METHOD STATEMENT OF INSTALLATION,
TESTING AND COMMISIONING OF 1 UNIT 33KV
EARTHING TRANSFORMER AT PMU PULAU
INDAH FOR TNB GRID
REVISION HISTORY
REVISION
SUBMISSION DATE
0.00
30.01.2023
1.00
09.02.2023
st
CHANGES
1 Submission
Ammendmant – Test, Add ERP,
`
TABLE OF CONTENTS
TABLE OF CONTENTS....................................................................................................................... i
ABBREVIATION ................................................................................................................................ iii
LIST OF FIGURES AND TABLES ................................................................................................... iv
1. INTRODUCTION............................................................................................................................ 1
2. SCOPE OF METHOD STATEMENT ........................................................................................... 1
3. WORK PROCEDURE .................................................................................................................... 1
3.1.
Preliminary Work.................................................................................................................... 1
3.1.1.
Standard Operation Procedure (SOP) for Covid-19 ........................................................ 1
3.1.2.
PTW Application and Safety Measures .......................................................................... 6
3.2.
Site Setting Up Work .............................................................................................................. 7
3.2.1.
List of Machine and Vehicle ........................................................................................... 7
3.2.2.
Vehicle and Equipment Position and Access Route ....................................................... 9
3.3.
Housekeeping and PTW Cancellation .................................................................................. 12
4. SITE LAYOUT PLAN................................................................................................................... 14
5. HAZARD IDENTIFICATION, RISK ASSESSMENT AND DETERMINING CONTROL
(HIRADC)............................................................................................................................................ 15
6. JOB SAFETY ANALYSIS (JSA) ................................................................................................. 27
EMERGENCY RESPONSE PLAN……………………………………………………………………..
7. WORK PROGRAM ...................................................................................................................... 34
8. APPENDIX 3: ECE CERTIFICATE ......................................................................................... 36
i
`
9. APPENDIX 5: LIST OF WORKERS AND NTSP CARD ....................................................... 37
10.
ii
ABBREVIATION
Abbreviation
Description
CP
Competent Person
CIDB
Construction Industry Development Board
DN
Distribution Network
EC
Energy Commission
ECE
Electrical Competent Engineer
GCQP
Grid Competent Qualified Personnel
GSPP
Genting Sanyen Packaging Paper
JSA
Job Safety Analysis
kV
Kilo Voltage
MOH
Ministry of Health
NSC
National Security Council
NTSP
NIOSH TNB Safety Passport
PMU
Pencawang Masuk Utama
PPE
Personal Protective Equipment
PTW
Permit to Work
SSS
Site Safety Supervisor
TNB
Tenaga Nasional Berhad
WHO
World Health Organization
XLPE
Cross-linked polyethylene
iii
LIST OF FIGURES AND TABLES
Figures
Figure
Description
Page
1
Working and assembly area outside PMU Pulau Indah
7
2
Access route
10
3
Cross – section of cable trenches
13
Tables
Table
Description
Page
1
List of Machineries and Vehicles
8-9
2
JSA for works
27
6
JSA for Covid-19
38
7
Work Program for Cable Laying Work
39
iv
1. INTRODUCTION
ELEKTRON BERKAT Sdn. Bhd. Will conduct the works disassembly and for Installation, Testing
and Commissioning Of 33kv Earthing Transformer at PMU Pulau Indah.
2. SCOPE OF METHOD STATEMENT
The scope of method statement (under TNB Grid) covers for disassembly of 33kV Earthing
Transformer Installation Testing and Commissioning.
3. WORK PROCEDURE
3.1.
Preliminary Work
3.1.1.
a.
Standard Operation Procedure (SOP) for Covid-19
World Health Organization states that the Covid-19 virus affects different people in
different ways. The WHO states that the common symptoms include:
i. Fever
ii. Tiredness
iii. Dry cough
Other symptoms can include:
i. Shortness of breath
ii. Aches and pains
iii. Sore throat
iv. And, in a few cases, people may report diarrhea, nausea or a runny
nose
It is believed that up to 30% of those infected do not show any symptoms and so
cleanliness and social distancing must be maintained.
1
`
Reference: National Security Council (NSC), Ministry of Health (MOH) (Covid 19:
Management Guidelines for workplaces), CIDB (Guidelines of Covid 19
Prevention Practices at Construction Site), Occupational Safety & Health Act 1994.
b.
The following advice is derived from general advice provided by the WHO. Basic
protective measures against COVID-19 as below:
i.
Frequent hand washing by crew using soap and warm water or alcoholbased (at least 65-70%) hand rub for 20 seconds.
ii.
Advised to use liquid-based soap Avoidance of touching the face including
mouth, nose, and eyes with unwashed hands (in case hands have touched
surfaces contaminated with the virus).
iii.
Workers should be encouraged to cover their nose and mouth with a
disposable tissue when sneezing, coughing, wiping, and blowing the
nose, then dispose of the used tissue immediately.
iv.
If a tissue is not available, one should cover their nose and mouth and
cough or sneeze into a bent elbow.
v.
All used tissues should be disposed of promptly into a waste bin
vi.
Workers should aim to maintain social distancing and keep at least one
meter distance from other people, particularly those that cough or sneeze
or may have a fever. If they are too close, other crew members can
potentially breathe in the virus.
vii.
Meat, milk, or animal products should always be handled with care, to
avoid cross contamination with uncooked foods, consistent with good food
safety practices. The consumption of raw or undercooked animal products
is to be avoided.
viii.
c.
A medical log should be maintained.
Personal Protective Equipment
i.
The routine uses of PPE including surgical masks, gloves and face
shields is only recommended for those near infected persons. Social
distancing measures should prevent the need to wear surgical mask during
site work and as well while travelling to and from towork site. The use of
KF94 respirator mask or surgical mask and gloves isrequired to reduce
encountering infected person
ii.
The WHO advice the following on the use of face masks:
2
`

