MAIN TENDER REFERENCE NO - SRFT19080138 SECTION 14 : STANDBY GENERATING PLANT 14.1 General 14.1.1 Description a. This section of the Specification covers the design, supply, installation, testing, commissioning and setting to work of complete generating plant as shown and as specified herein. The standby generating system shall include, but not be limited to, the followings: (i) complete diesel engine/generator set including radiator, antivibration mountings, holding down bolts, etc.; (ii) complete exhaust system including all silencers, suspension and thermal insulation; (iii) complete fuel delivery system including a daily service tank, all pipes, valves, feed pump and pipe works where required and as specified on the Specification & Drawing; (iv) control panel complete with all accessories, monitoring auxiliaries contact and control, to provide a complete and operable system; (v) DC electric starting system. (vi) Complete generator control system complete with sensing cable, control cable, control auxiliaries control and cable supporting system. (vii) Acoustic Treatment b. The generating plant shall have provision for both manual and fully automatic starting facilities, and be capable of accepting the designed connected load in the event of a complete mains failure, and to do so in not more than 10 seconds. This is applicable to single or multiple generating plants. c. The generating plant shall be adequately sized to meet the load requirements under worst case considerations given on the specification and drawings. Details of the sizing shall be submitted for approval. The sizing of the generating plants shall consider, but not be limited to the following factors: (i) derating factors (altitude, ambient temperature, power factor, etc.); 14 - 1 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 (ii) impact load; (iii) transient voltage dip; (iv) momentary overload; (v) re-generative power; (vi) rectifier loads; (vii) phase loads unbalance; (viii) instability due to interaction between voltage regulation systems (e.g. AVRs of generating plants and UPSs); and (ix) a 10% overload capacity in excess of the nameplate continuous rating for one hour in any of twelve (12) consecutive hours of full load operation. Notwithstanding the above, the generating system shall have a minimum full continuous rating as indicated on the specification and drawings. 14.1.2 14.1.3 Particular Requirements on Quality Assurance a. The manufacture of various components and accessories shall be as recommended by the generator manufacturer to ensure compatibility of the components. b. Notwithstanding any description or detail (implied or otherwise) included hereafter and on the specification and drawings, the generating plant and the final installation shall comply with the statutory obligations, local requirements and Singapore Standard SS 535 c. The Contractor shall be responsible for co-ordination and guarantee of the overall performance of the generator, driver, gears and all auxiliaries. Submittals As a minimum, the following shall be submitted for approval at the appropriate stages of the Works: 14 - 2 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 a. detailed schedule of equipment and components and manufacturer's data, including fuel pipe insulation material, selection of engines, alternators, sizing of radiator, sizing of vibration isolators both for the engine as well as for the pipes hangers. b. general layout of the generator set, control panel, fuel tanks, pipework, exhaust outlets, etc. which is to be consistent with the size of the generator plantroom; c. detailed and co-ordinated working drawings on Generator Room equipment layout, with requirements on engine exhaust system, fuel supply system, cooling system; including calculations, pipe sizes, construction details, installation details; d. electrical control wiring diagrams showing details of all wirings internal and external to the generator control panel, together with terminal numbers for cable terminations to external equipment; e. detailed calculation on battery sizing; f. equipment weight; g. builder's works requirement; h. proposal on testing procedures and report format for testing of the generating set at the manufacturer's works and on site; i. torsional calculation from the supplier: j. site installation procedure and; k. testing and commissioning procedures l. generating plant / room airflow calculation l. current transformer CT selection calculation l. generator vibration mount / spring isolator calculation endorsed by Professional Engineer, 14 - 3 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 14.2 Product 14.2.1 General a. The generating plant shall comprise a diesel engine generator mounted on a common base skid and complete with factory supplied anti-vibration resilient mounting. c. All exposed moving parts, except manually operated controls, shall be totally enclosed or guarded to prevent contact by personnel. d. All exposed surfaces which are sufficiently hot to cause injury shall be adequately guarded. e. All exposed ferrous metal surface of the generating set, underframe and ancillary equipment shall, where applicable, be treated with rustproofing primer paint undercoat, with the finishing coat to manufacturer's standard. f. The following service conditions shall apply:(i) Ambient Temperature - Maximum design 40°C Minimum design 19°C g. (ii) Ambient air which may be salutiferous, with relative humidity of not less than 90% shall be taken into account. (iii) Altitude - 1000 metres or less above sea level . Electrical Characteristics (i) Normal System Voltage : 400 volts, 3 phase, 4 wire (ii) Frequency : 50 Hz (iii) System Neutral : Solidly ground (iv) Control Power : DC 24V 14 - 4 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 h. Diesel engine and generator shall be installed on a common baseplate as one assembly. i. The generator plant is normally at rest in a standby mode and is automatically started on failure of the utility system. It shall be suitable for continuous operation as an emergency power source. j. Basis of Rating k. 14.2.2 (i) The diesel engine generator set shall be rated on a continuous duty basis and the continuous rating shall be expressed in KVA available at the generator terminals at 0.8 power factor. (ii) The excitation shall be able to support 300% of full load current over 10 seconds. The rated voltage shall be 120% of generator field voltage required at rated output of the generator. The generating plant control panel shall be floor mounted type free from vibration of generator during operation. Diesel Engine a. Engine Performance and Type (i) The engine shall be rated for continuous operation and suitable for driving the electric alternator as specified hereinafter. The performance of the engine shall comply with SS 535 and BS ISO 3046-1. (ii) The engine shall also be capable of driving the alternator at 10% overload for a period of one (1) hour in accordance with the requirements of SS 535 and BS ISO 3046-1. (iii) The engine shall be direct injection, cold starting, water cooled, pressure lubricated, four stroke and single acting compressor ignition diesel engine conforming with the performance requirements of BS ISO 3046-1. (iv) The engine shall be suitable for running on diesel of BS 2869 Class A2 or equivalent. 14 - 5 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 (v) The engine shall be of the naturally aspirated type. (vi) The engine shall be rated for continuous duty to BS ISO 3046-1 and sized to match the continuous rating of the generator with overload capacity as specified hereafter. (vii) Engine crankshaft speed shall not exceed 1500 rpm. The normal direction of rotation shall be anti-clockwise. (viii) The engine shall comply with emission standards minimum of EU Stage II, US Tier II or Japan Tier I or better. NEA letter of compliances shall be submitted. (ix) Accessories mounted on the engine shall include but not limited to the following: Speed Governor Overspeed Trip Mechanism Hours Run Counter Tachometer Lubricating Oil Pump Exhaust Outlet, Oil and Water Thermometer Alarm System Oil Pressure Gauge Temperature Gauge 14 - 6 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 b. c. DC Electric Starting System (i) The generating set shall be equipped with an engine starter motor which shall be suitable for 24V DC operation, complete with manual and automatic starting and starter cut-out switch as described herein. (ii) The engine starting control equipment shall be arranged to disconnect the mains operated battery charger to prevent it being overloaded during starting. (iii) The starter motor shall be of adequate power for its duty and of "non-hold-on" type in which the piston is moved axially to engage with a gear-ring on the engine flywheel before the starter motor is fully energised. The pinion shall positively disengage when the engine starts or when the motor is deenergised. (iv) The starting equipment shall incorporate a fail-to-start device for automatically disconnecting the starter motor if the engine fails to start within a pre-determined time, say 15 seconds, so as to avoid undue discharge of the batteries. (v) A total of three (3) consecutive starts, say with 15 seconds duration, shall be made to start the engine, after which disconnection of the starter by the fail-to-start device shall operate the visual and audible alarm as specified hereafter. No further attempts shall be made to start the engine by the automatic starting system until the fail-to-start mechanism has been reset manually. Batteries and Chargers (i) A 24V DC engine starting battery set of nickel- cadmium type of adequate ampere hour capacity and discharge rate. The battery shall comply with BS EN 60623, IEC 60623 and be capable of providing three thirty second cranking time without recharging. The Contractor shall submit full calculation of the battery capacity for Engineer’s approval. The battery shall be housed in a corrosion resistant container of an approved type. (ii) The Contractor shall also supply, delivery and install a separate battery set of maintenance free nickel - cadmium type of adequate ampere hour capacity and discharge rate for the purpose of DC shunt trip and other protection circuits. The Contractor shall submit full calculation of the battery capacity for Engineer’s approval. 