COMMISSIONING PROCEDURE 1 X 23.1 TPH WASTE HEAT RECOVERY BOILER (AQC-3) ON CEMENT KILN SUPPLIED TO M/s ULTRATECH CEMENT LIMITED RAJASHREE CEMENT, MALKHED, KARNATAKA TBWES PROJECT NO.: PL 1862 SUPPLIED BY THERMAX BABCOCK & WILCOX ENERGY SOLUTIONS PVT. LTD. PUNE, INDIA RECORD OF REVISIONS: REV. DATE PREPARED BY REVIEWED BY APPROVED BY 0 12.08.2021 SP Executive – FE CSG Sr. Manager – FE CSG Sr. Manager – FE Note: This is a computer generated document and hence requires no Signature. PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) 1. BOILER COMMISSIONING ACTIVITIES SEQUENCE......................................... 3 2. PRE-COMMISSIONING CHECK LIST ................................................................ 4 3. FLUSHING OF BOILER, PIPING AND VESSELS .............................................. 11 4. TRIAL OF AUXILIARIES / EQUIPMENT’S....................................................... 13 5. REFRACTORY DRY OUT & ALKALI BOIL OUT ................................................. 14 A. B. INPUTS REQUIRED FROM CUSTOMER ........................................................................................... 14 CHECKLIST PRIOR TO ALKALI BOIL OUT ACTIVITY ....................................................................... 15 REFRACTORY DRY OUT AND ALKALI BOIL OUT CURVE.....................................................20 6. STEAM BLOWING OF MAIN STEAM PIPING .................................................. 21 INPUTS REQUIRED FROM CUSTOMER: ................................................................................................... 21 PROCEDURE FOR STEAM BLOWING ....................................................................................................... 22 PRESSURE RAISING CURVE.................................................................................................................... 26 SKETCH FOR STEAM BLOWING ARRANGEMENT ..................................................................................... 27 ACCEPTANCE CRITERIA FOR STEAM BLOWING ...................................................................................... 28 LOG SHEET FOR STEAM BLOWING:........................................................................................................ 29 7. SAFETY VALVE SETTING ................................................................................ 30 PROCEDURE .......................................................................................................................................... 30 Commissioning Procedure | WHRB Page 2 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) 1. BOILER COMMISSIONING ACTIVITIES SEQUENCE Commissioning of the boiler would proceed as under 1. Pre-commissioning Check list 2. Flushing of piping and vessels 3. Trials of auxiliaries and equipment 4. Refractory Dry-out & Alkali boil out 5. Steam blowing of main steam piping 6. Safety valve setting Commissioning Procedure | WHRB Page 3 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) 2. PRE-COMMISSIONING CHECK LIST AREAS TO BE CHECKED S. No 1. DESCRIPTION AREAS TO BE CHECKED AVAILABILITY OF DOCUMENTS 1. O & M Manual comprising : General procedures, Operation, Maintenance and trouble shooting. Basic drawings with latest rev. for pressure parts, P&I Diagram, Thermal expansion drawing etc., Mechanical components manual, General assembly Drawing, Data sheets, Process flow data, Electrical and Instruments components manual and data sheets, logic write-ups, valve & instrumentation schedule, wiring diagram. 2. Approved design calculations & analysis reports for piping, structural stability etc. 3. Calibration certificates & handing over protocols & inspection dossier. 4. Commissioning procedures. 5. Reference drawings. 6. Vendor list / contract details, nearest agent. 7. Commitment of inputs & outputs operating condition. 8. Handing over documents. (Completion of mechanical checklist points). 1. Installation checks. 2. Boiler, casing & supporting. 3. Piping & supports. 4. Structure and platforms. 5. Mechanical auxiliaries. 6. E & I auxiliaries. 7. Customer scope items. 8. Inputs for commissioning. 9. General & Safety. 1. With respect to P & I Diagram of latest revision : • Check instrument type, location and quantity. • Piping connection and size. • Input condition with respect to operating data. • Sampling points. • Location and connection of Mechanical components (like valves, safety valves etc.) 2. With Thermal Expansion Drawing : • Position of pointers to measure expansion for Boiler and Riser and down comers. • Check clearance / provision available for : Pressure parts • Buck-stay assembly, Casing & Ducting, Supports etc. • Ensure proper expansion clearance for steam drum / supporting main down comers. 3. With Boiler General Assembly Drawing : • General Layout. 2. AREAS OF CHECK 3. INSTALLATION CHECK Commissioning Procedure | WHRB STATUS Page 4 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) • • • • • • 4. BOILER PRESSURE PARTS / CASING / SUPPORTING 1. • • • • • • 2. • • • • • • • • 3. • • • • 4. • • • • 5. PIPING AND SUPPORTS Commissioning Procedure | WHRB 1. • • • Location of Mechanical and Electrical & Instruments and its accessories. Expansion bellows. Routing of Ducting. Access. Co current & reverse current of flow (steam/water) with respect to the flue gas. Draining facility from all bottom headers and venting facility for top header. Steam Drum Internal: Sparger pipe location, orientation of holes, supporting as per steam drum internal drawing. Demister pad as per specification sheet, condition and mounting arrangement. Availability of proper manhole gaskets. Installation of Baffle plates, and its tightening with proper hardware as per internals drawing. Inspect for any blockage of ports for mountings & instrument tapping points. Internal cleaning & removal of foreign material. Coils hanging support arrangements: Check for alignment. Check for locking arrangement. Check for deflection. Check for gaps. Check for hardware. Check completion of welding for stiffeners and corners (as per drawing). Clearance and stopper removal. Check completion of coil guide support. Spring supports for Risers and Down comers Check for proper support (Type) with tag nos. Check for expansion clearance and movement and cleats. Check for removal of temporary supports. De-locking. Casing : Seal welding inspection and leak test acceptance. Cleaning inside casing and inspection, Box-up manholes, hand – holes, inspection doors, peep holes, hopper slide gates, etc., with proper gaskets and hardware (with spring washers if required). Plug / blind additional / temporary instrument tapping point openings. Piping : Clearance for insulation. Clearance for Thermal expansion. Cleaning / Flushing before installation of on-line instruments (like Control Valve, Flow element, Pressure Indicators.) Page 5 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) • • • 2. • 6. 