GE Renewable Energy – Original – Technical Documentation Wind Turbine Generator Systems 3MW Platform - 50/60 Hz Installation Manual Applicable for Wind Turbine Generators from 2.5 MW to 3.8 MW imagination at work © 2017 General Electric Company. All rights reserved. GE Renewable Energy – Original – www.gepower.com Visit us at https://renewables.gepower.com All technical data is subject to change in line with ongoing technical development! Copyright and patent rights This document is to be treated confidentially. It may only be made accessible to authorized persons. It may only be made available to third parties with the expressed written consent of General Electric Company. All documents are copyrighted within the meaning of the Copyright Act. The transmission and reproduction of the documents, also in extracts, as well as the exploitation and communication of the contents are not allowed without express written consent. Contraventions are liable to prosecution and compensation for damage. We reserve all rights for the exercise of commercial patent rights. 2017 General Electric Company. All rights reserved. GE and are trademarks and service marks of General Electric Company. Other company or product names mentioned in this document may be trademarks or registered trademarks of their respective companies. imagination at work Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual Table of Contents 1 2 3 4 5 6 7 8 Introduction ..................................................................................................................................................................................................... 7 1.1 Prerequisites for the Installation.................................................................................................................................................. 9 1.2 Confidentiality .................................................................................................................................................................................... 10 1.3 Installer's Responsibilities ............................................................................................................................................................ 11 Tooling requirements! .............................................................................................................................................................................. 13 1.4 GE Energy Responsibility .............................................................................................................................................................. 14 1.5 Acronyms and Definitions............................................................................................................................................................ 14 Reference Documentation .................................................................................................................................................................... 15 2.1 Technical Reference Documents ............................................................................................................................................. 15 2.2 Work Instructions ............................................................................................................................................................................. 16 2.3 Checklists ............................................................................................................................................................................................. 17 2.4 Drawings – Turbine Components............................................................................................................................................. 19 2.5 Drawings - Tooling .......................................................................................................................................................................... 20 Tools, Parts Shipped as Loose Kits ..................................................................................................................................................... 21 3.1 Tools ....................................................................................................................................................................................................... 21 3.2 Parts Shipped as Loose Kits ........................................................................................................................................................ 21 Safety ............................................................................................................................................................................................................... 22 4.1 Operations Involving the Use of a Crane.............................................................................................................................. 32 4.2 Qualification and Orientation of the Installation Personnel ........................................................................................ 32 4.3 Safety Equipment............................................................................................................................................................................. 33 4.4 Personal Protective Equipment (PPE)...................................................................................................................................... 33 4.4.1 Safety Harness ............................................................................................................................................................................. 34 4.4.2 Protective Equipment for Measurements on Live Components .......................................................................... 35 Preparatory Work....................................................................................................................................................................................... 37 Foundation .................................................................................................................................................................................................... 38 6.1 Tower Base Ring ............................................................................................................................................................................... 38 6.1.1 Drawings ......................................................................................................................................................................................... 38 6.2 Identifying the Tower Base Ring ............................................................................................................................................... 39 Tower Base Ring (75 m and 85 m)...................................................................................................................................................... 39 Tower Base Ring (98.3 m) ....................................................................................................................................................................... 39 Tower Base Ring (110 m and 120 m) ................................................................................................................................................ 40 Tower Base Ring (131 m) ........................................................................................................................................................................ 40 6.2.1 Preparing the Foundation Anchor Bolts and Installing the Tower Base Ring ............................................... 41 6.2.2 Preparing the Tower Base Ring ............................................................................................................................................ 41 6.2.3 Verifying the Foundation is Level ........................................................................................................................................ 41 6.2.4 Installing the Tower Base Ring ............................................................................................................................................. 42 6.3 Preparing the Foundation ............................................................................................................................................................ 44 Pre-assembled Power Module (PPM) ................................................................................................................................................ 46 7.1 Safety Information for Installation of the PPM .................................................................................................................. 47 7.2 Overview of the Hooking Points ................................................................................................................................................ 49 7.3 Overview of the Installation Sequence .................................................................................................................................. 50 7.4 Assembling the PPM ....................................................................................................................................................................... 53 7.5 Installing the Fit Up Aid Tool (Transformer Alignment Brackets)............................................................................... 56 Tower................................................................................................................................................................................................................ 82 8.1 First Tower Section .......................................................................................................................................................................... 83 8.1.1 Inspecting the Tower Section................................................................................................................................................ 85 8.1.2 Preparing the Tower Section ................................................................................................................................................. 86 8.1.3 Example Attachment and Usage of the Lifting Gear ................................................................................................. 88 8.1.3.1 Plate Lifting Gear.................................................................................................................................................................... 88 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx x GE Renewable Energy – Original – Installation Manual 8.1.3.1.1 Attachment of Plate Lifting Gear ............................................................................................................................... 88 8.1.3.1.2 Lifting the Tower Section from the Low-loading Trailer................................................................................. 90 8.1.3.2 HTS ACTEK WKA System ..................................................................................................................................................... 94 8.1.3.2.1 Attachment of HTS ACTEK WKA System ................................................................................................................ 94 8.1.3.2.2 Lifting the Tower Section from the Low-loading Trailer................................................................................. 96 8.1.4 Assembling the First Tower Section ................................................................................................................................ 100 8.1.4.1 Installing the Guide Rail System................................................................................................................................... 101 8.1.4.1.1 Assembling the Rail Assembly ................................................................................................................................. 104 8.1.4.1.2 Installing the Controller Level Guide Rail System ........................................................................................... 106 8.1.4.1.3 Installing the Transformer Level Rail Assembly .............................................................................................. 110 8.1.4.2 Installing the Base Section over the PPM ................................................................................................................ 115 8.2 Installing the Entrance Stairway ............................................................................................................................................ 125 8.3 Adjusting the Entrance Door ................................................................................................................................................... 129 8.4 Completing the PPM Assembly ............................................................................................................................................... 130 9 Assembling the Following Tower Sections .................................................................................................................................. 140 9.1.1 Inspecting the Tower Section ............................................................................................................................................. 143 9.1.2 Preparing the Tower Section .............................................................................................................................................. 144 9.1.3 Attachment and Usage of the Lifting Gear ................................................................................................................. 146 9.1.4 Installing the Tower Section ................................................................................................................................................ 147 9.2 Corrosion Protection .................................................................................................................................................................... 155 9.3 Checking/Adjusting the Railing Doors................................................................................................................................. 155 10 Nacelle ..................................................................................................................................................................................................... 156 10.1 Inspecting the Nacelle ................................................................................................................................................................ 162 10.2 Preparing the Nacelle.................................................................................................................................................................. 162 10.3 Lifting the Nacelle ......................................................................................................................................................................... 175 10.3.1 Lifting Gear for the Nacelle ............................................................................................................................................ 175 10.3.2 Attachment of the Lifting Gear..................................................................................................................................... 175 10.4 Assembling the Nacelle .............................................................................................................................................................. 183 11 Hub ............................................................................................................................................................................................................ 188 Typical Hub Configurations ..................................................................................................................................................................... 188 11.1 Inspecting the Hub ....................................................................................................................................................................... 189 11.2 Lifting the Hub ................................................................................................................................................................................ 190 11.2.1 Attaching the Lifting Gear ............................................................................................................................................... 192 12 Rotor Blades.......................................................................................................................................................................................... 196 12.1 Inspecting the Rotor Blades ..................................................................................................................................................... 196 12.2 Offloading the Rotor Blades ..................................................................................................................................................... 197 12.3 Preparing the Blades ................................................................................................................................................................... 205 12.4 Blade Handling ............................................................................................................................................................................... 209 12.4.1 Example: Double Crane Lift ............................................................................................................................................ 213 12.4.2 Example: Single Crane Lift .............................................................................................................................................. 214 13 Rotor ......................................................................................................................................................................................................... 217 13.1 Preparing the Rotor ...................................................................................................................................................................... 217 13.1.1 GE Pitch Control System (MSS Hub Pitch System) ............................................................................................... 219 13.1.2 GE Pitch Control System (For Turbines with PTB Hub Pitch System) .......................................................... 227 13.2 Attachment of the Blades ......................................................................................................................................................... 236 13.3 Assembling the Rotor .................................................................................................................................................................. 238 13.4 Assembling the Nose Cone and Final Rotor Assembly Work................................................................................... 248 13.5 Final Rotor Assembly Work ...................................................................................................................................................... 252 13.6 Lifting the Rotor.............................................................................................................................................................................. 256 13.6.1 Example Lifting Gear - Lifting Tool for 100 m and 103 m Rotor Diameter.............................................. 256 Typical Hub Configurations ................................................................................................................................................................ 256 13.6.2 Attaching the Rotor Lifting Gear .................................................................................................................................. 259 13.7 Installing the Rotor (Hub with Blades) ................................................................................................................................. 260 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. x Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual Blades with serrations: ......................................................................................................................................................................... 263 Blades with serrations: ......................................................................................................................................................................... 269 14 Checks ..................................................................................................................................................................................................... 283 15 Cables ...................................................................................................................................................................................................... 287 15.1 Slip Ring Wires ................................................................................................................................................................................ 288 15.2 Lowering the Power, Control & Communication Cables ............................................................................................ 297 15.3 Lowering the Generator, Rotor, Stator & Ground Cables .......................................................................................... 313 15.3.1 Arranging the Cables at the Transition between the Cable Saddle and the Tower Cable Tray ... 327 Plastic Cable Ties ..................................................................................................................................................................................... 328 15.3.1.1 Arranging the Cables at the Transition between the Cable Saddle and the Tower Cable Tray “OLD” TPH Structure for 98.3mHH .................................................................................................................................................. 329 15.3.1.2 Arranging the Cables at the Transition between the Cable Saddle and the Tower Cable Tray “NEW” BoM Structure for 110mHH ................................................................................................................................................. 330 15.4 Installing the Cable for the Cable Untwisting Switch .................................................................................................. 331 15.5 Splicing the Stator, Generator and Ground Cables ...................................................................................................... 332 General Overview of the Cable Arrangement at Each Level Prior to Installation .................................................... 333 Overview of the Final Cable Arrangement at Each Level .................................................................................................... 334 16 Signs and Labeling to be Attached to the Wind Turbine Generator System by the Operator/Owner ..... 344 17 Installation of the Ladder and Fall Protection System ..................................................................................................... 344 18 Connections .......................................................................................................................................................................................... 345 18.1 Electrical Connections at PPM ................................................................................................................................................ 346 18.1.1 PAS00 Grounds: ................................................................................................................................................................... 346 18.2 Electrical Connections and Testing Requirements ....................................................................................................... 353 Field Tests ................................................................................................................................................................................................... 353 18.3 Medium Voltage Cables between the Grid and MVSG (Grid and Next Turbine).............................................. 356 18.4 Connection of the HV Cables between MVSG and the Transformer.................................................................... 360 18.5 690 V Transformer to Converter CAE Cabinet................................................................................................................. 368 18.6 6kV Cables between the Transformer and SSC Cabinet ............................................................................................ 372 18.6.1 6kV Cables between the Transformer and SSC Cabinet Schneider Configuration............................. 373 18.6.2 6kV Cables between the Transformer and SSC Cabinet LimitAmp Configuration .............................. 377 Opening De Energized SSC cabinet during installation ........................................................................................................ 378 18.7 690 V Converter CAE Cabinet to AUX Transformer ...................................................................................................... 389 18.8 400 V LVDP to AUX Transformer ............................................................................................................................................ 392 18.9 Control/Communication between MCC/SSC and the Converter CCC Cabinet ............................................... 395 18.10 Control/Communication AUX Cables between MCC/SSC and the Transformer Junction Box. TransformerLevel ......................................................................................................................................................................................... 399 18.10.1 PT – 100 Cable and Tower Door Exhaust Fan .................................................................................................. 403 18.11 Connect the 400 V Auxiliary Cables (Top Box) to LVDP ............................................................................................... 404 18.12 Connect the Power Cables (690 V) from the Generator to Converter Cabinet................................................ 406 18.13 Connecting the 6 kV Generator Stator Cables to the Stator Switch Cabinet SSC ......................................... 411 18.13.1 Connecting the 6 kV Generator Stator Cables to the Stator Switch Cabinet SSC LimitAmp Cabinet ................................................................................................................................................................................................ 419 18.13.1.1 Routing and Terminating Cables to the Bus Bars .......................................................................................... 421 18.13.2 Critical to Quality Testing and Inspections ........................................................................................................ 423 Generator .................................................................................................................................................................................................... 423 Converter – 400 V.................................................................................................................................................................................... 423 Converter – 690 V.................................................................................................................................................................................... 423 Generator to (SSC) – 6 kV ..................................................................................................................................................................... 424 Transformer to (SSC) – 6 kV ................................................................................................................................................................ 424 Prior to Closing Cabinet Panels or Completion of Work. ...................................................................................................... 424 18.14 Installing the Floodlighting ....................................................................................................................................................... 425 19 Ground Resistance Test .................................................................................................................................................................. 425 20 Verify the Gearbox and Generator Alignment ..................................................................................................................... 426 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx x GE Renewable Energy – Original – Installation Manual 21 Remaining Work ................................................................................................................................................................................. 427 21.1 Mechanical Completion ............................................................................................................................................................. 427 22 Transport Fixtures .............................................................................................................................................................................. 428 22.1 Downtower Equipment (PPM) .................................................................................................................................................. 428 22.2 Tower .................................................................................................................................................................................................. 428 22.3 Nacelle ................................................................................................................................................................................................ 428 22.4 Hub ....................................................................................................................................................................................................... 428 22.5 Nose Cone......................................................................................................................................................................................... 428 22.6 Blades ................................................................................................................................................................................................. 428 22.7 Special Tool Return ....................................................................................................................................................................... 428 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. x Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 1 Introduction This Installation Manual describes the basic procedures for the assembly of 3MW Platform Wind Turbine Generator Systems with 100 m, 103 m, 120 m, 130 m and 137 m rotor hub heights from 70 m to 131 m and a rated power of 2.5-3.8 MW. These instructions apply to the steel tubular tower, nacelle, and rotor blades. The installation requirements and instructions must be followed precisely in order to avoid damage and to guarantee a problem-free and exact installation. It is the owner’s/installer’s responsibility to meet all safety, local and general regulations that apply for the specific site, task or project during installation. It will enable the constructor to safely erect a Wind Turbine Generator System (WTGS) in accordance with the specifications of the manufacturer. The following components are considered in this document: Tower base ring Pre-assembled Power Module (PPM) Rotor Assembly and Installation Considerations 120 m diameter and smaller can be installed as a completely assembled rotor. Rotors with a 2900 hub must be installed utilizing Single Blade Method SBI. SBI method requires the following electrical and mechanical preparations before beginning rotor assembly. Parties responsible for performing this work will review and understand the procedures before beginning the work. The following is a list of activities that will be covered under separate reference documentation. Contact GE representative for a copy of the latest revisions. Install the unbalanced rotor turning gear before the nacelle leaves the ground. Receive and assemble SBI tool and partial disassembly is required to relocate to next pad. All power and communication cables must be lowered and secured to PPM but not terminated Identify power source to the top box to enable the Yaw and Gearbox oil pump systems. Connect appropriate size and Voltage portable generator to the temporary wiring to the top box. Follow the Temporary Yaw procedure to correctly orient machine head to perform SBI. Energize gearbox oil pump for a minimum of 5 min. to before activating turning gear, leave oil pump running while the turning gear is engaged. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 7/428 GE Renewable Energy Installation Manual – Original – Install the Hub (2900 Hubs have double row bolt pattern on the main-shaft connection). Using turning gear orient the hub to the first position to install the blades and apply Rotor Lock/LOTO. Connect SBI tool and taglines to the blades and install onto the hub. Verify all blade to pitch bearing torqueing is complete. De-energize and remove all SBI related temporary equipment (Mechanical and Electrical). Hybrid Tower The Hybrid Tower consists of a concrete section with steel tube tower sections on top. This manual does not cover Hybrid Tower Installation. Refer to the Hybrid Tower Installation Manual. DTO (Design to Order) Refers to non-standard equipment in the scope supply that is not part of the standard design, and so is not addressed in this installation manual. DTO equipment may be required to meet local codes and standards or customer specific requirements. In cases where this equipment must be installed in the field, work instructions will be made available by GE via project specific addendum to the installation manual. Contact GE Project representative. This Installation Manual is designed to provide the owner/installer with information on how to install the Wind Turbine Generator (WTGS) in a safe manner in accordance with the manufacturers’ specifications, and is subject to revision by GE Energy. The installation instructions include important warnings, cautions, and notes about installing the wind turbine. These instructions do not cover components not provided by GE Energy. The wind turbine generators are built in accordance with technical standards and the established safety rules. Nevertheless, dangerous risks can arise for individuals, equipment can be impaired, and materials damaged, if the converter and other devices are operated: By personnel who are not trained and properly instructed and/or Outside of guidelines prescribed by the company. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 8/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 1.1 Prerequisites for the Installation Road/Crane/Rigging Installer is required to design and procure all rigging and lifting devices, provide equipment offloading/staging plan, provide a project specific lift plan(s). Ensure rigging and lifting design is safe and does not damage GE `s equipment/subcomponents when it is attached to the lifting points or any part of the General Electric equipment. The sail area and drag coefficient of the rotor must be incorporated through the lift plan. Static loads and dynamic loads must be verified by the crane operator The work zone must be clearly identified and personnel not involved in crane lift operations must leave the crane work zone (danger zone) before lift operations starts. Figure 1: WTGS Crane Work Zone (Danger Zone) CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 9/428 GE Renewable Energy – Original – Installation Manual An extensive analysis to determine the prerequisites for the installation (e.g. weather conditions, land requirement or sufficient curing of the foundation) has to be carried out before the turbine is erected. The roads and pads must meet the requirements of the Typical Road, Crane Pad & Turbine assembly area specification. Offloading staging activities plan must include site survey and knowing the general characteristics of the roads and condition of the soil for equipment safe/unrestricted travel, offload, staging and Installation. Staging plan must include Safety and Equipment damage preventive measures including but not limited to resetting equipment to prevent damage due to poor cribbing/matting configuration, soft ground due to potential freeze thaw cycles, rain, melting ice or flood zone, potential damage due to extreme weather conditions such as high winds. Proper cribbing/matting and tie off arrangement shall be factored in, and must be sufficient and properly rated to support weight of the components. GE Energy will provide typical weights, dimensions and center of gravity for lifting GE-provided components only. Refer to the Transportation Description, weights and dimensions (see section 2) for exact descriptions and the dimensions of all the turbine components which are to be mounted, and the data required for the assembly, such as weights, fixing points, etc. Modifying the GE equipment lifting points is strictly prohibited. 1.2 Confidentiality This document is to be treated confidentially. It may only be made accessible to authorized persons. It may only be made available to third parties with the expressed written consent of GE Company. All documents are copyrighted within the meaning of the Copyright Act. The transmission and reproduction of the documents, also in extracts, as well as the exploitation and communication of the contents are not allowed without express written consent. Contraventions are liable to prosecution and compensation for damage. We reserve all rights for the exercise of commercial patent rights. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 10/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 1.3 Installer's Responsibilities The role of the constructor is defined depending on the contract conditions: Installation in GE's scope The Installer is a General Electric employee or a GE subcontractor. Installation in customer scope The installer is a non-General Electric employee. GE's representative is the single point of contact for the installer and responsible for the technical advisory at the installation site. For both cases this installation manual defines the installer’s responsibilities. The Installer must ensure that the erecting engineers are familiar with this Installation Manual. The Installer is responsible for the safety of the personnel and must inform the personnel about the existing legal requirements and accident prevention regulations and ensure that they are complied with. Furthermore, the country-specific safety and environmental regulations must be complied with. The installation personnel may not alter the control and protective system of the WTGS, add or omit anything without the written authorization of GE Energy. The installation teams must have been trained and oriented in the correct installation of a WTGS. The training records have to be made available on GE request. Personnel performing Electrical Work are required to request training for operating, assembling and testing of the SSC and MVSG cabinet 30 days before performing this work. General Tool Calibration and Testing NOTE Tool calibration The Installer has to ensure that the tools used are calibrated and that the respective calibration/inspection data sheets are available to GE Energy on request. All measuring and test equipment must have a certificate of calibration and visibly labeled. A third party verification of calibration certificate is also required on any new or used tooling that measures pressure, force or resistance, e.g. dial indicators, torque wrenches electrical, mechanical and hydraulic, laser alignment tools, multimeters, electrical validation testing equipment and electrical crimping tooling. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 11/428 GE Renewable Energy – Original – Installation Manual NOTE Daily Tool Log! CRITICAL TO QUALITY! Failure to perform inspections prior to each shift can allow damaged or substandard tooling to be utilized by employees. The Installer assumes responsibility for any re-work associated with damaged or sub-standard tooling found to be the root cause of improper installation per GE specifications. A verification of all 3rd party calibrations certificates is required and a copy will be kept in the site job books on any new or used tooling that measures pressure, force, distance or resistance. A log of daily checks performed shall be documented and may be mandated by the regional Installation Manager. The original logs shall be available to GE upon request and the originals will be added to the site job books if deemed necessary. NOTE Over torque using impact wrenches! Over torque leads to bolt failure. CRITICAL TO QUALITY! When using impact wrenches do not exceed the torque values that are specified for the bolt being tightened. Final torque must be applied using a calibrated torque wrench! NOTE CRITICAL TO QUALITY! Submit an RFI to GE for a list of the latest approved torque tooling for level 1 component connections e.g., Tower flanges, Rotor assembly and installation. The following is the minimum daily check information that must be recorded in the installer provided form: 3rd party date of tool being tested Date check performed Operator performing check Tool ID (serial #) CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 12/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual Check value, 3 tests recorded with AvgEquipment used to check (MFG./Model/Serial Number) torque wrenches electrical, mechanical and hydraulic, Pressure gauges, crimp heads, force gauges for hydraulic crimping. Hydraulic tooling must be tested as an entire functional unit. Tooling requirements! 1. Certificate of calibration from the manufacturer 2. Send new tool to third party for calibration verification. If tool requires re-calibration, 3. Send in to get calibrated and issue new certificate of calibration. 4. Send to 3rd party for new verification certificate. As long as the tool remains in calibration only the verification certificate has to be renewed each year. All measuring and test equipment must have Identification traceable to a certificate of calibration. All tool calibration verification services shall be subcontracted. Examples of calibration requirements are, but not limited to: Pressure gauges Torque wrenches - electrical, mechanical and hydraulic Norbar or equivalent test equipment Skidmore or equivalent test equipment Electric screw driver Multimeters Laser alignment equipment Electrical validation equipment Micrometer and digital and/or dial calipers Consult with GE site representative for any tool used that is not listed as to if 3rd party calibration is required. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 13/428 GE Renewable Energy Installation Manual – Original – 1.4 GE Energy Responsibility GE Energy’s responsibilities are to provide the owner/installer with comprehensive documentation to install a wind turbine generator. General Electric provides all turbine components, ship loose kits, special tooling, and technical advisors where applicable. GE Energy reserves the right to withdraw its employees from unsafe site/work areas. The installation manual is important for the safe installation of the turbine. The site constructor must ensure the installation crews are familiar and comply with these instructions. Furthermore, adherence to local, state, and country regulations regarding safety, environmental protection, electrical codes and related fields is required. Construction personnel are not allowed to change, add or modify the control and protection system of the turbine without written authorization of a designated GE Energy representative, prior to change or modification. Construction crews must be trained and instructed in the proper installation of the turbine. 1.5 Acronyms and Definitions Acronym Definition CICL Cable Installation Check List DFIG Directly Fed Induction Generator DTO Design to Order (Refers to non-standard equipment orders that is required to meet local standards/regulations that is not part of the original design ICL Installation Check List IIP Installation Inspection Procedure LVDP Low Voltage Distribution Panel MCC Main Controller Cabinet in PPM, communicates with top box Nm Newtonmeter PPM Pre-assembled Power Module SSC Stator Switch Cabinet UPS Uninterruptible Power Supply WTGS Wind Turbine Generator System LVDP Low Voltage Distribution Panel Table 1: Acronyms and Definitions CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 14/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – 2 Reference Documentation 2.1 Technical Reference Documents Content Document Name Basic Information Operating_Manual_3MW-xxHz_Basic Technical Data Technical_Description_3MW-xxHz_DFIG Safety Manual Operating_Manual_3MW_xxHz_Safety Operating Manual Operating_Manual_3MW_xxHz_Operating Transport Manual Transport_Documents_3MW-DFIG-xxHz Manual for the Handterminal Operating_Manual_Generic_xxHz_mContrUnit_exo rPalm Maintenance Manual Operating_Manual_3MW-xxHz_Maintenance Idling Manual Idling_Manual_3MW-DFIG-xxHz Road & Crane Pad Specification Site_Roads_Crane_Spec_3MW-DFIG120_130_137-xxHz_EMEA Site_Roads_Crane_Spec_3MW-DFIG-100_103xxHz_RoadCrane_EMEA Specification Handling and Lifting (Drag Coefficient Sail Area) Component_SailArea_DragCoef_Generic-xxHz Wind Speed Limitations for Assembly and Maintenance Contact Engineering for the latest Wind Speed Limitations. Customer Information for the Anchor Bolt System General_Description_3MW50Hz_foundation_anchorAdapt Weights and Dimensions Weights_and_Dimensions_3MW_xxHz Requirements for the Tower to Foundation Interface Refer to contract technical foundation documents. WebHMI-Remote Application Operating_Manual_Generic_xxHz_ControllerHMI_ MarkVle Storage Manual Storage_Manual_3MW-DFIG-xxHz Table 2: Technical reference documents CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 15/428 GE Renewable Energy Installation Manual – Original – 2.2 Work Instructions Work Instruction Document Name Technical Specification Wind Turbines Tower Internals Bolting and Torqueing 103W2364 Bolt Torque Specification Bolt_Torque_Specification_3MW_xxHz Generator Installation Engineering to provide Flex Coupler Installation 2.X_Machine Head_Exchange of the coupling for Gen 0 Turbines Gearbox Alignment 2.x_WDI_gearbox_alignment Generator Alignment 2.x_WDI_generator_aligning Gearbox Installed on the Ground 2.x_xxHz_WDI_gearbox_Install Connection of Power Cables GEWE.all_WDI_cable_crimping Insulation Integrity Test 104W2311 Lightning Arrester Resistance, CE Measurement (optional) 2.5-100_xxHz_WDI_allComp_TestEN60204 (if applicable) Transformer Operating and Test Manual Vendor specific Switchgear Operating and Test Manual Vendor specific Stator Synch Switch Operating and Test Manual Vendor specific WDI Single Blade Installation Request latest version from GE engineering. Table 3: Work instructions CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 16/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 2.3 Checklists The Installer is responsible for the daily maintenance of the following turbine specific documents (request the latest version from GE's representative). All completed pre-condition checklists section 5 IIP must be submitted to GE prior to Installation Inspection. Checklist Document Installation Check List Installation_Checklists_3MW-DFIG-xxHz_ICL Torque Report Installation_Checklists_3MW-DFIG-xxHz_BoltTorque Generator Alignment Report Contact Engineering for the latest generator alignment form. Gearbox Alignment Report Contact Engineering for the latest gearbox alignment form. Cable Installation Checklist Installation_Checklists_3MW-DFIG-xxHz_CICL Grid Checklist Installation_Checklists_3MW-DFIG-xxHz_Grid Energization Process Flow Chart 3.x Equipment only Energization Process Flow Chart Haca Safety Rail Inspection Protocol HACA rail check list (if applicable) or alternatively depending on the configuration of the WTGS Tuf-Tug Fall Arrest System Inspection Protocol Tuf-Tug Cable Safe Climb System inspection checklist Installation Inspection Protocol Installation_Checklists_3MW-DFIG-xxHz_IIP Receiving Inspection Forms Receiving_Inspection_Checklists_3MW-DFIG-xxHz_XXX all receiving forms Table 4: Checklists NOTE If equipment will be delivered to a lay down area for long-term storage refer to Technical Guidelines for Storage of Wind Turbine Generator Systems. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 17/428 GE Renewable Energy Installation Manual – Original – NOTE Receiving Inspections: GE provides a copy of the Receiving Checklists on EX works projects only. If the GE receiving inspector is not on site, GE provides a copy of the Receiving Checklists to the customer to perform the equipment receiving inspection. Contact the GE representative for the latest revisions. The customer will provide to GE the copies of the completed inspection checklist prior to start of the installation activities. NOTE If equipment for two different projects is shipped to the same long term storage area, the customer is responsible for maintaining equipment assignment for the project it was intended for to insure the correct configuration is delivered to the correct location. If the customer decides to relocate any major component after the component has been delivered to a pad, ensure the new pad location is communicated to the GE site representative for configuration management purposes. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 18/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – 2.4 Drawings – Turbine Components Drawing numbers for project may change depending on configuration. GE project team to provide all applicable documents. Drawing no. Content Comment 117W6882 3-level PPM assembly, corresponding BoM PPM assembly 117W6871 Transformer platform (section 1) PPM assembly 117W6997 Controller platform (section 2) PPM assembly 117W6892 Converter platform (section 3) PPM assembly 117W6917 Assembly drawing ladder DTE PPM assembly 114W8755 Assembly drawing converter PPM assembly 105T5350 Fan and Plenum Assembly Instructions PPM assembly 117W5906 Assembly ventilator PPM assembly Engineering to provide Tower section lift and handling Per hub height and tower design 114W5453 Left side panel assembly 2.5-2.75 (PMG + BTP Nacelle) Generator installation 114W5454 Right side panel assembly 2.5-2.75 (PMG + BTP Nacelle) Generator installation 117W6136 Machine head lift drawing 103W3327 Hub lift drawing 115W5268 Assembly hub steps/casting assembly Hub assembly 114W4337 2.5 hub assembly mechanical parts outside pages Hub assembly 103W2754 Blade support and lift drawing Per blade design Engineering to provide Rotor lift drawing Per rotor diameter and blade design 108W6416 Aviation lights, weather station mechanical assembly If applicable Engineering to provide Turbine electrical schematics and wiring diagram Project specific Table 5: Drawings – Turbine components CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 19/428 GE Renewable Energy Installation Manual – Original – 2.5 Drawings - Tooling Drawing no. Content Comment Engineering to provide Fit up aid tool drawing for turbines with 85 m and 98.3 m HH as applicable 114W8776 Brace right alignment tool DTE PPM Assembly 114W8775 Brace left alignment tool DTE assembly PPM Assembly GE-PPM-D6025-00 PPM rail system configuration detail PPM Assembly GE - PPM - DT7988-01 Upper rail PPM Assembly GE - PPM - DT7988-02 Lower rail PPM Assembly GE - PPM - DT7988-03 Tube bracket and joiner PPM Assembly GE - PPM - DT7988-04 Primary support short PPM Assembly GE - PPM - DT7988-15 Primary support medium PPM Assembly GE - PPM - DT7988-06 Primary support long PPM Assembly GE - PPM - DT7988-07 Pivot link arm PPM Assembly GE - PPM - DT7988-08 Latch arm PPM Assembly GE - PPM - DT7988-09 Latch arm assembly PPM Assembly GE - PPM - DT7988-10 PPM V5 main assembly PPM Assembly Table 6: Drawings – Turbine components CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 20/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 3 Tools, Parts Shipped as Loose Kits 3.1 Tools NOTE For current tool list contact GE representative. Installer is responsible for all tools and consumables. 