14 - 7 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 14.2.3 (iii) The battery charger shall be constant potential type, complete with DC voltmeter and ammeter, surge suppressor, controls, float and boost charging selection, battery discharging indication, protection against over-charging and indication and charger failure alarm. All controls and sensors shall be wired to the set control panel. (iv) The Contractor is to provide steel battery racks. They shall be painted with two coats of electrolytically resistant paint. The racks shall be properly arranged for easy maintenance and installation. (v) A battery disconnect switch mounted on a board/panel shall be provided and of which shall be capable of safely interrupting the short circuit current of the battery. Alternator a. b. Enclosure (i) The alternator shall comply with the requirements of BS 5000-3 and have dimensions and frame size in accordance with BS 5000-3. The housing shall be drip proof to IP 23 of BS EN 60947-1 screen protected and have axial flow forced air ventilation and rated to provide the nett output and overload capacity as specified. (ii) The alternator shall be built in with thermostatically controlled heater and with manual isolating switch at the control panel. Alternator Performance (i) The alternator must be capable of withstanding an overspeed of 20% above synchronous value for 2 minutes without mechanical damage or permanent distortion. Mechanical protection of the alternator against overspeed effects shall be provided by the engine overspeed protection devices specified. (ii) The alternator must be capable of withstanding an unbalance load with the current in one (1) phase more than the other phases by 60%. (iii) The alternator shall withstand three (3) phase short-circuit conditions without damage. Excitation shall be maintained under external short-circuit fault conditions to produce a short circuit current of three (3) times full load. The field shall be suppressed under internal fault conditions by direct field suppression on slip ring machines or by suppression of the excitor field on brushless machines. 14 - 8 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 (iv) Steady state voltage variations shall not exceed +1% from no load to full load. The alternator set shall be capable of supplying its rated KVA output at rated speed and power factor at voltages ranges from +2% to -2% at rated value. (v) The alternator set shall be capable of supplying its rated KVA output at rated voltage and power factor at frequency ranging from +2% to -2% at rated value. (vi) Its excitation system shall be designed to withstand a 10% overload for one (1) hour at rated voltage, speed and power factor without dangerous temperature rise. (vii) The alternator set shall be capable of withstanding for 15 seconds a current 50% in excess of its rated current with the field set for rated load excitation. (viii) The alternator set shall be capable of withstanding 150% of rated current at its terminals for 15 seconds without damage when operating at rated KVA and power factor with fixed excitation. The machine phase currents under fault conditions are such that the negative phase sequence current, (In) expressed in per unit of stator current at rated KVA, and the duration of the fault in seconds, t, are limited to values which given an integrated product. (In) x (In) x t equal to or less than 40. The maximum phase current is limited by external means to a value which does not exceed the maximum phase current obtained from a three-phase fault. (ix) The deviation factor of wave from of the open-circuit line-toline terminal voltage of alternator shall not exceed 0.1. (x) For sudden applied load conditions, recovery of stable condition shall start within ½ second and frequency regulation shall not exceed 2 Hz from no load to rated load. 14 - 9 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 c. d. Alternator Type (i) The alternator shall be brushless, self-exciting, selfregulating type, continuously rated to BS 5000-3. It shall have a conventional stator and salient pole revolving field system incorporating on a common shaft, the armature of the AC excitor and a three (3) phase full wave silicon diode main field rectifier. Each diode shall be provided with fuse protection. The alternator shall be self-excited from its output terminals through a static automatic voltage regulator. (ii) The windings shall be suitably insulated and impregnated for operation in tropical climates and adequately braced to withstand short circuit forces. The rotor shall be of the salient pole type with fully interconnected damper windings. The stator windings shall be star connected with neutral connections brought out and labelled A-B-C for phases and a-b-c for neutral ends. (iii) The alternator characteristics must be matched to the torque characteristics of the engine, in such a manner that with full load connected to the alternator, it can utilize all the available engine power without exceeding it. (iv) The stator windings shall be star connected with the neutral terminal brought out and solidly earthed. (v) Insulation to prevent shaft current flow shall be provided for the alternator. Insulation The rotor winding shall be Class F (155°C) and the stator and excitor windings shall be Class E (120°C) suitable for use in local condition/ climate. The stator and rotor windings of the alternator and excitor shall have oil, acid, moisture resistant Class F thermosetting insulating varnish with a final/heavy insulating coat of air drying and anti-tracking varnish. e. Bearings The alternator shall be fitted with heavy duty double ball or double roller bearings which shall be pre-packed with suitable lubricant for life. f. Automatic Voltage Regulator (i) A rapid response automatic voltage regulator shall be provided to regulate the generated voltage. 14 - 10 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 (ii) The voltage control unit shall be mounted in the control panel. Automatic voltage control if provided by a solid state unit shall have a frequency sensing device to prevent overloading of excitor components during under speed conditions. Manual voltage control with an auto/manual selector shall also be provided. The voltage regulator sensing device shall be a three (3) phase type and shall respond to average voltage output and not peak voltage output. Steady State Condition Under the steady state condition, the automatic voltage regulator or any other voltage stabilizing system shall be capable of maintaining the voltage to within +2.5% of its set value for all loads between no load and rated load, including cold to hot variations and load power factor between 0.8 lagging and unity. The load conditions shall also include out of balance loading of up to 10% between any two (2) phases. Following transient changes, the voltage shall be restored to within these limits in less than 10 seconds. Transient Condition The excitation system shall be designed to promote rapid voltage recovery following sudden application or disconnection of load. The voltage shall recover to within 2.5% of the steady state value within 0.3 second after the application or disconnection of load up to the rated load. Transient Voltage Rise The voltage shall be arranged to fall off with excessive reduction of engine speed. The transient voltage dip or rise upon the application or rejection of the load up to the rated load shall not exceed 20%. g. Radio Interference The whole of the equipment shall be efficiently protected against emission of electromagnetic interference. 14 - 11 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 h. Temperature Rise The temperature rise shall be in accordance with BS 5000-3 for the appropriate insulation Class in a 40°C ambient. i. Waveform The voltage waveform of the generating set shall be as close as practicable to a sine wave both at no load and at full load with a power factor of at least 0.8 lagging. The line to line voltage waveform shall be in accordance with BS 5000-3 and the total harmonic distortion shall not exceed 5%. Three (3) copies of oscillograms of the voltage waveform taken shall be provided. 