Chapter 5 Long Term Construction Project (IFRS 11) Long term construction projects generally are construction projects that extend over one accounting period. Problems on long term construction projects have appeared very often in the CPA board examination. The principal problem to be encountered by CPA candidates on this topic is the computation of the gross profit to be recognized each year. The procedures and principles used in solving this problem are based on Philippine Accounting Standards (PAS) 11 “Construction Contract” Gross Profit Recognition The gross profit on a construction project may be recognized upon its completion or each year as the construction progresses. These two alternative methods of gross profit recognition are referred to as: 1. The Zero Profit Method 2. The Percentage of Completion Method Zero Profit Method This method is used when reasonable estimate of the percentage of completion cannot be made. Under this method, revenue is recognized each year in an amount exactly equal to costs incurred until reasonable estimates of the percentage of completion is available. The total gross profit on the project is recognized in the year of completion of the project. Percentage of Completion Method Under this method, gross profit is recognized at the end of each accounting period based on the percentage of completion of the project. The percentage of completion is usually computed by dividing the cost incurred to date by the total estimated cost to complete the project. The formula to compute the gross profit to be recognized each year is as follows: Contract price Less: Total estimated costs (1) Cost incurred to date Pxx Pxx Estimated cost to complete xx (2) Total estimated cost xx Estimated gross profit xx Multiply by percentage of completion (1 ÷ 2) % Gross profit earned to date xx Less: gross profit earned in prior year(s) xx Gross profit earned this year Pxx Once the percentage of completion is known, the following alternative formula may be used: Contract price Pxx Multiply by percentage of completion % Value of contract earned xx Less: cost incurred to date xx Gross profit earned to date xx Less: gross profit earned in prior year(s) xx Gross profit earned this year Pxx Cost incurred to date. These include precontract costs and costs incurred after contract acceptance. Precontract costs include costs of architectural designs, cost of securing the contract and any other costs that are expected to be recovered if the contract is accepted. Estimated costs to complete. These are the anticipated cost of materials, labors, subcontracting costs, and indirect costs (overhead) required in completing the project at a scheduled time. Cost of Materials purchased in Advance of their Use Construction materials purchased several weeks or months before they are actually use in constructions should not be treated as costs incurred for purposes of computing the percentage of completion ratio until the materials have been physically used in production, unless they are specifically purchased for the project. Anticipated Loss on Long Term Construction Projects In some cases, the total estimated costs may increase due to increase in the costs of construction materials. While the increase in the total estimated costs may result in a loss in the year the estimated cost increased, the entire contract will still result in a profit. Sometimes however, an increase in total estimated costs is so great that a loss on the entire contract is anticipated; that is, total estimated costs exceeds the total revenue from the contract. When a loss is anticipated, PAS No. 26 “Construction Contracts” require reporting the loss in its entirety immediately when the loss is first anticipated. Construction in Progress in Excess of Billings/Billings in Excess of Construction in Progress This represents the difference between the Construction in Progress (CIP) account and the Contract Billings as shown below: Construction in Progress Less: Contract Billings CIP in excess of billings (current asset) Billings in excess of CIP (current liability) Pxx xx xx Pxx Under the zero profit method, the Construction in Progress account before the year of completion is debited for the costs incurred to date. In the year of completion the Construction in Progress account is debited for the cost incurred and gross profit earned on the project. On the other hand, under the percentage of completion method, the Construction in Progress account is debited every year for the costs incurred and gross profit earned each year. In the year of completion, the balance of Construction