TENDER No. SCOPE OF WORK SH-FCP-EPC-PREQUALCAFC-HUILE 2011-01 SHEET 1 OF 180 CENTRAL AREA FIELD COMPLEX PROJECT ITT FOR EPC PART D – SCOPE OF WORK Rev. Date Page Description Prep‟d Chk‟d App‟d 0 09/03/12 180 Issued for ITT PMT A.N.K A. E Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 CAFC PROJECT INVITATION TO TENDER ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING PART D – SCOPE OF WORK Page 2 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 CONTENTS FOREWORD 9 EXPLANATION OF TERMS 10 ACRONIMS 12 INTRODUCTION 15 1. PROJECT OVERVIEW 16 1.1 CAFC DEVELOPMENT SUMMARY 16 1.2 CONCEPT 17 1.3 COMMON FACILITIES INSTALLED AT MLE 18 1.4 DEVELOPMENT LOCATION 19 2. GENERAL CONTRACTING AUTHORITY REQUIREMENTS 2.1 SUPPORT TO CONTRACTING AUTHORITY 3. GENERAL WORK DESCRIPTION 22 27 33 3.1 DESIGN CONCEPT AND DATA REVIEW 35 3.2 HSE 36 3.3 DESIGN INTERFACES 36 3.4 FUTURE FACILITIES 38 3.5 ALGERIAN REGULATORY BODIES 38 4. PROJECT MANAGEMENT 39 4.1 OVERVIEW 39 4.2 PROJECT EXECUTION PLAN 40 4.3 ORGANISATION 41 4.4 PROJECT PROCEDURES 42 4.5 QUALITY ASSURANCE 42 4.6 SOFTWARE 43 4.7 DOCUMENTATION 44 4.7.1 48 Data and Document Management TOOL MIAP: 50 TOOL SPCPUMA: 50 TOOL EDAM: 50 Page 3 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 4.7.2 CODING METHODOLOGY FOR CORRESPONDENCE 4.8 52 MANAGEMENT OF CHANGE 53 4.8.1 Management of Change Policy 54 4.8.2 Documents concerned by MOC 54 4.9 DAMAGE AVOIDANCE PROCEDURES 55 4.10 HSE PLAN AND MANAGEMENT 55 4.11 BRIDGING SYSTEM 56 4.12 PLANNING, SCHEDULING AND PROGRESS REPORTING 56 4.13 INTERFACE MEETINGS 58 5. SCOPE OF WORK AND DETAILED DESIGN/ENGINEERING 60 5.1 GENERAL 60 5.2 FACILITIES 64 5.2.1 Process Engineering 64 5.2.2 Mechanical/Equipment 70 5.2.3 Piping and Layouts 74 5.2.4 Pipelines 75 5.2.5 Operations and Maintenance 76 5.2.6 Instrument and Controls Systems 78 5.2.7 IT and Telecommunications Systems Design 82 5.2.8 Electrical and Power Systems Engineering 85 5.2.9 Corrosion Protection 87 5.2.10 Civil 88 5.2.11 HSE 94 5.2.12 Lifecycle Cost Assessment 97 6. HSE MINIMUM REQUIREMENTS 6.1 NATIONAL LEGISLATION, REGULATION, CONTRACTING AUTHORITY AND INTERNATIONAL HSE CODES AND STANDARDS 99 99 6.2 DESIGN HSE PHILOSOPHY 100 6.3 HAZARD MANAGEMENT AND RISK MANAGEMENT 101 6.3.1 GENERAL PRINCIPLES 101 6.3.2 HAZARD IDENTIFICATION STUDY (HAZID) 102 6.3.3 HAZOP STUDIES 102 6.3.3.1 FEED HAZOP 102 6.3.3.2 EPC HAZOP 102 6.3.4 SIL ASSESSMENT AND VERIFICATION 103 6.3.5 FIRE AND EXPLOSION RISK ANALYSIS (FERA) 103 6.3.6 QUANTITATIVE RISK ANALYSIS (QRA) 104 6.3.7 DESIGN CASE SCENARIO 104 6.3.8 DESIGN AND SAFETY REVIEWS 104 6.3.9 ENVIRONMENTAL, SOCIAL AND HEALTH IMPACT ASSESSMENT (ESHIA) 105 Page 4 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 NOTE: ESHIA WILL BE PROVIDED TO THE CONTRACTOR AND CONTRACTOR SHALL BE RESPONSIBLE TO CONDUCT ALL THE ACTIVITIES PART OF THE EPC ACCORDING TO THE FINDING AND RELEVANT ACTION PLAN. 105 6.3.10 HUMAN FACTORS STUDY 105 6.3.11 SAFETY CRITICAL ELEMENTS (SCE‟S) IDENTIFICATION PROCESS AND MINIMUM REQUIREMENTS 106 6.3.12 HSE ACTION TRACKING 106 6.4 INHERENT SAFETY 106 6.5 LAYOUT PHILOSOPHY 107 6.5.1 LAYOUT CRITERIA TO MINIMIZE RISKS 107 6.5.2 MINIMUM SAFETY DISTANCES 107 6.5.3 FIRE ZONE 108 6.5.4 ACCESS AND EVACUATION 108 6.5.4.1 ACCESS REQUIREMENTS 108 6.5.4.2 ROADS DESIGN 108 6.5.4.3 EVACUATION 109 6.6 PROCESS SAFETY CRITERIA 109 6.6.1 GENERAL 109 6.6.2 EQUIPMENT SAFETY REQUIREMENTS 110 6.6.3 EMERGENCY SHUTDOWN SYSTEMS 110 6.6.4 BLOW DOWN AND FLARE SYSTEMS 111 6.6.5 VENTING AND FLARING SYSTEMS 112 6.7 112 DRAIN SYSTEMS 6.7.1 CLOSED DRAIN SYSTEM 112 6.7.2 OPEN DRAIN SYSTEM 113 6.8 ELECTRICAL SYSTEM DESIGN 113 6.8.1 HAZARDOUS AREA CLASSIFICATION 113 6.8.1.1 EQUIPMENT SELECTION 114 6.8.1.2 VENTILATION AND PRESSURIZATION 114 6.8.2 EMERGENCY POWER SYSTEM 114 6.9 115 FIRE & GAS DETECTION SYSTEM 6.9.1 FIRE DETECTION 115 6.9.2 FLAMMABLE GAS DETECTION 116 6.9.3 MANUAL ALARM CALL POINT 116 6.10 117 ALARM SYSTEMS 6.10.1 ALARMS IN CONTROL ROOM 117 6.10.2 PA/GA AND FIELD ALARM SYSTEMS 117 6.10.3 ALARM VOTING FOR AUTOMATIC ACTIVATIONS 117 6.11 117 FIRE PROTECTION SYSTEMS 6.11.1 ACTIVE FIRE PROTECTION REQUIREMENTS 118 6.11.1.1 118 FIREWATER PROTECTION SYSTEM 6.11.2 PASSIVE FIRE PROTECTION REQUIREMENTS 118 6.12 119 BUILDINGS SAFETY CRITERIA Page 5 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 6.12.1 BUILDINGS LOCATION 119 6.12.2 BUILDING SAFETY DESIGN REQUIREMENTS 119 6.12.3 HVAC REQUIREMENTS 119 6.13 STRUCTURAL DESIGN 120 6.14 PLANT CONSTRUCTION 120 6.15 PERSONNEL SAFETY AND OCCUPATIONAL HEALTH 121 6.15.1 PERSONNEL PROTECTION 121 6.15.2 SAFETY SHOWERS AND EYEBATHS 121 6.15.3 SAFETY SIGNS 122 6.15.3.1 122 MARKING AND ILLUMINATION OF ESCAPE ROUTES 6.15.4 MEDICAL FACILITIES 123 6.15.5 MACHINERY GUARDS 123 6.15.6 MANUAL HANDLING 123 6.15.7 ELECTRICAL SAFETY KIT 123 6.15.8 HOT AND COLD SURFACES/FLUIDS 123 6.15.9 HAZARDOUS MATERIALS STORAGE AND HANDLING 123 6.15.10 MATERIAL SAFETY DATASHEETS (MSDS) 123 6.15.11 RADIOACTIVE MATERIALS 124 6.15.12 TENORM 124 6.15.13 PROHIBITED SUBSTANCES 124 ENVIRONMENTAL STANDARDS 125 6.16 6.16.1 PROJECT ENVIRONMENT REQUIREMENTS 125 6.16.2 NOISE CONTROL 125 7. MATERIALS PROCUREMENT AND MANAGEMENT 127 7.1 GENERAL 127 7.2 SCOPE 127 7.3 PROCUREMENT ORGANISATION 127 7.4 PROCUREMENT METHODS AND PROCEDURES 128 7.5 APPROVED SUPPLIERS LIST 128 7.6 BID PACKAGES 130 7.7 SUPPLIER QUALITY MANAGEMENT 130 7.8 SUPPLIER INTERFACE MEETINGS 130 7.9 MATERIALS STATUS REPORTING 131 7.10 INSPECTION AND EXPEDITING 131 7.11 PROTECTION, PACKING, MARKING AND SHIPPING REQUIREMENTS 132 7.12 SUPPLIER DOCUMENTATION 132 7.13 CUSTOMS CLEARANCE 132 7.14 SPARES 133 7.14.1 General 133 7.14.2 Insurance Spares 133 7.14.3 Operating Spares 133 Page 6 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 7.14.4 Commissioning and Start-Up Spares 134 7.14.5 Cataloguing Spares 134 7.15 SPECIAL TOOLS 134 7.16 LOGISTICS 134 8. TECHNICAL INTEGRITY MANAGEMENT 135 8.1 MANAGEMENT SYSTEM 135 8.2 INTEGRITY PLAN 136 8.3 SYSTEM REQUIREMENTS 136 8.3.1 General 136 8.3.2 Specific Points to be addressed in the Technical Integrity Plan 137 8.3.3 Specific points to be addressed by the Contractor 138 8.3.4 General Notes to System Requirements 139 8.3.5 Risk Assessment and Management Programmes 140 8.3.6 Audits 141 8.3.7 Quality Control 142 9. CONSTRUCTION 146 9.1 GENERAL 146 9.2 CONSTRUCTION ENGINEERING AND TEMPORARY WORKS 147 9.3 SITE PREPARATION 148 9.4 SITE CONSTRUCTION FACILITIES 148 9.5 STORAGE OF EQUIPMENT AT SITE 150 9.5.1 General 150 9.5.2 Mechanical 150 9.5.3 Instrument/Electrical/Telecommunications 151 9.6 9.7 SITE CONSTRUCTION 151 9.6.1 General 151 9.6.2 Civil Works 152 9.6.3 Mechanical Equipment 154 9.6.4 Piping Systems 154 9.6.5 Gathering Systems 155 9.6.6 Structural 156 9.6.7 Instruments, Electrical and Telecommunications 156 9.6.8 HVAC Systems 158 9.6.9 Safety Equipment 158 9.6.10 Corrosion Protection and Painting 159 9.6.11 Welding Procedures/Welder Qualification 160 PRECOMMISSIONING ACTIVITIES UP TO MECHANICAL COMPLETION 10. COMMISSIONING AND START UP 10.1 160 163 COMMISSIONING OF UTILITIES AND PROCESS SYSTEMS WITH INERT FLUIDS163 Page 7 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 10.2 START UP 165 10.3 RESPONSIBILITIES 167 10.4 HEALTH, SAFETY AND ENVIRONMENT CONSIDERATIONS 167 10.5 PLANNING 169 10.6 PRE-COMMISSIONING, COMMISSIONING AND START-UP ACTIVITIES 170 10.7 GENERAL PROCEDURES 170 10.8 HANDOVER AND ACCEPTANCE PROCEDURES 171 10.9 PERFORMANCE TESTING 174 10.10 FAILURE OF FACILITIES TO PERFORM 174 10.11 TRAINING 174 10.12 VENDOR SUPPORT 175 10.13 DOCUMENTATION 176 10.14 ENGINEERING SUPPORT 176 11. SPECIAL NOTES REGARDING CAFC OIL PROJECT Page 8 / 180 Part D - Scope of Work 177 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 FOREWORD The written descriptions set forth in this Part D – “Scope of Work” of the ITT shall form part of Annex II – “Extent and Limit of Supplies and Services” of the Contract and in addition supplement the annexes of the Contract including the FEED. They are not intended to describe in every detail all Work to be performed or for all things which are to be included and reflected the Contract Price. In case of any conflict identified by Contractor between this description of the Work and the drawings, specifications and data contained in Annex I – “Technical” of the Contract including the FEED Package or between the description of the Work and the codes and standards, it shall be the Contractors responsibility to present the differences to the Contracting Authority for resolution. The more stringent requirement shall prevail unless otherwise approved by the Contracting Authority. Page 9 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 EXPLANATION OF TERMS Live Commissioning Means the dynamic running of systems to further check out the functionality and integrity of complete systems, and continues on from Pre-Commissioning. It is the last series of checks and tests before running the process systems on hydrocarbons. It includes the operation of the utilities systems where applicable to progress the commissioning of process systems, all as more fully described in Annex 2 (Scope of Work) Contracting Authority Shall mean SONATRACH and First Calgary Petroleums Ltd as defined in the Form of Agreement, their successors and assigns. Contractor Shall mean the party or parties specified as Contractor in the Form of Agreement appointed to perform the Work including its successors and assigns. Mechanical Completion Shall mean that a system or sub system is installed and erected and all aspects of checking, inspection and testing, prior to Pre Commissioning. Plant Operating Efficiency A measure of production performance, calculated according to the principles to be defined by Contracting Authority. Refer to document Tests and Performances Criteria Pre-Commissioning Means the series of inspections and tests, generally static, to check the functionality of components and systems. PreCommissioning commences after mechanical completion. It includes energisation of systems to allow static tests to be carried out, all as more fully described in Annex II – “Extent and Limit of Supplies and Services” of the Contract Operation The quality or state of being functional or operational Start-Up Generally follows issue of Ready for Start Up Certificate and commencement of the introduction of hydrocarbons into the Permanent Works to continue to commission the process systems. Work Shall mean all work that the Contractor is required to carry out in accordance with the provisions of the Contract including all related services, resources and equipment to be provided in accordance with the Contract, all as fully defined Annex II – “Extent and Limit of Supplies and Services” of the Contract Page 10 / 180 Part D - Scope of Work Works Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Shall mean the Permanent Works and Temporary Works : Permanent Works: Shall mean the property of Contracting Authority arising from the Works. Temporary Works : Shall mean all temporary infrastructure, structures or items that may be necessary to enable the CONTRACTOR to access, fabricate, construct or install the Permanent Works, whether on or off the worksite, but which are not intended for incorporation into the Permanent Works . Page 11 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 ACRONIMS AFC Approved For Construction AFD Approved For Design ARH Autorité de Régulation Hydrocarbure BdV Base de Vie (Living Quarters) CAFC Central Area Field Complex CCR Central Control Room CER Central Equipment Room CCTV Closed Circuit Television CDR Contractor‟s Design Report CMMS Computerised Maintenance Management System CP Cathodic Protection CPF Central Processing Facility CTC Organisme National de Contrôle Technique de la Construction CV Curriculum Vitae DC Direct Current DPEM Direction du Patrimoine Energétique et Minier DLE Dry Low Emissions EPC Engineering, Procurement and Construction ESHIA Environment Safety Health Impact Assessment F&G Fire & Gas FAT Factory Acceptance Test FEED Front End Engineering Design prepared by CONTRACTOR FEED Package Results of FEED package prepared by Competitive FEED HAZID Hazard Identification HAZOP Hazard and Operability HF High Frequency HSE Health, Safety, Environment HSEMS HSE Management System HV High Voltage HVAC Heat, Ventilation and Air Conditioning I/O Input/Output IBO Industrial Base Operations ICSS Integrated Control and Safety System ISO International Standards Organisation IT Information Technology ITP Inspection and Test Plans ITT Invitation To Tender Page 12 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 LAN Local Area Network LER Local Equipment Room LPG Liquefied Petroleum Gas LV Low Voltage MAOP Maximum Allowable Operating Pressure MDR Manufacturer Data Records MLE Menzel Ledjmet East MLN Menzel Ledjmet North NCR Non-conformance Report NDE Non-Destructive Examination ONML Office National de Métrologie Légale P&ID Piping & Instrument Diagram PABX Private Automatic Branch Exchange PCS Process Control System PFD Process Flow Diagrams PHSER Project Health, Safety and Environmental Review PIM Pre-Inspection Meeting PMT Contracting Authority Project Management Team PSC Production Sharing Contract (between Sonatrach, First Calgary Petroleums) PSV Pressure Safety Valve PTT Postes Télécommunications & Téléphones QA Quality Assurance QC Quality Control RAM Reliability, Availability and Maintainability RCM Reliability Centered Maintenance ROW Right of Way RP Recommended Practices RTU Remote Terminal Unit SDO Service Delivery Organisation SIL Safety Integrated Level SIMOPS Simultaneous Operations with Drilling, Construction etc. SP Special Piping SPIR Spare Parts List and Interchangeability Record STU Sewage Treatment Unit UCP Unit Control Panel UFD Utility Flow Diagrams UHF Ultra High Frequency UPS Uninterruptible Power Supply Page 13 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 VHF Very High Frequency VPN Virtual Private Network Page 14 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 INTRODUCTION SONATRACH and First Calgary petroleum Ltd under Production Sharing Contract, intend to develop Central Area Field Block 405b in the Berkine Bassin- Algeria. This is a desert location (SAHARA), approximately 300km east-south-east from the town of Hassi Messaoud The development consists of a field gathering system, central processing facilities and tie-Ins between MLE and CAFC plants. Page 15 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 1. PROJECT OVERVIEW A simplified schematic overview of the project is given in Figs 1.1 below. Fig 1.1 shows the overall requirement of the CAFC project. Fig 1.2 shows the location of the CAFC project within Algeria whilst Fig 1.3 gives more detail on the field development within Block 405b. CAFC oil and gas processing facility will be built adjacent to the MLE CPF. Export lines are sized to cater for both MLE and the Central Area Field Complex (CAFC). F6-2 Lean and Rich Gas F6-2 Gas MLE F6 Associated Gas F6-1 Oil Condensate Phase 2: TAGI Gas CAFC F6-2 Oil Plant Gas Phase 1: TAGI Gas Injection TAGI Oil CAFC Oil Treatment MLE/CAFC storage tanks Fig 1.1 CAFC Project Simplified Overview 1.1 CAFC DEVELOPMENT SUMMARY The CAFC development concept consists of a field gathering system and 41 oil wells to be connected to CAFC plant, central processing facility and necessary support infrastructure. - The CAFC Oil wells (TAGI, F6-1 and F6-2 SWP) will be connected to the CAFC oil slug catchers through gathering systems dedicated to TAGI reservoir and to F6 Oil. The total number of wells is 51 divided in 41 oil producer (17 TAGI, 9 F6-2 and 15 F61), 4 water injectors (TAGI), 3 gas injectors (TAGI) and 3 water producers. The associated gas from F6-1 and F6-2 should be sent to MLE plant for final treatment, while TAGI associated gas has to be re-injected till the gas cap blow down, expected in 10 years. Page 16 / 180 Part D - Scope of Work - Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The CPF shall process part of the associated gas relevant to the gas injection and the Oil products. CAFC CPF will be provided with its own flares and off-spec oil tank. The gas injection system is to re-inject gas into TAGI reservoir. The water injection system is to re-inject the produced and Barremian water into TAGI reservoir. Infrastructure includes: o Construction Camp o Black top & Gypsum roads and access roads 1.2 CONCEPT The general concept for development scheme consists on developing CAFC project comprising following facilities: Wells production / infields manifolds/ production and distribution gathering system Central Processing Oil Facility, associated utilities where applicable and common installations Gas injection & Water Injection Infrastructures: road network and construction camp The design and construction of CAFC project for common utilities installations will be optimised in synergies with MLE plant. A site topographical and geotechnical surveys should be carried out during the EPC activities in order to acquire information regarding the physical characteristics of soil, assess the site situation and planning civil works to be carried out. Site preparation for CAFC facilities is executed by Contracting Authority and handed over to the selected Contractor. An Environmental, Social and Health Impact Assessment (ESHIA) study has been carried by a third party contractor and submitted to local authorities. EPC Contractor shall comply with the requirements of the MLE & CAFC ESHIA studies that will be provided. The CAFC project is part of a two phase development scheme: The initial phase shall consist of installing the CAFC wellsites and Oil gathering system, and developing the CAFC CPF along with its infrastructure. nd A inlet gas booster compression is foreseen for 2 phase, but not included in the present SoW It is expected that the MLE booster compressor required for MLE CPF after approximately year 5 will also be used for CAFC The second phase which is excluded from the Work is GAS Blowdown phase. Page 17 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 1.3 COMMON FACILITIES INSTALLED AT MLE The MLE NGL plant allowed space for future processing of the Central Area Facilities Complex (CAFC) fields. a. Common Installation for Combined Facilities Process o Oil Storage for combined MLE and CAFC production is foreseen in MLE Plant. o o Booster and Export Oil Pumps MLE Project designed pumps for CAFC and MLE combined but installed pumps for MLE Production ONLY. Remaining pumps to be installed within CAFC project. CAFC RAM study to confirm CAFC plant availability specification is met with the required pumps configuration. Oil Fiscal Metering - MLE Installed a larger fiscal meters for all products with required turndown. No furthers fiscal meters are required for CAFC, only the new technical meter as described in the FEED SoW. Condensate Production coming from CAFC Gas Treatment could be connected to MLE Liquid Processing Off gas The compressed off-gas for F6 gas only coming from the oil treatment section will be dehydrated and re-injected along TAGI gas released from the slug catcher. A connection to MLE plant is foreseen to be used in case of an emergency. Utilities o MLE Plant designed and installed sufficient size of the following utilities for CAFC rates: - Fuel gas - Diesel fuel - Utility Water - potable water - de-mineralized water - F&G - instrument air - plant air - inert gas - firewater - main power distribution Instrumentation & Control/Tele The control room to be used will be in the same building of MLE project. MLE and CAFC projects shall be independent in terms of systems (DCS, SCADA, ESD/F&G, etc.) to be used. However, it shall be necessary to exchange some Page 18 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 information/data. This means that the CAFC equipment (DCS, SCADA, ESD/F&G, etc.) shall be housed in the electrical building inside the CAFC area. In order to allow communication among the different parts of the plant, PAGA, PABX TETRA and security radio telecommunication systems have been foreseen as integration/extension of MLE systems. Also, Fibre Optical Cables (FOC) shall be foreseen to exchange data between CAFC plant and remote sites, and between CAFC and MLE plants, as per FEED documentation and MOM interface meeting between MLE & CAFC PMT during CAFC FEED. 1.4 DEVELOPMENT LOCATION The CAFC field lies within the Ledjmet Block 405b in the Berkine Basin of Algeria approximately 1200 km by road from the Algerian ports. It is also approximately 220 km south-east of Hassi Messaoud which is an oil field activities center and regional base for Sonatrach, FCP, contractors and suppliers. Location maps are shown in Fig 1.2 and 1.3 below. Page 19 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Fig 1.2 Location of CAFC The next drawing shows the red dashed area in more detail. Fig 1.3 Location of CAFC Page 20 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 In the diagrams above and below, the Block 405b perimeter is highlighted in blue and the difference in the area is due to the relinquishment of some of the block area back to Sonatrach. Fig 1.4 Location of CAFC wells Page 21 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 2. GENERAL CONTRACTING AUTHORITY REQUIREMENTS As part of its obligations under the Contract, the Contractor shall provide to the Contracting Authority the Permanent Works necessary to develop and exploit the CAFC field including, but not limited to: from 41 oil production wells, 4 water injection wells, 3 gas injection wells, 3 water producing wells,, a Central Processing Facility (the “CPF”), and all necessary infrastructure, as detailed in the document entitled “Process Basis of Design –” , and in the FEED Technical Data. The primary components of the Permanent Works include, but are not limited to, the following: the Permanent Works shall as a minimum be capable of achieving or exceeding all of the criteria stated in above in all environmental and seismic conditions (and all combinations thereof) up to and including the more onerous of the conditions as specified in the document entitled “Process Basis of Design” for all conditions and all modes of operation (and all combinations thereof) for which the Permanent Works and/or any part thereof are or may be intended to be used; The Permanent Works shall be capable of operating on the most onerous of soil conditions at the Location of the Permanent Works, as independently determined and resulting from the Geotechnical Survey to be performed by Contractor. Moreover Contractor shall consider all conditions and all modes of operation (and all combinations thereof) for which the Permanent Works and/or any part thereof are or may be intended to be used; the Permanent Works shall have a design operational life of a minimum of twenty-five (25) years, for all conditions and all modes of operation (and all combinations thereof) for which the Permanent Works and/or any part thereof are or may be intended to be used (except where the document entitled “Process Basis of Design ” otherwise indicates); the Work shall at all times comply with the Contracting Authority HSE MS standards (Ref. Part C – Annex XI) and HSE Minimum Requirements (See section 6) and shall incorporate all facilities required for the Permanent Works to comply with such standards, for all conditions and all modes of operation (and all combinations thereof) in which the Permanent Works are or may be intended to be used; Page 22 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 the Permanent Works shall incorporate all facilities necessary to perform the functions stated in above, whilst complying in all respects with the Contracting Authority HSE MS standards (Ref. Part C – Annex XI) and HSE Minimum Requirements (See section 6) and with the product specifications, noise and emissions requirements as detailed in the document entitled “Process Basis of Design” for all conditions and all modes of operation (and all combinations thereof) in which the Permanent Works are or may be intended to be used; the Permanent Works shall be designed, engineered, procured, constructed and commissioned such that they are capable of providing a minimum overall availability (defined as the average system production over the expected production without any fault and any preventive maintenance) of ninety seven per cent (97%) (including the Contracting Authority‟s assumed three years shutdown period), whilst complying in all respects with the Contracting Authority HSE MS standards (Ref. Part C – Annex XI) and HSE Minimum Requirements (See section 6) and with the requirements as detailed in the document entitled “Process Basis of Design” for all conditions and all modes of operation (and all combinations thereof) in which the Permanent Works are or may be intended to be used; The Permanent Works shall be designed in accordance with Best Industry Practice for ease of operation and maintenance, taking into account the fact that they are located in a very remote area, with difficult access and that they operate under harsh weather conditions. Accordingly, all equipment comprising the Permanent Works shall be robust, efficient, reliable in operation and capable of being serviced on site. As far as practically possible, equipment shall be standardised within the Permanent Works; the Permanent Works shall be demonstrated as having successfully completed all of the Process Performance Tests as detailed in the Annex VII – “Performance Guarantees” whilst complying in all respects with the Contracting Authority H HSE MS standards (Ref. Part C – Annex XI) and HSE Minimum Requirements (See section 6) and with the requirements as specified in the document entitled “Process Basis of Design”; the Permanent Works shall be capable of achieving the specified turndown level and operating with the minimum production feed flow rate, as specified in the document entitled “Process Basis of Design” whilst complying in all respects with the Contracting Authority HSE MS standards (Ref. Part C – Annex XI) and HSE Minimum Requirements (See section 6) and with requirements as detailed in the above referenced document; Page 23 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 the Permanent Works shall incorporate all means of access (including but not limited to means of access for personnel, Materials, Installations and such other materials, construction plant or other temporary works as may be required) and all facilities required to, safely and efficiently, construct, commission, operate, service, maintain and replace each part of the Permanent Works, in such manner as to fully comply with the Contracting Authority HSE MS standards (Ref. Part C – Annex XI) and HSE Minimum Requirements (See section 6); the Permanent Works shall permit easy access to all parts of the Permanent Works that are required to be accessed for the safe and efficient operation thereof, for all conditions and all modes of operation (and all combinations thereof) in which the Permanent Works are or may be intended to be used; and the Permanent Works shall incorporate all support infrastructure required for the Project, including, but not limited to, all buildings and roads as specified in the document entitled “Process Basis of Design”. The Permanent Works must comply with the following: 1. 2. 3. 4. 5. 6. Algerian statutory requirements; The Contract; Contracting Authority documents; Process Basis of Design; All other Contracting Authority Technical Data; FEED ITT Package documents (including reference list of applicable codes and standards); International codes, standards, best practice and guidelines. 7. In the case of an inconsistency between the requirements of any of the aforementioned, then priority shall be given in descending order. The more onerous requirements shall apply, unless otherwise expressly determined by the Contracting Authority in writing. Contracting Authority shall have the right at all times to modify its requirements in the interests of improving the Safety, Health, Environment and welfare of personnel in the workplace. To the extent that there is a conflict between the project HSE requirements and this document, the more stringent requirement as determined by COMPANY shall prevail. In the event that the Contractor wishes to seek from the Contracting Authority a concession or waiver of any of the technical requirements of the Contract, the Contractor shall, to the extent permitted by Article xx of the Contract, submit a Variation Order Request in accordance with Article xx of the Contract. (i) The Contracting Authority shall have no liability to the Contractor for any adverse impact on the Contract Price, Contract Schedule or Key Milestones for any Page 24 / 180 Part D - Scope of Work (ii) (iii) (iv) Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 request for a concession or waiver regardless of whether or not such request is granted by the Contracting Authority, other than by way of a Variation Order in accordance with Article xx of the Contract. For the avoidance of doubt, the granting of any concession or waiver shall not in any way relieve the Contractor of any of its obligations for Performance Testing or any other provisions under the Contract. The Approval of any Contractor‟s Technical Data and any project document which contains any provision which is not in accordance with the Contract shall not be considered an Approved concession or waiver unless Contractor has complied fully with the above requirements for a Variation Order Request. EPC contractor is wholly responsible at EPC stage for all the design related variation arising during detailed engineering, procurement and construction. The scope of work described herein provides a general overview of the activities to be performed by the Contractor and is intended only to be sufficient for identification of each major element of the Work. The descriptions herein are not intended to provide either a comprehensive list of activities or detail of each such activity involved in the execution of the Work and must be read in conjunction with all other documents forming the Contract. The Contractor shall carry out all activities necessary to fulfil the Contractor‟s responsibility for the complete performance of the Work in accordance with the Performance Criteria, the Contracting Authority and the Competent Authorities, as appropriate. The Contractor shall Design, Engineer, procure, supervise, manage, supply, transport, construct and Commission the Permanent Works. Performance Testing (including the Process Performance Tests) shall be undertaken by the Contractor to demonstrate to the Contracting Authority‟s satisfaction that the Permanent Works meets the Performance Criteria. The Contractor shall guarantee the Work and perform, complete, deliver and guarantee all other work or works which the Contractor is, or may be, required to perform, complete, deliver or guarantee under the Contract, all in conformity, in all respects, with the provisions of the Contract, including, but not limited to, the Contracting Authority Requirements and/or the requirements of the Contracting Authority‟s Representative, the requirements of all Competent Authorities and all other requirements of whatever nature and howsoever arising which the Contractor may have to comply with in respect of the Work and/or any part thereof. As the Work progresses, details of the Permanent Works may change, however the basic configuration of the Permanent Works shall remain unchanged. Similarly, all existing specifications, drawings, procedures, databases, manuals and other documents relating to the Permanent Works shall be revised by the Contractor (subject to Approval), as appropriate, and additional specifications, drawings, procedures, manuals and other documents as specified in the Contract and/or as necessary for the proper execution of the Work shall be prepared by the Contractor for Approval and/or for submission to the Competent Authorities. The process of Design development approval as required by the Competent Authorities is an integral part of the Work and shall not, in any circumstances whatsoever, be deemed to be, or recognised as, a Variation. In case of conflict between the provisions of the Contract and any of the requirements listed above, the more onerous requirements shall apply, unless otherwise expressly determined by the Contracting Authority in writing. Page 25 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 In summary, the major elements of the Work shall include, but are not limited to: (i) management and services; (ii) detail design and engineering; (iii) Correct any inconsistency, lack, incompleteness; mistake arising during EPC Phase from FEED documentation (iv) In the preliminary phase of the EPC, Contractor shall identify the external battery limits and shall propose solutions for the integration between CAFC and MLE facilities especially in term of HSE, operability and maintainability aspects (v) Support Contracting Authority in the interface management (vi) procurement, inspection, expediting, freight forwarding, customs clearance and delivery of all Materials to the relevant Locations; (vii) arranging all approvals from the Competent Authorities, in particular the ARH and CTC; (viii) maintaining Quality Assurance throughout the Work and demonstrating such to the Contracting Authority‟s satisfaction at all times; (ix) construction to Mechanical Completion status; (x) preparation of all pre-commissioning and Commissioning procedures; (xi) Commissioning; (xii) Execution of the Performance Testing, in cooperation with Contracting Authority (including the Process Performance Tests); (xiii) provision of on site engineering support to the Contracting Authority‟s operations organisation for the Guarantee Period; (xiv) provision of the guarantees in accordance with the Contract; (xv) provision of HSE services and co-ordination thereof for the Work; (xvi) define and develop the project HSE requirements for all CAFC project facilities with the aim to collate and document all the HSE design criteria and philosophies, applicable regulations, codes and standards that are to be adhered regarding detail design and engineering, procurement, construction and commissioning and start up of the CAFC project facilities (xvii) provision of status information regarding all relevant legislation at the commencement of the Contract and ongoing monitoring, and advice to the Contracting Authority, of any change in such legislation which affects, or may affect, the Work; (xviii) preparation of the process operations manual (in French and English languages); (xix) preparation of Final Status (“as-built”) documentation; Page 26 / 180 Part D - Scope of Work (xx) Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 preparation, loading and commissioning of a computerised maintenance management system (in the French and English languages); and (xxi) Compilation of all vendor operating and maintenance manuals and other documentation (in the French and English languages). (xxii) Undertake a programme of training for Contracting Authority operational personnel both on site and abroad in suppliers‟ works. The Contracting Authority shall be responsible for the planning, engineering, materials procurement and execution of: (i) the construction of all drilling pads for the hydrocarbon production wells, gas injection, water injection and water extraction wells; (ii) the construction of all temporary access roads to such drilling pads; and (iii) The sub-surface completion of, and installation of wellheads (including the supply and installation of the master safety valve, subsurface valve), for the hydrocarbon production wells, gas injection, water injection / aquifer water wells. The Contracting Authority undertakes to keep the Contractor informed of these activities in order to allow the Contractor to maintain and update its overall Contract Schedule planning. Contractor hereby agrees and warrants that it will utilise its best endeavours to ensure that Contracting Authority drilling and completion programme is not affected by the performance of this work. 2.1 SUPPORT TO CONTRACTING AUTHORITY Provide the following office requirements for Contracting Authority Personnel in Contractor‟s Engineering Design Office: Contracting Authority PMT shall be co-located in Contractor‟s office for the duration of the Contract. The team will be immediately mobilized after the signature of EPC award. Contractor shall provide office facilities, furniture, parking and other associated services (e.g. telephone, reproduction services, and stationery) for Contracting Authority personnel (30 people) in the Engineering Design office. The office space shall be equipped with smoke and fire detectors, burglar alarms connected to a central security system or the local police station, fire-fighting equipment and escape-ways. The office space shall satisfy Contracting Authority security requirements. Contracting Authority shall determine access to the offices. The offices shall all be equipped with necessary connections and power supply. Page 27 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The facilities are to include the following: 2 fully equipped and lockable Project Manager's office with conference table and 4X2 chairs and additional spider phones. Minimum 2 fully equipped lockable one-man Engineering Manager's offices. Fully equipped open office for 26people and with partition screenings for each work place. Option for extension for 4 more people. Project conference room for 20 people fully equipped with spider phone, PC, roofmounted overhead projector, board and flip-over. 1 secure document control room (approximate size 25 sq. m.) with lockable filing cabinets 1 copy room equipped with: o o o One heavy duty colour copy machine with scanner, latest model “Xerox” or equivalent, able to copy A3 size documents onto A3 size paper and reduces A3 to A4 and other reduction facilities, normal A4 copies, single and double sided copies, approximately sixty (60) copies per minute and sorting/stapling facilities. Laser telefax receiving and transmitting system located within the provided office space and operated independently from Contractor‟s own telefax facilities Paper shredding machine 1 computer room environment to accommodate 3 servers and access to this room to maintain servers Access to a separate office with a 3D CAD viewing station Access to a conference room equipped with all necessary equipment for external videoconferences. Office furniture equipment and services positioned in the area above office shall include: o 1 desk with lockable drawers o 1 side table o 2 x 3 shelf bookcases o 1 lockable filing cabinet o 1 high quality office chair o 1 visitor‟s chair o 1 table lamp o 1 telephone o 1 waste paper bin o hat/coat hooks/stand o 2 computer network connection (Ethernet) cabled to central computer room Provision of complimentary coffee, espresso machine, tea and cold drinking water (carbonated and still) Page 28 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Kitchen facilities including refrigerator and microwave oven Access to vending machines Access to use of Contractor‟s canteen at home office during normal working hours, at the same rate as charged to Contractor‟s personnel. Stationery and office supplies, including computer consumables, except Contracting Authority printed stationary and printed forms. A telephone service operated from Contractor‟s switchboard at the home office for Contracting Authority personnel. Parking facilities for 30 cars in close proximity to Contracting Authority‟s office location. Services to these offices and their contents in respect as such items as heating, air-conditioning, power, lighting, water, sanitation, cleaning, repair and maintenance. Provide and administer renting of cars (one for each manager and one each two discipline engineer) and high quality and fully furnished living accommodation (for 30 people) as per Contracting Authority standard in the neighborhood (Rome or Dubai) of the principal office location for Contracting Authority‟s personnel. Location of living accommodation will be selected according to the following criteria: safe area, quality, easy access to Contractor Engineering Offices. The Contractor shall provide such support services as may be requested by the Contracting Authority. Such services may include, but are not limited to: additional offices and office facilities for the Contracting Authority; obtaining and administrating Competent Authority and/or third party services in accordance with Contracting Authority instructions; Support services to arrange and administer travel reservations and obtain tickets, visas, etc. for the Contracting Authority‟s Representative and/or other Contracting Authority personnel. additional secretarial, administrative and support services as the Contracting Authority may require; and Courier services for the urgent transportation of documents, packages and the like. 1. Other Locations Where elements of the Work are to be performed at Locations the Contractor shall ensure the provision of similar adequate, dedicated office space, facilities and services for the Contracting Authority at such Locations, if so requested by the Contracting Authority‟s Representative. Page 29 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor shall provide access to its canteen services (if any) at any Location for use by the Contracting Authority‟s personnel and their visitors during the periods such facilities are normally available to the Contractor‟s personnel. 2. Provide during construction phase the following offices requirements for Contracting Authority Personnel in Contractor‟s SITE offices as detailed above and for the numbers of Personnel stated in Accommodation, Catering and Vehicle Attachment hereto except hiring of Contractor‟s staff and provision of parking facilities. 3. Accommodation and Messing for Contracting Authority Personnel at the Site Location 4. The Contractor shall provide, mobilise, maintain, operate and demobilise fully furnished and air-conditioned single occupancy accommodation and messing for up to thirty (30) Contracting Authority personnel assigned to and/or visiting the Location of the Permanent Works. Such Contracting Authority personnel shall also have full access to all recreational facilities provided by the Contractor for its own personnel at such Location. 5. Provide the following secure IT and communications facilities for Contracting Authority Personnel in Contractor‟s Engineering Design Office: Provide dedicated project assistants according to the project workload. For each member of the Contracting Authority‟s Personnel + 2 visitors (total 32 persons): o o o o o o o o 1 desktop PC 19” LCD monitor (second monitor to be added on a as needed basis) Full internet and e mail access Windows XP Professional operating system Microsoft Office suite (Word, Excel, PowerPoint, Outlook) Anti-virus and Anti-malware software Contracting Authority's electronic data management system software Other general and engineering software on a as needed basis (e.g. Acrobat Reader, Acrobat Professional, WinZip, MS Project, MS Access, Visio Professional, AutoCAD, Microstation) Contracting Authority‟s electronic data management system shall be Contracting Authority‟s electronic archive for administrative documentation and correspondence and for all technical documentation distributed to Contracting Authority for review/approval and preparation for final handover. The configuration of the system shall be compatible with Contracting Authority's electronic data management system (EDAM). Contractor personnel shall not have access to Contracting Authority project team‟s electronic data management repository. Selected Contracting Authority personnel shall have administrative rights to the system hosted on Contractors IT network. Contracting Authority shall be able to access Contracting Authority's electronic data management repository from the Internet (external log in). Page 30 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 A shared Contracting Authority‟s project mailbox (MS Outlook) to be provided. Contracting Authority common IT facilities: o o o o o o o Multifunction printer A3 format Colour printer Colour Scanner sixe A3 Local Area Network as per Contractor‟s standard Direct internet line (min. 4 Mbit synchronous) for the connection of Contracting Authority provided wireless network (for PMT and visitor‟s laptops). Minimum WPA encryption Backup and recovery administration as per Contractor standard, minimum daily backup Access to a 3D model viewing station in or close to the Contracting Authority‟s offices The PMT shall be able to access Contracting Authority home office networks from the supplied IT facilities using terminal server technology (Citrix, iLink, IRAS, VPN). Contractor shall provide IT helpdesk and technical support to all communications and hardware/software services provided, as per Contractor‟s standard. Contractor shall provide any and all data, metadata, and information created by Contracting Authority or by Contractor on behalf of Contracting Authority upon Contracting Authorities request. Contractor shall provide such information in a manner or on media as required by Contracting Authority. NOTE: Contracting Authority may choose to bring and install their own IT facilities for Contracting Authority‟s Personnel located on SITE offices. This shall include communication router/switches, security services, wireless access point, desktop and/or laptop PCs, print server, application server, file server, backup device, multifunction printer and colour printer. Contracting Authority IT equipment shall be connected to a network line to Contracting Authority home network using VPN technology. If Contracting Authority chooses this option Contractor is to provide: Accommodation for a minimum 4 Mbit synchronous data communication line (supplied by third party service provider). The line shall amongst other support remote access/replication to Contracting Authority's electronic data management system server in Contracting Authority offices in Algeria. Space for a Router and Switch and any security devices Contracting Authority deems appropriate in a secured Computer Room with restricted access Space for print server, application server, file server and backup device in a secured Computer Room with restricted access. Page 31 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 A cabled fast Ethernet LAN within Contracting Authority‟s project team offices to be connected between the Contracting Authority provided switch, servers, printers, PC‟s, laptops and wireless access point. 19” LCD monitor, keyboard and mouse for 32 laptops. Technical support for above items to a standard deemed appropriate by Contracting Authority, and commensurate with Contracting Authority‟s IT standards. 6. Provide the IT and communications facilities for Contracting Authority Personnel in Contractor‟s SITE offices as detailed above Page 32 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 3. GENERAL WORK DESCRIPTION This work covers a single Contract for all engineering, detailed design, procurement, construction, Mechanical Completion, Commissioning and Start-Up of the main facility, gathering system associated roads and infrastructure. This Work forms the basis of a fixed price “lump-sum” Contract. The scope includes design, procurement and installation of the Oil Gathering system, Central Processing Facility, Gas & Water injection Systems, interface tie-in piping/instrumentation/electrical between CAFC and MLE, plant and roads, as described in this document and the FEED package. In addition, the Contractor‟s Scope of Work shall include all civil works for site preparation beyond the preliminary site preparation performed by Contracting Authority and the provision of the infrastructure to support the sites during the construction, Commissioning, Start-Up handover and operational phases. All Work shall be performed in accordance with the Contract including resources to supervise and administer Subcontractors. The Contractor shall furnish all resources, consumables, Materials and Equipment, construction plant, labour, tools and services required to manage, engineer, design, document, procure, fabricate, transport, install, construct, test, inspect and commission the facilities in accordance with the Contract and this Scope of Work and perform all operations to complete the Work. In outline, the Contractor shall provide all necessary materials, consumables, services, equipment and labour to undertake, as a minimum, the following: 1. All Project Management, Engineering, Detailed Design, Procurement, Construction, Commissioning and Start-Up including those activities required to: Design, procure and construct, commission and start-up the Central Processing Facility, Oil Gathering system, Gas & water injection systems, interface tie-in piping/instrumentation/electrical between CAFC and MLE plant and roads in accordance with the Project codes, standards and specifications described in this Scope of Work and the FEED Package. Participate in scheduled Project Health Safety and Environmental Reviews, (PHSER). One review shall be held during detailed design and one prior to fabrication/construction, and one prior to Start-Up. Manage intermediary and final Hazard Identification (HAZID), Hazard and Operability (HAZOP) and SIL Assessment sessions involving Supplier and Contracting Authority participation. Manage, liaise and provide all necessary documentation to gain the necessary approvals of all Algerian regulatory and certification authorities. Interface with the Contracting Authority Project Management Team and the other Contractors involved in the Project as required. Prepare final documentation in accordance with project specifications. 