lOMoARcPSD|27223832 ACCA MA F2 Exam kit Management Accounting (Association of Chartered Certified Accountants) Studocu is not sponsored or endorsed by any college or university Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 Question Bank ACCA Management Accounting (MA) From September 2020 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 ii I n t ro d u c t i on A C C A MA Q ue s t ion Ba nk No part of this publication may be reproduced, stored in a retrieval system or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording or otherwise, without the prior written permission of First Intuition Ltd. Any unauthorised reproduction or distribution in any form is strictly prohibited as breach of copyright and may be punishable by law. We are grateful to the Association of Chartered Certified Accountants for permission to reproduce past examination questions and model answers. Additional comments and guidance have been prepared by First Intuition Ltd. © First Intuition Ltd, 2020 ARPIL 2020 RELEASE Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA Q ue s t ion Ba nk I n t ro d u c t i on How to use this Question Bank 1 QUESTION PRACTICE IS KEY TO SUCCESS This Question Bank has been written to help you pass Paper MA Management Accounting. Targeted question practice In the first section there are banks of questions based around each chapter of the Course Notes. The number of questions reflects the weighting of the topic to the syllabus. You should attempt to do all the questions before attempting the mock assessments at the end. Do the practice exam and the mock assessments The importance of question practice cannot be underestimated and you should attempt the mocks under assessment conditions. For this paper you have two hours to answer 35 questions in section A and all three questions in section B. It is vital you stick to the time allocation and answer every question. The types of question that may be included are as follows: Multiple Choice Number Entry You are required to choose one answer from a list of options by clicking on the appropriate radio button You are required to select more than one response from the options provided by clicking the appropriate tick boxes You are required to select a response to a number of related statements by clicking on the radio button which corresponds to the appropriate response for each statement You are required to key in a numerical response to the question Gapfill You are required to enter answers into blank areas Hot Spot You are required to choose one or more answers by clicking on the appropriate hotspot area/ areas on an image Multiple Response Multiple Response Matching Each of the above types of question are included in this Question Bank. Downloaded by Hooria Noor (nhooria9@gmail.com) OT MTQ iii lOMoARcPSD|27223832 iv I n t ro d u c t i on A C C A MA Q ue s t ion Ba nk Contents Topic Number of questions Q A 30 1-2 3 4-9 10-12 13-30 1 1 1 2 3 119 119 119 120 120 8 123 Page ref Chapter 1: Management accounting and information Objective test questions Accounting for management Planning, decision-making and control Data and information Sampling Presenting information Chapter 2: Statistical techniques Objective test questions 21 Statistical techniques 1-21 Chapter 3: Summarising and analysing data Objective test questions 30 Expected values 1-11 14 126 Averages and distributions 12-30 17 128 30 1-19 10-27 28 29 30 22 24 28 28 28 133 134 136 136 136 30 1-30 29 137 1-7 34 142 30 1-30 36 144 1-18 44 148 30 1-30 48 152 Chapter 4: Costing Objective test questions Cost classification Cost behaviour Cost coding Cost measurement Management of business units Chapter 5: Accounting for materials Objective test questions Accounting for materials Chapter 6: Accounting for labour Objective test questions 7 Accounting for labour Chapter 7: Accounting for overheads Objective test questions Accounting for overheads Chapter 8: Absorption and marginal costing Objective test questions 18 Absorption and marginal costing Chapter 9: Process costing Objective test questions Process costing Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA Q ue s t ion Ba nk I n t ro d u c t i on Number of questions Topic Page ref Q A 55 57 58 159 161 161 59 59 59 59 163 163 163 163 61 62 165 165 64 67 167 169 68 169 1-16 70 170 18 1-18 73 173 77 78 176 177 80 82 87 178 179 182 89 94 184 188 94 188 Chapter 10: Other costing techniques Objective test questions 29 Job and batch costing Service and operation costing Alternative cost accounting approaches 1-8 9-13 14-19 Chapter 11: Nature and purpose of budgeting Objective test questions 9 Nature and purpose of budgeting Budgetary control and reporting Behavioural aspects of budgeting Flexible budgets Multi task questions 1 Alanowl 2 Worsley Ltd 1-2 3 4 5-9 Chapter 12: Budget preparation Objective test questions Budget preparation Capital budgeting 17 1-16 17 Multi task question 1 Moonstar Chapter 13: Discounted cash flow Objective test questions 16 Discounted cash flow Chapter 14: Investment appraisal Objective test questions Investment appraisal Multi task questions 1 Maurice Ltd 2 Edrich Ltd Chapter 15: Material and labour variances Objective test questions 40 Standard costing systems Variance calculations Causes of variances 1-9 10-36 37-40 Chapter 16: Other variances Objective test questions Variance calculations Causes of variances 27 1-25 26-27 Multi task question 1 Cuddlyfud Downloaded by Hooria Noor (nhooria9@gmail.com) v lOMoARcPSD|27223832 vi I n t ro d u c t i on A C C A MA Q ue s t ion Ba nk Number of questions Topic Page ref Q A 96 96 189 189 97 99 100 102 189 190 191 193 104 104 193 193 109 110 198 198 112 112 112 113 113 113 113 114 200 200 200 200 201 201 201 201 114 116 117 201 202 203 205 217 Chapter 17: Variance review and control Objective test questions 3 Reconciliation of budgeted and actual profit Cost control and reduction 1 2-3 Multi task questions 1 2 3 4 Henry Edted Wakeuup Harvey hedge Chapter 18: Financial performance measures Objective test questions 30 Performance measurement overview Financial measures 1-2 3-30 Multi task questions 1 Oldted 2 Loxwood Foods Chapter 19: Non-financial performance measures and performance reporting 1 Objective test questions 10 Non-financial measures Balanced scorecard Activity, efficiency and capacity ratios Process and job performance measurement Non-profit seeking and public sector organisations Manufacturing and service businesses Benchmarking Performance reports 1 2 3-5 6 7 8 9 10 Multi task questions 1 Fuzzy Limited 2 Broadbridge Clinics Ltd 3 Sydney Darwin Limited Practice exam Full exam 227 Formulae and tables Mock exams Full exams to practise are provided. Question practice, under assessment conditions, is vital to passing this exam. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA Q ue s t ion Ba nk I n t ro d u c t i on ACCA Specimen paper It is vital that you try the computer based specimen exam on the ACCA website. The specimen uses the software that you will meet in your real exam and you must be familiar with it. You will find it on the ACCA website: www.accaglobal.com The ACCA also provide some additional constructed response questions. We strongly suggest you attempt these. Downloaded by Hooria Noor (nhooria9@gmail.com) vii lOMoARcPSD|27223832 viii I n t ro d u c t i on A C C A MA Q ue s t ion Ba nk Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 1: M an ag e me n t ac c o u n ti n g a n d i n fo rmat i o n Chapter 1: Management accounting and information Objective test questions Accounting for management 1 The following statements relate to management accounts: I II III They are used to aid planning, control and decision making They must be produced in a prescribed format There is a legal requirement for most companies to produce them annually Which of the above statements are true? 2 I only I and III I, II and III II and III Cost accounting and management accounting are items which are interchangeable. Is this answer TRUE or FALSE? True False Planning, decision-making and control 3 Management accounts may be I II III a historical record a future planning tool provided in non-monetary format Which of the above statements are true? II only II and III I and II I and II and III Data and information 4 Figures relating to a training organisation are as follows: % of first time students who passed final exam) 98% Increase in % of students passing first time since last sitting 2% Does the figure provide the training organisation with data or information? Data Information % of first time students who passed final exams Increase in % of students passing first time since last sitting Downloaded by Hooria Noor (nhooria9@gmail.com) 1 lOMoARcPSD|27223832 2 1: M an ag e me n t ac c o u n ti n g a n d i n fo rmat i o n 5 Which TWO of the following are limitations of management information in providing guidance for managerial decision making? 6 It is usually based on what has happened in the past It does not take account of external factors effecting the business It is not set out in a legally prescribed format It may be stated in monetary and non-monetary terms Which of the following types of business is LEAST likely to use big data analytics to analyse the product or service mix it offers? 7 A sports equipment shop A travel agent A local bus company A bank Are the following internal or external information sources? Internal External Current exchange rate Weekly sales figures Inflation rate Lists of potential customers 8 Which THREE of the following are limitations of information found on the internet? 9 A C C A MA The information may not be tailored for the exact purpose for which it is required There is so much information that there is a danger of information overload The information is cheap and easy to acquire The source of the information may not be reliable Which of the following statements are correct? I II III Strategic information is mainly used by senior management in an organisation Productivity measurements are examples of tactical information Operational information is required frequently by its main users Select one: I, II and III I and II I and III Sampling 10 A sample is acquired by taking every nth item in the sampling frame. This is an example of Random sampling Systematic sampling Cluster sampling Quota sampling Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 1: M an ag e me n t ac c o u n ti n g a n d i n fo rmat i o n 11 Which of the following BEST describes cluster sampling? 12 The sampling frame is divided into non overlapping groups and random units are selected from each group The population is divided into groups and then all units within randomly selected groups are taken A sample of ‘X’ units is taken from the sampling frame The population is divided into groups and then a number of the units within these groups are selected at random Identify the sampling method being used in each of the cases below. Stratified Random Multistage Systematic A number of UK universities are selected and then all girls in the selected university are selected 10 children are randomly chosen from each year group in a School Every 100th person to enter a supermarket is selected on a given day Presenting information 13 Which section of a report sets out the purpose of the report? Contents Terms of reference Recommendations Appendices Use the following information to answer the next six questions. The following information relates to the free newspapers that a sample of 200 people read in the city of Leochester. Post News Chronicle Press 14 Men surveyed 23 41 13 17 94 Women surveyed 24 34 23 25 106 Which is the most popular newspaper amongst women? Post News Chronicle Press Downloaded by Hooria Noor (nhooria9@gmail.com) Total 47 75 36 42 200 3 lOMoARcPSD|27223832 4 1: M an ag e me n t ac c o u n ti n g a n d i n fo rmat i o n 15 A C C A MA To the nearest whole per cent, what percentage of men read the Post? % 16 What number of women surveyed do not read the News or the Chronicle? 17 What percentage of people does not read the Press? % 18 To the nearest whole %, what percentage of the Chronicle’s readership is male? % 19 For which paper does the percentage of men and women reading the paper differ the most? Post News Chronicle Press Use this diagram to answer the next four questions. The following graph shows the pass rates for the Tax and Law exams for an accountancy qualification: Tax 36% 38% 51% 41% 20X0 20X1 20X2 20X3 Law 61% 49% 55% 54% 70% 60% 50% 40% Tax 30% Law 20% 10% 0% 20X0 20X1 20X2 20X3 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 1: M an ag e me n t ac c o u n ti n g a n d i n fo rmat i o n 20 In which year was the difference in the percentage pass rate between the two papers the greatest? 20X0 20X1 20X2 20X3 21 For both papers combined, in what percentage of sittings was the pass rate over 50%? % 22 In how many years did the pass rate for Law fail to reach 60%? years 23 In which year was the pass rate for Tax the lowest? 24 20X0 20X1 20X2 20X3 On a scattergraph illustrating fixed and variable cost, what does the figure a represent? Total cost Fixed cost Variable cost per unit Production Downloaded by Hooria Noor (nhooria9@gmail.com) 5 lOMoARcPSD|27223832 6 1: M an ag e me n t ac c o u n ti n g a n d i n fo rmat i o n A C C A MA Use this diagram to answer the next five questions. The following diagram illustrates the percentage of viewers for four popular television programmes that are broadcast at 8pm on Sunday evening. Assume that the number of male and female viewers is equal. Women Stir Heward's Way Gently Gently Upton Castle Men 0% 20% 40% 60% 25 Which programme has the largest audience? Stir Heward’s Way Gently Gently Upton Castle 26 Which programme is least popular amongst women? 27 100% Stir Heward’s Way Gently Gently Upton Castle The same television company broadcasts Heward’s Way and Gently Gently on different channels. Has it achieved a greater than 50% share of the male audience? 28 80% Yes No Which programme has the least difference in viewer numbers between the male and female audience? Stir Heward’s Way Gently Gently Upton Castle Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 1: M an ag e me n t ac c o u n ti n g a n d i n fo rmat i o n 29 Advertisers who advertised in the commercial breaks in Upton Castle hoped that it would achieve a 25% share of total audience. Did it achieve this figure? 30 Yes No What type of chart is this? 5 4.5 4 3.5 3 Aye 2.5 Bea 2 Cee 1.5 1 0.5 0 Q1 Q2 Q3 Simple bar chart Multiple bar chart Component bar chart Ogive Downloaded by Hooria Noor (nhooria9@gmail.com) Q4 7 lOMoARcPSD|27223832 8 2: St at i s t i c al t e c h n i qu e s A C C A MA Chapter 2: Statistical techniques Objective test questions Statistical techniques 1 A price index was established at 20X1 with prices at $400 and the index at 100. By 20X4 the index stood at 110. Prices increased by 15% in 20X5 and by a further $12 in 20X6. What will be the level of the index at the end of 20X6 to one decimal place? 2 The linear regression equation for production costs for a business is: y = 122,000 + 5.3x, where x is the number of units If production is expected to be 105,000 units in the next quarter the anticipated production costs are: $ 3 The following data has been collected about a company’s costs (y) in relation to its output (x) (x) 26 30 33 44 48 50 231 (y) 6,566 6,510 6,800 6,985 7,380 7,310 41,551 xy 170,716 195,300 224,400 307,340 354,240 365,500 1,617,496 x2 676 900 1,089 1,936 2,304 2,500 9,405 y2 43,112,356 42,380,100 46,240,000 48,790,225 54,464,400 53,436,100 288,423,181 Calculate the correlation coefficient to 3 decimal places. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 2: St at i s t i c al t e c h n i qu e s 4 The following data has been observed in a time series: Year Quarter 1 1 Sales $ 60,000 2 144,000 Moving average $ Centred moving average $ 160,500 3 198,000 163,500 4 240,000 172,500 2 1 72,000 2 180,000 Complete the two missing figures for the four-point (centred) moving averages. 5 The sales of lawnmowers over the last year have been as follows: Q1 3,180 +180 Actual units sold Seasonal variation Q2 3,530 +230 Q3 3,140 -460 Using an additive time series model and assuming the trend continues, the trend value for Q4 sales is closest to: 6 3,267 units 3,283 units 3,900 units 3,950 units A company uses time series analysis and regression techniques to estimate future sales demand. Using these techniques, it has derived the following trend equation: y = 10,000 + 4,200x where y is the total sales units; and x is the time period The following seasonal variations apply for each of the quarters (using the multiplicative model): Quarter 1 2 3 4 Seasonal Variation -15% +20% -10% +5% Calculate the forecast sales units for period 25, which is in the first quarter of year 5. units Downloaded by Hooria Noor (nhooria9@gmail.com) 9 lOMoARcPSD|27223832 10 2: St at i s t i c al t e c h n i qu e s 7 Which of the following statements is not an accurate statement of the limitations of using time series or regression analysis for forecasting? 8 A C C A MA It assumes that historical trends will continue to apply. It assumes that the pattern of seasonal variations will continue. The results become less reliable for predictions that are within the range of existing observations. It is less useful for longer term forecasting. The following data can be used in regression analysis to calculate the value of ‘b’ in the equation y = a + bx, where y = total cost, a = fixed cost and b = variable cost. n=7 ∑ 𝑥𝑥 = 28 ∑ 𝑦𝑦 = 112 ∑ 𝑥𝑥𝑦𝑦 = 532 ∑ 𝑥𝑥 2 = 140 The value of ‘b’ in the equation for total costs y = a + bx is: 9 If the correlation coefficient is 0.81, the coefficient of determination is equal to: 10 19.00% 34.39% 65.61% 81.00% A multiplicative model should be assumed. Quarterly sales of Product A in 20X0 are shown in the following table. Sales (units) Seasonal variation Q1 3,500 +40% Q2 3,300 +10% Q3 2,450 -30% Q4 3,200 -20% The trend value for Q3 sales (in units) is: units 11 Assuming a multiplicative model, if actual sales in Quarter 1 are 30,000 units and the seasonal variation for Quarter 1 is -25%, the trend (in units) for Quarter 1 is: units Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 2: St at i s t i c al t e c h n i qu e s 12 Assuming an additive model, the trend equation for forecasting sales is: Trend = 144,000 + 1,800Q (where Q = Quarter Number) Quarter 2 has a seasonal adjustment factor of +1,870 The forecast sales (to the nearest thousand units) for Quarter 2 are: 146,000 units 147,000 units 148,000 units 149,000 units 13 In 20X1, the base year for a price index, the price level was $400. By 20X4 the price level had risen to 448. What index number would represent the 20X4 level? 14 The quantity sold in a market for a commodity in 20X8 was 513,000 kg. The index number that corresponded to this quantity was 114. What was the base level of the index (the quantity where the index = 100)? kg 15 A spreadsheet is least likely to be used for which of the following tasks? Calculation of depreciation Writing a memo Budget preparation Analysis of sales by product Use the following information to answer the next two questions. Moonstar Ltd’s results for the second quarter of 20X3 were as follows. A 1 2 3 4 5 6 7 16 Sales Cost of sales Gross profit Other operating costs Operating profit Operating profit % B April 68,500 54,050 14,450 6,230 8,220 What would be the formula for May operating profit? =C2 – C3 =C2 * C3 =C4 – C5 =C4*C5 Downloaded by Hooria Noor (nhooria9@gmail.com) C May 71,250 56,120 15,130 6,610 8,520 D June 75,300 59,270 16,030 6,920 9,110 11 lOMoARcPSD|27223832 12 2: St at i s t i c al t e c h n i qu e s 17 What formula would go in B7? 18 A C C A MA =B4/B6*100 =B6/B4*100 =B6/B2*100 =B6/100*B2 A company has recorded its total cost for different levels of activity over the last five months as follows: Month Activity level Units 300 350 400 420 330 7 8 9 10 11 Total cost $ 16,000 18,500 21,050 21,750 17,800 The equation for total cost is being calculated using regression analysis on the above data. The equation for total cost is of the general form ‘y=a + bx’ and the value of ‘b’ has been calculated correctly as $25.00. What is the value of ‘a’? Select one: 19 $9,020 $10,020 $11,560 $12,560 If a garden pot cost $20 in 20X8. The price indices are as follows. 20X7 85 20X8 92 20X9 95 20Y0 101 How much does the pot cost in 20Y0 (to the nearest $0.01)? $ 20 Regression analysis is being used to find the line of best fit (y = a + bx) from ten pairs of data. The calculations have been done and the following information is available. ∑x = 420 , ∑y = 350, ∑x2 = 18,800, ∑y2 = 12,245, ∑xy = 15,100 What is the value of ‘a’ in the equation of the line of best fit? 18.52 19.27 20.52 21.27 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 2: St at i s t i c al t e c h n i qu e s 21 The price of the mye was $160 in 20X5 and $189 in 20X6. What is the simple price index for the mye in 20X6, using 20X5 as a base year? Downloaded by Hooria Noor (nhooria9@gmail.com) 13 lOMoARcPSD|27223832 14 3: Su mmari s i n g a n d a n a l y s i ng d a t a A C C A MA Chapter 3: Summarising and analysing data Objective test questions Expected values Use the following data to answer the next two questions. The matrix shows the various profit outcomes for three projects, X, Y, and Z, depending on whether the product price is $10 or the product price is $15. Profit Project X Y Z 1 Project X Project Y Project Z It is impossible to say If the two product prices are equally likely to occur, which project should be chosen? 3 P = $15 80 160 100 Using expected values, which project should be chosen? 2 P = $10 60 -28 40 Project X Project Y Project Z Either Project X or Project Z A company undertook a check of all invoices received from suppliers over a month and discovered the following error rates: Number of errors on invoice 0 1 2 3 4 5 or more Number of invoices 80 65 30 15 10 0 The expected number of errors per invoice is zero 0.72 1.00 1.05 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 3: Su mma ri s i n g a n d a n a l y s i ng d a t a 4 A sandwich salesman wants to determine how many sandwiches to order from the supplier every day. Daily customer demand could be 20 (30% probability), 30 (20% probability), 40 (35% probability) or 50 (15% probability). The salesman buys the sandwiches for $1 and sells them for $2.50. Any sandwiches which are not sold have to be thrown away at the end of that day. What is the optimum level of sandwiches to order? 5 20 30 40 50 A museum counts the number of visitors to a particular exhibit over the period of a month and the results are as follows: Number of visitors 0 – under 100 100 – under 200 200 – under 300 300 – under 400 400 – under 500 Frequency (Number of days) 5 9 6 7 3 The expected number of visitors is: 6 The most likely value of a series of numerical outcomes is known as the: 7 Expected value Mean Probability Standard deviation JAH is planning to produce and sell product MT. It has made the following forecasts about sales and costs. Production volume will equal sales volume and there will be no inventory. Sales (units) Probability Variable cost per unit Probability 30,000 0.1 $6 0.2 50,000 0.6 $8 0.3 70,000 0.3 $10 0.5 Fixed costs will be $80,000 for the production of up to 40,000 units and $100,000 if production is greater than 40,000 units. The selling price will be $12 per unit. What is the expected value of profit next year to the nearest $? $ Downloaded by Hooria Noor (nhooria9@gmail.com) 15 lOMoARcPSD|27223832 16 3: Su mmari s i n g a n d a n a l y s i ng d a t a 8 A project is thought to have a 0.6 probability of making a profit of $2,500 and a 0.4 probability of making a profit of $1,000. Find the change in expected profit if the probabilities actually turn out to be 0.55 and 0.45 respectively. 9 A C C A MA A fall of $75 A gain of $75 A fall of $150 A fall of $225 A broker has estimated the profits or losses for a particular investment and their respective probabilities as follows: Profit ($000) –1 1 3 5 Probability 0.1 0.3 0.4 0.2 The expected profit ($000) on this investment will be: 10 $2,000 $2,400 $2,600 $3,000 The results of a random test carried out on 400 boxes of glasses show the number of defective glasses found per box of six checked. Number of defective glasses per box checked 0 1 2 3 4 5 6 Number of boxes of glasses (frequency) 316 79 3 1 1 0 0 The expected number of defective glasses per box is (to 2 decimal places): 0.20 0.21 0.22 0.23 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 3: Su mma ri s i n g a n d a n a l y s i ng d a t a 11 A supermarket chain has 1,000 branches in Europe. The number of visitors to each store is counted on a particular day and the results are as follows: Number of visitors to store 0 – under 100 100 – under 200 200 – under 300 300 – under 400 400 – under 500 Frequency (Number of stores) 50 100 250 550 50 The expected number of visitors is: 295 300 305 310 Averages and distributions 12 Complete the blank in the following definition: “The is the most frequently occurring item in a population.” Select the correct option Average Median Mean Mode Use the following data to answer the next two questions. The following represent the number of rejects found each week during a 10-week quality control process: 1, 3, 5, 2, 2, 6, 1, 3, 4, 2 13 What is the median number of rejects? 14 2 2.5 2.9 3 In week 11, 1 reject is found. The new median number of rejects is: 1 2 2.5 3 Downloaded by Hooria Noor (nhooria9@gmail.com) 17 lOMoARcPSD|27223832 18 3: Su mmari s i n g a n d a n a l y s i ng d a t a 15 A C C A MA The following statistics relate to daily sales of a particular product within a four-week period : Daily sales ($) 0 to <$50 $50 to < $100 $100 to < $150 $150 to < $200 $200 to < $250 Midpoint x 25 75 125 175 225 Number of days (f) 2 3 7 12 4 28 f×x 50 225 875 2,100 900 4,150 What is the standard deviation? Use the following data to answer the following two questions. The quarterly purchases of material Z are as follows: Quarter 1 2 3 4 16 What is the variance and the standard deviation? 17 Purchases (units) 80 40 50 20 190 The variance is 47.5 and the standard deviation is 21.65 The variance is 468.75 and the standard deviation is 21.65 The variance is 26.5 and the standard deviation is 468.75 The variance is 468.75 and the standard deviation is 47.5 What is the coefficient of variation (to the nearest whole %)? % Use the following data to answer the following two questions. The heights of adult females are normally distributed with a mean of 163 cm and a standard deviation of 1.5 cm. 18 Clare falls within one standard deviation of the mean. What range of heights does she fall within? cm Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 3: Su mma ri s i n g a n d a n a l y s i ng d a t a 19 Jenny is extremely tall and is beyond 3 standard deviations away from the mean. What percentage of the population is Jenny taller than (to 3 decimal places)? 20 49.865% 50.135% 99.865% 99.952% Categorise each of the following data as discrete or continuous: Discrete Continuous Materials used – 5,000 kg Output produced – 1,000 units Time taken by labour – three hours 21 Which of the following statements about the median is true? 22 Some populations can have several medians. It gives the expected value of the population. It measures dispersion. It is the middle point of a population. A charity is analysing donations received from regular donors. It has produced the following table that shows the mean and standard deviation of donations in the most recent year (20X3) and three years ago (20X0). 20X3 $ $165 $38 Mean Standard deviation 20X0 $ $155 $41 Which of the following statements about this information is correct? 23 The standard deviations show that the amounts donated were less variable in 20X3 than in 20X0. The standard deviations show that the average donation has fallen. The means show that the average donation has fallen. The means show that the amounts donated were less variable in 20X3 than in 20X0. Which of the following sets of data has the widest spread? Mean Standard deviation A 125 20 B 150 25 C 175 20 Data A Data B Data C Data D Downloaded by Hooria Noor (nhooria9@gmail.com) D 200 25 19 lOMoARcPSD|27223832 20 3: Su mmari s i n g a n d a n a l y s i ng d a t a 24 A C C A MA The number of new orders received by five sales staff last week is as follows: 2, 4, 6, 8, 10 The standard deviation of the number of new orders received is 25 The number of daily complaints to a railway company has an average (arithmetic mean) of 12 and a standard deviation of 3 complaints. The coefficient of variation, measured as a percentage, is therefore: 26 1.33 2.83 6 8 0.25% 4% 25% 400% The number of rejects from 50 samples of the same size is as follows: Number of rejects in each sample 0 1 2 3 4 5 Number of samples (frequency of reject) 5 10 10 20 5 0 The arithmetic mean number of rejects per sample is: 27 2.2 2.4 3 20 The following statements relate to data analysis: I II 50% of scores are always less than the mean The variance measures the average spread of a population Which of the above statements are true? 28 I only II only Both I and II Neither I nor II Based upon evidence from a number of years, PCM’s sales revenue is believed to be normally distributed with a mean of $50,000 and a standard deviation of $8,000. The following calculations have been used to illustrate what these signify: I II $50,000 + (1.65 × $8,000) = $63,200 $50,000 – (1.65 × $8,000) = $36,800 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 3: Su mma ri s i n g a n d a n a l y s i ng d a t a Which of the following statements is correct? 29 The probability that sales revenue will be greater than $63,200 is 10%. The probability that sales revenue will be greater than $36,800 is 80%. The probability that sales revenue will be in the range $36,800 to $63,200 is 95%. The probability that sales revenue will be in the range $36,800 to $63,200 is 90%. The quarterly sales for Product MWR are as follows: Quarter 1 2 3 4 Sales (units) 500 400 800 200 1,900 The standard deviation is (to 2 decimal places): 30 The number of books read by a group of eight friends in one year was as follows: 2 5 0 3 5 4 4 1 The standard deviation of the number of books read, correct to 1 decimal place, is closest to: Downloaded by Hooria Noor (nhooria9@gmail.com) 21 lOMoARcPSD|27223832 22 4: Co s t i n g A C C A MA Chapter 4: Costing Objective test questions Cost classification 1 An organisation manufactures cars. Are the following production or non-production costs? Production costs 2 Production worker salaries Marketing campaign Factory electricity bill Head office stationary The cost of registering the patent Overtime premiums paid, exceptionally, to production factory workers to begin production Material components used to manufacture the new product Finance department costs Insurance paid by a manufacturing company on its factory buildings would be classified as: 4 M Co has just registered a patent and started to make a new product. Which of the following are direct costs? 3 Non Production costs Direct cost Production overhead cost Administration overhead cost Selling overhead cost A garage workshop calculates the prices of repairs by adding overheads to the prime cost and then adding 25% to total costs as a profit mark-up. The repair of the Peugeot was charged out at $690. Overheads of $69 were incurred. What is the prime cost of the repair? $ 5 A firm receives an invoice for using electricity. The invoice contains a service charge and charge per unit of electricity used. This is an example of what type of cost? Semi–variable cost Step-cost High-low cost Fixed cost Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 4: Co s t i n g 6 The best definition of a fixed costs are costs which 7 remain constant in total when output volume changes remain constant when measured per unit of output will never increase vary substantially in total, from month to month, when production is constant Direct expenses are any expenses which are incurred on a specific product other than direct material cost and direct labour. Is the following statement TRUE or FALSE? 8 A company pays $2 per unit as a royalty to the patent holder of a product. This cost would be classified as a 9 True False Dividend payment Production overhead Selling overhead Prime cost An indirect cost should be coded to: A cost object A cost unit A separate cost centre The cost centres that incur the costs Downloaded by Hooria Noor (nhooria9@gmail.com) 23 lOMoARcPSD|27223832 24 4: Co s t i n g A C C A MA Cost behaviour Use the following graphs to answer the next four questions. A Total cost $ Level of activity Total cost $ B Level of activity Total cost $ C Level of activity D Total cost $ Level of activity 10 Which graph BEST depicts the behaviour of a variable cost? 11 Which graph BEST depicts the behaviour of a semi variable cost? Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 4: Co s t i n g 12 Which graph BEST depicts the behaviour of a stepped fixed cost? 13 Which graph BEST depicts the behaviour of a fixed cost? 14 Which of the following statements BEST describes the behaviour of a stepped fixed cost? 15 Costs do not change with the level of activity until the activity level exceeds a certain point. They then increase, but then remain stable again until activity levels exceed another critical point. Costs do not change with the level of activity i.e. they vary with time rather than production. Costs consist of a fixed element plus an additional element that increases on a unit basis as the level of activity increases. Costs with no fixed element which vary as the level of activity varies. A factory incurred total costs at various output levels as follows: Number of units produced 9,000 12,000 15,000 19,000 24,000 Total cost ($) 50,000 59,000 72,000 89,000 110,000 Using the high-low method what is the fixed cost? $ 16 A factory incurred total costs at various output levels as follows: Number of units produced 10,000 13,000 17,000 21,000 25,000 Total cost ($) 50,000 64,000 80,000 102,000 95,000 Using the high-low method what is the fixed cost? $10,000 $20,000 $30,000 $40,000 Downloaded by Hooria Noor (nhooria9@gmail.com) 25 lOMoARcPSD|27223832 26 4: Co s t i n g 17 A C C A MA What is represented at point K on the scattergraph below? Cost K Activity level 18 A factory employs one supervisor for every 50 employees. What type of cost is the cost of supervisors’ salaries? 19 Fixed Variable Semi-variable Step Which of the following statements is false? 20 Marginal cost Variable cost per unit Fixed cost Step cost Variable costs are relevant for decision-making. Variable costs vary with a measure of activity. Variable costs are only variable in the short-term. Variable cost per unit is the same for each unit produced. Which of the following is not a fixed cost? Salary of chief executive Depreciation of factory building Insurance of motor vehicles Commission received by sales staff Use the following information to answer the next two questions A factory incurred total costs at various output levels as follows: Number of units produced 7,000 14,000 18,000 23,000 27,000 Total cost ($) 58,000 81,000 91,000 104,000 128,000 Management is aware that fixed costs increase by $12,000 if the number of units produced exceeds 25,000. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 4: Co s t i n g 21 What are the variable costs per unit? $ 22 What are the fixed costs, excluding the $12,000 stepped cost? $ Use the following information to answer the next two questions A factory incurred total costs at various output levels as follows: Number of units produced 4,000 10,000 13,000 17,000 24,000 Total cost ($) 60,000 108,000 123,000 157,000 195,000 Management is aware that variable costs decrease by $1.50 per unit if the number of units produced exceeds 20,000. 23 What are the variable costs per unit if production is less than 20,000 units? $ 24 What are the fixed costs? $ 25 The firm of solicitors is predicting its total costs for the next period. The past costs have been recorded at two activity levels. Number of cases Period 1 Period 2 380 480 Total costs $ 83,275 92,275 The firm is expecting to have to deal with 750 cases in the next period. Select one: 26 $46,500 $146,786 $131,468 $116,575 An organisation manufactures a single product. The total cost of making 4,000 units is $20,000 and the total cost of making 20,000 units is $40,000. Within this range of activity the total fixed costs remain unchanged. What is the variable cost per unit? $ Downloaded by Hooria Noor (nhooria9@gmail.com) 27 lOMoARcPSD|27223832 28 4: Co s t i n g 27 A C C A MA The following data relates to product XL. Expected monthly production is 40,000 units. $ Labour cost per unit Material cost per unit Variable overhead per unit Fixed overheads per month 4 3 2 10,000 What is the total cost of the budgeted monthly production of the XL? $ Cost coding 28 An organisation uses the following codes to classify its costs. Cost item Stationery Travel costs Membership subscriptions Code 100100 100200 100300 Department Head Office Customer services Publishing Teaching Code HO CS PB TCH What account code would be used for a membership subscription paid in respect of a member of the publishing team? Cost measurement 29 Which of the following is the definition of a cost centre? Any activity for which management may require costs to be measured A function or location for which costs are ascertained Any activity for which cost budgets are prepared A unit of production or service for which costs can be measured. Management of business units 30 Over which of the following is the manager of an investment centre likely to have control? Sales prices Capital investment Apportioned head office costs Controllable costs Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 5: A c c o u n t i n g f o r ma t e ri als Chapter 5: Accounting for materials Objective test questions Accounting for materials 1 24,400 units of product Oh have been ordered from suppliers. There are outstanding customer orders of 26,700 units. If 30,500 units of Product Oh are currently in inventory, what is the free inventory? units 2 Which of the following functions are fulfilled by a Goods Received Note? 3 Provides information to update inventory records Allows prices charged by supplier to be checked Allows quantities delivered by supplier to be checked Provides confirmation to supplier that payment has been made for goods An electrical goods retailer sells a popular make of DVD player. The retailer sells 25 DVD players on average each day and it takes 15 days for the retailer’s supplier to deliver orders for the DVD player. What is the reorder level for the DVD player? DVD players 4 Greenwood uses components at the rate of 459 units a month. Greenwood is open 6 days a week and 51 weeks per year. The supplier takes 5 days to deliver the goods having received an order. What is the reorder level for the component? units 5 Which of the following statements about inventories is incorrect? 6 Safety inventories are maintained in case there is unexpected demand. LIFO is based on the assumption that the oldest units are sold first. Daily demand has to be constant for the reorder level to be established by the formula Lead time in days × Daily demand A purchase requisition is completed when more inventory is required. What is the Economic Batch Quantity used for? Establishing the quantity to be produced Establishing the inventory required for production to take place Establishing the reorder level Establishing the reorder quantity Downloaded by Hooria Noor (nhooria9@gmail.com) 29 lOMoARcPSD|27223832 30 5: A c c o u n t i n g f o r mat e ri als 7 A C C A MA The demand for product Why is 600 units per month. The cost of each unit of Why is $25 and the annual cost of holding an item in inventory is 20% of purchase price. Ordering costs are $40 per order. Calculate the Economic Order Quantity of Why to the nearest unit. units 8 Dewie Limited uses 20,000 units of component Y during the year. The monthly cost of holding a unit of Y in inventory is $0.50. Dewie uses the Economic Order Quantity model as a basis for calculating its orders of Y and the Economic Order Quantity of Y is 1,200 units. What is the annual holding cost of Y? $ 9 Edted Limited uses 50,000 units of component W during the year. The annual cost of holding a unit of W in inventory during the year is $8. Edted uses the Economic Order Quantity model as a basis for calculating its orders of W and the Economic Order Quantity of W is 1,500 units. The cost of each order is $180. What is the total annual cost of W? $ 10 The materials inventory account for Tigs Limited is as follows: $ 12,000 17,000 1,000 30,000 Balances b/f Purchases Returns Work-in-progress Losses Balance c/f $ 14,000 1,500 14,500 30,000 Which of the following statements about this account are definitely true? 11 Which of the following is not included in the Economic Order Quantity formula? 12 The purchases figure represents the amount paid to suppliers. The losses figure includes any inventory that has been written off as obsolete. The returns figure is materials returned to suppliers. The work-in-progress figure represents materials issued to production. Purchase cost of item Quantity demanded Costs of keeping item in inventory Costs of ordering item from suppliers Which of the following documents is not a document that is sent to, or provided by, a supplier? Purchase requisition Purchase order Delivery note Invoice Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 5: A c c o u n t i n g f o r ma t e ri als 13 Could the costs of ordering and holding inventory be fixed or variable or both? Fixed 14 Ordering inventory Variable Holding inventory Dandy Limited uses 100,000 units of component Z600 during the year. The annual cost of holding a unit of Z600 in inventory during the year is $2. The cost of each order is $40. What is the Economic Order Quantity of Z600? units What is the total annual cost of Z600? $ 15 Herbage Limited uses 45,000 units of component Y300 during the year. The annual cost of holding a unit of Y300 in inventory during the year is $3. The cost of each order is $50. Herbage has just been offered a 5% discount on the purchase price of Y300 for orders of more than 2,000 units. The purchase price of one unit is $4. What is the optimum reorder quantity of Y300? units 16 Loxwood Limited manufactures components at the rate of 3,000 units a month. It costs $150 to set up the production line for a new batch. The annual demand for the product is 35,000 units. The Economic Batch Quantity is 5,000 units. What is the annual batch set-up cost for Loxwood Limited? $ 17 Leolion Limited manufactures 18,000 bookcases per annum. It sold 12,000 bookcases last year. The annual holding cost of 1 bookcase is $10. It costs $50 to set up the machinery for a new batch. The Economic Batch Quantity is 600 units. What is the total annual cost for Leolion Limited? $ Use the following information to answer the next two questions. Timted Limited manufactures 150,000 baskets per year. It sold 120,000 baskets last year. The annual cost of holding one basket is $10. It costs $75 to set up the machinery for a new batch. 18 What is the Economic Batch Quantity for Timted Limited? units Downloaded by Hooria Noor (nhooria9@gmail.com) 31 lOMoARcPSD|27223832 32 5: A c c o u n t i n g f o r mat e ri als 19 A C C A MA What is the total annual cost for Timted Limited? $ 20 FIFO assumes that the oldest items in inventory are issued first. 21 True False Danlion made purchases and issues of raw materials during the first week of May and had opening inventory figures on 1 May as follows. Quantity Purchase cost per unit $ 1 May Opening inventory 200 20 5 May Purchases 600 22 7 May Issues to work-in-progress 400 Which of the following methods will show the lowest figure for cost of materials issued to work-in-progress? FIFO LIFO AVCO Use the following information to answer the next six questions. Puppypup made the following purchases and sales of its most popular item, a large cuddly dog in October. The value of opening inventory was Date 1 5 8 11 23 30 22 Opening inventory Purchases Sales Purchases Sales Purchases Quantity 000 20 25 35 40 30 25 Calculate the value of closing inventory using the FIFO method. $ 23 Calculate profit for the month using the FIFO method. $ 24 Calculate the value of closing inventory using the LIFO method. $ Downloaded by Hooria Noor (nhooria9@gmail.com) Cost/Revenue per unit $ 15.00 15.50 24.00 17.25 24.00 17.25 lOMoARcPSD|27223832 A C C A MA 5: A c c o u n t i n g f o r ma t e ri als 25 Calculate profit for the month using the LIFO method. $ 26 Calculate the value of closing inventory using the average cost method. $ 27 Calculate profit for the month using the average cost method. $ 28 A company always determines its order quantity for a raw material by using the Economic Order Quantity (EOQ). What would be the effect on EOQ and the Total annual holding cost of inventory of an INCREASE in the cost of ordering a batch of materials? EOQ Annual holding cost 29 Higher Lower Unchanged The annual demand for an inventory item is 6,000 units. The cost of placing an order is $60 and the cost of holding an item in inventory for one year is $15. What is the EOQ to the nearest unit? Select one: 30 219 48,000 75 155 A Goods Received Note is matched against which TWO of the following documents? Purchase order Supplier’s invoice Supplier’s statement Stores requisition Downloaded by Hooria Noor (nhooria9@gmail.com) 33 lOMoARcPSD|27223832 34 6: A c c o u n t i n g f o r l ab ou r A C C A MA Chapter 6: Accounting for labour Objective test questions Accounting for labour Use the following information to answer the next three questions. In 20X2 Growler Ltd planned to make 50,000 units in 150,000 hours. In the end it made 60,000 units in 175,000 hours. 1 Calculate Growler’s labour efficiency ratio to 1 decimal place % 2 Calculate Growler’s labour capacity ratio to 1 decimal place. % 3 Calculate Growler’s labour production volume ratio to 1 decimal place. % 4 In Furryl Limited’s factory a standard working day is 8 hours. The rate of pay is $12 per hour. The standard time allowed to produce one unit is 6 minutes and there is a premium at basic rate of salary of 40% of time saved. On one day an employee produces 95 units. What is his pay for the day? 5 $96.00 $103.20 $114.00 $134.40 Which of the following might be costs validly incurred to prevent staff leaving an organisation? Training course costs Company doctor salary Commission to recruitment agency Costs of correcting poor work Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 6: A c c o u n t i n g f o r l ab ou r 6 Peter works with four other employees in a production process. As an incentive, the team can be rewarded by a bonus scheme where the team leader receives 40% of any bonus earned in the team scheme, and the remaining bonus is shared between Peter and the three other employees. On Tuesday the team worked 8 hours and produced 126 units. The standard time allowed for the production of one unit is 5 minutes. The group bonus is payable at $9 per hour on 60% of the time saved. What is Peter’s share of the bonus on Tuesday to the nearest cent? $ 7 Fluff Limited incurred basic pay costs of $60,000 in July. The overtime payments made were $5,000. 25% of the overtime could be allocated to specific jobs for which customers incurred the additional costs. What journal entries would be recorded in July in relation to these costs? Debit: Work in Progress Account $60,000, Overtime Premium Account $5,000 Credit: Labour $65,000 Debit: Work in Progress Account $61,250, Overtime Premium Account $3,750 Credit: Labour $65,000 Debit: Labour $65,000 Credit: Work in Progress Account $60,000, Overtime Premium Account $5,000 Debit: Labour $65,000 Credit: Work in Progress Account $61,250, Overtime Premium Account $3,750 Downloaded by Hooria Noor (nhooria9@gmail.com) 35 lOMoARcPSD|27223832 36 7: A c c o u n t i n g f o r o v e rh e ads A C C A MA Chapter 7: Accounting for overheads Objective test questions Accounting for overheads 1 A business has two production departments (P1 and P2) and two service departments (S1 and S2). Overhead costs have been apportioned to the departments as follows: P1 P2 S1 S2 $80,000 $120,000 $9,300 $6,000 S1 is expected to work a total of 50,000 hours for the other departments, split as follows: Total 50,000 hours P1 P2 S2 30,000 15,000 5,000 S2 is expected to work a total of 70,000 hours for the other departments split as follows: Total 70,000 hours P1 P2 S1 42,000 21,000 7,000 Using the reciprocal method, what overheads are apportioned to each of the production departments? 2 P1 $ P2 $ A factory production department budgets the following: Overhead Machine hours Direct material costs Direct labour hours Direct labour cost $80,000 1,000 $10,000 20,000 $150,000 The direct labour cost includes the wages of various employees who earn differing amounts based on their skills, grade and experience. As the department appears to be labour intensive, a direct labour hour rate would be an appropriate overhead absorption rate 3 True False A business absorbs production overheads in one of its departments on the basis of direct labour hours. There were 5,000 budgeted labour hours for the forthcoming period. The fixed production overhead absorption rate was $3.50 per hour. During the period the following actual results were recorded: Actual labour hours Fixed production overhead 4,000 $16,000 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 7: A c c o u n t i n g f o r o v e rh e a ds Which ONE of the following statements is correct? 4 Overhead was $1,500 over-absorbed Overhead was $2,000 under-absorbed Overhead was $3,500 under-absorbed Overhead was $3,500 over-absorbed A department absorbs overheads on the basis of machine hours. The budgeted and actual results of the department were as follows. Budget 20,000 2 hours a unit $400,000 Number of units Machine hours Overheads Actual 21,000 42,000 hours $410,000 Which of the following statements is correct? 5 Overhead was neither over absorbed nor under absorbed Overhead was $10,000 under absorbed Overhead was $10,000 over absorbed Overhead was $20,000 over absorbed A department has over absorbed fixed production overheads in the last month by $4,000. The fixed production overhead absorption rate, based on a budgeted level of activity of 2,000 units, was $5 per unit. Actual production was 3,000 units. What was the actual fixed production overhead incurred in the period? 6 $10,000 $11,000 $15,000 $19,000 Indicate whether the following statements are true or false of absorption costing: True False Only variable costs are assigned to cost units whilst fixed costs are treated as period costs Service department costs are reapportioned to production centres A production overhead associated with a cost centre should be allocated to that cost centre Only production overheads are allocated/apportioned to cost centres 7 Under-absorbed overheads always occurs when: Absorbed overheads are lower than budgeted overheads Actual overheads are lower than budgeted overheads Absorbed overheads are lower than actual overheads Absorbed overheads exceed actual overheads Downloaded by Hooria Noor (nhooria9@gmail.com) 37 lOMoARcPSD|27223832 38 7: A c c o u n t i n g f o r o v e rh e ads A C C A MA Use the following information to answer the next two questions. A production department has the following actual and budgeted data for the last period: Labour hours Variable production overhead per labour hour Fixed production overhead Actual Budgeted 1,000 1,250 $2 $2.50 $40,000 $38,000 Overheads are absorbed on the basis of the budgeted number of labour hours and budgeted expenditure. 8 The fixed production overhead absorbed during the period was: 9 The fixed production overhead absorbed during the period was: 10 $30,400 $32,900 $38,000 $40,000 Under-absorbed by $2,000 Under-absorbed by $7,600 Under-absorbed by $9,600 Over-absorbed by $12,000 An architectural practice recovers overheads on the basis of chargeable hours spent on each client. Budgeted overheads for the last period were $195,000. Actual chargeable hours were 4,000 and overheads were over-absorbed by $6,000. Actual overheads were $194,000. What was the budgeted overhead absorption rate per hour? $47 per hour $48.50 per hour $48.75 per hour $50 per hour Use the following information to answer the next two questions. A production department, which absorbs overheads on the basis of machine hours, budgeted at a machine hour absorption rate of $20 per hour. The following data is available: Actual overhead Budgeted overhead Actual machine hours 11 $410,000 $420,000 20,000 The number of machine hours the department had budgeted to work were: hours Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 7: A c c o u n t i n g f o r o v e rh e a ds 12 Overhead was $10,000 over-absorbed $10,000 under-absorbed Neither over nor under-absorbed $20,000 under-absorbed Use the following data to answer the next two questions. Budgeted machine hours Actual machine hours Budgeted overhead Actual overhead 13 What is the machine hour absorption rate? 14 $9.58 $9.68 $10.10 $10.00 What is the under-/over-absorbed overhead? 15 $ 48,000 46,000 464,640 460,000 $4,640 over-absorbed $14,720 under-absorbed $19,360 under-absorbed $24,841 over-absorbed The following relates to a business which absorbs overhead on the basis of labour hours. Budget 50,000 100,000 Direct labour hours Fixed overhead Actual 49,500 98,000 Which of the following statements is true? Overheads are under absorbed by $1,000 due to lower than expected labour hours Overheads are over absorbed by $1,000 due to lower than expected labour hours coupled with lower than expected expenditure Overheads are under absorbed by $2,000 due to lower than expected expenditure Overheads are neither over nor under absorbed Use the following information to answer the next three questions. A dental practice absorbs overheads based on the expected number of patients. A rate of $8 per patient has been calculated for absorbing fixed overheads. The following total overhead expenditure has been estimated at two activity levels: Number of patients Total overhead ($) 8,250 100,000 15,250 135,000 Downloaded by Hooria Noor (nhooria9@gmail.com) 39 lOMoARcPSD|27223832 40 7: A c c o u n t i n g f o r o v e rh e ads 16 What is the estimated level of variable overhead per patient, to the nearest cent? 17 $5 $8.85 $10 $12.12 What is the estimated fixed overhead? 18 A C C A MA $35,000 $58,750 $66,000 $122,000 What is the estimated number of patients that will be seen, to the nearest patient? patients 19 A cost centre has calculated its overhead absorption rate at $11 per direct labour hour based on estimated direct labour hours of 79,000. The actual direct labour hours worked last period were 78,500 and the actual overhead incurred was $861,000. What was the over- or under-absorbed overhead? 20 A company uses the direct method to reapportion service department costs. Use of this method suggests: 21 $2,500 under-absorbed $2,500 over-absorbed $8,000 under-absorbed $8,000 over-absorbed There are more maintenance than service departments. Service departments do not do any work for each other. The company uses a single overhead absorption rate. There will be no over or under-absorption of overheads. Which of the following would be the most appropriate method for allocating machine maintenance costs to departments in a factory? The number of machines in each department The floor area occupied by the machines The operating hours of the machines in each department The value of the machines in each department Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 7: A c c o u n t i n g f o r o v e rh e a ds 22 A product requires 5 hours of labour at $12.50 per hour and includes direct expenses of $100. If Absorption rates are $16.50 per direct labour hour then calculate the total cost per unit. Select one: 23 $189 $245 $232.50 $172.50 The following information is available for the two production departments (machining and assembly) and one service department (the canteen) at a manufacturing company. Machining $25,000 30 Budgeted overheads Number of staff Assembly $20,000 20 Canteen $11,000 5 After reapportionment of the service cost centre costs, what will be the overhead cost of the assembly department cost centre? Select one: 24 $25,500 $24,400 $24,000 $4,400 The production overhead control account for a company is as follows: $ 86,175 69,985 10,200 166,360 Expenses creditor Wages control Inventory control Total Work in progress Profit and loss $ 162,200 4,160 Total 166,360 Which of the following statements are correct? 25 I II III IV Indirect materials issued from inventory was $10,200 Overhead absorbed during the period was $86,175 Overhead for the period was over absorbed by $4,160 Indirect wages cost incurred was $69,985 I and IV I, II and III All four statements I, III and IV A company has four cost centres: Cost centre No of direct employees No of indirect employees Overhead allocated Process 1 A 4 2 $4,480 Process 2 B 12 4 $9,150 Downloaded by Hooria Noor (nhooria9@gmail.com) Process 3 C 14 6 $14,250 Process 4 D Nil 8 $4,200 41 lOMoARcPSD|27223832 42 7: A c c o u n t i n g f o r o v e rh e ads A C C A MA The canteen overhead of $40,640 is to be reapportioned on the basis of total number of employees in each process cost centre. After reapportionment, what is the total overhead allocated and apportioned to Production cost centre A. 26 $2,600 $4,480 $4,877 $9,357 A company manufactures two products, X&Y, in a factory divided into two production cost centres, Assembly and Finishing. The following information is available: Cost centre Allocated fixed overhead costs Direct labour minutes per unit Product X Product Y Assembly $144,000 36 48 Finishing $82,500 31.25 30 Budgeted production is 6,000 units of Product X and 7,500 units of Product Y. Fixed overhead costs are to be absorbed on a direct labour hour’s basis. What is the budgeted fixed overhead cost per unit for Product Y? 27 A company uses an overhead absorption rate of $3.20 per machine hour, based on 45,000 budgeted machine hours for the period. During the same period, the actual total overhead expenditure amounted to $140,875 and 45,500 machine hours were recorded on actual production. The overheads for the period are (choose one of the below) 28 $12 $15 $17 $18 Under absorbed by $4,725 Under absorbed by $3,125 Over absorbed by $4,725 Over absorbed by $3,125 A company’s packing dept has budgeted labour hours of 3,450 and budgeted overhead costs of $41,400. If the actual hours were 3,320 and the actual overheads were $40,860, the overheads for the period were: Under absorbed by $540 Over absorbed by $540 Under absorbed by $1,020 Over absorbed by $1,020 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 7: A c c o u n t i n g f o r o v e rh e a ds 29 The following extract of information is available concerning the four cost centres of X plc: Cost centre Department Number of direct employees Number of indirect employees Overhead allocated and apportioned Production Machinery 14 6 Production Finishing 12 4 Production Assembly 4 2 Service Canteen $78,400 $45,840 $25,500 $22,380 8 Allocation of overheads is based on the total number of employees working in each production department. After re-apportionment, what will be the total cost of the Finishing Department (to the nearest $)? 30 $45,840 $50,200 $54,366 $68,145 What is the journal entry for manufacturing overheads incurred? Debit Production Overheads Account Credit Bank and Cash Account Debit Bank and Cash Account Credit Production Overheads Account Debit Production Overheads Account Credit Work In Progress Account Debit Work In Progress Account Credit Production Overheads Account Downloaded by Hooria Noor (nhooria9@gmail.com) 43 lOMoARcPSD|27223832 44 8: A b s o rp t i o n a nd marg i n al co s t i ng ACCA MA Chapter 8: Absorption and marginal costing Objective test questions Absorption and marginal costing 1 Fill in the blank in the following definition. is ‘sales value minus variable cost of sales’. Select an option from the drop down box: Gross profit Contribution Absorption cost profit Variable cost profit 2 A business makes a single product and has budgeted figures for the next period as follows: Revenue per unit Direct material and direct labour per unit Absorbed fixed overhead per unit Variable overhead per unit $ 10 4 2 1 What is the budgeted contribution per unit? 3 Last month a production department had opening inventory of 3,000 units and closing inventory of 2,500 units. The profit of the department using marginal costing was $40,000. If the fixed overhead absorption rate was $4 per unit, the profit using absorption costing is: 4 $3 $4 $5 $6 $20,000 $30,000 $38,000 $42,000 M and Co’s budgets for the last period were Production Fixed overhead 10,000 units $200,000 Fixed overheads are absorbed on a per unit basis. Opening inventory at the start of the period was 500 units and closing inventory was 200 units. If the profit under marginal costing is $30,000 what is the profit under absorption costing? $24,000 $26,000 $34,000 $36,000 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 8: A b s o rp t i o n a nd marg i n al co s t i ng 5 In the last period a business sold 5,000 units of product X and its profit using marginal costing principles was $2,000. If absorption costing had been used, a loss of $10,000 would have arisen. If the business absorbed fixed production cost was $4 per unit, how many units were produced? 6 Last month a business had an absorption costing profit of $80,000. The opening inventory was 1,000 units and the closing inventory was 1,200 units. The fixed production overhead absorption rate was $3 a unit. What was the profit under marginal costing? 7 2,000 3,000 6,000 8,000 76,400 79,400 80,600 83,600 Last period, a business has an opening inventory of 40,000 units and a closing inventory of 42,000 units. Profits based on marginal costing were $600,000 whilst those based on absorption costing were $620,000. What was the fixed overhead absorption rate per unit? $ Use the following information to answer the next two questions. The data below relates to a company’s product: Sales price Direct material Direct labour Variable overhead Fixed overhead absorption rate $ per unit 100 22 10 8 15 Last month 9,800 units were sold. Budgeted production for the month was 10,000 units and 10,200 units were actually produced. Actual fixed overhead incurred were $140,000. 8 What is the marginal costing profit? $ 9 What is the absorption costing profit? $ Downloaded by Hooria Noor (nhooria9@gmail.com) 45 lOMoARcPSD|27223832 46 8: A b s o rp t i o n a nd marg i n al co s t i ng ACCA MA Use the following information to answer the next two questions. This information relates to each unit of a single business product produced by a company: Selling price Direct material and direct labour Variable overheads $105 $12 $13 Last period opening inventory was 1,000 units, 10,000 units were produced and 10,200 units were sold. Fixed overheads incurred were $75,000 and were absorbed over the units of production. 10 What is the marginal costing profit? $ 11 What is the absorption costing profit? $ 12 A business had an opening inventory of 1,000 units and a closing inventory of 1,500 units. The profit using absorption costing was $50,000 and the fixed overhead absorption rate was $12 per unit. What was the profit under marginal costing? 13 $32,000 $44,000 $56,000 $68,000 A business has the following budget: Sales Production Fixed production overhead 20,000 units 18,000 units $36,000 The business currently uses absorption costing. What would the effect on profit be, if it were to use marginal costing instead? 14 $4,000 lower $4,000 higher $48,000 lower $48,000 higher K manufactures a single product. The fixed overhead absorption rate was $4 per hour and 3 labour hours were required for each unit manufactured. The opening inventory was 1,500 units and the closing inventory was 2,000 units. The profit using absorption costing was $25,000. What was the marginal costing profit? $19,000 $23,000 $25,000 $31,000 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 8: A b s o rp t i o n a nd marg i n al co s t i ng 15 E Limited’s production budget for its first year of trading, during which 2,500 units are expected to be manufactured is as follows: $ 225,000 62,500 Variable production costs Fixed production costs The unit selling price is $275. Actual sales for the first year were 2,200 units whereas production was as budgeted. Comparing the profit calculated on an absorption or marginal basis, absorption costing profit is: Select one: 16 $34,934 lower $34,934 higher $7,500 lower $7,500 higher The following data is available for the period. Opening inventory Closing inventory Absorption costing profit 13,500 16,000 $32,750 What would be the profit for the period using marginal costing? 17 $35,250 $30,250 $36,750 Not possible to calculate A company manufactures and sells a single product. For this month the budgeted fixed production overheads are $96,000, budgeted production is 24,000 units and budgeted sales are 23,440 units. The company currently uses absorption costing. If the company used marginal costing, what would be the EFFECT on the budgeted profit? 18 $2,240 higher $2,240 lower $7,840 higher $7,840 lower A company has opening inventory of 27,500 units and closing inventory of 24,500 units. Profits based on marginal costing are $53,000 and $44,000 based on absorption costing. What is the fixed overhead absorption rate per unit? $ Downloaded by Hooria Noor (nhooria9@gmail.com) 47 lOMoARcPSD|27223832 48 9: P ro c e s s c o st i n g A C C A MA Chapter 9: Process costing Objective test questions Process costing 1 Any normal loss in a process account is valued at the same rate as good production whilst the abnormal loss is valued at scrap value If actual output is less than input but more than expected output, an abnormal gain occurs 2 True False M & Co’s production of a single product in a single process results in a 10% normal loss. This loss can be sold for scrap at $1 per kg. The following information is available for the last period: Direct materials 50,000 kg Direct labour Overheads absorbed Output $120,000 $60,000 $20,000 45,000 kg There was no opening or closing inventory. What is the value per unit of the output, to the nearest cent? $3.90 $4 $4.33 $4.44 Use the following information to answer the next three questions. M & Co’s production of a single product in a single process results in a 10% normal loss. Without any further processing, this loss can be sold for scrap at $1.50 per kg. The following information is available for the last period: Materials 20,000 kg Direct Labour Overheads Output $40,000 $6,000 250% of labour 16,000 kg There was no opening or closing work in progress. 3 What is the value credited to the process account, to the nearest $, for the scrap value of the normal loss? $ 4 What is the value of the abnormal loss, to the nearest $, for the above period? $ Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 9: P ro c e s s c o st i n g 5 What is the value of the output for period, to the nearest $? $ 6 6,000 kg of material costing $40 a kg were input into a process last period. The normal loss for the process is 10% and scrapped output can be sold for $10 a kg. 4,000 labour hours were worked at $10 an hour and there were 5,600 kg of good output. There was no opening or closing work in progress. What was the value of the good output per unit (to the nearest cent)? $49.29 $50.74 $51.11 $51.85 Use the following information to answer the next two questions. A product goes through two processes. Last month’s data for process two was as follows: Material transferred from process one Conversion costs Output transferred to finished goods Closing work in progress 3,200 litres at $5 a litre 8,500 2,800 litres 100 litres Normal loss is 5% of input. All losses are fully processed and have a scrap value of $3 a litre. Closing work in progress is fully complete for material but is only 20% processed. 7 What is the value of the completed output? $ 8 What is the value of the closing work in progress (to the nearest cent)? $ 9 A product passes through two processes. The last period’s details for process two are: Opening WIP Materials transferred in from process one Labour and overheads Output transferred to finished goods Closing WIP Nil 15,000 kg valued at $60,000 $26,000 12,000 kg 1,000 kg Normal losses are 10% of input and have a scrap value of $1 per kg. Closing work in progress is 100% complete for material and 50% complete for labour and overheads. What was the value of the closing work in progress? $4,797 $4,897 $5,300 $5,400 Downloaded by Hooria Noor (nhooria9@gmail.com) 49 lOMoARcPSD|27223832 50 9: P ro c e s s c o st i n g A C C A MA Use the following information to answer the next two questions. Product X is made in a single process, The following data relates to the last period: Material Labour Overhead Opening WIP 400 units $4,000 $5,000 $1,000 Closing WIP 200 units 100% complete 50% complete 20% complete Units added and costs incurred during the period 1,600 units at a cost of $16,000 $18,000 $4,000 There were no losses during the period. The weighted average method of inventory valuation is used. 10 What is the number of equivalent units to be used when calculating the labour cost per unit? 11 1,600 1,700 1,900 2,000 What was the value of the units transferred to finished goods? $ Use the following information to answer the next five questions. A product passes through two processes. Details of the first process were as follows. Input Cost of materials Labour and overheads Output transferred to Process 2 12,000 kg $30,000 $34,800 10,000 kg Normal loss is 10% of input and has nil scrap value. Details of the second process for the last period were: Input transferred from Process 1 Labour and overheads Output transferred to finished goods Closing work in progress 10,000 kg $27,000 8,000 kg 1,000kg Normal loss is 5% of input and has a scrap value of $3 a kg. Closing work in progress is 100% complete for materials and 50% complete for labour and overheads. There was no opening work in progress for either process and no closing work in progress for Process 1. 