INSPECTION REPORT Inspection Report Number Project code I. General Client: Supplier: Sub-Supplier: P.O. Number: Sub-Supplier P.O. Number: 258592-140323-1 406449 Rev: 0 M/s. Tata Projects Ltd. M/s. Skipper Ltd. NA 4500325361 NA Project: Location Location Rev. Nil Rev. NA II. Visit Details: NOI/E-mail Ref.: SL/PDI/22-23/310 Inspection Location: Uluberia, Howrah, West Bengal Contact Details Supplier Name Mr. Jameson Robinson Phone Sub Supplier Name NA Phone Visit Date(s) 14.03.2023 Inspection Stage Stage Final Pre Dispatch P.O. Order Status Completed Partially Completed III. a). Inspected Items (Annexure may be prepared, if required) Sr. No. / Description P.O. Qty. Offered PO Item Qty. No. / BBU No. 1800 Steel Monopole Date: 14.03.2023 400 kV Khargar – Vikhroli TL (200248) Uluberia, Howrah, West Bengal NA Date 22.10.2020 Date NA Date: 13.03.2023 +91 7605058063 NA Inspection Accepted Rejected Sample Qty. Qty. Qty. Hold Qty. 40.650 MT 18 mm x 2000 mm x 11930 Plate as per ASTM A572 Grade 65 Type 2 (Heat no. A263018) 13.45 MT 13.45 MT Nil Nil 13.45 MT 22 mm X 2000 mm x 12000 mm 12.43 MT 12.43 MT Plate as per IS 2062 E450 BR (Heat no. B09611) b). Offered condition: Plates were offered in as rolled and as rolled condition. Nil Nil 12.43 MT IV. Summary of Inspection Activities Performed: a) Reference Documents Document No. Rev. Title Approval Status Document Supplied by SL/PDI/22-23/310 Nil Inspection Call M/s. TPL M/s. TPL SKP/MQP/UTM/TPL/001 02 SQP M/s. ATL M/s. TPL 3870-E-ETL-MPT-DC-C-V-007 R1 GAD M/s. ATL M/s. TPL Concerned Authorities Self IS 2062, ASTM A572 Latest Relevant Standards b) Previous report reference, if any: 249458-170123-1, 250299-270123-1 Page 1 of 3 Format No: 15.03.01/F-01/R5 Date: 08-05-2021 INSPECTION REPORT c) Inspection, Measuring and Test Equipment: Sr. No. Description ID No. Make Type Range 01 Vernier Caliper 0031365 Mitutoyo Digital 0-300 mm 14.07.2023 Yes 02 Steel Tape SL/MT/HM3-14 Freemans Analogue 0-5000 mm 12.07.2023 Yes SL/MT/HM3-02 Freemans Analogue 0-5000 mm 12.07.2023 Yes 03 Steel Tape Calibration Traceability Validity to NABL/NPL a). Accuracy of measurements ensured - Yes b). Test witnessed at NABL Approved Laboratory - Yes No NA If Yes, Verify and note the NABL certificate number and its validity. If No, Verify the facilities as per check list: TQS-IS-CL-02** **This is applicable for tests witnessed at unapproved Laboratories/manufacturing facility. (Tick applicable clause) d) ITP/QAP/MQP – Activities: (H- Hold, W- Witness, R- Review, S- Surveillance) ITP/QAP Clause 1.1 Inspection activity as per QAP/ITP H/W/R/S Raw Material Inspection – Physical & Chemical H Quantum of Check 1/Cast or Heat e) Inspection Activity Narrative Summation: 1. Visual Check: Checked for surface condition, stenciling (Heat no., plate no., grade, make, ISI mark, etc. and found in order. 2. Dimensional Check: Checked for thickness, width, length and found within tolerance limits. 3. Test Piece Identification: Test pieces were hard stamped thus: TPL/1694 as per IS 2062 and ASTM A572 as for chemical & mechanical tests at NABL accredited laboratory. 4. Review of Documents (QAP cl. nos. 1.1, 2.1, 2.2, 2.3): MTC and calibration certificates were reviewed and found in order. Note – All the Non-conformities to be recorded in Section g). f). Record Notes/Details of discussion with Client: NA g) Non-Conformance/Issues: NA Sr. No. Description of Component Description of Non-Conformance/Issues 1 h) Identification: Location of Stamping: Test pieces were hard punched Specimen Metal Stamp Sticker Marking TPL/1694 Specimen: Note: TPL Stamping is done for identification purpose only. V. Conclusion: Inspected items are kept under hold till satisfactory results of test pieces are obtained from NABL accredited laboratory. VI. Attachments: Page 2 of 3 Format No: 15.03.01/F-01/R5 Date: 08-05-2021 INSPECTION REPORT Sr. No. Descriptions No. of Pages 1 Offer List 01 2 MTC 02 3 Calibration Certificates 03 4 Photographs 01 VII. Safety Compliance: a). Safety PPE Used: Safety Shoe VIII. IRN Issued with this Report: Supplier / Sub Supplier Helmet Yes Goggles Ear Plugs Nose mask Hand Gloves No Tata Projects Ltd. Client / Client Representative Signature & date: 14.03.2023 Signature & date: 14.03.2023 Signature & date: Name: Ramesh Das Name: Sudipto Datta Name: Mobile: 8788089420 Mobile: 9121161133 Mobile: Liability: Client/vendor/supplier/manufacturer shall note that this inspection report is issued without prejudice to contractual obligations of the vendor/supplier/manufacturer and does not relieve him from the guarantee and obligations set forth in the purchase order and other contractual documents. It should also be noted that in all cases where the test certificate/inspection reports issued by the vendor/supplier/laboratory are reviewed by the surveyor for conformity to the requirements of the standard/specification, the responsibility for the accuracy and validity of the inspection/test results lies with the issuer of the said certificate/report. Page 3 of 3 Format No: 15.03.01/F-01/R5 Date: 08-05-2021