. METHOD STATEMENT OF INSTALLATION, TESTING AND COMMISIONING OF 1 UNIT 33KV EARTHING TRANSFORMER AT PMU PULAU INDAH FOR TNB GRID REVISION HISTORY REVISION SUBMISSION DATE 0.00 30.01.2023 1.00 09.02.2023 st CHANGES 1 Submission Ammendmant – Test, Add ERP, ` TABLE OF CONTENTS TABLE OF CONTENTS....................................................................................................................... i ABBREVIATION ................................................................................................................................ iii LIST OF FIGURES AND TABLES ................................................................................................... iv 1. INTRODUCTION............................................................................................................................ 1 2. SCOPE OF METHOD STATEMENT ........................................................................................... 1 3. WORK PROCEDURE .................................................................................................................... 1 3.1. Preliminary Work.................................................................................................................... 1 3.1.1. Standard Operation Procedure (SOP) for Covid-19 ........................................................ 1 3.1.2. PTW Application and Safety Measures .......................................................................... 6 3.2. Site Setting Up Work .............................................................................................................. 7 3.2.1. List of Machine and Vehicle ........................................................................................... 7 3.2.2. Vehicle and Equipment Position and Access Route ....................................................... 9 3.3. Housekeeping and PTW Cancellation .................................................................................. 12 4. SITE LAYOUT PLAN................................................................................................................... 14 5. HAZARD IDENTIFICATION, RISK ASSESSMENT AND DETERMINING CONTROL (HIRADC)............................................................................................................................................ 15 6. JOB SAFETY ANALYSIS (JSA) ................................................................................................. 27 EMERGENCY RESPONSE PLAN…………………………………………………………………….. 7. WORK PROGRAM ...................................................................................................................... 34 8. APPENDIX 3: ECE CERTIFICATE ......................................................................................... 36 i ` 9. APPENDIX 5: LIST OF WORKERS AND NTSP CARD ....................................................... 37 10. ii ABBREVIATION Abbreviation Description CP Competent Person CIDB Construction Industry Development Board DN Distribution Network EC Energy Commission ECE Electrical Competent Engineer GCQP Grid Competent Qualified Personnel GSPP Genting Sanyen Packaging Paper JSA Job Safety Analysis kV Kilo Voltage MOH Ministry of Health NSC National Security Council NTSP NIOSH TNB Safety Passport PMU Pencawang Masuk Utama PPE Personal Protective Equipment PTW Permit to Work SSS Site Safety Supervisor TNB Tenaga Nasional Berhad WHO World Health Organization XLPE Cross-linked polyethylene iii LIST OF FIGURES AND TABLES Figures Figure Description Page 1 Working and assembly area outside PMU Pulau Indah 7 2 Access route 10 3 Cross – section of cable trenches 13 Tables Table Description Page 1 List of Machineries and Vehicles 8-9 2 JSA for works 27 6 JSA for Covid-19 38 7 Work Program for Cable Laying Work 39 iv 1. INTRODUCTION ELEKTRON BERKAT Sdn. Bhd. Will conduct the works disassembly and for Installation, Testing and Commissioning Of 33kv Earthing Transformer at PMU Pulau Indah. 2. SCOPE OF METHOD STATEMENT The scope of method statement (under TNB Grid) covers for disassembly of 33kV Earthing Transformer Installation Testing and Commissioning. 3. WORK PROCEDURE 3.1. Preliminary Work 3.1.1. a. Standard Operation Procedure (SOP) for Covid-19 World Health Organization states that the Covid-19 virus affects different people in different ways. The WHO states that the common symptoms include: i. Fever ii. Tiredness iii. Dry cough Other symptoms can include: i. Shortness of breath ii. Aches and pains iii. Sore throat iv. And, in a few cases, people may report diarrhea, nausea or a runny nose It is believed that up to 30% of those infected do not show any symptoms and so cleanliness and social distancing must be maintained. 