Uploaded by reinard.dt

Steam-Blowing-CheckSheet

advertisement
Appendix 1
CHECK LIST
STEAM BLOWING ACTIVITY
SYSTEM CODE:
SUB-SYSTEM:
DATE:
TIME :
No.
____/____/____
____:____
DESCRIPTION
CHECK
YES NO N.A.
SAFETY
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
Dedicated work permit obtained.
System under steam blowing is marked on P&ID.
System under steam blowing is inspected; ensure piping insulation is
as complete as possible before introducing steam.
System under steam blowing is properly supported.
At the steam blowing point the area involved is barricaded off.
Tool box meeting is done.
Piping insulation is complete
Monitoring of steam blowing is arranged.
Around the barricaded area the following signs are posted:
“STEAM BLOWING IN PROGRESS”
“USE EAR PROTECTION”
“NO ENTRY”
A warning bell whistles, or sirens are ready to be sounded.
All personnel not involved in the steam blowing must leave the
restricted area.
A HSE Officer is present on the area.
All involved personnel must wear PPE (ear protection)
Special PPE (___________________________________) are worn.
At the discharge point a barrier is installed.
All roads involved in the activity are closed.
GENERAL
Pipe circuit clearly identified
Blow out pipe with temporary valve and steam silencer installed at all
outlet positions. Check that pipe has been proper installed and
supported to avoid any stress on the blown line
Steam inlets and outlets determined
Temporary bypasses, jumpers, and blind disks installed
Equipment intake and discharge disconnected to prevent entry of
cleaning medium
Orifice plates removed
in-line service strainers removed
bypass control valves and safety valves removed or blocked
instrument connections blanked and protected
Space between consecutive open flanges is more than 1/6 of pipe
diameter when blowing
spring supports and spring hangers are blocked out per manufacturer's

















































































28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
instructions
equipment near blowing outlets to be protected to prevent damage to
fragile devices such as pressure gauge glass
STEAM BLOWING OPERATION
Flush the system using steam condensate at a velocity of at least 3 m/s
(or at the highest velocity limited by MAOP) for a minimum two
hours, and drain rapidly under air pressure to remove as much mobile
debris as possible. If necessary, isolate sections of the system to
achieve this velocity.
Crack open inlet valve and start with warming up of line. Valve at the
end of header have to be open
Open all drain valves on the main header and branches to avoid pipe
hammering
When condensate is no longer visible at the drain points, open more
inlet valve and increase steam speed to remove loose foreign matter
and heat up metal quickly at a temperature as much as possible near
the operating one; then cut off steam flow and let pipe metal
temperature drop below 175° F. Again increase steam flow and
temperature and this procedure repeat a several times.
Install target plate at the end of header and again open valve to
continue with steam blowing several hours.
Close inlet valves and after cooling down of header remove silencer
with blow out pipe.
Reinstall spool and spectacle blind with new gasket and tight stud
bolts.
ACCEPTANCE CRITERIA
Process and utility pipes, steam color at the outlet point is sufficient
indication to indicate the completion of internal cleaning.
Special service (Process requirement or steam turbine supply) for
deep and accurate cleaning fix target plate(copper, aluminium,
stainless steel) at the steam blowing outlet point
Target plate highly polished and installed when the exhaust steam
appears clean
Verify plate is placed over fixed support perpendicular to pipe
Verify plate dimension to be 0.2 x 0.8 diameter
Verify plate is replaced after each blowing
Replaced plate shall be marked with number of flow
Verify number of marks do not increase during consecutive blowing
and in compliance with equipment manufacturer recommendations
Remark:
SUBCONTRACTOR SIGNATURE
PRE-COMMISSIONING SIGNATURE













































Download