Project Manufacturing (Engineer To Order) in SAP managed by Noveco solutions Project Manufacturing – Engineer To Order Characteristics of Engineer To Order (ETO) • The final product is always unique. It contains standard components and assemblies purchased or manufactured in-house as well as customer specific assemblies. • There is a high degree of engineering for customer specific requirements. • Cost Estimation is done based on costs of standard assemblies, components, costs of engineering plus cost of manufacturing of a final product. • • The final design may not be completed before project starts. The final cost may be different from initial estimates due to design or engineering change or due to manufacturing mistakes. Made to Customer Order ETO Manufacturing of Standard Assemblies Purchased items or Made to Stock Project Manufacturing – Engineer To Order Key requirements for Financial Control • • Estimating must include: – cost of manufacturing of standard assemblies – cost of engineering & design and sub-contracted costs – cost of fabrication of customer specific requirements – risks and contingencies etc. ETO Cost Breakdown Manufacturing to Customer Order Project Monitoring and Forecasting: – create detailed project cost plan from the approved estimate – capture engineering costs as manufacturing project is in progress – roll up manufacturing costs to project WBS at any time during project execution – include engineering and design changes into project budget, forecast and revenue plan – update project forecast Cost To Complete and Estimated At Completions (EAC) – calculate project progress based on engineering and manufacturing progress Plant Stock Engieneering Purchased Servcies Purchased Components Manufacturing Standard Assemblies Project Lifecycle Management in SAP : Project Execution Estimation Reporting Planning Variations Cost Distribution Forecasting Execution ▾ ▾ ▾ • Project Structures • Procurement • Goods & Service Receipts • Time Sheets • Vendor Invoices • Customer Billing • Payments • Settlement Actual Costs & Revenues Open Purchase Orders Execution Cost Distribution Planning Forecasting ! Estimation ≈ Variations Reporting Scheduling • Estimates / Bidding Process • Project Planning • Dates Scheduling (Gantt Chart) • Cost Distribution (time phasing) • Financial Forecasts • Change and Risk Management • Progress • Reporting not in SAP : Project Planning, Forecasting, Variation Management, Reporting etc. ETO Project Lifecycle Tendering and Planning phase Estimating Costs and Revenues • Respond on customer Tenders • Create Estimates from existing templates • Flexible hierarchical structure • Price calculation on materials, BOMs, Product Costing, services, external and internal labour • Calculate additions on Risks, Contingencies Price Escalations • Add Profit Margin to calculate Sales Contract Value • Initiate procurement of long lead items Sales Contract • Create Sales Contract in SAP from approved Estimate Project Planning • Create Project structure • Generate Cost & Revenue planning from approved Estimate • Revenue Plan generated from Sales Contract • Project scheduling with Gantt Chart • Distribute Costs and Revenue along project time line • Simulate Project Cash Flow • Simulate availability of internal resources (e.g. engineers, project managers etc.) Project Execution Phase Resource & Capacity Planning • Simulate Availability of Resources and Capacities • Allocate resources to project WBS elements and / or network activities • Allocate project WBS elements and / or network activities to Work Centers Procurement Materials & Services. Timesheets • MRP (Material Requirements Planning) • Procurement of materials, equipment, services to Project • Time allocation using CATS • Project inventory • Vendor Invoices • Outgoing Payments (cash out) Project Forecasting • Calculate Costs to Complete (CTC) and Estimated at Completion (EAC) from Actual Costs and Purchasing Commitments • Adjust Forecast costs and work to complete • Redistribute plan revenue based on updated CTC and purchase commitments • Progress and Earned Value calculation • Forecast Project Cash Flow • Forecast history • Drill down reporting • Run Result Analysis (profit recognition) at month-end based on the most recent project forecasts Variations & Risk Management Customer Billing • Create, Estimate and Approve Project Variations • Milestone billing based on Sales Contract Billing Plan • Automatically update project Budget, Cost Forecast and Revenue plan from approved variations • Resource Related (Cost Plus) Billing • Assess project risks: Threats and Opportunities • Simulate Pessimistic, Optimistic scenario impact on project profitability • Variation history tracking • Incoming payments (Cash In) Reporting • Operation project reporting • Multi-project reporting with graphical KPIs • Estimate vs Project Costs analysis • Dash-board Analytics Project Lifecycle: steps in SAP system Tendering and Planning phase Estimating Costs and Revenues • Respond on customer Tenders Sales Contract • Create Sales Contract Project Planning • Create Project structure • Create Cost Plan • Revenue Plan generated from Sales Contract Project Execution Phase Resource & Capacity Planning Procurement Materials & Services. Timesheets • MRP (Material Requirements Planning) • Procurement of materials, equipment, services to Project • Time allocation using CATS Project Forecasting • Run Result Analysis (profit recognition) at month-end based on the most recent project forecasts Variations & Risk Management Customer Billing Reporting • Milestone billing based on Sales Contract Billing Plan • Plan vs Actual Reports • Resource Related (Cost Plus) Billing • Purchasing Commitment • Incoming payments (Cash In) • Actual Cost Line Items • Actual, Plan Contribution Margin • Project inventory • Vendor Invoices • Outgoing Payments (cash out) Project System Business Challenges Symptoms: • • You use SAP Project System as a cost collector All planning, forecasting and reporting is done outside of your SAP system As a result: • • • • • • High use of excel spreadsheets No information transparency No data consistency Lack of standardization and information accuracy High efforts during month end process No real time project reports available SAP Project System + Noveco ePM Estimation / Bid Management Project Structures Scheduling & Gantt Chart Procurement to Project Project Cost / Revenue Plan & Distribution Project Inventory & Labour Confirmation Customer Billing Vendor Invoicing Project Financial / Cost Accounting Cost Forecast (EAC / CTC) Project System ePM: Extended Project Management Variation & Risks Management Cash Flow Forecast Progress Analysis Settlement Reports on Actual Costs and Revenues Resource & Capacity Planning Graphical KPI & Full Project Reporting Noveco complements SAP PS with new functionality, making it more powerful and easy to use. ETO Project Lifecycle Tendering and Planning phase Estimating Costs and Revenues • Respond on customer Tenders • Create Estimates from existing templates • Flexible hierarchical structure • Price calculation on materials, BOMs, Product Costing, services, external and internal labour • Calculate additions on Risks, Contingencies Price Escalations • Add Profit Margin to calculate Sales Contract Value • Initiate procurement of long lead items Sales Contract • Create Sales Contract in SAP from approved Estimate Project Planning • Create Project structure • Generate Cost & Revenue planning from approved Estimate • Revenue Plan generated from Sales Contract • Project scheduling with Gantt Chart • Distribute Costs and Revenue along project time line • Simulate Project Cash Flow • Simulate availability of internal resources (e.g. engineers, project managers etc.) Project Execution Phase Resource & Capacity Planning • Simulate Availability of Resources and Capacities • Allocate resources to project WBS elements and / or network activities • Allocate project WBS elements and / or network activities to Work Centers Procurement Materials & Services. Timesheets • MRP (Material Requirements Planning) • Procurement of materials, equipment, services to Project • Time allocation using CATS • Project inventory • Vendor Invoices • Outgoing Payments (cash out) Project Forecasting • Calculate Costs to Complete (CTC) and Estimated at Completion (EAC) from Actual Costs and Purchasing Commitments • Adjust Forecast costs and work to complete • Redistribute plan revenue based on updated CTC and purchase commitments • Progress and Earned Value calculation • Forecast Project Cash Flow • Forecast history • Drill down reporting • Run Result Analysis (profit recognition) at month-end based on the most recent project forecasts Variations & Risk Management Customer Billing • Create, Estimate and Approve Project Variations • Milestone billing based on Sales Contract Billing Plan • Automatically update project Budget, Cost Forecast and Revenue plan from approved variations • Resource Related (Cost Plus) Billing • Assess project risks: Threats and Opportunities • Simulate Pessimistic, Optimistic scenario impact on project profitability • Variation history tracking • Incoming payments (Cash In) Reporting • Operation project reporting • Multi-project reporting with graphical KPIs • Estimate vs Project Costs analysis • Dash-board Analytics Project Lifecycle: steps in SAP system Tendering and Planning phase Estimating Costs and Revenues • Respond on customer Tenders • Create Estimates from existing templates Sales Contract • Create Sales Contract in SAP from approved Estimate • Flexible hierarchical structure • Price calculation on materials, BOMs, Product Costing, services, external and internal labour • Calculate additions on Risks, Contingencies Price Escalations • Add Profit Margin to calculate Sales Contract Value • Initiate procurement of long lead items * Managed by Noveco Project Planning • Create Project structure • Generate Cost & Revenue planning from approved Estimate • Revenue Plan generated from Sales Contract • Project scheduling with Gantt Chart • Distribute Costs and Revenue along project time line • Simulate Project Cash Flow • Simulate availability of internal resources (e.g. engineers, project managers etc.) Project Execution Phase Resource & Capacity Planning • Simulate Availability of Resources and Capacities • Allocate resources to project WBS elements and / or network activities • Allocate project WBS elements and / or network activities to Work Centers Procurement Materials & Services. Timesheets • MRP (Material Requirements Planning) • Procurement of materials, equipment, services to Project • Time allocation using CATS • Project inventory • Vendor Invoices • Outgoing Payments (cash out) Project Forecasting • Calculate Costs to Complete (CTC) and Estimated at Completion (EAC) from Actual Costs and Purchasing Commitments • Adjust Forecast costs and work to complete • Redistribute plan revenue based on updated CTC and purchase commitments • Progress and Earned Value calculation • Forecast Project Cash Flow • Forecast history • Drill down reporting • Run Result Analysis (profit recognition) at month-end based on the most recent project forecasts Variations & Risk Management Customer Billing • Create, Estimate and Approve Project Variations • Milestone billing based on Sales Contract Billing Plan • Automatically update project Budget, Cost Forecast and Revenue plan from approved variations • Resource Related (Cost Plus) Billing • Assess project risks: Threats and Opportunities • Simulate Pessimistic, Optimistic scenario impact on project profitability • Variation history tracking • Incoming payments (Cash In) Reporting • Operation project reporting • Multi-project reporting with graphical KPIs • Estimate vs Project Costs analysis • Dash-board Analytics Project Lifecycle in SAP directly Scheduling Estimation Planning Reporting ✓ Cost Distribution Variations Forecasting • • • • • • • • Procurement Goods and Service Receipts Time Sheets Vendor Invoices Customer Billing Payments Estimates / Bidding Process ➕ Project Planning ➕ Dates Schedule (Gantt Chart) ➕ Cost Distribution (time phasing) ➕ Resource Planning Execution PPM Settlement ➕ ➕ With Noveco you can move the project management lifecycle and reporting into your SAP environment, making it excel sheet free!! Project Structures in SAP : Entire Project Management Lifecycle BW / BO High Level Project Capacity Planning ➕ Financial Forecasts ➕ Change and Risk Management ➕ Cash Flow ➕ Progress, Earned Values ➕ History tracking ➕ Graphical Reporting Cloud Analytics Noveco software add-on to SAP PS Noveco is a family of seamlessly integrated software components designed to simplify SAP standard Project System (PS) and enhance it with missing functionality such as cost and revenue estimating, project cost and revenue forecasting, cash flow forecasting, variation management, risk analysis, resource planning, graphical reporting directly in SAP Noveco enables integrated financial management of your project lifecycle directly inside your SAP system Execution Estimating Planning Budgeting . . Forecasting Efficient Project Management . . Monitoring Reporting Analysis Settlement Project Lifecycle: steps in SAP system Tendering and Planning phase Estimating Costs and Revenues • Respond on customer Tenders • Create Estimates from existing templates Sales Contract • Create Sales Contract in SAP from approved Estimate • Flexible hierarchical structure • Price calculation on materials, BOMs, Product Costing, services, external and internal labour • Calculate additions on Risks, Contingencies Price Escalations • Add Profit Margin to calculate Sales Contract Value • Initiate procurement of long lead items * Managed by Noveco Project Planning • Create