3.2 Parts Shipped as Loose Kits There are three categories of loose kits. 1. Tower paint 2. Bulk items shipped for all units such as fragile products or small parts and items shipped as a kit for each turbine such as hoist or nacelle bolts are included in the erection accessories and PPM accessories which are delivered in a container. 3. Items shipped as a kit inside major components such as nuts and washers for rotor assembly, hub nuts and washers or lifting lugs for PPM (Pre-assembled Power Module). 4. Parts shipped late from General Electric or a vendor (MSD) to close shortage issues. NOTE Tower bolts are shipped in tower kits. Do not mix tower bolts; always maintain kit integrity (1 kit to 1 tower). Bolt information is recorded in ICL. All bolts nuts & washers used for any particular tower flange assembly must be from the same manufacturer. If kit number is missing contact GE for further instructions. NOTE Consult with GE representative for a sample-packaging list for all parts shipped loose kits parts as they may vary by pole and contractor may be required to stage these parts at the site inside components prior to installation. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 21/428 GE Renewable Energy Installation Manual – Original – NOTE Bulk shipments / Ship loose kit acceptance (Future PSL) Each package contains a packing slip attached to either the outside or inside of the container. The installer is responsible for verifying all bulk shipments / ship loose kits are received in full as they arrive on-site. Complete quality form WFFOFPSL-007 “Ship Loose Kit Acceptance Form” and provide it to the GE Energy representative within two working days. The installer will be responsible for supplying shortage items at their expense if not noted on form or the form is not provided to the GE Energy representative within two days of ship loose kits arriving on-site. The installer is responsible for maintaining custody and security of the PSL/MSD and all major components. NOTE The collection system to GE WTG interconnects hardware and foundation grounding hardware is supplied by the buyer. 4 Safety Parties (companies and individuals) performing this work are responsible for reviewing the scope of work and determining all training, safety measures, guidelines, and work practices that are necessary and for adhering to and enforcing them. Untied long hair, loose clothing (e.g. flapping coats, tops with wide sleeves or trousers with wide trouser legs) as well as scarves, ribbons, headscarves or jewelleryent for Measurements on Live Components may not be worn during the installation work! There is a fundamental danger of injury through being caught, pulled in or picked up by rotating components! Clothing must be adapted to the respective work and the weather conditions. DANGER Head injury risk! Since there is a high risk of head injury, hard hats must be worn on the work site at all times. Workers may trip or fall, or may bang their heads while working in confined spaces. Due to wind conditions and other risk factors, workers may encounter falling, flying or swinging objects. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 22/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual DANGER Risk of falling objects! Never remain in front or underneath the tower opening. Whilst the tower is being erected any object or material that remained in the tower or inadequately secured cable can fall out of the tower. The process requires lifting and lowering equipment inside the tower and working with, and staging, tools and materials on all tower platform levels. There are many gap openings around the platforms and possible open personnel and tool hatches Personnel will be working with small parts and tools which can fall through the holes or open hatches. Always ensure all equipment and tools are secured in closed tool bags. All tools will be secured and tether rope will be utilized as required Cover all hole openings that create a risk of falling objects as required. All tower internal tool/materials hoisting operations must be performed by properly trained personnel using the properly rated hoisting equipment, rated certified lifting bags, hooks with safety latch. Before use, take a moment to inspect all hoisting equipment and bag(s) to ensure there is no damage, cuts/tears, or signs of excessive rubbing/wear. Lifting equipment will be carefully coordinated. Two-way communication must be available via radio. All non-essential personnel must clear the area before hoisting operations begin. Never remain in front or underneath the tower opening. DANGER Uneven/Slippery surfaces! Uneven surfaces are present due to the shape of the WTG equipment. Slippery surfaces may be present during wet or icy conditions. Use caution when walking into any WTG surface that is not designed as permanent walkaway. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 23/428 GE Renewable Energy – Original – Installation Manual DANGER Foot injury risk! Steel or composite safety boots must be worn to reduce the risk of injury to feet, in particular from striking against and jamming between objects, from encountering falling or rolling objects, and from treading on or against pointed and sharp objects. DANGER Crushing hazard! During installation always ensure that hands, feet, and body are not between any potential pinch points. DANGER Hand crush, cuts and burns risk! Hands are exposed to mechanical dangers (cutting, grazing, pinching, and crushing), and to danger from heat and cold (from touching hot objects and convective heat). When protective gloves are prescribed or recommended, they must be worn. Use caution when working around exposed rotating components while the rotor is turning. DANGER Eye or facial injury risk! Eye protection must be used during all work activities, along with using a fullface shield if there is imminent risk of eye or facial injury (when grinding work is being performed). CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 24/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual CAUTION Wear hearing protection! Proper hearing protection must be worn when working with any electrical or hydraulic impact tooling! Always assess the next task at hand. If 85 decibels will be exceeded, hearing protection must be worn. Observe requirements for hearing protection per your company's policies. CAUTION Know what you are lifting! When the weight exceeds the limit for a single person, or if the load is awkward / difficult to maneuver due to shape or size. Request the help of a second person, Transfer the load into smaller containers or use the crane or a fork lift. Reference assembly drawings for weights. DANGER Falling hazard - Climbing tower ladder! Prior to installing the top section verify the fall arrest system (Top Double TBracket and Head assembly is installed according to vendor installation instructions. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 25/428 GE Renewable Energy Installation Manual – Original – DANGER Falling hazard! When crew persons must climb the tower prior to installation of the permanent safety cable system, personnel must be connected to a temporary fall restraint system to allow ascent to top of tower section. If an employee is working at a height that exposes them to a potential fall, fall arrest equipment must be used, and 100 % tie-off at all times. When climbing the tower, double lanyards (Y construction) are to be equipped along with the safety harness and ladder safety device (e.g., Ladsafe/Tuf Tug). The safety harness and the entire safety equipment must be checked before use. Damaged equipment must never be used. WARNING Climbing tower ladder! Tower ladder sections (aluminum) surpass the fixed ladder codes of OSHA and ANSI and are suitable for a 330-pound load (150 kg). When multiple persons are climbing different sections of the ladder separated by ladder supports to the tower shell, the ladder will support three climbers at one time. This only applies to towers provided by GE Energy. DANGER Climbing tower ladder! When climbing tower using the cable fall arrest system one person per tower section and a maximum of two people climbing the tower is allowed. Never free climb the tower ladder. Always use the ladder safety system. The ladder safety system is only rated for one climber per tower section, maximum of two people climbing the tower in different tower sections at any given time i.e., (While ascending or descending a ladder section, the ladder section to be climbed must be cleared of any climbers. If multiple climbers are ascending or descending, the tower hatches must be closed before the next climber begins to climb the cleared ladder section. If multiple climbers are climbing to the same section, climber to close the hatch and stand away from the ladder. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 26/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual DANGER Risk from lifting heavy loads! Prior to lifting all heavy loads, a pre-lift meeting with all parties involved is required (crane operator, rigger, supervisor, signalman, area safety, tag line holders and any other personnel involved). All lifting must be done in strict accordance with the installers lifting plan and applicable job safety analyses must be reviewed prior to commencing work. DANGER Risk from overhead suspended load! Never work under a suspended load. Make sure all people, vehicles, equipment and materials are clear of the crane tail and load swing. DANGER Risk of equipment damage and personnel safety! Aligning the WTG equipment bolt hole joints may be challenging due to possible high winds and site conditions. The process requires qualified and/or trained personnel as required: In the use of equipment/crane signals, Skills in the use of standard iron worker tools to aid in bolt hole joint alignment! Qualified to operate the GE brake and rotor lock system Understand the proper operation of taglines are required to aid aligning the bolt holes which allows the WTG to be installed safely. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 27/428 GE Renewable Energy Installation Manual – Original – CAUTION Blade handling! When handling blades on shipping fixture(s): Specific blade manufacturer’s handling instructions must be reviewed with the crews and understood prior to commencing work. Only use lifting points that are designated by blade manufacturer for lifting. DO NOT use tie down points that are not designed for LIFTING. Only use lifting points that are rated with enough capacity to lift the entire weight of the blade(s). If unsure, always consult with GE technical advisors and or GE engineering prior to handling individual blades and/or blades in shipping fixtures for proper lifting point identification according to the engineering design. CAUTION Blade and rotor damage prior to installation! Each site should assess the need for additional blade and assembled-rotor tiedown arrangement. Locations and instances which demonstrate high groundlevel winds warrant additional consideration which may include: Additional standard tie-downs and anchor points, further assessment of cribbing and dunnage and the potential for cribbing and dunnage to sink into the ground. WARNING If the tower is completely assembled, including the rotor and access to the rotor is required, park the rotor in a Y-position, such that one blade is pointed down, in line with the tower. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 28/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual DANGER Hydraulic disc brake and brake disc rotor lock use! The installer must personally ensure all personnel assigned to work activities inside the WTG are properly trained on the use of the hydraulic disk brake and disk rotor lock, to ensure the hydraulic disc brake and brake disc rotor lock are 100 % engaged and locked out before attempting to: Pre-tighten and torque the main shaft to hub hardware after rotor is fully engaged onto the main shaft during rotor installation. Disconnect the crane and remove the crane out of the working area after rotor is installed. Perform any work outside and/or inside of the hub after the rotor has been installed. Perform any work inside and/or outside the nacelle near exposed rotating components after the rotor has been installed. All GE employees must ensure the hydraulic disk brake and disk rotor lock is 100 % locked out before exiting the nacelle. ATTENTION Check components! All components must be checked for visible damage, deformation and cracks prior to assembly! The components must be stored and mounted in such a way that any damage that could adversely affect the standing stability or load-bearing capacity and could thus cause potential accidents is avoided. Please contact the GE site representative if damage is found prior to installing the component. DANGER Risk of damage to equipment! Tag lines must remain attached when installing components to stabilize the load where environmental conditions (winds) may cause components to make contact when hoisting. Using Tandem picks on the nacelle during offloading and staging without the use of a properly sized spreader bar will result in damage to the fiberglass rigging hatch openings. This will result in installation delays, as nacelles with fiberglass damage will not be allowed to be installed until corrected. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 29/428 GE Renewable Energy Installation Manual – Original – DANGER Risk of damage to the wind turbine generator system! The rotor lock and the high-speed shaft brake must always be released before leaving the turbine. Make sure that the machine is idling. DANGER Rotor lock not to be used to stop rotation! Never use the rotor lock to stop drive train rotation. The hydraulic hand brake must be used to stop the rotation. No hub entry on wind speeds > 14 m/s, 12 m/s with 120 meter rotors. DANGER Electrical hazard! Refer to the latest revision Energization Process Flow Chart and Verify GE and Customer LOTO procedures are complementary. Follow site specific LOTO policy if LOTO needs to removed or re-applied. Ensure all pre- energization/de-energization checks per this document are adhered to. Follow electrical PPE requirements in the Electrical Service Bulletin (Element HS 13. 2C) for any electrical work on the WTG (See the EHS Outage Plan or the Construction EHS Plan). DANGER Electrical hazard! Verify appropriate energy isolation procedures are followed based on local standards and/or GE `s requirements. Use caution during the inspection! Medium voltage or high voltage may be present in the WTGS. The collection system terminates at the second level medium voltage switchgear. Verify that the installer LOTO plan and GE LOTO plan are complementary to ensure the equipment is de-energized. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 30/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual DANGER Electrical hazard! If WTG has a PMG Generator, the rotor must be locked before performing phase check and electrical validation testing and before terminating the generator cables. Verify appropriate energy isolation procedures are followed based on local standards and/or GE requirements. I.e. local standards, customer LOTO plan and GE LOTO plan must be complementary to ensure the equipment is deenergized. WARNING Tower rescue equipment (Abseiling device!) An abseiling device must be available in the event of an emergency; the system depends on the turbine configuration. Check the integrity of the seal of the equipment bag on each visit to the nacelle. The abseiling device is pre-assembled and is ready for use immediately after it has been removed from the equipment bag. Perform an additional visual inspection of the abseiling device immediately before use. Care for and maintain the abseiling device as per manufacturer’s recommendations. ATTENTION Environmental Risk! Follow all applicable local regulations for use, containment and disposal of all chemical substances. NOTE Emergency evacuation routes: Where the main access road to any particular pad is blocked due to limited space, the Buyer & Installer is responsible to plan for an alternative emergency vehicle route and or site specific emergency evacuation plan in case there is an emergency. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 31/428 GE Renewable Energy Installation Manual – Original – 4.1 Operations Involving the Use of a Crane WARNING Mind the maximum allowable wind speed! For technical data to calculate the maximum allowable wind speed for crane activities especially on parts and systems with a high sail area with respect to system weight refer to the document “Specification handling and Lifting (Drag Coefficient Sail Area)”. All operations involving the use of a crane may only be carried out based on the respective crane limitations, site/weather specific circumstances and field personal experience. The final decision if work may be executed rests with the crane operator and installer representative based on the lift plan. 4.2 Qualification and Orientation of the Installation Personnel Only trained and oriented personnel may be deployed during the installation. Only trained People are allowed to install the (optional) service lift. The spheres of responsibility of the personnel for the operation of tools must be clearly defined! A responsible person who monitors safety during the installation and prevents any work which compromises safety from being carried out must be appointed. The installation personnel must be informed about and oriented in the current legal and accident prevention regulations. Furthermore, the installation personnel must be oriented in the available safety devices on and in the Wind Turbine Generator System and the safety devices of the installation equipment. It must be ensured that the installation personnel have completely understood the instructions and that all the instructions are complied with. Only thus will all concerned carry out work with safety in mind and with an awareness of the dangers. In addition to the Installation Manual and the binding regulations for accident prevention in the country of use and applicable at the location, the technical regulations for safety and working in accordance with good professional practice must also be complied with. NOTE Comply with the accident prevention regulations! The country-specific accident prevention regulations must always be complied with. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 32/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 4.3 Safety Equipment The safety equipment serves to reduce risks and dangers. It must be guaranteed that every erecting engineer uses his personal protective equipment (PPE), in order to prevent accidents or serious injuries. 4.4 Personal Protective Equipment (PPE) Everybody must wear Personal Protective Equipment (PPE) when working on or in the WTGS to protect themselves from injury in accordance with the GE Climbing Rules: The PPE includes: Full body fall protection harness w/ front, back and side D-rings. Traveling safety hook Double lanyards Y construction with shock absorbers Suspension trauma strap Hard hat equipped with chin strap Steel-toe (or composite toe) safety boots (sturdy lugged soled footwear, capable of supporting ankle) Lanyard keepers are required for double lanyards with a single shock ABSORBER pack Safety glasses Gloves appropriate for climbing Hearing protection (if required) Rescue/escape system (Europe: black bag) with the rope length greater than tower height. Breathing apparatus (if required) Thermal clothing (if required) The PPE must be approved and furnished with marks of conformity; which certify that it is suitable for the work, the protection and also for the climatic conditions of the site. The extent and the equipment of the personal protective equipment may vary in some countries. NOTE Check the protective equipment! Check the completeness, the condition and the function of your personal protective equipment in good time before entering the WTGS. If a piece of the equipment is missing, it must be replaced before starting work. The safety harness and the entire safety equipment must be checked before use. Damaged equipment must never be used. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 33/428 GE Renewable Energy Installation Manual – Original – The PPE must be inspected and tested by a technically competent person after any fall, or at least at the intervals recommended by the manufacturer. NOTE Follow the instructions! Follow the manufacturer's instructions for all component parts of the personal protective equipment! 4.4.1 Safety Harness The safety harness is used for your safety during the ascent and descent of the tower (safety harness and traveling safety hook) and when carrying out work in areas where there is a danger of falling (safety harness and safety rope). WARNING Check the safety harness! Check the safety harness and the safety equipment, before you use it. Damaged components must not be used and must be exchanged immediately. Care and handling of the safety harness and the complete safety equipment: Never expose to acids/caustic chemicals. If this is unavoidable, rinse with water immediately afterwards. Protect from sharp edges and sharp-edged objects. For clean and care, refer to manufacturer recommendations. Store in a well-aired place out of direct sunlight. Additionally, follow all of the manufacturers handling and care instructions. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 34/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 4.4.2 Protective Equipment for Measurements on Live Components DANGER CRITICAL TO SAFETY: Ask and answer this question every day! “Are you planning to work on (or near) electrical equipment or cables, etc.?”. If you answered “Yes”! You are required to work with your Site EHS and Site Leadership to establish a Risk Assessment and train/ issue/communicate the Site Specific LOTO plan to all affected team members BEFORE executing ANY work. Examples including but not limited to Installation and Post Installation of: Electrical equipment or any other testing that requires energizing or deenergizing e.g., IR/VLF/Hi-Pot Testing Temporary Energizing/Lighting Commissioning /Pre-Commissioning/Portable Generators Permanent or Temporary Grid/PMT Load Bank DANGER Life-threatening hazard! Danger! Electricity! Contact can cause extremely serious injuries and even death. DANGER Electrical hazard! Refer to the latest revision Energization Process Flow Chart and Verify GE and Customer LOTO procedures are complementary. Follow site specific LOTO policy if LOTO needs to removed or re-applied. Ensure all pre- energization/de-energization checks per site-specific LOTO are adhered to prior to beginning any work. Follow electrical PPE requirements in the Electrical Service Bulletin (Element HS 13. 2C) for any electrical work on the WTG (See the EHS Outage Plan or the Construction EHS Plan). CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 35/428 GE Renewable Energy Installation Manual – Original – Special PPE is required for measurements or work on live components. This provides protection against electricity flowing through the body, e.g. as a result of touching live components in operation. Furthermore, it provides protection against accidental arcs caused by insulation breakdowns e.g. as a result of switching operations under load. Please refer to the GE Electrical Service Bulletin to check specific requirements for the different risk categories. NOTE The following PPE requirements listed in Table 7 below are an addition to the requirements outlined by the Wind Turbine Climbing Rules. Danger class 2 Required Electrical PPE Note: Underwear must be of cotton or other natural fiber. Cal/cm (Joule/cm2) Uniform: Long sleeves and long pants required (minimum of untreated natural fiber non-melting clothing. 4.5 oz/yd²: 153 g/m2 weight) such as 100 % cotton or at least NFPA Category 1 or EN Class 1 0 Up to 1.2 (Up to 5) Other PPE: Safety glasses Ear canal inserted hearing protection (starting 1Q10) 1000 V or higher gloves and leather shells Uniform: Arc resistant (AR) shirt and AR pants or overalls (4 cal/cm²); at least NFPA Category 1 or EN Class 1 1 Other PPE: Safety glasses Arc-rated face shield (starting 1Q10) Hard hat (class E) (all new hard hats and required 1Q10) All leather upper heavy duty work shoes – EH rated (all new shoes and required by 1Q10) 1000V or higher gloves and leather shells Ear canal inserted hearing protection (starting 1Q10) 1.2 to 4 (5 -16.6) Uniform: Arc resistant (AR) shirt & AR pants or overalls (8 cal/cm²); at least NFPA Category 2 or EN Class 1 2 4.1 to 8 (17 - 27.3) 3 8.1 to 25 Other PPE: Safety glasses Arc-rated face shield or arc flash suit hood Hard hat (class E) (all new hardhats and required 1Q10) All leather upper heavy duty work shoes – EH rated (all new shoes and required by 1Q10) 5 1000 V or higher gloves and leather shells 6 Ear canal inserted hearing protection 7 Balaclava 1 2 3 4 Uniform: Arc resistant (AR) shirt and AR pants or overalls (8 cal/cm²); at least NFPA Category 2 or EN Class 2 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 36/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Danger class 2 Cal/cm (Joule/cm2) (28 – 104) – Original – Installation Manual Required Electrical PPE Note: Underwear must be of cotton or other natural fiber. Other PPE: PPE same as level 2 plus Arc-rated flash suit (jacket and pants) & flash suit hood 1000 V or higher gloves and leather shells Layers of AR clothing must add to 25 cal/cm² or greater Uniform: Arc resistant (AR) shirt and AR pants or overalls (8 cal/cm²); at least NFPA Category 2 or EN Class 2 4 25.1 to 40 (104 – 167) Over 40 cal/cm² (Over 167 J/cm²) Other PPE: PPE same as level 2 plus Arc-rated flash suit (jacket and pants) and flash suit hood 1000 V or higher gloves and leather shells Layers of AR clothing must add to 40 cal/cm² or greater. Arc blast potential must be heavily considered when this level of protection is needed. The preferred method is to reduce the risk level through engineering controls. Table 7: Protective equipment for measurements on live components Cal/cm2 denotes the unit up to which the PPE resists the released energy. 5 Preparatory Work 1. Barricade and/or cordon off as per country specific the installation site to limit access to unauthorized personnel. 2. Check the lifting gear for proper inspections and certifications. 3. Conduct a Pre-lift meeting, complete Job Safety Analyses (JSAs). 4. Personnel not involved in crane lift operations must leave the crane work zone (danger zone) before lift operations start. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 37/428 GE Renewable Energy – Original – Installation Manual 6 Foundation ATTENTION Confirm that the grounding ring(s), the installation rods and the soil resistivity test verification report are complete in accordance with the respective grounding specification. Inspect the foundation for cracks/damage; report any foundation damage to the customer and GE prior to erection activities. Verify with Civil Superintendent that foundation has been cleared to start tower assembly work and minimum required foundation submittals per respective foundation specifications are complete. DANGER Electrical hazard! Refer to the latest revision Energization Process Flow Chart and Verify GE and Customer LOTO procedures are complementary. Follow site specific LOTO policy if LOTO needs to removed or re-applied. Ensure all pre- energization/de-energization checks per Site Specific LOTO are adhered to prior to beginning any work. Follow electrical PPE requirements in the Electrical Service Bulletin (Element HS 13. 2C) for any electrical work on the WTG (See the EHS Outage Plan or the Construction EHS Plan). The Installation of the foundation is not part of this Installation Manual. Refer to the contract technical foundation documents for details. 6.1 Tower Base Ring The tower base ring is the bottom part of the tower. The PPM is placed inside the base ring on the foundation. 6.1.1 Drawings See contract technical foundation documents. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 38/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 6.2 Identifying the Tower Base Ring ATTENTION Identify the tower base ring! The positioning of the PPM differs depending on the type of tower base ring [108 holes or 124 holes). Tower Base Ring (75 m and 85 m) Hole pattern for foundation – tower base ring connection 54 x ø 55 mm – flange inside 54 x ø 55 mm – flange outside Hole pattern for TBR – tower base section connection: 115 x ø 52 mm. Figure 2: Tower base ring (75 m & 85 m) Tower Base Ring (98.3 m) Hole pattern for foundation – tower base ring connection 62 x ø 55 mm – flange inside 62 x ø 55 mm – flange outside Hole pattern for TBR – tower base section connection: 121 x ø 52 mm. Figure 3: Tower base ring (98.3 m) CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 39/428 GE Renewable Energy Installation Manual – Original – Tower Base Ring (110 m and 120 m) Hole pattern for foundation – tower base ring connection 62 x ø 55 mm – flange inside 62 x ø 55 mm – flange outside Hole pattern for TBR – tower base section connection: 106 x ø 61 mm. Figure 4: Tower base ring (110 m and 120 m) Tower Base Ring (131 m) Hole pattern for foundation – tower base ring connection 80 x ø 55 mm – flange inside 80 x ø 55 mm – flange outside Hole pattern for TBR – tower base section connection: 147 x ø 52 mm Figure 5: Tower base ring (131 m) CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 40/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 6.2.1 Preparing the Foundation Anchor Bolts and Installing the Tower Base Ring Reference Customer Information for the Anchor Bolt System. General_Description_3MW-50Hz_foundation_anchorAdapt. If tower base ring is already installed go to section 6.3 1. Tap each bolt lightly to break the bolts free of cement seepage. Verify threads are free of cement and defects. 2. Verify anchor bolts are sealed where it meets the concrete to ensure that there is no water in the anchor bolts sleeve that could cause corrosion and possibly freeze depending on the site location. 3. Clean debris from the entire foundation surface. Any loose or adhesion-inhibiting parts and cement slurry must be removed. 4. Protect anchor bolts from grout area with foam or other means as indicated in customer and/or GE foundation design specification to keep grout from adhering to the anchor bolts. General_Description_3MW-50Hz_foundation_anchorAdapt CUSTOMER SPEC: Request from customer. 5. Remove the nuts and washers from the anchor bolts. 6. Place the nuts and washers on the foundation at a sufficient distance from the anchor bolts so they can be easily acquired when placing them back onto the bolts after tower base Ring is lowered. 7. All anchor bolts project at least 100 mm beyond lower tower base ring flange. 6.2.2 Preparing the Tower Base Ring 1. Inspect the tower base ring interior, exterior, and flange for exposed metal surfaces, corrosion, burrs, and high spots. 2. Remove burrs and high spots using a course half-round file and buff the surface using medium grit sandpaper. Remove corrosion using medium grit sandpaper and protect from corrosion (e.g. cold galvanize) or as required per manufacturers specifications. 3. Paint exposed metal surfaces of the interior and exterior of tower base ring per manufacturer’s specifications. Ensure the correct paint and primer is used for interior or exterior repairs, consult with GE` s representative for details. 4. Completely clean and wash interior and exterior. 6.2.3 Verifying the Foundation is Level 1. Please refer to customer and/or GE foundation specification to ensure the minimum/maximum grout thickness per foundation design. General_Description_3MW-50Hz_foundation_anchorAdapt Contact GE for the site-specific GE Tower Foundation Interface Specification. Contact Customer for customer specific Foundation Interface Specification. 2. Using a laser level, shoot four points per quarter between leveling locations, and mark the results at each location. Return to the highest point recorded within the circumference and use as a reference point. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 41/428 GE Renewable Energy 3. – Original – Installation Manual From reference point adjust the level locations by using metal shim plates to ensure the minimum/ maximum grout thickness as required by foundation design. Do not put shims directly underneath the door. Contact GE for the site-specific GE Tower Foundation Interface Specification. Contact Customer for customer specific Foundation Interface Specification. 6.2.4 Installing the Tower Base Ring 1. To prevent a pinch point/crush hazard, place four 4 x 4 wood blocks on the foundation spaced every 90 degrees between the anchor bolts. 2. Prepare the foundation for applying grout in accordance with grout manufacturer's and foundation designer's instructions. 3. Attach the rigging and tag lines to the tower base ring. 4. Instruct crane operator to hoist the tower base ring over the foundation and onto the anchor bolts. ATTENTION Crushing hazard! During Installation always ensure that hands, feet, and body are not between any potential pinch points. 5. Crew persons holding tag line will guide the tower base ring down over the anchor bolts onto the foundation. Align the TBR over the anchor bolt in accordance with the foundation specification. 6. Remove the four woodblocks after the tower base ring is safely installed over the anchor bolts on the leveling metal shim plates. 7. Verify the tower base ring is level in accordance with the foundation specification. If the tower base ring is to be grouted now, install nuts with two turns per nut, raise the tower base ring and re-insert the support (wood blocks); grout per manufacturer’s specifications, remove the supports (blocks) and lower the tower base ring section, check level again. Ensure excess grout is removed and the flange is clean. 8. Install all nuts and washers, install washers (with chamfer facing away from flange) and nuts per manufacturer's specifications onto the anchor bolts. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 42/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 9. – Original – Installation Manual Tighten the top nuts with an impact wrench to approximately 100-foot pounds (150 Nm) at the leveling shim pack locations. For GE foundation design refer to the 3MW Platform Bolt Torque Specification mentioned in chapter 2.2. For all other designs refer to manufacturer design specifications. 10. Final tensioning of anchor bolts is done after grout has cured according to manufacturer's instructions. 11. In section 7 of the ICL enter: Grout type, date and time, required grout strength achieved, Enter minimum grout compressive strength required before the anchor bolts can be tensioned and actual measured bar (PSI) grout break (proven by testing). 12. Ensure anchor bolts are clearly marked with a single line running down the threads nut washer and clamped part extending beyond the protection caps. This will serve as a visual reference for future maintenance inspections to indicate tensioning is complete. 13. Record pretension and elongation in kN and mm data respectively in the torque report. Refer to foundation design specification. 14. Mark the centerline for the tower entry door on the upper flange of the tower base ring for PPM and tower door centerline installation reference point. 15. Using a permanent marker neatly write the anchor bolt tension values on the inside tower wall: (Pre-tension load (kN) = Value = Date: ) CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 43/428 GE Renewable Energy – Original – Installation Manual 6.3 Preparing the Foundation 1. Inspect the bottom and the top base ring flange and the shell for exposed metal surfaces, corrosion, burrs and high spots and dirt from concreting. 2. Remove burrs and high spots using a coarse half-round file and buff the surface using medium grit sandpaper. Remove corrosion using medium grit sandpaper. 3. Inspect the anchor bolts (anchor bolt size M 48, hot dip galv) for dirt from concreting, defects on the corrosion protection and defects on the threads. 4. Verify the tower base ring is leveled by using a surveyor's level. 5. Pretension the anchor bolts on the tower base ring according to the specifications of the foundation designer. 6. Check again the level of the tower base ring according to the tolerances of the foundation designer. 7. Install the protection caps on the bolts as required per the foundation design. Figure 6: Cleaning the surface of the foundation ATTENTION Water damage! Verify no water accumulation is present inside the foundation and/or in conduits. If water is present, remove it and seal all transformer and foundation conduit openings to keep water out. Figure 7: Installing the protection caps on the bolts CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 44/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – 8. Shorten all plastic pipes, through which the telephone line (option), fiber-optic cables (for wind farm connection) and the grid connection are subsequently routed, by means of an angle grinder or a saw. 9. Remove all sharp edges and install conduit edge protection caps. 10. Verify ground cables are installed free of defects and in the foundation in accordance with the "Requirements for the Tower to Foundation Interface" document and/or country- and local-specific electrical code. Installation Manual Figure 8: Shortening the plastic pipes NOTE Meet grounding resistivity requirements! The grounding resistivity requirements must be met before the tower is erected! Where applicable, ground wires must be terminated at every stage of the installation process! 11. Verify bolts, tools, and materials are staged inside the base ring with enough clearance from the flange. Figure 9: Staging the bolts inside the tower base ring CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 45/428 GE Renewable Energy Installation Manual – Original – 7 Pre-assembled Power Module (PPM) The "Pre-assembled Power Module" is installed in the tower base of the Wind Turbine Generator System. The PPM enables the transformer and medium-voltage switch gear to be integrated in the tower. The PPM consists of the following three sections: Section 1 (transformer level) Section 2 (controller level) Section 3 (converter level) Section 3: Converter level Section 2: Controller level Section 1: Transformer level Figure 10: Structure of the 3-level PPM CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 46/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 7.1 Safety Information for Installation of the PPM ATTENTION Secure against unauthorized entry/climbing! If the first tower section is not installed on the same day as the PPM, the PPM must be secured against unauthorized entry and climbing, in order to protect the turbine from damage and people from injury. This can be provided by disassembly of the bottom section of the ladder or by a night security service. The ladder and the fall protection systems must be checked as described in section 17 Installation of the Ladder and Fall Protection System on page 344 before a new segment of the ladder is used. All personnel concerned must wear their personal protective equipment (PPE) when carrying out work on the PPM. DANGER Falling hazard! Ensure that you are always protected by your PPE when carrying out work on the PPM. Use the hooking points marked in signal yellow which are located on each platform (section). DANGER Life-threatening hazard - working under suspended loads! Everybody must leave the danger area! The banksman may not give a signal to raise or lower until everybody has left the danger area. Never stay under suspended loads! CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 47/428 GE Renewable Energy – Original – Installation Manual ATTENTION Check the components! All components must be checked for visible damage, deformations and cracks which could affect their bearing capacity before assembly. Findings have to be reported to the GE site representative. The components must be stored and assembled in such a way that damage which could adversely affect their stability or bearing capacity and thereby lead to safety hazards is prevented. ATTENTION Crushing hazard! During Installation always ensure that hands, feet, and body are not between any potential pinch points. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 48/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 7.2 Overview of the Hooking Points A total of three safety hooking points for personal falling protection are provided in the PPM. They are marked in signal yellow and are located on the controller level, two on columns and one above the transformer level hatch for rescue from this level. The hooking points must be used when carrying out work which requires removal of the installed fall protection systems or safety rails. Transformer Level Consideration when working on the Pre-Assembled Power Module (PPM) Please make sure that no object (like a cable or a long toll) goes into the transformer level from other levels while the medium voltage or auxiliary transformers are energized. Figure 11: 3-level PPM – Hooking points CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 49/428 GE Renewable Energy Installation Manual – Original – 7.3 Overview of the Installation Sequence The 3-level PPM is constructed in eight primary steps, which are described in detail in the following section. The graphic shows an initial overview of the steps to be carried out. 1. Place the transformer level (section 1) on the foundation. Install the ladder components. 2. Assemble the converter onto its support frame. (The converter fan shrouds will be installed after tower door section has been installed). 3. Place the converter with its support frame (section 3) onto the controller level (section 2). 4. Place the controller/ converter assembly (sections 2 and 3) onto the transformer level (section 1) and secure the twist locks. 8. Ensure the shrouds are dismantled before lowering down the base section. 5. 6. 7. Alternatively, place the controller level (section 2) onto the transformer level (section 1) and secure the twist locks. Place the converter with its support frame (section 3) onto the controller/transformer assembly(sections 1 and 2). Install the temporary rail Connect the door section to alignment system for the the base ring. Assemble the installation of the door section stairs. of the tower. Ensure the shrouds are dismantled before lowering down the base section. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 50/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – 9. 10. Install the converter fan shrouds, the platform cover plates to close the gaps around the converter. Assemble the power meter and shadow monitoring boxes (when required) as well as hatches, steps, railings, brackets and ladders in the transformer, controller and converter levels. Extend the four vibration dampers. Assemble the air inlet ducts. ATTENTION Check the wind speed! The PPM must be secured against tipping over from a wind speed of v = 25 m/s. This can be provided by bracing the PPM with chain hoist. All PPM components must remain protected from elements such as moisture, rain, snow, contaminants such as dirt, dust, oil, rodents and damage during installation process. The installer must hold available protection material for storage e.g., tarps - shrink wrap - taking into consideration condensation and freezing weather. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 51/428 GE Renewable Energy – Original – Installation Manual 11. All PPM components must remain protected from elements such as moisture, rain, snow, contaminants such as dirt, dust, oil, rodents and damage during installation process. 12. The installer must hold available protection material for storage e.g., tarps shrink wrap - taking into consideration condensation and freezing weather. Figure 12: Example PPM transformer and controller level covered with a tarp CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 52/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 7.4 Assembling the PPM WARNING Due to large sail area the base section must be installed immediately after installing anything above the transformer. WARNING Take care when working on the low-loading trailer Work on the loading platform of the low-loading trailer may only be carried out when it is stationary. All personnel must leave the loading platform before the low-loading trailer is moved. DANGER Falling hazard! Retractable lanyards or temporary fall arrest system shall be used until the permanent fall arrest system is installed. DANGER Falling hazard! Ensure that you are always protected by your PPE when carrying out work on the PPM. Use the hooking points marked in signal yellow which are located on the controller level (section 2). CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 53/428 GE Renewable Energy Installation Manual – Original – WARNING Keep free all passageways and escape ways! Do not obstruct with tools or construction material. DANGER Prevent damage to the WTGS! When lifting PPM components, ensure the load is stabilized to prevent unexpected swing and potential contact with other objects and to ensure the cribbing will not shift. Platform (Section) Drawing number Structure of the PPM, DTE assembly 117W6882, 444W8673; For 131m request latest version from GE engineering. Transformer platform (Section 1) 117W6871, 444W6900 Controller platform (Section 2) 117W6997, For 131m request latest version from GE engineering. Converter platform (Section 3) 117W6892, 44W8727 Assembly Drawing Ladder DTE 117W6917, 444W7063 (131 and 85 m); 444W9057 (110 m) Assembly Drawing Converter Request latest version from GE engineering. Operation Manual for Cast Resin Transformers without enclosure DT4622 Table 1: Requisite installation Diagrams CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 54/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – 1. Cut holes from the lifting points. The packaging must be maintained until the nacelle is installed. 2. Remove all the securing devices located between the low-loading trailer and the PPM section. 3. Remove any loose parts which could drop out while lifting the section. 4. Carry out the Transformer Receiving Inspection. Installation Manual Figure 13: Unpacking the transformer platform 5. Attach an M39 bolt-on attachment swivel with a lifting capacity of 15 t at each pillar of section 1 (transformer level). 6. Lash the section by means of the bolt-on attachment swivels. NOTE Minimum length of lashes (chains or slings) to lift the transformer level is 6000 mm. Adjust the rigging as required to ensure the transformer is level. 7. Before lifting, lash a tag line to each of two opposed points, in order to prevent the section from swinging during the lifting operation. 8. This allows the section to be guided without danger. Figure 14: Attaching an M39 bolt-on attachment swivel Figure 15: Guiding the section CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 55/428 GE Renewable Energy Installation Manual – Original – 7.5 Installing the Fit Up Aid Tool (Transformer Alignment Brackets) 1. Before lowering the transformer platform, care shall be taken that the right tool is used and fixed in the pre- marked holes, see following drawing. Hole "1" is located centrally in front of the tower door, (N). next to the tower manufacturer 0 reference mark and or as identified by the civil contractor. The position of the tower door is pad specific, in relation to the position of conduits. 2. 75/85 m RH bracket in hole 15 & 16 Counting counter-clockwise from hole "1" insert alignment brackets for the 75/85 m, 98.3 m, 110 m or 120 m tower configuration. Reference illustrations. 75/85 m LH bracket In hole 44 & 45 98.3 m RH bracket in hole 16 & 17 98.3 LH bracket in hole 46 & 47 110/120 m RH bracket in hole 14 & 15 110/120 m LH bracket in hole 40 & 41 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 56/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual NOTE Refer to specific tower drawing for correct fit up aid tool as bolt hole pattern varies for different hub heights (HH) and hole “x” will vary. 3. Secure the two alignment brackets to the tower base ring flange with hardware. Ensure the templates are oriented correctly and the right size hardware is used to prevent movement of the alignment templates during installation of the transformer. Figure 16: Transformer alignment templates ATTENTION Prevent damage to the WTGS! When lifting PPM components, ensure the load is stabilized to prevent unexpected swing and potential contact with other objects. 4. 5. Give detailed instructions to the crane operator to swing the section over the tower base ring. Figure 17: Transformer Positioning Slowly lower the section. An erecting engineer must be positioned at each template to supervise the lowering of the PPM. DANGER Crushing hazard! During Installation always ensure that hands, feet, and body are not between any potential pinch points. Use tag lines to guide the load. Figure 18: Transformer Positioning CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 57/428 GE Renewable Energy 6. – Original – Installation Manual Insert the transformer platform between the brackets of the fit-up aid tool. First dock the transformer platform to the left bracket, and then pull it against the right bracket. Figure 19: Transformer Positioning 75/85m 7. Loosen nut A completely. 8. Loosen nut C. Figure 20: Aligning the transformer level CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 58/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 9. – Original – Installation Manual Place a water level or spirit level on the flange of the tower base ring. 10. Hold it to the pillar of the transformer platform. 11. Measure the distance from the top surface of the pillar flange to the bottom surface of the water level and adjust the adjustment nut B resulting in a distance of 611 mm. Depending on ground thickness shim plates may be required. NOTE Consult with engineering prior to using shim plates! 12. Hold nut B and using a torque wrench with a crows-foot torque nut C to 200 Nm against nut B. Figure 21: Aligning the transformer level 13. Repeat this adjustment at the other three pillars. 14. If needed, use a bottle jack as required to adjust level. Ensure all four feet are set firmly on the foundation, the PPM Transformer oriented correctly on the foundation for ease of access to the walkway through the tower entry door. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 59/428 GE Renewable Energy Installation Manual – Original – 15. After positioning the section, remove all hoisting gear, tag lines and attachment swivels and the fit up aid tool. Figure 22: Disconnecting the rigging 16. Terminate the foundation ground leads to the transformer grounding bus bar in accordance with the foundation tower interface specification, torque the bolts and mark them with a paint pen. Figure 23: Termination of foundation grounds. 17. Place step (FN 3) in its final position. 18. Drill holes into the concrete floor to install the anchor bolts (FN 15, 16 and 17) per drawing no. 117W6917/444W7063/ 444W9057. A 19. Bolt the brackets (FN 4) to the step. 20. Place the converter coolant drain barrel inside the base ring. B A - Barrel B - Step Figure 24: Floor step. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 60/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 21. Perform Insulation Resistance test and Transformer Turns Ratio (TTR) as prescribed in the Transformer manufacturer manual. Request latest version from GE engineering. NOTE Transformer testing must be completed before tower erection. 22. Provide a copy of the test results to GE. Figure 25: Transformer manual for TTR instructions ATTENTION The transformer coils and all other equipment must remain protected from elements such as moisture, rain, snow, contaminants such as dirt, dust, oil, rodents and damage during installation process. The installer must hold available protection material for storage e.g., tarps - shrink wrap taking into consideration condensation and freezing weather. Figure 26: Equipment protected from elements CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 61/428 GE Renewable Energy Installation Manual – Original – 23. Stage the ladder parts inside the tower for later installation according to drawing 117W6917/444W7063/444W9057. WARNING Do not use the transformer ladder unless it is fully installed according to drawing. Figure 27: Staging the ladder system at the transformer level 24. Remove all packaging material from the converter and the converter support frame. 