Uploaded by lywong0810

Toshiba VRF Units T&C Procedure (2)

advertisement
8. TEST OPERATION
8-1. Procedure and Summary of Test Operation
A test operation is executed in the following procedure. When a trouble or an error occurs in each step, remove
causes of a trouble or an error referring to the section “9. Troubleshooting”.
Check before test operation
Check the basic items, mainly the installation work.
Be sure to enter the check results in the check list 1 and 2.
Check the main power supply
is turned on.
It is the check after the power has been turned on.
Check the refrigerant circuit system is normally turned on.
Start the address setup in the outdoor/indoor units.
(NOTE) The operation does not start by only power-ON.
Set up the addresses.
Carry out a test operation.
Check air blowing and cooling/heating operation in the indoor unit.
Test operation
END
8-2. Check Items before Test Operation
2
Prior to the test operation, check the following items
so that there is no trouble in the installation work.
<Main check items for electric wiring>
4
Header unit (A)
3
Follower unit (B)
U3 U4
1
The communication system differs from
that of R22 or R407 refrigerant
“Modular Multi system”
air conditioner.
Check again cautious points on wiring.
Outdoor
unit
1. In case that a center control
system is not connected:
3-phase
380-415V
Leak interception
U1 U2
Follower unit (C)
U3 U4
U5 U6
U1 U2
U3 U4
U5 U6
U1 U2
U5 U6
Earth
5
5
Main switch
U1 U2
Indoor
unit
A B
U1 U2
U1 U2
A B
A B
U1 U2
A B
1-phase 230V
Leak interception
Main switch
No.
Remote controller
Main check items
Check

Are indoor and outdoor communication lines of the header unit connected to U1/U2
terminals?
‚
Is the relay connector between U1/U2 terminal and U3/U4 terminal removed?
(Set up at shipment from the factory)
ƒ
Is the communication line between each outdoor units connected to U5/U6 terminal?
„
Is the terminal resistance (SW30-2) on the interface P.C. board of the header unit
turned on? (Set up at shipment from the factory)
Is the end terminal of the shield cable grounded?
NOTE) The above figure does not show all the electric cables.
For details, refer to the installation manuals for outdoor unit, indoor unit, remote controller, or optional devices.
88
2. In case that a central control system is connected (Before address setup)
Central control units
U1 U2
U3 U4
4
Other refrigerant line
2
5
Header unit (A)
U3 U4
Other refrigerant line
3
Follower unit (B)
U3 U4
Follower unit (C)
U3 U4
U3 U4
Outdoor unit
U1 U2
U5 U6
U1 U2
1
U5 U6
U1 U2
U5 U6
U1 U2
U5 U6
Earth
To indoor unit
3-phase
380-415V
Leak interception
6
6
Main switch
U1 U2
U1 U2
U1 U2
U1 U2
Indoor unit
A B
A B
A B
Remote
controller
Remote
controller
Remote
controller
A B
1-phase 230V
Leak interception
Main switch
No.
Main check items