2. Provide office facilities and services to Contracting Authority Personnel for the duration of the Project. Procurement of all equipment, steelwork and bulk materials. Page 33 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 3. Execute all required civil works and associated infrastructure, including all temporary works 4. Provision of a comprehensive logistics infrastructure to ensure materials are received in country, handled, customs cleared, transported to the sites for storage and installation. 5. Provision of all necessary covered and uncovered secure storage facilities for Materials and Equipment at all parts of the procurement chain. Ensure all necessary equipment preservation activities (including but not limited to vendor recommendations) are carried out. 6. Obtain all necessary Algerian Government and Statutory permits and approvals. 7. The Construction of the complete Central Processing Facility, Oil Gathering system, Gas & water injection systems, interface tie-in piping/instrumentation/electrical between CAFC and MLE plant and roads together with various elements of the scope either specifically detailed, or implied, that together define the Work. 8. Supply of materials and completion of fabrication, testing and all construction and installation activities for the Work. 9. Provision and installation of all required facilities for the Central Processing Facility, Oil Gathering system, Gas & water injection system, interface tie-in piping between CAFC and MLE plant and roads. This includes but is not limited to equipment and utility services, power distribution and emergency power generation, distributed control system, instrumented safety systems, materials handling facilities, telecommunications and equipment rooms. 10. Provision and installation of all necessary load banks and controls necessary to undertake site testing and Commissioning of the emergency generator. Provision of a temporary generator, to enable commissioning. Contractor shall substantiate actual power requirements and temporary power generator sizing. 11. Mechanical Completion activities 12. Pre-Commissioning, Commissioning activities and Start-Up activities 13. Provision, fabrication, installation and subsequent removal of any temporary piping required for testing and cleaning activities. 14. Cleaning of critical piping systems and equipment by retro-jetting, chemical cleaning or other appropriate methods. Critical systems shall be defined and agreed with Contracting Authority and shall include but shall not be limited to compressor suction pipework, compressor discharge pipework and recycle lines (including discharge coolers), fuel and seal gas systems, columns, Oil & Gas Gathering System, etc. System cleanliness shall be demonstrated. Methods to demonstrate cleanliness shall be defined and agreed with Contraction Authority. Detailed design of these and other critical systems shall be designed to facilitate these activities. Demonstration of system cleanliness is a key requirement prior to ready for Start-Up and the introduction of hydrocarbons. Page 34 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 15. Provision of any necessary Construction camps and all temporary site facilities and support services, including site offices and accommodation for the Contracting Authority personnel. 16. Provision of all necessary transportation to convey the Contractor‟s workforce to and from the construction sites. 17. Provision of water treatment, storage and distribution system, adequate for supporting the temporary construction camps and facilities throughout the course of the Work. 18. Provision of a sewage collection, treatment and disposal, adequate for supporting the temporary construction camps and facilities throughout the course of the Work, with particular attention given to the HSE expectations. 19. Provision of site First Aid facilities and related medical supply, qualified personnel and ambulances, consistent with the size, hazards and location of the workforce. 20. Provision of site access and security compatible with program provided by the Contracting Authority. 21. Provision of Suitable Site accommodation and all necessary facilities for Contracting Authority Personnel 22. Removal of all temporary services and reinstatement upon completion of the Works. 23. Provision of all Materials and Equipment. 24. Provision of all Hydrotesting services including, installation and subsequent removal of all materials required for the disposal of hydrotest water. 25. Provision of all materials and services required for the Fibre Optic cable links within this Scope of Work. 26. Any additional construction plant and personnel which prove to be required for the safe and proper performance of the Work or to satisfy the requirements of any approving authority shall be supplied by the Contractor. The cost of all such additional items shall be deemed to be included within the Contract price. 27. Contracting Authority shall perform early site preparation, earth moving and sand levelling, civil preparation including gypsum layer for CPF, and temporary construction camp. Contractor shall endorse and use the as-is final state of the early site preparation as the basis for execution of the Project. Any further site preparation required for the requirements of the Project is Contractor‟s responsibility and are part of the Work. 3.1 DESIGN CONCEPT AND DATA REVIEW Front End Engineering Design (FEED) on the CAFC Project has been carried out by the FEED Contractors. Information available from the FEED is to be used as a basis for scoping and programming the Work. The Contractor shall review, verify, endorse and take responsibility for the accuracy of the FEED documents included in FEED Package whilst preparing his tender and during the onset of the Work. Page 35 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor shall also require to perform a SITE SURVEY to endorse FEED and take responsibility for the accuracy of the FEED documents included in FEED Package whilst preparing his tender and during the onset of the Work. A list of project specifications has been included with the FEED package. All specifications shall be reviewed and updated as necessary by the Contractor, to ensure that they comply with the latest Algerian Law and the latest industry standards and best practices. Where it is identified that a specification is not provided as part of the FEED package Contractor shall produce and submit for Contracting Authority, the relevant document complying with the requirements of Algerian Law, project philosophies and recognised industry standards. Contractor shall incorporate safety and integrity critical lessons learnt from previous projects and requirements from Contracting Authority. This shall include but shall not be limited to lessons learnt from serious incidents and near misses The Contractor shall take responsibility for any conflict, error or omissions in the documentation after the award of the Contract. The Contractor shall be responsible for the removal of all “HOLDS” on documentation as part of the Detailed Design. Where a “HOLD” is indicated, the Contractor shall clarify with the Contracting Authority prior to removal of the “HOLD”. The following sections provide additional details describing the development of certain key documents provided. The design development requirements described below are not intended to represent all design developments associated with these documents. 3.2 HSE The design shall be consistent with CONTRACTING AUTHORITY HSE minimum requirements and Process Safety Philosophies and Reports as reported in Section 6 except where otherwise indicated within this document or the FEED package. CONTRACTING AUTHORITY HSE and Process Safety Philosophies and Reports shall be updated by the Contractor at the appropriate time within the design process as described above. Some of these documents have been updated during FEED. CONTRACTOR shall further define and develop the project HSE requirements for all CAFC project facilities with the aim to collate and documents all the HSE design criteria and philosophies, applicable regulations, codes and standards that are to be adhered regarding detail design and engineering, procurement, construction and commissioning and Start Up of the CAFC project facilities. 3.3 DESIGN INTERFACES CONTRACTOR shall be responsible for identification, engineering and assistance to CONTRACTING AUTHORITY in managing of all interfaces (limited to PLANT TIE-IN) with CONTRACTING AUTHORITY, and via CONTRACTING AUTHORITY with CONTRACTING AUTHORITY‟s other contractors and third parties that may arise in performance of the WORK. Page 36 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Design and installation interfaces include, but are not limited to those listed in the following sub-sections. 1. TIE-IN interface MLE and CAFC MLE PMT has provided the engineering and design documentation for the valved TIEIN‟s for utilities and process connections to enable CAFC CPF to operate. Generally these TIE-IN‟s have NOT been run back along MLE pipe racks to battery limit locations between the two plants although space has been allowed on the MLE pipe racks. CAFC FEED contractor has to include in his EPC Offer: - Purchase of all necessary pipe, fittings and instrumentation - Installation and routing of all piping, fittings, and instrumentation from within CAFC plant to the MLE plant to the battery limit tie in locations. - Testing, clean up and hook up of all TIE-IN‟s Specific details of the required TIE-IN‟s have been agreed with MLE PMT during CAFC FEED study. (details attached here MOMxxxxxxxxxxxx dated 23rd September) ATTACHMENT A to F Adobe Acrobat 7.0 Document Adobe Acrobat 7.0 Document Adobe Acrobat 7.0 Document Adobe Acrobat 7.0 Document Adobe Acrobat 7.0 Document Adobe Acrobat 7.0 Document January 2012 MLE PMT and CACF PMT agreed the TIE-IN‟s. MOM is attached here for clarification. ATTACHMENT I D:\Algeria\interface\ Jan25_2012\MOM 27 01 12 signed copy.pdf CONTRACTING AUTHORITY will furnish detail documentation of MLE/CAFC TIEIN‟s during EPC Clarification period. Page 37 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 2. OIL BOOSTER & EXPORT Pump Installation CAFC production requires the addition of two sets of oil booster and export pumps installed alongside the existing MLE pumps within the MLE CPF. These additional pumps will be identical to the existing ones and be procured from the same vendor. CAFC FEED contractor has to include in his EPC offer: - Purchase of 2 off oil booster and 2 off oil export pumps exactly the same as the existing MLE pumps and from the same vendor. - Note, pump foundations are included in MLE SOW - Install, hook up, test and make ready for operation. 3.4 FUTURE FACILITIES The future facilities at CAFC CPF include, but are not limited to: Booster inlet compression (not foreseen in the present SoW as this will probably be integrated with MLE booster compressor) 3.5 ALGERIAN REGULATORY BODIES The Contractor shall ensure that all the inspection requirements of the Algerian regulatory bodies are met. This shall include but not be limited to any necessary payments and coordinating visits to design offices, construction sites and supplier locations. Algerian regulatory bodies include but are not limited to ARH, DPEM, CTC, ARPT and ONML. Page 38 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 4. PROJECT MANAGEMENT 4.1 OVERVIEW The Contractor shall provide sufficient resources to effectively plan and safely manage the Work, including establishment and operation of Quality and Integrity Assurance requirements and Control measures and material procurement, expediting, inspection and control procedures and the securing of all necessary permits and approvals. The Contractor shall provide active management, direction and supervision of the Work, including, but not limited to, the following: (i) ensuring that the Work complies with the Contracting Authority HSE MS standards (Ref. Part C – Annex XI) and HSE Minimum Requirements (See section 6) and with all national laws, codes and international standards and that the Contractor's procedures are followed rigorously; (ii) organising the Work; (iii) reviewing and controlling project performance to ensure that the Work meets all requirements of the Contract; (iv) preparing and providing to the Contracting Authority the project control reports described in the Contracting Authority‟s Administration Instructions; (v) obtaining all approvals and satisfying all other requirements of the Competent Authorities in relation to the Work; (vi) co-ordinating and supervising all contacts with the Contracting Authority and the Competent Authorities in relation to the Work; (vii) keeping the Contracting Authority's Representative informed on all key activities in the Work in a timely manner and promptly highlighting any areas of concern; and (viii) Avoiding and resolving all the disputes between its subcontractors. The Contractor shall provide all project services necessary to manage the Work in accordance with the requirements of the Contract, with emphasis on efficient methods of working and meeting the Contract Schedule, including, but not limited to: (i) organisation of the project services; (ii) review and execution of effective controls to ensure that the Work is executed in accordance with the Contract; (iii) project management and provision of project control functions, planning, scheduling, cost control and document control as required to fulfil the Contractor's obligations under the Contract; Page 39 / 180 Part D - Scope of Work (iv) Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 co-ordination and provision of all project personnel, office services, translation services, accounting and secretarial functions necessary for the execution of the Work; (v) co-ordination of the Work and supervision of all contacts with the Contracting Authority and the Subcontractors; (vi) mobilisation of manpower for the Work; (vii) interface between the Contractor‟s project management and field construction operations; (viii) preparation of detailed work schedules and execution plans; (ix) monitoring of progress and comparison of actual performance with the detailed work schedules and reporting of deviations to the management of the Contractor and the Contracting Authority; and (x) Production of progress reports as specified in the Contracting Authority‟s Administration Instructions. 4.2 PROJECT EXECUTION PLAN The Contractor shall submit with their offer a preliminary Project Execution Plan for Contracting Authority review and evaluation, and within six weeks after award of the Contract, a definitive Project Execution Plan based upon the Contractor‟s offer as amended by Tender Clarifications, which shall be submitted to the Contracting Authority for Review. This shall set out the entire Work plan for the Project covering all topics including but not limited to: Organisation Management Design engineering Construction Engineering including follow-on engineering and MLE Interface Tie in execution Procurement and Logistics Technical Integrity Management Construction Facilities Risk Management Plans and Procedures Materials Transportation and Management Personnel Transportation Planning and Cost Control Subcontract Management Prefabrication Construction Camps and Facilities Page 40 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 CMMS Population Mechanical Completion Commissioning As-Built Drawings Certification Start-Up and subsequent Performance Testing Health, Safety, Environment and Quality (HSEQ) Industrial Relations Managing/interfacing community relations Change management Technical Query Procedures Final Documentation & operating manuals The Plan shall identify all of the Key Resources proposed for use in the execution of the Project. As the Project progresses through to completion, formal review and update of the Project Execution Plan shall be carried out to reflect the change in focus of the Project. The Contractor shall appoint a Project Director or Senior Project Manager who shall take ownership of the plan and who shall be responsible to the Board of Directors of the Contractor for successful delivery of the Project to the Contracting Authority. He shall ensure that all of the resources required meeting the overall Project Schedule and the individual Project Milestones are available and meet the specified acceptance criteria. He shall be the prime contact between the Contracting Authority and the Contractor and shall be accountable to the Contracting Authority for the achievement of the delivery of the Project to the standards contained in the Contract. The Contractor shall nominate a Project Sponsor from within the Contractor‟s Board of Directors in order to ensure that Project goals are met. 4.3 ORGANISATION The Contractor shall provide, in the Annex XV – “Contractor Personnel” of the Contract, an integrated Project Organisation, which shall be mobilised as a single Project Task Force. The Base Case shall be for the Project Task Force to be mobilised in a single Engineering, Procurement and Construction Management office location, with a fully networked Information Technology system linking all Key Personnel. At the appropriate time in the schedule, the Contractor shall mobilise a team to site (Contractor has to communicate in due time to Contracting Authority the number of persons composing this team). As a minimum, the following Key Personnel shall be nominated by Contractor, and submitted to Contracting Authority for approval: Project Manager Engineering Manager Senior Project Engineer Page 41 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Discipline Technical Leads Project Control Manager Quality Assurance Manager Quality Control Manager Community Relations Manager Lead Discipline Managers Construction Manager Commissioning Manager Materials Manager Welding and NDT Engineer HSE Manager (Detailed Engineering and Construction phase) Lead Safety Engineer Site HSE Engineers & Superintendent Operation and Maintenance Manager Project Information Manager Document Control Manager Procurement Manager Third Party Inspection Coordinator Security Manager Logistics Manager Contractor shall give to Contracting Authority organization chart both for Engineering Phase and for Construction phase. 4.4 PROJECT PROCEDURES The Contractor shall prepare a Project Management Procedures Manual no more than 1 month after effective date of the Contract. These procedures shall clearly set out the method by which the Project shall be controlled and shall include a comprehensive Work Breakdown Structure. These procedures will be reviewed and approved by Company; however, Company procedures will always have precedence. 4.5 QUALITY ASSURANCE The Contractor shall implement a documented Quality System (the “Contractor‟s Quality System”) in accordance with the requirements of ISO 9001:2008, to maintain Quality Assurance. The design and development of computer software shall be controlled in accordance with ISO9001:2008. The Contractor‟s Quality System shall be suitable for all the Work, shall be detailed within the Contractor‟s Quality Assurance procedures for each Location and shall be made project specific by application of the Contractor‟s Quality Plan(s) for the Project as outlined in Annex XIII – “Quality Plan”. The Contractor shall demonstrate the execution and maintenance of Quality Assurance to the Contracting Authority‟s satisfaction through all phases of the Work. Page 42 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor shall implement all aspects of the work in accordance with the procedures in the Contractor‟s Quality Plan. The plan will be an integral part of the Project and will come into effect at signature of the Contract. 4.6 SOFTWARE The Contractor shall use the following software for the execution of the Contract: HAZOP software - PHA or LIHOU Instrumentation Database - INtools Electrical engineering - ETAP Process engineering - Hysys - PRO II - Unisim - Pipesim - OLGA - FLARENET - FLAREsim Piping (CAD) - PDMS (3D) - AutoCAD or MicroStation (2D) - CAESAR II Pipeline: - Archgis - Autocad - Microstation Steelwork - STAAD.Pro HSE - Recognized Software‟s for Consequence Analyses - Software‟s for Quantitative Risk Analysis CMMS - EAM Planning - Primavera 3.1/ Microsoft Project Document Data Management: - EDAM Material Management - MIAP (to be defined during KoM or dedicated meetings organized by Contractor). Piping Specifications - SPCPUMA (to be defined during KoM or dedicated meetings organized by Contractor). General including - Microsoft Office applications (2003 or above) - Word, Excel, PowerPoint, Access, Visio Professional. Files generated by Microsoft applications shall be backwards compatible to version 2003. - Adobe Acrobat Professional, Reader Page 43 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Where required by the Contracting Authority, Contractor shall submit input and output files in source format and .pdf format for review by the Contracting Authority. 4.7 DOCUMENTATION The Contractor shall prepare all documents including Drawings, Specifications, calculations etc. required to perform the Work. This shall include all documents described or listed in this Scope of Work, all documents listed in the project specifications and any other documents that the Contracting Authority or the Contractor deem necessary to fully define, build and operate the Permanent Works. Existing Contracting Authority documentation that is affected by the new design shall not be renumbered, but the existing drawings shall be updated with new information. In agreement with Contracting Authority procedures, Contractor shall prepare a Master Document Register (MDR), which shall include all Contractor supplied formal and detail design documentation. The Table of Contents for the MDR shall be submitted to the Contracting Authority for review within 30 days after award of Contract. The Contractor shall develop and maintain the MDR of all documents, showing planned, forecast actual dates, current percentage complete and status for each document, which shall be subject to audit by the Contracting Authority at any time. The document register shall include all documents to be produced and/or updated by Contractor and all Supplier Documents The document register in place at the end of FEED attached in Annex I – “Technical” of the Contract shall be confirmed and validated by the Contractor to include all design deliverables within thirty (30) days of Contract award. All procurement deliverables shall be included within sixty (60) days of Contract award and all construction/Commissioning deliverables shall be included within one hundred and eighty (180) days of Contract award. As Contractor updates the document register, each document shall be identified after approval from Contracting Authority as requiring either review, approval or only for information. The dates that specify when Contractor shall submit documents to the Contracting Authority shall be delivered from Contract Control Schedule. The Contract Control Schedule shall be prepared by Contractor and reviewed and approved by Contracting Authority. All deliverables shall be submitted with approved planned dates. Any change must be submitted to Contracting Authority for approval. For each document the Contractor shall give a weight and submit the changes to the Contractor Authority. Any weight change in deliverables must be submitted to Contracting Authority for approval. From this Register of the Contractor's planned documents, the Contracting Authority shall identify those which shall be submitted to the Contracting Authority for Review/Information. Annex V – “Documents to be submitted to the Contracting Authority” of the Contract identifies the minimum level of document review required by Contracting Authority. Page 44 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 All documents shall be available to the Contracting Authority in locations to include: Contracting Authority Home Offices, Contractor‟s Project Office and the field construction SITE. All documents shall be developed such that they can be provided to the client in electronic format. Contractor shall prepare and maintain an index of all Supplier manuals. This shall be maintained in an electronic format for eventual hand over to the Contracting Authority. Contractor shall maintain all Drawings and documents relevant to Start-Up up to and including final "As Built" status. The "As Built" documents shall be incorporated into the final Contractor‟s Design Report for handover by the Contractor and acceptance by the Contracting Authority. Contractor shall produce Operating and Maintenance Manuals for all equipment, including all equipment data books, operating instructions, emergency procedures, maintenance instructions and recommended spares lists for each item, as provided by Suppliers. The Operating and Maintenance Manuals (or procedures) shall be prepared in English and translated into French. Both the Operating and Maintenance Manuals are to be completed by Contractor at least 8 months prior to Start-Up. The contents of the typical operating, maintenance and safety manual shall be followed at a minimum: Process description, with Plot Plan, PFDs, Material Balances; Utilities description; Distributed Control System; Overview Drawings, such as Electrical One Line Diagrams, Area Classification Diagrams, Material Selection Diagram, Hazardous Area Diagram; General Safety Instructions; Operating Instructions; Outline for Individual Equipment, including: Brief description of Major Equipment; Operating Instructions; Operating Limitations; Safety Items and Operational Hazards; Recommendations for Maintenance and Repairs; Recommended spare parts list Support Systems, including: Corrosion Protection System; Communications System; Safety Systems. Page 45 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Contracting Authority require detailed “valve-by-valve” Operating Procedures in order to verify clear, complete procedures and to certify competency of operator‟s knowledge and interaction between control and process systems. The Operating Procedures for the Facilities shall be prepared by Contractor. Contracting Authority shall provide technical support and recommendations during the review process. The Operating Procedures shall require review and approval by Contracting Authority and shall include, as a minimum, the following: System descriptions Technology descriptions How the system shall be started, operated and shut down, covering normal, abnormal, and emergency situations Design limitations Operational set points Drawings (P&ID‟s, Cause and Effects, etc) Any special operating procedures Timeline and programme to include manpower requirements List of commissioning, test, start up and recommended spare parts procured List of Commissioning Lubricants, consumables and bulk materials List of Chemicals List of all Equipment with general information List of Operations and Maintenance Training Requirements Contractor shall review the content of the Maintenance Manuals and ensure that all technical requirements are included. The finalised Maintenance Manuals shall be provided for approval to the Contracting Authority 8 months prior to Start-Up The following activities shall be also considered: Review all Vendors Operating and Maintenance manuals for completeness; Obtain from Vendors any clarification, explanation and additional information necessary to satisfy the commissioning and operation requirements. Documentation, including “As-built” documentation and Engineering Information shall be supplied by the Contractor in accordance with Annex V – “Documents to be submitted to the Contracting Authority” of the Contract.. The Contracting Authority reserves the right to review all Contract deliverables. However, it is the intention that the Contracting Authority shall only review certain key documents. The key documents are detailed in the review matrix to be defined and inserted in Annex V – “Documents to be submitted to the Contracting Authority” of the Contract. Review of documents by Contracting Authority does not relieve Contractor of the responsibility to provide complete, safe and operable facilities in full accordance with Contracting Authority supplied documents and Scope of Work. A program for document Page 46 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 review shall be submitted to Contracting Authority by Contractor within 30 days of Contract award. It is Contractor's responsibility to ensure that Contracting Authority‟s Representatives are notified in good time of the issue of key documents for review and to expedite review to avoid delay to the Work. Contracting Authority shall require an Information Management Plan to be submitted for review by Contracting Authority within 8 weeks of contract award. The Information Management Plan shall: Identify all database/software sources and the layout and structure of data within any database on a discipline-by-discipline basis. Advise software name and version. Provide a schematic illustration of information systems and flow of data between them. Identify direct application-to-application links, file-to-file transfers and manual transfers. List main document types to be produced by Contractor with reference to production software. Describe how 3D CAD models shall be organized, managed and interfaced with other system tools. Describe how 3D CAD models shall be developed and used throughout the various project phases. Allocate responsibilities to all parties involved. Define how information shall be collected, processed, stored and exchanged. Identify Document control procedures, including document distribution, review and approval of engineering and supplier documentation, client review and approval, Identify documentation quality plan and procedures. Progress reporting for design documentation, documentation and engineering data. supplier Provide schedules and identify deliveries against the project milestones. Special attention shall be given to identify milestones for pre-handover to Contracting Authority for operations and maintenance planning activities. Detail measures to ensure information integrity and singe source philosophy. Detail the implementation of a Master Tag register and how to ensure this remains the tag master throughout all phases of the project. Define how to ensure the electronic version of the document is regarded as the original (both engineering and supplier documentation). Define how data transfer to Contracting Authority systems on a basis to be mutually defined. Page 47 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Define how information shall be distributed on the Sites. Define how to documentation. ensure correct updating and as-built As-built procedures. Detail the process by which formal handover shall be achieved. Handling of French translations of documents. The plan shall be coordinated with the Contract Master Schedule. Contractor shall give Contracting Authority access to a 3D model viewing station in Contractors offices and on Site and should be accessible externally by the Contracting Authority. The view model shall be updated by Contractor at regular intervals. Contractor shall hand over the complete 3D design model developed during detail engineering. This shall include all catalogues and specifications used and a description of the hierarchical structure of the model. Service descriptions used for tags shall be unambiguous, indicate both equipment function and location, and be in line with the tag description practise established in the Computerised Maintenance Management System. Contracting Authority requires total access to all design and supplier documentation for maintenance planning, training and other preparations for operations activities. Information shall be transferred from Contractor‟s systems to Contracting Authority databases at agreed milestones. A test transfer of electronic information shall be carried out as early in the project as possible to verify the data transfer procedures. This shall include all relevant types of digital formats. Transfer of documentation and information into Contracting Authority data management system is the responsibility of Contractor. This includes data quality, completeness, consistency, data format and compliance with existing codes and attributes. Contracting Authority shall on a regular basis carry out verifications to ensure that information complies with requirements. 4.7.1 Data and Document Management The design activities shall be developed according to the requirements of technical specification defined in the tender documentation and according to the following Contracting Authority Standards: Contract requirements for technical document management and facility technical data delivery The following paragraph provides a detailed list of Contract requirements concerning technical document management and facility technical data delivery for Company database. Each requirement shall be accomplished according to a listed set of Company specifications The requirements include: Technical organization for document and material management Page 48 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Minimum technical data required for typical basic design documents Detailed full life document planning and progress report Document approval management Implementation of CAD Programs Computerized delivery of technical data to Company Database Delivery of model and spare part data for integration with maintenance Paint & Coating Activities Technical organization for document and material management 06215.DOC.GEN.SDS 20189.COO.GEN.SDS blocks 20198.COO.GEN.SDS Facility functional Units Technical document identification and title Item Numbering Minimum technical data required for typical basic design documents 20259.DOC.GEN.SDS 06221.DOC.ELE.PRG 06227.DOC.GEN.PRG 06222. DOC.PRC.PRG 06223. DOC.MEC.PRG 06224. DOC.MEC.PRG 06225. DOC.STA.PRG 06681.DOC.ELE.PRG 06682.DOC.ELE.PRG P&ID Piping and instrumentation Diagram OLD One line Diagram Facilities Plot plans Equipment List Line List Hand Valve and Line Accessories List Loops and instrument List Electric load list Electric cable list and electric cable report Detailed full life document planning and progress report 27605.VAR.GEN.SDS Technical Documentation required during the Project Development Phase Document approval management 27608.DOC.GEN.SDS Management of approval of technical documents Piping Class Management CONTRACTOR will apply COMPANY standard methodology and software ( SPCPuma ) to manage and generate the facility piping class and relative piping Referance Database ( RDB ) to import in a 3D CAD Model , according to document: The COMPANY will provide to the CONTRACTOR the appropriate access to COMPANY Piping Class Database Implementation of CAD Programs 20204.CAE.GEN.PRG Procedure for preparation of 2D CAD Drawings Page 49 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 20205.CAE.GEN.PRG General procedure for preparation of 3D CAD models and deliverables production 20206.CAE.GEN.PRG Standard rules for preparation of 3D CAD models and deliverables production by using Intergraph PDS3D 27901.CAE.GEN.PRG Standard rules for preparation of 3D CAD Models and deliverables production by using AVEVA Vantage PDMS 20248.CAE.GEN.SDS Survey of existing facilities through laser scanning to obtain the as-built 3D CAD Model and associated data and document 27906.CAE.GEN.PRG Standard rules for preparation of 3D CAD models and deliverables production by using Intergraph SMARTPLANT 3D Computerized delivery of technical data IN Company Database 06214.DOC.GEN.SDS Instructions to Contractors for information submission to DBIMP 20203.DOC.GEN.SDS Handover of plant component data and key documents for DBIMP The COMPANY will provide to the CONTRACTOR the appropriate access to COMPANY data Loading web site or, in alternative, the excel template. Delivery of model and spare part data for integration with maintenance 20202.DOC.GEN.PRG Model and spare parts data required from Vendors Paint & Coatings Activities 20000 VAR.PAI.FUN. Rev.3 - Protective coatings, galvanising and metallising for internal and external surfaces of offshore and onshore structures and related components 20550 PIP.COR.FUN. Rev.0 – External coatings for corrosion protection of steel Pipes and components 20551 PIP.COR.FUN. Rev.0 – Internal coatings for corrosion protection of steel Pipes and components 20552 VAR.PAI.FUN. Rev.0 – Maintenance of coated surfaces Guide to implementation of OOC / ENI E&P computer programs for CAE (computer Aided engineering) Guide to implementation of OOC / ENI E&P proprietary computer programs for CAE (Computer Aided engineering) or other recommended programs. Tool MIAP: ITEM BR 001 Rev A01 Tool SPCPUMA: ITEM BR.002 Rev A01 Overview of Miap information system (item coding, bulk material coding, model and spare part coding) (to be defined during KoM or dedicated meetings organized by Contractor) Overview of SPCPUMA Functionalities (computerization of Piping specs, creation of piping spec catalogues (to be defined during KoM or dedicated meetings organized by Contractor) Tool EDAM: Page 50 / 180 Part D - Scope of Work EDAM Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Engineering Document Approval Management Page 51 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 4.7.2 Coding Methodology for Correspondence The information exchange and the engineering documents transmission will be performed in accordance with the following criteria. All the official information shall be transmitted in written. In principle any form of written communication is accepted (e-mail, fax and letter). The official information exchange between Company and Contractor shall take place through the respective authorized representatives. The main exchange of technical information shall be through e-mail or informatics platform. For all the meetings between Company and contractor a minute of meeting shall be edited. The conversations between Company and contractor not reported in writing will have no effect. Communications regarding different matters or relative to different discipline will be accepted provided that the main points are recalled in the object of the communication so as to allow their traceability. In general the following indications shall be included in the correspondence in order to be used: - References to previous correspondence; - Reply or expected actions; - Timing for the actions or expected replies. In order to facilitate the management of the technical correspondence among the parties involved in the project the below reported identification shall be used: FFFFFFSS_NNN_OOO_DDD_X_NNNNNN Where: FFFFFF Facility Code SS Sub-facility Code NNN Correspondence Type OOO Originator (business name code - three alphanumerical characters) RRR Receiver (business name code - three alphanumerical characters) X Discipline (see Ref.2) NNNNN Sequential number Correspondence Type LET Letter FAX Fax EMA E-mail TRN Transmittal MOM Minutes of Meeting EMREngineering Monthly Report EWR Engineering Weekly Report VOR Variation Order (Technical) Request Page 52 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 WSTWork Statements TQ Technical Query Ex. 00220600_LET_ENI_TCM_G_00001 Note The weekly and the monthly reports shall have instead of the sequential number the date in following format: YYYY_MM_DD Ex. 00220600_EMR_ENI_TCM_G_2009_04_01 The identification of transmittal IN of contractor and of transmittal OUT of Company for the management of the approval cycle is defined in 27608.DOC.GEN.SDS - Management and approval of technical documentation The Company can request the contractor in each moment the files of the documents on information support (CD or DVD). This support shall be identified as follows: FFFFFFSS_CCC_NNN_Data Where: FFFFFF SS CCC NNN Data Facility code Sub-facility code Business name Code of contractor Sequential number of CD/DVD Creation date of the CD in format: YYYY.MM.DD In the CD/DVD shall be inserted the index of the files contained (including code, title and revision of the document). In the index to each file shall be applied a hyperlink which sends to the relative document. 4.8 MANAGEMENT OF CHANGE The Contractor shall submit their proposed Management of Change (MOC) procedure with their tender for Contracting Authority review to be integrated in Annex XVI – “Contract Administration Manual” of the Contract. Contractor shall implement a change control procedures to ensure that changes in the design of the work are controlled, in accordance with the Contracting Authority minimum requirements. These procedures will be reviewed and approved by Company; however, Company procedures will always have precedence. Page 53 / 180 Part D - Scope of Work 4.8.1 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Management of Change Policy All temporary and permanent changes to organization, personnel, systems, procedures, equipment, products, materials or substances shall be evaluated and managed to ensure that health, safety and environmental risks arising from these changes remain at an acceptable level. Contractor shall comply with changes to laws and regulations and take account of new scientific evidence relating to HSE effects. 4.8.2 Documents concerned by MOC Management of Change procedure shall be applied to the following documents including but not limited to: Plot plans PFDs and UFDs P&ID‟s Equipment Data Sheets Equipment List Line List Material Safety Data Sheets Emissions Tracking Matrix Cause and Effect Chart Electrical One Line Drawings Electrical Area Classification PSV Design Basis and Calculations Instrument Index Aspect / Impact Matrix Operating Procedures Maintenance Procedures Training Documentation Emergency Response Plans Compliance Matrix Environmental Management Program Safeguarding Philosophy and Diagrams DP/DT Drawings Material Selection Drawings CV Datasheets RV Datasheets Hazardous Area Classification Layouts and Reports Safety Systems Design Design Pressure and Temperature Diagrams Page 54 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Heat and Material Balance 4.9 DAMAGE AVOIDANCE PROCEDURES The Contractor shall ensure that no damage is done to existing MLE facilities or adjacent land, property and habitation during execution of the Work. Contractor shall provide fully developed damage avoidance procedures no more than 1 month after effective date of the Contract and shall follow the procedures. Procedures may require installation of temporary protection for simultaneous operation with a live NGL plant. Such procedures shall include damage avoidance to existing infrastructure, and local community facilities and relationships. To facilitate the preparation of these procedures, Contracting Authority will provide required documents which are included in Annex XI – “HSE Management System Requirements” of the Contract. 4.10 HSE PLAN AND MANAGEMENT The Contractor shall prepare an HSE Plan and Management System in accordance with the requirements of Annex XI – “Health, Safety and Environmental” of the Contract The Contractor shall develop and implement an Approved safety management plan to maintain Best Industry Practice with respect to construction and Commissioning which shall apply to both Contractor and Subcontractor personnel. This shall include a safety organisation for each Location, supported by procedures and the Contractor‟s project management team. This plan shall address all safety critical activities such as personal protective equipment, scaffolding, rigging, trenching and excavations, vehicle movements, speed limits, etc. The Contractor shall prepare and implement a management system (“HSE Management System”) for all phases of the Work to ensure that the Contracting Authority's HSE standards and other requirements are implemented in the Design. The Contractor shall submit its proposed HSE Management System. The HSE Plan and Management System shall be revised and updated as the Project proceeds. The Contractor‟s organisation and arrangements necessary for the implementation of his HSE MS shall be developed into the Contractor‟s HSE Plan. The HSE Plan shall be prepared specifically for the Work. The HSE Plan shall be subject to Contracting Authority‟s review and shall be finalised and completed within four (4) weeks of Contractor‟s “Instruction to proceed with the Work”. Contracting Authority reserve the right to review any proposed amendments to the agreed plan, which may be necessary as the Work progresses. The Contractor‟s HSE Plan shall make specific reference as to the procedures, permits etc. which shall be used to ensure that the safety of the operations are not compromised. Page 55 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor shall establish an organisation plan and procedures to ensure that all HSE aspects of the Work are thoroughly considered, planned, implemented and followed up during all phases of the Work. The HSE programme, which is to broadly comply with the requirements of Contracting Authority‟s HSE standards and policy, shall be updated as necessary through the period of the contract. The Contractor shall provide a dedicated HSE Manager who shall have overall accountability for the implementation of the Contractor‟s Health, Safety, Environmental requirements and Technical Integrity requirements, as detailed in Section 6 of this document and in the Annex XI – “Health, Safety and Environmental” of the Contract . The HSE Manager shall be directly responsible to the Project Manager. The HSE Manager shall be supported by representatives of the Contractor‟s HSE organisation. The Contractor‟s offer shall include an overview of the proposed HSE Plan and a nomination for the HSE Manager‟s position together with the dedicated HSE staff for detailed engineering and construction & SIMOPS phase. The Contractor shall develop and implement a Contracting Authority Approved safety management plan to maintain best industry practice with respect to construction and commissioning both for the Contractor and Subcontractor personnel. This shall include a safety organisation for each Location, supported by procedures and the Contractor‟s project management team. This plan shall address all HSE critical activities such as personal protective equipment, scaffolding, lifting and rigging, trenching and excavations, vehicle movements, and land transportation, confined space activities, working at height, radioactivity, SIMOPS activities, etc. 4.11 BRIDGING SYSTEM A suitable bridging system to the Contracting Authority‟s safety management, travel and security plans shall be developed by the Contractor and submitted to the Contracting Authority for Approval. Similarly, all Subcontractors shall be covered by suitable bridging documents to clearly identify safety interfaces and responsibilities and required actions in an emergency situation. 4.12 PLANNING, SCHEDULING AND PROGRESS REPORTING The Contractor shall prepare detailed schedules for all areas of the Work. The Contracting Authority Work Breakdown Structure attached in the ITT and to be included in Annex II – “Breakdown of Prices for Goods and Services” shall form the basis of the Contractor‟s Planning, Scheduling, Cost and Progress Reporting System. A dedicated analysis should be done for the early works, with different planning and S-curves. The Contractor shall prepare a document where it is described how he shall interface with the Contracting Authority Work Breakdown Structure together with information on the Contractor‟s Management System. The Contractor shall also provide a Level 2 schedule, histograms, planning and control procedures with his offer, to be approved by Contracting Authority. Page 56 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Schedules shall be prepared in a structured way showing individual elements. Each element shall be able to be definitively progressed and be rolled up to multiple levels of control. The schedule shall issue for comments and approval to Contracting Authority. Any changes to the deliverable planned schedule dates and item shall be submit to Contracting Authority for approval; until such approval the original schedule shall be maintained. The Contractor shall update task level schedules through a weekly reporting system designed to verify that Work is proceeding according to plan. The Contractor shall produce look-ahead summaries of activities planned and resources to be employed, covering the period up to one month ahead at any time. Weekly reviews shall be held with the Contracting Authority‟s Representatives to verify progress and ensure that data flow continues to support the schedule. The weekly and the monthly reports shall include: 1 - “Baseline Curve Scheduled” (= ”Original Baseline Curve” ) and relevant per cent progress (“Scheduled Progress”); 2 - “Actual Curve” and relevant per cent progress (“Actual Overall Progress”); The weekly and the monthly reports can include the possible “Baseline Curve Rescheduled” and the relevant “Target Overall Progress” only if approved by Contracting Authority. Problem areas shall be identified and remedial action put in place by the Contractor. The role of the Contracting Authority‟s Representatives shall be to ensure that remedial actions are adequate and are appropriately co-ordinated across the Project. It is the Contractor‟s responsibility to co-ordinate those actions within the Project and to advise Contracting Authority of any potential impact on interfaces with other groups. The Contractor shall prepare summary link schedules for Procurement, Construction and Commissioning showing all critical activities throughout the execution of the Project. In the Monthly Report he shall identify all critical and marginally subcritical activities and report on his strategy for ensuring that the Project Schedule shall be maintained. The Contractor shall provide, maintain and be responsible for all management of Contractor‟s personnel and resources, which are involved in this Contract covering all aspects of the Work. Contractor‟s systems shall be data based and capable of providing quick “what if” analyses of adverse trends and problem situations. Systems shall be capable of producing a comprehensive range of reporting options to provide timely and concise decision-making information. Schedules shall be developed and maintained using Primavera version 3.1 software or equivalent subject to Contracting Authority approval. Where required by the Contracting Authority, the Contractor shall submit data files in .PRX (source file) and .PDF formats for review by the Contracting Authority. Page 57 / 180 Part D - Scope of Work 4.13 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 INTERFACE MEETINGS The Contractor shall hold weekly engineering meetings with the Contracting Authority to review the issues and various discipline activities and progress. Contractor shall minute issues and report progress against each item at the beginning of meetings. Furthermore the Contractor lead discipline engineers shall have weekly scheduled meetings with their Contracting Authority‟s counterparts to discuss discipline related issues. These meetings shall also be minuted by the Contractor. The Contracting Authority lead discipline engineers and other Contracting Authority project personnel shall be able to discuss comments on reviewed documents or any issues face to face with the Contractor‟s counterparts and other Contractor personnel on an ad-hoc basis. Major Package and sub-order technical issues shall also be addressed on a weekly basis at the above meetings, on top and above of any procurement meetings/activities. Moreover the Contractor shall hold Interface meetings with MLE PMT when required under the control by the Contracting Authority, in order to coordinate and facilitate interface activities. 