25. Remove all the securing devices located between the low-loading trailer and the PPM section. 26. Remove any loose parts which could drop out while lifting the section. 27. Carry out the Converter Level Receiving Inspection. 28. Offload the converter and the converter support frame on a level surface near the tower assembly area. Figure 28: All equipment protected from elements 29. Remove the shipping material from the converter fans and remove the 4 loose fan plenum covers and place them aside. A - 4 plenum covers are shipped loose on top of the fan A Figure 29: Fan plenum covers CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 62/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 30. Loosen the hardware to remove the square covers bolted to the top of the fan. B B - Cover Figure 30: Fan square covers 31. Remove the converter fan top covers to allow access to the lifting point. 32. Remove the covers and place them aside. 33. Screw the hardware back onto the fan bolts for later use. Figure 31:Removing the square cover CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 63/428 GE Renewable Energy Installation Manual – Original – 34. Place the fan plenum covers inside the tower base section and secure with rope. The fan plenum covers will be installed on the converter fans after the base section is installed over the PPM. Figure 32:Place the fan plenum covers inside the tower base section 35. Remove the three cross braces and the two-heat exchanger protective covers that are bolted to the top of the converter cabinet. Reference the latest ESS DTA drawing. Figure 33: Cross braces and the two heat exchanger protective covers 36. Remove the two fan top covers and place them aside. A - Heat exchanger protective covers A Figure 34: Heat exchanger protective covers CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 64/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 37. Remove the motor fan assembly shipping crate hardware. Figure 35:Shipping crate hardware 38. Attach rigging to the two fan lifting points. 39. Lift the converter fans on top of the converter. Figure 36: Lifting the converter fan motor 40. Align over the converter cabinet bolt holes. 41. Remove the rigging. Figure 37: Placing the fan motor ontop of converter CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 65/428 GE Renewable Energy Installation Manual – Original – 42. Install and tighten all hardware according to the torque values provided in 105T5350. Figure 38: Securing the fan motors with hardware 43. Open converter support frame and ensure all PSL parts are accounted for. If any parts are missing contact GE site representative. Figure 39:Converter support frame/PSL CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 66/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 44. Remove all shipping material from the converter support frame. Figure 40: Converter support frame 45. Attach the rigging to the converter. NOTE The slings must be long enough so that there is not pressure put against the converter fan motors. Alternatively, a spreader bar is used to keep the sling pressure off from the fan motors 46. Remove the shipping crate hardware. ATTENTION Crushing hazard! Be aware of and keep your body away from pinching points during assembly operations. Figure 41: Rigging and removing DTE from shipping crate CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 67/428 GE Renewable Energy – Original – Installation Manual 47. Lift the converter and place it on top of the converter frame. 48. Ensure the load is stabilized before installing the mounting hardware. Figure 42: Placing the converter over the support frame CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 68/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 49. Apply thread locking compound to the mounting hardware. 50. Install the hardware to secure the Converter DTE to the converter frame. Reference the latest ESS DTA drawing. Figure 43: Installing the hardware 51. Tighten all bolts with an impact wrench not to exceed the final torque specified in 114W8775. Figure 44:Tightening hardware with an impact wrench CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 69/428 GE Renewable Energy Installation Manual – Original – 52. Torque all hardware to the values provided in 114W8775. Figure 45: Torquing the hardware 53. Remove all packaging material from the top of section 2 (controller level). 54. Remove all the securing devices located between the low-loading trailer and the PPM section. 55. Remove any loose parts which could drop out while lifting the section. 56. Carry out the Controller Level Receiving Inspection. Report any issues to the GE site representative. 57. Place the hatches, steps and railings for the controller level per drawing 117W6917 and 117W6882/444W8673 on the platform for later installation and secure all items against falling with tension belts. For 131m request latest version from GE engineering. Figure 46: Exposing the top of the controller CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 70/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 58. Ensure all hatches, steps and railings for the controller level are accounted for. Contact GE site representative if any parts are missing. 59. Optional: Place the hatches, steps and railings for the controller level per drawing 117W6917 and 117W6882/ 444W8673 on the platform for later installation and secure all items against falling with tension belts. For 131m request latest version from GE engineering. Figure 47: Accounting for platform parts 60. Instruct the crane to lift the converter over the controller level. ATTENTION Use two-way radios! A two-way radio is required for communication between the crane operator and the erecting engineer. Precise instructions for the required changes in the position of the tower sections can be given by this means. Figure 48: Placing converter over controller CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 71/428 GE Renewable Energy Installation Manual – Original – ATTENTION Crushing hazard! Be aware of and keep your body away from pinching points during assembly operations. 61. Align the converter leg holes to the controller level guide pins. Figure 49: Aligning converter over controller 62. Install the hardware on all 4 legs. Figure 50: Installing the hardware CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 72/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 63. Tighten the hardware with a ratchet and/or impact wrench not to exceed the final torque. Figure 51: Tightening the hardware 64. Using a torque wrench and back up wrench, torque the hardware according to the torque values provided in 117W6892/444W8727. Figure 52: Torquing the hardware 65. Detach the rigging from the converter lifting points. DANGER Equipment failure hazard The hardware that connects the converter to the converter frame and the converter frame to the controller is not rated to lift the weight of the controller unit. Do not attempt to lift the controller and converter unit together using the converter lifting eyes. Figure 53: Removing the rigging CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 73/428 GE Renewable Energy – Original – Installation Manual DANGER Falling hazard If an employee is working at a height that exposes them to a potential fall, fall arrest equipment must be used, and 100 % tie-off at all times is required. 66. Install a new set of rigging connected to the four controller lifting points. NOTE The slings must be long enough so that there is no pressure put against the converter fan motors. Alternatively, a spreader bar is used to keep the sling pressure off of the fan motors Figure 54: Connecting the the rigging to the controller lifting points. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 74/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 67. Instruct the crane operator to lift the controller/converter over the transformer. ATTENTION Crushing hazard! Be aware of and keep your body away from pinching points during assembly operations. Figure 55: Lifting the controller/converter over the transformer 68. Align the controller /converter over the transformer ensuring the correct orientation i.e., the MVSG over the cable tray/grid cables. Figure 56: Aligning the the controller/converter over the transformer CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 75/428 GE Renewable Energy Installation Manual – Original – 69. Connect the sections by locking the interlocking devices of the two sections. The interlocking devices are locked by means of a service key in accordance with the manufacturer's specification. 70. Ensure proper locking, by loosening, pushing up and turning to engage the interlocking device. 71. Verify a second time the locking devices on all four corners are engaged tight and marked with a pint pen. A - Lock nut A Figure 57: Engaging the four lock nuts 72. Tap the four lock nuts clockwise with a hammer until it is tight. Alternatively use Twist Lock Wrench Jost 915.259.000 Type Universal. Figure 58: Tightening the four lock nuts CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 76/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 73. Install four ratchet straps to stabilize the load while tower base section is installed. Figure 59: Securing the PPM with rachet straps 74. Detach the rigging from the controller lifting points. Figure 60: Removing the rigging CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 77/428 GE Renewable Energy – Original – Installation Manual Option 2: Installing controller level on top over the transformer first and then installing the converter on top the controller. 75. Instruct the crane operator to slowly lift the controller level and lower it on to the interlocking devices (twist locks) of section 1 (transformer level). NOTE Ensure the shrouds are dismantled before lowering down the base section. Figure 61: Mounting controller level section 2 on transformer level section 1 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 78/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – 76. Connect the sections by locking the interlocking devices of the two sections. The interlocking devices are locked by means of a service key in accordance with the manufacturer's specification. 77. Ensure proper locking, by loosening, pushing up and turning to engage the interlocking device. 78. Verify a second time the locking devices on all four corners are engaged tight and marked with a paint pen. A - Lock nut A Figure 62: Engaging the four lock nuts 79. Tap the four lock nuts clockwise with a hammer until it is tight. Alternatively use Twist Lock Wrench Jost 915.259.000 Type Universal. Figure 63: Tightening the four lock nuts CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 79/428 GE Renewable Energy – Original – Installation Manual 80. Prepare the converter as described in the previous section. NOTE The slings must be long enough so that there is no pressure put against the converter fan motors. Alternatively, a spreader bar is used to keep the sling pressure off of the fan motors. 81. Instruct the crane operator to slowly lift converter level (section 3) and lower it on to the controller level (section 2). DANGER Falling Hazard If an employee is working at a height that exposes them to a potential fall, fall arrest equipment must be used, and 100 % tie-off at all times is required. 82. Secure the sections with the hardware as described in previous section. Figure 64: Mounting converter level, section 3 on controller level section 2 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 80/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 83. Detach the PPM from the crane. Figure 65: Detach the rigging from the converter lifting points. 84. Complete the assembly of the PPM after the first tower section has been lowered onto the tower base ring. Details will be given in section 8.4. Completing the PPM Assembly. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 81/428 GE Renewable Energy – Original – Installation Manual 8 Tower Quantity Description 2 AC extension cord, 100’ 2 Bucket, canvas, 5 gallon 1 Bull pin to align flanges ar Cable tie, ship loose 1 Caulking gun 1 Container, gasoline ar Crimp tool – vendor specific 1 Cutter, cable (safety cable) ar Decals, warning label ar Die set- vendor specific 2 Duffel bag, canvas 1 File set, various, 12” 1 Generator, 6.5 kW with GFCI ar Heat shrink, ship loose 1 Ladder, extension, 16’ 1 Ladder, step, 10’ ar Lubricant, spray 1 Mop, sponge, heavy duty ar Paint pen, purple ar Paint, tower touch up, exterior ar Paint, tower touch up, interior 1 Pressure washer, with 120’ hose 3 Radio, two-way ar Rags 1 Ratchet, ½” drive ar Rigging ar Sandpaper, medium grit 1 Screwdriver set ar Sikaflex®, 262 1 Socket, 60 mm, ½-inch drive 1 Socket, deep, 24 mm, ½-inch drive ar Splices, ship loose 1 Stripper, cable 2 Tagline, nylon rope CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 82/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Quantity – Original – Installation Manual Description ar Tape, electrical 1 Torch, propane or heat gun 1 Water tank, 500 gallon 1 Qualified wrench, torque, hydraulic or electric 1 Wrench, combination, 2-3/8 inch 3 Wrench, combination, 24 mm 2 Wrench, combination, 50 mm 1 Wrench, combination, 9/16 inch 1 Wrench, impact, 1” drive 8.1 First Tower Section WARNING Take care when working on the low-loading trailer! Work on the loading platform of the low-loading trailer may only be carried out when it is stationary. All personnel must leave the loading platform before the low-loading trailer is moved. ATTENTION Check the wind speed! The tower may only be erected in accordance with section 4.1 ‘Operations Involving the Use of a Crane’. ATTENTION Prevent damage from the WTGS! If the nacelle cannot be mounted immediately and the "open" tower has to remain without a nacelle (e.g. overnight), only three tower sections may be mounted In this case, the top tower flange must be protected against the effects of the weather by suitable means. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 83/428 GE Renewable Energy – Original – Installation Manual WARNING Overhead suspended load! Never work under a suspended load. Always confirm accurate load center of gravity, lifting gear and equipment securely attached, Make sure all personnel, vehicles, equipment, and materials are clear of the crane tail and load swing. All lifting must be done in strict accordance with the installers lift plan and applicable job safety analysis must be reviewed prior to all lifts. WARNING Lifting heavy loads! Prior to lifting all heavy loads, a pre-lift meeting with all parties involved is required. (The crane operator, the rigger, the supervisor, the signalman, and any other personnel involved, such as area safety, tag line holders). All lifting must be done in strict accordance with the installers lift plan and applicable job safety analysis must be reviewed as well. WARNING Uneven/Slippery surfaces! Uneven surfaces are present due to the shape of the WTG equipment. Slippery surfaces may be present during wet or icy conditions. Use caution when walking into any WTG surface that is not designed as permanent walkaway. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 84/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 8.1.1 Inspecting the Tower Section 1. If the tower will be immediately installed remove the transport tarp and the tower straps from the tower flange. Fold up the transport tarp. Leave tarp and tower straps on if the tower will remain in storage. 2. Perform the Tower Receiving Inspection. Inspect the tower for signs of shipping damage. Contact the GE site representative if damage is found. 3. Visually inspect all bolted connections for attaching the platform and ladder to the tower wall, the cable tray to the tower wall and cable clamps to the tray, the fall arrest system to the ladder or safety cable stand-offs to the ladder. If any tower internal loose bolts are found contact GE site representative. The bolt has to be removed and replaced with a new bolt with new thread locker and then be torqued to the right torque in accordance with the tower internals assembly manual. NOTE Tower internal hardware is glued with thread locking. If it gets checked with torque, the thread locking will be disturbed and the bolt may become loose during WTG operation. 4. Inspect the fall arrest system mounting hardware and inspect the safety cable for kinks or cuts. If the cable is damaged contact GE's site representative. 5. Inspect the interior, exterior, and flanges for exposed metal surfaces, corrosion, burrs, and high spots. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 85/428 GE Renewable Energy – Original – Installation Manual 8.1.2 Preparing the Tower Section DANGER Fall hazard! Tower internal surface can represent a slippery surface during cleaning operations. Please be aware of the work environment and try to mitigate the risk by avoiding to walk over slippery surfaces. Once the tower sections are installed there is a danger of falling through open floor due to uninstalled hatches and flaps. Close these before beginning the work! Figure 66: Example temporary cover plate over open hole 1. Remove burrs and high spots using a course half-round file and buff the surface using medium grit sandpaper. Remove corrosion using medium grit sandpaper and spray cold galvanized compound. Repair any minor damaged paint surfaces preparing surface and applying the paint or primer per manufacturer’s instructions. Any major paint damage must be reported to GE representative and repaired in accordance with the manufacturer's instruction. Tower internal cleaning: 2. Any loose, lightly imbedded or accumulated dirt/debris must be removed from the tower internal surfaces to prevent short or long term contamination by falling down tower to the electrical components. Tower external cleaning: 3. Any material or contaminate that affects the life expectancy of the coating and any accumulated mud or other material that can become dislodged during operation must be removed. Cosmetic appearances are the customer’s decision for level of cleanliness. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 86/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual E – EL Contracts: Cosmetic appearances are the customer’s decision for level of cleanliness. ELI – ELIF – ELIFT Contracts: Cosmetic appearances are GE´s decision for level of cleanliness if WTG installation is in GE scope. It is recommended that cleanliness is clearly defined and understood by all parties prior to first unit installation preferably during the pre-installation meeting (PIM). 4. Verify the cables are secured in the cable tray with ties and clamps. Verify the cables are secured below the deck to prevent damage to cables and PPM. 5. Attach safety signs in the tower. Figure 67: Example of cables secured in cable tray 6. Install the fall arrest system or check the pre-assembled fall arrest system as per manufacturer’s instructions before erecting the first tower section. Fall restraint system is required to allow ascent to the top of the segment. Figure 68: Fall arrest system at base section CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 87/428 GE Renewable Energy Installation Manual – Original – 8.1.3 Example Attachment and Usage of the Lifting Gear 8.1.3.1 Plate Lifting Gear 8.1.3.1.1 Attachment of Plate Lifting Gear NOTE For handling of the lifting devices refer to the supplier’s documentation Please refer to outline drawing for the lifting point. Below pictures are for reference only. WARNING Take care when working on the low-loading trailer Work on the loading platform of the low-loading trailer may only be carried out when it is stationary. All personnel must leave the loading platform before the low-loading trailer is moved. 1. Install the temporary rail alignment system plates for the installation of the tower base section. Critical to Quality: 2. Brackets must be installed as shown in illustration to prevent damage to converter. A A. Tower flange bolt hole numbers B: Tower configuration B Figure 69: Example Right hand and Left hand brackets for a 75/85 HH tower. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 88/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual NOTE Refer to specific tower drawing for correct anti rotation device as bolt hole pattern varies for different hub heights (HH) and hole “x” will vary. NOTE Confirm correct brackets are being used as bolt hole patter may be different for each hub height. 3. Mount two lifting plates on the bottom flange of the base section. If installing plates with tower on a horizontal position, use a crane or an aerial lift to reach the mounting positions. 4. Mount one more lifting plate on the bottom flange of the tower section at the 12 o'clock position. Use a crane or an aerial lift to reach the mounting positions. DANGER If installing the plates after the tower is in the vertical position, ensure the tower is supported by matts prior to installing the plates to keep personnel from reaching under a suspended load. Figure 70: Example Right hand and Left hand brackets installed on a 75/85 HH tower base flange. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 89/428 GE Renewable Energy Installation Manual – Original – 8.1.3.1.2 Lifting the Tower Section from the Low-loading Trailer DANGER Falling objects hazard warning! Do not stand in front of or under the tower opening under any circumstances. Inspect the tower section before the lifting to remove any tool material that could fall down while it is being set upright. ATTENTION Check the wind speed! The tower may only be erected in accordance with section 4.1 ‘Operations Involving the Use of a Crane’. ATTENTION Check the wind speed! If the nacelle cannot be mounted immediately and the "open" tower has to remain without a nacelle (e.g. overnight), only three tower sections may be mounted. In this case, the top tower flange must be protected against the effects of the weather by suitable means. NOTE Use two-way radios! A two-way radio is required for communication between the crane operator and the erecting engineer. Precise instructions for the required changes in the position of the tower sections can be given by this means. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 90/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual ATTENTION Risk from lifting heavy loads! Prior to lifting all heavy loads, a pre-lift meeting with all parties involved is required (crane operator, rigger, supervisor, signalman, truck driver if applicable, area safety, tag line holders and any other personnel involved). All lifting must be done in strict accordance with the installers lifting plan and applicable job safety analyses must be reviewed prior to commencing work. ATTENTION Risk from overhead suspended load! Never work under a suspended load. Make sure all people, vehicles, equipment and materials are clear of the crane tail and load swing. 1. Slightly raise the tower section. 2. Remove the transport braces located between the tower section and the lowloading trailer. Figure 71: Lifting the tower section from the low-loading trailer 3. Bring the tower section to a vertical position by means of the main and support crane per the site-specific lift plan. The main crane lifts the load while the support crane lowers the load. Precise coordination between the two crane operators is essential. Figure 72: Raising the tower section CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 91/428 GE Renewable Energy Installation Manual – Original – Figure 73: Raising the tower section DANGER Crushing hazard! During installation always ensure that hands, feet, and body are not between any potential pinch points. Enter the area to remove the counter plate only after the load is stabilized on the wood or support frames with the crane holding the load. 4. Instruct the crane operator to slowly lower the tower section onto a wood or steel mat with sufficient dimensions and load capacity as shown in the adjacent Figure 74. or alternatively Figure 74: Example of removing the counter plate CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 92/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – 5. onto a specific support frame (put up on a wood or steel mat) with sufficient dimensions and load capacity as shown in the adjacent Figure 75. 6. Ensure the load is stabilized and unhook the lifting plate on the bottom tower flange from the support crane. Installation Manual Figure 75: Example of wooden support frame 7. Lash four tag lines to the bottom tower flange. Lash a tag line to each of two opposed points, in order to prevent the section from swinging during the lifting operation. This allows the section to be guided without danger. Figure 76: Tag line on the tower flange CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 93/428 GE Renewable Energy Installation Manual – Original – 8.1.3.2 HTS ACTEK WKA System 8.1.3.2.1 Attachment of HTS ACTEK WKA System 1. Mount 4 hooking points on top tower flange as shown in Figure 77. Ensure that the hooking points form a rectangle. The D-rings of the WKA-B-Flex are attached to the exterior of the tower. Figure 77: Arrangement of the hooking points NOTE For handling of the lifting devices refer to the supplier’s documentation Please refer to outline drawing for the lifting point. Below pictures are for reference only. WARNING Take care when working on the low-loading trailer! Work on the loading platform of the low-loading trailer may only be carried out when it is stationary. All personnel must leave the loading platform before the low-loading trailer is moved. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 94/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 2. – Original – Installation Manual Attach the guide pulleys to the crane hook by means of two ropes (steel or textile). Figure 78: Mounting the hooking points 3. Using suitable shackles, connect one end of the rope to the top right-hand hooking point and the other end of the rope to the bottom right-hand hooking point. 4. Using suitable shackles, connect one end of the rope to the top left-hand hooking point and the other end of the rope to the bottom left-hand hooking point. Ensure that the guide pulleys of the two steel ropes do not cross. Figure 79: Position of the hooking points on the flange 5. Mount two hooking points on the bottom tower flange as shown in Figure 80. 6. Using suitable shackles, connect the hooking points to the hook of the support crane. Figure 80: Hooking points on the bottom tower flange CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 95/428 GE Renewable Energy Installation Manual – Original – 8.1.3.2.2 Lifting the Tower Section from the Low-loading Trailer DANGER Falling objects hazard warning! Do not stand in front of or under the tower opening under any circumstances. Any objects or materials remaining in the tower or any inadequately secured cables could fall out of the tower while it is being set upright. ATTENTION Check the wind speed! The tower may only be erected in accordance with section 4.1 ‘Operations Involving the Use of a Crane’ If the nacelle cannot be mounted immediately and the "open" tower has to remain without a nacelle (e.g. overnight), only three tower sections may be mounted. In this case, the top tower flange must be protected against the effects of the weather by suitable means. ATTENTION Check the wind speed! If the nacelle cannot be mounted immediately and the "open" tower has to remain without a nacelle (e.g. overnight), only three tower sections may be mounted. In this case, the top tower flange must be protected against the effects of the weather by suitable means. NOTE Use two-way radios! A two-way radio is required for communication between the crane operator and the erecting engineer. Precise instructions for the required changes in the position of the tower sections can be given by this means. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 96/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual DANGER Risk from lifting heavy loads! Prior to lifting all heavy loads, a pre-lift meeting with all parties involved is required (crane operator, rigger, supervisor, signalman, area safety, tag line holders and any other personnel involved). All lifting must be done in strict accordance with the installers lifting plan and applicable job safety analyses must be reviewed prior to commencing work. DANGER Risk from overhead suspended load! Never work under a suspended load. Make sure all people; vehicles, equipment and materials are clear of the crane tail and load swing. 1. Slightly raise the tower section. 2. Remove the transport braces located between the tower section and the lowloading trailer. Figure 81: Lifting the tower section from the low-loading trailer CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 97/428 GE Renewable Energy 3. Installation Manual – Original – Bring the tower section to a vertical position by means of the main and support crane. Figure 82: Raising the tower section The main crane lifts the load while the support crane lowers the load. Precise coordination between the two crane operators is essential here. Figure 83: Raising the tower section DANGER Crushing hazard!! During installation always ensure that hands, feet, and body are not between any potential pinch points. Enter the area to remove the counter plate only after the load is stabilized on the wood or support frames with the crane holding the load. ATTENTION Risk from lifting heavy loads! When lifting WTGS components, ensure the load is stabilized to prevent unexpected swing and potential contact with other objects. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 98/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 4. – Original – Installation Manual Instruct the crane operator to set the tower on wood blocks or a steel frame per previous step 4 on page 92 with the crane holding approximately 80% of the load. Figure 84: Tower on wood blocks 5. Ensure the load is stabilized, check the stability of the wooden blocks and soil. 6. If stability is OK, proceed to remove the tail pick lifting equipment. 7. Release the connection from the support crane to the hooking points on the bottom tower flange. 8. Remove the hoisting rings from the bottom tower flange. Figure 85: Removing the hooking points 9. Lash two tag lines to the bottom tower flange. Lash a tag line to each of two opposed points, in order to prevent the section from swinging during the lifting operation. This allows the section to be guided without danger. Figure 86: Tag line on the tower flange CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 99/428 GE Renewable Energy Installation Manual – Original – 8.1.4 Assembling the First Tower Section 1. Ensure that the arrangement of the nuts, bolts, washers is correct. The level of the washers must always point towards the nut and bolt head respectively. Figure 87: Arrangement of the bolts 2. Apply a 12 mm Sikaflex®-252 or a comparable sealing material between the outer edge and the holes of the tower base ring. Figure 88: Applying Sikaflex®-252 ATTENTION Danger of collision! Lower the tower section slowly and carefully. A collision between the tower section and the platform must be avoided, since this could cause damage. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 100/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual DANGER Falling hazard! Ensure that you are always protected by your PPE when carrying out work on the PPM. Use the hooking points marked in signal yellow which are located on each platform (section). ATTENTION Overhead suspended load! Never work under a suspended load. Always confirm accurate load center of gravity, lifting gear and equipment securely attached, Make sure all personnel, vehicles, equipment, and materials are clear of the crane tail and load swing. All lifting must be done in strict accordance with the installers lift plan and applicable job safety analysis must be reviewed prior to all lifts. 8.1.4.1 Installing the Guide Rail System The guide rail system will be attached to the controller and transformer level posts located on the opposite side of the tower entry door. The controller level guide rail system can be installed on the controller level prior to installing the controller converter over the transformer, this way the work is done closer to the ground. The transformer rail posts can be installed later after the controller/converter is placed over the transformer. This way the team will not fight alignment of the posts when staking the PPM. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 101/428 GE Renewable Energy 1. – Original – Installation Manual Verify all guide rail system parts are accounted for and in good condition. Reference drawing D7988-10 Main Assembly PPM Rail System. Quantity Description 1 Top left rail post 1 Bottom left rail post 1 Top right rail post 1 Bottom right rail post 2 Bottom left rail clamps large size rail clamps part# 8 2 Bottom right rail clamps medium size rail clamps part# 8 6 Controller level rail clamps small size part #7 Part #7 controller small clamps, 3 each. Part #7 controller level small clamps, 3 each. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 102/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual Part# 6, transformer level (Bottom left large rail clamps) 2 each. Part# 8, transformer level (Bottom right small rail clamps) 2 each. Part#3 Top left rail post Part#3 Top right rail post Part#4 Bottom left rail post Part#5 Bottom right rail post CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 103/428 GE Renewable Energy Installation Manual – Original – 8.1.4.1.1 Assembling the Rail Assembly 1. Assemble the controller level LH and RH rail assembly. Attach part #7 to part #3 and secure with carriage bolt nut and washer. Tighten the hardware. Part #7 Part #3 Figure 89: Controller level LH and RH rail assembly. 2. Assemble the transformer level LH rail assembly. 3. Top bracket part#7: Attach part #7 to the top of part #4 and secure with carriage bolt nut and washer. Tighten the hardware. 4. Lower brackets part#6: Attach part #6 to the lower and middle brackets of part #4 with gusset facing down and secure with carriage bolt nut and washer. 5. Leave the hardware loose to allow part# 6 brackets to pivot. Top Bracket Part #7 Part #4 Lower Brackets Part #6 Figure 90: Transformer level LH rail assembly. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 104/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – 6. Assemble the Transformer level RH rail assembly. 7. Top bracket part#7: Attach part #7 to the top of part #4 and secure with carriage bolt nut and washer. Tighten the hardware. 8. Lower brackets part#8 (large Brackets): Attach part #8 to the lower and middle brackets of part #5 with gusset facing down and secure with carriage bolt nut and washer. 9. Leave the hardware loose to allow part# 8 brackets to pivot. Top Bracket Part #7 Part #5 Lower Brackets Part #8 Figure 91: Transformer level RH rail assembly. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 105/428 GE Renewable Energy Installation Manual – Original – 8.1.4.1.2 Installing the Controller Level Guide Rail System 1. Measure and mark the Controller Level posts located on the opposite side of the tower entry door. 1080 mm 74 mm 63.5 mm 1080 mm Figure 92: Marking the controller post CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 106/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – 2. Position the LH upper rail assembly primary support against the left hand side post of the controller level. 3. The tapered end of the post is pointing down. B A - Primary support A B - Controller level LH post Figure 93: Positioning the rail post against the controller post 4. Position the magnet latch arm assembly on the backside of the post. A - Primary support B - Magnet latch assembly A B Figure 94: Positioning the magnet latch assembly CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 107/428 GE Renewable Energy 5. Latch the primary support to the magnet latch assembly. 6. Adjust the latch bolts as required to prevent the latches from disengaging and/or over stressing and damaging the latches. Installation Manual – Original – Figure 95: Rail system latches to magnet latch assembly 7. Adjust the rail assembly as required and latch the next primary support to the controller post. Figure 96: LH controller post CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 108/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 8. – Original – Installation Manual Repeat steps to install the RH rail assembly on the RH controller post. Figure 97: RH controller post 9. Insert the pins to prevent the latches from disengaging. Figure 98: Securing rail system latches with safety pin CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 109/428 GE Renewable Energy Installation Manual – Original – 8.1.4.1.3 Installing the Transformer Level Rail Assembly 1. If required measure and mark the transformer Level posts located on the opposite side of the tower entry door. 63.5 mm 972 mm 867 mm 2. Position the RH rail assembly primary support against the bottom of the RH side post of the controller level. 3. Push the post up inserting it onto the tapered end of the upper rail assembly post. C 4. If required remove the carriage bolt and reinstall after the primary support is latched against the post. D B A Figure 99: Securing RH lower brackets part#7 (small brackets) A - Carriage bolt B - Controller level upper rail assembly post C - Controller level RH Post D - RH rail assembly primary support CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 110/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 5. Position the magnet latch arm assembly on the backside of the post. Installation Manual – Original – A A - Magnet latch assembly B - Primary Support B Figure 100:Securing LH lower brackets part#7 (small brackets): 6. Latch the primary support to the magnet latch assembly. Adjust the latch bolts as required to prevent the latches from disengaging and/or over stressing and damaging the latches. Figure 101: Rail system latches to magnet latch assembly CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 111/428 GE Renewable Energy 7. – Original – Installation Manual Adjust the rail assembly as required and position the lower two primary supports against the transformer post. Figure 102: Securing RH lower brackets part#6 (medium brackets): CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 112/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 8. – Original – Installation Manual Repeat steps to position the LH rail assembly. Figure 103: Securing lower brackets part#8 (large brackets) 9. Ensure all pins are correctly inserted to prevent latches from disengaging. Figure 104: Securing rail system latches with safety pin CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 113/428 GE Renewable Energy – Original – Installation Manual For reference: The following drawings show the rail assembly location in relation to the anti-rotation devices mounted to bottom flange of the base section. These illustrations apply to tower configurations 75/85 m HH, 98.3 m HH, 110 m HH or 120 m HH and 131 m HH respectively. NOTE Typical view is from the top of tower looking toward the ground. Figure 105: Tower flange bolt hole configurations for 75/85 mHH, 98.3 HH, or 110/120 m HH. For 131m request latest version from GE engineering. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 114/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 8.1.4.2 Installing the Base Section over the PPM 1. Rearrange the converter to transformer cables out of the walkway and/or the tower flange path to prevent damage. 2. Rearrange the grid to transformer cables away from tower flange path to prevent damage. Figure 106: Securing thec ables 3. Remove the grounding boss bolts prior to installing the base section to prevent cable damage when installing the tower section over the PPM. Figure 107: Ground boss location on the flange 4. Verify hole 1 on the tower base ring is clearly identified. This hole matches the tower center line mark provided by customer and will align with hole 1 of the tower base flange. NOTE Typical customer door center line is marked by the customer's foundation contractor and is located at 90 degrees from the foundation conduits. 5. Mark the inside and outside face so that the marks are clearly visible during installation of the base section. Figure 108: Example TBR with customer provided tower door centerline marks CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 115/428 GE Renewable Energy Installation Manual – Original – 6. Prior to lifting the tower base section identify and mark hole 1, this is located on the tower flange centered directly below the tower door. 7. Place a mark with duct tape on the outside face of the tower flange so that the marks are clearly visible during installation of the base section. Figure 109: Tower base door center line marks 8. Prior to lifting the tower install four taglines to help stabilize the tower when guiding the tower over the PPM. Figure 110: Install four taglines CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 116/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual DANGER Crushing hazard! Do not put your hands between the flanges. Danger of serious crush injuries. Ensure that you keep a safe distance from the flanges. During Installation always ensure that hands, feet, and body are not between any potential pinch points. 9. The tower section will be positioned over the PPM using the rail system to maintain tower stability while guiding the tower over the converter cabinet without causing damage. 10. Supporting personnel will be positioned at each corner holding tension on the tag lines to maintain control of the base section while it is being lowered. 11. Instruct the crane operator to bring the tower section slowly over the PPM. Figure 111: Lowering the first tower section CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 117/428 GE Renewable Energy – Original – Installation Manual 12. Instruct the crane operator to slowly lower the tower section over the PPM until the anti-rotation plates make contact with the rail system. Figure 112: Lowering base until anti-rotation plates make contact with the rail system. 13. Instruct the tag line personnel to maintain slight pressure from the tower base flange to the PPM guide rails as the base section is being lowered over the PPM/converter cabinet. Figure 113: Base section being lowered over the PPM/converter cabinet CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 118/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 14. Instruct the tag line personnel as required to maintain tension to ensure the tower flange clears the ladder and all other PPM components as it is being lowered. 15. The foreman directing the lift needs to ensure that no excessive pressure is being applied to the guide rail system and the load is floating barely touching on the way down. Figure 114: Load is floating barely touching on the way down. 16. Place four wood blocks of the appropriate size. 17. Firmly lower the base onto the woodblocks with the crane holding the load, aligning the pins to the TBR holes and ensuring the tower door flange marks are aligned. Critical to Safety: The bull pins keep the tower section from being moved during wind gusts and prevents pinch points. 18. Remove the tag lines and the antirotational devices. Figure 115: Bull pins to keep the tower section aligned CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 119/428 GE Renewable Energy Installation Manual – Original – Critical to Quality: 19. Ensure that the tower base door is correctly aligned with the mark on the tower base ring flange. A A - Base flange door B - Tower base Ring flange door mark B Figure 116: Base flange and TBR doo marks CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 120/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 20. A ladder is placed inside the PPM prior to the base being installed. It is resting against the PPM and then positioned to the tower wall (door combing) for access to the transformer level. We have ample clearance due to not installing the fan/duct work under the tower door until after tower installation. - A man lift can be used for entrance as well. DANGER Danger of falling down! Once the tower base section is installed there is a Danger of falling through open floors due to uninstalled hatches and floor plates. Figure 117: Temporary ladder placed outside to access tower Use extreme caution when accessing the tower and transformer level! 21. The blocks need to be removed to complete the application of the Sikaflex®. Once the blocks are removed the Sikaflex® can be applied safely by a crew member from the outside. 22. The bull pins stay engaged while the blocks are removed. The blocks are pushed out with a bar from the inside to prevent hands/body parts from crushing hazard. Figure 118: Removing the blocks and guide pins inserted tp TBR. DANGER Crushing hazard! During removal of woodblocks and application of Sikaflex® always ensure that hands, feet, and body are not between any potential pinch points. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 121/428 GE Renewable Energy Installation Manual – Original – Critical to Quality: 23. Keeping hands away from danger zone carefully apply a continuous (NO GAPS) 12 mm bead of Sikaflex® or equivalent on the remaining face at the top flange of the tower base section. Cover the area between the outside edge and the holes ensuring no gap so water cannot penetrate inside the tower. Figure 119: Application of Sikaflex®. Critical to Quality: 24. Ensure that the door is correctly aligned. B A - Foundation bolt door marks B - Base section hole 1 mark C - Tower base ring hole 1 mark C A Figure 120: Example tower door markings 25. Instruct the crane operator to lower the tower section down further. Figure 121: Tower flanges small gap outside CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 122/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 26. Lower the tower section but leave a small gap of approx. 10 cm. The gap provides some room for maneuvers to insert all the bolts. 27. Insert all the bolts in the flange. The bolts are pushed through the flange from below and the nut is tightened from above. 28. Once all the bolts are finger-tight, the tower can be let down completely. Figure 122: Tower flange small gap inside CAUTION Wear hearing protection! Proper hearing protection must be worn when working with any electrical or hydraulic impact tooling! Always assess the next task at hand. If 85 decibels will be exceeded, hearing protection must be worn. Observe requirements for hearing protection per your company's policies. DANGER Pinch point - Crushing hazard! When working with hydraulic and pneumatic torque tooling, ensure that your hands and any part of your body are not between any pinch points (i.e. any part of your body is not between the tool reaction arm and back up pressure surface). Ensure personnel are properly trained on safe operations of hydraulic and pneumatic tools. 29. Using an impact wrench tighten all bolts in a star pattern/rolling triangle. Reference the 3MW Platform Bolt Torque Specification for final torque. Figure 123: Impact wrench CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 123/428 GE Renewable Energy Installation Manual – Original – DANGER Danger of collapse! Only after all bolts have been tightened by means of the impact wrench the lifting gear can be detached. 30. Remove the lifting gear from the top tower flange. 31. If required after base tower installation the service platform (lift) must be put on the base tower upper platform for later installation. 32. Remove the guide rail system, secure all hardware for future use. Figure 124: Removing the lifting gear DANGER Pinch point - Crushing hazard! When working with hydraulic and pneumatic torque tooling, ensure that your hands and any part of your body are not between any pinch points (i.e. any part of your body is not between the tool reaction arm and back up pressure surface). Ensure personnel are properly trained on safe operations of hydraulic and pneumatic tools. 33. Perform the final torque using qualified torque tooling and mark with a paint pen. Legibly record torque values in 3 locations: ICL, Daily Torque Log and on the tower wall next to the flange bolts directly across from, the ladder. 34. Details of the required torques can be found in the 3MW Platform Bolt Torque Specification. 35. Verify no gap is present between the tower flanges. 36. If a gap is present, do not proceed until the gap is closed, ensure Sikaflex® was applied properly and contact a GE Energy site representative for further instructions CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 124/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 37. Remove any paint residues or dirt from the ground straps boss to ensure perfect contact of the ground strap with the tower sections. Figure 125 38. Mount the ground straps between the tower flange sections. Torque the bolts and mark them with a paint pen. Figure 126 8.2 Installing the Entrance Stairway WARNING Fall hazard! When the stairs cannot be installed due to space limitations between rotor and stairs, the installer must provide temporary safe means of egress to the tower that meet the local standards. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 125/428 GE Renewable Energy Installation Manual – Original – 1. Pre-assemble the modules on a horizontal surface (e.g. trailer) beginning with the longest modules at the top of the stair (1, 2) and consequently adding module (3). 2. The single step module (4) can only be mounted at the bottom of the stair. 3. Support the stairway on point "A". 4. Add the top module (5). 5. Check the complete stair assembly for loose hardware/damage prior to installing. 6. Attach round slings to the stairway at point "B" and secure them against shifting. Figure 127: Pre-assembling the modules of the stairway Figure 128: Adding the top module Figure 129:Lifting the stairway 7. Lift it slowly towards the door section by means of a crane or similar. Figure 130: Lifting the stairway CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 126/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 8. – Original – Installation Manual Tighten the hardware with an impact wrench. Do not exceed final torque. Torque all bolts and mark with paint pen. Figure 131 9. Adjust the stairway as required so the top platform at the entrance door is horizontal. Figure 132 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 127/428 GE Renewable Energy – Original – Installation Manual 10. If foundation dimensions do not fit, add or remove optional single step modules. Figure 133 11. If applicable, install tower door stair ground lead. Ensure mating surface is clean, torque and mark with paint pen. 12. Connect the grounding cable at the bottom of the stairway. Figure 134 13. Temporarily support the ladder legs ensuring the ladder is level until final grading done. Figure 135: Installation of the stairway completed CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 128/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 8.3 Adjusting the Entrance Door 1. Adjust the entrance door according to the adjoining figure. Figure 136: Adjusting the entrance door (1) 2. Adjust the entrance door according to the adjoining figure. Figure 137: Adjusting the entrance door (2) 3. Adjust the entrance door according to the adjoining figure. 4. Secure the tower door to prevent unauthorized entry i.e., (install a key lock cylinder). Figure 138: Adjusting the entrance door (3) CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 129/428 GE Renewable Energy Installation Manual – Original – ATTENTION The transformer coils and all other equipment must remain protected from elements such as moisture, rain, snow, contaminants such as dirt, dust, oil, rodents and damage during installation process. The installer must hold available protection material for storage e.g., tarps shrink wrap - taking into consideration condensation and freezing weather. If grid is not available after tower installed and extreme weather is anticipated, it is recommended to temporarily seal tower door filter inlets to prevent snow/dust from entering the tower. 