Uploaded by liquidevolution

Jamaica Basic Manual of construction - 2022

advertisement
BASIC
CONSTRUCTION
MANUAL
FORA
SINGLE
STOREY
DOMESTIC
DWELLING
(RATES ARE APPLICABLE TO ALL BUILDINGS)
PRODUCED AND PUBLISHED BY
INCORPORATED MASTERBUILDERS
ASSOCIATION
OF JAMAICA
FIRST EDITION 2003
REPRINTED 2022
Copyright Incorporated Masterbuilders Association of Jamaica 2003
ACKNOWLEDGEMENT
This Basic Construction manual was developed by Incorporated Masterbuilders
Association of Jamaica and during the process of it’s development, received assistance from a number of individuals and institutions.
The Incorporated Masterbuilders Association wishes to acknowledge the invaluable contribution made by the following persons in the development and production of this manual.
Mr. Stephen Hodges - CRDC chairman
Mr. Garth Lampart - UTECH lecturer
Mr. Rori Peynado
Mr. Len Smith
- UTECH lecturer
- Quantity Surveyor
Jamaican Institute of Architects
Bureau of Standards
The
HEART Trust
Milton Baker
(J.1.A)
FOREWORD
For many years the demand has far outstripped the supply for housing in
Jamaica. In recent years recession in the economy has resulted in a further
widening of this gap.
Shortfall in the housing stock, by the public or private sector, has forced house
seekers to self directed means to satisfy their needs. This at times has led to
many dwellings being constructed informally without adherence to building
safety codes and practices, which specifies minimum accepted building
requirements.
Jamaica is located in the hurricane and earthquake zones. Hence, shortcoming in
building construction has created a grave concern for the possible loss of lives
and damage to property that could result in the event of these natural disasters.
The Incorporated Masterbuilders Association of Jamaica has recognized the
inherent dangers of improperly constructed dwellings and seek to offer this
Basic Construction Manual as a guide to owners, small contractors and builders
of single storey domestic dwellings with the hope that adherence to the
minimum standards outlined will reduce the risk of loss of live and property.
In addition to construction guidelines, this manual also includes the latest Joint
Industry Council’s (JIC) rates available at the time of printing, along with a
listing of suggested job work rates for a number of construction activities.
These job work rates are provided only as a guide when negotiating rates.
Several factors such as, the condition of work, scope of work and geography,
will have varying impacts on these rates. Therefore, it is suggested that these
factors be considered when negotiating rates, as the ones included in this manual
may not be the latest being used in the industry. Copies of the latest rates are
always available from the office of the Incorporated Masterbuilders Association
of Jamaica.
Also included is an example of a simplified Form of Agreement that may be
used by owners and contractor / builder when a dwelling is to be constructed. It
is advisable that some form of written contract be entered into as projects at
times do not always end amicably.
CONTENT
STAGE 1
— PREPARING A PLAN OR SKETCH
STAGE 2
— SETTING OUT
STAGE 3
— EARTH WoRK- FOUNDATION
STAGE 4
— REINFORCEMENT
STAGE 5
— CONCRETING - BLOCKWALLS- RENDERING
STAGE 6
— ROOF - CONCRETE- TIMBER
STAGE 7
— FLOOR - CONCRETE- TIMBER
STAGE 8
— FIXTURES - WINDOWS/DOORS/CUPBOARDS/CLOSETS
STAGE 9
— PLUMBING
STAGE 10
— ELECTRICAL WORKS
STAGE 11
— FINISHING - PAINTING/CABINET MAKING/JOINERY/PLASTER
— JIC AGREEMENT
& LABOUR
RATES
— SUGGESTED SUBCONTRACT / JOB WORK
AUTHOR
TYPESETTING
—
—
NEVILLE BOXE
DONETTE
SPENCE
RATES
Basic Single Storey Building Construction
THE PLAN OR SKETCH _
THE
FIRST STEP TOWARDS
DWELLING
DRAWINGS
INFORMATION
MATERIALS,
IS TO PREPARE
AND
THE
CONSTRUCTION
A DRAWING
OR
A SKETCH.
SKETCHES
ARE
IMPORTANT
REGARDING
THE
SIZE, SHAPE, TYPE OF
AND
IMPORTANT
OF A
AS THEY
CONTAIN
SPECIFICATIONS FOR THE SAFETY
OF THE BUILDING.
e
The drawings are best prepared by a qualified Architect,
however some experienced
provide this service.
e
draftsman
or builder
also
Seek approval from your local Parish Council or agency
where applicable.
e
At least one person involved in the construction of the
building should be able to read and interpret the drawings
to ensure conformance with the details and specifications.
o
dl
O
SETTING OUT THE BUILDING
BJECTIVE
To examine the drawing or sketch in order to position the buildings on the
site or lot and ensuring that the stipulated distances from boundaries on existing
structures are maintained. Then mark out exactly the positions of external and
internal walls on profile boards and to ensure squareness and accuracy.
Picasa.
e Contractor/builder
e Skilled carpenter
OOLS/EQUIPMENT
QUANTITY
1
ITEM/DESCRIPTION
5 lb hammer
Pi PI] PI] Pi RPipB
Spirit level
Plumb bob
Pencil or chalk
Builder’s square
Mason’s square
Rule
Long tape
PP
T
Cord line
MATERIALS
1”x 3” Timber (profile boards)
2”x 4” Timber (pegs)
1/2” @ Steel (pegs)
Mi erson
=>STEP 1
Clear site of debris, shrubs, trees and any obstacle that would interfere
with the setting out and construction of the building.
=> STEP 2
Drive steel pegs at the approximate position of the proposed building in
relation to land space or lot boundaries.
DISTANCE
FROM
REAR | BOUNDARY
+—
SIDE
APPROXIMATE
POSITIONOF =
BUILDING =
BOUNDARY
DISTANCE
FROM
FRONT | BOUNDARY
SIDE
Lot
Boundary
If the land has a registered title it is best that the boundaries be located by a
commissioned land surveyor to avoid mis-locating building. Failure to locate
building accurately could result in costly legal implications.
=> STEP 3
e
Use measurements and steel pegs to locate approximate position of outer walls
of the building.
e
Drive 2’x4” timber pegs in locations approximately 2’-0” outside the walls at
each commer to accommodate profile boards (1”x3” timber).
e
Locate profile boards at approximate floor level height, using a spirit level and
chord line, to ensure that the profile boards around the entire perimeter, are
accurately leveled.
e On these profile boards the shape and exact dimensions of the building will be
marked.
PLAN SHOWING
PROFILE BOARDS
PROFILE BOARDS ARE LOCATED
APPROXIMATELY 2'-0” FROM
OUTER WALLS
Profile Board
= —+
APPROXI
MATELY
2’-0"
FROM
OUTER
WALL
Aggregate
Profile Board
Concrete Mixer
oS
¥ LEVELLED _ANO
rE FLOOR LEYE
CUNDATION CAN
ELY
=> STEP 4-
MEASURED
Mark the positions of walls, foundations and ensure squareness.
e
Locate the position of wall and foundation on first set of profiles, marking with
pencil, nail or saw cut.
e
Locate second and subsequent walls and foundations using lines and :a) Mason’s square
b) Builder’s square
c) The 3:4:5 method
e
The 3:4:5 method: any combination of the ratio will ensure a square cornerexample using a long tape and setting out triangle with sides e.g. (15’-0” x 20’-0”
x 25’-0").
a
o
co
oy
=
TD
Pp
3:4:5 TRIANGULAR
METHOD
Building Edge
L
|
a
}S
1,
4
\
BUILDERS LEVEL
MAISONS LEVEL
_
r
zx
: ed i
\
L
|
BR.
\
}
XN
x
a
7
\
SA
\
\
S
Lot Boundary
a
%
4
/
}r™
‘
YX
co
oI
|
Diagonal Lines
\ a |
aN
hey
bo
*——~
fu
#} wl
it
Profile Board
u
\
oO
o
oO
LOCATE FRONT
POSITION OF WALL
IN RELATION TO
BOUNDARY
PLAN DIAGONAL METHOD OF CHECKING
e
To check the accuracy and squareness of the setting out, the diagonal method may
be used.
To do this, use a long tape to measure both diagonals. Their measurement
should be the same. If they are not, re-check the squareness of each corner and
the measurement of each wall length.
Measuring Tape
@
Spirit Level
Profile Board
(1 x 3" Timber)
2” x 4° Timber
3
=
Chord Line
—_ 4
Trench Centreline
Plumbing Bob on String
Intersection of Chord Lines
Chord Line
=> STEP 5- MARKING
OUT FOUNDATION
e
Locate lines in the position marked out on the profiles for foundation.
e
Use a trail of sand or other suitable material and mark out the position
of foundation on ground in preparation for excavation.
©
Eff
O
EARTHWORKS « FOUNDATION
BJECTIVE
To accurately excavate trench as set out on profile to depth not less than
2’-0” in earth to facilitate pouring of reinforced concrete foundation.
P ERSONNEL
e
e
T
Contractor/builder/supervisor
Labourers
OOLS/EQUIPMENT
ITEM/DESCRIPTION
QUANTITY
MANUAL
a aesiac ree
-
.
1 |
1
Backhoe ‘ excavator
7
a
=
Pickaxe
——
If extensive rock is encountered a jack hammer connected to an air compressor plant
would be required.
Merson
DIGGING THE FOUNDATION TRENCH
e
Remove the building lines attached to the profile board to avoid them getting
broken.
e
Replace the lines in the notches on the profile boards should you need to check
the accuracy of the trench layout.
e
Foundation trenches should always be dug deep enough to reach firm soil.
The sides of the foundation trench should be vertical, the bottom level and the
comers must be square.
e
Check that the soil at the bottom of the trench is firm. If not, the supervisor
must ensure that action is taken to appropriately reinforce the foundation.
POSSIBLE ACTIONS
*
Deepen the trench until firm soil is reached. If deep foundation is not
reached then an alternate foundation design must be considered- (raft
foundation or pile foundation) and a civil or structural engineer
should be consulted.
«
Alternate design for foundation may be expensive therefore in such
situations, it might be best to seek a better site.
ANTI-PEST TREATMENT
Treat the surface of the ground and excavations under the building with soil
poisoning chemicals to eradicate subterranean termites.
©
Pieeannc
No
1.
FOR CONCRETE
Pegs are driven into the bottom of the trench and leveled in order that a
minimum of 200mm (8”) thick allowance is made for concrete.
The trench must be made level by removing soil, never by adding soil. If soil
is added, the foundation may fail. It may mean digging the trench slightly
deeper, but it will ensure your building remains strong.
3.
Remember the purpose of the reinforced concrete foundation is to distribute
the weight of the building safely to firm soil.
tl
O
STEEL
REINFORCEMENT
FOUNDATION
WALL BARS
STIFFENER/COLUMNS
LINTELS/BEAMS
ROOF SLAB/CANTILEVERS
BJECTIVE
To
cut,
bend,
place
and
fix
steel
reinforcement,
as
designated
accordance with the building code.
P
ERSONNEL
e Contractor builder/supervisor
e Steel fixer
e Labourer
E
QUIPMENT & MATERIALS
QUANTITY
ITEM/DESCRIPTION
MATERIALS
As needed
Mild steel corrugated bars.
1/4", 3/8", 1/2", 5/8", 3/4", diameter
No. 126 steel fabric
EQUIPMENT
2
Hack saw
]
Steel cutter
1
Bending Bench
and
in
©
Merson
Cut, bend place and fix reinforcement as per bending schedule (if provided).
e
For the safety of the building, all laps and bends should conform
building code.
TYPICAL BENDS
——
pan
|
[
a
EG ee
Fae
Se)
TYPICAL FOUNDATION
STEEL
Transverse Steel Bar
Longitudinal Steel Bars
TYPICAL STRIP FOUNDATION
4*———
PS
SAOATS
e
Concrete Block Wall
Vertical Steel bars
Anchored in Surip Foundation
fx
2
iS
‘
sania
my
xa
WY
Reinforced Concrete
‘
Strip Foundation
*
—
2
&_
|
24" (600)
|
Longitudinal Steel Bar
with the
TYPICAL COLUMN/STIFFENER
Horizontal Steel Bar
—
Passes Through Stiffener
+——————_
.
Horizontal Steel Bar
Anchored in stiffener Column
Concrete Block Wall
—_,
Vertical Steel Bar
Fy
wc
o| |
Stiffener Column
=,
_D—
we
i|
12° (300)
|
CC
iE =
¥
—j—}.
TT}
i
y
i
Vertical Steel Bar
Block Pocket Next to Stiffener Column
Horizontal Steel Bar Passes
Through Stiffener Column
TYPICAL BEAM/LINTEL
TYPICAL
SLAB ROOF WITH OVERHANG
Over Support Steel Bars
jen
Reinforced Concrete Roof Slab
Steel Link
Reinforced
2
Concrete Belt
Beam
=a"
a
°
Overhang
‘
ra
5
f
vi
Block
iC
Wal!
a
———
Steel Bars Bottom of Slab
wh.
Vertical Steel Bars
I]
Lat
Anchored inConcrete Belt Beam
eh.
=5§ ———"|-"|
| J
ar
Inside Building
TYPICAL FLOOR REINFORCEMENT
Concrete Block Wall
Steel Close To Top
Top Concrete Floor Slab
Fit, TL LEW
Ground Level
———+}-—
Compacted Fill
ie.
Reinforced Concrete Strip Foundation
CONCRETING
O
BJECTIVE
To prepare specified concrete by mixing the basic ingredients.
e Coarse aggregate (gravel)
e Fine aggregate (sand)
e Cement (ordinary Portland cement)
e Water (drinking water)
HAND MIXING OF CONCRETE
Prhisdinxt
e Contractor or builder/supervisor
© Four (4) labourer
E
QUIPMENT/MATERIAL
EQUIPMENT
Gauge box
Square point shovel
5 gallon bucket
MATERIALS
As needed
Cement (bags)
stone- 1/2” to 1” size
Sand (washed)
Water (suitable for drinking)
STEP 1
Construct a gauge box size to hold one bag of cement.
Drum of Water
Mixing Board
Wheel Barrow
Concrete Mix
Gauge Box
Fine Aggregate
Coarse Aggregate
sap
a ee
er eared)
rey
Ye
©
STEP 2
Gather materials
e
e
e
e
Fine aggregate (sand)
Coarse aggregate (gravel)
Cement (Portland)
Water
Cement
1 box full
2 box full
Gauge Box
4 Box full
Gauge Box
Make a batch of
—
ing proportions
1:2:4. This means | part
cement to 2 parts sand to 4 parts gravel.
concrete usby volume
STEP 4
e
Fill gauge box with sand and deposit on mixing board or a concreted area.
e
Spread sand evenly about 3" (75mm) thick.
STEP 5
Measure and spread
cement ontop ofsand laid
on mixing board.
ae
~
-«
eS
ie
g board
©
STEP 6
Use shovel to thoroughly mix cement and sand together.
STEP 7
Level
oot
and
spread
the sand and concrete mix
about 3” (75mm) bed as in step 2.
STEP 8
Use gauge box to measure and spread the
coarse aggregate (gravel) on the sand cement mix.
STEP 9
Mix the material and move
Sym
around as you mix.
=U)
Move Around and Mix
the Concrete
Continue mixing until
es
all the materials are
thoroughly mixed and
uniform in colour.
Concrete Mix
STEP 10
Mixing
Board
Using your shovel make a
circle of your mix and a
hollow in the center for
water.
Make Hollow in
Centre of Mix
®
STEP 11
The quantity of the water required for
the mix is calculated as follows.
L “4 t. ~
Tt Py
Mixing Board. ——+ |)
Note:
If the sand or stone is somewhat
wet, then the amount of water
used should be slightly reduced.
Conerete Mix
Sa
SN
—
The mix should be relatively stiff
and not soupy, to ensure adequate
strength.
The strength of the concrete is
affected by the amount of water in
the mix. Too much or too little
water gives weak concrete. Strong
concrete is not soupy or too stiff.
The amount of water added to get a good mix should be measured.
Mixing Board
For each batch
of concrete that follows, the same amount of water should be added to the mix.
This will ensure consistency in the strength of the mix.
@
STEP 12
When the water has been somewhat absorbed by the materials, use the shovel
and carefully mix, ensuring that the water does not escape from the center of
the mix.
Mixing Board
STEP 13
After thoroughly mixing,
there should be consistency
in appearance. The concrete is now ready to be
poured.
Note:
When water was added the setting
process began, so delays in pouring should be avoided.
WALLS
O
- BLOCKLAYING
BJECTIVE
To provide load bearing support for the roof and act as a cladding to protect
against the elements of wind, rain, dust and smoke.
General Note
Load bearing walls should be a minimum 6" or 150mm in thickness.
Non-load bearing walls separate rooms, but do not support the roof. They
should be at least 4" or 100mm thick.
Pp ERSONNEL
e
e
becis
Masons
labourer
EQUIPMENT/MATERIAL
As Needed
Blocks
®
Mortar
“a
Mason’s Tools
“a
Corners/Rods for laying line
Laying Concrete Blocks
It is of utmost importance that block walls are laid straight and plumbed
vertically. The best method to ensure this is by using corner rods which are
plumbed with a spirit level and stabilized with braces.
The rods may be of timber with a straightened edge, or light metal such as
aluminum. The line is fixed and leveled horizontally about 3/16” or 4mm away
from the wall. The mason uses this as a guide keeping the gap constant by eye
sight. He should not try to build close against the line.
Some
ma-
LL
"sons
resort to using
a spirit level to
level
and
plumb
each row of block
especially at the corners to ensure that the wall is laid vertical and straight.
bal.
reyes
StSaeco
tt
-_
@
Meson
1. Laying block is one of the most
common tasks performed by a
mason.
2. The most effective method of laying block is to use a mason’s
line as a guide.
3. Laying block to a line requires the use of many repetitive activities such as:
e
Spreading mortar
Placing block
wy
~
°
=
—
w
w
oO
Oo
Soe
oo
£
=
iz
®
4. Now lets follow the procedure followed to lay block to a line.
5. First fix the masons line from corner to corner. In the case of the first course a
second line near the bottom edge of the block is required to plumb the first
course.
6. Safety note:
A line which fails to remain straight when pulled can cause serious injury to
people working on the line. Fix the line securely to the corners on guides.
=
sania he
{
L
Res,
eI
—f
Dew ac
7. Place the blocks along the line leaving enough space for spreading the mortar.
8. Next spread the mortar for bedding the first course.
9. Starting from the corner lay each block to the line gauging the cross joints.
@
10. The top end of the block should be level with the top of the line.
11. The clearance between the block and the line should be approximately 3/16" or
4mm.
12. Fill the cross joints solid.
13. For each subsequent course of blocks fit the line to the corners. Make sure that
the line is fixed to the same course height at each corner.
@
14. Place the blocks to be laid along the wall and spread mortar for the joint along
the top of the previous course.
15. Lay the blocks to the line taking care to regulate cross joints and
check the positioning of the top edge of the block with the mason’s line.
e
Lay block
©
Check line for level
and clearance
fi
o JK M7
VAR
>
d
@
©
16, Fill all cross joints and clear away all excess mortar.
e
Fill cross joints
e
Clear excess mortar
17. Repeat these procedures until you have constructed the block wall to the
specified height.
18. Practice laying block to the line until you feel you have mastered the skill.
Ell
O
ROOF
BJECTIVE
To install covering to dwelling in accordance with type and design indicated on
the drawing.
Function of Roof
The main function of a roof is to provide protection from the weather. In
our geographic location, the ability to resist the forces of hurricane is of utmost
importance.
Type of Roof structure
1. Timber Structure
This supports coverings such as:
e Sheets— zinc, aluminum (plain, troughed or corrugated)
e Shingles— wood, fiberglass, aluminum
e Tiles— clay, concrete
2. Reinforced Concrete Slab
This acts as both a structural element and cover.
We will focus on the construction of :
1. Timber roof structure supporting zinc or aluminum sheeting.
2. Reinforced concrete slab.
1. Timber Structures with Zinc/Aluminum Sheeting
P ERSONNEL
e Contractor or builder/supervisor
e Skilled carpenter or roofer
e labourer
EQUIPMENT/MATERIAL
T
OOLS/EQUIPMENT
(QUANTITY | ——_—‘ITEM/DESCRIPTION,
1
Carpenter’s saw
1
Hammer
L
Chisel
1
Rule
a
Long Tape
1
Cord line
MATERIALS =|
Battens/ Purlins
ITEM DESCRIPTION
Treated 1"x 2
(25 x 50mm.
Covering Materials
Hurricane Straps
50 x 50mm. 25 x 75mm. 50 x 100mm)
|/Sheets of zinc, aluminum
Wood
Wall Plate
2"x 2", 1"x 3", 2"x 4" timber
Treated
fillets
2" x 4" (50 x 100mm) timber.
|Twisted steel straps
Nails
As described in drawings
Screws
As described in drawings
Nuts & Bolts
As described in drawings, hold down bolts
©
heron
(a) With wall plate
=>STEP 1
>
Ensure
that
hold
down
bolts
are
cast
in concrete
belt
beam
at 4'-
0" (1200mm) centres with 2 1/2" (62mm) projection.
Timber Wall Plate
———_
Reinforced Concrete
Belt Beam
—__,]
Flat Washer
*
Coat
Under Nut
|
212 "(62MM)END PROJECTED
ABOVE CONCRETE IN BELT BEAM
_#
HOLD DOWN BOLTS
(é 4-0" INTERVALS
Concrete Block Wall
——*
A
7
STEP 2
(b) Without wall plate
Rafter support are accurately positioned and strapped to belt beam
formwork prior to pouring of concrete.