Project structure • Generate Cost & Revenue planning from approved Estimate • Revenue Plan generated from Sales Contract • Project scheduling with Gantt Chart • Distribute Costs and Revenue along project time line • Simulate Project Cash Flow • Simulate availability of internal resources (e.g. engineers, project managers etc.) Project Execution Phase Resource & Capacity Planning • Simulate Availability of Resources and Capacities • Allocate resources to project WBS elements and / or network activities • Allocate project WBS elements and / or network activities to Work Centers Procurement Materials & Services. Timesheets • MRP (Material Requirements Planning) • Procurement of materials, equipment, services to Project • Time allocation using CATS • Project inventory • Vendor Invoices • Outgoing Payments (cash out) Project Forecasting • Calculate Costs to Complete (CTC) and Estimated at Completion (EAC) from Actual Costs and Purchasing Commitments • Adjust Forecast costs and work to complete • Redistribute plan revenue based on updated CTC and purchase commitments • Progress and Earned Value calculation • Forecast Project Cash Flow • Forecast history • Drill down reporting • Run Result Analysis (profit recognition) at month-end based on the most recent project forecasts Variations & Risk Management Customer Billing • Create, Estimate and Approve Project Variations • Milestone billing based on Sales Contract Billing Plan • Automatically update project Budget, Cost Forecast and Revenue plan from approved variations • Resource Related (Cost Plus) Billing • Assess project risks: Threats and Opportunities • Simulate Pessimistic, Optimistic scenario impact on project profitability • Variation history tracking • Incoming payments (Cash In) Reporting • Operation project reporting • Multi-project reporting with graphical KPIs • Estimate vs Project Costs analysis • Dash-board Analytics Integrated Project Management in SAP * Project Portal / Reporting * Resource Planning Profit Take (Result Analysis) * Noveco Applications Advanced Analytics Portfolio Planning (PPM) Reporting Analysis Monitoring Forecasting Progress Tracking * Project Manager Workbench Planning Execution Variations * Estimate: Cost & Revenue Create Project * Schedule Dates Procurement, Time Sheets Invoicing, Billing * Project Variations Tender Preparation: Cost and Revenue Estimation Estimate Configurable BOM Quotation Sales Order Engineering & Design Cost Estimation: Standard BOM • Preliminary Engineering & Design • Make To Order using standard BOMs • Configurable BOMs • New Customer specific BOMs • Purchased Components & Equipment To Be Engineered BOM • Long Lead Procurement items • Stock Materials and Consumables Delivery & Installation • Internal Labour, Machine, Setup Time • Service, Sub-contract Noveco Estimating solution in SAP • Multi-Level Tree Hierarchy with work packages and sub-packages • Version and Status Control • BOMs are part of cost estimation • Fully integrated with Project Cost and Revenue Planning • Easy and Flexible User Interface Noveco Estimating solution in SAP Example of a Resource Package that will be further engineered (no BOM exists yet). Its cost roughly estimated and included in Tender price Noveco Estimating solution in SAP • Example of a BOM of standard component (may be configurable) • It is fully costed and included into the Estimate. • PP orders will consume exact same resources as were estimated here Integrated Project Management in SAP * Project Portal / Reporting * Resource Planning Profit Take (Result Analysis) * Noveco Applications Advanced Analytics Portfolio Planning (PPM) Reporting Analysis Monitoring Forecasting Progress Tracking * Project Manager Workbench Planning Execution Variations * Estimate: Cost & Revenue Create Project * Schedule Dates Procurement, Time Sheets Invoicing, Billing * Project Variations Typical Structure for Manufacturing (ETO) Projects Project Structures for Manufacturing projects Manufacturing Project (ETO) Engineering & Design Motor Kit Assembly Electrical Kit Assembly Fitting & Installation Final Assembly Create Project Structure Sales Order and Project Planning Sales Order / Contract Project ✓ Quotation Sales Order • Quotation accepted by customer • Create Sales Order or Contract • Terms and Conditions • Down payment plan Project Planning: • Revenue / Billing Plan • Revenue Plan comes from Sales Order • Cash Flow of Incoming Payments • Project Structure: WBS elements, Network Activities • Link to Project WBS automatically generates: ⁃ Revenue Plan ⁃ Cash Flow forecast • Project Schedule • Procurement