vehicle braking and turning. 1.3.3 General Terms Borrow Area is a site from which natural material, other than solid stone, is removed for construction of the works. (The term borrow pit is also used.) Quarry is an open surface working from which stone is removed by drilling and blasting, for construction of the works. The Republic of Kenya – Ministry of Roads 5 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Stabilized Materials are naturally occurring gravels and clayey sands, or crushed stone, to which either cement or lime, or both, have been added, in order to improve their engineering properties. Lean Concrete is a high quality, well graded aggregate and Portland cement mixture, mixed in a stationary plant and laid by a paver. It is used as a high quality base. Rock fill is rock material of such particle size that the material can only be placed in layers of compacted thickness exceeding 300mm. Boulders with volumes greater than 0.2m³ are not normally used. Graded Crushed Stone consists of quarried stone which has been crushed to a range of sizes, conforming to a high quality specification for grading, cleanliness, strength, shape and soundness. Normally graded crushed stone is used for roadbase or as the aggregate in bituminous bound material. . Gravel Wearing Course consists of a surfacing applied to a road formation where no bituminous surfacing is to be placed. The gravel can include one or a combination of the following materials: lateritic gravel, quartzitic gravel, calcareous gravel, some forms of partly decomposed rock, soft stone, coral rag, clayey sands and crushed rock. 1.3.4 Bituminous Materials Bituminous Binders are petroleum-derived adhesives used to stick chippings onto a road surface, as in surface dressings, or to bind together a layer of surfacing or base material. There are three principal types used in road work: Straight-Run (or Penetration) Bitumen is bitumen whose viscosity or composition has not been adjusted by blending with solvents or any other substance. Cut-Back Bitumen is bitumen whose viscosity has been reduced by the addition of volatile diluent, such as kerosene or diesel. Short Residue Bitumen is the primary product of the refinery before the air-blowing process, and is bitumen of variable viscosity whose penetration can be measured, and which approximates to a slow-curing cut-back bitumen. Bitumen Emulsion is bitumen in finely-divided droplets dispersed in water by means of an emulsifying agent to form a stable mixture. Surface Dressing is a method of providing a running surface to a pavement and consists of applications of bituminous binder and single sized stone chippings. The usual form of this method on a new road is a double surface dressing with the second layer of chips being half the nominal size of the first. Single, triple and other types of surface dressings are also used. Instead of chippings sand may be used (=sand seal). Two layers of chippings may also be applied to one coat of bitumen (=’racked-in’ surface dressing). Emulsion Slurry Seal is a surfacing material, used by itself in one or two layers, or on top of a single surface dressing. It consists of fine aggregate, mineral filler and bitumen emulsion. Cape Seal is a surfacing where a slurry seal is applied on top of a surface dressing to produce a surface less harsh than a surface dressing and which is flexible and durable, The Republic of Kenya – Ministry of Roads 6 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Fog Spray is a light application of bitumen emulsion or cut-back, applied to the top of a surface dressing, in order to improve the waterproofing quality of the surfacing and to assist in holding the chippings. Otta Seal is similar to a surface dressing except that a graded aggregate is used instead of single sized chippings. It may be applied as a single or double layer. Asphalt Concrete is a bitumen-bound premix. It consists of a mixture of coarse aggregate, fine aggregate and filler, bound with straight-run bitumen. The proportions and grading of the constituents may be varied by using the Marshall test method to meet specific strength, deformation and volumetric criteria. Sand Asphalt is a surfacing material consisting of a hot-mixed, hot-laid, plant mixture of natural sand and, in some cases, mineral filler and crushed fine aggregate, bound with straight-run bitumen. Gap-Graded Asphalt is a hot laid, plant mixture of gap-graded aggregate, filler and straightrun bitumen, used for pavement surfacing. Binder Course is the lower layer when two-course asphalt concrete is used as a surfacing. It usually differs from the upper, wearing course, in having larger sized aggregate, a slightly lower bitumen content, lower stability and greater voids. Sand Bitumen is a base material consisting of a cold, mixed-in-place combination of sand (or clayey sand) and either bitumen emulsion or cut-back. This material is intended for use in areas with little or no gravel deposits. Dense Bitumen Macadam is a hot-laid, hot-mixed recipe bituminous mixture consisting wellgraded aggregate, filler and straight-run bitumen, normally used for base construction. Dense Emulsion Macadam is a cold laid, plant mixture of well graded aggregate, filler and bitumen emulsion, used for base construction. The specifications are very similar to dense bitumen macadam. Prime Coat consists of low viscosity, usually cutback bitumen, applied to an absorbent surface, usually the top of the base, which prime purpose is to help bind it to the overlaying bituminous layer. . Tack Coat is a light application of bituminous binder applied to a bituminous or concrete surface in order to glue this surface to the overlying, normally bituminous course. 1.3.5 Traffic Private cars (cars) are all passenger motor vehicles seating not more than 9 persons, including the driver. Light Vehicles are all goods vehicles of not more than 15kN unladen weight. Buses are all passenger motor vehicles seating more than 9 persons, including the driver. Medium Goods Vehicles are all two-axle goods vehicles of more than 15kN unladen weight. The Republic of Kenya – Ministry of Roads 7 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Heavy Goods Vehicles are all goods vehicles having more than two axles. Commercial Vehicles include buses and goods vehicles of more than 15 kN unladen weight. Equivalent Standard Axle (ESA) is a concept enabling the damaging effect of a range and number of different axle loads to be considered in the structural design of a pavement. The equivalent standard axle imposes a load of 80 kN (8,200 kgf) and other axles are correlated to this by the following equation: 80 ESA L 4.5 where ESA is the equivalent standard axle, L is the axle load in kN divided by the standard 80kN axle, and 4.5 the exponent representing the relative damage Design Period is the time period over which the proposed pavement must carry the predicted number of equivalent standard axles without the need for major rehabilitation work, except for maintenance. At the end of this period the pavement should still be in a sufficiently good condition that strengthening will result in a further period of satisfactory traffic-carrying. Traffic Classes are the predicted cumulative numbers of equivalent standard axles divided into the following classes: Traffic Class Cumulative Number of Standard Axles (ESA) T1 0.003 to 0.25 T2 0.25 to 1 T3 1 to 3 T4 3 to 10 T5 10 to 25 T6 25 to 60 T7 60 to 100 1.3.6 Abbreviations AASHO American Association of State Highway Officials, which became AASHTO AASHTO American Association of State Highway and Transportation Officials AADT Average Annual Daily Traffic ADT Average Daily Traffic ACV Aggregate Crushing Value ALD Average Least Dimension ASL Above Sea Level ASTM American Society for Testing and Materials The Republic of Kenya – Ministry of Roads 8 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement BS British Standard CBR California Bearing Ratio COMESA Common Market for East and South Africa CR Crushing Ratio DCP Dynamic Cone Penetrometer ESA Equivalent Standard Axle FI Flakiness Index GM Grading Modulus = [300-(% passing 2mm)-(% passing 0.425mm)-(% passing 0.075mm)]/100 HF Hubbard - Field KEBS Kenya Bureau of Standards ISO International Standard Organization LAA Los Angeles Abrasion LL Liquid Limit MC Moisture Content MDD Maximum Dry Density OMC Optimum Moisture Content PL Plastic Limit PI Plasticity Index PM Plasticity Modulus = (PI * % passing 0.425mm sieve) SADC Southern African Development Community SG Specific Gravity SS Standard Specification for Road Construction SSS Sodium Sulphate Soundness TS Tensile Strength UC Uniformity Coefficient = Ratio of Sieve size through which 60% of material passes to Sieve size through which 10% of material passes UCS Unconfined Compressive Strength The Republic of Kenya – Ministry of Roads 9 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 VH Part 3 - Materials and Pavement Vibrating Hammer The Republic of Kenya – Ministry of Roads 10 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 1.3.7 Comparison of BS and ASTM Sieve Sizes BS sieve Aperture size 75mm 63 50 37.5 28 20 14 10 6.3 5 3.35 2 1.18 600µm 425 300 212 150 75 63 ASTM D422 Aperture Size 3 inch 2½ inch 2 inch 1½ inch ¾ inch ⅜ inch #4 #6 #8 # 10 # 16 # 20 # 30 # 40 # 50 # 60 # 70 # 100 # 200 # 230 75mm 63.5 50.8 38.1 19.05 9.52 4.75 3.35 2.36 2.00 1.18 850 µm 600 425 300 250 212 150 75 63 The Republic of Kenya – Ministry of Roads 11 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 2 Traffic 2.1 General Deterioration in paved roads caused by traffic is a function of the magnitude of the individual wheel loads and the frequency with which they are applied. For pavement design purposes, therefore, it is necessary to know not only the total number of vehicles using the road but also the axle loads. Traffic loading is normally expressed in terms of ‘equivalent standard axles’, ‘ESA’, a concept developed following the AASHO Road Test carried out in the USA in the late 1950s. An axle carrying 8.16 tonnes was arbitrarily defined as a ‘standard axle’, to which axles of different weights were correlated to derive equivalence factors, thereby obtaining an expression of the damaging effect. Thus: 80 ESA L 4.5 Where ESA is the equivalent standard axle, L is the axle load in kN divided by the standard 80kN axle, and 4.5 the exponent representing the relative damage. This equation was derived by Liddle (1962) for the test conditions at the time. Although Liddles’ formula is safe only up to axle weights of 130kN (13 tonnes), nevertheless, in the absence of anything better, current practice is still to use this equation for greater axle weights. A more secure practice would be to determine the proportion of axle weights greater than 130kN and then to adjust the traffic category accordingly (see later). There is now considerable evidence that the 4.5 exponent varies according to the pavement type, thickness, balance (how the strengths of the constituent layers compare with one another), and subgrade strength. Values between 3 and 5 have been determined from research in South Africa with a Heavy Vehicle Simulator (Van Zyl et al, 1984). For the sake of simplicity, and also since most current pavements in Kenya are of the same type, the 4.5 value is retained. A tandem axle may inflict slightly more or slightly less damage than two separate axles depending on various factors but, again for simplicity, it is recommended that they are treated separately in the calculation of ESA. The ultimate objective in design is thus to determine the cumulative number of ESA in the design period. This is achieved in a number of operations: the axle load distribution of the traffic is evaluated the axle loads converted into ESA the initial daily number of ESA calculated, and an annual growth rate over the design period selected. 2.2 Present Kenya legislation The Kenya Roads Board (KRB), website (www.krb.go.ke/), states that there is an estimated 185,000km of roads in Kenya, defined in Table 2.1: The Republic of Kenya – Ministry of Roads 12 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Table 2.1: Kenya Road Classification Type Class Description Length, km Authority responsible National A, B, C Main highways 14,000 Roads Dept, Ministry of Roads & Public Works District D, E Secondary roads 49,000 District Roads Committees Unclassified Rural 100,000 Urban City & town Urban 14,000 Special Purpose Park & Game Park & Reserve Reserve Game 8,000 City, Municipal Councils & Town Kenya Wildlife Service, Forest Department Low volume roads (<200vehicles per day) comprise over 80% of the road length and roughly carry about 40% of the traffic, in terms of vehicles per day. These roads will be generally constructed either of gravel or earth and some will also have an all-weather surfacing. The legal limits currently in force in Kenya, according to Legal Notice No 118-Traffic Amendment Rules 2008, are listed in Table 2.2: Table 2.2: Vehicle Axle Load Legal Limits Axle Group Legal Limit (kg) Error allowance Allowable Axle Load Single Steering 8,000 - 8,000 Single Rear 10,000 400 10,400 Tandem Rear 16,000 600 16,600 Triple Rear 24,000 800 24,800 The Maximum Gross Vehicle Weight of a vehicle is defined in Table 2.3: Table 2.3: Maximum Permissible Gross Vehicle Weights Vehicle Type Legal Limit (kg) Vehicle with two axles 18,000 Vehicle with three axles 24,000 Vehicle & semi-trailer with total of three axles 28,000 Vehicle & semi-trailer with total of four axles 34,000 Vehicle & drawbar trailer with total of four axles 36,000 Vehicle & semi-trailer with total of five axles 42,000 Vehicle & drawbar trailer with total of five axles 42,000 Vehicle & semi-trailer with total of six axles 48,000 Vehicle & drawbar trailer with total of six axles 48,000 No vehicle with more than six axles is permitted unless special exemption is granted. The Republic of Kenya – Ministry of Roads 13 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement These recommendations compare well with those of SADC and COMESA which are listed in Table 2.4. Table 2.4: SADC and COMESA Vehicle Weight Limits Economic Load Limits (tonnes) Grouping Single Axle Tandem (8 tyres) Steering Drive (2 tyres) (4 tyres) SADC 8 10 18 COMESA 8 10 16 Tridem GVM (12 tyres) 24 24 56 53 By comparison, in the UK, the maximum permitted weight of an articulated vehicle increased by more than a third between 1983 and 2001. Today goods vehicles with 6 axles can weigh 44 tonnes, articulated combinations can be up to 16.5m long while drawbar combinations (and bendy buses) can be up to 18.75m long. Many stakeholders are convinced these increases have been beneficial in terms of safety the environment and the economy. Many others are equally convinced that they have had the opposite effect. In Sweden and Finland vehicles of up to 60 tonnes and 25.25m length are permitted and several other countries in Europe are considering permitting them with the Netherlands at an advanced trial stage. Enforcement of axle load limits is undertaken by Roads Dept. of the Ministry of Roads & Public Works and operations are carried out on a 24/7 hour basis. There are five permanent weighbridge stations located along the Mombasa to Nairobi and Malaba road at Mariakani, Athi River, Gilgil, Webuye and Isebania. In addition there are weighbridge stations at Mombasa Port, Mtwapa, Namanga, Nairobi, Maai Mahui, Kisumu and Malaba. All vehicles greater than 7 tonnes gross weight must be weighed and non-compliant vehicles charged and prohibited from using the road until in compliance. The KRB states a compliance rate of 80 to 90%. However, it is understood that on many routes the overloading may exceed these values, especially if there is no monitoring. It is therefore recommended that for any new project an axle load survey is carried out to obtain an accurate assessment of the design traffic. An additional factor leading to increased stress on the pavement is tyre pressures, which have increased significantly in recent years. The tyre pressure used in the AASHO road test in 1962 was 0.48MPa (70psi) whereas a study carried out in Kenya in 1987 recorded the mean value as 0.7MPa (102psi). Additionally, tyre configurations have changed, whereby modern single tyres or ‘super single’ tyres (wider than singles) have replaced the original twin tyres on trucks, each with different damaging effects. These factors are presently not considered in the computation of ESA. 2.3 Evaluation of Traffic for Design Purposes 2.3.1 Traffic Counts The loads imposed by private cars and light goods vehicles with axle weights < 1.5tonnes do not contribute significantly to the structural damage of a paved road and thus, for design purposes, can be ignored. However, for economic and congestion forecasting, the total traffic is determined and routine traffic counts are carried out annually by the Ministry of Transport & Communications at a number of census points. They distinguish between cars, The Republic of Kenya – Ministry of Roads 14 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement light goods, buses, medium goods and heavy goods vehicles. Where such results are available, the initial daily traffic can be estimated by extrapolation. A standard type of vehicle classification scheme is presented in Table 2.5. Table 2.5: Vehicle Classification Scheme Category Type Description 1 Light vehicles 1a Motorcycles Motorcycles with/without side cars 1b Passenger cars Cars seating up to nine passengers 1c Small buses Matatus, minibuses seating up to 30 passengers 1d Light Goods 2 Medium and heavy vehicles 2a Large buses Buses and coaches seating more than 30 passengers 2b Medium goods 2 axles, twin tyres on rear axle, >1.5 tonnes unladen weight, <8.5 tonnes gross vehicle weight 2c Heavy goods 3 axles 2d Heavy goods 4 axles or more, trailers included, >3 tonnes unladed weight or >8.5 tonnes gross vehicle weight 3 Others Tractors, road rollers, or vehicles with 5 or more axles depending on survey requirements Where traffic census data is not available or is insufficient, specific traffic counts are required at key points and axle load surveys carried out to determine the initial daily traffic and possible seasonal variations. The recommended survey period is one week, for 24 hours at least on two days to determine the nighttime flows, and the counts are classified into the abovementioned traffic classes. Times when there are especially increased or decreased traffic flows should be avoided. Automatic counters can be used for greater accuracy because the survey can be conducted over a longer period and detect seasonal variations caused by the weather or harvest time for example but, unless very sophisticated and expensive types are used, obviously cannot distinguish vehicle types. Details of automatic counters are contained in TRL ORN 40 (2004). 2.3.2 Axle Load Surveys Axle load surveys are required to estimate the ESA. Most of the ESA will be carried by the medium and heavy vehicles and Fig 2.1 proposes a scheme to distinguish the different types of these vehicles in the execution of an axle load survey. Figure 2.1: Commercial Vehicle Types The Republic of Kenya – Ministry of Roads 15 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement The most common method of carrying out an axle load survey is to weigh a sample of vehicles at the roadside using portable weighpads. It is possible to weigh about 60 vehicles per hour using this method. If the traffic flow is too high a sample should be selected for weighing. Weigh-in-motion equipment is popular but it is less accurate, requires regular calibration and more expensive. It is important that weighpads are regularly calibrated by either the manufacturer using a proving ring or in the field with a vehicle of known weight. On many roads it will be necessary to consider whether the axle load distribution of the traffic in both directions is the same and significant differences can occur for example on roads connecting docks, quarries, heavy industrial works and mining areas. In Kenya the Mombasa-Nairobi-Uganda highway is a good example. Survey results from the more heavily trafficked direction should be used for pavement design purposes. 2.3.3 Evaluation of Axle Loads The axle loads will be obtained by multiplying the average daily number of commercial vehicles by the appropriate Equivalence Factor and then summing the ESA for all the vehicle types. In Table 2.6 the effect of road width and vehicle flow is considered for design purposes. The Republic of Kenya – Ministry of Roads 16 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Table 2.6: Calculation of Commercial Traffic Carriageway Width, m Traffic, Commercial Commercial considered Vehicles per day Traffic to be Single, ≤ 7 Total commercial traffic in BOTH DIRECTIONS Single, > 7 Total commercial traffic in MOST HEAVILY TRAFFICKED LANE Dual < 2000 Total commercial traffic in ONE DIRECTION Dual > 2000 A special study of the distribution will be necessary traffic Notes 1. On single carriageway roads, the offside wheeltracks of commercial vehicles tend to follow the central part of the road, the more so as the carriageway becomes narrower and the traffic lighter. Where the carriageway width is 7m or less it is assumed that the central section of the road is used by over 70% of the commercial vehicles and, in this case, the sum of the ESA in both directions is taken to allow for the overlap. 2. On dual carriageway roads, the inside, slow-traffic lanes will usually carry at least 80% of the commercial vehicles, as long as the flow does not exceed 2000 commercial vehicles per day. If it is more, then special studies will be needed to estimate the proportion of commercial vehicles using each dual carriageway lane. 2.3.4 Estimating the Cumulative Number of Standard Axles To estimate the total number of ESA for the pavement design, it is necessary to forecast the annual traffic growth rate and decide the length of the design period, as described below: 2.3.4.1 Forecasting the Annual Growth Rate This is a difficult exercise but it may help to separate traffic into the following three categories and estimate how each category could grow in the future: Normal Traffic: traffic which would pass along the existing road in ordinary circumstances whose growth could be based on national historical trends, fuel sales or any other specific local circumstances. Diverted Traffic: traffic that changes from another route but still retains the same origin and destination Generated Traffic: additional traffic that is generated in response to the improvement of a road. Guidance can be obtained from the following factors: historical growth, economic trends, geometric capacity of the road, increases in vehicle numbers and loading and social realities. Typical growth rates range from 2 to 15% per annum, averaging about 4% per annum. The Republic of Kenya – Ministry of Roads 17 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 2.3.5 Length of Design Period Design period should not be confused with design life. At the end of the design period the road pavement will not be completely worn out or have deteriorated to the point that reconstruction is needed but only require to be strengthened to carry traffic for a further period. During the design period, it is accepted that routine maintenance (eg shoulders and drainage system maintenance, vegetation control, patching and sealing) and periodic maintenance (surface dressing, asphalt overlays, slurry seals) will be carried out. The aim is to minimize the total expenditure on the pavement, including the initial construction cost and subsequent maintenance or strengthening costs discounted to the present day value. This raises the question of stage construction. Stage construction offers economic advantages and initial design periods should not exceed 15 years, even if longer overall lives are anticipated. It also provides an opportunity to choose the structural characteristics of the second stage in the light of actual conditions, which may differ substantially from the original conditions. The cumulative number of ESA, T, for the chosen design period, N (in years), is then obtained from the following: T 365t1 1 i N 1 i Where: t1 is the average daily number of standard axles in the first year after opening, and i is the annual growth rate expressed as a decimal fraction 2.4 Traffic Classification The traffic classes listed in Table 2.7 adequately account for all traffic categories likely to be carried by the bituminous roads of Kenya. Table 2.7: Traffic Classes Class T1 Cumulative Number ESA 0.003 to 0.25 million T2 0.25 to 1 million T3 1 to 3 million T4 3 million to 10 million T5 T6 T7 10 million to 25 million 25 million to 60 million 60 million to 100 million of Description Very light traffic; very few heavy vehicles. These roads can be defined as ‘Low Volume’ (<200vpd) and are the transition from gravel to paved roads; they may use non-standard materials and may also have all-weather surfacings Light traffic; mainly cars, pick-ups and small trucks with <10% heavy commercial vehicles. Moderate traffic; 10% to 20% heavy commercial vehicles High traffic volume and/or >20% heavy commercial vehicles Very high traffic volume and/or many laden commercial vehicles Very high volume of heavily laden commercial vehicles The Republic of Kenya – Ministry of Roads 18 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement The proportion of axle loads greater than 130kN should be determined and, if this proportion is greater than 50% of the total axle loads, consideration should be given to increasing the traffic class by one for the purposes of design. The Republic of Kenya – Ministry of Roads 19 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 3 Natural Environment 3.1 Climate Climate has a fundamental influence on road materials and performance. Straddling the Equator from 40N to 40S with a land area of 580,000 km2 (85% of the area of France), Kenya has a tropical climate, ameliorated by relief. It is hot-humid at the coast, warm-temperate inland and hot-dry in the north and northeast parts of the country. There are two rainy seasons: one between March and June, and the other between October and November. The temperature remains high throughout these months except in the uplands. The rainfall is sometimes heavy and falls in the afternoon and evening. The hottest period is from February to March and coolest in July to August. From the coast on the Indian Ocean the low plains rise to central highlands, thence to the shores of Lake Victoria at 1130m ASL. The highlands are bisected by the Great Rift Valley but are also the site of the highest point in Kenya, Mount Kenya, which reaches 5,199 m ASL. Mount Kilimanjaro which at 5,895m ASL is the highest point in Africa can be seen from Kenya just south of the Tanzanian border. The design of drainage systems largely depends on the expected climatic conditions. The choice of roadmaking materials will also be influenced by climate: in this respect, the following areas have been demarcated: ‘wet’ areas (mean annual rainfall greater than 500mm), where the use of plastic pavement materials, defined as having a PI >50, should be avoided if possible. Bituminous surfacings should be as impervious as possible. Shoulders should be impermeable or properly sealed. Great attention should always be paid to both internal and external drainage ‘dry’ areas (mean annual rainfall less than 500 mm), where higher plasticities can be accepted for pavement materials and open-textured base materials can be used. Difficulties may occur with cement-treated materials, because of the rapid evaporation of water hindering the hydration of cement and the tendency of the treated material to crack extensively as a result of shrinkage and volumetric changes caused by the daily temperature variations. Drainage and protection against erosion should not be neglected as short but heavy storms are likely to occur even in the driest areas. The diversity of climate is illustrated by Figs 3.1 and 3.2. The Republic of Kenya – Ministry of Roads 20 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Figure 3.1: Kenya: Temperature maxima-minima The Republic of Kenya – Ministry of Roads 21 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Figure 3.2: Rainfall maxima-minima The Republic of Kenya – Ministry of Roads 22 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 3.2 Geology Kenya can be subdivided into three basic regions: the coastal fringe of Mesozoic and Tertiary strata the plains containing ancient soils derived from the weathering of the Pre Cambrian basement gneisses and granites, and Recent sandy or gravelly soils derived from the re-working of these deposits, and the highly weathered to relatively unweathered extrusive igneous rocks accompanying the volcanism associated with the development of the Rift Valley trough fault system which commenced in early Tertiary times and continues intermittently to the present. The extrusive rocks consist of volcanic ash and tuff and lava, generally of basic alkaline composition, which have been subject to profound tropical weathering, producing a variety of fertile soils, for example the red coffee soils, and black cotton soils, and other subgrades of variable suitability for road construction. Fig 3.3 illustrates the distribution of the main geological regions. A consequence of the variable geology is that there is a wide range of road-making materials available in Kenya. Many different sorts of gravels occur, including lateritic gravels, quartzitic gravels, calcareous gravels, coral limestone, etc. Various types of sand and silty or clayey sands are also found. Kenya also has abundant resources of hard stone lava aggregate and gneiss and granite stone although the degree of weathering of these materials is variable and often profound. The Republic of Kenya – Ministry of Roads 23 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Figure 3.3: Geology The Republic of Kenya – Ministry of Roads 24 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 3.3 Demography The current population of Kenya (late 2009) is around 40 million who are concentrated in the warm-temperate and fertile volcanic uplands, and along the coast as shown on the attached map. The main road network is thus to be found in this region, and is the area where most road building and road maintenance activity occurs. Apart from these, a main highway connects the port of Mombasa to the capital Nairobi and beyond to Uganda and other countries in central Africa and is thus of prime strategic importance. Fig 3.4 shows the population distribution. The Republic of Kenya – Ministry of Roads 25 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Figure 3.4: Demography The Republic of Kenya – Ministry of Roads 26 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 4 Earthworks Construction of new roads, and sometimes also reconstructed roads if they are widened, invariably requires the movement of soil and rock prior to building the road pavement. Cuttings and embankments will be constructed to obtain a satisfactory alignment on most roads and the following discusses the main factors to be considered. 4.1 Cuttings In most regions of the world cuttings are made in materials in different stages of weathering. This is particularly true in tropical regions where the higher temperatures increase the rate of chemical reaction, and if rainfall is significant, the result is often a quite profound and variable weathering profile. Cuttings in weathered rock and soil are generally unstable because of accumulation of water in the material and slips occur when this accumulation of water reduces the cohesion of the soil and increases its mass. Wherever a cutting is required, the following factors will affect its design and cost: Type, volume and position of the materials to be excavated Level and flow of water table and springs Stability of the slopes Drainage and protection against erosion 4.1.1 Type, volume and position of the materials to be excavated The type of material excavated governs the construction methods, the use to which the material can be put, its suitability as subgrade material and the slopes that can be safely constructed. From both economical and technical viewpoints it is important to determine with reasonable accuracy the respective volumes of rock, ‘rippable’ material and ‘diggable’ material occurring in each cut. This is not easy to determine, and it may not be possible until the construction phase, but an approximation can be achieved with boreholes: rotary percussion are the quickest and cheapest. Tropical weathering generally results in the occurrence of two types of materials: residual soils and weathered rock, which together with the fresh unweathered rock, if it is reached by the cutting, makes three material types. The depth and degree of weathering is usually very variable, both vertically and horizontally and the properties of the residual materials can vary over short distances at the same level. The depth to rock is clearly important not only because of its effect on the cost of the cuttings but also because the presence of rock can provide a surface on which a perched water table can exist. Depending on the type of rock and its structure, springs could also occur. The design CBR of the roadbed (= subgrade) in a cutting should be taken as the lowest realistic CBR value encountered within the material depth. The Republic of Kenya – Ministry of Roads 27 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 4.1.2 Level and flow of water table and springs Water tables and springs may be permanent, seasonal or (in the case of water tables) perched: all types can occur in Kenya. In any case, their presence and characteristics must be determined (although this is sometimes not easy to do) as they will affect the method of excavation, the stability of the cut slope and the drainage system required. 4.1.3 Stability of the slopes The analysis of slope stability is usually based on measurements of soil density, moisture content and soil strength together with calculations of soil stresses using slip-circle analysis. However, this type of analysis assumes that the soil mass is uniform, which is rarely the case and it is more common for failures to occur along vertical planes of weakness, or other pre-existing planes of weakness, such as joint or bedding planes, even if the rock is completely or profoundly weathered. In most cases slope angles are determined by experience and those that have generally been found to be satisfactory, where there is no water seepage or external loads present, are shown in Table 4.1: Table 4.1: Slope Angles for Earthwork Materials Material Sand (cohesionless) Silty sand/silt Residual (red) soil Weathered rock Fresh rock Vertical : Horizontal 1:2 1:1 1.5:1 if depth <4m 1:1 if depth >4m 2:1 to 4:1 5:1 to 10:1 It is advisable that any cutting greater than 5m height, or if the water table situation is problematical, should be studied by a specialist. This may well require a detailed site investigation and associated laboratory testing, resulting in recommendations for elaborate soil stabilization techniques, outside the scope of this manual. 4.1.4 Drainage and protection against erosion Control of ground water in the cut slopes is important for it is essential to disperse surface water from the road formation at all stages of construction. Adequate drains must be constructed at the toe of the cut slope to carry away surface water flowing off the cut slope; otherwise it could prejudice the stability of the road formation. Cut-off drains, constructed at the top of the cutting to prevent water from above the cutting adding to the run-off on the slope itself, must be properly lined and maintained otherwise they will exacerbate the instability of the cut slope. Control of slope erosion is sometimes difficult to reconcile with slope stability. For example, in the red clays, which are common in Kenya, a cut slope of 1:1 (see Table 4.1) would be extensively eroded where its height exceeded about 5m. Two solutions are possible. Either the slope is cut at 1:1 and planted with grass (preferably at the beginning of the first rainy period) or the slope is cut at 1.5:1 and provided with 2m wide benches at every 4m vertical spaces. The Republic of Kenya – Ministry of Roads 28 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement For aesthetic and safety reasons a low angle slope is normally considered more desirable than a near vertical slope. The need to balance the amount of cut and fill material may also have an influence on slope angles. In deep cuttings, where the pavement is laid soon after completion of the cutting, consideration should be given to heave, especially if the foot of the cutting is still in residual soil. 4.2 Embankments Embankments will be needed when the vertical alignment of the road has to be raised above the level of the existing ground either to satisfy design geometric standards or to prevent damage by surface or ground water. Most embankments are low, between 0.5m to 1.5m high; heights of 5m or more may, however, be used on major highways. Wherever an embankment is required, the following factors will affect its design and cost: Foundation conditions Acceptable fill material Slope stability Placing and compaction of fill 4.2.1 Foundation Conditions The residual soils widespread in Kenya are not usually compressible and any settlement that does occur is likely to be substantially complete by the time the embankment is constructed. Nevertheless, when an embankment has to be built on wet, compressible soil, such as soft clay, detailed investigations are necessary to determine the most suitable construction method, the rate of construction and any special measures required. Usually, either the soft clay is removed and replaced with coarse rockfill or it is substantially consolidated before the road pavement is constructed. The consolidation will involve either pre-loading with a higher (heavier) embankment or the installation of vertical sand drains or a combination of both. Normally 90% consolidation will have to be achieved before placing the pavement layers. If the consolidation option is chosen, the rate of dissipation of construction pore pressures in the soft, saturated foundation material must be investigated and a suitable construction rate decided. This is very important, especially if a high pre-loading embankment is proposed, in order to avoid a shear failure during construction. Even if the proposed embankment is only a few metres high, a full geotechnical investigation is necessary to determine the magnitude and rate of settlement and the likely pore pressures generated during construction. Piezometers can be installed in the foundation material to determine its pore pressures, enabling faster safe rates of construction if the forecasts have been pessimistic or to prevent failure if optimistic. Conventional oedometer consolidation tests using specimens of undisturbed samples from the horizontal plane normally give accurate predictions of the amount of settlement for a layer of soft, saturated clay loaded by an embankment. However, the time of settlement predicted by this method is usually much longer than in practice because in most normally consolidated clays the drainage path in the horizontal direction is many times more permeable than in the vertical direction. Oedometer tests with specimens cut from undisturbed samples from the vertical plane will give an accurate prediction of time of settlement under an embankment load. The Republic of Kenya – Ministry of Roads 29 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 4.2.2 Acceptable fill material Almost all material types, from sandy clays to broken rock, can be used for embankment construction, the main limitation being the ease with which they can be handled and compacted. Usually, the material will be obtained from cuttings or borrow pits close to the embankment. Material of low plasticity is preferred because it will pose fewer problems in wet weather. If more plastic material is used, it must be shaped and compacted quickly so as to shed rain water. If the embankment is higher than 6 metres it is desirable to reserve material of low plasticity for the lower layers. Materials generally unacceptable for fill are as follows: containing more than 5% of organic matter, such as topsoil, swamp material, wood etc having a swell of more than 3%, such as black cotton soil having a plasticity index more than 50: however, some residual red clays with a PI > 50 may successfully be used. These soils, when compacted in embankments to a greater density than found in situ, develop considerable shrinkage and suction forces associated with seasonal wet and dry periods. These forces are large and can give rise to longitudinal cracks to repeatedly be formed through to the surface of any road pavement containing rigid or semi-rigid layers. having a moisture content greater than 105% of the optimum moisture content of BS Light (AASHTO T99), and having a CBR < 2% Embankments have nevertheless been constructed with these ‘unacceptable’ materials, eg Embakasi near JK International Airport. Special precautions, described in Chapter 11, are then required. A fully flexible pavement will be the most suitable on these embankments but if rigid or semi-rigid layers are necessary (lean concrete, concrete, cement or lime stabilized gravels), the problem of cracking may possibly be overcome by incorporating a layer of polythene sheet at the top of the subgrade earthworks and laying a thin layer of sand or crushed fines, before the subbase. Rockfill can be used providing that boulders no greater than 0.2m3 (600mm size) are used and that this material is not placed within 600mm of formation level. If it is possible the best materials, either from cuttings or borrow pits, should be reserved for the upper layers of fill. 4.2.3 Slope stability Side slopes for embankments up to 8m height, resting on non-saturated soils, are normally constructed between 1:1.5 and 1:3, (vertical:horizontal) as follows: Table 4.2 Slope Angles for Embankment Materials Material Sands, cohesionless Other materials Recommended slope angle, vertical:horizontal 1:3 if height ≤ 1m 1:2 if height > 1m 1:3 if height ≤ 1m The Republic of Kenya – Ministry of Roads 30 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 1:2 if height >1 but < 3m 1:1.5 if height >3 but < 10m Embankments higher than 10m or founded on soft, wet materials should be subject to individual specialist analysis. 