If you are healthy, you only need to wear a mask if you are taking care of
a person with suspected Covid-19 infection.

Wear a mask if you are coughing or sneezing.

Masks are effective only when used in combination with frequent handcleaning with alcohol-based hand rub or soap and water.

If you wear a mask, then you must know how to use it and dispose of it
properly.

Make sure there are no gaps between face and the mask.

Avoid touching the mask while using it; if you do, clean your hands with
alcohol-based hand rub or soap and water.

To remove the mask: remove it from behind (do not touch the front of
mask); discard immediately in a closed bin; clean hands with alcoholbased hand rub or soap and water.
d.
Responsibilities
i.
Project Manager

Ensure that resources are sufficient to conduct the function safely and that
the study is carried out in compliance with the NSC, MOH Covid-19
Guideline, CIDB & DOSH. Responsible for the overall site compliance of
the Covid 19.
ii.
Project Engineer / Site Supervisor / Safety & Health Officer / Site Safety
Supervisor

Ensure the employees are tested for Covid-19 before commence work at
site.

Ensure the list of approved employees is prepared and send to the nearest
police station for travel authorization. Staff and workers not on the name
list are not permitted to access the project site.

Ensure all workers registered via My Sejahtera before entering the
premises.

Do not allow any other staff or personnel to access the project site without
the permission of MITI.

Staff and workers to take temperatures daily and check for respiratory
symptoms. Temperature more than 37.5oC not permitted to work. Provide
TNB Standard Form as per Appendix 1 and record workerstemperature
reading on daily basis.
3
`

Safety signage on COVID-19 & regular reminders in tool box talk are
encouraged as part of awareness in daily operation & works on site to all
parties.

Social distancing to be always maintained (1 meter).

Provide briefing and training for control measures of Covid -19 outbreak
to all the employees and sub-contractors, suppliers, and vendors.

Site Personnel and workers should be briefed and informed on the risk of
exposing to COVID-19, including proper hygiene methods to ensure safety
of all at project site.

Ensure the transportation vehicle (interior) is sanitized before and after
sending the workers to project site and home.

Consider obtaining travel declaration from employees and workers on
travel history.

Ensure the compliance of PPE Usage such as face mask (3-ply/reusable)
and hand gloves at all time. (Mandatory requirements). The reusable face
mask shall be cleaned often.

Ensure the staff and workers are sanitized their hands regularly. Suggest
for frequent hand wash as well using liquid soap prepared at the site office
toilet.

Provide suitable and sufficient rubbish bins for hand towels, face mask and
gloves with regular removal and disposal.

Do not allow any staff to come to work with Covid -19 symptoms such as
flu, cough, difficulties in breathing, sore throat and fever.

Break times should be staggered to reduce congestion and contact at all
times.

Control and monitor number of workers before enter, during works and
leaving the site. Screening procedure via thermal sensor daily shall be
applied to staff and workers before enter the site.
iii.
Sub-Contractor/Workers

Worker Leader should ensure social distancing is applied during
transportation to and from site.

Worker Leader should ensure all workers is fit to works before enter site
and to pass through screening process daily (thermal sensor by Main
4
`
contractor personnel). Those reading 37.5oC & above not allowed to enter
site.

Register via My Sejahtera before entering TNB Premises.

Attend briefing on the Covid-19 control measures before commence work
at site.

Carry out regular housekeeping at the workplace and ensure social
distancing 1.5-2 meters to be maintained at all time.

Fill up the TNB Standard Form as per Appendix 1 in daily basis.

Re-usable face mask should be thoroughly cleaned after use and not shared
between other workers.

The reusable face mask should be properly washed after use and not shared
with another worker.

The disposable face mask will be disposed of on a regular basis and no
longer using the disposable face mask for more than 1 day. Dispose it the
designated rubbish bin provided at site.

Regularly clean & sanitize the inside of vehicles cabs and between uses by
different operators (Mobile crane, Sky lift, Lorry, Excavator, Back-hoe,
Compactor & etc).