in Progress account is closed to the Contract Billings account which have the same balance. Accounting for Change Order Change orders are modifications of an original contract. Contract revenue and costs should be adjusted to reflect change orders that are approved by the contractor and customer. PROBLEMS 1. The following data pertains to Bell Co’s construction jobs, which commenced during 2013. Project 1 Project 2 Contract price P420,000 P300,000 Costs incurred during 2013 240,000 280,000 Estimated costs to complete 120,000 40,000 Billed to customers during 2013 150,000 270,00 Received from customers during 2013 90,000 250,000 What amount of gross profit (loss) would Bell report in 2013 under the zero profit method and the percentage-of-completion method? a. P(20,000) and P20,000 b. P20,000 and P(20,000) c. P20,000 and P340,000 d. P40,000 and P420,000 2. Cord Builders, Inc. has consistently used the percentage-of-completion method of accounting for construction-type contracts. During 2011 Cord started work on a P9,000,000 fixed-price construction contract that was completed in 2013. Cord’s accounting records disclosed the following: December 31 2011 2012 Cumulative contract costs incurred P3,900,000 P6,300,000 Estimated total cost at completion 7,800,000 8,100,000 How much income would Cord have recognized on this contract for the year ended December 31,2012? a. P100,000 b. P300,000 c. P600,000 d. P700,000 3. State Co. recognizes construction revenue and expenses using the percentage-ofcompletion method. During 2012 a single long-term project was begun, which continued through 2013. Information on the project follows: 2012 2012 Accounts receivable from construction contract P100,000 P300,000 Construction expenses 105,000 192,000 Construction in progress 122,000 364,000 Partial billings on contract 100,000 420,000 Profit recognized from the long-term construction contract in 2013 should be a. P50,000 b. P108,000 c. P128,000 d. P228,000 4. Lake Construction Company has consistently used the percentage-of-completion method of recognizing income. During 2012 Lake entered into a fixed-rate contract to construct an office building for P10,000,000. Information relating to the contract is as follows: At December 31 2012 2013 Percentage completion 20% 60% Estimated total cost at completion P7,500,000 P8,000,000 Income recognized (cumulative) 500,000 Contract costs incurred during 2013 were a. P3,200,000 b. P3,300,000 c. P3,500,000 d. P4,800,000 5. Hand Construction, Inc. has consistently used the percentage-of-completion method of recognizing income. During 2013 Hansen started work on a P3,000,000 fixed-price construction contract. The accounting records disclosed the following data for the year ended December 31,2013: Costs incurred P930,000 Estimated cost t complete 2,170,000 Progress building 1,100,000 collections 700,000 How much loss should Hansen have recognized in 2013? a. P230,000 b. P100,000 c. P30,000 d. P0 6. Marr construction company has consistently used the percentage-of-completion method. On January 10,2012. Marr began work on a P6,000,000 construction contract. At the inception date, the estimated cost of construction was P4,500,000. The following data relate to the progress of the contract: Income recognized at 12/31/12 P600,000 Costs incurred 1/10/10 through 12/31/13 3,600,000 Estimated cost to complete at 12/31/13 1,200,000 How much income should Marr recognize for the year ended December 31,2013? a. P300,000 b. P525,000 c. P600,000 d. P900,000 7. The following data relating to a construction job started by SS Co. during 2013: Total contract price P100,000 Actual cost during 2013 20,000 Estimated remaining costs 40,000 Billed to customer during 2013 30,000 Received from customer during 2013 10,000 How much gross profit would SS Co. recognized for 2013 under the zero profit method and the percentage-of-completion method? a. P0 and P13,333, respectively b. P0 and P26,667, respectively c. P4,000 and P13,333, respectively d. P12,000 and P33,333, respectively 8. On April 1,2013, BB, Inc., entered into a cost-plus-fixed-free contract to construct an electric generator for Dalton Corporation. At the contract date, BB estimated that it would take two years to complete the project at a cost of P2,000,000. The fixed fee stipulated in the contract is P300,000. BB appropriately accounts for this contract under the percentage-of-completion method. During 2013, BB incurred costs P700,000 related to the project, and the estimated cost of December 31, 2013 to complete the contract is P1,400,000. Dalton was billed P500,000 under