KPD & TAY Oil and Gas Field Power Generation Report Submitted To: Mr. Khalid Somro (I/C Electrical KPD-TAY) Submitted By: Akhlas Ahmad (ATE Trainee) 1|Page Table of Contents INTRODUCTION TO KPD-TAY PLANT 3 POWER REQUIREMENTS OF PLANT 4 POWER FLOW 4 MCC5 6 INTRODUCTION TO POWER HOUSE 8 GAS ENGINE GENERATOR SET 8 GAS ENGINE DESCRIPTION AND FEATURES 9 ENGINE FUEL DESIGN FEATURES GAS ENGINE SPECIFICATIONS 9 9 10 ESM CONTROL SYSTEM 11 STARTING PROCEDURE OF GAS ENGINE PRE-CHECKS BEFORE STARTING A GAS ENGINE (KPD) SYNCHRONIZATION STOP PROCEDURE (NORMAL SHUTDOWN) EMERGENCY SHUTDOWN FAULT EMERGENCY SHUTDOWN CUSTOMER INITIATED SHUTDOWN ESM COMPONENTS (WITHIN SCOPE OF OPERATION) 12 14 14 16 18 18 18 20 FAULT ALARMS AND SAFETY SHUTDOWNS 21 SAFETY SHUTDOWNS 22 MV SWITCHGEAR (POWER HOUSE) 23 PROTECTION RELAYS IN M.V SWITCHGEAR KPD 23 2|Page Introduction to KPD-TAY Plant KPD-TAY Plant is located adjacent to Company’s existing Kunnar LPG plant in Sindh Province and about 25 Kilometers from Hyderabad City. OGDCL has completed the Early Production Facilities (Project Phase-I) and at present OGDCL is producing 1100 BPD of Oil and 100 MMSCFD gas without LPG/NGL extraction. OGDCL plans to develop KPD-TAY Integrated (Project Phase-II) by installing Wellhead facilities and Flow lines for 29 wells, 25 Kilometer long Trunk Line (Dia 12”), gas gathering system, Dehydration plant, Amine plant, LPG Plants, Hot Oil system, Power Generation, Sale Gas/ Wellhead Compression, Sale Gas Metering, and Allied Utilities to process 250 MMSCFD raw gas.The major part of project was awarded to M/S Shamgdong Kerui on EPCC basis and remaining supplies & works was awarded to five (05) PC Contractors. All the contractors are onboard and project activities are in progress. Product Name Gas LPG Oil Quantity 225 MMCFD 410 M. Tons/Day 5100 BOPD Plant major installations are done by foreign and local contractors. Trade Contractors Mechanical (Pipe Lines, Towers, Kerui Petroleum Pumps, Fans, Compressors ect) Motor Control Center/s Descon Engineering Limited, Siemens AG, IGEL Electric GmbH & ZEL Central Control Room Siemens AG, ABB 3|Page Power Requirements of Plant TOTAL ESTIMATED LOAD 8000-9000 KW Voltage Generation 6.6 KV (MV) L.V (Stepped Down) 415 v M.V Load 2400-2700 KW (30% of Total Load) L.V Load 5600-6300 KW (70% of Total Load) Power Flow Power house energize Main MCC with 6.6 KV (MV) supply. Main MCC MV switchgear takes MV input and further distributes 6.6 KV to MV motors in Amine and Dehydration area. Additionally, MV Switchgear energizes step-down transformers with 6.6 KV to be stepped-down to L.V supply (415 V). There are 6 step-down transformers which take MV supply from Main MCC MV Switchgear and step-down it to L.V (415 V). 1. Transformer 1 (1250 KVA) energizes MCC1 which feeds Amine Area, Dehydration Area and LPG Recovery Area Train 1. 2. Transformer 2 (1250 KVA) energizes MCC2 which feeds Amine Area, Dehydration Area and LPG Recovery Area Train 2. 3. Transformer 3 (1600 KVA) energizes MCC3A which feeds Sale gas Compression Area. 4. Transformer 4 (1600 KVA) energizes MCC3B which provide redundancy for Transformer 3. 4|Page 5. Transformer 5 (2000 KVA) energizes MCC4A which feeds Hot Oil Area, Cooling Tower and Lighting load. 6. Transformer 6 (2000 KVA) energizes MCC4B which provide redundancy for Transformer 5. Transformer Rating Feeding Area Input/Output MCC1 1250 KVA 6600/400 V MCC2 1250 KVA MCC3A 1600 KVA MCC3B (Redundant) 1600 KVA MCC4A 2000 KVA MCC4B (Redundant) 2000 KVA Amine, Dehydration, LPG Recovery Train 1 Amine, Dehydration, LPG Recovery Train 2 Sale gas Compression Area Sale gas Compression Area Hot Oil Area, Cooling Tower, Lighting Hot Oil Area, Cooling Tower, Lighting 5|Page 6600/400 V 6600/400 V 6600/400 V 6600/400 V 6600/400 V MCC5 MCC5 consist of MV Switchgear, L.V Train and 2 step-down transformers. MCC5 MV Switchgear is supplied 6.6 KV via Main MCC Switchgear which is stepped-down to L.V (400 v). All gas engine auxiliaries are supplied via MCC5 L.V Train. Additionally, Admin Area, Fire Station, AC UPS and Workshops are also supplied via MCC5 L.V