BASIC CONSTRUCTION MANUAL FORA SINGLE STOREY DOMESTIC DWELLING (RATES ARE APPLICABLE TO ALL BUILDINGS) PRODUCED AND PUBLISHED BY INCORPORATED MASTERBUILDERS ASSOCIATION OF JAMAICA FIRST EDITION 2003 REPRINTED 2022 Copyright Incorporated Masterbuilders Association of Jamaica 2003 ACKNOWLEDGEMENT This Basic Construction manual was developed by Incorporated Masterbuilders Association of Jamaica and during the process of it’s development, received assistance from a number of individuals and institutions. The Incorporated Masterbuilders Association wishes to acknowledge the invaluable contribution made by the following persons in the development and production of this manual. Mr. Stephen Hodges - CRDC chairman Mr. Garth Lampart - UTECH lecturer Mr. Rori Peynado Mr. Len Smith - UTECH lecturer - Quantity Surveyor Jamaican Institute of Architects Bureau of Standards The HEART Trust Milton Baker (J.1.A) FOREWORD For many years the demand has far outstripped the supply for housing in Jamaica. In recent years recession in the economy has resulted in a further widening of this gap. Shortfall in the housing stock, by the public or private sector, has forced house seekers to self directed means to satisfy their needs. This at times has led to many dwellings being constructed informally without adherence to building safety codes and practices, which specifies minimum accepted building requirements. Jamaica is located in the hurricane and earthquake zones. Hence, shortcoming in building construction has created a grave concern for the possible loss of lives and damage to property that could result in the event of these natural disasters. The Incorporated Masterbuilders Association of Jamaica has recognized the inherent dangers of improperly constructed dwellings and seek to offer this Basic Construction Manual as a guide to owners, small contractors and builders of single storey domestic dwellings with the hope that adherence to the minimum standards outlined will reduce the risk of loss of live and property. In addition to construction guidelines, this manual also includes the latest Joint Industry Council’s (JIC) rates available at the time of printing, along with a listing of suggested job work rates for a number of construction activities. These job work rates are provided only as a guide when negotiating rates. Several factors such as, the condition of work, scope of work and geography, will have varying impacts on these rates. Therefore, it is suggested that these factors be considered when negotiating rates, as the ones included in this manual may not be the latest being used in the industry. Copies of the latest rates are always available from the office of the Incorporated Masterbuilders Association of Jamaica. Also included is an example of a simplified Form of Agreement that may be used by owners and contractor / builder when a dwelling is to be constructed. It is advisable that some form of written contract be entered into as projects at times do not always end amicably. CONTENT STAGE 1 — PREPARING A PLAN OR SKETCH STAGE 2 — SETTING OUT STAGE 3 — EARTH WoRK- FOUNDATION STAGE 4 — REINFORCEMENT STAGE 5 — CONCRETING - BLOCKWALLS- RENDERING STAGE 6 — ROOF - CONCRETE- TIMBER STAGE 7 — FLOOR - CONCRETE- TIMBER STAGE 8 — FIXTURES - WINDOWS/DOORS/CUPBOARDS/CLOSETS STAGE 9 — PLUMBING STAGE 10 — ELECTRICAL WORKS STAGE 11 — FINISHING - PAINTING/CABINET MAKING/JOINERY/PLASTER — JIC AGREEMENT & LABOUR RATES — SUGGESTED SUBCONTRACT / JOB WORK AUTHOR TYPESETTING — — NEVILLE BOXE DONETTE SPENCE RATES Basic Single Storey Building Construction THE PLAN OR SKETCH _ THE FIRST STEP TOWARDS DWELLING DRAWINGS INFORMATION MATERIALS, IS TO PREPARE AND THE CONSTRUCTION A DRAWING OR A SKETCH. SKETCHES ARE IMPORTANT REGARDING THE SIZE, SHAPE, TYPE OF AND IMPORTANT OF A AS THEY CONTAIN SPECIFICATIONS FOR THE SAFETY OF THE BUILDING. e The drawings are best prepared by a qualified Architect, however some experienced provide this service. e draftsman or builder also Seek approval from your local Parish Council or agency where applicable. e At least one person involved in the construction of the building should be able to read and interpret the drawings to ensure conformance with the details and specifications. o dl O SETTING OUT THE BUILDING BJECTIVE To examine the drawing or sketch in order to position the buildings on the site or lot and ensuring that the stipulated distances from boundaries on existing structures are maintained. Then mark out exactly the positions of external and internal walls on profile boards and to ensure squareness and accuracy. Picasa. e Contractor/builder e Skilled carpenter OOLS/EQUIPMENT QUANTITY 1 ITEM/DESCRIPTION 5 lb hammer Pi PI] PI] Pi RPipB Spirit level Plumb bob Pencil or chalk Builder’s square Mason’s square Rule Long tape PP T Cord line MATERIALS 1”x 3” Timber (profile boards) 2”x 4” Timber (pegs) 1/2” @ Steel (pegs) Mi erson =>STEP 1 Clear site of debris, shrubs, trees and any obstacle that would interfere with the setting out and construction of the building. => STEP 2 Drive steel pegs at the approximate position of the proposed building in relation to land space or lot boundaries. DISTANCE FROM REAR | BOUNDARY +— SIDE APPROXIMATE POSITIONOF = BUILDING = BOUNDARY DISTANCE FROM FRONT | BOUNDARY SIDE Lot Boundary If the land has a registered title it is best that the boundaries be located by a commissioned land surveyor to avoid mis-locating building. Failure to locate building accurately could result in costly legal implications. => STEP 3 e Use measurements and steel pegs to locate approximate position of outer walls of the building. e Drive 2’x4” timber pegs in locations approximately 2’-0” outside the walls at each commer to accommodate profile boards (1”x3” timber). e Locate profile boards at approximate floor level height, using a spirit level and chord line, to ensure that the profile boards around the entire perimeter, are accurately leveled. e On these profile boards the shape and exact dimensions of the building will be marked. PLAN SHOWING PROFILE BOARDS PROFILE BOARDS ARE LOCATED APPROXIMATELY 2'-0” FROM OUTER WALLS Profile Board = —+ APPROXI MATELY 2’-0" FROM OUTER WALL Aggregate Profile Board Concrete Mixer oS ¥ LEVELLED _ANO rE FLOOR LEYE CUNDATION CAN ELY => STEP 4- MEASURED Mark the positions of walls, foundations and ensure squareness. e Locate the position of wall and foundation on first set of profiles, marking with pencil, nail or saw cut. e Locate second and subsequent walls and foundations using lines and :a) Mason’s square b) Builder’s square c) The 3:4:5 method e The 3:4:5 method: any combination of the ratio will ensure a square cornerexample using a long tape and setting out triangle with sides e.g. (15’-0” x 20’-0” x 25’-0"). a o co oy = TD Pp 3:4:5 TRIANGULAR METHOD Building Edge L | a }S 1, 4 \ BUILDERS LEVEL MAISONS LEVEL _ r zx : ed i \ L | BR. \ } XN x a 7 \ SA \ \ S Lot Boundary a % 4 / }r™ ‘ YX co oI | Diagonal Lines \ a | aN hey bo *——~ fu #} wl it Profile Board u \ oO o oO LOCATE FRONT POSITION OF WALL IN RELATION TO BOUNDARY PLAN DIAGONAL METHOD OF CHECKING e To check the accuracy and squareness of the setting out, the diagonal method may be used. To do this, use a long tape to measure both diagonals. Their measurement should be the same. If they are not, re-check the squareness of each corner and the measurement of each wall length. Measuring Tape @ Spirit Level Profile Board (1 x 3" Timber) 2” x 4° Timber 3 = Chord Line —_ 4 Trench Centreline Plumbing Bob on String Intersection of Chord Lines Chord Line => STEP 5- MARKING OUT FOUNDATION e Locate lines in the position marked out on the profiles for foundation. e Use a trail of sand or other suitable material and mark out the position of foundation on ground in preparation for excavation. © Eff O EARTHWORKS « FOUNDATION BJECTIVE To accurately excavate trench as set out on profile to depth not less than 2’-0” in earth to facilitate pouring of reinforced concrete foundation. P ERSONNEL e e T Contractor/builder/supervisor Labourers OOLS/EQUIPMENT ITEM/DESCRIPTION QUANTITY MANUAL a aesiac ree - . 1 | 1 Backhoe ‘ excavator 7 a = Pickaxe —— If extensive rock is encountered a jack hammer connected to an air compressor plant would be required. Merson DIGGING THE FOUNDATION TRENCH e Remove the building lines attached to the profile board to avoid them getting broken. e Replace the lines in the notches on the profile boards should you need to check the accuracy of the trench layout. e Foundation trenches should always be dug deep enough to reach firm soil. The sides of the foundation trench should be vertical, the bottom level and the comers must be square. e Check that the soil at the bottom of the trench is firm. If not, the supervisor must ensure that action is taken to appropriately reinforce the foundation. POSSIBLE ACTIONS * Deepen the trench until firm soil is reached. If deep foundation is not reached then an alternate foundation design must be considered- (raft foundation or pile foundation) and a civil or structural engineer should be consulted. « Alternate design for foundation may be expensive therefore in such situations, it might be best to seek a better site. ANTI-PEST TREATMENT Treat the surface of the ground and excavations under the building with soil poisoning chemicals to eradicate subterranean termites. © Pieeannc No 1. FOR CONCRETE Pegs are driven into the bottom of the trench and leveled in order that a minimum of 200mm (8”) thick allowance is made for concrete. The trench must be made level by removing soil, never by adding soil. If soil is added, the foundation may fail. It may mean digging the trench slightly deeper, but it will ensure your building remains strong. 3. Remember the purpose of the reinforced concrete foundation is to distribute the weight of the building safely to firm soil. tl O STEEL REINFORCEMENT FOUNDATION WALL BARS STIFFENER/COLUMNS LINTELS/BEAMS ROOF SLAB/CANTILEVERS BJECTIVE To cut, bend, place and fix steel reinforcement, as designated accordance with the building code. P ERSONNEL e Contractor builder/supervisor e Steel fixer e Labourer E QUIPMENT & MATERIALS QUANTITY ITEM/DESCRIPTION MATERIALS As needed Mild steel corrugated bars. 1/4", 3/8", 1/2", 5/8", 3/4", diameter No. 126 steel fabric EQUIPMENT 2 Hack saw ] Steel cutter 1 Bending Bench and in © Merson Cut, bend place and fix reinforcement as per bending schedule (if provided). e For the safety of the building, all laps and bends should conform building code. TYPICAL BENDS —— pan | [ a EG ee Fae Se) TYPICAL FOUNDATION STEEL Transverse Steel Bar Longitudinal Steel Bars TYPICAL STRIP FOUNDATION 4*——— PS SAOATS e Concrete Block Wall Vertical Steel bars Anchored in Surip Foundation fx 2 iS ‘ sania my xa WY Reinforced Concrete ‘ Strip Foundation * — 2 &_ | 24" (600) | Longitudinal Steel Bar with the TYPICAL COLUMN/STIFFENER Horizontal Steel Bar — Passes Through Stiffener +——————_ . Horizontal Steel Bar Anchored in stiffener Column Concrete Block Wall —_, Vertical Steel Bar Fy wc o| | Stiffener Column =, _D— we i| 12° (300) | CC iE = ¥ —j—}. TT} i y i Vertical Steel Bar Block Pocket Next to Stiffener Column Horizontal Steel Bar Passes Through Stiffener Column TYPICAL BEAM/LINTEL TYPICAL SLAB ROOF WITH OVERHANG Over Support Steel Bars jen Reinforced Concrete Roof Slab Steel Link Reinforced 2 Concrete Belt Beam =a" a ° Overhang ‘ ra 5 f vi Block iC Wal! a ——— Steel Bars Bottom of Slab wh. Vertical Steel Bars I] Lat Anchored inConcrete Belt Beam eh. =5§ ———"|-"| | J ar Inside Building TYPICAL FLOOR REINFORCEMENT Concrete Block Wall Steel Close To Top Top Concrete Floor Slab Fit, TL LEW Ground Level ———+}-— Compacted Fill ie. Reinforced Concrete Strip Foundation CONCRETING O BJECTIVE To prepare specified concrete by mixing the basic ingredients. e Coarse aggregate (gravel) e Fine aggregate (sand) e Cement (ordinary Portland cement) e Water (drinking water) HAND MIXING OF CONCRETE Prhisdinxt e Contractor or builder/supervisor © Four (4) labourer E QUIPMENT/MATERIAL EQUIPMENT Gauge box Square point shovel 5 gallon bucket MATERIALS As needed Cement (bags) stone- 1/2” to 1” size Sand (washed) Water (suitable for drinking) STEP 1 Construct a gauge box size to hold one bag of cement. Drum of Water Mixing Board Wheel Barrow Concrete Mix Gauge Box Fine Aggregate Coarse Aggregate sap a ee er eared) rey Ye © STEP 2 Gather materials e e e e Fine aggregate (sand) Coarse aggregate (gravel) Cement (Portland) Water Cement 1 box full 2 box full Gauge Box 4 Box full Gauge Box Make a batch of — ing proportions 1:2:4. This means | part cement to 2 parts sand to 4 parts gravel. concrete usby volume STEP 4 e Fill gauge box with sand and deposit on mixing board or a concreted area. e Spread sand evenly about 3" (75mm) thick. STEP 5 Measure and spread cement ontop ofsand laid on mixing board. ae ~ -« eS ie g board © STEP 6 Use shovel to thoroughly mix cement and sand together. STEP 7 Level oot and spread the sand and concrete mix about 3” (75mm) bed as in step 2. STEP 8 Use gauge box to measure and spread the coarse aggregate (gravel) on the sand cement mix. STEP 9 Mix the material and move Sym around as you mix. =U) Move Around and Mix the Concrete Continue mixing until es all the materials are thoroughly mixed and uniform in colour. Concrete Mix STEP 10 Mixing Board Using your shovel make a circle of your mix and a hollow in the center for water. Make Hollow in Centre of Mix ® STEP 11 The quantity of the water required for the mix is calculated as follows. L “4 t. ~ Tt Py Mixing Board. ——+ |) Note: If the sand or stone is somewhat wet, then the amount of water used should be slightly reduced. Conerete Mix Sa SN — The mix should be relatively stiff and not soupy, to ensure adequate strength. The strength of the concrete is affected by the amount of water in the mix. Too much or too little water gives weak concrete. Strong concrete is not soupy or too stiff. The amount of water added to get a good mix should be measured. Mixing Board For each batch of concrete that follows, the same amount of water should be added to the mix. This will ensure consistency in the strength of the mix. @ STEP 12 When the water has been somewhat absorbed by the materials, use the shovel and carefully mix, ensuring that the water does not escape from the center of the mix. Mixing Board STEP 13 After thoroughly mixing, there should be consistency in appearance. The concrete is now ready to be poured. Note: When water was added the setting process began, so delays in pouring should be avoided. WALLS O - BLOCKLAYING BJECTIVE To provide load bearing support for the roof and act as a cladding to protect against the elements of wind, rain, dust and smoke. General Note Load bearing walls should be a minimum 6" or 150mm in thickness. Non-load bearing walls separate rooms, but do not support the roof. They should be at least 4" or 100mm thick. Pp ERSONNEL e e becis Masons labourer EQUIPMENT/MATERIAL As Needed Blocks ® Mortar “a Mason’s Tools “a Corners/Rods for laying line Laying Concrete Blocks It is of utmost importance that block walls are laid straight and plumbed vertically. The best method to ensure this is by using corner rods which are plumbed with a spirit level and stabilized with braces. The rods may be of timber with a straightened edge, or light metal such as aluminum. The line is fixed and leveled horizontally about 3/16” or 4mm away from the wall. The mason uses this as a guide keeping the gap constant by eye sight. He should not try to build close against the line. Some ma- LL "sons resort to using a spirit level to level and plumb each row of block especially at the corners to ensure that the wall is laid vertical and straight. bal. reyes StSaeco tt -_ @ Meson 1. Laying block is one of the most common tasks performed by a mason. 2. The most effective method of laying block is to use a mason’s line as a guide. 3. Laying block to a line requires the use of many repetitive activities such as: e Spreading mortar Placing block wy ~ ° = — w w oO Oo Soe oo £ = iz ® 4. Now lets follow the procedure followed to lay block to a line. 5. First fix the masons line from corner to corner. In the case of the first course a second line near the bottom edge of the block is required to plumb the first course. 6. Safety note: A line which fails to remain straight when pulled can cause serious injury to people working on the line. Fix the line securely to the corners on guides. = sania he { L Res, eI —f Dew ac 7. Place the blocks along the line leaving enough space for spreading the mortar. 8. Next spread the mortar for bedding the first course. 9. Starting from the corner lay each block to the line gauging the cross joints. @ 10. The top end of the block should be level with the top of the line. 11. The clearance between the block and the line should be approximately 3/16" or 4mm. 12. Fill the cross joints solid. 13. For each subsequent course of blocks fit the line to the corners. Make sure that the line is fixed to the same course height at each corner. @ 14. Place the blocks to be laid along the wall and spread mortar for the joint along the top of the previous course. 15. Lay the blocks to the line taking care to regulate cross joints and check the positioning of the top edge of the block with the mason’s line. e Lay block © Check line for level and clearance fi o JK M7 VAR > d @ © 16, Fill all cross joints and clear away all excess mortar. e Fill cross joints e Clear excess mortar 17. Repeat these procedures until you have constructed the block wall to the specified height. 18. Practice laying block to the line until you feel you have mastered the skill. Ell O ROOF BJECTIVE To install covering to dwelling in accordance with type and design indicated on the drawing. Function of Roof The main function of a roof is to provide protection from the weather. In our geographic location, the ability to resist the forces of hurricane is of utmost importance. Type of Roof structure 1. Timber Structure This supports coverings such as: e Sheets— zinc, aluminum (plain, troughed or corrugated) e Shingles— wood, fiberglass, aluminum e Tiles— clay, concrete 2. Reinforced Concrete Slab This acts as both a structural element and cover. We will focus on the construction of : 1. Timber roof structure supporting zinc or aluminum sheeting. 