4.2.4 Placing and compaction of fill Compaction increases the density of a material by expelling air from the voids and bringing the individual particles in closer contact. This increases the shear resistance and reduces settlement. Therefore, soils in embankments and cuttings are usually compacted using special equipment, such as rollers, tampers and vibrators; and the success of compaction depends on the soil type and in situ moisture content, the type of compaction equipment and the energy applied. It is therefore essential that laboratory tests are carried out beforehand to determine the dry density/moisture content characteristics of the candidate soils and to define the achievable densities. Uniformity of compaction is of prime importance in preventing uneven settlement. Although some settlement can be tolerated, it must be minimized, especially on the approaches to bridges and culverts where adequate compaction is essential. For construction on level ground, all soft and organic material must be removed and hollows filled to obtain a level surface to receive the fill. Any backfilling required to achieve a level surface shall be compacted to a dry density equivalent to 93% of BS Heavy (AASHTO T180), corresponding to about 100% of BS Light. For construction on sloping ground, where the slope is greater than 1:3 (vertical:horizontal), horizontal benches shall be cut into the sloping ground. Immediately on completion of this operation, the whole of the area to receive the fill shall be compacted to 93% of BS Heavy (AASHTO T180) to a depth of 150mm. The time between preparing the area and placing the fill shall be kept to a minimum to conserve the moisture. Fill shall normally be placed in layers of compacted thickness up to 250 mm. Thicker layers may be permitted only where trial sections have proved that the required compaction can readily be achieved over the full layer depth. The minimum layer thickness shall be twice the maximum particle size of the fill material. Normally, the layers of fill material shall be compacted throughout to a minimum of 93% of BS Heavy (AASHTO T180), except for the uppermost 150mm which shall be compacted to a minimum of 95% of BS Heavy (AASHTO T180). The British Standard Vibrating Hammer Test, BS 1377, Part 4 (1990) shall be used for noncohesive soils and a minimum level of 93% of maximum density shall be specified for the lower layers and a minimum of 95% of maximum density for the upper layers. For very high fills, higher compaction may be required to minimize settlement. The moisture content of the material shall be adjusted so that the above specified compaction levels are attained. In situ moisture contents below the Optimum Moisture Content of BS Heavy can be accepted, provided that the compaction equipment and method are sufficient to achieve the specified compaction level. In arid areas, compacting the The Republic of Kenya – Ministry of Roads 31 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement material in a very dry state can be effective and economical. However, research has shown that dry-compacted material has more air voids than the equivalent material compacted at the optimum moisture content and can be loose even at high density, needing to be confined. Nevertheless, dry-compacted non-plastic materials have given good performance in the arid areas on N Kenya. Normal laboratory compaction tests cannot be accurately carried out on materials containing a high proportion, approximately 25% or more, of particles greater than 40mm size. On such materials the minimum density and appropriate moisture content required shall be determined from site compaction trials. In the UK compaction requirements are usually specified by means of a method specification which eliminates the need for in situ density tests. Where fairly homogenous materials are used, the compaction requirements may consist of a method specification with the parameters being fixed after full scale compaction trials: Maximum thickness of compacted layer Characteristics of the compacting equipment Number of passes for each roller The permissible range of moisture content When rockfill is used it shall be placed at the bottom of the embankment. The largest sizes of rock shall be placed in layers of maximum compacted thickness of 1m. The interstices shall then be filled with smaller rocks, spalls and approved finer material. The whole layer shall be compacted until the interstices are completely filled or until the required settlement is obtained. Heavy vibratory rollers are generally the most suitable machines for compacting rockfill. It is most important that the specified compaction is achieved over the whole width of the embankment. Loose material left on the slopes may absorb water and endanger the stability of the slopes. The Republic of Kenya – Ministry of Roads 32 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 5 Drainage and Erosion Control 5.1 Drainage of Surface Water This chapter deals with the drainage of surface and ground water, and methods of protecting slopes and ditches from erosion. Cross drainage (culverts) is dealt with in Part VI of the Road Design Manual (Bridge Design). 5.1.1 Side Ditches The design of these ditches is covered in Part I of the Road Design Manual (Geometric Design of Rural Roads) where standard cross sections for different terrain and gradient/capacity curves are given. 5.1.2 Cut Off Ditches It is usually desirable to construct a cut-off ditch at the top of cutting slopes to prevent water flowing down the face. The preferred type, consisting of a combined ditch and bank, is detailed in Part 1 of the Road Design Manual (Geometric Design of Rural Roads). The moderate slopes of 1 vertical: 2 horizontal used in this document have been chosen to allow the inevitable movement of pedestrians and livestock with as little damage to the ditch as possible. 5.1.3 Discharge Channels Depending on topographic conditions it is sometimes necessary to collect water at the top of either a cutting or an embankment and discharge it down the slope. For this purpose discharge channels shall be constructed and lined with masonry, concrete or metal. The usual dimensions are 400 mm wide by 400 mm deep. If half-round channel elements are used the diameter should normally be 500 mm. 5.1.4 Collection of Water in Embankments On embankments, where water is to be discharged down the side slopes in discharge channels, it is necessary to lead all water to the tops of these channels. This can be achieved by some form of kerbing or a recessed channel. The kerbing can be formed from masonry, precast concrete units or in-situ concrete. The channel can be formed from precast concrete or metal channels, with an internal diameter in the range 300 to 400 mm. For safety reasons these features should be placed outside the edge of the surfacing. Where a crash barrier is installed the kerbing or channel should be installed immediately in front of the supports, on the traffic side. The Republic of Kenya – Ministry of Roads 33 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 5.1.5 Embankment Toe Ditches At the base of embankments, toe ditches may be necessary to remove water from the vicinity of the embankment or to prevent erosion of the fill. They shou1d be designed on similar principles to side ditches mentioned in Section 5.1.1 above. 5.2 Drainage of Ground Water Ground water may be encountered in the following situations: in cuttings, a water table with a level above or near formation, or springs, and in low-lying or poorly drained flat areas, a water table near formation, likely to affect the subgrade by capillary rise. 5.2.1 Drainage Remedies 5.2.1.1 Choice of proper alignment The best expedient for the prevention of drainage problems is carrying out a proper survey of the areas concerned and selecting both vertical and horizontal alignments so that the formation is as far away as practicable from water tables and springs. In particular, in lowlying or poorly drained areas, it is necessary that the road be raised by means of an embankment to avoid surface flooding. 5.2.1.2 Subsoil drains Longitudinal subsoil drains can be used to lower a water table. These will normally consist of porous concrete, open jointed or perforated pipe laid in a trench with a surround and backfill of free-draining material, e.g. graded crushed stone (maximum size : 60 mm), clean coarse gravel or sand. The pipe size will depend on the expected flow of water but will generally not be less than 100 mm internal diameter. The depth of the trench will depend on the level of the water table and the permeability of the soil but normally it should be at least 1metre deeper than the formation level and 500 mm wide. In some cases where it is necessary to prevent surface water from entering subsoil drains, the upper 500 mm of the trench shall be backfilled with impermeable clayey material. If the surrounding ground is likely to squeeze or wash into the free-draining material, filter protection is required. This can be achieved by placing filter material as free-draining material in the trench. Filter materials shall comply with the following requirements: 5*S15<F15<5.S85 Where: F15 is the sieve size, in mm through which 15% by weight of the filter material passes. S15 is the sieve size, in mm through which 15% by weight of the natural soil passes. The Republic of Kenya – Ministry of Roads 34 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 585 is the sieve size, in mm in which 85% by weight of the natural soi1 passes. It is important that the pipe be surrounded by filter material to prevent fines from clogging the openings. A non-woven gee-fabric of an approved type may be placed around the draining material to prevent silt or fine particles from being washed into it. It may also be useful to place nonwoven gee-fabric around the pipe. The effective pore size of the fabric should comply with the above filter criteria. Where the flow of water is small and where non-woven geo-fabric is placed around the draining material, it may be unnecessary to place a pipe. Where pipe drains are used, inspection chambers with silt traps shall be constructed every 100 m along straight sections and at every change in direction. These will enable the pipe to be rodded or flushed out. 5.2.1.3 Blanket drains Blanket drains are used to remove seepage water appearing in the base of cuttings or in the subgrade. The blanket shall consist of a filter layer in contact with the soil, and a coarser collector layer. Non-woven gee-fabric may also be used, to prevent fines from blocking the draining layer. Protection by filter layers or non-woven geo-fabric may be required on both sides of the blanket drain. 5.2.1.4 Seepage Remedies If during construction unanticipated local seepages or springs are encountered in cuttings they may be controlled by either a counterfort drain or sub-horizontal well. In it simplest form a counterfort drain consists of an excavated “slot” or deep trench running into the cut slope, which is then backfilled with free-draining material and in large cases a porous pipe. The filter criteria already stated will apply and some arrangement must be made to lead away the intercepted water. Geo-fabric can also be used as already described. Sub-horizontal wells are formed by drilling into the cut slope at a slight upward angle to intercept water-bearing strata. The hole is then lined with a slotted or perforated pipe to keep it open and to carry the water out. Usual diameters range from 50 to 100 mm and lengths may reach 50m. 5.3 Erosion Control Erosion problems may occur on the side slopes of embankments or cuttings, gravel shoulders or at any other point where surface run-off concentrated or a spring occurs. The obvious remedies are therefore well-designed surface and sub-surface drainage features and appropriate slope angles for the soils and rocks present. This last measure is problematic as there is no standard test to assess “erodibility”. The best guidance would be obtained from observations of actual road sections, assuming these exist. The Republic of Kenya – Ministry of Roads 35 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Various surface protection systems can be used in conjunction with the above. 5.3.1 Protection of Slopes 5.3.1.1 Topsoiling and Grassing Sprigs of indigenous “runner” type, grass may be planted on slopes by one or two methods: The slope shall be covered with a layer of fine topsoi1 free of stones greater than 50mm. The minimum thickness should be 75mm. The layer shall then be planted with grass Sprigs of grass shall be planted at approximately 200 mm centres in pockets of topsoil, 75 mm deep. Planting should be carried out at the beginning of a rainy season. 5.3.1.2 Surface treatments with seeds and fertilizers When difficulties are anticipated in establishing a healthy growth of grass on a sterile soil, a mixture of grass seeds and fertilizer may be applied. This can be done either as a wet or dry process. In the former process grass seed, fertilizer, mulch material and water are mixed to form slurry which is then sprayed onto the ground. In the dry process grass seed and fertilizer are mixed and applied to the ground, followed by watering and possible application of mulching material. 5.3.1.3 Gravel or stone blanketing Erodible materials may be protected by placing coverings of gravel or stone blankets. The blanketing material should have a maximum size of 40 mm and he placed in an even layer of at least 75 mm. 5.3.1.4 Fascines Placing fascines or branches over the most vulnerable areas, generally combined with some form of grass planting, will help stabilize the slope until it is covered by grass or other vegetation. 5.3.1.4.1 Serrated slopes Serrated slopes aid in the establishment of vegetation. Serrations may be constructed in any material that is rippable or that will hold a vertical or subvertical face for a few weeks, until vegetation becomes established. 5.3.1.4.2 Other protective works More costly types of protection, such as stone pitching (possibly grouted), gabions, masonry or placing of concrete may also be used, but, in general, they are economically justified only where the overall slope stability has to be improved. The Republic of Kenya – Ministry of Roads 36 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 5.3.2 Protection of Ditches and Channels 5.3.2.1 Critical Length of unlined ditches The critical length of unlined ditches must be determined, with regard to erosion control. The critical length is defined as the maximum length of unlined ditch, in which water velocities do not give rise to erosion. The maximum velocity of water can be calculated from the slope, shape and dimensions of the ditch, volume of water and from the roughness coefficient of the material. Knowing the maximum permissible velocity for each type of material, the maximum length of ditch in this material can then be determined. The recommended maximum permissible velocities for different types of material are as follows: Table 5.1: Maximum velocity of water flow Material Max. permissible velocity (m/s) Fine sand Silt – Coarse sand Silty Clay – fine gravel Stiff clay Coarse Gravel Soft rock – Conglomerate Hard rock – Masonry - Concrete 0.3* 0.4 – 0.6* 0.5 -0.8* 0.9 – 1.3 1.2 – 1.7 1.8 – 2.5 3.0+ 5.3.2.2 *Where the materials are grassed, the maximum permissible velocity is of the order of 1.5 m/s if a good cover is provided and 1.1m/s if a sparse cover is provided. Methods of protection Sections of ditch beyond the critical length must be protected from erosion by lining. The following methods may be used: Grassing Turfing Stone pitching (possibly grouted) Placing of masonry Concreting Reducing the gradient and constructing steps (the steps must be paved) Placing velocity breakers 5.3.2.3 Sedimentation Control If water velocities are too low sedimentation may occur. Ditches and drains should therefore be given sufficient gradient everywhere, in so far as topography and erosion control will permit. Sedimentation velocities for a few types of material are approximately the following: Silt Fine sand Coarse sand Fine gravel Gravel 0.08 m/s 0.15 m/s 0.20 m/s 0.30 m/s 0.65 m/s The Republic of Kenya – Ministry of Roads 37 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 6 Subgrade The aim of the design process is to protect the bearing capacity of the in situ subgrade material in order that the road pavement will be able to fulfill its service objective over the design period. The bearing capacity and quality of the subgrade (or roadbed or fill) is of prime importance in the selection of pavement type and is improved by overlaying it with layers of material to achieve an integrated and structurally balanced system. 6.1 Subgrade Classes For practical purposes the design subgrade bearing capacity or strength is expressed as the ‘California Bearing Ratio’, or CBR, in line with general practice. It has been proved for Kenyan soils that there is good correlation between the CBR and the elastic modulus. A survey of Kenyan subgrade soils showed that they can be grouped into six bearing capacity classes, S1 to S6, shown in Table 6.1, corresponding to values obtained on materials of the same type along homogeneous sections of road. The CBR range reflects natural variations in the soil and the normal scatter of test results: Table 6.1: Subgrade Classes Soil Class CBR Range S1 S2 S3 S4 S5 S6 2 3 to 4 5 to 7 8 to 14 15 to 29 30+ Modulus, MPa (of median value) 15 25 50 80 125 >250 Notes: 1. No accommodation for CBR values < 2 has been made, because it is inappropriate to lay a pavement on soils of such poor bearing capacity. Such weak soils are saturated expansive clays, saturated fine silts or compressible (swampy) soils, e.g. mud, soft clay, etc. These materials will, where possible, either be improved by chemical or/and mechanical stabilization and re-classified; or they will be removed and other cover applied. 2. The use of S1 soils as direct support for the pavement should be avoided and, where practicable, such poor quality soils should be excavated and replaced, or improved, or covered with an improved subgrade. 3. The CBR range of S5 is fairly wide. This is because Class S5 is either gravelly material or unsoaked soil, the CBR values of which always show considerable scatter. Furthermore, the difference in the pavement thickness required is comparatively small when the subgrade bearing strength varies from the lower to the upper limit of this Class. The Republic of Kenya – Ministry of Roads 38 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 4. S6 covers all subgrade materials having a CBR > 30 and which comply with the plasticity requirements for natural materials for subbase. In such cases, no subbase is required. No class of higher bearing capacity has been considered as such natural subgrade materials are rare and as a roadbase is always necessary to provide a homogeneous and uniform layer. However, the reconstruction of roads sometimes results in a new structure being constructed on an old road, the surface of which is considered as subgrade and whose residual strength is often considerably greater than CBR 30. 5. Where the subgrade CBR values are very variable the designer should balance the cost of having very short sections of different subgrade categories against a conservative design taking account of the worst conditions encountered over longer sections. 6.2 Classification of Kenyan Subgrades The materials listed in Table 6.2 cover almost all the natural subgrade materials found in Kenya, classified according to bearing strength: Table 6.2: Kenyan Natural Subgrades Bearing Strength Class After 4 days At OMC soak (BS Light ) Black cotton soils S1 S5 Micaceous silt (weathered rock) S1 S3 Other residual silt (weathered rock) S2 S4 Red clays (coffee soils) S3 S5 Sandy clays from volcanics S3/S4 S5 Ash and pumice* S3/S4 S5 Silty loam from gneiss or granite S4 S5 Calcareous sandy soil S4 S5 Sandy clay on PreCambrian basement S4 S5 Clayey sand on PreCambrian basement S4/S5 S5/S6 Dune sand S4 S4/S5 Coastal sand S4 S5 Weathered lava S4/S5 S5/S6 Quartz gravel S4/S6 S5/S6 Soft weathered volcanic tuff S4/S6 S5/S6 Calcareous gravel S4/S6 S5/S6 Laterite gravel S5/S6 S6 Coral gravel S5/S6 S6 1. Material Type * The ash and pumice soils tend to have a low field density, thus a correspondingly very low maximum dry density than anticipated from the measured CBR value. Such soi1s, with a Standard Compaction MDD less than 1.4 mg/m³ should not be used in construction unless improved. The Republic of Kenya – Ministry of Roads 39 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 6.3 Determining the Subgrade Strength 6.3.1 Recommended Subgrade CBR Test Procedure The strength of the subgrade depends on the type of material, its density and the prevailing moisture content. For each type of material, it is therefore necessary to determine the relative compaction that could be obtained in-situ and the maximum moisture content likely to occur in the subgrade. In order to obtain a complete knowledge of the relationship between density, moisture content and CBR, a “6 point” CBR test should be carried out on a representative sample of each type of subgrade material encountered. The tests are conducted in the following way: The material shall be compacted at 3 different levels of compaction. The samples shall be prepared at the moisture content expected at the time of field compaction. At each level of compaction, one CBR shall also be measured on one soaked specimen. The time of soaking will depend on the anticipated wettest conditions. The amount of water absorbed during soaking and the eventual swell shall also be measured. The above method enables an estimate to be made of the subgrade CBR at different densities and thus helps in determining the relative compaction required. It also indicates the loss of strength which soaking may cause. A full particle size analysis should also be done on each representative sample. 6.3.2 Subgrade Compaction Requirements The upper 150mm of the subgrade shall be compacted to a dry density corresponding to a minimum of 95% of BS Heavy (or AASHTO T180). The lower 150mm shall be compacted to a minimum of 93% of BS Heavy, equivalent to about 100% of BS Light (or AASHTO T99) These criteria apply to cuttings where there is no improved subgrade, and on all embankment fills. In cuttings where an improved subgrade is placed, the upper 150mm of the cutting surface material, prior to placing the improved subgrade layer(s), shall be compacted to a minimum of 93% of BS Heavy and the lower 150mm to a minimum of 90% of BS Heavy, equivalent to about 95% of BS Light. All improved subgrade, compacted to a dry density of 95% of BS Heavy, shall have a minimum soaked CBR of either 7% or 15%, as described later in this Chapter. The British Standard Vibrating Hammer Test, BS 1377, Part 4 (1990) shall be used for noncohesive soils and a minimum level of 93% of maximum density shall be specified for the lower layers and a minimum of 95% of maximum density for the upper layers. The maximum compacted thickness which shall be laid at one time is generally 200 mm. The moisture content shall be adjusted if possible in order that the required relative compaction is obtained, and at the time of compaction it shall not exceed 105% of the Optimum Moisture Content of BS Heavy. The Republic of Kenya – Ministry of Roads 40 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Dry compaction may be possible in arid areas with gravelly or sandy materials but research in N Kenya has shown that they remain loose even at target densities and need to be confined (by the pavement layers). Dry compaction of clays is not normally satisfactory because the swell of such materials is abnormally high when allowed to absorb water. It is advantageous to obtain relative compactions higher than the above figures, since compaction not only improves the subqrade bearing strenqth, but also reduces permeability. Increasing the subgrade bearing strength provides a better platform for the construction of the pavement layers. This applies, in particular, to clayey sands, silty sands and granular materials, the coarse particles of which are hard and do not crumble under heavy compaction. 6.3.3 Estimating the Subgrade Moisture Content The moisture content of the subgrade soil under the road pavement at any given time will depend on the following factors: local climate depth of the water table type of soil topography and drainage permeability of the pavement materials permeability of the shoulders A study of Kenyan subgrade moisture conditions revealed the general relationships between mean annual rainfall, soil type, drainage conditions and subgrade moisture content which are given in the Table below. Table 6.3: Relation between rainfall, soil type and subgrade moisture Mean Annual Rainfall, mm > 500 (‘Wet’) < 500 (‘Dry’) Water Table Soil Type Deep Clays Silts Drainage Subgrade Content or Impermeable pavement, reasonable surface drainage Permeable pavement, poor surface drainage Deep or Sands or none sandy clays Moisture Averages less than OMC; maximum 3% > OMC Often exceeds OMC; maximum saturated Well below OMC; maximum equal to OMC Note: 1 OMC at BS Light (AASHTO T99) 2 Permeable pavements are pavements constructed with open-textured materials or deteriorated pavements showing surfacing and/or base cracking 6.3.4 Determining the Subgrade Design Strength In the absence of a direct and accurate evaluation of the ultimate subgrade moisture content, the subgrade strength shall be determined as follows: The Republic of Kenya – Ministry of Roads 41 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement if the mean annual rainfall is more than 500mm, subgrade strength shall be determined from the 4 day soaked CBR at the specified compaction level of BS Heavy (AASHTO T180. In saturated conditions it may be necessary to adopt the OMC of BS Light (AASHTO T99) compaction if the mean annual rainfall is less than 500 mm, the subgrade strength may be determined as the CBR at the OMC of BS Heavy. However, such a design shall only be permitted only where it has been established that no prolonged soaking may occur and, for this purpose, consideration shall also be given to factors such as permeability of the natural ground and the topography, ie the ability of water to drain rapidly under all circumstances. 6.4 Subgrade Requirements for Pavement Design 6.4.1 Materials Suitable for Pavement Support Materials directly supporting the pavement shall normally comply with the following: CBR ≈ 15% at specified compaction, normally 95% of BS Heavy (AASHTO T180) Swell < 2% at 100% MDD (Modified Compaction) and 4 days soak Organic matter < 3% (percentage by weight) Thus, all situations where the natural subgrade is S4 or less will require placement of an improved subgrade. The nature and arrangement of the improved subgrade will depend on the CBR of the natural subgrade and the available materials but the intention is to reinforce the natural subgrade with improved subgrade layers of CBR 7 and CBR 15 in the manner described graphically in the catalogues presented in Chapter 9. Class S1 soils (CBR 2 or less) will thus either require stabilization or removal and replacement with better quality material. Class S5 (CBR 15 to 29) and S6 (CBR 30 or more) soils will not require an improved subgrade. 6.4.2 Improved Subgrade Placing an improved subgrade not only increases the bearing strength of the pavement support but also: protects the upper layers of earthworks against adverse weather conditions (protection against soaking and shrinkage), facilitates the movement of construction traffic, permits more effective compaction of the pavement layers, reduces the variation in the subgrade bearing strength, and prevents pollution of open-textured sub-bases by plastic fines from the natural subgrade. The Republic of Kenya – Ministry of Roads 42 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 6.4.3 Lime Treated Subgrade Treatment of subgrade soils with lime is encouraged because otherwise they may have to be removed and disposed. It may be effective in the following cases: where the soils are excessively clayey and no better material is economically available; treatment with hydrated lime may be a cost-effective solution. where the soils are excessively wet and cannot expeditiously be dried out; treatment with quicklime may allow construction to proceed and provide a markedly stronger subgrade. Specifications for lime treatment are given in Chapter 7. The Republic of Kenya – Ministry of Roads 43 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 7 Pavement Materials Pavement materials consist of subbases, bases and surfacing. Recommendations for their properties are described below. 7.1 Subbases The functions of the subbase are to act as a construction platform for the upper pavement layers and as a separation layer between the subgrade and the roadbase. In certain circumstances it may also act as a drainage layer, especially in concrete roads. The selection of a suitable subbase material will, therefore, depend on the design function of the layer and the anticipated moisture conditions, both at construction and in service. 7.1.1 Natural Materials Natural materials in Kenya suitable for subbases can be lateritic, quartzitic or calcareous gravels, some forms of soft stone, coralstone (on the coast), clayey and silty sands, and conglomerate. When used as subbase they shall invariably have low plasticity and should comply with the other requirements in Table 7.1. Table 7.1: Subbase: natural materials: specifications Material Properties CBR,%, 4 Swell Atterberg Limits (KS 999: Part 2) LL, max %3 PI, max %, or LS, max % Grading Modulus2 Particle Size Field density Layer restrictions Notes: 1. 2. 3. 4. Material Class Min 30 (soaked) Max 1% at BS Heavy General material Coral gravel Wet1 Dry Wet Dry 45 50 45 55 16 20 18 24 8 10 9 12 Min 1.2 Max size: ⅔ of compacted layer Min 95% of BS Heavy Min thickness compacted layer: 100mm Max thickness compacted in one layer: 200mm ‘Wet’ and ‘Dry’ refers to rainfall zones corresponding to >500mm and <500mm per year respectively Grading Modulus is [300-(% passing 2mm)-(% passing 0.425mm)-(% passing 0.075mm)]/100 Atterberg Limits: LL, Liquid Limit; PI, Plasticity Index; LS, Linear Shrinkage CBR values measured at specified field density (normally 95% of BS Heavy) Materials derived from weathered igneous rock, particularly basic rocks like basalt, phonolite and dolerite, which are common in Kenya, often contain decomposed minerals and can be of very poor quality. Their use should be avoided if possible; at least before using for the first time they should be subject to a petrographic analysis by a specialist to determine the proportion of weathered minerals. If the proportion of weathered minerals is greater than 50% they should definitely be avoided. Weathered micaceous rocks, such as schists and some gneisses, are likely to give rise to similar difficulties. ‘Soft stone’ can also be used for subbase. A poor quality soft stone shall be assessed and used in accordance with the requirements for natural gravel. The Republic of Kenya – Ministry of Roads 44 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 7.1.2 Graded Crushed Stone Graded crushed stone may be used as subbase material where no suitable natural gravel can be found. The material requirements, traffic limitations and construction procedures are summarized in Table 7.3. It shall comply with the following criteria: Table 7.2: Graded Crushed Stone: Specifications for Subbase Material Properties Compaction, Vibrating hammer SG of compacted layer Stone cleanliness Stone toughness Stone durability Stone particle shape Grading, sieve size, mm 75 63 50 37.5 28 20 10 6.3 2 1 0.425 0.075 Particle Size Compaction moisture content Layer restrictions Material Class GCS2 Average 96% of MDD No result < 94% of MDD Average dry density min 82% of SG No result < 80% of SG SEV (AASHTO T176) min 30 PI max 6 (wet area): max 8 (dry area) ACV max 32, or TFV min 90 (dry) and 70(wet) Water Absorption max 2% (if in doubt then max Mg2SO4 Soundness 18%; KS 1238-20) Flakiness Index max 35% Envelope 0/40 Envelope 0/60 100 95-100 100 85-100 90-100 75-95 75-95 60-87 60-90 50-80 35-75 30-67 25-63 23-58 15-45 13-40 8-35 7-32 4-23 4-20 0-12 0-10 Max size shall be ⅔ of compacted layer Between 80-105% of OMC (Vibrating hammer) Min thickness compacted layer: 100mm (0/40); 150mm(0/60) Max thickness compacted in one layer: 200mm ‘Crusher-run’ should be used as much as possible; the grading envelopes given cover the crusher-runs usually obtained. For softer stones a grading at the design stage which is coarser than the envelope may be acceptable. Material shall consist of crushed stone, free of clay, organic and any other deleterious material Grading after compaction shall be considered: compaction may cause further crushing and produce additional fines in the case of soft stone The Republic of Kenya – Ministry of Roads 45 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Generally, the fines (% passing 0.425mm sieve) shall be only slightly plastic: in dry areas, the plasticity may be further relaxed (PI<8) Graded crushed stone should always be kept moist during handling, transporting and laying and should not be stockpiled in heaps higher than 5 m, in order to avoid segregation Care must be taken to ensure that the layer edges are properly compacted No visible movement under a steel wheeled roller applying at least 5000 Kg/metre width of roll. 7.1.3 Stabilised Natural Materials Natural gravels, sands and clayey sands, which do not meet the subbase requirements given in Table 7.1, may be stabilised with cement or lime. The choice of stabilizer depends on the percentage of fines (material passing 0.425 mm sieve) and the PI; reference is made to Section 7.2.3, Table 7.4. The materials suitable for stabilisation and the stabilized material shall comply with the criteria given in Table 7.5, category CS. Curing shall be carried out by covering the surface with approved plastic sheeting, moist soil, straw and/or keeping the surface damp by frequent applications of a light spray of water. 7.1.3.1 Cement bound granular subbases These materials are intended to perform as rigid monolithic pavement layers to increase the dynamic stiffness of the pavement. For traffic classes T6 and T7 a DBM base is required: this is a rigid layer which needs a rigid layer to be constructed on, otherwise it will break. Typically, they are graded crushed stone, conforming to the requirements in Table 7.3, to which is added 2% to 3% cement in a plant mixer. The strength of this material should conform to CB1 or CB2 in Table 7.6. 7.2 Bases The main function of the base is to act as the load-spreading layer of the road pavement. Therefore, only strong materials will be suitable. Bases fall into two categories: unbound and bound. Unbound bases, such as natural gravels and crushed stone, rely on their intrinsic internal friction to develop the necessary bearing capacity. Bound bases have a binder, either bitumen or cement or lime, which is used to strengthen them and enhance their ability to reduce the traffic stresses on the layers below. 7.2.1 Natural gravel Natural gravels meeting the requirements in Table 7.3 are very scarce in Kenya. Lateritic gravels are not suitable owing to their poor nodule hardness and high plasticity. Weathered rocks are of even poorer quality. Only quartz gravels and coral gravels are potentially satisfactory. It may be advantageous to stabilize them mechanically, by mixing in sand to reduce the plasticity, or stone (crushed or not) to provide hard, coarse, angular particles. An addition of up to 30% of sand or stone is regarded, practically and economically, as a maximum. The Republic of Kenya – Ministry of Roads 46 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Normally the specified field compaction will be 95% of BS Heavy: in practice, compaction up to 97% of BS Heavy may be considered. However, the bearing strength will be significantly increased by higher compaction only if the coarse particles are hard enough to resist heavy compaction without being crushed or pulverized. Natural gravels are suitable only for Traffic Classes T1 to T5, for they are prone to attrition and their properties are too variable. Table 7.3: Specification for Natural Gravel as Base Material Properties CBR,%, at specified field density Swell Atterberg Limits Particle Strength Grading, sieve size, mm 50 37.5 28 20 10 5 2 1 0.425 0.075 Field Density Layer restrictions Material Class Min 80 Max 0.5% at BS Heavy General Coral gravel LL max 30 LL max 35 PI max 8 (LS max 4) PI max 10 (LS max 5) PM max 90 ACV max 35, or TFV min 75 (dry) and min 50 (wet) Envelope 0/40 100 95-100 80-100 60-100 35-90 20-75 12-50 10-40 7-33 4-20 Min 95% of MDD BS Heavy at 80-105% OMC Min thickness compacted layer: 125mm Max thickness compacted in one layer: 200mm 7.2.2 Graded Crushed Stone Graded crushed stone (GCS), either basaltic rock, gneiss or granite, is the most widely used base material in Kenya. Recommended specifications are presented in Table 7.4: Table 7.4: Crushed Stone Specifications for Base Material Properties Compaction, Vibrating hammer, KS 999-4 SG of compacted layer Stone cleanliness Stone toughness Stone durability Material Class GCS1 Average 98% of MDD No result < 96% of MDD Average dry density min 85% of SG No result < 82% of SG SEV (AASHTO T176) min 30 Fines non plastic ACV max 30, or TFV min 110 (dry value) and 75(wet value) Water Absorption max 1% The Republic of Kenya – Ministry of Roads 47 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Stone particle shape Grading, sieve size, mm 50 37.5 28 20 10 6.3 2 1 0.425 0.075 Particle Size Layer restrictions Part 3 - Materials and Pavement (if doubt then max Mg2SO4 Soundness 18%: KS 1238-20) Flakiness Index max 30% 0/20 0/30 0/40 % passing % passing % passing 100 100 90-100 100 90-100 75-95 90-100 65-95 60-90 60-75 40-70 40-75 40-60 30-55 30-63 30-45 20-40 20-45 15-30 15-32 15-35 13-27 10-24 10-26 4-10 4-10 4-12 Max size shall be ⅔ of compacted layer Min thickness compacted layer: 125mm Max thickness compacted in one layer: 200mm GCS is not considered suitable for Traffic Classes T6 or T7 For Traffic Class T5 the GCS must be entirely crushed: for T4 and lower the GCS may be semi-crushed The grading generally required is 0/40 mm but for T4 and T5 a finer grading is required in order to minimize segregation and provide sufficient stability GCS should always be kept wet during handling, transporting and laying and should not be stockpiled in heaps higher than 5 m, to avoid segregation. Special care must be taken to ensure that the layer edges are always properly compacted, by providing an extra width or specific lateral abutment Adding material from another source to achieve the grading is permissible providing it is passing 5mm sieve, a maximum content of 15%, non plastic and free of deleterious material 7.2.3 Stabilized materials 7.2.3.1 General Since there is an indigenous cement and lime industry in Kenya, it can be advantageous to treat otherwise unsuitable natural materials with cement or lime. It will be only appropriate, however, when the cost of the treatment is less than the cost of the removal of the unsuitable material plus replacement by suitable material. Stabilization enhances the properties of road materials in the following ways: retention of strength when saturated with water increased resistance to erosion increased effective elastic moduli of the layers above the stabilized layer Possible problems are associated with these desirable effects: environmental and traffic stresses can cause stabilized layers to crack cracks can reflect through the surfacing allowing water to enter the structure The Republic of Kenya – Ministry of Roads 48 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement the stabilization reactions are reversible if the stabilized material is exposed to the atmosphere, resulting in decrease in the strength of the stabilized layers the stabilization procedure requires skill; for instance, the operation must be carried out relatively quickly, especially with cement stabilizer, and the resulting mixture of the stabilizer and natural material must obviously be as homogeneous as possible. The balancing of these advantages and disadvantages generally limits the amounts of admixed stabilizer to between 2% and 6%. There is a significant difference between improved materials and stabilized materials. Improvement consists of treating materials with a small amount of lime (and cement sometimes) in order principally to reduce the plasticity and improve the engineering characteristics. Stabilization consists of treating materials with a sufficient amount of lime or cement, so that their bearing capacity is significantly increased. Some soils do not stabilize well. Soils containing more than 1% of organic matter are one example. Also, if montmorillonite is present amongst the clay minerals, its large volume changes with changing moisture content may disrupt the stabilized soil. An indication of the suitability of the soil for stabilization is provided by the Initial Consumption of Lime test (BS 1924 1990) which determines the amount of lime, or cement, required to complete the neutralizing reactions and initiate the stabilizing reactions whereby strength-forming calcium silicates and aluminates are progressively created. Normally, the amount of stabilizer used in the contract is the ICL value + 1%. Soils containing >0.3% of sulphate should be avoided for stabilization as there have been instances of deleterious reactions between the sulphate and the strength-forming calcium silicates and aluminates. 