12 What is the quantity of abnormal loss for Process 1? kg 13 What is the value of the output from Process 1 transferred to Process 2? $ Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 9: P ro c e s s c o st i n g 14 What is the monetary value of the output from Process 2 for the period? $ 15 What is the monetary amount of the abnormal loss for Process 2? $ 16 What is the monetary value of the closing work in progress? $ 17 T produces a single product that passes through one process. The details for the process are as follows: Material input Direct labour Production overhead Normal losses 25,000 kg @ $3 per kg $29,250 $15,125 5% of input In Period 1 the output was 23,400 kg. Losses can be sold for scrap for $0.50 per kg. There was no opening and closing work-in-progress. What is the value of the abnormal loss that would be shown in the process account for Period 1? 18 $175 $1,575 $1,750 $1,925 A company produces a single product that passes through two processes. The details for Process 1 are as follows: Material input Direct labour Production overhead Normal losses 15,000 kg @ $4 per kg 27,400 14,600 10% of input, sold at $0.50 per kg In period 1 the output from Process 1 was 13,250 kg. There was no opening and closing work-inprogress. What is the value of the output to Process 2? $99,375 $100,111 $100,847 $101,125 Downloaded by Hooria Noor (nhooria9@gmail.com) 51 lOMoARcPSD|27223832 52 9: P ro c e s s c o st i n g A C C A MA Use the following information to answer the next four questions. FT Limited bought 26,000 units of material and produced two joint products, the pye and the mye, and one by-product, the tye. The tye is produced regularly when material goes through the process. The materials cost $88,000. The labour costs were $50,000 and the other overheads $39,000. The process produced 15,000 units of the pye that were sold at $20 per unit and 10,000 units of the mye that were sold for S40 per unit. The 1,000 units of the tye that were produced are sold for S2 scrap value per unit. 19 What were the costs of the pye, apportioning joint costs using number of units? $ 20 What were the costs of the mye, apportioning joint costs using number of units? $ 21 What were the costs of the pye, apportioning joint costs using sales value? $ 22 What were the costs of the mye, apportioning joint costs using sales value? $ 23 Which of the following statements is incorrect? By-products are sometimes sold as scrap. By-products are equivalent to abnormal losses. Any proceeds of one-off by-products should be credited to the statement of profit or loss. By-products have relatively low volume compared with other products that are produced at the same time. Use the following information to answer the next four questions. Tomtig Limited produces cleaning fluid using two processes. At the start of May 20X4 the first process had opening Work-In-Progress of 1,500 units. The materials included within these units were complete and valued at $50,000. 40% of the conversion costs consisting of labour and overheads valued at $9,000 had also been charged to these units. During May 20X4 6,400 units were transferred to the second process. There were no process losses. $330,000 was spent on materials and $54,000 on conversion costs. At the end of the period closing Work-In-Progress was 1,100 units. The materials within these units were complete. 30% of the conversion work had been undertaken. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 9: P ro c e s s c o st i n g 24 What is the value of the units transferred out using the weighted average method? $ 25 What is the value of closing Work-In-Progress using the weighted average method? $ 26 What is the value of the units transferred out using the FIFO method? $ 27 What is the value of closing Work-In-Progress using the FIFO method? $ 28 A company operates a process costing system using the FIFO method. No losses occur in the process. The following data relates to this month. Units 150 1,000 200 Opening WIP Completed in month Closing WIP Degree of completion 70% 100% 30% The cost per equivalent unit of production for this month was $11.00. What is the value of closing work in progress? 29 $495 $660 $1,650 $2,200 Two products G and H are created from a joint process. G can be sold immediately after splitoff. H requires further processing before it is in a saleable condition. There are no opening inventory and no work in progress. The following data are available for the last period. Total joint production costs Further processing costs (Product H) Product G H $384,000 $159,600 Selling price per unit $0.84 $1.82 Sales units 400,000 200,000 Closing inventory units 12,000 28,000 Using the physical unit method of apportioning joint production costs, what was the cost value at arriving at the closing inventory of Product H for the last period? Downloaded by Hooria Noor (nhooria9@gmail.com) 53 lOMoARcPSD|27223832 54 9: P ro c e s s c o st i n g A C C A MA Select one: 30 $36,400 $37,530 $40,264 $45,181 A company which operates a process costing system had work in progress at the start of last month of 400 units (valued at $1,800) which were 60% complete in respect of all costs. Last month, a total of 2,500 units were completed and transferred to the finished goods warehouse. The cost per equivalent unit for cost arising last month was $10. The company uses the FIFO method of cost allocation. What was the total value of the 2,500 units transferred as good output to the finished goods warehouse last month? $22,600 $22,800 $24,400 $26,600 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 10: O t h e r c o s t i ng t e c hn i q u e s Chapter 10: Other costing techniques Objective test questions Job and batch costing 1 A business operates a job costing system. The standard net profit margin for the business is 25% of sales. The estimated costs for job 200 are as follows: Direct Materials Direct Labour 2 kg at $5 per kg 3 hours at $8 per hour Selling, administration and distribution overheads are budgeted to be $100,000 for the period. They are recovered on the basis of the period’s total production cost of $500,000.The production overheads, which are recovered on the basis of a total of 30,000 labour hours are budgeted to be $200,000. What price will be quoted to the nearest cent for job 200? $ 2 The following details relate to job ZX during April. The job was completed at the end of April and a mark-up of 20% was charged on the costs of the job. Direct costs brought forward April transactions Materials transferred from stores Materials transferred from job WW Materials transferred to job XV Costs of labour Costs of production overheads $ 20,000 14,000 8,000 6,000 9,000 1,400 What price will be charged at the end of April for job ZX? 3 Which of the following are advantages of adopting a job costing system for the work of internal service departments? 4 $50,880 $53,000 $55,680 $58,000 Costs will be borne by user departments that incurred them. User departments may use service departments more carefully. It means that the efficiency of service departments can be measured. Budgeting service department expenditure should become easier. Complete the blank in the following definition: Batch costing is a form of specific order costing where costs are attributed to batches of product (unit costs can be calculated by dividing by .) Downloaded by Hooria Noor (nhooria9@gmail.com) 55 lOMoARcPSD|27223832 56 10: O t h e r c o s t i ng t e c hn i q u e s A C C A MA Select an option from the drop down box: the number of batches a batch the number of products in the batch a product Use the following information to answer the next two questions. A printing firm is going to offer a flier service to charities in its area. The following costs have been estimated for a batch of 5,000 leaflets. Machine set up costs Artwork Paper Other printing materials Labour $80 $25 per order $22.50 per 1,000 leaflets $18 4 hours at $8 per hour Fixed overheads are $4,500 per annum. They are allocated on the basis of orders received, with the number of orders received each year expected to be 150. Management requires 20% profit on selling price. 5 The selling price, to the nearest cent, for an order of 5,000 leaflets, is expected to be: $ 6 The selling price, to the nearest cent, per 5,000 leaflets, for an order of 20,000 leaflets is expected to be: $ 7 TG Co’s costs for job I14 consist of materials and labour, production and non-production overheads. Job I14’s production overheads were absorbed at a rate of $8 per labour hour, and non-production overheads were absorbed at a rate of 25% of prime cost. The mark-up on job I14 was 20%. Job I14 was billed for $9,000 and took 40 labour hours. What was the prime cost of job I14? $ 8 DL Co’s costs for job K16 consist of materials and labour, production and non-production overheads. Job K16’s production overheads were absorbed at a rate of $12 per labour hour, and non-production overheads were absorbed at a rate of 50% of prime cost. The margin on job K16 was 25%. Job K16 was billed for $12,000 and took 50 labour hours, with labour charged at an hourly rate of $44 per labour hour. What was the cost of materials on job K16? $ Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 10: O t h e r c o s t i ng t e c hn i q u e s Service and operation costing 9 Which of the following are characteristics of service costing? 10 High levels of direct costs as a proportion of total costs Use of composite cost units Appropriate cost unit depends on the service offered Service offered may be of short or long duration Calculate the most appropriate unit cost for a distribution function of a company using the following information: Miles travelled 2,037,000 Tonnes carried Number of drivers 8,798 67 Hours worked by drivers Tonne-kilometres carried 1,200,600 Cost incurred 2,194,900 11 Student Course Lecturer Lecturer hour Which of the following would be problems in using a cost per patient day measure to assess the performance of all the wards in a hospital? 13 $1.08 $1.83 $17.66 $249.48 Which of the following would be suitable cost units for a training company? 12 124,320 It does not indicate the quality of care provided. It does not include any indication of activity. It does not reflect the differing mixes of care required in different types of ward. It does not differentiate between the different sizes of wards. Which of the following would be appropriate cost units for a passenger coach company? I II III Vehicle cost per passenger-kilometre Fuel cost for each vehicle per kilometre Fixed cost per kilometre Select one: (I) only (I) and (II) (I) and (III) (II) and (III) Downloaded by Hooria Noor (nhooria9@gmail.com) 57 lOMoARcPSD|27223832 58 10: O t h e r c o s t i ng t e c hn i q u e s A C C A MA Alternative cost accounting approaches 14 How is target cost calculated? 15 Required selling price – Actual profit margin Required selling price – Required profit margin Market price – Actual profit margin Market price – Required profit margin Are the following statements TRUE or FALSE? Life cycle costing assesses costs on an accounting period basis. Life cycle costing clearly allocates development costs to individual products. 16 They fulfil financial reporting requirements by allocating costs to time periods. They differentiate between cost unit-based activities and product differentiating activities. They are suitable for high-volume, repetitive production processes. They focus on product development, where the majority of costs are incurred. At which stage of the Product Life Cycle does demand reach its limit and the organisation have to market the product in order to sustain its position? 19 Performance testing Re-inspection costs Product liability costs Costs of repairing items returned from customers Which of the following are true of traditional costing methods? 18 False Which of the following would be classified as external failure costs under total quality management? 17 True Introduction Growth Maturity Decline Activity based costing (ABC) in most suited to which ONE of the following situations? If labour costs are the most significant production cost If indirect costs are a high proportion of total costs If a company makes identical units of only one product If a company is operating in a manufacturing environment Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 11: N at u re a n d p u rp o s e o f bu d g e ti n g Chapter 11: Nature and purpose of budgeting Objective test questions Nature and purpose of budgeting 1 2 Indicate whether the following statements are TRUE or FALSE: True False A budget helps to control an organisation by forcing it to create a plan A budget helps an organisation to co-ordinate the allocation of resources A budget can help an organisation to motivate staff An organisation is legally required to prepare a master budget annually Which of the following best describes a top-down budget? A budget where proposed expenditure is scaled down until it matches available resources A budget that is compatible with the operational objectives of local management A budget where local budget holders do not participate in the budget-setting process A budget where central costs are budgeted prior to targets being set for local costs Budgetary control and reporting 3 A centre to which both revenues and expenses are assigned is known as a: Cost centre Profit centre Investment centre Control centre Behavioural aspects of budgeting 4 Which of the following is a disadvantage of involving staff in the budgeting process? Staff members’ contribution may be based on their local knowledge. Staff will not be motivated by helping to set targets that they can control. Staff suggestions may be ignored and staff may become demotivated as a result. Staff will include their specific resource requirements. Flexible budgets 5 A business has the following production cost budget: Budgeted production cost 10,000 units 15,000 units $70,000 $80,000 Downloaded by Hooria Noor (nhooria9@gmail.com) 59 lOMoARcPSD|27223832 60 11: N at u re a n d p u rp o s e o f bu d g e ti n g A C C A MA The budgeted production cost for a level of activity of 12,000 units is: $ 6 The budgeted production overhead for a business is $200,000 at an activity level of 100,000 units and $300,000 at an activity level of 200,000 units. If the actual activity level is 140,000 units, the flexed budget for production overhead is: 7 Which of the following is an advantage of fixed budgeting? 8 $300,000 $280,000 $240,000 $210,000 It is based on assumptions that normally turn out to be true in practice. It is quicker to carry out than flexible budgeting. It provides appropriate benchmarks for cost control. It is useful for decision-making purposes. A company has drawn up the following flexed budget for the year. 60% $ 150,000 60,000 42,000 30,000 Variable materials Variable labour Production overhead Other overhead 70% $ 175,000 70,000 46,000 30,000 What would be the total cost in a budget that is flexed at the 85% level of activity? Select one: 9 $380,800 $374,500 $379,500 $668,000 Complete the following statement: A fixed budget is Select one: A budget for fixed costs only A budget for a single activity level A budget for all costs of production A budget for all possible sale volumes Downloaded by Hooria Noor (nhooria9@gmail.com) 80% $ 200,000 80,000 50,000 30,000 lOMoARcPSD|27223832 A C C A MA 11: N at u re a n d p u rp o s e o f bu d g e ti n g Multi task questions 1 ALANOWL The new management accountant at Alanowl Limited is completing a budget for Quarter 1 of next year for its principal product. The product was launched just under five years ago and demand has steadily increased. The accountant has modelled demand using a multiplicative time series model with the equation Sales = 15,000 + 1,000Q, with Q = the quarter number. Quarter 1 is Quarter 20 and its demand was expected to be 1.05 of trend. However a recent marketing campaign has been very successful with the result that demand is expected to be 44,000 units. The accountant has found it difficult to split the costs of this product into fixed and variable elements. He knows costs include costs of quality inspection. Quality inspection costs are $28,000 for each quarter, with an additional $7,200 for every 10,000 units produced, because of the additional time required. Other costs for the product for the fourth quarter of this year, when production and demand were 34,000 units, were $758,000. The accountant estimates that other costs for a demand level of 44,000 units will be $928,000. He believes that variable costs per unit will decrease by $0.50 per unit if production and demand exceed 40,000 units, because of the availability of discounts from suppliers. The accountant is assuming that production and sales for each quarter will be the same. Sales price per unit is $35. Required: (a) Calculate the sales revenue that Alanowl would have received in the next quarter, had sales continued to follow the time series model. $ (2 marks) (b) Complete the budget proforma, comparing the budget for Quarter 4 in the current year with Quarter 1 next year. Quarter 4 $ Quarter 1 $ Sales Quality costs Other fixed costs Variable costs Profit (6 marks) (c) The accountant is wondering whether it is still worth using a multiplicative time series model to attempt to predict demand. Which of the following is not a disadvantage of a multiplicative time series model? The model is likely to become less reliable the further into the future it is taken. Random variations can upset the pattern of trend and seasonal variations. The reliability of the forecast is very dependent on the quantity and quality of the data supporting it. The model cannot cope with an increasing or decreasing trend. (2 marks) (10 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) 61 lOMoARcPSD|27223832 62 11: N at u re a n d p u rp o s e o f bu d g e ti n g A C C A MA 2 WORSLEY LIMITED The Chief Executive of Worsley Limited is angry. He has just seen the cost figures for the production of the company’s principal product for May and wants to know why they were so much higher than budgeted. The budgeted selling price of the product was $70. In May Worsley aimed to produce and sell 6,000 units. Each unit requires 3 kg of material at $5 per kg and 2 hours of labour at $8 per hour. Variable overhead is $6 per unit. The Managing Director has been reviewing the following statement. (Bracketed figures mean that revenues were lower, or costs or resource usage were higher, than budgeted.) Sales Sales revenue Costs Material Labour Variable overhead Resource usage Material Labour Budgeted 6,000 units $ 42,000 Actual $ 42,000 Difference $ - $ 90,000 96,000 36,000 $ 136,000 143,000 47,000 $ (46,000) (47,000) (11,000) 18,000 kg 12,000 hr 28,000 kg 18,500 hr (10,000 kg) (6,500 hr) In anticipation of marketing activity by Worsley’s competitors, Worsley’s Sales and Marketing Director authorised a large price cut so that the average selling price during May was $42. As a result 10,000 units were produced and sold. Required: (a) Complete a revised statement comparing the costs and resource usage that would have been budgeted, and also including sales revenue figures, for a production level of 10,000 units. Budgeted 10,000 units Sales Actual $ Sales revenue Costs Difference $ $ 42,000 $ $ Material 136,000 Labour 143,000 Variable overhead $ 47,000 Resource usage Material kg 28,000 kg kg Labour hr 18,500 hr hr (6 marks) (b) Which TWO of the following statements about fixed budgets are true? Fixed budgets are useful at the planning stage to establish broad objectives. Variance analysis using fixed budgets allows for variations in volume. Fixed budgets are easier to prepare than flexible budgets. Use of fixed budgets generally gives management realistic cost targets to achieve. (2 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 11: N at u re a n d p u rp o s e o f bu d g e ti n g The Sales and Marketing Director has claimed that if prices had been left unchanged, sales revenues would be affected by competitor marketing activity. A member of the Accounts Department has reviewed these claims and has estimated that there is a correlation coefficient between marketing expenditure by Worsley’s principal competitor and Worsley’s total sales revenue of – 0.8, and that Worsley’s total sales revenue is the dependent variable. (c) Which ONE of the following statements about this calculation is TRUE? A negative figure indicates a weak correlation between competitor marketing expenditure and Worsley’s sales revenues. The coefficient of determination indicates how much of the change in total sales revenue is due to the competitor’s marketing activity. The coefficient of determination is – 0.64. The competitor’s marketing expenditure is 80% of Worsley’s sales revenues from this product. (2 marks) (10 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) 63 lOMoARcPSD|27223832 64 12: B u d g e t p re p arat i o n A C C A MA Chapter 12: Budget preparation Objective test questions Budget preparation 1 Which ONE of the following is not a functional budget? 2 Which of the following costs would not be included in the cash budget of a publishing company? 3 Finished goods inventories are budgeted to increase Finished goods inventories are budgeted to decrease Raw materials inventories are budgeted to increase Raw materials inventories are budgeted to decrease A business has no production resource limitations. Which TWO of the following must be available BEFORE a raw materials purchases budget can be completed. 5 Overtime payments paid to proof-readers Depreciation of printing machine Capital cost of printing machine Administrative expenses A business has budgeted for a greater quantity of material in its material usage budget than it has in its material purchases budget. Which of the following statements can be inferred from this situation? 4 Labour budget Selling and distribution cost budget Cash budget Administration cost budget Sales budget Selling and distribution budget Production budget Direct Labour budget Overhead budget M & Co’s sales budget shows budgeted sales of 2,500 units of product X next quarter. Budgeted inventories are: Opening inventory Closing inventory 200 units 300 units How many units of product X (to the nearest unit) should be included in the production budget for the next quarter? units Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 12: B u d g e t p re p arat i o n 6 Budgeted sales of product X are 19,950 units. 5% of all units of X produced are scrapped at the end of the production process by the quality control department. Inventories, which have all passed quality control, are budgeted to be as follows: Product X 1,000 units 1,475 units Opening inventory Closing inventory How many units need to be in the production budget for X in the above period? 7 19,950 units 20,425 units 21,000 units 21,500 units Budgeted sales of product X next quarter are 10,000 units. Each unit of X needs 3 kg of raw material. Budgeted inventories are as follows: Opening inventory Closing inventory Product X 1,000 units 850 units Raw material 500 kg 1,200 kg What are the budgeted purchases of raw materials for the next quarter? 8 29,550 kg 30,000 kg 30,250 kg 30,700 kg A job needs 2,990 actual labour hours and it is anticipated that there will be 8% idle time. If the wage rate is $9 an hour, what is the budgeted labour cost for the job? $ 9 M and Co produce X. Each unit of X needs 3 direct unskilled labour hours costing $8 an hour. M and Co’s quality control department reject 5% of all units produced at the end of the production process. All inventories of finished goods have been accepted by the quality control department Budgets for the next period are: Opening inventory of finished goods Closing inventory of finished goods Sales 5,000 units 4,000 units 40,995 units What is the direct unskilled labour budget, to the nearest $, for the period? 10 $959,880 $1,010,400 $1,007,880 $1,035,663 M & Co’s budgeted sales figures are: September October November $ 100,000 120,000 80,000 Downloaded by Hooria Noor (nhooria9@gmail.com) 65 lOMoARcPSD|27223832 66 12: B u d g e t p re p arat i o n A C C A MA 20% of monthly sales are for cash. Remaining sales are on credit. Of the credit sales, 60% are expected to pay in the month after sale and take a 2% discount, 38% are expected to pay in the second month after sale, and the remaining 2% are expected to be bad debts. Budgeted cash receipts in November are: $16,000 $72,448 $102,848 $104,000 Use the following information to answer the next two questions. A business manufactures and sells a product each unit of which requires 30 minutes of direct labour and 1 kg of raw material. The wage rate is $11 per hour and the raw material costs $2 per kg. Budgeted figures are: September 100,000 4,000 Sales units Completed opening inventory October 122,000 2,000 November 80,000 8,000 The product is produced one month prior to sale and wages are paid in the month of production. Raw materials are paid for in the month following purchase and there is no raw materials inventory. 11 The figure to be included in October’s cash budget for wages is: 12 The figure to be included in October’s cash budget for raw material is: 13 $440,000 $473,000 $649,000 $660,000 $160,000 $172,000 $240,000 $244,000 M and Co invoices customers on the last day of each month. Customers paying in the following month are entitled to a 1% settlement discount. Budgeted sales values are: May $60,000 June $40,000 July $45,000 M & Co anticipates the following: Invoices paid one month after sale Invoices paid two months after sale Bad debts 75% 20% 5% The receipt to be shown in the cash budget in July is: $ Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 12: B u d g e t p re p arat i o n 14 M Ltd is preparing its production budget for Product Y. Budgeted annual sales are 4,000. Opening inventory is 750 units and M Ltd wants to increase inventories by 20% at the year end. Calculate budgeted production for the year. Select one: 15 3,250 4,000 4,150 4,750 A company has budgeted sales of 12,000 units. 5% are scrapped as they do not pass quality control. Opening inventory is 1,450 and closing inventory needs to increase by 200 units. All inventory needs to have passed quality control. The production budget will be (to the nearest whole unit)? Select one: 16 10,500 12,200 12,631 12,842 A retailer sells an item for $600 on which there is a mark-up of 25%. What profit did the retailer make on this transaction? Select one: $90 $120 $150 $200 Capital budgeting 17 Which of the following would be part of a capital expenditure budget? Construction of an extension of an existing building Replacement of motor vehicles Repairs to machinery Refurbishment of head office- Downloaded by Hooria Noor (nhooria9@gmail.com) 67 lOMoARcPSD|27223832 68 12: B u d g e t p re p arat i o n A C C A MA Multi task question 1 MOONSTAR The accountant of Moonstar Limited is currently preparing the cash budget for the company for January. The following information is available. (a) The opening balance at the bank on 1 January was $378,400. (b) Moonstar’s sales in November were $525,000 and in December were $685,000. Expected sales revenue for January is $480,000. 10% of sales are for cash. 60% of revenue from credit sales is received the month after the sale takes place, 35% 2 months after and 5% of credit sales are written off as bad debts. (c) Moonstar intends to sell off six of its fleet of vans for cash in January. The average profit on each sale should be $2,000 and Moonstar should receive an average of $6,000 for each van. (d) Moonstar’s purchases in December were $384,000. It originally planned to make purchases of $366,000 in January. Moonstar normally pays suppliers the month after purchases are made. However Moonstar’s major supplier has offered Moonstar a 2% discount provided it pays for its purchases in the month that purchases are made and Moonstar will accept this discount. 15% of the value of Moonstar’s planned purchases for January will be from this supplier. (e) Employee salaries for December were $42,000 and employees are due to receive a 5% pay increase in January. Employees will also receive a 3% bonus in January, based on annual salaries at the end of the previous year. (f) Moonstar took out a 10 year loan from its bank of $1 million two years ago. The loan is repayable in ten equal annual instalments, on 1 January each year. Interest on the loan is payable twice yearly, in June and December. Required: (a) Complete the cash budget for January. $ Cash receipts Receipts from accounts receivable Cash sales Sale of non-current assets Cash payments Payments to suppliers ( ) Payments to employees ( ) Loan repayment and interest ( ) Cash movement ( ) Opening balance 378,400 Closing balance (8 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 12: B u d g e t p re p arat i o n The forecasts for sales for the rest of the year are very favourable and the Finance Director of Moonstar Limited anticipates having a cash surplus throughout the year. (b) Which two of the following would be actions that Moonstar could take to make use of the predicted surplus? Pay off some of the rest of the loan Delay payments to suppliers Offer more generous credit periods to customers Minimise inventory levels (2 marks) (10 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) 69 lOMoARcPSD|27223832 70 13: Di s c o u n t e d c as h f l o w A C C A MA Chapter 13: Discounted cash flow Objective test questions Discounted cash flow 1 Timothy will receive an annual income of $4,000 for four years, with the first payment occurring in three years’ time. Timothy’s cost of capital is 5%. The present value of the annuity payment is: 2 An investment of $6,000 is made in a 5 year fixed term deposit account which pays interest at the nominal rate of 7% per annum. If interest is applied in six monthly instalments, and left in the account to accumulate, what balance will be on the account at the end of year 5 (to the nearest $)? 3 $12,868 $14,184 $16,000 $20,304 $8,464 $8,415 $8,100 $7,126 An investor has been offered the opportunity to invest a sum of money now, at a fixed interest rate of 7% per annum, which will be used to generate an annual year-end income of $21,000 in perpetuity. How much needs to be invested now? $ 4 Jackson takes out a loan of $5,000 at an interest rate of 9% per annum. The loan is to be paid back over 5 years in equal annual instalments. The annual instalment (to the nearest $) is: 5 $703 $1,000 $1,285 $1,450 $38,000 is invested in a bank account. The account earns compound interest at 3% per annum. The cash value of the account, to the nearest $, at the end of eight years will be: $46,735 $47,120 $47,869 $48,137 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 13: Di s c o u n t e d c a s h f l o w 6 $x is invested in a bank account. The account earns compound interest at 4% per annum and after 10 years the investment is worth $14,802. The value of the original investment (to the nearest $100) is: $ 7 Rental income of $800 is to be received over a period of four successive years. The tenant is required to pay the first rental payment in advance (i.e. now). Interest rates during this fouryear period are unchanged at 5%. The present value (to the nearest $) of this rental income is: 8 $3,000 is invested for four years at a six-monthly interest rate of 5%. At the end of four years the investment will be worth (to the nearest $): 9 $2,178 $2,478 $2,778 $2,978 $3,600 $3,647 $4,040 $4,432 Teddy is expecting to receive $9,000 starting in a year’s time and continuing indefinitely. Interest rates are expected to remain constant at 6% in perpetuity. What is the present value of Teddy’s perpetuity? $ 10 Sydney invests $2,000 with compound interest at 6%. At the end of four years he withdraws $750 from his investment and keeps the remaining sum on investment for another two years. What is the value of Sydney’s investment to the nearest cent at the end of six years? $ 11 Darwin invests $4,000 with nominal interest rate 9%, compounded monthly. What is the value of Darwin’s investment to the nearest cent at the end of two years? $ Use the following data to answer the next two questions. Auckland invests $8,000 for four years at a 2% quarterly interest rate. 12 What is the value of Auckland’s investment at the end of four years to the nearest cent? $ Downloaded by Hooria Noor (nhooria9@gmail.com) 71 lOMoARcPSD|27223832 72 13: Di s c o u n t e d c as h f l o w 13 A C C A MA What is the effective annual rate of interest on Auckland’s investment to two decimal places? % 14 What is the annual percentage rate (APR) if interest is compounded quarterly and the quarterly rate is 2.5%? The answer needs to be in % to 2 decimal places. % 15 Dave will receive $2,500 each year for 12 years, starting in one year’s time. What is the present value if interest rates are 9%? Answer to the nearest $. $ 16 Hilda intends to take out a loan for $72,000. The loan will be paid back over six years in equal annual instalments, with the first instalment due to be paid in 12 months’ time. The annual interest rate on the loan is 8%. What is the annual repayment on the loan, to the nearest $100? $ Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 14: I n v e s t me n t ap p rai s al Chapter 14: Investment appraisal Objective test questions Investment appraisal 1 A project has the following cash flows: Year 0 1 2 3 $ (100,000) 20,000 40,000 70,000 Using 10% as the discount rate, calculate the net present value to the nearest $000. $ 2 An investment has an NPV of $24m at 5% and an NPV of -$6m at 10%. Calculate the internal rate of return of the investment. % 3 An investment project has an initial investment when it begins followed by constant annual returns. How is the payback period calculated? 4 Initial investment/Annual profit Initial investment/Annual cash inflow Annual profit/Initial investment Annual cash inflow/Initial investment Company X needs to use two materials for a specific job. The job requires 700 kg of Material A and 400 kg of Material B. A is used regularly by X. There are 500 kg in inventory that were purchased for $2,000. The scrap value of A is $1.00 per kg. A can be purchased on the open market currently for $5 per kg. There are 300 kg of spare inventory (not needed elsewhere in the business)of B currently in inventory that were purchased for $450. B has no resale value. B can be purchased on the open market currently for $2.50 per kg. The relevant cost of materials for this job is: $1,250 $3,700 $3,750 $4,500 Downloaded by Hooria Noor (nhooria9@gmail.com) 73 lOMoARcPSD|27223832 74 14: I n v e s t me n t ap p rai s al 5 Which of the following are problems with using the simple payback method of investment appraisal? 