8.4 Completing the PPM Assembly DANGER Falling hazard!! Once the tower base section is installed there is a Danger of falling through open floor due to uninstalled hatches and flaps. Close these before beginning the work! CAUTION Know what you are lifting! When the weight exceeds the limit for a single person, or if the load is awkward / difficult to maneuver due to shape or size. Request the help of a second person, Transfer the load into smaller containers or use the crane or a fork lift. Reference assembly drawings for weights. 1. Verify all hatches and hand rails are accounted for and in good condition. Contact GE site representative if any issues are found. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 130/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual DANGER Falling hazard!! Once the tower base section is installed there is a danger of falling through open floors due to uninstalled hatches and floor plates. Close open holes before beginning the work! DANGER Falling hazard!! Use caution when walking into the tower to install the floor plates or performing any other work. 2. Remove the transport shipping braces. 3. Remove the transformer shipping braces. Figure 139 Figure 140 4. Inspect for any loose hardware and debris inside the coils. Figure 141 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 131/428 GE Renewable Energy 5. – Original – Installation Manual Assemble the hatches, steps and railings at the controller level according to installation drawing 117W6882/444W8673. For 131 m request latest version from GE engineering. Figure 142 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 132/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 6. Install the controller/transformer ladder mounting bracket to the controller platform. Reference Drawing 117W6917/444W7063/ 444W9057. 7. In the transformer level install the foundation step. 8. Mount the two ladder mounting brackets. – Original – Installation Manual Figure 143 9. Position the ladder against the upper and lower mounting brackets, and install the hardware. 10. Tighten the hardware according to torque values provided in the assembly drawing. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 133/428 GE Renewable Energy – Original – Installation Manual Figure 144 11. Install the fan covers on converter fans. Tighten the hardware. Reference the latest ESS DTA drawing. 12. Remove all the shipping material from the covers. Figure 145: Assembling shrouds on converter fans CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 134/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 13. Assemble the fan shrouds around the converter fans. Reference the latest ESS DTA drawing. 14. Remove all tools debris from the fan shroud Figure 146 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 135/428 GE Renewable Energy – Original – Installation Manual 15. Assemble the earthquake absorbers (pos. nos. 15, 16, 17 and 70, 72, 75, 76, 77) at the controller level according to assembly drawing 117W6882/444W8673. For 131m request latest version from GE engineering. Figure 147: Assembling earthquake absorbers at the controller level CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 136/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 16. Uncoil the converter coolant drain hose. 17. Connect it to the bottom of the converter. 18. Route the hose down through ladder trays and place the other end inside the drain barrel in the transformer level. Figure 148: Converter coolant drain hose at the transformer level. 19. Verify all cooler fans parts are accounted for. Contact GE site representative if any parts are missing. NOTE Cooling fan design could be different. Refer to the specific turbine configuration to determine task applicability. Figure 149 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 137/428 GE Renewable Energy Installation Manual – Original – 20. Install the cooler fan under tower door floor plate according to assembly drawing 117W5906 (Assembly Ventilator). A B C Figure 150: Installing the cooler fan under tower door A - Air duct B - Fan motor C - Tower door floor plate 21. Unbolt and lift the tower door floor plate. DANGER Falling hazard!! Danger of falling through open hatches and flaps. Close these before beginning the work! Figure 151: Removing the door floor plate. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 138/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 22. Install the fan motor and air duct and tighten the hardware according to assembly drawing. NOTE Support the cooler fan duct during installation with a rope or similar to prevent accidental movement. Figure 152: Installing the cooler fan under tower door 23. Reinstall the door floor cover, adjust for correct clearance and tighten hardware. Figure 153: Installing coolers and hoses at the transformer level CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 139/428 GE Renewable Energy – Original – Installation Manual 9 Assembling the Following Tower Sections WARNING Take care when working on the low-loading trailer! Work on the loading platform of the low-loading trailer may only be carried out when it is stationary. All personnel must leave the loading platform before the low-loading trailer is moved. ATTENTION Check the wind speed! The tower may only be erected in accordance with section 4.1 ‘Operations Involving the Use of a Crane’. ATTENTION Prevent damage from the WTGS If the nacelle cannot be mounted immediately and the "open" tower has to remain without a nacelle (e.g. overnight), only three tower sections may be mounted In this case, the top tower flange must be protected against the effects of the weather by suitable means. WARNING Overhead suspended load! Never work under a suspended load. Always confirm accurate load center of gravity, lifting gear and equipment securely attached. Make sure all personnel, vehicles, equipment, and materials are clear of the crane tail and load swing. All lifting must be done in strict accordance with the installers lift plan and applicable job safety analysis must be reviewed prior to all lifts. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 140/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual WARNING Lifting heavy loads! Prior to lifting all heavy loads, a pre-lift meeting with all parties involved is required. (The crane operator, the rigger, the supervisor, the signalman, and any other personnel involved, such as area safety, tag line holders). All lifting must be done in strict accordance with the installers lift plan and applicable job safety analysis must be reviewed as well. DANGER Crushing hazard! During Installation always ensure that hands, feet, and body are not between the any potential pinch point. WARNING Risk of Falling objects! Never remain in front or underneath the tower opening. Whilst the tower is being erected any object or material that remains in the tower or inadequately secured cable can fall out of the tower. The process requires lifting and lowering equipment inside the tower and working with, and staging, tools and materials on all tower platform levels. There are many gap openings around the platforms and possible open personnel and tool hatches. Personnel will be working with small parts and tools which can fall through the holes or open hatches. Always ensure all equipment and tools are secured in closed tool bags. All tools will be secured and tether rope will be utilized as required Cover all hole openings that create a risk of falling objects as required. All tower internal tool/materials hoisting operations must be performed by properly trained personnel using the properly rated hoisting equipment, rated certified lifting bags, hooks with safety latch. Before use, take a moment to inspect all hoisting equipment and bag(s) to ensure there is no damage, cuts/tears, or signs of excessive rubbing/wear. Lifting equipment will be carefully coordinated. Two-way communication must be available via radio. All non-essential personnel must clear the area before hoisting operations begin. Never remain in front or underneath the tower opening. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 141/428 GE Renewable Energy Quantity – Original – Installation Manual Description 2 AC extension cord, 100’ 2 Bucket, canvas, 5 gallon 1 Bull pin to align flanges ar Cable tie, ship loose 1 Caulking gun 1 Container, gasoline ar Crimp tool – vendor specific 1 Cutter, cable (safety cable) ar Decals, warning label ar Die set- vendor specific 2 Duffel bag, canvas 1 File set, various, 12” 1 Generator, 6.5 kW with GFCI ar Heat shrink, ship loose 1 Ladder, extension, 16’ 1 Ladder, step, 10’ ar Lubricant, spray 1 Mop, sponge, heavy duty ar Paint pen, purple ar Paint, tower touch up, exterior ar Paint, tower touch up, interior 1 Pressure washer, with 120’ hose 3 Radio, two-way ar Rags 1 Ratchet, ½” drive ar Rigging ar Sandpaper, medium grit 1 Screwdriver set ar Sikaflex®, 262 1 Socket, 60 mm, ½-inch drive 1 Socket, deep, 24 mm, ½-inch drive ar Splices, ship loose 1 Stripper, cable 2 Tagline, nylon rope ar Tape, electrical CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 142/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Quantity – Original – Installation Manual Description 1 Torch, propane or heat gun 1 Water tank, 500 gallon 1 Qualified wrench, torque, hydraulic or electric 1 Wrench, combination, 2-3/8 inch 3 Wrench, combination, 24 mm 2 Wrench, combination, 50 mm 1 Wrench, combination, 9/16 inch 1 Wrench, impact, 1” drive 9.1.1 Inspecting the Tower Section 1. If the tower will be immediately installed remove the transport tarp and the tower straps from the tower flange. Fold up the transport tarp. Leave tarp and tower straps on if the tower will remain in storage. 2. Perform the Tower Receiving Inspection. Inspect the tower for signs of shipping damage. Contact the GE site representative if damage is found. 3. Visually inspect all bolted connections for attaching the platform and ladder to the tower wall, the cable tray to the tower wall and cable clamps to the tray, the fall arrest system to the ladder or safety cable stand-offs to the ladder. 4. If any tower internal loose bolts are found, contact GE site representative. The bolt will have to be removed and will have to be replaced with a new bolt with new thread locker and then torqued to the right torque in accordance with the tower internals assembly manual. NOTE Tower internal hardware is glued with thread locking. If it gets checked with torque, the thread locking will be disturbed and the bolt may become loose during WTG operation. 5. Inspect the fall arrest system mounting hardware and inspect the safety cable for kinks or cuts. 6. If the cable is damaged contact GE's site representative. 7. Inspect the interior, exterior, and flanges for exposed metal surfaces, corrosion, burrs, and high spots. Critical to Safety: 8. On the tower top section verify the tower hoist is properly mounted onto the tower frame. Inspect all hoist mounting brackets looking for missing or cracked welds. Refer to the hoist manufacturer's installation/mounting instructions. Critical to Safety: CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 143/428 GE Renewable Energy 9. – Original – Installation Manual If Service Lift option is required, check if handrail gates are installed. If not, install handrail gates according to the supplier instruction. Handrail gates are part of the Service Lift kit. 9.1.2 Preparing the Tower Section DANGER Fall hazard! Tower internal surface can represent a slippery surface during cleaning operations. Please be aware of the work environment and try to mitigate the risk by avoiding to walk over slippery surfaces. NOTE Note the arrangement of the transportation braces! The exact arrangement of the transportation braces is specified by a banksman or the site lead. 1. Remove burrs and high spots using a course half-round file and buff the surface using medium grit sandpaper. Remove corrosion using medium grit sandpaper and spray cold galvanize compound. 2. Repair any minor damaged paint surfaces preparing surface and applying the paint or primer per manufacturer’s instructions. 3. Any major paint damage must be reported to GE representative and repaired in accordance with the manufacturer's instruction. Tower Cleanliness: 4. Tower internal cleaning: Any loose, lightly imbedded or accumulated dirt/debris must be removed from the tower internal surfaces to prevent short or long term contamination by falling down tower to the electrical components. 5. Tower external cleaning: Any material or contaminate that affects the life expectancy of the coating and any accumulated mud or other material that can become dislodged during operation must be removed. Cosmetic appearances are the customer’s decision for level of cleanliness. E – EL Contracts: Cosmetic appearances are the customer’s decision for level of cleanliness. ELI – ELIF – ELIFT Contracts: Cosmetic appearances are GE´s decision for level of cleanliness if WTG installation is in GE scope. It is recommended that cleanliness is clearly defined and understood by all parties prior to first unit installation preferably during the pre-installation meeting (PIM). CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 144/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 6. – Original – Installation Manual Verify the cables are secured in the cable tray with ties and clamps. Verify the cables are secured below the deck to prevent damage to the cables and PPM. Figure 154: Example for securing of the cables 7. Install the fall arrest system or check the pre-assembled fall arrest system as per manufacturer’s instructions before erecting the tower section. 8. Fall restraint system is required to allow ascent to the top of the segment. WARNING Falling hazard!! If the fall arrest system is not available a temporary fall arrest system must be provided by the installer and removed after the permanent fall arrest system is installed. This applies to all mid sections. Figure 155: Temporary fall arrest system tower mid-section segments Despite the temporary system a certified tieoff point must be used at all times. Figure 156: Top section fall arrest system CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 145/428 GE Renewable Energy 9. Installation Manual – Original – After the tower section is stacked, position the parts (bolts, nuts, washers, sealing material, cable crimps, shrink sleeves etc.) and tools needed to make the connection to the next tower section on the platform of the tower section currently being prepared and secure them against falling off. 10. Do not exceed the weight rating of the platform, parts and tools must be evenly spread on the platform and must not interfere with opening the hatch. Figure 157: Positioning the parts and tools on the platform 11. For the top section verify the hoist is secured with all the hardware marked as torqued. Figure 158 NOTE Repeat this section for towers with additional tower sections. 9.1.3 Attachment and Usage of the Lifting Gear Depending on the variant of the lifting gear used, repeat the steps in sections 8.1.3.1 Plate Lifting Gear 8.1.3.2 HTS ACTEK WKA System. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 146/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 9.1.4 Installing the Tower Section 1. Position the parts (bolts, nuts, washers, sealing material, cable crimps, shrink sleeves etc.) and tools needed to make the connection to the next tower section on the platform of the tower section currently being prepared. If this is a top section the permanent fall arrest system must be lowered down the ladder and secured at the bottom of the top section. Figure 159: Positioning the parts and tools on the platform Figure 160: Positioning the parts and tools on the platform 2. If applicable, before lifting the top section, prepare the tower section to avoid the effect of wind induced tower vibrations transverse. Reference Installation of Coil Avoiding Wind Induced Tower Vibrations Transversal to the Wind Direction 3MW.X_Tower(System)_Tower Vibration Avoidance System Installation. Figure 161: Example rope fixed and coiled around the tower CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 147/428 GE Renewable Energy 3. – Original – Installation Manual Apply 12 mm Sikaflex®-252 or a comparable sealing material between the outer edge and the holes of the previously installed tower section. This prevents moisture entering into the tower from the outside. Figure 162: Applying sealing agent to the flange 4. Instruct crane operators to lift the tower into the upright position. Figure 163 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 148/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – 5. Remove the tail pick crane rigging. 6. Instruct the crane operator to slowly lower the tower section over the previously installed tower section. 7. Guide the tower section by means of the tag lines, in order to prevent it from swinging. The tower section is received by two erecting engineers protected by safety devices standing on the tower platform of the first tower section. This facilitates the subsequent alignment of the tower section. Installation Manual DANGER Fall hazard! Personnel must be 100 % tied off and clear of the load at all times. Figure 164: Lifting the tower section WARNING Crushing hazard! Once the tower reaches the appropriate elevation, personnel must stay below the flange, until the tower section is near or directly over the tower to be installed. Do not reach outside the tower flange perimeter. Always ensure that hands, feet, and body are not between any potential pinch points. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 149/428 GE Renewable Energy Installation Manual – Original – 8. Giving precise instructions to the crane operator, lower the tower section until one flange is positioned above the other as shown in Figure 165. 9. Turn the tower section until the hole patterns of the flanges are lined up with each other and the two flanges can be fixed in position with four bolts. 10. Insert four opposed bolts in the tower flange to serve as fixing aids. 11. Insert ladder and rail joints. Take good care that the segments of the ladder and the rail of the fall protection system are well aligned and joined properly. Figure 165: Aligning and fixing the tower in position 12. Lower the tower section but leave a small gap of approx. 10 cm. The gap provides some room for maneuver to insert all the bolts. 13. Insert all the bolts in the flange. The bolts are pushed through the flange from below and the nut is tightened from above. Figure 166: Connecting the flanges using bolts 14. Ensure that the arrangement of the nuts, bolts, washers is correct. The bevel of the washers must always point towards the bolt head and the nut respectively. Once all the bolts are finger-tight, the tower can be let down completely. Figure 167: Alignment of the washers CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 150/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual CAUTION Wear hearing protection! Proper hearing protection must be worn when working with any electrical or hydraulic impact tooling! Always assess the next task at hand. If 85 decibels will be exceeded, hearing protection must be worn. Personnel must wear ear protection when noise levels reach or exceed local regulations. Observe requirements for hearing protection per your company's policies. WARNING Pinch point - Crushing hazard! When working with hydraulic and pneumatic torque tooling, ensure that your hands and any part of your body are not between any pinch points ( e.g. any part of your body is not between the tool reaction arm and back up pressure surfaceEnsure personnel are properly trained on safe operations of hydraulic and pneumatic tools. 15. Using an impact wrench tighten all bolts in a star pattern/rolling triangle. Reference the 3MW Platform Bolt Torque Specification for final torque. 16. Mount the ladder splice section between the base and the mid and splices as required on additional tower mid sections. 17. Connect the ladder between the tower sections and torque the bolts to 25-30 ft-lbs. For Haka rail climb system, install splice plates to top and mid section connection. Install the u-bolt to the ladder rung. Figure 168: Tightening the flange bolts DANGER Danger of collapse! Only after all the bolts have been tightened by means of the impact wrench the lifting gear can be detached. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 151/428 GE Renewable Energy Installation Manual – Original – 18. Remove the lifting gear from the top tower flange. If this is the topmost section lower the safety cable to the bottom of the tower. 19. Remove the temporary fall arrest system from tower section. Figure 169: Removing the lifting gear 20. Now tighten all the bolts to the required torque by means of a hydraulic low-clearance wrench. 21. Details of the required torques can be found in the 3MW Platform Bolt Torque Specification. Critical to Quality: 22. Verify no gap is present between the tower flanges. 23. If a gap is present, do not proceed until the gap is closed, ensure Sikaflex® was applied properly and contact a GE Energy site representative for further instructions. DANGER Pinch point - Crushing hazard! When working with hydraulic and pneumatic torque tooling, ensure that your hands and any part of your body are not between any pinch points (e.g. any part of your body is not between the tool reaction arm and back up pressure surface). Ensure personnel are properly trained on safe operations of hydraulic and pneumatic tools. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 152/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 24. Remove any paint residues or dirt from the ground straps to ensure perfect contact of the ground strap with the tower sections. 25. Mount the ground straps between the tower sections. Torque the bolts and mark them with a paint pen. Write the torque data on tower wall. 26. Write torque data next with flange bolt torque/10 % torque values. Figure 170: Ground straps 27. Install the deflector plates to the tower wall below the tower flange connections. Figure 171: Example flange deflector plate Figure 172: Deflector plates below the tower flanges CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 153/428 GE Renewable Energy Installation Manual – Original – 28. Uncoil and lower the safety cable to the bottom of the tower base section. Care must be taken to ensure that the safety cable is not kinked. 29. Thread the cable through the eyebolt. Install the thimble, remove all of the slack in the cable and tighten the clamps (2 each). Ensure the cable clamps are oriented correctly U-bolt “saddle” is positioned against the cable going up the tower and the U-bolt positioned against the short end of the wire (never saddle a dead horse). Figure 173: Painting the flanges 30. Tension the safety cable until the sway is removed (do not over tension). Cut off excess cable using steel cable cutters. Leave a two-inch tail. To prevent injury wrap electrical tape around the end of the cable tail until there is not exposed strands. Refer to the fall arrest manufacture technical manual for final inspection of the fall arrest system. 31. Remove the temporary fall arrest system from all previous segments. Figure 174: Fall arrest cables attched to the bottom of the tower CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 154/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 9.2 Corrosion Protection 1. The flanges on all sections are subsequently painted again to guarantee reliable corrosion protection. Review SDS and make sure to wear appropriate PPE. Figure 175: Painting the flanges 9.3 Checking/Adjusting the Railing Doors 1. Open the railing door up to 90° and check if it closes automatically. 2. If not, check if the hinges are installed in accordance with the supplier manual. 3. If not, adjust the upper hinge ('A' including spring element) to be parallel to the door and railing. 4. Adjust the lower hinge 'B' in exactly the same way as the upper hinge, except both parts must be angled approx. 35° to the outside. 5. Check if the catch 'C' closes properly. If not, adjust it accordingly. 6. Check the handrail for loose mounting hardware and tighten as required. Figure 176: Checking/adjusting the railing doors CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 155/428 GE Renewable Energy – Original – Installation Manual 10 Nacelle NOTE Rotors with 2900 hub are installed utilizing the Single Blade Installation Method (SBI). Reference the single blade installation and the Temporary Yaw and Gearbox oil pump systems GEI for: Installing the unbalanced rotor turning gear before the nacelle leaves the ground. Qualified installation personnel to work with a GE site representative to help Identify power source to the top box to enable the Yaw and Gearbox oil pump systems. NOTE If generator is shipped separately, install the Generator according to 2.X_Machine Head_Generator. Install on the Ground and high-speed coupling according to Coupling specific vendor technical specifications. WARNING Risk from overhead suspended load/Crushing hazard! Be aware of transport trailer Air ride systems! Do not access through nacelle bottom hatch if air ride is being adjusted. The nacelle has to be accessed through the roof hatch. Quantity Description 2 AC extension cord, 100’ 2 Bar, connecting, 2’ ar Bolts, nuts, and washers 2 Bucket, canvas, 5 gallon 1 Caulking gun 1 Container, gasoline 2 Duffel bag, canvas 1 File set, various, 12” 1 Generator, 6.5 kW with GFCI 2 AC extension cord, 100’ CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 156/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Quantity – Original – Installation Manual Description 2 Bar, connecting, 2’ ar Bolts, nuts, and washers 2 Bucket, canvas, 5 gallon 1 Caulking gun 1 Container, gasoline 2 Duffel bag, canvas 1 File set, various, 12” 1 Generator, 6.5 kW with GFCI 1 Knife, putty 1 Ladder, extension, 16’ ar MoS2 anchor brand jet lube, spray (For galvanized bolts only reference the bolt torque specification) 1 Mop, sponge, heavy duty ar Paint pen, purple 1 Pressure washer, with 120’ hose 3 Radio, two-way 1 Ratchet, ½-inch drive ar Rigging ar Sandpaper, medium grit ar Sikaflex®, 262, ship loose 1 Socket, 46 mm, ½-inch drive 1 Socket, 50 mm, ½-inch drive 1 Socket, deep, 19 mm, ½-inch drive 1 Socket, deep, 24 mm, ½-inch drive 2 Tagline, nylon rope, 500’ (150 m ¾" for 80 m HH and up to 200 m ¾" for 100 m HH tower) 1 Water tank, 500 gallon 1 Wrench, Allen, 10 mm 1 Wrench, Allen, 12 mm 1 Wrench, combination, 24 mm 1 Wrench, combination, 50 mm 1 Wrench, crescent, 12-inch 1 Wrench, impact, 1-inch drive 1 Qualified wrench, torque, hydraulic or electric 1 Socket, 60 mm, 1-inch drive (for 1.x-100/103) CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 157/428 GE Renewable Energy Installation Manual – Original – Recommended or Equivalent Temporary Fall Protection Parts Americas Quantity Description 1 3/8 lifeline with snap hook 30 ft. (5901003) 1 4 ft. sling (shocker) WLL 5000 lbs 1 5/8 bolt type anchor shackle 3-1/4 t WLL 1 12 inch softener ar Wire rope clips ar Thimble ar Cable tie Temporary Fall Protection Parts Europe Quantity Description 1 Aluminum pipe hook RHK 60 with stitched rope termination with identification label serial number 1 Guided-type fall arrester SK 12- 16 1 Work positioning rope as per EN 358 12 or 14 mm core sheathed rope 1 Strap-type energy absorber as per EN 355 EN 355 NOTE A temporary fall arrest system may need to be installed for protection while transferring from the yaw deck to the nacelle if alignment will not allow for direct transfer from yaw deck to nacelle. This must be identified while the machine head is on the ground so that the temporary fall arrest can be installed. The figure below illustrates which orientations of the nacelle relative to the tower door can result in obstruction of both nacelle ladders. Contact GE site representative for technical assistance. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 158/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual A temporary fall arrest system may need to be installed for protection while transferring from the yaw deck to the nacelle if alignment will not allow for direct transfer from yaw deck to nacelle. This must be identified while the machine head is on the ground so that the temporary fall arrest can be installed. The figure below illustrates which orientations of the nacelle relative to the tower door can result in obstruction of both nacelle ladders. Contact GE site representative for technical assistance Figure 177: Orientations of the nacelle relative to the tower door If applicable install a temporary fall protection: 1. Inspect the cable: 2. Verify a min. of 30 feet in length of 3/8 approved personal fall protection safety cable with one eyelet. 3. Inspect for damage such as broken wires. 4. Verify labels are present and fully legible. Cable must be rated to support 5,000 lbs. 5. Inspect the snap hook ensure the gate lock correctly. 6. If the safety cable has wire rope clips verify they are tight. Figure 178: Example fall arrest protection parts installation CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 159/428 GE Renewable Energy Installation Manual – Original – A retractable lanyard can be utilized where allowed by local regulations. 7. Prior to lifting the machine head secure the retractable lanyard. Secure a rope and hook to the bottom of the ladder to be able to reach from the yaw deck after the machine head is positioned on the tower. Figure 179: Example fall arrest protection parts installation 8. Attach a softener between the sling cable and the gearbox lifting point. 9. Double wrap the sling cable onto approved anchor point e.g., gearbox lifting point. 10. Attach anchor type shackle to the cable sling, verify the cotter pin is secure. 11. Hook the temporary safety cable to the shackle. 12. Ensure there is true engagement of hook to the shackle and that the hook gate is locked. 13. Use fall-arrest PPE and Ladsafe/TufTug to transfer from the tower to the nacelle. Adhere to climbing rules at all times. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 160/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual Figure 180 NOTE A temporary cover shall be placed over the elevator opening at the yaw deck to avoid potential fall of persons/materials through it. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 161/428 GE Renewable Energy Installation Manual – Original – 10.1 Inspecting the Nacelle Carry out Nacelle Receiving Inspection. Inspect the machine-head for signs of shipping damage. Contact the GE site representative if damage is found. 10.2 Preparing the Nacelle DANGER Risk from overhead suspended load/Crushing hazard! Be aware of transport trailer Air ride systems. Do not access through nacelle bottom hatch if air ride is being adjusted. The nacelle has to be accessed through the roof hatch. 1. Remove the shipping plastic (A) from the transportation cap locations and from the back of the nacelle. A – Shipping plastic Figure 181: Shipping plastic 2. Remove the tarpaulin and shipping locks from the rotor flange. 3. Clean nacelle and apply touch-up paint (as necessary). 4. Verify the cables are secured in a loose knot to protect cables from pinching and are covered with shrink-wrap. Remove tarpaulin for return shipping (if applicable). Figure 182: Example of the nacelle CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 162/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual WARNING Fall hazard! When climbing on top of the nacelle roof, always ensure the ladder is secured with rope to the rail. Use the following rules when using a ladder to inspect equipment. Check the ladder for damage prior to use. Remove from service if damaged. Use electrician's (fiberglass) ladders only. Maintain 3-point contact while ascending/descending the ladder. Buckle rule: stay substantially at the center of the ladder. No carrying anything (camera in pocket, ok). Secure ladder with one person at the bottom of ladder holding it and one climbing. Extend the ladder 3-rungs over top edge. No climbing to the top of the ladder. The person at bottom will maintain control of the ladder until the ladder is secured with rope. Figure 183: Securing ladder to nacelle Position the ladder at a 4-1 angle. If applicable: 5. Climb inside the nacelle and remove the transportation fixtures (C) located at the rear end of the generator support frame. The fixtures are attached to the frame with bolt pin and cotter pins. Remove all hardware (C and B) and secure for later return to place of origin. A - Floor cover (to be installed after removing the transportation fixtures) B - Clevis pins 2pcs C - Transportation fixture Figure 184: Transportation fixtures CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 163/428 GE Renewable Energy 6. Installation Manual – Original – After removing the transportation fixtures install the floor covers (A). Torque the hardware and mark with a paint pen. Refer to 114W5454. Figure 185: Floor cover If applicable: For rail transport the transportation caps 114W5386P001 and 114W5387P001 are supplied loose inside the nacelle enclosure. The caps are marked left and right for correct installation. Also refer to 114W5454 and 114W5453. Figure 186: Transportation caps CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 164/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – 7. Clean and dry the marked surfaces where the sealant will be applied. 8. Apply a continuous 3-4 mm bead of sealant (GE part 104W5085P001) all around between the fiberglass parts (GE parts 114W5386P001/ 114W5387P001) on each side of the line of bolts as shown in adjacent figure. Apply just before bolting. 9. Make sure that the caps are properly sealed. Installation Manual ATTENTION Temperature range for application of sealant (GE part 104W5085P001) is from + 5°C to + 40°C. Figure 187: Applying a bead of sealant at outer flange Application of sealant only within the temperature range permitted! ATTENTION Danger of water ingress! Take good care to seal this detail (A) water tight. Figure 188: Applying a bead of sealant at inner flange CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 165/428 GE Renewable Energy Installation Manual – Original – 10. Attach the caps with hardware according to GE drawings 114W5453 and 114W5454. Exterior Type 2 connection (9 bolts in total): 115W6720P001 weld nut, M8 104W9989P001 rivet, ST/ST 5/32X5/8, round head L415AP17 washer, plain, M8 L14DP17035 SCREW, hex cap, M8 X 1.25 X 35 392A1652P001 thread locking compound, medium strength Figure 189: Exterior hardware Interior Type 1 connection (4 bolts in total): L14AP19050T screw, hex cap,M10X1.5X50 L415P19T washer plain,M10 L216P19B lock nut, prevailing torque, M10 X 1.5 Figure 190: Interior hardware CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 166/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual ATTENTION Awkward postures! Tight spaces. Use caution. 11. Seal around all edges of the cap, at each bolt head and specifically take good care around the detail marked (B) in the adjacent figure. 12. Inside, add nuts to bolts (A), L215P17 lock nut, prevailing torque, M8 X 1.25M (2 places). Figure 191: Seal around edges If you want to install obstruction lights continue with Step 15. If you do not install any obstruction lights: 13. Seal the drill holes in the nacelle roof with a cover plate and sealant (GE part 104W5085P001). 14. Seal the edge of the plate and bolts with a bead of sealant (GE part 104W5085P001) to keep moisture out. Figure 192: Cover plate CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 167/428 GE Renewable Energy Installation Manual – Original – If applicable: 15. Install the exterior aviation light support posts (A) as required for the particular WTGS. Figure 193: Aviation light support posts 16. Drill holes (H) (40 mm ) at the location of the lights. Refer to 115W2558. H – Hole locations for aviation light cables 17. Feed the cables for the aviation lights through these holes and then through the black PVC-conduit pipes under the nacelle roof. Refer to 108W6416. Figure 194: Holes for aviation light cables CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 168/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 18. Install the aviation light support posts and seal around the bottom edges with sealant (GE part 104W5085P001). Seal all four bolt heads and washers water tight with sealant (GE part 104W5085P001). Refer to position (A) in the adjacent figure. 19. Under the baseplate and against the nacelle roof surface add one bead of sealant (GE part 104W5085P001) around the center cylinder, refer to position (B) in adjacent figure. Figure 195: Aviation light seal 20. Install the optional aviation lighting. Refer to the site-specific documentation. See GE drawing 108W6416 for the routing and connectors of the aviation light cables to their terminations. Figure 196: Optional aviation lighting CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 169/428 GE Renewable Energy – Original – Installation Manual 21. The weather station is shipped inside the nacelle, remove the packaging and lift the weather station up to the roof. 22. Install the weather station platform and bolt in place using the fixing accessories provided. Tighten the fixing accessories to the requisite torque and mark them with a marker pen. Details of the required torques can be found in the 3MW Platform Bolt Torque Specification. 23. Seal the edge of the plate and bolts with a bead of Sikaflex® or equivalent to keep moisture out. 24. Route anemometer and wind vane cables through nacelle top hole, to the cable tray inside the nacelle to the terminal box. Figure 197: Weather station 2.85-103 to 2.75-120 Figure 198: Weather station 3.2-130 to 3.6-137 25. Inside the nacelle, in the oil cooler cabinet on the rear of the nacelle, attach the electrical grounding braids. When the unit arrives at the wind park, the grounding braids are mounted at location (B). 26. Disconnect the braids (from location B) and mount them to the welded-on cylinder (A) on the weather mast baseplate. Figure 199: Connecting grounding braids to MET mast base CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 170/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 27. After completing work in the cooler compartment, replace the loose oil cooler floor plate in its position. 28. Retighten all hardware. 29. Terminate wires per point to point. 30. Inspect the rear of the nacelle back compartment for loose debris, trash and install the fiber glass cover with the hardware provided. 31. Install the tarpaulin between the back of the generator and the back of the nacelle. Figure 200: Replacing oil cooler floor plate 32. Check the hydraulic hand pump for proper functioning and loose hardware and leaks. 33. Verify that 80 liters of gearbox oil are present and properly secured in the nacelle. 34. Activate the desiccant breather by pulling the o-ring seal if applicable. 35. Check the yaw bearing threads for cleanliness. Remove contaminants with a tap if necessary. 36. Verify the gear ring to tower flangemating surface is clean. 37. Check the hydraulic/ gear oil/ cooling hoses and fittings are tight. Report any oil leaks to GE prior to flying the nacelle. Figure 201: Hydraulic hand pump for the rotor lock 38. Verify the main flange to hub flangemating surface is clean. 39. Verify all hub-mounting nuts and washers are present. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 171/428 GE Renewable Energy – Original – Installation Manual 40. Check inside the top box cabinet for rodent, debris. Figure 202 41. Check cables at the top box, below the generator and the cables coiled below the main shaft for possible damage due to rodents or transportation handling. Contact GE site representative if any damage is found. Figure 203 42. Verify the nacelle floor hatch is closed and carabineer available. If not present, contact GE representative. Figure 204 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 172/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 43. If applicable remove the shroud cover of the rotor main shaft. 44. Ensure that grounding brushes in main shaft is present and free of damage. Bracket(s) may have to be removed for rotor installation torque. Figure 205 45. If applicable, verify the nacelle internal crane is in the properly locked position. Secure from side to side and front to back movement by placing temporary restraining ropes. Figure 206: Push nacelle crane to locked position 46. Install temporary fall arrest system for equivalent for transferring from the yaw deck to the nacelle once installed. WARNING Falling hazard! If an employee is working at a height that exposes them to a potential fall, fall arrest equipment must be used, and 100 % tie-off at all times is required. A retractable lanyard or hard fix tie off points may be utilized. Figure 207 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 173/428 GE Renewable Energy – Original – Installation Manual WARNING Falling hazard! If the nacelle yaw deck ladders cannot be deployed correctly due to orientation of the machine head, a temporary fall arrest system can be installed to safely transfer between the tower and the machine head. This must be identified while the machine head is on the ground so that the temporary fall arrest can be installed. 47. Rotate the high-speed coupler to align the rotor lock pin with a hole on the perforated rotor lock disk. This ensures that the rotor can be locked in the Yposition during hub entry and if needed in the future. Figure 208 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 174/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 10.3 Lifting the Nacelle ATTENTION Check the wind speed! The nacelle may only be installed in accordance with section 4.1 ‘Operations Involving the Use of a Crane’. If the nacelle cannot be mounted immediately and the "open" tower has to remain without a nacelle (e.g. overnight), only three tower sections may be mounted. In this case, the top tower flange must be protected against the effects of the weather by suitable means. Refrence General_Description_MW-xxHz_WindSpeedLimitations. 10.3.1 Lifting Gear for the Nacelle NOTE Please refer to outline drawing for the lifting point. Below pictures are for reference only. 10.3.2 Attachment of the Lifting Gear 1. Verify the gear ring to tower flangemating surface is clean. 2. Remove the hatch and the cover over the lifting lugs of the nacelle and place them inside the nacelle. 3. Attach two guide ropes to the lifting beam. 4. Attach the lifting beam to the crane. Figure 209: Remove the roof hatches CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 175/428 GE Renewable Energy 5. Installation Manual – Original – Instruct the crane operator to position the lifting beam over the nacelle and bring the lifting gear to the lifting lugs. Figure 210: Positioning the lifting gear Arrangement of the lifting lugs in the nacelle: 6. The arrangement of lifting lugs is shown in adjacent figure. Confirm lifting strap clearance at all locations before putting tension on the straps. Figure 211: Lifting lugs in the nacelle CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 176/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual WARNING Avoid equipment damage! Use caution when attaching the lifting gear so that damage does not occur to the hydraulic power unit, yaw motors or any cables. 7. Attach lifting gear to the front lifting lugs. Figure 212: Attaching the nacelle The lifting gear is attached to the lifting lugs on the top of the bedplate. Figure 213: Lifting lugs on the main bearing CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 177/428 GE Renewable Energy 8. – Original – Installation Manual Attach lifting gear to the left and right rear lifting lugs. Figure 214: Lifting lugs on the base frame NOTE Two more lifting lugs are located on the left and right of the rear of the base frame. The shackles are attached to these by means of sling loops. 9. Once the lifting beam is secured to the nacelle, attach one guide rope to the main shaft and the other to the rear tie-off point on top of the nacelle to make it easier to make adjustments during the lifting operation. Figure 215: Lifting lugs on the base frame ATTENTION Danger of equipment damage! Only apply tag lines to load rated fixing points. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 178/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 10. Pick up the lifting belts slightly without lifting the load. 11. Turn the spindle until the suspension is over the center of gravity of the load. 12. If an incorrect angle arises, it can be corrected later under load. NOTE The center of gravity needs to be adjusted for lifting the nacelle with or without gearbox or generator. Figure 216: Aligning the load WARNING Crushing hazard! During Installation always ensure that hands, feet, and body are not between any potential pinch points. 13. After all pre-installation work has been finished inside the nacelle the transport ring needs to be removed before the nacelle is installed on top of the tower. 14. The crane matts/cribbing must be positioned on the ground, in relation to the transport fixture. 3 meters (approx. 12”) off the ground (heavy crane matts or 12”x12” timbers, are standard dunnage) and that allows access through the rear floor tool hatch. Figure 217: Positioning of crane matts/cribbing WARNING Lifting heavy loads! Prior to lifting all heavy loads, a pre-lift meeting with all parties involved is required. (crane operator, rigger, supervisor, signalman, and any other personnel involved, such as area safety, tag line holders). All lifting must be done in strict accordance with the installers lift plan and the applicable job safety analysis must be reviewed as well. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 179/428 GE Renewable Energy Installation Manual – Original – 15. After receiving the starting signal from an authorized person (i.e. the danger zone is safe and free of workers) start lifting up the nacelle. Refer to the site-specific plan. 16. Lift up the nacelle from the ground – approx. 1 m-2 m. Figure 218: Lifting up the nacelle 17. Put down the nacelle on crane matts/cribbing to support the nacelle. 18. Reduce the hook load by max. 30 % and check the stability of the crane matts/cribbing and underground while reducing the hook load. 19. Wait approx. 5 min, then check the stability again. 20. If stability is not sufficient go back to step 14 above, otherwise continue. Figure 219: Example Nacelle supported by crane matts/cribbing CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 180/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 21. Remove all bolts between transportation fixture and yaw bearing to loosen the transportation fixture. 22. Unhinge the hooks from the nacelle-totower fit-up aids. The transport fixture is now detached from the nacelle. Figure 220: Shipping fixture of 3.2-130 to 3.6-137 Figure 221: Shipping fixture of 3.2-130 to 3.6-137 DANGER Risk from overhead suspended load! After finishing the removal of the hardware for the shipping fixture and ensuring the load is stable all personnel must exit the nacelle prior to beginning the lifting. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 181/428 GE Renewable Energy Installation Manual – Original – 23. After receiving the starting signal from an authorized person (i.e. the danger zone is safe and free of workers) start lifting up the nacelle. Refer to the site-specific plan. 24. Instruct the crane operator to lift the nacelle approximately 40 cm from the transport ring. Stabilize the load and verify the nacelle is level. Figure 222: Lifting and stabilizing the load 25. Instruct the crane operator to hoist the nacelle into position above the top of the tower. 26. Ensure the appropriate tension on the taglines is maintained to keep the nacelle stabilized during the lifting process. Figure 223: Lifting the nacelle CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 182/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 10.4 Assembling the Nacelle WARNING Crushing hazard! Do not put your hands between the flanges. Danger of serious crush injuries! Ensure that you keep a safe distance from the flanges. 1. Use the fit-up aids to facilitate the positioning of the nacelle on the tower flange. The fit-up aids have to be positioned on the inside of the tower flange. 2. Giving precise instructions to the crane operator lower the nacelle until the hole pattern of one flange is positioned exactly above the other. Figure 224: Fit-up aids for the nacelle NOTE Do not mix bolts and nuts from different manufacturers in bolted flange connections! CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 183/428 GE Renewable Energy 3. Installation Manual – Original – Insert four opposed bolts in the flange to serve as alignment aids. Critical to Quality: 4. Ensure all the bolts engage by hand before using the impact wrench or torqueing the bolts. If bolts do not fully engage due to bad threads, contact GE prior to final torqueing and or disconnecting the crane. Figure 225: Capturing the nacelle 5. If the unit requires a service lift installed, install the service lift backup brackets to the flange using longer bolts according to drawing 117W5670. 6. Install the remaining washers and bolts in the yaw deck. 7. After all bolts have been installed, instruct the crane operator to lower the nacelle completely on to the tower flange. Figure 226: Installing service lift backup brackets to the flange CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 184/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual DANGER Pinch point – Crushing hazard! When working with hydraulic and pneumatic torque tooling ensure that your hands and any part of your body are not between any pinch points (i.e. no part of your body is between the tool reaction arm and the back up pressure surface). Ensure personnel are properly trained on safe operations of hydraulic and pneumatic tools. NOTE Uncontrolled torque increase! When the electric torque wrench has switched off after reaching the preset torque, it may not be switched on again on the same bolt, since this causes an uncontrolled torque increase. CAUTION Wear hearing protection! Proper hearing protection must be worn when working with any electrical or hydraulic impact tooling! Always assess the next task at hand. If 85 decibels will be exceeded, hearing protection must be worn. Observe requirements for hearing protection per your company's policies. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 185/428 GE Renewable Energy Installation Manual – Original – 8. Using an impact wrench tighten all bolts in a star pattern/rolling triangle. 9. Reference the 3MW Platform Bolt Torque Specification for final torque. DANGER Fall hazard! If the nacelle yaw deck ladders cannot be deployed correctly due to orientation of the machine head, a temporary fall arrest system can be installed to safely transfer between the tower and the machine head. This must be identified while the machine head is on the ground so that the temporary fall arrest can be installed. Figure 227: Tightening the bolts 10. Remove the crane lifting gear. 11. Remove the tag lines and secure to lifting gear. 12. Instruct the crane operator to move lifting gear out of the work area. 13. Remove the fit-up aids as required. DANGER Danger of collapse! Before the assembly of the rotor, all bolted connections between the tower sections and between the tower and the nacelle must be tightened as per the document 3MW Platform Bolt Torque Specification. WARNING Pinch point – crushing hazard! When working with hydraulic and pneumatic torque tooling ensure that your hands and any part of your body are not between any pinch points (i.e. no part of your body is between the tool reaction arm and the back up pressure surface). Ensure personnel are properly trained on safe operations of hydraulic and pneumatic tools. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 186/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 14. Perform the final torque using qualified torque tooling and mark with a paint pen. Details of the required torques can be found in the 3MW Platform Bolt Torque Specification. 15. Replace the cover over the lifting lugs on the roof of the nacelle, add the steel bars, and connect the bolts. 16. Close the roof hatch. 17. If applicable, fit the lamps in the lighting fixture and mount the covers. 18. Connect the optional temporary or permanent aviation lighting. Refer to manufacturer's instructions. 