14.2.4 Radiator a. The engine shall be water cooled by means of a matching heavy duty radiator complete with belt-driven fan, coolant pump, thermostat temperature control liquid-cooled exhaust manifolds, intercooler, coolant corrosion resistant filters suitably designed to suit the site conditions. b. The radiator shall be mounted on the same base skid supporting the generating set where a set mounted radiator is required. c. The radiator fan shall be suitably selected with sufficient fan static pressure to overcome pressure losses through the fresh air intake acoustic louver-wall, radiator, silencers, ducts, exhaust plenum box, exhaust tunnel and aluminum louver. The air flow quantity shall be sufficient for engine combustion, removal of heat generated by the complete generating set operating at full rated load and radiator cooling as recommended by the generating set manufacturer. d. The radiator shall be fitted with duct adapter flange to enable the ventilation ductwork to be attached to the radiator. A short section of ductwork shall be installed between the radiator and the metal louvres provided. Ductwork shall be constructed of galvanized steel sheets in accordance with SMACNA construction standards. Gauge of sheet metal of ductwork shall be in accordance with the recommendation of ASHRAE with G115 designation zinc coating to ASTM A653 / A653M-11. All ductworks shall have air-tight joints. e. The fan rating shall be adequate to allow for the additional resistance of airflow to the ductwork and louvres fitted. f. Corrosion inhibitor shall be added to the cooling system. 14 - 12 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 h. 14.2.5 14.2.6 Automatic shutdown of the generating set through overheating shall be incorporated. A visual audio indication shall be provided on the control panel to indicate the generating set has shut down due to overheating coolant. Status indication for radiator fan shall be provided at the control panel. Coupling Arrangement and Anti-Vibration Mountings a. The diesel engine shall be direct coupled to the alternator which shall be of the single or two bearing type. b. Anti-vibration units shall be mounted below the baseplate, or between the generating set assembly and the baseplate, so that the complete installation can be located on a solid concrete floor without transmitting vibration to adjacent apparatus or any part of the building. c. Vibration isolation equipment for the generating set shall comprise of unhoused steel springs in series with two (2) layers of 8mm thick, 40 durometer neoprene waffle pads and 63mm minimum total static deflection. d. A rigid base frame suitable for point mounting of isolators shall be provided. There shall be no rigid ties to the structure. All conduits and pipework are to be looped or flexible. Limit stops or restraint (out of contact during normal operation) are to be fitted to the base to limit transient movement during stops/starts. Exhaust Silencers and Fuel a. A residential type silencer shall be provided. The silencer shall be of chambered construction, complete with moisture trap, exhaust drain and adequately sized to assure proper operation without excessive back pressure when installed. The silencer shall be designed to reduce the emitted noise to a level of 70 dBA measured at a distance 1m from the exhaust outlet. b. Stainless steel flexible bellows connectors and adapter, sized to match the engine and exhaust silencer, shall be provided for installation between each engine and the associated silencer. c. A fuel pipe complete with flexible bellows connectors, all adequately sized, shall be connected beyond the silencer to discharge the fuel to the location as shown on the Specification & Drawings. d. Bends in fuel pipe shall have a minimum radius of three (3) times the diameter of the pipe. 14 - 13 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 14.2.7 14.2.8 14.2.9 e. The finish of all fuel pipework and silencers shall be aluminium cladding of not less than 0.6mm thickness. f. The entire system shall be supported by spring type hangers with an approved design. Lubrication System a. Lubrication shall be by pressure lubricating oil system with engine driven oil pump throughout the whole engine in conjunction with the built-in oil-to-coolant heat exchanger. Multiple full flow filters with renewable elements shall be provided. Automatic shut down of the generating set through low lubricating oil pressure must be incorporated. A failure warning light shall be provided on the control panel to indicate that the generating set has shut down due to low lubricant pressure. Oil pressure gauge shall be incorporated. b. Main, crank pin and camshaft bearings together with the valve gear shall be lubricated by a gear type pressure pump feeding from a wet sump. An audio signal alarm which shall remain on until they are reset manually shall be provided. An oil temperature stabilizer shall be provided. Governor a. The engine shall be fitted with an electronic speed sensing governor to provide steady running at any load within the rated load range. Cyclic irregularity and angular deviation of the engine complete with the direct coupling to the generator shall be equal or better than the requirements as laid down in BS ISO 3046-4:2009. b. The governor shall be of the centrifugal type integral with the fuel injection pump. A speedometer must be provided and automatic shut down of the engine through overspeed must be incorporated. c. A failure warning light and an audio signal alarm shall be provided on the control panel to indicate that the generating set has shut down due to over speed at 110% of rated speed. They shall remain on until they are reset manually. Fuel Service Tank a. A fuel service tank shall be to BS EN12285-2:2005 and of 1000 litres capacity as shown on Specification & Drawings. The tank plate shall be of carbon steel to BS EN 10025-1. 14 - 14 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 b. 14.2.10 14.2.11 Tank shall be of welded construction and welding shall be carried out by the electric arc method. Electrodes shall be hermetically sealed and shall be supplied together with welding schedules indicating the run and type of electrode to be used. Each tank shall be supplied with all necessary fittings and connections including the following: (i) roof manhole and hinged cover; (ii) glass type and/or dial type visual level indicators marked in litres; (iii) earth terminal near base of tank; (iv) drain valve and pipe; (v) copper vent pipe connecting to a goose neck with stainless steel wire gauge covered opening; (vi) isolating valve; (vii) remote leakage indicator; and (viii) high and low level alarm. Engine Heater a. A water jacket heating system shall be provided to maintain the engine jacket water to about 30°C or as recommended by the manufacturer, so as to ensure ease of starting on demand. b. The heater shall be thermostatically controlled and be disconnected whenever the engine is put into operation. Miscellaneous a. Fuel Injection System The fuel injection system shall be complete with primary and secondary fuel filters with replaceable elements, and an engine driven, mechanical, positive displacement fuel pump, all mounted on the engine. 14 - 15 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 b. Lubricating System Enclosed forced feed lubricating system shall be complete with positive displacement, mechanical lubrication oil pump, lubricating oil cooler, filters and dipsticks oil level indicator. c. Air Cleaner Replaceable dry element air cleaner shall include an automatic device to give an alarm when the filter becomes clogged. 14.2.12 14.2.13 Positions of Control and Adjustment Devices a. All operational controls shall be arranged such that they are grouped together in a readily accessible and logical position. b. Setting up devices shall unauthorised adjustment. be separately located to prevent Engine Status Indication The engine shall be provided with the following status indication as a minimum: 14.2.14 a. oil pressure; b. oil temperature; c. engine temperature; d. service hours; e. tachometer; and f. battery charger ammeter. Engine Protection a. The engine shall be provided with the following protective devices and control as a minimum to effect early warning and/or shut down in the event of: (i) low lubricating oil pressure; 14 - 16 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 14.2.15 (ii) high engine coolant temperature; (iii) low coolant level; (iv) engine overspeed; (v) engine overcrank; and (vi) low fuel level. b. The above protection shall be in two (2) stages; it shall give visual and audible warnings at an initial stage and shall shut down the engine when a pre-determined danger level is reached. c. All visual alarms, audible alarms and the associated muting switches shall be wired to the control panel. Voltage Regulation and Adjustment a. b. Voltage Regulation (i) An automatic voltage regulation system shall be provided to maintain the output voltage at the generator's terminal to within +1% of its rated value from no load to full load under steady state condition. (ii) The performance of the voltage regulation system of the generator shall be of Grade VR2.23 as specified in BS 4999140. Voltage Adjustment A means of adjusting the output voltage shall be provided to facilitate adjustment of the machine output voltage at any level within its design parameters. 