1 ` Reference: National Security Council (NSC), Ministry of Health (MOH) (Covid 19: Management Guidelines for workplaces), CIDB (Guidelines of Covid 19 Prevention Practices at Construction Site), Occupational Safety & Health Act 1994. b. The following advice is derived from general advice provided by the WHO. Basic protective measures against COVID-19 as below: i. Frequent hand washing by crew using soap and warm water or alcoholbased (at least 65-70%) hand rub for 20 seconds. ii. Advised to use liquid-based soap Avoidance of touching the face including mouth, nose, and eyes with unwashed hands (in case hands have touched surfaces contaminated with the virus). iii. Workers should be encouraged to cover their nose and mouth with a disposable tissue when sneezing, coughing, wiping, and blowing the nose, then dispose of the used tissue immediately. iv. If a tissue is not available, one should cover their nose and mouth and cough or sneeze into a bent elbow. v. All used tissues should be disposed of promptly into a waste bin vi. Workers should aim to maintain social distancing and keep at least one meter distance from other people, particularly those that cough or sneeze or may have a fever. If they are too close, other crew members can potentially breathe in the virus. vii. Meat, milk, or animal products should always be handled with care, to avoid cross contamination with uncooked foods, consistent with good food safety practices. The consumption of raw or undercooked animal products is to be avoided. viii. c. A medical log should be maintained. Personal Protective Equipment i. The routine uses of PPE including surgical masks, gloves and face shields is only recommended for those near infected persons. Social distancing measures should prevent the need to wear surgical mask during site work and as well while travelling to and from towork site. The use of KF94 respirator mask or surgical mask and gloves isrequired to reduce encountering infected person ii. The WHO advice the following on the use of face masks: 2 ` If you are healthy, you only need to wear a mask if you are taking care of a person with suspected Covid-19 infection. Wear a mask if you are coughing or sneezing. Masks are effective only when used in combination with frequent handcleaning with alcohol-based hand rub or soap and water. If you wear a mask, then you must know how to use it and dispose of it properly. Make sure there are no gaps between face and the mask. Avoid touching the mask while using it; if you do, clean your hands with alcohol-based hand rub or soap and water. To remove the mask: remove it from behind (do not touch the front of mask); discard immediately in a closed bin; clean hands with alcoholbased hand rub or soap and water. d. Responsibilities i. Project Manager Ensure that resources are sufficient to conduct the function safely and that the study is carried out in compliance with the NSC, MOH Covid-19 Guideline, CIDB & DOSH. Responsible for the overall site compliance of the Covid 19. ii. Project Engineer / Site Supervisor / Safety & Health Officer / Site Safety Supervisor Ensure the employees are tested for Covid-19 before commence work at site. Ensure the list of approved employees is prepared and send to the nearest police station for travel authorization. Staff and workers not on the name list are not permitted to access the project site. Ensure all workers registered via My Sejahtera before entering the premises. Do not allow any other staff or personnel to access the project site without the permission of MITI. Staff and workers to take temperatures daily and check for respiratory symptoms. Temperature more than 37.5oC not permitted to work. Provide TNB Standard Form as per Appendix 1 and record workerstemperature reading on daily basis. 3 ` Safety signage on COVID-19 & regular reminders in tool box talk are encouraged as part of awareness in daily operation & works on site to all parties. Social distancing to be always maintained (1 meter). Provide briefing and training for control measures of Covid -19 outbreak to all the employees and sub-contractors, suppliers, and vendors. Site Personnel and workers should be briefed and informed on the risk of exposing to COVID-19, including proper hygiene methods to ensure safety of all at project site. Ensure the transportation vehicle (interior) is sanitized before and after sending the workers to project site and home. Consider obtaining travel declaration from employees and workers on travel history. Ensure the compliance of PPE Usage such as face mask (3-ply/reusable) and hand gloves at all time. (Mandatory requirements). The reusable face mask shall be cleaned often. Ensure the staff and workers are sanitized their hands regularly. Suggest for frequent hand wash as well using liquid soap prepared at the site office toilet. Provide suitable and sufficient rubbish bins for hand towels, face mask and gloves with regular removal and disposal. Do not allow any staff to come to work with Covid -19 symptoms such as flu, cough, difficulties in breathing, sore throat and fever. Break times should be staggered to reduce congestion and contact at all times. Control