Direct visiting truck drivers to remain in vehicles and use contact-less
methods such as mobile phones to communicate with your workers
wherever possible.

Do not share tools and equipment with other workers. Ensure all the
workers have their own tools to carry out the job.

Rubbish collection and storage points should be increased and emptied
regularly throughout and at the end of each day.

Remind colleagues to report if they observe another work colleague is
displaying any unhealthy/potential symptoms relating to COVID 19.

Prohibit any colleagues who have showed symptoms or contracted with
COVID-19 to return to work place until they have medical evidence, they
are clear from the virus.

The workers should be asked to bring pre-prepared meals and refillable
drinking bottles from home. Workers not allowed go out from the project
site during the break time. Sub-con can provide packed food to the
respective workers if needed.
5
`

Report to SHO/SSS if any of the staff and workers are having any
unhealthy/potential symptoms relating to Covid-19.

3.1.2.
a.
Adhered to the PPE compliance at all time.
PTW Application and Safety Measures
This method statement must be presented to TNB Grid and approved by relevant
approval authority prior PTW issuance.
b.
ECE shall properly verify and inspect that the site / work area is safe to carry out
installation work before any work commencement. Among things to verify are yard
condition, trenching, identifying live parts, obstacles, and others.
c.
ECE shall ensure sufficient and suitable road access for machinery to move into and
work within the work area.
d.
AP TNB Grid and ECE will carry out barricade. Barricade of plastic red chain
(indicate Live Parts) and plastic yellow chain (indicate work area) will be used. The
barricade and signage shall not be removed until work completion and only with
authorization of the AP TNB Grid and ECE.
e.
Site Safety Supervisor to ensure all workers are equipped with proper PPE. For this
cable laying work, minimum PPE as below shall be adhered:
i.
Safety helmet
ii.
Safety boot with Steel Toe
iii.
Reflective vest jacket
iv.
Glove
6
f.
AP TNB Grid, ECE, then will carry out assessment of the assembly area during emergency
period.
Figure 1: Working and Assembly Area Outside PMU Pulau Indah
g.
AP TNB Grid then will issue the PTW to the ECE certified by EC and CP TNB GD at site.
Appendix 2 shows the ECE Certificate for this project.
h.
Safety tool box talk lead by ECE and AP TNB Grid to all workers will be carried out.
Appendix 4 show the list of Workers that will involve for this project. The contain of tool
box talk to all workers will cover:
i.
ii.
Scope of Work
Hazard and Control Measures
iii.
Boundary Work Area as Figure 1
iv.
Assembly Area during Emergency Period as Figure 1
v.
vi.
Usage of PPE
Adhere of SOP Covid-19 as Section 3.1.1
3.2. Site Setting Up Work
3.2.1.
a.
List of Machine and Vehicle
Table 1 below shows the list of machineries and vehicles that will be used during theproject:
7
`
LIST OF MACHINERY & TOOLS
No
Machine/Equipment
Quantity
1
Hand Tools
2
2
Complete Spanner Set, Cutring Pliers, Tube Cutters,
Screwdriver Set Hammer Hack Saw
Adjustable Wrench
2
4
Plastic wrap (to wrap cable ends)
1
5
Traffic Cone
10
6
Crowbar
2
7
Torque Wrench
1
8
`
No
Machine/Equipment
Quantity
7
Crimping Tool
1
8
Drilling Machine
1
9
4 x 4 Pick Up
1
10
Testing Equipment for Cable & ETx
11
Lorry Crane 20T
1
12
Water Jet
1
Table 1: List of Machineries and Vehicles
9
LOT
3.2.2.
Vehicle and Equipment Position and Access Route
The location of equipment that will be used during jointing cable work will be at
placed inside the PMU Pulau Indah. The access route and location of vehicle are also
placed inside the PMU Pulau Indah.
Figure 2 below shows the access route and working area
Figure 2: Access route
1
0
3.3 Disassemble Earthing Transformer
3.3.1 Remove all CT wiring, control wiring, AC and DC supply cables. Remove from conduit
and secure them so that no water enters the cables. Place cable securely in the cable trench.
Label all cables that are removed. Ensure all ferule numbers are secured and taped.
3.3.2 End Cap shall be fixed at Power Cable ends.
3.3.3 Do not Remove bushing complete with current Transformer and place in wooden crate and
secure for storage.
3.3.4 Drill 30mm diameter holes, 300mm deep x 6 locations on the pad after removal of
transformer.
3.3.5 Remove diverter switch and place in wooden crate and secure for storage.
3.4 Preparation of transportation:
3.4.1 Using crane of appropriate size (20 Ton), lift the transformer tank from the pad.
3.4.2 Crane and low bed truck to be supplied by others.
3.4.3 Transport Earthing Transformer to EWT Factory. On the Lorry Crane the Transformer shall be