Train. Important: In case of blackout, Diesel engine will energize MCC5 via Main MCC and all gas engine auxiliaries will be supplied via MCC5 in order to start gas engine/s to restore Power supply. MCC5 Transformer 1 feeds L.V train and Transformer 2 provide redundancy for Transformer 1. Transformer Rating Feeding Area Input/Output MCC5A 2000 KVA Gas engine Auxiliaries, AC UPS, Admin Area, Fire Station & Workshop 6600/415 v Mcc5B (Redundant) 2000 KVA 6|Page 6600/415 v // Power Flow Block Diagram (Power House to Main MCC) 7|Page Introduction to Power House Power house consist of 6 gas engine generators (3.4 MW x 6), 1 Diesel engine (1.4 MW), M.V switchgear along with DC UPS, AC UPS and MCP Panel along with computer. Gas Engine Generator Set 5 gas engine generators are installed in power house as primary source of power supply. Reasons for using gas engine set in KPD-TAY Plant over Turbine or Diesel system: Fuel – Gas Engine is very suitable to install in KPD-TAY Plant as Natural gas is most convenient source of fuel here as a matter of cost. Shutdown Period – Gas Engine set allow shutdown period to be very short as sequence maintenance can be very handy in order to avoid blackout/overall shutdown. Easy to Operate – Gas engines are easy to operate (Start /Stop) as compare to Gas turbine. Important: Power house total capacity is 17000 KW. As per estimated total load (8000-9000 KW), 4 Generators will be on-load while each generator will be bearing 2250 KW 66% of its total capacity, which will increase efficiency and reliability minimizing the required maintenance ratio as well. Dated 11/16/2016, total load is 3300-3400 KW, 3 generators are on-load, each sharing 33% (about 1100 KW) of load. 8|Page Gas Engine Description and Features The Dresser Waukesha 12V/16V275GL+ engine is a four-cycle, prechamber, lean burn, V-configuration engine. The 16V275GL+ has a total cylinder displacement of 285 L (17,398 cu. in.) and the 12V275GL+ has a total cylinder displacement of 214 L (13,048 cu. in.). Engine Fuel The 12V/16V275GL+ engines operate on natural gas, and are designed for low fuel consumption and reduced exhaust emissions. This is accomplished through a “stratified charge” combustion chamber in which a very lean fuel mixture is burned. The lean combustion concept requires pre-chamber-type cylinder heads that permit the engine to run at a natural gas AFR of approximately 32:1 on current models (Spindt). Spindt is a method of measuring AFR. It is an AFR calculated from the chemical composition of air, fuel and the measured exhaust gas constituents. Design Features The design features of the engines include: • • • • High horsepower Sturdy construction, rugged and compact Low exhaust emissions Easy access to all major components, resulting in good serviceability • Fuel-efficient and minimal fuel system complexity • Dresser Waukesha ESM, a total engine management system designed to optimize engine performance and maximize uptime 9|Page Gas Engine Specifications Property Values Manufacturer Model No Weight Volts Act Power Appr. Power Frequency Phase AMPS P.F Number of Cylinders Speed Range Firing Order Waukesha 16V275GL 57200 KG 6600 v 3360 KW 4200 KVA 50 HZ 3 367 A 0.8 16 750-1000 rpm 1R-1L-4R-4L-7R-7L-6R-6L-8R-8L5R-5L-2R-2L-3R-3L Normal Oil Pressure Low Oil Shutdown Set-point Pre-Lube Duration Post-Lube Duration Normal Gas Pressure Air Starting Pressure 60-65 PSI 45 PSI 90 Secs 60 Secs 45-60 PSI 120-150 PSI Exciter Properties Field AMPS Field Volts PMG Volts PMG Hertz 10 | P a g e 5.5 A 50 V 120/240 V 100 Hz ESM Control System The Dresser Waukesha ESM is a system designed to optimize engine performance and maximize uptime. The ESM integrates: Spark timing control Speed governing Knock detection Start-stop control Air-fuel control Diagnostic tools Fault logging Engine safeties In addition, the ESM system has safety shutdowns such as low oil pressure, engine over-speed, high IMAT, high coolant outlet temperature and uncontrolled knock. 