7.2.3.2 Choice and Quality of Stabilizer The choice of stabilizer depends on the plasticity of the natural material, see Table 7.5: Table 7.5: Choice of Stabiliser % Passing 75µm sieve Less than 25%*** More than 25% PI < 6, or PI x (% passing 75µm) < 60 6 to 10 > 10 < 10 10 to 20 > 20 Best Stabiliser Cement* Cement preferred Cement or lime Cement preferred Cement or lime Lime preferred** * Lime requires the presence of clay minerals for reaction to take place and is therefore suitable only for materials with high PI. ** Cement can be used to stabilize materials of high PI provided they are treated beforehand with approx 2% of lime, which reduces plasticity and improves workability. *** Desert sands do not usually stabilize well with cement. They are more effectively stabilized with bitumen (see later). Cement shall conform to KS EAS 18-1 ’Cement: Composition, Specifications and Conformity Criteria, Part I. Lime shall conform to KS 02-97 1982 ‘Specification and Methods of Test for Building Limes’. The water used shall contain less than of 2000ppm sulphate and 1000ppm of chloride. In addition, unless cement and lime are properly stored and used in a fresh condition, their activity will be substantially reduced. Even if properly stored they will suffer a The Republic of Kenya – Ministry of Roads 49 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement progressive loss in strength with time: after 3 months, 20%; after 6 months, 30%; after 1 year, 40%. 7.2.3.3 Design Criteria Typical design criteria are presented in Table 7.6: Table 7.6: Design Criteria for Stabilised Materials Material properties After stabilisation: CBR, min (95% MDD BS Heavy) UCS, MPa Before stabilisation: Atterberg Limits, max values LL PI LS Aggregate strength TFVdry , KS 1238-12 Grading, Sieve Size, mm 50 37.5 20 5 2 0.425 0.075 Organic content BS 1377: Part 3 Sulphate (SO3) content BS 1377: Part 3 Layer Thickness Compaction level Material class CB1 CB2 CS1 CS2 70 40 3.0 to 6.0 1.5 to 3.0 1 to 2 Max 1 25 8 4 Minimum 50 kN 30 12 6 - 25 - 25 - - - 100 100 85 – 100 80 – 100 60 – 90 55 – 90 30 – 65 25 – 65 20 – 50 15 – 50 10 – 30 10 – 30 5 - 15 5 - 15 Maximum Maximum 0.5% 1.0% Maximum 0.3% Maximum 1.0% Max particle size 1/2 of compacted layer thickness but not >50mm. 97% of BS Heavy 95% of BS Heavy It is recommended that materials should have a Uniformity Coefficient of at least 5. (Uniformity Coefficient = Ratio of Sieve size through which 60% of material passes to Sieve size through which 10% of material passes) For cement the Unconfined Compression Strength (UCS) shall be measured on 150mm cubes after 7 days airtight moist curing and 7 days soaking in water at 27 ± 2˚C in accordance with BS 1924: Part 2. The compaction degree of the specimens shall be 97% MDD of BS Heavy Compaction. For each source of material to be stabilised the UCS shall also be determined on specimens cured airtight for 14 days. The ratio of UCS measured after 7 days curing and 7 days soaking and the UCS measured on specimen cured for 14 days shall not be less than 75%. For lime the curing period is 21 days, moist cure, followed by 7 days soaking, unless otherwise instructed by the Engineer. The strength of stabilised subbase, CS, can optionally be measured by the CBR test. Testing shall be carried out according to BS 1924, Part 2 The Republic of Kenya – Ministry of Roads 50 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 7.2.3.4 Practical Considerations Plant mixing is the most effective way of homogenization of stabilizer and material but the plant must be close to the site to avoid delays. However, it is a costly operation compared to mix-in-place methods and only materials relatively low in plasticity can be treated (with a Plasticity Modulus <700) in this manner. It is estimated that the variation of stabilizer content with plant mixing compared to mix-in-place is ± 10% and ± 20% respectively. If cement stabilizer is used, mixing, compaction and finishing shall be completed within 2 hours and the treated layer shall be protected against evaporation within 4 hours. If lime stabilizer is used, the respective times allowed are 4 hours and 8 hours. Protection and curing shall normally be achieved by the application of a bitumen seal coat. A prime coat is normally inadequate to prevent evaporation. Other methods that can be used are plastic sheeting, moist soil, straw or by keeping the surface damp by spraying. No vehicle shall be allowed on a cement treated layer for the first 7 days after compaction. If two or more layers are constructed it is important to prevent carbonation occurring at the surface of the bottom layer. The layer thickness should be between 100mm and 200mm. 7.2.4 Lean Concrete As its name implies, this is a weak concrete containing about 5% to 7% of cement (compared to 12% to 13% cement for proper concrete) and having a compressive strength of 10MPa to 15MPa at 7 days. Aggregate parameters are listed in Table 7.3, the quality of the aggregate the same as crushed stone for base. Ordinary Portland Cement can be used but there are many varieties of cement produced in Kenya and it may be worthwhile considering the use of slow setting and/or low heat of hydration cements to allow more time for construction and to offset the shrinkage problems. It is paver-laid, in thick layers of minimum 150mm, with the same conditions for finishing and protection as stabilized materials, discussed above. Both cement bound granular subbases/bases and lean concrete are laid without joints. They inevitably crack to relieve the stresses generated during cement hydration and, unless the material is covered with a substantial thickness of upper base and surfacing, the cracks will reflect through to the surface and allow the weather to penetrate. Since the main purpose of these layers is to enhance the strength of flexible pavements on weak foundations, the cracks are a disabling feature. 7.2.5 Sand Bitumen Mixes Comprehensive guidance is provided by Southern African Bitumen Association (Sabita) of South Africa, including some information provided free on the internet: www.sabita.co.za. Bitumen stabilization is appropriate in hot, dry areas, such as NE Kenya. Sandy soils predominate in these areas and, indeed, may be the only readily available material. Water is not needed at any stage in construction. Also, it is often the case that the bearing capacity of the subgrade is high, requiring only thin bases. Bitumen stabilized mixes are usually not robust and suitable only for Traffic Classes T1 or T2, providing there are few heavy commercial vehicles. The Republic of Kenya – Ministry of Roads 51 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Bitumen stabilized bases always require bituminous surfacings to prevent abrasion by traffic and to protect the bitumen from the harsh environment. A surface dressing is the most appropriate because of the thick bitumen film applied although other surfacings such as a Cape Seal or Otta Seal may also be suitable. The sand used should be well graded, preferably non-plastic and a typical target grading is shown in Table 7.7: Table 7.7: Sand Specification for Sand Bitumen Mixes Sieve Size,mm 5 2 1 0.6 0.425 0.075 % passing 100 90 – 100 90 – 100 80 – 90 70 – 80 10 – 20 However, most natural desert sands are single-sized and, as such, are unsuitable by themselves for bitumen stabilization because of the lack of mechanical stability. It may be necessary to find sands with different gradings and mix to obtain a more satisfactory grading. The quantity of fines (<0.075mm) should be limited to the lower end of the grading in Table 7.7 because the higher the proportion of fines the greater the percentage of bitumen required for the mix stability. Bitumen content will range between 3% and 6%, by weight of dry sand, and the more viscous the bitumen the higher the stability of the mix. Use of penetration grade bitumen (say Pen 60/70 or 80/100) will produce the highest stabilities but will require heating the sand as well as the bitumen. Probably the extra energy required to heat the sand is comparable to the additional cost of using cutback bitumen (say MC 30) or bitumen emulsions (say, anionic A2 or A3), and then waiting for the flux to evaporate before compacting the mixture. An approach successfully adopted in South Africa is to use a 60% anionic emulsion, applied at a 1% to 3% rate (residual bitumen 0.6 to 0.8%) combined with 1% of cement. It is conjectured that the emulsion initially benefits compaction and then the combined effect of the bitumen and cement contributes to a long term gain in strength. Bitumen-sand mixtures can be adequately compacted with 6 to 10 tonne steel rollers. It is not necessary to test the field densities to which they are compacted but it is important to check regularly the grading and bitumen content. The Hveem Stabilometer is probably more suitable than the Marshall test in indicating the influence of sand grading and bitumen content on the mechanical properties of these mixtures. Marshall design criteria are given in the Table 7.8: Table 7.8: Marshall design for Sand Bitumen Mixes Marshall Parameters Traffic Class T1 T2 1kN 1.5kN Marshall Stability at 600C (min) Marshall Flow Value at 600C 2.5mm 2mm (max) The bitumen and sand should be mixed in a pugmill type of mixer. The equipment needed is quite basic for small scale operations. In addition to the mixer and trucks for transportation, a The Republic of Kenya – Ministry of Roads 52 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement bitumen heater (if penetration grade is used) and a steel-wheeled roller are required. With larger operations, more control is needed: for example, loading hoppers and elevators, large mixers and a spreader-finisher for laying the material are required. 7.2.6 Dense Bitumen Macadam Bituminous premixes are produced in plant using aggregates of good quality, hot-mixed, transported to site and laid and compacted while still hot. The mixes must be designed to provide high deformation resistance, high fatigue resistance and good durability while being sufficiently workable during construction to allow satisfactory compaction. The exact requirements depend on the application, whether as a base or surfacing. In Kenya dense bitumen macadam, also known as close-graded bitumen macadam, is normally used for base for heavily trafficked roads of Traffic Class T5 or greater. It is a ‘recipe premix’, ie a mix of bitumen and aggregate which has been proven by experience to be satisfactory, rather than a mixture which has been designed from mechanical testing procedures, such as the Marshall test procedure. It is particularly appropriate for having high stiffness and resistance to deformation but, since the air voids content can be in excess of 5%, it needs a surfacing for protection against the environment. 7.2.6.1 Aggregates The aggregates used for DBM (and for all bituminous premixes) must be clean, hard and durable, similar in quality to crushed stone for roadbase. They consist of coarse aggregate, with particle size greater than 2.36mm; and fine aggregate, with particle size between 2.36mm and 0.075mm. (The definition of fine aggregate is that of the Asphalt Institute; note that AASHTO define coarse and fine aggregate with reference to the 4.75mm sieve). Premix also contains a small proportion of filler, consisting of rock fines, cement, or lime. The coarse and fine aggregates and filler are combined into various grading envelopes depending on their use. Recommended envelopes and aggregate properties for wearing and base, or binder, course are listed in Table 7.9: Table 7.9: Aggregate Specification for Dense Bitumen Macadam Material Properties Stone cleanliness Material Class Coarse Aggregate < 5% passing 0.075mm sieve Stone toughness Stone durability ACV max 28 Water Absorption max 2% (if in doubt then max Mg2SO4 Soundness 18%) Stone particle shape Flakiness Index max 25% Adhesion to bitumen Coating > 95% Grading of 0/30, % passing 0/40, % passing aggregate mix sieve size, mm sieve size, mm 50 100 37.5 100 95-100 28 90-100 70-94 20 71-95 - The Republic of Kenya – Ministry of Roads 53 Fine Aggregate SEV (AASHTO T176) min 45 (for material passing 4.75mm sieve) Mg2SO4 Soundness max 20% Coating > 95% Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 14 10 6.3 2 1 0.300 0.150 0.075 Layer restrictions Part 3 - Materials and Pavement 58-82 56-76 44-60 44-60 26-40 25-40 20-33 20-33 7-21 7-21 4-15 2-8 2-8 Min thickness compacted layer: 60mm (0/30), 75mm (0/40) Max thickness of compacted layer: 100mm (0/30), 125mm (0/40) The filler material should consist of cement, lime or other mineral dust and be non-plastic, with 100% passing the 0.425mm sieve and a minimum of 75% passing the 0.075mm sieve. Bulk density in toluene can range from 0.5 to 0.9g/l. For 0/30 DBM and lower the following Marshall requirements in Table 7.10 are recommended: Table 7.10: Recommended Marshall criteria Design Traffic (M ESA) Min Stability (kN at 600C) Flow (mm) Compaction level (no. of blows) T1 to T2 T3 to T4 T5 T6 to T7 3.5 6.0 7.0 9.0 2 to 4 2x50 2 to 4 2x75 2 to 4 2 to 4 To refusal To refusal The bitumen used must be of Penetration grade and meet the requirements in Table 7.11: Table 7.11: Bitumen Specifications Test Min or Max Penetration at 250C Softening Point (0C) Flash Point (0C) Solubility in Trichlorethylene, % TFOT heating for 5hr @ 1630C Loss by mass, % Penetration (% of original) Ductility at 250C Min Min Max Min Min Test Method (ASTM) D5 D36 D92 D2042 D1754 Penetration Grade 80/100 42 to 51 219 99 60/70 46 to 56 232 99 40/50 49 to 59 232 99 0.8 50 75 0.5 54 50 0.5 58 - Normally in Kenya either 60/70 or 80/100 Penetration grade bitumen is used: however, 40/50 penetration grade bitumen has been used successfully elsewhere in warm climates. In asphalt production two factors are important: the minimum mixing temperature should be used to achieve complete coating of the aggregate but high enough to enable compaction to be completed, and the mixing temperature must not be elevated above the allowable range to compensate for long delivery journeys or because of cold weather; The Republic of Kenya – Ministry of Roads 54 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Control of mix temperature should be based on bitumen viscosity but as a general guide the maximum temperature limits shown in Table 7.12 for mixing and delivery to the paver should be adhered to: Table 7.12: Bitumen Temperature Maxima-Minima Operation Mixing (ASTM D 946) Max.(ºC) Delivery to paver (ºC) Grade of bitumen 40-50 60-70 170 165 80-100 160 150-170 140-160 145-165 Compaction should start at as high a temperature as possible without causing undue distortion of the mix under the rollers and completed before the mat has cooled to less than about 90ºC. If necessary, asphalt delivery vehicles should be insulated and covered to prevent excessive cooling during long journeys or during delays, especially on sites subject to cold and windy conditions. No formal design method exists to determine the optimum composition of 0/40 (and some 0/30) basecourses) because the maximum particle size for the Marshall test is 25mm. Therefore, it is important that trials should be carried out to determine suitable mix proportions and procedures. Durable mixes require a high degree of compaction and this is best achieved by specifying density in terms of the maximum theoretical mix density or, alternatively, by using a modification of the Percentage Refusal Density test with extended compaction time (BS 598, part 104 (1989). A comprehensive discussion is contained in Appendix G of TRL Road Note 19. Mixing times and temperatures should be set at the minimum required to achieve good coating of the aggregates and satisfactory compaction. Temperatures between 1300C and 1500C are recommended for the mixing plant and between 1200C and 1500C for laying. The maximum compacted thickness for one layer is 200mm. The highest bitumen content commensurate with adequate stability should be used. For the heaviest trafficked roads it is necessary to design the DBM to refusal density following the procedure outlined for asphaltic concrete below. 7.2.7 Dense Emulsion Macadam Dense emulsion macadam (aka close graded emulsion macadam) is a cold mixed, cold laid plant mixture of well graded aggregate and bitumen emulsion and its principal use will be as a pavement overlay material. The requirements for aggregate and filler are basically the same as for DBM. The emulsion can be either slow-setting anionic A3 or slow-acting cationic K3. The amount of residual bitumen should normally be between 3 and 5% by weight of the dry aggregate. Dense emulsion macadam may be a cheap alternative to dense bitumen macadam. Although its strength is only slightly less than that of dense bitumen macadam, no heating or drying of aggregate and no heating of the binder are required. Moreover, the mixture can be laid by grader. Dense emulsion macadam should be laid in layers of compacted thickness not exceeding 150 mm to permit the evaporation of water. Full details of the mix design for dense emulsion macadam are given in Part V of the Road Design Manual. Dense emulsion The Republic of Kenya – Ministry of Roads 55 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement macadams require heavy compaction to be continued at intervals until all movement ceases; this may not be achieved until a period of some days after laying. 7.3 Surfacings 7.3.1 Prime Coat A prime coat is an application of low viscosity bituminous binder to an unbound surface, usually an unbound or a cement/lime-bound surface, in order to promote and maintain adhesion between the roadbase and a bituminous surfacing. MC 30 and MC 70 are the most suitable binders. MC 30 can be used for practically all types of materials. MC 70 is suitable only for open textured materials, such as graded crushed stone. The depth of penetration should be between 3 and 10mm and the quantity sprayed should be dry within two days. The rate of application will depend on the texture and density of the material to be primed. It is usually between 0.8 and 1.2litre/m2. It is good practice to dampen the surface to be primed as this facilitates the penetration of the binder Priming a cement-treated layer with cut-back can cause slight surface disintegration, because of interference with the cement hydration. If difficulties arise, priming should be replaced with a bitumen emulsion tack coat, although the absorbance of an emulsion is not as good as cutback bitumen. If the prime coat has to be trafficked before the surfacing is placed, it should be blinded with clean, non-plastic natural sand, crusher dust or fine aggregate. Prime coats applied to saline surfaces are subject to salt blistering. Reference is made to Chapter 11.3 for further details. 7.3.2 Tack Coat The prime function of a tack coat is to glue a new bituminous surface to an underlying bituminous surface. Tack coats should be very thin, otherwise they will act as a lubricant rather than a glue (especially in hot climates) and unnecessarily increase the bitumen proportion in the overlying asphalt. It is best to use a bitumen emulsion, spread thin to approximately 0.2 to 0.8 l/m2. All tack coats should be applied to a cleaned surface shortly before laying the next bituminous layer but allowing sufficient time for evaporation of cutter or run-off of emulsion water. Rapid curing cut-backs (RC 250, 800 or 300); medium curing cut-backs (MC 250, 800 or 3000); quick-breaking emulsions (Al or Kl-70); or A3 Anionic emulsion diluted with water l:l. MC 30 & MC 70 prime cut-backs are not suitable for tack coats. 7.3.3 Surface Dressing 7.3.3.1 General Surface dressing, or chip seal as it is otherwise known, is a very effective and versatile technique. It consists of the spraying of a bitumen film followed by the application of a layer of aggregate chippings. Thus, surface dressing does not impart structural strength to the pavement or improve the riding quality but it does provide a waterproof seal and can restore surface texture. It can be used as the principal seal for surfacing lightly trafficked roads or The Republic of Kenya – Ministry of Roads 56 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement used as a maintenance process to re-seal all types of roads. The lives of all bituminous surfacings are extended by periodic applications of surface dressing. The main property of surface dressings that lends itself to such versatile behaviour is the bitumen film, which is much thicker in surface dressing than bituminous pre-mixes. On heavily trafficked roads where the pre-mixes are compacted to refusal, the bitumen content is even lower than normal and in these situations surface dressing is applied to protect the pre-mix from early weathering. Surface dressing can be applied to new and rehabilitated roads carrying up to about 1000 vehicles per day. The technique consists of applying a prime coat on the finished base followed usually by a double surface dressing, ie a second application of bitumen and aggregate on top of the first. The advantage of this is that any deficiencies in the first application will be covered by the second application. The quality of a double surface dressing will be greatly improved if traffic is allowed to run on the first dressing for a period of at least two weeks. This permits the formation of a firm interlocking mosaic for the introduction of the second layer. However, this attribute may be compromised by traffic or animals contaminating the first seal. For maintenance purposes, a single seal (or other types of seal, see later) is usually laid. An intermediate type of surface dressing, shown to be appropriate for heavy and/or fast traffic is known as ‘racked-in’ where a heavier bitumen application is used than for a single surface dressing (but less than a double seal). A layer of large chippings is then applied followed immediately by an application of smaller chippings to ‘lock up’ the larger chippings and form a stable mosaic. Yet another type of surface dressing, known as a ‘pad coat’ is used when the hardness of the surface allows very little embedment, such as a cement stabilized road base or a dense crushed rock roadbase. A first layer of 6mm chippings are applied which will provide the basis for a second layer of 10mm or 14mm chippings. The success of surface dressings depends primarily on the adhesion of the aggregate chippings to the road surface; the chippings must therefore be clean and free from dust. Inaccurate rates of spread of both bitumen binder and aggregate, poor quality materials and poor workmanship can drastically reduce the effective life of a surface dressing. The substrate must have a uniform surface texture and should be cleaned to remove extraneous material, and should be dry, before surface dressing is applied. If it is not uniform the bitumen binder will permeate into open-textured areas but remain on the surface in close-textured areas. On existing roads, potholes should be repaired and trafficked for about a month before the surface dressing is applied. Detailed, up-to-date advice on surface dressing is contained in Overseas Road Note 3, 2nd Edition, published by TRL Ltd in 2003. The main points relevant to Kenyan conditions are summarized below. 7.3.3.2 Bitumen binder 7.3.3.2.1 Selection Penetration grade bitumens, cutback bitumens and bitumen emulsions can all be used for surface dressing. The bitumen must be capable of being sprayed, ‘wet’ the surface of the road in a continuous film, adhere to the chippings and be strong and durable enough to hold The Republic of Kenya – Ministry of Roads 57 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement the chippings against the traffic forces at the prevailing temperatures. In Kenya either a cutback binder, MC 3000, or a cationic bitumen emulsion, K1-60 or K1-70, are preferred, MC 3000 being used where road temperatures exceed 350C. Penetration grade bitumen is more readily available and it may be necessary to modify it on site by ‘cutting back’, or diluting it, with diesel or kerosene. Diesel is preferable because it is less volatile and normally between 2% and 10% is necessary to modify 80/100Pen bitumen to the required viscosity range. In new construction it is essential to apply a prime coat to bind the surface and ensure good adhesion between base and surfacing. The prime coat is usually fluid cutback bitumen, either MC 30 or MC 70. Emulsion bitumens are not suitable. Polymer-modified bitumen is often used (but not yet in Kenya) in order to improve the binder performance where the road surface experiences high stresses. Examples are thermoplastic rubbers and crumb rubber derived from waste car tyres. Latex rubber is also used to modify emulsion bitumens. 7.3.3.3 Aggregate Chippings Hard, tough, clean crushed aggregate chippings of roughly cubical or sub angular shape with single nominal sizes 6, 10, 14 and 20mm are required. Table 7.13 presents these requirements, reproduced from KS 02-1228 1994. The methods for the tests defined below are contained in KS 1238 2003. Table 7.13: Specification for Aggregate Chippings for Surface Dressing Material Properties Traffic, vpd Toughness, ACV, max % Durability (by Na2S04) Surface Dressing Aggregate >6000 16 2000-6000 500-2000 20 23 Max 12% <500 26 Shape (Flakiness), max,% Cleanliness, % passing 0.075mm sieve Polished Stone Value* Grading, sieve size, mm 28 20 14 10 6.3 5 3 2 0.5 20 20 25 14/20 100 85 – 100 0 – 30 0–7 0–2 - 60 10/14 100 85 – 100 0 – 30 0–7 0–2 - 25 <0.5% 6/10 10 85 – 100 0 – 30 0 – 10 0–2 - 50 3/6 100 85 – 100 0 – 30 0 – 10 0–2 * The Polished Stone Value test (KS 1238-15 2003) of the chippings is important if the primary purpose of the surface dressing is to restore the skid resistance of the road. The PSV required is related to the nature of the road site and the speed and intensity of the traffic. Where only the weaker aggregates are available, use of a rubber-shod roller is preferred to a steel-shod roller in order to minimize chipping fracture. Dusty chippings are a problem, particularly in hot climates, because it adversely affects adhesion to the bitumen. The chippings should either be washed in the stockpiles or, The Republic of Kenya – Ministry of Roads 58 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement preferably, pre-coated before spreading. This is particularly beneficial if traffic conditions are severe. Pre-coating should be carried out using either of the following methods: Using a pre-coating fluid comprising either bitumen emulsion or a mixture of diesel or kerosene containing 20% of Pen 60/70 bitumen and applied as a light coating, or Using Pen 60/70 bitumen at the rates shown in Table 7.14: coating by this method may be carried out in a conventional asphalt plant Table 7.14: Bitumen Coating Rate for Surface Dressing Chippings Nominal Size of Chippings, mm 6 10 14 20 Target Bitumen Content, % by mass 1.0 0.8 0.6 0.5 The selection of the nominal chipping size to be used depends on the traffic volume and substrate hardness. The interaction of these two variables is resolved in Table 7.15: Table 7.15: Selection of Surface Dressing Chipping Size Surface Type Very hard (concrete) Hard (aged asphalt surface) Normal (aged surface dressing) Soft (new asphalt surfacings) Very soft (bleeding surface dressings) Approx no. of commercial vehicles per lane per day 2000-4000 1000-2000 200-1000 10 10 6 14 14 10 20* 14 10 ** 20* 14 ** ** 20* <200 6 6 10 14 14 * Care should be taken with 20mm chippings that no loose chippings are left on the road prior to opening when open to traffic **Unsuitable conditions for surface dressing 7.3.3.4 Design 7.3.3.4.1 Average Least Dimension and Bitumen Application Rate Obtaining the optimum rate of spread of bitumen binder in an even film on the road surface is the most important factor in ensuring the success of a surface dressing. The determination of the application rate is based on the Average Least Dimension (ALD) of the chippings. This is the average thickness of a single layer of chippings when they have settled in their final interlocked position. It can either be directly determined by measuring a representative sample of about 200 chippings according to the method described in Chapter 14 or indirectly determined from the nomograph in Fig 7.1 using the Flakiness Index and Median Size of the chippings (=the sieve size through which 50% of the chippings pass). Figure 7.1: Determination of Bitumen Application rate The Republic of Kenya – Ministry of Roads 59 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 7.3.3.4.2 Weighting factor The ALD of the chippings is used with a weighting factor to determine the spray rate of the bitumen binder. The weighting factor, F^, is determined by summing the four variables listed in Table 7.15: Table 7.16: Weighting Factor for Bitumen Spray rate Total Traffic Very light Light Medium Medium-heavy Heavy Very heavy Climate Wet & cold Tropical Temperate Semi-arid Arid Vpd/l 0-50 50-250 250-500 500-1500 1500-3000 3000+ Factor +3 +1 0 -1 -3 -5 +2 +1 0 -1 -2 Existing Surface Untreated/primed base Very lean bituminous Lean bituminous Average bituminous Very rich bituminous Factor +6 +4 0 -1 -3 Type of Chippings Round/dusty Cubical Flakey Pre-coated +2 0 -2 -2 Using ALD and F^ in the following equation will determine the basic binder spray rate: R 0.625 F ^*0.023 0.0375 F ^*0.0011ALD Where: F^ = Weighting Factor ALD= average least dimension (mm) R = Rate of Spread of bitumen (kg/m2) Alternatively the two values can be used in the design chart given in Fig 7.2. The Republic of Kenya – Ministry of Roads 60 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Figure 7.2: Determination of Binder Application Rate from ALD and Weighting Factors The intercept between the F^ line and the ALD line is located and the rate of spread of binder is read off directly at the bottom of the chart. For slow traffic or climbing lanes the rate of spread should be reduced by approximately 10%. For fast traffic or downgrades steeper than 3% the rate of spread of binder should be increased by approximately 10%. As regards the application of emulsion, K1-60, will run off the road if the rate of application exceeds about 1.2 1/m2, on a smooth primed base, and 1.51/m² on a chip seal. Consequently, with emulsion, the application rates should be calculated as follows: 1. Determine the total amount of residual bitumen required, by using Chart S1c. 2. Calculate the total amount of emulsion required. 3. Split this amount into two sprays for single surface dressing and three sprays for double surface dressing, so that no run-off will occur and the upper spray rate is minimized. (Because of its low viscosity emulsion flows down and fills the voids between chippings). 7.3.3.4.3 Chipping Application Rate An estimate of the rate of application of aggregate chippings, assuming a loose density for the chippings of 1.35 Mg/m3, can be obtained from the following equation: Chipping Application Rate = 1.364*ALD A more precise and practical method of estimating the chipping application rate is to spread a single layer of chippings on a tray of known area. The chippings are then weighed and the process repeated ten times, the average being calculated, and then being increased by 10% to allow for ‘whip-off’. This value can be finally refined by observing if any binder remains The Republic of Kenya – Ministry of Roads 61 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement exposed after spreading, or if chippings rest on top of one another, indicating too low or too high a chipping application rate respectively. For double seals, aggregate chippings are generally half the size of the first seal. Recommended combinations are: 14/20 + 6/10; 10/14 + 3/6. Where triple seals are required (for instance if traffic is very high) the procedure for the first two seals is the same as for double surface dressing with the third seal being crushed rock fines. Adhesion agents are available for adding to binders to improve the ‘affinity’ between the aggregate and the binder and help minimize the damage to surface dressings that can occur in wet weather. These agents can enhance adhesion between chippings and binder even when they are wet. The effectiveness and the amount of additive needed can be determined by the Immersion Tray Test, fully described in ORN 3. Fresh hydrated lime can be used to enhance adhesion when about 12% by mass of bitumen is added and it also retards bitumen hardening. It should not be added to cationic bitumen emulsions which already contain an adhesion agent. 7.3.4 Slurry Seals and Cape Seals A slurry seal is a mixture of fine aggregates, Portland cement filler, bitumen emulsion and additional water (ASTM, D 3910, 1996). When freshly mixed they have a thick creamy consistency and can be spread to a thickness of 5 to 10 mm. Slurry mixes are best made and spread by purpose made machines. Both anionic and cationic emulsions may be used in slurry seals but cationic emulsion is normally used in slurries containing ‘acidic’ aggregates (ie most aggregates other than limestone), and its early breaking characteristics are also advantageous when rainfall is likely to occur. Suitable aggregate gradings, reproduced from ASTM D 3910, are given in Table 7.17. Type 1 is suitable for crack sealing and correcting fretting damage. Type 2 is suitable for filling more serious surface damage and Type 3 is suitable for sealing new and undamaged AC surfaces. Crack sealing will not be effective if the cracks penetrate down to the full depth of the AC layer. The coarse aggregate should be entirely crushed and sound aggregate (normally basalt in Kenya) in order to give optimum skid resistance. Table 7.17: Slurry Seal Types Sieve size No. mm ⅜” 4 8 16 30 50 100 200 9.5 4.75 2.36 1.18 0.600 0.300 0.150 0.075 Type of seal Percentage passing sieve size 1 2 3 100 100 100 90-100 70-90 90-100 65-90 45-70 65-90 45-70 28-50 40-60 30-50 19-34 25-42 18-30 12-25 15-30 10-21 7-18 10-20 5-15 5-15 The Republic of Kenya – Ministry of Roads 62 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement The ASTM standard must be referred to for full details of test methods and mix design. Tests include; ‘consistency’, to determine optimum mix design ‘set time’ to determine the time to initial set ‘curing time’ to determine initial cohesion of the slurry and resistance to traffic ‘wet track abrasion test’ to measure the wearing quality of the seal There would be great advantage if the bitumen emulsion was made with a polymer modifier or rubber additive such as latex. This would ensure early strong bonding between the bitumen and the aggregate and make the mix more stable in hot weather. Slurry seals are normally applied on top of a single surface dressing to make a ‘Cape Seal’, which has a smoother texture than surface dressing alone and is more durable. However, to avoid bleeding, the quantity of bitumen used in the surface dressing should be less than that normally required. Cape Seals are more expensive than double surface dressings, and require specialized machinery and expertise to apply. They are probably not economic for low volume roads. Table 7.18: Cape Seal specification Chipping Size in Surface Dressing, mm 20 14 10 Coverage (m2/m3) 130 to 170 170 to 240 180 to 250 7.3.5 Otta seal Named after a location in Norway where it was first applied, an Otta Seal is a graded aggregate or gravel containing all sizes including filler used instead of single sized chippings. It is thus more economical in its use of stone. There is no formal design procedure but recommendations based on case studies have been published. An Otta Seal may be applied as a single or double layer and experience has shown them to be satisfactory for 10 years’ service or more on roads carrying up to 300 vpd. The grading of the aggregate is based on the predicted traffic level. For light traffic (<100 vpd) a ‘coarse’ grading is used while for heavier traffic a ‘dense’ grading should be used. Grading envelopes are recommended in Table 7.19: Table 7.19: Otta Seal Specifications Sieve size, mm 19 16 12 9.5 4.75 2.36 1.18 0.6 0.3 0.15 0.075 Percentage passing Dense 100 79 – 100 61 – 100 42 – 100 19 – 68 8 – 51 6 – 40 3 – 30 2 – 21 1 – 16 0 – 10 The Republic of Kenya – Ministry of Roads 63 Coarse 100 77 – 100 59 – 100 40 – 85 17 – 46 1 – 20 0 – 10 0–3 0–2 0–1 0–1 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement The selection of bitumen binder reflects the aggregate quality but normally cutback bitumen MC 800, MC 3000 or Pen 200/150 are used. Spray rates are selected empirically and thus it is essential that pre-construction trials are carried out. Typically, spray rates for single seals are between 1.6 and 2.1m2 but adjustments are normally necessary and the Design Guide should be consulted (NPRA, 1999). An important aspect of Otta Seal construction is the need for extensive rolling for two to three days after construction. The rolling forces the binder upwards, coating the aggregate and initiating the process continued by traffic, of forming a pre-mix appearance to the surface. After-care can be lengthy and involves sweeping back dislodged aggregate to be further compacted by traffic. 7.3.6 Sand Seal In situations where aggregate for surface dressing is unobtainable or too expensive, sand can be used as a replacement. Sand seals are less durable than surface dressing because of abrasion by traffic but they can provide a satisfactory surfacing for traffic levels up to 100 vpd. The sand should be clean and coarse, with maximum size of 6mm, containing no more than 15% finer than 0.3mm and a maximum of 2% finer than 0.15mm. The sand should be applied at a rate of 6 to 7 m3/m2. The bitumen binder, which either be a cutback or an emulsion, should be spread at a rate of 1 to 1.2 kg/m2, depending on the type of surface being sealed. 7.3.7 Fog Spray A light spray of bitumen emulsion is ideal for improving early retention of chippings in a new surface dressing. The road surface is usually dampened before spraying. The emulsion must break completely before traffic is allowed onto the surfacing and it may be necessary to dust the surface with crusher dust or sand beforehand. If the emulsion is diluted with water, to obtain a 45% bitumen content to ensure the bitumen will flow around the chippings, the suitability of the water must be established by mixing small trial batches. The spray rate for the diluted emulsion will depend on the surface texture of the new dressing but the best results will be achieved if the residual bitumen in the fog spray is treated as part of the design spray rate for the surface dressing. The spray rate is likely to be between 0.4 and 0.8 l/m2 and it is important to avoid over-application of bitumen which will otherwise result in reduced skid resistance. 