19. Inspect the interior of the tower for scratches and bare metal surfaces. Apply latex-based paint as per the manufacturer's instructions. Figure 228: Closing roof hatch CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 187/428 GE Renewable Energy Installation Manual – Original – 11 Hub Quantity Description ar Cribbing 1 8’ Extension Ladder 3 Radio, two-way Per lift plan Rigging 2 Tagline, nylon rope, 20’ 1 Tape measure, 100’ Typical Hub Configurations Typical 2500/2570 Figure 229: Utilized on 120m Rotor diameter and smaller Typical 2900 Figure 230: Utilized in 130m Rotor diameter and larger Both hub configurations require the use of 3 lifting plates attached to the bearings to offload as shown on the illustration. Request outline drawings for bearing bolt hole pattern from GE representative to aid in lifting plate customer design. Figure 231: Hub lifting gear CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 188/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 11.1 Inspecting the Hub Carry out Hub Receiving Inspection. Inspect the hub for signs of shipping damage. Contact the GE site representative if damage is found. WARNING Electrical hazard! Stored energy may be present within electrical cabinets. Consult with GE engineering to identify the voltages that could be present. ATTENTION Check components! All components must be checked for visible damage, deformation and cracks prior to assembly! The components must be stored and mounted in such a way that any damage is avoided that could adversely affect the standing stability or loadbearing capacity and could thus cause potential accidents. Please contact the GE site representative if damage is found. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 189/428 GE Renewable Energy – Original – Installation Manual 11.2 Lifting the Hub Remove the transportation frame only if final assembly can be accomplished immediately (store with transportation frame attached). ATTENTION CRITICAL TO SAFETY! Rotors cannot be assembled with intent to store. If rotors are not installed within 30 days after assembly, the installer must begin a documented maintenance cycle. GE will provide lubricant and directions, but it is the installer’s responsibility for executing and submitting documentation to GE. ATTENTION CRITICAL TO SAFETY! Only use devices specifically designed for lifting the hub. Do not use the transportation tie-down brackets for lifting the hub. The transportation tie-down brackets are strictly used for transportation tie-down only and are not load rated for lifting. Moving the hub prior to blade assembly is to be done using three load rated lifting brackets fixed to the three lifting points. NOTE Please check the outline drawing for the lifting points. Below pictures are for reference only. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 190/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 1. – Original – Installation Manual If required remove the transport tarp from the hub to attach the rigging. To protect the hub from the elements, remove the shipping materials only if final assembly can be accomplished immediately (store with shipping materials attached). The nose cone may be shipped inside the machine head and will be removed during installation of the generator. Figure 232: Example Hub transportation 2. Offload the nose cone near the area where the rotor will be assembled. Figure 233: Typical nose cone lifting eye supplied with the hub, 3 each. Figure 234: Example nose cone offloading CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 191/428 GE Renewable Energy Installation Manual – Original – 11.2.1 Attaching the Lifting Gear ATTENTION Avoid damage! Use caution when attaching the lifting gear so that no cables or hoses inside the hub are damaged or pinched. 1. Mount three lifting lugs to the bearing of the hub for unloading from the trailer. Figure 235: Hub lifting gear Figure 236: Typical hub lifting locations CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 192/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual Critical to Quality: Lifting bar method may be used only when shrink wrap has been removed to reposition the hub during rotor assembly. 2. Do not use the lifting bar to offload the hub if the hub will remain in storage. ATTENTION Danger of equipment damage! The hub must be sealed to prevent damage! Do not damage the shrink wrap! The hub must be sealed to prevent water from entering the hub. 3. Attach a tag line to the transportation frame to stabilize and safely offload the hub. 4. Lift the hub from the transportation trailer. Figure 237: Lifting bar method Figure 238: Tag line on the transportation frame 5. 2900 rotor hubs will be staged and prepared in accordance with the latest Single Blade Installation GEI. 6. 2900 hubs do not require 1m clearance from the ground. Ensure the hub is staged and stabilized over appropriate bearing surface support. Figure 239 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 193/428 GE Renewable Energy Installation Manual – Original – 7. The hub must be set down on a firm horizontal surface that can support the weight of an assembled rotor. 8. Lay a wooden bed over the area for setting down the hub. Check that the area is horizontal, in order to exclude stressing of the blade bearings during the manual blade pitching. NOTE It is recommended for 120 m and larger rotors to use a rotor assembly stand if a stand is not available proceed to Step 9. 9. Ensure there is a clearance of 1 m minimum between the ground and the shipping fixture feet to allow blade pitching. 10. Detach the tag line from the hub. Detach the lifting lugs to the bearing ring of the hub. 1m Figure 240 11. If applicable remove any dirt or temporary surface coatings from the inner and outer bearing surfaces. 12. Clean the hub and touch up any damage to the paint. Figure 241: Clean coating from the bearing surface CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 194/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 13. Ensure the correct quantity of blade mounting hardware nut/washers is at hand. Figure 242: Example blade mounting hardware 14. If hub arrives with metal covers installed, remove the metal covers covering the bearing teeth to prevent damage to studs and allow access to torque bolts. Bolt must be discarded and replaced with new ones after the blades are installed. Figure 243: Remove the bearing metal covers Figure 244: Example bearing metal cover CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 195/428 GE Renewable Energy Installation Manual – Original – 12 Rotor Blades ATTENTION Rigging requirements! Rigging requirements are based on the site-specific lift plan. Consult with GE to obtain equipment outline drawings, containing bolt hole patters and approved lifting points, weights and dimensions. 12.1 Inspecting the Rotor Blades ATTENTION Check components! All components must be checked for visible damage, deformation and cracks prior to assembly! The components must be stored and mounted in such a way that any damage is avoided that could adversely affect the standing stability or load-bearing capacity and could thus cause potential accidents. Please contact the GE site representative if damage is found. 1. Check the blade support position and blade condition. The blade must not touch metal fixtures. Report to GE representative as required. 2. Inspect the blade studs for damaged threads and corrosion. 3. Inspect the bearing and blade mating surfaces for high spots or protrusion. 4. Ensure the blade root access doors in the blades are closed and the handles are in locked position or ensure the blade closeout cap hardware is tight on the blades. 5. Inspect the zero reference plates for damage. 6. Ensure the blade surface is free of any contamination like dirt or salt from sea or land transport. If not ok, clean the blade surface accordingly. 7. Inspect the blade tip drain holes for blockage (all three blades). Inspect hole to ensure it is clear. If blockage is encountered, contact GE representative. 8. All blade damage must be reported and blade repair must be done in accordance with manufacturer’s recommendations. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 196/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 12.2 Offloading the Rotor Blades NOTE For handling of the lifting devices refer to the supplier’s documentation. Please refer to outline drawing for the lifting point. WARNING Mind the maximum allowable wind speed! For technical data to calculate the maximum allowable wind speed for crane activities, especially on parts and systems with a high sail area with respect to system weight, refer to the document: Component_SailArea_DragCoef_Generic-xxHz. WARNING Take care when working on the low-loading trailer! Work on the loading platform of the low-loading trailer may only be carried out when it is stationary. All personnel must leave the loading platform before the low-loading trailer is moved. DANGER Risk from overhead suspended load! Never work under a suspended load. Make sure all people, vehicles, equipment and materials are clear of the crane tail and load swing. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 197/428 GE Renewable Energy Installation Manual – Original – WARNING Blade handling - use certified lifting points only! When handling blades on shipping fixture(s) specific blade manufacturer's handling instructions for the specific blade configuration (e.g. 114W3337 for the 48.7 m blade or 103W2754 for the 50.2 m blade or 109W3740 for the 58.7 m blade) must be reviewed with the crews and understood prior to commencing work. Only use lifting points that are designated by the blade manufacturer for lifting. DO NOT use transportation tie down points for lifting! Only use lifting points that are rated with enough capacity to lift the entire weight of the blade. If unsure, always consult with GE Technical Advisors and GE Blade Engineers prior to handling individual blades and/or blades in shipping fixtures. CAUTION Use caution when operating heavy equipment around personnel and wind turbine components. 1. Remove the rear lighting gear from the blade. 2. Remove the entire lashing and all twist locks to unload the blades from the truck. Figure 245: Example for blade rear lighting The recommended method for lifting the blade requires the use of one crane with a spreader bar. The spreader bar must be capable of handling both the 29 m and the 37.5 m positions of the tip fixture. Alternatively, lifting the blade requires the use of two cranes with 35 t load capacity each. Both cranes will need to be coordinated to keep both fixtures as even as possible. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 198/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual Figure 246: Reaction Loads for Lift Z=0 - Z=29000 Figure 247: Reaction Loads for Lift Z=0 - Z=37500mm Critical to Safety: 3. Ensure the twist locks on the tip fixture are in the locked position before proceeding to lift. Figure 248: Twist locks Figure 249: Lifting the tip fixture The tip fixture requires four D-Rings and four steel cables attached to crane. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 199/428 GE Renewable Energy – Original – Installation Manual ATTENTION Danger of equipment damage! If two straps are used make sure that the straps are hooked to fixture in opposite corners (refer to figure). Figure 250: Lifting the root fixture The root fixture requires 2 D-Rings and 2 cables attached to crane. 4. Attach rigging to approved lifting points on the blade fixture. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 200/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 5. – Original – Installation Manual If using single crane with lifting bar install a tag line to stabilize the load. DANGER Danger of blade destruction and serious personal injury! It is strictly forbidden to lift the blade solely at the tip fixture or the root fixture! Figure 251: Lifting points 6. Lift the root and tip fixtures slowly and evenly. The lifting/handling accelerations must be limited to 3 m/s² (0.3 g). Figure 252: Allowed vertical and transversal lifting cable angles The allowed hoisting cable or sling angles are limited to +0 °/-3 ° in the vertical direction and 60 ° in the transversal direction. Figure 253: Leveled lifting The maximum allowed shipping fixture inclination when lifted is 3 °. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 201/428 GE Renewable Energy – Original – Installation Manual Alternatively, the blade can be lifted off the trailer with two forklift trucks. NOTE Important for tandem lifting! Each forklift truck shall be de-rated by 20%. Hoist ropes to remain vertical at all times. Good communications are crucial. Figure 254: Unloading the blade with two forklift trucks Figure 255: Unloading the blade with two forklift trucks Figure 256: Unloading the blade with two forklift trucks Figure 257: Unloading the blade with two forklift trucks Figure 258: Unloading the blade with two forklift trucks ATTENTION Danger of equipment damage! If two straps are used make sure that the straps are hooked to fixture in opposite corners (refer to figure). CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 202/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual Example 58.7 LM super pack and stack shipping fixture. Refer to 109W3740. 7. The 58.7 blades are shipped with the trailing and leading edge in a horizontal position. 8. Refer to the latest revision 109W3740 for approved lifting points and handling methods. The package shall be lowered onto a near flat ground surface. 9. Verify a maximum of 200 mm flatness deviation. This is the permissible tolerance without damaging the blades. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 203/428 GE Renewable Energy Installation Manual – Original – Figure 259: Blade positioned permissible flatness deviation (max. 200 mm) 10. In case of an uneven surface, lower down the blade package until the first fixture touches the ground. 11. Then line the other fixture by supporting it with adjustment shims (e.g. wooden or metal blocks). Both transport fixtures need to be laid down on the ground evenly. Figure 260: Blade positioned with adjustment shims A (flatness deviation more than 200 mm) Likewise, a maximum of 100 mm flatness deviation on ground is allowed in transversal direction. 12. In case of an uneven surface, lower down the blade package until the first fixture touches the ground. 13. Then line the other fixture by supporting it with adjustment shims (e.g. wooden or metal blocks). Figure 261: Blade positioned with adjustment shims A (flatness deviation more than 100 mm) NOTE If blades are not installed immediately, always secure the blades during storage to prevent damage during high winds. For complete storage instructions refer to the document 3MW Platform Storage Manual. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 204/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 12.3 Preparing the Blades 1. Check the blade bolts for damage and even projection. Correct damaged threads and remove high spots with a file. 2. Remove corrosion with wire brush. 3. If threads and high spots cannot be corrected or corrosion cannot be removed, contact the GE site representative. NOTE Please check the outline drawings for the lifting points. Below pictures are for reference only. Measure the blade lifting points against dimensions provided in blade handling drawing to make sure they are correct. NOTE If blade de-icing equipment will be installed refer to work instruction for blade de-icing equipment installation. 4. Remove all dirt or non-permanent surface coating materials on the bolts, blade end face, and bearing face. 5. Remove any water and debris from the root end of the blade. 6. Check carefully and remove any shipping bracket washers lodged between the blade closeout and the inside wall of the blade. 7. Apply lubricant per 3MW Platform Bolt Torque Specification to 100 % of the threads on the blade studs. Review Materials Safety Data Sheet (SDS) prior to use. Shake the spray can thoroughly for a minimum of one minute. The lubricant will have a silvery appearance (if clear, continue shaking the can). Figure 262: Clean flange CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 205/428 GE Renewable Energy 8. Preparing the 58.7 Blades: Once the fixture is removed, remove the shipping hardware from the root. 9. Support the blade root by straw bales or equivalent and/or crane if installing the blade immediately to the hub. – Original – Installation Manual Figure 263 10. Support the shipping fixture by crane or forklift to remove the weight from the shipping fixture hardware. 11. Loosen and remove the shipping fixture hardware. 12. Remove the shipping fixture and place out of the work area. Figure 264 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 206/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 13. Once the shipping fixture is removed locate the blade studs for installation. These bolts are secured to the shipping fixture. Contact GE site representative if bolts are missing. Figure 265 14. Apply Loctite 277 to the new stud. Review Materials Safety Data Sheet (SDS). 15. Install ensuring the stud projection matches the other studs. NOTE Studs do not bottom out. Verify the projection of the stud matches the others. Figure 266 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 207/428 GE Renewable Energy Installation Manual – Original – Figure 267: Reference marking A – 0-reference mark B – Name plate C – 0-reference marking plate D –Reference line E – Highlighted stud end 16. Highlight the 0-reference mark (A) on the face and inside the edge of the blade using a red paint pen. 17. Place a red paint pen line (D) across the face of the blade flange centered with the 0-reference mark (A). 18. Highlight the end of the stud (E) directly left of the 0-reference mark using a red paint pen. Figure 268: Reference marking CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 208/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 12.4 Blade Handling NOTE Blade and rotor damage prior to installation! CRITICAL TO QUALITY AND SAFETY: When abnormally high ground winds are anticipated, it is recommended that the contractor reschedules this activity and to double up on blade handling and control resources prevent blade damage. Each site shall assess the need for additional blade and assembled-rotor tiedown arrangement. Locations and instances which demonstrate high groundlevel winds warrant additional consideration which may include: Additional standard tie-downs and anchor points, further assessment of cribbing and dunnage and the potential for cribbing and dunnage to sink into the ground. WARNING Blade and rotor damage during installation! In high wind prone areas, do not build rotors until ready to install. Stress caution on building rotors too far in front of installation. "Pay attention to the Weather forecast", When abnormally high ground winds are anticipated, it is recommended that the contractor double up on dead men and use a strap with a higher minimum tensile strength then 5000 lbs. each Leg during rotor assembly and storage. Use blade tip socks to secure rotor back to the tower for increased stability in high wind events. Build rotor on the transportation frame and/or hub stand to increase footprint and stability. Include compaction in the rotor hub assembly area. In known soft soil conditions require increased dunnage foot print for component stability. Ensure all tie down straps are tight and strong enough for the application. Fully assembled rotors ensure zero degree blade orientation if rotor cannot be installed. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 209/428 GE Renewable Energy Installation Manual – Original – The rotor blades are marked with center of gravity marks. These marks help to balance the blades. Figure 269: Example Center of gravity Several marked fastening points are located on each rotor blade. 1. Support the blade for lifting or storage as labeled in accordance with specific blade manufacturer drawings. Consult with GE representative for specific blade drawings. Figure 270: Example Lift here and Support points. ATTENTION Danger of damaging the blade! Do not deviate sling location from blade manufacturer specified lifting locations under any circumstances without written approval from the GE blade engineer. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 210/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual ATTENTION Danger of damaging the blade! Always check the trailing and leading edge protectors for padding to prevent blade damage. Always check the trailing and leading edge protectors for any debris that could damage the blades. Make sure Vortex generators (VG's) are protected and use the correct trailing edge protection method according to blade handling drawing. CAUTION Use caution when operating heavy equipment around personnel and wind turbine components. 2. After the rotor blade has been lifted off the trailer, remove the top section (A) of the tip fixture if rotor will be assembled. 3. Loosen the threaded torque bar (B). 4. Remove the pin rod (C) holding the top portion of the padding. Figure 271: Example 48m GE Tip Fixture positioning CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 211/428 GE Renewable Energy 5. Installation Manual – Original – Lift the top portion of the padding (D) and remove it from the fixture to prevent blade damage when rotating the blade. NOTE Replace all brackets with hardware after the blade is removed from the fixture. Figure 272: Lift padding and remove 6. For single or double crane lift: Position crane(s) to lift the blades at the specified lifting locations per specific blade drawing. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 212/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 12.4.1 Example: Double Crane Lift 1. Place and center protective caps (for leading edge and trailing edge) at lifting locations as per specific blade drawing. 2. Place and center slings at lifting locations as per specific blade drawing. Refer to drawing for min. sling width and length. Figure 273: Example only sling position for double crane lift If the blade is shipped in a degree position, first rotate blade so the trailing edge is facing up. 3. Using properly sized lifting equipment support the root fixture with a separate crane or forklift. Secure a line (A) to the upper left corner of the root fixture (B). 4. Slowly lift the root fixture (B) until the blade rotates into vertical position as required per blade specific drawing. Figure 274: Lifting root fixture CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 213/428 GE Renewable Energy – Original – 5. Once the blade is vertical and stabilized, lift the blade with the main crane until the load is supported. 6. Remove the root fixture and store outside of the work area. Installation Manual ATTENTION Danger of damaging the blade! Do not deviate sling location from blade manufacturer specified lifting locations under any circumstances without written approval from the GE blade engineer. Figure 275: Example removing root fixture 12.4.2 Example: Single Crane Lift 1. Place and center protective caps (for leading edge and trailing edge) at lifting locations as per specific blade drawing. 2. Place and center slings under a spreader bar at specified lifting locations per drawing. Refer to drawing for min. sling width and length. Figure 276: Example place slings and spreader bar CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 214/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 3. – Original – Installation Manual Adjust the slings length above the spreader bar so that the hook is on the same vertical line as blade CG (Center of Gravity). Front 48.7 25' and Rear 22' 3 " If using a chain fall, ensure the chain fall or spreader must not make contact with the blade. Figure 277: Example lifting with spreader bar 4. Lift the blade by the root fixture, rotating the blade so that the trailing edge (TE) is vertical (pointing up) with a separate crane or forklift. Care must be taken to ensure the trailing edge does not lean and place too much pressure against the slings. 5. Once the blade is vertical and stabilized, lift the blade with the main crane until the load is supported. ATTENTION Figure 278: Example lifting blade until load is supported Danger of damaging the blade! The chain fall or spreader must not make contact with the blade. Do not deviate sling location from blade manufacturer specified lifting locations under any circumstances without written approval from the GE blade engineer. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 215/428 GE Renewable Energy 6. Installation Manual – Original – Once the blade is stabilized remove the root fixture and store it outside of the work area. WARNING Operating the fork lift! Do not operate the fork lift if you don't have the required training. The stability of the forklift is determined by the location of its center of gravity. Ensure that the load is evenly distributed on the forks while travelling. Figure 279: Example placing fix out of work area Follow the equipment operating manual. 7. If the blade is not balanced during lifting, using the chain fall adjust sling length above spreader bar to keep blade balanced during lifting. ATTENTION Danger of damaging the blade! Do not deviate sling location from blade manufacturer specified lifting locations under any circumstances without written approval from the GE blade engineer. Figure 280: Example blade balanced CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 216/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 13 Rotor 120 m diameter and smaller can be installed as a completely assembled rotor. 130 m rotor diameter and larger must be installed utilizing Single Blade Method the Single Blade Process (SBI). Refer to the latest GEI- for Single Blade Installation. 13.1 Preparing the Rotor NOTE E-palms are a delicate electronic device. Care must be taken of these units including storage in warm environment to prevent battery failure. Abused or failed e-palms must be sent by customer to vendor for repair. NOTE If hubs have been in long term storage inspect the battery chargers for signs of water damage and corrosion and report to the GE representative to ensure corrective action is taken before the units are commissioned. NOTE For the GE pitch systems it is not required to pitch the bearing to 360 °. Immediately after the blades are pitched for storage or installation, place the battery box switches in the off position on each axis cabinet and install a single tie wrap to axis 1 power switch. NOTE For cold weather climate axis box heaters may be switched to the on position. Contact GE site representative for details or use and external heat source. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 217/428 GE Renewable Energy Installation Manual – Original – Quantity Description ar Brush, wire 1 File set, various, 12” 1 Water cooled generator minimum 6.5 kV 1 (Water cooled recommended) 25 kVA generator minimum 400 V; 400 volt AC (+/- 10%) 3 phase power generator. (400 VAC generators are not common in some countries, however you can use a common 480 VAC generator with the output voltage turned down to 440 VAC on the pitch system) use a 5c-6 AWG cable (L1-L2-L3-Ground and Neutral) and appropriate grounding from the generator to a grounding rod as required. 1 400 VAC fusible disconnect box 1 Ladder, step, 10’ ar MoS2 anchor brand jet lube, spray ar Paint pen, red 3 Radio, two-way ar Rags 1 Ratchet, ¾-inch drive Per lift plan Rigging ar Sandpaper, medium grit 1 Socket, 50 mm, ¾-inch drive or 55 mm for 2500 hub 2 Tagline, nylon rope, 100’ 1 Wrench, combination, 50 mm 1. Remove shrink-wrap material around the outer edge of the hub bearing prior to installing each blade. Do not remove from all three bearings at once. 2. Verify that the nuts and washers are staged in the hub for blade assembly. 3. Rotate the blade bearing ring to the desired position for blade installation. 4. Inspect the hub, pitch motors and pitch cabinets for signs of water and humidity. If water is present, dry the affected components before any operation. Report any rust/damage as necessary before operating the pitch system. Operating the pitch system with humidity could cause damage to the equipment. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 218/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 13.1.1 GE Pitch Control System (MSS Hub Pitch System) 1. Follow the steps below to operate the GE pitch system. ATTENTION E-palms are a delicate electronic device. Care must be taken of these units including storage in warm environment to prevent battery failure. Abused or failed e-palms must be sent by customer to vendor for repair. ATTENTION Ensure cables are properly secured with cable gland strain relief to prevent from accidently pulling cables and creating an arc flash. ATTENTION Prior to energizing the hub controls. The Hub controller cabinet will need to be closed and hinges locked in the closed position. DO NOT open while energized. Cable routing through the door is not acceptable. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 219/428 GE Renewable Energy Installation Manual – Original – DANGER Electrical hazard! Only trained and qualified personnel must perform electrical wiring tasks in the hub and operate the portable generator. The temporary power cable must be inspected for damage before each use. Route the power cable between the generator and the temp disconnect fuse box. Route the power cable between the hub control box and the temp disconnect fuse box. The cable must be additionally protected against mechanical damage as required and to prevent a tripping hazard. Inside the hub route the cable through J-box using the proper size cable gland provide maximum strain relief to the temporary power cable. Power cable must be ferruled to ensure proper termination. Ensure the J-Box is closed prior to energizing the generator. The temporary generator must be properly grounded. Temporary generator Site Specific LOTO must be adhered to. 2. Before energizing the hub open the cabinet doors for Axis 1 and Install the jumpers from terminal AEPC terminal J8 to AEPC-TB1. Figure 281: Factory terminal block TB1 Figure 282: Factor terminal block J8 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 220/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Figure 283: Jumper configuration – Original – Installation Manual Figure 284: Jumpers installed 107W4129p001 harness 109W1126p001 connectors 3. Zip-tie all the three 89° limit switches. NOTE The bearings will not pitch using the Exor ePalm10 handheld if the 89° limit switches are not activated. Figure 285: 89° limit switch CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 221/428 GE Renewable Energy Installation Manual – Original – 4. Terminate the temporary power cable to hub. 5. The hub junction box comes with a M63 hole cover. Remove the J-Box hole cover and save and ensure the cover is re installed after the hub assembly is completed. The installer is responsible for procuring the strain relief to secure the temp power cable to the hub junction box. 6. Use a 5c-6 AWG cable (L1-L2-L3-Ground and Neutral). 7. Ensure the generator is properly grounded to earth as required. Figure 286: J-Box cable strain relief 8. Install a 40 amp fusible disconnect box between the hub and the generator. Critical to Safety: 9. Mount the fusible disconnect box inside the hub between the hub and generator. Figure 287: Disconnect box CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 222/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 10. Terminate the power cable between the fuse disconnect box and the center box inside the hub. Use the correct tool (flat blade screw driver width 5.5 mm) to prevent hardware damage. 11. Connection points: Conductor Term Pin L1 X3 1 L2 X3 2 L3 X3 3 N X3 4 PE X3 5 Figure 288: Wires terminated the hub J-Box terminal block ATTENTION Electrical hazard! CRITICAL TO SAFETY: Close all Junction boxes. Ensure the generator is grounded to earth prior to energizing hub. Verify 400 VAC power switch is in the off position. Follow manufacturers operation procedures for energizing the generator. After energizing Check the voltage output to ensure proper operation of the pitch system. ALC Sensor Target Verification: 12. Identify the Axis 1 by marking the blade bearing closest to the hub shaft flange. Axis 1 is the down blade (tail pick blade). Figure 289: Verify were axis 1 is located for ALC verification CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 223/428 GE Renewable Energy Installation Manual – Original – DANGER Be aware of internal and external pinch points. Ensure all personnel are clear from pinch point and the crush zone prior to beginning operating the pitch system. NOTE 1 2 Item 1 - Ensure the control box auto/manual switch is on manual. Item 2 - The axis box selector switch corresponds with blade being pitched. Figure 290: Selecting pitch mode ('manual') CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 224/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – 13. Connect the Exor ePalm 10 to the port provided on the hub controller cabinet. 14. The blade bearing can now be rotated left or right having control with the EXOR 10 ePalm. A – Auto\Manual Selector Switch B – Blade Access Selector Switch C – 400VAC power switch A B C D D - EXOR ePalm connection port Figure 291: Connection e-palm CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 225/428 GE Renewable Energy Installation Manual – Original – The following overview is displayed: Handheld F1 IP Address View F2 Jog View F3 Cal View F4 Status View F5 Rotor Assembly If the hub is on the ground (not connected to rest of turbine) press F5 for hub assembly mode the following page is displayed: Assembly Request Set F8 Return 15. Navigate to the Jog View by pressing the F2 button. The following page is displayed: Jog View F8 Home F7 Cal View F1 Axis 1 Jog View F2 Axis 2 Jog View F3 Axis 3 Jog View 16. Navigate to the view for the blade to be jogged by pressing F1, F2 or F3. The following overview is displayed: Axis 1 Jog F8 Home F7 Cal View F1 Fwd F2 Rev F3 Stop F4 FFWd F5 FRev 17. Make sure that the E-stop pushbuttons on the handheld and axis box 1 are out. 18. Press the dead-man switch so that it clicks once, neither all the way in nor all the way out. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 226/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 13.1.2 GE Pitch Control System (For Turbines with PTB Hub Pitch System) 1. Before energizing the Hub open the cabinet doors for Axis 1 and Install the jumpers from terminal AEPC terminal J8 to AEPC-TB1. 2. Add the following jumpers to the AEPC card in axis cabinet 1: Terminal points J8.1 to TB1.3 Terminal points J8.2 to TB1.1 Terminal points TB1.2 to TB1.9 Terminal points TB1.4 to TB1.8 Figure 292: Factory terminal block TB1 Figure 293: Jumper configuration1 Figure 294: Remove factory terminal block TB1 from the AEPC card. Figure 295: Install J8 jumper connector to J8 in AEPC card CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 227/428 GE Renewable Energy Figure 296: Install TB1 jumper terminal block to TB1 terminal block in AEPC card 3. Installation Manual – Original – Figure 297: Jumper installed Zip-tie all three 89 ° limit switches. NOTE The bearings will not pitch using the Exor ePalm10 handheld if the 89 ° limit switches are not activated. Figure 298: 89° limit switch CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 228/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – 4. Terminate the temporary power cable to hub. 5. The hub junction box comes with a M63 hole cover. Remove the J-Box hole cover and save and ensure the cover is re installed after the hub assembly is completed. 6. The installer is responsible for procuring the strain relief to secure the temp power cable to the hub junction box. 7. Use a 5c-6 AWG cable (L1-L2-L3-ground and neutral) 8. Ensure the generator is properly grounded to earth as required. Installation Manual Figure 299: J-Box cable strain relief 9. Install a 40 amp fusible disconnect box between the hub and the generator. Critical to Safety: 10. Mount the fusible disconnect box inside the hub between the hub and generator. Figure 300: Disconnect box CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 229/428 GE Renewable Energy Installation Manual – Original – 11. Terminate the power cable between the fuse disconnect box and the PTB box inside the hub. Use the correct tool (hex tool width 5.5 mm) to prevent hardware damage. Connection Points: Conductor Term Pin L1 X3 1 L2 X3 2 L3 X3 3 N X3 4 PE X3 5 Figure 301: Example connect 400 Volt AC 3 phase power 12. Cable size: use a 5c-6AWG cable as required Connection Port and Switches Provided on Top of Axis 1 Control Cabinet: D E F A - Exor ePalm 10 B - 400V AC power switch C - EXOR ePalm AEPC connection port D - AEPC bypass switch E - Blade axis selector switch C F - Auto\Manual selector switch G - Emergency E-Stop switch I G H - Handheld E-stop I - Battery switch (DO NOT REMOVE CABLE TIE) H B A Figure 302: Connecting e-palm CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 230/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual ATTENTION Electrical hazard! Close the Junction box. Ensure the generator is grounded to earth prior to energizing hub. Verify 400 VAC power switch is in the off position. Ensure the generator is grounded to earth prior to energizing hub. Check the voltage output to ensure proper operation of the pitch system. 13. Switch the AC disconnect in axis box 1 to the 'ON' position. Wait several minutes for the DC link to charge. Figure 303: AC disconnect 14. To jog using the Exor ePalm handheld: Make sure the handheld E-stop is out. Figure 304: Handheld E-Stop CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 231/428 GE Renewable Energy Installation Manual – Original – 15. Press in E-stop bypass button on axis 1 control cabinet and keep pressed in until the handheld is connected. Figure 305: E-Stop bypass button 16. Unplug the E-stop bypass plug on axis 1 cabinet. Figure 306: E-Stop bypass plug CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 232/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 17. Plug the Exor ePalm10 handheld into the axis cabinet 1 plug. If the HTM file cannot be found unplug it, wait a minute and plug it back in. 18. Release the AEPC bypass button. Figure 307: Pitch Terminal Box 19. Turn the 'auto/manual' switch to 'manual'. NOTE If the handheld is removed without pressing the bypass switch the turbine safety chain will open. Figure 308: Auto manual/switch CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 233/428 GE Renewable Energy Installation Manual – Original – The following overview is displayed: Handheld F1 IP Address View F2 Jog View F3 Cal View F4 Status View F5 Rotor Assembly 20. If the hub is on the ground (not connected to rest of turbine) press F5 for hub assembly mode the following page is displayed: Assembly Request Set F8 Return 21. Navigate to the Jog View by pressing the F2 button. The following page is displayed: Jog View F8 Home F7 Cal View F1 Axis 1 Jog View F2 Axis 2 Jog View F3 Axis 3 Jog View 22. Navigate to the view for the blade to be jogged by pressing F1, F2 or F3. The following overview is displayed: Axis 1 Jog F8 Home F7 Cal View F1 Fwd F2 Rev F3 Stop CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 234/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual F4 FFWd F5 FRev NOTE Contact the GE site representative if the blade pitch system does not operate correctly. 23. Make sure that the E-stop pushbuttons on the handheld and axis box 1 are out. 24. Press the dead-man switch so that it clicks once, neither all the way in nor all the way out. 25. Press the F1 or F4 button to go toward the 90 degree limit switch or F2 or F5 to go toward the zero degree limit switch. 26. Verify that the nuts and washers for the assembly of the rotor blade are available in the hub. 27. Remove the shrink-wrap from the outer edge of the hub bearing before you install the respective rotor blade. 28. Actuate the blade bearing 360 degrees in each direction to ensure sufficient lubrication is present in the bearing. Top up grease as necessary. If the bearing does not actuate, you must verify that the connector of the pitch motor fan is correctly seated in the junction box. Also verify that the portable auxiliary generator is generating sufficient amperage to drive the Pitch Drive Control Box. 29. Rotate the blade bearing ring to the desired position for blade installation. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 235/428 GE Renewable Energy – Original – Installation Manual 13.2 Attachment of the Blades WARNING Crushing hazard! During the approach of the rotor blade to the hub, ensure that nobody is located between the rotor blade and the hub. Ensure that you keep a safe distance from the flanges. 1. Before mounting the first blade, ensure the pitch gear rings are free of debris. Follow the respective recommendations of the blade manufacturer when attaching the lifting gear to the rotor blades. 2. Attach tag lines to stabilize the load. 3. Carefully lift the rotor blades from the transportation frames to avoid damage. Follow the respective recommendations of the blade manufacturer. Figure 309: Bringing the rotor blade to the hub WARNING Crushing hazard! During Installation always ensure that hands, feet, and body are not between any potential pinch points. WARNING Mind the maximum allowable wind speed! For technical data to calculate the maximum allowable wind speed for crane activities especially on parts and systems with a high sail area with respect to system weight refer to the document Component_SailArea_DragCoef_Generic-xxHz. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 236/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – 4. When lifting the blades with a single crane a minimum of two persons shall maintain control of the blades with the tag lines during the alignment and installation of the blades on the hub. 5. Verify that two the limit switches on each blade are not damaged. Installation Manual Figure 310: Guiding the rotor blade CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 237/428 GE Renewable Energy – Original – Installation Manual 13.3 Assembling the Rotor ATTENTION Hazard – working under suspended loads! Never work under suspended loads! DANGER Crushing hazard! During rotor assembly ensure that hands, feet and body are not positioned between the blade flange and the hub flange! CAUTION Wear hearing protection! Proper hearing protection must be worn when working with any electrical or hydraulic impact tooling! Always assess the next task at hand. If 85 decibels will be exceeded, hearing protection must be worn. Observe requirements for hearing protection per your company's policies. ATTENTION Uncontrolled increase in torque! Once the electric or hydraulic torque wrench has reached the final set torque value switch the tool to the off position and remove it from the bolt. Do not reset or switch on the tool on the same bolt as this will result in an uncontrolled increase in torque. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 238/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual ATTENTION Danger of potential failure! Rotors must be completely assembled once work begins; no partially torqued assemblies are allowed. Once a rotor is assembled, it must be immediately final torqued. Assembly without torqueing exposes individual bolts to undue stress and can lead to potential failure. The blade stud to the immediate left of the 0degree reference mark must mate with the hole to the right of the zero mark on the hub provided by manufacturing. Figure 311: Blade bolt marks Figure 312: Hub bearing bolt hole marks CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 239/428 GE Renewable Energy 1. Installation Manual – Original – Utilizing the cranes and the PDCB/ePalm align the blade bolts through the pitch bearing flange holes on the hub. Take precaution when installing the blade screw bolts that no bolts are bent. DANGER Crushing hazard! During Installation always ensure that hands, feet, and body parts are not between any potential pinch points. Figure 313: Blade to hub alignment 2. The top edge of the blade flange must make contact with the bearing flange. 3. Ensure that the gap is less than 5 mm around the entire blade to bearing connection prior to releasing the blade from the crane. Verify the limit switches are undamaged. Figure 314: Checking the contact CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 240/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual CAUTION Wear hearing protection! Proper hearing protection must be worn when working with any electrical or hydraulic impact tooling! Always assess the next task at hand. If 85 decibels will be exceeded, hearing protection must be worn. Observe requirements for hearing protection per your company's policies. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 241/428 GE Renewable Energy – Original – 4. If applicable remove corrosion inhibitor from the inner bearing face prior to installing washers and nuts. 5. Position washers and nuts (located inside the hub) on the exposed bolts on the 3 and 9 o’clock position. 6. Install the washers with the bevel on the inside diameter pointing outwards toward the nut. The nuts shall be installed with the marks pointing outwards. Do not apply any lubricant to the washers or nuts. 7. Tighten the exposed bolts on the 7 to 9 and 2 to 4 o’clock positions. 8. Using an impact wrench achieve a torque between 50-95 % of the final pre-torque value specified in the Work Instructions for the bolted connections. Do not use impact tooling that exceeds 95 % of the pretension torque! Refer to the 3MW Platform Bolt Torque Specification. 9. Install all accessible hardware at the exposed positions before removing the crane load. Installation Manual Figure 315: Exposed positions and torque in progress CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 242/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual WARNING Rotating parts -Pinch point - Crushing hazard! When working with hydraulic and pneumatic torque tooling, ensure that your hands and any part of your body are not between any pinch points (e.g. any part of your body is not between the tool reaction arm and back up pressure surface. Ensure personnel have been properly trained on the safe use of hydraulic and pneumatic tools. 10. Position blocks/fixtures with pressed straw bales or another soft support under the manufacturer labeled support points of the blades to ensure the blade tip does not make contact with the ground. 11. Remove the crane and repeat steps 1 (on page 240) through 10 (on page 243) for the other two blades. All three blades must be installed before the nuts are tightened up to 100 % of the pre-torque value. Once the third blade has been installed, the weight shall be evenly distributed and the blade support blocks/fixtures can be removed. Figure 316: Example blade support 12. Use calibrated torque tools to torque all accessible nuts to 100 % of the pre-torque value listed in the 3MW Platform Bolt Torque Specification. Torque bolts using the bolt torque pattern specified in the 3MW Platform Bolt Torque Specification. 13. Verify blade perimeter is clear of personnel and equipment, and pitch blades as required to expose and pretorque remaining hardware. 14. Once pre-torque is complete check between bearing surface and blade flange to ensure there are no gaps. If a gap is present repeat steps 12 thru 13 above till no gaps are present. Figure 317: Use a calibrated torque tool CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 243/428 GE Renewable Energy Installation Manual – Original – 15. Mark the bolts with a visible paint pen once the pre-torque value has been attained. A straight line is marked from the bolt end face, nut, and washer and bearing face. Figure 318: Nut at 100 % pre-torque CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 244/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual WARNING Rotating parts – Pinch point – Crushing hazard! When working with hydraulic and pneumatic torque tooling, ensure that your hands and any part of your body are not between any pinch points (e.g. any part of your body is not between the tool reaction arm and back up pressure surface). Ensure personnel have been properly trained on safe operations of hydraulic and pneumatic tools. Figure 319: Torque tool 16. Apply final nut turn 120 ° or two flats with an accuracy of ±5 °as specified in the 3MW Platform Bolt Torque Specification. The final nut turn can be achieved in any desired bolt pattern. 17. Make a color alignment mark on the screw bolt, nut and surrounding bearing surface of each bolted connection before going to the next nut. This is necessary to avoid losing track of which nuts have been tightened (as the blade is pitched to reach all screw bolts). Figure 320: 120 degree or 2 nut flats 18. Verify blade perimeter is clear of personnel rigging and auxiliary equipment, and pitch the blades as required to access and apply final nut turn (120 ° or two nut flats with an accuracy of ±5 °) to the remaining bolts. If a stud rotates more than 10 degrees during the nut turn contact the GE site representative. 19. Repeat steps 16 through 18 above for the remaining blades. 20. Verify blade perimeter is clear of personnel, rigging and auxiliary equipment, and pitch the blades as required verify pitch alignment. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 245/428 GE Renewable Energy – Original – Installation Manual 21. Verify the alignment of each blade by individually pitching the blades to 0 degrees. Rotate until the blade is in the horizontal position and the 0-reference mark is in the hub sight. 22. Verify the alignment of each blade by pitching the blades (individually) to 0 degrees. Rotate until the blade is in the horizontal position and the zero-reference mark is in line with the hub zero reference bracket (hub gun sight). 23. In this blade position, insert a straight edge through the hub gun sight to help align the blade zero-degree mark to hub gun sight. Figure 321: Zero reference mark in the hub sight 24. Mark a straight line with a (paint pen and punch mark marks) with a center punch tool. Initial, date & note "0 degrees" next to each paint pen reference mark. A - DR - Zero Degrees -01-30-2013 A Figure 322: Extend the marking with a marker pen 25. Verify that the hand rail and nose cone bolts have been torqued and marked with a paint pen. 26. Inspect both ends of the hand rail mounting brackets looking for damage, missing or cracked welds. Figure 323: Checking the hand rails and nose cone bolts CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 246/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 27. Install the cover plates over the pitch bearing using the provided M16 hardware along with medium strength thread locking compound. 28. Torque and mark bolts with a paint pen. Figure 324 Installing the steps over the pitch bearing teeth CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 247/428 GE Renewable Energy Installation Manual – Original – 13.4 Assembling the Nose Cone and Final Rotor Assembly Work NOTE Use of a retractable or a positioning lanyard is recommended. 1. Nose cone mating surface to hub shall be flat and clean of any contaminant. 2. Ensure bolt hole threads are clean and free of debris. NOTE If the nose cone is installed before the installation of the blades only remove the shipping material from the bolt mounting locations on the hub. Leave the other shipping material attached to the hub to protect it from the elements. The shipping material can be removed prior to assembling the rotor. Figure 325: Remove shipping material from bolt mounting locations on the hub NOTE Use hand tools only. Impact tools will damage fiberglass. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 248/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 3. – Original – Installation Manual Attach the lifting gear to the three lifting lugs of the nose cone. DANGER Crushing hazard! During Installation always ensure that hands, feet, and body are not between any potential pinch points. Figure 326: Lifting the nose cone Prior to installing the nose cone: 4. The nosecone will have to be set on temporary cribbing to remove the shipping supports. Wrench size is 24 mm. Figure 327: 5. Instruct the crane operator to slowly lift the nose cone and position it onto the hub. Figure 328: Lifting the nose cone CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 249/428 GE Renewable Energy 6. Installation Manual – Original – Bolt the nose cone onto the rotor hub. Critical to Quality: 7. Ensure the nose cone connection to hub is flat prior to torqueing. Check bolt hole alignment. After bolting, no gap allowed between mating surfaces, hub to nose cone. Do not force into position or over torque hardware. ATTENTION Safety relevant bolt connection! Glue bolt with middle hard thread locker. 