11 | P a g e Starting Procedure of Gas Engine The ESM manages the start, normal stop and emergency stop sequences of the engine, including prelube and postlube. Logic to start and stop the engine is built into the ECU, but the user/customer supplies the interface (user panel) (control panel buttons, switches, touch screen) to the ESM. The ESM’s start-stop process is controlled by the following digital inputs: • Start Signal – a momentary “high” (8.6 – 36 volts) input to the ECU indicating the engine should be started. The minimum duration of the signal is 1/2 second but should not exceed 1 minute. • Run/Stop Signal – a continuous “high” (8.6 – 36 volts) input to the ECU indicating the engine should be running. When this input goes “low” (less than 3.3 volts), the ECU performs a normal shutdown. • Emergency Stop Signal – a continuous “high” (8.6 – 36 volts) input to the ECU indicating the engine is OK to run. When the input is “low” (less than 3.3 volts), the ECU performs an emergency shutdown. For the engine to start, the start signal must be configured as a momentary event such that it goes “high” (8.6 – 36 volts) for at least 1/2 second (not to exceed 1 minute). In addition, to start the engine, the shutdown signals must both be “high” (8.6 – 36 volts). Although the start signal must go “low” (<3.3 volts) after starting, the shutdown 12 | P a g e signals must remain high for the engine to run. If either shutdown signal goes low, even for a fraction of a second, the engine will stop. During the start sequence, the ESM performs the following steps: • Prelubes engine (programmable from 0 – 10,800 seconds from the Prelube Time field located on the [F3] Start-Stop Panel) • Engages starter motor (programmable rpm range using ESP software) • Turns ignition on (after a user-calibrated purge time using ESP software) • Turns main fuel on (programmable above a certain rpm and after a user-calibrated purge time using ESP software) • Turns prechamber fuel on (programmable above a certain rpm and after a user-calibrated purge time using ESP software) When the user initiates a start from the user panel, a signal is sent to the ECU to begin the start procedure. After receiving a start signal, and confirming the emergency stop and run/stop signals are high, the ECU prelubes the engine for a user-calibrated period of time. Once the prelube is complete, the starter is activated. The ignition is energized after the engine has rotated through a minimum of two complete engine revolutions and a user-calibrated purge timer has expired. When the engine speed reaches an rpm determined by Dresser Waukesha, the main gas shutoff valve is energized. After the engine speed exceeds a slightly higher rpm, the prechamber main gas shutoff valve is energized at an rpm calibrated by Dresser Waukesha, factoring in the value located in “Starter OFF rpm adj” field located on the Start-Stop Panel. The engine then increases speed until it 13 | P a g e reaches its governed rpm. Once the starter is activated, a timing circuit begins. If the engine does not reach a minimum rpm within a calibrated amount of time, the ECU will initiate a shutdown and deenergize the starter. Pre-Checks before Starting a Gas Engine (KPD) 1. Utility air pressure must be 120-150 PSI. 2. Check the utility air valve position, open if closed. 3. Check the oil level on gauge; re-fill if lower than 15 MM out of 30 MM. 4. Check fuel gas valve position, must be opened. 5. Fuel gas pressure must be 25-60 PSI. 6. Put all radiator fans on Auto Mode. 7. Inlet fan 1 & 3 should be on Manual Mode. 8. Exhaust temperature should be greater than 900F. Note: Wait until exhaust temperature reach 700F, if exhaust temperature does not reach 900F within 10 minutes, check issues related to exhaust values. 