Rafter supports are installed to ensure that the angle iron do not protrude above rafter.
Establish desired pitch of roof using carpenter’s square, level and
cord line.
q 7]
|
tr
“1
1/4" x 1 1/4" x 1/4" (32x 32 x 6mm)
ANGLE IRON APPROX. 14" (350) LONG
CAST IN BELT BEAM AT EVERY RAFTER
—
@
e
Position and strap rafter support to belt bead form work prior to pouring of concrete. Rafter support are installed to ensure that the strap
does not protrude above rafter.
e
Establish desired Pitch of roof using carpenter’s square, level and
cord, to line out roof.
e
Bolt each rafter to hold down angle iron on top of belt beam using
3/8” (LOmm)dia. Bolts.
=
a
=
oe
"
>
2 No. 3/8" (10mm) DIA MS BOLTS
FOR MEMBERS 2" x 6" (50 x 150) & ABOVE.
1No. 3/8" (10mm) DIA MS BOLTS
FOR MEMBERS
“ANCHOR
7
|
;
o
3/8" (10mm) BOLTS
AND NUTS
2" x 4" (50 x 100)
STRIPS
a
ee
RAFTER SUPPORT&
=f
HURRICANE STRAP)
‘ik “\
1
»
2" x 4"(60 x100) OR 2" x 6"
\
— (60x 150) RAFTER
1" x 3* Battens §——
Laths nailed to rafters
Secured with twisted hurricane straps
&
1/2" x 10" Hold down bolts
i
a
x
pea
*
==
5r
5
e
6" CC load bearing wall
PITCHED ROOF
1:2" x 10" Hold down bolts
2" x4" Wall plate __6" C.C load bearing wall
r
FLAT ROOF (10% 08 Less)
=> STEP 2 cont’d.
e
e
Locate and position ridge board using temporary support, then by using an adjustable carpenter’s square, cut rafters to fit neatly with ridge
board.
Locate and notch rafters to obtain perfect fit on timber wall plate. It is
best to establish the outermost rafters first and then level and stretch
lines from the extreme locations. Intermediary rafters may then be cut
and fitted, ensuring conformity with the established lines.
e
The foot of the rafters should be accurately notched to fit neatly to the
timber wall plate.
=> STEP3
INSTALLING ROOF
e
COVERING
Battens (laths) or purlins are nailed or screwed in place at spacings
not exceeding 3'-8" (1100mm).
(Recommended at 2’6” for most construction).
Hurricane Strap
Fascia Board
——
i
Le eA
Blocking Board
j
RAFTER NOTCHED
Reinforced Concrete Belt Beam
e
Roof coverings may be purchased in full length of the span on either
side of ridge of a pitch roof.
e
The foot of rafters should be accurately notched to fit neatly to the timber wall plate.
After the roof structure is accurately established it may then be perma-
e
nently nailed and hurricane straps used to connect rafters to the wall
plate.
e
Use cord line to establish position of fascia board the cut vertically or at
right angles to rafter. If the sheets are in shorter length, then laps
should be a minimum of 8" (200mm) and 1 1/2" (37mm) corrugation
across.
Batten
\
Rafter
e
Ridge Board
Timber fillets should be used where ever the sheet is nailed or screwed
to
to
I
one
.
1/2
ed
the :purlin,
avoid
|
Corrugated roof covering
leaks.
REINFORCED
P
CONCRETE
ROOF
ERSONNEL
Contractor/ Building supervisor
Skilled mason
Skilled carpenter
Concrete batcher
Steel fixer
Labourer
T
OOLS / EQUIPMENT
All tools as listed before for carpenter, mason and steel fixer.
MI
ATERIALS
Form Work
2" x 4" (50 x 100mm) timber
1" x 3" (25 x 75mm) timber laths
5/8" (16mm) plywood metal or wooden props.
Reinforcement
1/2" (12mm) reinforcing steel bars.
3/8" (10mm) reinforcing steel bars.
Concrete
Cement, Washed sand, coarse aggregate size 1/2" - 3/4"
(12—20mm), clean water.
REINFORCED
P
CONCRETE
ROOF
ERSONNEL
Contractor/ Building supervisor
Skilled mason
Skilled carpenter
Concrete batcher
Steel fixer
Labourer
T
OOLS / EQUIPMENT
All tools as listed before for carpenter, mason and steel fixer.
MI
ATERIALS
Form Work
2" x 4" (50 x 100mm) timber
1" x 3" (25 x 75mm) timber laths
5/8" (16mm) plywood metal or wooden props.
Reinforcement
1/2" (12mm) reinforcing steel bars.
3/8" (10mm) reinforcing steel bars.
Concrete
Cement, Washed sand, coarse aggregate size 1/2" - 3/4"
(12—20mm), clean water.
Note:
a small slope
Reinforced Concrete roofs are usually installed flat or with
should be
Care
(pitch). This form of roof is excellent for resisting hurricane.
taken to ensure that:
a) the reinforcement used conforms to the specification,
h
b) the quality of the concrete is 1:2:4 minimum mix with just enoug
water
c) water does not settle on top of the roof slab.
Meron
=
STEP
1
slab. Form work
Construct and erect form work to support designed roof
Minimum
for belt beam and lintel may be installed at this stage as well.
concrete thickness 4" (100mm) . Allow for water drips at slab eaves.
= STEP 2
the design,
Prepare, cut, bend and install all reinforcement according to
ensuring correct spacings and laps.
= STEP 3
Batch and mix 3000 psi (1:2:4) concrete, pour
concrete around
vibrator
reinforcement. Compact and vibrate the concrete. A mechanical
should be used, or hand tamped if one is not available.
=> STEP 4
float to
The surface of the slab should be dressed using wood or steel
resist water penetration.
= STEP 5
wet freCover the exposed surface of concrete with paper or jute and
concrete.
quently for seven (7) days to ensure proper curing of the
= STEP 6
us defects
After ten (10) days remove all formwork and repair any obvio
in the exposed concrete soffit.
|
FLOORS
SOLID OR CONCRETE
FLOORS
F UNCTION AND DESCRIPTION
To provide safe support for the occupants and furniture of the dwelling. This
support form the ground and may consist of a hardcore spread and compacted on
stripped ground within the perimeter of the building plan. Reinforced concrete is
then spread evenly on top of the hardcore.
O
BJECTIVE
To provide a level, even and smooth floor with concrete.
P
ERSONNEL
e Contractor/building supervisor
e Mason
e Labourers
E
QUIPMENT / MATERIALS
EQUIPMENT
2
Large Trowel
2
Wheel Borrow
MATERIALS
1
|
Minimum
2000 psi concrete
Hardcore material, dump sand &
marl.
|
As required
Batter boards, screed & wooden
Steel fabric
rod
Q
Meernop
e
Strip topsoil within perimeter walls by (approx. (6”)150mm).
e
Place and compact
finished floor level.
e
Place steel fabric across floor area ensuring that it is elevated above the
compacted hardcore.
e
hardcore
material
up
to
4”
(100mm)
below
the
Place and level wooden screed boards at convenient spacing in order to
rod off and level the concrete ensuring a flat and level floor.
e
Prepare and mix concrete of minimum 2000 psi strength, transport in
wheel barrows, place compact and rod in line with screed board.
e
After completion of pouring and leveling, surface may be wood floated
or metal troweled to designed finish. At this stage colouring may be
added to the finished surface if desired.
FIXTURES
WINDOWS/DOORS/CUPBOARD/CLOSETS
On completion of
the structural enclosure of a dwelling,
fixtures such as
doors, windows, cupboards and closets are ready to be installed.
O
BJECTIVE
To install fixtures in a manner to provide security, utility and beauty.
Pasco,
e Contractor or builder/Supervisor
e Finishing carpenter/Joiner
E
QUIPMENT / TOOLS / MATERIALS
|
TEMS
i
~~ poors
|
DESCRIPTION
Interior and exterior
Jambs— metal or timber
Hinges, locks
WINDOWS
Full frame— aluminum
Glass louvre, wooden louvre, casement, french
CUPBOARDS
CLOSETS
Kitchen, bathroom
@
Meron
INSTALLING THE FRAME
Frames may be of wood or metal. Both timber and metal frames are
pinned to openings to provide and maintain rigidity and support to
e
door/window.
Squareness at corners is obtained with a carpenter’s square.
e
The
jambs are plumbed and straightness maintained with the use of
spacers until the pins are hardened in mortar.
HANGING THE DOOR
e
The door to be hung internally or externally is first fitted against
the installed jamb and cut where necessary, trimmed and dressed to
provide a neat fit with approximately 1/8"(3mm) surround except
for the bottom, where spacing should be 1/4” (6mm).
e
If the frame is metal, it is usually supplied from the manufacturers
with a hinge and stop.
If a timber frame, then hinges are located near the top and bottom
approx. 6”-8” (150-200mm) of the door.
e
Doors are then screwed in position, tested for accuracy, swing, fit,
e
Locks and bolts are then installed.
and adjustments, including trimming done to _ensure a proper fit.
Approximately
1/8” space between
door and frame
minimises
Saereomanpncoonsnaace
ir
@
WINDOWS
Framed Windows
If window frames are required then these are installed in similar manner as
door frames. At times windows may be supplied with hinged on the frame, if
not installation is similar to that of doors.
Full Framed Aluminum
The openings should be accurately squared and dressed, leaving minimum
installation space of approximately 1/8” (3mm) all around.
Windows are installed by plugging the walls and then screwing the frames in
position.
Window frame screwed to
dressed opening.
Cupboard Closets
These may be pre-constructed and installed on location, or installed in
position using frames and doors installation guide described above.
PLUMBING
O
BJECTIVE
To install water supply system to dwellings and wastewater disposal system
from the dwelling.
P ERSONNEL
e Qualified plumber
WATER SUPPLY SYSTEM
The supply may be provided by legally connecting to public
main using conduits (pvc, galvanized iron) 1/2°(12mm) or
3/4°(16mm) laid in trenches and at times casted in the concrete
walls of the dwelling.
WASTEWATER SYSTEM
Large size drain pipes (pvc mainly 4”- 6” or 100mm-150mm),
should be used to transmit wastewater from kitchen and bath
room to septic tank, and absorption pit, or the public sewer
main.
Pipes should be laid with minimal fall of 1:40 for 4” (100mm)
diameter pipes and 1:60 for 6” (150mm) diameter pipes.
‘
O
|
ELECTRICAL WORK
BJECTIVE
To provide safe electrical services to dwelling. In no circumstance should
electrical installation be attempted without employing the services of a qualified and certified electrician. All wiring conduits and fittings should be in
stalled by him.
P ERSONNEL
°
Certified electrician
@
FINISHING
RENDERING/PAINTING
D
ESCRIPTION
RENDERING
This is the application of one or more coats of cement mortar to the surface of a block or stone wall to provide an even and smooth surface. This
may be done for beauty or to provide water proofing to the wall. Forming corners and straight edges in mortar requires great skill and time.
Rendering may be done inside and outside, the standard form
being two coats of 1/2” (12mm) thick cement mortar.
APPLICATION
¢
Holes or hollows in wall should be filled and any projecting blocks
e
All loose dirt and dust must be cleaned from walls.
e
Walls should be well dampened before applying rendering.
e
Rendering should start at the top of the wall and work downwards.
e
A board should be placed at the bottom of the wall to catch any
mortar that drops. This mortar can be used again providing it is still
fresh.
e
Rendering should be applied evenly and to correct thickness. This
can be ensured by screeding and lining out with plumb line and
level prior to commencing rendering.
¢
Outside corners should be dressed by using straight edge boards.
These should be checked and provided by a skilled carpenter.
These should be fixed so that they project past the end of the walls
by the desired thickness of the screeding.
e
Finishing to wall may be done with a wooden float or metal float
depending on the desired texture.
or mortar in joints chiseled off.
@
WHEN TO RENDER
It is advisable to apply rendering after most of the walls are substantially
completed and initial settlement of building has taken place.
nearest
Approx. 1/8" thk. rendering |
[LS PRS
ort inal coat applied to
i
first coat (rough cast} ——=|
ms
fos
Slight movement in a building wall will result in cracks in the rendering,
it is best to wait until settlement has taken place.
3/8" thk. rough cast
—=— applied to blockwall
FORM
AGREEMENT
OF AGREEMENT
made this.............:00-0:-s::2se08 Gay! Ofer nent iREIN
BETWEEN
EMPLOYER
of
CONTRACTOR
of
FOR THE WORKS
SITUATE
eens cent teeters
SUPERVISING OFFICER (S.O.)........0:00:0eccee
cnneamgueecnnon enscenneet RENEE or other appointed by the Employer.
NOW
IT IS HEREBY AGREED AS FOLOWS:
Ds
For the consideration hereinafter mentioned the Contractor
will upon and subject to the conditions annexed hereto carry
out and complete the works described in the specifications
and/or Bills of Quantities and/or as shown on the contract
Drawings.
2s
The Employer will pay to the Contractor the sum of
or such other sum as shall become payable
hereunder at the time and in the manner specified in the said
conditions.
AS WITNESS the hands of the parties
hereto signed by the said Employer
sevecececomenenres Perera
In the presence of:
Name
AGAess
Description
cab geUPesWeee aes Te eeeeUT ss seeesrmEenReenesenenentd
—_aveseasiseasecccdeoenee supueveemasncapseonecssaasen -
— ..scsseeeeseeeeseeeeeee seveneecerensnesccensensees a
Signed by the said Contractor
ecweonaewen: +
eRes
cesses
ACATeSS.......ccecsencceeceerennenees san (ese
Description......-.ssecseessececsenseneee saStep
eewtea soreness tes
CONDITIONS HEREINBEFORE
REFERRED TO
Contractor’s obligation:
The contractor shall with due
diligence and in good and workmanlike manner carry out and
complete the works to the reasonable satisfaction of the S.O.
all in accordance with these conditions of contract together
with Architects drawings, specifications, schedules or other notes,
quotations etc. attached to this Contract.
Date for commencement ...............0.
0.0. :c cece cee cece eee eee ee eee
@ontract
epee
Date for completion
.......... cee cececeeee seen ceeeeeeee eens eceeeeees
Liquidated damages
ow. .....cesceecscseceeeseeeeneeet
eee eceeeeeeees
Defect
Liability period
.................cceceeeseeee
cee eeen teen renee
Payment Terms (esses
10.
secec eects eens nent ee eeeeeeeneeenenenenerens
Retention percentage
(see 7 above)
Performance
oo... cece ceeecececeeeceeeeeeeeeeeveneneneneees
i.
Bond
S.O. Instructions:
The
S.O.
may issue written
instructions which the contractor shall forthwith carry
out. If instructions are given orally, they shall forthwith
be confirmed in writing by the S.O.
The S.O. may without invalidating the contract, order
an addition to or omission from or other change in the
works or in the order or period in which they are to be
carried out and any such instruction shall be valued by
the S.O. on a fair and reasonable basis.
The $.0. shall issue instructions as to the expenditure
of any provision or prime cost sums before any such
work is carried out. These instructions shall be valued
on a fair and reasonable basis.
Instead of the valuation referred to in sub-clauses (ii)
and (iii) hereof, an inclusive price may be agreed
between the S.O. and the contractor prior to the
contractor carrying out any instructions such as referred
to in those sub-clauses.
11.
Contractors Representative:
The Contractor shall at all
reasonable times keep on the work a competent person in charge.
12
Statutory Obligations, Fees and Charges:
The contractor
shall comply with all notices
required by any statute, any
statutory instrument, rule or order or any regulation or by law
applicable to the works and shall pay all fees and charges in
respect of the works legally recoverable from him.
13.
Sub-Contracting:
The contractor shall not sub-contract the
works or any part thereof without the written consent of the
S.O. which consent shall not be unreasonably withheld.
The contractor shall be liable for, and shall
14. Insurance:
indemnify the Employer against any expense liability loss claim
or proceedings whatsoever in respect of:
Personal injury to or death of any persons (s);
Injury or damage to any property real or personal; as may
be associated with the execution of the works.
Without prejudice to his liability to indemnify the Employer, the
Contractor shall maintain and shall cause any Sub-contractor
to maintain Contractors All Risk, Third Party Liability and Public
Liability Insurances as are necessary to cover the liability of the
Contractor or Sub-Contractors.
15. Practical Completion — Defects Liability:
The .S.0.
pleted.
1.
16.
shall certify the
date when
in his opinion
the works have been practically com-
11.
Any defects, excessive shrinkages or other faults which
appear within the defects liability period and are due to
materials or workmanship not in accordance with the
contract shall be made good by the Contractor entirely
at his own cost unless the S.O. shall otherwise instruct.
111.
The S.O. shall certify the date when in his opinion the
Contractor’s obligations under this clause have been
discharged.
Payment— Interim Payments:
The S.O. shall if requested by the contractor at
intervals of four weeks calculated from the date for
commencement inserted in clause 2 certify interim
payments to the Contractor in respect of the goods on site
for the purposes of the works and any amounts either
ascertained or agreed under Clause 10 and the Employer
shall pay to the contractor the amount so certified
within 14 days of the date of the certificate.
11.
Provided the contractor shall have supplied all
documentation reasonably necessary for the computation
of the amount to be certified the $.0. shall 10 days
after the date of practical completion certified under
clause 15 (1) certify payment to the Contractor of ninety
five per cent of the total amount to be paid to the
contractor under the contract including any amounts
ascertained or agreed under Clause 10 less only the
amount of any interim payments made under sub-clause
hereof and the Employer shall pay to the Contractor the
amount so certified within 14 days of that certificate.
111.
Provided the contractor shall have supplied all
documentation reasonably necessary for the computation
of the amount to be certified the $.O. shall 10 days after the
date certified under Clause 15 (iii) issue a final certificate
certifying the amount remaining due to the due to the
Contractor or due to the Employer as the case may be
and such sum shall as from the 14" day after the date of the
final certificate be a debt payable as the case may be by the
Employer to the Contractor or by the Contractor to the
Employer.
17. Determination by Employer: The Employer may but not
unreasonably or vexatiously by notice by registered post or
recorded delivery to the Contractor forthwith determine the
employment of the contract under this contract if the
Contract shall make default in any or more of the following
respects that is to say:
i.
If the Contractor without reasonable cause fails to
proceed diligently with the works or wholly suspends the
carrying out of the works before completion;
ii.
If the Contractor becomes bankrupt or makes any
composition or arrangements with his creditors or has a
winding up order made or a resolution for voluntary
winding up passed or a Receiver or Manager of his
business is appointed or possession taken by or on behalf
of any creditor or any property the subject of a charge.
Provided always that the right of determination shall be
without prejudice to any other rights or remedies which the
Employer may possess.
18. Determination by Contractor: The Contractor may but not
unreasonably or vexatiously by notice by registered post of
recorded delivery to the Employer forthwith determine the
employment of the Contractor under the contract if the
Employer shall make default in any one or more of the
following respects that is to say:
If the Employer fails to make any interim payment due in
accordance with clause 7, after certification by the
8.0.;
ii.
If the Employer or any person for whom the Employer is
responsible interferes or obstructs the carrying out of
the works or fails to make the premises available for the
Contractor in accordance with clause 2;
If the Employer becomes bankrupt or make a composition
or arrangements with his creditors.
19. Arbitration: If any dispute or differences concerning this
Contract shall arise between the Employer or the S.O. on his
behalf and the Contractor, such a dispute shall be settled as per
the Arbitration Act.
20. Fluctuation: The fluctuations provisions of the C.L.C.
Standard Form of Contracts shall be incorporated into this
Contract.
BUILDING AND
CONSTRUCTION
INDUSTRY
LABOUR MANAGEMENT AGREEMENT
The following attachments contain copies of the Building & Construction
Industry’s Labour Management Agreement for a specific period (2021-2023).
the
THIS AGREEMENT (commonly known as the JIC Agreement) forms
between
latest in a series of agreements which commenced in 1956 and is made
rs Asthe employers in the industry represented by the Incorporated Masterbuilde
opersociation of Jamaica and the workers represented by the major trade unions
relaorderly
ating in Jamaica, with the specific intention to maintain sound and
tions within the industry.
This agreement contains:
°
°
*
Terms of wage agreement
Rate of pay per 8-hour day
Disciplinary guidelines
LABOUR MANAGEMENT AGREEMENT 2021 — 2023
Building & Construction Industry
PART Il - PERMANENT PROVISIONS
THIS AGREEMENT is made the 24th day of March 2021 between the
Employers’ Side of the Joint Industrial Council for the Building and
Construction Industry (being representatives of the Incorporated
Masterbuilders Association of Jamaica representing the employers in
the building and construction industry of Jamaica who are hereinafter
called the “Employers”) and the Workers Side of the said Council
(being representatives of the Bustamante Industrial Trade Union, The
Trade Union Congress of Jamaica and the National Workers Union of
Jamaica) (hereinafter called the “Unions”) WHEREAS in the interest of
sound industrial relations in the building industry the parties hereto
have agreed —
The following clauses of this Agreement numbered 3 to 48
shall form part of the permanent terms of employment of the workers
of the building and construction industry and shall remain in force until
varied by agreement between the Workers’ Side and the Employers’
Side of the Council and the expression “the Unions” used therein shall
mean the recognised bargaining representatives of the workers from
time to time.
3
Functions of Management
The Employers have the sole right, responsibility and
function to conduct their business and mange their operations in such
manner as they shall think fit. Accordingly each Employer has the
(1)
To maintain orderly labour relations.