7.3.8 Thin Surfacings An effective way of providing good surface texture and skid resistance would be to surface an AC wearing course or binder course mix with a dense but specialist thin bituminous layer. This would have several advantages; the AC can be made entirely with basalt aggregate; a denser AC mix could be used if necessary, although the seal would prevent premature aging of the bitumen in the lower layer; the thin surfacing can be designed to be durable and to have good skid resistance without increasing the risk of plastic deformation; The Republic of Kenya – Ministry of Roads 64 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement it should be possible to add a second thin layer, when required for maintenance purposes, without the need for milling; and in built-up areas there will be less interference with kerb heights. There are several types of thin surfacing materials that would be suitable for use on roads in Kenya. However, it is probable that the use of modified bitumen and high standards of manufacture and construction would be required. The most suitable surfacings are likely to be proprietary materials. There are many proprietary thin surfacings. Nichols et al (2002) reported on several such materials that have been laid in the UK with favourable results. Three categories types of thin surfacings were described; paver-laid surface dressings: ultra-thin surfacings developed in France thin AC: generally with polymer-modified bitumen thin Split Mastic Asphalt (SMA); generally unmodified bitumen with fibres multiple surface dressing: polymer modified bitumen and aggregate applied separately micro-surfacing: thick slurry surfacing generally with modified bitumen Table 7.20 lists the wide choice of surfacings currently approved for use in the UK. For Kenya it will be important to have materials that are relatively insensitive to hot conditions and use of modified bitumen would meet this requirement. The use of a coarse grading for the underlying asphalt layer would assist in resisting embedment of aggregate in the surface layer. Table 7.20: Selection of Proprietary Surfacings currently available The Republic of Kenya – Ministry of Roads 65 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Category Name UK producer Paver-laid surface dressing Safepave Fibre-reinforced Safepave UL-M Hitex Axoflex Tuffgrip Colrug Thinpave Viapave Masterflex Associated Asphalt Limited Thin AC Thin stone mastic asphalt Multiple surface dressing Masterpave Axofibre Viatex Steelpave Smatex Premier Pave Nashpave Masterphalt Smartpave Duratex F Surphalt Finatex Jean Lefèbvre (UK) Limited Aggregates Industries UK Limited Lafarge Aggregates Limited Hanson Quarry Products Europe Colas Limited Aggregate Industries Limited RMC Aggregates (UK) Limited Tarmac Limited Tarmac Limited Lafarge Aggregates Limited RMC Aggregates (UK) Limited SteelPhalt Aggregates Industries UK Limited Foster Yeoman Limited Tarmac Limited Tarmac Limited Hanson Quarry Products Europe Ltd Tarmac Limited Total Bitumen Total Bitumen 7.3.9 Asphalt Concrete 7.3.9.1 General The road user mainly requires an asphalt concrete premix surfacing to provide a satisfactory riding quality and impart a sufficient skid resistance under all weather conditions. The design engineer requires a premix surfacing to protect the underlying pavement layers from ingress of water and the abrasive and disruptive actions of traffic and have a maximum maintenance-free life. There are two generic types of asphalt premix surfacing: The Republic of Kenya – Ministry of Roads 66 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Interlocked aggregate mixes, such as asphaltic concrete, which derive stability from the aggregate interlock, obtained by careful adjustment of the mix grading, and from the cohesion provided by the bitumen, and Mortar type mixes, such as gap-graded asphalt or sand asphalt, which derive stability from the cohesion of the fines-filler-bitumen mortar. Asphalt concrete is the bituminous surfacing of choice in Kenya. There is some doubt concerning the stability of gap-graded asphalts in hot climates, and even in temperate climates their use is declining in favor of alternative premixes, such as thin surfacings, allegedly more durable and resistant to deformation. 7.3.9.2 Design The design of asphaltic concrete mixtures assumes that the particle size distribution (=grading) of the aggregate should produce the highest possible density in the aggregate fraction of the mixture. This is achieved by producing a continuously graded aggregate following the ‘Fuller Curve’ (derived by Fuller & Thompson in 1907), according to the formula below: P 100 * d / D 0.45 where P is the percentage of aggregate passing sieve size d, and D is the maximum size of aggregate in the mixture. Table 7.21 shows sieve sizes raised to the power 0.45 and Fig 7.3 shows the maximum density grading as a straight line. Table 7.21: Sieve sizes raised to 0.45 power Sieve size (mm) 37.5 25.4 19 12.5 9.5 4.75 2.36 2.00 1.18 0.6 0.425 0.3 0.15 0.075 To power 0.45 5.11 4.29 3.76 3.12 2.75 2.02 1.47 1.37 1.08 0.80 0.68 0.58 0.43 0.31 Figure 7.3: Maximum density grading The Republic of Kenya – Ministry of Roads 67 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 100 Maximum density line 90 Passing sieve size (%) 80 Nominal maximum size Maximum size stone 70 60 50 40 30 20 10 0 Sieve size, mm (raised to 0.45 power) A compacted blend of crushed aggregates will give a maximum density if the particle size distribution follows the Fuller curve. However, this minimises the Voids in the Mineral Aggregate (VMA) that can accommodate both bitumen and the necessary air voids after compaction. This type of mix will be very sensitive to proportioning errors and it is best practice to modify the distribution away from the maximum density line. This is especially important when designing heavy duty asphalt concretes for the highest traffic classes. Mixtures of aggregate of the chosen grading and bitumen of the selected Penetration grade are evaluated using the rather complex and long-winded, and poorly reproducible, Marshall procedure. This procedure was elaborated by Bruce Marshall in the 1950s to determine the optimum strength for various aggregate-bitumen mixtures and an indication of the density to which the asphalt should be compacted on the road, although it did not explain that there were two phases of asphalt compaction; a) during the laying of the asphalt and b) during the passage of traffic over the design life. The stability of these mixes depends crucially on the air voids contained in the compacted mixture (Voids in the Mix = VIM) and, it has been found by experience, if VIM falls below 3%, the mixture becomes very susceptible to plastic deformation. The original Marshall design generated asphalt mixtures and defined their stability and flow at a standard temperature in order to estimate road compaction in the wheelpaths after a few years’ trafficking, up to a maximum very approximate 1 million esa, a reasonable value for the traffic at that time. However, traffic loads have since increased well beyond this value and the Marshall design has had to be modified by increasing the compaction effort in the procedure. In practice this would require the samples to be compacted with an inordinate number of blows such that the Marshall method becomes impractical. Alternatively, a more forceful method of compaction is used by employing the Percentage Refusal Density Test (PRD) (BS 598 Part IV 1989). Asphalt mixtures are compacted to refusal and the mixture still containing 3% air voids is selected. In practice, field compaction is required to achieve 95% of this refusal density, with no value <93%. There are three general types of grading envelope; The Republic of Kenya – Ministry of Roads 68 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 (i) (ii) (iii) Part 3 - Materials and Pavement those that span the maximum density ‘Fuller’ line; those that lie mostly below the maximum density line; and those that lie mostly above the maximum density line. Selection of an appropriate grading depends upon the level of traffic loading in terms of equivalent standard axles, and in some cases where vehicles have very high axle loads. Mixes made with an aggregate grading which spans the maximum density line need to be designed and made with care because the grading can be made to lie very near to the maximum density line and, therefore be sensitive to proportioning errors in the asphalt plant. The surface finish is also likely to be smooth with little surface texture and far from ideal for wet weather skid resistance. Mixes made with an aggregate grading which lies above the maximum density line contain a high proportion of sand size aggregate. This type of mix can be ‘tender’ and require care during compaction. The surface texture will tend to be very fine, giving poor wet weather skid resistance. Because of the high sand content air voids in the mix are more likely to be discontinuous than in the coarser mixes, even at the same total air voids content. Such mixes should potentially be the most durable and could be appropriate for roads carrying light traffic. Mixes made with an aggregate grading which lies below the maximum density line should be the most suitable mixes for heavy traffic. These aggregate gradings should provide enough voids within the aggregate matrix (VMA) to enable asphalt mixes to carry sufficient bitumen to coat the aggregate and also enable good workability, at the same time retaining adequate VIM under heavy traffic. The tendency is to use coarser gradings as the traffic loading increases and a very coarse mix is probably most appropriate for climbing lanes and other severely loaded sites. The difficult balance between mix resistance to deformation and durability must be reached and it may be necessary to seal this type of mix with a surface dressing. 7.3.9.3 Grading and other properties The aggregate and filler properties are similar to those for DBM, Table 7.9. Properties for the various premixes are given in Table 7.22: Table 7.22: Properties of Asphalt Concrete Type I (High Stability: stiff, rut-resistant, for T5 and above ) Sieve Wearing Course Binder Course Size (mm) 0/14 0/10 0/6 0/20 0/14 0/10 28 100 20 100 90-100 100 14 90-100 100 75-95 90-100 100 10 70-90 90-100 100 60-82 70-90 90-100 6.3 55-75 60-82 90-100 47-68 52-75 60-82 4 45-63 47-67 75-95 37-57 40-60 45-65 2 33-48 33-50 50-70 25-43 30-45 30-47 The Republic of Kenya – Ministry of Roads 69 Type II (Flexible, for T4 and below ) Wearing Course 0/14 100 90-100 70-95 55-85 46-75 35-60 0/10 100 90-100 62-90 50-80 35-65 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 1 23-38 0.425 14-25 0.300 12-22 0.150 8-16 0.075 5-10 Bitumen Grade** Bitumen Content, nom. Marsh. Stably., 75 blows, kN Flow Value, mm Voids in Mix, % Voids, %, at Refusal Density Void in Mineral Aggregate, % Voids filled with bitumen, % Fine Aggregate (<2mm) Filler* Layer Thicknes Mixing Temp Laying Temp Compaction Equipment Part 3 - Materials and Pavement 23-38 33-50 14-25 20-33 12-22 16-28 8-16 10-20 5-10 6-12 60/70 to 80/100 18-32 20-35 11-22 12-24 9-17 10-20 5-12 6-14 3-7 4-8 60/70 to 80/100 20-35 12-24 10-20 6-14 4-8 25-45 14-32 11-27 6-17 3-8 80/100 25-50 14-33 11-27 6-17 3-8 5.5-7.0 4.5-6.0 5.0-6.5 5.5-7.5 5.5-7.5 6.0-8.0 5.0-6.5 Min 9 Min 9 4 to 7 2 to 4 2 to 4 2 to 5 3 to 5 Min 3* 4 to 10 Min 3* 3 to 8 Min15 (at design VIM) 65-73 Min13 (at design VIM) ±5% (of the value determined at JMF optimum bitumen content) Sand Equivalent >40; Sulphate Soundness <12 Cement, lime, limestone; non-plastic; passing 0.425mm 100%; passing 0.075mm >75%; Bulk density in toluene 0.5-0.9g/ml. Maximum filler:bitumen ratio 1.2 0/10 25mm; 0/20 50mm Bitumen 130 to 1500C (60/70); 120 to 1400C (80/100) By Paver min. temperature 1300C (60/70); 1250C (80/100) Density (min) 96% of Lab design Marshall Min temperature at end of compaction 800C (60/70) 700C (80/100) Steel wheel rollers: 5 to 7kg/mm of roll width Pneumatic tyred rollers; min 2 tonnes per wheel *The purpose of the filler is to extend the bitumen (ie fill the voids) and to make it stiffer. Too much filler (beyond 1.2 times bitumen content) makes the mixture difficult to work. **Bitumen properties are given in Table 7.11. Type I asphaltic concrete is a fairly stiff type of mix designed to resist rutting and high stresses. Type II asphalt concrete is a more flexible mix, designed to resist comparatively high flexural deformation. It must be placed in a thin layer, maximum 50mm. The desired rigidity (or flexibility) will be obtained by the proper combined choice of the following factors: Penetration grade of bitumen, degree of crushing of coarse aggregate, angularity of sand, mix grading, amount of filler, amount of bitumen, filler to bitumen ratio and Voids in total Mix (VIM). The production of flexible asphalt concrete Type II will generally require the use of an appreciable proportion of rounded sand and a comparatively high amount of bitumen 80/100. It is important to bear in mind that the mix composition should strike a balance between the requirements of stability and durability. In particular, it is not desirable to achieve Marshall The Republic of Kenya – Ministry of Roads 70 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement stabilities much higher than the minimum values recommended since this would produce a lean mix prone to rapid hardening of the bitumen and fatigue cracking. Because of the rapid ageing of bitumen generally observed in Kenya, the use of bitumen harder than 60/70 grade is not recommended. It is advisable to use the softest grade of bitumen and the highest bitumen content compatible with the achievement of the recommended minimum stability, maximum flow value and minimum voids requirements. Overheating of the aggregate and of the bitumen must be avoided, as it causes oxidization of the bitumen. Asphalt Concrete Type I, because of its low voids content, is very sensitive to mix variations. Furthermore, as the bitumen filling is thin, the mix is somewhat difficult to work and compact. This type of mix requires very strict control of production, laying and compaction. It is suitable for the heavy traffic classes. Asphalt Concrete Type II is suitable only for medium and light traffic. 7.3.9.4 Design for Heavy Traffic: Refusal Density (Superpave™) Superpave™, or Superior Performing Asphalt Pavements, is a procedure which was developed in the 1990s in the USA from the Strategic Highway Research Programme as an improved system for specifying bitumen binders, aggregates, developing asphalt mixture design and analyzing and establishing pavement performance prediction. It purports to be a performance-based specification system. However, to be able to follow it completely requires a substantial investment in new equipment and products, currently outside the range of the budgets of most developing (and some developed) countries’ budgets. For example, Table 7.23 lists the equipment required to investigate bitumen properties. Table 7.23: Superpave equipment for bitumen performance characterisation Property Aging Temperature/ viscosity Equipment Rolling Thin Film Oven Standard AASHTO T240 Pressure Aging Vessel AASHTO PP1 Rotational Viscometer Dynamic Shear Rheometer Purpose Investigate aging during construction Investigate aging over pavement life Bitumen performance during handling Visco-elastic properties applicable to rutting and fatigue Aggregate characteristics required were subdivided into ‘consensus’ and ‘source’ properties but mostly this amounted to the same situation as before, which is to be expected. Instead, elements of Superpave™ have been adopted, the most significant of which is a means of compacting the asphalt trial mixes in the laboratory in a more appropriate manner, and beyond the normal Marshall level of compaction, in order to replicate conditions on the heaviest trafficked roads. To do this, a piece of equipment known as a gyratory compactor is required. This compacts the trial mix in a manner more akin to the action of traffic than the Marshall hammer, and is much quicker. Presently in Kenya most major projects include it in the equipment list and it is used and compared alongside the PRD Test (BSI, 1989). Eventually the gyratory compactor will replace the PRD Test because: it can be adapted for large moulds if larger sized aggregate is used it gives good density distribution through the depth of a sample The Republic of Kenya – Ministry of Roads 71 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement it can mould Marshall samples, and it is more representative of field compaction than the impact-type Marshall compaction. For the heaviest trafficked roads, T5 to T7, it is necessary to design the asphaltic concrete to a greater degree of compaction than is practical by usual Marshall design. A number of gradings should be investigated so that a workable mix is identified containing a minimum of 3% Voids in the Mix (VIM) at Refusal Density. It is important to use a strong aggregate because there is the danger that the more robust compaction will damage the aggregate and change its grading: so, if possible, the aggregate should come from a source known to give good results. These mixes will most likely have the grading characteristics displayed in general in Fig 7.4 and listed in Tables 7.24 and 7.25: Figure 7.4: Generalised Superpave grading Table 7.24: Superpave: Grading Control Points Nom Max Sieve Size Size, mm mm 37.5 0.075 2.36 25.0 37.5 50 25.0 0.075 2.36 19.0 25.0 37.5 19.0 0.075 2.36 12.5 19.0 25.0 12.5 0.075 Control Point % passing 0 6 15 41 90 90 100 100 1 7 19 45 90 90 100 100 2 8 23 49 90 90 100 100 2 10 The Republic of Kenya – Ministry of Roads 72 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 2.36 9.5 12.5 19.0 28 90 100 Part 3 - Materials and Pavement 58 90 100 - Table 7.25: Superpave: Grading ‘Restricted Zone’ Boundaries Sieve Size within restricted zone 4.75 2.36 1.18 0.6 0.3 Minimum and maximum boundaries of sieve size for nominal maximum aggregate size (minimum-maximum % passing 37.5 25.0 19.0 12.5 34.7-34.7 39.5-39.5 23.3-27.3 26.8-30.8 34.6-34.6 39.1-39.1 15.5-21.5 18.1-24.1 22.3-28.3 25.6-31.6 11.7-15.7 13.6-17.6 16.7-20.7 19.1-23.1 10.0-10.0 11.4-11.4 13.7-13.7 15.5-15.5 Nominal Maximum Size is one sieve larger than the first sieve to contain more than 10% of aggregate. Where possible the largest particle size should be less than 25mm so that the requirements of the Marshall test design can be complied with. Mixes identified for compaction trials shall be made to the laboratory design bitumen content and two other bitumen contents of +0.5% and +1.0% additional bitumen. Cores will be cut to determine the density of the compacted material. The core will then be reheated to 145 ±50C in the appropriate mould and compacted to refusal with the vibrating hammer test. The cores from the compaction trial must have a density equivalent to 95% of the refusal density. The compaction trials are aimed to identify a workable mix which can be made to a bitumen content which gives no less than 3% VIM at refusal density. Trials shall also be carried out with the Gyratory Compactor, if available, to determine the number of revolutions that are equivalent to the refusal density using the vibrating hammer. For this heavy duty asphalt the maximum Marshall Stability should be 18,000N after 2x75 blows and at compaction to refusal shall have 3% VIM. Having established the suitability of the aggregate source, several gradings should be tested, including that used for the Marshall test, to establish the bitumen content and VIM at refusal density and a bitumen content corresponding to a VIM of 3% should be selected. Compaction trials should be carried out to establish the workability of the premix. The temperature of the bitumen and aggregates on mixing should be 1100C ±30C above the softening point of the bitumen. Compaction of the premix should commence as soon as it can support the roller and should be completed before its temperature falls below 900C. Rolling should continue until the voids measured in the completed layer are in accordance with the requirement for a minimum compacted density of 98% of the Marshall optimum or a minimum mean value of 95% of refusal density (with no value less than 93%). Mixes designed to 3% VIM at refusal density and compacted during construction to a mean density of 95% of refusal density will have 8% VIM. Mixes of this type should be very resistant to secondary compaction by traffic but will be permeable and allow the ingress of water. They should be trafficked and the bitumen hardened. Then the asphalt should be sealed with a single surface dressing containing 14/10mm chippings. This is to protect the bitumen of the heavy duty asphalt from premature oxidation and aging. The period of hardening will depend on the traffic level and should be such that the chippings do not become embedded in the wearing course. The Republic of Kenya – Ministry of Roads 73 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Minimum thicknesses for the individual layers are as follows: 37.5mm mix, 65mm; 25mm mix, 60mm; 19mm mix, 50mm; 12.5mm mix 40mm. 7.3.10 Gap-graded Asphalt Gap-graded asphalt has a certain range of particle sizes missing from the total aggregate grading. It generally consists of aggregate of a fairly uniform size blended with sand and filler. As there is very little stone-to-stone contact in the compacted mix, the stability is derived from the cohesion of the sand-filler-bitumen mortar. Although it has been successfully used on a section of Nairobi – Mombasa road it is not robust in terms of deformation resistance, as would be expected. Even in temperate climates on heavily trafficked roads it has a tendency to rut quickly and therefore probably is suitable only for medium to light traffic. Its main virtues are its flexibility, its fatigue resistance, and its durability, due to the good distribution of the voids structure and the rounded shape of most of the fine aggregate. The gap-graded mixes specified are designed for thin wearing courses (25-50mm). These mixes are impermeable, because of the comparatively high bitumen content and the good distribution of the voids structure. The coarse aggregate is limited to 55% by weight. “Low stone content” mixes (less than 40%) are easy to work and compact and are very tolerant to mix variations, whereas “High stone content” mixes (more than 45%) become sensitive to changes in bitumen content. Gradings and other properties are listed in Table 7.26: Table 7.26: Gap-graded Asphalt Specification Criteria Coarse Aggregate Grading Sieve size (mm) 20 14 10 2 % passing 100 38 to 100 0 to 69 0 to 2 Mix Design Requirements Marshall Stability (S), N Flow, (F), mm Marshall Quotient, Q, S/F Voids in Mortar of Mix, % Filler/Bitumen Ratio Fine aggregate + Filler Grading Sieve size % passing (mm) 1 100 0.425 70 to 97 0.300 49 to 93 0.150 16 to 58 0.075 0 to 20 Min Max 3000 9000 2 6 2 3 9 0.9 1.3 7.3.10.1 Mix design method 1. Prepare mixture of fine aggregate and filler to give 1:6 ratio by mass of filler to fine aggregate retained on 0.075mm sieve. Determine the optimum bitumen content which gives maximum Marshall Quotient. 2. By adding coarse aggregate and reducing bitumen content the Marshall Quotient may be increased to the specified value. 20% coarse aggregate will increase quotient The Republic of Kenya – Ministry of Roads 74 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement by factor of approx. 1.5, 30% by 1.9, 40% by 2.4 and 55% by 3.0. For an increase in coarse aggregate the revised bitumen content is given by: NBC OBC 100 S / 100 2.3S / 100 where: NBC = Nominal Bitumen Content S = % of coarse aggregate added 3. Prepare mixes in accordance with BS 594 at bitumen content from (2) to check specified requirements. Gap-graded mixes typically have the following grading and compaction characteristics: 7.3.11 Sand Asphalt Sand asphalt consists of natural sand plus, in some cases, mineral filler and a small proportion of crushed fine aggregate, bound with Penetration bitumen. The recommended grading is listed in Table 7.27: Table 7.27: Sand Asphalt Grading Grading of Aggregate + Filler Sieve size, mm % passing 10 100 6.3 95-100 2 70-100 1 47-95 0.425 20-75 0.300 15-60 0.150 8-30 0.075 4-12 Marshall properties are Stability, 3000 tp 9000 N; Flow 2 to 6mm; Voids in Mix 5 to 10%. Sand Asphalt is, suitable for wearing course in a thin layer (max. 50 mm). Because of its relative richness in binder and the good distribution of the voids structure, sand asphalt is impermeable, flexible and has a good fatigue resistance. As its resistance to rutting is not very high, sand asphalt is suitable only for light and medium traffic, ie Classes T1 and T2. 7.4 Other Materials 7.4.1 Reclaimed Asphalt Pavement (RAP) 7.4.1.1 Current Practice in Kenya It can be economically viable, and environmentally desirable, to reclaim worn-out asphalt and granular pavements, re-process and re-use them in the rehabilitated road. Implementation of the technology, however, requires significant investment in specialist skills and equipment, appropriate Governmental pressure to carry it out and the formulation of The Republic of Kenya – Ministry of Roads 75 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement suitable specifications and/or methodologies to control the process. Details of the latter are presented in Appendix H of ORN 19 2002 and summarized here. Presently in Kenya, the technology is in its infancy. On the major road projects of the Northern Corridor route, RAP is produced by milling the old road surface, and either mixed with fresh aggregate and cement to make ‘cement-improved subbase’ and/or mixed with additional crushed stone to make an ‘upper subgrade’. It could be that the strength of these re-processed layers is manifestly greater than the normal requirement in order to ensure that the life of the road will be long. The stockpiling of RAP prior to re-processing it is a critical part of the procedure. It is important that the variability of the RAP is well controlled. Stockpiled RAP tends to agglomerate and a crust forms, depending on the hardness of the bitumen and the ambient temperature. To offset this tendency, it has been found that the larger the stockpile the better. RAP readily absorbs moisture and it is best stored under roofing in an open-sided building. 7.4.1.2 RAP in Capping Layers A capping layer would only be used in the reconstruction of a road pavement where (in the unlikely event) the in situ subgrade CBR was <5%. The existing UK specification requires RAP to meet the grading specification in Table 7.28. The capping layer can consist of 100% of RAP providing the bitumen content is <10%. The recycled material can be laid to a maximum thickness of 200mm providing the required density is obtained. This is 95% of BS Heavy, BS 1377, Part 4, 1990. Alternatively, the material can be laid by method specification. Table 7.28: Grading Specification for RAP Bs Sieve Size Mm 125 90 75 37.5 10 5 0.6 0.063 % passing sieve size 100 80-100 65-100 45-100 15-60 10-45 0-25 0-12 7.4.1.3 RAP in Subbase Layers The quality of the aggregate in the RAP should at least meet the requirements for this layer. Fresh aggregate can be added to modify the grading and the compacted layer of the blended material should be acceptable providing the bitumen is hard enough not to hinder compaction and enable the required moisture content, which is between the optimum moisture content and -2% of optimum moisture content achieved with the BS Vibrating Hammer test, BS 1377, Part 4, 1990.to be met. This is also subject to a Trafficking Trial, whereby the compacted RAP is laid on a prepared trial area constructed t a specified standard and then trafficked with a loaded truck until 1000 esa have been applied. The mean deformation in the wheelpaths must be <30mm for the material to be acceptable. The Republic of Kenya – Ministry of Roads 76 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 7.4.2 Modified Bitumens Until now, Kenya has not used modified bitumens, which is surprising because they have been in existence for more than 15 years. It may be because of bad experience or cost, or a combination of reasons. The main problem is that the field is a very specialized one; investigations have to be carried to identify the modifier best suited to the bitumen of choice because the beneficial effects are not guaranteed. Unmodified bitumen has weaknesses: it becomes rapidly more ‘fluid’ at high temperatures, facilitating rutting in asphalt and embedment in surface dressing: and in the intense light of the tropics it rapidly ages and hardens, accelerating cracking. Numerous proprietary products are commercially available to ameliorate these characteristics. The products can be categorized as follows: 7.4.2.1 Polymers It is possible to create additives which are claimed to enhance the good properties of bitumen whilst suppressing the bad properties. Ethyl vinyl acetate (EVA), styrene butadiene styrene (SBS) and styrene butadiene rubber (SBR) are three such examples. They all increase the viscosity, and visco-elastic stiffness, of bitumen at high temperatures and increase fatigue life. 7.4.2.2 Rubbers It is claimed that natural rubber can be added to bitumen to enhance its resilience. Much of the motivation for this has been the desire to recycle used vehicle tyres and the benefits are still uncertain. 7.4.2.3 Chemical additives Elemental sulphur and manganese have both been used as additives. Sulphur becomes a liquid at a temperature greater than ≈1200C and is added to improve workability at high temperature. Manganese is used to increase bitumen viscosity and stiffness but with the disadvantage that bitumen becomes more brittle. 7.4.3 Cold Bituminous Mixes Under normal conditions bitumen will only adhere to aggregate if the two materials are heated sufficiently to drive off all water and fluidize the bitumen, an energy-intensive and thus expensive procedure. Thus there is a strong motivation to invent a mechanism whereby a form of bitumen workable at ambient temperature will mix with cold, wet aggregate, with the added benefit of safety of working. 7.4.3.1 Emulsion Bitumen Bitumen emulsion is a suspension of bitumen in water, manufactured by turning hot bitumen into fine droplets by introducing it into a rapidly circulating drum and combining it with an emulsifying agent and water. The emulsifying agent enables the bitumen and water to coexist as a relatively stable fluid, with the bitumen comprising between 40% and 70% of the total volume. The Republic of Kenya – Ministry of Roads 77 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 7.4.3.2 Foamed Bitumen The bitumen foam is produced by the rapid mixing of hot bitumen, air and water. The water content within the bitumen is from 2% to 5% of bitumen volume but, transformed into steam, the foam expands into many times the volume of the bitumen itself, and then it can be readily mixed into the aggregate. The ratio of peak foam volume to original bitumen volume is known as the ‘expansion ratio’ and the time until this peak volume is halved is known as the ‘half-life’. The expansion ratio is typically between 5 and 20 while the half life is typically between 10s and 40s. In contrast to bitumen emulsions, which can be stored for months, foamed bitumen has to be used quickly, within tens of seconds: the advantage it has over emulsion is that it requires less water. The presence of the water and the need to drive it off presents the principal challenge to the successful use of both forms of cold mix. Once compacted into the pavement the process of strength gain (‘curing’) begins. Since both cold mixes contain water, they inevitably contain less bitumen and, in terms of volume, there is insufficient bitumen in the mix eventually to coat the aggregate particles. The presence of water during compaction of the cold mix means that the mix is left with a high void content once the water has evaporated, thus reducing stiffness and fatigue resistance compared to a well-compacted dense asphalt. Mitigating measures can be taken but the best one is to change to a more open grading with a higher void content at full compaction. This permits a higher bitumen percentage to be used and encourages the water to evaporate, at the cost of a reduced stiffness. 7.4.4 Block Paving Block paving consists of an interlocking mosaic of small blocks, in Kenya usually made from fine concrete or from cut stone (usually by hand, so the material is not too hard). The blocks are placed on a substrate of compacted medium-coarse sand. Beneath the sand is the base, which can be a granular material and it is important that this is of sound quality otherwise the whole structure will easily deform. The blocks themselves may have the properties of concrete but it is the discontinuities between them and the substrate which have the crucial effect on performance. They are commonly seen in city centres and are used for aesthetic reasons and also for resistance to deformation. It is usually the quality of workmanship and not the quality of materials and design that determines their longevity. The common standard size of block is 200 x 100mm, by 60mm thickness. The substrate is usually 30 to 50mm of sand or sand-cement mortar for heavy duty applications and sand is also used to fill the interstices between the blocks. The thickness of sand is important: if it is either too thin or too thick failure can occur; and also obviously the quality of sand in terms of its angle of internal friction. It is also crucial that the strength and uniformity of the substrate is even, otherwise individual blocks will either become loosened or will fracture. However, it is also very important that the filling between the blocks and the block pattern itself are well constructed. The pattern known as ‘herring-bone’ is one of the most effective at generating the necessary block interlock: Fig 7.5 illustrates typical patterns. Use of block paving is not recommended in situations such as the corners of streets because the twisting forces of turning vehicles is very disruptive to the individual blocks. Figure 7.5: Typical patterns for concrete blocks The Republic of Kenya – Ministry of Roads 78 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 7.4.5 Geosynthetic materials Unbound materials have nil tensile strength and sometimes it is necessary to provide this by means of geosynthetic reinforcement. A successful fabrication can make a very significant improvement to the deformation resistance of an unbound material. On other occasions geosynthetic material is used as a separator to avoid intermingling of soil material with pavement layers; and also sometimes as additional strengthening to an asphalt overlay or inlay.. 7.4.5.1 Reinforcement 7.4.5.1.1 Subgrade The reinforcement membrane imparts strength by interacting with the shear strength of the material being reinforced. The reinforcement must therefore achieve interlock with the individual particles. Thus, for soils with particle sizes of the order of µm (micrometers), a membrane of appropriate texture must be used; whilst for granular materials a geogrid is more suitable. Together with the stress reinforcement through particle-to-particle interlock there is also a contribution due to the friction of the soil particles with the membrane. The main contribution of the membrane, however, is to withstand the tensile stresses that may be suffered by the soil. Obviously, the support is greatest in the plane of the membrane and decreases away from it, however, as yet, there is no method of predicting the zone of influence of the membrane. 7.4.5.1.2 Pavement Geogrids are increasingly being used to enhance the life of an asphalt inlay or overlay by slowing down the rate of crack formation and by providing additional shear resistance against rutting, especially in high stress sites. A secondary benefit is that cracks are prevented from opening even after penetrating the full depth of the pavement. Geogrids are manufactured from steel, glass fibre, plastic and also asphalt. They are also placed into a layer of sprayed bitumen, applied at an approximate rate of 1litre/m2 and in this situation act as a sealant, preventing water from entering even after cracks have formed. They also have a role as separators, preventing reflective cracking. The Republic of Kenya – Ministry of Roads 79 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement The geosynthetic used must therefore be matched with the purpose and the material being reinforced. It is the responsibility of the engineer to assess the need for and the effectiveness of the varied products available in the marketplace. 7.4.5.1.3 Separator Materials used for this purpose are called geotextiles, and are classed either as ‘woven’ or ‘non-woven’, and can be manufactured of plastic, glass fibre or plant-based material. The main property is that they should permit water to flow freely yet not soil. It is important to take account of the rupture strength possibly being exceeded by large particles or construction traffic. 7.4.6 Hand-Packed Stone In Kenya this form of construction is commonly used for bus bays and parking lots. Large stones, usually of 15cm size and consisting of lava aggregate, are placed directly onto the natural ground. The gaps between the stones are then infilled with rock fines and small chippings, sometimes vibrated in with a hand operated machine, until the fines completely cover the stones and present a level surface. The integrity of the surface then depends how well the large stones have been packed together on the natural ground, how well the fines have been vibrated in, and how strong the natural ground is to start with. 7.4.6.1 Stone quality Generically, a hand-packed stone surface comprises a closely placed layer of broken stone pieces that are wedged into place with stone chips hand rammed into the interstices; the remaining voids are filled with fines. The hand packed stone layer is normally bedded on a thin layer of coarse sand, with grading as follows: 90-100% passing 4.75mm; 0-15% passing 0.300mm; 0-2% passing 0.150mm. The surface relies on the development of mechanical interlock between the discrete unbound particles for its strength and is thus highly dependent on the provision of adequate edge support without which the layer would progressively ravel from the edge inwards under the passage of traffic. The hand-packed stone surfacing disperses the stresses caused by traffic loading and acts as a barrier to erosion and pulverisation of the roadbed that would otherwise result from tyre friction. The large pieces of broken stone form an interlocking load-bearing matrix in conjunction with the smaller stone chips that must be tightly wedged to firmly anchor the whole layer in place. Thus, load transfer takes place at relatively few contact points and the crushing strength of the stone will influence the rate of its degradation under traffic loading. The stone should be tough and durable and obtained from breaking down unweathered hard rock and should ‘ring’ when struck with a geological hammer; a hollow, dull sound is indicative of degradation. Crystalline igneous rocks such as granite and stable basalt are preferable. The use of rounded cobbles or sedimentary rock with weakly bonded bedding planes should be avoided. The finished surface is durable and fairly impermeable but, as the hand-packed stone forms the trafficked surface, the riding quality is only moderate. 7.4.6.2 Roadbed Where the soaked CBR of the roadbed material is ≥ 5% (95% BS Light) the recommended thickness of the stone packed surface is 150mm. If the CBR value is even lower a thickness of 200mm is recommended. The Republic of Kenya – Ministry of Roads 80 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 7.4.6.3 Construction The roadbed is shaped to a camber of 3-5% and compacted to refusal density at a moisture content close to the optimum. After setting out the finished road line and level a 250mm wide by 200mm deep trench is excavated to accommodate kerbstones along each edge of the road. The minimum triaxial dimensions of kerbstones should be 400, 200 and 100mm. The smallest face of each kerbstone is dressed so that it is flat and approximately perpendicular to the longest axis. The kerbstones, placed in the trench with their longest axis vertical and smallest face uppermost, are firmly bedded and laid to the final road level. The trench is backfilled with moist, well compacted excavated material to firmly anchor the kerbstones in position. Supplementary drainage measures should be provided to prevent any ingress of water through the surface from becoming trapped behind the kerbstone edge support where it would otherwise penetrate the roadbed causing it to soften and loose strength and the handpacked stone surface to deform and ultimately fail. The salient features are illustrated in Fig 7.6. Figure 7.6: Hand-packed stone construction The Republic of Kenya – Ministry of Roads 81 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement A variant that has recently been trialled for labour-intensive roads in Kenya is to use ‘quarry waste’, comprising moderately to highly weathered stone for the construction of low cost, sealed roads. The quarry waste is placed on a road bed that has been compacted to refusal, spread and then compacted to shape using a vibrating roller. A thin bituminous seal is then placed on top. 7.4.7 Rumble Devices Data regarding rumble devices and speed humps can be obtained by free download from: http://www.dft.gov.uk/stellent/groups/dft roads/documents/divisionhomepage/032065.hcsp 7.4.7.1 Purpose Features with a vibratory and audible effect can be used, usually in rural areas, to alert drivers to take greater care in advance of a hazard such as a bend or junction. Although rumble devices have been used, in places, with the aim of reducing speeds, the evidence so far indicates that any speed reduction obtained will tend to be minimal, and will be eroded with the passage of time. It is also known that in some locations drivers have learned to accelerate over the devices to lessen the vibratory effect. 