the contract. the gross profit to be recognized by BB Inc. under the contract on December 31,2013 us. a. P300,000 b. P100,000 c. P200,000 d. P0 9. The Robert Construction Corporation uses the percentage-of-completion method of accounting. In 2013, Robert began work on a contract it had received which provided for a contract price of P8,000,000. Other details follows: Costs incurred during the year P1,200,000 Estimated costs to complete as of December 31 4,800,000 Billings during the year 1,440,000 Collections during the year 1,000,000 What should be the gross profit recognized in 2013? a. P160,000 b. P240,000 c. P400,000 d. P1,600,000 10. In 2013, Long Corporation began construction work under a three-year contract. The contract price is P800,000. Long uses the percentage-of-completion method for financial-accounting purposes. The income to be recognized each year is based on the proportion of cost incurred to total estimated costs for completing the contract. The financial-statement presentations relating to this contract at December 31,2013 follows: Statement of financial position Accounts receivable-construction contract building Construction in progress Less contract buildings Cost-of-uncompleted contract in excess of billings P50,000 47,000 P15,000 3,000 Statement of comprehensive income Income (before tax) on the contract recognized in 2013 P10,000 The cash collected in 2013 and the initial estimated gross profit on this contract are: a. P32,000 and P10,000, respectively b. P32,000 and P160,000, respectively c. P15,000 and P160,000, respectively d. P15,000 and P30,000, respectively 11. Cortez Construction Company, Inc., entered into a firm fixed-price contract with Rod Association on July 1,2011 to construct a four-story office building. At that time, Cortez estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is P4,000,000. Cortez appropriately accounts for this contract under the zero profit method in its financial statements and for income tax reporting. The building was deemed substantially completed on December 31,2013. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract and accumulated billings to Rod under the contract were as follows: At December 31,2011 10% P350,000 P3,150,000 At December 31,2012 60% P2,500,000 P1,700,000 At December 31,2013 100% P4,250,000 - Percentage of completion Contract costs incurred Estimated costs to complete the contract Billings to Rod P720,000 P2,160,000 P3,600,000 The amount to be shown as excess of cost over billings or (billings in excess of cost) in December 31,2013 a. P(400,000) b. P260,000 c. P400,000 d. P(260,000) 12. X company uses the percentage-of-completion method of recognizing income. In 2012, work was started on a P18,000,000 job completed in 2012. Records in 2013 show the following: Progress billing P6,600,000 Costs incurred 4,500,000 Collections 4,200,000 Cost to complete 10,600,00 Gross profit recognized in 2013 was: a. P1,400,000 b. P1,200,000 c. P900,000 d. P600,000 13. In 2013 North Construction Co. was contracted to do the private road network of Subdivision Corp. for P100 million. The project was estimated to be completed in two years. The construction contract provided among other things the following: a. Five percent mobilization fee (to be deducted from the last billing) payable within fifteen days after the signing of the contract; b. Retention provision of 10% on all billings, payable with the final bill after the acceptance of the completed project; and c. Progress billings on construction are payable within seven days from acceptance. North estimated its gross margin on the project at 25%. It used the percentage of completion method of accounting. By the end of the year, North presented progress billing corresponding to 50% completion. Subdivision Corp. accepted all the bills presented except the last one for 10% which was accepted on 10 January. With the exception of the second to the last billing of 8% accepted in 2013 which was due on 3 January 2014, all accepted billings were settled. In 2013 North realized gross profit from the subdivision project the sum of a. P10,000,000 b. P12,500,000 c. P25,000,000 d. P7,500,000 14. On September 14.2013, Contractors Inc. won the bid for the construction of a 1,000 room hotel for Victoria, Inc. on the reclamation are for P1.2 billion. On the terms of payment, parties agreed the following: a. One percent mobilization fee (deductible from the final bill) payable within fifteen days after the signing of the contract; b. Retention of 10% on all billings, payable with the final bill after the acceptance of entire