Resource Planning in PS using Noveco solutions Key Requirements Requirements • Plan Individual Resources across projects and workcenters in SAP PS directly • Estimate required hours of individual resources (e.g. Drafting, Electrical Engineer, Project Manager etc.) on Project Network Activities or WBS elements using Activity Type or generic cost elements • Determine person availability by reading personnel HR time schedule and allocations to other projects • Allocate available hours: 1) individual Person; or 2) Position with assigned persons; or 3) Work Center with all Positions and Persons included to a project Network Activity or WBS element Pre-requisites • • • • • • • SAP HR module is implemented HR Work Centers are created for every ”logistic” WC Persons assigned to HR Work Centers Personnel is assigned to Activity Type (info type 315) Personnel is assigned to Work schedule (info type 007) Cost Elements assigned to Noveco Resource Names SAP PS & Noveco has accurate cost and work planning / forecast: labour costs plan is done using quantity and rate cost and work to complete is distributed along WBS and NWA Resource Planning in SAP PS with Noveco Project System (PS) Human Resources (HR) Person No. 100933 Name Charles Brown Sender Cost Center NOV001 Activity Type 6010 6010 Cost Estimation Description Activity Type Qty (Hrs) Rate Value Elect. Engineer 6010 6010 200 H $120.0 $24,000.0 CAD drafting 7000 80 H $100.0 $8,000.0 Info Type 315 Cost Estimation Description Activity Type Qty (Hrs) Rate Value Designer 6020 100 H $120.0 $12,000.0 Proj. Manager 8000 90 H $100.0 $9,000.0 • PS : Estimate Costs using Activity Types • HR : Assign Activity Type to a Personnel record • FICO : Activity Types assigned to Cost Elements (1:1) • PS : Cost Elements assigned to CE Groups • Noveco : CE Groups assigned to Resource Names Activity Types: Cost Elements – Resource Names Value Categories Resource Name Cost Elements Activity Types Engineering & Design Designer Designer Structural Designer Senior Designer System Designer System Designer Engineer Civil Engineer Labour Structural Engineer Fitter Electrician Materials Cost planned on project is directly linked to a personnel: - From Cost Elements / Value Category / Resource Name in Project - To Activity Type / Cost Element / Resource Name assigned to Employee master record in HR Project Cost Forecast define Resource Requirement DEMAND for Resources: (PS / Noveco ) SUPPLY of Resources: (HR) Cost planned on project Network Activities using Activity Types define: - Quantity of Hours Required - Rate per Hour to calculate Cost To Complete - Resource Names (e.g. Engineer, Draftsmen etc.) are determined from Cost Element assigned to Activity Type - Activity Types are defined in HR master record for every employee Project Cost Forecast define Resource Requirement DEMAND for Resources: (PS / Noveco ) Noveco Resource Plan works equally with WBS elements and / or Network Activities SUPPLY of Resources: (HR) Resource Demand Distribution Distribute your resource demand along the project proposed Start - Finish dates Planning of Individual Resources Using Noveco Solutions.. Resource Plan by Project Required Hours by project item, resource name and period List of Projects List of Resources Available Hours by personnel, resource name and period Resource Planning Projects Generate Resource Demand PM Workbench Resource Demand: - Distribute required quantity of hours by project in Noveco Project Manager Workbench - Resource Demand is distributed by month on Project WBS or NWA by Resource Name (e.g. Engineer, Project Manager) - In the example above, the NWA 904606/0010 generates resource demand for for Engineer and Designer HR Personnel Generate Resource Supply Info Type 315 – Time Sheets Defaults Defines Resource Name Info Type 0007 – Planned Working Time Defines Available Hours from Persons Work Schedule Resource Demand vs Supply Resource Demand: Red colour means not allocated resource demand As you navigate along the project structure, the system is trying to find suitable individuals from the resource list to match project demand Resource Supply: Green colour means not allocated resource supply Resource Allocation You can allocate individual resources to project WBS or NWA by several userfriendly ways: 1. Select a person (or multiple persons), select project item and click on “Allocate” button 2. Drag a line from the ALV screen to a project item on the tree or on the project ALV screen 3. Drag a person (or multiple persons) from Resource Tree and drop to Project Tree or project ALV Resource Allocation If you don’t want to allocate each person individually, you can allocate a position (or entire Work Center) with all its resources to a project item by drag & drop Review current allocations to the project item Resource Allocation Look for persons current allocations to various projects Resource Allocation You can search for corresponding resource demand for a specific pool of resources Resource Allocation Shift Project Requirements if there are no resources available Planning Resources considering cost budget Resource Prices and Project Cost Plan Rates Labour Plan Cost Rate from WBS or NWA Employee Contractor Persons Price per hour from HR info type 315 Resource Prices and Project Cost Plan Rates