7.4.7.2 Types Rumble devices come in a variety of different forms, which have been described as rumble strips, jiggle bars, and rumble areas. Rumble strips and jiggle bars are similar in concept and design, both comprising narrow strips of material laid transversely across the carriageway. Normally rumble strips will be laid in a series of groups consisting of between two to five strips per group. Spacing between the groups can vary. Fig 7.7 gives examples. Rumble areas are generally constructed of coarse chippings, but can also be formed from block paving or gravel filled cellular blocks. The Republic of Kenya – Ministry of Roads 82 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 7.4.7.3 Noise Rumble devices can generate considerable noise over a large area depending on the topography and ambient noise levels. Rumble areas tend to be less noisy than rumble strips, but a more expensive form of construction. Noise generated will vary from location to location and depend on the pattern and type of device used. In general, siting of rumble devices close to residential properties should be avoided. Some authorities do not use rumble devices within 200m of residential properties. Where a conflict seems likely to arise between safety gains and increased noise levels, consideration should be given to whether the noise disbenefit outweighs the benefit of accident reduction. Additionally consideration could be given to using a lower height device, though this may be at the expense of overall effectiveness. 7.4.7.4 Regulation requirements The UK Traffic Calming Regulations permit rumble devices up to 15mm in height, provided no vertical face exceeds 6mm in height. The requirement not to exceed 6mm for the vertical face is important. Heights greater than 6mm could create difficulties for two wheeled vehicle drivers, particularly cyclists. If materials such as thermoplastic are used to form rumble devices they confer the advantage that any faces formed are rounded. 7.4.7.5 Rumble Device layouts Choice of the most appropriate layout to adopt depends largely on local circumstances. The following should therefore only be considered as general advice, to be modified as the particular location dictates. 7.4.7.5.1 Full or half width Rumble devices can be constructed across part of a carriageway only, so that they only affect drivers approaching a hazard. Existing evidence suggests that, particularly where drivers can see a long way ahead, they may cross the centre line of the road to avoid the devices. This obviously can be dangerous but also lessens the effectiveness of the rumble devices. Extending the device across the full width of the carriageway will prevent this. 7.4.7.5.2 Cycle and drainage provision To allow for drainage and help cyclists to avoid rumble devices it is advisable to provide a gap, preferably in the range of 750mm to 1m, between the edge of carriageway and the device. 7.4.7.5.3 Appearance Rumble devices should be of a contrasting colour from the generality of the carriageway, so that drivers can see them. White must not be used, to avoid confusion with road markings. Rumble devices should also be clearly visible at night: where the colour of the construction is relied on, rather than signing, the use of a suitable reflective material may be feasible. 7.4.7.5.4 Location Rumble devices will be most appropriate in rural locations in advance of hazards such as bends and junctions. There is some evidence to suggest that rumble strips should not be used on bends with a radius less than 1,000m, because of possible danger to motorcyclists. Rumble devices used in urban areas will generally be limited because of the noise they can generate. If rumble areas are used to indicate the start of shared surface roads the overall The Republic of Kenya – Ministry of Roads 83 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement height should be in the order of 5mm in order to reduce noise levels, and make them more friendly for cyclists to cross. 7.4.7.5.5 Signing Where rumble devices do not stand out visually from the rest of the road surface, authorities should consider whether they should be signed. Where rumble devices are used at the approach to a hazard such as a bend or junction they should where possible be sited in obvious relationship to signing warning of the hazard. Where this cannot be achieved, specific signing for the rumble devices should be considered. 7.4.7.5.6 Height For normal use a height of 13mm is adequate for providing both audible and vibratory warning, whilst achieving any speed reduction that might be obtainable. When used in combination with other features, such as at gateways, lower heights may yield acceptable results. In all cases it is important to ensure that vertical faces do not exceed 6mm in height. For rumble areas a 14mm chipping size set in an epoxy resin has been used relatively successfully and can comply with the maximum height of 15mm generally. 7.4.7.5.7 Pattern The pattern to be adopted will depend on physical features and driver behaviour at the particular location. Irregular spacing between groups or areas will help to break up the noise patterns generated, which may make them more acceptable to any nearby residents. Decreasing the space between groups or areas is generally the most effective. The number of groups/areas and strips per group should be kept to the minimum. In the case of rumble strips, about 50 strips divided into 2 to 4 groups will normally be sufficient. With regard to rumble areas 4 to 6 areas will normally be adequate, though where these take the form of narrow bands this number may need to be doubled. Normally, spacing between rumble strips in the individual groups will be between 300mm and 500mm. Spacings below 400mm are more suitable for roads having speed limits less than 40mph. On roads with higher speeds, the closer spacing tends to allow vehicles to "float" over the strips. The pattern of rumble devices should finish within 50m of any hazard it is associated with. 7.4.7.6 Materials and costs Rumble areas are generally much more expensive than rumble strip schemes, particularly those using thermoplastic material. Currently prices for rumble area schemes range from $5000 to $15,000, depending on materials used. This needs to be set against the average cost of a personal injury accident. Rumble strips have mainly been constructed in a thermoplastic material. They vary from $1000 to $2000 per scheme. It is likely, however, that they would need to be replaced more frequently than rumble areas. The Republic of Kenya – Ministry of Roads 84 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Figure 7.7: Examples of Rumble Strips 7.4.8 Speed Humps Road humps are a common sight in Kenya and are an extremely effective means of keeping vehicle speeds low. However, there appears to be little standardization in shape and, since most are constructed of asphalt with a painted surface, after time they become invisible to the motorist and therefore can be dangerous. In the UK, regulations originally permitted the construction of humps ranging from 50mm to 100mm in height but subsequent experience indicated that a height of 75mm was optimal, still resulting in significant speed reduction and substantially lessening the likelihood of the grounding of vehicles, compared to 100mm high humps. Both flat and round-topped kerb-to-kerb humps are effective: Fig 7.8 gives design examples. Both types may be tapered at the sides to allow a drainage channel between the hump and the kerb. At low speeds, vehicles can cross these humps without causing undue discomfort to passengers or damage to the vehicle, but as speeds increase, they become progressively more uncomfortable. Fig 7.9 shows the design of a later development, the sinusoidal hump, with a shallower initial rise. Compared to the round and flat-topped humps, the sinusoidal hump is more comfortable for vehicles but with an attendant lower speed reduction. Humps may be used along single carriageway and dual carriageway roads providing there is a 30mph speed limit and the road is not a trunk, special, or principal road. The Republic of Kenya – Ministry of Roads 85 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Figure 7.8: Design of Round and Flat Topped Speed Humps Figure 7.9: Design of Sinusoidal Hump Road humps and rumble strips shall be constructed after completion of the surfacing. A prime coat should be applied to the surface, consisting of MC 70 cutback bitumen, applied at a rate of 0.55l/m2, or as directed by the Engineer. The material for the hump or rumble strip shall be as directed by the Engineer. It should be of a different colour compared to the surfacing. If it is asphalt, it should be placed and compacted into moulds and finally shaped to the required profile by rollers and tampers. The Republic of Kenya – Ministry of Roads 86 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 8 Structural Design Method 8.1 Design Principles 8.1.1 Thicknesses and Materials Characteristics No pavement structure can be designed independently of the characteristics of the pavement materials. Indeed, every material has a different behaviour which is largely influenced by the characteristics of the other pavement layers. 8.1.2 Design Period The concept of design period should not be confused with that of pavement life. Each of the pavement structures proposed has been designed to carry a certain cumulative traffic. When the pavement has carried the design traffic, it will need to be strengthened so that it can continue to carry traffic for a further period. The need for, and design of, pavement strengthening is discussed in Part 4, Overlay and Asphalt Pavement Rehabilitation Manual. In this respect, it is necessary that paved roads be regularly surveyed, so that strengthening can be planned and implemented before extensive deterioration has occurred. It is assumed that during the design period maintenance will be carried out. Maintenance includes the shoulders and drainage systems, erosion and vegetation control, patching and sealing. This maintenance is essential and its neglect will seriously affect the pavement performance. 8.1.3 Stage Construction An early decision that has to be made is whether it is best to initially design a strong pavement, which will last throughout the design period without the need for strengthening, or to design a weaker, and therefore more economic, pavement with the aim of strengthening it at some intermediate stage to enable it to last the remainder of the design period (= Stage Construction). Stage construction is suitable for medium and light traffic (Classes T1, T2, T3 and T4). However, the pavements proposed for light traffic (Classes T1, T2 and T3) are generally minimum or nearminimum pavements and it is therefore impracticable to reduce them further. Stage construction is most suitable for pavements carrying medium traffic (Class T4), when normal construction includes 50 mm of premix as surfacing (see Chapter 9). Stage construction would then consist of: Construction of the full road base thickness, and application of double surface dressing. An overlay of 30 - 50 mm of premix after about 5 years. It is important that this overlay is allowed for in the design. Stage construction is not recommended for heavy traffic, especially overloaded axles (Classes T5, T6 and T7), as the risks of premature deterioration are unacceptable for such important roads. Moreover, it is difficult and costly to handle traffic during strengthening operations. The Republic of Kenya – Ministry of Roads 87 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 8.1.4 Safety Factor It is apparent that the heavier the traffic, the more costly the pavement and hence the higher the safeguard against failure should be. For example, under heavy traffic (Classes T5, T6 and T7), it is unwise to place sophisticated (and expensive) materials, such as lean concrete or dense bitumen macadam, directly on heterogeneous and deformable natural materials. The ratio of the upper pavement layer to the lower pavement layer should be within the range 1.5 to 7.5. If a thick bituminous layer is placed directly on a layer of graded crushed stone it is likely to suffer tension cracking from bottom to top. Addition of cement to the graded crushed stone to enhance its stiffness is recommended. The exact amount of cement should be determined in the laboratory in accordance to the required stiffness to be achieved. 8.1.5 Minimising Base and Surfacing Thicknesses The thicknesses of road base and surfacing, which are made of the most expensive materials, should be kept constant and as low as possible, for each class of traffic. 8.2 Practical and experimental considerations 8.2.1 Use of Flexible Pavements Flexible pavements are defined as pavements composed of a base made of fairly deformable material, such as natural gravel, graded crushed stone or cement or lime-improved material with a thin bituminous surfacing (surface dressing or not more than 50 mm of bituminous premix). Experience has shown that such flexible pavements are perfectly suitable for light and medium traffic (Classes T1, T2, T3 and T4), i.e. up to 10 million standard axles, provided that this does not include a substantial proportion of overloaded axles as defined in Chapter 2. For heavy traffic (Classes T5, T6 and T7), it is necessary to construct a semi-rigid pavement with a base of bound material, such as dense bitumen macadam, lean concrete, cement stabilized gravel and/or a thick bituminous surfacing (high stability asphalt concrete). The most common mechanisms of deterioration of the proposed pavement structures are rutting in the subgrade, fatigue cracking at the bottom of the bituminous layer and horizontal cracking at the bottom of cement/lime treated layer. 8.2.2 Influence of Subgrade 8.2.2.1 Compressive strain criterion Due to the difficulty in estimating subgrade soil parameters most of the current analytical design methods use the so called “subgrade strain criterion”. This approach relies on the assumption that the strength of a soil is directly related to its stiffness which might not be always generally true. Various relationships have been proposed, usually based on real evidence of performance, which is reasonable within the range of subgrades and pavements encountered in gathering that evidence. In this manual no specific relationship has been used, since each is site-specific. It might be reasonable to use them in comparative design processes but they should not be assumed to be a permanent deformation law unless proven to be applicable to the specific conditions intended. It is widely accepted that the compressive strain in the surface of the subgrade is the criterion that governs the total thickness cover required in the case of a flexible pavement. If The Republic of Kenya – Ministry of Roads 88 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement the compressive strain is excessive, permanent deformation will occur in the subgrade, causing deformation at the pavement surface. The relationship between the maximum permissible compressive strain and the cumulative number of standard axles is usually given by an empirical equation called the “subgrade failure criterion” which relates the vertical strain at subgrade level to pavement rutting performance. Many subgrade failure criteria appear in the technical literature but each failure criterion is an inseparable component of a specific pavement design method and should not be extracted and used outside the context it was developed for. In the case of rigid and semi-rigid pavements, the deciding criterion is generally not the compressive strain in the subgrade, but the horizontal tensile strain in the upper pavement layers. 8.2.2.2 Subgrade modulus In the deeper, less highly stressed layers of the pavement, the stress levels rarely reach failure. This means that the stress levels never approach the failure line. To determine the transient deformation which will occur under traffic loading we need to know the (shear) strain response to the change in stress which results from the traffic. This response is characterized by the stiffness of the subgrade, improved subgrade or sub-base. It is to be noted that the stiffness decreases as the stress level increases i.e. as the stress gets closer to failure conditions. The modulus taken into account should correspond to the moisture content of the subgrade soil most of the time under the pavement, since the effects of repeated loading are relevant. At present, quantification relies on conventional soil index tests, the California Bearing Ratio test (CBR) and the Plate Bearing test (PBT). The CBR does not give a very reliable indication of material behaviour. It is an empirical test in which (in its laboratory embodiment) a plunger is advanced once into a cylindrical pot of recompacted soil at a constant rate. The load causing 2.5 and 5mm penetration is recorded and expressed as a percentage of the load required for the same penetration in a certain standard material. This depth of penetration is more than sufficient to cause rupture and large permanent deformation. This loading regime may be compared with that imposed by pavement traffic which comprises many repeated light loadings. The test provides information largely relating to soil strength whereas the designer requires stiffness and permanent deformation Furthermore very different CBR results are obtained from in situ and from laboratory measurements on the same material. Design methods are usually imprecise as to test conditions and whether in situ testing is required. For these reasons, the test cannot be recommended and values obtained should be used with great caution. The saving grace of the test, and doubtless the reason for its continued use, is its relative simplicity, speed and low cost. It is interesting to note that it has not been used in pavement design in California for many years. The plate bearing test (PBT) overcomes many of these problems in that it essentially measures in situ stiffness. However speed of loading effects is not matched by the test. The PBT can therefore be used during construction as a means of checking that the actual stiffness is greater than that required for the successful performance of higher layers. Often, these direct or semi-direct means of determining the stiffness of the pavement layers will not be possible and empirical or semi-empirical methods might be used. The subgrade moduli of the most common types of soils at their equilibrium moisture contents should be determined by direct measurements (e.g plate bearing tests). The design system should incorporate the dynamic elastic modulus of the subgrade as one of the principal design parameters. The Republic of Kenya – Ministry of Roads 89 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 8.2.2.3 Permanent deformation The size of the permanent strain depends on how close to failure the stresses are during the loading pulse. Although it may be very small in any one cycle, because its effect is cumulative, over many cycles there may be a noticeable build up of permanent deformation. A stress path may approach failure either because the applied stress is large, or because the pore water pressure is high, thereby reducing the level of effective stress. Thus a welldrained aggregate sub-base or subgrade is less likely to experience rutting problems during construction than a wet one. 8.2.3 The Behaviour of Pavement Materials 8.2.3.1 Unbound materials Protection of the subgrade is the basic pavement design requirement, however, it is important that the overlying layers do not deform excessively under repetitive loading. This is not being considered explicitly and reliance is made on material specifications. It is to be ensured that granular layers should have a suitably high angle of internal friction, giving a suitably high shear strength leading to an increased stiffness It is important to appreciate that the dynamic modulus of any unbound layer is not simply a function of the component material, but is also dependent to a large degree on the stiffness of the underlying material. The Shell Pavement Design Manual (1978) used the concept of modular ratio limitations in successive unbound layers. In addition, the resistance to attrition of each material has been evaluated and the consequent traffic limitations are given in the Pavement Materials Charts in Chapter 7. 8.2.3.2 Hydraulically Bound Materials A hydraulically bound material (cemented) will in most cases end up in a cracked state, which means that its apparent stiffness will inevitably be less than that of the intact material. Experience suggests that a cement bound base layer with an initial stiffness in the range 10000-20000 MPa can easily end up with an apparent in situ stiffness of no more than 5000 MPa. It is this apparent stiffness which affects the way the layer spreads load to underlying materials and supports overlying layers. The deciding criterion is usually the tensile stress at the bottom of the cemented layer. 8.2.3.3 Bituminous Bound materials – fatigue characteristics When bound materials are used, the deciding criterion is usually the horizontal tensile strain at the bottom of the bituminous base or surfacing. If this strain is excessive, the layer will crack. The principal task is that of developing a fatigue characteristic for use in design and this can only be achieved by calibrating against observed pavement performance. Any relationship derived from laboratory testing should be assessed carefully. Laboratory test results on bituminous materials do not replicate real conditions and also the set ups and procedures adopted during testing might lack realism. In this manual, the fatigue characteristics of bound materials have been estimated on the basis of measured characteristics of the material and from theoretical considerations. Bituminous have a visco-elastic nature and their stiffness modulus therefore depend on the rate of application of the load and on the temperature. Temperature has a significant effect on the stiffness as well as the fatigue and permanent deformation resistance of bituminous mixtures. It is therefore quite obvious that accurate knowledge of the temperature distribution in the pavement should be available in order to allow realistic analyses of the stresses and strains in asphalt pavements to be made. Assuming a constant temperature over the The Republic of Kenya – Ministry of Roads 90 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement thickness of the asphalt layer is far from reality unless one is dealing with thin asphalt layers. Furthermore the total asphalt thickness is commonly made of different types of asphalt mixtures, especially in case the total thickness is larger than 100 mm. 8.2.3.4 Bituminous Bound materials – top-down cracking The true mode of deterioration in a bituminous layer might be by surface cracking. It is necessary to develop a calculation technique for strain originating at the surface. Although there is no consensus some useful working approximations have been made and are based on the assumption that surface strain is a function of asphalt compression. It has been observed that for an identical granular pavement foundation but varying asphalt thicknesses top-down cracking tends to predominate on thick pavements and that bottom-up cracking predominates for thin pavements. 8.2.3.5 Pavement materials moduli The above mentioned factors should be considered when assigning stiffness moduli to the various pavement layers. It is known that rigid and semi-rigid pavement layers need adequate support. It is suggested from empirical studies that, materials whose moduli are less than 10% of the succeeding rigid or semi rigid layer are unlikely to give that support. From consideration of the moduli tabulated earlier, suitable support layers are given in Table tabulated below. Table 8.1: Suitable Support Layers for Rigid or Semi-Rigid Pavement Layers Rigid or Semi Rigid Pavement Layer Stabilised material Suitable Support Layers Subgrade min CBR = 15% Subbase gravel Cement Stabilised material Graded Crushed Stone (GCS) Stabilised material Dense Bituminous Macadam Stabilised material Graded Crushed Stone (GCS) Lean Concrete Stabilised material Asphalt Type I Dense Bituminous Macadam Lean Concrete Cement Stabilised material Graded Crushed Stone (GCS) Stabilised material Asphalt Type II Stabilised material Sand Asphalt and Gap Graded Asphalt Stabilised material Graded Crushed Stone (GCS) 8.3 Calculation of stress, strain, deflection and layer thickness 8.3.1 Calculation of stress, strain and deflection For various pavement structures, an analysis of stresses and strains due to traffic loads were made using an elastic multi layer system. In carrying out these analyses, the following assumptions regarding the behaviour of the materials were made: the pavement layers are composed of homogeneous and isotropic linear elastic material their horizontal extent is infinite the layer thickness is uniform, and The Republic of Kenya – Ministry of Roads 91 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement a load of uniform pressure is applied over a circular contact area However, it should be noted that: If granular layers are separated from the applied load by a significant thickness of asphalt or concrete, it is reasonable to assume elastic material properties for them in the subgrade stress or strain calculation. Multi-layer linear elastic analysis can then be used, assigning an elastic modulus and Poisson’s ratio to each layer, and stresses and strains calculated under the design load It is logical to expect that the stiffness behaviour of asphalt to be very far from linear – but not so. The point here is that the magnitude of strain taking place within the aggregate skeleton is small compared to that common in an unbound material (i.e. unbound layer not overlain by a thick bituminous structure) and in the small strain region the stiffness of an unbound material is approximately constant. Furthermore the loading rate is usually high enough to ensure that the bitumen is kept near the elastic end of its visco-elastic behaviour spectrum. The combination is sufficient to give an approximately linear stress-strain response. However, the actual value of stiffness modulus will vary significantly with bitumen properties which in turn depend on temperature and loading rate. In the design procedure, the pavement is regarded as a three-layer system, if it comprises a thin bituminous surfacing (surface dressing or thin bituminous surfacing), a four-layer system, if it comprises a thick bituminous surfacing (more than 50 mm) and a five layer system if an improved subgrade layer is considered. The lowest layer, taken as semi-infinite, represents the subgrade including improved subgrade, if any. The upper layers represent respectively the subbase, base and, if any, the thick bituminous surfacing. Layered analytical models are generally based on the work of Burmister (1943) The calculation of stress, strain and deflection are computed with the following assumptions; The design load is assumed to be uniformly distributed over one circular area giving an applied pressure of 0.56MPa Most of the pavement materials have a Poisson's ratio equal to 0.35 except for hydraulically bound layers who are assigned a value of 0.25 (All layers are considered to have complete friction between them (fully bonded) The computer program ALIZE of the LCPC has been used to calculate the horizontal tensile stress and strain at the bottom of each layer made of bound material, the vertical compressive stress and strain in the surface of each layer, including the subgrade, and the deflection at the surface of the pavement. Design axle loads up to 80 kN are considered. 8.3.2 Determination of layer thicknesses In the case of flexible pavements, the total pavement thickness required has been determined by a comparison between the compressive strain applied to the subgrade and the maximum permissible strain which depends on the number of load applications. In the case of bound materials, the thickness required for each individual layer has been determined by a comparison between the tensile strain at the bottom of the layer and the maximum permissible strain, as deduced from the fatigue law of the material. The Republic of Kenya – Ministry of Roads 92 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement In addition, it has been checked that compressive strain on the subgrade is within a permissible range. 8.4 Construction Principles 8.4.1 Minimum layer thickness For each material, there is a minimum layer thickness below which proper laying and compaction are not possible. For granular materials, if D is the maximum particle size then the minimum practical thickness is 2.5 D for surfacing and base and 2 D for subbase layers. In addition, irrespective of the material type, it is impractical to lay subbase and bases to compacted thicknesses of less than 100 mm. For the different types of material considered, the minimum practical thicknesses are as follows: Table 8.2: Minimum layer thicknesses Layer Material Type Minimum Thickness (mm) Subbase Natural Gravel 100 Clayey Sand 100 GCS2 0/40 100 GCS2 0/60 125 Base Natural Gravel 125 Clayey Sand 100 GCS1 0/20 100 GCS1 0/30 100 GCS1 0/40 125 DBM 0/30 125 DBM 0/40 150 Surfacing Asphalt Concrete 0/20 50 Asphalt Concrete 0/10 25-30 Sand Asphalt 25-30 8.4.2 Minimum significant thickness increments Considering the usual level and thickness tolerances within which the different layers have to be constructed, it is clear that thickness variations of less than 25 mm are meaningless. Consequently, the layer thicknesses of the structures proposed vary by minimum increments of 25 mm. 8.4.3 Compliance with the specifications All the materials are assumed to comply with the requirements given in Chapter 7 and all the layers to be constructed in accordance with current specifications.1 1 References Burmister, DM (1943): Theory of Stresses and displacements in layered systems and application to the design of airport runways. Proc. Highway Res. Board, 23, Washington DC, pp 126-148 Autret, P et al (1982): ALIZE III Practice. 5th Int. Conf. on Structural Design of Asphalt Pavements, Delft University The Republic of Kenya – Ministry of Roads 93 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 94 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 9 Standard Pavement Structures The Republic of Kenya – Ministry of Roads 95 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 96 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 97 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 98 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 99 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 100 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 101 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 102 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 103 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 104 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 105 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 106 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 107 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 108 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 109 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 10 Pavement Shoulders, Drainage and Cross Sections In an ideal world, the road shoulders would be an extension of the carriageway. Thus, there would be no question that the shoulders were structurally adequate for purpose, would support the sides of the carriageway and, provided they were sealed, would prevent rainwater seeping into the edge of the carriageway and weakening it. However, in the real world, in order to economise, the shoulders are often constructed of different, usually inferior materials, are not sealed, leading to their differential erosion and premature weakening of the carriageway. 10.1 Shoulders Deterioration of paved roads often begins with edge-fretting, especially if the shoulders are unsealed; the repair of such damaged roads is then difficult to carry out effectively. Thus, the pavement shoulders should be considered as a fundamental part of the pavement which functions are to: improve road safety by providing better visibility and convenient hard standing for temporarily disabled vehicles and police roadblocks give added width to the carriageway for emergency use provide lateral support to the pavement layers, especially if granular materials are used for the base facilitate removal of surface water from the road and, protect the edges of the subqrade against soaking and facilitate the internal drainage of pavement layers. Shoulders should therefore have sufficient strength to carry occasional traffic, be impervious to surface water, be properly shaped so as to shed water completely and be erosion resistant. It is always preferable to construct the base and subbase materials right across the shoulders to the drainage ditches. This provides lateral support to a granular base and simplifies the construction. 10.1.1 Bearing Capacity of the Shoulders Use of the same pavement structure for the shoulders as for the carriageway simplifies construction and ensures that the bearing capacity of the shoulders will be adequate for the design life of the road. If this is not the case, site conditions will determine the strength required for the pavement depending mainly on the likelihood of heavy traffic using the shoulder. Generally shoulders to bituminous roads should be constructed at least with material of gravel wearing course quality, which is to a minimum strength of CBR 30% or, if stabilized material is used, to CS standard. For the heaviest traffic (Classes T5 to T7), higher strengths are required, and in this case the shoulders should definitely be constructed to the same standard as the carriageway. The Republic of Kenya – Ministry of Roads 110 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement For lightly trafficked roads (Classes T1 and T2), where no suitable gravel is available, material with a minimum soaked CBR of 15% at 95% of BS Heavy can be used. In arid areas the soaked condition may be relaxed to CBR of 15% at 95% of BS Heavy, at OMC. 10.1.2 Surfacing of Shoulders A waterproof and durable bituminous surfacing must be used for roads where the shoulders are paved. Prime coats alone are inadequate. If the shoulder base material is a non-cohesive material such as graded crushed stone or non-plastic gravel, the shoulders must be primed and sealed. The type of seal may be either a single or double surface dressing, preferably with a sand seal cover, or an Otta seal with a sand seal cover, or asphalt concrete Type 2 in the case of traffic classes T5 to T7. If the shoulder base material is a cohesive material, such as plastic gravel or cement (or lime) stabilised material, the shoulders may be left unsurfaced, except in the case of traffic classes T5 to T7 where they should be surfaced as above. It is preferable, however, that all shoulders should be sealed because, in addition to increasing their longevity, sealing prevents the ingress of surface water at carriageway edges. For lightly trafficked roads (Classes T1 and T2), shoulders can be left unsealed but protected from erosion by topsoiling and grassing. After the final trimming and compaction, the shoulders shall be topped with 20 mm of humus or topsoil and lightly rolled. Sprigs of indigenous “runner type” grass should then be planted or alternatively the planting of seed may be used. This type of protection is applicable to gravel (and earth) shoulders, in fairly wet areas. The shoulder surface should then be about 20 mm below the carriageway edge. Where shoulders are unsealed attention should be paid to the internal drainage of the carriageway base because suitable gravel for the shoulders is likely to be impermeable, thus preventing drainage from the base. If the carriageway base is constructed of permeable materal, the following alternative measures are required: either place a 75mm thick drainage layer immediately below the shoulder gravel, or install a special drainage facility Consideration may be given to protection of surfaces from high speed running by heavy traffic. This may be done either by providing rumble strips at intervals or by using special paver edging shoes to provide a distinct non-dangerous drop-off at the edge of the carriageway to the shoulder level. Kerbs at the edge of the carriageway are the best protection for edge-fretting but they are expensive. Their use should be considered for all roads carrying heavy traffic subjected to frequent entry and exit and stopping on shoulders, or in urban areas. However, there is a small problem in that they create a discontinuity along the road edges, with possible water ingress, and should only be used where a permeable base and subbase are used. All surface treatments for shoulders should wherever possible be designed to give the shoulders a contrasting texture or colour compared with the carriageway. 10.1.3 Prevention of cracks in the shoulders Longitudinal cracks in shoulders are associated with differential settlement in earthworks or pavement layers owing to road widening. Good techniques for earthworks and pavement The Republic of Kenya – Ministry of Roads 111 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement construction, set out in the Standard Specifications for Highway Construction, minimize these risks. Longitudinal cracks in shoulders can also be caused by the presence of expansive soils in the subgrade. Design and construction methods to counteract cracking caused by expansive soils are set out in Chapter 11. Transverse cracks can develop in shoulders due to either thermal movement in bituminous layers or by shrinkage in stabilized layers. All that can be done if this occurs is to re-seal the cracks during periodic maintenance. 10.2 Drainage 10.2.1 Drainage on the Road Surface and Shoulders Rain falling on the road surface and shoulders must be conveyed rapidly to the side ditches. For this purpose, road and shoulder surfaces are given a crossfall, the value of which depends on the nature or the surface. The following crossfalls are recommended: Bituminous and concrete road surfacings : 2.5% Earth and gravel road surfaces :3 to 4% Gravel shoulders : 4% Primed or cement treated shoulders : 6% For minor roads constructed in hilly territory, frequent crossfall changes can lead to flat spots on the finished pavement, which hold water. Cement stabilised bases are particularly vulnerable to this fault as they cannot normally be re-trimmed and re-compacted within the specified time limits. The crossfall on this type of road may therefore be steepened to 4%, at the discretion of the designer 10.2.2 Drainage of the Pavement Layers Effective drainage of granular pavement layers is essential for their good performance and is ensured by attention to cross section details. In particular, ‘boxed-in’ pavements, where water could be trapped in the pavement layers, must not be used. Measures to ensure proper drainage of the pavement layers must be included in the design, particularly where internal drainage could be impaired, possibly in the following circumstances: where shoulders are designed with different materials to those of the carriageway where kerbstones are extended into granular pavement layers, and where unpaved shoulders comprising near impermeable materials are used. 10.2.3 Granular bases Where a granular base and paved shoulders are used, the base and subbase layers must be extended across the full width of the shoulders 10.2.4 Cemented or Bituminous bases Where economically possible the base should be extended across the full width of the shoulders. The Republic of Kenya – Ministry of Roads 112 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 10.2.5 Part 3 - Materials and Pavement Drainage of the Subgrade Sufficiently deep open side drains or alternatively special facilities such as sub-surface drains will ensure proper drainage of the subgrade. Particular attention to design and construction details is required where rock occurs, which could trap water in the subgrade. In soils, open side drains shall not be less than 0.5m deep, measured from the drain bottom to formation level. In cuttings in soils open side drains shall be not less than 1m deep, measured from the drain bottom to formation level. This depth can be reduced to 0.5m if the subgrade is cement or lime modified. In cuttings in solid rock the required drainage measures depend on site conditions and shall be decided in individual cases. The need for sub-surface drains as alternatives to open drains depends on site conditions, requiring careful consideration owing to their high cost. Construction in urban areas, the presence of subsoil wells and in some types of cuttings are instances where these types of drains are required. 