Uploaded by Chirawat Narupantawat

CP2 Full Practical Manual(1)

advertisement
CATHODIC PROTECTION 2
Technician
CP 2│CATHODIC PROTECTION TECHNICIAN
Practical Manual
IMPORTANT NOTICE:
Neither NACE International, its officers, directors, nor members thereof accept any
responsibility for the use of the methods and materials discussed herein. No authorization is
implied concerning the use of patented or copyrighted material. The information is advisory
only and the use of the materials and methods is solely at the risk of the user.
Printed in the United States. All rights reserved. Reproduction of contents in whole or part or
transfer into electronic or photographic storage without permission of copyright owner is
expressly forbidden.
Table of Contents
Introduction | 1
CP Concepts Review | 2
Field Measurements | 3
Practical Test Stations #1 | Lab
Practical Test Stations #2 | Lab
Stray Current | 4
Practical Test Stations #3 | Lab
Introduction
1
Chapter 1: Introduction
Overview
Corrosion is one of the most important problems encountered by the owners and operators of
underground, offshore, submerged and other metallic structures exposed to an electrolyte. If
corrosion is not controlled, it can lead to large costs in repairs or facility replacement. Even
greater costs can be incurred from environmental damage, injuries and fatalities.
Corrosion control personnel must have a good basic understanding of corrosion mechanisms.
They also need to know the various conditions under which corrosion can occur on
underground facilities.
The CP 2 - Cathodic Protection Technician training course is the second course in the 4-level
NACE Cathodic Protection Training and Certification Program. This course will focus on the
topics of corrosion theory, cathodic protection principles and systems, advanced field testing
and data collection.
Throughout the week, there will be in-class experiments to help demonstrate and reinforce
principles discussed in the lecture sections.
CAUTION: Students should realize that these experiments are conducted under controlled
conditions, field conditions will vary.
1.1 Quizzes and Examinations
Quizzes will be given at the end of each chapter as knowledge checks.
There are two final examinations: one written and one hands-on practical examination covering
selected test instruments.
The written exam is a computer based test. Students will schedule and attend the written exam
through an approved proctoring center and results will be provided at that time. See “Certification Tab” for additional information.
The practical exam is given on the last day of the course and is closed book. Under normal circumstances, within 10 to 15 business days following receipt of practical exams at NACE Headquarters, students may access their practical scores online at www.nace.org.
Passing the practical examination is required for successful completion of the course. All questions are from the concepts presented in this training manual.
1.2 Code of Conduct Policy
While on site at a NACE course, appropriate behavior towards instructors, NACE class location
staff, and fellow students is required. If appropriate behavior is not maintained, NACE has the
authority to take proper action against the student(s) in violation, which could result in revocation of one or more of the following: NACE Certification, Membership, and current/future
classroom attendance.
©NACE International
CP 2 | Technician
2
Introduction
1.3 Classroom and Electronic Device Policy
To provide the best environment for training, please observe and follow these requirements:
•
•
•
•
•
•
•
•
•
No smoking or other tobacco products; including electronic (vapor) cigarette
Class starts at designated times
Participants are responsible for their own learning and for timekeeping
Please turn off mobile ring tones, and do not make or answer calls, text messages or tweets
while in the classroom
Observe designated times for lunch breaks, coffee breaks and smoke breaks
Note location(s) of restrooms and smoking facilities
Mobile phones, smart phones, tablets, notebooks, cameras and any other devices containing cameras are not permitted during quizzes and exam.
Students are not allowed to be on the Internet or connect with the outside world through
their computer.
Students are not allowed to recored or take pictures of any portion of the classroom/lab
activities (including lectures).
All laptops must be kept in silent mode so as not to disturb others in the class.
1.4 Logo Policy
NACE International policy regarding the use of its logos, certification numbers, and titles is that
the certification number and category title may only be used by the following individuals:
• NACE Cathodic Protection Technician
Logos, certification numbers, and titles may not be used by any other persons. All active CP
card holders are permitted to use the term NACE Cathodic Protection Tester. Individuals may
also show their certification number on business cards and follow the below example, which
illustrates how this information can be listed on business cards: NACE Cathodic Protection
Technician:
John Smith
NACE Cathodic Protection Technician - Certified, Cert. No. 9650
ABC Company, Knoxville, TN
1.5 About NACE International
NACE International is recognized globally as the premier authority for corrosion control
solutions and is built upon over 75 years of knowledge and expertise from dedicated members
worldwide. NACE has grown into an organization with more than 37,000 members strong,
representing every major industry, in over 130 local sections and communities, throughout 140
countries. NACE’s mission is to equip society to protect people, assets, and the environment
from the adverse effects of corrosion.
Membership
NACE International membership provides you access to industry leading tools and resources,
the latest research, and networking opportunities from around the world to help you succeed at
every step in your career.
CP 2 | Technician
©NACE International
Introduction
3
NACE offers various membership levels for both individuals and organizations. Membership
levels to choose from include: Individual, Corporate, Student, Senior, and Lifetime.
To learn more about NACE membership and benefits visit nace.org/membership.
Conferences
NACE International connects our global audience at the local level by hosting industry and
technology-specific events such as conferences, seminars, exhibits, and area events and section
meetings so you can stay ahead of the latest technology and emerging industry trends.
One of NACE’s biggest events that is hosts annually is its CORROSION Conference &
Exposition. This conference is the world’s largest event for the prevention and mitigation of
corrosion, it welcomes more than 6,000 corrosion professionals from around the globe each year
and over 400 exhibitors. This comprehensive technical conference is packed with infinite
opportunities to exchange knowledge and connect with the entire corrosion-fighting
continuum: scientists and researchers, engineers and technicians, coatings inspectors and
contractors, educators and students, business executives and owners — all focused on the study,
prevention, and control of corrosion.
Go to nace.org/events for more information about upcoming events.
Technical Committees
NACE is a leading voice in developing corrosion-related standards and reports that affect
different industries. So why not lend your expertise to developing corrosion-related standards
and reports with one of NACE’s 300 technical committees and ~4000+ participants.
NACE technical committees are a community of end-users, consultants, manufacturers,
technologists, researchers, scientists, technicians, military, and governmental bodies united with
a common mission: combining industry expertise to establish standard best practices for
corrosion control and mitigation.
Participation in standards development is easy and open to everyone. Anyone can participate in
the process, but to fully engage in standards development, you must be a NACE member.
Go to nace.org/jointcc to learn more about lending your expertise.
Education
NACE is your place to turn to in achieving your career goals and offers a full array of classroom
and online training resources. Our courses are the most recognized and widely accepted
corrosion training programs in the world and are designed for continued, career-long
professional development.
With over 40 courses to choose from that have been developed by industry experts, our
programs provide the hands-on skills and knowledge necessary to address corrosion in a variety
of application-oriented and industry specific areas that focus on key technologies, best
practices, regulations, and business management topics.
Go to nace.org/edu to learn more about advancing your career through our educational
programs.
©NACE International
CP 2 | Technician
4
Introduction
NACE International Institute (NII)
The NACE International Institute (NII) was formed in 2012 to establish an organization focused
on certification activities and further advancing the corrosion profession. NACE credentials are
the ultimate proof of competence in the corrosion industry and are the most specified in the
world. NII has rapidly grown to include other key programs including IMPACT PLUS, NIICAP
and MPI.
Certification demonstrates commitment to your profession, continued mastery of your field and
offers credibility from your peers, within your company or in today’s competitive job market.
Position yourself for success by earning one of the more than 20 certifications available in
Coating Inspection, General Corrosion, Pipeline, Cathodic Protection, General Coatings, and
other specialty areas.
Please visit https://www.naceinstitute.org/Certification/ where you can;
•
•
•
•
•
•
Browse through current certification offerings by focus area
See detailed requirements for each certification
Prepare to take an exam by reviewing the Exam Preparation guide
Find detailed exam information and policies in our examinee user guides
Complete online applications
Renew your certification
Explore https://www.naceinstitute.org/ to find out more about other programs offered by the
NII including, NIICAP, IMPACT PLUS and MPI.
Publications
Whether you are considering a career in the corrosion industry – or are looking to learn more
about the latest technologies and practices to advance your career – NACE offers the world’s
most comprehensive technical resources that address dozens of industries affected by corrosion.
The NACE Store provides the largest offering of technical resources dedicated to corrosion
control and mitigation. From technical standards that set the criteria for corrosion issues
worldwide—to the latest technical papers and research presented at our conferences—to an
extensive library of books, the NACE Store is THE destination for industry-leading corrosion
resources. For more information go to store.nace.org.
NACE produces three industry-leading corrosion and protective coatings publications:
Materials Performance magazine, CoatingsPro magazine and CORROSION journal. These
publications provide insight from global corrosion experts on the latest case studies,
technologies and best practices for corrosion control and mitigation, and protective coatings
industries.
Materials Performance magazine is included with your NACE membership. It is the leading
resource on practical corrosion solutions and is read by 37,000 professionals worldwide. Stay on
top of the latest technical and industry news with your monthly subscription to Materials
Performance Magazine. This award-winning publication also features case studies and editorials
from leading experts and is delivered straight to your mailbox or your inbox as part of your
membership benefits. For more information go to materialsperformance.com.
CP 2 | Technician
©NACE International
Introduction
5
CoatingsPro magazine is the leading magazine serving coatings professionals with more than
27,000 readers worldwide, delivering current information on products, services, tips, and
techniques. To subscribe for free, go to coatingspromag.com.
CORROSION journal is one of the premier sources for corrosion research. It provides the
highest quality of innovative research articles that highlight the needs, gaps, and opportunities
in wide ranging areas of corrosion mitigation, prevention and control. Subscriptions are
available for an individual to site-wide institutional access.
For more information go to corrosionjournal.org.
©NACE International
CP 2 | Technician
CATHODIC PROTECTION 2
Technician
®
Chapter 1
Introduction
®
Introduction to
1
NACE International
Equips society to protect
people, assets, and the
environment from the adverse
effects of corrosion.
NACE International
built upon over
75 yrs.
of experience
Available
on-line about
10-15 business days
following
the course
with more
than
37,000 members
representing every
major industry
in over
130 local sections
and communities
NACE
Headquarters
NACE
Training Center
NACE
Office
www.nace.org
throughout more than
140 countries
Invest in Your Future
Provides YOU access to
TOOLS and RESOURCES, the latest
RESEARCH, and NETWORKING
OPPORTUNITIES from around the
world to help you succeed at every
step in your career.
nace.org/membership
2
NACE Offers Corrosion Professionals
Networking &
Volunteer
Opportunities
Industry
Standards &
Reports
Conferences
Magazines,
Education &
Training
Journals & Books
Certification
Programs
NACE Connects YOU Globally
Stay ahead of emerging trends by attending any of NACE’s
international or local industry and technology-specific
conferences, seminars, exhibits, and area/section events.
nace.org/events
Have a Voice in Industry Standards
Lend your expertise to developing corrosionrelated standards and reports with one of
NACE’s 300 Technical Committees and
~4000+ participants.
Join a community of corrosion professionals
united with a common mission of:
“Setting the standard for
best practices in corrosion control.”
nace.org/jointcc
3
Advance YOUR Career through Education
 Select from over 40 courses,
designed by technical experts
 Online and Instructor-led
courses are available
 Are application oriented and
industry-specific courses
that focus on:
 Key technologies
 Best practices
 Regulations
 Standards
nace.org/edu
Increase YOUR Knowledge Through CTS
Stay current on latest trends and best practices in the corrosion industry
with the Corrosion Technical Series (CTS). Technical discussions are
presented by Industry experts on emerging topics. Network with speakers
and peers from all over the country throughout this 1-2 day event.
nace.org/edu
Standout Among YOUR Peers
The NACE International Institute (NII)
 Validate your skills by earning one of the most recognized
corrosion certifications in the world
 Select from over 20 certifications in 6 different subjects:
1. Coating Inspector
4. Cathodic Protection
2. General Corrosion
5. General Coatings
3. Pipeline
6. Specialty
 Demonstrate your dedication to staying current in your
field of expertise by becoming certified
www.naceinstitute.org/certification
4
Subscribe to Industry Publications
Keep up with the latest technologies, best practices for corrosion control and
mitigation, and protective coatings with these leading publications from NACE.
Included with
NACE Membership
Complimentary
Subscription
Individual
Subscription
materialsperformance.com
coatingspromag.com
corrosionjournal.org
Build YOUR Library of Knowledge
 Choose from over 450
books in 20 categories,
and more than 250
technical standards
and reports
 Get the latest informative
reference material,
learning from real success
stories, and detailed
guidance on how to apply
the latest technologies in
your industry
www.store.nace.org
Classroom Guidelines
Classroom
Guidelines
and
Logistics
 Arrive on time
 No disturbances – turn your cell
phone off
 Respect one another
 Actively participate
 Agree to disagree
 Students are responsible for their
own learning
Classroom Logistics
 Breaks
 Restrooms
 Abide by all safety regulations
 Fire exits, first aid, eye wash,
proper protective equipment, etc.
5
Identify Safety Risks in Course
Chemical
 Copper sulfate (Instructor will advise location of MSDS)
Electrical
 Many electrical devices in course. Most safe but others not
 Consider all electrical tests hazardous
Fire
 Location of Fire Alarm(s)
 Preferred exit and alternate
 Muster Points
Tripping
 Obstacles on floor
 Wet floors
 Ice in cold climates
Other specific to Building?
CP2 | Technician
General Safety Precautions
Personal Protective Equipment (PPE)
 Eye Protection
 Remove Contact Lenses and use glasses
 Gloves - Recommended
 Lab Coat - Recommended
MSDS sheets
 Know location in course
 Students are to read
 Understand First Aid
CP2 | Technician
Copper Sulfate
 Poison: if ingested
(stomach, lungs or eyes)
 Read MSDS
 Nausea, vomiting damage
to body cells or organs.
 Use Eye protection
 Irritant to Eyes
 Damage to clothing and
carpets
 Understand First Aid
 Wear gloves
 Wash immediately after
contact
 Do not eat before washing
CP2 | Technician
6
Course Safety - Electrical
 Many electrical devices in course: some hazardous - others not.
 Assume all are hazardous and work accordingly
 Use insulated probes and clips
 Do not touch bare probes, clips or terminals!
 Wear Eye protection
 Wires can flip into eyes and arcs can occur!
 Rectifiers
 Turn off / unplug when connecting, adjusting or testing!
 Short circuits
 Cause arcing and failure of equipment
 Cause toxic fumes from burning wire insulation or electrical components
 Contact instructor if unsure of connection
 Arcing
 Shorting power source
 Connecting to power source when energized
CP2 | Technician
Rectifiers and Power Source Safety
With Rectifier Circuit Breaker ON: all terminals are
“HOT”
 Make connections with rectifiers off
 Do no touch terminals with hands or hands
holding metal clips, metal probes etc.
 Use manufactured insulated meter probes
for measurements
 Use one hand method of measuring any
voltage (Instructor to demonstrate)
With Rectifier Circuit Breaker OFF: only panel
terminals de-energized
 AC supply and breaker terminals still hot
 Do not attempt to insert tools or metal
probes inside rectifier.
 Turn off and unplug rectifier before working
inside.
CP2 | Technician
Other Precautions
Fire
 Instructor to advise Muster Point locations
 If a fire:
 Turn on fire alarm
 Exit Building
 Gather at Muster Point
Tripping
 Do not leave articles on the floor in the
classroom or in hallways
 Wet floors should be immediately cleaned or
place a hazard sign
Advise instructor of any hazards
CP2 | Technician
7
Course Schedule
CP2 Practical Schedule
Chapter 1
Introduction, Welcome, Overview
Chapter 2
CP Concepts Review
Chapter 3
Field Measurements
Lab 1
Practical Test Stations #1
Lab 2
Practical Test Stations #2
Chapter 4
Lab 3
Stray Current
Practical Test Stations #3
Practical Exam
Note: Schedule is subject to change
Accessing Your Digital Course Materials
1. Students must sign into
their NACE Profile
2. Click Education History >
Online Course Materials
3. Click Library
4. View the course materials
Successful
Course
Completion
To “successfully complete” this course and
receive a Certificate of Completion and earn
4.5 CEUs, the following criteria must be met:
 Attend the entire course (Part 1: Theory
and Part 2: Practical)
 Successfully pass each learning
assessment with a score of 70% or higher
 Learning assessments include a practical
exam
The Training Certificate of Completion denotes successful completion of
the NACE course, and should not be considered or represented to Industry
as the achievement of a NACE Institute Certification.
NACE Institute certifications are only awarded once a candidate successfully
completes all set certification requirements, including, but not limited to, exams,
work experience and educational requirements.
8
Exams
Computer Based Testing (CBT)
A multiple choice exam that you schedule and attend
at an approved proctoring center, with results
provided at the end of the test.
Hands on Practical Exam
12 stations, 10 minutes allowed at each work
station. The exam is given on the last day of class
and is closed book. However, reference sheets are
provided.
Certification and CBT Resources
Computer Based Testing (CBT) Resources
Located under the Certification tab in your manual:
 Becoming Certified
 Scheduling your exam
Located at www.naceinstitute.org/certification:
 Exam Preparation Guide
 Certification Requirements
 Exam Blue Print
 Types of Questions
 Exam Preparation
 Examinee user guides and policies
 Online certification application
 Renew your Certification
Available on-line about
10-15 business days
following the course
1. Go to www.nace.org
2. Select Training & Education
3. Check My Exam Results
4. Log in to your NACE profile
Exam Results
9
Course Objectives
 Perform advanced field tests, including: current requirement test,
shorted casing test, IR drop test, soil resistivity, and interference
tests, and evaluate the results
 Perform tests to verify the presence of stray current interference
and recommend method(s) to mitigate the interference
 Conduct and understand the importance of periodic surveys, including
IR-Free readings, polarization decay tests, and current measurements
 Maintain documentation and records, including data plotting
and analysis
 Describe AC voltage and the methods for mitigation
 Test and troubleshoot rectifier component parts
 Recognize the purpose and use of corrosion coupon
test stations
 Recall code requirements related to CP
1
CP Tester
Beginner
NACE CP
2
CP Technician
Intermediate
www.nace.org/cp
3
CP Technologist
Intermediate Advanced
4
CP Specialist
Advanced (Engineering Level)
Training Courses
Online Courses:
Specialty Courses:
CP Fundamentals
Virtual Test Stations
Coatings in Conjunction w/ CP
CP Interference
Certification Path
An approved application is required before certification
is issued for CP 2, CP 3 and CP 4 certifications:
CP 1
Tester
CP 2
Technician
CP 3
Technologist
CP 4
Specialist
Applications include work experience, academic/education
background, and qualification references.
Online application forms can be found at:
www.naceinstitute.org
10
Student
Introductions
 Name and Organization
 Job Function
 Industry Experience
 Course Expectations
Chapter 1
Introduction
®
11
2-1
Experiment 2.1 - Corrosion Cell and Cathodic Protection
Student to perform
Part A - Corrosion Cell with Different Environment Changes
Preparation
To ensure consistent results during class and from class-to-class, the following preparation is
advised.
A)
B)
Use simulated seawater: (35g NaCl/litre ~= 1 Cup NaCl/7.8 litre ~= 2 heaping tablespoons
NaCl /litre). This will help to obtain potentials similar to those in the Practical Galvanic
series.
Presoak the samples overnight or for at least 4 hrs in advance: This will depassivate the
samples and establish steady-state corrosion potentials. Otherwise the potentials will be
constantly shifting during the test often voiding the results.
Procedure
1. Place simulated seawater in the tray
2. Place a steel sheet in left side of tray
3. Place a copper sheet in right side of tray
4. Measure potentials as shown in Figure 2.1 and enter results in table below
Figure 2.1 Potential Measurement of metals
5.
Connect the two metals together as shown in Figure 2.2, measure the corrosion current
(Icorr), not polarity and enter results in table below.
©NACE International
CP 2 | Technician
2-2
Figure 2.2 Measurement of Corrosion Current
6.
Remeasure the potentials as in Figure 2.3 with them connected via the ammeter and enter
the results in table below.
Figure 2.3 Measurement of Potentials with
Corrosion Current
7.
Still connected as in Figure 2.3, either blow air on to the copper sheet or rub the copper surface, repeat the potential and current measurements and enter results in table below
8.
Allow to stabilize, stir the electrolyte aggressively and repeat the potential and current measurements. Enter results in table below
CP 2 | Technician
©NACE International
2-3
9. Disconnect the ammeter and quickly measure potentials while the electrolyte is still agitated
and record results
Results
Test
Step 4 - Open Current
EFe
ECu
Icorr
Step 5 & Step 6 - Corrosion
Cell
Step 7 - Depolarizing
Cathode
Step 8 - Corrosion Cell
with moving electrolyte
Step 9 - Open circuit with
moving electrolyte
Conclusions
•
•
•
•
•
•
The cathode of the corrosion cell was the ___________ sheet
Adding air or rubbing the surface of the copper sheet resulted in a ______________ (positive - negative) shift in potential
Adding air or rubbing the surface of the copper sheet resulted in a ____________ (decrease increase) in Icorr
Circulating the water resulted in a ____________ (positive - negative) shift in potential
Circulating the water resulted in a _____________ (decrease - increase) in Icorr
Circulating the water resulted in a _____________ (decrease - increase) in the open circuit
potential
©NACE International
CP 2 | Technician
2-4
Part B - Corrosion Cell with CP
Procedure
10. Using the equipment in Part A, allow EFe, & ECu potentials and Icorr to stabilize and record.
11. Measure pH and potentials of both metals as shown in Figure 2.3 and enter results in table
below.
12. Install an impressed current cathodic protection system as shown in Figure 2.4 noting that a
sacrificial anode is shown in the figure, but an impressed current system is optional.
13. After connecting to the 10,000 Ohm resistor, measure:
A. the potentials of the two metals,
B. the current between the two metals,
C. either the total CP current or the voltage across the resistor and calculate the total
cathodic protection current from the voltage across the known resistor.
14. Repeat step 13 at the different resistor values. Note when the current between metals
changes directions.
Figure 2.4 CP System Added to Corrosion Cell
15. Measure pH at both metal surfaces and record
CP 2 | Technician
©NACE International
2-5
Results
Circuit
EFe
ECu
Icorr /
IFe,CP
Total ICP
(mVCSE)
(mVCSE)
(mA)
(mA)
pH
Cu
Fe
Step 1 Open
Circuit
Step 10
Polarized
Step 13 CP
ON, RLimit 10,000 in
series
Step 14 CP
ON, RLimit =
1,000 
Step 14 CP
ON, RLimit =
100 
Step 14 CP
ON, RLimit =
10 
Polarization Plot
Plot the results on a polarization diagram on graph paper provided
Conclusions
•
Corrosion current __________ (increases or decreases) as cathodic protection current
increases
•
Corrosion current ___________ (increases or decreases) as the cathode polarized potential is
made more electronegative.
•
Corrosion from galvanic couple is stopped at ______________Ohms (what resistor value)
•
Corrosion on the steel is mitigated at __________ Ohms (what resistor value?)
•
The pH after cathodic protection was applied ___________ (increased/decreased/no change)
©NACE International
CP 2 | Technician
2-6
CP 2 | Technician
©NACE International
Chapter 2
Concepts of Cathodic
Protection - Review
®
Pipeline Corrosion Cell
Cathode
2
Anode
Microscopic Corrosion Cell on the Surface of a Pipeline
CP2 | Technician
Cathodic Protection - Definition
3
When the potential of all cathode sites reach the open
circuit potential of the most active anode site, corrosion on
the structure is eliminated.
CP2 | Technician
1
Application of Cathodic Protection Decreasing Corrosion Current
4
C.P. CURRENT
ANODE
-0.65 volt
CATHODE
-0.50 volt
CATHODE
-0.65 volt
I corr = 1 mA
CATHODE
-0.65 volt
I corr = 0 mA
Reduction
In corrosion
current
BEFORE
Cathodic Protection
AFTER
Cathodic Protection
CP2 | Technician
Structure Polarization
5
 Cathodic protection is a polarization phenomenon
 The most cathodic sites on the structure polarize first
 Polarization of the cathode sites to the open circuit potential
of the most active anode sites on the structure
CP2 | Technician
Cathode Polarized to the Open
Circuit Potential of the Anode
+
EC,OC
6
Cathode polarizes to
open-circuit potential
of anode, resulting in
zero corrosion current
EC,P
ECORR
E
EA,OC
EA,P
E’C,P
ECPA,P
_
ECPA,OC
I CORR
ICP
Log I
CP2 | Technician
2
CP Current Requirement
7
 Depends upon surface area to be protected
 Current requirement is directly proportional to surface area
 Protective coatings reduce the exposed surface area
 Polarization behavior of the structure in its environment
 Current requirement is inversely proportional to polarization
 The more the environment favors an increase in polarization
the lower the CP current requirement
CP2 | Technician
Cathodic Protection Criteria
8
NACE Standard SP0169
Control of External Corrosion on Underground or
Submerged Metallic Piping Systems” several criteria for
determining when adequate cathodic protection is
achieved are found in Section 6, “Criteria and Other
Considerations for Cathodic Protection”
CP2 | Technician
Criteria for Underground or Submerged
Iron or Steel Structures (Reverse Ordered Intentionally)
9
6.2.1.3 A structure-to-electrolyte potential of –850 mV or more negative as
measured with respect to a saturated copper/copper sulfate (CSE) reference
electrode. This potential may be either a direct measurement of the polarized
potential or a current-applied potential. Interpretation of a current-applied
measurement requires consideration of the significance of voltage drops in the
earth and metallic paths.
6.2.1.2 A minimum of 100 mV of cathodic polarization. Either the formation or
the decay of polarization must be measured to satisfy this criterion.
∆E100 = EOFF − EDEPOLARIZED
OR
∆E100 = EOFF − ECORR
6.2.1.1 Criteria that have been documented through empirical evidence to
indicate corrosion control effectiveness on specific piping systems may be used
on those piping systems or others with the same characteristics.
CP2 | Technician
3
Measured Potential
10
The potential across the structure/electrolyte
interface is the sum of the corrosion potential and the
cathodic polarization plus a voltage (IR) drop error if
current-applied.
Emeasured = Ecorr + Polarization + Voltage (IR) Drop
CP2 | Technician
Measuring Polarization on a Structure
Normal Reference
Electrode Location
‐0.900
V
‐
+
11
Preferred Reference
Electrode Location
Structure
To Electrolyte
Boundary
Polarization Film
CP2 | Technician
Cathodic Protection - Monitoring
-1.6
12
Von
-1.4
Voltage (IR) drop
Potential
-1.2
-1.0
-0.8
Instant Off or Voff
Polarization
Decay
-0.6
-0.4
Polarization Decay Time
Time
CP2 | Technician
4
Criteria for Other Materials
13
Other NACE International Criteria
 Aluminum
 100 mV polarization
 Copper
 100 mV polarization
 Reinforced Concrete Structures
 100 mV polarization
 E log I
CP2 | Technician
Instrument SAFETY in Experiments
14
 Even lower voltages can be hazardous
 Know capacity of meter
 Replace damaged digital multimeter (DMM) test leads
 Keep fingers behind probe guards Do not touch probe tip
 Do not press wire/terminal/probe tip with fingers
 Confirm correct meter dial position for measurement
 Confirm correct test lead polarity
 Never connect ammeter leads across a
 voltage source
 Low ammeter resistance shorts power supply
 Never use Ohmmeter in circuit having voltage
One-hand Method
CP2 | Technician
EXPERIMENT 2.1
15
Experiment 2.1
Part A: Corrosion Cell with Different
Environment Changes
CP2 | Technician
5
Experiment 2.1 – Part A
16
 Presoak samples in
simulated seawater (35g
NaCl / litre of H2O)
-0.45 V
-0.18 V
Same Meter
 Place Fe and Cu at each end
of tray containing seawater
 Measure potentials of each
 Record
Noble
Active
CP2 | Technician
Experiment 2.1 – Part A
17
 Connect metals through an ammeter
 Measure current (Icorr) and polarity
 Record
14 mA
Corrosion Current (Icorr)
Conventional Current
Active
Noble
CP2 | Technician
Experiment 2.1 – Part A
18
 Measure potentials of metals when connected
 Record in table
Icorr
14 mA
-0.31 V
Corrosion Current
-0.29 V
Same Meter
Conventional Current
Active
Noble
CP2 | Technician
6
Experiment 2.1 – Part A
Table for Readings
Test
EFe
19
ECu
Icorr
Step 4 – Open Circuit
Step 5 & Step 6 –
Corrosion Cell
Step 7 – Depolarizing
Cathode
Step 8 – Corrosion Cell
with moving electrolyte
Step 9 – Open circuit
with moving electrolyte
CP2 | Technician
Experiment 2.1 – Part A - Conclusions
20
 The cathode of the corrosion cell was the ___________ sheet
 Adding air or rubbing the surface of the copper sheet resulted in a ______________
(positive - negative) shift in potential
 Adding air or rubbing the surface of the copper sheet resulted in a ____________
(decrease - increase) in Icorr
 Circulating the water resulted in a ____________ (positive - negative) shift in potential
 Circulating the water resulted in a _____________ (decrease - increase) in Icorr
 Circulating the water resulted in a _____________ (decrease - increase) in the open
circuit potential
CP2 | Technician
Experiment 2.1 – Part B
21
Experiment 2.1
Part B: Corrosion Cell with Cathodic
Protection
CP2 | Technician
7
Experiment 2.1 – Part B
22
 Continue from Part A
Corrosion Current
14 mA
-0.31 V
-0.29 V
 Allow potentials to stabilize
Same Meter
 Measure pH of 2 metals
 Record
Conventional Current
Active
Noble
CP2 | Technician
Experiment 2.1 – Part B
23
 Install a CP system
 Connect through 10,000 Ω
resistor & measure:
5 mA
10 mA
-0.31 V
-0.29 V
 Potentials of 2 metals
 Current and polarity
ICP Total
 Total current or Voltage
across resistor
10,000 Ω
1,000 Ω
100 Ω
 Repeat with other resistors
10 Ω
Anode
RLimit
 Measure pH
 Record
CP2 | Technician
Experiment 2.1 – Part B
Table for Readings
Circuit
24
EFe
ECu
Icorr / IFe,CP
Total ICP
(mVCSE)
(mVCSE)
(mA)
(mA)
pH
Cu
Fe
Step 1 – Open
Circuit
Step 10 Polarized
Step 13 CP ON,
RLimit = 10,000 Ω
in series
Step 14 CP ON,
RLimit = 1,000 Ω
Step 14 CP ON,
RLimit = 100 Ω
Step 14 CP ON,
RLimit = 10 Ω
CP2 | Technician
8
Experiment 2.1 – Part B - Conclusions
25
 Corrosion current __________ (increases or decreases) as cathodic
protection current increases
 Corrosion current ___________ (increases or decreases) as the cathode
polarized potential is made more electronegative.
 Corrosion from galvanic couple is stopped at ______________Ohms
(what resistor value)
 Corrosion on the steel is mitigated at __________ Ohms (what resistor
value?)
 The pH after cathodic protection was applied ___________
(increased/decreased/no change)
CP2 | Technician
Chapter 2
Concepts of Cathodic
Protection - Review
®
9
Field Measurements
3-1
Chapter 3: Field Measurements
Knowledge of proper test procedures is an essential skill of a cathodic protection technician.
They must understand the instrumentation, the proper assembly of the instrumentation for
each test, the theory behind the tests and the possible sources of error that can lead to
misinterpretation of results.
3.1 Instruments
Analog meters operate on the basis that the magnetic field created by a meter current through a
coil that causes the coil to rotate in a permanent magnet field. A needle on the coil points to a
dial that is calibrated to voltage current, or resistance. The meter current is proportional to the
voltage thus the meter scale can be calibrated into Volts or amperes. The meter coil changes
continuously with a changing meter current and thus tracks a changing voltage or current. A
cathodic protection technician should be familiar with these instruments as they are used on
instrumentation requiring analog indications (e.g. DCVG meters, ‘null’ meters, some locators,
etc.) and are commonly used for output indication on DC power sources.
Most field instruments employ electronic signal
conditioning with digital displays – often termed
‘digital’ meters. Compared to analog meters discussed
above, the electronics in these meters generally have
much higher input impedance, are more rugged, and
have some protection against over voltage. The typical
functions of a digital multimeter (DMM) are, at least, an
AC/DC voltmeter, AC/DC ammeter and a DC
Ohmmeter but can have other functions such as
frequency, continuity, diode test circuit, etc. (Figure 3.1)
Digital multimeters (DMMs) condition the input signal
with analog electronics, then convert that conditioned
signal to a digital format, where it may be further
conditioned, and then display the measured value
digitally.
Figure 3.1 Typical Digital Multimeter (left)
and Internal Block Diagram (right)
DMMs typically use 3½ digit (i.e. 1.999) displays as shown above, though a higher resolution is
also available. Displayed values are typically updated 2 to 4 times per second, which can be
difficult to read if the input signal is changing rapidly (an advantage for analog displays!). The
LCD displays can be damaged if exposed to extreme hot or cold temperatures (e.g. if kept on the
dash of a vehicle), so due care is required.
©NACE International
CP 2 | Technician
3-2
Field Measurements
3.1.1 DMM Voltage Measurement
When used on DC or AC Voltage ranges, the input
signal is protected, conditioned and converted as
illustrated in Figure 3.2.
When taking an instant OFF potential, the DMM
displayed value changes rapidly as the measurement is
falling from the ON potential to the OFF potential
and then starts to depolarize. This can make it
difficult for the user to determine which value is the
actual ‘instant off’ potential. Taking the displayed
value between 0.5 and 1 second after interruption will
avoid any spiking that occurs briefly upon current
interruption, before any significant depolarization
occurs.
Figure 3.2 DMM Voltage Measurement
Schematic
3.1.2 DMM Current Measurement
When used on DC or AC Current ranges, the input
signal is protected, conditioned and converted as
illustrated in Figure 3.3.
With the ammeter in series with the external circuit,
the external current goes through a shunt in the meter
of a known resistance. The shunt resistor is sized to a
current such that the voltage across the resistor can be
measured and calibrated to it. The digital electronics
calculates and displays the current based on the
measured voltage across the known shunt resistance.
Figure 3.3 DMM Current Measurement
As the current to be measured decreases, the shunt
Schematic
resistance must increase to provide a sufficiently high
voltage for the measurement electronics. Thus, when inserting an ammeter into a circuit, the
internal ammeter resistance increases the total circuit resistance, reducing the total current.
Therefore, the current measured will always be less than the actual current without the ammeter
installed. Further a measurement on two different ammeter scales may be quite different for the
same reason. Use the highest scale that will give a reading and be aware of the internal ammeter
resistance on each scale.
CP 2 | Technician
©NACE International
Field Measurements
3-3
3.1.3 DMM Resistance Measurement
An ohmmeter measures the electrical resistance of
components between the meter terminals. To measure
these components, they normally must be taken out of
the circuit or the circuit must be open to ensure that
no voltage from an external source exists. An external
voltage will either oppose or enhance the internal
voltage giving false readings, blow an internal fuse, or
in extreme cases will damage the instrument.
The Ohmmeter circuit in Figure 3.4 employs an
internal DC voltage source to force current through a
known internal resistance and the resistance under test Figure 3.4 DMM Resistance Measurement
Schematic
which are connected in series. The digital electronics
calculates and displays the test resistance based on the
ratio between the measured voltage across the internal resistance and that of the internal DC
voltage source.
Note that as the DMM Ohmmeter operates with an internal DC source, it cannot be used on any
circuit where there is a back-emf (DC voltage), as exists between any two metal structures in an
electrolyte, as the emf will add or subtract from the total DC volts in the measurement circuit,
so the displayed resistance value will be either higher or lower than actual. For these types of
measurements, an AC resistance meter must be used.
3.1.4 Other DMM Features & Functions
3.1.4.1 AC Volts vs. rms
A basic digital AC voltmeter records the peak AC voltage and multiplies this value by a factor
(1/√2 = 0.7071) to determine the actual AC Volts. This is only accurate if the waveform is a true
sine wave. Otherwise, if not a true sine wave, a rms AC voltmeter must be used to determine the
correct AC voltage. If in doubt, use a rms AC voltmeter.
3.1.4.2 Auto-Range
A basic meter requires that the range be preset by the operator. If the scale is too small for the
reading, a symbol such as “OL” will appear. If the scale is too large, the readout will be
inaccurate. Thus, it is important to select the correct scale (mV, V etc.).
A DMM with an auto-range feature will select the best range automatically. This may be
advantageous in some situations but requires the user to pay attention to the scale of the
displayed value (e.g. Volts versus mV). If the measured value has large rapid changes in
magnitude, then this could cause the meter to continuously change ranges, resulting in display
changes that are difficult to follow. For example, this may occur when measuring instant OFF
potentials that are less than 1V while the ON potentials are greater than 2V, or measuring
potentials that are affected by dynamic stray currents. It is usually possible to disable autoranging to and select a fixed measurement range.
©NACE International
CP 2 | Technician
3-4
Field Measurements
3.1.4.3 Diode Test
A diode requires a driving voltage greater than its inherent forward voltage before it will
conduct. Thus, DMM diode testing circuits impresses a DC voltage and displays this value in
Volts when the diode conducts. In this case the diode is conducting from the positive to negative
meter leads. A good diode does not conduct in the reverse direction therefore the reading with
the meter leads reversed will be “OL”. The combined readings indicate the diode is in good
operating condition.
A shorted diode is noted by both forward and reverse readings of 0 Volts (no breakdown voltage
required) and an open circuit diode is noted by “OL” readings in both directions.
3.1.4.4 Frequency
This scale is intended to measure the number of AC cycles per second (hertz). Functionally,
DMMs measure the number of times an input signal changes slope direction (i.e. positive to
negative) in one second. Consequently, it may also be used on a full wave rectifier that is not
filtered as it will detect the peak to peak half cycles that in this case will be 100 or 120 hertz
depending on the AC input. If 50 or 60 hertz are recorded, the rectifier is half-waving.
3.1.4.5 Hold Feature
Some DMM have a “hold” feature that allows a reading to be frozen on the readout. This is an
advantage when taking a reading in conditions where it is difficult to read the meter scale such
as poor lighting or to keep the reading on display until it is recorded.
3.2 Measurement of Cathodic Protection Effectiveness
Various techniques may be used to determine the degree to which a structure under cathodic
protection (CP) is actually protected against corrosion, including:
•
•
•
•
•
•
•
Structure-to-electrolyte potential
Test coupons
Current measurements
Soil resistivity
Direct observation
Leak frequency
In-Line Inspection
3.3 Structure-to-Electrolyte Potentials
The definition of a structure-to-electrolyte potential, otherwise referred to as a pipe-toelectrolyte, pipe-to-soil, tank-to-electrolyte, or structure-to-soil potential is:
“The potential difference between the metallic surface of the structure and electrolyte that is
measured with reference to an electrode in contact with the electrolyte.”
These measurements must include:
•
Magnitude
CP 2 | Technician
©NACE International
Field Measurements
•
•
•
3-5
Polarity
Units
Reference electrode
A structure-to-electrolyte potential is a measurement taken with the voltmeter connected in
parallel in the circuit. The external circuit resistance of this measurement is high, so a highinput resistance voltmeter is required to avoid “shunting” too much current from the structure
and, therefore, obtaining inaccurate measurements. In addition, a reference electrode, often
referred to as a reference cell, is used to make contact with the soil.
Structure-to-electrolyte potential profile surveys are used to:
•
•
•
•
•
Locate anodic areas on non-cathodically protected pipelines
Determine the effectiveness of cathodic protection on cathodically protected structures
Locate stray currents
Locate electrical shorts and contacts
Locate coating holidays
Potential measurements are a common means for determining if adequate protection has been
achieved. With the application of current from the environment onto a structure, a potential
change with respect to the environment will occur. The potential change is a reflection of
polarization. Measurements are made to determine whether one of the cathodic protection
criteria is met (see Chapter 2 for discussion on CP criteria). According to the NACE standards,
voltage drops other than across the structure-to-electrolyte boundary must be considered in
order to assess the effectiveness of a CP system using fixed potential measurements. Several
methods are used to consider these voltage drops:
•
•
•
•
Minimizing the distance between the reference electrode and the surface of the structure
Measuring the potential when the current is interrupted (instant-off potential)
Measuring the formation of polarization or decay of polarization of the structure when the
current is energized or disconnected
Installing external CP coupons in the vicinity of the structure to replicate a coating holiday
Advantages of the structure-to-reference potential method are that it is relatively
straightforward, and potential measurements comply with standard criteria. Disadvantages are
that all sources of CP current must be interrupted simultaneously, stray currents will affect the
readings, polarized potentials of structures with direct-coupled galvanic anodes cannot be
obtained, and surface potential measurements actually measure average potentials. The
averaging of the actual structure-to-electrolyte potentials means that surface measurements
might not detect small corrosion cells that are not being cathodically protected.
3.3.1 The Potential Measurement Circuit and Measurement Error
The intent of the potential measurement is to determine the structure potential (Etrue)
accurately at the test location. The measurement circuit can be approximated by the electrical
circuit in Figure 3.5.
©NACE International
CP 2 | Technician
3-6
Field Measurements
Figure 3.5 Electrical Schematic of the Structure-to-Electrolyte Measurement
Circuit
It is the true potential difference (Etrue) between the pipe and reference electrode that ideally
should appear across the meter terminals. Because the meter circuit is a series circuit, the
magnitude of the voltage drop that appears across the meter will be proportional to the ratio of
the meter resistance to the total meter circuit resistance.
For the measurement circuit, Kirchhoff’s voltage law applies and the true potential difference is
equal to the sum of the voltage drops around the series circuit.
Etrue = ImRt
[3.1]
Etrue = Im [Rtl,1 + Rtl,2 + Rtl,3 + Rp,e + Rr,e + Rm]
Etrue = Vtl,1 + Vtl,2 + Vtl,3 + Vp,e + Vr,e + Vm
Vm = Etrue – [Vtl,1 + Vtl,2 + Vtl,3 + Vp,e + Vr,e]
Let Vcirc equal all voltage drops in the circuit except for the meter voltage drop
Vm = Etrue – Vcirc
but: Etrue = ImRt and Vcirc = ImRcirc
and:
then:
Rt – Rcirc = Rm
[3.2]
Hence, the amount of voltage (Vm) that appears across the meter compared to the true potential
difference (Etrue) is proportional to the ratio of the meter resistance (Rm) compared to the total
resistance.
CP 2 | Technician
©NACE International
Field Measurements
3-7
For example: Consider a true potential (Etrue) of 1,000 mV, each test lead resistance (Rtl) of
0.01Ω, a pipe-to-earth resistance (Rp,e) of 10Ω, a reference electrode resistance to earth (Rr,e) of
100 kΩ, and a meter resistance (Rm) of 1 MΩ. Calculate the voltage that would appear across the
voltmeter.
Rt = 3Rtl + Rp,e + Rr,e + Rm
= 3(0.01) + 10 + 105 + 106
Rt = 1.1 MΩ
= 909 mV
This is an error of:
If the meter input resistance in the foregoing example is increased to 10 MΩ, the voltmeter
would read 990 mV which would reduce the error to 1%. The voltage across the voltmeter
approaches the true potential as the meter resistance becomes much greater than the other
resistances in the measuring circuit.
High resistances in the measuring circuit, other than across the voltmeter, should therefore be
avoided. Reference electrode contact resistance can be a source of error when the reference is
placed on dry soil, well drained gravel, crushed stone, frozen ground, asphalt, or concrete. To
minimize this error, the contact conductance can be improved by wetting the area around the
reference. In extreme cases, a hole can be drilled from the surface to a depth of permanent
moisture and the reference placed in the hole, or an electrolytic bridge can be created between
the reference and earth.
3.3.1.1 Minimizing Reference Electrode Contact Resistance
•
•
•
•
Wet soil as needed
Avoid grass
Avoid asphalt, concrete, and gravel surfaces
Access ports (Figure 3.6)
©NACE International
CP 2 | Technician
3-8
Field Measurements
Figure 3.6 (Left) Methods of Minimizing Reference Electrode Contact
Resistance (Dry soil or frozen ground) and (Right) Methods of Minimizing
Reference Electrode Contact Resistance (Asphalt or concrete)
In Figure 3.6 (Right), the depth from grade to clay must be below the frost line in frozen soil and
to the depth of permanent moisture in dry soil. For asphalt or concrete, a soapy water solution
will usually provide sufficient electrolytic contact even if the water level in the hole drops.
High measurement circuit resistance can also occur as a result of broken test leads, high test lead
connection resistances, and pipe resistance to earth if the pipeline is short and well coated.
When measuring a structure-to-electrolyte potential, it may not be immediately apparent that a
high circuit resistance is present. If the voltmeter has an input resistance selector switch, the
existence of a high resistance in the measurement circuit can be identified by switching to a
lower or higher input resistance. If the potential indicated by the voltmeter differs significantly
(i.e., more than 10%) between the two input impedances, then there is a high resistance in the
measurement circuit. Further by knowing the two input resistances and their corresponding
measured voltage, the true potential can be calculated.
[3.3]
where:
Etrue = true potential (V)
K = input resistance ratio Rl/Rh
Rl = lowest input resistance
Rh = highest input resistance
Vl = voltage measured with lowest input resistance
Vh = voltage measured with highest input resistance
For example: If a potential difference (Vl) of –650 mVcse was measured with an input resistance
(Rl) of 1.0 MΩ and a potential difference of –800 mVcse (Vh) was measured with an input
resistance (Rh) of 10 MΩ, then the true potential (Etrue) would be calculated as follows:
CP 2 | Technician
©NACE International
Field Measurements
3-9
In addition, the total circuit resistance (Rt) can be determined:
[3.4]
Rt = 10.3 MΩ
This means that the resistance in the measuring circuit, excluding the meter resistance is:
Rcirc = Rt – Rm
[3.5]
= 10.3 MΩ – 10 MΩ
Rcirc = 0.3 MΩ or 300,000 Ω
As charges flow in the earth to or from the pipe and
with earth’s resistance, voltage drops occur in the earth
creating a voltage gradient around the pipe as
illustrated for a bare pipe in Figure 3.7.
The radial lines denote the current paths while the
lines perpendicular to the current lines represent the
equipotential surfaces created by the current. The
equipotential surfaces, which are perpendicular to the
current paths, are not evenly spaced but increase with
distance away from the pipe because each successive
shell of earth has a larger surface area and hence a
lower resistance.
Figure 3.7 Voltage and Current Lines
around a Bare Pipeline Receiving
Cathodic Protection Current
If a potential measurement is taken with the reference
electrode located at A and the current direction is
Source: Parker, Marshall and Peattie, Edward,
Pipeline Corrosion and Cathodic Protection, 3rd
toward the pipe (as would be the case in cathodic
Edition, Gulf Publishing Co., Houston, TX, p.25
protection), then there is a voltage drop (Vs) in the soil
between the reference electrode and the pipe surface.
The soil at point A is more positive than the soil immediately adjacent to the pipe surface. If the
potential difference between adjacent equipotential surfaces is 10 mV, the voltage drop in the
soil between the pipe surface and the reference location would be 10 lines  10 mV/ line = 100
mV. The soil at the pipe surface is –100 mV with respect to the soil at the reference electrode.
©NACE International
CP 2 | Technician
3-10
Field Measurements
For example, if the polarized potential (Ep) of the pipe is –790 mVcse the voltmeter will read:
Vm = –790 mVcse + (–100 mV)
Vm = –890 mVcse
Thus, there is a 100 mV error in the measurement that makes it appear as if the pipe is 100 mV
more negative than it really is.
For a well coated pipeline, the equipotential field forms in close proximity to the holidays as
shown in Figure 3.8 and Figure 3.9.
Figure 3.8 Current and Voltage Lines around a
Holiday on a Coated Pipeline
Figure 3.9 Current and Voltage Lines in
Immediate Vicinity of a Holiday
On a coated pipeline, most of the voltage drop is concentrated in the immediate vicinity of the
holiday. Typically 95% of the total voltage drop between the reference and the steel exposed at
the holiday is found within about 10 diameters of the holiday (i.e., 10 d). For a 1 cm diameter
holiday, 95% of the voltage occurs within a radius of 10 cm from the holiday.1
3.3.2 Voltage Drop Errors in the Potential Measurement Due to Current in the
Pipeline
Voltage drops also occur in current-carrying metal paths and if the connection to the pipe is
remote from the location of the reference electrode, as shown in Figure 3.10, there will be a
voltage (IR drop) error (Vp) in the potential measurement due to the current in the pipe (Ip) and
the pipe resistance (Rp). (See Chapter 6 for close interval potential surveys.)
1.
Gummow, R.A., The Cathodic Protection Potential Criterion for Underground Steel Structures, NACE International, CORROSION/93, Paper No. 564, p. 5.
CP 2 | Technician
©NACE International
Field Measurements
3-11
Figure 3.10 Voltage Drop in a Pipeline Carrying Current
3.3.3 Voltage (IR) Drop Determination and Correction
Potential measurements can include errors caused by voltage (IR) drops in the soil and/or in the
structure itself. The magnitude of these voltage (IR) drop errors must be determined and the
readings corrected.
Methods that can be employed to minimize these errors include:
•
•
•
Interrupt all influencing current sources and measure the potential before significant depolarization occurs (instant OFF potential).
Place the reference electrode close to the exposed metal surface. On a coated structure, the
reference is placed next to a coating fault (holiday).
Use of coupons to replicate a coating fault.
If the current and/or the resistance of its path has been determined to be low, this error may be
ignored. An example of such a case may be in the low resistivity of seawater.
3.3.3.1 Current Interruption
An effective method of eliminating voltage (IR drop) errors
is by making the current zero thereby making the voltage (IR
drop) error equal to zero. Typically, zero voltage (IR drop)
error is achieved by temporarily interrupting the current
and instantly reading the structure potential. This potential
must be read quickly since the structure will begin to
depolarize with time (see Figure 3.11).
However, there may be significant spiking of the potential
due to inductive and capacitive effects associated with the
interruption of the cathodic protection current. The
“instant-off” potential should be measured after this spiking
has decayed (see Figure 3.12) but before significant
depolarization of the structure has occurred.
Time
(Milliseconds)
Figure 3.11 Waveprint Illustrating
Depolarization During OFF Cycle
©NACE International
CP 2 | Technician
3-12
Field Measurements
Figure 3.12 Structure-to-Electrolyte Potential
“Waveprint”Illustrating the “Spike” During Current Interruption
To measure the “OFF” structure-to-electrolyte potential, all sources of current influencing the
area under investigation must be interrupted. This can be accomplished by installing a current
interrupter in all current sources influencing the system in the area under investigation. The
interrupters are essentially a mechanical or electronic relay connected to a very precise
chronometer. Multiple units can be synchronized to cycle in unison, allowing multiple current
sources to be interrupted simultaneously, effectively removing all current from the structure at
the same instant. With no current, the voltage (IR drops) go to zero and the measured potential
is the polarized potential of the pipeline.
Potential Measured (Em) = Ecorr + Polarization + voltage (IR Drop) error
[3.6]
Em = Ecorr if voltage (IR drop) = 0
[3.7]
This is illustrated in Figure 3.13.
Figure 3.13 Elimination of IR Drop by Current Interruption
and Subsequent Depolarization
CP 2 | Technician
©NACE International
Field Measurements
3-13
This technique has the added advantage that the voltage (IR drop) error in the circuit’s metallic