completed project; and c. Progress billings on construction within seven days from date of acceptance. By the end of 2013, the company had presented only on progress billing for 10% completion which Victora, Inc. evaluated and accepted on 28 December for payment in January. The company used the percentage of completion method of accounting. a. P9,800,000 b. P10,800,000 c. P12,000,000 d. P1,200,000 15. Bona constructors, Inc. has the following date for large jobs in its Jobs in Progress account (000’s omitted): Project no. Actual cost Estimated total Contract price Percent cost complete 101 P8,756 172,800 192,000 5 102 11,457 14,875 17,500 75 103 53,865 61,250 87,500 80 104 22,800 39,760 49,700 55 105 44,500 122,310 151,000 35 P141,378 410,995 497,700 The company accounts for its large jobs under the percentage of completion method. Billings are done as follows: a. 20% down payment upon contract signing. b. Balance is billed according to percentage of completion less an application of the down payment which is also according to percentage of completion. The total billings made for the large jobs is: a. P203,286 b. P99,540 c. P104,246 d. P193,786 16. Builders Construction, Inc. uses the percentage of completion method in recognizing income. In 2011, Builders Construction, Inc. was engaged by SM on a fixed-price contract to build a 4 story shopping mall. On January 1,2013, a fire damaged the accounting records of Builders Construction, Inc. the president of the company has contracted you to reconstruct the contract information. The following data were taken from the salvaged files: December 31 2011 2012 Architect’s estimated cost P7,500,000 P8,000,000 of completion Costs incurred 3,000,000 Percentage of completion 60% Income recognized to date 500,000 1,200,000 Compute for the percentage completed in 2011 on SM shopping mall a. 40% b. 25% c. 20% d. 30% 17. Mega Construction Company was awarded a contract to construct a new sewage system for MWSS for a piece of P3,250,000. The principal estimate of the cost to complete the project was P3,000,000. The contract provides for periodic progress billings. A final billing equal to 25% of the contract price is to be made upon final inspection and acceptance by the MWSS. The construction record for the system was as follows: Date Cost to incurred to date Estimated cost to complete Dec. 31,2011 P1,075,000 P1,612,500 Dec. 31,2012 2,625,000 750,000 Aug. 15,2013 3,425,000 The construction was inspected on August 15,2011, January 15,2012 and Oct. 1,2012 and progress billings equal to 25% of the contract price were made on each of these dates. The system was completed, and final inspection and acceptance took place on August 21,2013. How much is the construction in progress, net of billings in the 2012? a. P875,000, current liability b. P2,463,600, current asset c. P287,500, current liability d. P62,500, current asset 18. City Builders Construction Company which uses the percentage of completion method presented the following data relating to the 4 projects: Project A Project B Project C Project D Contract price P2,900,000 P3,400,000 P1,700,000 P2,000,000 Cost incurred, 2012 1,680,000 1,440,000 320,000 Estimated cost to complete, 1,120,000 1,760,000 960,000 2012 Cost incurred,2013 960,000 680,000 863,000 560,000 Estimated cost to complete, 1,300,000 117,000 1,040,000 2013 Operating expenses for 2012 and 2013 were P120,000 for each year. How much is the net income for the two year ended December 31: 2012 2013 a. P135,000 P309,000 b. P255,000 P489,000 c. P195,000 P429,000 d. P369,000 P135,000 19. Cebu Construction Company began operation on January 2,2013. During the year, the company entered into a contract with Tommy Company to construct a manufacturing facility. At that time, Cebu Company estimated that it would take five years to complete the facility at a total cost of P1,800,000. The total contract price for construction of the facility is P2,500,000. During the year, the company incurred P440,000 in construction costs related to the construction project. The estimated cost to complete the contract is P1,560,000. Tommy was billed and paid 30% of the contract price subject to a 10% retention. Using the percentage of completion method, how much is the excess of Construction in Progress over Contract Billings or Contract Billings over Construction in Progress? a. P200,000, current asset b. P125,000, current liability c. P200,000, current liability d. P62,50, current asset 20. Marlboro Construction, Inc. entered into a construction contract in 2012 that called for a contract price of P9,600,000. At the beginning of 2013, a change order increased the initial contract price by P480,000. The company uses the percentage of completion method for completing the project. The following data is available: 2012 2013 Cost incurred to date P4,920,000 P8,640,000 Estimated costs to complete 4,920,000 2,160,000 What gross profit (loss) should Marlboro Corporation recognized in 2012 and 2013? 