10.3 Cross Sections Normally, the cross section design for a road is determined by the geometric standards applied to the project and includes any special circumstances such as problem soils. Standard principles and designs are given in Parts I and II of the Kenya Design Manuals. 10.3.1 Edge Restraint The edges of the roadbase must be given sufficient lateral support, so that they can support heavy vehicles. This problem is particularly serious in the case of non cohesive materials, such as graded crushed stone. Proper compaction of the edges is in any case difficult and lower densities frequently result. Two alternative solutions are available: Lay a base wider than the bituminous surfacing, so that the base edges are not trafficked. The extra width shall be 200 - 300 mm on each side. It shall be primed and sealed, together with the inner edge of shoulder (total width of edge seal: 400 - 600 mm). Alternatively, concrete kerbs may be placed. However, they are expensive and are justified only when graded crushed stone bases are used, or in urban areas. Moreover, they create a discontinuity along the edges, with possible cracking and subsequent water ingress. Kerbs along roadbases are therefore recommended only where a pervious subbase is laid. 10.3.2 Recommended Cross-Sections 10.3.2.1 Normal shoulders (width ≥ 1.5m) Resulting from the above considerations, recommended pavement cross-sections are shown below: Figure 10.1: Shoulder cross sections The Republic of Kenya – Ministry of Roads 113 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 114 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Type A normally applies to roads with bases comprising one of the following materials: plastic natural gravel cement or lime improved material cement stabilized gravel bitumen stabilized silty or clayey sand dense bitumen macadam lean concrete Type B applies to roads with graded crushed stone or non-plastic gravel bases and impervious subbases, when the base is not more than 150mm thick. Type C applies to roads with graded crushed stone or non-plastic gravel bases and pervious subbases. It may also be chosen for roads with cement or bitumen-treated bases, if the base impermeability is uncertain or if extending the subbase is found to be a simpler construction procedure. Type D applies to roads with graded crushed stone or non-plastic gravel bases and impervious subbases. Since the drainage layer and the upper shoulder must not be less than 75 mm thick, this cross-section is suitable only when the base thickness exceeds 150mm. Type E applies to cohesionless or low cohesion base materials with pervious subbases. It should be noted that the list of pavement cross sections given in this Manual is not exhaustive. The design engineer may, for technical and/or economic reasons, choose other types of cross-sections, provided the basic requirements for drainage and edge restraint are complied with. 10.3.2.2 Narrow shoulders (width < 1.5m) The base and subbase should be extended right across the shoulders. This type of pavement cross-section is referred to as “Type X” The Republic of Kenya – Ministry of Roads 115 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 11 Problem Soils This chapter describes particular subgrade soils which can be a problem to the highway engineer in road construction. They are described as ‘Low strength soils’, ‘Expansive soils’, ‘Saline soils’ and ‘Organic’ soils. 11.1 Low Strength Soils Soils with CBR < 3%, or < 2% in arid areas, occurring within the design depth, are defined as ‘Low Strength Soils’. Before they can be included in the foundation structure they require treatment which can include one or several of the following measures: Removal and replacement Chemical stabilisation with either lime and/or cement Mechanical stabilisation, or Raising of the vertical alignment to increase cover, thereby re-defining the design depth Details regarding the treatment of such soils will vary according to soil properties, site conditions, available equipment, alternative materials and parallel experience and will be determined at the time of the project. 11.2 Expansive Soils 11.2.1 Definition Otherwise known as ‘black cotton soil’ because of its characteristic appearance, the main property of expansive soil is the significant volume changes it undergoes when wetted and dried. When a road is sealed a strip of land is created under the road which is protected from seasonal variation of rainfall. The centre of the strip will be subject to different moisture (and therefore volume) changes. This can result in longitudinal cracking along the road edges if it is founded on black cotton soil, which become more accentuated with time and progressively extend towards the center of the road. Figure 11.1: Moisture Variation in Expansive Soils The Republic of Kenya – Ministry of Roads 116 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 11.2.2 Part 3 - Materials and Pavement Distribution It is believed that the primary source of residual expansive clay soils is the in situ weathering of basic igneous, metamorphic and pyroclastic rocks, which occur in abundance in Kenya. Thus, expansive soil is quite common and local knowledge is very useful to identify areas where it can be a problem. Typically it forms in flat, poorly drained environments which favour the formation of the expansive soil minerals. 11.2.3 Identification Apart from their appearance other indicators of expansive soils are described in Table 11.1: Table 11.1: Indicators of Expansive Soils Soil Description Soil Type Consistency, when slightly moist to dry Consistency, when wet Structure Colour Typical Features of Expansive Soils The more clayey, the more likely to be expansive Stiff or very stiff Soft and sticky Cracked surface and slickensided fissures Usually dark but this is not always so The shrinking and swelling property is caused by the preponderance of the clay mineral montmorillonite. There is no quantitative test to determine the amount of montmorillonite present but normal classification tests enable the severity of the expansiveness to be established, as explained below. It has been found that the ratio of Plasticity Index to clay fraction is more or less constant for any one soil, but this constant varies depending on clay type. The correlation between PI and clay type is termed ‘Activity’, where: Activity = PI/clay fraction To be consistent, the clay fraction is expressed as that portion of the soil sample passing the 0.425mm sieve, rather than the percentage passing 2µm. On this basis clays can be classified into four groups as shown in Table 11.2. The Republic of Kenya – Ministry of Roads 117 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Table 11.2: Activity of clays Description Inactive clays Normal clays Active clays Highly active clays Activity <0.75 0.75 to 1.25 1.25 to 2 >2 If the presence of active or highly active clays is established, further testing involving the determination of the Shrinkage Limit (KS 999 Part 2: 2001) is advisable. The Expansiveness, ex, is calculated from the following empirical formula: ex = 2.4*Wp – 3.9*Ws + 32.5 where Wp = Plastic Limit * fraction passing the 425m sieve/100 and Ws = Shrinkage Limit * fraction passing the 425m sieve/100 Expansiveness is then classified according to Table 11.2: Table 11.3: Degree of Expansiveness of Expansive Soils Expansiveness, ex <20 20 to 50 >50 11.2.4 Classification Low Medium High Remediation Four possible treatments are possible to overcome the problem of expansive soils: avoid by re-alignment excavate and replace with non-expansive materials stabilise with lime, or minimise moisture changes by engineering measures 11.2.4.1 Re-alignment This is only possible if the expansive soil is limited in extent. 11.2.4.2 Replacement This is the simplest and most effective treatment but the cost and effect on the environment by sidecasting large quantities of material must be assessed. Indeed, in Kenya the thickness of black cotton soil is usually between 1 to 1.2m and it is underlain by weathered igneous rock (phonolite in Nairobi area) which can be used as backfill. In practice it is sufficient to remove the expansive soil to a depth of 1m. Even if some expansive clay remains it should be adequately confined and protected from moisture changes. The backfill should be at least of S2 quality and impermeable enough not to act as a drain. Embankments should be constructed with suitable fill material as discussed later. The Republic of Kenya – Ministry of Roads 118 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 11.2.4.3 Stabilisation If proper mixing can be achieved, treatment of expansive soil with 4% to 6% of hydrated lime is usually effective and provides the following improvements: reduces the Plasticity Index to less than 20 increases considerably the Shrinkage Limit reduces Swell to negligible values, and increases the CBR to minimum of 10 (after 7 days cure) and 15 (after 28 days cure) alters the grading by agglomeration of the clay particles similar to that of a silt All these improvements render the treated soil easily workable and it can be assumed that it will become of S4 quality. However, it is costly because a substantial thickness must be treated (minimum 300mm) and therefore is advantageous where no suitable backfill or improved subgrade material exists, or there are strong environmental objections to sidecasting large amounts of expansive soil. The mixing procedure is to add the lime in two or three increments, followed by intense mixing by pulvimixer. The mixed soil should be left fallow for two to three days between each mixing operation to enable the lime to take effect. Wet weather makes initiating this operation impossible owing to the physical nature of the soil. 11.2.4.4 Engineering Measures for Construction on Expansive Soils If none of the above measures can be avoided, special precautions are required to avoid damage to the road structure caused by detrimental volume changes when building on or with expansive soils. Widening of shoulders is beneficial whenever economically feasible. The zone of seasonal moisture (and volume) change is thus moved further away from the carriageway. Side drains, if required, should be placed at a minimum distance of 4 to 6 m, depending on road category (Category A roads requiring 6 m). Side fill consisting of expansive soil requires protection from erosion by grasses but no trees should be planted or allowed to root on the embankment slope. Table 11.3 proposes alternative methods of construction over expansive soil: Table 11.4: Construction on Expansive Soils Expansiveness Low ex<20 Medium ex20-50 High ex>50 Alternative proposed construction over expansive soil Paved Trunk Roads Other Paved Roads Sealed shoulders Side slopes 1:6* As normal design See Fig 11.2 Sealed shoulders Side slopes 1:6 minimum Earthworks cover min 1m Earthworks cover min 0.6m See Fig Excavate and replace 0.6m clay as Fig Earthworks cover min 1m Sealed shoulders Side slopes 1:6 min The Republic of Kenya – Ministry of Roads 119 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Shoulder width min 2m Alternative: None Part 3 - Materials and Pavement Alternative: Sealed shoulders Shoulder width min 2m Earthworks cover min 1m Side slopes min 1:6 * Where the earthworks cover is > 2m the side slopes can be made maximum 1:4 Processing and compaction of expansive soils does not reduce their swell properties and their strength is not significantly increased. Attempts to adjust the moisture content, eg to achieve an optimum are time-consuming, impractical and unnecessary. Nominal rolling of the roadbed is desirable to obtain a working surface for construction of pavement layers. Fill materials used for replacement of expansive soil should meet the specifications for fill. Plastic soils with minimum PI of 15 should be used when available at economic haulage distances. Figure 11.2: Alternative methods of construction on Expansive Soil 11.3 Saline Soils The presence of soluble salts, ie NaCl, Na2CO3, NaHCO3, (but not gypsum, Na2SO4, which is only slightly soluble) in pavement or earthwork materials, or more critically in the subgrade and/or groundwater can cause damage to prime coats and thin surfacings. This is a The Republic of Kenya – Ministry of Roads 120 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement significant risk in arid climates because of the migration of these salts to the surface as a result of evaporation. Coastal areas, or possibly areas in the vicinity of the saline lakes in Kenya, are most at risk from this mode of damage. The content of soluble salt can be rapidly but indirectly determined by laboratory or field determination of electrical conductivity. It is prudent to determine the precise configuration of soluble salts by chemical analysis on a few samples and relate this to the conductivity. If the tests are carried out on potential pavement materials, rather than subgrade, construction water should be added at 1.5 times the required amount to obtain the OMC, to allow for evaporation, before the sample is tested. Prime coats are very vulnerable to the formation of blisters in the bituminous surfacing and by fretting of the edges of the surfacing. If the soluble salt content, measured as % Total Soluble Salt (TSS), exceeds approximately 0.3% in the upper 50mm of the road base, they are susceptible to damage. Cutback prime is more vulnerable than emulsion prime. Blistering damage is accelerated if the road is low-trafficked. Surface dressing is more resistant to attack. Single and double surface dressings are not susceptible to damage unless the %TSS exceeds 1.0%; however, if surface dressings are constructed on saline subgrades, it is recommended that an impermeable fabric be placed beneath the road base to prevent the upward rise of salt and protect the surface dressing from eventual salt damage. If the road is well trafficked, the susceptibility to damage is reduced. 11.4 Organic Soils These commonly occur in swamp areas and require special investigations to evaluate ground stability and potential for excessive settlement. Typically, remediation consists of surcharging the pavement structure for a specified time before removing the surcharge and constructing the pavement. Other remediation measures comprise removal and replacement of the organic soil or, in extreme cases, construction of the road ‘floating‘ on the swamp material. A high content of organic matter (>2%) is undesirable in pavement materials, particularly in stabilized layers because it causes increased demand for stabilizer to achieve the required strength. The Republic of Kenya – Ministry of Roads 121 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 12 Gravel Roads 12.1 Introduction Approximately 80% of the road network length in Kenya is of earth or gravel type and therefore their construction justifies some consideration. Earth roads consist of tracks made from the in situ soil and are normally suitable for light traffic in dry weather. The provision of a gravel surface is part of the process in making an all-weather road designed to particular standards of alignment and traffic-carrying capacity. However, there is no doubt regarding the shortcomings of earth and gravel roads. In dry weather they can be very dusty. Unless they are well maintained their surfaces can become corrugated and potholed, and impassable in wet weather. The ideal material for surfacing gravel roads is clayey gravel or clayey sand which should be found in the local area. However, in many parts of Kenya suitable gravel sources are in short supply, often necessitating considerable haulage, and this situation is made worse because the gravel is progressively lost by the action of traffic, at a rate of roughly 10 to 30mm per 100 ADT, and has to be replaced. Vehicle operating costs are higher on earth and gravel roads than on roads with permanent surfacings. Road accidents probably occur more frequently. Thus, there are powerful incentives in all countries to increase the proportion of permanently surfaced roads. The mechanism of deterioration of gravel roads is directly related to the number of vehicles using the road rather than the number of equivalent standard axles. The traffic volume is therefore used in the design of unpaved roads, as opposed to paved roads where traffic volumes are converted into a cumulative number of equivalent standard axles. For earth and gravel roads maximum traffic volumes up to approximately 300ADT are typical, after which construction of a permanent surfacing is considered. 12.2 Design Elements of Gravel Roads The elements of a gravel road are illustrated in Figure 12.1: Figure 12.1: Elements of a Gravel Road The Republic of Kenya – Ministry of Roads 122 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Subgrade Part 3 - Materials and Pavement Gravel Wearing Course Capping Layer (If required) Roadbed (Where no embankment is used) Fig. 1.1 Elements of a Gravel Pavement The deterioration of gravel roads differs from those of permanently-surfaced roads. In this context, the main purposes of the gravel wearing course are: to enable all-weather trafficking, and to protect the sub-grade from undue strain However, the potential defects of a gravel road require other considerations in their design. Typical defects affecting gravel roads include dustiness, potholes, stoniness, corrugations, ruts, cracks, ravelling (formation of loose material), erosion, slipperiness, impassibility and loss of wearing course material. Many of these have a direct effect on the road roughness and safety. A major problem for unpaved roads built on steep alignments is the efficient removal of surface water to the side drains. As the gradients increase, the problem becomes more acute irrespective of any increase in the cross-fall of the road. The problem of gulley erosion along the centre of unpaved roads will be exacerbated as vertical gradients increase above the value of the cross-fall. The cross-fall of the carriageway and shoulders of gravel roads should range between 4 and 6%. Although proper drainage is very important for gravel roads, an excessive cross-fall could cause erosion of the surface. Erosion is frequently manifested in the form of longitudinal gullies along the surface of steep roads with gradients higher than about 5%. Construction of both the carriageway and shoulders of gravel roads should be identical. 12.3 Design of Gravel Roads It is recommended that pavement and improved subgrade for major gravel roads (>50ADT) should be constructed in accordance with Table 12.1: The Republic of Kenya – Ministry of Roads 123 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Table 12.1: Subgrade design for Gravel Roads Subgrade < 50 ADT Class S3 150mm GW S2 150mm GW S1 Dry 150mm GW 150mm S2 Wet 150mm GW 300mm S2 50 to 100 ADT 100 to 300 ADT 150mm GW 150mm GW 100mm S3 Dry 150mm GW 150mm S3 150mm S2 150mm GW 150mm GW 150mm S3 Dry 150mm GW 150mm S3 150mm S2 Wet 150mm GW 200mm S3 200mm S2 Wet 150mm GW 200mm S3 300mm S2 The use of an improved sub-grade has the following advantages: provides extra protection under heavy axle loads protects underlying earthworks provides a running surface for construction traffic assists compaction of upper pavement layers provides homogenous sub-grade strength acts as a drainage filter layer, and enables more economical use of available gravel materials. It is assumed that 50% of the ADT will be ‘heavy’ vehicles, defined as having an unladen weight of > 3 tonnes, or buses with > 40 seats. Roads with approximately < 50 ADT are normally earth roads built by labour-based methods. However, for subgrade values of Class S1 and longitudinal gradients of > 6%, a gravel wearing course is recommended. 12.4 Material Specifications 12.4.1 Gravel wearing course materials (GW) These materials are required to have the following, somewhat conflicting, requirements: sufficient cohesion to prevent ravelling and corrugating, especially in dry conditions, and a limited amount of fines, particularly plastic fines, to avoid slipperiness in wet conditions. Table 12.2 shows the essential characteristics required: Table 12.2: Material specifications for Gravel Roads Grading, sieve size, mm % passing 37.5 Class 1 Class 2 - 100 The Republic of Kenya – Ministry of Roads 124 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 28 20 14 10 5 2 1 0.425 0.075 Plasticity Index (PI) Linear Shrinkage (alternative to PI) Grading Coefficient Shrinkage Product Bearing Strength CBR at 95% T180 Note: Part 3 - Materials and Pavement 100 95-100 95-100 85-100 80-100 65-100 65-100 55-100 45-85 35-92 30-68 23-77 25-56 18-62 18-44 14-50 12-32 10-40 Wet Areas: 5 to 20 Dry Areas: 10 to 30 Wet Areas: 3 to 10 Dry Areas: 5 to 15 16 to 34 120 to 400 >20 (soaked for wet areas) >20 (at OMC for dry areas) Grading Coefficient = [(%passing 28mm) – (%passing 0.425mm) x (%passing 5mm)]/100 Shrinkage Product = Linear Shrinkage x (%passing 0.425mm ) Local knowledge of performance may enable materials outside of the recommended specifications to be used. In particular, rejected quarry materials fall into this category. In Kenya, these usually consist of weathered volcanic rocks, whose grading and physical properties vary according to the degree of weathering and which may be further changed by compaction during construction. However, suitable material is hard, angular and durable and should be free of organic matter and lumps of clay. Figure 12.1 illustrates the performance characteristics expected of gravel wearing course materials. Figure 12.2: Performance Characteristics of Gravel Wearing Courses The Republic of Kenya – Ministry of Roads 125 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 12.4.2 Part 3 - Materials and Pavement Subgrade materials (S2, S3) The subgrade of the gravel road is classified according to its CBR strength as shown in Table 13.3: Table 12.3: Gravel road Subgrade Classification Subgrade CBRdesign % Class Wet Zones 4 day soaked S3 >15 S2 7 to 14 S1 3 to 6 Density for CBR determination (% of MDD) Dry Zones OMC 4 day soaked >15 >7 95% of AASHTO T180 7 to 14 3 to 14 93% of AASHTO T180 3 to 6 2 to 6 100% of AASHTO T90 Note: BS-Light compaction effort is used on poor in-situ soils and deep in-situ soils rather than BS-Heavy due to its better correspondence with the actual effect from compaction equipment under conditions with poor support for compaction. Depending on the CBRdesign of the sub-grade, improved sub-grade layers may be required, on which the gravel wearing course is placed. Soils used in improved subgrade layers shall be non-expansive and free from any deleterious matter. Laboratory test results shall meet the requirements in Table 13.4: Table 12.4: Improved Subgrade Specifications for Gravel Roads Material properties CBR, %, wet climate zone CBR, %, dry climate zone CBR swell, % PI Max. particle size Compacted layer thickness S3 (Upper Layer) >15 after 4 days soak >15 at OMC >7 after 4 days soak <1.5 <25 ⅔ of layer thickness 250mm max. S2 (Lower Layer) >7 after 4 days soak >7 at OMC >3 after 4 days soak <2.0 <30 ⅔ of layer thickness 250mm max. Note: CBR swell is measured at 100% of AASHTO T180 12.5 Deterioration and Maintenance 12.5.1 Gravel Loss and Recharge According to research carried out in the 1970s in Kenya, the annual loss of gravel on a gravel road is a function of traffic volume, rainfall, gravel type and geometric variation. The interaction between traffic and rainfall contributes significantly to the loss of gravel. Annual gravel loss varies between 10 mm and 30 mm per 100 ADT, depending on climate and road alignment. Fig 12.2 illustrates how loss rates for laterite gravel may vary with rainfall. Figure 12.3: Variation of gravel loss with rainfall The Republic of Kenya – Ministry of Roads 126 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement The wearing course of a new gravel road has a thickness D calculated from: D = D1 + N. GL D1 is the minimum thickness calculated from Figure N is the period between re-gravelling operations in years GL is the annual gravel loss Re-gravelling operations should be planned to ensure that the actual gravel thickness never falls below about 0.5 D1. 12.5.2 Maintenance Periodic dragging and grading must be used to preserve a reasonably even running surface on gravel roads. Dragging is a dry season task using tractor-towed brooms, drags or sledges to redistribute loose material over the road surface and reduce the rate at which corrugations occur. Grading is a wet season task using motor graders to restore the running surface and bring back some of the gravel lost to the sides of the road. The road surface is loosened to the depth of the corrugations, the ‘lost’ material reclaimed and the mixture spread to the correct camber over the running surface. The material can either be left loose to be compacted by traffic or watered and rolled, an activity which will significantly reduce the rate at which corrugations appear. In dry weather dust raised by traffic can be a serious problem, especially in populated areas. Some relief, albeit temporary, can be obtained by spraying with water but this must be kept up. The addition of salts, such as calcium chloride or common salt, to the water act to retain moisture in the surfacing providing the relative humidity is sufficient The Republic of Kenya – Ministry of Roads 127 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement but, of course, they are removed by rain. Certain organic compounds, for example the liquor which is a by-product of paper making or waste molasses from sugar cane production are effective for longer. Waste mineral oil can also be used but the surface becomes slippery when wet and the benefit is lost after re-grading. The Republic of Kenya – Ministry of Roads 128 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 13 Concrete Roads 13.1 Introduction This Chapter presents summary guidance and recommendations for engineers responsible for the design of concrete pavements. Hitherto there has been little interest in constructing concrete pavements in Kenya, owing principally to lack of familiarity and expertise to build them compared to asphalt roads. Although their construction cost may be higher than asphalt pavements, once properly built, however, their maintenance costs are potentially significantly lower. Concrete roads are popular in other countries: in the Philippines they comprise over 75% by length of the road network, including low volume roads, whilst in the Mekong delta in Vietnam they are the normal means of road construction for all types of roads. In Chile, concrete road building is firmly established, largely because of the initiative of local cement manufacturers in promoting the training of engineers and workmen in concrete technology. It is a characteristic of concrete pavements that either they are a great success, lasting many years without much attention, or they are a problem from the start, sometimes because of design faults but more often because of construction faults. Misaligned dowel bars can cause early trouble and concrete of inadequate strength can be broken up quickly under heavy traffic loads, the main justification for their proposed construction in Kenya. In recent years there has been concern regarding the premature failure of some of the major asphalt roads in Kenya, manifested in spectacular rutting. Although this is probably a result of either inappropriate asphalt mix design or implementation, or both, and while modern developments have sought to mitigate the problem of asphalt failure, there has lately been renewed interest in concrete for use on heavily trafficked roads. Pilot concrete road trials have recently been constructed in Kenya. In August 2006 about 4km of dual carriageway (Mbagathi Way) in Nairobi was reconstructed with a concrete pavement (the cement being donated by Bamburi Cement Co). In March 2007 the Gilgil weighbridge facility near Naivasha, 200m long by 22m wide, was reconstructed with a concrete pavement (with an EU grant). The performance of these two projects is currently being monitored. The Appendix contains details of the construction of Mbagathi Way. There are environmental advantages to be gained from constructing concrete road pavements compared to asphalt. Firstly, owing to its pale colour, concrete is safer than asphalt roads because it increases visibility, especially at night. Secondly, a concrete surface will also reflect heat energy better than asphalt, which will be beneficial to the passage of vehicles in hot climates. Thirdly, vehicles travelling on concrete surfaces require in general less energy for propulsion than asphalt. Fuel savings between 10-20% are indicated. Disadvantages include traffic noise and the relative difficulty of repairing concrete roads compared to asphalt. This Volume contains a: description of the different types of concrete pavements, their components and functions The Republic of Kenya – Ministry of Roads 129 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement factors influencing the design process and selection of pavement type, and design procedure for the pavement type, slab reinforcement and joint details. 13.2 Concrete Pavement Characteristics & Types 13.2.1 Characteristics The strength of a concrete pavement derives mainly from the concrete itself, unlike asphalt pavements where successive layers contribute to the overall strength. Concrete is a rigid material, considerably stronger in compression than in tension so the fundamental design objective is to ensure that the stresses imposed by traffic and induced by thermal expansion and contraction can be endured by the concrete without it fracturing. Concrete can be damaged chemically by deleterious salts, either contained in the aggregate or entering from outside, but in their absence concrete does not deteriorate from tropical weathering. Concrete pavements are stressed by variation in temperature, and to a lesser extent by moisture content, because of the volume changes that occur. Where concrete is exposed, the volume changes must be accommodated by expansion and contraction joints, the spacings of which are determined by the temperature variation range. In humid tropical regions with only small temperature fluctuations, joints can be quite widely spaced but in deserts there are large fluctuations of temperature and special attention to joint design and spacing is required. Probably it is not appropriate to consider concrete pavements for the more arid parts of northern Kenya for this single reason but, in any case, traffic volumes are small here and concrete pavements could not be economically justified. Skid resistance of concrete pavement surfaces is important and must be adequate both at construction and maintained at regular intervals thereafter. Figure 13.1: Effects of Temperature on Concrete The Republic of Kenya – Ministry of Roads 130 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 13.3 Types Concrete pavements are categorized into three different types: Jointed Unreinforced (JUCP) Jointed Reinforced (JRCP) Continuously Reinforced (CRCP) In JUCP pavements the concrete is cast in predetermined slabs separated by joints to control the cracking. The slabs are connected by dowels, to transmit the vertical stresses more evenly, and tie bars, to connect them together. In JRCP pavements the concrete is cast in slabs and reinforced with steel bars. The slabs are placed and separated by joints to control the cracks. The slabs are connected by dowels and tie bars as for JUCP pavements. JRCP pavements are used where it is suspected that soil movement below the slab will cause it to crack. Longitudinal reinforcement is the main characteristic but transverse reinforcement is added to assist the placing of the former. CRCP pavements are the highest cost but should incur the least maintenance. They are normally constructed on the highest traffic roads where a good quality (ie least bumpy) finish is required. The main reinforcement is either prefabricated steel mesh or longitudinal steel bars installed at mid-depth in the slab and which is used to control cracks induced by volume changes. 13.4 Pavement Components and Functions 13.4.1 Subgrade and Sub-base The load bearing capacity of the subgrade (=foundation) is not so important in concrete road design. The main requirement is to provide a foundation on which construction traffic can operate without injuring the shape to which it has been trimmed. Subgrades with CBR >30 are suitable, except they must be free draining because eventually water will enter the pavement through the joints; when it does it must be able to drain away, otherwise ‘mud-pumping’ will occur as heavy vehicles pass from one slab to the next. If a sub-base is laid, it must also be free-draining and should continue through the road shoulder. In Kenya it is likely that concrete roads will be constructed on old, probably reconstituted, asphalt pavements: obviously, in this situation subgrade strength will be > 30% CBR but it is reiterated that attention should be paid to the drainage condition. Fig 13.2 shows that concrete pavements generally consist of a sub-base and slab constructed on the subgrade, or foundation. (The foundation can also be an embankment). The foundation consists of the roadbed and, if the roadbed is weak (CBR < 15), a capping layer comprising selected fill is required which serves to protect the subgrade during the construction period. The sub-base performs the following functions: acts as a free-draining layer and prevent ‘pumping’ of water at joints and edges of slabs provides a stable construction platform and uniform slab support, and moderates any shrink or swell of the subgrade. The Republic of Kenya – Ministry of Roads 131 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement If the roadbed material is strong enough and the design traffic relatively low, a subbase may not be necessary but it is important that the layer immediately below the slab is free-draining. Subbase materials shall be granular and non-plastic and can be cement stabilised to enhance their properties. Figure 13.2 Structure of Concrete Pavement 13.4.2 Concrete Slab The slab consists of Portland cement concrete, reinforcing steel (optionally), load transfer devices (dowels), tie bars and joint sealants. 13.4.2.1 Portland Cement Concrete The main influences on the structural performance of concrete in roads are the strength of the concrete and its coefficient of thermal expansion. For concrete to harden satisfactorily the cement must be sound, the mixture of cement and aggregate properly designed, the water: cement ratio carefully controlled, and the concrete well compacted and kept moist during the curing period. The initial setting of the concrete is accelerated at high temperatures and this requires that particular care is necessary in tropical climates to compact the concrete before initial setting has occurred and keep it moist during curing. In drier climates, special measures are required to protect the concrete for at least 7 days after placing. 13.4.2.1.1 Cement The cement should conform to KS EAS 18-1. In addition, unless cement is properly stored and used in a fresh condition, the concrete quality will be substantially reduced. The Republic of Kenya – Ministry of Roads 132 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Cement that has lost strength due to hydration before use is characterized by the formation of lumps. 13.4.2.1.2 Water The water used for concrete preparation should be potable and should ideally conform to the requirements of BS EN 1008. 13.4.2.1.3 Aggregate KS 95 2003 specifies the quality and grading requirements for aggregates suitable for concrete production. It is clearly an advantage to use aggregates with low coefficient of thermal expansion and in Table 13.1 the effect of aggregate on this parameter is given. Table 13.0.1: Coefficient of Expansion of various aggregates Aggregate used Quartzite Granite/gneiss Basalt Limestone/marble Coefficient of Expansion of Concrete, per 0C *10-6 Range Average 11.7 to 14.6 13.2 8.1 to 10.3 11.4 7.9 to 10.4 9.2 4.3 to 10.3 7.3 From Table 13.1 it is clear that limestone would be the most suitable aggregate but it is not common in Kenya and has a low Polished Stone Value and would not be suitable for the surface of concrete roads. Obviously it is important to use tough and durable aggregate and especially important to limit the proportion of flaky and elongate particles, an excessive amount of which can prejudice concrete compaction and strength. It is preferable to use aggregate with nominal maximum size >25mm for better load transfer across slabs. Higher concrete strengths and better shrinkage reduction are attained with the larger aggregate sizes but the maximum aggregate size is a function of the slab thickness. Sometimes the maximum aggregate size is restricted to 20mm to minimise the risk of segregation. Table 13.2 presents general limits for aggregate sizes and gradings but reference should be made to KS 95 2003 for details. Table 13.2: Aggregate Sizes and Gradings for OPC Concrete Sieve size (mm) Percentage by Mass of Total Aggregate Passing Sieve Coarse Aggregate 40mm down 50 37.5 20 14 10 5 2.36 100 90-100 35-70 10-40 0-5 Fine Aggregate 20mm down 100 90-100 40-80 30-60 0-10 All-in Aggregate 40mm down 100 30-100 60-100 The Republic of Kenya – Ministry of Roads 133 20mm down 100 95-100 45-80 100 95-100 25-50 35-55 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 1.18 0.6 0.3 0.15 30-100 15-100 5-7 0-10 Part 3 - Materials and Pavement 8-30 10-35 0-8 0-8 13.4.2.1.4 Concrete itself Stresses from traffic loads require consideration of the modulus of rupture (or flexural strength) but, although this parameter has a greater influence on the structural performance of concrete, it is more difficult to measure than compressive strength. Thus, typical compressive strengths specified are 30 MPa (N/mm2) at 7 days and 40 MPa at 28 days, with the tests performed on 150mm cubes under standard conditions (test KS 02595-1986). The correlation between modulus of rupture and compressive strength depends on the aggregate type and shape; the amount of elongate or flaky aggregate particles adversely affects the modulus of rupture. Normally, concrete made with natural aggregate is inferior in strength to that made with crushed rock. The mechanical strength required for aggregate for pavement concrete is similar to that required for bituminous road bases. Regarding the fine aggregate, it is better if possible to use material with gradings towards the coarse end of the envelope, in order to improve workability. All-in aggregate, ie crusher-run stone is also commonly used.2 The (compacted) concrete will normally consist of between 250 to 350 kg/m3 of Ordinary Portland Cement, coarse and fine aggregate, the precise proportions of which are determined during design by compressive strength tests. To control workability the tendency is always to increase the added water but it is crucial to keep the water: cement ratio below 0.5, otherwise the concrete will have insufficient strength and durability. For small contracts, the workability is measured using the slump cone test (KS 02-595-1986), where a standard cone is filled with wet concrete, the cone lifted and the concrete allowed to subside. The slump is then the difference between the cone height and the highest point of the slumped concrete. It should be limited to 75mm. However, with the lean and dry mixtures used in roads, the test is not very discerning in identifying variations, and the more precise compacting factor test is better for large contracts. In this test, there are two cones one above the other. The uppermost cone is filled with concrete and then allowed to fall into and overflow the lower, smaller cone. Its surface is then leveled and the concrete then allowed to fall into a basal cylinder. The bulk density of the contents of this cylinder is then measured to measure the compaction produced by the energy of the falling concrete. The principles of concrete compaction are similar to that of soils. A mix too dry is difficult to compact. A mix too wet renders the maximum density impossible to achieve. Once the mix proportions have been specified and the method of compaction selected there is normally no need to determine the densities achieved in the compacted concrete. However, in particular with the thicker slabs, there is a tendency for segregation with the larger particles falling to the bottom of the slab. This risk is greatest when the concrete is too wet. This is the reason for limiting the maximum aggregate size to 20mm. 2 The following approximate correlation is useful: Flexural Strength (MPa) = c√Compressive Strength, where c ≈ 0.75. Values of Flexural Strength ranging from 3.8 to 4.5 after 28 days are usually acceptable for concrete in roads. The Republic of Kenya – Ministry of Roads 134 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 13.4.2.2 Reinforcing Steel 13.4.2.2.1 General Cracks in concrete develop by: temperature and/or moisture-related contractions and expansions, and frictional resistance between the slab base and underlying layer Tensile stresses result, maximizing at mid-slab, and if they exceed the tensile strength of the concrete, it cracks transversally and the stress is transferred to the reinforcing steel if present. The purpose of the (longitudinal) reinforcing steel is to control concrete cracking and hold the cracks tightly closed, maintaining the pavement as an integral unit. In general the amount of steel is small, and is insufficient to add to the flexural strength of the concrete slab and thus the structural strength of the pavement. Transverse reinforcing steel is used to ensure that the longitudinal reinforcing steel remains in the correct position during slab construction and also mitigates any longitudinal cracking that could eventually occur. The selection of JUCP, JRCP or CRCP is a function of the pavement slab length. For joint spacing less than 5 meters, transverse cracking is not expected and reinforcement normally not required, therefore JUCP pavements are appropriate. For joint spacing between 5 and 15 meters, reinforcement is required, increasing in amount in proportion to the slab length, although the increasing cost of reinforcement is offset by a decreasing amount of joint dowels and sealants. The upper limit of 15m also allows slab and joint movements to be restricted and riding quality optimized. Beyond 15m CRCP pavements are recommended, with no joints but a considerably greater amount of reinforcing steel than JRCP. The choice between the different concrete pavement types is fundamentally an economic one and a balance of traffic levels, construction cost and maintenance interventions. 