path is also eliminated. On structures having multiple current sources influencing the potential
reading it may be difficult to interrupt all the sources or to interrupt them simultaneously. Since
voltage (IR drop) error at any given location is the sum of the effects of current applied at all
sources, the total voltage (IR drop) error can be calculated by summing the individual effects.
Interruption cycles vary based upon the type of structure-to-electrolyte potential survey that is
being conducted. Key factors in selecting an interruption cycle include:
•
•
•
•
Minimizing depolarization during the survey
Minimizing depolarization during the OFF period
Maintaining polarization over the duration of the survey project
Ability to measure accurate OFF potential data after the “spike” has dissipated.
Maintaining an 80%/20% or 75%/25% (4:1 or 3:1) “duty cycle” is important to minimize
depolarization during the day and over the duration of the survey project. The duty cycle is the
percentage of ON time to OFF time. An example would be 3 seconds ON and 1 second OFF.
In addition, it is important to turn off the current interrupters at night. This will reduce the
amount of time the current sources are being cycled and help rebuild any polarization which
may have been lost during the day when the current sources were cycling ON and OFF.
Maintaining the synchronization of the current interrupters is accomplished by several means.
Current interrupters available today include quartz crystal timing devices which, once
synchronized together, will maintain the timing for a period of time. Global Positioning
Satellites (GPS) also provide precise timing and is available at no charge to the public. GPSsynchronized interrupters which maintain precise timing indefinitely as they “resynchronize”
themselves at predetermined times throughout the day are available. Note that some will fail in
the on position if they lose their satellite signal and then restart when it comes back. Unless
there is a stationary datalogger monitoring the data, this event can go unnoticed and true
polarized potentials will not be taken.
One method of verifying interruption synchronization and of checking the magnitude and
duration of the inductive/capacitive spike is by recording a “wave print” or waveform. A wave
print is a graph of hundreds or thousands of structure-to-electrolyte potentials recorded every
second for the duration of an interruption cycle. The data is graphed versus time and can be
reviewed in the field to review:
•
•
•
•
Interrupter synchronization (see Figure 3.14)
Depolarization during the OFF period (see Figure 3.11)
Spiking magnitude and duration (see Figure 3.12)
Dynamic stray currents (see Figure 3.15)
©NACE International
CP 2 | Technician
3-14
Field Measurements
Figure 3.14 Waveprint Illustrating Non-Synchronized Current
Interrupters
Figure 3.15 Waveprint Illustrating Dynamic Stray Current
Interference
3.3.3.2 Reference Electrode Near the Structure
To minimize the voltage (IR drop) error associated with the electrolyte, the reference electrode
should be positioned as near to the structure as possible. This may not eliminate all voltage (IR
drop) errors.
When dealing with underground piping or tanks, the ideal position of the electrode would be at
the bare structure surface or at a coating holiday. There are times, however, when the electrode
is purposely placed at some distance from the structure; this is discussed later under the section
“Remote Earth.”
CP 2 | Technician
©NACE International
Field Measurements
3-15
Inside water storage tanks, the electrode should be positioned as close to the wall of the tank as
possible. The same is true for waterfront and offshore structures; the electrode should be as
close to the piling as possible. In moving water, the electrode may swing about, so some
structures are equipped with guide wires or perforated plastic ducts to restrict the movement of
a portable electrode.
For on-grade storage tanks, data is frequently taken around the periphery of the tank. This may
not yield accurate data about the potentials under the tank bottom, particularly if the anodes are
in a ring around the tank or the tank is large in diameter. Stationary reference electrodes under
the tank bottom yield the best data. Alternately, if a perforated plastic tube is installed under the
tank and filled with water, a reference electrode can be pulled through it and potentials
measured at intervals underneath (see Figure 3.16).
Figure 3.16 Reference Cell Under AST
Placing the reference electrode close to the structure minimizes the voltage (IR-drop) error in
the electrolyte in proportion to the electrode’s closeness of the electrode to the surface.
Unfortunately, for underground structures, this is not a practical technique except at points of
structure-to-soil entry and exit. Also, on coated structures, the electrode cannot normally be
placed any closer to the structure than a point immediately outside the coating, and it is across
the coating where much of the voltage (IR) drop exists.
©NACE International
CP 2 | Technician
3-16
Field Measurements
3.3.3.3 External CP Coupons and Probes
Coupons
Coupons can be used judiciously, particularly when accompanied
by other engineering tools and data, to evaluate whether cathodic
protection (CP) at a test site complies with a given criterion.
Coupons may be used on a wide variety of structures and offer an
advantage in the following conditions.
•
•
•
•
•
Multiple influencing rectifiers
Multiple pipelines or complex underground structures
Direct connected sacrificial anodes
Stray (telluric) current
Localized corrosive areas
•
•
Areas shielded from surface measurements
AC assessments
Figure 3.17 External CP
Coupon
A CP coupon is a metal sample meeting the following conditions. (Figures 3.17 & 3.18)
•
•
•
•
•
Nominally of the same metal and surface condition as the structure;
Small to avoid excessive current drain on the cathodic protection system;
Placed at structure depth in the same backfill as the structure;
Prepared with all mill scale and foreign materials removed from the surface; and
Placed at a known location of an ineffective coating where applicable.
(See ANSI/NACE Standard SP0104 for more information on coupons2.)
Figure 3.18 Special Test Station for Monitoring
Cathodic Protection
2.
ANSI/NACE Standard SP0104, “The Use of Coupons for Cathodic Protection Monitoring Applications” (Houston, TX:
NACE).
CP 2 | Technician
©NACE International
Field Measurements
3-17
Measurements on coupons can include:
1. Structure-to-Electrolyte Potentials (reference electrode located close to coupon or in soil
tube)
• Native (Free Corroding) - before connecting to a CP structure)
• Initial - after connecting but before CP
• ON - connected to a CP structure - may include a voltage (IR) error
• Instant OFF - immediately after disconnecting the coupon from CP
• Depolarized - after leaving disconnected
2. Current
• Value
• Direction
• Current density (calculated)
3. Corrosion Rate (measured with Electrochemical Impedance Spectroscopy (EIS), Linear
Polarization Resistance (LPR), Electrical Resistance (ER))
Caution should be exercised in using a free corroding coupon potential after a long exposure.
From an ongoing study of a total 483 free corroding 10 cm2 coupons, a significant potential
change was noted over a period of 10 years such that:
•
•
•
•
174 (36%) shifted electropositively by more than 100mV;
77 (16%) shifted electronegatively by more than 100mV;
146 (30%) shifted between +/- 100mV; and
86 (18%) had no potential reading.
The actual potentials are shown in Figure 3.19.
Figure 3.19 Potential Change of Free Corroding Coupon ~10
years after Installation
Source: Kuwait Oil Company
©NACE International
CP 2 | Technician
3-18
Field Measurements
Coupon potentials measured to a nearby reference electrode may not be identical to those
measured between the structure and a surface reference electrode as the latter can be affected by
many factors such as:
•
•
•
Different electrolyte conditions
• Soil type, moisture, chemistry, resistivity, temperature, oxygen etc.
• Resulting in different reactions and products
Number and size of exposed metal surfaces (coating holidays)
Coating conductance variations
•
•
•
•
•
Current variations around and along the structure
Stray current
Circulating/long-line current
Bimetallic or different alloy structure composition
Permanently attached sacrificial anodes.
As a result, the structure potentials are a weighted average of all areas exposed to different
conditions. In contrast, the coupon potential represents a single, small area of exposed metal to
the electrolyte at a given location. That is, the coupon may be a better indication of the status of
CP at that location being independent of these factors. However, neither the coupon or structure
potential measurements are necessarily in error, only that the factors affecting the potentials in
each case must be understood.
As the coupon essentially receives the same CP current density as the structure, it can
demonstrate whether the CP system has the capacity to provide CP to a coating holiday of
equivalent size of the coupon at that location.
A coupon has preferably two insulated test leads brought above ground of which one is
connected to a pipeline test lead under operating conditions. The other test lead is used for
potential measurements. The coupon receives CP current via the pipeline and represents a
coating holiday on the pipeline at the test site. A second coupon may be left exposed without CP
for a free corroding potential.
The voltmeter used must be of a high impedance as otherwise the polarization of the coupon can be
drained via the measuring circuit. The time of measurement should also be limited to 3 seconds to
avoid causing depolarization of the coupon.
Advantages of a coupon include being able to measure a polarized coupon-to-electrolyte
potential, free of voltage drop, with a minimum of specialized equipment (without interruption
of the CP system), personnel, and travel; and may provide a more comprehensive evaluation of
the polarization at the test site than conventional structure-to-electrolyte potential
measurements under the influence of the factors listed above. A disadvantage is that it can have
high initial costs to install coupons, especially for existing structures and are limited to
measurements at the coupon location.
Two test procedures to assess the adequacy of cathodic protection on metallic structures are
suggested as guides but others can be employed.
CP 2 | Technician
©NACE International
Field Measurements
3-19
Coupon Test Method 1 – Polarized Structure-to-Electrolyte Potential
A polarized potential of the coupon is measured with respect to either a stationary reference
electrode located near the coupon or to a portable reference electrode placed inside the
nonmetallic coupon station housing and in contact with the internal soil column near the
coupon. The connection to the structure CP system (test lead) is quickly interrupted and an
instant OFF potential is recorded to compare to the CP polarized potential criterion (-0.850
VCSE) (NACE SP0169).
Depending on the coupon size and current, the coupon current and polarity can be
measured with a zero-resistance ammeter, current clip-on ammeter, appropriately sized
shunt or resistor permanently placed in series with the coupon lead. Typically, the current to
be measured is very small. A discharge of current from the coupon either questions the
validity of the test or it may indicate a corresponding discharge of current from the pipeline.
Coupon Test Method 2 – Polarization Measurement
The amount of cathodic polarization can be determined by comparing the polarized
coupon-to-electrolyte potential with a subsequent depolarized potential, after the coupon
has been left disconnected from the pipeline. At least 100 mV of cathodic polarization decay
will satisfy the CP criterion (NACE SP0169).
A high impedance recording voltmeter may be set to provide a record of the polarization
decay. Again, note that the instrument itself may cause accelerated depolarization. It is not
necessary to allow the coupon to fully depolarize if the 100-mV criterion can be satisfied
before this occurs.
Errors in the potential measurement can occur from improper installation allowing voids to
exist at the coupon surface, allowing greater than normal oxygen to access from the surface,
high reference electrode contact (e.g. dry soil in tube if used), broken or high resistance wire
contacts and low impedance voltmeters depolarizing the coupon.
Electrical Resistance Probes
An “Electrical Resistance Probe” monitors metal consumption by measuring the change in
electrical resistance (ER) of an element with time. As the element corrodes, its cross-section
reduces causing an increase in resistance. Since temperature affects electrical resistivity,
temperature compensation is needed. The exposed resistive element is mounted together with a
reference resistor, which is isolated from the electrolyte but is at the same temperature and the
resistances are compared. Since the resistance ratio between the exposed and reference elements
at equal temperatures is the same, temperature is no longer a factor.
Real time corrosion rates can be measured allowing the detection of a sudden change in the rate.
A limitation is that the ER method allows only the measurement of uniform corrosion but
cannot identify localized corrosion or pitting.
An assessment of cathodic protection can be made with ER probes installed in the soil in areas
of anticipated maximum exposure.
Dynamic Stray Current Testing with Coupons/Probes
Although the instant-OFF potential of the coupon is not expected to be affected by the dynamic
stray current, the ON potential when connected to the structure will be influenced thus the
©NACE International
CP 2 | Technician
3-20
Field Measurements
voltage (IR) error should be determined under quiet stray current conditions. A monitoring
program should, however, include the measurement of the ON potential and coupon current
over time.
An assessment of CP under dynamic stray current conditions can be made with coupons and/or
soil ER corrosion probes if installed in areas of anticipated maximum exposure. When using
coupons, it is important to measure instant-OFF potentials with time, so different stray current
conditions are monitored. If measuring ON structure-to-electrolyte potentials only, the voltage
(IR) error in the ON potential must be removed before using the result as a criterion.
Coupons can be designed in such a way that the difference between ON and OFF potentials are
very low because reference electrodes are located close to them or a nonmetallic tube is used as
a salt bridge. These coupons are known as “IR Free” or concentric. This voltage (IR) drop can be
measured by interrupting the coupon connection to the structure. If this value is not significant,
the ON potential may be considered as a polarized potential. Long time potential measurements
are necessary to assess polarization criteria for different conditions during a typical day.
3.4 Current Measurement
Measuring current in the cathodic protection circuit is a necessary procedure in evaluating
system performance. Typical current measurements are:
•
•
•
•
galvanic anode current
impressed current system output currents
current in the structure
bond current
Both direct and indirect methods of current measurement are available. A direct measurement
involves inserting an ammeter into the cathodic protection circuit as illustrated in Figure 3.20.
3.4.1 Using an Ammeter to Measure Current
An electronic ammeter is typically composed of a voltage measuring device that measures the
voltage drop across a low-resistance internal shunt. Ideally, an ammeter should have a low input
resistance compared to the circuit resistance (i.e., Rm << Rcp) to prevent measurement error.
Figure 3.20 Measurement of CP Current Using an
Ammeter
CP 2 | Technician
©NACE International
Field Measurements
3-21
For example, in Figure 3.20 from Ohm’s law:
[3.8]
but with the ammeter inserted in the series circuit, the current measured on the ammeter (Im) is
given by:
[3.9]
Hence, the measured current (Im) will be less than Icp, depending on the resistance of the
ammeter.
In many digital multimeters when the mA
scale is selected, the ammeter circuit has an
input resistance of several ohms. This can
lead to significant errors if the ammeter is
used to measure the current from a galvanic
anode.
Even if a 10 A or 20 A scale is chosen, the
input resistance, which may be as low as 0.1Ω,
may still be too high to produce an accurate
current measurement in some circumstances.
Figure 3.21 Current Measurement in Parallel
For instance, if the ammeter is placed in
Drain Conductors
series with a negative drain cable in a parallel
set of drain cables, as shown in Figure 3.21, an appreciable error can occur.
If the shunt resistance inside the ammeter is 0.01Ω and the resistance of the negative return
cable is 0.01Ω, insertion of the ammeter has doubled the negative return resistance in that
circuit and possibly reduced the return current (I1) by half.
In both the above examples, a more accurate method is to install an appropriately rated shunt
permanently in each circuit, simply measure the voltage drop across the shunt and calculate the
current (see the Shunt Table in the Reference Sheets provided at the back of the course manual).
3.4.2 Using a Shunt to Determine Current Magnitude
In the parallel negative drain cable example, a shunt of the same rating, hence the same
resistance, should be installed in series with each negative drain cable as illustrated in Figure
3.22.
©NACE International
CP 2 | Technician
3-22
Field Measurements
Figure 3.22 Use of Shunts for Current Measurements in Parallel
Conductors
When selecting a shunt, its current rating must exceed the anticipated circuit current, and the
millivolt drop at the anticipated operating current should be easily measurable on a standard
digital multimeter.
For instance, if a shunt rated at 5 A, 50 mV is placed in series with a galvanic anode having an
output of 5 mA, the voltage drop across the shunt will be:
Vshunt = Icp  Rshunt
[3.10]
Vshunt = 0.05 mV
This small shunt voltage drop is below the resolution of most digital voltmeters used in the field.
For a 5 mA current, a shunt resistance of at least 1Ω is more appropriate (See the Shunt Table in
the Reference Sheets provided at the back of the course manual.)
CP 2 | Technician
©NACE International
Field Measurements
3-23
3.4.3 Zero Resistance Ammeter
Sometimes the currents are so small (e.g., < 0.1
mA) they cannot be measured accurately without
using very-high-resistance shunts, which can alter
the current magnitude because of their resistance.
An example is the measurement of coupon
current as illustrated in Figure 3.23.
If the coupon has a surface area of 10 cm2 and a
current density of 10 A/cm2 the coupon current
(Icp) would be:
Figure 3.23 Current Measurement Using a Zero
Resistance Ammeter (ZRA)
Icpn = iA
[3.11]
where:
i = current density (A/cm2)
A = area (cm2)
Icpn = 10 A/cm2 or 10 cm2
Measurement of such a small current with an ammeter would introduce a high resistance into
the circuit as would a shunt since a resistance of 100Ω is required to measure in the 10 mV
range. Under these circumstances, a zero resistance ammeter (ZRA) should be used.
To avoid altering steady state conditions, connect the ZRA in parallel with the terminals on the
test post before opening the link.
3.4.4 Clamp-On Ammeter
A relatively noninvasive method of measuring current in a conductor is by using a clamp-on
ammeter as illustrated in Figure 3.24.
Figure 3.24 Using a Clamp-On Ammeter to Measure Current
©NACE International
CP 2 | Technician
3-24
Field Measurements
The clamp-on ammeter contains a “Hall effect” device that produces a voltage output
proportional to the strength of the magnetic field, which is proportional to the magnitude of the
current in the conductor. The clamp on ammeter must be installed around a single conductor and
should be centered around that conductor. Accuracy of the clamp-on ammeter diminishes at
currents of a few mA. When there are multiple current-carrying conductors in a congested area,
the accuracy is reduced if there is magnetic interference from adjacent conductors.
3.4.5 Pipeline Current Measurements
3.4.5.1 Clamp-On Ammeter
An illustration of the use of clamp-on ammeters is given in Figure 3.25.
Figure 3.25 Pipe Current Measurement Using Sensing Loop
and Swain Meter
Source: Swain, W.H., Clamp-On Ammeters Can Watch Cathodic Protection Current Flow,
Pipe Line & Gas Industry, March 1998, p.38
3.4.5.2 2-Wire Line Current Test
Current in a pipeline can be measured by means of a test (current span) station calibrated test
station such as shown in Figure 3.26 or by using test stations and aboveground appurtenances as
a temporary current span test station. In an IR-drop test, the pipe simulates a low-resistance
shunt. When properly calibrated, a voltmeter can be used to measure a voltage drop between the
two wires or connection points to the pipe. Using Ohm’s Law, the current in the pipeline steel
can be calculated.
A 2-wire current span test station can be used where a known length of pipeline and the
diameter and wall thickness or the weight per foot are known. The current in the pipe span can
be calculated by measuring the voltage drop across the span, determining the resistance of the
span from a pipe table, and using Ohm’s Law as you would with a shunt. Figure 3.26 shows the
test setup to measure the mV drop in the section of pipeline.
Table 3.1 provides some resistance values for common pipe sizes. The section of pipe must be
continuous with the same diameter and wall thickness without attachments through the pipe
span to be used.
CP 2 | Technician
©NACE International
Field Measurements
3-25
Figure 3.26 2-Wire Line Current Test
Because the voltage drop across a pipe span is relatively small, with earlier instruments it was
necessary to correct for the voltage drop in the test leads caused by the current drawn by the
meter. However, with the high-input resistance meters available today, this correction is not
necessary.
For example, if the voltage drop across a 61-m (200-ft) span of 762 mm (30-in) pipe weighing
176.65 kg/m (118.7 lbs/ft) is 0.17 mV, then current is calculated as follows:
Pipe resistance/ft from Table 3.1 = 8.01 /m (2.44  /ft)
= 0.00000801 /m (0.00000244 /ft)
Total resistance = 61 m x 0.00000801 /m
= 0.000488 
OR = 200 ft x 0.00000244 /ft
= 0.000488 
Measured voltage drop = 0.17 mV
Current (I) = V/R = 0.00017V/0.000488= 0.348 A
©NACE International
CP 2 | Technician
3-26
Field Measurements
Table 3.1: Table of Pipe Resistances - Steel Pipe Resistance*
Pipe Size
in.
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
32
34
36
Outside
Diameter
Wall Thickness
Weight
Resistance
in.
cm
in.
cm
lb/ft
kg/m
/ft
/m
2.35
4.5
6.62
8.62
10.75
12.75
14.00
16.00
18.00
20.00
22.00
24.00
26.00
28.00
30.00
32.00
34.00
36.00
5.97
11.43
16.81
21.89
27.31
32.38
35.56
40.64
45.72
50.80
55.88
60.96
66.04
71.12
76.20
81.28
86.36
91.44
0.154
0.237
0.280
0.322
0.365
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.39
0.60
0.71
0.82
0.93
0.95
0.95
0.95
0.95
0.95
0.95
0.95
0.95
0.95
0.95
0.95
0.95
0.95
3.65
10.8
16.0
28.6
40.5
46.6
54.6
62.6
70.6
78.6
86.6
94.6
102.6
110.6
118.7
126.6
134.6
142.6
5.43
16.07
28.28
42.56
60.27
73.81
81.26
93.16
105.07
116.97
128.88
140.78
152.69
164.59
176.65
188.41
200.31
212.22
76.2
26.8
15.2
10.1
7.13
5.82
5.29
4.61
4.09
3.68
3.34
3.06
2.82
2.62
2.44
2.28
2.15
2.03
256.84
87.93
46.87
33.14
23.39
16.09
17.36
15.12
13.42
12.07
10.96
10.04
9.25
8.60
8.01
7.48
7.05
6.66
*Conversions: 1 in. = 2.54 cm 1 ft = 0.3048 m
Based on steel density of 489 lbs/ft3 (7832 kg/m3) and steel resistivity of 18 μ-cm.
Refer again to Figure 3.26. Note the meter is showing a positive indication. This means the
current is entering the meter on the positive terminal. The positive terminal is connected to the
west end of the span. Since the meter is in parallel with the span, current on the pipe is from
west to east.
The accuracy of this test method depends greatly on accurate knowledge of the dimensions of
the pipe. Should there be an odd-sized joint within the span, or some appurtenance such as a
valve, the calculated resistance will not be correct. The 4-wire test method overcomes these
difficulties.
3.4.5.3 4-Wire Line Current Test
Pipeline current can also be measured using the four-wire span illustrated in Figure 3.27. For
accurate measurement, the span is calibrated by injecting a known DC test current through the
pipe using the outside test leads (1) and (4) and measuring the resulting voltage drop across test
leads (2) and (3).
CP 2 | Technician
©NACE International
Field Measurements
3-27
Figure 3.27 Calibrating a Pipeline Current Span
The resistance of the pipe between test leads (2) and (3).
Is calculated from Ohm’s law:
[3.12]
The result can be anticipated prior to the test by referring to Table 3.1.
Attention to polarity is important in this measurement since there will probably be a residual
current during the test, and the test current may cause a reversal in the voltage drop polarity.
For example:
V2-3 = +21 mV (before test current applied)
V2-3 = –19 mV (after test current applied)
It =10 A
The resistance (Rpipe) of the pipe section being tested is:
The calibration factor is calculated as follows:
[3.13]
©NACE International
CP 2 | Technician
3-28
Field Measurements
where:
K = calibration factor of pipe section (A/mV)
Itest = test current applied to section (A)
Etest = E with current applied – E with no current applied (mV)
Therefore the current calibration factor is:
During the test there was residual current in the pipe from another source other than the test
current which magnitude is:
with a direction from 2 to 3 in Figure 3.27.
Normally, if the pipeline operating temperature is stable, this need only be done once as the
calibration factor will remain the same for subsequent tests at the same location. On pipelines
where the temperature of the pipe changes considerably (with accompanying changes in
resistance), more frequent calibration may be necessary.
Once the calibration factor is known, the normal current magnitude can be calculated. First,
measure the voltage drop in mV across the measuring span (with the test equipment removed
between 1 and 4 in Figure 3.27)using the inside test wires. This voltage drop is due to normal
pipeline current.
Calculate current by multiplying the calibration factor by the voltage drop measured above:
[3.14]
where:
I = pipeline current (A)
K = calibration factor of pipe (A/mV)
EmV = voltage drop of pipe section (mV)
The polarity of the voltage drop will determine the direction of current.
•
•
If the voltage drop reading is positive, then the direction of current is from the positive to
the negative terminal of the voltmeter.
If the reading is negative, then the direction of current is from the negative to the positive
terminal.
Most digital meters will not read below 0.1 mV. If readings below 0.1 mV are anticipated, or if a
zero reading is obtained during a test, a more sensitive meter must be used.
CP 2 | Technician
©NACE International
Field Measurements
3-29
3.4.6 Coating Resistance Calculations
Coating resistance measurements are a means of establishing a coating’s ability to provide a
dielectric barrier between the structure and the environment. The better barrier a coating
provides, the higher the coating resistance. The coating resistance is simply the resistance of the
structure to the environment multiplied by the surface area of the structure. Units are therefore
Ω-m2 (Ω-ft2). Coating resistance measurements years apart can reveal the long-term
performance of a coating and if anything has occurred that detrimentally affected the overall
structure coating (e.g., electrical shorts, construction damage, and abnormal soil stress).
The resistance of a pipe coating can be determined by impressing a current on to a known pipe
surface area and measuring the change in potential due to the current being impressed as
illustrated by Figure 3.28.
Figure 3.28 Set-Up for Coating Resistance Measurement
The current being impressed (IC) is determined by measuring the change in the current in the
pipeline at each end of the section (ΔITS1, ΔITS2) due to the test and calculating the difference
between these values which is the current pickup in that section of pipeline (Equation 3.15).
[3.15]
The potential change (ΔEave) due to this current being applied is the average shift between the
ON and OFF potentials in the pipeline section under test (ΔETS1, ΔETS2 etc.). Equation 3.16
shows the average potentials if potentials are taken at two locations. If potentials are taken at
intervals through the section, then all must be averaged.
[3.16]
The pipe-to-earth resistance (coating resistance (RC)) is calculated by Equation 3.17.
©NACE International
CP 2 | Technician
3-30
Field Measurements
[3.17]
This is the total resistance of the pipe surface area (Apipe) of the pipe section under test
(Equation 3.18). The area of the pipe surface is calculated from the outside diameter (d) and the
length of the pipe section (L).
[3.18]
To be able to compare it with other coatings the specific coating resistance of a unit area (rC) of
coating is determined by equation 3.19.
[3.19]
The coating effectiveness may be defined in terms of conductance (Gpipe) of the pipe section
which is the inverse of resistance (Equation 3.20) or specific conductance (gC) in terms of a unit
area of coating which is the inverse of specific resistance (Equation 3.21).
[3.20]
[3.21]
See NACE TM0102 “Measurement of Protective Coating Electrical Conductance on
Underground Pipelines” for further information.
EXAMPLE:
Calculate the coating resistance and conductance for a pipeline section as follows.
Pipe Outside Diameter (d) = 610 mm (24 inches) Length of Pipe Section (L) = 1,609 m (5280 ft)
The data in italics in the table was obtained in the field and the regular font was calculated from
the above equations as referenced in the table.
CP 2 | Technician
©NACE International
Field Measurements
3-31
Factor
TS1
TS2
IONTS
3.00 A
2.80 A
IOFFTS
0.20 A
0.10 A
DITS
2.80 A
2.70 A
Pipe Section
(metric)
Pipe Section
(Imperial)
= 2.80 - 2.70
= 0.10 A
= 2.80 - 2.70
= 0.10 A
Apipe
(Eq 3.16)
rC
(Eq 3.17)
= 1.10 + 0.85
2
= 0.975 V
= 0.975
0.10
= 9.75 
= π .610 x 1609
= 3,080 m2
= 9.75 x 3080
= 30,030 Ω-m2
= 1.10 + 0.85
2
= 0.975 V
= 0.975
0.10
= 9.75 
= π 2 x 5280
= 33,158 ft2
= 9.75 x 33158
= 323,291 Ω-ft2
GC
(Eq 3.18)
=
= 0.103 Siemens (S)
=
= 0.103 Siemens
(S)
gC
(Eq 3.19)
=
= 0.0000333 S/m2
(33.3 μS/m2)
=
= 0.00000309 S/ft2
(3.09 μS/ft2)
IC
(Eq 3.13)
EONTS
-2.00 V
-1.70 V
EOFFTS
-0.90 V
-0.85 V
ETS
1.10 V
0.85 V
Eave
(Eq 3.14)
RC
(Eq 3.15)
3.5 Current Requirement Tests
When a structure is in place in its final configuration, it is possible to perform current requirement
tests to determine the current needed for cathodic protection. Such tests have the advantage of
producing data on the actual structure and its environment and do not involve assumptions as to
effectiveness of the protective coating and other factors. Structures which have been designed for the
application of cathodic protection can be tested in their entirety or broken down into sections.
©NACE International
CP 2 | Technician
3-32
Field Measurements
Current requirement testing involves installation
of either a permanent or test anode system. The
purpose is to introduce current into the earth at
the site where the permanent cathodic protection
system (anode bed) will be located. For large
structures, a representative area can be chosen for
the initial test phase. A suitable power supply
(batteries, test rectifier, or motor generator
system) is then connected between the structure
and test anode bed (groundbed) as illustrated in
Figure 3.29. Test current is applied between the
anode bed and the structure and the changes in
potential of the structure are measured.
Figure 3.29 Test Circuit for Current Requirement
Test
With this circuit, controlled amounts of current can be applied to the structure from the anode
until the desired potentials are obtained.
The potential measured includes the following:
•
•
The potential between the structure and the reference electrode
A voltage (IR drop) produced between the point in the electrolyte where the reference electrode is located and the structure
Calculation:
[3.22]
where:
Itest = Test current applied to structure (A)
Ireq = Estimated additional current requirement (A)
Eptest = Polarization from test (V) [EOFF – EINITIAL]
Epreq = Polarization required (V)
= [0.850 V – EINITIAL] for -850 mVCSE polarized potential criterion
or
0.100 V (100 mV) for 100 mV polarization criterion
The formulas used for these calculations consider:
The value of resistance producing a voltage (IR drop)
R = (EON - EOFF)/ION
CP 2 | Technician
[3.23]
©NACE International
Field Measurements
3-33
The voltage (IR) drop can be calculated for other intermediate levels of current (I1) using an
average value for R:
Voltage (IR) drop = I1 x R
[3.24]
Following is an example of a current requirement calculation:
1. Static structure-to-electrolyte potential = –0.645 VCSE
2. Desired polarized structure-to-electrolyte potential = –0.850 VCSE
3. Test current = 50 mA (0.050 A)
4. Polarized potential due to test current = 0.775 VCSE
From Equation 3.25:
[3.25]
3.6 Electrical Isolation
3.6.1 Problems
Electrical isolation is important to the success of cathodic protection except where the system
being protected cannot be electrically isolated and the CP system is designed to take this into
account. In an isolated system, the failure of the CP system to maintain a satisfactory level of
cathodic protection might be caused by an electrical short to another metallic structure
including other pipelines, power grounds, station grounding, etc.
An isolation can be rendered ineffective by a fault in the isolating fitting or by a metallic bypass
around the isolation.
3.6.2 Locating the Problem
There are many methods to locate an electrical isolating device and/or tests to determine if the
device is functioning properly:
•
•
•
•
•
•
•
•
Pipeline/cable locators
Isolation testing instrument
Structure-to-electrolyte potential
Interrupted structure-to-electrolyte potential
DC line current measurements
Fixed cell to moving ground
Current response test
Isolation resistance test.
©NACE International
CP 2 | Technician
3-34
Field Measurements
Each technique has advantages and disadvantages including whether or not the particular test
can be used under the circumstances and if the test is conclusive under those circumstances.
For more information on isolation testing consult NACE SP0286 “Electrical Isolation of
Cathodically Protected Pipelines”.
3.7 Corrosivity Evaluations
Electrolyte resistivity and pH are two of the factors that determine the corrosivity of an
electrolyte. Electrolyte resistivity is a measure of the ability of the electrolyte to support
electrochemical corrosion, and electrolyte pH is a measure of the acidity or alkalinity of the
electrolyte. Both influence the corrosion rates of metals placed underground or that are
submerged.
Resistivity and pH are not the only factors affecting corrosion since total acidity, aeration,
moisture content, soil type, soil permeability and composition, and heterogeneity play a role in
determining the corrosivity of a given soil. Because of the natural heterogeneity of soil, there is
no single value of soil resistivity that represents a particular site. Instead, for a given site a range
of values are measured and calculations made to determine the “layer” resistivities.
3.8 Soil Resistivity Testing
3.8.1 Purposes
Soil resistivity is one factor that can determine the corrosivity of an environment. Resistivity is
also essential in the design of cathodic protection systems.
3.8.2 Measurement Techniques
Various means of measuring electrolyte resistivities are used. These include the Wenner FourPin Method as described in ASTM Test Method G57, Collins Rod, and electromagnetic
induction methods.
3.8.2.1 Wenner Four-Pin Method
The four-pin resistivity method developed by
Wenner involves the use of 4 pins driven into the
ground (Figure 3.30). Current is applied to the
outer pins, and the voltage between the inner
pins is measured. The resistivity is a function of
the current, voltage, and spacing of the
electrodes (which is equal to the depth of the
test). The current is usually applied using an
instrument that supplies alternating current;
otherwise, polarization effects occur at the
electrodes that can alter the reading. If a DC
current is used, “instant” current and potential
measurements must be taken. Stray earth
currents can also affect the readings if these
effects are not separated from the data.
CP 2 | Technician
Figure 3.30 Wenner Four-Pin Soil Resistivity
Measurement
©NACE International
Field Measurements
3-35
The first step is to determine the resistance in ohms between the center pair of pins. Using the
commercially available equipment detailed above, the resistance is indicated directly by the soil
resistance meter. If the pin depth is insignificant with respect to the pin spacing (depth <5% of
pin spacing), the resistivity is calculated using Equation 3.26.
[3.26]
Where:
ρ – resistivity (Ω-cm)
π – pi constant (=3.1416…)
a – Spacing of the pins (cm)
b – depth of the pins (cm)
R – resistance (Ω)
If the spacing is measured in feet, a conversion factor of 191.5 can be used that includes the
conversion of feet to cms and 2 as in Equation 3.27.
 = 191.5 a R
[3.27]
Where:
ρ – resistivity, Ω-cm
191.5 = Factor (= 2 π 30.48 cm/ft), cm/ft
a – inside pin spacing, ft
R – resistance, Ω
For Example:
Where the inner and outer pin spacings are not equal, the resistivity can be calculated by
Equation 3.22 (ASTM 57).
Where:
ρ – resistivity (Ω-cm)
π – Pi constant (=3.1416…)
a – Inner pin spacing (cm)
b – outer pin spacing (cm)
R – resistance (Ω)
Note that if a = b in equation 3.23, it simplifies to equation 3.21.
©NACE International
CP 2 | Technician
3-36
Field Measurements
For Example:
If the resistance reading from the meter is 8Ω at a pin spacing of 3.084 m (304.8 cm), then the
average resistivity to an approximate depth of 3 m is:
 = 2 x  x 304.8 cm x 8 Ω = 15,320 Ω-cm
or, similarly if the resistance reading is 8Ω at a pin spacing of 10 ft, then the average resistivity to
a depth of 10 ft is
 = 191.5 cm/ft x 10 ft x 8 Ω = 15,320 Ω-cm
If the line of soil pins runs closely parallel to a metallic structure, the presence of the structure
may cause the indicated soil resistivity values to be lower than is actually the case. This is
because a portion of the test current will choose the metallic structure path rather than through
the earth. For this reason, this situation should be avoided.
When taking soil resistivity measurements along a structure, it is good practice to place the line
of pins perpendicular to the structure, with the nearest pin no closer than 3 m (15 ft) from the
structure.
3.8.2.2 Layer Resistivity Calculations
The Barnes Layer method of predicting the resistivity of layers is based on the principle that
each layer is a resistor that is in parallel with the other layer resistors (R1, R2, R3 etc.). Therefore,
the parallel resistance equation would apply (Equation 3.28) where RT is the total resistance of
all resistors in parallel.
[3.28]
If only two parallel resistances are involved, the Equation 3.28 becomes Equation 3.29.
[3.29]
If the measured resistance (not resistivity) of the upper layer (R1) and that of the upper and
lower layers combined or the total resistance (RT) is substituted in Equation 3.29, the predicted
resistance of the lower layer (R2) can be calculated from which the resistivity is calculated.
This approach will only apply if the total measured resistance (RT) values become smaller with
depth. In theory this should always occur but because a resistance measurement to deeper
depths requires larger pin spacings, the sample of soil changes horizontally as the depth
increases. If the sample includes an increased amount of high resistivity soil at larger pin
spacings, a higher resistance at a deeper depth might be measured. In this case the measurement
location should be moved.
CP 2 | Technician
©NACE International
Field Measurements
3-37
Figure 3.31 illustrates three different layers of resistance and resistivity. The resistance can be
measured to depths of a1, a2 and the resistivity calculated by Equation 3.26 but the resistance
and resistivity of layers L1, L2 and L3 are desired.
Figure 3.31 Average and Layer Resistivity
The depth of Layer 1 (L1 (cm)) is the same as (a1 (cm)) and the measured resistance (Ra1
(Ohms)) is the same as the layer resistance (RL1 (Ohms)). The resistivity (ρL1 (Ohm-cm)) can be
determined from Equation 3.30 modified from Equation 3.26.
[3.30]
From the measured resistance values for Layer 2, the layer resistance can be calculated from
Equation 3.29 but using the symbols in Figure 3.31, it becomes Equation 3.31.
[3.31]
Where:
RL2 - Resistance of Layer 2 (L2) (Ohms)
R1 - Resistance measured to depth a1 (Ohms)
R2 - Resistance measured to depth a2 (Ohms)
The resistivity (ρL2 (Ohm-cm)) of Layer 2 (L2 (cm)) in Figure 3.31 can then be calculated by
Equation 3.32 modified from Equation 3.26.
[3.32]
Similarly, the resistance of Layer 3 can be calculated by Equation 3.33.
©NACE International
CP 2 | Technician
3-38
Field Measurements
[3.33]
Where:
RL3 - Resistance of Layer 3 (L3) (Ohms)
R2 - Resistance measured to depth a2 (Ohms)
R3 - Resistance measured to depth a3 (Ohms)
The Layer 3 (L3 (cm)) resistivity (ρL3 (Ohm-cm)) in Figure 3.31 can then be calculated by
Equation 3.26.
[3.34]
Example 1
Predict the resistivity of the three layers of soil given the following data using Figure 3.31 as a
reference.
a1 = 160 cmRa1 = 10.0 Ωρa1 = 10,050 Ω-cm
a2 = 320 cmRa2 = 7.4 Ωρa2 = 14,880 Ω-cm
a3 = 480 cmRa3 = 3.1 Ωρa3 = 9,350 Ω-cm
The calculations are given in the table for each layer.
Example 1
Factor
Layer Depth (L)
Layer 1
L1 = a1
= 160 cm
RL1 = Ral
= 10.0 
Layer 2
L2 = a2 – a1
= 320 – 160
= 160 cm
Eq 3.31
Layer 3
L3 = a3 – a2
= 480 – 320
= 160 cm
Eq 3.33
= 28.46 Ω
Eq 3.32
= 5.33 Ω
Eq 3.34
Layer Resistance
(RL)
Layer Resistivity
(L)
ρL1 = ρa1 = 10,050
Ω-cm OR
Eq 3.30
= 2 π 160 x 28.46
= 28,610 Ω-cm
= 2 π 160 x 5.33
= 5,360 Ω-cm
= 2 π 160 x 10.0
= 10,050 Ω-cm
CP 2 | Technician
©NACE International
Field Measurements
3-39
Example 2
Alternately, if using Equation 3.27 and equivalent spacing in feet, predict the resistivity of the
three layers of soil in Ohm-cm given the following data using Figure 3.31 as a reference.
a1 = 5.25 ft Ra1 = 10.0 Ωρa1 = 10,050 Ω-cm
a2 = 10.50 ftRa2 = 7.4 Ωρa2 = 14,880 Ω-cm
a3 = 15.75 ftRa3 = 3.1 Ωρa3 = 9,350 Ω-cm
The calculations using adaptations from Equation 3.27 are given in the table for each layer.
Example 2
Factor
Layer Depth (L)
Layer 1
L1 = a1
= 5.25 ft
RL1 = Ra1
= 10.0 Ω
Layer 2
L2 = a2 – a1
=10.50 – 5.25
= 5.25 ft
Eq 3.31
Layer 3
L3 = a3 – a2
= 15.75 – 10.50
= 5.25 ft
Eq 3.33
= 28.46 Ω
Eq 3.27 modified
= 5.33 Ω
Eq 3.27 modified
= 191.5 x 5.25 x
28.46
= 28,610 Ω-cm
= 191.5 x 5.25
x 5.33
= 5,360 Ω-cm
Layer Resistance
(RL)
Layer Resistivity
(L)
ρL1 = ρa1 = 10,050 Ωcm OR
Eq 3.27 modified
= 191.5 cm/ft x
5.25 ft x 10.0Ω
= 10,050 Ω-cm
3.9 Measuring pH
Electrolyte pH can be measured in several ways. For liquids, pH (litmus) paper or a pH meter
may be used. For soils, a pH meter may be used, or a filtrate may be made from distilled water
and a soil sample and the pH measured with litmus paper, a pH meter, or a pH test kit. Note that
a pH meter uses a glass electrode with a rather fragile glass bulb on the bottom. Care must be
taken when using these instruments not to break the electrode bulb.
Soil pH may also be measured using an antimony electrode and a copper-copper sulfate
electrode. The antimony electrode consists of a slug of antimony metal in the bottom of a
nonmetallic tube. The slug is connected to a terminal on the top of the tube.
It is important to keep the antimony shiny and bright. Use fine non-metal bearing sand paper or
emery cloth for cleaning. Do not use steel wool or other metallic abrasive since particles of
metal may become embedded in the antimony and affect the reading.
©NACE International
CP 2 | Technician
3-40
Field Measurements
The antimony electrode and copper-sulfate reference electrode are placed close together with
the electrode tips in the soil and connected to a voltmeter. It does not matter which cell is
connected to which terminal of the meter since it is the potential between the two electrodes
that is of interest. Take care not to get any copper sulfate on the antimony slug. There is a scale
on the side of the antimony electrode that is calibrated in mV and pH. Once the potential
difference between the two electrodes is obtained, the pH can be determined from the scale.
3.10 Concrete Structures
The following discussion pertains primarily to atmospherically exposed reinforced concrete
structures, such as bridges and buildings. Reinforced concrete structures requiring cathodic
protection are found in immersed situations as well, such as prestressed concrete pipes,
prestressed concrete pilings, and cement-mortar-coated steel pipes.
Since cathodic protection requires a continuous structure, and since reinforcing is usually only
connected through tie wires, electrical continuity must be verified. Items such as drains,
railings, and expansion joints must also be continuous with reinforcing to avoid interference.
Electrical continuity can be evaluated using AC-resistance measurements. Connections to two
widely spaced points on the structure are made through the AC instrument. A resistance of less
than 0.100Ω indicates continuity.
Continuity can also be estimated by measuring the rebar-to-reference cell potential between
several locations using a constant reference cell location. rebar-to-structure potentials within
0.001 V of each other suggest that the points are continuous. Measurements greater than
0.001 V but less than 0.003 V indicate uncertain continuity, and measurements greater than
0.003 V indicate that the structure is discontinuous.
Depth of concrete cover is important when an impressed current cathodic protection system is
to be installed. The anode must not come into contact with the rebar or any other metallic
component of the structure, otherwise a short circuit will occur rendering the system useless.
Depth of cover is measured using a Pachometer.
Metal reinforcing-to-reference electrode potentials are taken on concrete structures to
determine the probability of corrosion of the embedded metal. Details of this procedure are
provided in ASTM Test Method C876, “Test Method for Half-Cell Potentials of Uncoated
Reinforcing Steel in Concrete.”
A high-impedance voltmeter is connected between the reinforcing steel and a reference
electrode placed on the surface of the concrete. The most commonly used reference electrode is
the copper-copper sulfate half-cell. Excavation of the concrete to expose the reinforcing steel
might be required to obtain the structure contact. Because of the high resistance inherent in the
measurement circuit, the voltmeter must have sufficient input impedance to accurately measure
the half-cell potentials. The minimum voltmeter impedance should be 10 x 106Ω and be
selectable to higher values in order to identify significant resistances in the circuit.
To reduce the contact resistance between the concrete surface and the half-cell, a moist sponge
is placed between the half-cell and the surface. It is also desirable to pre-moisten the entire
surface with clean potable water. This will reduce instabilities, but will result in a “leveling” of
the measured potentials.
CP 2 | Technician
©NACE International
Field Measurements
3-41
Half-cell potential measurements can be interpreted as follows:
Potential
Probability of Corrosion
More positive than –200 mV
–200 to –350 mV
More negative than –350 mV
< 5 percent
About 50 percent
> 95 percent
Potential measurements on concrete that is completely saturated, e.g., submerged piling, may be
more negative than –350 mV yet have little corrosion activity because the water saturation limits
oxygen diffusion which reduces corrosion.
Potential measurements are usually taken in a grid pattern, for example, one reading every 0.6
to 1.5 m (2 to 5 ft). The resulting data is plotted on a contour map showing areas that are
corroding.
3.11 Direct Inspection
A CP technician may be requested to inspect a structure for corrosion. This is an opportunity to
gather enough forensic information to determine the cause of the corrosion and to predict the
fitness for service.
As a minimum the following steps should be followed but each owner can have additional
specific requirements such as ultrasonic or magnetic flux leakage (crack) testing that require
special training.
1. Before excavation, measure potentials and soil resistivity over the site
2. Photographs are to be taken at each stage of exposure.
3. When the structure is exposed, a pH of the surface should be compared to the soil pH
and potentials repeated at the ends of the excavation (a high pH is expected at the surface of
a structure with CP).
4. Inspect the coating for signs of deterioration, damage and lack of adhesion. Outline
these areas for a photograph.
5. Note any moisture underneath the coating and take a pH of this moisture with litmus
paper.
6. Obtain samples of any corrosion product and seal in a plastic bag as they may be used for
further analysis and/or bacteria tests.
7. After the surface is cleaned, identify the welds to known geographical points (GPS) or if
a pipeline to the pipe chainage and weld numbers.
8. Locate areas of corrosion, outline them, tie them to the clock position and closest weld.
Overlay them with a grid of known dimensions. Measure depths of pits and record them on
the surface for photographs.
9. Record any repairs made
10. Inspect the repair coating for holidays and adherence.
11. Repeat the potential measurements and adjust the CP system if necessary.
3.12 Leak Frequency
Comparing the cumulative frequency of leaks vs. time often identifies the effect of corrosion
control. It is typical of corrosion that the cumulative frequency increases logarithmically with
©NACE International
CP 2 | Technician
3-42
Field Measurements
time. Leaks that occur from purely mechanical causes would not behave with such regularity.
The effect of cathodic protection is to slow down or flatten the leak rate curve.
Figure 3.32 is an example of a leak vs. time curve before and after the application of cathodic
protection. Figure 3.32 comes from actual data on the leak history of a cast iron water main
before and after cathodic protection was installed. The leaks occurring before 1984 show the
logarithmic increase in the number of leaks with time. The leaks are shown to have essentially
stopped after cathodic protection was installed.
Maintaining leak record curves is a method that can be used to prove the effectiveness of
cathodic protection. It is particularly useful for owners of structures that are not regulated by a
government agency.
Figure 3.32 Cumulative Leaks vs. Time Before and After Cathodic
Protection
CP 2 | Technician
©NACE International
Chapter 3
Field Measurements
®
Measurement of CP Effectiveness
2
▪ Instruments
▪ Structure-to-electrolyte potential
▪ Test coupons
▪ Current measurements
▪ Soil resistivity layers
▪ Direct inspection
▪ Leak frequency
CP2 | Technician
Analog Meters
3
▪ Needle attached to coil rotates
through permanent magnetic
field as current in coil increases
Scale
Pointer
Permanent Magnet
▪ Needle points to a calibrated
scale
▪ Typically relatively low internal
resistance
Range
Resistors &
Selector Switch
N
▪ Usual type in DC power sources
S
Im
Moving
Coil
Damping Resistor
+
▪ High internal impedance
CP2 | Technician
1
Digital Meters
4
Digital Meters
▪ Condition input with analog
electronics & convert to digital.
Digital Display
▪ Many samples taken of which
an average displayed 2 to 4
per sec to minimize variations
(e.g. noise) & improve accuracy
1.999
VOLTS AMPS OHMS
Analog to Digital
Conversion
Analog Signal
Conditioning
▪ Read out on 3 ½ or 4 ½ digit
LED or LCD display
Signal Input
▪ Display damaged at extreme
temperatures
CP2 | Technician
Digital Multimeters (DMM)
5
DMM Functions:
▪ Minimum AC/DC voltmeter. DC ammeter, DC Ohmmeter
▪ May also include Hertz, continuity & diode test
▪ May have Auto-ranging & Hold features
▪ All functions eventually derived from a voltage and ADC
CP2 | Technician
Digital Voltmeter
6
▪ When on DC/AC Voltage – input protected, conditioned and
converted (figure)
▪ ON to OFF - display changes rapidly
▪ Instant OFF potential: record displayed value 0.5 to 1
second after interruption
▪ Avoids error due to spiking
CP2 | Technician
2
Digital Ammeter
7
▪ Ammeter in series
▪ All current through internal resistor
(shunt)
▪ Voltage across internal resistance
processed & displayed in A, mA, μA.
▪ Ammeter increases total circuit
resistance & reduces overall current
▪ Lower current requires higher
resistance internal shunt.
▪ Different scales have different
internal resistances & change
total current
▪ Use highest scale that can be
read accurately
CP2 | Technician
Digital DC Ohmmeter
8
▪ Impresses a current through
known resistance & external
resistance under test
▪ Digital electronics calculates
and displays test resistance
▪ Based on ratio of two
resistances
▪ Resistance affected by
temperature but
eliminated with ratio of
both at same temperature.
▪ Readout calibrated in Ohms
(kΩ, Ω etc.)
CP2 | Technician
Digital DC Ohmmeter Precautions
9
▪ DMM Ohmmeter uses internal voltage source
▪ External voltage gives reading too low or too high depending
on polarity.
▪ Do not use DMM in circuit with external voltage including:
▪ back emf (anodes) or
▪ galvanic potential (road casings)
▪ Use AC Ohmmeter in these cases.
CP2 | Technician
3
Other DMM Features
10
AC Volts versus Volts rms
▪ Basic voltmeter assumes a pure sine wave
▪ Reads peak AC x 0.7071 (1/√2) to convert to AC Volts
▪ Rms measures AC wave for true value
Auto-range
▪ Basic meter requires selecting correct scale
▪ Auto-range selects best scale while processing data
▪ Convenient but adds time
▪ Must pay attention to scale on readout
▪ Instant OFF potential cycle may be too short
(numbers flashing)
▪ Manually set scale if so
CP2 | Technician
Other Instrument Features
11
Diode Test
▪ Diode requires small voltage before conducting in forward
direction
▪ If good, reads forward voltage and OL in reverse
▪ If shorted, reads 0 V in both directions
▪ If open circuit, reads OL in both directions
Hertz
▪ Measures number of AC cycles (hz) (50 or 60 hz)
▪ DC output - measures peaks (100 or 120 hz if full wave)
Hold
▪ Freezes readout where difficult to read or capture reading
CP2 | Technician
Structure-to-Electrolyte Potentials
12
“The potential difference between the metallic surface of the
structure and electrolyte that is measured with reference to
an electrode in contact with the electrolyte.”
Measurements must include:
▪ Magnitude
▪ Polarity
▪ Units
▪ Reference Electrodes
CP2 | Technician
4
Structure-to-Electrolyte Potentials
13
Used to:
▪ Locate anodic areas on non-cathodically protected pipelines
▪ Determine the effectiveness of cathodic protection
▪ Locate stray currents
▪ Locate electrical shorts and contacts
▪ Locate coating holidays
CP2 | Technician
Minimizing IR Drop
14
▪ Reduce distance between reference electrode and structure
surface
▪ Measure potential with current interrupted (instant-off
potential)
▪ Measure polarization formation or decay (after current ON or
after left OFF)
▪ Install external CP coupons to replicate a coating holiday
CP2 | Technician
Structure-to-Electrolyte Measurement Circuit
15
Where:
Rm = voltmeter input resistance
Rtl = test lead resistance
Rt = total circuit resistance
Rp,e = Resistance of the pipe with respect to
Remote Earth
Rr,e = Resistance of the Reference Electrode
with respect to Remote Earth
Im = meter current
Etrue = Polarized potential of the pipe with
respect to the Reference Electrode
Vm =
Rm
Rt
Vm = voltmeter reading
x Etrue
re = remote earth
CP2 | Technician
5
Measurement Error (Example)
16
Given:
Etrue = 1,000 mV, Rm = 1 MΩ, Rr,e = 100 kΩ, Rp,e = 10 Ω, and
Rtl = 0.01 Ω each
Calculate voltage across the voltmeter
Rt
=
=
=
Rt
Vm =
Rm
Rt
Rm + Rr,e + Rp,e + 3Rtl
106 + 105 + 10 + 3(0.01)
1.1 MΩ
X Et = 909mV
Error:
1,000 − 909
 100 = 9%
1,000
▪ If Rm = 10 MΩ
Rt = 990 mV reducing error to 1%
CP2 | Technician
Methods to Minimize Electrode Contact Resistance
17
Wet soil as needed
Avoid grass
Avoid asphalt/concrete/gravel surfaces
Access ports
▪
▪
▪
▪
Small diameter
Hole filled with
A soapy water
PVC tube
Dry Soil or
Frozen Ground
Clay
CP2 | Technician
Etrue Knowing Two Input Resistances
E𝑡𝑟𝑢𝑒 =
18
Vh (1 − K)
V
1 − (K h )
Vl
where:
Etrue
=
true potential (V)
K
=
input resistance ratio Rl/Rh
Rl
=
lowest input resistance
Rh
=
highest input resistance
Vl
=
voltage measured with lowest input resistance
Vh
=
voltage measured with highest input resistance
CP2 | Technician
6
Etrue Knowing Two Input Resistances
19
Example:
Vl of –650 mVcse at Rl = 1.0 MΩ
Vh = –800 mVcse at Rh = 10.0 MΩ
Calculate Etrue:
E true =
=
- 720 mV
1 − 0.123
- 800 mV (1 − 0.1)
 - 800 mV 