2012 2013 a. (P240,000) (P720,000) b. (P240,000) (P480,000) c. P240,000 (P960,000) d. P240,000 (P720,000) 21. East Builders works on a P70 million contract in 2013 to construct a shopping mall for SM Inc. during 2013, East Builders uses the percentage of completion method of revenue recognition. At December 31,2013, the account balances were: Construction in progress P24.55 million Accounts receivable 2.4 million Contract billings 12.0 million Estimated costs to complete 31.85 million How much is the actual cost incurred in 2013? a. P24.5 million b. P49 million c. P7.5 million d. P17.150 million 22. On July 1, 2011 Summer Construction Corporation contracted to build an office building for JG Inc., for a total price of P975,000. Data relating to the project from 2011 to 2013 are as follows: 2011 cost P75,000 2012 P600,000 Contract incurred to date Estimated costs to 675,000 400,000 complete Billings to JG Inc. 150,000 550,000 Summer construction Corp. uses the Zero Profit Method. 2013 P1,050,000 275,000 What is the balance of the Construction in Progress account net of billings at December 31,2012? a. P125,000 due to JG Inc. b. P125,000 due from JG Inc. c. P25,000 due from JG Inc. d. P25,000 due to JG Inc. 23. Using the data in number 22. Assuming the use of percentage of completion method, how much is the gross profit (loss) to be recognized in 2012? a. P(47,500) b. P47,500 c. P(22,500) d. P22,500 24. West corporation company recognized gross profit of P31,500 on its long term project what has accumulated costs P61,250. To finish the project, the company estimates that it has to incur additional cost of P122,500. Billings made were 40% of the contract price. What is the balance of the Construction in Project account net of billings? a. P18,500 current liability b. P18,500 current asset c. P55,050 current asset d. P55,050 current liability 25. North Construction Company uses the percentage of completion method of recognizing gross profit on long term construction contracts. The company started work on two contracts during 2011. Data relating to the two contracts are given below: Contract price Actual cost Estimated cost to 12/31/12 complete Contract 1 P1,800,000 450,000 P450,000 Contract 2 1,350,000 262,500 487,500 in 2013. Contrast 3 was started for a contract price of P2,700,000. As of December 31,2013, the following data are available: Actual cost 1/1/12 to Estimated cost to complete 12/31/13 Contract 1 P840,000 P210,000 Contract 2 540,000 360,000 Contract 3 540,000 960,000 How much income is to be recognized in 2013? a. P1,302,000 b. P432,000 c. P642,000 d. P270,000 26. Using the data in No. 25, what is the balance of the Construction in Progress account as of December 31,2013? a. P3,222,000 b. P3,942,000 c. P1,920,000 d. P2,562,000 27. In 2009, South Builders agreed to construct a commercial building at a price of P1,000,000. South Builders uses the percentage of completion method of recognizing revenue on long term construction projects. The data relating to the projects from 2011 to 2013 are as follows: 2011 2012 2013 Cost incurred each year P280,000 P320,000 P185,000 Estimated cost to complete 520,000 200,000 Billings to date 150,000 400,000 1,000,000 Collections of billings to date 120,000 320,000 940,000 What is the amount of gross profit to be recognized in 2012? a. P800,000 b. P78,500 c. P85,000 d. P90,000 28. Using the data in No. 27, what is the balance of Construction in Projects net of Contract Billings account of South Builders’ on December 31,2012? a. P350,000 b. P300,000 c. P550,000 d. P380,000 29. Using the data in No. 27, assuming the company uses the zero profit of recognizing revenue from the project, what is the balance of the Construction in Progress account net of contract billings as of December 31,2012? a. P200,000 b. P250,000 c. P350,000 d. P300,000 30. On January 2,2013, JGG Builders Corp. of Ilocos enters into a contract to construct a building for P40,000,000. During the construction period many change orders are made to the original contract. All of the changes were accepted by both the customer and the contractor. The following schedule summarizes the change orders in 2013: Cost incurred in Estimated costs to Contract price 2013 complete Basic contract P8,000,000 P28,000,000 P40,000,000 Change order # 1 50,000 50,000 125,000 Change order # 2 50,000 Change order # 3 300,000 300,000 600,000 Change order # 4 125,000 100,000 Under the percentage of completion method, what is the gross profit to be recognized on December 31,2013 (rounded to the neared peso)? a. P907,828 b. P888,889 c. P909,063 d. P970,830 e. ANSWERS 1. 