4.14 MANAGEMENT OF EXTERNAL INTERFACES The primary Parties involved at the interfaces with the WORK are as defined in this SOW. The design interface main work responsibilities at such interfaces are defined in item 3.3 (DESIGN INTERFACE). CONTRACTOR shall prepare the design, planning scheduling or other work required for progressing the resolution of such interface matters. Interfaces include those area where CONTRACTOR has to exchange information with other parties for carrying out his own WORK, as well as physical interfaces at the limits of supply between CONTRACTOR and other Parties. Any additional cost and/or time impact due to such interfaces shall be recognised by CONTRACTING AUTHORITY to CONTRACTOR through a CHANGE ORDER. CONTRACTOR shall issue drawings and documents as requested by other Parties and be responsible for review of all engineering WORK associated with the interface to ensure that the final design is on accordance with his own engineering WORK. CONTRACTOR shall therefore be required to attend regular interface meetings.. All official contact with the Parties involved at the interfaces with the WORK shall be channelled through CONTRACTING AUTHORITY. CONTRACTING AUTHORITY may, however, at its options allow CONTRACTOR to have direct contact with interface party or impose such conditions on him. CONTRACTOR shall: Via CONTRACTING AUTHORITY, initiate and organize contact at the technical level with the Parties involved. Page 58 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Keep CONTRACTING AUTHORITY advised with sufficient notice so that CONTRACTING AUTHORITY representative may attend any meetings arranged to discuss such matters. Provide for travel to and attendance at meetings in other Parties offices and for staging meetings in CONTRACTOR‟s offices. Prepare minutes of meeting, arrange for signature by, and issue to, all Parties. In addition, CONTRACTOR shall formally advise CONTRACTING AUTHORITY of any interface problems, which may arise form such meetings. Prepare, submit for APPROVAL and implement a detailed interface plan and coordination procedure to cover for external interface activities as defined above. Where aspects of a commercial nature are involved, CONTRACTING AUTHORITY shall be the first and sole point of contact. Technical interface co-ordination meeting shall take place as soon as practical after AGREEMENT DATE with the Parties involved at the interface. CONTRACTING AUTHORITY shall initiate interface kick of meetings. Further meetings shall be held at regular intervals during the course of work. CONTRACTOR shall schedule his WORK, in respect of interface matter to coincide with the schedules of the other PARTIES. CONTRACTOR‟s proposed schedule shall be subject to APPROVAL. Page 59 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 5. SCOPE OF WORK AND DETAILED DESIGN/ENGINEERING 5.1 GENERAL The Contractor shall review, verify, endorse and take responsibility for the accuracy of the FEED documents included in FEED Package whilst preparing his tender and during the onset of the Work. Annex I – “Technical” of the Contract lists the documents resulting from FEED and Contracting Authority, which form the basis of the scope of this Contract. This includes, but is not limited to: Process and Utility / Flow Diagrams Process Simulation Files and Calculations Process and Utility P & IDs Process and Equipment Design Data Heat and Material Balance Specifications, Standards, Regulations And Recommended Practices Material Take-Offs Design Philosophies Site Layouts Flowlines and Trunkline Alignment Sheet Typical Pipeline Installation Drawings Equipment Lists Equipment Data Sheets Single Line Diagrams Electrical Load list Electrical studies Control System Statement of Requirements and System Hierarchy Drawings Block Flow Diagrams FEED HAZID and HAZOP reports for follow-up during EPC phase Safety systems HSE studies and risk analyses At all times the Contractor must give particular attention to the very hot environment in which the facility shall be built and operated and the desert environment with sand/dust presence. It is understood that the Work may be conducted at multiple geographical locations. In addition to the Contractor‟s home site, subsidiary locations may include Algeria, and possible engineering satellite offices as agreed with the Contracting Authority. At all times control and Page 60 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 execution of the Work shall be at the Contractor‟s home site, and all relevant control and engineering information available and accessible from there. Contractor‟s engineering shall be efficiency optimisation oriented. When and where it is necessary for the Contracting Authority to obtain information from Personnel at these locations, usage of video-conference, electronic mail and group telecommunications shall be made available by the Contractor for efficient conduct of the Work. The Contractor shall organise and undertake all activities, including but not limited to: 1. Obtaining all permits necessary for the execution of the Project prior to activities in Algeria. This shall include briefing, discussing and reaching agreement with the appropriate Algerian regulatory authorities. 2. Detail design for all civil works including all site preparation, foundations, roads, and drainage. This shall include all survey necessary for the execution of the Work and site investigation. 3. Detail design for all structural and architectural works. 4. Detail design of process, utility, electrical, mechanical, pipelines, piping, ICSS, control and protection instrumentation, safety, and telecommunications required to provide complete, safe, reliable and operational facilities. This includes maintaining and providing copies of all calculations and providing same to the Contracting Authority in original electronic format. This is to include arranging any necessary agreements/licences. This shall also require setting up appropriate sub-agreements with the Contracting Authority to allow full access to and usage of information necessary for the design, erection and operation of all facilities. The Contractor shall be responsible for the overall system design to ensure process design requirements are met. 5. Prepare all necessary, Approved for Design (AFD) and Approved for Construction (AFC) Drawings, P&IDs, Data Sheets, Specifications, tender requisitions, purchase requisitions and equipment lists sufficient to fully describe all components for procurement, fabrication, transportation, storage, installation, Commissioning, start-up and operation. 6. Prepare AS BUILT documentation at the end of the Work, within 90 days of the agreed Mechanical Completion date for documentation detailed in Annex V – “Documents to be submitted to the Contracting Authority” of the Contract.. 7. Amend and/or update the Project Specifications, Drawings, Data Sheets, equipment Lists and Studies developed during execution to meet Project specific requirements as well as to provide a clear, concise technical documentation package. Prepare any additional Specifications required for the Work not included in the execution documentation. Page 61 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 These Specifications shall cover the design, Commissioning and operation of the equipment. manufacture, construction, Where elements of the Work (e.g. civil details, architectural, piping design) are subcontracted, Contractor shall apply all procedures, codes, standards and specifications such that this work is conducted to a standard equal to that of the Contractor and documentation provided to the MLE Project is of an equal standard. 8. Maintain a design change control system. 9. Complete all necessary material take-offs. 10. Produce fabrication Drawings, as required. 11. The minimum codes, standards and specifications to which the Work shall be executed are included in the Contract Package. This includes all Contracting Authority codes, standards, specifications, philosophies, inspection requirements, etc. Where the necessary information is not provided the Phase documents and actual design become the basis for the development of the minimum standard to which the work is to be completed. 12. Produce field erection Drawings, including Drawings for temporary erection aids. 13. Preparation and maintenance of Contractor‟s Design Report. This shall include summary of final design, basis, calculations etc. 14. The Contractor shall perform all required engineering and shall maintain a dedicated qualified engineering design team required to complete the design, procurement and all construction support engineering for the Work listed as it progresses through until Operation. 15. Provision of general logistic and administrative assistance, including but not limited to obtaining permits, visas, accommodation, hotel rates, car rental, transportation for Contracting Authority Personnel 16. Prepare Tender and Purchase Requisitions. 17. Prepare bid evaluation documentation for Supplier selection. 18. Procure all Materials and Equipment in accordance with Contracting Authority Approved Specifications, and Data Sheets. 19. Conduct Supplier clarification meetings to assist in bid appraisals. Contracting Authority shall be invited to participate in technical meetings. 20. Attend selected Supplier kick-off meetings following purchase order award. Contracting Authority shall be invited to participate in kick-off meetings. 21. Attend selected Supplier factory inspections to ensure that delivery schedules are met. Contracting Authority shall be invited to attend in factory inspections. 22. Attend Supplier Factory Acceptance Testing of equipment. Contracting Authority shall be invited to attend in Factory Acceptance Testing. Page 62 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 This shall include advising the Contracting Authority of Factory Acceptance Testing, with at least fourteen (14) days notice, making available records of defects and comments. The Contracting Authority reserves the right to attend these tests. 23. Check, verify completeness, record and catalogue all material mill certificates, equipment documentation and test reports. 24. Prepare detailed installation procedures for equipment based upon Supplier recommendations. 25. Prepare detailed inter-connection cabling and wiring/termination Drawings for coordination of packaged equipment from various Suppliers. 26. Implement Welding, quality control and non-destructive testing plans and procedures / workpacks. This shall include special welding procedures and welder qualifications for carbon steel, alloy steel and other work. 27. Prepare system mark-ups and hydrotest diagrams for Mechanical Completion tests. 28. Develop Inspection and Test Plans. 29. Implement expediting, inspection and testing as required by the Inspection and Test Plans. 30. Populate the Computerised Maintenance Management System (CMMS) in the French and English languages according with provided templates 31. Prepare Commissioning documents and procedures. 32. Prepare detailed Operating Manuals and Maintenance Manuals and manage, review and approve Supplier Documentation Manuals. 33. Support the Contractor‟s Construction Team in interpretation of design in the field and co-ordinate to ensure that Technical Integrity is maintained throughout the Project. 34. Expedite Suppliers and interface with other Contractors required for the execution of the work by the Contractor. 35. Manage Suppliers to obtain equipment sizes and weights to ensure timely definition of detailed layouts of equipment, piping, cabling, tubing etc. 36. Interface with Suppliers to ensure Technical Integrity is maintained in accordance with the Specifications and Data Sheets throughout the Project. 37. Prepare all documents required to be submitted for approval by Algerian agencies. Such documents shall be prepared in English and French. Make changes to design where these agencies can show that all acceptable interpretation of Applicable Code, Standards and Specifications has not been made. 38. Provision of miscellaneous presentational materials necessary to the Contracting Authority in gaining acceptance of the Work in the presence of Shareholder and third party organisations. 39. Provide copies and licences for all software supplied with the Project including PLC, CMS, etc. The HSE scope of work shall include, but is not limited to: Page 63 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Preparation of overall HSE policy, plan and procedures for all phases of work; Participation in design reviews of providing expert leadership for formal safety reviews of the facility design e.g. HAZOP, SIL, HAZID, PHSER, etc; Incorporation of the results of the formal safety reviews into the design Verification that the design and the prosecution of the work complies with all laws, regulations and the HSE plan / procedures; Provision of expert advice personnel at the construction sites to assist line managers in ensuring a good safety outcome; Compiling, analysing and reporting on safety statistics and metrics achieved e.g. LTIFR etc. 5.2 FACILITIES 5.2.1 Process Engineering The facilities are described in the document “Process Basis of Design”. The Contractor shall use this document, the information given below and in the Part C of the Contract (the more onerous where there is a conflict) as the basis for updating the “Process Basis of Design” to include the facilities associated with the Project This shall be completed within 6 weeks of contract award and shall be subject to Contracting Authority approval. The Heat & Material balances (in the form of HYSYS output) form the basis for the documents contained within the FEED package. Each equipment item is sized based on whichever of the cases is most onerous when applied to that item. This principle shall be followed by the Contractor. Where there is a specific reason, the design basis data may be modified in order to take account of specific considerations applicable to specific equipment items. Such cases shall be indicated by the data sheets or other FEED documents. Note: If there are any discrepancies between the FEED documents and the heat and material balance, the information contained within the heat and material balance, as may have been modified during FEED update, shall take precedence over any information obtained from FEED documents. The Contractor shall review, verify, endorse and take responsibility for the design of the gathering (oil and water production) and distribution (gas and water injection) system (offplot), lines sizing, flow assurance studies (static and transient conditions), material selection, described by the design documents included within the ITT in order to ensure that ALL of design cases can be met at the site conditions described within the design documents. The Contractor shall review, verify, endorse and take responsibility for the design of all the associated process facilities, lines, vessels, pumps, cables, control systems, utilities, safety systems, flares, drainage systems, power generation, electrical systems, cooling systems, Page 64 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 material selection etc., described by the design documents included within the ITT need to be designed and sized in order to ensure that ALL of these design cases can be met at the site conditions described within the design documents. The Contractor shall verify the sizing of all process equipment: columns coolers, vessels, pumps, etc. Equipment sizes shall be increased where necessary. Contracting Authority approval is required to change the size of any piece of equipment. As part of the Contractor‟s offer, he shall confirm the latest version of equipment list and shall include summary rating information (loads, dimensions, power output, etc) for each equipment item included within his bid. 5.2.1.1 Process Flow Diagrams and Utility Flow Diagrams During Detailed Engineering, at Project Completion, or after significant process design changes, the Contractor shall update and maintain the PFD‟s, UFD‟s and Heat and Mass Balance calculations to ensure consistency with P&ID‟s. Contractor shall provide Contracting Authority with the simulation calculations and the means of reviewing them (2 computer licences and simulation models). The Process and Utility diagrams shall be produced in both English and French 5.2.1.2 Piping and Instrument Diagrams The Piping and Instrument Diagrams (P&ID‟s) were developed during FEED to meet Project requirements based on existing proven designs in Algeria and are included in the FEED Package. The P&IDs have been subjected to a preliminary HAZOP during FEED. All HAZOP findings and recommendations shall be incorporated at the FEED stage. Any outstanding issues shall be closed by the Contractor subject to Contracting Authority approval. Line sizing on the P&IDs has been carried out based on the principles of the line sizing philosophy In the FEED package. The Contractor shall verify line sizes on this basis and if necessary shall increase line internal diameters when layouts and pipe runs are sufficiently well defined. The line sizing verification shall include CAFC tie-ins where applicable. Line sizes shall only be changed with Contracting Authority approval. Where additional piping specifications are required these shall be developed during detailed design subject to the approval of the Contracting Authority. Specifications have been applied to the P&IDs. The suitability of these shall be verified by the Contractor using process review, HAZOP and suitable techniques. The robustness of the piping specification shall be increased where appropriate e.g. an increase in the maximum design temperatures and pressures, or a decrease in the minimum design temperatures and pressures. The robustness of a piping specification shall only be modified with the Contracting Authority approval. The Contractor shall be responsible for updating all process and utility P&ID‟s, along with notes and details on these drawings, to meet the needs of the Project as Detailed Design information becomes available. This shall include data from equipment Suppliers and Page 65 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 interfaces with “Supplier systems” when data from the successful Supplier is available and interfaces at delivery points. These shall be developed and issued at AFC level and updated as necessary as all final information becomes available. The Contractor shall produce a register of LO/LC valves which shall list valve tag number, system description, P&ID number, line number, valve location, position in normal operation etc. The P&IDs diagrams shall be produced in both English and French. 5.2.1.3 Equipment Data Sheets Basic process data sheets / loadsheets have been developed for the majority of items of equipment during FEED to a level available for obtaining budget prices for equipment. New process and utility data sheets shall be produced and existing data sheets updated and issued in a controlled manner for approval. Due consideration shall be given to the full range of operating conditions in preparation of the data. As the process and utility design develops, the data sheets shall be re-issued as necessary. The Equipment List prepared during FEED shall be updated to include all additional equipment and design changes and be issued for approval by Contracting Authority. The equipment List shall include all attributes to be agreed with Contracting Authority. The Equipment List shall be maintained and updated as the design proceeds. 5.2.1.4 Process Design Calculations The Contractor shall prepare and submit to Contacting Authority a full set of process design calculations including, but not limited to, the following: Equipment sizing Line sizing/hydraulics (flow assurance studies for off plot systems) Flare system sizing Flare and vent radiation/dispersion Control valve sizing Relief valve sizing Blowdown valve/orifice plate sizing Equipment emission levels Relief valve/pressure safety valve sizing. Material selection study Utilities consumption These calculations shall be indexed by process system and, as discussed earlier, be stored by the Contractor with an electronic copy to the client. Hand calculations shall be scanned and stored. Page 66 / 180 Part D - Scope of Work 5.2.1.5 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Flare and Vent Systems A Flare and Blowdown Report was produced during the FEED. The Contractor shall develop this to produce a Flare, Vent and Blowdown Design Report setting out the following: Relief Loads Assessment Blowdown Loads Assessment Continuous Emission Assessment Radiation calculations and conclusions Dispersion calculations and conclusions Flare Stack Sizing Flare Tip Sizing Header and tail pipe sizing Blowdown Valve Sizing Blowdown temperature assessment Noise calculations Evaluation of Acoustic Induced Vibration Flare Drum and Flare Drum Pump Sizing Relief Valve Sizing Orifice Size sizing Bursting Disk sizing The Contractor shall review the work done during FEED and verify all technical, capacity, process, mechanical, piping, structural, etc evaluations have been adequately completed and incorporate actual Supplier data as appropriate. This shall include but not be limited to: Evaluation of relieving scenarios Capacity evaluation Comparison of design temperature requirements Acoustic Vibrational Analysis Pipe stress analysis Flare drum nozzle loading evaluation Flare structure Guy rope evaluation 5.2.1.6 Register of Safety Related Devices A register of safety related devices shall be prepared in the early stages of the Work. The register shall be maintained and updated with all Supplier data throughout the course of the Work. This shall include turbo machinery and process facilities. As part of the document a register of all “HP/LP” interfaces and pressure let down points shall be made that shall Page 67 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 quantitatively demonstrate that wherever a change in design pressure is made the lower system pressure is protected. 5.2.1.7 Instrument Protection Systems The Contractor shall carry out an analysis to determine the functional requirements and Safety Integrity Levels for all Instrument Protection Systems to ensure that the appropriate equipment and system architectures are selected. Contracting Authority‟s personnel shall participate in this exercise. This exercise shall include Instrument Protection Systems contained within equipment packages. Contractor is responsible for performing a SIL analysis and to ensure that systems are designed according to the SIL requirements that result from the analysis. Along with the SIL analysis, the Contractor shall produce a register with required testing frequencies for trips. 5.2.1.8 Shutdown Hierarchy Drawings and Cause and Effects The Contractor shall produce the Shutdown Hierarchy Drawings and Cause and Effects Drawings to cover the following: Process control logic Utility control logic ESD logic These documents form a comprehensive schedule of all I/O to the Emergency Shutdown / Plant Control System. The Contractor shall incorporate into the Cause and Effects Drawings all relevant Supplier data in order to ensure that there is a sound understanding of the control and shutdown logic throughout the facilities. The Contractor shall prepare the Drawings in such a way that it is clear where the logic is being implemented, e.g. Unit Control Panels, PCS, ESD system, F&G system. 5.2.1.9 Line lists The Contractor shall be responsible for producing a line list with all the design and operating data required by Piping. Line Lists shall be updated and issued so that they are current with the status of the P&ID‟s. 5.2.1.10 Material Safety Datasheets (MSDs) The Contractor shall prepare MSDs for all chemicals and other hazardous materials used within the facilities. This is to include but is not limited to corrosion inhibitors, molecular sieves, mercury and H2S removal chemicals, methanol, anti-foams and amine chemicals. These shall be in the French, Arabic and English Languages. 5.2.1.11 Instrument Data Sheets and Schedules The Contractor shall prepare process Instrument Data Sheets for control valves, relief valves and in-line instrument schedules for pressure, temperature, flow, level, quality and other inline instruments showing all relevant process data including alarm and trip setting. All alarm, trip and control settings shall be shown on the P&ID‟s. Page 68 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Furthermore, the Contractor shall produce and alarm and trip register combined with an alarm response manual which shall list all the facilities (supplier‟s included) trips and alarms, and include setpoints, possible cause of alarm/trip and suggested Operator action. All alarms shall be subjected to a criticality review. 5.2.1.12 Process Design Manual The Contractor shall prepare a Process Design Manual that presents a summary of the process design on a unit by unit / system by system basis. This shall be sectioned to include but not limited to: design basis, system product specification, schedule of design setting cases, any particular features or constraints arising from the design history / development, and a simple description of the process, control and shutdown systems, materials selection and key features for operations to consider. 5.2.1.13 Operating Procedures The Contractor shall produce operating procedures for CAFC CPF. The Contractor shall gather input and guidelines from Suppliers and ensure that these procedures cover start-up scenarios, normal operation, shutdowns, abnormal operation, a description of system components and their operation and maintenance. 5.2.1.14 Equipment and Bulk Numbering System All equipment, piping, instruments and cables shall have a unique and well visible in the field tag number. It is the Contractor‟s responsibility to ensure that all numbering complies with the Project Numbering Specification. These procedures will be reviewed and approved by Company; however, Company procedures will always have precedence. To be defined during KoM or in meetings after KoM that will called by Contractors. The guideline will be equal the guideline used during FEED phase; so double tagging (MLE philosophy, ENI E&P philosophy). Please note that the double tagging shall be implemented in the Engineering Lists only (e.g. Equipment List, Line List, Loop and Instrument List, etc.). No double tagging is required in drawings. About Eni Tagging see standard 20198.COO.GEN.SDS “Item Numbering”. Contractor shall do a document that explains the philosophy to transcode TAG from MLE philosophy to ENI E&P philosophy. Tag numbers shall be indicated for all functional components on Contractor, Subcontractor and Supplier design documents and drawings. It shall be Contractor‟s responsibility to change any tag numbers issued during FEED which do not meet the above requirements and update all documentation in line with the tag number philosophy. To control the status of all tag numbers issued, Contractor shall establish and maintain a Master Tag register. The register shall ensure consistency between various sources of tag Page 69 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 information and at all times during the project reflect current status of planned, installed, asbuilt, replaced and voided tags. 5.2.2 5.2.2.1 Mechanical/Equipment Description of Scope of Work The Contractor shall carry out detailed design of all mechanical (rotary and static) equipments foreseen for CAFC Plant with reference to the equipment lists and layouts in accordance with the Project Codes, standards and Philosophies and preliminary data sheets provided with the FEED Package. EPC Contractor shall be responsible for the specification, design, procurement, installation and testing of all mechanical equipment such as: 5.2.2.2 o Pressure Vessels o Columns o Tanks o Heat exchangers o Air Coolers o Compressors o Pumps o Packages o Heaters o Filters o Any other equipment Detailed Engineering The EPC Contractor shall as a minimum: • Update and review the preliminary FEED mechanical documentation (data sheets and specifications) and prepare any additional document required to enable that the tender requisitions to be prepared in a time sufficient to allow Supplier‟s data to be incorporated into the design. The updated documentation shall be issued for Contracting Authority‟s approval. • Use the preliminary specifications developed during FEED as a basis for the development of the final enquiry packages. The final specifications shall cover the scope of supply and all technical requirements. The updated and detailed specifications shall be issued to Suppliers as part of the various enquiry packages and the Suppliers shall be expected to fully comply with these requirements. The final scope of work and any possible exception or deviation to the specification shall be subject of agreement and approval by the Contracting Authority. Page 70 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 • Prepare specifications, drawings and data sheets for any identified additional equipment. • Revise specifications and data sheets to reflect the purchased equipment for purchase. Any agreed exceptions shall be embodied as an appendix to the specification or data sheet. • Manage communication with other disciplines and with Suppliers to ensure that all interfaces for equipment are agreed and correctly engineered in accordance with Project requirements and limits of supply • Obtain from the Suppliers sufficient documentation and information to enable the Project design to proceed and to confirm that the packages are manufactured, tested, preserved and packed in accordance with the applied national, international and Contracting Authority‟s codes • Conduct all necessary technical clarifications of the bids and hold clarification meetings with Suppliers in order to enable Supplier designs and the Contractor‟s design to be efficiently integrated. Contracting Authority shall be invited by Contractor to attend these meetings. • Conduct a Noise study and prepare a report including expected Noise Contour maps for each site. • Carry out Mechanical handling and accessibility study as part of the initial design, with particular reference to the requirements of the compressor packages. • Carry out an operability and maintainability study for all equipment. • Perform an Erection / Construction study for all mechanical equipment, tie in with MLE CPF and prepare a report. • Update all Technical Drawings and Documents to reflect the developments to As Built status associated with the Long Lead Items (LLI) as detailed in the Long Lead Items Purchase Order documentation and in the Long Lead Items Supplier documentation • Be responsible for the integration of the LLI machinery into the Project design, review Supplier documentation and confirm compliance with Project specifications and standards, witness testing, etc., Using Project specific data from the chosen Suppliers, confirm and modify as required layouts drawings and foundation designs and other associated documentation. • Ensure compliance with the control, instrument and electrical specifications and philosophies for machinery control systems. • Ensure that the fire and gas detection and fire protection philosophy for machinery packages is consistent with the overall Project philosophy. • Ensure that the Suppliers understand and accept the Contract P&ID‟s and issue the Suppliers P&ID‟s accordingly EPC Contractor shall include Supplier P&ID‟s in the Plant P&ID‟s set. For Pressure Vessels, Heat Exchangers and Tanks EPC Contractor shall: Page 71 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 • Check and confirm Supplier information, calculation notes and mechanical drawings of pressure vessels and tubular exchangers, showing thickness, weights and sizes, in sufficient detail to satisfy structural and piping design requirements. For compressors EPC Contractor shall: • Liaise with the civil/structural discipline to confirm that the shelters over the compressor sets are designed correctly to interface with the various Gas Turbine / Compressor parts that pass through the shelter. • Design maintenance crane arrangement under the compressor shelter. • Liaise with the compressor Suppliers with respect to process piping to achieve the following requirements: - The process piping which connects together the various compression, process and process cooler skids shall be designed, supplied and installed by the EPC Contractor. - The design, including stress calculations, dynamic response, residual pulsations (reciprocating compressors) and layout, shall be reviewed by the compressor Supplier and confirmed to be suitable. - The compressor Supplier shall have a representative on site during fit up and installation and shall confirm that the piping places does not place unacceptable loads onto the compressor and shall confirm during commissioning that the piping places no unacceptable loads onto the compressor during operation. In addition: Equipment shall be selected on the basis of acceptable Supplier design and technical integrity including life cycle costing. In all cases equipment shall be shown to be tried and tested in hot, arid desert environment, or where this is not appropriate assurance process demonstrated by the Contractor to the Contracting Authority. Equipment shall be inspected and verified as technically acceptable, performance witness tested where applicable, and delivered to the Contractor‟s construction site to meet the installation schedule. Where appropriate, the Contractor shall attend Supplier‟s works for inspection and witness tests. The Contractor shall deliver final certified equipment dossiers for all equipment in the form of a Mechanical Equipment Data Report. Contracting Authority and Algerian Inspection Agencies shall be advised of all factory acceptance tests / inspections at least two week before test. The Contractor shall ensure that the documents outlined in the Supplier Data Requirements list are in place and that the documentation is received in a timely manner to ensure input to design documentation and construction, pre-Commissioning, Mechanical Completion, final Commissioning procedures and Start-Up. Page 72 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor shall design and select Supplier equipment with a view to compatible sparing and shall whilst maintaining Technical Integrity keep equipment uniform, compact, and simple for operation, access and maintenance. The Contractor shall ensure that the Supplier has completed all instrumentation electrical and noise data sheets. Any omissions shall be addressed and are the responsibility of the Contractor. All equipment shall be adequately supported during transportation and storage, in accordance with the Specifications. Sufficient access to inspect and maintain the equipment in accordance with the Supplier‟s recommendations shall be provided on site for storage and installation. The Contractor shall ensure long-term storage preservation procedures are instigated as recommended by the Supplier, and in accordance with the Specifications. The Contractor shall make use of Criticality Assessment programmes to assess and specify the inspection, quality control and test requirements for each item ordered and shall justify those requirements for review by the Contracting Authority. The Contractor shall prepare a Mechanical Handling Study and shall identify all devices, lifting beams, cranes, anchors, and ensure that adequate access, laydown and storage areas and padeyes are provided in the facilities to meet the Contracting Authority Constructability, Installation, Operating and Maintenance criteria. As a minimum, the Contractor shall develop and provide the following documentation: Sizing, Mechanical Design Calculations notes & sketches Detailed mechanical specifications, including the scope of supply. Mechanical data sheets, equipment weights and envelopes. These shall incorporate best practise and experience of the Contractor including use of alloy materials, vessel internals, coatings etc. Noise Study and Report Machine and Auxiliary Layout Machine Characteristic Performance Curves HVAC Design specifications. Mechanical handling and access study, incorporating crane and mechanical handling device selection and location. Technical Bid tabulation evaluations. Purchase and enquiry requisitions. Supplier documentation All equipment where maintenance activities are carried out in-situ shall be provided with shelters, which enable a high degree of weather protection without hindering the maintenance activities or access. Page 73 / 180 Part D - Scope of Work 5.2.3 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Piping and Layouts The Contractor shall develop a fully detailed design of equipment layouts and all pipework and pipe supports for the Work. The design shall include, but not be limited to, the production of the following documents: Plot Plan Equipment Layout Drawings A Piping Key Plan Piping Plan Drawings (to aid construction sequencing and phasing) Piping Section Drawings (to aid construction) 3 3D CAD model (shall include all lines /4” and larger) Piping Isometrics Fabrication isometrics including maintenance/hydrotest, high / low flow point, drains / vents Piping Material Take-Offs – Preliminary, Intermediate and Final Piping Stress and Flexibility analysis criteria Piping SP Items Lists Piping SP Items Data Sheets Piping Standard Drawings for all details (sample points, flow orifice taps etc.) Utility Stations Pipe Support Standard Detail Drawings Special Pipe Support Detail Drawings Nozzle loading Data Sheets Service Support Schedule Service Support Material Take-Offs – Preliminary and Final Piping Valve and Material Specification (Piping Classes) Manual Valve data sheets Insulation and Painting Specification Fabrication and Testing Specification Nozzle Loading Specification 3D Model Design Execution Procedure Requisition packages for all piping equipment Page 74 / 180 Part D - Scope of Work 5.2.4 5.2.4.1 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Pipelines Oil and Water gathering System Contractor shall design, procure, transport, construct, hook-up live pipeline, test, commissioning and start-up the Oil, Water Supply and Water Injection flow lines and truck lines to and from CPF as detailed in various documents included with the FEED package (e.g. P&IDs, SLDs, instrument drawings, etc) that shall form part Annex I – “Technical” of the Contract. This includes all Intermediate Field Manifolds, anchor blocks and all ancillary works (cathodic protection instrumentation, metering and telecommunication system, etc…) 5.2.4.2 Pipeline Engineering In detail Contractor shall perform any complementary engineering works in order to satisfy the requirements of the Project in accordance with the FEED documentation. In particular EPC Contractor shall: -perform topographical survey and staking out of pipeline routes -perform soil investigation survey and produce geotechnical report -perform soil resistivity survey and report -issue typical pipeline installation drawings, as deemed necessary for the project -issue of General route maps -issue of Alignment sheets drawings, updated with all the design information‟s -issue of Crossings detail drawings -issue of materials takes off -perform stress analysis of the pipelines, including upheaval buckling verification, and plant approaches (off set or anchor blocks solution) -issue of technical pipeline specifications 5.2.4.3 Tie-ins Design Tie-ins are foreseen to integrate CAFC oil facilities with MLE NGL plant & utilities. Contractor has to run TIE-IN piping between CAFC and MLE plants. These are consisting of CAFC product rundown line, future export equipments and utility systems. All the basic engineering to run the interface piping has been completed. It is also included with Bill of materials. Contractor will procure, install and commission piping and other electrical and instrumentation tie-ins from the MLE to CAFC. Contractor is responsible for the planning and preparation of the Works to ensure this work is carried out safely in the most effective way, considering possible SIMOPS operation with a live NGL plant. MLE EPC CONTRACTOR has identified the TIE-IN location and produced Page 75 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 isometrics for piping with MTO. CONTRACTOR has to evaluate them and submit a plan for possible TIE-IN. 5.2.5 5.2.5.1 Operations and Maintenance Review The Contractor shall organise, at an appropriate time in the design development, but prior to full design “freeze”, an Operations and Maintenance review to consider, unit by unit, Operational aspects of the design. This shall include but is not limited to site access/egress, valve access, provision for maintenance and inspection, catalyst/packing charging, unchanging etc. Use of the 3D integrated surface design model shall be used for this review and shall supplant necessity for 2D drawings traditionally used for this purpose. Findings from the review shall be addressed by the Contractor and where can be reasonably judged necessary for the safe and efficient conduct of operation, implemented by the Contractor. 5.2.5.2 Engineering CONTRACTOR shall submit a maintenance proposal to cover CAFC Plant operation phase. Maintenance Engineering shall be in compliance with ENI Standards about Reliability Centered Maintenance (RCM) [22011.MAN.GEN.RWP]. The requirements are deeply described in Annex XII “CAFC plant Operability and Maintainability requirements for EPC Contractors”. This chapter provides technical and functional general requirements to be observed by CONTRACTOR in all the activities related to the preparation of the technical documents and management during the overall supply. In order to assure the best conditions for maintenance and in order to ensure the goals of the efficiency, reliability, availability and HSE security level of the whole asset, CONTRACTOR shall: Perform a complete RCM analysis Prepare the maintenance and inspection plans and procedures for the whole asset. CONTRACTOR shall develop the described tasks in collaboration with COMPANY foreseeing progress meetings at least once a month. CONTRACTOR shall issue a preliminary O&M activities schedule with the EPC Bid submittal and a detailed schedule within the first progress meeting. 5.2.5.3 RCM analysis CONTRACTOR shall perform a RCM analysis in accordance to Company Standard [22010.MAN.GEN.SDS rev 01 “Guideline for RCM Implementation”] and [22011.MAN.GEN.RWP rev 01 “RCM Handbook”]. RAM analysis will be the basis of the Page 76 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 maintenance strategies selection as well as the Maintenance plans development. Reliability data collection, as starting point for the RAM analysis, shall be compliant with Annex XII “CAFC plant Operability and Maintainability requirements for EPC Contractors”. The list of main activities that are required is the following: Master Equipment List (MEL) for CMMS population Reliability Data Collection Bill of Materials (BOM) for CMMS population Spare Parts Interchangeability Record (SPIR) Lubricants, consumables and bulk materials lists RAMS/RCM Analysis Failure Mode and Effect Analysis (FMEA) Maintainability analysis (MA) Criticality analysis (CA) Reliability centred maintenance (RCM) Risk based inspection (RBI) Availability analysis (AA) Availability analysis shall take as reference the RAM study performed during the FEED phase, developing all pending aspects pointed out by COMPANY as deeply described in par. 5.7.9.4 of Annex XII “CAFC plant Operability and Maintainability requirements for EPC Contractors”. 5.2.5.4 Maintenance Plans and Procedures CONTRACTOR is responsible to collect from Sub-CONTRACTORS all the information and documentation related to maintenance (Maintenance and inspection plans, maintenance procedure etc…). CONTRACTOR shall prepare a complete set of maintenance and inspection plans for the Scope of supply, completed with all the information requested by COMPANY in document TBA “CAFC plant Operability and Maintainability requirements for EPC Contractors”. The aim is to keep the installation to the optimum preservation status and to guarantee the optimal performance and HSE security level throughout lifetime (starting from pre-commissioning to the decommissioning). Any change or modification to the maintenance plan which may have a detrimental effect on the system shall be subject to COMPANY Approval. COMPANY shall be notified prior to including such modifications or changes in the plan. Page 77 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 In addition CONTRACTOR shall prepare for the whole asset a full set of Maintenance and inspection procedures, starting from the information collected from the SUB CONTRACTORS. Maintenance and inspection procedures should as a minimum address the instructions to perform the following activities: Routine preventative maintenance Repair or replacement of failed minor equipment Repair of failed major equipment Refurbishment after a period of field operation Paint/surface coating field repair Fault finding Preservation\Maintenance of spare parts and sub-assemblies. Maintenance and inspection plans and procedures have to be delivered at least 3 months prior to pre-commissioning phase, in an electronic format and template approved by COMPANY and ready to feed the chosen CMMS. 5.2.6 5.2.6.2 Instrument and Controls Systems Description of Scope of Work Scope of this Work is the design, procurement, installation and testing of: - all the field instrumentation necessary to properly control CAFC plant; - The Integrated Control and Safety System (ICSS). - Instrumentation cables The ICSS equipment shall be installed in the CER in the electrical substation building in CAFC premises and in MLE CCR; these two rooms shall also cater for the space needed for future expansion of the hardware (both cabinets and operator stations). The ICSS shall comprise, but not limited to: - Distributed Control System (DCS) for the control of process and utilities, providing adequate information for the operators; this will include also the information available from third party systems control packages to be integrated in the DCS as described in the FEED documents in Annex I – “Technical” of the Contract; Page 78 / 180 Part D - Scope of Work - Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Emergency Shutdown System (ESD) for the control of the plant in upset conditions, protecting personnel, the environment, the plant and the equipment; - Fire and Gas System (F&G) to protect from fire and gas hazards, providing alarms and activating protection systems; - Remote control of Wellheads and Intermediate Manifolds through the SCADA system; - Operator interfaces to the above mentioned systems, such as operator and engineering stations, graphic pages, alarm management system, auxiliary panels etc., fully compliant with equipment and philosophies provided; - Extension of the synoptic display of MLE plant in CCR. Provision shall be made for all the abovementioned aspects for future expansion, in terms of space, hardware and software capabilities. Moreover, Contractor shall be responsible for the integration of all CAFC control systems with MLE ones, both in terms of hardware connections and behaviour, assuring ease of operation of the two plants from the same team of operators. 