1 − 0.1 
 - 650 mV 
=
- 720 mV
0.877
= - 821 mVcse
CP2 | Technician
Rtotal & RCircuit
20
Rt =
=
Rm  E true
Vm
10 M  821 mV
800 mV
Rt
= 10.3 MΩ
Rcirc
= R t – Rm
= 10.3 MΩ – 10 MΩ
Rcirc
= 0.3 MΩ or 300,000 Ω
CP2 | Technician
Bare Pipe Voltage Gradients
Equipotential
21
Vm
line (surface)
Example:
Given: 10 mV per equipotential line
If Ep is –790 mVcse
Voltmeter will read:
Current
line
Vm = –790 mVcse
+ (–10 mV x 10)
Vm = –890 mVcse
CP2 | Technician
7
Coated Pipe Voltage Gradient
22
Voltmeter
Holiday
d
CP2 | Technician
Voltage Drop with Current in a Pipeline
23
Voltmeter
(1)
Ip
Ip
(2)
Ip
Vp = Ip Rp
Vp = Potential at (2) to trailing wire
tied to (1) minus potential to pipe (2)
to same reference electrode position
CP2 | Technician
Voltage (IR-Drop) Error Determination & Correction
24
▪ Interrupt the current and measure the potential before
significant depolarization occurs ("instant off" potential)
▪ Voltage (IR) error = On – instant OFF
▪ Place reference electrode close to exposed metal (coating fault
(holiday))
▪ Coupons
▪ May be neglected if current and/or resistance is small. Before
neglecting magnitude must be determined.
CP2 | Technician
8
Current Interruption
▪ All sources of current must be
interrupted
▪ Must be read quickly as
structure depolarizes
Potential
▪ If spiking, then read after spike
Time
P/S Potential (Volts)
▪ Effective as when I= 0 A, then
IR = 0 V
1.7
1.6
1.5
1.4
1.3
1.2
1.1
1
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
Time Milliseconds
CP2 | Technician
Current Interruption Showing IR & Depolarization
26
Em = Ecorr + Ep + IR
Potential ( - mV)
( )
(–)
ON Potential
Voltage (IR) Drop
100 mV
Polarization
OFF Potential
100 mV Depolarization
Native (Free Corroding, Static) Potential
(+)
Time
CP2 | Technician
Interruption Cycle
27
▪ Interruption cycles vary based upon survey and equipment
▪ Key factors in interruption cycle:
▪ Maintain polarization during survey
▪ Minimize depolarization during OFF period
▪ Measure true OFF-potential after a “spike” has
dissipated (0.3 to 0.6 seconds)
▪ Leave interrupters in ON position when not surveying
CP2 | Technician
9
Using a Datalogger Waveprint
28
Used to:
▪ Confirm synchronization (Top
figure not synchronized)
▪ Polarization & depolarization
▪ Spiking magnitude & direction
▪ Detect dynamic stray current
(bottom figure)
▪ Determine Etrue in stray
current
CP2 | Technician
Reference Electrode Near Structure
Aboveground
Storage Tank
29
Test / Access
Station
Grade
Reference Cell
Monitoring Tube
Rim 25'
On -1411 -698
Off -902 -664
Center
-404
-402
55'
Rim
-601 -1455
-578 -911
Potentials (mV CSE)
CP2 | Technician
External Coupons
30
▪ Used with other tools & data to evaluate CP to a given criterion.
▪ Applicable to variety of structures and conditions such as:
▪ Multiple influencing rectifiers
▪ Multiple pipelines or complex underground structures
▪ Direct connected sacrificial anodes
▪ Stray current including telluric
▪ Localized corrosive areas
▪ Areas shielded from surface measurements
▪ AC assessments
CP2 | Technician
10
External Coupons
22
▪ Coupons - bare metal samples [1]
▪ Represents coating holiday
▪ Same metal and surface as the structure;
▪ Small to avoid excessive current drain on CP;
Coupons
▪ At structure depth in the same backfill;
▪ Mill scale and foreign materials removed
▪ Placed at a known location of an ineffective
coating where applicable.
▪ Reference at coupon or in soil tube
▪ Measure voltage (IR) drop free potentials by
disconnecting coupon.
[1] ANSI/NACE
Standard SP0104, “The Use of Coupons for Cathodic Protection Monitoring Applications”
CP2 | Technician
External Coupon Measurements
32
Structure-to-electrolyte potentials:
▪ Native (before connecting to CP structure)
▪ Initial (after connecting but before CP)
▪ ON (connected to CP & may include voltage (IR) drop)
▪ Instant OFF (immediately after disconnecting coupon from CP)
▪ Depolarized (after leaving disconnected)
Current
▪ Value
▪ Direction
▪ Current density (calculated)
Corrosion Rate (Special - EIS, LPR, ER)
CP2 | Technician
External Coupon Measurements
33
▪ Caution with Native (Free Corroding) coupon potentials after
exposure
▪ Ongoing study of 483 10 cm2 native coupons - significant
change in ~10 years
▪ 174 (36%) more (+) than 100 mV
▪ 77 (16%) more (-) than 100 mV
▪ 146 (30%) +/- 100 mV
▪ 86 (18%) no reading
▪ Actual potentials on graph
CP2 | Technician
11
Potentials - Coupons vs Structure
34
▪ Coupon potentials may not be identical to structure
▪ Structure potential is subject to:
▪ Electrolyte variations (soil, moisture, chemistry, temperature,
O2) - different reactions and products
▪ Number & size of holidays
▪ Coating conductance variations
▪ Current variations around/along structure
▪ Stray current
▪ Circulating / long-line current
▪ Bimetallic or different alloys
▪ Permanently attached sacrificial anodes
CP2 | Technician
Coupons vs. Structure Potentials
35
▪ Structure potential – weighted average of surfaces in
different conditions
▪ Coupon potential – single small metal surface in limited
conditions
▪ Coupon receives same CP - not subject to all influences
▪ Coupon may be better indication of local status
▪ Neither coupon / structure potential necessarily in error
▪ Important to understand factors affecting each
▪ Coupon can demonstrate if CP system can protect a holiday
of that size and location
CP2 | Technician
External Coupons Test Methods
36
Test Method 1
▪ Interrupt current (disconnect) coupon lead in test station
▪ Measure instant OFF potential:
▪ High impedance voltmeter
▪ stationary reference near coupon OR
▪ portable reference in plastic tube (electrolytic bridge) to coupon
▪ Measure current (zero resistance ammeter, clip-on ammeter (if large
coupon), shunt)
▪ Note polarity for current pickup/discharge
Test Method 2
▪ Measure polarized potential as Test #1
▪ Leave coupon disconnected and measure depolarized potential
▪ Calculate polarization by “Depolarized potential – polarized potential”
CP2 | Technician
12
External Coupon Errors
37
Improper Installation
▪ Soil voids at coupon surface
▪ Oxygen ingress to coupon through unconsolidated backfill
▪ Broken or high resistance wire contacts
▪ Poor stationary reference location
Measurements
▪ Low impedance voltmeter depolarizing coupon
▪ Poor reference contact
▪ Extreme dry soil in tube
▪ Especially in soil tube if soil above ground level
CP2 | Technician
Electrical Resistance (ER) Probe
38
▪ Exposes a resistive element to electrolyte
▪ As element corrodes, cross section reduces,
increasing resistance
▪ Resistance is temperature dependent
▪ Exposed element compared to a
nonexposed element
▪ Resistance ratio is same regardless of
temperature
▪ Corrosion rate determined by metal loss
versus time
▪ Suitable for uniform corrosion, not suitable
for pitting corrosion
CP2 | Technician
External Coupons – Dynamic Stray Current
39
▪ Coupon not affected by stray current except when connected
▪ Both ON & instant OFF potentials to be recorded
▪ Voltage (IR) error reduced but still considered
▪ Coupons designed to minimize error
▪ Reference near coupon, or
▪ Reference in soil tube close to coupon
▪ ON may be more electropositive than OFF
▪ High impedance datalogger for stray current.
CP2 | Technician
13
Current Measurement
40
Typical current measurements in CP
▪ Galvanic current output
▪ Impressed current output
▪ Current in structure
▪ Bond current
CP2 | Technician
Current Measurement with an Ammeter
41
▪ Ammeter is inserted in series
▪ Adds resistance to circuit
A
– Without Ammeter
Icp =
Vd,cp
R cp
Vd,cp
Rcp
– With Ammeter
(Possible significant errors)
Im =
Icp
Vd,cp
Rcp + Rm
CP2 | Technician
Shunt to Measure Current
42
Shunt remains in circuit, therefore
current stays balanced
V
equally rated shunts
I1
I2
I3
I4
IT
CP2 | Technician
14
Shunt Current Calculations
Current through shunt resistance
produces a voltage drop
43
▪ Three ways to calculate shunt
current
▪ Ratio
Vmeas / Vshunt x I shunt
Vshunt = Icp x Rshunt
Rshunt = Vrating / Irating
▪ Calibration Factor
Vmeas x K (factor)
Example: 5 A, 50 mV Shunt
Icp = (0.05 V) 5A
▪ Resistance
Icp = Vshunt / Rshunt
Rshunt = 0.050 / 5 = 0.01Ω
Vshunt = 5A x 0.01 = 0.05 V (50 mV)
[See Tables in CP Technician
Reference Sheet at back of
manual for table]
CP2 | Technician
Zero-Resistance Ammeter
44
Zero-resistance
Ammeter
I cp
Soil Tube
I cp
Steel Coupon
CP2 | Technician
Clamp-On (Clip-on) Ammeter
45
Magnetic Field
I
dc
Clamp-On
Ammeter
Clamp
Earth
Current
+0.9 A
Clamp
+0.4 A
Indicator
Earth current leaving subject pipeline is 0.9 – 0.4 = 0.5 A
CP2 | Technician
15
2-Wire Line Current Test
Pipe resistance or size
and wall thickness or
weight per foot known
46
Wires must be
color coded
East
Current
West
Pipe span in meters or feet
CP2 | Technician
2-Wire Line Current Test (Example)
47
Pipe Span: 762 mm (30-in.) diameter. 61-m (200-ft) long
Weight 176.65 kg/m (118.7 lbs/ft)
Span voltage = 0.17 mV,
Calculate pipe current
Pipe resistance/ft from Table = 8.01 /m (2.44  /ft )
= 0.00000801 /m (0.00000244 /ft)
Total resistance = 61 m x 0.00000801 /m = 0.000488 
OR
= 200 ft x 0.00000244 /ft = 0.000488 
Current (I) =
𝑉
𝑅
=
.00017𝑉
.000488𝛺
= .348A or 348 mA
CP2 | Technician
4-Wire Line Current Test
48
Calibrating Current Span
𝐑𝐩𝐢𝐩𝐞 =
∆𝐕𝟐 − 𝟑
∆𝐈𝐭
K = Itest / E test
+
A
It
V
1
2
3
4
R pipe
CP2 | Technician
16
Resistance of 4-Wire Span (Example)
49
V2-3 = +21 mV (before test current applied) (residual current)
V2-3 = –19 mV (after test current applied)
It
= 10 A
Calculate Resistance (Rp) of the pipe section & residual current:
Rpipe =
+21 mV - (-19 mV)
10 A
R pipe =
+40 mV
10 A
I residual =
=
0.021V
.004 
4mW
= 5.25 A
CP2 | Technician
Calibration Factor of 4-Wire Span (Example Continued)
V2-3 =
+21 mV (before test current applied)
V2-3 =
–19 mV (after test current applied)
ΔE
=
40 mV
It
=
10 A
50
Calculate Calibration Factor (K) of the pipe section:
K = Itest / E test =
10 A
0.25 A
=
40 mV
mV
Calculate residual current from factor:
Iresidual =
21 mV 
0.25 A
mV
= 5.25 A
CP2 | Technician
Coating Resistance Calculations
51
= I1 – I2
CP2 | Technician
17
Earth Current Measurement
52
Voltmeter With Reading
+
-
Reference Electrode
Reference Electrode
Current
CP2 | Technician
Coating Resistance Calculations (Example)
Factor
Pipe OD (d) = 610 mm
(24”)
TS1
TS2
IONTS
3.00 A
2.80 A
IOFFTS
0.20 A
0.10 A
ΔITS
2.80 A
2.70 A
EONTS
-2.00 V
-1.70 V
EOFFTS
-0.90 V
-0.85 V
ΔETS
1.10 V
0.85 V
IC
Pipe Section
Pipe Section
(metric)
(Imperial)
= 2.80 – 2.70
= 2.80 – 2.70
= 0.10 A
= 0.10 A
(Eq 3.13)
Length (L) = 1,609 m
(5,280 ft)
ΔEave
=
(Eq 3.14)
RC
1.10 + 0.85
2
= 0.975 V
=
0.975
=
1.10 + 0.85
2
= 0.975 V
=
0.10
0.975
0.10
(Eq 3.15)
= 9.75 Ω
= 9.75 Ω
Apipe
= π .610 x 1609
= π 2 x 5280
(Eq 3.16)
= 3,080 m
2
= 33,158 ft2
rC
= 9.75 x 3080
= 9.75 x 33158
(Eq 3.17)
= 30,030 Ω-m2
= 323,291 Ω-ft2
GC
=
(Eq 3.18)
53
1
9.75
=
= 0.103 Siemens (S)
1
1
9.75
= 0.103 Siemens (S)
1
gC
= 30030
= 323291
(Eq 3.19)
= 0.0000333 S/m2
= 0.00000309 S/ft2
(33.3 µS/m2)
(3.09 µS/ft2)
CP2 | Technician
Current Requirement Test
54
Adjustable
Current Source
Reference
Electrode
A
-
-
V +
+
Anode
Test Anode bed
Soil Electrolyte
Pipe
CP2 | Technician
18
Current Requirement if Test Sub-Criterion
Example:
55
Ireq = Epreq*Itest
Eptest
Itest
= Test current applied to structure (A)
Ireq
= Estimated additional current required (A)
ΔEptest = Polarization from test (V) [EOFF –EINITIAL]
ΔEpreq = Polarization required (V)
= [-0.850 V – EINITIAL] for -850 mVCSE polarized
potential criterion
OR
= 0.100 (100 mV) polarization criterion
Considers resistance producing IR drop: R = (EON - EOFF)/ION
CP2 | Technician
Example of Current Requirement Calculation
56
Example:
Native (Static) pipe-to-soil potential
=
– 0.645 VCSE
Desired polarized p/s potential
=
– 0.850 VCSE
Test current
=
0.050 A (50 mA)
Polarized potential from test current
=
– 0.775 VCSE
Ireq = Epreq*Itest
Eptest
I req =
[-0.850 V - (-0.645 V)] 0.050 A
[−0.775 V − (− 0.645V)]
= 0.0788 A or 78.8 mA
CP2 | Technician
Coating Resistance Calculations (1)
Pipe Surface Area =
57
d x  x L
= 0.61m x  x 1609 m = 3080 m2
=
24 in
x  x 5280 ft = 33,158 ft 2
12 in / ft
CP2 | Technician
19
Coating Resistance Calculations (2)
Eave =
ETS 1 + ETS 2
2
Eav e =
58
1.10 V + .85 V
= 0.975 Volt
2
If more than two potentials are taken, you will need to
average all potentials to determine Eave
CP2 | Technician
Coating Resistance Calculations (3)
59
Ic = ITS1 − ITS 2 = 2.80 A − 2.70 A = 0.10 A
CP2 | Technician
Coating Resistance Calculations (4)
Rc =
60
Eave 0.975 V
=
= 9.75 
IC
0.1 A