(2)
To exercise their functions as defined in this agreement with
right in his sole discretion:
due regard to the welfare, speedy and efficient operation of
the building industry, as well as the welfare and best interest
of the workers.
(a)
(3)
To stabilise
employment.
rates
of
pay
and
other
conditions
of
(4)
To establish a formula for the prompt and fair disposition of
grievances, and
(5)
To ensure that works shall proceed smoothly
interruption and at the highest attainable efficiency.
(b)
without
NOW THIS AGREEMENT WITNESSETH as follows:
PART 1- RATES OF PAY AND TERMS OF WAGE AGREEMENT
1.
Rates of Pay and Retroactive Date
The wage rates to be paid by the Employers in the building
and construction industry with effect from the 1st day of February 2021
shall be the rates set out in the Schedule hereto.
2,
Terms of Wage Agreement
The rates of pay and the other terms and conditions of
employment established by this Agreement shall remain in force until
the 31st day of January 2023.
construction industry shall
otherwise) to make claims
for any change in the terms
other claim involving any
period of
(c)
(d)
(e)
(f)
(g)
provided in Clause 21. Claims for any changes desired after the 31st
day of January 2023 shall be made before the 31st day of October
to control and regulate the use of all equipment and other
property of the employer;
to introduce new or improved equipment, methods or
facilities and to change job procedures;
to
establish
working
schedules
and
to
make
work
assignments;
to hire new workers; to promote, transfer, lay off and recall
workers; to discipline and dismiss workers for just cause;
and to retire workers;
to establish new occupational classification:
(h)
(i)
to select supervisory personnel;
to have any part of his work performed by contractors or
(j)
to make rules and regulations which the Employer considers
necessary or advisable for the orderly, efficient and safe
conduct of his business.
sub-contractors;
The Workers in the building and
not be entitled (either through a Union or
for any increases in their remuneration or
and conditions of their employment or any
cost to the Employers in respect of the
their employment up to the 31st day of January 2023 except as is
2022.
to manage his business, works and construction sites; to
plan, direct and control his operations and the working force
including the days, times, methods and manner of working,
allocation of work and number of workers required in any
department or operation;
to determine the work to be done; to establish the methods
and rate of production and to change such methods and
rate;
4,
Classification of Workers
Where in the Schedule hereto any type of work is divided
into two or more separate classes levels or grades (Example: Level III
(Grade |), Level Il (Grade II) and Level | (Grade III) Carpenter/Joiner)
the determination of the worker's skill and his proper level (grade) will
be made by the Employer at the commencement of the worker's
employment on a job and if disputed by the worker shall be subject to
the Grievance Procedure. Every effort shall be made to have a Level
Three (Grade One) in each category. If there is no agreement on this
the normal Grievance Procedure mentioned above shall apply.
commencement of the next working day and he was not
instructed before 5:00 p.m. on the previous day not to
and actually reports for work at the
report
commencement of such next working day.
Fair Wages Clause for Task Workers
All Employers who are carrying out work on a task basis
must advise and ensure that their sub-contractors and task workers
keep proper books, make statutory deductions, payments and pay
rates of wages and observe conditions of employment not less
favourable than those laid down by this Agreement. In the case of
day workers, the sub-contractors must observe the daily rates and
also the various fringe benefits such as paid holidays, vacation leave,
5.
overtime, premiums, end of project bonus, etc.
In the case of work
carried out by task and paid for on a measurement basis, the rates
should be sufficient to allow workers to earn not less than the daily
rate plus benefits. The Unions holding bargaining rights shall be
supplied with the names and addresses of the sub-contractors on any
project on request.
Workers employed directly by a sub-contractor shall have
the right to union representation provide that they work under the
terms and conditions of this agreement.
Those contractors who employ sub-contractors be minded
ctors should be registered sub-contractors who will
sub-contra
that the
If a worker is requested to and does remain at the work site,
(b)
available to work, after the first four hours of a day, he will be paid a
full day's pay.
9.
Overtime
Except in the case of watchmen, overtime is defined as time
(a)
worked in excess of 8 hours per day Mondays to Fridays inclusive and
all work on Saturdays and Sundays.
Mondays to Fridays
(b)
Saturdays
(c)
6.
Functions of Union
The Unions have the right to exercise all the functions of a
(a)
trade union subject to the provisions of this Agreement and will
exercise such functions in accordance with trade union principles and
practices. Accordingly the Unions have the right:
(ii)
(iii)
Sundays
All work on Sundays will be paid for at double time, except
(e)
in the case of watchmen. A watchman will be paid at the rate of
double time for work done on his scheduled rest day.
to ensure that the agreed wage rates are paid and that the
other benefits and conditions herein specified are observed.
To protect the workers against arbitrary disciplinary action
through the Grievance Procedure.
To deal with grievances.
10.
11.
Public Holidays worked
All workers (except Watchmen) who work on official Public
Holidays on the instructions of their Employer will be paid at double
time on an hourly basis for all work on such holidays. Watchmen will
be paid an additional $557.62 for each Public Holiday worked by
them. This is not in addition to the premium under Clause 10.
consent of the Employer.
Union delegates shall be regular workers on the job on
(c)
represent the workers. Reasonable time off with pay will
they
which
be granted to authorised delegates to attend meetings with
management about labour disputes arising in their Employer's
business at their respective places of employment provided that
permission to attend to such business shall be obtained by each
delegate from his supervisor and shall be subject to the exigencies of
the Employer's work.
12.
Height Pay
Height Pay shall be payable if all the following conditions
exist:
The worker is working at more than 30 feet above ground or
(a)
floor level in such circumstances that there is the danger of a clear fall
of at least 30 feet, and
The worker is not protected by any wall, rail or other barrier
(b)
(temporary or permanent), except in the case of work on scaffolds.
The rate of Height Pay for each full hour (over threequarters of an hour shall be regarded as a full hour) of work at a
height, measured from the point at which the work is being done to the
nearest floor or to the ground shall be —
$6.07 per hour
between 30 feet and 60 feet
Normal Hours
The normal work week will be 40 hours consisting of 5 days
(Monday to Friday) of 8 hours each, except in the case of watchmen.
8.
Reporting Pay
A worker will be paid a minimum
(a)
although he is not taken on, if either:
(i)
Public Holidays not worked
Each worker who has worked for the same Employer on
both the normal working day prior to and on the normal working day
following each Public Holiday will be paid the normal single time pay
which the worker would have earned had the day not been a Holiday.
Except when dealing with a grievance under the provisions
(b)
of Clause 29 or attending a meeting with management, union activities
shall not be conducted on any Employer's premises without the prior
he
All work on Saturdays will be paid for at double time, expect
in the case of watchmen. A watchman will be paid at the rate of
double time for work done on his scheduled rest day.
The workers will work, if possible, reasonable overtime
(d)
whenever requested by an Employer so to do.
abide by the Joint Industrial Council (JIC).
(i)
Overtime shall be paid at time and a half.
of half a day’s pay
for each additional 30 feet
he is specifically instructed to report for work and actually
reports for work at the time he is instructed to report or
he is working on a job in the ordinary course of which he
would be expected to report for work at the
2
$7.39 per hour
20% of their single time rate for such work, including Saturdays,
Sundays and Public Holidays.
This premium shall not rank for overtime pay for Public
Holidays (whether worked or not), sick leave or in the calculation of
any other premium or fringe benefit.
18.
Leader’s Rate
Any worker who is designated by the Employer as a charge
hand or leading hand and who is placed in charge of a working crew
13.
Depth Pay
Workers who work in excavations in which the shortest
horizontal measurement is less than the depth of the excavation shall,
where the depth where the worker is working exceeds seven feet, be
paid a premium called “Depth pay” at the following rates.
between 7 and 10 feet
between 11 and 16 feet
or gang, and who also performs work in his regular job classification,
shall during that time be paid a ‘leader's rate” of $29.58 an hour, in
addition to his regular rate of pay. Craftsmen or tradesmen working
with helpers or assistants are not a crew or gang for this purpose.
$5.68 per hour
$5.68 per hour
19.
and an additional $4.66 in respect of
each additional 6 feet or part thereof
entitlement shall be one day for every 20 normal working days worked
by him but not more than 18 days in respect of each year.
for each hour (over three-quarters of an hour shall be regarded as a
full hour) during which they work at such depth.
14.
Holidays with Pay (Vacation)
(a)
Every worker will be granted holidays with pay in
accordance with The Holidays with Pay order 1973 except that the
(b)
Each worker who has been permanently employed with the
same Employer for between five (5) and ten (10) years will be granted
one additional normal working week's holiday with pay. A worker's
employment with a particular Employer shall not be considered to be
continuous unless such worker has actually worked for such Employer
for at least 200 days in each calendar year (Januaryto December).
Working in Water Pay
Workers who are physically working in either:
(a)
permanent water with a static water level (e.g. the sea or
swamp) of up to 3 feet in depth, or
(b)
temporary flood water for more than one hour,
(c)
Each
same employer
working week's
Employer shall
shall be paid a premium called “Water Pay” at the rate of $8.54 an
hour for the duration of the contract for each full hour (over threequarters of an hour shall be regarded as a full hour) during which they
are physically working in such water. This premium for working in
permanent water with a static water level of over 3 feet in depth shall
be negotiated having regard to the circumstances in each case.
worker who has been permanently employed with the
for over ten (10) years will be granted four (4) normal
holiday pay. A worker's employment with a particular
not be considered to be continuous unless such
worker has actually worked for such Employer
for at least 200 days in
each calendar year (January to December).
20.
(a)
Sick Leave Pay
Sick Leave with pay will be granted in accordance with the
Holidays with Pay Order 1973 except
that the entitlement shall be one day for every twenty (20) normal
working days worked by the worker but not more than twelve (12)
days in respect of each year.
15.
Over Water Pay
Workers shall be paid a premium called “Over Water Pay” of
$7.12 an hour for the duration of the contract for each full hour (over
three-quarters of an hour shall be regarded as a full hour) during
which they are actually working over water which is more than 4 feet
deep from the static water level provided this shall not apply to work
done on or from a permanent fixed platform. This premium shall not
(b)
Any unused portion of sick leave not claimed for during the
year shall be paid to the worker.
rank for overtime pay for Public Holidays (whether worked or not),
vacation leave, sick leave or in calculation of any other premium or
fringe benefits. A worker shall not be entitled to this premium as well
21.
New Job Classification
An Employer may require the establishment of new and
different job Classifications other than those listed in the Schedule
hereto PROVIDED HOWEVER that no such new and different job
classifications shall be put into effect by an Employer unless and until
that Incorporated Masterbuilders Association gives notice in writing to
as Height Pay and/or Working in Water Pay but shall be entitled to
whichever is highest.
16.
Subsistence And Travelling Allowance
A worker who is normally employed by an Employer in or
around the town or city where he ordinarily lives and who is requested
by the Employer to go to and work at some other place at such a
the Joint Industrial Council of the proposed new and different job
distance that the worker cannot reasonably return home each night
classification and of the proposed rate or rates to be made applicable
thereto but if no objection in writing is made to the proposal by the
Unions within fourteen days of the giving of such notice they shall be
treated as effective at the expiration of the said period of fourteen
days. If however the Unions tender an objection to such proposals
both sides of the Joint Industrial Council agree to discuss the same.
In any discussions between the Unions and the Employers on such
proposals, they will act in good faith in considering them and the rate
or rates to be applied to any such new and different job classifications
shall be set by reference to and in the most proper relationship to
other rates paid for comparable jobs.
will be provided with accommodation by the employer or in lieu of the
accommodation be reimbursed a subsistence and travelling allowance
of $5,500 per night. There will be an additional 10% on subsistence
for the following areas: the North Coast from Monetgo Bay to Ocho
Rios, Negril, Mandeville, Ewarton, Nain, Port Antonio and Port Maria.
17.
Night Premium
Workers who are required by their Employers to work
between 6:00 p.m. and 6:00 a.m. (except Watchmen) and are not
entitled to overtime pay for such work, will be paid a night premium of
3
Redundancy payments shall be granted in accordance with
and subject to all the conditions set out in The Employment
(Termination and Redundancy Payments) Act and all Regulations and
Orders made thereunder expecting that the computation thereof shall
22.
Seniority
In matters relating to promotion, demotion, transfer, lay off,
termination of employment and rehiring the following principles shall
be on the following basis:
govern:-
(a)
It is the responsibility of the Employer to maintain the highest
level of efficiency; therefore the Employers must be the ones to judge
the requirements of any job and of the ability of any worker or
candidate for employment to fulfil the requirements of any job. In
exercising this judgement, skill, competence, efficiency and merit of
the workers or candidates shall govern.
intended
to
Less than one year
One year through 5 years
None
2 weeks’ pay plus 2 weeks’ pay for
each year of service over one year.
10 weeks’ pay plus 3 weeks’
pay for each year of
service over 5 years.
10 years through 15 years 25 weeks’
pay plus 4 weeks’ pay for each year
of service over 10 years.
45 weeks’ pay plus 5 weeks’
pay for each year of service
over 15 years.
70 weeks’ pay plus 7 weeks’
pay for each year of
service over 20 years.
15 years through 20 years
investigation through the Grievance Procedure.
Construction Employment Premium
The provisions of this clause are
Redundancy Payment
5 years through 10 years
Where, in the judgement of the Employer, two or more
(b)
workers or candidates are equally suitable in all respects for
promotion or retention, the worker with the longest continuous service
with the Employer shall be given preference.
If a worker has good reason to believe that he has not been
(c)
given fair consideration, he or she may present his or her case for
23.
Number of Years of
Continuous Service
Over 20 years
more
effectively secure that work within the Industry proceeds smoothly
without interruption and at the highest attainable efficiency.
Accordingly the workers within the Industry and the Unions undertake
to use their best endeavours to ensure that there will be no strikes,
slow down or other interference with work on any project.
Employment in the construction industry is by nature temporary which
invariably results in workers being unable to qualify for Redundancy
payments, even after many years employment. In light of this the JIC
Labour Management Agreement had since 1975 included a provision
of 15% which was subsequently increased in 1989 to 16% paid on
basic single time rate of the total hours worked. This was to be paid at
the end of the worker's employment and was entitled End of Project
Bonus. This method of compensation will be discontinued henceforth.
The payment previously known as End of Project Bonus will be
replaced by the Construction Employment Premium which will be 16%
paid on and included in the basic single time rate of the total hours
worked. For the avoidance of doubt the Construction Employment
Premium will be added to and paid with the basic single time rate and
will be subject to the following conditions:
(a) The unions agree to co-operate in maintaining a high standard of
productivity and in controlling absenteeism.
The Construction Employment Premium shall be paid to
(b)
each worker including task workers with their regular payments.
(c) Any dispute regarding the amount or payment or non-payment of
any Construction Employment Premium shall be submitted to the
Grievance Procedure.
(d) The
Construction
Employment
overtime.
24,
Premium
is not payable
on
25.
No Strikes No Lockouts
There shall be no strikes, slowdowns or other work
stoppages or interference with work or production and the Unions
agree that they will not authorise, sanction, approve, instigate or assist
any of the same. An Employer will not lock out his workers.
26.
J.L.C. Constitution
This Agreement shall
be
read
conjointly
the
it.
Duties of Delegates & Unions in Unauthorised Strike
If any strike, which is contrary to the provisions of the
preceding clauses, shall occur all Union delegates, stewards and
other representatives amongst the workers and the officers of the
Union shall in good faith use their best endeavours at all times during
such strikes to persuade all workers to resume normal work.
27.
Equipment to be Maintained During Strike
The Unions agree that if an Employer so requests sufficient
workers will continue to work during any strike as are needed to
maintain and protect property and equipment from damage or
deterioration and the Unions agree to direct and authorise sufficient
workers so to do.
28.
29.
Grievance Procedure
All complaints, grievances and disputes concerning
(a)
alleged violation of or non-compliance with this Agreement
concerning the conditions of employment of the workers (but
including any desired or proposed changes in this Agreement nor
demands for increase of pay or otherwise involving cost to
employers) shall be submitted to the following procedure:
Redundancy Payments
with
Constitution of the Joint Industrial Council and in no way supersedes
any
or
not
any
the
FIRST STEP:
A worker may present his grievance or complaint
to his Supervisor within not more than three working days after the
alleged incident or incidents which gave rise to the same or discovery
shall, with effect from 1s‘ April 1978 be paid wage rates ten percentum
higher than the rates set out in the Schedule hereto:
(b)
For the purpose of this clause “Special Projects” are:
of the grievance PROVIDED that grievances arising out of discharged’)
and dismissals shall be initiated in the Second Step. The aggrieved
High rise buildings of more than 6 floors (including the ground
floor)
worker may be accompanied by or present his grievance through his
Union delegate if he so desires. If the disposition of the complaint,
grievance or dispute by the Supervisor in this First Step is not
satisfactory then the matter may be taken up under the next Step.
(ii)
(iv)
SECOND STEP:
In case the disposition under the First Step is not
satisfactory, the worker involved may present his complaint, grievance
then,
THIRD STEP:
The written grievance may be referred by either
the Employer or the Union to the Council within not more than
fourteen working days after the disposition under the Second Step.
dams.
(vi) Embassies
32.
Premium Industries
(a)
The owners of certain industries (known colloquially as
“Premium Industries”) have agreed with one or more Unions that they
will stipulate with any contractors engaged by them to do certain
construction work that they should pay specific rates of pay and
accord particular fringe benefits which are higher than those agreed
by the Joint Industrial Council. Nothing in this Agreement is intended
to prevent any Contractor from paying any specific rates and
according particular fringe benefits which may be so stipulated.
(b)
FOURTH STEP: _ If no solution is reached in the Council either side
shall have the right to require within not more than fourteen working
days of the termination of the negotiations in the Council that the
matter be placed before a suitable independent and mutually agreed
Industrial buildings or plant within the plant compounds of
one of the alumina or bauxite companies.
(ii) Cement factories
(iii) Oil refineries
(iv) Electricity generating stations for Jamaica Public Service
arbitrator whose decision shall be final and binding on all parties. The
a disposition is not made
in this time the grievance may be carried
forward into the next Step.
(c)
Any grievance which is not taken up or pursued within the
time limits mentioned
above shall be regarded
as having been
abandoned.
30.
Dismissals
lf an Employer shall dismiss a worker and the justification of
the dismissal shall have been arbitrated and the arbitrator shall have
found that the dismissal was not justified and the Union shall have
demanded compensation and/or reinstatement for such worker and no
agreement thereon with the Employer shall have been reached and
such dispute has been negotiated at the Ministry of Labour under the
Chairmanship of one of the Conciliation Officers of the Ministry and no
agreement shall have been reached then and only in these
circumstances, the Unions, the Employer and the workers shall be
relieved from Clause 25 hereof and the workers shall be free to strike
and the employer to lock out in respect of such dispute.
31,
(a)
Special Projects
Workers engaged in the construction of Special Projects
The following have been recognised as Premium Industries:
(i)
terms of reference to be placed before the arbitrator shall be mutually
agreed.
(b)
At each step, the Employer's representative will consider
and give the dispositions provided for under this Grievance Procedure
within five working days after the presentation of such grievance and if
dredging
The construction of shipping ports, fishery terminals,
wharves and warehouses at ports throughout Jamaica.
(v) Highways and bridges associated with major highways, and
or dispute to the site manager or site engineer on which he is working
within five working days after the disposition of the same by the
Supervisor or in the case of a discharge or dismissal within seven
working days of the discharge or dismissal. The aggrieved worker
may be accompanied by and present his grievance through his Union
delegate or a representative of the Union who is not one of the regular
workers of the Employer if the Union so wishes. If the disposition of
the grievance by the manager in this Second Step is not satisfactory,
Hotels with 130 rooms or more
(iii) Reclamation of land from the sea, rivers or swamps by
Co. Lid.
(c)
The Council agrees that the construction of the following
facilities.
Airports and Airdromes
Naval Installations
Nuclear Stations
Military Camps and Installations
Dry Docks
shall be regarded as premium undertakings and accordingly rates of
pay and fringe benefits which are higher than those agreed by the
Joint industrial Council shall be applied thereto. This provision shall
however only apply to contracts covering such installations or
facilities.
33.
Voluntary Check-Off
The Employer shall make deductions for union dues for any
of the Unions who are signatories to
this Agreement and which has been recognised by the Employer as
the sole bargaining agent for the workers on any particular building
site, from the wages of the workers who authorise the Employer to do
so in writing in such form as the Employer may from time to time
approve and will pay over the same to such Union once per month.
The Unions undertake that no interference or coercion will be
exercised against any worker to give any such authority and that any
such authority may be revoked at any time by any worker by notice in
writing to the Employer.
Government Training Programme
The rates of pay, premiums and other fringes under this
Agreement shall not apply to workers employed or engaged under or
in connection with the Human Employment and Resource Training
Programme or under the provisions of any other statue or
Governmental policy promoting the education and/or employment of
people in Jamaica.
34.
35.
Insurance
Each worker will be provided with insurance coverage in
(a)
accordance with the Standard Form of Building Contract which
requires that the Employers and the Contractor take out appropriate
Employers Liability Insurance for coverage against personal injuries or
death arising out of or caused by the carrying out of their duties on the
site and also in accordance with the terms and conditions of the
oh
Pipe Work
This premium
laying and jointing drain
in trenches. This does
other premium or fringe
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
Drain Pipe Work
38.
Lay Off Notice
Two weeks’ Notice verbal or writing or payment in lieu of
notice shall be given for layoffs of a permanent nature, to
workers who have completed four weeks of continuous or unbroken
service.
39.