2. Reinforced concrete slab. 1. Timber Structures with Zinc/Aluminum Sheeting P ERSONNEL e Contractor or builder/supervisor e Skilled carpenter or roofer e labourer EQUIPMENT/MATERIAL T OOLS/EQUIPMENT (QUANTITY | ——_—‘ITEM/DESCRIPTION, 1 Carpenter’s saw 1 Hammer L Chisel 1 Rule a Long Tape 1 Cord line MATERIALS =| Battens/ Purlins ITEM DESCRIPTION Treated 1"x 2 (25 x 50mm. Covering Materials Hurricane Straps 50 x 50mm. 25 x 75mm. 50 x 100mm) |/Sheets of zinc, aluminum Wood Wall Plate 2"x 2", 1"x 3", 2"x 4" timber Treated fillets 2" x 4" (50 x 100mm) timber. |Twisted steel straps Nails As described in drawings Screws As described in drawings Nuts & Bolts As described in drawings, hold down bolts © heron (a) With wall plate =>STEP 1 > Ensure that hold down bolts are cast in concrete belt beam at 4'- 0" (1200mm) centres with 2 1/2" (62mm) projection. Timber Wall Plate ———_ Reinforced Concrete Belt Beam —__,] Flat Washer * Coat Under Nut | 212 "(62MM)END PROJECTED ABOVE CONCRETE IN BELT BEAM _# HOLD DOWN BOLTS (é 4-0" INTERVALS Concrete Block Wall ——* A 7 STEP 2 (b) Without wall plate Rafter support are accurately positioned and strapped to belt beam formwork prior to pouring of concrete. Rafter supports are installed to ensure that the angle iron do not protrude above rafter. Establish desired pitch of roof using carpenter’s square, level and cord line. q 7] | tr “1 1/4" x 1 1/4" x 1/4" (32x 32 x 6mm) ANGLE IRON APPROX. 14" (350) LONG CAST IN BELT BEAM AT EVERY RAFTER — @ e Position and strap rafter support to belt bead form work prior to pouring of concrete. Rafter support are installed to ensure that the strap does not protrude above rafter. e Establish desired Pitch of roof using carpenter’s square, level and cord, to line out roof. e Bolt each rafter to hold down angle iron on top of belt beam using 3/8” (LOmm)dia. Bolts. = a = oe " > 2 No. 3/8" (10mm) DIA MS BOLTS FOR MEMBERS 2" x 6" (50 x 150) & ABOVE. 1No. 3/8" (10mm) DIA MS BOLTS FOR MEMBERS “ANCHOR 7 | ; o 3/8" (10mm) BOLTS AND NUTS 2" x 4" (50 x 100) STRIPS a ee RAFTER SUPPORT& =f HURRICANE STRAP) ‘ik “\ 1 » 2" x 4"(60 x100) OR 2" x 6" \ — (60x 150) RAFTER 1" x 3* Battens §—— Laths nailed to rafters Secured with twisted hurricane straps & 1/2" x 10" Hold down bolts i a x pea * == 5r 5 e 6" CC load bearing wall PITCHED ROOF 1:2" x 10" Hold down bolts 2" x4" Wall plate __6" C.C load bearing wall r FLAT ROOF (10% 08 Less) => STEP 2 cont’d. e e Locate and position ridge board using temporary support, then by using an adjustable carpenter’s square, cut rafters to fit neatly with ridge board. Locate and notch rafters to obtain perfect fit on timber wall plate. It is best to establish the outermost rafters first and then level and stretch lines from the extreme locations. Intermediary rafters may then be cut and fitted, ensuring conformity with the established lines. e The foot of the rafters should be accurately notched to fit neatly to the timber wall plate. => STEP3 INSTALLING ROOF e COVERING Battens (laths) or purlins are nailed or screwed in place at spacings not exceeding 3'-8" (1100mm). (Recommended at 2’6” for most construction). Hurricane Strap Fascia Board —— i Le eA Blocking Board j RAFTER NOTCHED Reinforced Concrete Belt Beam e Roof coverings may be purchased in full length of the span on either side of ridge of a pitch roof. e The foot of rafters should be accurately notched to fit neatly to the timber wall plate. After the roof structure is accurately established it may then be perma- e nently nailed and hurricane straps used to connect rafters to the wall plate. e Use cord line to establish position of fascia board the cut vertically or at right angles to rafter. If the sheets are in shorter length, then laps should be a minimum of 8" (200mm) and 1 1/2" (37mm) corrugation across. Batten \ Rafter e Ridge Board Timber fillets should be used where ever the sheet is nailed or screwed to to I one . 1/2 ed the :purlin, avoid | Corrugated roof covering leaks. REINFORCED P CONCRETE ROOF ERSONNEL Contractor/ Building supervisor Skilled mason Skilled carpenter Concrete batcher Steel fixer Labourer T OOLS / EQUIPMENT All tools as listed before for carpenter, mason and steel fixer. MI ATERIALS Form Work 2" x 4" (50 x 100mm) timber 1" x 3" (25 x 75mm) timber laths 5/8" (16mm) plywood metal or wooden props. Reinforcement 1/2" (12mm) reinforcing steel bars. 3/8" (10mm) reinforcing steel bars. Concrete Cement, Washed sand, coarse aggregate size 1/2" - 3/4" (12—20mm), clean water. REINFORCED P CONCRETE ROOF ERSONNEL Contractor/ Building supervisor Skilled mason Skilled carpenter Concrete batcher Steel fixer Labourer T OOLS / EQUIPMENT All tools as listed before for carpenter, mason and steel fixer. MI ATERIALS Form Work 2" x 4" (50 x 100mm) timber 1" x 3" (25 x 75mm) timber laths 5/8" (16mm) plywood metal or wooden props. Reinforcement 1/2" (12mm) reinforcing steel bars. 3/8" (10mm) reinforcing steel bars. Concrete Cement, Washed sand, coarse aggregate size 1/2" - 3/4" (12—20mm), clean water. Note: a small slope Reinforced Concrete roofs are usually installed flat or with should be Care (pitch). This form of roof is excellent for resisting hurricane. taken to ensure that: a) the reinforcement used conforms to the specification, h b) the quality of the concrete is 1:2:4 minimum mix with just enoug water c) water does not settle on top of the roof slab. Meron = STEP 1 slab. Form work Construct and erect form work to support designed roof Minimum for belt beam and lintel may be installed at this stage as well. concrete thickness 4" (100mm) . Allow for water drips at slab eaves. = STEP 2 the design, Prepare, cut, bend and install all reinforcement according to ensuring correct spacings and laps. = STEP 3 Batch and mix 3000 psi (1:2:4) concrete, pour concrete around vibrator reinforcement. Compact and vibrate the concrete. A mechanical should be used, or hand tamped if one is not available. => STEP 4 float to The surface of the slab should be dressed using wood or steel resist water penetration. = STEP 5 wet freCover the exposed surface of concrete with paper or jute and concrete. quently for seven (7) days to ensure proper curing of the = STEP 6 us defects After ten (10) days remove all formwork and repair any obvio in the exposed concrete soffit. | FLOORS SOLID OR CONCRETE FLOORS F UNCTION AND DESCRIPTION To provide safe support for the occupants and furniture of the dwelling. This support form the ground and may consist of a hardcore spread and compacted on stripped ground within the perimeter of the building plan. Reinforced concrete is then spread evenly on top of the hardcore. O BJECTIVE To provide a level, even and smooth floor with concrete. P ERSONNEL e Contractor/building supervisor e Mason e Labourers E QUIPMENT / MATERIALS EQUIPMENT 2 Large Trowel 2 Wheel Borrow MATERIALS 1 | Minimum 2000 psi concrete Hardcore material, dump sand & marl. | As required Batter boards, screed & wooden Steel fabric rod Q Meernop e Strip topsoil within perimeter walls by (approx. (6”)150mm). e Place and compact finished floor level. e Place steel fabric across floor area ensuring that it is elevated above the compacted hardcore. e hardcore material up to 4” (100mm) below the Place and level wooden screed boards at convenient spacing in order to rod off and level the concrete ensuring a flat and level floor. e Prepare and mix concrete of minimum 2000 psi strength, transport in wheel barrows, place compact and rod in line with screed board. e After completion of pouring and leveling, surface may be wood floated or metal troweled to designed finish. At this stage colouring may be added to the finished surface if desired. FIXTURES WINDOWS/DOORS/CUPBOARD/CLOSETS On completion of the structural enclosure of a dwelling, fixtures such as doors, windows, cupboards and closets are ready to be installed. O BJECTIVE To install fixtures in a manner to provide security, utility and beauty. Pasco, e Contractor or builder/Supervisor e Finishing carpenter/Joiner E QUIPMENT / TOOLS / MATERIALS | TEMS i ~~ poors | DESCRIPTION Interior and exterior Jambs— metal or timber Hinges, locks WINDOWS Full frame— aluminum Glass louvre, wooden louvre, casement, french CUPBOARDS CLOSETS Kitchen, bathroom @ Meron INSTALLING THE FRAME Frames may be of wood or metal. Both timber and metal frames are pinned to openings to provide and maintain rigidity and support to e door/window. Squareness at corners is obtained with a carpenter’s square. e The jambs are plumbed and straightness maintained with the use of spacers until the pins are hardened in mortar. HANGING THE DOOR e The door to be hung internally or externally is first fitted against the installed jamb and cut where necessary, trimmed and dressed to provide a neat fit with approximately 1/8"(3mm) surround except for the bottom, where spacing should be 1/4” (6mm). e If the frame is metal, it is usually supplied from the manufacturers with a hinge and stop. If a timber frame, then hinges are located near the top and bottom approx. 6”-8” (150-200mm) of the door. e Doors are then screwed in position, tested for accuracy, swing, fit, e Locks and bolts are then installed. and adjustments, including trimming done to _ensure a proper fit. Approximately 1/8” space between door and frame minimises Saereomanpncoonsnaace ir @ WINDOWS Framed Windows If window frames are required then these are installed in similar manner as door frames. At times windows may be supplied with hinged on the frame, if not installation is similar to that of doors. Full Framed Aluminum The openings should be accurately squared and dressed, leaving minimum installation space of approximately 1/8” (3mm) all around. Windows are installed by plugging the walls and then screwing the frames in position. Window frame screwed to dressed opening. Cupboard Closets These may be pre-constructed and installed on location, or installed in position using frames and doors installation guide described above. PLUMBING O BJECTIVE To install water supply system to dwellings and wastewater disposal system from the dwelling. P ERSONNEL e Qualified plumber WATER SUPPLY SYSTEM The supply may be provided by legally connecting to public main using conduits (pvc, galvanized iron) 1/2°(12mm) or 3/4°(16mm) laid in trenches and at times casted in the concrete walls of the dwelling. WASTEWATER SYSTEM Large size drain pipes (pvc mainly 4”- 6” or 100mm-150mm), should be used to transmit wastewater from kitchen and bath room to septic tank, and absorption pit, or the public sewer main. Pipes should be laid with minimal fall of 1:40 for 4” (100mm) diameter pipes and 1:60 for 6” (150mm) diameter pipes. ‘ O | ELECTRICAL WORK BJECTIVE To provide safe electrical services to dwelling. In no circumstance should electrical installation be attempted without employing the services of a qualified and certified electrician. All wiring conduits and fittings should be in stalled by him. P ERSONNEL ° Certified electrician @ FINISHING RENDERING/PAINTING D ESCRIPTION RENDERING This is the application of one or more coats of cement mortar to the surface of a block or stone wall to provide an even and smooth surface. This may be done for beauty or to provide water proofing to the wall. Forming corners and straight edges in mortar requires great skill and time. Rendering may be done inside and outside, the standard form being two coats of 1/2” (12mm) thick cement mortar. APPLICATION ¢ Holes or hollows in wall should be filled and any projecting blocks e All loose dirt and dust must be cleaned from walls. e Walls should be well dampened before applying rendering. e Rendering should start at the top of the wall and work downwards. e A board should be placed at the bottom of the wall to catch any mortar that drops. This mortar can be used again providing it is still fresh. e Rendering should be applied evenly and to correct thickness. This can be ensured by screeding and lining out with plumb line and level prior to commencing rendering. ¢ Outside corners should be dressed by using straight edge boards. These should be checked and provided by a skilled carpenter. These should be fixed so that they project past the end of the walls by the desired thickness of the screeding. e Finishing to wall may be done with a wooden float or metal float depending on the desired texture. or mortar in joints chiseled off. @ WHEN TO RENDER It is advisable to apply rendering after most of the walls are substantially completed and initial settlement of building has taken place. nearest Approx. 1/8" thk. rendering | [LS PRS ort inal coat applied to i first coat (rough cast} ——=| ms fos Slight movement in a building wall will result in cracks in the rendering, it is best to wait until settlement has taken place. 3/8" thk. rough cast —=— applied to blockwall FORM AGREEMENT OF AGREEMENT made this.............:00-0:-s::2se08 Gay! Ofer nent iREIN BETWEEN EMPLOYER of CONTRACTOR of FOR THE WORKS SITUATE eens cent teeters SUPERVISING OFFICER (S.O.)........0:00:0eccee cnneamgueecnnon enscenneet RENEE or other appointed by the Employer. NOW IT IS HEREBY AGREED AS FOLOWS: Ds For the consideration hereinafter mentioned the Contractor will upon and subject to the conditions annexed hereto carry out and complete the works described in the specifications and/or Bills of Quantities and/or as shown on the contract Drawings. 2s The Employer will pay to the Contractor the sum of or such other sum as shall become payable hereunder at the time and in the manner specified in the said conditions. AS WITNESS the hands of the parties hereto signed by the said Employer sevecececomenenres Perera In the presence of: Name AGAess Description cab geUPesWeee aes Te eeeeUT ss seeesrmEenReenesenenentd —_aveseasiseasecccdeoenee supueveemasncapseonecssaasen - — ..scsseeeeseeeeseeeeeee seveneecerensnesccensensees a Signed by the said Contractor ecweonaewen: + eRes cesses ACATeSS.......ccecsencceeceerennenees san (ese Description......-.ssecseessececsenseneee saStep eewtea soreness tes CONDITIONS HEREINBEFORE REFERRED TO Contractor’s obligation: The contractor shall with due diligence and in good and workmanlike manner carry out and complete the works to the reasonable satisfaction of the S.O. all in accordance with these conditions of contract together with Architects drawings, specifications, schedules or other notes, quotations etc. attached to this Contract. Date for commencement ...............0. 0.0. :c cece cee cece eee eee ee eee @ontract epee Date for completion .......... cee cececeeee seen ceeeeeeee eens eceeeeees Liquidated damages ow. .....cesceecscseceeeseeeeneeet eee eceeeeeeees Defect Liability period .................cceceeeseeee cee eeen teen renee Payment Terms (esses 10. secec eects eens nent ee eeeeeeeneeenenenenerens Retention percentage (see 7 above) Performance oo... cece ceeecececeeeceeeeeeeeeeeveneneneneees i. Bond S.O. Instructions: The S.O. may issue written instructions which the contractor shall forthwith carry out. If instructions are given orally, they shall forthwith be confirmed in writing by the S.O. The S.O. may without invalidating the contract, order an addition to or omission from or other change in the works or in the order or period in which they are to be carried out and any such instruction shall be valued by the S.O. on a fair and reasonable basis. The $.0. shall issue instructions as to the expenditure of any provision or prime cost sums before any such work is carried out. These instructions shall be valued on a fair and reasonable basis. Instead of the valuation referred to in sub-clauses (ii) and (iii) hereof, an inclusive price may be agreed between the S.O. and the contractor prior to the contractor carrying out any instructions such as referred to in those sub-clauses. 11. Contractors Representative: The Contractor shall at all reasonable times keep on the work a competent person in charge. 12 Statutory Obligations, Fees and Charges: The contractor shall comply with all notices required by any statute, any statutory instrument, rule or order or any regulation or by law applicable to the works and shall pay all fees and charges in respect of the works legally recoverable from him. 13. Sub-Contracting: The contractor shall not sub-contract the works or any part thereof without the written consent of the S.O. which consent shall not be unreasonably withheld. The contractor shall be liable for, and shall 14. Insurance: indemnify the Employer against any expense liability loss claim or proceedings whatsoever in respect of: Personal injury to or death of any persons (s); Injury or damage to any property real or personal; as may be associated with the execution of the works. Without prejudice to his liability to indemnify the Employer, the Contractor shall maintain and shall cause any Sub-contractor to maintain Contractors All Risk, Third Party Liability and Public Liability Insurances as are necessary to cover the liability of the Contractor or Sub-Contractors. 15. Practical Completion — Defects Liability: The .S.0. pleted. 1. 16. shall certify the date when in his opinion the works have been practically com- 11. Any defects, excessive shrinkages or other faults which appear within the defects liability period and are due to materials or workmanship not in accordance with the contract shall be made good by the Contractor entirely at his own cost unless the S.O. shall otherwise instruct. 111. The S.O. shall certify the date when in his opinion the Contractor’s obligations under this clause have been discharged. Payment— Interim Payments: The S.O. shall if requested by the contractor at intervals of four weeks calculated from the date for commencement inserted in clause 2 certify interim payments to the Contractor in respect of the goods on site for the purposes of the works and any amounts either ascertained or agreed under Clause 10 and the Employer shall pay to the contractor the amount so certified within 14 days of the date of the certificate. 11. Provided the contractor shall have supplied all documentation reasonably necessary for the computation of the amount to be certified the $.0. shall 10 days after the date of practical completion certified under clause 15 (1) certify payment to the Contractor of ninety five per cent of the total amount to be paid to the contractor under the contract including any amounts ascertained or agreed under Clause 10 less only the amount of any interim payments made under sub-clause hereof and the Employer shall pay to the Contractor the amount so certified within 14 days of that certificate. 111. Provided the contractor shall have supplied all documentation reasonably necessary for the computation of the amount to be certified the $.O. shall 10 days after the date certified under Clause 15 (iii) issue a final certificate certifying the amount remaining due to the due to the Contractor or due to the Employer as the case may be and such sum shall as from the 14" day after the date of the final certificate be a debt payable as the case may be by the Employer to the Contractor or by the Contractor to the Employer. 