7. STRUCTURE MECHANICAL AUXILIARIES • • • • • • • • • • 1. • • • • 2. • • • • • • • • • • • 3. • • • • • • Commissioning Procedure | WHRB Availability of vents and drains and its plugs (wherever applicable). Box-up with proper Gasket and hardware. Orifice – installation check :• Orientation of taping. • Provision of orifice plate in proper direction. • Jack bolts. • Attemperator spray water nozzle check. Pipe Supports : Installation checks of all supports with respect to final drawing and data sheets for type, expansion clearance, anchoring etc. Removal of temporary supports. De-locking of spring supports. Pointers to measure expansion. Foundation bolts tightening. Final grouting. Provision of brazing as per drawing. Proper hand – railing and its rigidity. Finishing and flushing of welding joints. Access to valves, manholes, inspection doors etc. Toe guards and closing of opening on platform. Check tightness of all hardware (if provided). SAFETY VALVES : Clean and obstruction free inlet and outlet nozzle and piping. Check name plate detail with respect to data sheet. Supporting and drain line of outlet piping. Availability of test gag tool. DEAERATOR: Check installation with respect to P & I diagram. Open manhole and check all internals, welding, supporting and orientation of nozzle Sparger pipes. Clean the tank, any plugging of nozzles. Checks spray nozzles and orientation. Accessibility for instruments and manhole. Insulation clearance. Supporting of instruments & impulse line. Expansion feasibility (provide scale on sliding saddle). Fixed saddle should have firm bolting. Nozzles are free from piping stresses. Proper gaskets and hardware for connections and manholes. DOSING SYSTEMS (LP/ HP): Check as per P & ID. No load trails of motor / direction / agitator trail run. Pump alignment, foundation bolt tightening. Strainer. Cleaning and flushing of unit. PRV setting. Page 6 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) • • • 4. • • • • Metering & discharge quantity measures. Start Up Procedure. Snubber & diaphragm for PI. EXPANSION BELLOWS : Dimensional checks. Joints / fastener as per drawing. Tightening of bolts. Removal of transportation lock, and check again for dimension. • Refractory / ceramic lining / bolster installation (If provided / if applicable) check. • Record and mark cold condition and verify with hot condition marking. 5. BOILER FEED WATER PUMPS: • O & M manual of BFW pump should be studied before installation and commissioning of pump. Installation, start up and shut down procedure should be strictly followed. • Check foundation provided is as per foundation drawing. • Check actual pipe routing and installation (NRV, isolation valves) with respect to final piping drawing, and in case of deviation, get approval from design dept. for piping stress analysis. • During pre-commissioning and line flushing, there is a possibility of strainer chocking due to the mill scale and particles left in the pipe. So the discharge pressure gauge and DP gauge across the strainer (if provided) should be closely monitored to detect the choking of the suction strainer. The strainer may have to be cleaned several times before the suction line is fully flushed. • Check strainer size with respect to Strainer spec / and for crack or puncher. • Ensure that the suction and discharge pipe is thoroughly flushed and cleaned before hook up with pump for operation. • Proper flushing of cooling water inlet and outlet pipes to pump. • Ensure proper quality and adequate quantity of cooling water to the pump. • Check for pump alignment as per pump O & M. • Check for direction of rotation. • Ensure pump is primed and free from air and vapor before starting. • Suction valve must be fully open. Keep discharge valve closed before starting the pump and open the valve gradually as soon as pump is started. • Check functioning have and hook up of extra low-level switch in suction vessel before commissioning of pump. This is to trip the pump in case of level low. • Check feed water quality as per spec. Commissioning Procedure | WHRB Page 7 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) 8. E&I AUXILIARIES Commissioning Procedure | WHRB • • 1. • • • Checks pump O & M for specific installation details. Check the no load and over load current of pump. Field Instruments Check instruments with data sheets / parts catalogues. Calibration. Proper isolation, snubbers, siphons (for PI’s) wherever required. • Installation as per hook up diagram. • Box-up with proper gaskets and hardware. • Mounting and supporting. • Access with platform. • Immersion length (U) and insertion contact for Temperature sensors. • All spare cable entries to be plugged. 2. Control Valves • Check instruments with data sheets / parts catalogues. • Flow direction and air fail condition. • Pneumatic testing of tubing. • Box-up with proper gaskets and hardware, properly greased. • Check condition of tubing, Air Filter Regulators and Pressure Indicators. • Protect diaphragm vent from foreign particles and moisture. • Stroke checking, action check (direct / reverse). • Safety interlocks checking. 3. Transmitters : • Check instruments with data sheets / parts catalogues. • Installation checks with respect to hook-up diagram and supporting of tubing, condensate pots and transmitter. • Hydro test of impulse lines. • Power supply cabling, gland and ferrule fixing. • Plugs for open ends (drains, flushing connection etc.) • Calibration and configuration check. • Continuity checking and loop checking. 