Scope of Works for Topographic Survey Introduction In order to fulfill the requirement of the client for Samanea Mixed Development PH-2 Project at Tangerang New Industry City, Cikupa, Tangerang, Indonesia,the topographic survey for area approximately 9.92 HA,are required primarily to assess the information on existing boundary markers, encroachment public road, objects, fence boundaries, electric poles, other utilities and topographic site conditions. The work will be supervised by qualified surveyor/engineer experienced in the type of work to be carried out. The program comprises the following tasks: Survey Work a. Set the vertical points with reference by GNSS Static survey method from according to government control point. b. The accuracy of horizontal distance shall be better than 3rd order class 1 (1:10,000) and the allowable error of elevation shall not exceed 12√K (km) in unit of mm. c. Determine site boundary with co-ordinates pointed out by the client representative. d. Determine spot levels across the project area at about 30 m spacing or as appropriate. e. Determine the ground levels at least 10 m outside boundary perimeter. f. Locate all existing buildings, objects and facilities in the area and at least 10 m outside site boundary perimeter including roads, junctions with names, nearby building boundary, drainages with invert level (both temporary and permanent), electricity and telephone poles. g. Locate trees positions, shrubs and types with diameter greater than 0.20 m. Report and Drawings Two copies of report will be submitted together with a soft copy in File.dwg format. The following information will be included: a. Introduction and description of works undertaken. b. Calculation of traverse and leveling in tabular forms. c. 2 copies of Plan Drawings on UTM grid showing all horizontal coordinates and level with appropriate scale on A1 paper and soft file in AUTOCAD R2000 format. Timing The survey team will be mobilized within 5 days after receiving the work order. All works including a final report and drawing will be completed in approximately 20 days after mobilization. SPECIFICATION FOR TOPOGRAPHICAL SURVEY WORKS 1- Bounda「y surveyed as actually demarcated by fences, walls, poles, boundary markers if any o「 as pointed out at site by the client o「 his 「 epresentatives. 2- Detail topographic survey includes: location of boundary, wall, klong wall fence, existing building, elect「icity and telephone pole,「 oad, footpath, ditch, canal, drainage, man hole, boulder, rock outcrop, t「ee with diamete「 bigge「 than 15 cm and any otherfeatu 「 es natl」「 al o「 man made ones. 3- Accuracy of traverse: 4 Spot level interval: 5- North: 口 1 : 5,000 口 Sm 口 曰1 : 10,000 口 10 m 口20 m 口1 : 20,000 因30 m and at change in the groun slope 囚 UTM 口 口 Project No巾 Magnetic 口 UTM dete「mined with Hand Held GPS 6- 7- 8- Coordinates: 囚UTM 口Other 口 P「oject datum 口 Assumed 口 UTM dete「mined with Hand Held GPS Elevation: 曰MSL 口 Assumed 口 MSL determined with Hand Held GPS 1:200 口 1:500 曰1:1,000 口 1m 口2m Contour lines interval: 口 0.5 m 曰none 10- P「oject datum Drawing with AutoCAD to scale: 口 9- 口 Deliverables: Drawing: 囚One 1 ( ) original on 「eproducible media 曰Two (2) pape「 copies ζAD file: D One (1) set on CD 口1:2,000 口 Sm