CP2 | Technician
20
Coating Resistance Calculations
61
▪ Resistance (RC) is the resistance to earth of the overall pipe
▪ Specific resistance (rCE) is resistance of one unit of area
▪ Each unit of area is in parallel
▪ Therefore the total resistance is multiplied by the unit area
If RC = 9.75 Ω
Specific coating resistance = rCE = Apipe x RC
= 3,080 m2 x 9.75 Ω (30,030 Ω-m2 )
= 33,158 ft2 x 9.75 Ω (323,291 Ω-ft2 )
CP2 | Technician
Coating Conductance
62
Conductance is the reciprocal of resistance (units Siemens
[S] or microsiemens [ S])
g = 1 = 1 = 0.0000333 S = 33.3 μS
rCE 30,030
m2
m2
g = 1 = 1 = 0.00000309 S = 3.09 μS
rCE 30,030
ft2
ft2
where:
g = conductance (S)
RCE = specific coating resistance (Ω)
CP2 | Technician
Electrical Isolation
63
Indication of Problems
▪ Short (metal to metal contact):
▪ Significant electropositive change in normal structure-toelectrolyte potential
▪ Decrease in resistance (short to another structure)
▪ Discontinuity (open circuit):
▪ Sudden change in structure-to-electrolyte potential along
a structure
CP2 | Technician
21
Electrical Isolation
64
Indication of Problems
▪ Significant electropositive change in normal (expected)
structure-to-electrolyte potential or decrease in resistance
indicates possible short
▪ A sudden electropositive shift in the structure-to-electrolyte
potential along a structure may indicate discontinuity
▪ A lower than expected structure-to-electrolyte resistance may
indicate a short to another large structure
CP2 | Technician
Locating the Problem
▪
▪
▪
▪
▪
▪
▪
▪
65
Structure-to-electrolyte potential measurement
Interrupted structure-to-electrolyte potential measurement
Pipeline/cable locators
Isolation testing instrument
DC line current measurements
Fixed cell to moving ground test
Current response test
Isolation resistance test
Tests not discussed but see …
NACE SP0286 Electrical Isolation of Cathodically Protected Pipelines
CP2 | Technician
Fixed Cell to Moving Ground Example
66
Site 4
Site 1
Site 3
Reference
Electrode
Site 2
Voltmeter
Site No.
Electrically Continuous
Electrically Discontinuous
1
–1.560 VCSE
–1.560 VCSE
2
–1.560 VCSE
–1.456 VCSE
3
–1.560 VCSE
–1.652 VCSE
4
–1.560 VCSE
–1.488 VCSE
CP2 | Technician
22
Corrosivity of Electrolyte (Soil)
67
Soil resistivity:
▪ measure of ability of
electrolyte to support
electrochemical corrosion
▪ Used in CP design
pH:
▪ measure of electrolyte
acidity or alkalinity
Both influence underground/
submerged metal corrosion
CP2 | Technician
pH Testing
68
Measurement of Electrolyte pH:
▪ For liquids, pH (litmus) paper or a pH meter
▪ For soils,
▪ Filtrate made from distilled water and a soil sample
▪ Measure with litmus paper, pH meter, or a pH test kit
▪ Note that a pH meter uses a fragile glass electrode
▪ Potential between antimony electrode and CSE (being careful
to not contaminate antimony).
▪ See conversion scale on side of antimony electrode for pH.
CP2 | Technician
Measuring Electrolyte Resistivity
69
▪ Wenner 4-Pin Method
▪ Other methods not discussed
▪ Uneven pin spacing method
▪ Single-Probe method
▪ Soil Box
▪ Electromagnetic Induction Method
CP2 | Technician
23
4-Pin Soil Resistivity Pin Location
70
▪ 4 pins in a straight line at equal spacing
▪ Avoid placing pins over underground structures
▪ Either metallic or non-metallic
▪ If unavoidable, place pins perpendicular (not parallel) to
pipelines or cables
CP2 | Technician
Resistivity by Wenner 4-Pin Method
71
▪ Current (I) is applied to the outer pins
▪ (C1 & C2)
Soil Resistivity
Meter
C1
▪ (P1 & P2)
▪ Resistance (R): R = V/I
a
OR
▪ AC resistance meter measures R directly
▪ Reversed wires gives a negative resistance so
instrument will not balance
C2
P2
P1
▪ Voltage (V) measured between inner pins
a
a
 =2aR
* a is in cm
▪ Approximate depth to spacing of inner electrodes (a)
▪ Average soil resistivity (ρ) to depth (a) calculated
from resistance (R)
CP2 | Technician
Resistivity Calculations (metric)
72
=2aR
 = resistivity in Ω-cm
 = pi (3.14)
a = pin Spacing in cm
R = resistance in Ω
CP2 | Technician
24
Resistivity Calculations (modified to feet)
73
If spacing is measured in feet but resistivity still in Ω-cm:
 = 191.5aR