14 - 17 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 14.2.16 Synchronising Control Panel a. Construction (i) The control panel shall be suitable for floor, wall or engine mounted as indicated, in the form of totally enclosed, selfcontained, flush fronted cubicles containing the equipment detailed. If it is floor mounted, it shall be provided with a 100mm channel base. (ii) It shall be manufactured from sheet steel of minimum thickness of 2.0mm in all folded and welded construction. It shall have provisions for hoisting and be dust and vermin proof. (iii) The control panel shall be arranged for front access wiring. Access of equipment shall be by means of hinged and lockable lift-off access doors fitted with Neoprene seals. Doors shall be provided with lift-off handles. The control panel shall be provided with a removable plate on the top complete with knock out holes, together with all other necessary brass glands and supports to enable incoming and outgoing cables to be installed and terminated. (iv) All surfaces shall be smooth and free from burrs, weld marks and sharp edges. (v) The whole of the control panel metal structure shall be thoroughly cleaned and degreased and the surface prepared for painting by treating with an approved cleaning solution such as Spartan Deren 'A'. The panel shall then be filled and spray painted on all internal and external metal surfaces with at least two coats of approved primer and brought to a fine smooth finish free of all imperfections. Finally apply four thin wet finishing coats avoiding orange peel effect and compound to a high quality finish. The total paint thickness shall be at least 45 microns. (vi) Special care shall be taken to achieve thorough bond between the metal and all coatings. Internal and external surfaces shall be to colours approved by the Engineer prior to commencing manufacture of the control panel. (vii) Where electrical apparatus is attached to lids or doors, means shall be taken to ensure continuity of the protective circuit in the form of an earth continuity conductor of an appropriate size. (viii) Wiring to apparatus and measuring instruments in covers or doors shall be installed such that no mechanical damage can occur as a result of movement of the door or cover. 14 - 18 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 (ix) b. Adjustment devices not required on a regular daily basis shall be so located to permit safe operation and shall be housed in a separate compartment. Generator Set Overcurrent and Earth Fault Protection The generator set shall be provided with overcurrent and earth fault relays complying with BS EN 60255 / IEC 60255 and shall have the following characteristics: Relay Type Make Overcurrent IDMTL Earth Fault DTL, Restricted Earth Fault High impedance instantaneous (voltage operated) The Contractor shall provide and install external shunt resistor for the restricted earth fault protection to achieve the primary fault setting of 10% to 30% full load current. 14 - 19 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 The Contractor shall also provide and install current transformers to achieve the above protection schemes. The CTs shall be rated in accordance with BS EN 60044-1, IEC 60044-1 and as follows: Protection Scheme CT Ratio Class Burden Overcurrent and Earth Fault Protections As shown in the Specification & Drawings 5P10 20VA Restricted Earth Fault As shown in the Specification & Drawings ‘X’ - The knee point voltage of Class X CT shall be selected such that it is three times the final voltage setting of restricted earth fault relay. The Contractor shall submit calculation to justify the suitability of the current transformer for the protection scheme, taking into the consideration of the burden of the protection relay, CT, cable, any accessories and etc. c. Apparatus Equipment and Accessories The control panel shall contain, but not be limited to the following:(i) Four (4) pole circuit breaker with shunt trip facility, adjustable trips for generator overcurrent, earth fault and reverse power relays, controls and indications as specified. The current rating and breaking capacity of the circuit breaker shall be compatible with the generator provided; (ii) voltmeter, flush mounting, hermetically sealed, moving iron, with fuses; (iii) voltmeter standby mains selector switch, phase to phase switching; (iv) ammeter, flush mounting, hermetically sealed, moving iron, with current transformers c/w half-hour maximum demand indicator; (v) ammeter phase selector switch; (vi) frequency meter; (vii) power factor meter; 14 - 20 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 (viii) hours counter; (ix) kWH meter; (xi) restricted earth fault protection relay; (xii) overcurrent IDMTL protection relay; (xiii) current transformers for protection; (xiv) voltage sensing units to detect failure of any phase of the normal mains supply; (xv) duty selector switch (Off/Test/Manual/Automatic); (xvi) engine 'START' and 'STOP' switches; (xvii) set of 'MAINS ON', 'STANDBY ON' and 'MAINS FAILURE' indicator lamps; (xviii) fault reset button; (xix) shutdown relays, indicating lamps and audible alarm bell for:- (xx) engine low oil pressure; high water temperature; engine overspeed; engine overcrank; and low fuel oil level. Solid state time delay circuits for: delay on start, adjustable from zero to 10 seconds; and delay on restoration, adjustable up to 30 minutes. 14 - 21 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 d. (xxi) Automatic battery charger - trickle and boost; (xxii) HRC fuses for control circuits and instruments; and (xxiii) Any other equipment required for the proper operation of the system or indicated in the Specification & Drawings. Wiring and Terminations (i) Wiring for mains voltage shall be PVC insulated to BS 6231, Type B in phase colours with a minimum size of 1.5mm². As an alternative to coloured cables, labeled black cables may be used for Phase connection with colour coded ferrules. (ii) Extra low voltage wiring shall be carried out in flexible PVC insulated cable to BS EN 50525 with a minimum size of 1mm². (iii) The colour coding shall be as follow: Phase connections – Brown, Black and Grey; Neutral connections - blue; Earth connections - green/yellow; and DC Circuits - grey with red and black ferrules to denote polarity. (iv) Wiring shall be carried on the front surface of the mounting plate either neatly strapped in plastic cable trunking of the ventilated type with clip-on covers and purpose made connector pieces and accessories, or strapped in looms with straps permitting easy access to the looms and clipped to the mounting plate. (v) All control wiring shall be identified with numbered ferrules. All wires associated with tripping circuits shall have red ferrules marked "Trip". The numbers shall be shown on the schematic wiring diagram. (vi) Terminals shall be suitably rated, fully fitted and numbered. They shall be normally mounted for top entry and front access. They shall be suitably sized to cater for long runs of externally mounted cable whose voltage drops necessitate a larger size than standard for the connected load. 14 - 22 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 e. f. Operation (i) The Synchronising Control Panel shall be designed for automatic operation on mains failure. (ii) When the mains supply is normal, the load is fed through the mains supply switch of the automatic transfer pair. (iii) The automatic control circuitry shall be arranged to serve a fault or failure of any phase of the mains supply voltage, and on receipt of such a signal the mains supply switch shall deenergise, open and the engine starting circuit shall be initiated. (iv) The mains supply voltage sensing unit shall not only detect a complete mains fault or failure but shall also sense a voltage drop of up to 20% or more in any phase of the normal mains voltage. (v) When the voltage and frequency (engine speed) of the generating set at up to normal values, the standby supply switch (mechanically and electrically interlocked with the mains supply switch) closes, thus providing electricity supply to the essential services. (vi) The duration of the entire starting sequence shall be within ten seconds from the moment of mains failure to standby on load. The Contractor shall state clearly in the Tender the period in seconds that would elapse for the generating set to complete the starting sequence from the moment of mains failure. (vii) When the mains supply returns to normal, the load shall be transferred automatically to the mains supply. The generating set shall shut down after a preset time delay, and the equipment shall reset for the next duty operation. (viii) The starting battery is maintained in a fully charged state when the set is idle by a mains operated battery charger. Beacon Light An orange beacon light shall be provided to indicate that the standby generator is running. It shall be located outside the standby generator room. 14 - 23 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 14.2.17 Generator Set Acoustic Enclosure a. General (i) Acoustically treated weatherproof enclosure to achieve 75dBA measured at 1-meter all round the enclosure (under free field condition) shall be provided for the diesel generator set. The enclosure shall be suitable to be placed in an outdoor