tied with an appropriate belt.
3.4.4 To provide material listing of what needs to be removed. And to sign the checklist/ official
letter.
3.4.5 Ensure the 33kV cables, Aux transformer and NER is not damaged during this exercise.
3.4 Lifting
a.
Before lifting work is commencing, several activities as below need to done:
i.
Inspect the materials that shall be used to lift load. Any defective materials
shall not be used and shall be replaced.
ii.
Ensure that rope or chain is secured to the designated lifting hook.
iii.
Ensure that the both end of the rope / chain are properly secured.
iv.
Ensure that the are below the load lifting is cleared.
v.
Ensure that no hands or foot are placed underneath the load while placing
the load on its location.
vi.
Ensure that sufficient work area is available for the lifting.
vii.
Ensure that the load swing radius is minimized while lifting using
viii.
guide rope attached to the load.
ix.
Ensure that the lifting process is carried as smooth as possible
3.3. Housekeeping
a.
Once the above works as stated completed, the working personals have to ensure
that there are no materials leftover in the switchyard area and at the respective cable
ends.
b.
During Transformer being serviced and repaired at EWT, the oil spill on the
11
chipping stone will be either washed and gathered at one area and packed with a
proper packaging.
The works we shall conduct a proper checklist and later hand over to Grid
Maintenance for disposal.
12
`
13
LORRY CRANE POSITION
WORKING AREA
`
3.4. Transformer Installation Works
1. Upon Transformer delivered to site Pulau Indah, We will coduct a visual Inspection to ensure
Earthing Tx is in good order.
2. It is ensured that the access is clear to shift the transformer.
3. Move the transformer manually to the transformer location.
4. For manual handling, rollers are used to facilitate forward motion to find the erection place.
5. After the transformer positioning, all wheels will be locked to arrest any movement of the
transformer by providing the necessary stopper. And skid based.
6. All the incoming and outgoing cable supports, cable ends and termination fittings required
for MV, LV, and control cables will be tested prior to installation.
7. For the Multicore cable connected to the Transformer accessories a connectivity test and
functional test will be carried out.
8. Inspection request for transformer installation prior to the start of any cable termination work
will be done.
9. The transformer skids shall have rounded off beam ends and shall be provided with pulling
lugs/holes to enable site movements.
10. All the holes for fixings bolts and provisions for passage of cables etc. are provided as
required. The alignment of the Earthing Transformer wil be conducted during offloading on
the Transformer Plinth.
11. The installation of cables, wires, raceways, supports, cable ends, and termination fittings will
be done in accordance with the appropriate sections of the project specification and/or as
shown on the approved shop drawings. All the electrical connectors and terminals will be
tightened according to the manufacturer’s published torque-tightening values. The torque
force is as per name plate.
3.4.1 Testing of Earthing Transformer
1.
2.
3.
4.
5.
6.
Winding Power Factor (TNB to Test)
Oil Power Factor (TNB to Test)
Impedance Voltage Test
Winding Resistance Test
Polarization Test
Oil Break Down Voltage
(To Compare with OEM Factory Routine Test Report)
3.4.2 Cable Test
1. Meggar Test
14
`
4. SITE PICTURE
15
SITE LAYOUT
WORKING AREA
LORRY AREA
16
4.0 Emergency Response Plan
This procedure defined the following requirements: Method to carry out to eliminate or minimize the impacts and risks from the emergency events on the environment, employees, the
public and surrounding e.g. neighbor.
Method to respond promptly to changes during emergency that may be associated with them.
4.2
REFERENCE (S)
ISO 14001: 2015
ISO 45001: 2018
HSE-102-01
SPM-HSE-01
4.3
4.4
DEFINITION (S)
NO
TERMS
DESCRIPTIONS
1.
ISR
IMS System Representative
2.
ERT Group
Emergency Response Team Group
3.
Spill
Any accidental release of a liquid with hazardous effect.
4.
Minor Spill
Spillage in small amount or area, which is localized and easilycontained.
5.
Major Spill
Spillage is large and may flow out of factory and cause injury ordamage to the properties and
environment or
6.
Normal Working Day
Working day that include administration staff and production staff.
7.
Off Day
Working day for Production Staff only.
17
RESPONSIBILITIES AND AUTHORITIES
NO
4.5
Clause 8.2 Emergency Preparedness and Response Clause 8.2 Emergency
Preparedness and Response Nonconformity and Corrective Action.
Clause 8.9 Emergency Preparedness and Response
PERSON-IN CHARGE
1.
Project Manager
2.
ISR
3
ERT Group