Laundry Allowance
The basic wage now includes a laundry allowance as was
agreed in the Labour Management Agreement for 2001-2003.
40.
Uniform Allowance
Uniforms shall be provided for regular workers who are
employed for more than one year and who:
Back brace
First aid kit
Fire extinguisher
Proper ladder/scaffolding
Sanitary facilities
Potable water
Safety helmets
Hard boots/water boots
Respirators
Gloves
(11)
Eye protection
(12)
Ear protection
42.
Identification Cards
Each worker shall have and carry a National Identification
Card on the job site. Where and when identification is required for
constant display the employer shall provide an appropriate carrying
case.
43.
applies only to workers who are physically
or sewer pipes of 30 ins. in diameter or over,
not rank for overtime or in calculation of any
benefits:
$11.39 per hour for duration of
agreement
$11.39 per hour for duration of
(b) Sewer Pipe Work
agreement
is to be paid to workers who
rate
normal
the
‘An additional 40% above
line.
asbestos
or
lines
sewer
work in active
(a)
are truck drivers
are heavy duty operators
(1)
(2)
36.
$850.02 per day in the second year
are asphalt workers
(c)
(d)
Provision of Safety Gears
Each worker will be provided with the relevant item of safety
equipment from the following list when it is deemed by the Employer
to be appropriate to the particular task that the worker is required to
carry out.
Each worker shall be covered on and off the job under a
(b)
insurance policy for $832,500.00 with provision for double
Life
Group
indemnity in the case of accidental death provided that the worker has
been employed for at least three (3) months by the same Employer.
$809.54 per day in the first year
form part of the garage staff
(b)
41.
insurance policy.
Overtime Meal Allowance
Workers who have been requested to work overtime after
the normal working pericd shall be provided with a cooked meal or in
lieu of the cooked meal, be reimbursed a Meal Allowance subject to
the qualifying period of two hours’ work after normal working time as
follows:
(a)
Heat Premium
The following workers shall be entitled to a Heat Premium
of:
$23.76 per hour for year 1,
and
$27.23 per hour for year 2
when required to work with hot asphalt:
Asphalt Distributor Operator, Bituminous Paving machine
Operator, Bituminous machine Screed Operator, Bituminous mixing
Plant Operator, Labourer (Asphalt Bituminous) and Luteman (Asphalt
Bituminous), Drivers and sidemen on trucks transporting asphaltic
concrete hot mix. Workers who are required to work with fibreglass
are also entitled to this premium.
44.
System Builders
A special premium of 5% above the rates of the Joint
Industrial Council shall be paid to workers employed in pre-cast or insitu System Building operations but excludes those workers involved
in the infrastructure works.
45.
site
Health & Safety Committee
A Health & Safety Committee shall be established on each
by the
Employer
nominating
two
workers
and
the
Unions
nominating two workers and from this number a Chairman shall be
per hour
appointed. If there is no Union representative the Employer shall
appoint persons to carry out the relevant duties.
46.
Trainee Operators
There shall be a total training allowance of $227.62 per hour
47,
Training of Union Delegates
It is agreed that all Delegates are to be trained within the
shortest possible time.
48,
Flexi-Time
It is agreed fo look at the maiter of flexi-time.
49.
Safety Manual for the Building & Construction Industry
Signed for:
Workers Side:
Signed for:
on behalf of B.L.TU
on
i”
The Safety Manual for the Bullding and Construction
Industry, and its requirements, now forms part of the requirement for
the Labour Management Agreement as of February 1, 2010. Each
worker is to be provided with a copy of the Safety Manual and shall
sign acknowledging receipt of same.
50.
Stakeholders Meeting
That there shall be a stakeholders (Union/Management)
meeting after the commencement of work on projects, undertaken by
members of the JIC involving main contractors and sub-contractors for
any project exceeding six months and employing over 50 workers.
This meeting should be held within 30 days upon commencement of
the project.
THE SCHEDULE
ANNEXED
behalf of N.W.U.
on behalf of T.U.C
Witness:
Ae
Dated this 29% day of March 2021
HOURLY RATES OF PAY
40 Hours Rates
(1 Feb. 2021 to 34 Jan. 2022
42.2021 to 34.1.2022 (+5%)
Effective 1.2.2021 to 31.1.2022 (+5%)
3
to 25 tons
to 26-39 tons
to 40-75 tons
76-125 tons
, Power Plant & Air Track
Screeder & Finisher
to 24 tons
tons
-80 tons
&
tons
Cars, pickups, Jeeps, Trucks
up to 10 tons
41-20 tons
20-39 ton
40 tons & over
to 1-
to
30
1-40
1-50
20 tons
tons
tons
tons
End Loaders:
to 10 tons (910-930)
4-21 tons (950-960)
32 tons (966)
tons
using
and
ll
Breaker, rock
and
Effective 1.2.2021 to 31.1.2022 (+5%)
1
1
Electricians
Weekend Overtime Rates
Overtime Rates
(Single
992.48
1,035.77
75.65,
23
1,061.10
15
4,061.10
714.79
1,323.31
1,381.02
4
53
31
1,414.81
192.20
414.81
05
797.53
7 40
20
923.24
691.10
701.34
627.49
652.82
668.68
38
1,116.53
1,172.36
1
:
921.46
935.08
836.65
870.43
891.58
14
17
982.32
924.23
4.60
4,025.87
1
47
1,367.83
4,440.29
1,508.02
956.40
HOURLY RATES OF PAY (1 Feb. 2021 to 31 Jan. 2022)
40 Hours Rates (Single)
Weekday
Effective 1.2.2021 to 31.1.2022 (+5%)
Categories
Maintenance Man (Field Service Minor
Repairs)
Mason
Mixer Operator
up to 21/44
over 21/14
Painter
Pilling Hand/Hammerman
Piling Winch Operator
Pipe Layer
Plant Mechanic
Light Vehicles - pickups, cars, jeep, mixer
Level 1
(Grade 3) |
Level 2
(Grade2) |
=
500.00
500.00
¥
465.06
597.84
536.09
490.19
521.81
551.41
539.41
656.49
599.80
=
-
compressor
Heavy Duty
Power Trowel Operator
462.51
606,55
:
Plumber
477.48
Pump attendant
Roller Operator (Hand Vibrating self
propelling, Asphalt Bituminous)
Roller (vibratory smooth/rubber tyres)
Rubber-tired tractor operator with
attachments
Sand Blaster
Scaffolder
Sheeter
Sheet Metal Worker
Sideman
Steel Erector! Rigger
Steel Fixer/Bender
Stresser
Tiler
Trailer Attendant
Trench Machine Operator
Welder
Winchman
654.49
607.32
=
=
672.37
=
646.56
=
646.56
=
=
601.37
=
=
=
=
599.39
781,40
622.20
671.51
874.28
-
598.07
784.33
-
566.52
675.61
617.44
Level 2
(Grade 2)
Level 3
(Grade 1)
Level 1
(Grade 3)
846.32
785.34
=
:
869.44
=
862.08
=
=
862,08
=
801.83}
773.07
693.23
=
633.86
674.75
713.03
697.51
848.91
775.60
-
775.07
1,010.43 |
804,56
-
868.34
1,130.54 |]
-
732.57
873.64
-
797.43 |
1,045.77
823.25
-
1,033.43 |
1,347.25 |
1,072.75
976.76 |_
-
1,157.78
1,507.37
1,164.85
-
=
867.00
=
:
561.14
560.09
-
=
-
725.62
724.25
-
-
967.49
965.67
=
=
-
476.97
510.56
=
-
=
-
616.77
660.21
-
-
822.37
880.28
=
518.02
-
574.05
700.86
-
564.14
549.29
509.99
-
=
602.07
=
631.45
-
561.00
646.56
+
-
669.86
742.30
906.29
729.49
710.29
659.47
778.53
-
816.54
-
748.01
862.08
-
-
893.14
1,208.38
972.85
947.06
879.29
1,088.71
989.72
1,038.05
=
-
556.51
433.84
623.76
532.48
687.51
642.93
719.63
561.00
806.59
688.55
889.02
831.37
959.51
748.01
1,075.45 |
918.06
547.73
456.60
-
550.28
630.65
456.60
659.78
587.89
433.84
645.67
725.36
674.77
-
708.27
590.43
-
714.57
815.50
590.43
853.17
760.21
561.00
834.92
937.97
872.56
-
944.36
787.24
-
948.76 | _ 1,113.22
1,087.34
787.24
1,137.56 | 1,250.63
1,013.61 | 1,163.40
748.01
-
applicable only to the construction site operations
because of the peculiar nature of this particular
Work in excess of 15 hours per shift
for other industries or business.
industry and is not to be regarded as a precedent
will attract overtime.
1" year - $24,319.71 per week; Overtime @ $349.43/hr.
per week; Overtime @ $377.38/hr.
**
New Rates to be paid not later than Pay week commencing April 5, 2021.
Outstanding payments to be made as early as possible but not later than pay week commencing May 3, 2021.
fons
>
1,128.44
*
=
1,047.12
=
1,159.26
650.25
N.B. The Council agrees that the 15 hour shift is
The agreed rate is the hourly rate. All other rates are calculated from the hourly rates.
The new base rates are inclusive of 16% Construction Employment Premium.
Payment for special and premium projects will be calculated on basic rate minus 16% Construction Employment Premium.
When only two rate are shown for a category, it means that there is no level (grades) in that category for which
no level (grade) is shown.
In case of work carried out by task and paid for on a measurement basis, the new task rate should reflect the new
wage rates set out in the above schedule, by adjusting the labour rate content of the task rate by the percentage increase
for the same category of work.
6.
1,030.76
924.30 |
845.15
899.67
950.71 |
930.01
1,131.88
1,034.14 |
=
exceeding 15 hours per shifts (including
Saturdays and Sundays)
5.
Level 3
(Grade 1)
-
Watchman - per week of6 shifts not
2" year - $26,265.29
Level 2
(Grade 2)
502.86
:
500.01
-
Steel bending/cutting machine operator
Level 1
(Grade 3)
Effective 1.2.2018 to 31.1.2019 (+5%)
-
433.84
‘Self-propelied Scraper Operator
Level 3
(Grade 1)
=
-
Weekend Overtime Rates
Overtime Rates
Effective 1.2.2021 to 31.1.2022 (+5%)
It was agreed that the Incorporated Masterbuilders Association of Jamaica would advise their Members
that the
Unions should have access to all projects undertaken by them.
ts
Note that in keeping with the HEART
8.
Therefore Grade 1 will now be Level 3, Grade 2 - Level 2 and Grade 3 - Level 1.
As per Jamaican Law all workers have the right to join a Trade Union of their choice.
Trust/NTA Certification of workers, grades have now been changed to Levels.
1,185.37
1,108.50
9.
be allowed access to the work site upon the
twas agreed that the Unions whose signatures are affix to this agrrement
presentation of a signature I.D.
HOURLY RATES OF PAY (1 Feb. 2022 to 31 Jan. 2023
Wee
40 Hours Rates
Effective 1.2.2022 to 31.1.2023 (+8%)
1
558.48
, Power Plant & Air Track
Screeder & Finisher
to 24 tons
tons
4-80 tons
tons
&
Cars,
up to
11-20
20-39
40
pickups, Jeeps, Trucks
10 tons
tons
ton
over
1-
1,429.17
4,491.5
4
645.01
1,145.99
68
1,145.99
771,97
498.81
886.23
746.80
886.23
99
666.10
699.
734.37
771.09
577.21
585.7
52.
545.24
to 25 tons
to 26-39 tons
to 40-75 tans
76-125 tons
41,071.88
1,118.63
945.70
731.34
Screed
Effective 1.2.2022 to 31.1.2023 (+8%)
Level 3
Effective 1.2.2022 to 31.1.2023 (+8%)
Level 3
4
Level 1
Level 2
828.92
865.07
Distributor
Electricians
Weekend Overtime Rates
Overtime Rates
764.14
802.41
842.53
884.67
706.85
861.34
904.39
949.61
09
46.39
757.41
677.69
705.05
i
.
i.
722.18
615.32
578.94
795.68
748.62
813:
856.81
902.19
62
.09
052.57
107.94
166.63
-50
774.68
4,403.42
1,477
0
1
1,628.
4,032.91
43
‘7.60
16
29.1
731.47
785.68
.60
974.89
1,047.58
1,126.13
AS
1
961.32
1,189.64
é
1,121.99
to
-30
-40
1-50
2
20 tons
tons
tons
tons
End Loaders:
to 10 tons (910-930)
4-21 tons (950-960)
32 tons (966)
tons
Labourer
other
Paving Breaker, rock
and
tools
4
1,317.47
1,383.46
1,452.
HOURLY RATES OF PAY (1 Feb. 2022 to 31 Jan. 2023)
Categories
Maintenance Man (Field Service Minor
Repairs)
Mason
40 Hours Rates (Single)
Weekday Overtime Rates
Weekend Overtime Rates
Effective 1.2.2022 to 31.1.2023 (+8%)
Effective 1.2.2022 to 31.1.2023 (+8%)
Effective 1.2.2022 to 31.1.2023 (+8%)
Level 1
(Grade3) |
Level 2
(Grade2) |
:
614.92
514.29
Mixer Operator
up to 21/14
over 24/14
-
Painter
Pilling Hand/Hammerman
Piling Winch Operator
Pipe Layer
Plant Mechanic
Light Vehicles - pickups, cars, jeep, mixer
compressor
Heavy Duty
Power Trowel Operator
Plumber
Pump attendant
Roller Operator (Hand Vibrating self
propelling, Asphalt Bituminous)
Roller (vibratory smooth/rubber tyres)
Rubber-tired tractor operator with
attachments
Sand Blaster
Scatfolder
Self-propelled Scraper Operator
Sheeter
Sheet Metal Worker
Sideman
Steel bending/cutting machine operator
Steel Erector/ Rigger
Steel Fixer/Bender
Stresser
Tiler
Trailer Attendant
‘Trench Machine Operator
Welder
Winchman
673.19
504.19
536.71
-
Level 1
(Grade 3)
665.03
-
Level 2
(Grade 2)
Level 3
(Grade 1)
795.16
-
713.03
870.50
651.97
694.03
:
-
Level 1
(Grade 3)
:
886.71
-
514.29
567.17
624.67
663.03
733.41
807.77
886.71
478.35
-
554.82
675.25
616.94
-
691.58
-
618.55
-
717.44
873.16
797.76
=
894.28
-
824.74 |
-
-
-
-
-
-
475.72
623.88
-
616.51
803.73
639.97
690.69
899.26
=
615.16
806.74
-
797.22
1,039.30 |
827.55
491.13
=
582.71
517.23
694.97
=
635.08
-
753.50
668.83
446.24
514.29
572.41
446.24
563.38
=
469.64
=
Watchman - per week of 6 shifts not
exceeding 15 hours per shifts (including
Saturdays and Sundays)
Work in excess of 15 hours per shift
will attract overtime.
1 year - $24,319.71 per week; Overtime @ $349.43/hr.
2"° year - $26,265.29
551.41
Level 3
(Grade 1)
per week; Overtime @ $377.38/hr.
577.18
576.09
490.60
525.15
532.82
720.89
580.25
564.99
524.56
649.50
641.58
547.69
566.00
648.67
469.64
678.63
604.69
446.24
:
590.45
:
619.27
707.16
661.30
664.12
746.09
694.05
-
:
577.03
:
665.04
:
740.19
577.03
728.51
=
607,30
~
-
893.15
1,162.84 |]
898.60
-
746.35
744.95
634.40
679.08
689.00
932.18
750.33
730.59
678.31
839.86
829.63
708.22
731.90
838.80
607.30
877.54
781.93
763.50
:
800.78
:
914.42
855.12
858.77
964.77
897.49
577.03
N.B. The Council agrees that the 15 hour shift is
applicable only to the construction site operations
because of the peculiar nature of this particular
industry and is not to be regarded as a precedent
for other industries or business.
-
-
Level 2
(Grade 2)
Level 3
(Grade 1)
1,060.21
-
950.71
1,160.68
=
869.29
925.37
=
-
977.87 |
1,077.04
956.59
1,164.22
1,063.68 |
-
=
1,192.38
-
-
-
820.21
1,075.65
-
1,062.95
1,385.74 |
1,103.40
|_1,190.86
1,550.44
-
846.77
-
1,004.66 |
891.77
1,198.13
-
769.38
:
886.71
:
986.92 |
769.38
971.35
Ss
809.73
-
995.13
993.26
845.86
905.43
918.66
1,242.91
1,000.44
974.12
904.44
1,119.82
1,106.18
944.29
975.87
1,118.40
809.73
1,170.06
1,042.57
769.38
-
|
|
|
|
|
|
|
1,018.00
:
1,067.71
1,219.24
1,140.18
1,145.02
=
=
1,286.36
1,196.64
=
JOINT INDUSTRIAL COUNCIL DISCIPLINARY GUIDELINES
Type of Offences
A,
Fighting on the job
Removal of Company's property off compound
2,‘
[without permission
Insubordination - Failure to carry out job related
4st Scheduled
Offences
2nd Scheduled
Offences
3rd Scheduled
Offences
4th Scheduled
Offences
2 Weeks Suspension _| Dismissal
Dismissal
Dismissal
3.
instruction by a Supervisor
1 Week Suspension
2 Week Suspension
4,
month period}
Warming
2 Days Suspension
5.
permission
Waming
4 Days Suspension.
Warming
2 Weeks Suspension
Dismissal
Warming
2 Weeks Suspension
Dismissal
4 Days Suspension
2 Weeks Suspension _| Disrnissal
Lateness beyond 15 minutes (4 times over a 7
Absent from work area/department without
Sleeping on the job
Being under the influence of alcohol on the job
Being under the influence of hard drugs (crack,
" — Ieocaine, heroin}
6.
iE
Ja
Early quitting from work area or Department
8.
‘Absent from work for 3.consecutive days without
reasonable excuse
2.
Operating company vehicle/equipment without
_|permission
10.
40a, | Operating company vehicle outside designated area
__|Dismissal
|Warming
2 Week Suspension
1 Week Suspension
42. _
|Falsification of Report
Dismissal
13.
jemployee
2 Weeks Suspension
|Witfully causing damage to Company property
Failure to report damage to Company property
15.
|within 24 hours
w
2 Weeks Suspension
Waming
44a.
2Weeks Suspension _| Dismissal
Dismissal
{Unauthorised absenteeism from work
14, _ |Negligently causing damage to Company property
_|Dismissal
Dismissal
Warning
41.
Punching Time Card or signing Register for another
2 Weeks suspension
Warning
Dismissal
2 Weeks Suspension _| Dismissal
_|Dismissal
2 Week Suspension
Dismissal
Dismissal
2 Weeks Suspension
_|Dismissai
Warning
5 Days Suspension
Failure to observe companies health, safety and
environmental (HSE) rules, basic safety rules
indicated in the JIC Safety Manual for the Building
46
'
land Construction Industry and the health safety and
environmental requirements of the facility within
which they are employed
l
N.B. Nothing in these Guidelines shall supersede either Contractua
any
Conditions or a Company's or Company's Rule, nevertheless, if
by
disciplinary action not in keeping with these guidelines is taken
n of
any member of the Incorporated Masterbuiiders Associatio
Jamaica the Unions reserve the right to pursue this as a grievance.
Signed for:-
Employers Side:
These disciplinary guidelines cannot take precedent over the HSE
rules of the facilities within which the worker is employed.
Alf warnings are to be in writing.
spelt out in
The Grievance Procedure shal! be applied for offences not
this document.
is not repeated
ifan offence is committed by @ worker and this offence
his record.
within a two year period, the offence will be removed from
Dated this 29°" day of March, 2021
Witness:...77-
Dismissal
Signed for:-
Workers Side:
SUGGESTED
FOR
SUBCONTRACT
RATES
OR JOB WORK
Over the years the Incorporated Masterbuilders Association of Jamaica, have
been bombarded with requests for guidelines for sub contractor’s or job work
rates.
In an attempt to partially satisfy these requests, this manual include the following
suggested rates as a guide for several sub contractors or job work activities.
(These rates are labour only).
The rates are listed in a number of skilled trade disciplines for construction works
undertaken in Kingston, St. Andrew and St. Catherine.
They were compiled through collaboration with various members of the Masterbuilders Association, along with professional Quantity Surveyors and would only
be valid for the current JIC period (2021-2023).
Again, these rates are suggested as only a guide, as factors such as special condi-
tions and locations outside those stated will require adjustments.
INDEX FOR JOB WORK
RATE
PAGES
1.
Excavation.....:.. seuneneacaueneaeensnsense seusnunneese
1-7
2.
Steelwork....cseeceeres anaeeseesaesnnnannoeseensesaes
&-9
3s
MaSONPYersseccscnseneeseaeneeeneseeneeneneens cia
10-19
4,
Carpentry..ccccscccssesescnnsecnseennseeenenneeneneeee wi
20 - 24
5.
JOINGLY..sccncs0ee aan gteteeeeuadenneneeenesnnssens
25 - 29
6.
Painting. ...ccnsssecsssscececnens paentesnsacednencnneneans
30 - 32
7.
Plumbing.....:: sesunesns seunananeenenusneensnaesens evans
33 - 36
8.
Scaffolding.....::::: pusucucunneneessocgescnuneeeneeoon
37-38
9.
Tiling. ..ccccsseneesessensonscenenseese epee strane
39 - 40
10.
Welding...........0: su nenneesenseneeneanenseeeessennaas
41 - 46
41.
