Flow Chart
(July 2022)
Flow Chart of Milestone Procedure
Employer's Representative
notices the Contractor
Milestone not achieved
The month which Milestone
Objective is scheduled to be
achieved
Payments of Cost Centre
related to non-achieved
Milestone shall be
suspended
CC 84(4)a
Resumption of payment by
the Milestone Objective is
achieved
CC 84(4)b
IPS shall be revised by the
Employer's Representative
and review next Milestones
CC 84(4)c
Yes
Employer's Representative
issues the Contractor
Milestone Certificate
Upon revised WP,
Employer's Representative
shall review IPS, Milestone
Objective and Dates
CC 84(5)
Contractor apply for
payment
Contractor shall assist and
provide info to the
Employer's Representative
CC 84(6)
Contractor Submit
Milestone Achievement
Employer's Representative
reviews Milestone Objective
Is Milestone
Objective
achieved ?
CC 84(8)
CC 85
CC 84(8)
No
• Ref: Contract Document Volume 8: Pricing Document
Milestone Number 1.1
Milestone Number 1.3
PMCSC2/C4/UN/L-2022-0044 Date July 4, 2022
แจ ้งเรือ
่ ง Non Achievement of Milestone ตาม CONDITIONS
OF CONTRACT Clause 84 (8)
แจ ้งให ้ผู ้รับจ ้างดาเนินการ ตาม CONDITIONS OF CONTRACT
Clause 84 (4)
UN/PMCSC2/PLC4/036/09/O65/072504 Date July 25, 2022
•
ผู ้รับจ ้างแจ ้งขอ Reconsideration of
Milestone No. CC1-1.3 for “Professional
Insurance shall be submitted within 2
months”
PMCSC2/C4/UN/L-2022-0085 dated July 29, 2022
ปรึกษาได ้ตอบจดหมายให ้ผรจ.
ดาเนินการสง่ Detail Work Program
ตามCONDITIONS OF CONTRACT Clause
16 (1) และดาเนินการปรับIPS/Milestone
ตาม CONDITIONS OF CONTRACT Clause
84 (5) &(6)
• CONDITIONS OF CONTRACT Clause 84 (5)
• CONDITIONS OF CONTRACT Clause 84 (6)