4. MCC Panel : • Cabling check with respect to Cable Schedule, wiring diagrams. • Installation checks for rigidity of mounting and weather and dust protection. • Earthling. • Meager check. • O/L relay setting. • Local push button – accessibility. • No-load trail, Motor direction of rotation. • Avoid crossing of power and signal cable. • Ensure proper ferruling and tagging foe easy identity. • Ensure proper lugs are provided and crimped. • Check for proper tightness of termination. Page 8 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) 9. INPUTS REQUIRED TO BE COMPLETED BEFORE COMMISSIONIN G (TBWES & Customer scope Of work) 11 GENERAL AND SAFETY (Customer Scope) Commissioning Procedure | WHRB 5. Control Panel : • Cabling check with respect to Cable Schedule, wiring diagram. • Installation check for rigidity of mounting. • Earthling. • Logic check / simulation. • UPS hook – up and trial run. 6. Lighting (Customer scope): • Location of fixture as per layout drawing. • Cabling as per Cable Schedule • Installation of lighting distribution board. • Protection area. 7. Motors. • Proper installation. • Cabling check. • No load and load trials. • Statutory formalities and approval. • Pre-commissioning check of items in customer’s scope. • Availability of adequate feed water. • Availability of required quantity of all utilities. • Availability of dosing, alkali boil-out and preservation chemicals (if required). • Obtaining periodical sampling and water analysis. • Overall operation of Boiler and logging readings. • DCS commissioning and fine tuning of instruments. • Availability and management of input parameters of flue gas. • Availability of Boiler operators and BOEs. • Availability of communication devices. • Interfacing with mother plant (Cement Kiln control room) operation. • First fill lubricants and greasing. • Greasing of all bolt and nuts. • Manpower and resource requirement & shift arrangement for commissioning and operation. • Pre-commissioning checks. • Pre-commissioning and Commissioning procedures. • Preparation of Start Up Procedures If required • Loop checking. • Safety interlocks checking. • Inspection during commissioning. • Personal Protective Equipment. • Safety gear at different locations. • Plant illumination. • General housekeeping. Page 9 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) THERMAL EXPANSION DIAGRAM Expansion Tramp quantity required (will be decided by commissioning engineer during commissioning). Pointer holders to be fixed / welded on boiler part. Pointer is set move freely inside the holder. Reference plate shall be fixed to a non-moving permanent boiler structure as available nearby. These tramps are preferably fixed in presence of commissioning engineer, just before the commissioning of boilers. 15 NB Pipe SCH 40 Length: 50 mm M.S. FLAT PLATE 50 x(>500*)x3 mm Pointer: M.S. Rod Dia. 12 mm & 150 mm long This needs to be welded to boiler part : Drums/ sidewall peephole box M.S. Plate Dimension: 100 X 100 X 10 This plate has to be firmly supported from platform / permanent structure Commissioning Procedure | WHRB Page 10 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) 3. FLUSHING OF BOILER, PIPING AND VESSELS OBJECTIVE The purpose of carrying out flushing is to remove foreign matter, mill scale dirt etc. resulting out of manufacturing, storing, fabrication & erection from boiler, vessels & piping. Such deposits in the piping walls sometimes restrict flow through the pipes/tubes causing, overheating and pressure/flow fluctuations and even failures. PRE-REQUISITES In order to commence flushing following prerequisites / inputs have to be made available: ♦ Flushing will be carried out with DM water @ ambient temperature with pH of 8.5 preferably at 6-kg/cm2 (g) pressure. ♦ Mechanical completion of piping including supports to be flushed. ♦ Identify the system to be flushed e.g. flushing is carried out for steam, feed water and drain piping & economiser assembly and mark the flushing circuits on P & IDs etc. commissioning engineer will identify the piping system/circuit to be flushed during site visit. ♦ Check for adequate illumination and personnel safety in and around the piping flushing area. ♦ Check for adequate supports and expansion loops, as per piping drawings. Supports are to be completed before beginning of flushing activity. If temporary supports are required, they should be provided, as reactive forces resulting from flushing/blowing off media, are more than normal conditions. ♦ Completion of line flushing up to the battery limit. ♦ Check for flushing media isolating valve in good working order. ♦ Remove all strainers (if provided), NRV plugs (except the main steam line) /internals, control valves (provide spool pieces in place PCV/FCV, orifice plate / Flow nozzle). ♦ Connect flushing media to the starting point of piping. ♦ Isolate / remove instruments e.g. pressure gauges, pressure switches, flow meters. ♦ Cordon off the area where flushing is to be done and preferably post a person for vigilance. As a safety measure, install signboards of caution. PROCEDURE ♦ Ensure that flushing media to the starting point of piping is connected. ♦ Ensure that flushing media isolating valve in good working condition. ♦ Remove all strainers, NRV plugs/internals, control valves (provide spool pieces in place Pressure Control Valve/Flow Control Valve, Orifice plate / Flow nozzle. ♦ Isolate/remove instruments e.g. temperature gauges, pressure switches, flow meters. ♦ Cordon off the area where flushing is to be done and preferably post a person for vigilance. As a safety measure, install signboards of caution to working personnel. Commissioning Procedure | WHRB Page 11 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) ♦ Piping will be flushed with DM water @ Ambient Temperature with pH of 8.5 by installing a temporary flushing pump and a loop connecting to deaerator. Slowly open the isolating valve of the flushing media, allow the piping circuit to fill and allow muck, etc. to get removed. Then continuous or intermittent flushing can be carried out at the specified pressure. Intermittent quick opening