environment. (ii) The enclosure shall be pre-assembled as a complete unit and includes the following: Diesel generator set comprising engine, alternator and radiator on a common baseframe 1000 litre day fuel tank, Generator set automatic mains failure panel, Battery bank and automatic charger unit, Sufficient lighting fixtures to provide illumination for maintenance purposes (applicable for big generator set enclosures), The circuit breaker panel and control panel shall be set mounted on the base frame instead of set mounted to minimize the vibration of the cable termination when in operation. (iii) The performance of the enclosure shall be designed and constructed to ensure that the specific acoustic criteria are met without affecting or derating the diesel generator set rating specified. (iv) The design of the enclosure must provide sufficient space for maintenance and operating purposes, maintenance aspects on the generator set shall not be compromised. (v) Lightings with switches shall be provided within the enclosure for 4 hours duration, powered by a dedicated DC supply. (vi) External pipe connections and openings must be provided at the enclosure such as: Lubricating oil drain point, 14 - 24 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 b. c. Engine breather outlet, External fuel pipelines connection – for automatic fuel filling, Cable entry to the generator set termination box. Enclosure Baseframe (i) The generator set acoustic enclosure can be housed as an integral skid mounted and completely portable unit that would only required a single crane to lift the complete generator set without any re-assembly work on-site. (ii) For special applications and site constraint, etc, the generator set may be installed on a concrete base with the acoustic enclosure mounted over the generator set and sealed to the concrete. (iii) The complete generator set baseframe shall be hot-dip galvanized. Enclosure Body (i) The outer skin of the enclosure shall be of stainless steel sheet (316) of not less than 2.5mm thick. (ii) The inner skin of the enclosure, including all doors, shall be lagged with approved type of non-combustible acoustic material. The construction of the acoustic insulation shall comply with the sound level stipulated above. (iii) The enclosure shall come complete with stiffeners to ensure that the external wall, doors and ceiling are all strongly assembled as one unit and will not warp or break during the transportation and hoisting of the enclosure. (iv) The enclosure shall have minimum four lifting points for transportation and hoisting. (v) Catladder with full length handhold to the top of the enclosure roof shall be provided. (vi) Provision shall be made for proper accessibility for maintenance. 14 - 25 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 d. e. f. Enclosure Doors (i) The enclosure shall come with full height doors on each side of the enclosure to give personnel entry. Rain shade shall be provided for each door. The location of the doors shall be designed so as to facilitate the easy access to the genset and its installed components for maintenance staff for the maintenance of the generator set. (ii) Heavy duty hinged doors complete with stainless steel lockable lock-sets shall be provided to each door. Additional latches or panic hinges shall be provided on the inside of the lock-sets to release the door mechanism from the inside of the enclosure to ensure that personnel working within the enclosure will never get locked in when the doors suddenly slam shut. Enclosure Air Flow (i) Fresh air inlet and radiator exhaust outlet for the enclosed generator set must be carefully designed to ensure proper ventilation during the operation of the generator set. The fresh air inlet air flows into the enclosure, besides providing cooling air to the engine radiator unit, also takes care of the heat dissipation for the diesel generator set and it’s associated equipment. (ii) The airflow velocity at the inlet and outlet of the enclosure must not be excessive and shall be below the allowed velocity needed to achieve the acoustic performance specified. (iii) The manufacturer must submit airflow calculation to ensure that the overall airflow pressure / static within the acoustic enclosure from the fresh air inlet position to the radiator hot air outlet position is within the engine radiator fan allowable external static pressure. External fan shall be provided for the acoustic enclosure to ensure proper operation of the generator set if the engine fan is not capable of providing the required airflow and static pressure. However, the nett kW rating of the generator set shall not be affected or reduced, manufacturer should size the fan within the generator set allowable losses. Sound Treatment to the Enclosure (i) Sound attenuation must be provided at the fresh air inlet and radiator exhaust outlet. The method of attenuation shall be approved by the Engineer. Sound attenuation section must be constructed using similar material as that used for the construction of the enclosure and acoustic insulation. 14 - 26 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 (ii) g. h. If acoustic splitters are used for sound attenuation, the splitters shall be aerodynamically shaped, having a bull nose at the inlet and followed by a parallel-sided section of varying length and terminated by an optimised tapered section. Engine Exhaust System (i) Residential exhaust silencer must be installed and connected to the engine through steel flexible and flanged pipe work. For acoustic enclosures requiring higher sound attenuation, an additional / secondary silencer must be installed. (ii) Exhaust pipe and flexible pipe within the enclosure shall be lagged with a heat insulating material and clad externally with aluminum sheet. (iii) Exhaust silencer, exhaust pipes and fittings shall be of stainless steel SS 316 materials. Fuel System (i) Fuel day tank must be constructed as per the tender specification. Fuel tank installed within the enclosure shall be provided with a means of containing any leaks from the tank and prevent any leakage of diesel out of the enclosure into the open. (ii) Fuel pipeline shall be installed within the fuel tank and the engine; flexible fuel pipeline must be used between the engine and the fuel pipeline. (iii) Proper fuel filling point and fuel level gauge must be provided and be easily accessible and visible. External fuel pipe connection points must be provided if external fuel transfer system is required. 14 - 27 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 14.3 Execution 14.3.1 Cabling a. Mains Cables and Connections (i) The Contractor shall provide and install all mains supply cables as shown on the specification and drawings. The cables shall be Fire-Resistant (FR) Cable unless of otherwise specified. All circuits shall be provided with separate continuity conductors sized to comply with SS 638. (ii) The cables shall be properly fixed on perforated metal cable ladder with PVC covered metal saddles or plastic saddles at 450mm intervals. Where the run of cables and ladder is on the ground, it shall be encased in metal trunking. (iii) All terminations, fixings, tools and accessories shall be of the same manufacturer as the cable installed. Terminations shall comply with BS EN 60702-2, IEC 60702-2 with dimensions rationalised to suit cables complying with BS 6207-3. (iv) Terminations of the PVC sheathed cables shall be protected by the correct size of plastic gland shroud. Any exposed metal sheath remaining after the installation of the installation of the cable gland shall be wrapped with PVC tape, as supplied by the cable manufacturer, before fitting the gland shroud. (v) Suitable anti-vibration loops on bends shall be formed in the cables immediately prior to termination in accordance with the cable manufacturer's recommendations. Any loop shall be formed such that the two sections of cable do not touch at the point of crossover. (vi) At all terminations, great care shall be taken to maintain earth continuity. All glands and locknuts shall be effectively fitted and tightened to the manufacturer's recommendations. (vii) The insulation resistance of a terminated cable shall be greater than 100 Megohms when measured with a 500 volts or 1000 volts insulation tester immediately after sealing. This test shall be repeated not less than twenty (24) hours later. 