17. Determination by Employer: The Employer may but not unreasonably or vexatiously by notice by registered post or recorded delivery to the Contractor forthwith determine the employment of the contract under this contract if the Contract shall make default in any or more of the following respects that is to say: i. If the Contractor without reasonable cause fails to proceed diligently with the works or wholly suspends the carrying out of the works before completion; ii. If the Contractor becomes bankrupt or makes any composition or arrangements with his creditors or has a winding up order made or a resolution for voluntary winding up passed or a Receiver or Manager of his business is appointed or possession taken by or on behalf of any creditor or any property the subject of a charge. Provided always that the right of determination shall be without prejudice to any other rights or remedies which the Employer may possess. 18. Determination by Contractor: The Contractor may but not unreasonably or vexatiously by notice by registered post of recorded delivery to the Employer forthwith determine the employment of the Contractor under the contract if the Employer shall make default in any one or more of the following respects that is to say: If the Employer fails to make any interim payment due in accordance with clause 7, after certification by the 8.0.; ii. If the Employer or any person for whom the Employer is responsible interferes or obstructs the carrying out of the works or fails to make the premises available for the Contractor in accordance with clause 2; If the Employer becomes bankrupt or make a composition or arrangements with his creditors. 19. Arbitration: If any dispute or differences concerning this Contract shall arise between the Employer or the S.O. on his behalf and the Contractor, such a dispute shall be settled as per the Arbitration Act. 20. Fluctuation: The fluctuations provisions of the C.L.C. Standard Form of Contracts shall be incorporated into this Contract. BUILDING AND CONSTRUCTION INDUSTRY LABOUR MANAGEMENT AGREEMENT The following attachments contain copies of the Building & Construction Industry’s Labour Management Agreement for a specific period (2021-2023). the THIS AGREEMENT (commonly known as the JIC Agreement) forms between latest in a series of agreements which commenced in 1956 and is made rs Asthe employers in the industry represented by the Incorporated Masterbuilde opersociation of Jamaica and the workers represented by the major trade unions relaorderly ating in Jamaica, with the specific intention to maintain sound and tions within the industry. This agreement contains: ° ° * Terms of wage agreement Rate of pay per 8-hour day Disciplinary guidelines LABOUR MANAGEMENT AGREEMENT 2021 — 2023 Building & Construction Industry PART Il - PERMANENT PROVISIONS THIS AGREEMENT is made the 24th day of March 2021 between the Employers’ Side of the Joint Industrial Council for the Building and Construction Industry (being representatives of the Incorporated Masterbuilders Association of Jamaica representing the employers in the building and construction industry of Jamaica who are hereinafter called the “Employers”) and the Workers Side of the said Council (being representatives of the Bustamante Industrial Trade Union, The Trade Union Congress of Jamaica and the National Workers Union of Jamaica) (hereinafter called the “Unions”) WHEREAS in the interest of sound industrial relations in the building industry the parties hereto have agreed — The following clauses of this Agreement numbered 3 to 48 shall form part of the permanent terms of employment of the workers of the building and construction industry and shall remain in force until varied by agreement between the Workers’ Side and the Employers’ Side of the Council and the expression “the Unions” used therein shall mean the recognised bargaining representatives of the workers from time to time. 3 Functions of Management The Employers have the sole right, responsibility and function to conduct their business and mange their operations in such manner as they shall think fit. Accordingly each Employer has the (1) To maintain orderly labour relations. (2) To exercise their functions as defined in this agreement with right in his sole discretion: due regard to the welfare, speedy and efficient operation of the building industry, as well as the welfare and best interest of the workers. (a) (3) To stabilise employment. rates of pay and other conditions of (4) To establish a formula for the prompt and fair disposition of grievances, and (5) To ensure that works shall proceed smoothly interruption and at the highest attainable efficiency. (b) without NOW THIS AGREEMENT WITNESSETH as follows: PART 1- RATES OF PAY AND TERMS OF WAGE AGREEMENT 1. Rates of Pay and Retroactive Date The wage rates to be paid by the Employers in the building and construction industry with effect from the 1st day of February 2021 shall be the rates set out in the Schedule hereto. 2, Terms of Wage Agreement The rates of pay and the other terms and conditions of employment established by this Agreement shall remain in force until the 31st day of January 2023. construction industry shall otherwise) to make claims for any change in the terms other claim involving any period of (c) (d) (e) (f) (g) provided in Clause 21. Claims for any changes desired after the 31st day of January 2023 shall be made before the 31st day of October to control and regulate the use of all equipment and other property of the employer; to introduce new or improved equipment, methods or facilities and to change job procedures; to establish working schedules and to make work assignments; to hire new workers; to promote, transfer, lay off and recall workers; to discipline and dismiss workers for just cause; and to retire workers; to establish new occupational classification: (h) (i) to select supervisory personnel; to have any part of his work performed by contractors or (j) to make rules and regulations which the Employer considers necessary or advisable for the orderly, efficient and safe conduct of his business. sub-contractors; The Workers in the building and not be entitled (either through a Union or for any increases in their remuneration or and conditions of their employment or any cost to the Employers in respect of the their employment up to the 31st day of January 2023 except as is 2022. to manage his business, works and construction sites; to plan, direct and control his operations and the working force including the days, times, methods and manner of working, allocation of work and number of workers required in any department or operation; to determine the work to be done; to establish the methods and rate of production and to change such methods and rate; 4, Classification of Workers Where in the Schedule hereto any type of work is divided into two or more separate classes levels or grades (Example: Level III (Grade |), Level Il (Grade II) and Level | (Grade III) Carpenter/Joiner) the determination of the worker's skill and his proper level (grade) will be made by the Employer at the commencement of the worker's employment on a job and if disputed by the worker shall be subject to the Grievance Procedure. Every effort shall be made to have a Level Three (Grade One) in each category. If there is no agreement on this the normal Grievance Procedure mentioned above shall apply. commencement of the next working day and he was not instructed before 5:00 p.m. on the previous day not to and actually reports for work at the report commencement of such next working day. Fair Wages Clause for Task Workers All Employers who are carrying out work on a task basis must advise and ensure that their sub-contractors and task workers keep proper books, make statutory deductions, payments and pay rates of wages and observe conditions of employment not less favourable than those laid down by this Agreement. In the case of day workers, the sub-contractors must observe the daily rates and also the various fringe benefits such as paid holidays, vacation leave, 5. overtime, premiums, end of project bonus, etc. In the case of work carried out by task and paid for on a measurement basis, the rates should be sufficient to allow workers to earn not less than the daily rate plus benefits. The Unions holding bargaining rights shall be supplied with the names and addresses of the sub-contractors on any project on request. Workers employed directly by a sub-contractor shall have the right to union representation provide that they work under the terms and conditions of this agreement. Those contractors who employ sub-contractors be minded ctors should be registered sub-contractors who will sub-contra that the If a worker is requested to and does remain at the work site, (b) available to work, after the first four hours of a day, he will be paid a full day's pay. 9. Overtime Except in the case of watchmen, overtime is defined as time (a) worked in excess of 8 hours per day Mondays to Fridays inclusive and all work on Saturdays and Sundays. Mondays to Fridays (b) Saturdays (c) 6. Functions of Union The Unions have the right to exercise all the functions of a (a) trade union subject to the provisions of this Agreement and will exercise such functions in accordance with trade union principles and practices. Accordingly the Unions have the right: (ii) (iii) Sundays All work on Sundays will be paid for at double time, except (e) in the case of watchmen. A watchman will be paid at the rate of double time for work done on his scheduled rest day. to ensure that the agreed wage rates are paid and that the other benefits and conditions herein specified are observed. To protect the workers against arbitrary disciplinary action through the Grievance Procedure. To deal with grievances. 10. 11. Public Holidays worked All workers (except Watchmen) who work on official Public Holidays on the instructions of their Employer will be paid at double time on an hourly basis for all work on such holidays. Watchmen will be paid an additional $557.62 for each Public Holiday worked by them. This is not in addition to the premium under Clause 10. consent of the Employer. Union delegates shall be regular workers on the job on (c) represent the workers. Reasonable time off with pay will they which be granted to authorised delegates to attend meetings with management about labour disputes arising in their Employer's business at their respective places of employment provided that permission to attend to such business shall be obtained by each delegate from his supervisor and shall be subject to the exigencies of the Employer's work. 12. Height Pay Height Pay shall be payable if all the following conditions exist: The worker is working at more than 30 feet above ground or (a) floor level in such circumstances that there is the danger of a clear fall of at least 30 feet, and The worker is not protected by any wall, rail or other barrier (b) (temporary or permanent), except in the case of work on scaffolds. The rate of Height Pay for each full hour (over threequarters of an hour shall be regarded as a full hour) of work at a height, measured from the point at which the work is being done to the nearest floor or to the ground shall be — $6.07 per hour between 30 feet and 60 feet Normal Hours The normal work week will be 40 hours consisting of 5 days (Monday to Friday) of 8 hours each, except in the case of watchmen. 8. Reporting Pay A worker will be paid a minimum (a) although he is not taken on, if either: (i) Public Holidays not worked Each worker who has worked for the same Employer on both the normal working day prior to and on the normal working day following each Public Holiday will be paid the normal single time pay which the worker would have earned had the day not been a Holiday. Except when dealing with a grievance under the provisions (b) of Clause 29 or attending a meeting with management, union activities shall not be conducted on any Employer's premises without the prior he All work on Saturdays will be paid for at double time, expect in the case of watchmen. A watchman will be paid at the rate of double time for work done on his scheduled rest day. The workers will work, if possible, reasonable overtime (d) whenever requested by an Employer so to do. abide by the Joint Industrial Council (JIC). (i) Overtime shall be paid at time and a half. of half a day’s pay for each additional 30 feet he is specifically instructed to report for work and actually reports for work at the time he is instructed to report or he is working on a job in the ordinary course of which he would be expected to report for work at the 2 $7.39 per hour 20% of their single time rate for such work, including Saturdays, Sundays and Public Holidays. This premium shall not rank for overtime pay for Public Holidays (whether worked or not), sick leave or in the calculation of any other premium or fringe benefit. 18. Leader’s Rate Any worker who is designated by the Employer as a charge hand or leading hand and who is placed in charge of a working crew 13. Depth Pay Workers who work in excavations in which the shortest horizontal measurement is less than the depth of the excavation shall, where the depth where the worker is working exceeds seven feet, be paid a premium called “Depth pay” at the following rates. between 7 and 10 feet between 11 and 16 feet or gang, and who also performs work in his regular job classification, shall during that time be paid a ‘leader's rate” of $29.58 an hour, in addition to his regular rate of pay. Craftsmen or tradesmen working with helpers or assistants are not a crew or gang for this purpose. $5.68 per hour $5.68 per hour 19. and an additional $4.66 in respect of each additional 6 feet or part thereof entitlement shall be one day for every 20 normal working days worked by him but not more than 18 days in respect of each year. for each hour (over three-quarters of an hour shall be regarded as a full hour) during which they work at such depth. 14. Holidays with Pay (Vacation) (a) Every worker will be granted holidays with pay in accordance with The Holidays with Pay order 1973 except that the (b) Each worker who has been permanently employed with the same Employer for between five (5) and ten (10) years will be granted one additional normal working week's holiday with pay. A worker's employment with a particular Employer shall not be considered to be continuous unless such worker has actually worked for such Employer for at least 200 days in each calendar year (Januaryto December). Working in Water Pay Workers who are physically working in either: (a) permanent water with a static water level (e.g. the sea or swamp) of up to 3 feet in depth, or (b) temporary flood water for more than one hour, (c) Each same employer working week's Employer shall shall be paid a premium called “Water Pay” at the rate of $8.54 an hour for the duration of the contract for each full hour (over threequarters of an hour shall be regarded as a full hour) during which they are physically working in such water. This premium for working in permanent water with a static water level of over 3 feet in depth shall be negotiated having regard to the circumstances in each case. worker who has been permanently employed with the for over ten (10) years will be granted four (4) normal holiday pay. A worker's employment with a particular not be considered to be continuous unless such worker has actually worked for such Employer for at least 200 days in each calendar year (January to December). 20. (a) Sick Leave Pay Sick Leave with pay will be granted in accordance with the Holidays with Pay Order 1973 except that the entitlement shall be one day for every twenty (20) normal working days worked by the worker but not more than twelve (12) days in respect of each year. 15. Over Water Pay Workers shall be paid a premium called “Over Water Pay” of $7.12 an hour for the duration of the contract for each full hour (over three-quarters of an hour shall be regarded as a full hour) during which they are actually working over water which is more than 4 feet deep from the static water level provided this shall not apply to work done on or from a permanent fixed platform. This premium shall not (b) Any unused portion of sick leave not claimed for during the year shall be paid to the worker. rank for overtime pay for Public Holidays (whether worked or not), vacation leave, sick leave or in calculation of any other premium or fringe benefits. A worker shall not be entitled to this premium as well 21. New Job Classification An Employer may require the establishment of new and different job Classifications other than those listed in the Schedule hereto PROVIDED HOWEVER that no such new and different job classifications shall be put into effect by an Employer unless and until that Incorporated Masterbuilders Association gives notice in writing to as Height Pay and/or Working in Water Pay but shall be entitled to whichever is highest. 16. Subsistence And Travelling Allowance A worker who is normally employed by an Employer in or around the town or city where he ordinarily lives and who is requested by the Employer to go to and work at some other place at such a the Joint Industrial Council of the proposed new and different job distance that the worker cannot reasonably return home each night classification and of the proposed rate or rates to be made applicable thereto but if no objection in writing is made to the proposal by the Unions within fourteen days of the giving of such notice they shall be treated as effective at the expiration of the said period of fourteen days. If however the Unions tender an objection to such proposals both sides of the Joint Industrial Council agree to discuss the same. In any discussions between the Unions and the Employers on such proposals, they will act in good faith in considering them and the rate or rates to be applied to any such new and different job classifications shall be set by reference to and in the most proper relationship to other rates paid for comparable jobs. will be provided with accommodation by the employer or in lieu of the accommodation be reimbursed a subsistence and travelling allowance of $5,500 per night. There will be an additional 10% on subsistence for the following areas: the North Coast from Monetgo Bay to Ocho Rios, Negril, Mandeville, Ewarton, Nain, Port Antonio and Port Maria. 