and monitor number of workers before enter, during works and leaving the site. Screening procedure via thermal sensor daily shall be applied to staff and workers before enter the site. iii. Sub-Contractor/Workers Worker Leader should ensure social distancing is applied during transportation to and from site. Worker Leader should ensure all workers is fit to works before enter site and to pass through screening process daily (thermal sensor by Main 4 ` contractor personnel). Those reading 37.5oC & above not allowed to enter site. Register via My Sejahtera before entering TNB Premises. Attend briefing on the Covid-19 control measures before commence work at site. Carry out regular housekeeping at the workplace and ensure social distancing 1.5-2 meters to be maintained at all time. Fill up the TNB Standard Form as per Appendix 1 in daily basis. Re-usable face mask should be thoroughly cleaned after use and not shared between other workers. The reusable face mask should be properly washed after use and not shared with another worker. The disposable face mask will be disposed of on a regular basis and no longer using the disposable face mask for more than 1 day. Dispose it the designated rubbish bin provided at site. Regularly clean & sanitize the inside of vehicles cabs and between uses by different operators (Mobile crane, Sky lift, Lorry, Excavator, Back-hoe, Compactor & etc). Direct visiting truck drivers to remain in vehicles and use contact-less methods such as mobile phones to communicate with your workers wherever possible. Do not share tools and equipment with other workers. Ensure all the workers have their own tools to carry out the job. Rubbish collection and storage points should be increased and emptied regularly throughout and at the end of each day. Remind colleagues to report if they observe another work colleague is displaying any unhealthy/potential symptoms relating to COVID 19. Prohibit any colleagues who have showed symptoms or contracted with COVID-19 to return to work place until they have medical evidence, they are clear from the virus. The workers should be asked to bring pre-prepared meals and refillable drinking bottles from home. Workers not allowed go out from the project site during the break time. Sub-con can provide packed food to the respective workers if needed. 5 ` Report to SHO/SSS if any of the staff and workers are having any unhealthy/potential symptoms relating to Covid-19. 3.1.2. a. Adhered to the PPE compliance at all time. PTW Application and Safety Measures This method statement must be presented to TNB Grid and approved by relevant approval authority prior PTW issuance. b. ECE shall properly verify and inspect that the site / work area is safe to carry out installation work before any work commencement. Among things to verify are yard condition, trenching, identifying live parts, obstacles, and others. c. ECE shall ensure sufficient and suitable road access for machinery to move into and work within the work area. d. AP TNB Grid and ECE will carry out barricade. Barricade of plastic red chain (indicate Live Parts) and plastic yellow chain (indicate work area) will be used. The barricade and signage shall not be removed until work completion and only with authorization of the AP TNB Grid and ECE. e. Site Safety Supervisor to ensure all workers are equipped with proper PPE. For this cable laying work, minimum PPE as below shall be adhered: i. Safety helmet ii. Safety boot with Steel Toe iii. Reflective vest jacket iv. Glove 6 f. AP TNB Grid, ECE, then will carry out assessment of the assembly area during emergency period. Figure 1: Working and Assembly Area Outside PMU Pulau Indah g. AP TNB Grid then will issue the PTW to the ECE certified by EC and CP TNB GD at site. Appendix 2 shows the ECE Certificate for this project. h. Safety tool box talk lead by ECE and AP TNB Grid to all workers will be carried out. Appendix 4 show the list of Workers that will involve for this project. The contain of tool box talk to all workers will cover: i. ii. Scope of Work Hazard and Control Measures iii. Boundary Work Area as Figure 1 iv. Assembly Area during Emergency Period as Figure 1 v. vi. Usage of PPE Adhere of SOP Covid-19 as Section 3.1.1 3.2. Site Setting Up Work 3.2.1. a. List of Machine and Vehicle Table 1 below shows the list of machineries and vehicles that will be used during theproject: 7 ` LIST OF MACHINERY & TOOLS No Machine/Equipment Quantity 1 Hand Tools 2 2 Complete Spanner Set, Cutring Pliers, Tube Cutters, Screwdriver Set Hammer Hack Saw Adjustable Wrench 2 4 Plastic wrap (to wrap cable ends) 1 5 Traffic Cone 10 6 Crowbar 2 7 Torque Wrench 1 8 ` No Machine/Equipment Quantity 7 Crimping Tool 1 8 Drilling Machine 1 9 4 x 4 Pick Up 1 10 Testing Equipment for Cable & ETx 11 Lorry Crane 20T 1 12 Water Jet 1 Table 1: List of Machineries and Vehicles 9 LOT 3.2.2. Vehicle and Equipment Position and Access Route The location of equipment that will be used during jointing cable work will be at placed inside the PMU Pulau Indah. The access route and location of vehicle are also placed inside the PMU Pulau Indah. Figure 2 below shows the access route and working area Figure 2: Access route 1 0 3.3 Disassemble Earthing Transformer 3.3.1 Remove all CT wiring, control wiring, AC and DC supply cables. Remove from conduit and secure them so that no water enters the cables. Place cable securely in the cable trench. Label all cables that are removed. Ensure all ferule numbers are secured and taped. 