MANAGEMENT ASSOCIATES MONTHLY PROGRESS REPORT REPORT NO. _3__ NAME: _Ali Husnain DESIGNATION: P.NO: PERIOD COVERED 31-12-2021 TO 01-02-2022 04-02-2022___________ TO: Unit Manager - L&D Thru: __________________ Management Associate_ ___25th__ _3009_____ APP. BATCH: DEPT./ SECTION: DATE: _Operations/Ammonia UM / Sec. Head / Dept. Mngr. OBJECTIVE Summary for the Month of January regarding activities performed and jobs observed. ACTIVITIES PERFORMED ➢ ➢ ➢ ➢ ➢ ➢ ➢ ➢ Line tracing of synthesis gas circuit from C-214 to C-211. Line tracing of lean solution, semi lean and rich solution circuit. Line tracing of condensate recovery circuit, low heat recovery steam generation and stripping steam circuits. Line tracing of flash vessel C-2001 and ejector steam circuits. Line tracing of process condensate circuit, vacuum condensate circuit and BFW circuits. Line tracing of DWM circuit, service air, N2, BBD circuits. Line tracing of HS, MS, LS steam circuit. Line tracing of Phosphate, NH3, Hydrazine dosing circuit. JOBS OBSERVED ➢ ➢ ➢ ➢ How to adjust the LTSC I/L temperature. Air injection to C-102 Start-up of KGT-306A Start-up of G/GHT-201B SELF-STUDY AND COURSE ATTENDED ➢ ➢ Study of Area specific course of CO2 removal and methanation Study of API of centrifugal compressor Name:-_________________ Signature: _______________