5.2.6.3 Detail Engineering The Contractor shall design all instrumentation and control systems required in order to safely and effectively control and monitor all facilities. During the Work the information shall all be available in the Contractor‟s offices where Contracting Authority‟s PMT is located. The Contractor shall develop all principal ICSS documents including, but not limited to, the following: - Cause and Effect Diagrams for ESD, F&G and control systems. These shall define logic functions within the main control system, process safety shutdown, and fire and gas systems. The cause and effects diagram developed during FEED shall be updated to reflect any development in detailed design e.g. as a result of the detailed design HAZOP (Contractor‟s and Supplier‟s) and input from all the Supplier data (i.e. Compressor C&E). Furthermore the Contractor shall organise a formal review of the Cause and Effects with the Contracting Authority once detailed design is confirmed and all data from the Suppliers is received. - Updated control system block diagrams; - Packaged equipment block diagrams; - Detailed process control descriptions and control narratives for every complex control loop; - Logic Diagrams/sequences for all equipment identified on P&IDs as well as electrical and mechanical packages interfaces, showing all the inputs (instruments/F&G/various equipment) with relevant tags, the functional logics to be implemented inside the automation systems (DSC, ESD/F&G, SCADA/RTUs) with relevant sequence numbering, and the outputs (instruments/F&G/various equipment, control room) with relevant tags Page 79 / 180 Part D - Scope of Work - Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Man-machine graphics interface displays. These displays, with hard copy printouts shall be produced in conjunction with appropriate personnel appointed by the Contracting Authority who shall be a specialist in the facility operations; - CCR and CER layouts and furniture specification; - Layouts of the cabinets for all control system components; - Functional design specification for all systems The Contractor shall develop all principal documents relative to instrumentation including, but not limited to, the following: - Supply specifications and Data Sheets (TDS, IDS, DDS) for all instrumentation and control equipment, items and materials; - A complete Instrument list; - Input /Output List for each system; - Provide a database (that can be integrated in the I/O list) capturing all key information relating to instrumentation and control systems. This database shall contain, as a minimum, the following information for packaged and non packaged instrumentation: o Plant Reference o Unit ID o Loop ID o Unique Tag o Service Description o Instrument Type o P&ID No. o System Connected to DCS, ESD or FGS o Signal Type Analogue or Digital o Signed mode input or output o Protection EExd or EExi o Engineering units o Range o Alarm Set Points HH, H, L and LL o Hook-up document number o Loop Drawing document number o Manufacturer o Model o P.O. Number - Cable specification and list; - Routing drawings for multi cables and multi tubes showing main transits, junction boxes, and field cabinets; - Loose instrument and junction boxes termination drawings; Page 80 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 - Junction box schedule and specification; - Instrumentation erection specification; - Sketches for instrument mounting (primary process connections, pneumatic/hydraulic secondary connections, electrical secondary connections); - Instrument mounting details/hook-up; - Instrument bulk material take-off, broken down per category of equipment and materials; - Plot plans to locate the tagged field instrumentation (electrical / pneumatic / hydraulic /etc.) - Loop Diagrams; - Calculation sheets for flanges, orifices flow elements, control valves, safety valves, choke valves, etc… - Cable and Cable Trays routing in the Instrument Equipment Room (building by building) and Control Room; - Terminal Blocks drawings (instruments/junction boxes/F&G/marshalling cabinets/among automation cabinets), - Instrument air usage calculation; - HVAC heat load calculations; - Power consumption (including UPS loads) calculations; - Operating manual for each system; - Maintenance manual for each system; - Bills of material; - Details of the serial interfaces (Protocol, Signal Map, etc ) chosen to allow the communication between different packages & ICSS Suppliers make and model number shall be clear in Supplier documentation for the tagged equipment items. The Contractor shall be responsible to prepare, for each different item, the complete technical documentation package to allow: - ITT to cater the different items - Technical Evaluation of the offers received - Contract Award for Instrumentation Items (by preparing the revision released “for order” for the technical documentation package) All the forms to be used to prepare the various documents (TDS, IDS, DDS, etc) shall be submitted to Company approval Page 81 / 180 Part D - Scope of Work 5.2.7 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 IT and Telecommunications Systems Design 5.2.7.1 Description of Scope of Work Permanent systems Contractor shall be responsible for the specification, design, procurement, installation and testing (including end-to-end testing) of permanent telecommunication systems and provision of telecommunication services; Contractor shall also be responsible of all the necessary actions towards Third Parties, such as PTT; ARPT etc. to insure the compliance of the installed systems with local regulations. The telecommunication systems shall comprise, but not limited to, the following: - Optical fibre backbone system (SDH) for the connection with remote sites and relevant interfaces to other systems; - Public Alert General Address system (PAGA); - Public Address Branching Exchange (PABX); - TETRA radio system; - CCTV and IDS at CPF and remote sites; - Extension of the WAN/LAN networks of MLE whenever required. Due to the strong interdependence between CAFC and MLE, Contractor shall maximize the compatibility between the telecommunication systems of the two plants, including, wherever possible, the use of shared equipment. Contractor shall also be responsible of the integration of telecommunication systems between the two plants, including testing of the interconnections. Temporary systems The Contractor shall be responsible for providing their own general business IT systems for use during the term of the Contract. This Work includes the specification, design, procurement, installation and testing of temporary Telecommunication systems and services necessary to support EPC activities, and shall comprise of, but not to be limited to, the following: - Telecommunications systems and services taken from the range required for permanent operations, for use by the Contractor, Contracting Authority and other contractors as appropriate. Telecommunications facilities provided for Liaison shall include voice and data needs at the MLE locations, Hassi Messaoud and Algiers and elsewhere as required for the execution of the project. - Office telephones (with international access and access to Contracting Authority telephone networks), for Contracting Authority personnel at each construction site. - Installation of Vehicle Radios into Contracting Authority Vehicles used during the construction phase of the Project. - Vehicle tracking facilities using GPS (Global Positioning Systems) - Hand -held GPS (Global Positioning Systems) receivers Page 82 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 It is the responsibility of the Contractor to obtain all licences and consents required for the Work, including Fibre Optic communications, radio, UHF etc. This work is further defined in, but is not limited by scope detailed in the FEED Package. 5.2.7.2 Detailed engineering The Contractor shall design all the telecommunication systems required in order to run the facilities in a safe and efficient manner. During the Work the information shall all be available in the Contractor‟s offices where Contracting Authority‟s PMT is located. Telecommunication systems associated with security and emergency response shall need to be operational prior to the start-up of construction activities. Contractor shall update the following documentation according to the possible changes appeared during detail engineering: - Telecommunication system block diagram; - Block diagrams for all subsystems; - Site survey/frequency reports. The Contractor shall develop all Telecommunications calculations, specifications, data sheets and inventories including, but not limited to, the following: - Specification for each telecommunication systems and equipment, including TDS, IDS and DDS; - Detailed design of the sub systems; - Equipment list, including: o Equipment list for all systems; o Material take offs; o Spare parts list; o Test and maintenance equipment list; - Equipment functional design specification of each system; - Telecommunications asset ; - TETRA Radio field coverage and interference calculations and design; - Calculation notes, including: o Optical loss budget, optical power budget, etc. o Link performance calculations o Equipment availability/reliability calculations - PAGA coverage calculations; - Cable specification and list for all telecommunication systems; - I/O list of all systems; - Operating manual for each system; - Maintenance manual for each system; Page 83 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 - Heat dissipation estimate for all the equipment; - Power consumption estimate for all the equipment; - Test documentation; - Radio licence technical submissions; - Radio licence applications in accordance with Algerian PTT requirements including but not limited to ARPT; - Technical bid tabulation evaluation. The Contractor shall develop detailed Telecommunications and main computer server Drawings which shall contain all Supplier data. These shall include, but not be limited to, the following: - Single line Drawings; - Schematic diagrams; - Room and Enclosure floor and cabinet layouts; - Cabinet layouts, including termination strips, equipment fascia details and cable trays; - General arrangements, including dimensions, fixing detail and utility requirement; - Power supply and earth single line diagrams; - Enclosure and cabinet wiring diagrams; - Junction box termination details; - Equipment termination details; - Equipment layout drawings; - Equipment wiring drawings; - List of radio frequencies; - Acceptance test methodology and test procedure; - Recommended spares lists for both installation and maintenance; - Register of spares for equipment; - Type approval and certifying authority approval dossier; The Contractor shall be responsible to prepare, for each different item, the complete technical documentation package to allow: - ITT to cater the different items - Technical Evaluation of the offers received - Contract Award for Instrumentation Items (by preparing the revision released “for order” for the technical documentation package) All the forms to be used to prepare the various documents (TDS, IDS, DDS, etc) shall be submitted to Company approval The Contractor is responsible for the preparation and management of all PTT (ARPT) license applications necessary for the Work. Page 84 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor shall ensure that adequate spare capacity is included for the future scope of the Project and that utilising this capacity can be achieved without disruption to the running system. 5.2.8 5.2.8.1 Electrical and Power Systems Engineering Description of Scope of Work Electrical power to CAFC shall be provided from the MLE substation through 60 kV GIS (Gas Insulated Switchgear). The main power for MLE plant comes from MLN (Menzel Ledjment North) substation (220/60 kV) by means of 60 kV overhead lines. The Contractor shall review the calculations and studies carried out during FEED (e.g. Short circuit, Load flow, etc.). These documents shall be reviewed and updated during detailed design. The Contractor shall carry out protection relay co-ordination studies, including relay setting schedules in order to guarantee the stability of the electrical distribution system of CAFC vs MLE also during the start up of the larger electric motors without any impact of the MLE plant to COMPANY satisfaction. The overall Single Line Diagrams, already developed to a considerable degree of completeness during FEED, shall be the basis for further detailed design to be performed by the Contractor. The sizing of the Emergency Generators, Switchboards and Transformers etc. has been based on input from the Load Lists which in turn have been developed from the P&IDs, vendor data and other project information. The Contractor shall confirm that the overall design intent can be achieved. All equipment and cable sizing shall be verified. Any change in sizing, loading or capacities requires approval from the Contracting Authority. Fault levels shall be calculated to ensure that they are within acceptable levels. The SLDs provided within the FEED package for the various Switchboards and Panels shall be updated and developed as necessary during detailed design. 5.2.8.2 Detailed Engineering The Contractor shall take responsibility for the design of all electrical systems including, but not limited to, the following: Electrical load list for normal grid supply and emergency generators, UPS and DC Power. Selection of power equipment (transformers, breakers, buses, …) to meet the system load requirements Cable schedule for all lighting, electrical control and power cables. Earthing may be by earth schedule / location plan. Electrical equipment lists. Load management system. Page 85 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 UPS and DC supply requirements. Inter-connection cable schematic Drawings. Register of all electrical equipment and devices for installation in hazardous areas, including a copy of / or dossier of hazardous certification for all such equipment. Detailed single line diagrams for all areas, including HV/LV distribution, Schedule of DC power and UPS loads. Layout, wiring and schematic Drawings for main and other substations. Layout, wiring and schematic Drawings for emergency power generation. Detailed layout Drawings showing the proposed distribution boards, power generation and electrical distribution for all sites including construction sites. Electrical layouts for power, control, lighting, grounding and auxiliary systems for each area. Motor Control Centre, switchgear and power control equipment layouts. Update of hazardous area electrical classification drawings prepared during FEED. Detailed interconnect diagrams for electrical devices, control panels, marshalling and junction boxes. Lighting and small power distribution board schedules (AC/DC/UPS). This includes details of the automatic changeover of supply in the redundant UPS system and DC Power Units. Typical electrical installation details required to perform all electrical work including, but not limited to, power, control, lighting, and earthing details. HV and LV switchgear control schematics. HV and LV switchgear arrangement Drawings. HV/LV switchboard layouts including base frame and switchroom cable duct details. Layout Drawings showing all electrical equipment. Site General Alarm and Public Address System. Security Systems design and layouts. Cable ladder/tray and cable trench layouts for electrical, instrumentation, F & G and communications cables. This requirement includes the cross sectional views of all such cable ladders, tray and cable trenches detailing the cable installation. Electrical drawing legend. Standard installation Drawings. Page 86 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Powerline (including structures) and tie-ins between CAFC and MLE Technical Bid tabulation evaluations. Purchase requisitions. Any documents not listed above but which are deemed necessary by the Contracting Authority to properly define, build and operate a complete electrical system. The Contractor shall determine the most appropriate area for all earthing installations for all sites to endorse the design, and to demonstrate the performance function of the site installation. As a minimum, the Contractor shall perform the following design functions and calculations, incorporating applicable Supplier information, or areas of the Work that are sub-contracted, such as accommodation, packaged switchrooms etc. Update the FEED electrical load list as the design develops, with particular regard to supplier information. Short circuit calculations for all switchboards and feeder cables, covering possible combinations of generators connected to the power system. Protective relay co-ordination study with required settings. Load Management System Transient Stability Study Sizing calculations for Emergency Generators, Transformers, Battery Banks, Battery Chargers, UPS, Circuit breakers and contactors. Design of power requirements and interconnecting supplies to complete the construction and Mechanical Completion phase using a temporary generator (not the facility emergency generator). Voltage drop calculations for complete electrical system including individual cables. Lighting level calculations for normal and emergency lighting in all areas. Security system design and facilities layout Site General alarm and Public Address System 5.2.9 Corrosion Protection The Contractor shall develop the design of the corrosion protection systems including coating/painting, cathodic protection system and chemical injection. All steel, pipework and equipment shall be supplied with protective systems (coating and painting) prepared and applied strictly in accordance with the standards and procedures set Page 87 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 down in the FEED Package. Any damage to protective coatings/paintings, which arises during fabrication, equipment installation and/or Commissioning shall be repaired by the Contractor. The Contractor shall develop the design of the cathodic protection system and the chemical injection system, where foreseen, in accordance with the requirements of the FEED Package and relevant company standards. Any damage and/or malfunctioning arising during installation and/or commissioning of both the systems shall be properly addressed and resolved by the Contractor. 5.2.10 Civil 5.2.10.1 5.2.10.1.1 Description of Scope of Work Civil Works The Work includes the design, materials procurement and execution of Civil Works and any further Site Preparation Works in addition to those provided by Contracting Authority. These works shall comprise, but are not to be limited to: Site clearing, stripping and grading beyond preliminary civils Site bulk earthworks beyond preliminary civils Flowlines and Trunklines Installation Road works Underground cable and piping trenches Telecommunication and Power cables installation over the whole gathering system Pipe sleepers and pipe racks Concrete foundations Foundations and retaining walls for Off spec oil Storage Tank Concrete Paving Bridge Culverts and Duct Banks Control of water in way of foundations; provide ground protection against ingress of rainwater; provide drainage suitable for extreme runoff conditions and provide subsoil isolation of strata under bearing pressure against ingress of groundwater Electrical Earthing Sewage Collection, Treatment and Disposal System for CPF, Leach Fields Evaporation Ponds Page 88 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Foundations and Anchors for Radio Antennae Self Supporting Towers Soil compacting Piling Fencing systems Provision of Concrete Batching Plant 5.2.10.1.2 Temporary Installation The Contractor shall plan, provide, mobilise, maintain, operate and, subsequently, demobilise all Temporary Installations required in connection with the Work. The Contractor shall be responsible for the provision of temporary facilities to support construction activities including but not limited to the following: (i) Construction labour camp to be located at a designated location close to the MLE CPF. The Contractor shall be responsible for provision of all facilities at this location to suit his anticipated site labour force. (ii) Lay-down and construction warehousing to be located at a designated location adjacent north part of the CPF. The Contractor shall be responsible for provision of all facilities at this location to suit his anticipated site labour force and material handling requirements. (iii) Construction offices to be located at a designated location agreed with the Contracting Authority. The Contractor shall be responsible for provision of all facilities at this location to suit his anticipated site labour force. (iv) On-site offices, changing rooms, store etc. as deemed necessary by the Contractor for the execution of the Work on CPF site and at off-site locations to support offsites work. Execute the project with No Accidents, No Harm to People and No Damage to the Environment. 5.2.10.1.3 Structural Systems The Work includes the design, procurement and construction of Structural Systems at the sites. The structural systems shall comprise of, but are not to be limited to, the following: Pipe Racks and sleepers Equipment Support Structures Gantry Crane Supports and Runway Beams Cable Tray Supports and major Pipe Supports Platforms, Ladders and Access Ways Flare System Supports and Anchors (as required) 5.2.10.1.4 Power Supply to temporary facilities Page 89 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Power for the temporary camp and offices shall be supplied by the Contractor. Contractor shall design, install, fuel and maintain generation and distribution network to support these facilities. This power supply shall be independent of any provided to assist Commissioning or Start-up activities. 5.2.10.1.5 Water Supply Contracting Authority shall provide access to raw water. Contractor shall check compatibility of the water with requirements of the work mainly concrete .Contractor may execute additional analysis to confirm quality of the water. Contractor shall run temporary lines as required from wells to camps and office locations as required for the construction works including but not limited to: Cement batch plant Flushing and hydrotests Accommodation The Contractor shall develop and provide to Contracting Authority water demand schedules and updated every two months as follows: Monthly average and daily peak requirements during the contract period Contractor shall supply a suitably sized water treatment plant at each location. 5.2.10.1.6 Liquid Effluent Disposal Contractor shall install temporary evaporation ponds complete with security fencing, at each camp location and worksites as required. The ground shall be reinstated by Contractor at demobilisation Contractor shall design and provide sewage collection and treatment units (STUs) at each camp location Sewage Treatment Units and evaporation pond sizes are to be confirmed by Contractor for the duty defined by peak personnel numbers and process requirements. The Contractor Camp evaporation pond shall be sized for peak Contractor headcount plus hydrotest water disposal, if appropriate. All liquid effluents, with the exception of clean rain water run-off shall be disposed of in the evaporation ponds. Re-injection of fluids is not acceptable. It is envisaged that clean rain water run-off from plant areas, following the first 15 minutes of rain fall can be routed to a suitable soak-away remote from the plant. This approach and the sizing basis for the Evaporation ponds must comply with Contracting Authority‟s Waste Management Philosophy and relevant local permitting regulations. As hydrotest fluids can potentially contain hazardous chemicals, the Contractor shall provide a plan for disposal of any hydrotest fluids for approval by Contracting Authority. Plan shall be agreed with Contracting Authority before release or batching of any fluids. 5.2.10.1.7 Solid Waste Disposal Page 90 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Contractor shall provide a temporary solid waste incineration facility for Contractor camps. Incinerator shall comply with all local authority regulations and be of sufficient capacity. Contractor shall incinerate solid waste before landfill to minimise volume. Waste unsuitable for such treatment shall be recycled. Contractor shall submit a waste management plan during the tendering phase to demonstrate how to address these issues. Contractor and his subcontractors shall comply with ESHIA findings and recommendations. Each site used by Contractor and subcontractors must be re-instated to its original state. 5.2.10.1.8 Site Access The Contractor shall upgrade and add to the existing field roads as required to allow free movement of bulk materials and equipment at site. Any damage caused during construction shall be repaired by the Contractor prior to demobilisation. The construction sites shall not be accessible except via a strict control system. The construction sites shall require new and dedicated access roads. These roads shall be designed to standards provided within the FEED package. 5.2.10.1.9 Roads The Contractor shall construct concrete, piste and/or tarmac roads to meet the requirements as described within the FEED package in Annex I – “Technical” of the Contract. Road construction shall include design and construction of wadi crossings and pipe/services as required. CONTRACTOR shall manage site construction traffic to minimise damage to the desert surface with as few new vehicle tracks as possible. 5.2.10.2 Detailed Engineering 5.2.10.2.1 Civil Engineering Contracting Authority shall perform early site preparation, earth moving and sand levelling, civils preparation including gypsum layer for CPF. Contractor shall endorse and use the as-is final state of the early site preparation as the basis for execution of the Project. Any further site preparation required for the requirements of the Project as Contractor‟s responsibility and are part of the Work. The civils design shall be in accordance with the requirements of Civil and Structural Design Criteria –in the FEED Package. The Contractor shall take the responsibility for the design of all civil aspects of the Work, including, but not limited to, the following: Undertake all necessary survey work over all sites included in the Work, prepare survey plans and establish permanent survey markers on the sites. Undertake all necessary geotechnical investigations over all sites included in the Work using suitably qualified and experienced geotechnical engineers and prepare a geotechnical report. The geotechnical report shall include all necessary drilling, test pit excavation and soil testing and shall include all required design parameters for the structures proposed. Page 91 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Undertake an assessment of the catchment areas contributing to storm-water flows from and across the sites. Select suitable locations for all facilities considering storm-water flows and local topography. Preparation of design Drawings and construction Specifications for all site roads, hardstands, laydown areas, stormwater and firewater drainage systems and all site access roads. Preparation of design Drawings, construction and equipment Specifications for all sewage systems, including sewage mains, treatment equipment and effluent systems. Preparation of design Drawings and construction Specifications for all underground services including service trenches, ducts and associated works. Preparation of design Drawings and construction Specifications for landscaping of the sites. Preparation of design Drawings and construction Specifications for foundations for all equipment, storage tanks, structures and buildings. Undertake all survey, geotechnical and design work required for the preparation of design Drawings and materials and construction Specifications for the installation of any construction/access roads. Preparation of materials Specifications for the supply of all civil materials. Preparation of design Drawings and construction Specifications for all perimeter fencing and other aspects to provide security for the Facilities. Preparation of bills of quantities for import and export materials. Preparation of documentation and calculations for building regulation / other approval by appropriate Algerian agencies. Although data shall be made available to the Contractor for topographical and geotechnical surveys already undertaken in the areas adjacent to the facilities, it shall be the Contractor‟s responsibility to verify or otherwise all of the data contained in the reports and acquire additional information through further surveys if required.. Contracting Authority take no responsibility for any errors or omissions in these reports and for any changes that may have taken place since the surveys were undertaken. 5.2.10.2.2 Structural Engineering The Contractor shall carry out the detailed design of all structures required for the Work. The structural design shall be in accordance with the requirements of Civil and Structural Design Criteria –in the FEED Package. The detailed design shall include, but not be limited to the following: Page 92 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Operational, erection and accidental load analyses / design of all steelwork and concrete works verifying acceptability of all members, joints and foundations. Analysis and calculations to support the Contractor‟s construction configurations and assembly methods. Design of lifting attachments, installation aids, temporary supports, and temporary transportation steel. Design and specification of access ladders, platforms, walkways and associated handrails and guards. A bill of quantities for all steelwork, concrete, reinforcement and associated formwork produced in sufficient time to avoid delays to construction arising from material shortages. Clearly dimensioned steel design Drawings enabling efficient development of cutting and fabrication Drawings and procedures. Clearly dimensioned concrete design Drawings enabling efficient placement of formwork, reinforcement and pouring of concrete. Structural general arrangements and details for development of detailed design by other disciplines. use in Passive fire protection Drawings showing extent of same on steelwork. Design and specification of crane monorails, structural steel for maintenance activities and major pipe supports. The Contractor shall deliver a structural design report including all analyses and calculations used to justify the design. 5.2.10.2.3 Building and Architectural Design The Contractor shall carry out the detailed design, including architectural design, of all buildings included in the Work. The buildings and architectural design shall be in accordance with the documents provided in the FEED Package. The detailed design shall include, but not be limited to the following: Clearly dimensioned general arrangement building and architectural Drawings enabling efficient development of all associated discipline Drawings. Incorporate designs and calculations by other disciplines, e.g. HVAC, telecommunications, controls, structural, building services, drainage and electrical. Incorporate computer floor and transit frame design for the Control Room and the Equipment Room. A bill of quantities for all architectural materials, fittings and furnishings produced in sufficient time to avoid delays to construction arising from material shortages. Page 93 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Documentation for building services in accordance with the relevant codes and standards as defined in the FEED Package documentation. Provide input into bid packages for CER. Architectural design of all buildings shall be by suitably qualified architects. The design shall take into account decor requirements, the site environmental conditions, local building practices and hazards associated with the site such as noise, fire and blast. . The Contractor shall deliver a building and architectural design report including all calculations used to justify the design. 5.2.10.2.4 HVAC Systems Design The Contractor shall design or sub-Contract the HVAC Systems for all buildings and rooms requiring controlled environments in order to meet reliability and availability requirements specified. The HVAC design shall be undertaken in accordance with the codes, standards and requirements detailed in the FEED Package. All HVAC systems shall be designed based on an ambient design temperature of 55 deg C. The HVAC design shall use a combination of pressurised, non-pressurised and naturally ventilated systems, with safety, equipment requirements and comfort of personnel foremost in the design considerations. The design shall minimise space requirements and remain consistent with good maintenance access and safety performance. The availability of the systems shall be a prime objective in the design. Appropriate redundancy and spare holding / commonality shall be achieved for this critical plant. The Contractor shall produce all HVAC systems Ducting and Instrument Diagrams, Specifications, Data Sheets, calculations and studies. Where appropriate, the HVAC system design shall be integrated with that of the F&G System and the Control & Monitoring System. Air conditioning units shall be provided with due consideration of the following: Where rooms are air conditioned by dedicated units, split units shall be used for low noise output The number of alternative equipment types and suppliers shall be minimised for ease of maintenance Condensers shall be adequately shaded to improve performance and operations life Units shall be suitable for continuous operation at the extreme local design temperatures 5.2.11 HSE Health, Safety and Environmental Systems and associated equipment shall be designed and installed to protect personnel health and safety, facilities integrity and the environment. The systems shall be in the spirit of and meet Contracting Authority HSE MS Requirements in Annex XI – Health, Safety and Environment of the Contract and HSE Minimum Requirements (See section 6). Page 94 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 5.2.11.1 Description of Scope of Work 5.2.11.1.1 Safety Systems This Work includes the design, procurement, installation and testing of Safety Systems at the CAFC sites. The Work shall comprise, but not to be limited to, the following: Fixed fire extinguishing systems. Portable extinguishers for facilities areas and buildings. Fire and gas detection systems. Manual alarm call points throughout the plant. Passive fire protection systems. Safety signs throughout the sites. Safety equipment throughout the sites.. The philosophies for the safety systems shall be consistent with the philosophies provided in the FEED Package. The Contractor shall develop the detailed requirements for approval of the Contracting Authority. 5.2.11.1.2 Environmental Systems This Work includes the design, procurement, construction / installation and commissioning of temporary Environmental Systems at the sites. The Work shall comprise, but not to be limited to, the following: Temporary landfill site, lined for hazardous waste. Removal of construction waste to appropriate facilities meeting Contracting Authority HSE Requirements, specifically within ISO 14001:2004 requirements. Sewage and effluent treatment facilities at sites suitable for all construction activities (including Subcontractors) (where located with temporary camps). Domestic water facilities at sites. Incineration facilities at sites. Crushing facilities at sites. Waste collection vehicles and front loaders at sites. Dust suppression vehicles at sites. Environmental testing / measuring equipment at sites. Waste storage bins at sites. The philosophies for the waste management are given in the FEED Package in Annex I – “Technical” of the Contract. However, the overall Waste Management Philosophy for Algeria is being revised. The Contractor shall develop the detailed requirements for approval of the Contracting Authority. Page 95 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor shall prepare, implement and monitor a Contracting Authority approved environmental management plan for the construction and commissioning of the Work. This plan shall also identify standards and procedures for water handling, waste management, waste material disposal, solvent disposal, etc. The Contractor shall maintain the locations in a clean and tidy condition at all times. For control rooms, instrument rooms and other areas where electronic equipment is installed, suitable working practices and temporary equipment shall be installed to maintain the environment as dust free. 5.2.11.1.3 Health Facilities The Contractor shall develop and implement a Health and Hygiene Management Plan in accordance with the HSE Requirements in Annex XI – “Health, Safety and Environmental” of the Contract. This plan, inclusive of all relevant procedures, shall be reviewed by the Contracting Authority and finalized by the Contractor with all comments incorporated at least four (4) weeks before site mobilisation. This Work includes the supply of Medical and Health Facilities and shall comprise of, but not to be limited to, the following: Temporary Health Facilities (including ambulance) to provide medical support during construction activities (including first aid room) at each site. First Aid Room at CPF and any construction site. The fully equipped first aid centres shall be staffed with qualified medical personnel, with facilities and procedures for handling and evacuating large scale casualties. All Health Facilities, including final inventories and layouts shall be agreed with the Contracting Authority‟s Occupational Health personnel. The Temporary Health Facilities shall be accessible to all Contractor and Subcontractor personnel, and in the case of emergency, Contracting Authority‟s personnel. 5.2.11.2 Safety and Environmental Engineering The Contractor shall carry out the detailed design of all Safety and Environmental systems included in the Work. The Contractor shall be responsible for ensuring that the design of Work meets the Contracting Authority stated goals for Safety, Environment, Emergency Response and Emergency systems, as well as the CAFC Project HSE Requirements in Annex XI – “Health, Safety and Environment” of the Contract. Compliance with the Environment Performance Standards and the Performance Standards for Safety Critical Items is mandatory. The Contractor shall develop and provide all of the principal safety related calculations and documentation as defined in the Contract deliverable list, including but not limited to, the following: Fire Water P&ID‟s. Page 96 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Fire Protection System design (including calculations). Fire Water Demand Calculation and Hydraulic analysis. Hazardous Area Classification Layout and Schedule. Active Fire Protection Layouts. Passive Fire Protection Layouts. Fire and Gas detection layouts. Safety Signs and Safety Equipment Layouts. Data Sheets for Fire Protection and Safety Systems. Safety Equipment Schedules and Technical Specification.. Safety Sign Schedules and Technical Specification. Fire Protection Specification.. Equipment Schedules and Technical Fire and Gas Cause and Effects Flare Radiation and Gas Dispersion Calculations. QRA Study. FERA and Blast Overpressure Studies. Noise and Vibration Study. Air Emission Study. HSE Case. The Contractor shall develop and provide all of the principal environmental related documentation, including but not limited to, the following: Equipment data sheets. Equipment schedules. 5.2.12 Lifecycle Cost Assessment Equipment and packages shall be selected upon the following basis: Proven equipment on similar conditions & environment Demonstrated reliability in a hot desert remote environment Lowest lifecycle cost Particular attention and demonstration of robustness to the extremely hot, arid environment prone to sand storm/ingress shall be made. In general, the review of lifecycle costs shall be based upon engineering judgement. However, the selection of the emergency power generators, compression and large pumps shall be based upon a formal, documented assessment of lifecycle costs. This shall take account of: Fuel consumption Maintenance periods – duration and frequency Cost of maintenance Page 97 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Reliability Maintainability of equipment Capital cost Cost of recommended spares Operability (cost of manpower) Availability and cost of Supplier support In addition to life cycle cost, the environmental expectations of the Contracting Authority must be considered in all equipment selection decisions. This is covered elsewhere. Page 98 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 6. HSE MINIMUM REQUIREMENTS This section defines the Health, Safety and Environment minimum requirements (hereinafter referred to as "HSE minimum requirements”), that the CONTRACTOR is expected to meet and to implement as a minimum acceptable standard during the execution of the contract activities. The HSE minimum requirements and activities in CAFC Project are categorized into the following 4 categories: (1) Engineering and Procurement; (2) Construction; (3) SIMOPS; (4) Interim Operation (to Handover; including Commissioning). These requirements cover all activities, regardless of location and status, undertaken as part of the work provided under the Contract, whether provided directly or by a SUB-CONTRACTOR, Vendor and Supplier (including, but not limited to, material and equipment of the CONTRACTOR or SUBCONTRACTOR). 6.1 NATIONAL LEGISLATION, REGULATION, CONTRACTING AUTHORITY AND INTERNATIONAL HSE CODES AND STANDARDS The aspects of the design which are related to HSE shall comply with all the applicable regulations, industry standards and project code and standards. In case of conflict between the Company‟s specifications and the reference Rules, Codes and Standard the following order of priority shall apply: 1. 2. 3. 4. 5. 6. 7. Algerian statutory requirements; The Contract; CONTRACTING AUTHORITY documents; Process Basis of Design; All other CONTRACTING AUTHORITY Technical Data; FEED ITT Package documents (including reference list of applicable codes and standards); International codes, standards, best practice and guidelines. In the case of an inconsistency between the requirements of any of the aforementioned, then priority shall be given in descending order. The more onerous requirements shall apply, unless otherwise expressly determined by the CONTRACTING AUTHORITY in writing. CONTRACTING AUTHORITY shall have the right at all times to modify its requirements in the interests of improving the Safety, Health, Environment and welfare of personnel in the workplace. To the extent that there is a conflict between the project HSE requirements and this document, the more stringent requirement as determined by COMPANY shall prevail. Page 99 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 6.2 DESIGN HSE PHILOSOPHY The design HSE philosophy is established with the intent to provide a framework and basis for the design of CAFC project facilities to ensure that all hazards with the potential to jeopardize the integrity of the project facilities and personnel attending the facilities have been identified and risks have been reduced to As Low As Reasonably Practicable (ALARP). The definition of the HSE design criteria during the detail engineering to be applied for CAFC project facilities design shall be part of the CONTRACTOR activities to manage the HSE-related risks during the entire performance of the work. CONTRACTOR shall further define and develop the projects HSE philosophies for all CAFC project facilities with the aim to collate and documents all the HSE design criteria and philosophies, applicable regulations, codes and standards that are to be adhered regarding design of the CAFC project facilities. CONTRACTOR shall comply with, and further develop and update as necessary the FEED project HSE philosophies during the EPC in consultation with and approval of the CONTRACTING AUTHORITY. CONTRACTOR shall comply with, and further develop and update as necessary the FEED HSE documentations during the EPC in consultation with and approval of the CONTRACTING AUTHORITY. Moreover CONTRACTOR shall agree with the CONTRACTING AUTHORITY on the HSE deliverables to be prepared by the CONTRACTOR during the EPC phase. Throughout the design of the installation, emphasis shall be placed on: Provision of safe working conditions for personnel working on the installation facilities (and immediate environs); Protection of the asset; Minimise the potential for hazardous occurrences; Minimise the risk and consequences of an accidental event; Provide sufficient safety devices and redundancy to isolate and minimise uncontrolled releases of flammable and toxic substances; Provide appropriate fire protection systems to rapidly bring under control and extinguish any reasonably foreseeable fire which could develop during normal operations; Protection of the environment and compliance with regulatory requirements; Minimal damage to the environment under non emergency conditions; Minimal adverse impact to the local community; Minimum damage to equipment and prevention of long downtime or production deferment which could be jeopardized by the occurrence of hazards inherent to hydrocarbon processing or any other risks linked to an onshore processing facilities and industrial activities. Ensure adequate means of Emergency Response (ER), Escape, Evacuation and Rescue (EER) in the event of an incident. The design philosophy is thus based on: a) Elimination and prevention of hazardous incidents, as far as is practicable: The application of codes of practice and standards, and performing the design in accordance with Algerian Regulations and CONTRACTING AUTHORITY HSE minimum requirements, standards and guidelines; CAFC project facilities shall be designed in accordance with CAFC project document „Codes & Standards‟ to be approved by the CONTRACTING AUTHORITY during the EPC phase‟; Compliance with a project HSE Philosophies appropriate to CAFC project facilities; Development of design and installation HSE systems based on the minimum requirements established in this document and as they will be defined in the project HSE philosophies and relevant CAFC project specifications. b) Mitigation of the effects should a hazardous incident occur: Page 100 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Minimize the potential or frequency of hazardous events; Control or mitigate the consequences of the hazards, including impact to the environment; Define the requirements regarding asset protection, and ensure they are duly taken into consideration. c) Emergency Response (ER), Escape, Evacuation and Rescue (EER) in the event of an incident. Provision of adequate escape, evacuation and rescue facilities. 6.3 HAZARD MANAGEMENT AND RISK MANAGEMENT A goal setting approach will be applied to the project for its whole lifecycle. This will link the processes of Hazard Management with Risk Assessment and other safety engineering studies and reviews. Together, during the project phase, these facilitate confident and informed engineering decision making which is directed at reducing risks to tolerable levels as the design matures and demonstrating they are as low as reasonably practicable and appropriate for that stage of the development. CONTRACTOR shall submit during the detail engineering a final HSE Plan for engineering clearly indicating the Hazard Management and Risk Management Process, (e.g. ALARP/ HAZID/ SIL/ QRA/EERA/HSE Impact assessments/HSE Case) it will use to implement HSE in the EPC phase. All studies shall form part of the overall risk management plan, to be developed during EPC by the CONTRACTOR and submitted to the CONTRACTING AUTHORITY for approval. All the methodologies for the required HSE studies shall be approved by CONTRACTING AUTHORITY at the early stage of the detailed engineering and in any case before the commencement of the studies. 6.3.1 GENERAL PRINCIPLES A fundamental element of CONTRACTING AUTHORITY HSE Policy is that management of risk is a continuous process and the cornerstone of all of the Contracting Authority HSE Elements. The CONTRACTOR shall regularly identify the hazards and assess the risks associated with all his Work. The CONTRACTOR shall take appropriate action to manage the risks and hence prevent or reduce the impact of potential accidents or incidents. Risk assessments shall be carried out to compare the risks as identified and analyzed with the criteria for maximum acceptable risks as stipulated by regulations or defined by CONTRACTING AUTHORITY policy. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP). At the design stage significant efforts shall be made to manage hazards by the application of Inherent Safety principles rather than by moving directly to control and mitigation methods. ALARP principles (and Cost Benefit Analyses when required) shall be used to judge the adequacy at each stage of the risk management process. Consideration of HSE aspects shall be incorporated into all stages of the project in order that issues can be addressed as soon as they arise. The earlier an HSE issue is identified, the easier it is to address the issue and find a cost effective, practical solution. It is the responsibility of the CONTRACTOR to demonstrate that the risks associated with CAFC project facilities design comply with the CONTRACTING AUTHORITY requirements. Formal studies methods shall be used to identify major hazards and assess risks so that adequate protection features are provided. The main studies to be carried out during the EPC are described in the following paragraphs. Page 101 / 180 Part D - Scope of Work 6.3.2 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 HAZARD IDENTIFICATION STUDY (HAZID) A preliminary risk assessment, Hazard Identification Study (HAZID) has been completed during FEED. As a result of this study a Hazard Register has been compiled detailing the Major Accident Hazards. The findings and recommendations of FEED HAZID, performed during FEED, shall be implemented by CONTRACTOR into CAFC project facilities design and operation during EPC phase. In every aspect of his Work, the CONTRACTOR shall carry out a risk assessment exercise to identify Major Accident Events (MAE). Once on-site activities have commenced and prior to commencing any new activity or as any condition changes affecting the previous analysis, a new risk assessment shall be conducted. All resultant findings or action items necessary to manage/control risks shall be updated in the Hazard Register. The Hazard Register shall be maintained by the CONTRACTOR through out the Contract duration. Any new Major Hazards and/or action items identified by the CONTRACTOR shall be brought to the attention of the CONTRACTING AUTHORITY and addressed through the tracking system. During the detailed engineering of the EPC phase, CONTRACTOR shall perform new HAZID follow up and shall perform a new HAZID to identify new possible Hazards related to CAFC project facilities design , CONTRACTOR shall take in consideration the existing MLE facilities. CONTRACTOR shall perform a Construction & SIMOPS HAZID before the commencement of the construction activities. 6.3.3 6.3.3.1 HAZOP STUDIES FEED HAZOP A preliminary Hazard and Operability Study has been carried out as part of FEED excluding of the following systems: Raw Water; Water Treatment; Drinking Water; Service Water; Drain Water. The findings from this study shall be incorporated into the P&IDs where possible. The HAZOP report is included in the FEED package and action sheets shall be available to CONTRACTOR during the ITT. Any actions outstanding at contract award shall be the responsibility of the CONTRACTOR. CONTRACTOR shall demonstrate that all the FEED HAZOP findings and recommendations have been implemented in the FEED documentation. Moreover all the actions related to the systems not studied during the FEED HAZOP shall be the responsibility of the CONTRACTOR. 6.3.3.2 EPC HAZOP HAZOP shall be performed for the complete set of equipment based on issued P&ID‟s and Cause & Effect Diagrams. HAZOP Action Sheets shall be issued for previous approval by the CONTRACTING AUTHORITY. A HAZOP follow-up schedule shall also be issued and kept up to date when implementing the actions. The principal Drawings available for review during the HAZOP shall include, but not be limited to, Process Flow Diagrams, equipment Arrangement Drawings, Electrical Area Classification Layouts, Area Protection Layout Drawings, Flare and Vent System Data, Control Valve and equipment Data Sheets, Cause and Effect Charts, PCS Logic, ESD Logic and F&G Logic, Safeguarding Diagrams, DP/DT Drawings, Line Lists, Material Selection Drawings. Page 102 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 For the avoidance of doubt, CONTRACTOR shall be responsible to implement all HAZOP findings and recommendations arising as a result of the final (HAZOP & SIL) to be per carried out during EPC phase. The HAZOP scope shall be for the whole of the CAFC facilities including tie-ins and shall include all utilities and Supplier packages. Supplier package HAZOP sessions shall take place at the appropriate time in the development of these packages. CONTRACTOR shall ensure that all required personnel attend the HAZOP sessions. A pre start-up HAZOP shall also be carried out and the CONTRACTING AUTHORITY shall assist in the co-ordination effort required to bring Operations personnel to the HAZOP if available. The selection of the independent chairperson and HAZOP recording and reporting procedures shall be subject to approval by the CONTRACTING AUTHORITY. If changes to design are made post-HAZOP, then procedures followed by the responsible CONTRACTOR shall determine whether further HAZOP of such systems shall be made. These procedures shall include approval by CONTRACTING AUTHORITY. CONTRACTOR shall use preferably use the PHA or LIHOU Technical Software Services as the HAZOP Manager Software. Any other alternative shall be subject to CONTRACTING AUTHORITY approval. 6.3.4 SIL ASSESSMENT AND VERIFICATION A SIL Assessment and subsequent Verification shall be performed by the CONTRACTOR during the EPC phase after the HAZOP. A hazard risk analysis (SIL Assessment and Verification) shall be undertaken for each protective function, based on the criteria defined in IEC 61508 and IEC 61511. Note: no SIL assessment was performed during the FEED phase, thus CONTRACTOR shall consider the implementation of any possible impact derived by the EPC SIL assessment. HAZID, HAZOP and SIL sessions shall be led by a third party approved by CONTRACTING AUTHORITY. Related costs shall be included and detailed in the lump-sum offer. 6.3.5 FIRE AND EXPLOSION RISK ANALYSIS (FERA) A Fire and Explosion Risk Analysis (FERA) has been performed during the FEED; CONTRACTOR shall perform a detailed FERA when proper project documentation will be available during the detailed engineering. The FERA Methodology shall be submitted to the CONTRACTING AUTHORITY at the early stage of the detailed engineering for its review and approval. A Blast Overpressure Study shall also be developed. Note: during the development of the FERA, CONTRACTOR shall pose particular attention of its results with respect to the blow down system design and philosophy. In fact, the current blow down philosophy foresees that the plant is divided in two macro-areas: slug catchers area and process area. In case of emergency, first the macro-area in which is detected the event will be depressurised and subsequently the second macro-area. Once identified potential reciprocal impacts between the areas, CONTRACTOR shall identify proper protective measures, since it is not acceptable that an event from one macro-area could impact the second macro-area. Page 103 / 180 Part D - Scope of Work 6.3.6 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 QUANTITATIVE RISK ANALYSIS (QRA) A preliminary Quantitative Risk Analysis (QRA) has been carried out at the FEED phase; CONTRACTOR shall perform a detailed QRA when proper project documentation will be available during the detailed engineering. The QRA Methodology shall be submitted to the CONTRACTING AUTHORITY at the early stage of the detailed engineering for its review and approval. Note: it is CONTRACTING AUTHORITY intention to perform an overall QRA considering both CAFC and MLE together, in order to determine the overall risks associated with the combined facilities. CONTRACTOR could be requested to develop the study and/or implement resulting actions. 6.3.7 DESIGN CASE SCENARIO The accidental scenario, both in terms of hazard likelihood and severity of consequences for assets, identified for a specific plant area and considering all possible operating conditions (e.g. Construction, SIMOPS), shall be used as a reference for systems design (e.g. fire fighting, F&G, safety distances, etc.). Once the Design Case Scenario has been selected and its risk assessed against Risk Acceptability Matrix for Assets, all the remaining risks shall be considered as Residual Risks and shall be analysed through a QRA process. 6.3.8 DESIGN AND SAFETY REVIEWS CONTRACTOR shall manage various design reviews and safety studies at the CONTRACTOR‟S offices during the course of the Work. CONTRACTOR shall demonstrate by means of one or more design reviews, as may be deemed necessary, that the design is safe, reliable, and efficient and in accordance with CONTRACTING AUTHORITY requirements. CONTRACTOR shall provide all facilities and information necessary for the effective implementation of the studies. Each of these design reviews shall require the active participation of the CONTRACTOR‟S key personnel who are working on the design, in an interactive discussion with CONTRACTING AUTHORITY. Such design review may also include third party participation. Design reviews and participation from outside the project shall be arranged at the discretion of the CONTRACTING AUTHORITY, although the CONTRACTOR shall recommend when, in the opinion of the CONTRACTOR such participation should be invited and shall include such milestones in the Project Schedule. The CONTRACTING AUTHORITY shall provide assistance to the CONTRACTOR concerning these studies and shall actively participate. The CONTRACTOR shall provide a „Case for Safety‟ for each site covering the project scope of work. This shall contain a summary of the relevant risk management studies and include the ALARP demonstration, content of the HSE Case report shall be agreed with the CONTRACTING AUTHORITY. CONTRACTING AUTHORITY shall ensure that a project HSE Case is a key deliverable of the Project HSE plan and the CONTRACTOR will be required to develop and submit to the CONTRACTING AUTHORITY for approval an HSE Case which demonstrates that all significant HSE risks have been identified, assessed and will be controlled to a level as low as reasonably Page 104 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 practicable (ALARP). The Project HSE Case shall be completed before construction execution and updated during Construction and SIMOPS phase. CONTRACTOR shall update the HSE Case during the WORKS to ensure that the HSE Case remains valid for the duration of the WORKS. The scope of work and document structure of the HSE Case report will be agreed with CONTRACTING AUTHORITY before the beginning of the activity. The HSE Case document is composed of four main parts: Facilities description; Safety management system description; Risk analysis and safety assessment; Emergency and remedial actions. 6.3.9 ENVIRONMENTAL, SOCIAL AND HEALTH IMPACT ASSESSMENT (ESHIA) An Environmental, Social and Health Impact Assessment (ESHIA) has been conducted during the FEED phase by CONTRACT AUTHORITY and, submitted to local authorities. EPC Contractor shall comply with the requirements of the MLE & CAFC ESHIA studies that will be provided. Furthermore CONTRACTOR shall update at the EPC phase the FEED project environment requirements according to the finding and the recommendation of the ESHIA and the latest Algerian laws and ensure that all the finding and recommendation of the ESHIA report are implemented at the EPC phase. Note: ESHIA will be provided to the CONTRACTOR and CONTRACTOR shall be responsible to conduct all the activities part of the EPC according to the finding and relevant Action Plan. 6.3.10 HUMAN FACTORS STUDY CONTRACTOR shall carry out a Human Factors Study during detailed design. The Scope of Work of the Human Factors Study shall include: An assessment of alarm protocols and priorities, location, numbers, access and visibility of alarms and controls during normal and emergency operations. Ergonomics of the local equipment rooms and changes to the current Control Room, including lighting, general layout and workstation layout during normal and emergency operations. Access to and egress from equipment, etc. The exact scope of the study shall be developed by the CONTRACTOR and shall be subject to the CONTRACTING AUTHORITY review. The study shall be initiated sufficiently early to be incorporated into aspects of change to the existing Control Room, design of local equipment rooms and procurement of the Integrated Control System. Page 105 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 6.3.11 SAFETY CRITICAL ELEMENTS (SCE’S) IDENTIFICATION PROCESS AND MINIMUM REQUIREMENTS All HSE Critical Systems shall be identified and their performance standards shall be set for the CAFC project. Setting the performance standards ensures that for the identified systems, the design, procurement and operation fully meets CONTRACTING AUTHORITY standards. 6.3.12 HSE ACTION TRACKING It shall be the CONTRACTOR responsibility to implement a suitable action tracking system, subject to Contracting Authority approval. All actions arising from new studies, risk assessments and all other safety related matters shall be compiled into action sheets and controlled by the CONTRACTOR. CONTRACTOR shall prepare a monthly report which addresses the various issues raised and compiled during different project reviews, detailing the number of action items closed in that month and the current status of the remainder of the action items. CONTRACTOR shall be responsible for initiating and undertaking any additional safety studies to justify the design. Where required, all such studies shall be subject to review by the CONTRACTING AUTHORITY. 6.4 INHERENT SAFETY The principles of inherent safety that shall be adopted are as follows: Segregation/separation.(See also Layout Philosophy section); Minimisation of inventories/storage, etc; Quality proven equipment; Design simplification. The design shall take all measures to ensure the stored inventories whether gas or liquids are minimised. The areas where this applies are: Pressurised process gas systems; Liquid hydrocarbon storage. Minimisation of the leak sources shall be achieved by: Minimising flanged connections; Minimising instrumentation; Using ring type joints where practical for gas service. Maximize ventilation/ Minimize congestion Correct spacing of equipment in accordance with the distances as described in following section the ventilation within the hazardous areas of the plant shall be maximised. Each risk area of the plant should be assessed for the adequacy of the spacing and ventilation. Orientations To minimise the consequences of explosion overpressure effects consideration in the design shall be given to orientating large items of equipment to reduce blockage. Buildings should be orientated for minimum exposure to overpressure as should large vessels. Further technical development shall be developed by the CONTRACTOR during the EPC phase to support this objective. Page 106 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 6.5 LAYOUT PHILOSOPHY 6.5.1 LAYOUT CRITERIA TO MINIMIZE RISKS In addition to normal engineering and process considerations, the design of the layout shall consider defined safety criteria in order to minimize risks for personnel and equipment from fire or flammable gas releases and maximize the capacity to deal with all possible emergency situations. In addition to the requirements outlined in the FEED documents, the following intrinsic safety principles governing plant layout shall be taken into account when locating the new facilities for CAFC Project: The overall arrangement orientation will be such that the prevailing wind will tend to disperse any hazardous release away from the safe area i.e. process equipment, hydrocarbon storage, and flare and vent areas shall be located downwind of the safe areas. In locating the flare the potential for dispersing flammables to be ignited shall be avoided either by separation or orientation; Adequate separation shall be provided between hydrocarbon-handling areas (hazardous areas) and emergency services, main safety equipment, escape routes, areas to be non-hazardous and permanently manned buildings; Vents (if any) shall be located so as to cause minimum interference or hazard to plant and personnel; For gas systems, vent (if any) and relief valves shall be collected and discharged in safe location, should the volumes to be vented be capable to create a hazardous condition; The plant layout shall meet safety requirements for Hazardous Area Classification for electrical equipment (See also Electrical System Design Section); Adequate separation between flammable hydrocarbons and ignition sources shall be provided and Limiting confinement and congestion in process areas; Units that contain large quantities of flammable fluids shall be located so the prevailing wind will blow any vapour from an accidental spill away from the plant; Process piping and equipment, which are potential sources of hydrocarbon leaks, should be routed so as to minimize the likelihood of external impacts (e.g. from vehicles, maintenance devices, etc.); Crash barriers shall be provided where there is any possibility of vehicle impact with pipelines, HV transmission lines, fire hydrants, etc. (e.g. at road crossings); Equipment shall not be located above live equipment for future phases nor shall it require lifting above/across live equipment; All basic design principles for minimising dropped objects and collisions shall be applied to layout; Signals shall be provided for the access ways in the Plant area to highlight headway and width at overhead pipeline crossing points, maximum load capacity and turning bend radius; Emergency shutdown systems shall be provided and located in such a way that the risk of involvement in a developing accident is minimized: SDV‟s shall be fire-rated and located at minimum practicable distance from the vessels and equipment served; The inlet and outlet ESDV‟s of a plant shall be isolated or protected from the Design Case Scenarios and survive at least the time required to safely evacuate the plant; Fire fighting equipment such as firewater/foam concentrate tanks and firewater pumps shall be located away from any units having high fire potential. 6.5.2 MINIMUM SAFETY DISTANCES Distances between units and equipment within the plant shall be established according to safe accessibility aspects for operation and maintenance. Utilities shall be used as a “buffer” between restricted and unrestricted areas. Page 107 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 As a minimum, all components or units that will be installed in plant areas shall be arranged/located to observe the safety distances prescribed in the CONTRACTING AUTHORITY standards and any other applicable standards identified during the EPC phase. Separation distances for safe and hazardous areas shall never be less than required by the results of hazard assessments (e.g. QRA, FERA, etc.).. Note: CONTRACTOR shall pose particular attention to the position of slug catchers and flare KO drums taking in consideration the equivalent Note reported in FERA section. 6.5.3 FIRE ZONE The process plant shall be divided into logical, physically located fire zones, which can be process isolated. Each zone must be easily identifiable with respect to physical and /or process boundaries. Fire zone definition carried out during the FEED stage shall be further reviewed and developed during EPC phase. The grouping of units into fire zones shall be closely linked to the process flow and arrangement. Each fire zone largely incorporates complete process units, which upon an ESD level activation with depressurization will not produce a depressurizing capacity that is greater than the predefined capacity of the flare system. As the governing factor for grouping is the flare capacity, this limits how far process units can be further grouped into larger fire zones. Furthermore, grouping of units into fire zones also corresponds to assembly of units with a comparable level of process risks. 6.5.4 6.5.4.1 ACCESS AND EVACUATION ACCESS REQUIREMENTS Access to the process / utility areas shall be available from all sides to allow for both fire fighting and maintenance activities. Space should also be provided for lay down of equipment during maintenance or replacement. For personnel safety in emergency situations it is necessary to provide some primary disposals to ensure an easy evacuation from hazardous areas. 6.5.4.2 ROADS DESIGN Site roads shall be provided giving good access for emergency vehicles, with due account given to their turning circles, and cranes, as necessary, to all site areas. Site access roads shall be provided with barriers and access control facilities to prevent unauthorized entry. All roads will be subject to appropriate speed restrictions. Equipment shall be located such that these site roads do not pass through areas classified as “hazardous”. Any road that of necessity is classified as hazardous shall be subjected to restricted vehicular access and the area shall be indicated accordingly. Roads shall provide access to all sides of the process areas and buildings for fire trucks, portable foam equipment and equipment to supplement permanently installed fire monitors; Major site roads shall be of minimum width 6m, and shall not be more than 400 m apart. Minor site roads shall be of minimum width of 4m. Minor site roads shall not be in an area classified as zone 0 or 1; The layout shall also meet requirements for vehicle and personnel traffic, security, emergency evacuation, fire fighting and access for maintenance and operation; Traffic barriers shall be provided around critical equipment, where located close to roadways; Access ways shall be provided for escape and fire-fighting purposes, linking plant areas with the site roads. Page 108 / 180 Part D - Scope of Work 6.5.4.3 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 EVACUATION At least two opposite escape routes shall be provided for plant area and buildings. Escape routes shall be arranged to direct escaping personnel away from the hazard towards the nearest exit from the building. The configuration of the primary escape routes shall ensure adequate room for fire and rescue teams to operate unhindered. Every escape route shall be readily accessible at all times, unobstructed, well marked and provided with adequate emergency lighting and signs. For internal areas (rooms) the maximum allowable travel length to an exit shall be 7 m. At least 2 exits shall be installed if length exceeds 7 m. Dead end corridors shall not exceed 5 m. For outside areas, escape routes shall be located at the outer edges of hazardous units. Main escape routes shall be at least 1.2 m wide and have clear headroom of 2.1 m. Escape/access routes leading to main escape routes shall have a minimum width of 0.8 m. Consideration shall be given to the evacuation of injured personnel on stretchers, Where changes in elevation of escape routes occur, ramps or stairways shall be provided. Their minimum clear width shall generally be the same as the escape route they serve. All doors and gates on escape routes shall be easily opened from either side and shall not be possible of being permanently locked, except by frangible elements. Doors that open out on to an escape route shall not reduce the escape path width below the minimum requirement .All doors shall be illuminated by an emergency lighting system and safety signs. Fixed ladders specifically designed for escape purposes are only required for escape from access platforms less than 5m in length or form towers, columns, etc. and as secondary escape from an elevated process area that has a main escape stairway. One (or more) Assembly Area shall be provided for an emergency evacuation of the plant personnel. This area shall be located so when an emergency evacuation is required, the operating personnel can go to the assembly area and be in a safe place; the assembly area shall be safe in prevailing wind conditions. The area shall be identified with a large sign and should have a sheltered telephone. Direction arrow markers shall be strategically positioned along escape routes where it is necessary to guide personnel to the assembly area. An Escape, Evacuation and Rescue (EER) Plan shall be a deliverable of the EPC phase and to be provided by the CONTRACTOR. 6.6 PROCESS SAFETY CRITERIA 6.6.1 GENERAL The process has to be as much as possible simple, in order to ensure the ease of all process operations. The PSD system shall automatically detect abnormal operating conditions within systems or equipment and initiate actions so that uncontrolled release of hydrocarbons is prevented. “Fail Safe” equipment has to be provided in order to limit the effects of failures or leakages (e.g. in principle, shutdown valves to isolate process sections shall fail in closed position, blow down valves shall fail in open position, etc.). All actuated valves with safety functions (e.g. SDV‟s, BDV‟s) shall be “single effect”. The BDV valve shall have an air accumulator to avoid spurious opening due to air instrument failure. Two levels of protection, operating on different functionally basis (i.e. fully independent) shall be provided. Duplication of identical safety devices with different set points does not satisfy the requirement of two levels of protection. Main process sections/equipment shall be sectioned and depressurized in an emergency. Process and facilities will be designed such that no single failure during operations can lead to unacceptable hazardous situations. These principles will apply to operational errors as well as equipment failures. Page 109 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Material selection shall be dictated in consideration of corrosion, erosion, equipment and personnel contamination .The most stringent level of integrity among utilities and process shall be adopted for the interconnection between the two. 6.6.2 EQUIPMENT SAFETY REQUIREMENTS Vessels and other equipment should be suitable for their operation duty and all reasonably expected forces such as tank contents, ground settlement, frost, wind, earthquake and other as appropriate. Maintenance activities on process equipment will be protected by ensuring positive isolation from the process. Adequate facilities for ensuring this shall be provided according the project isolation philosophy. All vessels that require access by personnel during maintenance will be designed with facilities to connect utility systems, to ensure positive isolation from connected pipe work and to allow adequate purging and ventilation before access. All major hydrocarbon vessels will incorporate relieving systems which will be vented to Flare System. Relieving systems shall be designed and arranged according to API RP 520, and sized to meet the depressurization requirements of ANSI/API Std. 521. All pipes containing hydrocarbons shall be arranged in such a way as to minimize the risk of mechanical damage, either as a result of vehicular movement or lifting operations (e.g. associated PSV recertification activities).All equipment shall be provided with the relevant certifications of conformity, according to the applicable codes and directives (e.g. PED, ATEX, and Machinery Directive). 6.6.3 EMERGENCY SHUTDOWN SYSTEMS The ESD System shall be designed to perform the timely and safe isolation and shutdown of equipment, systems and operations following the detection of an abnormal or unsafe condition/incident. The ESD system shall be integrated with the Fire & Gas Detection System and will be activated by one or more of the following inputs: Process trips; Confirmed alarms from Fire & Gas detectors; Power failure; Push buttons located in Control Room. The operation of the ESD System shall be totally independent from the Distributed Control System (DCS). The following criteria shall be applied: The shutdown system, including sensors, actuators and associated connections and circuits, shall operate independently from other process and alarm systems .The ESD System shall be based on programmable microprocessors; sensors will be hardwired. The ESD circuits and actuators shall fail to a safe position on loss of power. The ESD System design shall consider interference from other electromagnetic sources, and shall incorporate suitable protection. It shall be possible to test critical items of the ESD System without stopping the normal process operations. ESD actuators and cables shall have resistance to the effects of fires and impacts. ESD handswitches located on the auxiliary panel will be clearly marked and shall be protected from inadvertent use. Care shall be taken in the design and structure of the ESD System to eliminate common-cause failures .The ESD System shall have sufficient separation/protection to ensure that a failure in any part of the system would not cause other part of the system inoperative. Page 110 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The inlet and outlet ESDV‟s of a plant, SDV‟s and BDV‟s shall be isolated or protected from the Design Case Scenarios and survive at least the time required to safely evacuate the plant. ESD valves shall not auto-reset. Individual local and remote (under a detailed operating procedure) reset shall be provided for ESD valves, only permitted once the shutdown cause has been locally checked and removed. BDV shall have the automatic reset (and not local) in order to avoid to forget some BDV opened before to re-start the plant. The ESD System shall be characterized by logic with a number of intervention levels whose priority shall be defined in relation to the extent of the deviations and their possible effects on production continuity, personnel and equipment safety. The CAFC shall have a dedicated ESD System shall be structured on different hierarchical safety shutdown levels, The ESD System shall subdivide the plant into discrete isolatable sections (fire zone) that can be singularly depressurized. CONTRACTOR shall develop and update the ESD philosophy developed during the FEED which shall guarantee plant area protection against the identified design case scenario to be defined during the EPC phase and considering synergy with MLE plant. 6.6.4 BLOW DOWN AND FLARE SYSTEMS The blow down system shall be designed to safely receive contain and burn plant hydrocarbon discharges from any emergency and process depressurization. Depressurization (blow down) systems are required to reduce the risks of loss of equipment integrity during a fire and/or to reduce a local loss of containment arising from a leak which may otherwise lead to escalation and the risk of catastrophic failures. The blow down philosophy is to depressurise the plant, fire zone by fire zone (following the results of QRA and Fire and Explosion Risk Analysis), in accordance with ANSI/API Std. 521. The design of the blow down system shall be based on achieving a pressure of 7 barg or 50% of design pressure, whichever is the lower, within 15 minutes from blow down initiation, in the involved fire zone(s).Blow down valves (BDV) shall be specified with a fail safe (open) failure mode and with air accumulator to avoid spurious opening in case of air instrument lack. The following general requirements shall be taken into account: The effect of cooling due to the gas expansion during depressurization shall be carefully evaluated during both normal operation and emergency conditions .Flare stacks shall be designed to withstand the loads imposed by all known environmental conditions (wind, temperature, sand, etc.). Tip selection will take into account the maximum allowed noise levels in manned areas. The tip shall be suitable for the calculated flare size and capacity, in order to ensure flame stability and flashback protection. Tip and flare upper section material selection shall take into account the effects of possible flame impingement. Flare tip will be equipped with an adequate number of pilots, with a reliable means of remote ignition; each pilot shall be provided with a thermocouple type flame detector; Open pipe flare tips shall be designed for a maximum Mach number of 0.5. Sterile areas shall be sized such that under foreseeable wind conditions flammable concentrations of gas do not occur at ground level under flame-out conditions and respecting the requirements in term of thermal radiation. In addition, it shall be ensured that ground level concentration of products of combustion of the flared gas do not exceed permissible limits for both short term and long term exposure. Continuous venting or flaring of flammable gas shall be avoided. However, if it is necessary to provide atmospheric vents from equipment or packages in flammable gas service, they shall be collected in a common vent stack discharging at safe location. The design objectives will be to operate without continuous flaring (except where specific consent is granted, e.g. for start-up operations or other specific purposes). The flare collection headers, Page 111 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 KO drums, risers and flare tips will be sized to cope with the maximum emergency loads. Adequate system shall be provided for the flare headers to prevent air ingress and burn back. Emergency depressurization (EDP) scenarios shall be verified at the EPC phase considering the final process configuration and operating/design conditions (fluids involved, EDP scenarios, effects of cooling/fireproofing protections, etc.) and considering synergy with MLE plant. 6.6.5 VENTING AND FLARING SYSTEMS The design shall not require continuous venting of gas other than the minimum necessary for purging. Flaring under normal operation shall be avoided. All facility venting shall be routed via dedicated blow down systems to a flare for safe disposal by burning of surplus flammable vapours produced from the plant. The flare and corresponding sterile area shall be located and designed with due attention to all relevant flaring rates and wind conditions to ensure that the heat radiation will be within acceptance limits in all areas of the installation and of the neighbours, with due regard to exposure of operators, structures such as cranes and towers, electrical and mechanical equipment and piping. The flare flame or hot gases shall not represent a hazard due to increased surface temperature in exposed areas. Particular attention should be paid to cranes, towers, structures and personnel in exposed areas. Further the design of the cold vent systems shall cater for heat loads caused by a possible ignition of the discharge. Flare radiation calculations shall include the effect of direct sun light. A means to prevent personnel entering the sterile area shall be provided. A dispersion analysis shall be carried out at the EPC phase to establish ground level concentration of pollutants in the event unburned gas is vented. 6.7 DRAIN SYSTEMS Drainage systems shall be provided to convey drainages from plant areas and systems to treatment, recovery or disposal facilities and according to CAFC drainage philosophy. Drainage systems shall be designed to: Safely dispose hydrocarbons during drain-down of process vessels and equipment; Contain any spillage of flammable or pollutant liquids; Minimize the spread and area exposure of spills and fires; Collect direct spills to a safe location, where spills can be retained and either recovered or disposed; Prevent backflow and fire spread through the system; Avoid any possible impact on the environment caused by accidental spills. Drainages from hazardous areas shall be physically separated from drains serving non-hazardous areas. This separation shall ensure that communication between hazardous and non-hazardous areas via the drain system is prevented. Two different kinds of drain systems shall be provided in the plant: 1. Closed (process) drain systems; 2. Open (atmospheric) drain systems. 6.7.1 CLOSED DRAIN SYSTEM Process drains from vessels, equipment, instrumentation and piping shall be routed, via dedicated closed drain headers, to a closed drain vessel. The closed drain vessel shall be sized to receive the maximum liquid load, provided that the process items are singularly drained. Where possible, adequate pump system shall be designed to reprocess fluids into the system. Page 112 / 180 Part D - Scope of Work 6.7.2 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 OPEN DRAIN SYSTEM Open drain systems collect rain waters and oily waters coming from the washing of process paved areas (oil is separated prior to the discharge of water, and separated oil is sent to the closed drain system). Kerbs or drip pans shall be provided under potential leak sources (e.g. vessels and pumps). All process area and utilities area (i.e. chemicals) shall be paved and sloped to low points. Transit of spill from one zone to another, including through drainage system shall be prevented. The drainage system for the process areas, bounded areas or kerbed areas shall be designed taking into account of the potential firewater / foam flows, which may be released in the event of a fire case. Moreover, since the plant is located in desert area, the design and the operation of the open drain system shall take into account problems related to sand accumulation. 6.8 ELECTRICAL SYSTEM DESIGN The electrical system design shall be in accordance with established codes, sound engineering practices and international standards. The electrical system shall be designed to provide the following: Safety to personnel and equipment; Reliability of service; Minimize the risks; Sufficient emergency power to safely shutdown in the event of an accident. 6.8.1 HAZARDOUS AREA CLASSIFICATION The facilities shall be classified according to the degree of hazard present in the place of the installation and the probability of flammable gas being released. The classification shall be carried out in accordance with the procedures laid down in IEC 6007910 or API Recommended Practice 505. Areas will be classified as Zone 0, Zone 1, Zone 2 or will be unclassified (i.e. non-hazardous), using the definitions given in these specifications. Details for hazardous area classification will be provided in “Hazardous Area classification report during the EPC phase. The following areas shall be defined as non-hazardous either by location or, if enclosed, by positive pressurization by an HVAC system: Assembly areas; Areas of emergency power and control ; Control and electrical rooms; Accommodation areas and offices; Air intakes. Hazardous Area Classification datasheets and drawings shall be prepared by CONTRACTOR, to ensure the new facilities foreseen in the Project are adequately specified according to the degree of classification of their area to include the following information: Characterization of the hazardous fluids; Identification of sources of release; Ventilation inlets and outlets; Air intakes and exhausts of internal combustion machinery; Location of all equipment units; Tank or process vents; The classification and extent of all hazardous zones; Page 113 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Ventilation type. 6.8.1.1 EQUIPMENT SELECTION Electrical equipment to be installed in hazardous area shall be suitable for use in the appropriate classified area, and shall comply with the requirements of ATEX Directive and IEC 60079 and be ATEX Certified by a recognised international authority (e.g. IEC, CENELEC, BASEEFA, CESI). The minimum certification of electrical apparatus to be installed in an hazardous area shall cover gas group IIA and temperature classification T3 (200°C). The minimum IP rating for outdoor electrical equipment, considering the desert environment, shall be IP 55. All mechanical equipment installed in hazardous area shall be of a type which will ensure that hot surfaces are insulated, shall be non-sparking and adequately protected against the generation of electrostatic charge. All internal combustion engines that shall be installed in hazardous area shall be specified with suitable protections, according to EN 1834-1:2000 requirements (e.g. protections for air intakes and flue gas discharges if located in hazardous area, automatic trip of the engine in case of overspeed, etc.). 6.8.1.2 VENTILATION AND PRESSURIZATION To minimize the classification of a hazardous area, adequate ventilation is necessary. In unrestricted open areas a natural airflow across the area is sufficient. In enclosed or sheltered areas, forced ventilations by means of suitable stirrer fans is likely to be required to achieve the minimum of 12 air changes per hour necessary to prevent the area being inadequately ventilated. Where forced ventilation is required, the following basic principles apply: Gas extractors shall be located as close to the source of hazardous area as possible; Gas extraction rate shall be equal or higher than the gas leakage/emission rate; Air flow patterns (e.g. location of fresh air inlet ducts and extractors) shall be designed in order to minimize the extension of the hazardous volume. 6.8.2 EMERGENCY POWER SYSTEM The emergency power shall be provided at CAFC Project separately/independently from each other. The emergency configuration at CAFC will be defined/determined during the design phase of the plant. Emergency electrical power supply is required at least for the following emergency systems (essential loads): Safety controls (including F&G and ESD systems); Critical monitoring equipment; Emergency lighting; Firefighting system; Ventilation/pressurization systems; Alarm and communication systems; UPS System. An Uninterruptible Power Supply (UPS) system shall be provided, located in a dedicated safe area and shall supply, at least, the following utilities: CAFC project will use the Battery back-up. Battery back-up shall be provided, but not limited to the following vital electric loads: Page 114 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Fire & Gas Detection system; Emergency shutdown (ESD) system; Distributed Control System (DCS) and control panels; Public Address/General Alarm (PA/GA) system; Internal and External Telecommunication systems. Batteries shall be sized to ensure alimentation to the above systems for a period as required in Eni E&P Standard n. 20208.VAR.ELE.SDS. ELECTRICAL POWER SYSTEM 6.9 FIRE & GAS DETECTION SYSTEM The objective of the Fire & Gas Detection System is to detect gas leaks or fires at an early stage, in order to promptly activate/initiate the relevant alarms and protection means. To achieve this, F&G detectors will be provided in all areas with a significant fire or gas hazard; detectors will be selected and located to maximize the speed and reliability of response. The functions of the F&G Detection System shall be: To monitor all areas where fire can arise; To monitor all areas where flammable/toxic vapours might be present in normal operation; To monitor air locks and HVAC air intakes to buildings/enclosures for toxic and flammable gas; To provide a facility for raising an alarm; To alert personnel on any fire, gas (toxic or flammable) emergency situation; To activate the automatic fire fighting system and ESD system; To close fire dampers of facilities where gas is detected; To alert personnel in Control Room of any fault detected by self-test facilities; To evaluate signals from F&G detection system, using voting techniques where necessary; To monitor state and availability of the fire fighting systems. F&G is mainly initiated automatically and/or manually via F&G detectors or devices/systems. Toxic gas detectors could be required in case toxic gaseous or liquid chemicals are handled/processed in the plant. 6.9.1 FIRE DETECTION Fire detection systems shall be installed where it is considered that the development of a fire constitutes a possible threat to the plant. The fire detection system shall be designed to: Detect a fire as early as possible; Initiate preventive/shutdown actions at an early stage in order to mitigate the consequences; Alert personnel of the danger; Activate the ESD System in the affected area; Shut down and depressurize the systems in the affected area on confirmed fire detection; Activate fire fighting/protection systems (as required). The selection of the fire detectors for an area shall reflect the anticipated prime indication of a fire. Heat, smoke and flame detectors shall be considered, depending on the expected type of fire to be detected and the environment in which the detectors are located. Page 115 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The location of the fire detectors shall take into account the following issues: Location of the foreseeable leak source; Released gas dispersion/dilution and influence of the ventilation air flow patterns; Anticipated flow of hot combustion gases; Shielding by beams, equipment and piping; Process system configuration; Accessibility for maintenance and testing. 6.9.2 FLAMMABLE GAS DETECTION Flammable gas detection shall be provided at locations where accidental releases or ignition of such gas constitutes a possible threat to the plant or personnel. The flammable gas detection shall be designed to: Detect earlier a release of flammable gas and warn personnel of impending danger; Allow preventive actions to be taken at an early stage, in order to reduce leakage and isolate ignition sources; Activate ESD in the affected area; Shut down and depressurize the systems in the affected area on confirmed gas detection. The requirement for number and type of detectors to be provided shall be based on an evaluation of: Materials processed in the detection area; Gas evolution rate and buoyancy; Process conditions (e.g. high pressure, low temperature) which could affect the dispersion of the released gas; The likelihood of successfully detecting the released material and the major accident potential. The local ambient conditions and strong sources of ignition need careful consideration in the selection and positioning of gas detectors. Installation, testing and maintenance shall ensure reliability in order to minimize spurious alarms. Flammable gas detectors shall be set at two thresholds of detection for explosive mixtures, in order to facilitate a prompt action in case of gas release. A detailed definition of type, number and location of gas detectors shall be performed during the detail engineering of the EPC phase. 6.9.3 MANUAL ALARM CALL POINT In addition to automatic fire detection devices, local manual fire alarm call points (MACs) shall be strategically located throughout the plant areas, so that personnel working on the plant can raise the alarm if a hazardous situation is detected. At least one MAC shall be provided in every unit or plant area; the maximum distance between two MAC‟s shall not exceed 150 m. These stations shall be of a break-glass type, specifically manufactured for this purpose. Once operated, the station shall remain in alarm position until manual reset (i.e. glass replaced). Page 116 / 180 Part D - Scope of Work 6.10 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 ALARM SYSTEMS 6.10.1 ALARMS IN CONTROL ROOM All the automatic detection systems installed in the different areas shall send, in case of emergency, a separate alarm signal to the main F&G Alarm Panel in Control Room. MACs, when operated, shall send a common alarm signal per area to the main F&G Alarm Panel in Control Room. 6.10.2 PA/GA AND FIELD ALARM SYSTEMS The PA/GA System consists of loudspeakers which must be strategically located throughout the plant area, in order to enable personnel to listen to vocal messages or alarms from any point of the plant. The system is supported with flashing lights in areas where noise levels are elevated. Emergency lights and sirens shall be located throughout the facilities to alert field personnel in case of emergency. Standard visual and acoustic signals, automatically activated by F&G detection or MAC activation, shall be as shown in the following table. Gas Alarm Cause Gas detection (at upper detection threshold) Acoustic Signal AS3 (YELP), corresponding to a short siren sound (600 1250Hz) repeated with a 0.25” cycle Fire/General Alarm (1) Visual Indication Red flashing light in all plant areas Cause Confirmed fire detection or MAC activation Acoustic Signal AS4 (SLOW WOOP) corresponding to a bitonal rising sound (500 1200Hz) repeated with a 4.1” cycle Visual Indication (1) Red continuous light in all plant areas (1) NOTES : AS3 signal takes priority to AS4 and can silence it during simultaneous emergencies. Head of Plant‟s messages take priority and usually silence other acoustic signals. 6.10.3 ALARM VOTING FOR AUTOMATIC ACTIVATIONS All loops and detectors shall be arranged such that any arising hazard can be easily located. A F&G Cause/Effect Matrix shall detail the alarms and executive actions taken on fire, gas, heat detection or manual activation. Detection in one loop (except for fusible plugs) or in one detector shall provide an alarm only. Any firefighting or shutdown/depressurization actions required to automatically occur in the hazardous process areas shall require a voting system of instruments. At least two detection devices (as a minimum 2ooN voting logic) in the same voting group shall be provided to sense the hazard before an automatic action occurs. 6.11 FIRE PROTECTION SYSTEMS The plant fire protection is achieved through a combination of the following: Active Fire Protection, by means of extinguishing or cooling agents (e.g. water, foam, inert gas) either manually or automatically activated on fire detection. Passive Fire Protection, by means of intrinsic safety principles (e.g. adequate spacing between equipment, containment by bunds or kerbs, drainage) or barriers/coatings on structures, which provides protection against heat transfer. Page 117 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Note: FEED requirements for active/passive fire protection have been developed in accordance with the preliminary FERA and shall be updated according to the final FERA to be carried at the EPC phase. 6.11.1 ACTIVE FIRE PROTECTION REQUIREMENTS The general philosophy for Active Fire Protection systems design is to identify critical facilities and buildings requiring fixed fire protection systems and areas where mobile/portable fire fighting systems need to be provided in order to permit to operating personnel to control small fires. The fixed fire fighting system will be designed based on the assumption that only one fire at a time may occur in the plant; the requirements for fire extinguishing and cooling facilities will be then calculated for the worst possible fire scenario, according to standards requirements. Active fire protection systems shall also be designed and located taking into account environmental conditions (i.e. wind direction, atmospheric corrosion). 