3.3.2 End Cap shall be fixed at Power Cable ends. 3.3.3 Do not Remove bushing complete with current Transformer and place in wooden crate and secure for storage. 3.3.4 Drill 30mm diameter holes, 300mm deep x 6 locations on the pad after removal of transformer. 3.3.5 Remove diverter switch and place in wooden crate and secure for storage. 3.4 Preparation of transportation: 3.4.1 Using crane of appropriate size (20 Ton), lift the transformer tank from the pad. 3.4.2 Crane and low bed truck to be supplied by others. 3.4.3 Transport Earthing Transformer to EWT Factory. On the Lorry Crane the Transformer shall be tied with an appropriate belt. 3.4.4 To provide material listing of what needs to be removed. And to sign the checklist/ official letter. 3.4.5 Ensure the 33kV cables, Aux transformer and NER is not damaged during this exercise. 3.4 Lifting a. Before lifting work is commencing, several activities as below need to done: i. Inspect the materials that shall be used to lift load. Any defective materials shall not be used and shall be replaced. ii. Ensure that rope or chain is secured to the designated lifting hook. iii. Ensure that the both end of the rope / chain are properly secured. iv. Ensure that the are below the load lifting is cleared. v. Ensure that no hands or foot are placed underneath the load while placing the load on its location. vi. Ensure that sufficient work area is available for the lifting. vii. Ensure that the load swing radius is minimized while lifting using viii. guide rope attached to the load. ix. Ensure that the lifting process is carried as smooth as possible 3.3. Housekeeping a. Once the above works as stated completed, the working personals have to ensure that there are no materials leftover in the switchyard area and at the respective cable ends. b. During Transformer being serviced and repaired at EWT, the oil spill on the 11 chipping stone will be either washed and gathered at one area and packed with a proper packaging. The works we shall conduct a proper checklist and later hand over to Grid Maintenance for disposal. 12 ` 13 LORRY CRANE POSITION WORKING AREA ` 3.4. Transformer Installation Works 1. Upon Transformer delivered to site Pulau Indah, We will coduct a visual Inspection to ensure Earthing Tx is in good order. 2. It is ensured that the access is clear to shift the transformer. 3. Move the transformer manually to the transformer location. 4. For manual handling, rollers are used to facilitate forward motion to find the erection place. 5. After the transformer positioning, all wheels will be locked to arrest any movement of the transformer by providing the necessary stopper. And skid based. 6. All the incoming and outgoing cable supports, cable ends and termination fittings required for MV, LV, and control cables will be tested prior to installation. 7. For the Multicore cable connected to the Transformer accessories a connectivity test and functional test will be carried out. 8. Inspection request for transformer installation prior to the start of any cable termination work will be done. 9. The transformer skids shall have rounded off beam ends and shall be provided with pulling lugs/holes to enable site movements. 10. All the holes for fixings bolts and provisions for passage of cables etc. are provided as required. The alignment of the Earthing Transformer wil be conducted during offloading on the Transformer Plinth. 11. The installation of cables, wires, raceways, supports, cable ends, and termination fittings will be done in accordance with the appropriate sections of the project specification and/or as shown on the approved shop drawings. All the electrical connectors and terminals will be tightened according to the manufacturer’s published torque-tightening values. The torque force is as per name plate. 3.4.1 Testing of Earthing Transformer 1. 2. 3. 4. 5. 6. Winding Power Factor (TNB to Test) Oil Power Factor (TNB to Test) Impedance Voltage Test Winding Resistance Test Polarization Test Oil Break Down Voltage (To Compare with OEM Factory Routine Test Report) 3.4.2 Cable Test 1. Meggar Test 14 ` 4. SITE PICTURE 15 SITE LAYOUT WORKING AREA LORRY AREA 16 4.0 Emergency Response Plan This procedure defined the following requirements: Method to carry out to eliminate or minimize the impacts and risks from the emergency events on the environment, employees, the public and surrounding e.g. neighbor. Method to respond promptly to changes during emergency that may be associated with them. 4.2 REFERENCE (S) ISO 14001: 2015 ISO 45001: 2018 HSE-102-01 SPM-HSE-01 4.3 4.4 DEFINITION (S) NO TERMS DESCRIPTIONS 1. ISR IMS System Representative 2. ERT Group Emergency Response Team Group 3. Spill Any accidental release of a liquid with hazardous effect. 