API 510 OPTIONAL WORKBOOK
API-510 PRESSURE VESSEL INSPECTOR CERTIFICATION EXAMINATION
PREPARATION COURSE
Presented by Intertek Consulting & Training in Association with CKRC Training
Solutions cc
Developed by CKRC Training Solutions cc
Module: 2.1 (Optional)
Subject: General – API 510, Pressure Vessel Inspection Code In-Service Inspection,
Rating, Repair, and Alteration
Author
Kevin Robert Maley
This courseware is based on the API 510 Body of Knowledge approved for the
API 510 Certification examination.
Unauthorized reproduction, distribution or incorporation of the material
contained in this workbook is a violation of copyright law.
Publication, Distribution and Copyright withheld by CKRC Training Solutions cc.
2023API.CKRC.DOC
Page 1
API 510 OPTIONAL WORKBOOK
Module Objective:
The Inspector shall have a sound general knowledge of the entire API 510 Code (Section 9 and Annex E are
excluded as per BOK).
Note: As API is in the process of developing new question formats (AIT's), CKRC is also adding new questions &
question banks to our courses.
These additional Modules are entirely optional and still in the developmental stages - we encourage students
to challenge as many questions as they want/need. We have not included a reading assignment, but Module
2.1 is also based on the API 510 document and can be attempted as either Open or Closed book.
The Quiz is not timed and can be attempted multiple times.
Module Instructions
Module 2.1 is in a test format.
This is an opportunity to familiarize yourself with the Recommended Practice and to test your current
understanding and knowledge base.
There will be three sections to this module
Section 1
 Review module and identify the required reading assignments (RA).
 Thoroughly complete the RA (This may need to be read through several times depending on your
familiarity with the material).
 NB: It is highly discouraged that the test questions be reviewed prior to attempting the RA.
Section 2
A downloadable PDF document containing the questions to work with offline.
(The test will have the same questions that will be found within the quiz; however, the order of the responses
may differ).
 Attempt the module test paper as an open book attempt (Record all reference and calculations, if
applicable).
 NB. All references and calculations should be recorded for comparison with the references provided
during the online quiz. This will be essential in later discussions of any problem areas that the student
requires further clarification or assistance.
Section 3
An online quiz containing the questions for grading purposes. This is an open book test.
 Each quiz will require a passing mark of 95% to signify module completion.
 The score and references for all correct answers will be available once the quiz is submitted.
 If a score of less than 95% is obtained the student should repeat the questions that were marked as
incorrect.
 There is no limit to the number of attempts.
 If a score of ≥95% cannot be obtained and / or there is disagreement with any of the proposed answers,
references or calculations provided, the student should submit a request for assistance / clarification
to the course instructor.
NB. It is essential that test / quizzes be attempted by each individual, collaboration on tests and quizzes is highly
discouraged, and will defeat the intent of the preparation course and will only become evident in the final score
of the API ICP Examination.
For any course related queries, please comment in a discussion post or email carike.maley@ckrctraining.co.za.
For any IT related queries, please contact carike.maley@ckrctraining.co.za or melissa@ckrctraining.co.za.
Publication, Distribution and Copyright withheld by CKRC Training Solutions cc.
2023API.CKRC.DOC
Page 2
API 510 OPTIONAL WORKBOOK
Module 2.1 Test 1
Number of questions: 42
Recommended Time limit: None
1) Define Localized Corrosion (Choose the correct option - only 1 answer is correct)
a) Corrosion that is not confined to a limited or isolated area of the metal surface of a pressure vessel.
b) Corrosion that is largely confined to a limited or isolated area of the metal surface of a pressure
vessel.
c) Corrosion that is strictly confined to a limited or isolated area of the metal surface of a pressure
vessel.
d) Corrosion of any area of the metal surface of a pressure vessel.
2) True/False: A pressure boundary is the portion of the pressure vessel that contains the pressure retaining
elements joined or assembled into a pressure tight, fluid-containing vessel.
a) This statement is true.
b) This statement is false.
3) Define the following acronym by choosing one of the options below: E&P
a) Expedition and Production.
b) Exploration and Processes.
c) Exploration and Production.
d) Exploration and Pressure.