17. Night Premium Workers who are required by their Employers to work between 6:00 p.m. and 6:00 a.m. (except Watchmen) and are not entitled to overtime pay for such work, will be paid a night premium of 3 Redundancy payments shall be granted in accordance with and subject to all the conditions set out in The Employment (Termination and Redundancy Payments) Act and all Regulations and Orders made thereunder expecting that the computation thereof shall 22. Seniority In matters relating to promotion, demotion, transfer, lay off, termination of employment and rehiring the following principles shall be on the following basis: govern:- (a) It is the responsibility of the Employer to maintain the highest level of efficiency; therefore the Employers must be the ones to judge the requirements of any job and of the ability of any worker or candidate for employment to fulfil the requirements of any job. In exercising this judgement, skill, competence, efficiency and merit of the workers or candidates shall govern. intended to Less than one year One year through 5 years None 2 weeks’ pay plus 2 weeks’ pay for each year of service over one year. 10 weeks’ pay plus 3 weeks’ pay for each year of service over 5 years. 10 years through 15 years 25 weeks’ pay plus 4 weeks’ pay for each year of service over 10 years. 45 weeks’ pay plus 5 weeks’ pay for each year of service over 15 years. 70 weeks’ pay plus 7 weeks’ pay for each year of service over 20 years. 15 years through 20 years investigation through the Grievance Procedure. Construction Employment Premium The provisions of this clause are Redundancy Payment 5 years through 10 years Where, in the judgement of the Employer, two or more (b) workers or candidates are equally suitable in all respects for promotion or retention, the worker with the longest continuous service with the Employer shall be given preference. If a worker has good reason to believe that he has not been (c) given fair consideration, he or she may present his or her case for 23. Number of Years of Continuous Service Over 20 years more effectively secure that work within the Industry proceeds smoothly without interruption and at the highest attainable efficiency. Accordingly the workers within the Industry and the Unions undertake to use their best endeavours to ensure that there will be no strikes, slow down or other interference with work on any project. Employment in the construction industry is by nature temporary which invariably results in workers being unable to qualify for Redundancy payments, even after many years employment. In light of this the JIC Labour Management Agreement had since 1975 included a provision of 15% which was subsequently increased in 1989 to 16% paid on basic single time rate of the total hours worked. This was to be paid at the end of the worker's employment and was entitled End of Project Bonus. This method of compensation will be discontinued henceforth. The payment previously known as End of Project Bonus will be replaced by the Construction Employment Premium which will be 16% paid on and included in the basic single time rate of the total hours worked. For the avoidance of doubt the Construction Employment Premium will be added to and paid with the basic single time rate and will be subject to the following conditions: (a) The unions agree to co-operate in maintaining a high standard of productivity and in controlling absenteeism. The Construction Employment Premium shall be paid to (b) each worker including task workers with their regular payments. (c) Any dispute regarding the amount or payment or non-payment of any Construction Employment Premium shall be submitted to the Grievance Procedure. (d) The Construction Employment overtime. 24, Premium is not payable on 25. No Strikes No Lockouts There shall be no strikes, slowdowns or other work stoppages or interference with work or production and the Unions agree that they will not authorise, sanction, approve, instigate or assist any of the same. An Employer will not lock out his workers. 26. J.L.C. Constitution This Agreement shall be read conjointly the it. Duties of Delegates & Unions in Unauthorised Strike If any strike, which is contrary to the provisions of the preceding clauses, shall occur all Union delegates, stewards and other representatives amongst the workers and the officers of the Union shall in good faith use their best endeavours at all times during such strikes to persuade all workers to resume normal work. 27. Equipment to be Maintained During Strike The Unions agree that if an Employer so requests sufficient workers will continue to work during any strike as are needed to maintain and protect property and equipment from damage or deterioration and the Unions agree to direct and authorise sufficient workers so to do. 28. 29. Grievance Procedure All complaints, grievances and disputes concerning (a) alleged violation of or non-compliance with this Agreement concerning the conditions of employment of the workers (but including any desired or proposed changes in this Agreement nor demands for increase of pay or otherwise involving cost to employers) shall be submitted to the following procedure: Redundancy Payments with Constitution of the Joint Industrial Council and in no way supersedes any or not any the FIRST STEP: A worker may present his grievance or complaint to his Supervisor within not more than three working days after the alleged incident or incidents which gave rise to the same or discovery shall, with effect from 1s‘ April 1978 be paid wage rates ten percentum higher than the rates set out in the Schedule hereto: (b) For the purpose of this clause “Special Projects” are: of the grievance PROVIDED that grievances arising out of discharged’) and dismissals shall be initiated in the Second Step. The aggrieved High rise buildings of more than 6 floors (including the ground floor) worker may be accompanied by or present his grievance through his Union delegate if he so desires. If the disposition of the complaint, grievance or dispute by the Supervisor in this First Step is not satisfactory then the matter may be taken up under the next Step. (ii) (iv) SECOND STEP: In case the disposition under the First Step is not satisfactory, the worker involved may present his complaint, grievance then, THIRD STEP: The written grievance may be referred by either the Employer or the Union to the Council within not more than fourteen working days after the disposition under the Second Step. dams. (vi) Embassies 32. Premium Industries (a) The owners of certain industries (known colloquially as “Premium Industries”) have agreed with one or more Unions that they will stipulate with any contractors engaged by them to do certain construction work that they should pay specific rates of pay and accord particular fringe benefits which are higher than those agreed by the Joint Industrial Council. Nothing in this Agreement is intended to prevent any Contractor from paying any specific rates and according particular fringe benefits which may be so stipulated. (b) FOURTH STEP: _ If no solution is reached in the Council either side shall have the right to require within not more than fourteen working days of the termination of the negotiations in the Council that the matter be placed before a suitable independent and mutually agreed Industrial buildings or plant within the plant compounds of one of the alumina or bauxite companies. (ii) Cement factories (iii) Oil refineries (iv) Electricity generating stations for Jamaica Public Service arbitrator whose decision shall be final and binding on all parties. The a disposition is not made in this time the grievance may be carried forward into the next Step. (c) Any grievance which is not taken up or pursued within the time limits mentioned above shall be regarded as having been abandoned. 30. Dismissals lf an Employer shall dismiss a worker and the justification of the dismissal shall have been arbitrated and the arbitrator shall have found that the dismissal was not justified and the Union shall have demanded compensation and/or reinstatement for such worker and no agreement thereon with the Employer shall have been reached and such dispute has been negotiated at the Ministry of Labour under the Chairmanship of one of the Conciliation Officers of the Ministry and no agreement shall have been reached then and only in these circumstances, the Unions, the Employer and the workers shall be relieved from Clause 25 hereof and the workers shall be free to strike and the employer to lock out in respect of such dispute. 31, (a) Special Projects Workers engaged in the construction of Special Projects The following have been recognised as Premium Industries: (i) terms of reference to be placed before the arbitrator shall be mutually agreed. (b) At each step, the Employer's representative will consider and give the dispositions provided for under this Grievance Procedure within five working days after the presentation of such grievance and if dredging The construction of shipping ports, fishery terminals, wharves and warehouses at ports throughout Jamaica. (v) Highways and bridges associated with major highways, and or dispute to the site manager or site engineer on which he is working within five working days after the disposition of the same by the Supervisor or in the case of a discharge or dismissal within seven working days of the discharge or dismissal. The aggrieved worker may be accompanied by and present his grievance through his Union delegate or a representative of the Union who is not one of the regular workers of the Employer if the Union so wishes. If the disposition of the grievance by the manager in this Second Step is not satisfactory, Hotels with 130 rooms or more (iii) Reclamation of land from the sea, rivers or swamps by Co. Lid. (c) The Council agrees that the construction of the following facilities. Airports and Airdromes Naval Installations Nuclear Stations Military Camps and Installations Dry Docks shall be regarded as premium undertakings and accordingly rates of pay and fringe benefits which are higher than those agreed by the Joint industrial Council shall be applied thereto. This provision shall however only apply to contracts covering such installations or facilities. 33. Voluntary Check-Off The Employer shall make deductions for union dues for any of the Unions who are signatories to this Agreement and which has been recognised by the Employer as the sole bargaining agent for the workers on any particular building site, from the wages of the workers who authorise the Employer to do so in writing in such form as the Employer may from time to time approve and will pay over the same to such Union once per month. The Unions undertake that no interference or coercion will be exercised against any worker to give any such authority and that any such authority may be revoked at any time by any worker by notice in writing to the Employer. Government Training Programme The rates of pay, premiums and other fringes under this Agreement shall not apply to workers employed or engaged under or in connection with the Human Employment and Resource Training Programme or under the provisions of any other statue or Governmental policy promoting the education and/or employment of people in Jamaica. 34. 35. Insurance Each worker will be provided with insurance coverage in (a) accordance with the Standard Form of Building Contract which requires that the Employers and the Contractor take out appropriate Employers Liability Insurance for coverage against personal injuries or death arising out of or caused by the carrying out of their duties on the site and also in accordance with the terms and conditions of the oh Pipe Work This premium laying and jointing drain in trenches. This does other premium or fringe (3) (4) (5) (6) (7) (8) (9) (10) Drain Pipe Work 38. Lay Off Notice Two weeks’ Notice verbal or writing or payment in lieu of notice shall be given for layoffs of a permanent nature, to workers who have completed four weeks of continuous or unbroken service. 39. Laundry Allowance The basic wage now includes a laundry allowance as was agreed in the Labour Management Agreement for 2001-2003. 40. Uniform Allowance Uniforms shall be provided for regular workers who are employed for more than one year and who: Back brace First aid kit Fire extinguisher Proper ladder/scaffolding Sanitary facilities Potable water Safety helmets Hard boots/water boots Respirators Gloves (11) Eye protection (12) Ear protection 42. Identification Cards Each worker shall have and carry a National Identification Card on the job site. Where and when identification is required for constant display the employer shall provide an appropriate carrying case. 43. applies only to workers who are physically or sewer pipes of 30 ins. in diameter or over, not rank for overtime or in calculation of any benefits: $11.39 per hour for duration of agreement $11.39 per hour for duration of (b) Sewer Pipe Work agreement is to be paid to workers who rate normal the ‘An additional 40% above line. asbestos or lines sewer work in active (a) are truck drivers are heavy duty operators (1) (2) 36. $850.02 per day in the second year are asphalt workers (c) (d) Provision of Safety Gears Each worker will be provided with the relevant item of safety equipment from the following list when it is deemed by the Employer to be appropriate to the particular task that the worker is required to carry out. Each worker shall be covered on and off the job under a (b) insurance policy for $832,500.00 with provision for double Life Group indemnity in the case of accidental death provided that the worker has been employed for at least three (3) months by the same Employer. $809.54 per day in the first year form part of the garage staff (b) 41. insurance policy. Overtime Meal Allowance Workers who have been requested to work overtime after the normal working pericd shall be provided with a cooked meal or in lieu of the cooked meal, be reimbursed a Meal Allowance subject to the qualifying period of two hours’ work after normal working time as follows: (a) Heat Premium The following workers shall be entitled to a Heat Premium of: $23.76 per hour for year 1, and $27.23 per hour for year 2 when required to work with hot asphalt: Asphalt Distributor Operator, Bituminous Paving machine Operator, Bituminous machine Screed Operator, Bituminous mixing Plant Operator, Labourer (Asphalt Bituminous) and Luteman (Asphalt Bituminous), Drivers and sidemen on trucks transporting asphaltic concrete hot mix. Workers who are required to work with fibreglass are also entitled to this premium. 44. System Builders A special premium of 5% above the rates of the Joint Industrial Council shall be paid to workers employed in pre-cast or insitu System Building operations but excludes those workers involved in the infrastructure works. 45. site Health & Safety Committee A Health & Safety Committee shall be established on each by the Employer nominating two workers and the Unions nominating two workers and from this number a Chairman shall be per hour appointed. If there is no Union representative the Employer shall appoint persons to carry out the relevant duties. 46. Trainee Operators There shall be a total training allowance of $227.62 per hour 47, Training of Union Delegates It is agreed that all Delegates are to be trained within the shortest possible time. 48, Flexi-Time It is agreed fo look at the maiter of flexi-time. 49. Safety Manual for the Building & Construction Industry Signed for: Workers Side: Signed for: on behalf of B.L.TU on i” The Safety Manual for the Bullding and Construction Industry, and its requirements, now forms part of the requirement for the Labour Management Agreement as of February 1, 2010. Each worker is to be provided with a copy of the Safety Manual and shall sign acknowledging receipt of same. 50. Stakeholders Meeting That there shall be a stakeholders (Union/Management) meeting after the commencement of work on projects, undertaken by members of the JIC involving main contractors and sub-contractors for any project exceeding six months and employing over 50 workers. This meeting should be held within 30 days upon commencement of the project. THE SCHEDULE ANNEXED behalf of N.W.U. on behalf of T.U.C Witness: Ae Dated this 29% day of March 2021 HOURLY RATES OF PAY 40 Hours Rates (1 Feb. 2021 to 34 Jan. 2022 42.2021 to 34.1.2022 (+5%) Effective 1.2.2021 to 31.1.2022 (+5%) 3 to 25 tons to 26-39 tons to 40-75 tons 76-125 tons , Power Plant & Air Track Screeder & Finisher to 24 tons tons -80 tons & tons Cars, pickups, Jeeps, Trucks up to 10 tons 41-20 tons 20-39 ton 40 tons & over to 1- to 30 1-40 1-50 20 tons tons tons tons End Loaders: to 10 tons (910-930) 4-21 tons (950-960) 32 tons (966) tons using and ll Breaker, rock and Effective 1.2.2021 to 31.1.2022 (+5%) 1 1 Electricians Weekend Overtime Rates Overtime Rates (Single 992.48 1,035.77 75.65, 23 1,061.10 15 4,061.10 714.79 1,323.31 1,381.02 4 53 31 1,414.81 192.20 414.81 05 797.53 7 40 20 923.24 691.10 701.34 627.49 652.82 668.68 38 1,116.53 1,172.36 1 : 921.46 935.08 836.65 870.43 891.58 14 17 982.32 924.23 4.60 4,025.87 1 47 1,367.83 4,440.29 1,508.02 956.40 HOURLY RATES OF PAY (1 Feb. 2021 to 31 Jan. 2022) 40 Hours Rates (Single) Weekday Effective 1.2.2021 to 31.1.2022 (+5%) Categories Maintenance Man (Field Service Minor Repairs) Mason Mixer Operator up to 21/44 over 21/14 Painter Pilling Hand/Hammerman Piling Winch Operator Pipe Layer Plant Mechanic Light Vehicles - pickups, cars, jeep, mixer Level 1 (Grade 3) | Level 2 (Grade2) | = 500.00 500.00 ¥ 465.06 597.84 536.09 490.19 521.81 551.41 539.41 656.49 599.80 = - compressor Heavy Duty Power Trowel Operator 462.51 606,55 : Plumber 477.48 Pump attendant Roller Operator (Hand Vibrating self propelling, Asphalt Bituminous) Roller (vibratory smooth/rubber tyres) Rubber-tired tractor operator with attachments Sand Blaster Scaffolder Sheeter Sheet Metal Worker Sideman Steel Erector! Rigger Steel Fixer/Bender Stresser Tiler Trailer Attendant Trench Machine Operator Welder Winchman 654.49 607.32 = = 672.37 = 646.56 = 646.56 = = 601.37 = = = = 599.39 781,40 622.20 671.51 874.28 - 598.07 784.33 - 566.52 675.61 617.44 Level 2 (Grade 2) Level 3 (Grade 1) Level 1 (Grade 3) 846.32 785.34 = : 869.44 = 862.08 = = 862,08 = 801.83} 773.07 693.23 = 633.86 674.75 713.03 697.51 848.91 775.60 - 775.07 1,010.43 | 804,56 - 868.34 1,130.54 |] - 732.57 873.64 - 797.43 | 1,045.77 823.25 - 1,033.43 | 1,347.25 | 1,072.75 976.76 |_ - 1,157.78 1,507.37 1,164.85 - = 867.00 = : 561.14 560.09 - = - 725.62 724.25 - - 967.49 965.67 = = - 476.97 510.56 = - = - 616.77 660.21 - - 822.37 880.28 = 518.02 - 574.05 700.86 - 564.14 549.29 509.99 - = 602.07 = 631.45 - 561.00 646.56 + - 669.86 742.30 906.29 729.49 710.29 659.47 778.53 - 816.54 - 748.01 862.08 - - 893.14 1,208.38 972.85 947.06 879.29 1,088.71 989.72 1,038.05 = - 556.51 433.84 623.76 532.48 687.51 642.93 719.63 561.00 806.59 688.55 889.02 831.37 959.51 748.01 1,075.45 | 918.06 547.73 456.60 - 550.28 630.65 456.60 659.78 587.89 433.84 645.67 725.36 674.77 - 708.27 590.43 - 714.57 815.50 590.43 853.17 760.21 561.00 834.92 937.97 872.56 - 944.36 787.24 - 948.76 | _ 1,113.22 1,087.34 787.24 1,137.56 | 1,250.63 1,013.61 | 1,163.40 748.01 - applicable only to the construction site operations because of the peculiar nature of this particular Work in excess of 15 hours per shift for other industries or business. industry and is not to be regarded as a precedent will attract overtime. 