Electrical......c.ssssssssscses: ieanENinaw anne sunuenenneee
47 - 49
Excavation
SCHEDULE OF TASK WORK
RATES
PERIOD
[
12.202
1
To
|
|
J.I.C. Direct Labor Rates
2
Grade
No of Men
1
0
2
o
3
0
J.C,
Hr/Each
Daily /Total
Direct Labor Rates
Labourer
2
2
457.0276284.
7,312.44
BASE RATE:-
3
$
7,312.44
J.C, Fringe Benefits
Sick Leave
1.00
Public Holidays Not Worked
1.00
Holiday with Pay Vacation
1.00
Production Incentive
15.00
18
$1,316.24
Leaders Rate 6% of
6.00
-
Total Team Rate:NOTES:
$
98,628.68
-
41 Construction Employment Premium
16 %is {Now included in Base Hourly Rate }
2 Far job rates, tatal team rate is divided by production
3 Job Work Total Rates include the construction employment premium and no further payment
will be made at the End of the Project.
Tday
f ace
ance of tht 5 works if a0
sorrected
done by the initial contracted Sub-Labourer/ Contractor
-1-
providing sue
remedial works were
Excavation
General suggested Job Work Rates Published
_as a
quide for the Indus
Included in the calculation are:- Sick Leave, Holiday with Pay,
{ Not Worked
),Leaders Rate, and Production Incentive
Public holidays
to be added based on project condition & location.
Refer to Clauses of the J.C Contract far Additional “age payment
NO. [EXCAVATION
_ CONCRETE AND GANGER
Note:
4) Unload and Pack Means Into Stores or Proper
Place
|Excavation in Compacted Earth to 5' Deep
|Excavation in Asphaltic Concrete (Barber Green)
|Excavation in compacted marl up to 5' deep
|Excavation in compacted sand up to to 5' deep
|Excavation in stiff clay up to 5' deep
|Excavation in stiff clay between 5’ & 10‘ deep
[Excavation in Rock or concretre (no compressor)
Excavation in Rack or concrete (with compressor)
4
2
3
4
5
6
7
8
9
10
|incl. Labourers
Excavation in Rock or concretre (with compressor)
|Labourers only
Backfill renches/foundations Excavations, with
excavated Sand
Excavation in concrete slab up to 8" Thick with out
11_|compressor
12
73
|Excavate for kerb foundations (12" x 12")
|Excavate shallow trenches (18" & 12") < 12" deep
|Excavate between 5' & 10' deep in compacted earth
Eacavate between 10' & 15' deep in compacted
15 jearth
16 |Eacavate in uncompacted Sand
17 |Excavate in uncompacted earth
48 |Excavate in uncompacted marl
49 |Demolish 4" Block walls with all cores filled
20 [Demolish 6" Block wall with all_cores filled
21 [Demolish 8" Block walls with all cores filled
22 |Load barford and spread for filling (Earth/Marl)
Load Barford for dump (all types of soild sand
44
23
24
25
26
27
|debris)
[Load barford and spread for filling (sand)
|Load barford with debris (board, ply, steel, block)
[Load wheel barrow and remove to dump (2FC)
|Load wheel barrow and remove to dump
Load wheel barrow and spread for filling (earth or
Matric
Total
Imperial
Total
Rate
UNIT
Rate
UNIT
Yd.Cu.
Y¥d.Cu.
Yd.Cu.
Yd.Cu.
Yd.Cu.
Y¥d.Cu.
Y¥d.Cu.
4079
2465
1438
863.
1233
1438
8629
m3.
m3
m3.
m3
m3
m3
m3
1411
3225
1881
1129
1612
1881
11286
Yd.Cu.
5393
m3
7054
Yd.Cu.
2157
m3.
2822
Yd.Cu.
173
m3
226
Yd.Cu.
4314
m3.
5643
Ft.Run
Ft.Run
72
96
m
m
236.
315
Yd.Cu.
1370
m3
1791
Yd.Cu.
Y¥d.Cu.
¥d.Cu.
Yd.Cu.
Yd.Sq.
Yd.Sq.
Yd.Sq.
Y¥d.Cu.
41659
539
616
863
434
616
863
360
m3
m3
m3
m3
m2
m2
m2
m3
2170
705
806
4129
516
737
1032
470
Y¥d.Cu.
Yd.Cu.
Load
Load
Yd.Cu.
176
288
173
29
288
m3
m3
Load
Load
m3
230
376
173
29
376
Yd.Cu.
454
m3
594
Yd.Cu.
360
m3
470
¥d.Cu.
No.
No.
No.
Yd.Cu.
216
270
270
192
3595,
m3
No.
No.
No.
m3,
282
270
270
192
3595
Yd.Cu.
4109
m3
4109
36 |SF) Man.
Yd.Cu.
4794
m3
4794
37 |RF) Man.
Yd.Cu.
5393
m3
5393,
|Columns and Beam
Yd.Cu,
3196
m3
3196
39
|slab
Pour only and vibrate Carmix Concrete to
Yd.Cu.
2332
m3
2332
|Foundations
Yd.Cu.
1726
m3
2257
40
28
|marl)
29
|Load wheel barrow and spread for filling (sand)
30
31
32
33
34
|Earth/mari
[Dig post holes (1.25' x_2') deep
|Plant post including bracing in proper position
|Mix and pour concrete in post holes
[Mix pour vibrate concrete in foundations man.
Mix pour vibrate concrete in walls and stiffeners (GF+
|FF) Man.
Mix pour vibrate concrete in walls and stiffeners (FF-
35
Backfill trenches/foundations. Exctns. With exctd.
Mix pour vibrate concrete in walls and stiffeners (SFHandle Mat. Pour Carmix Concrete and vibrate to
38
Handle Mat. Pour Carmix Concrete and Vibrate to
aha
Excavation
General suggested Job Work Rates Published
as a quide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays { Not Worked ),Leaders Rate, and Production Incentive
Refer to Clauses of the J.1.C Contract for Additional ‘age payment to be added based on project condition
NO.|EXCAVATION
CONCRETE AND GANGER
Note:
1) Unload and Pack Means Into Stores or Proper
&
location.
Imperial
Metric
Total
Total
UNIT
Rate
UNIT
Rate
Yd.Cu.
2465
m3
3225
Yd.Cu.
Yd.Cu.
Yd.Cu.
Y¥d.Sq.
1728
508
332
114
m3
m3
m3
m2
2257
664
434
132
Yd.Sq.
FtSq.
Ft.Sa.
Each
Each
Each
Each
Yd.Cu.
Yd.Sq.
100 Sq.Ft.
Load Trucks (5 Yd. Cu. - 10 Yd.Cu.) By hand with
56 |marl, earth, sand, etc.
1233
192
375
91
261
508
863
332
63
288
m2
m2
m2
Each
Each
Each
Each
m3
m2
m2
1474
2064
4038
91
261
508
863
434
82
34
Load
1726
Load
1726
57
Load
3319
Load
3319
Load
4794
Load
4794
Place
41
|Pour Only and vibrate_Carmix Concrete to Columns
Pour Only and Vibrate Carmix Concret to beams
42 |and slabs
43 |Handle Sand Gravel at Mixer for Concrete Mant.
44 |Ram earth or marl manually including wetting
45 |Grade and ram bottom of trench
/To sort and dry pack stones to absorption. Pit walls
46 |(12" x 18") Thick
47 |Cut Concrete surfaces (ups to 1") Thick
48 |Cut Concrete surfaces (1.25" to 3") Thick
49 |Cut down trees (up to 12” girth)
50 |Cut down trees (13" to 24" girth)
51 [Cut down trees (25" to 36" girth)
52 |Cut down trees (37" to 48" girth)
53 |Spread top soil (6" - 12" Thick)
54 |Spread top soil (less than 6" Thick)
55 |Grade sub-base to receive top soil
Load Trucks (11 Yd. Cu. - 16 Yd.Cu.) by Hand with
58
59
60
61
62
63
|Marl, earth, sand ,etc.
Load Trucks (17 Yd.Cu, |Marl, earth sand, etc.
Mix pour vibrate concrete
|Man.
Mix pour vibrate concrete
_[Man.
Mix pour vibrate concrete
|Man.
Mix pour vibrate concrete
|Fls.Man.
Mix pour vibrate concrete
22 Yd.Cu.) By hand with
in isolated beams (FF)
Yd.Cu.
4314
m3
5643
Y¥d.Cu.
in isolated beams (SF)
5076
m3
6639
Yd.Cu.
S752
m3
7524
Yd.Cu.
4314
m3.
5643
Yd.Cu.
5076
m3
6639
Y¥d.Cu.
5752
m3
7524
in isloated beams (RF)
in beams and slabs all
in Ground Floor slabs (ins.
|Bdgs.) Man.
65
Mix pour vibrate concrete in Ground Floor slabs
|(Quts.Bdgs.) Man
Mix pour vibrate concrete in beam,column, wall with
|crane
Yd.Cu.
4013
m3
5249,
66
|Mix pour vibrate concrete in foundations with crane
Y¥d.Cu.
3656
m3
4782
67
|Mix pour vibrate concrete in beams,slabs with crane
Y¥d.Cu.
Handle Mat. Pour Carmix Concrete and vibrate to
|Columns and Beam
3256
m3
4259
68
Yd.Cu.
3196
m3
4180
64
69
70
71
72
73
74
Handle Mat. Pour Carmix Concrete and
|Col. and Beam-Crane
Handle Mat. Pour Carmix Concrete and
|slab
Handle Mat. Pour Carmix Concrete and
|slab - Crane
Pour only and vibrate Carmix Concrete
|Foundations
Vibrate to
Yd.Cu.
2465
m3.
3225
Yd.Cu.
2332
m3
3050
Y¥d.Cu.
1675
m3
2192
Yd.Cu.
1685
m3
2204
Y¥d.Cu.
2538
m3
3320
Yd.Cu.
1876
m3
2454
Vibrate to
Vibrate to
to
|Pour Only and vibrate Carmix Concrete to Columns
Pour Only and Vibrate Carmix Concrete to beams
|and slabs
eG
Excavation
Industry
General suggested Job Work Rates Published_as a quide for the
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays{ Not Worked ),Leaders Rate, and Production Incentive
to be added based on project condition & location.
Refer to Clauses of the J.1.C Contract for Additional age payment
Metric
Imperial
NO.
[EXCAVATION
Note:
CONCRETE
AND GANGER
UNIT
Total
Rate
UNIT
Total
Rate
4) Unload and Pack Means Into Stores or Proper
75
76
77
78
79
80
81
82
83
84
85
86
Place
Pour Only and Vibrate Carmix Concrete to
|Foundations - Crane
Pour Only & Vibrate Carmix Concrete to Column &
|Beams-Crane
Pour Only and Vibrate Carmix Concrete to slabs
|with Crane
|Handle Sand Gravel at Mixer for Concrete Man.
|Handle sand gravel at mixer for blockwork man.
|Handle sand gravel at mixer for rendering mani.
[Make pre-cast slab (18" x 18" x 2")
[Make pre-cast slab (24" x 24" x 2")
[Make pre-cast kerbs (3"x 10")
|Ram earth or marl manually including wetting
|Grade and ram bottom of trench
[Grade and ram fill to receive concrete
Lay and Fit 24" Diameter Culvert pipe using
87 |backhoe/Loader
Lay and fit 18" Diameter Culvert pipe using
89
90
91
92
|backhoe/Loader
To sort and dryfill stones in soakaway pits and
|trenches
|Cut Concrete surfaces (ups to 1") Thick
[Cut Concrete surfaces (1.25" to 3") Thick
[Cut concrete surfaces (3.25” to 6" ) Thick
93
|Cut off porjecting
88
rebar (3/8" & 1/2") using hacksaw
94 |Cut off projecting rebar (9/8" & 3/4") using hacksaw
95 [Cut off projecting rebar (1") using hacksaw
96 |Cut off projecting rebar (3/8" x 1/2") using torch
97 |Cut off projecting rebar (5/8" x 3/4") using torch
‘98 |Cut off projecting rebar (1") using torch
99 [Bush and clean (Grass, weeds, shrubs) site
100/Cut down trees (up to 12" girth)
101|Cut down trees (13" to 24" girth)
102|Cut down trees (25" to 36" girth)
103|Cut down trees (37" to 48" girth)
104] Cut down trees (48" to 60" girth)
105|Cut down trees (61" to 72" girth)
Cut up trees (Bole/branch) and dump (up to 12"
106} girth)
Cut up trees (bole/branch) and dump (13 to 24"
107 |girth)
Cut up trees (bole/branch) and dump (25" to 36"
108|girth)
Cut up trees (bole/branch) and dump (37" to 48"
409| girth)
Cut up
110|girth)
Cut up
114 |girth)
112|Cut up
113|Cut up
trees (bolefbranch) and dump (49" to 60"
Yd.Cu.
1166
m3
1525
Yd.Cu.
2026
m3
2649
Y¥d.Cu.
Yd.Cu.
Y¥d.Cu.
Y¥d.Cu.
Each
Each
Each
Yd.Cu.
Y¥d.Sq.
Yd.Sq.
1338,
539
29
12
78
123
180
345
114
gt
m3
m3
m3
m3
Each
Each
Each
m3
m2
m2
1750
705
38
16
78
123
180
451
132
109
Ft.Run.
114
m
373
Ft.Run
88
m
289
Yd.Cu.
Ft.Sq.
Ft.Sq.
Ft.Sq.
1321
188
375
719
m3
m2
m2
m2
1728
2019
4038
7740
Each
35.
Each
35
44
52
27
38
45
247
91
270
508
863.
1233
Each
Each
Each
Each
Each
m2
Each
Each
Each
Each
Each
44
52
27
38
45
27
91
270
508
863.
1233,
Each
Each
Each
Each
Each
100 Ft.Sq.
Each
Each
Each
Each
Each
Each
1726
Each
1726
Ft.Run
8
m
25
Ft.Run
27
m
87
Ft.Run
52
m
172
FtRun
90
m
295
Ft.Run
131
m
429
Ft.Run
FtRun
Ft.Run
180
90
173
m
m
m
590
295
566
trees (bole/branch) and dump (61" to 72"
and get_out tree root (up to 24" girth)
and get out tree root (25" to 48" girth)
Excavation
General suggested Job Work Rates Published_as a quide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays ( Not Worked ),Leaders Rate, and Production Incentive
Refer to Clauses of the J.1.C Contract for Additional
%age payment to be added based on project condition
120 | Off load cement from truck and pack in storeroom
121|Unload and pack lumber 1" x 2", 1" x 4"x 2" x 2"
Unload and pack lumber:
137|Long
142]24")
Metric
UNIT
Total
Rate
UNIT
Total
Rate
Ft.Run
Yd.Cu.
Y¥d.Sq.
100 Ft.Sq.
288
332
63
288
m
m3
m2
m2
944
434
75
3
Each
35,
Each
35
Each
35
Each
35
Bag
Length
23
6
Bag
Length
23
6
Length
1
Length
14
Length
Length
Length
Bundle
Ft.Sq.
Ft.Sq.
19
22
29
8
66
72
Length
Length
Length
Bundle
m2
m2
18
22
29
8
714
774
Each
Box
Each
Each
166
ii
19
19
Each
Box
Each
Each
166
11
19
19
Length
8
Length
8
Length
11
Length
1
Length
Length
22
29
Length
Length
22
29
Length
"1
Length
1
1"x 6", 1"x 8", 2" x 3", 3"
122|x 4"
Unload and pack lumber: 1" x 10", 1" x 12" 2" x 6",
123]3" x 3", 3" x4"
124|Unload & pack lumber: 2" x 8", 2" x 10", 4" x 4"
125|Unload & pack lumber: 2" x 12" 3" x 8", 4"x 6"
126|Unload and pack shingles
127| Unload and pack formwork in building
128|Remove Fromwork from building pack and load
Unload & pack or unpack and load shed panels (8' x
129]5")
130] Unload and Pack wire nailes (50 Lb. Boxes)
131| Unload and pack props. In building
132|Remove from building pack and load props
Unload & Pack PVC Pipes 1/2" - 1 1/2" Dia. 20°
133}Long
Unload and Pack PVC pipes 2" -3" Diameter 20"
134}Long
Unload and Pack PVC Pipes 4" -6" Diameter 20°
135|Long
136|Unload & Pack PVC Pipes 8" - 12" Dia. 20' Long
Unload & Pack Steel Pipes 1/2"- 1 1/2" Dia. 20'
Unload
138|Long
Unload
139|Long
140|Unload
Unload
141|24')
Unload
location.
Imperial
NO.
[EXCAVATION
CONCRETE AND GANGER
Note:
1) Unload and Pack Means Into Stores or Proper
Place
114|Cut up and get out tree root (49" to 72" girth)
115|Spread top soil (6" - 12" Thick)
116}|Spread top soil (less than 6" Thick)
117|Grade sub-base to receive tap soil
Unload and pack in stores plywood and gypsum
118/sheets
Take from stores and load plywood and gypsum
119|sheets
&
and Pack Steel Pipes 2" - 3" Diameter 20°
Length
22
Length
22
Length
Length
33
8
Length
Length
33
8
Length
14
Length
ch
Length
22
Length
22
Length
33
Length
33
Length
41
Length
41
Length
1
Length
aa
Length
22
Length
22
Length
33
Length
33
& Pack Steel Pipes 4" - 6" Diameter 20'
and Pack Scaffolding Pipes 20' Long
& Pack Metal RHS. Up to 1 1/2"x1 1/2" (20'and Pack Metal RHS 2” x 2" to 3" x 3" (20'-
Unload and Pack Metal RHS
4" x 4" to 5" x 5" (20'-
143|24")
Unload and Pack Metal RHS 6" x 6" to 8" x 8" (20'-
144]24')
Unload & Pack flats, Ls, Chs. (Up to 3" Girth) 20°
145|Long
Unload & Pack Flats, Ls,Chs (3.5" to 6" Girth) 20°
146|Long
Unload & Pack Flats, Ls,Chs (6.5" to 9" Girth) 20°
147|Long
Excavation
General suggested Job Work Rates Published
as a guide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
{ Not Worked ).Leaders Rate, and Production Incentive
Public holidays
payment to be added based on project condition &
Refer to Clauses of the J.|.C Contract for Additional %age
Unload and Pack Means
Into Stores or Proper
& Pack Flats, Ls,Chs (9.5" to 12" Girth) 20°
Metal Plates 8" x4" Up to 1
and
Metal Plates 8' x 4°, 5/16" to 1/2”
&
Metal Plates 8' x 4', 9/16"
metal
and
8x 5" 13/16" to
x 17' to 8' x 20'-
rucks
Material
1
Material
material
material
¥
etc.
sand, etc.
etc.
(7
and small
to 3/4"
1" Thick
location.
Excavation
General suggested Job Work Rates Published
_as a quide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays { Not Worked ),Leaders Rate, and Production Incentive
Refer to Clausas of the J.I.C Contract for Additional %age payment to be added based on project condition &
RETE
190
1) Unload and Pack Means Into Stores or
Place
|Unioad and
Pack Louvre Doors
when
193 [Dum
6"
494
4"
|Dum
location.
Steelwork
SCHEDULE OF TASK WORK
RATES
PERIOD
1.22022
J.C. Direct Labor Rates
Steel Fixer /Bender
1
J.LC.
Grade
No of Men
Hr/Each
4
2
3
1
2
1
694.37
575.07
468,56
Daily /Total
5,554.96
9,201.19
3,748.44
Direct Labor Rates
Labourer
0.00
0
2
BASE
J.LC. Fringe Benefits
Sick Leave
Public Holidays Not Worked
Holiday with Pay Vacation
Production Incentive
3
RATE:-
$
18,504.59
1.00
1.00
1.00
15.00
48.00
18.00% of
6.00
Leaders Rate 6% of
$
3,330.83
3
333.30
$
22,168.71
NOTES:
1
Construction Employment Premium
16% is (Now included in Base Hourly Rate
For job rates, total team rate is divided by production
will be
Job Work Total Rates include the construction employment premium and no further payment
made at the End of the Project.
works, (if any } corrected , providing such. igitecial works were
t
Sub-Labouter! Contractor
the
inthe event the initial Sub- Labourer/ Contractor, abandon the works.or is terminated
~8-
Steelwork
Refer to Clauses of the J.1.C Contract for Additional %age payment to be added based on project condition & location.
IMPERIAL
Nos.
METRIC
Total
UNIT
Rate
Total
UNIT
Rate
it
3/8" Mild Stee! Rebar
Lb.
2
3
4
23
1/2" Mild Steel Rebar
5/8" Mild Steel Rebar
3/4" Mild Steel Rebar
Kg.
50
Lb.
Lb.
Lb.
23
23
23
Kg.
Kg.
Kg.
50
50
50
Lb.
23
Kg.
50
Yd.Sq.
Doz.
94
$28
m2
Doz.
208
528
5
6
7
1" Mild Steel Rebar
Fabric
1/4" Stirrups
8
3/8" Stirrups
Doz.
554
9
3/8" Stirrups (Large > 6' Girth)
Doz.
554
Doz.
693
Doz.
693
Doz.
792
Doz.
792
Doz.
924
Doz.
924
Doz.
Doz.
Doz.
Doz.
Doz.
426
482
715
462
683
Doz.
Doz.
Doz.
Doz.
Doz.
426
482
715
462
693
10
1/2" Stirrups
11
1/2" Stirrups (Large > 7' Girth)
12
13
14
15
16
1/4"
3/8"
1/2"
3/8"
1/2"
17
3/8" High Tensile Steel Rebar
Lb.
25
Kg.
56
18
1/2" High Tensile steel Rebar
Lb.
19
5/8" High Tensile Steel Rebar
25
Kg.