9. Generator must be remain Off-load 5-10 minutes after start-up. 10. Before putting on load, temperature of oil header should be equal or greater than 140F and temperature of jacket water should be equal or greater than 160F. Additionally, oil pressure must be equal or greater than 75 PSI. Synchronization Synchronization is auto and is controlled by ESM. Synchronization period can take up-to 180 secs. 14 | P a g e 15 | P a g e Stop Procedure (Normal Shutdown) During the normal shutdown sequence, the ESM performs the following steps: • • • • Begins cooldown period (programmable using ESP software) Shuts off fuel Stops ignition when engine stops rotating Postlubes engine (programmable from 0 – 10,800 seconds using the Start-Stop Panel) When performing a normal engine shutdown, the engine should be stopped by causing the normal stop (or run/stop) input to go “low”. This turns off the fuel supply before ignition is halted, eliminating unburned fuel. It runs the postlube procedure supplying oil to vital engine components. When the run/stop digital input to the ECU goes low (less than 3.3 volts), and a user-calibrated cooldown period is met, the ECU stops the engine. This is accomplished by first de-energizing the main gas shutoff valve and prechamber main gas shutoff valve and then, when the engine speed drops to zero, de-energizing the ignition. If the engine fails to stop in a preprogrammed period of time (typically less than 1 minute) after the main gas shutoff valve has been de-energized, the ignition is de-energized, forcing a shutdown. Note: The emergency shutdown switch should be pulled out (OFF position) at all times, unless an emergency situation occurs that requires the immediate shutdown of the engine. 16 | P a g e Stop Flow Diagram 17 | P a g e Emergency Shutdown When an E-Stop is activated, the main gas shutoff valves are closed and the ignition is de-energized immediately. Warning: The customer emergency shutdown must never be used for a normal engine shutdown. The customer emergency shutdown must only be used to shut down the engine when personal injury or property damage may result. All other engine shutdowns are to be initiated as a normal shutdown using the RUN/STOP input. Using the customer emergency shutdown may result in unburned fuel in the exhaust manifold. Failure to comply increases the risk of an exhaust explosion. Fault Emergency Shutdown If the ESM detects a serious engine fault and shuts the engine down, it will energize a digital output from the ECU so that the user knows the ESM shut down the engine. It is extremely important to not use ESD222 CUST ESD for normal shutdowns, as the postlube will not occur and the risk of an exhaust explosion increases. If the ESM detects a fault with the engine or with the ESM’s components that is not serious enough to shut the engine down, a different digital output will be energized so that the user knows of the alarm. Customer Initiated Shutdown After a Customer Emergency Shutdown ESD222 CUST ESD is initiated (ESD pin 15 low), the Emergency Shutdown input ESD pin 15 should then be raised “high.” Raising ESD pin 15 high allows the ECU to go through a reboot. A subsequent start attempt may fail if it 18 | P a g e is initiated less than 60 seconds after raising ESD pin 15 high because the ECU is rebooting. Emergency Shutdown Flow Diagram 19 | P a g e ESM Components (Within Scope of Operation) ECU The ECU is the central module or “hub” of the ESM system. The ECU is the single entry point of system control for easy interface and usability. The entire ESM system interfaces with the ECU. Based on system inputs, the ECU logic and circuitry drive all the individual subsystems. HMI The HMI provides the interface to the NOx Control Module (NCM) as well as allows the user to view overall ESM system status. The HMI is a high-resolution 160 x 180 pixel FSTN display with onengine mounting (optional off-engine mounting available). The HMI interfaces with the NCM through CAN communication for ESM displayed values, faults and stepper calibrations. The HMI provides the MODBUS output for customer use. The ESM system will continue to control the engine without the HMI connected, but the HMI must be present for NCM setup and monitoring and MODBUS communications. Power Distribution Junction Box The power distribution junction box is used to protect and distribute 24 VDC power to all the components on the engine that require power, such as the ECU, IPM-D and actuators; no other power connections are necessary. It also triggers controlled