2. 3. 4. 5. A A A B B 6. 7. 8. 9. 10. A A B C B 11. 12. 13. 14. 15. C D B C A 16. 17. 18. 19. 20. C D A A B 21. 22. 23. 24. 25. D A A C C 26. A 27. A 28. A 29. A 30. A SOLUTIONS AND EXPLANATIONS 1. Under the zero profit method. The expected income on project 1 [P420,000 – (240,000 + 120,000) = P60,000] is not recognized until the project is completed. However, under this method, an expected loss on a contract must be recognized in full in the period in which it is discovered. Project 2 has an expected loss of (P20,000) [P800,000 – (280,000 + 40,000)] which must be recognized immediately in 2013. Under the percentage –of-completion method gross profit is recognize using the following formula: Costs to date X Estimated profit = Gross profit to date Total estimated costs Bell would recognize gross profit of P40,000 on project 1: P240,000 x P240,000+120,000 [420,000- (240,000+120,000)] = P40,000 Note that prior years’ gross profit need not be subtracted from P40,000 because the project commenced during 2013. Under both the percentage-of-completion method and the zero profit method, an expected loss must be recognized in full in the period in which the expected loss is discovered. Project 2 has an expected loss of (P20,000) [300,000-(280,000+40,000)] which must be recognized in full in 2013. The net gross profit recognized on the two project is P20,000 (P40,000 profit less (P20,000) loss. 2. The total expected income on the contract at 12/31/2012 is P900,000 (P9,000,000 – 8,100,000). The formula for recognizing profit under the percentage-of-completion method is: Costs to date X Expected = Profit recognize Total expected costs profit to date P6,300,000 x 900,000 = P700,000 8,100,000 This result is the total profit on the contract in 2009 and 2010. The 2009 profit recognized must be subtracted from 700,000 to determine the 2010 profit. At 12/31/2010, the total expected income on the contract was P1,200,000 (P9,000,000- 7,800,000). The income recognize in 2011 was P600,000, as computed below: P3,900,000 x 1,200,000 = P600,000 7,800,000 Therefore, 2012 income is P700,000 less P600,000, or P100,000. 3. Profit to be recognized using the percentage-of-completion method is generally computed as follows: Costs to date X Expected = Profit recognized Total expected costs profit in previous periods Not enough information is given in this problem to perform this computation, so 2013 profit must be computed indirectly. Since only construction expenses and profit are debited to the construction-in-progress (CIP account), 2012 profit must have been P17,000 (P122,000 CIP less P105,000 const.exp). Cumulative profit recognized by the end of 2011 must be P67,000 [364,000 CIP less 297,000 cumulative const.exp. (P105,000 + 192,000)]. Therefore, 2013 profit was 50,000 (67,000-17,000). CIP 2012 Exp. 10,000 2012 profit ? 2012 Profit = P17,000 2012 End. Bal 122,000 2013 Exp. 192,000 2013 profit ? 2013 Profit = P50,000 2013 End. Bal 364,000 4. Based on the information given it must be assumed that costs incurred are used to measure the extent of progress toward project completion. At 12/31/2012, the project was 20% complete and total estimated costs were P7,500,000. Therefore, costs incurred as of 12/31/2012 were 20% of 7,500,000, or 1,500,000. At 12/31/2013, the project was 60% complete and total estimated costs were P8,000,000. Therefore, costs incurred as of 12/31/2013 are 60% of P8,000,000 or P4,800,000. The costs incurred during 2013 were P4,800,000 less P1,500,000 or P3,300,000. 