RESPONSIBILITY AND AUTHORITY
 Approved any relevant information that to be communicated tothe external
parties
 Implementation and maintenance of the procedures Review with ERT and HSE
Safety Committee after any incidents or accidents
 To be the first team to control in case of any emergency situationoccurred
RECORDS
All records identified within the procedure shall be maintained according to the retention tspecified.
4.6 PROCEDURES
4.6.1 General
a) The potential emergencies are divided into few categories.
i) By activity, product or services on routine, non-routine and emergencies
- Fire, explosion, spillage, injuries or accidental discharges of gases or released to air, water and land
ii) By locations or locality
- Bomb-threat, floods etc.
iii) By others
- Severe Acute Respiratory Disease, hysteria, mental disorder
b) ERT Members, Top management, Security personnel, Safety and Health Officer, Administration Manager,
HSE Safety Committee and Receptionist shall be responsible to deal with Emergency Response.
c)
The applicable equipment shall be located at the potential emergencies are occurred e.g.
i) Emergency Kit e.g. Spill clean-up kit is stationed at the potential spillage areas.
ii) Eye wash and shower is provided at various locations for any chemical splash.
iii) Personnel protective equipment (PPE) is stationed in strategic location.
iv) Firefighting equipment are available at all strategic locations.
d) The emergency response plan shall be established and updated if significant changes to Layout,process
etc.
e) Fire or emergency evacuation drill shall be carried out at least once per year and record shall be
recorded in Drill Report (DR) by ERT group.
f) Fire drills training shall be carried out together or separately from evacuation drills training and chemical
handling training. All drills shall be recorded and reviewed for effectiveness of the procedure, Function of
equipment, mobility of ERT members and response taken.
g) The emergency plan is considered normal working day, off day and public holiday.
h) The maintenance of firefighting equipment shall be carried out by Human resource and
Administration department and the relevant records are kept accordingly.
18
4.7 Competencies of ERT Members
4.7.1 The general competencies of ERT members are described below; NO
1.
Education
2.
Experience
3.
4.
4.8
COMPETENCY
Training/Skills
Personality
DESCRIPTIONS
Minimum Secondary Level
Minimum one-year work experience in service or manufacturingenvironment.
Fundamentals and detail of ERT training; a) First aid and CPR training
b) Hazardous waste operations and emergency response
c) Spillage clean-up.
d) Handling of the emergencies, hazard classification, SDSunderstanding,
hazard
identification
and
assessment,
monitoring equipment, first aid, Fire control,
Physically fit, no health problem
Communication
4.8.1
During emergency event shall be done through telephone and PA system, hailers, and fire alarms.Public
Address System shall be maintained for emergency.
4.9 Evacuation plan or layout
4.9.1Evacuation plan or layout shall be located at all strategic place and updated if any changes occurred that
affected the escape route entry. The layout plan shall be reviewed by theERT Team when there
is any layout change.
4.9.2 During emergency, all employees shall assemble at designated Assembly Area as identify in the
Emergency Plan.
4.9.3 Emergency Handling Flowchart shall be as Attachment A.
19
4.9.4 The Emergency response plan for fire or spillage shall follow accordingly to flowchart in
Attachment A.
4.9.5 The Safety Officer and Fire Squad Leader with the BOMBA shall coordinate the Fire Investigation.
4.9.6 All accident, incidents and near misses shall be investigated by SHO and HSE Safety Committee and responsible
department’s personnel as shown in the HSE-102-01 Non-Conformance Corrective Action.
4.9.7 The ERT member shall be trained on handling of the following matters; 4.9.7.1 First aid and CPR
4.9.7.2 Fire and Spilled Control
4.9.7.3 Use of all emergency equipment such as fire extinguisher
PPE,
4.10 Emergency Spills of Chemical and Waste Chemical
4.10.1
The purpose is to ensure members are equipped to control any liquid spillages in a controlled andsafe
manner.
4.10.2
HOD shall maintain the emergency spill kits. Checking must be made to ensure all equipment ispresent
and in a satisfactory condition.
4.10.3
The equipment may set out around the site and contains Rubber Gloves, Protective Glasses, Shovels, Sand
Bags, and Emergency Contact List.
4.10.4
All concerned member who handles the chemical shall be trained to contain liquid spills. The members shall
be authorized and will be instructed on how to contain and clear up all chemical spills in a safe and organized