4) Complete the following sentence by selecting the missing words (drag & drop answer into the statement).
An owner/user of pressure vessels _______ exercise control of the vessel and pressure relief device
inspection program, inspection frequencies, and maintenance and is responsible for the function of an
authorized inspection agency in accordance with the provisions of this Code.
a) should
b) shall
c) could
d) would
5) True/False: when pressure equipment integrity may be affected, concerning the MOC process - the
inspection group need not be involved in the approval process for changes that may affect pressure vessel
integrity.
a) This statement is true.
b) This statement is false.
Publication, Distribution and Copyright withheld by CKRC Training Solutions cc.
2023API.CKRC.DOC
Page 3
API 510 OPTIONAL WORKBOOK
6) Operating, maintenance, engineering (process and mechanical), or other personnel who have special
knowledge or expertise related to particular pressure vessels shall be responsible for timely notification to
the inspector or engineer of potential issues that may affect vessel integrity such as? (Multiple response)
a) any unusual conditions that may develop (e.g. noises, leaks, vibration etc.)
b) vessel failures, repair actions conducted, and failure analysis reports.
c) any action that requires MOC.
d) operations outside defined IOW.
7) In accordance with API 510; which of the following processes can be used where thickness measurements
are obtained for CMLs, that will ensure that a minimum thickness at a CML is located? (multiple response)
a) Ultrasonic measurements.
b) Magnetic Particle Testing.
c) Eddy Current Testing.
d) Radiography.
8) In accordance with API 510; more or fewer CMLs should be selected for pressure vessels with any of the
following characteristics: (match the correct answers)
More CMLs
Low potential for creating a safety or
environmental emergency in the event of a leak.
Higher expected or experienced corrosion rates.
Fewer CMLs
Higher potential for localized corrosion.
Generally uniform corrosion rates.
Relatively noncorrosive contents
9) In accordance with API 510; if inspection of a piece of pressure equipment is to be deferred beyond the
established interval, which of the procedures below should be included? (multiple response)
a) Any required operating controls needed to make the extended run.
b) Verify pressure-relieving devices satisfy design requirements.
c) Need for appropriate nonintrusive inspection with NDE, if any, is needed to justify the temporary
extension.
d) Field metallographic replication for identifying metallurgical changes.
e) Proper documentation of the deferral in the equipment records.
10) True / False: Inspection repair recommendations that cannot be completed by their due date can be
deferred for a non-specific period of time by a documented change in date of required completion.
a) This statement is true.
b) This statement is false.
11) In accordance with API 510; which Code should be consulted for guidelines on the inspection and repair of
shell and tube heat exchangers?
a) ASME PPC-1, Article 3.12.
b) ASME PPC-2, Article 3.12.
c) ASME PPC-2, Article 4.12.
d) ASME PPC-1, Article 4.12.
Publication, Distribution and Copyright withheld by CKRC Training Solutions cc.
2023API.CKRC.DOC
Page 4
API 510 OPTIONAL WORKBOOK
12) In accordance with API 510; examples of different types of CMLs include locations for _________,
locations for ___________ and locations for __________. (Select the missing word(s) to correctly
complete the sentence – (Multiple response)
a) thickness measurement.
b) low-temperature hydrogen attack examinations.
c) stress corrosion cracking examinations.
d) high-temperature hydrogen attack examinations.
13) True/False: The examiner does not need API 510 inspector certification and does not need to be an
employee of the owner/user.
a) This statement is true.
b) This statement is false.
14) Each owner/user organization should be audited periodically to determine if the inspection agency is
meeting the requirements of the API 510 inspection Code. The audit team should determine in general
whether (multiple response):
a) The requirements and principles of this inspection Code are being met.
b) Documented inspection plans are in place for covered pressure vessels.
c) Owner/user responsibilities are being properly discharged.
d) Inspection data analysis, evaluation, and recording are adequate.
15) In accordance with API 510; which Code should be consulted for more information on inspection of heat
exchangers?
a) API 571, Annex A.
b) API 572, Annex A.
c) API 573, Annex A.
d) API 574, Annex A.
16) In accordance with API 510; the examiner shall perform the NDE in accordance with _________,
________, ____________. (Multiple response) – choose from the list below to correctly complete the
sentence.)
a) job requirements.
b) operations outside defined IOW.
c) NDE procedures.
d) owner/user specifications.
e) extent of previous examination.
