ACCT 102 Management Accounting Practice Questions – Job‐order Costing 1. Which industry is most unlikely to use a job-order costing system? A. construction B. aircraft C. printing of textbooks D. production of beer E. software development Answer: [___________________] Use the following information for question 2 to 5 Jia Jia Company has 2 departments. Manufacturing overhead costs are applied based on direct labour cost in Department (Dept) A and machine hours in Department (Dept) B. The following information is available for the month of October 2012. Budget Direct labour costs Machine hours Manufacturing overhead costs Actual Job#8 Direct materials costs Direct labour costs Machine hours Job#9 Beginning Work in Process Direct materials costs Direct labour costs Machine hours Job #10 Direct materials costs Direct labour costs Machine hours Dept. A $180,000 51,000 $225,000 Dept. B $165,000 40,000 $180,000 Units Dept. A Dept. B 100 $10,000 $11,000 5,000 $13,000 $14,000 3,000 $5,000 $9,000 $13,000 2,000 $4,000 $11,000 $16,000 4,000 $9,000 $8,000 8,000 $9,000 $12,000 5,000 120 50 Due to a lack of materials, Job#9 remains incomplete at the end of October 2012. Only Job#8 and Job #10 were completed. There were no other jobs in October 2012. 2. Compute the budgeted Manufacturing Overhead rate for Department A and Department B. Answer: Manufacturing Overhead Rate for Dept A [ _________ % of direct labour cost] Manufacturing Overhead Rate for Dept B [$____________per machine hour] Department A: $225,000/$180,000 = 125% of direct labour cost Department B: $180,000/40,000 = $4.50 per machine hour 3. If the actual manufacturing overhead cost incurred by both departments added together was $100,000 in total, was the manufacturing overhead over or under applied and by how much? 1|P ag e ACCT 102 Management Accounting Practice Questions – Job‐order Costing Answer: [$___________________] Under-applied/Over applied (Circle your answer) Job#8: ($11,000 x 125%) + ($4.50 x 3,000) = $27,250 Job#9: ($13,000 x 125%) + ($4.50 x 4,000) = $34,250 Job#10: ($8,000 x 125%) + ($4.50 x 5,000) = $32,500 Total applied overhead = $94,000 Under-applied = $100,000 - $94,000 = $6,000 4. What was the work in process in ($) as at the end of the month? Assume that over and under applied overheads are all written off to cost of goods sold. Answer: Work in Process [$___________________] Job#9: $5,000 +$4,000 + $9,000 + $11,000 + $13,000 + $16,000 + $34,250 = $92,250 5. The client for Job #10 required an urgent delivery of 10 units before the end of October. None of the products for Job #8 was delivered before the end of October. What was the total finished goods inventory in ($) as at the end of the month? Answer: Finished Goods [$__________________] Job#10: $9,000 +$8,000 + $9,000 + $12,000 + $32,500 = $70,500 40/50 or 80% not delivered, FG of Job#10 = $70,500 * 80% = $56,400 Job#8: $10,000 + $13,000 + $11,000 + $14,000 + $27,250 = $75,250 Finished Goods = $56,400 + $75,250 = $131,650. 2|P ag e ACCT 102 Management Accounting Practice Questions – Job‐order Costing Use the following information to answer Q6 to Q9. Manchester Co. uses a job-order costing system. Manufacturing overhead is applied to the jobs using normal costing on the basis of direct labour costs ($). Actual total manufacturing overhead incurred during the year was $119,000. The following was recorded in the Work in Process account for the year: Balance, Jan 1 Direct materials Direct labour Manufacturing overhead Work in Process of all the jobs $ 50,000 Completed projects 230,000 during the year 75,000 $390,000 120,000 6. Compute the predetermined overhead rate that was in use during the year. Answer: [__________________] Applied OH $30,000POR x DL$ $120,000 = POR x $75,000 POR = $1.60/DL$ 7. At the end of the year, only one job, Project M, was still in process. Project M has been charged with $10,000 in direct labour costs. Complete the following Job Cost sheet for Project M: Job Cost sheet for Project M Direct materials ? Direct labour ? Manufacturing overhead ? Balance as at 31 