8. Torque and mark the bolts with a paint pen in accordance with the latest revision Assembly Spinner to Hub DWG. 115W5268 and /or 114W4337. Contact GE representative for thread locking compound and assembly issues. 9. Remove the lifting gear. Figure 329: Bolting on the nose cone CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 250/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual Hub manhole cover tether: 10. Verify the hub manhole tether is available. If not present contact GE representative. Figure 330: Attaching the karabiner to the handle on hub cover CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 251/428 GE Renewable Energy – Original – Installation Manual 11. Once the hub installation is finished, unhook the karabiner from the handle and wrap the tether around the nose cone steel frame to prevent it from moving while the rotor is turning. Use the karabiner to fix it into position and make sure it is correctly secured. A: Carabiner B: Tether cable c: Nose cone steel frame Figure 331: Hub cover tether secured to nose cone steel frame 13.5 Final Rotor Assembly Work WARNING Electrical hazard! Stored energy may be present within electrical cabinets. Consult with GE engineering to identify the voltages that could be present. 1. Inspect all three blades for handling damage and report damage to GE site representative. All fiberglass damage must be repaired prior to rotor installation. 2. Verify that the light fixtures are not damaged. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 252/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 3. If applicable, verify the oil sight glasses for each pitch drive are protected from impact damage. 4. Secure any loose cable bundles that will flap back and forth to prevent damage. 5. Properly dispose of trash and debris from the interior of the hub. 6. Before exiting the hub verify the entire hub is clean and free of debris and loose tools that can cause damage. 7. Clean the interior of the hub with biodegreaser cleaner. Figure 332: Example desiccant packs ATTENTION If wind turbines will be idling without grid connection refer to the document Idling_Manual_3MW-DFIG-xxHz prior to removing desiccants packs. ATTENTION Risk of equipment damage! Please make sure that no loose equipment remains in or on the hub! Loose material left inside the hub will tumble when the rotor brakes are released and the rotor starts to spin creating dust debris damaging electrical components. Loose material such as desiccant packs, manuals, cable ties, tools, and rags must be removed out of all hub cabinets. Loose cables must be secured with cable ties to prevent damage when rotor starts spinning. Bolted desiccant packs must be securely bolted to the cabinets. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 253/428 GE Renewable Energy – Original – Installation Manual On the day of rotor installation: 8. Verify blade perimeter is clear of personnel, rigging and auxiliary equipment, and rotate all three blades to –90 degrees (trailing edge facing up). 9. Follow site-specific LOTO to de-energize the hub. 10. Disconnect the 400 V power cable. 11. Hub 400 V J-Box keys must be removed and turned over to GE. 12. Cut the cable ties from the limit switches. 13. Ensure the battery switches are in the "off" position and zip-tied. 14. Ensure the pitch boxes are de-energized. 15. Verify the manuals and desiccant packs in the hub main controller and axis boxes are removed. Critical to Safety and Quality: 16. In the hub, remove the following terminal block jumpers from the AEPC card in axis cabinet 1 after the rotor has been assembled: Terminal points J8.1 to TB1.3 Terminal points J8.2 to TB1.1 Terminal points TB1.2 to TB1.9 Terminal points TB1.4 to TB1.8 Figure 333: Removing J8 jumper connector Figure 334: Removing TB1 jumper terminal block CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 254/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 17. Re install factory terminal block to prevent damage due to loose cables flapping back and forth in the AEPC card. Figure 335: Installing factory terminal block Figure 336: Factory terminal block re-installed 18. Verify all cabinet doors are properly latched, ratchet straps are installed and loose strap ends are secured. 19. Ensure the hardware is secured and the manhole cover is mounted and tethered. 20. Use a high-pressure cleaner to remove all dirt and debris from the exterior of the rotor assembly. WARNING Potential hazards and environmental considerations associated with the use of a pressure washer! Possible environmental impact based on local codes. Excessive chemicals that have a potential negative impact on the environment must be removed before pressure washing. High pressure energy: Potential exposure to contaminated water and/or other chemicals. High pressure is generated by the pressure washer and has the potential to inject contaminated and/or other chemical treated water into body parts if personnel are careless and/or not trained properly. Follow manufacturers operation procedures and warnings. Walking working surfaces – un even slippery surfaces. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 255/428 GE Renewable Energy Installation Manual – Original – 13.6 Lifting the Rotor 13.6.1 Example Lifting Gear - Lifting Tool for 100 m and 103 m Rotor Diameter Typical Hub Configurations Typical 2500/2570 Typical 2900 Figure 337: Utilized on 120 m Rotor diameter and smaller Figure 338: Example 2900 hub Always Confirm Rotor lifting Equipment (Spiders) for 2500 and/or 2570 hubs 2900 hub and larger must be installed utilizing Single Blade Method the single blade Process (SBI). Refer to the latest GEI- for Single Blade Installation. NOTE The Installer is responsible to confirm hub configuration to ensure you have the correct lifting gear information. If you have any questions, contact your GE representative for clarification. Caution: For 2500 Spiders confirm orientation of spider to prevent improper lift angle. NOTE Please refer to outline drawing for the lifting point. Below pictures and process are for reference only. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 256/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 1. – Original – Installation Manual Unscrew the threaded rods, in order to retract the safety bolts. Figure 339: Unscrew the threaded rods The safety bolts must securely engage in the load-bearing plates of the rotor for lifting. Figure 340: Pins of the rotor lifting gear 2. Adjust the lifting gear to the respective rotor diameter in accordance with the manufacturer's instructions. Figure 341: Adjusting screws CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 257/428 GE Renewable Energy 3. Installation Manual – Original – Figure with retracted safety bolts, before the lifting gear is placed on the rotor. Figure 342: View of the lifting gear 4. Verify that the pins of the adjustable lifting gear are securely locked as shown in Figure 343 and Figure 344. Figure 343: View of the lifting gear Figure 344: View of the lifting gear CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 258/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 13.6.2 Attaching the Rotor Lifting Gear 1. Attach the lifting gear to the main crane. 2. Bring the lifting gear to the rotor spider. Figure 345: Bringing the lifting gear to the rotor 3. Mount the lifting gear in accordance with the manufacturer's instructions. Figure 346: Mounting the lifting gear Figure 347: Lifting gear attached to the rotor spider CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 259/428 GE Renewable Energy Installation Manual – Original – 13.7 Installing the Rotor (Hub with Blades) ATTENTION Check the wind speed! The rotor may only be installed in accordance with section 4.1 ‘Operations Involving the Use of a Crane’. ATTENTION Mind the lift plan! The sail area and drag coefficient of the rotor must be incorporated through the lift plan. Static loads and dynamic loads must be verified by the crane operator. Personnel not involved in crane lift operations must leave the crane work zone (danger zone) before lift operations start. Any person not involved with installation or crane lift operations shall be a minimum of two lengths of the crane boom height away from the work being performed. ATTENTION Risk of rework! Before installing the rotor, one of the holes in the perforated disk on the main shaft has to be exactly aligned with the rotor lock piston. The rotor must be mounted in the Y-position. At a maximum its position may deviate only one flange boring from the centric position (symmetric position of the rotor blades)! Failure to install the rotor in the Y-position in relation to the main shaft markings will require removal and repositioning of rotor. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 260/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual WARNING CRITICAL TO QUALITY to the safe operation of the turbine and to personnel safety! Verify the foundation bolts have been tensioned/torqued, and all tower flange bolts have been torqued. The GE Energy technical advisor will have the option to verify all paint pen marks are present at all bolted connections and the tower exterior is clean and free of damage prior to rotor installation. Inspect the interior and exterior pitch bearing seals. Look for cracked, gapped, missing or otherwise damaged seals. The seals must be smoothly seated around the entire bearing perimeter. If the seal is damaged contact the GE site representative. ATTENTION Prevent damage from the WTGS! If the rotor cannot be installed at this time, pitch all three blades back to the 0-degree position. Secure the rotor with ropes to suitable anchoring points. Also secure the leading edge of each blade (approx. 40 cm from the tip) to anchoring points using tag lines. Place protective mats between the blade and the tag lines to prevent damage. ATTENTION Risk of Equipment Damage! Close axis box panels, close the hub main access hatch, ensure all hardware is present and secure. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 261/428 GE Renewable Energy Installation Manual – Original – 1. Prior to lifting the rotor, starting with tail pick blade rotate to -90 degrees and attach crane. After tail pick blade is secure rotate the remaining two blades to -90 degrees (trailing edge facing up). On the blade opposite the rotor lifting gear: 2. Place and center blade vendor specific leading edge (LE) and trailing edge (TE) protective caps at lifting locations as per specific blade drawing. Figure 348: Placing LE&TE protective caps WARNING Danger of damaging the blade! Always check the trailing and leading edge protectors for padding to prevent blade damage. Always check the trailing and leading edge protectors for any debris that could damage the blades. NOTE CRITICAL TO QUALITY: Projects with multiple blade configurations ensure blade vendor specific edge protection is utilized. 3. Place and center slings at lifting locations as per specific blade drawing. Refer to drawing for min. sling width and length. 4. Attach the sling to the hook of the support crane. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 262/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual Example tag lines on non-serrated blades: 5. Place blade bags over the tips of blades no. 2 and 3. Attach a tag line to each bag. Continue with step 9 on page 266. ATTENTION Danger of damaging the blade! Do not tie tag lines to hub handrails, tie tag lines to the rigging only. Figure 349: Blade bags mounted non serrated blades Blades with serrations: Lifting blades with serrations can be accomplished by using a quick disconnect tool or equivalent that allows the installation team release the tail pick rigging without the use of man basket. NOTE Quick release tool is installer's responsibility to procure. GE can provide "Technical Guidance" for the hub fixture. A man basket will be needed to disconnect the support crane if you choose not to use quick disconnect. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 263/428 GE Renewable Energy – Original – Installation Manual Example tag lines on serrated blades: 6. Place blade sleeves for tag lines on the 2nd and 3rd blades. 7. Close the sleeve and insert the locking pin in the opening mechanism. 8. Attach a rope to the pin to unlock/open the sleeve after the rotor is installed. Figure 350: Typical sleeves Figure 351: Placing tag lines on serrated blades CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 264/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual DANGER Life-threatening hazard - working under suspended loads! Everybody must leave the danger area! The banksman may not give a signal to raise or lower until everybody has left the danger area. Never stay under suspended loads! ATTENTION Check the components! All components must be checked for visible damage, deformations and cracks which could affect their bearing capacity before assembly. Findings have to be reported to the GE site representative. The components must be stored and assembled in such a way that damage is prevented which could adversely affect their stability or bearing capacity and thereby lead to safety hazards. DANGER Crushing hazard! During installation always ensure that hands, feet, and body are not between any potential pinch points. ATTENTION Mind the weather conditions! The crane operator is responsible for monitoring the weather conditions at all times and determining when a safe lift of the rotor is possible. The tag lines must be secured to a suitable point (fastening point on a vehicle) at all times. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 265/428 GE Renewable Energy Installation Manual – Original – ATTENTION Danger of equipment damage! If the rotor assembly makes contact with any object it must be inspected before the installation proceeds. 9. Reach under the hub and loosen the guide pin (approximately 2.5 cm) directly beside the handrail between the two lifting lugs. This will allow the rotor to be installed more easily. 10. Verify the rotor is stabilized. Loosen and remove the nuts and washers from the transportation frame below the hub. Figure 352: Removing the shipping hardware WARNING Do not remove the hub bolts! The bolts and the threads could be damaged. Figure 353: Example damaged stud CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 266/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 11. When lifting the rotor the mounting flange must be kept perpendicular to the shipping fixture flange as much as possible to prevent the studs from binding on the fixture bolt holes and damaging bolt threads. 12. Instruct the crane operators to carefully lift the rotor horizontally and from a safe distance verify the shipping fixture is loose and bolts are not binding against the bolt holes. 13. Continue lifting until the studs clear the shipping fixture. Figure 354: Keeping the hub flange perpendicular to the shipping fixture ATTENTION CRITICAL TO QUALITY! Check for foreign debris on flanges! The hub is a friction-critical connection and must therefore be thoroughly cleaned of all foreign debris or dirt. If any foreign debris is found on the surface or pinched between the flanges after the installation, the rotor may have to be removed and cleaned. CRITICAL TO SAFETY! If flange surface cleaning is required, the rotor will need to be supported (stabilized) on a stand or cribbing with the crane holding the load to allow safe access for personnel to clean the flange and/or bolt holes as required. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 267/428 GE Renewable Energy Installation Manual – Original – 14. Lift the rotor by means of the main and support crane, so that the lower rotor blade cannot touch the ground while the rotor is being set upright. There must be permanent communication between the erecting engineers and the crane operators while the rotor is being set upright by the cranes, in order to lift the rotor without any danger. The rotor is set upright by the main crane lifting the rotor, while the support crane lowers the bottom rotor blade. Figure 355: Setting the rotor upright 15. Remove the lifting gear of the support crane from the rotor. Instruct the operator of the support crane to swing the jib out of the lifting area to ensure the main crane does not collide with the tag lines. NOTE If the blades have serrations a man basket will be needed to disconnect the support crane. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 268/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual Blades with serrations: Lifting blades with serrations can be accomplished by using a quick disconnect tool or equivalent that allows the installation team release the tail pick rigging without the use of man basket. NOTE Quick release tool is installer's responsibility to procure. GE can provide "Technical Guidance" for the hub fixture. A man basket will be needed to disconnect the support crane if you choose not to use quick disconnect. 16. The rotor can be safely guided from the ground by means of the two tag lines attached to the top rotor blades per blade manufacturer's instructions. Maintain the tension of the tag lines to control the rotor movement. The taglines can be anchored to a counterweight or vehicle but it is Critical to Quality to ensure any tag line pull or tug for flange alignment must be done manually. Pulling the tag line with a moving vehicle is not authorized. Figure 356: Examples to help control and stabilize the rotor with taglines 17. Verify the high-speed shaft shroud in the nacelle is removed to allow manual rotation of the high-speed coupler when mating the rotor to the main-shaft. Figure 357: High-speed shaft CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 269/428 GE Renewable Energy – Original – Installation Manual DANGER Crushing hazard! When installing or removing the rotor, ensure that your hands or any part of your body are not between the machine head and the rotor pinch point crush zone. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 270/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 18. Instruct the crane operator to lift the rotor so that it is level with the main shaft. Figure 358: Rotor level with the main shaft 19. Rotate the high-speed coupler to align the hub studs with the main shaft while ensuring that the rotor lock is aligned with a hole on the perforated rotor lock disk. This ensures that the rotor can be locked in the Y-position during hub entry. Figure 359: Rotor lock pin is aligned with a hole on the perforated rotor lock disk Figure 360: Example rotor in Y position CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 271/428 GE Renewable Energy – Original – Installation Manual WARNING Rotating parts! Untied long hair, loose clothing (e.g. flapping coats, tops with wide sleeves or trousers with wide trouser legs) as well as scarves, ribbons, headscarves or jewelry may not be worn during installation work! There is a fundamental danger of injury through being caught, pulled in or picked up by rotating components! Clothing must be adapted to the respective work and the weather conditions. WARNING Rotating parts! During application of the rotor lock always ensure that hands, feet, and body are not between the any potential pinch points e.g. high-speed coupling, brakes disc, mounting flanges. WARNING Rotating parts – Pinch point – Crushing hazard! When the main shaft is rotating, ensure that your hands and any part of your body are not in contact with the pinch point of the main shaft. Also ensure clothing and PPE are not caught in rotating parts (e.g. any part of your body is not between the main shaft and nacelle wall, hub and nacelle wall). Ensure the personnel are properly trained on safe operations of the rotor lock and the secondary brake. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 272/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual WARNING Hydraulic disc brake and high-speed rotor lock use! The installer must personally ensure all personnel assigned to work activities inside the WTGS are properly trained on the use of the hydraulic disk brake and rotor lock. The installer must ensure the hydraulic disc brake and rotor lock are 100 % engaged and locked out before attempting to pre-tighten and torque hardware after aligning the main shaft during rotor installation and after rotor is fully engaged onto the main shaft, disconnecting the main crane and removing it out of the working area after the rotor has been installed, performing any work outside or inside of the hub after rotor has been installed, performing any work inside or outside the nacelle near exposed rotating components after the rotor has been installed. All employees must ensure the hydraulic disk brake and high-speed rotor lock is 100 % locked out before exiting to the top of nacelle. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 273/428 GE Renewable Energy – Original – Installation Manual 20. Insert the guide pin in the main shaft. Again, ensure that the rotor lock is aligned with the rotor lock disk to ensure ther rotor is in the Y position when the rotor lock pin is engaged for hub entry. ATTENTION Risk of rework! Failure to install the rotor in Y-position in relation to the mainshaft markings will require removal and repositioning of the rotor. Figure 362: Hub stud aligned and engaged with the specific main shaft bolt hole WARNING Danger to life and equipment! If damaged during rotor installation bolts can be exchanged by hand tools or by hand. A maximum of two bolts may be exchanged while the rotor is mounted. All further exchanges/repairs have to be carried out on the ground. Figure 361: Example rotor in Y position hand rail centered perfectly with the center of the machine head. Figure 363: Rotor lock pin is aligned with a hole on the perforated rotor lock disk and hand rail centered perfectly with the center of the machine head Figure 364: Example rotor in Y position hand rail centered perfectly with the center of the machine head. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 274/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual ATTENTION Risk of equipment damage! The rotor must be guided precisely to prevent damage to the slipring wires. 21. Instruct the crane operator to move the rotor so that it fully engages with the main shaft. WARNING Risk of equipment damage! If for any reason the rotor is mounted in a wrong position, the rotor position needs to be corrected imediately at the time of installation/before torqueing the hub bolts. 22. Tighten the guide pin flush with the other hub adapter studs. Failure to tighten the guide pin prior to releasing the rotor brakes can result in damage to equipment. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 275/428 GE Renewable Energy Installation Manual – Original – 23. Install washers and nuts on all accessible hub adapter bolts by means of an impact wrench. 24. Before removing the lifting gear from the rotor at least 16 screws with 80-90 % of the final torque must be applied. Figure 365: Tightening the nuts WARNING Danger to life and equipment! If damaged during rotor installation bolts can be exchanged by hand tools or by hand. A maximum of two bolts may be exchanged while the rotor is mounted. All further exchanges/repairs have to be carried out on the ground. CAUTION Wear hearing protection! Proper hearing protection must be worn when working with any electrical or hydraulic impact tooling! Always assess the next task at hand. If 85 decibels will be exceeded, hearing protection must be worn. Observe requirements for hearing protection per your company's policies. WARNING Pinch point – Crushing hazard! When working with hydraulic and pneumatic torque tooling, ensure that your hands and any part of your body are not between any pinch points (e.g. any part of your body is not between the tool reaction arm and back up pressure surface). Ensure the personnel are properly trained on safe operations of hydraulic and pneumatic tools. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 276/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – 25. Turn the pressure relief valve of the hydraulic hand pump in a clockwise direction and pump the arm of the hand pump to activate the brake. WARNING Rotating parts – Pinch point – Crushing hazard! During application of the rotor lock always ensure that hands, feet, and body are not between the any potential pinch points e.g. high-speed coupling, brakes disc, mounting flanges. 26. Check the (high-speed) hydraulic disc brake for proper functioning. 27. Make sure that the blades are in pitch position of 85° (feathered position). 28. Using the hydraulic disc brake apply and release the brakes as needed to stop the rotor and align the (low-speed) rotor lock pin to the perforated disc. Figure 366: Hydraulic disc brake and hydraulic hand pump 29. The following pictures show an example WTG that is on the ground with the rotor lock pin aligned and fully engaged into the perforated disc. A B A - Perforated disc B - Rotor lock pin cylinder CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 277/428 GE Renewable Energy – Original – Installation Manual WARNING Rotor lock must not be used to stop rotation! Never use the rotor lock to stop drive train rotation. The hydraulic hand brake must be used to stop the rotation. WARNING Both rotor locks (high-speed shaft and lowspeed shaft) have to be used for 130 m and 137 m rotor diameter (redundancy requirement). Figure 367: Low-speed shaft rotor lock with lock and tag to apply LOTO 30. Engaging the pin of the low-speed shaft (LSS) rotor lock: Ensure that the appropriate hole of the rotor lock disk and the pin are aligned. Use a wrench with an opening of 17 mm and turn the spindle in counter clockwise direction until the pin is completely engaged. Insert the locking pin and attach lock and tag (LOTO). 31. Engaging the high-speed shaft rotor lock: Pull out the spring-loaded locking pin of the rotor lock to enable the crank mechanism and advance the rotor lock as far as possible. If necessary, briefly actuate/release the "rotor brake" by the switch on the gear box, in order to disengage the brake for a short time, thereby placing the brake disk in a better position. Fully engage the rotor lock until the locking pin locks home again at the lower position and attach lock and tag (LOTO). Figure 368: High-speed shaft rotor lock with lock and tag to apply LOTO CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 278/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 32. Turn the pressure relief valve of the hydraulic hand pump in a clockwise direction and pump the arm of the hand pump to activate the secondary brake (hydraulic disc brake). Figure 369: Hydraulic disc brake 33. The lifting gear can be removed after the threaded rods have been unscrewed. WARNING Fall hazard! Wear PPE to prevent yourself from falling down! WARNING Figure 370: Detaching the lifting gear Danger of falling objects! Do not stand under the load. Beware of falling tools and objects. Wear protective helmet! CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 279/428 GE Renewable Energy Installation Manual – Original – 34. Instruct the crane operator to remove the crane from the work area. 35. Release rotor lock and secondary brake to allow blade rotation. 36. Install and torque the remaining hardware. 37. Remove the blade bags and the tag lines as the blade rotates. NOTE If the blades have serrations a man basket will be needed after the rotor has been installed to remove protective caps and tag lines. Figure 371: Detaching the lifting gear ATTENTION Danger of equipment damage! As the rotor is pin-wheeling with the brake and rotor lock disengaged, listen within the nacelle for any loose materials, parts or tools remaining in the hub. Reapply the brake prior to installing the washers and nuts and disengage the brake prior to rotating the rotor. WARNING Rotating parts – Pinch point – Crushing hazard! When the main shaft is rotating, ensure that your hands and any part of your body are not in contact with the pinch point of the main shaft. Also ensure clothing and PPE are not caught in rotating parts (e.g. any part of your body is not between the main shaft and nacelle wall, hub and nacelle wall). Ensure the personnel are properly trained on safe operations of the rotor lock and the secondary brake. Critical to Quality to the safe operation of the turbine, and to personnel safety: 38. Apply final torque to all hub adapter hardware per 3MW Platform Bolt Torque Specification. 39. Place a paint pen mark across each stud, nut and flange face. 40. Clear the hub adapter flange area and disengage the rotor lock CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 280/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 41. Disengage the hydraulic rotor brake. 42. Slowly rotate the rotor with the tag lines to allow installation of the next set of accessible nuts. WARNING Rotating parts – Pinch point – Crushing hazard! When working with hydraulic and pneumatic torque tooling, ensure that your hands and any part of your body are not between any pinch points (e.g. any part of your body is not between the tool reaction arm and back up pressure surface). Ensure the personnel are properly trained on safe operations of hydraulic and pneumatic tools. 43. Repeat steps as required. Tighten all hub adapter nuts by means of an approved torque tool. 44. Check nuts #1, 2, 3, 4, 5 or more as required with maintenance torque to ensure tension has not released. If any nuts are loose, verify 100% of the connection until all are torqued. The 10% inspection cannot be performed until 100% is torqued. Details of the required torques can be found in the 3MW Platform Bolt Torque Specification. 45. Mark the bolts, nuts and adjacent flange surface of each bolted connection with a colored line. Figure 372: Mark the bolted connections CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 281/428 GE Renewable Energy – Original – Installation Manual 46. Mark the torque values on the fiberglass wall for later reference. Figure 373: Mark the bolted connections 47. Disengaging the low-speed shaft rotor lock: To disengage the pin: Remove the LOTO lock from the safety bolt. Disengage the safety bolt to ensure no damage is done to the safety bolt and or pin. Use a wrench with an opening of 17 mm and turn the spindle in clockwise direction until the pin is completely disengaged. Figure 374: Disengage the low-speed shaft rotor lock pin using a wrench 48. Disengaging the high-speed shaft rotor lock: Remove the lock and tag (LOTO). Pull out the spring-loaded locking pin of the rotor lock to enable the crank mechanism and turn the rotor lock gear out of the brake disk gear as far as possible. Make sure that the spring-loaded locking pin is engaged. Rotor lock is open. Figure 375: Disengage the high-speed shaft rotor lock pin CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 282/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 14 Checks If during an IIP inspection any bolt is found loose or not torque marked, all bolts in the circle must be inspected and torqued as required. 1. Ensure the hub-mounting bolts are 100 % torqued. 2. Perform a 10 % torque inspection on hub adapter nuts. The 10 % torque inspection will be spread out evenly on the hub adapter flange. 3. Re-install the hub adapter flange cover. ATTENTION Rotating parts – Pinch point – Crushing hazard! When main shaft is rotating, ensure that your hands and any part of your body are not in contact with the rotating parts of the main shaft and highspeed shaft. Also ensure clothing and PPE are not caught in rotating parts (e.g. any part of your body is not between the main shaft or high-speed shaft or brake disc). Ensure the personnel are properly trained on safe operations of the rotor lock and the secondary brake. To check the brake pad and disc for uniform distance (brake pads must be centered and not drag on the disc). 4. Apply the rotor lock. 5. Bleed the pressure from the system. 6. With the brake completely open, inspect the air gap between the brake pad and disc for uniform distance. If the distance is even, continue with step 12 below. If the distance is uneven, adjust the brake as follows: Figure 376: Checking air gaps 7. Loosen the lock nut. 8. Adjust the air gap between the brake pad and the disc by turning the screw. (Adjustment gap consult with GE site representative). 9. Tighten the lock nut. 10. Assure application of Rotor Lock LOTO following the appropriate LOTO procedure before entering the hub. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 283/428 GE Renewable Energy – Original – Installation Manual ATTENTION Danger of equipment damage! In the hub, confirm the following terminal block jumpers from the AEPC card in axis cabinet 1 have been removed: Terminal points TB1.2 to TB1.9 Terminal points TB1.4 to TB1.8 Terminal points J8.1 to TB1.3 Terminal points J8.2 to TB1.1 Ensure the manufacturer terminal block is connected. Reference section 13.5 Final Rotor Assembly Work. 11. Seal hub and shaft joint/connection: Execute hub entry procedure. Engage the rotor and hydraulic brake. Apply Sikaflex® from inside between hub and shaft joint / connection. Figure 377: Sikaflex® 12. Verify the nacelle top rigging hatch is installed. 13. Verify that the front and rear hatches in the nacelle roof are closed and latches are engaged. 14. Verify the floor hatch is secured. 15. Clean scuff marks from the tower interior. 16. Apply touch-up paint as necessary. 17. Once the rotor is installed, the high-speed coupling cover must be completely installed, all hardware must be accounted for and snug tight. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 284/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 18. Remove all tools and debris from the interior of the nacelle. WARNING Rotating parts – Pinch point – Crushing hazard! When the main shaft is rotating, ensure that your hands and any part of your body are not in contact with the pinch point of the main shaft. Also ensure clothing and PPE are not caught in rotating parts (e.g. any part of your body is not between the main shaft and nacelle wall, hub and nacelle wall). Ensure the personnel are properly trained on safe operations of the rotor lock and the secondary brake. 19. Release the rotor lock. WARNING Prevent damage from the WTGS! The installer must ensure that the rotor lock and the high-speed brake are released after the crane has moved out of the area and work has been completed. Never leave the rotor lock and the brake applied overnight. 20. Perform a 10 % torque inspection of all the tower flange connections. Figure 378: 10 % Inspection CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 285/428 GE Renewable Energy Installation Manual – Original – 21. Perform a 10 % torque inspection of anchor bolts. The 10 % torque check marks need to be clearly visible for future maintenance inspections. Figure 379: Example anchor bolt 100 %torque and 10 % marks 22. In order to provide a reliable corrosion protection, paint the flanges once again. Referto SDS. 23. Clean scuff marks from tower interior. 24. Apply touch-up paint as necessary. 25. Ensure all the work is inspected in accordance with the Installation Checklist (ICL) and Installation Inspection Procedure (IIP). Figure 380: Applying touch up paint CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 286/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 15 Cables DANGER Electrical hazard! Refer to the latest revision Energization Process Flow Chart and Verify GE and Customer LOTO procedures are complementary. Follow site specific LOTO policy if LOTO needs to removed or re-applied. Ensure all pre- energization/de-energization checks per Site Specific LOTO are adhered to prior to beginning any work. Follow electrical PPE requirements in the Electrical Service Bulletin (Element HS 13. 2C) for any electrical work on the WTG (See the EHS Outage Plan or the Construction EHS Plan). CAUTION Awkward postures / Reach / Fall Hazard! The cable access points are located in limited space and difficult to reach areas. If an employee is working at a height that exposes them to a potential fall, an appropriate ladder and/or fall arrest equipment must be used as required, and 100 % tie-off at all times. A retractable lanyard can be utilized. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 287/428 GE Renewable Energy – Original – Installation Manual 15.1 Slip Ring Wires DANGER Rotating parts – Danger of crushing During application of the high-speed brake always ensure that hands, feet, and body are not between any potential pinch points e.g. high-speed coupling, brake disc, mounting flanges. The high-speed coupling can only be stopped using the hydraulic brake. WARNING Rotating parts – Pinch point – Crushing hazard! When the main shaft is rotating, ensure that your hands and any part of your body are not in contact with the pinch point of the main shaft. Also ensure clothing and PPE are not caught in rotating parts (e.g. any part of your body is not between the main shaft and nacelle wall, hub and nacelle wall). Ensure the personnel are properly trained on safe operations of the rotor lock and the secondary brake. WARNING Rotating parts! Untied long hair, loose clothing (e.g. flapping coats, tops with wide sleeves or trousers with wide trouser legs) as well as scarves, ribbons, headscarves or jewelry may not be worn during installation work! There is a fundamental danger of injury through being caught, pulled in or picked up by rotating components! Clothing must be adapted to the respective work and the weather conditions. DANGER Rotor Lock not to be used to stop rotation! Never use the low-speed shaft rotor lock or high-speed shaft rotor lock to stop drive train rotation. The hydraulic hand brake must be used to stop the rotation. No hub entry on wind speeds > 14 m/s, 12 m/s with 120, 130 and 137 meter rotors. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 288/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – 1. Perform hub entry procedure (apply LOTO Rotor Lock LOTO). 2. Check the (high-speed) hydraulic disc brake for proper functioning. 3. Make sure that the blades are in pitch position of 85° (feathered position). 4. Using the hydraulic disc brake apply and release the brakes as needed to stop the rotor in the Y position. 5. Apply the low-speed shaft rotor lock and the high-speed shaft rotor lock. Figure 381: Hydraulic disc brake and hydraulic hand pump Figure 382: Rotor stopped in the Y-position The following pictures show an example WTG that is on the ground with the rotor lock pin aligned and fully engaged into the perforated disc. A - Perforated disk A B B - Rotor lock pin cylinder CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 289/428 GE Renewable Energy Installation Manual – Original – WARNING Rotor lock must not be used to stop rotation! Never use the rotor lock to stop drive train rotation. The hydraulic hand brake must be used to stop the rotation. WARNING Both rotor locks (high-speed shaft and low-speed shaft) have to be used for 130 m and 137 m rotor diameter (redundancy requirement). 6. Engaging the pin of the low-speed shaft (LSS) rotor lock: Ensure that the appropriate hole of the rotor lock disk and the pin are aligned. 7. Use a wrench with an opening of 17 mm and turn the spindle in counter clockwise direction until the pin is completely engaged. Insert the locking pin and attach lock and tag (LOTO). Engaging the high-speed shaft rotor lock: Pull out the spring loaded locking pin of the rotor lock to enable the crank mechanism and advance the rotor lock as far as possible. 8. Figure 383: Low-speed shaft rotor lock with lock and tag to apply LOTO If necessary, briefly actuate/release the "rotor brake" by the switch on the gear box, in order to disengage the brake for a short time, thereby placing the brake disk in a better position. Fully engage the rotor lock until the locking pin locks home again at the lower position and attach lock and tag (LOTO). Figure 384: High-speed shaft rotor lock with lock and tag to apply LOTO Apply LOTO lock to prevent the locking pin from accidentally disengaging. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 290/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 9. – Original – Installation Manual In an energized tower verify all applicable breakers, switches, and overloads in the top box and hub main controller are in the “Off” position. If applicable, place the UPS switch in the off position. 10. Enter the hub. 11. Verify all batteries and main switches for each axis box are in the “Off” position. 12. Confirm all temporary jumpers have been removed. 13. Confirm the bypass plug of the AEPC card is disconnected and the current plug for the AEPC card is connected. 14. Retrieve the conduit from the top box and place it in the hub. 15. Using the hub junction box key, open the box cover. Figure 385: Junction box cover 16. Prior to running the slip ring cables through the conduit, check all cables for pinched and/or damaged insulation and exposed strands. If damage is found, the slip ring cables must be replaced. Notify GE site representative if any damage is found. Figure 386 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 291/428 GE Renewable Energy Installation Manual – Original – 17. Do not remove any electrical tape covering wire ends. 18. Remove the elbow from the conduit. 19. Feed the cable bundle through the conduit. B A - Flex conduit A B - Slip ring wires Figure 387 20. Feed the cable bundle through the access hole of the hub junction box. 21. Install the elbow and the seal of the hub junction box onto the conduit. 22. Tighten the flex conduit lock ring (see arrow in adjacent figure). A - Junction box hole B B - Locking ring C - Elbow or connector A C Figure 388 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 292/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 23. Secure the slip ring flex conduit to the brace with a minimum of 4 cable ties and route it correctly to the junction box. 24. Route the cable bundle neatly in the junction box. Remove the tape from the slip ring cable bundle. Figure 389: Secure slip ring flex conduit to the brace 25. Terminate the cables in the hub junction box. Contact the GE site representative for the latest wiring chart. The following tooling is recommended to prevent damage to wire terminal: (Wago 5.5 mm) screwdriver or Clutch Type G Power Bit, 3/16, 2 In L Grainger Item # 1YHY3 Brand IRWIN Mfr. Model # 3052036 UNSPSC # 27112814 Figure 390 26. Use caution when inserting the ferrules into the terminals. Make sure that the ferrule is inserted into the block and not behind the block. Do not over tighten the screw of any terminal onto the plastic sheath of the ferrule. 27. Perform a wire pull test on every wire after terminating to ensure that no wires are loose. 28. Check for wire strands and remove them from the cabinet. 29. Perform a pull test on each conductor to ensure proper termination. 30. Verify the wire runs are neat and secured with cable ties if necessary. 31. Remove all materials and tooling from the slip ring junction box. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 293/428 GE Renewable Energy – Original – Installation Manual NOTE Prevent damage to the WTGS! Loose cabinet doors will tumble and damage equipment inside the hub when the rotor is spinning. 32. Close and secure the hub junction box doors. Verify the locking mechanism is engaged. Figure 391: Verify the lock clip is engaged 33. If applicable, install straps on the hub main control cabinet and each axis box. Figure 392 34. Inspect all three hub axis cabinet doors, ensure all lock mechanisms are properly engaged. ATTENTION Prevent damage to the WTGS! Loose manuals/desiccant bags will pulverize create dust and debris damaging the equipment if they are left inside the hub while the rotor is spinning CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 294/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual ATTENTION Prevent damage to the WTGS! Make sure, that all cables are fixed to prevent damage! 35. Verify entire hub is clean and free of trash, debris and loose tools that can cause damage. 36. Verify the hub access cover is re-installed and all hardware is present. 37. Disengaging the low-speed shaft rotor lock: To disengage the pin: Remove the LOTO lock from the safety bolt. Disengage the safety bolt to ensure no damage is done to the safety bolt and or pin. Use a wrench with an opening of 17 mm and turn the spindle in clockwise direction until the pin is completely disengaged. Figure 393: Disengage the low-speed shaft rotor lock pin using a wrench 38. Disengaging the high-speed shaft rotor Lock: Remove the lock and tag (LOTO). Pull out the spring-loaded locking pin of the rotor lock to enable the crank mechanism and turn the rotor lock gear out of the brake disk gear as far as possible. Make sure that the spring-loaded locking pin is engaged. Rotor lock is open. Figure 394: Disengage the high-speed shaft rotor lock pin CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 295/428 GE Renewable Energy – Original – Installation Manual 39. Always adhere to Rotor lock LOTO procedures. 40. Check the (high-speed) hydraulic disc brake for proper functioning. DANGER Clear all personnel and equipment from all rotating parts, pinch/crush hazard areas. Figure 395 41. Release the hydraulic disc brake: Verify the low-speed rotor lock is fully retracted (disengaged from the perforated disc) and is not dragging. Verify the brakes are mechanically released, the high-speed brake pads are centered and not dragging on the disc. Verify the rotor is completely free and can rotate. 42. Contact GE personnel if brake disc is dragging. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 296/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 15.2 Lowering the Power, Control & Communication Cables DANGER Danger of falling! The safety harness must always be fastened as described in the Safety Manual! DANGER Falling objects hazard! Cables are heavy and may require multiple crew members located thought the tower and or equivalent mechanical means as required to lower cables in a controlled manner. If the cables begin to fall uncontrollably do not attempt to stop them as this can cause serious injury. DANGER Falling hazard! If an employee is working at a height that exposes them to a potential fall, an appropriate ladder and/or fall arrest equipment must be used as required, and 100 % tie-off at all times. A retractable lanyard can be utilized. NOTE Always lower the cables in a hand over hand fashion. Never drop the cables as this can cause internal damage to the conductors. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 297/428 GE Renewable Energy Installation Manual – Original – Figure 396: Work at saddle WARNING Electrical hazard! High/medium voltage grid may be present inside the turbine, collection system terminates at the 2nd level switch gear. Verify that the customer LOTO plan and the GE LOTO plan are complementary to ensure the equipment is de-energized. Site specific LOTO must be implemented before work begins. WARNING Electrical hazard! The rotor must be locked before performing phase check and electrical validation testing and before terminating the generator cables. Verify appropriate energy isolation procedures are followed based on local standards and/or GE requirements. I.e. local standards, customer LOTO plan and GE LOTO plan must be complementary to ensure the equipment is deenergized. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 298/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual ATTENTION Ensure the E-stop, yaw switch & control cables are pulled out of way so that they do not get tangled and to prevent damage during cable drop – Verify enough slack is present to attach control boxes to plate on the opposite side. CAUTION Know what you are lifting! When the weight exceeds the limit for a single person, or if the load is awkward / difficult to maneuver due to shape or size: Request the help of a second person. Transfer the load into smaller containers or use the crane or a fork lift. Reference assembly drawings for weights. ATTENTION Extreme Cold Weather Sites: Cold weather sites may require warming up the cables before handling to prevent damage to the cable insulation and to remove the cable bundle memory. Refer to Work Instructions - Cold Weather Cable Installation Guidelines for recommendations. CAUTION Awkward postures / Reach / Fall hazard! The cable access points are located in limited space and difficult to reach areas. If an employee is working at a height that exposes them to a potential fall, an appropriate ladder and/or fall arrest equipment must be used as required, and 100 % tie-off at all times. A retractable lanyard can be utilized. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 299/428 GE Renewable Energy – Original – Installation Manual The Power, Control & Communication Cables are shipped inside the machine. It is recommended coordinating with the mechanical installer to ensure the cables are not disturbed, tangled or damaged during the nacelle and rotor installation process. Any damage to the cables must be reported to GE site representative. The cables are terminated to the top box and routed through a series of cable trays and coiled towards the front of the machine head underneath the main shaft. 1. If applicable, while the unit is on the ground check the cable arrangement and re arrange as required in the sequence that better suits the installer’s process ensuring that the cables do not get damaged. Figure 397 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 300/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 2. – Original – Installation Manual The crew member located in the nacelle will sort/identify as required and lower the control and communication cables down through the yaw deck opening with the assistance of a crew member located on the yaw deck, starting with the largest diameter cable first. NOTE When lowering the cables provide sufficient amount of slack so that the cables are not placing too much load on any object and cables do not get damaged due to friction, sharp objects or damage to the insulation due to cable weight. Figure 398: Lowering the cables CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 301/428 GE Renewable Energy – Original – 3. The crew member on the yaw deck will carefully help support the weight and lower the cables through the hole opening down to the crew member located at the cable guide platform (saddle deck). 4. Provide a sufficient amount of slack between the yaw deck cable guide platform and the nacelle so that the cables are not putting a load on the cable bundle to prevent chaffing damage. 5. Allow adequate clearance over the hoist, ladder, and safety cable anchor and the safety climbing system. 6. The nacelle/ yaw deck crew person will advise the saddle crew when there is enough slack left on the cable bundle to form the required drip loop at the saddle. 7. The saddle crew will temporarily secure the cable ensuring there is enough cable slack to form the required drip loop. 8. Refer to next chapter for final drip loop dimensions. Installation Manual Yaw deck NOTE CRITICAL TO QUALITY AND SAFETY! Ensure the cables are secured in multiple locations through the tower ensuring the weight of the cable and temporary cable support means are sufficient and do not damage or cut into the insulation. NOTE Saddle deck CRITICAL TO QUALITY! When securing cables to cable tray(s) or other means verify that the cables do not exceed the cable size specific minimum bend radius at all places where they would be likely to damage the insulation on conductors. Figure 399 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 302/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 9. – Original – Installation Manual Verify that the length of the power, control and communication cables allow for termination in the main controller MCC, LVDP and CCC cabinet in the PPM before proceeding. 10. Coil the excess cables and secure out of the working area. 11. Keep the cables separated and untangled as much as possible as this will make it easier for the crews to help build the final cable bundle down the tower later on through process. 