14 - 28 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 b. c. Small Wiring (i) All small wiring shall be PVC insulated and PVC sheathed single core copper cables, rated at 600/1000 volts and complying to BS EN 50525. All conductors shall be at least 2.5sq.mm in cross sectional area. (ii) Cables shall be protected throughout their length by a continuous enclosure of conduit or trunking except where cables are installed within the enclosure of electrical equipment. (iii) All circuits shall be provided with separate earth continuity conductors sized to comply with SS 638. Operation (i) Complete or partial failure of Utility’s electricity supply (including voltage drop in any phase to 80% of Utility’s declared value) at the transformer feeder shall be detected by the sensing relays of the standby generators. Thereupon the 'mains' contacts of the associated automatic transfer switches (ATSs) shall be opened and the engine and the auxiliaries (i.e. radiators fans, etc.) shall be started up after a short time delay. As soon as speed, frequency and voltage of the standby generator reach the operating values, the 'standby' contacts of the ATSs shall be closed and arrangements shall be made to transfer the loads to the standby generators concerned in 3 steps of loads not exceeding approximately 60%, 20% and 20% of the capacity of the standby generators sets. The loads to be designated for each of the steps shall be subject to the Engineer's approval. The costs of providing changeover contactors, time delay relay, motorised ACB/MCCB's, wiring, etc. as required to achieve this load transfer shall be deemed to have been included in the Contract Sum. The transfer of the entire loads shall be effected within 10 seconds after the closing of the ‘standby' contacts of the ATS. Upon restoration of the mains supply, the process shall be reversed i.e. the 'standby' contacts of the ATSs shall be opened to be followed by closure of the 'mains' contacts of the ATSs. (ii) Time delay circuits shall be incorporated in the control circuit of the standby generators set so that changeover to mains after mains supply has been resumed shall only be effected after the engine has run for a minimum period of 15 minutes after start up and 15 minutes after mains resumption to ensure that the engine is not repeatedly started and stopped in the event of a series of supply interruptions. 14 - 29 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 d. e. Automatic Operation (i) On operation of the voltage relay at the upstream of the ‘Normal' breaker of the ATS in the designated LV switchboard during failure of the mains supply, a signal shall initiate the start-up system of the engine. A time delay, adjustable between 0 to 5 seconds, shall be incorporated in the system to prevent automatic starting in the event of momentary voltage interruptions to the mains supply. (ii) If the failure persists at the expiry of the time delay period the prime mover start sequence shall begin. (iii) Within 15 seconds of the start sequence commencing, the generating set shall be established at its running speed and full load transfer shall take place automatically. (iv) Should the prime mover fail to start after a period of 15 seconds, the sequence shall be interrupted for a period of 5 seconds and a further two attempts to start of 5 seconds duration shall then be made. If it again fails to start, the starting sequence shall be locked out, an audible and visual alarm given and it shall remain in this locked out condition until manually reset. (v) Restoration of the mains supply during the starting period shall not interrupt the starting sequence but shall prevent operation of the load transfer. Subsequent failure of the mains supply while the generating set is running shall, after expiration of the 0.5 to 1.0 seconds time delay, cause the load transfer to take place. (vi) On full restoration of normal supply, load transfer and shutting down of the generating set shall be either by manual or automatic operation selectable by a selector switch on the control panel. Upon activation of this command, load transfer shall take place immediately. The generating sets shall run unloaded for a short cool-down period of 0 to 15 minutes adjustable and then shut down. Manual Operation (i) The control panel shall also be equipped with an "Auto/Manual" rotary control switch. The system shall operate as described above in "Auto" selection and shall hold the existing status of the system until manual controls are effected. 14 - 30 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 f. (ii) The generating set shall be able to start manually, by control switches located on the control panel. Once started and running normally, the generator can be manually connected to the desired essential loads. (iii) During the whole of the manual starting sequence, all the loads shall not be transferred to the generator as long as the mains power remains available. However, upon actuation of a "Manual Load Transfer" push button, a signal shall be initiated to open the "Normal" circuit breaker and close the "Standby" circuit breaker to enable load transfer as per in the automatic operation. By re-setting the "Manual Load Transfer" push button, the load shall be transferred back to the mains supply. Synchronising Facilities Manual synchronizing facilities, with synchronizing check features, are required for the circuit breakers controlling the generators, stepup transformers and bus-sections. Automatic synchronishing facilities shall be additionally supplied on the generators. Where the terms “running” and “incoming” are used, the term “incoming” shall apply to the circuit which is to be synchronized with the power system and “running” refers to the power system. The hinged synchronizing panel or trolley located in the power plant control room shall be equipped as follows:1 – ‘Incoming’ voltmeter 1 – ‘Running’ voltmeter 1 – Synchroscope 1 – Auto/manual synchronishing selector switch 1 – 3 position manual synchronishing selector switch with “OFF”, “SYNCH CHECK”, “SYNCH CHECK OVERRIDE” positions 1 – ‘Synch Check in Service’ white lamp 1 – ‘Synch Check Override’ amber lamp 2 – Lamps bright at synchronism 1 – Phase Reversing VT 1 – Automatic synchronishing relay 1 – Synchronising check relay 14 - 31 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 1 – ‘DEAD LINE” undervoltage check relay 1 – ‘DEAD BUS” undervoltage check relay If a hinged panel is used, instruments shall be sufficiently large to permit easy viewing from each section of the power plant control panel. If a trolley is used, it shall have large diameter rubber tyred wheels and shall be complete with a plug and lead with facilities for storage of the trailing cable when it is not in use. Interlocking shall be provided such that the relevant circuit-breaker cannot be closed manually unless the relevant circuit has been selected for synchronishing. Synchronising check relays shall check the phase and magnitude of the voltage difference at synchronising with contacts connected to prevent inadvertent manual synchronishing outside acceptable limits. Synchronising check circuits shall be arranged such that the relevant circuit-breaker will not close if the circuit breaker control switch is put into the “CLOSE” position, when the measured parameters are outside of the prescribed limits, and held in that position. Means shall be provided at the synchronizing panel to override the check circuits when switching dead equipment or lines, together with warning lamp indication that the relays are out of circuit. This facility shall be padlock such that override can only be selected after the padlock has been removed. Deadline, or deadbus, check features shall be included to prevent the use of override facilities for closing a circuit-breaker which would result in the connecting together of live circuits and/or busbars. 14.3.2 Automatic Features The generating set shall be provided with the following automatic protective features complete with indicating lamps: a. Shutdown (i) The generating set shall shutdown under any of the below conditions: if the coolant temperature exceeds a safe figure; if the speed exceeds a safe figure; if the lubricating oil pressure falls below a safe figure; 14 - 32 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 (ii) b. if there is an overload on any or all of the phases; if there is an under or over voltage; and if there is an operation of protective relay. Failure warning lights and audible alarm sounder connections for remote indications shall be incorporated to indicate that the generating set has shutdown due to any of the above mentioned. The generating set main circuit breaker shall be opened under any of the above abnormal conditions and interlocked to prevent the breaker from being close unless the engine is running and all conditions restored to normal. Mains Voltage Monitoring The mains voltage shall be monitored on all three (3) phases, failure or low voltage (below 10% of the rated voltage) on all/or anyone phase will initiate starting of the generating set. c. Starting Delay An adjustable starting delay over 5 seconds shall be provided to prevent the diesel engine starting up unnecessarily during transient voltage fluctuation. d. False Start If the engine fails to start up after three numbers of attempted start, the generating set which is incorporated with an automatic system shall prevent any further starting and at the same time sets up an audible and visual alarm indicating that the plant has failed to start. e. Repeat Starting A triple repetition of the starting process shall be incorporated in the system. f. Taking Over the Load The load shall only transferred to the generating set when the alternator has reached its rated voltage and shall be approximately 10 seconds after starting of engine. 