Request for
Inspection Works
Request
PMPT-INR-18569-01
Construction Site: Posorja Multipurpose Terminal – Terminal Works
Part/Lot No.: FIRE FIGHTING Piping
Section of Specs. : ES-132.003-301-23-001-R04-B
Drawing No.: D-132.003-301-23-001-R09
Description of Inspection requested
(Submitted to the Engineer at least 24 hours before the time of the inspection)
To be held
on / at / with
Date
14-02-2019
Time
8:00-16:00
Location
Name
Near FHP47-1, 20 meters
GAO SHUAI
(Supervisor Name)
We will start backfilling ,we will check the compaction degree in each layer of 200mm~250mm
Activities for according to the project specifications for comments and the approval of CGR.
which the
inspection is
requested
(short description)
Inspection
Forms
Inspection Form(s) No(s): ________ CL-03_______ will be available at time above.
Other
information During backfilling, CGR should be Surveillance. And the contractor will record the compaction
degree.
Submitted by
CHEC
Received by
Name/Date/Signed
APPROVED
Name/Date/Signed
CGR
REJECTED
Name: ___________________________ Signature: __________________ Date:
CGR inspection comments shall be included in the respective Inspection Form.
(For other comments than inspection findings):
1
2
3
4
CL-03
Request for inspection works
PMPT-INR-18569-01
Compaction Degree
FM-177
Source of filling
SAND
Test report
FM-175
Design
elevation(m)
01-06-2019
Degree of
compaction
required
thickness of
the layer (cm)
90%
Number of layer
/
Total length of trench(m)
20 m
Test mode and
test depth(mm)
Method A , ___150____mm
Test method
ASTM D6938
Equipment model
MODEL 5001 EZ
Test serial
number
Sign Resp.Operator:
NA
Distance from
Wet density
VP-02/VP-06
(kg/m3)
Water content
(%)
Sign Resp. Technical CHEC:
Dry density
(kg/m3)
Maximum
density value
(kg/m3)
Sign Resp. Engineer CGR:
200~250
Degree of
Compaction
(%)