= resistivity in Ω–cm
191.5 = factor in cm/ft
a
= pin spacing in feet
R
= resistance in Ω
Factor = 2* 𝛑 X
2.54𝑐𝑚
1 𝑖𝑛.
𝑋
12 𝑖𝑛
1 𝑓𝑡
= 191.5 𝑐𝑚/𝑓𝑡
CP2 | Technician
Barnes Layer Analysis – Parallel Resistance Formula
74
▪ Barnes Layer predicts resistivity of layers
▪ Principle:
▪ each layer is a parallel resistance (R), and
▪ parallel resistance equation applies;
1/RT = 1/R1 + 1/R2 + 1/R3 + … + 1/RN
▪ If only two resistances (layers) then:
R2 =
R1RT
(R1 - RT)
▪ Barnes Layer only applies if RT reduces with increased
depth (a)
▪ May not due to larger surface sample with depth
CP2 | Technician
Average and Layer Resistivity Symbols
1 avg
a1
2 avg
a2
a3
3 avg
75
L1
L1
L2
L2
L3
L3
CP2 | Technician
25
Layer Resistivity Equations for Barnes Layer Analysis
Resistances (R1, R2, & R3)
measured at spacings
(a1, a2, & a3)
Resistivity of Layers (L1, L2
and L3) are desired
1 avg
L1
RL1
L1
= 2a1R1
= a1
= R1
= 2L1 RL1
2 avg
L2
RL2
L2
= 2a2R2
= a2 – a1
= (R1 R2)/(R1 – R2)
= 2L2 RL2
3 avg
L3 layer
RL3
L3
= 2a3R3
= a3 – a2
= (R2 R3)/(R2 – R3)
= 2L3 RL3
76
CP2 | Technician
Example Calculations for Barnes Layer Resistivity
(metric)
a1 = 160 cm
a2 = 320 cm
a3 = 480 cm
Ra1 = 10.0 Ω
Ra2 = 7.4 Ω
Ra3 = 3.1 Ω
ρa1 = 10,050 Ω-cm
ρa2 = 14,880 Ω-cm
ρa3 = 9,350 Ω-cm
Example 1
Layer 1
Layer 2
L1 = a 1
L2 = a2 – a1
=160 cm
=320 – 160
= 160 cm
Factor
Layer depth (L)
Layer resistance (RL)
RL1 = Ra1
= 10.0 Ω
Layer resistivity (ρL)
ρL1 = ρa1 = 10,050
Ω-cm OR
𝜌𝐿1 = 2 𝜋𝐿1 𝑅𝐿1
= 2 π 160 x 10.0
= 10,050 Ω-cm
77
𝑅𝐿2 =
𝑅1 𝑅2
(𝑅1 − 𝑅2 )
10 𝑥 7.4
=
(10 − 7.4)
= 28.46 Ω
𝜌𝐿2 = 2 𝜋𝐿2 𝑅𝐿2
= 2 π 160 x 28.46
= 28,610 Ω-cm
Layer 3
L3 = a3 – a2
= 480 – 320
= 160 cm
𝑅𝐿3 =
𝑅3 𝑅3
(𝑅2 − 𝑅3 )
7.4 𝑥 3.1
=
(7.4 − 3.1)
= 5.33 Ω
𝜌𝐿3 = 2 𝜋𝐿3 𝑅𝐿3
= 2 π 160 x 5.33
= 5,360 Ω-cm
CP2 | Technician
Example Calculations for Barnes Layer Resistivity
(Spacing in feet)
a1 = 5.25 ft
a2 = 10.50 ft
a3 = 15.75 ft
Ra1 = 10.0 Ω
Ra2 = 7.4 Ω
Ra3 = 3.1 Ω
78
ρa1 = 10,050 Ω-cm
ρa2 = 14,880 Ω-cm
ρa3 = 9,350 Ω-cm
Example 2
Factor
Layer depth
(L)
Layer 1
L1 = a 1
=5.25 ft
Layer
resistance
(RL)
RL1 = Ra1
= 10.0 Ω
Layer
resistivity (ρL)
ρL1 = ρa1 = 10,050 Ω-cm
OR
𝜌𝐿1 = 191.5𝐿1 𝑅𝐿1
= 191.5 cm/ft x 5.25 ft x
10.0Ω
= 10,050 Ω-cm
Layer 2
L2 = a2 – a1
=10.50 – 5.25
= 5.25 ft
𝑅𝐿2 =
𝑅1 𝑅2
(𝑅1 − 𝑅2 )
10 𝑥 7.4
=
(10 − 7.4)
= 28.46 Ω
𝜌𝐿2
= 191.5𝜋𝐿2 𝑅𝐿2
= 191.5 x 5.25 x
28.46
= 28,610 Ω-cm
Layer 3
L3 = a3 – a2
= 15.75 – 10.50
= 5.25 ft
𝑅𝐿3 =
𝑅3 𝑅3
(𝑅2 − 𝑅3 )
7.4 𝑥 3.1
=
(7.4 − 3.1)
= 5.33 Ω
𝜌𝐿3 = 191.5𝐿3 𝑅𝐿3
= 191.5 x 5.25 x
5.33
= 5,360 Ω-cm
CP2 | Technician
26
Reinforced Concrete Structures
79
Atmospherically exposed structures
▪ Bridge decks
▪ Bridge substructures
▪ Buildings
Buried or immersed structures
▪ Reinforced and prestressed pipelines
▪ Prestressed pilings
▪ Cement-mortar coated steel pipelines
CP2 | Technician
Concrete Structures Continuity
80
▪ Cathodic protection requires a continuous structure
▪ Drains, railings, reinforcing bars, and expansion joints must
all be verified for electrical continuity
▪ Electrical continuity can be verified using AC resistance
measurements
▪ Resistance <0.100 Ω (excluding test wires) between widely
spaced points of contact indicates electrical continuity
▪ Fixed electrode to moving ground techniques:
▪ <1mV difference indicates continuity; and
▪ >3 mV indicates discontinuity between contacts
CP2 | Technician
Concrete Structures Depth of Cover
81
▪ Depth of concrete cover is important with an impressed
current CP system
▪ Anode system must not contact reinforcing or other metal
component of the structure
▪ Otherwise, a short circuit will occur
▪ Depth of cover is measured using a Pachometer
▪ Depth of cover unimportant with a galvanic anode CP system
CP2 | Technician
27
Concrete Structures Potential Surveys
82
▪ A high-impedance voltmeter and a CSE most common for
potentials
▪ Removal of some concrete might be required for metal
contact
▪ To reduce the CSE contact resistance,
▪ Place a moist sponge between the concrete & CSE, or
▪ Completely pre-wet the entire concrete surface
CP2 | Technician
Concrete Structures Potential Surveys
83
▪ Typically potential measurements taken in a grid pattern
(approximately every 0.6 m to 1.5 m (2 ft to 5 ft)) and
▪ Plot on a contour map
▪ Interpretation of potential measurements by ASTM Test
Method C876 for atmospherically-exposed concrete:
Potential wrt CSE
Probability of Corrosion
more pos. than −200 mV
−200 to −350 mV
more neg. than −350 mV
< 5%
about 50%
> 95%
CP2 | Technician
Direct Inspection of Structure
84
Gather forensic information to determine cause of corrosion
▪ Before excavation, measure potentials & soil resistivity over site
▪ Photograph each stage of exposure
▪ Repeat potentials during excavation
▪ Immediately on exposure, measure pH of metal surface and soil
▪ Inspect coating for deterioration, damage and lack of adhesion
▪ Take a pH of moisture underneath coating with litmus paper
▪ High pH is expected at the surface of a structure with CP
▪ Sample corrosion product and seal in a plastic bag
▪ Used for further analysis and/or bacteria tests.
CP2 | Technician
28
Direct Inspection (cont’d)
85
▪ After surface is cleaned, identify welds to known geographical
points (GPS)
▪ if a pipeline, to pipe chainage and weld numbers
▪ Locate & outline areas of corrosion, measure clock position and
distance to closest weld or ID location
▪ Overlay metal loss features with a grid of known dimensions
▪ Measure depths of pits and record them on the surface for
photographs
▪ Record and photograph any repairs made
▪ Inspect the repair coating for holidays and adherence
▪ After backfill, repeat the potential measurements
▪ Adjust the CP system if necessary
CP2 | Technician
Leak Frequency
86
1000
636
Cumulative Breaks
100
53
10
1
1970
1975
1980
1985
1990
Year
CP Installed 1984
1995
2000
Actual
Projected (W ithout CP)
CP2 | Technician
Knowledge Check | 1
87
A structure-to-electrolyte potential measures the
potential difference between
A. two different structures acting as electrodes.
B. the structure and a standard reference electrode.
C. the structure and the anode.
D. two different points on the structure.
CP2 | Technician
29
Knowledge Check | 2
88
If 5.0 A of battery current passes through the outside
leads of a 4-wire current span spaced at 30 m(100 ft),
resulting in a voltage drop of 5.0 mV with the test
current applied and of 1 mV without the test current,
what is the calibration factor of the current span?
A. 0.00025 A/mV
B. 4.0 A/mV
C. 1.25 A/mV
D. 5.0 A/mV
CP2 | Technician
Knowledge Check | 3
89
Polarized potentials are measured
A. when the rectifiers are ON.
B. just after the rectifiers are turned OFF.
C. after the rectifiers are left off for several days.
D. just after the rectifiers are turned ON.
CP2 | Technician
Knowledge Check | 4
90
Polarization is determined by
A. subtracting the ON from the instant OFF potential.
B. measuring the instant OFF potential.
C. subtracting the instant OFF from the Native (free
corroding) potential.
D. subtracting the IR Drop from the ON potential.
CP2 | Technician
30
Knowledge Check | 5
91
Current pickup on a pipeline is indicated when
A. The structure-to-electrolyte potential over the pipe
is more electronegative than to each side.
B. The structure-to-electrolyte potential over the pipe
is more electropositive than to each side.
C. The two electrode method (side drain) shows the
electrode over the pipe is more electropositive.
D. A CIS shows a more electropositive potential with
the rectifier ON than OFF.
CP2 | Technician
Knowledge Check | 6
92
A 61 cm diameter (24-in) pipe has a current span at
each end of a 2 km (1.24 miles) section with the
following information determined:
EONTSI = -1200 mVCSE
EOFFTSI = -1000 mVCSE
IONTSI = 3.0 A
IOFFTSI = 0.20 A
EONTS2 = -1140 mVCSE
EOFFTS2 = -980 mVCSE
IONTS2 = 2.8 A
IOFFTS2 = 0.20 A
What is the pipe-to-earth resistance in Ω?
A. 0.9
B. 9
C. 66.7
D. 900
CP2 | Technician
Knowledge Check | 7
93
A 61 cm diameter (24-in) pipe which has a current span
2 km (1.24 miles) with the following information
determined:
EONTSI = -1200 mVCSE
EOFFTSI = -1000 mVCSE
IONTSI = 3.0 A
IOFFTSI = 0.20 A
EONTS2 = -1140 mVCSE
EOFFTS2 = -980 mVCSE
IONTS2 = 2.8 A
IOFFTS2 = 0.20 A
What is the specific coating resistance Ω-m2
A. 0.00023
B. 0.023
C. 3,450
D. 345,000
CP2 | Technician
31
Knowledge Check | 8
94
A 61 cm diameter (24-in) pipe has a current span at
each end 2 km (1.24 miles) section with the following
information determined:
EONTSI = -1200 mVCSE
EONTS2 = -1140 mVCSE
EOFFTSI = -1000 mVCSE
EOFFTS2 = -980 mVCSE
IONTSI = 3.0 A
IONTS2 = 2.8 A
IOFFTSI = 0.20 A
IOFFTS2 = 0.20 A
What is the specific coating conductance in siemens/m2?
A. 0.0000029
B. 0.00029
C. 43.5
D. 4,347
CP2 | Technician
Knowledge Check | 9
95
Structure-to-electrolyte potentials can be used for
which of the following purpose(s)?
A. Confirm if a CP potential criterion is met.
B. Locate anodic areas on non-CP pipelines.
C. Determine resistivity of the soil.
D. Locate stray current.
CP2 | Technician
Knowledge Check | 10
96
Which of the following potential measurements would
clearly indicate that a tank is isolated?
A.
A structure-to-electrolyte potential of -950 mVCSE with the
electrode at the pipe and a tank-to-electrolyte potential of -800
mVCSE with the electrode at the tank.
B. A structure-to-electrolyte potential of -950 mVCSE with the
electrode at the pipe and a tank-to-electrolyte potential of -940
mVCSE with the electrode at the tank.
C. A structure-to-electrolyte potential of -950 mVCSE with the
electrode at the pipe and tank-to-electrolyte potential of -800
mVCSE with the electrode at the pipe .
D. A structure-to-electrolyte potential of -650 mVCSE with the
electrode at the tank and a tank-to-electrolyte potential of -640
mVCSE with the electrode at the tank.
CP2 | Technician
32
Knowledge Check | 11
97
When using the Wenner four-pin method, what is the
resistivity when 10 Ω was measured with a pin spacing of
5 m?
A. 314 Ω-cm
B. 31,416 Ω-cm
C. 50,000 Ω-cm
D. 314,160 Ω-cm
CP2 | Technician
Knowledge Check | 12
98
What is the resistivity of a block of material that is 2
cm by 3 cm and 10 cm long has a resistance along its
length of 1000 Ω?
A. 100 Ω-cm
B. 600 Ω-cm
C. 1667 Ω-cm
D. 15,000 Ω-cm
CP2 | Technician
Knowledge Check | 13
99
What is the true potential if the voltmeter reads 1000
mV with a test lead resistance of 0.01Ω, a pipe-toearth resistance (Rp,e) of 10 Ω, a reference electrode
resistance to earth (Rr,e) of 100 kΩ, and a meter
resistance of 1 MΩ?
A. 800 mV
B. 909 mV
C. 1010 mV
D. 1100 mV
CP2 | Technician
33
Knowledge Check | 14
100
What is the percent error if the voltmeter read 1000
mV with a test lead resistance of 0.01Ω, a pipe-toearth resistance (Rp,e) of 10 Ω, a reference electrode
resistance to earth (Rr,e) of 100 kΩ, and a meter
resistance of 10 MΩ?
A. 1%
B. 2%
C. 5%
D. 10%
CP2 | Technician
Knowledge Check | 15
101
If a potential difference (Vl) of -750 mVCSE was
measured with an input resistance (Rl) of 1.0 MΩ and
a potential difference of -850 mVCSE (Vh) was
measured with an input resistance (Rh) of 10 MΩ, what
is the true potential (Etrue)?
A. -399 mV
B. -821 mV
C. -862 mV
D. -1128 mV
CP2 | Technician
Knowledge Check | 16
102
If current being impressed on to a structure is causing
a potential gradient of 50 mV per meter (average) and
the reference electrode is 3 m from the structure, what
is the potential being measured if the true potential at
the structure is -800 mV?
A. -150 mV
B. -650 mV
C. -950 mV
D. +950 mV
CP2 | Technician
34
Knowledge Check | 17
103
With proper instrumentation, a dual soil coupon can be
used to predict which of the following?
A. The potential of the pipe surface at the location of
the coupon.
B. The polarized potential of a coating holiday of a
given size at the location.
C. The amount of polarization of a coating holiday of a
given size at the location.
D. The amount of CP current pick up on a coating
holiday of a given size at the location.
CP2 | Technician
Knowledge Check | 18
104
When an ammeter with an internal resistance of 0.1Ω
is inserted into a circuit that is normally operating at
10 V and 20 A, it will read a current of
A. 9.5 A
B. 16.7 A
C. 20.1 A
D. 24.0 A
CP2 | Technician
Knowledge Check | 19
105
If the voltage drop across a 61 m (200 ft) span of 762
mm (30 in.) pipe weighing 176.65 kg/m (118.7 lbs/ft)
is 0.34 mV, calculate the current.
A. 0.309 A
B. 0.348 A
C. 0.464 A
D. 0.696 A
CP2 | Technician
35
Chapter 3
Field Measurements
®
36
Stray Current
4-1
Chapter 4: Stray Current
Stray currents are currents through electrical paths other than the intended circuit. Stray current
is not the galvanic corrosion current between anodes and cathodes on the same structure. Stray
currents, or interference currents, can be classified as being either static or dynamic.
Stray current can refer to either alternating current or direct current. AC stray current can be
both a safety hazard and a corrosion problem. DC stray current causes significant corrosion of
most metals.
Stray current is especially damaging because large currents, often involving many amperes,
might be involved. Even small amounts of stray currents can be highly damaging if discharged
over a small surface area. In some areas, particularly around older rail rapid-transit systems or
in the vicinity of underground mine railroads, pipelines may carry hundreds of amperes of stray
current. For every ampere discharged from a structure, a certain amount of metal is lost.
Faraday’s Law allows us to relate the corrosion lost to the amount of current discharged. For
ferrous metals (cast iron, ductile iron, steel), copper, and lead the loss rates are:
•
•
•
Ferrous 9.1 Kg / A-yr (20 pounds / A-yr)
Copper 10.4 Kg / A-yr (23 pounds / A-yr)
Lead 33.85 Kg / A-yr (74.64 pounds/ A-yr)
It is apparent that, if not controlled, stray current can destroy a structure very rapidly or at least
to a potentially catastrophic situation. Structures in environments that normally would not be
considered extremely corrosive will be subjected to accelerated corrosion when exposed to stray
current conditions. Further consideration must be given to the current density for total
penetration of the metal.
Stray current enters the pipe or other structure through the soil (or other electrolyte) but does
not cause corrosion at that point. Some amphoteric metals such as aluminum and lead may
suffer “cathodic corrosion” in stray current “pick up” areas. Many structures, in fact, receive
“free” cathodic protection from stray currents at the point of entry. The damaging effect of stray
current typically occurs if the current leaves the structure through the electrolyte where
corrosion will be accelerated.
The objective of stray current analysis is to determine:
•
•
•
•
•
The source of the stray current.
Where and over what area does the stray current enter the structure?
Where and over what area does the stray current leave the structure?
What is the magnitude of the stray current?
How can the stray current be mitigated?
4.1 Dynamic Currents
Dynamic stray currents are those currents that vary in amplitude and/or change in direction.
These currents can be man made or natural in origin.
©NACE International
CP 2 | Technician
4-2
Stray Current
4.1.1 Sources of Dynamic Stray Currents
Dynamic stray current can originate from any of the following sources:
•
•
•
•
•
•
DC transit systems
Welding
Mining operations
Electrical power transmission
Industrial plants
Telluric
Examples of man-made sources are DC welding equipment, mining operations, and DC transit
systems. Telluric currents are naturally occurring stray currents that are caused by disturbances
in the Earth’s magnetic field by sun spot activity. Figure 4.1 shows stray currents from a DC
railway. These are commonly called stray traction currents.
Figure 4.1 Illustration of Dynamic Stray Currents from a Transit
System
4.1.1.1 Natural (Telluric) Currents
Telluric current is generated by the interaction of the solar wind (high-energy particles given off
by the sun), the Earth’s magnetic field, and metal structures at the surface of the Earth. The
current generated shifts in magnitude and direction with time. It generally occurs during times
of increased sun spot activity. Telluric currents create significant monitoring difficulties to
confirm a cathodic protection criterion is met.
4.1.2 Detecting Dynamic Stray Currents
Dynamic stray currents can be readily detected from structure-to-electrolyte potentials and/or
line current measurements. Dynamic stray currents can be indicated by a structure-toelectrolyte potential that is changing with time with the reference electrode in a stationary
position in contact with the electrolyte. These potential changes are a direct result of current
changes at the source of the interference.
CP 2 | Technician
©NACE International
Stray Current
4-3
Figure 4.2 Pipe Potential Fluctuating Due to Dynamic Stray
Current
Varying voltage gradients in the earth can be detected using two reference electrodes space 3 to
6 m (10 to 20 ft) apart. Reference electrodes placed on the soil over the existing pipeline or
proposed pipeline route will show the voltage gradients that the pipe is exposed to between the
two cells Figure 4.3 and Figure 4.4. Figure 4.4 shows an example of current pickup, current
passing by and current discharge on a pipeline.
Figure 4.3 Potential Measurement Between Two Electrodes
©NACE International
CP 2 | Technician
4-4
Stray Current
Figure 4.4 Potential Measurement Between Two Electrodes
The analysis of dynamic stray currents may require the use of correlations, or comparisons, of
currents and voltages from one point on the structure to another. It is necessary to have
sufficient test facilities on the structure to measure structure-to-soil potentials and current on
the structure. If the structure has few or no test facilities and stray currents are detected, then
install additional test facilities to permit a meaningful analysis.
4.1.2.1 Continuous Data Recording
The techniques from section 4.1.2 “Detecting Dynamic Stray Currents” on page 4-2 provide
valuable information about where stray current enters and discharges from a structure. Section
4.1.2 does not:
•
•
•
provide information on the value of the maximum stray current affecting the structure
show whether the stray current voltages observed during the test period are significant
document the predominant direction of voltage or current.
To perform this function, data about the stray current magnitude over time is needed. This data
is obtained using a long term (24 hours or more) voltage or current recording. A recorder or
data logger should be used for this purpose.
CP 2 | Technician
©NACE International
Stray Current
4-5
Figure 4.5 Data Logger Plot Illustrating Dynamic Stray
Currents
Select the location to be tested using the results of the correlations, the best location being the
one of most exposure. The location of the recording should obviously be one of the test stations
used in the correlations as long as the voltages in the long term recording can be correlated back
to the other test stations using the correlations. Select a location where the recording device will
be safe and out of the way of traffic, pedestrians, and vandals. Note: The recording device should
be identified with the company name, address, and telephone number.
More than one recording device might be needed.
4.1.2.2 Finding the Source of the Stray Current
Engineering solutions to stray current problems can be complex. Frequently, more than one
source of current is involved. Transit systems, for example, do not operate from a single
substation; rather they are supplied by a number of substations operating in parallel and feeding
many different lines simultaneously. Such transit systems operate with many thousands of
amperes of current, and the effects can be seen for many miles on underground structures. If
stray current is to be successfully drained from the structure of interest to the source, two
conditions must be met.
1. The source must tend to pick up stray current at the point where the mitigation bond is
to be installed. This is point determined using the correlations described above.
2. The structure must tend to discharge stray current at the point where the mitigation
bond is to be installed. This point is also determined using the correlations described
above.
Sufficient current must be drained to mitigate the most severe stray current exposure. This is
determined by measuring or calculating the maximum current through the proposed bond or
other mitigation system.
©NACE International
CP 2 | Technician
4-6
Stray Current
4.2 Static (Steady State) Currents
Static, or steady state, interference current can be
defined as those that maintain a constant amplitude
and constant geographical paths with time. The best
example of steady state interference is from a
cathodic protection (CP) system. Figure 4.6 shows
how interference can occur from a CP system on a
foreign pipeline.
Although interference is often shown where
pipelines cross, this may not always be the case
depending on the polarity and strength of the
voltage gradients to remote earth that extend from
Figure 4.6 Static Stray Current Interference
from a CP System
one structure or source to the other structure. That
is, tests should not be limited to only pipeline
crossings. Interference can be from one pipeline’s cathodic gradient causing discharge from the
other pipeline or from an anodic gradient causing a current pickup that must leave the other
pipeline by some means to return to its source.
4.2.1 Current Discharge Interference
When a voltage gradient that is negative with respect to remote earth overlaps a foreign
structure, it promotes a detrimental current discharge from the foreign structure in the area of
influence. This cathodic gradient could be considered as the controlling factor in this situation.
If current discharges from a structure, then it must pick up current outside of the area of
influence. This is illustrated in Figure 4.7.
Figure 4.7 Cathodic Interference
CP 2 | Technician
©NACE International
Stray Current
4-7
4.2.2 Current Pickup Interference
If a foreign structure crosses a voltage gradient that is positive with respect to remote earth, it
will promote a current pickup on the foreign structure within the area of influence. The anodic
gradient could be considered as the controlling factor in this case. Because there is an
unintended current pick up on the structure, the current must discharge outside the area of
influence to return to its source. This may be through the soil that is detrimental or may occur
through the foreign CP system. A current pickup is illustrated in Figure 4.8.
Figure 4.8 Current Pickup Interference
In certain conditions, a foreign structure may cross voltage gradients that promote anodic and
cathodic interference from a single current source. For example, a foreign structure could cross
the cathodically protected structure at one location and its impressed current groundbed at
another location.
4.2.3 Detection of Static Interference Currents
Certain changes and/or conditions in the system may indicate the presence of interfering
currents, including:
•
•
•
•
Structure-to-electrolyte potential changes on the affected structure caused by the foreign
cathodic protection current source
Changes in line current magnitude or direction caused by the foreign cathodic protection
current source
Localized pitting in areas near or immediately adjacent to a foreign structure
Breakdown of protective coatings in a localized area near a foreign anode bed or near any
other source of stray direct current
Static interference is detected by analysis of structure-to-electrolyte potential surveys. This can
sometimes misinterpreted as a structure-to-electrolyte potential survey because of static stray
currents. In an unprotected pipeline, the corroding (anodic) areas exhibit a potential that is
more negative when measured against a reference electrode, while the non-corroding (cathodic)
areas yield a more positive (less negative) potential. Consider the case where stray current is
towards the pipe in a protective direction. In this case, the stray current makes the soil more
©NACE International
CP 2 | Technician
4-8
Stray Current
positive than the pipe, and a more negative area appears on the structure-to-electrolyte potential
profile, giving a false indication of a corroding area. The reverse is true in areas where stray
current leaves the structure. Surface potential profiles may be misleading, as they may represent
a composite of current leaving the structure being surveyed and close to a crossing structure.
Static interference effects are detected similarly on protected pipelines. In this instance,
however, the interpretation of the potentials is opposite to that described above for an
unprotected pipeline. Figure 4.9 and Figure 4.10 show examples of close-interval surveys (CIS)
and the effect of static stray current on structure-to-electrolyte potentials for coated and
uncoated cathodically protected structures. The key points to consider in detecting static
interference effects on a pipeline are:
•
•
•
•
•
Potential profiles show abnormal variation from previous surveys.
Large negative values are noted remote from any cathodic protection system on the pipeline
or are noted on unprotected piping.
Unusual currents are measured along the pipeline.
Low negative or positive potentials are present.
Changes in the current output of a nearby cathodic protection system may cause changes in
the structure-to-electrolyte potential of the pipeline.
Figure 4.9 Effect of Static Stray Current on Pipeto-Electrolyte Potentials for Uncoated Cathodically
Protected Structure (Interfered-with line) (Line 2)
Figure 4.10 Effect of Static Stray Current on Pipe-toElectrolyte Potentials for Coated Cathodically
Protected Structure (Interfered-with line) (Line 2)
4.3 Sample Field Data
4.3.1 Structure-to-Electrolyte Potentials
When testing for stray current interference with an interrupter installed in the suspected source
of interference it is critical that the ON and OFF structure-to-electrolyte potentials be identified
CP 2 | Technician
©NACE International
Stray Current
4-9
by the length of the interrupter cycles and the assumption that the ON potential is the most
negative value must NOT be made.
Consider an example where two structures are protected by independent cathodic protection
(CP) systems and the structure designated as the “Foreign” Structure is afforded a new system
that adversely affects the other structure (Affected Structure). The data from three test locations
along the Affected Structure are shown in Table 4.1.
Table 4.1: Sample of Data Indicating Current Discharge and Pickup Interference
LOCATION
Structure-to-Electrolyte Potential (mVCSE)
X
Y
Z
ON
OFF
-1600
-400
-1000
-1100
-1050
-1000
A negative change in potentials as the “foreign” current comes ON indicates possible current
pick-up. In some cases, a negative shift on a structure when the foreign CP system is energized
can be attributed to voltage gradients in the environment that don’t result in current pick-up. A
potential shift in the positive direction (less negative) with the foreign structure CP system
energized can be indicative of an overall reduction in CP current collected on the affected
structure, or can indicate current discharge.
In the example data shown in Table 4.1, a current pickup is likely indicated at Point “X” on the
affected structure and suggests that it is in an anodic gradient of the foreign structures CP
anodes. A current discharge is indicated at Point “Y” on the affected structure as the potentials
become less negative than the free corrosion potential when the foreign structure’s CP system
comes ON. There is no current pickup or discharge at Point “Z” on the affected discharge.
4.3.2 Basic Stray Current Testing
The test procedure for stray current interference will vary depending on the structures and
conditions. With a sound understanding of the basic concepts the sample procedure given below
can be adapted to a specific situation.
4.3.2.1 Interruption
The first concept is to determine the effect of the interfering current on the “interfered-with”
pipeline or structure. This is done by interrupting only the “interfering” source. This is not to be
confused with determining a polarized potential used for criterion purposes. The “off”
potentials so obtained are not polarized potentials as the interfered-with pipeline CP current is
still being applied.
Interrupting the interfered-with source does not show the effect of the interfering power source
and interrupting them together is the combined effect which does not distinguish between the
“interfering” versus the “interfered-with” sources.
An option is to interrupt the two power sources on different cycles which overlap (Example: 4
seconds on/2seconds off and the other at 8 seconds on/4 seconds off).
©NACE International
CP 2 | Technician
4-10
Stray Current
4.3.2.2 Identification of “on” and “off” Potentials and Polarity
The “on” potential may be either more electronegative than the “off” potential or it can also be
more “electropositive”. One must not assume the “on” potential will always be the most
electronegative potential. Instead the “on” potential is identified by the length of the cycle time.
If using a long “on” cycle, either use a watch or count to determine which reading stays for the
longest period of time and this is the “on” potential regardless of being more or less than the
other potential.
The polarity of the potential can switch from the “on” cycle to the “off” cycle or from one
location to another. It is imperative to observe the polarity on the meter during each cycle at all
reading locations.
The examples in Table 4.2, taken with the interfering power source(s) interrupting, illustrate
how fatal errors can result in missing serious interference effects by always assuming the “on” is
more electronegative than the “off” and/or all readings are electronegative. The readings in
Table 4.2 Example 1 indicate that there is no current discharge at either Location A or B
however, the actual readings in Example 2 show there is indeed significant current discharge at
these locations. The condition at Location A was missed because the surveyor assumed
incorrectly that the “on” reading was the most electronegative. The condition at Location B
which is very severe was missed because the polarity was not noted.
Table 4.2: Examples of Incorrect Potential Records
4.3.2.3 Reference Electrode and Structure Contact
The reference electrode must be near the structure but in the cathodic or anode gradient caused
by the interfering source that is, the expected point of maximum exposure.
CP 2 | Technician
©NACE International
Stray Current
4-11
For example, there is a pipeline crossing in the middle of a field but the test station is located 20
meters (66 feet) away at a fence, the test station may be outside of the cathodic gradient at the
crossing. A reference electrode located at the test station is not expected to determine the
condition at the crossing. The reference electrode must be placed at the crossing and the
preferred location would be between the pipelines. The voltmeter wires must be extended to the
test station.
Should there be a resistance bond between the pipelines, the wires carrying current must not be
used for structure-to-electrolyte potential measurements. The voltage (IR) drop in the wire due
to the current and wire resistance will increase the electronegative potential value on the
positive side of the resistor (interfered-with) and reduce the electronegative potential on the
other side (interfering).
The following example illustrates this error:
Assume:
Ibond = 2 A
If bond wire is #12 AWG and 20 meters (66 feet) long
Rwire = 0.16 Ohms
Verror = IR = 2A x 0.16 Ohms
= +/- 0.32V = +/- 320 mV … a very large error!
4.3.2.4 Test Data
The data in Table 4.3 is taken with the interfering source interrupted, that is, the “off” potentials
is with the interfering structure source “off” but the interfered-with structure source is still “on”.
Therefore the “off” potential is not a true potential. The potentials recorded are only on the
interfered-with pipeline. Locations B and C both show cathodic interference effects with the
potentials becoming less electronegative (more electropositive) with the interfering current
coming on. The point of maximum exposure is the combined largest shift in potentials with the
least electronegative potential.
Table 4.3: Potentials Showing Current Discharge Interference
Table 4.4 are potentials on the “interfered-with” pipeline but with the “interfering” source being
interrupted. Locations B and C both indicate anodic interference with Location B the point of
maximum exposure with the largest shift and the most electronegative potential.
©NACE International
CP 2 | Technician
4-12
Stray Current
Table 4.4: Potentials Showing Current Pickup Interference
4.3.3 Current Measurements
Current measurements within a structure such as a pipeline can be used to predict current
pickup and discharge areas using the principle of Kirchoff’s Current Law as illustrated by Figure
4.11.
Figure 4.11 Current Pickup and Discharge Using Pipeline Current
Current was measured at locations A, B, and C and the current discharge or pickup was
determined using Kirchoff’s Current Law, that is, the difference in current between the points
measured represents a current pickup or discharge. In Figure 4.11, there must be a current
discharge between A and B equal to the difference of current (1.0 – (-2.0) = 3.0 A) while there
must be a current pickup between B and C equal to the current difference between these points
(-2.0 - 4.0 = -6.0 A).
4.4 Resolving Interference Problems
Interference problems are individual in nature, and the resolution should be agreeable to all
parties involved. Resolving interference problems generally involves one or more of the
following:
•
•
•
•
Removal of the detrimental effects of interfering current by installing a metallic return path
Counteracting the effect of interfering current by applying cathodic protection
Consultation with utility coordinating committee
Removing or relocating the interfering current source
CP 2 | Technician
©NACE International
Stray Current
•
4-13
Preventing the pick up or limitation of the interfering current
These general approaches can be translated into some typical specific techniques:
•
•
•
•
•
•
•
•
•
Adjust current output from the interfering systems.
Reduce the stray current at the source (e.g., isolation from ground, better conductivity of the
negative return paths, or lower voltages).
Apply coating to current pick-up area(s).
Install a mitigation bond, or electrical connection, between the structures to drain the stray
current back to its source through an electrical conductor rather than the earth.
Relocate existing structures or re-route proposed structures.
Properly locate isolating fittings.
Apply cathodic protection to the affected structure at the interfering current’s discharge site.
Relocate anodes
Break up the structure of interest into smaller electrically isolated segments to reduce the
stray current voltage gradients being traversed by the structure.
4.4.1 Tests with Bonds
The potentials taken in testing for and mitigating stray current interference are not intended to
duplicate a polarized potential survey to confirm a cathodic protection criterion. If a potential is
taken with a bond in place, the system is still tied to a cathodic protection system. If the bond
current is interrupted, the resulting potential will be subject to the effect of interference. A true
polarized potential must be taken with all DC power sources and any bond interrupted. Do not
be confused with the “off” potentials used in interference as being a polarized potential.
Because of the above problems, the “on” potential is often used as a “target” potential. This “on”
potential is related to a polarized potential obtained with all sources interrupted. The intent of
any mitigation device is to return the pipeline back to the target “on” potential. There is no
obligation to meet a cathodic protection criterion if it was not meeting it without interference.
A possible procedure to test and install a mitigation bond is given below.
•
•
•
•
•
•
•
Interrupt “interfering” and “interfered-with” power sources at different cycles or separately
Determine the point of “maximum electropositive shift exposure” with all power sources
“on”. This will be the largest electropositive potential shift and/or the least electronegative
potential.
Determine the interfered-with “on” and “off” potentials when interfering power source off.
The true polarized potential is obtained with all power sources “off”. Relate the “on” to the
“off” potential for future reference.
“Target” potential is the interfered-with “on” potential at maximum electropositive shift
exposure with interfering power sources “off”.
Remove interrupter(s) from interfering power sources.
Install bond and measure potentials on both systems.
Adjust resistance until interfered-with potential meets the target “on” potential.
©NACE International
CP 2 | Technician
4-14
Stray Current
Tests using cathodic protection mitigation such as sacrificial anodes are more difficult as
readings may see the current discharge from the anodes.
The bonds for cathodic interference are to be
installed at the point(s) of maximum
electropositive shift exposure. However, it may
not always be practical and a nearby location is
chosen. Regardless, the bond must be installed at
a location where the interfering pipe potential is
more electronegative than the interfered-with
pipe potential. This will ensure the stray current
goes through the bond back to its source as
shown in Figure 4.12, Case 1.
If the potentials are reversed as shown in Figure
4.12 Case 2, the current will go in the wrong
direction and can increase the stray current
problem on the interfered-with pipeline.
In addition to measuring potentials on each side
of the bond (using noncurrent carrying wires) it
is very important to record not only the current
but the direction of current through the bond.
Figure 4.12 Current Direction Through Bond
Class Exercise
Complete the exercise at the end of the chapter.
CP 2 | Technician
©NACE International
Stray Current
4-15
4.4.2 Installation of Metallic Bonds to Control Interference
Figure 4.13 illustrates a metallic bond between pipelines. The resistance of the bond must be
lower than the parallel path through the soil.
Figure 4.13 Electrical Bonding
Note: Protected structure must be more negative than foreign structure at the bond location to
return current safely.
Figure 4.14 illustrates the use of a metallic bond to control stray current interference from a
transit system.
Figure 4.14 Installation of Metallic Bond
When installing metallic bonds, the following should be considered:
•
•
Uni-directional control devices, such as diodes or reverse current switches, may be required
in conjunction with the metallic bond if currents are changing magnitude and direction
present. These devices prevent reversal of current.
A resistor may be needed in the metallic bond circuit to control the electrical current from
the affected structure to the interfering structure. At the proper bond resistance, the discharge of interfering current from the structure to electrolyte is stopped.
©NACE International
CP 2 | Technician
4-16
•
•
Stray Current
If cathodic protection exists on the interfering structure, attaching metallic bonds can
reduce the magnitude of protection. Supplementary cathodic protection may then be
required on the interfering structure to compensate for this effect.
A metallic bond may not perform properly in the case of a cathodically protected bare or
poorly coated pipeline that is causing interference on a coated pipeline. A metallic bond can
increase the current discharge. Coating the bare pipe at current pickup points or installing
local galvanic anodes on the coated pipe may reduce interference effects.
4.4.2.1 Single Bond Problem
If after doing all that is practical to minimize the accumulation of stray currents on structures it
is necessary to control the stray current, a bond may be required. If there is a definite location
(i.e., structure such as the substation on the trolley system) of current discharge, it is frequently
possible to design a metallic bond through which this current can be returned to the traction
system or, in the case of an industrial operation, to the power source (Figure 4.15). This requires
accumulating certain data and calculating the needed bond resistance. Mitigation of dynamic
interference is not part of this course but is covered in an separate “Cathodic Protection
Interference” course.
Figure 4.15 Solution of a Single Bond Problem
In relatively simple cases where a single source of stray current is involved, a trial-and-error
solution may be possible. If you are only interested in eliminating the corrosive changes in
potential caused by the source using a bond connection, then a variable resistor of adequate
current-carrying capacity is inserted at the proposed bond location. The value of resistance is
slowly reduced while the structure-to-electrolyte at the most critical location is observed. When
the structure-to-electrolyte potential of the interfered-with structure at the most critical
location is returned to normal, the correct value of resistance for the bond has been set.
Typically, it is desirable to use a resistance bond instead of a solid bond for the following
reasons:
•
•
•
The resistance bond limits the amount of current for the structure being protected.
The resistance bond must be of low enough resistance to ensure that the stray current return
is using this metallic path rather than the electrolyte.
Resistance bonds are subject to damage by high current surges and therefore must be
inspected frequently (see Chapter 7)
CP 2 | Technician
©NACE International
Stray Current
4-17
4.4.2.2 Controlling the Direction of Stray Current Through the Bond
Sometimes the direction of stray current through the bond is in the desired direction for much
of the time but not all of the time. In these cases, stray current is toward the source when the
structure to be protected is discharging current (corroding) and the reverse when the structure
is receiving stray current. Stray current onto the structure is not desirable since it causes a
discharge point at some other location(s). Diodes or reverse-current switches are used to
prevent a reverse current. The resistance to the forward current created by these devices must be
included in the bond calculations.
4.4.2.3 Reverse-Current Switch
With dynamic stray current sources the direction of
current through a bond could reverse causing
accelerated corrosion. A diode can be installed to
prevent this but it may be slow to respond. A relay
can be installed that will open or reverse current. A
combination of a diode and a relay reduces the
disadvantages of each. Another solution may be a
potentially controlled rectifier that controls the
current in a forced drainage bond as shown in Figure
4.16.
4.4.2.4 Controlling Stray Current Through
Cathodic Protection
Figure 4.16 Forced Drainage Bond
Stray current can safely be returned to its source
through a cathodic protection system. An example using a carefully located sacrificial (galvanic)
anode is shown in Figure 4.17.
Figure 4.17 Galvanic Anodes
©NACE International
CP 2 | Technician
4-18
Stray Current
4.4.2.5 Coating
Coating of a known current pickup area can reduce the amount of stray current but the major
portion of the anodic gradient should be coated (see Figure 4.18). Do not coat areas of current
discharge as this will cause accelerated pitting at the small coating holidays.
Figure 4.18 Protective Coatings
4.5 AC Testing and Mitigation
Increased difficulty in obtaining utility rights-of-way and the concept of utility corridors have
brought many underground structures, and pipelines in particular, into close proximity with
electric power transmission and distribution systems. The electromagnetic field created by the
alternating current expands and collapses and changes direction 100 to 120 times per second
(Figure 4.19).
Figure 4.19 AC Interference on Pipeline from
Changing Electromagnetic Field
Any metallic object subjected to an alternating electromagnetic field will exhibit an induced
voltage. In addition, power conductor faults to ground can cause substantial fault currents in the
underground structure.
CP 2 | Technician
©NACE International
Stray Current
4-19
There are three basic methods by which AC currents and voltages appear on metallic structures
near AC power lines. These methods are as follows:
•
•
•
Electrostatic coupling, where the structure acts as one side of a capacitor with respect to
ground. This is only of concern when the structure is abovegrade (e.g., pipeline supported
on skids).
Electromagnetic induction, where the structure acts as the single-turn secondary of an aircore transformer in which the overhead power line is the primary. This type of induction
may occur when the structure is either above or below ground.
Resistive coupling, where AC power is transmitted to ground the underground structure.
Stray alternating currents can cause corrosion on metallic structures, although the amount of
metal loss is less than an equivalent amount of DC current discharge would produce. For
instance, 1 A DC discharge results in a loss of approximately 20 lbs of steel in one year, while one
ampere of AC would consume less than 1 lb. The corrosion weight loss varies depending on the
metal and the alternating current density. For instance, aluminum can exhibit a weight loss of
approximately 40% of the DC equivalent at AC densities greater than about 40 mA/cm2.
Even though the corrosion weight loss for AC currents is less than for equivalent DC currents,
the magnitude of AC stray current is often large–hundreds of amperes under electromagnetic
induction and thousands of amperes during power line faults. These high current levels can
produce a shock hazard for personnel and can damage the structure and related equipment,
such as cathodic protection facilities.
4.5.1 Electrostatic or Capacitive Coupling
Any two materials separated by a dielectric material can be considered as a capacitor.
Capacitance is the ability to store electrical charge between two conductors relative to the
voltage between the conductors. In this case the air is the dielectric and the power line is one
conductor while the pipe or equipment is the other conductor.
Injury is more likely from an uncontrolled
reaction to a shock rather than electrocution due
to this couple.
This coupling is of most concern on
aboveground equipment or pipelines such as
during construction or maintenance of the
pipeline. During these operations a qualified
person should be on site to monitor the AC
voltage and install grounds or bonds around
open sections of pipe as necessary.
Figure 4.20 Electrostatic Coupling
4.5.2 Electromagnetic Induction
The most important AC-induced interference current occurs as a result of electromagnetic
induction as illustrated in Figure 4.19. Charges in the pipeline are alternately separated toward
opposite ends of the pipeline. The resulting stray current magnitude is directly proportional to
the phase currents (I) and their relative magnitudes and to the length (L) of mutual exposure;
it is inversely proportional to the relative distance (d) between the structure and the power line
conductors.
©NACE International
CP 2 | Technician
4-20
Stray Current
Figure 4.21 Electromagnetically-Induced AC Voltages
Figure 4.22 Electromagnetically-Induced Voltage Analogy
The induced voltage does not directly depend on the power line voltage; therefore, relatively low
voltage AC power systems can produce electromagnetically-induced currents. In particular,
single-phase heavily loaded AC power distribution lines can produce significant AC straycurrent activity.
The pipe acts as a single-turn secondary of an air-core transformer, and the overhead AC power
lines are primary (see Figures 4.21 and 4.22). The induced voltage (Vinduced) appears across the
ends of the pipe. The voltage to ground (Vground) at each end of the structure is one-half the
total induced voltage.
Figure 4.23 Electromagnetically-Induced Voltages on a
Parallel Pipeline
CP 2 | Technician
©NACE International
Stray Current
4-21
For a short, well-coated structure that is not electrically lossy (i.e., causing attenuation or
dissipation of electrical energy), the induced voltage profile with distance is linear. However, for
poorly coated or very long, well-coated structures the voltage profile is nonlinear and the
induced voltage peaks are of a lower magnitude. The induced voltage peaks appear at any
electromagnetic field or pipeline discontinuity. For example, where a pipeline closely parallels a
power line for some distance, induced voltage peaks would be expected where the power line
and pipeline separate. Under such circumstances, the induced voltage effect can extend some
distance along the pipeline from the power line right-of-way.
Measuring the structure’s AC voltage with respect to earth can easily identify interference
currents of an AC origin. The reference electrode used for cathodic protection measurements
can be used as the ground contact. It is prudent to measure both AC voltage and DC potentials
with respect to earth on all structures in close proximity to power lines. Typically, the DC
potentials will be more positive at the AC voltage peaks than in the absence of AC interference.
4.5.3 Resistance or Conductive Coupling
During power line faults to ground, large AC currents can be transmitted to the earth through
resistance coupling and, subsequently, into nearby underground structures. These currents,
which can be several thousand amperes, can cause substantial physical damage to structure
coatings; in extreme cases where the AC density is high, steel piping has been known to melt.
Normally, these faults occur infrequently and are of short duration; therefore, they do not
represent a serious risk to operating personnel.
4.5.4 AC Voltage on Pipelines
Hazardous AC voltages can occur on a structure as a result of induction, ground return
currents, or faulted power circuits. In cases where a structure or test leads parallel power
transmission circuits, significant AC voltages may be encountered.
If an AC voltage is near or is in excess of 15 V, the structure is considered hazardous and
personnel working on the structure must be advised that a hazardous situation exits. The owner
or supervisor must also be advised that steps need to be taken to reduce the hazardous voltage.
If the AC voltage is determined to be less than 15 V, no specific action is necessary. However, be
aware that unlike DC potentials the AC voltage changes with the load on the power line so that
it can increase from when measured to later in the day. Therefore contact the power company to
find out what percent of load they were operating at when the readings were taken. This will
indicate the AC voltage that can be expected at full load conditions otherwise continue to
measure it during the day. Whenever an AC voltage is close to 15 V (e.g., 12 VAC to 14 VAC) the
same action should be taken as if it were 15 VAC or greater.
4.5.5 Measurement of AC Voltage-to-Ground
The measurement of an AC voltage-to-ground is similar to a DC structure-to-electrolyte
potential in that the voltage is measured between the structure and a reference electrode in the
ground. There are significant differences including:
•
The voltage measured may be hazardous and safety is of great concern. Do not touch any
metal directly or through the meter leads/clips until it is established that there is no hazardous voltage.
©NACE International
CP 2 | Technician
4-22
•
•
•
•
•
•
Stray Current
The reference electrode can be any bare metal but if a structure-to-electrolyte potential is
also to be taken then a standard reference electrode can be used.
The exposed portions of the reference electrode must not be touched and the electrode is to
be installed first. If using a CSE then the top should be taped to prevent accidental contact.
Induced AC voltage changes with the power line load and/or power line fault conditions.
AC voltages change on aboveground pipelines under construction as the pipe length
increases during the welding operation.
Induced AC voltages can be expected to
be higher at the discontinuities between
the pipeline and the power line, that is,
where they come together, separate or
there is a change in the pipe or power line
electrical characteristic (Figure 4.24).
The measurement should duplicate step
voltages. Therefore the electrode should
be about one (1) meter away from the
Figure 4.24 Examples of a Discontinuity
closest contact point(s) above ground on
the structure. (Unlike structure-to-electrolyte potentials where the reference electrode is to be placed close to the structure where it
enters the ground.)
Measure the AC structure-to-ground voltage first to make certain that it is safe to continue to
work.
First, place the electrode into the ground approximately one (1) meter from the structure
contact point then contact the structure with an insulated probe and turn the meter to AC Volts.
If the AC voltage is 15 V or greater, cease work until the AC voltage has been mitigated or, if
qualified, proceed with further investigation into the cause and best means of mitigation. At no
time should the structure be contacted under these conditions. Qualified personnel are to install
temporary grounds, grids and/or nonmetallic fences at the work area or where the public can
contact the structure until permanent protective equipment is installed.
4.5.6 Mitigation of AC Interference
The close proximity of structures to AC power lines and their sharing parallel paths for
relatively long distances is the principal cause of stray AC. If the structure is remote from the
power line(s), the interference can be virtually eliminated. Obviously, this method of mitigation
is practical only at the preconstruction stage of either the power line(s) or the structure.
Otherwise, the mitigation must be accomplished by alternative methods.
AC mitigation methods include:
•
•
•
Significant separation between pipe and HVAC system
Ground pipe using distributed galvanic anodes
Grounding pipe using a metal such as zinc, magnesium, steel, or copper. DC decouplers
such as a capacitor, polarization cells, or polarization cell replacements (PCR) connected
between pipe and a separate “grounding” structure will reduce the CP requirements when a
more noble ground is tied directly to the structure. A DC decoupler allows AC current to
pass but blocks DC current.
CP 2 | Technician
©NACE International
Stray Current
•
•
•
4-23
Note: These devices may interfere with close interval surveys.
Protective devices for electrical isolating devices such as flange kits or joints.
Step-and-touch protection systems (gradient mats or grids)
Figure 4.23 shows that the induced voltage is reduced if the structure becomes electrically
conductive to earth. A well-coated structure would normally result in higher induced voltages.
On short lines, this effect can be remedied by using distributed sacrificial anodes on the
structure; the anodes will not only be sufficient to provide cathodic protection current but will
also simultaneously lower the resistance of the structure with respect to earth. Another
approach is to use a zinc strip or ribbon anode parallel to the structure as the grounding
method.
On longer lines, the approach is to install grounds
at the higher voltage peaks, normally at the
discontinuities. In Figure 4.25 a similar effect
could likely be achieved by installing larger
grounds at the two voltage peaks.
Even with the grounds, hazardous voltages may
still exist at other separation points and require
more extensive grounds to reduce the AC voltage
to 15 V or less.
Corrosion personnel must be aware of the possible
shock hazard that can appear on a structure
Figure 4.25 Mitigation of AC Interference Using
subjected to AC interference. Precautions such as
Distributed Galvanic Anodes
nonmetallic dead-front test stations should be
incorporated into the cathodic protection systems,
and nearby cathodic protection rectifiers should be protected from AC fault currents with
devices such as capacitors, polarization cells, and zinc grounding cells.
Bare casings interconnected through a capacitor bank, polarization cell replacement, or a
polarization cell to the structure also are effective in mitigating AC interference.
4.5.6.1 Polarization Cells
Figure 4.26 shows a polarization cell used as a DC
decoupler that allows AC current to pass to a ground
while blocking the DC current intended for the cathodic
protection of the structure. The cell consists of a
container filled with a potassium hydroxide solution (the
electrolyte) into which stainless steel plates are
immersed and alternately connected to the cell
terminals. One of the cell terminals is connected to the
structure and the other to ground (or if used to protect
an insulating joint from AC, the terminals are connected
across the insulating joint).
The cell acts as an electrochemical switch to shunt
voltage to ground. Under normal conditions, the plates
of the cell polarize and allow normal cathodic protection
©NACE International
Figure 4.26 Polarization Cell
CP 2 | Technician
4-24
Stray Current
potentials to exist. As the applied voltage across the cell increases from either AC or DC, the
polarization film on the plates breaks down and the cell shunts current. The cells must be
properly vented (to allow gases generated during operation to escape) and periodically
inspected to ensure adequate electrolyte levels.
4.5.6.2 Semiconductor Devices
Solid state devices are available that block the low-potential DC cathodic protection current
from leaking across an insulating device while still providing instant protection from highvoltage spikes and induced AC. These devices do not involve caustic liquid electrolytes and are a
low-maintenance device. Figure 4.27 shows a semiconductor-type device.
Figure 4.27 Semiconductor Device for AC and High-Voltage
Fault Control (courtesy of Dairy land Electrical Industries)
4.5.6.3 Ground Mats
Ground mats may be required to protect personnel from electric shock while working on well
coated pipelines. Induced voltage from AC power lines and lightning strikes can create large
voltage gradients between a pipeline and earth.
Ground mats are metal conductors placed in the soil around locations where a person may come
in contact with the pipeline. Test station wires, line valves, and other fittings are examples of
where a hazard may exist. The ground mat is connected to the pipe thus assuring that the pipe
and the ground in the immediate area are at the same electrical voltage. They are not intended to
be an electrical ground as they are installed close to the surface often in high-resistivity soil or
frost.
Ground mats can be made from any metal. A more active metal such as zinc or magnesium is
used to have minimum impact on the cathodic protection system. Other metal such as copper
or steel can be used but will add significantly to the current required for cathodic protection due
to their large area of earth contact. If the mats are constructed of copper or other noble alloy or
metal, adequate cathodic protection must be applied to eliminate the corrosive galvanic couple
or isolated using a DC decoupler. Figure 4.28 illustrates how ground mats are applied with the
rings becoming consecutively deeper at about 15° away from the structure.
CP 2 | Technician
©NACE International
Stray Current
4-25
It should be noted that if zinc or magnesium is used as a gradient mat around a test station, then
the instant OFF potential is no longer valid as all sources of DC current have not been
interrupted.
Figure 4.28 Typical Ground Mat Used to Protect
Personnel from Electric Shock
Figure 4.29 Spiral Gradient Ground Map (Top
View)
4.5.7 AC Corrosion
AC current has long been known to cause corrosion but at a rate much below that for an
equivalent amount of DC current. It was also largely believed that AC corrosion could be
overcome by cathodic protection. However, in the 1990’s corrosion failures occurred on
cathodically protected pipelines that were attributed to AC. Research is ongoing with some
recent understanding summarized in NACE SP21424-20181 and ISO 18086:20152.
A very simplified description of the AC corrosion process is during the anodic half AC cycle, the
bare metal surface is oxidized with the formation of an oxide film while during the cathodic
cycle, this oxide film is reduced and converted to a non-protective rust layer. In the following
anodic cycle, a new oxide film grows, and the oxide film is increased and so the cycles continue.
It is assumed that the oxide film never fully forms in field conditions otherwise the corrosion
rate would be much higher. However, subsequent research has shown that AC corrosion is much
more complex.
AC corrosion is a result of the AC current density that in turn is dependent on the AC voltage
and the spread resistance of the steel surface at the coating holiday. Spread resistance refers to
the resistance from the pipe to remote earth through a specific coating defect, or of a coupon or
probe of known area1.
In practice, the current density is difficult to predict as the holiday size is not known, and the
spread resistance is not only dependent on the local soil resistivity but on the presence of earth
alkaline ions (Ca2+ & Mg2+) and/or alkaline ions (Na+, K+, Li+) in the soil. Calcium ions form
products that increase the spread resistance, but sodium can form hygroscopic products (attract
water) that reduce the spread resistance.
With a CP polarized potential more electropositive than ~ -1.10 VSCE in an environment
containing large quantities of earth alkaline ions, calcium deposits form on the surface of the
1. NACE SP21424-2018 Alternating Current Corrosion on Cathodically Protected Pipelines: Risk Assessment, Mitigation and
Monitoring
2. ISO 18086 Corrosion of metals and alloys – Determination of AC corrosion – Protection criteria
©NACE International
CP 2 | Technician
4-26
Stray Current
steel resulting in an increase of spread resistance. However, when the CP polarized potential is
more electronegative than ~ -1.10 VSCE with a hydrogen evolution reaction, the deposits formed
on the steel surface are destroyed and the spread resistance decreases3,4.
AC corrosion can be mitigated by CP at low AC and DC current densities but cannot be
mitigated by cathodic protection at a high AC or DC current densities.
Further the AC current density can be greater at the edges of the coating holiday or coupon than
in the middle thus an average current density may not yield an accurate prediction.
The prediction of AC corrosion is best completed using coupons or probes recognizing that
these results give an average current density. Since conditions vary, a single voltage threshold
value to control AC corrosion is not applicable.
NACE SP21424-2018 provides the following current density criteria with effective CP:
“Unless effective AC corrosion control has been otherwise documented, the AC current density
should not exceed a time weighted average of:
•
30 A/m2 (2.79 A/ft2)if DC current density exceeds 1 A/m2 (0.093 A/ft2)
• 100 A/m2 (9.3 A/ft2) if DC current density is less than 1 A/m2”
ISO 18086:2015 provides the following criteria.
“ …effective AC corrosion mitigation can be achieved by meeting the cathodic protection
potentials defined in ISO 15589-1 :2015 Table 1 and
•
maintaining the AC current density (rms) over a representative period of time (e.g. 24 h) to
be lower than 30 A/m2 on a 1 cm2 coupon or probe, or
•
maintaining the average cathodic current density over a representative period of time (e.g.
24 h) lower than 1 A/m2 on a 1 cm2 coupon or probe if AC current density (rms) is more
than 30 A/m2, or
• maintaining the ratio between AC current density (Ja.c.) and DC current density (Jd.c.) less
than 5 over a representative period of time (e.g. 24 h).
Note: Current density ratios between 3 and 5 indicate a small risk of AC corrosion. However, to
reduce the corrosion risk to a minimum value, smaller ratios than 3 are preferable.”
Some notable differences in criteria between these standards are given below thus judgement is
necessary with their application.
•
NACE states that the “… AC current density should not exceed 30 A/m2 if the DC current
density exceeds 1 A/m2” while ISO states the “…AC current density be lower than 30 A/m2”
(regardless of DC current density)
3. Yanxia Du, Sili Xie, Yingwu Xiao etc. Research on the Effects of Environmental Parameters on AC corrosion Behavior. NACE
CORROSION 2018. Paper No. 10676.
4. Andreas Junker, Louise J. Belmonte. Nick Kioupis. Investigation of stone-hard-soil formation from AC corrosion of cathodically protected pipeline. Materials and Corrosion.2018,69:1170-1179.
CP 2 | Technician
©NACE International
Stray Current
•
•
4-27
NACE infers an upper AC current density limit of 100 A/m2 if the DC current density is less
than 1 A/m2 while ISO does not indicate an upper limit if the AC current density is greater
than 30 A/m2.
Current density ratios in the ISO criteria are not addressed in the NACE criteria.
A low DC current density yields a limited increase in pH, does not significantly change the
spread resistance and has less reductive effect on the metal oxides. A high DC current density
can result in either a high or low AC corrosion rate. The ratio of AC to DC current densities may
be used to assess the possibility of corrosion, where the precise coupon area is not critical. If the
ratio is below a certain threshold (see ISO 18086:2015 criteria third bullet), no AC corrosion
occurs since metal oxidation in the anodic half wave is prevented. The ratio is used only as an
indicator of possible corrosion.
Research has also demonstrated that a polarized potential of -850 mVCSE may not be effective in
controlling AC corrosion, rather an increased electronegative potential may be necessary to a
limit (e.g. of limit is -1.15 VCSE).
In summary, AC corrosion mechanisms are still being researched and debated. At low AC
current densities, CP can be successful in controlling AC corrosion, but caution against high DC
current densities or potentials more electronegative than -1.15 VCSE is advised. The present
consensus is that coupons installed where AC current densities are likely to be high are the
preferred method to predict AC corrosion or its successful mitigation. Lowering the AC voltage
by grounding will in turn reduce the AC current density5.
5. NACE SP0177, Mitigation of Alternating Current and Lightning Effects on Metallic Structures and Corrosion Control Systems
©NACE International
CP 2 | Technician
4-28
Stray Current
Experiment 4.1 - Demonstration of Stray Current Interference
Preparation
•
•
•
Use fresh water (no salt), as the higher the resistivity, the larger the effect
Keep the water shallow (e.g. ~1cm above the structures), to increase the resistance of the
ionic path through the water relative to that through the ‘foreign structure’
In step 4 below, add a resistance in series with 9V battery to limit & regulate the current to
~5-10 mA during the experiment and ~2-5 mA if left overnight.
Procedure
1.
Place tap water in tray
2.
Place steel sheet or steel rod across left side of tray (see Figure 4.30 A to C)
3.
Measure the pH with litmus paper and record in the table below and measure potentials at
A. B, C
4.
Connect the steel sheet or rod to a CP system (a battery, resistor and anode installed to the
extreme right side of the tray) (See Figure 4.30)
5.
Install an ammeter or shunt in the circuit and measure or calculate current
6.
Measure the potentials to the steel at locations A, B, C and record the results in the table
below
Figure 4.30 Set up of Steel Rod (pipeline) and isolated (foreign
pipeline) demonstrating current pickup and current discharge
interference
7.
Measure the pH at A, B & C after CP applied
8.
Disconnect the CP system
9.
Place a steel rod lengthwise along tray (Figure 4.30 D to F)
CP 2 | Technician
©NACE International
Stray Current
4-29
10. Measure potentials and pH along this foreign (isolated) steel rod at locations D, E & F and
record the results in the table below
11. Connect the CP system
12. Repeat the potentials at A, B, C, D, E, & F and current and record the results in the table
below.
13. Install a resistance bond between the CP protected line to the foreign structure (Figure
4.31).
Figure 4.31 Resistance Bond and Ammeter Installed Between
Structures
14. Repeat step 12 plus the bond current/resistance and record the results in the table below.
15. Remove the resistance bond.
16. Leave CP operating overnight. Note corrosion occurring due to interference and record pH
©NACE International
CP 2 | Technician
4-30
Stray Current
Results
Step
CP Structure-to-Electrolyte
Potentials (mVCSE) or pH
A
B
C
Foreign Structure-to-Electrolyte
Potentials (mVCSE)
D
E
F
ICCP
Current
(mA)
Step 3
Step 3
pH
Steps 5,
6&7
Step 7
pH
Step 10
Step 10
pH
Step 12
Step 14
Step 15
pH
•
Resistance bond current ________ mA
•
Bond resistance ______ Ohms
Conclusions
•
•
•
•
•
•
•
Stray current pickup on the foreign structure occurs at ______ (name all)
Stray current discharge on the foreign structure occurs at ______ (name all)
An increase in current on the CP structure occurs at ________ (name all)
A decrease in current on the CP structure occurs at ________ (name all)
Effect on potential of bonding the foreign structure to the CP structure ________________
Effect on current of bonding the foreign structure to the CP structure __________________
The effect of pH was _________________________________________ (at each location)
CP 2 | Technician
©NACE International
Chapter 4
Stray Current Interference
®
Stray Current - Definition
2
Stray current: Current through an electrical path(s) other than
the intended circuit
Interference: Any detectable electrical disturbance on a structure
caused by a stray current
▪ Stray current not galvanic corrosion current between anodes and
cathodes on same structure
▪ Stray current or interference, can be classified as being either:
▪ Static
▪ Dynamic
CP2 | Technician
Stray Current
3
▪ Stray current can be either DC or AC
▪ AC can be both a safety and a corrosion hazard
CP2 | Technician
1
DC Stray Current Corrosion
4
Foreign Structure
Corrosion occurs at
Current discharge
point
DC Current
Source
CP2 | Technician
DC Stray Current Corrosion
5
At current discharge, accelerated corrosion possible
▪ large magnitude of current or
▪ high current density
Consumption rates are:
▪ Ferrous 9.1 Kg / A-yr (20 pounds / A-yr)
▪ Copper 10.4 Kg / A-yr (23 pounds / A-yr)
▪ Lead
33.85 Kg / A-yr (74.64 pounds / A-yr)
CP2 | Technician
Stray Current Analysis
6
▪ Source of the stray current?
▪ Area stray current enters the structure?
▪ Area stray current leaves the structure?
▪ Magnitude of the stray current?
▪ How can stray current be mitigated?
CP2 | Technician
2
Dynamic Stray Current
7
▪ Dynamic stray current changes in amplitude and/or direction
▪ Dynamic stray currents are
▪ man-made or
▪ geomagnetic (telluric current)
CP2 | Technician
Dynamic Stray Current Sources
8
▪ DC transit systems
▪ Welding
▪ Mining operations
▪ Electrical power transmission
▪ Industrial plants
▪ Telluric
CP2 | Technician
Stray Current
9
Transit Power Line
DC
Generator
Protection
(Cathodic Area)
Corrosion
(Anodic Area)
CP2 | Technician
3
Telluric Currents
10
▪ Natural Earth Currents
▪ Interaction of solar particles with Earth’s magnetic field
▪ Highest near magnetic poles
▪ Dynamic changes
▪ Affect Cathodic Protection Measurements
CP2 | Technician
Detection of Dynamic Stray Currents
11
▪ Structure-to-electrolyte potential changes
▪ Usually during reading
▪ Varying earth gradient voltages
▪ Changes in line current magnitude or direction
CP2 | Technician
Potential Fluctuating Due to Dynamic Stray Current
12
CP2 | Technician
4
Earth Current (Potential) Measurement Between Two
Reference Electrodes
13
Voltmeter With + Reading
+
-
Reference Electrode
Reference Electrode
Current
CP2 | Technician
Earth Current (Potential) Measurement Between Two
Reference Electrodes
(+)
(+)
V
V
V
V
(+)
14
(–)
V
V
(–)
(–)
CP2 | Technician
Mitigating Stray Current - General
15
▪ Stray current from one or more sources
▪ To successfully drain stray current from structure:
▪ Structure must tend to discharge stray current at bond
▪ Source must tend to pick up stray current at bond
▪ Interfering structure must be more electronegative than
interfered-with structure
▪ Sufficient current must be drained
CP2 | Technician
5
Static (Steady State)
16
Static or steady-state interference currents:
▪ those that maintain constant amplitude and constant
geographical paths
Example:
▪ CP systems
CP2 | Technician
Static Stray Current Interference from a CP System
17
Stray Current
CP2 | Technician
Types of Interference
18
▪ Current Discharge Interference
▪ Current Pickup Interference
With current pickup there may be an
associated current discharge
CP2 | Technician
6
Cathodic Interference
19
▪ Cathodic voltage gradient promoting current discharge from
foreign structure when it:
▪ overlaps a foreign structure’s gradient
▪ is electronegative with respect to remote earth,
▪ A corresponding current pick up current exists elsewhere
CP2 | Technician
Current Discharge Interference
Interference
Current
Pickup
Foreign
Pipe
20
Interference
Current
Pickup
Interference Current
Discharge
Voltage Gradients
Around the
Protected Pipe
Impressed Current
Anode bed Remote
from Foreign Pipe
Rectifier
Protected
Pipe
PROFILE VIEW
CP2 | Technician
Current Pickup Interference
21
▪ Anode gradient promoting current pick up on foreign
structure when it:
▪ overlaps the foreign structure’s gradient and
▪ is electropositive with respect to remote earth
▪ Current discharge elsewhere is concern for accelerated
corrosion
▪ Possible coating damage in anodic gradient
CP2 | Technician
7
Current Pickup Interference
Interference
Current
Discharge
Protected
Pipeline
Remote from
Foreign Pipe
Foreign
Pipe
22
Interference
Current Pickup
Interference
Current
Discharge
Voltage Gradients
Around the Anode
bed
Rectifier
Impressed
Current Anode bed
TOP VIEW
CP2 | Technician
Detection of Static Interference Currents
23
▪ Structure-to-electrolyte potential changes
▪ Changes in the structure current magnitude or direction
▪ Localized pitting near or at foreign structure
▪ Coating breakdown in localized area near stray current source
CP2 | Technician
Static Interference Detection by Potentials
24
Current discharge indicated by electropositive potential change
▪ Energy source is external
Mixed metal system:
▪ Most electronegative metal discharges most current and
corrodes
▪ Energy source is between metals
CP2 | Technician
8
Current Pickup from Interfering Anode bed
Effect of Static Stray
Current on Potentials for
Uncoated CP Structure
25
1400
Struccture-to-Electrolye
Potential (-mVcse)
1200
Current pickup from
Interfering Anodes
1000
800
600
400
A
B
C
D
Current Discharge
To Interfering Line
200
(+)
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Distance
Interfering
Rectifier
Interfering
Line
Line
1
B
Interfered-with
Line
A
Line 2
D
CP2 | Technician
Current Pickup from Interfering Anode bed
Struccture-to-Electrolye
Potential (-mVcse)
Effect of Static Stray
Current on Potentials
for Coated CP Structure
1400
Current pickup from
Interfering Anode Bed
1200
1000
A
800
B
C
600
400
Current Discharge
To Interfering Line
200
(+)
26
1600
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Distance
Interfering
Rectifier
Line
1
B
Interfering
Line
Interfered-with
Line
A
Line 2
D
CP2 | Technician
Combined Current Discharge and Pickup Interference
27
Potential Profile On Foreign Pipeline
Current Pickup –
Near Anode Bed
–
E
+
Current Discharge
CP2 | Technician
9
Interference Shown by Potential Field Data
28
▪ (X) More electronegative with current ON - current pickup
▪ (Y) More electropositive with current ON - current discharge
▪ (Z) No effect
Structure-to-Electrolyte Potential (mV CSE)
Location
ON
OFF
X
-1600
-1100
Y
-400
-1050
Z
-1000
-1000
CP2 | Technician
Steady State Interference Testing with Potentials
29
Interrupt “interfering” power source
▪ NOT power source on “interfered-with” structure
▪ NOT both rectifiers interrupted synchronously
Use different cycle length to determine ON or OFF potential
▪ DO NOT assume the most electronegative is ON potential!
CP2 | Technician
Missed Interference
▪ Interference missed by incorrectly
identifying on/off potentials and/or
polarity
▪ Example 1 incorrectly indicates
no current discharge at Location
A or B
▪ Example 2 correct readings
showing current discharge
especially at B
▪ Location A was missed by assuming
the “on” was the highest number
▪ Location B was missed by not
reading the polarity
30
Assumed – mV with cycle and Polarity Ignored
Potentials
(mVcse)
Location
Remarks
Incorrect
ON
OFF
A
1000
800
B
1000
850
Actual measurements
Potentials
(mVcse)
Location
ON
OFF
A
-800
-1000
B
+1000
+850
Remarks
CP2 | Technician
10
Structure-to-Electrolyte Potential Measurements
Reference electrode
▪ Must be at point of exposure
▪ Example:
▪ Test station remote from pipe
crossing
▪ Outside cathodic gradient
▪ Reference must be placed at
crossing
▪ Voltmeter wires extended to
nearest test station
▪ Preferred reference location between the pipelines
31
Structure Contact for Potentials
▪ Must NOT use a current carrying wire
▪ If current bond wires used for
potential measurements:
▪ Current increases negative
potential on positive (interferedwith) side
▪ Reduces negative potential on the
negative (interfering) side
▪ Example:
▪ Ibond = 2 A
▪ Bond Wire #12 AWG - 20 meters
▪ Rwire = 0.16 Ohms
▪ Eerror = IR = 2A x 0.16 Ohms
▪ = +/- 0.32V = +/- 320 mV
CP2 | Technician
Interference Test Data
32
Current Discharge Interference
Current Pickup Interference
▪ Interfering source interrupted (OFF
potential is with Interfered-with on)
▪ Interfering source interrupted (OFF
potential is with Interfered-with on)
▪ Potentials taken on interfered-with pipe
▪ Potentials taken on interfered-with pipe
▪ OFF is not a polarized potential
▪ OFF is not a polarized potential
▪ Table 1 Location B & C experiencing
current discharge interference but C is
maximum exposure
▪ Table 2 Location B & C experiencing
current pickup interference but B is
maximum exposure
Table 1
Potentials (mVcse)
Location
ON
OFF
A
-1000
-1000
B
-800
-870
C
-600
-840
D
-900
-900
Remarks
Table 2
Potentials (mVcse)
Location
Max exposure
ON
OFF
A
-1100
-1100
B
-1800
-1200
C
-1400
-1100
D
-1000
-1000
Remarks
Max exposure
CP2 | Technician
Interference from Current Data
33
Current reducing or in opposite directions indicates
current discharge
Measured
Calculated
A
B
C
1.0 A
2.0 A
4.0 A
3.0 A
6.0 A
CP2 | Technician
11
Resolving Interference Problems
34
▪ Provide metallic return path for interfering current
▪ Counteract interfering current by CP
▪ Install sacrificial anode by interfering pipe and
▪ Connect to interfered-with pipe
▪ Consult with owners and/or Electrolysis Coordinating
Committee to readjust source
▪ Removal or relocation of interfering current source
▪ Prevention of pick up or limit interfering current
CP2 | Technician
Resolving Interference Problems
35
▪ Adjust current output from interfering systems
▪ Reduce stray current at the source
▪ Apply coatings to strategic areas (current pickup not
discharge areas)
▪ Relocate structure
▪ Install isolation fittings
CP2 | Technician
Tests with Bond Connected: Potentials
36
True Polarized Potentials
Target Potential
▪ Not with bond installed
▪ Now tied to another CP
system
▪ Target ON potentials used with
interfering sources interrupting
▪ If bond current also
interrupted, OFF potential is
an “interfered-with” potential
▪ Do not confuse this OFF with a
polarized potential
▪ Structure now affected
with stray current
▪ One Mitigation Method:
▪ Bond returns ON potential
to that before interference
▪ Bond not intended to meet
criterion if not before
▪ Interfering company not
obliged to provide CP
CP2 | Technician
12
Interference Mitigation Bond Test
▪ Interrupt “interfering” and “interferedwith” sources separately or at different
cycles
37
▪ “Target” is ON potential at
▪ maximum exposure
▪ interfering power sources off
▪ Determine point of “maximum
▪ Remove interrupter
exposure” with both cycles on
▪ Largest electropositive shift and/or ▪ Install bond
▪ Least electronegative potential
▪ Adjust resistance until interferedwith potential meets target ON
▪ Determine interfered-with ON and OFF
potential
potentials with interfering source off
▪ True polarized potential is obtained
Tests using CP mitigation are more
with all power sources “off”
difficult as reference may pick up
current discharge from anode
CP2 | Technician
Bonds
38
Bond Location to return stray current safely:
▪ Locate at point of maximum exposure
CASE 1 Bond provides safe return path
-700 mVcse
(+)
▪ Always measure:
▪ Potential on each side
▪ Current through bond
▪ Polarity
▪ Describe current direction
-900 mVcse
(-)
Resistor
▪ Interfering potential must be more
electronegative than interfered-with
potential (Case 1)
▪ Otherwise bond current is reversed
▪ stray current discharge increased on
interfered-with pipe (Case 2)
wrt
Interfering
Pipe
Interfered-with
Pipe
CASE 2 Bond makes condition worse
-700 mVcse
(+)
wrt
-600 mVcse
(-)
Resistor
Interfered-with
Pipe
Interfering
Pipe
CP2 | Technician
Class Exercise
39
Answer the right four (4) columns for each case where stray current interference is
occurring. Write reasons for your decision for each case. Interfered-with and
interfering power sources are assumed before the test but may not be true.
Class Exercise at the end of chapter 5
Case
Interfered with
Pipe-to-Electrolyte
Potential (mVcse)
Interfering
Pipe-toElectrolyte
Potential (mVcse)
DC Power
Source
Interrupting
ON
OFF
ON
OFF
A
-600
-800
-1200
-850
B
-800
-600
-1500
-1500
Interferedwith
-1100
Interfering &
interferedwith
synchronized
-1500
Interference
Cathodic
Will Res
Bond
Mitigate?
Target
Potentia
l for
Bond
Anodic
Interfering
C
-850
-750
D
-1200
-900
-850
-600
Interfering
E
-400
-900
-1200
-1200
Interferedwith
F
-400
-400
-1400
-1000
Interfering
CP2 | Technician
13
Cathodic Protection Interference Mitigation Bond
40
Mitigation
Bond
Cathodic
Protection
Current
Interference (Corrosive)
Current
Interfering
Pipeline
Foreign or Interfered with Pipeline
Interference control current in bond
CP2 | Technician
Installation of Metallic Bond
Load Current
Required to
Operate Train
Overhead Positive
Feeder
41
DC
Substation
+
Tracks Negative
Return
_
Bond
Cable
Parallel soil return path
Bond across High
Resistance Joints
CP2 | Technician
Installation of Metallic Bond
42
Considerations:
▪ Uni-directional control devices (diodes or reverse current switches)
▪ Resistor
▪ Interfering structure must be more electronegative
▪ otherwise bond current reversed - increasing interference
▪ Instead of Bond:
▪ Reduce interfering CP source (supplementary CP may be required
elsewhere)
▪ Coat pickup structure instead of bond
▪ Increase CP on interfered-with structure
▪ Add galvanic anodes at discharge
CP2 | Technician
14
Resistance Bond vs. Solid Bond
43
▪ Resistance bond limits amount of current lost to interfered-with
structure
▪ Resistance must be lower than parallel path through electrolyte
▪ Resistance bond subject to failure from current surges
▪ Solid bonds are lower in resistance but do not control current
CP2 | Technician
Controlling the Direction of Stray Current through
the Bond
44
▪ Diodes or reverse-current switches prevent reverse current
▪ Diode or reverse-current switch part of bond circuit resistance
CP2 | Technician
Interference Mitigation Forced Drainage Bond
45
Rectifier
+
Controller
Pipeline
Stationary
Reference
Electrode
CP2 | Technician
15
Interference Mitigation Galvanic Anodes
46
Protected Structure
Current Discharge
from Anode
Galvanic
Anode
Current Pickup
From ICCP Anode
ICCP
Anode
CP2 | Technician
Interference Mitigation Protective Coatings
47
Recoated Area
Foreign Structure
Reduced Current Pickup
in Recoated Section
Protected Structure
CP2 | Technician
AC Interference – Pipeline & Power Line
48
Electromagnetic Induction Coupling
▪ Structure acts as secondary winding
▪ Applies to above or below-ground structures
Electrostatic (Capacitive) Coupling
▪ Charge on aboveground structures only
Conductive (Resistive) Coupling
▪ AC fault or lightning surges from electrical ground to
structure through electrolyte
CP2 | Technician
16
Electromagnetic Induction
49
▪ AC-induced voltage from parallel power line
▪ Charges in pipeline alternately separated toward opposite ends of
section under influence
▪ Voltage peaks at end and zero in middle
▪ Exposure length between physical discontinuities
▪ Pipe and power line - join, cross, depart, or power line
transformation
▪ Induced voltage directly proportional to
▪ phase currents (IΦ) and
▪ length (L) of mutual exposure
▪ Induced voltage inversely proportional to distance (d) between pipe
and power line conductors
CP2 | Technician
AC Induced Voltage on Pipeline from Changing
Electromagnetic Field
50
Magnetic Field
Produced By
Overhead Lines
Pipeline
Soil
CP2 | Technician
Electromagnetic Induction
Overhead Primary
51
1
VINDUCED= f ( I F, ,L )
d
Air
Core
VINDUCED
V Induced
V0 =
2
Underground Pipeline
Secondary
CP2 | Technician
17
Electromagnetic Induction
52
Poorly Coated Short Pipeline
Or
Well Coated Long Pipeline
+
E
Well Coated Short Pipeline
Distance
CP2 | Technician
Electromagnetic Induction
53
Overhead Conductor - IF
d = distance between overhead
conductor and pipeline
Length, L
Vo
Vo
Soil
(Voltage to Ground)
CP2 | Technician
Electrostatic Coupling
54
Vehicles or above
ground pipe
Pipe
Soil
CP2 | Technician
18
Conductive (Resistive) Coupling
55
Power Line Faults to Ground
▪ Very High Currents
▪ Infrequent
▪ Short Duration
▪ Possible pipe damage (arc burns)
▪ Possible CP damage
CP2 | Technician
Conductive (Resistive) Coupling
56
Fault current
Pipeline
Soil
CP2 | Technician
AC Conditions
57
▪ Hazardous AC voltage = 15 VoltsAC or greater
▪ More frequent with common utility corridors or right-of-way
▪ AC electromagnetic field changes
▪ 100 times/second at 50 Hertz or
▪ 120 times/second at 60 Hertz
▪ Changing electromagnetic field induces voltage on parallel
pipeline
▪ Single turn air core transformer (AC is primary & pipe
secondary)
▪ Phase-to-ground faults expose an underground structure to
high currents
CP2 | Technician
19
AC Structure-to-Earth Voltage Testing
58
AC structure-to-earth voltage
▪ AC voltmeter
▪ Any independent ground can be used as a reference
▪ Connect to reference in ground first
Do not touch any metal directly or through tools, meter
leads/clips
▪ If CSE, tape top terminal
Induced AC voltage changes during day
▪ with power line load and/or power line fault conditions
CP2 | Technician
AC Structure-to-Earth Voltage Testing (cont’d)
59
▪ VoltsAC increases on
aboveground pipe as length
increases during welding
▪ Higher induced AC voltages
at ends or discontinuities
CP2 | Technician
AC Structure-to-Earth Voltage Testing (cont’d)
60
▪ Measurement duplicates “touch voltage”.
▪ Place electrode ~one (1) meter (~3 ft) from closest
contact point(s)
▪ Contact electrode first and pipe next
▪ Unlike structure-to-electrolyte potentials where reference
electrode is placed close to structure
CP2 | Technician
20
AC Interference Mitigation
61
▪ Install structure remote from power lines where practical
▪ Install surge protection across isolating features
▪ Install grids at above-ground pipe appurtenances (valves etc.)
▪ Shallow ribbon spiral or grid
▪ Grid not a substitute for a ground being shallow
CP2 | Technician
AC Interference Mitigation (cont’d)
62
Install electrical grounds (galvanic anodes or metal grounds):
▪ Connect to ground first and pipe next
▪ Use DC decoupler in series with metal grounds
▪ Capacitors, polarization cells, or polarization cell
replacements (PCR)
▪ Allows AC to pass but blocks DC
▪ Not to be confused with Surge Protectors
▪ Pass high fault current only
▪ Devices may interfere with CP surveys
CP2 | Technician
Mitigation of AC Interference Using Distributed
Galvanic Anodes
63
Overhead AC Transmission Line
Underground Pipeline
Distributed Sacrificial Anodes
Without Anodes
Induced
Voltage
With Anodes
Distance
CP2 | Technician
21
Polarization Cell
64
Fill Hole
Cell Terminals
Potassium
Hydroxide
Solution
Stainless
Steel
Plates
CP2 | Technician
Semiconductor Polarization Cell Replacement (PCR)
65
CP2 | Technician
Spiral Gradient Control Mat
Washed
Stone
Zinc Ribbon
Mat Sign
(Typical)
Earth
Surface
300mm
Extend
Gravel
Pipeline
66
Valve
Stranded
Copper Cable
With Insulation
Typical Thermite
Weld Connection
Copper Cable to Zinc Ribbon
Core Wire Connection
CP2 | Technician
22
Spiral Gradient Control Mat – Top View
Aboveground
appurtenance
67
Underground Mat Sign
300mm (1 ft) (Typical)
Stranded Copper
Cable Connection
Zinc Ribbon
2m
Minimum
Grid being shallow is not
intended to act as a ground
CP2 | Technician
AC Corrosion
68
Simple version:
▪ Metal oxidized during anodic half cycle
▪ During cathodic half cycle, oxide film reduced to non-protective
rust layer
▪ Repeated during each cycle
▪ Assumed oxide film never fully forms or corrosion rate more
But is more complex …
SP0169-2013 expects AC corrosion >100 A/m2 with
CP - recommends investigation >30 A/m2
CP2 | Technician
AC Corrosion
69
▪ Depends on AC current density
▪ In turn depends on:
▪ AC Voltage
▪ Spread resistance (Varies with CP reactions)
Reference ISO 18086:2015 and NACE SP21424-2018
CP2 | Technician
23
AC Corrosion – Spread Resistance
70
▪ Spread resistance is:
▪ Resistance of coating defect, coupon or probe to remote earth
▪ Dependent on earth alkaline (Ca+, Mg+) & alkaline (Na+, K+,
Li+) ions in soil
▪ Ca+ products increase & hygroscopic Na+ products reduce SR
▪ With CP more (+) than ~-1.10 VSCE Ca+ products form on Fe to
increase spread resistance
▪ With CP less (+) than ~-1.10 VSCE, with H2 evolution,
▪ products destroyed and
▪ spread resistance decreases
CP2 | Technician
AC Corrosion – Current Density
71
▪ AC corrosion mitigated at low AC & DC current densities
▪ Not mitigated at high AC / DC current densities
▪ Predict current density from coupons
▪ Not accurate to calculate due to unknown defect size and
variable spread resistance
▪ AC can be greater at edges of holiday or coupon
▪ average may be conservative prediction
CP2 | Technician
AC Corrosion Criteria
72
▪ NACE SP0169-2013 expects AC corrosion >100 A/m2 with
CP - recommends investigation >30 A/m2
▪ NACE SP21424-2018: Meet CP criteria and not to exceed
▪ 30 A/m2 if DC exceeds 30 A/m2
▪ 100 A/m2 if DC less than 1 A/m2
▪ ISO 18086:2015: CP criteria &
▪ AC < 30 A/m2 over 24 hr on 1 cm2 coupon/probe
▪ AC > 30 A/m2 over 24 hr on 1 cm2 coupon/probe –
maintain CP < 1 A/m2
▪ Ratio over 24 hrs; Jac/Jdc < 5 preferably < 3.
(J – current density)
CP2 | Technician
24
Notable Differences in Criteria
NACE
1
2
3
73
ISO
Jac < 30 A/m2 if Jdc > 1
A/m2
Suggests upper Jac limit of
100 A/m2 if Jdc < 1 A/m2
Jac < 30 A/m2 (regardless
of DC)
No upper limit if Jac > 30
A/m2
Jac/Jdc not addressed
Jac/Jdc < 5 preferably <3
recommended
Precise coupon area not
critical with ratio
CP2 | Technician
AC Corrosion – Jac & Jdc
74
▪ Low Jdc
▪ Limited increase in pH
▪ Less reductive effect on metal oxides
▪ High Jdc
▪ Results in a high or low spread resistance
▪ With a low or high Jac
▪ Low Jac/Jdc ratio metal oxidation in anodic half cycle
prevented
CP2 | Technician
AC Corrosion – Summary
75
▪ AC Corrosion still researched and debated
▪ Low Jac, CP can be effective
▪ -850 mVCSE may not be sufficient
▪ Caution against high potential
▪ Less electronegative than -1.15 VCSE
▪ Use coupons/probes to predict Jac.
▪ Lowering VAC by grounding will reduce Jac and AC corrosion
CP2 | Technician
25
Knowledge Check | 1
76
A mitigation control bond should be designed to
A. Carry the necessary current.
B. Restrict the current to that required to mitigate the
problem.
C. Keep the current going in one direction if
necessary.
D. Return the potential on the interfered with
structure to its pre-interference state.
CP2 | Technician
Knowledge Check | 2
77
A mitigation bond may cause more problems under
which of the following conditions?
A. Where the interfering structure bond point is more
electropositive than the interfered with structure.
B. Where the interfering structure bond point is more
electronegative than the interfered with structure.
C. Where there are more than one, or changing,
current discharge points.
D. Where the interfering structure bond point potential
varies from being more electronegative to more
electropositive than the interfered with structure.
CP2 | Technician
Knowledge Check | 3
78
AC Voltages on pipelines do NOT result from
A. resistive (conductive) coupling
B. electrostatic (capacitive) coupling
C. electromagnetic induction coupling
D. thermodynamic coupling
CP2 | Technician
26
Knowledge Check | 4
79
On a cathodically protected pipeline, AC corrosion can
be expected at which current densities?
A. 30 mA/m2
B. 10 A/m2
C. 110 A/m2
D. 200 A/m2
CP2 | Technician
Knowledge Check | 5
80
The AC voltage-to-ground on a section of pipeline near
a power line tends to be
A. Highest where the power line and pipeline cross
B. Highest where the power line and pipeline separate
after a parallel section
C. Highest at the ends of the overall pipeline with the
parallel section in the middle
D. The same along the pipeline/power line parallel
section
CP2 | Technician
Knowledge Check | 6
81
Methods of making hazardous AC voltages safe
includes installing which of the following?
A. grounds at the discontinuities between power line
and pipeline
B. a bond to the steel power line tower
C. a gradient mat or a grid around aboveground
structures
D. a remote ground away from the parallel section
CP2 | Technician
27
Knowledge Check | 7
82
A polarization cell is used to
A. polarize the pipeline
B. polarize the electrical ground
C. provide DC coupling but block AC
D. provide AC coupling but block DC
CP2 | Technician
Knowledge Check | 8
83
Tests for interference can be indicated by which of the
following?
A. Structure-to-electrolyte potential changes
B. Changes in line current magnitude or direction
C. Localized pitting in areas near or immediately
adjacent to a foreign structure
D. Breakdown of protective coatings in a localized
area
CP2 | Technician
Knowledge Check | 9
84
When AC voltage of 13 VAC is measured on a pipeline,
what course of action should be taken?
A.
Wait until next year or take an AC voltage to confirm it has not
changed.
B. Contact the power company to determine what percent of load the
power line is operating.
C. Advise other personnel that a near hazardous situation exists on
the pipeline.
D. Advise the owner or supervisor that an AC mitigation program
should investigated.
CP2 | Technician
28
Knowledge Check | 10
85
The purpose of a gradient mat is to
A. Electrically ground the pipe to the earth to
eliminate the AC voltage.
B. Bring the voltage difference between the pipe and
earth close to 0 VAC.
C. Provide cathodic protection to large structures such
as tank bottoms.
D. To eliminate the earth gradient to obtain a true
polarized potential.
CP2 | Technician
Knowledge Check | 11
86
Which of the following is NOT a source of dynamic stray
current?
A. Cathodic protection
B. Mining equipment
C. Transit systems
D. Telluric current
CP2 | Technician
Knowledge Check | 12
87
Stray current CANNOT be detected by
A. structure-to-electrolyte potentials.
B. reference electrode to electrode measurements.
C. pipeline current span measurements.
D. soil resistivity measurements.
CP2 | Technician
29
Knowledge Check | 13
88
Cathodic interference occurs
A. in a voltage gradient that is a positive to remote
earth.
B. in a voltage gradient that is negative to remote
earth.
C. at the cathode in a corrosion cell.
D. at the structure’s cathodic protection system.
CP2 | Technician
Knowledge Check | 14
89
An electronegative peak in potentials along a pipeline
between CP power sources may be indicative of
A. Current pick up interference
B. Current discharge interference
C. Shorted casing
D. Shorted isolation
CP2 | Technician
Knowledge Check | 15
90
Analysis of dynamic stray current does NOT typically
include the evaluation of
A. soil resistivity.
B. the interaction of voltages between different
structures.
C. measuring of current on the structure.
D. the amount of CP current pick up on a coating
holiday of a given size at the location.
CP2 | Technician
30
Knowledge Check | 16
91
Recommended methods of mitigating cathodic
interference from another cathodic protection system
include which of the following?
A. Drainage control bond
B. Cathodic protection
C. Coating the current discharge area
D. Reduce source of stray current
CP2 | Technician
Knowledge Check | 17
92
Which location(s) indicates a stray current discharge
on an interfered-with pipeline?
Location
Pipe-to-Electrolyte Potential (mVcse)
Power Source Interrupting
ON
OFF
A
-1500
-900
Interfering
B
-1100
-900
Interfered-with
C
-1500
-900
D
-700
-900
Interfering & Interfered-with
synchronized
Interfering
A. A
B. B
C. C
D. D
CP2 | Technician
Knowledge Check | 18
93
Which location(s) indicates a stray current pickup on
an interfered-with pipeline?
Location
Pipe-to-Electrolyte Potential (mVcse)
Power Source Interrupting
ON
OFF
A
-1500
-1000
Interfering
B
-1100
-900
Interfered-with
C
-1500
-900
D
-800
-1000
Interfering & Interfered-with
synchronized
Interfering
A. A
B. B
C. C
D. D
CP2 | Technician
31
Knowledge Check | 19
94
Where would be the best location to install a
resistance bond to mitigate interference?
Location
Interfered-with Pipe-toelectrolyte Potential
(mVcse)
Interfering Pipe-toelectrolyte Potential
(mVcse)
Power Source Interrupting
ON
OFF
ON
OFF
A
-700
-820
-1050
-850
Interfering
B
-800
-700
-1100
-900
Interfered-with
C
-850
-750
-1500
-1100
D
-700
-850
-650
-600
Interfering & Interfered-with
synchronized
Interfering
A. A
B. B
C. C
D. D
CP2 | Technician
Experiment 4.1
95
Experiment 4.1
Demonstration of Stray Current
Interference – Instructor Demo
CP2 | Technician
Experiment 4.1
96
To Demonstrate DC Interference and Its Mitigation
C
1 cm
1 cm
steel
rod
B
mag
anode
D
E
9V
10 ohm
F
A
A
CP2 | Technician
32
Experiment 4.1
97
resistance bond
A
3
Steel rod
Mag
anode
2
6
5
4
1
A
9V
10 ohm
CP2 | Technician
Experiment 4.1 – Table for Readings
Step
CP Structure-to-Electrolyte Potentials
(mVCSE) or pH
A
B
C
Foreign Structure-to-Electrolyte
Potentials (mVCSE)
D
E
98
ICCP Current
(mA)
F
Step 3
Step 3 pH
Step 5, 6 & 7
Step 7 pH
Step 10
Step 10 pH
Step 12
Step 14
Step 15 pH
CP2 | Technician
Experiment 4.1 – Conclusions
99
▪ Stray current pickup on the foreign structure occurs at ______ (name all)
▪ Stray current discharge on the foreign structure occurs at ______ (name all)
▪ An increase in current on the CP structure occurs at ________ (name all)
▪ A decrease in current on the CP structure occurs at ________ (name all)
▪ Effect on potential of bonding the foreign structure to the CP structure ___________
▪ Effect on current of bonding the foreign structure to the CP structure _____________
▪ The effect of pH was ___________________________________ (at each location)
CP2 | Technician
33
Chapter 4
Stray Current Interference
®
34
Chapter 4 | Exercise
Handout Sheet
Answer the right four (4) columns for each case where stray current interference is occurring.
Write reasons for your decision for each case.
Case
Interfered-with
Pipe-toElectrolyte
Potential
(mVcse)
ON
OFF
Interfering
Pipe-toElectrolyte
Potential
(mVcse)
ON
OFF
DC Power
Source
Interrupting
-600
-800
-1200
B
-800
-600
-1500
-850
-750
-1500
-1200
-900
-850
-600
d
Interfering
-400
-900
-1200 -1200
Interferedwith
-400
-400
-1400
C
D
E
F
NACE International
Will Res
Bond
Mitigate?
Target
Potential
for Bond
Cathodic Anodic
A
-850
Interference
Interfering
-1500 Interferedwith
Interfering &
Interfered-1100
with
synchronize
-1000 Interfering
CP2|Page 1
CP 2│CATHODIC PROTECTION
TECHNICIAN
Practical Exercises Data Sheets
SET #1
Version: March2020
NACE International | CP2
Page | 1
NACE International | CP2
Page | 2
Station 1
RECTIFIER TROUBLESHOOTING
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 3
Practical Exercise Station 1 - Rectifier Troubleshooting
There are a number of rectifiers set up at this station. Troubleshoot each rectifier to determine its fault.
RECTIFIER STATION 1
AC INPUT VOLTAGE ______________________________________
AC STEP-DOWN VOLTAGE _________________________________
TAP SETTINGS _________________________________
DC VOLTAGE ON PANEL METER ____________________________
DC AMPS ON PANEL METER ________________________________
DC VOLTAGE ON RECTIFIER OUTPUT TERMINAL USING MULTIMETER ___________________________
DC mV ACROSS SHUNT ______________________________________
DC AMPS FROM SHUNT READING ______________________________
CYCLES
Secondary Taps
___________Hz
DC Output
___________Hz
WHAT PROBLEM DOES THIS RECTIFIER HAVE, IF ANY?
___________________________________________________________________________________
HOW COULD THIS PROBLEM BE CORRECTED?
___________________________________________________________________________________________
HOW WOULD YOU DETERMINE CORRECT PARTS (SIZE, RATING, TYPE, ETC.) NEEDED FOR THE REPAIR?
____________________________________________________________________________________________
NACE International | CP2
Page | 4
RECTIFIER STATION 2
AC INPUT VOLTAGE ______________________________________
AC STEP-DOWN VOLTAGE _________________________________
TAP SETTINGS _________________________________
DC VOLTAGE ON PANEL METER ____________________________
DC AMPS ON PANEL METER ________________________________
DC VOLTAGE ON RECTIFIER OUTPUT TERMINAL USING MULTIMETER ___________________________
DC mV ACROSS SHUNT _______________________________________
DC AMPS FROM SHUNT READING ______________________________
CYCLES
Secondary Taps
___________Hz
DC Output
___________Hz
WHAT PROBLEM DOES THIS RECTIFIER HAVE, IF ANY?
___________________________________________________________________________________
HOW COULD THIS PROBLEM BE CORRECTED?
___________________________________________________________________________________________
HOW WOULD YOU DETERMINE CORRECT PARTS (SIZE, RATING, TYPE, ETC.) NEEDED FOR THE REPAIR?
____________________________________________________________________________________________
NACE International | CP2
Page | 5
RECTIFIER STATION 3
AC INPUT VOLTAGE ______________________________________
AC STEP-DOWN VOLTAGE _________________________________
TAP SETTINGS _________________________________
DC VOLTAGE FROM PANEL METER ____________________________
DC CURRENT FROM PANEL METER ________________________________
DC VOLTAGE ON RECTIFIER OUTPUT TERMINAL USING MULTIMETER ______________
DC mV ACROSS SHUNT_______________________
DC CURRENT FROM SHUNT ______________________________
CYCLES
Secondary Taps ___________Hz
DC Output
___________Hz
WHAT PROBLEM DOES THIS RECTIFIER HAVE, IF ANY?
___________________________________________________________________________________
HOW COULD THIS PROBLEM BE CORRECTED?
___________________________________________________________________________________________
HOW WOULD YOU DETERMINE CORRECT PARTS (SIZE, RATING, TYPE, ETC.) NEEDED FOR THE REPAIR?
____________________________________________________________________________________________
NACE International | CP2
Page | 6
RECTIFIER STATION 4
Confirm that there is no power to the rectifier.
DIODE TEST FROM RECTIFIER PANEL
Remove taps and one load connection
Diode: Coarse Tap to Positive
Forward _____ Reverse _____Status? _______
Diode: Fine Tap to Positive
Forward _____ Reverse _____Status? _______
Diode: Negative to Coarse Tap
Forward _____ Reverse _____Status? _______
Diode: Negative to Fine Tap
Forward _____ Reverse _____Status? _______
WHICH DIODE NEEDS REPAIR AND HOW WOULD YOU DETERMINE CORRECT PARTS (SIZE, RATING, TYPE, ETC.)
NEEDED FOR THE REPAIR?
_____________________________________________________________________________________________
NACE International | CP2
Page | 7
NACE International | CP2
Page | 8
Station 2
IMPRESSED CURRENT INTERRUPTION
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 9
Practical Exercise Station 2 - Impressed Current Interruption
Current interrupters are used to “interrupt” an electrical circuit in order to obtain “on “ and “interrupted”
structure-to-electrolyte potential measurements.
During this exercise you will practice installing the interrupter and obtaining measurements using the
interrupter.
Part A.
Installing the current interrupter
Turn off the rectifier using the rectifier circuit breaker. (Note in some jurisdictions this breaker will need to
be locked out.)
1. Connect the rectifier negative terminal to the structure.
2. To install the interrupter in the anode cable as follows.
3. Connect one lead wire of the current interrupter to the anode cable and the other connection to
the positive rectifier terminal. Watch for polarity on certain interrupters and if polarity is indicated,
connect rectifier positive to interrupter positive.
4. Set the interrupter for the proper time you wish the interrupter to turn “on” and “off”.
Part B.
Test Procedure
1. Connect meter to measure a structure-to-electrolyte potential to the reference electrodes.
2. Take native structure-to-electrolyte potentials to reference electrodes at locations marked A, B,
and C.
3. Turn on the interrupter.
4. Turn on the rectifier using the rectifier circuit breaker.
5. Confirm that the current output is being interrupted.
6. Determine the length of the ON cycle and the OFF cycle.
7. Take structure-to-electrolyte potential measurements at locations marked A, B, and C noting the
length of time each reading is displayed and comparing it to the length of each cycle on the
interrupter.
8. Determine the ON and OFF potentials by the length of time of the cycle. DO NOT ASSUME THE
MOST ELECTRONEGATIVE POTENTIAL IS ALWAYS THE “ON” POTENTIAL. IF THE “ON” POTENTIAL
IS LESS ELECTRONEGATIVE THAN THE “OFF”, THE RECTIFIER IS CONNECTED WITH REVERSE
POLARITY.
9. If necessary, change the leads to achieve a more electronegative potential when the rectifier
comes on.
NACE International | CP2
Page | 10
Record data in the table below.
Note: Potentials measured must be converted to the equivalent values of other reference electrodes as noted.
Reference
Electrode Location
Native structure-toelectrolyte
potential
VZN
Structure-toelectrolyte
potential measured
"ON"
VCSE
VZN
VCSE
Structure-toelectrolyte potential
measured
"INTERRUPTED"
(INSTANT OFF)
VZN
Voltage (IR)
Drop
VCSE
A
B
C
Do the potential measurements meet a cathodic protection criterion?
Yes