6.11.1.1 FIREWATER PROTECTION SYSTEM The firewater protection system as defined at the FEED stage shall be reviewed and verified by the CONTRACTOR to reflect the design development during the EPC and considering the results and the recommendation of the FERA and the other HSE studies (e.g. QRA, ). CONTRACTOR shall perform a design review of the fire fighting system at the end of the EPC phase. Note: for the design of the fire fighting system, CONTRACTOR shall take into account that the firewater flow rate is fixed since provided by the MLE plant firewater system. In case this value is exceeded, proper reduction measures shall be implemented. 6.11.2 PASSIVE FIRE PROTECTION REQUIREMENTS Passive Fire Protection is required where intense fire exposure can cause the collapse of equipment, the spread of burning liquids, and the loss of operability capabilities of critical systems. The aim of passive fire protection is then to avoid the escalation of the emergency, due to the collapse of heavy structures or equipment containing dangerous fluids (e.g. flammables). In particular, the purposes of passive fire protection are as follows: To prevent, within a specified time, the collapse of steel work supporting equipment containing flammable materials via fireproofing. The release of such materials would increase the intensity of a fire and the problems and hazards of search and rescue and fire fighting (i.e. to limit the escalation of fire between adjacent fire areas). To protect safety critical equipment for a period sufficient to fulfil its function. As a minimum, fire resistant materials shall be provided as primary protection of: Structures directly or indirectly supporting significant hydrocarbon inventories or emergency systems. Structures supporting heavy loads which, where their failure would lead to a significant hydrocarbon release, or catastrophic failure, loss or damage to a control centre or emergency system; Class 0 hydrocarbon storage vessels or other plant that could fail catastrophically or lead to further significant releases. The requirements for passive fire protection coatings on structural steel will be based on an assessment of the implications for further loss of hydrocarbon containment following structural failure, and the durations of fires relative to the time necessary for structural failure to occur. FEED requirements shall be reviewed and detailed according to the results of the HSE studies to be carried out by the CONTRACTOR during the EPC phase. The extent of provision of structural passive fire protection shall take into account the hazard distances presented by credible fire scenarios, considering also the benefits of depressurization systems in reducing fire durations and hence heat doses to structures. Identification of fire Page 118 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 potential equipment, structures to be fireproofed and degree of protection shall be in accordance with API 2218 criteria and FERA results. Note: fireproofing shall be by means of in tumescent epoxy based paint only. 6.12 BUILDINGS SAFETY CRITERIA 6.12.1 BUILDINGS LOCATION Critical buildings (i.e. central/local control room, electrical substation, offices, etc.) should be located as far as possible from highly congested process units containing large amounts of flammable gases. Buildings should be located upwind from any potential hazard (e.g. fire, flammable or toxic gas source). If spacing criteria are not applicable/sufficient, a certain degree of protection shall be provided, according to international standard requirements and/or defined on the basis of risk assessment studies. CONTRACTOR shall demonstrate that no additional impacts have been generated from CAFC facilities on MLE CPF buildings. 6.12.2 BUILDING SAFETY DESIGN REQUIREMENTS Buildings that are permanently manned by plant personnel and/or that must remain operational shall be located/designed in such a way to protect personnel from the effects of accidental releases (i.e. explosions, fires or toxic concentrations).In addition to buildings location criteria and safety spacing, in order to limit the damage to these buildings in case of explosion and to guarantee a minimum protection without special additional requirements, the following minimum design criteria shall be considered: Buildings shall be supported by a steel or reinforced concrete frame; structural details should allow a large plastic deformation before collapse .Roofs and ceilings shall be designed such that they cannot easily collapse during an explosion; the structural integrity of the roof must not be endangered by damage to the supporting walls; Buildings should preferably be rectangular shaped and single storey with flat roof. The roof should not be charged with heavy equipment .Windows should be avoided, or their surface should be minimised and should be fitted with suitable glass .Doors, frames and fixings should ensure the same structural resistance as the rest of the cladding; In addition the following features shall be considered in building design, to allow a rapid and safe evacuation in case of emergency: Access to the building areas (e.g. doors) shall be located onto the side opposite from process areas; Emergency exit doors of buildings shall be equipped with anti-panic bars; Minimum door dimensions shall be 2.1m height and 0.9 m width; Doors from enclosed areas shall open outwards, in the direction of escape; No locking facilities shall be provided for doors along escape routes. 6.12.3 HVAC REQUIREMENTS All buildings shall be provided with an air conditioning system that shall ensure that the air quality is kept within acceptable limit values and shall have adequate cooling/heating capacity. All ventilation air intakes shall be located in non-hazardous areas and as far as possible away from any contamination sources. They shall be placed at high level and provided with high efficiency sand-trap louvers and bird screens. Page 119 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The openings should be located where the influence of the wind pressure is at a minimum. Openings for air intake and air/gas exhaust should be located so that exhaust air/gas cannot recirculate again through the air intake. Acceptable internal conditions shall be achieved for air temperature/humidity, air velocities, and air quality and noise level. The following data unless otherwise specified in the other project documentations should apply for the design of the HVAC systems, according to ASHRAE guidelines: Internal design conditions: 25°C with 50% RH Tolerances: ±1°C; ±10% RH Maximum working condition: 42°C with 100% RH Minimum working condition: 10°C with 100% RH Maximum final air velocity near person: 0.25m/sec Maximum ambient sound pressure level: 50dB(A) Internal overpressure: 25Pa In addition to the above requirements the HVAC system shall be provided with flammable gas detectors in the fresh air suction ducts. The HVAC system shall automatically close all fresh air intakes and exhaust outlets and operate in recirculation mode or completely shutdown the system in case of flammable gas detection at the air intakes. 6.13 STRUCTURAL DESIGN Accidental loads shall be identified and taken into account in the structural design. The probability, magnitude and potential consequences of identified loads shall be assessed and analysed. Loads caused by extreme weather, earthquake damage to structural elements (damaged condition) or extreme temperatures shall be considered. Explosion loads affecting structures and equipment shall be considered. Explosion loads shall be established by use of recognized computer models. 6.14 PLANT CONSTRUCTION Plant construction shall be taken into consideration during the design in order to minimize hazards to personnel, environment and damage to equipment during construction. A risk assessment associated with construction of the facility shall be carried out during the design phase in order minimize hazards during construction. Construction and SIMOPS HAZID studies shall be carried out by the CONTRACTOR at the EPC phase. The design should consider but not limited to the following: Injuries or damage caused by mechanical works such as cutting, welding, heavy lifts, transporting equipment, use of impact tools, exposure to pits/trenches and working at heights. The design should minimize site construction, e.g. vessels and columns should be delivered fully dressed. Exposure to hazardous chemicals or substances, e.g. pipe work preparation prior to painting, nucleonic testing of welds .Mechanical and electrical isolation requirements during construction and commissioning. Leak testing and pressure testing of piping and vessels. Cleaning and purging requirements prior to commissioning in order to remove any material that may create a hazard when hydrocarbon is introduced, e.g. oxygen. Page 120 / 180 Part D - Scope of Work 6.15 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 PERSONNEL SAFETY AND OCCUPATIONAL HEALTH To ensure plant operating personnel safety and health, various types of facilities and equipment for personal protection shall be provided and strategically located throughout the plant areas and buildings. 6.15.1 PERSONNEL PROTECTION Suitable personnel protective equipment (PPE) shall be provided for day-to-day operation and non-routine activity. The following non-routine activity and hazards should be considered: Vessel entry; Handling toxic and radioactive material; Protection from solar radiation; Welding, cutting, grinding, etc; Working at height. Walkways across pipes and working platforms on vessels and equipment shall be provided with non-slip surfaces. An adequate number of the following safety equipment, stored in a suitable ambient, shall be as minimum provided for personnel working in the plant area: Safety shoes; Polycarbonate helmets; Spectacles; Portable breathing equipment (with spare bottles); Thermo-reflective gloves; Thermo-reflective and fireproof blankets; Fireproof overalls; First Aid box/cabinet. 6.15.2 SAFETY SHOWERS AND EYEBATHS Safety showers shall be provided in all areas where direct contact with chemicals would be damaging or harmful to people, especially in chemical hazardous areas. They shall be equipped with eye wash fountains. They shall be readily accessible and immediately available in the event of an emergency. They shall not be obstructed or obscured from view in all directions. Where visual obstructions cannot be avoided, means shall be provided to indicate their locations. They shall use potable water only. After use the standpipe shall drain automatically. In principle, the following areas/buildings should be equipped with both safety showers and eyebaths: Methanol and other chemicals pump and injection areas; Glycol storage, handling and boiler areas; Laboratory; Process utility area; Strategic locations within process areas; Workshops; Battery rooms. These emergency units shall be connected to potable water supplies, and designed to ensure the water is at a safe temperature for use, considering the possible direct exposure to sun radiation. They shall be fitted with suitable alarms to give indication of operation in control room. Portable eye washes shall be provided also inside the battery room. Safety showers and eyebaths shall be clearly indicated and easily accessible. Page 121 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 6.15.3 SAFETY SIGNS Warning and safety signs shall be provided to warn people of hazards and the need for protective equipment throughout the facility. The signs shall be clear, easy to understand and consistent throughout the facilities. Warning symbols shall follow CONTRACTING AUTHORITY and internationally recognized standards. Wording will be in Arabic, English and French. They shall indicate: Prohibited activities (e.g. no smoking) ; Warnings (e.g. hazardous chemicals); Mandatory requirements (e.g. helmets must be worn); Location of fire-fighting equipment; Location of personnel safety equipment; Locations of manual alarm call point. Readily visible windsocks shall be provided inside the plant, as an aid to determine direction of any gas cloud during a release and to assist in escape route planning. 6.15.3.1 MARKING AND ILLUMINATION OF ESCAPE ROUTES Doors and hatches for emergency exits shall have illuminated signs carrying the words “EMERGENCY EXIT” and “NOT TO BE OBSTRUCTED” in French, English and Arabic. Escape routes shall be provided with adequate battery powered emergency lights signs or outside with electro luminescent direction signs. Plans shall be positioned around each area, which shall: Show the location of escape routes; Show manually operated fire-fighting equipment; Be easy to read; Be robust in construction; Provide instruction of actions to be undertaken in the event of an emergency or on hearing the respective alarms. Escape ways shall be provided with non-slip surface. Anywhere where oil or other spillage might occur, Self-drained grating shall be provided. Escape routes shall be clearly identified. Plans shall be displayed throughout the plant and shall: Show the location of escape routes, Show location of safety, fire-fighting and survival equipment; Be easy to read; Be robust in construction. Safety and warning signs and operating instructions for safety equipment shall be provided throughout the complete facilities in Arabic, English and French. There are six basic categories of signs as follows: Fire fighting: those giving information/instructions with regard to fire prevention and fire fighting equipment; Mandatory: those giving instructions or information that must be obeyed or observed; Emergency: those giving information, which should be heeded to avoid possible dangerous occurrences; Warning: Those giving information, which should be heeded to avoid possible dangerous occurrences; Prohibition: those that prohibit a particular activity; General: those that convey general information of a non-critical nature not covered by the five categories above. Road and traffic signage shall comply with Algerian Regulation. Page 122 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 6.15.4 MEDICAL FACILITIES A medical facility is foreseen at the Base de Vie (MLE) for the treatment and stabilisation of personnel who may become injured or ill as a result of an accident or illness. First aid boxes shall be installed in plant control room, operator shelters, buildings, workshops and stores. First aid boxes suitable for electrical injuries also shall be provided in electrical substation. 6.15.5 MACHINERY GUARDS All exposed moving parts on all machinery shall be suitable guarded to protect personnel from injury. Guards and safety devices provided shall be well maintained and kept in position whilst machinery is running. 6.15.6 MANUAL HANDLING Manual handling requirements shall be minimized or suitable facilities provided to prevent hazard/injury to personnel. The areas for consideration shall include but not limited to the following: Mechanical lifting facilities should be provided for weights that may injure personnel. Minimize handling of hazardous substances; provide bulking handling facilities and suitable personnel protection. 6.15.7 ELECTRICAL SAFETY KIT Electrical safety kits shall be provided inside local and central control rooms and electrical substation. 6.15.8 HOT AND COLD SURFACES/FLUIDS Appropriate design measures shall be taken to protect against injury from hot or cold equipment that has an external surface temperature that may be hotter than +70°C or colder than –10°C, and may in normal operations be touched by personnel. The design measures may include the use of insulation or guard barriers. The design should not rely on personnel wearing gloves or other PPE, except for items such as handrails, which may exceed 70°C due to solar heating, and where the use of insulation would be impractical. 6.15.9 HAZARDOUS MATERIALS STORAGE AND HANDLING A hazardous material inventory shall be maintained. This shall include all flammable materials, corrosive or toxic substances and any radioactive materials which are to be stored permanently or temporarily at the installations. Recommendations for the storage of the materials identified in the hazardous material inventory shall be made, according to their nature. Paints and flammable materials shall be stored as far as it is practicable from other hazardous areas. Corrosive or toxic chemicals shall be stored in suitable containers, marked with warnings and precautionary measures. No asbestos to be employed in buildings, thermal insulation or gaskets Ceramic fibre insulation should be avoided because of its relatively high pulmonary biopersistence. This requires that workers wear BA sets when working the material in order to comply with the occupational exposure limits. Adequate PPE shall be provided and worn by the operators during hazardous materials handling operations. 6.15.10 MATERIAL SAFETY DATASHEETS (MSDS) Material Safety Data Sheets shall be provided for all chemicals, detailing all safety information for material handling and emergency response. MSDS shall be written in the spoken language of the people involved in their handling (as a minimum Arabic, English and French). Page 123 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 6.15.11 RADIOACTIVE MATERIALS Special consideration shall be given to handling of radioactive material, and use of radioactive material shall be minimized. Formal procedures shall be developed and used whenever radioactive materials are brought into the field, or onto the site, e.g. for radiography of equipment or pipelines. Radioactive materials or equipment shall be manipulated only by certified personnel and shall be handled under strict procedures. These procedures shall be written in the spoken language of the people involved in their handling (as a minimum, Arabic, French and English). 6.15.12 TENORM The primary radio nuclides of concern in petroleum industry TENORM are radium-226 (Ra-226), radium-228 (Ra-228) and their associated progeny. The waste streams most likely to be contaminated by elevated radium concentrations include (i) produced water, which is formation water that is brought to the surface along with the produced oil and gas; (ii) scale, which is a hard, insoluble deposit that accumulates on the surfaces of equipment and solid debris that come in contact with produced water; and (iii) sludge, which is a slightly granular, usually hydrocarbon-rich deposit that accumulates in the bottom of some storage and process vessels. The evaluation of TENORM impact in water management shall be considered. It is important that systems for water treatment and waste disposal will investigate options before installing water treatment. If possible, pilot tests are a good way to determine how much waste the system will produce and whether the system will be able to dispose of the amount, concentration and type of waste. 6.15.13 PROHIBITED SUBSTANCES The use of certain materials is restricted, including but not limited to: Asbestos 2-naphthylamine 4-aminobiphenyl Benzidine and related salts 4-nitrodiphenyl Carbon tetrachloride CFCs (chlorofluorocarbons) Cadmium Compounds Halogenated Hydrocarbons Mercury compounds PCBs (Polychlorobiphenyls) And other compounds based on the above Arsenic compounds Benzene Bitumen Chloroform Hexavalent chromium (VI) and chromates Ethylene glycol monoethyl ether (2- Ethoxyethanol) Ethylene glycol monoethyl ether (2- Ethoxyethylacetate) Ethylene glycol monomethyl ether (2-Methoxyethylacetate) Formaldehyde n-Hexane Isocyanates Lead compounds Methane dichloride Nickel compounds Trichloroethylene Page 124 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 1,1,1-Trichloroethane 6.16 ENVIRONMENTAL STANDARDS Regulations applicable to CAFC project facilities include international, national and any other requirements. All projects undertaken in Algeria are subject to all national environmental legislation and all international legislation to which Algeria has ratified and/or signed. All the emissions from the facilities shall meet, the requirements to ensure the control of pollution caused by facilities activities. The aim shall be to minimize wastes and other gaseous or liquid emissions categorized as follows: Air emission; Waste water discharges; Soil contamination and groundwater protection; Solid and liquid waste management; Spills. It also shall be taken into account: the mitigation of noise and vibrations sources, to improve working conditions across every plant areas; the evaluation of terrestrial impacts and project footprint. 6.16.1 PROJECT ENVIRONMENT REQUIREMENTS CONTRACTOR shall update during the EPC phase the project environment requirements document developed during the FEED according to the results of the project ESHIA, therefore submit it to the CONTRACTING AUTHORITY for review and approval; the scope shall cover all areas of wastes limited to emissions to air, effluent discharges, solid waste and sludge and noise. In additions the report will address occupation health and occupational noise limits ensuring that they are never reached. It also shall be taken into account the mitigation of noise and vibrations sources, to improve working conditions across every plant areas and minimize the impacts outside the plant fence. All environmental parameters which characterize the emissions from the plants shall comply with the limits detailed in local laws and recognized international standards, as detailed in the following sections. 6.16.2 NOISE CONTROL CONTRACTOR shall ensure that all equipment meets the noise requirements specified in the FEED package in Annex I – “Technical”. CONTRACTOR shall update the equipment noise data sheets as necessary prior to issue of the equipment packages for enquiry, to achieve the overall noise limitations for the facility. CONTRACTOR shall provide Acoustic Insulation as necessary to meet the overall facilities noise criteria. CONTRACTOR shall also carry out noise and vibration studies throughout the design to ensure that sound levels do not exceed those permitted and that no acoustic „vibration‟ could occur and propagate to impinge upon the integrity of structures and equipment to the detriment of the facility and Plant Safety, Operability and Reliability. Page 125 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 A noise and vibration survey shall be carried out on site by the CONTRACTOR to confirm that the design intent has been achieved. CONTRACTOR shall be responsible for any corrective actions resulting from the noise survey. Page 126 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 7. MATERIALS PROCUREMENT AND MANAGEMENT 7.1 GENERAL The Contracting Authority has a contractual responsibility and an obligation to give priority to Algerian goods and services insofar as their price availability and performance shall be competitive in relation to those of a similar nature, which can be provided by non-Algerian businesses. Whereby competitiveness shall be evaluated according to the following criteria: For the providers of services: Experience in Algeria and/or other references, implemented technical resources, speed of performance of services, competence of staff employed, price of service for provision in Algeria. For product suppliers: Quality of products, equipment and goods supplied, price for delivery of goods in Algeria, speed of delivery. The Contractor is advised that the Contracting Authority consider it a condition precedent that the Contractor provides the same obligation. 7.2 SCOPE The Contractor shall be fully responsible for all work associated with the procurement of all Materials and Equipment. This includes all work necessary for the Contractor to make an award to a Contracting Authority approved Supplier as attached in Annex VIII – “List of Subcontractors and proposed Suppliers and Vendors” of the Contract preparation of Drawings and Specifications, preparation of bid lists, preparation of bid packages, bidding, bid evaluation including clarification meetings, awarding, scheduling, Supplier kickoff meetings, approval of Supplier documents, expediting, inspection, witness testing and acceptance, transportation, receiving inspection, commissioning, data books, as-built Drawings, etc. Bid Evaluation Procedures shall be subject to approval by the Contracting Authority. Award of all major equipment items to be defined by Contracting Authority shall be subject to Contracting Authority approval. 7.3 PROCUREMENT ORGANISATION The Contractor shall establish a Procurement and Materials Management Team for the Contract, led by an experienced Materials Manager or equivalent that is responsible to the Contractor‟s Project Manager for all Supply Management and supply activity (ref. Annex XIII – “Quality Plan”. The team shall comprise procurement professionals deemed appropriate for procurement, expediting, delivery, care, management and certification of all Materials and Equipment, including consumables, used in the supply and construction of the works. It shall include Head Office Team Members, local procurement officers and remote international expediting and inspection resources as required. If the Contractor proposes to source Subcontract Personnel to support the Teams, then the organisation presented shall include those Personnel. Page 127 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 7.4 PROCUREMENT METHODS AND PROCEDURES The Contractor shall prepare Project specific procedures for procurement based on the Contractor‟s corporate standards, which encompass all purchasing and materials management activities, progress assessment and reporting, materials identification and tracking. However, Contractor shall comply with the minimum requirements of the Contracting Authority procedures. The Contractor shall detail the procurement strategy, plan and procedures to be followed to enable monitoring of progress and material cost. The Contractor shall detail the Procurement Policy including the items listed below: Local and International Procurement offices Project procurement organisation Authorisation levels Proposed country of source, including level of procurement from Algerian Suppliers. Procurement of all equipment and bulk materials shall be subject to Contracting Authority review. Contracting Authority shall be copied on all correspondence and be given the opportunity to participate in all technical meetings between the Contractor and the Supplier. Contracting Authority shall also have the right to review the technical sections of the Supplier‟s bid along with the Contractor‟s technical bid evaluation. 7.5 APPROVED SUPPLIERS LIST An Approved Suppliers List is included in Annex VIII – “List of Subcontractors and proposed Suppliers and Vendors” of the Contract. This shall be used for the procurement of all equipment and bulk materials. This list also applies to Suppliers for Packaged equipment. The Contractor shall include these Suppliers on bid lists for Materials and Equipment. The addition of Suppliers not currently shown on the list shall be subject to the review/agreement of Contracting Authority. The Contractor shall request additions to the approved list at least two weeks in advance of issuing the bid package to Suppliers. The following categories from the approved project listing are deemed to be “Key Subcontracts”: Surface Facilities, Prefabrication, Construction and Installation Civil works and Roads Buildings Metallic Structures Inland Freight Ocean Freight Medium and Low voltage switchboards, DCP and UPS panels Transformers Distribution boards Integrated Control Systems Package (ESD/DCS/F&G) Page 128 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Control Valves Manual Valves Relief Valves Choke Valves Mechanical HIPPS Valves Wellhead control Panel / HPU Flow control butterfly Valves Emergency Power Generation Flash Gas Compressors Gearbox Couplings Shaft Seals Centrifugal Pumps Other API Centrifugal Pumps Booster and Export Pumps for Oil (to be purchased from the same supplier as for MLE) Pumps general service/Chemicals Water Injection Pumps Oil Stabilisers, Oil Desalters (electric precipitators) Separators Pressure Vessels, General Scrubbers Column Trays LT KO Drums (SS) Gas Dehydration Package Off spec Storage Tank (Oil ) Produced Water Treatment Package Flare Package Heat Exchangers Pipelines Additionally, the following categories of equipment are “Principal Equipment” and as such the agreed vendor list for these items are deemed to be frozen for the duration of the EPC Contract and no amendments or additions will be considered: Integrated Control Systems Package (ESD/DCS/F&G) Flash Gas Compressors Gas injection compressors Page 129 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Booster and Export Pumps for Oil Oil Stabilisers Oil Desalters (electric precipitators) Separators LT KO Drums (SS) Control Valves Safety Valves Manual Valves (Insulation Valves) 7.6 BID PACKAGES The Contractor shall ensure that all equipment bid packages include a reimbursable element for training of Contracting Authority Personnel by the Supplier, either at the Construction Site or at the nearest Supplier location (whichever provides the lowest overall cost for training). Contracting Authority shall be consulted for agreement on this prior to contract award. For those courses at the Construction Site, the Contractor shall provide suitable training centre. Enquiry documents for shall be subject to review by Contracting Authority prior to issue. Contractor shall prepare an un-priced bid tabulation and recommendation for Contracting Authority‟s review and approval for major equipment. Contracting Authority reserves the right to approve or disapprove the selected Supplier. Un-priced Purchase Orders for shall be subject to review by Contracting Authority prior to commitment. The Contractor shall make use of Criticality Assessment Programmes to assess and specify inspection, quality control and test requirements for all items ordered. The Contractor shall conduct all necessary technical clarifications of the bids and shall hold clarification meetings with Suppliers to enable Supplier designs and the Contractor‟s design to be efficiently integrated. The Contractor shall ensure that all equipment bid packages include for the provision of all necessary Vendor support at the Site during construction, pre-commissioning, commissioning and start-up. The Contractor shall obtain written guarantees from Suppliers that the appropriate level of support shall be provided at the Site, at the appropriate time. The vendor support requirements shall be stated in the Contractor‟s Execution Proposal. Due to the criticality of Vendor packages the Contracting Authority reserve the right to review and confirm suitability of Vendor proposed representatives for key packages. 7.7 SUPPLIER QUALITY MANAGEMENT The Contractor shall develop a plan for the control of Suppliers‟ goods and services, in accordance with this Scope of Work. 7.8 SUPPLIER INTERFACE MEETINGS The Contractor shall schedule periodic Supplier interface meetings appropriate to the work scope for each Supplier, which shall be used as a basis for progressing and reporting Page 130 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Supplier status. The Contractor shall issue minutes of these meetings and these minutes shall be held in the Order File. All minutes shall be subject to Contracting Authority informal audit at any time. The Contracting Authority‟s Representatives shall be notified of, and invited to, all Supplier interface meetings at least seven days in advance. 7.9 MATERIALS STATUS REPORTING The Contractor shall develop and implement a system for reporting status of all materials progress. Each Purchase Order shall be tracked from Bid Evaluation, Placement of Order, manufacturing sequence to delivery to Construction site. The Contractor shall prepare and issue, as a minimum, the following weekly materials status reports: Procurement package/Purchase Order status report(s) detailing the current progress/status of all activities up to, and including Purchase Order award. This is to cover the full listing of all category(s) of materials that the Contractor is directly responsible for. Expediting and Inspection Status report(s) covering all activities after Purchase Order award. This is to cover expediting status by line item and Inspection status by line item. Traffic/freight status by line item, showing status and location up to receipt at the Contractor‟s storage yard. Material identified as surplus or scrap. On receipt of material at the construction site, the Contractor shall log all material received and prepare a register of all Materials and Equipment identifying the purpose or intended purpose of the material. 7.10 INSPECTION AND EXPEDITING The Contractor shall implement an inspection and progress monitoring programme. The Contractor and Contracting Authority shall jointly agree on the inspection required for the equipment items. The Contractor shall be responsible for all costs associated with Supplier inspection and progress monitoring program. The Contractor shall invite the Contracting Authority representative to participate in all major package pre-inspection meetings Contractor shall ensure that it package equipment engineers maintain status involvement and are responsible to ensure all aspects of expediting are maintained. The Contractor shall submit resumes for the proposed Supplier inspectors to Contracting Authority for approval. If, after a period of time on the job, at the Contracting Authority sole discretion, Contracting Authority determines that an inspector is not suitable for the work the inspector shall be replaced. The Contractor shall ensure that all the inspection requirements of the Algerian regulatory bodies are met. This shall include but not be limited to any necessary payments and coordinating visits to design offices, construction sites and supplier locations. Algerian regulatory bodies include but are not limited to DPEM, CTC, ARPT, ARH and ONML. Page 131 / 180 Part D - Scope of Work 7.11 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 PROTECTION, PACKING, MARKING AND SHIPPING REQUIREMENTS The Contractor shall prepare and issue with all orders for equipment a specification for adequate protection and preservation of the equipment during transport to, and storage at, the construction site. Contractor shall develop Specifications to set out Contracting Authority‟s minimum requirements for handling, preservation and storage of equipment. The Contractor shall ensure that all Suppliers make specific offloading and storage recommendations within their bids, relative to the packaging offered. Such recommendations shall cover the maintenance and preservation during (a) storage and (b) following unpacking and after installation at site but prior to commissioning. The Contractor shall determine whether there is any requirement for long term preservation as a result of schedule delays. The Contractor shall ensure sufficient resources and consumables are available for this purpose, if deemed necessary. Consistent with Algerian regulations, the Contractor shall ensure that „Release dossiers‟ are included with each shipment. These dossiers shall contain all documentation applicable to the shipment to allow the Contractor to immediately issue the equipment for installation. Suppliers shall be required to comply with all requirements associated with transportation of hazardous goods, including all Algerian regulations and those in force in the countries of origin and transit. 7.12 SUPPLIER DOCUMENTATION A Supplier Data Requirements list shall be included as part of each bid package and purchase order or contract. The Contractor shall ensure that all Supplier documentation is received in a timely manner in order to ensure input to design, construction, Mechanical Completion and Commissioning procedures. The Contractor shall deliver final certified equipment dossiers (MDR‟s) for all equipment. 7.13 CUSTOMS CLEARANCE The Contractor is responsible for Custom Clearance at point of entry to Algeria and shall prepare all necessary manifests and information required for custom clearance in respect of all Materials and Equipment. The Contractor shall be responsible for all costs incurred as the equipment passes the ships rail at the port of entry to Algeria including taxes, customs duties, agents fees/ commissions, port fees, handling, mooring, storage, transportation to the CONTRACTOR‟S storage yard, as well as any other applicable charges except as excluded in the terms of the Contract. Upon receiving items the Contractor shall immediately check all documentation, unload, inspect, report any damage, and properly store the equipment. Any damage identified after the Contractor‟s receiving inspection may be for the Contractor‟s account. Page 132 / 180 Part D - Scope of Work 7.14 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 SPARES 7.14.1 General The Contractor shall be responsible for the procurement, expediting and delivery of all spares for Contractor procured equipment to the Contracting Authority warehouse facility at MLE. Spares delivered prior to the completion and handover of the warehouse shall remain in Contractor care and custody until they can be stored in the Contracting Authority warehouse. The Contractor shall request each Supplier to include a clause, which limits the allowable escalation of costs for spares for 10 years following the placement of the Purchase Order. 7.14.2 Insurance Spares The Contractor shall review the master equipment list and recommend insurance spares for equipment to Contracting Authority. The requirement for insurance spares shall be advised by Contracting Authority, following consideration of the Contractor‟s recommendation. The respective orders for equipment placed by the Contractor shall include an option for the supply and delivery of those insurance spares on the understanding that the order for the spares may be assigned to Contracting Authority within six months of order placement by the Contractor. The Contractor shall be reimbursed third party Supplier documented cost (e.g. Purchase Order value) for the spares from the Provisional Sum Price. All other costs required to purchase the spares are deemed to be included in the lump sum Contract Price. Contractor shall be responsible for the procurement, expediting and delivery of all spares to Contracting Authority‟s warehouse at MLE. 7.14.3 Operating Spares The Contractor shall include in the commercial offer the cost of the recommended two year Operated Spare Parts as a Provisional Sum and identify this as a separate price. Contracting Authority intends to use the higher price of the EPC Tender offer for spares in the final price comparison between the two contractors. Contracting Authority shall endeavour to advise the Contractor the requirements for Operating Spares within 12 weeks of receipt of the list so that the Contractor can place orders for these spares. The recommendations shall be detailed by completing the SPIR form. It is the responsibility of the Contractor to ensure SPIRs are accurately completed. The SPIR form should be completed in accordance with Contracting Authority requirements (Procedure Sonatrach de Codification) and implemented to Computerized Management System as described in Annex XII “CAFC plant Operability and Maintainability requirements for EPC Contractors”. The Contractor shall be reimbursed third party Supplier documented cost (e.g. Purchase Order value) for the spares from the Provisional Sum Price. All other costs required to purchase the spares are deemed to be included in the Contractor management costs. The Contractor shall be responsible for the procurement, expediting and delivery of all spares to Contracting Authority‟s warehouse at MLE. Page 133 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 7.14.4 Commissioning and Start-Up Spares The Contractor, shall instruct all Suppliers to provide costs for Commissioning and Start-Up spares for the facilities. Therefore it shall be the responsibility of the Contractor and Suppliers to ensure sufficient spares are retained on site to Commission and Start-Up the facilities and equipment, any/all commissioning spares not used shall be provided to Contracting Authority. All Commissioning and Start-Up spares shall be provided by the Contractor as part of Contract Price Lump Sum. 7.14.5 Cataloguing Spares The Contractor shall catalogue all procured spares in a form compatible with the Contracting Authority‟s chosen computerised maintenance management system (CMMS) 7.15 SPECIAL TOOLS The Contractor as part of the Materials and Equipment supply shall provide special tools for the installation and maintenance of Materials and Equipment as part of Contract Price Lump Sum. 7.16 LOGISTICS The Contractor should provide a plan with its tender in Schedule 13 of the ITT on how it shall develop a logistics strategy and execution plan to be agreed by Contracting Authority and form part of the Contract in Annex II – “Extent and Limit of Supplies and Services”. This should cover: Plans for Air, Sea and Road transportation of materials to Algeria Inland transportation of materials and transportation of Personnel Freight Forwarding and customs clearance The logistics organization Material packaging handling and inventory control procedures Supply base/warehousing equipment and facilities How you intend to interface with the appropriate Algerian authorities at all levels Opportunities for cost saving by sharing with other Projects Page 134 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 8. TECHNICAL INTEGRITY MANAGEMENT 8.1 MANAGEMENT SYSTEM The Contractor shall submit a preliminary Technical Integrity Management plan with his bid documentation. The proposed system shall ensure effective technical management and technical integrity compliance whilst ensuring that optimum value solutions are adopted. The system shall fully satisfy the CAFC Project HSE Requirements included in this document and Annex XI – “Health, Safety and Environment” of the Contract, and meet the requirements of: ISO 9001, 2008, “Quality Systems - Model for Quality Assurance in Design/Development, Production, Installation, and Servicing”, ISO 9004-1, 2000, “Quality Management and Quality System Elements - Guidelines”, ISO14001 2004 “Environmental Management Systems.”, OHSAS 18001:1999 Amendment 2002 “ Occupational Health and Safety Management Systems” Implementation shall be in accordance with the Contractor‟s standard management systems, which include Quality, Safety, and Environmental Systems and shall be fully detailed in a project specific Technical Integrity Plan. The System detail and an outline of the Integrity Plan should be included within the Contractor‟s Execution Proposal in Schedule 5 of Part B1 of the Schedule and to form part of Annex XVI – “Contract Administration Manual” of the Contract. The system shall provide for the planned and systematic control of all Technical Integrity related activities performed during Design, Procurement, Construction, Pre-Commissioning, Commissioning and Start-Up. The Contractor‟s System Manuals and particularly the Integrity Plan together with all related/referenced procedures shall be submitted to the Contracting Authority‟s Representatives for Review, Comment and APPROVAL. The Contractor shall provide evidence from an Accredited Certification Body of their proposed System Certification or a recent compliance audit report and attestation from a Contracting Authority‟s approved (third party) auditing body confirming Quality System Compliance. ISO Accreditation or Compliance evidence must be submitted within the Contractor‟s Execution Proposal to form part of Annex XVI – “Contract Administration Manual” of the Contract. The Contractor shall ensure that all major Subcontractors and JV Partners have Systems which comply with this section and that they are seamlessly interfaced for the Project. Contractor shall supply details on how any major Subcontractors or JV Partners shall comply with the overall Technical Integrity Management Requirements within his Execution Proposal in Schedule 5 of Part B1 of the Schedule and to form part of Annex XVI – “Contract Administration Manual” of the Contract. Page 135 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 8.2 INTEGRITY PLAN The Integrity Plan shall include: a) Narrative details of how the Contractor interprets the individual technical integrity elements of ISO 9001/ 9004, ISO 14001, BS 8800, this Section of the Scope of Work and the HSE Section of the Scope of Work for the application of the Project work scope including the controls and verification to be put in place to assure Integrity during each stage of the design, procurement, construction, Pre-Commissioning, Commissioning and Start-Up. b) Detail in a matrix format how the Contractor‟s system addresses the detail noted above. It should reference responsible parties within the Contractor‟s organisation for the implementation/control of each area, the applicable procedures used to control/assure each area and the verifying documents produced for each area (see Figure 1 for sample format). Combination of „a‟ and „b‟ is acceptable if the narrative detail is included in the Matrix. Plans shall be developed for the full CONTRACT SCOPE and shall be included within the Contractor‟s Execution Proposal in Schedule 5 of Part B1 of the Schedule and to form part of Annex XVI – “Contract Administration Manual” of the Contract. The Plan shall detail co-ordination, control and assurance of all interfaces, including JV‟s and multiple sites. 8.3 SYSTEM REQUIREMENTS This section describes the Contracting Authority specific requirements/ interpretations that shall be incorporated into the appropriate sections of the Contractor‟s standard Management Systems for the Project. 8.3.1 General The Contractor‟s Management Systems shall cover all management aspects and shall impose the same requirements on Subcontractors and suppliers. The System shall ensure the work as a whole is included, from Project initiation to completion of Start-Up. This shall include: Review and monitoring of the Systems by an independent Quality Assurance organisation, within the Contractor‟s organisation, staffed with sufficient resources to perform the work. Details of the organisation and proposed resources for this Project shall be submitted to the Contracting Authority‟s Representatives together with the CV‟s of QA Managers and QC Managers for home office. A well defined and documented policy signed by the most senior Contractor management, and demonstrating the Contractor commitment to the Project Integrity requirements shall be issued. This policy statement shall be included within the Contractor‟s Execution Proposal in Schedule 13 of Part B1 of the ITT and form part of the Contract in Annex II – “Extent and Limit of Supplies and Services” Page 136 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Methods of performing Project planning in accordance with the Contract requirements. As a minimum, procedures shall identify the responsibility for each design and construction activity and provide a mechanism for the timely production of all working procedures and discipline interfaces necessary to fulfil the specified requirements and to meet the Project work schedule. Details of provisional procedures should be included within the Contractor‟s Execution Proposal in Schedule 13 of Part B1 of the ITT and form part of the Contract in Annex II – “Extent and Limit of Supplies and Services”. Document Control Procedures to control status and ensure only the latest approved revision of documents are available for work. Procedures and instructions for the control and verification of design documents and design activities, including design review, design verification, any required design validation and design changes at the home office and field office. A copy of the Contractor‟s standard procedures for the home office shall be submitted to the Contracting Authority Representative. Methods for setting staff and workforce competence levels, selection, and training. This shall include setting qualifications and experience for professional staff as well as setting qualifications, experience and if necessary trade testing for technician and construction craft staff. Implementation of Audit programmes. 