13.4.2.2.2 Reinforcing Steel Requirement The area of reinforcing steel in JRCP and CRCP pavements are given by complex equations, to be found in the documents referenced. The same applies to the type and quality of this steel. Needless to say, much more steel is required for CRCP than for JRCP pavements. In order to achieve its intended function it is important that the reinforcement is correctly placed and fixed in position to allow uninterrupted paving operations. The steel should be free of contaminating substances which will prejudice the bond with the concrete. Bonding and anchorage properties are not affected by rust which normally forms on steel after normal exposure but after prolonged storage it will have to be removed. 13.4.2.3 Dowell Bars The most common failures of concrete roads occur at the transverse joints and it is imperative that adequate load transfer support is provided to minimise cracking, spalling and corner breaks. Load transfer support across the slabs is provided by dowels and enhanced by: The Republic of Kenya – Ministry of Roads 135 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement stiff sub-bases large sized coarse aggregate (>25mm) small joint openings, and dowels Dowels are normally 20mm diameter, 400mm long and fitted at about 300mm spacings. Since they are load transfer devices they must be strong and robust and closely spaced to resist bending and shear of the concrete. To allow slabs to move horizontally relative to one another, at least 65% of the dowel must be coated with a bond-breaking compound, eg bitumen. Dowels must not ‘lock’ the joint where they are placed, otherwise an uncontrolled crack may occur close to the joint. End dowels should be at least 200mm distant from the slab edge. It is very important that dowels are aligned parallel with the pavement direction, otherwise strains will be generated that will be cracking and early deterioration of the concrete. Where joint openings are less than 1mm, dowels need not be utilized. For dowelled joints the joint opening should be 6mm or less. Short-slabbed pavements thus do not need dowels but it is common practice to use dowels regardless of joint opening. On roads carrying heavy vehicles it is essential to provide dowels across joints to limit the vertical movement between slabs as vehicles pass over. It is also desirable to use dowels in roads over unconsolidated soils to prevent differential settlements between adjacent slabs. In transverse joints dowels are bonded into the concrete on one side of the joint. Bonding on the other side is prevented, usually by coating the dowels with bitumen and, for expansion joints, by providing a loose end-cap. It is particularly important that they are accurately aligned perpendicular to the face of transverse joints or parallel to the road if the joints are skewed. 13.4.2.4 Tie Bars In contrast to dowels, tie bars are not load-transfer devices but fixing devices whose function is to tie two slabs together. Thus, whereas dowels must be smooth and lubricated on one end to maintain freedom of movement, dowels must be deformed or hooked and firmly anchored in the slab to function properly. Typically they are used to prevent separation at longitudinal joints but at the same time allowing some warping to occur. They hold the joints together so that load transfer is achieved by aggregate interlock in the concrete. Tie bars are generally 12mm diameter, 750mm long and spaced at intervals of 600mm. When the width of the pavement in construction is greater than 4.5m, hinge joints are made. The concrete is sawed to a third of its thickness; the joint is sealed and then tied by inserting tie bars at two thirds slab thickness into the slab. Construction break joints are made by using long (at least 750mm) tie bars to join the old and new concrete. Reference is made to the South African M10 manual which contains details on the length and width of dowels and tie bars. Figure 13.3: Definition of Dowell and Tie Bars The Republic of Kenya – Ministry of Roads 136 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 13.4.2.5 Joints Joints are necessary in concrete pavements in order to relieve stresses that build up in the slab by temperature and/or moisture changes, friction with the underlying layer, and those necessary at the end of a working day. In directional terms there are transverse and longitudinal joints and four joint types are fabricated: Contraction Expansion Warping Construction The different types of joints are illustrated in Fig 13.4. Figure 13.4: Types of Concrete Joints The Republic of Kenya – Ministry of Roads 137 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 13.4.2.5.1 Contraction/Expansion Joints These joints provide weakened sections between slabs to induce tension cracking in the slab. If they were not made random cracking would develop on the pavement surface. They also alleviate the warping strain. The principal requirements are to: induce a crack at a predetermined location and seal it against water and debris ingress permit the joint to open and close transfer loads across the joint Expansion joints are installed to provide space for the expansion of the pavement, thereby preventing the development of compressive stresses, which otherwise would cause the pavement to buckle. They contain joint filler which performs as a spacer during construction. The filler consists of a semi-elastic material, either a fibrous material or soft wood, about 15mm thickness. In concrete spread and compacted by hand, there is a practical advantage in using expansion joints with a softwood filler. A wooden lath, 25mm x 25mm can be nailed to the top of the joint filler and used as a guide to round the joint edges (=arrissing). When the concrete has hardened, the lath is removed to reveal the slot for the sealing compound. Removal of the lath is eased by slightly tapering its cross section. Contraction joints are of two types; 1 which is sawn into the hardened concrete and 2, which developed with the onset of mechanisation, consist of slots sawn across the pavement to about ⅓ of the slab thickness to induce cracks. The raggedness of the crack that develops helps to transfer loads across the joint. The recommended interval between contraction joints is dependent on the shrinkage properties of the concrete, the friction with the subbase and the slab thickness. For The Republic of Kenya – Ministry of Roads 138 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement unreinforced concrete the maximum spacing is 5m. In reinforced concrete a spacing of 25m is recommended. 13.4.2.5.2 Warping Joints The warping joint is placed to provide additional strength against heavy traffic loads in slabs subject to large diurnal temperature variations. It resembles a dummy joint with fixed dowels placed in the concrete where the crack will form and acts, in effect, as a hinge. They are used in situations such as in longitudinal joints or special situations where manholes occur, or in irregular shaped slabs. They allow a slight rotation of the slab portions. Longitudinal joints are always warping joints but they can be found sometimes as transverse joints. The purpose of longitudinal joints is to control longitudinal cracking, which can occur soon after construction. They should be spaced at intervals equivalent to a traffic lane width, i.e about 3.7m, and away from wheel paths to minimize edge loading. CRCP pavements also have longitudinal joints but no transverse joints. 13.4.2.5.3 Construction Joints Construction joints are required when there are interruptions to concrete pouring, such as at the end of a working day. They may be located in the middle third of a slab, in which case a keyed and tied joint is used; or at a planned contraction joint in which case a dowelled joint is used. The new concrete should be jointed to the old concrete by using uncoated tie bars. The length of these tie bars should be at least 750 mm. The intention for the keyed and tied joint is that it becomes an integral part of the slab. The key provides load transfer and tie bars are used to hold the joint tightly closed. It will not normally be necessary to seal this joint. All construction joints should be constructed normal to the longitudinal axis of the pavement. For JUCP and JRCP, they shall be coupled with other joints and additional reinforcement shall be placed when dealing with transverse construction joints for CRCP. 13.4.2.5.4 Other Types of Joints Mis-matched Joints: reinforcing of slabs is necessary where the joint patterns of adjacent pavements do not permit the matching of joints. In such circumstances the mis-matching of the joints can cause cracking in the adjacent pavement slab. Partial slab reinforcement is therefore required in all cases except where an expansion joint is provided between the abutting pavement sections. Where this reinforcement is required, the slab opposite the mis-matched joint is reinforced with steel fabric in a direction at right angles to the mis-matched joint. Acute Angles: at kerb returns, curved edges, or at the perimeter of angle-parking areas joints may form acute angles in the corners of slabs. In these cases there is potential for a crack to form across the acute angle in the slab corner. This can be avoided by offsetting the joint at least 300mm from the curved edge or corner, thus removing the acute angle and reducing the potential for the crack to occur. The Republic of Kenya – Ministry of Roads 139 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 13.4.2.6 Effects of weather on placing of joints With concrete roads constructed in hot weather, contraction predominates as the weather cools. In any subsequent expansion it is unlikely that all the joints will be able to close to their original dimensions. For this reason at least one joint in four should be an expansion joint. With work done in the cool season, all joints should be expansion joints. 13.4.2.7 Joint Protection Most joints should be sealed with materials meeting the Standard Specifications. Transverse joints spaced not more than 4.5 m apart are usually 6 to 8 mm in width and sealed with prefabricated elastomeric compounds. Sealant is applied at the surface; the dimensions of the sealant reservoir depend on the slab length, and hence the movement at the joint, and the sealant properties. Tables 3.3 and 3.4 give details: The edges of the sawn joint slots usually are rounded (=arrissed). In general the depth to width ratio of sealant ranges from 1 to 1.5 and the sealant should be placed 3 mm to 13 mm below the surface of the pavement. As the concrete expands and contracts, these sealing compounds accommodate large strains. The sealant will be compressed between 20 to 50 percent of its normal width. They are unlikely to remain effective in preventing water from entering the joint for more than two or three years. Nevertheless, as long as they remain in place, they fulfill their other important function, which is to prevent loose stones and other debris on the road surface from being wedged in the joint. Stones so wedged, can cause spalling of the edges of the joint as the concrete expands. Table 13.0.3: Reservoir Dimensions for Field Moulded Sealants Joint Spacing (m) Sealant Reservoir Shape Width (mm) Sealant Depth (mm) 5 6 20 6 10 20 10 12 20 12 15 25 Table 13.0.4: Joint & Sealant Width for Pre-formed Compression Seals Joint Spacing (m) 6 10 12 15 Sealant Dimensions Joint Width (mm) Sealant Width (mm) 6 11 10 16 11 20 12 22 Figure 13.4: Types of Joints and Dowell Bars The Republic of Kenya – Ministry of Roads 140 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 13.5 Factors influencing the design process and selection of pavement type In general, the preferences for the different pavement types are as follows: 1. JUCP: this is the cheapest form of concrete pavement and is suitable where the traffic volume, especially the number of commercial vehicles, is low. This pavement type should be constructed in slab lengths less than 5m to retard the (inevitable) development of uncontrolled cracking 2. JRCP: this type of construction is preferred for all levels of traffic and especially if there is an enhanced risk of settlement of the subgrade. 3. CRCP: this type of construction is the most expensive, containing the highest amount of steel reinforcement, and is employed normally for the highest traffic levels The main factors influencing the selection of concrete slab type are as follows: traffic volume and particularly number of commercial vehicles climate, particularly diurnal temperature range subgrade characteristics environment, whether urban or non-urban quality of the available materials Since the initial aim in Kenya would be to construct concrete roads on the more heavily trafficked routes such as the Northern Corridor route, Mombasa-Nairobi-Nakuru-Eldoret, The Republic of Kenya – Ministry of Roads 141 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement where there have been serious shortcomings with asphalt performance, it would be advisable to use reinforced concrete to restrain the development of cracks. Moreover, on these higher altitude routes, the diurnal temperature range will exacerbate the expansion and contraction of the concrete slab. Other possibilities would be the tropical coast routes where temperatures are high and the diurnal range not so extreme. Pilot scale concrete road trials were constructed in the Mombasa area in the 1960s, it is understood with good results. 13.6 Stress Development and Design Criteria Stresses in rigid pavements develop from environmental changes; the temperature and moisture variation throughout the day; and, together with the stress imposed by traffic, deform the slab. The weight and rigidity of the slab resists these stresses until it yields, when cracks are formed. The stresses are defined as of three types: Horizontal tensile Horizontal compressive Vertical Obviously, these stresses cannot be prevented from occurring, and the purpose of concrete pavement design is to keep them within an acceptable range. For all slabs transverse cracking occurs at intermediate positions between the joints and the function of the reinforcing steel is to hold the slab together so that the transfer of the traffic loads will not disrupt the slab. For JUCP the short slab length assists in ensuring that intermediate cracks do not occur. 13.6.1 Horizontal Tensile During the setting period and possibly later depending on the humidity, tensile stresses are induced in the concrete. Subsequently, the acceleration/retardation of traffic also induces horizontal stresses and, since the reaction of the lower surface of the concrete is limited by friction with the subbase, cracks can occur because concrete is comparatively weak in tension. If uncontrolled cracks become too wide, water infiltration to the subbase occurs and degradation of the slab follows. Crack development in JUCP and JRCP is controlled by manufacturing joints at regular intervals and by placing a separation membrane between the slab and the subgrade. In CRCP the continuous reinforcement allows cracks to occur at regular intervals, thus limiting their width to acceptable values. 13.6.2 Horizontal Compressive The compressive stresses are the reverse of the tensile stresses and if they become too high, the slab will buckle. The Republic of Kenya – Ministry of Roads 142 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement The placing of expansion joints and the provision of a separation membrane allow the expansion of concrete and the dissipation of these stresses. 13.6.3 Vertical Vertical stresses occur by the repetitive action of traffic and the weight of the concrete slab on the underlying subbase. 13.7 Concrete Pavement Design 13.7.1 Traffic As with bituminous road pavements, the concept of Equivalent Standard Axles (ESA) is used as an indicator of design traffic loading, with similar reservations regarding the 4th power relationship between axle loading and permanent damage, especially with overloaded vehicles. The damaging effects of heavy vehicles vary according to the time of day but the concrete pavement is most vulnerable at night when the ends of the slabs curl up and behave as unsupported cantilevers (see Fig 2.1). Where traffic includes vehicles with axle loads > 10 tonnes special treatment is advisable to reduce the imposed stresses, which include: Strong load transfer devices across joints Closer joint spacing Use of mesh reinforcement in the concrete Increased slab thickness 13.7.2 Failure Criteria The ultimate condition determining the life of a concrete pavement is the deterioration in riding quality. Before this limit is reached, cracks will have appeared in the concrete surface and the deterioration is expressed in the gradual spreading of these cracks. On lightly trafficked roads, say Traffic Classes up to T3, it may be possible to extend the life of the pavement by applying a bituminous surface to restore riding quality. On more heavily trafficked roads the development of cracks will probably be associated with the breaking up of the concrete to the extent that it must either be removed and replaced or broken down in place to create what is essentially a crushed stone base, the so called ‘crack and seat’ technique . Methods for measuring surface roughness are of limited value in providing criteria for deterioration in riding quality since concrete roads do not usually deteriorate uniformly. Variations in construction quality, often due to varying weather conditions, can produce wide differences in the performance of adjacent lengths of concrete. On the most affected lengths, deterioration can be measured by the amount of cracking, recording the length of narrow and wide cracks per square metre. The rate of development of cracking can thus indicate the timing and extent of repair work necessary. On well designed and constructed concrete roads, cracks may not appear for 20 years or more, progressively intensifying thereafter depending on the traffic loading. Construction faults, for example misaligned dowell bars in joints may cause earlyappearing local areas of disintegration. It is the joints which are the greatest source of The Republic of Kenya – Ministry of Roads 143 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement weakness in concrete roads so the longest lived roads are those where particular care has been taken over the design and construction of joints. 13.7.3 Thickness design The analysis of stresses in concrete pavements by multi-layer elastic theory is simpler than for ‘flexible’ pavements. Westergard produced the first theoretical analysis of the stresses developed in concrete pavements in 1926 and, subsequently, finite element analysis methods have emerged to permit greater precision to the estimation of stresses developed under different loading conditions, see Acum and Fox (1951) and Zienkewicz (1967). If these methods were employed to design concrete road slabs with the same rigour used in structural concrete their application would be relatively simple and would indicate the slab thickness and reinforcement necessary so that the tensile stresses developed in the concrete never exceeded a critical level with a proper safety margin. But such construction would be prohibitively expensive and concrete road slabs are designed with the assumption that fatigue fractures will eventually occur. Safeguards are built into the design so that the effects of the fractures are contained with the roads continuing to give good service for many years after the first cracks have appeared. The theoretical work is useful in identifying the critical points in the slabs where special measures are needed to counteract the effects of tensile fracture but in producing a practical design method there is no substitute better than the observation of performance of concrete roads in the field. 13.7.3.1 Capping Layer and Subbase A capping layer is required only if CBR of the subgrade is < 15%. The required thickness of a capping layer for a subgrade CBR value less than 15% can be obtained from Fig 6.1. The capping layer material shall have a minimum CBR value of 15% at 95% of MDD and OMC of BS Heavy. A sub-base layer is required when the subgrade CBR is< 30% or to obtain the surface levels with the tolerances required. Generally, the thickness of the sub-base provided will be 150 mm and it can consist of cement-stabilized material. The sub-base shall have a minimum CBR value of 30% at 95% of MDD and OMC of BS Heavy. Material for fill should have a CBR swell of less than 2% and a minimum CBR value of 5% at 95% of maximum dry density and optimum moisture content using BS Light compaction. For subgrade CBR values less than 2%, the roadbed material needs to be treated either by replacement or in-situ stabilization. A separation membrane (such as a polythene sheet) is required between sub-base and concrete slab, mainly in order to reduce the friction between the slab and the sub-base in JUCP and JRCP pavements, thus inhibiting the formation of mid-slab cracks. The minimum thickness of the polythene sheet shall be 2.6 mm. It also reduces the loss of water from the fresh concrete. For CRCP pavements, a bituminous spray should be used on the sub-base, instead of polythene, because a degree of restraint is required. Figure 13.5 Relationship between Subgrade Strength and Capping Layer Thickness The Republic of Kenya – Ministry of Roads 144 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement m m 13.7.3.2 Concrete Slab Thickness and Reinforcement The following section presents criteria for determining the thickness and reinforcement for each of the concrete pavement types, based on the design traffic volume. For practical reasons it is undesirable to construct concrete slabs with a thickness less than 125 mm. 13.7.3.2.1 Jointed Unreinforced Concrete Pavement (JUCP) Fig 6.2 presents the design thickness of JUCP concrete slab calculated from the design traffic ESAs. It assumes the presence of an effective lateral support to the edge of the most heavily-trafficked lane, such as a shoulder with a pavement structure able to carry occasional loads. If this shoulder is absent, an additional slab thickness is required, and this additional thickness can be determined from Fig. 6.3. JUCP pavements have no reinforcements for crack control. However, the longitudinal and transverse joints are provided with reinforcements. The joint details are discussed in a previous section. 13.7.3.2.2 Jointed Reinforced Concrete Pavement (JRCP) Fig 6.3 presents the thickness of JRCP concrete slab calculated from the design traffic ESAs. Longitudinal reinforcement steel is used between joints for crack control. The same Figure can also be used to determine the longitudinal reinforcement in terms of The Republic of Kenya – Ministry of Roads 145 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement mm2/m for a design thickness of concrete slab. Thus, several alternate combinations of thickness of concrete slab and amount of reinforcement can be compared. In the absence of an effective lateral support provided by the shoulder adjacent to the most heavily trafficked lane, an additional slab thickness is required and can be determined using Figure 6.4. In addition to the longitudinal reinforcement, JRCP pavements shall be provided with transverse reinforcement, if required, depending on site conditions. In that case, reinforcement shall be provided at 600 mm spacing and consist of 12 mm diameter steel bars. 13.7.3.2.3 Continuously Reinforced Concrete Pavement (CRCP) CRCP pavements can withstand severe stresses induced by differential movements. CRCP contains relatively high percentages of steel and no joints except for construction joints and some expansion joints. Since the pavement contains very few joints it is generally smooth riding and, if the steel is properly designed, it is potentially a lowmaintenance pavement. The minimum and maximum spacing recommended for longitudinal steel is 100 mm and 220 mm respectively and the minimum steel cover recommended is 65 mm. For a traffic volume up to 100M ESAs, the thickness of CRCP concrete slab shall be 200mm . Longitudinal reinforcement in CRCP pavements shall consist of 0.6% of the concrete slab cross-sectional area. The diameter of the bars should not exceed 20 mm and the center-to-center spacing of the bars should not be greater than 225 mm. If required, transverse reinforcement shall be provided to control the width of any longitudinal cracks that may form. The diameter of the bars should not be less than 12 mm and the maximum center-to-center spacing of the bars should not be greater than 750 mm. Transverse reinforcement is normally required only for ease of construction. It may be omitted except where there is a risk of differential settlements. As with JUCP and JRCP pavements, in the absence of effective shoulder support adjacent to the most heavily trafficked lane, the additional slab thickness required can be determined using Fig 6.3. The minimum thickness of concrete pavement for JUCP and JRCP pavement is 150 mm. For CRCP pavements the minimum thickness is 200 mm. Hence, the designer should carefully assess the necessity and requirements for such pavements, depending on the design traffic volume. Figure 13.6: Concrete Slab Design Thicknesses vs Traffic The Republic of Kenya – Ministry of Roads 146 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Figure 13.7: Additional Slab Thickness where no lateral support is present 13.7.3.2.4 Concrete Slabs constructed on old Asphalt Pavements: ‘whitetopping’ Reference is made to a publication by the American Concrete Association on ‘whitetopping’, or overlaying asphalt roads with concrete. The support given by the existing pavement + subgrade must be taken into account in the thickness design of the concrete slab. Figs are nomograms which can be used to estimate the Westergard modulus of subgrade reaction, or k-value, on top of the existing pavement. Fig is for asphalt on a granular base and Fig is for asphalt on a cementtreated base. The asphalt thickness is the residual asphalt remaining after milling of the old surface. Figure 13.8: Slab design thickness for old asphalt road on granular base The Republic of Kenya – Ministry of Roads 147 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Figure 13.9: Slab design thickness for old asphalt road on cement-treated base For Traffic Classes T5 and upwards concrete slab thicknesses ranging from 200mm to 300mm should be satisfactory. For Traffic Classes T4 and below, concrete slab thicknesses between 130mm and 180mm would be appropriate. The Republic of Kenya – Ministry of Roads 148 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 13.8 Construction issues There are three levels of sophistication in the construction of concrete roads. At one extreme there are labour-intensive methods employing a minimum of mechanical plant. In the middle comes the use of mechanical spreaders and finishers with the side-forms being placed to correct line and level. In extreme mechanisation there are slip-form pavers in which the side forms are carried on the machine with wire guidance, or lasers, to secure correct line and level. Increasing mechanisation makes high output possible and good surface finish, but complicates the installation of joints and reinforcement. 13.8.1 Labour Intensive works The minimum plant required, in addition to transport, is a rotating drum mixer and vibrating tamper bar with an appropriate power source. Timber side forms can be locally made and used. Coarse and fine aggregates are apportioned using wooden gaugeboxes, the proportions being set so that the correct cement content can be obtained by adding cement in bags or half-bags. Water is added by volume, using the slump cone test to control workability. A 12 man gang can lay up to 500m2 of concrete per day. In alternate-bay construction, a sequence of operations is established in which alternate bays are constructed on each successive day, facilitating the installation of joints and accurate location of dowell bars. Under a competent foreman, labour intensive works can be very effective and provide gainful employment in regions where unemployment is a problem. 13.8.2 Medium mechanisation works The availability of ready-mixed concrete calls for more mechanisation in spreading and finishing. The ready-mixed concrete should be discharged into a mobile hopper from which the concrete is drawn off into wheelbarrows and raked into an even profile. An additional 10 to 15% of the finished slab thickness is required to allow for compaction. Compaction can be carried out using vibratory equipment, either pokers or vibrating screens working on the side forms. The additional surcharge is regulated automatically using mechanical spreaders and finishers. Even the medium mechanisation works require a substantial investment in plant and equipment and the construction of substantial works is necessary to justify their use. 13.8.3 High mechanisation works Slip-form pavers are the ultimate in the ingenuity of machinery manufacturers but require an enormous effort and investment to mobilise. It is doubtful whether they are appropriate in countries such as Kenya where concrete roads are needed in a few places. 13.8.4 Roller-compacted concrete pavements In this process, mechanical spreaders as used for bituminous materials are used, adapted by increasing the compactive effort of the vibrating screen. The compaction The Republic of Kenya – Ministry of Roads 149 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement process is completed by using steel-wheeled rollers, and joints are cut into the completed concrete. The concrete mixtures are of low workability, with low water: cement ratios. The advantage of this method is that it uses plant which has other uses in road-making, thereby reducing operation costs. 13.8.5 Surface finish A rough surface of the finished concrete is required to give adequate skid resistance and this is achieved by cutting closely spaced (at 2cm spacing) grooves in the hardened concrete. The grooves may be cut in the longitudinal direction or transversally, the advantage of the latter being that it assists drainage, although being much noisier. The noise created by grooved concrete roads is an issue in developed countries and has resulted in concrete roads losing favor. 13.8.5.1 Concreting in hot climates High temperatures increase the rate of hydration of cement. The concrete thus begins to harden rapidly after mixing so that it can become difficult to spread and compact. Also, the rapid early gain in strength can be accompanied by shrinkage and cracking of the concrete with the result that the subsequent gain in strength is much lower than with concrete cured at a lower temperatures. For concrete cured in damp conditions at 200C, normally a gain of about 40% in compressive strength is obtained between 7 and 28 days, with a slight increase afterwards. In contrast, in concrete cured at 500C there is likely to be little gain in strength between 7 and 28 days, with the likelihood of weakening afterwards because of the shrinkage cracks that will have developed. Using more finely ground Portland cement accentuates these effects. Workability during concrete laying can be increased by adding more water but to maintain the concrete strength, more cement is the required. This has disadvantages, apart from cost because of the risk of shrinkage during hydration. Air entraining agents can be used to improve workability and chemical compounds are available to retard the concrete setting, eg sugar, but it should be confirmed that their use is not detrimental to the concrete hardening. The most effective measures involve keeping the concrete components as cool as possible before mixing, protecting the surface of the concrete from the sun if possible and keeping the concrete damp for the first 7 days. 13.9 Maintenance and repair Well built concrete roads should require little maintenance. Nevertheless, it is impossible to keep joints sealed against the entry of water, particularly where there are large daily or seasonal temperature changes, since the the volume changes in the seal slots are too large for the sealing compound to absorb without parting from the concrete. Another problem are loose surface stones. If they become wedged in the top of joints they can cause spalling of the concrete at the edges of joints. Therefore, the joints on concrete roads should be inspected yearly and loose stones removed. Fresh sealing compound may also be required in the joints. The Republic of Kenya – Ministry of Roads 150 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Joints that have become badly spalled can be repaired by cutting out and replacing the damaged concrete but this is a specialised skill and may only be worthwhile on new concrete roads. Restoring transverse grooves in concrete surfaces worn smooth can be done but an alternative is to provide a bituminous surface dressing. Use of polymer-modified bitumen may assist in obtaining a more durable result. Mud-pumping may occur at the joints of more heavily trafficked roads, indicating structural inadequacies in that there is no provision for water to drain away beneath joints. Deterioration can be arrested by drilling holes and placing fresh concrete in the defective foundation. 13.10 References Design Manual for Roads and Bridges (DMRB), Volume 7 (Pavement Design); IAN 73/06 (Foundation Design); HD29 (Surveys & Investigations); HD30 (Maintenance Assessment Procedure); HD32 (Maintenance of Concrete Roads) Manual of Contract Documents for Highway Works (MCHW), Volume 3. Also: www.standardsforhighways.co.uk/dmrb/index.htm and www.standardsforhighways.co.uk/mchw/index.htm Cement & Concrete Association. Australia, Concrete Roads Manual 1997 AASHTO Pavement Design Guide 1993 Whitetopping-State of the Practice: American Concrete Association, 1998 Road Building in the Tropics: HMSO State of the Art Review 9, Millard, 1993 ROAD DESIGN MANUAL: Vol. 3: Pavement Design, Part II: Rigid Pavements. The Republic of Uganda, Ministry of Works, Housing and Communications The Republic of Kenya – Ministry of Roads 151 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Appendix : Construction details for Mbagathi Way, Nairobi The Republic of Kenya – Ministry of Roads 152 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 153 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 154 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 155 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 156 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 157 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 The Republic of Kenya – Ministry of Roads 158 Part 3 - Materials and Pavement Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 14 Materials Sampling and Testing 14.1 Introduction Road design may be divided into three stages, namely feasibility, preliminary design and final design. Normally, there is always a feasibility study but sometimes the preliminary and final design phases are compressed together. This Chapter describes the materials sampling and testing programmes applicable to each design stage. 14.2 Mass of Samples Required The total mass of sample required depends on the tests to be carried out, the grading of the material (its maximum particle size, in particular) and its susceptibility to crushing during compaction. Table 13.2.1 shows the minimum mass of sample required for various sequences of tests and typical materials, including allowance for drying, wastage and rejection of coarse fragments where necessary. 14.2.1 Soil and Gravel Tests required Fine grained soil (max. size 2 mm) Grading * * * Atterberg Limits * * Compaction * CBR (1 point) * CBR (3 points) * Coarse grained gravel (max. size 40 mm) not susceptible to crushing * * * * Coarse grained gravel (max. size 40 mm) Susceptible to crushing * * * * * * * * * * 14.2.2 Property * * * * * * * Treatment Tests Minimum Sample Mass (kg) * * * * * * * * * * * * * * 5 20 35 80 20 * 40 60 150 20 60 80 180 Stone Tests Required The Republic of Kenya – Ministry of Roads 159 Test Number Mass required, kg Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Toughness Cleanliness Durability Skid Resistance Shape Notes Part 3 - Materials and Pavement Aggregate Crushing Value (ACV) 10% Fines Crushing Value (TFV)* Aggregate Impact Value (AIV) Sand Equivalent Value (SEV) % passing 0.075mm sieve Water Absorption (WI)** Magnesium Sulphate Soundness (MSS)*** Polished Stone Value**** (PSV) KS 1238-11: 2003 KS 1238-12: 2003 KS 1238-13: 2003 AASHTO T176 KS KS 1238KS 1238-20: 2003 60 120 (dry + wet) 10 5 5 KS 1238-15: 2003 25 Flakiness Index (FI) Aggregate Angularity (AA) KS 1238-6: 2003 10 25 * Can be determined on wet and dry samples, thus indicating durability, and is preferred to the ACV when testing weaker stone. If AIV is determined first, the approximate correlation TFV = 2800/AIV will indicate the TFV value. ** A good indicator of durability *** Sodium Sulphate Soundness test sometimes preferred; limiting values are different to MSS. 14.2.3 Feasibility Study Sometimes known as ‘pre-feasibility’, by the end of this stage it will have been decided whether a road construction, improvement or rehabilitation project is justified. To a large extent it is a political decision but some technical input will be necessary in order to estimate costs. For example, it may be necessary to estimate AADT, have some knowledge of soil strengths or have an approximate idea of roughness. This study will indicate what type of project is necessary and provides the information required to commission a preliminary design study. To this end, it typically identifies alternative corridors, the traffic patterns, broad environmental and engineering parameters, and cost estimates to enable the terms of reference of the preliminary design to be drafted. 