Dec ? WIP, 31 Dec = balance of Project M (Sum of Debit entries – sum of credit entries) = 50,000 + 230,000 + 75,000 + 120,000 – 390,000 = $85,000 Direct materials Direct labour Manufacturing overhead = Balance as at 31 Dec $59,000 (balancing figure) $10,000 (given) $16,000 (1.6 x $10,000) $85,000 (from above) 3|P ag e ACCT 102 Management Accounting Practice Questions – Job‐order Costing 8. Value of finished goods at the beginning of the year was $100,000 and at the end of the year was $5,000. If Manchester Co. closes underapplied or overapplied overhead cost to the cost of goods sold, calculate the adjusted cost of goods sold. Answer: [__________________] Overapplied overhead = Actual OH – Applied OH = $119,000 - $120,000 = $1,000 COGS before adjustment = BGF + COGM – EFG = $100,000 + $390,000 - $5,000 = $485,000 Less Overapplied OH $1,000 Adjusted COGS = $484,000 9. Give one reason to explain why you agree or disagree with Manchester Co.’s policy to close the underapplied or overapplied overhead costs to cost of goods sold. Answer: Agree. The overapplied overhead is insignificant and the impact of the write-off to COGS is immaterial. or Disagree. It is more accurate to split the amount of overapplied into COGS, WIP and FG. 4|P ag e Job-order Costing – Challenging Questions INFORMATION FOR QUESTIONS 1 THROUGH 3 The Leininger Company uses a normal job order costing system. The operating data for October 2009 are summarized below in which wage rate was $25 per hour and factory overhead was applied at the rate of $15 per direct labor hour. Beginning Inventories: Materials (both direct and indirect) Work in Process (Job #101) Finished Goods (Job #100) $27,000 18,000 14,000 Materials Purchased $30,000 Materials Requisitioned for Production: Direct Materials: Job #101 Job #102 Job #103 Indirect Materials Factory Labor Costs: Direct Labor: $59,000 Job #101 Job #102 Job #103 $ 7,000 9,000 10,000 $ 8,000 12,000 4,000 Indirect Labor Other Operating Costs Incurred: Other manufacturing overhead Selling and Administrative Expenses $ 1,400 13,000 $26,000 $12,000 $24,000 $ 9,000 $14,400 Jobs #101 and #102 were completed during October. Jobs #100 and #102 were sold. Question 1. The Ending WIP amounts to: Answer: [__$ 16,400______] Question 2. The product cost of Job #101 amounts to: Answer: [__$ 37,800______] Question 3. After closing over- or under-applied MOH against the Cost of Goods Sold (COGS), the adjusted COGS during October 2009 is: Answer: [__$ 50,200_____] 1 Job-order Costing – Challenging Questions Question 4 DEF Mfg Ltd allocates manufacturing overheads using a simple POR system with direct labour hours as the driver. The company has budgeted total annual manufacturing overheads of $1,080,000 for 2010. Average monthly utilization of direct labour is projected to be 2,000 hours at an average cost of $20 per hour. The following table contains relevant cost data of DEF Mfg Ltd in relation to its operations in the month of March 2010. Account Bal as at: 1st March Materials Added in March Dir Labour used in March Job # 201 $21,000 $6,000 $4,000 Job # 202 $17,000 $9,000 $8,000 Job # 203 Job # 204 $15,000 $14,000 $11,000 $12,000 All jobs except Job # 203 were completed by 31st March. Job # 201 and #204 were also delivered to their respectively “buyer” before the end of March. Actual manufacturing overheads for March amounted to $89,600. The company always writes off all over- or under- applied OH directly to Cost of Goods Sold. Compute the following for the month of March: (i) (ii) (iii) Ending WIP Ending Finished Goods Cost of Goods Sold (after adjusting for over or under applied OH) ANSWER (i) Ending WIP $ 60,500 (ii) Ending Finished Goods $ 52,000 (iii) Cost of Goods Sold $ 94,100 2 Job-order Costing – Challenging Questions Question 5 Monotone MA Company uses a job cost system for its jobs. In addition to the two direct cost categories (direct materials and direct labour), the company applies manufacturing overhead costs on the basis of machine hours (MH) worked. For the month of September, 2010, the following