8.3.2 Specific Points to be addressed in the Technical Integrity Plan a) b) c) d) The Basis of the Engineering Design Detail including environmental requirements, special local design requirements, statutory requirements, base specification and codes of practice to be followed for each discipline. Risk / criticality assessment and management plans. Philosophy for the control, review, verification and validation of design documents and design activities, including design changes at the home and field offices. Design Deviation procedure detailing reason for proposed deviation, drawings and documents/specifications affected, technical justification, cost impact and schedule impact. System shall ensure that all design deviations can be cross-referenced to the appropriate Construction Completion sub-section and input into a Construction Completion database to ensure closure prior to final sign off. It should also be noted that: A design deviation, approved by the Contracting Authority, shall be required for all changes to the Contract specifications or where Contracting Authority has approved the original design documents. Page 137 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Field design change system shall be utilised for all design changes after any document/drawing has been issued for construction. The change control procedures shall address the following points: The technical integrity of facilities and equipment Accountability for approving changes within Contractor and Contracting Authority. a level of evaluation which is proportionate to the risk acquisition of required permits alterations to operating procedures and design documents communication of potential consequences and action required time limitations personnel training requirements Re-HAZOP of changes and HSE Stage review Cross reference to Construction Completion System number The change control procedures for the home and field offices shall also cover all temporary design changes and ensure that execution time is managed and they do not exceed the approved scope or time limitation. e) f) g) h) i) j) 8.3.3 Procedure for developing Inspection and Test Plans (ITP‟s) including format and requirements. Philosophy and plans for performing internal audits of quality related activities and external audits of suppliers and Subcontractors. Methods of identifying, performing, and documenting competence and training on the Project. Strategy to be followed during Construction including development of method statements and construction ITP format/requirements. Methods for planning, controlling and verifying Construction Completion of the Work to the specified requirements, including Handover Certification requirements. Strategy for the control and delivery of Contractor‟s design, Supplier and construction drawings / records, operation/ maintenance manuals and certification. This shall include how all of these documents shall be compiled, numbered and indexed to match the Project standard numbering system, the medium (paper/ electronic) they shall be provided in and the number of copies that shall be handed over to the Contracting Authority. Development of Constructability, Operations and Maintenance Philosophies taking into account Contracting Authority life cycle costs. Specific points to be addressed by the Contractor Contractor shall ensure that the following points are addressed in its Project and Construction Execution Plans submitted in Schedules 13 and 14 of Part B1 of the ITT and to be inserted in Annex II – “Extent and Limits of Supplies and Services” a. Implementation of all strategies identified in Section 7.3.2 Page 138 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 b. Methods for ensuring that purchasing documents contain all necessary commercial, technical, and quality requirements and data. c. Optimisation of risk/criticality assessment. d. Procedures and methods for verification of purchased Materials and Equipment, and services by inspection, surveillance, and compliance audit. The procedures shall provide for interfaces necessary to co-ordinate with the Contracting Authority representatives. Note Contracting Authority intends to undertake a limited audit approach over Supplier activities. e. A procedure for identification, reporting, tracking and resolution of non-conformance‟s in the Supplier shops and at construction sites. These shall be database cross-referenced to the construction completion database to ensure closure before sign off. f. Field Non-conformance Reports (NCR‟s) shall require field Concession Requests to be raised where equipment is repaired (i.e. not in a new condition) or accepted in a condition which does not meet the design specifications. Contracting Authority APPROVAL shall be required for all Concession Requests. g. Procedures for the control, storage, and maintenance of material or equipment supplied by the Contracting Authority. h. Methods for the qualification, process control and documentation of all construction activities to meet the specified technical, safety and quality requirements. This shall include developing specific procedures/method statements, detailing how, what and where an activity shall be performed together with the responsible persons and the verifying document produced. This shall take into account the output from the documented design review clash check, maintainability and constructability reviews etc. i. Methods for inspection and testing of material and equipment at the storage and construction sites. j. Finalisation of procedures for the control of field design changes as detailed above. k. Methods for the control, storage, and calibration of inspection, measuring, and test equipment. l. Methods for tracking inspection and test status of Materials and Equipment. m. Procedure for documenting and controlling corrective action. n. Procedure for the handling, storage and preservation of Materials and Equipment. o. Methods for control, storage and handover of spare parts and associated documentation. p. Procedures for the identification, control and documentation of specialist Supplier representative work scope at the field during Mechanical Completion and Commissioning activities. q. Implementation of the QC systems. r. Implementation of the Mechanical Completion systems. 8.3.4 General Notes to System Requirements Where the word „documented‟ is included here and in the ISO/ BS series, written procedures/work instructions shall be in place to direct and control the Work. Where Joint Ventures are involved at any stage, specific details shall be provided to demonstrate how the individual quality systems and technical management systems of different JV members shall interface and efficiently work together. The overall Technical Integrity Plan and related procedures shall be approved within one month of Contract Award (to a minimum level of „approved with comments‟). Page 139 / 180 Part D - Scope of Work 8.3.5 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Risk Assessment and Management Programmes In order to assure all the design and specification areas are addressed and meet the requirements of MLE Project HSE Expectations, ISO 9001:2008 Section 4.4/ISO 9004-1 Section 8.0, the Contractor shall carry out a full assessment exercise on every discipline area/system to enable individual Integrity programmes to be developed. This shall include all aspects and items. The Contractor shall develop or provide his standard proven procedure for assigning risk/criticality ratings. This should be a formalised technique for measuring the relative importance to be assigned to a specific area based on the risk/consequence that failure would have on health, safety, the environment or the construction operational integrity or Project delivery. The system should include provision for engineering judgement and review of the proposed ratings. The procedure should include aspects such as: Occupational safety Technical safety / integrity Environmental impact Operational significance Availability and accessibility for repair / replacement Design maturity Complexity of manufacture / construction / installation Economics Delivery impact on schedule A draft assessment procedure, or previous example shall be submitted to Contracting Authority‟s Representatives. Contractor shall also submit suggested criticality ratings for all major items of equipment. The results of the risk assessment shall be used to develop the minimum assurance and Integrity Management requirements to be applied during design, procurement and construction activities for each level of assessed risk/ criticality. It should be noted that this shall involve higher level of control above standard code requirements for high risk/ criticality areas and may involve upgrading requirements from other areas of the Contract. Where the Contract requirement is higher than the calculated Risk the Contract shall normally be applied. The Contractor shall develop Integrity programmes for every work/discipline area during engineering. The programmes shall be approved by the Contracting Authority‟s Representatives. The Contractor shall provide, within his execution proposal, the proposed Integrity programme samples for each risk/ criticality level (typically 1, 2, 3 and 4 where 1 is the highest level). These programmes shall cover the following areas, identifying the individual controls to be implemented for design, procurement and construction. The proposed programmes should cover as a minimum: Structural / Civil Engineering Page 140 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Rotating Machinery Piping Pressure Vessels Electrical Systems (including field equipment) Instrument Systems (including field equipment) Packages 8.3.6 Audits Throughout all stages of the Contract, the Contractor shall develop an internal and external system and technical compliance audit programme for the Contracting Authority approval. This shall include as a minimum an audit of every section/discipline of the Project against CAFC Project HSE Expectations in Annex XI – “Health, Safety and Environment”, ISO 9001/9004, ISO 14001, BS 8800 the Project environmental and safety system and the approved Project procedures and specifications. Copies of all audit reports and corrective actions shall be handed to the Contracting Authority‟s Representatives in a timely manner. Where deficiencies are identified, follow up audits shall be required to address them and confirm close out/compliance. The audit programme shall be issued within 1 month of Contract award, and shall cover as a minimum the programme for the first 3 months. A rolling programme shall be re-issued on a regular basis thereafter every 3 months. A draft of the proposed Contractor‟s audit programme shall be submitted within the Contractor‟s Execution Proposal in Schedule 5 “Project Management and Controls/Progress Management” of the ITT. Follow up audits shall be conducted at regular intervals on key areas in accordance with the approved audit programme. Contracting Authority shall have the right to conduct their own independent Technical, Safety, Environmental, Quality and Commercial audits. The Contractor shall make available all necessary staff and resources to assist the Contracting Authority in completing such audits in a timely and efficient manner. Contractor costs for this assistance shall be included within the Contract. Contracting Authority may achieve their aims for technical auditing by active participation of the Contractor‟s own planned technical audits. All High/ Medium Risk/ Criticality 1 and 2 Suppliers/Subcontractors shall have a compliance audit performed on them by the Contractor, except where Contractor can provide documented evidence of recent satisfactory audit or performance for the Contracting Authority approval. All criticality 1 and 2 Suppliers/Subcontractors must have previous audit records or quality verification evidence satisfactory to the Contracting Authority‟s Representatives before award of purchase order/subcontract. Where a Suppliers/Subcontractor proposes to subcontract more than 25% of any stage of the actual Construction (i.e. design, procurement, and manufacturing or construction stages) the same criteria as above shall be applied by the Contractor, except that the audit shall be a joint exercise with the main vendor/Subcontractor. Page 141 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 QC staff shall not be involved as auditors since they are not independent of the CONSTRUCTION and audits shall include an assessment of the performance/effectiveness of the QC function. 8.3.7 8.3.7.1 Quality Control General The Contractor shall have an independent QC organisation (independent from QA, construction and other line functions) within his overall organisation with sufficient resources to oversee the Construction. The Contractor shall provide details of his organisation, including the ratios of QC staff to construction staff for each discipline together with key quality control personnel CV‟s. The qualifications and competence of these personnel shall be subject to review and approval by Contracting Authority. The execution of vendor and field quality control shall be fully documented in procedures to be approved by the Contracting Authority. These shall include but not be limited to the minimum requirements included in the Contract, the Project specifications and approved quality programmes. No vendor or field construction work shall start without full approval of the relevant QA and QC procedures with all comments incorporated. 8.3.7.2 Supplier/Subcontractor QC For all activities, Inspection and Test Plans (ITP‟s) shall be developed and implemented by the Contractor, Subcontractors and Suppliers. These shall cover the following areas in a matrix format: Quality verification activity/stage Reference document/procedure or method statement to perform activity including specific reference to actual section/page Acceptance criteria Records produced The ITP shall cover the major quality related activities in chronological order from initial drawings through manufacturing/construction, process controls to final testing, documentation and certification. Against each activity/stage space shall be provided for all parties including the Contracting Authority to mark their QC involvement. . Contracting Authority shall have the right to review and approve all ITP‟s and procedures and add their comment/actual witness involvement. Contracting Authority intervention / witness shall be decided in accordance with risk/ criticality output. All Contractor Supplier inspection reports and release notes shall be made available to Contracting Authority, if/when requested. These reports shall typically include: Documentation approval status Problems/areas of concern Page 142 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 New and outstanding non-conformance‟s Detail reference to ITP stage Written detail of work performed and acceptability to acceptance criteria Contracting Authority shall have the right to witness any test. Where Contracting Authority have marked involvement on the ITP, written notice should be given 14 working days in advance and confirmation of the stage 72 hours prior to the actual activity. Contracting Authority shall also have the right to call for inspection hold points. The same conditions for notification shall apply. Contracting Authority however does not intend to specify hold points unless exceptional circumstances arise. Any delays due to late notification or late cancellation shall be borne by Contractor. Where materials are ordered and manufacturing is scheduled to start before full ITP approval, the Contractor shall ensure that as a minimum commented approval of relevant sections of the ITP is obtained prior to the work starting. The Contractor shall hold pre-inspection meetings (PIM‟s) with all high and medium risk/ criticality Suppliers/Subcontractors and on construction before any physical work commence. These meetings shall confirm that all technical points understood, the relevant documentation are approved, and that all QC activities to be undertaken are recorded on the ITP and understood. Third Parties should attend where they are to be involved in the inspection activities. Contracting Authority may also attend these meetings. 8.3.7.3 Supplier Release The Contractor shall put in place a release certificate scheme which identifies that all documents are approved, that there are no outstanding technical queries or concessions not fully closed out and that the release inspector is fully aware of the final approved document status. The release certificate shall be used as the trigger to allow the inspector to release the equipment AND Materials and Equipment if he finds the final inspection acceptable. A copy of this certificate shall be forwarded to the Contracting Authority‟s Representatives if/when requested. 8.3.7.4 Construction QC All activities shall be clearly defined in procedures/method statements, detailing the scope of work, how it shall be performed, where it shall be performed, who is responsible for the actual activity, which is responsible for verifying the activity and which record/verification document shall be produced. All stages of construction shall be controlled in ITP‟s identical to the above Supplier/ Subcontractor format detailing the quality verifications performed by the Contractor‟s construction and quality control organisations with allowance for the Contracting Authority QC surveillance/witness mark up. Pre-inspection meetings shall be held at the work location/ start before the start of all physical work as described above for Supplier/Subcontractor activities. Page 143 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 All QC activities and status/records shall be compiled on a database referencing the appropriate ITP, procedure and certification so that the QC status can be continually monitored as work progress. Details of the proposed system shall be submitted in Schedule 9 of Part B1 of the ITT and form part of the Contract in Annex XIII – “Quality”. Contracting Authority shall be provided with a weekly update of all QC problems on Construction together with a regular and brief description of all non-conformances issued. The Contractor‟s QC Manager shall be delegated the clear power and immediate access to Contractor senior management to stop any work that is non-conforming. As part of his own management system, Contracting Authority shall use the non-conformance system operated by the Contractor to raise any construction non-conformance‟s found. The Contractor shall handle these non-conformances in accordance with the approved procedure. This shall involve the preparation of a corrective action within 72 hours. Where such nonconformances are identified as major the affected work shall be stopped. Where the Contracting Authority‟s Representatives has concerns over the quality of work he shall have the right to re-test. Where work is covered over the re-test shall include removal of covering. No work shall be covered without the approved procedures and ITP‟s being followed, therefore construction activities shall not be started until confirmation that all QC activities have been signed off. Contractor shall establish a construction quality audit schedule which shall be updated on a rolling quarterly basis. A joint Contractor/Contracting Authority/Subcontractor QC walkabout shall be established and carried out on a weekly basis. This forum allows all parties to see evidence of best practices (and unsatisfactory practices). 8.3.7.5 Document Control/Quality Records The Contractor shall implement a computerised document control system for all documents, drawing and quality records from the initial engineering stage through construction to final document handover. The system shall provide up to date approval status/tracking of documents, revision control and controlled issue to all parties involved in the construction. The Contracting Authority‟s Representatives shall be provided with regular updated registers from the system and remote electronic access to the system so he can check document status to programme and the revision and approval status. The configuration of the system shall be compatible with Contracting Authority's electronic data management system (EDAM). The Contractor shall provide details prior to Contract Award of how he shall compile, index and control Supplier and construction QC verification records and certification. The Contractor shall also provide details of the system he shall use to verify Construction Completion of all engineering and construction work. Page 144 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor shall provide details of how all drawings, documents and records shall be formatted, indexed and handed over to the Contracting Authority in a consistent format in accordance with the requirements of the Contract. Contractor shall provide fire-safe and environmental protected storage for all documents throughout the Contract. Document format indexing system, storage and packaging shall be approved by the Contracting Authority Contractor‟s document control system shall be able to interface with the Contracting Authority document control system (EDAM) for transfer and control of all documents, The Contractor shall provide the Contracting Authority‟s Representatives with working copies of key design, Supplier and Subcontractor documents and drawings as part of the Contract. The Contracting Authority‟s Representatives shall identify the documents he wishes to have copies of for comment, and information purposes by mark up of the document registers. This may include multiple copies of some documents, e.g. plot plans, P&ID‟s to facilitate timely review. In addition, the Contractor shall provide reasonable numbers of working copies of drawings and documents as requested by the Contracting Authority Representative on an ad-hoc basis. The Contractor shall include within his document control system a procedure for control, recording and close out of Contracting Authority comments. However, Company procedures will always have precedence. Page 145 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 9. CONSTRUCTION 9.1 GENERAL The scope of Work is generally as outlined in the Drawings and other information as contained in FEED Package. The Work shall be carried out on a Brownfield area as well as on pipeline routes requiring rights of way. All measures shall be put in place to ensure that the execution of construction activities is carried out consistently with ALARP principles. Contractor must include consideration of the above and the restrictions that this may impose on over and above those experienced at a purely Greenfield location. For work on the Greenfield area the Contractor shall implement its own permit to work system. This permit to work system and any associated processes and procedures (isolations, risk assessments, etc) shall be provided to the Contracting Authority for review as part of the Contractors tender. For all works involving activities on the existing facilities the Permit to Work system in force in MLE plant will be implemented. This permit to work system and any associated processes and procedures (isolations, risk assessments, etc) shall be provided by the Contracting Authority for review. The Contractor‟s services shall include, but not be limited to, the following: 1. Administration, planning, management and control services, as required to effectively control the execution and timely completion of the Work. The Contractor shall provide an organisation chart identifying all posts in the organisation and the names of individuals occupying managerial or lead engineer positions, for each of the construction sites and for any support bases in Algeria. The reporting relationship between the Construction teams and the rest of the Project management shall be shown on the same or an additional organisation chart. 2. Provision of all direct and indirect labour or subcontracted services inclusive of tools, equipment, facility and consumable materials necessary to undertake the Work. 3. Responsibility for management of interfaces between disciplines and Subcontractors to ensure completion of the Work. Supervisors and superintendents shall require to have sufficient fluency in French or Arabic, or ready access to a translator, to ensure that supervision and control of all work is carried out efficiently and safely. 4. Provision of a Construction HSE Plan in accordance with Contracting Authority requirements which will include procedures, risk assessments, tool box talks to cover all types of work including confirmed space entry, multi-crane lifts, etc. 5. Receipt, offloading, storage and preservation of all materials. 6. Provision of a materials management system to enable full control of warehouse and storage yard materials. 7. Security of the materials stored on the Site. Page 146 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 8. Medical services and safety provision, as required by Algerian law and as defined in Annex XI – “Health, Safety and Environment” of the Contract. Contractor is responsible for providing medical services and medivac facilities for all for Contracting Authority‟s and Contractor‟s staff and visitors, and for Subcontractors, if they do not have their own services. Medical services are to be accessible for all Contracting Authority personnel in emergencies. 9. Identification, engineering and implementation of all temporary facilities required to complete construction, Commissioning and Start-Up of the Work. 10. Care and maintenance of all capital equipment comprising part of the Permanent Work. 11. Provision of Site Services to support construction. 12. Provision and servicing of office and living accommodation and facilities for Contractor‟s and Contracting Authority staff and visitors at all the construction sites. 13. Management of security on the sites and in all areas of sub-contract activity, if away from the main sites. 14. Management of the interface with Algerian Regulatory Approval Agencies relating to the performance of the Works, except in instances where it is agreed that Contracting Authority or others shall manage, like ARH. 15. Provision of general logistic administrative assistance for obtaining permits, visas, accommodation, hotel rates, car rental, transportation, etc. for Contracting Authority Personnel. 9.2 CONSTRUCTION ENGINEERING AND TEMPORARY WORKS The Contractor‟s Construction Engineering services shall include, but not be limited to, the following: 1. The design of all Temporary Works and facilities. 2. The preparation of all required construction, fabrication and erection Drawings. 3. Method Statements, Risk Assessment, Job Safety Analysis etc. for all activities. 4. Transport and lifting plans and support documentation for all major lifts and movements of major items of equipment or material etc. 5. The design of temporary power generation and electrical distribution systems required for site establishment, installation and Commissioning up to Provisional Acceptance. 6. The design and provision of temporary power generation and associated equipment to allow start up of the facility prior to establishment of power supply from MLE 60 kV GIS – Contractor shall substantiate the sizing of the temporary power generator. 7. The design of all temporary facilities and materials required for testing, Precommissioning and Commissioning activities for all piping, equipment and other systems which are part of the Work; 8. The provision and implementation of a bill of materials reporting system, with issue of exception reports to the Contracting Authority. Page 147 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 9. The design and production of all drawings, procedures and support documentation required for the installation of the Permanent Works; 10. The preparation of all “as-built” and certification documentation, and in particular the provision of “as-built” key drawings in readiness for Commissioning. 11. The design of the construction site support facilities includes site accommodation for Contractor personnel. 12. The preparation of all necessary fabrication Specifications. 13. The preparation of hydrotest procedures and corresponding hydrotest test packs. 14. The preparation of system Handover Procedures. 9.3 SITE PREPARATION The Contractor shall ensure that all facilities and other Sites are suitable for the Work and shall provide all relevant technical data, design calculations and Drawings as required to ensure satisfactory compliance with Contracting Authority requirements. The Contractor shall provide adequate open storage areas, as well as covered storage space. Controlled environment storage facilities shall also be provided for equipment or material that is sensitive to temperature or humidity. The Contractor shall provide at the Sites all necessary construction workshops, fabrication and testing facilities, machinery, facility and equipment necessary to complete the Work. This shall include a separate instrument/electric workshop and Inspection facilities. The Contractor shall provide all access roads to site, from existing roads. Contractor shall minimise unnecessary additional tracks in the desert and environmentally sensitive areas as defined in the environmental baseline report. The Contractor shall provide office accommodation facilities at site, including office space for the use of Contracting Authority. 9.4 SITE CONSTRUCTION FACILITIES The Contractor shall provide all services required to support the construction phase of the work and these shall include, as a minimum: Temporary construction camps for the field centre. The camp must be laid out and located with agreement with Contracting Authority. All necessary fully equipped office and accommodation facilities for Contractor‟s personnel All necessary office facilities for Contracting Authority personnel (30). The Contractor shall provide and be responsible for office and accommodation, catering, and transportation of the Contracting Authority personnel and visitors during construction to the standards to be defined by Contracting Authority. Page 148 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Food storage, preparation and dining facilities for Contractor personnel Leisure facilities for Contractor personnel Sewage treatment and disposal for the facilities Drainage facilities Transport vehicles and drivers for Contracting Authority, Contractor and Subcontractor personnel and construction materiel First Aid and Medical Centre Temporary power generation and distribution for Contracting Authority, Contractor and Subcontractor personnel and construction activities Telecommunications facilities at each site to allow control of the Work and communication with Home Offices Fire-fighting facilities Concrete batching plant as required Vehicle parking areas (with sunshade & hardstanding) Waste collection and disposal facilities, including refuse incineration and disposal, construction waste disposal and hazardous chemical/substance disposal. Refuelling, fuel and Maintenance facilities for Contractor and Subcontractor provided equipment and vehicles IT facilities and systems at each site for Contractor and Subcontractor personnel with links to home office data and systems and to Contracting Authority at site Utility systems for life support and construction needs, except where prior agreement has been reached to tie into existing infrastructure. Secure outdoor and covered storage for Contracting Authority Materials and Equipment. Covered storage shall include bonded areas and air-conditioned areas sealed against dust ingress for storage and inspection of delicate items. Vehicle marshalling point for procurement/construction traffic. control of logistics and The Contractor is responsible for layout of temporary construction camps and personnel safety during CPF Commissioning and Start-Up. This may involve relocation of personnel when commissioning commences. The Contractor shall provide facilities for the storage and issue of diesel fuel, chemicals, paint and other toxic and hazardous materials. These areas shall be covered with the ground paved and kerbed to prevent spillage‟s contaminating the earth. These areas are to be located sufficiently away from accommodation or office spaces. Adequate drainage and treatment facilities shall be provided. Page 149 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor shall provide temporary HVAC services for the CER and LER. The Contractor shall remove all the temporary facilities upon completion of the Work. The temporary site shall be returned, as near as possible, to its original condition. The Contractor shall produce procedures for spillage cleanup, disposal and site remediation for approval by Contracting Authority. The Contractor is responsible for clearing up all spillages such as fuel oil and chemicals, immediately after they occur, and disposal. Final clean-up and site remediation shall to be done prior to Contract completion. 9.5 STORAGE OF EQUIPMENT AT SITE 9.5.1 General The Contractor shall provide Storage, Preservation and Maintenance Procedures incorporating Supplier‟s recommendations prior to the receipt of equipment on site. These Procedures shall consider any Long Term preservation requirements. The storage and maintenance procedure shall be supported by an ITP and this shall be documented within Contractor QC System. The Contractor shall inspect all equipment and devices upon receipt at site and submit a full written report to the Contracting Authority‟s Representatives. The report shall include a listing of any defects or transit damage including Overage/Shortage/Damage Reports. The Contractor shall protect the Materials and Equipment against mechanical damage and ingress of dust, sand, moisture, welding sparks, sand and grit blasting and other foreign matter by providing suitable protective covers. The Contractor shall carry out regular inspections and presentation checks of the equipment and devices for the duration of the period of storage. All inspections shall be fully documented and submitted to the Contracting Authority‟s Representatives. If long term storage is required the Contractor shall ensure long term preservation procedures are followed and instigated as recommended by the Supplier. 9.5.2 Mechanical All mechanical and packaged equipment delivered and accepted on Sites shall be under the responsibility of the Contractor throughout the construction and Commissioning phases until the issuance of Provisional Acceptance by Contracting Authority. Prior to permanent installation the equipment shall be stored in a controlled environment, as necessary, and maintained in accordance with the Supplier‟s recommendations on preservation and maintenance of the equipment. Adequate consumables such as oils and greases, temporary aids, packings, etc. shall be supplied by the Contractor. First fill requirements for all equipments will be provided by Contractor. The Contractor shall rotate periodically all rotating equipment shafts in order to prevent bearing damage and shall maintain suitable records. The Contractor shall ensure that all equipment when stored is adequately supported and has sufficient access to inspect and maintain the equipment in accordance with the Supplier‟s Page 150 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 recommendations. No equipment shall be stored directly onto the ground without timber packings which allow for air circulation. 9.5.3 Instrument/Electrical/Telecommunications The Contractor shall provide controlled environment storage for control panels, sensitive instrumentation and telecommunications equipment and electrical equipment to ensure that there is no degradation arising from temperature, humidity and dust effects. The Contractor shall be responsible for taking delivery of all items of Materials and Equipment, for their storage in suitable clean and dry areas and for their proper protection both during storage and after installation. The Contractor shall ensure that corrosion inhibitors are used and that anti-condensation heaters are energised, where fitted, when environmental conditions warrant. 9.6 SITE CONSTRUCTION 9.6.1 General The Contractor shall ensure that the installation of all Materials and Equipment complies fully with statutory requirements, standards and codes detailed. The Contractor shall keep the work areas, and areas occupied by Subcontractors, in a clean and orderly fashion at all times. Unwanted scrap, waste materials, etc. shall be segregated and removed from site at appropriate intervals. The Contractor shall ensure that all items are checked against AFC data sheets and purchase orders prior to acceptance. Name plate details and inscriptions shall also be inspected to ensure that the correct items have been delivered. The Contractor shall ensure that all his personnel are fully competent tradespersons skilled in the particular field of work in which they are engaged. The Contractor shall ensure that a high level of qualified supervision is available permanently on-site to oversee and check the works undertaken by all Subcontractors. The minimum supervision to labour ratio shall be 1:10 The Contractor shall take full responsibility for the quality of the Work performed by all Subcontractors. Materials and Equipment to be supplied by the Contractor and Subcontractors shall be new (unless otherwise agreed) and suitable for the intended use and location. Lifting or slinging of equipment shall be undertaken in accordance with the Lifting Operations and Lifting Equipment Practice to be approved by the Contracting Authority. Contractor shall implement and manage a Contracting Authority approved scaffolding management system. The Contractor shall co-ordinate and ensure the attendance of Supplier representatives, as necessary, to assist in installation, protection and Commissioning. Page 151 / 180 Part D - Scope of Work 9.6.2 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Civil Works Contractor shall endorse and use the as-is final state of the early site preparation as the basis for execution of the Project. Any further site preparations required for the requirements of the Project are Contractor‟s responsibility and are part of the Work. The Contractor shall complete all civil works required for construction. This shall include, but not be limited to, all activities associated with and the provision of all machinery and construction activities including, but not limited to the following: Survey work and geotechnical investigations Earthworks Sewers, storm water, contaminated water and oily water drainage Storm water / effluent treated water discharge channel Roadworks, including permanent access Fencing Foundations Pipeline trenches Cable trenches for buried cables, both permanent and temporary Building transit frames Landscaping Shuttering Batch Plant Road crossings All Work shall be undertaken in accordance with the drawings and specifications developed and approved during the detailed design phase of this Contract. The Contractor shall complete all construction Specifications and Procedures prior to commencement of work on site. These documents shall be subject to review by Contracting Authority. The Contractor shall ensure that all civil construction works are subject to regular quality control checks and inspections, in accordance with the Specifications and agreed Inspection and Test Plans. These activities shall include, but not be limited to, the following: Inspection of excavations to ensure that adequate safety provisions are in place to prevent accidents and that adequate provision has been taken to prevent damage to existing structures or services adjacent to the works. Establishment of a written permit system to allow any blasting work on the Site. Inspection of backfill and compaction works to ensure complete compliance with Specifications and Drawings. All compaction testing shall be carried out by qualified personnel approved by Contracting Authority. Page 152 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Inspection of all sub-grade surfaces for roads. This shall include checking of levels, batters, widths and alignments. Testing of road sub-base, base course and aggregate materials. Inspection of road sub-base/base construction to ensure compliance with Specifications. Inspection and testing of all concrete pavement work and materials to ensure compliance with Specifications. Inspection and testing of all structural concrete work and material to ensure compliance with Specifications. Inspection of application of all bitumen and asphaltic concrete road surfaces. Inspection and testing of sewers, drainage pipes and manholes. Inspection of construction and finishing of all open drains to ensure compliance with Specifications. Inspection of construction and placement of evaporation pond sub-surface liners to ensure that the work has been completed in accordance with Supplier instructions/recommendations. Ensure all necessary equipment (including standby equipment) and experienced manpower is available at the Sites to enable placement, compaction, and finishing of all concrete and reinforcement work, in compliance with the Specifications. Provide all materials necessary to ensure curing of concrete complying with the Specifications. Ensure all cement used for the Work complies with the Specifications. No blended cement shall be used. Inspect all concrete mix delivered to the Site and supervise all concrete testing to ensure compliance with the Specifications. Remove from the Site all concrete that does not conform with the Specifications. Supervise and inspect all reinforcement fixing to ensure compliance with Drawings and Specifications. Supervise and inspect assembly of all formwork to ensure construction is adequate to safely support the concrete pour in accordance with the Specifications. Supervise placement of all equipment and structural anchor bolts to ensure compliance with Drawings and Specifications. Ensure placement of membranes under all concrete slabs in accordance with the Drawings and Specifications. Ensure all work, stages of work, materials and processes, shall be made available for, and be subject to, the inspection and approval by Contracting Authority, CTC, ONML, DPEM as may be required. Page 153 / 180 Part D - Scope of Work 9.6.3 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Mechanical Equipment The Contractor shall carry out the installation of all equipment. The Contractor‟s scope of Work shall include, but not be limited to, the following:Fabrication and/or installation of mechanical equipment, pressure vessels, storage tanks, static and packaged equipment and all items identified in the equipment List Fabrication and installation of all steelwork supports Sealing, grouting, bolting and seal welding of equipment in accordance with the Specifications The Contractor shall take all necessary steps to protect the equipment from damage during installation and shall ensure that the Supplier‟s recommendations on lifting aids and the slinging of the equipment are followed. The Contractor shall, where applicable, use only the special tools and equipment provided by the Supplier. Special tools shall be left with the equipment. The Contractor shall ensure that all preservation fluids are removed from equipment and that all temporary aids and attachments are removed prior to function testing. The equipment shall then be made ready for testing in accordance with the Supplier‟s recommendations. This shall include the supply of all flushing oils and First Fill lubricating oils. The Contractor shall ensure that all motor drivers are checked and tested for correct rotation prior to final coupling. The Contractor shall produce and follow Function Testing and Start-Up Procedures in order to ensure system/equipment integrity. After installation and completion of testing prior to handover the Contractor shall ensure the equipment is fully maintained and shall continue to perform all maintenance activities required to maintain the integrity of the equipment until Conditional Acceptance. A record of these activities shall be maintained. 9.6.4 Piping Systems The Contractor shall carry out the fabrication, installation and Mechanical Completion of all process and utilities piping systems, including all associated supports, in accordance with the Specifications. The Contractor‟s Scope of Work shall include, but not be limited to, the following: Identification of systems for hydrotest, production of hydrotest test packs and issuance of Mechanical Completion certificates Fabrication, installation, supporting, cleaning (including chemical cleaning), flushing, protective coating, inspection (including, but not limited to NDT), pressure testing, coating, insulation and of all pipework, valves and fittings for all of the facilities. Page 154 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Contractor shall implement a joint integrity management programme acceptable to Contracting Authority to ensure minimum leaks during N2 leak testing to be incorporated in its flange management system. This programme shall be the subject of an ITP and shall be recorded in the Contractor QC system. All flanged joints shall be torqued to pre-determined settings. All flanges shall be tagged with the applied torque settings and the name of the individual making the joint. Joint tags shall only be removed after successful leak testing. Pipework in critical systems shall be cleaned by the Contractor to the satisfaction of the Contracting Authority. Methods employed may include retrojetting, pull through, potblowing, etc, however Contractor shall make provision for internal inspection of critical systems by means of access points, CCTV/Boroscope, etc. The Contractor shall provide and maintain end caps to close off open ended piping systems. The Contractor shall be responsible for the preparation and testing of all welding procedures and welder qualifications as required to satisfy the requirements of the Specifications. 9.6.5 Gathering Systems The Contractor shall carry out the fabrication, installation and Mechanical Completion of all Oil and Production System and Water and Gas Injection System piping, including all associated supports, in accordance with the Specifications. The Contractor‟s Scope of Work shall include, but not be limited to, the following: identification of systems for hydrotest, production of hydrotest test packs and issue of Mechanical Completion certificates fabrication, installation, supporting, trenching, burial, cleaning (including chemical cleaning), flushing, protective coating, inspection (including, but not limited to NDT), pressure testing, coating, insulation, Commissioning and reinstatement of all pipework, valves and fittings for all of the facilities. Following pressure testing, Oil gathering systems shall be dewatered and left in inert conditions prior to Commissioning. Contractor shall implement a joint integrity programme acceptable to Contracting Authority to ensure minimum leaks during leak testing. This programme shall be the subject of an ITP and shall be recorded in the Contractor QC system. All joints shall be torqued to pre-determined settings. All flanges shall be tagged with the applied torque settings and the name of the individual making the joint. Joint tags shall only be removed after successful leak testing. Page 155 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Pipework shall be cleaned by the Contractor to the satisfaction of the Contracting Authority. Methods employed may include retrojetting, pull through, potblowing, etc, however Contractor shall make provision for internal inspection of critical systems by means of access points, CCTV/Boroscope, etc. The Contractor shall provide and maintain end caps to close off open ended piping systems. Contractor shall be responsible for the preparation and testing of all welding procedures and welder qualifications as required satisfying the requirements of the Specifications. 9.6.6 Structural The Contractor shall fabricate, assemble, erect, inspect and dimensionally check and provide protective coating of all structures including, but not limited to service support racks, platforms, ladders, hand rails, structural steel, foundations, equipment supports and Mechanical Completion in accordance with Drawings and Specifications. The Contractor‟s Scope of Work shall include, but not be limited to, the following: Implement all necessary survey work and foundation testing prior to design of structures. Supervise production of all design and shop drawings and fabrication of steel structures. Ensure all structural work complies with dimensional tolerances and quality requirements given in the Specifications. Inspection of all steelwork prior to departure from fabrication workshop to ensure all steelwork, loose pieces and bolts are coated, marked and tagged in accordance with the Specifications. Provision of suitable transportation and storage facilities for steelwork in accordance with Specifications. Inspection and supervision of site erection to ensure compliance with Specifications. Ensure all repairs to damaged protective coating are completed in a manner consistent with Specifications. Provide material Specifications. 