56
Lb.
25
Kg.
20
3/4" High Tensile stee! Rebar
56
Lb.
21
25
1" High Tensile Steel Rebar
Kg.
56
Lb.
25
Kg.
56
Links
Links
Links
Chairs
Chairs
Masonry
SCHEDULE OF TASK WORK RATES
PERIOD
4
3
|i
1.22022
|
|
|
J.C. Direct Labor Rates
Masonry
2
No of Men
HrJEach
4
4
706.85
5,654.78
2
2
578.98
9,263.79
3
0
0.00
0.00
J.C. Direct Labor Rates
Labourer
457.03,
3
2
BASE
3.
Daily [Total
Grade
J.LC.
10,968.66
25,887.23
RATE:-
Fringe Benefits
Sick
Public Holidays Not Worked
Holiday with Pay Vacation
Production Incentive
1.00
%
1.00
%
1.00
%
15.00
%
18.00
%
4,659.70
25,887.23
18.00% of
5,654.78
Leaders Rate 6% of
6.00
%
339.29
30,886.22
NOTES:
4
2
3
Construction Employment Premium
16%
is
For job rates, total team rate
(Now included in Base Hourly
Rate
is divided by production
no further
Job Work Total Rates include the construction employment premium and
payment will be made at the End of the Project.
ted
Sub-Labourer!
Contra:
tor abandon the works.or is t
~10—-
Masonry
General suggested Job Work Rates Published
as a quide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays{ Not Worked
),Leaders Rate, and Production
Incentive
Refer to Clauses of the J.C Contract for Additional “age payment to he added based on project condition & location.
MASONRY
Nos.
IMPERIAL
Total
Rate
UNIT
UNIT
METRIC
Total
Rate
|Notes.
1) Add
Extra Arris Rate for Beams with More
Than 2 Arris
2)
For Electric. Manholes
use 70% of Sewer
Manhole Rates
Lay 8" Blocks & Fill all Pockets (Ground Floor
1
|to First Floor)
Lay 8" Blocks & Fill all Pockets (Ground Floor
Y¥d.Sq.
1,103
m2
1,319
2
|& Above)
Yd.Sq.
1,287
m2
1,539
Yd.Sq.
1,471
m2
1,759
Y¥d.Sq.
936
m2
4,119
|Floor & Above)
Lay 6" Blocks & Fill All Pockets (Ground
Y¥d.Sq.
1,065
m2
1,274
6
[Floor to First Floor)
Yd.Sq.
965
m2
1,154
7
Lay 6" Blocks & Fill All Pockets ( First Floor
|&Above)
Yd.Sq.
1,103
m2
1,319
Y¥d.Sq.
1,287
m2
1,539
Yd.Sq.
835
m2
998
Y¥d.Sq.
965
m2
1,154
Yd.Sq.
882
m2
1,055
¥d.Sq.
965
m2
1,154
Yd.Sq.
1,188
m2
1,424
Yd.Sq.
772
m2
923
¥d.Sq.
858
m2
1,026
Lay 8" Blocks & Fill All Pockets (Manholes,
3
|Drains)
Lay 8" Blocks & Fill
4
|(Ground Floor
Alternate Pockets
to First Floor)
Lay 8" Blocks & Fill Alternate Pockets (First
5
Lay 6" Blocks & Fill All Pockets( Manholes,
8
9
10
11.
12
13
14
15
|Drains, and Gully Basins)
Lay 6" Blocks & Fill Alternative
|(Ground Floor to First Floor)
Lay 6" Blocks & Fill Alternative
|Floor & Above)
Lay 4" Blocks & Fill All Pockets
|Floor to First Floor)
Lay 4" Blocks & Fill All Pockets
|Above)
Lay 4" Blocks & Fill All Pockets
|Drains, Gully Basins)
Lay 4" Blocks & Fill Alternative
|(Ground Floor to First Floor)
Lay 4" Blocks & Fill Alternative
|Floor & Above)
Pockets
Pockets (First
(Ground
(First Floor &
(Manholes,
Pockets
Pockets (First
Lay 6" x 6" Breather Blocks & Rake Joints
16
|(All Floors)
Lay 9" x 9" Breather Blocks & Rake Joints
Yd.Sq.
3,089
m2
3,694
17
|(All Floors)
Lay 12" x 12" Breather Blocks & Rake Joints
Yd.Sq.
2,059
m2
2,463
Yd.Sa.
1,817
m2
2,173
18
|(All Floors)
Lay 6" High Concrete Louvres and Rake
19
|Joints (18" x 36")
Fill Alternate Pockets One Course High U/S
20
|Belts 8" W
21
22
23
24
Fill Alternate Pockets One Course High U/S
|Belts 6" W
|Hack Concrete Surfaces for Rendering
|Paint Bondcrete to Concrete Surfaces
Cut Stone Face Lay Point Joints as Extra
|Over Wall
Each
222
222
Ft.Run
61
M
199
Ft.Run
Yd.Sq.
Yd.Sq.
45
315
94
M
m2
m2
149
377
113
Yd.Sq.
9,640
m2
11,529
Yd.Sq.
12,576
m2
15,041
13,087
m2
15,653
Cut Stone Face Lay Point Joints as facing on
25
|Wall 4"Thick
Cut Stone Face Lay Point Joints as facing on
26
|Bank 6" Thick
Yd.Sq.
a
Masonry
for the Industry
General suggested Job Work Rates Published as a guide
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays ( Not Worked ),Leaders Rate, and Production Incentive
be added based on project condition & location.
Refer to Clauses of the J.I.C Contract for Additional “age payment fo
Add Extra Arris Rate for Beams with More
2 Arris
For Electric. Manholes use 70% of Sewer
Rates
6" Thick
Stone Face and Build
Mortar
Wi
Arrisses to Stone W:
Arrisses and
. And 6"
from stones 6" Thick
eep
> 12"
Pipes
Weep Holes
Stonewalls < 12"
only(Up to1
to 1"
Walls
Cast only
Drains,
For
For
Basins
Cast
4" Thick)
Thick
only
all T
only
For
T
only
m
=
8" Girth
Girth
A
Girth
(Ditto
only
[= |F [F IF
) For Beams
" Girth
Cast only
ms
1" Thick)
Cast
2" Grith
Cast only (Ditto 1"
[= l=
8" Grith
" Grith
Cast only
alalzl= l=
Grith
only (Ditto 1"
36" Grith
to
iT
to
Walls
Walls
3|3
NI’
to
Finish to Manholes,
Basins
S/S/S|S]/=
to
to1
to Beams
to Beams
to
i fm
Masonry
General suggested Job Work Rates Published
as a quide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays { Not Worked ),Leaders Rate, and Production Incentive
Refer to Clauses of the J.1.C Contract for Additional “age
payment to be added based on project condition &
IMPERIAL
Total
MASONRY
Nos.
focation.
|Notes
1) Add Extra Arris Rate for Beams
UNIT
Rate
METRIC
Total
UNIT
Rate
with More
Than 2 Arris
2)
58
For Electric. Manholes
use 70% of Sewer
Manhole Rates
|Granite Only to Beams (2R) 36" Girth
Rough Cast (Up to 1" Thick) and Granite
|Walls
FtRun
363
M
1,192
Yd.Sq.
882
m2
1,055
[Walls
Rough (Cast Up to 1” Thick) and Tyrolean
[Walls
Rough (Cast Up to 1" Thick) and Stee! Finish
Y¥d.Sq.
882
m2
1,055
Yd.Sq.
1,065
m2
1,274
62
|Walls
Yd.Sq.
4,188
m2
4,424
63
Rough Cast (Ditto 1" Thick) and Steel Finish
|M/H, Drains & G/Basins
¥d.Sq.
1,716
m2
2,052
¥d.Sq.
950
m2
1,137
Ft.Run
401
M
1,316
Ft.Run
461
M
1,513
Ft.Run
533
M
4,747
Ft.Run
$83
M
1,912
Ft.Run
216
M
709
Ft.Run
281
M
921
Ft.Run
336
M
1,107
Ft.Run
363
M
1,206
Ft.Run
435,
M
1,427
59
Rough (Cast Up to 1" Thick) and Pebble
60
61
Rough Cast (Ditto 1" Thick) and Granite
64
65
66
67
|Ceilings
Rough Cast
|Beams (2R)
Rough Cast
|Beams (2R)
Rough Cast
|Beams (2R) 30" Girth
Rough Cast
68 |Beams (2R)
Rough Cast
69
[columns (1R
Rough Cast
70
{columns (1R
Rough Cast
71
(Ditto 1" Thick) and Granite
18" Girth
(Ditto 1" Thick) and Granite
24" Girth
(Ditto 1" Thick) and Granite
(Ditto 1" Thick)
36" Girth
(Ditto 1" Thick)
12" Girth)
(Ditto 1" Thick)
18" Girth)
(Ditto 1" Thick)
and Granite
and Granite
and Granite
and Granite
|columns (1R 24" Girth)
Rough Cast (Ditto 1" Thick) and Granite
72
|columns (2R 18" Girth)
Rough Cast (Ditto 1" Thick) and
73
[columns (2R 24" Girth)
Rough Cast (Ditto 1" Thick) and
74
|columns (2R 30" Girth)
Rough Cast (Ditto 1" Thick) and
75
|columns (2R 36" Girth)
76
|Arrises
77 + |Curved Arrisses
78
|Fairface Walls
79 | Fairface Ceilings
80
|One Coat Render to Walls and
81
82
83
84
85
Granite
Granite
Ceilings
|Dress Water Drip Formed in Soffit of Slab
Form and Dress Water Drip into Rendering
|of Slab Soffit
Set screeds to Floors/Roofs using Mortar
Pin Out and Dress Plumbing/Electrical Pipe
|Through Walls (1/2" - 1")
Pin Out Plumbing/Electrics (1/2" - 1")
|Chasings (Rough
Ft.Run
490
M
1,609
Ft.Run
Ft.Run
Ft.Run
Yd.Sq.
Y¥d.Sq.
Yd.Sq.
542
92
144
289
368
468
M
M
M
m2
m2
m2
41,778
303
471
345
440
560
Ft.Run
144
M
471
Ft.Run
Yd.Sq.
172
131
M
m2
563
157
Each
AB
Ft.Run
48
M
158
FtRun
66
M
216
FtRun
86
M
281
Granite
Walls)
Each
48
Pin Out Plumbing/Electrics (1 1/4" - 2")
86
|Chasings (Rough Walls)
Pin Out Plumbing/Electrics (3"-4") Chasings
87.
|(Rough Walis)
—13—
Masonry
General suggested Job Work Rates Published as a guide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays ( Not Worked
),Leaders Rate, and Production
Incentive
to be added based on project condition & location.
Refer to Clauses of the J.|.C Contract for Additional ‘nage payment
IMPERIAL
UNIT
MASONRY
Nos.
Total
Rate
METRIC
UNIT
Total
Rate
[Notes
1) Add Extra Arris Rate for Beams with More
Than 2 Arris
2) For Electric. Manholes use 70% of Sewer
Manhole Rates
Rod-Off Floor Slabs to Receive Tiles or
Yd.Sq.
Yd.Sq.
Yd.Sq.
119
406
406
m2
m2
m2
142
486
486
|Rod-Off and Steel Float Floor Slabs Manually
Rod-Off and Steel Float Floor Slabs
Yd.Sq.
606
m2
724
92
|Mechanically
¥d.Sq.
289
m2
345
93
|Woodfloat Floor Slabs or Broom Finish Slabs
Yd.Sq.
286
m2
342
94
Screed and Dress Tread (10 - 12") Wide
|Wood Float Including Redge
Ft.Run
249
M
817
Ft.Run
372
M
4,221
Ft.Run
172
M
563
Ft.Run
Ft.Run
FtRun
257
91
52
M
M
M
844
298
172
Ft.Run
213
M
699
Yd.Cu.
686
m3
2,252
88
89
g0
|Screeds
|Rod-Off and Broom Finish Floor Slabs
|Rod-Off and Wood Finish Floor Slabs
91
‘Screed and Dress Tread (10 - 12") Wide
95
96
97
98
99
100
101
102
103
404
105
106
407
|Steel Float
Screed and
|Float Finish
Screed and
|Float
|Mark Floor
[Mark Floor
Including Redge
Dress Riser (6"-8") Wide Wood
Incl. Redge
Dress Riser (6" -8" ) Wide Steel
Slabs with Metal Tool
Slabs with Cotton Cord
[Lay Haunch and Point Kerbs
Provide Labour Pour and Settle Pre-mix
|Concrete
Trap G/Basins From 4" Blocks Complete 15"
|W. x15" Lg.x 15" Internal Dia
Trap G/Basins From 4" Blocks Complete 18”
|W. x 18" Lg. x18" Internal Dia.
Sewer M/H From 6" Blocks Complete
|W.x18" Lg.x 18" Internal Dia.
Sewer WH From 6” Blocks Complete
|x18" Lg. x 24" Internal Dia.
Sewer M/H From 6" Blocks Complete
|x 24" Lg.x 24" Internal Dia.
Sewer M/H From 6” Blocks Complete
|x 24" Lg.x 30" Internal Dia.
Each
5,828
Each
7,722
Each
7,722
Each
8,825
Each
8,825,
Each
10,295
Each
10,295
Each
12,555
Each
12,555
Each
14,638
Each
14,638
Each
13,697
Each
13,697
Each
14,921
Each
14,921
Each
17,352
Each
17,352
Each
16,003
Each
16,003.
18" W
24" W
24" W
Sewer W/H From 6" Blocks Complete 24" W
|x 36" Lg.x 24" Internal Dia.
5,828
18"
4108 |x 30" Lg.x 24" Internal Dia.
Sewer MH From 6" Blocks Complete 30" W
105 |x 34" Lg.x 30" Internal Dia.
‘Sewer M/H From 6" Blocks Complete 30" W
406 |x 30" Lg.x 30" Internal Dia.
Sewer MH From 6" Blocks Complete 30" W
107
Each
Masonry
General suggested Job Work Rates Published
Included in the calculation are:
as a quide for the Industry
Sick Leave, Holiday with Pay,
Public holidays ( Net Worked ),Leaders Rate, and Production Incentive
Refer to Clauses of the J.1.C Contract for Additional %age payment to be added based on project condition & location.
IMPERIAL
Total
Rate
MASONRY
Nos.
|Notes
UNIT
UNIT
METRIC
Total
Rate
41) Add Extra Arris Rate for Beams with More
108
109
110
111
112
113
114
115
116
117
118
119
420
121
122
123
124
125
426
Than 2 Aris
2) For Electric. Manholes use 70% of Sewer
Manhole Rates
Sewer M/H From 6" Blocks Complete 36" W
|x 36" Lg.x 24" Internal Dia.
Rough Cast (Up to 1" Thick) and Spanish
|Wave Walls
Rough Cast (Ditto 1" Thick) and Steel Finish
|M/H, Drains and G/Basins
Rough Cast (Ditto 1" Thick) and Granite 2R
|Jamb/Wall Top
Rough Cast (Ditto 1" Thick) and Granite 1R
|Jamb
Rough
|Curved
Rough
|Curbed
Rough
|Beams
Rough
|Beams
Rough
|Beams
Rough
|Beams
Rough
|Beams
Rough
Cast (Ditto 1" Thick)
Jamb/Wall Top
Cast (Dito 1" Thick)
Jamb
Cast (Ditto 1" Thick)
(2R) 18" Girth
Cast (Ditto 1" Thick)
(2R) 24" Girth
Cast (Ditto 1" Thick)
(2R) 30" Girth
Cast (Ditto 1" Thick)
(2R) 36” Girth
Cast (Ditto 1" Thick)
(2R) 42" Girth
Cast (Ditto 1" Thick)
Cast
(2R)
Cast
(2R)
Cast
Cast
(2R)
Cast
(1R)
Cast
Each
17,255
Yd.Sq.
996
m2
1,192
Yd.Sq.
4,716
m2
2,052
FtRun
269
M
884
Ft.Run
159
M
522
Ft.Run
401
M
1,316
Ft.Run
243
M
798
Ft.Run
396
M
1,299
Ft.Run
461
M
1,513
Ft.Run
533
M
1,747
Ft.Run
583
M
1,912
Ft.Run
630
M
2,068
Ft.Run
686
M
2,252
Ft.Run
772
M
2,533
Ft.Run
882
M
2,895
Ft.Run
965
M
3,167
Ft.Run
1,065
M
3,494
Ft.Run
229
M
7541
FtRun
300
M
984
Ft.Run
368
M
1,206
Ft.Run
444
M
1,448
Ft.Run
218
M
714
FtRun
278
M
913
and Granite 1R
and Granite
and Granite
and Granite
and Granite
and Granite
and Granite
(Ditto 1" Thick) and Granite
60" Girth
(Ditto 1" Thick) and Granite
72” Girth
(Ditto 1" Thick) and Granite
|Beams (2R) 84" Girth
Rough
|Beams
Rough
|Beams
Rough
17,255
and Granite 2R
|Beams (2R) 48" Girth
Rough
|Beams
Rough
|Beams
Rough
Each
(Ditto 1" Thick) and Granite
96" Girth
(Ditto 1" Thick) and Granite
12" Girth
(Ditto 1" Thick) and Granite
|Beams (1R) 18" Girth
Rough Cast (Ditto 1" Thick) and Granite
127
|Beams (1R) 24" Girth
Rough Cast (Ditto 1" Thick) and Granite
128
30" Girth
(Ditto 1" Thick) and Granite
12" Girth)
(Ditto 1° Thick) and Granite
18" Girth)
|Beams (1R)
Rough Cast
4129 |columns (1R
Rough Cast
130 |columns (1R
~15—
Masonry
General suggested Job Work Rates Published as a guide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays ( Not Worked ),Leaders Rate, and Production Incentive
to be added based on project condition & location.
Refer to Clauses of the J.1.C Contrast for Additional “age payment
IMPERIAL
MASONRY
Nos.
431
432
433
134
435
136
|Notes
1) Add Extra Arris Rate for Beams
Than 2 Arris
2) For Electric. Manholes use 70%
Manhole Rates
Rough Cast (Ditto 1" Thick) and
|columns (1R 24” Girth)
Rough Cast (Ditto 1" Thick) and
|columns (2R 18" Girth)
Rough Cast (Ditto 1" Thick) and
|columns (2R 24" Girth)
Rough Cast (Ditto 1" Thick) and
|columns (2R 30" Girth)
Rough Cast (Ditto 1" Thick) and
|columns (2R 36" Girth)
Rough Cast (Ditto 1" Thick) and
Total
Rate
UNIT
METRIC
UNIT
Total
Rate
with More
of Sewer
Granite
Ft.Run
336
M
1,101
Ft.Run
368
M
1,206
Ft.Run
435
M
1,427
FtRun
490
M
1,609
FtLRun
542
M
1,778
FtRun
623
M
1,718
Granite
Granite
Granite
Granite
Granite
|columns (3R 24" Girth)
Rough Cast (Ditto 1" Thick) and Granite
437
|columns (3R 30" Girth)
Ft.Run
583.
M
1,912
438
Rough Cast (Ditto 1" Thick) and Granite
|columns (3R 36" Girth)
Ft.Run
630
M.
2,068
Ft.Run
686
M
2,252
Ft.Run
735
M
2,413
Ft.Run
718
M
2,357
FtRun
835
M
2,739
FtRun
936
M
3,071
Rough Cast (Ditto 1” Thick) and Granite
439
440
441
442
|columns (3R
Rough Cast
|columns (3R
Rough Cast
|columns (4R
Rough Cast
42" Girth)
(Ditto 1" Thick) and Granite
48" Girth)
(Ditto 1" Thick) and Granite
36” Girth)
(Ditto 1" Thick) and Granite
|columns (4R 48” Girth)
Rough Cast (Ditto 1" Thick) and Granite
443
|columns (4R 60" Girth)
Rough Cast (Ditto 1" Thick) and Granite
144
|columns (4R 72" Girth)
FtLRun
1,030
M
3,378
445
Rough Cast (Ditto 1" Thick) and Granite
|columns (4R 84" Girth)
Rough Cast (Ditto 1" Thick) and Granite
Ft.Run
1,144
M
3,753
146
|columns (4R 96" Girth)
Ft.Run
4,235
M
4,054
Ft.Run
908
M
2,981
FtRun
41,030
M
3,378
447
448
Rough Cast
|columns (5R
Rough Cast
|columns (5R
Rough Cast
(Ditto 1" Thick) and Granite
48" Girth)
(Ditto 1" Thick) and Granite
60" Girth)
(Ditto 1" Thick) and Granite
449
|columns (5R 72" Girth)
Ft.Run
1,136
M
3,726
150
Rough Cast (Ditto 1" Thick) and Granite
|Circular columns 6" Dia
Rough Cast (Ditto 1" Thick) and Granite
Ft.Run
552
M
1,810
451
|Circular columns 9" Dia
Rough Cast (Ditto 1" Thick) and Granite
Ft.Run
772
M
2,533
452
|Circular columns 12" Dia
FtRun
996
M
3,269
453
|Circular columns 15" Dia
Rough Cast (Ditto 1" Thick) and Granite
|Circular columns 18" Dia
Rough Cast (Ditto 1" Thick) and Granite
|Circular columns 21" Dia
Rough Cast (Ditto 1" Thick) and Granite
|Circular columns 24" Diameter
|Spanish Wave Only to Walls.
|Wood Float Top of 18" x 18" Pre-cast slab
|Wood Float Top of 24" x 24" Pre-cast slab
FtRun
1,188
M
3,898
Ft.Run
1,404
M
4,606
Ft.Run
1,600
M
5,251
Ft.Run
Yd.Sq.