4. Minor Spill Spillage in small amount or area, which is localized and easilycontained. 5. Major Spill Spillage is large and may flow out of factory and cause injury ordamage to the properties and environment or 6. Normal Working Day Working day that include administration staff and production staff. 7. Off Day Working day for Production Staff only. 17 RESPONSIBILITIES AND AUTHORITIES NO 4.5 Clause 8.2 Emergency Preparedness and Response Clause 8.2 Emergency Preparedness and Response Nonconformity and Corrective Action. Clause 8.9 Emergency Preparedness and Response PERSON-IN CHARGE 1. Project Manager 2. ISR 3 ERT Group RESPONSIBILITY AND AUTHORITY Approved any relevant information that to be communicated tothe external parties Implementation and maintenance of the procedures Review with ERT and HSE Safety Committee after any incidents or accidents To be the first team to control in case of any emergency situationoccurred RECORDS All records identified within the procedure shall be maintained according to the retention tspecified. 4.6 PROCEDURES 4.6.1 General a) The potential emergencies are divided into few categories. i) By activity, product or services on routine, non-routine and emergencies - Fire, explosion, spillage, injuries or accidental discharges of gases or released to air, water and land ii) By locations or locality - Bomb-threat, floods etc. iii) By others - Severe Acute Respiratory Disease, hysteria, mental disorder b) ERT Members, Top management, Security personnel, Safety and Health Officer, Administration Manager, HSE Safety Committee and Receptionist shall be responsible to deal with Emergency Response. c) The applicable equipment shall be located at the potential emergencies are occurred e.g. i) Emergency Kit e.g. Spill clean-up kit is stationed at the potential spillage areas. ii) Eye wash and shower is provided at various locations for any chemical splash. iii) Personnel protective equipment (PPE) is stationed in strategic location. iv) Firefighting equipment are available at all strategic locations. d) The emergency response plan shall be established and updated if significant changes to Layout,process etc. e) Fire or emergency evacuation drill shall be carried out at least once per year and record shall be recorded in Drill Report (DR) by ERT group. f) Fire drills training shall be carried out together or separately from evacuation drills training and chemical handling training. All drills shall be recorded and reviewed for effectiveness of the procedure, Function of equipment, mobility of ERT members and response taken. g) The emergency plan is considered normal working day, off day and public holiday. h) The maintenance of firefighting equipment shall be carried out by Human resource and Administration department and the relevant records are kept accordingly. 18 4.7 Competencies of ERT Members 4.7.1 The general competencies of ERT members are described below; NO 1. Education 2. Experience 3. 4. 4.8 COMPETENCY Training/Skills Personality DESCRIPTIONS Minimum Secondary Level Minimum one-year work experience in service or manufacturingenvironment. Fundamentals and detail of ERT training; a) First aid and CPR training b) Hazardous waste operations and emergency response c) Spillage clean-up. d) Handling of the emergencies, hazard classification, SDSunderstanding, hazard identification and assessment, monitoring equipment, first aid, Fire control, Physically fit, no health problem Communication 4.8.1 During emergency event shall be done through telephone and PA system, hailers, and fire alarms.Public Address System shall be maintained for emergency. 4.9 Evacuation plan or layout 4.9.1Evacuation plan or layout shall be located at all strategic place and updated if any changes occurred that affected the escape route entry. The layout plan shall be reviewed by theERT Team when there is any layout change. 4.9.2 During emergency, all employees shall assemble at designated Assembly Area as identify in the Emergency Plan. 4.9.3 Emergency Handling Flowchart shall be as Attachment A. 19 4.9.4 The Emergency response plan for fire or spillage shall follow accordingly to flowchart in Attachment A. 4.9.5 The Safety Officer and Fire Squad Leader with the BOMBA shall coordinate the Fire Investigation. 4.9.6 All accident, incidents and near misses shall be investigated by SHO and HSE Safety Committee and responsible department’s personnel as shown in the HSE-102-01 Non-Conformance Corrective Action. 