6 A C C A MA It is difficult to understand. It ignores the time value of money. It uses profits, not cash flows. The result by itself does not tell you whether to accept or reject a project. Teddy is considering purchasing a new machine. The relevant cash flows are: Year Cost Inflows 1 2 3 $ 120,000 45,000 80,000 100,000 Calculate the discounted payback period of the new machine in months. Teddy’s cost of capital is 7%. months 7 Complete the blank in the following definition: A is a future incremental cash flow Select an option from the drop down box: Sunk cost 8 Relevant cost Variable cost Growler Ltd is about to invest in an operation to extract minerals from a site of natural beauty near the coast of the country in which it is located. The cost of the investment will be $360 million. The net cash inflows from the investment are expected to begin two years after the investment and be $100 million in years 2 to 4, $125 million in year 5 and $115 million in year 6. After extraction has finished at the end of six years, Growler Ltd will have to undertake rectification work on the area. Rectification will take a year and the costs of rectification will be $18 million, incurred at the end of the year. Growler Ltd uses a cost of capital of 9% to appraise its investments. What will be the net present value of this investment, to the nearest $m? $ 9 Flexible cost million Dandy Ltd makes three different products. Details of the unit costs for these products are as follows: Alpha Beta Gamma $ $ $ Direct costs per unit Material 50 60 75 Labour 38 55 48 Overheads Variable 23 28 32 Absorbed fixed 15 Downloaded by Hooria Noor (nhooria9@gmail.com) 28 25 lOMoARcPSD|27223832 A C C A MA 14: I n v e s t me n t ap p rai s al Dandy can buy in units of Alpha for $145, of Beta for $170 and of Gamma for $150. Which products should Dandy make and which products should Dandy buy in? 10 Buy in all three products Make Alpha, buy in Beta and Gamma Make Alpha and Beta, buy in Gamma Make Alpha and Gamma, buy in Beta F is currently drawing up a quote for a job that has to be completed within one week. The job requires 50 skilled labour hours and 25 unskilled labour hours. Currently skilled workers are paid $875 and unskilled workers $420 for a 35 hour week. Currently skilled labour has spare capacity amounting to 30 labour hours and unskilled labour has spare capacity amounting to 35 labour hours. If spare capacity has already been utilised and the time spent on the job is in excess of 35 hours by either skilled or unskilled labour, then overtime is payable by the hour at 120% of the current salary per hour for every hour that exceeds 35 hours. What is the total relevant cost to F of using skilled and unskilled labour on this job? 11 12 $450 $500 $575 $1,625 For decision-making purposes, which of the following are relevant costs? I II III IV Unavoidable costs Opportunity costs Sunk costs Absorbed costs I II only I II III only II IV only I IV only A project has the following cash flows: Year 0 1 2 3 $ (150,000) 30,000 70,000 80,000 Using 5% and 10% as the rates in the calculation, calculate the internal rate of return to 1 decimal place 5.7% 6.5% 8.5% 9.3% Downloaded by Hooria Noor (nhooria9@gmail.com) 75 lOMoARcPSD|27223832 76 14: I n v e s t me n t ap p rai s al 13 A C C A MA A project has a positive NPV of $3,450 at a discount rate of 10% and a negative NPV of-$2,657 at a discount rate of 14%. What is the project’s estimated IRR to 2 decimal places? % 14 A business is looking to invest in a project which will cost $120,000 and generate the following cash inflows at the end of Years 1 – 4. Year 1 2 3 4 Cash inflow ($) 15,000 25,000 35,000 40,000 The business’s cost of capital is 4%. The net present value of the project (to the nearest $100) is: 15 $(17,100) $(17,200) $(17,300) $(17,400) The following statements relate to net present values and internal rates of return. I A project is worthwhile if its net present value is greater than $0 II If the cost of capital of a business is greater than the internal rate of return of a proposed project, then the project should be accepted. III One of the disadvantages of the net present value method of project appraisal is that is does not show the change in shareholders’ wealth. IV It is not possible to have more than one internal rate of return for a project that is being appraised. Which of the above statements are true? 16 Only Statement I Statements I and II Statements I and III Statements I and IV The net present value of Project L at 10% was $1,200 and at 15% it was $(400). The internal rate of return of the project (to the nearest whole percent) is: 11% 12% 13% 14% Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 14: I n v e s t me n t ap p rai s al 17 A project has an initial investment of $85,000. What will the payback period be in years (to 1 decimal place) if the project generates profit of $25,500 p.a. and is to be depreciated straight line over 10 years to a zero residual value. Select one: 18 5.0 3.3 2.5 8.5 If the NPV of a project at a 6% discount rate is $25,000 and the NPV at a 14% discount rate is $10,000, what is the best estimate of the IRR of the project? Below 6% Above 14% Approximately 9% Approximately 12% Multi task questions 1 MAURICE LTD Maurice Ltd is about to make an investment in facilities to produce a new product. The following spreadsheet will be used to appraise the investment. 1 2 3 4 5 6 7 8 9 10 11 12 A Year B 0 $000 Revenues Cost of investment Running costs Net cash flow Discount factor 5% Discount factor 10% Discounted cash flow 5% Discounted cash flow 10% Net present value at 5% Net present value at 10% C 1 $000 450 D 2 $000 550 E 3 $000 650 F 4 $000 700 (240) 210 0.952 0.909 (295) 255 0.907 0.826 (335) 315 0.864 0.751 (355) 345 0.823 0.683 (900) (900) 1.000 1.000 Required: (a) Calculate the payback period for this investment in months. months (b) Calculate the discounted payback period for this investment to the nearest month, using a discount rate of 5%. months (c) (2 marks) (2 marks) Calculate the Internal Rate of Return of this investment, using discount rates of 5% and 10%, to the nearest 0.1%. % Downloaded by Hooria Noor (nhooria9@gmail.com) (2 marks) 77 lOMoARcPSD|27223832 78 14: I n v e s t me n t ap p rai s al (d) Which of the following formula would correctly calculate the discounted cash flow in cell C9? (e) A C C A MA = (SUM(C3:C6))*C7 = (SUM(C3:C6))/C7 = C6*C7 = C6/C9 (2 marks) Which of the following list are advantages of the discounted payback method of investment appraisal? Advantage? Yes No It considers the time value of money. It considers cash flows over the whole life of a project. The answer provides a clear decision rule. It uses relevant cash flows. (2 marks) (10 marks) 2 EDRICH LIMITED Edrich Limited is going to convert one of its out-of-town discount outlets into a new retail outlet selling top quality goods. The following costs and benefits relate to the change. (a) The costs of converting the outlet will be $100,000 in total. This includes $5,000 already spent surveying customer reactions to the proposed change. (b) The annual light and heat costs of the building are expected to rise from $10,000 to $12,000. (c) Depreciation on shop fixtures and fittings will rise from $12,000 to $15,000 per year. (d) The notional rent will charged by Head Office will rise from $60,000 to $75,000 per annum. (e) Six extra staff will be required in the shop to provide a higher standard of service. Their average annual salary will be $30,000. Two of them will be newly recruited and four of them will be relocated from existing shops, where they will not be replaced. Relocation costs are expected to be $5,000, incurred during the first year the outlet is open in its new form. (f) Current sales from the outlet are $600,000 per annum and would be expected to rise by 10% per annum after the end of the next year if the outlet was not converted. The new outlet is expected to make sales of $800,000 per annum in its first year of trading, rising by 15% per annum in the following two years. Required: (a) State the amounts that would be included in a net present value evaluation in relation to the following expenses. $ Costs of conversion Light and heat Year 1 Depreciation Year 1 Notional rent Year 1 Staff salaries Year 1 Staff relocation costs (6 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 14: I n v e s t me n t ap p rai s al (b) Using a discount rate of 10%, calculate the net present value of the incremental sales gained through redeveloping the outlet to the nearest $000. $ (c) 000 (2 marks) Which of the following are advantages of the Net Present Value method of investment appraisal compared with the internal rate of return method? Advantage compared with IRR? Yes No It is only possible to have a single NPV figure, but it is possible to have more than one IRR. It considers cash flows over the whole life of a project. The answer provides a clear decision rule. It requires a cost of capital to be estimated. (2 marks) (10 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) 79 lOMoARcPSD|27223832 80 15: M at e ri al a nd l a b o u r v a ri a n c es A C C A MA Chapter 15: Material and labour variances Objective test questions Standard costing systems 1 There are four types of cost standard: A basic standard A current standard An attainable standard An ideal standard Match each of these cost standards against the correct definition below. Definition Cost standard This standard assumes that current efficiency and cost levels will be maintained This standard assumes that nothing has changed since the standard was first set This standard assumes an optimum level of efficiency and cost and minimisation of waste This standard assumes that there will be some improvements in current efficiency and cost levels 2 Nigel is a baker. Each loaf of bread baked requires 750 grams of flour. During the baking process there is a 20% loss of flour due to spillage. The standard price of flour is $2 per 1,000 grams. The standard cost of the flour per loaf of bread produced, to the nearest cent, is: $1.50 $1.80 $1.88 $2 3 A business budgets for 12 labour hours to assemble its product. In addition, the business incorporates the cost of idle time into the standard cost of products. The idle time budgeted is 15% of time paid. The wage rate is $8 an hour. The standard labour cost of one unit of product to the nearest cent is: $81.60 $96 $110.4 $112.94 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 15: M a t e ri a l a nd l a b o u r v a ri a n c es 4 A business assembles three types of machine. The standard labour hours per machine and the number of machines made in the last period are shown below. Machine A Machine B Machine C Standard hours 12 15 20 Number produced 100 50 90 In the last period 4,000 actual hours were worked. Employees were paid $10 per standard labour hour produced. What were the wages paid for the last period? 5 $25,000 $40,000 $37,500 $112,800 Indicate whether the following statements are TRUE or FALSE. A standard cost is the planned unit cost of a product A standard hour is any hour during which the labour force is paid at its basic rate of pay 6 False Which of the following might management use in order to identify the standard quantities of materials needed to make a product? 7 True Past experience Detailed product specifications Discussions with experts in each department Financial accounts Jo is paid a guaranteed $1,000 dollars a month. In addition he receives a bonus per unit for each unit in excess of 100 that he makes in the month. If he produces in excess of 110 or 120 units, the bonus for each unit produced above those production levels increases. Last month Jo made 122 units. Bonus rates were as follows: Monthly output 100 to 110 units 111 to 120 units 121 to 130 units Bonus per unit $ 15 20 25 What was Jo paid last month? $ Downloaded by Hooria Noor (nhooria9@gmail.com) 81 lOMoARcPSD|27223832 82 15: M at e ri al a nd l a b o u r v a ri a n c es 8 Standard costing can be defined as: 9 A C C A MA A technique that reports variances by comparing actual costs to predetermined standards A technique that attributes overheads to products or services based on standard use of resources A technique that treats fixed costs as period costs and charges them in full against profit in the period in which they are incurred A technique that uses standard cost drivers to assign resources to activities and activities to cost objects Which of the following is not a type of standard that is used in standard costing? Current standard Ideal standard Attainable/expected standard Relevant standard Variance calculations Material variances Use the following information to answer the next three questions. A business operates a standard marginal costing system. The following budget is available: Budgeted production 1,000 units Direct materials 5 kg at $5 per kg $25 per unit Actual results were: Actual production 1,200 units Direct materials 5,100 kg $26,000 Budgeted and actual sales in the period were equal to the number of units produced. 10 What is the total direct material cost variance? 11 $1,000 adverse Nil $4,000 favourable $5,000 adverse What is the direct material price variance? $1,000 adverse $500 adverse $1,000 favourable $500 favourable Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 15: M a t e ri a l a nd l a b o u r v a ri a n c es 12 What is the direct material usage variance? 13 $4,500 adverse $500 adverse $4,500 favourable $500 favourable Last period a business used 500 kg of material in the production of 600 units of product P. This material cost $900. The standard cost card for product P shows that the standard direct material content is 0.8 kg at $1.40 per kg. The direct material price and usage variances are: 14 Material price Material usage $200 adverse $28 favourable $200 adverse $28 adverse $228 adverse $36 adverse $228 adverse $36 favourable A business purchased 4,000 litres of a liquid for $38,000. The material price variance was $2,000 favourable. What was the standard price per litre of the liquid? 15 $9 $9.50 $10 It is not possible to calculate the standard price from the information given A businesses budget shows that it expected to make 10,000 units of X using 12kg of direct material per unit at a budgeted cost of $2.90 per kg. 9,750 units were actually produced. The direct materials cost for these units was $350,000 and 11kg per unit were used. What is the total direct material variance? $10,700 adverse $2,000 adverse $28,275 favourable $10,700 favourable Use the following information to answer the next three questions. A product has a standard direct material cost of $20 per unit. The standard material cost is $10 per kg. Last month 500 units were produced and the direct materials cost $9,800. 1,050 kg of direct materials were used. All materials purchased in the period were used in the period. 16 What was the direct material price variance? favourable/adverse $ 17 What was the direct materials usage variance? $ favourable/adverse Downloaded by Hooria Noor (nhooria9@gmail.com) 83 lOMoARcPSD|27223832 84 15: M at e ri al a nd l a b o u r v a ri a n c es 18 What was the total material variance? favourable/adverse $ 19 A C C A MA 12,000 kg of material was used in making product X. The standard cost card shows the standard cost of this material to be $2 per kg. The material usage variance was $6,000 favourable. What was the standard allowed weight of the material for the period? 9,000 kg 12,000 kg 15,000 kg 18,000 kg Use the following information to answer the next three questions. Last month a business budgeted to produce 5,000 units of one of its products. The product standard usage of raw material is 6 kg per unit with a standard cost of $5 per kg. Actual production was 4,900 units using 29,500 kg of raw material at a cost of $146,000. 20 What is the total direct material cost variance? 21 What is the direct material price variance? 22 $1,000 adverse $1,000 favourable $1,500 favourable $1,500 adverse What is the direct material usage variance? 23 $1,000 adverse $1,000 favourable $4,000 adverse $4,000 favourable $500 adverse $500 favourable $2,500 adverse $2,500 favourable Last month a business produced 12,000 units of product X using 54,000 hours of direct labour costing $540,000. The standard cost card shows that the standard labour input for a unit of X is 4.25 hours at a rate of $10.20 an hour. What is the labour rate variance? $10,800 favourable $10,800 adverse $50,400 favourable $50,400 adverse Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 15: M a t e ri a l a nd l a b o u r v a ri a n c es 24 Last month a business reported an adverse direct labour efficiency variance of $3,000. Workers were actually paid $10 an hour which was the same as the standard labour cost per hour. 900 units were made and total wages were $39,000. How many standard hours were included in the production budget for each unit? hours 25 In the last period 15,000 labour hours were worked at a standard cost of $8.50 per hour. The labour efficiency variance was $4,250 favourable. How many standard hours were produced? 26 15,500 14,500 15,000 It is not possible to work this out without further information A business reports an adverse labour efficiency variance of $40,000. If 44,000 hours were worked producing 10,000 units and the standard wage rate was $10 per hour, how many standard hours were allowed per unit? 0.4 4 4.4 4.8 Use the following information to answer the next three questions. Last month production of product X was 20,000 units. 50,000 hours of direct labour were used at a cost of $400,000. The standard cost card shows that standard labour input for a unit of X is 2.75 hours at the rate of $7.50 an hour. 27 What is the total labour cost variance? 28 What is the labour rate variance? 29 $12,500 adverse $12,500 favourable $25,000 adverse $25,000 favourable $25,000 adverse $25,000 favourable $12,500 adverse $12,500 favourable What is the labour efficiency variance? $37,500 favourable $37,500 adverse $40,000 favourable $40,000 adverse Downloaded by Hooria Noor (nhooria9@gmail.com) 85 lOMoARcPSD|27223832 86 15: M at e ri al a nd l a b o u r v a ri a n c es A C C A MA Use the following information to answer the next three questions. A business budgeted to produce 12,000 units of product X. The standard cost card shows that each unit of X is expected to require 3 labour hours at $12 an hour. The actual results were Production Labour 35,200 hours 30 11,600 units $354,000 What is the labour efficiency variance? favourable/adverse $ 31 What is the labour rate variance? favourable/adverse $ 32 What is the total labour cost variance? favourable/adverse $ 33 The standard direct material cost per unit for a product is calculated as follows: 10 litres at $2.75 per litre Last month the actual price paid for 11,000 litres of material used was 5% above standard and the direct material usage variance was $2,200 favourable. No inventories are held. What was the actual production last month (in units)? 34 1,020 1,180 1,280 1,380 The standard direct material cost per unit for a product is calculated as follows: 10 litres at $2.75 per litre Last month the actual price paid for 11,000 litres of material used was 5% above standard and the direct material usage variance was $2,200 favourable. No inventories are held. What was the direct material price variance for last month? $1,512.50 fav $1,512.50 adv $1,592 fav $1,592 adv Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 15: M a t e ri a l a nd l a b o u r v a ri a n c es 35 C Ltd used 34,500kg of material at a total standard cost of $258,750. The material usage variance was $2,145 favourable. Calculate the standard allowed weight of material for the actual production achieved by C Ltd in March? 36 33,936 kg 34,214 kg 34,786 kg 35,072 kg A business has a budgeted labour cost per unit of $17.50. This month production details were as follows: Budget 30,000 units Actual 29,500 units The actual labour cost for the month was $554,250. What was the labour total variance as a percentage of the flexed budgeted figure? 7.4% adverse 7.4% favourable 6.9% adverse 6.9% favourable Causes of variances 37 Which of the following would explain a favourable materials usage variance? I 38 39 II III Industrial action which meant that there was lower production and therefore less material used than budgeted Use of a higher grade material which lead to less wastage New machinery which provides better efficiency in materials usage I only I and III I, II and III II and III Which of the following would explain an adverse direct labour efficiency variance? I II III Poor supervision of the workforce Improved working methods were implemented during the period A lower grade of material was used which takes longer to process I only I and III I, II and III II and III Which ONE of the following factors could explain an adverse material price variance? A sudden shortage of materials worldwide led to suppliers increasing their prices. The material usage variance was adverse. The closing inventory of raw materials is higher than the opening inventory. Problems with machinery inside the factory meant that material purchases were greater than planned. Downloaded by Hooria Noor (nhooria9@gmail.com) 87 lOMoARcPSD|27223832 88 15: M at e ri al a nd l a b o u r v a ri a n c es 40 Which one of the following would help explain a favourable materials price variance? Select one: A reduction in quality control checking standards Using a higher quality of materials than specified in the standard Achieving a lower output volume than budgeted A discount offered by a materials supplier Downloaded by Hooria Noor (nhooria9@gmail.com) A C C A MA lOMoARcPSD|27223832 A C C A MA 16: O t h e r v a ri an c e s Chapter 16: Other variances Objective test questions Variance calculations Variable overhead variances Use the following information to answer the next three questions. A business has budgeted to produce 600 units of a product. The standard cost card shows that 3,000 labour hour were budgeted and that the total variable production overhead cost was expected to be $12,000. The actual results for the period were: Production Labour Variable overhead 610 units 3,100 hours $12,300 Use the following information to answer the next three questions. The standard cost card for a product shows the following: Direct Labour Variable production overhead 6 hours at $10 per hour $ per unit 60 6 Last period the number of direct labour hours worked to produce 1,000 units was 6,200. The variable production overhead cost incurred was $6,100. 1 The total variable overhead expenditure variance to the nearest $ is: Adverse Favourable $................... 2 The variable overhead expenditure variance to the nearest $ is: Adverse Favourable $................... 3 The variable overhead efficiency variance to the nearest $ is: Adverse Favourable $................... Use the following information to answer the next three questions. The standard variable production cost of a product is 2 hours at $5 = $10 per unit Last month 2,000 units were made and the workforce worked 3,600 hours. The actual variable overhead cost was $15,000. Downloaded by Hooria Noor (nhooria9@gmail.com) 89 lOMoARcPSD|27223832 90 16: O t h e r v a ri an c e s 4 A C C A MA What was the total variable overhead variance? Adverse Favourable $................... 5 What was the variable overhead expenditure variance? Adverse Favourable $................... 6 What was the variable overhead efficiency variance? Adverse Favourable $................... 7 Last period 500 labour hours were worked and the total variable overhead cost was $5,600. The variable overhead expenditure variance was $400 favourable. What was the standard variable overhead cost per labour hour? $11.20 $12 $10.40 There is insufficient information available to calculate this Fixed overhead variances Use the following information to answer the next five questions. Harvey Limited manufactures baskets. In 20X8 the planned production was 200,000 units. Fixed overheads were absorbed on a labour hour basis at $4 per hour for 3 labour hours. The actual production of baskets in 20X8 was 220,000 units. The baskets took 645,000 labour hours to make. Total fixed overheads were $2,375,000. 8 What was the total fixed overhead variance? $................... 9 Favourable What was the fixed overhead expenditure variance? $................... 10 Adverse Adverse Favourable What was the fixed overhead volume variance? $................... Adverse Favourable Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 16: O t h e r v a ri an c e s 11 What was the fixed overhead capacity variance? $................... 12 Adverse Favourable What was the fixed overhead efficiency variance? $................... Adverse Favourable Use the following information to answer the next five questions. Adam Limited manufactures containers. In 20X9 the planned production was 500,000 containers. Budgeted fixed overheads were $7,000,000. Fixed overheads are absorbed in each container on a material usage basis, the standard usage for each unit being 2 kg. The actual production of containers in 20X8 was 520,000 units. 1,055,000 kg of material were used in making the baskets. Total fixed overheads were $6,925,000. 13 What was the total fixed overhead variance? $................... 14 Adverse Favourable Adverse Favourable What was the fixed overhead capacity variance? $................... 17 What was the fixed overhead volume variance? $................... 16 Favourable What was the fixed overhead expenditure variance? $................... 15 Adverse Adverse Favourable What was the fixed overhead efficiency variance? $................... Adverse Favourable Downloaded by Hooria Noor (nhooria9@gmail.com) 91 lOMoARcPSD|27223832 92 16: O t h e r v a ri an c e s A C C A MA Sales variances Use the following information to answer the next two questions. The standard cost of producing one unit of a product is as follows: Direct material Direct Labour Variable overhead cost $ 3.60 0.60 0.30 The standard selling price is $9 a unit. Sales of 4,600 units are budgeted each period. In the last period 4,620 units were sold for $41,500. 18 What is the sales price variance? 19 $80 adverse $80 favourable $100 adverse $100 favourable What is the sales volume variance? $90 adverse $90 favourable $180 favourable $180 adverse Use the following information to answer the next two questions. Last period 20,100 units of X were sold. Budgeted sales revenue Standard selling price per unit Standard contribution per unit Actual sales revenue 20 What was the sales price variance? 21 $ 500,000 25 10 512,500 $10,000 adverse $10,000 favourable $12,500 adverse $12,500 favourable What was the sales volume variance? $1,000 adverse $1,000 favourable $10,000 adverse $10,000 favourable Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 16: O t h e r v a ri an c e s 22 The following information is available regarding product X: Budgeted sales Actual sales Actual sales revenue Sales price variance 10,000 units 9,800 units $96,000 $2,000 (A) What is the standard selling price per unit? $ per unit A business reported the following. Use these results to answer the next two questions. Output and sales (units) Selling price per unit Variable cost per unit 23 $36,000 adverse $36,000 favourable $64,000 adverse $64,000 favourable What was the sales volume variance? 25 Actual 18,000 $52 $21 What was the sales price variance? 24 Budget 20,000 $50 $20 $42,000 adverse $42,000 favourable $60,000 adverse $60,000 favourable The standard cost of producing one unit of a product is as follows: Direct material Direct labour Variable overhead cost Absorbed fixed overhead $ 5.20 2.80 1.20 1.70 The standard selling price is $16 per unit. Sales of 9,000 units are budgeted each period. In the last period 9,200 units were sold for $145,000. Using absorption costing principles, what is the favourable sales volume variance? $ Downloaded by Hooria Noor (nhooria9@gmail.com) 93 lOMoARcPSD|27223832 94 16: O t h e r v a ri an c e s A C C A MA Causes of variances 26 In the last period a machine breakdown meant fewer units than budgeted were produced. This resulted in an adverse sales volume contribution variance. Which of the following might be an inter-related variance? 27 An adverse labour efficiency variance An adverse variable overhead efficiency variance A favourable material usage variance A favourable labour rate variance An adverse material price variance resulted from the use of a more expensive material than standard. Indicate which of the following might be related: A favourable variable overhead efficiency variance A favourable material usage variance A favourable labour rate variance A favourable sales volume variance Multi task question 1 CUDDLYDUD The standard cost card for the Cuddlydud is as follows: Standard cost card Selling price Direct material 6 kg @ $6 per kg Direct labour 2 hrs @ $24 per hour Variable overheads 2 hrs @$4 per hour Fixed overheads absorbed 2 hrs @ $7 per hour $ 155 36 48 8 14 15,000 units of the Cuddlydud were budgeted to be produced and sold during July, but 15,100 were actually produced and sold. Actual labour hours were 29,700. Actual fixed overheads were $206,400. Required: (a) Calculate the sales volume variance using marginal costing. favourable/adverse (b) Calculate the fixed overhead expenditure variance using marginal costing. favourable/adverse (c) (1 mark) Calculate the fixed overhead expenditure variance using absorption costing. favourable/adverse (d) (2 marks) (1 mark) Calculate the fixed overhead capacity variance using absorption costing. favourable/adverse Downloaded by Hooria Noor (nhooria9@gmail.com) (2 marks) lOMoARcPSD|27223832 A C C A MA 16: O t h e r v a ri an c e s (e) Calculate the fixed overhead efficiency variance using absorption costing. favourable/adverse (2 marks) There was no opening inventory of the Cuddlydud in August, but in that month 300 units more were produced than sold. (f) Calculate the difference in the level of profit for August between the profit calculated using marginal costing and the profit calculated using absorption costing. (2 marks) (10 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) 95 lOMoARcPSD|27223832 96 17: V ari an c e re v i e w and c o n t ro l A C C A MA Chapter 17: Variance review and control Objective test questions Reconciliation of budgeted and actual profit 1 The budgeted profit for a business was $45,000 but the following variances arose: Material price variance Material usage variance Labour rate variance Labour efficiency variance Variable overhead expenditure variance Variable overhead efficiency variance Fixed overhead expenditure variance Fixed overhead capacity variance Fixed overhead efficiency variance Sales price variance Sales volume variance The actual profit was: $ Cost control and reduction 2 Which TWO of the following statements in relation to value analysis are true? 3 It assumes that the product design is rigid. It takes into account a required standard of quality. It seeks the lowest cost method of achieving a desired end. The market price that the business can charge is assumed to be fixed. Which of the following is NOT considered an element of value? Select one: Use value Marketing value Exchange value Cost value Downloaded by Hooria Noor (nhooria9@gmail.com) $ 1,200(F) 3,000(F) 2,900(F) 800(A) 1,900(A) 2,400(A) 1,000(A) 700(F) 1,900(A) 3,600(F) 4,100(A) lOMoARcPSD|27223832 A C C A MA 17: V a ri an c e re v i e w and c o n t ro l Multi task questions 1 HENRY Henry uses standard costing to control its costs and revenues. A standard cost card for its one product is given below, along with a standard cost operating statement for the last quarter. Standard cost card $ 150 36 56 16 42 Selling price Direct material 3kg @ $12 per kg Direct labour 4 hrs @ $14 per hour Variable overhead 4 hrs @ $4 per hour Contribution Standard cost operating statement $ 840,000 21,000 861,000 (4,100) Budgeted contribution Sales volume variance Flexed contribution Sales price variance Cost variances Material price Material usage Labour rate Labour efficiency Variable overhead expenditure Variable overhead efficiency Total cost variances Favourable $ 2,476 Adverse $ 4,800 24,360 11,200 12,300 3,200 29,176 29,160 16 856,916 Actual contribution Budgeted fixed overhead Fixed overhead expenditure variance 480,000 (5,600) (474,400) 382,516 Actual profit Required: Fill in the gaps from the choices listed below each gap. (a) Henry uses standard _______ costing. (b) Absorption Marginal (1 mark) In the last month units sold were _____ budgeted. 140 more than budgeted 140 less than budgeted 500 more than budgeted 500 less than budgeted Downloaded by Hooria Noor (nhooria9@gmail.com) (2 marks) 97 lOMoARcPSD|27223832 98 17: V ari an c e re v i e w and c o n t ro l (c) The sales price variance indicates that average sales price was _____ than expected. (d) $2,996,000 $3,000,000 $3,070,900 $3,075,000 (2 marks) Material usage and Labour efficiency Material usage and Variable overhead efficiency Labour efficiency and Variable overhead efficiency (1 mark) The decision to pay labour a bonus for greater productivity resulted in labour taking ____ hours less than allowed for in the flexed budget. (g) (1 mark) The reasons for the _______ variances were identical. (f) Higher Lower Actual sales revenue was _____. (e) A C C A MA 200 800 1,200 2,800 (2 marks) The fixed overhead expenditure variance was _____ . Favourable Adverse (1 mark) (10 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 17: V a ri an c e re v i e w and c o n t ro l 2 EDTED Edted uses a standard costing system to control its costs and revenues. A standard cost card for its product is given below, along with a standard cost operating statement for the last quarter. Standard cost card $ 180 36 48 15 24 57 Selling price Direct material 4 kg @ $9 per kg Direct labour 3 hrs @ $16 per hour Variable overhead 3 hrs @ $5 per hour Fixed overheads 3 hrs @ $8 per hour Profit Standard cost operating statement $ 798,000 34,200 832,200 73,000 Budgeted profit Sales volume variance Flexed budgeted profit Sales price variance Cost variances Material price Material usage Labour rate Labour efficiency Variable overhead expenditure Variable overhead efficiency Fixed overhead expenditure Fixed overhead capacity Fixed overhead efficiency Total cost variances Favourable $ 11,826 Adverse $ 13,770 12,921 11,680 5,120 3,650 12,140 8,560 5,840 54,477 31,030 23,447 928,647 Actual profit There was no opening and closing inventory of raw materials. There was no opening inventory of finished goods. Edted produced 14,600 units during the year and has not yet carried out an inventory count of closing finished goods inventory. Required: Fill in the gaps from the choices listed below each gap. (a) Edted uses standard _______ costing. (b) (1 mark) In the last month units sold were _____ budgeted. (c) Absorption Marginal 190 more than budgeted 190 less than budgeted 600 more than budgeted 600 less than budgeted (2 marks) Actual sales revenue was _____ per unit than budgeted. More Less (1 mark) Downloaded by Hooria Noor (nhooria9@gmail.com) 99 lOMoARcPSD|27223832 100 17: V ari an c e re v i e w and c o n t ro l (d) The actual quantity of materials used was ____ kg. (e) 54,957 56,870 59,930 61,843 (2 marks) Labour was paid ____ per hour than was budgeted for actual hours worked. (f) A C C A MA $0.300 less $0.300 more $0.313 less $0.313 more (2 marks) The actual level of fixed overhead expenditure was _______. $323,860 $333,740 $338,260 $348,140 (2 marks) (10 marks) 3 WAKEUUP Wakeuup processes materials for healthy breakfast cereals. The standard costs for each tonne of processed material are as follows: 1.2 tonnes of raw, unprocessed, materials are required at $30 per tonne. It takes 2 labour hours to produce 1 tonne of processed material, with labour being paid at $22.50 per hour. 2 hours of variable overhead at a cost of $10 per hour are budgeted for the product. The standard selling price is $160 per tonne. The standard contribution per tonne is $54 per tonne. Fixed costs in July were budgeted at $160,000 and budgeted production and sales were 25,400 units. Actual production and sales in July were 24,900 units. Sales revenue achieved was $3,996,450. Cost details were as follows: 30,200 tonnes of raw materials were paid for, costing $901,470. 