devices such as the pre-lube motor and fuel valve. The power distribution junction box contains circuitry to clamp input voltage spikes to a safe level before distribution. It will disable individual output circuits from 20 | P a g e high-current events such as a wire short. Also, LEDs inside the power distribution junction box aid in troubleshooting of the individual output circuits. Stepper (AGR, Actuator, Gas Regulator) A stepper motor is mounted on the gas regulator and is used to adjust the gas/air at the direction of the NCM. ESM Sensors A wide variety of sensors are used to provide critical operating information to the ECU. If a sensor provides a signal outside the normal range long enough, the ECU will flag either an alarm or a shutdown, depending on how great the value deviates from normal or if the values exceed the set-points programmed in ESP. Sensors normally do not require maintenance or adjustments. Fault Alarms and Safety Shutdowns When a fault occurs, several actions may take place as a result. A fault can have both internal actions and external visible effects. Each fault detected will cause one or more of the following actions to occur: • Alarm is logged by the ECU and appears in the ESP fault log. • Yellow status LED on the front of the ECU lights and begins to flash a fault code. • Shutdown occurs and the red status LED on the front of the ECU lights and flashes a code. • Sensors and actuator switch into a “default state” where the actuator/sensors operate at expected normal values or at values that place the engine in a safe state. When the default state takes control, an alarm is signaled and the fault is logged but the 21 | P a g e engine keeps running (unless, as a result of the fault, a shutdown fault occurs). • Alarm or shutdown signal is transmitted over the customer interface (RS-485 MODBUS and digital output). • Fault banner flashes on HMI screen. • Fault log available from the HMI. Safety Shutdowns The ESM provides numerous engine safety shutdowns to protect the engine. These engine safety shutdowns include: • E-Stop button on each side of the engine • Low oil pressure • Engine overspeed – 10% overspeed instantaneous – Factorycalibrated to run no more than rated speed – User-calibrated driven equipment overspeed • Customer-initiated emergency shutdown • Engine overload (based on percentage of engine torque) • Uncontrollable knock • HT water coolant temperature • HT water coolant pressure • High IMAT • Overcrank • Engine stall • Security violation • High oil temperature • Failure of magnetic pickup • Internal ECU 22 | P a g e MV Switchgear (Power House) MV switchgear in Power House is responsible for M.V output transmission to Main MCC. M.V switchgear receives inputs from 6 generators via SPP (Surge Protection Panel), merge the power using section breakers, apply required protections and control the input and output. Power House transmission scheme allow M.V Switchgear to supply Main MCC via one of 3 available output feeders while each feeder has a standby feeder as well. As per to-date, 2 feeders are available/ready and only one of these shall be energized to supply the system while one output feeder is spare. M.V switchgear protection relays and DC components are supplied by DC UPS. Vacuum Circuit Breaker is used for primary circuit tripping purpose. Protection Relays in M.V Switchgear KPD Multi-Functional Protective Relay with Local Control 7SJ68 Multi-Functional Protective Relay with Local Control 7SJ68 provide following critical protections: 1. Voltage Protection Over-Voltage Protection Under-Voltage Protection 2. Unbalanced Load Protection 23 | P a g e 3. Frequency Protection Under-Frequency Protection Over-Frequency Protection 4. Load Jam Protection 5. Thermal Overload Protection 6. Earth Fault Protection 7. Circuit Breaker Failure Protection Differential Protection 7UT68 1. 2. 3. 4. Differential Protection Differential Current Protection Over Excitation Protection Reveres Power Protection And all above mention protections as well. 24 | P a g e M.V Switchgear Output Scheme Flow Diagram 25 | P a g e