9.6.7 certificates for steelwork as per the Instruments, Electrical and Telecommunications The Contractor shall install all electrical systems, field and panel mounted instruments, telecommunications systems and cables in accordance with Supplier instructions/recommendations and Project Specifications and drawings. The Contractor shall provide and install power cables and TLC cables along the whole gathering system network. Page 156 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor shall ensure that all certified equipment has been labelled or marked by the manufacturer with the correct certification protection type, gas group and temperature classification where applicable and that the appropriate certificate has been supplied. The Contractor shall not permit any cutting, drilling or welding of any certified equipment nor the painting of flame path gaps. Contractor shall have in place a Cable Management Procedure that shall include testing of cable on delivery. Before installing any major item of equipment, the Contractor shall ensure that all floors are suitably finished, floor foundations are adequate and fixings and access ways are suitable for the equipment to be installed. The Contractor shall ensure that all panels are mounted in the correct order/sequence as shown on the installation Drawings and that all circuit designation labels are checked for correct identification. The Contractor shall, where applicable, use only the special tools and equipment provided by the Supplier. Special tools shall be left with the equipment. The Contractor shall ensure that equipment is not installed until all welding, painting, finishing and fireproofing in the location concerned has been completed or that adequate protection has been provided. Prior to installation, the Contractor shall check the proposed location of all of the equipment and supports in order to ensure that clashes do not occur, that adequate access for maintenance is available and that adequate access for cable termination, including proper cable bending radii, has been provided. The Contractor shall ensure that all cables run in continuous lengths from points of design to destination. Joints or splices are not acceptable, except in the case of optical fibre cabling where joints shall be minimised. The Contractor shall ensure that all cables are handled and installed in a manner which does not cause damage by abrasion or excessive tension. The Contractor shall ensure that all cables are identified by means of indestructible, clearly legible markers showing their respective numbers as indicated on the cable schedule. The cable markers shall be located at each end of the cable, at both sides of any transits, at each change in direction and at 20 metre intervals along the entire cable run. The Contractor shall supply and install cable core markers designated with a unique number of each cable core in all instrumentation, control and telecommunications cables at each terminal/connection point, as indicated in the cable schedule and termination drawings. The Contractor shall ensure that all multi-cable transit units are gas, water and fire tight, and have the same blast/fire rating as the wall, ceiling or floor in which they are installed. Sufficient transits shall be installed to permit the passage of the maximum number of cables capable of being installed on the associated cable ladders, trays or trenches. Page 157 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor shall ensure that hydraulic and pneumatic tubing is installed in accordance with the Hook-up Drawings and the Specifications. All instruments shall be prepared for installation and calibrated in a clean workshop area. 9.6.8 HVAC Systems HVAC systems for controlled environment areas shall be installed strictly in accordance with the design Specifications, Drawings and data sheets, including recommendations by Suppliers. Systems and equipment shall be common for all areas as far as reasonably practicable. The Contractor shall undertake all function testing checks. individually tested prior to a full F&G system shutdown test. 9.6.9 All fire dampers shall be Safety Equipment The Contractor shall install all Safety systems and equipment, including emergency equipment, First Aid equipment, etc., as defined in the Specifications. The Contractor shall implement Inspection and Test Plans to control the installation and testing of safety systems and equipment. Such plans shall be subject to review by Contracting Authority Safety Representative and by the appropriate Algerian Authorities. Systems and equipment to be installed and tested by the Contractor shall include, but not be limited to, the following: Fire and Gas Detection Equipment. The Contractor shall install fire and gas detectors throughout the Facilities in accordance with the Specifications. The Contractor shall ensure that area coverage is sufficient to meet fire and gas system performance requirements and shall additionally include provision for an independent audit by Contracting Authority for detection coverage. The Contractor shall implement all fire and gas detection equipment loop checks and calibration tests in accordance with Supplier‟s procedures. Active Fire Protection The Contractor shall install and test active fire protection systems, including firewater and automatic / manual CO 2 systems in accordance with the Specifications Passive Fire Protection The Contractor shall apply passive fire protection to equipment and structures as defined in the Specifications Page 158 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor shall nominate a Supplier or Subcontractor for the supply and application of the passive fire protection and shall submit the nomination to Contracting Authority for review. The application of passive fire protection shall be undertaken only by trained and qualified personnel approved by the nominated Supplier. Upon completion of the construction work and before application for Mechanical Completion the Contractor shall repair any damage to the passive fire protection that has occurred during construction activities. All repairs shall be undertaken in accordance with Supplier approved procedures. Escape Routes. The Contractor shall provide escape routes throughout the Facilities in accordance with the Specifications. The Contractor shall, on completion of construction, verify that all escape routes are clearly marked and are not obstructed by equipment prior to completion of the Work. Safety Signs. The Contractor shall install safety signs throughout the sites. All signs shall be provided in French, Arabic and English and shall include pictorial representations of the objective at the sign, wherever possible. Safety Equipment. The Contractor shall procure and install throughout the sites safety equipment, including firefighting equipment, First Aid equipment, safety showers and eye washes, in accordance with Specifications. 9.6.10 Corrosion Protection and Painting The Contractor shall coat all surfaces in accordance with the Paint & Coatings Specifications Call in the chapter 3.1.1.1 of this document. The Contractor‟s Scope of Work shall include, but not be limited to, the following: Application of corrosion protection coatings to all internal and external surfaces as required, following any request included in the properly paint/coating functional specifications, regarding all the phasis of the work. The Contractor shall make good, and continue to make good throughout the duration of the Contract, any defects in the surface finishes and all damaged areas whether caused by accidental damage, design revision, rework or out-of-sequence work; Page 159 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Marking of colour code and of direction arrows for all pipework, valves and equipment in accordance with the Paint & Coatings Specifications Call in the chapter 3.1.1.1 of this document. 9.6.11 Welding Procedures/Welder Qualification The Contractor shall be responsible for the preparation and testing of all relevant welding procedures WPS/PQR. The Contractor shall be responsible for all welder qualifications in accordance with the Specifications. 9.7 PRECOMMISSIONING ACTIVITIES UP TO MECHANICAL COMPLETION The Contractor shall prepare procedures which outline the activities required for achieving Mechanical Completion for all the systems and disciplines and Contracting Authority‟s QA requirements. These procedures shall be submitted to Contracting Authority for review. As part of the construction activities the Contractor shall undertake all inspection and testing actions necessary to prove and validate the correct and complete execution of the Work. Pre-Commissioning is a series of inspections and static tests, to check the conformity of components and systems. Pre-Commissioning activities are to be carried out to achieve Mechanical Completion. Pre-commissioning activities need to be carried out on a system by system basis. The Contractor shall prepare precommissioning plans and procedures for activities up to Mechanical Completion and these shall include, but are not limited to, the following actions: 1. Factory Acceptance Tests (FAT) of all packages/equipment delivered to Construction Site as applicable 2. Conformity checks Check conformance with P & ID‟s, Line Lists and relevant Drawings, as constructed inspections with reference to project and Vendor Docs Visual inspection for damage or incomplete work NDE of welds Alignment and levelling checks of equipment Visual examination of excavations prior to foundation construction and at various stages of concrete construction process including standard material testing 3. Static and De-energised tests Hydrostatic and pneumatic pressure testing of piping systems and pipelines. Fluids used for pressure testing shall be of quality acceptable for all materials in contact with the fluid. Flushing and drying of piping systems Page 160 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Inerting Insulation and continuity tests Earth loop impedance tests Megger volt tests on electric cables Instrumenst calibration Coating integrity tests All other applicable tests Completion of all associated and necessary documentation Completion of all check sheets The Contractor shall undertake and be responsible for all testing in accordance with the appropriate Specifications. Specialist support services shall be provided as required for any testing of Contractor designed and Specialist Supplier systems and equipment. The Contractor shall submit full details of the test methods, test equipment, records and identification. The Contractor shall provide a system that tracks progress and status of certification by system and sub-system/discipline, so that readiness of systems for Commissioning purposes can be readily assessed. Mechanical Completion shall include, without limitation, the following work: All spades, orifice plates and the like shall be in position, as per the P & ID‟s All drivers and driven machinery shall be aligned according to Suppliers specifications All electrical circuits shall have been tested and all electrical equipment shall be ready to receive power. Motors, where stipulated, shall have performed their “no load” run. Contracting Authority shall issue an “Livening Up” certificate prior to energisation of any electrical systems. All necessary pressure and vacuum tests shall have been witnessed, as necessary, by the representatives of appropriate Algerian authorities All pipework supports shall be in place and spring hangers stops removed All relevant certification documentation shall be signed as complete, assembled, and compiled for future reference Incomplete items shall be detailed on punch lists, split by system. Page 161 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Punchlist items shall be categorised as follows: CATEGORY A item: This means that this item is not complete and the remaining work must be mandatory completed prior to achieve Mechanical Completion CATEGORY B Item: This means that this item is not complete and the remaining work must be completed prior to introduction of hydrocarbons and Start-Up. CATEGORY C Item: This means that this item is not complete and the remaining work may be completed during or after Start-Up. Punchlists for each system shall be reviewed by the Contracting Authority. Contracting Authority shall be provided access to the Completion databases to allow such reviews. As construction and pre-commissioning activities have been carried out, the Contractor shall submit “Mechanical Completion” certificates for each and all systems to be approved by Contracting Authority. Such certificates will include punch lists, showing that all Categories A items have been properly cleared. Page 162 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 10. COMMISSIONING AND START UP All the explanations, responsibilities, activities, handover and acceptance procedures contained in this section for Commissioning and Start-Up apply on a system by system basis. The Contractor shall appoint a person responsible for the purposes of Commissioning. This is likely to be the Contractor Commissioning Manager. This person shall ensure that the activities proposed by the Contracting Authority and the execution of these activities have the full agreement of the Contractor. 10.1 COMMISSIONING OF UTILITIES AND PROCESS SYSTEMS WITH INERT FLUIDS Commissioning of Utilities and process systems with inert fluids is a series of dynamic and tests, to check the functionality of components and systems. Commissioning commences after Mechanical Completion. Commissioning is the functional verification of Equipment, Systems, Areas and Facilities. It involves the functional testing and adjustment of a system, to ensure compliance with drawings, specifications and contractual requirements. Commissioning involves the dynamic running of systems to further check out the functionality and integrity of complete systems, and continues on from Mechanical Completion. It is the last series of checks before running the process systems on hydrocarbons. It includes the operation of the utilities systems to progress the commissioning of process systems. For utilities systems and systems not requiring production hydrocarbon gas for full operation, Commissioning involves all activities needed to make these fully operational and ready for handover to Contracting Authority. Commissioning shall involve for example running the temporary generator (minimum rating to be substantiated by Contractor) and emergency power generator (which operate on diesel) to provide power to the site. For hydrocarbon gas process systems, Commissioning is the last series of checks before introducing hydrocarbons, and all such further work necessary to bring the various sections and components of the facility to a state of readiness for the introduction of hydrocarbons and their safe start-up and operation. The Contractor shall prepare commissioning plans and procedures and these shall include, but are not limited to, the following actions: Dynamic Verifications Functional (hot) instrument loop checks Uncoupled motor runs Alignment procedures Stroke all valves Shutdown functional tests F&G calibration & functional tests Electrical distribution network testing Page 163 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Electrical isolations / de-isolations. The Contractor shall comply with Contracting Authority isolation standards. Control system site integration and acceptance testing Site Acceptace Tests of packages / equipment, including mobilization and demobilization of relevant Vendors as required De-preservation, preservation and re-preservation Safety isolations Site familiarisation and orientation of Operations personnel. Operational tests of Utilities and Process Systems Running-in and on-line tests for a significant period of time of plant utilities & whwnever applicable of main process equipment in closed loop with inert fluids ICSS, including F&G, DCS and ESD system set-up and tests including Supplier Packages. These set ups and tests shall include Site Integration Tests (SITs) ensuring that Supplier Packages fully integrate into the ICSS with expected functionality. These are to be followed by a global Site Acceptance Test (SAT) for the ICSS. Pre-Start Up Activities Cleaning of critical piping systems and equipment by retro-jetting or chemical cleaning or other appropriate methods. Critical systems shall be defined and agreed with Contracting Authority and shall include but shall not be limited to compressor suction pipework between the suction scrubber and the compressor inlet, compressor discharge pipework and recycle lines (including the discharge coolers), fuel and seal gas systems, columns, Gathering System etc. System cleanliness shall be demonstrated. Methods to demonstrate cleaniness shall be defined and agreed with Contraction Authority. Detailed design of these and other critical systems shall be designed to facilitate these activities. . Demonstration of system cleanliness is a key requirement prior to ready for Start-Up and the introduction of hydrocarbons. Contractor shall outline his plans for chemical cleaning as part of his bid, confirming the requirement stated here. Page 164 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Leak testing. All leak testing and purging shall be carried out using a third party specialist and independant high pressure nitrogen supply, under the responsibility and supervision of the Contractor. System leak testing shall be carried out to 95% of the system PSV set-point. Leaks shall be detected by taping flanges where possible and using a pin hole with soapy bubble. Visible significant bubbling shall constitute a leak. All leaks shall be repaired with the system de-pressured. Pressurisation to leak test pressure shall be done in 3 stages i.e. 30%, 60% and 100% with a 30 minute hold time to the next pressure level and final held at 100% of test pressure for 1 hour. Nitrogen purging of all pressure systems Facility isolations and valve line up for non-hydrocarbon systems. The Contractor shall comply with Contracting Authority‟s isolation standards. Testing of active fire protection systems, including automatic / manual CO2 systems in accordance with the specifications As built documentation Incorporation of Commissioning defects into Master punchlist Site familiarisation, training and orientation of Operations personnel De-preservation, preservation and re-preservation As systems are commissioned and brought into operations, or being ready for introduction of hydrocarbons, the Contractor shall submit “Ready for Start-up” clearance for each system to be approved by Contracting Authority. When all systems certificated are approved, the Contractor can submit the “Ready for Start-up” Certificate for approval by Contracting Authority, after which Start-Up shall begin. Such certificate will show that all Category B punch list items have been properly cleared by Contractor. 10.2 START UP Start Up is defined as the commencement of the introduction of hydrocarbons into the Permanent Works to continue to commission the process systems. It occurs only after all checks, inspections, Pre-Commissioning and Commissioning activities have been successfully completed and accepted by Contracting Authority, and when all Ready for StartUp clearances for each system and the Ready for Start-up Certificate have been approved by Contracting Authority, when all Category A and B punchlist items and HSE and operability defects have been satisfactorily cleared, and when all documentation necessary for safe operation of the facilities, certification, etc. has been provided to Contracting Authority. The Contractor shall remain responsible for the care and maintenance of the facilities during the Start-Up and until signature by Contracting Authority of the Provisional Acceptance Certificate. The Contractor shall direct the Start-Up with the assistance of the Contracting Page 165 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Authority and shall be responsible for the management of HSE during this period. The Contractor permit to work system, using SH-FCP approved forms, shall be in force and shall be managed and operated by the Contractor‟s Personnel. Contracting Authority reserves the right to stop work at any site if it considers the activity to be an unsafe act, or poses environmental risk. The Contractor with assistance from the Contracting Authority shall prepare a Start-Up plan for approval by the Contracting Authority. A daily Start-Up meeting shall be held during the Start-Up period. The Contracting Authority shall present all daily activities and associated procedures and processes to the Contractor at this meeting. Activities shall be proposed at the meeting at least 24 hours prior to their execution. The timing of activities shall be agreed between the Contractor and the Contracting Authority. This meeting shall be minuted by the Contractor. The minutes shall be reviewed and approved by the Contracting Authority and the Contractor. They shall be signed by representatives of both parties and filed. The Contracting Authority shall also present a 7 day lookahead. No Start-Up activities shall take place without being minuted at the daily Start-Up meeting. Start-Up shall include activities to be agreed with the Contracting Authority. At the end of the Start-Up activities, when the facilities are operating sufficiently reliably and stably, the Contractor shall request permission to perform the Provisional Acceptance Test. The Provisional Acceptance Test shall have been successfully completed when all the equipment has operated together at 100% of design criteria without trips or major alarms for a period of 96 hours. Refer to document Annexe I – “Technical” and Annexe VI - “Performances Guaranties” The Contractor shall provide all the necessary resources to support the Start-Up. This shall include commissioning support, specialist support (vendor/supplier), engineering support, and assistance for the above activities until Conditional Acceptance. The Contractor shall provide the following team (as a minimum) for the Start-Up activities: Major Equipment Vendor Rotating machinery field engineers Major Equipment Vendor Engine controls engineers Major Equipment technicians Vendor Rotating machinery Major Equipment Vendor E&I technician Third party vibration monitoring specialist Contractor‟s Start-up engineer Contractor‟s Production technician x 2 Contractor‟s Control room technician Contractor‟s Instrument technician x 2 Contractor‟s Mechanical technician Contractor‟s Electrical technician ICSS Vendor Control systems Engineer x 2 Page 166 / 180 Part D - Scope of Work mechanical Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Condition monitoring system engineer Once the Start-Up activities and the Performance Test have been carried out successfully, the Provisional Acceptance Certificate shall be offered up by the Contractor to the Contracting Authority for signature. Any minor reservation remaining at this stage will be recorded as such in the Provisional Acceptance Certificate. 10.3 RESPONSIBILITIES The Contractor shall be responsible for all activities as defined above. The Contractor shall ensure sufficient time in the overall project programme to carry out the Start-Up activities and the Performance Test for satisfactory reliable operation of the facilities. The Contractor shall propose a programme and schedule for Commissioning as part of their lump sum to be agreed with Contracting Authority during clarifications. The Contractor shall provide all the necessary resources (specialist personnel, vendor/supplier representatives, labour, Materials and Equipment) during Commissioning. The Contractor shall provide a temporary diesel electrical generator set to carry out all the Commissioning activities and to mitigate against any Start-Up delays which might occur in the event of late connection to MLE 60 kV GIS for power supply or any interruption to such supply. The Contracting Authority may wish to provide personnel to support Commissioning activities. If so, the Contractor shall integrate the Contracting Authority Personnel under the Contractor‟s supervision. Responsibility for the execution of the Commissioning shall remain with the Contractor. The Contractor shall be responsible for all interfaces between Construction, and Operations on Commissioning activities. All isolations shall be managed by Contractor up to Start-Up and thereafter by Contracting Authority. The Contractor shall be responsible for assisting the Contracting Authority in obtaining all the approvals and consents required from the Authorities for Commissioning and shall be responsible for providing the support required for the necessary approvals for the introduction of the first hydrocarbon gas into to the facilities. 10.4 HEALTH, SAFETY AND ENVIRONMENT CONSIDERATIONS The Contractor shall implement the agreed HSE standards throughout Commissioning. The Contractor shall ensure that all the Subcontractors work to the same detailed HSE standards for the duration of their work activities. Contractor shall implement an overall HSE Management System meeting current best practice e.g. ISO 14001, OHSAS 18001, OGP Report 376, OGP Report 291 and ensure interfaces with Contracting Authority and other participants are managed. Contractor‟s HSE Management System shall be documented and meet the requirements of OGP Report 343. Page 167 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor shall ensure that safe systems of work are implemented from the commencement of Commissioning to protect people from hazards. The Contractor shall be responsible for overall emergency response management during Commissioning. For incidents resulting from any activities the Contractor shall have standalone emergency response capability, including emergency management, emergency plan and all associated systems. The Contractor shall continue to use his permit to work system during Commissioning. An adequate energy isolation procedure shall be put in place as soon as a system is made live with electricity, pressurised and/or flammable fluids. This shall be included with the Contractor‟s bid for approval by the Contracting Authority. The Contractor‟s permit to work system shall be submitted with the Contractor‟s bid for approval by the Contracting Authority. This shall be rigidly enforced throughout Commissioning up to Provisional Acceptance. The Contracting Authority‟s permit to work system shall be introduced on and from Provisional Acceptance. Hazards associated with all Commissioning and operational jobs shall be identified and risks analysed by the Contractor. Risk mitigation/elimination measures shall be stated on all work permits. Additionally, toolbox talks shall be carried out before all operational tasks involving all non-operational personnel. All work shall be adequately planned. Simultaneous operations (SIMOPS) involving operations with construction/existing production or maintenance activities in MLE CPF, etc. shall be identified and planned beforehand. Specific procedures shall be written by the Contractor for all simultaneous operations. The Contractor shall ensure that all personnel involved in Commissioning undergo a comprehensive site familiarisation and job induction training programme, and specific permit to work system training in both the Contractor‟s and Contracting Authority‟s systems. The Contractor shall ensure that the labour-force is represented at regular HSE briefings and meetings. The Contractor shall ensure that the hazards associated with major activities are identified, understood, and eliminated wherever possible. The Contractor shall prepare method statements and procedures for major activities. During Commissioning, the Contractor shall install all permanent Safety systems and equipment, including emergency equipment, First Aid equipment, eye washes, etc. The Contractor shall replace these if damaged. The Contractor shall install temporary safety signs throughout the facilities during Commissioning to supplement the permanent safety systems. All signs shall be provided in French, English, and Arabic, and shall include pictorial representations of the objective at the sign, wherever possible. Lifting or slinging of equipment shall be undertaken in accordance with the Lifting Operations and Lifting Equipment Practice. The Contractor shall erect barriers to restrict movements whilst equipment is under potentially hazardous test, and when it is in operation. Page 168 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor shall maintain all escape routes throughout the execution of Commissioning. The Contractor shall identify and plan all the licences, consents, and approvals from the appropriate Authorities required for all Commissioning activities described above. The Contractor shall ensure that atmospheric emissions, solid wastes, and liquid discharges are kept to an absolute minimum during Commissioning. The Contractor shall ensure adequate communication during Commissioning and Start-Up and provide sufficient intrinsically safe radios to those involved in the work. The Contractor shall also provide radios to the Contracting Authority operations staff involved in operations and maintenance routines prior to the issue of the Provisional Acceptance Certificate. The Contractor shall compile a register of all safety equipment and devices, showing location and status of functional and final checks during Commissioning. Contractor shall carry out a liaison risk assessment for the workforce including Subcontractors. Contractor shall operate under the direction of the Contracting Authority liaison management system whilst in Algeria 10.5 PLANNING The Contractor shall be responsible for adequate planning of Precommissioning & Commissioning. All completion activities shall be based on commissioning packages, and planned on a system, sub-system prioritised basis, in a fully integrated network, in order to meet both the Start-Up date and an optimal sequence of completion The Contractor shall propose a programme and schedule for Commissioning as part of their lump sum Contract Price. The Contractor shall be adequately represented with commissioning specialists during the detailed engineering and construction phases. Amongst other activities, the Contractor‟s commissioning representatives shall be involved in: Design interfaces (specifying system boundary limits, system isolations) Participation in HAZOP‟s Equipment selection, and test run procedures Facility layout Constructability reviews Commissioning operability Preparation of Pre-Commissioning, Commissioning and Start-Up procedures and plans, including the sequence by which systems are commissioned. Page 169 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Studies into the acceleration of Commissioning and early Start Up, whilst minimising environmental emissions and wastes. These shall include the use of temporary generators as an alternative to the main power from MLE during initial startup and an investigation into the requirements of the CAFC Start Up. Gaining approvals required by the Algerian authorities, and licences and consents required for the Pre-Commissioning, Commissioning and Start-Up process. The Contractor shall incorporate best practices and lessons learned from projects recently commissioned in southern Algeria into Pre-Commissioning, Commissioning, and Start-Up plans. The Contractor shall integrate into his project execution team representatives from critical equipment vendors, e.g. compression suppliers, to ensure healthy close-working relationships through out the project, and to ensure lessons learned from earlier projects are incorporated. 10.6 PRE-COMMISSIONING, COMMISSIONING AND START-UP ACTIVITIES The Contractor shall produce Pre-Commissioning, Commissioning and Start-up procedures and method statements detailing the activities to be carried out, for Contracting Authority review and approval. The Contractor shall ensure that the Computerised Maintenance Management System (CMMS) is on-line and available for use at the commencement of Commissioning. The Contractor shall support initial use of the CMMS starting from commissioning, assist with data entry and work processing. The Contractor shall ensure through facilitation, training and support of the Company‟s maintenance personnel (including tracking and reporting on CMMS usage) that all maintenance / repair & defect activities, and all planned maintenance activities due on the Permanent Work throughout Commissioning are effected through, entered in, documented and closed out on the CMMS. The Contractor shall supply and maintain a project completion and certification system tool for all phases including Pre-Commissioning, Commissioning and Start-Up up to Conditional Acceptance. Operating and maintenance manuals shall be prepared by the Contractor. The manuals shall be provided to the Contracting Authority 10 months prior to Start-Up. The Contractor shall provide and be responsible for office and accommodation, messing, and transportation of the Contracting Authority‟s Personnel and visitors until signing of the Provisional Acceptance Certificate to the standards to be defined by Contracting Authority. 10.7 GENERAL PROCEDURES The Contractor shall prepare procedures which detail how the Commissioning activities shall be carried out for each piece of equipment and system, for the Contracting Authority to review and approve. For process systems, Commissioning activities should be split between activities prior to hydrocarbons and activities after introduction of hydrocarbons. Page 170 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor shall also prepare Start Up procedures for the facilities, with input from Suppliers and Contracting Authority to be prepared 10 months in advance of Start-Up. The Start-Up procedure shall be agreed by the Contracting Authority and the Contractor. Contractor shall provide a of list of procedures that shall be prepared by the Contractor 10 months in advance of Commissioning to reviewed and approved by Contracting Authority. The total list includes, but is not limited to the following: Flushing of pipework Commissioning and mechanical systems prior to Control of cleanliness of all facilities prior to Commissioning Chemical cleaning and passivation of systems Commissioning and Start-Up procedures Operating procedures, emergency situations covering normal, abnormal, and Tightness test/leak testing and joint management. Joint management shall include a tagging procedure recording flange, bolt and torque parameters and the individual responsible for making the joint. Equipment, piping and pipelines inerting procedure Isolation procedure for working safely on equipment and facilities. Contractor to adopt the Contracting Authority‟s isolation standard following the livening of electrical equipment and introduction of hydrocarbons. The competency of responsible individuals within the Contractors organisation shall be demonstrated as per Contracting Authority procedures. Compressor factory and site test runs Control of emissions, waste, discharges, and water abstraction Verification of compliance of critical equipment Progress reporting SIMOPS (construction/operations interface) procedures Safe Systems of Work Procedures (Permit to Work) Procedures for working at heights, in confined spaces, locking out and tagging live/pressurised systems. 10.8 HANDOVER AND ACCEPTANCE PROCEDURES Contractor shall develop and maintain a Project completion and certification tool during all phases including handover to operation. This tool shall enable the tracking of the status all systems and equipment through the process of Mechanical Completion, Pre-Commissioning, Live Commissioning and Start-Up. This completion tool shall be the basis for issuing certificates for document completion of the different phases. Page 171 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 The Contractor may be required to provide essential resources and support for 3 months following the signing of the Provisional Acceptance Certificate (reimbursable basis). These resources shall be drawn from the Contractor‟s site team and shall be agreed during Start-Up. Page 172 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Precommissioning, Commissioning, and Performance test battery limits prior to handover to Operations are summarised in the following figure: Handover and Acceptance Procedures shall be based on the following principles: Ready for Start-Up clearance of each particular system by the Contractor indicates that the system is ready for the introduction of hydrocarbon gas. Ready for Start-Up Certificate will be issued upon clearance of all systems being achieved. Provisional Acceptance by the Contracting Authority shall occur when Performance Tests have been successfully completed. A Provisional Acceptance Certificate shall be offered up to the Contracting Authority by the Contractor. The 2 year Warranty Period shall run from the date of issue of the Provisional Acceptance Certificate. Final Acceptance by the Contracting Authority occurs on the expiry of the Warranty Period. A Final Acceptance Certificate shall be offered up to the Contracting Authority by the Contractor. The Contractor shall complete all outstanding work and punchlist items, as quickly as practicable and, in any case, before offering to the Contracting Authority a Provisional Acceptance Certificate. Page 173 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 From the date of signing the Provisional Acceptance Certificate, the Contracting Authority shall assume full responsibility for the operation and routine maintenance of the facilities. Provisional Acceptance cannot be achieved until: All punchlist items are satisfactorily closed out As built drawings and documentation, including manuals, are available (in paper and electronic format) The Provisional Acceptance Certificate has been issued and the Performance Tests have been satisfactorily completed. Final Acceptance cannot be achieved until: All Provisional Acceptance conditions have been met Defect-free operation for 24 months following Provisional Acceptance. 10.9 PERFORMANCE TESTING The Performance Test shall be carried out at a time when both parties agree that Commissioning is complete and the facilities are operating sufficiently reliably and stably to conduct a meaningful test as defined in Annex VII – “Performance Guarantees”. Operational reasons, outside the control of Contracting Authority, may dictate precise windows, during which the Performance Test can be undertaken. The Performance Test procedure shall be developed and agreed during clarifications prior to Contract award and shall include a summer and winter test. In the event that Contracting Authority cannot provide a suitable opportunity or conditions to conduct the Performance Test within 24 months after signature by the Contracting Authority of the Provisional Acceptance Certificate, the responsibility of the Contractor in this regard shall be relinquished. If reservoir fluids, having the characteristics stated in the specifications, are not available for use during the test runs of the facilities, any Performance and Utilities Warranty, which forms part of the Contract, shall be correspondingly adjusted. This shall be achieved using standard chemical engineering practice and agreed between both parties. 10.10 FAILURE OF FACILITIES TO PERFORM In the event that the Works or any section thereof fails to operate in accordance with the design premise or the Contract, the Contractor shall at its own expense carry out appropriate remedial design and construction work and provide necessary replacement materials, equipment and facilities. On completion of such remedial work the Contractor shall demonstrate that the design criteria have been met. 10.11 TRAINING The Contractor shall provide training and training aids for the Contracting Authority and Contracting Authority operational staff. This shall include the following training for critical packages: Page 174 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 Attendance at FATs and at critical tests/inspections Supplier on-the-job training during site Pre-Commissioning & Live Commissioning activities training on main equipments including: operation, mechanical, electrical, instrumentation, DCS, telecommunication et safety. Specific Supplier classroom training programmes on site (in English & French) Training programmes shall be drawn up by the Contractor and reviewed by the Contracting Authority The critical packages are: Gas injection driven Compressors Off gas compressors ICSS (including DCS, F&G and ESD) Electrical and instrumentation The Contractor shall also organise a general classroom session with centrifugal compressor simulator training (operation) and on-the-job training for the non-critical systems and equipment not covered above. The number and duration of each course will be developed by the contractor according to the needs of the future plant; The Contractor shall ensure that all major equipment critical packages include a fixed proposal and cost element for training of the Contracting Authority personnel by the Supplier at the construction sites prior to placing the order. These proposals shall be reviewed with the Contracting Authority. Training costs shall include all overseas training costs including local transportation and full hotel accommodation. . This is to be estimated at US $250.00 per day per person and be reimbursable. For courses at the construction sites, the Contractor shall provide a Training office. The Contractor shall ensure that the training provided is in English and French and is of a standard, which contributes to the overall competence of the Contracting Authority operational staff. 10.12 VENDOR SUPPORT The Contractor shall arrange for vendors of critical equipment to attend site to support installation, Pre-Commissioning, Live Commissioning and Start Up, and further, the Contractor shall agree with the Contracting Authority the equipment over and above critical equipment which requires vendor support on site. The Contractor may be required to arrange for vendors of critical equipment to be available for the Contracting Authority on a reimbursable basis, as required by Contracting Authority to support operation for up to 3 months following Provisional Acceptance. Page 175 / 180 Part D - Scope of Work 10.13 Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 DOCUMENTATION The Contractor shall provide good quality as-built drawings and documents as outlined in Annex V – “Documents to be submitted to the Contracting Authority” in French and English (both hard-copy and electronic format). The listing of required drawings and documents, and their format, shall be agreed between the Contractor and the Contracting Authority. The Contractor shall ensure that all Supplier documentation is received in a timely manner in order to ensure it can be incorporated in Pre-Commissioning, Live Commissioning, and StartUp procedures. The Contractor shall compile the necessary drawings and documents in the required format for the certification and approvals authorities. 10.14 ENGINEERING SUPPORT The Contractor shall provide discipline engineering support, as necessary, through to Provisional Acceptance. Page 176 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 11. SPECIAL NOTES REGARDING CAFC OIL PROJECT The Scope of Wok (SOW) as indicated in all the technical documentation contained in the ITT Annex 1 is derived from the original competitive FEED for the development of the total CAFC facilities which included the SOW for both OIL and GAS projects. Subsequent to the completion of the competitive FEED, the project was split into two separate projects:CAFC Oil CAFC Gas Gathering This ITT refers to the CAFC Oil Project, and any residual reference to CAFC Gas Gathering in the ITT documentation should be ignored, or at best used “for information only”. This Section (11. Special Notes Regarding CAFC Oil Project) is intended to advise last minute changes or updates to the basic technical documentation contained in the ITT Annex 1. 11.1 CAFC OIL GATHERING SYSTEM 1. The original competitive FEED documents were prepared for the total CAFC facilities including the lean and rich gas gathering system consisting of 10 lean gas wells, 7 rich gas wells, 17 gas flowlines, 3 gas manifolds stations and 2 gas trunklines. The lean and rich gas gathering system is presently under implementation as a separate project and does not form part of this Work. The Gas Gathering system is expected to be commissioned before, and be in operation during, the construction phase of the CAFC oil project. 2. The lean and rich gas wells are located in the same area as the oil wells and some of the gas flowlines and trunklines are run in the same pipeline corridors as the oil flowlines and trunklines. Contractor must consider existence of these live facilities in close proximity of the work sites in design and construction of the CAFC oil facilities. 3. Power supply for some oil wells and manifolds is to be taken from the nearby gas well pads /manifolds as detailed in the FEED documents 4. The well names and locations of some of the oil producer, gas injection and water injection wells have been revised. These are also preliminary and are subject to change during the EPC phase. 5. To avoid any confusion, the manifold MOP-01 shall be split into two separate manifolds at the same location. Each manifold shall be connected to a maximum of 8 wells and will be dedicated to each trunkline F6-1 and F6-2 separately. Note that the separation distance between the manifolds shall be determined according to FERA rules and guidelines. 6. The Tagi, F6-1 and F6-2 oil flowlines and trunklines shall be submitted to 100% X-ray inspection in accordance with the “Algerian safety regulation for transportation pipelines intended for combustible gas”. OLD WELL NAMES AND LOCATIONS Well Name X meters Y meters 1. F6-1 Oil Wells Names & Locations: NEW WELL NAMES AND LOCATIONS Well Name X meters Y meters Page 177 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 MZLS-3 364096 3340185 MZLN-8 368639 3344047 CAFC F6-1 - A 363960 3337010 CAFC F6-1 - B 357065 3341350 CAFC F6-1 - C 370450 3333570 CAFC F6-1 - D 356600 3342500 CAFC F6-1 - E 356600 3343500 CAFC F6-1 - F 359410 3343800 CAFC F6-1 - G 358125 3341480 CAFC F6-1 - H 360790 3339620 CAFC F6-1 - I 362210 3340320 CAFC F6-1 - L 362770 3337520 CAFC F6-1 - M 365400 3339720 CAFC F6-1 - N 365790 3337010 CAFC F6-1 - O 358555 3340505 2. F6-2 Oil Wells Names & Locations LEW-1 357003 3340422 LEW-3 356065 3341620 LES-4 369067 3336614 F6-2 Oil A 358970 3340105 F6-2 Oil B 358970 3341190 F6-2 Oil C 357970 3340860 F6-2 Oil D 357260 3342375 F6-2 Oil E 355255 3342550 F6-2 Oil F 357970 3341970 3. TAGI Oil Wells Names & Locations MZLS-3 MZLN-8 CAFC F6-1 - A CAFC F6-1 - B CAFC F6-1 - C CAFC F6-1 - D CAFC F6-1 - E CAFC F6-1 - F CAFC F6-1 - G CAFC F6-1 - H CAFC F6-1 - I CAFC F6-1 - L CAFC F6-1 - M CAFC F6-1 - N CAFC F6-1 - O 364096 368639 363960 357065 370450 356600 356600 359410 358125 360790 362210 362770 365400 365790 358555 3340185 3344047 3337010 3341350 3333570 3342500 3343500 3343800 3341480 3339620 3340320 3337520 3339720 3337010 3340505 LEW-1 LEW-3 LES-4 F6-2 Oil A LEW-5 F6-2 Oil C F6-2 Oil D F6-2 Oil E LEW-4 357003 356065 369067 358970 359431 357970 357260 355255 357880 3340422 3341620 3336614 3340105 3340697 3340860 3342375 3342550 3342140 LES-3 370958 3337287 LES-3 370958 3337287 LES-6 371435 3338221 LES-6 371435 3338221 LES-7 372521 3339204 LES-19 Hor 371947 3339140 LES-8 372386 3340637 LES-8 372386 3340637 LES-10 373100 3338851 LES-10 373100 3338851 LES-11 370550 3340160 TAGI OIL V8 370849 3340006 LES-12 371139 3338041 TAGI Oil V1 371139 3338041 LES-13 374500 3341975 TAGI OIL V3 371300 3336900 LES-14 373100 3338980 LES-20 Hor 371937 3339169 LES-15 372762 3340261 LES-22 Dir 372829 3340050 LES-16 370848 3336789 TAGI OIL V5 370550 3337300 LES-17 370860 3338687 TAGI Oil V4 370860 3338687 LES-18 371736 3339366 LES-11 Hor 371454 3340693 LES-19 370526 3341246 TAGI Oil V6 370526 3341246 LES-20 371660 3339997 TAGI Oil V7 371660 3339997 LES-21 371099 3339785 LEC-3 371498 3341512 LES-22 370228 3338600 LES-21 Hor 371535 3337160 4. TAGI Gas Injection Wells Names & Locations LEC-2 372682 3342017 LEC-2 372682 3342017 LES-GI 1 373950 3342234 LEC-4 GI 374140 3342490 LES-GI-2 371640 3342080 LES-7 372521 3339204 Page 178 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 5. TAGI Water Injection Wells Names & Locations LES-WI 1 368787 3337598 LES-18 WI 369750 3338141 LES-WI 2 369247 3339884 LES-16 WI 369362 3339747 LES-WI-3 368985 3335174 LES-17 WI 368985 3335174 LES-WI-4 372510 3338225 LES-WI-4 372510 3338225 6. Water Source Wells Names & Locations Water Prod. 1 372375 3340920 Water Prod. 1 372375 3340920 Water Prod. 2 371400 3339535 Water Prod. 2 371400 3339535 Water Prod. 3 373695 3338270 Water Prod. 3 373695 3338270 11.2 PIPING SPECS Piping specs originally included in the competitive FEED have been further developed during the CAFC Gas Project and are to be used for the Oil Project. The main difference relates to the 600# piping classes where the Gas Project uses RTJ flanged connections instead of RF. There are a few minor differences in other classes. SEE ATTATCHMENT G 11.3LEGEND SHEETS The development of the CAFC Gas Gathering Project has produced a set of P&ID Legend Sheets which reflect the changes in piping classes noted above as well as further developments during the detail design. These Gas Project P&ID legend Sheets are to be integrated into the Oil Project and a set of Oil Project P&ID Legend Sheets developed during the detail design which is mutually compatible with the Gas Project. SEE ATTACHMENT H 11.4FLOWLINE MODIFICATIONS In addition to the instrumentation shown on the P&ID‟s, all flowlines are to include for a Temperature and Pressure Indicator (TI & PI) at the end of each flowline. 11.5 INSTRUMENTATION MODIFICATIONS All the instrumentation devices shall be provided with Ex-i (and not Ex-d) electrical execution. Page 179 / 180 Part D - Scope of Work Sonatrach / FCP Tender No. Central Area Field Complex Project SH-FCP-EPC-PREQUAL-CAFCHUILE 2011-01 11.6 RING MAIN UNIT PACKAGE The CAFC GAS Project has developed the technical specifications for the Active and Passive Cooled Shelters. The ring main unit consists of No.5 Manifolds, No.1 Wellsite and all the other wells, in which will be installed electrical/instrumentation shelters complete with all necessary electrical and instrumentation equipment (in separate rooms). In the manifolds and wellsite will be installed shelters active cooled (ACS) type while in each well will be installed shelters passive cooled (PCS) type. The ACS will be complete with MV and LV switchboards, MV/LV transformers, UPS and batteries, RTU SCADA, SHD, IDS and TETRA System if necessary. The PCS will be complete with LV switchboards, UPS and batteries, RTU SCADA, SHD and IDS. These shelters shall have also F&G system, with detectors, etc. As for the Gas Gathering system, the connection between No.5 Manifolds and No.1 Wellsite shall foresee an interlock (mechanical) philosophy between the disconnector and the earthing switch installed in the same panel and a key interlock between the earthing switch and the disconnector installed in the site connected to. The closing of all earthing switch shall be possible only in case that the disconnector downstream and the disconnector upstream shall be open. 12. ATTACHMENTS TIE-IN INTERFACE MLE & CAFC ATTACHMENT ATTACHMENT ATTACHMENT ATTACHMENT ATTACHMENT ATTACHMENT ATTACHMENT A B C D E F I ATTACHMENT G PIPING CLASS SPECIFICATION ATTACHMENT H LEGEND SHEETS Document Number: 141200DPFM11760 rev. 02 sheets 1 to 6 dated 14/10/2011 Page 180 / 180 Part D - Scope of Work