51,050 labour hours were paid for, costing $1,153,730. Variable production overhead costs were $494,000. Fixed overhead costs were $164,000. Required: (a) Complete the standard cost operating statement with the cost variances and calculate the actual profit. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 17: V a ri an c e re v i e w and c o n t ro l Standard cost operating statement $ Budgeted contribution 1,371,600 Sales volume variance (27,000) Flexed contribution 1,344,600 Sales price variance 12,450 Favourable Cost variances $ Adverse $ Material price Material usage Labour rate Labour efficiency Variable overhead expenditure Variable overhead efficiency Total cost variances Budgeted fixed overhead 160,000 Fixed overhead expenditure variance Actual profit (8 marks) (b) Which TWO of the following could explain an adverse labour efficiency variance? Idle time is less than the amount allowed in the budget Introduction of new, better quality, equipment Stricter quality control procedures resulting in a lower volume of good output Under-estimation when budgeting of the time taken to produce individual units (2 marks) (10 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) 101 lOMoARcPSD|27223832 102 17: V ari an c e re v i e w and c o n t ro l A C C A MA 4 HARVEYHEDGE The standard cost card for Harveyhedge’s main product, the Sweelin, is shown below. The expected sales and production for June were 1,750 units. Standard cost card $ 200 42 44 18 30 66 Selling price Direct material 6 kg @ $7 per kg Direct labour 2 hrs @ $22 per hour Variable overhead 2 hrs @ $9 per hour Fixed overheads 2 hrs @ $15 per hour Profit The actual data for June for this product is shown below but is incomplete. $ 9,900 F 1,200 A 5,250 A 2,730 F 2,640 F 3,520 A 2,340 F 1,350 A 4,060 1,950 Sales volume variance Sales price variance Material usage variance Material price variance Labour rate variance Labour efficiency variance Total variable overhead variance Total fixed overhead variance Number of labour hours worked Quantity produced Required: Calculate the following figures for Harveyhedge in June. (a) Actual sales revenue $ (b) (2 marks) Actual material usage (in kg) kg (c) Actual labour costs incurred $ (d) (1 mark) Variable overheads incurred $ (e) (1.5 marks) (1.5 marks) Actual fixed overheads incurred $ (2 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 17: V a ri an c e re v i e w and c o n t ro l The board of Harveyhedge is worried about the levels of labour efficiency and would like further information on how this can be measured. (f) Which two of the following measures would provide information about the efficiency of Harveyhedge’s workforce? Expected output for a worker week compared with the actual output Actual output for a worker week compared with the actual labour time Expected labour time for actual output produced compared with actual labour time Expected quality of output produced compared with actual quality of output produced (2 marks) (10 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) 103 lOMoARcPSD|27223832 104 18: Fi n an c i al p e rf o rman c e me as u res A C C A MA Chapter 18: Financial performance measures Objective test questions Performance measurement overview 1 Which of the following elements would be included in a company’s mission statement? 2 Strategy Profitability Liquidity Values Reduction in the number of customer complaints by 20% in a year is an example of what kind of objective? Fundamental Strategic Tactical Operational Financial measures Use the following information to answer the next thirteen questions. Statement of financial position Non-current assets Current assets Inventories Receivables Cash $000 $000 20,000 6,000 3,000 1,000 10,000 30,000 Equity Non-current liabilities Loan Current liabilities Trade payables Taxation 20,000 8,000 1,500 500 2,000 30,000 Statement of profit or loss Revenue (all credit sales) Cost of sales Gross profit Other operating expenses Profit before interest and tax Finance cost Profit before tax Downloaded by Hooria Noor (nhooria9@gmail.com) $000 25,000 (16,000) 9,000 (2,000) 7,000 (500) 6,500 lOMoARcPSD|27223832 A C C A MA 18: Fi n an c i al p e rf o rman c e me as u res 3 What is the return on capital employed? % 4 What is the gross profit margin? % 5 What is the net profit margin? % 6 What is the asset turnover? 7 What is the current ratio? 8 What is the quick ratio? 9 What is the inventory turnover? 10 What are inventory days? days 11 What is the receivables collection period? days 12 What is the payables payment period? days 13 What is the debt to equity ratio? % Downloaded by Hooria Noor (nhooria9@gmail.com) 105 lOMoARcPSD|27223832 106 18: Fi n an c i al p e rf o rman c e me as u res 14 A C C A MA What is the gearing ratio? % 15 What is the interest cover? Use the following information to answer the next thirteen questions. Statement of financial position Non-current assets Current assets Inventories Receivables Cash $000 $000 50,000 3,000 6,000 3,000 12,000 62,000 Equity Non-current liabilities Loan Current liabilities Trade payables Taxation 40,000 16,000 5,000 1,000 6,000 62,000 Statement of profit or loss $000 40,000 (25,000) 15,000 (3,000) 12,000 (2,000) 10,000 Revenue (all credit sales) Cost of sales Gross profit Other operating expenses Profit before interest and tax Finance cost Profit before tax 16 What is the return on capital employed? % 17 What is the gross profit margin? % 18 What is the net profit margin? % Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 18: Fi n an c i al p e rf o rman c e me as u res 19 What is the asset turnover? 20 What is the current ratio? 21 What is the quick ratio? 22 What is the inventory turnover? 23 What are inventory days? days 24 What is the receivables collection period? days 25 What is the payables payment period? days 26 What is the debt to equity ratio? % 27 What is the gearing ratio? % 28 What is the interest cover? Downloaded by Hooria Noor (nhooria9@gmail.com) 107 lOMoARcPSD|27223832 108 18: Fi n an c i al p e rf o rman c e me as u res 29 A C C A MA The rail operation serving the North-East of Earland is government-owned. The service operates in a region with few large towns and in quite rural, sometimes difficult terrain, with a poor road infrastructure. The prices charged by this service are capped by the government. The rail company that serves the short-distance commuter routes into Earland’s capital city is privatelyowned and the fares it charges to commuters are not regulated by the government. Which of the following factors should not be allowed for when comparing the Return On Capital Employed of the two rail providers to assess the efficiency of their management? 30 The prices charged The social need for rail transport The potential demand for rail services The remuneration of senior management A company has a capital employed of $600,000. It has a cost of capital of 12% per year and a return on investment of 15%. What is the company’s residual income? $ Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 18: Fi n an c i al p e rf o rman c e me as u res Multi task questions 1 OLDTED Oldted has just published its financial statements for the year ended 31 August. The figures for this year are shown with comparatives for last year. Statement of financial position Non-current assets Current assets Inventories Receivables Cash Equity Non-current liabilities Loan Current liabilities Trade payables Taxation Current year $000 $000 29,100 11,410 1,260 320 9,580 1,100 450 12,990 42,090 23,500 11,130 39,910 21,320 9,860 10,810 8,130 600 Statement of profit or loss Revenue Cost of sales Gross profit Other operating expenses Profit before interest and tax Finance cost Profit before tax Taxation Profit after tax Previous year $000 $000 28,780 7,240 540 8,730 42,090 7,780 39,910 $000 32,200 (25,410) 6,790 (3,200) 3,590 (810) 2,780 (600) 2,180 $000 29,220 (22,860) 6,360 (3,150) 3,210 (690) 2,520 (540) 1,980 Required: (a) Calculate the % change in gross profit, to the nearest 0.1%. % (b) Calculate the return on capital employed for this year, to the nearest 0.1%. % (c) (1 mark) Calculate the return on capital employed for last year, to the nearest 0.1%. % (d) (1 mark) (1 mark) Calculate the asset turnover for this year to 2 decimal places. (1 mark) (e) Calculate the asset turnover for last year to 2 decimal places. (1 mark) Downloaded by Hooria Noor (nhooria9@gmail.com) 109 lOMoARcPSD|27223832 110 18: Fi n an c i al p e rf o rman c e me as u res (f) A C C A MA Calculate the inventory turnover for this year. (1 mark) (g) Calculate in days the change in the inventory period between this year and last year. days (2 marks) The directors of Oldted are concerned about the level of inventory holding and ordering costs. (h) Which ONE of the following would be a way of minimising the total of these costs? More frequent inventory counts Use of the Economic Order Quantity model Making more use of supplier discounts Increasing buffer inventory levels (2 marks) (10 marks) 2 LOXWOOD FOODS Loxwood Foods is a food manufacturing and distribution based on a model of autonomous profit making divisions. In the year that has just ended Loxwood’s Ready Meals division made an operating profit of $1.5m. Its non-current assets were $6.5m and it had net current assets of $1m. Up to now, the Ready Meals division has only offered a limited selection of vegetarian meals. As however these have been the division’s biggest revenue earner over the last two years, Loxwood’s board wants the division to make a significant investment to expand the range very significantly. To do this, the division will need to invest an additional $1.5m in non-current assets and an additional $0.8m in net current assets. The expanded range is forecast to make an additional $0.45m profit for the Ready Meals division. Loxwood uses a cost of capital of 9% to appraise the performance of its divisions. Required: (a) Calculate the return on investment for the Ready Meals division for last year, to the nearest 0.1%. % (b) Calculate the forecast return on investment for the Ready Meals division if the expansion takes place, to the nearest 0.1%. % (c) (1.5 marks) Calculate the residual income for the Ready Meals division for last year. $ (d) (1.5 marks) m (1.5 marks) Calculate the forecast residual income for the Ready Meals division if the expansion takes place. $ m Downloaded by Hooria Noor (nhooria9@gmail.com) (1.5 marks) lOMoARcPSD|27223832 A C C A MA 18: Fi n an c i al p e rf o rman c e me as u res (e) Which two of the following would be disadvantages of using the Residual Income (RI) approach to appraise the performance of the Ready Meals division? RI could increase every year because assets are getting older, even though profits may remain static or fall. RI cannot easily be used to compare the performance of divisions of different sizes. RI is inflexible, since a single cost of capital has to be used to compare every division. RI does not provide a clear indicator that prompts managers to undertake profitable investments. (2 marks) The Managing Director of the Ready Meals division has commented that she believes that Loxwood will have to offer the new range at the same prices that competitors are offering similar products. Given that she wishes to maintain the same profit margin on the new meals as on the current vegetarian meals, Loxwood will have to find ways to limit the costs of these products. (f) This approach to costing is known as: Activity-based costing Process costing Target costing Job costing (2 marks) (10 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) 111 lOMoARcPSD|27223832 112 19: N o n - fi n an c i al p e rf o rman c e me as u re s a n d pe rf o rman c e re p o rt i n g A C C A MA Chapter 19: Non-financial performance measures and performance reporting Objective test questions Non-financial measures 1 Which of the following would be a suitable measure of resource utilisation in a training business? I II III Number of teaching days per tutor/trainer Average number of empty classrooms per day Material cost per student I only III only I and II only II and III only Balanced scorecard 2 Match the following performance indicators with the perspective of the balanced scorecard that they provide. A B C D Market share Staff absenteeism rates Number of deliveries made within a week of order Time from order to despatch from factory I II III IV Financial Customer Innovation and Learning Internal business process Activity, efficiency and capacity ratios Use the following information to answer the next three questions. Oldted Limited budgeted to produce 100,000 units in September with a standard time per unit of 3 hours. Oldted actually produced 105,000 units in September and its actual hours of production were 285,000 hours. 3 What was the activity ratio in % of Oldted, to one decimal place? % 4 What was the efficiency ratio in % of Oldted to one decimal place? % Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 19: N o n - fi n an c i al p e rf o rman c e me as u re s a n d pe rf o rman c e re p o rt i n g 5 What was the capacity ratio in % of Oldted to one decimal place? % Process and job performance measurement 6 Which TWO of the following methods can be used to assess resource utilisation? Idle time Expenditure on resources Productivity Customer satisfaction Non-profit seeking and public sector organisations 7 After a number of accidents at its factory, LP’s board compelled all staff working at the factory to attend compulsory health and safety training. The directors were pleased to see that the number of accidents in the factory fell significantly after staff had undertaken training. The reduction in the number of accidents is a measure of the training course’s: Economy Efficiency Effectiveness Equality Manufacturing and service businesses 8 Which of the following performance measures would be helpful for a service industry company? Net profit margin Number of returning customers Staff turnover Comparison of actual performance with standard production times Benchmarking 9 A manufacturing business compares the operational efficiency of all its other factories against its best performing factory. This is an example of what type of benchmarking? Strategic Competitive Internal Functional Downloaded by Hooria Noor (nhooria9@gmail.com) 113 lOMoARcPSD|27223832 114 19: N o n - fi n an c i al p e rf o rman c e me as u re s a n d pe rf o rman c e re p o rt i n g A C C A MA Performance reports 10 Which of the following performance measures is most likely to be reported because of government regulations? CO2 emissions Growth in customer numbers Cash flow Staff turnover Multi task questions 1 FUZZY LIMITED The Finance Director of Fuzzy Limited is concerned about the performance of its Western division. He has the following information available for last year. $000 18,000 5,500 80,000 46 44 45 11 50,000 hours 49,500 hours 49,700 hours Revenue Operating profit Capital employed Number of employees at start of year Number of employees at end of year Average number of employees Number of staff leaving during the period Budgeted employee hours Actual hours worked Standard hours produced The division’s imputed charge for the purpose of calculating performance is 10%. Required: (a) Calculate the return on investment in % to 2 decimal places. % (b) Calculate the residual income. $ (c) (1 mark) Calculate the labour turnover ratio in % to 2 decimal places. % (d) (1 mark) Calculate the labour efficiency ratio in % to 2 decimal places. % (e) (1 mark) (1 mark) Calculate the labour capacity ratio in % to 2 decimal places. % Downloaded by Hooria Noor (nhooria9@gmail.com) (1 mark) lOMoARcPSD|27223832 A C C A MA 19: N o n - fi n an c i al p e rf o rman c e me as u re s a n d pe rf o rman c e re p o rt i n g (f) Calculate the labour activity ratio in % to 2 decimal places. % (g) (1 mark) State which of the following are advantages of the Return on Investment measure of divisional performance. Yes No Divisional managers have to consider the costs of financing their divisions. Divisional managers avoid dysfunctional decision-making. It is directly related to net present value. It means that managers will select projects with positive net present values. It relates size of income to size of investment. It is an absolute measure of performance. It helps in comparing performance of managers who control divisions of different sizes. It is easily understood by managers. (2 marks) (h) Which TWO of the following reasons could explain adverse results for measurement of labour efficiency? The rate of staff turnover was higher than budgeted. Errors were made when allocating time to jobs during planning. Idle time that was built into the budget was incurred at the expected level. There was an increase in wage rates. (2 marks) (10 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) 115 lOMoARcPSD|27223832 116 19: N o n - fi n an c i al p e rf o rman c e me as u re s a n d pe rf o rman c e re p o rt i n g A C C A MA 2 BROADBRIDGE CLINICS LTD Broadbridge Clinics Ltd is a private healthcare provider, offering rest and recuperation to patients recovering from serious operations. Its clinics are open 365 days a year. The following data was included in the company’s annual report last year. Statement of profit or loss $000 3,940 1,356 (340) 1,016 Revenue Operating profit Taxation Profit after tax Statement of financial position summary $000 8,765 8,345 420 Assets Equity Current liabilities Staff average numbers (full-time equivalents) Doctors Nurses Administration staff Other staff Other statistics Number of patients Average length of stay (nights) Average number of beds 12 38 7 15 1,250 20 90 Required: Calculate the following ratios and other statistics for Broadbridge Clinics. (a) (b) (c) Return on capital employed to the nearest %. % (1 mark) % (1 mark) Net profit percentage to the nearest %. Operating profit per patient night to the nearest $. $ (d) (2 marks) Percentage occupation of beds to the nearest %. % (e) Revenue per member of the medical staff to the nearest $000. $ (f) (2 marks) (1 mark) Operating profit per employee to the nearest $000. $ (1 mark) Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 19: N o n - fi n an c i al p e rf o rman c e me as u re s a n d pe rf o rman c e re p o rt i n g The Managing Director of the clinics has been concerned by complaints of the lack of flexibility in the services provided to patients by the clinics. (g) Which TWO of the following are indications of the flexibility of service delivery by the clinics? Speed of delivery of care to patients Number of available beds Staff turnover Care plans tailored to individual patients (2 marks) (10 marks) 3 SYDNEY DARWIN LIMITED The directors of Sydney Darwin Limited are worried about the company’s annual financial situation. Sydney Darwin’s bank has expressed concern about the length of time that it has maintained an overdraft and has asked Sydney Darwin’s directors to reduce the overdraft significantly over the next six months. The bank is also concerned about Sydney Darwin’s ability to pay its finance costs and repay its bank loan. Sydney Darwin has just published its accounts for the most recent accounting year. Statement of financial position Non-current assets Current assets Inventories Receivables $000 $000 26,100 3,410 2,340 5,750 31,850 18,800 Equity Non-current liabilities Bank loan Current liabilities Bank overdraft Trade payables Taxation 8,100 950 3,900 100 4,950 31,850 Statement of profit or loss Revenue Cost of sales Gross profit Other operating expenses Profit before interest and tax Finance cost Profit before tax Taxation Profit after tax $000 38,200 (31,450) 6,750 (5,550) 1,200 (800) 400 (100) 300 Required: Calculate the following ratios for Sydney Darwin Limited. (a) Interest cover (1 mark) Downloaded by Hooria Noor (nhooria9@gmail.com) 117 lOMoARcPSD|27223832 118 19: N o n - fi n an c i al p e rf o rman c e me as u re s a n d pe rf o rman c e re p o rt i n g (b) A C C A MA Gearing, using total capital for comparison, to the nearest %. % (c) (1 mark) Current ratio to 2 decimal places. (1 mark) (d) Quick ratio to 2 decimal places. (1 mark) Sydney Darwin’s directors wish to understand what these calculations mean. (e) (f) Which ratio gives the best indication of Sydney Darwin’s ability to pay its finance costs? Interest cover Gearing Current ratio Quick ratio (2 marks) Which ratio gives the best indication of Sydney Darwin’s ability to raise money quickly to reduce its overdraft? Interest cover Gearing Current ratio Quick ratio (2 marks) The Managing Director of Sydney Darwin Limited believes that the company’s management needs to carry out a fundamental review of all the company’s operations, in order to find effective ways of reducing costs. He believes that the company needs to have a completely fresh look at the procedures it carries out, without being influenced by what it currently does. (g) This approach to cost management is known as: Total quality management Activity-based costing Target costing Business process re-engineering (2 marks) (10 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 1: M an ag e me n t ac c o u n ti n g a n d i n fo rmat i o n ANSWERS TO CHAPTER QUESTIONS Chapter 1: Management accounting and information Objective test questions Accounting for management 1 I Only There is no legal requirement to produce management accounts and they do not need to be in a prescribed format. 2 False Cost accounting is concerned with costing of production. Management accounting is concerned with summarising and budgeting the financial accounts. Planning, decision-making and control 3 I and II and III Management accounts are both a historical record and a future planning tool. Management accounts may be provided in monetary and non- monetary format. Data and information 4 % of first time students who passed final exams Increase in % of students passing first time since last sitting Data Information Data is the raw unprocessed figures that have been collected about an activity or procedure. Information is processed data that is now in a form that makes it valuable to the user 5 It is usually based on what has happened in the past It does not take account of external factors effecting the business For decision making, it is useful to have information on what might happen in the future and this may depend on what is likely to happen in the external environment. Management accounts do not provide this information. This is where the judgement of senior managers is important 6 A local bus company A local bus company is likely to be looking at a much more limited range of information than the others to assess likely demand for its services. Downloaded by Hooria Noor (nhooria9@gmail.com) 119 lOMoARcPSD|27223832 120 1: M an ag e me n t ac c o u n ti n g a n d i n fo rmat i o n A C C A MA 7 8 Internal External Lists of potential customers Current exchange rate Weekly sales figures Inflation rate The information may not be tailored for the exact purpose for which it is required There is so much information that there is a danger of information overload The source of the information may not be reliable There is as much mis-information as there is information on the internet. So although it is cheap and easy to acquire, great care is needed. 9 I, II and III Sampling 10 Systematic sampling The advantage of systematic sampling is that it is cheap and easy to use 11 The population is divided into groups and then all units within randomly selected groups are taken. Cluster sampling is a non-random sampling method that divides the population into clusters. Clusters are selected randomly, and then all units within selected clusters are included in the sample. No units from non-selected clusters are included. 12 Stratified Random Multistage Systematic A number of UK universities are selected and then all girls in the selected university are selected 10 children are randomly chosen from each year group in a School Evert 100th person to enter a supermarket is selected on a given day Presenting information 13 Terms of reference Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 1: M an ag e me n t ac c o u n ti n g a n d i n fo rmat i o n 14 News 24 15 % (23/94) × 100% 49 16 106 – 34 – 23 = 49 17 79 % 36 % (200 – 42 /200) × 100% 18 (13/36) × 100% 19 News Men % 24.5 43.6 13.8 18.1 100.0 Post News Chronicle Press 20 20X0 21 50 % 3 years (1 + 3) / 8 × 100% 22 23 20X0 24 Fixed cost Downloaded by Hooria Noor (nhooria9@gmail.com) Women % 22.6 32.1 21.7 23.6 100.0 Difference % 1.9 11.5 7.9 5.5 121 lOMoARcPSD|27223832 122 1: M an ag e me n t ac c o u n ti n g a n d i n fo rmat i o n 25 Stir 26 Gently Gently 27 Yes 28 Stir 29 No 30 Multiple bar chart Downloaded by Hooria Noor (nhooria9@gmail.com) A C C A MA lOMoARcPSD|27223832 A C C A MA 2: St at i s t i c al t e c h n i qu e s 123 Chapter 2: Statistical techniques Objective test questions Statistical techniques 1 129.5 Prices in 20X4 = 110 × (400/100) = $440 Prices in 20X6 = ($440 × 1.15) + S12 = $518 Index in 20X6 = $518 × (100/400) = 129.5 2 678,500 $ y = 122,000 + 5.3x therefore y = 122,000 + 5.3(105,000) = 678,500 3 0.957 r = (6 × 1,617,496) – (231 × 41,551) / √ [ (6 × 9,405) – (231 x 231)] [(6 × 288,423,181) – (41,551 × 41,551)] = 106,695 / √ (3,069 × 4,053,485) = 106,695/111,535 = 0.957 4 Year Quarter 1 1 Sales $ 60,000 2 144,000 Moving average $ Centred moving average $ Working 162,000 (160,500 + 163,500) / 2 168,000 (163,500 + 172,500) / 2 160,500 3 198,000 163,500 4 240,000 1 72,000 2 180,000 172,500 2 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 124 2: St at i s t i c al t e c h n i qu e s 5 A C C A MA 3,900 units Q1 3,180 +180 3,000 Actual units sold Seasonal variation Trend = Actual – Seasonal 97,750 6 Q2 3,530 +230 3,300 Q3 3,140 -460 3,600 units y = 10,000 + 4,200x Under additive model, actual sales = TxS T = 10,000 +4200(25) = 115,000 T x S = 115,000 × 85% = 97,750 units 7 The results become less reliable for predictions that are within the range of existing observations. 3 8 𝑏𝑏 = 𝑏𝑏 = 𝑏𝑏 = 9 𝑛𝑛 ∑ 𝑥𝑥𝑥𝑥−(∑ 𝑥𝑥)(∑ 𝑥𝑥) 2 𝑛𝑛 ∑ 𝑥𝑥 −(∑ 𝑥𝑥)2 7 ∑ 532−(28 ×112) (7 ×140)−(28)2 3,724−3,136 980−784 588 = 196 = 3 65.61% Coefficient of determination (𝑟𝑟 2 ) is the correlation coefficient (r) squared = 0.812 = 0.6561 = 65.61% 3,500 10 units Q3 sales = 2,450 which is 30% less than the trend. Therefore trend = 2,450 0.7 = 3,500 40,000 11 units Actual sales = Trend × seasonal variation Let trend = x 30,000 = x × 0.75 x (trend sales) = 30,000 0.75 = 40,000 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 2: St at i s t i c al t e c h n i qu e s 12 149,000 units Trend sales = 144,000 + (1,800 × 2) = 144,000 + 3,600 = 147,600 Forecast sales = Trend + Seasonal variation Forecast sales = 147,600 + 1,870 = 149,470 or 149,000 (to the nearest 1,000 units) 13 112 Index number = (448/400) × 100 = 112 14 450,000 kg Base level = 513,000 × (100/114) = 450,000 15 Writing a memo 16 =C4 – C5 17 =B6/B2*100 18 $10,020 19 $ 21.96 $20 × 101/92 = $21.96 20 21 20.52 118.1 189/160 × 100 = 118.1 Downloaded by Hooria Noor (nhooria9@gmail.com) 125 lOMoARcPSD|27223832 126 3: Su mmari s i n g a n d a n a l y s i ng d a t a A C C A MA Chapter 3: Summarising and analysing data Objective test questions Expected values 1 It is impossible to say Without the probabilities to assign, it is impossible to calculate the expected value of each project. 2 Either Project X or Project Z If the prices are equally likely then, EV of project X = $70,Y = $66 and Z = $70 3 1.05 Number of errors on invoice 0 1 2 3 4 5 or more Number of invoices 80 65 30 15 10 0 Total EV 0 65 60 45 40 0 210 There are 210 errors in total on 200 invoices = 210/200 = 1.05 per invoice 4 40 p Order Qty 20 30 40 50 .3 20 Level of demand .2 30 .35 40 .15 50 EV 30 20 10 0 30 45 35 25 30 45 60 50 30 45 60 75 30 37.5 40 33.75 Ordering 40 has the highest expected profit Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 3: Su mma ri s i n g a n d a n a l y s i ng d a t a 5 230 Number of visitors 0 – under 100 100 – under 200 200 – under 300 300 – under 400 400 – under 500 Midpoint (a) 50 150 250 350 450 Frequency (Number of days) (b) 5 9 6 7 3 30 (a) × (b) 250 1,350 1,500 2,450 1,350 6,900 Expected number of visitors = 6,900/30 = 230 6 Expected value 7 $ 85600 Demand 30,000 50,000 70,000 8 Variable Cost $ Contribution per unit $ 6 8 10 6 8 10 6 8 10 6 4 2 6 4 2 6 4 2 Total Contribution ($’000) 180,000 120,000 60,000 300,000 200,000 100,000 420,000 280,000 140,000 Fixed Costs ($’000) 80,000 80,000 80,000 100,000 100,000 100,000 100,000 100,000 100,000 A fall of $75 Current expected value (0.6 × 2,500) + (0.4 × 1,000) = $1,900 Revised expected value (0.55 × 2,500) + (0.45 × 1000) = $1,825 So a fall of $75 Downloaded by Hooria Noor (nhooria9@gmail.com) Profit ($’000) (x) Joint Probability (p) 0.02 0.03 0.05 0.12 0.18 0.30 0.06 0.09 0.15 1.000 EV (profit) 100,000 40,000 (20,000) 200,000 100,000 Nil 320,000 180,000 40,000 (px) 2,000 1,200 (1,000) 24,000 18,000 Nil 19,200 16,200 6,000 85,600 127 lOMoARcPSD|27223832 128 3: Su mmari s i n g a n d a n a l y s i ng d a t a 9 A C C A MA $2,400 Multiply the profit with estimated probability. Take sum of all the expected values to calculate the final. Profit ($000) –1 1 3 5 10 Probability 0.1 0.3 0.4 0.2 EV –0.1 0.3 1.2 1 2.4 0.23 (0 × 316) + (1 × 79) + (2 × 3) + (3 × 1) + (4 × 1) + (5 × 0) + (6 × 0) = 0 + 79 + 6 + 3 + 4 + 0 + 0 = 92 Expected number of defects per box = 92/400 = 0.23 (to 2 decimal places) 11 295 Number of visitors to store 0 – under 100 100 – under 200 200 – under 300 300 – under 400 400 – under 500 Midpoint (a) 50 150 250 350 450 Frequency (Number of stores) 50 100 250 550 50 Proportion (b) 0.05 0.1 0.25 0.55 0.05 Averages and distributions 12 “The mode is the most frequently occurring item in a population.” 13 2.5 Arranged in order the number of rejects are: 1, 1, 2, 2, 2, 3, 3, 4, 5, 6 The median is the average of the 5th and 6th value: (2 + 3)/2 14 2 Arranged in order the number of rejects are now: 1, 1, 1, 2, 2, 2, 3, 3, 4, 5, 6 The median is the 6th value which is now 2 Downloaded by Hooria Noor (nhooria9@gmail.com) (a) × (b) 2.50 15.00 62.50 192.50 22.50 295.00 lOMoARcPSD|27223832 A C C A MA 3: Su mma ri s i n g a n d a n a l y s i ng d a t a 54.27 15 Midpoint x 25 75 125 175 225 Daily sales ($) 0 to < $50 $50 to < $100 $100 to < $150 $150 to < $200 $200 to < $250 Mean daily sales = x̅ = ∑ 𝑓𝑓𝑥𝑥 697500 =σ=� 28 − � = �2,945 = 54.27 28 � 28 ∑𝑓𝑓 𝒙𝒙𝟐𝟐 ∑ 𝑓𝑓 2 Number of days (f) 2 3 7 12 4 28 f×x 50 225 875 2100 900 4,150 − ��� x2 190 4 (𝒙𝒙 - �) 𝐱𝐱 32.5 (7.5) 2.5 (27.5) 𝟐𝟐 (𝒙𝒙 − ���� 𝐱𝐱) 1056.25 56.25 6.25 756.25 1875.00 = 47.5 Variance = σ2 = ∑(𝑥𝑥−𝑥𝑥̅ )2 𝑛𝑛 = 1875/4 = 468.75 Standard deviation, σ = � ∑(𝑥𝑥−𝑥𝑥̅ )2 𝑛𝑛 = √468.75 = 21.65 17 46 Coefficient of variation = % σ x� × 100 = 21.65 47.5 × 100 = 45.6% 18 161.5 ─ 164.5 625 5,625 15,625 30,625 50,625 103,125 = �24911 − (148.21 × 148.21) = √24,911 − 21,966 Purchases (units) 80 40 50 20 190 1 2 3 4 𝒙𝒙𝟐𝟐 =$148.21 The variance is 468.75 and the standard deviation is 21.65 Quarter x̅ = 4150 $4,150 = ∑ 𝑓𝑓 Standard deviation, σ = � 16 129 cm Downloaded by Hooria Noor (nhooria9@gmail.com) f𝒙𝒙𝟐𝟐 1,250 16,875 109,375 367,500 202,500 697,500 lOMoARcPSD|27223832 130 3: Su mmari s i n g a n d a n a l y s i ng d a t a 19 A C C A MA 99.865% 3 standard deviations above mean = 0.49865 Jenny is taller than everyone below 0.49865 = 0.49865 + 0.5 = 0.99865 = 99.865% 20 Discrete Continuous Materials used – 5,000 kg Output produced – 1,000 units Time taken by labour – three hours Hours or kg can take on any value – they don’t have to be whole numbers, and are therefore continuous data. The units produced are distinct and separate and are therefore discrete. 21 It is the middle point of a population. Populations can only have one median. The average is the expected value of the population. The standard deviation indicates the degree of dispersion of the values in a population. 22 The standard deviations show that the amounts donated were less variable in 20X3 than in 20X0. Standard deviation has fallen, showing a smaller variation. The mean has risen, indicating the average donation has risen, not fallen. The standard deviations do not indicate average donations, the means do not indicate how variable the amounts donated were. 23 Data B A 125 20 0.16 Mean Standard deviation Coefficient of variation B 150 25 0.167 C 175 20 0.114 D 200 25 0.125 Coefficient of variation = Standard deviation / Mean The bigger the coefficient of variation, the wider the spread. B has the largest coefficient of variation. 24 2.83 𝑥𝑥̅ = (2 + 4 + 6 + 8 + 10) / 5 = 6 𝑥𝑥 2 4 6 8 10 ∑ 𝑥𝑥 − 𝑥𝑥� –4 –2 0 2 4 0 (𝑥𝑥 − 𝑥𝑥�)2 16 4 0 4 16 40 Standard deviation = �40/5 = 2.83 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 3: Su mma ri s i n g a n d a n a l y s i ng d a t a 25 25% Cv = Standard Deviation / Mean 3/12 = 0.25 → 25% 26 2.2 Application of the formula ∑ 𝑓𝑓𝑥𝑥/ ∑ 𝑓𝑓 = 110 / 50 Number of rejects in each sample 0 1 2 3 4 5 27 Number of samples (frequency of reject) 5 10 10 20 5 0 ∑f = 50 fx 0 10 20 60 20 0 ∑fx = 110 Neither I nor II 50% of scores are always less than the median. The variance is a measure of the total spread of a population rather than average spread around the mean (which is measured by the standard deviation). 28 The probability that sales revenue will be in the range $36,800 to $63,200 is 90%. There is a 5% chance that sales revenue will be greater than $63,200 and a 5% chance that sales revenue will be less than $36,800. 29 216.51 Quarter 1 2 3 4 x̅ = 1,900 4 187,500 4 𝟐𝟐 (𝒙𝒙 − ���� 𝐱𝐱) 625 5,625 105,625 75,625 187,500 = 475 The standard deviation, σ = � =� (𝒙𝒙 - 𝐱𝐱 �) 25 (75) 325 (275) Sales (units) 500 400 800 200 1,900 = 216.51 ∑(𝑥𝑥−𝑥𝑥̅ )2 𝑛𝑛 Downloaded by Hooria Noor (nhooria9@gmail.com) 131 lOMoARcPSD|27223832 132 3: Su mmari s i n g a n d a n a l y s i ng d a t a A C C A MA 30 1.7 x̅ = 24 8 =3 (𝒙𝒙 - 𝐱𝐱 �) -1 2 -3 0 2 1 1 -2 Number of books read 2 5 0 3 5 4 4 1 (𝑥𝑥−𝑥𝑥̅ )2 Standard deviation = � 𝑛𝑛 ����𝟐𝟐 (𝒙𝒙 − 𝐱𝐱) 1 4 9 0 4 1 1 4 24 24 = � 8 = √3 = 1.7 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 4: Co s t i n g Chapter 4: Costing Objective test questions Cost classification 1 2 Production costs Non Production costs Production worker salaries Marketing campaign Factory electricity bills Head office stationary Material components used to manufacture the new product The material is directly traceable to each unit of production, hence they are direct costs. The cost of registering the patent is an overhead. The cost is linked to the production of the product, but is not traceable to the individual units of production (the cost is not an incremental cost for each additional unit produced). The finance department costs cannot be traced directly to a product so they are indirect costs. Overheads are always classed as factory overheads unless the overtime is worked at the specific request of the customer to get his order completed or the overtime is worked regularly in the normal course of operations in which case it is incorporated into the direct labour hourly rate. 3 4 $ Production overhead cost 483 Selling price of the repair $690 Less profit mark-up ($138) Cost of repair $552 Less overhead cost ($69) Prime cost $483 5 Semi–variable cost A fixed and variable element as per the electricity example is a semi-variable cost Step-cost –This is a fixed cost which increases once operating capacity is surpassed High-low cost –This is a method to split a semi variable cost into fixed and variable elements Fixed cost –This is cost which remains constant as output rises Downloaded by Hooria Noor (nhooria9@gmail.com) 133 lOMoARcPSD|27223832 134 4: Co s t i n g 6 A C C A MA remain constant in total when output volume changes TOTAL fixed costs remain constant as OUTPUT varies. The Fixed cost PER UNIT, would fall as output increases as the fixed cost is spread over a great number of units. 