14 - 33 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 g. Alternator Voltage Monitoring The alternator voltage shall be continuously monitored on three phases. If the voltage drops below the 10% value, the alternator breaker or contactor shall be opened and an alternator fault indicated both visually and audibly. Automatic re-energisation of the alternator will be blocked. h. Delayed Main/Resumption An adjustable time delay (0 to 30 minutes) to prevent the set from shutting down in the event of a momentary mains return must be provided in the system. i. Slowing Down After reconnection of the load to the main supply, the unloaded generating set shall continue to run for about 5 minutes before stopping. j. Emergency Shutdown An emergency push button to disconnect the entire standby generating plant, shutdown the generating set and block the automatic system shall be incorporated in the plant. k. Operation Selector Switch A selector switch shall be provided for the following modes of operation:(i) Manual starting/stopping of the engine - intended for commissioning and maintenance of the plant. (ii) Automatic operation (iii) No load test - to test the functionality of the standby generating plant without connection to the load. The test duration shall be terminated automatically by a timer and adjustable over 15 minutes. Any failure or abnormalities that would arise from this test would bring on the alarm. (iv) Load test whereby a failure is simulated and the complete process of load take-over by the standby generating plant is tested. 14 - 34 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 14.3.3 14.3.4 Generator Plant Room a. The Contractor shall install a framed Single Line Diagram of the main circuit, change-over and supply scheme, and control circuit diagram in the generator plant room. b. A first aid chart shall also be provided and displayed. b. The Contractor shall provide a 5mm thick x 750mm wide rubber mat, extending the length of the control panel, placed in front of the control panel. c. A key box cabinet to accommodate keys and generator plant 200 page log book). d. Wall mounted collapsible Table. e. Danger signage on Generator, HV equipment generator plant room doors etc. Painting In addition to painting the control panel as previously specified the Contractor shall paint the standby generator set bed plate in a similar manner as specified for the control panel and shall touch up any paintwork of the diesel engine, alternator, control panel, etc. damaged during site installation. 14.3.5 Acoustic Treatment A suitable sound proofing techniques shall be applied to the generator room such that the noise level of the generator room measured at 1m from the circumference outside the generator room shall not exceed 70 dBA. 14.3.6 Interfacing with Building Management System (BMS)/Power Monitoring and Control (PMCS) a. The BMS, to be provided by others, shall monitor and log the conditions of the standby generating plant as indicated in Table below contained in the Specification. All status and control wirings to be linked to the BMS shall be brought to a marshalling cubicle from which the information will be picked up by the field equipment of the BAS (Building Automation System). All status and control interface shall be provided in the form of dry contacts, and in pairs of N.O. and N.C. contacts. 14 - 35 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 Table : Monitoring of Standby Generating Plant Device/Alarm Interfacing with Control panel The Building Automation System Alarm/Status Alarm/Status Main supply status X X Generator breaker status X X Generator breaker trip on fault X X Generator running X X Engine overcrank lockout X Common alarm Engine overspeed shutdown X Common alarm Engine fail to start X Common alarm Low fuel level X Common alarm Low lubricating oil pressure X Common alarm High coolant temperature X Common alarm Battery system fail X X Battery discharging X Common alarm X denotes individual function/signal required. b. 14.3.7 14.3.8 The marshalling cubicle shall be installed inside the Room and shall be of an approved design. Generator Earthing a. An earthing terminal shall be provided in the Generator Room for the earthing of the standby generating plant. b. The generator frame, generator neutral, fuel service tank, generator switchboard, cable trays/ladders, etc. shall be individually connected to the earth terminal provided in the Generator Room. The size of the protective conductors shall not be less than 3mm x 25 mm copper. Testing a. Test in Works (i) Acceptance tests shall be carried out at the works of manufacturer to establish that the generating set complies with the Specifications and is entirely suitable for its intended purpose. 14 - 36 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 (ii) All tests shall be made in a manner prescribed in the relevant British Standard Specification. For Engine 1. 2. Test measurements of the following: cooling water temperature; lubricating oil temperature and pressure; exhaust gas temperature; fuel and lubricating oil consumption; protection circuits settings (e.g. over-speed trip, lubricating oil pressure trip, cooling water temperature trip); and brake horse power. Functional checks to demonstrate: the ability of all malfunction and protection and warning devices to respond correctly to conditions in which they should operate; the dynamic and steady state characteristics of the governing system; and the ability of the starting system to perform in accordance with the Contract. For Alternator 1. Test measurements of: temperature rise of alternator and exciter windings; coil resistances of alternator and exciter windings; and 14 - 37 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 2. insulation resistance of alternator and exciter windings. Functional checks to demonstrate: withstand flash test for one (1) minute; voltage regulation with automatic voltage regulator and manual control (if fitted); and a load test of sufficient duration for the alternator to reach its final steady operating temperature followed by one (1) hour at 110% load. The load test shall be conducted complying to the Specification. The Contractor shall be responsible for providing the artificial load bank. The manufacturer shall provide a test report embodying the results of all tests carried out, after completion of the tests. The test report shall contain: a description and identification of the equipment tested including fabrication block and production numbers; the name, address and contract or order number of the Contractor ordering the equipment; date, place and time of test; the testing party and the signature of the testing Engineer; the properties tested and the source of the parameters for such properties, that is British Standards; and the results of the test and any deviations from the Specifications. 14 - 38 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 No item of equipment subject to inspection and test shall be despatched from the works of the manufacture until the Engineer has received and approved in writing the results of the tests. Acceptance of test reports and approval of tests by the Engineer of any equipment shall not relieve the Contractor from an obligation to supply the complete equipment in accordance with the Contract Specifications and suitable for the purpose intended. b. Load Tests (i) The generating set shall subject to a step-load of 100% or better with voltage dip not more than 20% in cold start condition. The load shall be a combine of resistive and reactive load bank. (ii) The generating set shall subject to the following steady-stale load tests at the manufacturer's premises. The voltage and frequency responses shall be recorded by a high-speed recordor to the acceptance: Load Duration 25% Full Load 10 mins 50% Full Load 10 mins 75% Full Load 10 mins 100% Full Load 1 Hours 110% Full Load 30 mins During the load test the following items shall be recorded at 15 minutes interval: cooling water temperature; engine oil pressure and temperature; exhaust gas temperature; fuel and lubricating oil consumption; 14 - 39 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 (iii) speed (frequency); voltage; current; load in kW; and measurement harmonic spectrum of output voltage. The generating set shall subject to the following impact load tests. The voltage and frequency responses shall be recorded by a high-speed record to the Engineer's acceptance: 0 to 25% Full Load Step; 0 to 50% Full Load Step; 0 to 60% Full Load Step; 0 to 75% Full Load Step; and 100% to 0% Full Load Step. The voltage and frequency dip/rise and recovery time shall meet the relevant BS standards referred in this specification. 14.3.9 Tests on Site a. The Contractor shall arrange with the Engineer for all tests at least seven (7) working days in advance. He shall supply all necessary instruments, apparatus, consumable stores, fuel, connections, skilled and unskilled labour and services with proper, reasonable and safe facilities required for the tests. Any costs which may be involved in the tests shall be included in the lump sum tender by the Contractor. The Contractor shall satisfy the Engineer that the instruments and equipment to be used for any tests are adequate with regard to accuracy and calibration for the tests to be undertaken. b. A complete written record shall be made by the Contractor of all inspections and tests. These records shall be made at the time of the tests and shall be countersigned by the Engineer as a true record. A copy of each record sheet shall be included with the operation and maintenance manual. 