Allocate person to project where Person Price > Project Plan Rate Resource Prices and Project Cost Plan Rates Allocate person to project where Person Price < Project Plan Rate Resource Prices and Project Cost Plan Rates Project item is fully allocated with required Resources Click here to change the Graph Resource Prices and Project Cost Plan Rates In this view you can see that the plan cost on the project item will be exceeded Resource Prices and Project Cost Plan Rates To view graph by each project item double click on it in the list Resource Prices and Project Cost Plan Rates To view graph by each project item double click on it in the list History Report: • Compare: Allocated Hours vs. Actual Hours • Resources Utilization: Available Hours vs Actual Hours Resource History Select persons from the list or Tree View Resource History report Resource History: Resource Planning Summary: • Resource Planning is performed directly in SAP PS using the most up-to-date information about project resource requirements • Available hours are read from the person’s SAP HR Work schedule taking into account normal hours, planned holidays, existing allocations. • Cost Plan on a project defines required resources (e.g. Engineer, Draftsman, Project Manager), which are related to persons default activity type defined in HR master record • Soft resource allocation to a project defines ”planned” allocation and can be shifted in time • Committed resource allocation cannot be shifted in time • Project WBS or NWA resource requirements can be shifted (if their requirements are not committed) to periods with available resources • Resources can be allocated as individual persons or as a group of resources (Position or even an entire Work Center can be allocated) • Resources from multiple Work Centers can be allocated to project items • A custom list of available resources can be created by each user • Friendly graphical user interface designed to simplify the resource allocation process About Noveco Solutions.. Noveco Noveco is a family of seamlessly integrated software components designed to simplify SAP standard Project System (PS) and enhance it with missing functionality such as cost and revenue estimating, project forecasting, variation management and reporting directly in SAP Noveco enables integrated financial management of your project lifecycle directly inside your SAP system Execution Estimating Planning Budgeting . . Forecasting Efficient Project Management . . Monitoring Reporting Analysis Settlement Noveco System Architecture SAP ECC or S4 HANA Human Resources (HR) Time Sheets (CATS) Finance (FI) and Controlling (CO) Materials Management and Procurement (MM/SRM) Project System (PS) + Sales Noveco Production and customer management (SD/CRM) Plant Maintenance, Customer Service (PM/CS) Planning (PP) Capacity and Resource Planning No middleware (BI, BO etc.) No interfaces No custom tables Always real-time Rich functionality Automatic forecasting Simple and intuitive interface Minimum training Quick implementation Project Management Lifecycle Run by Noveco Run by SAP or other software Project Initiation • • • • • Estimating: Costs and Revenues Project Structure & Planning Budget Approval Start/Finish Dates Scheduling Plan Cost Distribution • • • • Efficient Project Management Purchase Orders / Contracts Time Sheets Invoicing & Billing Variations Execution • Final Settlement • Project Close • • • • • Monitoring & Forecasting Project Close Out • Settlement • Result Analysis/Profit Take • Period Close KPIs Review Cost / Margin Forecast Resource Planning Progress Analysis Materials and Procurement forecast Period Closing Reporting • • • • Operational Dash Board Programs/Portfolio Analytical SAP Project System with Noveco SAP standard Project System (ECC or S/4) • • • • • • • • • • • • Create and maintain Project structure: WBS and Networks Plan Cost and Revenue • Schedule Dates • Assign Purchase Orders to Project Assign Maintenance and Production orders to Project Assign Sales Orders to Project Collect Actual Cost and Revenue Settle Costs Run Result Analysis Reporting Noveco Project System • • • • • • • Estimation: Revenue and Costs Create Cost and Revenue Plan from Estimate Distribute (time phase) Cost, Commitments and Revenue Forecast remaining costs to complete and calculate Estimate at completion Progress Analysis Project Risk Management PO Accruals Management Variation Management Resource Management Forecast History Reporting Integrated Project Management in SAP PS with Noveco ECC / S4 HANA PM PS FI/CO Variation Management Reporting PP MM HR Estimation Project Manager Workbench SD ● ● ● ● ● ● ● Cost & Revenue Estimating Project Manager Workbench Cost, Revenue Forecasting Progress Analysis Variation Management Resource Management Comprehensive Reporting How Quickly Noveco ePM can be Implemented • • • • • Technical installation takes approximately 30 minutes (AddOn installation) SAP PS and Noveco configuration takes 2 hours to complete You may review your value categories and cost element groups You will run Noveco in your SAP Test environment the same day you installed it Implementation in Production environment will be different in each individual case Our Customers For more information visit Noveco Systems on www.novecosystems.com