7 True Only direct materials and direct labour are separately identified in the prime cost. All other direct costs are grouped together as direct expenses. 8 Prime cost The royalty per unit can be directly allocated to a particular unit of production. This can be allocated as a DIRECT expense and so is a prime cost. 9 A separate cost centre Cost behaviour 10 C 11 D 12 B 13 A 14 Costs do not change with the level of activity until the activity level exceeds a certain point. They then increase, but then remain stable again until activity levels exceed another critical point. 15 14,000 $ Output 24,000 9,000 15,000 Highest output Lowest output Difference 60,000 Variable cost = 15,000 = $4 per unit. Total cost = Fixed cost + Variable cost $110,000 = Fixed cost + $4 × 24,000 Fixed cost = $110,000 ─ $96,000 = $14,000 Downloaded by Hooria Noor (nhooria9@gmail.com) Cost ($) 110,000 50,000 60,000 lOMoARcPSD|27223832 A C C A MA 4: Co s t i n g 16 $20,000 Output 25,000 10,000 15,000 Highest output Lowest output Difference Cost ($) 95,000 50,000 45,000 45,000 Variable cost = 15,000 = $3 per unit. Total cost = Fixed cost + Variable cost $95,000 = Fixed cost + $3 × 25,000 Fixed cost = $95,000 ─ $75,000 = $20,000 17 Fixed cost 18 Step The cost of supervisors increases at intervals when a certain number of employees work for the factory. 19 Variable costs are only variable in the short-term. Variable costs can be variable in the long-term as well. 20 Commission received by sales staff. This will vary with sales levels. 21 $ 2.90 Highest activity level is 27,000 and lowest activity level is 7,000 Adjusted highest activity level cost = $128,000 – $12,000 = $116,000 Variable cost per unit = ($116,000 – $58,000/27,000 – 7,000) = $2.90 22 $ 37,700 Fixed cost at lowest level = $58,000 – (7,000 × $2.90) = $37,700 Downloaded by Hooria Noor (nhooria9@gmail.com) 135 lOMoARcPSD|27223832 136 4: Co s t i n g A C C A MA 23 8.55 $ Highest activity level is 24,000 and lowest activity level is 4,000 Adjusted highest activity level cost = $195,000 + (24,000 × 1.50) = $231,000 Variable cost per unit at lowest level = ($231,000 – $60,000)/(24,000 – 4,000) = $8.55 24 25,800 $ Fixed cost at lowest level = $60,000 – (4,000 × 8.55) = $25,800 25 26 $ 1.25 27 $ 370000 $116,575 Labour cost per unit (40,000 × $4) Material cost per unit (40,000 × $3) Variable overhead per unit (40,000 × $2) Fixed overheads per month Total cost Cost coding 100300 PB 28 Cost measurement 29 A function or location for which costs are ascertained Management of business units 30 Sales prices Capital investment Controllable costs Downloaded by Hooria Noor (nhooria9@gmail.com) $ 160,000 120,000 80,000 10,000 370,000 lOMoARcPSD|27223832 A C C A MA 5: A c c o u n t i n g f o r ma t e ri als Chapter 5: Accounting for materials Objective test questions Accounting for materials 1 28,200 units Free inventory = Materials currently in inventory + Materials ordered from suppliers – Materials allocated to customers Free inventory = 30,500 + 24,400 – 26,700 Free inventory = 28,200 2 Provides information to update inventory records Allows quantities delivered by supplier to be checked 3 375 DVD players Reorder level = Lead time in days × Daily demand Reorder level = 15 × 25 = 375 4 90 units Reorder level = Lead time in days × Daily demand Reorder level = 5 × (459 × 12)/(51 × 6) = 90 units 5 LIFO is based on the assumption that the oldest units are sold first. 6 Establishing the quantity to be produced. 7 339 EOQ = units 2CoD Ch EOQ = √ (2 × 40 × 600 × 12/25 × 0.2) = 339 units Downloaded by Hooria Noor (nhooria9@gmail.com) 137 lOMoARcPSD|27223832 138 5: A c c o u n t i n g f o r mat e ri als A C C A MA 8 3,600 $ Annual holding cost = Ch(Q/2) Annual holding cost = 0.50 × 12 × (1,200/2) = $3,600 9 12,000 $ Total annual cost = Co(D/Q) + Ch(Q/2) Total annual cost = (180 × 50,000/1,500) + (8 × 1,500/2) = $12,000 10 The losses figure includes any inventory that has been written off as obsolete. The work-in-progress figure represents materials issued to production. The supplier was not necessarily paid for purchases during the month. The returns figure represents returns from production to inventory. 11 Purchase cost of item 12 Purchase requisition This is an internal document, sent by Stores to the Purchasing Department 13 Fixed Variable Ordering inventory Holding inventory 14 2,000 EOQ = units 2CoD Ch EOQ =√ (2 × 40 × 100,000/2)= 2,000 units $ 4,000 Total annual cost = 40 × (100,000/2,000) + 2 × (2,000/2) = $4,000 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 5: A c c o u n t i n g f o r ma t e ri als 15 2,000 units Ordering EOQ units EOQ = 2CoD Ch EOQ =√ (2 × 50 × 45,000/3) = 1,225 units Total annual cost = 50 × (45,000/1,225) + 3 × (1,225/2) + 45,000 × 4 = $183,674 Using 2,000 units Total annual cost = 50 × (45,000/2,000) + 3 × (2,000/2) + 45,000 × 4 × 0.95 = $175,125 Ordering 2,000 units is cheaper. 16 $ 1,050 Annual batch set-up cost = CoD/Q = 150 × 35,000/5,000 = $1,050 17 $ 2,000 Total annual cost = CoD/Q + Ch(1 – (D/R))Q/2 = 50 × 12,000/600 + 10(1 – 12,000/18,000) × 600/2 = 1,000 + 1,000 = $2,000 18 3,000 units 2C 0D Economic Batch Quantity = CH (1 - D / R) Economic Batch Quantity = √ (2 × 75 × 120,000/10 (1 – 120,000/150,000)) = 3,000 units 19 $ 6,000 Total annual cost = CoD/Q + Ch(1 – (D/R))Q/2 = 75 × 120,000/3,000 + 10(1 – 120,000/150,000) × 3,000/2 = 3,000 + 3,000 = $6,000 Downloaded by Hooria Noor (nhooria9@gmail.com) 139 lOMoARcPSD|27223832 140 5: A c c o u n t i n g f o r mat e ri als 20 True 21 FIFO A C C A MA FIFO will assume that the oldest, and here the cheapest, inventory is issued first. 22 776,250 $ Date No of units 000 20 25 (20) (15) 40 (10) (20) 25 45 Opening 5 8 8 11 23 23 30 Closing Cost per unit $ 15.00 15.50 15.00 15.50 17.25 15.50 17.25 17.25 Value $ 300,000 387,500 (300,000) (232,500) 690,000 (155,000) (345,000) 431,250 776,250 23 527,500 $ $ 1,560,000 (1,032,500) 527,500 Sales (65,000 × $24) Cost of Sales (as above) Profit 24 $ Date Opening 5 8 8 11 23 30 Closing 753,750 No of units 000 20 25 (25) (10) 40 (30) 25 45 Cost per unit $ 15.00 15.50 (15.50) (15.00) 17.25 17.25 17.25 Value $ 300,000 387,500 (387,500) (150,000) 690,000 (517,500) 431,250 753,750 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 5: A c c o u n t i n g f o r ma t e ri als 25 505,000 $ $ 1,560,000 (1,055,000) 505,000 Sales (65,000 × $24) Cost of Sales (as above) Profit 26 768,450 $ Date Opening 5 8 11 23 30 Closing No of units 000 20 25 45 (35) 40 50 (30) 25 45 Cost per unit $ 15.00 15.50 15.28 15.28 17.25 16.85 16.85 17.25 Value $ 300,000 387,500 687,500 (534,800) 690,000 842,700 (505,500) 431,250 768,450 27 519,700 $ $000 1,560,000 (1,040,300) 519,700 Sales (65,000 × $24) Cost of Sales (as above) Profit 28 Higher Lower Unchanged EOQ Annual holding cost If the Ordering cost per batch (Co) increased, this would raise the EOQ (see formula) As Ch = % × (Purchase cost + Order cost), then any increase in Order Cost will increase in the Annual Holding cost 29 219 30 Purchase order Supplier’s invoice Downloaded by Hooria Noor (nhooria9@gmail.com) 141 lOMoARcPSD|27223832 142 6: A c c o u n t i n g f o r l ab ou r A C C A MA Chapter 6: Accounting for labour Objective test questions Accounting for labour 1 102.9 % Expected hours = 60,000 × (150,000/50,000) = 180,000 hours Labour efficiency ratio = (Expected hours/Actual hours) × 100% = (180,000/175,000) × 100% = 102.9% 2 116.7 % Labour capacity ratio = (Actual hours/Planned hours) × 100% = (175,000/150,000) × 100% = 116.7% 3 120.0 % Labour production volume ratio = (Expected hours/Planned hours) × 100% = (180,000/150,000) × 100% = 120.0% 4 $103.20 Basic salary = $12 × 8 hours = $96 Time that should have been taken to produce 95 units = 95 × (6/60) = 9.5 hours Time saved = 9.5 hours – 8 hours = 1.5 hours Bonus = 1.5 × 40% × $12 = $7.20 Pay = $96 + $7.20 = $103.20 5 Training course costs Company doctor salary Better training opportunities may be a means of motivating staff to stay. Replacement costs would also include costs of training, of staff who had joined the organisation. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 6: A c c o u n t i n g f o r l ab ou r 6 $ 2.03 Time that should be taken to produce 126 units = 126 × (5/60) = 10.5 hours Time saved = 10.5 hours – 8 hours = 2.5 hours Total bonus = 9 × 2.5 × 60% = $13.50 Peter’s share = $13.50 × (100% - 40%) /4 = $2.03 7 Debit: Work in Progress Account $61,250, Overtime Premium Account $3,750 Credit: Labour Account $65,000 Downloaded by Hooria Noor (nhooria9@gmail.com) 143 lOMoARcPSD|27223832 144 7: A c c o u n t i n g f o r o v e rh e ads A C C A MA Chapter 7: Accounting for overheads Objective test questions Accounting for overheads 1 P1 $ 90,200 P2 $ $125,100 Equations can be formulated as: S1 = 9,300 + (7/70)S2 S2 = 6,000 + (5/50)S1 S1 = 9,300 + 0.1 (6,000 + 0.1S1) 0.99S1 = 9,900 S1 = 10,000 S2 = 6,000 + (0.1 × 10,000) S2 = 7,000 P1 $ 80,000 6,000 4,200 90,200 Costs S1 S2 P2 $ 120,000 3,000 2,100 125,100 S1 $ 9,300 (10,000) 700 Nil S2 $ 6,000 1,000 (7,000) Nil 2 As the department appears to be labour intensive a direct labour hour rate would be an appropriate overhead absorption rate 3 True False Overhead was $2,000 under-absorbed Absorption was $3.50 × 4,000 = $14,000 compared with actual overheads of $16,000. 4 Overhead was $10,000 over-absorbed Absorption 2 × 21,000 × $10 = $420,000 compared with the actual overhead of $410,000. 5 $11,000 Overhead absorbed in the period was $5 × 3,000 = $15,000. This is an over-absorption of $4,000, so actual overheads are $11,000. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 7: A c c o u n t i n g f o r o v e rh e ads 6 True False Only variable costs are assigned to cost units whilst fixed costs are treated as period costs Service department costs are reapportioned to production centres A production overhead associated with a cost centre should be allocated to that cost centre Only production overheads are allocated/apportioned to cost centres 7 Absorbed overheads are lower than actual overheads 8 $30,400 Fixed production overheads were absorbed at the rate of $30.40 per labour hour. 1,000 labour hours were worked so fixed overheads absorbed were $30.40 × 1,000 = $30,400. 9 Under absorbed by $9,600 Actual overheads were $40,000 compared with the $30,400 absorbed. 10 $50 per hour Overheads of $200,000 ($194,000 + $6,000) were absorbed in 4,000 actual labour hours. 11 21,000 12 $10,000 under-absorbed 13 $9.68 Budgeted overhead Budgeted machine hours 14 hours 464,640 = 48,000 =$9.68 per machine hour. $14,720 under absorbed $9.68 × 46,000 = $445,280 which is less than the actual overhead of $460,000. 15 Overheads will be over absorbed by $1,000 due to lower than expected labour hours coupled with lower than expected expenditure. Downloaded by Hooria Noor (nhooria9@gmail.com) 145 lOMoARcPSD|27223832 146 7: A c c o u n t i n g f o r o v e rh e ads 16 A C C A MA $5 Patients 15,250 8,250 7,000 Highest number of patients Lowest number of patients Difference Variable overhead = 17 35,000 7,000 Cost ($) 135,000 100,000 35,000 = $5 per patient $58,750 The variable cost for 8,250 patients at $5 per patient is $41,250. The fixed cost must be $58,750 (100,000 – 41,250). 18 7,344 58,750 8 19 patients = 7,344 $2,500 over-absorbed The actual overhead ( $861,000) is compared with the overhead actually absorbed $863,500 ($11 × 78,500). 20 Service departments do not do any work for each other. Therefore there is no need to take account of time spent on work for other service departments. 21 The operating hours of the machines in each department 22 $245 23 $24,400 24 I and IV Statements I and IV are correct. II III IV V Indirect materials issued from inventory was $10,200 - correct Overhead absorbed during the period was $86,175 – No, overhead absorbed was $162,200. Overhead for the period was over absorbed by $4,160 – No, overhead was under absorbed – $4,160 has been debited to the income statement. Indirect wages cost incurred was $69,985 - correct Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 7: A c c o u n t i n g f o r o v e rh e ads 25 $9,357 26 $18 Assembly Total minutes are X (36 × 6,000) and Y (48 × 7,500) = 576,000 OAR = $144,000 / 576,000 = $0.25 per minute Finishing Total minutes are X (31.25 × 6,000) and Y (30 × 7,500) = 412,500 OAR = $82,500 / 412,500 = $0.20 per minute Y (48 × $0.25) + (30 × $0.20) = $18 27 Over absorbed by $4,725 Actual overhead = $140,875 Absorption (Activity × OAR) = $145,600 (45,500 units $3.20 per unit) Over absorption = $4,725 (the actual cost was over estimated) 28 Under absorbed by $1,020 29 $54,366 30 Debit Production Overheads Account Credit Bank and Cash Account Downloaded by Hooria Noor (nhooria9@gmail.com) 147 lOMoARcPSD|27223832 148 8: A b s o rp t i o n a nd marg i n al co s t i ng A C C A MA Chapter 8: Absorption and marginal costing Objective test questions Absorption and marginal costing compared 1 Contribution is ‘sales value minus variable cost of sales’. 2 $5 The direct costs and the variable overheads are deducted in computing the contribution. However, the absorbed fixed overhead is not deducted. 3 $38,000 As closing inventory has fallen by 500 units, the profit under absorption costing is lower than the marginal costing profit by $2,000 ($4 × 500). 4 $24,000 Closing inventory has fallen by 300 so the profit under absorption costing is lower than the marginal costing profit. Overheads are absorbed at the rate of 200,000�10,000 = $20 per unit so the profit is lower by $20 × 300= $6,000. 5 2,000 The absorption costing loss is $12,000 lower than the marginal costing profit so with a fixed overhead absorption rate of $4 a unit, closing inventory has fallen by 3,000 units. This means that production in the period was 2,000 units (5,000 – 3,000). 6 79,400 Closing inventory increased by 200 units, so the absorption costing profit is higher than the marginal costing profit. With a fixed overhead absorption rate of $3 a unit, the absorption costing profit is $600 higher. 7 $ 10 The absorption costing profit was $20,000 higher than the marginal costing profit and the closing inventory was 2,000 units higher than the opening inventory. Therefore the fixed overhead absorption rate was $10 per unit. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 8: A b s o rp t i o n a nd marg i n al co s t i ng 8 448,000 $ $ 588,000 (140,000) 448,000 Contribution for month (9,800 × $60*****) Less actual fixed overhead incurred Marginal costing profit *****Contribution per unit (100 – 40) $60 9 454,000 $ $ 980,000 (392,000) 588,000 (147,000) 13,000 454,000 Sales (9,800 × $100) Less variable costs ( 9,800 × $40) Less: fixed overhead absorbed (9,800 × 15) Add: over-absorbed overhead (10,200 × $15) ─ $140,000 Absorption costing profit EXAM SMART For learning purposes, we have shown how to calculate the absorption costing profit. However, given the marginal costing profit calculated in above, you could more quickly calculate the absorption costing profit by adding the $15 × 400 =$6,000 to the marginal cost profit. The $6,000 is the amount of overhead absorbed into the increased closing inventory. 10 741,000 $ The unit cost for marginal costing purposes is $25 ( $12 + $13) $ Sales ($105 × 10,200) Opening inventory (1,000 × 25) Production (10,000 × 25) Less: Closing inventory ( 800 × 25) Contribution Less: Fixed costs Marginal costing profit Downloaded by Hooria Noor (nhooria9@gmail.com) $ 1,071,000 25,000 250,000 (20,000) (255,000) 816,000 (75,000) 741,000 149 lOMoARcPSD|27223832 150 8: A b s o rp t i o n a nd marg i n al co s t i ng A C C A MA 11 739500 $ 75,000 The fixed overhead absorption rate was 10,000 = $7.50 making the unit cost for absorption costing purposes $32.50 (25 + 7.5) $ Sales ($105 × 10,200) Opening inventory (1,000 × 32.50) Production (10,000 × 32.50) Less: Closing inventory (800 × 32.50) $ 1,071,000 32,500 325,000 (26,000) (331,500) 739,500 Absorption costing profit EXAM SMART Again, the absorption costing profit could have been arrived at more quickly by looking at the fixed overhead that had been absorbed in the decreased inventory (200× $7.50) and deducting it from the marginal costing profit. 12 $44,000z Closing inventory has risen by 500 units so the absorption costing profit will be $6,000 higher than the marginal costing profit. 13 $4,000 higher Closing inventory is budgeted to fall by 2,000 units and so the absorption costing profit will be 36,000 lower than the marginal costing profit. The fixed overhead absorption rate is = $2 a unit, 18,000 so the marginal costing profit is $ 4,000 higher than the absorption costing profit. 14 $19,000 Marginal costing profit = Absorption costing profit – (Increase in inventory × overhead absorbed) Marginal costing profit = $25,000 – ((2,000 – 1,500) × $4 × 3) = $19,000 15 $7,500 higher 16 Not possible to calculate A cost of a stores (warehouse) assistant cannot be directly attributed to a particular cost unit and so is classified as indirect labour. All the others can be considered a direct cost. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 8: A b s o rp t i o n a nd marg i n al co s t i ng 17 $2,240 lower As production is greater than sales, this increases closing inventory. As closing inventory is greater than opening inventory then a greater value of fixed overheads is held in the inventory valuation, so absorption profit is greater than marginal profit. OAR unit =- budget overhead / budget units = $96,000/24,000 units = $4 per unit Difference in profit = Change in inventory levels x OAR unit = (24,000 – 23,440) × $4 = $2,240 Therefore marginal costing profit would be $2,240 lower than absorption costing profit. 18 $ 3 Difference in profit = Change in inventory levels × OAR unit ($37,000 – $28,000) = (78,500 units – 75,500 unit) × OAR unit OAR unit = $9,000/3,000 units = $3 per unit Downloaded by Hooria Noor (nhooria9@gmail.com) 151 lOMoARcPSD|27223832 152 9: P ro c e s s c o st i n g A C C A MA Chapter 9: Process costing Objective test questions Process costing 1 True False Any normal loss in a process account is valued at the same rate as good production whilst the abnormal loss is valued at scrap value If actual output is less than input but more than expected output, an abnormal gain occurs It is true that abnormal losses are treated differently from normal losses. However, the above statement is the wrong way round. It is normal losses that are valued at their scrap value and abnormal losses that are valued at the same rate as good production. 2 $4.33 Costs – Scrap value Expected output = 200,000−5,000 45,000 3 $ 3,000 The 10% normal loss is 2,000 kg which are sold for $1.50 a kg. 4 $ 6,444 The total costs of inputs are $61,000. This needs to be adjusted for the value of the normal loss. This is allocated across the expected output of 18,000 kg so the cost of the 2,000 kg of abnormal 61,000−3000 loss is × 2,000 = $6,444. 20,000−2000 5 $ 51,556 The total costs of inputs are $61,000. This needs to be adjusted for the value of the normal loss. This is allocated across the expected output of 18,000 kg so the cost of the 16,000 kg of output 61,000−3000 is 18,000 × 16,000 = $51,556. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 9: P ro c e s s c o st i n g 6 $50.74 The total costs are $240,000 + $40,000 = $280,000. Output value per unit = Total costs - Scrap value of normal loss Expected output = 280,000−6,000 5,400 = $50.74 7 22,344 $ Output Finished goods Normal loss Abnormal loss Closing inventory Materialsequivalent units 2,800 Litres 2,800 160 140 100 3,200 140 100 3,040 Cost 15,520 8,500 Materials (3,200 × $5 – 160 × $3) Conversion costs Conversion costsequivalent units 2,800 140 20 2,960 Equivalent units 3,040 2,960 Cost per equivalent unit $5.11 $2.87 $7.98 Cost of completed production 2,800 litres at $7.98 = $22,344. EXAM SMART Hint: Don’t forget the abnormal loss! 8 568.40 $ $511 Materials (100 equivalent units at 5.11) Conversion costs ( 20 equivalent units at 2.87) 9 $57.40 $568.40 $5,300 Output Output Normal loss Abnormal loss (bal) Closing WIP Kg 12,000 1,500 500 1,000 15,000 Materials equivalent units 12,000 500 1,000 13,500 Downloaded by Hooria Noor (nhooria9@gmail.com) Labour and overhead equivalent units 12,000 500 500 13,000 153 lOMoARcPSD|27223832 154 9: P ro c e s s c o st i n g A C C A MA Materials ($60,000 – $1,500) Labour and overhead Cost 58,500 26,000 Equivalent units 13,500 13,000 Cost per EU $4.3 $2 Value of WIP $ 4,300 1,000 5,300 Materials ( 1,000 × 4.30) Labour and overhead (500 × 2) 10 1,900 Output Finished goods Closing WIP Units 1,800 200 2,000 Material Equivalent units 1,800 200 (100%) 2,000 Labour Equivalent units 1,800 100 (50%) 1,900 Overhead Equivalent units 1,800 40 (20%) 1,840 11 44,694 $ Material 4,000 16,000 20,000 Opening WIP Added Total cost Equivalent units ( above) Cost per equivalent unit 2,000 $10 Labour 5,000 18,000 23,000 1,900 $12.11 The value of the units transferred to finished goods is 1,800 × 24.83 = $44,694 12 800 kg Abnormal loss = 12,000 – (10% × 12,000) – 10,000 = 800 kg 13 $ 60,000 Cost per kg = (30,000 + 34,800)/(12,000 – 1,200) = $6 Cost of output transferred = 10,000 × $6 = $60,000 Downloaded by Hooria Noor (nhooria9@gmail.com) Overhead 1,000 4,000 5,000 1,840 2.72 lOMoARcPSD|27223832 A C C A MA 9: P ro c e s s c o st i n g 14 73,280 $ Output Finished goods Normal loss Abnormal loss Closing WIP Material Equivalent units 8,000 Kg 8,000 500 500 1,000 10,000 500 1,000 (100%) 9,500 Material $58,500 (60,000 – 1,500) 9,500 $6.16 Total cost Equivalent units (above) Cost per equivalent unit Labour and overhead Equivalent units 8,000 500 500 (50%) 9,000 Labour and overhead $27,000 9,000 $3 Value of output is $9.16 × 8,000 = $73,280 15 4,580 $ The abnormal loss is 500 × $9.16 (above) = $4,580 16 7,660 $ Material $6.16 1,000 $6,160 Costs per equivalent unit (above) Equivalent units in WIP ( above) Value in WIP Labour and overhead $3 500 $1,500 The total value of the closing WIP is $7,660 17 $1,750 Materials Direct labour Production overhead Kg 25,000 $ 75,000 29,250 15,125 119,375 Output Normal loss Abnormal loss Abnormal loss = 25,000 – (25,000 × 5%) – 23,400 = 350 kg Costs per kg = (75,000 + 29,250 + 15,125 – 625)/(25,000 – 1,250) = $5 Downloaded by Hooria Noor (nhooria9@gmail.com) Kg 23,400 1,250 350 25,000 $ 117,000 625 1,750 119,375 155 lOMoARcPSD|27223832 156 9: P ro c e s s c o st i n g 18 A C C A MA $99,375 Materials Direct labour Production overhead Kg 15,000 $ 60,000 27,400 14,600 102,000 Kg 13,250 1,500 250 15,000 Output Normal loss Abnormal loss $ 99,375 750 1,875 102,000 Abnormal loss = 15,000 – (15,000 × 10%) – 13,250 = 250 kg Costs per kg = (60,000 + 27,400 + 14,600 – 750)/(15,000 – 1,500) = $7.50 19 $ 105000 Total costs = 88,000 + 50,000 + 39,000 – (1,000 × 2) = $175,000 Volume Pye Mye 15,000 10,000 25,000 Costs of pye = $175,000 × (15,000/25,000) = $105,000 20 $ 70,000 Costs of mye = $175,000 × (10,000/25,000) = $70,000 21 $ 75,000 Costs of pye = $175,000 × (300,000/700,000) = $75,000 22 $ 100,000 Costs of mye = $175,000 × (400,000/700,000) = $100,000 23 By-products are equivalent to abnormal losses. By-products are equivalent to normal losses. Downloaded by Hooria Noor (nhooria9@gmail.com) Unit price $ 20 40 Sales value $ 300,000 400,000 700,000 lOMoARcPSD|27223832 A C C A MA 9: P ro c e s s c o st i n g 24 384,192 $ Process account Units 1,500 Opening WIP Raw materials Conversion cost $ 59,000 330,000 54,000 443,000 Transfer to process 2 Units 6,400 $ ? Closing WIP 1,100 ? Statement of equivalent units Costs Opening WIP Inputs Total Equivalent units Transfer to Process 2 Closing WIP Total Total $ 59,000 384,000 443,000 Raw materials $ 50,000 330,000 380,000 Conversion costs $ 9,000 54,000 63,000 Units 6,400 1,100 7,500 Units 6,400 1,100 7,500 Units 6,400 330 6,730 $50.67 $9.36 Total $ 384,000 Raw materials $ 330,000 Conversion costs $ 54,000 Units 1,500 4,900 1,100 9,000 Units 4,900 1,100 6,000 Cost per equivalent unit Transfers to Process 2 = 6,400 × ($50.67 + $9.36) = $384,192 25 58,826 $ Closing WIP = (1,100 × $50.67) + (330 × $9.36) = $58,826 26 379,598 $ Statement of equivalent units Costs Inputs Equivalent units Finishing opening WIP Starting and finishing Closing WIP Total Cost per equivalent unit $55.00 Value of transferred Opening WIP = $59,000 + (900 × $8.81) = $66,929 Value of Started and Finished units = 4,900 × ($55.00 + $8.81) = $312,669 Total value transferred = $379,598 Downloaded by Hooria Noor (nhooria9@gmail.com) Units 900 4,900 330 6,130 $8.81 157 lOMoARcPSD|27223832 158 9: P ro c e s s c o st i n g A C C A MA 27 63,407 $ Closing WIP = (1,100 × $55.00) + (330 × $8.81) = $63,407 28 $660 Value = 200 × $11 × 30% = $660 29 $36,400 Physical units are used to apportion joint production costs so this will be based on production units (sales + closing inventory as no opening inventory) G 412,000 units H 228,000 units Total 640,000 Costs relating to H are therefore $136,800 (228/640 × $384,000) + $159,600 (further processing costs of H) = $296,400 This relates to the 228,000 production units so $1.30 per unit giving a closing inventory value of $36,400 (28,000 units × $1.30). 30 $24,400 Value = Value of units started and finished in month + Value of completed units in opening WIP Value = ((2,500 – 400) × $10) + ($1,800 + (400 × 40% × $10)) = $24,400 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 10: O t h e r c o s t i ng t e c hn i q u e s Chapter 10: Other costing techniques Objective test questions Job and batch costing 1 86.40 $ $ 10.00 24.00 34.00 20.00 54.00 10.80 64.80 21.60 86.40 Direct material (2 kg × $5) Direct labour (3hr × $8) Prime cost Production overhead ($200,000 × 3/30,000) Cost of production Sales overhead ($100,000 × 54/500,000) Cost of job Profit margin ($64.80 × 25/75) Price quoted 2 $55,680 A T account is the best way to review the transactions. Costs b/f Materials from stores Materials from WW Labour Overheads $ 20,000 14,000 8,000 9,000 1,400 52,400 Materials to XV Cost of sales (bal fig) $ 6,000 46,400 52,400 $46,400 × 120% = $55,680 3 4 Costs will be borne by user departments who incurred them. User departments may use service departments more carefully. The efficiency of service departments can be measured. Budgeting service department expenditure should become easier. Batch costing is a form of specific order costing where costs are attributed to batches of product (unit costs can be calculated by dividing by the number of products in the batch). Downloaded by Hooria Noor (nhooria9@gmail.com) 159 lOMoARcPSD|27223832 160 10: O t h e r c o s t i ng t e c hn i q u e s 5 $ A C C A MA 371.88 Machine set up costs Artwork Paper ($22.50 × 5) Other printing materials Labour (S8 × 4) Fixed overheads absorbed ($4,500/150) Margin (× 20/80) 6 $ 245.31 Margin (× 20/80) $ 80.00 25.00 450.00 72.00 128.00 30.00 785.00 196.25 Per 5,000 leaflets 981.25 245.31 Machine set up costs Artwork Paper ($22.50 × 5 × 4) Other printing materials ($18 × 4) Labour ($8 × 4 × 4) Fixed overheads absorbed ($4,500/150) 7 $ 5744 Total costs = $9,000/(1 + mark-up) = $9,000/(1 + 0.2) = $7,500 Production overheads = 40 × 8 = $320 Prime cost + Non-production overheads = $7,500 – $320 = $7,180 Prime cost + 0.25 Prime cost = $7,180 Prime cost = $5,744 8 $ 80.00 25.00 112.50 18.00 32.00 30.00 297.50 74.38 371.88 $ 3400 Total costs = $12,000 × (1 – margin) = $12,000(1 – 0.25) = $9,000 Production overheads = 50 × $12 = $600 Prime cost + Non-production overheads = $9,000 – $600 = $8,400 Prime cost + 0.5 Prime cost = $8,400 Prime cost = $5,600 Prime cost – Labour cost = Materials cost Materials cost = $5,600 – (50 × $44) = $3,400 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 10: O t h e r c o s t i ng t e c hn i q u e s Service and operation costing 9 10 Use of composite cost units Appropriate cost unit depends on the service offered Services offered may be of short or long duration $1.83 Tonne-kilometre is the most appropriate unit, so cost per unit = ($2,194,900/1,200,600) = $1.83. 11 Student Course Lecturer hour Number of lecturers does not necessarily provide a measure of activity. 12 It does not tell us about the quality of care provided. It does not reflect the differing mixes of care required in different types of ward. 13 (I) and (II) Alternative cost accounting approaches 14 Market price – Required profit margin 15 16 True False Life cycle costing assesses costs on an accounting period basis. Life cycle costing clearly allocates development costs to individual products. Product liability costs Costs of repairing items returned from customers These relate to costs incurred when the products have gone outside the company and the company is dealing with the consequences of faults that have been discovered. 17 They fulfil financial reporting requirements by allocating costs to time periods. They are suitable for high-volume, repetitive production processes. 18 Maturity Downloaded by Hooria Noor (nhooria9@gmail.com) 161 lOMoARcPSD|27223832 162 10: O t h e r c o s t i ng t e c hn i q u e s 19 A C C A MA If indirect costs are a high proportion of total costs ABC is designed to better cope with situations where overheads area large proportion of production costs. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 11: N at u re a n d p u rp o s e o f bu d g e ti n g Chapter 11: Nature and purpose of budgeting Objective test questions Nature and purpose of budgeting 1 2 True False A budget helps to control an organisation by forcing it to create a plan A budget helps an organisation to co-ordinate the allocation of resources A budget can help an organisation to motivate staff An organisation is legally required to present a master budget annually to external stakeholders A budget where local budget holders do not participate in the budget-setting process Budgetary control and reporting 3 Profit centre Behavioural aspects of budgeting 4 Staff suggestions may be ignored and staff may become demotivated as a result. Flexible budgets 5 74,000 $ Production cost is a semi variable cost. Using the high-low method the variable element is: Units 15,000 10,000 5,000 $ 80,000 70,000 10,000 The variable cost is $2 per unit. The fixed cost is $50,000 so for 12,000 units the cost is $50,000 + 12,000 × $2 = $74,000. 6 $240,000 The variable cost element is 300,000−200,000 200,000−100,000 = $1 per unit. So the fixed cost must be $100,000 and the cost of 140,000 units is $100,000 + 140,000 × $1 = $240,000. Downloaded by Hooria Noor (nhooria9@gmail.com) 163 lOMoARcPSD|27223832 164 11: N at u re a n d p u rp o s e o f bu d g e ti n g 7 It is quicker to carry out than flexible budgeting. 8 $379,500 Flexed budget (85,000 units) Variable materials 150 × 85/60 Variable labour 60 × 85/60 Mixed cost – (see working 1) Other overhead (fixed) Total A C C A MA $ $212,500 $85,000 $18,000 + 85 × $400 = $52,000 $30,000 $379,500 Working 1 Units 80% 60% 20% Highest Output Lowest Output Difference $ $50,000 $42,000 $8,000 Variable Cost 1% = $8,000/20 = $400 Total Cost = Fixed cost + Variable cost per unit x Output Using the High point $50,000 = Fixed costs + $400 × 80 $50,000 = Fixed costs + $32,000 Therefore Fixed costs = $50,000 – $32,000 = $18,000 9 A budget for a single activity level A budget for fixed costs – incorrect – a fixed budget includes revenue A budget for a single activity level – correct – a budget for the units the business expects to produce and sell A budget for fixed (non-current) assets – incorrect – a fixed budget is a budgeted income statement, statement of financial position and cash flow. A budget for multiple activity levels - no, this is a flexible budget which is used for planning and decision making. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 11: N at u re a n d p u rp o s e o f bu d g e ti n g Multi task questions 1 ALANOWL (a) 1,286,250 $ Sales revenue = $35 × 1.05 × (15,000 + (1,000 × 20)) = $1,286,250 (b) Sales Quality costs Other fixed costs Variable costs Profit Quarter 4 $ 1,190,000 (49,600) (105,200) (652,800) Quarter 1 $ 1,540,000 (56,800) (105,200) (822,800) 382,400 555,200 Quality costs = $28,000 + (3 × 7,200 (Q4)) or (4 × 7,200 (Q1)) Other costs: At higher activity level, 44,000 units, adjusted other costs are $928,000 + (44,000 × $0.50) = $950,000 Variable cost per unit at 34,000 units will be ($950,000 - $758,000)/(44,000 – 34,000) = $19.20 so variable costs = 34,000 × $19.20 = $652,800 Variable costs per unit at 44,000 units will be $19.20 - $0.50 = $18.70 per unit so variable costs = 44,000 × $18.70 = $822,800 Fixed costs = $758,000 - $652,800 = $105,200 (c) The model cannot cope with an increasing or decreasing trend. The model can cope with a changing trend, and is better than the additive model in that respect. 2 WORSLEY LIMITED (a) Sales Sales revenue Costs Material Labour Variable overhead Resource usage Material Labour Budgeted 10,000 units $ 70,000 $ 150,000 160,000 60,000 30,000 kg 20,000 hr Downloaded by Hooria Noor (nhooria9@gmail.com) Actual $ 42,000 $ 136,000 143,000 47,000 28,000 kg 18,500 hr Difference $ (28,000) $ 14,000 17,000 13,000 2,000 kg 1,500 hr 165 lOMoARcPSD|27223832 166 11: N at u re a n d p u rp o s e o f bu d g e ti n g (b) Fixed budgets are useful at the planning stage to establish broad objectives. Fixed budgets are easier to prepare than flexible budgets. A C C A MA Fixed budgets do not adjust for variations in volume, with the result that there can be large variances. Fixed budgets will not result in realistic cost targets, if, as here, actual activity differs significantly from budgeted activity. (c) The coefficient of determination indicates how much of the change in total sales revenue is due to competitor’s marketing activity. A negative figure indicates an inverse, not necessarily a weak, relationship. A negative figure close to 1 will indicate a strong inverse relationship. The coefficient of determination is + 0.64. The correlation coefficient is not a measurement of simple proportion. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 12: B u d g e t p re p arat i o n Chapter 12: Budget preparation Objective test questions Budget preparation 1 Cash budget A functional budget is a budget prepared for a particular department or function. All of these budgets feed into the master budget. The cash budget is part of the master budget. 2 Depreciation of printing machine Depreciation is not a cash flow so it is not included in the cash budget. However, capital costs are cash flows so they are included. 