1" year - $24,319.71 per week; Overtime @ $349.43/hr. per week; Overtime @ $377.38/hr. ** New Rates to be paid not later than Pay week commencing April 5, 2021. Outstanding payments to be made as early as possible but not later than pay week commencing May 3, 2021. fons > 1,128.44 * = 1,047.12 = 1,159.26 650.25 N.B. The Council agrees that the 15 hour shift is The agreed rate is the hourly rate. All other rates are calculated from the hourly rates. The new base rates are inclusive of 16% Construction Employment Premium. Payment for special and premium projects will be calculated on basic rate minus 16% Construction Employment Premium. When only two rate are shown for a category, it means that there is no level (grades) in that category for which no level (grade) is shown. In case of work carried out by task and paid for on a measurement basis, the new task rate should reflect the new wage rates set out in the above schedule, by adjusting the labour rate content of the task rate by the percentage increase for the same category of work. 6. 1,030.76 924.30 | 845.15 899.67 950.71 | 930.01 1,131.88 1,034.14 | = exceeding 15 hours per shifts (including Saturdays and Sundays) 5. Level 3 (Grade 1) - Watchman - per week of6 shifts not 2" year - $26,265.29 Level 2 (Grade 2) 502.86 : 500.01 - Steel bending/cutting machine operator Level 1 (Grade 3) Effective 1.2.2018 to 31.1.2019 (+5%) - 433.84 ‘Self-propelied Scraper Operator Level 3 (Grade 1) = - Weekend Overtime Rates Overtime Rates Effective 1.2.2021 to 31.1.2022 (+5%) It was agreed that the Incorporated Masterbuilders Association of Jamaica would advise their Members that the Unions should have access to all projects undertaken by them. ts Note that in keeping with the HEART 8. Therefore Grade 1 will now be Level 3, Grade 2 - Level 2 and Grade 3 - Level 1. As per Jamaican Law all workers have the right to join a Trade Union of their choice. Trust/NTA Certification of workers, grades have now been changed to Levels. 1,185.37 1,108.50 9. be allowed access to the work site upon the twas agreed that the Unions whose signatures are affix to this agrrement presentation of a signature I.D. HOURLY RATES OF PAY (1 Feb. 2022 to 31 Jan. 2023 Wee 40 Hours Rates Effective 1.2.2022 to 31.1.2023 (+8%) 1 558.48 , Power Plant & Air Track Screeder & Finisher to 24 tons tons 4-80 tons tons & Cars, up to 11-20 20-39 40 pickups, Jeeps, Trucks 10 tons tons ton over 1- 1,429.17 4,491.5 4 645.01 1,145.99 68 1,145.99 771,97 498.81 886.23 746.80 886.23 99 666.10 699. 734.37 771.09 577.21 585.7 52. 545.24 to 25 tons to 26-39 tons to 40-75 tans 76-125 tons 41,071.88 1,118.63 945.70 731.34 Screed Effective 1.2.2022 to 31.1.2023 (+8%) Level 3 Effective 1.2.2022 to 31.1.2023 (+8%) Level 3 4 Level 1 Level 2 828.92 865.07 Distributor Electricians Weekend Overtime Rates Overtime Rates 764.14 802.41 842.53 884.67 706.85 861.34 904.39 949.61 09 46.39 757.41 677.69 705.05 i . i. 722.18 615.32 578.94 795.68 748.62 813: 856.81 902.19 62 .09 052.57 107.94 166.63 -50 774.68 4,403.42 1,477 0 1 1,628. 4,032.91 43 ‘7.60 16 29.1 731.47 785.68 .60 974.89 1,047.58 1,126.13 AS 1 961.32 1,189.64 é 1,121.99 to -30 -40 1-50 2 20 tons tons tons tons End Loaders: to 10 tons (910-930) 4-21 tons (950-960) 32 tons (966) tons Labourer other Paving Breaker, rock and tools 4 1,317.47 1,383.46 1,452. HOURLY RATES OF PAY (1 Feb. 2022 to 31 Jan. 2023) Categories Maintenance Man (Field Service Minor Repairs) Mason 40 Hours Rates (Single) Weekday Overtime Rates Weekend Overtime Rates Effective 1.2.2022 to 31.1.2023 (+8%) Effective 1.2.2022 to 31.1.2023 (+8%) Effective 1.2.2022 to 31.1.2023 (+8%) Level 1 (Grade3) | Level 2 (Grade2) | : 614.92 514.29 Mixer Operator up to 21/14 over 24/14 - Painter Pilling Hand/Hammerman Piling Winch Operator Pipe Layer Plant Mechanic Light Vehicles - pickups, cars, jeep, mixer compressor Heavy Duty Power Trowel Operator Plumber Pump attendant Roller Operator (Hand Vibrating self propelling, Asphalt Bituminous) Roller (vibratory smooth/rubber tyres) Rubber-tired tractor operator with attachments Sand Blaster Scatfolder Self-propelled Scraper Operator Sheeter Sheet Metal Worker Sideman Steel bending/cutting machine operator Steel Erector/ Rigger Steel Fixer/Bender Stresser Tiler Trailer Attendant ‘Trench Machine Operator Welder Winchman 673.19 504.19 536.71 - Level 1 (Grade 3) 665.03 - Level 2 (Grade 2) Level 3 (Grade 1) 795.16 - 713.03 870.50 651.97 694.03 : - Level 1 (Grade 3) : 886.71 - 514.29 567.17 624.67 663.03 733.41 807.77 886.71 478.35 - 554.82 675.25 616.94 - 691.58 - 618.55 - 717.44 873.16 797.76 = 894.28 - 824.74 | - - - - - - 475.72 623.88 - 616.51 803.73 639.97 690.69 899.26 = 615.16 806.74 - 797.22 1,039.30 | 827.55 491.13 = 582.71 517.23 694.97 = 635.08 - 753.50 668.83 446.24 514.29 572.41 446.24 563.38 = 469.64 = Watchman - per week of 6 shifts not exceeding 15 hours per shifts (including Saturdays and Sundays) Work in excess of 15 hours per shift will attract overtime. 1 year - $24,319.71 per week; Overtime @ $349.43/hr. 2"° year - $26,265.29 551.41 Level 3 (Grade 1) per week; Overtime @ $377.38/hr. 577.18 576.09 490.60 525.15 532.82 720.89 580.25 564.99 524.56 649.50 641.58 547.69 566.00 648.67 469.64 678.63 604.69 446.24 : 590.45 : 619.27 707.16 661.30 664.12 746.09 694.05 - : 577.03 : 665.04 : 740.19 577.03 728.51 = 607,30 ~ - 893.15 1,162.84 |] 898.60 - 746.35 744.95 634.40 679.08 689.00 932.18 750.33 730.59 678.31 839.86 829.63 708.22 731.90 838.80 607.30 877.54 781.93 763.50 : 800.78 : 914.42 855.12 858.77 964.77 897.49 577.03 N.B. The Council agrees that the 15 hour shift is applicable only to the construction site operations because of the peculiar nature of this particular industry and is not to be regarded as a precedent for other industries or business. - - Level 2 (Grade 2) Level 3 (Grade 1) 1,060.21 - 950.71 1,160.68 = 869.29 925.37 = - 977.87 | 1,077.04 956.59 1,164.22 1,063.68 | - = 1,192.38 - - - 820.21 1,075.65 - 1,062.95 1,385.74 | 1,103.40 |_1,190.86 1,550.44 - 846.77 - 1,004.66 | 891.77 1,198.13 - 769.38 : 886.71 : 986.92 | 769.38 971.35 Ss 809.73 - 995.13 993.26 845.86 905.43 918.66 1,242.91 1,000.44 974.12 904.44 1,119.82 1,106.18 944.29 975.87 1,118.40 809.73 1,170.06 1,042.57 769.38 - | | | | | | | 1,018.00 : 1,067.71 1,219.24 1,140.18 1,145.02 = = 1,286.36 1,196.64 = JOINT INDUSTRIAL COUNCIL DISCIPLINARY GUIDELINES Type of Offences A, Fighting on the job Removal of Company's property off compound 2,‘ [without permission Insubordination - Failure to carry out job related 4st Scheduled Offences 2nd Scheduled Offences 3rd Scheduled Offences 4th Scheduled Offences 2 Weeks Suspension _| Dismissal Dismissal Dismissal 3. instruction by a Supervisor 1 Week Suspension 2 Week Suspension 4, month period} Warming 2 Days Suspension 5. permission Waming 4 Days Suspension. Warming 2 Weeks Suspension Dismissal Warming 2 Weeks Suspension Dismissal 4 Days Suspension 2 Weeks Suspension _| Disrnissal Lateness beyond 15 minutes (4 times over a 7 Absent from work area/department without Sleeping on the job Being under the influence of alcohol on the job Being under the influence of hard drugs (crack, " — Ieocaine, heroin} 6. iE Ja Early quitting from work area or Department 8. ‘Absent from work for 3.consecutive days without reasonable excuse 2. Operating company vehicle/equipment without _|permission 10. 40a, | Operating company vehicle outside designated area __|Dismissal |Warming 2 Week Suspension 1 Week Suspension 42. _ |Falsification of Report Dismissal 13. jemployee 2 Weeks Suspension |Witfully causing damage to Company property Failure to report damage to Company property 15. |within 24 hours w 2 Weeks Suspension Waming 44a. 2Weeks Suspension _| Dismissal Dismissal {Unauthorised absenteeism from work 14, _ |Negligently causing damage to Company property _|Dismissal Dismissal Warning 41. Punching Time Card or signing Register for another 2 Weeks suspension Warning Dismissal 2 Weeks Suspension _| Dismissal _|Dismissal 2 Week Suspension Dismissal Dismissal 2 Weeks Suspension _|Dismissai Warning 5 Days Suspension Failure to observe companies health, safety and environmental (HSE) rules, basic safety rules indicated in the JIC Safety Manual for the Building 46 ' land Construction Industry and the health safety and environmental requirements of the facility within which they are employed l N.B. Nothing in these Guidelines shall supersede either Contractua any Conditions or a Company's or Company's Rule, nevertheless, if by disciplinary action not in keeping with these guidelines is taken n of any member of the Incorporated Masterbuiiders Associatio Jamaica the Unions reserve the right to pursue this as a grievance. Signed for:- Employers Side: These disciplinary guidelines cannot take precedent over the HSE rules of the facilities within which the worker is employed. Alf warnings are to be in writing. spelt out in The Grievance Procedure shal! be applied for offences not this document. is not repeated ifan offence is committed by @ worker and this offence his record. within a two year period, the offence will be removed from Dated this 29°" day of March, 2021 Witness:...77- Dismissal Signed for:- Workers Side: SUGGESTED FOR SUBCONTRACT RATES OR JOB WORK Over the years the Incorporated Masterbuilders Association of Jamaica, have been bombarded with requests for guidelines for sub contractor’s or job work rates. In an attempt to partially satisfy these requests, this manual include the following suggested rates as a guide for several sub contractors or job work activities. (These rates are labour only). The rates are listed in a number of skilled trade disciplines for construction works undertaken in Kingston, St. Andrew and St. Catherine. They were compiled through collaboration with various members of the Masterbuilders Association, along with professional Quantity Surveyors and would only be valid for the current JIC period (2021-2023). Again, these rates are suggested as only a guide, as factors such as special condi- tions and locations outside those stated will require adjustments. INDEX FOR JOB WORK RATE PAGES 1. Excavation.....:.. seuneneacaueneaeensnsense seusnunneese 1-7 2. Steelwork....cseeceeres anaeeseesaesnnnannoeseensesaes &-9 3s MaSONPYersseccscnseneeseaeneeeneseeneeneneens cia 10-19 4, Carpentry..ccccscccssesescnnsecnseennseeenenneeneneeee wi 20 - 24 5. JOINGLY..sccncs0ee aan gteteeeeuadenneneeenesnnssens 25 - 29 6. Painting. ...ccnsssecsssscececnens paentesnsacednencnneneans 30 - 32 7. Plumbing.....:: sesunesns seunananeenenusneensnaesens evans 33 - 36 8. Scaffolding.....::::: pusucucunneneessocgescnuneeeneeoon 37-38 9. Tiling. ..ccccsseneesessensonscenenseese epee strane 39 - 40 10. Welding...........0: su nenneesenseneeneanenseeeessennaas 41 - 46 41. Electrical......c.ssssssssscses: ieanENinaw anne sunuenenneee 47 - 49 Excavation SCHEDULE OF TASK WORK RATES PERIOD [ 12.202 1 To | | J.I.C. Direct Labor Rates 2 Grade No of Men 1 0 2 o 3 0 J.C, Hr/Each Daily /Total Direct Labor Rates Labourer 2 2 457.0276284. 7,312.44 BASE RATE:- 3 $ 7,312.44 J.C, Fringe Benefits Sick Leave 1.00 Public Holidays Not Worked 1.00 Holiday with Pay Vacation 1.00 Production Incentive 15.00 18 $1,316.24 Leaders Rate 6% of 6.00 - Total Team Rate:NOTES: $ 98,628.68 - 41 Construction Employment Premium 16 %is {Now included in Base Hourly Rate } 2 Far job rates, tatal team rate is divided by production 3 Job Work Total Rates include the construction employment premium and no further payment will be made at the End of the Project. Tday f ace ance of tht 5 works if a0 sorrected done by the initial contracted Sub-Labourer/ Contractor -1- providing sue remedial works were Excavation General suggested Job Work Rates Published _as a quide for the Indus Included in the calculation are:- Sick Leave, Holiday with Pay, { Not Worked ),Leaders Rate, and Production Incentive Public holidays to be added based on project condition & location. Refer to Clauses of the J.C Contract far Additional “age payment NO. [EXCAVATION _ CONCRETE AND GANGER Note: 4) Unload and Pack Means Into Stores or Proper Place |Excavation in Compacted Earth to 5' Deep |Excavation in Asphaltic Concrete (Barber Green) |Excavation in compacted marl up to 5' deep |Excavation in compacted sand up to to 5' deep |Excavation in stiff clay up to 5' deep |Excavation in stiff clay between 5’ & 10‘ deep [Excavation in Rock or concretre (no compressor) Excavation in Rack or concrete (with compressor) 4 2 3 4 5 6 7 8 9 10 |incl. Labourers Excavation in Rock or concretre (with compressor) |Labourers only Backfill renches/foundations Excavations, with excavated Sand Excavation in concrete slab up to 8" Thick with out 11_|compressor 12 73 |Excavate for kerb foundations (12" x 12") |Excavate shallow trenches (18" & 12") < 12" deep |Excavate between 5' & 10' deep in compacted earth Eacavate between 10' & 15' deep in compacted 15 jearth 16 |Eacavate in uncompacted Sand 17 |Excavate in uncompacted earth 48 |Excavate in uncompacted marl 49 |Demolish 4" Block walls with all cores filled 20 [Demolish 6" Block wall with all_cores filled 21 [Demolish 8" Block walls with all cores filled 22 |Load barford and spread for filling (Earth/Marl) Load Barford for dump (all types of soild sand 44 23 24 25 26 27 |debris) [Load barford and spread for filling (sand) |Load barford with debris (board, ply, steel, block) [Load wheel barrow and remove to dump (2FC) |Load wheel barrow and remove to dump Load wheel barrow and spread for filling (earth or Matric Total Imperial Total Rate UNIT Rate UNIT Yd.Cu. Y¥d.Cu. Yd.Cu. Yd.Cu. Yd.Cu. Y¥d.Cu. Y¥d.Cu. 4079 2465 1438 863. 1233 1438 8629 m3. m3 m3. m3 m3 m3 m3 1411 3225 1881 1129 1612 1881 11286 Yd.Cu. 5393 m3 7054 Yd.Cu. 2157 m3. 2822 Yd.Cu. 173 m3 226 Yd.Cu. 4314 m3. 5643 Ft.Run Ft.Run 72 96 m m 236. 315 Yd.Cu. 1370 m3 1791 Yd.Cu. Y¥d.Cu. ¥d.Cu. Yd.Cu. Yd.Sq. Yd.Sq. Yd.Sq. Y¥d.Cu. 41659 539 616 863 434 616 863 360 m3 m3 m3 m3 m2 m2 m2 m3 2170 705 806 4129 516 737 1032 470 Y¥d.Cu. Yd.Cu. Load Load Yd.Cu. 176 288 173 29 288 m3 m3 Load Load m3 230 376 173 29 376 Yd.Cu. 454 m3 594 Yd.Cu. 360 m3 470 ¥d.Cu. No. No. No. Yd.Cu. 216 270 270 192 3595, m3 No. No. No. m3, 282 270 270 192 3595 Yd.Cu. 4109 m3 4109 36 |SF) Man. Yd.Cu. 4794 m3 4794 37 |RF) Man. Yd.Cu. 5393 m3 5393, |Columns and Beam Yd.Cu, 3196 m3 3196 39 |slab Pour only and vibrate Carmix Concrete to Yd.Cu. 2332 m3 2332 |Foundations Yd.Cu. 1726 m3 2257 40 28 |marl) 29 |Load wheel barrow and spread for filling (sand) 30 31 32 33 34 |Earth/mari [Dig post holes (1.25' x_2') deep |Plant post including bracing in proper position |Mix and pour concrete in post holes [Mix pour vibrate concrete in foundations man. Mix pour vibrate concrete in walls and stiffeners (GF+ |FF) Man. Mix pour vibrate concrete in walls and stiffeners (FF- 35 Backfill trenches/foundations. Exctns. With exctd. Mix pour vibrate concrete in walls and stiffeners (SFHandle Mat. Pour Carmix Concrete and vibrate to 38 Handle Mat. Pour Carmix Concrete and Vibrate to aha Excavation General suggested Job Work Rates Published as a quide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays { Not Worked ),Leaders Rate, and Production Incentive Refer to Clauses of the J.1.C Contract for Additional ‘age payment to be added based on project condition NO.|EXCAVATION CONCRETE AND GANGER Note: 1) Unload and Pack Means Into Stores or Proper & location. Imperial Metric Total Total UNIT Rate UNIT Rate Yd.Cu. 2465 m3 3225 Yd.Cu. Yd.Cu. Yd.Cu. Y¥d.Sq. 1728 508 332 114 m3 m3 m3 m2 2257 664 434 132 Yd.Sq. FtSq. Ft.Sa. Each Each Each Each Yd.Cu. Yd.Sq. 100 Sq.Ft. Load Trucks (5 Yd. Cu. - 10 Yd.Cu.) By hand with 56 |marl, earth, sand, etc. 1233 192 375 91 261 508 863 332 63 288 m2 m2 m2 Each Each Each Each m3 m2 m2 1474 2064 4038 91 261 508 863 434 82 34 Load 1726 Load 1726 57 Load 3319 Load 3319 Load 4794 Load 4794 Place 41 |Pour Only and vibrate_Carmix Concrete to Columns Pour Only and Vibrate Carmix Concret to beams 42 |and slabs 43 |Handle Sand Gravel at Mixer for Concrete Mant. 44 |Ram earth or marl manually including wetting 45 |Grade and ram bottom of trench /To sort and dry pack stones to absorption. Pit walls 46 |(12" x 18") Thick 47 |Cut Concrete surfaces (ups to 1") Thick 48 |Cut Concrete surfaces (1.25" to 3") Thick 49 |Cut down trees (up to 12” girth) 50 |Cut down trees (13" to 24" girth) 51 [Cut down trees (25" to 36" girth) 52 |Cut down trees (37" to 48" girth) 53 |Spread top soil (6" - 12" Thick) 54 |Spread top soil (less than 6" Thick) 55 |Grade sub-base to receive top soil Load Trucks (11 Yd. Cu. - 16 Yd.Cu.) by Hand with 58 59 60 61 62 63 |Marl, earth, sand ,etc. Load Trucks (17 Yd.Cu, |Marl, earth sand, etc. Mix pour vibrate concrete |Man. Mix pour vibrate concrete _[Man. Mix pour vibrate concrete |Man. Mix pour vibrate concrete |Fls.Man. Mix pour vibrate concrete 22 Yd.Cu.) By hand with in isolated beams (FF) Yd.Cu. 4314 m3 5643 Y¥d.Cu. in isolated beams (SF) 5076 m3 6639 Yd.Cu. S752 m3 7524 Yd.Cu. 4314 m3. 5643 Yd.Cu. 5076 m3 6639 Y¥d.Cu. 5752 m3 7524 in isloated beams (RF) in beams and slabs all in Ground Floor slabs (ins. |Bdgs.) Man. 65 Mix pour vibrate concrete in Ground Floor slabs |(Quts.Bdgs.) Man Mix pour vibrate concrete in beam,column, wall with |crane Yd.Cu. 4013 m3 5249, 66 |Mix pour vibrate concrete in foundations with crane Y¥d.Cu. 3656 m3 4782 67 |Mix pour vibrate concrete in beams,slabs with crane Y¥d.Cu. Handle Mat. Pour Carmix Concrete and vibrate to |Columns and Beam 3256 m3 4259 68 Yd.Cu. 3196 m3 4180 64 69 70 71 72 73 74 Handle Mat. Pour Carmix Concrete and |Col. and Beam-Crane Handle Mat. Pour Carmix Concrete and |slab Handle Mat. Pour Carmix Concrete and |slab - Crane Pour only and vibrate Carmix Concrete |Foundations Vibrate to Yd.Cu. 2465 m3. 