and shutting off isolating valves will help in clear off loose mill scales, silica and dirt with shocks. Once clear media comes out of the final point of the circuit flushing can be stopped. ♦ Instrument air lines shall be flushed with Air only. ♦ After completing the flushing activities, Replace control valves, strainers etc., which had been removed during the flushing operation. SAFETY PRECAUTIONS ♦ Clear out/cordon off the area where flushing is being carried out as live pressurized steam will flush off through the system end point. ♦ Please make available plenty of safety gear e.g. asbestos hand gloves, ear mufflers, transparent eye protective goggles and first aid kit. Note: - If control valves/isolating valves to be kept in on line position, while steam flushing, keep their position to 100% open to avoid damage to seat of the valves or accumulation of dirt. Commissioning Procedure | WHRB Page 12 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) 4. TRIAL OF AUXILIARIES / EQUIPMENT’S OBJECTIVE Boiler auxiliaries trials are conducted for equipment like motors, feed water pumps, etc. PRE-REQUISITES Ensure the availability of instruction manual for different auxiliaries from their respective manufacturers. It is essential that the persons conducting trials of auxiliaries must go through the manufacturer’s instruction manuals, before starting any work. Ensure complete erection of equipment is over and complete the pre-commissioning checks as per equipment supplier’s recommendations, quality plan / drawing details. Ensure the driven equipment and the prime mover/driving equipment is released for testing / conducting trial run. Ensure that no load trial has been completed for prime mover / driving equipment and is cleared for auxiliary trial run. Ensure the availability of concerned inspection authorities and ensure the availability of calibrated instruments for recording the relevant data. DESCRIPTION Run the equipment/auxiliary at specified conditions for specified number of hours as per equipment supplier's recommendations, and record the parameters. Check whether actual site parameters, are matching with the design parameters. Note deviations if any, for reference towards corrective action (refer supplier's instruction manual for corrective action). Release the equipment/auxiliary for continuous operation. Note: Approach TBWES commissioning engineer, available at site for any clarifications on the trials. During the trial runs record all relevant data in specified formats available with TBWES Commissioning engineers. Commissioning Procedure | WHRB Page 13 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) 5. REFRACTORY DRY OUT & ALKALI BOIL OUT A. INPUTS REQUIRED FROM CUSTOMER Sr.No Description 1. Boiler feed water 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. Power supply for all drives UPS for control room Operator - Field Panel Communication arrangement (Walkie Talkie & telephone etc) Manpower / Operating staff. Mechanical Engineer & E & I Engineer Illumination of Boiler and surroundings. Water analysis laboratory Chemicals for normal Boiler water treatment (for LP & HP Dosing units) Instrument air & cooling water Assistance of Mechanical & Electrical maintenance dept. Operational spares First aid 550 m3 (For flushing, ABO and Rinsing) Quantity Required Remarks Quality as specified in the O & M manual. As required As required 6 (2 per shift) 3 (1 per shift) 4 nos. 8 hours shift Field & control room 3 each (8 hrs/shift) + 1 reliever As required As required As required As required As and when required As required As required 2. Alkali Boil-out Chemicals Sr.No 1. 2. 3. Description Hydrous Tri - Sodium Phosphate – 4600 ppm Na3PO4 12H2O An hydrous Di - Sodium Phosphate – 1000 ppm Na2HPO4 Wetting agent (non - foaming detergent ) Commissioning Procedure | WHRB Quantity (In Kg) 90 20 5 Page 14 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) B. CHECKLIST PRIOR TO ALKALI BOIL OUT ACTIVITY Status of Comp. DESCRIPTION OF ACTIVITY a) PRE – ALKALI BOIL OUT (ABO) CHECKLIST: 1. Ensure all the Pre-commissioning checks are completed. Complete trial runs and ensure proper operation of all the accessories. Sign out all the necessary protocols. 2. Install all the Pressure, Temperature and Level Instruments / local indicators for the complete system. Mark or explain to the operator regarding the LG for % levels with permanent marker for the sake of clarity. 3. Complete hydro test for all the Boiler parts and piping, light penetration test for the flue gas path if applicable, and thorough flushing with Boiler quality water for all Boiler pressure parts & piping. Sign out the necessary protocols. 4. Ensure availability of required quantity of DM water, uninterrupted power supply (UPS), Power supply for all drives and proper area & plant illumination. 5. Ensure availability of Utilities like cooling water for sample cooler & Blow down tank, Instrument air for Control valves, plant air (if applicable), etc. 6. Ensure availability of sample bottles & water analysis laboratory at site. 7. Ensure availability of experienced operators (3 per shift) round the clock. Decide on manpower planning and individual responsibilities required from all related agencies. Give adequate training on the commissioning activities to all concerned. 8. Necessary communication devices to be made available. Decide on the mode of usage. All concerned should be familiar with its usage. 9. Ensure availability of drain and vent system from various parts of Boiler and their routing to trench / safe location. Decide and determine the mode of disposal of water after Alkali Boil Out. 10. Check the sparger pipe holes for chocking, if required remove the sparger pipes for thorough flushing and re-fix the same after flushing. Check whether the orientation of sparger pipes and its supporting are OK. Clean the steam drum thoroughly and carryout joint inspection. Firmly box-up the steam drum manhole with new gaskets. 11. Ensure that the flow orifice at steam piping is not installed as the same will be installed after completion of steam blowing. 