Appendix H BE Form 07 DEPARTMENT OF EDUCATION BRIGADA ESKWELA SCHOOL ACCOMPLISHMENT REPORT (to be accomplished by the School Head) DIVISION: Bohol REGION: VII SCHOOL: Concepcion Elementary School SCHOOL ID: 118446 SCHOOL ADDRESS: Tangcasan Sur, Loay, Bohol Level: Type of School Elementary Central School High School Non-Central School / / Multigrade Primary Integrated School SCHOOL HEAD : PTCA PRESIDENT: CONTACT NUMBER: VERONICA G. JAPSON 09082069448 CONTACT NUMBER: VICTOR GASLANG 09489851363 A. SCOPE OF REPAIR AND MAINTENANCE WORK COMPLETED What was done? Repaired Repainted Replaced 1. Roofs 2. Ceilings 3. Walls 4. Windows and Doors 5. Chairs/Desk,Tables and / Others Plastered cleaned cleaned cleaned cleaned Blackboards 6. Comfort Rooms 7. Leaking Pipes/Water conection 8. School Grounds/Landscaping 9. School Signs 10. School MRF 11. School Stage 12. School LR 13. School Office 14. Literacy Chambers 15. Electricals 16. School Parks / / cleaned New connection cleaned / / / / / / cleaned cleaned finishing Cleaned/singnage cleaned New Construction New installation New Construction BE Form 07 DEPARTMENT OF EDUCATION B. DONATIONS/ MATERIALS RESOURCES GENERATED Type of Donations Sources (Please refer to the attached pages…) Estimated Cost P 1,262,570.00 Total P 1,262,570.00 BE Form 07 DEPARTMENT OF EDUCATION C. VOLUNTEER SERVICES Type of Volunteer Name of Individuals/ Organization 1. PTA Members/Parents 2. Brgy. Officials 3. Municipal Gov’t Officials/Employees 4. Provincial Gov’t Officials 5. NGO’s / Civic Organizations 6. Private Citizens 7. Private Companies/ Corp. 8. Other Gov’t Offices 9. Parents 9. Teachers 10. Pupils 11. Others: Alumni 12. Prominent Volunteers (Mun. Employees) TOTAL Number of Volunteers Day Day Day Day Day Day TOTAL 1 2 3 4 5 6 124 34 48 38 68 24 336 24 5 7 7 4 18 65 6 4 3 2 10 5 30 15 1 1 1 1 1 20 35 12 21 7 11 37 123 10 2 2 8 3 2 27 15 2 4 2 5 4 32 45 12 35 14 41 12 36 19 19 263 72 230 96 4 45 12 41 20 43 12 40 13 49 12 39 18 15 40 12 39 12 25 15 8 16 26 17 107 376 183 212 199 234 216 1,420 BE Form 07 DEPARTMENT OF EDUCATION D. ESTIMATED COST OF VOLUNTEER SERVICES RENDERED. Refer to Guide for computing Labor Cost Type of Services Total Number of Volunteers Masonry Carpentry Electrical/Electronic Landscaping/ Gardening Painting Ordinary Labor Welder/Plumber Others Total 160 159 12 205 240 230 17 181 1,420 D. SIGNIFICANT EVENTS/EXPERIENCES What happened? Who were involved? The parents, teachers and Brgy. Officials were eager to do voluntary works Parents, Teachers, Brgy. Officials, & other Volunteer Groups. Total Number of Hours Rendered 1104 1054 62 1396 1712 1540 136 1448 5,680 Total Estimated Cost P 82,800 P 79,050 P 4,650 P 52,350 P 128,400 P 57,750 P 10,200 P 54,300 P 213,000.00 When? What is/are important contribution to the operation of the school or to the existing needs of the school? August 1– 26, 2022 The school is much safer and ready for the opening of classes. E. ISSUES AND CONCERNS (Describe briefly problems encountered and how resolved) ISSUE: Limited time for project implementation. RESOLUTION: Utilized Brigada Plus. E. LESSONS LEARNED / BEST PRACTICES Spirit of voluntarism, cooperation, harmonious relationship of school personnel and stakeholders are very important for the realization of the Brigada Program towards the achievements of goal and mission of the school. Despite of limited time and resources, with the collaboration of internal and external stakeholders, the planned school works and projects were successfully realized. BE Form 07 DEPARTMENT OF EDUCATION F. SUGGESTIONS TO STRENGTHEN BRIGADA ESKWELA PROJECT (Include support needed from Central, Region, and Division Office that can increase the impact of Brigada Eskwela Project in your School.) G. EVIDENCES / ATTACHMENTS a. Photos (before, during, after) b. Photocopy of all completed BE Forms (check if attached) ____ __ Form 01 ____ ___ Form 05 ____ __ Form 02 ____ ___ Form 06 ____ __ Form 03 ____ __ Form 04 Prepared by: Name and Designation: Date: MARIO B. SOLANA Brigada Eskwela Coordinator O8-27-2022 Submit copy of this completed form to ADOPT-A-SCHOOL PROGRAM DISTRICT COORDINATOR or District Supervisor on or before June 15.