No
If so, which criterion was met? _____________________________
Which location is the conclusion based on?
A ____
B ____
C ____
Why?_________________________________________________________________
Which reference electrode location is closest to the anode?
A
B
C



Which reference electrode location is closest to the structure?
A
B
C
NACE International | CP2



Page | 11
NACE International | CP2
Page | 12
Station 3
CURRENT REQUIREMENT TEST
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 13
Practical Exercise Station 3 - Current Requirement Test
A temporary anode, a current interrupter and a power supply are used to apply current to the structure.
The objective of the test is to determine by measurement and calculations the current required to achieve
a -0.85 VoltCSE polarized potential on the structure.
Part A.
Measure and record native structure-to-electrolyte potentials at the locations identified or supplied by
instructor.
Part B.
Install the current interrupter in the DC power supply.
To install in the D.C. Circuit of a rectifier, turn off breaker or disconnect the D.C. fuse and connect the
interrupter in the anode cable as in Part A of Station 2.
1. Connect the power supply negative to the structure.
2. Connect one side of the current interrupter to the anode cable and the other connection to the positive
terminal of the DC power supply.
3. Set the interrupter for the proper time you wish the interrupter to turn “on” and “off” if not preset by
instructor.
4. Turn on the interrupter.
5. Turn on the power source and confirm that it is being interrupted.
6. Determine the length of the ON and OFF cycle.
Measure and record ON and OFF structure-to-electrolyte potentials at the location identified by noting the
length of time for each cycle. Potentials must be converted to Volts and current to amperes in the following
equations.
Measure and record the power source current output.
STRUCTURE-TO-ELECTROLYTE POTENTIAL (mVcse)
Native
NACE International | CP2
On
Off
POWER SOURCE
CURRENT (mA)
Page | 14
CALCULATE Ireq
Ireq = _ Polarization Required x Itest
Polarization Achieved During Test
I req =
Ireq
=
(−0.850V − E Nativ e ) * I test
( EOff − E Native )
____
OR
I req =
Ireq
=
− 0.100V * I test
(E Off − E Native )
____
In this case, which criterion would be achieved first (at the least current)? ___________________________
NACE International | CP2
Page | 15
NACE International | CP2
Page | 16
Station 4
CATHODIC PROTECTION
COMMISSIONING
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 17
Practical Exercise Station 4 - Cathodic Protection Commissioning
Commissioning (energizing and adjusting) a new Cathodic Protection system is an important task and must
be done properly. Adequate levels of cathodic protection must be maintained without causing overvoltage
situations, stray current interference or premature failure of the anode system. Your task is to energize a new
Cathodic Protection system however stray current interference will be demonstrated in a different station.
Unfortunately, the construction crew that installed the Cathodic Protection system forgot to label which wire
is the anode wire and which wire is the pipe wire but the test lead that would normally be at a nearby point is
known to be on the pipeline.
Identify which wire(s) is/are connected to the pipe and to the anode (explain why), connect the rectifier up
properly, install an interrupter, take ON and OFF structure-to-electrolyte (S/E) potentials and adjust the
output of the rectifier until the pipeline meets the –850 VCSE polarized potential criterion for steel. Start
with rectifier on minimum output setting.
STRUCTURE-TO-ELECTROLYTE POTENTIAL
WIRE NO.
Anode wires: _______________
_______
Pipe wires:
_______
_______________
How did you come to the above conclusion? _________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
NACE International | CP2
Page | 18
Attempt No.
Tap Setting
Rect. Voltage
Output
Rect. Amperage
Output
S/E On
S/E Off
1
2
3
4
5
At what tap setting and current output does the pipe meet a CP criterion and which criterion is met?
Tap Setting:___________________________________________________________________
DC Current output:_____________________________________________________________
Which criterion was met and why do you say the pipe meets this criterion?
_____________________________________________________________________________
_____________________________________________________________________________
NACE International | CP2
Page | 19
NACE International | CP2
Page | 20
Station 5
CURRENT SPAN
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 21
Practical Exercise Station 5 - Current Span
Students are to become competent in conducting tests to calibrate pipeline current spans. Calibrating the
current span is similar to establishing the shunt value or shunt factor in a current shunt. Once calibrated,
the calibration factor can be used to determine the residual current flowing from CP current sources
and/or stray current influences in the pipe span.
PROCEDURE
Part A.
Test Span Calibration
1. Calibrate the current spans #1 and #2 by impressing the provided current from the CS-10
power source through the outside wires (top terminals) of the respective test station and
measuring the voltage drop across the inside wires (bottom terminals) at each tests station.
TEST CONNECTIONS
+
CS-10
mV
-
+
Test Station
Panel
PIPE
Note: There are two identical test heads. Test Station #1 represents Current Span #1. Test Station #2
represents Current Span #2. Span #1 and Span #2 are spaced along a segment of pipe and may be a
mile or more apart from each other.
The test circuit is essentially a series electrical circuit as shown in the following schematic drawing.
NACE International | CP2
Page | 22
Controlled Power Supply
Current Interrupter
-
+
A
ITEST
CS-10
mV
-
+
IRESIDUAL
VTEST
ITOTAL (IT)
Resistor (RSPAN)
2. Test Station #1 Measurements
(Note polarity and thus direction)
ITEST1 ON (CS-10 ON)
__________mA
ITEST1 OFF (CS-10 OFF)
__________mA
ITEST1 = ITEST1 ON - ITEST1 OFF
__________mA
VTEST1 ON (CS-10 ON)
__________mV
VTEST1 OFF (CS-10 OFF)
__________mV
3. Test Station #2 Measurements
(Note polarity and thus direction)
ITEST1 ON (CS-10 ON)
__________mA
ITEST1 OFF (CS-10 OFF)
__________mA
ITEST1 = ITEST1 ON - ITEST1 OFF
__________mA
VTEST1 ON (CS-10 ON)
__________mV
VTEST1 OFF (CS-10 OFF)
__________mV
4. Pipe Span Resistance and Calibration Factor
NACE International | CP2
Page | 23
Calculate the current span resistance [Ω] and the calibration factor (A/mV) for each current span.
Note: potentials must be in Volts to calculate resistance and mV to calculate CF.
RSPAN =
(VTESTON − VTESTOFF )
( I TEST )
CFspan =
( I TEST )
(mVTESTON − mVTESTOFF )
Test Station #1
R1span = _______ Ω CFspan = _______ A/mV
Test Station #2
R2span = _______ Ω CFspan = _______ A/mV
5. Residual Current
Was there a residual current on the pipe section; that is, was there a VTEST reading with no Test
Current from CS-10?
Yes? ______ No?________
If so, calculate the current.
I RESIDUAL =
(VTESTOFF )
( RSPAN )
I RESIDUAL = mVOFF CFSPAN
Test Station #1 Residual Current = ________A ________mA
Test Station #2 Residual Current = ________ A ________mA
NACE International | CP2
Page | 24
Station 6
COATING CONDUCTANCE
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 25
Practical Exercise Station 6 - Coating Conductance
Students are to become competent in completing tests to measure and calculate the pipe coating
resistance and conductance.
The instructor will connect the station such that the pipe is receiving an interrupted supply of current from
an anode.
The instructor will give the following information:
RSPAN1 = _____________ Ω
or
CFSPAN1 = _____________ A/mV
RSPAN2 = _____________ Ω
or
CFSPAN2 = _____________ A/mV
Pipe Diameter _____________ m
Pipe Length _____________ m
Student:
□
□
1.
Confirm that the power supply is on and interrupting.
Confirm that the switch behind Test Station #1 is in the “on” position as it controls the
structure-to-electrolyte potentials
Test Connections
Test Station #1
+
+
mV
V or
mV
V or
mV
mV
-
Test Station #2
-
-
Reference Electrode
+
-
+
Reference Electrode
Panel Top
PIPE
PIPE
The test is intended to determine the pipe to earth resistance through the coating (Rc) between
the test stations as represented by the darker colored pipe.
NACE International | CP2
Page | 26
This can be represented by an electrical circuit as shown below.
-
mVp1
+
-
Rp1
mVp2
+
Rp2
Ip1
Ip2
Rc
r
r
r
r
ΔEave
Ic
The objective is to calculate Rc by: RC =
∆E AVE
IC
2. Test Station #1 Measurements
mVp1 ON
__________mV
(Pipe Span with current ON)
mVp1 OFF
__________mV
(Pipe Span with Current OFF)
E1ON
__________mV
(ON Structure-to-electrolyte Potential)
E1OFF
__________mV
(OFF Structure-to-electrolyte Potential)
3. Test Station #2 Measurements
mVp2 ON
__________mV
(Pipe Span with current ON)
mVp2 OFF
__________mV
(Pipe Span with Current OFF)
E2ON
__________mV
(ON Structure-to-electrolyte Potential)
E2OFF
__________mV
(OFF Structure-to-electrolyte Potential)
NACE International | CP2
Page | 27
4. Calculate Current in Each Pipe Span
Equation Summary
IC
ΔIP1
=
- ΔIP2
IP1ON
ΔIP1
= IP1ON
-
IP1OFF
IP2ON
ΔIP2
= IP2ON
-
IP2OFF
IP1OFF
IP2OFF
V (in Volts) = mV / 1000
=
VP1ON
/ RP1
=
VP2ON
/ RP2
IP1ON
=
VP1OFF
/ RP1
IP1OFF
=
VP2OFF
/ RP2
IP2OFF
OR
IP2ON
=
mVP1ON
x CF1
=
mVP2ON
x CF2
=
mVP1OFF x CF1
=
mVP2OFF X CF2
mV = V x 1000
Test Station #1
IP1 ON
__________A
IP1 OFF
__________A
ΔIP1
__________A
Test Station #2
IP2 ON
__________A
IP2 OFF
__________A
ΔIP2
__________A
5. Current Pick Up in Coating Section (IC)
IC = ΔIP1 - ΔIP2
IC = __________A
6. Average Potential Across Coating Due to Current Applied
∆E1 = E1ON – E1OFF.
∆E2 = E2ON – E2OFF.
∆E1 = _______ mV
∆E2 = _______ mV
Calculate the average ∆E
[∆Eave =(∆E1 + ∆E2 )/ 2].
Average ∆Eave ________ mV
NACE International | CP2
Page | 28
7. Pipe Coating Resistance
Calculate the total resistance of the pipe section to earth between test stations.
RC =
∆E AVE
IC
Total pipe coating resistance (Rc) = ____________ Ω
8. Pipe Surface Area
Calculate surface area of pipe based on diameter and length of pipe given by:
A = πdL
Where:
A - Surface area of pipe
D – Outside Pipe Diameter
L – Length of coated pipe section
π – 3.1416
Pipe Diameter = ____________ m (given)
Pipe Length =
____________ m (given)
Surface area = ____________ m2
9. Specific Coating Resistance
Calculate the specific unit coating resistance (rc )in Ω-m2 .
rC = Rc * A
Specific unit coating resistance (rc) = ____________ Ω-m2
10. Specific Coating Conductance
Calculate the specific unit coating conductance (gc ) in S/m2 .
gC =
1
rC
Specific unit coating conductance (gc) = ____________ S/m2
NACE International | CP2
Page | 29
NACE International | CP2
Page | 30
Station 7
MITIGATION OF DC INTERFERENCE
USING A RESISTANCE BOND
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 31
Practical Exercise Station 7 - Mitigation of DC Interference Using a Resistance Bond
This exercise will demonstrate DC stray current interference and how it can be mitigated using a resistance
bond. The test station is shown in the photograph above with instructions for each part of the exercise as
follows:
Part A
1. Measure the AS FOUND potential of Line 1 and Line 2 at each of the locations.
Location
A
Connected to (VCSE)
Line 1
B
Line 1
C
Line 1
B
Line 2
D
Line 2
E
Line 2
A/F Potential (VCSE)
Part B
1. Connect the impressed current system to Line 2.
2. Measure the potential of Line 1 and Line 2 while interrupting the impressed current CP System.
Location
Connected to
A
Line 1
B
Line 1
C
Line 1
B
Line 2
D
Line 2
E
Line 2
NACE International | CP2
ON Potential (VCSE)
OFF Potential (VCSE)
Page | 32
Part C
1. What is the location of maximum exposure to interference on the line not connected to the interrupting
source? ________________________________
2. Starting at the highest resistance value available, install different resistors between Line 1 and Line 2 at the
point of maximum exposure.
3. Record the potentials at the location of maximum exposure and the value of the resistance in the table
below.
4. Repeat using lower resistance values until there is no longer a stray current interference situation (“on”
potential of the interfered-with structure has been returned to its original value).
5. Once the ideal resistance is obtained (potential returned to original value before interference current) at
the crossing, measure the voltage drop across this fixed resistance and record in the table below
6. Calculate the interference control current drain.
7. Turn off and disconnect the apparatus.
Control
Resistance Ohms
Potential Line 1
at maximum
exposure
ON
OFF
Potential Line 2 at
maximum
exposure
ON
OFF
Voltage Across
Bond Resistor
Interference
Control
Current
R=
R=
R=
R=
Current in resistance bond with DC interference mitigated: ______ mA
NACE International | CP2
Page | 33
NACE International | CP2
Page | 34
Station 8
MEASUREMENTS IN
ELECTRICAL CIRCUITS
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 35
Practical Exercise Station 8 – Measurements in Electrical Circuits
This exercise gives students practice connecting resistors in both series and parallel circuits. Using the
resistor board provided, follow the instructions noted in Part A and Part B of this exercise.
CAUTION: Remember to:
— measure resistance with the power off
— return the meter from Resistance to the DC Volts setting and
— turn the power back on after the connections are complete.
Part A: Parallel Circuit
1. Measure and record the resistance of Resistors A, B, C and D.
2. Measure source voltage (before connecting resistors): ___________________
3. Connect resistors A, B, C and D in parallel and complete the following table using Ohm’s Law where
necessary. Include polarity, numerical value and units when recording the measurement.
4. Explain difference (if any) with source voltage after connecting resistors:
____________________________________________________________________________________
____________________________________________________________________________________
RESISTOR
RESISTANCE
BATTERY EMF
(VOLTS)
VOLTAGE DROP
(VOLTS)
CURRENT
(AMPERES)
A
B
C
D
TOTAL
NACE International | CP2
Page | 36
5. Calculate the total resistance of the circuit. (Show your work.)
RESISTANCE (OHMS)
6.
Which of Kirchoff’s Laws applies to this circuit?
Kirchoff’s Law
Voltage