manner. Only members who are authorized should attempt to contain any spills.
4.10.5
Emergency System - Trained Member, please ensure your own safety. If there is doubt over the identity of
the chemicals, or known high risk in the containment of the chemicals, contact the ‘Emergency Services’ or
MR or Safety Officer immediately. Block off all drains and ensure chemicaldoes not enter drainage system.
Identify the chemical or chemicals to establish the necessary containment method. Using the equipment
provided and ensures the chemicals is trapped in the smallest possible area allowing capacity for further spillage
and if possible, stop or reduce the rate of leak.
4.10.6
For other Emergency System-Untrained Member, please ensure your own safety and evacuate theimmediate
vicinity. Contact the Security and recognized member.
4.10.7
When the spill has been contained, the responsible manager shall issue official notification and thepillage
must then be cleaned up and residue disposed of in accordance with the recommendations given on the CSDS
and identify as a Schedule waste according to Schedule Waste, Regulation, 2005.
4.10.8
Spillage Recording: Records of all spills will be completed as HSE-102-01 Non-conformance and
Corrective Action.
4.11 Other Types of Emergencies
4.11.1 Other type of emergencies except fire, spillage and explosion, the ERT are still responsible to managed and
control the emergencies situation.
4.11.2 In case of electrical failure, the respective department will responsible to handle the situation.
4.12
Incident Review
4.12.1
4.12.1.1
4.12.1.2
4.12.1.3
4.12.1.4
4.12.1.5
4.12.1.6
4.12.1.7
4.12.1.8
20
All emergency response actions shall be reviewed and the results provided
to the HSE
Safety Committee. If necessary, to raise incident report as specified and the following
items to be included in the review should include at a minimum:
Description of incident, including events leading up to the emergency situation
Employees response
Root causes
Potential system or procedural failures
Corrective actions
Required changes in policies, procedures or instructions
Lessons learnt from external incidents
Follow-up training or communications.
1) Flow Chart of Break Out of Fire During Working Hour
FLOW CHART
FLOW DESCRIPTION
1. Nearest person to react by using Fire
Extinguisher.
1. If uncontrolled - Break glass.
1. Employee determine the
fire location from thefire
indicator panel.
1.1 Call Fire Brigade (Bomba).
2. Designated Admin. Officer
announce the incidentand
follow by evacuation.
1. Department Heads/
supervisors standby and
evacuate after the
announcement.
2. Department Heads/21
ERT Leader
instructmaintenance
to cut off
electricity.
1. Security/ ERT Leader guide Bomba to the
location.
2. ERT Team hand over the
situation to Bomba and
evacuate.
1. Department Heads/ supervisors
take his departmentattendance.
2. Any missing person
must be reported to Fire
Department (Bomba).
2) Flow Chart of Break Out of Fire After Working Hour
FLOW CHART
FLOW DESCRIPTION
1. Nearest person to react by using Fire
Extinguisher.
1. If uncontrolled - Breakglass.
1. ERT shall determine the
fire location from thefire
indicator panel.
2. Call Fire Department (Bomba).
3. Security call Human Resource
Department Head andERT
Leader
22
1. Duty Supervisor standby and
evacuate after thealarm bell.
1. HSE Officer guide Bomba to
the affectedlocation.
.
1. Duty Supervisors take his department
attendance.
2. Any missing person
must be reported to Fire
Department (Bomba).
3) Flow Chart of Hysteria Procedure
FLOW CHART
FLOW DESCRIPTION
1. Nearest control staff informs
Department Heads/
Supervisors.
2. Department Heads/ Supervisors isolate
the victim.
3. Department Heads/
Supervisors inform
HRDHead, ERT Leader
and First-Aider.
1. First-Aider submit
report to HSE
Department Head.
23
1. HSE Department
Head explain to
General Manager.
4)
Flow Chart of Severe Injuries Procedure
FLOW CHART
FLOW DESCRIPTION
1. Nearest person to accident
inform Department
Supervisors or Department
Heads
2. Department Supervisors/
Department Heads inform
Human Resource Department
Head, ERT Leader and FirstAider.
1. Human Resource Department Head
immediately callpolice, ambulance
and the victim family.
24
1. The Department Head
concern shall submit an
accident report to Human
Resource Department.
2. ERT, Human Resource
Department Head and
Department Heads compile an
Accident Correctiveand
Preventive Action Report.
1. Human Resource Department
Head reports toGeneral
Manager.
5) Flow Chart of Chemical/ Diesel Spillage Procedure
FLOW CHART
FLOW DESCRIPTION
1. The Department Technician/
Department Supervisorshall
inform to the ERT in case the
chemical/ diesel spillage is out
of control.
2. The ERT shall immediately
respond and assist to clean up the