3225 Yd.Cu. 2332 m3 3050 Y¥d.Cu. 1675 m3 2192 Yd.Cu. 1685 m3 2204 Y¥d.Cu. 2538 m3 3320 Yd.Cu. 1876 m3 2454 Vibrate to Vibrate to to |Pour Only and vibrate Carmix Concrete to Columns Pour Only and Vibrate Carmix Concrete to beams |and slabs eG Excavation Industry General suggested Job Work Rates Published_as a quide for the Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays{ Not Worked ),Leaders Rate, and Production Incentive to be added based on project condition & location. Refer to Clauses of the J.1.C Contract for Additional age payment Metric Imperial NO. [EXCAVATION Note: CONCRETE AND GANGER UNIT Total Rate UNIT Total Rate 4) Unload and Pack Means Into Stores or Proper 75 76 77 78 79 80 81 82 83 84 85 86 Place Pour Only and Vibrate Carmix Concrete to |Foundations - Crane Pour Only & Vibrate Carmix Concrete to Column & |Beams-Crane Pour Only and Vibrate Carmix Concrete to slabs |with Crane |Handle Sand Gravel at Mixer for Concrete Man. |Handle sand gravel at mixer for blockwork man. |Handle sand gravel at mixer for rendering mani. [Make pre-cast slab (18" x 18" x 2") [Make pre-cast slab (24" x 24" x 2") [Make pre-cast kerbs (3"x 10") |Ram earth or marl manually including wetting |Grade and ram bottom of trench [Grade and ram fill to receive concrete Lay and Fit 24" Diameter Culvert pipe using 87 |backhoe/Loader Lay and fit 18" Diameter Culvert pipe using 89 90 91 92 |backhoe/Loader To sort and dryfill stones in soakaway pits and |trenches |Cut Concrete surfaces (ups to 1") Thick [Cut Concrete surfaces (1.25" to 3") Thick [Cut concrete surfaces (3.25” to 6" ) Thick 93 |Cut off porjecting 88 rebar (3/8" & 1/2") using hacksaw 94 |Cut off projecting rebar (9/8" & 3/4") using hacksaw 95 [Cut off projecting rebar (1") using hacksaw 96 |Cut off projecting rebar (3/8" x 1/2") using torch 97 |Cut off projecting rebar (5/8" x 3/4") using torch ‘98 |Cut off projecting rebar (1") using torch 99 [Bush and clean (Grass, weeds, shrubs) site 100/Cut down trees (up to 12" girth) 101|Cut down trees (13" to 24" girth) 102|Cut down trees (25" to 36" girth) 103|Cut down trees (37" to 48" girth) 104] Cut down trees (48" to 60" girth) 105|Cut down trees (61" to 72" girth) Cut up trees (Bole/branch) and dump (up to 12" 106} girth) Cut up trees (bole/branch) and dump (13 to 24" 107 |girth) Cut up trees (bole/branch) and dump (25" to 36" 108|girth) Cut up trees (bole/branch) and dump (37" to 48" 409| girth) Cut up 110|girth) Cut up 114 |girth) 112|Cut up 113|Cut up trees (bolefbranch) and dump (49" to 60" Yd.Cu. 1166 m3 1525 Yd.Cu. 2026 m3 2649 Y¥d.Cu. Yd.Cu. Y¥d.Cu. Y¥d.Cu. Each Each Each Yd.Cu. Y¥d.Sq. Yd.Sq. 1338, 539 29 12 78 123 180 345 114 gt m3 m3 m3 m3 Each Each Each m3 m2 m2 1750 705 38 16 78 123 180 451 132 109 Ft.Run. 114 m 373 Ft.Run 88 m 289 Yd.Cu. Ft.Sq. Ft.Sq. Ft.Sq. 1321 188 375 719 m3 m2 m2 m2 1728 2019 4038 7740 Each 35. Each 35 44 52 27 38 45 247 91 270 508 863. 1233 Each Each Each Each Each m2 Each Each Each Each Each 44 52 27 38 45 27 91 270 508 863. 1233, Each Each Each Each Each 100 Ft.Sq. Each Each Each Each Each Each 1726 Each 1726 Ft.Run 8 m 25 Ft.Run 27 m 87 Ft.Run 52 m 172 FtRun 90 m 295 Ft.Run 131 m 429 Ft.Run FtRun Ft.Run 180 90 173 m m m 590 295 566 trees (bole/branch) and dump (61" to 72" and get_out tree root (up to 24" girth) and get out tree root (25" to 48" girth) Excavation General suggested Job Work Rates Published_as a quide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays ( Not Worked ),Leaders Rate, and Production Incentive Refer to Clauses of the J.1.C Contract for Additional %age payment to be added based on project condition 120 | Off load cement from truck and pack in storeroom 121|Unload and pack lumber 1" x 2", 1" x 4"x 2" x 2" Unload and pack lumber: 137|Long 142]24") Metric UNIT Total Rate UNIT Total Rate Ft.Run Yd.Cu. Y¥d.Sq. 100 Ft.Sq. 288 332 63 288 m m3 m2 m2 944 434 75 3 Each 35, Each 35 Each 35 Each 35 Bag Length 23 6 Bag Length 23 6 Length 1 Length 14 Length Length Length Bundle Ft.Sq. Ft.Sq. 19 22 29 8 66 72 Length Length Length Bundle m2 m2 18 22 29 8 714 774 Each Box Each Each 166 ii 19 19 Each Box Each Each 166 11 19 19 Length 8 Length 8 Length 11 Length 1 Length Length 22 29 Length Length 22 29 Length "1 Length 1 1"x 6", 1"x 8", 2" x 3", 3" 122|x 4" Unload and pack lumber: 1" x 10", 1" x 12" 2" x 6", 123]3" x 3", 3" x4" 124|Unload & pack lumber: 2" x 8", 2" x 10", 4" x 4" 125|Unload & pack lumber: 2" x 12" 3" x 8", 4"x 6" 126|Unload and pack shingles 127| Unload and pack formwork in building 128|Remove Fromwork from building pack and load Unload & pack or unpack and load shed panels (8' x 129]5") 130] Unload and Pack wire nailes (50 Lb. Boxes) 131| Unload and pack props. In building 132|Remove from building pack and load props Unload & Pack PVC Pipes 1/2" - 1 1/2" Dia. 20° 133}Long Unload and Pack PVC pipes 2" -3" Diameter 20" 134}Long Unload and Pack PVC Pipes 4" -6" Diameter 20° 135|Long 136|Unload & Pack PVC Pipes 8" - 12" Dia. 20' Long Unload & Pack Steel Pipes 1/2"- 1 1/2" Dia. 20' Unload 138|Long Unload 139|Long 140|Unload Unload 141|24') Unload location. Imperial NO. [EXCAVATION CONCRETE AND GANGER Note: 1) Unload and Pack Means Into Stores or Proper Place 114|Cut up and get out tree root (49" to 72" girth) 115|Spread top soil (6" - 12" Thick) 116}|Spread top soil (less than 6" Thick) 117|Grade sub-base to receive tap soil Unload and pack in stores plywood and gypsum 118/sheets Take from stores and load plywood and gypsum 119|sheets & and Pack Steel Pipes 2" - 3" Diameter 20° Length 22 Length 22 Length Length 33 8 Length Length 33 8 Length 14 Length ch Length 22 Length 22 Length 33 Length 33 Length 41 Length 41 Length 1 Length aa Length 22 Length 22 Length 33 Length 33 & Pack Steel Pipes 4" - 6" Diameter 20' and Pack Scaffolding Pipes 20' Long & Pack Metal RHS. Up to 1 1/2"x1 1/2" (20'and Pack Metal RHS 2” x 2" to 3" x 3" (20'- Unload and Pack Metal RHS 4" x 4" to 5" x 5" (20'- 143|24") Unload and Pack Metal RHS 6" x 6" to 8" x 8" (20'- 144]24') Unload & Pack flats, Ls, Chs. (Up to 3" Girth) 20° 145|Long Unload & Pack Flats, Ls,Chs (3.5" to 6" Girth) 20° 146|Long Unload & Pack Flats, Ls,Chs (6.5" to 9" Girth) 20° 147|Long Excavation General suggested Job Work Rates Published as a guide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, { Not Worked ).Leaders Rate, and Production Incentive Public holidays payment to be added based on project condition & Refer to Clauses of the J.|.C Contract for Additional %age Unload and Pack Means Into Stores or Proper & Pack Flats, Ls,Chs (9.5" to 12" Girth) 20° Metal Plates 8" x4" Up to 1 and Metal Plates 8' x 4°, 5/16" to 1/2” & Metal Plates 8' x 4', 9/16" metal and 8x 5" 13/16" to x 17' to 8' x 20'- rucks Material 1 Material material material ¥ etc. sand, etc. etc. (7 and small to 3/4" 1" Thick location. Excavation General suggested Job Work Rates Published _as a quide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays { Not Worked ),Leaders Rate, and Production Incentive Refer to Clausas of the J.I.C Contract for Additional %age payment to be added based on project condition & RETE 190 1) Unload and Pack Means Into Stores or Place |Unioad and Pack Louvre Doors when 193 [Dum 6" 494 4" |Dum location. Steelwork SCHEDULE OF TASK WORK RATES PERIOD 1.22022 J.C. Direct Labor Rates Steel Fixer /Bender 1 J.LC. Grade No of Men Hr/Each 4 2 3 1 2 1 694.37 575.07 468,56 Daily /Total 5,554.96 9,201.19 3,748.44 Direct Labor Rates Labourer 0.00 0 2 BASE J.LC. Fringe Benefits Sick Leave Public Holidays Not Worked Holiday with Pay Vacation Production Incentive 3 RATE:- $ 18,504.59 1.00 1.00 1.00 15.00 48.00 18.00% of 6.00 Leaders Rate 6% of $ 3,330.83 3 333.30 $ 22,168.71 NOTES: 1 Construction Employment Premium 16% is (Now included in Base Hourly Rate For job rates, total team rate is divided by production will be Job Work Total Rates include the construction employment premium and no further payment made at the End of the Project. works, (if any } corrected , providing such. igitecial works were t Sub-Labouter! Contractor the inthe event the initial Sub- Labourer/ Contractor, abandon the works.or is terminated ~8- Steelwork Refer to Clauses of the J.1.C Contract for Additional %age payment to be added based on project condition & location. IMPERIAL Nos. METRIC Total UNIT Rate Total UNIT Rate it 3/8" Mild Stee! Rebar Lb. 2 3 4 23 1/2" Mild Steel Rebar 5/8" Mild Steel Rebar 3/4" Mild Steel Rebar Kg. 50 Lb. Lb. Lb. 23 23 23 Kg. Kg. Kg. 50 50 50 Lb. 23 Kg. 50 Yd.Sq. Doz. 94 $28 m2 Doz. 208 528 5 6 7 1" Mild Steel Rebar Fabric 1/4" Stirrups 8 3/8" Stirrups Doz. 554 9 3/8" Stirrups (Large > 6' Girth) Doz. 554 Doz. 693 Doz. 693 Doz. 792 Doz. 792 Doz. 924 Doz. 924 Doz. Doz. Doz. Doz. Doz. 426 482 715 462 683 Doz. Doz. Doz. Doz. Doz. 426 482 715 462 693 10 1/2" Stirrups 11 1/2" Stirrups (Large > 7' Girth) 12 13 14 15 16 1/4" 3/8" 1/2" 3/8" 1/2" 17 3/8" High Tensile Steel Rebar Lb. 25 Kg. 56 18 1/2" High Tensile steel Rebar Lb. 19 5/8" High Tensile Steel Rebar 25 Kg. 56 Lb. 25 Kg. 20 3/4" High Tensile stee! Rebar 56 Lb. 21 25 1" High Tensile Steel Rebar Kg. 56 Lb. 25 Kg. 56 Links Links Links Chairs Chairs Masonry SCHEDULE OF TASK WORK RATES PERIOD 4 3 |i 1.22022 | | | J.C. Direct Labor Rates Masonry 2 No of Men HrJEach 4 4 706.85 5,654.78 2 2 578.98 9,263.79 3 0 0.00 0.00 J.C. Direct Labor Rates Labourer 457.03, 3 2 BASE 3. Daily [Total Grade J.LC. 10,968.66 25,887.23 RATE:- Fringe Benefits Sick Public Holidays Not Worked Holiday with Pay Vacation Production Incentive 1.00 % 1.00 % 1.00 % 15.00 % 18.00 % 4,659.70 25,887.23 18.00% of 5,654.78 Leaders Rate 6% of 6.00 % 339.29 30,886.22 NOTES: 4 2 3 Construction Employment Premium 16% is For job rates, total team rate (Now included in Base Hourly Rate is divided by production no further Job Work Total Rates include the construction employment premium and payment will be made at the End of the Project. ted Sub-Labourer! Contra: tor abandon the works.or is t ~10—- Masonry General suggested Job Work Rates Published as a quide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays{ Not Worked ),Leaders Rate, and Production Incentive Refer to Clauses of the J.C Contract for Additional “age payment to he added based on project condition & location. MASONRY Nos. IMPERIAL Total Rate UNIT UNIT METRIC Total Rate |Notes. 1) Add Extra Arris Rate for Beams with More Than 2 Arris 2) For Electric. Manholes use 70% of Sewer Manhole Rates Lay 8" Blocks & Fill all Pockets (Ground Floor 1 |to First Floor) Lay 8" Blocks & Fill all Pockets (Ground Floor Y¥d.Sq. 1,103 m2 1,319 2 |& Above) Yd.Sq. 1,287 m2 1,539 Yd.Sq. 1,471 m2 1,759 Y¥d.Sq. 936 m2 4,119 |Floor & Above) Lay 6" Blocks & Fill All Pockets (Ground Y¥d.Sq. 1,065 m2 1,274 6 [Floor to First Floor) Yd.Sq. 965 m2 1,154 7 Lay 6" Blocks & Fill All Pockets ( First Floor |&Above) Yd.Sq. 1,103 m2 1,319 Y¥d.Sq. 1,287 m2 1,539 Yd.Sq. 835 m2 998 Y¥d.Sq. 965 m2 1,154 Yd.Sq. 882 m2 1,055 ¥d.Sq. 965 m2 1,154 Yd.Sq. 1,188 m2 1,424 Yd.Sq. 772 m2 923 ¥d.Sq. 858 m2 1,026 Lay 8" Blocks & Fill All Pockets (Manholes, 3 |Drains) Lay 8" Blocks & Fill 4 |(Ground Floor Alternate Pockets to First Floor) Lay 8" Blocks & Fill Alternate Pockets (First 5 Lay 6" Blocks & Fill All Pockets( Manholes, 8 9 10 11. 12 13 14 15 |Drains, and Gully Basins) Lay 6" Blocks & Fill Alternative |(Ground Floor to First Floor) Lay 6" Blocks & Fill Alternative |Floor & Above) Lay 4" Blocks & Fill All Pockets |Floor to First Floor) Lay 4" Blocks & Fill All Pockets |Above) Lay 4" Blocks & Fill All Pockets |Drains, Gully Basins) Lay 4" Blocks & Fill Alternative |(Ground Floor to First Floor) Lay 4" Blocks & Fill Alternative |Floor & Above) Pockets Pockets (First (Ground (First Floor & (Manholes, Pockets Pockets (First Lay 6" x 6" Breather Blocks & Rake Joints 16 |(All Floors) Lay 9" x 9" Breather Blocks & Rake Joints Yd.Sq. 3,089 m2 3,694 17 |(All Floors) Lay 12" x 12" Breather Blocks & Rake Joints Yd.Sq. 2,059 m2 2,463 Yd.Sa. 1,817 m2 2,173 18 |(All Floors) Lay 6" High Concrete Louvres and Rake 19 |Joints (18" x 36") Fill Alternate Pockets One Course High U/S 20 |Belts 8" W 21 22 23 24 Fill Alternate Pockets One Course High U/S |Belts 6" W |Hack Concrete Surfaces for Rendering |Paint Bondcrete to Concrete Surfaces Cut Stone Face Lay Point Joints as Extra |Over Wall Each 222 222 Ft.Run 61 M 199 Ft.Run Yd.Sq. Yd.Sq. 45 315 94 M m2 m2 149 377 113 Yd.Sq. 9,640 m2 11,529 Yd.Sq. 12,576 m2 15,041 13,087 m2 15,653 Cut Stone Face Lay Point Joints as facing on 25 |Wall 4"Thick Cut Stone Face Lay Point Joints as facing on 26 |Bank 6" Thick Yd.Sq. a Masonry for the Industry General suggested Job Work Rates Published as a guide Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays ( Not Worked ),Leaders Rate, and Production Incentive be added based on project condition & location. Refer to Clauses of the J.I.C Contract for Additional “age payment fo Add Extra Arris Rate for Beams with More 2 Arris For Electric. Manholes use 70% of Sewer Rates 6" Thick Stone Face and Build Mortar Wi Arrisses to Stone W: Arrisses and . And 6" from stones 6" Thick eep > 12" Pipes Weep Holes Stonewalls < 12" only(Up to1 to 1" Walls Cast only Drains, For For Basins Cast 4" Thick) Thick only all T only For T only m = 8" Girth Girth A Girth (Ditto only [= |F [F IF ) For Beams " Girth Cast only ms 1" Thick) Cast 2" Grith Cast only (Ditto 1" [= l= 8" Grith " Grith Cast only alalzl= l= Grith only (Ditto 1" 36" Grith to iT to Walls Walls 3|3 NI’ to Finish to Manholes, Basins S/S/S|S]/= to to1 to Beams to Beams to i fm Masonry General suggested Job Work Rates Published as a quide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays { Not Worked ),Leaders Rate, and Production Incentive Refer to Clauses of the J.1.C Contract for Additional “age payment to be added based on project condition & IMPERIAL Total MASONRY Nos. focation. |Notes 1) Add Extra Arris Rate for Beams UNIT Rate METRIC Total UNIT Rate with More Than 2 Arris 2) 58 For Electric. Manholes use 70% of Sewer Manhole Rates |Granite Only to Beams (2R) 36" Girth Rough Cast (Up to 1" Thick) and Granite |Walls FtRun 363 M 1,192 Yd.Sq. 882 m2 1,055 [Walls Rough (Cast Up to 1” Thick) and Tyrolean [Walls Rough (Cast Up to 1" Thick) and Stee! Finish Y¥d.Sq. 882 m2 1,055 Yd.Sq. 1,065 m2 1,274 62 |Walls Yd.Sq. 4,188 m2 4,424 63 Rough Cast (Ditto 1" Thick) and Steel Finish |M/H, Drains & G/Basins ¥d.Sq. 1,716 m2 2,052 ¥d.Sq. 950 m2 1,137 Ft.Run 401 M 1,316 Ft.Run 461 M 1,513 Ft.Run 533 M 4,747 Ft.Run $83 M 1,912 Ft.Run 216 M 709 Ft.Run 281 M 921 Ft.Run 336 M 1,107 Ft.Run 363 M 1,206 Ft.Run 435, M 1,427 59 Rough (Cast Up to 1" Thick) and Pebble 60 61 Rough Cast (Ditto 1" Thick) and Granite 64 65 66 67 |Ceilings Rough Cast |Beams (2R) Rough Cast |Beams (2R) Rough Cast |Beams (2R) 30" Girth Rough Cast 68 |Beams (2R) Rough Cast 69 [columns (1R Rough Cast 70 {columns (1R Rough Cast 71 (Ditto 1" Thick) and Granite 18" Girth (Ditto 1" Thick) and Granite 24" Girth (Ditto 1" Thick) and Granite (Ditto 1" Thick) 36" Girth (Ditto 1" Thick) 12" Girth) (Ditto 1" Thick) 18" Girth) (Ditto 1" Thick) and Granite and Granite and Granite and Granite |columns (1R 24" Girth) Rough Cast (Ditto 1" Thick) and Granite 72 |columns (2R 18" Girth) Rough Cast (Ditto 1" Thick) and 73 [columns (2R 24" Girth) Rough Cast (Ditto 1" Thick) and 74 |columns (2R 30" Girth) Rough Cast (Ditto 1" Thick) and 75 |columns (2R 36" Girth) 76 |Arrises 77 + |Curved Arrisses 78 |Fairface Walls 79 | Fairface Ceilings 80 |One Coat Render to Walls and 81 82 83 84 85 Granite Granite Ceilings |Dress Water Drip Formed in Soffit of Slab Form and Dress Water Drip into Rendering |of Slab Soffit Set screeds to Floors/Roofs using Mortar Pin Out and Dress Plumbing/Electrical Pipe |Through Walls (1/2" - 1") Pin Out Plumbing/Electrics (1/2" - 1") |Chasings (Rough Ft.Run 490 M 1,609 Ft.Run Ft.Run Ft.Run Yd.Sq. Y¥d.Sq. Yd.Sq. 542 92 144 289 368 468 M M M m2 m2 m2 41,778 303 471 345 440 560 Ft.Run 144 M 471 Ft.Run Yd.Sq. 172 131 M m2 563 157 Each AB Ft.Run 48 M 158 FtRun 66 M 216 FtRun 86 M 281 Granite Walls) Each 48 Pin Out Plumbing/Electrics (1 1/4" - 2") 86 |Chasings (Rough Walls) Pin Out Plumbing/Electrics (3"-4") Chasings 87. |(Rough Walis) —13— Masonry General suggested Job Work Rates Published as a guide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays ( Not Worked ),Leaders Rate, and Production Incentive to be added based on project condition & location. Refer to Clauses of the J.|.C Contract for Additional ‘nage payment IMPERIAL UNIT MASONRY Nos. Total Rate METRIC UNIT Total Rate [Notes 1) Add Extra Arris Rate for Beams with More Than 2 Arris 2) For Electric. Manholes use 70% of Sewer Manhole Rates Rod-Off Floor Slabs to Receive Tiles or Yd.Sq. Yd.Sq. Yd.Sq. 119 406 406 m2 m2 m2 142 486 486 |Rod-Off and Steel Float Floor Slabs Manually Rod-Off and Steel Float Floor Slabs Yd.Sq. 606 m2 724 92 |Mechanically ¥d.Sq. 289 m2 345 93 |Woodfloat Floor Slabs or Broom Finish Slabs Yd.Sq. 286 m2 342 94 Screed and Dress Tread (10 - 12") Wide |Wood Float Including Redge Ft.Run 249 M 817 Ft.Run 372 M 4,221 Ft.Run 172 M 563 Ft.Run Ft.Run FtRun 257 91 52 M M M 844 298 172 Ft.Run 213 M 699 Yd.Cu. 686 m3 2,252 88 89 g0 |Screeds |Rod-Off and Broom Finish Floor Slabs |Rod-Off and Wood Finish Floor Slabs 91 ‘Screed and Dress Tread (10 - 12") Wide 95 96 97 98 99 100 101 102 103 404 105 106 407 |Steel Float Screed and |Float Finish Screed and |Float |Mark Floor [Mark Floor Including Redge Dress Riser (6"-8") Wide Wood Incl. Redge Dress Riser (6" -8" ) Wide Steel Slabs with Metal Tool Slabs with Cotton Cord [Lay Haunch and Point Kerbs Provide Labour Pour and Settle Pre-mix |Concrete Trap G/Basins From 4" Blocks Complete 15" |W. x15" Lg.x 15" Internal Dia Trap G/Basins From 4" Blocks Complete 18” |W. x 18" Lg. x18" Internal Dia. Sewer M/H From 6" Blocks Complete |W.x18" Lg.x 18" Internal Dia. Sewer WH From 6” Blocks Complete |x18" Lg. x 24" Internal Dia. Sewer M/H From 6" Blocks Complete |x 24" Lg.x 24" Internal Dia. Sewer M/H From 6” Blocks Complete |x 24" Lg.x 30" Internal Dia. Each 5,828 Each 7,722 Each 7,722 Each 8,825 Each 8,825, Each 10,295 Each 10,295 Each 12,555 Each 12,555 Each 14,638 Each 14,638 Each 13,697 Each 13,697 Each 14,921 Each 14,921 Each 17,352 Each 17,352 Each 16,003 Each 16,003. 