3 Raw materials inventories are budgeted to decrease A change in the levels of finished goods would be allowed for in the production budget and hence the materials usage budget. If more materials are being used than are being purchased, it must be because the raw materials inventories are budgeted to decrease. 4 Sales budget Production budget As there are no production limitations, sales is the principal budget factor. Before the raw materials budget can be compiled the business must budget for sales quantity and the level of production (which may be more or less than sales quantity due to changes in budgeted inventories). 5 2,600 units The business must budget for sales and also for the increase in the inventory level. 6 21,500 units 20,425 units need to be produced to meet sales and the increase in the inventory level. This is 100 95% of total production so total production needs to be 20,425 × = 21,500. 95 7 30,250 kg Production this quarter is 9,850 units and 29,550kg of raw material is needed. In addition, 700 kg are needed to increase raw material inventory levels. Downloaded by Hooria Noor (nhooria9@gmail.com) 167 lOMoARcPSD|27223832 168 12: B u d g e t p re p arat i o n A C C A MA 8 29,250 $ 2,990 × 9 100 92 = 3,250 hours are needed to allow for idle time. The cost at $9 an hour is $3,250. $1,010,400 The important thing here is to work out the number of units that need to be produced, 40,995 – 100 1,000 = 39,995 × 95 = 42,100 units at the cost of $24 a unit. 10 $102,848 $ 16,000 56,448 30,400 102,848 November cash sales (20%) October credit sales (80% ×60% × 98%) September credit sales (80% × 38%) 11 $473,000 In October the 80,000 units sold in November plus the increase in the November opening inventory was produced. 43,000 hours of labour at $11 an hour were paid for in October. 12 $240,000 In October the raw materials paid for were the ones used in September’s production, as raw materials are paid for in the month following purchase. September’s production relates to October’s sales with an adjustment for completed inventory. Therefore, 120,000 units were paid for. 13 41,700 $ 20% of sales value from May and 75% of sales value from June. 14 4,150 15 12,842 16 $120 Selling Price Cost Mark up 125% 100% 25% Downloaded by Hooria Noor (nhooria9@gmail.com) $600 $600 × 25/125 = $120 lOMoARcPSD|27223832 A C C A MA 12: B u d g e t p re p arat i o n Capital budgeting 17 Construction of an existing building Replacement of motor vehicles Refurbishment of Head Office Multi task question 1 MOONSTAR (a) $ Cash receipts Receipts from accounts receivable Cash sales Sale of non-current assets Cash payments Payments to suppliers Payments to employees Loan repayment and interest Cash movement Opening balance Closing balance 535,275 48,000 36,000 (437,802) (59,220) (100,000) 22,253 378,400 400,653 Receipts from accounts receivable Nov sales Dec sales $525,000 × 90% × 35% $685,000 × 90% × 60% $ 165,375 369,900 535,275 Cash sales = 10% × $480,000 = $48,000 Sale of non-current assets = 6 × $6,000 = $36,000 Payments to suppliers = December purchases + payment to supplier in January = $384,000 + ($366,000 × 15% × 98%) = $437,802 Payments to employees = Monthly salaries + Bonus = ($42,000 × 1.05) + ($42,000 × 12 × 0.03) = $59,220 Loan is repayment only. Interest is not paid in January. (b) Pay off some of the rest of the loan Offer more generous credit periods to customers Delaying payments to suppliers and minimising inventory levels are actions that would be taken if Moonstar faced a cash shortage. Downloaded by Hooria Noor (nhooria9@gmail.com) 169 lOMoARcPSD|27223832 170 13: Di s c o u n t e d c as h f l o w A C C A MA Chapter 13: Discounted cash flow Objective test questions 1 $12,868 Year 3 4 5 6 $ 4,000 4,000 4,000 4,000 Discount factor 5% 0.864 0.823 0.784 0.746 $ 3,456 3,292 3,136 2,984 12,868 An alternative method is to multiply the amount by the cumulative discount factor for years 1 to 6 minus the cumulative discount factor for year 2. 4,000 × (5.076 – 1.859) = $12,868 2 $8,464 6 monthly interest rate = 3.5% (7% × 6/12), applied for 10 six month periods $6,000 × 1.03510 = $8,463.59 3 300,000 $ 21,000 0.07 4 = $300,000 $1,285 Annual instalment × 𝐴𝐴𝐴𝐴1−5 @ 9% = $5,000 Annual instalment = $5000/ 𝐴𝐴𝐴𝐴1−5 @ 9% = $5,000 / 3.890 =$1,285.34 5 $48,137 $38,000 × (1.03)8 = $48,137 6 10,000 $ Let x = original investment x × (1.04)10 = $14,802 $14,802 x = (1.04)10 = $9,999.70 = $10,000 (to the nearest $100) Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 13: Di s c o u n t e d c a s h f l o w 7 $2,978 From cumulative present value tables, 5% for three years = 2.723 Present value of rental income = $800 × (1 + 2.723) = $800 × 3.723 = $2,978.40 = $2,978 (to the nearest $) 8 $4,432 Future value of investment = $3,000 × (1 + 𝑟𝑟)𝑛𝑛 where n is the number of six-monthly periods = 8 and r = interest rate = 5% Future value of investment = $3,000 × (1 + 0.05)8 = $4,432 (to the nearest $) 9 150,000 $ 9,000/0.06 = $150,000 10 $ 1994.33 Value of investment after four years = $2,000 × (1.06)4 = $2,524.95 Value of investment after six years = ($2,524.95 – $750) × (1.06)2 = $1,994.33 11 $ 4,785.65 Monthly interest rate = 9%/12 = 0.75% Value of investment = $4,000 × (1.0075)24 = $4,785.65 12 $ 10,982.29 Value of investment = $8,000 × (1.02)16 = $10,982.29 13 8.24 % Effective annual rate = (1.02)4 – 1 = 8.24% Downloaded by Hooria Noor (nhooria9@gmail.com) 171 lOMoARcPSD|27223832 172 13: Di s c o u n t e d c as h f l o w 14 A C C A MA 10.38 % APR = 1.0254 – 1 = 0.1038 APR = 10.38% 15 $ 17903 PV = $2,500 × 7.161 = $17,903 16 $ 15600 Annual repayment = Amount of loan/ Year 6 8% annuity factor = $72,000/4.623 = $15,574, $15,600 to the nearest $100 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 14: I n v e s t me n t a p p rai s a l Chapter 14: Investment appraisal Objective test questions Investment Appraisal 1 4,000 $ Year 0 1 2 3 Discount factor 10% 1.000 0.909 0.826 0.751 $ (100,000) 20,000 40,000 70,000 9 2 IRR = 5 + 24 24− −6 $ (100,000) 18,180 33,040 52,570 3,790 % (10 − 5) = 9% 3 Initial investment/Annual cash inflow 4 $3,750 As A is used regularly, the 500 kg will have to be replaced and an extra 200 kg purchased at $5 per kg. The relevant cost of A is thus $5 × 700 = $3,500 The relevant cost of B is the cost only of purchasing the 100 extra kg as the 300 kg currently in inventory are surplus and have no scrap value. The relevant cost of B is thus $2.50 × 100 = $250 5 It ignores the time value of money. The result by itself does not tell you whether to accept or reject a project. 25 6 months Discount factor 7% $ (120,000) 1.000 Discounted cash flow $ (120,000) 45,000 80,000 100,000 0.935 0.873 0.816 42,075 69,840 81,600 Year Cost Inflows 1 2 3 Cumulative $ (120,000) (77,925) (8,085) 73,515 Payback = 2 years + ((8,085/(8,085 + 73,515)) × 12) months = 2 years 1 month 7 A relevant cost is a future incremental cash flow. Downloaded by Hooria Noor (nhooria9@gmail.com) 173 lOMoARcPSD|27223832 174 14: I n v e s t me n t a p p rai s al 8 A C C A MA 12 $ million Year 0 2 3 4 5 6 7 9 Cash flow $m (360) 100 100 100 125 115 (18) Cost of investment Inflow Inflow Inflow Inflow Inflow Rectification work Discount factor 9% 1.000 0.842 0.772 0.708 0.650 0.596 0.547 Discounted cash flow $m (360.00) 84.20 77.20 70.80 81.25 68.54 (9.85) 12.14 Make Alpha and Beta, buy in Gamma. The absorbed fixed overheads are not relevant to the decision. The relevant cost of Alpha is $111, which is less than the buy in price of $145. The relevant cost of Beta is $143, which is less than the buy in price of $170. The relevant cost of Gamma is $155, which exceeds the buy in price of $150. 10 $575 Relevant cost of unskilled labour is zero as surplus hours exceed hours needed on job. Cost of skilled labour per hr = $875/35 = $25. Relevant cost relates to hrs not covered by surplus: 50 hrs – 30 hrs = 20 hrs. 50 hrs – 35 hrs = 15 hrs will be at overtime rate. Relevant cost = (5 hrs × $25) + (15 hrs × $25 × 120%) = $575 11 I II only Sunk costs have already been incurred so don’t affect the decision. Absorbed costs are not influenced by the decision. 12 8.5% Year 0 1 2 3 Discount factor 5% $ (150,000) 30,000 70,000 80,000 1.000 0.952 0.907 0.864 Discount factor 10% $ (150,000) 28,560 63,490 69,120 11,170 IRR = 5 + ((11,170/(11,170 + 4,830)) × (10 – 5)) = 8.5% Downloaded by Hooria Noor (nhooria9@gmail.com) 1.000 0.909 0.826 0.751 $ (150,000) 27,270 57,820 60,080 (4,830) lOMoARcPSD|27223832 A C C A MA 14: I n v e s t me n t a p p rai s a l 12.26 13 𝐼𝐼𝐼𝐼𝐼𝐼 = 10% + 14 3450 3450− −2657 % (14% − 10%) = 12.26% $17,100 Cash inflow ($) (120,000) 15,000 25,000 35,000 40,000 Year 0 1 2 3 4 15 Only Statement I 16 14% Discount factor 1.000 0.962 0.925 0.889 0.855 Net present value ($) (120,000) 14,430 23,125 31,115 34,200 (17,130) 1,200 IRR ≈ 10% + 1,200−(−400) × (15 – 10)% 1,200 = 10 + ( 1,600 × 5%) = (10 + 3.75)% = 13.75% = 14% (to the nearest whole percent) 17 2.5 Cash generated p.a. = profit + depreciation = 25,500 + 8,500 = 34,000 Payback = 85,000/34,000 = 2.5 years 18 Approximately 12% IRR must be between 6% and 14% since the NPV is positive at a 6% discount rate and negative at a 14% one. The NPV is closer to zero at a 14% discount rate so the best answer is that the IRR is closer to 14% than 6% (hence 12% is the most suitable answer). Downloaded by Hooria Noor (nhooria9@gmail.com) 175 lOMoARcPSD|27223832 176 14: I n v e s t me n t a p p rai s al A C C A MA Multi task questions 1 MAURICE LTD 40 (a) months The cumulative cash flows are as follows: $000 (690) (435) (120) 225 1 2 3 4 Payback period = 3 years + (120/120 + 225) × 12 = 3 years 4 months The calculations in the following table are used in (b) and (c). A 1 2 3 4 5 6 7 8 9 10 11 12 B Year 0 $000 Revenues Cost of investment Running costs Net cash flow Discount factor 5% Discount factor 10% Discounted cash flow 5% Discounted cash flow 10% Net present value at 5% Net present value at 10% C D E F 1 $000 450 2 $000 550 3 $000 650 4 $000 700 (240) 210 0.952 0.909 200 191 (295) 255 0.907 0.826 231 211 (335) 315 0.864 0.751 272 237 (355) 345 0.823 0.683 284 236 (900) (900) 1.000 1.000 (900) (900) 87 (25) 44 (b) months The cumulative discounted cash flows are as follows: $000 (700) (469) (197) 87 1 2 3 4 Payback period = 3 years + (197/197 + 87) × 12 = 3 years 8 months 8.9 (c) IRR = 5 + (d) 87 87− −25 = C6*C7 % (10 − 5) = 8.9% (e) Advantage? Yes No It considers the time value of money. It considers cash flows over the whole life of a project. The answer provides a clear decision rule. It uses relevant cash flows. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 14: I n v e s t me n t a p p rai s a l 2 EDRICH LIMITED (a) $ 95,000 2,000 0 0 60,000 5,000 Costs of conversion Light and heat Year 1 Depreciation Year 1 Notional rent Year 1 Staff salaries Year 1 Staff relocation costs The $5,000 of customer research is a sunk cost and is not included. The increase in expenditure in light and heat is the relevant cost. Depreciation and notional rent are not cash flows, so are not included. Only the salaries of newly-recruited staff are relevant here. Staff relocation costs are relevant costs. (b) 646 $ 000 Calculation is as follows New outlet Old outlet Incremental sales Discount factor Discounted cash flows Net present value $ 800 600 200 0.909 181.8 645.9 $ 920 660 260 0.826 214.8 $ 1,058 726 332 0.751 249.3 (c) Advantage compared with IRR? Yes No It is only possible to have a single NPV figure, but it is possible to have more than one IRR. It considers cash flows over the whole life of a project. The answer provides a clear decision rule. It requires a cost of capital to be estimated. The IRR method also considers cash flows over the whole life of a project. The need to estimate a cost of capital is a difficulty with the NPV method, not an advantage. Downloaded by Hooria Noor (nhooria9@gmail.com) 177 lOMoARcPSD|27223832 178 15: M at e ri al a nd l a b o u r v a ri a n c es A C C A MA Chapter 15: Material and labour variances Objective test questions Standard costing systems 1 Definition Cost standard This standard assumes that current efficiency and cost levels will be maintained A current standard This standard assumes that nothing has changed since the standard was first set A basic standard This standard assumes an optimum level of efficiency and cost and minimisation of waste An ideal standard This standard assumes that there will be some improvements in current efficiency and cost levels 2 An attainable standard $1.88 Flour required 750g × 100/80 = 937.5g. 937.5g costs $1.88 3 $112.94 Labour needed 12 × 100/85 = 14.118 hours 4 $37,500 Wages paid are based on the total number of standard hours in the level of output produced. Standard hours are 3,750 (12 × 100 + 15 × 50 + 20 × 90) 5 A standard cost is the planned unit cost of a product A standard hour is an hour during which the labour force is paid at its normal rate of pay True False A standard hour is the quantity of work achievable in an hour if the workforce is working at standard efficiency levels. 6 Past experience Detailed product specifications Discussions with experts in each department Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 15: M a t e ri a l a nd l a b o u r v a ri a n c es 7 1,400 $ 8 A technique that reports variances by comparing actual costs to predetermined standards 9 Relevant standard Variance calculations Material variances 10 $4,000 favourable 1,200 units should have cost $30,000. They actually cost $26,000 so there is an overall favourable material cost variance of $4,000. 11 $500 adverse The budgeted cost of the 5,100 kg of material purchased was $25,500. The actual cost was $26,000 so there was a $500 adverse variance. 12 $4,500 favourable It was budgeted that 1,200 units would need 6,000 kg of material. In fact only 5,100 kg were used leading to a favourable variance of $4,500. 13 Material price Material usage $200 adverse $28 favourable $200 adverse $28 adverse $228 adverse $36 adverse $228 adverse $36 favourable 500 kg of material should have cost $700 but did cost $900, so there is a $200 adverse material price variance. 600 units should have used 480 kg of material but did use 500kg. Thus at the standard cost there is a $28 adverse material usage variance. 14 $10 Price variance ($2,000) = standard cost – actual cost ($38,000). Standard cost = $40,000. The standard cost per kg purchased is $10 per litre. Downloaded by Hooria Noor (nhooria9@gmail.com) 179 lOMoARcPSD|27223832 180 15: M at e ri al a nd l a b o u r v a ri a n c es 15 A C C A MA $10,700 adverse 9,750 units should have cost $339,300 but actually cost $350,000. There is an adverse variance of $10,700. 16 700 $ favourable 1,050kg should have cost $10,500 but actually cost $9,800 so there is a $700 favourable variance 17 500 $ adverse 500 units should have used 1,000 kg of direct materials. 50 additional kg used at the standard cost of $10 per kg give a $500 adverse material quantity variance. 18 200 $ favourable 500 units should have cost $10,000. They actually cost $9,800 so there is a $200 favourable total material variance. 19 15,000 kg The standard cost of 12,000 kg was $24,000. This is $6,000 favourable so the expected cost was $30,000 which would have been 15,000 kg at the standard price. 20 $1,000 favourable The materials in 4,900 units should have cost $147,000. They actually cost $146,000, so there is a favourable variance of $1,000. 21 $1,500 favourable 29,500 kg should have cost $147,500. They actually cost $146,000 so there is a $1,500 favourable variance. 22 $500 adverse 4,900 units should have used 29,400 kg of material. Actual usage was 29,500 so there was a 100kg overuse at $5 per kg. This gives a $500 adverse variance. 23 $10,800 favourable 54,000 labour hours should cost $550,800. Actual cost was $540,000 so there is a $10,800 favourable variance. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 15: M a t e ri a l a nd l a b o u r v a ri a n c es 24 4 hours Labour efficiency variance (3,000) = Std labour rate (10) × Excess hrs spent on 900 units Excess hours = 300. Actual hours worked were $39,000/$10 per hour = 3,900 hours so the budgeted hours were 3,900 – 300 = 3,600 or 4 hours a unit (3,600/900 = 4). 25 15,500 The favourable labour efficiency variance means that less hours were worked than standard. Labour efficiency variance ( 4,250) = Standard labour rate ( 8.50) × Hours underspent Hours underspent = 500, so the standard hours were 15,500 26 4 The labour efficiency variance is adverse so more hours than expected were worked. Labour efficiency variance (40,000) = Standard labour rate (10) × Hours overspent Hours overspent = 4,000. This means the standard hours for 10,000 units was 40,000 or 4 hours a unit. 27 $12,500 favourable The standard cost of producing 20,000 units is $412,500. As the actual cost was $400,000 there is a $12,500 overall labour cost variance. 28 $25,000 adverse The standard cost of 50,000 hours is $375,000. As $400,000 was spent there is an adverse labour rate variance of $25,000. 29 $37,500 favourable The standard number of hours in 20,000 units is 55,000. 5,000 less hours than standard were worked which, at the standard rate, means there is a favourable labour rate variance of $37,500. 30 $ 4,800 adverse The budgeted labour hours in 11,600 units are 34,800. 400 excess hours were worked. At the standard rate of $12 an hour this gives an adverse labour efficiency variance of $4,800. Downloaded by Hooria Noor (nhooria9@gmail.com) 181 lOMoARcPSD|27223832 182 15: M at e ri al a nd l a b o u r v a ri a n c es A C C A MA 31 68,400 $ favourable The budgeted cost of 35,200 labour hours is $422,400. The actual cost was $354,000, so there is a favourable labour rate variance of $68,400. 32 63,600 $ favourable The budgeted cost of 11,600 units was $417,600. When compared to the actual cost of $354,000 this gives a favourable overall labour cost variance of $63,600. 33 1,180 Material usage variance @ actual production = (should use – did use) @ standard cost per litre $2,200 = (production × 10 litres – 11,000 litres) × $2.75 $2,200/$2.75 = 800 = Production × 10 litres – 11,000 litres Production = (11,000 + 800)/10.0 = 1,180 units 34 1,512.50 adv Price variance @ actual purchases = should cost – did cost = 11,000 × $2.75 – 11,000 x $2.75 × 1.05 = $1,512.50 Adverse 35 34,786 kg Standard cost per KG = Standard cost / Units = $258,750/34,500kg = $7.50 per kg At Actual production, materials usage variance = (Should use – Did use) at Standard cost per kg. So, $2,145 Fav = (Should use – 34,500) × $7.50 $2,145/$7.50 = 286 = Should use – 34,500, therefore Should use = 34,500 + 286 = 34,786 kg. 36 7.4% adverse Labour total variance = Flexed budget at Standard cost – Actual cost Labour total variance= 29,500 units × $17.50 ─ $554,250 = $(38,000) Adverse Variance as % of flexed budget = $38,000/$516,250 = 7.36% Adverse Causes of variances 37 II and III Lower production than usual does not affect the materials usage variance as the usage variance Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 15: M a t e ri a l a nd l a b o u r v a ri a n c es 38 I and III 39 A sudden shortage of materials worldwide led to suppliers increasing their prices. 40 A discount offered by a materials supplier A reduction in quality control checking standards – no, expect a favourable usage variance Using a higher quality of materials than specified in the standard - no, expect a favourable usage variance Achieving a lower output volume than budgeted – no, the budget is flexed so no variance if as standard A discount offered by a materials supplier – Yes, this represents a price decrease not reflected in the standard cost so will show a favourable price variance Downloaded by Hooria Noor (nhooria9@gmail.com) 183 lOMoARcPSD|27223832 184 16: O t h e r v a ri an c e s A C C A MA Chapter 16: Other variances Objective test questions Variance calculations Variable overhead variances 1 $100 Adverse Favourable The variable overhead associated with 1,000 units was budgeted to be $6,000. As the overhead was actually $6,100 there was a $100 adverse variance. 2 $100 Adverse Favourable The variable overhead was budgeted to cost $1 an hour, so $6,200 in total. It actually cost $6,100 so there is a $100 favourable variance. 3 $200 Adverse Favourable The budgeted labour hours in 1,000 units were 6,000. 6,200 hours were worked. At the standard rate of $1 an hour this means that there was a $200 adverse efficiency variance. 4 $5,000 Adverse Favourable The standard variable production overhead in 2,000 units was $20,000. The actual overhead was $15,000 so there was a $5,000 favourable variance. 5 $3,000 Adverse Favourable The 3,600 hours worked had a standard cost of $18,000. Actual cost was $15,000, so there was a $3,000 favourable expenditure variance. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 16: O t h e r v a ri an c e s 6 $2,000 Adverse Favourable 4,000 hours were expected to be worked in 2,000 units but only 3,600 hours were worked. The 400 hours at the standard rate of $5 an hour gives a $2,000 favourable variable overhead efficiency variance. 7 $12 The $400 favourable overhead expenditure variance tells us that the expected cost associated with 500 labour hours was $6,000 or $12 per hour. 8 $265,000 Adverse Favourable Total variance = Actual units @ standard cost per unit – Actual costs Total variance = (220,000 × $4 × 3) – $2,375,000 = $265,000 favourable 9 $25,000 Adverse Favourable Expenditure variance = Budgeted cost – Actual cost Expenditure variance = (200,000 × $4 × 3) – S2,375,000 = $25,000 favourable 10 $240,000 Adverse Favourable Volume variance = (Actual production – Budgeted production) at standard cost Volume variance = (220,000 – 200,000) × $4 × 3 = $240,000 favourable 11 $180,000 Adverse Favourable Capacity variance = (Actual time – Budgeted time) × Standard cost per hour Capacity variance = (645,000 – (200,000 × 3)) × $4 = $180,000 favourable Downloaded by Hooria Noor (nhooria9@gmail.com) 185 lOMoARcPSD|27223832 186 16: O t h e r v a ri an c e s A C C A MA 12 $60,000 Adverse Favourable Efficiency variance = (Time production should take – Actual time) × Standard cost per hour Efficiency variance = ((220,000 × 3) – 645,000) × $4 = $60,000 favourable 13 $355,000 Adverse Favourable Total variance = Actual units @ standard cost per unit – Actual costs Standard cost per unit = 7,000,000/(500,000 × 2) = $7 Total variance = (520,000 × $7 × 2) – $6,925,000 = $355,000 favourable 14 $75,000 Adverse Favourable Expenditure variance = Budgeted cost – Actual cost Expenditure variance = $7,000,000 – $6,925,000 = $75,000 favourable 15 $280,000 Adverse Favourable Volume variance = (Actual production – Budgeted production) at standard cost Volume variance = (520,000 – 500,000) × $7 × 2 = $280,000 favourable 16 $385,000 Adverse Favourable Capacity variance = (Actual usage – Budgeted usage) × Standard cost per kg Capacity variance = (1,055,000 – (500,000 × 2)) × $7 = $385,000 favourable 17 $105,000 Adverse Favourable Efficiency variance = (Materials production should use – Actual usage) × Standard cost per kg Efficiency variance = ((520,000 × 2) – 1,055,000) × $7 = $105,000 adverse Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 16: O t h e r v a ri an c e s Sales variances 18 $80 adverse The sales price variance is the difference between what 4,620 units were sold for ( $41,500) and what they were expected to be sold for (4,620 × $9 = $41,580). 19 $90 favourable 20 more meals than budgeted were sold leading to a favourable variance. 20 meals at the standard contribution of $4.50 a meal gives a $90 variance. 20 $10,000 favourable 20,100 units should have sold for $502,500 but were actually sold for $512,500, so there is a $10,000 favourable sales price variance. 21 $1,000 favourable 100 more units were sold than planned. 100 units at the standard contribution of $10 per unit gives a $1,000 favourable sales volume contribution variance. 22 10 $ per unit An adverse sales price variance of $2,000 indicates that the standard selling price of the 9,800 units was $98,000 ($96,000 + $2,000) or $10 per unit. 23 $36,000 favourable The sales price variance is the difference between the budgeted and actual selling price of the units sold. 24 $60,000 adverse The sales volume contribution variance is the difference between the budgeted and actual sales at the standard contribution of $30. 25 $ 1020 Standard profit per unit = $16 – $5.20 – $2.80 – $1.20 – $1.70 = $5.10 Variance = (9,200 – 9,000) × $5.10 = $1,020 favourable Downloaded by Hooria Noor (nhooria9@gmail.com) 187 lOMoARcPSD|27223832 188 16: O t h e r v a ri an c e s A C C A MA Causes of variances 26 An adverse labour efficiency variance An adverse variable overhead efficiency variance 27 A favourable variable overhead efficiency variance A favourable material usage variance A favourable sales volume variance Multi task question 1 CUDDLYDUD (a) 6300 $ Favourable Sales volume variance = (Actual sales – Budgeted sales) × Contribution per unit = (15,100 – 15,000) × ($155 – 36 – 48 – 8) = $6,300 Favourable (b) 3600 $ Favourable Expenditure variance = Budgeted expenditure – Actual expenditure = (15,000 × $7 × 2) – $206,400 = $3,600 Favourable (c) $ 3600 Favourable 2100 Adverse It’s the same as for marginal costing. (d) $ Capacity variance = (Actual hours – Budgeted hours) × Absorption rate = (29,700 – (15,000 × 2)) × $7 = $2,100 Adverse (e) 3500 $ Favourable Efficiency variance = (Expected hours for actual production – Actual hours) × Absorption rate = ((15,100 × 2) – 29,700) × $7 = $3,500 Favourable (f) 4200 $ Difference = Change in inventory levels × Overheads absorbed per unit = 300 × $7 × 2 = $4,200. Value of closing inventory under absorption costing will be higher and therefore profit will be greater. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 17: V a ri an c e re v i e w and c o n t ro l Chapter 17: Variance review and control Objective test questions Reconciliation of budgeted and actual profit 1 44,300 $ Cost control and reduction 2 3 It takes into account a required standard of quality. It seeks the lowest cost method of achieving a desired end. Marketing value The four elements of value are, cost, exchange, esteem and use. Multi task questions 1 HENRY (a) Marginal (b) 500 more than budgeted Variance is positive, so units sold were more budgeted. Extra number sold = Variance/Contribution per unit = 21,000/42 = 500 units (c) Lower (d) $3,070,900 Expected sales revenue = Flexed contribution × Selling price/Contribution per unit = $861,000 × (150/42) = $3,075,000 Alternatively: 20,500 units actually sold. Budgeted units 840,000/42=20,000, plus 500 extra calculated part (b). Expected revenue 20,500 × 150=3,075,000 Actual sales revenue = Expected revenue – Adverse variance = $3,075,000 – $4,100 = $3,070,900 (e) Labour efficiency and Variable overhead efficiency (f) 800 Hours saved = Variance/Standard cost per hour = 11,200/$14 = 800 hours (g) Favourable Downloaded by Hooria Noor (nhooria9@gmail.com) 189 lOMoARcPSD|27223832 190 17: V ari an c e re v i e w and c o n t ro l A C C A MA 2 EDTED (a) Absorption (b) 600 more than budgeted Variance is positive, so units sold were more budgeted. Extra number sold = Variance/Profit per unit = 34,200/57 = 600 units (c) More (d) 59,930 Variance = (Quantity used (Q) × Standard price) – (Budgeted Quantity for Actual production × Standard price) 13,770 = 9Q – (14,600 × 4 × $9) 9Q = 539,370 Q = 59,930 (e) $0.300 less Hours worked = Standard hours produced – (Efficiency variance/Standard cost per hour) = (14,600 × 3) – (11,680/16) = 43,070 Labour cost = (43,070 × $16) – 12,921 = $676,199 Cost per hour = $676,199/43,070 = $15.70, $0.300 less than the budgeted cost per hour Alternatively: 12,921/43,070 = 0.3 less as 12,921 was a favourable variance. (f) $348,140 Actual expenditure = Budgeted expenditure + Adverse expenditure variance Budgeted quantity to be produced = Budgeted profit/Profit per unit = 798,000/57 = 14,000 Budgeted expenditure = (3 × $8 × 14,000) = $336,000 Actual expenditure = $336,000 + $12,140 = $348,140 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 17: V a ri an c e re v i e w and c o n t ro l 3 WAKEUUP (a) Standard cost operating statement Budgeted contribution Sales volume variance Flexed contribution Sales price variance Cost variances Material price Material usage Labour rate Labour efficiency Variable overhead expenditure Variable overhead efficiency Total cost variances $ 1,371,600 (27,000) 1,344,600 12,450 Favourable $ 4,530 Adverse $ 9,600 5,105 28,125 16,500 21,030 12,500 55,330 (34,300) Budgeted fixed overhead Fixed overhead expenditure variance 160,000 4,000 (164,000) 1,158,750 Actual profit Material price = Standard cost of purchases – Actual costs = (30,200 × $30) – $901,470 = $4,530 Favourable Material usage = (Standard usage in production – Actual usage) × Standard cost = ((24,900 × 1.2) – 30,200) × $30 = $9,600 Adverse Labour rate = Standard cost of hours taken – Actual costs = (51,050 × $22.50) – $1,153,730 = $5,105 Adverse Labour efficiency = (Standard time for production – Actual time) × Standard cost = ((24,900 × 2) – 51,050) × $22.50 = $28,125 Adverse Variable overhead expenditure = Standard costs of production – Actual costs = (51,050 × $10) – $494,000 = $16,500 Favourable Variable overhead efficiency = (Standard time for production – Actual time) × Standard cost = ((24,900 × 2) – 51,050) × $10 = $12,500 Adverse Fixed overhead expenditure = Budgeted expenditure – Actual expenditure = $160,000 – $164,000 = $4,000 Adverse (b) Stricter quality control procedures resulting in a lower volume of good output Under-estimation when budgeting of the time taken to produce individual units Downloaded by Hooria Noor (nhooria9@gmail.com) 191 lOMoARcPSD|27223832 192 17: V ari an c e re v i e w and c o n t ro l A C C A MA 4 HARVEYHEDGE (a) 378800 $ Quantity sold = Expected quantity + Sales volume variance/Profit per unit = 1,750 + ($9,900/66) = 1,900 units Sales revenue = Quantity sold at standard price – Sales price variance = (1,900 × $200) – $1,200 = $378,800 12450 (b) kg Material usage variance = (Expected usage – Actual usage) × Standard price – 5,250 = ((1,950 × 6) – Actual usage) × $7 7 × Actual usage = 81,900 + 5,250 Actual usage = 12,450 kg (c) $ 86680 Labour costs = Standard costs for hours worked – Labour rate variance = (4,060 × 22) – $2,640 = $86,680 (d) $ 32,760 Actual cost = Expected cost – Total variance = (1,950 × $18) – $2,340 = $32,760 (e) $ 59850 Actual cost = Expected cost – Total variance = (1,950 × $30) – – $1,350 = $59,850 (f) Expected output for a worker week compared with the actual output Expected labour time for actual output produced compared with actual labour time The comparison of actual output with actual labour time gives no indication about efficiency if how long labour was expected to take is not known. Comparison of actual quality with expected quality would be a measure of effectiveness. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 18: Fi n an c i al p e rf o rman c e me as u res Chapter 18: Financial performance measures Objective test questions Performance measurement overview 1 Strategy Values 2 Tactical Financial measures 3 25 % Return on capital employed = Profit before interest and tax/Total assets – Current liabilities × 100% = 7,000/(30,000 – 2,000) × 100% = 25% 4 36 % Gross profit margin = Gross Profit/Revenue × 100% = 9,000/25,000 × 100% = 36% 5 28 % Net profit margin = Profit before interest and tax/Revenue × 100% = 7,000/25,000 × 100% = 28% 6 0.89 Asset turnover = Revenue/Total assets less current liabilities = 25,000/28,000 = 0.89 Downloaded by Hooria Noor (nhooria9@gmail.com) 193 lOMoARcPSD|27223832 194 18: Fi n an c i al p e rf o rman c e me as u res A C C A MA 7 5 Current ratio = Current assets/Current liabilities = 6,000 + 3,000 + 1,000/1,500 + 500 =5 8 2 Quick ratio = Current assets excluding inventory /Current liabilities = 3,000 + 1,000/1,500 + 500 =2 9 2.67 Inventory turnover = Cost of sales/Inventory = 16,000/6,000 = 2.67 10 137 days Inventory days = Inventory/Cost of sales × 365 days = 6,000/16,000 × 365 days = 137 days 11 44 days Receivables collection period = Trade receivables/Revenue × 365 days = 3,000/25,000 × 365 days = 44 days 12 34 days Payables payment period = Trade payables/Cost of sales × 365 days = 1,500/16,000 × 365 days = 34 days Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 18: Fi n an c i al p e rf o rman c e me as u res 13 40 % Debt to equity ratio = Long-term debt/Equity × 100% = 8,000/20,000 × 100% = 40% 14 28.6 % Gearing = Long-term debt/Equity + Long-term debt × 100% = 8,000/(20,000 + 8,000) × 100% = 28.6% 15 14 Interest cover = Profit before interest and tax/Finance cost = 7,000/500 = 14 16 21.4 % Return on capital employed = Profit before interest and tax/Total assets – Current liabilities × 100% = 12,000/(62,000 – 6,000) × 100% = 21.4% 17 37.5 % Gross profit margin = Gross Profit/Revenue × 100% = 15,000/40,000 × 100% = 37.5% 18 30 % Net profit margin = Profit before interest and tax/Revenue × 100% = 12,000/40,000 = 30% Downloaded by Hooria Noor (nhooria9@gmail.com) 195 lOMoARcPSD|27223832 196 18: Fi n an c i al p e rf o rman c e me as u res A C C A MA 19 0.71 Asset turnover = Revenue/Total assets less current liabilities = 40,000/62,000 – 6,000 = 0.71 20 2 Current ratio = Current assets/Current liabilities = 3,000 + 6,000 + 3,000/5,000 + 1,000 =2 21 1.5 Quick ratio = Current assets excluding inventory /Current liabilities = 6,000 + 3,000/5,000 + 1,000 = 1.5 22 8.33 Inventory turnover = Cost of sales/Inventory = 25,000/3,000 = 8.33 23 44 days Inventory days = Inventory/Cost of sales × 365 days = 3,000/25,000 × 365 days = 44 days 24 55 days Receivables collection period = Trade receivables/Revenue × 365 days = 6,000/40,000 × 365 days = 55 days Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 18: Fi n an c i al p e rf o rman c e me as u res 25 73 days Payables payment period = Trade payables/Cost of sales × 365 days = 5,000/25,000 × 365 days = 73 days 26 40 % Debt to equity ratio = Long-term debt/Equity × 100% = 16,000/40,000 × 100% = 40% 27 28.6 % Gearing = Long-term debt/Equity + Long-term debt × 100% = 16,000/(40,000 + 16,000) × 100% = 28.6% 28 6 Interest cover = Profit before interest and tax/Finance cost = 12,000/2,000 =6 29 30 $ The remuneration of senior management 18,000 (RI + (600,000 × 12%))/600,000 = 0.15 RI + (600,000 × 12%) = 90,000 RI = $18,000 Downloaded by Hooria Noor (nhooria9@gmail.com) 197 lOMoARcPSD|27223832 198 18: Fi n an c i al p e rf o rman c e me as u res A C C A MA Multi task questions 1 OLDTED 6.8 (a) % Change in gross profit = ((6,790 – 6,360)/6,360) × 100% = 6.8% 10.8 (b) % Return on capital employed = PBIT/TALCL = (3,590/(42,090 – 8,730)) × 100% = 10.8% 10.1 (c) % Return on capital employed = (3,210/(39,910 – 7,780)) × 100% = 10.0% 0.97 (d) Asset turnover = Revenue/TALCL = (32,200/(42,090 – 8,730)) = 0.97 1.01 (e) Asset turnover = (29,220/(39,910 – 7,780)) = 0.91 2.23 (f) Inventory turnover = Cost of sales/Inventory = 25,410/11,410 = 2.23 11 (g) days Inventory days = (Inventory/Cost of sales) × 365 This year = (11,410/25,410) × 365 = 163.9 days Last year = (9,580/22,860) × 365 = 153.0 days (h) Use of the Economic Order Quantity model Taking advantage of supplier discounts may reduce the total costs associated with holding and ordering inventory, but these costs combined will be at their lowest at the Economic Order Quantity 2 LOXWOOD FOODS 20.0 (a) % Return on investment = Profit/investment × 100% = (1.5/(6.5 + 1)) × 100% = 20% 19.9 (b) % Return on investment = ((1.5 + 0.45)/(6.5 + 1 + 1.5 + 0.8)) × 100% = 19.9% (c) $ 0.825 m Residual income = Profit – (Investment × Cost of capital) = 1.5 – (0.09 × (6.5 + 1)) = $0.825m (d) $ 1.068 m Residual income = 1.5 + 0.45 – (0.09 × (6.5 + 1 + 1.5 + 0.8)) = $1.068m Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 18: Fi n an c i al p e rf o rman c e me as u res (e) RI could increase every year because assets are getting older, even though profits may remain static or fall. RI cannot easily be used to compare the performance of divisions of different sizes. If assets get older, their value will fall as they are depreciated and this may outweigh falls in profit. There is no need for companies to use the same cost of capital for every division. Different divisions may have different cost depending on their risk profile. If profit exceeds the imputed interest charge, this will indicate to managers that they should undertake the investment. (f) Target costing Downloaded by Hooria Noor (nhooria9@gmail.com) 199 lOMoARcPSD|27223832 200 19: N o n - fi n an c i al p e rf o rman c e me as u re s a n d pe rf o rman c e re p o rt i n g A C C A MA Chapter 19: Non-financial performance measures and performance reporting Objective test questions Non-financial measures 1 I and II only Tutors and classrooms are major resources for a training business and so I and II would be appropriate measures of resource utilisation. Balanced scorecard 2 AI BIII CII DIV Activity, efficiency and capacity ratios 3 105.0 % Activity ratio = (Standard hours produced/Budgeted hours) × 100% Activity ratio = (105,000 × 3/300,000) × 100% = 105.0% 4 110.5 % Efficiency ratio = (Standard hours produced/Actual hours worked) × 100% Efficiency ratio = (105,000 × 3/285,000) × 100% = 110.5% 5 95 % Capacity ratio = (Actual hours worked/Budgeted hours) × 100% Capacity ratio = (285,000/300,000) × 100% = 95% Process and job performance measurement 6 Idle time Productivity Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 19: N o n - fi n an c i al p e rf o rman c e me as u re s a n d pe rf o rman c e re p o rt i n g Non-profit seeking and public sector organisations 7 Effectiveness Manufacturing and service businesses 8 Net profit margin Number of returning customers Staff turnover Benchmarking 9 Internal Performance reports 10 CO2 emissions Multi task questions 1 FUZZY LIMITED 6.88 (a) % ROI = Divisional profit/Divisional investment × 100% = (5,500/80,000) × 100% = 6.88% (b) $ –2500000 RI = Divisional profit – Notional interest = $5,500,000 – ($80,000,000 × 10%) = – $2,500,000 (c) 24.44 % Turnover = Number of staff leaving in period/Average number of staff employed × 100% = (11/45) × 100% = 24.44% (d) 100.40 % Efficiency ratio = Standard hours produced/Actual hours worked × 100% = (49,700/49,500) × 100% = 100.40% (e) 99.00 % Capacity ratio = Actual hours worked/Budgeted hours = (49,500/50,000) × 100% = 99.00% (f) 99.40 % Activity ratio = Standard hours produced/Budgeted hours = (49,700/50,000) × 100% = 99.40% Downloaded by Hooria Noor (nhooria9@gmail.com) 201 lOMoARcPSD|27223832 202 19: N o n - fi n an c i al p e rf o rman c e me as u re s a n d pe rf o rman c e re p o rt i n g A C C A MA (g) (h) Yes No Divisional managers have to consider the costs of financing their divisions. Divisional managers avoid dysfunctional decision-making. It is directly related to net present value. It means that managers will select projects with positive net present values. It relates size of income to size of investment. It is an absolute measure of performance. It helps in comparing the performance of managers who control divisions of different sizes. It is easily understood by managers. The rate of staff turnover was higher than budgeted. Errors were made when allocating time to jobs during planning. A greater number of new, inexperienced, staff than expected is likely to lead to more errors and lower productivity. Errors in allocation could explain both an adverse and a favourable variance. If idle time was taken into account when planning, it shouldn’t affect efficiency calculations. An increase in wage rates should account for an adverse labour rate variance but (hopefully) have a favourable impact on labour efficiency. 