12. Make ready the temporary chemical charging tank & keep ready near the steam drum so that chemical for Alkali Boil Out (ABO) can be charged in to the steam drum. 13. Ensure availability of required chemicals and solution tank for mixing of chemicals for the ABO. Ensure availability of adequate quantity of personnel protection equipment (PPE’s) required for chemical charging. 14. Box up all the manholes in the flue gas path after joint internal inspection. Sign out the necessary protocols. 15. Check freeness of operation of bypass damper and flue gas isolation damper & Air dilution damper. Mark the damper position externally with respect to inside Commissioning Procedure | WHRB Page 15 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) configuration (whether open / close). 16. Insulation of Boiler casing, steam drum, and necessary ducting should be completed. Provide personal protection guards for hot areas where insulation is not feasible. 17. Ensure installation of expansion pointers for measurement of Boiler thermal expansion. Mark the pointer location in cold condition. Ensure that the delocking for spring supports is done and mark location of cold load setting. 18. Ensure that all transportation clamps / cleats of fabric and metallic expansion joints are removed. 19. One of the drum transmitters for pressure, levels on the steam drum and feed water piping instruments can be kept on line. Ensure and confirm whether all the necessary safety interlocks are implemented and tested for reliable operation. One of the level gauges can be kept on line for cross checking. 20. The following equipment’s should be made operational • Feed water control valves • Isolation valves in the Feed water line in the feed water control station on the BFW pump discharge • Isolation valve on start up vent line • Main steam stop valve on the main steam piping 21. Take all the Instruments in the flue gas path on line and check for proper indications on DCS panel. Ensure operation of all control / shut off valves as listed above is made available from DCS. 22. Ensure that the HP dosing unit is ready so that the same can be taken on line. Chemicals for HP dosing can be prepared just before taking the unit on line. 23. All necessary parameters to be logged periodically in the log sheet enclosed for along with this procedure. Also important events to be recorded. 24. Ensure Flue gas isolation damper at the Boiler inlet is made operational from local & also from the DCS. Commissioning Procedure | WHRB Page 16 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) b) POSITION OF VALVES BEFORE COMMENCING OF ABO: 1. All root valves on the Instrument tapping in the steam drum to be kept isolated except for the following items • One of the level indicators on the steam drum. • Pressure indicator on the steam drum. • One of the level gauges can be kept on line for cross checking. 2. The Steam drum vents valves to be kept open. 3. The entire instruments in the flue gas path should be on line. 4. Keep all the drain valves on the SH & MSL piping in open condition. 5. Isolate the Main Steam Stop Valve on SH outlet piping and keep the isolation valves on start up vent piping open. 6. Isolate valves on HP dosing skid. 7. Also keep the CBD line isolation valves and in closed condition. 8. All isolation valves of the sample cooler on the boiler feed water line, on the main steam piping, on the CBD piping to be kept in closed position. 9. All sample coolers cooling water isolation valves at inlet & outlet should be in open condition. Ensure that there is enough water flow. PROCEDURE FOR ALKALI BOIL OUT Sr. No. a. Description of Activities Water filling in the boiler: 1. Gradually charge Boiler feed water in boiler through feed water lines. 2. Water will get in to the steam drum and flow through the down comers to evaporator modules. 3. Fill water up to minimum visible level in the steam drum. Ensure steam drum vent is in open position. 4. Keep the chemicals and the solution tank near steam drum. b. Pre – Requests: 1. Isolate all the pressure and level instruments from the system. Only the drum pressure gauge and level transmitter will be in line. 2. Ensure the chemical mixing tank is ready. 3. Ensure the entire super heater vents, start up vent & MSL drain are in open condition. c. Commencing Refractory Dry Out: 1. During refractory dry out process, the bypass damper will be in fully open condition. If required the same can be closed partially or fully according to the requirement of process. 2. During refractory dry out and Chemical Boil out period the flue gas intake will be controlled according to the requirement only. 3. Gradually allow the flue gas to enter in to the WHRB to raise the flue gas temperature Commissioning Procedure | WHRB Page 17 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) Sr. No. Description of Activities at WHRB inlet @ 25 Deg C/Hour to 100 to 120 Deg C. During initial startup temperature controlling is difficult; however try to maintain the rate of increase as specified. During this initial time the bypass damper will also be in open condition. Continue to maintain the flue gas temperature at WHRB inlet duct between 100 to 120°C for 24 Hours. This is to drive out all the moisture present the refractory. d. Chemical charging: 1. At the end of this 100 to 120 °C cycle, stop the flue gas intake by closing the inlet damper. 2. Prepare chemical solution and charge into the steam drum through the drum manhole. After the chemical charging close the drum manhole. 3. Start the flue gas intake by opening the flue gas inlet damper. Monitor the WHRB inlet temperature & gradually increase the flue gas intake in order to maintain temperature as required. e. Warming-up of water and raising the steam drum pressure: 1. Increase flue gas intake and raise the flue gas temperature at boiler inlet duct @ 25 Deg C/Hour to 300 Deg C. Maintain the temperature for 8 Hours. 2. As the flue gas temperature is increased, steam will start coming from steam drum vents and through super heater (S.H) drains. When steam drum pressure raises above 2 kg/cm2 (g) close steam drum vents. When drain is removed completely close the superheater & main steam drain valve. Now, steam will be coming from start-up vent on S.H outlet piping. Partially close the valve on start-up vent valve and keep it throttled. 