18" W 24" W 24" W Sewer W/H From 6" Blocks Complete 24" W |x 36" Lg.x 24" Internal Dia. 5,828 18" 4108 |x 30" Lg.x 24" Internal Dia. Sewer MH From 6" Blocks Complete 30" W 105 |x 34" Lg.x 30" Internal Dia. ‘Sewer M/H From 6" Blocks Complete 30" W 406 |x 30" Lg.x 30" Internal Dia. Sewer MH From 6" Blocks Complete 30" W 107 Each Masonry General suggested Job Work Rates Published Included in the calculation are: as a quide for the Industry Sick Leave, Holiday with Pay, Public holidays ( Net Worked ),Leaders Rate, and Production Incentive Refer to Clauses of the J.1.C Contract for Additional %age payment to be added based on project condition & location. IMPERIAL Total Rate MASONRY Nos. |Notes UNIT UNIT METRIC Total Rate 41) Add Extra Arris Rate for Beams with More 108 109 110 111 112 113 114 115 116 117 118 119 420 121 122 123 124 125 426 Than 2 Aris 2) For Electric. Manholes use 70% of Sewer Manhole Rates Sewer M/H From 6" Blocks Complete 36" W |x 36" Lg.x 24" Internal Dia. Rough Cast (Up to 1" Thick) and Spanish |Wave Walls Rough Cast (Ditto 1" Thick) and Steel Finish |M/H, Drains and G/Basins Rough Cast (Ditto 1" Thick) and Granite 2R |Jamb/Wall Top Rough Cast (Ditto 1" Thick) and Granite 1R |Jamb Rough |Curved Rough |Curbed Rough |Beams Rough |Beams Rough |Beams Rough |Beams Rough |Beams Rough Cast (Ditto 1" Thick) Jamb/Wall Top Cast (Dito 1" Thick) Jamb Cast (Ditto 1" Thick) (2R) 18" Girth Cast (Ditto 1" Thick) (2R) 24" Girth Cast (Ditto 1" Thick) (2R) 30" Girth Cast (Ditto 1" Thick) (2R) 36” Girth Cast (Ditto 1" Thick) (2R) 42" Girth Cast (Ditto 1" Thick) Cast (2R) Cast (2R) Cast Cast (2R) Cast (1R) Cast Each 17,255 Yd.Sq. 996 m2 1,192 Yd.Sq. 4,716 m2 2,052 FtRun 269 M 884 Ft.Run 159 M 522 Ft.Run 401 M 1,316 Ft.Run 243 M 798 Ft.Run 396 M 1,299 Ft.Run 461 M 1,513 Ft.Run 533 M 1,747 Ft.Run 583 M 1,912 Ft.Run 630 M 2,068 Ft.Run 686 M 2,252 Ft.Run 772 M 2,533 Ft.Run 882 M 2,895 Ft.Run 965 M 3,167 Ft.Run 1,065 M 3,494 Ft.Run 229 M 7541 FtRun 300 M 984 Ft.Run 368 M 1,206 Ft.Run 444 M 1,448 Ft.Run 218 M 714 FtRun 278 M 913 and Granite 1R and Granite and Granite and Granite and Granite and Granite and Granite (Ditto 1" Thick) and Granite 60" Girth (Ditto 1" Thick) and Granite 72” Girth (Ditto 1" Thick) and Granite |Beams (2R) 84" Girth Rough |Beams Rough |Beams Rough 17,255 and Granite 2R |Beams (2R) 48" Girth Rough |Beams Rough |Beams Rough Each (Ditto 1" Thick) and Granite 96" Girth (Ditto 1" Thick) and Granite 12" Girth (Ditto 1" Thick) and Granite |Beams (1R) 18" Girth Rough Cast (Ditto 1" Thick) and Granite 127 |Beams (1R) 24" Girth Rough Cast (Ditto 1" Thick) and Granite 128 30" Girth (Ditto 1" Thick) and Granite 12" Girth) (Ditto 1° Thick) and Granite 18" Girth) |Beams (1R) Rough Cast 4129 |columns (1R Rough Cast 130 |columns (1R ~15— Masonry General suggested Job Work Rates Published as a guide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays ( Not Worked ),Leaders Rate, and Production Incentive to be added based on project condition & location. Refer to Clauses of the J.1.C Contrast for Additional “age payment IMPERIAL MASONRY Nos. 431 432 433 134 435 136 |Notes 1) Add Extra Arris Rate for Beams Than 2 Arris 2) For Electric. Manholes use 70% Manhole Rates Rough Cast (Ditto 1" Thick) and |columns (1R 24” Girth) Rough Cast (Ditto 1" Thick) and |columns (2R 18" Girth) Rough Cast (Ditto 1" Thick) and |columns (2R 24" Girth) Rough Cast (Ditto 1" Thick) and |columns (2R 30" Girth) Rough Cast (Ditto 1" Thick) and |columns (2R 36" Girth) Rough Cast (Ditto 1" Thick) and Total Rate UNIT METRIC UNIT Total Rate with More of Sewer Granite Ft.Run 336 M 1,101 Ft.Run 368 M 1,206 Ft.Run 435 M 1,427 FtRun 490 M 1,609 FtLRun 542 M 1,778 FtRun 623 M 1,718 Granite Granite Granite Granite Granite |columns (3R 24" Girth) Rough Cast (Ditto 1" Thick) and Granite 437 |columns (3R 30" Girth) Ft.Run 583. M 1,912 438 Rough Cast (Ditto 1" Thick) and Granite |columns (3R 36" Girth) Ft.Run 630 M. 2,068 Ft.Run 686 M 2,252 Ft.Run 735 M 2,413 Ft.Run 718 M 2,357 FtRun 835 M 2,739 FtRun 936 M 3,071 Rough Cast (Ditto 1” Thick) and Granite 439 440 441 442 |columns (3R Rough Cast |columns (3R Rough Cast |columns (4R Rough Cast 42" Girth) (Ditto 1" Thick) and Granite 48" Girth) (Ditto 1" Thick) and Granite 36” Girth) (Ditto 1" Thick) and Granite |columns (4R 48” Girth) Rough Cast (Ditto 1" Thick) and Granite 443 |columns (4R 60" Girth) Rough Cast (Ditto 1" Thick) and Granite 144 |columns (4R 72" Girth) FtLRun 1,030 M 3,378 445 Rough Cast (Ditto 1" Thick) and Granite |columns (4R 84" Girth) Rough Cast (Ditto 1" Thick) and Granite Ft.Run 1,144 M 3,753 146 |columns (4R 96" Girth) Ft.Run 4,235 M 4,054 Ft.Run 908 M 2,981 FtRun 41,030 M 3,378 447 448 Rough Cast |columns (5R Rough Cast |columns (5R Rough Cast (Ditto 1" Thick) and Granite 48" Girth) (Ditto 1" Thick) and Granite 60" Girth) (Ditto 1" Thick) and Granite 449 |columns (5R 72" Girth) Ft.Run 1,136 M 3,726 150 Rough Cast (Ditto 1" Thick) and Granite |Circular columns 6" Dia Rough Cast (Ditto 1" Thick) and Granite Ft.Run 552 M 1,810 451 |Circular columns 9" Dia Rough Cast (Ditto 1" Thick) and Granite Ft.Run 772 M 2,533 452 |Circular columns 12" Dia FtRun 996 M 3,269 453 |Circular columns 15" Dia Rough Cast (Ditto 1" Thick) and Granite |Circular columns 18" Dia Rough Cast (Ditto 1" Thick) and Granite |Circular columns 21" Dia Rough Cast (Ditto 1" Thick) and Granite |Circular columns 24" Diameter |Spanish Wave Only to Walls. |Wood Float Top of 18" x 18" Pre-cast slab |Wood Float Top of 24" x 24" Pre-cast slab FtRun 1,188 M 3,898 Ft.Run 1,404 M 4,606 Ft.Run 1,600 M 5,251 Ft.Run Yd.Sq. Each Each 1,796 566 78 126 M m2 Each Each 5,892 677 78 126 154 455 456 157 458 159 Rough Cast (Ditto 1" Thick) and Granite — 16—- Masonry General suggested Job Work Rates Published as a quide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays( Not Worked ),Leaders Rate, and Production Incentive Refer to Clauses of the J.C Contract for Additional “age payment to be added based on project condition & location. IMPERIAL MASONRY Nos. METRIC Total [Notes UNIT Total Rate UNIT Rate 1) Add Extra Arris Rate for Beams with More Than 2 Arris 2) 160 161 162 For Electric, Manholes use 70% of Sewer Manhole Rates |Fairface Walls |Fairface Ceilings Fair Face Mortar Joints to 6" x 6" Breather |Blocks Y¥d.Sq. Yd.Sq. 289 368 m2 m2 345 440 Yd.Sq. 1,065 m2 1,274 Yd.Sq. 965 m2 1,154 Yd.Sq. 877 m2 1,049 Fair Face Mortar Joints to 9" x 9" Breather 163 164 |Blocks Fair Face Mortar Jints to 12" x 12" Breather |Blocks Fair Face Jambs (Ends) of 6" Concrete 165 |Louvres Ft.Run 179 M 586 166 |One Coat Render to Walls and Ceilings Y¥d.Sq. 463 m2 560 167 |Dress Water Drip Formed Ft.Run 144 M 471 Ft.Run 172 M 563 Each 74 Each 74 Each 88 Each 88 Ft.Run 49 M 162 Ft.Run 68 M 224 168 169 in Soffit of Slab Form and Dress Water Drip into Rendering |of Slab Soffit Pin Out and Dress Plumbing/Electrical Pipe |Through Walls (1 1/4" - 2") Pin Out and Dress Plumbing/Electrical Pipes 170 [Through Wall (3"-4") 171 |Chasings (Rough Walls) Pin Out Plumbing/Electrics (1 1/4" - 2") |Chasings (Rough Walls) Pin Out Plumbing/Electrics (3"-4") Chasings 172 Pin Out Plumbing/Electrics (1/2" - 1") 173 |(Rough Walls) Ft.Run 87 M 285 174 Pin Out Dress Plumbing/Electrics Small |Chasings (Finish Walls) Ft.Run 147 M 483 475 |Pin Out Top of Walls Under Beams or Slabs Pin Out Around Electrics Outlets (Rough FtLRun 86 M 281 176 |Walls) FtRun 51 M 169 FtRun 100 M 327 Ft-Run 147 M 483 Ft.Run 283 M 930 Ft.Run FtRun Ft.Run 401 48 260 M M M 1,316 158 852 Pin Out and Dress Around Electrics Outlets 177 180 181 182 |(Dress Walls) Patching (Rough Cast and Granite) less |Than 12" Wide Build and Dress One Reveal Band Up to 8” |Wide including Nailing Timber Build and Dress Two Reveal Band Up to 8" |Wide including Nailing Timber |Nail Timber strip Only to Form Reveal |Form Chamfer Including Arrisses 183 |Screeds Yd.Sq. 119 m2 142 184 |Rod-Off and Broom Finish Floor Slabs Yd.Sq. 406 m2 486 178 179 Rod-Off Floor Slabs to Receive Tiles or ~17— Masonry General suggested Job Work Rates Published as a quide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays( Not Worked ), Leaders Rate, and Production Incentive Refer to Clauses of the J.I.C Contract for Additional “age MASONRY Nos. |Notes 1) Add Extra Arris Rate for Beams with More Than 2 Aris 2) payment to be added based on project condition & IMPERIAL Total Rate UNIT location. UNIT METRIC Total Rate For Electric. Manholes use 70% of Sewer Manhole Rates: 485 |Rod-Off and Wood Finish Floor Slabs Yd.Sq. 406 m2 486 186 |Rod-Off and Steel Float Floor Slabs Manually Yd.Sa. 606 m2 724 187 Rod-Off and Steel Float Floor Slabs |Mechanically Wood Float Floor Slabs or Broom Finish Yd.Sq. 289 m2 345 Y¥d.Sq. 286 m2 342 FtLRun 249 M B17 FtRun 372 M 1,221 Ft.Run 172 M 563 FtRun Ft.Run 257 91 M M 844 298 Ft.Run 52 M 172 188 189 190 |Slabs (Screed and |Wood Float Screed and |Steel Float Dress Tread (10 - 12") Wide Including Redge Dress Tread (10 - 12") Wide Including Redge Screed and Dress Riser (6"-8") Wide Wood 191 |Float Finish Including Redge Screed and Dress Riser (6" -8" ) Wide Steel 192 193 |Float |Mark Floor Slabs with Metal Tool 494 |Mark Floor Slabs with Cotton Cord 495 |Joint and Seal 18" Diameter Culvert Pipes FtRun 278 M 913 196 |Joint and Seal 24" Diameter Culvert Pipes Ft.Run 363 M 1,192 |Fillet Ft.Run 144 M 471 |Fillet Ft.Run 172 M 563 |Fillet Ft.Run 230 M 756 497 198 199 Mix Material Hoist Cast and Dress 2" x 2" Mix Material Hoist Cast and Dress 3" x 3" Mix Material Host Cast and Dress 4" x 4" Mix Material Hoist Cast and Dress 6" x 6" 200 201 |Fillet {Lay Haunch and Point Kerbs Ft.Run Ft.Run 294 213 M. M 965 699 202 Provide Labour Pour and Settle Pre-mix |Concrete Yd.Cu. 686 M3 898 Each 191 203 204 |Lay paving Slabs Without Pointing on Sand Lay Bricks/pavers (9" x 4") and Point and |Clean Joints Lay Bricks/pavers (9" x 4") and Point and Each 191 Ft.Sq. 455 m2 4,896 172 M 563 205 |Clean Joints FtLRun 206 Trap G/ Basins From 4" Blocks Complete 12" |W. x12" Lg.x 12" Int.Dia. Trap G/Basins From 4" Blocks Complete 15" Each 4,290 Each 4,290 Each 5,720 Each 5,720 Each 7,722 Each 7,722 Each 8,825 Each 8,825 Each 10,295 Each 10,295 207 208 209 210 |W. x15" Lg.x 15" Int. Dia. Trap G/Basins From 4” Blocks Complete 18" |W. x 18" Lg.x 18" Int. Dia. Sewer M/H From 6" Blocks Complete 18" |W.x18" Lg.X 18" Int. Dia. Sewer WH From 6" Blocks Complete 18" W |x 18" Lg. x 24" Int. Dia. ~18= Masonry General suggested Job Work Rates Published as a quide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays{ Not Worked ),Leaders Rate, and Production Incentive Refer to Clauses of the J.1.C Contract for Additional “.age payment te be added based on project condition & location. IMPERIAL MASONRY Nos. [Notes Total Rate UNIT 1) Add Extra Arris Rate for Beams METRIC UNIT Total Rate with More Than 2 Arris 2) For Electric. Manholes Manhole Rates 211 212 213 214 216 217 use 70% of Sewer Sewer M/H From 6" Blocks Complete 24" W |x 24" xLg. x 24" Int. Dia. ‘Sewer M/H From 6" Blocks Complete 24" W |x 24" Lg. x 30" Int. Dia. ‘Sewer M/H From 6" Blacks Complete 24" W |x 30" Lg. x 24" Int. Dia. ‘Sewer M/H From 6" Blocks Complete 30" W |x 34" Lg. x 30" Int. Dia. Sewer M/H |x 30" Lg. x Sewer M/H |x 36" Lg. x From 6" Blocks Complete 30" W 30" Int. Dia. From 6" Blocks Complete 30" W 24" Int.Dia. Each 12,555 Each 12,555 Each 14,638 Each 14,638 Each 13,709 Each 13,709 Each 14,921 Each 14,921 Each 17,410 Each 17,410 Each 16,036 Each 16,036 Each 47,255 Each 17,255 Each 20,187 Each 20,187 Each 23,170 Each 23,170 Each 37,897 Each 37,897 Each 45,690 Each 45,690 Sewer M/H From 6" Blocks Complete 36" W 218 |x 36" Lg, x 24" Int. Dia. Sewer M/H From 6" Blacks Complere 36" W 219 |x 36" Lg. x 30" Int. Dia. Sewer M/H From 6" Blacks Complete 36" W 220 |x 36" Lg.x 36" Int. Dia. Sewer M/H From 6" Blocks Complete 48" W 221 |x 48" Lg. x 48" Int Dia. 222 Sewer M/H Fram 6" Blocks Complete 48” W |x 48" Lg. x 60" Int. Dia. METRIC Rate FINISH rowel on finished application with color tint to floors & aaeneane NOTE as wwcennccene Item #1 ~19— Carpentry SCHEDULE OF TASK WORK RATES PERIOD 4 J.C. Direct Labor Rates Carpentry 2 DailyTotal No of Men HrJEach 1 2 4 4 706.85 585.73 5,654.78 4,685.84 3 1 486.49 3,891.92 Grade J.C. Direct Labor Rates Labourer BASE RATE:3 J.LC. Fringe Benefits 0.00 0.00 0 2 Sick Leave 1.00 Public Holidays Not Worked Holiday with Pay Vacation 4.00 1.00 14,232.54 15.00 Production Incentive 18.00 2,561.86 14,232.54 18.00% of 5,654.78 Leaders Rate 6% of 6.00 TEAM RATE :- 339.29 47,133.68 NOTES: 1 Construction Employment Premium 2 For job rates, total team rate is divided by production 3 payment will be Job Work Total Rates include the construction employment premium and no further made at the End of the Project. 16% is (Now included in Base Hourly Rate } 4 BO Carpentry General suggested Job Work Rates Published as a quide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays { Not Worked ),Leaders Rate, and Production Incentive Refer to Clauses of the J.I.C Contract for Additional %age payment to be added based on project condition & location. and Forms to Belt and amd Forms to Forms to to stairs) of Manholes New Circular Formwork Colunms Oil To Formwork or Timber or of Concrete Poured nsert to Under Rebar Fix Inside Formwork to Base Plate Fit Hurricane Fit Gutter Brackets to Timber Fit Gutter Brackets to Concrete x or i Ends x or Beam Ends or x Ends x 10" Rafter or Beam x 2" Framing to oar Rafters/Joists x Rafters/Joists "x Rafters/Joists "x4 Rafters/Joists = 94. Carpentry the Industry General suggested Job Work Rates Published as a quide for Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays ( Not Worked ),Leaders Rate, and Production Incentive te be added based on project condition & Refer to Clauses of the J.1.C Contract for Additional “age payment ongue of RaftersNoists ongue of Rafters/Joists x x 3" Bearers x2" x3" Bearer x2" & 1"x3" x 2" Battens to ) to Roof or Wall (wooden to Roof or W. to or to Roof or Wall Lath at to Roof or Wall at x . to Roof or Wall x Tiles to RooffWall "x3" Purlins Roof to to Roofs and or (Wooden to 1"x 6" Fascia = 22 location. Carpentry General suggested Job Work Rates Published _as @ quide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays { Not Worked ),Leaders Rate, and Production Incentive Refer to Clauses of the J.1.C Contract for Additional %age payment to be added based on project condition & location, Matric Rate "x 6" 388, 1"x 8" x "x 1" x 10" 1" x 12" Fascia 1x1 Board Board On Centered Vi 16" On Centered Vi Frame Frame Vertical Install Corner Beads to Walls Install (i/2" = Plywood Sheeting (3/16" - 3/8") Walls Install Plywood (1/2" = 3/4") to and Plaster Walls and Plaster Only to Roof or Wail Only to Roof or Wall or o Gables Zinc russes 1 Sheds Plus Lath russes @ 5 & Zinc and Stack =-23— Carpentry General suggested Job Work Rates Published _as a a1 jefor the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays ( Not Worked ),Leaders Rate, and Production Incentive be added based on project condition & Refer to Clauses of the J.LC Contract for Additional Gage payment to location. Metric Total Rate and Stack x x Boards x on Boards x etc. to nstall Concrete Board To Walls Board 24 = Joinery SCHEDULE OF TASK WORK RATES PERIOD 1 2 J.C. Direct Labor Rates. Joinery Grade No of Men 1 2 1 1 832.91 708.73 3 0 0.00 DailyTotal 6,663.24 5,669.88 0.00 J.C, Direct Labor Rates Labourer 2 3 HrJEach J.C. 0 0.00 0.00 BASE RATE:- 12,333.12 Fringe Benefits Sick Leave 7.00 Public Holidays Not Worked Holiday with Pay Vacation Production Incentive 1.00 4.00 15.00 18.00 18.00% of 12,333.12 Leaders Rate 6% of 6,663.24 2,219.96 6.00 399.79 14,952.88 NOTES: Construction Employment Premium 16% is {Now included in Base Hourly Rate For job rates, total team rate is divided by production Job Work Total Rates include the construction employment premium and no further payment will be made at the End of the Project. a setoff, for remedial works, which if dn e paid, by the Main Contracter within 7 days cf acceotance of the works ( if any | corrected . providing such remedial works were dene by the initial contracted Sub-L abourer/ Contractor in the event the initial Sub- Labourer! Contractor, abandon the works. orIs terminated the retention witheld may be used to provide relief ta the Main Contractor for correcting the works. — 25— Joinery General suggested Job Work Rates Published as a quide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays ( Not Worked ),Leaders Rate, and Production Incentive based on project condition & location. Refer to Clauses of the J.1.C Contract for Additional %age payment to be added - SHOP RATES to Arches Add to x3" Top x4" x 6" x x 4" x "x3" "x4 "x6" Bevelled Top WPP Top WPP. Bevelled to Mah. Etc. to . Ete. Bevelled to Mah. Etc. Molded T Molded Top WPP Molded Ts “x3" "x4" "x6" Molded Top Molded Top Top x 1/2" x 1/2" x Mah. Etc. Mah. Mah. Etc. For Flush Doors W or Doors Cedar/WPP WPP 7x3" "x4 "x2" "x3" "x4" "x2" x 4" x 6" x 8" x 4" x 6" WPP 3/3]3/3/3)3/3]/3]3/3(3/3/3 /3)3/31/3 [33 |3)3 1/3 [3 | 3]3 1/3 [3 JOINERY For WPP : Cedar/Mah. Cedar/Mah. Rails Molded: Door/Ditto Frame WPP Door Frames Door Frames WPP. Door Frames Ete. Door Frames Mah. Etc. x 8" Door es WPP. . Etc. /2" x1 1/2" Door f2"x11 (3/8" - Etc. and Fit 13/3/3/5/3]3/3 ng WPP. WPP Mah.Ete. Mah. Etc. WPP Etc. Etc. 3 x 4" Handrails x andrails x 4" Handrails x6" x12" Treads x 12" Treads x1 Cedar/Mah., 3/36 m Rebates in Jamb & x 4" Newel Post 3 PP x4" x2" WPP x 2" Baluster Make Com 6" x 2" Pane (U 4" x3" and 1" x 4" Door Strips Wx Door 6" x 3" Pane 6" x 4" Pane Make . LID) & Laminate From Pine Kitchen 51 e |Laminate From Hx 1" W) From 96 — Joinery General suqgested Job Work Rates Published _as a quide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays{ Not Worked ),Leaders Rate, and Production Incentive Refer to Clauses of the J.C Contract for Additional “age payment to be added based on project condition IMPERIAL JOINERY - SHOP RATES Notes Nos.