2 BROADBRIDGE CLINICS LTD 16 (a) % Return on capital employed = (Operating profit/TALCL) × 100% = ($1,356,000/($8,765,000 – $420,000)) × 100% = 16% 34 (b) % Net profit percentage = (Operating profit/Revenue) × 100% = ($1,356,000/$3,940,000) × 100% = 34% (c) $ 54 Operating profit per patient night = Operating profit/Number of patients × Average stay = $1,356,000/(1,250 × 20) = $54.24 76 (d) % Occupancy = (No of patients × Average stay)/(Average no of rooms × 365) × 100% = (1,250 × 20)/(90 × 365) × 100% = 76% (e) $ 79000 Revenue per member of medical staff = $3,940,000/(12 + 38) = $78,800 (f) $ 19000 Operating profit per employee = $1,356,000/(12 + 38 + 7 + 15) = $18,833 Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 A C C A MA 19: N o n - fi n an c i al p e rf o rman c e me as u re s a n d pe rf o rman c e re p o rt i n g (g) Speed of delivery of care to patients Care plans tailored to individual patients Number of available beds is not itself an indication of flexibility if beds are available but there are no patients to fill them. 3 SYDNEY DARWIN LIMITED 1.5 (a) Interest cover = PBIT/Finance cost = 1,200/800 = 1.5 30 (b) % Gearing = (Long-term debt/Equity + Long-term debt) × 100% = (8,100/8,100 + 18,800) × 100% = 30% 1.16 (c) Current ratio = Current assets/Current liabilities = 5,750/4,950 = 1.16 0.47 (d) Quick ratio = Current assets excluding inventory/Current liabilities = (5,750 – 3,410)/4,950 = 0.47 (e) Interest cover (f) Quick ratio The quick ratio shows the company’s ability to realise its more liquid assets (that is, excluding inventory, which may be difficult to sell). (g) Business process re-engineering Downloaded by Hooria Noor (nhooria9@gmail.com) 203 lOMoARcPSD|27223832 204 19: N o n - fi n an c i al p e rf o rman c e me as u re s a n d pe rf o rman c e re p o rt i n g Downloaded by Hooria Noor (nhooria9@gmail.com) A C C A MA lOMoARcPSD|27223832 205 ACCA Practice Examination Management Accounting (MA) Time allowed: 2 hours Section A – ALL 35 questions are compulsory and MUST be attempted Section B – ALL THREE questions are compulsory and MUST be attempted Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 206 P rac t i c e e xami n at i on q u es t i o n s A C C A MA Q ue s t ion Ba nk Section A 1 2 Are the following statements relating to management accounts TRUE or FALSE? True False Accuracy is more important than timeliness They are prepared primarily for internal rather than external stakeholders Which quality of information can be defined as the omission of information that is not needed for a decision? 3 A sample is taken by first dividing the population into different ethnic groups and then sampling randomly within each group. What is this sampling method called? 4 5 Random Block Cluster Multi-stage Are the following statements relating to inventory valuation TRUE or FALSE? True False Inventory is valued by including both production and nonproduction costs The LIFO method of inventory valuation assumes that the oldest items in inventory will be sold last A factory employee is paid a fixed salary of $15,000 per annum, plus an overtime rate of $20 per hour for each hour above 40 worked per week. What type of cost is the factory employee’s salary? 6 Relevant Understandable Authoritative Easy to use A fixed cost A variable cost A semi variable cost A step cost Which section of a report is most likely to contain a detailed list of the information sources used? Contents Terms of reference Recommendations Appendices Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 P rac t i c e e xami n at i on q u es t i o n s A C C A MA Q ue s t ion Ba nk 7 The following pie chart shows what students taking the MA exam planned to do on their holidays after they had taken the exam. Holiday activity Skiing Sightseeing Walking Sunbathing Are the following statements about the pie chart TRUE or FALSE? The % of students going on active holidays (defined as Skiing and Walking) is greater than the % of students taking other types of holidays The % of students going on a Sightseeing holiday is greater than 25% 8 False Within the time series model, longer term fluctuations caused by such factors as economic activity are known as a: 9 True Cyclical variation Random variation Seasonal variation Trend Using a multiplicative time series model, a business has identified the following seasonal variations in the quarterly demand for its product: Q1 300 -25% Demand (units) Seasonal variation Q2 500 +40% The seasonal variation for Q4 is: Not possible to determine +30% 0% -30% Downloaded by Hooria Noor (nhooria9@gmail.com) Q3 140 +15% Q4 650 ? 207 lOMoARcPSD|27223832 208 P rac t i c e e xami n at i on q u es t i o n s 10 A C C A MA Q ue s t ion Ba nk A construction company is bidding for three property development contracts, which are awarded independently of each other. The board estimates it has a 45% chance of winning Contract A, 20% chance of winning Contract B, and 35% chance of winning Contract C. The profits from A, B and C are estimated to be $500,000, $550,000 and $575,000 respectively. The expected value to the company of the profits from all three contracts will be closest to 11 $500,000 $525,000 $536,250 $542,000 The number of holidays undertaken by a group of eight friends in one year was as follows: 1 3 2 0 3 2 4 1 The standard deviation of the number of holidays undertaken, correct to 2 decimal places, is : 12 The annual demand for a product is 30,000 units. The cost of placing an order is $160 and the annual cost of holding an item in inventory is $15.00. Calculate the Economic Order Quantity, to the nearest unit. units 13 Puppypup made the following purchases and sales of its most popular item, a large cuddly dog, in November. The value of opening inventory was $776,250. Date 1 7 9 14 23 28 Opening inventory Purchases Sales Purchases Sales Purchases Quantity 000 45 15 20 30 60 10 Cost/Revenue per unit $ 17.25 18.00 25.00 18.25 25.00 18.40 Calculate the value of closing inventory using the FIFO method. $ 14 Eleanor is a lawyer who normally works 40 hours a week. She is paid at the rate of S60 per hour with an overtime premium of 25% of all overtime hours worked. In the week commencing 7 May, Eleanor worked 53 hours. The hours worked included 2 hours idle time, 5 hours on one client to cover for a colleague who was off sick and 6 hours to complete a job by 9 May at another client’s request. What is the direct cost of Eleanor’s time in the week commencing 9 May? $ Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 P rac t i c e e xami n at i on q u es t i o n s A C C A MA Q ue s t ion Ba nk 15 A standard working day at Tigger Limited is 8 hours. The rate of pay is $16 per hour. The standard time allowed to produce one unit is 10 minutes and there is a premium at basic rate of salary of 25% of time saved. On one day an employee produces 60 units. What is his pay for the day? $ 16 Complete the blank in the following definition: A is a customer order or task of relatively short duration. Select an option from the drop down box: Process 17 Batch Job Contract 100,000 kg of materials were added to a process. The process has a normal loss of 5%. What is the expected output? kg 18 19 The input to a process costing system was 5,000 units. There was no opening or closing work in progress. Normal losses are 2% of input. In which of the following circumstances is there an abnormal gain? I II III Actual output = 5,000 units Actual output = 4,950 units Actual output = 4,800 units None of them I only II and III I and II Product X is manufactured in a single process. At the start of the last period there was no work in progress. During the period 600 kg of raw material costing $12,000 was input into the process and $9,000 was spent on conversion. 500 kg of X was transferred to finished goods. The normal process loss is 10% of input. The abnormal loss was 10kg. The closing work in progress was 100% complete with respect to materials and 50% complete with respect to conversion costs. The material equivalent units in closing work in progress were: units 20 Which of the following organisations would NOT normally use service costing? IT consultant Hospital Accountancy firm Large manufacturing company Downloaded by Hooria Noor (nhooria9@gmail.com) 209 lOMoARcPSD|27223832 210 P rac t i c e e xami n at i on q u es t i o n s 21 At what stage of the product life cycle should sales revenues increase and the product start to make a profit? 22 23 A C C A MA Q ue s t ion Ba nk Introduction Growth Maturity Decline Indicate whether the following statements about budgeting are TRUE or FALSE: True False A business must establish its long term objectives BEFORE it commences budgeting Better local knowledge is an advantage of bottom-up budgeting compared with top-down budgeting Fill in the blank in the following statement. A is a ‘detailed budget of estimated cash inflows and outflows incorporating both revenue and capital items’. Select an option from the drop down box: Master budget Flexible budget Cash budget Cash flow statement 24 25 A business wishes to increase its finished goods inventory by 10%. Indicate whether the following statements are TRUE or FALSE: True False The quantity of finished goods in the production budget is the budgeted sales quantity minus the opening inventory plus the increased closing inventory The quantity of finished goods in the production budget must also be higher by exactly 10% if the finished goods inventory increases by 10% Which of the following would not be included in a cash budget? Dividend paid to shareholders Tax paid to the taxation authorities Receipt on the sale of a motor vehicle Depreciation of computer equipment Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 P rac t i c e e xami n at i on q u es t i o n s A C C A MA Q ue s t ion Ba nk 26 Fill in the blank in the following definition. A is a ‘budget set prior to the control period and not subsequently changed in response to changes in activity, costs or revenue. It may serve as a benchmark in performance evaluation’. Select an option from the drop down box: Fixed budget 27 Master budget Rolling budget Incremental budget A business has produced the following flexed budget for the product that it manufactures: Level of activity Direct materials Direct labour Production overhead 50% $15,000 $33,750 $17,500 75% $22,500 $50,625 $18,750 90% $27,000 $60,750 $19,500 In a budget flexed at the 55% level of activity, the value of direct materials is: $ 28 How and where the company is going to compete is a definition of which element of a mission statement? 29 Which of the following indicators is a financial performance measurement? 30 Purposes Strategy Behavioural standards Values Cash flow Output per employee Number of complaints received Sales volume growth The following information is taken from the financial statements of FT Limited. Revenues Gross profit Profit before interest and tax Profit after taxation Capital employed 20X9 $000 60,000 37,500 24,000 9,600 240,000 Calculate the change in return on capital employed from 20X8 to 20X9. Increase from 24.0% to 25.0% Increase from 15.0% to 15.6% Increase from 9.5% to 10.0% No change; remains at 4% Downloaded by Hooria Noor (nhooria9@gmail.com) 20X8 S000 50,400 31,500 19,950 8,400 210,000 211 lOMoARcPSD|27223832 212 P rac t i c e e xami n at i on q u es t i o n s 31 Which of the following is an advantage of using annual profit as a performance indicator? 32 A C C A MA Q ue s t ion Ba nk It cannot easily be manipulated. It is easy to understand. It motivates directors to focus on the longer-term. It gives a good indication of market share. Henry has calculated that the profit for the division for which he has responsibility in 20X8 was $3,000,000. The costs he took into account when calculating the profit included $300,000 of centrally allocated Head Office costs. The division’s net assets at the start of 20X8 were $14,800,000 and were S15,200,000 at the end of 20X8. The Finance Director has estimated that the Cost of Capital for Henry’s division is 8%. Calculate the Residual Income for Henry. $ 33 Which TWO of the following are non-financial measures? 34 Which of the following is not an advantage of the balanced scorecard? 35 Number of new products introduced Increase in market share Fall in inventory levels Customer retention rate It emphasises the importance of customer value. It steers the business away from solely focusing on financial measures. It considers how the business is developing its markets by producing new products. It provides a means of reconciling short-term and long-term objectives. Which of the following groups make up the three Es in value for money analysis? Economy, Efficiency, Expenditure Economy, Expenditure, Effectiveness Efficiency, Expenditure, Effectiveness Economy, Efficiency, Effectiveness Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 P rac t i c e e xami n at i on q u es t i o n s A C C A MA Q ue s t ion Ba nk Section B 1 BRIAN Brian produces a product called a kitmonk, which includes 8 kg of raw materials costing $10 per kg. Forecast sales in the next calendar year are as follows: January February March April May June July August September October November December Units 2,000 1,800 1,900 2,200 2,400 2,500 2,100 1,700 2,200 2,600 2,800 3,000 Required: (a) Initially Brian has adopted a policy of closing inventory at the end of each month equalling 30% of expected sales in the following month. What, in units, is the opening inventory for February? units (b) At the start of April, opening inventory was 500 units, but Brian intends to return to its initial policy at the end of April. What, in units, is the budgeted level of production for April? units (c) (2 marks) Raw materials purchases in September are expected to be $185,600, in October $212,800 and in November $228,800. Brian pays for 60% of raw materials in the month of purchase and 40% one month later. What is the budgeted level of payment for raw materials in October? $ (e) (2 marks) Opening inventory of finished goods in July is expected to be 630 units and closing inventory is expected to be 510 units. Brian does not maintain inventory of raw materials. What is the budgeted amount of raw materials purchases in July? $ (d) (1 mark) (1 mark) Excess demand worldwide is expected to mean that Brian will only be able to purchase 20,000 kg of raw materials in December. Opening inventory of finished goods in December will be 900 units, but the target level of closing inventory is having to be relaxed because of the shortage of raw materials. What will be the expected level of closing inventory at the end of December? units Downloaded by Hooria Noor (nhooria9@gmail.com) (2 marks) 213 lOMoARcPSD|27223832 214 P rac t i c e e xami n at i on q u es t i o n s (f) A C C A MA Q ue s t ion Ba nk Because of the lower demand over the summer, Brian may face a short-term shortage of cash between June and August. Which of the following methods would it be appropriate for Brian to use to alleviate the short-term cash shortage? (2 marks) Use Not use Taking out a bank overdraft Taking out a five year bank loan Investing in short-term debt instruments Agreeing with suppliers to delay payment (10 marks) 2 CEDRIC Cedric is about to make an investment in facilities to produce a new product. The following details will be used to appraise the investment. 1 2 3 4 5 6 7 8 9 A Year B 0 $000 Revenues Cost of investment Running costs Net cash flow Discount factor 8% Discount factor 10% Discount factor 20% C 1 $000 900 D 2 $000 1,200 E 3 $000 1,340 F 4 $000 500 (330) 570 0.926 0.909 0.833 (550) 650 0.857 0.826 0.694 (620) 720 0.794 0.751 0.579 (240) 260 0.735 0.683 0.482 (1,500) (1,500) 1.000 1.000 1.000 Required: (a) Calculate the payback period for this investment to the nearest month. months (b) (2 marks) Calculate the discounted payback period for this investment to the nearest month, using a discount rate of 8%. months (c) (2 marks) Calculate the Internal Rate of Return (IRR) of this investment, using discount rates of 10% and 20%, to the nearest 0.1%. % (d) (2 marks) Which of the following list are advantages of the IRR method of investment appraisal? (2 marks) Advantage? Yes No It considers the time value of money It considers cash flows over the whole life of a project It considers the relative size of investments It considers relevant cash flows Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 P rac t i c e e xami n at i on q u es t i o n s A C C A MA Q ue s t ion Ba nk (e) Which of the following list are advantages of using a computer spreadsheet in an investment appraisal? (2 marks) Advantage? Yes No Spreadsheets can be used to do repetitive calculations quickly Spreadsheets automatically highlight incorrect data that has been input Spreadsheets make it easy to see the formulae used Spreadsheets allow what-if analysis to be performed quickly on the data in the appraisal (10 marks) 3 GRAHAM The standard cost card for Graham’s product, the Teded, is as follows: $ 250 50 64 16 32 88 Selling price Direct material 5 kg @ $10 per kg Direct labour 4 hrs @ $16 per hour Variable overhead 4 hrs @ $4 per hour Fixed overhead 4 hrs @ $8 per hour Profit The incomplete operating statement for the Teded is as follows: Profit reconciliation: $ Sales volume variance 13,200 Sales price variance (14,500) Cost variances Material price variance Material usage variance Labour rate variance Labour efficiency variance Variable overhead expenditure variance Variable overhead efficiency variance Fixed overhead expenditure variance Fixed overhead capacity variance Fixed overhead efficiency variance Favourable $ 7,500 Adverse $ 8,000 6,310 7,200 1,230 3,940 2,800 3,600 Actual profit The number of units budgeted to be produced and sold in the period was 7,800. The number of units actually produced was 8,000 and actual labour hours were 31,550. Downloaded by Hooria Noor (nhooria9@gmail.com) 215 lOMoARcPSD|27223832 216 P rac t i c e e xami n at i on q u es t i o n s A C C A MA Q ue s t ion Ba nk Required: (a) Is the following statement TRUE or FALSE? Graham is using marginal costing to account for the Teded (b) True False What is the flexed budgeted profit for the Teded? $ (c) (d) (e) (1 mark) How many units of the Teded were sold in the period? units (1 mark) units (1 mark) What was the actual material usage? What was the average labour rate per hour? $ (f) (1 mark) What was the variable overhead efficiency variance (no need to say whether favourable or adverse)? $ (g) (1 mark) What was the fixed overhead volume variance (no need to say whether favourable or adverse)? $ (h) (1 mark) What was the amount of overhead under/over-absorbed (no need to say whether under or over-absorbed)? $ (i) (1 mark) Which of the following might be an explanation for the favourable labour efficiency variance? (2 marks) Explanation? Yes No Errors on time sheets Use of higher grade staff Lower pay rises than budgeted and promised Lower learning rate (10 marks) Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 217 ACCA Practice Examination Management Accounting (MA) Answers Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 218 P rac t i c e e xami n a t i on an s w e rs A C C A MA Q ue s t ion Ba nk Section A 1 True False Accuracy is more important than timeliness They are prepared primarily for internal rather than external stakeholders It is more important that management accounts are timely, rather than completely accurate. They must be accurate enough for their purpose but do not need to be completely accurate or go into unnecessary detail. Management accounts are created for the internal managers, rather than for the external stakeholders such as customers, shareholders or employees 2 Relevant 3 Multi-stage Multi-stage sampling is a probability sampling method that involves selecting a sample in two or more stages. Clusters designed to contain more population units than are required for the final sample are initially selected. Population units are then chosen from clusters to derive a final sample. 4 Inventory is valued by including both production and nonproduction costs The LIFO method of inventory valuation assumes that the oldest items in inventory will be sold last True False Inventory is valued using production costs only. LIFO assumes that the newest items will be sold first, and therefore that the oldest items will be sold last. 5 A semi variable cost 6 Appendices Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 P ra c t i c e e xa mi n a t i on a n s w e rs A C C A M A Q ue s t ion Ba nk 7 The % of students going on active holidays (defined as Skiing and Walking) is greater than the % of students taking other types of holidays The % of students going on a Sightseeing holiday is greater than 25% 8 Cyclical variation 9 -30% True False The sum of the seasonal variations always equates to zero -25% + 40% + 15% = +30%, so remaining variation must be -30% 10 $536,250 Expected value = (0.45 × $500k) + (0.2 × $550k) + (0.35 × $575k) = $536,250 11 1.22 x̅ = 16 8 =2 (𝒙𝒙 – 𝐱𝐱 �) -1 1 0 -2 1 0 2 -1 Number of holidays 1 3 2 0 3 2 4 1 (𝑥𝑥−𝑥𝑥̅ )2 Standard deviation = � 𝑛𝑛 𝟐𝟐 (𝒙𝒙 − ���� 𝐱𝐱) 1 1 0 4 1 0 4 1 12 12 = � 8 = √1.5 = 1.22 12 800 EOQ = � units 2Co D Ch EOQ =√ (2 × 160 × 30,000/15)= 800 units Downloaded by Hooria Noor (nhooria9@gmail.com) 219 lOMoARcPSD|27223832 220 P rac t i c e e xami n a t i on an s w e rs A C C A MA Q ue s t ion Ba nk 13 366500 $ Date No of units 000 45 15 (20) 30 (25) (15) (20) 10 10 10 20 Opening 7 9 14 23 23 23 28 Closing Total Closing Cost per unit $ 17.25 18.00 17.25 18.25 17.25 18.00 18.25 18.40 18.25 18.40 Value $ 776,250 270,000 (345,000) 547,500 (431,250) (270,000) (365,000) 184,000 182,500 184,000 366,500 14 3150 $ Basic pay (40 × $60) Basic rate for hours covering colleague’s absence (5 × $60) Full rate for customer job (6 × $60 × 125%) $ 2,400 300 450 3,150 Only the basic salary for the hours covering the absent colleague are direct costs, as the reason for the overtime is the colleague’s absence and not demands that the client has made. The hours worked to complete the job by 9 May can be related to a specific job and are due to the demands of the client and are charged in full. Any idle time hours are excluded. 15 136 $ Basic salary = $16 × 8 hours = $128 Time that should have been taken to produce 60 units = 60 × (10/60) = 10 hours Time saved = 10 hours – 8 hours = 2 hours Bonus = 2 × 25% × $16 = $8 Pay = $128 + $8 = $136 16 A job is a ‘customer order or task of relatively short duration’. 17 95000 kg The normal loss is 5%, so expected output is 95% × 100,000 kg = 95,000 kg Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 P ra c t i c e e xa mi n a t i on a n s w e rs A C C A M A Q ue s t ion Ba nk 18 I and II There is an abnormal gain when actual output exceeds the expected output. 19 30 units Kg 600 (500) (60) (10) 30 Input Transferred to finished goods Normal loss Abnormal loss Closing work in progress As the closing work in progress was 100% complete with respect to materials, there were 30 equivalent units. 20 Large manufacturing company 21 Growth 22 A business must establish its long term objectives BEFORE it commences budgeting Better local knowledge is an advantage of bottom-up budgeting compared with topdown budgeting 23 True False A cash budget is a ‘detailed budget of estimated cash inflows and outflows incorporating both revenue and capital items’. 24 True False The quantity of finished goods in the production budget is the budgeted sales quantity minus the opening inventory plus the increased closing inventory The quantity of finished goods in the production budget must also be higher by exactly 10% if the finished goods inventory increases by 10% The quantity of finished goods in the production budget will be influenced by the change in the level of sales as well as the change in the level of inventory. 25 Depreciation of computer equipment This is not a cash expense. Downloaded by Hooria Noor (nhooria9@gmail.com) 221 lOMoARcPSD|27223832 222 P rac t i c e e xami n a t i on an s w e rs 26 A C C A MA Q ue s t ion Ba nk A fixed budget is a ‘budget set prior to the control period and not subsequently changed in response to changes in activity, costs or revenue. It may serve as a benchmark in performance evaluation’. 27 16,500 $ The direct materials cost is an entirely variable cost of $300 per % of activity. 15,000 50 = 300, 22,500 75 = 300, therefore $300 × 55 = $16,500 28 Strategy 29 Cash flow 30 Increase from 9.5% to 10.0% 27,000 90 = 300 Use PBIT, 20X8 ($19,950/$210,000) × 100% = 9.5%, 20X9 ($24,000/$240,000) × 100% = 10% 31 It is easy to understand. 32 $ 2100000 Residual Income = 3,000,000 + 300,000 – ((14,800,000 + 15,200,000)/2) × 8%) = $2,100,000 33 34 Number of new products introduced Customer retention rate It provides a means of reconciling short and long-term objectives. The balanced scorecard can highlight that there are conflicts between short and long-term objectives, but may not provide a clear guide to resolve these conflicts. 35 Economy, Efficiency, Effectiveness Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 P ra c t i c e e xa mi n a t i on a n s w e rs A C C A M A Q ue s t ion Ba nk Section B 1 BRIAN (a) 540 units Opening inventory = 30% × February sales = 30% × 1,800 = 540 units (b) 2420 units Production = Sales + Closing inventory – Opening inventory Production = 2,200 + (30% × 2,400) – 500 = 2,420 (c) $ 158400 Production = Sales + Closing inventory – Opening inventory Production = 2,100 + 510 – 630 = 1,980 Cost of kg required for production = 1,980 × 8 × $10 = $158,400 (d) $ 201920 Budgeted payment = (40% × $185,600) + (60% × $212,800) = $201,920 (e) 400 units Maximum production = 20,000/8 = 2,500 units, as 8 kg used per unit Closing inventory = Opening inventory + Production – Sales = 900 + 2,500 – 3,000 = 400 (f) Use Not use Taking out a bank overdraft Taking out a five year bank loan Investing in short-term debt instruments Agreeing with suppliers to delay payment A bank overdraft is designed to be used in the short-term. Longer-term finance is not necessary as the shortage is temporary. Investment would be appropriate if the business has a cash surplus, not shortage (it would be investing in someone else’s debt). Suppliers may well agree to a delay providing it does not become regular. Downloaded by Hooria Noor (nhooria9@gmail.com) 223 lOMoARcPSD|27223832 224 P rac t i c e e xami n a t i on an s w e rs A C C A MA Q ue s t ion Ba nk 2 CEDRIC 29 (a) months The cumulative cash flows are as follows: $000 (930) (280) 440 1 2 3 Payback period = 2 years + (280/(280 + 440)) × 12 = 2 years 5 months = (2 × 12) + 5 = 29 months The calculations in the following table are used in (b) and (c). A 1 2 3 4 5 6 7 8 9 10 11 12 13 14 B Year 0 $000 Revenues Cost of investment Running costs Net cash flow Discount factor 8% Discount factor 10% Discount factor 20% Discounted cash flow 8% Discounted cash flow 10% Discounted cash flow 20% Net present value at 10% Net present value at 20% C E 2 $000 1,200 3 $000 1,340 (550) 650 0.857 0.826 0.694 557 537 451 (620) 720 0.794 0.751 0.579 572 541 417 F 4 $000 500 (1,500) (1,500) 1.000 1.000 1.000 (1,500) (1,500) (1,500) 274 (32) (330) 570 0.926 0.909 0.833 528 518 475 33 (b) D 1 $000 900 (240) 260 0.735 0.683 0.482 191 178 125 months The cumulative discounted cash flows are as follows: $000 (972) (415) 157 1 2 3 Payback period = 2 years + (415/(415 + 157)) × 12 = 2 years 9 months = (2 × 12) + 9 = 33 months 19.0 (c) IRR = 10 + 274 274 − − 32 % (20 − 10) = 19.0% Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 P ra c t i c e e xa mi n a t i on a n s w e rs A C C A M A Q ue s t ion Ba nk (d) Advantage? Yes No It considers the time value of money It considers cash flows over the whole life of a project It considers the relative size of investments It considers relevant cash flows IRR does not consider the relative size of investments, which is one of its disadvantages compared with NPV. (e) Advantage? Yes No Spreadsheets can be used to do repetitive calculations quickly Spreadsheets automatically highlight incorrect data that has been input Spreadsheets make it easy to see the formulae used Spreadsheets allow what-if analysis to be performed quickly on the data in the appraisal Spreadsheets do not highlight incorrect data and it is not possible to see the formulae used without accessing the spreadsheet file. 3 GRAHAM (a) Graham is using marginal costing to account for the Teded True False The cost card includes fixed overheads, so Graham must be using absorption costing. (b) $ 699600 Budgeted profit = Budgeted number of units × Profit per unit = 7,800 × $88 = $686,400 Flexed budgeted profit = Budgeted profit + Sales volume variance = $686,400 + $13,200 = $699,600 (c) 7950 units Favourable sales volume variance in units = $ variance/Profit per unit = $13,200/$88 = 150 units Number of units sold = 7,800 + 150 = 7,950 (d) 40800 kg Usage variance in kg = $ variance/Standard cost per kg = $8,000/$10 = 800 kg adverse 8,000 units should have used 8,000 × 5 kg = 40,000 kg Actual usage = 40,000 kg + 800 kg = 40,800 kg Downloaded by Hooria Noor (nhooria9@gmail.com) 225 lOMoARcPSD|27223832 226 P rac t i c e e xami n a t i on an s w e rs A C C A MA Q ue s t ion Ba nk (e) 16.20 $ Variance per labour hour = $ variance/actual hours = 6,310/31,550 = $0.20 adverse Average labour rate per hour = $16 + $0.20 = $16.20 (f) 1800 $ The efficiency variance in hours will be the same as for labour. In $ it will be Labour efficiency variance × VOR per hour/Labour rate per hour = $7,200 × $4/$16 = $1,800 (favourable) (g) 6400 $ Volume variance = Capacity variance + Efficiency variance = $2,800 + $3,600 = $6,400 (favourable) (h) 2460 $ Overhead under/over absorbed = Total fixed overhead variance = Capacity variance + Efficiency variance + Expenditure variance = $2,800 + $3,600 – $3,940 = $2,460 (over-absorbed) (i) Explanation? Yes No Errors on time sheets Use of higher grade staff Lower pay rises than budgeted and promised Lower learning rate Errors on timesheets could explain both favourable and adverse efficiency variances. Higher grade staff should work more efficiently. The level of pay rises directly affects the labour rate variance, and if there is an impact on motivation, it is likely to be adverse if pay rises are lower than expected. A higher learning rate would lead to a favourable efficiency variance. Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 Fo rmu l ae an d T ab le s A C C A MA Q ue s t ion Ba nk Formulae and Tables Downloaded by Hooria Noor (nhooria9@gmail.com) 227 lOMoARcPSD|27223832 228 Fo rmu l ae an d T ab le s A C C A MA Q ue s t ion Ba nk Present value table Downloaded by Hooria Noor (nhooria9@gmail.com) lOMoARcPSD|27223832 Fo rmu l ae an d T ab le s A C C A MA Q ue s t ion Ba nk Annuity table Downloaded by Hooria Noor (nhooria9@gmail.com) 229 lOMoARcPSD|27223832 230 Fo rmu l ae an d T ab le s A C C A MA Q ue s t ion Ba nk Downloaded by Hooria Noor (nhooria9@gmail.com)