Flow Chart (July 2022) Flow Chart of Milestone Procedure Employer's Representative notices the Contractor Milestone not achieved The month which Milestone Objective is scheduled to be achieved Payments of Cost Centre related to non-achieved Milestone shall be suspended CC 84(4)a Resumption of payment by the Milestone Objective is achieved CC 84(4)b IPS shall be revised by the Employer's Representative and review next Milestones CC 84(4)c Yes Employer's Representative issues the Contractor Milestone Certificate Upon revised WP, Employer's Representative shall review IPS, Milestone Objective and Dates CC 84(5) Contractor apply for payment Contractor shall assist and provide info to the Employer's Representative CC 84(6) Contractor Submit Milestone Achievement Employer's Representative reviews Milestone Objective Is Milestone Objective achieved ? CC 84(8) CC 85 CC 84(8) No • Ref: Contract Document Volume 8: Pricing Document Milestone Number 1.1 Milestone Number 1.3 PMCSC2/C4/UN/L-2022-0044 Date July 4, 2022 แจ ้งเรือ ่ ง Non Achievement of Milestone ตาม CONDITIONS OF CONTRACT Clause 84 (8) แจ ้งให ้ผู ้รับจ ้างดาเนินการ ตาม CONDITIONS OF CONTRACT Clause 84 (4) UN/PMCSC2/PLC4/036/09/O65/072504 Date July 25, 2022 • ผู ้รับจ ้างแจ ้งขอ Reconsideration of Milestone No. CC1-1.3 for “Professional Insurance shall be submitted within 2 months” PMCSC2/C4/UN/L-2022-0085 dated July 29, 2022 ปรึกษาได ้ตอบจดหมายให ้ผรจ. ดาเนินการสง่ Detail Work Program ตามCONDITIONS OF CONTRACT Clause 16 (1) และดาเนินการปรับIPS/Milestone ตาม CONDITIONS OF CONTRACT Clause 84 (5) &(6) • CONDITIONS OF CONTRACT Clause 84 (5) • CONDITIONS OF CONTRACT Clause 84 (6)