[1) For Gircular Frames to Arches Add 50% to Rates 53 Make Kitchen Wall Cupboard (2' H x 1' W) From Cedar |(Sprayed) Total Rate UNIT UNIT Ft.Run 5,621 m & location. METRIC Total Rate 18,444 54 |Make Kitchen Wall Cupboard (2' H x 1' W) From Ply Only Make Vanitory Cupboard (32" H x 22" W) From Plywood Ft.Run 3,966 m 13,013 55 |(No LID) Ft.Run 4,504 m 14,777 Ft.Run 5,138 m 16,859 Ft.Run 4,504 m 14,777 Ft.Run 5,457 m 17,905 Ft.Sq. 1,150 m2 12,381 FtSq. 804 m2 8,653 Make Vanitory Cupboard (32" H x 22" W) From Ply & 56 |Laminate (No LID) Make Vanitory Cupboard (32" H x 22" W) From Pine 57 |(Sprayed) (" ) 59 Make Vanitory Cupboard (32" H x 22" W) From Cedar |(Sprayed) (") Make Serpentine Louvre (Rods, Blades,Stops,etc.) 40x |16 14 Blades 60 |Make Fixed Louvre Doors (1 3/8" - 1 3/4") Thick 58 = Dye Joinery General suggested Job Work Rates Published _as a quide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays { Not Worked ),Leaders Rate, and Production Incentive based on project condition & Refer to Clauses of the J.C Contract for Additional %age payment to be added JOINERY - SITE RATES ‘Circular Frames to Add 50% WPP Top WPP x 6" x3" "x4" "x6" "x3" x4" "x6" x "x4" x6" x1 Bevelled Top Mah. Top Mah. ETC Bevelled Top Mah. ETC. Top WPPMolded Top W Top WPP Molded Top Mah. Etc. Mah. Etc. Molded Top Mah. Etc. ‘ace “edie x 3/3/3|3/3/3|3]3/3/3|3]3|3 Bevelled Top Bevelled for Face of Flush Doors Cedar/Mah. WPP 3" "x4" WPP "xO 9" Cedar/ Mah. "xa" Cedar, x4" Frames WPP x 6" Door/Window Frames x 8" Door Frames WPP x 4" Door/Window Frames x6" Frames Mah. Etc. x 8" Door/Window Frames Mah. Shower Surface MTD. Dish Furface MTD. Towel Rails Mounted Towel Roll Holder Toilet Holder Mtd. Tooth Holder Surf/Mtd/ f2"x11 /2" x1 1/2" Door WPP Mah. Etc. x 3/4" Materials x 4" Handrails WPP x 6" x 4" Handrails Mah. Etc. x6" Etc. x 12" Tread WPP x 12" Treads WPP Winders Treads x etx 12" x x4" x2" WPP WPP WPP. x 2" Balusters: Cedar/Mah. secrete nailed) on and 10" Fit and Doors Small <2" 4" Fit and Casement Doors e> and Fit and and Fit and Fit and Fit it Casement Windows ent Windows Raised Panel Doors Doors Closet Louvre Doors in Hollow Flush Door Solid Core Flush Door Steel Door & Frame holes for m @ 3/3]3)3|3/3|3/3/3/3]3/3]3 9. - x3" x 4" 3/3/3/3|3|3/3)3/3|3/3|3/3|3|3/3/3 o nN Slole}|rlo}a]s]elm|—= Rates tocation. Joinery General suggested Job Work Rates Published _as a guide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays{ Not Werked ),Leaders Rate, and Production Incentive Refer to Clauses of the J.1.C Contract for Additional “4age payment to be added based on project condition & jocation. JOINERY - SITE RATES IMPERIAL Notes Nos.|1) For Circular Frames to Arches Add 50% to Rates Total Rate UNIT METRIC UNIT Total Rate Fit Double Stee! Doors and Frame Including Holes for 63 |Joggles Each 7,476 Each 7,476 64 |Fit Night Lock, Indicator Bolt or Flush Bolt Each 1,495 Each 1,495 65 |Fit Mortice Lock Each 1,869 Each 1,869 66 |Fit Dead Lock Each 2,136 Each 2,136 67 |Fit Double Action Mortice Lock 68 69 70 71 |Fit Panic Latch/Lock With Bars or Rails |Fit Barre! Bolts Including Keeper In Floor |Fit Casement Stay |Fit Casement Pull Fit Glass to Casement Door and Window With Including |Putty 72 73 |Fit Glass to Casement Door & Window Including Strips 74 75 76 |Fit |Fit |Fit Fit Large Glass to Casement Ditto With/Including Putty Large Glass Panels Including Strips Mirrors on Walls Small < 5 Ft. Sq. Mirrors. on Walls with Ply Backing Incl. Ply SM < 77 [Sft-Sq. 78 79 Fit Mirrors in Timber Frame on Walls incl. Frame SM< [5tt.Sq. |Fit Mirrors on Walls Large 80 |Fit Mirrors on Walls with Ply Backing Including Ply. Large Fit Mirrors in Timber Frame on Walls Including Frame: 81 [Lg 82 | Shelving framed with 1" x 2" @ 2" On Center 83 |Install Kitchen Floor Cupboard Including Shelves 84 |Install Kitchen 85 |Install Kichen Floor Cupboard 86 |Install Kitchen 87 88 89 90 |Install Kitchen Wall Cupboard Including Shelves |Fit Metal Louvre Window in Masonry Opening |Fit Metal Louvre Window In Timber Frames |Fit Metal Jambs For Louvres In Masonry Opening 91 |Fit Metal Jambs For Louvres in Timber Frames 92 |Fit Door 93 94 95 96 |Fit Door Closers External |Fit Hinges Alone 4" Butts |Fit Hinges Alone 3" Butts |Cut, Fit and Screw Timber Louvres to Metal Jamb Floor Cupboard Floor Cupboard LID Postformed LID Corian/Equal LID Pull 97 |Fit Door Stop or Bumper Each 2,991 Each 2,991 Each Each Each Each 4,984 498 498 348 Each Each Each Each 4,984 498 498 348 Each 230 Each 230 Each 230 Each 230 Ft.Sq. Ft.Sq, Ft.Sq. 220 220 427 m2 m2 m2 2,367 2,367 4,599 Ft.Sq. 427 m2 4,599 Ft.Sq. Ft.Sq. 427 374 m2 m2 4,599 4,024 Ft.Sq. 374 m2 4,024 Ft.Sq. Ft.Saq. Ft.Run 374 220 2,490 m2 m2 m 4,024 2,367 8,171 Ft.Run 4,150 m 3,774 Ft.Run 1,495 m 4,906 Ft.Run 1,495 m 4,906 Ft.Run Ft.Sq. Ft.Sq. Ft.Run 1,870 393 305 305 m m2 m2 m 6,135 4,236 3,285 1,001 FtRun 234 m. 767 Each 1,068 Each 1,068 Each Pair Pair Each 2,136 623 534 374 Each Pair Pair Each 2,136 623. 534 374 267 Each 267 Each 98 |Adjust Clips and Fit Glass Louvres to Metal Jambs Each 130 Each 130 99 |Caulk Both Sides of Jambs with Compound Ft.Run 64 m 209 Ft.Sq. Ft.Sq. 1,359 374 m2 m2 14,632 4,024 Assemble & Fit Serpentine Louvres Complete 4100|/40"x16"x14 Blades 101|Make Strips and Install Lattice In Frames With Strips 20x Painting SCHEDULE OF TASK WORK RATES PERIOD 4 J.C. Direct Labor Rates Painting 2 DailyTotal Grade No of Men HrJEach 4 4 655.91 5,247.24 2 4 595,53 4,764.21 3 o 0.00 0.00 J.C. Direct Labor Rates Labourer BASE RATE:- 3. J.LC, 10,011.45 Fringe Benefits 1.00 Sick Leave Public Holidays Net Worked 1.00 Holiday with Pay Vacation 1.00 Production Incentive 15.00 18.00 18.00% of Leaders Rate 6% of 1,802.06 10,011.45 5,247.24 314.83 6.00 412,128.35 TEAM RATE :- NOTES: 1 Construction Employment Premium 16% is (Now included in Base Hourly Rate 2 For job rates, total team rate is divided by production 3 further payment Job Work Total Rates include the construction employment premium and no will be made at the End of the Project. 4 Retention of 10% to 2 maximum of Ste 2 tolal earnings may be witheldé-ageinstal sik 7.davs of acceptance of the works( if any } corrected done by the initial contracted Sub-Labourer! Contractor providing such remedial works were Painting General suggested Job Work Rates Published _as a quide for the Industry Refer to Clauses of the J..C Contract for Additional %age payment to be added based on project condition & IM focation. METRIC otal als|a|afeo|e|~/ofal=folo|= Rate all- Two Paint - “J 2 ® Coat - Two Coats: - Two Paint - Wood Floor - Two Coats al Gfoms Painting General suggested Job Work Rates Published _as a quide for the Industry based on project condition & location. Refer to Clauses of the J.1.C Contract for Additions! Sage payment to be added - Rafter - One =32= Plumbing SCHEDULE OF TASK WORK RATES PERIOD J.C. Direct Labor Rates Plumbing Grade No of Men HrJEach DailyTotal 1 2 1 41 729.66 611.84 5,837.30 4,894.74 3 0 0.00 4 457.03 3,656.22 BASE RATE:- 14,388.23 0.00 J.1.C. Direct Labor Rates Labourer 2 J.C. Fringe Benefits Sick Leave Public Holidays Not Worked Holiday with Pay Vacation Production Incentive 1.00 1.00 4.00 15,00 18.00 18.00% of 14,388.23 Leaders Rate 6% of 2,589.88 5,837.30 6.00 TEAM RATE :- 350.24 17,328.35 NOTES : Construction Employment Premium 16 % is (Now inchided in Base Hourly Rate } For job rates, total team rate is divided by production Job Work Total Rates include the construction employment premium and no further payment will be made at the End of the Project. Retention of 16.% to # maximum @.setoff, for remedial works. acceptance of the works if any of 5% of total earnings may be withald against all work as if withheld must be naid, by the Main Contractor within 7 days of guch remedial works were done by | } co! {40 tha Main Cor Qc 3,97 Is terminated the ctor for correcting the works. Plumbing General su’ ested Job Work Rates Published _as a guide for the Indus! Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays { Not Worked ),Leaders Rate, and Production Incentive be added based on project condition & tecation. Refer to Clauses of the J.I.C Contract for Additional %ago payment to ‘otal PLUMBING Rate PVC PIPES & FITTINGS DRAINAGE 284 473 Diameter 95. 95 403 244 1 Three End With Mixer and Waste Connection Water Heater (30 - 40) Gal. With B/Off, Supply Hot & Cold =94= Plumbing General suggested Job Work Rates Published _as a quide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays { Not Worked ),Leaders Rate, and Production Incentive Refer to Ciauses of the Nos Contract for Additional %age payment te be added based on project condition & |-WATER SUPPLY 1/4" Diameter Diameter Diameter 40 Double 40 Schedule 1/2" Dia. Gate Valve Ends) and —~35-- location. Plumbing General suggested Job Work Rates Published as a quide for the Indus Included in the calculation are:- Sick Leave, Holiday with Pay, Public holidays{ Not Worked ) Leaders Rate, and Production Incentive & Additional “sage payment to be added based on project condition for Rofer to Clauses of the J.C Contract = WATER SUPPLY ~36 — location. Scaffolding SCHEDULE OF TASK WORK PERIOD RATES J.LC. Direct Labor Rates Scaffolding Grade No of Men 41 2 3 J.C. HrJEach 41 41 4 DailyTotal 619.98 559.47 468.56 4,959.81 4,475.72 3,748.44 Direct Labor Rates Labourer 2 0 0.00 BASE RATE:J.1.C. 0.00 13,183.97 Fringe Benefits Sick Leave 1.00 Public Holidays Not Worked Holiday with Pay Vacation Production Incentive 1.00 1.00 15.00 18.00 18.00% of 13,183.97 Leaders Rate 6% of 2,373.12 4,959.81 6.00 297.59 TEAM RATE :- 15,854.68 NOTES: Construction Employment Premium 16% is (Now includedin Base Hourly Rate } For job rates, total team rate is divided by production Job Work Total Rates include the construction employment premium and no further payment will be made at the End of the Project. wither ainst all work f , for remedial works, which if withheid mu é oald, by the Main Contractor within 7 days of acceptance of the works i the initial contracted S: cied Sul urer! Contract nH in the event the initial ub- Labourer! Contractor, abandon the works. or is terminated the fetention witheld may be used to provide relief to the Main Contractor for correcting the works. =v. Scaffolding General suggested Job Work Rates Published as a guide for the Industry Included in the calculation are:- Sick Leave, Holiday with Pay, Refer to Clauses of the J.C Unbraced Incentive Public holidays { Not Worked ),Leaders Rate, and Production & Contract for Additional %age payment to be added based on project condition to Upto 10° Tied to Braced Formwork Soffit Board 10' to 20° to Dismantie Above 40" ~38- location. Tiling SCHEDULE OF TASK WORK RATES PERIOD J.C, Direct Labor Rates Tiling Grade No of Men 1 2 3 Hr/Each 0 1 1 0.00 681.11 591.55. DailyTotal 0.00 5,448.90 4,732.38 J.1.C. Direct Labor Rates Labourer 2 0 J.C. Fringe Benefits 0.00 BASERATE:- 0.00 —~—~—=«*10,187.28 1.00 1.00 1.00 15.00 18.00 18.00% of 10,181.28 Leaders Rate 6% of 5,448.90 TEAM RATE :- 1,832.63 6.00 326.93 12,340.84 NOTES: Construction Employment Premium For job rates, total team rate is divided by production Job Work Total Rates include the construction employment premium and no further payment will be made at the End of the Project. Retention of 1 : ff, for remedial works, which if wi a SGion days. of, Tiling to be added based on project condition & Refer to Clauses of the J.C Contract for Additional “age payment location. METRIC For 12+) Floors Grout and Clean Tiles 6" Lay with Grount and Clean. Clean, & Clean In Wall in Wall Grout & to and Walls Floors and Walls Columns and Beams Columns and Beams’ ~- 40- Welding | 1 SCHEDULE OF TASK WORK RATES PERIOD 1202 | To | 31.1..2023 J.C. Direct Labor Rates Welding 2 Grade No of Men Hr./Each 41 1 728.75 5,829.99 2 1 634.93 5,079.44 3 0 0.00 0.00 0 0.00 0.00 J.C. DailyTotal Direct Labor Rates Labourer 2 BASE 3 RATE:- 10,909.43 JLC. Fringe Benefits Sick Leave Public Holidays Not Worked Holiday with Pay Vacation Production Incentive 1.00 4.00 1.00 15.00 18.00 18.00% of Leaders Rate 6% 10,909.43 of 5,829.99 1,963.70 6.00 TEAM RATE :- 349.80 13,222.92 NOTES: 1 Construction Employment Premium 16% is {Now included in Base Hourly Rate 2 Far job rates, total team rate is divided by production 3 Job Work Total Rates include the construction employment premium and no further payment will be made at the End of the Project. 4 Retention of 10% to_a maximum of 5% of total earnings may be witheld against all work as. a setoff. for remedial works, —41—- which If withheld musi be paid. by the Main Contractor within Welding to be added based on project condition & Refer to Clauses of the J.I.C Contract for Additional Yage payment location. METRIC ‘otal DRILLING WELDING INSTALLATION & Torch Torch Torch Torch Torch Torch Cut Torch CPSAW CPSAW CPSAW CPSAW CPSAW Mark Cut CPSAW CPSAW 4/8" x1 Through ( - 14 With Press Holes = with Press =1 with Press with Press with Press with Press = Through with Press » *) with Press 18" 1 with Press -1 with Press with Press. with Press Thick with Press - (7/8" = 1 with Press with Press =4 (7/8" - with Press - Through - 1/4 Hand Drill -1 Hand Drill whe Welding Refer to Clauses of the J.C Contract fer Additional %ege payment to be added based on project condition & DRILLING WELDING INSTALLATION 1/8" ~ 1/4") Hand Drill Hand Drill Drill Holes (1/8"~ Hand Drill “1 Hand Drill Hand Drill Holes e eter with Hand Drill 1/8"-1 Dia. Hand Drill Hand Drill Holes (5/8"-. Hand Drill 18"-1 with Hand Drill with Hand Drill with Hand Drill with Hand Drill with Hand Drill Drill 1/8" with Torch with Torch Drill Holes 41 with Torch with Torch with Torch with Torch Holes = with Torch =f with Torch 18" with Torch Holes '~1/2") with Torch Diameter with Torch a] with Torch with Torch with Torch with Torch '- 1") Diameter Through Torch " Fillett Weld Fillet Weld Butt Weld -1 location. Welding Refer to Clauses of the J.1.C Contract for Additional %age payment DRILLING WELDING INSTALLATION Weld to Up S41 . Ls. to 3" Girth: Solid Ls. RHS. elt, Above 6" Girth Solid Gutter cover 4 Covers Make Covers 1/8" Thick Plate With Handle 12" x 12" Covers 1/8" Thick Plate With Handle 18" x 18" Covers 1/8" Thick Plate With Handle 24" x 24" Make Covers 3/16" Thick Plate With Handle 12" x 1 Make Covers 3/16" Thick Plate With Handle 18" x 1 to be added based on project condition & focation. Welding Refer to Clauses of the J.LC Contract for Additional %age payment to be added based on project condition & Nos._|CUTTING DRILLING WELDING INSTALLATION UNIT 100 |Make Covers 3/16" Thick Plate With Handle 24” x 24" Each 401 |Make Covers 1/4" Thick Plate With Handle 12" x 12" 102 |Make Covers 1/4" Thick Plate With Handle 18" x 18” 103 IMPERIAL Total Rate UNIT location. METRIC. Total Rate 2,645 Each 2,645 Each 1,469 Each 1,469 Each 2,204 Each 2,204 |Make Covers 1/4" Thick Plate With Handle 24" x 24" Each 2,645 Each 2,645 104 |Make Covers 3/8" Thick Plate With Handle 12" x 12" Each 1,653 Each 1,653 105 |Make Covers 3/8" Thick Plate With Handle 18" x 18” Each 2,204 Each 2,204 106 [Make Covers 3/8" Thick Plate With Handle 24" x 24" Each 3,306 Each 3,306 4107 |Make Covers 12" x 12" Each 1,653 Each 1,653 108 |Make Covers 1/2" Thick Plate With Handle 18" x18" Each 2,645 Each 2,645 |Make Covers Each 3,306 Each 3,306 Ft.Sq. 735 m2 7,907 Ft.Sq. 661 m2 7,117 Ft.Sq. 630 m2 6,778 Fi.Sq. Each 1,017 696 Ft.Sq. 139 m2 1,498 Ft.Sq. 249 m2 2,686 m2 2,333 109 110 111 112 1/2" Thick Plate With Handle 1/2" Thick Plate With Handle 24" x 24" Make Louvre Grill 1 1/4" x 1/4" & 1/2" x 12" @ On |Center HZ SGL/Bay Make Louvre Grill 1 1/4" x 1/4” & 1/2" x 1/2" @ 4" On |Center HZ DBL/Bay Make Louvre Grill 1 1/4"x 1/4" & 1/2" x 1/2" @ On |Center HZ TPUBay Make Gate Grill 1 1/4" x 1/4" & 1/2" x 1/2" @ 4" 12” 113 114 115 116 117 118 419 120 4121 122 |On Center VT & HZ |Make Hinges Fram 3/4" Pipe & 5/8" Bar 4.5" Long Priming Grill Work 1/2" x 4/2" @ 4" cc Measured Flat |One Side Installation of Grills In Masonry Opening Less Than 8 |FtSq. Installation of Grills In Masonry Opeing > Than 8 |Ft.Sq. Make Column Clamps 1/4" x 3” x 48" Flat With Bend |& Slots Make Column Clamps Wedges 1/4" x 7 1/2"x 6" Flat |With Tapers Make wall Ties (Bolts) 1/2" x 36" With End Plate & |Threading Make Wall Tie Washers 1/4” x 3" x 3" With 1/2" |Diameter Hole Make Gratings 1" x 1/4" Flat @ 1" On Centered 18" x |18" Make Gratings 1" x 1/4" Flat @ 1" On Centered 24" x 123 |24" 124 125 126 127 128 Make |30" Make |18" Make |24" Make |30" Make |18" x Ft.Sq. 217 m2 Each 10,849 696 Each 1,017 Each 1,017, Each 165 Each 165 Each 551 Each 551 Each 281 Each 281 Each 6,611 Each 6,611 Each 9,445 Each 9,445 Each 13,223 Each 13,223 Each 3,778 Each 3,778 Each 5,289 Each 5,289 Each 6,611 Each 6,611 Each 7,778 Each 7,778 Gratings 1" x 1/4" Flat @ 1" On Centered 30" x Gratings 1" x 1/4" Flat @ 2" On Centered 18" x Gratings 1" x 1/4" Flat @ 2" On Centered 24" x Gratings 1" x 1/4" Flat @ 2" On Centered 30" x Gratings 2" x 1/4" Flat @ 1 1/2” On Centered 18" Welding to be added based on project condition & Refer to Clauses of the J.C Contract for Additional “age payment DRILLING WELDING INSTALLATION x 129 |24" x 130 24" Flat @ 4 2x x30" Make 131 |18" 132 133 |30" ~- 46 -- Iecation. Electrical SCHEDULE OF TASK WORK [ 1 1.2 2022 | RATES PERIOD To I 311.203 | J.C. Direct Labor Rates Electrical Grade 2 No of Men Each 1 2 1 41 812.25 690.00 3 1 Total 6,498.04 5,519.96 0.00 J.C. Direct Labor Rates Labourer 2 0 0.00 BASE RATE:- 3 J.I.C. Fringe Benefits Sick Leave Public Holidays Not Worked Holiday with Pay Vacation Production Incentive 0.00 12,018.00 1.00 1.00 1.00 15.00 18.00 18.00% of 12,018.00 Leaders Rate 6% of 6,498.04 2,163.24 §.00 TEAM RATE :- 389.88 14,571.12 NOTES: 1 Construction Employment Premium 16% is {Now inciuged in Base Hourly Rate} 2 For job rates, total team rate is divided by production 3 Job Work Total Rates include the construction employment premium and no further payment will be made at the End of the Project. 4 ae the tance of the works (ifif any 1 corrected , providing such remedial works were done by 8 contracted Sul Labourer, nontas! retention witheld may be used to rovide relief | to the Main Contractor for “correcting the works. aay a Electrical Refer to Clauses of the J.1.C Contract for Additional %age Rates are for Basic Residential Construction payment to be added based on project condition & location. IMPERIAL Total Rate 3/3)3)3)3|3 with 4/2" diameter diameter 1" diameter 4-1/4" diameter 1-1 2" diameter renches 3/3)3/3]3/3)3 Installation with 4" diameter 1diameter 1-1/2" diameter 2-1/2" diameter diameter a" a" Switch & 5 . 20 5 . & blank & Boxes 6" Hx BWx4"D x8"Wx4"D 10" Hx 12"W x6" D 1 x 20" Wx 8" D Hx 24" Wx H x 36" W x 8" D boards with 10 branch breaker with 14 breaker 18 branch breaker 4 150 15 amp &C/ dimmer switch with 2-3 outlet, 15 amp nsulated Wires and Cables 2.5 mm2 4mm2 PVC Wire 40 mm2 PVC 16 PVC Wire mm2 mm2 PVC Wire 50 mm2 Wire mm2 PVC Wire 95 mm2 Wire 20 mm2 PVC 150 Wire mm2 PVC 3/3]3 /3]3/3/3/3|3|3/3]3/3 1 Electrical Refer to Clauses of the J.l.C Contract for Additional ‘sage payment to be added based en project condition & focation, Rates are for Basic IMPERIAL Total 10 16 25 35 3/3 /3/3/3]3/3/3]3/3/3/3 mm2 Bare 4mme2 Bare mm2 Bare mm2 mm2 Bare mm2 Bare mm2 Bare 70 mm2 Bare 420 mm2 Bare 150 mm2 Bare mm2 3/3/3/3]3/3/3/3/3]3/3/3/3 4mm2 PVC 6 mm2 PVC 16 25 35 50. mm2 PVC mm2 mm2 PVC mm2 PVC. 95 mm2 PVC 20 mm2 Pvc mm2 PVC 3/3 /3/3/3/3/3/3/3]3/3]3/3 mm2 PVC mm2 PVC 6 mm2 PVC 10 mm2 PVC mm2 mm2 PVC mm2 PVC 20 mm2 50 mm2 PVC mm2 —49— «)