4.9.7 The ERT member shall be trained on handling of the following matters; 4.9.7.1 First aid and CPR 4.9.7.2 Fire and Spilled Control 4.9.7.3 Use of all emergency equipment such as fire extinguisher PPE, 4.10 Emergency Spills of Chemical and Waste Chemical 4.10.1 The purpose is to ensure members are equipped to control any liquid spillages in a controlled andsafe manner. 4.10.2 HOD shall maintain the emergency spill kits. Checking must be made to ensure all equipment ispresent and in a satisfactory condition. 4.10.3 The equipment may set out around the site and contains Rubber Gloves, Protective Glasses, Shovels, Sand Bags, and Emergency Contact List. 4.10.4 All concerned member who handles the chemical shall be trained to contain liquid spills. The members shall be authorized and will be instructed on how to contain and clear up all chemical spills in a safe and organized manner. Only members who are authorized should attempt to contain any spills. 4.10.5 Emergency System - Trained Member, please ensure your own safety. If there is doubt over the identity of the chemicals, or known high risk in the containment of the chemicals, contact the ‘Emergency Services’ or MR or Safety Officer immediately. Block off all drains and ensure chemicaldoes not enter drainage system. Identify the chemical or chemicals to establish the necessary containment method. Using the equipment provided and ensures the chemicals is trapped in the smallest possible area allowing capacity for further spillage and if possible, stop or reduce the rate of leak. 4.10.6 For other Emergency System-Untrained Member, please ensure your own safety and evacuate theimmediate vicinity. Contact the Security and recognized member. 4.10.7 When the spill has been contained, the responsible manager shall issue official notification and thepillage must then be cleaned up and residue disposed of in accordance with the recommendations given on the CSDS and identify as a Schedule waste according to Schedule Waste, Regulation, 2005. 4.10.8 Spillage Recording: Records of all spills will be completed as HSE-102-01 Non-conformance and Corrective Action. 4.11 Other Types of Emergencies 4.11.1 Other type of emergencies except fire, spillage and explosion, the ERT are still responsible to managed and control the emergencies situation. 4.11.2 In case of electrical failure, the respective department will responsible to handle the situation. 4.12 Incident Review 4.12.1 4.12.1.1 4.12.1.2 4.12.1.3 4.12.1.4 4.12.1.5 4.12.1.6 4.12.1.7 4.12.1.8 20 All emergency response actions shall be reviewed and the results provided to the HSE Safety Committee. If necessary, to raise incident report as specified and the following items to be included in the review should include at a minimum: Description of incident, including events leading up to the emergency situation Employees response Root causes Potential system or procedural failures Corrective actions Required changes in policies, procedures or instructions Lessons learnt from external incidents Follow-up training or communications. 1) Flow Chart of Break Out of Fire During Working Hour FLOW CHART FLOW DESCRIPTION 1. Nearest person to react by using Fire Extinguisher. 1. If uncontrolled - Break glass. 1. Employee determine the fire location from thefire indicator panel. 1.1 Call Fire Brigade (Bomba). 2. Designated Admin. Officer announce the incidentand follow by evacuation. 1. Department Heads/ supervisors standby and evacuate after the announcement. 2. Department Heads/21 ERT Leader instructmaintenance to cut off electricity. 1. Security/ ERT Leader guide Bomba to the location. 2. ERT Team hand over the situation to Bomba and evacuate. 1. Department Heads/ supervisors take his departmentattendance. 2. Any missing person must be reported to Fire Department (Bomba). 2) Flow Chart of Break Out of Fire After Working Hour FLOW CHART FLOW DESCRIPTION 1. Nearest person to react by using Fire Extinguisher. 1. If uncontrolled - Breakglass. 1. ERT shall determine the fire location from thefire indicator panel. 2. Call Fire Department (Bomba). 3. Security call Human Resource Department Head andERT Leader 22 1. Duty Supervisor standby and evacuate after thealarm bell. 1. HSE Officer guide Bomba to the affectedlocation. . 1. Duty Supervisors take his department attendance. 2. Any missing person must be reported to Fire Department (Bomba). 3) Flow Chart of Hysteria Procedure FLOW CHART FLOW DESCRIPTION 1. Nearest control staff informs Department Heads/ Supervisors. 2. Department Heads/ Supervisors isolate the victim. 3. Department Heads/ Supervisors inform HRDHead, ERT Leader and First-Aider. 1. First-Aider submit report to HSE Department Head. 23 1. HSE Department Head explain to General Manager. 4) Flow Chart of Severe Injuries Procedure FLOW CHART FLOW DESCRIPTION 1. Nearest person to accident inform Department Supervisors or Department Heads 2. Department Supervisors/ Department Heads inform Human Resource Department Head, ERT Leader and FirstAider. 