Plan Generate Cost Plan on Project Noveco Estimate 1 Project 2 1. Create Estimate 3 4a 2. Create Project 3. Transfer to Project 4. Save Cost Plan a. via ECP 4b Cost Plan (Original Estimate) Easy Cost Planning b. directly Transfer Cost Estimate to Project “as engineered” “as built” Estimate Project Transfer Cost and Revenue plan to Project Benefits ✓ Estimate structure may be different from Project Structure ✓ Labour rates and materials prices are are up-to-date ✓ Project Structures are designed to according its tasks and phases and not to resemble cost structure ✓ Costing details are transferred to Project and will be consistent with actual costs collected on a project ✓ Compare Estimated Costs and Actual Costs or Cost Forecast at any moment during project execution Transfer Cost Estimate to Project • Transfer cost from the Estimate to Project by drag & drop • Transferred Costs and Revenue will be saved as project cost and revenue plan. • This way you can create project baseline. Integrated Project Management in SAP * Project Portal / Reporting * Resource Planning Profit Take (Result Analysis) * Noveco Applications Advanced Analytics Portfolio Planning (PPM) Reporting Analysis Monitoring Forecasting Progress Tracking * Project Manager Workbench Planning Execution Variations * Estimate: Cost & Revenue Create Project * Schedule Dates Procurement, Time Sheets Invoicing, Billing * Project Variations Project Scheduling with Noveco Fiori Gantt Chart Before: Project Scheduling Before project is scheduled Before: Project Scheduling Set Start or Finish Dates and click ‘Schedule’ • A full Scale Project scheduling functionality in SAP PS by Noveco • Gantt Chart with buildin scheduling, drag & drop function • Automatic cost distribution based on new dates • Complete and seamless integration with Project Dates and Cost Plan in PS After: Project Scheduling Dates are scheduled and costs are automatically distributed Project Scheduling • You can Drag & Drop WBS structure • It will move all subelements of that WBS to new dates Project Scheduling As a result only WBS subelements dates have changed Project Scheduling • You can Drag & Drop Network Header • It will move all network activities that are linked with relationships to new dates across different WBS elements Project Scheduling As a result all activities linked with relationships rescheduled with new dates Project Scheduling • You can change duration, start or finish dates of an activity by dragging its edges left or right • New dates will be determined for all dependent network activities Project Scheduling • New dates are recalculated for all dependent activities • New dates redetermined for corresponding network headers and WBS elements After: Project Scheduling After new dates are recalculated costs are re-distributed After: Project Scheduling Project Lifecycle: steps in SAP system Tendering and Planning phase Estimating Costs and Revenues • Respond on customer Tenders • Create Estimates from existing templates Sales Contract • Create Sales Contract in SAP from approved Estimate • Flexible hierarchical structure • Price calculation on materials, BOMs, Product Costing, services, external and internal labour • Calculate additions on Risks, Contingencies Price Escalations • Add Profit Margin to calculate Sales Contract Value • Initiate procurement of long lead items * Managed by Noveco Project Planning • Create Project structure • Generate Cost & Revenue planning from approved Estimate • Revenue Plan generated from Sales Contract • Project scheduling with Gantt Chart • Distribute Costs and Revenue along project time line • Simulate Project Cash Flow • Simulate availability of internal resources (e.g. engineers, project managers etc.) Project Execution Phase Resource & Capacity Planning • Simulate Availability of Resources and Capacities • Allocate resources to project WBS elements and / or network activities • Allocate project WBS elements and / or network activities to Work Centers Procurement Materials & Services. Timesheets • MRP (Material Requirements Planning) • Procurement of materials, equipment, services to Project • Time allocation using CATS • Project inventory • Vendor Invoices • Outgoing Payments (cash out) Project Forecasting • Calculate Costs to Complete (CTC) and Estimated at Completion (EAC) from Actual Costs and Purchasing Commitments • Adjust Forecast costs and work to complete • Redistribute plan revenue based on updated CTC and purchase commitments • Progress and Earned Value calculation • Forecast Project Cash Flow • Forecast history • Drill down reporting • Run Result Analysis (profit recognition) at month-end based on the most recent project forecasts Variations & Risk Management Customer Billing • Create, Estimate and Approve Project Variations • Milestone billing based on Sales Contract Billing Plan • Automatically update project Budget, Cost Forecast and Revenue plan from approved variations • Resource Related (Cost Plus) Billing • Assess project risks: Threats and Opportunities • Simulate Pessimistic, Optimistic scenario impact on project profitability • Variation history tracking • Incoming payments (Cash In) Reporting • Operation project reporting • Multi-project reporting with graphical KPIs • Estimate vs Project Costs analysis • Dash-board Analytics Integrated Project Management in SAP * Project Portal / Reporting * Capacity Planning Profit Take (Result Analysis) * Noveco Applications Advanced Analytics Portfolio Planning (PPM) Reporting Analysis Monitoring Forecasting Progress Tracking * Project Manager Workbench Planning Execution Variations * Estimate: Cost & Revenue Create Project * Schedule Dates Procurement, Time Sheets Invoicing, Billing * Project Variations Capacity Evaluation on Work Centers Projects Work Centers WC Hierarchy Welding Assembly Paint March April May June July August September October Cross Project Capacity Planning on Work Centers • Check Work Centers Available Capacity before committing delivery date • Cross Project High level planning and capacity evaluation • Does not require PP orders capacity loading Work Centers Resource Planning • Resource Planning is performed directly in SAP PS using the most up-to-date information about project resource requirements • Available hours are read from person’s SAP HR Work schedule taking into account normal hours, planned holidays, existing allocations. • Cost Plan on a project defines required resources (e.g. Engineer, Draftsman, Project Manager), which are related to persons default activity type defined in HR master record • Project WBS or NWA resource requirements can be shifted (if their requirements are not committed) to periods with available resources • Resources can be allocated as individual persons or as a group of resources (Position or even an entire Work Center can be allocated) • Resources from multiple Work Centers can be allocated to project items • A custom list of available resources can be created by each user • Friendly graphical user interface designed to simplify the resource allocation process Resource Planning with Fiori App • Fiori Tabular Resource Planning functionality available • The same functionality as in WinGui version Resource Planning with Noveco Fiori Gantt Chart Resource Planning with Fiori App with Gantt Chart Set filter to show required resources only • Fiori Resource Planning in Gantt Chart View • Combines Gantt Chart scheduling and tabular Resource allocation functionality • Project elements can be dragged and dropped along the time line to simulate resource availability Resource Planning with Fiori App with Gantt Chart Drag & Drop available resources to project elements Only Project Managers appear in the Resource view Resource Planning with Fiori App with Gantt Chart Resource Planning with Fiori App with Gantt Chart Set filter to show DESIGNERs only Resource Planning with Fiori App with Gantt Chart Resource Planning with Fiori App with Gantt Chart Resource Planning with Fiori App with Gantt Chart Resource Planning with Fiori App with Gantt Chart Resource Planning with Fiori App with Gantt Chart Project Lifecycle: steps in SAP system Tendering and Planning phase Estimating Costs and Revenues • Respond on customer Tenders • Create Estimates from existing templates Sales Contract • Create Sales Contract in SAP from approved Estimate • Flexible hierarchical structure • Price calculation on materials, BOMs, Product Costing, services, external and internal labour • Calculate additions on Risks, Contingencies Price Escalations • Add Profit Margin to calculate Sales Contract Value • Initiate procurement of long lead items * Managed by Noveco Project Planning • Create Project structure • Generate Cost & Revenue planning from approved Estimate • Revenue Plan generated from Sales Contract • Project scheduling with Gantt Chart • Distribute Costs and Revenue along project time line • Simulate Project Cash Flow • Simulate availability of internal resources (e.g. engineers, project managers etc.) Project Execution Phase Resource & Capacity Planning • Simulate Availability of Resources and Capacities • Allocate resources to project WBS elements and / or network activities • Allocate project WBS elements and / or network activities to Work Centers Procurement Materials & Services. Timesheets • MRP (Material Requirements Planning) • Procurement of materials, equipment, services to Project • Time allocation using CATS • Project inventory • Vendor Invoices • Outgoing Payments (cash out) Project Forecasting • Calculate Costs to Complete (CTC) and Estimated at Completion (EAC) from Actual Costs and Purchasing Commitments • Adjust Forecast costs and work to complete • Redistribute plan revenue based on updated CTC and purchase commitments • Progress and Earned Value calculation • Forecast Project Cash Flow • Forecast history • Drill down reporting • Run Result Analysis (profit recognition) at month-end based on the most recent project forecasts Variations & Risk Management Customer Billing • Create, Estimate and Approve Project Variations • Milestone billing based on Sales Contract Billing Plan • Automatically update project Budget, Cost Forecast and Revenue plan from approved variations • Resource Related (Cost Plus) Billing • Assess project risks: Threats and Opportunities • Simulate Pessimistic, Optimistic scenario impact on project profitability • Variation history tracking • Incoming payments (Cash In) Reporting • Operation project reporting • Multi-project reporting with graphical KPIs • Estimate vs Project Costs analysis • Dash-board Analytics Integrated Project Management in SAP * Project Portal / Reporting * Resource Planning Profit Take (Result Analysis) * Noveco Applications Advanced Analytics Portfolio Planning (PPM) Reporting Analysis Monitoring Forecasting Progress Tracking * Project Manager Workbench Planning Execution Variations * Estimate: Cost & Revenue Create Project * Schedule Dates Procurement, Time Sheets Invoicing, Billing * Project Variations Project Execution: MRP, Procurement, Actual Costs Time Sheets Record Hours Engineering & Design CAD modeling Purchase Order Sub-Contract Direct Procurement of Services $ Electrical Sub-Assembly Materials Requirements Planning → Requirements Quantity → Requirements Dates Mechanical Sub-Assembly Final Assembly Pass Material Requirements to MRP ← Stock Reservations ← Purchase Requisitions ← Production Orders Execution of Production Orders • Assign Purchase Orders directly to Production Orders • Post Order confirmations Purchase Order Equipment Services Components Work Confirmation Hours Hours Hours Stock / Inventory EA Kilograms Meters • Issue materials from stock • Project actual costs and purchase commitments are posted Integrated Project Management in SAP * Project Portal / Reporting * Resource Planning Profit Take (Result Analysis) * Noveco Applications Advanced Analytics Portfolio Planning (PPM) Reporting Analysis Monitoring Forecasting Progress Tracking * Project Manager Workbench Planning Execution Variations * Estimate: Cost & Revenue Create Project * Schedule Dates Procurement, Time Sheets Invoicing, Billing * Project Variations Project Manager Workbench • Automatically re-calculates cost to complete (CTC) and Estimated at Completion (EAC) from actual costs and PO commitments posted to PP orders at any time • Recalculates and updates Project Progress • Manual and Automatic distribution of Budget, CTC and Purchasing Commitments • Manual adjustment of CTC and EAC • Full forecast history tracking • Supports monthly review cycle using planning period concept • Drill-down into transactional data: commitments, actual line items etc. • Variation & Risk Management • Cash Flow Forecast • Workbench uses PS info-system to read and write and resides directly in SAP • No BW, BI-IP etc. is required • No interfaces, no data transfer Update Project Forecast • Actual Costs and PO commitments rolled up to WBS from Production Orders • Recalculate project Costs to Complete (CTC) and Estimated at Completion (EAC) from PP orders • Manually update (if needed) cost and work to complete • Drill down to source documents • Real time integration Distribute Remaining Cost To Complete Manually or automatically distribute: • Cost To Complete • Current Budget • Plan Revenue • PO Commitments Calculate Project Progress • Project Progress is automatically recalculated • PP orders progress is automatically included into project overall progress Project Cash Flow report • Project Cash Flow report calculates and presents: • Cash In from Sales Order billing plan, invoices, down payments etc. • Cash Out from Purchase Order commitments, invoices, down payments, remained CTC etc. Project Manager Workbench • Graphical presentation of project KPIs • Configurable layout • Up to 20 graphs available Integrated Project Management in SAP * Project Portal / Reporting * Resource Planning Profit Take (Result Analysis) * Noveco Applications Advanced Analytics Portfolio Planning (PPM) Reporting Analysis Monitoring Forecasting Progress Tracking * Project Manager Workbench Planning Execution Variations * Estimate: Cost & Revenue Create Project * Schedule Dates Procurement, Time Sheets Invoicing, Billing * Project Variations (multi-) Project reporting Multiple Project Reporting with graphical view directly from ECC or S4 (no BW or other reporting tools needed) Noveco Application in SAP UI5 / Fiori Fiori Tiles: Launchpad Project Manager Workbench (Fiori version) Project Manager Workbench (Fiori version) Project Manager Workbench (Fiori version) Project Manager Workbench (Fiori version) Project Manager Workbench (Fiori version) Project Manager Workbench (Fiori version) Project Manager Workbench (Fiori version) Project Manager Workbench (Fiori version) Project Manager Workbench (Fiori version) Project Manager Workbench (Fiori version) Project Manager Workbench (Fiori version) Summary • With Noveco solutions you can now effectively control your ETO project manufacturing and engineering processes directly in SAP Project System • The Original Project Cost Plan is always accurate, since it is based on Product Costing. • The system automatically recalculates Cost and Work To Complete from actual costs posted to network activities and PP orders. • You can adjust project Forecast Costs at any time, if necessary. • The system calculates Project progress by taking production progress into account. • You can Drill Down into source documents. • Run operational reports directly from SAP PS. Strategic Planning System Landscape including Noveco Analysis, Resourcing Reports Program & Portfolio Planning Result Analysis Resource Planning PS Information System ● ● ● ● ● ● ● Monitoring, Forecasting, Variations, Progress Execution Estimation Budget values Company Reporting Advanced Analytics Time Sheets, Invoices Actual Costs Sales Orders Revenue Transactional System Project Manager Workbench Automatic Forecasting Manual adjustment of CTC or Work TC Progress Analysis Exception and drill down reporting Integrated variations into cost forecast Forecast history Purchase Orders, Commitments Variations S A P E C C / S 4 Noveco: Estimation, Forecasting, Progress and Variation Management ● Full scale Estimating solution in SAP PS. Create estimates before project is created / approved in SAP ● Project Manager Workbench provides one central place to review KPIs, update forecasts, track and update progress, execute analytical and drill down reports ● Complete Cost and Work To Complete management: Automatic reduction and Manual adjustment ● Instant Integration with ECC transactions: PO, time sheets, invoices etc. ● Forecasting results are immediately available for Result Analysis, Progress Analysis, PS Reports and BI (no custom interfaces needed to native SAP reports) ● Period Sensitive Forecasts: designed for month end forecasts in live transactional system ● Saves project forecast history w/o need to perform version copy by the user ● Project Costs Forecasts integrated with PM/CS and PP orders ● Integrates Project Variations into cost forecasting and budgeting ● No modifications to SAP standard core applications. No “z-tables” to keep forecasts costs, all data read/written from/to SAP standard database. Business Value of Integrated Project Forecasting in SAP ● Connects upstream (estimating, procurement, timesheets) and downstream (monitoring, resource allocation, analytical reports) activities of project management lifecycle ● Closes the loop between execution and analysis processes providing 360 degree flow of information ● Replaces spreadsheets and other third party tools with centralized SAP database ● Reduces amount of effort required to produce project forecasts and analytical reports ● Reduces number of interdependent systems and interfaces needed; reduce costs of maintenance and support of systems other then SAP ● Decreases potential for errors of data entry and manipulation ● Improves quality, transparency and accuracy of data ● Allows potential savings and process efficiency by relieving Project Managers from performing routine transactional and administrative activities. ● Integrates Resource (personnel) Planning into project planning and forecasting ● Determine realistic project progress ● Unleashes the true power of integrated SAP system Our Customers For more information visit Noveco Systems on www.novecosystems.com