3. Maintain the steam drum level between 45% to 55% constantly. Drum level need to be maintained manually. Adjust the flue gas damper opening so as to raise the steam drum pressure gradually as per the startup curve enclosed. Maintain the flue gas temperature (at boiler inlet) at 300 Deg C for a period of 8 hours. 4. Open the CBD valve for few seconds in every 4 hours to avoid line blockage. 5. As the HP steam drum pressure reaches at ~ 9 Kg/cm2 (g), take sample from CBD sample cooler point and analyze for pH, Conductivity/TDS, Phosphate, Fe2O3, oil content. 6. The steam generated is circulated through S.H and vented out through start up vent. By adjusting the opening of start up vent valve, maintain the steam drum pressure at around 9 kg/cm2 (g). f. Alkali Boil Out: 1. Along with maintaining the flue gas temperature, maintain the steam drum pressure to around 9 kg/cm2 (g). Effective alkali boil out (internal cleaning of boiler) commences. Hold the pressure for 12 hours (min.). Take sample from CBD once in 2 hours. 2. The effectiveness of alkali boil out will be identified by change in phosphate ppm and Oil and Fe2O3 content from the initial value. The phosphate will be consumed to remove oil/grease and loose iron particles. Commissioning Procedure | WHRB Page 18 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) Sr. No. Description of Activities 3. At the end of this procedure, the phosphate, oil level will stabilize and there is some residual phosphate level which indicates completion of boil out. With the result of the phosphate stability, we can declare the process is completed. 4. When the HP boiler pressure is around 9 kg/cm2(g) note down the boiler expansion readings. Measure and mark the boiler locations in hot condition. Also observe and mark the location of hot condition for spring supports. g. Completion of Alkali Boil Out and carry out on line flushing 1. After completion of ABO close the damper, box up the WHRB and allow the unit to cool by natural cooling. 2. When the drum pressure drops to 2-kg/cm2 (g), open the start up vent and drum air vent 3. At the above pressure take a blow down from the blowdown valves one by one for not more than 10 seconds per drain valve. While this is being done it must always be ensured that the drum level does not fall below the normal working level and the water level is always visible in the level gauge. If the steam drum level drops substantially stop draining at once and maintain drum level as specified (45 to 55%). 4. Keep the valve on CBD line in open position and carry out on line flushing. Replenish with fresh boiler feed water and keep close watch to maintain the steam drum level. 5. Rinsing is done until feed water pH is in close proximity with drain water sample’s pH. When the drum pressure drops to atmospheric, start draining the boiler slowly and in the meantime make up the level with feed water. Stop rinsing when the drain water sample pH is in close proximity with the inlet feed water pH. 6. Dilute the blow down tank content with water and divert the solution to a predetermined safe location. 7. After rinsing Open the steam drum manholes and remove the sediments (if any). 8. Protocol for Alkali Boil out will be jointly signed by customer & TBWES representative. h. Cooling down and inspection: 1. Drain water from boiler. Open steam drum manhole. Open all the manholes in boiler inlet duct / casing. 2. Carry out joint inspection of steam drum inside and the boiler inlet duct refractory lining. Also check the condition of S.H and Evaporator supporting arrangement. 3. Clean the steam drum thoroughly. Flush the Blow down piping / de choking (if any). i. Reinstating: 1. Results of water samples collected after alkali boil-out and rinsing is analyzed for following : a) Stable phosphate (min 50ppm) and oil content & Fe2O3 level at the end of alkali boil-out, b) No traces of oil content at the end of flushing procedure after the end of alkali boil-out (oil content < 5 ppm is acceptable in the boiler water after boil out). 2. Thoroughly check for cleanliness and stability of steam drum internals. Flush and Commissioning Procedure | WHRB Page 19 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) Sr. No. Description of Activities clean (if required) the steam drum nozzles. 3. After complete cleaning box-up steam drum manholes with proper gasket. 4. Flush the drum level gauge glass after alkali boil out. REFRACTORY DRY OUT AND ALKALI BOIL OUT CURVE Not To Scale Commissioning Procedure | WHRB Page 20 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) 6. STEAM BLOWING OF MAIN STEAM PIPING INPUTS REQUIRED FROM CUSTOMER: Sr.no Description Quantity Required 1 Boiler feed water 2 Power supply for all drives As Required 3 UPS for control room As Required 5 Operator - Field 6 (2 per shift) Panel 7 Communication arrangement (Walkie Talkie & telephone etc) 8 Manpower for operating staff. Mechanical Engineer Approx. 450 m3 for steam blowing 3 (1 per shift) 4 nos. Remarks Quality as specified in the O & M manual. 8 hours shift Field & control room 3 each (8 hrs/shift) + 1 reliever E & I Engineer 9 Illumination of Boiler and surroundings. As Required 10 Water analysis laboratory As Required 11 Dust handling from the Conveyor As Required 12 Chemicals for normal Boiler water treatment(for HP & LP Dosing units) As Required 13 Instrument air & cooling water As Required 14 Assistance of Mechanical & Electrical maintenance dept. As and when required 15 Operational spares As Required 16 First aid As Required Commissioning Procedure | WHRB Page 21 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) PROCEDURE FOR STEAM BLOWING A. Pre-requisites : Status of 1. Alkali boil out activity is successfully completed and inspection is completion satisfactory. Boiler is reinstated for further activities. 2. DCS should be completely operational. Necessary communication devices for co-ordination with commissioning engineers are available. 3. Steam piping to be mechanically completed. All pre-commissioning checks shall be checked and satisfied by commissioning team. 4. Ensure that all pipe supports are provided and welded as per drawing. 