12. When lowering the fiber optic cable, take care that it is not crushed, pinched between sharp objects, or bent sharply (smallest bend radius 113 mm), as this will cause permanent damage to the cable. 13. Lower the hoist power cable located at the bottom of the top section with the communication cable bundle. 14. If applicable: If the aviation lighting is installed and terminated to the top box, the power and photocell cables must be lowered down the tower with the other power, control and communication cables. Figure 400 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 303/428 GE Renewable Energy – Original – Installation Manual 15. After all the control and communication cables have been lowered arrange the cables in a bundle keeping the cables uniform and straight. 50cm 16. Tape the cables together temporarily using insulating tape at intervals of 50 cm to form a bundle. Start at the yaw deck and continue down to the saddle. Figure 401 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 304/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 17. Lower the cable down through the top platform, and lead them over and behind the cable guide platform down to the bottom of the tower. Rotor 690 V Rotor PE 6 kV 18. Arrange the control / communication bundles on the right side of the saddle (when viewed facing the tower wall). PE & Neutral 400 V tor PE Comm bundle 19. Form the communication cable bundle final drip loop per the dimensions provided in the next chapter. 20. Secure the cable bundles to the cable tray under the saddle with cable ties in a cross pattern. 21. Continue bundling the cable routing it to the tower cable tray maintaining the minimum bend radius. Figure 402: Identification of the cable bundles Figure 403: Typical “NEW” BoM Structure for 110mHH (Cable transition below the saddle) Figure 404: Typical “OLD” TPH structure for 98.3mHH (Cable transition below the saddle) CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 305/428 GE Renewable Energy – Original – Installation Manual 22. On the tower cable tray secure bundle with cable ties on every rung for the first 12 rungs and every third rung after that on the tray. Figure 405: Typical “NEW” BoM Structure for 110mHH (Cable transition below the saddle) Figure 406: Typical “OLD” TPH structure for 98.3mHH (Cable transition below the saddle) CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 306/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 23. The fiber optic cable is routed on the outside of the bundle and secured with cable ties to the cable bundle between every rung for the first 12 rungs on the tray. After 12 rungs, ties can be spaced to between every third rung all the way down the tower. Figure 407 24. Allow enough excess cable to accommodate the bridge at the tower flange connections. Finish forming at the bridge locations during rotor, stator, and ground cable installation. Figure 408 25. At the bridge locations secure the power and communication cables at every rung on the cable bridge and every third rung after that. Figure 409 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 307/428 GE Renewable Energy – Original – Installation Manual 26. Terminate the lights and receptacles at each level per the latest tower 109W3886 schematics. 27. Connect the lighting and power sockets. Figure 410 Figure 411 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 308/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – DANGER Falling hazard! If an employee is working at a height that exposes them to a potential fall, an appropriate ladder and/or fall arrest equipment must be used as required, and 100 % tie-off at all times. A retractable lanyard can be utilized. A 28. At the converter level the communication cables will transition to the right onto the horizontal cable tray and then down through vertical tray. 29. When cables go from horizontal to vertical ensure the minimum bend radius is maintained. B 30. On the vertical tray located next to the light fixture the cables will be positioned on the left hand side of the cable tray. A - Horizontal cable tray B - Vertical cable tray cables secured on the left-hand side Figure 412 31. The communication bundle at the converter level will be located on the left side of the cable tray going down to the Controller/Transformer level. Figure 413 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 309/428 GE Renewable Energy – Original – Installation Manual DANGER Falling hazard! If an employee is working at a height that exposes them to a potential fall, an appropriate ladder and/or fall arrest equipment must be used as required, and 100 % tie-off at all times. A retractable lanyard can be utilized. 32. On the controller/transformer level continue securing the cable bundle to the cable tray with cable ties. Figure 414 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 310/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 33. On the transformer level transition the cable bundle from the tower cable tray over the DIN Rail. 34. Secure cables to the upper DIN rail with cable clamps allowing for a 100 to 150mm drip loop between the tower and the DIN rail. 35. From the DIN rail route the cables to the transformer cable tray and into the MCC/LVDP. Refer to the latest point to point drawing for cable designations. Figure 415 ATTENTION Excess cable! The GE WTG has extra cable for the service loop. Upon customers request the cables can be cut back and re-ferruled for appearance purposes. Customer will be responsible for additional ferrules and responsible to ensure proper identification of the cables is completed. ATTENTION Cutting cables - CRITICAL TO QUALITY! When cutting around the circumference of the outer insulation of a multi conductor cable, care must be taken not to cut or nick the insulation of the inner conductors. Always inspect for damaged or cut strands near the outer insulation and repair as needed. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 311/428 GE Renewable Energy – Original – Installation Manual ATTENTION Wire ferrules - CRITICAL TO QUALITY! All wires must be ferruled. When crimping ferrules, always select the proper crimping tool for the job. Do not use a ring crimper to crimp a ferrule and vice versa. When applying ferrules or ring terminals, make sure that the conductors are stripped to fill the entire length of the barrel. The insulation of the conductors must be fully inserted against the plastic base. No copper should extend from either end of the ferrule or ring. Always check the crimp for broken or bent pins and make sure the terminal will not pull off the wire. 36. Secure the cables with cable clamps at the DTA access point. 41. 37. Inside the cabinet, route to the cables through the cable trays to the terminal blocks ensuring the appropriate bend radius is provided. 38. Terminate the wires in the respective terminal block in MCC/LVDP/CCC according to the latest point to point drawing. Critical to Quality: 39. Verify all wires are ferruled. Use caution when inserting the ferrules into the terminals. Make sure the ferrule is inserted into the block and not behind the block. Do not over tighten the screw of a terminal onto the plastic sheaf of the ferrule. 2222222222222222 40. Perform a wire pull test on each wire after terminating to ensure that no wires are loose. Figure 416 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 312/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – 15.3 Lowering the Generator, Rotor, Stator & Ground Cables The stators, rotor, and 400 V are shipped inside the machine coiled towards the front of the WTG underneath the main shaft. Any damage to the cables must be reported to GE site representative. 1. In the WTG Identify the cable bundles: 1 trefoil for the stator cables (L1, L2 & L3) 1 PE (stator ground) 3 trefoils for the rotor cables with K - L - M in each rotor ground 1 trefoil 400 V (L1, L2 & L3) 1 PE 1 Neutral A - Rotor cables B - 6 kV stator cables A B Figure 417: Generator stator connection – 6 kV and rotor cables 2. If cables are not marked open the generator rotor collector box to identify the different phase cables K – L - M. Multiple Generator configuration cables may need to be rotated for other turbine configurations. Figure 418: Rotor cables from generator junction box K, L, M CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 313/428 GE Renewable Energy 3. Installation Manual – Original – Identify the cables in cable bundles below the components from the generator to the gearbox. The new position of the cable bundles must allow some space between the cables. 4. Put new cable ties around the bundles all along the cables. 5. Use several cable ties along the power cables to fix them in bundles. 6. Ensure bend of the cables does not exceed the minimum bend radius. 222222 Generato r Figure 419 The crew person located in the nacelle must separate the stator and ground cables and mark them with phase tape. 7. Secure the phase cable sets before entry and after exit of the double cable guide platform by means of cable ties at intervals of 15 cm. 8. Ensure cable ties do not create pressure points or sharp edges and do not contact other cables. 9. Verify that the cables are routed evenly and do not cross. 10. Cable from waterfall will be arranged different which will affect spacer arrangement. 11. Add cable designations. Figure 420 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 314/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – 12. The crew person located in the nacelle must lower the cables down through the yaw deck opening one at a time with the assistance of a crew person located on the yaw deck. Yaw deck Saddle deck Figure 421 13. The crew person located on the yaw deck must lower the cables down through the yaw deck hole to the cable guide platform (saddle). Figure 422 14. Route the cables through the tower collector ring located between the yaw deck and the saddle. Verify that the cables are routed evenly and do not cross. A A - Collector ring CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 315/428 GE Renewable Energy Installation Manual – Original – Figure 423 15. After all the cables are lowered, install the support plate to the beam at the yaw deck. 16. Install the switch buttons to the support plate. Ensure the switch buttons face towards the back (generator side), away from the cable bundle. A A – Generator side A Figure 424 Figure 425: Install the switch plate and buttons CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 316/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 17. Once all cables are lowered five spacers have to be installed along the cable line. The position of the spacers is defined in the adjacent figure. +- 50mm on all spacers. Dimensions are taken from center to center of the spacers. NOTE This does not apply to 3.8. The 3.8 design has 3 spacers only. Consult with GE representative for latest GEI. Figure 426: Distribution of the spacers (measure given in m) CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 317/428 GE Renewable Energy Installation Manual – Original – 18. Identify the cable trefoils/bundles as they were laid from this point to down tower. 19. Keep the same trefoils/bundles and tie them together with cable ties. NOTE Make sure that the heads of all cable ties around the cable bundles are pointing outwards to avoid damages to the other cables. Rotor 690 V Rotor PE 6 kV PE & Neutral 400 V tor PE Comm bundle Figure 427: Distribution of the cables 20. Prepare all spacers by removing the metal band. Figure 428: CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 318/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 21. Beginning with the top spacer at the yaw deck, position the spacer in between the cable bundle and push the cable trefoil/bundle into the spacer slots as shown in adjacent figure. Figure 429: Preparation of the spacers 22. Arrange the communication cable bundles in the upper most spacer with the 6 kV and the 690 trefoils opposite of the communication bundles. NOTE There may be some variation in the arrangement depending on the yaw angle of the machine head to the cable saddle. In some cases it may require a minimum of crossing of trefoils between the lowest spacer and the saddle deck. See Figure 426: Distribution of the spacers (measure given in m) as reference. Figure 430: Distribution of the cables CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 319/428 GE Renewable Energy Installation Manual – Original – The spacer does have eight chambers. The picture shows the top view of the spacer: 50 Hz: Chamber 1 3x1x150qmm Chamber 2 1x1x240qmm (PE) Chamber 3 3x1x240qmm Chamber 4 3x1x240qmm Chamber 5 3x1x240qmm Chamber 6 3x1x95qmm (400V) Chamber 7 all 10 control cable (24V and 230V cable) Chamber 8 2x 1x95qmm(N, PE), 1x 1x50qmm (PE) Figure 431: Distribution of the cables 60 Hz: Chamber 1 3x 1x350kcmil Chamber 2 1x 1x535kcmil (PE) Chamber 3 3x 1x535kcmil Chamber 4 3x 1x535kcmil Chamber 5 3x 1x535kcmil Chamber 6 3x 1x3/0AWG (400V) Chamber 7 all control, 24V and 230V cable (~10x) Chamber 8 2x 1x3/0AWG (N, PE), 1x 1x1/0AWG (PE) CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 320/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 23. Measure the location of the spacer and adjust as required to the dimensions provided in illustration in previous for distribution of the spacers. Figure 432 24. Install and tension the metal band. 25. Tighten the bolt using the Allen key, size 8, until the clamping strap ends touch (max. torque 35 Nm!). Figure 433 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 321/428 GE Renewable Energy Installation Manual – Original – 26. Repeat steps for the remaining spacers, using a scaffold for installation of the spacers 2, 3 and 4. Figure 434: Finished spacers 27. Once the spacers are installed, lower the fiber optic through the center of the spacers. 28. Secure the fiber optic to the communication cable bundle and to each spacer with a cable tie. 29. If applicable, remove any cable tie sharp ends and or wrap the cable tie ends with electrical tape to protect other cables from damage. Figure 435 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 322/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – DANGER Fall hazard – Open holes! Falling hazard! If an employee is working at a height that exposes them to a potential fall, an appropriate ladder and/or fall arrest equipment must be used as required, and 100 % tie-off at all times. A retractable lanyard can be utilized. 800 mm Cover open holes as required. 30. The installer located at the cable guide platform has to route the cables over the cable guide platform and form an initial drip loop measuring approx. 1-1.5 m (42 inches) from the cable tie location to the bottom of the drip loop. Figure 436: Lowering the cables down further 31. If applicable, temporarily install two cable ties around each cable securing it back to itself immediately below the cable guide platform to support the extra cable weight. 32. The final drip loop must extend at least 800 mm below the cable guide platform measured from the bottom of the saddle to the top of the drip loop. Ensure sufficient clearance to surrounding mechanical parts. 33. Pull the cables through the remaining cable tray in the tower top. 34. The twist shall be evenly distributed throughout the cables bundles. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 323/428 GE Renewable Energy – Original – Installation Manual 35. Pull the generator stator and ground and all other cables over the cable saddle. Rotor 690 v Rotor PE 6 kV PE & Neutral 400 V tor PE Comm bundle 36. They are arranged in this order for best transition to the cable ladder in the tower. Critical to Quality: 37. Secure cables with cable ties ensuring that the heads of all cable ties around the cable bundles are pointing outwards, and no sharp ends are left on the ties to avoid damages to the other cables. No cable ties between spacers 38. Pull the ground cables through the transition cable tray and secure with cable ties. 12 -15in. below the cable saddle tie holes. 39. Verify that the cables are properly supported at the transition. 40. If applicable, cut the cable ties securing each cable to itself below the cable guide platform. No cable ties in this area Figure 437: Identification of the cable bundles 41. Pull the cables through the remaining cable tray in the tower top. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 324/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 42. Apply High temp protection tape to the cables in accordance with the latest GEI. Figure 438: High temp protection tape application area NOTE Refer to “1.6-100_2.x_xxHz_WDI_RETR_cable_ArmorcastInst” for application of adhesive permeated fiberglass. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 325/428 GE Renewable Energy – Original – Installation Manual 43. Install adhesive permeated fiberglass (e.g., Armorcast) to power cable, exposed to the cable collector rings and „Platform A‟ opening to avoid cable wear during operation. NOTE 3.8 uses bumper design and does not require Armorcast. Reference the Latest GEI. 44. The Installation shall be done by wrapping each trefoil of power cables starting approx. 15 cm below and ending approx. 15 cm above the collector ring. 45. To cure the adhesive permeated fiberglass, spray it with pure water after wrapping. Secure the adhesive permeated fiberglass with a cable tie at both ends. Figure 439: Example Armorcast application area 46. Ensure adhesive permeated fiberglass mixture is consistent with manufacturer specification to ensure adhesive permeated fiberglass is adhered to the cables correctly. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 326/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 15.3.1 Arranging the Cables at the Transition between the Cable Saddle and the Tower Cable Tray Once the drip loop has been formed and the cables are secured to the saddle, the cables can then be arranged between the saddle and the tower cable tray. The sequence in which the cables are secured between the saddle and the tower tray does not matter as long as: The correct cable phasing order is maintained for best transition to the cable ladder to match the cable arrangement in the tower with minimal crossing of cables. The minimum bend radius of the cables is not exceeded. Cables are protected from sharp edges e.g., metal or cable tie sharp ends. Enough cable ties are used to support the weight of the cable to protect the cables from cables from chaffing against each other. NOTE The switch is located in the machine head and will be installed in manufacturing. Since the communication cables will not be spliced, the cable bundle can be formed and secured to the cable tray with cable ties all the way down the tower as per previous chapter. There are two different tower electrical internal designs: “OLD” TPH structure for 98.3 m HH “NEW” BoM Structure for 110 m HH Figure 440: Cable trays at saddle CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 327/428 GE Renewable Energy – Original – Installation Manual Plastic Cable Ties Plastic cable ties are required to secure the cables to the Cable tray transition below the saddle. All Cable ties must be installed with an installation gun set to 104lbs +/- 8lbs or 463N +/- 36N of tension. The installation gun must be approved with plastic zip tie vendor to provide consistent pressure and cleanliness. Cable tie installation instructions: 1. Connect 2 cable ties together to form 1 long cable tie with two tie heads. 2. Wrap cable tie around trefoil bundle and rung by looping flat across bundle in front and then diagonally around rung in back. See adjacent figures Figure 441 Critical to Quality: 3. Tighten ties to 104lbs +/- 8lbs or 463N +/36N of tension. 4. Ensure that all slack is removed from ties before tightening and cutting off tails with installation gun. Figure 442 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 328/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 15.3.1.1 Arranging the Cables at the Transition between the Cable Saddle and the Tower Cable Tray “OLD” TPH Structure for 98.3mHH 1. Bundle the trefoils maintaining cable arrangement continuity coming off of the saddle i.e., one of each phase per trefoil. 2. Match the cable arrangement coming off of the saddle to the cable arrangement in the tower with minimal crossing of the cables. 3. When routing the cables over to the tower tray, allow for gradual bend radius of cables without exceeding the minimum bend radius allowed depending on the cable size. 4. Secure the cables to the cable trays on suitable position with cable ties forming the proper bend radius. 5. Using a cable tie cut tool ensure the cable zip‐tie tail is cut even with the buckle to avoid any sharp edges. This applies to all zip tie installation. NOTE Per the NEC (NFPA 70) 300.34: Conductors must not be bent to a radius of less than 8 times the outside diameter of the conductor (or cable) measured from the inside of the bend for non-shielded conductors. For shielded conductors the requirement is 12 times the outside diameter. This requirement is both for during and after installation. If the above requirement cannot be met, contact GE engineering before proceeding. For purposes of this document “exceeding” the minimum bend radius shall mean bending the conductor to a radius less than the NEC requirements as listed above. Figure 443: Example “OLD” TPH structure for 98.3 m HH The bend radius of the conductor shall be measured from the inside of the bend of the conductor. 6. On the tower cable tray identify the approximate location of the splice to ensure there are cable rungs available above the splice to apply cable ties to support the splice. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 329/428 GE Renewable Energy – Original – Installation Manual 15.3.1.2 Arranging the Cables at the Transition between the Cable Saddle and the Tower Cable Tray “NEW” BoM Structure for 110mHH 1. Bundle the trefoils maintaining cable arrangement continuity coming off of the saddle i.e., one of each phase per trefoil. 2. Match the cable spacing arrangement coming off of the saddle to the cable arrangement in the tower with minimal crossing of the cables. 3. Secure the cables to the cable trays with cable ties and neoprene/steel tie as required as per the latest engineering directive 4. Using the appropriate cable tie tool setting apply tension and cut the regular cable ties and the steel ties even with the buckle to avoid any sharp edges. This applies to all zip tie installation. NOTE Per the NEC (NFPA 70) 300.34: Conductors must not be bent to a radius of less than 8 times the outside diameter of the conductor (or cable) measured from the inside of the bend for non-shielded conductors. For shielded conductors the requirement is 12 times the outside diameter. This requirement is both for during and after installation. If the above requirement cannot be met, contact GE engineering before proceeding. For purposes of this document “exceeding” the minimum bend radius shall mean bending the conductor to a radius less than the NEC requirements as listed above. The bend radius of the conductor shall be measured from the inside of the bend of the conductor. 5. Figure 444: Example transitioning cables over to the cable tray“NEW” BoM Structure for 110 mHH On the tower cable tray identify the approximate location of the splice to ensure there are cable rungs available above the splice to apply cable ties to support the splice. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 330/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual DANGER Fall hazard! If an employee is working at a height that exposes them to a potential fall, an appropriate ladder and/or fall arrest equipment must be used as required, and 100 % tie-off at all times. A retractable lanyard can be utilized. Typical cable arrangement below the saddle deck. Communication and other power cables are routed and secured to the small horizontal cable tray in the field. Stator/Rotor cables are secured by the tower manufacturer. Figure 445: Cables below the yaw deck “NEW” BoM Structur 15.4 Installing the Cable for the Cable Untwisting Switch NOTE The switch is located in the machine head and will be installed in manufacturing. On site only final work on the switch is required! CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 331/428 GE Renewable Energy Installation Manual – Original – 15.5 Splicing the Stator, Generator and Ground Cables Only technicians qualified to perform work on Medium Voltage equipment should be performing electrical connections or testing. The stator, generator and ground cables 400 V and other PE cables are pre - installed in the machine head and in each tower section by manufacturers respectively. The field teams will verify that the cables are in good condition prior to lifting the tower. Once the tower is erected the installer will splice the cables at each tower level ensuring the correct phase rotation and markings of the cables are maintained through the tower. All splicing activities must comply with the following requirements: Crimp the connectors using a crimp tool setup approved by the manufacturer of the connector that meets applicable IEC/UL/CSA electrical codes and standards. The tool must have the ability to induce pump pressure and compression of the crimp head on a daily basis. Intermixing of products and tooling of several vendors is possible if the vendors have carried out respective testing and provided written approval. Deviation from this requirement can result in cancelation of UL certification. For 6 kV cables; follow manufacturer’s instructions provided with the 6 kV kit. Where applicable reference latest revision GEI _GE.all_Tower (System)_Power Cable Splice and Lug Installation_575V_690V. The electrical insulation for the splices must be applied in accordance with the vendor specific application procedures. WARNING Crushing hazard! Before using the crimping tool, read the operating manual and the safety information contained therein. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 332/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual General Overview of the Cable Arrangement at Each Level Prior to Installation 1. Prior to lifting the tower verify cables on each section are secured, undamaged and labeled accordingly. 2. If cables are not labeled it is recommended to label the cables for ease of identification during cable splicing once the tower is erected. 6 kV stators L1-L2-L3. Rotors K – L - M. 400 V Lights and Receptacles Hoist Contact GE site representative if any issues are found. 3. Figure 446: Example top of tower Verify that the cable ends on the top and the bottom of the tower section are long enough to make the splice once the tower is erected. Contact GE site representative if any issues are found. Figure 447: Example bottom of the tower Figure 448: Example cable tray below the saddle Figure 449: Example converter level CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 333/428 GE Renewable Energy Installation Manual – Original – Overview of the Final Cable Arrangement at Each Level A: Top section: Typical cables splice arrangement at transition between the cable saddle and the tower cable tray. Rotor 690V Rotor 6 kV 400 V PE & Comm bundle PE Neutral lights receptacles B: Tower Flanges: Typical cable splice arrangement at flanges. Rotor 690V Rotor 6 kV 400 V PE & Comm bundle PE Neutral lights receptacles C: Converter level: Typical cable arrangement at the converter level. A Comm bundle lights PE & Neutral 400 V 6 kV Rotor PE receptacles The 690 V rotor cables will transition into the converter rotor cabinet. A - 6 kV splice CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 334/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual D: Typical cable arrangement and tie configuration at the tower flange above splice. Cable ties can be secured over the cold shrink, but shall not be placed over the region that covers the mastic, and on the side of the mastic that is away from the splice. In order to avoid this situation, the cable tie can be secured on the vertical rail of the cable ladder if needed, and not on the horizontal rung. Figure 450 F: Typical cable arrangement and tie configuration a tower flanges below splice. Figure 451 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 335/428 GE Renewable Energy – Original – Installation Manual G: On the converter level 4. Secure the 6 kV cables between the SSC and the converter level splice to the cable tray with cable ties allowing for enough extra cable slack to make the connection and both ends. The cables ties on the 6 kV cables are applied after splicing to ensure cable ties are not placed over the insulation. On this section power and ground cables (400 and 690 V) are long enough to reach its final termination point. Figure 452 5. Splice the stator and rotor cables below the cable saddle according connector specific instructions. The following requirements must be complied with: Crimp the connectors using a crimp tool setup approved by the manufacturer of the connector that meets applicable IEC/UL/CSA electrical codes and standards The tool must have the ability to induce pump pressure and compression of the crimp head on a daily basis. Intermixing of products and tooling of several vendors is possible if the vendors have carried out respective testing and provided written approval. Deviation from this requirement can result in cancelation of UL certification. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 336/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual “NEW” BoM Structure for 110mHH (Cable transition splices below the saddle) Figure 453 Figure 454 “OLD” TPH structure for 98.3mHH (Cable transition splices below the saddle) Figure 455 Figure 456 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 337/428 GE Renewable Energy 6. Prepare and splice the 6 kV trefoil for the stator cables (L1, L2 & L3). 7. The 6 kV cables will be measured, cut and spliced in strict accordance with the manufacture splicing instructions. 8. Manufacturer methods must be followed and recommended tools and materials must be used. 9. Extreme care must be used to avoid any contamination e.g. debris or moisture of the splice. – Original – Installation Manual 10. Splice 1 PE (stator ground). Figure 457 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 338/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 11. The multiple layers of 6 kV electrical insulation are applied in strict accordance with the manufacture instructions. 12. Remove excess conductive paste to prevent arcing. Figure 458 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 339/428 GE Renewable Energy – Original – Installation Manual 13. Splice the 3 trefoils for the rotor cables with K - L - M in each and 1 rotor ground. 14. The Rotor cables will be measured, cut and spliced in strict accordance with the connectors’ manufacture splicing instructions. 15. Splice manufacturer methods must be followed and recommended tools and materials must be used. Figure 459 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 340/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 16. The rotor electrical insulation is applied in strict accordance with the manufacture instructions. 17. Remove excess conductive paste to prevent arcing. Figure 460 18. Splice the 1 trefoil 400 V (L1, L2 & L3). 1 PE 1 Neutral The cables will be measured, cut and spliced in strict accordance with the splice manufacture splicing instructions. Manufacturer methods must be followed and recommended tools and materials must be used. Figure 461 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 341/428 GE Renewable Energy – Original – Installation Manual 19. The electrical insulation is applied in strict accordance with the manufacture instructions. 20. Remove excess conductive paste to prevent arcing. Figure 462 21. Secure the trefoils to the cable trays with cable ties above and below the splices. 22. Repeat steps at all applicable tower levels. 23. Remove all trash and debris from the tower. Figure 463 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 342/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 24. Apply High temp protection tape to the cables in accordance with the latest GEI. Typical applied between the top of midsection and bottom of the top section splice Refer to the latest GEI for the application of fire protection tape. Figure 464 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 343/428 GE Renewable Energy Installation Manual – Original – 16 Signs and Labeling to be Attached to the Wind Turbine Generator System by the Operator/Owner In accordance with DIN EN 50308; (or equivalent for US and ASIA poles); the operator/owner of the Wind Turbine Generator Systems (WTGS) is obliged to attach additional warning signs to the WTGS. These are intended to cover safety aspects which are not related to the scope of supply of the manufacturer of the Wind Turbine Generator Systems. The warning signs must state that it is dangerous and prohibited for unauthorized persons to enter or climb the WTGS, it is prohibited to remain in the vicinity of the WTGS while work is being carried out outside the nacelle, deposits of ice which have formed on the rotor blades (depending on the location of the WTGS) could be thrown a considerable distance from the WTGS. 17 Installation of the Ladder and Fall Protection System Immediately after the installation of a ladder section, the correct installation of the ladder and fall protection equipment must be checked. ATTENTION The inspection of the ladder and fall protection equipment must be performed by a qualified person only! ATTENTION The inspection must be repeated after any repair! The subsequent inspection intervals must be adapted to the respective operational conditions. The intervals depend on the frequency of use, the load during use and the frequency and seriousness of the defects found in the preceding tests. Verification of regular inspection is essential for warranty claims. Follow the vendor's inspection protocol. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 344/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 18 Connections DANGER Danger of electrical shock! Uncontrolled stored energy: Make sure that all components are de-energized. DANGER Electrical hazard! Remove any water accumulation from the foundation prior to setting up foundation electrical connections. WARNING Pinch points! Use the hooking points marked in signal yellow which are located on each platform (section). WARNING Falling hazard! Personnel must be attached to a specified tie-off point at all times. WARNING Slip trip hazards! Ensure that you are always protected by your PPE when carrying out work on the PPM. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 345/428 GE Renewable Energy – Original – Installation Manual 18.1 Electrical Connections at PPM DANGER Electrical hazard! Refer to the latest revision Energization Process Flow Chart and Verify GE and Customer LOTO procedures are complementary. Follow site specific LOTO policy if LOTO needs to removed or re-applied. Ensure all pre- energization/de-energization checks per Site Specific LOTO are adhered to prior to beginning any work. Follow electrical PPE requirements in the Electrical Service Bulletin (Element HS 13. 2C) for any electrical work on the WTG (See the EHS Outage Plan or the Construction EHS Plan). CAUTION Awkward postures / Reach / Fall Hazard! The cable access points are located in limited space and difficult to reach areas. If an employee is working at a height that exposes them to a potential fall, an appropriate ladder and/or fall arrest equipment must be used as required, and 100 % tie-off at all times. A retractable lanyard can be utilized. 18.1.1 PAS00 Grounds: 1. Set up the connections of the ground bus bar as per the latest electrical wiring diagram. Where required cables will be routed through cable trays and secured with cables in a pattern on every rung. Where required cables must be protected from sharp edges/chaffing or other hazard that could potentially damage the cable in any way and cause an arc flash. Consult with GE site representative for torque data recording requirements and location. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 346/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 2. – Original – Installation Manual Remove all paint residues or dirt from the tower flange ground bosses to ensure perfect contact of the ground cables with the tower sections. Figure 465: Removing paint residues from the tower flange 3. Route the four 4 ground wires between the tower flanges and PAS00 ground bus bar laying the cables on the floor unobstructed. 4. Mount the ground straps to the tower flange with hardware ensuring the correct washer is utilized. Torque the bolts and mark them with a paint pen. 5. Write the torque data on a visible location for IIP inspection. A A - PAS00 bus bar Figure 466: Connecting the ground cables CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 347/428 GE Renewable Energy 6. Bolt the ground straps to PAS00 ground bus bar. 7. Torque the bolts and mark them with a paint pen. Write the torque data on a visible location for IIP inspection. Installation Manual – Original – A A - PAS00 bus bar Figure 467 Foundation ground leads: 8. Position foundation ground lead(s) against the PAS00 ground bus bar. 9. Position the lug against the cable and the bus bar hole to mark the cable. 10. Cut the ground leads ensuring there is sufficient cable to insert into the lug barrel. 11. Attach the lug to ground lead and crimp the lug according the lug manufacturer’s instructions. 12. Mount the ground straps to PAS00 ground bus bar with hardware ensuring hardware is oriented correctly. Torque the bolts and mark them with a paint pen. Write the torque data on a visible location for IIP inspection. Figure 468 13. Repeat steps for all remaining cables. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 348/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual Flange Grounds: 14. Mount the ground straps between the tower flanges with the correct hardware. 15. Torque the bolts and mark them with a paint pen. Write the torque data on a visible location for IIP inspection. Figure 469 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 349/428 GE Renewable Energy Installation Manual – Original – Ground cable potential PAS00 to the PE bus bar PAS01 of the controller level. 16. Cables are terminated from 1 end by WTG manufacturer. The Installer will uncoil and route the ground cable through the cable tray to PAS01 bus bar located between the transformer and controller level. A 17. Red dotted line shows approximate routing location. 18. Terminate the pre-lugged cable to the PAS01 ground bus bar with hardware ensuring hardware is oriented correctly. Torque the bolts and mark them with a paint pen. Write the torque data on a visible location for IIP inspection. A - PAS01 bus bar Figure 470 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 350/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – 19. Connect the ground cable potential PAS01 between the PE bus bar PAS01 of the controller level to the transformer level leg. Installation Manual A 20. Torque the bolts and mark them with a paint pen. Write the torque data on a visible location for IIP inspection. A - PAS01 bus bar Figure 471 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 351/428 GE Renewable Energy Installation Manual – Original – 21. Route the ground cable potential between the AUX 690 V PE the PE bus bar PAS02 of the converter level. A 22. Secure the cable to cable tray with the AUX 690 V L1-L2-L2 cables with cable ties. 23. Torque the bolts and mark them with a paint pen. Write the torque data on a visible location for IIP inspection. 24. Route the ground cable between the tower to the PE bus bar PAS02 of the converter level. A - PAS02 bus bar Figure 472 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 352/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 18.2 Electrical Connections and Testing Requirements DANGER Life-threatening hazard! Danger! Electricity! Before performing any work on or in electrical equipment within the WTG you must be trained on the safety and operation of that specific model and manufacturer of equipment. Personnel performing this work are required to request training for operating, assembling of the SSC cabinet 30 days before performing this work. Only technicians qualified to perform work on Medium Voltage equipment should be performing electrical connections or testing. Field Tests Before performing any work on or in electrical equipment within the WTG you must be trained (by manufacturer or manufacturer trained representative) on the safety and operation of that specific model and manufacturer of equipment. Field testing of installed MVSG and SSC cabinets to be completed by an electrical contractor qualified to perform work per manufacturer manual. This test is required to check internal parts were not damaged during transportation and handling. Contact GE for equipment manuals. This work must be conducted by an electrical contractor or technician who is trained and certified by the regionally required Testing or Regulatory agency (i.e. NETA in the USA) for the equipment and voltage level being worked on and the testing being performed. Consult the Authority Having Jurisdiction (AHJ) for specific requirements. The cable assembly between the switch gear and the transformer supplied by GE will be VLF tested by the installer. Contact GE for acceptable test voltage. Electrical contractors must complete insulation integrity testing IR/Hipot/VLF test where applicable per the latest revision of 104W2311: Transformer winding to converter 690 V cables Converter to generator 690 V cables Converter to auxiliary transformer 6 kV configuration: cable connection from transformer to synchronization switch and synchronization switch to generator 400 tower cables 400 V auxiliary transformer to LVDP 34.5 kV cables from MVSG to transformer CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 353/428 GE Renewable Energy Installation Manual – Original – ATTENTION For all cable runs, the cables must be disconnected from the equipment on both ends. NOTE Verify electrical validation tests for installed MV cable assembly between switchgear and high side transformer is complete according to 104W2311. ATTENTION Some country electrical codes or regulations may require additional testing for the generator stator and rotor ground/PE cables. All crimping activities must comply with the following requirements: Crimp the connectors using a crimp tool setup approved by the manufacturer of the connector that meets applicable IEC/UL/CSA electrical codes and standards. The tool must have the ability to induce pump pressure and compression of the crimp head on a daily basis. Intermixing of products and tooling of several vendors is possible if the vendors have carried out respective testing and provided written approval. Deviation from this requirement can result in cancelation of UL certification. For 6 kV cables; follow manufacturer’s instructions provided with the 6kv splice kit. Reference document: GE.all_Tower (System)_Power Cable - Splice and Lug Installation Procedure inside Tower and/or specific vendor crimping instructions where applicable. T-Body Connectors: Refer to the T-Body manufacturer`s instructions. Contact GE for equipment manuals. The electrical insulation for the splices must be applied in accordance with the vendor specific application procedures. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 354/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 1. – Original – Installation Manual Verify the protection settings in the switch gear are per the specific wiring diagram. ATTENTION Danger of equipment damage! Protect cables from sharp edges when inserting cables into the MVSG cabinet. Closely inspect cables after installation to ensure there is no damage. Figure 473: Connection of MVSG/transformer (examples) CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 355/428 GE Renewable Energy – Original – Installation Manual 18.3 Medium Voltage Cables between the Grid and MVSG (Grid and Next Turbine) DANGER Life-threatening hazard! Danger! Electricity! Before performing any work on or in electrical equipment within the WTG you must be trained on the safety and operation of that specific model and manufacturer of equipment. Personnel performing this work are required to request training for operating, assembling of the SSC cabinet 30 days before performing this work. Only technicians qualified to perform work on Medium Voltage equipment should be performing electrical connections or testing. Refer to Technical_Description_3MW-DFIG-xxHz_MVCableInst Requirements for the Medium Voltage Cable to Switchgear Interface. 1. If the cables are routed into foundation prior to installing the PPM, ensure these cables are undamaged secured from possible damage during installation of the PPM and the base section. Figure 474 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 356/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual Overview of typical MVSG DANGER Life-threatening hazard! Danger! Electricity! Before performing any work on or in electrical equipment within the WTG you must be trained on the safety and operation of that specific model and manufacturer of equipment. Personnel performing this work are required to request training for operating, assembling of the SSC cabinet 30 days before performing this work. Only technicians qualified to perform work on Medium Voltage equipment should be performing electrical connections or testing. DANGER Life-threatening hazard! Danger! Electricity! Before performing any work on or in electrical equipment within the WTG you must be trained on the safety and operation of that specific model and manufacturer of equipment. Personnel performing this work are required to request training for operating, assembling of the SSC cabinet 30 days before performing this work. Only technicians qualified to perform work on Medium Voltage equipment should be performing electrical connections or testing. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 357/428 GE Renewable Energy Installation Manual – Original – MVSG Panels are removed by pulling the cover up and then away from the cabinet. Grid Next Turbine WTG transformer CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 358/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – 2. After the base section is installed carefully route and protect the cables between the foundation and MVSG GRID and if applicable route the Grid cables for the Next WTG. 3. Secure the cables to the transformer cable ladder. Refer to: Technical_Description_3MW-DFIGxxHz_MVCableInst Requirements for the Medium Voltage Cable to Switchgear Interface. 4. Verify correct phasing between grid and MVSG and mark the cables with phase tape. 5. Terminate the cables in MVSG grid and/or next turbine respectively. Refer to: Technical_Description_3MW-DFIGxxHz_MVCableInst Requirements for the Medium Voltage Cable to Switchgear Interface. Installation Manual Figure 475 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 359/428 GE Renewable Energy Installation Manual – Original – 18.4 Connection of the HV Cables between MVSG and the Transformer DANGER Life-threatening hazard! Danger! Electricity! Before performing any work on or in electrical equipment within the WTG you must be trained on the safety and operation of that specific model and manufacturer of equipment. Personnel performing this work are required to request training for operating, assembling of the SSC cabinet 30 days before performing this work. Only technicians qualified to perform work on Medium Voltage equipment should be performing electrical connections or testing. Use these instructions in conjunction with the Transformer (vendor specific) Operation & Maintenance Manual and Insulation Integrity testing 104W2311: 1. Carefully route the cable between the transformer and the MVSG as detailed in provided assembly drawings. A: Cables are routed from the transformer level up to the controller level through the cable openings located on the floor of the MVSG. B: Cables are secured with cable ties to the cable tray located on the transformer level. C: The other end of the cables are routed to the transformer terminals maintaining the respective phase rotation sequence. A 2 ATTENTION Connections in installer's scope! These connections may only be carried out by a certified party. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 360/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – C B 3 1 Figure 476 1 - Transformer terminals 2 - MVSG 3 - Cable tray located in the transformer level 2. Remove the (MVSG to Transformer) panels. Pull the cover up and then away from the cabinet. Figure 477 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 361/428 GE Renewable Energy 3. – Original – Installation Manual Inspect the inside of the MVSG ensuring the cable support brackets are present and the bushings are undamaged. Any issues found must be reported to GE site representative. Figure 478 4. Inside bottom of MVSG: Remove cable access floor panel. Figure 479 5. Inspect the HV cable for damage to the insulation or connectors. 6. Carefully push the cables up into the MVSG maintaining the correct phase sequence. 7. Verify correct phasing between transformer and MVSG and mark the cables with phase tape. Figure 480 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 362/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – 8. Verify that the minimum bend radius as recommended by cable manufactures is not exceeded. 9. Secure the cables to the cable ladder with cable ties providing the maximum strain relief possible to the cable and terminals. 10. The cable must be additionally protected against mechanical damage with a cable protection tube or cover depending on the used cable type and size. Figure 481 11. In the transformer; Route the three cables to the respective terminals ensuring no mechanical strain to the cable/terminals. A 12. Inspect the transformer contact terminals for any damage. 13. Test 34.5 kV cables according to 104W2311. 14. Test the MVSG according to manufacturer’s testing protocol. 15. Terminate the 34.5 kV cables to the transformer ensuring the cable contact leads and terminals are prepared as required in accordance with the transformer Operation & Maintenance Manual. 16. Install the connection bar at the same time of installing 34.5 kV high voltage cable. 17. Using a torque wrench, ensure all bolted connections are tightened to the values given in the transformer Operation & Maintenance Manual. Torque 34.5 kV terminals Torque adjustment tap hardware 18. Mark the hardware with a paint pen. 19. Record the torque values in and area as agreed to with the IIP inspectors for the final inspection. Figure 482: 34,5 kV connections A - 34.5 kV terminals CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 363/428 GE Renewable Energy Installation Manual – Original – Figure 483: Connection bar 20. Cover the terminals with silicon fabric as directed by the transformer Operation & Maintenance Manual. Figure 484 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 364/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 21. Route and terminate the 34.5 kV concentric grounds to MVSG ground bar. 22. Torque the hardware and mark with a paint pen. Figure 485 Critical to Quality: 23. The installer is required to read, understand and follow the required TBody connector’s installation procedures prior to commencing the work. Critical to Quality: 24. Only trained experienced personnel may perform this work. 25. In the MVSG cabinet, prepare cables as per the T-body and cable manufacturer’s instructions. 26. Do not cut or nick the insulation. Figure 486 27. In the MVSG cabinet, prepare bushings as per the T-body manufacturer’s instructions. Figure 487 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 365/428 GE Renewable Energy – Original – Installation Manual 28. In the MVSG cabinet, install the T-Body and tighten to bushing in accordance with the T-Body manufacturer’s instructions. 