1. Human Resource Department Head immediately callpolice, ambulance and the victim family. 24 1. The Department Head concern shall submit an accident report to Human Resource Department. 2. ERT, Human Resource Department Head and Department Heads compile an Accident Correctiveand Preventive Action Report. 1. Human Resource Department Head reports toGeneral Manager. 5) Flow Chart of Chemical/ Diesel Spillage Procedure FLOW CHART FLOW DESCRIPTION 1. The Department Technician/ Department Supervisorshall inform to the ERT in case the chemical/ diesel spillage is out of control. 2. The ERT shall immediately respond and assist to clean up the chemical spillage using absorbent cloth and wearing personal protection equipment. In case the chemical/ diesel spillage flow into the perimeter drain, immediate action shall be taken by placing sand bag at the outlet drain. 1. The Department Technician/ Department Supervisor shall inform his Department Head and HSE Department Head. 25 1. After cleaning, the waste shall be put in containerand stored in scheduled waste storage area. 1. Department Head submit Accident Report toHSE Department Head. 1. HSE Department Head report to General Manager. 1. ERT take control of the area 1.1 No traffic passing ` 1.2 No work are continued 1.3 First Aid - if have 5. HAZARD IDENTIFICATION, RISK ASSESSMENT AND DETERMINING CONTROL (HIRADC) 26 ` 27 ` 28 ` 29 ` 30 ` 31 ` 32 ` 33 ` 34 ` 24 ` 25 ` 26 ` 6. JOB SAFETY ANALYSIS (JSA) This section describes the safety aspect that required worker attention and explains the potential risk and control measures for each activity as describe in the Section 3. Potential Risk for each step of activities has been identified and control measures need to be taken before and while carrying out the job. 6.1. JSA for Transformer ACTIVITIES POTENTIAL CONTROL MEASURES RISKS Setting up of Lorry Crane Lorry Crane topples down Toolbox briefing to conduct on daily basis before start work. Ensure the lorry crane have valid PMA and the operator have competency from DOSH. PERSON INCHARCE GCQP Site Engineer SSS Supervisor (Subcon) Ensure the ground is firm and in good condition. Provide steel plate if the ground is soft. Timber padding to provide for the outriggers. Wear safety helmet, safety shoes & gloves. Operation of Falling from Cordon off work area and display warning signage. the lorry crane. height Ensure the workers are experienced to perform the job. GCQP Site Engineer SSS Supervisor (Subcon) Wear safety shoes, safety helmet, safety harness full body harness & gloves 27 ` ACTIVITIES POTENTIAL RISKS Sharp edges from structure CONTROL MEASURES PERSON INCHARCE Identify and avoid any sharp edges. GCQP Wear safety shoes, safety helmet, Site Engineer safety harness full body harness & SSS gloves. Supervisor (Subcon) Falling Cordon off work area and display warning signage. material Ensure there is no workers underneath the work area. Ensure the working tools & GCQP Site Engineer SSS Supervisor (Subcon) equipment secured with lanyard attached to the pouch/bag of the workers who’re climbing to the structure. Wear safety shoes, safety helmet, safety harness full body harness & gloves. Hot weather (Dehydration) Drink small amounts of cool water GCQP frequently to prevent dehydration. Site Engineer Drink throughout the day to relieve SSS thirst. Supervisor Ensure the worker are fit to work (Subcon) and if they’re not well do not let them to work at height. Rainy/Stormy Weather Stop work immediately. GCQP Ensure the workers stays out from Site Engineer switchyard and goes to dedicated rest area. 28 SSS ` ACTIVITIES POTENTIAL RISKS Manual CONTROL MEASURES Do not carry excessive weight and weight to be known prior to carry. Handling (Ergonomics) PERSON INCHARCE GCQP, Site Engineer, Correct body posture while carrying the load. Request for additional manpower if the load is heavy. Wear safety shoes, safety helmet, SSS & Supervisor (Subcon) safety harness-full body harness & gloves. Struck by Ensure the workers are experienced to perform the job. object Wear safety shoes, safety helmet, safety Concrete Slab Engineer, Ensure the working tools in good condition. Lifting the GCQP, Site harness-full body harness & SSS & Supervisor (Subcon) gloves. Electrocution Safety clearance to be obtained & adhered at all time while working GCQP, Site Engineer, in LIVE substation. Wear safety shoes, safety helmet, safety harness full body harness & gloves. Sharp edges Identify and avoid any sharp edges. Wear safety shoes, safety helmet, from structure SSS & Supervisor (Subcon) GCQP, Site Engineer, safety SSS & 29 ` ACTIVITIES POTENTIAL CONTROL MEASURES RISKS Wear safety shoes, safety helmet, safety harness full body harness & PERSON INCHARCE Supervisor (Subcon) gloves. Slips, trips & falls Clear obstruction Maintain good housekeeping GCQP, Site Engineer, Wear proper PPE SSS & Supervisor (Subcon) Cable damage To conduct safety briefing Check the