5. Do not carry out insulation for superheated steam piping. 6. Commission all the instruments in flue gas path. Check and certify for loop checking and stroke checking of all instruments on waterside. 7. Take all the instruments on Boiler feed piping, evaporator, super heater and steam drum on line. 8. Line up De-aerator level control and fill water in steam drum up to 50% level through feed water line. Carry out on line checking of steam drum level control and safety interlocks in waterside. 9. Line up spray water piping to attemperator and complete loop checking. 10. Do not install flow nozzle on Main (Super Heater) steam piping. 11. Mark the sliding supports for cold position for measuring thermal expansion of steam piping. 12. Disconnect main steam piping from common header and provide temporary piping arrangement (with less bends) to safe location as shown in steam blowing arrangement. Firmly support the piping. Keep necessary hardware and gaskets for temporary piping ready. 13. Install sacrificing valve as shown in steam blowing arrangement diagram. 14. Fix the target plate holding assembly as shown in the steam blowing diagram. 15. Provide anchor support very close to steam blowing point(s) to take care of sudden / abnormal variation in piping stresses during blowing. These supports need to be removed after successful completion of steam blowing. 16. Keep sufficient target plates (Aluminium & SS). 17. Record all important parameters in the log sheet (prepared for steam blowing) periodically. 18. Take all measures for safe blowing. Carry out steam blowing only during day, when daylight is available. 19. All the instruments in boiler and steam piping shall be taken for operation except steam flow measurement. Commissioning Procedure | WHRB Page 22 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) B Valve positions: 1. Keep main steam stop valve on main superheated steam piping closed. 2. Keep CBD valves in crack open position. 3. Line up H.P. Dosing unit and keep its isolation valve near steam drum open along with the respective valves in dosing unit. 4. All drain valves in evaporator to be kept closed. 5. All drain and vent valves in super-heater to be kept open. 6. Keep the isolation valves on upstream of steam trap closed and open the bypass valves. Steam Traps (if any) should be fitted after completing the steam blowing. 7. All the control valves circuit will be operational. 8. Position of other valves to be as specified in the boiler start-up procedure. C Boiler start up and warming up of steam piping : 1. Follow Boiler start up procedure mentioned in start-up procedure (O&M Manual). 2. Ensure the availability of flue gas from the Cement kiln. 3. Then start the boiler as per the startup procedure. 4. As steam comes out continuously from steam drum puppy header vent and steam drum pressure rises to 2 kg/cm2 (g), close the same. Allow the steam to vent through start up vent valve. 5. Maintain flue gas temperature at boiler inlet less than 300°C until the steam starts flowing through the super heater and the boiler pressure raises up to 5 kg/cm2(g) min. 6. Maintain steam drum water level at 50% +/- 5%. 7. Check auto operation of the (Attemperator control) and take it on line. Set TCV on auto mode for super heater steam temperature. 8. Increase flue gas temperature and gradually raise the steam drum pressure as per the boiler pressure raising curve up to 8 Kg/cm2(g). Maintain the steam drum pressure by throttling the start up vent valve. 9. Closely watch superheated steam temperature. This should not be allowed to exceed beyond rated temperature by de-superheating and adjusting the steam flow through start up vent. D Steam blowing of main steam piping: 1. Ensure all the pre-requisites are completed. 2. Ensure the operation of the MSSV in remote mode. And keep the valve in closed condition. 3. Ensure operation of sacrificing valve. 4. Gradually open the by-pass valve of the Main steam stop valve and allow the steam to warm up the main steam piping. Ensure no steam is coming out from the drains points. 5. Initially, the steam blowing cycle (i.e. releasing the pressure) is done Commissioning Procedure | WHRB Page 23 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) slowly to watch carefully for the thermal expansion while releasing the pressure. In case of any abnormal noise / restriction for thermal expansion close the valve and open the start up vent. Implement remedial measures. Repeat the exercise and confirm integrity. For the initial blow maintain the drum pressure at 8 kg/cm2(g). 6. After warming up the line throttle the start-up vent valve and simultaneously open the main steam stop valve and maintain steam drum pressure at 8 kg/cm2(g). 7. Just before blowing drop the steam drum level to ~35 % and close the attemperation spray water to avoid carry over. 8. Ensure there is no condensation in the line & dry steam is coming out through all the drains and from the main steam piping. 9. Open sacrificing valve and close start up vent valve. Drop steam pressure up to 5 kg/cm2 (G). This is the 1st blowing cycle. Stop blowing by closing the sacrificing valve and opening startup vent simultaneously. MSSV to be closed afterwards. 10. Whenever the steam drum pressure is relieved suddenly, the steam drum level will shoot up which happens by swelling as the steam drum pressure drops. This is false indication of level and a momentary phenomenon. Subsequently the level will drop. Hence allow feed water flow gradually to make up the steam relieved. 11. Check the condition of main steam piping supports. If required rectify the supports and proceed for the second cycle. Ensure all the supports are in good condition. 12. Leave sufficient interval (~ 2 to 3 hours) in between steam blowing cycle so that the main steam piping cools down i.e., pipe skin temperature should drop at least by 100 Deg C. 13. Initially, the steam blowing cycle (i.e. releasing the pressure) is done slowly to watch carefully for any abnormal noise/ thermal expansion while releasing the pressure. Implement remedial measures to avoid any abnormalities. Once this is ensured the steam blowing (releasing the pressure) can be done suddenly, which will flush the pipe effectively. 