Current

NACE International | CP2
Page | 37
Practical Exercise Station 8 - Measurements in Electrical Circuits
Part B: Series Circuit
1. Measure and record the resistance of Resistors A, B, C and D.
2. Connect resistors A, B, C and D in series
3. Measure voltage across resistors
4. Complete the following table using Ohm’s Law where necessary. Include polarity, numerical value
and units when recording the measurement.
5. Measure source voltage.
RESISTOR
RESISTANCE
BATTERY EMF
(VOLTS)
VOLTAGE DROP
(VOLTS)
CURRENT
(AMPERES)
A
B
C
D
TOTAL
5. Calculate the total resistance of the circuit. (Show your work.)
RESISTANCE (OHMS)
7.
Which of Kirchoff’s Laws applies to this circuit?
Kirchoff’s Law
Voltage

Current

NACE International | CP2
Page | 38
Station 9
UNDERGROUND STORAGE TANK
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 39
Practical Exercise Station 9 - Underground Storage Tank
This test station simulates conditions for an underground fuel storage tank installation. You will obtain the
measurements indicated in the table that follows and record data obtained.
PART A
Continuity Test (Fixed Cell Reference Electrode Position)
Structure
Being Tested
Tank
Fill Pipe
Product
Pipe
Vent Pipe
Station
Ground
Survey
Comments
Fill Pipe
Product
Pipe
Vent Pipe
Station
Ground
Survey
Comments
Potentials
PART B
Potential Survey
Structure
Being Tested
Reference
Electrode
Location
Product end
of tank
Tank
ON
OFF
ON
OFF
ON
OFF
ON
OFF
ON
OFF
Center
Vent end of
tank
At product
riser
At vent riser
At station
ground
CONCLUSIONS ON TEST RESULTS
1. What structures are electrically continuous? ___________________________________________________
2. What structures meet a CP (NACE) criterion? __________________________________________________
NACE International | CP2
Page | 40
Station 10
CALCULATION STATION
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 41
Practical Exercise Station 10 – Calculation Station
1.
Make the following conversions
-0.050 VSCE to VSSC
+0.750 VZn to VSCE
+0.075 VSSC to VCSE
2.
What is the efficiency of a rectifier operating as follows:
DC output of 20 Volts 10 Amperes
KWH meter revolutions of 4 per minute with a factor of Kh = 2.
NACE International | CP2
Page | 42
Station 11
ROAD CASING AND CARRIER
PIPE MEASUREMENTS
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 43
Practical Exercise Station 11 – Road Casing and Carrier Pipe Measurements
OBJECTIVE
The object of this station is to demonstrate the difference in an electronic and a electrolytic shorted road
casing and to demonstrate the fact that the pipeline inside a shorted casing is not receiving CP even
though the potential outside the casing meets criterion.
PROCEDURE
1. Student to measure the on/off potential of pipe and casing with the reference outside of each
casing and decide if it is shorted.
2. Student to measure the on/off pipe and casing potentials to a reference inside each casing and
decide if the pipe meets the criterion.
Test Wire
#1
CASING A
Reference Electrode Outside
Casing
On
Off
Reference Electrode Inside
Casing
On
Off
CASING B
Reference Electrode Outside
Casing
On
Off
Reference Electrode
Inside Casing
On
Off
#2
Test Wire
#3
#4
1. What is the casing status?
a. Casing A
i. Electronic short
ii. Electrolytic couple
b. Casing B
i. Electronic short
ii. Electrolytic couple
NACE International | CP2
Yes
No
Yes
No
Yes
No
Yes
No
Page | 44
2. Does the carrier pipe inside the casing meet the polarized potential criterion?
a. Casing A
i. Meets criterion
Yes
N No
b. Casing B
i. Meets criterion
NACE International | CP2
Yes
No
Page | 45
NACE International | CP2
Page | 46
Station 12
SOIL RESISTIVITY MEASUREMENTS
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 47
Practical Exercise Station 12 - Soil Resistivity Measurements
During this exercise, you will measure resistance and calculate resistivity using the 4-pin Wenner method and
then calculate layer resistivity using the Barnes Layer formula.
Part A
1. Using the equipment provided, connect the 4 wires from the meter to the station electrodes at the
spacing in the table below.
2. Enter the results and calculate the resistivity based on a pin depth of 0.1 cm.
Pin Spacing (cm)
Resistance (Ohms)
Resistivity (Ohm-cm)
2.5
_____________
_____________
5.0
_____________
_____________
7.5
___________
___________
Part B
Using the Barnes Layer formula and the following data, calculate the resistivity of each layer.
Pin Spacing (m)
Resistance (Ohms)
1.00
25.0
2.00
7.2
3.00
4.6
Resistivity (Ohm-cm)
Using the Barnes Layer formula and the data above, calculate the resistivity of each layer in the table
below.
Layer (cm)
Layer Resistance (Ohms)
Layer Resistivity (Ohm-cm)
0 to 100
100 to 200
200 to 300
NACE International | CP2
Page | 48
Note:
Care should be taken in the resolution of the answers. The significant number of digits in the data
determines the significant number of digits in the answer.
Basic rules:
All non-zero digits are significant: 1, 2, 3, 4, 5, 6, 7, 8, 9.
•
Zeros between non-zero digits are significant: 102, 3004, 50006.
•
Leading zeros are never significant: 0.01, 002.345, 0.000678.
•
In a number with or without a decimal point, trailing zeros (those to the right of the last non-zero
digit) are significant provided they are justified by the precision of the data: 345,000; 6.0600;
7.8000; 13.5700.
NACE International | CP2
Page | 49
NACE International | CP2
Page | 50
Station 13
POLARITY BOARD
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 51
Practical Exercise Station 13 – Polarity Board
1.
Measure and record the potential differences between each pair of banana jacks listed below. Record
magnitude, polarity and units for each measurement using the second color in each case as the
reference.
2.
After obtaining and recording the potential differences, use the data to order the colored banana jacks
by most negative polarity to most positive polarity.
PAIR
POTENTIAL
White to Blue
Red to Yellow
Green to Red
Blue to Yellow
Order the banana jacks by color from most negative to least negative.
Colored Banana Jack
MOST
NEGATIVE
LEAST
NEGATIVE
NACE International | CP2
Page | 52
CP 2│CATHODIC PROTECTION
TECHNICIAN
Practical Exercises Data Sheets
SET #2
Version: March2020
NACE International | CP2
Page | 1
NACE International | CP2
Page | 2
Station 1
RECTIFIER TROUBLESHOOTING
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 3
Practical Exercise Station 1 - Rectifier Troubleshooting
There are a number of rectifiers set up at this station. Troubleshoot each rectifier to determine its fault.
RECTIFIER STATION 1
AC INPUT VOLTAGE ______________________________________
AC STEP-DOWN VOLTAGE _________________________________
IDENTIFY COMPONENTS LABELED A ________________________
IDENTIFY COMPONENTS LABELED B ________________________
TAP SETTINGS _________________________________
DC VOLTAGE ON PANEL METER ____________________________
DC AMPS ON PANEL METER ________________________________
DC VOLTAGE ON RECTIFIER OUTPUT TERMINAL USING MULTIMETER ___________________________
DC mV ACROSS SHUNT ______________________________________
DC AMPS FROM SHUNT READING ______________________________
CYCLES
Secondary Taps
___________Hz
DC Output
___________Hz
WHAT PROBLEM DOES THIS RECTIFIER HAVE, IF ANY?
__________________________________________________________________
HOW COULD THIS PROBLEM BE CORRECTED?
__________________________________________________________________
HOW WOULD YOU DETERMINE CORRECT PARTS (SIZE, RATING, TYPE, ETC.) NEEDED FOR THE REPAIR?
____________________________________________________________________________
NACE International | CP2
Page | 4
RECTIFIER STATION 2
AC INPUT VOLTAGE ______________________________________
AC STEP-DOWN VOLTAGE _________________________________
IDENTIFY COMPONENTS LABELED C __________________________
IDENTIFY COMPONENTS LABELED D __________________________
TAP SETTINGS _________________________________
DC VOLTAGE ON PANEL METER ____________________________
DC AMPS ON PANEL METER ________________________________
DC VOLTAGE ON RECTIFIER OUTPUT TERMINAL USING MULTIMETER ___________________________
DC mV ACROSS SHUNT _______________________________________
DC AMPS FROM SHUNT READING ______________________________
CYCLES
Secondary Taps
___________Hz
DC Output
___________Hz
WHAT PROBLEM DOES THIS RECTIFIER HAVE, IF ANY?
__________________________________________________________________
HOW COULD THIS PROBLEM BE CORRECTED?
__________________________________________________________________
HOW WOULD YOU DETERMINE CORRECT PARTS (SIZE, RATING, TYPE, ETC.) NEEDED FOR THE REPAIR?
__________________________________________________________________
NACE International | CP2
Page | 5
RECTIFIER STATION 3
AC INPUT VOLTAGE ______________________________________
AC STEP-DOWN VOLTAGE _________________________________
TAP SETTINGS _________________________________
DC VOLTAGE FROM PANEL METER ____________________________
DC CURRENT FROM PANEL METER ________________________________
DC VOLTAGE ON RECTIFIER OUTPUT TERMINAL USING MULTIMETER ______________
DC mV ACROSS SHUNT_______________________
DC CURRENT FROM SHUNT ______________________________
CYCLES
Secondary Taps ___________Hz
DC Output
___________Hz
WHAT PROBLEM DOES THIS RECTIFIER HAVE, IF ANY?
__________________________________________________________________
HOW COULD THIS PROBLEM BE CORRECTED?
__________________________________________________________________
HOW WOULD YOU DETERMINE CORRECT PARTS (SIZE, RATING, TYPE, ETC.) NEEDED FOR THE REPAIR?
__________________________________________________________________
NACE International | CP2
Page | 6
RECTIFIER STATION 4
Confirm that there is no power to the rectifier.
DIODE TEST FROM RECTIFIER PANEL
Remove taps and one load connection
Diode: Coarse Tap to Positive
Forward _____ Reverse _____Status? _______
Diode: Fine Tap to Positive
Forward _____ Reverse _____Status? _______
Diode: Negative to Coarse Tap
Forward _____ Reverse _____Status? _______
Diode: Negative to Fine Tap
Forward _____ Reverse _____Status? _______
WHICH DIODE NEEDS REPAIR AND HOW WOULD YOU DETERMINE CORRECT PARTS (SIZE, RATING, TYPE, ETC.)
NEEDED FOR THE REPAIR?
_____________________________________________________________________________________________
NACE International | CP2
Page | 7
NACE International | CP2
Page | 8
Station 2
IMPRESSED CURRENT INTERRUPTION
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 9
Practical Exercise Station 2 - Impressed Current Interruption
Current interrupters are used to “interrupt” an electrical circuit in order to obtain “on “ and “interrupted”
structure-to-electrolyte potential measurements.
During this exercise you will practice installing the interrupter and obtaining measurements using the
interrupter.
Part A.
Installing the current interrupter
Turn off the rectifier using the rectifier circuit breaker. (Note in some jurisdictions this breaker will need to
be locked out.)
1. Connect the rectifier negative terminal to the structure.
2. To install the interrupter in the anode cable as follows.
3. Connect one lead wire of the current interrupter to the anode cable and the other connection to
the positive rectifier terminal. Watch for polarity on certain interrupters and if polarity is indicated,
connect rectifier positive to interrupter positive.
4. Set the interrupter for the proper time you wish the interrupter to turn “on” and “off”.
Part B.
Test Procedure
1. Connect meter to measure a structure-to-electrolyte potential to the reference electrodes.
2. Take native structure-to-electrolyte potentials to reference electrodes at locations marked A, B,
and C.
3. Turn on the interrupter.
4. Turn on the rectifier using the rectifier circuit breaker.
5. Confirm that the current output is being interrupted.
6. Determine the length of the ON cycle and the OFF cycle.
7. Take structure-to-electrolyte potential measurements at locations marked A, B, and C noting the
length of time each reading is displayed and comparing it to the length of each cycle on the
interrupter.
8. Determine the ON and OFF potentials by the length of time of the cycle. DO NOT ASSUME THE
MOST ELECTRONEGATIVE POTENTIAL IS ALWAYS THE “ON” POTENTIAL. IF THE “ON” POTENTIAL
IS LESS ELECTRONEGATIVE THAN THE “OFF”, THE RECTIFIER IS CONNECTED WITH REVERSE
POLARITY.
9. If necessary, change the leads to achieve a more electronegative potential when the rectifier
comes on.
NACE International | CP2
Page | 10
Record data in the table below.
Note: Potentials measured must be converted to the equivalent values of other reference electrodes as noted.
Reference
Electrode Location
Native structure-toelectrolyte
potential
VZN
Structure-toelectrolyte
potential measured
"ON"
VCSE
VZN
VCSE
Structure-toelectrolyte potential
measured
"INTERRUPTED"
(INSTANT OFF)
VZN
Voltage (IR)
Drop
VCSE
A
B
C
Do the potential measurements meet a cathodic protection criterion?
Yes


No
If so, which criterion was met? _____________________________
Which location is the conclusion based on?
A ____
B ____
C ____
Why?_________________________________________________________________
Which reference electrode location is closest to the anode?
A
B
C



Which reference electrode location is closest to the structure?
A
B
C
NACE International | CP2



Page | 11
NACE International | CP2
Page | 12
Station 3
CURRENT REQUIREMENT TEST
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 13
Practical Exercise Station 3 - Current Requirement Test
A temporary anode, a current interrupter and a power supply are used to apply current to the structure.
The objective of the test is to determine by measurement and calculations the current required to achieve
a -0.85 VoltCSE polarized potential on the structure.
Part A.
Measure and record native structure-to-electrolyte potentials at the locations identified or supplied by
instructor.
Part B.
Install the current interrupter in the DC power supply.
To install in the D.C. Circuit of a rectifier, turn off breaker or disconnect the D.C. fuse and connect the
interrupter in the anode cable as in Part A of Station 2.
1. Connect the power supply negative to the structure.
2. Connect one side of the current interrupter to the anode cable and the other connection to the positive
terminal of the DC power supply.
3. Set the interrupter for the proper time you wish the interrupter to turn “on” and “off” if not preset by
instructor.
4. Turn on the interrupter.
5. Turn on the power source and confirm that it is being interrupted.
6. Determine the length of the ON and OFF cycle.
Measure and record ON and OFF structure-to-electrolyte potentials at the location identified by noting the
length of time for each cycle. Potentials must be converted to Volts and current to amperes in the
following equations.
NACE International | CP2
Page | 14
Measure and record the power source current output.
STRUCTURE-TO-ELECTROLYTE POTENTIAL (mVcse)
Native
On
Off
POWER SOURCE
CURRENT (mA)
CALCULATE Ireq
Ireq = _ Polarization Required x Itest
Polarization Achieved During Test
I req =
Ireq
=
(−0.850V − E Nativ e ) * I test
( EOff − E Native )
____
OR
I req =
Ireq
=
− 0.100V * I test
(E Off − E Native )
____
In this case, which criterion would be achieved first (at the least current)? ___________________________
NACE International | CP2
Page | 15
NACE International | CP2
Page | 16
Station 4
CATHODIC PROTECTION
COMMISSIONING
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 17
Practical Exercise Station 4 - Cathodic Protection Commissioning
Commissioning (energizing and adjusting) a new Cathodic Protection system is an important task and must
be done properly. Adequate levels of cathodic protection must be maintained without causing overvoltage
situations, stray current interference or premature failure of the anode system. Your task is to energize a new
Cathodic Protection system however stray current interference will be demonstrated in a different station.
Unfortunately, the construction crew that installed the Cathodic Protection system forgot to label which wire
is the anode wire and which wire is the pipe wire but the test lead that would normally be at a nearby point is
known to be on the pipeline.
Identify which wire(s) is/are connected to the pipe and to the anode (explain why), connect the rectifier up
properly, install an interrupter, take ON and OFF structure-to-electrolyte (S/E) potentials and adjust the
output of the rectifier until the pipeline meets the –850 VCSE polarized potential criterion for steel. Start
with rectifier on minimum output setting.
STRUCTURE-TO-ELECTROLYTE POTENTIAL
WIRE NO.
Anode wires: _______________
_______
Pipe wires:
_______
_______________
How did you come to the above conclusion? _________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
NACE International | CP2
Page | 18
Attempt No.
Tap Setting
Rect. Voltage
Output
Rect. Amperage
Output
S/E On
S/E Off
1
2
3
4
5
At what tap setting and current output does the pipe meet a CP criterion and which criterion is met?
Tap Setting: ___________________________________________________________________
DC Current output: _____________________________________________________________
Which criterion was met and why do you say the pipe meets this criterion?
_____________________________________________________________________________
_____________________________________________________________________________
NACE International | CP2
Page | 19
NACE International | CP2
Page | 20
Station 5
CURRENT SPAN
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 21
Practical Exercise Station 5 - Current Span
Students are to become competent in conducting tests to calibrate pipeline current spans. Calibrating the
current span is similar to establishing the shunt value or shunt factor in a current shunt. Once calibrated,
the calibration factor can be used to determine the residual current flowing from CP current sources
and/or stray current influences in the pipe span.
PROCEDURE
Part A.
Test Span Calibration
1. Calibrate the current spans #1 and #2 by impressing the provided current from the CS-10
power source through the outside wires (top terminals) of the respective test station and
measuring the voltage drop across the inside wires (bottom terminals) at each tests station.
TEST CONNECTIONS
+
CS-10
mV
-
+
Test Station
Panel
PIPE
Note: There are two identical test heads. Test Station #1 represents Current Span #1. Test Station #2
represents Current Span #2. Span #1 and Span #2 are spaced along a segment of pipe and may be a
mile or more apart from each other.
The test circuit is essentially a series electrical circuit as shown in the following schematic drawing.
NACE International | CP2
Page | 22
Controlled Power Supply
Current Interrupter
-
+
A
ITEST
CS-10
mV
-
+
IRESIDUAL
VTEST
ITOTAL (IT)
Resistor (RSPAN)
2. Test Station #1 Measurements
(Note polarity and thus direction)
ITEST1 ON (CS-10 ON)
__________mA
ITEST1 OFF (CS-10 OFF)
__________mA
ITEST1 = ITEST1 ON - ITEST1 OFF
__________mA
VTEST1 ON (CS-10 ON)
__________mV
VTEST1 OFF (CS-10 OFF)
__________mV
3. Test Station #2 Measurements
(Note polarity and thus direction)
ITEST1 ON (CS-10 ON)
__________mA
ITEST1 OFF (CS-10 OFF)
__________mA
ITEST1 = ITEST1 ON - ITEST1 OFF
__________mA
VTEST1 ON (CS-10 ON)
__________mV
VTEST1 OFF (CS-10 OFF)
__________mV
4. Pipe Span Resistance and Calibration Factor
NACE International | CP2
Page | 23
Calculate the current span resistance [Ω] and the calibration factor (A/mV) for each current span.
Note: potentials must be in Volts to calculate resistance and mV to calculate CF.
RSPAN =
(VTESTON − VTESTOFF )
( I TEST )
CFspan =
( I TEST )
(mVTESTON − mVTESTOFF )
Test Station #1
R1span = _______ Ω CFspan = _______ A/mV
Test Station #2
R2span = _______ Ω CFspan = _______ A/mV
5. Residual Current
Was there a residual current on the pipe section; that is, was there a VTEST reading with no Test
Current from CS-10?
Yes? ______ No?________
If so, calculate the current.
I RESIDUAL =
(VTESTOFF )
( RSPAN )
I RESIDUAL = mVOFF CFSPAN
Test Station #1 Residual Current = ________A ________mA
Test Station #2 Residual Current = ________ A ________mA
NACE International | CP2
Page | 24
Station 6
COATING CONDUCTANCE
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 25
Practical Exercise Station 6 - Coating Conductance
Students are to become competent in completing tests to measure and calculate the pipe coating
resistance and conductance.
The instructor will connect the station such that the pipe is receiving an interrupted supply of current from
an anode.
The instructor will give the following information:
RSPAN1 = _____________ Ω
or
CFSPAN1 = _____________ A/mV
RSPAN2 = _____________ Ω
or
CFSPAN2 = _____________ A/mV
Pipe Diameter _____________ m
Pipe Length _____________ m
Student:
□
□
1.
Confirm that the power supply is on and interrupting.
Confirm that the switch behind Test Station #1 is in the “on” position as it controls the
structure-to-electrolyte potentials.
Test Connections
Test Station #1
+
+
mV
V or
mV
V or
mV
mV
-
Test Station #2
-
-
Reference Electrode
+
-
+
Reference Electrode
Panel Top
PIPE
PIPE
The test is intended to determine the pipe to earth resistance through the coating (Rc) between
the test stations as represented by the darker colored pipe.
NACE International | CP2
Page | 26
This can be represented by an electrical circuit as shown below.
-
mVp1
+
mVp2
-
Rp1
+
Rp2
Ip1
Ip2
Rc
r
r
r
r
ΔEave
Ic
The objective is to calculate Rc by: RC =
∆E AVE
IC
2. Test Station #1 Measurements
mVp1 ON
__________mV
(Pipe Span with current ON)
mVp1 OFF
__________mV
(Pipe Span with Current OFF)
E1ON
__________mV
(ON Structure-to-electrolyte Potential)
E1OFF
__________mV
(OFF Structure-to-electrolyte Potential)
3. Test Station #2 Measurements
mVp2 ON
__________mV
(Pipe Span with current ON)
mVp2 OFF
__________mV
(Pipe Span with Current OFF)
E2ON
__________mV
(ON Structure-to-electrolyte Potential)
E2OFF
__________mV
(OFF Structure-to-electrolyte Potential)
4. Calculate Current in Each Pipe Span
Equation Summary
IC
=
ΔIP1
- ΔIP2
IP1ON
=
VP1ON
/ RP1
=
mVP1ON
x CF1
x CF2
ΔIP1
= IP1ON
-
IP1OFF
IP2ON
=
VP2ON
/ RP2
IP2ON
=
mVP2ON
ΔIP2
= IP2ON
-
IP2OFF
IP1OFF
=
VP1OFF
/ RP1
IP1OFF
=
mVP1OFF x CF1
IP2OFF
=
VP2OFF
/ RP2
IP2OFF
=
mVP2OFF X CF2
V (in Volts) = mV / 1000
NACE International | CP2
IP1ON
OR
mV = V x 1000
Page | 27
Test Station #1
IP1 ON
__________A
IP1 OFF
__________A
ΔIP1
__________A
Test Station #2
IP2 ON
__________A
IP2 OFF
__________A
ΔIP2
__________A
5. Current Pick Up in Coating Section (IC)
IC = ΔIP1 - ΔIP2
IC = __________A
6. Average Potential Across Coating Due to Current Applied
∆E1 = E1ON – E1OFF.
∆E2 = E2ON – E2OFF.
∆E1 = _______ mV
∆E2 = _______ mV
Calculate the average ∆E
[∆Eave =(∆E1 + ∆E2 )/ 2].
Average ∆Eave ________ mV
7. Pipe Coating Resistance
Calculate the total resistance of the pipe section to earth between test stations.
RC =
∆E AVE
IC
Total pipe coating resistance (Rc) = ____________ Ω
NACE International | CP2
Page | 28
8. Pipe Surface Area
Calculate surface area of pipe based on diameter and length of pipe given by:
A = πdL
Where:
A - Surface area of pipe
D – Outside Pipe Diameter
L – Length of coated pipe section
π – 3.1416
Pipe Diameter = ____________ m (given)
Pipe Length =
____________ m (given)
Surface area = ____________ m2
9. Specific Coating Resistance
Calculate the specific unit coating resistance (rc )in Ω-m2 .
rC = Rc * A
Specific unit coating resistance (rc) = ____________ Ω-m2
10. Specific Coating Conductance
Calculate the specific unit coating conductance (gc ) in S/m2 .
gC =
1
rC
Specific unit coating conductance (gc) = ____________ S/m2
NACE International | CP2
Page | 29
NACE International | CP2
Page | 30
Station 7
MITIGATION OF DC INTERFERENCE
USING A RESISTANCE BOND
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 31
Practical Exercise Station 7 - Mitigation of DC Interference Using a Resistance Bond
This exercise will demonstrate DC stray current interference and how it can be mitigated using a resistance
bond. The test station is shown in the photograph above with instructions for each part of the exercise as
follows:
Part A
1. Measure the AS FOUND potential of Line 1 and Line 2 at each of the locations.
Location
A
Connected to (VCSE)
Line 1
B
Line 1
C
Line 1
B
Line 2
D
Line 2
E
Line 2
A/F Potential (VCSE)
Part B
1. Connect the impressed current system to Line 2.
2. Measure the potential of Line 1 and Line 2 while interrupting the impressed current CP System.
Location
Connected to
A
Line 1
B
Line 1
B
Line 2
C
Line 1
D
Line 2
E
Line 2
NACE International | CP2
ON Potential (VCSE)
OFF Potential (VCSE)
Page | 32
Part C
1. What is the location of maximum exposure to interference on the line not connected to the interrupting
source? ________________________________
2. Starting at the highest resistance value available, install different resistors between Line 1 and Line 2 at the
point of maximum exposure.
3. Record the potentials at the location of maximum exposure and the value of the resistance in the table
below.
4. Repeat using lower resistance values until there is no longer a stray current interference situation (“on”
potential of the interfered-with structure has been returned to its original value).
5. Once the ideal resistance is obtained (potential returned to original value before interference current) at
the crossing, measure the voltage drop across this fixed resistance and record in the table below
6. Calculate the interference control current drain.
7. Turn off and disconnect the apparatus.
Control
Resistance Ohms
Potential Line 1
at maximum
exposure
ON
OFF
Potential Line 2 at
maximum
exposure
ON
OFF
Voltage Across
Bond Resistor
Interference
Control
Current
R=
R=
R=
R=
Current in resistance bond with DC interference mitigated: ______ mA
NACE International | CP2
Page | 33
NACE International | CP2
Page | 34
Station 8
MEASUREMENTS IN
ELECTRICAL CIRCUITS
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 35
Practical Exercise Station 8 – Measurements in Electrical Circuits
This exercise gives students practice connecting resistors in both series and parallel circuits. Using the
resistor board provided, follow the instructions noted in Part A and Part B of this exercise.
CAUTION: Remember to:
— measure resistance with the power off
— return the meter from Resistance to the DC Volts setting and
— turn the power back on after the connections are complete.
Part A: Parallel Circuit
1. Measure and record the resistance of Resistors A, B, C and D.
2. Measure source voltage (before connecting resistors): ___________________
3. Connect resistors A, B, C and D in parallel and complete the following table using Ohm’s Law where
necessary. Include polarity, numerical value and units when recording the measurement..
4. Explain difference (if any) with source voltage after connecting resistors.
____________________________________________________________________________________
____________________________________________________________________________________
RESISTOR
RESISTANCE
BATTERY EMF
(VOLTS)
VOLTAGE DROP
(VOLTS)
CURRENT
(AMPERES)
A
B
C
D
TOTAL
NACE International | CP2
Page | 36
5. Calculate the total resistance of the circuit. (Show your work.)
RESISTANCE (OHMS)
6.
Which of Kirchoff’s Laws applies to this circuit?
Kirchoff’s Law
Voltage

Current

NACE International | CP2
Page | 37
Practical Exercise Station 8 - Measurements in Electrical Circuits
Part B: Series Circuit
1. Measure and record the resistance of Resistors A, B, C and D.
2. Connect resistors A, B, C and D in series
3. Measure voltage across resistors
4. Complete the following table using Ohm’s Law where necessary. Include polarity, numerical value
and units when recording the measurement.
5. Measure source voltage.
RESISTOR
RESISTANCE
BATTERY EMF
(VOLTS)
VOLTAGE DROP
(VOLTS)
CURRENT
(AMPERES)
A
B
C
D
TOTAL
5. Calculate the total resistance of the circuit. (Show your work.)
RESISTANCE (OHMS)
7.
Which of Kirchoff’s Laws applies to this circuit?
Kirchoff’s Law
Voltage

Current

NACE International | CP2
Page | 38
Station 9
UNDERGROUND STORAGE TANK
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 39
Practical Exercise Station 9 - Underground Storage Tank
This test station simulates conditions for an underground fuel storage tank installation. You will obtain the
measurements indicated in the table that follows and record data obtained.
PART A
Continuity Test (Fixed Cell Reference Electrode Position)
Structure
Being Tested
Tank
Fill Pipe
Product
Pipe
Vent Pipe
Station
Ground
Survey
Comments
Fill Pipe
Product
Pipe
Vent Pipe
Station
Ground
Survey
Comments
Potentials
PART B
Potential Survey
Structure
Being Tested
Reference
Electrode
Location
Product end
of tank
Tank
ON
OFF
ON
OFF
ON
OFF
ON
OFF
ON
OFF
Center
Vent end of
tank
At product
riser
At vent riser
At station
ground
CONCLUSIONS ON TEST RESULTS
1. What structures are electrically continuous? ___________________________________________________
2. What structures meet a CP (NACE) criterion? __________________________________________________
NACE International | CP2
Page | 40
Station 10
CALCULATION STATION
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 41
Practical Exercise Station 10 – Calculation Station
Et
R1
R3
R2
NACE International | CP2
R1 = 4 Ohms
I2 = 2 Amperes
I3 = 1 Amperes
Et = 20 Volts
It = ____ Amperes
Rt = ____ Ohms
I1 = _____ Amperes
V1 = ___ Volts
V2 = ___ Volts
V3 = ___ Volts
R2 = ____ Ohms
R3 = ____ Ohms
Page | 42
Station 11
ROAD CASING AND CARRIER
PIPE MEASUREMENTS
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 43
Practical Exercise Station 11 – Road Casing and Carrier Pipe Measurements
OBJECTIVE
The object of this station is to demonstrate the difference in an electronic and a electrolytic shorted road
casing and to demonstrate the fact that the pipeline inside a shorted casing is not receiving CP even
though the potential outside the casing meets criterion.
PROCEDURE
1. Student to measure the on/off potential of pipe and casing with the reference outside of each
casing and decide if it is shorted.
2. Student to measure the on/off pipe and casing potentials to a reference inside each casing and
decide if the pipe meets the criterion.
Test Wire
#1
CASING A
Reference Electrode Outside
Casing
On
Off
Reference Electrode Inside
Casing
On
Off
CASING B
Reference Electrode Outside
Casing
On
Off
Reference Electrode
Inside Casing
On
Off
#2
Test Wire
#3
#4
NACE International | CP2
Page | 44
1. What is the casing status?
a. Casing A
i. Electronic short
ii. Electrolytic couple
b. Casing B
i. Electronic short
ii. Electrolytic couple
Yes
No
Yes
No
Yes
No
Yes
No
2. Does the carrier pipe inside the casing meet the polarized potential criterion?
a. Casing A
i. Meets criterion
Yes
N No
b. Casing B
i. Meets criterion
NACE International | CP2
Yes
No
Page | 45
NACE International | CP2
Page | 46
Station 12
SOIL RESISTIVITY MEASUREMENTS
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 47
Practical Exercise Station 12 - Soil Resistivity Measurements
During this exercise, you will measure resistance and calculate resistivity using the 4-pin Wenner method and
then calculate layer resistivity using the Barnes Layer formula.
Part A
1. Using the equipment provided, connect the 4 wires from the meter to the station electrodes at the
spacing in the table below.
2. Enter the results and calculate the resistivity based on a pin depth of 0.4 cm.
Pin Spacing (cm)
Resistance (ohms)
Resistivity (Ohm-cm)
2.5
5.0
7.5
Part B
Using the data provided, calculate the resistivity
Pin Spacing (m)
Resistance (Ohms)
1.60
10.0
3.20
6.8
5.60
3.2
Resistivity (Ohm-cm)
Using the Barnes Layer formula and the data above, calculate the resistivity of each layer in the table below.
Layer (cm)
Layer Resistance (Ohms)
Layer Resistivity (Ohm-cm)
0 to 160
160 to 320
320 to 560
NACE International | CP2
Page | 48
Note:
Care should be taken in the resolution of the answers. The significant number of digits in the data
determines the significant number of digits in the answer.
Basic rules:
All non-zero digits are significant: 1, 2, 3, 4, 5, 6, 7, 8, 9.
•
Zeros between non-zero digits are significant: 102, 3004, 50006.
•
Leading zeros are never significant: 0.01, 002.345, 0.000678.
In a number with or without a decimal point, trailing zeros (those to the right of the last non-zero digit) are
significant provided they are justified by the precision of the data: 345,000; 6.0600; 7.8000; 13.5700.
NACE International | CP2
Page | 49
NACE International | CP2
Page | 50
Station 13
POLARITY BOARD
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 51
Practical Exercise Station 13 – Polarity Board
1.
Measure and record the potential differences between each pair of banana jacks listed below. Record
magnitude, polarity and units for each measurement using the second color in each case as the
reference.
2.
After obtaining and recording the potential differences, use the data to order the colored banana jacks
by most negative polarity to most positive polarity.
PAIR
POTENTIAL
White to Blue
Red to Yellow
Green to Red
Blue to Yellow
Order the banana jacks by color from most negative to least negative.
Colored Banana Jack
MOST
NEGATIVE
LEAST
NEGATIVE
NACE International | CP2
Page | 52
CP 2│CATHODIC PROTECTION
TECHNICIAN
Practical Exercises Data
Sheets
SET #3
Version: March2020
NACE International | CP2
Page | 1
NACE International | CP2
Page | 2
Station 1
RECTIFIER TROUBLESHOOTING
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 3
Practical Exercise Station 1 - Rectifier Troubleshooting
RECTIFIER STATION 1
AC INPUT VOLTAGE ______________________________________
AC STEP-DOWN VOLTAGE _________________________________
IDENTIFY COMPONENTS LABELED A ________________________
IDENTIFY COMPONENTS LABELED B ________________________
TAP SETTINGS _________________________________
DC VOLTAGE ON PANEL METER ____________________________
DC AMPS ON PANEL METER ________________________________
DC VOLTAGE ON RECTIFIER OUTPUT TERMINAL USING MULTIMETER
___________________________
DC mV ACROSS SHUNT ______________________________________
DC AMPS FROM SHUNT READING ______________________________
CYCLES
Secondary Taps
___________Hz
DC Output
___________Hz
WHAT PROBLEM DOES THIS RECTIFIER HAVE, IF ANY?
__________________________________________________________________
HOW COULD THIS PROBLEM BE CORRECTED?
__________________________________________________________________
HOW WOULD YOU DETERMINE CORRECT PARTS (SIZE, RATING, TYPE, ETC.) NEEDED FOR THE
REPAIR?
____________________________________________________________________________
NACE International | CP2
Page | 4
RECTIFIER STATION 2
AC INPUT VOLTAGE ______________________________________
AC STEP-DOWN VOLTAGE _________________________________
IDENTIFY COMPONENTS LABELED C __________________________
IDENTIFY COMPONENTS LABELED D __________________________
TAP SETTINGS _________________________________
DC VOLTAGE ON PANEL METER ____________________________
DC AMPS ON PANEL METER ________________________________
DC VOLTAGE ON RECTIFIER OUTPUT TERMINAL USING MULTIMETER
___________________________
DC mV ACROSS SHUNT _______________________________________
DC AMPS FROM SHUNT READING ______________________________
CYCLES
Secondary Taps
___________Hz
DC Output
___________Hz
WHAT PROBLEM DOES THIS RECTIFIER HAVE, IF ANY?
__________________________________________________________________
HOW COULD THIS PROBLEM BE CORRECTED?
__________________________________________________________________
HOW WOULD YOU DETERMINE CORRECT PARTS (SIZE, RATING, TYPE, ETC.) NEEDED FOR THE
REPAIR?
__________________________________________________________________
NACE International | CP2
Page | 5
RECTIFIER STATION 3
Confirm that there is no power to the rectifier.
DIODE TEST FROM RECTIFIER PANEL
Remove taps and one load connection
Diode: Coarse Tap to Positive
Forward _____ Reverse _____Status? _______
Diode: Fine Tap to Positive
Forward _____ Reverse _____Status? _______
Diode: Negative to Coarse Tap
Forward _____ Reverse _____Status? _______
Diode: Negative to Fine Tap
Forward _____ Reverse _____Status? _______
WHICH DIODE NEEDS REPAIR AND HOW WOULD YOU DETERMINE CORRECT PARTS (SIZE,
RATING, TYPE, ETC.) NEEDED FOR THE REPAIR?
_________________________________________________________________________________
____________
NACE International | CP2
Page | 6
Station 2
IMPRESSED CURRENT
INTERRUPTION
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 7
Practical Exercise Station 2 - Impressed Current Interruption
Record data in the table below.
Potentials measured must be converted to the equivalent values of other reference
electrodes as noted.
Reference
Electrode
Location
Native structure-toelectrolyte potential
VZN
VCSE
Structure-toelectrolyte potential
measured "ON"
VZN
VCSE
Structure-to-electrolyte
potential measured
"INTERRUPTED"
(INSTANT OFF)
VZN
Voltage (IR)
Drop
VCSE
A
B
C
Do the potential measurements meet a cathodic protection criterion?
Yes