chemical spillage using
absorbent cloth and wearing
personal protection equipment.
In case the chemical/ diesel spillage
flow into the perimeter drain,
immediate action shall be taken by
placing sand bag at the outlet drain.
1. The Department Technician/
Department Supervisor shall inform
his Department Head and
HSE Department Head.
25
1. After cleaning, the waste shall
be put in containerand stored
in scheduled waste storage
area.
1. Department Head submit
Accident Report toHSE
Department Head.
1. HSE Department
Head report to
General Manager.
1. ERT take control of the area
1.1 No traffic passing
`
1.2 No work are continued
1.3 First Aid - if have
5. HAZARD IDENTIFICATION, RISK ASSESSMENT AND DETERMINING
CONTROL (HIRADC)
26
`
27
`
28
`
29
`
30
`
31
`
32
`
33
`
34
`
24
`
25
`
26
`
6. JOB SAFETY ANALYSIS (JSA)
This section describes the safety aspect that required worker attention and explains the potential
risk and control measures for each activity as describe in the Section 3. Potential Risk for each step
of activities has been identified and control measures need to be taken before and while carrying
out the job.
6.1. JSA for Transformer
ACTIVITIES
POTENTIAL
CONTROL MEASURES
RISKS
Setting up of
Lorry Crane
Lorry Crane
topples down
 Toolbox briefing to conduct on daily
basis before start work.
 Ensure the lorry crane have valid
PMA and the operator have
competency from DOSH.
PERSON INCHARCE
 GCQP
 Site Engineer
 SSS
 Supervisor
(Subcon)
 Ensure the ground is firm and in
good condition.
 Provide steel plate if the ground is
soft.
 Timber padding to provide for the
outriggers.
 Wear safety helmet, safety shoes &
gloves.
Operation of
Falling from
 Cordon off work area and display
warning signage.
the lorry
crane.
height
 Ensure the workers are experienced
to perform the
 job.
 GCQP
 Site Engineer
 SSS
 Supervisor
(Subcon)
 Wear safety shoes, safety helmet,
safety harness full body harness &
gloves
27
`
ACTIVITIES
POTENTIAL
RISKS
Sharp edges
from structure
CONTROL MEASURES
PERSON INCHARCE
 Identify and avoid any sharp edges.
 GCQP
 Wear safety shoes, safety helmet,
 Site Engineer
safety harness full body harness &
 SSS
gloves.
 Supervisor
(Subcon)
Falling
 Cordon off work area and display
warning signage.
material
 Ensure there is no workers
underneath the work area.
 Ensure the working tools &
 GCQP
 Site Engineer
 SSS
 Supervisor
(Subcon)
equipment secured with
 lanyard attached to the pouch/bag
of the workers who’re climbing to
the structure.
 Wear safety shoes, safety helmet,
safety harness full body harness &
gloves.
Hot weather
(Dehydration)
 Drink small amounts of cool water
 GCQP
frequently to prevent dehydration.
 Site Engineer
Drink throughout the day to relieve
 SSS
thirst.
 Supervisor
 Ensure the worker are fit to work
(Subcon)
and if they’re not well do not let
them to work at height.
Rainy/Stormy
Weather
 Stop work immediately.
 GCQP
 Ensure the workers stays out from
 Site Engineer
switchyard and goes to dedicated
rest area.
28
 SSS
`
ACTIVITIES
POTENTIAL
RISKS
Manual
CONTROL MEASURES
 Do not carry excessive weight and
weight to be known prior to carry.
Handling
(Ergonomics)
PERSON INCHARCE
GCQP, Site
Engineer,
 Correct body posture while
carrying the load.
 Request for additional manpower if
the load is heavy.
 Wear safety shoes, safety helmet,
SSS &
Supervisor
(Subcon)
safety harness-full body harness &
gloves.
Struck by
 Ensure the workers are experienced
to perform the job.
object
 Wear safety shoes, safety helmet,
safety
Concrete Slab
Engineer,
 Ensure the working tools in good
condition.
Lifting the
GCQP, Site
 harness-full body harness &
SSS &
Supervisor
(Subcon)
gloves.
Electrocution
 Safety clearance to be obtained &
adhered at all time while working
GCQP, Site
Engineer,
in LIVE substation.
 Wear safety shoes, safety helmet,
safety harness full body harness &
gloves.
Sharp edges
 Identify and avoid any sharp edges.
 Wear safety shoes, safety helmet,
from structure
SSS &
Supervisor
(Subcon)
GCQP, Site
Engineer,
safety
SSS &
29
`
ACTIVITIES
POTENTIAL
CONTROL MEASURES
RISKS
 Wear safety shoes, safety helmet,
safety harness full body harness &
PERSON INCHARCE
Supervisor
(Subcon)
gloves.
Slips, trips & falls
 Clear obstruction
 Maintain good housekeeping
GCQP, Site
Engineer,
 Wear proper PPE
SSS &
Supervisor
(Subcon)
Cable damage
 To conduct safety briefing
 Check the live cable condition
GCQP, Site
Engineer,
before the installation.
 If the cable is found to be
defective, it shall not be installed
and arrangement made for it to be
SSS &
Supervisor
(Subcon)
returned to the supplier for
replacement.
Hot weather
 Drink small amounts of cool water
frequently to
(Dehydration)
GCQP, Site
Engineer,
 prevent dehydration. Drink
throughout the day to
 relieve thirst.