live cable condition GCQP, Site Engineer, before the installation. If the cable is found to be defective, it shall not be installed and arrangement made for it to be SSS & Supervisor (Subcon) returned to the supplier for replacement. Hot weather Drink small amounts of cool water frequently to (Dehydration) GCQP, Site Engineer, prevent dehydration. Drink throughout the day to relieve thirst. Ensure the worker are fit to work and if they’re not well do not let SSS & Supervisor (Subcon) them to work at height. Rainy/Stormy Stop work immediately. GCQP, Site Engineer, Weather 30 6.2. JSA for working near live area ACTIVITIES PERSON IN- POTENTIAL RISKS CONTROL MEASURES Arc / electric shock radiation (Other services including TNB cables) Cable marker / cable slab Turn off the cable Trial hole GCQP, Site Engineer, SSS & Supervisor (Subcon) Create utility mapping Cable marker / cable slab Make a site visit with the Utilities involved Trial hole GCQP, Site Engineer, SSS & Supervisor (Subcon) Wearing mask and goggle GCQP, Site Engineer, SSS & Supervisor (Subcon) Wearing ear plug Scheduled the work Use the jack liner before starting work Check site conditions before and after work GCQP, Site Engineer, SSS & Supervisor (Subcon) GCQP, Site Engineer, SSS & Supervisor (Subcon) Live Cable / Serious Injury, Fatal Digging other services include gas pipes, telecommunications lines, water or sewage and other utilities Respiratory disorders and eye pain Soil dust Hearing impairment Noise pollution Machinery is upside down Unstable position of excavator 31 CHARCE ` Fall in the gutter Create area barriers Install cones and safety notice boards Provision of cones, safety signage and traffic control Wearing PPE Unsealed gutters Collided with a vehicle Traffic is busy with vehicles Summoned by the Department of Environment (DOE) / fell due to slippery GCQP, Site Engineer, SSS & Supervisor (Subcon) GCQP, Site Engineer, SSS & Supervisor (Subcon) Inspect the machinery before starting work Scheduled maintenance GCQP, Site Engineer, SSS & Supervisor (Subcon) Do a site inspection before starting work Wearing PPE GCQP, Site Engineer, SSS & Supervisor (Subcon) GCQP, Site Engineer, SSS & Supervisor (Subcon) Leaking engine / hydraulic oil Bitten by venomous animals/insects Landslides and injuries. Unstable ground / cliff conditions Fainted Install scaffolding/shoring on ditches for a depth of more than 1.5 meters Ensure that the distance between vehicles/building materials/soil waste and drains is not less than 1 meter Rest / less exposure period / change of employee Scorching hot weather Table 5: JSA for working near live area 32 GCQP, Site Engineer, SSS & Supervisor (Subcon) ` 6.3 JSA for Covid-19 ACTIVITIES POTENTIAL RISKS Carry out work Interact with workers who have symptoms of Covid-19 or come in contact with surfaces contaminated with the Covid19 activities at the TNB project site during and after the PKP implementation period CONTROL MEASURES Regularly checks body temperature and covid symptoms for employees prior to entering PERSON INCHARCE GCQP, Site Engineer, SSS & Supervisor (Subcon) the project site Often wash your hands with water and soap/hand sanitizer before and after work Practicing social distancing of at least 1 meter Wears 3 ply surgical mask double with a cloth mask / Wears 4 ply surgical mask (KF94) Table 6: JSA for Covid-19 33 GCQP, Site Engineer, SSS & Supervisor (Subcon) GCQP, Site Engineer, SSS & Supervisor (Subcon) GCQP, Site Engineer, SSS & Supervisor (Subcon) ` 1. WORK PROGRAM CABLE LAYING WORK FOR INSTALLATION OF 33KV AT PMU PULAU INDAH Working Days TASK 1 2 31 Days PTW APPLICATION SETTING ALL EQUIPMENT MOBILIZE TEAM AND DISASSMBLE EARTHING Tx ARRANGE AND TAGGING ALL CABLES LOADING EARTHING TX ON LORRY CRANE OEM REPAIR EARTHING TX HOUSEKEEPING OIL SPILL UNLOAD EARTHING TX INSTALLATION EARTHING TX TESTING EARTHING TX HOUSEKEEPING Table 7: Work Program for Disassemble and Installation of Earthing Transformer 34 32 33 34 ` 1. APPENDIX 3: ECE C 35 36 ` APPENDIX 5: LIST OF WORKERS AND NTSP CARD VALIDITY. Identity Card No. 1. Name Muhammad Izzuddin Bin Hassanuddin Number 990522-08-7533 NTSP Card Number / Validity TNB052285SP CIDB Validity Dose 1 Dose 2 Vacci nation Vacci nation Booster Vaccination / / / / / / / / / / / / / / / 1990522PR1800321865 VALIDITY: 11/02/2023 (Pending Renewal) 2. Annuar Bin Mohamad 790412-01-6033 VALIDITY: 22/05/2023 TNB0083663N W11221120110132 VALIDITY: 19/01//2025 Validity:12/04/2023 1000715PH2100270867 3. Muhammad Irwan Ikhwal 000715-06-0655 TNB07880302-06 VALIDITY: 24/08/2024 4. Zurulhafizie Bin Mhd Idrus B21140420160051 951102-08-5871 TNB039550N VALIDITY: 24/05/2025 5. Mohd Firdaus Bin Mahadzer Validity: September/2026 980428-02-5927 TNB08015302-06 Validity:30/09/2024 37 Validity: 01/01/2023 (*To be renewed) 1980428KD2100296844 Validity:28/04/2023 38 ` NO. KAD NTSP KAD CIDB 1 39 ` 2 40 ` 3 41 ` 4 42 ` 5 43 ` Appendix: Calibration Certificate