17) In accordance with API 510; when nonconformances are found, should the owner/user authorized
inspection agency take necessary corrective actions?
a) Yes.
b) No.
Publication, Distribution and Copyright withheld by CKRC Training Solutions cc.
2023API.CKRC.DOC
Page 5
API 510 OPTIONAL WORKBOOK
18) IOWs should be established for process parameters (both _______ and _______) that could impact
equipment integrity if not properly controlled. (Fill in the missing word(s) to correctly complete the
sentence.
a) physical, chemical.
b) physical, controlled.
c) pressure, chemical.
19) Match the following Terms, Definitions, Acronyms or Abbreviations to the correct description. (Drag &
Drop the correct term/definition/acronym or abbreviation to their description)
Approval/agreement to perform a specific activity
CDW.
(e.g. repair) prior to the activity being performed.
Designated areas on pressure vessels where periodic Authorized inspection agency.
external examinations are conducted in order to
directly assess the condition of the vessel.
An imperfection whose type or size exceeds the
Examination Point.
applicable acceptance criteria and is therefore
rejectable.
An area within a CML defined by a circle having a
Inspection.
diameter not greater than 3 in. for pressure vessels.
The inspection organization of an insurance
Authorization.
company that is licensed or registered to write and
does write pressure vessel insurance.
The external, internal, or on-stream evaluation (or
Defect.
any combination of the three) of the condition of a
vessel conducted by the authorized inspector or
his/her designee in accordance with this Code.
Any welding technique used to obtain controlled
CMLs
grain refinement and tempering of the underlying
heat-affected zone in the base metal.
20) Which of the following Normative references are indispensable for the application of the API 510
document? (Multiple response – more than one response may be correct/incorrect, only select those
which you know as true)
a) API RP 571, Damage Mechanisms Affecting Fixed Equipment in the Refining Industry.
b) API Standard 574, Inspection Practices for Piping System Components.
c) API RP 582, Welding Guidelines for the Chemical, Oil and Gas Industries.
d) API RP 2201, Safe Hot Tapping Practices for the Petroleum and Petrochemical Industries.
e) ASME B31.3, Process Piping.
f) ASME Boiler and Pressure Vessel Code, Section VIII: Rules for Construction of Pressure Vessels; Division
1.
21) What is an IOW?
a) Established limits for process variables (parameters that can affect the integrity of the equipment if
the process operation deviates from the established limits for a predetermined amount of time.
b) A document that contains data and information from the manufacturer of the pressure vessel that
certifies that the materials of construction contained in the vessel meet certain material property
requirements, tolerances, etc.
c) A condition where a pressure vessel has not been prepared for an internal inspection.
d) An inspection performed from the outside of a pressure vessel while it is on-stream using NDE
procedures to establish the suitability of the pressure boundary for continued operation.
Publication, Distribution and Copyright withheld by CKRC Training Solutions cc.
2023API.CKRC.DOC
Page 6
API 510 OPTIONAL WORKBOOK
22) Which of the processes below should be included in the owner/user organization’s pressure
vessel/pressure-relieving device inspection systems and inspection/repair systems and procedures to
meet the requirements of the API 510 inspection Code? (multiple response)
a) Corrective action for inspection and test results.
b) Training requirements for inspection personnel regarding inspection tools, techniques, and technical
knowledge base.
c) Internal auditing for compliance with the QA inspection manual.
d) Establishing and documenting the appropriate inspection intervals.
23) In accordance with API 510; who is responsible to the owner/user to assure that the inspection, NDE,
repairs, and pressure testing activities meet API 510 Code requirements?
a) Inspection engineer.
b) Owner/user.
c) Inspector.
d) Operator.
24) If detailed thickness grids are needed in a specific CML to perform FFS assessment of the metal loss; which
Code should be referred to for preparation of such thickness grids? (Multiple response)
a) Parts 4 and 5 of API 579-1.
b) ASME FFS-1.
c) ASME FFS-2.
d) Parts 2 & 3 of API 579-1.