5. The requirement is to determine the amount of loss to be recognized in 2013 on a long term,f ixed-price construction contract. Under both the percentage-of-completion method and the zero profit method, an expected loss on a contract must be recognized in full in the period in which the expected loss is discovered. Therefore, Hanson must recognize a loss of P100,000 in 2013. Expected contract revenue Expected contract costs (P930,000 + 2,170,000) Expected loss P(100,000) P3,000,000 3,100,000 6. Contract Price Less total estimated costs: Cost to date Cost to complete Estimated gross profit % of completion (P3,600,000 / 4,800,000) P6,000,000 P3,600,000 1,200,000 4,800,000 1,200,000 75% Income recognize to date 900,000 Income recognize at 2012 600,000 Income recognized in 12/31/2013 P300,000 7. Under the zero profit method no gross profit is to be recognized since the project is not yet completed, under the percentage-of-completion method the gross profit to be recognized in 2013 is computed below: Contract price P100,000 Estimated cost: Cost to date 20,000 Cost to complete 40,000 60,000 Estimated gross profit 40,000 % of completion (P20,000 / 60,000) 33 1/3% Gross profit recognized P13,333 8. BB Inc. will earn P300,000 in total income from this project, regardless of the actual costs incurred, since it is a cost-plus-fixed-free contract. The amount to be recognized in 2013 is computed as follows: Costs incurred to date X Fixed = Income recognize Total estimated costs fee for 2008 P700,000 *P700,000+1,400,000 X 300,000 = P100,000 *Costs incurred to date plus estimated costs to complete the project. Note that the P500,000 billed under the contract is not relevant in determining the amount of gross profit to be recognized. 9. Contract price Estimated costs: Cost incurred during the year Cost to complete Estimated gross profit % of completion (1,200,000 / 6,000,000) Gross profit earned in 2013 P8,000,000 1,200,000 4,800,000 10. The cash collection in 2013 is computed below: Contract billings Less: Accounts receivable Cash collected in 2013 6,000,000 2,000,000 20% P400,000 P47,000 15,000 P32,000 The initial gross profit on the contract is computed as follows: Contract price Gross profit rate: Income recognized Const. in progress Initial gross profit P800,000 - P10,000 = 50,000 Alternative Computation: GP recognized Divided by percentage of completion: CIP = P50,000 = CP 80,000 Initial Gross Profit 11. Contract costs incurred to date, 2013 Less: Loss on contract to date: Contract price Total estimated cost Net Billings to date Costs in excess of billings 12. Contact price Estimated cost: Cost incurred Cost to complete 20% P160,000 P10,000 0.0625 P160,000 P4,250,000 4,000,000 4,250,000 ( 250,000) 4,000,000 3,600,000 P 400,000 P18,000,000 5,400,000 10,800,000 16,200,000 Estimated gross profit % of completion (P5,400,000 / 16,200,000) Gross profit realized in 2013 1,800,000 33 1/3% P 600,000 13. Contact price Gross profit rate Estimated gross profit % of completion (P5,400,000 / 16,200,000) Gross profit realized in 2013 P100,000,000 25% 25,000,000 50% P 12,500,000 14. 15. The fee received by contractor’s fee is P12,000,000 (1% of the bid price of P1.2 Billion). 20% Down payment on contract price: Total P192,000 x .20 17,500 x .20 87,500 x .20 49,700 x .20 151,000 x .20 Billing on balance, less applied down payment: (P192,000 x .80 x 0.05) – (P38,400 x 0.05) ( 17,500 x .80 x 0.75) – ( 3,500 x 0.75) ( 87,500 x .80 x 0.80) – ( 17,500 x 0.80) ( 49,700 x .80 x 0.55) – ( 9,940 x 0.55) ( 151,000 x .80 x 0.35) – ( 30,200 x 0.35) Total Total billing made for large jobs 16. Income recognized to date, 12/31/2013 Divided by percent completed Total estimated gross profit Add: Total estimated cost Total contract price Less: estimated Cost as of 12/31/2011 Estimated Gross Profit at 12/31/2011 Percent completed thru 12/31/2011 (P500,000 / 2,500,000) 17. Construction in Progress: Cost incurred to date,2012 Gross profit (loss) earned to date, 2012 (3,375,000 – 3,250,000) Balance as of December 31,2012 P38,400 3,500 17,500 9,940 30,200 P5,760 7,875 42,000 16,401 31,710 P99,540 103,746 P203,286 P1,200,000 60% 2,000,000 8,000,000 10,000,000 7,500,000 2,500,000 20% P2,625,000 ( 125,000) 2,500,000 Less: Contract billings, 2012 (3,250,000 x 75%) Current asset 2,437,500 P 62,500 18. 2012 Contract price Estimated costs: Cost incurred to date Estimated costs to complete Total Estimated Gross profit Percentage of completion Gross profit earned this year (225,000) 2013 Contract price Estimated costs: Cost incurred to date Estimated costs to complete Total Estimated Gross profit (loss) Percentage of completion Gross profit (loss) to date Gross profit earned in prior yr. Gross profit (loss) earned This year (P429,000) Project A Project B Project C P2,900,000 P3,400,000 P1,700,000 1,680,000 1,120,000 2,800,000 100,000 60% P60,000 1,440,000 1760,000 3,200,000 200,000 45% P90,000 320,000 960,000 1,280,000 420,000 25% Project A Project B Project C Project D P2,900,000 3,400,000 P1,700,000 P2,000,000 2,640,000 -02,640,000 260,000 100% 260,000 60,900 2,120,000 1,360,000 3,480,000 (80,000) (80,000) 90,000 1,183,000 117,000 1,300,000 400,000 91% 364,000 105,000 560,000 1,040,000 1,600,000 400,000 35% 140,000 -0- P200,000 P(170,000) P259,000 P140,000 