No

If so, which criterion was met? _____________________________
Which location is the conclusion based on?
A ____
B ____
C ____
Why? _________________________________________________________________
Which reference electrode location is closest to the anode?
A
B
C



Which reference electrode location is closest to the structure?
A
B
C
NACE International | CP2



Page | 8
Station 3
CURRENT REQUIREMENT TEST
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 9
Practical Exercise Station 3 - Current Requirement Test
STRUCTURE-TO-ELECTROLYTE POTENTIAL (mVcse)
Native
On
Off
POWER SOURCE
CURRENT (mA)
CALCULATE Ireq
Ireq for –0.850 VCSE ________
OR
Ireq for 100 mV _______
In this case, which criterion would be achieved first? __________________________________________
______________________________________________________________________________________
NACE International | CP2
Page | 10
Station 4
CATHODIC PROTECTION
COMMISSIONING
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 11
Practical Exercise Station 4 - Cathodic Protection Commissioning
Identify which wire(s) is/are connected to the pipe and to the anode (explain why), connect
the rectifier up properly, install an interrupter, take ON and OFF structure-to-electrolyte (S/E)
potentials and adjust the output of the rectifier until the pipeline meets the –850 VCSE
polarized potential criterion for steel. Start with rectifier on minimum output setting.
STRUCTURE-TO-ELECTROLYTE POTENTIAL
WIRE NO.
Anode wires: _______________
_______
Pipe wires:
_______
_______________
How did you come to the above conclusion? ______________________________________
______________________________________________________________________
______________________________________________________________________
Attempt No.
Tap Setting
Rect. Voltage
Output
Rect. Amperage
Output
S/E On
S/E Off
1
2
3
4
5
At what tap setting and current output does the pipe meet a CP criterion and which criterion is
met?
Tap Setting: ___________________________________________________
DC Current output: ___________________________________________
Which criterion was met and why do you say the pipe meets this criterion?
__________________________________________________________________
__________________________________________________________________
NACE International | CP2
Page | 12
Station 5
CURRENT SPAN
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 13
Practical Exercise Station 5 - Current Span
Test Span Calibration
1. Calibrate the current spans at Test Station #1
2. Record Test Station #1 Measurements
(Note polarity and thus direction)
ITEST1 ON (CS-10 ON)
__________mA
ITEST1 OFF (CS-10 OFF)
__________mA
ITEST1 = ITEST1 ON - ITEST1 OFF
__________mA
VTEST1 ON (CS-10 ON)
__________mV
VTEST1 OFF (CS-10 OFF)
__________mV
3. Pipe Span Resistance and Calibration Factor
Calculate the current span resistance [Ω] and the calibration factor (A/mV) for each
current span.
Test Station #1
R1span = _______Ω CF span = ________ A/mV
4. Residual Current
Was there a residual current on the pipe section; that is, was there a VTEST reading
with no Test Current from CS-10?
Yes? ______ No? ________
If so, calculate the current.
Test Station #1 Residual Current = ________A ________mA
NACE International | CP2
Page | 14
Station 6
COATING CONDUCTANCE
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 15
Practical Exercise Station 6 - Coating Conductance
CALCULATE THE COATING CONDUCTANCE OF THE PIPELINE SECTION.
The instructor will give the following information:
RSPAN1 = _____________ Ω
CFSPAN1 = _____________ A/mV
RSPAN2 = _____________ Ω
CFSPAN2 = _____________ A/mV
Pipe Diameter _____________ m
Pipe Length _____________ m
1. Test Station #1 Measurements
mVp1 ON
__________mV
(Pipe Span with current ON)
mVp1 OFF
__________mV
(Pipe Span with Current OFF)
E1ON
__________mV
(ON Structure-to-electrolyte Potential)
E1OFF
__________mV
(OFF Structure-to-electrolyte Potential)
2. Test Station #2 Measurements
mVp2 ON
__________mV
(Pipe Span with current ON)
mVp2 OFF
__________mV
(Pipe Span with Current OFF)
E2ON
__________mV
(ON Structure-to-electrolyte Potential)
E2OFF
__________mV
(OFF Structure-to-electrolyte Potential)
3. Calculate Current in Each Pipe Span
Test Station #1
IP1 ON
__________A
IP1 OFF
__________A
ΔIP1
__________A
NACE International | CP2
Page | 16
Test Station #2
IP2 ON
__________A
IP2 OFF
__________A
ΔIP2
__________A
4. Current Pick Up in Coating Section (IC)
IC = __________A
5. Average Potential Across Coating Due to Current Applied
∆E1 = _______ mV
∆E2 = _______ mV
Calculate the average ∆E
Average ∆Eave ________ mV
6. Pipe Coating Resistance
Calculate the total resistance of the pipe section to earth between test stations
Total pipe coating resistance (Rc) = ____________ Ω
7.
Pipe Surface Area
Calculate surface area of pipe based on diameter and length of pipe given by
Surface area = ____________ m2
8. Specific Coating Resistance
Calculate the specific unit coating resistance (rc )in Ω-m2 .
Specific unit coating resistance (rc) = ____________ Ω-m2
9. Specific Coating Conductance
Calculate the specific unit coating conductance (gc ) in S/m2 .
Specific unit coating conductance (gc) = ____________ S/m2
NACE International | CP2
Page | 17
NACE International | CP2
Page | 18
Station 7
MITIGATION OF DC INTERFERENCE
USING A RESISTANCE BOND
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 19
Practical Exercise Station 7 - Mitigation of DC Interference Using a Resistance Bond
Part A
1. Measure the ON Potential of Line 1 and Line 2 at each of the locations.
Location
A
Connected to (VCSE)
Line 1
B
Line 1
B
Line 2
D
Line 2
A/F Potential (VCSE)
Part B
1. Connect the impressed current system to Line 2.
2. Measure the potential of Line 1 and Line 2 while interrupting the impressed current CP
System.
Location
Connected to
A
Line 1
B
Line 1
B
Line 2
D
Line 2
ON Potential (VCSE)
OFF Potential (VCSE)
Part C
1. What is the location of maximum exposure to interference on the line not connected to the
interrupting source? ________________________________
2. Starting at the highest resistance value available, install different resistors between Line 1 and
Line 2 at the point of maximum exposure.
3. Record the data in the table below with the reference at the location of maximum exposure
and the value of the resistance in the table below.
Control
Resistance Ohms
Potential Line 1
at maximum
exposure
ON
OFF
Potential Line 2 at
maximum
exposure
ON
OFF
Voltage Across
Bond Resistor
Interference
Control
Current
R=
R=
R=
R=
Current in resistance bond with DC interference mitigated: ___ mA
NACE International | CP2
Page | 20
Station 8
MEASUREMENTS IN
ELECTRICAL CIRCUITS
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 21
Practical Exercise Station 8 – Measurements in Electrical Circuits
Part A: Parallel Circuit
1. Measure and record the resistance of Resistors A, B, C and D.
2. Measure source voltage (after connecting resistors): ___________________
3. Connect resistors A, B, C and D in parallel and complete the following table.
4. Explain difference (if any) with source voltage after connecting resistors.
________________________________________________________________________
________________________________________________________________________
RESISTANCE
RESISTOR
BATTERY EMF
(VOLTS)
VOLTAGE DROP
(VOLTS)
CURRENT
(AMPERES)
A
B
C
D
TOTAL
5. Calculate the total resistance of the circuit. (Show your work.)
RESISTANCE (OHMS)
6.
Which of Kirchoff’s Laws applies to this circuit?
Kirchoff’s Law
Voltage

Current

NACE International | CP2
Page | 22
Practical Exercise Station 8 - Measurements in Electrical Circuits
Part B: Series Circuit
1.
2.
3.
4.
Measure and record the resistance of Resistors A, B, C and D.
Connect resistors A, B, C and D in series.
Complete the following table.
Measure source voltage.
RESISTOR
RESISTANCE
VOLTAGE DROP
(VOLTS)
CURRENT
(AMPERES)
A
B
C
D
TOTAL
5. Calculate the total resistance of the circuit. (Show your work.)
RESISTANCE (OHMS)
7.
Which of Kirchoff’s Laws applies to this circuit?
Kirchoff’s Law
Voltage

Current

NACE International | CP2
Page | 23
NACE International | CP2
Page | 24
Station 9
UNDERGROUND STORAGE TANK
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 25
Practical Exercise Station 9 - Underground Storage Tank
PART A
Structure
Being Tested
Continuity Test (Fixed Cell Reference Electrode Position)
Tank
Fill Pipe
Product
Pipe
Vent Pipe
Station
Ground
Survey
Comments
Product
Pipe
Vent Pipe
Station
Ground
Survey
Comments
Potentials
PART B
Structure
Being Tested
Reference
Electrode
Location
Product end
of tank
Potential Survey
Tank
ON
OFF
Fill Pipe
ON
OFF
ON
OFF
ON
OFF
ON
OFF
Center
Vent end of
tank
At product
riser
At vent riser
At station
ground
CONCLUSIONS ON TEST RESULTS
1. What structures are electrically continuous?
2. What structures meet a CP (NACE) criterion? ______________________________________
NACE International | CP2
Page | 26
Station 10
CALCULATION STATION
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 27
Practical Exercise Station 10 – Calculation Station
Given the following, what is the specific coating conductance of the pipe section?
5 km long & 914 mm Diameter
0.5 A
On -1000 mVCSE
Off -950 mVCSE
NACE International | CP2
0.1 A
On -980 mVCSE
Off -950 mVCSE
Page | 28
Station 11
ROAD CASING AND CARRIER
PIPE MEASUREMENTS
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 29
Practical Exercise Station 11 – Road Casing and Carrier Pipe Measurements
Test Wire
#1
CASING A
Reference Electrode Outside
Casing
On
Off
Reference Electrode Inside
Casing
On
Off
CASING B
Reference Electrode Outside
Casing
On
Off
Reference Electrode
Inside Casing
On
Off
#2
Test Wire
#3
#4
1. What is the casing status?
a. Casing A
i. Electronic short
ii. Electrolytic couple
b. Casing B
i. Electronic short
ii. Electrolytic couple
Yes
No
Yes
No
Yes
No
Yes
No
2. Does the carrier pipe inside the casing meet the polarized potential criterion?
a. Casing A
i. Meets criterion
Yes
N No
b. Casing B
i. Meets criterion
NACE International | CP2
Yes
No
Page | 30
Station 12
SOIL RESISTIVITY MEASUREMENTS
(SEE NEXT PAGE FOR TEST DATA)
NACE International | CP2
Page | 31
Practical Exercise Station 12 - Soil Resistivity Measurements
During this exercise, you will measure the resistance and calculate the resistivity using the
4-pin Wenner method and then calculate layer resistivity using the Barnes Layer formula.
Part A
1. Using the equipment provided, connect the 4 wires from the meter to the station
electrodes at the spacing in the table below.
2. Enter the results and calculate the resistivity based on a pin depth of 0.1 cm.
Pin Spacing (cm)
Resistance (Ohms)
Resistivity (Ohm-cm)
2.50
5.00
7.50
Part B
Using the data provided, calculate the resistivity.
Pin Spacing (m)
Resistance (Ohms)
2.50
12.0
5.00
4.2
7.50
0.8
Resistivity (Ohm-cm)
Using the Barnes Layer formula and the data above, calculate the resistivity of each layer in the
table below.
Layer (cm)
Layer Resistance (Ohms)
Layer Resistivity (Ohm-cm)
0 to 250
250 to 500
500 to 750
Note:
NACE International | CP2
Page | 32
Care should be taken in the resolution of the answers. The significant number of digits in the
data determines the significant number of digits in the answer.
Basic rules:
All non-zero digits are significant: 1, 2, 3, 4, 5, 6, 7, 8, 9.

Zeros between non-zero digits are significant: 102, 3004, 50006.

Leading zeros are never significant: 0.01, 002.345, 0.000678.
In a number with or without a decimal point, trailing zeros (those to the right of the last nonzero digit) are significant provided they are justified by the precision of the data: 345,000;
6.0600; 7.8000; 13.5700.
NACE International | CP2
Page | 33
NACE International | CP2
Page | 34
CP2 | Reference Sheets
RESISTIVITY
CONVERSIONS
EMF
E or e
V
mV
µV
I
i
mA
µA
R, or Ω
electromotive force – any voltage unit
any voltage unit
volts
millivolts
microvolts
any amperage unit
current density (amp/area)
milliamperes or milliamps
microamperes or microamps
Resistance
1,000,000 volts
1,000 volts
1.0 volt
0.100 volt
0.010 volt
0.001 volt
0.000001 volt
=
1 megavolt
=
1 kilovolt
= 1000 millivolts
= 100 millivolts
= 10 millivolts
=
1 millivolt
=
1 microvolt
1,000,000 amperes
1,000 amperes
1.0 ampere
0.100 ampere
0.010 ampere
0.001 ampere
0.000001 ampere
=
1 mega-ampere
=
1 kiloampere
= 1000 milliamperes
= 100 milliamperes
= 10 milliamperes
=
1 milliampere
=
1 microampere
1,000,000 ohms
1,000 ohms
1.0 ohms
0.100 ohm
0.010 ohm
0.001 ohm
0.000001 ohm
=
1 mega-ohm
=
1 kilo-ohm
= 1000 milliohms
= 100 milliohms
= 10 milliohms
=
1 milliohm
=
1 micro-ohm
1 meter = 1000 mm = 100 cm
1 inch
= 25.4 mm = 2.54 cm
= 0.0254m
1 foot
= 304.8mm = 30.48 cm = 0.3048m
ρ=R A
L
R = ρL
A
ρ, Resistivity in ohm-cm
R, Resistance in ohms
A, Cross-Sectional Area in cm2*
L, Length in cm*
*length and area can be in any units as long as they are consistent
where
WENNER METHOD
ρ=2πaR
where ρ, resistivity in ohm-cm*
a, the spacing of the pins (cm)*
R, the resistance measured (ohms)
ρ, resistivity (ohm-cm)*
*pin spacing can be in any units as long as it is consistent with resistivity
OR
ρ=191.5aR
where ρ, resistivity in ohm-cm
a, the spacing of the pins (feet)
R, the resistance measured (ohms)
ρ, resistivity (ohm-cm)
191.5 = conversion factor from feet to cm
RESISTIVITY LAYER CALCULATIONS
RL2 =
R2 Layer
ρ2 Layer
(R1 R2)
(R1 – R2)
ρL2= 2πL2 RL2
R3 Layer
RL3 = (R2 R3) / (R2 – R3)
ρ3 Layer
ρL3 = 2πL3 RL3
OHMS LAW
V = IR
I=V/R
R=V/I
POWER
P = EI
P = I2 R
NACE International | Page 1
CP2 | Reference Sheets
SERIES CIRCUIT
PARALLEL CIRCUIT
ET = V1 + V2 + V3
ET = V1 = V2 = V3
IT = I1 = I2 = I3
IT = I1 + I2 + I3
RT = R1 + R2 + R3
1/RT = 1/R1 + 1/R2 + 1/R3
RT =
CONSUMPTION RATE (K) FOR VARIOUS METALS(1)
Reduced
Species
Al
Cd
Be
Ca
Cr
Cu
H2
Fe
Pb
Mg
Ni
OH
Zn
1
1
1
1
+
+
R1
R2
R3
GEOMETRY
Area of circle =
π r2
Surface area of a cylinder = π *d * L
Oxidized
Species
Al***
Cd**
Be**
Ca**
Cr***
Cu**
H*
Fe**
Pb**
Mg**
Ni**
O2
Zn**
Molecular
Weight M (g)
26.98
112.4
9.01
40.08
52.00
63.54
2.00
55.85
207.19
24.31
58.71
32.00
65.37
Electrons
Transferred (n)
3
2
2
2
3
2
2
2
2
2
2
4
2
Equivalent Weight
M/n (g)
8.99
56.2
4.51
20.04
17.3
31.77
1.00
27.93
103.6
12.16
29.36
8.00
32.69
Theoretical Consumption
Rate (Kg/A-y)
2.94
18.4
1.47
6.55
5.65
10.38
0.33
9.13
33.85
3.97
9.59
2.61
10.7
π = Pi approximately = 3.14
STEEL PIPE RESISTANCE(A)
FARADAY’S LAW
Pipe
Size
Wt = KIT
where
Wt
K
I
T
in.
=
=
=
=
weight loss, kg
electrochemical equivalent, kg/A-yr
Amps
years
RELATIVE VALUES OF TYPICAL REFERENCE ELECTRODES TO A
HYDROGEN ELECTRODE
Electrode (Half-Cell)*
Potential (volt)
Copper-Copper Sulfate (CSE)
+0.316
Silver-Silver Chloride (3.5%) (SSC)
+0.256
Saturated Calomel (SCE)
+0.244
Standard Hydrogen (SHE)
0.000
Zinc (ZN)
–0.800
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
32
34
36
Outside Diameter
in.
2.35
4.5
6.62
8.62
10.75
12.75
14.00
16.00
18.00
20.00
22.00
24.00
26.00
28.00
30.00
32.00
34.00
36.00
Wall Thickness
Weight
Cm
in.
cm
lb / ft
5.97
11.43
16.81
21.89
27.31
32.38
35.56
40.64
45.72
50.80
55.88
60.96
66.04
71.12
76.20
81.28
86.36
91.44
0.154
0.237
0.280
0.322
0.365
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.39
0.60
0.71
0.82
0.93
0.95
0.95
0.95
0.95
0.95
0.95
0.95
0.95
0.95
0.95
0.95
0.95
0.95
3.65
10.8
16.0
28.6
40.5
46.6
54.6
62.6
70.6
78.6
86.6
94.6
102.6
110.6
118.7
126.6
134.6
142.6
kg / m
5.43
16.07
28.28
42.56
60.27
73.81
81.26
93.16
105.07
116.97
128.88
140.78
152.69
164.59
176.65
188.41
200.31
212.22
Resistance
µohms/ft µohms/m
76.2
26.8
15.2
10.1
7.13
5.82
5.29
4.61
4.09
3.68
3.34
3.06
2.82
2.62
2.44
2.28
2.15
2.03
256.84
87.93
46.87
33.14
23.39
16.09
17.36
15.12
13.42
12.07
10.96
10.04
9.25
8.60
8.01
7.48
7.05
6.66
(A) Based on steel density of 489 lbs/ft3 (7832 kg/m3) and steel resistivity of 18 microhmcm.
NACE International | Page 2
CP2 | Reference Sheets
4-WIRE CURRENT SPAN TEST STATION
𝑅𝑅𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 =
∆𝑉𝑉𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 𝑉𝑉
∆𝐼𝐼𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 𝐴𝐴
Ir = 𝐶𝐶𝐶𝐶 ∗ 𝑉𝑉𝑉𝑉𝑉𝑉𝑉𝑉 𝑚𝑚𝑚𝑚
CFspan = 𝐾𝐾 =
OR
Ir =
∆𝐼𝐼𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 𝐴𝐴
∆𝐸𝐸𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 𝑚𝑚𝑚𝑚
COATING CONDUCTANCE
∆Eave
Rc =
∆Ic
∆Eave =
𝑉𝑉 𝑜𝑜𝑜𝑜𝑜𝑜 𝑉𝑉
∆E1 (∆E 2 ) = ( EON − EOFF )
𝑅𝑅𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠
Where: Rspan – Resistance of pipeline span (Ω)
ΔV - Voltage drop due to test current (Von – Voff)
ΔI - Net Test Current (Ion – Ioff)
CF = K = Calibration Factor (A/mV)
Ir - Pipeline or residual pipeline current (A)
V - Voltage drop across span
(∆E1 + ∆E 2 )
2
∆Ic = ∆I 1 − ∆I 2
∆I 1 (∆I 2 ) = ( I ON − I OFF )
Gc =
g=
1
r
𝑟𝑟 = 𝑅𝑅𝑐𝑐 𝑥𝑥 𝐴𝐴
1
Rc
g=
Gc
A
A=π d L
Where: Rc – Coating resistance of pipe section (Ω)
ΔEave
- Average pipe-to-electrolyte potential change due to applied current
(V)
ΔE1 (ΔE2)
- Potential change at each end of pipe section due to applied
current (V)
Eon (Eoff) - On or off pipe-to-electrolyte potential at each end of pipe section
ΔIc
- Net current pickup in pipe section (A)
ΔI1 (ΔI2)
- Net pipeline current at each end of pipe section due to applied
current (A)
Ion (Ioff)
- On or off pipeline current at each end of pipe section (A)
r
- Specific coating resistance (Ω-m2 or Ω-ft2 depending on surface
area units)
A
- Surface area of pipe (m2 or ft2)
π
- Pi = 3.1416
Gc
- Coating conductance of pipe section (Siemens)
g
- Specific coating conductance (Siemens/ m2 or Siemens/ft2)
NACE International | Page 3
CP2 | Reference Sheets
RECTIFIER EFFICIENCY FORMULA
SHUNT TYPES AND VALUES
P
Efficiency = DC *100
PAC
Shunt Rating
PDC = VDC x IDC
PDC = DC power (watts)
VDC = Output DC Voltage (Volts)
Output DC Current (Amperes)
IDC =
PAC = VAC x I AC
PAC = AC power (watts)
Input AC Voltage (Volts)
VAC =
Input AC Current (Amperes)
IAC =
AC Input Power =
3600 K N
T
where:
K = meter constant (shown on face of meter)
N = No. disk revolutions (observe for 60 sec.)
T = time in seconds of observation
CURRENT REQUIREMENT CALCULATIONS
I req =
I req
(−0.850V − E Nativ e ) * I test
( EOff − E Native )
− 0.100V * I test
=
(E Off − E Native )
mV
Ohms
A/mV
RS
5
50
.01
.1
SS
25
25
.001
1
SO
50
50
.001
1
SW or CP
1
50
.05
.02
SW or CP
2
50
.025
.04
SW or CP
3
50
.017
.06
SW or CP
4
50
.0125
.08
SW or CP
5
50
.01
.1
SW or CP
10
50
.005
.2
SW
15
50
.0033
.3
SW
20
50
.0025
.4
SW
25
50
.002
.5
SW
30
50
.0017
.6
SW
50
50
.001
1
SW
60
50
.0008
1.2
SW
75
50
0.00067
1.5
SW
100
50
.0005
2
5
50
.01
.1
Holloway Type
J.B. Type
R
Etrue = Vmeter x total
Rmeter
Agra-Mesa
K=
Rl
Rh
Vh (1 − K)
…….
Vh
1− K
Vl
Shunt Factor
Amps
METER MEASUREMENT ERROR
Etrue =
Shunt Value
Cott or MCM
Red
2
200
.1
.01
Yellow
8
80
.01
.1
Orange
25
25
.001
1
NACE International | Page 4
CP2 | Reference Sheets
U.S. Customary/Metric Conversion for Units of Measure
Commonly Used in Corrosion-Related Publications
1 A/ft2
1 acre
1 A·h/lb
1 bbl (oil, U.S.)
1 bpd (oil)
1 Btu
1 Btu/ft2
1 Btu/h
1 Btu/h·ft2
1 Btu/h·ft2·°F
1 Btu·in/h·ft2·°F
1 cfm
1 cup
1 cycle/s
1 ft
1 ft2
1 ft3
1 ft·lbf (energy)
1 ft·lbf (torque)
1 ft/s
1 gal (Imp.)
1 gal (U.S.)
1 gal (U.S.)/min (gpm)
1 gal/bag (U.S.)
1 grain
1 grain/ft3
1 grain/100 ft3
1 hp
1 microinch (µin)
1 in
1 in2
1 in3
1 in·lbf (torque)
1 inHg
NACE International
= 10.76 A/m2
= 4,047 m2 = 0.4047 ha
= 2.205 A·h/kg
= 159 L = 0.159 m3
= 159 L/d = 0.159 m3/d
= 1,055 J
= 11,360 J/m2
= 0.2931 W
= 3.155 W/m2 (K-factor)
= 5.678 W/m2·K
= 0.1442 W/m·K
= 28.32 L/min = 0.02832 m3/min =
40.78 m3/d
= 236.6 mL = 0.2366 L
= 1 Hz
= 0.3048 m
= 0.0929 m2 = 929 cm2
= 0.02832 m3 = 28.32 L
= 1.356 J
= 1.356 N·m
= 0.3048 m/s
= 4.546 L = 0.004546 m3
= 3.785 L = 0.003785 m3
= 3.785 L/min = 0.2271 m3/h
= 89 mL/kg (water/cement ratio)
= 0.06480 g = 64.80 mg
= 2.288 g/m3
= 22.88 mg/m3
= 0.7457 kW
= 0.0254 µm = 25.4 nm
= 0.0254 m = 2.54 cm = 25.4 mm
= 6.452 cm2 = 645.2 mm2
= 16.387 cm3 = 0.01639 L
= 0.113 N·m
= 3.386 kPa
1 inH2O
1 knot
1 ksi
1 lb
1 lbf/ft2
1 lb/ft3
1 lb/100 gal (U.S.)
1 lb/1,000 bbl
1 mA/in2
1 mA/ft2
1 Mbpd (oil)
1 mile
= 249.1 Pa
= 0.5144 m/s
= 6.895 MPa
= 453.6 g = 0.4536 kg
= 47.88 Pa
= 16.02 kg/m3
= 1.198 g/L
= 2.853 mg/L
= 0.155 mA/cm2
= 10.76 mA/m2
= 159 kL/d = 159 m3/d
= 1.609 km
1 square mile
1 mile (nautical)
1 mil
1 MMcfd
1 mph
1 mpy
1 oz
1 oz fluid (Imp.)
1 oz fluid (U.S.)
1 oz/ft2
1 oz/gal (U.S.)
1 psi
1 qt (Imp.)
1 qt (U.S.)
1 tablespoon (tbs)
1 teaspoon (tsp)
1 ton (short)
1 U.S. bag cement
1 yd
1 yd2
1 yd3
= 2.590 km2
= 1.852 km
= 0.0254 mm = 25.4 µm
= 2.832 x 104 m3/d
= 1.609 km/h
= 0.0254 mm/y = 25.4 µm/y
= 28.35 g
= 28.41 mL
= 29.57 mL
= 2.993 Pa
= 7.49 g/L
= 0.006895 MPa = 6.895 kPa
= 1.1365 L
= 0.9464 L
= 14.79 mL
= 4.929 mL
= 907.2 kg
= 42.63 kg (94 lb)
= 0.9144 m
= 0.8361 m2
= 0.7646 m3
CP2 | Page 5
CP2 | Reference Sheets
Color Code for Resistors
A
B
C
D
First Significant
Figure. If double
wide, resistor
is wire wound.
Tolerance
Multiplier
Second Significant Figure
Band A
Black
Brown
Red
Orange
Yellow
Green
Blue
Violet
Gray
White
0
1
2
3
4
5
6
7
8
9
Band B
Black
Brown
Red
Orange
Yellow
Green
Blue
Violet
Gray
White
Values
0
1
2
3
4
5
6
7
8
9
Black
Brown
Red
Orange
Yellow
Green
Blue
Silver
Gold
Band C
1
10
100
1,000
10,000
100,000
1,000,000
Silver
Gold
Band D
± 10%
± 5%
0.01
0.1
Example
A
B
C
D
A = Red = 2
C = Orange = 1,000
B = Blue = 6
D = Silver = ± 10%
Resistance Value = 26,000 Ω ± 10%, or between 23,400 Ω and 28,600 Ω.
NACE International
CP2 | Page 6
BECOMING CERTIFIED
All certifications are administered and managed by the NACE International Institute (NII). NACE
International continues to set the standard for corrosion education worldwide, as part of its
mission to protect people, assets and the environment from corrosion. Built upon decades of
knowledge and expertise from industry subject matter experts, the NACE International Institute
certifications are the most recognized and widely accepted corrosion certifications in the world.
Why should you get a NACE International Institute Certification?
• Personnel qualifications are reaching the highest level of standardization ever; a necessity in
a global economy.
• Worldwide businesses rely on the NACE Institute certifications as a metric for increased
standardization of personnel performance.
• The value of a certification held by someone increases as new international standards
related to that certification unfold.
******************************************************************************
Certification requirements could include but are not limited to:
Educational or academic requirements
Successful completion of required exam(s)
NDA (Non-Disclosure Agreement) - a signed NDA will be required before taking any NII
certification exam
4) Submission of a certification application and subsequent approval by the NACE Institute
5) Work experience requirements (amount varies per certification type and level)
6) Qualification references
1)
2)
3)
To submit an application for consideration or to find out more information about our
certification programs please visit the NACE International Institute website at
http://www.naceinstitute.org/Certification/
Houston, Texas USA | Phone: +1 281-228-6223 or +1 800-797-6223 | Fax: +1 281-228-6300
niifirstservice@nace.org
Scheduling Your Computer-based
Exam with Pearson Vue
1. Go to naceinstitute.org,
Click on the Login button
Sign in with your credentials
2. Click on the down arrow next
to your profile icon
3. Click on the profile button and
then on ‘My Certification Portal’
Accessing Your Exam
4. Select ‘Schedule/Manage
Exams’
5. Your pre-paid exam will be listed
here
(If taking an exam that is not
included in a course registration fee,
choose an exam here)
Terms, Conditions, and
Accommodations
6. Agree to the legal Terms and
Conditions
Enter your digital signature (full name) and Click Agree
(if you do not agree, you will not be able to proceed)
7. Special Accommodations
If needed in accordance with the ADA for the course or
exam, please select ‘Yes’ and complete the application.
Please allow 5-10 business days for response.
If you do not need special accommodations,
select ‘No’ and proceed to checkout
Scheduling Your Exam
Note: If your exam is pre-paid (included with a course registration fee)
a zero balance due will be reflected at checkout. For exam retakes,
payment will be required.
Once the checkout process is complete, you will be redirected to the
Pearson VUE scheduling portal to schedule your CBT (computer-based testing)
exam. For non-CBT exams, you will be directed to the NACE Institute for scheduling.
8. On the Pearson VUE page, you will be able to see your
pre-approved exams available for scheduling. Select your
exam to continue.
Select a Test Center
9. Select ‘Schedule
this Exam’
10. Pearson VUE will
search for the nearest
Pearson Test Centers based
on your address. You can
also change the address and
find others more convenient to
your current location. Select a
Test Center and click next.
Select Your Test Date, Confirm
Details
11. Select a date, which will show
available times to schedule your
exam.
12. Confirm your appointment
details before proceeding to check out
Personal Information and Policy
Acceptance
13. Confirm your personal
information and click
next.
14. Review the policy
information, click the
acknowledgement, and
click next.
Verify Exam Details
15. Verify your exam details and click submit order to
finalize your exam registration
Submit Exam Order
16. An email confirmation will be sent to the email
address on record. You’re registered!
CP2 | Reference Sheets
Does
Breaker
Trip?
No
Temporary short or circuit
resistance dropped.
output voltage level
Restore
Yes
Disconnect DC
Output Cable & Reset
Breaker
Tripped
Input Circuit
Breaker
Yes
Lower Voltage Taps
& Reset Breaker
Does
Breaker
Trip?
No
Look for short
in output circuit
Yes
Remove taps
Does
Breaker
Trip?
Fault in
transformer or
breaker
Fault in rectifier between
Transformer and output
NACE International
CP2 | Page 7
CP2 | Reference Sheets
NACE International
CP2 | Page 8
CP2 | NACE Standards
English
SP0169-2013 (Formerly RP0169), "Control of external corrosion on underground or
submerged metallic piping systems"
SP0177-2014 (Formerly RP0177), Mitigation of alternating current and lightning effects
on metallic structures and corrosion control systems
SP0200-2014, Steel-cased pipeline practices
TM0497-2012, Measurement techniques related to criteria for cathodic protection on
underground or submerged metallic piping systems
TM0102-2002, Measurement of protective coating electrical conductance on
underground pipelines
SP0290-2007 (Formerly RP0290), Impressed current cathodic protection of reinforcing
steel in atmospherically exposed concrete structures
SP0285-2011 (Formerly RP0285), “Corrosion control of underground storage tank
systems by cathodic protection”
SP0196-2015 (Formerly RP0196), “Galvanic anode cathodic protection of internal
submerged surfaces of steel water storage tanks”
SP0575-2007 (Formerly RP0575), Internal cathodic protection (cp) systems in oiltreating vessels
SP0193-2016 (Formerly RP0193) External cathodic protection of on-grade carbon steel
storage tank bottoms
SP0286-2007 (Formerly RP0286), Electrical isolation of cathodically protected pipelines
TM0115-2015, “Cathodic disbondment test for coated steel structures under cathodic
protection”
NACE SP0104-2014(Formerly RP0104), "The use of coupons for cathodic protection
monitoring applications"
SP0408-2014, Cathodic protection of reinforcing steel in buried or submerged concrete
structures
SP0100-2014 (Formerly RP0100), Cathodic protection to control external corrosion of
concrete pressure pipelines and mortar-coated steel pipelines for water or waste water
service
NACE TM0294-2016, “Testing of embeddable impressed current anodes for use in
cathodic protection of atmospherically exposed steel-reinforced concrete”
CP2 | NACE Standards
SP0572-2007 (Formerly RP0572), Design, installation, operation, and maintenance of
impressed current deep anode beds
NACE STANDARD TM0105-2016, “Evaluation of coatings containing conductive carbon
pigmentation for use as an anode on atmospherically exposed reinforced concrete”
TM0101-2012 Measurement techniques related to criteria for cathodic protection of
underground storage tank systems
RP0375-2006, Field-applied underground wax coating systems for underground
pipelines: application, performance, and quality control
NACE STANDARD TM21423-2017, “Test method for determination of substrate and
surface temperature limits for insulative coatings used for personnel protection”
SP0176-2007 (Formerly RP0176), Corrosion control of submerged areas of permanently
installed steel offshore structures associated with petroleum production
MR0174-2007, Selecting inhibitors for use as sucker-rod thread lubricants
TM0404-2004, Offshore platform atmospheric and splash zone new c
TM0304-2004, Offshore platform atmospheric and splash zone maintenance coating
system evaluation
SP0107-2017, “Electrochemical realkalization and chloride extraction for reinforced
concrete”
SP0207-2007, Performing close-interval potential surveys and dc surface potential
gradient surveys on buried or submerged metallic pipelines
SP0187-2017 (Formerly RP0187), Design considerations for corrosion control of
reinforcing steel in concrete.
SP0487-2007 (FORMERLY RP0487), Considerations in the selection and evaluation of
rust preventives and vapor corrosion inhibitors for interim (temporary) corrosion
protection
NACE NO. 12/AWS C2.23M/SSPC CS 23, “Specification for the application of thermal
spray coatings (metallizing) of aluminum, zinc, and their alloys and composites for the
corrosion protection of steel”
TM0183-2018, Evaluation of internal plastic coatings for corrosion control of tubular
goods in an aqueous flowing environment
TM0113-2013, "Evaluating the accuracy of field-grade reference electrodes"
CP2 | NACE Standards
Chinese
RP0285-2002, Corrosion control of underground storage tank systems by cathodic
protection
SP0177-2007 Mitigation of alternating current and lightning effects on metallic
structures and corrosion control systems
RP0388-2001, Impressed current cathodic protection of internal submerged surfaces of
carbon steel water storage tanks
RP0196-2004, Galvanic anode cathodic protection of internal submerged surfaces of
steel water storage tanks
SP0572-2007 - Design, installation, operation, and maintenance of impressed current
deep anode beds
RP0169-2002, Control of external corrosion on underground or submerged metallic
piping systems
SP0206-2006, Internal corrosion direct assessment methodology for pipelines carrying
normally dry natural gas (dg-icda)
NACE NO. 12/AWS C2.23M/SSPC-CS 23, Specification for the application of thermal
spray coatings (metallizing) of aluminum, zinc, and their alloys and composites for the
corrosion protection of steel
RP0176-2003, Corrosion control of steel fixed offshore structures associated with
petroleum production
RP0288-2004, Inspection of linings on steel and concrete
SP0207-2007 Performing close-interval potential surveys and dc surface potential
gradient surveys on buried or submerged metallic pipelines
Spanish
SP0285-2011 (ANTES RP0285), "Control de la corrosión exterior en sistemas de
tanques de almacenamiento enterrados mediante protección catódica"
Download