14.2.4 Preliminary Design 14.2.4.1 Alignment Soils 14.2.4.1.1 Sampling At least one sample shall be taken per kilometer of the anticipated alignment. More frequent samples must be taken where there are major changes in soil type, indicated either from geological data or visual observation. In the proposed cut sections pits shall be dug if possible down to at least 0.5 m below the proposed formation level. In the case of a new alignment, the depth of any pit shall in no case be less than 1.5m, unless rock or other material impossible to excavate by hand is encountered. The position of each trial pit shall be accurately determined and recorded. In every trial pit, all layers, including top soil, shall be accurately described and their thicknesses measured. All layers of more than 300 mm (except top soil) shall be sampled. The sample shall be taken over the full depth of the layer by taking a vertical slice of material. The log of each trial pit shall be accurately drawn and included in the Materials Report. If deep cuttings are proposed the investigation of the material at formation depth may only be practical near the time of construction. The Republic of Kenya – Ministry of Roads 160 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 14.2.4.1.2 Testing of soils on new alignments Sufficient sample shall be taken for the following tests to be carried out: In situ moisture content and dry density Grading to 0.075 mm sieve Atterberg Limits Compaction test, BS Heavy CBR and Swell on samples prepared at 90% and 95% of MDD and OMC (BS Heavy). (CBR shall be measured after 4 days soak, except in arid areas, where they can normally be measured at OMC, depending on the equilibrium moisture contents predicted under the pavement in the area. The moisture contents after 4 day soaking shall be measured, both on the whole CBR specimen and on a sample taken from beneath the plunger, after testing.) 14.2.4.1.3 Testing of subgrade and gravel wearing course on alignments of existing gravel roads This applies to existing gravel roads which are to be upgraded, the geometric standards of which are good enough to maintain the existing alignment. Where more than 100 mm of existing gravel wearing course is in place on the road and where the shape is adequate, samples of subgrade are to be submitted to the tests enumerated in the preceding section. It must be decided whether or not to re-compact the subgrade so the in-situ moisture content and dry density must be measured and compared against 90% and 95% of BS Heavy. Where a gravel road is to be upgraded on the same alignment, the existing gravel wearing course may provide extra material either for sub-base, or for improved subgrade. Measurements of thickness and width of gravel wearing course shall then be recorded every 100 m. One sample per kilometer of existing gravel wearing course shall be taken, where the gravel layer is at least 150 mm thick. Each sample shall be submitted to tests enumerated in the preceding section. 14.2.4.2 Soil and Gravel Borrow Pits Borrow pits and quarries should be spaced so as to obtain the most economic use of materials. The spacing depends on the availability of suitable material, environmental considerations, land use etc but a distance of 20km is optimal to minimize haulage costs. The minimum thickness of deposit normally considered workable is of the order of 1 m. The absolute minimum depends on the area of the deposit and the thickness of overburden. If there is no overburden as may be the case in arid areas, horizons as thin as 300 mm may be workable. 14.2.4.2.1 Field investigations and sampling procedure Trial pits shall normally be dug on a 60 m grid, through the full depth of the layer(s) proposed for use. A minimum of 5 trial pits is required for each proposed borrow pit. The location of each proposed borrow pit shall be identified, showing the position of each trial pit, the characteristic features of the site and the means of access and location. In every trial pit, all layers, including top soil and overburden, shall be accurately described and their thickness measured. All layers proposed for use shall be sampled. The sample shall be taken over the The Republic of Kenya – Ministry of Roads 161 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement full depth of the layer proposed, by taking a vertical slice of material. The log of each trial pit shall be accurately drawn and included in the Materials Report. 14.2.4.2.2 Sample testing For characterization purposes at least one sample shall be obtained per 4,000 m³ of material proposed for use. At least one sample shall be taken from each positive trial pit, even if the volume represented is smaller than 4,000 m³. Each sample shall be submitted to the following identification tests: Grading to 0.075 mm sieve Atterberg Limits Large samples for Compaction and CBR tests shall be obtained by either of the following: 1.Mix Method: Large samples can be obtained by mixing "small" identification samples. A mix must be representative of a workable area. All the "small" samples to be incorporated in a mix must be the same type of material and must have fairly consistent Grading and Atterberg Limits. Within each borrow pit, the mixes chosen should adequately cover the range of materials proposed for use. 2. Re-sampling Method: Using the identification results, large samples can be obtained by re-sampling from existing trial pits representative of the material types found within the potential borrow pit area. At least one large sample, whether mixed or re-sampled, is required per 15,000 m³ of material proposed for use and shall be submitted to the following tests: Grading to 0.075 mm sieve Atterberg Limits Compaction test (BS Heavy) CBR and Swell after 4 days soaking, on specimens normally prepared at OMC and normally 95% and 100% of MDD of BS Heavy. The moisture contents after soaking shall be measured as indicated previously. For types of gravel susceptible to crushing during compaction, the grading of the specimen compacted closest to 95% MDD shall be determined after compaction and CBR testing and compared with the grading before compaction of the specimen prepared for CBR. 14.2.4.2.3 Stabilization testing If the natural materials do not meet the CBR requirements, stabilization tests shall be carried out on the relevant large samples, as defined above: Each sample shall be mixed with cement or lime, or both, whichever from the characterization tests is expected to give the best results. (If both stabilizers are used, lime is added first to reduce the plasticity followed by the addition of cement to achieve the required strength). Three additive amounts (normally at 1% intervals up to a maximum of about 5%) shall be chosen to span the performance requirements and the following tests carried out : Compaction test (BS Heavy) on the large sample mixed with the amount of additive expected to be appropriate (usually the intermediate value of the three), followed by: CBR and/or UCS tests on specimens prepared at OMC and 95% MDD of BS Heavy with each of the 3 additive amounts. With lime, samples shall be soaked for 7 days The Republic of Kenya – Ministry of Roads 162 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement and ideally cured for 24 days but at least 7 days: for cement samples shall be soaked for 7 days and cured for 7 days. UCS tests are carried out for all samples stabilized with cement: with lime it is possible to achieve viable CBR results at low levels of lime addition. At least one sample per 15,000 m3 of material proposed for stabilisation shall be submitted to the above tests. 14.2.4.3 Stone Quarries Sources of stone visually considered suitable, both in terms of stone quality and quantity, should be selected for further investigation. The suitability of stone from existing quarries should obviously first be investigated since the overburden thickness, degree of weathering and, possibly, the available reserve will be apparent. (Even if the material from a quarry has been exhausted or is no longer available it is still worthwhile examining the quarry to gather information regarding, for instance, the depth of weathering.) The location of each potential source of stone shall be indicated on a key plan. A site plan of each potential quarry shall be prepared, showing the characteristic features of the site, such as the orientation and heights of faces and benches, whether the face is of overburden or stone, the water table level, the means of access and potential location for a crusher. 14.2.4.3.1 Sampling Hand sampling from existing faces or outcrops shall be carried out. (If it is an existing quarry residual stockpiles of crushed stone may still remain and should be sampled.) At least three hand samples shall be taken from each potential source. The position of each sampling point, or group of sub-sampling points, shall be accurately located and indicated on the site plan. Each sample shall be accurately described, from a geological and mineralogical viewpoint. In particular care shall be taken to ensure that the samples are obtained from fresh rock and not from weathered or altered rock and, if in doubt, the services of a specialist should be sought. In Kenya, there are particular problems with identifying fresh rock because much of the available stone aggregate is basic igneous rock susceptible to weathering. 14.2.4.3.2 Testing Sufficient sample shall be taken to carry out the following tests: TFV, dry and wet, and PI on the fines from the TFV dry test, or ACV FI MSS (if doubt still remains on the soundness of the stone) 14.3 Final Design 14.3.1 Earthworks and Subgrade 14.3.1.1 Sampling At least one sample shall be taken per 500 m along the length of the proposed alignment: if changes of soil type are evident either from visual observation or from geological data, more samples are necessary to enable a comprehensive evaluation of the subgrade strength. A good knowledge of the materials to be cut is also essential, as they will possibly be used as fill material. The Republic of Kenya – Ministry of Roads 163 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Pits shall be excavated mostly in proposed cut areas, down to at least 0.5 m below the anticipated formation level, unless rock is encountered. The position of each pit shall be accurately determined and reported. In hilly or mountainous terrain, deep holes will be required to accurately determine the materials to be cut. It is sometimes impossible to dig trial pits to the depth of the anticipated formation level. It is then recommended to use a hand or power auger to drill holes to the depth required. In every pit, all layers, including top soil, shall be accurately described and their thicknesses measured and recorded. All layers of more than 300 mm (except top soil) shall be sampled. In every pit in cuts, one sample shall be taken at the approximate level of the formation. The other samples shall be representative either of the anticipated fill materials or of the anticipated subgrade in fills. The sample shall be taken over the full depth of the layer by taking a vertical slice of material. The log of each test hole shall be accurately drawn and included in the Materials Report. It is important to be able to assess the quantities of the various earthwork categories, i.e. either rock, rippable or diggable material. It will in some cases be necessary to drill boreholes or use effective indirect means, for example seismic or ground penetrating radar, to achieve these estimates. 14.3.1.2 Testing of Soils on new alignments 14.3.1.2.1 Basic testing For each sample, sufficient material shall be obtained to carry out the following tests: Grading to 0.075 mm sieve Atterberg Limits Compaction test (BS Heavy) CBR and Swell on samples prepared at 90% and 95% of M.D.D and OMC (BS Heavy). (CBR shall be measured after 4 days soak, except in arid areas, where they can normally be measured at OMC, depending on the equilibrium moisture contents predicted under the pavement in the area. The moisture contents after 4 day soaking shall be measured, both on the whole CBR specimen and on a sample taken from beneath the plunger, after testing.) 14.3.1.2.2 Subgrade Classification and testing of samples representative of each soil category The results from the above basic testing, combined with the relevant field observations, will enable the subgrade soils to be grouped into homogeneous zones. A zone should include soils of similar grading, Atterberg Limits, Compaction and CBR. Usually, the number of soil zones will not exceed 4 or 5 for a given road project. For each soil zone, one representative large sample shall then be taken and submitted for the following tests: Full grading analysis Atterberg Limits Compaction test (BS Heavy) "6 points" CBR test, as summarized below The Republic of Kenya – Ministry of Roads 164 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Mineralogical composition determination For a "6 points" CBR test the material shall be compacted at 3 levels of compaction, normally around 90, 93 and 95% MDD at BS Heavy. The specimens shall be moulded at the moisture content expected at the time of in-situ compaction, in general at OMC. At each level of compaction, one CBR shall be measured immediately and one CBR shall be measured eventually on one soaked specimen. The time of soaking will depend on the anticipated subgrade conditions. The amount of water absorbed during soaking and the eventual swell shall be measured. This method enables an estimate to be made of the subgrade CBR at different densities and thus assists in determining the relative compaction to be specified. It also indicates the loss of strength which soaking may cause. 14.3.1.2.3 Treatment tests (when appropriate) If treatment of the alignment materials is contemplated, for use either as improved subgrade or as subbase, the treatment tests shall be carried out on the large zone samples in the manner indicated in the section on Preliminary Design above. 14.3.1.3 Testing of subgrade on existing gravel road alignments 14.3.1.3.1 Basic Testing This applies to existing gravel roads which are to be upgraded, the geometric standards of which are good enough to maintain the existing alignment. Where more than 100 mm of existing gravel wearing course is in place on the road and where the shape is adequate, samples of subgrade are to be submitted to the tests enumerated in the preceding section. It must be decided whether or not to re-compact the subgrade so the insitu moisture content and dry density must be measured and compared against 90% and 95% of BS Heavy. Where a gravel road is to be upgraded on the same alignment, the existing gravel wearing course may provide extra material either for subbase, or for improved subgrade. Measurements of thickness and width of gravel wearing course shall then be recorded every 100 m. One sample per kilometer of existing gravel wearing course shall be taken, where the gravel layer is at least 150 mm thick. Each sample shall be submitted to tests enumerated in the preceding section. 14.3.1.3.2 Subgrade Classification and testing of samples representative of each soil category An identical procedure discussed in the relevant Section above should be followed. 14.3.1.4 Existing Gravel Wearing Course (where appropriate) No further sampling or testing is required at this stage. Indeed, existing gravel wearing courses are subject to changes both in quantity and quality, under the action of traffic and weather. They should be considered as possible extra sources of material, to be reevaluated at the construction stage. The Republic of Kenya – Ministry of Roads 165 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 14.3.2 Part 3 - Materials and Pavement Soil and Gravel Borrow Pits Information obtained at the Preliminary Design stage will enable the most suitable borrow areas to be selected, taking into consideration the following factors: quality of the materials location of the proposed borrow pits, minimizing haul distance ease of working, considering, inter alia, land acquisition, clearance and restoration, access, overburden thickness 14.3.2.1 Field investigations and sampling procedures Pits shall be dug on a 30 m grid, through the full depth of the layer(s) proposed for use. The position of each proposed borrow pit shall be indicated on a key plan. A site plan of each proposed borrow pit shall be prepared, showing the position of each trial pit, the characteristic features of the site and the means of access and location. In every trial pit, all layers, including top soil and overburden, shall be accurately described and their thicknesses measured and recorded. All layers proposed for use shall be sampled. The sample shall be taken over the full depth of the layer proposed for use by taking a vertical slice of material. The log of each trial pit shall be accurately drawn and included in the Materials Report. 14.3.2.2 Frequency of sampling and testing For characterization purposes at least one sample shall be obtained per 1,000 m³ of material proposed for use. At least one sample shall be taken from each positive trial pit, even if the volume represented is smaller than 1,000 m³. Each sample shall be submitted to the following identification tests: Grading to 0.075 mm sieve Atterberg Limits Large samples for Compaction and CBR tests shall be obtained by either of the following: 1.Mix Method: Large samples can be obtained by mixing "small" identification samples. A mix must be representative of a workable area. All the "small" samples to be incorporated in a mix must be the same type of material and must have fairly consistent Grading and Atterberg Limits. Within each borrow pit, the mixes chosen should adequately cover the range of materials proposed for use. 2. Re-sampling Method: Using the identification results, large samples can be obtained by re-sampling from existing trial pits representative of the material types found within the potential borrow pit area. At least one large sample, whether mixed or re-sampled, is required per 5,000 m³ of material proposed for use and shall be submitted to the following tests: Grading to 0.075 mm sieve Atterberg Limits Compaction test (BS Heavy) CBR and Swell after 4 days soaking, on specimens normally prepared at OMC and normally 95% and 100% of BS Heavy. The moisture contents after soaking shall be measured as indicated previously. The Republic of Kenya – Ministry of Roads 166 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement For types of gravel susceptible to crushing during compaction, the grading of the specimen compacted closest to 95% MDD shall be determined after compaction and CBR testing and compared with the grading before compaction of the specimen prepared for CBR. In addition to the following tests, the 10% Fines test (TFV) shall be determined on the coarse particles of at least one typical sample from each gravel site. 14.3.2.3 Stabilization testing (where required) The results obtained at the Preliminary Design stage combined with the results of the above tests will enable the design engineer to decide which borrow pit materials require treatment and the nature of that treatment (i.e. type of additive and approximate percentage needed, method of mixing). Stabilisation tests shall then be carried out on the relevant large zone samples, as defined above. The Initial Consumption of Lime test (BS 1924) should first be carried out to determine if there are adverse components within the material to be stabilized. In particular, soils with a significant organic matter content, or high pH, or high sulphate content may require too high a level of stabilizer for economic use. Each sample shall be mixed with cement or lime, or both, whichever from the characterization tests is expected to give the best results. (If both stabilizers are used, lime is added first to reduce the plasticity followed by the addition of cement to achieve the required strength). Three additive amounts (normally at 1% intervals up to a maximum of about 5%) shall be chosen to span the performance requirements and the following tests carried out : Compaction test (BS Heavy) on the large sample mixed with the amount of additive expected to be appropriate (usually the intermediate value of the three), followed by: CBR and/or UCS tests on specimens prepared at OMC and 95% MDD of BS Heavy with each of the 3 additive amounts. With lime, samples shall be soaked for 7 days and ideally cured for 21 days but at least 7 days: for cement samples shall be soaked for 7 days and cured for 7 days. UCS tests are carried out for all samples stabilized with cement: with lime it is possible to achieve viable CBR results at low levels of lime addition. At least one sample per 5,000 m3 of material proposed for stabilisation shall be submitted to the above tests. 14.3.2.4 Stone Quarries The most suitable potential quarry sites will have been selected from investigations carried out at the Preliminary Design stage. It is advisable to obtain expert advice to confirm the selection of quarry sites, especially new sites. There are subtleties of tropical weathering and/or geological complexity which may elude the untrained investigator and the repercussions of poor quarry selection can have potentially serious and costly consequences. 14.3.2.4.1 Investigations, drilling and sampling: A comprehensive quarry investigation would normally comprise fieldwork and laboratory testing phases. The Republic of Kenya – Ministry of Roads 167 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 14.3.2.4.1.1 Fieldwork Production of a topographical map of the proposed quarry at scale 1:1000 showing: terrain relief, means of access and location rock outcrops and/or existing quarry faces, and location of surface samples, excavated samples and boreholes. The boreholes shall be drilled on an approximate 30 m grid to prove overburden thickness and nature, and quantity and quality of stone. Normally the core diameter should be 76 mm, in order to recover stone in sufficient quantity for testing. The log of each borehole shall be accurately recorded, drawn and included in the Materials Report. A bulldozer or mechanical excavator should be used if necessary to prove the availability of solid rock. The excavation can be shown to tenderers during a conducted site visit. Samples of fresh rock shall be obtained by hand, or pneumatic drilling from existing faces and outcrops. Great care shall be taken to avoid sampling from weathered and/or altered rock zones and to ensure that the samples are representative of the stone to be used. In addition, whenever possible, deeper samples shall be obtained by blasting. Depending on the consistency of the stone and whether it is an existing or a new quarry 5 to 10 samples are required per quarry. 14.3.2.4.1.2 Testing Each sample shall contain sufficient material to carry out the following tests: TFV, dry and wet, and PI on the fines from the TFV dry test, or ACV Specific Gravity (oven-dry method), including Water Absorption Magnesium Sulphate Soundness Plasticity Index on 10% Fines Value fines & Plasticity Index on Material passing the 425 micron sieve Bitumen Affinity (for stone proposed for use with bitumen) In addition, one large sample shall be obtained from each quarry, so as to be representative of the stone to be used. This large sample shall be crushed with a small crusher (and not broken by hand), to a maximum size depending on the proposed use of the stone (usually ranging from 20 to 40 mm). The crushed stone shall be submitted to the above tests and in addition to the following tests: Grading to 0.075 mm sieve Flakiness Index Sand Equivalent Value Compaction test (Vibrating Hammer method), if appropriate. The Republic of Kenya – Ministry of Roads 168 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 15 Standard Methods of Testing In the previous RDM the recommended test methods for soils and gravels were based on both BS and AASHTO standards. The Kenya Bureau of Standards (KEBS) have now published a complete set of standards, wholly adopted from BS 1377 (Testing of Soils) and BS 812 (Testing of Aggregates) but not BS 1924 (Stabilised materials for civil engineering purposes). As these are locally available it is proposed to adopt them in this Manual. However, over the past 10 years, the BS standards have been progressively integrated and replaced by European ‘EN’ standards. This has not yet reached BS 1377 and BS 1924 but BS 812 has been replaced with only a few of the original tests retained. This presents a dilemma for this Manual because it will be seen to be promoting the use of standards which have become or are becoming obsolescent. Changing laboratory equipment to cater for the new tests will be a costly process which is considered to be unacceptable in the Kenyan environment. 15.1 Soils In 2001 KEBS published a set of soil testing standards wholly adopted from BS 1377 1990. Table 14.1 itemizes these, together with the equivalent AASHTO and ASTM standards: Table 15.1: Soil Testing Standards KS 999 2001 Part No. Subject 1 General Requirements and Sample preparation Classification Moisture content Liquid & Plastic Limits Shrinkage Limit Linear Shrinkage Mass density Particle density Particle Size Distribution 2 3 4 9 Chemical Tests Organic Matter Content Total Sulphate Content Total Dissolved Solids pH value Compaction-related tests Includes BS Heavy and CBR tests In-Situ Tests Includes sand replacement and nuclear density methods AASHTO Test No T89 & T90 T11 & T27 T180 T191 ASTM Test No (Vols 04.02, 04.03 & 04.08) D0421 D2216 D4318 D0427 D42.7 C127 & C128 D0422, D1140 D0698 D1157 D1883 D4546 D1556 D2922 Notes: The mass in g) of sample required for sieve analysis is around 400 D, D being the maximum particles size (in mm), and Samples containing particles larger than 20 mm shall be prepared for compaction and CBR tests by sieving an adequate quantity of the representative material over The Republic of Kenya – Ministry of Roads 169 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement the 50 mm and 20 mm sieve. Weigh the material passing the 50 mm sieve and retained on the 20 mm sieve and replace it with an equal mass of material passing the 20 mm sieve and retained on the 5 mm sieve. Take the material for replacement from the remaining portion of the main sample. For gravel samples the aggregations of particles shall be broken with a wooden hammer or pestle. Care shall be taken that no discrete particles are crushed in this operation. Differences have been recorded when determining Atterberg limits on either ovendried or air-dried soils. For the sake of consistency it is recommended that Atterberg Limits should be determined on oven-dried soils. 15.2 Aggregates In 2003 KEBS published a complete set of aggregate testing standards for use in Kenya, KS 1238, wholly adopted from BS 812. Table 14.2 itemizes some of these tests, together with the equivalent AASHTO and ASTM standards: Table 15.2: Aggregate Testing Standards Property Tests Required Toughness Aggregate Crushing Value (ACV) 10% Fines Crushing Value (TFV) Aggregate Impact Value (AIV) Cleanliness Sand Equivalent Value (SEV) % Deleterious Materials Durability Los Angeles Abrasion Value (LAA) Water Absorption (WI) Shape Other Tests Magnesium Sulphate Soundness (MSS) Polished Stone Value (PSV) Flakiness Index (FI) Moisture Content Water-soluble Chloride Content Sulphate Content KS 1238 Test No 11 12 13 21 - AASHTO Test No T176 T112 T96 8 T84 (fine) T85 (coarse) T104 20 15 6 10 16 17 ASTM Test No C2419 C142 C131 or C535 C88 T278 D4791 BS 812 was replaced by CEN standards at the turn of the millennium. A list of the relevant aggregate tests is given in Table 15.3. It is clear that the range of tests is more comprehensive than the current list. Table 15.3: CEN Tests BS EN No. 932-1 932-2 932-3 932-4 932-5 932-6 Tests for General properties of aggregates Method of Sampling Methods for reducing laboratory samples Procedure & terminology for simplified petrographic description Common equipment and calibration Definitions of repeatability and reproducibility Tests for geometric properties of aggregates 933-1 Determination of particle size distribution: sieving method 933-2 Determination of particle size: test sieves and nominal size of apertures The Republic of Kenya – Ministry of Roads 170 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 933-3 933-4 933-5 933-6 933-7 933-8 1097-1 1097-2 1097-3 1097-4 1097-5 1097-6 1097-7 1097-8 Part 3 - Materials and Pavement Determination of particle shape: flakiness index Determination of particle shape: shape index Percentage of crushed & broken surfaces in coarse aggregate Flow coefficient of coarse aggregate Determination of shell content: percentage of shells in coarse aggregates Sand Equivalent test Tests for mechanical and physical properties of aggregates Determination of resistance to wear: Micro-Deval test Methods for the determination of resistance to fragmentation Determination of loose bulk density and voids Determination of the voids in dry-compacted filler Determination of the water content by drying in a ventilated oven Determination of particle density and water absorption Determination of the particle density of filler-pyknometer method Determination of the polished stone value Tests for thermal and weathering properties 1367-2 Magnesium Sulphate test 1367-3 Boiling test for Sonnenbrand basalt 15.2.1 Determination of Average Least Dimension Riffle out a representative sample of about 200 aggregate particles of each size fraction Sieve the sample through a sieve with an aperture size half the nominal size of the aggregate to be tested and discard the particles passing the sieve By means of calipers with platens of at least 5 mm in diameter (or square), measure the smallest dimension of each particle retained on that sieve, accurate to 0.1 mm, and record the measurements and the number of particles tested. Calculations Calculate the average least dimension to the nearest 0.01 mm as follows: Average least dimension (mm) = A/B, where A = sum of the smallest dimension of all the particles in mm B = number of particles Report the average least dimension to the first decimal place. 15.3 Cement or Lime Stabilised Materials Stabilized materials should be tested in accordance with BS 1924: 1990, (Stabilised materials for civil engineering purposes) Parts 1 and 2. These two Parts contain details of sample preparation, moisture content determination, compaction and strength testing and durability testing. Materials to which stabilizer has been added have a different grading. Before testing with stabilizer, compaction testing should be carried out to determine the OMC and MDD of the new grading. The Republic of Kenya – Ministry of Roads 171 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Samples containing larger particles than 20 mm shall be prepared for compaction and CBR tests as indicated in Section 14.1. (The fraction coarser than 20 mm shall be replaced by an equal weight of 5/20 mm material). The determination of Unconfined Compressive Strength shall be carried out according to test 10. The specimens should be compacted to a pre-determined density and cured at a temperature of 270C ± 20C. 15.4 Cement and Lime Testing Ordinary Portland cement shall be sampled and tested in accordance with Kenya Standard KS 1260 2001, ‘Methods of Physical Testing of Cement’. Lime shall be tested in accordance with Kenya Standard KS 02 97, or BS EN 459-1:2001. 15.5 Bituminous Binders Tests involving bitumen are traditionally carried out in Kenya mainly to American standards and it is therefore proposed to retain them. 15.5.1 Sampling procedures Sampling of straight-run bitumens and cut-backs shall be carried out in accordance with AASHTO method T40 (ASTM D 140). Sampling of bitumen emulsion shall be carried out in accordance with BS 434, except that where a delivery is made in drums or barrels, the number of samples shall be as indicated in AASHTO Sampling Method T40, paragraph 11.1. 15.5.2 Testing procedures Tests on straight-run bitumen shall be carried out in accordance with the following test procedures: Penetration Softening point (Ring and Ball) Flash and fire points (Cleveland open cup) Loss on Heating Ductility Water Thin film Oven Test Rolling Thin Film Oven Test Solubility in organic solvents Specific gravity AASHTO T49 (ASTM D 5) AASHTO T53 (ASTM D 2398) AASHTO T48 (ASTM D 92) AASHTO T47 (ASTM D 6) AASHTO T51 (ASTM D 113) AASHTO T55 (ASTM D 95) AASHTO T179 (ASTM D 1754) AASHTO T240 AASHTO T44 (ASTM D 2042) AASHTO T228 (ASTM D 70) Tests on cut-back bitumen shall be carried out in accordance with the following test procedures: Kinematic viscosity Flash point (Tag open cup) (RC-MC) Flash point (Cleveland open cup) (SC) Distillation Water The Republic of Kenya – Ministry of Roads 172 AASHTO T201 (ASTM D 2170) AASHTO T79 (ASTM D 1310) AASHTO T48 (ASTM D 92) AASHTO T78 (ASTM D 402) AASHTO T55 (ASTM D 95) Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement Specific gravity Asphalt residue from 100 pen (SC) Tests on residue from distillation AASHTO T228 (ASTM D 3142) ASTM D 243 ASTM D 243 Penetration Ductility Solubility AASHTO T49 (ASTM D 5) AASHTO T51 (ASTM D 113) AASHTO T44 (ASTM D 2042) STV viscosity BS 3235 Tests on bitumen emulsion shall be carried out in accordance with BS 434 test procedures: Residue on 0.710 mm sieve Residue on 0.150 mm sieve Stability to mixing with coarse aggregate Stability to mixing with cement Binder content Engler viscosity Redwood II viscosity Storage stability (short period) Storage stability (long period) Particle charge 15.6 Bituminous Mixtures 15.6.1 Sampling procedures Sampling of bituminous mixtures shall be carried out in accordance with AASHTO method T168 (ASTM D 979). 15.6.2 Testing procedures Tests on bituminous mixtures shall be carried out in accordance with the following test procedures: Moisture and volatile distillates Quantitative extraction of bitumen Specific gravity of compacted mixture Recovery of bitumen from solution Coating and stripping Degree of particle coating Coating and stripping (with adhesion agent) Maximum specific gravity Degree of pavement compaction The Republic of Kenya – Ministry of Roads 173 AASHTO T110 (ASTM D 1461) AASHTO T164 (ASTM D 2172) or BS 598 AASHTO T166 (ASTM D 1188 and D 2726) AASHTO T170 (ASTM D 1856) or BS 598 AASHTO T182 (ASTM D 1664) AASHTO T195 (ASTM D 2489) ASTM D 2727 AASHTO T209 (ASTM D 2041) AASHTO T230 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Marshall Stability Hubbard-Field Stability 15.6.3 Part 3 - Materials and Pavement AASHTO T245 (ASTM D 1559) ASTM D 1138 CEN Tests The following is a list of CEN tests for bituminous mixtures and fillers: Table 15.4: CEN Tests CEN Standard Aggregates: Tests for Fillers BS EN 1744-4 BS EN 13179-1 BS EN 13179-2 Test Description Water susceptibility of fillers for bituminous mixtures Delta Ring and Ball test Bitumen Number Bitumen and Bituminous Binders BS EN 12591 Specification for paving-grade bitumen prEN 13924 Specification for hard paving-grade bitumen prEN 14023 Specification for polymer-modified bitumen BS EN 58 Sampling of bituminous binders BS EN 1426 Determination of needle penetration BS EN 1427 Determination of softening point: Ring and Ball method BS EN ISO 2592 Determination of flash and fire points BS EN 12592 Determination of solubility BS EN 12593 Determination of Frauss breaking point BS EN 12594 Preparation of test samples BS EN 12595 Determination of kinematic viscosity BS EN 12596 Determination of dynamic viscosity by vacuum capillary BS EN 12607-1 Determination of the resistance to hardening under the influence of heat and air: RTFOT method BS EN 12607-2 Determination of the resistance to hardening under the influence of heat and air: TFOT method BS EN 12607-3 Determination of the resistance to hardening under the influence of heat and air: RTF method prEN 13302 Determination of viscosity of bitumen using a rotating spindle apparatus Bituminous Mixtures prEN 13108-1 prEN 13108-2 prEN 13108-4 prEN 13108-20 BS EN 12697-1 prEN 12697-2 BS EN 12697-3 prEN 12697-5 prEN 12697-6 prEN 12697-8 prEN 12697-9 prEN 12697-10 prEN 12697-11 prEN 12697-12 prEN 12697-15 Material specification-Asphalt Concrete Material specification-Asphalt Concrete for very thin layers Material specification-Hot Rolled Asphalt Quality-type testing of asphalt mixes Test methods-Soluble binder content Test methods-Particle size distribution Test methods-Bitumen recovery, rotary evaporator Test methods-Maximum density Test methods-Bulk density, measurement Test methods-Air voids content Test methods-Reference density Test methods-Compatibility Test methods-Affinity between aggregate and binder Test methods-Moisture sensibility Test methods-Segregation sensitivity The Republic of Kenya – Ministry of Roads 174 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 prEN 12697-19 prEN 12697-22 prEN 12697-23 prEN 12697-26 prEN 12697-27 prEN 12697-28 Part 3 - Materials and Pavement Test methods-Permeability of Porous asphalt specimen Test methods-wheel tracking Test methods-Indirect tensile test Test methods-Stiffness Test methods-Sampling Test methods-Preparation of samples for determining binder content, water content and grading Test methods-Dimensions of a bituminous specimen Test methods-Specimen preparation by impact compactor Test methods-Specimen preparation by gyratory compactor Test methods-Specimen preparation by vibratory compactor Test methods-Specimen preparation by slab compactor Test methods-Marshall test Test methods-Laboratory mixing Test methods-Common equipment and calibration prEN 12697-29 prEN 12697-30 prEN 12697-31 prEN 12697-32 prEN 12697-33 prEN 12697-34 prEN 12697-35 prEN 12697-38 Surface characteristics-road and airfield prEN 13036-1 Test methods-Measurement of pavement macro-texture using a patch technique prEN 13036-2 Test methods-Procedure for determination of skid resistance of a pavement surface prEN 13036-4 Test methods-Measurement of slip/skid resistance of a surface: the Pendulum test prEN 13036-5 Test methods-Determination of longitudinal evenness parameters or indicators prEN 13036-6 Test methods-Profilometer-based method for measuring longitudinal evenness prEN 13036-7 Test methods-method for measuring surface irregularities: the Straight-Edge test prEN 13606-8 Test methods-Determining parameters or indicators for transverse evenness: Measurement method 15.6.3.1 The Brazilian Test The Brazilian test comprises the measurement of the force required to crush a cylindrical sample along one of its diameters between two parallel flat platens. The samples are to be prepared in accordance with and to the size required by the Marshall test (ASTM D1559) compacted using 50 blows of the rammer on each, face of the sample. The temperature of the sample at the time of test is to be 25˚C ±2˚C and the platens during the test are to be moved together at a content rate of 0.86 mm/sec. The indirect tensile stress is calculated as:2 x Load at failure/perimeter of sample x thickness of sample The Republic of Kenya – Ministry of Roads 175 Draft Document – October 2009 DESIGN MANUAL for ROADS and BRIDGES 2009 Part 3 - Materials and Pavement 16 Footpaths Possibly 50% of all fatalities and serious accidents in Kenya are suffered by pedestrians. A proportion is certainly caused by careless/dangerous driving, or pedestrian inattention but it is almost as certain that the numbers would be reduced if footpaths were properly constructed. That this is manifestly not the case in Kenya is presumably a reflection of funding. Footpaths should be constructed on a raised platform on the edge of the road shoulder, if adjacent to the road, but if there is a drain next to the shoulder then preferably on the outside of the drain. The edge of the platform should consist of a kerb, manufactured either from stone or from pre-cast concrete block. This should be a minimum of 100mm height and the width of the kerb should be at least equal to the height. The kerb should be firmly secured into the surface on which it is laid. The footpath itself should be at least one metre wide. The foundation of the footpath should be thoroughly cleared of vegetation and the subbase of the footpath can consist of either an unbound mixture, such as non-plastic sand, or a cement-bound mixture, depending on the footpath surfacing. Most importantly, the surfacing should be inclined to permit drainage, otherwise water will pond on the footpath and pedestrians will be inclined to use the carriageway. The footpath surfacing can consist of either natural stone or pre-cast concrete flagstones, of maximum size 450mm square, or asphalt concrete (Type II, 0/10). If the surfacing is of flagstones, the subbase should either consist of a layer of mortar between 10mm and 40mm thick, or a layer of 0/4mm sand 25mm ±5mm thick. It is important that the sand is well compacted. The joints between the flagstones should be filled with finer (0/2mm) sand. There are specifications for this construction. Kerbs shall conform to BS EN 1340. Pre-cast concrete flagstones shall conform to BS EN 1339: natural stone flagstones shall conform to BS EN 1341. The method of construction of the footpath should conform to BS 7533-4. The sand subbase should conform to BS EN 12620. Figure 16.1: Well constructed footpath and Non-existent footpath, Elegayo Marakwet St, Kilimani, Nairobi The Republic of Kenya – Ministry of Roads 176 Draft Document – October 2009