29. Terminate the concentric neutrals to the bus bar. 30. Torque the hardware and mark with a paint pen. NOTE If MV cable shield is not passing through CT (current transformer) - usually, when CT is attached on MVSG bushing- refer to Figure 488 for routing details. If MV cable shield does pass through CT it must be returned through CT, in order to cancel out shield currents sensed by CT (see Figure 489). Figure 488: Example 1 Figure 489: Example 2 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 366/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 31. Ensure the rubber seals are installed correctly and or apply foam to seal cable entry point. 32. Any unused holes must be sealed. 33. Remove all tools and debris from inside of the cabinet. 34. Reinstall the door panels. NOTE Do not leave cabinet panels open. Cabinet panels must be closed at the end of the shift or as soon as the work is complete. Figure 490 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 367/428 GE Renewable Energy Installation Manual – Original – 18.5 690 V Transformer to Converter CAE Cabinet 1. Inspect the 690 V cable for any damage to the insulation. 2. Carefully route the cable between the transformer and the converter as detailed in provided assembly drawings. A: cables are pushed up from the transformer level. B: through the controller level floor opening C: up the cable tray located between the MCC and the SSC cabinets. D: Into the converter CAE cabinet through cable glands. 1 D 1 - Bottom of CAE cabinet 2 - Controller level 3 - Transformer level C 2 B A 3 3. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 368/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – 4. Secure the cable to the cable tray with cable ties in sets of two. This tray is located in controller level between the SSC and the MCC cabinets. 5. The illustration shows 1 set of two cables on the MCC side of the tray and the other two sets on the SSC side of the cable tray. NOTE MCC Where applicable, cables must be protected from sharp edges/chaffing or other hazard that could potentially damage the cable in any form and cause an arc flash. SSC Figure 491 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 369/428 GE Renewable Energy – Original – 6. Verify correct phasing between transformer and converter and mark the cables with phase tape. 7. In the converter level: Push the cables through the cable glands maintaining the correct phase designation. Installation Manual Figure 492 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 370/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – 8. In the converter level CAE cabinet: Position cable against the busbar, Position the lug against the cable and center the lug/bus bar holes to mark the cable. 9. Move the cable outside of the cabinet and cut the cable ensuring there is sufficient cable to insert into the lug barrel. Installation Manual Figure 493 10. Attach the lug to the cables and crimp the lug according the lug manufacturer’s instructions. Figure 494 11. Perform testing of the cables in accordance with the Insulation Integrity Testing procedure 104W2311. 12. Terminate the cable(s) to the bus bar ensuring hardware is oriented correctly. Torque the bolts and mark them with a paint pen. Write the torque data on cabinet door. 13. Verify the cable glands are tight. Repeat steps for all remaining cables. 14. Remove all tooling and debris form the cabinet. Figure 495 15. Close the Cabinets doors. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 371/428 GE Renewable Energy – Original – Installation Manual 18.6 6kV Cables between the Transformer and SSC Cabinet DANGER Life-threatening hazard! Danger! Electricity! Before performing any work on or in electrical equipment within the WTG you must be trained on the safety and operation of that specific model and manufacturer of equipment. Personnel performing this work are required to request training for operating, assembling of the SSC cabinet 30 days before performing this work. Only technicians qualified to perform work on Medium Voltage equipment should be performing electrical connections or testing. DANGER Electrical hazard! Refer to the latest revision Energization Process Flow Chart and Verify GE and Customer LOTO procedures are complementary. Follow site specific LOTO policy if LOTO needs to removed or re-applied. Ensure all pre- energization/de-energization checks per Site Specific LOTO are adhered to prior to beginning any work. Follow electrical PPE requirements in the Electrical Service Bulletin (Element HS 13. 2C) for any electrical work on the WTG (See the EHS Outage Plan or the Construction EHS Plan). CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 372/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 18.6.1 6kV Cables between the Transformer and SSC Cabinet Schneider Configuration DANGER Danger of personal injury and damage to the equipment! Failure to isolate the WTG from the Grid and any other energy sources i.e., (UPS, capacitors etc.) can result in unintended exposure to energization. Confirm the Wind Turbine is de-energized in accordance with the Site Specific LOTO. Installation, operation, and service are performed only by experienced personnel trained in this specific configuration of equipment. CAUTION Awkward postures / Reach / Fall Hazard! The SSC cable access points are located in limited space and difficult to reach areas below and above the cabinet. If an employee is working at a height that exposes them to a potential fall, an appropriate ladder and/or fall arrest equipment must be used as required, and 100 % tie-off at all times. A retractable lanyard can be utilized. DANGER Hand crush, cuts and burns risk! Hands are exposed to mechanical dangers (cutting, grazing, pinching, and crushing), and to danger from heat and cold (from touching hot objects and convected heat). In these cases protective gloves must be worn. Use caution when working around exposed rotating components while the rotor is turning. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 373/428 GE Renewable Energy 1. Use caution not to damage components when working in or around the back of the SSC cabinet. 2. Remove back panel of the SSC cabinet. 100% tie off is required. 3. A: Route 3 6 kV cables between the transformer and the SSC cabinet. 4. B: Secure the cables to the lower support DIN rail with cable ties. 5. C: Secure cables to the upper DIN rail with cable clamps. 6. D: Perform testing in accordance with 104W2311. 7. E: Maintaining the proper phasing push cables through the hole openings into the SSC cabinet. 8. F: Maintaining the correct phasing terminate the cables on the transformer side L1 – L2 – L3. 9. G: Maintaining the correct phasing terminate cables on the SSC side L1 – L2 – L3. 10. H: Torque the hardware on both transformer and SSC ends and mark with a paint pen. Installation Manual – Original – G E SSC C A B F CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 374/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 11. In the transformer, route the concentric neutrals from each cable and terminate to the designated grounding point. 12. Torque the hardware and mark with a paint pen. Figure 496 13. In the SSC, route the concentric neutrals from each cable and terminate to the designated grounding point. 14. Torque the hardware and mark with a paint pen. Figure 497 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 375/428 GE Renewable Energy Installation Manual – Original – 15. Remove the insulator caps and place outside of the cabinet to allow for connection final inspection. Insulator boots must be reinstalled after IIP is complete. Figure 498 16. Once the IIP is complete cut a hole the size of the cable/ heat shrink diameter. 17. Install the boot covering each one of the termination points. Figure 499 18. Inspect inside the cabinet, on top and around connectors in SSC and transformer. 19. Remove any debris that can potentially cause an arc flash event in SSC and transformer. 20. This may require the removal of panels and use of mirror and flash light as required. 21. Verify no loose or misplaced tooling is left attached to the bus bars in SSC and Transformer. 22. Look for misplaced hardware, such as nuts, washers, and bolts that may have fallen near or around the SSC and transformer. 23. Using a mirror and a flashlight, verify manufacturer materials such as loose manuals or loose cables are not left in SSC and Transformer. 24. Inspect for debris or damaged cables in SSC and transformer. 25. Close all cabinet doors at the end of shift and/or after completion of work. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 376/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 18.6.2 6kV Cables between the Transformer and SSC Cabinet LimitAmp Configuration DANGER Life-threatening hazard! Danger! Electricity! Before performing any work on or in electrical equipment within the WTG you must be trained on the safety and operation of that specific model and manufacturer of equipment. Personnel performing this work are required to request training for operating, assembling of the SSC cabinet 30 days before performing this work. Only technicians qualified to perform work on Medium Voltage equipment should be performing electrical connections or testing. DANGER Electrical hazard! Refer to the latest revision Energization Process Flow Chart and Verify GE and Customer LOTO procedures are complementary. Follow site specific LOTO policy if LOTO needs to removed or re-applied. Ensure all pre- energization/de-energization checks per Site Specific LOTO are adhered to prior to beginning any work. Follow electrical PPE requirements in the Electrical Service Bulletin (Element HS 13. 2C) for any electrical work on the WTG (See the EHS Outage Plan or the Construction EHS Plan). DANGER Danger of personal injury and damage to the equipment! Failure to isolate the WTG from the Grid and any other energy sources i.e., (UPS, capacitors etc.) can result in unintended exposure to energization. Confirm the Wind Turbine is de-energized in accordance with the Site Specific LOTO. Installation, operation, and service are performed only by experienced personnel trained in this specific configuration of equipment. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 377/428 GE Renewable Energy – Original – Installation Manual CAUTION Awkward postures / Reach / Fall Hazard! The cable access points are located in limited space and difficult to reach areas. If an employee is working at a height that exposes them to a potential fall, an appropriate ladder and/or fall arrest equipment must be used as required, and 100 % tie-off at all times. A retractable lanyard can be utilized. DANGER Hand crush, cuts and burns risk! Hands are exposed to mechanical dangers (cutting, grazing, pinching, and crushing), and to danger from heat and cold (from touching hot objects and convected heat). In these cases protective gloves must be worn. Use caution when working around exposed rotating components while the rotor is turning. Opening De Energized SSC cabinet during installation DANGER Life-threatening hazard! Danger! Electricity! Before performing any work on or in electrical equipment within the WTG you must be trained on the safety and operation of that specific model and manufacturer of equipment. Personnel performing this work are required to request training for operating, assembling of the SSC cabinet 30 days before performing this work. Only technicians qualified to perform work on Medium Voltage equipment should be performing electrical connections or testing. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 378/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – Critical to Quality and Safety: Reference the latest GEI for opening the SSC LimitAmp cabinet doors. Upper compartment = Low Voltage compartment Lower compartment = High Voltage compartment Figure 500: Upper and Lower compartment 1. Remove the two isolation barriers. Figure 501: Isolation Barriers CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 379/428 GE Renewable Energy 2. – Original – Installation Manual Loosen the black cable clamps that secure cables going into the top cabinet compartment. A Figure 502: View from outside of the cabinet (exterior left hand side cover removed Figure 503: Interior divider cover (Transformer cable routing) A - Wind Ground Cable Clamp 3. Verify 3 sets of cable clamps and saddles are present. Figure 504: Cable clamps CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 380/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual On the Transformer Level: DANGER Life-threatening hazard! Danger! Electricity! Before performing any work on or in electrical equipment within the WTG you must be trained on the safety and operation of that specific model and manufacturer of equipment. Personnel performing this work are required to request training for operating, assembling of the SSC cabinet 30 days before performing this work. Figure 505: 6 kV cables coiled on top of transformer Only technicians qualified to perform work on Medium Voltage equipment should be performing electrical connections or testing. The three 6kV cables are shipped terminated and coiled on top of the transformer as shown on the illustration. 4. Inspect for damage and that the cables are labeled correctly. These cables will need to be terminated if they are shipped loose. CAUTION Awkward postures / Reach / Fall Hazard! The PPM cable access points are located in limited space and difficult to reach areas. If an employee is working at a height that exposes them to a potential fall, an appropriate ladder and/or fall arrest equipment must be used as required, and 100 % tie-off at all times. A retractable lanyard can be utilized. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 381/428 GE Renewable Energy Installation Manual – Original – 5. A: Route 3 6 kV cables between the transformer and the SSC cabinet. 6. B: Secure the cables to the lower support DIN rail with cable ties. SSC A B B Figure 506: Cables secured to DIN rail CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 382/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 7. Installation Manual – Original – C: Secure the cables to the upper DIN rail with cable clamps. C C Figure 507: Cables secured below the SSC cabinet CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 383/428 GE Renewable Energy – Original – 8. Push the cables up through the hole openings into the SSC cabinet maintaining the proper phasing sequence. 9. Align the cable lugs to the bus bar. Ensure there is enough length to terminate without putting strain on the cable or exceeding the minimum bend radius. Installation Manual 10. Ensure lugs are oriented correctly in relation the bus bar and tighten the pinch block and cable glands. 11. Perform testing in accordance with 104W2311. ATTENTION For all cable runs requiring testing, the cables must be disconnected from the equipment on both ends for testing purposes. Figure 508: Pinchblocks Figure 509: Routing the cables through the SSC cabinet (Note: Picture shown without internal equipment for illustration purposes) CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 384/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 12. Maintaining the correct phasing terminate cables on the SSC side L1 – L2 – L3 bus bar. 13. Torque the hardware on both transformer and SSC ends and mark with a paint pen. Reference the 3MW Bolt Torque Specification. Figure 510: SSC side L1 – L2 – L3 Bus bars Critical to Quality: 14. Apply Electrical Insulation Linerless Rubber Splicing Tape 130C in accordance with Appendix – A Taping the Upper Connection. ATTENTION CRITICAL TO QUALITY: Failure to apply the tape as prescribed can lead to catastrophic damage to equipment. Figure 511: Electrical Insulation Linerless Rubber Splicing Tape CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 385/428 GE Renewable Energy – Original – Installation Manual 15. Terminate the concentric neutrals to the nearest equipment grounding bus bar shown on the illustration. Reference the 3MW Bolt Torque Specification. Figure 512: Concentric neutral Cable Termination Point 16. Terminate the Ground to the equipment grounding bus bar shown on the illustration. Reference the 3MW Bolt Torque Specification. Figure 513: Wind Ground Cable Termination Point CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 386/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 17. If applicable: Maintaining the correct phasing terminate the cables on the transformer side L1 – L2 – L3. Reference the 3MW Bolt Torque Specification. Figure 514: Transformer side L1 – L2 – L3 Figure 515: Transformer side L1 – L2 – L3 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 387/428 GE Renewable Energy Installation Manual – Original – 18. If applicable: In the transformer, route the concentric neutrals from each cable and terminate to the designated grounding point. 19. Torque the hardware and mark with a paint pen. Reference the 3MW Bolt Torque Specification. Figure 516: Concentric neutrals terminated to transformer side 20. Terminate SSC Ground to the PE bus bar PAS01 of the controller level. The bus bar is located near the transformer access hatch. Reference the 3MW Bolt Torque Specification. Figure 517: PE Bus Bar PAS01 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 388/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – 18.7 690 V Converter CAE Cabinet to AUX Transformer 1. Inspect the 690 V converter to AUX transformer cables for damage to the insulation. 2. Carefully route the cable between the AUX transformer and the converter CAE cabinet as detailed in provided assembly drawings. A: Cables are routed from the AUX termination points to the cable tray on the bottom of the Aux and right hand side of the Aux transformer. B: Cables are secured with cable ties to the cable tray located on the right hand side of the AUX transformer. C: Cables transfer to the horizontal cable tray located on the top right hand side of the transformer (cable tray is part of the bottom of the controller level). D: Route the cables to the cable tray located on the controller level on the back left hand side of the LVDP. E: Route the cables on the cable tray located on top of LVDP and the SSC cabinets. F: Route cables into the converter CAE cabinet through cable glands. 1 F E LVDP D C B 1 - Bottom of CAE cabinet 2 - Auxiliary transformer 2 A Figure 518 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 389/428 GE Renewable Energy 3. 4. Installation Manual – Original – Verify the power cables between converter CAE cabinet and AUX transformer are phased correctly and phasing is maintained when pushing the cables into the CAE cabinet. A Test 600 V cables between converter CAE cabinet and AUX transformer according to 104W2311. A - Inside of CAE Cabinet at converter level B - Bottom of CAE cabinet View from top of MCC cabinet 1 2 3 1 2 3 B Figure 519: 1, 2, 3 front to back of the cabinet CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 390/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – 5. Set up the connections (690 V) between the converter cabinet and AUX transformer as per the labeling. 6. Write phasing and testing date, company name and initials inside the door of the cabinet. 7. Verify the cables are correctly lugged as per lug manufacturer's instructions. 8. Verify the power cables from AUX transformer to converter are terminated, torqued and marked with a paint pen. 9. Write torque value on the inside of the door. 10. Record the torque values in the torque report. Installation Manual Figure 520 11. Perform a wire pull test to ensure the cable connectors are not loose. 12. Inspect inside the cabinet, on top and around connectors in the converter remove any tools/debris that can potentially cause an arc. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 391/428 GE Renewable Energy Installation Manual – Original – 18.8 400 V LVDP to AUX Transformer 1. Inspect the (400 V AUX transformer to LVDP) cables for damage to the insulation. 2. Carefully route the cable between the LVDP cabinet and the AUX transformer as detailed in provided assembly drawings. A: Cables are coiled secured with cable ties to the cable tray located on the right hand side of the AUX transformer below the LVDP. B: Cables are routed to the cable tray located on the right hand side of the AUX transformer. C: Alow for a gradual drip loop between the cable clamps located directly below the termination point of each cable and cable tray. D: Route cables to termination points in AUX transformer. 1 LVDP A 1 - LVDP cabinet factory terminated side 2 - AUX transformer termination point B 2 D C Figure 521 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 392/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – 3. Verify the power cables between AUX transfomer and LVDP are phased correctly. 4. Test 400 V cables according to 104W2311. 5. Set up the connections (400 V) between AUX transformer and LVDP as per the labeling. 6. Write phasing and testing date, company name and initials inside the door of the LVDP cabinet. 7. Verify the cables are correctly lugged as per lug manufacturer's instructions. 8. Verify the power cables from auxiliary transformer to LVDP are terminated, torqued and marked with a paint pen. 9. Write torque value as agreed to with the IIP inspector for reference during IIP inspection. Installation Manual A 10. Record the torque values in the torque report. 11. Perform a wire pull test to ensure the cable connectors are not loose. Figure 522 A - AUX transformer 400 V termination points. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 393/428 GE Renewable Energy Installation Manual – Original – 12. Route the ground cable between LVDP and AUX transformer. 13. Terminate the cable in the ground bus bar 14. Route the gray cable W1926.06 208V Supply between LVDP and AUX transformer. Th an ks ag ai n 15. Terminate the cables in the auxiliary cabinet per the latest point to point drawing. Figure 523 16. Inspect inside the cabinet, on top and around connectors in the LVDP and auxiliary transformer. 17. Remove any debris that can potentially cause an arc. 18. This may require the removal of panels and use of mirror and flash light as required. 19. Verify no loose or misplaced tooling is left attached to the bus bar. 20. Look for misplaced hardware, such as nuts, washers, and bolts that may have fallen near or around the LVDP and auxiliary transformer bus bar. 21. Using a mirror and a flashlight, verify manufacturer materials such as loose manuals or loose cables are not left in LVDP and auxiliary transformer bus bar. 22. Inspect for debris or damaged cables. 23. Close all cabinet doors at the end of shift and/or after completion of work. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 394/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy Installation Manual – Original – 18.9 Control/Communication between MCC/SSC and the Converter CCC Cabinet Cables/conduits are routed from the MCC and SSC through a series of cable trays and secure with cable ties. 1. Verify the cables are not rubbing against any hardware or sharp edges. 2. A: In the controller level identify the conduits designated for CCC cabinet level. Reference the point to point drawing. 5. 7. 3. G: Maintaining the correct hole designation, push cables up into the CCC cabinet. Tighten the cable glands as required. 4. F: Lay and secure cables over the tray located above the MVSG. B: Start below MCC and SCC onto cable tray below. 6. E: Route and secure to vertical cable tray. C: Below LVDP cabinet, push the cables trough cable tray located between the controller and transformer level. 8. D: Pull cables out and up the cable tray located on the right hand side of the MVSG cabinet. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 395/428 GE Renewable Energy 9. – Original – Installation Manual In the converter level open the CCC cabinet. 10. Route the cables to the respective terminal block. 11. Verify the cables are ferruled. Figure 524 12. Terminate the wires according to the latest point to point drawing. Figure 525 Figure 526 13. Perform a pull test to ensure the connection is not loose. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 396/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 14. On the top of the converter cabinet: route the cables for the 2 converter fans through the holes located on top of the CCC cabinet. Figure 527 15. Inside the CCC cabinet route the cables through cable tray. 16. Verify the cables are ferruled. 17. Terminate the wires according to the latest point to point drawing. Figure 528 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 397/428 GE Renewable Energy – Original – Installation Manual 18. Route and secure the Ethernet cable. 19. Terminate to designated port according to the latest point to point drawing. 20. Perform a pull test on all cables to ensure the connection is not loose. 21. Vacuum and/or remove any debris, e.g. wire strands, metallic shavings, tools, unaccounted for hardware and animal/rodent debris. 22. Close all cabinet doors. Figure 529 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 398/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 18.10 Control/Communication AUX Cables between MCC/SSC and the Transformer Junction Box. TransformerLevel Cables terminated to MCC and SCC cabinet side and cables are shipped coiled on the controller level. 1. 2. A: From the MCC and SCC push the cables trough cable tray located between the controller and transformer level. A B: Route and secure the cables down the cable tray. Notice cables are on the inside of the tray and excess cable coiled. B Figure 530 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 399/428 GE Renewable Energy 3. Installation Manual – Original – C: From the bottom of the cable tray route the cable over and into the AUX transformer junction box maintaining correct cable hole designation for each cable. C Figure 531 4. In the controller level identify the conduits containing the cables that will be routed from the MCC/SSC to the junction box located in the transformer level. Reference the point to point drawing. Figure 532 5. Move the cables to the back of the MCC/SSC. Figure 533 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 400/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 6. – Original – Installation Manual Route the cables through the cable tray located between the controller cabinet and the transformer level. Figure 534 7. Once all the cables are pulled to the other side of the transformer, route the cables to the vertical cable ladder securing the conduits on the inside of the cable ladder with cable ties. Figure 535 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 401/428 GE Renewable Energy 8. – Original – Installation Manual Open the junction box and route the cables to the respective terminal block. Ensure the conduits are secure off of the ground. Figure 536 9. Terminate the wires according to the latest point to point drawing. Figure 537 10. Vacuum and/or remove any debris, e.g. wire strands, metallic shavings, tools, unaccounted for hardware and animal/rodent debris. 11. Reinstall J-Box cover. Figure 538 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 402/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 18.10.1 PT – 100 Cable and Tower Door Exhaust Fan 1. Route the PT-100 cable between the MCC and the Junction box located in the top of the auxiliary transformer. 2. Terminate the wires according to the latest point to point drawing. 3. Pull test the wires to ensure cables are terminated correctly. Figure 539 4. Route the cable between the MCC and the exhaust fan motor terminal box. 5. Terminate the wires according to the latest point to point drawing. 6. Pull test the wires to ensure cables are terminated correctly. Figure 540 7. Refer to the latest point to point drawing and consult with GE site representative for other cables not covered under these procedures. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 403/428 GE Renewable Energy Installation Manual – Original – 18.11 Connect the 400 V Auxiliary Cables (Top Box) to LVDP The 400 V cables are installed in each tower section by tower manufacturers. The field teams will splice cables at each tower level. The following steps cover transition between the base section cable tray into the LVDP cabinet. 1. A: 400 V Transition from the tower cable tray to the DIN rail allowing for enough slack to form a 170 mm drip loop. 2. B: Secure the cables to the DIN Rail with cable clamps. B A Figure 541 3. Verify the power cables (400 V) between the converter and the Top Box are phased correctly. 4. Write phasing date inside the door of cabinet. 5. C: Route the cables through the cable tray and secure with cable ties. C C A Figure 542 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 404/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 6. Installation Manual – Original – D: Maintaining the correct phase rotation, push cables up into the LVDP cabinet through the cable glands. D Figure 543 7. Measure the cables against the termination point. 8. Pull the cables outside the cabinet and cut them to the appropriate length. Figure 544 9. Strip and remove the insulation and take care not to damage conductors. 10. Apply a ferrule to each one of the cables according to vendor instructions. 11. Complete test per 104W2311. 12. Mark the cable ends with electrical tape or other means in accordance with the applicable electrical code. Figure 545 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 405/428 GE Renewable Energy Installation Manual – Original – 13. Terminate the converter to auxiliary transformer power cables, torque and mark them with a paint pen. 14. Write torque value, company name, date and initials on the back of the cabinet. 15. Record the torque values in the torque report. 16. Pull test all cables by hand to ensure conductors and hardware are not loose. 17. Ensure cable glands are tight. 18. Inspect inside the cabinet, on top and around connectors in the converter. 19. Vacuum and/or remove any debris, e.g. wire strands, metallic shavings, tools, unaccounted for hardware and animal/rodent debris. Remove any debris that can potentially cause an arc. Figure 546 18.12 Connect the Power Cables (690 V) from the Generator to Converter Cabinet The 690 V cables are installed in each tower section by tower manufacturers. The field teams will splice cables at each tower level. The following steps cover transition between the base section cable tray into the rotor cabinet in the converter level. The following requirements must be complied with: Crimp the connectors using a crimp tool setup approved by the manufacturer of the connector that meets applicable IEC/UL/CSA electrical codes and standards. The tool must have the ability to induce pump pressure and compression of the crimp head on a daily basis. Intermixing of products and tooling of several vendors is possible if the vendors have carried out respective testing and provided written approval. Deviation from this requirement can result in cancelation of UL certification. Document: GEI _GE.all_Tower (System)_Power Cable Splice and Lug Installation_575V_690V. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 406/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 1. Verify the power cables (690 V) between the converter and the generator are phased correctly. 2. Write phasing date inside the door of cabinet. – Original – Installation Manual Figure 547: Cables prior to connecting 3. Ensure cables trefoils are routed per drawing and secured to the tower cable tray. Ensure the cables are parallel and not crossed. 4. Ensure the cables are not resting against any sharp edges. 5. Maintaining the correct phase rotation, push cables into the rotor cabinet through the cable glands. NOTE Note the cable labeling! Refer to the document: GEI _GE.all_Tower (System)_Power Cable Splice and Lug Installation_575V_690V. Figure 548: Cables pushed into the Rotor Cabinet CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 407/428 GE Renewable Energy 6. Place the lug against the bus bar aligning bolt hole(s). 7. Place the cable against the lug and mark the cable allowing for enough cable to be inserted into the lug barrel for final crimp and ensuring there is a nice cable transition from the tower cable tray into the cabinet as shown on the illustration. Installation Manual – Original – Figure 549: Marking the cables to cut 8. Pull the cables outside the cabinet and cut them to the appropriate length. Figure 550 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 408/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 9. – Original – Installation Manual Place the lug against the cable to mark the correct cable insulation strip length that will be inserted into the barrel. Allow for enough cable to be inserted into the lug barrel for final crimp in accordance with the connector’s manufacturer crimping requirements. 10. Strip and remove the cable insulation and take care not to damage conductors. 11. Install heat shrink sleeves over the cables. 12. Install the lugs. Figure 551 13. Crimp lugs per manufacturer's instructions. Ensure no strands are cut or outside the connector. 14. Complete the tests per the latest revision 104W2311 Insulation Integrity Test Procedure. Figure 552 15. Apply heat shrink in accordance vendor application instructions. 16. Mark the cable ends with electrical tape or other means in accordance with the applicable electrical code. Figure 553 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 409/428 GE Renewable Energy – Original – Installation Manual 17. Ensuring the correct hardware orientation, terminate the rotor cabinet bus bars, torque and mark them with a paint pen. 18. Write torque value, company name, date and initials on the back of the cabinet. 19. Record the torque values in the torque report. 20. Pull test all cables by hand to ensure conductors and hardware are not loose. 21. Ensure cable glands are tight. 22. Inspect inside the cabinet, on top and around connectors in the converter for misplaced tools or hardware. Figure 554 23. Vacuum and/or remove any debris, e.g. wire strands, metallic shavings, tools, unaccounted for hardware and animal/rodent debris. Remove any debris that can potentially cause an arc. 24. Close the rotor panel. Figure 555 DANGER Danger of equipment damage! If a tool or hardware is dropped anywhere inside the cabinets or unaccounted for, or damaged cables are found, do not energize the turbine until missing or unaccounted parts or tools have been found and removed. Report to GE's site manager immediately if parts or tools cannot be found. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 410/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 18.13 Connecting the 6 kV Generator Stator Cables to the Stator Switch Cabinet SSC DANGER Life-threatening hazard! Danger! Electricity! Before performing any work on or in electrical equipment within the WTG you must be trained on the safety and operation of that specific model and manufacturer of equipment. Personnel performing this work are required to request training for operating, assembling of the SSC cabinet 30 days before performing this work. Only technicians qualified to perform work on Medium Voltage equipment should be performing electrical connections or testing. The 6 kV cables are pre-installed in the machine head and in each tower section by manufacturers respectively. The field teams will lower the cables from the WTG to the tower and splice cables at each tower level ensuring the correct phase rotation sequence and marking of the cables are maintained thought the tower. The following steps cover transition between the tower and the SSC cabinet in the PPM controller level. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 411/428 GE Renewable Energy 6 kV cables are spliced at the converter level and routed through the cable tray and secured with cable ties down to the controller level back of the SSC cabinet. Cables transferring between the tower and SSC – Original – Installation Manual Front Side 6 kV Generator to Schneider SSC Connections Back side of the Schneider SSC cabinet CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 412/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – 1. Verify the stator cables (6 kV) between Generator, Tower and SSC are phased correctly. 2. Mark the cables with electrical tape or other means in accordance with the applicable electrical code. 3. Write the phasing date inside the door of cabinet. 4. Verify the stator lugs at the generator are isolated. Installation Manual ATTENTION For all cable runs, the cables must be disconnected from the equipment on both ends for testing purposes. Figure 556 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 413/428 GE Renewable Energy – Original – Installation Manual DANGER Fall hazard! If an employee is working at a height that exposes them to a potential fall, an appropriate ladder and/or fall arrest equipment must be used as required, and 100 % tie-off at all times. A retractable lanyard can be utilized. 5. Remove back panel of the SSC cabinet and Route 3 6 kV cables between the tower and the SSC cabinet. Secure cables to the upper DIN rail with cable clamps. Figure 557 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 414/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 6. – Original – Installation Manual Maintaining the proper phasing sequence push the cables through the hole openings into the SSC cabinet. Figure 558 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 415/428 GE Renewable Energy 7. Open the SCC cabinet door In some SSC configurations the 6 kV bus bars are located behind the ceramic fuses. 8. Carefully remove the fuses and place in safe area to prevent damage. GE Limitamp SSC does not require removal of the fuses. – Original – Installation Manual Figure 559 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 416/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy 9. – Original – Installation Manual In SSC cabinet: Remove the 3 plastic covers to expose the bus bar connecting points. Figure 560 10. Position the cables against the respective bus bar. 11. Measure and cut the cables to length. 12. Install the concentric neutrals. Figure 561 CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 417/428 GE Renewable Energy – Original – Installation Manual 13. Crimp the cables per splice manufacturer's instructions. 14. Apply heat shrink sleeves per manufacturer’s instructions. 15. Perform a pull test after the cables have been spliced to ensure the cable connectors are not loose. 16. Perform test between SSC and generator (6 kV stator cable connections) according to GE procedure 104W2311. 17. Maintaining the correct phase rotation sequence terminate cables on the SSC bus bars L1 – L2 – L3. 18. Torque the hardware and mark with a paint pen. ATTENTION CRITICAL TO QUALITY! Figure 562 While torqueing the hardware, DO NOT use the red bracket for support and avoid any external pressure on the red bracket. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 418/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 19. In the SSC, route the concentric neutrals from each cable and terminate to the designated grounding point. 20. Torque the hardware and mark with a paint pen. Inspect inside the cabinet, on top and around connectors in SSC. Figure 563 18.13.1 Connecting the 6 kV Generator Stator Cables to the Stator Switch Cabinet SSC LimitAmp Cabinet DANGER Life-threatening hazard! Danger! Electricity! Before performing any work on or in electrical equipment within the WTG you must be trained on the safety and operation of that specific model and manufacturer of equipment. Personnel performing this work are required to request training for operating, assembling of the SSC cabinet 30 days before performing this work. Only technicians qualified to perform work on Medium Voltage equipment should be performing electrical connections or testing. The 6 kV cables are pre - installed in the machine head and in each tower section by manufacturers respectively. The field teams will lower the cables from the WTG to the tower and splice cables at each tower level ensuring the correct phase rotation sequence and marking of the cables are maintained thought the tower. The following steps cover transition between the tower and the SSC cabinet in the PPM controller level. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 419/428 GE Renewable Energy – Original – 6 kV cables are spliced at the converter level and routed through the cable tray and secured with cable ties down to the controller level back of the SSC cabinet. Installation Manual Front Side 6 kV Generator to GE SSC Connections Verify the stator cables (6 kV) between Generator, Tower and SSC are phased correctly. Maintaining the correct phase rotation, push cables into the SSC cabinet through the cable glands. Cables transferring between the tower and SSC secured to the DIN Rail with fast clamps. Adjust the cable as required maintaining the required Cables are secured with cable ties minimum bend radius for the 6kv to the tower cable tray located cable. behind the SSC cabinet. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 420/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 18.13.1.1 Routing and Terminating Cables to the Bus Bars 1. Align the cable lugs to the bus bar. Ensure there is enough length to terminate without putting strain on the cable or exceeding the minimum bend radius. 2. Adjust the cables as needed to provide spacing between the cables to conform to regional standards. 3. Test the cable in accordance with 104W2311 prior to terminating the cables. DANGER Electrical Hazard! Cable ends need to be isolated on both ends to prevent contact with other equipment during the test. ATTENTION Figure 564: Aligning the cable terminals to the bus bar For all cable runs that require testing, the cables must be disconnected from the equipment on both ends for testing purposes. 4. Once IR testing is completed ensure the lugs are oriented correctly in relation the bus bar and tighten the cable glands and cable clamps. Critical to Quality: 5. Place the cables so that the cable connector is resting against the inside of the bus bar and aligned with the center hole as shown on the illustration. 6. Maintaining the correct phasing terminate cables on the SSC side L1 – L2 – L3. . 7. Torque the hardware and mark with a paint pen. 8. Reference to the 3MW bolt torque specification. Figure 565: Cables bolted to the bus bars CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 421/428 GE Renewable Energy Installation Manual – Original – Critical to Quality: 9. Apply Electrical Insulation Linerless Rubber Splicing Tape 130C in accordance with Appendix – A Taping the Lower Connection. Critical to Quality: Failure to apply the tape as prescribed can lead to catastrophic damage to equipment. Figure 566: Electrical Insulation Linerless Rubber Splicing Tape applied 10. Terminate the concentric neutrals to the nearest equipment grounding bus bar shown on the illustration. Reference to the 3MW bolt torque specification. Figure 567: Equipment grounding bar 11. Verify the stator cables (6 kV) between Generator, Tower and SSC are phased correctly. 12. Mark the cables with electrical tape or other means in accordance with the applicable electrical code. 13. Write the phasing date inside the door of cabinet. 14. Verify the stator lugs at the generator are isolated. Figure 568: (6 kV) stator cables at Generator CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 422/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 15. Inspect inside the cabinet, on top and around connectors in SSC cabinets and transformer. 16. Remove any debris that can potentially cause an arc flash event in SSC and cabinets and transformer. 17. This may require the removal of panels and use of mirror and flash light as required. 18. Verify no loose or misplaced tooling is left attached to the bus bars in SSC and Transformer. 19. Look for misplaced hardware, such as nuts, washers, and bolts that may have fallen near or around the SSC and transformer. 20. Using a mirror and a flashlight, verify manufacturer materials such as loose manuals or loose cables are not left in SSC and Transformer. 21. Inspect for debris or damaged cables in SSC and transformer. 22. Re-install all isolation barriers. 23. Close all cabinet doors at the end of shift and/or after completion of work. WARNING CRITICAL TO QUALITY! Failure to account for all hardware or remove all tooling and debris can result in catastrophic damage to equipment. 18.13.2 Critical to Quality Testing and Inspections Generator 1. Confirm proper phasing and all testing according to 104W2311 is done. 2. Terminate the stator/rotor and ground cables in the generator per point to point drawing. 3. Write torque value, company name, date and initials on the outside the generator cover. 4. Record the torque values in the torque report. Converter – 400 V 1. Confirm proper phasing and all testing according to 104W2311is done. 2. Terminate the 400 V cables in the LVDP per point to point drawing. 3. Write torque value, company name, date and initials on the inside of the converter cover. 4. Record the torque values in the torque report. Converter – 690 V 1. Confirm proper phasing and all testing according to 104W2311 is done. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 423/428 GE Renewable Energy Installation Manual – Original – 2. Terminate the rotor and ground cables in the converter per point to point drawing. 3. Write torque value, company name, date and initials on the inside of the converter cover. 4. Record the torque values in the torque report. Generator to (SSC) – 6 kV 1. Confirm proper phasing and all testing according to 104W2311 is done. 2. Terminate the stator and ground cables in the synchronization switch per point to point drawing. 3. Write torque value, company name, date and initials on the outside of the synchronization switch cover. 4. Record the torque values in the torque report. Transformer to (SSC) – 6 kV 1. Confirm proper phasing and all testing according to 104W2311 is done. 2. Terminate the stator and ground cables between the transformer to synchronization switch per point to point drawing. 3. Write torque value, company name, date and initials on the outside of the synchronization switch cover and near the transformer connection visible for inspection. 4. Record the torque values in the torque report. 5. Terminate the ground cable in the generator junction box per the latest point-to-point-drawing. 6. Write torque value, company name, dates and initials on the inside of the cover in an area visible to inspectors. 7. Terminate the stator cables in the generator junction box per the latest point-to-point-drawing. 8. Write torque value, company name, dates and initials on the inside of the cover in an area visible to inspectors. 9. Re-terminate the ground cables to the grounding bus bar in the PPM. 10. Re-terminate the stator cable lugs in the converter threads. Prior to Closing Cabinet Panels or Completion of Work. 1. Inspect inside the cabinet, on top and around connectors. 2. Remove any debris that can potentially cause an arc flash event. 3. This may require the removal of panels and use of mirror and flash light as required. 4. Verify no loose or misplaced tooling is left attached to the bus bars and in any of the transformer coils. 5. Look for misplaced hardware, such as nuts, washers, and bolts that may have fallen near or around the any of the electrical connectors, bus bars or transformer coils. 6. Using a mirror and a flashlight, verify manufacturer materials such as loose manuals or loose cables are not left in any of the equipment/electrical components. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 424/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – 7. Inspect for debris or any damaged cables. 8. Close all cabinet doors at the end of shift and/or after completion of work. Installation Manual NOTE The final installation of the climb assist or the service platform (lift) must be performed as per manufacturer's instructions. The installation and commissioning certification must be added to the Job Site Book. 18.14 Installing the Floodlighting 1. Mount the fixture of floodlight and motion sensor above the tower entry door on the outside of the tower. 2. Connect the installation box to the supply lines of the fixture. Refer to the manufacturer's instructions. 3. Connect the power cable inside the main controller cabinet as per the electrical wiring diagram. 4. The final adjustment of the light fixture is as required during maintenance activities. Figure 569: Floodlighting 19 Ground Resistance Test 1. Perform the CE ground resistance test as per the document: 2.5-100_xxHz_WDI_allComp_TestEN60204 (if required by the electrical codes of the respective country). CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 425/428 GE Renewable Energy Installation Manual – Original – 20 Verify the Gearbox and Generator Alignment Refer to: Document: 2.x_WDI_gearbox_alignment Document: 2.x_xxHz_WDI_generator_aligning NOTE After rotor installation has been completed the installer will verify the alignment of the gearbox in accordance with the WDI 2.x_WDI_gearbox_alignment and use tolerances given in the WDI. Consult with GE to obtain the WDI applicable to each unit. NOTE If cables are not installed prior to Generator Alignment, ensure that the cables are protected from damage and falling objects. NOTE After gearbox alignment has been completed the installer will verify the alignment of the generator in accordance with the WDI 2.x_xxHz_WDI_generator_aligning and use tolerances given in the coupler specified drawing. Consult with GE to obtain coupler drawings applicable to each unit. 1. Ensure a blank copy of the coupler drawing does indeed match the coupler for the unit being worked on. Verify generator axial, angularity, and offset is within specified tolerances. If it is not, move the generator in the appropriate direction per WDI so that axial, angularity, and offset are within specified tolerances. Consult with GE for the current alignment report form. The final alignment must be verified by GE and the alignment report must be placed in the Job Site Book. 2. Ensure all guards and hardware have been properly installed. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 426/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx GE Renewable Energy – Original – Installation Manual 21 Remaining Work After all the work has been concluded, the entire Wind Turbine Generator System must be cleared. DANGER Check the WTGS – especially the control cabinets – before concluding the work! Remove all loose parts, tools and materials from the WTGS – especially from the control cabinets. Tools and materials left behind in the control cabinets can lead to an arc flash or unsafe working conditions for the service engineers when the turbine is commissioned. DANGER Hazard at the generator junction box! Remove rotor lock LOTO: Disengage the rotor lock. Verify the rotor locking accessories are properly secured. Open the high-speed shaft brake valve and check that the pressure gauge reads 0 bar, then close the valve. Verify the brakes are mechanically released, the high-speed brake pads are centered and not dragging on the disc. Verify the rotor is completely free and can rotate. 21.1 Mechanical Completion Mechanical completion shall be in accordance with the contract language. CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx 427/428 GE Renewable Energy – Original – Installation Manual 22 Transport Fixtures 1. Consult with the GE site representative to establish the fixture return sequence schedules/ in accordance with Logistics procedures (LOG). 22.1 Downtower Equipment (PPM) 1. Return small parts, tie-downs and transportation frames to the place of origin. 22.2 Tower 1. Return transportation frames, transport braces, tie-downs, small parts and tarpaulins to the place of origin. 22.3 Nacelle 1. Disassemble, band and palletize transportation frames and small parts, as required, and load them onto a transport vehicle. 2. Return the feet or welded fixtures, small parts, and shaft cover to the place of origin. 22.4 Hub 1. Return small parts, tie-downs and transportation frames to the place of origin. 22.5 Nose Cone 22.6 Blades 1. Disassemble, band and palletize transportation frames and small parts as required, and load them onto a transport vehicle. 2. Return transportation frames, supports, small parts, tie-downs to the place of origin. 22.7 Special Tool Return PPM bumper rails E-palms Blade edge protectors PPM alignment jig CONFIDENTIAL - Proprietary Information. DO NOT COPY without written consent from General Electric Company. UNCONTROLLED when printed or transmitted electronically. © 2017 General Electric Company. All rights reserved. 428/428 Installation_Manual_3MW-DFIG-xxHz_EN_r02.docx