Are indoor and outdoor communication lines of the header unit connected to U1/U2
terminals?
‚
Is the relay connector between U1/U2 terminal and U3/U4 terminal removed?
(Set up at shipment from the factory) (Before address setup, remove the relay connector.)
ƒ
Is the communication line between outdoor and indoor units connected to U5/U6 terminal?
„
Is the communication line of the central control system connected to the header unit U3/U4
terminals of each refrigerant line?
(The communication line of the central control system may be connected to the communication lines of the indoor/outdoor communication lines.)
Check
Is the terminal resistance (SW30-2) on the interface P.C. board of the header unit turned on?
(Set up at shipment from the factory)
(After address setup, turn off SW30-2 of the header unit except the smallest unit after
check of trial operation.)
†
Is the end terminal of the shield cable grounded?
‡
When the refrigerant line and the central control system of the custom air conditioner are
connected:
→ Are TCC-LINK adaptors correctly connected?
→ When the digital inverter air conditioner operates with group operation, twin, or triple
operation, are the adopters connected to the header unit of the indoor unit?
NOTE) The above figure does not show all the electric cables.
For details, refer to the installation manuals for outdoor unit, indoor unit, remote controller, or optional
devices.
89
<Check list 1>
• Using the “Check list 1”, check there is no trouble in the installation work.
Is capacity of the leak
breaker appropriate?
Outdoor total capacity XXXX A
Is diameter of the power cable correct?
Is control communication line correct?
Header unit (A)
XXXX A
Follower unit (B)
XXXX A
Follower unit (C)
XXXX A
Follower unit (D)
XXXX A
Header unit (A)
XXXX mm²
Follower unit (B)
XXXX mm²
Follower unit (C)
XXXX mm²
Follower unit (D)
XXXX mm²
Indoor unit XXXX A
Indoor unit XXXX mm²
Indoor –outdoor connection terminals (U1, U2)
XXXX
Outdoor–outdoor connection terminals (U5, U6)
XXXX
Central control system connection terminals (U3, U4)
XXXX
Is power of indoor units supplied collectively?
Is earth grounded
Is insulation good?
Is the main power voltage good?
XXXX V
Is diameter of connecting pipe correct?
Is the branch kit correct?
Is drain water of the indoor unit arranged so that it flows without accumulation?
Is thermal insulation of pipes good? (Connecting pipes, Branch kit)
Is not short-circuit of discharge air in indoor/outdoor units?
After airtight test for pipes, are vacuuming and adding of refrigerant executed?
Are valves of all the outdoor units fully opened?
Gas side
Liquid side
Balance side
Header unit (A)
XXXX
XXXX
XXXX
Follower unit (B)
XXXX
XXXX
XXXX
Follower unit (C)
XXXX
XXXX
XXXX
Follower unit (D)
XXXX
XXXX
XXXX
90
• Check the additional amount of refrigerant.
<Check list 2>
Calculate the additional amount of refrigerant from the additional amount of refrigerant (A) by the pipe diameter at liquid side and the pipe length to be connected and the corrective amount of refrigerant (C) by the
system capacity.
Additional amount Actual liquid Additional amount of
Corrective amount of
=
×
+
of refrigerant
pipe length
refrigerant per liquid pipe 1m
refrigerant by system capacity


































(A)
(C)
Firstly enter the total length for each liquid pipe in the following table, and then calculate the additional amount
of refrigerant by pipe length.
<Additional amount of refrigerant by pipe length>
Pipe dia at
liquid side
Standard amount of refrigerant
kg/m
Total pipe length at each liquid side
Additional amount of refrigerant pipe
dia at each liquid side kg
Ø6.4
0.025 ×
=
kg
Ø9.5
0.055 ×
=
kg
Ø12.7
0.105 ×
=
kg
Ø15.9
0.160 ×
=
kg
Ø19.0
0.250 ×
=
kg
Ø22.2
0.3505 ×
=
kg
Additional amount of refrigerant by pipe
length (A)
kg
Next, refer to the following table for the corrective amount of refrigerant (C) by system capacity.
<Corrective amount of refrigerant by system capacity>
System horse
power HP
Normal type
Unit
1
Unit
2
Unit
3
Unit
4
Corrective amount
of refrigerant (C) kg
System horse
power HP
Normal type
Unit
1
Unit
2
Unit
3
Unit
4
Corrective amount
of refrigerant (C) kg
5
5
0
28
10
10
8
–2.0
6
6
0
30
10
10
10
0
8
8
1.5
32
8
8
8
10
10
2.5
32
12
10
10
12
12
3.5
34
10
8
8
14
8
6
0
34
12
12
10
16
8
8
0
36
10
10
8
18
10
8
0
36
12
12
12
20
10
10
3.0
38
10
10
22
8
8
6
0
40
10
22
12
10
5.0
42
24
8
8
8
–4.0
44
24
12
12
7.0
26
10
8
–4.0
8
8
–6.0
1.0
8
–6.0
3.0
8
–6.0
10
8
–6.0
10
10
10
–5.0
12
10
10
10
–4.0
12
12
10
10
–2.0
46
12
12
12
10
0
48
12
12
12
12
2.0
4.0
Lastly add the additional amount of refrigerant by pipe length (A) to the corrective amount of refrigerant by
system capacity (C). It is the final additional amount of refrigerant.
As the result, If minus sign is indicated, do not add the refrigerant (=0kg).
<Additional amount of refrigerant>
Additional amount of refrigerant by pipe length (A)
kg
Corrective amount of refrigerant by system HP (C)
kg
Additional amount of refrigerant
kg
91
Download