information is extracted from its accounting records: a. Beginning Inventory @ 01.09.2010 Direct materials: Finished goods: Job #A110 Work-in-process (WIP) – Job # A111: – Job # B112: $ 50,000 $ 80,000 $180,000 $125,000 b. Total direct materials issued to the various jobs during September are as follows: $ 50,000 Job# A111: Job# B112: $ 30,000 Job# B114: $ 80,000 TOTAL $160,000 c. Total direct labour costs for the month amounted to $54,000, all production workers are paid the same rate, the direct labour hours (DLH) worked for each job during the month are as follows: Job# A111: 400 DLH Job# B112: 600 DLH Job# B114: 800 DLH TOTAL 1,800 DLH d. Manufacturing overhead is allocated using a predetermined overhead rate (POHR). The estimated overhead for September was $20,000. e. The actual machine hours utilized in September matched with the budgeted machine hours. Job# A111: 400 MH Job# B112: 600 MH Job# B114: 1,000 MH TOTAL 2,000 MH f. Ending inventory @ 30.09.2010 Direct materials: $60,000 Only Job# B114 remained unfinished on 30.09.2011. All completed jobs have been delivered to customers in September. g. Total “Actual Manufacturing Overhead” amounted to $19,500 as shown below: Job# A111: $ 3,800 Job# B112: $ 5,500 Job# B114: $10,200 $19,500 What is the total cost to-date for Job# B114, if overhead application adjustment is written off directly to Cost of Goods Sold? Answer: [__$114,000______] 3 Job-order Costing – Challenging Questions Question 1. The Ending WIP amounts to: Answer: [__$ 16,400______] Workings: Job 103: Applied Overhead: Direct Labour Hours = 4,000/25 = 160 hrs Applied overhead = 160 hrs x $15 per hour = $2,400 Direct Material Direct Labour Overhead applied 10,000 4,000 2,400 16,400 Question 2. The product cost of Job #101 amounts to: Answer: [__$ 37,800______] Workings: Job 101: Applied Overhead: Direct Labour Hours = 8,000/25 = 320 hrs Applied overhead = 320 hrs x $15 per hour = $4,800 BWIP Direct Material Direct Labour Overhead applied 18,000 7,000 8,000 4,800 37,800 Question 3. After closing over- or under-applied MOH against the Cost of Goods Sold (COGS), the adjusted COGS during October 2009 is: Answer: [__$ 50,200_____] Workings: COGS Job 100 Job 102 $ Direct Material Direct Labour Overhead applied $ 14,000 9,000 12,000 7,200 W1 28,200 Under-applied overhead adj Adjusted COGS 8,000 50,200 W2 4 Job-order Costing – Challenging Questions Workings W1: Job 102 Applied Overhead: Direct Labour Hours = 12,000/25 = 480 hrs Applied overhead = 480 hrs x $15 per hour = $7,200 W2: Overhead adjustment: Actual Manufacturing Overhead Incurred: Indirect Materials Indirect Labour Other Manufacturing O/H $ 12,000 9,000 1,400 22,400 Applied Overhead: Job 101 Job 102 Job 103 Or Direct Labour Wage rate per hour Total labour hour Overhead absorption rate Applied Overhead $ 4,800 7,200 2,400 14,400 $24,000 ÷ $25 960 hrs x $15 per hr $14,400 Underapplied overhead =$ 22,400 – 14,400 = $ 8,000 OR FOH Incurred = 22,400 FOH Applied = 14,400 Adjusted COGS = 14,000+28,200+8,000 = 50,200 5 Job-order Costing – Challenging Questions Question 4 ANSWER (i) Ending WIP $ 60,500 (ii) Ending Finished Goods $ 52,000 (iii) Cost of Goods Sold $ 94,100 Workings: Predetermined OH Rate = $1,080,000 / (2,000 hrs per mth x 12 mths) = $45 per dlh a b c d e Account Bal as at: 1 March Mat Added in March Lab Added in March Applied OH ( = f x $45) Total Costs ( = a + b + c + d) Status at end of March f Direct Labour hours ( = c / $20) Job # 201 $21,000 $6,000 $4,000 $9,000 $40,000 CoGS Job # 202 $17,000 $9,000 $8,000 $18,000 $52,000 FG 200 400 Job # 203 Job # 204 $15,000 $14,000 $31,500 $60,500 WIP $11,000 $12,000 $27,000 $50,000 CoGS 700 Actual OH = $89,000 (given) Applied OH = $9,000 + $18,000 + $31,500 + $27,000 Actual OH (given) Under-Applied OH = = = $85,500 $89,600 $ 4,100 Total CoGS (before adjustment) = $40,000 + $50,000 Plus Under-Applied OH CoGS (after adjustment) = = = $90,000 $ 4,100 $94,100 600 Question 5 Answer: [__$114,000______] Workings: DM DL MOH TOTAL 80,000 800*(54,000/1,800) = 24,000 1,000*(20,000/2,000) = 10,000 114,000 6