Ensure the worker are fit to work
and if they’re not well do not let
SSS &
Supervisor
(Subcon)
them to work at height.
Rainy/Stormy
 Stop work immediately.
GCQP, Site
Engineer,
Weather
30
6.2. JSA for working near live area
ACTIVITIES
PERSON IN-
POTENTIAL RISKS
CONTROL MEASURES
Arc / electric shock
radiation (Other
services including
TNB cables)
Cable marker / cable slab
Turn off the cable
Trial hole
GCQP, Site
Engineer, SSS
& Supervisor
(Subcon)

Create utility mapping
Cable marker / cable slab
Make a site visit with the
Utilities involved
Trial hole
GCQP, Site
Engineer, SSS
& Supervisor
(Subcon)

Wearing mask and goggle
GCQP, Site
Engineer, SSS
& Supervisor
(Subcon)


Wearing ear plug
Scheduled the work

Use the jack liner before
starting work
Check site conditions before
and after work
GCQP, Site
Engineer, SSS
& Supervisor
(Subcon)
GCQP, Site
Engineer, SSS
& Supervisor
(Subcon)
Live Cable /
Serious Injury,
Fatal
Digging other
services include gas
pipes,
telecommunications
lines, water or
sewage and other
utilities
Respiratory
disorders and eye
pain
Soil dust
Hearing
impairment





Noise pollution
Machinery is
upside down

Unstable position
of excavator
31
CHARCE
`
Fall in the gutter


Create area barriers
Install cones and safety
notice boards

Provision of cones, safety
signage and traffic control
Wearing PPE
Unsealed gutters
Collided with a
vehicle

Traffic is busy with
vehicles
Summoned by the
Department of
Environment
(DOE) / fell due to
slippery


GCQP, Site
Engineer, SSS
& Supervisor
(Subcon)
GCQP, Site
Engineer, SSS
& Supervisor
(Subcon)
Inspect the machinery before
starting work
Scheduled maintenance
GCQP, Site
Engineer, SSS
& Supervisor
(Subcon)
Do a site inspection before
starting work
Wearing PPE
GCQP, Site
Engineer, SSS
& Supervisor
(Subcon)
GCQP, Site
Engineer, SSS
& Supervisor
(Subcon)
Leaking engine /
hydraulic oil

Bitten by
venomous
animals/insects

Landslides and

injuries.

Unstable ground /
cliff conditions
Fainted

Install scaffolding/shoring
on ditches for a depth of
more than 1.5 meters
Ensure that the distance
between vehicles/building
materials/soil waste and
drains is not less than 1
meter
Rest / less exposure period /
change of employee
Scorching hot
weather
Table 5: JSA for working near live area
32
GCQP, Site
Engineer, SSS
& Supervisor
(Subcon)
`
6.3 JSA for Covid-19
ACTIVITIES
POTENTIAL RISKS
Carry out work
Interact with
workers who
have symptoms
of Covid-19 or
come in contact
with surfaces
contaminated
with the Covid19
activities at the
TNB project
site during and
after the PKP
implementation
period
CONTROL MEASURES
Regularly checks body
temperature and covid symptoms
for employees prior to entering
PERSON INCHARCE
GCQP, Site
Engineer, SSS &
Supervisor
(Subcon)
the project site
Often wash your hands with water
and soap/hand sanitizer before and
after work
Practicing social distancing of at
least 1 meter
Wears 3 ply surgical mask double
with a cloth mask / Wears 4 ply
surgical mask (KF94)
Table 6: JSA for Covid-19
33
GCQP, Site
Engineer, SSS &
Supervisor
(Subcon)
GCQP, Site
Engineer, SSS &
Supervisor
(Subcon)
GCQP, Site
Engineer, SSS &
Supervisor
(Subcon)
`
1. WORK PROGRAM
CABLE LAYING WORK FOR INSTALLATION OF 33KV AT PMU PULAU INDAH
Working Days
TASK
1
2
31 Days
PTW APPLICATION
SETTING ALL EQUIPMENT
MOBILIZE TEAM AND DISASSMBLE
EARTHING Tx
ARRANGE AND TAGGING ALL
CABLES
LOADING EARTHING TX ON LORRY
CRANE
OEM REPAIR EARTHING TX
HOUSEKEEPING OIL SPILL
UNLOAD EARTHING TX
INSTALLATION EARTHING TX
TESTING EARTHING TX
HOUSEKEEPING
Table 7: Work Program for Disassemble and
Installation of Earthing Transformer
34
32 33
34
`
1. APPENDIX 3: ECE C
35
36
`
APPENDIX 5: LIST OF WORKERS AND NTSP CARD VALIDITY.
Identity Card
No.
1.
Name
Muhammad Izzuddin Bin Hassanuddin
Number
990522-08-7533
NTSP Card
Number / Validity
TNB052285SP
CIDB Validity
Dose
1
Dose
2
Vacci
nation
Vacci
nation
Booster
Vaccination
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
1990522PR1800321865
VALIDITY:
11/02/2023
(Pending Renewal)
2.
Annuar Bin Mohamad
790412-01-6033
VALIDITY: 22/05/2023
TNB0083663N
W11221120110132
VALIDITY:
19/01//2025
Validity:12/04/2023
1000715PH2100270867
3.
Muhammad Irwan Ikhwal
000715-06-0655
TNB07880302-06
VALIDITY:
24/08/2024
4.
Zurulhafizie Bin Mhd Idrus
B21140420160051
951102-08-5871
TNB039550N
VALIDITY:
24/05/2025
5.
Mohd Firdaus Bin Mahadzer
Validity:
September/2026
980428-02-5927
TNB08015302-06
Validity:30/09/2024
37
Validity:
01/01/2023
(*To be renewed)
1980428KD2100296844
Validity:28/04/2023
38
`
NO.
KAD NTSP
KAD CIDB
1
39
`
2
40
`
3
41
`
4
42
`
5
43
`
Appendix: Calibration Certificate