Each
Each
1,796
566
78
126
M
m2
Each
Each
5,892
677
78
126
154
455
456
157
458
159
Rough Cast (Ditto 1" Thick) and Granite
— 16—-
Masonry
General suggested Job Work Rates Published
as a quide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays( Not Worked ),Leaders Rate, and Production Incentive
Refer to Clauses of the J.C Contract for Additional “age payment to be added based on project condition & location.
IMPERIAL
MASONRY
Nos.
METRIC
Total
[Notes
UNIT
Total
Rate
UNIT
Rate
1) Add Extra Arris Rate for Beams with More
Than 2 Arris
2)
160
161
162
For Electric, Manholes use 70% of
Sewer
Manhole Rates
|Fairface Walls
|Fairface Ceilings
Fair Face Mortar Joints to 6" x 6" Breather
|Blocks
Y¥d.Sq.
Yd.Sq.
289
368
m2
m2
345
440
Yd.Sq.
1,065
m2
1,274
Yd.Sq.
965
m2
1,154
Yd.Sq.
877
m2
1,049
Fair Face Mortar Joints to 9" x 9" Breather
163
164
|Blocks
Fair Face Mortar Jints to 12" x 12" Breather
|Blocks
Fair Face Jambs (Ends) of 6" Concrete
165
|Louvres
Ft.Run
179
M
586
166
|One Coat Render to Walls and Ceilings
Y¥d.Sq.
463
m2
560
167
|Dress Water Drip Formed
Ft.Run
144
M
471
Ft.Run
172
M
563
Each
74
Each
74
Each
88
Each
88
Ft.Run
49
M
162
Ft.Run
68
M
224
168
169
in Soffit of Slab
Form and Dress Water Drip into Rendering
|of Slab Soffit
Pin Out and Dress Plumbing/Electrical Pipe
|Through Walls (1 1/4" - 2")
Pin Out and Dress Plumbing/Electrical Pipes
170
[Through Wall (3"-4")
171
|Chasings (Rough Walls)
Pin Out Plumbing/Electrics (1 1/4" - 2")
|Chasings (Rough Walls)
Pin Out Plumbing/Electrics (3"-4") Chasings
172
Pin Out Plumbing/Electrics (1/2" - 1")
173
|(Rough Walls)
Ft.Run
87
M
285
174
Pin Out Dress Plumbing/Electrics Small
|Chasings (Finish Walls)
Ft.Run
147
M
483
475
|Pin Out Top of Walls Under Beams or Slabs
Pin Out Around Electrics Outlets (Rough
FtLRun
86
M
281
176
|Walls)
FtRun
51
M
169
FtRun
100
M
327
Ft-Run
147
M
483
Ft.Run
283
M
930
Ft.Run
FtRun
Ft.Run
401
48
260
M
M
M
1,316
158
852
Pin Out and Dress Around Electrics Outlets
177
180
181
182
|(Dress Walls)
Patching (Rough Cast and Granite) less
|Than 12" Wide
Build and Dress One Reveal Band Up to 8”
|Wide including Nailing Timber
Build and Dress Two Reveal Band Up to 8"
|Wide including Nailing Timber
|Nail Timber strip Only to Form Reveal
|Form Chamfer Including Arrisses
183
|Screeds
Yd.Sq.
119
m2
142
184
|Rod-Off and Broom Finish Floor Slabs
Yd.Sq.
406
m2
486
178
179
Rod-Off Floor Slabs to Receive Tiles or
~17—
Masonry
General suggested Job Work Rates Published
as a quide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays( Not Worked ), Leaders Rate, and Production Incentive
Refer to Clauses of the J.I.C Contract for Additional “age
MASONRY
Nos.
|Notes
1) Add Extra Arris Rate for Beams with More
Than 2 Aris
2)
payment to be added
based on project condition &
IMPERIAL
Total
Rate
UNIT
location.
UNIT
METRIC
Total
Rate
For Electric. Manholes use 70% of Sewer
Manhole Rates:
485
|Rod-Off and Wood Finish Floor Slabs
Yd.Sq.
406
m2
486
186
|Rod-Off and Steel Float Floor Slabs Manually
Yd.Sa.
606
m2
724
187
Rod-Off and Steel Float Floor Slabs
|Mechanically
Wood Float Floor Slabs or Broom Finish
Yd.Sq.
289
m2
345
Y¥d.Sq.
286
m2
342
FtLRun
249
M
B17
FtRun
372
M
1,221
Ft.Run
172
M
563
FtRun
Ft.Run
257
91
M
M
844
298
Ft.Run
52
M
172
188
189
190
|Slabs
(Screed and
|Wood Float
Screed and
|Steel Float
Dress Tread (10 - 12") Wide
Including Redge
Dress Tread (10 - 12") Wide
Including Redge
Screed and Dress Riser (6"-8") Wide Wood
191
|Float Finish Including Redge
Screed and Dress Riser (6" -8" ) Wide Steel
192
193
|Float
|Mark Floor Slabs with Metal Tool
494
|Mark Floor Slabs with Cotton Cord
495
|Joint and Seal 18" Diameter Culvert Pipes
FtRun
278
M
913
196
|Joint and Seal 24" Diameter Culvert Pipes
Ft.Run
363
M
1,192
|Fillet
Ft.Run
144
M
471
|Fillet
Ft.Run
172
M
563
|Fillet
Ft.Run
230
M
756
497
198
199
Mix Material Hoist Cast and Dress 2" x 2"
Mix Material Hoist Cast and Dress 3" x 3"
Mix Material Host Cast and Dress 4" x 4"
Mix Material Hoist Cast and Dress 6" x 6"
200
201
|Fillet
{Lay Haunch and Point Kerbs
Ft.Run
Ft.Run
294
213
M.
M
965
699
202
Provide Labour Pour and Settle Pre-mix
|Concrete
Yd.Cu.
686
M3
898
Each
191
203
204
|Lay paving Slabs Without Pointing on Sand
Lay Bricks/pavers (9" x 4") and Point and
|Clean Joints
Lay Bricks/pavers (9" x 4") and Point and
Each
191
Ft.Sq.
455
m2
4,896
172
M
563
205
|Clean Joints
FtLRun
206
Trap G/ Basins From 4" Blocks Complete 12"
|W. x12" Lg.x 12" Int.Dia.
Trap G/Basins From 4" Blocks Complete 15"
Each
4,290
Each
4,290
Each
5,720
Each
5,720
Each
7,722
Each
7,722
Each
8,825
Each
8,825
Each
10,295
Each
10,295
207
208
209
210
|W. x15" Lg.x 15" Int. Dia.
Trap G/Basins From 4” Blocks Complete 18"
|W. x 18" Lg.x 18" Int. Dia.
Sewer M/H From 6" Blocks Complete 18"
|W.x18" Lg.X 18" Int. Dia.
Sewer WH From 6" Blocks Complete 18" W
|x 18" Lg. x 24" Int. Dia.
~18=
Masonry
General
suggested
Job Work
Rates Published
as a quide
for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays{ Not Worked ),Leaders Rate, and Production Incentive
Refer to Clauses
of the J.1.C Contract for Additional “.age payment te be added based on project condition &
location.
IMPERIAL
MASONRY
Nos.
[Notes
Total
Rate
UNIT
1) Add
Extra Arris Rate for Beams
METRIC
UNIT
Total
Rate
with More
Than 2 Arris
2)
For Electric. Manholes
Manhole Rates
211
212
213
214
216
217
use 70% of Sewer
Sewer M/H From 6" Blocks Complete 24" W
|x 24" xLg. x 24" Int. Dia.
‘Sewer M/H From 6" Blocks Complete 24" W
|x 24" Lg. x 30" Int. Dia.
‘Sewer M/H From 6" Blacks Complete 24" W
|x 30" Lg. x 24" Int. Dia.
‘Sewer M/H From 6" Blocks Complete 30" W
|x 34" Lg. x 30" Int. Dia.
Sewer M/H
|x 30" Lg. x
Sewer M/H
|x 36" Lg. x
From 6" Blocks Complete 30" W
30" Int. Dia.
From 6" Blocks Complete 30" W
24" Int.Dia.
Each
12,555
Each
12,555
Each
14,638
Each
14,638
Each
13,709
Each
13,709
Each
14,921
Each
14,921
Each
17,410
Each
17,410
Each
16,036
Each
16,036
Each
47,255
Each
17,255
Each
20,187
Each
20,187
Each
23,170
Each
23,170
Each
37,897
Each
37,897
Each
45,690
Each
45,690
Sewer M/H From 6" Blocks Complete 36" W
218
|x 36" Lg, x 24" Int. Dia.
Sewer M/H From 6" Blacks Complere 36" W
219
|x 36" Lg. x 30" Int. Dia.
Sewer M/H From 6" Blacks Complete 36" W
220
|x 36" Lg.x 36" Int. Dia.
Sewer M/H From 6" Blocks Complete 48" W
221
|x 48" Lg. x 48" Int Dia.
222
Sewer M/H Fram 6" Blocks Complete 48” W
|x 48" Lg. x 60" Int. Dia.
METRIC
Rate
FINISH
rowel on finished application with color tint to
floors &
aaeneane NOTE
as
wwcennccene
Item #1
~19—
Carpentry
SCHEDULE OF TASK WORK
RATES
PERIOD
4
J.C.
Direct Labor Rates
Carpentry
2
DailyTotal
No of Men
HrJEach
1
2
4
4
706.85
585.73
5,654.78
4,685.84
3
1
486.49
3,891.92
Grade
J.C. Direct Labor Rates
Labourer
BASE RATE:3
J.LC.
Fringe Benefits
0.00
0.00
0
2
Sick Leave
1.00
Public Holidays Not Worked
Holiday with Pay Vacation
4.00
1.00
14,232.54
15.00
Production Incentive
18.00
2,561.86
14,232.54
18.00% of
5,654.78
Leaders Rate 6% of
6.00
TEAM RATE :-
339.29
47,133.68
NOTES:
1
Construction Employment Premium
2
For job rates, total team rate is divided by production
3
payment will be
Job Work Total Rates include the construction employment premium and no further
made at the End of the Project.
16%
is (Now included in Base Hourly Rate }
4
BO
Carpentry
General suggested Job Work Rates Published as a quide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays { Not Worked ),Leaders Rate, and Production Incentive
Refer to Clauses of the J.I.C Contract for Additional %age payment to be added based on project condition & location.
and
Forms to Belt
and
amd
Forms to
Forms to
to
stairs)
of Manholes
New Circular Formwork Colunms
Oil To Formwork
or Timber
or
of Concrete Poured
nsert
to
Under Rebar
Fix
Inside Formwork
to
Base Plate
Fit Hurricane
Fit Gutter Brackets to Timber
Fit Gutter Brackets to Concrete
x
or
i
Ends
x
or Beam
Ends
or
x
Ends
x 10" Rafter or Beam
x 2" Framing to
oar
Rafters/Joists
x
Rafters/Joists
"x
Rafters/Joists
"x4
Rafters/Joists
= 94.
Carpentry
the Industry
General suggested Job Work Rates Published as a quide for
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays ( Not Worked ),Leaders Rate, and Production Incentive
te be added based on project condition &
Refer to Clauses of the J.1.C Contract for Additional “age payment
ongue
of RaftersNoists
ongue
of Rafters/Joists
x
x 3" Bearers
x2"
x3" Bearer
x2" & 1"x3"
x 2" Battens
to
)
to Roof or Wall (wooden
to Roof or W.
to
or
to Roof or Wall
Lath at
to Roof or Wall
at
x
. to Roof or Wall
x
Tiles to RooffWall
"x3"
Purlins
Roof
to
to Roofs and
or
(Wooden
to
1"x 6" Fascia
= 22
location.
Carpentry
General suggested Job Work Rates Published
_as @ quide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays { Not Worked ),Leaders Rate, and Production Incentive
Refer to Clauses of the J.1.C Contract for Additional %age payment to be added based on project condition &
location,
Matric
Rate
"x 6"
388,
1"x 8"
x
"x
1" x 10"
1" x 12" Fascia
1x1
Board
Board
On Centered Vi
16" On Centered Vi
Frame
Frame
Vertical
Install Corner Beads to
Walls
Install
(i/2" =
Plywood Sheeting (3/16" - 3/8")
Walls
Install Plywood
(1/2" = 3/4") to
and Plaster Walls
and Plaster
Only
to Roof or Wail
Only
to Roof or Wall
or
o Gables
Zinc
russes 1
Sheds
Plus Lath
russes @ 5
& Zinc
and Stack
=-23—
Carpentry
General suggested Job Work Rates Published
_as a a1
jefor the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays ( Not Worked ),Leaders Rate, and Production Incentive
be added based on project condition &
Refer to Clauses of the J.LC Contract for Additional Gage payment to
location.
Metric
Total
Rate
and Stack
x
x
Boards
x
on
Boards
x
etc. to
nstall Concrete Board
To Walls
Board
24 =
Joinery
SCHEDULE OF TASK WORK
RATES
PERIOD
1
2
J.C. Direct Labor Rates.
Joinery
Grade
No of Men
1
2
1
1
832.91
708.73
3
0
0.00
DailyTotal
6,663.24
5,669.88
0.00
J.C, Direct Labor Rates
Labourer
2
3
HrJEach
J.C.
0
0.00
0.00
BASE RATE:-
12,333.12
Fringe Benefits
Sick Leave
7.00
Public Holidays Not Worked
Holiday with Pay Vacation
Production Incentive
1.00
4.00
15.00
18.00
18.00% of
12,333.12
Leaders Rate 6% of
6,663.24
2,219.96
6.00
399.79
14,952.88
NOTES:
Construction Employment Premium
16% is {Now included in Base Hourly
Rate
For job rates, total team rate is divided by production
Job Work Total Rates include the construction employment premium and no further payment will be
made at the End of the Project.
a setoff, for remedial works, which if
dn
e
paid, by the Main Contracter within
7 days cf
acceotance of the works ( if any | corrected . providing such remedial works were dene by
the initial contracted Sub-L abourer/ Contractor
in the event the initial Sub- Labourer! Contractor, abandon the works. orIs terminated the
retention witheld may be used to provide relief ta the Main Contractor for correcting the works.
— 25—
Joinery
General suggested Job Work Rates Published
as a quide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays ( Not Worked ),Leaders Rate, and Production Incentive
based on project condition & location.
Refer to Clauses of the J.1.C Contract for Additional %age payment to be added
- SHOP RATES
to Arches Add
to
x3"
Top
x4"
x 6"
x
x 4"
x
"x3"
"x4
"x6"
Bevelled Top
WPP
Top
WPP.
Bevelled to Mah. Etc.
to
. Ete.
Bevelled to Mah. Etc.
Molded T
Molded Top
WPP
Molded Ts
“x3"
"x4"
"x6"
Molded Top
Molded Top
Top
x 1/2"
x 1/2"
x
Mah. Etc.
Mah.
Mah. Etc.
For Flush Doors W
or
Doors Cedar/WPP
WPP
7x3"
"x4
"x2"
"x3"
"x4"
"x2"
x 4"
x 6"
x 8"
x 4"
x 6"
WPP
3/3]3/3/3)3/3]/3]3/3(3/3/3 /3)3/31/3 [33 |3)3 1/3 [3 | 3]3 1/3 [3
JOINERY
For
WPP
:
Cedar/Mah.
Cedar/Mah.
Rails Molded:
Door/Ditto Frame WPP
Door Frames
Door Frames WPP.
Door Frames
Ete.
Door Frames Mah. Etc.
x 8" Door
es
WPP.
. Etc.
/2" x1 1/2" Door
f2"x11
(3/8" -
Etc.
and Fit
13/3/3/5/3]3/3
ng
WPP.
WPP
Mah.Ete.
Mah. Etc.
WPP Etc.
Etc.
3
x 4" Handrails
x
andrails
x 4" Handrails
x6"
x12" Treads
x 12" Treads
x1
Cedar/Mah.,
3/36
m
Rebates in Jamb &
x 4" Newel Post
3
PP
x4"
x2"
WPP
x 2" Baluster
Make
Com
6" x 2" Pane
(U
4" x3" and 1" x 4"
Door
Strips
Wx
Door
6" x 3" Pane
6" x 4" Pane
Make
. LID)
& Laminate
From Pine
Kitchen
51
e
|Laminate
From
Hx 1" W) From
96 —
Joinery
General suqgested Job Work Rates Published
_as a quide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays{ Not Worked ),Leaders Rate, and Production Incentive
Refer to Clauses of the J.C Contract for Additional “age payment to be added based on project condition
IMPERIAL
JOINERY - SHOP RATES
Notes
Nos.[1) For Gircular Frames to Arches Add 50% to
Rates
53
Make Kitchen Wall Cupboard (2' H x 1' W) From Cedar
|(Sprayed)
Total
Rate
UNIT
UNIT
Ft.Run
5,621
m
& location.
METRIC
Total
Rate
18,444
54
|Make Kitchen Wall Cupboard (2' H x 1' W) From Ply Only
Make Vanitory Cupboard (32" H x 22" W) From Plywood
Ft.Run
3,966
m
13,013
55
|(No LID)
Ft.Run
4,504
m
14,777
Ft.Run
5,138
m
16,859
Ft.Run
4,504
m
14,777
Ft.Run
5,457
m
17,905
Ft.Sq.
1,150
m2
12,381
FtSq.
804
m2
8,653
Make Vanitory Cupboard (32" H x 22" W) From Ply &
56
|Laminate (No LID)
Make Vanitory Cupboard (32" H x 22" W) From Pine
57
|(Sprayed)
("
)
59
Make Vanitory Cupboard (32" H x 22" W) From Cedar
|(Sprayed) (")
Make Serpentine Louvre (Rods, Blades,Stops,etc.) 40x
|16 14 Blades
60
|Make Fixed Louvre Doors (1 3/8" - 1 3/4") Thick
58
= Dye
Joinery
General suggested Job Work Rates Published
_as a quide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays { Not Worked ),Leaders Rate, and Production Incentive
based on project condition &
Refer to Clauses of the J.C Contract for Additional %age payment to be added
JOINERY - SITE RATES
‘Circular Frames to
Add 50%
WPP
Top
WPP
x 6"
x3"
"x4"
"x6"
"x3"
x4"
"x6"
x
"x4"
x6"
x1
Bevelled Top
Mah.
Top
Mah. ETC
Bevelled Top
Mah.
ETC.
Top
WPPMolded Top
W
Top
WPP
Molded Top
Mah. Etc.
Mah. Etc.
Molded Top
Mah. Etc.
‘ace
“edie
x
3/3/3|3/3/3|3]3/3/3|3]3|3
Bevelled Top
Bevelled
for Face of Flush Doors Cedar/Mah.
WPP
3"
"x4"
WPP
"xO
9"
Cedar/ Mah.
"xa"
Cedar,
x4"
Frames WPP
x 6" Door/Window Frames
x 8" Door
Frames WPP
x 4" Door/Window Frames
x6"
Frames Mah. Etc.
x 8" Door/Window Frames Mah.
Shower
Surface MTD.
Dish Furface MTD.
Towel Rails
Mounted
Towel Roll Holder
Toilet
Holder
Mtd.
Tooth
Holder Surf/Mtd/
f2"x11
/2" x1 1/2" Door
WPP
Mah. Etc.
x 3/4"
Materials
x 4" Handrails WPP
x 6"
x 4" Handrails Mah. Etc.
x6"
Etc.
x 12" Tread WPP
x 12" Treads
WPP Winders
Treads
x
etx 12"
x
x4"
x2"
WPP
WPP
WPP.
x 2" Balusters: Cedar/Mah.
secrete nailed) on and
10"
Fit and
Doors Small <2" 4"
Fit and
Casement Doors
e>
and
Fit and
and
Fit and
Fit and
Fit
it
Casement Windows
ent Windows
Raised Panel Doors
Doors
Closet Louvre Doors in
Hollow
Flush Door
Solid Core Flush Door
Steel Door & Frame
holes for
m
@ 3/3]3)3|3/3|3/3/3/3]3/3]3
9.
-
x3"
x 4"
3/3/3/3|3|3/3)3/3|3/3|3/3|3|3/3/3
o
nN
Slole}|rlo}a]s]elm|—=
Rates
tocation.
Joinery
General suggested Job Work Rates Published
_as a guide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays{ Not Werked ),Leaders Rate, and Production Incentive
Refer to Clauses of the J.1.C Contract for Additional “4age payment to be added based on project condition & jocation.
JOINERY - SITE RATES
IMPERIAL
Notes
Nos.|1) For Circular Frames to Arches Add 50% to
Rates
Total
Rate
UNIT
METRIC
UNIT
Total
Rate
Fit Double Stee! Doors and Frame Including Holes for
63 |Joggles
Each
7,476
Each
7,476
64
|Fit Night Lock, Indicator Bolt or Flush Bolt
Each
1,495
Each
1,495
65
|Fit Mortice Lock
Each
1,869
Each
1,869
66
|Fit Dead Lock
Each
2,136
Each
2,136
67
|Fit Double Action Mortice Lock
68
69
70
71
|Fit Panic Latch/Lock With Bars or Rails
|Fit Barre! Bolts Including Keeper In Floor
|Fit Casement Stay
|Fit Casement Pull
Fit Glass to Casement Door and Window With Including
|Putty
72
73 |Fit Glass to Casement Door & Window Including Strips
74
75
76
|Fit
|Fit
|Fit
Fit
Large Glass to Casement Ditto With/Including Putty
Large Glass Panels Including Strips
Mirrors on Walls Small < 5 Ft. Sq.