14. Closely watch the steam drum level in the field as well as in DCS. Monitor piping support. 15. As the drum pressure drops to 5 kg/cm2(g), close sacrificing valve and keep start-up vent valve in throttled position and raise drum pressure again to 14 kg/cm2(g). Maintain drum level at 50% +/- 5%. 16. Repeat the above steam blowing exercise several times as long as you could visually observe the steam blowing is clear. 17. Now, isolate sacrificing valve and insert soft metal target plate in the target plate holder provided for temporary piping. Raise steam drum pressure to 14 kg/cm2 (g). Repeat the blowing one time with the target plate. Close sacrificing valve and remove target plate. If target plate is not clean, repeat steam-blowing cycle for 4 to 5 times without target plate. Subsequently, soft metal target plate can be inserted and checked. 18. Target plate will be checked as per the acceptance criteria. Up on Commissioning Procedure | WHRB Page 24 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) acceptance, the steam blowing is said to be completed. 19. Remove temporary piping and supports provided for steam blowing. Reinstate the main steam piping. 20. Now the flow nozzle can be installed. Note: Please read this document along with the following documents: 1. Pressure raising curve. 2. Acceptance criteria for target plate after steam blowing. 3. List of inputs required from TBWES and Customer. 4. Log sheet for recording parameters during steam blowing. 5. P&ID Drawing. 6. Steam blowing scheme along with the sketches. Commissioning Procedure | WHRB Page 25 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) PRESSURE RAISING CURVE Commissioning Procedure | WHRB Page 26 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) SKETCH FOR STEAM BLOWING ARRANGEMENT Commissioning Procedure | WHRB Page 27 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) ACCEPTANCE CRITERIA FOR STEAM BLOWING It is recommended to install the target plate after completing few blows of the critical pipelines without the target plate. For evaluating the cleanliness and termination point of the steam blowing, target plate of aluminum / stainless steel is to be used. Indications for the result of each blowing period are the number of pitting found on the target plate. The highest velocity of steam is in the center of the pipe. Hence judgment should be made for the end point of steam blowing in the target plate area. The area for the above is 3/4th of the discharge pipe diameter at the center. The result of the blowing operation can be judged by the absolute number of pitting on the target plate in the central zone. The piping is considered clean if there are not more than 3 dents of 1 mm diameter in 1sq. cm area. Besides this there shall be no pitting in the rim zone and shall not have any deformed edges. Note: Protocol for steam blowing shall be jointly signed by TBWES and customer. Commissioning Procedure | WHRB Page 28 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) LOG SHEET FOR STEAM BLOWING: Date Cycle No. Before blowing Time Steam SH steam Drum temp. pressure Commissioning Procedure | WHRB After blowing Time Steam SH steam Drum temp. pressure Target plate fitted Y/N Observation / Remarks Page 29 PROJECT: M/s Ultra Tech Rajashree Cement, Karnataka (PL 1862) 7. SAFETY VALVE SETTING OBJECTIVE The objective of this procedure is to outline the procedures involved in setting the safety valves to the designed set pressures before allowing the boiler to go for commercial steaming. PRE - REQUISITES Ensure proper mounting of the safety valve exhaust pipe, such that no load is coming to the safety valves. Follow instructions of vendor for safety valve exhaust piping support. Check for the proper opening and closing of the start-up vent. Ensure the drain of main steam line is kept open. Close all other vents and drains. Normally the highest set pressure valve is floated first (i.e. drum safety valve) While setting this valve the other drum safety valve and the safety valve on the super heater outlet line are gagged. PROCEDURE Start the boiler as per cold start up procedure on low fire. When the drum pressure reaches about 75% of operating pressure, gently tighten gags on one of the drums and main steam safety valves. Raise pressure slowly by throttling the start-up vent valve. When 80% of popping up pressure is reached manually operate the safety valve under test. This will blow off any debris or dust left over in the valve internals. Always maintain water level 50mm below normal level in the drum. Raise the boiler pressure by increasing the flue gas quantity. When the valve pops, reduce the gases and open start up vent valve. When the valve sits back, note down the pop up and re-set pressure. Restore drum level. The set pressure is adjusted by either tightening or loosening the adjusting nut (by reducing or increasing the spring tension). Tightening of the nut increases the set pressure and vice versa. Blow down which is the difference between set & reset pressure should normally be within 5% of the set pressure. In order to adjust the blow down notched rings (Nozzle ring and Guide ring) are provided near the seat of the safety valve. To increase the blow-down the blow-down ring is to be rotated towards left (lower the ring) to decrease the blow down the ring to be rotated vice versa. Note down the expansion reading and record in the protocol. REFERENCE Read carefully the supplier's O & M Manual before starting the activity and familiarize yourself with the components of the equipment A detailed description of the key features of safety valves is provided in the safety valve manual, compiled in operation & maintenance manual. NOTE ♦ All the procedures mentioned are guidelines for carrying out the boiler pre commissioning and commissioning activities. ♦ Due to various reasons there may be variations in the actual procedures followed at site and all the deviations to be jointly (by customer and TBWES) recorded in commissioning protocols deviation report for references. Commissioning Procedure | WHRB Page 30