25) True / False: In accordance with API 510 the risks associated with operational shutdown and start-up and
the possibility of increased corrosion due to exposure of vessel surfaces to air and moisture should be
evaluated when an internal inspection is being planned.
a) This statement is true.
b) This statement is false.
26) In accordance with API 510; may an inspection or pressure relief device servicing interval be deferred by
the inspector without other approvals, based on review of equipment history and appropriate risk
analysis?
a) Yes.
b) No.
27) May RBI assessments be used to establish the appropriate inspection intervals for internal, on-stream, and
external inspections, as well as inspection and testing intervals for pressure-relieving devices?
a) Yes.
b) No.
Publication, Distribution and Copyright withheld by CKRC Training Solutions cc.
2023API.CKRC.DOC
Page 7
API 510 OPTIONAL WORKBOOK
28) RBI assessments should be in compliance with the recommended practices of which other Code?
a) API 510.
b) API 570.
c) API 580.
d) API 653.
29) Which of the following Codes have additional guidance on material verification programs such as PMI
testing?
a) API 578.
b) API 576.
c) API 579.
d) API 577.
30) In accordance with API 510; does the examiner’s employer need to maintain certification records of the
examiners employed for the inspector who is responsible to the owner/user to determine that all NDE
examiners are properly qualified for the work they perform?
a) Yes.
b) No.
31) Complete the following sentence by selecting the missing words (drag & drop answer into the statement).
Management ______ have an appropriate requirement and work process to ensure that inspectors have
an annual vision test to ensure that they are capable of reading standard J-1 letters on standard Jaeger
test type chards for near vision.
a) should
b) shall
c) could
d) would
32) Is the pressure vessel engineer responsible to the owner/user for activities involving design, engineering
review, analysis, or evaluation of pressure vessels and pressure-relieving devise as specified in the API 510
inspection Code?
a) Yes.
b) No.
33) The RBI assessment shall be reviewed and approved by the engineer and inspector at intervals not to
exceed ___ years. (Choose an option to correctly complete the sentence)
a) 2
b) 5
c) 10
d) 20
Publication, Distribution and Copyright withheld by CKRC Training Solutions cc.
2023API.CKRC.DOC
Page 8
API 510 OPTIONAL WORKBOOK
34) Which of the following entities make repairs in accordance with the API 510 inspection Code? (Multiple
response – more than one response may be correct/incorrect, only select those which you know as true)
a) The holder of a valid ASME Certificate of Authorization that authorizes the use of an appropriate
ASME Code symbol stamp.
b) A repair contractor whose qualifications are acceptable to the pressure vessel owner or user.
c) The holder of a valid R-stamp issued by the National Board for repair of pressure vessels.
d) The holder of a valid SR-stamp issued by the National Board for repair of pressure vessels.
35) True/false: API 580 provides methods of conducting RBI in accordance with the principles in the Code.
a) This statement is true.
b) This statement is false.
36) True/False: A pressure vessel not in operation because of a process outage is not considered an in-service
pressure vessel.
a) This statement is true.
b) This statement is false.
37) Define the following acronym by choosing one of the options below: IOWs
a) Integral Operating Windows.
b) Integrity Offshore Windows.
c) Integrity Operating Welding.
d) Integrity Operating Windows.
38) True/False: A “heat-affected zone” is the portion of the base metal whose mechanical properties or
microstructure have been altered by the heat of welding or thermal cutting.
a) This statement is true.
b) This statement is false.
39) True / False: CMLs with the highest corrosion rates and the most remaining life shall be included in next
planned examinations.
a) This statement is true.
b) This statement is false.
40) True / False: Inspector recommendations cannot be changed or deleted after review by pressure vessel
engineer or inspection supervision.
a) This statement is true.
b) This statement is false.
Publication, Distribution and Copyright withheld by CKRC Training Solutions cc.
2023API.CKRC.DOC
Page 9
API 510 OPTIONAL WORKBOOK
41) True / False: An inspection plan shall be established for all pressure vessels and pressure-relieving devices
within the scope of the API 510 Code.
a) This statement is true.
b) This statement is false.
42) Define the following acronym by choosing one of the options below: WPS
a) Welding procedure specification.
b) Welding procedure services.
c) Working procedure specification.
d) Welding process specification.