Mirrors. on Walls with Ply Backing Incl. Ply SM <
77 [Sft-Sq.
78
79
Fit Mirrors in Timber Frame on Walls incl. Frame SM<
[5tt.Sq.
|Fit Mirrors on Walls Large
80
|Fit Mirrors on Walls with Ply Backing Including Ply. Large
Fit Mirrors in Timber Frame on Walls Including Frame:
81 [Lg
82 | Shelving framed with 1" x 2" @ 2" On Center
83 |Install Kitchen Floor Cupboard Including Shelves
84
|Install Kitchen
85
|Install Kichen
Floor Cupboard
86
|Install Kitchen
87
88
89
90
|Install Kitchen Wall Cupboard Including Shelves
|Fit Metal Louvre Window in Masonry Opening
|Fit Metal Louvre Window In Timber Frames
|Fit Metal Jambs For Louvres In Masonry Opening
91
|Fit Metal Jambs For Louvres in Timber Frames
92
|Fit Door
93
94
95
96
|Fit Door Closers External
|Fit Hinges Alone 4" Butts
|Fit Hinges Alone 3" Butts
|Cut, Fit and Screw Timber Louvres to Metal Jamb
Floor Cupboard
Floor Cupboard
LID
Postformed
LID
Corian/Equal LID
Pull
97 |Fit Door Stop or Bumper
Each
2,991
Each
2,991
Each
Each
Each
Each
4,984
498
498
348
Each
Each
Each
Each
4,984
498
498
348
Each
230
Each
230
Each
230
Each
230
Ft.Sq.
Ft.Sq,
Ft.Sq.
220
220
427
m2
m2
m2
2,367
2,367
4,599
Ft.Sq.
427
m2
4,599
Ft.Sq.
Ft.Sq.
427
374
m2
m2
4,599
4,024
Ft.Sq.
374
m2
4,024
Ft.Sq.
Ft.Saq.
Ft.Run
374
220
2,490
m2
m2
m
4,024
2,367
8,171
Ft.Run
4,150
m
3,774
Ft.Run
1,495
m
4,906
Ft.Run
1,495
m
4,906
Ft.Run
Ft.Sq.
Ft.Sq.
Ft.Run
1,870
393
305
305
m
m2
m2
m
6,135
4,236
3,285
1,001
FtRun
234
m.
767
Each
1,068
Each
1,068
Each
Pair
Pair
Each
2,136
623
534
374
Each
Pair
Pair
Each
2,136
623.
534
374
267
Each
267
Each
98
|Adjust Clips and Fit Glass Louvres to Metal Jambs
Each
130
Each
130
99
|Caulk Both Sides of Jambs with Compound
Ft.Run
64
m
209
Ft.Sq.
Ft.Sq.
1,359
374
m2
m2
14,632
4,024
Assemble & Fit Serpentine Louvres Complete
4100|/40"x16"x14 Blades
101|Make Strips and Install Lattice In Frames With Strips
20x
Painting
SCHEDULE OF TASK WORK
RATES
PERIOD
4
J.C.
Direct Labor Rates
Painting
2
DailyTotal
Grade
No of Men
HrJEach
4
4
655.91
5,247.24
2
4
595,53
4,764.21
3
o
0.00
0.00
J.C. Direct Labor Rates
Labourer
BASE RATE:-
3.
J.LC,
10,011.45
Fringe Benefits
1.00
Sick Leave
Public Holidays Net Worked
1.00
Holiday with Pay Vacation
1.00
Production Incentive
15.00
18.00
18.00% of
Leaders Rate 6% of
1,802.06
10,011.45
5,247.24
314.83
6.00
412,128.35
TEAM RATE :-
NOTES:
1
Construction Employment Premium
16% is (Now included in Base Hourly Rate
2
For job rates, total team rate is divided by production
3
further payment
Job Work Total Rates include the construction employment premium and no
will be made at the End of the Project.
4
Retention of 10% to 2 maximum of Ste 2 tolal earnings may be witheldé-ageinstal sik
7.davs
of acceptance of the works( if any } corrected
done by the initial contracted Sub-Labourer! Contractor
providing such remedial works were
Painting
General suggested Job Work Rates Published
_as a quide for the Industry
Refer to Clauses of the J..C Contract for Additional %age payment to be added based on project condition &
IM
focation.
METRIC
otal
als|a|afeo|e|~/ofal=folo|=
Rate
all- Two
Paint -
“J
2
®
Coat
- Two Coats:
- Two
Paint - Wood Floor - Two Coats
al Gfoms
Painting
General suggested Job Work Rates Published
_as a quide
for the Industry
based on project condition & location.
Refer to Clauses of the J.1.C Contract for Additions! Sage payment to be added
- Rafter - One
=32=
Plumbing
SCHEDULE OF TASK WORK
RATES
PERIOD
J.C.
Direct Labor Rates
Plumbing
Grade
No of Men
HrJEach
DailyTotal
1
2
1
41
729.66
611.84
5,837.30
4,894.74
3
0
0.00
4
457.03
3,656.22
BASE RATE:-
14,388.23
0.00
J.1.C. Direct Labor Rates
Labourer
2
J.C. Fringe Benefits
Sick Leave
Public Holidays Not Worked
Holiday with Pay Vacation
Production Incentive
1.00
1.00
4.00
15,00
18.00
18.00% of
14,388.23
Leaders Rate 6% of
2,589.88
5,837.30
6.00
TEAM RATE :-
350.24
17,328.35
NOTES :
Construction Employment Premium
16 %
is
(Now inchided in Base Hourly Rate }
For job rates, total team rate is divided by production
Job Work Total Rates include the construction employment premium and no further payment will be
made at the End of the Project.
Retention of 16.%
to # maximum
@.setoff, for remedial works.
acceptance of the works if any
of 5% of total earnings may be withald against all work as
if withheld must be naid, by the Main Contractor within 7 days of
guch remedial
works were done by |
} co!
{40 tha Main Cor
Qc
3,97 Is terminated the
ctor for correcting the works.
Plumbing
General su’
ested Job Work Rates Published
_as a
guide for the Indus!
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays { Not Worked ),Leaders Rate, and Production Incentive
be added based on project condition & tecation.
Refer to Clauses of the J.I.C Contract for Additional %ago payment to
‘otal
PLUMBING
Rate
PVC PIPES & FITTINGS
DRAINAGE
284
473
Diameter
95.
95
403
244
1
Three End
With Mixer and Waste
Connection
Water Heater (30 - 40) Gal. With B/Off, Supply
Hot & Cold
=94=
Plumbing
General suggested Job Work Rates Published
_as a quide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays { Not Worked ),Leaders Rate, and Production Incentive
Refer to Ciauses of the
Nos
Contract for Additional %age payment te be added based on project condition &
|-WATER SUPPLY
1/4" Diameter
Diameter
Diameter
40
Double
40
Schedule
1/2" Dia. Gate Valve
Ends) and
—~35--
location.
Plumbing
General suggested Job Work Rates Published
as a
quide for the Indus
Included in the calculation are:- Sick Leave, Holiday with Pay,
Public holidays{ Not Worked ) Leaders Rate, and Production Incentive
&
Additional “sage payment to be added based on project condition
for
Rofer to Clauses of the J.C Contract
= WATER SUPPLY
~36 —
location.
Scaffolding
SCHEDULE OF TASK WORK
PERIOD
RATES
J.LC. Direct Labor Rates
Scaffolding
Grade
No of Men
41
2
3
J.C.
HrJEach
41
41
4
DailyTotal
619.98
559.47
468.56
4,959.81
4,475.72
3,748.44
Direct Labor Rates
Labourer
2
0
0.00
BASE RATE:J.1.C.
0.00
13,183.97
Fringe Benefits
Sick Leave
1.00
Public Holidays Not Worked
Holiday with Pay Vacation
Production Incentive
1.00
1.00
15.00
18.00
18.00% of
13,183.97
Leaders Rate 6% of
2,373.12
4,959.81
6.00
297.59
TEAM RATE :-
15,854.68
NOTES:
Construction Employment Premium
16%
is (Now includedin Base Hourly Rate }
For job rates, total team rate is divided by production
Job Work Total Rates include the construction employment premium and no further payment will be
made at the End of the Project.
wither
ainst all work
f , for remedial works, which if withheid
mu
é oald, by the Main Contractor within 7 days of
acceptance of the works
i
the
initial contracted
S:
cied Sul
urer! Contract
nH
in the event the initial ub- Labourer! Contractor, abandon the works. or is terminated the
fetention witheld may be used to provide relief to the Main Contractor for correcting the works.
=v.
Scaffolding
General suggested Job Work Rates Published as a guide for the Industry
Included in the calculation are:- Sick Leave, Holiday with Pay,
Refer to Clauses of the J.C
Unbraced
Incentive
Public holidays { Not Worked ),Leaders Rate, and Production
&
Contract for Additional %age payment to be added based on project condition
to
Upto 10°
Tied to
Braced
Formwork Soffit
Board 10' to 20°
to
Dismantie
Above 40"
~38-
location.
Tiling
SCHEDULE OF TASK WORK
RATES
PERIOD
J.C, Direct Labor Rates
Tiling
Grade
No of Men
1
2
3
Hr/Each
0
1
1
0.00
681.11
591.55.
DailyTotal
0.00
5,448.90
4,732.38
J.1.C. Direct Labor Rates
Labourer
2
0
J.C.
Fringe Benefits
0.00
BASERATE:-
0.00
—~—~—=«*10,187.28
1.00
1.00
1.00
15.00
18.00
18.00% of
10,181.28
Leaders Rate 6% of
5,448.90
TEAM RATE :-
1,832.63
6.00
326.93
12,340.84
NOTES:
Construction Employment Premium
For job rates, total team rate is divided by production
Job Work Total Rates include the construction employment premium and no further payment will be
made at the End of the Project.
Retention of 1
:
ff, for remedial works,
which if wi
a SGion
days. of,
Tiling
to be added based on project condition &
Refer to Clauses of the J.C Contract for Additional “age payment
location.
METRIC
For
12+)
Floors
Grout and Clean
Tiles 6" Lay with
Grount and Clean.
Clean,
& Clean
In Wall
in Wall
Grout &
to
and Walls
Floors and Walls
Columns and Beams
Columns and Beams’
~- 40-
Welding
|
1
SCHEDULE OF TASK WORK RATES
PERIOD
1202
|
To
|
31.1..2023
J.C. Direct Labor Rates
Welding
2
Grade
No of Men
Hr./Each
41
1
728.75
5,829.99
2
1
634.93
5,079.44
3
0
0.00
0.00
0
0.00
0.00
J.C.
DailyTotal
Direct Labor Rates
Labourer
2
BASE
3
RATE:-
10,909.43
JLC. Fringe Benefits
Sick Leave
Public Holidays Not Worked
Holiday with Pay Vacation
Production Incentive
1.00
4.00
1.00
15.00
18.00
18.00% of
Leaders Rate 6%
10,909.43
of
5,829.99
1,963.70
6.00
TEAM RATE :-
349.80
13,222.92
NOTES:
1
Construction Employment Premium
16%
is {Now included in Base Hourly Rate
2
Far job rates, total team rate
is divided by production
3
Job Work Total Rates include the construction employment premium and no further payment
will be made at the End of the Project.
4
Retention of 10% to_a maximum of 5% of total earnings may be witheld against all work as.
a setoff. for remedial works,
—41—-
which If withheld musi be paid. by the Main Contractor within
Welding
to be added based on project condition &
Refer to Clauses of the J.I.C Contract for Additional Yage payment
location.
METRIC
‘otal
DRILLING WELDING INSTALLATION
&
Torch
Torch
Torch
Torch
Torch
Torch
Cut
Torch
CPSAW
CPSAW
CPSAW
CPSAW
CPSAW
Mark Cut
CPSAW
CPSAW
4/8"
x1
Through (
- 14
With Press
Holes
=
with Press
=1
with Press
with Press
with Press
with Press
=
Through
with Press
»
*)
with Press
18"
1
with Press
-1
with Press
with Press.
with Press
Thick with Press
-
(7/8" = 1
with Press
with Press
=4
(7/8"
-
with Press
-
Through
- 1/4
Hand Drill
-1
Hand Drill
whe
Welding
Refer to Clauses of the J.C Contract fer Additional %ege payment to be added based on project condition &
DRILLING WELDING INSTALLATION
1/8" ~ 1/4")
Hand Drill
Hand Drill
Drill Holes (1/8"~
Hand Drill
“1
Hand Drill
Hand Drill
Holes
e
eter
with Hand Drill
1/8"-1
Dia.
Hand Drill
Hand Drill
Holes (5/8"-.
Hand Drill
18"-1
with Hand Drill
with Hand Drill
with Hand Drill
with Hand Drill
with Hand Drill
Drill
1/8"
with Torch
with Torch
Drill Holes
41
with Torch
with Torch
with Torch
with Torch
Holes
=
with Torch
=f
with Torch
18"
with Torch
Holes
'~1/2")
with Torch
Diameter
with Torch
a]
with Torch
with Torch
with Torch
with Torch
'- 1") Diameter Through
Torch
" Fillett Weld
Fillet Weld
Butt Weld
-1
location.
Welding
Refer to Clauses of the J.1.C Contract for Additional %age payment
DRILLING WELDING INSTALLATION
Weld
to
Up
S41
.
Ls.
to 3" Girth: Solid
Ls. RHS.
elt,
Above 6" Girth Solid
Gutter
cover 4
Covers
Make Covers 1/8" Thick Plate With Handle 12" x 12"
Covers 1/8" Thick Plate With Handle 18" x 18"
Covers 1/8" Thick Plate With Handle 24" x 24"
Make Covers 3/16" Thick Plate With Handle 12" x 1
Make Covers 3/16" Thick Plate With Handle 18" x 1
to be added based on project condition &
focation.
Welding
Refer to Clauses of the J.LC Contract for Additional %age payment to be added based on project condition &
Nos._|CUTTING DRILLING WELDING
INSTALLATION
UNIT
100
|Make Covers 3/16" Thick Plate With Handle 24” x 24"
Each
401
|Make Covers 1/4" Thick Plate With Handle 12" x 12"
102
|Make Covers 1/4" Thick Plate With Handle 18" x 18”
103
IMPERIAL
Total
Rate
UNIT
location.
METRIC.
Total
Rate
2,645
Each
2,645
Each
1,469
Each
1,469
Each
2,204
Each
2,204
|Make Covers 1/4" Thick Plate With Handle 24" x 24"
Each
2,645
Each
2,645
104
|Make Covers 3/8" Thick Plate With Handle 12" x 12"
Each
1,653
Each
1,653
105
|Make Covers 3/8" Thick Plate With Handle 18" x 18”
Each
2,204
Each
2,204
106
[Make Covers 3/8" Thick Plate With Handle 24" x 24"
Each
3,306
Each
3,306
4107
|Make Covers
12" x 12"
Each
1,653
Each
1,653
108
|Make Covers 1/2" Thick Plate With Handle 18" x18"
Each
2,645
Each
2,645
|Make Covers
Each
3,306
Each
3,306
Ft.Sq.
735
m2
7,907
Ft.Sq.
661
m2
7,117
Ft.Sq.
630
m2
6,778
Fi.Sq.
Each
1,017
696
Ft.Sq.
139
m2
1,498
Ft.Sq.
249
m2
2,686
m2
2,333
109
110
111
112
1/2" Thick Plate With Handle
1/2" Thick Plate With Handle 24" x 24"
Make Louvre Grill 1 1/4" x 1/4" & 1/2" x 12" @ On
|Center HZ SGL/Bay
Make Louvre Grill 1 1/4" x 1/4” & 1/2" x 1/2" @ 4" On
|Center HZ DBL/Bay
Make Louvre Grill 1 1/4"x 1/4" & 1/2" x 1/2" @ On
|Center HZ TPUBay
Make Gate Grill 1 1/4" x 1/4" & 1/2" x 1/2" @ 4" 12”
113
114
115
116
117
118
419
120
4121
122
|On Center VT & HZ
|Make Hinges Fram 3/4" Pipe & 5/8" Bar 4.5" Long
Priming Grill Work 1/2" x 4/2" @ 4" cc Measured Flat
|One Side
Installation of Grills In Masonry Opening Less Than 8
|FtSq.
Installation of Grills In Masonry Opeing > Than 8
|Ft.Sq.
Make Column Clamps 1/4" x 3” x 48" Flat With Bend
|& Slots
Make Column Clamps Wedges 1/4" x 7 1/2"x 6" Flat
|With Tapers
Make wall Ties (Bolts) 1/2" x 36" With End Plate &
|Threading
Make Wall Tie Washers 1/4” x 3" x 3" With 1/2"
|Diameter Hole
Make Gratings 1" x 1/4" Flat @ 1" On Centered 18" x
|18"
Make Gratings 1" x 1/4" Flat @ 1" On Centered 24" x
123 |24"
124
125
126
127
128
Make
|30"
Make
|18"
Make
|24"
Make
|30"
Make
|18" x
Ft.Sq.
217
m2
Each
10,849
696
Each
1,017
Each
1,017,
Each
165
Each
165
Each
551
Each
551
Each
281
Each
281
Each
6,611
Each
6,611
Each
9,445
Each
9,445
Each
13,223
Each
13,223
Each
3,778
Each
3,778
Each
5,289
Each
5,289
Each
6,611
Each
6,611
Each
7,778
Each
7,778
Gratings 1" x 1/4" Flat @ 1" On Centered 30" x
Gratings 1" x 1/4" Flat @ 2" On Centered 18" x
Gratings 1" x 1/4" Flat @ 2" On Centered 24" x
Gratings 1" x 1/4" Flat @ 2" On Centered 30" x
Gratings 2" x 1/4" Flat @ 1 1/2” On Centered
18"
Welding
to be added based on project condition &
Refer to Clauses of the J.C Contract for Additional “age payment
DRILLING WELDING INSTALLATION
x
129 |24" x
130
24"
Flat @ 4
2x
x30"
Make
131 |18"
132
133
|30"
~- 46 --
Iecation.
Electrical
SCHEDULE OF TASK WORK
[
1
1.2 2022
|
RATES
PERIOD
To
I
311.203
|
J.C. Direct Labor Rates
Electrical
Grade
2
No of Men
Each
1
2
1
41
812.25
690.00
3
1
Total
6,498.04
5,519.96
0.00
J.C. Direct Labor Rates
Labourer
2
0
0.00
BASE RATE:-
3
J.I.C. Fringe Benefits
Sick Leave
Public Holidays Not Worked
Holiday with Pay Vacation
Production Incentive
0.00
12,018.00
1.00
1.00
1.00
15.00
18.00
18.00% of
12,018.00
Leaders Rate 6% of
6,498.04
2,163.24
§.00
TEAM RATE :-
389.88
14,571.12
NOTES:
1
Construction Employment Premium
16%
is {Now inciuged in Base Hourly Rate}
2
For job rates, total team rate
is divided by production
3
Job Work Total Rates include the construction employment premium and no further payment will be
made at the End of the Project.
4
ae
the
tance of the works (ifif any 1 corrected , providing such remedial works were done by
8 contracted Sul Labourer, nontas!
retention witheld may
be used to rovide relief
|
to the Main Contractor for “correcting the works.
aay a
Electrical
Refer to Clauses of the J.1.C Contract for Additional %age
Rates are for Basic Residential Construction
payment to be added based on project condition & location.
IMPERIAL
Total
Rate
3/3)3)3)3|3
with
4/2" diameter
diameter
1" diameter
4-1/4" diameter
1-1
2" diameter
renches
3/3)3/3]3/3)3
Installation
with
4" diameter
1diameter
1-1/2" diameter
2-1/2" diameter
diameter
a"
a"
Switch &
5
.
20
5
. & blank
&
Boxes
6" Hx
BWx4"D
x8"Wx4"D
10" Hx 12"W
x6" D
1
x 20" Wx 8" D
Hx 24" Wx
H x 36"
W x 8" D
boards
with 10 branch breaker
with 14
breaker
18 branch breaker
4
150
15 amp
&C/
dimmer
switch with
2-3
outlet,
15 amp
nsulated Wires and Cables
2.5 mm2
4mm2 PVC
Wire
40 mm2 PVC
16
PVC
Wire
mm2
mm2 PVC
Wire
50 mm2
Wire
mm2 PVC
Wire
95 mm2
Wire
20 mm2 PVC
150
Wire
mm2 PVC
3/3]3 /3]3/3/3/3|3|3/3]3/3
1
Electrical
Refer to Clauses of the J.l.C Contract for Additional ‘sage payment to be added based en project condition & focation,
Rates are for Basic
IMPERIAL
Total
10
16
25
35
3/3 /3/3/3]3/3/3]3/3/3/3
mm2 Bare
4mme2 Bare
mm2 Bare
mm2
mm2 Bare
mm2 Bare
mm2 Bare
70 mm2 Bare
420 mm2 Bare
150
mm2 Bare
mm2
3/3/3/3]3/3/3/3/3]3/3/3/3
4mm2 PVC
6 mm2 PVC
16
25
35
50.
mm2 PVC
mm2
mm2 PVC
mm2 PVC.
95 mm2 PVC
20 mm2
Pvc
mm2 PVC
3/3 /3/3/3/3/3/3/3]3/3]3/3
mm2 PVC
mm2 PVC
6 mm2 PVC
10
mm2 PVC
mm2
mm2 PVC
mm2 PVC
20 mm2
50 mm2 PVC
mm2
—49—
«)
Download