2012 P255,000 120,000 P135,000 2013 P429,000 120,000 P309,000 Gross profit earned each year Operating expenses Total comprehensive income 19. Progress billing (P2,500,000 x 30%) Less: Construction in Progress Costs incurred to date Gross profit recognized: Contract price Total costs (P1,560,000 + 440,000) Gross profit % of completion (P440,000/2,000,000) Current asset 750,000 440,000 2,500,000 2,000,000 500,000 22% 110,000 550,000 P200,000 20. Using the formula under the percentage of completion method the computation is: 2012 2013 Contract price P9,600,000 P10,800,000 Estimated costs: Cost incurred to date 4,920,000 8,640,000 Estimated costs to complete 4,920,000 2,160,000 Total 940,000 10,800,000 Loss recognized to date (240,000) (720,000) Loss recognized in prior year (240,000) Loss recognized this year P(240,000) P(480,000) 21. Percentage of completion based on cost incurred to date: Construction in progress P24.5 million = 35% Divided by contract price 70.0 million Therefore, estimated cost to complete of P31.85 million is equal to 65% Total estimated cost (P31.85 million / 65%) Estimated cost to complete Actual cost incurred in 2013 P49 million 31.85 million P17.15 million 22. Compute first the gross profit (loss) to be recognized each year as follows: 2011 2012 Contract price P975,000 975,000 Less: Cost incurred to date 75,000 600,000 Estimated cost to complete 675,000 400,000 Total estimated cost 750,000 1,000,000 Estimated gross profit 225,000 (25,000) Percentage of completion 10% 60% Construction in progress net of billings – 2012: Cost incurred to date – 2012 Loss recognized in 2012 Construction in Progress Less: Billings to date (P150,000 + 550,000) Due to JG Inc. 23. Gross profit earned in 2012 2011 Revenue (P975,000 x 10%) Cost incurred (actual cost) Gross profit Gross profit To date P97,500 75,000 P22,500 2013 P975,000 1,050,000 1,050,000 (75,000) 100% P600,000 ( 25,000) 575,000 700,000 P(125,000) Gross profit recognized in Prior Years P - Gross profit recognized This Year P97,500 75,000 P22,500 2012: Revenue (P975,000 x 60%) Cost (revenue + loss) Gross profit (loss) P585,000 610,000 P(25,000) P97,500 75,000 P22,500 24. Percentage of completion (P61,250 / 183,750) Estimated gross profit (P31,500 / 33.33%) Total estimated cost (61,250 + 122,500) Contract price Construction in progress (P31.300 + 61,250) Less: Billings (278,250 x 40%) Due to 25. Gross profit recognized in 2012: Contract price Cost incurred to date Estimated cost to complete Total estimated cost Estimated gross profit Percentage of completion Gross profit earned - 2012 Gross profit recognized in 2013 Contract price Cost incurred to date Estimated cost to complete Total estimated cost Estimated gross profit Percentage of completion Gross profit recognized to date Gross profit earned in prior years Gross profit recognized this years Total gross profit recognized in 2013 33.33% P94,500 183,750 P278,250 P92,750 111,300 P(18,550) Contract 1 P1,800,000 450,000 450,000 900,000 900,000 50% P450,000 Contract 1 P1,800,000 840,000 210,000 1,050,000 P750,000 80% 600,000 450,000 P150,000 Contract 2 P1,350,000 262,500 487,500 750,000 600,000 35% P210,000 Contract 2 P1,350,000 540,000 360,000 900,000 450,000 60% 270,000 210,000 P60,000 26. Total cost incurred to date (P840,000 + 540,000 ) Total gross profit to date (P600,000 + 270,000 ++ 432,000) Construction in Progress, December 31,2013 27. Contract price Cost incurred to date P487,500 535,000 P(47,500) 2009 P1,000,000 280,000 Contract 3 P2,700,000 540,000 960,000 1,500,000 1,200,000 36% 432,000 P432,000 P642,000 P1,920,000 1,302,000 P3,222,000 2010 P1,000,000 600,000 Estimated cost to complete Total estimated cost Estimated gross profit Percentage of completion Gross profit earned to date Gross profit earned in prior year Gross profit recognized this years 520,000 800,000 200,000 35% 70,000 P70,000 200,000 800,000 200,000 75% 150,000 70,000 P80,000 28. Gross profit earned to date – 2012 Cost incurred to date Construction in progress- 2012 Less: Billings to date Construction in progress net of billings P150,000 600,000 750,000 400,000 P350,000 29. Cost incurred to date- 2012 Less: Billings to date Construction in progress net of billings , Dec.31,2012 P600,000 400,000 P200,000 30. Total contract price after change order Total cost incurred to date after change order Total estimated costs to complete after change order Total estimated cost Estimated gross profit Percentage of completion (P8,475,000 /36,875,000) Gross profit earned in 2013 P40,825,000 8,475,000 28,400,000 36,875,000 3,950,000 22.9830% P 907,828