14 - 40 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 c. Inspection or approval of tests and acceptance of test certificates by the Engineer of any equipment, works or installation shall not relieve the Contractor from the obligation to supply the complete equipment and complete work and installations in accordance with the Contract Specifications and suitable for the purpose intended. d. Three (3) copies of certificates of test shall be submitted to the Engineer within fourteen (14) days of completion of tests. e. Certificates of test shall contain or have attached to them the following information: f. 14.3.10 (i) the name of Contract and Contract No. as designated by the Engineer; (ii) a description of equipment, system or installation tested including any fabrication, block or production numbers; (iii) the name and address of the Contractor; (iv) date and time of the test; (v) environmental conditions; (vi) the testing party and the signature of the Contractor's testing Engineer; (vii) the results of the test and any deviations from Specifications and Drawings; and (viii) signature and stamp of the Contractor's Professional Engineer. Any faults or defects revealed by the inspection or testing shall be made good and re-testing shall be made, all at the expense of the Contractor. Load Test a. Test Criteria (i) Steady-state voltage +2.5% variation. (ii) Steady-state frequency +1% variation. 14 - 41 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 b. c. (iii) The diesel engine must operate normally without leakage of fuel, lubricating oil, water and exhaust gas. (iv) The diesel engine must not stall. (v) The data obtained during the test must be consistent with the data obtained from previous tests of the same generator. Test Procedure (i) Connect the test resistor load to generator output. (ii) Start the generator without load and let it run free for an hour for warming up. (iii) Apply 100% load and take readings as tabulated every 20 minutes for 2 hours. (iv) Increase the load to 110% and two (2) further sets of readings one at 10 minutes and the other at 30 minutes later. (v) Apply the dynamic load test by quickly varying the load from 0% to 100% and back to 0% in step of 25% load variation. Take readings for each load condition (vi) Put the generator in full load and then cut load off and then full load again for another three (3) sets of readings. Precautions (i) The test resistor load area must be cordoned off. (ii) One electrician must be standing by to monitor the operation and record measurement data at equal time interval. (iii) Fire extinguisher must be made available before starting the generator. (iv) Warning sign must be displayed at test resistor load. (v) All electronic components must be isolated and all capacitors must be short-circuited before performing the insulation tests. 14 - 42 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 14.3.11 Drawings a. b. 14.3.12 Layout of Plant and Equipment (i) The Contractor shall submit the general layout of the generator set, control panel, fuel tanks, pipe work, exhaust outlets, etc. which is to be consistent with the size of the generator plant room. (ii) Unless otherwise indicated, any plinths and trenches necessary for the installation of the generator shall be provided by the Contractor at his own cost. (iii) Layout, construction and installation drawing will be drawn on A1 sheets and details may be produced on A4 sheets. Working Shop Drawing and Schedules (i) The Contractor shall, before the relevant works proceed, prepare and submit for approval by the Engineer all working drawings based on the Contract Drawings. They shall take into account any modifications, either to the building or the installation which may have taken place, incorporating details of the actual items of plant and equipment to be installed. (ii) The Contractor shall prepare all necessary schedules of equipment and necessary wiring diagrams, including internal diagrams for items of electrical equipment and diagrams showing the inter-connection between different items. (iii) The single-line diagram of the main circuit showing the change over arrangement shall be duly endorsed by the Contractor's Professional Engineer. (iv) The Contractor shall, prior to commencing manufacture, submit to the Engineer for technical appraisal, manufacturer's shop drawings of the duct and pipe work to be supplied and erected under the terms of the Contract. Drawings shall relate the location of ducts and pipes with the supporting and adjacent building structure. Manuals a. Operation and Maintenance Instruction Manuals (i) The Contractor shall provide the Engineer with copies of the Operation and Maintenance Instruction Manual for the generating sets covering the following:14 - 43 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 b. record drawings of the installation; general description of systems; setting up and operating instructions equipment and systems installed; control sequences for systems installed; the scheduled details of all equipment settings and actual values maintained in controlled variables during commissioning; frequency and details of routine maintenance requirements for all plant and equipment, shown on a set of schedules produced for this purpose; and manufacturer's literature, including detailed drawings and electrical circuit details, printed operating and maintenance instructions, for all specific items of equipment and plant supplied under this Contract. for all (ii) The manuals shall be encased in A4 size plastic covered loose leaf ring binders, with hard covers. Drawings larger than A4 shall be folded and accommodated in the binder so that they may be unfolded without being in any way detached from the rings. (iii) Attention is drawn to the fact that the Works will not be accepted as complete and that final payment will not be made for the Works until the manuals have been accepted by the Engineer as being satisfactory. (iv) The Contractor shall provide training to the Engineer and the Board's maintenance staff in the running of the plant and system. The location and function of all items listed on the record schedules and the procedures for starting up, shutting down, isolating sections, etc. shall be comprehensively explained and demonstrated to the Engineer's satisfaction. Fuel Upon completion of works, the Contractor shall provide sufficient diesel fuel to fill up fully the daily service fuel tank and the underground storage tank. The engine shall operate satisfactorily on light diesel fuel oil to BS 2869 Class A2. 14 - 44 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 c. 14.3.13 Spare Parts (i) The Contractor shall provide, on completion, two copies of the Spare Parts Manual for the generating set. Full details of all engine parts and assembly shall be provided in the manuals. (ii) The Contractor shall guarantee that spares will be obtainable locally for a minimum period of over ten (10) years from the date of completion. (iii) The Contractor shall supply the following spares and tools for each generating set installed: one (1) fan belt, one (1) oil filter element with seals and one (1) fuel filter element with seals; and one set of maintenance tools and gauges (as recommended by the generator manufacture) contained - suitable steel box with lids fitted with padlock. Operational Training on Site Training in the operation and maintenance of the standby generator set for Technical personnel from the Employer shall be carried out on site after testing and commissioning. For Tender purposes, the Contractor shall include allowances in his Tender for a one (1) week training period. 14.3.14 Specialist Maintenance During Defect Liability Period a. The Tender shall include for any normal service and maintenance required during the Defect Liability period on all plant and equipment supplied under the Contract. b. In addition, the Contractor shall perform the following test run and maintenance routine monthly within the Defect Liability Period: (i) initiate automatic starting and stopping of the generating set through simulated mains failure and restoration of normal supply; (ii) test run the generating set for a minimum period of half an hour; 14 - 45 2730011A/EL MAIN TENDER REFERENCE NO - SRFT19080138 (iii) before starting, check lubricating oil, level cooling, water level, fuel level, battery electrolyte level, and refill if necessary; (iv) during running, check and record voltage, current, frequency, power factor, hours, counter, lubricating oil temperature and pressure, engine speed and cooling water temperature; (v) check for leakage and loose connections in fuel, lubricating oil and water piping and electrical wiring; (vi) check and record battery voltage and charger current; and (vii) clean battery terminals and check tightness of connection. c. Each of the above test run routine maintenance shall be carried out in the presence of the Employer's representative. d. The Contractor shall supply all necessary lubricating oil, battery water, coolant, grease, etc. for topping up during the fortnightly test run and routine maintenance. e. Should any parts, equipment or material become defective or faulty, the Contractor shall replace and rectify such defects and faults at no cost to the Employer. All efforts shall be made to avoid putting the system out of service in the event of repair. 14 - 46 2730011A/EL